You are here:
AustLII >>
Databases >>
New South Wales Civil and Administrative Tribunal - Appeal Panel >>
2016 >>
[2016] NSWCATAP 108
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Context | No Context | Help
Augustus v Mohammed [2016] NSWCATAP 108 (18 May 2016)
Last Updated: 18 May 2016
|
Civil and Administrative Tribunal
New South Wales
|
Case Name:
|
Augustus v Mohammed
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
3 March 2016
|
Date of Orders:
|
18 May 2016
|
Decision Date:
|
18 May 2016
|
Jurisdiction:
|
Appeal Panel
|
Before:
|
P Callaghan SC, Principal Member S Thode, Senior Member
|
Decision:
|
(1) The time for instituting this appeal is extended to 6 November
2015. (2) Subject to order 4, the Appeal and the Application for Leave to
Appeal are dismissed. (3) The order appealed from is affirmed. (4) The
subject proceedings are remitted to the Consumer and Commercial Division of this
Tribunal (as previously constituted, if practicable)
for consideration (on the
evidence tendered at the hearing on 17 August 2015) of any order that may be
appropriate to be made in
respect of the first respondent in the subject
proceedings, Ausko Building & Construction Pty Ltd. (5) The Registrar is
to arrange for a copy of this decision to be forwarded to Ausko Building &
Construction Pty Ltd at its registered
office promptly after publication of this
decision with a covering letter drawing attention particularly to Order 4
above. (6) If the Respondents wish to make an application for their costs of
this appeal, they are to do so by filing, and serving on the
Appellants, written
submissions within 14 days after the publication of this decision and the
Appellants may file, and serve on the
Respondents, submissions in reply within
14 days after service on them of the Respondents’ submissions. Any such
application
will then be decided on the papers. (7) The application for a
stay (and other order) is dismissed.
|
Catchwords:
|
APPEAL – NCAT internal appeal – appeal dismissed –
application for leave to appeal dismissed – extension of
time for
institution of appeal – identification of questions of law – issue
not raised at hearing PROCEDURAL FAIRNESS – case management
– bias HOME BUILDING ACT – s3A –
s48MA LEAVE TO APPEAL – fairness – new evidence –
weight of evidence EVIDENCE – expert evidence – costs
of expert’s report PROCEDURE – no order made in
appealed decision in respect of one respondent – stay - costs
|
Legislation Cited:
|
|
Cases Cited:
|
|
Texts Cited:
|
Nil
|
Category:
|
Principal judgment
|
Parties:
|
Appellants: Viji Augustus, Sylvia Shanthi Augustus, Roshan Iyadurai,
Rebecca Roshan, Stanley James and Aravinda Stanley Respondents:
Abdul Kaheel Mohammed and Shahim Mothi Sheikh
|
Representation:
|
Appellants: in person through Stanley James Respondents: J.
Antoun, Solicitor, of Uther Webster & Evans
|
File Number(s):
|
AP 15/60640
|
Decision under appeal:
|
|
Court or Tribunal:
|
Civil and Administrative Tribunal
|
Jurisdiction:
|
Consumer and Commercial Division
|
Date of Decision:
|
22 September 2015
|
Before:
|
J.A. Ringrose, General Member
|
File Number(s):
|
HB 14/61603
|
REASONS FOR DECISION
Background
- On
13 October 2012 the respondents to this appeal (principally referred to herein
as “the purchasers”) entered into a
contract with the appellants to
purchase a townhouse type dwelling (“the property”) which was to be
built at Girraween
as one of four such adjacent properties to be developed by
the appellants, using Ausko Building and Construction Pty Ltd (“the
builder”) as builder. The contract price for the property (with upgrades)
was $521,000.00. The purchase was settled on 17 February
2014.
- The
purchasers notified a building dispute in respect of the subject property to
Fair Trading NSW in July 2014. After investigations
by that Office and some
rectification work on the property, the purchasers on 29 December 2014
instituted proceedings against the
builder and the appellants in the Consumer
and Commercial Division of this Tribunal against the builder as first respondent
and the
appellants in pairs as the second, third and fourth respondents seeking
a work order, at a claimed total cost of $71,282.74 (“the
subject
proceedings”).
Subject Proceedings-Interlocutory
- There
was a first directions hearing in the subject proceedings on 10 February 2015 at
which all parties appeared with Ms Sheikh representing
the purchasers, Mr
Michael Lee, a director of the builder representing the builder, and Messrs
Augustus and James representing the
appellants. A short adjournment was given to
the parties so that they could discuss rectification work to the property.
Directions
were then made and later confirmed in writing to the parties in the
following terms:
- (a) By
determination of member, on 10 February 2015 the hearing was adjourned to a date
to be fixed by the Registrar.
- (b) Shahin
Mothi Sheikh and Abdul Khaleel Mohammed shall send to Viji Augustus and Sylvia
Shanthi Augustus and Roshan Paul Ravikumar
Iyadurai and Rebecca Vinodhini Roshan
and Ausko Building & Construction Pty Limited, a copy of all documents
including expert
reports, scott schedule, quotes attached to the application
filed with the Tribunal on 7 January 2012.
- (c) Viji
Augustus and Sylvia Shanthi Augustus and Roshan Paul Ravikumar Iyadurai and
Rebecca Vinodhini Roshan and Ausko Building &
Construction Pty Limited shall
send to Viji Augustus and Sylvia Shanthi Augustus and Roshan Paul Ravikumar
Iyadurai and Rebecca Vinodhini
Roshan and Ausko Building & Construction Pty
Limited, the Tribunal and any other respondents, a copy of all documents
including
expert reports, witness statements, scott schedule, on which the
respondent intends to reply at the hearing by 13 March 2015.
- (d) The
parties’ experts shall consult each other with a view to narrowing points
of difference between them and identifying
remaining points of difference and
shall file with the Tribunal a copy, and provide a copy to the other party
setting out all agreed
points and all remaining points of difference on or
before 27 March 2015.
- (e) Shahin
Mothi Sheikh and Abdul Khaleel Mohammed shall allow Viji Augustus and Sylvia
Shanthi Augustus and Roshan Paul Ravikumar
Iyadurai and Rebecca Vinodhini Roshan
and Ausko Building & Construction Pty Limited reasonable access to the
premises for the
purpose only of carrying out an inspection of the alleged
defective or incomplete work. On such occasion, Viji Augustus and Sylvia
Shanthi
Augustus and Roshan Paul Ravikumar Iyadurai and Rebecca Vinodhini Roshan and
Ausko Building & Construction Pty Limited
(or their representative), may be
accompanied by a building consultant or other expert witness.
- (f) Parties are
to provide documents in a folder, secured by means of rings or other binding
device, typed (except for copies of original
handwritten documents), with
numbered pages and an index.
- During
the directions hearing the Member recommended that there be a meeting of
experts. Ms Sheikh requested a copy of the contract
between the builder and the
appellants.
- A
second directions hearing took place on 7 April 2015. There was no appearance on
behalf of the builder but the purchasers appeared
themselves and Messrs Augustus
and Iyadurai attended to represent the appellants. The Tribunal was informed
that rectification work
on the property was to be done by 18 June 2015 and the
proceedings were stood over for further directions on 30 June 2015.
- On
30 June 2015, again there was no appearance on behalf of the builder and the
other parties appeared, the purchasers themselves
and Messrs Augustus and
Iyadurai on behalf of the appellants. Ms Sheikh said rectification work was
still being done and Mr Augustus
said there were some copyright problems in
relation to release of approved construction drawings which the purchasers
wanted. The
Member expressed concern about non-compliance with the
Tribunal’s previous directions. The Member said: “I’m going
to
set the matter down for hearing because this cannot go on drifting along like
this.” Ms Sheikh advised that no work had
commenced until 14 or 15 June
2015 and Mr Augustus spoke of completion within four weeks thence as a maximum.
The Member granted
an adjournment for four weeks for work to be completed and
said “Because if it’s not finished the matter will be set
down for a
priority hearing.” Directions were made as follows:
- (i) By
Determination of member, on 30 June 2015 the hearing was adjourned to a date to
be fixed by the Registrar.
- (ii) On or
before 7 July 2015 the respondents, Roshan Paul Ravikumar Iyadurai and Rebecca
Vinodhini Roshan and Viji Augustus and Sylvia
Shanthi Augustus and Stanley
Pandian James and Aravinda Stanley are to deliver to the applicants a copy of
the approved plans for
the building of the dwelling.
- (iii) On or
before 21 July 2015 the applicants are to file and serve points of claim in
respect of the remaining rectification works
not completed by the respondents
Roshan Paul Ravikumar Iyadurai and Rebecca Vinodhini Roshan and Viji Augustus
and Sylvia Shanthi
Augustus and Stanley Pandian James and Aravinda Stanley or
not agreed to be carried out by the respondents Roshan Paul Ravikumar
Iyadurai
and Rebecca Vinodhini Roshan and Viji Augustus and Sylvia Shanthi Augustus and
Stanley Pandian James and Aravinda Stanley.
- (iv) On or
before 4 August 2015 the respondents are to file and serve points of defence to
the applicants’ revised points of
claim.
- (v) On or
before 21 July 2015 the applicants are to file and serve an amended Scott
Schedule in respect of the remaining rectification
works not completed by the
respondent or not agreed to be carried out by the respondent (“Revised
Scott Schedule”).
- (vi) On or
before 4 August 2015 the respondents are to file and serve a response to the
Revised Scott Schedule.
- (vii) On or
before 21 July 2015 the applicants are to file and serve all witnesses
statements, expert reports and other documents
upon which the applicant intends
to rely.
Note: Any documents must be provided in a folder(s) marked Main Bundle (rather
than attached to statements or reports) which shall
have an index and each page
shall be numbered consecutively. Documents should be organised in sale order,
earliest to latest.
All documents referred to by any witness shall be included in the bundle and
identified in the witness statement or expert report
by bundle page number. No
duplicate documents.
Failure to comply with these requirements for the preparation of the bundle may
result in the Tribunal making orders preventing a
party from relying on any
evidence not provided in accordance with these requirements.
(viii) On or before 28 July 2015 the respondents are to file and serve all
witnesses statements, expert reports and other documents
upon which the
respondent intends to rely.
Note: Any additional documents (not already in the Main Bundle provided by the
applicant) will be provided by the respondents in
a folder(s) marked
Supplementary Bundle (rather than attached to statements or reports) which shall
have an index and each page shall
be numbered consecutively. Documents should be
organised in date order, earliest to latest.
All documents referred to by any witness shall be included in the Supplementary
Bundle (unless already in the main Bundle) and identified
in the witness
statement or expert report by bundle page number. No duplicate documents should
be in the bundle.
If there is more than one respondent, the respondents must meet and prepare a
joint Supplementary Bundle with no duplicate documents.
Failure to comply with these requirements for the preparation of the bundle may
result in the Tribunal making orders preventing a
party from relying on any
evidence not provided in accordance with these requirements.
General Note: Subject to these directions, the parties must comply with the
Chairperson’s Direction in relation to the provision
of expert evidence,
including in relation to the Expert Code of Conduct, detail of which can be
found on the Tribunal website.
(ix) The Tribunal notes that the applicants have filed with their application a
bundle of documents on which they rely as having
complied with the directions
made by this Tribunal made on 10 February 2015. If the applicants rely on any of
those documents they
must be prepared in accordance with the directions made 10
February 2015 and these directions.
(x) The Tribunal notes that the respondent, Ausko Building & Construction
Pty Limited, did not appear before the Tribunal on
7 April 2015 or 30 June 2015.
If Ausko Building & Construction Pty Limited does not comply with the
directions of this Tribunal
or appear it will not have an opportunity to be
heard in defence of the claim and may have orders made against it in its
absence.
(xi) If a party requires an extension of time to comply with these directions,
an application should be made in writing to the Registrar
no later than the day
prior to the date of submissions of documents to the Tribunal.
(xii) A failure by a party to provide documents in accordance with the Tribunal
orders may result in the party not being able to
rely on the documents at the
hearing, unless leave is granted to do so.
(xiii) All evidence from a party’s witness(es) in support of that
party(ies) must be in the form of a statement, statutory
declaration, affidavit
or expert report as appropriate.
(xiv) Direction 3 of the Tribunal made on 10 February 2015 is vacated and in its
place make Direction 8 of these Directions.
(xv) In any of the orders made today, the applicants are to serve both Ausko
Building & Construction Pty Limited and Roshan Paul
Ravikumar Iyadurai and
Rebecca Vinodhini Roshan and Viji Augustus and Sylvia Shanti Augustus and
Stanley Pandian James and Aravinda
Stanley.
(xvi) The Tribunal directs the Registrar to serve notices on the respondent
Ausko Building & Construction Pty Limited at its
registered office, xxxx,
Pendle Hill NSW 2145 and not at its Post Office Box Number.
The
notices to the parties of these directions concluded with advice that a separate
written notice of the new hearing date will be
sent to them in the near
future.
- A
notice listing the hearing of the proceedings for 17 August 2015, dated 2 July
2015, was forwarded by the Registry to all the parties.
The substantive parts of
the notice were in the following terms:
The application has been listed before the Tribunal and you are required to
appear at:
Location: NSW Civil and Administrative
Tribunal
Government Office
Building
Ground Floor, 2-6 Station
Street
cnr Belmore & Station Streets
PENRITH NSW 2750
Date and Time: Monday 17th August 2015 at 9.15 AM (AEST)
Please arrive at least 15 minutes before the start of the hearing.
It is important that you are on time as the Tribunal may decide the matter in
your absence.
The decision made will be binding on you.
- On
17 July 2015 by email to the Tribunal the purchasers sought an extension of time
for lodgement of their material by 2 days, from
21 July 2015 to 23 July 2015.
Their stated reason was to the effect that the expert’s report needed to
be amended to take account
of some repair work which had been carried out.
- By
a faxed letter dated 27 July 2015 the appellants requested an extension of time
to 25 August 2015 to comply with the direction
that their material for the
hearing be filed and served by 28 July 2015. Their stated grounds for the
application were that the purchasers’
material had not been received until
24 July 2015 and that the purchasers’ claims in the subject proceedings
were “undermining
a prior ‘good faith’ agreement between the
parties to finalise the matter.” That application was promptly opposed
by
the purchasers in writing with complaints by them that, among other things, the
builder’s licence had expired on 21 July
2015, progress by the appellants
in relation to rectification work had been negligible and the appellants were
not honouring their
commitments to complete it. The Tribunal refused the
appellants’ request. A letter dated 4 August 2015 to the respondents
notified
them of that refusal and concluded as follows:
You should comply with procedural directions as soon as possible. Issues of
non-compliance with procedural directions may be raised
with the Tribunal at the
hearing.
The hearing date is confirmed.
Subject
Proceedings-Hearing
- The
hearing on 17 August 2015 took place (as had the directions hearings) at
Penrith. Appearing were both purchasers, Mr Lee on behalf
of the builder and
Messrs Augustus and Iyadurai on behalf of the appellants. In the early stages of
the hearing, among other things:
- (a) Mr Lee
confirmed that the builder’s licence had been suspended and that the
builder had not put on any evidence;
- (b) The
appellants confirmed that they had not put on any evidence and had lodged only a
letter advising that they had provided some
plans and documents to the
purchasers and, three days before hearing, a response (which they had prepared
themselves) to the Scott
Schedule;
- (c) The Member
noted that the hearing had been set down for four hours.
- (d) The Member
canvassed with those present the interlocutory history of the proceedings.
- (e) The Member
ultimately (at page 14 of a 60 page transcript) said “so it’s my
intention in the absence of anything further,
to proceed to a hearing on the
evidence that has been provided by owners because that is the only evidence
that’s been provided
in a proper form and according to the
timetable.”
- Ms
Sheikh gave evidence, answering questions from the Member. She was questioned by
Mr Augustus on behalf of the appellants. The purchasers’
expert gave
evidence in response to questions from the Member and with reference to his
report and Scott Schedule. He was questioned
by Mr Iyadurai.
- The
Member then engaged in discussions with Messrs Augustus and Iyadurai. He
admitted into evidence communications to the Tribunal
from them including their
response to the Scott Schedule and a plan which had apparently been used for the
development application
concerning the property. That discussion continued over
several pages of transcript and towards its conclusion the Member addressed
these remarks to them:
“The problem is now, one, the hearing is today – and I’ll let
you speak after I’ve finished: I just want
to explain this to you. One,
you have no expert report and the hearing is today. Two, there is no agreement
that can be reached to
sort of offset a claim for faulty building works unless
that agreement is reached and usually reached for consideration. In other
words,
someone says, ‘well, okay, well, if we pay you so much, will you forego
these defects and only on those.’
Three, the obligation on a developer is – well, it’s an obligation
on a developer. A purchaser from a developer has the
same rights against the
developer as an owner would have against a builder under the Home Building Act
and, as I say, if it was your house and your builder and you had a list of
claims, you would have a right to pursue all of those
claims against the builder
and, because of the Act, the purchaser from you has those rights. Now,
it’s not an answer to this
claim now to say ‘We want to fix it.
We’re going to fix it’, because the first problem you’ve got
is the
builder is now not licensed. So the Tribunal cannot make any order that
the builder fix it.
You as developers are not licensed to carry out building work so the Tribunal
cannot make any order that you do the work because,
again, that’s illegal
for the Tribunal to make such an order. So the only order available now where
the builder is unlicensed
and the developers are unlicensed and where parties
haven’t reached agreement is for me to make an order about how much you
have to pay for these works to be done, and the difficulty I have – well,
not the difficulty I have, the difficulty for you,
I guess, is that there is no
Scott Schedule prepared by an expert. There is no alternate costing and there is
no basis upon which,
apart from if there was some obvious thing that came out of
questions you asked, I can say ‘Well, I should disallow this or
disallow
that.’
So I just want to say those things to you so that I’ll now give you a
chance to say whatever it is you want to say to me about
the whole thing, but I
just wanted you to get it into perspective. So now is your chance to say
anything more you want to say.’”
- Ms
Sheikh spoke to the Member concerning the fees paid to the purchasers’
expert and the Member involved Mr Iyadurai in that
discussion. The Member also
made some comments to him to the effect that he had heard nothing from the
appellants concerning apportionment
between the appellants and the builder and
he concluded those comments by saying:
“...I’m not being asked to apportion it between you. I’ve got
no evidence on which I can apportion it, but that
might be something between you
and the builder you’ll have to work out later. All
right?”
- The
Member then posed these questions which brought no response from any of those
present:
“All right. Nothing more from anybody? All done?
Finished?”
The Member’s decision was thereupon
reserved.
Appealed Decision
- A
reserved decision was published, with reasons, on 22 September 2015 (“the
appealed decision”). The appellants were ordered
to pay to the purchasers
within one month $55,951.40 for rectification costs plus goods and services tax
and $7,480.00 for expert
report costs. No order was made against, or concerning,
the builder.
Appeal
- A
Notice of Appeal was filed by the appellant on 6 November 2015. It sought in
place of the orders in the Appealed Decision orders
that the subject proceedings
be dismissed and that the “Respondents to complete the rectification of
works agreed between the
applicant and respondent according to section 48MA of
the Home Building Act.” It also sought leave to appeal and an extension of
the time for instituting the appeal.
- The
Notice of Appeal specified the grounds of appeal thus:
Significant procedural errors
1. We were not given an opportunity to request for hearing adjournment so that
we can present all our evidence in our defence in
a more formal manner.
2. We were not given an opportunity to complete the works in spite of having an
agreement on which the works were progressing and
one of the respondents having
a building licence. We also note that Section 48MA of Home Building Act states
that “Rectification of defective work is preferred outcome in proceedings
– a court of tribunal determining a
building claim involving an allegation
of defective residential building work or specialist work by a party to the
proceedings (the
responsible party) is to have regard to the principle that
rectification of the defective work by the responsible party is the preferred
outcome. In this case the respondent was willing to and agreed with the
applicant to complete the rectification work. The original
Decision maker did
not consider this section of HBA in coming to this decision.
New Evidence
Significant new evidence such as Building Expert report and witness statements
as to applicant’s refusal to provide access
to the property to complete
the rectification works was not available at the time of the original hearing.
The respondent’s
request for extension of time to provide the expert
report was refused by the Tribunal.
Decision was not fair and equitable
1. The applicant and the respondents (Stanley and Viji) reached a verbal
agreement in early April subsequent to the hearing at the
Applicant’s
residence to complete the 20 items of work as a settlement to the claim made by
the applicant. Email correspondence
between the respondent and applicant in
support of the verbal agreement was provided which was not accepted by the
decision maker.
Further to this the applicant herself had accepted in the
earlier hearing that the works were in progress and that she wanted them
to be
completed prior to her festival. This can be verified by the Tribunal’s
records of the audio hearing of the hearing.
2. We were not given a fair go, as the member failed to explain the format of
the proceeding and the member used our inexperience
to intimidate us thereby
preventing us from presenting our arguments coherently and objectively without
fear.
3. The order has been made on an expert report that has not based its assessment
of defects on established scientific methodologies
but rather based on
applicants statements and the experts own biases. For example the report states
that there is inadequate slope
in the toilet floor but fails to demonstrate how
this was determined.
4. Michael/the builder (Ausko Building Constructions Pty Ltd) being one of the
respondents was not included in the final Tribunal
order which is incorrect.
Importantly, no reason has been given for omitting Ausko Building Constructions
Pty Ltd from the order.
- The
Notice of Appeal specified that in respect of the application for leave to
appeal, that the decision was not fair and equitable,
that the appealed decision
was against the weight of evidence and that significant new evidence was now
available that was not reasonably
available at the time of the hearing.
- In
support of the allegation that the decision was not fair and equitable this
statement was attached to the Notice of Appeal:
1. We were not given an opportunity to request for hearing adjournment so that
we can present all our evidences in our defence in
a more formal manner. Our
request for extension of time was not granted (Ref 1). Our letter of request was
sent to the applicants
for consideration. However, the applicants’
response was never communicated to us. The respondents building expert report
and
the witness reports providing evidence of access refusal were not present
when the original decision maker made this decision. We
believe that Tribunal
decision is wrong and unfair because the crucial evidence was missing when the
decision was made. The new expert
report and witness reports as to
applicant’s refusal to provide access to complete the rectification works
will shed more light
on the matter and will help the decision maker to make a
fair and evidence-based decision.
2. The respondents from the beginning are willing to complete the agreed items
of works in a professional manner. An agreement was
reached between the
applicants and the respondents to complete 20 items as a settlement towards the
claims. Subsequently these works
were carried out except for one item for which
the tradesperson was denied access by the applicant. The intent of the
respondents
was to complete all agreed work to the satisfaction of the
applicant. The intent of the respondents was to complete all agreed works
in
accordance with relevant standards and codes. The intent of the respondents was
to complete the works in accordance with the agreement
and were completing the
agreed works. In this regard it should be noted that one of the respondents has
a building licence.
The original decision maker did not consider section 48MA of Home Building Act
which says ‘Rectification of defective work is preferred outcome in
proceedings - A court or tribunal determining a building
claim involving an
allegation of defective residential building work or specialist work by a party
to the proceedings (the responsible
party) is to have regard to the principle
that rectification of the defective work by the responsible party is the
preferred outcome.’
In this case the respondent was willing to and agreed
with applicant to complete the rectification works. The original Decision maker
did not consider this section of HBA in coming to this decision.
3. The applicant and the respondents (Stanley and Viji) reached a verbal
agreement in early April subsequent to the hearing at the
Applicant’s
residence to complete the 20 items of work as a settlement to the claim made by
the applicant. Email correspondence
between the respondent and applicant in
support of the verbal agreement was provided which was not accepted by the
decision maker.
Further to this the applicant herself had accepted in the
earlier hearing that the works were in progress and that she wanted them
to be
completed prior to her festival. This can be verified by the Tribunal’s
records of the audio hearing of the hearing.
In this regard the tribunal member
directed the applicant to allow access to her property during normal working
hours (check the
recording of April hearing). In spite of this direction, the
tradespersons were not given adequate access during normal working hours
(statutory declaration to this effect will be provided in accordance with
tribunal procedural requirements).
4. We were not given a fair go, as the member failed to explain the format of
the proceeding and the member used our inexperience
to intimidate us thereby
preventing us from presenting our arguments coherently and objectively without
fear.
5. The respondents were not given prior notice of the opportunity available to
cross-examine the applicant and the applicant’s
expert witness.
Additionally the respondents were not given an opportunity to bring the required
witnesses from their side.
6. Michael/the builder (Ausko Building Constructions) being one of the
respondents was not included in the final Tribunal order which
is incorrect.
Importantly no reason is given or omitting Ausko Building Constructions Pty Ltd
from the order.
- As
to the allegation that significant new evidence was then available that was not
reasonably available at the time of the hearing,
the Notice of Appeal
stated:
The Tribunal should have considered an extension of time to allow reasonable
amount of time to prepare themselves and provide for
an expert report. Further,
the Tribunal never considered the agreement between the applicants and
respondents to complete 20 items
as a settlement to the applicant’s
claims.
- The
statement attached to the Notice of Appeal added in respect of this
allegation:
We acted in good faith and were in the process of completing the agreed works as
settlement for the claims made by the applicant.
Moreover there was an implicit
understanding between the applicant and the respondents to focus on having the
works completed rather
than expending on expert reports. In this regard the
tribunal members at previous hearings indicated that the reports submitted to
date by the applicant were not expert reports. The applicant acknowledged this
and stated that progress has been made on agreed works
(refer to recording of
tribunal hearing). Furthermore, as there was no intent by both parties to
involve third parties in these negotiations
and agreement, and significant
progress has been made on the agreed works, we did not envisage a scenario where
the applicant and
the expert would take advantage of the tribunals June
determination by submitting a report and Scotts Schedule with an expanded
original
works list. In this regard we also note that the applicant’s
expert report is not based on established scientific methodologies
for assessing
defects but rather based on applicants statements and the experts own
biases.
Since we did not expect a defects list of this nature, we sought an extension of
time and a postponement of the hearing to submit
our expert report, which was
denied with no reasons as stated earlier. In this regard it should be noted that
all experts contacted
indicated that to provide an expert report covering all
the items claimed in the applicant’s report would take at least 3 weeks,
whereas we only had a week from the receipt of the applicants expert report.
Thus in response to the applicant’s report and Scotts Schedule, the
respondents provided a response against each listed item
in the report. Our
responses reflected our agreement, works that have been completed, our
professional judgment, the current functionality
and performance of the item
considered as defective and our past experience. We note that the determining
member did not give due
regard to our responses as they were not in the
requested format and were not prepared by an
‘expert’.
- The
Notice of Appeal identified the new evidence that the appellants now seek to
produce to the Tribunal as:
An expert building report;
Witness statements as to applicant’s refusal to provide access;
Bring the witnesses to the Tribunal.
- It
gave this explanation of why this evidence was not available at the time of the
hearing:
Respondent did not file the expert report when it was due because at the time as
the respondent was engaged in settlement negotiations
with the applicants and
also were carrying the works that were agreed to in the settlement negotiations.
The applicants themselves
have state that they are very happy with progress of
works in the April Tribunal hearing and they wanted the respondents to complete
20 remaining items before Eid festival.
The applicants confirmed on several instances they intend to withdraw the case
at the hearing. As the respondents anticipated the
applicant’s withdrawal
of application based on the rectification works being carried out, the
respondent did not think it was
necessary to obtain expert report at the
time.
However the applicant did not withdraw the proceedings contrary to the
applicant’s agreement with the respondent. Whilst the
respondent attempted
to get an extension to file the evidence, leave was not granted by tribunal.
Therefore Tribunal did not consider
evidence of significant relevance in coming
to this decision.
- The
appellants indicated in the Notice of Appeal that in respect of their
application for an extension of time, in addition to the
material detailed
above, they relied on this situation:
Legal advice was sought for with respect of appeal. The advice was received
later than 28 days after the limitation day lapsed.
Appeal
Hearing
- At
the appeal hearing Messrs Augustus, Iyadurai and James were in attendance and Mr
James acted as the spokesman for them and the
other appellants. Mr J. Antoun,
Solicitor, appeared for the respondents and the respondent, Ms Sheikh, was in
attendance with him.
Prior to the hearing each party had lodged written
submissions and other material with the Tribunal. The respondents’ written
submissions which Mr Antoun had prepared were extensive and had been served on
the appellants only a few days before the hearing
of the appeal; we permitted
the respondents to file and serve a response to the respondents’
submissions and they did so on
or about 15 March 2016. Included in the material
with the parties’ submissions were transcripts of the directions hearings
and the final hearing in the subject proceedings. The appellants also lodged a
form of Application for stay of original decision
pending appeal bearing date 7
February 2016 but, apparently, this was received at the Tribunal’s Penrith
registry only on 11
March 2016 and was referred to the Appeal Panel after the
hearing of the appeal; that application sought orders in the following
terms:
We are seeking stay for the payment of $55,951.40 and $7,480.00 that was made by
NCAT dated 22 September 2015. In addition to this
we also seek from the
respondents Abdul Kaheel Mohammed and Shahim Mothi Shekih against carrying out
any work for which the above
monetary amount of $55,941.40 was made in the
decision dated 22 September 2015.
The following details were
given for reasons for the stay application:
We have lodged an appeal no; AP15/60640 against NCAT decision dated 22 September
2015. Please note that the appeal is in progress.
If above requested stays are
not granted, the appeals lodged by us will be useless as the orders are in force
before the appeal is
finished; through their solicitors, the respondents
objected to that application by the appellants being dealt with on the papers
and made submissions by way of letter, endorsed as having been copied to the
appellants, in opposition to the application.
Issues and
Consideration
Extension of Time for Appeal
- The
Civil and Administrative Rules 2014 relevantly provide in r 25 that an
internal appeal such as this must be lodged within 28 days from the date the
appellant was notified
of the decision. Section 41 of the NCAT Act permits the
Tribunal to extend that time and the appellants have sought such an extension.
The appellants were approximately fourteen days late in instituting this appeal.
They rely on their having obtained legal assistance
in respect of the appeal,
which assistance was, they say, later than the lapse of the 28 day period. The
purchasers oppose the granting
of such an extension.
- In
Jackson v NSW Land and Housing Corporation [2014] NSWCATAP 22 an Appeal
Panel at [22] reviewed a number of cases and said (among other
things):
Generally, in an application for an extension of time to appeal the Appeal Panel
will be required to consider:
a. The length of the delay;
b. The reason for the delay;
c. The appellant’s prospect of success, that is whether
the applicant has a fairly arguable case; and
d. The extent of any prejudice by the respondent (to the
appeal).
- Here,
the length of the delay is significant but not extreme. The appellants’
explanation relates to late legal advice but it
suffers from a lack of detail.
As circumstances have transpired, we are not dealing with the application on an
interlocutory basis
as we have heard the appeal, and any separate assessment of
the appellants’ prospects of success is not really appropriate.
As to
prejudice to the respondents, we have been informed through the appeal hearing
that the respondents have obtained a Local Court
judgment in respect of the
order in the appealed decision and may have recovered by way of garnishee order
some of the subject sum.
Weighing up all these circumstances we have concluded
that it is appropriate to extend the time for the
appeal.
Questions of Law and Other Grounds
- Section
80(2) of the Civil and Administrative Tribunal Act 2013 (“the NCAT
Act”) relevantly provides that an appeal may be made to an Appeal Panel
against a decision such as the appealed
decision as of right on any question of
law, or with leave of the Appeal Panel on any other grounds.
- As
was pointed out in Ferella v Chief Commissioner of State Revenue [2014]
NSWCA 378 at [22] it is “necessary for the notice of appeal to identify
precisely the particular questions of law.” Here, the Notice of
Appeal
does not clearly distinguish in the formulation of the matters relied on between
asserted questions of law and other grounds
and presents those matters in a
somewhat discursive and repetitive style. We appreciate, however, the guidance
given in Prendergast v Western Murray Irrigation Ltd [2014] NSWCATAP
69:
In circumstances where the appellants are not legally represented, it is
apposite for the Tribunal to approach the issue by looking
at the grounds of
appeal generally. It is necessary for the Appeal Panel to determine whether a
question of law has in fact been
raised, subject to any procedural fairness
considerations that might arise to the respondent.
- We
also add the helpful, but not exhaustive, list of potential questions of law
given in the Prendergast decision at [12].
- (1) Whether
there has been a failure to provide proper reasons.
- (2) Whether the
Tribunal identified the wrong issue or asked the wrong question.
- (3) Whether a
wrong principle of law had been applied.
- (4) Whether
there was a failure to afford procedural fairness.
- (5) Whether the
Tribunal failed to take into account procedural fairness.
- (6) Whether the
Tribunal took into account an irrelevant consideration.
- (7) Whether
there was no evidence to support a finding of fact.
- (8) Whether the
decision was so unreasonable that no reasonable decision-maker would make
it.
- Clause
12(1) of Schedule 4 of the NCAT Act provides that an application for leave to
appeal from a decision of the Consumer and Commercial
Division of this Tribunal
may be granted:
...only if the Appeal Panel is satisfied the appellant may have suffered a
substantial miscarriage of justice because:
(a) the decision of the Tribunal under appeal was not fair and equitable, or
(b) the decision of the Tribunal under appeal was against the weight of
evidence, or
(c) significant new evidence has arisen (being evidence that was not reasonably
available at the time the proceedings under appeal
were being dealt
with).
- In
relation to that clause, in Collins v Urban [2014] NSWCATAP 17 at [80] an
Appeal Panel of this Tribunal, by way of summary of relevant general principles,
after a review of a number of cases, said that:
“Accordingly, it should be accepted that a substantial miscarriage of
justice may have been suffered because of any of the
circumstance referred to in
cl 12(1)(a), (b) or (c) where there is a “significant possibility”
or “a chance which
was fairly open” that a different or more
favourable result would have been achieved for the appellant had the
circumstance
referred to in para (a) or (b) not occurred or if the fresh
evidence at para (c) had been before the Tribunal as first
instance.”
And similarly at [84] the Appeal Panel said
that:
In order to be granted leave to appeal, the applicant must demonstrate something
more than that the primary decision maker was arguably
wrong in the conclusion
arrived at or that there was a bona fide challenge to an issue of fact ...
Ordinarily it is appropriate to grant leave to appeal only in matters that
involve:
issues of principle;
questions of public importance or matters or administration or policy which
might have general application; or
an injustice which is reasonably clear, in the sense of going beyond merely what
is arguable, or an error that is plain and readily
apparent which is central to
the Tribunal’s decision and not merely peripheral, so that it would be
unjust to allow the finding
to stand;
a factual error that was unreasonably arrived at and clearly mistaken; or
the Tribunal having gone about the fact finding process in such an unorthodox
manner or in such a way that it was likely to produce
an unfair result so that
it would be in the interests of justice for it to be reviewed
...
- We
propose working through, in turn, the various matters relied on by the
appellants in their Notice of Appeal and submissions, however
they are
presented, whether as questions of law, as relating to leave to appeal, or
otherwise.
Lack of Procedural Fairness
- The
appellants allege various matters that could constitute a denial to them of
procedural fairness. An allegation of failure to afford
procedural fairness
would constitute a question of law (Prendergast at [12], Ayoub v CPT
Corp Pty Ltd [2015] NSWCATAP 239 at [19] ) and may ground a case that the
decision was not fair and equitable. These allegations principally include the
following passages
in the Notice of Appeal:
- (a) “We
were not given an opportunity to request for hearing adjournment so that we can
present all our evidence in a more formal
manner”.
- (b) “Significant
new evidence such as Building Expert report and witness statements as to
applicants’ refusal to provide
access to the property to complete the
rectification work was not available at the time of the original hearing. The
respondents’
request for extension of time to provide expert report was
refused by the Tribunal.”
- (c) “We
were not given a fair go, as the member failed to explain the format of the
proceedings and the member used our inexperience
to intimidate us thereby
preventing us from presenting our arguments coherently and without fear.
- (d) “The
respondents were not given prior notice of the opportunity available to
cross-examine the applicant’s expert
witness. Additionally the respondents
were not given an opportunity to bring the required witnesses from their
side.”
- The
appellants’ submissions repeat those allegations and develop some of them
by further allegations such as that:
- (a) The 30 June
2015 directions hearing had the effect that the direction on 10 February 2015
that they supply their material including
an expert report by 13 March 2015
“stands cancelled”. At the hearing on 17 August 2015 the Member
overlooked this and
his “judgment was based on the prejudice that the
appellants did not provide a timely report and the overlooking of direction
8 in
member Boyce’s orders in June is biased due to the error of fact and
contributed to procedural errors...”
- (b) Two of the
appellants are directors of a company that has a current building licence to
undertake construction work and “because
of the member’s
biases/prejudice and negative impression towards us, he did not seek to clarify
his assumptions nor gave us
the opportunity to expand our statement by using our
other licence”. The appellants were there referring to a NSW Fair Trading
licence contractor’s licence of Blessed Sydney Contracting Pty
Ltd.
- The
background against which those allegations should be considered involves matters
of fact and law.
- Dominant
relevant matters of fact we assess to be:
- (a) At the
directions hearing on 30 June 2015, as detailed in [7] of this decision above,
it was made quite clear, in our opinion,
that if the appellants did not finish
the work on the property within four weeks, the proceedings would go to a
“priority hearing”
and that in the meantime the applicants (and the
purchasers) had to comply with a procedural timetable; that timetable involved
among
other things evidence and other material being produced by the appellants
and the timetable was scheduled to conclude on 4 August
2015. The appellants
were, in our opinion, squarely on notice that the proceedings would proceed to a
hearing by the Tribunal if
the appellants had not finished the work on the
property within the four weeks and that preparation by the appellants for such a
hearing had to be attended to by them concurrently with work on the
property.
- (b) The
appellants were notified by a letter dated 2 July 2015 that the proceedings were
listed for hearing on 17 August 2015 ([8]
above).
- (c) The
appellants failed to comply with the directions made on 30 June 2015, even after
their application for an extension of time
made on 27 July 2015 was rejected by
a letter from the Tribunal Registry dated 4 August 2015 which also advised them
that they “should
comply with procedural directions as soon as
possible”. ([10] above).
- (d) At the
hearing on 17 August the appellants made no explicit application for
adjournment. The Member thoroughly discussed the history
of the proceedings with
the parties before proceeding with the hearing ([11] above). In the course of
that historical coverage, the
Member referred, quite appropriately in our
opinion, to the earlier default of the appellants in complying with the
directions of
10 February 2015 for service of material they relied on including
expert report by 13 March 2015 before he referred to their similar
default in
complying with the directions of 30 June 2015. No reference was made by the
appellants to the Blessed Sydney Contracting
Pty Ltd licence.
- Issues
of law may arise here concerning the principle of case management. The High
Court of Australia addressed that principle in
Expense Reduction Analysts
Group Pty Ltd v Armstrong Strategic Management Marketing Pty Ltd [2013] HCA 46; (2013) 250
CLR 303 at [51]:
In Aon Risk Services Australia Ltd v Australian National University [2009] HCA 27; (2009) 239
CLR 175, it was pointed out that case management is an accepted aspect of the
system of civil justice administered by the courts in Australia.
It had been
recognised some time ago by courts in the common law world that a different
approach was required to tackle the problems
of delay and cost in the litigation
process. Speed and efficiency, in the sense of minimum delay and expense, are
essential to a
just resolution of proceedings. The achievement of a just but
timely and cost-effective resolution of a dispute has effects not only
upon the
parties to the dispute but upon the court and other litigants. The decision in
Aon Risk Services Australia v Australian
National University was concerned with
the Court Procedures Rules 2006 (ACT) as they applied to amendments to
pleadings. However,
the decision confirmed as correct an approach to
interlocutory proceedings which has regard to the wider objects of the
administration
of justice.
- Section
36 of the NCAT Act bears on case management, particularly:
(1) The "guiding principle" for this Act and the procedural rules, in their
application to proceedings in the Tribunal, is to facilitate
the just, quick and
cheap resolution of the real issues in the proceedings.
(4) In addition, the practice and procedure of the Tribunal should be
implemented so as to facilitate the resolution of the issues
between the parties
in such a way that the cost to the parties and the Tribunal is proportionate to
the importance and complexity
of the subject-matter of the
proceedings.
- Section
38 also relevantly provides
(2) The Tribunal is not bound by the rules of evidence and may inquire into and
inform itself on any matter in such manner as it
thinks fit, subject to the
rules of natural justice.
...
(4) The Tribunal is to act with as little formality as the circumstances of the
case permit and according to equity, good conscience
and the substantial merits
of the case without regard to technicalities or legal forms.
(5) The Tribunal is to take such measures as are reasonably
practicable:
(a) to ensure that the parties to the
proceedings before it understand the nature of the proceedings, and
(b) if requested to do so-to explain to the parties any aspect
of the procedure of the Tribunal, or any decision or ruling made
by the
Tribunal, that relates to the proceedings, and
(c) to ensure that the parties have a reasonable opportunity
to be heard or otherwise have their submissions considered in the
proceedings.
- Some
of the appellants’ complaints, however, go further than those to which
case management may relate, with allegations such
as those in the Notice of
Appeal that they were not “given a fair go” and “the member
used our inexperience to
intimidate us...”. Those and additional
complaints submitted by the appellants and noted in [37] above amount to
allegations
of bias, certainly perceived bias and probably even actual bias, on
the part of the Tribunal. These are serious allegations and as
such would need
correspondingly cogent evidence to sustain them. To make out even perceived bias
it would have to be established
that in all the circumstances “...a
fair-minded lay observer might reasonably apprehend that the (Tribunal) might
not bring
an impartial mind to the resolution of the question the (Tribunal) is
required to decide”. (Ebner v Official Trustee [2000] HCA 63; (2000) 205 CLR 337
at [6]).
- In
the circumstances of these proceedings which have outlined at [4] to [15] of
this decision above in respect of the interlocutory
stages and the hearing on 17
August 2015, we see the Tribunal as having given the appellants adequate
opportunities to participate
in the hearing by questioning the purchasers’
witnesses, by the production of their own evidence, and otherwise; we also see
the appellants as having failed to make proper use of those opportunities,
particularly by failing to produce their own evidence.
- The
Member’s decision to proceed with the hearing on 17 August 2015 was, in
our opinion, appropriate. We see no justification
for any of the
appellants’ additional allegations noted in [37] above; and we will
comment further on the licence situation
below. We are of the firm view that in
these respects about which the appellants complain, there was no denial of
procedural fairness
and that the subject decision was fair and equitable; the
appellants did not thereby suffer a substantial miscarriage of justice.
We
certainly see no acceptable basis for the claims by the appellant of bias in the
Tribunal; at the hearing the appellants were
treated firmly but fairly by the
Member and the Member spoke to them by way of explanation and guidance, not
intimidation.
Section 48MA Home Building Act
- The
appellants complain, in conjunction with allegations that they were not given an
opportunity to complete rectification work on
the property, that the Tribunal
did not consider s48MA of the Home Building Act 1989 (“the
HBA”). That section relevantly provides that in determining a building
claim involving an allegation of defective
residential building work by a party
to the proceedings (“the responsible party”) the Tribunal is to have
regard to the
principle that rectification of the defective work by the
responsible party is the preferred outcome. The section was inserted in
the HBA
by the Home Building Amendment Act 2014 (“the amending Act”)
and came into operation on 15 January 2015. Clause 121(2)(a) of Schedule 4 of
the HBA provides that
an amendment made by the amending Act does not apply to or
in respect of proceedings commenced in a court or tribunal before the
commencement of the amendment (whether or not the proceedings were finally
determined before that commencement). The subject proceedings
were commenced on
29 December 2014. Section 48MA was not raised as an issue in the subject
proceedings and it did not apply to the
subject proceedings in any event.
- We
add that matters bearing on these complaints by the appellant concerning the
principle covered by s48MA of the HBA, were taken
into account in the subject
proceedings:
- (a) Much of the
interlocutory history of the subject proceedings involved delays for the
appellants to do work on the property, and
that work, evidently to a significant
extent, was not completed.
- (b) At [11] in
the appealed decision it was recorded that “the building licence of Ausko
Building and Construction Pty Ltd was
suspended on 15 July, and that licence was
due to expire on 21 July 2015”.
New
Evidence
- It
is convenient to turn to the issue of new evidence before dealing with the issue
concerning weight of evidence. As we have noted
at [23] above, the Notice of
Appeal identified the new evidence that the appellants now seek to produce to
the Tribunal as:
An expert building report.
Witness statements as to the applicant’s refusal to provide access.
Bring witnesses to the Tribunal.
- The
appellants included various items of an evidentiary nature in the material
lodged by them for the appeal hearing. Those items
do not include an
expert’s report and it appears that the appellants have not obtained one.
Included among the items are:
- (a) A copy of a
NSW Fair Trading contractor licence in the name Blessed Sydney Contracting Pty
Ltd current to 21 November 2018;
- (b) A statutory
declaration (undated) by the appellants Messrs James and Augustus in the
following terms:
We both appellants went to the
respondent’s house in the month April 2015 around 8 pm at the agreed time
and initiated a dialogue
with a view to reach a settlement. After 2 hours of
deliberations, we reached an agreement to undertake about 10 major items as a
settlement of the total of around 64 items. The respondents told us to type the
agreement and bring it next day for their signatures.
The respondents next day
said they have changed their mind and would want to add another 10 items. We
agreed to their request. When
we went with the agreement the respondents evaded
signing and asked us to bring it again later. They did not sign the agreement
and
at the same time made us to complete 19/20 of the agreed
works.
(c) A statutory declaration (dated 6 February 2016) by a tiling and
waterproofing contractor who says he was engaged by the builder
to do
waterproofing on the property in March 2013 and sent an employee to do repair
works on the property in May 2015. He says, in
effect, that repairs could not be
carried because of difficulties (which he detailed to an extent) his employee
told him he had in
getting access to the property.
- No
explanation is proffered by the appellants in this appeal as to why this new
evidence was not available at the time of the hearing.
The contractor’s
licence of Blessed Sydney Contracting Pty Ltd was not referred to by the
appellants at the hearing (as we
will detail below). The allegations concerning
an agreement as to work to be done on the property for the appellants and as to
difficulties
of access to the property for the purpose of such work, were made
at the hearing, and dealt with in the appealed decision at [15]
thereof:
Ms Shahin Sheikh gave evidence on behalf of the applicant and was available for
cross-examination by the respondents. It was suggested
that there were problems
with the applicants refusing to provide access to the property but this was
disputed by the applicants.
In cross-examination on behalf of the respondents,
it was suggested that there was an agreement to rectify only 20 items and that
the developers were to be released from further liability on completion of those
items. This assertion was disputed by Ms Sheikh
on behalf of the
applicants.
While the Member did not go on to make explicit
findings concerning the matters that he was there referring to, it is clear
enough
that he did not accept the appellants’ (the then respondents)
contentions concerning them.
- In
the particulars in the Notice of Appeal concerning the claim that the decision
was not fair and equitable, the appellants state
that “the new expert
report and witness reports as to applicants’ refusal to provide access to
complete the rectification
works will shed more light on the matter and will
help the decision maker to make a fair and evidence-based decision”. What
the appellants have put up at the hearing of the appeal does not persuade us of
that.
- The
appellants have not in our opinion made out any case that they may have suffered
a substantial miscarriage of justice because
significant new evidence is now
available that was not reasonably available at the time of the
hearing.
Weight of Evidence
- Our
scrutiny of the Notice of Appeal and the appellants’ submissions leads us
to discern that complaints by the appellants that
the appealed decision was
against the weight of evidence centre on the following matters:
- (a) The alleged
agreement concerning the appellants satisfying the purchasers’ claims by
performing rectification work on the
property (which we will henceforth refer to
as “the rectification arrangement”). Associated with the
rectification arrangement
are the issues raised by the appellants concerning
access by the appellants to the property and HBA licence authority for the
appellant
to do that work.
- (b) The
purchasers’ expert evidence.
- The
appealed decision at [15] thereof dealt with the rectification arrangement, as
we have quoted at [50] of this decision above.
At the hearing of the subject
proceedings at transcript p.30 Ms Sheikh, during questioning by Mr Iyadurai
(assisted by the Member)
concerning the rectification arrangement, said
“...it was a part of negotiations which were initiated but it’s
never
come to an agreement...”. At transcript p.22 in response to
questions from the Member she gave evidence that access was given
for the
purposes of rectification work except on one occasion when a tradesman arrived
without notice when she was going out. There
was no evidence to the contrary
offered at the hearing by the appellants. In these circumstances we cannot
accept that the way in
which the Member dealt with the rectification arrangement
and access, was against the weight of evidence.
- Associated
with the rectification arrangement is a question relating to HBA licence
authority for the appellants to do rectification
work on the property. As we
have pointed out in [50] above the contractor’s licence of Blessed Sydney
Contracting Pty Ltd was
not referred to at this hearing and we will now relate
some details about that. At the hearing at p.7 of the transcript the Member
spoke to Mr Iyadurai about the builder then being unlicensed and only a licensed
builder being able to do rectification. Mr Iyadurai
responded that they had
tradespersons who were licensed during the work and the Member said that he had
no evidence of that. Towards
the end of the hearing, as we have quoted in [11]
of this decision above, the Member included in comments to Mr
Iyadurai:
So the only order available now where the builder is unlicensed and the
developers are unlicensed and where the parties haven’t
reached agreement
is for me to make an order about how much you pay for these works to be
done...”.
Neither on those occasions, nor on any occasion
during the hearing, did the appellants make any reference to this licence or how
the
appellants had used, or could use, that in relation to rectification work on
the property.
- In
their submissions the appellants assert that the report of the purchasers’
expert was not independent and professional. The
report was by a building
consultant who listed his qualifications as including his being a clerk of
works, licenced as a master builder
and building consultant and accredited as a
consultant with the Master Builders Association and with the Institute of
Building consultants.
His curriculum vitae was attached which detailed his
continuous career in the building construction industry to date, commencing
in
1972 with a carpentry and joinery trade course. He was retained by the
purchasers, he said in his report:
“...to carry out an inspection of the incomplete and unsatisfactory works
on the property and furnish a report. The report
is to comment on any defects
that exist, unfinished works and provide remedy to rectify any claimed
defect.”
- The
report records that inspections were carried out by him on 28 April 2014, 21
October 2014 and 7 July 2015. The report used at
the hearing was a revision of
an earlier report or reports and was prepared following the consultant’s
last inspection of the
property on 7 July 2015. The report detailed and
scheduled numerous works which were “incomplete, unsatisfactory or not
attempted”.
A Scott Schedule with costings was attached. As we have noted
above at [12], the consultant gave evidence at the hearing in response
to
questions from the Member and with reference to his report and Scott Schedule,
and he was questioned by Mr Iyadurai. The questions
which Mr Iyadurai asked him
related only to particular items such as driveway drainage, bathroom drainage,
and landscaping, particularly
with reference to the local Council’s
occupation certificate, and also to the need for maintenance by the purchasers.
No direct
challenge was made by Mr Iyadurai to the consultant’s expertise
or to any of his costings or other details in the report.
- A
principal expression of their complaints about the expert report in the
appellants’ submissions is that:
“The opinions in the expert report are not based on facts, matters and
assumptions and the cost estimates are not competitive
quotes and they are not
substantiated by any calculations, neither has he provided reasons for his
opinion which further confirms
that the expert is not professional and does not
meet the requirements of an expert report.”
Their
submissions in reply add a complaint that the report fails to meet the
requirements of the Tribunal’s Practice Direction
No.3 and of Makita
(Australia) Pty Ltd v Sprowles [2001] NSWCA 305; (2001) 52 NSWLR 705.
- We
are considering these complaints concerning this report in the context of an
allegation that the appealed decision was against
the weight of evidence.
Effectively, the appellants’ submissions are that the report should not
have been admitted into evidence
and should not have been used for the purposes
of the appealed decision. We note that in Makita v Sprowles at [85]
Heydon J said:
“In short, if evidence tendered as expert opinion evidence is to be
admissible, it must be agreed or demonstrated that there
is a field of
‘specialised knowledge’; there must be identified an aspect of that
field in which the witness demonstrates
that by reason of specified training,
study or experience, the witness has become an expert; the opinion proffered
must be ‘wholly
or substantially based on the witness’s expert
knowledge; so far as the opinion is based on facts ‘observed’ by
the
expert, they must be identified and admissibly proved by the expert, and so far
as the opinion is based on ‘assumed’
or ‘accepted’
facts, they must be identified and proved in some other way; it must be
established that the facts on which
the opinion is based form a proper
foundation for it; and the opinion of an expert requires demonstration or
examination of the scientific
or other intellectual basis of the conclusions
reached; that is, the expert’s evidence must explain how the field of
‘specialised
knowledge’ in which the witness is expert by reason of
‘training, study or experience’ and on which the opinion
is
‘wholly or substantially based’, applies to the facts assumed or
observed so as to produce the opinion propounded.”
- We
also note that the Tribunal’s Practice Direction 3 deals with Expert
Witnesses principally by adopting a code of conduct
for such witnesses based on
Schedule 7 to the Uniform Civil Procedure Rules 2005. It stipulates that
an expert’s report must include an acknowledgment that the expert has read
the experts’ code of conduct
and agrees to be bound by it. It suffices for
us to say that we see the purchasers’ consultant’s report as
substantially
complying with the requirements summarised by Heydon JA and the
experts’ code of conduct. The report did not include an acknowledgment
that the consultant had read the experts’ code of conduct and agreed to be
bound by it. The Procedural Direction, however,
includes clause
3:
“The Tribunal may excuse an expert witness or any other person from
complying with this Procedural Direction before or after
the time for
compliance.”
- In
our opinion in the circumstances we have related above, it was in order for the
Member to have received this report into evidence
and acted upon
it.
Other Matters
- The
appealed decision at [25] stated:
“It has not been disputed in the present case that the second, third and
fourth respondents were developers within the meaning
of s3A of the Home
Building Act 1989. I am satisfied that for the purposes of subsection (2)
‘residential building work’ was being done in a building or
residential
development where 4 proposed dwellings would be owned by the
partnership comprised of the second, third and fourth
respondents.”
- In
submissions in reply an issue has been raised on behalf of the appellants that
there was no concession by the appellants to the
effect there stated in the
decision and that there was no pleading or evidence to support it. Section 3A of
the HBA provides:
(1) For the purposes of this Act, an individual, a partnership
or a corporation on whose behalf residential building is done in
the
circumstances set out in subsection (2) is a developer in relation to that
residential building work.
(1A) Residential building work done on land in the
circumstances set out in subsection (2) is, for the purpose of determining
who
is a developer in relation to the work, deemed to have been done on behalf of
the owner of the land (in addition to any person
on whose behalf the work was
actually done).
Note: This makes the owner of the land a developer even if the work is actually
done on behalf of another person (for example, on
behalf of a party to a joint
venture agreement with the owner for the development of the land). The other
person on whose behalf
the work is actually done is also a developer in relation
to the work.
(2) The circumstances are:
(a) the residential building work is
done in connection with an existing or proposed dwelling in a building or
residential development
where 4 or more of the existing or proposed dwellings
are or will be owned by the individual, partnership or corporation, or
(b) the residential building work is done in connection with an
existing or proposed retirement village or accommodation specially
designed for
the disabled where all of the residential units are or will be owned by the
individual, partnership or corporation.
(3) A company that owns a building under a company title is
not a developer for the purposes of this Act.
- At
the directions hearing in the subject proceedings on 7 April 2015 the following
exchange occurred between the Member and Messrs
Augustus and Iyadurai
(transcript p.4):
MEMBER: What is Ausko Building & Construction Pty Limited
– I see in the notes that they’re not licensed. Were
they the
builders?
V AUGUSTUS: They’re the builders, yes.
MEMBER: And you were the developers? You owned the land?
V AUGUSTUS: Correct.
IYADURAI: We did own the land.
MEMBER: Did own the land, you developed it—
IYADURAI: Correct, yeah.
MEMBER: --you sold it off.
IYADURAI: Yep.
MEMBER: Units, are they, townhouses?
IYADURAI: Townhouses.
- At
the hearing on 17 August 2015 Ms Sheikh gave evidence to the effect that there
were four lots involved in the development, which
included the property
(transcript p.17). During the hearing there were numerous references to the
appellants as “the developers”.
- It
was not in dispute at the hearing that the appellants were developers. It is
clear that in points of fact and law, the appellants
were developers. The issue
is baseless. It should not have been raised on appeal, particularly in
submissions in reply (Mamo v Surace [2014] NSWCA 58; (2015) 86 NSWLR 275 at [75] to [82];
Drivas v Burrows [2014] NSWCATAP 87 at [30] to [33] and Nelmeer
Ashfield Pty Ltd v Farah [2015] NSWCATAP 276 at [48], [74] and [75])).
- In
the submissions in reply, the point is also taken that the appellants dispute
the award in favour of the purchasers of $7,480.00
in respect of the cost to
them of the building consultant. This point is linked to the appellants’
challenges in this appeal
to the receipt of the consultant’s evidence at
the hearing, which challenges we have already rejected in these reasons. In
the
appealed decision at [61] the Member explained this order:
“The applicants have been self-represented but it is noted that expert
report costs relevant to the proof of this application
have been incurred in a
total sum of $7,480.00 inclusive of GST. The Tribunal and the respondents have
all been provided with copies
of each tax invoice and a summary of the total
costs in accordance with directions which were made. Having perused the tax
invoices
and the summary, I am satisfied that it would not be appropriate for
the monies payable to the applicants to be reduced by the cost
of the experts
reports which were necessary to allow the claim to be properly established. In
the circumstances the respondents are
ordered to pay the costs of the applicant
in an assessed sum of $7,480.00.”
- Such
an order would be within the generality of the monetary orders which the
Tribunal is empowered to make by s48O(1)(a) of the HBA:
An order that one party to the proceeding pay money to another party or to a
person specified in the order, whether by way of debt,
damages or restitution,
or refund of any money paid by a specified person.
In our opinion
this order in the appealed decision was appropriate and does not warrant any
review in this appeal.
- In
the appealed decision no order was made in respect of the builder. The
appellants complain about that. As the contractor for the
work on the property,
the builder also had a potential liability to the purchasers, which has not been
determined, despite the builder
being a party to the subject proceedings and
represented at the hearing on 17 August 2015. The builder was not party to this
appeal
and no representative of the builder attended the hearing of the appeal.
The proceedings should be remitted to the Consumer and Commercial
Division as
previously constituted if that be practicable, for consideration of any order
that may be appropriate to be made in respect
of the builder. The builder
provided no evidence at the hearing and that consideration should be made on the
evidence that was tendered
at the hearing of the subject
proceeding.
Conclusion
- It
follows from the reasons we have given above that we are satisfied that none of
the grounds relied on by the appellants has been
made out. The Appeal and
Application for Leave to Appeal should be dismissed. The orders made in the
appealed decision should be
affirmed, and the proceedings should be remitted to
the Consumer and Commercial Division for consideration of the issue of any order
that may be appropriate to be made in respect of the
builder.
Stay
- As
we have noted above at [26], there is an extant application by the appellants
for a stay in respect of the appealed decision, coupled
with an order
restraining the purchasers from carrying out rectification work on the property.
Section 43(3) of the NCAT Act empowers
the appeal panel in its discretion to
order such a stay or make such other order as “it considers appropriate to
secure the
effectiveness of the determination of the ... appeal”. Having
regard to the conclusions we have come to in this appeal, such
a stay or any
other order is not appropriate and that application should be
dismissed.
Costs
- The
purchasers had legal representation at this appeal and have asked for costs. The
issue of the costs was not the subject of any
submissions at the appeal hearing.
As the Notice of Appeal was lodged before 1 January 2016 new r 38A in the NCAT
Rules does not
apply and in accordance with s 60 of the NCAT Act special
circumstances warranting an award of costs would have to exist. Nevertheless,
the purchasers should be given an opportunity to pursue the issue of costs and
we will make orders concerning that.
Orders
- The
Appeal Panel therefore makes the following orders:
- (1) The time
for instituting this appeal is extended to 6 November 2015.
- (2) Subject to
order 4, the Appeal and the Application for Leave to Appeal are dismissed.
- (3) The order
appeal from is affirmed.
- (4) The subject
proceedings are remitted to the Consumer and Commercial Division of this
Tribunal for consideration (on the evidence
tendered at the hearing on 17 August
2015) of any order that may be appropriate to be made in respect of the first
respondent in
the subject proceedings, Ausko Building & Construction Pty
Ltd.
- (5) The
Registrar is to arrange for a copy of this decision to be forwarded to Ausko
Building & Construction Pty Ltd at its registered
office promptly after
publication of this decision with a covering letter drawing attention
particularly to Order 4 above.
- (6) If the
Respondents wish to make an application for their costs of this appeal, they are
to do so by filing, and serving on the
Appellants, written submissions within 14
days after the publication of this decision and the Appellants may file, and
serve on the
Respondents, submissions in reply within 14 days after service on
them of the Respondents’ submissions. Any such application
will then be
decided on the papers.
- (7) The
application for a stay (and other order) is
dismissed.
********
I hereby certify that this is a true and accurate record of the reasons for
decision of the Civil and Administrative Tribunal of New
South
Wales.
Registrar
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWCATAP/2016/108.html