You are here:
AustLII >>
Databases >>
State Administrative Tribunal of Western Australia >>
2022 >>
[2022] WASAT 79
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Context] [No Context] [Help]
FAQIRI and A & M CONSTRUCTION GROUP PTY LTD [2022] WASAT 79 (5 September 2022)
Last Updated: 6 September 2022

JURISDICTION : STATE ADMINISTRATIVE
TRIBUNAL
ACT :
BUILDING SERVICES (COMPLAINT RESOLUTION AND ADMINISTRATION) ACT
2011
(WA)
CITATION : FAQIRI and A & M CONSTRUCTION GROUP PTY LTD [2022]
WASAT 79
MEMBER : MS V HAIGH, MEMBER
MR R AFFLECK, SENIOR SESSIONAL MEMBER
HEARD : 15 AND 16 DECEMBER 2021 AND 17 JUNE 2022
DELIVERED : 5 SEPTEMBER 2022
FILE NO/S : CC 173 of 2022
CC 1233 of 2020
CC 1572 of 2020
BETWEEN : FATIMA FAQIRI
First Applicant
HAFIZULLAH FAQIRI
Second Applicant
AND
A & M CONSTRUCTION GROUP PTY LTD
Respondent

Building service complaint - Building remedy
order - Whether work has not been carried out in a proper and proficient manner
or is
faulty or unsatisfactory - Monetary order sought by owner - Compensation -
Failure to mitigate loss
Legislation:
Building Act 2011 (WA), s
3
Building Services (Complaint Resolution and Administration) Act 2011
(WA),
s 3
,
s 5(1)
,
s 7(1)
,
s 9(1)
,
s 10
,
s 11(1)(d)
, s 36(1),
s 36(2)
,
s 38(1)(a)
,
s 38(1)(b) 
Result:
CC 1233 of 2020 and CC 1572 of 2020
Applications
partly successful
CC 173 of 2022
Application partly successful in relation
to one item
Category: B
Representation:
Counsel:
First Applicant
|
:
|
In Person
|
Second Applicant
|
:
|
In Person
|
Respondent
|
:
|
Mr A Searle
|
Solicitors:
First Applicant
|
:
|
N/A
|
Second Applicant
|
:
|
N/A
|
Respondent
|
:
|
Searle Construction Lawyers
|
Case(s) referred to in decision(s):
Bellgrove v Eldridge [1954] HCA 36;
(1954) 90 CLR 613
Diploma Construction (WA) Pty Ltd v South Central WA Pty Ltd
[2015] WASC 289
Gemmill Homes Pty Ltd v Sanders [2018] WASC 179
Hippydayze Pty Ltd and Mener Group Pty Ltd [2019] WASAT 92
Jennings and Howitt [2019] WASAT 133
Lewis and Waco Pty Ltd [2016] WASAT 127
Nelson v Mardesic (1998) 22 SR (WA) 42
Owners of Strata Plan 59377 and Carine Homes Pty Ltd
[2014] WASAT 39
Total Investments Pty Ltd and Rapley Wilkinson Pty Ltd
[2015] WASAT 29
Waldron and Afra Construction Pty Ltd [2013] WASAT 207
REASONS
FOR DECISION OF THE TRIBUNAL:
Introduction
- Mr
Hafizullah Faqiri and Mrs Fatima Faqiri (owners) engaged
A & M Construction Group Proprietary Limited (builder) of
which Mr Amjad Umer Menom is the director, to build their double storey
brick and tile home (Dwelling) at 9 Jeffrey Street Kewdale.
- The
Home Building Works Contract was signed on 7 September 2018 for a total sum of
$540,000
(Contract).[1]
- The
building work commenced on 20 October 2018 and was completed (aside from the
matters the subject of this dispute) on 11 December
2019.
- It
is not in dispute that the owners supplied the designs and plans for the
Dwelling.
- The
owners lodged three building service complaints with the Building Commissioner
comprising 84 items.
CC 1233 of 2020 (BC 2020 - 670) - the first proceeding
- On
16 May 2020 the owners lodged a building service complaint (Complaint 1)
under
s 5(1)
of the
Building Services (Complaint Resolution and
Administration) Act 2011
(WA) (Act). Complaint 1 relates to 77 items
affecting the whole dwelling ranging from cracks through the cornices to issues
with the roof.
- Given
that the proposed remedial work is likely to exceed $100,000 the Building
Commissioner referred the Complaint 1 to the Tribunal
(pursuant to
bsraaa2011583
/s11.html" class="autolink_findacts">s 11(1)(d) of
the Act).
CC 1572 of 2020 (BC 2020 - 1958) - the second proceeding
- On
11 October 2020, the owners lodged a building service complaint (Complaint
2) under
s 5(1)
of the Act. Complaint 2 relates to four items being the
slab at the backyard fence, a water closet (WC), the kitchen bench being
the incorrect height in the alfresco area outdoors, and a pet wash bath not
being connected to plumbing.
- The
Building Commissioner referred Complaint 2 to the Tribunal (pursuant to
s
11(1)(d)
of the Act) as an associated matter was currently being heard by the
Tribunal, and because it would assist Complaint 2 to have it
heard concurrently
with the associated matter.
CC 173 of 2022 (BC 2022 - 176) - the third proceeding
- Subsequently,
on 16 January 2022, and after the above two proceedings had been part
heard, the owners lodged a building service complaint
(Complaint 3) under
s 5
(1) of the Act. Complaint 3 relates to three items of complaint concerning
the ceiling in the kitchen, garage, study and the soffit
lining around the
outside of the house (Item 1), unsatisfactory brickworks to the zero
locked garage wall (Item 2), upper floor ceiling water staining in
eaves, around balcony, on top of the staircase, and in the cedar wood lining in
the balcony
(Item 3).
- The
Building Commissioner referred Complaint 3 to the Tribunal (pursuant to
s
11(1)(d)
of the Act).
- The
Tribunal made orders that the three proceedings are to remain as separate
proceedings but be heard and determined together and
that evidence in one
proceeding is to be evidence in the other proceeding.
The issues for determination
- The
issues to be determined are:
- Were
the building works (items of complaint) carried out by the builder in a manner
that is not proper and proficient or is faulty
or unsatisfactory?
- If
the answer to 1) is in the affirmative, what is the appropriate form of the
building remedy order (BRO) (if any) in respect of the complaint
items?
- If
any of the building works were carried out in a manner that is not proper and
proficient or is faulty or unsatisfactory are the
owners entitled to any
compensation?
Statutory framework
-
Section
5(1)
of the Act relevantly provides that a person may make a complaint to the
Building Commissioner about a regulated building service
not being carried out
in a proper and proficient manner or being faulty or unsatisfactory. A
complaint made under
s 5(1)
of the Act is defined in
s 3
of the Act as a
'building service complaint'.
- A
'regulated building service' is defined in
s 3
of the Act to be a building
service carried out by a registered building service provider. Relevantly a
'building service' includes
'building work' as defined in s 3 of the Building
Act 2011 (WA) being the construction, assembly or placement of a building or
an incidental structure.
- Having
accepted a regulated building service complaint (s 7(1) of the Act), the
Building Commissioner is required to cause an investigation to be carried out
and, after having regard to any report
given under s 10 of the Act, may refer
the complaint to the Tribunal for it to deal with under s 38 of the Act (s 3, s
9(1) and s 11(1) of the Act).
- Where
a building service complaint is referred to the Tribunal by the Building
Commissioner under s 11(d) of the Act, s 38(1)(a) of the Act enables the
Tribunal to make a BRO where it is satisfied that the regulated building service
is carried out in a manner
that is not proper and proficient or is faulty or
unsatisfactory. The Tribunal may otherwise decline to make a BRO under s
38(1)(b) of the Act.
- The
standard of 'proper and proficient' is higher standard of care than 'proper and
workmanlike manner' or the reasonable care and
skill of a tradesman or
contractor.[2]
- The
building contract may be relevant as to what is proper and proficient as it
'defines what the builder was required to do, which
informs the issue of
workmanship'.[3]
- The
phrase 'not been carried out in a proper and proficient manner or is faulty or
unsatisfactory' is a broad expression apt to cover
a wide range of deficiencies
in the construction of a building which can be taken into
account.[4]
- A
mere departure by a builder from its contractual obligations is insufficient to
establish the work was not carried out in a proper
and proficient manner or was
faulty or
unsatisfactory.[5]
- Under
s 36(1) of the Act, a BRO made by the Tribunal may require a person who carried
out a regulated building service to do one or more of the
following:
- remedy
the building service as specified in the BRO;
- pay
to an aggrieved person such costs of remedying the building service as the
Tribunal considers reasonable and specifies in the
BRO; and/or
- pay
an aggrieved person a sum of money specified in the BRO to compensate the
aggrieved person for the failure to carry out the building
service in a proper
and proficient manner or for faulty or unsatisfactory building work.
- A
BRO may require that the order be complied with within a timeframe specified in
the BRO: s 36(2) of the Act.
Procedural history and evidence
- The
hearing of the first two proceedings commenced on 15 December 2021 for two
days. Both parties were represented on these days
of the hearing.
- When
the hearing resumed on 17 June 2022 the owners were unrepresented, their
solicitors having ceased to act for them on 24 January
2022.
- Further,
when the hearing of the first two proceedings resumed on 17 June 2022, the
hearing of the third proceeding commenced.
- The
documentary evidence in respect of the three proceedings comprises:
- the hearing book
(HB) for the first two proceedings comprising 619 pages (excepting pages
417-464 which comprise the site inspection report of the Building
and Energy
Inspector (BEI) dated 27 August
2020);[6]
- a supplementary
short summary of evidence - Mrs Faqiri dated 7 December
2021;[7]
- a short summary
of evidence - Mr Memon dated 7 December
2021;[8]
- building
permit dated 31 October 2018 with
appendices;[9]
- owners'
(applicants') amended complaint
schedule;[10]
- pages 417-463 of
the HB for the first two proceedings being the site inspection report of the BEI
dated 27 August
2020;[11]
- screenshots of
texts between Mrs Faqiri and the builder and screenshots of
photographs;[12]
- photographs
taken on 30 June 2021 by the
owners;[13]
- email dated 19
February 2021 from the builder with attached complaint schedule of items it
agreed to
rectify;[14]
- email from
Armenti Form and Space to the builder dated 16 February
2019;[15]
- email dated 16
December 2021 from the builder attaching
two quotes;[16]
- HB for all three
proceedings comprising 655 pages excepting pages
106-120;[17]
- plans dated 23
July 2018 (nine
pages);[18]
- site inspection
report - BEI dated 27 August
2020;[19] and
- resume of Mr
Bradley Porteous.[20]
- Oral
evidence in respect of the three proceedings was as follows:
- the
owners gave evidence themselves and called expert witnesses, Mr Whittle of
Intune
Consulting[21],
Mr Just, manager at Structerre consulting
engineers[22] and
Mr Porteous (previously the BEI at the Building and Energy Commission and
the author of the site inspection report)
[23] whose evidence it
was submitted was a central plank of their case; and
- evidence
on behalf of the builder was given by Mr Memon and expert witness Mr
Machell, chartered building
professional[24].
- Concurrent
expert evidence was given at the outset of the first day of the hearing by Mr
Whittle (on behalf of the owners) and Mr
Machell (on behalf of the builder) in
respect of complaints relating to the roof.
- Towards
the conclusion of the hearing on the second day counsel for the owners made an
application to, amongst other things, lead
further expert evidence from Mr
Whittle in relation to the upper floor
roof.[25] It was
envisaged that Mr Whittle would conduct a further inspection of the roof and
produce a further report. That application
was opposed by counsel for the
builder. We declined to grant leave to the owners to lead this further expert
evidence.[26]
- For
completeness we note that on 17 February 2022 there was a conferral of the
parties' costings experts. In brief the experts recommended
that the Tribunal
make findings as to the scope of works, prior to them assessing costs.
The Tribunal's consideration
- It
is not in dispute, and we accept, that the builder carried out a regulated
building service which is the subject of the items
of complaint.
- We
now turn to consider the issues to be determined.
Issue 1: Were the building works (items of complaint) carried out by the builder
in a manner that is not proper or proficient or
is faulty or unsatisfactory?
- In
respect of Complaint 1 and Complaint 2 the parties prepared a complaint schedule
comprising 73
items.[27] All items
to which we refer are items numbered in accordance with the owners' amended
complaint schedule (complaint schedule). The complaint schedule sets out
the corresponding numbers in the BEI's report (which are different).
- The
owners withdrew 11
items[28] in the
complaint schedule.
- The
builder admitted liability in relation to 28 of the
items[29].
In respect of the admitted items only the cost
of remedying the items is in dispute as the builder does not take issue with
what
the BEI says in his site inspection report in relation to those items and
the scope of the rectification works set out in that
report.[30]
- The
builder disputes liability and quantum in relation to the balance of the items
(that is items 1, 8, 10, 14, 16, 18, 21, 23, 25,
28, 29, 30, 38, 42, 43, 44, 45,
48, 51, 55, 61, 64, 68, 69, 71, and 73).
- In
respect of item 51, the builder admits liability in relation to the lower floor
roof. Only the upper floor roof remains in dispute.
- In
respect of Complaint 3 there are three items of complaint.
- Item
1 is disputed.
- Item
2 is admitted, and the scope of the works identified in Mr Whittle's report
is accepted by the builder.
- Item
3 relates to upper floor ceiling water staining in the eaves, around the
balcony, on top of the staircase, as well as the cedarwood
lining in the
balcony.
- In
support of this item the owners rely on the photos supplied in conjunction with
the previous reports and in particular Mr Whittle's
report dated 20 October
2021. They also rely on a report provided by Mr Whittle following an
inspection on 11 February 2022 of the
upper floor roof.
- The
owners are seeking that the builder fix the upper floor roof and the staining as
a result of water ingress. The builder denies
the complaint item noting that
the owners were refused leave to adduce any further evidence in relation to item
51 (all roof leaks)
and that this complaint item is simply an attempt to
circumvent this order.
- At
the commencement of the hearing on 17 June 2022 counsel for the builder made
an application to have Item 3 dismissed.
- We
granted his application and struck out/dismissed Item 3 as it relates to item 51
and is an attempt to circumvent the ruling we
made, at the completion of the
part heard hearing on 16 December 2021, to refuse to grant the owners leave to
file further expert
evidence.[31]
CC 1233 of 2020 and CC 1572 of 2020 - items of complaint
- We
now turn to consider each of the items of complaint in Complaint 1 and Complaint
2 in numerical order.
Item 1 - wardrobe recess in bedroom
- It
is not in dispute that the wardrobe recess in bedroom three, in order to comply
with the plans, ought to have been built with
a small nib wall. It is not in
dispute that it has been built without a small nib wall.
- The
builder contends that there was an agreement to settle the dispute, which the
owners do not now want to honour, which was that
an Ikea wardrobe be installed
at his cost. The builder says that when the owners could not find an Ikea
wardrobe to fit, they instructed
him to go ahead and install what is there now,
which is two sliding doors, a shelf and a
rail.[32]
- The
owners deny that they instructed the builder to install what is there now. They
contend that there was no variation of the Contract.
Variations to the Contract
- Clause
16 of the Contract provides that:
(a) the contract may be varied at the owners request with the builder's consent.
The builder's consent must not be unreasonably withheld.
(b) the builder may decline to execute any variation required by the owner
unless the owner first:
(i) gives written notice of
the requirements of the variation; and
(ii) in response to the builder's written notice requiring evidence to the
builder's satisfaction of capacity to pay for the variation,
gives that
evidence.
(c) If the builder agrees to undertake any variation, then the
details:
(i) must be in writing;
(A) setting out the cost and all the terms of the variation;
(B) showing the date of the variation;
(ii) must be signed by the builder and the owner or their respective agents;
and
(iii) the owner or owners agent must be given a copy of the signed
variation;
(A) as soon as reasonably practicable after it has been signed by both
parties; and
(B) before the work to which the variation relates is commenced.
- On
the basis of the evidence before us we find that there was no written variation
of the Contract signed by the parties in accordance
with clause 16.
- We
find that in building the wardrobe recess in bedroom three without a
small nib wall the builder has carried out a regulated building service in a
manner that
is not proper or proficient or is faulty or unsatisfactory.
- We
concur with the scope of the remedial action proposed by the BEI in his report,
that the wardrobe robe recess in bedroom three
is to be remedied so that it
complies with the plans in a proper and proficient manner, protecting all
adjacent surfaces.
Item 8 - sink in alfresco
- The
owners complain that the sink installed in the alfresco area has a left-handed
drainer rather than a right-handed drainer in
accordance with the approved plans
and hardware list in the signed Contract. They rely on the quote from
Spectra Selection Centre
(Spectra) dated 28 May 2018 which provides
for a right-handed
drainer.[33]
- It
is not in dispute that the sink that was installed has a left-handed
drainer.[34]
- We
accept Mr Whittle's evidence that this is contrary to the plans and the signed
Contract (listing the hardware) which provides
for a righthanded
drainer.[35]
- The
builder says the owners chose a left-handed drainer from Spectra and this is
confirmed by an email from Spectra to the builder
dated 30 November
2021.[36] Mrs Faqiri
refutes this.
- Mr
and Mrs Faqiri say that they did not sign a variation for a sink with a
left-handed drainer.
- On
the basis of the evidence before us we find that there was no written variation
of the Contract signed by both parties in accordance
with clause 16.
- We
find, that in installing a left-handed drainer in the alfresco, the builder
carried out a regulated building service in a manner
that is not proper or
proficient or is faulty or unsatisfactory.
- We
concur with the scope of the remedial action proposed by the BEI in his report,
that the existing alfresco sink be removed and
replaced with a new sink in
accordance with the Contract/Spectra quotation dated 28 May 2018, and that the
work is to be done in
a proper and proficient manner protecting all adjacent
surfaces.
Item 10 - left-hand pier of the garage
- The
owners claim, and it is not in dispute, that the left-hand pier of the garage is
wider than the pier on the right-hand side of
the garage, and the photographic
evidence confirms this.
- We
accept Mr Whittle's evidence that the right-hand pier is 520 millimetres
wide, and the left-hand pier is 630 millimetres wide,
being a difference of 110
millimetres.
- The
owners are seeking to have the left-hand pier remedied to be the same width as
the right-hand pier, in accordance with the ground
floor plans.
- The
builder contends that he built the left-hand pier in accordance with the
elevation plans, which show the piers of differing
widths.
The plans
- We
find that there is a discrepancy between the ground floor plans and the
elevation plans.
- We
find that the ground floor plans have dimensions and show the piers of the same
width.
- We
find that the elevation plans do not have dimensions and show the piers of
differing widths, the left-hand pier being wider than
the righthand pier.
- Mr
Whittle gave evidence, which we accept, that it is common practice to build off
the floor plans not the elevation plans, and that
a dimension drawing is used in
preference to a drawing without
dimensions.[37]
- In
respect of any discrepancies in drawings the conditions of Contract contain the
following relevant
provisions:[38]
- Paragraph 3(a)
of the conditions of Contract provides that if the builder finds any discrepancy
or ambiguity in the drawings or between
the drawings in the specification, the
builder must immediately refer the matter to the owner who must direct the
builder in writing what is to be done. If the owner fails to direct the
builder within five working days of the request for directions, the builder must
determine what is to be done.
- Paragraph 3(b)
of the conditions of Contract requires that where the builder determines what is
to be done, the builder must advise
the owner in writing of the course
adopted.
- Paragraph 3(c)
of the conditions of Contract provides that if there is a difference between
scaled dimensions and figures on the drawings,
the figures prevail. Drawings to
a larger scale take precedence over those to a smaller scale.
- The
builder gave evidence that on discovering the discrepancy in the drawings prior
to constructing the pier he met with Mr Faqiri
on site to discuss the
discrepancy and that Mr Faqiri agreed that it be constructed in accordance with
the elevation plans. Mr Faqiri
denies that he agreed with the builder to build
the pier the way it is constructed now.
- We
accept that the builder discussed the discrepancy with Mr Faqiri. However,
none of the next steps required to be undertaken in
accordance with the
conditions of Contract were taken by either of the parties to resolve the
discrepancy. The builder did not,
upon the owners' failure to direct him in
writing what is to be done within five working days of the request for
directions, determine
what is to be done and advise the owner in writing of the
course adopted.
- Clause
3(c) of the Contract, which is consistent with Mr Whittle's evidence regarding
common practice, provides that the ground floor
drawings which show dimensions
prevail over an elevation drawing which has no dimensions on it.
- We
find that the left-hand pier ought to be the same width as the righthand
pier, in accordance with the ground floor plans.
- We
find that in failing to build the left-hand pier the same width as the
right-hand pier the builder has carried out a regulated building service in a
manner that is
not proper or proficient or is faulty or unsatisfactory.
- In
respect of the appropriate remedy the owners are seeking to have the left-hand
pier remedied to be the same width as the right-hand
pier, in accordance with
the ground floor plans.
- The
builder submits that it would be unreasonable to order him to pull down half the
garage to rectify the size of the left-hand
side brick pier by a nominal amount
of millimetres. The builder submits that the appropriate remedy is a nominal
sum for loss of
amenity.
- In
considering the parties' respective submissions concerning the appropriate
remedy, we have regard to the principle that any remedial
work must be both
'necessary' and 'reasonable'. What is 'necessary' and 'reasonable' in any
particular case is a question of
fact.[39]
- In
our view the left-hand pier was constructed substantially in accordance with the
Contract, being only 110 millimetres wider.
We accept the builder's
submission that it would be unreasonable to insist on strict compliance with the
Contract and carry out the
rectification sought by the owners. Further in our
view the cost of carrying out the rectification sought by the owners is out of
proportion to the benefit to be obtained.
- In
our view there has been a loss of amenity as the lack of symmetry makes the
front elevation visually less attractive and the owners
ought to be compensated
for this loss of amenity.
- We
do not have any submissions from the parties as to what may be considered a
nominal sum. In our view, given that the total Contract
price for the
construction of this house was $540,000 we consider that a nominal sum for the
loss of amenity is $1,000.
Conclusion
- We
consider that the builder ought to pay the owners a nominal sum of $1,000 in
compensation for carrying out a regulated building
service in a manner that is
not proper or proficient or is faulty or unsatisfactory.
Item 14 - upper floor ensuite shower mixer tap handles
- The
owners claim that the upper floor ensuite shower mixer tap handles are not the
selected shower handles as described in a Spectra
quote/invoice dated 27
November 2018 (which quotation is not in evidence).
- We
note here that it was an earlier Spectra quotation dated 28 May 2018 that formed
part of the Contract.
- The
builder gave evidence, which we accept, that the process of changing selections
was 'a fairly loose arrangement' and that there
was no record of any changes,
only a record of the original
selections.[40]
- On
the evidence before us we are not satisfied that the upper floor ensuite shower
mixer tap handles are not the selected shower
handles as described in the
Spectra quote/invoice dated 27 November 2018.
- Further,
on the evidence before us we find that there was no written variation of the
Contract signed by the parties in accordance
with clause 16.
- We
are not satisfied that the builder carried out a regulated building service in a
manner that is not proper or proficient or is
faulty or unsatisfactory.
Accordingly, we dismiss this item.
Item 16 - entrance texture - overlapping paint job
- Under
cross-examination the builder admitted that this item was unsatisfactory.
- The
only dispute is in respect of the appropriate remedial action.
- The
builder contends that rectification only requires paint touchups. He
disputes the remedial action proposed by the owners
which is that the whole of
the external plastering needs to be
redone.[41]
- In
his oral evidence Mr Porteous agreed that the unsatisfactory work could be
remedied by paint touch-ups.
[42]
- On
the basis of the evidence, we find that the builder has carried out a regulated
building service in a manner that is not proper
or proficient or is faulty or
unsatisfactory.
- On
the evidence of Mr Porteous, we find that the defective work can be remedied by
touching-up with paint.
Item 45 - entrance external wall texture - overlapping paint job
-
This item is related to item 16 and so we have dealt with it out of sequence
with the other items.
- Again,
the owners seek to have both the texturing and the overlapping paint remedied.
- On
the basis of the evidence, we find that the builder has carried out a regulated
building service in a manner that is not proper
or proficient or is faulty or
unsatisfactory.
- On
the evidence of Mr Porteous, we find that the defective work can be remedied by
touching-up with paint.
- We
return to deal with the remaining items in sequence.
Item 18 - kerb to council crossover
- The
owners complain that the kerb to council crossover is unfinished, chipped, and
cracked in multiple locations.
- The
builder says this is not part of the Contract. The builder says that the
Contract only requires him to install the crossover
not reinstate damaged or
non-existent curb of approximately 3 metres in length.
- Item
31 in the scope of works (comprising the Contract) simply states 'crossover to
council requirement (exposed concrete)'.
- The
BEI observed that there are missing sections of concrete kerbing next to the
driveway crossover, and that the kerbing is chipped
and cracked in a number of
locations. In his opinion it is defective.
- The
BEI recommends that the builder remedy the concrete kerbing to the front of the
property so that it complies with the local council's
requirement of item 'v' of
the building permit BA4 No 580/2018 which states that:
in the event that access ways, parking areas and hard stand is not
satisfactorily maintained, the City's Director Technical Services
may require by
notice in writing, that the area be brought up to satisfactory standard within a
specified period of time and notice
shall be complied with within that period.
Without limitation, the notice may require that lines marking car bays be
repainted,
pot holes be repaired, damaged kerbs be replaced and degraded access
be resurfaced generally in accordance with the City's engineering
requirements
and design guidelines.
- We
accept the BEI's opinion that due to the crossover being cracked, displaced,
missing and chipped it is unsatisfactory and requires
remedying to comply with
these provisions in the building permit. He required all work to be done
to a proper and proficient manner
protecting all adjacent surfaces.
- We
find that the builder has carried out a regulated building service in a manner
that is not proper or proficient or is faulty or
unsatisfactory.
- We
concur with the scope of the remedial action proposed by the BEI in his report,
that the crossover be remedied to comply with
the provisions in the building
permit and that all work be done to a proper and proficient manner protecting
all adjacent surfaces.
Item 21 - incomplete carpet edges
- It
is not in dispute that the carpet edges have been left unfinished. Nor is it in
dispute that it was the builder's job to lay
the carpet and that the owners
undertook the tiling themselves after handover.
- We
accept the builder's evidence in relation to building practices that it is the
last trade that finishes the job.
- We
find that in the circumstances where the owners undertook the tiling after
handover it was not the builder's responsibility to
return to trim the carpet
edges.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 23 - brick fence/screen wall on southern boundary
- There
are three separate items of complaint relating to the brick fence/wall on the
southern boundary, each of which deal with a
different aspect of the wall,
namely the height of the wall (item 23), the height of the concrete footings
(item 55) and the insufficient/faulty
slab (item 70).
- For
convenience we will deal with each of these items relating to the wall in turn,
and out of sequence with items in respect of
other works.
- In
respect of item 23 the owners claim that the wall was not built in accordance
with the plans approved by the Council. They contend
that according to the
plans the external height of the wall ought to be 1.8 metres. They are
seeking that the height be remedied.
They are seeking $35,758.50 in costs to
remedy the wall.[43]
- We
turn firstly to consider the height of the wall as constructed, which is not in
dispute.
- On
the basis of the photographic evidence and the report of Mr Just we find that
the ground on which the wall is built is on a slope,
being higher on the
right-hand side closest to Yomba Street, than the left. Further, we find that
the levels either side of the wall
are different with the external soil level
being higher than the internal soil
level.[44]
In particular we accept Mr Just's observations that the wall retains up to
820 millimetres on the external side, leaving the external
height of the
wall at 1,200
millimetres.[45]
- What
is in dispute is whether the height of the wall is in accordance with the
approved plans.
- There
are a number of problems with the approved plans, which were supplied by the
owners, and which we find to be deficient. The
problems are as
follows.[46]
- Firstly,
the elevations on the
plans[47] show the
wall constructed as if the ground was level which is incorrect. As we have
stated, the wall was built on ground that slopes
upwards on the right-hand side
towards Yomba Street. We accept Mr Just's evidence that in this respect the
plans are
wrong.[48]
- Secondly,
the plans do not provide for a retaining wall with the consequential difference
in height on either side of the wall.
Yet the built wall retains 820
millimetres on the external side, leaving the external height of the wall at
1,200 millimetres.
- Thirdly,
whilst the plans provide for the height of the wall to be 1,800 millimetres, the
issue is where the height is to be measured
from. Mr Just conceded that the
plans do not refer to the height of the wall being measured from the ground
level.[49] Further Mr
Just conceded that everything on the elevation is referenced to the floor slab
level, and that if the 1,800 millimetres
is measured from the floor slab level
then the height of the built wall complies with the
plans.[50] Mr
Porteous also conceded, in cross-examination, that the height of the wall would
be measured from the floor
slab.[51]
- Fourthly,
the finished floor level of the slab on the site plan attached to the building
permit for the house is
10.3.[52] In
comparison the site plans for the wall, which was the subject of a later
building permit[53]
show that the finished floor level of the slab for the house is higher, at
10.5.[54]
- On
the basis of Mr Just's and Mr Porteous' evidence, and the site plans the subject
of the building permit for the wall we find that
the height of the wall is to be
measured from the finished floor level of the slab (10.5).
Conclusion
- For
these reasons we do not accept the owners' contention that according to the
plans the external height of the wall ought be 1.8
metres.
- We
find that the height of the built wall is compliant with the approved
plans.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 55 - brick fence/screen wall on southern boundary
- The
owners complain that the concrete footings to the wall are approximately 100
millimetres higher than the nearest concrete paving.
Further they complain that
the wall plaster /texture coating/painting has not been finished right down to
the footings. These observations,
which we accept, are in the BEI's report.
- The
owners want the concrete footings to the wall to be remedied so that they are
installed at a height that will allow for the fitting
of paving. Further they
want the plastering/texture coating/painting remedied so that it is finished
right down to the top of the
concrete footings.
- As
previously stated, there are a number of problems with the approved plans,
including that the elevations on the plans show the
wall constructed as if the
ground was level which is incorrect as we have stated. The wall was built on
ground that slopes upwards
on the righthand side towards Yomba
Street.
- On
the basis of the site plans we accept that the spot levels of the soil in the
backyard around the wall are
higher[55] than the
house slab level, indicating soil build up around the house. We accept Mr
Just's evidence that the natural grade of the
soil, as depicted on the site
plans would have covered the
footings.[56]
- In
contrast the photographic evidence, which we accept, shows that the soil
alongside the footings has been dug out and levelled.
The builder contends that
it was the owners who did this.
- When
it was put to Mr Faqiri in cross-examination that he had dug out and levelled
the soil alongside the wall he was evasive and
unconvincing.[57] He
responded, 'I make it ready for the paving' which he said was 'my
job'.[58]
-
We consider it likely that Mr Faqiri, in making the area ready for paving,
exposed the footings, creating a height differential
between the footings and
the paving. Further this would also explain why the wall
plastering/texturing/painting does not continue
down to the top of the concrete
footings, the plastering/texturing/painting having been done prior to Mr Faqiri
making the ground
ready for paving.
- On
the evidence before us we are not persuaded that the concrete footings, or the
plastering/texture coating/painting is defective
as alleged.
- For
these reasons we do not accept that the wall is defective as alleged by the
owners.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 70 - slab - brick fence/wall on southern boundary
- The
owners complain that the slab (or footings) for the wall is insufficient and
faulty.
- The
owners refer to their related complaint item 23 and seek a remedy 'fix as per
standard'.
- Whilst
this item is inchoate in the complaint schedule, Mr Just, in his evidence,
identified other aspects of the footings that in
his opinion meant they were not
compliant with the plans; in particular, that the pier footings are undersized
(520 x 520 x 100 millimetres
deep) being less than the minimum dimensions (750 x
750 x 300 millimetres deep), that the footings are on bricks in one location,
and over a stump at another location.
- We
accept Mr Just's evidence that the pier footings are undersized, and the
footings are on bricks in one location, and over a stump
at another location.
Mr Just did not know why putting the footings on bricks 'would have ever
been done', and that not taking time to 'grub out the tree' was poor
workmanship.
- We
accept Mr Just's evidence that in these respects the wall was not constructed in
accordance with the plans and that for these
reasons the work was faulty and
unsatisfactory.
- Mr
Just agreed that the footings could be remediated, and that any remediation
would depend on what the council allowed.
[59]
Conclusion
- We
conclude that because the pier footings are undersized, the footings are on
bricks in one location, and over a stump at another
location, the builder
carried out a regulated building service in a manner that is not proper or
proficient or is faulty or unsatisfactory.
- We
find that the scope of the remedial action requires the dimensions of the pier
footings to comply with the plans, and the footings
not be located on bricks and
tree stumps.
- We
return now to deal with the remaining items in sequence.
Item 25 - upper floor sitting room window
- The
owners complain that in the upper floor sitting room, instead of installing a
window the builder has installed a glass panel
with gaps around the perimeter.
They are seeking to have a framed window installed with no gaps around the
perimeter.
- We
accept the evidence of the BEI and Mr Whittle, that the upper floor sitting room
has a glass panel with a 25-30 millimetre gap
around the perimeter, which
accords with the upper floor plan (associated with the building permit).
- Mrs
Faqiri says that the designer, Armenti, changed these plans to provide for a
window and that he emailed this changed plan to
the builder on 16 February
2019.[60]
- The
builder's evidence is that as of 16 February 2019 the brickwork had been built,
and the frames had been delivered on site.
- On
the basis of the evidence before us we find that there was no written variation
of the Contract signed by both parties in accordance
with clause 16.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 28 - cedar wood ceiling lining in portico and alfresco
- The
owners complain that the cedar wood ceiling lining in the portico and alfresco
areas has not been varnished and this is not in
dispute.
- The
builder says that varnishing the cedar wood ceiling lining in the alfresco and
portico is not in the Contract
[61] and we accept
this.
- Further
the owners complain that the alfresco cedar wood ceiling lining is water damaged
and this is not in dispute. They are seeking
to have the cause and effect of
the staining remedied (as recommended by Mr Porteous in his
report).[62]
- In
so far as the cause of the water damage in the alfresco is concerned this
relates to item 51, and liability has been admitted
for the lower floor roof
including the alfresco roof.
- In
respect of the effect of the water damage the builder concedes that the staining
needs to be rectified
[63] and that this can
be done by sanding out the staining. Mr Whittle agreed under cross-examination
that the staining could be remedied
by sanding
it.[64]
- We
accept Mr Porteous' opinion that both the cause and effect of the water-stained
cedar ceiling lining in the alfresco ought be
remedied.
- Further
on the basis of the evidence of the builder, Mr Porteous and Mr Whittle we find
that the water-stained cedar wood ceiling
lining in the alfresco is
unsatisfactory and that it can be remedied by sanding.
Conclusion
- On
the basis of the evidence before us we are not satisfied that in not varnishing
the portico and alfresco cedar ceiling linings
the builder carried out a
regulated building service in a manner that is not proper or proficient or is
faulty or unsatisfactory.
- In
so far as complaint item 28 relates to the staining to the alfresco ceiling we
find that the builder carried out a regulated building
service in a manner that
is not proper or proficient or is faulty or unsatisfactory.
- In
so far as the cause of the leaking in the alfresco is concerned this relates to
item 51, this item is admitted, and as stated
above, the builder does not take
issue with the remedial action in the BEI report in respect of admitted items.
- In
so far as the remedial action is concerned, we find that the effect of the water
staining in the alfresco ought be remedied by
sanding the alfresco ceiling.
Item 29 - extra dirt left on site - front yard, front of house
- The
owners complain that the builder left extra dirt on site and that it cost them
$500 to have it removed.
- When
the BEI did a site inspection on 31 July 2020, he observed building rubbish on
site.
- The
builder disputes that any rubbish on site was the builder's rubbish and further
points out that there is no evidence of this
cost having been incurred by the
owners.
- We
are not persuaded that the building rubbish observed by the BEI during his site
inspection on 31 July 2020 was left by the builder
in circumstances where the
builder completed the building work in December 2019, and the owners have, on
their own evidence, been
undertaking work on their property. Further there is
no evidence of the cost of removal of the building rubbish.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 30 - portico downpipe
- It
is not in dispute that the portico downpipe on the left-hand side of the main
entrance/portico is inside the pier and protrudes
approximately 3 metres
from the ground.
- The
owners complain that the downpipe should have stayed inside the pier and
protruded out at ground level rather than approximately
3 metres from the
ground.[65]
- The
floorplans show the downpipe on the face of the pier (rather than inside the
pier) and we so find. Further the general notes
on the
plans[66] provide that
'position of downpipes approximate only and to builder's discretion'.
- Whilst
conceding that the plans show the downpipe on the face of the pier in Mr
Whittle's opinion the downpipe should have stayed
inside the pier and made its
way down to the bottom of the pier rather than stopping one storey
up.[67]
- Mr
Porteous's evidence is that the portico downpipe, in exiting at the
first floor level rather than being brought to the ground,
is not compliant
with Australian
Standards.[68]
- In
our view based on the evidence of Mr Porteous and Mr Whittle we find that the
downpipe is defective in that it stopped one storey
up, rather than continuing
to ground level.
- On
the basis of the evidence before us we find that the builder has carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory.
- The
works ought to be remedied by continuing the downpipe to the ground. Given that
the floorplans provide for downpipes on the
face of the pier rather than inside
the pier we are of the view that the appropriate rectification is for the
downpipe to continue
to the ground, on the face of the pier.
Item 38 - accessories to alfresco sink
- The
owners complain that they were not supplied with the accessories for the
alfresco sink, including a cutting board and a cover
plate for one of the sinks.
- The
builder says that the accessories were supplied.
- Given
the conflicting evidence regarding the supply of these items we are not
persuaded that these items have not been supplied as
alleged.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 42 - water tap outside the study not installed
- The
owners complain, and it is not in dispute, that a tap has not been installed
outside the study room.
- Mr
Porteous's conclusion that this is unsatisfactory, is based on an earlier
version of the ground floor plan which was superseded
by the ground floor plan
the subject of the building permit dated 1 August 2018, which does not show a
tap outside the study.
- Whilst
the electrical floor plans the subject of the building permit show a tap outside
the study, we accept the builder's evidence
that electrical plans are not
followed when installing
plumbing.[69]
- On
the basis of the ground floor plan dated 1 August 2018 we find there is no tap
on the ground floor plan outside the study, and
therefore its absence is in
accordance with those plans and not
unsatisfactory.[70]
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 43 - main entrance door missing door handle
- The
owners complain that the main entrance door is missing a door handle.
- On
the basis of the owners' evidence, which was confirmed by the BEI, we accept
that the main entrance door is missing a handle.
- The
parties agree that the builder's contractor attended to install the handle, and
that the owners did not allow him to carry out
the installation. Mrs Faqiri
says this was because the door is faulty.
- The
parties have given contradictory evidence as to who has possession of the
handle. The builder says the owners have it, whereas
the owners say the
contractor took the handle away with him.
- We
accept the builder's unchallenged evidence that the handle was picked up by the
owners from the supplier directly and consider
that in the circumstances it is
unlikely that the contractor took it.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 44 - no perimeter lighting to the bulkheads
- The
owners complain that there is no perimeter lighting to the bulkheads in bedrooms
one and two, the theatre room, the entry void,
the sitting room, dining and
living area in accordance with the Contract.
- The
electrical plan indicates perimeter lighting to all of these areas of the
dwelling.[71]
- The
builder contends that perimeter lighting to the bulkheads in these rooms is not
in the builder's contracted scope of works.
The builder contends that item 21
in the scope of works in respect of lighting provides only that two light
fittings be supplied,
and installed per room and we accept this
evidence.[72]
- We
accept the builder's evidence that the plans allow the owners to install
perimeter lighting after handover and that the electrician
made provision for
that by providing a General Power Outlet and cabling to enable the owners to
install perimeter lighting after
handover.[73]
- On
the basis of the scope of works we find that only two light fittings per room
were to be fitted and installed as part of the Contract.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 48 - internal door frames dented and mis-manufactured
- The
owners complain that most of the internal door frames are mismanufactured
and have dented frames and that the builder painted
over them.
- The
owners are seeking that the remedial work proposed by the BEI be undertaken,
that is that the door frames be repaired and repainted.
- The
BEI and Mr Whittle both observed dented doorframes and we accept their evidence.
- In
the BEI's opinion it was unsatisfactory that the dents were left in some of the
internal door frames and painted over.
- The
builder says that the owners' painter did not properly prepare the frames and
that painting was not within the builder's scope
of works.
- On
the basis of the evidence before us we find that the paint work was not within
the builder's scope of work identified in the
Contract[74] and that
the owners' painter did not properly prepare the frames for painting.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 51 - all roof
- The
owners contend, and it is not in dispute, that the roof leaks. There is an
upper floor roof, and a lower floor roof.
- The
builder admits liability in relation to the lower floor roof and only contests
liability in relation to the upper floor roof.
- The
builder admits that the ground floor roof needs rectification and that it needs
to be sarked, which entails removing all of the
tiles, installing sarking, and
reinstalling the tiling and making good the
tiling.[75]
- We
note here that sarking is a waterproof membrane on the underside of the roof
tiles designed to catch small amounts of water and
direct it to the gutter.
[76]
- In
respect of the upper floor roof the owners contend that all of the roof
leaks [77] and
requires sarking to be installed.
- The
builder contends that no sarking is required to the upper floor roof given the
roof pitch (greater than 20°) and the length
of the rafters.
The lay evidence regarding the roof
- We
have endeavoured to distil from Mrs Faqiri's evidence regarding the roof, only
her evidence in relation to the upper floor roof,
given that liability for the
lower floor roof has been admitted.
- The
upper floor comprises three bedrooms, a sitting room with an adjacent balcony,
kitchenette, and a void over the
entry.[78]
- Mrs
Faqiri gave evidence of water ingress from February 2020, and her communications
with the builder in February and July 2020 confirm
her observations of a leak in
the upper floor roof near the
manhole.[79]
- The
builder concedes that there is a leak to the upper floor roof where the manhole
is located.[80]
- Mrs
Faqiri gave evidence that the Department of Fire and Emergency Services attended
on 30 June 2021 and put tarpaulins on
the roof.[81]
Mrs Faqiri did not say whether the tarpaulins were covering the upper floor roof
however we note that when Mr Whittle inspected
the roof in October 2021, he
observed that tarpaulins were covering the majority of the lower floor
roof. There is no mention in
his evidence of tarpaulins covering the upper
floor roof.
The expert evidence
- The
evidence of Mr Porteous, Mr Whittle and Mr Machell is relevant to this
item.
Mr Porteous' evidence
- Mr
Porteous, in his capacity as the BEI, provided a report dated 27 August
2020 following a site inspection on 31 July 2020.
- Mr
Porteous gave evidence that when he conducted a site inspection it was raining.
He did not go up on the upper floor roof although
he looked inside the roof
space of the upper floor roof and the only leak he observed was one leak between
two roof tiles above the
upper floor manhole in the hallway.
- Mr
Porteous gave evidence that all of the other comments in his report related to
the lower floor roof.
- At
the time of his inspection, he did not see anything else that needed to be
rectified on the upper floor
roof.[82] He resiled
from the comments in his report that the entire roof needed remedying. He
agreed that the remedial action required this
one instance of leaking to be
rectified. [83]
- Mr
Porteous gave evidence that the upper floor roof did not require sarking given
the pitch of the
roof.[84]
Mr Whittle's evidence
- At
the request of the owners Mr Whittle of Intune Consulting prepared a report
dated 20 October 2021 following a site inspection
that same day.
- Mr
Whittle observed water damage to only one location
upstairs[85] being a
small area, near the manhole at the apex of the roof.
- Mr
Whittle agreed that the National Construction Code does not require sarking for
a roof with a pitch greater than 20 degrees but
that it was his preference, and
sound practice to sark any tiled roof.
[86]
Mr Machell's evidence
- At
the request of the builder Mr Machell provided a report dated 24 November
2021[87] based on a
desktop review of the architectural plans and the reports of Mr Whittle and the
BEI.
- Mr
Machell was asked for his opinion as to whether the upper floor roof is required
to have sarking installed underneath the roof
tiles.
- The
National Construction Code at 3.1.5 provides that the maximum rafter length that
does not require sarking is 6 metres with a
roof pitch of greater than 22°.
- For
this reason, in Mr Machell's opinion there is no need for sarking because the
longest rafters on the plan are less than 6 metres
and the roof pitch is
25.35°.
- Further
Mr Machell gave evidence that he would not install sarking where it is not
required. He disagreed with Mr Whittle, about
it being best practice to install
sarking even when not
required.[88]
Consideration of the evidence
Sarking
- On
the basis of Mr Machell's evidence, we find that the rafters in the upper floor
roof are less than 6 metres with a roof pitch
at 25.35°.
- On
the basis of the evidence of Mr Machell, Mr Whittle, and Mr Porteous, we
find that given the length of the rafters and pitch of
the roof the National
Construction Code does not require sarking to the upper floor roof.
- We
therefore reject the contention of the owners that the entirety of the upper
floor roof requires sarking and is defective.
One leak
- On
the basis of the lay evidence, the photographic evidence, and the evidence of Mr
Porteous and Mr Whittle we find that there is
only one leak in the upper floor
roof, which is a leak between two roof tiles above the upper floor ceiling
access panel (manhole)
in the hallway. Notably, both Mr Porteous and Mr Whittle
record this one instance of leaking, which was observed by Mr Porteous in
July
2020 to be the only leak in the upper floor roof, and the evidence of this same
leak was observed by Mr Whittle approximately
15 months later when he conducted
his inspection on 20 October 2021.
- On
the basis of this evidence, we find that in so far as the upper floor roof has a
leak between two roof tiles above the upper floor
ceiling access panel the
builder carried out a regulated building service in a manner that is not proper
or proficient or is faulty
or unsatisfactory.
- We
accept Mr Porteous' evidence that the only rectification required to the upper
floor roof is to remedy the leak between two roof
tiles above the upper floor
ceiling access panel.
Item 61 - ensuite WC, study, and internal garage doors are missing buffers
- The
owners are seeking to have the missing door frame buffers replaced.
- The
builder says that the owners' painter removed the buffers while painting.
- As
we have already found painting was not part of the Contract.
- In
the circumstances we consider it likely that the buffers were removed by the
owners' painter and not replaced. We do not consider
that the absence of the
buffers is due to the builder's defective work.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 64 - downpipe wrongly located on the right-hand side of the garage instead
of the left-hand side
- The
owners are seeking that the downpipe located on the right-hand side of the
garage be relocated to the left-hand side of the garage
in accordance with the
plans.
- The
builder says that the downpipe was installed in accordance with his discretion,
and he refers to the general notes on the plans
provided by the owners which
state that 'number and position of downpipes approx only and to the builder's
discretion'.
- We
find that the plans show the downpipe on the left-hand side of the garage. We
agree with the builder that the notes on the plans
give the builder discretion
in relation to the location of the downpipes, and for this reason we do not
consider that the location
of the downpipe on the right-hand side of the garage
is defective.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 68 – alfresco hotplate
- The
owners complain that the alfresco hotplate is too close to the glass
splashback/wall causing burning.
- The
builder says that the position of the hotplate is because the hotplate selected
by the owners is too large to have a gap at the
rear of it.
- The
BEI in his report referred to Australian Standard 5601.1:2013 Figure 6.3
Required clearances around domestic gas cooking appliances,
states in part '(c)
Requirement 3 Notes: 3 Consideration is to be given to window treatments and
painted surfaces on glass splashbacks
when located near cooking
appliances'.
- The
BEI observed that there was only a 100 millimetre distance from the closest gas
burner to the glass splashback. He noted that
the manufacturer of the glass
splashback had not been identified.
- Mr
Whittle is of the opinion that the hotplate should be positioned away from the
back wall splashback to prevent overheating and
to enable cleaning and that it
ought to be installed to comply with the relevant Australian
Standards.[89]
However, he conceded under crossexamination that there is no relevant
Australian Standard.
- Mr
Whittle conceded that he had not consulted the manufacturer's installation guide
in respect of the appropriate clearances in relation
to the hotplate from
adjoining
walls.[90]
- On
the basis of the evidence of the BEI and Mr Whittle, we are not persuaded that
the position of the hotplate is in breach of any
Australian Standard or not
installed in accordance with manufacturer's guidelines.
- Based
on the evidence before us we are not satisfied that the builder carried out a
regulated building service in a manner that is
not proper or proficient or is
faulty or unsatisfactory. Accordingly, we dismiss this item.
Item 69 - living room double entry doors
- The
owners complain, and we accept, that the double entry doors to the living room
are bowed up to 8.0 millimetres, the second opening
door face is damaged next to
the top mounted flush bolt, and that there are gaps between the doors and the
door frames that range
from 3 to 8 millimetres. All of this was observed
by the BEI.
- The
owners want the double entry doors remedied to comply with Australian Standard
2688:2017 Timber and Composite doors item 4.1.2,
item 5.3.3.3, Australian
Standard 19091984 installation of timber doorsets item 7.1 and item 7.2.
Repairs to the doors that
require painting is to be in keeping with the
manufacturer's recommendations and AS2311.
- In
the complaint schedule the builder has agreed to make this item comply with
AS2688:2017.
- On
the basis of the evidence, we find that the builder carried out a regulated
building service in a manner that is not proper or
proficient or is faulty or
unsatisfactory.
- We
find that the living room double entry doors ought be remedied to comply with
Australian Standard 2688:2017.
Item 71 - wrong toilet basin
- The
owners complain that the wrong toilet basin was supplied to the toilet next to
bedroom three. The owners rely on the Spectra
invoice which indicates five
toilets of the same kind. They say that one of them, namely the toilet next to
bedroom three, is not
of the same brand.
- The
builder says that he agreed to supply and install a new toilet, that the
supplier contacted the client for replacement and that
they refused to provide
access. Mrs Faqiri denies refusing
access.[91]
- Based
on the evidence before us we find that the builder carried out a regulated
building service in a manner that is not proper
or proficient or is faulty or
unsatisfactory.
- For
this reason, we conclude that this item be remedied by the supply and
installation of a toilet basin (in the toilet next to bedroom
three) of the same
kind as the others specified in the Spectra invoice that forms part of the
Contract.
Item 73 - pet wash plumbing
- The
owners claim that the pet wash plumbing has not been connected and that it is
blocked.
- In
his report Mr Whittle expressed the view that the pet wash drain was blocked or
never installed causing the pet wash area to drain
extremely slowly which in his
opinion is unsatisfactory.
- Mrs
Faqiri gave evidence that the plumbing has not worked since the
beginning.[92]
- The
builder says that the plumbing is not blocked.
- On
the basis of Mrs Faqiri's evidence and Mr Whittle's evidence we accept that the
pet wash plumbing is blocked or was never installed.
- Based
on the evidence before us we find that the builder carried out a regulated
building service in a manner that is not proper
or proficient or is faulty or
unsatisfactory.
- For
these reasons the cause of the blockage ought to be remedied.
CC 173 of 2022 – Complaint 3
Item 1 - ceiling in kitchen, garage, study room on ground floor and soffit
lining around the outside of the house
- The
owners complain that the ceilings in the kitchen, garage, study room (all ground
floor rooms) and soffit lining around the outside
of the house are water damaged
and stained due to the faulty roof. They are seeking to have the gyprock and
insulation replaced
as they say that with the tarp over the roof the water has
not been drying out and 'mulding will occur' (Tribunal emphasis).
- The
owners rely on Mr Whittle's
report[93] and also
photographs of stained ceilings in the kitchen, garage, study and the soffit
lining around the outside of the house, all
taken on or about 25 March 2022.
They also rely on photographs taken in or about February 2020 (when they
discovered the lower floor
leaking roof).
Mr Whittle's report
- In
so far as Mr Whittle's report is relevant to the four areas the subject of this
complaint, Mr Whittle commented that ceiling staining
extends to almost every
room on the ground floor, and the soffit lining around the outside of the house.
Photographic evidence of
the stained soffit lining was provided with his
report.
- In
his report he stated that the extent of the water damage over two years
'would lend itself to mould forming on the opposite side
of the sheet in the
roof space' and that 'if the ceiling sheets have lost their original shape and
structural integrity from the
constant exposure to the water ingress they would
need replacing'.
The lay evidence
- Mrs
Faqiri agreed that only three of the 16 rooms on the ground floor have stained
ceilings.[94]
Consideration
- We
do not accept Mr Whittle's evidence that ceiling staining extends to almost
every room on the ground floor because his evidence
is inconsistent with Mrs
Faqiri's evidence, which we accept, that the staining on the ceilings on the
ground floor relate to only
three of the 16 rooms on the ground floor,
namely the kitchen, study, and garage.
- Further,
we accept Mrs Faqiri's evidence, which is corroborated by Mr Whittle's evidence
that there is staining to the soffit lining
around the outside of the house.
- As
to whether the ceiling sheets have lost their shape and structural integrity Mr
Whittle's evidence is that ceiling sheets would
need replacing 'if' they had
lost their original shape. His evidence falls short of establishing that the
ceiling sheets have in
fact lost their structural integrity.
- As
to the existence of mould, his evidence is that the water damage would 'lend
itself to mould forming'. His evidence falls short
of establishing that there
is any mould. Further we note that the owners' complaint is predicated on
moulding occurring in the future
('mulding will occur').
- On
the evidence before us we are not satisfied that the ceiling sheets have lost
their original shape and structural integrity, nor
are we satisfied of the
existence of any moulding.
- It
is difficult to discern from the few photographs of the ceilings taken in
February 2020 whether the ceilings are stained. On
the evidence before us we
are unable to make any findings as to the existence of any staining to the
ceilings and soffit lining at
that time.
- On
the basis of the evidence of Mrs Faqiri and Mr Whittle we are satisfied that as
a consequence of the faulty and unsatisfactory
lower floor roof there is
staining to the ceilings in the kitchen, study, garage and soffit lining around
the outside of the house.
There is no evidence before us, nor is it contended
by the builder, that there is any other cause of the staining.
- The
issue is whether the owners should be compensated for this loss.
- The
builder says that the owners have failed to mitigate their loss including
refusing to reasonably allow the builder to attend
the house to conduct any
necessary remedial works to the
roof.[95]
- We
accept that the owners can only be compensated for any loss incurred due to the
failure of the builder to carry out the building
service in a proper and
proficient manner or arising from faulty or unsatisfactory work, and cannot be
compensated for loss suffered
by them due to their failure to take reasonable
steps to reduce or mitigate the extent of the loss being suffered (refer to
Hippydayze Pty Ltd and Mener Group Pty Ltd
[2019] WASAT 92 (Hippydayze)).
- We
find that the owners have unreasonably denied the builder access to the house to
remedy any defects, including the leaking lower
floor roof (see [293]-[303]
below). Further we find that it was not until June 2021 (approximately 15
months after they first discovered
the leaking lower floor roof) that the owners
arranged for a tarpaulin to cover the lower floor roof.
- We
find that the owners have failed to mitigate their loss and for this reason, we
dismiss this item.
Issue 2: What is the appropriate form of the BRO in respect of the complaint
items?
- The
owners have expressed a strong preference for a monetary order, under s 36(1)(b)
of the Act, as they say they have lost confidence
in the builder's willingness
or ability to fix the defects.
- The
builder would prefer that remedial orders be made in respect of any defective
work, which he is willing to undertake.
The applicable principles
- Section
36(1) of the Act confers discretion on the Tribunal as to the form of the BRO.
- The
owners have no right to elect the remedy sought under s 36(1) of the Act but are
entitled to express a
preference.[96]
- It
follows that the Tribunal cannot fetter its discretion by simply adopting the
owners' preference for a monetary order. The owners'
preference, and reasons
for seeking a monetary order, however, are relevant matters for the Tribunal to
consider when determining
the type of BRO to
make.[97]
- In
Hippydayze the Tribunal identified the following matters (which
are not exhaustive) that may be relevant to the exercise of the Tribunal's
discretion
under s 36(1) of the Act, particularly when exercising its discretion
to make a building remedy order in monetary
terms:[98]
... whether there has been an irretrievable breakdown in the relationship
between the parties (Trengove and Celebration Nominees Pty Ltd [2012]
WASAT 65 at [36]); whether an owner has justifiably lost confidence in the
workmanship and skill of the respondent (Nelson v Mardesic (1998) 22 SR
(WA) 42); whether the respondent has attempted to remedy the regulated building
service previously unsuccessfully and whether the respondent
has refused to
perform remedial work when invited to do so[.]
- It
is common practice to give a builder an opportunity to remedy its own defective
work. This is because an order to remedy compensates
the owner while minimising
the hardship to the builder who can usually carry out the work at substantially
less cost than the amount
charged by a third-party
contractor.[99]
However, the nature and extent of the complaints may raise concerns about the
proficiency and competency of the builder and support
a finding by the Tribunal
that a monetary order is more appropriate than ordering a builder to perform
remedial
work.[100]
The parties' positions
- In
summary, in support of their preference for a monetary order, the owners say
that they were willing to allow the builder back
to remedy the defective work
and that the builder returned and fixed some of the items of defective work but
not others. Further
they say that the builder has had adequate opportunity to
remedy the defects, having promised on numerous occasions since January
2020 to
return and remedy various items of defective work.
- As
we have said, the builder would prefer that remedial orders be made in respect
of any defective work, and he is willing to undertake
such work. The builder
says that he has been willing to remedy the defects, but the owners restricted
access to their property to
weekends and after 3.30 pm on weekdays. Further he
says that since the BEI issued his assessment of the items of complaint in
September
2020 the owners have refused to let him undertake any repairs in
relation to the items of complaint. The builder says this has exacerbated
the
damage claimed, in particular the water damage to the ceilings and internal
finishes has increased with no repairs allowed to
the lower floor roof for over
a year.[101]
Findings
- We
make the following findings in relation to the purported relationship breakdown
between the parties.
- The
owners commissioned a report from master building inspectors who inspected the
property in midDecember
2019.[102] The
report identified numerous defects and the report was forwarded to the builder.
- The
builder attended at the property in late January 2020 and agreed to undertake
various works to remedy the defects.
- After
the owners took possession of the house in late January 2020, they identified
further defects and in particular, the leaking
roof.
- The
owners gave the builder restricted access (after 3.30 pm on weekdays
and anytime on weekends) to effect any repairs.
- The
restricted access was because of the owners' requirement that they be at home
when any repairs were being undertaken.
- Both
the owners work full-time, although Mrs Faqiri sometimes works from home.
- The
builder advised the owners in March 2020 that this restricted him from being
able to undertake the work to ensure that the house
was completed in a timely
manner.[103]
- The
builder attended on various occasions in March, April, June and July 2020 to
rectify some of the works.
- On
some occasions the owners did not co-operate when the builder/his contractors
attended to rectify the works.
- In
an email to the Senior Complaints Officer at the Building and Energy Commission
dated Friday, 4 September 2020 the owners stated
that they did not want any
rectification undertaken by the builder until their case was 'progressed and
looked at by
SAT'.[104]
- Following
the commencement of proceedings in this Tribunal, the owners contend that after
the mediation in January 2021 they were
willing to allow the builder to attend
the Dwelling and make the necessary
repairs.[105] The
builder refutes that assertion and says that his responses in the complaint
schedule record his intention to repair the defects
by mid March 2021(which we
note is a matter of record) and yet there was no invitation by the owners to
allow him to carry out
these
works.[106]
- Further
the builder's uncontradicted evidence, which we accept, is that when he attended
the owners' house in late March 2021 to
discuss the rectification work, at a
prearranged meeting time confirmed with the owners, they did not want to discuss
anything with
the
builder.[107]
- On
the evidence before us we find that following lodgement of the proceedings at
this Tribunal the builder was willing to undertake
repairs, but the owners were
unwilling to allow the builder to attend to carry out rectification work.
Conclusion
- Whilst
the owners have expressed a preference for a monetary order (on the basis that
they have lost confidence in the willingness
and ability of the builder to
rectify the defective work) the builder is willing to undertake rectification
work and would prefer
that a works order be made, rather than a monetary order.
- We
accept that there has been a breakdown in the relationship between the owners
and the builder and that this is a relevant factor
for our consideration in the
exercise of our discretion under s 36(1) of the Act. However, this finding is
not determinative. We
accept that in most cases, as in this case, it is a
natural consequence of any dispute between an owner and a builder.
- On
the basis of the above findings, we conclude that the owners' loss of confidence
in the builder's willingness and ability to fix
the defects is unjustified and
unreasonable, particularly given the restrictive access they imposed on the
builder to remedy the
defects. Further we note that the Contract provides that
any defects be remedied by the builder during normal business
hours[108] and that
the owners prevented this.
- We
consider that the builder ought to be provided with an opportunity to remedy his
own defective work because such an order will
compensate the owners while
minimising hardship to the builder who will be able to carry out the work at
substantially less cost
than the amount charged by a third party contractor who
may be engaged by the owners to undertake that work. We are not satisfied
that
the nature and extent of the items of complaint raise concern about the
proficiency and competency of the builder to satisfactorily
carry out the
remedial work.
- On
the evidence before us we are not persuaded to exercise our discretion and grant
a monetary order.
Issue 3: If any of the building works were carried out in a manner that is not
proper and proficient or is faulty or unsatisfactory
are the owners entitled to
any compensation?
- In
respect of item 51, as stated above the builder has admitted liability in
relation to the lower floor roof, and further we have
found that some remedial
work is required to the upper floor roof.
- The
owners are seeking compensation (under s 36(1)(c) of the Act) for the cost of
alternative accommodation while the roof issues
are
addressed.[109] In
support of their claim they have provided quotations for the cost of alternative
accommodation varying between $122 per night
to $265 per night for their family
of five, all in the Cloverdale area. We note that the quote for
accommodation at the higher daily
rate was for 12 bed accommodation. We
consider a mid-range of $200 per night to be a reasonable sum.
- We
are satisfied that the owners will incur these costs as a result of the builder
failing to carry out the work in a proper and
proficient manner or being faulty
or unsatisfactory.
- Accordingly,
we will make an order that the builder pay to the owners the sum of $200 per
night for the cost of alternative accommodation
while the roof is being
remediated, being compensation pursuant to s 36(1)(c) of the Act.
- In
respect of Item 10 as discussed above, we consider that the builder ought to pay
the owners a nominal sum of $1,000 in compensation
being compensation pursuant
to s 36(1)(c) of the Act.
- For
the above reasons, the Tribunal makes the following orders.
Orders
The Tribunal orders:
- Pursuant
to s 46(1) of the State Administrative Tribunal Act 2004 (WA) the
applicants have leave to withdraw items 9, 13, 15, 27, 32, 34, 35, 36, 37, 41,
50, and 72 and the items are withdrawn.
- Pursuant
to
s 38(1)(b)
of the
Building Services (Complaint Resolution and
Administration) Act 2011
(WA) the Tribunal declines to make
orders:
(i) relating to CC 1233 of 2020 and CC 1572 of 2020 in
respect of items 14, 21, 23, 25, 29, 38, 42, 43, 44, 48, 55, 61, 64, 68; and
(ii) relating to CC 173 of 2022 in respect of item 1;
and those items are dismissed pursuant to s 46(2) of the State
Administrative Tribunal Act 2004 (WA).
- Within
28 days and pursuant to
s 36(1)(a)
of the
Building Services
(Complaint Resolution and Administration) Act 2011
(WA), the respondent
is to remedy the following items:
(a) the items it has admitted:
(i) in respect of CC 1233 of 2020 and CC 1572 of 2020 being items 2, 3,
4, 5, 6, 7, 11, 12, 17, 19, 20, 22, 24, 26, 31, 33, 39, 40,
46, 47, 49, 51 (in
respect of the lower floor roof only) 52, 53, 54, 56, 57, 65, 66; and
(ii) in respect of CC 173 of 2022 being item 2; and
(b) the items that the Tribunal has identified as not being carried out in a
proper and proficient manner or faulty or unsatisfactory
being items 1, 8, 16,
18, 28, 30, 45, 51 (upper floor roof), 69, 70, 71, 73 (relating to CC 1233 of
2020 and CC 1572 of 2020).
- To
remedy the items referred to in order 3(a) the respondent is required to
undertake the remedial work set out in the attached tables.
- To
remedy the items referred to in order 3(b):
(a) in respect of item
1, the robe in bedroom 3 is to be remedied so that it complies with the plans in
a proper and proficient manner,
protecting all adjacent surfaces;
(b) in respect of item 8, the existing alfresco sink be removed and replaced
with a new sink in accordance with the contract/Spectra
Selection Centre
quotation dated 28 May 2018, and that the work is to be done in a proper and
proficient manner protecting all adjacent
surfaces;
(c) in respect of items 16 and 45 remedy the overlapping paint by touching up
with paint;
(d) in respect of item 18, the crossover is to be remedied to comply with the
provisions in the building permit and all work is to
be done in a proper and
proficient manner protecting all adjacent surfaces;
(e) in respect of item 28, the staining in the alfresco ceiling be remedied
by sanding;
(f) in respect of item 30, the respondent is to rectify the defect by
continuing the downpipe to the ground, on the face of the pier;
(g) in respect of item 51, the two roof tiles the cause of the leak above the
manhole in the upper floor roof be remedied;
(h) in respect of item 69 the living room double entry doors be remedied to
comply with Australian Standards 2688:2017;
(i) in respect of item 70 the dimensions of the pier footings be remedied to
comply with the plans, and the footings be remedied so
as not to be located on
bricks and tree stumps;
(j) in respect of item 71 the respondent supply and install a toilet basin
(in the toilet next to bedroom 3) of the same kind as the
others as
specified in the Spectra invoice forming part of the contract; and
(k) in respect of item 73 the respondent is to remedy the cause of the
blocked or non-existent pet wash plumbing.
- Within
28 days and pursuant to
s 36(1)(c)
of the
Building Services (Complaint
Resolution and Administration) Act 2011
(WA), the respondent pay to the
applicants compensation in the sum of $1,000 in respect of item 10.
- Pursuant
to
s 36
(1)(c) of the
Building Services (Complaint Resolution and
Administration) Act 2011
(WA), the respondent pay to the applicants
compensation in the sum of $200 per night for the cost of alternative
accommodation while
the roof is being remediated (in respect of item 51).
Table
|
CC 173 of 2022
|
Item No:
|
Scope of works necessary
|
2
|
Waterproof and seal the entire external zero lot brick wall and brick
joints to prevent moisture passing through the brick wall.
|
Table
|
CC 1233 of 2020 and CC 1572 of 2020 –
Items of Complaint
|
Item No:
|
Scope of works necessary
|
2
|
Replace and install the doors so that the clearance between the doors and
the frame is equal and parallel. The installation of the
doors is to include
the painting of all edges equal to the face, so the material is not affected by
moisture. All work is to be done in a proper and proficient manner protecting
all adjacent surfaces. The respondent is to remove all building rubbish from
site
|
3
|
Remedy the theatre entry doors so they comply with Australian Standard
2688:2017 Timber and composite doors item 4.1.2, item 5.3.3.3,
Australian
Standard 1909 - 1984 Installation of timber door sets item 7.1, and item 7.2.
All work is to be done in a proper and
proficient manner protecting all adjacent
surfaces. The respondent is to remove all building rubbish from site.
|
4
|
Remedy the front entry doors so they comply with Australian Standard
2688:2017 Timber and composite doors item 4.1.2, Australian Standard
1909 - 1984
Installation of timber door sets item 7.1, and item 7.2. All work is to be done
in a proper and proficient manner protecting
all adjacent surfaces. The
respondent is to remove all building rubbish from site.
|
5
|
The respondent is to remove the doors and door frames to the entries of the
ground floor ensuite and replace with a standard door
frame and door to suite.
All work is to be done in a proper and proficient manner protecting all adjacent
surfaces. The respondent
is to remove all building rubbish from site.
|
6
|
The respondent is to remove the doors and door frames to the entries of the
living room door and replace with a door frame and door
to suite. All work
is to be done in a proper and proficient manner protecting all adjacent
surfaces. The respondent is to remove
all building rubbish from site.
|
7
|
Remove and replace the kitchenette sink so it is in accordance with the
complainant’s selection as noted on the respondent's
tax invoice number -
INV-0105 in a proper and proficient manner protecting all adjacent surfaces.
The respondent is to remove all
building rubbish from site.
|
11
|
The respondent is to remedy the concrete floor slab at the external entry
of the upper floor bathroom, so it complies with Australian
Standard 3600:2018
Concrete structures Table 8.4.3, 17.1.3 Handling, placing and compacting of
concrete and 17.1.4 Finishing of unformed
concrete surfaces. All work is to be
done in a proper and proficient manner protecting all adjacent surfaces. The
respondent is
to remove all building rubbish from site.
|
12
|
The respondent is to remedy the dining room concrete floor slab, so it
complies with Australian Standard 3600:2018 Concrete structures
Table 8.4.3,
17.1.3 Handling, placing and compacting of concrete and 17.1.4 Finishing of
unformed concrete surfaces. All work is
to be done in a proper and proficient
manner protecting all adjacent surfaces. The respondent is to remove all
building rubbish
from site.
|
17
|
The respondent is to remedy the wall tiles inside the recessed feature wall
panels to the front elevation of the home so as to eliminate
the large gaps
around the perimeters of the tile panels. All work is to be done in a proper
and proficient manner protecting all
adjacent surfaces. The respondent is to
remove all building rubbish from site.
|
19
|
The respondent is to remedy the upper floor bathroom ceiling cornices, so
they are installed and comply with Australian Standard 2589:2017
item 4.6 Fixing
of cornices, The Western Australian Guide to Standards and Tolerances item 10.16
Cracking in cornices and item 10.17
Cracking at junctions of dissimilar
materials. Any additional painting is to be in keeping with the colour and
texture of the surrounding
surfaces. All work is to be done in a proper and
proficient manner protecting all adjacent surfaces. The respondent is to remove
all building rubbish from site.
|
20
|
The respondent is to remedy the window and door frame, so they are left
clean and in accordance with the Western Australian Guide
to Standards and
Tolerances item 19.09 Cleaning. All work is to be done in a proper and
proficient manner protecting all adjacent
surfaces. The respondent is to remove
all building rubbish from site.
|
22
|
The respondent is to remedy the alfresco roof gutter above the dining room
sliding door, so a stop end that a manufactured stop end
is installed that
matches the roof gutter profile. All work is to be done in a proper and
proficient manner protecting all adjacent
surfaces. The respondent is to remove
all building rubbish from site.
|
24
|
The respondent is to remedy the garage ceiling cornices so they are
compliant with Western Australian Guide to Standards and Tolerances
item 10.17
Cracking at junctions of dissimilar materials, the cut through pieces of
cornices and drill holes are patched to an industry
standard. The respondent is
to repaint the ceilings in accordance with Australian Standard 2311:2017 Guide
to the painting of buildings.
All work is to be done in a proper and
proficient manner protecting all adjacent surfaces. The respondent is to remove
all building
rubbish from site.
|
26
|
The respondent is to remedy the alfresco roof gutter above the dining room
sliding door, so a stop end that a manufactured stop end
is installed that
matches the roof gutter profile. All work is to be done in a proper and
proficient manner protecting all adjacent
surfaces. The respondent is to remove
all building rubbish from site.
|
31
|
The respondent is to remedy the floor tiles to the 1st floor bathroom floor
including the shower floor, so they conform to Australian
Standard 3958.1-2007
Ceramic tiles Part 1:  Guide to the installation of ceramic tiles - Falls in
floor finishes. The respondent is expected to maintain the 1st floor
bathroom
waterproofing in good order during the floor tile remedy works and upon
completion the integrity of the ground floor ensuite waterproofing
is to remain
uncompromised. Other than surface tension, water from the shower is to be
directed to the floor waste and not pool on
the tiles. The remedial tiling
is to be in keeping with the colour and texture of the existing tiles and grout.
All work is to be
done in a proper and proficient manner protecting all
adjacent surfaces. The respondent is to remove all building rubbish from
site.
|
33
|
The respondent is to remedy the internal stair timber skirting so as to get
a uniform finish with no broken sections in the skirting
from the base of the
stairs to the top landing. All work is to be done in a proper and proficient
manner protecting all adjacent
surfaces. The respondent is to remove all
building rubbish from site.
|
39
|
The respondent is to remedy the upper floor ceiling access panel by
painting the panel in accordance with Australian Standard 2311:2017
Guide to the
painting of buildings. All work is to be done in a proper and proficient
manner protecting all adjacent surfaces.
The respondent is to remove all
building rubbish from site.
|
40
|
The respondent is to remedy the ground floor ensuite bath tap mixer, so it
is installed as per the manufacturer's specification and
Australian Standard
3740-2010 item 3.10 Penetrations 3.10.1 Shower areas. The respondent is to
remove the overspread of flexible
sealant from the face of the tiles.
All work is to be done in a proper and proficient manner protecting all
adjacent surfaces.
The respondent is to remove all building rubbish from
site.
|
46
|
The respondent is to remedy the removed concrete paving below the gas meter
box, the new paving is to be of similar colour and texture
to the existing. All
work is to be done in a proper and proficient manner protecting all adjacent
surfaces. The respondent is to
remove all building rubbish from
site.
|
47
|
The respondent is to remedy the front entry doors and door frame by
cleaning the plaster smears and painting the doors and door frame
in accordance
with Australian Standard 2311:2017 Guide to the painting of buildings. The
respondent is to remove the glue from the
front entry door reveals so the wall
plaster is readied for painting. All work is to be done in a proper and
proficient manner protecting
all adjacent surfaces. The respondent is to
remove all building rubbish from site.
|
49
|
The respondent is to install the upper floor kitchenette oven as per the
manufacturer's specifications. All work is to be done in
a proper and
proficient manner protecting all adjacent surfaces. The respondent is to remove
all building rubbish from site.
|
51 (Lower roof only)
|
The respondent is to remedy the entire roof tiles and guttering so they
comply with the manufacturer's technical information and standards
guide, and
the National Construction Code - 2016 Volume Two - item F2.2.1 Surface water.
The respondent is to remedy all gaps,
cracked and damaged tiles and
complete the installation of the roof tiles, flashings and sarking so that
moisture ingress does not
occur. All work is to be done in a proper and
proficient manner protecting all adjacent surfaces. The respondent is to
remove all
building rubbish from site.
|
52
|
The respondent is to remedy the garage ceiling cornices so they are
compliant with Western Australian Guide to Standards and Tolerances
item 10.17
Cracking at junctions of dissimilar materials, the cut through pieces of
cornices and drill holes are patched to an industry
standard. The respondent is
to repaint the ceilings in accordance with Australian Standard 2311:2017 Guide
to the painting of buildings.
All work is to be done in a proper and
proficient manner protecting all adjacent surfaces. The respondent is to remove
all building
rubbish from site.
|
53
|
The respondent is to remedy the wall plaster chips to the theatre and
sitting rooms around the high and low gas vents. All work is
to be done in a
proper and proficient manner protecting all adjacent surfaces. The respondent
is to remove all building rubbish
from site.
|
54
|
The respondent is to remedy the external cavity perimeter wall weepholes,
so they are installed as per the manufacturer's installation
guide. All work is
to be done in a proper and proficient manner protecting all adjacent surfaces.
The respondent is to remove all
building rubbish from site.
|
56
|
The respondent is to remove the doors and door frames to bedroom 2 ensuite
entry and the garage external rear pedestrian door and
replace them with a
standard entry door frames and doors to suite. The respondent is to paint
finish the newly installed doors and
door frames in a similar colour and texture
finish to existing. All work is to be done in a proper and proficient manner
protecting
all adjacent surfaces. The respondent is to remove all building
rubbish from site.
|
57
|
The respondent is to remedy the roof gutters surrounding the laundry, so
they are compliant with the National Construction Code Volume
Two, 2016 item
3.5.2.4 Installation of gutters. The respondent is to remedy the roof tiles, so
they comply with the manufacturer's
technical information and standards guide,
and the National Construction Code - 2016 Volume Two - item F2.2.1 Surface
water. All
work is to be done in a proper and proficient manner protecting all
adjacent surfaces. The respondent is to remove all building
rubbish from
site.
|
65
|
The respondent is to remedy the unprotected cabinet panels to the kitchen,
vanities, alfresco, kitchenette and laundry so they are
compliant with
Australian Standard 4386:2018 Cabinetry in the built-in environment - Commercial
and domestic - 6.3.2 Surface finishes
and 6.3.6 Exposed edges.
The respondent is to close the openings in the bases of all cabinets just
above the kick boards. All work
is to be done in a proper and proficient manner
protecting all adjacent surfaces. The respondent is to remove all building
rubbish
from site.
|
66
|
The respondent is to remedy the gap below the ceiling cornice and the chips
to the alfresco wall plastering. The wall plaster repairs
must be of similar
colour and texture to the existing, this may require repaired areas to be
re-texture coated to the nearest architectural
breaks in order to achieve a
consistent and uniform finish. All work is to be done in a proper and
proficient manner protecting
all adjacent surfaces. The respondent is to
remove all building rubbish from site.
|
I certify that the preceding paragraph(s)
comprise the reasons for decision of the State Administrative Tribunal.
MS V Haigh, MEMBER
5 SEPTEMBER 2022
[1] Exhibit 1 pages
13 to 42.
[2]
Waldron and Afra Construction Pty Ltd [2013] WASAT 207
at [14]; approved in Lewis and Waco Pty Ltd
[2016] WASAT 127 at
[14].
[3]
Owners of Strata Plan 59377 and Carine Homes Pty Ltd
[2014] WASAT 39 at
[23].
[4]
Diploma Construction (WA) Pty Ltd v South Central WA Pty Ltd
[2015] WASC 289 at
[31].
[5] Total
Investments Pty Ltd and Rapley Wilkinson Pty Ltd
[2015] WASAT 29 at
[32].
[6] Exhibit
1.
[7] Exhibit 2
pages 610-619; and Exhibit
1.
[8] Exhibit
3.
[9] Exhibit
4.
[10] Exhibit
5.
[11] Exhibit
12.
[12] Exhibit
6.
[13] Exhibit
7.
[14] Exhibit
8.
[15] Exhibit
9.
[16] Exhibit
10.
[17] Exhibit
11.
[18] Exhibit
13.
[19] Exhibit
12.
[20] Exhibit
14.
[21] In respect
of his report at page 465-499 of Exhibit
1
[22] In respect
of his report at pages 501-514 of Exhibit
1.
[23] In respect
of his report at page 417-464 of Exhibit
1.
[24] In respect
of his report at pages 545-522 of Exhibit
1.
[25] ts 248, 16
December 2021.
[26]
ts 252, 16 December
2021.
[27] Exhibit
5.
[28] Items 9,
13, 15, 27, 32, 34, 35, 36, 37, 41, 50, and
72.
[29] Items 2,
3, 4, 5, 6, 7, 11, 12, 17, 19, 20, 22, 24, 26, 31, 33, 39, 40, 46, 47, 49, 52,
53, 54, 56, 57, 65 and
66.
[30] ts 6, 15
December 2021 and ts 26 and 27, 17 June
2022.
[31] ts
28-30, 17 June
2022.
[32] ts 193,
16 December
2021.
[33] Exhibit
1pages 40-42.
[34]
Exhibit 1 page
184.
[35] Exhibit 1
pages 40 and
467-468.
[36]
Exhibit 1 page
117.
[37] ts 59, 15
December 2021.
[38]
Exhibit 1 page
26.
[39]
Bellgrove v Eldridge [1954] HCA 36;
(1954) 90 CLR 613 at
[7].
[40] ts 203,
16 December
2021.
[41] ts 223,
16 December
2021.
[42] ts 58,
17 June 2022.
[43]
Exhibit 5
[44]
Exhibit 1 page
508.
[45] Exhibit 1
page 505.
[46]
Exhibit 4.
[47]
Exhibit 1 page
87.
[48] ts 91, 15
December 2021.
[49]
ts 91, 15 December 2021.
[50] ts 92 and 95,
15 December
2021.
[51] ts 46,
17 June 2022.
[52]
Exhibit 1 page
61.
[53] Exhibit 1
pages 80-89.
[54]
Exhibit 1, page
87.
[55] Exhibit 1
page 61.
[56] ts
99-100, 15 December
2021.
[57] ts
183-184, 16 December
2021.
[58] ts 184,
16 December
2021.
[59] ts 103,
15 December
2021.
[60] Exhibit
9.
[61] Exhibit
5.
[62] Exhibit 1
page 438.
[63] ts
239, 16 December
2021.
[64] ts 74,
15 December
2021.
[65] Exhibit
1 page 477.
[66]
Exhibit 1 page
61.
[67] ts 61, 15
December 2021.
[68] Exhibit 1
page 439.
[69]
Exhibit 1 page 600; ts 218, 16 December
2021.
[70] Exhibit
4.
[71] Exhibit 1
pages 66-67.
[72]
Exhibit 1 page
39.
[73] ts 217, 16
December 2021.
[74]
Exhibit 1 page
39.
[75] ts 104, 17
June 2022.
[76] ts
37 and ts 38, 15 December
2021.
[77] Exhibit
5.
[78] Exhibit
4.
[79] Exhibit 1
pages 138 and 378; Exhibit
6.
[80] ts 243, 16
December 2021.
[81]
Exhibit 7.
[82] ts
37-41, 17 June
2022.
[83] ts 39,
17 June 2022.
[84]
ts 40, 17 June
2022.
[85] Exhibit
1 page 484.
[86] ts
30, 15 December
2021.
[87] Exhibit
1 pages
545-565.
[88] ts
45, 15 December
2021.
[89] Exhibit
1 page 469.
[90] ts
74-75, 15 December
2021.
[91] ts 164,
16 December
2021.
[92] ts 164,
16 December
2021.
[93] Exhibit
1 pages 465-500.
[94] ts 93, 17
June 2022.
[95]
Exhibit 11 page
5.
[96]
Gemmill Homes Pty Ltd v Sanders [2018] WASC 179
(Gemmill) at
[134].
[97]
Gemmill at
[147].
[98]
Hippydayze at
[126].
[99]
Nelson v Mardesic (1998) 22 SR (WA) 42 at
46.
[100]
Jennings and Howitt [2019] WASAT 133 at
[31].
[101]
Exhibit 1 page
598.
[102]
Exhibit 1, page 399 to
416
[103] Exhibit
1, page 170
[104]
Exhibit 1 page
136.
[105]
Exhibit 1 page
584.
[106]
Exhibit 3.
[107]
ts 192-193, 16 December
2021.
[108]
Exhibit 1 page
35.
[109] ts 23,
15 December 2021.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/wa/WASAT/2022/79.html