[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales |
Last Updated: 29 November 2004
NEW SOUTH WALES SUPREME COURT
CITATION: Bell Partners v Kann Finch
[2004] NSWSC 1034 revised - 26/11/2004
CURRENT JURISDICTION:
Common Law
FILE NUMBER(S): 12030/2004
HEARING DATE{S): 29
October 2004
JUDGMENT DATE: 08/11/2004
PARTIES:
Bell
Partners Accountants and Business Advisors Pty Ltd
(Plaintiff)
Kann
Finch Pty Ltd
(Defendant)
JUDGMENT OF: Master Harrison
LOWER COURT JURISDICTION: Local Court
LOWER COURT FILE
NUMBER(S): 12233/03
LOWER COURT JUDICIAL OFFICER: Magistrate Michael
Price
COUNSEL:
Mr M B J Lee
(Plaintiff)
Mr J
Orsborn
(Defendant)
SOLICITORS:
Freidman
Reeves
(Plaintiff)
Holding
Redlich
(Defendant)
CATCHWORDS:
Appeal decision of Local
Court Magistrate; summary judgment; Building Construction Industry Security of
Payment Act 1999 (NSW)
ACTS CITED:
Building and Construction Industry
Security of Payment 1999 (NSW) - s 13
Local Court (Civil Claims) Act 1970
(NSW) - s 69
Local Court (Civil Claims) Rules 1988 (NSW) - Pt 10A r
2
DECISION:
(1) The appeal is dismissed
(2) The decision of the
Magistrate Michael Price dated 7 June is affirmed
(3) The amended summons
field 29 October 2004 is dismissed
(4) The plaintiff is to pay the
defendant's costs as agreed or assessed.
JUDGMENT:
IN THE SUPREME COURT
OF NEW SOUTH
WALES
COMMON LAW DIVISION
MASTER
HARRISON
MONDAY, 8 NOVEMBER 2004
12030/2004
- BELL PARTNERS ACCOUNTANTS AND
BUSINESS ADVISORS PTY LTD
v
KANN FINCH PTY LTD
JUDGMENT (Appeal decision of
Local Court Magistrate;
summary judgment; Building Construction
Industry Security of Payment Act 1999
(NSW))
1 MASTER: By amended summons filed 29 October 2004 the
plaintiff seeks firstly, to appeal the decision of Local Court Magistrate Judge
Michael
Price made on 7 June 2004 pursuant to s 69 of the Local Court (Civil
Claims) Act 1970 (NSW); secondly, an order setting aside the orders made on
7 June 2004; thirdly, an order that the defendant’s motion
be dismissed
with costs; and fourthly, in the alternative, an order setting aside the orders
of Magistrate Judge Price made on 7
June 2004 and remitting the matter the Local
Court for determination. The plaintiff is Bell Partners Accountants and Business
Advisors
Pty Limited (Bell). The defendant is Kann Finch Pty Ltd (Kann). The
plaintiff relied on two affidavits of Scott Maurice Freidman
sworn 23 August
2004 and 21 October 2004 respectively.
2 At the outset, it may be helpful
to make some brief comments concerning the remedy pursued by the plaintiff.
Section 69(2) of the
Local Courts (Civil Claims) Act 1970 (NSW) permits a
party who is dissatisfied with a judgment as being erroneous in point of law to
appeal to this Court. The onus
lies on the plaintiff to demonstrate that there
has been an error of law. What is a question of law (as opposed to a question of
fact) was considered, inter alia, in Allen v Kerr & Anor (1995) Aust
Torts Reports 81-354; Azzopardi v Tasman UEB Industries Ltd (1985) 4
NSWLR 139 at 155-156 and two more recent cases, namely Carr v Neill
[ 1999] NSWSC 1263 and R L & D Investments Pty Ltd v Bisby [2002] NSWSC 1082. Section 69(4) of the Act provides that the court may determine an
appeal by either (a) setting the judgment or order aside or (b)
by varying the
terms of the judgment or order or (c) by setting the judgment or order aside and
remitting the matter for determination
in accordance with the court’s
directions or (d) by dismissing the appeal.
Grounds of
appeal
3 Bell Partners appeal the whole of the decision of Magistrate
Judge Price. The grounds of appeal are firstly, that the Magistrate
erred by
ordering summary judgment where there was no evidence before him as required by
Part 10A r 2 of the Local Court (Civil Claims) Rules 1988 (NSW)
(LCR) by a responsible person giving evidence that Bell Partners had no
defence to the claim of Kann Finch in the proceedings; secondly,
the Magistrate
erred by purporting to find that Kann Finch was entitled to a progress payment
entitling it to serve on Bell Partners
a progress claim pursuant to s 13 of the
Building and Construction Industry Security of Payment Act 1999 (NSW)
(the Act); thirdly, alternatively, the Magistrate erred by purporting to find
the progress claim served by Kann Finch
were effective progress claims in
accordance with the provisions of the Act; fourthly, the Magistrate erred by
ordering summary
judgment in circumstances where a triable issue existed in the
proceedings; and fifthly, the Magistrate erred in purporting to deliver
a
reserved judgment otherwise than in accordance with the provisions of Part 3 r 8
of the rules.
Local Court proceedings
4 On 22 April 2004
Kann Finch, by notice of motion dated 1 March 2004, sought summary judgment,
interest and costs against Bell Partners
for services provided within the
meaning of the Act.
5 On 7 June 2004 the Magistrate gave reasons for
judgment.
“ ‘.... The work, the subject of this decision, is
described as “provide design services”. In the present
instance the
work is covered by s 6 definition of related goods and services, specifically
6(1)(b). S 15 precludes judgment in favour
of a claimant, the plaintiff, unless
the court is satisfied of the existence of circumstances referred to in (1) and
(b) the respondent,
the defendant, is not in those proceedings entitled (1) to
bring any cross-claim against the claimant or (2) to raise any defence
in
relation to matters arising under the construction contract.’
This
Court is not of the view that the matters raised by the respondent to this
motion give rise to a triable issue and given the
statutory scheme within the
legislation, the defence is without merit; or, to use the words more
accurately, is hopeless.
Specifically, the Court would find that there
has been compliance with the specific requirements of the particular
legislation, that
is, the Building and Construction Industry Security and
Payment Act (1999), so far as payment claims be concerned and a want of any
issue of Payment Schedules by the recipient.
IN THOSE CIRCUMSTANCES, THE
MOTION IS GRANTED THAT THE APPLICANT, THAT IS, THE PLAINTIFF, MAY PROCEED TO
SUMMARY JUDGMENT IN ACCORDANCE
WITH THE ACT.”
Summary
judgment
6 Relevantly, Part 10A r 2 of the LCR
provides:
“Summary judgment
(1) Where, on application by the
plaintiff in relation to any claim for relief or any part of any claim for
relief of the plaintiff:
(a) there is evidence of the facts on which the
claim or part is based, and
(b) there is evidence given by the plaintiff
or by some responsible person that, in the belief of the person giving the
evidence,
the defendant has no defence to the claim or part, or no defence
except as to the amount of any damages claimed,
the court may, at any
time, give such judgment for the plaintiff on that claim or part as the nature
of the case requires.”
7 The test for summary judgment is not in
doubt. The Magistrate referred to the correct test. The plaintiff submitted
that the Magistrate
erred in law as there was no affidavit evidence given by
Kann or a responsible person of Kann, that in their belief there was no
defence
to the claim.
8 Both parties referred to Long Leys Co Pty Ltd v
Silkdale Pty Ltd (1991) NSWCA, 19 December 1991. Essentially the case
before the Magistrate was a legal one and involved the interpretation of s 13 of
the Act. Bell
did not put on any evidence. Under the Act there are limited
avenues for Bell to challenge the rights of Kann to recover the amounts
due
under the payment claims.
9 In Long Leys, Sheller JA (with whom
Priestley and Meagher JJA agreed) when considering a similar SCR in
relation to summary judgment stated:
“However, on an application
for summary judgment where the defendant appears, the Court is bound to consider
the pleading, all
the evidence admitted and submissions put to it. If having
done so it concludes that the defendant has no defence I do not think
that it is
powerless or, as has been suggested in some of the cases, without jurisdiction
to make an order for summary judgment for
reason only that the plaintiff’s
affidavit does not comply with the rule.
In the present case we are told
that at least one day was spent in argument before the Master and one day before
Sully J. The arguments
ranged at large upon the question of whether the
appellant had any defence and if so what it was. It would be quite extraordinary
if the Court, having listened to every argument that the wit of ingenious
counsel could advance to show that there was an arguable
defence and having come
to the conclusion that there was none, must refuse the application for summary
judgment because of a failure
to comply with Pt132(1)(b). As Vaughan Williams LJ
pointed out in Symon and Co v Palmer’s Stores (1903) Ltd at 264 provisions
such as those contained in Pt132 are salutary provisions for the purpose of
preventing a defendant, who knows perfectly well that
he owes the sum claimed,
postponing the time of payment, and putting the plaintiff to further expense in
a litigation which ought
never to have taken place. To refuse an application for
summary judgment because of the form of the affidavit in a case where the
existence of an arguable defence has been fully investigated and there is found
to be none uses the rule to defeat the purpose that
it is intended to
achieve.”
10 Part 1 r 5 of the LCR allows the Court, if it
thinks fit, to dispense with compliance with the rules either before or after
the occasion for compliance
arises. It was within the Magistrate’s power
to dispense with the requirements. In this case, like in Long Leys, the
Magistrate fully investigated the existence of an arguable defence and found
there was none. There is no error of law.
Building and Construction
Industry Security of Payment Act 1999 (NSW)
11 The submissions put
before the Magistrate were before this Court. Kann submitted that 5 payment
claims dated 19 September 2003
were issued to Bell in compliance with the Act
and because Bell did not serve a payment schedule in response as required by s
14
of the Act, it became liable to pay the amount claimed.
12 The first
submission to the Magistrate concerned progress payments. Firstly, the object
of the Act is set out in s 3. It is:
“(1) ... to ensure that any
person who undertakes to carry out construction work (or who undertakes to
supply related goods
and services) under a construction contract is entitled to
receive, and is able to recover, progress payments in relation to the
carrying
out of that work and the supplying of those goods and services.
(2) The
means by which this Act ensure that a person is entitled to receive a progress
payment is by granting a statutory entitlement
to such a payment regardless of
whether the relevant construction contract makes provision for progress
payments.”
13 “Progress payment” and ‘Payment
claim” are defined in the definitions contained in s 4. They are
different.
A “payment claim” means a claim referred to in s 13.
The statutory regime
14 The scheme for payment of payment
claims under the Act is set out in ss 8, 13, 14(4) and 15. They provide that on
and from each
reference dated under a construction contract a person who had
undertaken to carry out construction work under the construction contract
is
entitled to a progress payment – s 8.
15 A person referred to in
s 8(1) who is or who claims to be entitled to a progress payment may serve a
payment claim on the person
who under the construction contract concerned is or
may be liable to make the payment – s 13. The payment claim can be served
up to 12 months after the construction work was carried out – s
13(4).
16 If a claimant serves a payment claim on a respondent and the
respondent does not provide a payment schedule to the claimant within
the time
required by the construction contract or within 10 business days after the
payment claim is served, whichever time expires
earlier, the respondent becomes
liable to pay the claimed amount to the claimant on the due date for the
progress payment to which
the payment claims relates – s 14(4).
17 If a respondent becomes liable to pay the claimed amount to the
claimant under s 14(4) as a consequence of having failed to provide
a payment
schedule within the time allowed by that section and fails to pay the whole or
any part of the claimed amount on or before
the due date for the progress
payment to which the payment claim relates (s 15(1)) then the claimant may
recover the unpaid portion
of the claimed amount from the respondent as a debt
due to the claimant in any court of competent jurisdiction – s
15(2)(a)(i).
18 If a claimant commences proceedings under s 15(2)(a)(i)
to recover the unpaid portion of the claimed amount from the respondent
as a
debt the respondent is not in those proceedings entitled to bring any
cross-claim against the claimant or to raise any defence
in relation to those
matters arising under the construction contract – s
15(4).
19 Einstein J stated in Isis Projects Pty Ltd v Clarence Street
Limited [2004] NSWSC 222 at para 33:
“Hence it is clearly
necessary in order that a claimant prove that a respondent's liability has
accrued under section 15 (1)
(a) [to satisfy the precondition to be found in
subsection (4) (a)], that the claimant prove that a valid payment claim
has been served and also clearly prove what is the due date for the progress
payment. There will of course always
be a due date for a progress payment under
a construction contract because the Act [s 11] provides for such a date as being
either:
· the date on which the payment becomes due and payable in
accordance with the terms of the contract; or
· if the contract
makes no express provision with respect to the matter, the date occurring 10
business days after a payment
claim is made in relation to the
payment.”
20 Bell’s submission before the Magistrate was that
the plaintiff’s entitlement to a progress payment could only arise
if it
issued progress payments in 3 equal intervals in 3 equal amounts of $6,216.00
during construction, but Kann did not issue the
progress claims in accordance
with the construction contract. According to Bell, Kann is not a person
entitled to a progress payment
and therefore may not serve a payment claim
pursuant to s 13 of the Act.
21 Five tax invoices were in evidence before
the Magistrate. They represented three instalments and two extra amounts.
There were
three reference dates for the first three payment claims as per
contract (email dated 21 November 2002). The contract provided that
the fee was
$18,650.00 to be invoiced over three equal intervals commencing when
construction began. If the proposed construction
period was six weeks long,
three payments of $6,216.00 each at week two, week four and week six were
expected. The first three tax
invoices were issued on a fortnightly basis (week
2, week 4 and week 6). The works commenced on 10 March 2003. The due dates or
reference dates for the progress payments were 24 March 2003, 7 and 21 April
2003. In respect of the extra works, there were some
carried out in April 2003.
Thus for the extra payments pursuant to s 11, the relevant reference dated would
be the end of the month,
being 30 April 2003. In respect of the July works, the
reference date is 31 July 2003. The passage set out in Isis has been
complied with. This argument is hopeless.
22 Bell’s second
submission to the Magistrate was that s 13 of the Act provides that a payment
claim must identify the construction
work or the related goods or services to
which the progress payment relates. According to Bell, payment claims 1, 3 and
4 identify
the same work performed and it is not possible for the Kann in
respect of each payment claim to identify what additional work if
any was done
by Bell in the periods referred to. Payment claims 3 and 4 are in respect of
periods which overlap in contravention
of s 13(5). Further Bell submitted that
progress claim 4 is also defective because, contrary to s 8(2)(b) it does not
identify a
reference date which is the end of the month during which the
relevant work was carried out. The Magistrate was correct to hold
that these
submissions were hopeless.
23 Finally Bell submitted that it is arguable
that the services identified in progress claim 1 do not come within the
definitions
of “construction work” or “related goods and
services” as those terms are defined by the Act. The Magistrate
held that
the work was described as provide design systems and this work fell within the
definition of related goods and services.
The Magistrate was entitled to do so.
This work clearly falls within the definition of related goods and services.
There is no
error of law.
Reserved decision
24 Bell
submitted there was no effective determination made and that to deliver a
reserved judgment without the parties having been
given the opportunity to be
present is a denial of natural justice. Whether it is a denial of natural
justice depends on the facts
and circumstances of each case.
25 At the
conclusion of the hearing on 22 April 2004 the Magistrate
stated:
“I might take the opportunity of re-reading those written
submissions on behalf of both parties. I’ll give a decision
late this
afternoon and I’ll get the registrar to notify you
both.”
26 The parties were not notified of the date that judgment
was to be delivered. Hence the parties were not present in Court when
the
Magistrate delivered his reasons for decision and judgment.
27 On 7 June
2004 the Local Court wrote to Bell Partners solicitor advising him of the
Magistrate’s orders. It stated:
“Please note that at the
notice of motion hearing 07/06/04 the Court made the following order ...
:
MOTION GRANTED. APPLICANT (PLAINTIFF) AT LIBERTY TO PROCEED TO SUMMARY
JUDGMENT IN ACCORDANCE WITH THE ACT.
(1) SUMMARY JUDGMENT BE ENTERED FOR
THE PLAINTIFF IN THE SUM OF $26,825.70 TOGETHER WITH INTEREST AND
COSTS.”
28 Relevantly, Part 3 r 8 of the LCR
provides:
“Reserved decision
(1) Where in any proceedings a
Magistrate or Assessor reserves a judgment or decision on any question of fact
or law, the Magistrate
or Assessor may:
(a) give the judgment or
decision:
(i) in court at the proper court in relation to those
proceedings,
(ii) in court at any other court at which the Magistrate or
Assessor is authorised to hear or dispose of those proceedings,
or
(iii) in chambers in accordance with rule 7, or
(b) draw up in
writing the judgment or decision, sign it and forward it to the registrar of
that proper court.”
29 While I agree that it is not desirable that
judgments be delivered without giving the parties an opportunity to be present,
Part
3 r 8(1)(a)(i) of the LCR provides that a Magistrate may give a
judgment in court at the proper court in relation to those proceedings. It does
not stipulate
that the parties should be notified of that date. The Magistrate
has complied with Part 3 r 8 of the LCR. On 7 June 2004, the day the
Magistrate delivered his judgment, the Registrar notified the parties in writing
of the decision.
There is no denial of natural justice. Even if the Magistrate
had not complied with Part 3 r 8(1)(a)(i) of the LCR or if I am wrong and
there is an error of law there would be no utility in remitting the matter back
for him to read his decision
to the parties. There has been no error of law.
30 The appeal is dismissed. The decision of the Magistrate Judge Price
dated 7 June 2004 is affirmed. The amended summons filed
29 October 2004 is
dismissed.
31 Costs are discretionary. Costs usually follow the event.
The plaintiff is to pay the defendant’s costs as agreed or
assessed.
The court orders:
(1) The appeal is
dismissed.
(2) The decision of the Magistrate Judge Price dated 7 June
2004 is affirmed.
(3) The amended summons filed 29 October 2004 is
dismissed.
(4) The plaintiff is to pay the defendant’s costs as
agreed or assessed.
**********
LAST UPDATED:
26/11/2004
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2004/1034.html