You are here:
AustLII >>
Databases >>
Victorian Civil and Administrative Tribunal >>
2022 >>
[2022] VCAT 895
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Context] [No Context] [Help]
Naqebullah v Victorian Building Authority (Review and Regulation) [2022] VCAT 895 (5 August 2022)
Last Updated: 5 August 2022
VICTORIAN CIVIL AND ADMINISTRATIVE
TRIBUNAL
ADMINISTRATIVE DIVISION
REVIEW AND REGULATION LIST
|
VCAT REFERENCE NO. Z669/2020
|
CATCHWORDS
|
Penalty review hearing – review of decision of the Internal Review
Manager of the Victoria Building Authority – Building Act 1993
(Vic); Building Regulations 2018 (Vic) – contravention of the
Act or Regulations – unprofessional conduct – negligent conduct
– non-compliance
with building permit – combustible cladding and
other fire safety breaches – appeal on penalties only – whether
suspension necessary – delay – culpability – consistency
between cases and admissibility of case snapshots –
good behaviour
post-investigation – avoidance of hardship – education and
supervision – sections 187(1)(c), 178, and 16(1) of the Building Act
1993 (Vic) – decision substituted.
|
APPLICANT
|
Obaid Naqebullah
|
RESPONDENT
|
Victorian Building Authority
|
WHERE HELD
|
Melbourne
|
BEFORE
|
Justice Quigley, President, and Member Clampett
|
HEARING TYPE
|
Penalty Hearing, via video conference
|
DATE OF HEARING
|
13 July 2022
|
DATE OF ORDER AND REASONS
|
5 August 2022
|
CITATION
|
Naqebullah v Victorian Building Authority (Review and Regulation) [2022]
VCAT 895
|
ORDERS
- Pursuant
to s 187(1)(c) of the Building Act 1993 (Vic), the decision of the
Internal Review Manager of the Victorian Building Authority dated 10 August 2020
is overturned and the
following decision is substituted in its place.
- On
Grounds 1, 7 and 8:
(a) The Applicant is reprimanded;
(b) The Applicant is fined a sum of $18,000;
(c) Within 18 months of the date of these Orders, the Applicant must complete an
accredited education course in the subject of ‘identifying
and applying
legal and ethical requirements including compliance with building permits’
(or similar), and that course must
be approved by the Victorian Building
Authority; and
(d) For a period of 12 months following the date of these Orders, the Applicant
must personally attend on site at all Mandatory Inspections
listed on the
Building Permit for all of the building projects conducted by Shangri-La
Construction Pty Ltd or any other business
at which the Applicant is the
responsible permit holder, to the satisfaction of the Victorian Building
Authority.
- On
Ground 2:
(a) The Applicant is reprimanded;
(b) The Applicant is fined a sum of $7,000 (cumulative with Order 2(b));
(c) Within 18 months of the date of these Orders, the Applicant must complete an
accredited education course in the subject of ‘identifying
and applying
legal and ethical requirements including compliance with building permits’
(or similar), and that course must
be approved by the Victorian Building
Authority (concurrent with Order 2(c)); and
(d) For a period of 12 months following the date of these Orders, the Applicant
must personally attend on site at all Mandatory Inspections
listed on the
Building Permit for all of the building projects conducted by Shangri-La
Construction Pty Ltd or any other business
at which the Applicant is the
responsible permit holder, to the satisfaction of the Victorian Building
Authority (concurrent with
Order 2(d)).
- On
Ground 6 – No additional action.
- In
the event that no appropriate education course is sourced within 18 months in
order to fulfil the requirement in Orders 2(c) and
3(c), the parties have
liberty to apply to the Tribunal to vary these Orders.
Justice Michelle Quigley President
|
John Clampett Member
|
APPEARANCES:
|
|
For Applicant
|
Dr Wolff of Counsel
|
For Respondent
|
Ms Brady of Counsel
|
REASONS
INTRODUCTION
- These
proceedings relate to building practitioner misconduct at a building site in
2012. Mr Obaid Naqebullah (the Applicant) is a registered builder who was
responsible for ensuring his building company complied with the building permit
in relation to the
site. The Victorian Building Authority (VBA or the
Respondent) found the Applicant guilty of various disciplinary action
offences and imposed sanctions which the Applicant challenges.
- In
these proceedings, the Applicant, seeks review pursuant to s 186(1) of the
Building Act 1993 (Vic) (the Act) of the penalties decision of the
Internal Review Manager of the VBA to impose certain sanctions in respect of
building practitioner
misconduct.
- On
review, the Tribunal may affirm the decision, amend the decision or substitute
another decision.
- The
Applicant sought to rely on two affidavits which were sworn by his
solicitor[1] and which exhibited a
number of records of the VBA which were summaries extracted from the VBA’s
Prosecution and Disciplinary
Register located on the VBA’s website. The
affidavits were tendered subject to leave being granted. The admission and the
weight
to be given to this evidence is considered in the body of this
decision.[2]
BACKGROUND
- In
2008, the Applicant obtained registrations in the categories of domestic builder
(unlimited) and commercial builder (limited –
medium rise). He later
obtained a registration in the category of commercial builder (unlimited) in
2018.
- On
8 April 2008, Shangri-La Construction Pty Ltd (ABN 44 130 534 244)
(Shangri-La) was registered as a company, with the Applicant as a
director. Shangri-La originally had another director but this shareholder was
not a builder.
- In
or about November 2011, the Applicant was appointed as the responsible
registered builder for the construction of a residential
apartment building,
containing 81 dwellings and a basement carpark, at 3-7 Dixon Street and 6-8
Murray Street in Clayton (the project).
- On
24 November 2011, the Stage 1 Building Permit for the project was issued (BP
20112708/1). On 13 December 2011, the Stage 2 Building
Permit was issued (BP
20112708/2).
- Construction
work on the project occurred between approximately December 2011 and June 2013,
and on 21 June 2013 an occupancy permit
was issued.
- On
28 June 2013, the Applicant became the sole director and secretary of
Shangri-La.
- By
June 2017, the Owners Corporation of the project building had concerns about the
fire safety of the building. They organised for
the building to be inspected by
a registered fire engineer, Mr Stephen Kip of SKIP Consulting Pty Ltd. He
attended the property on
two occasions in that month. On 28 June 2017, Mr Kip
wrote to the Owners Corporation with his findings, highlighting several areas
of
fire safety non-compliance, including:
- 11.1 The
external cladding was combustible and not installed properly;
- 11.2 The
insulation in the external walls was combustible; and
- 11.3 The
plasterboard ceilings and the walls separating some apartments were not
installed in accordance with the manufacturers fire
test reports and were
therefore not adequately fire resistant.
- On
10 July 2017, the Owners Corporation provided Mr Kip’s letter to the
Municipal Building Surveyor (MBS) for the Monash City Council. Between
July and August 2017, the MBS attended the building for multiple inspections,
with either Mr
Kip or another fire engineer Dr Jonathan Barnett, resulting in a
statement being produced for the VBA. The MBS statement included
findings
that:
- 12.1 The
external cladding used was not the type of cladding approved on the building
permit documents – it was combustible
expanded polystyrene
(EPS);
- 12.2 The
structural steel columns did not meet the required standard because they had an
outer layer of EPS cladding;
- 12.3 The
external walls of sole occupancy units did not meet the required standard
because they had an outer layer of EPS cladding;
- 12.4 There were
points of ignition such as barbeques in range of the EPS cladding;
- 12.5 There was
no fire separation space between the top storey units and the ceilings below;
and
- 12.6 There was
no separation between the pump room and electrical room.
- The
MBS concluded that the building was not constructed in accordance with the
permits and the stamped blueprints and was not consistent
with the relevant fire
engineering report. The MBS formed the opinion that the occupants of the
building were at risk and issued
various emergency orders. These orders related
to security and avoidance measures and did not result in any evacuation
orders.
- On
21 March 2018, Dr Barnett provided a detailed report based on the findings of
the MBS investigation. The main conclusions of the
Barnett report were that the
construction issues may:
- 14.1 Allow the
spread of fire from one unit to other units; and
- 14.2 Cause
external walls, common walls or ceilings to collapse prior to occupants being
safely evacuated or during fire brigade intervention.
- A
consultant building practitioner, Mr Stuart McLennan, was contracted by the VBA.
On 2 May 2018, Mr McLennan produced a technical
report concluding that the risk
to the occupants and members of the fire service was “extreme”.
- On
3 July 2018, the VBA issued an initial allegations letter to the Applicant. The
Applicant was given an opportunity to respond to
the allegations and the VBA
conducted further investigations. On 8 November 2019, the VBA issued a Show
Cause Notice to the Applicant,
per s 182 of the Act – this set out 11
grounds on which the VBA proposed to take disciplinary action.
- Following
the show cause process, including oral and written submissions made by the
Applicant, on 26 May 2020 the VBA issued a Notice
of Decision (the Previous
Decision) finding 9 of the 11 grounds substantiated and imposing the
following penalties:
- 17.1 Reprimands;
- 17.2 $54,000 in
fines; and
- 17.3 A total
suspension of his registrations for 6 months.
- On
13 July 2020, the Applicant sought internal review of the Previous Decision, per
s 185(2) of the Act. The internal review process included the Applicant
providing a further written response and attending a meeting with
the Internal
Review Unit for oral submissions. In his submissions, the Applicant sought
reprimands and a smaller fine only.
- Following
the review process, the VBA Internal Review Manager issued a decision. The
Notice of Internal Review Decision (the Decision), dated 10 August 2020,
overturned the Previous Decision, reduced the guilty grounds to 6 grounds, and
imposed the following penalties:
- 19.1 Two
reprimands;
- 19.2 $20,000 in
fines; and
- 19.3 A total
suspension of his registrations for 3 months.
- A
detailed breakdown of the Decision is as follows:
Ground
|
Summary of Ground
|
Penalty
|
Ground 1
|
Mr Naqebullah contravened s 16(1) of the
Act[3] in that he
carried out building work that was not in accordance with the Act, the building
regulations and the building permit.
More particularly, Mr Naqebullah did so by substituting non-fire rated
expanded polystyrene (EPS) for fire rated Multiboard as an external
cladding material, where Multiboard was detailed for use by the permit.
|
Reprimand Penalty of $15,000
2 months suspension
|
Ground 7
|
Mr Naqebullah engaged in conduct in relation to his practice as a
registered commercial builder that was negligent in a particular
manner.
More particularly, Mr Naqebullah breached his duty as a registered builder
by failing to address any claimed conflict arising between
the building permit
and the specification documents by means of referring that conflict to the
registered building surveyor (RBS) for resolution.
|
Ground 8
|
Mr Naqebullah engaged in unprofessional conduct by performing
building work that used combustible EPS material in the construction of the
building’s external walls without
forming a reasoned basis as to why the
use of EPS met the performance requirements relevant to fire resistance under
the Building
Code of Australia (the BCA) and when such use was contrary
to the Act, the BCA, and the building permit.
|
Ground 2
s 179(1)(a)(i) of the Act
|
Mr Naqebullah contravened s 16(1) of the
Ac[t]44 As above.
by carrying out building work that was not in accordance with the Act, the
building regulations and the building permit.
More particularly, Mr Naqebullah did so by failing to install internal
fire-rated construction to non-loadbearing walls, loadbearing
walls and ceilings
of the building’s sole occupancy units and adjoining common areas in
accordance with the Act, building regulations
and permit issued in relation to
that work.
|
Reprimand
Penalty of $5,000
1 month suspension
|
Ground 6
s 179(1)(f)(ii) of the Act
|
Mr Naqebullah engaged in conduct in relation to his practice as a
commercial builder that was negligent in a particular manner.
More particularly, Mr Naqebullah breached his duty to ensure that the
building work the subject of Grounds 1 and 2 was carried out
in a manner that complied with the Act, building regulations and the building
permit, including by carrying out the
building work without considering,
properly or at all:
(i) that the (as-built) construction of the building would “significantly
compromise the safety of the building occupants”;
(ii) that such construction contravenes his obligation to construct the Building
according to the relevant permit and would contravene
requirements under the
Act and BCA (where Mr Naqebullah ought to have been aware of such
requirements) with the result that
he would not be acting in a competent manner
and to a competent standard in discharging his duties as a builder;
and
(iii) whether the construction of the building using EPS cladding was
contrary to the BCA, there being no evidence that an alternative
solution was
developed to show the satisfaction of relevant performance requirements under
the BCA.
|
No additional disciplinary action
|
Total: 2 reprimands; penalty of $20,000; and 3 months suspension of
registrations
|
- On
14 August 2020, the Applicant applied to the Tribunal for a review of the
Decision, pursuant to s 186(1) of the Act. Section 187(2)
functions to
automatically stay the operation of the decision until the Tribunal’s
review is finalised.
- The
final hearing was held on 13 July 2022.
THE APPLICABLE LAW
Legislative Framework
- The
relevant sections of the Act are contained in the following paragraphs.
- Section
179 sets out the grounds on which disciplinary action may be taken against a
registered building practitioner. It relevantly
provides:
(1) Each of the following is a ground for which disciplinary action may be
taken against a registered building practitioner—
(a) the practitioner has contravened—
(i) this Act or the regulations under this Act;
...
(b) the practitioner has engaged in unprofessional conduct or has failed to
comply with a code of conduct;
...
(f) the practitioner has engaged in conduct in relation to the practitioner's
practice as a building practitioner that is—
(i) constituted by a pattern of incompetence; or
(ii) negligent in a particular matter ...
- Section
16(1), as in force at the time of the conduct in question, provided:
(1) A person must not carry out building work unless a building permit in
respect of the work has been issued and is in force under
this Act and the work
is carried out in accordance with this Act, the building regulations and the
permit.
Penalty: 500 penalty units, in the case of a natural person.
- Section
178 sets out the types of disciplinary action that may be taken against a
practitioner where a disciplinary ground is made
out. It
provides:
In this Division, disciplinary
action in relation to a registered building
practitioner means one or more of the following—
(a) reprimand the practitioner;
(b) direct the practitioner—
(i) to do a specified thing, including to rectify or complete
specified building work; or
(ii) not to do a specified thing;
(c) require the practitioner to successfully complete a specified course of
training within a specified period;
(d) impose a penalty of not more than 150 penalty
units, in the case of a natural person, or 750 penalty units, in the case
of a body
corporate, unless—
(i) a charge has been filed in the Magistrates' Court in relation
to the matter; or
(ii) the matter has been dealt with by a court exercising its criminal
jurisdiction; or
(iii) the matter has been dealt with by the issue of an infringement
notice;
(e) vary a condition (other than a prescribed condition), or impose a
condition, on the practitioner's registration;
(f) suspend registration for not more than 3 years either wholly, or as
a partial suspension in relation to a specified matter;
(g) cancel registration;
(ga) disqualify the practitioner from being a nominee director of
a registered body corporate or a specified registered body
corporate
for a specified period not exceeding the period during which the
body corporate is registered;
(gb) in the case of a registered body corporate, disqualify
a registered building practitioner who is an officer of
the body corporate
from being a nominee director, or being otherwise
involved in the management, of the body corporate for a specified period not
exceeding
the period during which the body corporate is registered;
(h) disqualify the practitioner for a specified period of up to 3 years from
being registered in any category or class
of building
practitioner.
- The
value of a penalty unit is currently $181.74, therefore:
- 27.1 The maximum
of 150 penalty units referred to in s 178(d) is $27,261.
- 27.2 The maximum
of 500 penalty units referred to in s 16(1) is $90,870.
- On
review of a final decision of the VBA, s 187(1) of the Act allows the Tribunal
to affirm the decision, amend the decision, or substitute
another decision in
its place. This means that the Tribunal is conducting a de novo hearing
of the penalty issue in this case.
- The
whole of the Tribunal Book was tendered as evidence before the Tribunal without
objection and was relied upon variously by both
parties in their submissions to
the Tribunal.[5]
Established Case Principles
- Some
established principles can be drawn from other building practitioner
disciplinary proceedings as well as similarly conducted
disciplinary
proceedings, such as legal practitioner disciplinary proceedings.
- The
purpose of penalties imposed by the Tribunal in building practitioner
disciplinary proceedings is primarily protective consistent
with the purposes of
the Act. The Act’s core objectives in s 4(1) include “to protect
the safety and health of people who use buildings”.
- Whilst
this protective purpose is paramount, in discharging that duty, specific and
general deterrence are relevant considerations
– that is, deterring both
the offending practitioner and all other practitioners from similar conduct. To
properly give effect
to the principles of deterrence, “which serve the
protection of the public”, penalties must be seen to punish the
offender.[6]
- Further,
the Tribunal notes the observations in Cole-Sinclair v Building Practitioners
Board that the range of disciplinary sanctions available under the
Act “operate as a mechanism by which the purposes and objectives of the
Act are to be
maintained”.[7]
- There
are a range of factors that the Tribunal should consider in determining penalty,
including:
- 34.1 The nature
and seriousness of the conduct and the risk of harm if it were engaged in by
others;
- 34.2 Specific
and general deterrence;
- 34.3 Any delay
from the time the investigation started to the end of the Tribunal hearing;
and
- 34.4 Evidence of
character and community
contributions.[8]
- The
nature or seriousness of the misconduct or the severity of the breach at issue
is a highly relevant consideration. The seriousness
of the misconduct or breach
can be measured in multiple ways, including by considering:
- 35.1 Whether or
not the conduct constituted an offence under the Act or the
Regulations;[9]
- 35.2 The
potential for serious consequences to flow from the conduct, whether or not such
consequences actually
eventuated;[10]
- 35.3 How
important the exercise of a particular statutory function or compliance with a
particular statutory obligation is to the
maintenance of the Act’s
specific objectives;[11] and
- 35.4 Whether
the conduct arose from (a) dishonesty or an ulterior motive for personal gain
(which is not alleged here); or (b) a professional
failing or serious mistake
made in the conduct of building
activities.[12]
- It
is well established, and evident in cases such as Stirling v Legal Services
Commissioner
(Stirling),[13]
that whilst disciplinary proceedings are not criminal in nature, criminal
sentencing principles apply by analogy. In addition to
community protection and
principles of deterrence, the principles weighing in favour of stringent
penalties include denunciation
and just punishment. The principles that can be
classified as mitigatory include rehabilitation, remorse, delay, personal
character
and circumstances, financial impact and mental
illness.[14]
- The
relevance of consistency or parity between cases was described by Member
Wentworth in Victorian Legal Services Commissioner v O’Brien (No
2):
Orders made in any comparable cases may be a useful guide
to proportionality, and parity is important, but every case necessarily
involves
a different combination of factors. The nature of the offending conduct and its
duration, the particular circumstances of
the practitioner, the context of the
offending, and the assessed risk of repetition are all factors which will rarely
be identical
in any two
cases.[15]
CONTENTIONS OF THE PARTIES
The Applicant
- The
Applicant’s primary contention on review was to avoid any suspension of
his registrations on the basis that such a penalty
was excessive. He also sought
that the reprimands be reduced to one reprimand (instead of two) and that the
total fines be reduced
to $10,000.
- The
Applicant pointed to his “clean history” and submitted that the
disciplinary action imposed by the Decision is “punitive”
and
“harsh and excessive”, in that:
- 39.1 Whilst the
Applicant accepts legal responsibility and shows remorse, his moral culpability
was not at the highest level –
this included raising the fact that in 2012
when the building was constructed the dangers of EPS cladding were not
known;
- 39.2 A
suspension is not consistent with disciplinary action taken against other
building practitioners – this raised a question
of the admissibility and
relevance of the snapshots of cases listed on the Prosecution and Disciplinary
Register of the VBA website,
which the Applicant sought leave to tender;
- 39.3 A
suspension would have financial and reputational consequences for both the
Applicant and third parties which would be unfair
and unreasonable on a balance
of all the circumstances; and
- 39.4 A
suspension amounts to an unreasonably punitive punishment, where the primary
purpose of the Act is a protective one.
The Respondent
- The
VBA submitted that the penalties imposed by the Decision were the minimum
required to serve the purposes of the Act and should
be affirmed.
- The
VBA contended that the culpability of the Applicant could not be reduced
materially, if at all. The VBA submitted that the Applicant’s
role as the
registered building practitioner and permit holder for the project attracted
ultimate responsibility for the offending
conduct. The VBA emphasised the fact
that, regardless of the importance to be placed on the use of combustible
cladding, the Applicant
had ultimately breached his fundamental duty to adhere
to the building permit – this was serious conduct.
- The
VBA objected to the admissibility of the case snapshots from the VBA website.
The VBA said that these summaries could not be relied
upon to demonstrate
consistency in disciplinary action between practitioners, because they were
devoid of any meaningful detail and
thus no sufficient comparisons could be
drawn.
- The
VBA pointed to the fact that the Applicant had not provided any evidence
supporting his contentions about the financial and business
consequences of a
suspension for himself and third parties such as employees and contractors. The
VBA conceded that delay had some
relevance in this case but was not materially
unfair to the Applicant, particularly due to the stay of the operation of the
Decision.
- The
VBA contended that a suspension was proportionate to the gravity of the conduct.
The VBA emphasised the importance of protecting
the community from further risk
and deterring others from repeating this kind of serious misconduct, which they
contended is a necessary
extension of the protective purposes of the Act.
- Whilst
general deterrence was in contention in this case, the parties were in agreement
that specific deterrence was not a relevant
consideration.
ANALYSIS AND FINDINGS
- The
relevant issues will be addressed according to the topics raised by the
Applicant and summarised at paragraph [39] above.
Culpability
- There
were two main aspects of culpability at issue in this case. The first related to
the role of the Applicant as the registered
building practitioner for the
project and the level of responsibility and liability conferred on him by that
role.
- The
second issue concerned the use of combustible cladding materials in building
sites constructed in the 2010s (resulting in the
Victorian Cladding Taskforce
being established in 2017 and the ban on combustible cladding effective in this
state from February
2021), and the relationship between that environment and the
timing of the Applicant’s conduct.
Role of the Applicant in the Conduct
- The
Tribunal agrees with the VBA that the Applicant’s role as the registered
building practitioner and permit holder for the
project attracts liability and
ultimate responsibility for the offending conduct. It follows that the legal
responsibility of the
Applicant cannot be disputed or reduced. The Applicant did
not contest liability and the review is on penalties alone.
- However,
the level of moral culpability that should be attributed to the Applicant must
be assessed for the purposes of determining
the appropriate penalty. As noted
above at [35], whether the conduct arose from (a) dishonesty or an ulterior
motive for personal
gain or (b) a professional failing or serious mistake, is an
important consideration.[16] In the
present case, the Applicant is not alleged to have acted for dishonest purposes
and this is consistent with his submissions.
Rather, the conduct is in the
category of falling below the standard of conduct required by reason of his
negligence and error.
- As
in the criminal jurisdiction, professional offending which falls into the
categories of intentional versus reckless or negligent
conduct should be
accorded different levels of culpability and gravity. The mistakes of the
Applicant in not properly supervising
and checking the work of the employees,
contractors, and other persons assigned to the project represent a serious
failure to discharge
the duties of a building practitioner conferred generally
under the Act and particularly upon the grant of a permit. His role and
his
culpability should be assessed on that basis. However, they should also be
assessed according to the reckless or negligent nature
of the conduct, showing
recognition for the absence of
dishonesty.[17]
- Further,
weight should be given to the fact that the contraventions for which the
Applicant has been found guilty relate in particular
to non-compliance with the
building permit. Compliance with permits is an essential pillar of the
regulation of the building industry.
Failures to adhere to critical requirements
of the industry, particularly where those requirements represent a safeguard for
the
protection of the public, should be taken very
seriously.[18] It is important to
ensure that message is conveyed to the community in penalising the Applicant.
This aspect, as well as the fact
that two of the grounds are s 16 offences,
demonstrates the gravity of the Applicant’s failures regarding
professional supervision
and
conduct.[19] The culpability of the
Applicant must be metered against the considerations of community perception and
protection.
The Significance of Combustible Cladding Issues: 2012 to
Now
- Submissions
were made on behalf of the Applicant that the fact that the building was
constructed in or about 2012, well before the
building industry and the public
became aware of the risks of EPS and other types of combustible cladding, was a
mitigating factor.
- It
was submitted that the danger of combustible cladding became a public issue in
late 2014, with the particularly notable fire incident
at the Lacrosse building
in Docklands.[20] The Victorian
Cladding Taskforce became active in early 2017, and the ban on combustible
cladding in Victoria did not come into effect
until February 2021. In that time
period, the discovery of various buildings which were constructed with
combustible cladding was
covered significantly in the media, and the building
industry was involved in the investigations and consultations that took
place.
- The
Tribunal agrees that the ubiquity of knowledge in the community may be a
mitigating factor, however it is not a significant one
overall in the current
context.
- What
ultimately should be noted is that the Applicant should have foreseen the
potential for serious consequences to arise as a result
of not ensuring
adherence to the permit.[21] This
contextualises the culpability of the Applicant in terms of the core standard at
issue.
Consistency
- Consistency
between penalties imposed on building practitioners, by reference to various
case samples, was a significant issue at
the hearing.
Admissibility of Case Snapshots from the VBA Disciplinary
Register
- The
Applicant filed two affidavits with the Tribunal on 12 July 2022, the day before
the hearing, containing various case snapshots
from the Prosecution and
Disciplinary Register section of the VBA website. The Applicant sought leave for
these affidavits to be
tendered into evidence so he could rely on the case
samples to demonstrate the rare occurrence of the VBA imposing suspension as
a
penalty, even in building practitioner disciplinary actions involving
combustible cladding.
- As
aforementioned, the VBA objected to the admissibility of these case summaries.
Whilst the Tribunal agrees with the VBA that the
case snapshots are very basic
and do not provide the level of detail that would be present in the decision of
a court or tribunal
in order to establish a precedent, the Tribunal is of the
view that the case snapshots are of some utility and relevance. The case
snapshots cannot be used to specify what exact penalties should be imposed in
any specific circumstance, however they do demonstrate
a general pattern of the
nature of the disciplinary dispositions most commonly utilised by the VBA.
- An
inference can be drawn, based on the case summaries, that the VBA does not
regularly impose suspensions, and that the most common
penalties are reprimands
and fines with an occasional emphasis on conditional or supervisory terms on a
practitioner’s registrations.
The Tribunal concludes that the case samples
are admissible, but only to the extent that the relevance and weight of the
cases are
limited to findings based on that
inference.[22]
Relevance and Weight of Consistency Issues
- The
Tribunal is of the view that there should be some weight attached to the
snapshot evidence of the lack of suspensions being imposed
by the VBA. The
Tribunal is of the view that this factor can be considered, alongside the many
factors that the Tribunal should consider
in determining the appropriate
penalty. It should be given some weight but there are other considerations which
ought to be taken
into account for or against suspension.
Consequences of a Suspension and Related
Considerations
- In
determining whether a suspension should be amongst the penalties imposed, the
relevant factors for the Tribunal to consider are
as follows:
- 62.1 The
financial and reputational consequences for the Applicant and third
parties;
- 62.2 The
professional history of the Applicant, including his performance since the
present investigation up to the date of the hearing;
and
- 62.3 Delay as a
general consideration.
Financial and Reputational Consequences
- The
Applicant runs an established building company, which evidently has the capacity
to attract significant construction projects.
Shangri-La employs 25 staff with a
cited turnover of between 30 and 50 million dollars per annum. For the
Applicant, establishing
the company was part of establishing a life in
Australia, following a difficult refugee migration from Afghanistan.
- The
Applicant contended that the flow-on consequences for his business, if his
registrations were suspended, would be drastic to the
extent that the company
would likely collapse. His reputation would be damaged to the extent that his
ability to obtain tenders for
projects would be significantly hindered.
- The
Applicant stressed that, during the period of the suspension, he would have no
employee qualified as a registered builder and
therefore no one to take over
responsibility for building permits. This would mean that all projects would
need to be paused for
the duration of the suspension, resulting in disputes with
existing clients and a hiatus of business that would be difficult to come
back
from.
- Whilst
the above matters would clearly have financial and reputational consequences for
the Applicant, the Tribunal agrees with the
VBA that the extent of these
consequences is difficult to gauge when the Applicant has not provided any
specific documentation in
support of the contention. However, balanced against
this is the fact it is difficult to provide documents outlining hypothetical
or
predicted consequences. Ultimately, the Tribunal can give some, but not
significant, weight to this factor.
Professional History of the Applicant
- The
Tribunal accepts that the Applicant has no previous disciplinary history prior
to the present offending and has run a successful
construction company over a
period of 14 years.
- As
there has been no further disciplinary action, the Tribunal can be reasonably
satisfied that some steps have been taken to ensure
greater care and attention
to detail. The Applicant has evidently learned from his mistakes and appears,
from the information before
the Tribunal, to have avoided any repetition of the
offending behaviour. The passage of five years since the defects in the building
were detected provides an ample period over which to assess the
Applicant’s progress. During that time, the Applicant has been
subject to
increased scrutiny by the VBA, who have checked the compliance of the
Applicant’s other construction projects over
the years without any
negative findings.
- In
professional disciplinary proceedings, courts and tribunals are
“obliged to take into account” an offending
practitioner’s failure to see the error of their
ways.[23] The other side of that
coin is that the Tribunal should give significant weight to the
Applicant’s demonstrated insight and
ability to rehabilitate his
behaviour. However, given the serious nature of the charged conduct, the
Tribunal is of the view that
a further period of scrutiny in the form of
supervision and training is required in order to solidify the Applicant’s
rehabilitation
(discussed further below at [84] to [86]).
Delay
- Whilst
the Tribunal agrees with the VBA that the delay in these proceedings has not
resulted in substantial unfairness to the Applicant
because of the operation of
the stay, the Tribunal is of the view that delay would have caused significant
distress to the Applicant.
It would be difficult for the Applicant to operate
his company on a day to day basis with no certainty as to that company’s
future.
- Delay
should be assessed from the time the investigation into the conduct
commenced.[24] It has been 5 years
since the issues were detected, and 2 years since the proceeding was initiated
with the Tribunal. This is not
an insignificant period, and therefore delay
should be given a moderate degree of weight in determining the appropriate
penalties.
Punitive versus Protective
- As
already stated, a strong theme in professional disciplinary proceedings is the
concept of punishing in order to
protect.[25] Ultimately, the task
before the Tribunal is to balance all of the above considerations against the
protective purpose of the Act
and the disciplinary process. The intended result
of that balancing exercise is clarity as to where the case at hand falls on the
punishment-protection scale.
Principles of Deterrence
- We
accept the proposition, set out in the cases of Thomas v Victorian Building
Authority and Quinn v Law Institute of Victoria Limited, that in
professional disciplinary proceedings discharging the protective sentencing
purpose requires a consideration of general
and specific
deterrence.[26] However, the inquiry
does not stop there – the level of relevance of these principles will vary
on a case by case basis.
- As
the parties have agreed that specific deterrence is not relevant in the present
case, there is no need to discuss that principle
in detail. It should be noted
that this is not a situation where the Applicant lacks insight or remorse which
would generally increase
the relevance of specific
deterrence.[27] Further, it is
accepted that the stress of the present proceedings and the related civil
proceedings in the Supreme Court would have
some deterrent effect on the
Applicant.
- Regarding
general deterrence, the factors which must be considered are more extensive.
Whilst the Tribunal has discussed how the timing
of the conduct in the context
of the public awareness of combustible cladding issues relates to the
Applicant’s culpability
(see above at [53] to [56]), there is more to be
said about the combustible cladding epidemic.
- Some
of the comments and findings made by the Victorian Cladding Taskforce in its
interim report delivered in November 2017 are relevant.
Not only do these
findings pertain to cladding, there were many findings relating to compliance
with standards and permits in the
building industry generally. Examples of these
findings include:
- 76.1 The
Taskforce was confronted with considerable and widespread concern at the level
of non-compliance with Victorian building
and construction regulations beyond
cladding; and
- 76.2 That deeper
issues of non-compliance in the building industry were significant contributing
factors to cladding
issues.[28]
- These
observations are important in analysing issues pertaining to general deterrence.
The findings by the Taskforce represent the
nexus between cladding issues and
the core issue in this matter – compliance with permits, the Act and the
Regulations. There
is certainly a need in the present case to send a message to
the community that these fundamental aspects of compliance must be adhered
to.
- As
stated by Member Eastman in Valentine v Victorian Building Authority, a
breach of building compliance laws:
...requires a penalty which
not only signifies the seriousness of the breaches of the Building Act and the
DBC Act, but which serves to ensure other members of the profession strictly
follow the requirements of the Act, signalling
this type of conduct will not be
tolerated, and which also has regard to the interests of maintaining
professional standards and
public confidence in the
profession.[29]
- Overall,
general deterrence is something that the Tribunal must have serious regard to in
this case. Deterrence ultimately achieves
a protective rather than punitive
end.[30]
Nature of Suspension
- A
suspension is a punitive penalty. Whilst a suspension may have some incidental
rehabilitative effect because of the lessons that
one would most likely learn
from being suspended, its purpose is to punish.
- It
should be noted that the type of suspension available in the present case is
discretionary, and it is so for a reason. The Applicant
in the present case has
not committed the kind of offending that would attract an immediate suspension,
which can be imposed by the
VBA where the offending practitioner appears not to
be fit and proper and where it is in the public
interest.[31] That kind of offending
sets the bar against which less serious conduct, such as that in the present
case (noting the various issues
discussed above between [47] and [56]), should
be judged. At some point, the need for a suspension falls away.
- In
Victorian Building Authority v Tsaganas, the Court of Appeal summarised
the inquiry as follows:
When, as in the present case, the
remedies imposed may include fines, orders for costs, requirements for ongoing
supervision and requirements
for further training, the decision-maker may
consider whether the purpose of specific deterrence and adequate protection of
the community
by way of deterrence and re-education will be adequately served by
the imposition of a conditional suspension or not. A judgment
of fact and degree
will have to be made as to whether in all the circumstances a conditional
transition back into the profession
is appropriate or
not.[32]
- On
a balance of all the matters before this Tribunal, for the reasons discussed
above, the Tribunal is of the view that the ultimate
penalty in the present case
does not need to be a significantly punitive one.
Importance of Supervision and Education
- Whilst
the issue of training and education was not promoted as a sentencing option by
the parties, the Tribunal is of the view that
in the present case supervision
and education would better serve the protective purposes of the Act than a
suspension. Being subject
to further checks and balances, whilst being able to
continue to operate his company, would ensure that the Applicant’s
interests
and those of the community are both served.
- In
the context of legal practitioner proceedings, the Court of Appeal in Quinn
discussed this issue. Maxwell P stated as follows:
...the
Tribunal’s protective function is paramount. Thus, where there is a choice
of sanctions, it is to be expected that the
Tribunal will choose that sanction
which maximises the protection of the public... [T]he imposition of a continuing
obligation...
would seem likely to afford considerably greater protection to the
public than a period of
suspension.[33]
- In
the view of the Tribunal, the imposition of supervision and education conditions
would also sit more squarely within the current
sentencing climate in building
practitioner disciplinary proceedings, as demonstrated by the above findings
regarding the rare use
of suspension in comparable cases (see above at [60]). It
could be said that the modern approach is one which encourages the longevity
of
a skilled and educated workforce, with the ultimate goal of future
compliance.
Penalty
- The
Tribunal agrees with the VBA that this case represents a serious failure by a
builder practitioner to comply with the conditions
of the relevant building
permit and the Act. However, the Tribunal is of the opinion that the gravity of
the offending conduct can
be reflected in an alternative penalty which
represents both punitive and rehabilitative considerations.
- Ultimately,
the Tribunal finds that a suspension is not necessary in this case, as the
principles applicable to this disciplinary
proceeding can be served by
alternative education and supervision conditions. The education and supervision
conditions should go
to the heart of the issue underlying the offending conduct
– ethical and compliant building practices.
- The
Applicant will be required to undertake an accredited education course in the
subject of ‘identifying and applying legal
and ethical requirements
including compliance with building permits’ (or similar), and that course
must be approved by the
VBA.[34] The
Applicant will also be required to personally attend on site at all Mandatory
Inspections listed on the Building Permit for all
of the building projects
conducted by Shangri-La Construction Pty Ltd or any other business at which the
Applicant is the responsible
permit holder, for a period of 12
months.[35]
- The
Tribunal is of the view, however, that the
reprimands[36] should remain as is,
and the fine[37] should be increased
slightly to account for some of the loss in punitive effect that results from
the removal of the suspension.
- The
Tribunal sees no reason to change the grouping of the Grounds of the conduct,
which were grouped in the Decision according to
the offences relating to the
cladding and the offences relating to the walls/ceilings. However, the penalties
imposed in the Decision
are to be substituted with the penalties outlined in the
Orders at the commencement of these reasons.
Conclusion
- The
Applicant neglected his duties as a building practitioner, and the results of
that neglect created a serious risk to members of
the public. However, the
Applicant has admitted his liability and, since the offending conduct occurred,
the Tribunal has not been
made aware of further complaint.
- The
passage of time since the period in which the issues in this proceeding arose
has demonstrated several things. It has revealed
a serious epidemic in the use
of combustible cladding in Victoria; it has revealed the less than acceptable
responses and adherence
to professional practice of some building practitioners
to that event; and it has revealed a transitioning from punitive to educative
strategies for practitioner rehabilitation in a manner which honours the
purposes and objectives of the Act. These matters give the
Tribunal confidence
that the Applicant can be trusted to maintain his registration, albeit subject
to specific training conditions,
appropriate admonition, and financial penalty.
Justice Michelle Quigley
President
John
Clampett
Member
[1] Affidavit of Daniel John Prior
and Further Affidavit of Daniel John Prior both sworn 12 July 2022 and marked
Exhibits A-2 and A-3
respectively.
[2] See below at paragraphs [58] to
[61].
[3] Note: The Show Cause Notice
should refer to s 16(1) rather than s 16(2) of the Act. At the relevant time,
the Act did not contain
a s 16(2), which was the result of later amendments.
However, at the relevant time, s 16(1) was in materially identical terms to
s
16(2) as it exists under the current Act.
[t]
[5] Tribunal Book was tendered as
Exhibit A-1
[6] Thomas v Victorian Building
Authority
[2020] VSC 150
, [62] (‘Thomas’); see also,
Quinn v Law Institute of Victoria Limited [2007] VSCA 122, [30]
(‘Quinn’).
[7] [2014] VCAT 1212, [16].
[8] Ibid, [18].
[9] Ibid, [21].
[10] See, e.g., Farag v
Building Practitioners Board [2015] VCAT 939 (‘Farag’),
[15]-[16] and [27]; and Stanbury v Victorian Building Authority [2021]
VCAT 297, [20] (‘Stanbury’).
[11] See, e.g. Valentine v
Victorian Building Authority [2021] VCAT 412, [24]-[27]
(‘Valentine’); and Cole-Sinclair v Building Practitioners
Board [2014] VCAT 1212, [27] (‘Cole-Sinclair’).
[12] Farag, above n 10,
[28]-[32].
[13] [2013] VSCA 374
(‘Stirling’).
[14] Ibid, [57]-[113].
[15] [2016] VCAT 1797, [25].
[16] Farag, above n 10,
[28]-[32].
[17] Contrast with the
seriousness to be attributed to dishonest conduct, see e.g. Valentine,
above n 11, [30].
[18] Valentine, above n
11, [26].
[19] Ibid, [24]-[27]; and
Cole-Sinclair, above n 11, [27].
[20] It was also noted that the
infamous and deadly Grenfell Tower fire tragedy had occurred in London in 2017,
attracting global attention.
[21] Farag, above n 10,
[15]-[16] and [27]; and Stanbury, above n 10, [20]
[22] It should be noted that
whilst the rules of evidence do not formally apply in these proceedings, where
the subject matter is a serious
one, as is the case here, serious consideration
should be given to the relevance and probative value of items sought to be
tendered,
and it is in that sense that admissibility is assessed.
[23] Hannebury v Legal
Ombudsman [1998] VSCA 142, [22].
[24] Valentine, above n
11, [18].
[25] Thomas, above n 6,
[62]; Quinn, above n 6, [30].
[26] Ibid.
[27] See e.g. Valentine,
above n 11, [37]; Stirling, above n 13, [60]; and Brott v Legal
Services Commissioner [2008] VCAT 2399, [49], [67].
[28] ‘Interim
Report’, Victorian Cladding Taskforce, November 2017.
[29] Valentine, above n
11, [40].
[30] Thomas, above n 6,
[61].
[31] Building Act 1993
(Vic), s 180.
[32] [2017] VSCA 248, [40].
[33] Quinn, above n 6,
[31]-[32].
[34] Building Act 1993
(Vic), s 178(c)
[35] Ibid, s 178(b)(i).
[36] Ibid, s 178(a).
[37] Ibid, s 178(d).
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/vic/VCAT/2022/895.html