AustLII Home | Databases | WorldLII | Search | Feedback

Supreme Court of Western Australia

You are here: 
AustLII >> Databases >> Supreme Court of Western Australia >> 2020 >> [2020] WASC 302

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Context | No Context | Help

WESTGEM INVESTMENTS PTY LTD v COMMONWEALTH BANK OF AUSTRALIA LTD [No 6] [2020] WASC 302 (27 August 2020)

Last Updated: 2 September 2020

JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA

IN CIVIL

CITATION : WESTGEM INVESTMENTS PTY LTD v COMMONWEALTH BANK OF AUSTRALIA LTD [No 6] [2020] WASC 302

CORAM : TOTTLE J

HEARD : 3 - 5, 9 - 11, 16, 24, 26 APRIL 2018; 2-4, 7, 9, 16, 22 - 23, 28 - 29, 31 MAY 2018; 5, 7, 11 - 12, 18 - 22, 28 JUNE 2018; 16 - 20, 23 - 27 JULY 2018 & 6 AUGUST 2018

DELIVERED : 27 AUGUST 2020

FILE NO/S : CIV 2722 of 2012

BETWEEN : WESTGEM INVESTMENTS PTY LTD (RECEIVERS AND MANAGERS APPOINTED) (IN LIQUIDATION) in its own right and as trustee for: (1) HOSSEAN POURZAND & JENNY MARIA POURZAND as trustees for THE HELEN TRUST; and (2) PAKWEST PTY LTD (RECEIVERS AND MANAGERS APPOINTED) as trustee for: (A) NEWPORT SECURITIES PTY LTD (RECEIVERS AND MANAGERS APPOINTED) (CONTROLLERS APPOINTED) as trustee for THE PAKWEST TRUST; and (B) OAKCURE PTY LTD as trustee for THE PARRY TRUST

First Plaintiff

HOSSEAN POURZAND in his own right and as trustee for THE HELEN TRUST & THE SHERIN TRUST & THE POURZAND FAMILY TRUST

First Named Second Plaintiff

JENNY MARIA POURZAND in her own right and as trustee for THE HELEN TRUST & THE SHERIN TRUST & THE POURZAND FAMILY TRUST

Second Named Second Plaintiff

PAKWEST PTY LTD (RECEIVERS AND MANAGERS APPOINTED) in its own right and as trustee for NEWPORT SECURITIES PTY LTD (RECEIVERS AND MANAGERS APPOINTED) (CONTROLLERS APPOINTED) and as trustee for various other companies listed in the statement of claim

Third Plaintiff

NEWPORT SECURITIES PTY LTD (RECEIVERS AND MANAGERS APPOINTED) (CONTROLLERS APPOINTED) in its own right and as trustee for THE PAKWEST TRUST & THE NEWPORT FAMILY TRUST & THE LUKE SARACENI FAMILY TRUST

Fourth Plaintiff

OAKCURE PTY LTD in its own right and as trustee for THE PARRY TRUST

Fifth Plaintiff

SEAPORT PTY LTD (RECEIVERS AND MANAGERS APPOINTED) in its own right and as trustee for THE SEAPORT TRUST

Sixth Plaintiff

LUKE SARACENI

Seventh Plaintiff

MAYPORT NOMINEES PTY LTD (RECEIVERS AND MANAGERS APPOINTED) in its own right and as trustee for THE MAYPORT UNIT TRUST

Eighth Plaintiff

QUEEN STREET PROPERTIES PTY LTD in its own right and as trustee for THE QUEEN STREET PROPERTIES TRUST

Ninth Plaintiff

GRAND EDITION PTY LTD (RECEIVERS AND MANAGERS APPOINTED) in its own right and as trustee for THE FARAH INVESTMENT TRUST NO 4

Tenth Plaintiff

LMS HOLDINGS PTY LTD as trustee for THE SARACENI FAMILY TRUST

Eleventh Plaintiff

TOKYO CITY PTY LTD as trustee for THE TOKYO CITY TRUST

Twelfth Plaintiff

MAREE SARACENI PTY LTD as trustee for THE TOKYO CITY TRUST & THE LUKE SARACENI FAMILY TRUST

Thirteenth Plaintiff

MAREE ANN SARACENI

Fourteenth Plaintiff

SINGLE HOLDINGS WA PTY LTD as trustee for THE TUART INVESTMENTS UNIT TRUST

Fifteenth Plaintiff

SARACEN PROJECT MANAGEMENT PTY LTD as trustee for THE SARACEN PROJECT MANAGEMENT TRUST

Sixteenth Plaintiff

CARDUP INDUSTRIAL LAND HOLDINGS PTY LTD in its own right and as trustee for THE CARDUP INDUSTRIAL LAND TRUST & THE CARDUP INDUSTRIAL LAND TRUST NO 2

Seventeenth Plaintiff

GOLDCUP NOMINEES PTY LTD as trustee for THE PAKWEST TRUST

Eighteenth Plaintiff

GOLDEN WEST PROPERTIES PTY LTD as trustee for THE POURZAND FAMILY TRUST & THE OZRA TRUST & THE GOLD HOUSE TRUST & JENNY'S TRUST

Nineteenth Plaintiff

AND

COMMONWEALTH BANK OF AUSTRALIA LTD

First Defendant

WESTPAC ADMINISTRATION 2 LTD

Second Defendant

WESTPAC ADMINISTRATION 3 LTD

Third Defendant

FILE NO/S : COR 77 of 2014

BETWEEN : BRYAN KEVIN HUGHES as liquidator of WESTGEM INVESTMENTS PTY LTD (IN LIQUIDATION) (RECEIVERS AND MANAGERS APPOINTED)

Plaintiff

AND

COMMONWEALTH BANK OF AUSTRALIA LTD

First Defendant

WESTPAC ADMINISTRATION 2 LTD

Second Defendant

WESTPAC ADMINISTRATION 3 LTD

Third Defendant

FILE NO/S : CIV 1596 of 2011

BETWEEN : COMMONWEALTH BANK OF AUSTRALIA LTD

Plaintiff

AND

LUKE SARACENI

Defendant

FILE NO/S : CIV 1651 of 2011

BETWEEN : COMMONWEALTH BANK OF AUSTRALIA LTD

Plaintiff

AND

TOKYO CITY PTY LTD as trustee for THE TOKYO CITY TRUST

Defendant

FILE NO/S : CIV 1652 of 2011

BETWEEN : COMMONWEALTH BANK OF AUSTRALIA LTD

Plaintiff

AND

LMS HOLDINGS PTY LTD as trustee for THE SARACENI FAMILY TRUST

Defendant


Catchwords:

Banking - Incorporation of Code of Banking Practice 2004 into commercial finance agreement - Where offer to enter into commercial finance agreement made by two banks only one of which had adopted Code of Banking Practice 2004 - Whether customer accepted an offer by bank to be bound by Code of Banking Practice 2004 - Where obligation to provide finance a joint obligation - Where offer to provide finance on terms inconsistent with Code of Banking Practice 2004 - Code of Banking Practice 2004 not incorporated into financial agreement

Banking - Construction of Code of Banking Practice 2004 - Meaning of customer - Meaning of small business - Meaning of expression '20 full time or equivalent people' - Where customer had one director and no employees - Where customer's business a commercial property development - Where trusts held ownership interests in development - Where consultants and contractors engaged in development - Beneficiaries of trusts and employees of contractors not to be counted as 'people' of the customer - Customer a small business

Contracts - Construction and interpretation of contracts - General principles - Commercial finance agreement - Where agreement contained defined terms - Where defined terms yield to context - Meaning of the terms Cost to Complete and Cost Overrun - Meaning of the term Provisional Sum - Meaning of the term 'certified by Project Certifier' - Whether contractual provisions applied correctly by defendant banks

Contracts - de minimis principle - Where obligation on parties to serve notice in writing - Where notice given orally - Whether de minimis principle engaged - Failure to serve a notice of default in accordance with terms of commercial finance agreement not a de minimis departure

Contracts - Implied terms - Implication of terms as a matter of proper construction - Whether parties must have intended term to apply - Implication of ad hoc terms - Whether terms necessary for business efficacy - Whether terms inconsistent with express terms - Turns on own facts

Contracts - Implied terms - Where contractual discretion or power to exercise rights on event of default - Whether terms to be implied that discretion or power to be exercised only if event established objectively - Term not implied

Contracts - Implied terms - Whether term of reasonableness in relying upon contractual provisions implied into commercial finance agreements - Where term not implied by law in agreement - Where term not capable of being implied by construction - Where term not necessary to give business efficacy - Where term incompatible with express terms of the agreement - Term not implied

Contracts - Implied terms - Whether term to be implied that party to commercial finance agreement unable to rely on counterparty's non-performance or default if party caused or materially contributed to non-performance or default - Ambit of principle of construction that party cannot take advantage of own breach of contract - Term not implied

Corporations - Insolvency - Pt 5.7B Corporations Act 2001 (Cth) - Voidable transactions - Meaning of insolvent transactions - Meaning of uncommercial transactions - Whether transactions uncommercial - Whether reasonable person in company's circumstances would have entered transactions - Turns on own facts

Corporations - Insolvency - Pt 5.7B Corporations Act 2001 (Cth) - Voidable transactions - Meaning of 'transaction' - Where third parties gave guarantees and securities in respect of company's borrowings - Whether third party transactions 'transactions of the company' - Whether statutory intention against setting aside third party agreements - Where no statutory intention present - Third party agreements transactions 'of' the company

Corporations - Insolvency - Pt 5.7B Corporations Act 2001 (Cth) - Voidable transactions - Meaning of unfair loans - Whether loans extortionate as to interest or charges - Where no evidence led as to usual industry practice concerning interest or charges - Where lack of evidence not decisive - Transactions not unfair loans

Corporations - Insolvency - Pt 5.7B Corporations Act 2001 (Cth) - Voidable transactions - Meaning of insolvency - Cash flow test of insolvency - Use of hindsight - Sources of financial support - Whether support from shareholders enabled company to maintain solvency - Whether forbearance from creditors enabled company to maintain solvency - Whether company could sell its major asset to maintain solvency - Essential business asset principle - Where company unable to pay its debts as and when they fell due - Where company in state of endemic illiquidity - Company insolvent

Corporations - Insolvency - Pt 5.7B Corporations Act 2001 (Cth) - Voidable transactions - Statutory defences - Section 588FG(2) Corporations Act 2001 (Cth) - Principles applicable to defences - Where evidence of knowledge of insolvency - Defences not established - Where unnecessary to rely on defences because transactions not uncommercial

Estoppel - Estoppel by deed - Relevant principles - Whether plaintiff is estopped from asserting case inconsistent with admissions in deed - Plaintiff estopped

Misleading or deceptive conduct - Contextual silence - Whether reasonable expectation of financier disclosing borrower's ability to meet payment obligations from finance facilities - Where no reasonable expectation of disclosure - Whether statements made misleading or deceptive in relation to borrower's capacity to meet payment obligations from finance facilities - Where statements did not convey misleading or deceptive connotations - Misleading or deceptive conduct not established

Misleading or deceptive conduct - Loss and damage - Causation - Misrepresentation in respect of control over asset to be given as security - Lack of control over secured asset revealed after agreement entered into - Where agreement would have been entered on the same terms even if true position concerning control of asset was known - Where no loss flowing from misleading conduct

Unconscionable conduct - Statutory unconscionability - Section 12CC of the Australian Securities and Investments Commission Act 2001 (Cth) - Unconscionability in connection with the supply or possible supply of financial services - Where supply as between sophisticated and well advised parties - Where allegation of extreme commercial pressure - Whether terms of supplies unconscionable - Whether conduct departed from community standards such as to warrant the label of unconscionable - Unconscionability not established

Unconscionable conduct - Statutory unconscionability - Section 12CC of the Australian Securities and Investments Commission Act 2001 (Cth) - Unconscionability in connection with the supply or possible supply of financial services - Asset lending - Whether financier required to satisfy itself of borrower's capacity to meet repayments - Whether supply entered into with knowledge that borrower would default - Where financial supply negotiated at arms-length between well-resourced commercial entities - Whether 'asset lending' unconscionable - Unconscionability not established

Unconscionable conduct - Statutory unconscionability - Section 12CC of the Australian Securities and Investments Commission Act 2001 (Cth) - Whether reliance by financiers on contractual rights unconscionable conduct - Unconscionability not established


Legislation:

Acts Interpretation Act 1901 (Cth), s 15AA
Australian Securities and Investments Commission Act 2001 (Cth), s 12BA, s 12BC, s 12CC, s 12DA, s 12GM
Contracts Review Act 1980 (NSW)
Corporations Act 2001 (Cth), s 9, s 91, s 95A, s 439A, s 508, s 513C, s 588E, s 588FB, s 588FC, s 588FD, s 588FE, s 588FF, s 588FG
Fair Trading Act 1987 (WA), s 5(4), s 9(2), s 10, s 11, s 77
Fair Work Act 2009 (Cth), s 23(1)
Property Law Act 1969 (WA), s 11(2)
Trade Practices Act 1974 (Cth), s 4(2), s 51A, s 51AB, s 51AC, s 52
Transfer of Land Act 1958 (Vic)

Result:

CIV 2722 of 2012:
Plaintiffs' action dismissed save as to the rectification claim and other claims to be determined at a later hearing
Defendants' counterclaim allowed in part

COR 77 of 2014:
Liquidator's action dismissed

CIV 1596 of 2011:
Plaintiff's claim allowed

CIV 1651 of 2011:
Plaintiff's claim allowed

CIV 1652 of 2011:
Plaintiff's claim allowed


Category: A

Representation:

CIV 2722 of 2012

Counsel:

First Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
First Named Second Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Second Named Second Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Third Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Fourth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Fifth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Sixth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Seventh Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Eighth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Ninth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Tenth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Eleventh Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Twelfth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Thirteenth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Fourteenth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Fifteenth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Sixteenth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Seventeenth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Eighteenth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
Nineteenth Plaintiff
:
Mr C R C Newlinds SC, Mr D Miller SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
First Defendant
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh
Second Defendant
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh
Third Defendant
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh


Solicitors:

First Plaintiff
:
Jackson McDonald
First Named Second Plaintiff
:
Jackson McDonald
Second Named Second Plaintiff
:
Jackson McDonald
Third Plaintiff
:
Jackson McDonald
Fourth Plaintiff
:
Jackson McDonald
Fifth Plaintiff
:
Jackson McDonald
Sixth Plaintiff
:
Jackson McDonald
Seventh Plaintiff
:
Jackson McDonald
Eighth Plaintiff
:
Jackson McDonald
Ninth Plaintiff
:
Jackson McDonald
Tenth Plaintiff
:
Jackson McDonald
Eleventh Plaintiff
:
Jackson McDonald
Twelfth Plaintiff
:
Jackson McDonald
Thirteenth Plaintiff
:
Jackson McDonald
Fourteenth Plaintiff
:
Jackson McDonald
Fifteenth Plaintiff
:
Jackson McDonald
Sixteenth Plaintiff
:
Jackson McDonald
Seventeenth Plaintiff
:
Jackson McDonald
Eighteenth Plaintiff
:
Jackson McDonald
Nineteenth Plaintiff
:
Jackson McDonald
First Defendant
:
King & Wood Mallesons
Second Defendant
:
King & Wood Mallesons
Third Defendant
:
King & Wood Mallesons


COR 77 of 2014

Counsel:

Plaintiff
:
Mr C R C Newlinds SC, Mr W A D Edwards, Mr R May & Mr D J Pratt
First Defendant
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh
Second Defendant
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh
Third Defendant
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh


Solicitors:

Plaintiff
:
Jackson McDonald
First Defendant
:
King & Wood Mallesons
Second Defendant
:
King & Wood Mallesons
Third Defendant
:
King & Wood Mallesons


CIV 1596 of 2011

Counsel:

Plaintiff
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh
Defendant
:
Mr C R C Newlinds SC, Mr W A D Edwards, Mr R May & Mr D J Pratt


Solicitors:

Plaintiff
:
King & Wood Mallesons
Defendant
:
Jackson McDonald


CIV 1651 of 2011

Counsel:

Plaintiff
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh
Defendant
:
Mr C R C Newlinds SC, Mr W A D Edwards, Mr R May & Mr D J Pratt


Solicitors:

Plaintiff
:
King & Wood Mallesons
Defendant
:
Jackson McDonald


CIV 1652 of 2011

Counsel:

Plaintiff
:
Mr P J Jopling QC, Mr J A Thomson SC, Ms S E Russell, Mr E A Gisonda & Mr V Ghosh
Defendant
:
Mr C R C Newlinds SC, Mr W A D Edwards, Mr R May & Mr D J Pratt


Solicitors:

Plaintiff
:
King & Wood Mallesons
Defendant
:
Jackson McDonald

Case(s) referred to in decision(s):


Table of Contents


TOTTLE J:

PART 1 - Introduction
  1. Raine Square is a retail and office complex in the centre of Perth. The development of the complex has given rise to the five actions with which this judgment is concerned. The primary parties are Westgem Investments Pty Ltd (in liquidation) and its liquidator on one side and the banks who financed the development on the other.
  2. This litigation is factually detailed and involves claims measured in the hundreds of millions of dollars. An exposition of the many issues that this combination of circumstances generated is not presently required because at the heart of the case there was an issue of contractual construction on which the outcome of Westgem's claims largely depended. That issue concerned the expressions 'Cost to Complete' and 'Cost Overrun' in the principal financing agreement. Unless Westgem succeeded on the construction issue it was difficult for it to succeed on the majority of its claims. I have determined the critical issue against Westgem and for that (and other reasons) Westgem's claims have (with a limited exception) failed. Westgem's failure on the construction issue had an indirect but significant influence on the separate claims made by the liquidator. The liquidator's claims have also failed.
  3. The principals of Westgem were Mr Luke Saraceni and Mr Hossean Pourzand. They were referred to in many contemporaneous documents as the 'Sponsors'. Mr Saraceni and Mr Pourzand and a number of entities associated with them were parties to the relevant transactions as guarantors and security providers. In appendix 1, tables A, B and C I list the capacity in which the parties participated in the various transactions with which the primary action is concerned. In appendix 1, table D I list the people and entities involved as parties to the primary action and the relief sought by them. In this judgment (unless the context indicates otherwise) references to Westgem are references to the parties in the Saraceni and Pourzand camps collectively.
  4. The defendants are the successors to the banks who financed the development. They were known at the relevant times as Bank of Western Australia Ltd (Bankwest) and Bank of Scotland International Australia Limited (BOSI), collectively 'the Financiers'.[1] A company related to BOSI, BOSI Security Services Pty Ltd,[2] was appointed to act as a security trustee (the Security Trustee). I will follow the practice adopted at the trial of using the former names of the Financiers when referring to them individually.
  5. In addition to being one of the two Financiers, Bankwest was the Facility Agent with authority to act on behalf of BOSI and itself in the management of the facilities established under the terms of a Multi‑Option Facility Agreement (the MOFA), the primary financing agreement for the development. In the MOFA the term 'Finance Parties' was defined as, the Facility Agent, the Security Trustee and each Financier.[3] I will adopt that definition in this judgment.
  6. In summary the actions involve:

(a) claims for damages made by Westgem against the Financiers for alleged breach of contract, misleading or deceptive conduct and unconscionable conduct;[4]

(b) claims by guarantors and security providers to have certain guarantees and securities set aside - these claims arise from the same factual substratum on which the claims for damages are based;[5]

(c) claims for the rectification of certain securities;[6]

(d) counterclaims by the Financiers:[7]

(i) for money due by Westgem and the guarantors;

(ii) for damages for misleading or deceptive conduct (also formulated as breach of contract claims) based on conduct that allegedly occurred in the course of negotiations for additional funding required by Westgem in 2010;

(e) claims by the liquidator to set aside certain transactions entered into by Westgem after 25 September 2009 as voidable transactions under Part 5.7B of the Corporations Act 2001 (Cth) (Corporations Act);[8]

(f) claims by Bankwest in what are known as the Seaport Guarantee proceedings to enforce the various guarantees and securities given by Mr Saraceni and entities associated with him.[9]

  1. This judgment determines issues of liability only. Directions were made for the determination of issues of quantum and certain other issues at a separate quantum hearing.
  2. The liability trial was heard between April and July 2018. On 20 June 2019 I heard an application by Westgem to reopen the trial and to allow Westgem the opportunity to amend its pleadings to withdraw certain admissions and to make submissions concerning the extent of liability under some of the guarantees and securities given. On 29 August 2019 I allowed Westgem's application to reopen,[10] and I subsequently ordered that the hearing of the reopened aspects of the case be deferred until after the delivery of this judgment.
An overview of the facts
  1. Mr Saraceni and Mr Pourzand were experienced property developers who had previously worked together on property developments. In September 2004 they incorporated Westgem as a 'special purpose' joint venture vehicle to develop Raine Square. They each held one of two shares issued in Westgem on trust for their related entities and trusts - the ultimate beneficial owners of Raine Square. Mr Saraceni was the sole director of Westgem.
  2. A number of companies related to Mr Saraceni were involved in various managerial capacities in the development. They were:

(a) Saracen Project Management Pty Ltd, the sixteenth plaintiff, appointed to manage the development under an agreement with Westgem made in August 2005.

(b) Saracen Properties Pty Ltd (a company established by Mr Saraceni in 1995 to undertake development projects) was responsible for coordinating and overseeing the financial management and administration of the development.

  1. Mr Mark Clohessy assisted Mr Saraceni and Mr Pourzand in their negotiations with the Financiers. He was closely involved with the financing of the development and played a major role in communicating with the Financiers on behalf of Westgem. Mr Clohessy's company, Security Capital Corporation Pty Ltd, was a licensed finance broker and was a commission agent of Bankwest until September 2008.
  2. Between December 2004 and March 2006 Westgem acquired the Raine Square site with funding from St George Bank Ltd to whom it granted a mortgage over the site. The site is bounded by Wellington Street to the north, William Street to the east, Murray Street to the south, and Queen Street to the west.
  3. In January 2006 Westgem and Bankwest commenced negotiations with a view to Bankwest leasing the office space in the proposed development. The negotiations culminated in the execution by Westgem and Bankwest of a document entitled 'Heads of Agreement' in October 2006. This was followed in April 2009 by an 'Agreement for Lease' (AFL).[11]
  4. In August 2006 Westgem obtained development approval from the City of Perth for a development of 21 levels of office space, three retail levels, three parking levels and a pedestrian tunnel under William Street connecting the William Street underground train station with Raine Square.
  5. In 2007 Westgem arranged for demolition, site retention and earthworks to be undertaken on the site at a cost of approximately $8.5 million.
  6. In December 2007 Westgem and a building company, Salta Constructions Pty Ltd (Salta), entered into a fixed price building contract for the construction of the development (the Salta Building Contract).[12]
  7. On 23 April 2008, Westgem and the Financiers entered into the MOFA for the provision of finance up to a limit of $327.2 million.[13] At the same time guarantees and securities were executed in favour of the Security Trustee. Between April 2008 and November 2010 the MOFA was varied on five occasions by deeds of variation,[14] and on a sixth occasion by a deed entitled 'Deed of amendment and restatement' (the Restated MOFA).[15]
  8. Work under the Salta Building Contract started in April 2008. Problems developed between Salta and Westgem. In December 2008 Salta submitted a revised construction programme that showed a delay of over three months. Between November 2008 and July 2009, 18 Contract Sum Adjustments were issued that increased the construction costs by nearly $10 million.
  9. By July 2009 the relationship between Salta and Westgem had deteriorated to the extent that Salta wanted to negotiate a new contract with a revised and much higher contract price and Westgem wanted to replace Salta with another builder. Both Salta and Westgem were considering the options open to them to terminate the Salta Building Contract.
  10. In 2009 the Financiers became increasingly concerned about escalating construction costs. In July and September 2009 the Financiers maintained, but Westgem disputed, that 'Cost Overruns' (as defined in the MOFA) had occurred. The most significant consequence of the occurrence of a Cost Overrun was that it required Westgem, in reality Mr Saraceni and Mr Pourzand, to contribute equity to the funding of the Project. The July 2009 Cost Overrun (the first Cost Overrun) was paid and a resolution of the differences arising from the September 2009 Cost Overrun (the second Cost Overrun) was achieved in the form of an agreement (termed the 18 November Letter Agreement - albeit that it was finally executed on 1 December 2009) under which the Financiers extended Westgem's time for payment of the second Cost Overrun and Westgem agreed to provide additional securities having a net equity of $50 million.
  11. Although the Financiers maintained that Westgem was in default under the terms of the MOFA they continued to fund the cost of the building work undertaken by Salta but in October 2009 they refused to fund the ancillary costs of the development, principally, consultants' costs, referred to as 'soft costs'. In the course of 2010 the Financiers did fund payment of soft costs on an ad hoc basis.
  12. In late 2009 and early 2010 Charter Hall Funds Management Ltd (Charter Hall) expressed an interest in acquiring Mr Pourzand's interest in the development, which was held by his company Oakcure.
  13. In February 2010 Salta suspended work (Salta Stoppage) and shortly thereafter terminated the Salta Building Contract (Salta Termination). Charter Hall lost interest in acquiring Mr Pourzand's interest in the development at that time. Ultimately, Charter Hall purchased Raine Square when the development was completed.
  14. Between March and September 2010, with very limited exceptions, no building work took place. Progress was, however, made off-site. Westgem found a replacement builder and Westgem and the Financiers negotiated the terms upon which the Financiers would fund the increased cost of completing the development. To facilitate these negotiations the expiry date under the MOFA was extended by deed on 30 June 2010 and again on 31 August 2010.[16]
  15. In September 2010:

(a) Westgem entered into a building contract with Probuild Constructions (Aust) Pty Ltd (the Probuild Building Contract).[17] Probuild took possession of the site and started work.

(b) The Restated MOFA and related securities were prepared and executed between 22 and 24 September 2010.[18] The Restated MOFA increased the Multi-Option Facility Limit to $446 million. The Westgem parties were required to provide additional guarantees and securities. The principal was to be repaid in four tranches. The first repayment of $23 million was due by 30 September 2010 and the second repayment of $27 million by 31 December 2010.

  1. Westgem did not repay $23 million on 30 September 2010 as required by the Restated MOFA. On 15 October 2010 the parties entered into an agreement by which Westgem's default in making the $23 million payment on 30 September 2010 was remedied, the repayment schedule was revised and Westgem was required to repay $50 million by 31 December 2010 (October 2010 Letter Agreement).
  2. Westgem did not make the $50 million payment due on 31 December 2010.
  3. On 11 January 2011 the Financiers appointed Mr Mark Mentha and Mr Clifford Rocke as receivers and managers of the property of Westgem. On the same day Mr Bryan Hughes was appointed as voluntary administrator of Westgem. Westgem went into liquidation on 18 October 2012 and Mr Hughes was appointed liquidator.
  4. On 27 October 2011 Practical Completion was achieved under the Probuild Building Contract and the AFL.
  5. In April 2012 Bankwest took possession of the office premises and started to pay rent.
  6. In August 2012 the retail complex was opened.
An overview of the claims
  1. While there is some overlap between the claims they may be categorised as follows.
Cost Overrun claims
  1. On 22 July 2009, in its capacity as Facility Agent, Bankwest determined that the first Cost Overrun in the amount of $12,920,000 had occurred and on 18 September 2009 it determined that the second Cost Overrun in the amount of $17 million had occurred. The Financiers maintained that each Cost Overrun gave rise to an Event of Default under the MOFA.
  2. The first Cost Overrun was paid by a combination of equity contributed on Westgem's behalf and arrangements that were accepted by the Financiers as the equivalent of equity. The first Cost Overrun did not give rise to a dispute at the time it was determined and paid.
  3. Westgem disputed that the second Cost Overrun had occurred. Protracted and robust negotiations followed and culminated in the 18 November Letter Agreement.
  4. In broad terms Westgem's case involves the following contentions:

(a) The Cost Overruns were not determined in accordance with a proper construction of the applicable provisions of the MOFA. Consequently, they were not validly determined and there were no Events of Default within the meaning of the MOFA. This critical construction argument turns on the meaning of 'Cost to Complete' in the MOFA.

(b) The Code of Banking Practice 2004 (the Banking Code) applied to the MOFA and the provisions of the Banking Code required Bankwest to act 'fairly and reasonably' and 'in a consistent and ethical manner' and by determining the Cost Overruns and maintaining that Westgem was in default the Financiers were in breach of the obligations imposed by the Banking Code.

(c) The assertion by the Financiers of Cost Overruns and defaults constituted breaches of various terms of the MOFA. Westgem argued the terms in question were either implied as a matter of construction of the MOFA or were implied as ad hoc terms.

(d) The conduct of the Financiers in alleging Cost Overruns and defaults constituted misleading or deceptive conduct and unconscionable conduct in contravention of the applicable provisions of the Australian Securities and Investments Commission Act 2001 (Cth) (the ASIC Act) and the Fair Trading Act 1987 (WA) (the FTA).

Salta Stoppage and Salta Termination claims
  1. Westgem argues that the Salta Stoppage and Salta Termination claims result from a chain of causation that extends back to the determination of the Cost Overruns.
  2. The determination of the first Cost Overrun on 22 July 2009 led to a delay in making a payment due to Salta. On 12 August 2009 Salta gave notice to Westgem requiring it to provide evidence to demonstrate its capacity to meet its payment obligations under the Salta Building Contract.[19] By letter dated 21 August 2009 Westgem's solicitors responded to the 12 August 2009 notice and provided Salta with a letter from Bankwest addressed to Westgem containing a statement that:[20]
[T]he availability of future funding remains subject to compliance with the terms of the Multi Option Facility Agreement and other Transaction Documents.
  1. Between September 2009 and February 2010 Salta sent letters and served various contractual notices on Westgem, on the Financiers and on the Security Trustee. Ostensibly Salta's object in taking these steps was for Salta to satisfy itself that Westgem had the funds to pay for work under the Salta Building Contract and, if it was not so satisfied, to ensure that it exercised its rights in compliance with the applicable contractual provisions governing suspension and termination of the work.
  2. Westgem contends that in the period between 20 November 2008 and 25 February 2009 the Financiers did not inform Salta of the true funding position under the MOFA. On Westgem's case the true position was that the Financiers were prepared to allow Westgem to draw on the MOFA irrespective of any subsisting breach, alternatively, Westgem had not committed any breach of the MOFA, or any breach of which the Financiers were aware and were prepared to rely on, which would entitle the Financiers to withhold advances under the MOFA so as to deprive Westgem of its capacity to meet its payment obligations under the Salta Building Contract.
  3. Put shortly, Westgem claims that by not disclosing what it contends was the true position, the Financiers impliedly represented to Salta that Westgem lacked the capacity to meet its payment obligations under the Salta Building Contract by reason of having committed a breach of the MOFA on which it was prepared to rely to withhold drawdowns. Westgem contended Salta relied on this implied representation in making the decision to suspend and thereafter terminate the Salta Building Contract.
  4. Westgem claims that the Financiers' conduct constituted misleading or deceptive conduct and unconscionable conduct in contravention of the applicable statutory provisions.
  5. Westgem further claims its loss included losses flowing from the delay in completing the development and the additional costs involved. This claimed loss gives rise to a substantial subsidiary issue because the Financiers contend that Westgem would not have been able to complete the development in any less time or at any less cost had the impugned conduct not taken place, and thus did not suffer any loss.
  6. Separately Mr Pourzand and his interests claim that if Salta had not suspended and then terminated the Salta Building Contract, Charter Hall would have acquired the Pourzand interest in Raine Square, and it would thereafter have stood behind Westgem and enabled the Project to proceed to Practical Completion.
The Combination claim and the Restated MOFA claim
  1. In its written submissions Westgem characterise this claim as one 'to be understood principally as an extension of causation by the [Cost Overrun claims and the Salta Stoppage and Salta Termination claims]'.[21] The submissions went on to explain that because of the cumulative wrongdoings of the Financiers the Westgem parties were left with no choice but to accede to demands by the Financiers to sign the Restated MOFA and provide the additional guarantees and securities.
  2. The Westgem parties contend that the Financiers acted unconscionably in contravention of the ASIC Act and in breach of contract by taking additional guarantees and securities under the Restated MOFA when they knew that it was impossible for Westgem to make the payment of $23 million by 30 September 2010. The Westgem parties contend that the Restated MOFA lacked 'any shred of commerciality' and was simply a vehicle to prolong Westgem's life long enough for the Financiers to improve their security position.
The guarantors' claims
  1. The guarantors apply to set aside the guarantees and securities provided pursuant to the 18 November Letter Agreement and the Restated MOFA. The success of these claims is dependent on the success of the primary claims by the Westgem parties.
The guarantors' rectification claims
  1. The guarantors' rectification claims can be divided into two groups. First the MOFA Share Mortgage rectification claim and secondly the Second Additional Securities rectification claims.[22] It is unnecessary to refer to either of these claims in detail.
  2. The MOFA Share Mortgage was one of several security instruments executed contemporaneously with the MOFA in favour of the Security Trustee. The MOFA Share Mortgage granted a mortgage to the Security Trustee over the shares held by Mr Saraceni and Mr Pourzand in Westgem. A number of limited guarantees were also executed at the same time as the MOFA Share Mortgage. In essence Westgem pleaded that the parties to the MOFA commonly intended the MOFA Share Mortgage to be limited to the same extent of liability as the limited guarantees, namely to limit liability under the MOFA Share Mortgage to $20 million. The Financiers accept that this was the parties' common intention and accepted that at any hearing as to quantum, liability under the MOFA Share Mortgage would be so limited.
  3. The basis of the proposed rectification of the Second Additional Securities is explained in detail in my judgment concerning Westgem's application to reopen the trial.[23] The hearing of these claims has been deferred until after the delivery of this judgment.
The Vasse Newtown counterclaim
  1. The Financiers claim that they executed the Restated MOFA on the understanding that Mr Saraceni through companies associated with him owned a 66.67% interest in a land development known as the Vasse Newtown project. The Financiers contend that in the course of negotiations about the terms upon which they might finance the completion of Raine Square, Mr Saraceni and Mr Clohessy made representations to the effect that Mr Saraceni's interest in the Vasse Newtown project was being marketed for sale and the proceeds of sale would be sufficient to enable Mr Saraceni to apply not less than $17 million in repayment of the principal under the Restated MOFA. In fact, on 27 August 2010 the companies which held Mr Saraceni's interest in the Vasse Newtown project entered into a transaction reducing their interest to a minority interest of 49% for a consideration that included a cash component of $7,236,591. Rather than the cash being applied to the repayment of the principal due to the Financiers, Mr Saraceni used the funds for purposes unrelated to Raine Square. The Financiers contend that Mr Saraceni engaged in misleading or deceptive conduct and had they known the true position in relation to the reduction in Mr Saraceni's interest in Vasse Newtown they would not have entered the Restated MOFA.
The Financiers' money claims
  1. The Financiers have claims under the Restated MOFA for the amounts due to them after taking into account the amount recovered from the sale of Raine Square in 2013 and the amounts recovered from the realisation of various securities. At the commencement of the trial the Financiers stated that the debt due to them stood at over $200 million.
  2. The Financiers' money claims include a claim for default interest under the MOFA. Westgem contends that there was no entitlement to claim default interest.
The liquidator's voidable transactions claims
  1. The liquidator seeks orders setting aside transactions entered into by Westgem after 25 September 2009 on the grounds that they were voidable transactions under Part 5.7B of the Corporations Act. The primary issues in these proceedings are whether Westgem was insolvent from September 2009 and whether a number of transactions (principally the 18 November Letter Agreement and the Restated MOFA) were uncommercial transactions.
Bankwest's Seaport Guarantor claims
  1. Bankwest has claims based on guarantees and securities given by Mr Saraceni and entities related to him as security for facilities granted by it to Seaport. The guarantors and security providers have sought to set off their damages claims against Bankwest's claims under the guarantees and securities. It was agreed that the outcome in these proceedings would be determined by the outcome of Westgem's claims for damages.
The evidence
  1. The events with which this litigation is concerned occurred many years before the trial. In making factual findings I have paid close attention to the record of events found in contemporaneous documents. As one would expect given the subject matter of the litigation and the length of the period over which events unfolded, the documentary record was extensive. An indication of the volume of documentary material adduced in evidence is provided by the length of the tender lists. Westgem's combined tender lists totalled approximately 229 pages, while the Financiers' list of documents referred to in their witness statements alone totalled 267 pages. The combined Financiers' tender lists, including documents referred to in expert evidence, comprised of over 9,785 documents. What was termed the 'core bundle' contained in excess of 14,000 pages of material representing approximately 10% of the total trial library.
  2. It is impossible to obtain a complete understanding of events from documents and in this respect the decision of Westgem not to adduce any lay evidence was surprising given the nature of the claims made by it and against it (and related parties) and the fact that before the trial commenced Westgem had foreshadowed calling a number of witnesses, including Mr Saraceni, Mr Pourzand and Mr Clohessy. The absence of any factual evidence from witnesses called on Westgem's behalf made it difficult to obtain a full appreciation of Westgem's position on various issues. With justification the Financiers described the absence of any oral evidence on Westgem's part as a 'glaring omission' and invited the court to draw adverse inferences consistent with the principles established in the case of Jones v Dunkel.[24] For their part, however, the Financiers filed and served witness statements for witnesses involved in important events (Mr Nagle, Mr Nathan and Mr Galbraith) but whom they did not call to give evidence, and the Jones v Dunkel point was raised against them. In the event, in the course of making factual findings I have not found it necessary to rely on inferences drawn in accordance with the Jones v Dunkel principles.
  3. Westgem made a limited number of criticisms of the credit and reliability of the Financiers' witnesses. I have dealt with those criticisms in the course of making factual findings in the context of the evidence to which they related and general observations on the credit and reliability of the witnesses are not required. I am acutely conscious of the elapse of time between hearing the relevant evidence and the delivery of this judgment and the potential effect of the passage of time on my recollection of the evidence and the witnesses. This litigation and the preparation of this judgment are matters that have never been far from my mind since the trial concluded. The limited number of credit issues meant that when they were raised in evidence, they formed an immediate and, I consider, lasting impression, and, of course, I have had the opportunity to refresh my memory by referring to the transcript.
Approach to the issues
  1. In this judgment I have confined myself to determining those issues necessary to dispose of the claims. In particular (with one exception), I have not dealt with the positive defences raised by the Financiers. This should not be understood as a criticism of the Financiers for raising those defences, there was a lot at stake in this litigation, and it is understandable that the Financiers should avail themselves of all potential defences. Rather I have taken the confined approach to keep the preparation of this judgment and its length within manageable proportions.
PART 2 - Cost Overrun claims
Structure of Part 2
  1. This part of the reasons comprises:

(a) a summary of the conclusions in respect of the Cost Overrun claims;

(b) an overview of the transaction documents;

(c) the framework of the Cost Overrun claims:

(i) the construction issue;

(ii) the implied terms;

(iii) the unconscionable conduct and misleading or deceptive conduct claims;

(d) the construction of the Cost Overrun provisions;

(e) the MOFA terms for which Westgem contends;

(f) factual findings in relation to the first Cost Overrun;

(g) the first Cost Overrun contractual claims;

(h) the first Cost Overrun statutory unconscionability claims;

(i) factual findings in relation to the second Cost Overrun;

(j) the second Cost Overrun contractual claims;

(k) the second Cost Overrun statutory unconscionability claims;

(l) the misleading or deceptive conduct claims; and

(m) the Financiers' defences.

Summary of conclusions
  1. I have concluded that Westgem's Cost Overrun claims must fail for the following reasons:

(a) I do not accept Westgem's argument on the construction of the term 'Cost to Complete'. As defined in the MOFA, Cost to Complete encompassed the construction costs required to achieve Practical Completion of the development and not merely Practical Completion of the Salta Building Contract.

(b) The Banking Code did not apply to the MOFA.

(c) The terms Westgem contended were incorporated into the MOFA as a matter of construction or as ad hoc implied terms were not terms of the MOFA.

(d) If the terms for which Westgem contended were terms of the MOFA the Finance Parties did not breach those terms.

(e) In particular Bankwest did not unreasonably determine the cost to complete as part of the process of establishing the occurrence of the first and second Cost Overruns.

(f) The evidence - in particular the contemporaneous construction cost forecasts undertaken on Westgem's behalf - established that the first and second Cost Overruns occurred. Thus, even if there were breaches by the Finance Parties as alleged by Westgem those breaches were not causative of any loss.

(g) The Finance Parties did not act unconscionably.

(h) By maintaining that the first and second Cost Overruns had occurred the Finance Parties did not engage in misleading or deceptive conduct.

The Transaction Documents The MOFA
  1. The MOFA was a financial agreement extending (inclusive of schedules) to 128 pages. It was a relatively complex commercial agreement that operated in conjunction with the Building Contracts and a deed known as the Builder's Side Deed and the securities held by the Security Trustee. The MOFA was negotiated between September 2007 and April 2008 following the submission by the Financiers of a 'Financing proposal' to Westgem on 6 September 2007.[25]
  2. The principal parties to the MOFA were Westgem as borrower, the Financiers, Bankwest as Facility Agent and the Security Trustee.
  3. Westgem was a party to the MOFA in its own right and, separately, as the trustee for the trustees of other trusts that held the title to two distinct areas of the Raine Square site referred to in the MOFA as 'Raine Square Area 1'[26] and 'Raine Square Area 2'.[27]
  4. A mortgage was granted by Westgem to the Security Trustee over the Raine Square site,[28] along with a fixed and floating charge over Westgem's assets.[29] As described earlier Mr Saraceni and Mr Pourzand executed the MOFA Share Mortgage as a mortgage over their respective shares in Westgem.
  5. Mr Saraceni and Mr Pourzand in their own rights, and the other Transaction Parties listed in appendix 1 and identified as MOFA Guarantors were parties to the MOFA as guarantors.[30] The liability of the MOFA guarantors was limited to $20 million of the principal debt together with a proportionate amount of interest, costs and other expenses subject to an exception in respect of Cost Overruns and some other presently irrelevant costs. As I will explain later it was of some significance that the guarantors' liability was unlimited in respect of Cost Overruns.
  6. Bankwest's role as Facility Agent and its duties were defined with precision at cl 41 of the MOFA. Its duties were expressed to be 'solely mechanical and administrative in nature' (cl 41.2(5)). As I will explain, this description was not entirely accurate.
  7. The MOFA included a recital entitled 'Introduction' that read as follows:[31]
The Borrower has requested the Financiers to provide it with financial accommodation in connection with the Project.
  1. 'Project' was a defined term. There was some controversy about the definition which I set out later in this judgment.
  2. The 'financial accommodation' referred to in the 'Introduction' was a finance facility. It was defined in cl 1.1(46) of the MOFA as follows:[32]
Facility means:

(a) the Multi-Option Facility;

(b) the Letter of Credit Facility; and

(c) the Overdraft (GST Float) Facility,

and Facilities has a corresponding meaning;
  1. Each of the three Facilities had a Facility Limit. In the case of the Multi‑Option Facility the limit was $316 million, (cl 1.1(77)) and this limit included an amount available for the purpose of funding 'Project contingencies'. The Facility Limit for the Letter of Credit Facility was $8.2 million, (cl 1.1(70)) and the Facility Limit in respect of the Overdraft (GST Float) Facility was $3 million, (cl 1.1(82)). Westgem was obliged to ensure that the amount outstanding in respect of each Facility did not exceed the applicable Facility Limit, (cl 5.1). The Multi-Option Facility and the Letter of Credit Facility were expressed to expire on 30 June 2010, (cl 1.1(45)).
  2. The purpose for which the Facilities might be used by Westgem was specified in cl 3 of the MOFA as follows:[33]
    1. Purpose
Unless otherwise agreed in writing by the Financiers, the Borrower may only use the Facilities for the following purposes:
(1) in respect of the Multi-Option Facility:
(a) to refinance existing liabilities owed by the Borrower:

(i) in its Raine Square Area 1 Capacity, in favour of St George Bank Limited in the amount $9,690,000; and

(ii) in its Raine Square Area 2 Capacity, in favour of St George Bank Limited;

(b) to fund the capitalisation of interest and the line fee and Letter of Credit fee payable under clause 19, in each case in accordance with clause 7.2;

(c) to meet the Borrower's interest rate hedging obligations under the Multi-Option Facility; and

(d) to carry out the Project in accordance with the Approved Project Budget;
(2) in respect of the Letter of Credit Facility, to fund contingent liabilities owed by the Borrower to the Lessee under the terms of the Heads of Agreement; and

(3) in respect of the Overdraft (GST Float) Facility, to meet the on-going GST obligations for the Project.
  1. The Approved Project Budget referred to in cl 3(1)(d) was a defined term, (cl 1.1(8)). I set out the definition later in this judgment. Westgem was required to provide to the Facility Agent prior to the commencement of each calendar month or at any other time reasonably requested by the Facility Agent, a certified copy of the Approved Project Budget, updated to take account of the applicable status of the Project, (cl 15.1(1)(g)).
  2. Westgem was required to satisfy a number of conditions precedent before it could make the first drawing under a Facility, (cl 13.1) and was required to satisfy a further set of conditions precedent before each successive drawing thereafter, (cl 13.2).
  3. Westgem was required to comply with reporting and notification obligations (cl 15.1 and cl 15.3) and comply with 'project undertakings' (cl 15.2). The evident purpose of the reporting and notification obligations provisions was to ensure that the Facility Agent was kept informed of any matters that might affect the financial stability of Westgem, the financial viability of the Project or the adequacy of the security held by the Security Trustee. The evident purpose of the 'project undertakings' obligations was to ensure that the Project was undertaken efficiently and in accordance with the Approved Project Budget. One of the project undertakings required Westgem to conduct Project Control Group meetings no less than once each calendar month and to permit the Facility Agent to participate in those meetings, (cl 15.2(6)). The Project Control Group was constituted by Westgem, Salta and the Project Certifier, (cl 1(94)). Another project undertaking required Westgem to co-operate with any Independent Consultant appointed by the Financiers, (cl 15.15).
  4. Westgem was required to observe financial ratios: a loan to valuation ratio (cl 16.1), a total development costs ratio (cl 16.2) and an interest cover ratio (cl 16.3). I refer to these ratios in more detail later in this judgment. As I will explain the requirement on Westgem to observe these ratios was part of the contractual mechanism by which the Financiers were able to control the credit risk.
  5. The MOFA provided that certain events were 'Events of Default'. These included the failure by Westgem to pay a Cost Overrun within five business days of demand being made by the Facility Agent, (cl 17.22). At any time after the occurrence of an Event of Default the Financiers could, following service of a written notice of demand, take steps to protect their interests including by declaring all moneys due under the Facility to be immediately due and payable and terminating the Financiers' obligations under the MOFA, (cl 18.1(1)).
The Salta Building Contract
  1. The Salta Building Contract was constituted by a formal instrument of agreement,[34] general conditions of contract (GCs),[35] with annexures that included a schedule of provisional sums and a bill of approximate quantities.
  2. Before turning to the provisions of the Salta Building Contract I note that 'Building Contracts' was a term defined in the MOFA as follows:
Building Contracts mean:

(a) the 'Formal Instrument of Agreement - Raine Square', incorporating AS-2124-1992 general conditions of contract and all associated annexures and attachments, dated on or about 20 December 2007; and

(b) any other agreement between the Borrower and the Builder,

for the construction of the Project;
  1. The document referred to in this definition is the Salta Building Contract. In this judgment, for clarity I will refer to the actual agreement with Salta as the Salta Building Contract and will use the expression 'Building Contracts' to refer to the definition in the MOFA. For reasons that will be explored in more detail it is necessary for me to distinguish between 'Building Contracts' as that term appears in the MOFA, and the Salta Building Contract.
  2. The relevant provisions of the Salta Building Contract were as follows:

(a) The contract price was $281,879,573 subject to adjustment for variations, re-pricing of provisional sums, and quantity remeasures.[36] The contract price of $281,879,573 included an allowance of $92,477,218 for provisional sums and $70 million of the provisional sum allowance related to the completion of Bankwest's fit out. $4.3 million of the provisional sum allowance related to the construction of the tunnel under William Street.

(b) Salta was required to execute and complete the 'work under the [Building] Contract', (GC 3.1). The phrase 'work under the [Building] Contract' was defined to mean:[37]

The work which [Salta] is or may be required to execute under the [Building] Contract and includes variations, remedial work, Constructional Plant and Temporary Works.

(c) 'Works' were defined to mean:[38]

The whole of the work to be executed in accordance with the [Building] Contract including variations provided for by the [Building] Contract, which by the [Building] Contract is to be handed over to [Westgem].

(d) Saraceni Project Engineering Pty Ltd, whose sole director and employee was Mr Frank Saraceni, was appointed to act as the superintendent under the Salta Building Contract.[39] Mr Frank Saraceni was Mr Luke Saraceni's brother. In contemporaneous correspondence exchanged between the parties, Mr Frank Saraceni was often referred to as the Superintendent.

(e) The Superintendent was empowered to direct Salta to increase, decrease or omit any part of the work under the Contract or change the character or the quality of any material or work, (GC 40.1). Salta could not vary the work under the Salta Building Contract unless directed by the Superintendent or with the Superintendent's written approval, (GC 40.1).

(f) Practical Completion of the work under the Contract was to be achieved by 28 February 2010, (GC 35.2).

(g) Salta might, on reasonable grounds, request Westgem and, if so requested, Westgem was required to provide to Salta's reasonable satisfaction documentation or evidence that Westgem had the capacity to meet its payment obligations under the Salta Building Contract, (GC 42.1).

  1. Further explanation of the provisions in the Salta Building Contract governing Bankwest's fit out is necessary. As was explained in uncontroversial terms in the Financiers' written opening submissions, fit out works may relate to the installation within a building of essential services, such as electrical, water, air conditioning and fire protection systems - 'service fit out works' - or they may relate to other aspects of the configuration and functionality of the interior of the building - 'non service fit out works'. Fit out works may be carried out concurrently with base build works as 'integrated fit out works' - abbreviated to 'IFO' - or separately as 'Non-integrated fit out works' - 'NIFO'.
  2. When the Salta Building Contract was signed the parties had not decided whether Bankwest would undertake its tenancy fit out works ‑ the subject of the $70 million provisional sum - as IFO or NIFO, and if done as IFO, whether the work would be undertaken by Salta. To cater for this uncertainty GC 11 of the Salta Building Contract, which was the clause that governed the administration of provisional sums, included the following:[40]
[Westgem] shall supply the design documents for the Bankwest Integrated Fitout (the "Fitout") in sufficient time for [Salta] to price the work and for the parties to reach agreement on the price so that [Salta] can meet its obligations under the [Building] Contract.

[Salta] is to allow for and make available adequate resources and personnel in the project to adequately undertake the Fitout works and the maximum preliminaries and profit margin shall not exceed 13% in accordance with the Salta letter dated 13 June 2007.

Despite the other provisions of this contract the [Salta] is not obligated to undertake any work in connection with the Fitout unless [Westgem] and [Salta] reach agreement on the terms and conditions for the work.

In the event that the parties do reach agreement on the price for the Fitout works then [Westgem] shall not be obligated to implement the Further Value Management savings provided for in the Contract Documents. If the parties do not reach agreement on the price for the Fitout works then [Westgem] shall be obligated to implement the Further Value Management savings provided for in the Contract Documents.
  1. The allowance for 'Value Management Savings' was simply an amount - $3.6 million - payable by Westgem to Salta if Salta was not awarded the IFO works. Put another way, it was a discount of $3.6 million allowed by Salta in Westgem's favour in respect of the construction costs in the event that Salta was awarded the IFO works -that this was so, is clear from emails exchanged between Westgem and Salta prior to the execution of the Salta Building Contract.[41] So far as I have been able to establish from the provisions of the Salta Building Contract there were, in fact, no savings that could justify the description 'Value Management Savings'.
  2. The agreement in relation to the $3.6 million nominal allowance for 'Value Management Savings' was varied by an agreement recorded in a letter dated 23 December 2008 signed on behalf of both Westgem and Salta whereby the 'Value Management Savings' were renamed the 'IFO Co-operation Fee'.[42] Westgem and Salta recorded that the Superintendent had issued Salta with instructions to proceed with the mechanical, electrical and fire services, in effect the services fit out, but not the IFO and that:[43]
Salta requires [Westgem], and [Westgem] agrees, to pay a co-operation and co-ordination fee of $3.6m (Co-operation Fee) to Salta for its co‑ordination and provision of access required to undertake the IFO works. The co-operation fee is to be paid as follows:
  1. If Salta is instructed to only undertake the Services component (or part thereof) of the IFO [Westgem] agrees to pay to Salta 50% of the Co-operation Fee as a lump sum payment on or before 31 January 2009 and the remaining 50% in equal monthly instalments of $300,000 plus GST with the first payment at the end of February 2009 and the last payment at the end of January 2010.
  2. If Salta is awarded IFO works other than services, then the site co-operation fee will be deemed fully incorporated into the IFO building contract and will be due and payable in accordance with that contract. However, subject to mutual agreement, further part payment of the co-operation fee may be negotiated.
  1. If [Westgem] pays the co-ordination fee in accordance with the terms of this letter then [Westgem] will not be required to implement the 'Further Value Management' savings pursuant to clause 11.0 of the [Building] Contract.
  1. In a chain of contentious emails in April 2009 the nature of the IFO Co‑Operation Fee was discussed by Mr Sam Tarascio (Managing Director of Salta) and Mr Frank Saraceni. In an email to Mr Frank Saraceni dated 20 April 2009 Mr Tarascio referred to the IFO Co‑Operation Fee as follows:[44]
As you know this fee is not actually an IFO co-ordination fee. It is actually a method of Westgem reimbursing to Salta a discount provided to the contract price at the front end. What we have conceded to date on this is that we are prepared to defer your payment of the balance of the IFO co-ordination fee until we reach practical completion of the project. The amount of $1.8 million already paid by you must remain in place.
  1. Mr Frank Saraceni replied to Mr Tarascio's email and said that he had 'no idea why you keep saying the $3.6M is not a fee you are charging to coordinate and cooperate in regard to the IFO works because that is exactly what we negotiated and signed up for'.[45] Mr Tarascio responded and accused Mr Saraceni of 'simply twisting the truth totally' and said that he was 'extremely frustrated and upset by [Mr Frank Saraceni's] email'.[46] In a subsequent email to Mr Tarascio dated 27 May 2009 Mr Frank Saraceni said that he had spoken to Mr Luke Saraceni and that they both agreed that 'the $3.6M has almost become a cancer on this project'.[47]
Builder's Side Deed
  1. One of the security documents executed on 23 April 2008 pursuant to the MOFA was a deed entitled 'Builder's Side Deed - Raine Square'. The parties to the deed were the Security Trustee, Westgem, Salta and Salta Properties Pty Ltd, a company related to Salta with the capacity to control Salta's affairs. The Builder's Side Deed created privity of contract between Salta, Salta Properties and the Security Trustee and was expressed to govern the way in which various rights in connection with the Salta Building Contract were to be executed.
  2. The Builder's Side Deed conferred rights on the Security Trustee in relation to the performance of the Salta Building Contract including rights:

(a) restricting the capacity of Westgem and Salta to vary the Salta Building Contract without the Security Trustee's consent;

(b) restricting Salta's right to terminate or suspend the Salta Building Contract by requiring notice to be given to the Security Trustee and conferring a right upon the Security Trustee to remedy any remediable default under the Salta Building Contract;

(c) restricting the right of Salta or Salta Properties to obtain security over the development;

(d) to be provided with information about progress under the Salta Building Contract and to participate in 'Project Control Group' meetings;

(e) to compel Salta and Salta Properties to take steps to maintain their financial viability;

(f) arising in the Security Trustee's favour in the event that the Salta Building Contract was terminated;

(g) to 'step in' and take over the Salta Building Contract in the event of a default by Westgem and a right to call upon Salta to novate the Salta Building Contract.

Agreement for Lease (AFL)
  1. The AFL was made on 7 April 2009 between Westgem as 'lessor' and Bankwest as 'lessee' and Pakwest, Newport, Oakcure, Seaport and Mr Pourzand as guarantors of Westgem's obligations.
  2. The AFL recited that the Heads of Agreement had been made by the parties on 19 October 2006 to regulate, among other matters, the development and construction of the 'Complex', the relocation of Bankwest from its existing premises (two office buildings in the Perth CBD) to the office tower in Raine Square, and the lease agreement to govern Bankwest's occupation of the office tower. The AFL provided that the latest completion date for practical completion of the building was 31 December 2010 and Bankwest's obligation to pay rent commenced 120 days after practical completion. The terms of the AFL were not in issue in the context of the claims that ultimately fell for determination. The relationship it established between Westgem and Bankwest as prospective lessor and lessee was an important part of the background against which the disputes unfolded.
  3. The AFL was amended by a series of agreements. I will refer to these agreements in more detail in the course of addressing the liquidator's claims. For present purposes the following summary is sufficient. The first amending agreement was the AFL Supplementary Agreement made on or about 25 September 2009.[48] It settled claims made by Westgem against Bankwest in respect of managing the Integrated Fit Out services and sought to align the provisions of the AFL with those of the Building Contract. The AFL Supplementary Agreement was replaced by the Amended AFL Supplementary Agreement which was executed on 16 September 2010.[49] The Second Supplementary Deed was also executed on 16 September 2010.[50] The Second Supplementary Deed extended the date by which practical completion had to be achieved under the AFL to a date 14 months after the execution of the deed and if practical completion had not been completed within 16 1/2 months after the execution of the deed, Bankwest would have the ability to terminate the AFL. The Second Supplementary Deed included a separate provision relating to the completion of the tunnel and specifying a separate and later practical completion date for the tunnel works.
The framework of the Cost Overrun claims Construction of the Cost Overrun/Cost to Complete provisions
  1. As foreshadowed the proper construction of the Cost Overrun provisions of the MOFA is critical to the determination of these claims. Before going into the detail I will summarise the issue and explain its commercial significance.
  2. The relevant provisions comprise a definition of the term, 'Cost to Complete', which is itself incorporated in the definition of the term 'Cost Overrun'. The purpose served by these provisions was to identify whether a requirement had arisen for Mr Saraceni and Mr Pourzand to contribute equity capital to the funding of the Project.
  3. The issue is whether the determination of the Cost to Complete, and thus a Cost Overrun was to be made:

(a) by reference to the cost of the works which at the date of the determination were required to be completed to achieve Practical Completion under the Building Contracts - the construction favoured by Westgem; or

(b) by reference to the cost of the works necessary to complete the Project - the construction favoured by the Financiers.

  1. The occurrence of a Cost Overrun was significant because:

(a) the conditions precedent to drawings under the MOFA included the provision by Westgem of a certificate from the Project Certifier confirming that the Cost to Complete did not exceed the Undrawn Commitment (a defined term - essentially the funds that remained to be drawn down under the MOFA) and as a further condition precedent there was a requirement for the existence of evidence satisfactory to the Facility Agent that there was no amount owing but unpaid in respect of a Cost Overrun;

(b) a Cost Overrun unpaid for five Business Days after demand was an Event of Default.

  1. The central element of Westgem's case is that, in its capacity as Facility Agent, Bankwest calculated the Cost to Complete incorrectly, primarily because in calculating the works required to achieve Practical Completion, it took into account the cost of works required to complete the Project rather than the costs that would be incurred under the Salta Building Contract. Westgem contends that this error led Bankwest to conclude that the first and second Cost Overruns had occurred when they had not.
The contractual terms contended for by Westgem
  1. Westgem's Cost Overrun claims are reinforced by allegations that Bankwest, in its capacity as Facility Agent, breached the following terms of the MOFA:

(a) A term that Bankwest would act fairly and reasonably and in a consistent and ethical manner and that in doing so Bankwest would have regard to the conduct of Westgem, its own conduct and the contract between it and Westgem.[51] This term was defined in the statement of claim as the 'Code Conduct Term' reflecting that its origin lay in the Banking Code adopted by Bankwest in 2005 - I will adopt this definition.[52]

(b) A term that Bankwest as Facility Agent would not allege an Event of Default or purport to exercise any of the Finance Parties' rights on default in respect of events which were not Events of Default.[53] I will refer to this as the Event of Default term.

(c) A term that Bankwest as Facility Agent would not allege an Event of Default or purport to exercise the Finance Parties' rights on default in respect of events which it did not have reasonable grounds to form the opinion was an Event of Default. I will refer to this as the reasonable grounds term.[54]

(d) A term that Bankwest as Facility Agent was required to: [55]

(i) afford Westgem a reasonable opportunity to provide information in relation to whether a Cost Overrun had occurred; and

(ii) reasonably consider any information provided by Westgem in connection with a claimed Cost Overrun.

This term was defined in the statement of claim as the Cost Overrun Consultation Term and I will adopt this definition.

(e) A term that the Financiers would not be entitled to:[56]

(i) insist upon the performance of a contractual obligation by Westgem if and to the extent that they (or any of them) had caused or materially contributed to Westgem's non‑performance of that obligation; and

(ii) rely upon an Event of Default if and to the extent that they (or any of them) had caused or materially contributed to the occurrence of that Event of Default.

I will refer to this as 'no reliance on events caused by own conduct term'.

(f) A term that unless there was a subsisting Event of Default under the MOFA:[57]

(i) Bankwest as Facility Agent was not entitled to appoint an Independent Consultant; and

(ii) Westgem was not obliged pursuant to cl 15.15 of the MOFA, among other things, to cooperate with or pay for an Independent Consultant; and

(iii) Bankwest was only entitled to appoint an Independent Consultant, among other things, to review and report on matters relating to Westgem and the MOFA guarantors, and Bankwest was not entitled to appoint an Independent Consultant to exercise material control over the business and affairs of Westgem.

This term did not feature to any significant extent in Westgem's case. I will refer to the terms as the 'Independent Consultant term'.

The unconscionable conduct and misleading or deceptive conduct claims
  1. Westgem argues that the Financiers' conduct in respect of the first and second Cost Overruns constituted unconscionable conduct in contravention of s 12CC of the ASIC Act (as in force prior to 1 January 2011) and conduct that was misleading or deceptive or was likely to mislead or deceive contrary to s 12DA of the ASIC Act or s 10 of the FTA.
The construction of the Cost Overrun provisions Structure of this section
  1. The order in which matters relevant to the construction of the Cost Overrun provisions are dealt with is as follows:

(a) the principles applicable to the construction of contracts;

(b) the critical definitions;

(c) the context in which the provisions operate;

(d) an overview of the parties' principal contentions; and

(e) consideration of the issues.

The applicable principles
  1. There was no dispute between the parties as to the principles applicable to the construction of commercial contracts. The meaning of the terms of a commercial contract is to be determined by reference to the understanding of a reasonable business person considering the text, context and purpose of the contract. 'Context' means the entire text of the contract as well as any contract or document referred to in the text of the contract.[58] Absent a contrary intention, the court is entitled to approach the task of construction of the clause on the basis that the parties intended to produce a commercial result, one which makes commercial sense.[59]
  2. The principles were stated more fully by the Court of Appeal in Black Box Control Pty Ltd v Terravision Pty Ltd as follows:[60]
The principles relevant to the proper construction of instruments are well known, and were not in dispute in this case. In summary:

(1) The process of construction is objective. The meaning of the terms of an instrument is to be determined by what a reasonable person would have understood the terms to mean.

(2) The construction of a contract involves determination of the meaning of the words of the contract by reference to its text, context and purpose.

(3) The commercial purpose or objects sought to be secured by the contract will often be apparent from a consideration of the provisions of the contract read as a whole. Extrinsic evidence may nevertheless assist in identifying the commercial purpose or objects of the contract where that task is facilitated by an understanding of the genesis of the transaction, its background, the context and the market in which the parties are operating.

(4) Extrinsic evidence may also assist in determining the proper construction where there is a constructional choice, although it is not necessary in this case to determine the question of whether matters external to a contract can be resorted to in order to identify the existence of the constructional choice.

(5) If an expression in a contract is unambiguous and susceptible of only one meaning, evidence of surrounding circumstances cannot be adduced to contradict its plain meaning.

(6) To the extent that a contract, document or statutory provision is referred to, expressly or impliedly, in an instrument, that contract, document or statutory provision can be considered in construing the instrument, without any need for ambiguity or uncertainty of meaning.

(7) There are important limits on the extent to which evidence of surrounding circumstances (when admissible) can influence the proper construction of an instrument. Reliance on surrounding circumstances must be tempered by loyalty to the text of the instrument. Reference to background facts is not a licence to ignore or rewrite the text. The search is for the meaning of what the parties said in the instrument, not what the parties meant to say.

(8) There are also limits on the kind of evidence which is admissible as background to the construction of a contract, and the purposes for which it is admissible. Insofar as such evidence establishes objective background facts known to the parties or the genesis, purpose or objective of the relevant transaction, it is admissible. Insofar as it consists of statements and actions of the parties reflecting their actual intentions and expectations it is inadmissible. Such statements reveal the terms of the contract which the parties intended or hoped to make, and which are superseded by, or merged into, the contract.

(9) An instrument should be construed so as to avoid it making commercial nonsense or giving rise to commercial inconvenience. However, it must be borne in mind that business common sense may be a topic on which minds may differ.

(10) An instrument should be construed as a whole. A construction that makes the various parts of an instrument harmonious is preferable. If possible, each part of an instrument should be construed so as to have some operation.

(11) Definitions do not have substantive effect. A definition is not to be construed in isolation from the operative provision(s) in which the defined term is used. Rather, the operative provision is ordinarily to be read by inserting the definition into it. (citations omitted)
  1. In the context of this case the comments of Sales J (as his Lordship then was) in Torre Asset Funding Ltd v The Royal Bank of Scotland plc, bear repeating:[61]
The court should be wary, when interpreting a complex set of commercial documents, of focusing too narrowly on a single phrase, but rather should look at such phrases in the commercial landscape of the instrument as a whole: see Re Sigma Finance, para [9] per Lord Mance SCJ, giving the lead judgment for the majority. As Lord Mance explained at para [12], endorsing the approach adopted by Lord Neuberger MR in the Court of Appeal:
'the resolution of an issue of interpretation in a case like the present is an iterative process, involving 'checking each of the rival meanings against other provisions of the document and investigating its commercial consequences' ... Like him, I also think that caution is appropriate about the weight capable of being placed on the consideration that this was a long and carefully drafted document, containing sentences or phrases which it can, with hindsight, be seen could have been made clearer, had the meaning now sought to be attached to them been specifically in mind ... Even the most skilled drafters sometimes fail to see the wood for the trees, and the present document on any view contains certain infelicities, as those in the majority below acknowledged ... Of much greater importance in my view, in the ascertainment of the meaning that the Deed would convey to a reasonable person with the relevant background knowledge, is an understanding of its overall scheme and a reading of its individual sentences and phrases which places them in the context of that overall scheme.'
  1. The applicable principles require that 'business common sense' be brought to bear on the contract, though, as the Court of Appeal observed in Black Box, reasonable minds may differ on what constitutes business common sense.[62] In this context Westgem's senior counsel emphasised, by reference to the observations of Neuberger LJ (as his Lordship then was) in Skanska Rashleigh Weatherfoil Ltd v Somerfield Stores Ltd,[63] that judges should be cautious about reaching conclusions about the intentions of business people. In Skanska Neuberger LJ, with whom Richards & Leveson LJJ agreed, observed:[64]
... [I]t seems to me to be right to emphasise that the surrounding circumstances and commercial common sense do not represent a licence for the court to rewrite a contract merely because its terms seem somewhat unexpected, a little unreasonable or not commercially very wise. The contract will contain the words the parties have chosen to use in order to identify their contractual rights and obligations. At least between them, they have control over the words they use and what they agree, and in that respect the words of the written contracts are different from the surrounding circumstances or commercial common sense which the parties cannot control, at least to the same extent.

Particularly in these circumstances, it seems to me that the court must be careful before departing from the natural meaning of the provision in the contract merely because it may conflict with its notions of commercial common sense of what the parties may, must or should have thought or intended. Judges are not always the most commercially minded, let alone commercially experienced, of people, and should, I think, avoid arrogating to themselves overconfidently the role of arbiter of commercial reasonableness or likelihood.
The definition of Cost to Complete and other critical definitions
  1. The definitions were set out in cl 1.1 of the MOFA. The definitions applied unless the context otherwise indicated (cl 1.1).
  2. 'Cost Overrun' was defined by cl 1.1(32) as:
[T]he amount by which the Cost to Complete exceeds the aggregate of the Undrawn Commitment for the Facility.
  1. 'Cost to Complete' was defined by cl 1.1(33) as:
[A]t any time, the amount reasonably determined by the Facility Agent (based on information provided by the Project Certifier and the Borrower) to be the amount required to be expended to achieve Practical Completion, being the aggregate of the following amounts:

(a) the likely cost to the Borrower under the Building Contracts (as certified by the Project Certifier) from that time of achieving Practical Completion;

(b) the likely payments of interest, fees, indemnities and other similar transaction costs to be paid by the Borrower under the Transaction Documents from that time until the achievement of Practical Completion; and

(c) the likely payments of rates, Taxes, insurance and consultants' fees in connection with the Project to be made by the Borrower from that time until the achievement of Practical Completion.
  1. 'Cost to Complete' was defined as an amount to be reasonably determined by the Facility Agent, however, when used in cl 13.2(6)(d), I consider that the term means an amount determined by the Project Certifier. Clause 13.2 is set out full in the next section of these reasons. For present purposes it suffices to note that cl 13.2(6)(d) provides:
The Borrower must provide the Facility Agent with a certified copy of a report from the Project Certifier confirming:

...

(d) that the Cost to Complete does not exceed the Undrawn Commitment;
  1. As can be seen the regime set out in cl 13.2(6) contemplated the provision by Westgem to the Facility Agent of a certified copy of a report from the Project Certifier confirming that the Cost to Complete does not exceed the Undrawn Commitment yet the Cost to Complete, as defined in cl 1.1(33), was an amount determined by the Facility Agent. Viewed objectively it is unlikely that the parties contemplated that the condition precedent in cl 13.2(6) should require Westgem to obtain a Cost to Complete determination made by the Facility Agent then have it confirmed by the Project Certifier before providing a certified copy of the Project Certifier's report to the Facility Agent. When used in cl 13.2(6) the expression 'Cost to Complete' means an amount determined by the Project Certifier, not the Facility Agent, in accordance with the formula in cl 1.1(33).
  2. The controversy over the definition of Cost to Complete primarily concerned the defined terms 'Building Contracts' and 'Practical Completion'.
  3. 'Building Contracts' was defined by cl 1.1(22) as:
(a) the 'Formal Instrument of Agreement - Raine Square' incorporating AS-2124-1992 general conditions of contract and all associated annexures and attachments, dated on or about 20 December 2007; and

(b) any other agreement between the Borrower and the Builder,

for the construction of the Project;
  1. 'Builder' was defined by cl 1.1(20) as Salta.
  2. 'Practical Completion' was defined by cl 1.1(87) as:
[T]he achievement of practical completion in respect of the Project in accordance with requirements of the Building Contracts;
  1. 'Undrawn Commitment' was defined in cl 1.1(125) as:
[I]n respect of a Facility, at the relevant time, the relevant Facility Limit as the Principal Outstanding for that Facility, at that time;
  1. Reference must also be made to the definitions of Project, the Works and the Land.
  2. 'Project' was defined in cl 1.1(93) as:
[T]he construction of the commercial high rise development known as 'Raine Square', comprising (among other things):

(a) a building of 21 storeys and having an estimated net lettable area of approximately 42,507 square metres; and

(b) all underground public and tenancy parking, certain retail areas and plaza and landscaped areas,

situated on the Land and which is the subject of the Works;
  1. 'The Land' was defined as meaning the property situated on the corner of William, Wellington, Queen and Murray Streets, Perth, Western Australia, and was more specifically described by various title particulars, (cl 1.1(65)). The tunnel is not within the boundaries of the Land - it runs under William Street.
  2. 'The Works' were defined to mean all of the works the subject of the Building Contracts, (cl 1.1(127)).
  3. 'Total Development Costs' were defined in cl 1.1(120) as:
[T]he aggregate of the following amounts, each as determined by the Facility Agent in its absolute discretion:

(a) the 'as is' value of the Project taken from the most recent Acceptable Valuation given to the Facility Agent under clause 15.7. That Acceptable Valuation must take into account the lease arrangements between the Lessee and the Borrower under the terms of the Heads of Agreement (excluding any applicable GST), the Acceptable Development Approval and each other Government Agency approval required for the Project;

(b) the Project building and construction costs determined in accordance with the Approved Project Budget, as certified by the Project Certifier;

(c) all professional fees and all project management and other costs related to the undertaking of the Works that are payable to any consultants engaged by or on behalf of the Borrower in connection with the Project Works, as certified by the Project Certifier;

(d) any additional costs and contingency allowances in connection with the Project Works not otherwise captured under any other paragraph of this definition, as certified by the Project Certifier;

(e) any marketing and leasing costs incurred or to be incurred in connection with the Project; and

(f) any capitalised interest and any other funding costs incurred or to be incurred in connection with the Project during the Project construction period that ends on the date of Practical Completion;
  1. The breadth of what is encompassed by the references in this definition to 'Project building and construction costs determined in accordance with the Approved Project Budget', 'professional fees and all Project Management and other costs related to undertaking the Works' and to the 'Project Works' (a term not defined and which does not appear elsewhere in the MOFA) is to be noted.
  2. 'Approved Project Budget' was defined as follows:[65]
[T]he detailed feasibility study and cash flow for the Project determined on a 'whole of project' basis including a monthly breakdown by category of cash flow showing the expected revenues and costs prepared by the Borrower and in a form and substance satisfactory to the Financiers in their absolute discretion and referred to in clause 15.2(2).
  1. Reference must also be made to certain terms in the Salta Building Contract. In the Salta Building Contract, 'Practical Completion' was defined in GC 2 as:
[T]hat stage in the execution of the work under the [Building] Contract when -

(a) the Works are complete except for minor omissions and minor defects -
(i) which do not prevent the Works from being reasonably capable of being used for their intended purpose; and

(ii) which the Superintendent determines [Salta] has reasonable grounds for not promptly rectifying; and

(iii) rectification of which will not prejudice the convenient use of the works; and
(b) those tests which are required by the [Building] Contract to be carried out and passed before the Works reach Practical Completion have been carried out and passed; and

(c) documents and other information required under the [Building] Contract which, in the opinion of the Superintendent, are essential for the use, operation and maintenance of the Works have been supplied.
  1. 'Works' was defined in GC 2 of the Salta Building Contract as:
[T]he whole of the work to be executed in accordance with the [Building] Contract, including variations provided for by the [Building] Contract, which by the [Building] Contract is to be handed over to [Westgem].
  1. By GC 40.1 of the Salta Building Contract the Superintendent could direct Salta to 'increase, decrease or omit any part of the work under the contract' - 'Work under the Contract' meant the work which Salta was or might be required to execute under the Contract and included variations, remedial work, and other work not presently relevant.
Context in which the provisions operate
  1. The definition of 'Cost to Complete' was of operative significance for two reasons. First, it was an element of the definition of 'Cost Overrun'. Secondly, as noted earlier, it was an element of the conditions precedent to each Drawing after the first Drawing ‑ Westgem was required to provide the Facility Agent with a report from the Project Certifier confirming, among other things, that the Cost to Complete did not exceed the Undrawn Commitment.
  2. The absence of a Cost Overrun was also, in effect, a condition precedent to any Drawing after the first Drawing. This was so for two reasons. First, it was a condition precedent that there was evidence satisfactory to the Facility Agent that there was no amount owing but unpaid in respect of a Cost Overrun (Westgem was obliged to pay every Cost Overrun within 5 Business Days of demand by the Facility Agent). Secondly, a failure to pay a Cost Overrun within five Business Days of a demand was an Event of Default and it was a condition precedent that no Event of Default had occurred or was subsisting at the date of a Drawdown Notice.
  3. Westgem's obligation to pay a Cost Overrun meant that it was obliged to contribute capital to the funding of the Project. Until the amount of the Cost Overrun was paid Westgem was unable to make any drawings on the Facility. Westgem's only asset of significant value was Raine Square. Thus any capital it was required to contribute to pay a Cost Overrun was capital that Mr Saraceni and Mr Pourzand were required to contribute from their resources. The guarantees given by each of them were unlimited in respect of Cost Overruns.
  4. The commercial purpose of the MOFA informs the construction of the Cost to Complete and Cost Overrun provisions. The stated purpose of the MOFA was to provide the funding required by Westgem for the construction of the Project not some aspect of it. This was evident from the 'Introduction' in the MOFA that recorded Westgem had requested the Financiers to provide it with financial accommodation 'in connection with the Project' and from the purposes stated in cl 3, in particular cl 3(1)(d) which recorded that the Multi-Option Facility was to be used for, among other purposes, '[carrying] out the Project in accordance with the Approved Project Budget'. The purpose of the MOFA was not limited to providing construction finance for a particular building contract with Salta.
  5. Raine Square was the primary security provided by Westgem. The amount to be advanced by the Financiers was subject to a fixed upper limit, (cl 2) and the MOFA contained provisions (described below) whose purpose was to ensure that Raine Square constituted and remained adequate security for the debt due to the Financiers under the MOFA.
  6. The Cost to Complete and Cost Overrun concepts formed part of a contractual regime that enabled the Financiers (through the Facility Agent) to control Westgem's access to funds. The Cost to Complete and Cost Overrun provisions must be construed in a manner harmonious with the other provisions that form part of that regime.
  7. The regime by which the Financiers were able to control Westgem's access to funds included:

(a) the requirement that the conditions precedent to the first Drawing were met (cl 13.1);

(b) the requirement that Westgem complied with the Loan to Valuation Ratio (LVR), the Total Development Cost Ratio (TDCR) and the Interest Covenant Ratio (ICR) (cl 16.1, cl 16.2 and cl 16.3);

(c) the requirement that the conditions precedent to each Drawing were met (cl 13.2); and

(d) the requirement that Westgem ensure that the Project was carried out in accordance with the Approved Project Budget (cl 15.2).

  1. The overarching point to be made about these provisions is that they demonstrate the importance to the Financiers of knowing both the 'as if completed' value of the Project and the cost to complete the Project, that is, the entire cost of the entire Project and not one component of it. Without this information the Financiers could not be assured that the Project constituted adequate security for the debt due to them and that the funds available to Westgem were going to be sufficient to complete the Project.
  2. The conditions precedent to the first Drawing included requirements that Westgem provide: (i) an 'Acceptable Valuation of the Project' confirming the current market value of the Project and an 'as if completed' market value of the Project';[66] (ii) a report from the Project Certifier that addressed, among other matters, 'the total cost to complete the Project';[67] (iii) the Approved Project Budget;[68] and (iv) evidence of Westgem's equity contribution that was to be applied towards payment of the Total Development Costs.[69] The emphasis in these provisions on the value of the Project and cost of completing the Project is readily apparent.
  3. Clause 16.1 specified the LVR - it required Westgem to ensure that the aggregate of the MOFA Facility Limit and the Letter of Credit Facility Limit did not exceed 70% of the 'as if completed value' of the Project. This obligation manifested the importance of the Project as security for the finance.
  4. Clause 16.2 required Westgem to ensure that the aggregate of the MOFA Facility Limit and the Letter of Credit Facility Limit did not exceed 80% of the Total Development Costs. The Total Development Costs were defined in the widest possible terms. They included 'the Project building and construction costs determined in accordance with the Approved Project Budget as certified by the Project Certifier' and any additional costs and contingency allowances in connection with the Project Works not otherwise captured in the definition of Total Development Costs.[70]
  5. Clause 16.3 required Westgem to comply with the ICR. In summary the ICR concerned the ratio between the income to be generated by the completed Project and the cost of interest under the fully drawn down Facilities. It is sufficient to record that the income had to be 1.2 times the cost of interest. The ratio gave the Financiers comfort that the income stream on completion of the Project would be sufficient to enable Westgem to meet the interest expense and enable Westgem to refinance.
  6. In the event of a breach of the LVR, TDCR or ICR the Facility Agent was entitled to demand additional security and a reduction of the amount outstanding on the Facilities (or to demand one or the other). In other words, in the event of a breach of any ratio the Financiers could require Westgem to contribute equity or further security.
  7. The degree of control the Financiers were capable of exercising over Westgem's ability to make Drawings under the MOFA is further illustrated by the extensive conditions precedent to any Drawing after the first Drawing. The conditions precedent speak for themselves. They were set out in cl 13.2 and were as follows:
(1) [the Drawing] is to be provided during the Availability Period;

(2) the Facility Agent is satisfied that after providing the Drawing the relevant Facility Limit and the aggregate Facility Limits would not be exceeded;

(3) the Facility Agent has received a Drawdown Notice in respect of it in accordance with clause 4;

(4) the Facility Agent is satisfied that it will be used for a purpose set out in clause 3;

(5) all Authorisations required by the Borrower for the Drawing have been obtained;

(6) the Borrower must provide the Facility Agent with a certified copy of a report from the Project Certifier confirming:
(a) the status of the Project;

(b) that all aspects of the Project and the Works are in order;

(c) that the amount of the Drawing is to be used to fund Works costs that are the subject of the Building Contracts or any other Works contract, verification of the amount of the Drawing and the original third party invoice to be funded by that Drawing;

(d) that the Cost to Complete does not exceed the Undrawn Commitment; and

(e) anything else that the Facility Agent requires in its absolute discretion;
(7) if the amount of the Drawing is to be used to fund Works Costs that are not the subject of the Building Contracts or any other Works contract, a certificate in form and substance satisfactory to the Facility Agent signed by the sole director of the Borrower certifying that the relevant amount is the subject of a third party cost or costs properly incurred by the Borrower, and which attaches the original invoice for that cost or, if there is more than 1, a listing of those costs. The Facility Agent may request any of the original invoices for those listed costs and the Borrower must deliver any requested invoice or invoices to the Facility Agent within 2 Business Days of a request being made by the Facility Agent but in any event prior to the relevant Drawdown Date;

(8) the representation and warranties by each Transaction Party in the Transaction Documents are true as at the date of the relevant Drawdown Notice and the relevant Drawdown Date as though they had been made at that date in respect of the facts and circumstances then subsisting;

(9) no Event of Default has occurred or is subsisting at the date of the relevant Drawdown Notice and the relevant Drawdown Date or will result from the provision of the accommodation;

(10) in the opinion of the Facility Agent, no circumstance or fact exists which is reasonably likely to have a Material Adverse Effect;

(11) evidence satisfactory to the Facility Agent that there is no amount owing and unpaid in respect of a Costs Overrun;

(12) evidence satisfactory to the Facility Agent that confirms that all Project Insurance Policies are current and on terms satisfactory to the Facility Agent.
  1. Further Westgem was obliged to ensure that the Project was carried out in accordance with the Approved Project Budget. The Approved Project Budget categorised the costs of the Project into: land costs; holding and statutory costs; consultancy costs; marketing and selling costs; finance costs; and construction costs. Within the construction cost category there was a 'Contingency' sub-category. Westgem was prohibited from utilising the contingency amount without the prior written consent of the Facility Agent and any request to use the contingency had to be accompanied by a report and certification from the Project Certifier (cl 15.2(4)).
  2. To divine the purpose of the contractual regime described above one need only consider the provisions themselves. No particular insight into the ways of the commercial world is required. The purpose of the regime was to enable the Financiers to assess the progress of the Project and to assess and manage the risk that Westgem might default on its obligations and, in the event of default, to manage the consequences.[71] In short the mechanisms enabled the Financiers to manage the 'credit risk'.
  3. The conferral of extensive and detailed rights on the Financiers' by the MOFA to assist them in managing credit risk is explicable by the fact that the Project itself was the primary security for funds advanced under the MOFA.
  4. Specifically in the event of an increase in building costs the Cost Overrun provision operated to ensure that Westgem met the increase out of its resources, in effect, out of Mr Saraceni's and Mr Pourzand's resources. In that respect, the Financiers' description of the Cost Overrun provision as a risk allocation mechanism was apt. The risk of an increase in the building cost was allocated to Westgem.
  5. The ability to call on Westgem to contribute equity in the event of a Cost Overrun enabled the Financiers to avoid a situation in which they were obliged to fund increased building costs that might potentially exhaust the funds available under the Facilities without achieving completion of the Project. If the Facility was drawn down to its limit but the Project was incomplete there was a risk that the Financiers' primary security in the form of the Project would be inadequate to cover the debt due by Westgem.
An overview of the parties' principal contentions

Westgem's contentions

  1. As noted earlier the central proposition on which Westgem's case on the construction issue was based was that Cost to Complete refers to the amount required to be expended in order to achieve Practical Completion under the Salta Building Contract. Westgem contended that because the Salta Building Contract permitted the Superintendent to vary the Works to be performed under it, the quantum of the Cost to Complete depended upon whether the Superintendent had directed Salta to 'increase, decrease or omit any part of the work under the Contract'.[72]
  2. Westgem contended that the Financiers' argument that Cost to Complete 'should be construed as including all costs which were to be incurred by Salta under the Salta Building Contract at the time when the MOFA was executed',[73] should be rejected because it is inconsistent the clear words of the definition and, so Westgem argued, there was no basis, textually, commercially or otherwise for such a strained construction, which seeks to freeze the calculation of the Cost to Complete under a variable building contract, to the cost at the date of the execution of the MOFA.
  3. Westgem developed a further argument to the effect that there were three reasons why the construction advanced by the Financiers would not assist them in any event. First, Westgem contended that items of work for which provisional sums had been allowed in the Salta Building Contract had not been directed to be performed by the Superintendent at the date the MOFA was executed. Those works were not a 'cost to be incurred by Salta under the Salta Building Contract when the MOFA was executed'. Secondly, the tunnel works were not situated on the Land and thus did not fall within the definition of the Project. Thirdly, even if the Financiers' construction of the Cost to Complete was correct, the methodology applied in purporting to determine the Cost to Complete did not adopt that construction.
  4. Westgem submitted that for a determination of a Cost Overrun to be valid, the determination must be made in accordance with the terms of the MOFA. Westgem emphasised that a Cost Overrun was a contractual construct that did not exist outside the MOFA. It was contended that an analogy could be drawn with cases (such as Australian Vintage Ltd v Belvino Investments No 2 Pty Ltd)[74] that had considered the validity of expert determinations and the principle that an expert determination is only valid if it complies with the terms of the contract, that is, if the expert had carried out the task the expert was required by the contract to undertake. Westgem submitted that it was not necessary for it to demonstrate that there was no Cost Overrun at all or that it was of a substantially lower amount. It was sufficient to show that the determination was made on the basis of a misinterpretation of the MOFA or materially departed from the MOFA, irrespective of whether that misinterpretation or material departure actually affected the result. Westgem relied on the authority of Veba Oil Supply & Trading GmbH v Petrotrade Inc.[75]
  5. Westgem sought to diminish the importance to the Financiers of the Cost Overrun provisions in assessing and managing the credit risk by contending that the Builder's Side Deed provided ample protection for the Financiers.[76] In support of this contention the plaintiffs referred to the restrictions on Salta and Westgem performing variations to the Works and to the other rights conferred upon the Security Trustee by the Builder's Side Deed.

Financiers' contentions

  1. The Financiers framed the constructional issue as a choice between a calculation of 'the Cost to Complete the Project' or a calculation of the 'Cost to Complete the Salta Building Contract'. So framed the issue reflects the nub of the dispute between the parties which was whether the element of the Cost to Complete set out in subparagraph (a) of the definition should include the costs of carrying out Works which were removed from Salta's scope of works (most significantly the tunnel works and what was known as the Podium) when those Works still had to be performed to complete the Project.
  2. The Financiers made a number of preliminary points:[77]

(a) At the time when the MOFA was executed the Salta Building Contract covered all anticipated aspects of the construction of the Project. In particular it included the tunnel.

(b) It was evident from cl 15.2(10) of the MOFA that it was initially intended that Salta would complete all of the construction works for the Project. Clause 15.2(10) recorded that Westgem must 'ensure that the builder which is engaged to carry out the Works and complete the Project remains at all times the Builder'.[78]

(c) Contrary to Westgem's submission the provisional sum items in the Salta Building Contract were within Salta's scope of works - they were denoted 'provisional sum items' because they had a fluctuating cost not because they lay outside the initial scope of Salta's work.

(d) The MOFA recognised that building work might be undertaken by builders other than Salta. In this respect the Financiers relied upon cl 13.2(6)(c) and cl 13.2(7).

(e) It was important to appreciate that Undrawn Commitment was a product of the Facility Limit and the Financiers' commitment pursuant to cl 2 to make advances for the purposes of the Project and was not a concept referable merely to the amount payable to any contractor under a particular contract - it was referable to the whole of the Project and the Approved Project Budget.

  1. The Financiers expressed the construction for which they contended in various ways. In their opening written submissions they contended that 'the term "Cost Overrun" should be construed as including all costs which were to be incurred by Salta under the Salta Building Contract at the time when the MOFA was executed'[79] and that properly construed the definition of 'Cost to Complete' depends on the likely cost to Westgem under the Building Contracts with Salta or any replacement Works contract with another builder from the time when the determination by the Facility Agent is made until the time of achieving Practical Completion of the Project.[80] In their closing written submissions the Financiers emphasised the importance of construing the term 'Building Contracts' as extending to any 'construction contract with another builder which supplements or replaces the contract with Salta' and that the likely cost to Westgem under such a contract had to be taken into account in the Cost to Complete calculation.[81]
  2. The Financiers contended, in effect, that Westgem's construction of the Cost to Complete definition would involve a disparity in approach to the elements making up the definition of Cost Overrun because on Westgem's construction, the Cost to Complete element would be limited to the likely cost of completing the works under the Salta Building Contract whereas the Undrawn Commitment was a concept referable to the cost of the whole Project (being the undrawn funds available under the Facilities that, subject to the terms of the MOFA, the Financiers were obliged to make available for the purpose of the Project, cl 2.1).[82]
  3. The Financiers contended that Westgem's construction had the potential to oblige them to make advances to fund 'Works contracts' entered into by Westgem with contractors other than Salta who between them would complete work excised from Salta's scope of works which would be necessary to complete the Project. The Financiers contended that contrary to the obvious intentions of the MOFA, this construction would on the one hand allow Westgem to exceed the Undrawn Commitment and on the other hand prevent the Financiers from invoking the protection of the Cost to Complete/Cost Overrun mechanism. In effect allowing Westgem to circumvent the negotiated protections for the Financiers by diminishing the works under the Salta Building Contract. This created the risk that the Facility Limit might be reached when the Project was only partially completed. In this circumstance the Financiers contended that the incomplete Project was unlikely to achieve the required LVR and ICR.
  4. The Financiers deployed the contention about the disparity between the two elements of the Cost Overrun definition to test Westgem's construction in another way.[83] They argued that if the Project, for the purposes of the definition of Cost to Complete, were to be understood as being limited to work to be completed under the Salta Building Contract, then by parity of reasoning Westgem could not request drawings under the MOFA for construction costs not payable to Salta.
  5. The Financiers submitted that Westgem's construction took no account of the commercial context in which the Cost to Complete and Cost Overrun provisions operated.[84] They criticised Westgem's construction as being entirely textual and divorced from any proper consideration of context. Further, the Financiers argued that Westgem's approach was contrary to the commercial object of the MOFA which was to fund all of the Project costs in accordance with the Approved Project Budget and not simply to finance the costs that relate to the construction work undertaken by a particular contractor, that is, Salta.
  6. The Financiers submitted that their construction reflected the following commercial objectives of the MOFA, that:

(a) the Project was brought to completion and the Financiers' security brought to its assumed value for LVR purposes;

(b) the Project was completed and capable of generating the level of income that was compliant with the ICR provisions so that Westgem would be able to refinance or sell the Project on completion of construction so as to be able to repay the Facility upon its expiry; and

(c) the Financiers were not required to assume greater risk by being required to extend additional credit to complete the Project.

  1. The Financiers contended that Westgem's textual approach overlooked two aspects of the text.[85] First, it overlooked that the MOFA contemplated that construction works might be carried out by builders other than Salta. Secondly it overlooked cl 1.2(h) which enabled a more expansive meaning to be accorded to the term 'Building Contracts'.
  2. The Financiers contended that Westgem's argument that 'Practical Completion' means Practical Completion under the Salta Building Contract, ignores the definition of 'Practical Completion' in the MOFA. They contended that 'Practical Completion of the Project' means Practical Completion of the Project in accordance with the requirements of any building contract necessary to achieve completion.[86]
  3. The Financiers contended that the definition of 'Works' should be understood in the same way, namely, as meaning 'all of the works the subject of the Building Contracts with Salta or any replacement or supplementation of those Building Contracts with another builder necessary to complete the Project in accordance with the Approved Project Budget'.[87]
  4. The Financiers disputed that the analogy drawn by Westgem with the expert determination cases was a valid one. The Financiers contended that as a matter of construction all that was required by the Cost to Complete definition was that the amount determined by the Facility Agent was objectively reasonable.[88]
Consideration of Cost Overrun construction issue
  1. I will begin my consideration by addressing textual considerations - the meanings of the terms 'Practical Completion' and 'Building Contracts' - the matters bearing on the meaning of these terms overlap considerably. I will then consider the influence of commercial purpose on the textual considerations. I will then address a number of specific issues raised by the parties' contentions concerning the construction of the Cost Overrun provisions.

'Practical Completion'

  1. 'Practical Completion' is a defined term used four times in the confined context of the definition of 'Cost to Complete'. It is central to the definition of 'Cost to Complete'. A construction of Practical Completion that attributes the same meaning to the term whenever it is used accords with the presumption that when a word or expression appears several times in a document it will have the same meaning throughout.[89] This presumption is even stronger where the same word or expression appears several times within the same contractual clause. There is no basis upon which 'Practical Completion' could be understood as having different meanings in different parts of the 'Cost to Complete' definition. To the contrary the text suggests that 'Practical Completion' has the same meaning in each of subparagraphs (a), (b) and (c) of the definition of 'Cost to Complete'. Each of those subparagraphs refers to likely costs or likely payments incurred over a period of time commencing on 'that date' (the date being the date of the determination) and ending with the achievement of Practical Completion. It would not only be counterintuitive but also most unlikely for the end date of each period, (fixed by the term 'Practical Completion'), to vary between subparagraphs.
  2. The 'Cost to Complete' definition specifies how the amount required to be expended to achieve 'Practical Completion' was to be determined. It did so by first referring to the amount broadly as the 'amount ... required to be expended to achieve Practical Completion' before prescribing how that amount was to be calculated - by aggregating the 'likely cost' and 'likely payments' specified in sub-paragraphs (a) (b) and (c).
  3. As noted earlier, 'Practical Completion' is defined in the MOFA as 'the achievement of practical completion in respect of the Project in accordance with the requirements of the Building Contracts' (emphasis supplied).
  4. I consider that whenever the term 'Practical Completion' appears in the 'Cost to Complete' definition it means Practical Completion of the Project and that Practical Completion of the Project was an event that was independent of, and not synonymous with, Practical Completion under the Salta Building Contract. Practical Completion under the Salta Building Contract was likely to be a necessary but not sufficient condition for the achievement of Practical Completion of the Project. My reasons for reaching this conclusion are as follows:
  5. First, the Project was not defined narrowly or exclusively by reference to the definition of 'Works' the subject of the Salta Building Contract but by a more expansive description of the elements of the development. It is the description of the physical components of the development that is the primary focus of the definition of the Project. Whilst it may be accepted that the scope of the work undertaken under the Salta Building Contract might be varied by the Superintendent, the elements of the Project as defined in the MOFA were not capable of being altered retrospectively by variations under the Salta Building Contract. In this respect the definition of 'Project' must be considered to be fixed at the date of execution of the MOFA - expressed in other terms the definition was a static and not a mobile one.
  6. Secondly, the requirement to make the payments referred to in subparagraphs (b) and (c) of the 'Cost to Complete' definition were not to cease on the achievement of practical completion under the Salta Building Contract. This points strongly to construing 'Practical Completion', where it appears in subparagraphs (b) and (c), as meaning Practical Completion of the Project and not Practical Completion under the Salta Building Contract. Once it is accepted that 'Practical Completion' in subparagraphs (b) and (c) means Practical Completion of the Project the requirement (as a matter of principle) for the term to bear the same meaning throughout the definition leads to the conclusion that in subparagraph (a) 'Practical Completion' means Practical Completion of the Project.
  7. Thirdly, as the Financiers contended, it is apparent that the parties contemplated some of the building work required to complete the Project might be the subject of contracts other than the Building Contracts. This emerges from the provisions setting out the conditions precedent to each Drawing.
  8. Clauses 13.2(6) and (7) refer to three categories of 'Works costs' that may be funded by a Drawing, which were required to be the subject of a report from the Project Certifier provided by Westgem to the Facility Agent. The three categories were:

(i) 'Works costs' that were the subject of the Building Contracts;

(ii) 'Works costs' that were the subject of 'any other Works contract';

(iii) 'Works costs' 'that [were] not the subject of the Building Contracts or any other Works contract'.

  1. Westgem argued that 'Works costs' and 'Works contract' are terms used in the MOFA to distinguish between 'hard' building costs incurred under the Building Contracts and 'soft' consultancy costs incurred under 'Works contracts'.[90] I accept the term 'Works costs' may include 'soft' costs incurred under contracts with consultants but, in my view, the meaning of 'Works costs' extended beyond consultants' costs to the cost of building work undertaken not only by Salta but by other builders as well under 'any other Works contract'. Clause 13.2(6)(b) draws a distinction between Works costs the subject of the Building Contracts and Works costs the subject of any other Works contract. As 'Building Contracts' is a term defined, primarily (subject to contrary contextual considerations), as any agreement between Westgem and Salta for the construction of the Project, this suggests that 'any other Works contract' is a contract for building work with builders other than Salta. There are three further reasons why the references to Works costs and Works contract should be understood as including building costs and building contracts as opposed to only consultants' costs:

(a) If the expression 'Works costs' was intended only to draw a distinction in cl 13.2(6) and (7) between 'hard' building costs and 'soft' consultancy costs the parties would have referred expressly to 'consultants' fees', as in subparagraph (d) of the definition of 'Cost to Complete', or to 'professional fees and all Project Management and other costs related to the undertaking of the Works that are payable to any consultants' as in the subparagraph (d) of the definition of 'Total Development Costs' rather than use the imprecise and generic term 'Works costs'.

(b) Clause 13.2(6) expressly contemplates that 'Works costs' may be the subject of the 'Building Contracts' and this makes it plain that it was contemplated that Works costs would extend to 'hard' building costs.

(c) As seen earlier in the MOFA 'Works' is defined to mean the works the subject of the Building Contracts, that is building works. It would be inconsistent for 'Works' to connote building work in that definition but for 'Works costs' not to connote the costs of building work.

  1. I am satisfied that the parties contemplated that the building work required to complete the Project might be completed by builders other than Salta under 'other Works contract(s)'. Once that premise is accepted it follows that the parties are taken to have contemplated that practical completion under the Salta Building Contract might be achieved even though building work required to achieve Practical Completion in respect of the Project was continuing (under the other Works contracts).
  2. Fourthly, as noted earlier, Westgem was obliged to prepare and update the Approved Project Budget and ensure that the Project was carried out in accordance with it, (cl 15.2(1) and (2)). The Approved Project Budget was defined as 'the detailed feasibility study and cash flow for the Project determined on a "whole of project basis" ...'. These provisions place emphasis on the Project as distinct from the Building Contracts. To construe Practical Completion of the Project as occurring simultaneously with practical completion under the Salta Building Contract would be inconsistent with the 'whole of project' approach to the Approved Project Budget. It makes no commercial sense to require the Approved Project Budget to be prepared on the basis of the whole Project - an enterprise greater than the Building Contracts - but to conclude that Practical Completion of the Project had occurred on Practical Completion under the Building Contract.
  3. In closing submissions Westgem's senior counsel acknowledged that the Approved Project Budget provisions and the Cost Overrun provisions were intended, in part, to protect the Financiers but argued that the Approved Project Budget provision did not necessarily inform the Cost Overrun provision.[91] I do not accept that submission. The undertaking to ensure that the Project was carried out in accordance with the Approved Project Budget and the undertaking to pay for every Cost Overrun within five Business Days of demand by the Facility Agent were each undertakings found in the subclauses of cl 15.2. They are part of the same contractual regime that enabled the Financiers to assess and manage the credit risk. To view the undertaking to complete the Project in accordance with the Approved Project Budget as not informing the Cost Overrun undertaking would not accord with established principles of contractual construction that hold that the MOFA is to be construed as a whole and its provisions are to be read together and, where possible, harmoniously.
  4. Fifthly, the term 'Practical Completion' in the MOFA is not defined as Practical Completion under the Building Contracts but 'Practical Completion of the Project in accordance with the requirements of the Building Contracts'. Had it been intended that the 'achievement of Practical Completion of the Project' would occur upon Practical Completion under the Building Contracts this simple proposition could and would have been articulated clearly in the MOFA.
  5. Sixthly, I acknowledge the inclusion in the definition of 'Practical Completion' of the words 'in accordance with the requirements of the Building Contracts'. These words might be taken to suggest that Practical Completion of the Project was to be regarded as being achieved on Practical Completion under the Salta Building Contract. It is, however, only one of several matters bearing on the proper construction of the definition of Practical Completion of the Project. Having regard to the matters to which I have referred above I do not regard it as decisive. Moreover an explanation for the inclusion of the words 'in accordance with the requirements of the Building Contracts' in the definition may be found in the omission from the MOFA of the precise criteria applicable to determine whether 'Practical Completion of the Project' had been achieved. The words 'in accordance with the requirements of the Building Contracts' import into the definition of 'Practical Completion of the Project' the criteria that must be satisfied to achieve Practical Completion in so far as those criteria can be applied to the Project (not all criteria are applicable because some involve the Superintendent making determinations). Significantly, however, importing the test for practical completion under the Building Contracts into the MOFA definition of 'Practical Completion' means that Practical Completion in respect of the Project is achieved if the Project is complete save for minor defects and omissions of the nature described in GC 2 of the Salta Building Contract.
  6. I add that in arriving at the conclusion that the references to Practical Completion in the Cost to Complete definition were references to Practical Completion of the Project and that Practical Completion of the Project was not synonymous with Practical Completion under the Building Contracts I have not ignored the indications in the MOFA and the Building Contracts that the achievement of Practical Completion of the Project was expected to coincide with Practical Completion under the Salta Building Contract. These indications appear from the definition of the 'Scheduled Project Completion Date' under the MOFA as '28 February 2010' and from the specification of '28 February 2010' as the date for practical completion of the 'complex' (an undefined term) in the Salta Building Contract. The fact Westgem may have planned that the achievement of Practical Completion under the Salta Building Contract would coincide with achievement of Practical Completion of the Project does not, however, determine the constructional issue that has been raised. If work were removed from the Salta Building Contract to be performed under a different agreement with Salta or another builder, then the date for Practical Completion of the Project would not necessarily change. Conversely the removal of work under the Salta Building Contract would be likely to change the anticipated date for practical completion under the Salta Building Contract.

Building Contracts

  1. I turn next to the meaning of the term 'Building Contracts' in the phrase 'the likely cost to the Borrower under the Building Contracts' in subpar (a).
  2. The definitions of 'Builder' as Salta and 'Building Contracts' as the formal agreement between Salta and Westgem or any other agreement between Salta and Westgem for the construction of the Project favour the more restrictive construction of 'Building Contracts' contended for by the Westgem, that is, the words mean what they say and Building Contracts should be construed as being limited to the Building Contracts with Salta.
  3. The simplicity of Westgem's argument and its close adherence to the text are superficially attractive but as the authorities make plain the task of construing a commercial document involves a synthesis of text, context and commercial purpose. Of course, in an agreement drawn with legal advice as part of a complex and sophisticated commercial enterprise, the deliberate use of defined words is not to be lightly passed over, even where the definition leaves open the possibility of another meaning for a defined phrase.[92] I respectfully adopt the statements of Leeming JA, with whom McColl and Gleeson JJA agreed, in Perpetual Custodians Ltd v IOOF Investment Management Ltd, where his Honour observed:[93]
... Lord Steyn has written extrajudicially that '[e]ven an agreed definition is of limited use: it takes no account of contextual requirements': (2001) 21 OJLS 59 at 60. The same point was made by Fullagar J in Halford v Price (1960) 105 CLR 23 at 33. Professor McMeel has written (The Construction of Contracts, 2nd ed (2011) Oxford University Press, p159) that 'even defined terms must yield to wider context or contrary intention.' Professor Carter has said that 'the absence of [words to the effect 'unless the context indicates otherwise'] does not mean that the definition necessarily applies to every usage of the term in the document' (The Construction of Commercial Contracts (2013) Hart, p 446). That must in my opinion be correct in principle. The ordinary approach to construction insists on reading the contract as a whole and doing so harmoniously, so as to resolve or minimise internal inconsistency. Foreign to that approach would be a slavish rule that defined terms inevitably bear every aspect of their defined meaning. The contestable nub of the matter is what is sufficient to constitute a displacing context or contrary intention. Owen and Steytler JJ have said that 'the deliberate use of defined words is not to be lightly passed over, even where the definition leaves open the possibility of another meaning for a defined phrase': BHP Petroleum (Australia) Pty Ltd v Sagasco South East Inc [2001] WASCA 159 at [24], a proposition whose force I acknowledge.
  1. The point is put clearly by Fullagar J in Halford v Price,[94] '[n]either in the case of a statute nor in the case of a contract or any other instrument is there any rule of law or of construction which requires us to apply a definition where to do so would be at variance with a context or with a general intent to be gathered from the whole of the instrument'.
  2. Westgem's construction does not pay adequate regard to the context of the clauses and commercial purpose of the MOFA. In my view the term 'Building Contracts' in subpar (a) means any contract for building work required to achieve Practical Completion of the Project. I hold that view for the following reasons.
  3. First, as the prefatory words of cl 1.1 of the MOFA make clear the definitions of 'Building Contracts' and 'Builder' only apply 'unless the context otherwise indicates'. The term 'Building Contracts' must be construed in the context of the 'Cost to Complete' definition and the contractual significance of the Cost to Complete calculation (as explained earlier in this judgment). There are matters of context that indicate that Building Contracts must comprehend contracts for building work required to complete the Project in addition to the contracts with Salta referred to in the definition of 'Building Contracts'.
  4. The first matter of context is that the Builder's Side Deed, which must be read together with the MOFA, recognised that the Salta Building Contract might be terminated before the Works were completed. Specifically, cl 6 of the Builder's Side Deed governed what was to occur in the event that the Salta Building Contract was terminated before Practical Completion under the Salta Building Contract was achieved. In that event Salta would no longer be the Builder and the Building Contracts would no longer be contracts with Salta. Unless the reference to the 'Building Contracts' was construed as extending to building contracts with other builders, the Cost to Complete calculation could not be undertaken. The provisions that depended on the ability to calculate a Cost Overrun would be rendered ineffective. This is not a result the parties could be taken to have intended. This conclusion is reinforced by what actually occurred, that is the Salta Building Contract was terminated and replaced by the Probuild Building Contract.
  5. The second matter of context is that, as was apparent from cl 13.2(6) and (7) of the MOFA, the parties contemplated the existence of contracts for the completion of building work required to complete the Project other than the Salta Building Contract, and that such other contracts would exist even if the Salta Building Contract was terminated.
  6. Secondly, construing the term 'Building Contracts' as extending to building contracts with builders other than Salta (as well as the Salta Building Contract) enables an accurate determination to be made of the 'amount ... required to be expended to achieve Practical Completion' in the event that work required to complete the Project (that is part of the Works) were excised from the Building Contract and made the subject of another contract with a builder other than Salta.
  7. Conversely, to construe 'Building Contracts' as being limited to the Salta Building Contract and, as a consequence, not to take into account the likely cost to Westgem under other building contracts for building work that was required to complete the Project would frustrate the calculation of the amount required to be expended to achieve Practical Completion of the Project. To state the obvious, if work were excised from the Salta Building Contract and incorporated in a new contract with another builder the amount required to achieve Practical Completion of the Project could not be determined by reference only to the likely cost to Westgem of the reduced scope of work under the Salta Building Contract.
  8. Westgem's construction of 'Building Contracts' would, as the Financiers contended, enable Westgem to reduce the Cost to Complete to avoid a Cost Overrun by excising work from the scope of the Building Contract and allocating that work to other builders under new contracts with payments in respect of amounts due under the new contracts being funded by Drawings under the MOFA. In those circumstances the Financiers' ability to manage the credit risk would be substantially undermined. They would not be able to withhold Drawings nor would they be able to call upon Westgem to contribute equity. In such a situation the risks inherent in increased construction costs would rest with the Financiers.
  9. Thirdly, I accept the Financiers' contention that cl 1.2(1)(d) can be relied upon to expand the reference to 'Building Contracts' in subpar (a) of the 'Cost to Complete' definition to include any building contract that replaces or supplements the Salta Building Contract. Clause 1.2(1)(d) provides, 'unless the context indicates otherwise', 'a party to this document or another agreement or document includes the party's executors, administrators, successors and permitted substitutes or assigns'. Further cl 1.2(1)(h) states that a reference to:
(h) an agreement or document is to the agreement or document as amended, novated, supplemented or replaced, except to the extent prohibited by this document;
  1. The Financiers contended that there were no contextual matters that 'indicate otherwise', rather there were matters of context that favour the view that cl 1.2(h) applies to the definition of 'Building Contracts' extending their meaning beyond contracts between Westgem and Salta. They point to the references to other Works contracts, which I have already discussed, and to the purpose of the MOFA being to fund the construction of the Project and not merely to fund the Salta Building Contract.
  2. Westgem contended that the Financiers' reliance on cl 1.2(h) should fail because Westgem gave an undertaking to ensure that the builder engaged to carry out the Works and complete the Project would be Salta (cl 15.2(10)), and 'Building Contracts' is a term defined by reference to contracts with Salta. In those circumstances, Westgem argued cl 1.2(h) could only operate to extend the reference to 'Building Contracts' to include an amended, novated, supplemented or replacement Building Contract with Salta. Westgem also made the point that relying on cl 1.2(h) to expand the meaning of 'Building Contracts' would have the result that 'Building Contracts' could mean building contracts with someone other than Salta but 'Builder' would mean Salta. This, it was submitted, would give rise to a nonsensical contract.[95]
  3. In my view the matters relied upon by the Financiers coupled with the recognition in the Builder's Side Deed that Salta might be replaced as the Builder are matters of context that support the application of cl 1.2(h) to the term 'Building Contracts' to give it the expanded meaning relied on by the Financiers.
  4. Further I accept the Financiers' contention that 'Works' should be construed as all of the works the subject of the Salta Building Contract in addition to all of the works the subject of any contract for building work required to complete the Project with builders other than Salta. Extending the definition of 'Works' to include building works undertaken by a builder other than Salta is a corollary of an expanded construction of 'Building Contracts'.

The influence of commercial purpose

  1. I have described the Cost Overrun provisions as forming part of a contractual regime that enabled the Financiers to assess and manage credit risk. The term 'Cost to Complete' must be construed in a manner that is both consistent with those provisions (the conditions precedent to the first Drawing, the LVR, TDCR and ICR and the conditions precedent to subsequent Drawings), and achieves their common purpose. To do otherwise would be to permit a definition to distort the parties' objective intentions. As explained earlier those provisions focus on the value of the completed Project and the total cost of completing the Project (in this respect I refer in particular to the expansive definition of Total Development Costs). It would be inconsistent with those provisions to construe the 'likely cost to [Westgem] under the Building Contracts ... of achieving Practical Completion' as being limited to the costs under the Salta Building Contract and ignore any other costs of building work required to achieve Practical Completion of the Project. Further, the ability of the Financiers to assess and manage the credit risk would be significantly eroded if that construction were accepted.

The relevance of the Builder's Side Deed

  1. I do not accept Westgem's submission that the Builder's Side Deed provided ample protection for the Financiers to prevent the value of the Project (as security for the Facilities) being diminished by variations under the Salta Building Contract. The Builder's Side Deed imposed restrictions on Salta and Westgem performing variations to the Works without the Security Trustee's consent. In particular:

(a) Clause 3.3 of the Builder's Side Deed provided as follows:[96]

3.3 Variations to the Works

(1) Neither the Borrower nor the Builder may without the prior consent of the Security Trustee perform a Variation to the Works or do anything which has the effect of a Variation to the Works unless the Variation or other act is a Permitted variation.

(2) The Borrower must promptly inform the Security Trustee of any Permitted Variations.

(b) 'Variation' was defined in the Builder's Side Deed in the following terms:[97]

Variation means a variation to the Works, directed by the Superintendent in accordance with the Building Contract, including in respect of any provisional sum work and any adjustment to the price as a consequence of performing that work.

(c) 'Permitted Variation' was defined as follows:[98]

Permitted Variation means a Variation to the Works which:

(a) will result in an increase to the cost of the Works of no more than $250,000 for each individual variation and no more than $2,500,000 in aggregate in any calendar year; or

(b) will increase the time taken to bring the Works to completion in accordance with the Building Contract by no more than 10 days for each individual variation and no more than 60 days when aggregated with all variations made up to that time whether with or without the Security Trustee's consent,

but which is not a Variation to the Works:

(c) as to quality of the Works which in the opinion of the Security Trustee (acting reasonably) may have a material adverse effect on the value of the Works; or

(d) which occurs because of the acceptance of work done other than in accordance with the Building Contract; or

(e) which would or might make the Works unsuitable for the purpose stated in the Building Contract as at the date of this document.
  1. The assumption of extensive obligations by the Salta companies in favour of the Financiers under the Builder's Side Deed assisted the Financiers in managing the risks arising from the performance of the Salta Building Contracts. The Builder's Side Deed created privity of contract between Salta and the Financiers and its provisions operated in the specific context of the Salta Building Contracts. The rights conferred upon the Financiers by the Builder's Side Deed supplemented the protection afforded by the MOFA. They do not provide a basis for adopting a restrictive approach to the construction of the protections under the MOFA. To the extent to which there is any duplication in the protection obtained by the Financiers it reflects the fact that banks lending large sums of money insist upon obtaining sweeping powers to protect their interests and this is part of the price borrowers pay for obtaining and using the money lent.[99]
  2. Before leaving the reliance that Westgem places on the Builder's Side Deed it is convenient to make a further point. Westgem contended the excision of the tunnel from Salta's scope of work was a Permitted Variation because the excision of tunnel did not result either in an increase in the cost of the Works of 'no more than $250,000' or an increase in the time taken to bring the Works to completion, and it was not a Variation which fell within one of the circumstances, the carve outs, specified in subpars (c), (d) or (e) of the definition of 'Permitted Variation'. In my view this contention highlights a difficulty in Westgem's argument that the Builder's Side Deed provided ample protection for the Financiers' interests. Assuming for the sake of this argument that Westgem's construction of the definition of 'Permitted Variation' is correct and the excision of the tunnel work constituted a Permitted Variation, the excision of the tunnel from Salta's scope of work and the awarding of the tunnel work to another builder provides an example of the potential for Westgem to reduce the likely cost under the Salta Building Contract without effecting a reduction in the amount required to be expended to achieve Practical Completion of the Project.

The requirement for adherence to the contractual formula and reasonableness

  1. If the Facility Agent made a determination of the Cost to Complete otherwise than in accordance with the provisions set out in the definition of 'Cost to Complete' in the MOFA then that determination would be of no contractual effect.
  2. 'Cost to Complete' meant 'the amount reasonably determined' ‑ the use of this language necessarily connotes that the Facility Agent was required to act honestly (honesty being an element of reasonableness) and reasonably so that if the Facility Agent determined an amount capriciously or irrationally, or made a determination that no reasonable person could make, it would not be an amount determined reasonably and would thus not be an amount determined in accordance with the MOFA. It would be a contractual nullity.
  3. If in determining the Cost to Complete the Facility Agent took into account all the matters it was required to take into account by the definition then considerable latitude should be afforded to the Facility Agent before reaching the conclusion that the Facility Agent had determined the amount unreasonably. If the amount so determined by the Facility Agent was objectively reasonable then it would be difficult to sustain the conclusion that there had been any capriciousness or irrationality on its part.
  4. As I explain later in these reasons, I consider that the Facility Agent adopted the correct construction of the Cost Overrun provisions, acted reasonably and that the conclusions that the first and second Cost Overruns occurred were objectively correct.

Provisional sums and the tunnel

  1. Westgem supported its contention that because the tunnel was listed as a 'provisional sum' item in Annexure Part C of the Salta Building Contract it did not form part of the work to be undertaken under the Salta Building Contract unless the Superintendent directed it to be undertaken by reference to GC 11 of the Salta Building Contract. GC 11 commenced with the heading 'Provisional Sums' and provided:
[Westgem] has provided the amounts and descriptions for the Provisional Sums listed in Annexure Part C which has been included in the Contract. [Salta does not warrant the sufficiency of the Provisional Sum amounts. A provisional sum included in the Contract shall not itself be payable by the Principal but where at the direction of the Superintendent the work or item to which the provisional sum relates is performed or supplied by -

(a) The Contractor, the work or item shall be valued under Clause 40.5; ...
  1. GC 11 continued by setting out in subcl (b) and (c) how work or items the subject of provisional sums were to be valued for payment purposes, depending on whether the work was carried out by a subcontractor or a Nominated Subcontractor. GC 11 dealt also with the integrated fit out works and provided that Salta was not obliged to undertake the integrated fit out works unless agreement was reached with Westgem on the terms on which it would undertake that work.
  2. 'Provisional Sum' was defined in cl 2 of the Building Contract to include 'monetary sum, contingency sum and prime cost item'. There was no definition of 'contingency sum' or 'prime cost item'.
  3. The Financiers contested Westgem's construction of the term 'Provisional Sum' on a number of different grounds. The first ground was that the authorities recognise a distinction between provisional sum items and contingent sum items. In Taylor Woodrow International Ltd v Minister of Health, Bray CJ referred to the explanations of the meanings of the expressions 'provisional sum' and 'prime cost' in the then current edition of Hudson's Building and Engineering Contracts (10th ed, 1970) and observed:[100]
There is no controversy about [prime cost items] and [provisional sums]. Though distinguished in traditional language they really mean much the same thing ... They are to some extent conventional figures inserted into the contract for certain items of labour or materials which are to be executed or provided, but the actual costs of which is uncertain and when ascertained may lead to an adjustment of the contract price up or down as the case may be. The word 'provisional' does not mean 'contingent' but something provided for in the contract to be subject to adjustment.
  1. The second ground relied on by the Financiers was that where in the Salta Building Contract the parties intended a sum should be contingent and the work not allocated to Salta, the Salta Building Contract said so, for example, the IFO work, which was the subject of an express provision included within GC 11 of the Salta Building Contract.
  2. The third ground relied on by the Financiers was that many of the items of work listed as Provisional Sum items were essential to the Project - they were not optional or discretionary items of work. The Provisional Sum items included items such as precast concrete panels, brickwork and blockwork, support structures and components and wall and ceiling finishes.
  3. Fourth, the Financiers pointed to the definition of 'Contract Sum' in GC 2 of the Salta Building Contract and noted that it included provisional sums.
  4. I do not accept Westgem's contention that because the tunnel was the subject of a provisional sum allowance, it did not form part of the work Salta was obliged to undertake under the Salta Building Contract, unless directed to do so by the Superintendent. The contractual definition of 'Provisional Sums' included both provisional sums or prime cost items in the sense explained by Bray CJ in Taylor Woodrow as well as the IFO works. The estimated cost of the IFO works could properly be characterised as a contingent sum because whether the work was undertaken or not depended on the contingency of an agreement being reached between Salta and Westgem being satisfied. The phrase 'A provisional sum included in the Contract shall not itself be payable by the Principal' in the third sentence of GC 11 was intended to convey no more than that the sum specified in Annexure Part C for a particular item of work was not necessarily the sum that was to be paid by the Principal for that item of work. It did not convey that the items of work themselves were 'contingent' or only to be undertaken if there was a direction by the Superintendent to do so. As the Financiers contended many of the items of work the subject of provisional sum allowances were essential to the construction of Raine Square.

The tunnel and the definition of the Land

  1. Westgem contended that the tunnel did not form part of the Project because the tunnel was not on the 'Land', that is, 'the property at the corner of William, Wellington, Queen and Murray Streets, Perth'. Westgem's contention highlights an internal inconsistency in the drafting of the definition of the Project - as Westgem correctly point out the tunnel was not situated on the Land - it was under William Street - but it was, however, the subject of the Works. An amount of $4,300,000 was allowed as a provisional sum in the Salta Building Contract for the tunnel works. The cost of the tunnel formed part of the fixed price of $211,879,573 ($282,879,573 less $70,000,000 for the Bankwest fit out works) that was included in the Approved Project Budget.[101] As the tunnel work was the subject of the Salta Building Contract it was part of the Works as defined in cl 1.1(127) of the MOFA. The tunnel was required to be completed under the City of Perth Development Approval that governed the Project and this reinforces the conclusion that it was both the subject of the Building Contract and part of the Project.[102]
  2. In my view the reference to the 'Land' was included in the definition of the Project to identify the Project's location and not as a criterion by which the precise ambit of the Project was to be determined. The drafting has gone awry and there is a disconnect between the definitions. An obvious mistake has been made. As part of the process of construction the court has power to correct obvious mistakes in the written expression of the parties.[103] In my view the definition of 'Project' should be construed as including the tunnel.

Conclusion on construction of Cost to Complete

  1. For the reasons I have stated I do not accept Westgem's construction of the definition of Cost to Complete. In my view subpar (a) of the definition required the likely cost to Westgem under the Building Contract with Salta and the likely cost of building work necessary to achieve Practical Completion of the Project under any other contracts for building work (whether entered into at the date of the determination or proposed to be entered into) to be taken into account for the purposes of calculating the amount required to be expended to achieve Practical Completion.

The MOFA terms contended for by Westgem

Code Conduct Term
  1. Westgem pleaded that the MOFA contained a term that Bankwest would act fairly and reasonably and in a consistent and ethical manner and that in doing so Bankwest would have regard to the conduct of Westgem, its own conduct and the contract between it and Westgem. This term was said to result from Bankwest's adoption of the Banking Code. Westgem contended that the Code Conduct Term was an express term of the MOFA,[104] alternatively that it constituted a collateral contract between Westgem and the MOFA guarantors.[105] Westgem contended that whichever contractual analysis was adopted the resulting contract conferred a benefit directly on each person who was a guarantor of Westgem's obligations and was enforceable under s 11(2) of the Property Law Act 1969 (WA) by each guarantor.[106]
  2. It was common ground that Bankwest adopted the Banking Code on 1 April 2005 and that it held itself out to the public as having adopted the Banking Code in respect of its dealings with its individual and small business customers or prospective customers and their guarantors.
  3. In summary, the reason why I have concluded that the Code Conduct Term was not incorporated into the MOFA is because I do not accept that by executing the MOFA Westgem was accepting an offer by Bankwest to provide banking facilities in accordance with the Banking Code. As I will explain there are a number of different elements to that conclusion.

Relevant provisions of the Banking Code

  1. The Banking Code was divided into Parts A to F. Part A comprised an introduction expressed as follows:[107]
This Code is a voluntary code of conduct which sets standards of good banking practice for us to follow when dealing with persons who are, or who may become, our individual and small business customers and their guarantors.[108]
  1. Part B comprised provisions described as 'Our Key Commitments and General Obligations' - cl 2 provided:[109]
    1. Our key commitments to you
2.1 We will:
(a) continuously work towards improving the standards of practice and service in the banking industry;

(b) promote better informed decisions about our banking services:
(i) by providing effective disclosure of information;

(ii) by explaining to you, when asked, the contents of brochures and other written information about banking services; and

(iii) if you ask us for advice on banking services:

(A) by providing that advice through our staff authorised to give such advice;

(B) by referring you to appropriate external sources of advice; or

(C) by recommending that you seek advice from someone such as your legal or financial advisor;

(c) provide general information about the rights and obligations that arise out of the banker and and customer relationship in relation to banking services;

(d) provide information to you in plain language; and

(e) monitor external developments relating to banking codes of practice, legislative changes and related issues.
2.2 We will act fairly and reasonably towards you in a consistent and ethical manner. In doing so we will consider your conduct, our conduct and the contract between us.

2.3 In meeting our key commitments to you, we will have regard to our prudential obligations.
  1. Part C dealt with disclosures to be made in respect of banking services. Part D set out 'Principles of Conduct'. These principles dealt with aspects of banking practice that might give rise to issues in the course of a retail banking relationship, such as, the provision of information on the opening of accounts, the cancellation of direct debits, the provision of statements, joint accounts and included provisions setting out how a bank should deal with guarantees (cl 28). Part E set out procedures for the resolution of disputes, the monitoring of compliance with the Banking Code and the imposition of sanctions.
  2. Part F set out provisions governing the application of the Banking Code (cl 39). Part F also contained a dictionary of the terms used in the Banking Code (cl 40). Clause 39.1 of the Banking Code provided:
On and after [1 April 2005]:

(a) we will be bound by this Code in respect of:
(i) any banking service that we commenced to provide to you; and

(ii) any Guarantee (as described in clause 28) we obtain from you,

except as provided for below;

  1. Clause 40 included the following relevant definitions:

(a) 'banking service'

means any financial service or product provided by us in Australia to you;

(a) including any financial service or product provided by us whether supplied directly or through an intermediary; and

(b) in the case of a financial service or product provided by another party and distributed by us, extends only to our distribution or supply of the service or product to you and not to the service or product itself.

(b) 'small business'

means a business having:

(a) less than 100 full time (or equivalent) people if the business is or includes the manufacture of goods; or

(b) in any other case, less than 20 full-time (or equivalent) people,

unless the banking service is provided for use in connection with a business that does not meet the elements in (a) or (b) above.

(c) 'we, us and our':

means the bank that you deal with that has adopted this Code.

(d) 'you and your'

means a person who at the time the banking service is provided, is an individual or a small business that is our customer (or, where this Code specifically applies to potential customers, a potential customer of ours) and includes, in clauses 28, 33 and 39 any individual from whom we have obtained, or proposed to obtain, a Guarantee...[110]

Overview of parties' principal contentions on the Code Conduct Term

Westgem's contentions

  1. Westgem contended that by holding itself out to the public as having adopted the Banking Code, Bankwest made an offer to its prospective individual and small business customers and their guarantors to be bound by the Banking Code in its dealings with them. It contended for factual findings to the effect that Westgem and its guarantors knew of Bankwest's offer and Westgem and its guarantors accepted that offer by engaging Bankwest to provide them with banking services. Westgem drew attention to the fact that the Banking Code was expressly incorporated into the terms of the guarantees given by Mr Saraceni and Mr and Mrs Pourzand.[111]
  2. The issue to which much of the argument on the Code Conduct Term was directed was whether Westgem was a small business within the meaning of that expression as defined in cl 40 of the Banking Code. Westgem contended that the expression '... having ... less than 20 full time (or equivalent) people' meant having less than 20 full time or equivalent employees. Westgem contended that this construction is consistent with the approach taken in other cases.[112] As Westgem had one director and no employees it was a 'small business' as defined by the Banking Code.
  3. In response to the Financiers' argument that Westgem was not a small business because it used more than 20 full time equivalent people to complete the Project, Westgem contended that 'using' more than 20 full time equivalent people did not mean that it was a business 'having' more than 20 full time equivalent people. Westgem argued that whilst 'somewhat ambiguous', the reference to 'having' in the definition of small business was a reference to employees as opposed to third parties engaged or used by the business. Westgem observed that having less than a certain number of employees, as opposed to 'people' is a common definitional requirement of a small business and referred to the definitions in the ASIC Act, s 12BC(2) and the Fair Work Act 2009 (Cth), s 23(1). It contended that the expression 'having ... people' in the definition of 'small business' was a product of plain English drafting rather than an intention to depart from what is commonly a requirement of being a small business. Westgem contended that its construction was one that led to certainty and was to be preferred over that contended for by the Financiers being one that would lead to 'interminable disputes and evidentiary difficulties'.

Financiers' contentions

  1. The Financiers made a preliminary point that even if it applies, the Banking Code is of limited, if any, significance for two reasons. First, there is authority to the effect that adherence to the Banking Code does not require a bank to qualify or negate its own interests to those of the customer or to prefer the interests of the customer. Rather, cl 2.2 of the Code is directed to the manner of exercise of the contractual right or power and does not operate to qualify or vary any contractual right or power: Seeto v Bank of Western Australia Ltd.[113] Secondly, the allegations of breaches of the Banking Code were only ever asserted by Westgem together with allegations of unconscionable conduct and thus the breaches of the Code of Conduct Term claims only have practical significance if the obligation to act fairly, reasonably and ethically impose a stricter obligation on Bankwest than its obligation not to act unconscionably.
  2. The Financiers primary contentions were as follows:

(a) the Banking Code does not apply because Bankwest was providing a banking service in connection with a business that had more than 20 full time people so it was not a 'small business';

(b) the Banking Code does not apply to BOSI or to the Security Trustee because they are not signatories to the Banking Code;

(c) the Banking Code was not incorporated into the MOFA, alternatively it did not form part of a collateral contract.

  1. The Financiers identified the critical issue for determination as whether 'at the relevant time, Westgem or, more accurately, the business activity it conducted, had less than 20 full time (or equivalent) people, or whether the banking service provided pursuant to the MOFA was for use in connection with a business which did not meet the elements just referred to'.[114]
  2. The Financiers contended that the definition of 'small business' focused not on the individual or legal entity with which the relevant Bank is dealing but rather with 'a business'. They contended that the focus of the provision was on the nature and scope of the activity being conducted in connection with which the banking service was provided. In this respect they emphasised that the definition of 'small business' did not operate by reference to the precise legal nature of that relationship between the 'business' and the 'people' referred to. They suggested that the term 'people' was selected in place of expressions which involve a consideration of such legal relationships such as employees and officers because the adoption of the concept of 'business' (as distinct from the person or entity conducting the business) means that such analysis is not apt.
  3. The Financiers argued that the definition calls for analysis of the nature of the business conducted and of the nature and extent of the participation in that business of individuals who might comprise 'people' of the business. This in turn requires consideration of the nature and degree of connection between the business enterprise and the individuals under consideration.
  4. The Financiers argued that the exception to the definition of 'small business' embodied in the words '[u]nless the banking service is provided for use in connection with a business that does not meet the elements in (a) or (b) above' is instructive and provides support for its contention that what is required is not an analysis of strict legal relationships but a qualitative assessment of those relationships in order to determine whether a business is a 'small business' for the purposes of the Banking Code.
  5. The Financiers contended that the definition of 'small business' should be given a purposive construction that should not be construed narrowly without a common sense appreciation of the objectives of the Banking Code, the nature of Westgem, the business conducted by it or of the service provided to that business. In this respect the Financiers emphasised that the banking service was being provided for the purposes of the construction of a high rise development involving estimated total expenditure of over $430,000,000.
  6. Although the Financiers' primary argument was that Westgem was not a 'small business' for the purposes of the Banking Code, in the alternative, it put acceptance of Bankwest's offer in issue.[115]

Statement of Agreed Facts

  1. The parties prepared a Statement of Agreed Facts,[116] which identified persons, companies and trusts (and their beneficiaries) which were in some way associated with Westgem or the Project and who potentially comprised 'people' for the purposes of the Banking Code. The Financiers analysed the 'people' as follows:

(a) Those with an ownership or economic stake in the business being the beneficiaries of the various trusts on whose behalf Westgem owned the Project - the Financiers contended the beneficiaries had an economic stake in the business and should be regarded as part owners of it.

(b) Those actively involved in the conduct of the business, in addition to Mr Saraceni and Mr Pourzand, and who could be divided into two sub-categories:

(i) Employees, or agents of, or consultants to, either Westgem or the various Saraceni entities engaged in connection with the Project and who in a practical sense carried on the business of Westgem. At any relevant time, there were no fewer than 13 such persons calculated on a full time (or equivalent) basis.

(ii) Persons employed or otherwise engaged by contractors or consultants retained by Westgem to conduct the Project or to provide advice to Westgem in connection with the Project or related banking service. Those persons included Mr Clohessy, Salta personnel (and subsequently, Probuild personnel), Bollig (the project architect) personnel, NS Projects personnel and employees of the leasing agents. At all relevant times there were no fewer than 20 persons in this category calculated on a full time (or equivalent) basis.

Consideration of Code Conduct Term

  1. As explained earlier, Mr Saraceni was the sole director of Westgem and it had no employees.
  2. Westgem contends that it and the guarantors accepted Bankwest's offer to be bound by the Banking Code in respect of its dealings with them in connection with the MOFA. This contention must be examined carefully.
  3. It may be accepted that by adopting the Banking Code Bankwest held itself out as making an offer to prospective individual and small business customers and their guarantors to be bound by the Banking Code when dealing with them.
  4. Albeit with some reservation, given the absence of direct evidence, I will accept that Westgem and its guarantors knew of Bankwest's offer.
  5. Westgem pleaded that Bankwest's offer was capable of acceptance by a prospective individual or small business customer entering into negotiations or an agreement for the provision of banking services by Bankwest in terms that were not inconsistent with or which did not exclude the operation of the Banking Code.[117]
  6. Proof of performance of the conditions to an offer by a person who knows of its existence will in general constitute prima facie evidence of acceptance of the offer.[118] In the context of a discussion about an offer of reward for the giving of information, Starke J stated the principle in R v Clarke, as follows: [119]
In my opinion the true principle applicable to this type of case is that unless a person performs the conditions of the offer, acting upon its faith or in reliance upon it, he does not accept the offer and the offeror is not bound to him. As a matter of proof any person knowing of the offer who performs its conditions establishes prima facie an acceptance of that offer ... It is an inference of fact and may be excluded by evidence.
  1. In Dalgety Australia Ltd v Harris,[120] Glass JA (with whom Samuels JA agreed) explained the necessity to examine the circumstances in which the acts proffered as acceptance of an offer were undertaken. Emphasising the need for careful examination, Glass JA observed:[121]
An inference available in an evidentiary situation where offeree and offeror are the only parties involved may not be available where the offeree's conduct is explicable by reference to a contract with a third party. Where the evidence establishes a course of dealing between the offeree and a third party which precedes the offer and follows it without alteration, the basis for inferring a causal connection between the offer and subsequent dealing may be entirely lacking.
  1. The act relied upon by Westgem as acceptance of Bankwest's offer to be bound by the terms of the Banking Code in its dealings with its individual and small business customers was the execution by Westgem and the guarantors of the MOFA.[122]
  2. Contrary to Westgem's case, the MOFA was not an agreement under which Bankwest agreed to provide Westgem with banking services. Rather the MOFA was an agreement under which BOSI and Bankwest jointly agreed to provide Westgem with banking services in the form of the Facilities.
  3. In the absence of an express provision to the contrary the obligation on BOSI and Bankwest to provide the Facilities was a joint obligation (albeit that as between themselves they contributed different proportions of the monies advanced under the Facilities).[123] It is common ground that BOSI had not adopted the Banking Code. The MOFA did not provide for the Facilities to be provided on the basis of one set of terms by BOSI (that is without regard to the provisions of the Banking Code) and on the basis of another set of terms by Bankwest (that is, in compliance with the Banking Code). That the Financiers bound themselves to provide the Facilities on a uniform basis and not on terms that differed between them compels the conclusion that it was not a term of the MOFA that Bankwest was obliged to comply with the provisions of the Banking Code.
  4. When regard is had to the nature of the obligations assumed by Bankwest and BOSI under the MOFA the only inference that arises from Westgem's execution of the MOFA is that it was accepting an offer made by BOSI and Bankwest to provide a banking service constituted by the Facilities on the terms set out in the MOFA. The inference that Westgem was accepting an offer by Bankwest to be bound by the Banking Code in its dealings with it, does not arise from Westgem's execution of the MOFA.
  5. The fact that Bankwest was a party to the MOFA in two capacities, as a Financier jointly with BOSI and, separately, as Facility Agent is a further matter that stands in the way of the incorporation of the Code Conduct Term as a term of the MOFA. It is important to note that Westgem alleged that Bankwest breached the Code Conduct Term in its capacity as Facility Agent. This requires an examination of Bankwest's responsibilities as Facility Agent.
  6. The terms of the MOFA governing the role of the Facility Agent were inconsistent with the Banking Code in the manner explained below. Consequently, executing the MOFA under which Bankwest was the Facility Agent, provides no support for an inference that by so doing Westgem was accepting an offer by Bankwest to be bound by the terms of the Banking Code. To the contrary these matters negate such an inference.
  7. Relevantly:

(a) Clause 41.1 governed the appointment of the Facility Agent and provided:

41.1 Appointment

Subject to clause 41.6:

(1) each of the Finance Parties appoints the Facility Agent to act as its agent under and in connection with the Transaction Documents; and

(2) each of the Finance Parties authorises the Facility Agent to exercise the rights, powers, authorities and discretions specifically given to the Facility Agent under or in connection with the Transaction Documents together with any other incidental rights, powers, authorities and discretions.

(b) Clause 41.2 set out the duties of the Facility Agent. Subclauses 41.2(1) to (5) concerned the Facility Agent's duties to give notice of various matters to the Finance Parties, however, subcl 41.2(5) summarised the nature of the Facility Agent's duties in these terms:

(5) The Facility Agent's duties under the Transaction Documents are solely mechanical and administrative in nature. The Facility Agent has no other duties save as expressly provided for in the Transaction Documents.

(c) Clause 41.6 governed the exercise of the Facility Agent's rights, powers, authorities or discretions and provided:

41.6 Finance Parties' instructions

(1) Unless a contrary indication appears in a Transaction Document, the Facility Agent must:
(a) exercise any right, power, authority or discretion vested in it as Facility Agent in accordance with clause 41.6(3); and

(b) request information under clause 15.1(1)(f) if reasonably instructed by a Finance Party; and

(c) not be liable for any act (or omission) if it acts (or refrains from taking any action) in accordance with the instructions of the Finance Parties.
(2) Unless a contrary indication appears in a Transaction Document any instructions given by the Finance Parties will be binding on all the Finance Parties.

(3)
(a) The Facility Agent must obtain the instructions of the Finance Parties prior to exercising any right, power, authority or discretion vested in it under any Transaction Document as follows:

(i) if an Event of Default has not occurred and the Facility Agent has been unable to obtain instructions after 20 Business Days, the Facility Agent may then exercise the relevant right, power, authority or discretion; and

(ii) if an Event of Default has occurred, the Facility Agent must not exercise the relevant right, power, authority or discretion without obtaining the instructions of the Finance Parties.

(b) The Facility Agent must not exercise any right, power, authority or discretion vested in it under any Transaction Document in the absence of instructions from the Finance Parties other than in accordance with this clause 41.6(3).

(c) If the Facility Agent exercises any right, power, authority or discretion vested in it under any Transaction Document in the absence of instructions from the Finance Parties in accordance with this clause 41.6(3), the Facility Agent must only do so in a manner that is not prejudicial to the interests of the Finance Parties under the Transaction Documents.

(d) The Finance Parties must use their best endeavours to promptly provide instructions to the Facility Agent for the purposes of this clause 41.6(3).
(4) The Facility Agent is not authorised to act on behalf of a Finance Party (without first obtaining that Finance Party's consent) in any legal or arbitration proceedings relating to any Transaction Document.

(d) Clause 41.10 provided that the Facility Agent could resign and either appoint a related body corporate as successor (cl 41.10(1)) or simply resign (cl 41.10(2)). On the appointment of a successor the retiring Facility Agent would be discharged from any further obligation.

246 In its capacity as the Facility Agent, Bankwest was involved in facilitating the provision of a banking service but it was not providing a banking service in its own right. It acted as the Financiers' agent and in that capacity did not assume any obligations to Westgem that were additional to those imposed on the Financiers by the MOFA.

  1. As Facility Agent, Bankwest was obliged to comply with instructions received from the Financiers. Its role, as described in cl 41.2(5), was 'solely mechanical and administrative in nature', though I observe that determining the Cost to Complete involved making a determination that was not 'mechanical and administrative in nature'. Importantly cl 41.2(5) made clear that as Facility Agent, Bankwest did not assume 'other duties save as expressly provided for in the Transaction Documents'. The limited nature of Bankwest's role was emphasised by its entitlement to resign as Facility Agent and for another entity to be appointed in its place.
  2. These features of the Facility Agent's role under the MOFA are inconsistent with the Banking Code. The Banking Code contemplates a bank operating in accordance with its terms unconstrained by the requirement to comply with instructions from any other entity not bound by the Banking Code. Moreover, the Banking Code does not contemplate a bank being able to bring an end to its obligations by 'resigning'.
  3. The inconsistency between the terms of the MOFA and the terms of the Banking Code stands in the way of concluding that Westgem accepted an offer from Bankwest to provide it with banking services in accordance with the terms of the Banking Code.

Westgem - a small business

  1. Although for the reasons set out above I have concluded that the Code Conduct Term was not a term of the MOFA, out of deference to the parties extensive submissions on the issue I will set out my reasons for concluding that Westgem was a 'small business' for the purposes of the Banking Code. I do so even though I am sure that the Banking Code was not prepared with sophisticated business people such as Mr Saraceni and Mr Pourzand, or transactions such as the financing of the Project, in mind.
  2. In Sam Management Services (Aust) Pty Ltd v Bank of Western Australia Ltd Young AJA observed that the Code is:[124]
... [A] document which was probably never prepared by its drafters to form part of the legal document. It is drafted as a lay person's document to be understood in a quick reading by a person considering dealing with the bank. It thus lacks the precision that one would expect in a term to be included in a contract dealing with megadollars.
  1. Young AJA went on to refer to the Code as 'promotional material'.
  2. The Code applies to 'individual and small business customers and their guarantors'. The defined term 'you and your' means 'a person who ... an individual or small business that is our customer'. The first question to be asked in determining the applicability of the Code is: who is the legal entity that is the customer? In this case it was not in dispute that the relevant legal entity was Westgem.
  3. The next question is whether Westgem was a 'small business customer', that is, relevantly, was it a business 'having ... less than 20 full time (or equivalent) people'.
  4. In the cases cited by Westgem: Sam Management Services (Aust) Pty Ltd v Bank of Western Australia Ltd; Commonwealth Bank of Australia v Starrs; International Skin Care Suppliers Pty Ltd v Commonwealth Bank of Australia, the proposition that the reference to people in the definition of small business means employees appears to have been an uncontroversial proposition and the arguments raised by the Financiers in this case did not arise.
  5. The qualification of 'people' by the words 'full time (or equivalent)' makes it clear that the definition is concerned with those working in the customer's business and does not include those with an economic stake in the business but who may not be working in it, relevantly in this case the beneficiaries of any trust on whose behalf the business is conducted. For substantially the same reasons the word 'people' cannot be construed as a reference to any entity (or its employees) with which a customer contracts, in this case, for example, the employees of Salta or Probuild. In my view the reference to 'people' in the definition of 'small business' is a reference to employees. I agree with Westgem's submission that the relatively imprecise language used is the consequence of the plain English style of drafting used throughout the Banking Code. Construing 'people' as employees provides certainty. It avoids the need for detailed inquiries (that resulted in this case in the Statement of Agreed Facts) that would themselves be antithetical to the apparent purpose of the Banking Code.
  6. Accordingly, had I found that Westgem had accepted Bankwest's offer to be bound by the Banking Code, I would also have found that Westgem was a small business to whom the Banking Code applied.
The Event of Default term
  1. Westgem contended that 'on a proper construction of cl 18 of the MOFA and of the MOFA as a whole' it was a term of the MOFA, alternatively it was an implied term that Bankwest as Facility Agent would not allege an Event of Default or purport to exercise any of the Finance Parties' rights on default in respect of events which were not Events of Default.[125]
  2. Clause 17 of the MOFA identified those events that constituted Events of Default and cl 18 (though headed 'Finance Parties' Rights on Default') set out the rights that might be exercised by the Financiers on the occurrence of an Event of Default. Relevantly, cl 18.1 of the MOFA provided:
    1. Finance Parties' rights on Default
18.1 Consequences

In addition to any other rights provided by law or any Transaction Document, at any time after an Event of Default (unless that Event of Default has been expressly waived by the Financiers in writing or remedied to the satisfaction of the Financiers) the Financiers may do all or any of the following:

(1) by notice to the Borrower declare all money (or any part of that money as specified by the Financiers in the notice) actually or contingently owing under this document or any other Transaction Document immediately due and payable, and the Borrower will immediately pay to the Facility Agent for the account of the Financiers the aggregate Principal Outstanding under all of the Facilities together with accrued interest and fees, and all other Secured Money (where applicable as cash cover under clause 18.4) or such part of that money as is specified by the Facility Agent in the notice;

(2) by notice to the Borrower terminate the obligations of the Finance Parties under the Transaction Documents;

(3) at the cost of the Borrower, appoint Independent Consultants to review and report to the Facility Agent on the affairs, financial condition and business of the Transaction Parties;

(4) instruct the Security Trustee to enforce any or all of the Security Documents;

(5) apply the Default Rate to the Secured Money; and

(6) take any action whatsoever that the Finance Parties (or any person acting on the Finance Parties' behalf) are authorised or entitled to take under this document or any other Transaction Document on the occurrence of an Event of Default that is continuing.

(Clauses 18.2 - 18.4 governed how a Finance Party was to deal with money received after an Event of Default and are not presently relevant.)

Westgem's contentions

  1. Westgem did not develop its submissions in relation to the Event of Default term in any detail. No reference was made to it in the opening or closing written outlines of submissions. In Westgem's written closing submissions, under the heading 'Did the MOFA contain certain terms relating to events of default?', the 'reasonable grounds term' (discussed below) is addressed however the 'Event of Default term' is not mentioned. Only passing reference was made to it in oral closing submissions.[126] Westgem did not support its argument that the Event of Default term arose as a matter of construction by reference to any authority or principle. Rather Westgem's Senior Counsel expressed the position in relation to the Event of Default term as being an ad hoc implied term in the sense that:[127]
The objective bystander looking at it, it would be obvious, it's not inconsistent with the actual terms. The contract doesn't really work without it, we think.

... I can't point to any express provision and I am - I do have to resort to an implied term but we do think it's a pretty obvious implied term.

The Financier's contentions

  1. The Financiers' submissions may be summarised as follows: there is a distinction between a promise not to assert an Event of Default except in particular circumstances and a wrong assertion of an Event of Default not having any legal consequences. The general consequences of wrongly exercising a contractual power is that the result of the attempted exercise of the power is contractually ineffective - it is not the case that there is a separate and independent breach of contract that may sound in damages.

Consideration of the implication of the Event of Default term

  1. The language used in cl 17 or cl 18 of the MOFA did not contain an express negative obligation of the nature contended for by Westgem, nor is it possible to interpret the language used as imposing such an obligation.
  2. Moreover, as can be seen, cl 18 does not confer any discretion on Bankwest as Facility Agent to take any of those steps stipulated in cl 18.1(1) - 18.1(6) - it confers a contractual power on the Financiers to take those steps.
  3. The construction exercise required by Westgem's pleading of the 'proper construction of cl 18 and the MOFA as a whole' is not an exercise of the nature described by Lord Bingham MR in Philips Electronique Grand Public SA v British Sky Broadcasting Ltd involving 'resolving ambiguities or reconciling apparent inconsistencies, to attribute the true meaning to the language which the parties have themselves expressed their contract'.[128] Nor do I understand that Westgem was invoking the interpretative approach to the implication of terms outlined in Attorney General of Belize v Belize Telecom Ltd[129] by Lord Hoffmann, that is to ask the question: what would the instrument, read as a whole against the relevant background, reasonably be understood to mean, so that the test for implication therefore merges with construction of the instrument.
  4. I understand Westgem to be invoking the process that might be seen as involving elements of both implication and interpretation (a process not far removed from Lord Hoffman's approach in Belize Telecom) - that a term that might be deduced by implication, as a matter of construction of the express terms of the contract: Marcus Clark (Victoria) Ltd v Brown,[130] Brambles Holdings Ltd v Bathurst City Council,[131] New South Wales Rifle Association Inc v Commonwealth,[132] Servcorp WA Pty Ltd v Perron Investments Pty Ltd[133] and WFI Insurance Ltd v Manitowoq Platinum Pty Ltd.[134]
  5. The line of authority that supports the proposition that a term might be implied as a matter of construction begins with the judgment of Higgins J in Marcus Clark (Victoria) Limited v Brown.
  6. In Marcus Clark the issue was whether a contract constituted by an order form and a hire purchase agreement constituted an agreement for the sale, and not merely the hire, of a new car. Knox CJ, Isaacs and Powers JJ held that on a true construction of the documents the agreement was for the sale of a new car. Higgins J dissented but his dissenting judgment has been frequently cited as authority for the proposition that a term may be found by implication from the express terms of a contract. In the course of setting out what had to be established by the purchaser in order to succeed, Higgins J said:[135]
What we have to find is a warranty, or a term of the contract, that the car is new; and it must be found by necessary implication, not by logical or quasi-logical inference.

... Such an implication is not to be adopted unless it is necessary, unavoidable. This is clearly shown in the decision of the Judicial Committee of the Privy Council in Douglas v Baynes, where Lord Atkinson, speaking for the Committee, adopted of the language of Kay LJ in Hamlyn & Co v Wood & Co:
'The Court ought not to imply a term in a contract, which the parties have reduced into writing, unless there arises from the language of the contract itself, and the circumstances under which it was entered into, such an inference that both parties must have intended the stipulation in question, that the Court is necessarily driven to the conclusion that the stipulation must be implied.'
...

In each case of construction of a written contract all the words have, of course, to be considered to find out what they mean as a whole; but there is a clear difference between finding the meaning of the words used, on the one hand, and, on the other hand, drawing an inference that they imply also some 'warranty undertaking or agreement' not directly within the meaning of the actual words. (Footnotes omitted - emphasis in original)
  1. In Brambles Holdings Ltd v Bathurst City Council, Heydon JA (as his Honour then was) explained that:[136]
... terms may be implied in one of four ways. The trial judge set out this orthodox classification in his unreported interlocutory judgment in Carlton & United Breweries Ltd v Tooth & Co Ltd, which was quoted by Young J the trial judge in that case:

a more precise classification of the different types of implied terms was given by Hodgson J in his first interlocutory judgment in the current proceedings. His Honour set out for classes of implied terms, the first two of which are in the class of terms implied in law, the second two the implied terms in fact. His Honour said:

There is a spectrum of different types of implied terms, covering inter alia, the following:

(i) Implications contained in the express words of the contract: see Marcus Clarke [sic] (Vic) Ltd v Brown.

(ii) Implications from the 'nature of the contract itself' as expressed in the words of the contract: see Liverpool City Council v Irwin.

(iii) Implications from usage (for example, mercantile contracts).

(iv) implications from considerations of business efficacy: see BP Refinery (Westernport) Pty Ltd v Hastings Shire Council; Codelfa Construction Pty Ltd v State Rail Authority of NSW. (citations omitted)
  1. In Equitable Life Assurance Society v Hyman,[137] Lord Steyn explained the process of implying terms 'from the language ... read in its particular commercial setting' as follows:[138]
... The process 'is one of construction of the agreement as a whole in its commercial setting': Banque Bruxelles Lambert SA v Eagle Star Insurance Co Ltd [1996] UKHL 10; [1997] AC 191, 212E, per Lord Hoffman. This principle is sparingly and cautiously used and may never be employed to imply a term in conflict with the express terms of the text... The inquiry is entirely constructional in nature ... the question is whether the implication is strictly necessary.
  1. If one puts to one side the difficulty that the only parties who were entitled to act on an Event of Default were the Financiers and not the Facility Agent, the critical issue (as explained by Higgins J in Marcus Clark) is whether the parties must be taken to have intended that the MOFA should contain a binding promise by the Financiers that they would not exercise their cl 18 rights unless an Event of Default in fact existed, so that, for example, an exercise of those rights in the mistaken belief that there was an Event of Default, would constitute a breach of the MOFA and give rise to a liability for damages.
  2. Whilst construction issues must be resolved having regard to the text, context and purpose of the particular contract under scrutiny (and thus generalised statements of principle may be of limited utility), there is no principle that requires a contractual power or discretion to be construed as being confined by an implicit promise by the party entitled to exercise it, that it will not be exercised unless any condition on which the existence of the discretion depends is objectively proven to be satisfied.
  3. That said, there is a degree of superficial attraction to the Event of Default term because it appears reasonable. Reasonableness is not, however, the criterion governing the implication of terms,[139] and I am not persuaded that the Event of Default term arises by necessary implication. To imply such a term, the parties must be taken to have intended that the MOFA should contain a binding promise in the form of the Event of Default term. When I have regard to the express terms of the MOFA and its purpose, I am not persuaded that the parties did so intend, especially given the inclusion of clauses excluding liability on the part of Bankwest and the Financiers (cl 41.8(1) and cl 29.3) to which I refer in more detail below.
  4. The implication of the Event of Default term was not necessary to deal with the consequences that might flow from the wrongful assertion of an Event of Default. In this respect I accept the Financiers' submission that, in the absence of an express term providing otherwise, the consequence of asserting that an event was an Event of Default, when in fact it was not, is that the asserted Event of Default is of no contractual effect, and is a nullity. This is not to say that a wrongful assertion of an Event of Default might not be attended by adverse consequences. In this case persistence in an erroneous assertion of an Event of Default might evince an intention on the part of the Financiers not to be bound by the terms of the MOFA and constitute a repudiation, which might in turn give rise to a liability for damages.[140] And, if a contractual power is exercised for a purpose other than for the purpose for which it was conferred, equity will intervene to restrain the exercise of the power or to set aside the result of its exercise.[141]
  5. In the alternative to the construction argument, Westgem pleaded the Event of Default term should be implied as a matter of fact as an ad hoc term: BP Refinery (Westernport) Pty Ltd v Shire of Hastings,[142] Codelfa Construction Pty Ltd v State Rail Authority of NSW.[143]
  6. The consideration of whether the Event of Default is to be implied as a matter of fact must begin with a recitation of the well‑established conditions that must be satisfied before a term will be implied as a matter of fact, those conditions being that the term must:[144]

(a) be reasonable and equitable;

(b) be necessary to give business efficacy to the contract so that no term will be implied if the contract is effective without it;

(c) be so obvious that 'it goes without saying';

(d) be capable of clear expression; and

(e) not contradict any express terms of the contract.

  1. It follows from the view that I have expressed in the context of my assessment of the implication by construction argument that I am not persuaded that the Event of Default term was necessary to give business efficacy to the MOFA. Consequently, it was thus not an ad hoc implied term of the MOFA.
  2. An additional reason for rejecting the ad hoc implication of the Event of Default term (whether framed as a term imposing an obligation on Bankwest as Facility Agent (as pleaded) or as an obligation imposed on the Financiers), is that it is inconsistent with express terms of the MOFA that exclude liability on the part of the Facility Agent and the Financiers. Clause 41.8(1) of the MOFA provided:
(1) Without limiting 41.8 (2), the Facility Agent will not be liable for any action taken by it, or for omitting to take action under or in connection with any Transaction Document, unless directly caused by its gross negligence or wilful misconduct.
  1. And, cl 29.3 of the MOFA provided:
(3) The Finance Parties will not be liable for any loss, cost or expense of the Borrower caused or contributed to by the waiver of, exercise of attempted exercise of, failure to exercise or delay in exercising a right of the Finance Parties.
The 'reasonable grounds' term
  1. In addition, and in the alternative, to the Event of Default term, Westgem contended that on a proper construction of cl 18 of the MOFA and of the MOFA as a whole, it was a term of the MOFA, alternatively it was an implied term, that Bankwest as Facility Agent would not allege an Event of Default or purport to exercise 'the Finance Parties' rights on default in respect of events which it did not have reasonable grounds to form the opinion was an Event of Default'.[145]

Overview of parties' contentions on reasonable grounds term

Westgem's contentions

  1. Westgem's Senior Counsel put the case based upon the reasonable grounds term as follows: [146]
... when they issued the notice of default there was a term that they not do that unless they had reasonable grounds to believe that there was an event of default. And they did not because they had not reasonably determined the Cost Overrun.
  1. In its written closing submissions Westgem contended that:

(a) Whilst not finally resolved at an appellate level in Western Australia, the better view is that a commercial contract carries with it an obligation on each party to act reasonably towards the other in exercising rights - in support of this contention Westgem relied upon the decision in Burger King Corporation v Hungry Jack's Pty Ltd.[147]

(b) The MOFA, as a matter of construction, required the Financiers to make a demand in respect of a Cost Overrun and allege an Event of Default only in circumstances where there was a reasonable basis to do so.

(c) Support for a reasonable grounds term was to be found in the decisions of Commonwealth Bank Of Australia Ltd v Renstel Nominees Pty Ltd,[148] and Commonwealth Bank of Australia Ltd v Spira.[149]

  1. In oral closing submissions senior counsel for Westgem contended that the reasonable grounds term was an ad hoc implied term that satisfied the BP Refinery criteria.[150]

The Financiers' contentions

  1. The Financiers drew attention to the inconsistency between the pleading of the reasonable grounds term in par 193A of the statement of claim and the pleading of the breach in par 235, which alleged that Bankwest as Facility Agent 'had not reasonably determined that the First Alleged Cost Overrun had occurred', and pointed out that the reasonable grounds term, as formulated in par 193A was concerned with the taking of enforcement action on the basis of the existence of an unpaid Cost Overrun not on the reasonableness of the determination of the Cost Overrun.[151]
  2. Having regard to the way in which Westgem pleaded a breach of the reasonable grounds term the Financiers concentrated their submissions on the definition of Cost to Complete and, in particular, on whether the Facility Agent was under an obligation to determine the Cost to Complete reasonably. They contended that the focus of the definition of Cost to Complete was the determination of 'an amount' and it was the amount that had to be reasonable and argued that it was significant that Westgem is not contending the amount of the Cost to Complete was objectively unreasonable.
  3. The Financiers argued that the 'Cost to Complete' definition was not concerned with the process by which the amount was derived.[152] They contended that the definition required an evaluative judgment to be made about the reasonableness of an amount but that there was no express contractual promise by the Facility Agent about the way in which the existence of a Cost Overrun would be determined. They contended that the only consequence of not making an objectively reasonable determination of the contractual elements which fed into the definition of a Cost Overrun was that there was no valid determination of a Cost Overrun.
  4. The Financiers contended the determination of a Cost Overrun did not involve the exercise of a contractual discretion - it was the product of the application of other contractual definitions - the definition of 'Cost to Complete' and the definition of 'Undrawn Commitment'.
  5. The Financiers' submissions did not engage in detail with the authorities relied upon by Westgem, but in the course of oral closing submissions reference was made to the decision in Mineralogy Pty Ltd v Sino Iron Pty Ltd,[153] in which Edelman J had reviewed the authorities in relation to the concepts of good faith and reasonableness in the context of contractual discretions. The Financiers placed emphasis on Edelman J's observation to the effect that the existence and content of a 'reasonableness' implication will depend on the context and argued that the importance of contractual context meant it would be wrong to pick up general notions of good faith and reasonableness as discussed in other cases and import them into the MOFA.[154]

Consideration of the reasonable grounds term

The authorities

  1. The implication of terms requiring parties to exercise contractual powers or discretions in good faith and reasonably is supported by a number of decisions of the Court of Appeal in New South Wales - most notably the Burger King decision on which Westgem relies (in which the concept of reasonableness was equated with good faith). The necessity for the implication of such terms has not, however, been universally accepted. In Western Australia the question has been discussed in various authorities but has not been settled at appellate level.[155] The implication of terms of good faith and reasonableness in all commercial contracts as a matter of law remains unresolved in Australia.[156]
  2. Before turning to the principal authority on which Westgem relied in its written closing submissions - Burger King - reference must be made to Renard Constructions (ME) Pty Ltd v Minister for Public Works,[157] as significant aspects of the reasoning of Priestley JA and Handley JA in that case were adopted in Burger King.
  3. Renard Constructions was a case involving a construction contract in which the principal had a contractual right to terminate the contract subject to requiring the defaulting party, the contractor, to 'show cause' why the contract should not be terminated. The contractor was called upon to show cause but, despite showing cause, the principal terminated the contract.
  4. Priestley JA considered that a term should be implied requiring the principal to give reasonable consideration to whether the contractor had shown cause and, if the contractor had failed to show cause, to give reasonable consideration to whether the power to terminate should be exercised. His Honour considered that the implication could be justified on three bases: as an ad hoc implication (based on the actual intentions of the parties);[158] as an implication as a matter of law (based on imputed intention as opposed to actual intention), because the contract was a standard construction contract;[159] or as a term implied: [160]
... by reference to an intention deduced from the full scope and bearing of [the parties'] contractual intent, not the parties' mental state, and in one sense as a matter of interpretation, and upon considering the circumstances in which the parties contracted. This could all be looked at as an example of the Court deciding what implied obligation would be attached to a contract, irrespective of the actual intention of the parties and thus either implication by law rather than ad hoc, or at least as a hybrid between the two. It may also illustrate the sharp distinction between the two kinds of implication may, at least in some cases be more a matter of form and substance.
  1. In considering whether the term should be implied as a matter of fact, that is, on an ad hoc basis, Priestley JA observed that minds might differ on whether the term to be implied was necessary to give business efficacy to the contract. However, in determining that the term was necessary to give business efficacy to the contract, his Honour attached importance to the possibility that, without the protection of the reasonableness implied term, the principal could serve a show cause notice in respect of a trivial breach in respect of which the contractor might fail to show cause.[161] In so doing, Priestley JA emphasised the importance of the contractual context in the implication of terms.
  2. Handley JA concluded that the decision of the principal was objectively unreasonable. He held that the principal had to act reasonably and the obligation to do so arose as a matter of construction of the contract rather than as a result of implication.[162] In the course of his reasoning Handley JA, like Priestley JA, emphasised the possibility that the power to terminate arose on the occurrence of any breach, however minor it might be. Meagher JA did not think any basis existed for the implication of an obligation of reasonableness but found that the principal had not complied with the clause entitling it to terminate because it was required to act on the basis of accurate information when forming a view that the contractor had shown cause, and it had not done so.
  3. Renard Constructions was followed in a number of cases prior to the decision in Burger King: see Hughes Bros Pty Ltd v Trustees of the Roman Catholic Church for the Archdiocese of Sydney;[163] Hughes Aircraft Systems International v Airservices Australia;[164] Alcatel Australia Ltd v Scarcella.[165] In Alcatel, Sheller JA (with whom Powell and Beazley JJA agreed), concluded that following Renard Constructions and Hughes Bros in New South Wales a duty of good faith, both in performing obligation and exercising rights, may by implication be imposed upon parties as a legal incident of a commercial contract.[166] His Honour held that there was no reason why such a duty should not be imposed as part of the commercial lease between the parties to the action, though, on the facts held that the duty had not been breached.
  4. The facts of Burger King were complicated. One of the central issues was whether Burger King's termination of the franchise agreement with Hungry Jack's breached its implied obligations of good faith and reasonableness. At first instance Rolfe J held the termination to be wrongful, amounting to a repudiation of the agreement.
  5. In the course of reasoning to the conclusion that terms of reasonableness and good faith were to be implied in the agreement as a matter of law, the Court of Appeal considered the meaning of the terms 'good faith' and 'reasonableness' and said:[167]
... It is worth noting that the Australian cases make no distinction of substance between the implied term of reasonableness and that of good faith. As Priestley JA said in Renard Constructions (at 263): 'The kind of reasonableness I have been discussing seems to me to have much in common with the notions of good faith'.

Priestley JA commented further (at 265) that: '... In ordinary English usage there has been constant association between the words fair and reasonable. Similarly, there is a close association of ideas between the terms unreasonableness, lack of good faith and unconscionability'.

Rolfe J observed that in Alcatel Australia, Sheller JA (at 369) appeared to equate the notions of 'reasonableness' and 'good faith'. Whilst Sheller JA did not say that in terms, his review of the case law and academic and extra-judicial writings on the topic, clearly support the proposition. In addition to his references to Renard Constructions, Sheller JA (at 367) refer to the statement of Sir Anthony Mason in his 1993 Cambridge Lecture, that it was probable that the concept of good faith 'embraced no less than three related notions':

(1) an obligation on the parties to co-operate in achieving the contractual objects (loyalty to the promise itself);

(2) compliance with honest standards of conduct; and

(3) compliance with standards of contract which are reasonable having regard to the interests of the parties.
  1. Although in Burger King the Court of Appeal held that the terms of good faith and reasonableness would be implied as a matter of law, the Court referred to the terms of the agreement itself (seemingly taking an approach to analysis applicable to determining whether an ad hoc term was to be implied) and accepted a submission made on behalf of Hungry Jack's to the effect that unless there was an implied requirement of reasonableness and good faith Burger King could, for the slightest of breaches of operational requirements, bring an end to Hungry Jack's valuable contractual rights. In this respect the Court was of the view it was significant that the question of whether there had been compliance with the operational requirements involved subjective and evaluative judgements.[168]
  2. In Commonwealth Bank of Australia v Renstel Nominees Pty Ltd, Byrne J held that the plaintiff bank's right to cancel an overdraft facility might, as the result of an implication of a term to that effect, be exercised only reasonably and in good faith. In so holding, his Honour followed Renard Constructions, Alcatel, and Hughes Aircraft Systems International v Airservices Australia, and a number of first instances decisions of the Victorian Supreme Court.[169] Byrne J rejected, however, a submission made by the defendants that the Bank had breached the implied term by acting 'without proper regard to the rights of the defendants and in circumstances where its own conduct precluded the defendants' enjoyment of their contractual rights without justification'.[170] His Honour considered that the bank, in exercising its contractual discretion to cancel the overdraft facility, was entitled to have regard to its own commercial interests even if they were inimical to those of the borrower, and therefore the facts relied upon by the defendants to establish unreasonableness and lack of good faith, were of limited significance.
  3. In Commonwealth Bank of Australia v Spira, Gzell J held that it was an implied term of a facility agreement between the plaintiff bank and the defendant borrower that the bank would exercise good faith in the performance of the facility agreement and expressed his agreement with the approach advocated by Priestley JA in Renard Constructions that a term of good faith and fair dealing in the performance of contract should be implied generally.[171] Gzell J commented on the content of the implied term of good faith and said:[172]
The Court of Appeal in Burger King did not discuss the content of the implied term of good faith save to comment, apparently favourably, upon the apparent equation of the notions of reasonableness and good faith in Alcatel (at 369). The matter was considered by Barrett JA in Overlook (at [61] - [67]). His Honour concluded that the implied obligation of good faith underwrites the spirit of the contract and supports the integrity of its character. A party is precluded from cynical resort to the black letter but is not fixed with a duty to subordinate self-interest entirely. The duty is not one to prefer the interests of the other contracting party. Rather it is a duty to recognise and have due regard to the legitimate interests of both parties in the enjoyment of the fruits of the contract as delineated in its terms. The cross-claimants submitted that I should adopt his Honour's delineation of the content of the duty and I am content to do so the purpose of this case, mentioning only the content of the implied term of good faith may need further scrutiny to avoid being merely a slogan.
  1. I interpolate that if the decisions in Renard and Burger King are to be understood as treating reasonableness and good faith as synonymous then they do not stand as authority for the more onerous standard of objective reasonableness that Westgem seeks to import into the MOFA by means of the 'reasonable grounds' term.
  2. In Vodafone Pacific Ltd v Mobile Innovations Ltd,[173] in the course of addressing the question whether the contract under consideration was a contract falling within a class of contracts into which terms of good faith and reasonableness were to be implied as a matter of law, Giles JA (with whose reasons Sheller and Ipp JJA agreed) observed:[174]
... I do not think the law has yet gone so far as to say that commercial contracts are a class of contract carrying the implied terms as a legal incident, and the width and indeterminacy of the class of contracts would make it a large step.
  1. Giles JA explained that, for the purposes of deciding whether the implication of the good faith and reasonableness term as a matter of law was precluded by expression of a contrary intent, it was necessary to have in mind a content for the obligation of good faith and reasonableness as only then could one sensibly enquire whether there was inconsistency with the terms of the contract. His Honour observed there was a 'regrettable lack of uniformity in the cases' in relation to the content of the duties.[175]
  2. In Androvitsaneas v Members First Broker Network Pty Ltd[176] (a case concerning the exercise of a contractual right to terminate a Credit Representative Deed) the Victorian Court of Appeal rejected a submission that the courts will imply as a matter of law and as a legal incident of a commercial contract, terms of good faith and reasonableness, stating:[177]
We express no final conclusions upon whether the termination power here exercised was attended by a duty to act reasonably and in good faith. It is not necessary to do so. It suffices to repeat a recent statement made by this court that we do not accept that an obligation of good faith should be implied indiscriminately into all commercial contracts, but to do so ordinarily requires satisfaction of the tests laid down in BP Refinery (Westernport) Pty Ltd v Hastings Shire Council. Whether a power conferred upon a party to a contract is fettered by a duty of good faith depends upon the terms in which the power is expressed.

Potential obstacles in this case to the ad hoc implication of a duty of good faith are that the relevant termination power is (a) found within a regime that deliberately distinguishes occasions when notification and opportunities to explain are afforded, and those when they are not; and (b) is expressed in the context of a breach that is either irremediable or one that must ‘reasonably’ be considered to be material. (footnotes omitted)
  1. The reference to the 'recent statement' was to a statement to the same effect made by the Victorian Court of Appeal in Specialist Diagnostic Services Pty Ltd v Healthscope Ltd.[178]
  2. A difficulty with implying a term of reasonableness and good faith into all commercial agreements was identified by Young J in Paul Kennedy Transport Pty Ltd v Australia and New Zealand Banking Group Ltd,[179] shortly after the decision in Renard Constructions. That case concerned an application by the plaintiff company to restrain a receiver, which had been put into its business by ANZ, from acting as such. The receiver had been appointed pursuant to a mortgage debenture in favour of ANZ. The plaintiff submitted (relying on Renard Constructions) that 'on the true construction of the mortgage debenture there was a contractual duty of the bank to act reasonably if a default had been made before putting in a receiver'. Young J referred to the decision in Renard Constructions and concluded his reasons with remarks of significance for this case:
It is very difficult indeed, in my view, to argue by analogy from that case to the case of a mortgagee. The rules have been for generations that even if the form of the mortgage is not one where the mortgagee becomes the owner of the property, the mortgagee is to be regarded as the owner of the property and is able to deal with the property as it considers most appropriate in its own interests, subject only to the contractual and fiduciary duties owed to the mortgagor. It is also clear that, with certain exceptions, the mortgagee when it sees a situation has arisen in which its security is threatened, may act so as to protect itself, at least so long as it does not sacrifice the interest of the mortgagor. It seems to me impossible in this background to find that there could be implied into the mortgage debenture a term that the mortgagee was only to act reasonably in an objective sense in appointing a receiver. (emphasis supplied)
  1. Observations to a similar effect to those of Young J cited above were made by the Full Federal Court (Neaves, Miles & O'Loughlin JJ) in Canberra Advance Bank Ltd v Benny.[180]
  2. In Mineralogy Pty Ltd v Sino Iron Pty Ltd [No 6], one of the issues addressed by Edelman J was whether a contractual discretion to issue termination notices in respect of alleged breaches of Facilities Deeds was subject to an implied term that the party issuing the notices would act reasonably and in good faith. Edelman J held that no such term should be implied. In the course of his analysis his Honour emphasised the importance of paying careful attention to the contractual context in determining the implication of terms. Edelman J held that the implication failed for three reasons all arising from the contractual context: first, the relevant contractual discretion concerned the issue of a termination notice rather than termination of the deeds themselves; secondly, a reasonable time had to be given to remedy the breach; and lastly, the discretion could only be exercised where the breach was, objectively determined, to be a 'serious or persistent' breach.
  3. Although the focus of Edelman J's analysis was on the implication of a 'good faith' term, his Honour's observations are instructive as to considerations that bear upon the implication of a term that a contractual discretion will be exercised reasonably. The guidance that may be derived from Edelman J's analysis includes the following.

(a) The test for implication of a term of good faith and reasonableness was that set out in BP Refinery (Westernport) Pty Ltd - his Honour implicitly rejected the earlier authorities in which it had been held that such terms are to be implied as a matter of law.

(b) One difficulty with the implication of a term of 'good faith' is that the phrase means different things in different contexts - I interpolate that 'reasonableness' shares this protean quality. Edelman J noted that in Macquarie International Health Clinic Pty Ltd v Sydney South West Area Health Service,[181] Allsop P extracted three particular rules which will usually form the content of the obligation of 'good faith' (although recognising the content of the obligation will always depend on the terms of the contract): first, obligations to act honestly and with fidelity to the bargain; secondly, obligations not to act dishonestly and not undermine the bargain entered or the substance of the contractual benefit bargained for; and thirdly, an obligation to act reasonably and having regard to the interests of the parties (which will, inevitably, at times conflict) and to the provisions, aims and purposes of the contract, objectively ascertained. None of those obligations requires the interests of the party to be subordinated to those of the other.

(c) The rejection of an implication of an obligation of good faith in all commercial contracts by the Victorian Court of Appeal in Androvitsaneas v Members First Broker Network was correct for two reasons: first, because questions of implication require close focus on the terms of the relevant contract, and, secondly because the potential for the content of a 'good faith' obligation to vary according to the contractual context.

(d) The content of a term requiring a contractual discretion to be exercised reasonably might reflect the reasonableness requirement in judicial review. In this respect Edelman J referred to the observations of Lady Hale in Braganza v BP Shipping Ltd,[182] to the effect that the implication of a term concerning the manner which a contractual discretion might be exercised was 'drawing closer and closer to the principles applicable in judicial review'. His Honour expressed the view that there were good reasons why this English approach should be applied to permit an Australian implication of reasonableness in the exercise of a discretionary statutory or contractual power. His Honour doubted whether there should be a general limitation on an implied qualification of reasonableness such that the obligation applies only to circumstances of irrationality or where the outcome of the exercise of power is so unreasonable that no reasonable decision maker could ever have acted in that way.[183]

  1. In Minumbra Lancewood Pty Ltd v AM Lancewood Investment Nominees Pty Ltd,[184] the borrower alleged that the lender had terminated a loan agreement on the grounds that an event of default had occurred when it had not. The event of default relied upon by the lender was that there had been a 'Material Adverse Change' which was defined as:[185]
any situation occurs which in the opinion of the Lender gives it grounds to believe that a material and adverse change in the business or financial condition of the Borrower has occurred or that the ability of the Borrower to perform its obligations under this Agreement has been or will be materially and adversely affected or that any other Event of Default is likely to occur.
  1. Robb J rejected the borrower's contention that the opinion that the lender was required to form had to be based on facts that objectively proved and supported the existence of one of the three 'limbs' included in the definition of event of default. Robb J concluded that if there was any requirement that there be a reasonable basis for the formation of the opinion it was 'not so extreme as to require that the opinion be objectively valid based upon the facts'. Robb J construed the provision and gave separate consideration to each 'limb'. Factors that were prominent in his Honour's reasons for rejecting the borrower's contentions were: first, that the first limb required an opinion that there were grounds to believe that a material and adverse change had occurred not that such a change had in fact occurred and the formation of the relevant opinion did not require an enquiry into whether the circumstances actually existed; secondly, it was likely that when the borrower was required to form the opinions it would be in situations where there was a need to act quickly on the basis of incomplete information; and, thirdly, the subject matter of the required opinions were not such that lent themselves to being established by objective facts - they involved nebulous concepts on which reasonable minds might differ or predictions involving speculation and calling for the exercise of judgment. Robb J also observed:
There are strong grounds for concluding that, if the plaintiffs' argument were accepted, the reality would be that the validity of the Lender's reliance upon an event of default ... would ultimately involve the court substituting its own opinion for that of the Lender, no matter how honestly and conscientiously the Lender formed its own opinion.
  1. I do not accept Westgem's submission that the better view is all commercial contracts carry with them an obligation on each party to act reasonably towards the other in exercising rights. The authorities, including Renard Constructions and Burger King, emphasise the importance of the contractual context - the express terms and the contractual purpose ‑ in analysing whether some form of reasonableness term should be implied. This militates against the implication of such a term as a matter of law.
  2. In my view, in the absence of an express term, whether a contractual power or discretion conferred on a party is subject to an obligation to act reasonably depends on whether a term to that effect can be implied as a matter of fact.[186] If the contract is a formal contract, a term will only be implied if the BP Refinery conditions are satisfied, or if a term to that effect might be deduced by implication, as a matter of construction of the express terms of the contract in accordance with the Marcus Clark line of authority.

The relevant contractual context in this case

  1. In assessing the contractual context it is important to focus on the events that the MOFA identified as Events of Default and the circumstances required to exist before an Event of Default was established. The Events of Default specified in cl 17 fall into two broad categories.
  2. The first category comprised those events the existence of which were matters that might be determined as a matter of objective fact and which did not require the formation of any kind of opinion. For example, cl 17.19 dealt with the creation of encumbrances as an Event of Default in the following terms:[187]
Any Transaction Party attempts to create a Security Interest over the Secured Property or allows one to exist or Security Interest comes into existence over the Secured Property, otherwise than in accordance with or as permitted under the Transaction Documents.
  1. The second category comprised Events of Default that required the existence of circumstances and an evaluative judgment about whether the circumstances would or would be likely to have a 'Material Adverse Effect' or whether a matter was 'material'.
  2. 'Material Adverse Effect' was defined as:[188]
... a material adverse effect on any one or more of the following:

(a) the ability of any Transaction Party to comply with its obligations under any Transaction Document;

(b) the effectiveness, priority or enforceability of this document or any of the Security Documents; or

(c) the value of the Secured Property;
  1. Clause 17.11 provided for an Event of Default in the second category, it provided:[189]
Any Native Title Claim is made that would or would be likely to have a Material Adverse Effect.
  1. Similarly cl 17.13 provided for an Event of Default if:[190]
Any event or series of events, whether related or not, occurs that has or would be likely to have a Material Adverse Effect.
  1. A different formulation, one that imported a requirement of reasonableness in the evaluative exercise, was used in cl 17.10. Clause 17.10 concerned 'Revocation of Authorisation' and provided:[191]
An Authorisation that is material to the performance by any Transaction Party of a Transaction Document, or to the validity and enforceability of a Transaction Document is repealed, revoked or terminated or expires, or is modified or amended or not renewed, or conditions are attached to it in a manner unacceptable to the Facility Agent, and is not immediately replaced by another Authorisation reasonably acceptable to the Facility Agent. (emphasis supplied)
  1. Clause 17.20, which concerned adverse decisions in litigation, adopted a similar but slightly different formulation to that used in cl 17.10, it provided:[192]
Any decision against a Borrower in any litigation, arbitration, Tax claim, dispute or administrative or other proceeding affecting the Borrower occurs where that decision (either alone or together with other decisions) is reasonably likely to have a Material Adverse Effect. (emphasis supplied)
  1. Some of the Events of Default required the existence of a factual circumstance and a judgment about the materiality of that circumstance without requiring a judgment as to whether there was a Material Adverse Effect, for example, whether a representation was not true in a material respect (cl 17.3) or whether a material part of the Secured Property was compulsorily acquired (cl 17.14(1)).
  2. Clause 18 was part of the contractual mechanism that enabled the Financiers to control the credit risk. The circumstances in which the Financiers might have wished to exercise their rights under cl 18 were varied but it may be assumed that those circumstances would have included situations in which the Financiers had limited and incomplete information and were required to make decisions to protect their own interests as a matter of some urgency (exemplified by the circumstances in which the first and second Cost Overruns occurred).

No reasonable grounds term in the MOFA

  1. The reasons why I am not persuaded that the reasonable grounds term was an ad hoc implied term of the MOFA as contended for by Westgem are as follows.
  2. First, I do not consider that the term was necessary to provide business efficacy to the MOFA. Unlike the provisions under consideration in Renard Constructions and Burger King, cl 17 and cl 18 did not confer a discretion on the Financiers to exercise their rights on the occurrence of a trivial breach. The subject matter of the Events of Default specified in cl 17 were not by nature trivial or unimportant matters. Moreover, where the formation of an opinion about the existence of a circumstance was required in order to establish an Event of Default, the opinion was qualified by a requirement that the circumstance 'is likely to have' or 'would [have] or would be likely to have a Material Adverse Effect' or, at least, a requirement that the circumstance was material. Unlike the contracts in Renard and Burger King the implication of a reasonableness term was not required to make the MOFA workable by protecting Westgem from the possibility of the Financiers terminating for trivial or immaterial breaches of the MOFA.
  3. Secondly, there was no express qualification or restriction on the Financiers' discretion to exercise the powers conferred by cl 18. The discretion to exercise those powers was conferred to enable the Financiers to protect their own interests in circumstances in which it was likely that their interests would conflict with Westgem's interests. It would be inconsistent with the absence of any express qualification in cl 18 to impose by means of an implied term a restriction on the exercise of the discretion by reference to considerations of reasonableness. In this respect I agree with the observations of Kenneth Martin J in Caratti Holdings Co Pty Ltd v Coventry Group Ltd, about the need for judicial caution when considering the implication of terms of good faith or reasonableness into commercial contracts negotiated at arm's length between well-resourced commercial parties. His Honour perceived the need for caution as arising out of a respect for the freedom of the parties to negotiate their own bargain, and out of the danger inherent in looking at one aspect of the bargain in isolation and ignoring the reality that 'commercial bargains invariably involve carefully weighed levels of interrelated 'give and take' over countless aspects of their end deal'.[193] These observations serve as a reminder that the protections conferred on the Financiers by the MOFA are part of the contractual price paid by Westgem to the Financiers for lending it the many millions of dollars on the commercial terms set out in the MOFA.
  4. Thirdly, as noted earlier, an important feature of the contractual context of the MOFA was that it was likely that the situations in which the Financiers might wish to exercise their rights under cl 18 would be situations in which they had incomplete information and were required to make decisions to protect their interests in short time frames. Added to this, a number of the Events of Default required judgments to be made about the consequences that would or would be likely to arise in the future as a result of specified circumstances. Such judgments are speculative in nature and inherently contestable - even more so when the opinions may be required to be formed as matter of some urgency on the basis of incomplete information, and in circumstances in which the Financiers were entitled to have regard to their own interests and not to subordinate their interests to those of Westgem. These are factors that militate against the implication of the reasonable grounds term contended for by Westgem. Moreover, the implication of the reasonable grounds term in the contractual context presented by the MOFA would not lead to the certainty that business people and, in particular, those involved in providing substantial project finance require from their contractual arrangements. Decisions made by the Financiers about the existence of an Event of Default would become the subject of litigation with the court being asked, in effect, to substitute its opinion of what was reasonable for that of the Financiers: cf the observations of Robb J in Minumbra Lancewood Pty Ltd v AM Lancewood cited above. Rather than bringing business efficacy to the MOFA, the reasonable grounds term contended for by Westgem had the capacity to create a state of uncertainty in the Financiers' ability to take steps to eliminate or minimise the credit risk.
  5. Fourthly, the express importation of a requirement of reasonableness into cl 17.10 and cl 17.20 (and inclusion of a reasonableness requirement in the definition of Cost to Complete) and the omission of such a requirement from the other Events of Default suggests that the parties did not intend that when the Financiers were required to make a judgment about the existence of any other Event of Default, reasonable grounds for that judgment were a contractual requirement.
  6. Fifthly, the reasonable grounds term is inconsistent with the express terms of the MOFA. The effect of the implication of the reasonable grounds term would be to create a potential basis of liability for the Financiers in the event that they were found to have exercised their rights under cl 18 without having reasonable grounds for the opinion that there was an Event of Default. The creation of such a liability is inconsistent with the exclusion of liability on the part of the Financiers contained in cl 29.3 to which I have already referred.
  7. My view that it is not necessary to imply a reasonable grounds term into the MOFA to give it business efficacy and the inconsistency between the reasonable grounds term and the express terms of the MOFA that excluded liability on the part of the Financiers also lead me to the conclusion that the term should not be implied as a matter of construction of the MOFA in accordance with the Marcus Clark line of authority.
The Cost Overrun Consultation Term
  1. Westgem contended that on a proper construction of cl 1.1(32) (the definition of Cost Overrun) and cl 1.1(33) (the definition of Cost to Complete), and of the MOFA as a whole, it was a term of the MOFA, alternatively it was an implied term, that Bankwest as Facility Agent was required to:[194]

(a) afford Westgem a reasonable opportunity to provide information in relation to whether a Cost Overrun had occurred; and

(b) reasonably consider any information provided by Westgem in connection with a claimed Cost Overrun.

  1. In Westgem's opening written outline of submissions it made no mention of the Cost Overrun Consultation Term. In its written closing submission the Cost Overrun Consultation Term was said to arise as a matter of construction in the following way:[195]
The definition of 'Cost to Complete' also imposed an express obligation on Bankwest as the Facility Agent to 'reasonably' determine the Cost to Complete based on information provided by Westgem and the Project Certifier, Ralph Beattie Bosworth Pty Ltd (RBB). The content of that obligation required Bankwest to at least consider the terms of the MOFA and whether any Cost Overrun calculation performed by RBB had been performed adequately and in accordance with the MOFA. Bankwest was also required to afford Westgem a reasonable opportunity to provide information as to the Cost to Complete and for Bankwest to reasonably consider that information (Cost Overrun Consultation Term).
  1. Westgem did not make any submissions on how the Cost Overrun Consultation Term was contended to arise as an implied term of the MOFA.
  2. The Financiers drew attention to the definition of Cost to Complete in cl 1.1(33) and to the requirement that the Facility Agent base its determination of Cost to Complete on information provided by the Project Certifier and Westgem. They contended a term introducing other notions of reasonableness was inconsistent with that express provision.[196]
  3. Self-evidently the obligation on the Facility Agent imposed by the definition of Cost to Complete was different in form and substance from the Cost Consultation Term that required the Facility Agent:

(a) to afford Westgem a reasonable opportunity to provide information in relation to whether a Cost Overrun had occurred; and

(b) to reasonably consider any information provided by Westgem in connection with a claimed Cost Overrun.

  1. I have set out earlier the principles governing the implication of terms from the proper interpretation of the express terms of the contract. It is not, however, possible to construe the language used in the definitions of Cost to Complete or Cost Overrun, as imposing obligations on the Facility Agent to afford Westgem a reasonable opportunity to provide information in relation to whether a Cost Overrun had occurred or to reasonably consider any information provided by Westgem in connection with a claimed Cost Overrun. I do not accept that the Cost Overrun Consultation Term can be implied as a matter of construction of the express terms of the MOFA or as an ad hoc term implied term.
  2. Essentially the same point defeats both bases on which the Cost Overrun Consultation Term is sought to be incorporated. It was not necessary for the effective operation of the MOFA because the existence of a Cost Overrun within the meaning of the MOFA did not depend on the Facility Agent making a determination to that effect. A Cost Overrun arose if the Cost to Complete exceeded the aggregate of the Undrawn Commitment. It was an arithmetical calculation. Moreover, the responsibility for making the calculation did not lie solely with Facility Agent, see cl 15.3(9) which required Westgem to notify the Facility Agent of 'the occurrence of a Cost Overrun within 5 Business Days of its occurrence'. As the Cost Overrun calculation was purely arithmetical there was no reason to introduce any reasonableness requirement at that stage of the process. The express requirement for the Facility Agent to make a reasonable determination of the Cost to Complete based on information provided by the Project Certifier and Westgem meant that there was no necessity for an implied consultation term at that earlier stage of the process.
No reliance on events caused by own conduct term
  1. Westgem pleaded that as a matter of law, or on a proper construction of MOFA, it was a term of the MOFA that the Financiers would not be entitled to:[197]

(a) insist upon the performance of a contractual obligation by Westgem if and to the extent that they (or any of them) had caused or materially contributed to Westgem's non-performance of that obligation; and

(b) rely upon an Event of Default if and to the extent that they (or any of them) had caused or materially contributed to the occurrence of that Event of Default.

  1. Westgem did not develop the basis upon which it contended that this was a term of the MOFA in its submissions. It did however allude to the principle that a party’s contractual entitlement arising upon a particular event will not be enlivened if the event came about through that party’s own wrongful conduct.[198]
  2. The Financiers argued that in order for the proposed term to apply it would have to be inferred that the parties to the MOFA intended to introduce a limit upon the ability of the Financiers to rely upon the existence of an Event of Default if they had caused or contributed to that event and they contended that there was no textual basis for drawing such an inference. The Financiers supplemented this submission by pointing out that Westgem had not identified any orthodox principle of law or constructional technique to justify the term.
  3. It is a rule of contractual construction that, in the absence of language to the contrary, a party cannot take advantage of its own breach of contract in order to terminate it or obtain a benefit under it.[199] The rule has been described as resting on a term implied to give business efficacy or as a more general term implied by law.[200] This principle is not unqualified. It only applies to the extent of undoing the advantage gained by the wrongdoer and not the extent of taking away a right previously possessed.[201]
  4. I do not accept that the no reliance on events caused by own conduct term should be implied into the MOFA. The term had potentially far more extensive consequences than those that might be brought about by the constructional rule that a party cannot take advantage of its own breach of contract. The term propounded covered acts or omissions that 'caused or materially contributed to' Westgem's non‑performance, or to an Event of Default. This was so even if those acts or omissions did not involve any breach of the terms of the MOFA by the Financiers or Facility Agent. They would operate in a way that had the effect of imposing additional obligations of an indeterminate nature. I do not accept that such a term reflected the presumed intention of the parties - it was not a term of the MOFA. In my view it cannot be said that such a term extends logically or analogically from the existing common law rule that a party cannot take advantage of its own breach of contract.[202]
First Cost Overrun - factual findings

The dramatis personae

  1. In appendix 2 I list the individuals who were involved in the events which are the subject of this litigation and the capacities in which they were so involved.

April 2009

  1. It is helpful to begin by recording that the original total construction budget recorded in the Approved Project Budget was $230,079,573.[203] This amount included a contingency sum of $18.2 million available to meet unbudgeted variations, overruns on provisional sum items and other unforeseen costs.[204]
  2. On 9 April 2009 Mr Nagle of Bankwest sent a letter to Mr Luke Saraceni in which he referred to the possibility that the practical completion date might extend beyond 30 June 2010 in which case the Financiers would need to consider extending the term of the MOFA and that there would be funding implications '... with the likelihood of additional equity contributions to support project financing'. Mr Nagle attached a report containing a review of the contingency budget undertaken by RBB and stated:[205]
The report highlights the current and potential contingency items. Subsequent to this report, RBB has recommended to the Financiers that the contingency allowance be utilised only for hard cost items.

On this basis, it is noted that any additional interest cost and other soft cost expenditure that may arise outside of the current funding allocations should not be funded under the existing contingency allowance. We are mindful of the prospective increase in interest costs should the practical completion date extend beyond 30 June 2010.

Can you please arrange to prepare an updated project cash flow to address the following:

(a) consultancy, project management, legal and quantity surveyor costs);

(b) Contingency usage and forecast; and

(c) Funding contingencies for delayed practical completion beyond 30 June 2010

We believe it is appropriate to consider these issues as soon as possible so that agreement may be reached on future project funding scenarios, including the existing term of the financing.
  1. On 10 April 2009 Mr Clohessy sent an email to Mr Nagle asking him to advise who had initiated the request for information contained in the 9 April 2009 letter.[206] Mr Nagle replied as follows:[207]
The request to meet and obtain updated information on the project is a result of a number of issues including normal credit risk management for a project of this size and nature. In addition Bankwest lending committee has requested to be kept updated on key project measures (e.g. pre-leasing and post completion funding scenarios).

It is important that we meet so that we can be pro-active in addressing the issues raised.

...
  1. On 23 April 2009 Mr Saraceni sent Mr Nagle a revised cash flow for the Project under cover of an email in which he explained Westgem was able to increase the amount of contingencies from $18.2 million to contingencies of $22.417 million for hard costs, plus soft cost contingencies of $2,483,833 to cover other unforeseen costs and that Westgem had found considerable savings in various fee budgets. Mr Saraceni concluded the email as follows: 'I trust you will adopt this redistribution of budgeted cost centres as shown we are still able to maintain the project within the facility limit'.[208]

May 2009

  1. By May 2009 there was a dispute between Salta and Westgem as to how much the Project was going to cost to complete. In Project Control Group Report No 10,[209] a report prepared by Salta for the Project Control Group meeting held on 29 April 2009, Salta stated that the 'current approved contract sum including provisional sums is $244,536,277' and that its 'Forecast Final Revenue' was $318,100,000 (this figure included the cost of the Integrated Fit Out works).
  2. Mr Sanders was asked to comment on the cost estimates produced by each of Salta and Westgem. On 7 May 2009 Mr Sanders sent an email to Mr Frank Saraceni and Mr Paul Simpson[210] stating that he had met with Bankwest the previous day to discuss the total project costs 'as Salta see them' and that the bank needed their response to Salta's projected costs. Mr Sanders said he would come to their offices to discuss later that day.
  3. On 4 May 2009 Mr Young sent Mr Nagle an amended cashflow.[211] The two met to discuss the amended cashflow on 5 May 2009.
  4. On 25 May 2009 Mr Young requested and Mr Nagle provided Mr Young with a schedule of drawdowns under the MOFA to date.[212] Mr Young provided Mr Nagle with an updated cashflow.[213]
  5. On 27 May 2009 Mr Nagle sent Mr Clohessy and Mr Young a cashflow prepared by Bankwest. In a covering email Mr Nagle said that the Financiers were considering adopting the cashflow, which he said was based on Westgem's key assumptions, together with the Financiers' own assumptions on major items. Mr Nagle commented on concerns held by the Financiers about the treatment in Westgem's cashflow of the 'consultants' budget' and about the level of 'soft cost contingency' that Mr Nagle described as a 'key discrepancy'.[214]
  6. On 27 May 2009 Bankwest received RBB's Drawdown Report No 14 in which it was reported that 'Salta have submitted a large number of variation claims that are currently being assessed. Although few have been approved, the total cost of $230,079,573 ex GST is likely to be exceeded. We can report more accurately on this issue in our next report'.[215]
  7. On 28 May 2009 Mr Nagle sent Mr Clohessy an email in which he stated 'RBB has indicated in this month's report that the current contingency limit (of $18.2 million) is likely to be insufficient for the project and will need to be reviewed. We will hold further discussions with RBB next week.'[216]
  8. Mr Young and Mr Nagle met again to discuss the project cashflow on 2 June 2009.[217]
  9. In the first two weeks of June 2009 Mr Sanders met with Mr Frank Saraceni and Mr Simpson to discuss the construction costs.

June 2009

Saracen's Financial Statement No 6

  1. For its internal purposes Saracen produced reports entitled Project Status Reports that summarised progress on the Project. Project Status Report 10 was dated 16 June 2009 and part of the report comprised a section entitled 'Financial Statement No 6' that summarised the estimated construction costs by reference to the 'contract sum' in the Salta Building Contract. The summary contained in Financial Statement No 6 was as follows:[218]
RAINE SQUARE DEVELOPMENT

Financial Statement No 6

Summary

Contract Sum (Excluding Fit Out) $211,879,573.00

Less Provisional Sums $ 22,477,218.00 $189,402.355.00



Adjustment of Provisions Sums (Excluding Fit out) $ 30,854,320.00

Variations $ 8,782,957.97

$229,039,632.97

_____________

Other adjustments

Risk items $9,600,000.00

Items generating

additional income $9,400,000.00

Additional Lessors

works (known to date) $381,000.00

Missed items $2,343,215.00

Other $67,500.00

Contingency $500,000.00 $22,291,715.00

______________

$251,331,347.97

______________

Financial Statement No 6

Other adjustments



Risk Items

Structure - in situ frame & floors Remeasure risk allowance $3,000,000.00

Fascade [sic] Design development risk $ -

Mechanical Services Design development risk $ 400,000.00

Electrical Services Design development risk $ 600,000.00

Siteworks & Landscaping Design risk allowance $1,000,000.00

Heritage Works Design risk allowance $1,000,000.00

Salta Fit-Out contribution risk $3,600,000.00

To Summary $9,600,000.00

Items generating additional income

Tunnel $7,000,000.00

Structure - in situ frame & floors Additional structure &

slabs to roof $ 700,000.00

Plant to roof $ 500,000.00

Pavilion structure Estimate - awaiting final

design $1,200,000.00

To Summary $9,400,000.00

Additional Lessors works (known to date)

Supermarket goods lift Budget $ 360,000.00

Supermarket greasetrap Budget $ 21,000.00

To Summary $ 381,000.00

Missed items

BMU to Level 15 As Level 22 allowance $ 500,000.00

Blinds/Pelmet detailing $1.25m included in

Finishes $ -

Lobby security gates Bankwest cost? Reduce

allowance $ 500,000.00

Landscaping - Glass trees Awaiting estimate $ 750,000.00

Additional lift finishes Approved costs $ 193,215.00

Lift Maintenance $300k - excluded $ -

Artwork Contribution Fixed allowance $ 400,000.00

To Summary $2,343,215.00

Other

Insurance claims - refundable Royal Hotel Room 143 $ 67,500.00

To Summary $ 67,500.00

Contingencies

Variations/EoTs $ 500,000.00

To Summary $ 500,000.00
  1. An understanding of the significance of the contract sum of $251.33 million in Financial Statement 6 can be gained by comparing it with the 'contract sum' of $243.9 million recorded in the Financial Statements numbered 2, 3 and 4,[219] and $247.8 million in Financial Statement No 5 dated 30 April 2009.[220]
  2. I infer from Financial Statement No 6 that as at 16 June 2009:

(a) Westgem's assessment was that the forecast construction costs required to achieve Practical Completion of the Project were $251,331,347.

(b) Westgem did not consider that any allowance should be made for a credit in Westgem's favour for liquidated damages payable by Salta. In this respect I note that Financial Statement No 6 included a contingency for a payment to Salta of $500,000 for 'variations/EoTs' as distinct from a credit in Westgem's favour for liquidated damages.

Mr Frank Saraceni's response budget

  1. On 17 June 2009 Mr Frank Saraceni sent Mr Sanders an email attaching what he described as his 'response budget' to the Salta budget, Mr Saraceni stated:[221]
Attached is our response budget to the Bank in regard of Salta budget as discussed for $38M [sic, $318 million].

I have done this in a way to best show how we are OK at present so no one should panic and we have allowed adequate contingencies from now on. We have also answered Salta EOT claims with our own LD credits which I am sure can be justified related to a June 30 finish as the Bank may be allowing for.

All up and in this format they should just place a close watching brief on the job to see how the contingencies go.

As mentioned on the sheet 100% of the variations which have been put in front of us have been assessed in this budget (ie none outstanding at present) and 75% of the provisional sums have been fully let with 25% still using our original budget values and we have allowed a further contingency to allow for both of these. The bank should not hang us at the moment for allowing contingencies and we will just say that we are allowing for them in the future by cashing up now.
  1. In the attachment to his email of 17 June 2009 Mr Frank Saraceni recorded that the 'Forecast Final' Contract Sum was $235,726,752 taking into account a credit in Westgem's favour of liquidated damages of $2,350,000 Mr Frank Saraceni considered would be recoverable from Salta.[222] If the credit for liquidated damages was not taken into account the figure was $238,076,752. In other words Mr Frank Saraceni's forecast figure involved an increase in construction costs (in effect, a Cost Overrun) of between approximately $5 million and $8 million depending on the view taken of Westgem's liquidated damages claims. As will be seen the possibility of a Cost Overrun in that range was raised in correspondence with the Financiers by Mr Clohessy.
  2. Mr Frank Saraceni's 'Forecast Final' of $235,726,752 was calculated as follows:

RAINE SQUARE DEVELOPMENT

Appraisal of Salta PCG Meeting Budget Figures



Budgeted to date
Comments
Contingency
Budget
Contract sum (excl IFQ
$ 211,879,573.00



Less Provisional Sums
-$ 22,477,218.00



Contract Sum less Provisional Sums
$ 189,402,355.00



Provisional Sums awarded and released (excl IFO)
$ 24,236,628.00
75% of Provisional Sums fully let to date

Approved variations to date
$ 3,965,380.00

100% agreed

Sub-total

$ 217,604,363.00


Variations received but not yet approved/rejected

-
Contingency
$ 5,535,098.00
Structure variations (incl above)
$ -
-


Structure remeasure
$ -

Contingency
$ 3,500,000.00
Balance of Provisional Sum Expenditure

$ 7,587,321.00
Contingency
$ 607,000.00
Value Management Savings not achieved

$ -
Contingency
$ 3,242,970.00



L&A Damages Contingency (Credit)
-$ 2,350.000.00
Forecast Final
A
$ 225,191,684.00
B
$ 10,535,068.00








A + B
$ 235,726,752.00
  1. It is difficult to make a precise comparison between the figures contained in Financial Statement No 6 and Mr Frank Saraceni's 'response budget' because the information is presented in a different format in each document and each used a different method of categorising costs, it is possible, however, to make the following observations.

(a) In Financial Statement No 6 the adjustment made for provisional sums (excluding the fit out) was $30,854,320 and the figure for variations was $8,782,957. In the Response Budget the provisional sum figure was apportioned between provisional sums awarded and let of $24,236,628 and a balance of $7,587,321 making a total of $31,823,949 (cf $30,854,320 in Financial Statement No 6) and the figure for variations was apportioned between 'approved variations to date' of $3,965,380 and 'variations received but not yet approved/rejected of $5,535,098 making a total of $9,500,478 (cf $8,782,957 in Financial Statement No 6). In summary the amounts in the Response Budget for provisional sums and variations exceed the amounts allowed for those items in Financial Statement No 6 by $1,687,150.

(b) Financial Statement No 6 includes an amount for 'remeasure risk allowance' associated with 'structure - in situ frame & floors' of $3 million that appears to be reflected in part in an amount in the response budget of a contingency of $3.5 million for 'Structure variation (incl above) Structure remeasure'. Financial Statement No 6 also includes an amount in respect of 'Salta Fit-Out contribution risk' of $3.6 million that appears to be reflected, again in part, in an allowance for 'Value Management Savings not achieved' of $3,242,970.

(c) It is possible that some of the amounts allowed in Financial Statement No 6 have been taken up in the figures in the Response Budget for provisional sums and variations and this may explain why the allowances for those amounts is $1,687,150 greater in the Response Budget than the comparable amounts in Financial Statement No 6.

(d) Given its significance in the context of the dispute between the parties an item of particular note recorded in the Financial Statement No 6 but not recorded in the Response Budget is an amount of $7 million for the tunnel. In the Response Budget the tunnel is listed as an item of 'provisional sum expenditure' with an allowance of $4.3 million.

(e) If no attempt to reconcile the figures is made and reference is made to the 'final figures' it remains the case that Financial Statement No 6 recorded construction costs that exceeded the construction costs in the Response Budget by $15,604,595 and by $15,254,595 if a credit is allowed for liquidated damages of $2,350,000.

  1. I infer from the figures contained in Financial Statement No 6 that in June 2009 Westgem knew that the projected construction costs exceeded the 'forecast final' figure of $235,726,752 contained in the Response Budget by over $15 million. I infer from the fact that the Financial Statement No 6 did not include an offsetting credit for liquidated damages and, in fact, included a contingency of $500,000 for 'Variations/Eots' that in June 2009 Westgem did not expect that they would be able to recover liquidated damages in the sum of $2,350,000 from Salta.
  2. Westgem did not disclose its assessment of the projected construction costs as recorded in the Financial Statement No 6 to the Financiers.

Mr Clohessy gives notice of requirement for additional equity

  1. On 29 June 2009 Mr Clohessy sent an email to Mr Quentin Boyes of CBA in which he stated that:[223]
We are currently working thru' the latest QS numbers with the bank and we anticipate having to inject additional funds of around $5 to $8 million for the July claim.

July 2009

Contract Sum Adjustment 17 - removal of tunnel from Salta scope

  1. On 7 July 2009 Saraceni Project Engineering, the Superintendent under the Salta Building Contract, provided Salta with Contract Sum Adjustment 17. This removed the tunnel works from Salta's contract and reduced the Salta contract sum from $250,605,040 to $246,318,957, a reduction of $4,286,084.[224]

Westgem prepares for Cost Overrun of up to $8 million

  1. On 7 July 2009 Mr Clohessy sent an email to Mr Matthew Ellis, Mr Pourzand's solicitor, which was copied to Mr Saraceni and Mr Pourzand and to Mr Stephen Josland - also a solicitor.[225] The subject line of the email was 'Raine Square additional Equity Contribution'. The email provided instructions to Mr Ellis to prepare documents recording an agreement reached between Mr Saraceni and Mr Pourzand about the contribution of additional equity to the Project. Mr Clohessy prefaced the instructions with the following statement:[226]
In summary we anticipate that Westgem will soon be required to contribute additional equity due to Cost Overruns. At this stage Luke anticipates up to $8 million however it may be more as the building progresses.
  1. Later in the email Mr Clohessy described the matter as being 'quite urgent'.

RBB's report of 16 July 2009

  1. On 16 July 2009 Mr Sanders prepared a report for the Facility Agent titled 'Cost to Complete Review'.[227] For the purposes of preparing the report Mr Sanders spoke to representatives of Westgem, reviewed the figures provided by both Salta and Saracen and reviewed the schedule of variation claims submitted by Salta. Mr Sanders did not review Salta's delay costs claims or consider the liquidated damages claim taken into account by Mr Frank Saraceni in his 'response budget'.[228] In his 16 July 2009 report Mr Sanders summarised the figures contained in the 17 June 2009 'response budget' prepared by Mr Frank Saraceni and then set out his assessment as follows:[229]
1. Original approved Construction Budget

Contract Sum $211,879,573

Allowances for variations 18,200,000

$230,079,573

2. Current Adjusted Contract Sum

To Variation Notification 15 $9,501,034

Contract Sum 211,879,573

$221,380,607

3. Saracen Engineering Forecast

Contract Sum $211,879,573

Less Provisional Sums (22,477,218)

Contract Sum less Provisional Sums $189,402,355

Provisional Sums awarded and released 24,236,628 Approved variations to date 3,965,380

Sub-Total $217,604,363

Balance of Provisional Sum Expenditure 7,587,321

Saracen Total $225,191,684

Add Contingent Allowances for:

  • Variation not yet approved $5,535,098
  • Structure remeasure $3,500,000
  • Provisional Sum expenditure $607,000
  • Value Management not achieved $3,242,970
    SARACEN TOTAL $238,076,752

4. RBB Review

Our review of the position is that Saracen's forecast as a reasonable position but to add further contingency.

Saracen Forecast $238,076,752
Further Contingency 1,923,248
Current Forecast $240,000,000
Contingency to Complete 3,000,000
RBB FORECAST $243,000,000

Total Contingency additional to Saracen 'Forecast' is $17,800,000 ($243.0m less $225.2m) of which it would be reasonable to allocate.

  • Committed contingency $8,900,000
  • Future contingency 8,900,000
    $17,800,000
Although we do not administer the project our overview of the issues providing a major effect on the budget are:
  • Overrun on Provisional Sums $10,000,000
  • Structural variations 2,000,000
  • Remeasure of structure 3,500,000
  • General variations 6,600,000
  • Ongoing contingency _$8,900,000
    $31,000,000
  1. In his witness statement Mr Sanders explained his concerns in relation to contingencies and variations. I accept his evidence - it was as follows:[230]
As set out in my report, the Saracen Cost Estimate was approximately $238 million. Given the rate that the initial contingency of $18.2 million had been utilised and the number of outstanding variations that needed to be assessed by the Superintendent I considered that a further contingency of approximately $5 million was required, making the total cost to complete $243,000,000. This is reflected in my hand written working copy of the Saracen Cost Estimate, in the bottom right-hand corner, which adds $5 million to the $238 million figure: [RBB.001.012.0006]. This additional contingency figure was based on investigations I described above, as well as other considerations, including that in my experience, based on the large portion of the contingency that had already been committed, it was highly unlikely that additional costs would be incurred, particularly given that Salta were likely to continue submitting a large number of variations.

The variations were the biggest issue, in my view. As set out in the PCG Report No 12, 174 variations (totalling $11,246,331) had been submitted by Salta and only 74 (totalling $5,916,459) have been formally approved by the Superintendent. In addition, Salta had claimed $3,581,729 in structure remeasure, but only $391,957 have been approved by the Superintendent: . . . I spoke to Frank Saraceni on numerous occasions and asked him to deal with the variations. I said words to effect that: "you should either approve the variations or reject them; either way they need to be dealt with." The effect of not approving the variations was that those figures were not "committed", as the contract sum has not formally been adjusted via a CSA. However, from my perspective, in order to determine the estimated cost of the project, it was necessary to make a provision for those variations as it was likely, based on my high level review of the schedule of variations, that at least some of the variations would be valid.

Mr Nagle gives notice of first Cost Overrun

  1. On 22 July 2009 Mr Nagle and Mr Clohessy had a telephone conversation in the course of which Mr Nagle told Mr Clohessy there had been a Cost Overrun of $13 million which Westgem was required to pay.[231] Later that day Mr Nagle sent an email to Mr Clohessy in which he referred to his earlier discussion with Mr Clohessy and to which he attached Mr Sanders' report of 16 July 2009.[232]

Discussions regarding financing of first Cost Overrun

  1. Westgem was not in a position to pay the Cost Overrun of $13 million and discussions between Mr Clohessy and Mr Leber of Bankwest took place with a view to securing a bridging finance facility of $8 million to assist in providing the $13 million required to cover the Cost Overrun. Mr Clohessy set about gathering the information required by Bankwest to enable it to determine whether to grant bridging finance.[233]

Bankwest's Cost to Complete assessment

  1. On 27 July 2009 Mr Nagle prepared a submission to the Risk Committee of Bankwest in which he set out a Cost to Complete assessment as follows:[234]
Cost to Complete Assessment ($000)
June 2009

Forecast





Breakdown of Cost to Complete




Statutory and Holding Costs

$1,134

$1,134
Construction Costs

$88,149

$88,149
Contingency Allowance

$12,445

$25,366
Fit Out Allowance

$28,772

$28,772
Admin and Consultants Costs

$2,560

$2,560
Marketing and Selling Costs

$1,512

$1,512
Finance Costs

$2,141

$2,141
Capitalised Interest

$17,806

$17,806
Cost to Complete

$154,519

$167,440





Facility Limit

$316,000

$316,000
Less Drawn to Date

$161,481

$161,481
Undrawn Commitment

$154,519

$154,519
Cost Overrun



$12,921
Total

$154,519

$167,440

  1. Westgem did not challenge the individual elements of Mr Nagle's calculation.
  2. Mr Nagle recommended to the Risk Committee that Bankwest fund $11,350,000 of the July progress claim made by Salta and proceed with due diligence for the provision of a stand alone bridging finance facility to fund the Cost Overrun.

Financing of first Cost Overrun

  1. On 31 July 2009 approval in principle was granted for Bankwest to provide a bridging loan facility of $6.5 million to Westgem.[235]
  2. On about 3 August 2009 the Financiers agreed that a payment of $1.8 million that had previously been made to Salta by Westgem should be treated as an equity contribution towards the $13 million demanded by the Facility Agent. The precise basis upon which this agreement was reached was not entirely clear on the evidence but the fact of the agreement was not in dispute.[236]

August 2009

Contract Sum Adjustments 19 and 20

  1. On 3 August 2009 the Superintendent provided Salta with Contract Sum Adjustments 19 and 20. Contract Sum Adjustment 19 had the effect of increasing the contract sum from $246,467,638.77 to $246,772,784.55, an increase of $305,145.[237] Contract Sum Adjustment 20 had the effect of increasing the contract sum from $246,772,784 to $259,081,656, an increase of $12,308,872.[238]

Westgem cash contribution to first Cost Overrun

  1. On 4 August 2009 Westgem made a cash contribution of $4.7 million that together with the $1.8 million treated as an equity contribution constituted the $6.5 million contribution to come from Westgem's own funds towards the Cost Overrun of $13 million.

RBB requests further information from Westgem

  1. On 5 August 2009 Mr Sanders sent an email to Mr Frank Saraceni and Mr Simpson in the following terms:[239]
Following discussions with the financier, we would like Saracen to prepare separate schedules of;

Variations claimed by Salta that you expect the tenant to fund. EOTs ditto.

We want to make sure things do not fall through any gaps of 'who is paying for what?'

The lending bank obviously talks to the tenant bank so they would also like to ensure everybody is on the same wavelength as to 'who is responsible for what'.

Contract Sum Adjustment 21

  1. On 7 August 2009 the Superintendent provided Salta with Contract Sum Adjustment 21 which had the effect of increasing the contract sum from $259,081,656 to $267,730,081, an increase of $8,648,425.[240]
  2. The adjustments made to the contract sum by Contract Sum Adjustments 19, 20 and 21 included adjustments in respect of variation claims made by Salta before Mr Frank Saraceni prepared his 'budget response' of 16 June 2009. The Financiers included in their closing submissions an analysis of the variation claims submitted to the Superintendent prior to 17 June 2009 that were referred to in Contract Sum Adjustments 19, 20 and 21.[241] The analysis recorded the dates on which the variation claims had first been made and the allowances that the Superintendent made in respect of them in Contract Sum Adjustments 19, 20 and 21 in addition to allowances made by the Superintendent at earlier dates. The analysis referred to contemporaneous documents maintained by the Superintendent. It is unnecessary to set out the detail contained in the source documents. The analysis was not challenged by Westgem. I accept the analysis provides a reliable summary of the facts derived from the source documents. The analysis shows that Contract Sum Adjustments 19, 20 and 21 included allowances in respect of variations for claims made prior to 17 June 2009 which were $4,288,053 more than the allowances the Superintendent had been prepared to make before issuing the Contract Sum Adjustments. I accept the analysis is reliable.
  3. In his evidence Mr Sanders stated his view that the variations that were approved by the Superintendent in Contract Sum Adjustment 20 '... had needed to be approved for a while ...'.[242] On the basis of that evidence and the analysis to which I have referred in the preceding paragraph I infer that the Superintendent had delayed approving the variations approved in Contract Sum Adjustment 20 in order to reduce the amount of any Cost Overrun. Had the Contract Sum Adjustments 19, 20 and 21 been issued prior to 22 July 2009 the first Cost Overrun would have been greater by approximately $4.288 million based on the analysis contained in the Financiers' closing submissions.[243]
  4. On 7 August 2009 Westgem was provided with Bankwest's latest project cash flow under cover of an email that recorded:[244]
... [T]here is only $1,592,731 available under Consultants which includes Architect, Project Management, Consultants, Construction Management and Accounting/Legal.

Softcost contingency is being absorbed by additional interest costs associated with the GST overdraft account and construction drawdowns being ahead of original forecasts, increasing overall interest expense.

Bankwest gives notice of Event of Default and Mr Clohessy responds

  1. On 10 August 2009 Bankwest served a letter on Westgem dated 7 August 2009. The material parts of the letter read as follows:[245]
In accordance with the terms of the Facility Agreement (including, but not limited to clauses 1.1(59), 1.1(94) and 13.2(6)), the Project Certifier, Ralph Beattie Bosworth Pty Ltd, has provided the Facility Agent with an updated report on the forecasted costings for the Project.

A copy of this report dated 16 July 2009 is attached to this letter. By its report, the Project Certifier's opinion is that the estimated Cost to Complete has increased from $230,079,573 to $243,000,000.

In accordance with the terms of the Facility Agreement, and based on the terms of the Project Certifier's report dated 16 July 2009, the Facility Agent determines that:
  1. a Cost Overrun in the amount of circa $12,921,000 has been incurred;
  2. under the terms of clause 15.2(9) of the Facility Agreement, the Borrower is required to pay for every Cost Overrun within 5 Business Days of demand by the Facility Agent; and
  3. under the terms of clause 13.2 of the Facility Agreement, the Financiers are not obliged to fund further Drawings pursuant to the Facility Agreement until such time as:
    1. there is no amount owing but unpaid in respect [of] Cost Overrun (this is set out at clause 13.2(11) of the Facility Agreement); and
    2. the Cost to Complete as reported by the Project Certifier does not exceed the Undrawn Commitment (this is set out at clause 13.2(6)(d) of the Facility Agreement).
The Facility Agent made a verbal demand of the Borrower on 22 July 2009 for the payment of the Cost Overrun.

We understand from further discussions that the Borrower has agreed to pay a portion of the Cost Overrun; however it is unable to pay the full amount of the Cost Overrun.

Given that 5 Business Days has passed since the date of demand by the Facility Agent, the Borrower's failure to pay the Cost Overrun in full is:
  1. a breach of the Project undertaking detailed in clause 15.2(9) of the Facility Agreement; and
  2. an Event of Default pursuant to clause 17.22 of the Facility Agreement.
  3. Following receipt of the Facility Agent's letter of 10 August 2009 Mr Clohessy responded to the letter on Westgem's behalf by email to Mr Nagle sent on 10 August 2009 in which Mr Clohessy stated:[246]
Thank you for copy of the advice. I would respectively advise that no formal notice of cost over run was made to the borrower pursuant to clause 40.1 of the MOFA and accordingly the borrower is not in breach. Our interpretation of the events was that a Cost Overrun was identified and the borrower in conjunction with its Banker have now facilitated the required injection of equity.
  1. In fact, contrary to the assertion made by Mr Clohessy in his email to Mr Nagle of 10 April 2009 the balance of $6.5 million required to comply with the Facility Agent's demand for the contribution of equity by Westgem was not paid until about 1 September 2009,[247] following agreement being reached on the terms of the bridging finance facility on 28 August 2009.[248]

Salta capacity to pay notice

  1. On 12 August 2009 Salta sent a letter to Westgem giving notice under GC 42.1 of the Salta Building Contract to the effect that Salta estimated that the likely final costs of the Project was $321,689,771 and requiring Westgem to provide it with documentary evidence, verified by the parties to the MOFA that it had the capacity to meet its payment obligations under the Salta Building Contract.[249]

Contract Sum Adjustment 20

  1. On 14 August 2009 Westgem provided Bankwest with Contract Sum Adjustment 20, which, as noted earlier, increased the contract sum by $12.3 million.[250]
  2. On 14 August 2009 Mr Frank Saraceni sent Mr Nagle an email explaining why the tunnel had been removed from Salta's scope of works. The background to how this came about is that on 4 August 2009 Mr Simpson had sent Mr Nagle 'Variation Notification 16' seeking the Security Trustee's approval of a 'Permitted Variation' under the terms of the Builder's Side Deed. Variation Notification 16 recorded the deletion of the tunnel by Contract Sum Adjustment 17 and made an allowance by way of deduction in that respect of $4,286,084 and an allowance by way of an addition in respect of Contract Sum Adjustment 18 in the sum of $148,681 and a further allowance by way of addition in the sum of $4,300,000 expressed as follows, 'Add back Tunnel P. Sum' so that the net effect of the variation notification was an increase in construction costs of $162,597.[251] I infer that Mr Nagle sought an explanation about the removal of the tunnel from Salta's scope of work. The explanation provided by Mr Frank Saraceni was as follows:[252]
I confirm that the provisional sum for the tunnel has been removed from Saltas contract because we refuse to have Salta do this work for us and cause more delusional grief for us.

The tunnel is currently out to tender to Arccon and Gallaghers and we are discussing it with Probuild as well who are our favoured contractors for this work as they are already on the site across the road.
  1. The adding-back of $4,300,000 as a provisional sum to be taken into account as a construction cost was reflected in the project cash flows prepared by Westgem and submitted to the Financiers, they were not reduced, however, by any allowance made in respect of the deletion of the tunnel.

Bankwest seeks further cost information from Westgem

  1. On 17 August 2009 Mr Nagle sent an email to Mr Clohessy in which he compared the adjustments to various provisional sum items recorded in Contract Sum Adjustment 20 with figures provided by RBB in its 16 July 2009 report and with the figures contained in Mr Frank Saraceni's 'response budget'. Mr Nagle stated:[253]
You will note that we have only just recently reported a Cost Overrun position to the Financiers, and while this included a provision for further contingencies, we hold real concerns that current reporting indicates further increases in costs.
  1. Mr Nagle identified four provisional sum items in respect of which Contract Sum Adjustment 20 increased the allowances by $4,975,260. Mr Nagle asked Mr Clohessy to provide background in relation to those items and to 're-confirm the estimated total level of Provisional Sums for the Project'. Mr Clohessy forwarded Mr Nagle's email to Mr Luke Saraceni and Mr Frank Saraceni. Mr Frank Saraceni forwarded the email to Mr Simpson with a request to telephone him to discuss Mr Nagle's email.

Financial statement No 7

  1. On 18 August 2009 Mr Simpson sent 'Financial Statement No 7' to Mr Frank Saraceni and Mr Rob Merson.[254] In this statement the final contract sum was recorded as $263,748,232, calculated as follows:[255]
Financial Statement No 7

Summary

Contract Sum (Excluding Fit Out) $211,879,573.00

Less Provisional Sums $ 22,477,218.00 $189,402,355.00



Adjustment of Provisions Sums (excluding Fit Out) $ 35,979,295.00



Variations $ 18,079,867.00

$243,461,517.00

_____________

Other adjustments

Risk items $8,600,000.00

Items generating

additional income $9,400,000.00

Additional Lessors

works (known to date) $ 326,000.00

Missed items $1,893,215.00

Other $67,500.00

Contingency $0.00 $20,286,715.00

______________

$263,748,232.00

______________
  1. Financial Statement No 7 contained a breakdown of the 'Other adjustments' figure that was as follows:[256]

Other adjustments



Risk Items

Structure - in situ frame

& floors Remeasure risk allowance $3,000,000.00

Facade Design development risk $

Mechanical Services See variations $

Electrical Services See variations $

Siteworks & Landscaping Design risk allowance $1,000,000.00

Heritage Works Design risk allowance $1,000,000.00

Salta Fit-Out contribution risk $3,600,000.00

To Summary $8,600.000.00

Items generating additional income

Tunnel $7,000,000.00

Structure - in situ frame Additional structure &

& floors slabs to roof $ 700,000.00

Plant to roof $ 500,000.00

Pavilion structure Estimate - awaiting final

design $1,200,000.00

To Summary $9,400,000.00

Additional Lessors works (known to date)

Supermarket goods lift Priced $ 305,000.00

Supermarket greasetrap Budget $ 21,000.00

To Summary $ 326,000.00

Missed items

BMU to Level 15 As Level 22 allowance $ 500,000.00

Blinds/Pelmet detailing In variation $

Lobby security gates Bankwest cost? Reduce

allowance $ 500,000.00

Landscaping - Glass trees Glass only - steel

elsewhere $ 300,000.00

Additional lift finishes Approved costs $ 193,215.00

Lift Maintenance $300k - excluded $

Artwork Contribution Fixed allowance $ 400,000.00

To Summary $1,893,215.00

Other

Insurance claims - refundable Royal Hotel Room 143 $ 67,500.00

To Summary $ 67,500.00

Contingencies

Variations/EoTs $___________

To Summary $___________

  1. On 19 August 2009 Mr Simpson sent an email to Mr Frank Saraceni commenting on the figures contained in Financial Statement No 7 and upon Mr Nagle's analysis of the increases in provisional sum allowances recorded in Contract Sum Adjustments 19, 20 and 21.[257] The email provides a telling insight Westgem's assessment of the costs of the Project and of its relationship with the Financiers. For those reasons I reproduce it in full below:[258]
Frank

It was always likely, but more so with the current chaos being created by Salta, that Steve Nagle would scrutinise the figures and latch onto increased amounts.

With Salta's actions it has made it virtually impossible for us to present anything other than a set of revised 'right' numbers and then prove we can manage them effectively for the rest of the contract. We need to have the Bank's support if we are going to discredit Salta's assertions.

I believe the figures I sent you yesterday, whilst unpalatable, represent a realistic cost to complete, albeit they exclude any allowance for EOT costs or LAD's which may be recoverable. I do not have a copy of Financial Report No 6 with me but am confident that if you and Rob compare it to the report I did yesterday, it is easy to pinpoint where our problems lie.

In response to Steve's comments, we should point out the following:
  1. CSA's are being used as a tool to manage the contractor. The larger ones issued recently were done so only to appease Salta and assist them with their internal accounting systems. A fair proportion of the monies contained in recently issued adjustments will not be expended until well into next year.
  2. The forecast figures he has highlighted are authorised amounts to date taken from an extremely positive 'snapshot' - they are not forecast to complete figures. He should not be comparing these figures but probably does not have any others to use! Of the items he has highlighted, only the Floor, Wall & Ceiling Finishes have significantly blown out in the past few months for, but not limited to, the following reasons:
    1. Inflexible high quality specification and very low over-optimistic rates in our original budget
    2. Errors in our original budget both in quantities and excluded items
    1. Complete lack of assistance and co-operation from Salta to Value Manage the package - verging on obstruction
    1. Errors in contractors tendering process - quantities and exclusions
We should not be giving the Bank any more figures at the moment that will be used in a few weeks to hang us. We need to convince them that things need to settle down and they should be assisting us to stabilise things with Salta which I believe they will do as long as we convince them that we know and have always known where the job is heading financially.
  1. I infer that the reference to the 'extremely positive snapshot' to which Mr Simpson refers in the second numbered paragraph of his email is a reference to Mr Frank Saraceni's 'response budget' sent to RBB on 17 June 2009. I think it unlikely that Mr Simpson would have referred to RBB's report of 16 July 2009 in such terms and the figures in the 'response budget' were more 'positive' from Westgem's perspective than the figures contained in RBB's report.

September 2009

Bankwest repeats request for information

  1. On 2 September 2009 Mr Nagle sent an email to Mr Clohessy by which he resent to Mr Clohessy his email of 17 August 2009 and stated:[259]
I have requested that Trevor Sanders review the position outlined in our earlier email.

It is proposed that we get together next week (with Frank) to go through the details. The position must be resolved quickly in time for the payment claim later this month.
First Cost Overrun contractual claims Breaches pleaded
  1. Westgem pleaded:

(a) The Facility Agent did not serve a notice or demand in respect of the first Cost Overrun in writing as was required by cl 40.1 of the MOFA.[260]

(b) Prior to asserting the existence of the first Cost Overrun and prior to issuing a default notice in respect of the first Cost Overrun Bankwest did not:[261]

(i) make any inquiries of Westgem so as to afford Westgem a reasonable opportunity to provide information in relation to whether a Cost Overrun had occurred;

(ii) give any, or any reasonable consideration, to the terms of the MOFA as to how a Cost Overrun was to be determined, or the notice requirements for making a demand for payment of a Cost Overrun;

(iii) give any, or any reasonable, consideration to whether the RBB calculation of the Cost to Complete had been performed adequately or in accordance with the MOFA.

(c) There was in fact no Cost Overrun either on 22 July 2009 when the demand was made or on 7 August 2009 when the notice of default was served. Specifically, Westgem alleged:[262]

(i) There was no Cost Overrun because the identification of an amount by which the Cost to Complete exceeded the aggregate of the Undrawn Commitment had not occurred in accordance with the construction of the Cost to Complete provision for which Westgem contended.[263]

(ii) Although RBB had advised Bankwest as Facility Agent that the original total approved construction budget for the Project was $230,079,573 and that RBB's forecast of the total cost of construction of the Project was $243,000,000 resulting in a difference of $12,920,427 this did not constituted a certification of the amount determined by RBB as the likely cost to Westgem under the Building Contract from that time to achieve Practical Completion under the Building Contract as required by cl 1.33(a) of the MOFA.[264]

(iii) At or about 22 July 2009 the Undrawn Commitment was $154,643,469 and the Cost to Complete did not exceed that figure. Westgem pleaded that the Cost to Complete would be established by expert evidence but no such evidence was adduced.[265]

(iv) The demand for payment of the first Cost Overrun on 22 July 2009 was not a valid demand for payment.[266]

(d) As at 22 July and 7 August 2009 Bankwest as Facility Agent had not reasonably determined that the first Cost Overrun had occurred because:[267]

(i) the first Cost Overrun had not occurred;[268]

(ii) Bankwest had construed the Cost to Complete provision incorrectly in that it had:[269]

(A) failed to apply correctly the contractual definitions of Cost Overrun and Cost to Complete; and

(B) it had failed to give reasonable consideration to the meaning of Cost Overrun under the MOFA as a person acting conscionably would have given.

(iii) Bankwest did not consider the matters referred to at par (c)(ii) above.[270]

(iv) Bankwest conducted itself as alleged in (b) above.[271]

  1. For the purposes of its breach pleas Westgem rolled up the impugned conduct and pleaded it involved:[272]

(a) Bankwest breaching the Code Conduct Term because it failed to act fairly and reasonably and in an ethical manner or failed to have any proper regard to the terms of the MOFA;

(b) the Financiers breaching:

(i) the Cost Overrun Term;

(ii) No reliance on events caused or contributed to by Financiers term;

(iii) the Cost Overrun Consultation Term;

(iv) the Event of Default term and the reasonable grounds term.

(c) The Financiers engaging in unconscionable conduct in contravention of s 12CC of the ASIC Act.

  1. Westgem alleged that by asserting the Cost Overrun on 22 July 2009 the Financiers engaged in conduct that was misleading or deceptive or was likely to mislead or deceive contrary to s 12DA of the ASIC Act or s 10 of the FTA.
Claims as developed in submissions
  1. Some elements of Westgem's case as advanced in closing written submissions overlapped with its pleaded case but other elements were not pleaded. The core propositions relied on by Westgem in closing were as follows:

(a) To be valid, a Cost Overrun must be determined in accordance with the terms of the MOFA and Mr Nagle's determination was not in accordance with the MOFA for the following reasons:

(i) Mr Nagle did not calculate the amount required to be expended to achieve Practical Completion under the Salta Building Contract rather he relied upon Mr Sanders forecast of the total construction costs of the Project, including the tunnel which had been removed from Salta's scope of works on 8 July 2009.[273]

(ii) In calculating the Cost to Complete Mr Nagle included the contingency of $5 million allowed by Mr Sanders in the RBB report of 16 July 2009 and this did not form part of the Cost to Complete because it was not a 'likely cost' but an amount set aside for unforeseen future events.[274]

(iii) In determining the first Cost Overrun Mr Nagle calculated the increase in total construction costs against the initial construction budget of $230,079,573 rather than by reference to the contractual concept of the Undrawn Commitment for the Facility which was not a fixed amount but one that varied.[275]

(iv) If as the Financiers contended the Cost to Complete was to be determined by reference to the cost of completing the work under the Building Contract at the time of the MOFA was executed, then Mr Nagle's determination did not accord with this construction because Mr Sanders included in his figures the cost of variations (up to Variation No 15), that is, he did not confine himself to the cost of performing the works under the Building Contract at the time of the execution of the MOFA.[276]

(v) Bankwest's determination was not reasonable because:[277]

(A) Mr Nagle did not read the provisions of the MOFA but simply adopted the conclusions set out in Mr Sanders' report.

(B) Mr Nagle determined the first Cost Overrun before he understood Mr Sanders' report.

(C) Mr Nagle made the determination on the basis of a report from Mr Sanders whom he knew had never read the MOFA or had it explained to him.

Breaches involving the construction and application of MOFA terms

The Cost to Complete provision

  1. The central proposition on which Westgem's claim in respect of the first Cost Overrun depended was that for the purposes of determining the construction costs element of the Cost to Complete the Facility Agent was obliged to take into account the cost of the works which at the date of the determination were required to be completed to achieve practical completion under the Salta Building Contract. As I have explained earlier I do not accept that proposition. In making a determination of the Cost to Complete the Facility Agent was required to take into account the cost of the construction works necessary to complete the Project and not merely the cost of achieving practical completion under the Salta Building Contract. It follows that Westgem's claim that Bankwest breached the MOFA by applying an incorrect construction of the Cost to Complete provision fails.
  2. I have found that the tunnel formed part of the Project. Removing the tunnel from Salta's scope of works by Contract Sum Adjustment 17 did not reduce the Cost to Complete. Accordingly Mr Nagle did not make an error in the application of the terms of the MOFA by relying on Mr Sanders' forecast of the total construction costs of the Project which included the cost of the tunnel.

The allowance for contingencies

  1. Westgem contended that by including the contingency of approximately $5 million ($1,923,248 and $3,000,000 allowed by Mr Sanders in the RBB report of 16 July 2009) in his calculation of Cost to Complete, Mr Nagle did not apply the provisions of the MOFA because the contingency was not a 'likely cost' that formed part of the Cost to Complete but an amount set aside for unforeseen future events.
  2. As the Financiers emphasised in their submissions this alleged error on the part of Mr Nagle was not pleaded, it was not identified as an error in Westgem's written or oral opening submissions and Mr Sanders was not cross-examined about the reasons why he made the allowance. For those reasons the Financiers argued Westgem's contention should be dismissed.
  3. In addition to those procedural reasons, the Financiers submitted that there were substantive reasons why Westgem's contention should not be upheld.
  4. First, the Financiers relied upon Mr Sanders' evidence about the additional contingency of approximately $5 million. I have set out this evidence above.[278]
  5. Second, the Financiers submitted that the Approved Project Budget included the specific line item allocation of funds for 'Contingency' of $18.2 million against which Westgem was entitled to draw, and had drawn against under the MOFA which confirmed that an allowance for contingencies was an allowance for the likely costs of construction.
  6. Third, a contingency is by its very nature a prediction about likely future costs.
  7. On the basis of Mr Sanders' evidence I have no hesitation in concluding that the approximate $5 million allowance for contingencies was made by him in respect of costs that he reasonably considered were likely costs that would be incurred by Westgem to achieve Practical Completion of the Project and thus it was correct for these costs to be taken into account for the purposes of the Cost to Complete determination.
  8. Further, it was appropriate for Mr Sanders to describe the allowance as an allowance for contingencies, rather than to attempt a more precise attribution of the amount to particular categories of work for two reasons: first, because this reflected the approach that had been adopted by the parties in the Approved Project Budget, and secondly, because of the number of outstanding variations that needed to be assessed by the Superintendent and the fact that Salta was likely to continue to submit a large number of variations. These factors made a more precise attribution impossible. A further reason why the term 'contingencies' was apt was because the costs were not certain but likely.

Reference to the Undrawn Commitment

  1. Westgem contended that in determining the first Cost Overrun Mr Nagle calculated the increase in total construction costs against the initial construction budget of $230,079,573 rather than by reference to the contractual concept of the Undrawn Commitment for the Facility which was not a fixed amount but one that varied. This contention was based on two items of evidence:

(1) Mr Sanders' evidence that he assessed there was a Cost Overrun on the basis that the projected expenditure on the Project would exceed the construction budget of $230,079.573.[279]

(2) In Bankwest's letter to Westgem of 7 August 2009 (sent on 10 August 2009) reference was made to RBB's report dated 16 July 2009 and to the opinion recorded in it that the estimated Cost to Complete had increased from $230,079,573 to $243,000,000 as the basis for determining that there had been a Cost Overrun.

  1. It is significant, however, that when Mr Nagle reported to the Risk Committee of Bankwest by means of the credit briefing paper dated 27 July 2009 he recorded the Cost to Complete as $167,440,000 and the Undrawn Commitment as $154,519,000 from which he calculated a Cost Overrun of $12,291,000.[280] The credit briefing paper is a contemporaneous business record that evidences Mr Nagle applied each element of the contractual definitions of Cost to Complete and Cost Overrun in concluding that there had been a Cost Overrun in the amount claimed and I make a finding to that effect.
  2. Further, as the Financiers submitted, there was no suggestion by Westgem that there had been any reduction in the likely costs of construction. In the absence of evidence of a reduction in costs (and, of course, no increase in the Facility) an increase in the costs of construction would inevitably lead to a Cost Overrun equal to the increased costs of construction. So, whilst the calculation of the Cost Overrun included in Bankwest's letter of 7 August 2009 did not refer to the Cost to Complete or the Undrawn Commitment it was a method of calculation that, in the circumstances that existed, was capable of producing the same result as one which referred to the Cost to Complete and Undrawn Commitment.
  3. There is a further point to be made. The Facility Agent's role was limited to making a determination of the Cost to Complete and the only controversial aspect of that determination was the 'likely cost ... under the Building Contracts' integer in cl 1(33)(a). As emphasised earlier in these reasons, a Cost Overrun for the purposes of the MOFA was an amount derived by simple arithmetical calculation - the difference between the Cost to Complete and the aggregate of the Undrawn Commitment. The existence of a Cost Overrun did not depend on the Facility Agent having made a determination to the effect that a Cost Overrun existed. A Cost Overrun either existed as a matter of arithmetical calculation or it did not. If a Cost Overrun existed the fact that the Facility Agent demonstrated its existence by a calculation that did not adopt the integers of the calculation set out in MOFA but used a method of calculation that was equally valid, and reflected the underlying logic of the MOFA, was immaterial.
  4. Other than to attack Mr Nagle's calculation on the ground that he had not referred to and identified the Undrawn Commitment, Westgem did not challenge the primary figures in Mr Nagle's calculation of the Cost Overrun contained in his credit briefing paper of 27 July 2009. I infer that the reason for this, and indeed the reason why Westgem did not attempt to establish by expert evidence the amount by which it contended the Undrawn Commitment exceeded the Cost to Complete as it pleaded it would,[281] was that it was unable to do so. This is not surprising given the internal estimates of the construction costs prepared by Westgem - in particular Financial Statement No 7. On the basis of Mr Sanders' report of 16 July 2009 and Westgem's own figures I am satisfied that in July 2009 the Cost to Complete was not less than $243 million, that is, that the likely cost to Westgem under the Building Contract (as I have construed that term) of achieving Practical Completion (as I have construed that term) would be at least $243 million.

Mr Nagle's understanding of the RBB report

  1. The allegation that Mr Nagle concluded that there had been a Cost Overrun before he understood the RBB report of 16 July 2009 was not pleaded. The allegation rests upon an interpretation of the contents of an email exchange between Mr Nagle and Mr Sanders on 23 July 2009.[282] In that email exchange Mr Nagle sought a time to meet Mr Sanders. He wrote, 'The only real issue I would like to confirm is the classification of the current/proposed contingencies'. Mr Nagle then set out in tabular form the figures for current contingencies. The figures appear to be derived from RBB's drawdown report of 25 June 2009 as they replicate the figures and cost categories (with one minor wording change) that appear on page 10 of the drawdown report.[283] Mr Nagle made no reference in the email exchange of 23 July 2009 to the RBB report of 16 July 2009 and the figures set out in Mr Nagle's email do not correspond to any figures contained in the RBB report of 16 July 2009. These contemporaneous documents do not provide support for an inference that Mr Nagle did not understand RBB's report of 16 July 2009. All that can be drawn from these documents is that on 23 July 2009 Mr Nagle wanted confirmation or clarification of the figures that were contained in the 25 June 2009 drawdown report. In his evidence Mr Sanders referred to the email exchange of 23 July 2009 but did not say whether he had in fact met with Mr Nagle.[284] Mr Sanders was not cross-examined as to whether there was a meeting or whether Mr Nagle manifested any lack of understanding of the RBB report of 16 July 2009.

Certification by RBB

  1. One of the grounds on which Westgem alleged that the first Cost Overrun had not occurred was that the RBB report of 16 July 2009 was not 'a certification as required by cl 1.1(33) of the MOFA ...'. This issue was not addressed in the plaintiffs' opening or closing submissions.
  2. It was a term of the MOFA that a Project Certifier would be appointed and would provide a report addressing the Financiers' pre-settlement requirements. The MOFA also provided that the Project Certifier would:[285]
... verify and monitor expenditure and report to the Financiers monthly on progress of the Project including quality control compliance.
  1. There was no provision in the MOFA that prescribed the manner in which the Project Certifier was to certify the likely cost to Westgem under the Building Contracts ... of achieving Practical Completion for the purposes of cl 1(33)(a). The absence of a prescribed certification requirement is to be contrasted with requirement imposed on Westgem in relation to certification. As set out in cl 13.2(6) Westgem was required to provide the Facility Agent with a certified copy of a report of the Project Certifier confirming certain matters and cl 13.2(7) Westgem was required to provide the Facility Agent with 'a certificate in form and substance satisfactory to the Facility Agent signed by the sole director of [Westgem] ...'. Clause 13.3 of the MOFA provided:
Anything required to be certified under this clause 13 or Schedule 5 must be certified by the sole director of [Westgem] as being true and complete as at the date of Financial Close (or if earlier at a date acceptable to the Facility Agent) and again upon the provision of each Drawdown Notice.
  1. The dictionary definitions of 'certified' include: 1. Having, or proved by, a certificate. 2. Guaranteed, reliably endorsed;[286] and make formal statement of, declare by certificate, inform with certainty.[287]
  2. In the absence of a definition, the phrase 'as certified by the Project Certifier' is to be given a business like interpretation. In my judgment the phrase 'as certified by the Project Certifier' requires a document prepared by RBB, signed by a person with authority within RBB that contained a formal statement of RBB's opinion of the likely cost to Westgem under the Building Contracts of achieving Practical Completion. It was not necessary for the document to be labelled 'certificate' or for the words 'I certify' to form part of the statement.
  3. The RBB report of 16 July 2009 was a formal record of RBB's opinion. As the Financiers pointed out in their submissions the report was on RBB letterhead, the subject heading was 'Cost to Complete review', it was addressed to Bankwest as Facility Agent and it was signed by Mr Sanders, a director of RBB. In my view it was a document in which RBB certified - that is reliably and formally stated ‑ its opinion about the construction costs. I consider the RBB report of 16 July 2009 complied with the requirements of cl 1(33) of the MOFA.

The relevance of legal advice

  1. The plaintiffs allege that the Facility Agent did not obtain legal advice as to whether the Cost Overrun existed or whether it had been determined in accordance with the terms of the MOFA. Westgem did not point to any evidence in their submissions that could be relied upon to support the allegation. The allegation is not supported by the evidence and is not established. In any event even if it had been established that the Facility Agent did not obtain legal advice as to whether a Cost Overrun existed or had been determined in accordance with the MOFA this would not have constituted a breach of the terms of the MOFA.

Alleged breaches involving the failure to consult and take information into account

  1. In response to Westgem's allegations about a failure to consult, an overarching observation may be made, if at the time Bankwest gave notice of the Cost Overrun, Westgem had considered that it had been deprived of the opportunity to provide relevant information, and if it had information that tended to show that the asserted Cost Overrun had not occurred, one would have expected Mr Saraceni or Mr Clohessy to have made a complaint to that effect, but none was made. In his email to Mr Nagle of 10 August 2009 Mr Clohessy complained that Bankwest had served notice of an event of default but he did not dispute that a Cost Overrun as set out in the notice had occurred and he did not complain that Bankwest had failed to consult with Westgem or that it had failed to take into account any information Westgem or its agents had provided.
  2. Had I held that the MOFA included a term to the effect of the Cost Overrun Consultation Term, any claim based on such a term would be undermined by two further matters. First, Westgem did not identify any information that might have led to the conclusion that a Cost Overrun had not occurred. Secondly, Westgem adduced no evidence that Bankwest did not make any inquiries of Westgem so as to afford it a reasonable opportunity to provide information in relation to whether a Cost Overrun had occurred.
  3. The first matter - Westgem's failure to adduce evidence of what information it might have provided to Bankwest had it not (as it contended) been deprived of the opportunity to do so - is explicable by the fact that Westgem knew that a Cost Overrun of at least $13 million was likely. This knowledge is to be inferred from Westgem's internal calculations as those calculations are explained in its internal communications. In August 2009 Mr Simpson calculated that the final contract price was $263,748,232 and recorded this in Financial Statement No 7. On 19 August 2009 Mr Simpson wrote to Mr Frank Saraceni and stated his view that his estimated costs whilst unpalatable were realistic. While Financial Statement No 7 and Mr Simpson's email were prepared a month after the RBB report of 16 July 2009, there is nothing to suggest that the increase in costs was not known by Westgem a month earlier. I infer from the tenor and content of Mr Simpson's email that the increase in costs was not in any sense a surprise to him.
  4. Accordingly, even it is assumed in Westgem's favour that the Cost Overrun Consultation Term was included in the MOFA and further assumed that no reasonable opportunity was afforded to Westgem to provide information in relation to the Cost Overrun to the Facility Agent, on the facts as I have found them, there was no information available to Westgem that would have enabled it to establish that a Cost Overrun had not occurred.
  5. As to the second matter - my factual findings record there were a series of communications between Westgem's representatives and RBB and Bankwest concerning the construction costs between the beginning of March and 22 July 2009. These included the provision of Westgem's estimate of costs of achieving Practical Completion provided on 22 June 2009. The subject matter of the communications was the cost of construction and, in particular, the expectation that the original construction budget would be exceeded. The communications constituted an opportunity for Westgem to provide information to the Facility Agent about the Cost to Complete and the possibility of a Cost Overrun and information was provided. Further, in the context of these communications it must be remembered that Westgem was under a positive obligation to notify the Facility Agent of the occurrence of a Cost Overrun within five Business Days of the occurrence and to notify the Facility Agent of any event or series of events which were likely to cause a Cost Overrun. Thus, not only did Westgem have the opportunity to communicate information about the Cost to Complete and potential Cost Overrun but it was obliged to do so.

Breaches involving the absence of a written notice of demand

  1. Clause 40.1 provided that all notices must be in writing and signed by an Authorised Officer of the sender. Bankwest did not send a written notice in respect of the Cost Overrun until its letter of 7 August 2009 sent on 10 August 2009.
  2. One aspect of Westgem's claim based on the failure to make a written demand was that the Cost Overrun alleged by the Facility Agent had not occurred because, among other reasons, the oral demand made on 22 July 2009 was not a valid demand for payment under the MOFA.[288]
  3. As stated earlier, the existence of a Cost Overrun did not depend on the Facility Agent making a determination to the effect that a Cost Overrun had occurred. Likewise the existence of a Cost Overrun did not depend upon a written demand being made by the Facility Agent. This is made plain by the obligation imposed on Westgem to notify the Facility Agent within five Business Days of the occurrence of a Cost Overrun (cl 15.3(9)).
  4. The occurrence of a Cost Overrun was not itself an Event of Default. The Event of Default specified in cl 17.22 was the occurrence of a Cost Overrun and failure by Westgem to pay the Cost Overrun within five Business Days of demand by Bankwest (in essence a failure to comply with cl 15.2(9) of the MOFA).
  5. The Financiers submitted that there were four answers to Westgem's claim based on the absence of a written demand for payment of the Cost Overrun, which was the subject of Mr Nagle's conversation with Mr Clohessy on 22 July 2009, and they were as follows:

(a) in the particular circumstances, the fact that a demand was made orally rather than in writing attracts the de minimis rule - the circumstances relied on by the Financiers were: Westgem knew that a Cost Overrun had been determined, it accepted that there was a Cost Overrun and made arrangements to pay the Cost Overrun, no relevant enforcement steps or other action was ever taken by the Finance Parties based on the assumed existence of a formal demand or resultant Event of Default and Westgem does not allege any loss caused by the absence of a written demand;

(b) the right to receive a demand in writing was waived by Westgem which set about paying the Cost Overrun and did not insist on a written demand before making payment;

(c) the substance of the letter from the Facility Agent to Westgem sent on 10 August 2009 constituted a written demand; and

(d) the oral demand and the letter of 7 August 2009 constituted the exercise or attempted exercise of the rights of the Finance Parties and thus attracted the application of cl 29.3 of the MOFA with the result that no liability attached to the Finance Parties.

  1. As stated above not every Cost Overrun constituted an Event of Default for the purposes of the MOFA. The terms of the MOFA reflect a distinction between an unpaid Cost Overrun and a Cost Overrun that Westgem failed to pay within five Business Days of demand by the Facility Agent. The absence of the former - an unpaid Cost Overrun -was a condition precedent to any Drawing (after the first Drawing) but it did not attract the serious potential consequences that flowed from an Event of Default constituted by a Cost Overrun remaining unpaid within five Business Days of (written) demand by the Facility Agent.
  2. Westgem's focus on obtaining the funds required to meet the Cost Overrun identified by Bankwest was explicable by its concern to be able to make further Drawings under the MOFA. It was not a circumstance that relieved Bankwest of the necessity to make a written demand for payment of the Cost Overrun if it wished to take advantage of the powers available to it on the occurrence of an Event of Default. I am not persuaded that the failure to serve a written notice demanding payment of the Cost Overrun was a matter that attracted the operation of the de minimis rule. The de minimis concept has been described as a very narrow one - applying only to 'microscopic deviations which business men and therefore lawyers will ignore'[289] and trivialities, matters of little moment or of a trifling or negligible nature.[290] The existence of an Event of Default under the MOFA was a matter of substantial significance given the powers available to the Financiers on the occurrence of an Event of Default. In my view if the Financiers wished to avail themselves of those powers in respect of a Cost Overrun it was incumbent on the Facility Agent to serve a written notice demanding payment.
  3. The steps taken by Westgem to pay the Cost Overrun did not involve any voluntary or intentional relinquishment of its rights nor the adoption of inconsistent positions in a manner that would justify the conclusion that there had been any waiver on its part[291] - its conduct was explicable by a desire to satisfy the conditions precedent to further Drawings under the MOFA.
  4. In its letter of 7 August 2009 Bankwest recorded that a 'verbal demand' had been made of Westgem for payment of the Cost Overrun on 22 July 2009 and that Westgem had agreed to pay a portion of the Cost Overrun but it was unable to pay the full amount and Bankwest asserted that the failure to pay the Cost Overrun in full was an Event of Default. I accept the Financiers' submission that the letter was in substance a written demand for payment of the Cost Overrun.
  5. I have relied upon the existence of cl 29.3 as a basis for holding that the Event of Default term and the reasonable grounds term were not terms of the MOFA but, independently of that reasoning, cl 29.3 provides a basis for holding that no liability attaches to the Finance Parties by reason of any failure to make a written demand for payment of the Cost Overrun.
  6. I add that even if declaring that the first Cost Overrun was an Event of Default without first having made a written demand for payment constituted an actionable breach of the MOFA it would be a breach that had no consequences in terms of causation. The existence of the unpaid Cost Overrun was sufficient to justify a refusal by the Financiers to permit further Drawings until it had been paid.

Breaches caused by or involving a material contribution by the Financiers

  1. Westgem did not identify any non-performance of an obligation on its part to which the Financiers had caused or materially contributed nor did it identify the way in which it might be alleged that the Financiers caused or materially contributed to the first Cost Overrun. Having regard to the facts, as I have found them, it is difficult to understand how the Financiers could have caused or materially contributed to the first Cost Overrun. I find that the Financiers did not cause or contribute to any non-performance by Westgem or to the first Cost Overrun.
The first Cost Overrun statutory unconscionability claim The relevant statutory provisions
  1. Westgem pleaded that the conduct alleged by it to constitute breaches of the various terms of the MOFA involved the Financiers engaging in unconscionable conduct in contravention of s 12CC of the ASIC Act (as in force prior to 1 January 2011).
  2. Under s 12CC(1) of the ASIC Act a person must not in trade or commerce in connection with the supply or possible supply of financial services engage in conduct that is, in all the circumstances, unconscionable. Section 12CC(2) sets out a non‑exhaustive list of the matters to which the court may have regard for the purposes of determining whether s 12CC(1) has been contravened. In 2009, s 12CC(2)(b) provided as follows:[292]
(2) Without in any way limiting the matters to which the court may have regard for the purpose of determining whether a person (the supplier) has contravened subsection (1) in connection with the supply or possible supply of financial services to another person (the service recipient), the court may have regard to:
(a) the relative strengths of the bargaining positions of the supplier and the service recipient; and

(b) whether, as a result of conduct engaged in by the supplier, the service recipient was required to comply with conditions that were not reasonably necessary for the protection of the legitimate interests of the supplier; and

(c) whether the service recipient was able to understand any documents relating to the supply or possible supply of the financial services; and

(d) whether any undue influence or pressure was exerted on, or any unfair tactics were used against, the service recipient or a person acting on behalf of the service recipient by the supplier or a person acting on behalf of the supplier in relation to the supply or possible supply of the financial services; and

(e) the amount for which, and the circumstances under which, the service recipient could have acquired identical or equivalent financial services from a person other than the supplier; and

(f) the extent to which the supplier's conduct towards the service recipient was consistent with the supplier's conduct in similar transactions between the supplier and other like service recipients; and

(g) if the person is a corporation—the requirements of any applicable industry code (see subsection (11)); and

(h) the requirements of any other industry code (see subsection (11)), if the service recipient acted on the reasonable belief that the supplier would comply with that code; and

(i) the extent to which the supplier unreasonably failed to disclose to the service recipient:
(i) any intended conduct of the supplier that might affect the interests of the service recipient; and

(ii) any risks to the service recipient arising from the supplier's intended conduct (being risks that the supplier should have foreseen would not be apparent to the service recipient); and
(j) the extent to which the supplier was willing to negotiate the terms and conditions of any contract for supply of the financial services with the service recipient; and

(ja) whether the supplier has a contractual right to vary unilaterally a term or condition of a contract between the supplier and the service recipient for the supply of the financial services; and

(k) the extent to which the supplier and the service recipient acted in good faith.
Applicable principles
  1. There was no dispute as to the principles that govern the application of the statutory provisions. It is unnecessary to refer to the principles in any detail. Both Westgem and the Financiers relied upon the statements of principle contained in the judgments of Bathurst CJ and Leeming JA in Ipstar Australia Pty Ltd v APS Satellite Pty Ltd.[293] In Westgem's written closing submissions it summarised the principles as follows:

(a) unconscionable conduct involves doing what should not be done in good conscience by reference to acceptable norms, standards or values;

(b) it is neither possible nor desirable to provide a comprehensive definition of unconscionable conduct in the range of conduct that may be unconscionable is wide; and

(c) unconscionability does not require moral obloquy or moral tainting.[294]

  1. In Australian Securities and Investments Commission v Kobelt,[295] Kiefel CJ and Bell J, and Gageler J separately suggested that, in the context of s 12CB, 'unconscionable' connotes such a departure from accepted community standards in the supply of financial services to warrant characterisation of the conduct as unconscionable, in other words as offensive to conscience.
  2. Determining whether a party engaged in unconscionable conduct entails 'a precise examination of the particular facts' and 'every connected circumstance' as well as 'a scrutiny of the exact relations established between the parties'.[296]
  3. The Financiers provided a more detailed outline of the applicable principles that incorporated the propositions distilled by Westgem from the authorities. The Financiers emphasised the following additional matters:

(a) In considering the question of whether the conduct is unconscionable, it is necessary to have regard to all the circumstances surrounding the transaction and this requires a close examination of the facts.[297]

(b) Where any one or more of these matters specified in s 12CC(2) existed in respect of particular conduct, each of those matters was to form part of the totality of the circumstances mandatorily to be taken into account for the purposes of determining whether a person has engaged in conduct that is unconscionable - a plaintiff cannot pick and choose to rely upon some of the matters specified but not on others.[298]

(c) Section 12CC(2)(l) expressly incorporated the concept of acting in good faith. In Ipstar Bathurst CJ observed that in the context of the exercise of contractual powers, the concept is understood as including compliance with honest standards of conduct and compliance with standards of conduct which are reasonable having regard to the interests of the parties, citing, among other decisions, the decision in Burger King.

The parties' contentions

Westgem's contentions

  1. In its closing written submissions Westgem articulated its statutory unconscionability case as follows:[299]
The community would expect that Bankwest as Facility Agent would first bother to read and understand the relevant provisions of the MOFA and Mr Sanders' report before making a determination and demand that would have significant consequences for the borrower and its guarantors. Bankwest's conduct in relation to Westgem was reckless and high-handed. Bankwest acted without regard to Westgem's contractual rights under the MOFA and without regard to the serious consequences that its actions would have for Westgem and its guarantors. The conduct is properly characterised in all the circumstances as being unconscionable.

Financiers' contentions

  1. The Financiers made the preliminary observation that Westgem did not call any witnesses to give evidence in support of its unconscionability claim - it relied entirely on the documents.
  2. The Financiers made ten submissions why there had been no unconscionable conduct on their part - the submissions were as follows:

(a) There was no relevant imbalance of bargaining position between the parties. In support of that submission the Financiers pointed to the following:

(i) The Facility was for $316 million.

(ii) Westgem had access to legal advice from multiple sources and financial/strategic advice from Mr Clohessy.

(iii) Mr Saraceni and Mr Pourzand were experienced property developers and, as disclosed to the Financiers and recorded in Bankwest's internal documents they had access to combined net assets of approximately $400 million.[300]

(iv) Bankwest was in a vulnerable position because the Facility provided for the construction of its own head office.

(b) It was reasonably necessary for the protection of the Financiers' legitimate interests for there to be a demand for any Cost Overrun to be paid as quickly as possible.

(c) There was no suggestion that Westgem was not able to understand any of the documents.

(d) There was no suggestion that the Financiers exerted undue influence or pressure on Westgem nor were any unfair tactics used against it. Westgem thought it would have to pay a Cost Overrun and when told that it had to pay a Cost Overrun, it accepted that there was a Cost Overrun and then paid it.

(e) There was no evidence that an equivalent financial service could have been obtained elsewhere. Mr McDonald gave evidence that Cost Overrun provisions are commonly found in facilities used to fund construction projects - he was not cross‑examined about this evidence.[301]

(f) There was no evidence about the extent to which the Financiers' conduct was inconsistent with its conduct in similar transactions.

(g) The Financiers did not unreasonably fail to disclose to Westgem any intended conduct that might affect its interests - the possibility that a Cost Overrun might be declared was a contractual stipulation contained in the MOFA negotiated between the parties.

(h) The Financiers were willing to negotiate the terms and conditions of the MOFA - those terms had been subject of extensive negotiation before the MOFA was executed.

(i) The Financiers did not have any contractual right to unilaterally vary any terms or conditions of the MOFA.

(j) There was no suggestion or evidence that the Financiers had acted dishonestly or otherwise than in good faith.

Consideration
  1. The statutory unconscionability claim arises in the unlikely context of a commercial dispute between, on one side, experienced property developers with very substantial assets advised by an experienced financial adviser, lawyers and quantity surveyors and on the other side, the Financiers. This context, coupled with Westgem's decision not to call any evidence to explain the effect on it of the alleged unconscionable conduct, constitutes a difficult platform from which to advance an unconscionable conduct claim.
  2. For the reasons developed below there was nothing inherently unconscionable in the Financiers' relying on their contractual rights and there was nothing in the circumstances that made the exercise of their contractual rights unconscionable.
  3. The failure by Westgem to establish that the MOFA incorporated the contractual terms for which it contended and the findings made on the alleged breaches of those terms constitute further substantial obstacles in Westgem's path to success on its unconscionability claim in respect of the first Cost Overrun. The effect of those conclusions and findings is that, in withholding further Drawings and in seeking payment of the first Cost Overrun, the Financiers were doing no more than exercising their rights under the MOFA.
  4. The contractual rights were part of the bargain freely entered into by Westgem after a long period of negotiation. The right to withhold further Drawings under the MOFA until a Cost Overrun was paid was not only part of the bargain but, given the facility limits and the ratio requirements referred to earlier in these reasons, it was not a right that was in any sense disproportionate to the event that gave rise to its exercise.
  5. The overwhelming impression conveyed by the contemporaneous documents - Westgem's internal documents and its communications with the Financiers' representatives is that Mr Saraceni, Mr Pourzand, Mr Clohessy and the managers who worked with them were experienced astute business people. Westgem was not an entity likely to be taken advantage of. Mr Clohessy was responsible for many of the communications exchanged with the Financiers. He advocated forcefully on Westgem's behalf and when he was unhappy with the Financiers' conduct he made that clear.
  6. The possibility of a Cost Overrun was not sprung on Westgem by the Financiers. The possibility had been raised by Mr Nagle in his letter to Mr Saraceni of 9 April 2009. By early July 2009 Mr Saraceni, Mr Pourzand and Mr Clohessy were putting in place arrangements to cover an anticipated Cost Overrun that would require a contribution of equity.
  7. Westgem's internal calculations disclosed that a Cost Overrun of (at least) $13 million was inevitable. As recorded in the factual findings, 'Financial Statement No 6', prepared for Westgem's internal purposes in June 2009, recorded that the 'contract sum' was $251,331,347 suggesting a Cost Overrun of approximately $20 million. In any event, the contract sum figure in Financial Statement No 6 exceeded the 'forecast final figure' contained in the Response Budget prepared by Mr Frank Saraceni and disclosed to RBB by at least $15 million. The Response Budget was, as Mr Simpson described it, 'an extremely positive snapshot', prepared (as I have inferred) to ease the Financiers' concerns about the possibility of a Cost Overrun. In the light of Westgem's internal calculations it is very difficult to see how it can be said that the Financiers acted unconscionably in pressing for payment of the Cost Overrun of $13 million.
  8. By failing to disclose to Bankwest the construction cost figures contained in Financial Statement No 6 and instead disclosing the 'extremely positive snapshot' figures contained in the Response Budget Westgem was not being candid with the Financiers. In this respect Westgem's conduct underlines the necessity for, and legitimacy of, the Financiers' reliance upon their contractual rights to protect their interests.
  9. For these reasons I am not satisfied that Westgem has established that the Financiers' conduct, in all of the circumstances, was unconscionable.
First Cost Overrun misleading or deceptive conduct claim
  1. Westgem alleges that Mr Nagle's assertion on 22 July 2009 that there was a Cost Overrun in the sum of $13 million constituted conduct that contravened the prohibitions against misleading or deceptive conduct contained in s 12DA of the ASIC Act and s 10 of the FTA.[302]
  2. As I have found that there was a Cost Overrun in the amount of $13 million on 22 July 2009 the misleading or deceptive conduct claim is not made out.
Financiers' positive defences to the first Cost Overrun claim
  1. The Financiers raised a wide range of positive defences to Westgem's first Cost Overrun claim. As I have concluded that Westgem's first Cost Overrun claims fail at a number of levels it is unnecessary to address the Financiers' further defences.
Second Cost Overrun - factual findings

September 2009

  1. Salta prepared Project Control Group Report No 14 for a meeting of the Project Control Group that took place on 2 September 2009. In the report Salta recorded its view that the 'current approved contract sum' was $267,730,082.[303]
  2. On 2 September 2009 Mr Nagle sent an email to Mr Clohessy in which he stated that he had asked Mr Sanders to review the position set out in his email to Mr Clohessy of 17 August 2009 (in which Mr Nagle had compared the adjustments to various provisional sum items recorded in Contract Sum Adjustment 20 with figures provided by RBB in its 16 July 2009 report and with the figures contained in Mr Frank Saraceni's 'response budget') and proposed that he and Mr Clohessy get together with Mr Frank Saraceni the following week to go through the details.[304] Mr Nagle stated that the position '... must be resolved quickly in time for the payment claim later this month'.
Mr Sanders' 3 September 'high level calculation'
  1. Following the Project Control Group meeting on 2 September 2009 Mr Sanders reviewed Salta's structure remeasure variation register and formed the view that there was approximately $6 million in structure remeasure costs yet to be approved by a Contract Sum Adjustment, but which were likely to be approved, and that there was an additional amount of approximately $1 million in further structural variations which were likely to be incurred.[305] Mr Sanders calculated that the total estimated construction cost had increased to $262,460,939 that he rounded up to $265,000,000. He prepared a note recording his calculations. The contents of Mr Sanders' note are relevant to a credit issue raised in relation to a cost to complete calculation undertaken by him later in September and for that reasons I include it in full:[306]
Contract Sum $211,879,573

CSA's

To No 21 $267,730,082

Add back Tunnel $4,300,000

$272,030,082

Deduct IFO CSA's 31,869,143

$240,160,939

Heritage works $2.5 m

Pavilion $1.5 m

Tunnel overrun $2.0 m 6,000,000

$246,160,939

Reinforcement overrun 3,000,000

249,160,939

Other
  • VM 1.8 m
  • P Sums balance 1.0 m
  • Plant room 0.5 m
3,300,000

252,460,939

Other variations etc 10,000,000

262,460,939

Say 265,000,000
  1. I accept the explanation of Mr Sanders' calculations given in his witness statement, which was as follows:[307]
On 3 September 2009, I performed some high level calculations, without going into much detail, of the construction cost to complete the project in order to get a feel for the then estimated total construction cost. I did so as I was concerned that the construction costs to complete the project were still blowing out: [RBB.001.012.0033]. I prepared this review based on the information and numbers that had been provided to me by Salta and the Superintendent, as well as my own observations of the project and my experience in assessing the costs to complete projects. My workings were as follows:

(a) I started with the original contract sum of $211,879,573 and added the variations up to CSA 21, which brought the contract sum to $267,730,082;

(b) I added back $4,300,000 for the tunnel for the reasons I have stated above, which brought the total to $272,030,082;

(c) I then deducted the CSAs which related to the IFO Works, totalling $31,869,143, which reflected the current value of the IFO Works in Salta's scope, bringing the total to $240,160,939;

(d) I then added:
(i) $2.5 million for the heritage works as, based on the estimate I prepared on 13 May 2009, I formed the view that the $500,000 allowance of the provisional sum would be inadequate for these works;

(ii) $1.5 million for the pavilion as I was aware that a variation would be required to cover these additional works; and

(iii) a $2 million contingency for tunnel overruns as, based on my initial estimate referred to in paragraphs 31to 37 above, I formed the view that there would be an overrun on the provisional sum for the tunnel of $4.3 million. As I explained above, I had initially estimated a provisional sum of $5 million for the tunnel in November 2007. I had formed that assessment based on what I had been told by Frank Saraceni regarding the works. However, by this stage, I was concerned that a provisional sum of $5 million would be insufficient.

These amounts brought the total to $246,160,939;

(e) I then added an additional $3 million for reinforcement remeasure overrun, which is a specific line item in the structure remeasure, which brought the figure to $249,160,939. I included this figure as an allowance for the ongoing dispute regarding the structure remeasure that I was aware of, based on my review of the correspondence, discussions with the Superintendent and attendance at PCG meetings.

(f) I also accounted for 'other' costs, including:
(i) 'VM' of $1.8 million for value management, which I took from Salta's figures in its letter dated 12 August 2009;

(ii) $1 million for the balance of provisional sums;

(iii) $500,000 for the plant room, which referred to a variation for relocating the plant room from the basement to the roof, which I was aware was required based on my attendance at PCG meetings and discussions with Paul Simpson; and
These amounts totalled $3.3 million. Adding those figures brought the total cost to $252,460,939; and

(g) finally, I added $10 million for other variations, being unprocessed variation claims and variations which might be submitted in the future. This brought the total forecast construction costs to $262,460,939. I then rounded this up to $265 million.

Westgem's September 2009 construction cost forecast

  1. On 4 September 2009 Mr Nagle and Mr Sanders met Mr Frank Saraceni to discuss project costs. At the meeting Mr Frank Saraceni produced a 'Summary of Construction Costs to the end of August 2009' which incorporated Contract Sum Adjustment 21 (Westgem's September 2009 construction cost forecast). The summary was as follows:[308]
RAINE SQUARE DEVELOPMENT

Summary of Construction Costs to end of August 2009

Incorporating CSA No. 21


Base Build
IFO/Tenant Funded
Total

Contract Sum


$ 281,879,573
Less Provisional Sums


$ 92,477,218



$189,402,355


$


$189,402,355
Approved Provisional Sum Expenditure
$ 38,433,306
$ 31,869,143
$ 70,302,450
Approved Variations

$ 7,025,277
$
$ 7,025,277
Provisional Sums not deleted or approved for expenditure
$ 1,000,000
$
$ 1,000,000


Adjusted Contract Sum to end of August 2009


$235,860,939


$ 31,869,143


$267,730,082
Credits to CSA's due



Removal of scope to podium to build shell and core only - non IFO work
-$ 2,000,000
$
-$ 2,000,000
Mechanical variations
-$ 600,000
$
-$ 600,000
Allowance for the tunnel
$ 4,000,000
$
$ 4,000,000
Contingency

$ 5,739,061
$
$ 5,739,061


Forecast Adjusted Contract Sum


$243,000,000


$31,869,143


$274,869,143


Other Items




Unapproved Variations with an SI and not subject to the structure re-measure
$ 2,772,326

$ 2,772,326
Extension of Time Claims
$
$
$

Westgem claims credits

  1. At the meeting on 4 September 2009 Mr Frank Saraceni told Mr Nagle and Mr Sanders that Westgem's quantity surveyors, Rider Levett Bucknall (RLB), were measuring 'credits' in Westgem's favour and that a Contract Sum Adjustment would be issued in respect of those credits in the order of $2 million. Mr Sanders said that he would advise the banks to use his figures for construction costs unless Mr Frank Saraceni could prove them wrong.[309]
  2. The claim that 'credits' were due and ought to be taken into account in calculating the Cost to Complete became (to adopt the phrase in the Financiers' closing submissions) 'a recurring theme' in the communications between Westgem and the Finance Parties in the period between September and November 2009. The credits in Mr Frank Saraceni's summary of construction costs were for 'the removal of scope to podium to build shell and core only' in the amount of $2 million and 'mechanical variations' in the sum of $600,000 and the tunnel.
  3. By email sent on 8 September 2009 Mr Sanders sought details of the credits from Mr Simpson[310] (this email was copied to Mr Nagle) and by email sent on the same day Mr Nagle stated to Mr Clohessy 'The information has yet to be provided. Can you please urgently address the matter'.[311]

Mr Sanders reviews Westgem's September 2009 forecast and Contract Sum Adjustment 22

  1. On 9 September 2009 Mr Nagle sent an email to Mr Sanders in which he stated that he had tried to reconcile the various cost estimates that had been provided including Westgem's 4 September cost estimate of $243 million but was finding it difficult to compare the estimates as he was unsure whether certain costs had been included or excluded. He asked Mr Sanders to review the position.[312]
  2. On the afternoon of 11 September 2009 Mr Nagle sent an email to Mr Clohessy recording that Mr Sanders had not received details of the 'CSA credits'.[313]
  3. On Friday, 11 September 2009 Mr Sanders was in the process of finalising a review of the forecast construction cost for the Project which he had started to prepare earlier in the week in response to Mr Nagle's request on 9 September 2009.
  4. At 4.26 pm on 11 September 2009 Contract Sum Adjustment 22 was sent by Mr Simpson to a number of people including Mr Sanders.[314] It referred to two adjustments described as follows:

(a) 'VFN 590 - Reduced scope of works to Podium level - based on Indicative Estimate prepared by Rider Levett Bucknall dated 7 September 2009 - Deduction: $1,700,000'.

(b) 'VFN 591 - Deduct supply and installation of window blinds - Deduction: $660,000'.

  1. The Podium was the name given to the level at the base of the main tower or viewed from another perspective the uppermost level, or roof, of the three levels of retail space from which the main tower emerged. The Podium comprised a landscaped area and an area to the north of the main tower on which a structure known as the Pavilion was to be constructed. The Pavilion was to contain conference and training facilities for Bankwest. The variation removed from Salta's scope of works the fit out of the Pavilion, with the result that, in respect of the Pavilion, Salta's scope was reduced to the construction of the 'shell and core' of the Pavilion. In subsequent communications and discussions the variation was referred to interchangeably as the Podium works or the Pavilion works.
  2. In the email to which Contract Sum Adjustment 22 was attached Mr Simpson stated:[315]
With regard to the values please note VFN 590 is based on an Indicative Estimate prepared for us by an Independent QS and whilst we acknowledge that the rates will need to be altered and the services figures confirmed, the overall amount is deemed sufficiently accurate for this purpose. VFN 591 is self-explanatory, will be covered in due course by an SI and then subject to confirmation by the subcontractor.
  1. Contract Sum Adjustment 22 attached a letter dated 7 September 2009 from RLB to Saraceni Project Engineering explaining the basis upon which it had prepared the 'Indicative Estimate' referred to in Mr Simpson's email and it is significant. Relevantly, the letter stated:[316]
Further to your recent instructions, we have prepared an Indicative Estimate for the cost savings anticipated as a consequence of the decision to construct the Podium level of the above development on a 'shell and core' basis.

We understand that the previously documented works to the office and pavilion areas on this level have been significantly reduced in scope and will now be substantially undertaken by the tenant as part of their fit-out works.

We attach our assessment of the deduction we anticipate as a consequence of the reduced scope of works by the base building contractor, in the total amount of $1,668,476 (excluding GST).

Our assessment has been based upon information provided by yourselves and advice received from each of the building services consultants.
  1. Also attached to Mr Simpson's email of 11 September 2009 was a copy of a handwritten calculation of the amount to be credited in respect of the removal of the supply and installation of the window blinds. The calculation contained the statement 'Value to be confirmed by subcontractor in due course'.[317]
  2. It is convenient to depart from a chronological account and record two matters:

(a) First, on 22 September 2009 Mr Artelaris sent an email to a representative of the blinds subcontractor in which he expressed the hope that the subcontractor appreciated the reasons why '[Westgem] have had to extract the blinds installation from Salta's contract' but, after referring to other matters, went on to state that the installation of the blinds might remain within the Salta contract. Mr Artelaris asked the blinds subcontractor to keep the communication 'strictly confidential between ourselves'.[318]

(b) Secondly, on 23 September 2009 Mr Nagle sent an email to Mr Sanders in which he recorded that he had spoken with the CBA Fit-Out team in respect of the Podium credit and stated:[319]

While the CSA removes the obligation from the Salta contract I have been advised that it is expected that the payment obligation still rests with Westgem (as part of its commitment to deliver the base build).

  1. Although by Contract Sum Adjustment 22 Westgem contended that VFN 591 gave rise to a credit in respect of window blinds, which should be taken into account when calculating the construction costs, ultimately, it did not press this contention and, as will be seen, the deduction of $660,000 did not feature in later lists of the credits Westgem contended were not taken into account when they should have been.
  2. On 12 September 2009 Mr Nagle sent an email to Mr Clohessy in which he referred to a telephone conversation with Mr Clohessy and stated:[320]
The $260m forecast to come from RBB does not take into account any potential CSA credits. These will be considered when the details are provided.

The forecast includes a general contingency for the rest of the project.
  1. I infer from this email that Mr Sanders had informed Mr Nagle of his revised cost forecast contained in the report that he had prepared but which was not sent to Mr Nagle until 14 September 2009 - Mr Sanders had met Mr Nagle on 11 September 2009.[321]
  2. Mr Sanders' evidence was that he did not recall reviewing Mr Simpson's email and Contract Sum Adjustment 22 as he was preparing his report. His evidence was that if he had received Contract Sum Adjustment 22 in time to review it before finalising his report he would not have allowed the credits against the adjusted contract sum for the Podium works or the blinds.[322]
  3. Mr Sanders' explanation as to why he would not have allowed a credit for the Podium works was that the credit was based upon an indicative estimate prepared by Westgem's quantity surveyors and not upon a figure agreed between the contracting parties. He said that it was unusual and he was surprised to see a negative Contract Sum Adjustment based on an estimate. He said he would not have acknowledged it as a credit unless he had some confidence that Salta would agree with the Contract Sum Adjustment. Further Mr Sanders understood that although the work had been removed from Salta's contract it still needed to be completed and he was not satisfied that the work would be funded from a source other than the construction budget. For these reasons he did not regard the deduction in respect of the cost of the Podium work as a 'credit'. Mr Sanders adopted a similar approach to the 'credit' Westgem contended it should have been allowed for the blinds. Mr Sanders considered that the blinds would need to be supplied and installed and that in the absence of any evidence to the contrary the cost would need to be funded from the construction budget and on that basis no 'credit' should be allowed. I accept Mr Sanders' evidence of the reasons why he would not have not have been prepared to allow credits for the Podium works or the blinds.[323]
  4. Mr Sanders forwarded Contract Sum Adjustment 22 to Mr Nagle by email sent at 11.44 am on Monday, 14 September 2009. In the forwarding email Mr Sanders stated: 'Received today'. The email recorded that it had been forwarded to Mr Sanders from an email address xerox.rbb.local at 10.14 am on 14 September 2009 ‑ Mr Sanders explained that he had printed the email from Mr Simpson and then scanned it.[324]

RBB's 14 September 2009 report

  1. On 14 September 2009 at 12.52 pm Mr Sanders sent his report on the Cost to Complete to Mr Nagle. The material parts of the report were as follows:[325]
1. Original approved Construction Budget
Contract Sum
$211,879,573
Allowance for variations
18,200,000
Total
$230,079,573


2. Current Adjusted Contract Sum
To CSA 21

Deduct IFO works
$267,730,082
Adjusted Contract Sum
31,869,143
Total
$235,860,939


3. Saracen Engineering Forecast (attached)
Adjusted contract Sum ex IFO
$235,860,939
Credits

■ Shell and core
(2,000,000)
■ Mechanical
(600,000)
Tunnel allowance
4,000,000
Contingency
5,739,061
Forecast Total
$243,000,000


4. RBB Review
Adjusted Contract Sum ex IFO
$235,860,939
Add back tunnel P.S
4,300,000

$240,160,939
Allow for Salta initiated risks (part allowance)

i) Reinforcement measure
3,000,000
ii) Structural variations
1,000,000
iii) Plant room revisions
500,000
iv) Landscape PS overrun
500,000
v) Variations general
6,000,000

251,160,939
Other items

i) Pavilion building
1,500,000

252,660,939
Possible Risk

i) Overrun on tunnel PS
2,000,000

254,660,939


Ongoing contingency required by Bankwest (say)
5,339,061
Forecast Total
$260,000,000
Note: excludes credits proposed by Saracen but not yet received.
  1. Mr Sanders was cross‑examined about the inclusion of the item 'Ongoing contingency required by Bankwest (say) 5,339,061'. Mr Sanders' evidence-in-chief in relation to the inclusion of this allowance in his calculations was as follows:[326]
I allowed an additional contingency for the balance of the Project at $5,339,061, taking the total forecast total to $260 million. This additional ongoing contingency was to allow for future variations not yet submitted or known, the ongoing dispute between Westgem and Salta regarding the quantum of remeasure, future overruns on provisional sums and any issues not yet contemplated. This additional ongoing contingency of approximately $5.3 million included an amount for heritage works. I had previously estimated that work to cost $2.5 million, based on certain assumptions as to the scope of those works, however the scope was yet to be confirmed and therefore the cost was uncertain. I had previously allowed in my hand written calculations on 3 September 2009 ... An ongoing contingency of $10 million.... On review of this assessment, I allowed for an ongoing contingency of $5.3 million. I had done so to be moderate in favour of Westgem, as I explained above in paragraph 23.
  1. In par 23 of his witness statement Mr Sanders had explained that when he was estimating construction costs during the life of the Project his approach was to be moderate, an approach which favoured the developer, and that he took this approach because he knew that if he was overly cautious and alarmist and estimated construction costs that might be above the developer's level of funding that would result in significant consequences which the developer and the bank would have to deal with but which might not, in fact, eventuate.
  2. In cross-examination Mr Sanders was referred to the explanation for making the allowances for contingencies contained in the passage of his witness statement set out in the preceding paragraph. He was asked about the words 'Ongoing contingency required by the bank (say)'. The cross‑examination began as follows:[327]
Why did you write those words?---Because I need - the bank requires an ongoing contingency to finish the project.

But I thought you said this was your opinion?---It is. I - I have the same view.

Well, why did you need to say that one was required by the bank?---Because when I discussed these things with Frank, he would rather I did not have it - and I am explaining I have to have it the bank requires it, I require it.

...

And when you say 'say' at the end of that sentence, what were you trying to communicate?---That it's an allowance rounding.

Right. That is what I thought you were going to say. Well, ordinarily, if it was an allowance and one was going to round, to say - to use the word 'say' indicates that you were either rounding up or rounding down the number; correct?---No.

Right. You do not use the word 'say' in relation to an absolutely specific number, do you?---I was making the point here that I was rounding this to 260 million.

Why?---Which included a contingency ongoing as I have stated in item F.

All right. So that means, does it, that the amount you chose for that contingency, and you say you chose it, was driven by a desire by you to reach a conclusion of $260 million; is that right?---No, that is saying - - -

Well, then, tell me why the figure is $5,339,061?---Because once I decided that - to allow a contingency in the order of five, five and a half million, I chose to round it.
  1. The cross-examiner pursued the proposition that Mr Sanders had adopted the contingency figure of $5,339,061 to arrive at a pre‑determined result:[328]
But doesn't this tell us that your process of thinking involved at least an element of reverse reasoning, and what I mean by that is you determine that you want the result to be $260 million and then you identify a contingency and an amount that brings the total to that number. That is what you are doing, isn't it?---No.

What you could do is simply have your contingency which, of course, is nothing more than a best guess is it, a contingency?---I could have

Sorry?---I could have put a number in, a round number and then rounded it.

You could have put a - - - ?---I chose to do it in one hit.

Right. And the reason you did that is because the bank had asked you to do it; correct?---No.

And that's why you wrote the words 'required by Bankwest'; correct?‑‑‑It is not correct.

Well, your only explanation for why you wrote the words 'required by Bankwest' is because, what, Frank Saraceni asked you to write those words?---No.

Why did you write those words again?---I was making the point that to go forward in the project in the calculation I needed to allow future contingency.

Yes?---It is a requirement of both me and the bank.
  1. Anticipating the line of cross‑examination Mr Sanders said that he could not believe 'you're suggesting that I concocted this to the bank's number'. That proposition was then put to Mr Sanders:[329]
All right. Just relax. I am suggesting to you that the words: ongoing contingency required by the bank - by Bankwest, meant when you wrote them, exactly what they say. That that was an ongoing contingency that Bankwest had required. That is what I am suggesting to you?---Well, it's not correct.

Right?---What they require is an ongoing contingency. You're suggesting to me that I put that number in there to get a bank's number.

Correct?---That's not correct.
  1. It was put to Mr Sanders that the reason for the inclusion of the contingency was that Mr Nagle had already demanded payment of $17 million and Mr Nagle needed Mr Sanders' calculations to show a Cost Overrun of $17 million.[330]
And what I am suggesting to you, it was not to get to the bank's number, it was to get back to the number you had told Mr Nagle at an earlier meeting on 11 September. And that what had happened is that you had had a meeting with Mr Nagle, some numbers had been scratched out by him and you, and that you had told him that you thought there would be a costs overrun of $17 million. That's what happened; correct?---I do not recall.

You do not recall. And then what happened is you had some form of communication with Mr Nagle prior to signing off on this report and you said something like 'Look, it's not going to be 17 million. It's going to be some amount less.' That happened, didn't it?---I don't believe so.

And Mr Nagle said to you 'well, it has got to be 17 million because I have already told Westgem it is 17 million and I have already demanded that they pay it'. Remember that?---No.

And he said, 'you can fix it just by putting an extra contingency in', didn't he?---Absolutely not.

And that is why you wanted people reading this to know that that contingency was something that the bank had required?---I will revisit that. The bank requires a contingency. You are suggesting they gave me a number, to match a number. It is not correct.

I am suggesting that Mr Nagle said he was in an embarrassed position because he had already made a demand on Westgem 17, so why do not you put in a further contingency so that it comes up to 17. That is what I am suggesting to you?---Well, you are wrong.
  1. In closing submissions Westgem contended that Mr Sanders' explanation for the words 'as required by Bankwest' in his report was illogical, implausible and inconsistent with contemporaneous documents in which Bankwest had decided to maintain a $5 million contingency. The 'contemporaneous document' cited by Westgem was an email from Mr Leber to Mr Jeff Malcolm of Bankwest in which, referring to the first Cost Overrun, Mr Leber had (relevantly) written:[331]
Recommended equity contribution is $13 million. This will meet all identified Cost Overruns to date & maintain a contingency of $5 million (approx. 5% of remain contract value) for the remainder of the project.
  1. Mr Sanders' explanation for including the words 'required by Bankwest' was unclear. The issue, however, is whether Mr Sanders' estimate of the construction costs contained in his report accorded with opinions genuinely held by him or whether he had adjusted his estimate at the Financiers' request. There are two reasons why I am satisfied that Mr Sanders had not adjusted his estimate at the Financiers' request. The first is that the objective circumstances support the conclusion that the estimate reflected Mr Sanders' opinion and was the product of the application of his professional expertise to the matters of which he was aware. The second is that in my assessment Mr Sanders was an honest witness and his denial that he had not included the contingency 'to match the bank's number' should be accepted.
  2. I will begin with the objective circumstances. The first circumstance is that Mr Sanders had included a contingency in his 16 July 2009 report of $4,923,248 ($1,923,248 and $3,000,000). The second circumstance is that in the high level calculations undertaken by Mr Sanders on 3 September 2009 he had estimated the construction costs at $265 million and this figure included a contingency of $10 million (albeit it was referred to as 'Other variations etc'). The third circumstance is that the inclusion of a contingency was not an unreasonable or unusual thing to do and the amount of $5,339,061 was not objectively unreasonable. In this respect it is to be noted that Mr Frank Saraceni had included a contingency in Westgem's 4 September 2009 construction cost forecast and had, so it appears, adopted an approach very similar to that adopted by Mr Sanders. That is, Mr Frank Saraceni had included a contingency in the very specific amount of $5,739,061, inferentially to produce a round number for the 'Forecast Adjusted Contract Sum' of $243 million. The fourth circumstance, which is perhaps an extension of the third circumstance, is that there is nothing sinister in both Mr Sanders and Bankwest holding the view that a contingency was required or that the inclusion of a contingency was a matter Mr Sanders had discussed with Mr Nagle or others at Bankwest. That there had been such a discussion does not justify the conclusion that Mr Sanders had included his contingency figure in order to arrive at a predetermined outcome. The fifth circumstance is that while Mr Nagle had sent an email to Mr Clohessy on 12 September 2009 in which he referred to the '$260 million forecast to come from RBB ...' there is no evidence to support the proposition put to Mr Sanders in cross‑examination that he adjusted his estimate because the Financiers had demanded Westgem pay a Cost Overrun of $17 million before they received his report and they did not want to withdraw such a demand.
  3. My observations about Mr Sanders' credit generally are as follows. My impression was that Mr Sanders found giving evidence a stressful experience. He appeared very tense. He was from time to time (understandably) defensive in his responses to questions as is apparent from the extracts of his cross‑examination set out above. My strong impression, however, was that the stress and tension Mr Sanders appeared to be under was not an indication that his evidence was untruthful or that he was dishonest. He was not evasive in his answers. He was genuinely upset that his professional integrity was the subject of attack. Mr Sanders had been a quantity surveyor since 1972. He had worked on a number of large construction projects and had acted as the independent certifier on developments comparable to Raine Square. He had held various positions in the Australian Institute of Quantity Surveyors and was the National President of that organisation between 2009 and 2011. It is inherently unlikely that a person of Mr Sanders' experience and seniority in his profession would jeopardise his professional reputation in the manner Westgem alleges.
  4. Mr Sanders was cross‑examined also about the last line of his report that read, 'excludes credits proposed by Saracen but not yet received'. It was suggested to Mr Sanders that this was not an accurate statement because by the time he sent the report to Mr Nagle on Monday, 14 September 2009, he had received Contract Sum Adjustment 22 as it had been sent to him the preceding Friday ‑ 11 September 2009. He was cross‑examined about why he had said that the document had been 'Received today' in his email to Mr Nagle of 11.44 am on 14 September 2009 and it was suggested to him that this wording created a false impression.[332] It was suggested to Mr Sanders that he 'couldn't bring himself not to pass on' Contract Sum Adjustment 22 to Mr Nagle and that he wanted to make sure that Mr Nagle knew that the opinion expressed in his report was out of date as it did not take into account Contract Sum Adjustment 22. Mr Sanders said that he had made a mistake and should have said in the email 'reviewed today'.[333] I found Mr Sanders's evidence about the wording of his email by which he forwarded Contract Sum Adjustment 22 to Mr Nagle a little unclear but I do not accept the proposition developed in the cross‑examination to which I have referred, that is, Mr Sanders was concerned to protect his own position from any adverse consequences that might flow from reliance on a report that was not based on the latest information. When cross-examined Mr Sanders was being asked about his thought processes at the time he sent a two word email some nine and a half years before he gave evidence. In the absence of evidence of any objective facts supporting the proposition that Mr Sanders was concerned about his own position I attribute the lack of clarity in his evidence to the elapse of time rather than anything more sinister.

Mr Sanders discusses RBB report with Mr Frank Saraceni

  1. Mr Sanders gave evidence, which I accept, that he discussed his 14 September 2009 report with Mr Frank Saraceni shortly after he prepared it. He said that Mr Saraceni accepted that the total construction cost was $243 million. Mr Sanders said that, in response, he had said to Mr Saraceni that in order to forecast a realistic cost to complete he had to take into account some of Salta's variation claims as well as include some added contingency to allow for likely future variations, overruns and remeasure and therefore his assessment was that the total construction costs would be $260 million.

Mr Nagle acts on RBB's 14 September 2009 report

  1. I infer that Mr Nagle read the email sent to him by Mr Sanders at 11.44 am on 14 September 2009 attaching Contract Sum Adjustment 22 and read Contract Sum Adjustment 22 and gave it consideration as a matter of some urgency. I infer he read these documents before determining the cost to complete for the purposes of assessing whether there was a further Cost Overrun. I draw this inference from the following facts: first, Mr Nagle had been seeking details of the credits claimed by Westgem since the issue of credits had been raised by Mr Frank Saraceni on 4 September 2009 and it would have been reasonable for Mr Nagle to assume that Contract Sum Adjustment 22 would have addressed those credits - in his email to Mr Clohessy of 12 September 2009 he referred to 'CSA credits'; second, earlier Contract Sum Adjustments, in particular Contract Sum Adjustment 20, had given rise to a number of concerns on Mr Nagle's part which meant it was likely that he would have paid immediate attention to a further Contract Sum Adjustment; third, Mr Nagle was required to make a determination of the Cost to Complete before Westgem's September drawdown request made for the purposes of funding Salta's September 2009 progress payment - he was subject to time constraints; and, fourth, in his email of 12 September 2009 Mr Nagle had told Mr Clohessy that RBB's figure of $260 million did not take account of 'CSA credits' and that they would be considered 'when the details are provided'.

Westgem's Financial Statement No 7.1

  1. On 14 September 2009 Financial Statement No 7.1 was prepared by Westgem.[334] It specified a forecast contract sum of $246,402,313. This sum did not include any allowance for contingencies. Financial Statement No 7.1 was not provided to the Finance Parties.
  2. On 14 September 2009 Mr Clohessy sent an email to Mr Nagle seeking a meeting with Mr Jon Sutton and Mr Peter Deans 'to discuss some of the issues Westgem is facing with Salta at present'.[335] In his email Mr Clohessy addressed the issue of the Project's cost and stated:
We believe [Salta's] constant attempts to cast doubts over the project's cost is more about pressuring the borrower to pay additional funds over and above the contract price and or mitigate the level of liquidated damages they already face. Whilst Luke believes that costs are under control, clearly the final cost has come under pressure for a number of reasons not the least of which is Salta's refusal to meet its obligation to work with the borrower to achieve cost savings. You may remember this was part of the rationale both for using Salta and also part of the strategy for getting the Bank into occupation on time. In addition variations requested by the bank as tenant and Luke's desire to deliver a higher standard finish has been the other driver of any increased project cost.

Mr Nagle's September 2009 Cost to Complete assessment

  1. On 17 September 2009 Mr Nagle, with assistance from Mr Leber, prepared a 17 page Credit Risk Summary.[336] The summary set out brief details of Mr Saraceni and Mr Pourzand, the Project, the MOFA and the history up to the first Cost Overrun. Mr Nagle recorded that since July 2009 RBB had received new information from both Westgem and Salta regarding the status of provisional sums, further agreed cost variations, and outstanding cost variations yet to be approved and that RBB had undertaken a cost review and recommended an increase in the construction cost estimate by $17 million bringing the revised construction cost estimate to $260 million. Mr Nagle set out in a table the key elements of the construction costs to highlight the variations between the figures in RBB's July review and the figures in their September review. Mr Nagle provided the following summary:[337]
RBB considers that the proposed construction cost estimate of $260 [million] to be the minimum forecast position for the Project. RBB cannot guarantee that further cost variations will not arise in the future, however the recommended position is based on the information to hand and the adoption of increased contingencies given recent experience.

It should be noted that this cost assessment is based only on construction costs. We are undertaking an additional review of soft costs and the interest provision. It is likely that the soft cost budget will need to increase and we are seeking the Borrower's input into this process. In addition, we note that the current cashflow forecast includes provision for capitalised interest to 30 June 2010 (estimated practical completion date for Salta and the current facility expiry date).

While the financiers do not have a funding commitment past this date, we note that under the terms of the Agreement to Lease, the Rent Commencement Date is 120 days after Practical Completion. This 120 day period in which interest will need to be serviced or capitalised is not covered in current funding. Based on fully drawn debt of $316 [million] at current margins, this represents an additional funding cost of circa $3 [million] for the 120 day period.
  1. Mr Nagle included in the Credit Risk Summary a table described as a 'Cost to Complete Assessment'. I observe that the table might have been described more accurately as a Cost Overrun Assessment as that was the issue to which the contents of the table were directed. The table was as follows:
Cost to Complete Assessment ($000)
August 2009
Forecast
Facility Limit
$316,000
$316,000
Less Drawn to Date
$182,209
$182,209
Undrawn Commitment
$133,791
$133,791
Cost Overrun

$17,000
Total
$133,791
$150,791

Although not identified as such in the table, I infer that the figure of '$150,791' was the Cost to Complete.

  1. Immediately following the 'Cost to Complete Assessment' table Mr Nagle recorded that the forecast increase in 'Project Costs reported by RBB constituted a Cost Overrun under the terms of the financing documentation' and referred to Westgem's obligation to meet the Cost Overrun within five days of demand and to the fact that the Financiers were not obliged to provide further funding until such time as the Cost to Complete did not exceed the Undrawn Commitment of the Facility.

Notice of second Cost Overrun given

  1. On 18 September 2009 Mr Nagle sent a letter to Mr Saraceni in which he gave notice to Westgem that Bankwest had determined that there was a Cost Overrun of $17 million and made a demand for payment of that amount within five Business Days, that is, by 25 September 2009.[338] Mr Nagle attached a copy of RBB's report of 14 September 2009 to the letter of 18 September 2009.
  2. On 18 September 2009 Mr McDonald of BOSI, Mr Don Galbraith (Head of Business Credit - Risk Management Division at Bankwest) and Mr Mark Wlossak of CBA discussed the possibility of appointing the consultancy business 333 Advisory Pty Ltd as investigating accountants in respect of the Project and made contact by telephone with Mr Berrick Wilson of 333 Advisory to discuss a possible retainer. 333 Advisory was a consultancy business associated with the insolvency accounting firm KordaMentha, an association, which as will be seen, was of concern to Mr Saraceni, Mr Pourzand and Mr Clohessy.

Westgem's response to notice of second Cost Overrun

  1. Mr Clohessy responded to the Financiers' demand for payment of the second Cost Overrun on Westgem's behalf by sending an email to Mr Nagle in the evening of 18 September 2009. Mr Clohessy wrote:[339]
As per our various communications Westgem does not agree with the Banks' QS in this regard for a number of reasons not limited to but including, credits which have not been accounted for, the deduction of LD's due from the builder and specific items listed in the calculation such as the re-measure of the structure and general variations not yet agreed to.

To that end you are aware we have 3 of our QS going over the numbers in fine detail and hope to have additional information in due course.
  1. In opening senior counsel for Westgem referred to Mr Clohessy's statement to the effect that Westgem had three quantity surveyors going over the numbers in fine detail and stated that Mr Clohessy might have been 'over‑egging the pudding'.[340]
  2. As will be seen from the communications between Westgem and the Finance Parties to which I refer below until the end of November 2009 Westgem's position was that there was a further Cost Overrun but it was not as much as $17 million.

Meeting of the Financiers and Westgem

  1. On 21 September 2009 there was a meeting between representatives of Westgem (Mr Saraceni, Mr Clohessy and Mr Pourzand) and representatives of the Financiers (Mr Galbraith, Mr Nagle, Mr Leber, Mr Wlossak, Mr Deans and Mr Nathan). Mr McDonald of BOSI participated in the meeting by telephone. According to Mr McDonald, whose evidence I accept, the following discussion took place:[341]

(a) Mr Saraceni said words to the effect that Salta was to blame for the problems on site and that it was making spurious claims that were not legitimate and that were getting people agitated.

(b) Mr Saraceni said the banks' numbers were wrong - the Quantity Surveyor was not taking into account credits when deciding the amount of the Cost Overrun; and he did not agree with the banks' numbers and that the true Cost Overrun was not as large as the banks were saying.

(c) Mr Saraceni said replacing Salta with another builder was a solution for Westgem.

(d) Mr McDonald said words to the effect 'you [being Westgem] keep challenging the banks' figures and saying that the Quantity Surveyor was not doing their job properly by not taking into account credits, but what we do know is that we had a starting point, there has been a validated Cost Overrun already which has been determined and paid by you, and here we are now a month or so later with another Cost Overrun, and so I think our guys are closer to the numbers and what you are'.

(e) Mr Saraceni said that there was a prospect of takeout financing, that CBA was looking favourably on a takeout, and that he could sell other assets within his portfolio that would give him the liquidity to reduce the debt.

(f) Mr McDonald said words to the effect that 'if you [being Mr Saraceni and Mr Pourzand] do not have any cash liquidity, you could fix the Cost Overrun in the interim by providing the banks with security until you get the cash that was needed'.

(g) Mr Saraceni said words to the effect of 'yes we can, but why would I if I do not have to'.

(h) Mr McDonald said, 'because that is what you signed up to under the contract'.

(i) Mr Saraceni said words to the effect of 'not when you have not taken into account adjustments for credits in the cost to complete'.

(j) Mr McDonald said words to the effect of 'I am sympathetic to Westgem's issues with Salta, but that does not stop you from providing additional security to remedy the determined Cost Overrun'.

  1. In addition there was a discussion about the possibility of appointing 333 Advisory as an Investigating Accountant and that 333 Advisory was a 'different brand' to the insolvency accounting firm KordaMentha to which it was related. Mr Saraceni said something that gave Mr McDonald the impression that he was accepting of the appointment of 333 Advisory. Notwithstanding Mr McDonald's evidence about Mr Saraceni's attitude towards the appointment of 333 Advisory, given statements made subsequently by and on behalf of Mr Saraceni about the appointment of 333 Advisory, I doubt that as at 21 September 2009 he was accepting of the appointment.
  2. Although it does not appear from Mr McDonald's account of the 21 September 2009 meeting I find that at this meeting Mr Saraceni made a statement to the effect that Westgem was unable to pay $17 million in respect of the Cost Overrun. I make this finding on the basis that in a letter sent on 25 September 2009,[342] Bankwest recorded that a statement to that effect had been made and there was no complaint to the effect that was not so. Further, Westgem's inability to pay $17 million explains why there was a discussion at the meeting of the provision of security until the necessary cash could be raised.

Financiers' strategy in light of second Cost Overrun

  1. Bankwest formulated a strategy for dealing with the consequences of the second Cost Overrun with which BOSI was generally comfortable. The strategy involved the following elements:[343]

(a) informing Westgem that the Financiers did not support Westgem's proposed strategy of withholding payments to Salta and that, subject to the satisfaction of conditions, the Financiers would pay the September 2009 progress claim;

(b) the conditions on which the financiers would pay Salta's September 2009 progress claim were: receipt of a legal opinion from Deacons with respect to the Financiers' right to pay, execution of new unlimited joint and several guarantees and indemnities from all existing personal and corporate guarantors, and an undertaking from Westgem and the guarantors to provide to the Security Trustee effective second ranking mortgage security over acceptable securities having net equity of $50 million by no later than 30 November 2009;

(c) issuing a letter of default to Westgem on 25 September 2009 if the second Cost Overrun was not met by that date; and

(d) appointing an investigating accountant.

  1. On 24 September 2009 a meeting of Bankwest's Executive Credit Committee was held. Mr Nagle, Mr Leber and Mr Nathan provided a report about Westgem to the meeting. The minutes of the meeting record the following:[344]
[Mr Ross Griffiths] commented that building needed to be completed but to consider whether the developer and the builder were needed. Builder is more important than the developer to the Bank. Developer to be made to understand the position and not to be confrontational with the builder as a result. Fall back position if extra security is not provided is to be considered and in this case the developer is to be exited. [Mr Peter Deans] supported this view and noted that leverage with the developer related to all the other facilities provided by BWA.

Bankwest appoints 333

  1. On 25 September 2009 Bankwest appointed 333 Advisory to provide advice in relation to the Project. One of the tasks to be undertaken by 333 Advisory was to prepare a report to be used to inform the Financiers of the current status of the construction aspects of the Project, the cost to complete construction of the Project and to determine whether there had been a Cost Overrun.
  2. On 25 September 2009 Bankwest gave notice that it had appointed Berrick Wilson of 333 Real Estate Pty Ltd as an independent consultant to advise and report to the Financiers.[345]
  3. For the purpose of this judgment I will refer to the two 333 entities collectively as 333.

Westgem's September 2009 drawdown request

  1. On 25 September 2009 Westgem submitted Drawdown No 18 to fund a payment to Salta of $10,884,401.56 plus GST and to fund payment to consultants of $289,314.48 plus GST. The request for payment was refused but a further request to fund the payment to Salta was acceded to on 16 October 2009 but no drawing was permitted in respect of the consultants' fees.

Westgem's protests the second Cost Overrun determination

  1. On the afternoon of 25 September 2009 Mr Deans, Mr Nathan and Mr Pavisich of Bankwest met with Mr Saraceni and Mr Clohessy. At the beginning of the meeting Mr Saraceni and Mr Clohessy were angry that 333 had been appointed by Bankwest. They said the appointment was unnecessary and was an overreaction. They were concerned about the reputational damage that might flow from the appointment of 333 because of the association with KordaMentha. Mr Pavisich's evidence, which I accept, was as follows:[346]
[Mr Saraceni and Mr Clohessy] spoke with raised voices saying words to the effect of '[the appointment is] unnecessary' and 'it is an overreaction'. They were very animated and abusive. Luke Saraceni said words to the effect 'I am going to throw the keys across the table. I am going to go and sit on a beach and watch you guys finish the building. I will spend the rest of my money suing you' and 'if you send 333 to level 50, I'll throw them out of the window'.
  1. Later on 25 September 2009 Bankwest gave notice that if the Cost Overrun was not paid in full on 25 September 2009 this would result in a breach of the Project undertaking specified in cl 15.2(9) of the Facility Agreement and an Event of Default.
  2. On 28 September 2009 Mr Clohessy sent a lengthy email to Mr Jon Sutton (managing director of Bankwest) and Mr Peter Barnes of CBA.[347] In that email Mr Clohessy complained about Bankwest's management of the MOFA and in particular about the second Cost Overrun. Mr Clohessy complained a 'breach notice' had been given before Westgem had the opportunity to provide Mr Sanders with details of credits due to Westgem. He also complained about the appointment of 333 and the association with KordaMentha and the potential that the appointment would damage 'the Project's reputation'. Mr Clohessy also complained about Bankwest's letter of 25 September 2009. Mr Clohessy provided the following summary of Westgem's position:[348]
We understand the size of this project in the current financial environment places it firmly in the spotlight, in addition Cost Overruns and speculation re the Builder's financial position make for a very nervous financier. Further we expect scrutiny and welcome constructive participation by other stakeholders in the project. I think this has been clearly demonstrated by the good working relationship which has quickly developed with Quentin's team. There are good reasons why this relationship is working and to the previous one under Bankwest control was not, namely we acknowledge their expertise and experience and perhaps more importantly I think they have opted for a cooperative approach rather than the previous adversarial one. Importantly the lines of communication are clear and the number of individuals involved small.

Unfortunately on the lending side it is the complete reverse, we are dealing with 2 lenders one of which clearly would prefer not to be in the deal and with the CBA takeover of Bankwest adding an additional level of credit overseeing Bankwest. Effectively we now have the boards of 3 banks, 3 credit departments and innumerable parties having input into every aspect of the project funding. We also have this absurd "Chinese wall" mentality between the bank as tenant and lender which makes communication even more difficult where effectively every ripple becomes a wave and every wave a tsunami.

Just one example of this is the first 'Cost Overrun', the fact is most of the original increase was due to two things, first increased costs to accommodate requests for variations from the tenant and second changes made by Luke to improve the building. The balance was as a direct result of Salta's refusal to assist to obtain cost savings as promised on items which had not been finalised when construction commenced. This was done in an effort to progress the project and with Bankwest's full knowledge. Notwithstanding this the word Cost Overrun sends shockwaves throughout the three banks because the communication is just not working. I might also add of the $13m additional cost, $6.5m in cash was injected by the borrowers and they provided an additional $16m security for the balance of the $6.5m lent by Bankwest. Strangely whenever the subject comes up your credit people act as if the bank had to inject additional funds. This is not to say we did not appreciate the cooperation to make it happen though.
  1. Mr Clohessy went on to set out the concerns held by Mr Saraceni and Mr Pourzand that their reputation, and the reputation of the Project, would be damaged by the appointment of an investigating accountant with a reputation for dealing with distressed real estate assets. Mr Clohessy concluded his email with the following remarks:
At the very time when Luke and his staff need to be focused intently on delivery of this project for the bank as the tenant the proposal to engage a full blown IA by a party whose involvement can only be seen as damaging in our view is clearly not in the interest of all parties.

To complete this project we do need the Banks assistance but in a cooperative constructive manner which we believe is now happening on the tenancy side but not on the lending side.

Luke believes he has acted honourably and fairly with the Bank, when there was pressure on to get the AFL signed Luke made it happen despite the fact we believe BOSI were acting unconscionably at the time. When Salta attempted to screw the Bank on the IFO, Luke against direct instructions from Bankwest staff to issue a cost plus contract to Salta refused because he knew it had the potential to severely damage the Bank both financially and with respect to timing. Luke's staff continues to assist the Bank in relation to the Bank now undertaking the IFO beyond what is contractually required.

We have undertaken to continue discussions in good faith on Tuesday with Alan Pavasich and Peter Deans but believe the disputed issue of Cost Overruns is being used to engineer a default under the MOFA and that if litigation and damages are to be avoided it is imperative to discuss these issues with you personally prior to that time.

October 2009

Westgem's Financial Statement No 7.2

  1. On 1 October 2009 Westgem prepared Financial Statement No 7.2.[349] It contained a projected contract sum of $250,052,313. This sum included an allowance for contingencies of $5 million. Financial Statement No 7.1 was not provided to the Finance Parties nor to Mr Gowdie whose role I describe in the next paragraph.

Mr Gowdie appointed and commences review

  1. 333 retained Mr John Gowdie as a consultant to assist in reviewing the Project. Mr Gowdie was an experienced construction and project manager. He was a director and the principal of Gowdie Management Group Pty Ltd, a company that had a staff of 17 and provided a range of programme, project management and construction services to the development, engineering and construction industry. In early October 2009 Mr Gowdie met with Mr Luke Saraceni and Mr Frank Saraceni and other members of Westgem/Saracen Properties' team working on the Project. Mr Gowdie was provided with a work space within Saracen Properties' office.
  2. Commencing in early October 2009 Mr Gowdie undertook a detailed review of the Project. This involved an analysis of a substantial volume of documentary material, detailed discussions with Mr Frank Saraceni, Mr Simpson, Mr Artelaris, Mr Merson and Mr Carmichael and others involved with Westgem and Saracen Properties and attendance on site. The steps taken by Mr Gowdie for the purposes of his review were set out in detail in his witness statement.[350] His evidence as to the work undertaken by him was not challenged in cross-examination and I accept it. It is on the basis of this evidence that I make the finding that Mr Gowdie undertook a detailed review of the Project. It is unnecessary to set out each step in the review process.
  3. Mr Gowdie was a substantial contributor to reports produced by 333 for the Financiers to which I refer in later paragraphs. Mr Gowdie was primarily responsible for the Cost to Complete analysis incorporated in the 333 reports.

Financiers' 2 October 2009 proposal and negotiations

  1. On 2 October 2009 Mr Nagle sent a draft letter to Mr Saraceni and Mr Clohessy setting out a proposal that would enable the Project to continue with the support of the Financiers.[351] In summary the proposal was as follows:

(a) Westgem would be required to continue with work on the Project in accordance with the Salta Building Contract;

(b) Westgem would be required to cooperate with 333;

(c) additional guarantees for $50 million would be required;

(d) additional securities with a value of at least $50 million would be required; and

(e) the Cost Overrun would be required to be remedied by 31 January 2010.

  1. On 2 October 2009 Mr Pavisich spoke separately to Mr Saraceni and Mr Clohessy. Each of them told Mr Pavisich that Mr Saraceni was 'comfortable to move forward' on the basis of the proposal set out in the letter of 2 October 2009 but Mr Pourzand was not because he was not prepared to provide an additional guarantee up to $50 million.[352]
  2. On 4 October 2009 emails were exchanged between Mr Clohessy and Mr Pavisich and Mr Nagle. In Mr Clohessy's email to Mr Nagle and Mr Pavisich, he wrote:[353]
Steve and Alan

I need some clarification.

I have not heard from Luke's solicitors yet and as you know Luke has advised Alan he and Hossean have only agreed to consider the bank's proposed terms if the guarantees given are limited to the amount of the banks QS's stated Cost Overrun i.e. $17m.

There are a couple of other points I would like to make.

Luke does not accept a breach has occurred, his position is if and when the cost to complete is determined by your QS after the investigation by [333] and it is not paid by the borrower as per the MOFA a breach will have occurred.

The letter suggests you can take seconds over all the borrower's assets currently encumbered to CBA and Bankwest, I was of the understanding it was to be over assets which gave you an additional $50m not all per se (albeit this might be all but not necessarily)

Alan and I discussed the banks would reserve the right to complete a review of all terms of the MOFA terms upon the completion of the report by 333 however the letter indicates this is regardless of the outcome.

Surely the report would have to indicate some breach. Are you suggesting just accepting the terms of your proposal gives the banks that right.

Please note these are my thoughts and not the borrower's response.
  1. Mr Pavisich responded to Mr Clohessy's email by an email of his in which he wrote:[354]
Hi Mark

In response to your email.

- I have not heard from Luke since Friday night where Luke advised he would meet with Hossean on Sunday to see if he could get an agreed way forward on the indicative terms of the banks letter. Luke confirmed while he believed Hossean could agree to the other terms the additional $50m gtee was not acceptable. We need confirmation one way or the other if the proposed way forward is acceptable to both sponsors. I asked Luke if Hossean would not move forward as per our letter did he think that an additional $17m gtee supported by $50m net equity in second mortgages would be acceptable. I advised this variation has not been discussed with anyone internally or with BOSI and may not even be possible so the current letter should also be considered as possibly the bank's final position. Let me know if there is one change to the indicative terms is acceptable so that I can discuss it with both banks.

- I think Luke (and Hossean) should get legal advice re the breach. Luke has acknowledged that there is a cost over-run he just questions the amount. The Bank's QS confirmed a cost over-run and the amount was requested from the Borrower within the required 5 days. The indicative terms outline is a way forward where the Bank agrees to reserve rights pending a IA review and what is required to make the next progress payment.

- Trying to keep this within the group was our thinking for the seconds from CBA/Bankwest mtge properties but do not need all of them if we get to $50m net equity with some of the properties.

- The Banks have the ability now to take action under the documents but deem it more appropriate to keep the project moving forward while getting a better understanding of all issues through the IA review before putting forward what is required. As the letter advises we are reserving our rights until certain things occur, including the outcome of the IA review.

Mark I would like to find a way forward but as I have confirmed BOSI will not seek credit approval until in principal [sic] agreement is reached.

Please let me know if Luke & Hossean are prepared to move forward on the indicative terms as per the letter issued. If not but are prepared to subject to the same terms but reducing the J & S [guarantee] to $17m then I can discuss this internally and with BOSI to determine if it will be acceptable.

Please call me on mobile if you need clarification of any of the above.
  1. Mr Pavisich gave evidence,[355] which I accept, to the effect that it appeared to him that Mr Saraceni was 'chopping and changing his position as to whether there was or was not a Cost Overrun' and that Mr Saraceni had said to him that there was a Cost Overrun but it was not $17 million. Mr Pavisich said that he made the suggestion that Mr Saraceni obtain legal advice on the Cost Overrun issue because he wanted to make sure that the message got through to him that the MOFA contained a process for determining Cost Overruns and there were potentially serious consequences if the Cost Overrun was not remedied. Mr Pavisich also gave evidence, which I accept, to the effect that he had a conversation with Mr Saraceni or Mr Clohessy at around this time in which he said to them words to the effect that 'if you do not find a resolution to the Cost Overrun, regardless of the amount, you run the risk of losing control of the Project' and 'you can keep arguing about the second Cost Overrun but if it keeps going on this way and we may need to appoint receivers to get the building completed. I am here to help you, but if the banks appoint, it is out of my hands'.[356]

Westgem counter-proposal 5 October 2009

  1. On 5 October 2009 Mr Clohessy sent an email to Mr Pavisich in which he put a counter-proposal to that contained in the Facility Agent's letter of 2 October 2009. Mr Clohessy stated:[357]
Luke advises that following further discussions with Hossean their position is as follows;

They believe a Cost Overrun has not been reasonable [sic] determined under the MOFA given the estimates do not include credits due to the borrower.

Notwithstanding they will agree to provide additional guarantees of $17M together with additional second mortgages to the value of 50 million over properties to be agreed. The determined Cost Overrun if any to be repaid by January 31st 2010. In addition they agreed to provide Real Estate 333 all reasonable information as per our discussions to assist in the review requested by the Banks.
  1. Mr Clohessy's email of 5 October 2009 repeated what had been said to the Finance Parties on Westgem's behalf on many occasions since 18 September 2009 and was repeated on subsequent occasions, that was, that Westgem did not accept the second Cost Overrun in the amount of $17 million had occurred because 'credits' had not been taken into account.

Financiers' revised 9 October 2009 proposal

  1. On 9 October 2009 Bankwest sent a further letter to Westgem setting out a revised proposal.[358] The significant revision was that the additional guarantees were to be joint and several guarantees limited to $17 million as opposed to $50 million. The additional securities to be provided were, however, to have an aggregate net equity of at least $50 million. The Financiers referred to this letter as the 'reservation of rights letter'.
  2. Mr McDonald of BOSI sought approval for entry into an agreement in terms of Bankwest's letter dated 9 October 2009 by completing a document entitled 'Request for Variation from Terms of Sanction' that was addressed to 'Lloyds International Credit Sanctioning'. In a section of this document entitled 'Proposal' Mr McDonald set out his view of the proposed agreement. It provides an insight as to how the Financiers viewed the negotiations with Westgem at that date.[359]
It is the Financier's view that that we must keep the Builder on site and make immediate payment for the amount which has been currently certified ($10,884,40), pending the outcome of the adjudication which may require the balance of the Builder's claim to also be paid. In consideration of the potential Cost Overrun identified, we have negotiated the following position with Westgem that needs to be satisfied before processing the current payment:
  1. Each guarantor under the facility grants a further guarantee in favour of the Security Trustee, limited to $17,000,000 (this is in addition to the existing guarantees which are limited to $40,000,000 plus Cost Overruns relating to the project).
  2. Each transaction party undertakes to provide additional second mortgage security over property owned by the transaction parties to a value of $50,000,000 (determined by the Financiers in their sole discretion), by 31 October 2009.
  3. The actual Cost Overrun (if any) determined by 333 Real Estate will be final and any amount identified is to be paid from the Borrower's resources by no later than 31 January 2010. Assuming compliance with this requirement, the additional guarantee support (including the collateral security) will then be released.
Therefore, subject to the provisions outlined above, we are looking to waive the cost to complete test and continue funding works completed as certified by the Financiers' QS, or as directed under any adjudication.
  1. On 13 October 2009 Mr Clohessy told the Financiers' representatives that Mr Saraceni and Mr Pourzand would not accept the terms set out in the Facility Agent's letter of 9 October 2009.[360]

Ongoing negotiations

  1. Later on 13 October 2009 there was a meeting between Mr Saraceni, Mr Pourzand, Mr Clohessy, Mr Leber, Mr Nagle and Mr Pavisich. Based on Mr Pavisich's evidence, whose recollection had been refreshed by reference to a contemporaneous file note prepared by Mr Nagle and to which Mr Pavisich, had made some amendments,[361] I find that at the meeting Mr Saraceni and Mr Pourzand repeated their contention that there had not been a Cost Overrun in the amount determined by Mr Sanders. They said that Westgem's quantity surveyors estimated that the project construction cost was $248 million and that on this basis a Cost Overrun of $5 million was evident. Mr Saraceni said that the estimate of $248 million included provision for liquidated damages. He objected to the Financiers' cost estimate of $260 million on the basis that it did not take into account contract 'credits'. Mr Saraceni and Mr Pourzand said that they would contribute $5 million towards funding that week.[362] Mr Saraceni and Mr Pourzand said that they disagreed with the scope of the work to be undertaken by the investigating accountant. Mr Pourzand said that he did not accept the terms that had been offered by the Financiers and described them as offensive and suggested that if his position was unacceptable then the financiers should appoint receivers immediately. Mr Saraceni said that Westgem would make its cost estimates available for review and consideration by the Financiers' quantity surveyor. No agreement was reached at this meeting but the parties agreed to consider a position that involved the following elements:

(a) Westgem would make available its quantity surveyors' information to the Financiers' quantity surveyors to enable them to undertake a further review of the cost to complete.

(b) Mr Saraceni and Mr Pourzand would contribute $5 million immediately by way of $3.4 million cash contribution and a contribution of $1.6 million by way of a return of the bank guarantee.

(c) Mr Saraceni and Mr Pourzand would abide by the revised cost to complete figure advised by the Financiers' quantity surveyors.

(d) should the Financiers' cost to complete estimate exceed $5 million, the guarantors would provide additional guarantees and second ranking mortgage securities to cover the Cost Overrun short fall by three times by no later than 31 October 2009.

(e) Mr Saraceni and Mr Pourzand would undertake to fund any Cost Overrun by 31 January 2010.

(f) The Financiers would release the additional securities provided upon payment of the Cost Overrun.

Decision to apply default interest rate

  1. On 15 October 2009 a meeting of Bankwest's Executive Credit Committee was held. At that meeting the members of the committee received an oral report from Mr Nagle, Mr Nathan, Mr Pavisich and Mr Wlossak about Westgem. The minutes of the meeting recorded:[363]
ECC members noted despite [Westgem's] reluctance to agree negotiated terms the Banks had little choice but to agree to make the builder payments to keep the project moving forward. It was also noted that charging of default interest should focus [Westgem's] attention on finding an agreed way forward.
  1. On 16 October 2009 Bankwest sent a letter to Westgem giving notice that the default rate of interest would be applied with effect from 25 September 2009.[364]

Westgem agree in principle to accept 333 determination

  1. On 16 October 2009 Mr Clohessy sent a memorandum to Mr Leber, Mr Pavisich and Mr Nagle in which he confirmed that Westgem maintained that no Cost Overrun had been reasonably determined in accordance with the terms of the MOFA and proposed terms to approach the resolution of the Cost Overrun issue. Among the points made on Westgem's behalf Mr Clohessy stated:[365]
As you are aware from both Westgem's written correspondence and our various discussions Westgem rejects the Lender's stated position that it is in breach of the MOFA dated 23 April 2008. It remains their position that no Cost Overrun has been reasonably determined pursuant to clause 17.22. The Bank's QS in his report of 14th of September 2009 states that the cost to complete of $260 million 'excludes credits proposed by Saracen but not yet received.'

Westgem is now in a position to present those credits to the Bank's QS for verification. If the QS is in agreement with Westgem's cost to complete or determines a higher figure the Cost Overrun will be paid within 5 working days and or they will request the bank considers alternative arrangements satisfactory to all parties. In the interim the bank has the sponsor's personal guarantees for Cost Overruns which should provide the lenders sufficient comfort until this issue is sorted amicably.

In anticipation of the lenders being of the view that this position varies from our advice to Alan Pavisich on 5 October 2009 which was negotiated in good faith, we would say that the Lenders' proposed agreement of 9 October 2009 goes significantly beyond what was contemplated in our various discussions. Westgem also acknowledges that the proposal put forward by Alan was done so by him on a best endeavours basis on his part. Accordingly the position now put forward by the lenders is not acceptable. Notwithstanding this Westgem has fully cooperated with the Banks' IA's in relation to determining the cost to complete and will do so until the issue is resolved.

In relation to the Cost Overrun previously determined in July 2008 of $13.5 the sponsors paid $6.5m by way of cash contribution and Bankwest advanced $6.5m as a short-term bridging facility with principle payments spread over a 9 month period with the final payment in May 2010. They are now in a position to make early repayment and thank the Bank or its indulgence in this regard.

...

In Westgem's view the issue of cost to complete and the builder's actions are related issues but the latter is of significantly greater urgency, if I have learnt one thing in 20 years financing construction projects the developer and the lender need united relationship when dealing with the builder. Salta have clearly attempted to damage this relationship and turned the building contract into a cost plus contract and this has intensified since their loss of the IFO work. Both the banks and Westgem's legal and professional resources need to be focused on achieving the best outcome under the building contract and side deed. Clearly bringing the builder to account has a significant impact on the issue of cost to complete. (emphasis supplied)
  1. I find that by 16 October 2009 Westgem had agreed in principle that it would accept the cost to complete determination made by 333, when it was made, and if on the basis of that determination there was a Cost Overrun, then it would pay the Cost Overrun within 5 days or negotiate alternative arrangements with the Financiers. The basis for this finding is Mr Clohessy's email of 16 October 2009 and in particular the passage emphasised in the quoted paragraphs of the email set out above. The context in which Mr Clohessy sent his email included the appointment of 333 and the review of the Project that was then being undertaken by Mr Gowdie and read in that context Mr Clohessy's reference to the 'Bank's QS' was a reference to Mr Gowdie.

Westgem seeks legal advice

  1. On 23 October 2009 Mr Clohessy sent an email to Mr Saraceni and Mr Pourzand suggesting that they obtain legal advice from the law firm Lavan Legal regarding Bankwest's default and penalty notice. Mr Clohessy commented that, '... we need to fast track the determination of the cost to complete and resolve the current impasse'.[366] Subsequently Mr Clohessy provided various relevant documents to Mr Stevens, a partner of Lavan Legal to enable him to provide advice.

Westgem's October 2009 drawdown request

  1. On 23 and 28 October 2009 Westgem requested a drawing to pay Salta $14,040,047 plus GST and consultants' costs of $415,660.62 plus GST. On 29 October 2009 Bankwest made available a drawing of $14,040,047 plus GST to pay Salta.
  2. On 26 October 2009 Westgem requested that the Financiers pay 'soft costs' of $415,000. This request was refused. Mr McDonald stated in an email to Mr Nagle that BOSI would not fund anything other than construction costs while a Costs Overrun subsisted.[367] In an email from Mr Pavisich to Mr McDonald sent on 27 October 2009, Mr Pavisich observed:[368]
... [Westgem] must realise that their failure to deal with the default has consequences for our funding of the project. Hopefully the next cost to complete report will allow common sense to prevail and get the customer back to the table.

If the non-funding of soft costs begins to affect the completion of the project then we need to have another look.

Westgem's updated costs summary

  1. On 26 October 2009 Mr Simpson sent an updated project costs summary to Mr Sanders that estimated the construction costs to be $250,452,362.[369] This summary included a deduction of approximately $4.2 million as a negative variation for the tunnel but included an allowance for the tunnel in the sum of $4.3 million as part of a total allowance for risk in the sum of $12.1 million. The summary also included a figure for 'Contingency' in the amount of $5 million. On the basis of the figures contained in Mr Simpson's updated project costs summary, the estimated construction costs had increased by approximately $7 million since 4 September 2009 when Mr Frank Saraceni had provided Mr Sanders and Mr Nagle with forecast contract sum of $243 million. In his evidence Mr Gowdie referred to a calculation shown to him by Mr Merson of certain 'risk items' that Mr Gowdie referred to as the 'Merson Cost to Complete Risk Analysis'. Mr Gowdie said that the risk items after deduction of 'credits' totalled $12.1 million. I infer from the allowances for risk of $12.1 million made in both the updated project costs summary sent by Mr Simpson to Mr Sanders and the 'Merson Cost to Complete Risk Analysis' that the latter document was an iteration of the former if not the same document.

Mr Sanders provides advice on credits

  1. On 29 October 2009 Mr Sanders sent a letter to the Financiers stating that his forecast total construction cost remained at $260 million as advised on 14 September 2009 as CSAs 17, 22 and 23 had removed work from the scope of Salta's contract but had not effected project savings as the works specified in the CSAs 'will/maybe required at a later date ...'.[370]

CBA demands repayment of Pakwest facility

  1. On 30 October 2009 CBA gave notice to Pakwest requiring immediate repayment of its cash advance facility provided pursuant to a Facility Agreement dated 1 August 2007.[371] This facility did not relate to Raine Square. The amount owing under the facility was in the realm of $18 million. CBA offered to renew the facility and set out the terms of the offer which it required be accepted by 6 November 2009. Mr Clohessy protested in strong terms in an email to Mr Pavisich, Mr Nagle and Mr Leber.[372]

November 2009

333 draft 4 November 2009 Cost to Complete summary

  1. On 4 November 2009, 333 provided Mr Nagle with a draft of a table in which Mr Gowdie had summarised the component elements of the Cost to Complete calculations of RBB, Westgem and Salta and compared them with his own analysis.[373] At that stage Mr Gowdie's forecast of the construction costs was $262,435,939. In relation to Contract Sum Adjustment 22 and 23 Mr Gowdie noted, 'These items have been fully deducted by the Superintendent from the Salta contract, however work is still required to complete these items or Salta are to submit a credit variation for the work. The risk is that Salta will have a very different view of the applicable credit to the work.'[374]

Discussions and investigations about credits

  1. On 4 November 2009 Mr Gowdie sent an email to Mr Frank Saraceni and other members of the Saracen Properties staff stating that he would like to discuss a number of items.[375] These included the provisional sum allowance for the tunnel, the design and costing of the Pavilion and CSA 22 and 23. In relation to CSA 22 and 23 Mr Gowdie observed, 'while these are deducts from Salta some of this work still needs to be undertaken and you are also waiting for Salta's view of the credit on these items. I would like to discuss'.[376] Mr Gowdie commented, 'I know we have discussed some of this before and some of it at length, however I need to reinforce my view in some areas'.
  2. Mr Frank Saraceni sent a copy of Mr Gowdie's email to Mr Carmichael. In a responsive email Mr Carmichael expressed the following view:[377]
Obviously John is attacking any perceived weakness from our position and has taken note of the fracas on site with Gallaghers as a point in question, adding fuel to the fire of Salta's statement regarding our management of the post contract situation.

Please do not leave Paul or Rob on their own with John at any time. I have already witnessed accounts whether they should have kept their mouths shut altogether and said nothing. They are liable to say anything which may shoot us in both feet. John is no fool and despite his laid-back and laissez-faire appearance he knows what he is doing and what the bank has briefed him to do - thoroughly!!

(The fracas on site with Gallaghers was a reference to a dispute between Salta and its concreting subcontractor Gallaghers that had resulted in Gallaghers withdrawing its labour from site. Paul was Mr Paul Simpson and Rob was Mr Rob Merson.)

  1. Mr Carmichael concluded his email with this statement:
I apologise if this appears to be somewhat longwinded but in order for John to give the Bank some comfort he has to be told the absolute truth, not deals being done on site as he has already. We have nothing to fear and we must be transparent in everything we tell him otherwise we will be over $260m before you know it or even more ($265m). Seems to ring a bell!!!
  1. On 5 November 2009 Mr Gowdie met with Mr Frank Saraceni, Mr Artelaris, Mr Merson and Mr Simpson. Mr Gowdie's evidence of what was discussed at that meeting, which I accept, was as follows:[378]

(a) Mr Gowdie raised the topic of the tunnel with Mr Frank Saraceni and his colleagues. Mr Gowdie was told that all work required to complete the tunnel had been allowed for in a provisional sum of $4.3 million and that Westgem had allowed for a contingency of $500,000. He was told the design for the tunnel was substantially complete, that there was a lump sum contract for the construction of the tunnel was expected to commence in March 2010. He was told that the necessary survey work had been completed and that there was an access agreement with the Public Transport Authority and that the Public Transport Authority had agreed to the design. Mr Gowdie asked for copies of the lump sum contract for the construction of the tunnel and for copies of the relevant regulatory approvals but these were not provided to him. Mr Gowdie's evidence, which I accept, was that he subsequently discovered that the design to the tunnel was not complete and that a survey had not been undertaken.

(b) There was a discussion of credits that Westgem maintained were due in its favour from Salta. Mr Gowdie was not given a detailed explanation of those credits nor anything to substantiate the amounts claimed to be due to Westgem.

  1. I interpolate that what was said to Mr Gowdie about the cost of the tunnel was inconsistent with the estimated cost of the tunnel contained in Financial Statement No 6 - $7 million.
  2. On 10 November 2009 Mr Clohessy sent an email to Mr Nagle, Mr Pavisich and Mr Leber recording his understanding that RBB and 333 had assessed the Cost to Complete at $260 million and $262 million respectively but that neither assessment took into account the credits Mr Frank Saraceni maintained should be taken into account or liquidated damages and asked for clarification as to the position.[379]
  3. On 10 November 2009 Mr Nagle sent an email to Mr Alex Frankl regarding the construction of the Podium and asked whether the cost of the construction of the Podium remained Westgem's obligation or whether Bankwest as tenant had adopted the financial commitment.[380] Mr Nagle did not receive a substantive response until 24 November 2009 when Mr Frankl sent Mr Nagle an email stating:[381]
We are working through this issue and it is tracked in our weekly meetings with Westgem and Salta. There is an acknowledgement from Westgem and Salta respectively that a credit is due against this deduction in their scope of work. We are not in a position to advise the exact split in dollars attributable to Westgem and Bankwest as tenant at this time.
  1. On 10 November 2009 Mr Frank Saraceni sent a letter to Mr Sanders and enclosed a 'Credits List' that itemised 'Savings/deductions to $260M budget' (the list included the Podium 'shell & core' referred to in Contract Sum Adjustment 22 but did not include the blinds).[382] The total allowed by Mr Saraceni in respect of items of work was $7,280,494 to which he had added liquidated damages of $2.1 million. Implicit in Mr Saraceni's calculations was an acceptance of the proposition that the cost to complete exclusive of credits that he maintained should be allowed in respect of items of work, as distinct from the liquidated damages, was approximately $252.7 million. On the basis of this figure there would have been a Cost Overrun of $9.3 million.
  2. On 11 November 2009 Mr Nathan sent an email to Mr Nagle and Mr Pavisich asking, in effect, whether Bankwest 'knew' whether the credits Mr Frank Saraceni said should be taken into account were legitimate matters requiring a reduction to the cost to complete and whether they had been considered by RBB in arriving at the $260 million construction cost forecast.[383]
  3. On 11 November 2009 Mr Frank Saraceni sent Mr Gowdie an email to which he attached the list entitled 'Credits List Raine Square savings/deductions to $260M budget'[384] sent to Mr Sanders the previous day. Mr Gowdie's evidence, which I accept, was that this was the first occasion on which he had received any documents identifying the credits claimed by Westgem.[385] Mr Gowdie described the credits as 'very high level and [lacking] any detail'.
  4. Shortly after receiving the list Mr Gowdie met Mr Frank Saraceni and other members of the Saracen Properties team. Mr Gowdie told Mr Frank Saraceni that he had concerns about the 'credits'. These included: that the credits related to items of work that would be removed from Salta's scope of work but which still needed to be undertaken by another builder to achieve completion so that although the items were potentially credits against work to be performed by Salta they were not credits for the Project and could not be treated as deductions to the cost to complete; he was concerned that the credits had already been taken into account in the Merson Cost to Complete Risk Analysis and he, Mr Gowdie, did not want to 'double-count' any allowances for credits; and, to the extent to which the credits related to items that remained within Salta's scope of works, he had not been provided with evidence that substantiated that the credits had been agreed by Salta.[386] Mr Gowdie was, however, prepared to make allowances for some of the credits, in particular in respect of the cost of the Pavilion.
  5. On 12 November 2009 Mr Carmichael sent an email to Mr Gowdie in which he stated that:[387]
Independently, I believe that at least $10.00m can be reduced from your bottom line without any difficulty and believe me by the time I am through checking their paperwork, they might suddenly wake up and realise what fools they have been.
  1. On 20 November 2009 Mr Frank Saraceni sent a letter to Mr Gowdie in which he referred to his recent conversations with Mr Gowdie and stated that 'not all credits have been formally forwarded and discussed to date'.[388] Mr Frank Saraceni added:[389]
The credits as listed in my recent correspondence dated 10 November 2000 were only the credits as were known at the time that the RBB estimate of $260M issued on 14 September 2009. I acknowledge that all parties were also at that time and since being distracted and placed under much unnecessary pressure by some major contractual and cash flow control issues with respect to the Builder's unjustified and aggressive contractual manoeuvrings. We however were always concerned that bona fide credits were not been given due and fair consideration.

We also confirm that since that time we have been pursuing numerous other credits due under the contract and attach a further list with estimates of values. The contractual status of these credits is also sound and have not been formally issued as this process has similarly being interrupted as noted above. Further some of these credits are still being reviewed or finalised through the overall value estimates are a product of our investigations to date and we believe sufficiently accurate.
  1. The list of credits attached to the letter of 20 November 2009 amounted to $4,200,000. None of the credits were included in Mr Frank Saraceni's 10 November 2009 list. The credits included the 'IFO Co‑ordination fee' of $1.8 million. Mr Gowdie's evidence, that I accept, was that he had been told by Mr Frank Saraceni that Westgem would honour the payment to Salta of $1.8 million in respect of the IFO fee and Westgem had included it in its own cost to complete calculation.
  2. Mr Gowdie was not prepared to make any allowance against the cost to complete for the credits in the list attached to Mr Frank Saraceni's letter of 20 November 2009. He considered that the 'credits' were 'figures on a page' with no backup or substantiation. Mr Gowdie told Mr Frank Saraceni that the credits had not been substantiated.[390]
  3. Mr Gowdie had also determined that he was not going to allow a credit against the construction costs for liquidated damages as the recovery of liquidated damages was too far in the future and might depend upon the outcome of protracted litigation and were very uncertain. He excluded from his analysis of the cost to complete all amounts - whether payable to Salta as delay costs or recoverable from them in the form of liquidated damages - which would only crystallise after practical completion and which would likely be resolved only after litigation or some other form of dispute resolution.[391]
  4. My impression of Westgem's reliance on 'credits' that should have been taken into account in calculating the Cost to Complete is that it involved generalised assertions that, with the very limited exception of the Podium credit ultimately allowed by Mr Gowdie, did not withstand detailed scrutiny. The 'credits' were a smokescreen used by Westgem to obscure increases in the construction cost forecasts of which Westgem was aware, or at least which it was concerned would occur.

333's forecast cost to complete

  1. On 13 November 2009 333 sent a formal report to the Financiers in relation to the Project. The report contained a table based on the 4 November 2009 draft Cost to Complete analysis containing Mr Gowdie's revised calculation of the cost to complete being $260.93 million. In relation to Contract Sum Adjustment 22 the following note was included in the report:[392]
CSA 22 contains a $1.7m deduction in relation to the Lvl 1 Podium to suit Tenant requests. The deduction is based on a figure produced by Rider Levett Bucknall. This figure is yet to be agreed with the contractor, therefore the full amount is not being credited. The tenant may well require a contribution to the fit out due to the works credited and this will be a negotiation between Westgem and the tenant, however this will be out [sic] part of the non integrated fit out which does not form part of our brief. The supply and installation of blinds - while it has been taken from the Contractor's scope, the item still needs to be purchased and installed.

18 November 2009 proposal

  1. On 18 November 2009 Bankwest sent Westgem a further revision of the letter first prepared on 2 October 2009 and revised on 9 October 2009 setting out the terms upon which the Financiers were prepared to resolve the issue of the second Cost Overrun.[393] I reproduce the provisions of the 18 November 2009 letter on which Westgem's case focusses later in these reasons. The principal commercial terms proposed in the letter may be summarised as follows:

(a) Westgem would be obliged to co-operate with 333's review.

(b) The guarantors would be obliged to acknowledge the occurrence of both the first Cost Overrun and the second Cost Overrun.

(c) Westgem would procure the provision of additional securities in favour of the Financiers with a net equity of $50 million by 14 December 2009.

(d) Westgem would not permit Cost Overruns to exceed $17 million and Westgem would pay the Cost Overruns by 31 January 2010.

(e) Upon payment of the Cost Overrun the Financiers would release the additional securities.

(f) The Financiers would be entitled to review the terms of the MOFA and propose amendments to it after receiving a report from 333, and if the amended terms could not be agreed within five business days, give not less than 60 days notice requiring Westgem to repay the money owing under the MOFA.

Although not a term proposed in the letter of 18 November 2009 the letter recorded that if an executed copy of the letter was not signed and returned by no later than 23 November 2009 that would constitute an Event of Default.

Westgem seeks legal advice

  1. On receipt of Bankwest's letter of 18 November 2009 Mr Clohessy sent an email to Mr Saraceni and Mr Pourzand suggesting that it was an opportune time to discuss the 'issue' - by which I infer he meant the second Cost Overrun issue - with Mr Stevens of Lavan Legal - the firm of lawyers whom Mr Clohessy had consulted.
  2. On 24 November 2009 Mr Clohessy sent an email to Mr Stevens attaching a copy of Bankwest's letter of 18 November 2009 and asking whether it would be possible to meet with Mr Stevens the following afternoon.[394]

Bankwest's concern about lack of response from Westgem

  1. On 24 November 2009 Mr Nathan sent an email to Mr Pavisich in which he recorded that the Financiers had required a response to the 18 November 2009 proposal by 23 November 2009. Mr Nathan went on to observe:[395]
... and as such technically we can exercise our rights any time now. Steve indicated that in his discussions with Mark Clohessy he is of the view that the conditions will be accepted albeit they will try to drag out the time frames. If you want Steve and myself to go see Clohessy/Saraceni to rattle the cage a bit let me know.

Westgem's response to Financiers' 18 November 2009 proposal

  1. On 24 November 2009 Mr Clohessy spoke to Mr Nagle and told him that Mr Luke Saraceni and Mr Pourzand would agree the position and put forward the additional mortgage security but that they would challenge the Financiers' right to charge default interest and fees.[396]
  2. Later on 24 November 2009 Mr Clohessy sent an email to Mr Nagle and Mr Luke Saraceni in which he stated:[397]
Steve my apologies for not responding sooner, as you know Luke was in China until Friday last week and so we have had limited time to meet since his return other than to meet our undertakings to 333 Real Estate in regards to cost to complete and financial matters. I meet with both Luke and Hossean today and will provide a response no later than tomorrow. Both Luke and Hossean are committed to providing the additional security as requested. There are a couple of issues we would like to raise with the Bank's letter however this will not delay provision of the additional security.
  1. On 25 November 2009 Mr Clohessy had a discussion with Mr Pavisich. I accept Mr Pavisich's evidence about this discussion.[398] It was to the effect that he and Mr Clohessy talked about some minor queries Mr Clohessy had in relation to the terms of the 18 November 2009 letter. In addition Mr Clohessy raised two issues. First he contended that Westgem was not in default when the second Cost Overrun was determined because Mr Sanders did not take into account credits due to Westgem. Mr Pavisich responded to this contention by pointing out that Mr Saraceni had acknowledged that Westgem was in default though not in the amount determined by the Facility Agent. In the course of cross‑examination Mr Pavisich explained that the discussion about the existence of a default took place in the context of Mr Clohessy seeking to persuade the Financiers that default interest should not have been applied when it was.[399] Mr Clohessy's second issue was the amendment fee that the Financiers proposed to charge. Mr Pavisich said the Financiers could raise the margin or line fees if that was Westgem's preferred 'way to go'. Mr Clohessy said that Westgem was keen to remedy the default and would return the 18 November 2009 letter the following day.
  2. On 26 November 2009, 333 produced a further report for the Financiers. The cost to complete forecast contained in this report was the same as that contained in the 13 November 2009 report, that is, $260.93 million.
  3. On 26 November 2009 Mr Clohessy sent a further email to Mr Nagle and Mr Saraceni.[400] Before sending the email to Mr Nagle, Mr Clohessy had sent a draft of it to Mr Saraceni and Mr Pourzand and by way of an explanation of the proposed email stated:[401]
Luke and Hossean please see my draft response to Steve Nagle, it is a very weak attempt to keep our options open to later challenge the imposition of penalty interest and the additional 500k fee. I am concerned that to argue at this point or refuse to sign may put you at risk of them taking harsher action. Please let me know urgently are you wish to proceed as we are past their deadline for acceptance.
  1. I infer that Mr Saraceni and Mr Pourzand approved the terms of Mr Clohessy's email to Mr Nagle because on 26 November 2009 Mr Clohessy sent an email to Mr Nagle in the terms of the draft sent to Mr Saraceni and Mr Pourzand in which he stated:[402]
Steve

As mentioned in my previous email the borrowers acknowledge that both the bank's QS and 333 Real Estate have now completed their respective reviews of the cost to complete and whilst they are still of the view that there are still additional credits which have not been taken into account which should be deducted from the final cost to complete accept a Cost Overrun has been determined. They also believe the imposition of penalty rates should not have applied until the Bank had reasonably determined it taking into account credits due to the borrower.

Notwithstanding this as per my memo of 16th of October in response to the Bank's correspondence of 9 October they are prepared to provide the additional security requested and I will detail the proposed properties by following email later today.

I mentioned yesterday to Alan that we were confused re 3.3(1) where it appears to be asking for guarantees on the first Cost Overrun of $12.9 million notwithstanding the borrower paid $6.5 of it. As per my request yesterday could you please have Deacons explain the interpretation of this clause. Alan confirmed with respect to clause 3.3(2)(a) that you will only be taking security over CBA and Bankwest assets (acceptable to you) only to a total of $50 million.

In the interim I will have the acknowledgement executed and returned.
  1. Mr Pavisich was cross-examined at some length, by reference to the first paragraph of Mr Clohessy's email of 26 November 2009, about whether he understood Westgem to have accepted that a Cost Overrun of $17 million had occurred. The substance of Mr Pavisich's evidence was that he had a recollection that Mr Saraceni or Mr Clohessy had said to him something to the effect that Westgem accepted that there had been a $17 million Cost Overrun. He was unable to recall when this was said and in particular whether it was said before or after 1 December 2009, being the date on which the 18 November Letter Agreement was executed on Westgem's behalf. I formed a positive impression of Mr Pavisich as a witness. He impressed me as an honest witness who did his best to recall the events about which he was giving evidence (not an easy task given the events occurred approximately nine years earlier) and to answer questions put to him in cross-examination without any attempt at evasion. I have, however, reservations about the reliability of Mr Pavisich's recollection of a statement that one or other of Mr Saraceni or Mr Clohessy had said that Westgem accepted that there was a Cost Overrun of $17 million and am not prepared to rely on Mr Pavisich's evidence in this respect. In part my reservations are based on the absence of any mention of this statement in Mr Pavisich's witness statement and, in part, because my impression is that the focus of Mr Pavisich's efforts was to find a way of resolving the problem caused by the second Cost Overrun rather than the detail of the quantum. I think it is likely that Mr Pavisich's recollection of the statement he attributes to Mr Saraceni or Mr Clohessy is an honest but mistaken combination in his mind of: the statement by Mr Saraceni that there was a Cost Overrun; the statement in Mr Clohessy's email of 16 October 2009 to the effect that Westgem would accept 333's determination of the Cost Overrun; and the acknowledgement contained in the 18 November Letter Agreement of a $17 million Cost Overrun.

Westgem's November 2009 drawdown request

  1. On 26 November 2009 Westgem requested a drawdown to fund a payment to Salta of $12,367,880.57 plus GST. On 30 November 2009 a drawing of $12,367,880.57 plus GST was made to enable Westgem to pay Salta.

18 November 2009 Letter Agreement

  1. On 27 November 2009 Mr Clohessy sent Mr Nagle an email in which he stated:[403]
Steve, as discussed Luke has signed document which is with Hossean, due to Hossean placing a larger share of the equity he requires a document to be prepared by his solicitor to be signed by Luke which I was hoping to have today however Luke is in Karratha with the Premier so I have not been able to finalise. Can I say as per my previous email they are committed to providing security and returning the acknowledgement, there is no attempt to stall or delay. Hossean is adamant he wants the documents completed. I would also like a response from Deacons re my query on guarantees.

December 2009

  1. On 1 December 2009 the 18 November 2009 letter was signed on behalf of Westgem and the guarantors (the 18 November Letter Agreement).

Professor O'Donovan's advice to Westgem

  1. On 3 December 2009 Mr Stevens sent Mr Clohessy a copy of Professor O'Donovan's memorandum of advice dated 25 November 2009.[404] In an accompanying email Mr Stevens commented 'You will see that based on the information available, from a technical perspective the chances are not considered great in terms of taking the Banks on'.[405] Mr Stevens asked whether Mr Clohessy wanted him to 'draft something up to the Banks to at least get them to slow down and think more about the situation?' Mr Clohessy replied that nothing was required at that stage.[406]

Variation to 18 November 2009 Letter Agreement

  1. On 22 December 2009 Mr Pavisich and Mr Nathan prepared a strategy paper for the Executive Credit Committee of Bankwest.[407] In summary the recommendations contained in the paper were as follows: the Financiers should accept the registered second mortgage securities being proposed by Westgem even though 333's assessment was that the upper equity limit of the securities was $44.5 million and that $3.1 million should be released to Mr Pourzand in certain circumstances; the Financiers should pay $356,000 in consultants' fees and a further payment of $392,000 should be paid on the provision of the additional securities; Westgem's proposal for the deferred payment of the second Cost Overrun should be accepted; the project progress claims be paid to Salta subject to the provisions of the Building Contract and the Builder's Side Deed; and that the Building Contract and Builder's Side Deed should be reviewed by counsel to determine the bona fides of Salta's view of its position.
  2. On 24 December 2009 the 18 November 2009 Letter Agreement was varied at the request of Mr Saraceni and Mr Pourzand because they were unable to pay the $17 million required to meet the second Cost Overrun by 31 January 2010. Mr Clohessy proposed that the second Cost Overrun be paid by instalments: $5 million on 31 January 2010, $5 million on 28 February 2010 and $7 million on 15 March 2010 (later extended to 25 March 2010).[408] The proposal was approved on 24 December 2009.[409] The Financiers agreed to accept additional securities with an upper value of $44 million rather than $50 million.

January 2010

Provision of additional securities

  1. On 28 January 2010:

(a) The First Additional Securities were executed in favour of the Security Trustee. These were the additional securities contemplated by the 18 November 2009 Letter Agreement and which should, in accordance with paragraph 3.3 of that agreement, have been provided by 14 December 2009. The First Additional Securities and the First Additional Security Providers are listed in appendix 1, table B.

(b) Westgem and the First Additional Security Providers entered a deed with the Finance Parties entitled 'Deed of consideration and acknowledgment (Additional Mortgages) - Multi-Option Facility Agreement - Raine Square' (the First DCA). Among other matters, the First DCA recorded that Westgem had agreed to pay a fee of $500,000 to the Financiers in consideration of them not exercising their Reserved Rights (as defined in the 18 November Letter Agreement).

February 2010

Payment of first tranche of second Cost Overrun

  1. On 2 February 2010 $5 million was paid on Westgem's behalf in respect of the second Cost Overrun. The second payment of $5 million that was due on 28 February 2010 was not made. There was no agreement to waive the payment or extend the time for payment. By 14 April 2010 a total of $6,977,000 had been paid in respect of the second Cost Overrun.

Westgem's Financial Statements No 8 and 8A

  1. On 1 February 2010 Westgem prepared Financial Statement No 8 and the following day prepared Financial Statement No 8A.[410] Financial Statement No 8 identified the projected contract sum as $261,228,193 and Financial Statement 8A identified the projected contract sum as $259,578,193. Financial Statement No 8 included a 'Contingency balance' of $500,000 and Financial Statement No 8A included a 'Contingency balance' of $1,500,000 but did not include $2,650,000 of work that was included in Financial Statement No 8 as 'Works to be carried out post Practical Completion'. Neither Financial Statement No 8 nor Financial Statement No 8A was provided to the Finance Parties.

Cost to Complete - construction costs

  1. Various estimates of the construction costs were contained in the evidence and I have referred to them in the course of setting out my factual findings. For the purposes of this litigation Westgem retained an experienced quantity surveyor Ms Anne Connolly to express opinions on a number of issues regarding construction costs and these opinions were recorded in a report prepared by Ms Connolly,[411] and in a report entitled 'Cost Expert Conclave Joint Report',[412] prepared jointly by Ms Connolly and Mr Peter Byford, a construction expert retained by the Financiers.
  2. One of the questions on which Ms Connolly was asked to express an opinion is what costs would have been incurred by Westgem to complete the 'Works' on the assumption that Salta had not terminated the Salta Building Contract in February 2010. For the purposes of answering this question Ms Connolly was asked to adopt a definition of 'Works' that excluded, among other items, the tunnel. Ms Connolly's answer to that question was to the effect that the total construction costs would have been in the range of $248,235,566 to $260,203,165.[413] As a result of conferral between the experts Ms Connolly revised her opinion as to the range to $255,577,337 to $256,680,022.[414] These figures included allowances for deductions in respect of liquidated damages of $7.5 million and they did not include any allowance for the IFO Cooperation Fee or - as I have said - for the tunnel. Even if the only adjustment that was made to Ms Connolly's figure was to add back the cost of the tunnel at $4.3 million (being the figure for the tunnel included in Westgem's 26 October 2009 forecast), Ms Connolly's range increases to $259,877,337 to $260,980,022.
  3. In the table below I set out the construction costs forecasts made between June 2009 and 2 February 2010 and include Ms Connolly's figures for comparison purposes.


Westgem

RBB

333

Ms Connolly

Financial Statement No 6

16 June 2009

$251.33m




Response Budget (excl liquidated damages)

17 June 2009

$238m




RBB 16 July 2009


$243m



Financial Statement No 7

18 August 2009

$263.74m




4 September 2009, 'Summary of Construction Costs'

$243m




RBB Report,

14 September 2009


$260m



26 October 2009

$250m




4 November 2009, '333 draft table'



$262.4m


13 November 2009, '333 report'



$260.9m


Financial Statement No 8

$261.2m




Financial Statement No 8A

$259.5




Ms Connolly's opinion extracted from Exhibit P11 with addition of $4m for tunnel




$259m - $261m

  1. All of the figures were estimates and to arrive at them judgments were required about events that were by their nature uncertain ‑ Mr Gowdie described calculating the cost to complete any project as a 'forward looking estimate that involves judgment based on experience and is dependent on the nature, and extent and quality of the information at hand'.[415] In the case of Ms Connolly's estimate there was uncertainty because she was working on the hypothesis that Salta had continued working on site as opposed to working on the basis of historical information.
  2. In my view, it may be concluded with some confidence that on 18 September 2009 the amount required to be expended on construction costs to achieve Practical Completion of the Project was at least $260 million. This conclusion may be sustained by reference to the estimates prepared by Westgem for its own internal purposes - in particular Financial Statement No 8 and Financial Statement No 8A estimates, considered independently of the estimates prepared by RBB and 333, but when the estimates are considered in combination they provide powerful support for the conclusion that the construction costs were at least $260 million. In reaching this conclusion I have not attached decisive significance to Ms Connolly's estimate but have relied upon it as providing confirmation of what may be drawn from the other estimates.
Second Cost Overrun contractual claims

Breaches alleged

  1. The breaches alleged in respect of the second Cost Overrun were expressed in substantially the same terms as the first Cost Overrun breaches.
  2. Westgem alleged that Bankwest did not:[416]

(a) make any inquiries of Westgem so at to afford it a reasonable opportunity to provide information in relation to whether a Cost Overrun had occurred;

(b) give any or any reasonable consideration to the terms of the MOFA as to how a Cost Overrun was to be determined;

(c) give any or any reasonable consideration to whether RBB's calculation of the cost to complete had been performed adequately in accordance with the MOFA.

  1. Westgem alleged the second Cost Overrun had not, in fact, occurred. In this respect Westgem's case repeated the substance of the allegations made in respect of the first Cost Overrun, that is, Bankwest adopted an incorrect construction of the Cost to Complete definition and there was no certification of the amount determined by RBB of the likely cost to Westgem of achieving practical completion under the Building Contract. Westgem pleaded that the Cost to Complete did not in fact exceed the Undrawn Commitment of $133,875,921 but did not adduce evidence in support of this plea.
  2. Westgem alleged that Bankwest had not reasonably determined the second Cost Overrun had occurred and in support of this allegation relied on the same facts as were relied on for the purposes of the other alleged breaches.
  3. As with the conduct relied upon to constitute breaches of the first Cost Overrun Westgem rolled up the conduct relied for the second Cost Overrun breaches and pleaded that it involved:[417]

(a) Bankwest breaching the Code Conduct Term because Bankwest failed to act fairly and reasonably and in an ethical manner and failed to have any proper regard to the terms of the MOFA;

(b) the Financiers breaching

(i) the Cost Overrun Term;

(ii) No reliance on events caused by own conduct;

(iii) the Cost Overrun Consultation Term

(iv) the no Event of Default term and the reasonable grounds term.

Consideration of claims as developed in closing submissions

Second Cost Overrun determined in accordance with MOFA

  1. Westgem relied on four propositions to make good the allegation that Bankwest did not determine the second Cost Overrun in accordance with the terms of the MOFA. For the reasons developed below I do not accept the propositions relied on by Westgem.
  2. Westgem's first proposition was that the Cost to Complete component of the Cost Overrun was determined by reference to the amount required to be expended on the construction costs required to achieve Practical Completion of the Project rather than, as Westgem contended, the amount required to be expended in order to achieve Practical Completion under the Salta Building Contract. For the reasons given earlier I do not accept Westgem's construction of the Cost to Complete provision and do not accept that in calculating the Cost to Complete by reference to the construction costs that would be required to achieve Practical Completion of the Project, Bankwest failed to determine the Cost to Complete and thus the second Cost Overrun in accordance with the terms of the MOFA.
  3. Westgem's second proposition was that Bankwest did not properly determine the cost to complete the Project because it took into account the contingency allowance of $5,339,061 included in Mr Sanders' 14 September 2009 report. Westgem contended that the amount should not have been included in Mr Sanders' calculations because it was not a likely cost. For very similar reasons to those I have given for rejecting the proposition that Bankwest was wrong to take account of the contingency in Mr Sanders' July 2009 construction cost forecast, I reject the contention that Bankwest was wrong to take account of the contingency of $5,339,061 in Mr Sanders' 14 September 2009 report. I will not repeat all of my earlier reasoning on the contingency issue. Mr Sanders explained why he had allowed the contingency in his 14 September 2009 report. On the basis of that explanation I am satisfied that Mr Sanders made the allowance to reflect what he considered to be the 'likely costs' of achieving Practical Completion of the Project. Whilst direct comparison between the figures is difficult because of differences in approach in presenting the figures, the fact that both Mr Frank Saraceni and Mr Simpson included allowances for contingencies of $5,739,061 and $5 million respectively, in the Westgem September 2009 construction cost forecast and the Westgem October 2009 construction cost forecast reinforces my view that taking account of Mr Sanders' allowance for contingencies as forming an element of the likely costs of construction involved no departure from the terms of the MOFA.
  4. Westgem's third proposition was that Bankwest purported to determine the Cost Overrun by reference to the difference between Mr Sanders' construction costs forecast of $260 million and the revised project budget of $243 million rather than by reference to the contractual concept of Undrawn Commitment. The same argument was raised by Westgem in relation to the first Cost Overrun and I repeat the observations I have made earlier in these reasons about that argument. Mr Nagle's calculation of the second Cost Overrun is evidenced by the Credit Risk Summary prepared by him on 17 September 2009 and, in particular, by the 'Cost to Complete assessment' shown in tabular form and to which I have referred earlier. That table did not contain the same level of detail of the Cost to Complete as was contained in Mr Nagle's July 2009 paper but it included the essential integers required to determine a Cost Overrun - the Undrawn Commitment of $133,791,000 and (though not expressly identified as such) the Cost to Complete of $150,791,000 giving a Cost Overrun of $17 million. Moreover, as the Financiers submitted, the first Cost Overrun was determined in circumstances in which any increase in construction costs would result in a Cost Overrun because there were no savings or reductions in other likely costs that could be offset against the increase in construction costs and the Facility Limit remained the same. The same circumstances prevailed in September 2009 and any increase in construction costs would result in a Cost Overrun for the same reasons.
  5. Moreover, although Westgem challenged Bankwest's assessment of the existence of the second Cost Overrun on the basis that an increase in construction costs resulted in a Cost Overrun, that was, in fact, the way in which in September 2009 Westgem itself regarded an increase in the construction costs. In opening senior counsel for Westgem, referring to the comparison made between the original construction budget and the construction cost forecasts, said 'Both sides are using that as the jumping off point' meaning that both sides treated an increase in construction costs as an event that resulted inevitably in a Cost Overrun.[418]
  6. Westgem's fourth proposition advanced to make good the allegation that Bankwest did not determine the second Cost Overrun in accordance with the provisions of the MOFA was that Mr Nagle did not determine the Cost Overrun by reference to the cost of performing the works under the Salta Building Contract at the time the MOFA was executed but by reference to additional works that had been included by variations. For the reasons explained earlier I consider the Cost to Complete had to be calculated by reference to the likely construction costs to be expended to achieve Practical Completion of the Project at the time the determination of the Cost to Complete was made not by reference to the cost of completing the work falling within Salta's scope of work under the Salta Building Contract at the time the MOFA was executed.

Second Cost Overrun reasonably determined

  1. In its closing submissions Westgem advanced three reasons why Mr Nagle's determination of the Cost to Complete had not been 'reasonably determined'.
  2. First, Westgem contended that Mr Nagle did not read the terms of the MOFA but 'blindly accepted' the conclusions set out in Mr Sanders' report and failed to notice an arithmetical error in Mr Sanders' calculations. The error was admitted - it involved an accidental omission of a line item in Mr Sanders' summary of the items generating the increased construction costs - and was explained by Mr Sanders in his witness statement.[419] I do not accept that Mr Nagle did not read the relevant terms of the MOFA. I infer from the references to the relevant definitions and terms of the MOFA in his 27 July 2009 paper and the 17 September 2009 Credit Risk Summary that he had read the relevant terms of the MOFA. In the course of opening senior counsel for Westgem stated that the arithmetical error '[didn't] really go anywhere in the case'.[420] Mr Sanders was not cross‑examined about the error.
  3. The second and third reasons overlap - the second reason rested on Westgem's contention that Mr Nagle did not take into account - by which Westgem meant failed to make an allowance in Westgem's favour - Contract Sum Adjustment 22, and the third reason was that it should have been obvious to Mr Nagle that Mr Sanders had failed to consider Contract Sum Adjustment 22 because his report was expressed to be 'up to CSA 21'. There is also an overlap between these reasons and Westgem's contention that Bankwest breached the Cost Consultation Term because Mr Nagle failed to consider Contract Sum Adjustment 22.
  4. I am satisfied that Mr Nagle did not fail to 'reasonably determine' the Cost to Complete by not allowing a 'credit' in respect of Contract Sum Adjustment 22.[421]
  5. Before commenting on each credit claimed by Westgem some overarching points may be made. Westgem's claims in respect of these credits did not rise above the level of assertion. Westgem called no evidence to establish that they were credits that Mr Nagle was obliged to have taken into account for the purpose of making a reasonable determination of the Cost to Complete. Westgem adduced no evidence to establish that reductions in the construction costs were actually achieved in the amounts claimed in the credits.
  6. Further, it was reasonable for Mr Nagle to take a cautious approach and not to make an allowance in respect of the credits. The good sense in this approach was amply demonstrated by Westgem's equivocation in respect of the credit for the blinds - removing the installation of the blinds from Salta's contract, 12 days later informing the blinds subcontractor on a confidential basis that the blinds might remain within Salta's contract and ultimately leaving the installation of the blinds within Salta's contract.
  7. Turning now to the specific credits claimed - objectively it was reasonable not to allow the credit claimed in respect of Podium works for the following reasons:

(a) The amount claimed was based on an 'indicative estimate' prepared by Westgem's quantity surveyors on the basis of information provided by Westgem. The figure had not been agreed with Salta. There was thus no certainty about the quantum.

(b) Second, the only justification for the credit was to be found in RLB's letter of 7 September 2009 attached to Contract Sum Adjustment 22. The justification was expressed as follows:

We understand that the previously documented works to the office and pavilion areas on this level have been significantly reduced in scope and will now be substantially undertaken by the tenant as part of their fit-out works.

Westgem itself provided no explanation for this credit directly to Mr Sanders or to Mr Nagle. There was no documentary evidence to confirm that Bankwest as tenant had agreed to undertake the work removed from Salta's scope. The credit was advanced on the basis of a consultant's unconfirmed understanding of a 'significant' reduction in scope. Importantly, there was nothing to suggest that the work would be paid for by Bankwest as tenant or that Bankwest (as tenant) would not require Westgem to fund the payment for the work out of the Facility. Objectively it was unlikely that Bankwest as tenant would agree to pay for work that Westgem had previously agreed to undertake. The significance of the absence of any written confirmation about these two important aspects of the 'credit' is reinforced by the fact that when Mr Nagle subsequently made inquiries with the 'fit-out team', he was told that the obligation to pay for the work rested with Westgem as part of its 'base-build' obligations.

(c) The paucity of information provided in support of the 'Podium' credit acquires greater significance when seen in the context of the concern expressed by Mr Sanders to Mr Frank Saraceni about 'things falling through the gaps of who is paying for what (see Mr Sanders' email to Mr Frank Saraceni of 5 August 2009)[422] and that both Mr Sanders and Mr Nagle had independently of each other sought information from Westgem about the credits. In those circumstances it was not unreasonable to expect a clear and cogent justification for the credit to have been provided.

  1. Similar points may be made in respect of the credit claimed in respect of the window blinds. This credit was presented as an estimate, the value of which was to be confirmed by the subcontractor. Thus, there was no certainty in relation to the amount. More fundamentally no explanation was provided as to the basis upon which the window blinds were being removed from Salta's scope of works. There was nothing in Contract Sum Adjustment 22 to suggest that the blinds were not required to complete the Project. There was no basis for Mr Nagle to conclude that the blinds were no longer required or that they would not have to be paid for out of funds drawn down from the Facility. The credit sought in respect of the blinds was not a credit that had been referred to by Mr Frank Saraceni in the Westgem September 2009 construction cost forecast or in any communications preceding Contract Sum Adjustment 22. Further, as referred to earlier, ultimately Westgem did not maintain its claim for a credit in respect of the blinds and it is difficult to see on what basis it could ever have been contended by Westgem that Mr Nagle should have allowed this credit when determining the Cost to Complete or that he acted unreasonably in failing to allow a credit.
  2. In my view Mr Sanders' reasons for concluding that the asserted credits should not be taken into account - essentially because there was uncertainty as to whether any 'credits' had been agreed and there was uncertainty as to the amounts - were cogent and convincing.[423]

No failure to consult or take information into account

  1. In its closing submissions Westgem did not develop its case in respect of breach of the Cost Overrun Consultation term beyond asserting that Bankwest breached the term because it did not consider Contract Sum Adjustment 22 before determining the second Cost Overrun.[424] In the light of the factual finding that Mr Nagle did read and consider Contract Sum Adjustment 22 before determining that the second Cost Overrun this aspect of Westgem's case must fail.
  2. Westgem did not seek any other specific factual findings that might establish the allegation that there was a failure by Bankwest to afford a reasonable opportunity to Westgem to provide information as to whether a Cost Overrun had occurred or that Bankwest failed to reasonably consider any such information. Contrary to the premise underlying Westgem's breach of the Cost Overrun Consultation Term - that is that Bankwest did not consult Westgem about costs - it was Bankwest that had been pressing for information which Westgem had not provided. At the risk of unnecessary repetition, Mr Nagle had been pressing Mr Clohessy for further information that addressed 'the real concerns that current reporting indicates further increases in costs' since his email of 17 August 2009.
  3. Westgem had the opportunity to provide information to Bankwest. Mr Frank Saraceni provided the Westgem September 2009 construction cost forecast to Mr Nagle and Mr Sanders and this was evaluated by Mr Sanders. Mr Sanders and Mr Nagle pressed Westgem for further information about credits and it was in response to those requests for information that Contract Sum Adjustment 22 was provided. For the reasons discussed above Contract Sum Adjustment 22 lacked supporting detail and was of limited utility. Further, Mr Sanders discussed his 14 September 2009 report with Mr Frank Saraceni.
  4. In the period following the giving of notice of the second Cost Overrun and the execution of the 18 November Letter Agreement there were extensive communications between Westgem and the Finance Parties about the second Cost Overrun and there is ample evidence that the information provided by Westgem in the course of those exchanges was considered, and, in particular, was considered by Mr Sanders and Mr Gowdie, who provided advice to Bankwest.
  5. No evidence was adduced by Westgem to suggest that there was further relevant information that could have been provided to Bankwest but which it did not have an opportunity to provide and there was no evidence that the consideration that was given to the information that was in fact provided was not reasonable.

RBB had certified Cost to Complete

  1. Westgem contended that the Financiers breached the MOFA because the Cost to Complete upon which the second Cost Overrun was based, was based on calculations that had not been certified as required by cl 1.1(33) of the MOFA. I reject this contention for the reasons given for rejecting the same argument when raised in respect of the first Cost Overrun.

Cost to Complete

  1. In support of its pleas that the second Cost Overrun had not in fact occurred Westgem pleaded that it would establish that at 17 September 2009 the Cost to Complete did not exceed the Undrawn Commitment but at trial it did not attempt to do so. The largest component of the Cost to Complete - and the most controversial - was the likely construction costs. As has been seen Westgem's complaints about the reasonableness of Bankwest's determinations of the Cost to Complete focussed on the approach adopted to making the determination. In essence Westgem alleged 'process unreasonableness' that embraced, on its case, a failure on Bankwest's part to apply the terms of the MOFA on their proper construction.
  2. I have found that the Cost to Complete was $260 million, that is, that the likely cost to Westgem under the Building Contract (as I have construed that term) of achieving Practical Completion (as I have construed that term) would be $260 million. The consequence of this finding is that even if Westgem has established the second Cost Overrun breaches those breaches would have been of no causative significance.

Bankwest acted fairly reasonably and in an ethical manner

  1. Westgem submitted Bankwest's conduct in respect of the second Cost Overrun constituted a breach of the Code Conduct term for the same reasons that it amounted to unconscionable conduct in contravention of s 12CC(1) of the ASIC Act. For the reasons explained below Westgem has not established that the Finance Parties engaged in unconscionable conduct in respect of the second Cost Overrun. For the reasons already given, the Code Conduct Term was not a term of the MOFA.
The second Cost Overrun statutory unconscionability claim

An overview of Westgem's case

  1. In broad terms there were three strands to Westgem's unconscionable conduct claim in respect of the second Cost Overrun. The first strand revolved around the determination of the second Cost Overrun itself and the Financiers' adherence to the view that the second Cost Overrun had occurred. Westgem argued that the Financiers' conduct was unconscionable because, so it argued, immediately after the second Cost Overrun had been determined Mr Nagle had doubts about whether he should have allowed a credit in respect of the reduced scope of the Podium work and subsequently, in November 2009, he knew that he should have made a such an allowance because Mr Frankl had informed him by email on 24 November 2009 that some credit was due.
  2. The second strand of Westgem's claim was the contention that the Financiers applied 'extreme commercial pressure' on Westgem and the guarantors to accept the terms of the 18 November Letter Agreement. Westgem contends the pressure was constituted by the application of the default interest rate; the application of 'leverage' to Mr Saraceni, Mr Pourzand and their interests manifested by CBA's requirement that the Pakwest facility be repaid or be renewed on terms less favourable to Pakwest than before; the refusal to pay soft costs; Mr Pavisich's insinuation that the banks might appoint a receiver; and Mr Nathan's willingness to 'rattle the cage' should that be required.
  3. The third strand of Westgem's claim was the contention that the terms of the 18 November Letter Agreement included terms that were not reasonably necessary for the protection of the Financiers' legitimate interests. In particular Westgem points to:

(a) The requirement that the guarantors acknowledge that the first and second Cost Overruns had occurred in circumstances in which the first Cost Overrun had been disputed but paid and the second Cost Overrun continued to be disputed.

(b) The requirement for the provision of additional securities with net equity of at least $50 million was disproportionate to the Cost Overrun of $17 million.

(c) The requirement to pay an amendment fee of $500,000 which Westgem contended bore no resemblance to the costs incurred by the Financiers as a consequence of the second Cost Overrun.

(d) The right conferred on the Financiers to review the terms of the MOFA and propose amendments after receiving a report from 333, and if the amended terms could not be agreed within five business days, give not less than 60 days notice requiring Westgem to repay the money owing under the MOFA.

(e) The statement in the letter of 18 November 2009 that if the letter was not signed and returned by 23 November 2009 that omission would, of itself, constitute an Event of Default.

Doubts about the occurrence of second Cost Overrun not evidence of unconscionable conduct

  1. I have found Bankwest acted reasonably in making the determination of the Cost to Complete component of the second Cost Overrun and conformably with that finding my assessment is that in discharging its responsibilities as Facility Agent, Bankwest acted conscientiously in the determination of the second Cost Overrun. I repeat my earlier observations in relation to Mr Nagle's concern from mid-August onwards to obtain information from Westgem and the time pressures under which he was required to operate.
  2. Westgem characterised Mr Nagle's inquiries with the 'CBA fit out team' and Mr Frankl about the credits claimed in Contract Sum Adjustment 22 as indicative of doubts on his part as to whether he should have allowed the claimed credits as deductions from RBB's construction cost forecast. In my view the further inquiries made by Mr Nagle about the credit claimed by Westgem in respect of the Podium are not to be taken as evidence of unconscionable conduct but rather a conscientious approach to his responsibilities. Mr Nagle's inquiries were necessary because the information that accompanied Contract Sum Adjustment 22 was, on its face, incomplete and thus unreliable. The uncertainty surrounding the credit for the Podium works was highlighted by the statement by Mr Frankl in his email of 24 November 2009 that he was not in a position to advise 'the exact split in dollars attributable to Westgem and Bankwest as tenant at this time', so that even at that stage the quantum of the credit was unknown.
  3. Two further points may be made. First, confirmation on 24 November 2009 from Mr Frankl that a credit in respect of the Podium works, in an amount that had still to be determined, does not have any bearing on the reasonableness of Mr Nagle's determination of the cost to complete on 18 September 2009 on the basis of the information then available to him. Second, on the basis of the 333 cost to complete analysis of 13 November 2009 there was a Cost Overrun of $17.93 million - 333's cost to complete was $260.93 million after making an allowance of $1.2 million in respect of the Podium work. Westgem had agreed to accept 333's determination - in those circumstances it cannot be said that the Financiers were unconscionable in relying on a lesser figure than the one determined by 333 which Westgem had agreed to accept.
  4. As explained earlier in these reasons the Cost to Complete and Cost Overrun provisions of the MOFA were part of the mechanism by which the Financiers were able to protect their commercial interests and manage risk. I am satisfied that by declaring that there had been a Cost Overrun of $17 million and thereafter maintaining that this had given rise to an Event of Default the Financiers were doing no more than relying on their contractual rights to protect their legitimate commercial interests. There was no evidence sufficient to support a finding the Finance Parties did not genuinely hold the view that there had been a Cost Overrun of $17 million or that they were otherwise being disingenuous or dishonest in maintaining the position that there was a Cost Overrun in this amount that had given rise to an Event of Default. I am satisfied that the Finance Parties believed that they were entitled to take the position they adopted, and in doing so they were not acting unconscionably. In my view the determination of the second Cost Overrun was the result of a bona fide analysis under the MOFA, I do not accept that in such circumstances (even assuming Westgem was successful on its claims that such an analysis was incorrect) that Westgem is able to establish that the conduct of the Financiers departed so markedly from community standards such as to be offensive to conscience.[425]

'Extreme commercial pressure'

  1. I do not accept Westgem's characterisation of the Finance Parties' conduct towards Westgem and its guarantors in the period between the occurrence of the second Cost Overrun and the execution by Westgem of the 18 November Letter Agreement as the 'application of extreme commercial pressure', but leaving that question of characterisation aside, the Finance Parties did not act unconscionably.
  2. I do not doubt that in appropriate circumstances the application of commercial pressure may be viewed as unconscionable. But whether that pressure will rise to such a standard must be considered in light of what prevailing community standard would consider to be pressure that goes against conscience. Such considerations must be tempered by an understanding that in the life of commerce and finance, many acts are done under pressure, sometimes overwhelming pressure.[426]
  3. Westgem's unconscionability claim relies on a number of aspects of the Finance Parties' conduct which Westgem contended either constituted unconscionable conduct or evidenced a willingness to adopt unconscionable tactics, but it overlooks three important matters. First, even though, the Financiers were not obliged to do so, (because the existence of an unpaid Cost Overrun was a condition precedent to drawdowns under the MOFA), the Financiers did permit Westgem to drawdown on the Facility to meet Salta's progress claims, albeit with some delay in respect of the September payment. Secondly, the Facility Agent and the Financiers did not disregard Westgem's protests about the amount of the second Cost Overrun and the 'credits'. They gave those protests genuine and serious consideration. Mr Nagle made his own inquiries in relation to the Podium works, Mr Sanders assessed the credits claimed in Contract Sum Adjustment 22 in October 2009 and determined that none should be allowed and 333 undertook a review of the Project. In the course of his detailed investigation Mr Gowdie discussed the credits with Mr Frank Saraceni and considered the detail of them, whilst he was prepared to allow a credit for the Podium works, the effect of his analysis was that there was a Cost Overrun of $17.9 million. Thirdly, the Financiers were prepared to negotiate and did negotiate with Westgem over the terms upon which they were prepared to grant further financial accommodation to Westgem.
  4. The statutory prohibition on unconscionable conduct does not operate to prevent parties from relying on their legal rights nor from making commercial decisions that suit their interests. It was not unconscionable for the Financiers to rely on their contractual right under the terms of the MOFA to apply the default interest rate and to refuse a drawdown request for 'soft costs'.
  5. Likewise it was not unconscionable for CBA as Bankwest's parent company not to renew Pakwest's finance facility on the same terms if it was under no obligation to do so.
  6. Against the background of Mr Saraceni's threats to walk away from the Project and to sue the Financiers, it would be unrealistic to expect that the Financiers would not take steps to protect their interests and record their intention to do so in robust language - it was legitimate for them to do so. Mr Pavisich's insinuation that a receiver might be appointed if agreement could not be reached in relation to the second Cost Overrun was a statement of the obvious made in the context of robust commercial discussions. Moreover, if Mr Saraceni had acted on his threat to walk away from the Project, the appointment of a receiver would have been inevitable.
  7. In the course of cross-examination it was put to Mr Pavisich that he and others had sought to bully and intimidate Westgem into signing the 18 November Letter Agreement. Mr Pavisich rejected the accusation and said that in his dealings with Westgem he had 'always tried to do the right thing, to get this building completed with them in place',[427] and that he had worked with Westgem to find a solution.[428] In the discussions and negotiations in the period between September 2009 and March 2010 Mr Pavisich was the main point of contact between the Financiers and Westgem about the second Cost Overrun. He communicated directly with Mr Clohessy and, to a lesser extent, with Mr Luke Saraceni. Based on the content and tenor of his email communications and his account of his conversations, my impression is that Mr Pavisich adopted a reasoned approach in his discussions with Mr Clohessy and Mr Saraceni. His approach was not one that could be characterised as bullying or intimidatory. Whilst self-evidently it was a generalised response to a generalised accusation of bullying and intimidation I accept Mr Pavisich's evidence that he tried to do the right thing and worked with Westgem to find a solution.

The terms of the 18 November Letter Agreement were not unconscionable

  1. The 18 November Letter Agreement was an agreement that extended Westgem's time to pay the second Cost Overrun in circumstances in which it had been unable to pay in accordance with the terms of the MOFA. The 18 November Letter Agreement recorded this accommodation in Westgem's favour.
  2. Two further observations about the wider commercial context may be made. First, the 18 November Letter Agreement must be seen in the context of the bargain struck by Mr Saraceni and Mr Pourzand embodied in the MOFA by which they assumed the risk of Cost Overruns. No doubt as experienced property developers they had made an assessment of the likelihood of that risk materialising and their ability to deal with the risk if it did materialise. If their assessment was wrong (or if they were simply unfortunate in relation to events beyond their control) and were unable to deal with the consequences of a Cost Overrun when it occurred, that was their commercial misfortune which arose as a consequence of a commercial agreement willingly entered into by them in the expectation of profits. The second observation, while no doubt trite, still needs to be made, it is simply that in business one party's commercial disadvantage is often another party's commercial advantage and the statutory prohibition of unconscionable conduct is not intended to prohibit a business from enjoying the benefit of its contractual counterparty's commercial disadvantage. Neither is it intended to relieve a party of the consequences of entering a deal that, as events unfold, turns out badly. As the High Court has made clear the prohibition against unconscionable conduct is concerned with conduct that is against conscience - it is a high threshold. It is not a panacea for all commercial failings, to be applied in favour of the party thought most deserving of sympathy.
  3. Turning to the terms of the 18 November Letter Agreement the first provision on which Westgem focussed was as follows:[429]
[E]ach Guarantor acknowledges that all Cost Overruns, including the Cost Overruns in the amount of $12,921,000 and $17,000,000 as set out in the notice to the Borrower dated 18 September 2009 sent by the Facility Agent for and on behalf of the Finance Parties, form part of the Guaranteed Money (as that term is defined in the Guarantees) for which each Guarantor is liable in accordance with the terms of that Guarantor's Guarantee;
  1. Westgem was seeking an accommodation from the Financiers in the form of time to pay the second Cost Overrun. It was doing so against the background of Mr Saraceni having threatened to sue the Financiers. In proposing the terms on which they would accommodate Westgem it was legitimate for the Financiers to attempt to limit the potential for further disputes by seeking an acknowledgement from the guarantors that the Cost Overruns formed part of the 'Guaranteed Money'. It was not in the Financiers' interests to accommodate Westgem yet remain exposed to the risk of being sued by it. It was understandable that the Financiers wanted a measure of certainty and the (limited) protection from action that an acknowledgement of the occurrence of the Cost Overruns by the guarantors provided. It must be remembered also that by 16 October 2009 Westgem had agreed in principle to accept the outcome of the 333 determination of the cost to complete. Westgem may not have accepted that the second Cost Overrun had occurred in the sense that its directing minds, Mr Saraceni and Mr Pourzand, had not been positively persuaded of the existence of a Cost Overrun but it had agreed to accept 333's assessment by way of a compromise.
  2. The requirement for an additional $50 million of security was recorded in the 18 November 2009 letter as follows:[430]
[E]ach Transaction Party undertakes, and by their execution of this letter hereby gives the undertaking (Undertaking), to provide to the Security Trustee, by no later than 14 December 2009:

(a) valid and enforceable second ranking mortgages over all land owned by the Transaction Parties that is currently mortgaged in favour of the Bank of Western Australia Ltd or the Commonwealth Bank of Australia, and which land is acceptable to the Financiers (in their sole and absolute discretion) (Additional Mortgages); and/or

(b) any other security or credit support acceptable to the Financiers in their sole and absolute discretion (Additional Credit Support),

which is to act as additional security for repayment of the Facility. The aggregate of the net equity value (as determined by the Financiers in their sole and absolute discretion) in the properties the subject of the Additional Mortgages and the Additional Credit Support must be at least $50,000,000.
  1. In discussions about the terms upon which the second Cost Overrun might be settled the value of the security sought by the Financiers was not a contentious issue. In his email to Mr Pavisich of 5 October 2009 Mr Clohessy indicated that Mr Saraceni and Mr Pourzand accepted that the Financiers required an additional $50 million of security. The absence of any controversy about the term at the time it was negotiated undermines Westgem's claim that it constituted or evidenced unconscionable conduct. In my view it was legitimate for the Financiers to ensure that they had adequate security and for them to the sole arbiters of the adequacy of the security.
  2. Westgem relies on the amendment fee of $500,000 - approximately 3% of the accommodation of $17 million - as evidence of unconscionable conduct on the part of the Financiers. Westgem adduced no evidence of the fees charged by financiers generally for financial arrangements of the nature contemplated by the 18 November Letter Agreement. Westgem paid an establishment fee of $1 million to Bankwest for the facilities established by the MOFA. No objection was made to the $500,000 fee at the time it was charged, though, as noted in the course of stating the factual background to the second Cost Overrun, there was some discussion between Mr Clohessy and Mr Pavisich about the possibility of reducing the establishment fee and increasing line fees. The proposition that the fee of $500,000 is evidence of unconscionable conduct, or constituted unconscionable conduct is not made out.
  3. The provision that conferred a right on the Financiers to require amendments to the MOFA after the Financiers had considered 333's report was as follows:[431]
The Transaction Parties also agree that, in consideration of the Finance Parties not immediately exercising the Reserved Rights pursuant to the terms of this letter as they are entitled to do in accordance with the Facility Agreement, the Financiers may review the Multi-Option Facility and the conditions of the Multi-Option Facility, including, without limitation, pricing, the Cost to Complete and the Security for the Multi-Option Facility after the report, or any interim report, of the Independent Consultant from 333 Real Estate Pty Ltd (IC Report) has been provided to the Facility Agent. Following a review by the Financiers of the IC Report:

(1) the Facility Agent may give a notice to the Borrower stating that the Financiers require amendments to the Multi-Option Facility. The Borrower and the Facility Agent agree to negotiate in good faith for a period of 5 Business Days from the date of service of that notice (Negotiation Period) to determine those amendments; and

(2) if the amendments required by the Financiers are not agreed by the end of the Negotiation Period, the Facility Agent may give a notice to the Borrower under which it nominates a date (being not less than 60 days from the date of service of that notice) (Nominated Date) by which the Financiers require the Borrower to pay to the Facility Agent the Secured Money In full.
  1. Westgem described this term, which, in effect, conferred on the Financiers a unilateral right to vary the terms of the MOFA, as an 'extraordinary term'. In a practical sense it gave the Financiers a right to terminate the MOFA even if the second Cost Overrun was remedied and Westgem had complied with the terms of the 18 November Letter Agreement. Mr Pavisich accepted that the provision gave the Financiers an 'extraordinary amount of power' over Westgem and added '... it basically says, you know, we can do what we like once we get the report'.[432]
  2. The rights conferred by cl 5.2 must be assessed in the commercial context that existed when the agreement was negotiated. Two matters are of particular relevance. First, on the basis of my findings, the Financiers were entitled to terminate the MOFA in November 2009, and demand repayment of all monies outstanding. Second, the Financiers wanted 333 to undertake a thorough review but it was not in their interests for the work to be further delayed. From the Financiers' perspective it was not unreasonable for them to press for the right to renegotiate the terms of MOFA once the Independent Consultant's review was completed. If the Independent Consultant's report had been available before the extension of time for payment of the $17 million was subject to a binding agreement, it would have been open to the Financiers to renegotiate the MOFA at that stage in the light of the report and if renegotiated terms could not be agreed, the Financiers could have demanded immediate payment of all monies then outstanding. It was not unreasonable for the Financiers to want to reserve the right of review.
  3. A difference between exercising the accrued right to terminate before the 18 November Letter Agreement was concluded on 1 December 2009, as opposed to exercising the rights under cl 5.2(2) was, of course, that in the latter instance, assuming Westgem did not remedy the Cost Overrun, the Financiers would have obtained the benefit of the additional $50 million security. This is not sufficient, however, to characterise the provision in cl 5.2(2) unconscionable.
  4. Westgem's acceptance of cl 5.2(2) of the 18 November Letter Agreement is indicative of Westgem's weak bargaining position. Mr Pavisich acknowledged the reality of the situation in which Westgem found itself in November 2009 - he accepted that in a practical sense Westgem needed 'to go along with the bank' and reach an agreement.[433] Looked at in isolation the provision was a 'bad bargain' from Westgem's perspective - it constituted a serious risk that even if the default was remedied, Westgem could be required to accept revised terms or repay the borrowed funds. The provision must be seen, however, as part of the consideration for the Financiers' making further financial accommodation available to Westgem so it could overcome the difficulty created by the second Cost Overrun. Whilst it constituted a risk, it was a risk that Mr Saraceni and Mr Pourzand, as experienced commercial operators in a disadvantageous commercial position, were prepared to take in order to obtain the benefit of the accommodation the Financiers were prepared to offer in respect of the second Cost Overrun. The fact the Financiers were able to take advantage of Westgem's inability to pay the second Cost Overrun and secure for themselves the opportunity to improve their commercial position was not unconscionable. In any event the Financiers did not invoke the right conferred by cl 5.2(2).
  5. Mr Pavisich was cross-examined extensively about the paragraph in the 18 November 2009 letter that asserted, in effect, that if its terms were not accepted by 23 November 2009, there would be an Event of Default. The paragraph read as follows:[434]
Please acknowledge your consent, acknowledgment. agreement and acceptance of the terms of this letter, and the provision of the Undertaking, by signing the attached copy and returning it to us by no later than 23 November 2009, failure to do so will constitute an immediate Event of Default (in addition to and without limiting or affecting in any way any subsisting Event of Default, including the Cost Overrun Default).
  1. A failure to sign the copy of the letter by 23 November 2009 was not capable of amounting to an Event of Default and the statement that it would do so, should never have been made. It appears to have been an ill-conceived attempt to put pressure on Westgem to accept the terms offered. That said, it does not advance Westgem's unconscionability claim because there is no evidence that Mr Saraceni, Mr Pourzand or Mr Clohessy took any notice of the statement or that it affected their decision-making in anyway. I infer from the fact that the letter was not signed until 1 December 2009 that either they did not appreciate what was being said in that paragraph of the letter or if they did, they simply ignored it. I suspect the latter alternative is more likely than the former.
  2. Westgem's unconscionable conduct claim based on the terms of the 18 November Letter Agreement faces the further difficulty that Westgem sought and obtained legal advice in relation to the 18 November 2009 letter. Westgem did not challenge the terms it identified as unconscionable when the letter was presented to it.

A final point

  1. Any force in Westgem's unconscionable conduct claim is blunted by Westgem's knowledge recorded in Financial Statement No 7 that its internal construction cost forecast made in August 2009 put the (construction) cost to complete at $263 million giving rise to a Cost Overrun of more than $17 million. Despite being obliged to do so (cl 15(9) and (10) of the MOFA) Westgem did not share this forecast with Bankwest.
The second Cost Overrun misleading or deceptive conduct claim
  1. Westgem's misleading or deceptive conduct claim in respect of the second Cost Overrun rests upon its claim that that the second Cost Overrun had not occurred at 18 September 2009 and that thus Bankwest's assertion of the existence of the second Cost Overrun was misleading or deceptive. The finding that the second Cost Overrun had occurred means that the misleading or deceptive conduct claim fails.

Financiers' positive defences to the second Cost Overrun claims

  1. As with the first Cost Overrun claims the Financiers raised a wide range of positive defences to Westgem's second Cost Overrun claim which involve some factual and legal complexity. As I have concluded that Westgem's second Cost Overrun claims fail on a number of levels it is unnecessary to address the Financiers' positive defences. I will, however, address one of the Financiers' positive defences, their estoppel by deed defence.
The estoppel by deed defence
  1. On 30 June 2010 the parties to the MOFA entered into a deed, the Fourth Deed of Variation,[435] and on 31 August 2010 they entered into a further deed, the Fifth Deed of Variation.[436] The primary purpose of each of these deeds was to extend the terms of Facilities that would otherwise have expired on 30 June 2010.
  2. Each deed contained a clause in the following terms:
5.1 The Borrower and each Guarantor acknowledges and agrees that:
(1) as set out in the Default Notice, the Borrower is currently in default under the Facility Agreement by way of Events of Default set out in the Default Notice; and

(2) the Finance Parties have reserved and continued to reserve, all of their rights and remedies in respect of those Events of Default.
  1. The 'Default Notice' referred to in the acknowledgement in cl 5.1 of the deeds was a default notice served by the Financiers on 5 March 2010.[437] Relevantly, the default notice stated:
Pursuant to a notice of demand dated 18 September 2009, the Facility Agent for and on behalf of the Finance Parties demanded the payment of the $17,000,000 Cost Overrun described in that notice by the Borrower on or before 25 September 2009.

The Borrower failed to make the $17,000,000 Cost Overrun payment in full on or before 25 September 2008 and, as at the date of this notice, that Cost Overrun remains unpaid in the amount of $12,000,000, in breach of clause 17.22 of the Facility Agreement (Cost Overrun Default).

...

The Cost Overrun default is an Event of Default under clause 17.22 of the Facility Agreement.

The Financiers' contentions

  1. The Financiers rely on the acknowledgement of the second Cost Overrun default as a foundation for an estoppel by deed. The Financiers contend that the deeds are not illegal, there is no application to have them rectified and no contention that they were induced by misrepresentation with the consequence that they might be rescinded in equity. The Financiers contend that Westgem should be held to its solemn and unambiguous statements in the deeds and that they are thus 'estopped, substantially and evidentially, from asserting that the statements in the deeds are untrue'.

Westgem's contentions

  1. Westgem answers the estoppel case in three ways. First, it says that if the court sets aside the 18 November Letter Agreement and finds that the 5 March 2010 default notice would not have been issued but for the Financiers' contravening conduct, the factual substratum of the acknowledgement falls away. The second answer is that the Fourth and Fifth Deeds of Variation containing the acknowledgements would not have been entered into were it not for the contravening conduct. The third answer is that the Financiers have not established detrimental reliance on the acknowledgements.
Applicable principles
  1. In Labracon Pty Ltd v Cuturich,[438] Lindsay J stated:[439]
The essential idea of estoppel by deed is that a party who, by entry into deed, expresses a solemn intention to be bound by a particular proposition will, in proceedings against a party entitled to the benefit of the deed, be precluded (that is, stopped), by reason of entry into the deed, from denying the truth, or at least, the operation of that proposition.
  1. The statement relied on as an estoppel must relate to specific facts, must be clear, certain and unambiguous.[440] A description of the rights of parties is a statement of fact.[441]
  2. An estoppel by deed does not operate at large. As explained in Spencer Bower: Reliance-Based Estoppel (2017, 5th ed):
The operation of an estoppel by deed is limited to actions founded on the deed because the agreement of the parties made by assent to the relevant recital is interpreted as an agreement to admit the proposition recited only for the purposes of the deed and the transaction effected thereby. The parties might, in theory, bind themselves by agreement under seal to admit a proposition for other purposes than the transaction effected by the deed itself, but this does not arise in practice. (Footnotes omitted)
  1. Unlike estoppel by convention, estoppel by deed does not require the person relying on an estoppel as a primary party to the alleged estoppel to prove that the party adopted or relied on the estoppel to their detriment.[442] In PW & Co v Milton Gate Investments Ltd,[443] Neuberger J (as his Lordship then was) explained that because estoppel by deed was a rule of evidence, 'there is, therefore, normally no question of considering the issue of unconscionability, which looms so large in relation to other estoppel, including estoppel by convention'.

Consideration

  1. Westgem pleaded that the MOFA was varied by the Fourth and Fifth Deeds of Variation.[444] The relief sought by Westgem and the MOFA Guarantors included orders made under s 12GM of the ASIC Act or s 77 of the FTA declaring both deeds were void ab initio. Estoppel by deed is not capable of providing a defence to those statutory claims but as I have concluded there is no basis upon which those claims can succeed and, as I have held also that the liquidator's claim to set aside the deeds as uncommercial has failed, it is appropriate to consider the merits of the defence.
  2. The requirement for a statement of specific facts in clear, certain and unambiguous terms is satisfied by the acknowledgement in each of the deeds of the existence of a default under the MOFA and the incorporation by reference of the 5 March 2009 default notice in which the second Cost Overrun was specified. The acknowledgement recorded the factual proposition, the existence of which Westgem's second Cost Overrun contractual claims sought to negate. The case it sought to advance was plainly inconsistent with the solemn and unambiguous acknowledgements in the deeds.
  3. Westgem's contractual claims in respect of the second Cost Overrun relied on the terms of the MOFA, which was varied by the two deeds of variation. In my view the acknowledgement of the existence of the second Cost Overrun is to be construed as an acknowledgement for the purposes of the transaction recorded in the MOFA that operates in respect of any claims made pursuant to the MOFA.
  4. Accordingly, Westgem is estopped from alleging that it was not in default under the terms of the MOFA by reason of the second Cost Overrun and the estoppel provides a defence to Westgem's contractual claims based on the proposition that the second Cost Overrun had not occurred.

PART 3 - Salta Stoppage and Salta Termination claims

Introduction
  1. The Salta Stoppage and Salta Termination claims involve allegations of contraventions of the statutory prohibitions against misleading or deceptive conduct, unconscionable conduct, and breach of the Code Conduct Term.
  2. The claims are based on the proposition that between 20 November 2009 and 25 February 2010, the Finance Parties' conduct conveyed to Salta that Westgem was in breach of the MOFA in such a way that the Finance Parties were entitled to, and were prepared to, withhold advances for the purpose of meeting Westgem's payment obligations to Salta under the Salta Building Contract, (termed the 'Capacity to Pay Conduct' and 'Capacity to Pay Representation').
  3. The conduct was alleged to be misleading because Westgem had not committed a breach of the MOFA on which the Finance Parties were prepared to rely in order to deprive Westgem of its ability to meet its payment obligations to Salta (described in closing as its primary case). Alternatively, Westgem had not committed a breach of the MOFA which entitled the Finance Parties to withhold advances (described in closing as its alternative case). Westgem contended these alternative facts reflected its 'true capacity to pay'.
  4. Westgem alleges that the Finance Parties' misleading or deceptive conduct caused Salta to suspend work under the Salta Building Contract on 8 February 2010 and terminate the Salta Building Contract on 25 February 2010. Westgem claims it suffered loss because if Salta had not terminated the Salta Building Contract, the development would have been completed without the delays suffered and without additional costs incurred as a consequence of the stoppage and termination.
  5. As a separate head of claim, Mr Pourzand's company Oakcure claims Salta's stoppage and termination deprived it of the opportunity to sell its interest in the development to, Charter Hall. The Finance Parties deny that Westgem or Oakcure suffered losses of the nature alleged.
  6. Westgem's senior counsel opened the case on the basis that the construction of the Cost Overrun provisions was the 'foundational issue' of Westgem's claims and that if Westgem was wrong on the construction of those provisions, Westgem's case 'gets very difficult'.[445] He went on to say of the Finance Parties' refusal to provide an assurance to Salta that Westgem was not in breach of the MOFA that this was 'a reasonable position, if you think that your customer is in default', before adding 'but, of course, our case is we weren't'.[446] This approach reflected Westgem's written outline of opening submissions in which it was contended that the 'Salta Stoppage and Salta Termination part of the case depends on the existence of the Second Alleged Cost Overrun'.
  7. In summary, my findings on this part of Westgem's claims are as follows:

(a) The Finance Parties' conduct did not convey or communicate anything to Salta about Westgem's capacity to pay. The circumstances were such that there was no reasonable expectation that the Finance Parties would disclose any information about Westgem's capacity to pay Salta and its failure to do so was not misleading.

(b) Westgem's 'true capacity to pay' was not as it contended. Westgem had committed a breach of the MOFA - the second Cost Overrun breach - on which the Financiers were prepared to rely to withhold advances.

(c) The Financiers' conduct was not unconscionable and, had the Code Conduct Term been a term of the MOFA, the Financiers' conduct involved no breach of it.

(d) It was Westgem's conduct that caused Salta to suspend work and thereafter to terminate the Salta Building Contract.

  1. The structure of the balance of this part of the reasons is as follows:

(a) relevant contractual provisions;

(b) the facts;

(c) the pleaded case;

(d) the relevant legal principles; and

(e) consideration.

Relevant provisions of the Salta Building Contract and Builder's Side Deed
  1. GC 42.1 of the Salta Building Contract conferred on Salta a qualified right to seek evidence from Westgem that it had the capacity to meet its payment obligations under the Salta Building Contract.
  2. GC 44.7 provided that a failure to provide evidence in breach of cl 42.1 constituted a 'substantial breach of contract' entitling Salta to give Westgem a written notice to show cause why Salta should not exercise a right referred to in GC 44.9. A show cause notice was required to specify the time and date by which Westgem must show cause and that date could not be less than seven days from the date of the notice.
  3. GC 44.9 of the Salta Building Contract set out Salta's rights (defined in the statement of claim as the GC 44.9 rights) in the event that Westgem failed to show reasonable cause - it provided:[447]
If by the time specified in a notice under Clause 44.7 [Westgem] fails to show reasonable cause why [Salta] should not exercise a right referred to in Clause 44.9, [Salta] may by notice in writing to [Westgem] suspend the whole or any part of the work under the Contract.

[Salta] shall lift the suspension if [Westgem] remedies the breach but if within 28 days after the suspension under Clause 44.9, [Westgem] fails to remedy the breach or, if the breach is not capable of remedy, fails to make any other arrangements to the reasonable satisfaction of [Salta], [Salta] may by notice in writing to [Westgem] terminate the Contract.

The [Salta] shall be entitled to recover from the [Westgem] any damages incurred by the [Salta] by reason of the suspension.
  1. The Builder's Side Deed contained provisions restricting the right of Salta and Westgem to vary the works under the Salta Building Contract without the Security Trustee's approval. Clause 3.3 of the Builder's Side Deed provided:[448]
3.3 Variations to the Works
(1) Neither the Borrower nor the Builder may without the prior consent of the Security Trustee perform a Variation to the Works or do anything which has the effect of a Variation to the Works unless the Variation or other act is a Permitted Variation.

(2) The Borrower must promptly inform the Security Trustee of any Permitted Variations.
  1. In its closing submissions Westgem placed particular reliance on the 'right to remedy' provisions of the Builder's Side Deed. These provisions required Salta to give the Security Trustee a copy of any 'show cause' notice at the same time as it was given to Westgem and required Salta to give the Security Trustee the opportunity to remedy the breach specified in the 'show cause' notice. The 'right to remedy' was governed by cl 3.5 and cl 3.5A of the Builder's Side Deed. For present purposes, it is sufficient to set out the provisions of cl 3.5(1) that were as follows:
3.5 Security Trustee's right to remedy
(1) Subject to clause 7, if the Builder proposes to terminate or suspend the Works or the Building Contract due to a default under the Building Contract and that default is remediable, it must:
(a) give the Security Trustee:

(i) in the case of a failure to pay money owing by the Borrower To the Contractor and under the Building Contract, 10 Business Days; and

(ii) in any other case, 21 Business Days,

from:

(iii) in the case of suspension, the date on which the Suspension Show Cause Notice Period expires; or

(iv) in the case of termination, the date on which the Termination Cause Notice Period expires,

to remedy the default (in each case, the Remedy Period);

(b) promptly provide the Security Trustee with sufficient information about the default to enable the Security Trustee to remedy it within the relevant Remedy Period; and

(c) not exercise any rights it has in relation to the default within the relevant Remedy Period unless the Security Trustee otherwise consents.[449]
The facts
  1. The primary facts were not controversial - they were largely established by the contemporaneous documents.

October 2008 - July 2009

  1. By July 2009 the relationship between Salta and Westgem had been strained for several months (vividly evidenced by the exchange of rancorous emails in April 2009 between Mr Tarascio and Mr Frank Saraceni over the IFO fee). Salta had issued show cause notices to Westgem in respect of its progress claims 24 and 25.[450] These related to breaches of the Salta Building Contract alleged to arise from the Superintendent's failure to issue payment certificates and to make payments to Salta within 14 days of receipt of progress claims in respect of work completed up to 30 April 2009 and 31 May 2009. The notice to show cause in respect of progress claim 25 alleged Westgem had made a short payment of approximately $1 million less than the amount certified.

Salta's 15 July 2009 letter

  1. On 15 July 2009 Mr Sam Tarascio of Salta sent a letter to Mr Frank Saraceni expressing concern about the state of the relationship between Salta and Westgem.[451] This letter provides an insight into the problems with the Salta Building Contract as seen from Salta's perspective in mid-2009. Mr Tarascio restated the key issue for Salta in relation to the project cost as it had been outlined at the July 2009 PCG meeting as follows:
In relation to the project cost/final contract sum I restate the key issue for Salta outlined to you at the PCG. This issue revolves around the operation of the contract requiring Salta to proceed with Superintendant's Instructions once they are given, despite the cost of the instruction not necessarily being agreed to at the time it is given. There is a large volume of work that has been instructed, for which there is no agreement on the price, and in some cases, the scope of the work. This has resulted in a situation whereby Salta's committed cost to complete the project is well in excess of the formally authorised contract sum by Westgem. Whilst we take on board your reassurances that 'Salta will be paid fairly for the work that it has done', it is also unreasonable to expect that we carry such a large discrepancy in cost to complete versus awarded contract sum. We really need you to confirm your intentions to pay us for the value of work carried out in performing the Contract including formally approving the necessary variations and providing a contract sum adjustment.

I am also mindful of your obligations under the Builder's Side Deed which:
  1. Require you to gain consent from the Security Trustee for variations which are not 'Permitted Variations'; and
  2. Requires you to inform the Security Trustee of any Permitted Variations.
...

In relation to project costs it is important for:
  1. Salta Constructions to be comfortable that it will receive fair payment to cover its cost and margin.
  2. Westgem to be comfortable that it is able to fund the project through to completion.
...

The solution

Salta Constructions is prepared to discuss a new 'line in the sand' on this project. This would involve negotiation of a new contract sum, new date for practical completion, and agreed scope of works.

...

Frank, I would strongly encourage you to consider this approach. I strongly believe that the bank, via its QS, has a feel for where this project is heading in terms of cost and time. It is best to put legacy issues behind us by agreeing the new parameters of the Project to give all parties certainty, and most importantly to relieve our project teams of the wasted energy involved in arguing the past.

... (emphasis in original)
  1. Under the heading 'The solution' Mr Tarascio set out what he saw as the essential elements of a new contract between Salta and Westgem involving a new contract sum, a new date for practical completion and a new scope of works.

Westgem's position late July 2009

  1. On 29 July 2009 Mr Clohessy sent an email to Mr Nagle at Bankwest attaching Mr Frank Saraceni's response to Salta regarding a non‑binding expert appraisal relating to Salta's extension of time claim No 1.[452] In his email to Mr Nagle, Mr Clohessy referred to Mr Saraceni's response as, 'Frank's response to Salta's latest inane ramblings ...' and expressed the belief that Salta was 'trying to use the bank to put pressure on Westgem when in fact it will probably only seek to raise concerns about Salta's viability going forward.'[453]
  2. On 30 July 2009 Mr Frank Saraceni sent an email to Mr Tarascio and Mr Hume of Salta expressing concern about the increasing number of variation and provisional sum expenditure requests.[454] He complained that these were putting unnecessary stress on Westgem's and the Superintendent's staff and budget. Mr Saraceni stated that any of Salta's project staff who did not understand or were not competent enough to follow clear principles and contract requirements should be removed from the Project. Mr Tarascio responded by email in forceful terms and among other things stated:[455]
With respect to provisional sums, you were aware that these were badly under provisioned prior to commencement of the job and you instructed us on the numbers to insert into the contract for provisional sums. This is why we made it clear in the contract that we would take no responsibility for the amounts you required us to insert into the contract. As is our obligation to do so, we are now highlighting any provisional sums that we are showing to be inadequate and if this is causing you a problem with your budgets Salta takes no responsibility whatsoever for this.

You are badly under resourced to manage a project of this nature and we have informed you of this on numerous occasions. I would suggest that any issues surrounding the processing of variations and SI's are very much the result of this under resourcing.
  1. On 3 August 2009 Mr Frank Saraceni replied to Mr Tarascio's letter of 15 July 2009.[456] In response to Mr Tarascio's outline of the key issue of project costs, Mr Frank Saraceni expressed disappointment at Salta's lack of assistance in controlling costs and the great number of 'unnecessary' variations and extension of time claims tying up valuable resources. Mr Saraceni said that Westgem and Salta were poles apart and that Mr Tarascio's view was 'far too biased' and suggested that previous attempts at negotiation had failed because of the mindset that 'Salta were blameless'. Mr Saraceni set out a plan designed to establish whether there was any common ground which might form the basis for Mr Tarascio's proposal to move forward.

Salta's delay cost claim

  1. On 4 August 2009 Salta issued a delay cost claim for the period 6 July 2007 and 8 December 2008 in the sum of $10,212,308.[457]

Salta's 4 August 2009 show cause notice

  1. On 4 August 2009 Salta issued a show cause notice to Westgem in relation to the late certification and payment of the full amount of its progress claim No 26 for work completed to 30 June 2009.[458] The Superintendent was required to issue a payment certificate by 15 July 2009 but did not do so until 22 July 2009. The full amount certified was not paid.

Salta's 12 August 2009 capacity to pay notice

  1. On 12 August 2009 Salta issued a capacity to pay notice in which it stated that its estimate of the likely final cost of the Project was $321,689,771.31 and it provided a breakdown of that sum.[459] The notice required Westgem to produce documentary evidence by 21 August 2009 'to the reasonable satisfaction of [Salta]' that Westgem had the capacity to 'pay all of [Salta's] claims, irrespective of whether [Westgem] believes that, after any dispute, the final amount payable will be less than those claims'. In the notice Salta referred to the MOFA as 'the multi-option facility agreement for the value of $327,000,000' and stated that it was clear that if the facility was all that was available to Westgem for payment of the project Works (defined in the notice as 'the Work under the Contract being performed by the Contractor plus the Provisional Sum work to be performed by others'), the Facility Agreement amount would be significantly exceeded and Westgem would not have the capacity to pay the full cost of the Works.
  2. I interpolate the Financiers contended that there was nothing in the capacity to pay notice of 12 August 2009 to suggest that Salta was aware of Bankwest's view that the first Cost Overrun had occurred and that Westgem had committed any breach of the MOFA. In a letter sent by Salta to Westgem on 14 December 2009 Salta stated that the 12 August 2009 capacity to pay notice:[460]
... arose from Salta's concern about the rapidly escalating cost of the project caused by the extensive variations and provisional sum expenditure ordered by the Superintendent on behalf of Westgem.
  1. I find that at the time the 12 August 2009 notice was prepared and served Salta was not aware of the first Cost Overrun or that the Financiers considered that Westgem had committed a breach of the MOFA. I make this finding in part on the basis of the statement contained in Salta's letter of 14 December 2009 and in part on the basis of an inference drawn from the absence of any mention of a Cost Overrun or possible breach of the MOFA in the 12 August 2009 capacity to pay notice or in the 14 December 2009 letter.

Westgem's response to Salta's capacity to pay notice

  1. Mr Clohessy described Salta's capacity to pay notice as 'inept attempts to cause [Westgem] grief' and that Salta's number was 'so far off the Bank's QS numbers it's a joke'.[461]
  2. Mr Frank Saraceni sought legal advice about the capacity to pay notice. He instructed Westgem's lawyers, Jackson McDonald, that the actual contract amount was $232 million and that 'the Bank's own QS told them it could at the end of the day with contingencies end up at $243 million'. Mr Frank Saraceni stated that his assessment was that Salta was attempting to 'claim a substantial breach ... to have the contract determined in some way by the courts as they are getting no joy from the contract the way it is' and 'Salta are 5 months behind on the contract and are losing money on the contract and desperate ...'.[462]
  3. Westgem took steps to make arrangements to engage another builder, Arccon, to replace Salta. Arccon prepared a detailed proposal for Westgem's consideration.[463]
  4. On 21 August 2009 Jackson McDonald sent a letter to Salta, on Westgem's behalf, in response to its capacity to pay notice.[464] Jackson McDonald denied that Salta had reasonable grounds for requesting evidence of Westgem's capacity to pay. Jackson McDonald contended that 'arguably' cl 42.1 of the Salta Building Contract only required Westgem to provide information to demonstrate that it had the capacity to make the next progress payment or, at most, 'the current adjusted Contract Sum' as opposed to Salta's 'estimate of the likely final costs of the Project'. The letter attached Westgem's calculations of the adjusted contract sum. The letter also contained statements to the effect that Salta's assessment of the final contract sum required adjustment by the removal of the amounts that have not been assessed or approved by the Superintendent. Jackson McDonald described Salta's variation and extension of time claims as 'unsubstantiated' and the RFI claims as 'frivolous' and that the claims were all part of 'a concerted attempt by Salta to deflect attention from Salta's failure to proceed with the works with due expedition and without delay'.
  5. Attached to Jackson McDonald's letter was a letter from Bankwest to Westgem dated 21 August 2009 which Jackson McDonald described as 'stating in effect that Westgem has finance facilities in place sufficient to meet the balance of its "payment obligations under the Contract"'. In fact this is not what was stated in Bankwest's letter. The letter, which was addressed to Westgem, was in the following terms:[465]
Dear Sir

We refer to our previous discussions and provide the following information in respect to the Multi Option Facility Agreement as at 5 August 2009.

Facility status as at 5 August 2009

Limit
Drawn
Undrawn
Multi-Option Facility
$316,000,000
$172,931,536.04
$143,068,463.96
Letter of Credit
Facility
$ 8,200,000
$ 7,600,000
$ 600,000
Overdraft (GST Float)
Facility
$ 3,000,000
$ 2,999.237.20
$ 762.80
Total
$327,200.000.00
$183,530,773.24
$143,669.226.76


Please note that the availability of future funding remains subject to compliance with the terms of the Multi-Option Facility Agreement and other Transaction Documents.

Please feel free to contact me if you have any questions.

Yours faithfully

Stephen Nagle

Director, Property Finance

BANK OF WESTERN AUSTRALIA LTD as Facility Agent
  1. Discussions between Salta and Westgem took place. Mr Frank Saraceni met with representatives of Salta on 26 August 2009 to discuss a possible negotiated outcome.[466] The negotiations were unsuccessful. They generated a further contentious exchange of emails between Mr Tarascio and Mr Frank Saraceni.
  2. On 3 September 2009 Mr Brian Cargill of Salta sent an email to Mr Frank Saraceni inquiring whether Mr Frank Saraceni wished to proceed with negotiations and stating that if agreement was not reached by close of business on 4 September 2019 Salta would issue its notices.[467] Mr Frank Saraceni responded in the negative.

Salta's 4 September 2009 capacity to pay show cause notice

  1. On 4 September 2009 Salta issued a show cause notice under cl 44.8 of the Salta Building Contract in respect of what it considered to be Westgem's failure to provide evidence addressing Salta's concerns about Westgem's capacity to pay Salta's assessment of the final cost to complete of $322 million.[468] The notice required Westgem to 'show cause' by 18 September 2009. In the notice Salta referred to Bankwest's letter of 21 August 2009 and said that it 'was not reasonably satisfied with the evidence of the documentation produced ...'. The notice was followed by a further exchange of contentions communications between the parties.
  2. On 5 September 2009 Mr Tarascio asked Mr Frank Saraceni to set up a meeting with Mr Luke Saraceni and Mr Pourzand.
  3. On 14 September 2009 Salta's solicitors replied to Jackson McDonald's letter of 21 August 2009 and set out the documentation or evidence that Salta considered should be provided by Westgem to satisfy Salta of Westgem's capacity to pay.[469] Salta sought documents and evidence which went beyond a statement by the Financiers about the funds available under the MOFA.

Westgem's response to Salta's capacity to pay show cause notice

  1. On 18 September 2009 Mr Luke Saraceni sent a letter to Salta disputing Salta's Cost to Complete estimate of $322 million and maintained that Westgem's estimate of $243 million was accurate.[470] In a covering email Mr Saraceni stated that he was 'making other arrangements ... to address the more important issue of Salta's capacity to complete the works on time and on budget and will advise you next week in more detail of our strategy'.[471] Mr Saraceni complained that Salta was misusing the 'show cause' provisions of the Salta Building Contract for the purpose of coercing Westgem into accepting Salta's unsubstantiated claims regarding variations, time and value management. Mr Saraceni attached a further copy of Bankwest's letter of 21 August 2009 to his letter and stated that in the unlikely event that the adjusted Contract Sum ultimately exceeded the amount available under the Facility Agreement, Westgem had alternative sources of funding that it would utilise. Mr Saraceni said Westgem would provide evidence of the alternative sources of funding if and when the adjusted Contract Sum exceeded the amount available under the Facility Agreement. Mr Saraceni concluded his letter as follows:[472]
While Westgem is prepared to meet with Salta to discuss any genuine concerns Salta may have as to Westgem's capacity to 'meet its payment obligations under the Contract' and to the extent necessary involve its Financier in such discussions Westgem is not prepared to meet Salta's unreasonable demands that it provide evidence of its capacity to pay Salta $321,689,771.37.

Payment certificate 27 dispute

  1. On 18 September 2009 the Superintendent issued payment certificate 27 in relation to Salta's progress claim 28 for work completed to 31 August 2009 which certified $10,884,401.56 of the $20,042,640 claimed by Salta. On 29 September 2009 Salta commenced an application for adjudication against Westgem in relation to this progress claim.[473]

Westgem's 24 September 2009 show cause notice

  1. On 24 September 2009 Westgem issued a notice to Salta to show cause why Westgem should not terminate the Salta Building Contract by reason of the substantial breaches set out in the notice.[474] The breach cited by Westgem in its notice was constituted by a statement by Mr Tarascio in his email to Mr Frank Saraceni of 5 September 2009 (in which, as referred to above, he asked for a meeting with Mr Luke Saraceni and Mr Pourzand) that 'your refusal to fairly process our claims for variations, time and value management will leave us substantially short and unable to complete the job. The cost of an alternative builder completing would be well in excess of the fair and reasonable price we are prepared to negotiate with you'. Westgem's notice generated further contentious correspondence.
  2. On 1 October 2009 Salta issued a show cause notice in relation to Westgem's failure to pay the full amount of Salta's progress claim 28 for work completed up to 31 August 2009.[475] The notice required Westgem to show cause by 9 October 2009.
  3. On 2 October 2009 Salta responded to Mr Saraceni's letter of 18 September 2009 and stated, in effect, that its assessment of the likely forecast final cost had increased to $333,074,615.[476] In its letter Salta observed that 'no updated letter from Bankwest' had been provided and that Salta had not been provided with any details of the MOFA or any of the 'Transaction Documents' referred to in Bankwest's letter of 21 August 2009. Salta complained about the lack of detailed information about the MOFA including that it was unaware of: how each of the stated limits for the three facilities referred to in the letter were established; the facility conditions applicable to each facility; and how the facility amounts were to be applied to the various project costs.
  4. Also on 2 October 2009, Salta sought confirmation from Westgem that variations that it had been instructed to undertake under the Salta Building Contract were properly approved under the Builder's Side Deed by the Security Trustee and were Permitted Variations.[477] Salta said that if the variations were not permitted it could not perform the works associated with the variations. The aggregate of the 'submitted value' of the variations was $6,888,151.
  5. On 12 October 2009 Salta sent a letter to the Security Trustee stating that Salta had issued a notice to show cause to Westgem on 1 October 2009 in relation to Westgem's failure to pay money owing under the Salta Building Contract and that if payment was not made within 5 days Salta must suspend work.[478]
  6. On 12 October 2009 Mr Tarascio expressed his concerns to Salta's internal and external lawyers about the conduct of Mr Frank Saraceni and sought advice about the possibility of removing the Superintendent and what Salta's position would be if it terminated the Salta Building Contract.[479] Mr Tarascio's comments about termination indicate not only the extent of Salta's lack of confidence in Mr Frank Saraceni but also his concern that the position Salta found itself in could threaten its financial viability. Mr Tarascio wrote:[480]
The conduct of the Superintendant and the Superintendant's Representatives, but particularly the Superintendant (Frank Saraceni) at our PCG last week was totally unacceptable and I believe that his performance would not only have been of great concern to Salta's project team, but also to the attendees from the bank. I believe this meeting clearly highlighted the Superintendant's complete misunderstand of the Superintendant's function in a project of this nature and demonstrated his clear bias in favour of the Principal. In particular the Superintendant's statements that:
  1. There is no chance of any of our Extensions of Time gaining approval;
  2. That we are not entitled to any payment of our August claim because the principal has issued a notice to show cause; and
  3. That we should 'bring on the disputes';
All demonstrate that he is not acting in the best interests of the project.

The Superintendant's actions and sheer incompetency to date together with his failure to properly perform his duties are now beginning to have serious consequences in terms of the project cash flow. As you are aware, the Principal has not yet made payment for our August claim of $20 million, for which the Superintendant certified only $10 million. In addition, I have serious doubts that the Superintendant will certify any of our September claim. As we stand, Salta Constructions has carried out work for August, September, and half of October. Without trying to use exact numbers, the total value of work carried out by Salta over this period is in the range of $50 to $60 million. This is work that has been carried out and therefore Salta is committed to paying its subcontractors for these works.

Can you confirm to me what Salta's rights in relation to receiving payment for these works are in the event:
  1. Salta terminates or repudiates the construction contract.
  2. The Principal terminates or repudiates the contract.
  3. In respect of termination or repudiation by either party, I assume it will be the Superintendent's role to determine the amount payable to Salta. Given the comments above, it is likely he will not certify a value of works satisfactory to us. What would be our next step if this is the case? Can we adjudicate if the contract is at an end.
  4. Can you please clarify the difference between repudiation and termination?
  5. Mr Tarascio concluded:
The conduct of the Superintendent (and Principal) needs to be addressed urgently as the viability of Salta Constructions is being affected.
  1. On 21 October 2009 Mr Tarascio sent a letter to Mr Luke Saraceni setting out Salta's contentions that there had been serious breaches of the Salta Building Contract and giving notice of Salta's claim for substantial loss and damage.[481] Echoing the observations made in his email to Salta's lawyers, Mr Tarascio complained about the effect that the Superintendent's conduct was having on Salta's cashflow and argued that the Superintendent should be removed and replaced immediately with an independent party.
  2. On 23 October 2009 Salta sent a letter to Westgem and the Security Trustee stating that: Westgem had failed to respond to its show cause notice of 4 September 2009 (issued in respect of the capacity to pay notice of 12 August 2009); it remained in substantial breach; and Salta would exercise its rights to suspend works under the Salta Building Contract.[482]
  3. On 29 October 2009 Westgem issued a notice to show cause to Salta based on Salta's notice of suspension dated 23 October 2009.[483] Also on 29 October 2009 Westgem responded to Salta on the issue of 'Permitted Variations' and stated:[484]
All of the subject Variation Instructions are issued within the parameters of budgets issued to and accepted by the Security Trustee and are accordingly either Permitted Variations as that term is defined in the Builders' Side Deed or are Variations issued with the consent of the Security Trustee.

...

Further, Westgem confirm that it accepts liability to pay for all Variations instructed by the Superintendent under the Building Contract regardless of whether or not such Variation constitutes a Permitted Variation or has otherwise been consented to by the Security Trustee under the terms of the Builders' Side Deed.

Westgem direct Salta to proceed with all Variation Instructions issued by the Superintendent and advise that Westgem will not accept any claims made by Salta arising out of its failure or refusal to proceed with Variation Instructions as directed by the Superintendent.
  1. On 18 November 2009 Salta sent a further letter to Mr Luke Saraceni complaining about the Superintendent and contending that Westgem was in breach of the Salta Building Contract by failing to ensure that the Superintendent acted in accordance with its terms.[485]

Salta requests a copy of the MOFA - 20 November 2009

  1. On 20 November 2009 Salta sent a letter to the Security Trustee and referred to its show cause notice of 4 September 2009 and asked the Security Trustee to:[486]
    1. provide us with a copy of the Facility Agreement with Westgem, so that we can satisfy ourselves that there are no breaches of the lender's Financial Covenant. If there are, we will advise you and seek your confirmation that such breaches have been waived by you;
    2. confirm that you are unaware of any breach by Westgem of its Financial Covenants;
    3. confirm that, to your knowledge, there has been no Event of Default;
    4. confirm that you are unaware of anything which would entitle the lenders to withhold advances pursuant to the Facility Agreement.
  2. Salta went on to record:
We are anxious to confirm that the money available pursuant to the Facility Agreement is available to discharge the liabilities of Westgem under the building contract for Raine Square. Our building contract with Westgem entitles us to such confirmation. Failure to provide such confirmation is a matter which would have to be considered very seriously by Salta, having regard to the very significant sums of money that are and will become due. In our opinion it would give rise to rights under clause 44.9 of the building contract. We look forward to your advice in this regard.

Security Trustee responds to Salta's request for a copy of MOFA ‑ 26 November 2009

  1. On 26 November 2009 the Security Trustee sent a letter to Salta in response to Salta's letter of 20 November 2009. Relevantly, the Security Trustee's letter read as follows:[487]
We make the following comments in reply to the Builder's Letter:
  1. the Borrower responded to the Builder's First Show Cause Notice, and specifically to the Builder's request that the Borrower provide evidence of its capacity to meet its payment obligations under the Building Contract, by way of the Borrower's Response Letter; and
  2. the respective contractual rights and obligations as between the Security Trustee and the Builder are governed exclusively by way of the [Builder's Side Deed]. Under the terms of the [Builder's Side Deed] the Security Trustee is not obliged to provide the information requested by the Builder in the Builder's Request Letter.
  3. On 27 November 2009 Salta responded to the Security Trustee's letter of 26 November 2009 stating that the failure to provide the information requested by Salta gave rise to significant rights on Salta's part.[488] In the course of a lengthy exposition of its position Salta observed that Bankwest's letter of 21 August 2009 was qualified by the statement to the effect that Westgem's ability to draw on the MOFA was subject to compliance with the terms of the MOFA and other Transaction Documents. Salta stated that Jackson McDonald had not provided evidence that established Westgem had complied with the MOFA and thus, in effect, there had been no adequate response to the capacity to pay notice. The concluding paragraphs of Salta's letter read as follows:
There is no documentation or evidence which has been provided to Salta by Westgem or BOSI proving that Westgem has a capacity to meet its payment obligations under the Contract. The refusal by BOSI to provide the information requested is most curious and leads to an inference that BOSI is unable to give the assurances sought in Salta's letter of 20 November 2009.

Of course Salta reserves all rights in relation to its show cause notice. However, it wishes to see this contract completed; subject to it being paid. Accordingly, we will provide you with a further 10 business days from today, to give BOSI or Westgem (a copy of this letter having been provided to it) the further opportunity to provide the necessary information.

Salta's 4 December 2009 capacity to pay notice

  1. On 4 December 2009 Salta issued a further capacity to pay notice to Westgem.[489] The notice was in the form of a letter from Salta in which it referred to its notice of 12 August 2009 and maintained that the provision by Westgem of Bankwest's letter of 21 August 2009 did not amount to evidence of Westgem's capacity to pay. Salta requested Westgem provide it with copies of the Facility Agreement and all other relevant documents together with evidence that there had been sufficient compliance with the terms of the MOFA that there was no basis for the Financiers to refuse to make available sufficient funds to meet Westgem's payment obligations under the Salta Building Contract. Salta contended also that Westgem had failed to obtain the Security Trustee's consent to variations. Salta stated that only nine of the 29 variations referred to in Salta's letter of 2 October 2009 were the subject of BOSI's consent. Salta stated:[490]
Further, in these circumstances, we consider that you have breached clause 3.3 of the Builder's Side Deed. Consequently, we are very concerned that the Financiers may refuse to fund Variations which are neither Permitted Variations or Variations in respect of which BOSI has consented.
  1. On 8 December 2009 the Security Trustee responded to Salta's letter of 27 November 2009. It referred to the comments contained in its 26 November 2009 letter and stated:[491]
... given that the Side Deed does not oblige the Security Trustee to provide the information requested by the Builder in its letter dated 20 November 2009, there is no reasonable basis for drawing any inferences whatsoever in respect of the Security Trustee or any other Finance Party.

Salta's internal assessment - 10 December 2009

  1. On 10 December 2009 Mr Steve Gerrard, a Salta executive with the title Commercial Manager, sent an email to Mr Regan and Mr Cargill of Salta setting out his assessment of Salta's position. Both sides placed reliance on this email. Mr Gerrard summarised Salta's views as expressed in its communications with Westgem and the Security Trustee. The email provides an insight into Salta's strategy and tactics. It is a significant email and I reproduce its full text:[492]
Brian, here are my thoughts on the current situation we face in relation to the potential suspension of the work on Raine Square. I am conscious that any suspension action would be unusual for a main contractor and that we would normally allow the contract to take its course. I have tried to set out the issues we face and weigh them up against the risks - here are my thoughts:

We have:
  1. $20m in losses being in my estimation - $6m on structure and the remeasure, $10m on delays, $4m on variations and other claims
  2. A Superintendent - brother of the Principal - and apparently the appointed gatekeeper for Westgem, who together with his rep's has a serious conflict of interest and is making negative statements, contract interpretations, determinations and assessments in relation to Salta entitlements that have been for 2 years having serious consequences on Salta and its financial capacity to continue
  3. The Bank who will stand (hide) behind the Side Deed and the Building Contract in order to ensure that it is not exposed and is very comfortable that Salta has proceeded with the additional unapproved work and does feel compelled to assist Salta unless that also assists/protects the Bank. The Bank's primary aim is to get Salta to completion asap with minimal disruption and exposure to them - that is their only corporate aim
  4. A raft of unapproved variations, re-measurements, provisional sum expenditures and other claims that we have substantially commenced and any not started will certainly will have done so within the next 3 months meaning the [Superintendent's] need to engage fairly with us keeps diminishing
  5. Substantial arguments about delays and costs which will always take a lot of energy to resolve and win, if we are right and if we can prove them
  6. A remote project with itinerant staff that will ultimately be unreliable in a court action in circumstances where the client has no rational reason to pay any monies and could potentially kill the company - Westgem - as soon as the side deed has outlived its usefulness and as a consequence the Bank does not need to step in
  7. The prospect of debilitating court action which in my experience management slowly loses its appetite for as it drags on
  8. The prospect of increased negative cash flow being a threat to the construction business, whereas we should be about $15 cash positive
  9. A contract that arguably has not been properly followed, e.g., in relation to late/missing notices of variations and eot's, which may stymie our litigation action and require extensive argument to be successful
  10. A Principal who will not engage with us in any meaningful way, who has not shown his capacity to pay for the project and hides behind misleading Bank documents because he at one stage did not actually have the capacity. We need to get him to the table very quickly
We now have:
  1. An opportunity to stop future variation work prohibited under the side deed and force proper valuations to be made by the Super and be provided to the Bank. This is important because our belief is that Westgem has not represented the true financial position to the Bank in the past, hoping of course that they will get to the end of the project without having to do so
  2. An opportunity to suspend work on variations and other substantial parts (or all) of the project on the basis of item 11, in that Westgem have not disclosed the true financial position and do not have capacity to pay
  3. An opportunity to get Westgem to commit the required funding and in the process accept that the funding will be used on this project
  4. An opportunity to change the Superintendent or override him and obtain speedy and fair valuations on all claims
  5. A potential 3 year litigation to recover our money unless something changes
We have created:
  1. A solid legal position that has been built to climax and allow our rights to be exercised, in circumstances where the failure to exercise can mean that the rights are no longer there unless some other special different circumstances arise.
  2. A team that now has prepared and submitted many of the claims – and enough backup for us to be able to show the Principal that they are not illegitimate
The downside:
  1. Westgem prove their capacity to pay
  2. The Bank consents to all future variations
  3. Westgem issues a show cause notice and suspends payment - an event that could be further considered by us prior to Salta being in a position of an unremedied breach that leads to termination
My view is to suspend now - on Monday - on a substantial portion of the work

This brings serious focus on the Super and the pricing and the proper arguments about Salta's rights that will leave Westgem no time to be creative in their rejections of the claims and in my experience might act like a truth serum for them.

I believe Luke is using Frank as a shield and he will no longer be able to do this if we act

I trust this view assists you in the further deliberations
  1. I infer that the reference to 'misleading Bank documents' in par 10 was a reference to Bankwest's letter of 21 August 2009. I draw that inference because it was the only document provided on behalf of the Financiers that had been relied upon by Westgem to that date and the pejorative reference to 'misleading Bank documents' reflected the view held by Salta that, although the letter was put forward by Westgem as proof of its capacity to pay, the qualified nature of the material statement in it deprived the letter of that effect.

Salta's 14 December 2009 notices

  1. On 14 December 2009 Salta issued a notice to show cause in relation to the capacity to pay notice served by it on 4 December 2009.[493] The notice to show cause required a response by 22 December 2009.
  2. On 14 December 2009 Salta also sent a letter to Westgem giving notice of suspension of all variation work which was not permitted variation work or work in respect of which the Security Trustee had not consented and all other works dependent on such variations. Salta justified the proposed suspension on the basis of Westgem's failure to provide evidence it had the capacity to meet its payment obligations under the Salta Building Contract. In its letter Salta rehearsed the arguments raised in earlier correspondence about the inadequacy of Bankwest's letter of 21 August 2009 as evidence of Westgem's capacity to pay. In addition Salta made the point that in their letter of 21 August 2009 Jackson McDonald had 'under-valued Westgem's obligation to pay Salta' and stated: [494]
The banking facilities relied upon by Westgem, if otherwise available, would not have satisfied Westgem's obligation to pay Salta.

Salta summarised its position as follows:

  1. Neither Westgem nor the Security Trustee have remedied Westgem's breach under clause 42.1. In particular, no evidence or documentation has been provided to the Contractor's reasonable satisfaction that:
(a) there has been compliance with the terms of the Multi Option Facility Agreement and Transaction Documents, to ensure that the financiers have a continuing obligation to advance moneys as and when necessary to meet Westgem's liabilities to Salta; and

(b) Westgem has the capacity to pay for the extensive variations ordered and delay costs or damages payable. When these variations and other costs are properly valued and the contract price adjusted, the amount which will be payable to Salta exceeds that which will be available under the Multi Option Facility Agreement and other facilities apparently available to Westgem (assuming Westgem has complied with the Multi Option Facility Agreement and Other Transaction Documents).
  1. On 15 December 2009 Salta suspended works on all non-permitted variations and works dependent upon those variations. In Mr Gowdie's evidence, which I accept, he said that the suspension brought works on the site to a standstill.[495]

Westgem's request for letter from Facility Agent

  1. On 15 December 2009 Mr Frank Saraceni sent an email to Mr Nagle and Mr Clohessy in which he said that Westgem's lawyer had recommended that it seek the Security Trustee's assistance. Mr Frank Saraceni recommended that the Security Trustee consider a simple letter which Westgem could submit as part of its show cause response to Salta along the lines:[496]
The Security Trustee has undertaken an independent investigation of the current and anticipated end project costs and is of the belief that to the best of its knowledge the project will have adequate facilities in place for completion.
  1. Mr Pavisich explained in his evidence that the Financiers could not provide a letter as requested by Mr Saraceni because the second Cost Overrun has not been cured and an event of default was in existence.[497] Mr Pavisich said that he told Mr Luke Saraceni that the Financiers could not provide a letter of the nature recommended by Mr Frank Saraceni. I accept Mr Pavisich's evidence.

Westgem contends it has capacity to pay - 22 December 2009

  1. On 22 December 2009 Mr Luke Saraceni responded to Salta's 14 December 2009 notice to show cause.[498] Mr Saraceni repeated the argument to the effect that Westgem was only obliged to demonstrate that it had the capacity to pay any amount that was certified as due and payable at the time it was called upon to demonstrate its capacity to pay. Mr Saraceni stated:[499]
Westgem does not accept that Salta has any reasonable grounds to request Westgem to provide documentation or evidence of Westgem's capacity to meet its payment obligations under the contract when all payments to date required by the contract have been met and circumstances where the Security Trustee is aware of all budgets on the project including those projected by Salta and the full asset liability of Westgem and in circumstances where the Security Trustee has not notified Salta of any concerns in regards to Westgem's capacity to meet its payment obligations under the contract.

The bank's facility has previously been confirmed as not being exceeded nor have the certified and issued works exceeded the facility and the only substantial expenditure remaining to be made by Westgem relates to the construction cost of the Project, as Salta are aware.

Notwithstanding Westgem's position that it is under no obligation to produce any further documentation or evidence of its capacity to meet its payment obligations under the contract, Westgem encloses herewith a letter from its Accountants David Hewitt & Co setting out advice in relation to Westgem's capacity to meet its payment obligations under the contract. David Hewitt & Co's advice is based on its independent review based of the Security Trustee's two independent Quantity Surveyor's final cost budget of $260m (excluding credits and IFO Works which is funded directly by the Bank) and which also exceeds Westgem's previous budget. This also substantially exceeds the contract amount let or certified to date.
  1. Mr Saraceni enclosed with his letter a letter from Westgem's accountant that read:[500]
We have been requested by [Westgem] which is currently constructing the Raine Square development to provide you with information concerning the current funding of the project.

... The bank report confirms that the current construction costs to completion, independently verified by external quantity surveyors, is funded by the bank together with an unsubstantial amount that will be provided from the substantial assets of the joint venturers. Based on the above the construction costs to completion are fully funded.

Please contact me if you require any further information.

Salta rejects Westgem's 22 December 2009 capacity to pay contentions

  1. On 24 December 2009 Salta sent a letter to the Security Trustee stating that it did not regard Westgem's 22 December 2009 response to its notice to show cause to be satisfactory and recording that Westgem's estimate of the final costs of $260 million was well short of Salta's own estimate.[501] Salta provided a lengthy and detailed explanation of why it considered Westgem's response to be inadequate. In summary Salta complained about the absence of any detail to support the assertions made in Westgem's letter of 22 December 2009. One of the matters addressed at some length by Salta was the apparent acceptance recorded in David Hewitt & Co's letter that there would be a shortfall between the total construction costs and the funding provided under the MOFA - described in the David Hewitt & Co letter as being 'unsubstantial'. Salta made the point that until it knew the amount of the shortfall it would was unable to consider whether the assets of the joint venturers would be sufficient to support the funding of it. Salta summarised its position as follows:[502]
All that has been provided by Westgem is mere assertion. This is not satisfactory from Salta's point of view. Nor is an offer to discuss matters after 11 January, because work will have resumed by then on that work which can proceed (ie that work which is not suspended), leaving Salta exposed to its financial detriment.

This issue needs to be resolved soon. If, as Westgem alleges it has arrangements in place with financiers and others, it should be a simple matter for it to provide documentation or evidence of this fact which would satisfy Salta. Its failure to do so is of great concern. If this issue is not resolved soon there is a real risk that Salta will be forced to terminate the Building Contract. While Salta would be very reluctant to take this course, it cannot proceed if satisfactory documentation or evidence as to Westgem's capacity to meet its payment obligations under the contract is not provided.
  1. Salta gave 21 Business Days' notice of its intention to 'terminate or suspend the works under the Building Contract due to the default of Westgem which is the subject of the show cause notice of 14 December 2009.'

The Financiers' position - December 2009

  1. On 22 December 2009 Mr Pavisich and Mr Nathan prepared the strategy paper for the Executive Credit Committee of Bankwest, to which I referred in the course of setting out the facts relating to the second Cost Overrun, and which led to the variation of the 18 November Letter Agreement.[503] In the strategy paper Mr Pavisich and Mr Nathan referred to Salta's show cause notices and urging that the Financiers do what they could to assist Westgem. They stated:
... In addition the Builder (Salta) has on a number of occasions issued Show Causes Notices questioning the Developer's (Westgem) capacity to financially complete the project wherein the consequence, of Westgem not being able to so demonstrate, being that Salta can ultimately terminate the contract. The Financiers should at this stage do everything in its power to avoid and/or not contribute to either this perception or outcome.
  1. Bankwest's Executive Credit Committee approved the recommendations contained in the 22 December 2009 strategy paper at a meeting held on 24 December 2009.[504]
  2. On about 11 January 2010 Mr Pavisich spoke to Mr Luke Saraceni and said that:[505]
I can't tell Salta that you have a facility of 'x' when documentation [to cure the Cost Overrun] isn't in place.

Finance Parties and Salta meet

  1. On 15 January 2010 representatives of the Finance Parties including Mr Pavisich and Mr McDonald along with Mr Wilson and Mr Gowdie of 333 met representatives of Salta including Mr Tarascio and Mr Regan. According to Mr Pavisich, whose evidence I accept, there was no discussion at the meeting about the status of the MOFA.[506] The focus of the discussions was on the difficulties Salta was experiencing with the construction process, specifically Salta did not know what it was supposed to be building. The Salta representatives proposed a revision of the contractual arrangements that would, in effect, have seen the Salta Building Contract converted into a cost plus contract supported by a cash flow facility provided by the Financiers. Mr Pavisich told the Salta representatives that any proposal for revised contractual arrangements would have to come from Salta and Westgem directly. Mr Pavisich's evidence was that he knew that a cost plus contract would not be acceptable to Westgem.

Salta and Westgem exchange correspondence regarding variations

  1. On 22 January 2010 Salta sent a letter to Westgem in relation to the dispute concerning non-permitted variations or prohibited variations. Referring to its letter of 4 December 2009 Salta stated:[507]
As a consequence Salta sought from Westgem documentation or evidence that Westgem had the capacity to meet its payment obligations. Westgem failed to provide documentation or evidence as requested in Salta's letter of 4 December 2009 which resulted in the Show Cause Notice of 14 December 2009. Westgem again failed to show cause and accordingly a further notice was issued to the Security Trustee on 24 December 2009. Unless Westgem or the Security Trustee demonstrate that funds are available to pay for the Prohibited Variations (ie the variations [in] respect of which consent is required and has not been received, irrespective of whether that work has been done or not) then all work may be suspended in accordance with the Show Cause Notice of 14 December 2009 and the subsequent notice to the Security Trustee of 24 December 2009. Accordingly, variations in respect of which consent has not been given are likely to delay the Works, even if those variations have been completed.

This is so because Westgem has failed to provide the evidence or documentation required by clause 42.1 of the Building Contract. Salta is or will shortly be entitled to suspend all work as a consequence of this failure. Therefore, it is critical to the continued performance of the works that Westgem obtain retrospectively consent in respect of all variations (whether completed not) and provide satisfactory documentation or evidence to establish Westgem's capacity to pay.
  1. On 25 January 2010 Westgem responded to Salta's letter of 22 January 2010 and contended that the variations directed by the Superintendent were either Permitted Variations or variations to which the Security Trustee had consented and that by suspending work on variations that Salta considered were Prohibited Variations Salta was in breach of the terms of the Salta Building Contract.[508]

27 January 2010 meeting

  1. On 27 January 2010 representatives of Westgem, Salta and the Financiers met.[509] The following account of the meeting is based on Mr Gowdie's contemporaneous note of the meeting as explained by him in his witness statement.[510] Those present at the meeting were: for Westgem, Mr Luke Saraceni, Mr Frank Saraceni and Mr Paul Fyfe from Jackson McDonald for some of the meeting; for the Financiers, Mr Pavisich, Mr Nagle, Mr McDonald (present by phone), Mr Berrick Wilson and Mr Gowdie (both of 333) and Mr Pazin, one of the Financiers' lawyers; for Salta, Mr Tarascio, Mr Regan, Mr Cargill and Mr Andrew Stephenson of Clayton Utz and Mr Richard Wilenski of Tottle Partners.

(a) Mr Stephenson said that there were two main issues, permitted variations and Westgem's capacity to pay. He said that Salta had raised Westgem's capacity to pay on two occasions and was still not satisfied. He said that Westgem's accountant's letter identified that Westgem did not have the capacity to pay and that there was an indication that a joint-venture party would pay and Salta wanted proof that was so. Mr Luke Saraceni or Mr Frank Saraceni disputed that Westgem's accountant's letter said that Westgem did not have the capacity to pay and said 'tell us what you want about capacity to pay', in response to which one of the Salta representatives referred him to Salta's letter of 24 December 2009 to which there had been no reply.

(b) It was said on Salta's behalf that it could suspend work from 29 January and termination could happen by mid-February but Salta would prefer to complete. Westgem said that if Salta suspended work it would undertake the work themselves and would not lose time. These exchanges gave rise to 'heavy' arguments between the parties.

(c) Mr Tarascio and Mr Luke Saraceni moved the discussion on to possible solutions. Mr Tarascio said Salta wanted drawings to be approved and signed off by the bank (so that there was a final 'for construction set of drawings') and for Salta to be told that its work was permitted. I infer this last point of discussion was directed to the issue of which variations had been permitted. One of the Salta representatives said Salta wanted an independent party to be appointed to determine current and previous issues under the Salta Building Contract.

(d) Mr Tarascio proposed an arrangement for payment he described as an 'interim contract sum' that involved the immediate payment to Salta of about 50% of what was in dispute, a sum of approximately $10 million, and that all subcontractors and Salta's overheads would be paid on a monthly basis with the total contract sum to be finalised three months following practical completion with any differences worked out at the end. If payments were not made on time then work would stop. At some point in the discussion Mr Tarascio said that Salta was approximately $10 million 'behind' and 'under water' on the job.

(e) Mr Saraceni said that Salta's proposal 'felt like [Westgem] was taking responsibility for the subcontractors' and asked how Salta would determine the subcontractors' costs to complete. He said that Westgem would need to see the current agreements with the subcontractors and that it would be difficult to make Salta's proposal work. Mr Saraceni said he was okay with all the points other than paying subcontractors and said something to the effect that 'the subcontractors will have [us] over a barrel'. Mr Stephenson disagreed and there was discussion about the possibility of bringing in new subcontractors.

(f) There was further discussion about the capacity to pay issue. Either Mr Luke Saraceni or Mr Frank Saraceni said that Salta was asking for too much on 'capacity to pay'. This appears to have been said in response to an argument from Salta that Westgem was required to demonstrate that it had the capacity to pay not just the contract sum under the Salta Building Contract but consultants' costs and the costs of other parties working on the Project. Mr Tarascio said he could not see how Salta's estimate of the costs to complete was wrong. He referred to $24 million in time extensions. There was a discussion in which Salta's cost to complete figure of $330 million was compared with Westgem's figure of $260 million.

(g) The meeting ended with one of Salta's representatives saying that they would put a proposal about a way forward in writing.

Salta's Proposed Way Forward

  1. Later on 27 January 2010 Salta provided a written proposal to Westgem entitled 'Proposed Way Forward'.[511] The objective of the proposals expressed to be 'to put in place a short-term solution to enable completion of construction of the Project'. The proposal identified four hurdles or 'key reasons' why completion of construction was at risk. Those reasons were identified as: establishment of approved work scope, the Principal's capacity to meet its payment obligations in accordance with cl 42.1 of the Building Contract, cash flow to complete the job and future changes to work scope. The proposal set out a solution to overcome each of the hurdles. To overcome the cash flow hurdle it was proposed that an interim amount of $15 million excluding GST be paid to Salta immediately.

Westgem's assessment of Salta's position

  1. In an email to Mr Pavisich, Mr Nagle and Mr Leber sent on 28 January 2010 (11.17 am) Mr Clohessy expressed the view that Salta's threats of suspension seemed 'to ring a bit hollow' and Salta's 'real requirements' were 'a cost plus contract going forward'. Mr Clohessy posed the question, 'Are there any other negatives attached with them suspending for a few days leading up to the 9th other than a small EOT claim and in all likelihood wont [sic] we still be arguing about the cost plus and other issues well after Fridays suspension date?'. Mr Clohessy suggested, in effect, that Westgem should take a more aggressive stance to put pressure on Salta.[512] This was a view reiterated by him in an email sent to Mr Pazin on 29 January 2010 in which Mr Clohessy said that his belief was that capacity to pay issue was a 'smoke screen for their real objective namely to attempt to rewrite the building contract'.[513] Mr Clohessy's emails were part of a string of communications between Westgem's representatives and the Financiers' representatives about how best to deal with Salta's threats to suspend work and to establish Westgem's capacity to pay.
  2. Mr Nathan responded to Mr Clohessy and referred to views expressed after the meeting between Salta, Westgem and the Financiers on 27 January 2010. Mr Nathan stated:[514]
In response to your below email and our telephone conversations, while there is no certainty as to what Salta may do even if Westgem/Luke/Hossean are able to provide assurances that they are in compliance with the financiers construction facility, provide comments etc. from 333 as to the developers/sponsors financial capacity to pay, all supported by a personal guarantee from Luke Saraceni up to the Salta assessed cost to complete figure, however I understand that the view reached by Luke and Paul Fyfe, at the conclusion of the 'Salta/Westgem' meeting on Wednesday, was that at least such actions may make any decision by Salta to terminate the contract more difficult.
  1. In response to Mr Nathan's email Mr Fyfe's advised by email that 'the only thing that will make Salta's decision to terminate more difficult is for Westgem to provide objective substantiation (such as a report by an independent QS) as to what the estimated final Contract Sum is (on the information available to date) likely to be and to then produce documentation and/or evidence of Westgem's capacity to pay that amount on a cash flow basis.'

Westgem provides evidence regarding its capacity to pay

  1. On 29 January 2010, whilst denying that it was obliged to do so, Westgem provided Salta with a copy of the MOFA and various other documents in an attempt to satisfy Salta's capacity to pay concerns.[515] The materials provided by Westgem constituted a considered attempt by it to verify its assertion that it had the capacity to meet its payment obligations. Westgem provided Salta with a copy of 'the banks Quantity Surveyors report supporting the cost to complete' of $260 million,[516] and stated that sum would be funded as to $243 million from the MOFA and $17 million 'via the Joint Venture Owners' and attached evidence that there were assets available to realise more than $17 million. Westgem provided a statement of Mr Luke Saraceni's assets and liabilities and recorded that Mr Saraceni had agreed to provide a personal guarantee in respect of any Cost Overruns.

Salta's response to Westgem's evidence of capacity to pay

  1. On 5 February 2010 Salta sent a letter to Westgem, which was copied to the Security Trustee, stating it was not satisfied with Westgem's capacity to pay.[517] The letter noted that Westgem's letter of 29 January 2010 was the first time Westgem had provided any documentation or evidence to justify its contention that it had the capacity to meet its payment obligations under the Salta Building Contract. Salta provided a long and detailed explanation of why the information provided did not satisfy it that Westgem had the capacity to meet its payment obligations under the Salta Building Contract. The reasons given by Salta are not capable of being readily summarised, however, Salta contested both Westgem's cost to complete figure ‑ noting that RBB's 14 September 2009 report was five months out of date - and the funding available to Westgem. On Salta's figures, the shortfall between the funding Westgem had available to it and its obligations to Salta and others involved in the construction of the development and the repayment of the $6.5 million facility (obtained to fund the first Cost Overrun) was $55,414,287.
  2. Salta's analysis of the availability of funds under the MOFA is instructive. Salta stated:[518]
In its first answer to Salta's clause 42.1 notice pursuant to the Building Contract dated 12 August 2009, Westgem provided Salta with a copy of a letter from BankWest dated 21 August 2009 stating that as at 5 August 2009 the undrawn amount pursuant to Multi Option Facility Agreement was $143,068,463.96. However, BankWest noted that this undrawn amount was subject to the following caveat:
'Please note that the availability of future funding remains subject to compliance with the terms of the Multi Option Facility Agreement and other Transaction Documents'.
Salta asked Westgem for confirmation that there was no relevant breach of the Multi Option Facility Agreement or Transaction Documents. It also asked the Security Trustee to confirm that there were no such breaches. Both Westgem and the Security Trustee have not responded to this request.

Salta has now had an opportunity to read for the first time the Multi Option Facility Agreement.

[Salta referred to the definition of Event of Default and set out the definitions of Cost Overrun and Undrawn Commitment]

Westgem has admitted in its correspondence under reply that there is a shortfall between the amount available under the Facility and the cost to complete. Accordingly, there has been a 'Cost Overrun'. Obviously we do not know whether the Facility Agent has made a demand of the type referred to in clause 17.22. However, for the reasons set out below Salta considers that:

(a) even on Westgem's figures the Cost Overrun would appear to be in the order of $17,000,000;

(b) on Salta's figures the Cost Overrun will be $55,414,287 plus delay costs;

(c) the material provided does not demonstrate that Westgem has a capacity to pay even $17,000,000, if a demand is made pursuant to clause 17.22 of the Multi Option Facility Agreement. Therefore, there is a continuing risk that an Event of Default could occur at any time on five days' notice (alternatively it may have already occurred).

In addition, we note that the borrower is defined to include Pakwest Pty Ltd as trustee for Newport Securities Pty Ltd. The same entities are described as guarantors in Schedule 1 of the Multi Option Facility Agreement and are therefore Transaction Parties for the purposes of the Multi Option Agreement.

Newport Securities Pty Ltd (Newport) has defaulted on a contract of sale for land with 150 Clarendon Pty Ltd (a member of the Salta Group) for an apartment at 150 Clarendon Street, East Melbourne. Proceedings have been issued against this entity to recover $3,325,000 being the balance of the purchase price; and a demand has been made against Mr Saraceni in his capacity as a guarantor. The apparent inability to pay this relatively small amount, raises concerns in relation to the Saracen Group meeting its payment obligations generally.

Accordingly Salta, on the material provided, is not confident that the undrawn amounts which might otherwise have been available pursuant to the Multi Option Facility Agreement are available. Clarification from either yourself or the bank in this regard would be appreciated.
  1. In the course of stating its conclusions Salta stated:
For present purposes even if Salta assumes that:

(a) the value of variations and adjustments to PC sums are as alleged by Westgem (something Salta denies);

(b) there is no breach of the Multi Option Facility Agreement;

(c) there are no financial obligations on Westgem in relation to BankWest's lease at BankWest Tower and Adelaide Terrace;

(d) there are no Cost Overruns on the construction of the tunnel or any costs whatsoever in respect of the capital works removed from Salta's Contract, but which must be done before the property will be suitable for a tenant,

then the documentation does not establish, to Salta's reasonable satisfaction, Westgem's capacity to meet its payment obligations under the Building Contract.
  1. Salta gave notice that it would suspend the whole of the work under the Building Contract on 8 February 2010.
  2. As is readily apparent from Salta's letter of 5 February 2010 it was concerned that Westgem lacked the capacity to meet its payment obligations under the Salta Building Contract and that Salta considered that in monetary terms those obligations far exceeded the funding resources available to Westgem - not only the funds available under the MOFA but available from other sources as well. Salta's concern was not limited to whether Westgem had committed a breach of the MOFA which entitled the Financiers to withhold drawdowns. It was concerned that even if Westgem had access to all the funding available under the MOFA it would still be unable to meet its obligations under the Salta Building Contract.
  3. At this point in the chronology it is convenient to record two inferential findings. First, the Finance Parties knew that Salta was considering exercising its rights under GC 44 of the Salta Building Contract to terminate the Contract. This may be inferred from Salta's correspondence to Westgem and to the Security Trustee. Second, the Finance Parties knew that if they did make a statement to Salta that Westgem was not in breach of the MOFA and that it was able to drawdown on the MOFA to pay Salta, Salta was more likely to exercise its rights under GC 44 of the Salta Building Contract. This may be inferred from the internal communications between the Finance Parties referred to below under the heading 'Financiers internal deliberations'.

Salta's notice of suspension

  1. On 5 February 2010 Salta sent two further communications, an email to the Financiers[519] and a letter to Westgem.[520] In an email to Mr McDonald of BOSI and Mr Pavisich of Bankwest, Mr Regan of Salta stated that there were three broad reasons why the Project was in the position it was in. The reasons were: Westgem's failure to obtain the Security Trustee's consent to variations that were not permitted variations; the number and value of variations directed by the Superintendent and the undervaluing of provisional sums; and Westgem's inability to reasonably satisfy Salta of its capacity to pay. Mr Regan asked for copies of the reports of the Quantity Surveyors that had been relied upon by the Financiers and asked that a meeting be convened to discuss the accuracies of the assumptions made in those reports.
  2. In the 5 February 2010 letter to Westgem, Salta stated that before it could return to work it would be necessary for Westgem to remedy the breaches that were the subject of the show cause notices of 4 September 2009 and 14 December 2009, and either provide Salta with evidence of the consent of the Security Trustee to the 'Prohibited Variations' or issue new drawings to Salta with only the original workscope plus permitted variations. Salta stated that the point had been reached where there was insufficient work available on site to allow an efficient use of resources.

Westgem's show cause notice - 5 February 2010

  1. On 5 February 2010 Westgem served a notice to show cause on Salta alleging Salta was in breach of contract by suspending work under the Salta Building Contract.[521]

Financiers' internal deliberations

  1. On 8 February 2010 Mr Nagle, Mr Pavisich and Mr Nathan prepared a strategy paper for the Executive Credit Committee of Bankwest.[522] The paper sought approval for the waiver of the requirement (arising from the terms of the 18 November Letter Agreement) that the security taken over one of the properties - the Tyne Square property - be registered immediately. The paper contained a brief summary of the dispute between Salta and Westgem and recorded:
It is expected that Westgem and Saraceni will continue to fight Salta's assertions in the short term and provide further information where possible. On this basis, we consider it imperative the Financiers be in a position to confirm that the Borrower is not in default of the Finance Facility.
  1. The recommendations were proposed so that the Financiers were '... in a position to confirm compliance with the Facility terms and support Westgem's negotiations with Salta ...'.
  2. Mr Griffiths had a number of queries about the recommendation contained in the 8 February 2010 strategy paper. In relation to the summary of the contractual disputes he asked:[523]
Please provide a copy of Salta's letter dated 5/2/10 and specifically comment on the conclusion reached that agreeing to the points raised under recommendation a) will be sufficient for Salta to now accept that Westgem has the capacity to meet its financial obligations under the Building Contract. Which in turn will lead to Salta recommencing work.

In broad terms, unless waiving the requirement as sought will, with some certainty, lead to Salta recommencing work, I am not convinced we want to 'give away' an event of default that will allow financiers to act should they wish to do so.

(Recommendation a) concerned the waiver of the requirement for immediate registration of the security over the Tyne Square property.)

  1. The recommendations were approved by the Executive Credit Committee on 12 February 2010 subject to two additional conditions to the effect that it would be an Event of Default: if Salta did not return to work by 1 March 2010; and if Westgem sought to vary the terms of the Salta Building Contract without prior approval from the Financiers.[524]

Salta's response to Westgem's contentions regarding permitted variations

  1. On 11 February 2010 Salta responded to Westgem's letter of 25 January 2010 relating to permitted variations and Westgem's capacity to pay.[525] It is unnecessary to refer to the contents of the letter in detail. Salta rehearsed the arguments which it maintained supported its position and set out why it was not persuaded by the arguments advanced by Westgem.

Westgem's assessment of its position

  1. On 11 February 2010 Mr Fyfe provided Mr Saraceni with written advice in relation to Westgem's position in the face of Salta's suspension. The substance of Mr Fyfe's advice was recorded in the following extracts:[526]
... What we have to get the Security Trustee to understand/appreciate is that unless the Security Trustee is prepared to provide unqualified confirmation that Westgem is not in breach of the Facility Agreement and that it considers/accepts that Westgem otherwise has the capacity and that it will support Westgem to meet its payment obligations under the Contract that there is a very real risk that it will be effectively giving Salta the ammunition it needs to support its assertion that Westgem has failed to comply with the capacity to pay clause in the Building Contract and accordingly set Salta up to claim that it has properly terminated the Building Contract.

... If the Security Trustee was to get on side and unequivocally support Westgem's position that it is able to meet its payment obligations under the contract Salta would be forced into the position of admitting that the present suspension of the works has nothing to do with Westgem not being able to evidence its capacity to pay and everything to do with Salta being unable to meet its financial obligations under the contract even when it has been paid all amounts that it is legally entitled to be paid ...
  1. On 12 February 2010 Mr Clohessy forwarded Mr Fyfe's advice to Mr Pavisich, Mr Nagle and Mr Nathan and stated, in effect, that even if the Financiers were of the view that Westgem was still in default they had the capacity to vary the terms of the 18 November Letter Agreement (as varied once already) and they would then be in a position to confirm that Westgem was not in breach of the MOFA.[527]
  2. On 12 February 2010 Mr Frank Saraceni circulated to representatives of the Financiers a document entitled 'Raine Square Westgem Step in Report'.[528] In the Executive Summary section of this Report Mr Frank Saraceni described Westgem's position as follows:[529]
Westgem have three basic options -
  1. Await Salta's decision whether they are prepared to continue under the present contract
  2. Continue to attempt to seek a resolution and pay additional costs necessary to have Salta continue on site
  3. Remove all works remaining in the contract from Salta and place new builder on site
  4. Mr Frank Saraceni recommended 'Option 3' and suggested '... Salta be removed as the builder and replaced with an agreed capable and competent builder. We strongly believe that should this not occur then options 1 and 2 will only increase risks associated with the project completion on a time and cost basis. The current financial position of Salta in regard to this project will only continue to cause similar problems and further project delays to completion.'
  5. On 17 February 2010 representatives of the Financiers, including Mr Pavisich, met representatives from three of the builders whom Westgem had recommended take over from Salta - Broad, Arccon and Diploma.[530]

333's assessment of Salta's losses

  1. On 12 February 2010, in response to a request from Mr Wlossak to Mr Gowdie for 'any view on the level to which Salta is underwater on this construction contract' which Mr Wlossak saw as 'important as it goes to the heart of whether Salta would be interested in completing the Project', Mr Tom Davis of 333 provided a report by email to the Financiers.[531] The analysis had been undertaken by Mr Gowdie and was 'a high level assessment'.[532] In the email, Mr Davis reported Mr Gowdie's view that Salta had originally expected to make a profit of $19 million but that there was no longer any expectation of a profit. Mr Gowdie considered that Salta had lost $10 million on preliminaries and had an exposure of $11 million in respect of subcontractor claims. Mr Gowdie's view was '[b]ased on the above estimate of Salta's unfavourable current position, it would appear unlikely that Salta would be prepared to complete the Development under the current structure. Not only is there an expectation no profit exists, but they may have lost approximately $11 million in preliminary costs and have exposure to subcontractors of approximately $11 million.[533]

Salta's response to Westgem's show cause notice - 12 February 2010

  1. On 12 February 2010 Salta responded to Westgem's notice to show cause dated 5 February 2010 and stated that it was entitled to suspend the works on the basis that Westgem had failed to show cause in response to its 4 December 2009 notice and because Westgem had failed to obtain approval from the Security trustee for the 'prohibited variations'.[534]

Westgem's capacity to pay contentions - 16 February 2010

  1. On 16 February 2010 Westgem sent a lengthy letter in response to Salta's letter of 5 February 2010 in relation to Westgem's capacity to pay.[535] Westgem maintained that it was not in breach of the Salta Building Contract and provided further information in support of its capacity to pay. In relation to the suggestion made by Salta that Westgem was in breach of the MOFA Westgem stated:[536]
Notwithstanding that it has no evidence of any breach of the Facility Agreement or transaction documents by Westgem Salta has requested from Westgem confirmation that there was no relevant breach.

Westgem confirm that it is not in substantial breach of the Facility Agreement or Transaction Documents and further, any current technical breach does not affect Westgem's capacity to pay.

The Security Trustee has not exercised any of its rights under the facility agreement.
  1. Westgem referred to Mr Saraceni's offer to guarantee 'payment of any shortfall in good faith' and stated that he clearly had sufficient net assets - $240 million - to fund any perceived shortfall.

Superintendent issues Salta negative payment certificate - 16 February 2010

  1. On 16 February 2010 the Superintendent issued payment certificate 33 in which he reduced the amounts previously certified for variations, reduced the amount previously certified for 'value management items' by $3.6 million and made other reductions, the effect of which was to certify a negative amount - that is an amount payable by Salta to Westgem - of approximately $3.4 million excluding GST.[537]
  2. Salta issued a show cause notice in relation to payment certificate 33 on 19 February 2010.[538] In its show cause notice Salta alleged that the Superintendent had not acted 'honestly and fairly' and was undervaluing Salta's work. Salta accused the Superintendent of adopting an adjusted contract sum of $235,187,450 for the purposes of the payment certificate 33 which was inconsistent with Westgem's adoption of the Financiers' quantity surveyors' figure of $260 million in its letters to Salta of 29 January 2010 and 16 February 2010. Salta stated that there was a real risk that Westgem would not be solvent by the time judgment was obtained in any action by Salta for damages for breach of contract.[539] Westgem responded to Salta's show cause notice on 23 February 2010 disputing, in forceful terms, Salta's allegations and, in effect, challenging Salta to make an adjudication application.[540]

Salta and Westgem - further correspondence

  1. On 19 February 2010 Salta responded to Westgem's letter of 16 February 2010 and sought further information from Westgem as to its capacity to pay and provided Westgem with a list of variations that it asserted required the approval of the Security Trustee.[541]
  2. On 19 February 2010 Westgem notified Salta that if it did not lift the suspension of works by 1 March 2010 Westgem would terminate the Salta Building Contract.[542] Westgem's notice was served without the consent of the Security Trustee.[543]
  3. On 19 February 2010 Salta sent another letter to Westgem regarding its (Salta's) notice of suspension and the notices served by Westgem on Salta.[544] In the letter Salta defended its position in some detail and claimed that Westgem had starved it of cash flow contrary to the provisions of the Salta Building Contract. Salta described the conduct of the Superintendent as 'reprehensible'.

Meeting between representatives of Salta and Financiers - 24 February 2010

  1. On 24 February 2010 a meeting took place between representatives of the Financiers (Mr Griffiths, Mr Wlossak, Mr Pavisich, Mr Green and Mr Mahaffy) and representatives of Salta (Mr Veevers, Mr Tarascio and Mr Regan). Based on accounts given by Mr Griffiths, Mr Pavisich and Mr Mahaffy, which I accept, the meeting was a long meeting at which both the Financiers and Salta put forward their respective points of view. The possibility of the Financiers exercising their step-in rights was discussed. Mr Veevers and Mr Tarascio said words to the effect of: 'we do not know what to build'; 'we are finding it difficult to get variations approved'; 'we are bleeding on this project'; and 'we want to complete the project, we do not want to walk away. That is not how we operate, we have a reputation to maintain'. Mr Veevers or Mr Tarascio said that for Salta to come back to site it would require an immediate injection of cash. Mr Pavisich's recollection was that this was approximately $5 million to $10 million.[545] One of the Financiers' representatives asked the Salta representatives to extend the remedy period under the Builder's Side Deed to 3 March 2010 - that is, not to purport to terminate until 3 March 2010 - so that the Financiers would have more time to consider the options available, if they decided to exercise their step-in rights. The meeting ended without a resolution and the Salta representatives said that they would consider their position and revert to the Financiers when they had done so. Following the meeting Mr Mahaffy sent an email to the Salta representatives asking that Salta consider executing a short agreement to provide for an extension of the period within which the Security Trustee could exercise its step-in rights.[546] Mr Regan responded to Mr Mahaffy's request and stated that Salta was unable devise a way to protect its rights against Westgem and grant the Financiers an extension of five days within which to exercise their step-in rights, but that Salta would preserve its 'team and infrastructure' until the night of 3 March 2010 in the 'expectation that all parties will endeavour during that period to reach an accord to enable the project to be completed'.[547]

Salta serves notice of termination

  1. On 25 February 2010 Salta terminated the Salta Building Contract. The notice recited Salta's deployment of the relevant provisions of the Salta Building Contract.[548]
The pleaded case
  1. Westgem's misleading or deceptive conduct claim relies on contextual silence. Westgem also put its case on the basis that the Finance Parties made representations as to future matters in circumstances where the Finance Parties did not have reasonable grounds for making the representations. Westgem pleaded that in accordance with s 9 of the FTA or alternatively s 51A of the Trade Practice Act 1974 (Cth) those representations were deemed to be misleading. To obtain a proper understanding of the nature of the claim it is necessary to reproduce rather than summarise the relevant paragraphs of the statement of claim.
The misleading or deceptive conduct - the representations
  1. Omitting all but critical particulars, the misleading or deceptive conduct was pleaded as follows:[549]
    1. Between on or about 20 November 2009 and 25 February 2010, Salta had a concern as to whether Westgem lacked capacity to meet its payment obligations under the Building Contract by reason of having committed a breach of the MOFA (Salta's Capacity to Pay Concern).
288A. Between on or about 20 November 2009 and 25 February 2010, Salta made known to the Finance Parties that its intention was to consider exercising its strict contractual rights under cl 44.9 of the Building Contract, in the event that Salta considered those rights were available to it to be exercised.
  1. As between on or about 20 November 2009 and 25 February 2010, the Finance Parties were requested to confirm to Salta that Westgem had the capacity to meet its payment obligations under the Building Contract and had not committed a breach of the MOFA:
289.1 by Salta, expressly, on 20 November 2009;

289.2 by Salta, impliedly, on 27 November 2009, 18 December 2009, 24 December 2000 and in 25 January 2010; and/or

289.3 by Saracen Project Management on behalf of Westgem, partly expressly and partly impliedly, on 15 December 2009.

289.4 by Clohessy on behalf of Westgem, partly expressly and partly impliedly, on 11 February 2010.
289A. Between on or about 20 November 2009 and 25 February 2010, the Finance Parties were aware that the non-provision by them of confirmation to Salta that Westgem had the capacity to meet its payment obligations under the Building Contract and/or had not committed a breach of the MOFA made it more likely that Salta would exercise cl 44.9 Rights.
  1. The Finance Parties did not, in response to the requests pleaded in paragraph 289 or otherwise, confirm to Salta that Westgem had the capacity to meet its payment obligations under the Building Contract and had not committed a breach of the MOFA.
  2. As between on or about 20 November 2009 and 24 February 2010:
291.1 the Finance Parties conducted themselves in their relationship with Salta in a manner inconsistent with Westgem having the capacity to meet its payment obligations under the Building Contract and/or having not committed a breach of the MOFA upon which the Finance Parties would rely to withhold payment of drawdowns (Capacity to Pay Conduct);

291.2 alternatively, the Finance Parties impliedly represented to Salta that Westgem lacked capacity to meet its payment obligations under the Building Contract by reason of having committed a breach of the MOFA of which the Finance Parties were aware, and upon which they were prepared to rely as the basis of withholding payment of drawdowns to allow Westgem to meet its payment obligations under the Building Contract (Capacity to Pay Representation).
Particulars of paragraphs 291.1 and 291.2
  1. Paragraphs 288 to 290 are repeated. The Financiers did not confirm that Westgem had the capacity to meet its payment obligations under the Building Contract and had not committed a breach of the MOFA notwithstanding that on 21 August 2009 they had provided a letter to Westgem for provision to Salta confirming the status of the facilities under the MOFA as at 5 August 2009.
  2. The Financiers had asserted the right to refuse to permit drawdowns under the MOFA resulting in late payments to Salta of amounts to which it was entitled, and paragraph (i) of the particulars to paragraph 271.1 is repeated;[550]
  3. The Finance Parties appointed 333 and 333 Advisory as pleaded in paragraphs 71 and 76, to the knowledge of Salta;
iiiA. The plaintiffs refer to [its 2807D.3(b)] and [287E.2(b)] of the Reamended Reply to the Defence to the Third Further Amended Second Substituted Statement of Claim. The Facility Agent and/or Financiers failed to instruct the Security Trustee to give consent or refusal, and/or the Security Trustee failed to give consent or refusal, under cl 3.3 of the Builder's Side Deed within a reasonable time to variations which Salta contended were not 'Permitted Variations' within the meaning of the Builder's Side Deed (as they were obliged to do by reason of the matters pleaded in paragraph 57B), notwithstanding that in some cases the Financiers had approved those variations (Alleged Non-Permitted Variations), by reason of which Salta was concerned that if it performed building work in relation to those variations, Westgem would be unable to make drawdowns under the MOFA to pay for those works. Further particulars will be provided separately of the Alleged Non-Permitted Variations;
  1. On or about 24 February 2010, the Finance Parties met with Salta to discuss, inter-alia, the possibility of the Security Trustee giving Salta a step-in notice under cl 7 of the Builder's Side Deed, being a right which was:
    1. only available to the Security Trustee when an Event of Default had occurred under the MOFA and associated securities; and
    2. a right of a kind which, in the common experience of building contractors, was only considered for exercise by a financier of a developer if the developer did not have sufficient financial capacity to complete the project or was in default under its finance facilities.
  2. The Capacity to Pay Representation was a representation as to both an existing and as to a future matter, and to the extent it was as to a future matter within the meaning of s 51A of the TPA and s 9 of the FTA, and the plaintiffs rely on s 51A(2) of the TPA and s 9(2) of the FTA.
The true position as alleged by Westgem
  1. Westgem pleaded its 'true capacity to pay' as follows:
    1. Between on or about 20 November 2009 and 25 February 2010, Westgem:
292.1 had not committed a breach of the MOFA which would entitle the Finance Parties to withhold advances under the MOFA such as to deprive Westgem of the capacity to meet its payment obligations under the Building Contract; and/or

292.2 had not committed a breach of the MOFA of which the Finance Parties were aware, and upon which they at that time were prepared to rely in order to withhold advances under the MOFA such as to deprive Westgem of the capacity to meet its payment obligations under the Building Contract,

(Westgem's True Capacity to Pay).

Particulars

As to subparagraphs 292.1 as between on or about 20 November 2009 and 25 February 2010:
  1. By reason of the following matters the Finance Parties were not entitled to rely upon the Leasing Covenant Breach Assertion:[551]
...
  1. For the reasons set out in Section E3, the First Alleged Cost Overrun did not exist and the Finance Parties were not entitled to rely upon the First Alleged Cost Overrun Assertion or the First Alleged Default Notice as an event of default under the MOFA, and/or there was no event of default under the MOFA by reason of the First Alleged Cost Overrun Assertion.
...

iiiA. The amount remaining available to be drawn down under the MOFA was the undrawn limit of the MOFA (being an amount which did not take into account amounts deducted from the facility limit by reason of the MOFA Default Rate Imposition or payment of any of the Financiers' costs debited to the MOFA by reason of the First or Second Alleged Cost Overruns).
  1. The Plaintiffs refer to paragraph 287D.3(b) of the Reply to the Defence to the Amended Second Substituted Statement of Claim, and say that in respect of the Alleged Non-Permitted Variation the Security Trustee was obliged to:
    1. advise its consent to the Alleged Non-Permitted Variation such that Salta would not rely upon that issue as being relevant to Westgem's capacity to pay (given that to the extent that the Financiers and/or Security Trustee had approved that Alleged Non-Permitted Variations, Westgem was able to pay the cost of the Alleged Non-Permitted Variations by making drawdowns on the MOFA).
    2. alternatively, advise its refusal to consent to the Alleged Non-Permitted Variation such that Salta would not rely upon that issue as being relevant to Westgem's capacity to pay given that the work the subject of such Variation did not need to be built or was not in fact a Variation (such that there was no obligation to make payment for that Alleged Non-Permitted Variation under the Building Contract),

in either case within the time referred to in paragraph 57B, and therefore Westgem was entitled to make drawdowns under the MOFA to meet its payment obligations under the Building Contract.

As to subparagraph 292.2, as between on or about 20 November 2009 and 25 February 2010:[552]
  1. the Finance Parties were not prepared to rely upon the alleged breach of the Leasing Covenant in order to withhold advances under the MOFA...
  2. the Finance Parties were not prepared to rely upon the existence of alleged issues concerning the construction of the Complex...
  3. the Finance parties were not prepared to rely upon the existence of any matters relating to the IFO...
  4. the Finance Parties were not prepared to rely upon the fact that Salta had alleged that Westgem had failed to comply with its obligations under the Building Contract by not providing evidence of its capacity to pay, including because they did not at any time rely upon the existence of any alleged breach of the Building Contract in order to withhold advances under the MOFA notwithstanding they knew that Salta was claiming that Westgem lacked capacity to pay (and paragraphs 288A to 289A are repeated).
  1. By reason of Westgem's True Capacity to Pay, the Capacity to Pay Conduct and/or the Capacity to Pay Representation was:
293.1 misleading or deceptive, or likely to mislead or deceive, in contravention of:
293.1.1 s 52 of the TPA;

293.1.2 alternatively, s 12DA of the ASIC Act;

293.1.3 alternatively, s 10 of the FTA;
293.2 in circumstances where the Finance Parties had the knowledge pleaded in paragraphs 288A and/or 289A, unconscionable, in contravention of:
293.2.1 s 51AB and/or s 51AC of the TPA;

293.2.2 alternatively, s 12CC of the ASIC Act (as in force prior to 1 January 2011);

293.2.3 alternatively, s 11 of the FTA;
293.3 in breach of the Code Conduct Term by reason that Bankwest failed to act fairly and reasonably and in an ethical manner,

(each a Capacity to Pay Contravention).

The causation plea
  1. The causation plea is more readily summarised. First, Westgem pleaded that but for the Finance Parties' misleading or deceptive conduct:[553]

(a) The Security Trustee would have informed Salta of 'Westgem's True Capacity to Pay' - that is, that Westgem had not committed a breach of the MOFA which would entitle the Finance Parties to withhold advances under the MOFA such as to deprive Westgem of the capacity to meet its payment obligations under the Salta Building Contract and/or had not committed a breach of the MOFA of which the Finance Parties were aware, and upon which they at the time were prepared to rely in order to withhold advances under the MOFA such as to deprive Westgem of the capacity to meet its payment obligations under the building contract.

(b) Alternatively, Salta would not have had a concern as to whether Westgem lacked the capacity to meet its payment obligations under the Salta Building Contract by reason of having committed a breach of the MOFA.

(c) As a consequence of (a) and (b), Salta would not have sent its letter dated 24 December 2009 to the Security Trustee and/or Salta would not have issued its notice of suspension on 5 February 2010 or its notice of termination on 25 February 2010.

  1. Secondly, and in the alternative, Westgem pleaded that but for the Financiers' allegations that the first and second Cost Overruns had occurred the misleading or deceptive conduct would not have occurred, and in turn, Salta would not have issued the suspension notice on 5 February 2010 because it would not have relied upon the existence of a $17 million Cost Overrun.[554] Westgem argued it would have been able to demonstrate its capacity to meet its payment obligations under the Salta Building Contract so as to satisfy Salta. In support of the proposition that Westgem would have been able to satisfy Salta of its capacity to pay, Westgem relied on Mr Pourzand's financial capacity, and the financial capacity of his daughter Farah Pourzand to demonstrate Westgem's capacity to pay.
  2. Westgem pleaded that but for Salta's (wrongful) termination of the Salta Building Contract:[555]

(a) the work under the Salta Building Contract would have been completed by a date between on or about 31 August and 31 December 2010;

(b) Westgem would not have not have terminated the Salta Building Contract;

(c) construction of the Project would not have been delayed;

(d) Bankwest would have been liable to pay rent for the office space between on or about 29 December 2010 and 30 April 2011 - in any event a date materially earlier than Bankwest in fact commenced paying rent; and

(e) Oakcure would have sold its interest in Raine Square to Charter Hall Funds Management Ltd as trustee for Charter Hall Wholesale Funds.

Applicable statutory provisions and principles
  1. The statutory provisions relied upon by Westgem prohibited the Finance Parties from engaging in misleading or deceptive conduct or conduct likely to mislead or deceive.[556] For the purposes of the provisions the definition of 'conduct' includes 'refusing to do an act', an expression which was in turn defined as including (relevantly) 'refraining, (otherwise than inadvertently) from doing an act'.[557]
  2. In Butcher v Lachlan Elder Realty Pty Ltd,[558] in a passage cited with approval on many occasions, McHugh J stated that the question whether conduct is misleading or deceptive or likely to mislead or deceive for the purposes of s 52 of the Trade Practices Act 1974 (Cth) (TPA) is a question of fact. His Honour outlined the approach to be adopted to determining that question as follows:[559]
In determining whether a contravention of s 52 has occurred, the task of the court is to examine the relevant course of conduct as a whole. It is determined by reference to the alleged conduct in the light of the relevant surrounding facts and circumstances. It is an objective question that the court must determine for itself. It invites error to look at isolated parts of the corporation's conduct. The effect of any relevant statements or actions or any silence or inaction occurring in the context of a single course of conduct must be deduced from the whole course of conduct. (citations omitted)
  1. Although McHugh J's observations were directed to s 52 of the TPA they apply equally to the other statutory prohibitions against misleading or deceptive conduct.
  2. Silence or the non-disclosure of information is a circumstance, to be assessed like any other, in determining whether conduct is misleading or deceptive or likely to mislead or deceive.[560]
  3. The existence of a reasonable expectation that if a fact exists, it would be disclosed, is an aid to the characterisation of conduct in cases of silence or non-disclosure (and not a substitute for the application of the statutory language).[561] The existence or otherwise of a reasonable expectation of disclosure involves an objective assessment that focuses on the effect, or likely effect, of the non-disclosure of the information, 'unmediated by antecedent and erroneous assumptions or beliefs or high moral expectations held by one person of another which exceeded the requirements of the general law and the prohibition imposed by the statute'.[562]
  4. The statutory prohibitions against misleading or deceptive conduct or conduct likely to mislead or deceive do not strike at '... the traditional secretiveness and obliquity of the bargaining process'.[563] Nor do the prohibitions require a party to commercial dealings to volunteer information that will assist the decision-making of another party.[564] As Gleeson CJ stated in Lam v Ausintel Investments Australia Pty Ltd:[565]
Where parties are dealing at arms' length in a commercial situation in which they have conflicting interests it will often be the case that one party will be aware of information which, if known to the other, would or might cause that other party to take a different negotiating stance. This does not in itself impose any obligation on the first party to bring the information to the attention of the other party, and failure to do so would not, without more, ordinarily be regarded as dishonesty or even sharp practice.
  1. Silence or non-disclosure is capable of being misleading in circumstances in which there is no obligation or duty to disclose at common law or in equity.[566]
  2. Where conduct is alleged to be misleading or deceptive because it involved a failure to disclose information, the plaintiff carries the onus of establishing how the non-disclosure had the potential to mislead or deceive.[567]
  3. Characterisation of conduct as misleading or deceptive is a task that generally requires consideration of whether the impugned conduct viewed as a whole has a tendency to lead a person into error.[568]
  4. As McLure P observed in Owston Nominees No 2 Pty Ltd v Clambake Pty Ltd,[569] contextual matters can have a material impact on widening the range of conduct properly attributable to a defendant. A defendant's actual conduct must be examined in its broader context to assess the full scope of what can properly be characterised, expressly or impliedly as its conduct. Ordinarily, the term 'representation' is used to capture in words both the defendant's contextual conduct and what it conveys or communicates to others.[570]
  5. The question whether conduct is misleading or deceptive or likely to mislead or deceive is logically anterior to the question whether a person has suffered loss or damage thereby. The distinction between characterisation of the conduct and determination of the causation of the claimed loss said to result from it must be maintained. It is necessary to acknowledge, however, that there may be practical overlaps in the resolution of these logically distinct questions. The characterisation of conduct may involve assessment of its notional effects, judged by reference to its context. The same contextual factors may play a role in determining causation.[571]
  6. The nature of the relationship between commercial parties including prior dealings between them, common assumptions and practices that may attend the relationship, the knowledge of the party to whom the conduct is directed, the complexity of the relevant transaction, and the level of sophistication of the parties are all factors that may be relevant to the determination of whether conduct is misleading or deceptive or likely to mislead or deceive.
Consideration 'Primary' and 'alternative' cases
  1. Westgem developed its misleading and deceptive conduct case in its closing submissions in a manner that the Financiers contended departed from the pleaded case. There is some force in the Financiers' contention. Westgem contended that the Capacity to Pay Representation (the implied representation Westgem had committed a breach of the MOFA of which the Finance Parties were aware and upon which they were prepared to rely to withhold drawdowns for the purposes of allowing Westgem to meet its payment obligations under the Salta Building Contract) pleaded in par 291.2 of the statement of claim was misleading because Westgem had not, in fact, committed a breach of the MOFA upon which the Finance Parties were prepared to rely. The representation was alleged to be misleading - not because there was no breach - but because the Finance Parties were prepared to allow Westgem to drawdown on the MOFA to meet its payment obligations under the Building Contract 'irrespective of whether the amount of the second Cost Overrun was paid or whether there had been other breaches of the MOFA'. A preparedness on the part of the Finance Parties to allow Westgem to drawdown on the MOFA irrespective of whether the amount of the second Cost Overrun was paid was not one of the grounds pleaded by Westgem to establish 'the true capacity to pay'[572] and, in turn, to establish that the Capacity to Pay Representation was misleading. Even though not pleaded, or at least not pleaded clearly, in closing submissions senior counsel for Westgem described this as Westgem's primary case. In its pleaded case Westgem identified other alleged breaches of the MOFA which it alleged the Finance Parties were not prepared to rely upon, but did not identify the second Cost Overrun breach, as one such breach.[573]
  2. In effect the 'primary case' rested on the proposition that the impugned conduct conveyed a half truth.
  3. It is convenient to note that in its closing submissions Westgem advanced what its senior counsel described as its 'alternative' case (that the Finance Parties conducted themselves in a manner inconsistent with Westgem having the capacity to meet its payment obligations and/or having not committed a breach of the MOFA on which the Finance Parties would rely to withhold drawdowns - the Capacity to Pay Conduct case pleaded in par 292.1 of the statement of claim) - on the basis that the case depended upon establishing that there had been no breach of the MOFA which 'entitled' the Finance Parties to withhold drawdowns.
  4. Further, in closing submissions Westgem relied for its misleading or deceptive case on the fact that the Security Trustee did not exercise its rights (under cl 3.4 and cl 3.5 of the Builder's Side Deed) to remedy the breach of the Salta Building Contract asserted by Salta by providing evidence that Westgem had the capacity to meet its payment obligations under the MOFA. It was contended that the existence of those rights created an expectation that the Security Trustee would remedy Westgem's defaults if it was in a position to do so. This was not a matter pleaded by Westgem.
  5. For the reasons I explain neither of these allegations advance Westgem's claim and it is unnecessary to consider whether Westgem should be permitted to rely on them.

Contextual matters

  1. Even when account is taken of the wide variety of circumstances in which misleading or deceptive conduct claims have been made, this case is unusual.
  2. All the parties were sophisticated commercial enterprises and their involvement in the development of Raine Square was governed by complex transaction documents. The parties were assisted in their dealings with each other by lawyers. Experienced management teams represented the interests of each party. The critical communications exchanged between the parties were worded with deliberation and each written communication was analysed carefully and its significance closely assessed. The difficulties these circumstances present for a misleading or deceptive conduct claim based on non‑disclosure are compounded by two further matters: first, the party allegedly misled, Salta, is not the plaintiff and has not complained that it was misled -and, importantly, there was no evidence that it was misled; and, second, the plaintiff, Westgem, was aware of the non-disclosure alleged to have made the conduct misleading yet it did not disclose the undisclosed matters.
  3. By the end of November 2009 the relationship between Westgem and Salta had deteriorated to the point where there was a mutual and profound level of distrust between them. Both sides wanted to terminate the Salta Building Contract. Salta wanted to replace the Salta Building Contract with another contract with new payment terms and a different superintendent, and Westgem wanted to replace Salta with another builder.
  4. For all parties, self-interest was the guiding principle and the parties regarded each other with suspicion and cynicism. They were in a difficult and tense commercial situation - each had millions of dollars at stake. Salta and Westgem had made it clear to each other, and to the Financiers, that they would rely on their legal rights and the parties were operating in an environment in which the prospect of litigation loomed large. In one sense the Financiers were confronted with a dilemma - if they did not provide Salta with the confirmation that there was no breach of the MOFA as Westgem urged them to do, there was a risk that Salta would terminate the Building Contract, but in order to provide that confirmation, they would be required to waive the second Cost Overrun breach and default, because to have provided the confirmation without doing so, as Mr Pavisich told Mr Saraceni, would have been misleading.
  5. There was a very substantial difference in the amount that Salta considered would be required to meet Westgem's payment obligations under the Building Contract and the amounts that the Finance Parties and Westgem respectively considered would be required to meet those obligations.
  6. From 24 December 2009 at the latest, Salta knew that the Finance Parties were not the sole source of funds from which Westgem's payment obligations under the Salta Building Contract were to be met.

No reasonable expectation of disclosure

  1. There was no reasonable expectation that the Finance Parties would make any statement - general or specific - about Westgem's capacity to meet its payment obligations under the Salta Building Contract.
  2. There were at least three reasons why there was no reasonable expectation that the Finance Parties would make a statement of a general nature about Westgem's capacity to meet its payment obligations under the Salta Building Contract.
  3. First, a positive representation that Westgem had the capacity to meet its payment obligations under the Salta Building Contract had the potential to expose the Finance Parties to significant liability to Salta in the event that Westgem did not have the capacity to meet those obligations. It was highly unlikely that the Finance Parties would have exposed themselves to a liability of this nature by making a representation in such unqualified terms and equally unlikely that Salta would have expected the Finance Parties to have done so. In this respect it is pertinent to note that Mr McDonald of BOSI characterised a statement to the effect that Westgem had the capacity to meet its payment obligations under the Salta Building Contract as a 'blank cheque'.[574]
  4. Secondly, Salta was a sophisticated and experienced commercial enterprise, and I find its management and lawyers, on seeing Bankwest's letter of 21 August 2009, understood (if they were not already aware) that the Finance Parties' ability to comment on Westgem's financial capacity was confined to an ability to comment on the funding available under the MOFA, and that Salta's management understood the Finance Parties could not comment generally on Westgem's capacity to meet its payment obligations.
  5. Thirdly, given Salta's experience and sophistication, it understood that the Finance Parties, as bankers, owed obligations of confidentiality to Westgem. Salta may not have known the nature and extent of the confidentiality obligations in fact owed by the Finance Parties,[575] but it was aware that the Finance Parties were likely to be subject to obligations of confidentiality that would have prevented them from making comments - positive or negative - about Westgem's financial capacity without Westgem's consent and that consent was unlikely to be given to any statement of a negative nature.
  6. Before leaving the issue of whether there was a reasonable expectation that the Financiers would make a statement of a general nature about Westgem's capacity to meet its payment obligations under the Salta Building Contract, it is convenient to deal with a point raised by the Financiers in closing submissions. The point was to the effect that, in the context of the dispute that had arisen between Salta and Westgem, a statement about Westgem's capacity to meet its payment obligations under the Salta Building Contract that was not qualified by some quantification of the extent of those obligations in monetary terms was 'ambiguous' given the widely divergent views of the construction costs of completion. The focus on 'capacity to pay' in the contemporaneous correspondence is apt to obscure the underlying issue, namely, whether, in order to complete the building works, Westgem would have to pay Salta a sum in the vicinity of $260 million, as it contended, or $321 million, as Salta contended in August 2009 (the figure subsequently increased). The communications between Westgem and Salta were not (as pleaded by Westgem)[576] framed by reference to the contractual concept of Westgem's 'capacity to meet its payment obligations under the Building Contract' in abstract terms unqualified by a monetary amount - the communications focused on the quantum of those obligations.
  7. I have concluded the Finance Parties' conduct did not convey anything about 'Westgem's capacity to meet its payment obligations under the Building Contract' but even if did convey a representation in those abstract terms, in the context of the parties' communications, such a representation would have been too uncertain in its meaning to have any significance attached to it. For the sake of completeness I record there is no evidence that the Finance Parties made any representation that Westgem had the capacity to pay any particular amount.
  8. There was no reasonable expectation that the Finance Parties would make a specific statement to Salta that there was no breach of the MOFA (if that was the case) or that there was a breach of the MOFA but that the Finance Parties were not prepared to rely on it to withhold drawdowns and thus prevent Westgem from meeting its payment obligations under the MOFA (if that was the case), or a statement to the effect that Westgem's financial capacity extended to a particular amount. First, as already observed, Salta would have appreciated the Finance Parties' confidentiality obligations operated to prevent them from making a specific statement about whether or not there had been a breach of the MOFA in the same way that they prevented them from making a general statement about Westgem's capacity. Secondly, it was in the Finance Parties' interests for the Project to be completed without delay and for Salta to be bound by the Salta Building Contract. In this respect the interests of Westgem and the Finance Parties coincided. Objectively, it was highly unlikely that the Finance Parties would make any statement to Salta about the existence or otherwise of a breach of the MOFA or their preparedness to rely on such a breach unless obliged to do so. Salta understood that the Finance Parties' objective was to get it to complete the Project without delay and without exposing the Finance Parties to any liability. This was the effect of Mr Gerrard's observations about the 'The Bank who will stand (hide) behind the Side Deed and the Building Contract in order to ensure that it is not exposed', in par 3 of his email of 10 December 2009 to Mr Cargill and Mr Regan.[577] Salta appreciated that the Finance Parties would be guided by their own interests and would not make any statements or representations that they were not obliged to make, or that if made, had the capacity to expose them to liability. Of course, neither of these reasons meant that it was not in Salta's interests to pressure the Finance Parties to make disclosures about Westgem's position.
  9. Westgem argued that there were two important matters of context that supported its claim that the Finance Parties' conduct was misleading or deceptive. The first of these was Bankwest's letter of 21 August 2009, which, Westgem argued, created an expectation that the Finance Parties would, when requested by Westgem, provide information about Westgem's access to finance under the MOFA. I do not accept that contention. It is not supported by Salta's contemporaneous view of the significance to be attached to the letter of 21 August 2009. In its correspondence Salta referred repeatedly to the qualification recorded in the letter that 'future funding remains subject to compliance with the terms of the Multi Option Facility Agreement and other Transaction Documents' as one reason why it drew no comfort from the letter. I find that Salta attached no significance to the letter of 21 August 2009 -Mr Gerrard referred to it as a 'misleading document'. Bankwest's 21 August 2009 letter did not give rise to any expectation that the Finance Parties would provide information to Salta about Westgem's access to finance under the MOFA when asked by Westgem to do so.
  10. The second matter of context relied upon by Westgem in its closing submissions was constituted by the rights of remedy conferred on the Security Trustee by cl 3.4 and cl 3.5 of the Builder's Side Deed. Westgem argued, in effect, that the existence of these rights created an expectation that the Security Trustee would remedy Westgem's defaults if it were in a position to do so. Clauses 3.4 and 3.5 of the Builder's Side Deed conferred rights upon the Security Trustee but imposed no obligation on it to exercise those rights. I do not accept that sophisticated commercial parties guided by legal advice would have an expectation that the Security Trustee would remedy Westgem's defaults simply because it had the right to do so.
  11. In addition, Westgem placed considerable reliance on Salta's response to the Security Trustee's letter to it of 26 November 2009, in which the Security Trustee had refused to provide any information to Salta in response to Salta's request for a copy of the MOFA and confirmation that Westgem was not in breach of it. Westgem argued, in effect, that the following sentence in Salta's response of 27 November 2009 reflected in essence the pleaded Capacity to Pay Conduct and Capacity to Pay Representation:[578]
The refusal by BOSI to provide the information requested is most curious and leads to an inference that BOSI is unable to give the assurances sought in Salta's letter of 20 November 2009.
  1. In the commercial context that I have described, I do not accept that such an inference arose from the Security Trustee's reliance on the absence of any obligation on it to provide the information sought by Salta, nor I do accept that Salta, in fact, drew such an inference. Salta's correspondence was tactical. In truth, as was apparent from Mr Gerrard's email of 10 December 2009, from the perspective of obtaining negotiating leverage over Westgem, Salta did not want Westgem to establish its capacity to pay - Mr Gerrard identified the possibility of Westgem establishing capacity to pay as a 'downside'. Salta's correspondence was contentious and it was designed to achieve its strategic aim of a renegotiated Building Contract. Salta wanted to establish that there was a breach of the MOFA in order to exert pressure on Westgem. The purpose of its correspondence was to extract an admission that it could use to its advantage. In this respect the Security Trustee frustrated Salta by responding with the metaphorical 'straight bat'. Salta's assertion that an inference arose that the Security Trustee could not provide the assurance sought was the best tactical response open to it. Asserting that the inference arose did not make it so. Moreover, I note the Security Trustee immediately denied that such an inference arose. If the existence of a representation based on an inference drawn from conduct is immediately negated by an express denial - before the representation is acted on - it is difficult for the representation to have any operative effect - especially in the circumstances of this case.
  2. As the authorities make clear, for the purposes of assessing whether conduct was misleading or deceptive all the surrounding circumstances must be taken into account. In this case, regard must be had to Westgem's own conduct.
  3. In my view it was Westgem own conduct that led to Salta having the confidence to assert that Westgem did not have the capacity to meet its payment obligations under the Building Contract and to rely on that assertion for the purposes of its notice of suspension served on 5 February 2000. It was Westgem's letters of 22 December 2009 and 29 January 2010 and the materials accompanying the letter of 29 January 2010 (which Westgem contended demonstrated its capacity to meet its payment obligations) that led Salta to conclude that there had been a $17 million Cost Overrun, a breach of the MOFA and a potential, if not actual, Event of Default.
  4. Salta fastened on the statement in David Hewitt & Co's letter provided to Salta under cover of Mr Luke Saraceni's letter of 22 December 2009 that:[579]
the current construction costs to completion ... is funded by the bank together with an unsubstantial amount that will be provided from the substantial assets of the joint venturers. (emphasis supplied)
  1. Salta contended this constituted an admission that Westgem did not have the capacity to pay. In response to pressure from Salta to quantify the 'unsubstantial amount' Westgem provided the materials that accompanied its letter of 29 January 2009 which disclosed the Cost Overrun of $17 million. Not only did the additional materials provided by Westgem fail to satisfy Salta's capacity to pay concerns but they provided the material that confirmed Salta's contentions.
  2. In Westgem's reply of 16 February 2010 to Salta's analysis of Westgem's financial materials, Westgem effectively conceded the existence of a breach of the MOFA by its statement that:
Westgem confirm that it is not in substantial breach of the Facility Agreement or Transaction Documents and further, any current technical breach does not affect Westgem's capacity to pay. (emphasis supplied)
  1. My observations about the significance of Westgem's conduct may appear to be directed to the issue of causation. The cases, to which I have referred earlier, acknowledge that there may be practical overlaps in the resolution of the logically distinct questions of characterisation and causation because the characterisation of conduct may involve assessment of its notional effects, judged by reference to its context. I consider that this is a case in which there is such an overlap.
  2. In my view the Finance Parties' conduct, as I have analysed it, was capable of doing no more than making Salta uncertain about whether there had been a breach of the MOFA whereas the provision by Westgem of its financial materials gave Salta the confidence to proceed with a notice of suspension based on the existence of a breach of the MOFA disclosed by Westgem, and its analysis of both of Westgem's financial position and that of Mr Luke Saraceni.
  3. Further, to the extent to which there was any uncertainty on Salta's part about the existence of a breach when it sent its letter of 5 February 2010 that uncertainty was removed by Westgem's letter of 16 February 2010 and the reference in that letter to Westgem 'not being in substantial breach'. The Finance Parties' conduct and any uncertainty arising from it were displaced by the effects of Westgem's own conduct - specifically the acknowledgement of a breach.
  4. The authorities make it clear that the impugned conduct must be assessed as a whole and not in a piecemeal way. That said, the matters particularised under par 291.1 and par 291.2 of the statement of claim are disparate both in nature and timing. Separate comment on each of them is required.

(a) Particular i: It may be accepted that in the relevant period Salta had concerns about Westgem's capacity to pay due, at least in part, because it was concerned that Westgem had breached the MOFA. It may also be accepted that the Finance Parties knew Salta was considering exercising its rights under cl 44 and the Finance Parties knew that if they did not confirm that there had been no breach of the MOFA, it was more likely that Salta would exercise those rights. These are matters of context which I have taken into account in analysing whether there was a reasonable expectation that the Finance Parties would disclose information about Westgem's capacity to pay and whether there had been a breach of the MOFA. Further, I have explained why the 21 August 2009 letter was not a letter to which Salta attached any significance.

(b) Particular ii: There is no evidence that Salta was aware of the communications between the Finance Parties and Westgem concerning payment of the September 2009 progress payment so the 'Financiers assertion of the right to refuse to permit drawdowns resulting in the late payment' did not convey anything to Salta about Westgem's capacity to pay. I do not accept that the late payment, either taken on its own or in the context of the relationship between the parties generally, conveyed anything about the Finance Parties' position in relation to the MOFA or, in turn, Westgem's capacity to pay. Westgem had been late in making progress payments to Salta before the second Cost Overrun was determined.

(c) Particular iii: The appointment of 333 may have caused Salta to think there may have been some difficulties in the relationship between the Financiers and Westgem, which was true, but it would have left Salta in a state of uncertainty as to the nature of those difficulties.

(d) Particular iiiA: The allegation that the Security Trustee had failed to give consent or refusal within a reasonable time to variations that Salta contended were not Permitted Variations within the meaning of the Builder's Side Deed 'by reason of which Salta was concerned that if it performed building work in relation to those variations Westgem would be unable to make drawdowns under the MOFA to pay for those works' was not addressed in Westgem's written closing submissions and was not developed in the oral closing submissions. I am not persuaded that any delay on the part of the Security Trustee in relation to its approach to the approval of variations conveyed anything to Salta about the capacity of Westgem to meet its payment obligations under the Salta Building Contract or about the existence or otherwise of a breach of the terms of the MOFA or the extent to which the Finance Parties were prepared to rely on any such breach.

(d) Particular iv: There was a discussion at the meeting held on 24 February 2010 between representatives of Salta and the Finance Parties' representatives about the possibility of the Financiers exercising their step in rights under cl 7 of the Builder's Side Deed. I accept this discussion would have conveyed to Salta the impression the Finance Parties considered that Westgem had committed a breach of the MOFA and that an Event of Default had occurred upon which the Finance Parties were considering placing reliance for the purposes of exercising their step in rights - all of which was true.

True capacity to pay

  1. Westgem accepts that the case pleaded in par 291.1 of the statement of claim (its 'alternative case') does depend on establishing that there was not a breach of the MOFA which entitled the Finance Parties to withhold advances under the MOFA so as to deprive Westgem of the capacity to meet its payment obligations to Salta. As I have found the second Cost Overrun occurred and, separately, that it constituted an Event of Default, it follows the alternative 'true capacity to pay' case fails.
  2. There are three problems with Westgem's 'primary case' (its contention that the Finance Parties' conduct was misleading because Westgem had not in fact committed a breach of the MOFA, upon which the Finance Parties were prepared to rely, in order to deprive Westgem of its ability to meet its payment obligations to Salta under the Building Contract).
  3. First, the suggestion that the Financiers were not prepared to rely on the second Cost Overrun involves a distortion of the true state of the relationship between the Financiers and Westgem in the period between service of the notice of the second Cost Overrun on 18 September 2009 and Salta's termination. The Financiers' willingness to rely on the second Cost Overrun breach is evidenced by the reliance on that breach as an Event of Default under the MOFA. The default provided the motivation for Westgem and the guarantors to enter the 18 November Letter Agreement. That the Financiers allowed drawdowns to enable Westgem to meet Salta's claims in November and December 2009 and January 2010 while Westgem and the guarantors sought to fulfil their obligations under the 18 November Letter Agreement (as varied) does not mean that the Financiers were not prepared to withhold drawdowns on the basis of the second Cost Overrun or that they would continue to fund payments to Salta regardless of the default. The Financiers had demonstrated by their conduct in relation to the first and second Cost Overruns the importance they attached to Westgem's adherence to the terms of the MOFA. The Financiers had applied the default rate of interest and had refused to allow drawdowns to pay soft costs. To suggest that the Financiers were prepared to continue to make advances if the second Cost Overrun was not remedied is wholly unrealistic. This proposition is not supported by the evidence relied on by Westgem, the limited effect of which, when viewed in context, is that the Financiers were prepared to allow drawdowns on the MOFA to pay Salta while Westgem and the guarantors fulfilled their obligations under the 18 November Letter Agreement.[580] Nor were the Financiers prepared to let drawdowns continue on what was described by Mr Thomson SC on behalf of the Financiers as a 'come what may' basis.[581] Mr Griffiths' evidence was clear - he wanted Salta to remain on site to complete the work but not at any price. And though this is of tangential relevance, it is to be remembered that Mr Griffiths was not prepared to 'give away an event of default that will allow the financiers to act should they wish to do so' unless there was some certainty that waiving the second Cost Overrun default would lead to Salta recommencing work.[582] Mr McDonald said that the Financiers would hold Salta to the cost to complete figure as advised by the Financiers' quantity surveyors. Mr Mahaffy said BOSI was not prepared to support Salta at any price.[583]
  4. Second, disclosure of the information Westgem contends was withheld from Salta, relevantly that Westgem was in breach of the MOFA but the Financiers were prepared to allow drawdowns in November and December 2009 and January 2010, would not have affected Salta's position. It is necessary to add that to avoid misleading Salta by conveying a half truth, the Finance Parties would also have had to disclose that the Financiers had, in fact, relied on the breach as an Event of Default. In my view, if Salta had been informed that the second Cost Overrun had occurred and that the Financiers had given notice of an Event of Default upon which they had relied to refuse to pay the consultants' costs, but that the Financiers had permitted Westgem to make drawdowns to pay Salta in November and December 2009 and January 2010 while Westgem sought to remedy the second Cost Overrun default, it would have provided no level of assurance to Salta that Westgem had the capacity to meet its payment obligations under the Salta Building Contract. There is no reason why Salta would have drawn any comfort from such disclosure unless there was a binding commitment on the part of the Financiers that they would not rely on the breach of the MOFA to withhold any future drawdowns, something the Financiers would never have been prepared to give. In the absence of such a commitment Salta would have known that the Financiers had the option to rely on the breach to withhold further drawdowns.
  5. Third, as pleaded Westgem's 'true capacity to pay' was a concept linked to the funds available to be drawn on under the MOFA, but as Salta had made plain in its notice of suspension of 5 February 2010 it was not satisfied, even if there was no breach, that the funds available under the MOFA would have been sufficient to meet its assessment of the cost of completing the work under the Salta Building Contract.
  6. There is one further matter to add in relation to Westgem's capacity to pay case - that is, its actual capacity as opposed to the 'true capacity to pay construct' pleaded in par 291 of the statement of claim. By February 2010 Westgem was including the cost of construction in its internal assessment as $260 million. For its internal purposes it acknowledged, in effect, the $17 million Cost Overrun but it was unable to fund that Cost Overrun. This was a very substantial obstacle to establishing that the Finance Parties' conduct was misleading.

No representation as to future matters

  1. The misleading or deceptive conduct case based on a representation as to future matters did not feature in Westgem's submissions.
  2. I have found that the Financiers' conduct did not convey any representations to Salta. It is therefore unnecessary to give separate consideration to the alternative formulations of Westgem's case, that there was a representation as to both an existing and a future matter.
  3. Had it been necessary to consider whether the Financiers had reasonable grounds for making the Capacity to Pay Representation,[584] then in accordance with the reasoning above I would have found that Finance Parties had established that reasonable grounds existed for the making of the representations.

Unconscionable conduct and alleged Code Conduct Term breach

  1. It follows from my finding that there was no misleading or deceptive conduct on the part of the Finance Parties that the unconscionable conduct and Code Conduct Term allegations are not established.

Causes of the Salta Stoppage and Salta Termination

  1. In the light of the findings I have made, strictly, it is unnecessary for me to consider the causes of the Salta Stoppage and Salta Termination. I will, however, summarise the conclusions I have reached on these issues and, in the following paragraphs, I identify those matters that I find led to Salta suspending and terminating the Building Contract. There is a substantial overlap between the matters.
  2. First, I infer Salta suspended work and subsequently terminated the Salta Building Contract because it was incurring substantial losses that threatened the viability of its business and it could not see the position improving under the contractual regime established by the Building Contract. In December 2009 Mr Gerrard estimated Salta's losses to be approximately $20 million. Mr Gowdie's February 2010 estimate was consistent with Mr Gerrard's estimate.
  3. Second, Salta's attempts to persuade or pressure Westgem into agreeing to new contractual terms, which had commenced in mid-2009, had not been successful and its attempts to obtain the Finance Parties' assistance to persuade Westgem to negotiate a new contractual regime had failed also. Salta's options were to suspend work and hope that the suspension broke the impasse and, if it did not, thereafter terminate, or continue working under the Salta Building Contract and risk incurring further losses - an option it was not prepared to take.
  4. Third, I infer, Salta considered the prospect of further losses was a real one because, as its representatives had said, in effect, 'it did not know what to build' because of the confusion over construction drawings and the number of variations.
  5. Fourth, though this factor is directly relevant only to the decision to terminate as opposed to the decision to suspend, the decision of the Superintendent to certify a negative amount in respect of payment certificate 33 reinforced to Salta the prospect of further losses and ongoing difficulties with the Superintendent.
  6. Fifth, Salta knew from Westgem's use of contractual notices that Westgem would terminate the Salta Building Contract if it saw an opportunity for it to do so.
  7. Sixth, the relationship between Salta on the one hand and Westgem and the Superintendent on the other, had deteriorated progressively throughout 2009. By February 2010, there was no goodwill between the parties, no trust and no working relationship. This was exemplified by the allegation made by Salta in its 19 February 2010 notice to show cause that the Superintendent had not acted 'honestly and fairly'.
  8. Seventh, Salta estimated that the cost of completing the work under the Salta Building Contract was over $321 million. Its assessment of the materials provided by Westgem was that Westgem did not have the capacity to meet payment obligations of this magnitude even assuming that there had been no breach of the MOFA. Earlier in this part of the reasons I have referred to Salta's pursuit of the capacity to pay issue as tactical - a means to put pressure on Westgem. I infer, however, that Salta had genuine concerns about Westgem's capacity to pay the cost of the work as estimated by Salta and that this was a reason why Salta terminated.
  9. As recorded earlier, even if the Finance Parties had disclosed that Westgem had committed the breach of the MOFA constituted by the unremedied second Cost Overrun but that they had still been prepared to advance funds to pay Salta in the period between November 2009 and January 2010, this would not have provided any assurance or comfort to Salta or dissuaded it from suspending and thereafter terminating the Salta Building Contract.

Losses allegedly suffered as a consequence of the Salta Stoppage and Salta Termination

  1. As noted earlier Westgem claimed that as a consequence of the Salta Stoppage and Salta Termination Westgem had suffered loss in that it had incurred construction costs it would not otherwise have incurred and suffered delays in completion of the Project (that in turn led to lost rental income) that it would not otherwise have suffered. In addition Oakcure contended that it has lost the opportunity of concluding a sale of its interest in the development to Charter Hall.
  2. The Financiers contested the loss claims made by Westgem and Oakcure, that is, they submitted that even if Westgem made out its claims that the Financiers had contravened the statutory prohibitions against misleading or deceptive conduct and unconscionable conduct, and established a breach of the Code Conduct Term, no loss was suffered as a result of the contravening conduct. The Financiers argued that it would have cost Westgem just as much and taken just as long to complete the Project had Salta not suspended and terminated the Salta Building Contract. The time and cost issues, as they were termed in the context of the litigation, are issues involving a very significant volume of detailed factual material, albeit the number of the issues (and their complexity) was reduced considerably as a result of conferral between the experts that took place under the supervision of a registrar of the Court.
  3. As I have found that Westgem has not made out the primary element of the claims - the misleading or deceptive conduct and whether that conduct caused the Salta Stoppage and Salta Termination ‑ it is unnecessary for me to go on to consider whether, had the claims been made out, that conduct caused the loss suffered by Westgem and Oakcure.
PART 4 - MOFA redocumentation claims Overview
  1. On 22 September 2010 the Financiers and Westgem entered into Deed of amendment and restatement: Multi-Option Facility Agreement Raine Square (Restated MOFA).[585] The Restated MOFA increased the borrowing limit under the MOFA by $132.6 million to $448.6 million.[586] The principal was required to be repaid in four tranches: $23 million by 30 September 2010; $27 million by 31 December 2010; $33.1 million by 30 June 2011; and the balance on the expiry of the facility on 30 September 2011.
  2. Westgem alleges that the Finance Parties engaged in unconscionable conduct by entering into the Restated MOFA knowing that Westgem would default on its obligations under that agreement. In addition to advancing its claim as one involving a breach of the statutory prohibition against unconscionable conduct Westgem alleged the impugned conduct involved breaches of the Code Conduct Term, the Event of Default term and the reasonable grounds term.
  3. The cornerstones of the MOFA redocumentation claims were two contentions:

(a) The MOFA redocumentation was caused by the Financiers' notice of default served on 5 March 2010,[587] which had itself been caused by the Finance Parties' wrongful conduct in relation to the first and second Cost Overruns and the capacity to pay conduct, all of which resulted in the Salta Stoppage and Salta Termination. Westgem argued as a consequence of those events the Financiers were able to manoeuvre Westgem into a position where it had no commercial choice but to enter into the Restated MOFA, which imposed obligations with which it was unable to comply. This, it was argued, was the ultimate cause of Westgem's demise. Westgem described the 5 March 2010 default notice as the 'lynchpin' on which its 'extended causation plea' depended.[588]

(b) The Financiers knew, before the Restated MOFA was executed, that Westgem would default on its obligations.

  1. Building on the contentions outlined above Westgem argued the Financiers' conduct constituted unconscionable conduct and breaches of the terms of the MOFA to which I have referred because the Restated MOFA was, in effect, asset lending. Westgem argued the Financiers improved their position significantly without taking any additional risk.[589]
  2. There is a substantial factual overlap between the MOFA redocumentation claims and the Financiers' counterclaim concerning Mr Saraceni's 66.67% interest (held by companies associated with him, Seaport Pty Ltd, the sixth plaintiff, and Single Holdings Pty Ltd) in the 'Vasse Newtown' property development. Unless it is necessary to distinguish between the parties I will refer to Seaport's and Single Holdings' interests as Mr Saraceni's interest in the Vasse Newtown project.
  3. As explained below, I do not accept the Financiers acted unconscionably as alleged by Westgem, and the statutory and contractual MOFA redocumentation claims are not established.
The facts

Vasse Newtown development

  1. Part of the land within the Vasse Newtown development was owned by Seaport and part was owned by Seaport and Single Holdings. In April 2010 the land was valued at $70.4 million.[590] It was subject to a first ranking mortgage to St George Bank which secured a debt of approximately $10 million.
  2. The Vasse Newtown project was the subject of an agreement made on 6 September 2006 between Seaport and Single Holdings and Vasse Newtown Pty Ltd (VNPL) of which Mr Clohessy was a director. VNPL was the corporate vehicle for a syndicate which had invested in the Vasse Newtown project. Pursuant to the agreement dated 6 September 2006 VNPL advanced $31.1 million to Seaport and Single Holdings in consideration for a 33.33% 'profit share' interest.[591] The advance was secured by second ranking mortgages over various titles within the project. Under the agreement:

(a) Interest was not payable, but the advance was to be repaid by providing a 33.3% profit share to VNPL.

(b) VNPL had no recourse if the principal and interest were not fully repaid out of the sale of the property.

(c) VNPL had a right of first refusal in the event Mr Saraceni received an offer to purchase the Project Land from a third party. Subject to affording VNPL the right of first refusal, Mr Saraceni had an unrestricted right to sell the Project Land (other than six specified lots - 'the Excluded Land') which was the subject of the Vasse Newtown project.

5 March 2010 default notice

  1. On 5 March 2010 Bankwest served a default notice on Westgem in which two categories of defaults were identified.[592] First, 'Builder Events of Default', which relied on cl 17.8 of the MOFA (breach or termination of a Material Document). The notice asserted that Salta's threatened suspension, subsequent suspension and termination of the Salta Building Contract were Builder Events of Default, as was Westgem's termination notice. The second category of defaults were described as 'Borrower Events of Default' and the notice asserted that the second Cost Overrun and the failure to pay the second Cost Overrun in accordance with the terms of the 18 November Letter Agreement were defaults falling within this category.

Negotiations leading to indicative terms sheet - March - June 2010

  1. The refinancing negotiations began before the 5 March 2010 default notice was served. On 2 March 2010 Mr Saraceni, Mr Pourzand and Mr Clohessy met Mr Griffiths, Mr Wlossak, Mr Pavisich and Mr Mahaffy to discuss the refinancing of the Project. In his report on this meeting to his colleagues in BOSI Mr Mahaffy said:[593]
There was a lot of love in the room and I was quite impressed with the sponsors' attitude. They said all the right things in terms of their willingness to support the project, and have demonstrated this with action in the form of last month's contribution of an additional $5.0M cash, together with pledges of security and the commitment to an asset sale program the first settlement under which is expected to occur within seven days (with more cash to be contributed to the project). The sponsors firmly believe there is a minimum of $100M equity in the project for them after allowing for cost escalation. Whether there is or isn't remains to be seen but I think the important point is that they believe it to be so and are acting in a manner congruent with that belief. I'm content to work with them ... at least up until the point where it becomes evident that we can't ... which is when I will recommend we assume full control (appointment docs drafted, ready and waiting in case of need).
  1. On 12 March 2010 Mr Saraceni and Mr Pourzand sent a letter to Bankwest attaching a proposal for the financing of the completion of the Project. In the letter and accompanying proposal Mr Saraceni and Mr Pourzand stated:[594]

(a) The cost of the Project had increased by $26 million.

(b) The total construction cost of the 'base building works' had increased from $260 million to $275.8 million.

(c) They proposed to contribute $41.5 million in equity divided equally between them.

(d) Mr Saraceni would contribute $400,000 in March, $17.4 million in June and $3 million in July 2010. Of the $17.4 million to be contributed in June 2010, $14.4 million was to come from the sale of 50% of Mr Saraceni's interest in the Vasse Newtown project as to which the following information was provided:[595]

Vasse 2 - Stage 2 of the Vasse Newtown subdivision currently held 66.67% by the Saracen Group. The project was recently valued at $70m with $10m of debt resulting in Saracen Group value of $40m. The syndicate who hold the other 33.33% have expressed an interest in increasing their ownership of the project. This would assist and expedite the sale process. Seaport would consider selling the full holding but preference is to retain a 33.33% interest with the forecast increased demand for residential land to increase the value of this asset.

(e) Mr Pourzand would contribute $4.3 million in March, a further $5 million in June and $11.5 million by the end of October 2010.

(f) Following the sale of assets required to fund the equity contributions, Mr Saraceni and his interests would hold real property assets with a net equity value of $77.9 million.

(g) On completion of the Project the equity held by Mr Saraceni and Mr Pourzand in it would be worth at least $134 million.

  1. On 23 April 2010 Mr Saraceni sent a letter to Bankwest in which he recorded 'positive discussions are continuing with the syndicate who have a 33.33% interest in the development and we have allowed for the sale to occur in June'.[596] A cashflow attached to the letter showed a projected income of $16 million from 'Vasse 2 Distribution' in June 2010.
  2. On 4 May 2000 Mr Nagle and Mr Nathan met Mr Saraceni, Mr Pourzand and Mr Clohessy. Mr Nathan reported on this meeting by email to Mr Griffiths. I accept Mr Nathan accurately summarised the discussions. He wrote:[597]
Our meeting with the sponsors today was focussed upon their need to revert to the financiers in early course on their proposed asset sales whereby they can progressively meet their additional equity needs albeit it has been identified by 333, in their earlier sponsors review, that to unlock the indicated equity a sales program over several years may be required. Before attending I had a number of discussions with Larry Mahaffy (BOSI) to ensure that there was a general consistency of view in respect to the initial approach. To this end no specifics have been articulated to the sponsors outside of advising that the financiers would consider a request for a facility to the level of the final funding shortfall albeit subject to being provided with additional R1M and or R2M security to 1.5x the facility amount requested (ie. asset equity levels being determined by 333's upper value assessment) with the existing $20m several guarantees also being increased by the sum of the requested facility. We (the financiers/the sponsors) will also need to agree a facility reduction covenant from ongoing asset sales. No commitments have been given to the sponsors but indicated that if they could accommodate these requirements we would be prepared to submit the request to the respective financiers credit process for consideration. I have subsequently spoken to Larry Mahaffy who indicated that BOSI is supportive of the position taken.

I have stressed to the sponsors that time is of the essence given that we/they can not afford to have concluded negotiations with the new builder wherein construction recommencement becomes stalled whilst financing negotiations are undertaken. All in all the sponsors appeared receptive and undertook to investigate how they could achieve the requirements and then revert. They indicated a week or two may be necessary to finalise the detail given the need to bring the building contract price closer to a realistic financing figure plus also to consider security availability etc. give a number of joint venture/profit-sharing arrangement that exist.
  1. On 4 May 2010 Mr Nagle and Mr Nathan prepared a strategy paper for Bankwest's Executive Credit Committee in which they set out the financing terms then being considered by the Financiers and identified the key issues as follows:[598]
    1. It is proposed that the Financiers will seek increased debt funding limits sufficient to complete the Project (assuming no further cash equity is available). Based on current forecasts this could be an increase of [$124.750 million].
    2. Financiers will seek increased recourse to the Sponsors including several recourse for the additional increase in funding. The Financiers currently have a several [$20 million] principal guarantee from each of the Sponsors and joint and several cost over-run guarantees.
    3. Financiers will seek additional security coverage for the increased funding by way of first or second mortgage security. The Financiers will be seeking to maximise the potential additional security coverage.
    4. Re-pricing of the facility with proposed margin of 3.00% p.a. and a Line fee of 1.50% p.a.
    5. An extended Facility Term to expire on 30 September 2011 (4 months after the scheduled practical completion date and corresponding with the rental commencement date for the BankWest tenancy).
In terms of further equity support from the Sponsors we advise that:
  1. Excluding proceeds from asset sales, the Sponsors are considered to have little capacity to contribute further cash equity into the Project at present.
  2. 333's review of the Sponsors financial position undertaken in March 2010 concluded that Saraceni had net equity of between $100 and [$115 million] in real property assets, and Pourzand had between $75 and [$95 million] net equity in real property assets.
  3. 333 identified that this equity may only be realised over an extended 18 - 24 month period.
  4. On 5 May 2010 Mr Griffiths, in anticipation of a meeting with Mr Saraceni and Mr Pourzand on 7 May, expressed the view to Mr Mentha of KordaMentha that:[599]
... Hand over the keys is an option for me. 18-24 months to realise equity is not within my tolerance level.
  1. On 5 May 2010 Mr Nathan sent an email to Mr Nagle about a meeting of Bankwest's Executive Credit Committee due to take place the following day and stated:[600]
Obviously we will need to be in a position to support the proposition of allowing more time to 333 and the sponsors to finalise the building contract numbers plus the funding/security arrangements etc. before bringing in the big guns, (i.e. we are so close an extra few weeks will not make a material difference to the outcome, we will still need to fund building completion under all scenarios, plus a warm body approach will be more beneficial to the financiers if it can be orchestrated) I have also checked with Norton Rose that the sponsor's could just throw the 'Raine Square' keys to the financiers along with a $50m cheque and, subject to a few minor adjustments, in effect walk away.
  1. On 7 May 2010 Mr Griffiths, Mr Nathan and Mr Nagle met Mr Saraceni and Mr Pourzand and Mr Clohessy. Mr Griffiths gave an account of this meeting in his witness statement which I accept.[601] The meeting lasted several hours and involved 'a robust discussion' particularly in relation to delays in recommencing construction and the requirements for further equity contributions to be made by Mr Saraceni and Mr Pourzand. Mr Griffiths said that he wanted all of Mr Saraceni's and Mr Pourzand's remaining assets to be provided as further security to a value of at least 1.5 times the additional funding. Mr Griffiths said he wanted a sales program of the properties to cover the increased project costs. At one stage in the meeting Mr Saraceni turned to Mr Pourzand and said words to the effect 'do you realise the banks can walk out of here and appoint receivers'. Mr Pourzand replied, 'no they wouldn't' and turned to Mr Griffiths and said words to the effect 'you wouldn't do that, would you?' to which Mr Griffiths said, 'yes I would'.
  2. Mr Griffiths reported to the Executive Risk Committee on 14 May 2010. He reported:[602]
Based on estimated cost to complete and assuming no equity contribution from the Sponsors the likely debt funding required will increase to circa $440m.

Current estimated value of the property on completion is $450m and this results in an LVR of 96%.

...

Importantly the Sponsors remain confident in this project and as such will provide additional security. The alternative was for them to hand over the keys and retain their other interests over which we largely have no recourse. In broad terms they see a sale of other assets say $80m to bring debt down to circa $360m plus a sale of 50% of the building at say $225m as bringing the LVR down to circa 60% [$135m versus $225m security]. As you would expect they are hoping for sale values in the range of $475m + as giving them even greater upside.

...

I expect we will have one more tense round of negotiations on additional security after which we can get on with the project.
  1. On 14 May 2010 Mr Saraceni and Mr Pourzand submitted a proposal to the Financiers in the form of a document headed 'Report covering funding, project management and builder prepared for the Financiers'.[603] The introductory paragraphs summarised how Mr Saraceni and Mr Pourzand viewed the Project:
It is vitally important that the Raine Square project moves forward in a commercial manner and although the Financiers have made it clear of their rights to appoint under their securities, we wish to highlight an alternative path which we believe provides a far greater return to all parties.

We question whether any formal appointment would substantially increases the significant control the Financiers already exert. We also have grave concerns of any formal appointment leading to litigious consequences that have not been fully considered by all parties. The flow on effects of a formal appointment leading to events of default of related companies and likely appointments by other financiers can all be avoided as can the ensuing scrutiny of obvious conflicts of interests.

As we see it, it is in the Financier's, Tenant's and Developer's best interests that the building be completed expeditiously.

On completion it has been acknowledged by the Financiers that we have significant equity in this project. Our forecast cost to complete the project, as outlined in section 1 below, results in forecast debt and equity as follows:

Financier's Indicated Value $m
Westgem's Minimum Value $m
Value on Completion
450.0
475.0
Forecast bank debt
351.7
351.7
Net equity
98.3
123.3
LVR
78.2%
74.0%


333 Advisory have also confirmed to the Financiers that we have significant equity in all of our other projects, some of which are outlined in the table in section 2.2 below.

Given this, we respectfully request the right, subject to stringent reporting requirements and compliance with pre-determined budgets, to resume control of project to facilitate completion expeditiously.
  1. In addition, Mr Saraceni and Mr Pourzand stated:

(a) Westgem proposed that the Financiers provide additional funding of $35.7 million;

(b) Mr Saraceni and Mr Pourzand would provide an equity contribution of $46 million;

(c) Mr Saraceni would contribute $17 million of the $46 million equity by 30 September 2010 and Mr Pourzand would contribute $6 million by 30 September 2010 and the balance of $23 million by 31 October 2010;

(d) the 'key asset sale' from Mr Saraceni's perspective was the sale of his 66.67% interest in the Vasse Newtown project which was to be the source of $17 million to be contributed by him by way of equity, and in this respect 'negotiations are in progress with the syndicate holding the remaining interest in the project and it is expected that an agreement for sale will be reached in a timely manner';

(e) Mr Saraceni's interest in the Vasse Newtown project was property over which 'new security' could be provided (subject to the consent of, and in a form suitable to, the primary lenders and the Financiers); and

(f) Mr Saraceni and Mr Pourzand were committed to the sale of a 50% interest in the Raine Square development on completion and:

The project has attracted numerous requests for equity participation despite the current cessation of the building works. The merits and benefits of each offer has been considered by the Sponsors and determined not to be adequate or appropriate at this stage of development and particularly with the current status of building works. These and other parties have expressed interest in investing in the project on completion and discussions are ongoing.

  1. On 19 May 2010 Westgem revised the proposal made on 14 May 2010.[604] The revisions were as follows: Mr Saraceni would contribute an additional $4 million in equity in December 2010 bringing the further equity contribution to $50 million; the personal guarantees from each of Mr Saraceni and Mr Pourzand would be increased to $50 million each; the guarantees in respect of Cost Overruns would remain; the personal guarantees from Mr Saraceni and Mr Pourzand would be increased to cover any situation in which acceptable security could not otherwise be provided; and certain properties would remain as securities. The 19 May 2010 proposal repeated the statement to the effect that Mr Saraceni's interest in the Vasse Newtown project could be provided as security.
  2. On 2 June 2010 Westgem sent a letter to Bankwest in which it recorded, on behalf of Mr Saraceni and Mr Pourzand, that they agreed:[605]
... to the suggestion to increase the size and reduce the number of cash equity contributions and propose to provide two lump sum cash equity contributions (total of $50 million) as follows:
  1. An amount of $23 million on or before 30 September 2010; and
  2. An amount of $27 million on a before 31 December 2010.
The overall cash contributions are affordable to the Sponsors on the basis of the sale of assets as shown in our previous submissions and are relatively consistent in terms of time frame and amount with our previous proposals. (emphasis supplied)
  1. The letter went on to record that:
The Vasse Newtown property is the most significant asset offered as security by the Saracen Group and the targeted source for the majority of the first cash equity contribution. Obtaining suitable security for the Financiers over this property remains an issue due to the existing loan arrangement with Vasse Newtown Pty Ltd. We are however confident that a sale contract will be executed in the near future providing surety around the ability to meet the cash contributions and thus reduce the security requirements.
  1. Under cover of separate letter sent by him to Bankwest on 1 June 2010,[606] Mr Saraceni provided a cash flow for the Saracen Group which included forecast income of $34 million in August 2010 for 'Vasse 2 Distribution'. I infer the figure of $34 million represented the cash that it was anticipated would be received from a disposal of Mr Saraceni's entire interest in the Vasse Newtown project.
  2. On 4 June 2010 Mr David Wheeler, Executive Director of Saracen Properties, sent emails to two third parties (unrelated to each other) in which he referred to revised cash flow statements which showed a sale of 17% of Mr Saraceni's interest in the Vasse Newtown project to 'Mark Clohessy' for $10.2 million in June 2010.[607] The Financiers were not informed of the proposed sale of 17% of Mr Saraceni's interest in the Vasse Newtown project to Mr Clohessy.

Mr Saraceni accepts indicative terms

  1. On 16 June 2010 Mr Burton of Bankwest sent an indicative terms sheet to Mr Saraceni, Mr Clohessy and Mr Pourzand.[608] The terms included terms to the effect that there would be reductions in the principal of $23 million on 30 September and $27 million on 31 December 2010. The terms also included terms to the effect that Mr Saraceni would undertake to sell his interest in the Vasse Newtown project and, in the interim, grant the Security Trustee a mortgage over his shares in Seaport and Single Holdings. The indicative terms provided that the Security Trustee would release this security on the application of $17 million from the proceeds of sale of Mr Saraceni's interest in the Vasse Newtown project in reduction of the debt due under the facility.
  2. On 17 June 2010 Mr Nagle, Mr Galbraith and Mr Nathan met with Mr Saraceni, Mr Clohessy and Mr Dower and went through the indicative terms. Mr Nathan reported to Mr Mahaffy on the outcome of this meeting by an email sent on 17 June 2010 in which he stated:[609]
Just a quick message to let you know that Don, Steve and myself met with Luke Saraceni, Mark Clohessy and Greg Dower this morning to go through the Indicative Terms Sheet. To this end all items have been accepted including the J&S Guarantees, the $33,100 30/6/2011 principal reduction plus also the 100% of net sale proceeds going to debt reduction with only funds from Vasse and 251 St George's being counted towards the designated principal reductions.
  1. On the basis of Mr Nathan's report to Mr Mahaffy I find Mr Saraceni accepted the terms of the Indicative Term Sheet and confirmed that the proceeds of sale of his interest in the Vasse Newtown project would be applied to fund the repayments due on 30 September and 31 December 2010.

Financiers' approval of further funding

  1. On 18 June 2010 Mr Griffiths sent Mr Galbraith an email in advance of a meeting of the Executive Risk Committee that was to take place later that day. In the email Mr Griffiths set out:[610]
Couple of thoughts just in case not covered in your preparation:

* seeking an extension of existing facilities by 2 months to allow finalisation of a proposal.

* Have reached the point where it is clear that funding Westgem to complete the building will be cheaper than making an insolvency appointment.

* In addition provided we get the additional security sought we are in a better risk position.

* We will also improve the documentation such that if further problems emerge including disagreements with the sponsors, we can make an insolvency appointment and take control.

* In broad terms the proposal we are likely to bring to ERC for a decision includes:

* Additional funding of $112m BWA share x

* Additional security real property $x, personal guarantees increased to $x

* Requirement for amortisation from asset sales of $x

* Result is 83% LVR at the outset (although not fully drawn) reducing to 70% by completion of construction.

* Sponsors already talking about the need to sell at least 50% of the project soon after completion of construction
  1. On 30 June 2010 the Executive Risk Committee approved the continued financing of the Project and an increase of $130 million in the Multi Option Facility limit (increasing it from $316 million to $446.6 million) and an increase of $2 million in the GST overdraft facility limit from $3 million to $5 million. Bankwest's contribution to the increased funding would be $70.6 million. Bankwest's continued financial support for the Project was predicated on:[611]
    1. Increased unsupported joint and several recourse to the Sponsors for the full facility amount plus interest, fees and Cost Overruns;
    2. Provision of additional first and second mortgage security for a net equity value of [$72.174 million];
    3. Establishment of an amortisation program totalling [$83.1 million] to reduce the commencing LVR of 87% to 74% by 30 June 2011;
    4. Amendment to Practical Completion and Lease Sunset dates under the BankWest Agreement to Lease to 30 June 2011 and 30 September 2011 respectively (being the dates set at 12 months and 15 months respectively from the proposed date of variation documents);
    5. Formal revaluation of all security properties by 31 March 2011.
The prospect of further Sponsor support through additional mortgage security and deferred amortisation of debt supports the Financier strategy to seek Project completion by the Sponsors rather than through formal administration. The Sponsor strategy is to re-commence the Project and re-establish Project viability and marketability, and to progress a strategy to sell part (50%) or full interest in the Project prior to, or on completion, to reduce debt commitments.
  1. It is convenient to break from a chronological account of the facts to record that on 29 July 2010 Mr Mahaffy and one of his colleagues prepared a submission (a Credit Proposal) to BOSI's Credit Committee for approval of the refinancing approved by Bankwest on 30 June 2010.[612] The Credit Proposal recorded that the first 'repayment milestone' was $50 million on 31 December 2010.[613] The Credit Proposal contained an explanation of the events leading to the proposal and included the following statement:[614]
When it became clear that Salta had neither the willingness nor capacity to continue and that a new Head Contractor had to be appointed, the Joint Financiers considered whether this was best done in a solvent or insolvent environment. Ultimately the Joint Financiers decided to reserve rights consequent upon a series of defaults under the MOF (including facility expiry, substantial unfunded Cost Overruns, failure to complete the Works by the Date for PC), appoint 333 as key construction consultant and work through the Sponsors to procure a suitable replacement Head Contractor in a solvent environment. This was done not so much because the Sponsors have unique skills necessary to procure completion of the works as because they have substantial net equity that they are willing to pledge in support of the Project that would be unavailable in insolvency. Working through the Sponsors in this manner to achieve a satisfactory resolution of the myriad issues confronting this Project has been a complex and time consuming exercise including because we are acutely aware of the de-facto director risk inherent in the situation, as a result of which the Joint Financiers' tier #1 lawyers Norton Rose have been intimately involved every step of the way.
  1. BOSI approved the proposed refinancing.

Mr Pourzand's inability to contribute to proposed $23 million repayment

  1. On 24 June 2010 Mr Pourzand sent an email to Mr Saraceni in which he said:[615]
Im so very sorry to bring it to your attention this morning i got a disturbing call that allen will not be able to make payment to me so therefore it will be impossible for me to make that $6m in september. at best I may be able to get between $1 - 2m.
  1. Mr Saraceni replied by email on the same day and said:[616]
I understand your predicament and we will attempt to satisfy the balance on the 30 September with the sale proceeds from the Vasse land, as long as you put the balance in December when the remaining $27 Million is required.

In other words the bank requires us to make two payments, one payment of $23 Million at the end of September and one of $27 Million in December of which we will make $21 million at that stage and you can make $2 Million. If you are short then by say $1 million we will look at it again to assist if we can.

We were always going to provide $21 million in total with it being $17 million in September and $4 million in December we will bring this $4 million forward to assist. This should satisfy the bank as it fits in with their requirements. On this basis you will then be responsible for the balance required in December.

Fourth Deed of Variation

  1. On about 30 June 2010 the parties executed a deed varying the MOFA by extending the Expiry Date under the MOFA to 31 August 2010.[617]

The sale of Mr Saraceni's interests in the Vasse Newtown Project

  1. On 21 June 2010 Mr Nathan of Bankwest asked Mr Saraceni by email for an update on progress of the sale of the assets which were to fund Westgem's equity contribution to the refinancing. Mr Saraceni responded by email on 28 June 2010. In relation to the sale of Mr Saraceni's interest in the Vasse Newtown project, Mr Saraceni stated:[618]
We have received a genuine cash offer from a substantial Perth based investment company which is slightly lower than our asking price but around acceptable levels and which would comply with the forecasts cash flow previously provided to you. The offer is subject to due diligence with settlement expected by the end of August which we believe to be achievable particularly as the offer is not subject to funding.
  1. On 20 July 2010 Mr Clohessy sent an email to Mr Galbraith informing him that the prospective purchaser of Mr Saraceni's interest in the Vasse Newtown Project was Perron Developments Pty Ltd (Perron) and attached a copy of a letter from Perron dated 9 July 2010, which contained terms and conditions relating to that acquisition.[619] The letter recorded that Perron was interested in purchasing the whole of Mr Saraceni's 66.67% interest in Vasse 2. In the accompanying email Mr Clohessy said '... we have given the Perron Group a 28 [day] due diligence period on Vasse ...'.
  2. On 29 July 2010 Mr Clohessy responded to a query from the Financiers' solicitor regarding the sale of Mr Saraceni's interest in Vasse Newtown stating 'due diligence is proceeding well and we anticipate it will become unconditional, draft contracts are being drawn and I will forward a copy when I receive it'.[620]
  3. Mr Clohessy's email of 29 July 2010 led Mr Mahaffy to think the sale to Perron was progressing and increased his confidence that the Westgem parties' equity contributions would be forthcoming.[621]
  4. On about 9 August 2010 Mr Galbraith reported that he had been advised that, aside from one minor local government planning issue, Perron had completed its due diligence and contracts were expected to be exchanged in 7 - 10 days in respect of the acquisition by Perron of part of Mr Saraceni's interest in the Vasse Newtown project.[622]
  5. On 23 August 2010 Mr Saraceni replied to a question from Mr Pourzand about the progress of the Perron negotiations in the following terms:[623]
The negotiations with Perron Group are not looking promising as they are unable to reach a suitable agreement with Mark Clohessy's group. At this stage Perron are being unreasonable with the control that they want and Marks group is unlikely to agree to accommodate their position. I am still working on other alternatives which involve Marks group and have not completely disregarded that the Perron Group may concede some points on the joint venture with Marks group.

We are continuing to work actively on all these areas and I have a large amount of resources engaging in trying to secure the equity injection deal with one of the above groups.
  1. The Financiers were not informed that the negotiations with the Perron Group were not looking promising.
  2. On 24 August 2010 Mr Geoff Hanson of Hanson Property sent an email to Mr Ray Fitzgerald of the St Ives Group (both of whom were involved in various ways with the Vasse Newtown project) which was copied to Mr Saraceni and Mr Clohessy among others, in which Mr Hanson made statements to the effect the sale to Perron was not proceeding and VNPL would be increasing its share in the Vasse Newtown project to 50% and that Mr Saraceni might sell down his remaining 50% interest.[624] The Financiers were not informed of these developments.
  3. On 24 August 2010 Mr Saraceni had an exchange of emails with the Financiers' lawyers in which he complained in forceful terms about the inclusion of a clause in the proposed mortgage over his shares in Seaport providing for the payment of interest in the event of a default in the payment to be made from the proceeds of sale of his interest in the Vasse Newtown project. Mr Saraceni made no mention of any proposal to dispose of a proportion of his interest in the Vasse Newtown project to VNPL.[625]
  4. On 25 August 2010 Mr Clohessy sent an email to Mr Pourzand and Mr Saraceni in which he referred to a conversation earlier that day with Mr Pourzand, and stated that the terms of the Perron Group's offer were not acceptable (by implication to VNPL) and that he and Mr Saraceni would continue to pursue other options regarding the sale of Mr Saraceni's interest in Vasse Newtown.[626]
  5. On 27 August 2010 Seaport, Single Holdings and VNPL executed an agreement varying the agreement between them concerning the Vasse Newtown project (the Variation Agreement).[627] The effect of the Variation Agreement was that Mr Saraceni reduced his interest in the Vasse Newtown project from a controlling interest of 66.67% to a minority interest of 49%, in consideration of payment to it (or at its direction) of the sum of $7,236,591 (the total consideration included a further $1,617,165 which was used to reduce existing indebtedness owed by Mr Saraceni's interests to VNPL). The payment of $7,236,591 was to be made on 10 September 2010.[628] The Variation Agreement conferred an option on VNPL, exercisable within 60 days, to increase its interest to a 66.67% interest by making a further cash advance of $7,851,447.[629]
  6. The Financiers were not informed of the making of the Variation Agreement.
  7. On 30 August 2010 Mr Clohessy sent an email to the Financiers' solicitors in which he stated that VNPL would not permit any form of security over Mr Saraceni's interest in the Vasse Newtown project in support of the Restated MOFA, and that VNPL needed an ability to deal with their loan agreement with Mr Saraceni's interests in any way it saw fit prior to those interests entering into an unconditional sales contract.[630] Mr Clohessy stated:
There are innumerable reasons we might want or need to make accommodations to Seaport up until it enters into an unconditional contract of sale and this might include increasing our interest in the project, further we hold a first right of refusal over Seaport's interest in the project.
  1. Mr Clohessy did not disclose that the sale to the Perron Group had fallen through, nor did he disclose that Mr Saraceni had reduced his interest in the Vasse Newtown project to a 49% interest and that VNPL now held a 51% interest.
  2. On 31 August 2010 a number of emails were exchanged between Mr Galbraith and Mr Saraceni and Mr Clohessy.[631] At 7:31 am Mr Galbraith sent an email to Mr Saraceni. He stated:[632]
We need your urgent input here with respect to Vasse Newtown and need to discuss jointly with BOSIAL and Norton Rose.

Two questions:-

What is the level of the credit limit (if any) and indebtedness that Seaport has to Vasse Newtown currently / can this be capped?

What is the status of the negotiations with Perron? / will it settle prior to 30/9/2010?
  1. Mr Saraceni responded and stated:[633]
The level of indebtedness is approximately $9.5 million. This cannot be capped as the joint venture partners want to proceed with the next stage of development which has a substantial level of presales. This is a successful ongoing project and it is unlikely that Vasse Newtown Pty Ltd will agree to this capping.

The Perron Group negotiations are continuing however they are required to also reach an agreement with Vasse Newtown Pty Ltd in order to enable the deal to be finalised. (emphasis supplied)
  1. Mr Clohessy also replied to Mr Galbraith following Mr Saraceni's reply. Mr Clohessy said:[634]
Luke has I think misunderstood your question, he has detailed the St George debt. The Vasse Newtown facility is limited to 33.33% of all net proceeds from the sale of the project plus any other amounts owed ... As Luke has mentioned given the nature of the investment Vasse Newtown will not agree to any capping of amounts owed. (emphasis supplied)
  1. Later on 31 August 2010 Mr Clohessy sent an email to Mr Galbraith, which was copied to Mr Saraceni, in which he stated:[635]
The status of the Perron deal is that they called me tonight to discuss a possible resolution to the core problem we have in moving forward. Their proposal has merit but I will try to make contact with the other Directors to discuss asap. It does however require some examination of the project cash flow which I am trying to do tomorrow.
  1. Neither Mr Clohessy nor Mr Saraceni disclosed:

(a) the negotiations with the Perron Group were not continuing;

(b) there was no 'Perron deal';

(c) the Variation Agreement had resulted in an increase in VNPL's interest to 51% and a reduction in Mr Saraceni's interest to 49% which had the effect of preventing the Perron deal from proceeding.

Discussions between Mr Saraceni, Mr Clohessy and Mr Pourzand

  1. Also on 31 August 2010 there was a meeting between Mr Saraceni and Mr Pourzand attended by some of their family members and advisers. Later in the day emails were exchanged between Mr Saraceni and Mr Pourzand, copied to Mr Clohessy, Mr Ellis (Mr Pourzand's solicitor) and Mr Lafferty (Mr Pourzand's accountant). The exchange began with an email from Mr Pourzand in which he wrote:[636]
Thanks for the meeting today, it was constructive and informative. As we discussed, based on previous commitments you are providing the first tranche of $23M by 30.9.10 (or whenever agreed with the bank) and i will provide $27M being the second tranche by 30.12.10 (or whenever agreed with the bank).

It was good to see that you have different pros and cons of going ahead with each option - i look forward to the next meeting to digest what else we need to do. It was also good to see Joels involvement and understanding of the project, Farah commented on that after the meeting. Please keep me informed regarding Vasse - and any progress made.
  1. Mr Saraceni replied:
I’m glad that you understand the options that we have and the risks associated either way with signing the documentation or not signing.

In relation to the first $23 million tranche - yes now that you have said that you will not be able to come up with your $6 million which was originally proposed we will see what we can do to help.

Please note that when you last raised the fact that you may not have the $6 million we said that we would endeavour to come up with $21 million (ie $17 million as part of the first tranche and $4 million as part of the second tranche) (see the attached email we sent you in that regard). However I now understand you may struggle with any amount at this stage and we will endeavour to cover this if at all possible.
  1. I infer from the account of the meeting contained in this emails that Mr Saraceni and Mr Pourzand discussed, and assessed, the risks of entering the Restated MOFA and the risks of not entering the Restated MOFA, and that they did so in an environment in which they had legal and accounting advice available to them. In fact Mr Pourzand's solicitor had provided written advice in relation to the drafts of the Restated MOFA that were current as at 11 August and 24 August 2010.[637]

Fifth Deed of Variation

  1. On 31 August 2010 the parties executed a deed varying the MOFA by extending the Expiry Date under the MOFA to 30 September 2010.[638]

Westgem indicates willingness to execute Restated MOFA

  1. On 1 September 2010 there was a meeting attended by Mr Galbraith, representatives of 333 and Norton Rose and, I infer, Mr Saraceni and Mr Clohessy. Mr Galbraith reported by email to Mr Lowan, Mr Griffiths and others on the meeting and said:[639]
We have had a long meeting with Westgem and with others (Norton Rose and 333) where the discussions eventually settled on the Vasse Newtown security and inability of Saraceni/Seaport to encumber its interest in the shares that it holds in Vasse Newtown and/or any contract of sale proceeds due to negative pledges with: -

St George (lending facility is $9.5 M secured by property worth [approximately] $70M) priority with Vasse Newtown.

Vasse Newtown priority (shareholder clause where if a shareholder cannot fund they potentially get diluted/pre-emptive rights & not unusual).

...

Perron is negotiating with the other investors in Vasse (there are 52) via Mark Clohessy (Vasse Newtown Director) on terms for the ongoing development funding and this needs to be agreed prior to execution of the sale contract for Saraceni's share holding.

Westgem, Saraceni and Pourzand are prepared to sign loan documents.

...

On the basis that we cannot get the charge over either Saraceni's shares and units in Vasse Newtown and/or the claim over the sale proceeds from Vasse Newtown then the Financiers proceed without these on the basis that we will have: -

a mortgage over the shares in Seaport (which holds the interest in Vasse Newtown in trust for the two named beneficiaries being Mr and Mrs Saraceni who will provide their consent and irrevocable instruction for the trustee [Seaport's sole director is Luke Saraceni] to pay to the Facility Agent $17.5M on their behalf from the proceeds of Vasse Newtown per page 9 of CRS dated 28/6/10).

all other documentation in place per our approvals.

financial close by 3/9/2010 (assumes that all is agreed today/tomorrow) and building works potentially start Monday, 6 September 2010.
  1. I infer from Mr Galbraith's email that in the course of the meeting Mr Saraceni said that Westgem would execute the Restated MOFA. I also infer that neither Mr Saraceni nor Mr Clohessy disclosed the fact that the sale of Mr Saraceni's interest in the Vasse Newtown project had fallen through and Mr Saraceni's interest had been reduced to a 49% interest as a result of the Variation Agreement.
  2. It is clear from the email that the Financiers remained under the impression Perron was still interested in acquiring Mr Saraceni's interest in Vasse Newtown.
  3. Mr Griffiths accepted the recommendation made by Mr Galbraith in relation to the taking of security over Mr Saraceni's interest in the Vasse Newtown project.[640]

Mr Clohessy explains the Variation Agreement to the VNPL investors

  1. On about 2 or 3 September 2010 Mr Clohessy sent a letter to all investors in VNPL in which he outlined what had occurred with Mr Saraceni. The account provided by Mr Clohessy to the investors in Vasse Newtown provides some insight into why the Perron deed had fallen through. It is to be contrasted with the information provided by Mr Clohessy to the Financiers. In his letter to the investors Mr Clohessy stated:[641]
... To recap, in short the project has stalled since late last year due to difficulties our partner Luke Saraceni is having with his Raine Square project. The builder walked off the site in December last year and subsequently the costs of completing the project have blown out and it has taken until the last week for him to get another builder and bank approval to restart. Because of this the lender on Vasse Newtown, St George Bank, has been reluctant to approve the next stage until they see a restart of the Raine Square project.

The impact of this on Saraceni has been that he needs additional cash to inject into the Raine Square project and consequently he informed me in April that he needed to sell his 66.6% interest in Vasse Newtown. You may remember we have a first right of refusal to buy his share, however in this market the amount of cash required is beyond us given the time constraints. The issue for us is that if we are not the buyer of his share he can offer the whole project for sale and in this market we could lose 30% or more of our equity.

For this reason in May we agreed that we would try and find a buyer for his share. Our strategy was for us to increase from our current 33.3% to 50% and seek a new partner of the other 50%. (The idea being to at least be a 50% partner giving us control over our investment going forward). The property was valued at $70m in April this year and has an existing debt to St George Bank of approximately $10m. After speaking to a number of potential buyers the Perron Group offered to take all Saraceni's share, however the terms they proposed for the joint venture going forward were not acceptable to us.

In short, they did not want to borrow funds against the project land for future development costs i.e. they were happy to pay cash for future works and this is not acceptable to us. You will remember currently that all project debt is borrowed against the property which is both the norm and sensible from our perspective.

The Perron Group then approach Luke to sell the entire asset to him which would have forced us to match the offer or be bought out resulting in the loss of a significant portion of our equity.

Fortunately Saraceni was not agreeable to sell to them unless they could reach agreement with us going forward, however it still leaves him in need of selling all or some of his 66% share of the project. (emphasis supplied)
  1. Mr Clohessy went on in the letter to explain that to protect its interests, VNPL had agreed to increase its share in the project to 51% and this meant that it was necessary to raise an additional $7.2m to move up to the 51% profit share'.[642]
  2. I infer from the account of events set out in Mr Clohessy's letter to the investors in VNPL and from the terms of the 6 September 2006 agreement between Mr Saraceni's interests and VNPL[643] that Mr Saraceni could have sold the entire Vasse Newtown project to the Perron Group and realised $33 million. He chose not to do so, however, because he was not prepared to sell a proportion of the Vasse Newtown project unless the Perron Group could reach agreement with VNPL.

Mr Clohessy explains the Variation Agreement to Mr Pourzand

  1. On 6 September 2010 Mr Clohessy sent an email to Mr Joel Saraceni, Mr Luke Saraceni's son, in which he asked whether Mr Joel Saraceni had said anything to Mr Pourzand about Vasse Newtown.[644] Mr Joel Saraceni replied:
No, he pressed me on it this morning and i told him we were still working on it and doing our best. Pretty vague I know but i thought i would leave it to Luke to elaborate. He seemed more pre-occupied with what came out of HK.
  1. Mr Clohessy responded:
Joel I do not want this to become a problem. Nigel has clients in Vasse and he is aware we are increasing to 51%. I dont think we can go past tomorrow without saying something???
  1. Mr Joel Saraceni responded:
Alright - we will let him know tomorrow what our new strategy with Vasse is. It should probably come from luke though, [so] I will talk to him about it tomorrow.
  1. On 7 September 2010 Mr Clohessy sent an email to Mr Pourzand in which he stated:[645]
Hossean, hi, the situation with Vasse is that I could not reach agreement with the Perron Group on Vasse.

Some of their terms were just not acceptable from our investors perspective. For this reason we reached agreement with Luke to assist him with his urgent cash flow requirements by increasing our interest in the property whilst still allowing him to continue to sell down the his remaining interest. I am still talking to a number of other parties.

Mr Clohessy explains the Variation Agreement to the Financiers

  1. On 9 September 2010 Mr Galbraith sent an email to Mr Clohessy asking whether there had been any further developments with Vasse Newton with Perron.[646] Before he replied to Mr Galbraith, Mr Clohessy sent a draft of his proposed reply to Mr Saraceni and Mr Greg Dower for their comments. Mr Clohessy's response to Mr Galbraith (sent also to Mr Nagle, Mr Nathan and Mr Mahaffy) incorporated the comments of Mr Saraceni and Mr Dower on the draft. The response sent by Mr Clohessy included the following:[647]
Seaport had reached an in principal [sic] agreement with Perron with respect to the sale of its 66.66% interest which would have resulted in net proceeds of 33m however Vasse Newtown and Perron were unable to reach agreement on the new JV terms. The failure of this sale to go forward has placed The Saracen Group under cash flow pressures and it therefore reached agreement with Vasse Newtown to extend its loan facility and profit share. Seaport’s remaining interest in the project remains for sale and is still sufficient to meet the requirements of Westgem for principle [sic] reductions under the MOFA. Both Seaport and Vasse Newtown are exploring all possibilities of sale of Seaports interest and still have a number of interested parties with whom serious negotiations are being discussed. In addition Vasse Newtown are looking at taking some or all of Seaport’s remaining equity.

...

This project needs to be restarted now, there may be a few boxes left un ticked but surely the facts remain;
  • The sooner it recommences it will finish
  • Commencement will allow lease up to progress
  • If it is finished it has its maximum value
  • Maximum value provide safety for all parties
Over recent months Luke's office has been negotiating with a number of international Banks and Institutions to take an equity or mezzanine position in Raine Square and in coming weeks we hope to have meaningful discussions with the current lenders to present end takeout solutions. Interestingly after extensive due diligence by all of these groups one comment remains constant and that is why has it taken 10 months to get this project restarted. The risk of end building cost blowout has been vastly overtaken by the costs of delay to recommence, namely interest penalties, legal fees, consultants costs and lack of competitive pressure on the builder.
  1. On 10 September 2010, in response to Mr Clohessy's email of 9 September 2010, Mr Galbraith asked whether Mr Clohessy was available at 10:30 am to discuss the price and timing of the likelihood of sale to other shareholders or other parties. Mr Clohessy responded that he was in a board meeting and stated 'Vasse timing unknown until we get a bit closer but working on it'.[648] Mr Clohessy did not disclose that Mr Saraceni had already reduced his interest to 49%.

Building Contract with Probuild

  1. On 13 September 2010 Westgem entered a building contract with Probuild to complete construction of the Project.[649]

Mr Saraceni's communications with Mr Griffiths regarding Goldman Sachs

  1. On 14 September 2010 Mr Saraceni sent Mr Griffiths an email about the possibility of Goldman Sachs acquiring an interest in the Project. Mr Saraceni stated:[650]
By way of background, Goldman Sachs (GS) has proposed a highly attractive recapitalisation proposal, one that we believe could substantially benefit all stakeholders in the Raine Square project as well as significantly reduce the banks current exposure.

In essence, the GS proposal seeks to achieve the following significant outcomes:
  1. GS funds all of the costs to complete the Project via one of its global real estate funds; and
  2. Minimum 3 year non-recourse term funding is provided and is set within current bank lending policy.
We are hoping to meet with you to discuss this. The purpose of the meeting will be for GS to outline a cooperative approach, including highlighting what adjustments might be required to our existing funding and other arrangements, in order to achieve the above outcomes.
  1. Mr Saraceni asked about Mr Griffiths' availability to attend a meeting with him and representatives of Goldman Sachs.
  2. On 15 September 2010 Mr Griffiths sent Mr Barnes of CBA an email seeking advice on issues arising from the possibility of Goldman Sachs becoming involved with the Project. In the email Mr Griffiths commented:[651]
On the basis that probable market value is less than cost to complete; a position made worse by the holding costs over the past 9 months where the project had stalled, I expect other assets of the sponsors will need to be sold to get debt sizing to acceptable parameters.

Further communications between Mr Clohessy and Mr Pourzand

  1. On 12 September 2010 Mr Pourzand sent an email to Mr Clohessy outlining the difficulties he was facing in relation to the Raine Square project. Mr Pourzand wrote: [652]
Thanks for your email. I have had time to think about it, since I bearly got any sleep last night. I am still not feeling 100% and have to go for X-rays and blood tests today. I hope Luke does not leave things until the last moment - I put in whatever i had and borrowed against my other facility in order to top up the Esplanade and helped Luke. Now there is a juggling pressure on me with the rental values coming down along with increasing margins, i am finding it all very difficult. Considering my position, what would be the implications on Raine Square, and what do you think the banks reaction would be? Please provide your advice at your earliest convenience.
  1. Mr Clohessy responded as follows:
Hossean hi, re your email below I have informed Don about the situation with Vasse and I think the issue still remains as to what their reaction will be if the principle reduction isn't made on Sept 30th. In one of our meetings recently Luke asked directly about this issue and got the response that the bank would 'consider its position at the time'.

My personal view is that they will charge penalty interest and reserve their position but continue on with the project. It's difficult seeing them take too drastic a response having made the decision to fully fund the development.

Clearly it would be better not to test them however and make the reduction if possible. Alternatively we need to have an alternative takeout scenario like the one Luke is working on with Goldman Sachs. (emphasis supplied)
  1. On the basis of the sentence to which emphasis has been added in the quote from Mr Clohessy's email to Mr Pourzand of 12 September 2010 above, I find that Mr Saraceni had raised the possibility that Westgem might not be able to make the $23 million payment on 30 September 2010. I think it likely that this possibility was raised with Mr Galbraith with whom Mr Clohessy and Mr Saraceni appeared to have the most contact at this stage. I infer, however, from Mr Clohessy's remark that '... it would be better not to test them however ...' that Mr Saraceni had not told the Financiers that the payment would definitely not be made.
  2. On 16 September 2010 Mr Pourzand sent an email to Mr Saraceni, Mr Clohessy and others in which he stated:[653]
September is coming to an end and there are many issues to be resolved. The 3 asian parties with their potential term sheets, capital security purchasing more in vasse, potential jv on vasse regarding other party. The time is running out and we need to know where are we going to be by the end of this month. And if these matters haven't been resolved lukes going to address the default rate and the unhappy banker. We have to make sure that we make our best endeavour to honour the commitments we've made. Looking at the past and making room for lukes wiggling wouldn't work this time from what I hear from various sources of information. Please whatever you guys are doing make sure we don't push them to the dead end. Please provide me with whatever deal happening on any front regarding the funding for raine square, so long as its inline with what's been previously agreed.
  1. Reading the reference to the '3 asian parties with their potential term sheets' in conjunction with the statement contained in the 14 May 2010 proposal that 'The project has attracted numerous requests for equity participation despite the current cessation of building works' I infer that Mr Pourzand was aware that there were third parties who were interested in acquiring an interest in the Project, a matter to which I will refer in more detail later. I also infer from the content and tenor of Mr Pourzand's email that Mr Saraceni and Mr Clohessy were taking the lead in managing the relationship with the Financiers and, at this stage, Mr Pourzand was playing a secondary role. In making his assessment of whether Westgem would be able to make the $23 million payment Mr Pourzand depended on information provided to him by Mr Saraceni and Mr Clohessy.

Exchanges between Financiers regarding $23 million repayment

  1. On 22 September 2010 Mr Galbraith sent an email to Mr Mahaffy in which he asked Mr Mahaffy to confirm if his 'approvals provide for deferral of the $23M debt reduction due 30/0/2010 to be $50M by 31/12/2010'. Mr Mahaffy replied, 'Confirmed'.[654]
  2. Also, on 22 September Mr Galbraith sent an email to Mr Nathan and Mr Nagle in which he stated:[655]
We have had no formal request from Westgem to extend the repayment terms however Luke is meeting with Ross Griffiths this Friday. I will likely go over for this meeting.

We need to start a brief paper to detail current status and rollup the $23M in September to $50M in December 2010.

Restated MOFA executed

  1. On 22 September 2010 the Restated MOFA was executed. There was some uncertainty in the evidence as to when the Restated MOFA came into effect. Mr Mahaffy's evidence was that he executed the Restated MOFA on 22 September 2010 but that 'the parties completed execution of the [Restated MOFA]' on 24 September 2010.[656] A Bankwest strategy paper prepared by Mr Nagle on 24 September 2010 (referred to below) stated 'Financial Close on the re-structured development finance facility was achieved on 24 September 2010'.[657]

Restated MOFA representations and warranties

  1. The Restated MOFA contained representations and warranties (the Restated MOFA warranties) to the following effects:

(a) There was no material fact known to them that had not been disclosed by them to the Facility Agent which would materially and adversely affect the business, assets, revenues or financial condition of any transaction party including Seaport and Mr Saraceni or both, or their capacity to perform their respective obligations under the Restated MOFA or the Seaport Share Mortgage.[658]

(b) To the best of their knowledge and belief, there was no material facts known to them that had not been disclosed to the Facility Agent, which could reasonably be expected to be material to the assessment of the nature and amount of the risk undertaken by the Financiers in entering into the Restated MOFA or the Seaport Share Mortgage and doing anything in connection with them.[659]

(c) All reports, financial information, models and any other written information provided by them to the Finance Parties (including the feasibility study and cash flow for the Project) were true and accurate in all material respects were not misleading in any material respect (whether by omission or otherwise) as at the date to which they were prepared or provided (as the case may be) and all written forecasts and projections provided by them to the Finance Parties were based on reasonable grounds, had been made in good faith and had not materially changed since that provision to the Finance Parties.[660]

(d) They were not aware of any event or series of events which had occurred which would or would be reasonably likely to have a material and adverse effect on the ability of Saraceni, Seaport or both to comply with their obligations under the Restated MOFA and/or the Seaport Share Mortgage (or both) or the value of the security property provided under, amongst other securities, the Seaport Share Mortgage.[661]

Seaport Share Mortgage

  1. Among the further securities executed in favour of the Security Trustee and held by it on behalf of the Financiers, was a mortgage by Mr Saraceni over his shares in Seaport - the Seaport Share Mortgage. The Seaport Share Mortgage contained representations and warranties (the Seaport Share Mortgage warranties) to the following effects:

(a) All information given and each statement made to the Security Trustee in relation to the Share Mortgage and Restated MOFA was correct, complete and not misleading.[662]

(b) Mr Saraceni had disclosed to the Security Trustee all information that he had or had access to and that was relevant to the assessment by the Financiers of the nature and amount of the risks undertaken by the Security Trustee becoming a creditor of Seaport or taking a Security interest from Seaport.[663]

(c) The warranties and representations given by Mr Saraceni under the Restated MOFA and of the Share Mortgage were correct and not misleading or would be correct and not misleading when given.[664]

The Goldman Sachs proposal

  1. On 23 September 2010 Mr Galbraith sent an email to Mr Griffiths about attending a meeting with Mr Saraceni and representatives of Goldman Sachs which was scheduled to take place the following day -the meeting was being held in Sydney and Mr Griffiths had suggested that it was unnecessary for Mr Galbraith to attend. In his email Mr Galbraith stated:[665]
If you do not mind I would like to attend tomorrow to ensure that I have a clear view on where he is heading given the current $23M repayment obligations due 30/9/2010 (and get your thoughts on extension of this repayment to 31/12/2010). (emphasis supplied)
  1. On 24 September 2010 Mr Griffiths and Mr Galbraith attended the meeting with Mr Saraceni and representatives of Goldman Sachs to which Mr Galbraith had referred in his email of the previous day. At the meeting the Goldman Sachs representatives presented a proposal for the recapitalisation of the Project.
  2. On 24 September 2010 Mr Nagle sent an email to Mr Galbraith asking for an update following Mr Galbraith's meeting in Sydney with Mr Griffiths and Mr Saraceni. Mr Nagle required the update so that he could include the latest position in the strategy paper he was preparing. Mr Galbraith replied by an email in which he stated:[666]
Meeting went well and bottom line is that GS need to refine their proposal.

GS high level was:

* Discount debt

* Increase rent

* GS provides mezzanine

* Senior debt resized to lvr ~ 52% and extended 2 – 3 years post completion

* Hossean sells hotel property and exits

* BWA Tower obligation met

As it stands it is not acceptable and GS are to discuss alternatives with LS / MC.

We will have a meeting with LS / MC late morning on Tuesday in Perth.

Made Ross aware of the impending debt reduction of $23M and view is that they make $6M as $17M was to come from Vasse.

If we defer the $23M to 31/12/10 impact on cash flow ($23M x 8%) is~$0.5M.

We do not want further delays on build so will consider deferal.

That's about it.
  1. I infer from Mr Galbraith's email to Mr Nagle of 24 September and his email exchange with Mr Mahaffy on 22 September 2010 that by 22 September 2010 he had reason to think that Westgem would not be able to make the repayment of $23 million on 30 September 2010 and that he had real doubt as to whether that repayment would be made or, at least whether it would be made in full. It that were not the case, it is unlikely that he would have asked Mr Nagle and Mr Nathan to prepare a strategy paper.
  2. On 24 September 2010 Mr Nagle prepared a strategy paper for the Executive Risk Committee of Bankwest that recommended approval of the deferral of the principal repayment of $23 million due on 30 September 2010 and to increase the principal repayment due on 31 December 2010 from $27 million to $50 million. The recommendation was supported by Mr Nathan and Mr Galbraith.[667] The purpose of the paper was to 'seek credit approval to defer the principal repayment of $23 million which was due on 30 September 2010'. Under the heading 'Amortisation' the following was recorded:
The [$23 million] payment due as at 30 September 2010 was to be made from part sale proceeds of Saraceni's net interest in the Vasse Newtown land development project [$17 million] and cash [$6 million].

Saraceni and the other joint venture counterparty in the Vasse Newtown asset were in advanced negotiations with the Perron Group for the sale of Saraceni’s interest ... the Perron Group was unable to agree terms with the remaining joint venture entity and the transaction failed to proceed ...

...

Saraceni has advised that sale negotiations are continuing with other parties, however the timing of this remains uncertain.
  1. I infer from the reference to Mr Saraceni's advice that sale negotiations are continuing with other parties that none of Mr Nagle, Mr Galbraith or Mr Nathan understood that Mr Saraceni had reduced his interest in the Vasse Newtown project to 49%.
  2. On 28 September 2010 Mr Galbraith sent an email sent to Mr Sutton and others in Bankwest in which he summarised what had been discussed at the meeting in Sydney on 24 September 2010.[668] The email was not sent to Mr Griffiths but, in his witness statement, he referred to it and said that Mr Galbraith's summary was consistent with this recollection. I accept the email provided a reliable account of the discussions - it was consistent with what had been recorded by Mr Galbraith in his email to Mr Nagle and Mr Nathan of 24 September 2010. The proposal put forward by Mr Saraceni at the meeting included terms to the effect that Goldman Sachs would buy BOSI's debt at a discount and Mr Pourzand would sell his interest in the Project for $18 million. Mr Galbraith also recorded that Mr Saraceni was 'talking with two other parties (JP Morgan and Forum Partners) whose proposals were considered inferior to GS'.

Proposal to defer $23 million repayment to 31 December 2010

  1. Mr Galbraith's 28 September 2010 email contained a section headed 'Westgem Debt Reduction of $23M due 30/9/2010'. In this section Mr Galbraith recorded that BOSI held approval to 'roll this reduction to a lump sum of $50M ($23M plus $27M) on 31/12/2010' and that Mr Griffiths was aware of this and was supportive.

Mr Griffiths' knowledge of the possibility of the $23 million repayment not being made on 30 September 2010 and the dilution of Mr Saraceni interest in the Vasse Newtown project

  1. Mr Griffiths' witness statement did not disclose the circumstances in which he became aware that Mr Saraceni had not sold his interest in the Vasse Newtown project, as Mr Saraceni had represented he would, and that the $23 million repayment would not be made on 30 September 2010.
  2. Mr Griffiths' evidence was that he had no recollection of Mr Saraceni asking, at the 24 September 2010 meeting, the Financiers to consider giving Westgem an extension of time within which to make the payment of $23 million due on 30 September 2010 but accepted that it was possible that he had done so.[669]
  3. Mr Griffiths was cross-examined at some length about when he became aware that the sale of Mr Saraceni's interest in the Vasse Newtown project was not going to occur in time for the proceeds of sale to be available to fund the payment of $23 million that was due to be made on 30 September 2010 and that Westgem wanted to defer that payment.[670] Mr Griffiths said he had no recollection about when he became aware of this and I accept that was so. Much of the cross‑examination on this topic was directed to reconstructing the sequence of events around the time the Restated MOFA was executed (the impression I formed was that much of Mr Griffiths' evidence was a reconstruction of events based on an examination of the contemporaneous documents - this was understandable and my observation is not critical of Mr Griffiths personally).[671] Mr Griffiths accepted that it was probable that he would have been 'extremely angry' if he had been told the day after the Restated MOFA had been made that the payment was not going to occur and that he would have felt that he had been misled. Mr Griffiths accepted that if the meeting held on 24 September 2010 was the first occasion on which he had learned that the $23 million payment would not be made on 30 September 2010 he would have remembered that to be the case.[672]
  4. Mr Griffiths' witness statement did not include a statement to the effect that he was not informed prior to the execution of the Restated MOFA that Mr Saraceni had not sold his interest in the Vasse Newtown project and that he could not contribute $17 million towards the $23 million payment due on 30 September 2010. In the course of cross‑examination, however, he denied he knew, prior to the entry into the Restated MOFA, that the sale of Mr Saraceni's interest was not going ahead.[673]
  5. The absence of contemporaneous documentary evidence establishing when and how Mr Griffiths was informed that Mr Saraceni's sale of his interest in the Vasse Newtown project was not going ahead in time to fund the $23 million payment due on 30 September 2010, makes it difficult to make a positive finding about Mr Griffiths' knowledge about the possibility of the payment not being made. I am guided by the objective circumstances. Mr Griffiths was a very senior executive within CBA. I think it is most unlikely the first indication he had received of the possibility of the $23 million payment not being made on 30 September 2010 was the parenthetical reference to Mr Galbraith's desire to seek his thoughts 'on an extension of this payment to 31/12/2010' contained in Mr Galbraith's email of 23 September 2010. Any Bankwest executive raising with Mr Griffiths, for the first time, the possibility of Westgem defaulting on the first payment due under the Restated MOFA, would have appreciated the need to provide an explanation of how the situation had arisen and not merely referred to a desire to 'get his thoughts'. I have found it is likely that Mr Saraceni had raised with Mr Galbraith the possibility the $23 million repayment would not be made on 30 September 2010 at a meeting in early September 2010. I think it is likely that Mr Galbraith communicated the possibility the $23 million repayment would not be made on 30 September 2010 to Mr Griffiths about the time the Restated MOFA was executed, and that when the Restated MOFA was executed, Mr Griffiths knew, at least, there was a possibility that the $23 million would not be paid on 30 September 2010 and that on 24 September 2010 Mr Galbraith told him that there was real doubt as to whether the repayment would be made in full.
  6. Mr Griffiths was not cross-examined about whether or not before the Restated MOFA was executed he was aware Westgem would not be able to make the $27 million repayment due on 31 December 2010. There is no basis for finding that he knew Westgem would default in making this repayment.
  7. Mr Griffiths' evidence was that he did not know before the Restated MOFA was executed that Mr Saraceni had reduced his interest in the Vasse Newtown project to 49% and received $7.2 million in consideration.[674] He regarded Mr Saraceni's conduct in failing to disclose the dilution of this interest as deceitful.[675] Mr Griffiths' evidence that he was unaware of the dilution of Mr Saraceni's interest before the Restated MOFA was executed was not challenged to any significant extent in cross-examination and I accept it.[676]

Mr Mahaffy's knowledge of the possibility of the $23 million repayment not being made on 30 September 2010 and the dilution of Mr Saraceni interest in the Vasse Newtown project

  1. Mr Mahaffy's evidence-in-chief about his reaction to Mr Clohessy's email of 9 September 2010 was as follows:[677]
I did not understand this email to be saying that the Sponsors would not be able to make the equity contribution of $23m by 30 September 2010, or the equity contribution of $27m by 31 December 2010, and I continued to assume that these repayments would be made. I understood that Mr Saraceni and Seaport were in serious negotiations with other parties who were interested in purchasing Seaport’s 66.67% interest in Vasse Newtown and that these other interested parties would be possible substitutes for what had previously been proposed as a sale to Perron Group. I did not know that the Saracen Group’s interest in Vasse Newtown had been diluted. I did not know that the Saracen Group had been paid an amount of about $7m upon dilution of its interest and had used those funds for purposes other than making an equity contribution to the Project.

If I had known this before about 22 September 2010, when I signed the Restated Facility, I would have regarded it as a very serious breach of trust on the part of the Sponsors as I had, for approximately six months, and relying on what the Sponsors had told me, understood that any amount raised from the sale of Saraceni’s interest in Vasse Newtown would be used to fund Cost Overruns on the Project. Had I become aware of these matters before about 22 September 2010, I would have concluded that the Sponsors’ willingness or ability to make any equity contribution was at least in doubt.
  1. There was tension between Mr Mahaffy's evidence-in-chief to the effect that after receipt of Mr Clohessy's email he continued to assume that the $23 million repayment would be made by 30 September 2010 and the evidence given by him in cross-examination. The state of Mr Mahaffy's awareness about the prospect of a sale of Mr Saraceni's interest in Vasse Newtown being completed in time to fund the $23 million payment was a major focus of the cross-examination.
  2. Mr Mahaffy accepted that the prospect of a sale of Mr Saraceni's interest in the Vasse Newtown project to someone other than Perron was no better than an 'even chance',[678] and 'no higher than a fifty-fifty probability'.[679] He characterised the assumption that such a sale could be achieved as 'heroic'.[680] In the context of being cross-examined as to when he discussed with Mr Galbraith that the $23 million payment would not be made on 30 September 2010, he said he presumed that the discussion occurred after the Restated MOFA had been executed (rather than when told the Perron transaction was not proceeding) because:[681]
... as I mentioned earlier, hope springs eternal. They had three weeks to go. We weren't clear or didn't feel we were clear that we understood fully the sponsors' financial position. They were telling us they could make the payment. And, in the event, we decided to wait and see whether - - -
  1. At one point Mr Mahaffy said:[682]
So at the time I think we were all hopeful that, however unlikely it may seem now, that a rabbit would be pulled out of the hat and money would be paid.
  1. Immediately after his reference to a rabbit being pulled out of the hat, Mr Mahaffy said that he regretted using that metaphor and that:[683]
My state of mind at the time was there was no better prospect than a fifty-fifty chance that the money would be paid on time.
  1. Mr Mahaffy explained the basis for his assumption that the $23 million would be paid on the due date as follows:[684]
The assumption was based on the representation by the sponsors. The sponsors said they were able to pay it. They continued to make those representations, and I was prepared to see whether or not they would deliver.
  1. Later in his evidence Mr Mahaffy said, in effect, that he knew it was doubtful whether funds would be realised from the sale of Mr Saraceni's interest in Vasse Newtown.[685] Mr Mahaffy said that if he had known that there was no real prospect of the $23 million being paid by 30 September 2010 he still 'would have recommended that the deal proceed'.[686]
  2. In the course of explaining his attitude towards the prospect of the $23 million payment not being made on 30 September 2010, Mr Mahaffy said that BOSI was focussed on the 'overall amount of $50 million' and less concerned about 'payment instalments' as credit approval had been sought on the basis that $50 million would be paid by December.[687] In this respect Mr Mahaffy's evidence was corroborated by the Credit Proposal prepared on 27 July 2010, of which he was the co-author, and the minutes of the relevant credit committee.[688]
  3. In the course of his evidence Mr Mahaffy also agreed that it would not be good and prudent practice for a bank to enter into a contract with a customer if the bank knew the customer was going to default on a payment due in the near future.[689] He said that he would regard such conduct as 'improper' and 'highly irregular'.[690]
  4. A credit point was raised in relation to Mr Mahaffy's evidence. In its written closing submissions Westgem contended that Mr Mahaffy used the 'pulling a rabbit out of a hat' metaphor in 'a moment of spontaneous honesty' and that I should find that his attempts to qualify his evidence were dishonest.
  5. Mr Mahaffy was the subject of a probing cross-examination that took place against a background of some personal difficulty, which made the process of giving evidence particularly taxing.[691] He was a defensive witness - his defensiveness manifested itself in a tendency to give long answers to questions when it was not necessary to do so. As I have highlighted in the preceding paragraphs, there was tension between Mr Mahaffy's evidence-in-chief to the effect that, after being informed that the Perron transaction had fallen through, he 'continued to assume' that the $23 million payment would be made and his evidence in cross‑examination. In the light of this I have approached Mr Mahaffy's evidence cautiously. I do not accept, however, that Mr Mahaffy was dishonest as contended by Westgem. The contention does not pay sufficient regard to the difficult circumstances in which Mr Mahaffy was giving evidence or to the subject matter of his evidence. Mr Mahaffy was giving evidence about his state of mind over a period of about two weeks some eight years earlier (and six years before he made the witness statement in which his evidence‑in‑chief was contained) on an issue that arose in the course of his work as a busy bank executive. The issue involved was, at the time, an uncertain future event - the prospect of Westgem making the $23 million payment - about which his views may have fluctuated in the two week period. Further, in assessing Mr Mahaffy's evidence it is necessary to guard against hindsight bias, what may seem inevitable knowing that the payment was not made, may not have been thought inevitable in the period before the payment fell due. In this respect it must not be forgotten that Mr Saraceni and Mr Pourzand had told the Financiers that they could make the payments and, even though on 9 September 2010 Mr Clohessy had disclosed that the transaction with Perron had fallen through, that disclosure was not accompanied by a request for a postponement of the date for the $23 million payment. To the contrary there was positive pressure from Mr Clohessy to restart the Project even though 'there may be a few boxes left unticked'.[692] Objectively, the pressure from Mr Saraceni and Mr Pourzand to get the Project started again, something which depended on executing the Restated MOFA, provided grounds to believe that the $23 million payment would be made.
  6. I find that after he read Mr Clohessy's email of 9 September 2010 and in the period up to the execution of the Restated MOFA, Mr Mahaffy began to have real doubts as to whether the payment of $23 million would be made on the due date. I find he was prepared to proceed with the Restated MOFA, notwithstanding this doubt, for three reasons. First, even though Mr Mahaffy thought there was real doubt the payment would be made, Mr Saraceni and Mr Pourzand had represented they would make the payment and, second, he knew that BOSI had approved the refinancing provided for in the Restated MOFA on the basis of principal reduction of $50 million by 31 December 2010 rather than by two tranches on 30 September 2010 and 31 December 2010. Third, the Restated MOFA improved the Financiers' security position - a matter addressed in more detail below.
  7. Mr Mahaffy's evidence, that he was unaware at the time the Restated MOFA was executed that Mr Saraceni had diluted his interest in the Vasse Newtown project to 49%, was not challenged in cross‑examination and I accept it.[693]
  8. Mr Mahaffy's evidence was that if he had been told about the dilution of Mr Saraceni's interest before the Restated MOFA had been executed, he would have wanted to think about it but 'on balance' he thought he would have recommended the transaction proceed anyway.[694] I find that had Mr Mahaffy been told about the dilution of Mr Saraceni's interest in the Vasse Newtown project, BOSI would have proceeded with the Restated MOFA.
  9. Mr Mahaffy was not cross-examined about whether, before the Restated MOFA was executed, he was aware that Westgem would not be able to make the $27 million repayment due on 31 December 2010. I am not persuaded that Mr Mahaffy, and through him BOSI, knew before the Restated MOFA was executed, that Westgem would not make the $27 million repayment due on 30 December 2010.

The increase in the value of securities provided to the Financiers

  1. The Financiers' willingness to advance Westgem the funds it required to complete the Project was dependent on the provision of additional first and second mortgage securities. As referred to earlier in this section of the reasons, 'the net equity value' of the additional securities required by the Financiers, and provided pursuant to the terms of the Restated MOFA was $72.1 million.
  2. To recap, prior to entry into the Restated MOFA the Financiers had the benefit of personal guarantees from each of Mr Saraceni and Mr Pourzand for up to $20 million, together with unlimited guarantees from them in relation to Cost Overruns and the benefit of securities granted pursuant to the 18 November Letter Agreement, which secured the balance of the second Cost Overrun ($17 million less the $7 million paid). Looked at from the Financiers' perspective, however, as Mr Nathan had emphasised in rather dramatic terms in his email to Mr Nagle of 5 May 2010, Mr Saraceni and Mr Pourzand 'could just throw the "Raine Square" keys to the financiers along with a $50m cheque and, subject to a few minor adjustments, in effect walk away'.[695] The additional security improved the Financiers' security position.
  3. Mr Griffiths and Mr Mahaffy were cross-examined about the benefit the additional securities conferred on the Financiers. Mr Griffiths accepted the proposition that getting the additional security was a terrific deal for the Financiers.[696] Mr Mahaffy said the banks were interested in obtaining the additional security irrespective of whether the $23 million was paid on 30 September 2010.[697] I have already recorded my finding that the provision of additional securities was one reason why Mr Mahaffy on behalf of BOSI was prepared to allow the Restated MOFA to be concluded even though there was real doubt about $23 million repayment being made on 30 September 2010. I make a similar finding in respect of Bankwest: that is, I find that the provision of additional security was one of the reasons Bankwest was prepared to allow the Restated MOFA to be concluded even though there was real doubt about the $23 million repayment being made on 30 September 2010.

Westgem seeks a deferral of $23 million payment

  1. On 29 September 2010 Mr Clohessy sent an email to Mr Galbraith in which he referred to 'our recent meeting' and attached 'an update on issues discussed' in the form of a memorandum in which he stated:[698]
Don as per your request please find below an update on the items discussed.
  • The proposed sale of Seaport’s interest in Vasse to the Perron Group is not proceeding. Notwithstanding that price was not an issue the Perron Group and the Vasse Newtown syndicate could not agree on joint venture terms going forward.
  • The failure of the above sale to take place would have placed stress on the Saracen cash flow however the Vasse Newtown syndicate has agreed to provide additional loan funds to Seaport and increased its profit share. Seaport’s reduced profit share is still sufficient to produce the required equity injection on sale. In the interim Seaport’s interest continues to be marketed for sale and there are a number of interested parties.
...
  • Part of the proposed $23 million equity injection ($6 milliion) [sic] was originally contributed by Hossean however he had personal requirements for the funds to maintain his own commitments and Luke had agreed to fund this from the Vasse sale proceeds.
  • Given the sale not proceeding we would request an extension of the date for equity injection be extended until the 31st of December 2010.
  1. Also on 29 September 2010, Westgem provided Mr Galbraith with an updated Saracen Group Cash Flow Forecast.[699] The notes to that document recorded an agreement had been concluded in August for VNPL to loan a further $7.2 million and increase their share of profit to 51% of the Vasse Newtown project.[700] The Cash Flow Forecast recorded the Projected Income for 'Vasse 2 Distribution' for September 2010 was $6.4 million and for October 2010 was $836,591.[701]
  2. In response to Mr Clohessy's memorandum of 29 September 2010 Mr Galbraith requested details of the loan agreements between Mr Saraceni's entities and VNPL. Mr Clohessy responded:[702]
Don hi, we have just varied the existing agreement with the effect that Seaport has reduced its profit share from 66.6% to 49% and Vasse Newtown from 33.35 to 51%. Seaport recieved [sic] additional funds of circa $7.2m to continue to funds its normal business operations including Raine Square. Luke's remaining interest is still of sufficient value to meet his commitment to the proposed principal reduction. Hopefully whilst he continues to sell we can now gain approval for funding of Vasse to move forward, if necessary Vasse Newtwon [sic] will go on to the title for its share if this helps either the sales process or funding to occur.
  1. Mr Galbraith responded:
Mark and Luke.

Appreciate if you can arrange for copies of the agreements to be provided to the lenders.

Whilst this transaction may have been completed prior to financial close; I believe that it should have been disclosed to the lenders.

Going forward, and subject to review of the JV documents requested; it is appropriate that an undertaking be provided by Seaport not to further vary the JV and loan agreements without the lenders prior written consent such consent not to be un-reasonably with-held.

Lets discuss on Monday.
  1. I infer from Mr Galbraith's email to Mr Saraceni and Mr Clohessy that neither he nor anyone at Bankwest was aware of the dilution of Mr Saraceni's interest in the Vasse Newtown project until he read the notes to the Saracen Group cashflow forecast provided to him on 29 September 2010. I am fortified in drawing this inference that at no stage did Mr Clohessy refer to his email to Mr Galbraith of 9 September 2010 or contend it was apparent from his email that Mr Saraceni had diluted his interest in the Vasse Newtown project.
  2. In an email sent on 4 October 2010 by Mr Nathan to Mr Galbraith, Mr Nathan stated:[703]
Have spoken to Mark Clohessy re the Vasse documents wherein he has indicated that the delay in sending them to us has been his computer document storage which is still not up and running. I have expressed the urgency and he is going to see if he can get the documents from another source. I also raised the banks concern that the cas[h] was provided to Sarecen as opposed to the financiers to which he responded that a major concern of the Vasse Newton JV partners is that Luke's business activities run out of working capital and that they would not have agreed to provide funds just to pay the financiers.

I also raised the concern that the equity now up for sale is not the controlling interest and as such may not be as marketable. Mark Clohessy responded that they would still facilitate the sale of a controlling interest if that is what it took to get the sale away.

I have also indicated that given the banks concerns any agreement to now roll the September and December amortisation payments into one would require an undertaking from Luke Saraceni as the sole director of Seaport not to borrow any further funds against the remaining equity in the Vasse project. Mark Clohessy didn't see that as a problem.

Don we will continue to proceed with the Westgem paper based upon the above but will not finalise until we have received the documents.
  1. On 4 October 2010 Mr Dower of Saracen sent an email to Mr Galbraith attaching a copy of the agreement of 27 August 2010 between VNPL and Mr Saraceni's entities.[704] Later on 4 October 2010 Mr Clohessy sent a detailed explanation of the context behind the execution of the Variation Agreement.[705] Among other matters Mr Clohessy stated:
I will leave Luke to speak for himself in relation to his motivations and thought process however I have no doubt from our discussions his motivation was to seek both liquidity and meet his commitments to the lenders. I have also made it consistently clear on every occasion that my actions in relation to Vasse would always be determined first and foremost by what was in the best interest of VN investors. VN would not have advanced funds to Seaport knowing they would be used first as a source of equity to Raine Square if Seaport/Saracen were not able to carry on business. I do understand however that the lenders may consider that equity has leaked from the Security pool even though it did so prior to financial closure, but I would request you consider two factors. First, Saracen having insufficient funds to meet normal business commitments has significant and obvious implications for all concerned and second VN would not have made funds available as an equity injection to Raine Square without resolving the first issue.

Financiers agree to deferral of $23 million payment

  1. On 8 October 2010 Bankwest approved deferral of the payment of the $23 million to 31 December 2010.
  2. On 13 October 2010 Bankwest, as Facility Agent, sent a letter to Westgem informing it the failure to pay the $23 million on 30 September 2010 was a default under the terms of the Restated MOFA but the Financiers would waive the default if certain conditions were met. Those condition were that Westgem paid $50 million by 31 December 2010, paid a default fee of $230,000 and that the 'Transaction Parties' (Westgem, Mr Saraceni and the other guarantors and Seaport) gave undertakings to the effect that if VNPL increased its profit share in the Vasse Newtown project, the consideration would be applied in reduction of the debt due under the Restated MOFA, Mr Saraceni's interest in the Vasse Newtown project would not be diluted any further without the Financiers' consent, any funds realised from the sale of Mr Saraceni's interest in Vasse Newtown would be applied in reduction of the debt and Mr Saraceni would continue to actively market the interest.[706] On 15 October 2010 Westgem and the guarantors agreed to the terms set out in the 13 October 2010 letter and the 13 October Letter Agreement was made.

Westgem defaults on $50 million payment due on 31 December 2010

  1. Mr Saraceni did not sell his remaining interest in the Vasse Newtown project before 31 December 2010 and no payment in respect of the $50 million due on 31 December 2010 was made.
Westgem's pleading regarding the Financiers' knowledge
  1. Westgem pleaded that when the Restated MOFA was executed the Financiers were aware of the following:[707]

(a) Their cost of funds had reduced since entry into the MOFA.

(b) Westgem and the guarantors under the Restated MOFA would not be able to make:

(i) the payment of $23 million by 30 September 2010;

(ii) the payment of $27 million by 31 December 2010 without the guarantors selling real property and that completion of such sales before that date was unlikely.

(c) Westgem would default in its payment obligations under the Restated MOFA.

(d) As a consequence of (b) and (c) the Finance Parties would most likely appoint receivers and managers who would complete the construction of the 'Complex'.

  1. Westgem did not adduce any evidence in support of the allegation that the Financiers' cost of funds had reduced since entry into the MOFA.
Consideration

Applicable principles - unconscionable conduct

  1. Earlier in this judgment I have set out the statutory provisions relied on by Westgem for its unconscionable conduct claim and the principles that guide the application of those provisions.[708] They were not controversial.

Asset lending comparison

  1. It is convenient to deal first with the comparison drawn in Westgem's closing submissions between the refinancing constituted by the Restated MOFA and asset lending. In Serventy v Commonwealth Bank of Australia [No 2][709] the Court of Appeal observed that lending without regard to the borrower's ability to service the loan and solely on the basis of the available security - 'pure asset-lending' - may or may not amount to unconscionable conduct - whether it does depends on all the circumstances. In Permanent Mortgages Pty Ltd v Vandenbergh,[710] Murphy JA made observations to the same effect and cautioned against the application of 'formulaic expressions such as asset-lending' and said:[711]
The benefits of entrepreneurial activity and the recognition of an individual's personal and commercial autonomy are important factors to take into account in any consideration of what may, on the face of things, appear to be imprudent or reckless borrowing. Even where, prima facie, there is pure asset lending, the totality of all the circumstances must be examined in assessing the alleged unconscionability of the loan transaction.
  1. In Provident Capital Ltd v Papa,[712] McFarlan JA, with whom Allsop P and Sackville AJA relevantly agreed, undertook a comprehensive review of the authorities in New South Wales concerning asset lending. McFarlan JA observed in relation to whether asset lending made a transaction 'unjust' for the purposes of the Contracts Review Act 1980 (NSW) that:
[I]t can be relevant in the determination of whether a contract is unjust, and whether relief should be granted against a financier, under the Contracts Review Act that the financier has shown no interest in the borrower's ability to service the loan. However the significance of that fact must be assessed in the context of all the circumstances surrounding the loan. In my opinion, of particular significance will be the financier's knowledge of the borrower's circumstances, the purpose of the loan and whether the borrower has obtained independent legal advice. Public interest does not necessarily require so-called asset lending to be proscribed, or even deterred. It may advance the interests of the parties to many transactions, and facilitate commerce generally, for financiers to be able to lend on a 'low doc' basis without requiring the expenditure of time and effort in ascertaining and verifying the ability of borrowers to service loans. In any event, that exercise will often be difficult. For example if Provident had sought to undertake it in the present case, it would have had to make a difficult business judgment about the viability and prospects of the gymnasium business, a topic about which even well-informed minds could undoubtedly have differed. Financiers should not be required to make such assessments if they do not wish to do so. If, instead, a financier is satisfied that a borrower is able to make the decision for him or herself or has received appropriate advice, the public interest reflected in the Contracts Review Act will ordinarily have been satisfied.
  1. The comparison Westgem seeks to draw between asset lending of the kind that has attracted condemnation in the authorities (generally lending secured against homes to unsophisticated consumers who cannot afford the repayments) and a development finance facility is weak and does not advance Westgem's case. The Restated MOFA was a complex agreement negotiated at arms-length by well-resourced commercial parties. As with the MOFA, the term of the facility provided by the Restated MOFA was limited to the time it was estimated it would take to complete the Project. Unlike the MOFA there was an obligation imposed on Westgem to repay $83.1 million of the further $132.6 million advanced under the Restated MOFA by repayments during the term of the facility with the balance being repaid on completion of the Project, either by a refinancing or by a combination of a sale of a partial interest in Raine Square and a refinancing. Westgem represented that it would be able to make the repayments. And, as I explain below, on the facts as I have found them, Westgem had a sufficient level of confidence that it would be able to fulfil its obligations under the Restated MOFA, or to refinance the Project, to justify the risk of entering into it.

The relevant circumstances

  1. As noted earlier, one of the cornerstones of Westgem's unconscionable conduct claim was the contention the events upon which the 5 March 2010 default notice was based did not involve any breach of the MOFA on its part. As I have found the first and second Cost Overruns involved breaches of the MOFA by Westgem I do not accept this contention.
  2. I turn now to the other cornerstone of Westgem's case ‑ its contention that the Financiers knew Westgem would not be able to make the repayments due under the Restated MOFA and would default on its obligations.
  3. The significance to be attached to the Financiers' knowledge that there was real doubt whether the $23 million repayment would be made on 30 September 2010 cannot be examined in isolation. It must be considered in the context of Mr Saraceni's and Mr Pourzand's conduct, their desire to enter into the Restated MOFA and their states of mind concerning the prospect of the $23 million payment being made.
  4. Mr Saraceni and Mr Clohessy appear to have been the only people in a position to make an accurate assessment of Westgem's ability to make the $23 million payment. They were reluctant to disclose what they knew. In his email to Mr Pourzand on 31 August 2010 Mr Saraceni did not tell Mr Pourzand the $23 million payment would not be made or would not be made unless he (Mr Saraceni) could dispose of his interest in the Vasse Newtown Project. In Mr Clohessy's email to Mr Pourzand of 12 September 2010 he did not tell Mr Pourzand that the payment would not be made. Rather he gave Mr Pourzand his opinion about the action the Financiers might take 'if the principle [sic] reduction isn't made on Sept 30th' (my emphasis) and said, 'Clearly it would be better not to test them and make the reduction if possible. Alternatively we need to have an alternative takeout scenario like the one Luke is working on with Goldman Sachs'. I think it unlikely that Mr Pourzand knew that the $23 million would definitely not be paid. In his email to Mr Clohessy of 16 September 2010 he made it clear he was aware of a risk the payment might not be made but not that he understood that it would not be made, but he was concerned that 'lukes wiggling wouldn't work this time'.
  5. I infer Mr Saraceni and Mr Clohessy knew by about the beginning of September 2010 that Westgem would not be able to make the $23 million repayment on 30 September 2010. I infer they considered it was in Westgem's interests not to disclose this, and not to disclose that Mr Saraceni had reduced his interest in Vasse Newtown, until after the Restated MOFA had been executed. I draw these inferences from the events which unfolded between the execution of the Variation Agreement and the execution of the Restated MOFA as I have found them to be. I infer the reason why Mr Saraceni and Mr Clohessy did not disclose these matters was because they understood that disclosure would be likely to cause further delay and it was in Westgem's interests to have the contract with Probuild signed and the Project started before raising, what they appreciated would be viewed as by the Financiers, further complications.
  6. Mr Saraceni was an experienced and successful property developer. It is unlikely he would have made the decision to enter the Restated MOFA and cause additional security to be provided if he did not have a significant level of confidence that by so doing he and Mr Pourzand would be able to complete the Project and, in due course, realise their equity in it. I find it likely Mr Saraceni was confident that if construction began again, and if he and Mr Pourzand retained control, he would be able to negotiate a transaction with a third party (Goldman Sachs or one of the other third parties who had expressed interest in acquiring an interest in the Project) which would enable Westgem to fulfil its obligations under the Restated MOFA or enable the Project to be refinanced. I infer it was the prospect of a transaction with a third party that gave Mr Saraceni the confidence to execute the Restated MOFA. In drawing this inference I rely in part on the evidence of discussions with third parties about equity participation in, and refinancing of, the Project, and in part on the rejection by Mr Saraceni of the offer by the Perron Group to acquire either his interest in, or the entirety of, the Vasse Newtown project, a matter to which I will refer again below. This is not to say the possibility of achieving the sale of assets did not also play a role in Mr Saraceni's decision-making but the dominant factor was the prospect of entering a transaction with a third party.
  7. Following Salta's termination of the Salta Building Contract there is no doubt the situation in which Mr Saraceni and Mr Pourzand found themselves put them under considerable commercial pressure. As I have observed several times not only were Mr Saraceni and Mr Pourzand wealthy, experienced and sophisticated property developers, they also had the benefit of Mr Clohessy's advice, assistance and advocacy as well as the assistance of lawyers and accountants. There was no imbalance between Mr Saraceni and Mr Pourzand and the Financiers in terms of experience, commercial sophistication and access to professional advice and assistance.
  8. Further, there is no evidence that in the course of the negotiations leading to the Restated MOFA the Financiers acted dishonestly or used illegitimate tactics. As I explain below in the course of addressing the Financiers' 'Vasse Newtown' counterclaim, it was Mr Saraceni who engaged in misleading conduct in order to get the Restated MOFA concluded.
  9. Mr Saraceni and Mr Pourzand sought the refinancing the subject of the Restated MOFA, and sought to persuade the Financiers that it was in their (the Financiers) interests to provide a further $132.6 million rather than act on the default notice of 5 March 2010. Mr Saraceni and Mr Pourzand had represented that they could make the repayments due on 30 September and 31 December 2010 out of asset sales. And, on the facts as I have found them, Mr Saraceni could have realised sufficient funds to cover the $23 million payment and $10 million of the $27 million due on 31 December 2010 by selling his entire interest in the Vasse Newtown project to the Perron Group but chose not to do so.
  10. Further, the representations as to Westgem's ability to meet its obligations under the MOFA were reinforced by the possibility of 'take out solutions' raised by Mr Saraceni and Mr Clohessy. As Mr Clohessy said in his email to Mr Galbraith of 9 September 2010:
Over recent months Luke's office has been negotiating with a number of international Banks and Institutions to take an equity or mezzanine position in Raine Square and in coming weeks we hope to have meaningful discussions with the current lenders to present end take out solutions.
  1. Separately Mr Saraceni had raised with the Financiers the prospect of Goldman Sachs' involvement in the Project.
  2. I do not accept the proposition that, because the Financiers gained additional security with an estimated net value of $72 million, they did not assume any additional risk by entering into the Restated MOFA. First, it must be remembered that the Financiers agreed to advance a further $132.6 million to a borrower, which had defaulted, to enable a commercial development, which had stalled, to proceed. Further, the Financiers had extended the term of the facility. Second, the proposition that the Financiers assumed no additional risk rests on two doubtful assumptions. First, it is doubtful, from a financier's perspective, that the commercial benefits ultimately derived from enforcing securities obtained from a debtor which defaults are the same, or of the same value to a financier's business as the commercial benefits obtained from a debtor which fulfils its contractual obligations. Further, the 'no-additional risk' proposition assumes the estimated net value of the security was a reliable estimate and was not at risk of being adversely affected by unexpected difficulties in realising the securities or by a fall in the market for the security.
  3. As recounted in setting out the facts, when asked by Westgem to do so, the Financiers agreed to defer the $23 million payment to 31 December 2010. Subject to the satisfaction of various conditions, they waived the default constituted by the failure to make the payment on 30 September 2010. The willingness to waive the default supports the conclusion that when the Financiers entered into the Restated MOFA they intended to provide Westgem with a real opportunity to complete the Project rather than using the Restated MOFA as a device to obtain additional security to be enforced at the first available opportunity.
  4. The Restated MOFA was a transaction Mr Saraceni and Mr Pourzand wanted to conclude as a step towards resolving the difficult commercial position in which they found themselves ‑ a position for which the Financiers' were not responsible. Entering the Restated MOFA put a large proportion of Mr Saraceni's and Mr Pourzand's assets at risk and the risk materialised. The statutory prohibition against unconscionable conduct is not, without more, intended to protect entrepreneurs from the adverse consequences flowing from risks voluntarily undertaken and upon which commerce so often depends. Assessed in the circumstances I have outlined in the preceding paragraphs, the Financiers' knowledge that there was real doubt whether the $23 million payment would be made on 30 September 2010 and the improvement in the Financiers' security position achieved by entry into the Restated MOFA are not sufficient to constitute unconscionable conduct on the Financiers' part. Westgem's unconscionable conduct claim fails. Had I concluded that the Code Conduct Term, the Event of Default term and the reasonable grounds term were terms incorporated in the MOFA I would have found that the claims based on the alleged breaches of those terms failed for substantially the same reasons.
PART 5 - Vasse Newtown counterclaim Overview
  1. The factual matrix in which the Vasse Newtown counterclaim arose is constituted by the factual findings set out in Pt 4 dealing with the MOFA redocumentation claims.
  2. The elements of the Vasse Newtown counterclaim may be summarised as follows:

(a) The Financiers alleged Westgem, Mr Saraceni and Seaport made representations that:[713]

(i) the repayments scheduled to be made under the Restated MOFA on 30 September and 31 December 2010 would be funded by the sale of all or part of Mr Saraceni's interest in Vasse Newtown project; and

(ii) Mr Saraceni held a 66.67% interest in the Vasse Newtown project.

(b) The Financiers assumed the truth of the representations and entered the Restated MOFA on that basis.[714]

(c) The representations were misleading because the sale to the Perron Group had fallen through and, in its place, Mr Saraceni had entered into the Variation Agreement which reduced his interest in the Vasse Newtown project to a minority 49% interest, thus funds, capable of application towards the discharge of Westgem's repayments due on 30 September and 31 December 2010, would not be available from the sale of Mr Saraceni's interest in Vasse Newtown project. The Financiers contend that Westgem, Mr Saraceni and Seaport were under a positive obligation to disclose these matters to the Financiers.[715]

(d) The Financiers allege that the impugned conduct constituted contraventions of the statutory prohibitions against misleading or deceptive conduct[716] (under s 12DA of the ASIC or s 10 of the FTA) and contraventions of the representation and warranties contained in the Restated MOFA and the Seaport Share Mortgage.[717]

(e) The Financiers allege that as a result of the contraventions they suffered loss and damage because had they known the true position they would not have provided the additional funding under the Restated MOFA, or provided the additional funding in the manner in which they did or entered into the Restated MOFA on its agreed terms or at all,[718] and further they were denied opportunities to improve their position.[719] In their closing written submissions the opportunities denied to the Financiers were described as follows: first, 'the opportunity to consider their options', which included the option of amending the Restated MOFA (for example to provide for payment of $50 million on 31 December 2010); second, the opportunity of demanding the money realised by Mr Saraceni from the sale of part of his interest in the Vasse Newtown project be directed to Restated MOFA repayment; and, third, the opportunity of preventing the sale on the grounds that a minority interest of 49.67% was harder to sell than a 66.67% interest.[720]

  1. The defence to the counterclaim rested primarily on the following four contentions:[721]

(a) The Financiers were told that Westgem would be unable to make the $23 million repayment on 30 September 2010 because the sale to the Perron Group had fallen through.

(b) There was no relevant obligation to disclose that Mr Saraceni had reduced his interest in the Vasse Newtown Project and, after the interest had been reduced to 49%, there was no representation Mr Saraceni held an interest of 66.67%.

(c) The reduction of Mr Saraceni's interest in Vasse Newtown was not material because his remaining interest was more than sufficient to make the $17 million contribution to the $23 million repayment.

(d) There was no evidence the alleged contraventions caused the Financiers any loss. In October 2010 the Financiers knew the $23 million payment had not been made and knew that Mr Saraceni's interest in the Vasse Newtown project had been reduced to 49% yet they re-affirmed the Restated MOFA and continued to provide the additional funding under the Restated MOFA.

  1. As I explain below I have found that Mr Saraceni, and through him Westgem and Seaport, engaged in misleading conduct in breach of the statutory prohibitions and in breach of the Restated MOFA warranties and the Seaport Share Mortgage but that the Financiers have not established the loss claimed by them.
Applicable legal principles
  1. Earlier in this judgment I have referred to the principles applicable to determining whether conduct is misleading or deceptive in contravention of the statutory prohibitions. Those are the principles I have applied. It is unnecessary to repeat them.
Consideration
  1. The Financiers' claim involves an assessment of what was and was not disclosed by Mr Saraceni and Mr Clohessy in respect of the sale of Mr Saraceni's interest in the Vasse Newtown project.

The representation about the availability of funds

  1. The factual findings (made in the context of the MOFA redocumentation claims) to the effect that before entering the Restated MOFA both BOSI and Bankwest knew that there was real doubt about whether the $23 million repayment would be made on 30 September 2010 undermine the Financiers' reliance on the representation that funds would be available from the sale of Mr Saraceni's interest in the Vasse Newtown project. On 9 September 2010 Mr Clohessy disclosed the sale to the Perron Group had fallen through. It was that sale which had been the focus of the discussion and communications between the Financiers and Mr Saraceni and Mr Clohessy since 20 July 2010 and it was that sale the Financiers understood would generate the funds required to make the $23 million repayment. Once told that it had fallen through, the Financiers knew there was real doubt that the $23 million repayment would be made on 30 September 2010. I find the Financiers did not enter the Restated MOFA on the assumption that funds capable of being applied towards the payment of the $23 million repayment due on 30 September 2010 would be available from the sale of Mr Saraceni's interest in the Vasse Newtown project.

The representation about the extent of Mr Saraceni's interest in Vasse Newtown project

  1. Westgem's refinancing proposals placed repeated emphasis on the extent of Mr Saraceni's interest in the Vasse Newtown project ‑ 66.67% and its value ‑ $40 million according to the April 2010 valuation and $33 million on the basis of the price offered by the Perron Group.
  2. This emphasis reflected the importance attached to this asset both as security and, more importantly, as an asset capable on sale of funding the repayments of principal due under the proposed Restated MOFA. The importance of the asset was an objective circumstance which gave rise to a reasonable expectation the Financiers would be informed of a reduction in Mr Saraceni's interest from 66.67% to 49%.
  3. I do not accept the contention, advanced in defence of this aspect of the claim, that a reduction from a majority interest of 66.67% to a minority interest of 49% would not have been considered material by the Financiers. The proposition underlying this contention is that the value of a 49% interest is directly proportionate to the value of a 66.67% interest but, as Mr Nathan pointed out in his email of 4 October 2010, a minority interest is not as marketable as a controlling interest and its value is ordinarily not proportionate to the value of the entire asset.
  4. The emails sent on 31 August 2010 by Mr Saraceni and Mr Clohessy in response to Mr Galbraith's inquiry about Seaport's indebtedness to VNPL and the status of the negotiations with the Perron Group were misleading. The statement in Mr Saraceni's email that 'The Perron Group negotiations are continuing ...' was incorrect. Plainly, negotiations for the sale of Mr Saraceni's 66.67% interest could not continue as Mr Saraceni had reduced his interest to 49%.
  5. The statement in Mr Clohessy's email of 31 August 2010 that, 'The Vasse Newtown facility is limited to 33.33%' was also incorrect. VNPL's facility was not limited to 33.33%, it was 51%.
  6. The statements made by Mr Saraceni and Mr Clohessy in their emails impliedly represented that Mr Saraceni's interest in the Vasse Newtown project was 66.67%. That neither Mr Saraceni nor Mr Clohessy disclosed Mr Saraceni had reduced his interest (the true position as they knew it to be) when there was a reasonable expectation that this would be disclosed also makes their conduct misleading.
  7. In his email to Mr Galbraith and others of 9 September 2010, Mr Clohessy disclosed the sale to the Perron Group had fallen through and that Mr Saraceni had reached an agreement with VNPL. For ease of reference I set out below the opening paragraph of that email in which Mr Clohessy said:[722]
Seaport had reached an in principal [sic] agreement with Perron with respect to the sale of its 66.66% interest which would have resulted in net proceeds of 33m however Vasse Newtown and Perron were unable to reach agreement on the new JV terms. The failure of this sale to go forward has placed The Saracen Group under cash flow pressures and it therefore reached agreement with Vasse Newtown to extend its loan facility and profit share. Seaport's remaining interest in the project remains for sale and is still sufficient to meet the requirements of Westgem for principle [sic] reductions under the MOFA. Both Seaport and Vasse Newtown are exploring all possibilities of sale of Seaports interest and still have a number of interested parties with whom serious negotiations are being discussed. In addition Vasse Newtown are looking at taking some or all of Seaport’s remaining equity.
  1. In their submissions the Financiers described this email as 'deliberately elliptical'.[723] This was an apt description. The email omitted the critical information about the extent of the reduction and the realisation of funds, matters to which, I infer, Mr Clohessy and Mr Saraceni must have known the Financiers would attach importance. The elliptical nature of Mr Clohessy's 9 September email is to be contrasted with Mr Clohessy's email to Mr Galbraith of 29 September 2010 in which he described what had occurred in clear terms in two sentences, he said:
Don hi, we have just varied the existing agreement with the effect that Seaport has reduced its profit share from 66.6% to 49% and Vasse Newtown from 33.35 to 51%. Seaport recieved [sic] additional funds of circa $7.2m to continue to funds its normal business operations including Raine Square. Luke's remaining interest is still of sufficient value to meet his commitment to the proposed principal reduction.
  1. Mr Clohessy's failure to disclose that the agreement (the Variation Agreement) to which he referred in his email of 9 September 2010 resulted in a reduction in Mr Saraceni's interest in Vasse Newtown from 66.67% to 49%, when there was a reasonable expectation that this would be disclosed, was misleading. Mr Clohessy had provided a draft of the 9 September 2010 email to Mr Saraceni for his comment before sending it. He sent it on behalf of Mr Saraceni.
  2. I infer that Mr Saraceni and Mr Clohessy misled the Financiers about the true position in relation to the proposed Perron transaction and the dilution of Mr Saraceni's interest in the Vasse Newtown project because they were concerned that if the Financiers knew what had occurred they would either not enter the Restated MOFA or there would be further delay before it was executed.
  3. As recorded earlier I accept Mr Mahaffy's evidence to the effect that before the Restated MOFA was executed he did not know that Mr Saraceni's interest in the Vasse Newtown project had been diluted. I have also found that none of Mr Griffiths, Mr Galbraith, Mr Nagle nor Mr Nathan understood Mr Saraceni's interest had been diluted. I find that the Financiers entered the Restated MOFA on the assumption that Mr Saraceni still owned a 66.67% interest in the Vasse Newtown project. In this respect they were misled.

Breaches of Restated MOFA warranties and Seaport Share Mortgage warranties

  1. I find the misleading conduct constituted breaches of the Restated MOFA warranties and the Seaport Share Mortgage warranties.

Loss not established

  1. In misleading or deceptive conduct cases the causation issue may be expressed in terms of whether the impugned conduct was a cause, in the sense that it materially contributed to, the loss claimed. It is sufficient that the conduct was a cause, it need not be the sole cause.[724]
  2. I am satisfied that the implied representation that Mr Saraceni's interest in the Vasse Newtown project was 66.67% was a cause of Financiers' entering into the Restated MOFA. I am so satisfied because of the importance that had been attached by both sides in the negotiations leading up to the Restated MOFA to Mr Saraceni's interest in the Vasse Newtown project being an asset that was to be realised to generate funds to make the repayments of principal required by the Restated MOFA.
  3. The Financiers claim that they suffered loss and damage because had they known the true position they would have acted differently, that is, not provided the additional funding on the terms which they did or not entered into the Restated MOFA on its agreed terms at all and would have taken the opportunity to improve their position. It was for the Financiers to adduce the evidence required to prove these losses, that is, to establish that they would have acted in the manner they alleged.[725]
  4. The fact that after they had learned that Mr Saraceni had reduced his interest in the Vasse Newtown project, the Financiers continued to provide funding, essentially under the terms of the Restated MOFA,[726] when they were provided with the opportunity not to do so by Westgem's failure to make the $23 million repayment on 30 September 2010 is, of itself, convincing evidence the claimed loss was not, in fact, suffered.
  5. My acceptance of Mr Mahaffy's evidence about what his attitude would have been, had he been told about the dilution of Mr Saraceni's interest in the Vasse Newton project before entering the Restated MOFA, and my finding based on that evidence, that BOSI would have proceeded to enter the Restated MOFA reinforces the conclusion that had the true position been disclosed BOSI would have not acted differently.
  6. Further, there was no evidence to suggest that Bankwest would have taken an approach that differed from that described by Mr Mahaffy and, I infer from the fact when Bankwest did know the true position it decided to continue to advance funds under the Restated MOFA, that had it known the true position prior to execution of the Restated MOFA it would still have proceeded to enter into it.
  7. In reaching these conclusions I take into account the evidence given by Mr Mahaffy to the effect he regarded Mr Saraceni's failure to disclose the dilution of his interest in Vasse Newtown before the Restated MOFA was executed, as a breach of trust and the evidence of Mr Griffiths that he regarded Mr Saraceni's conduct as deceitful. That the Financiers continued to advance funds under the Restated MOFA, however, even though they regarded Mr Saraceni's conduct so seriously, reinforces the inference that they would have entered the Restated MOFA if the dilution had been disclosed to them in advance.
  8. I am not satisfied that the Financiers suffered loss of the nature alleged by them.
PART 6 - Rectification of the MOFA Share Mortgage
  1. As recounted earlier in this judgment, Mr Saraceni and Mr Pourzand gave a share mortgage over the shares in Westgem as security for the facilities under the MOFA. The share mortgage contained an unlimited obligation to pay the whole of the Secured Money as defined in the MOFA whereas it had been agreed that the amount to be secured by the mortgage was limited to $20 million together with other specified unliquidated amounts. Mr Saraceni and Mr Pourzand claimed that the share mortgage should be rectified.[727] In their defence filed on 2 October 2017 the Financiers accepted that the share mortgage should not be enforced otherwise than on the basis that the amount secured is limited to $20 million and the other specified unliquidated amounts and argue that there is no utility in making an order of rectification. In a practical sense, given there is no dispute about the operation of the share mortgage, the only aspect of the dispute left to resolve concerns the costs of the rectification claim up to 2 October 2017. I will hear the parties in relation to this costs dispute following the delivery of judgment.
Application of MOFA Default Rate
  1. Westgem pleaded that on the proper construction of the MOFA the Financiers were not permitted to apply the MOFA Default Rate (a rate of interest higher than the rate at which interest otherwise accrued under the MOFA) to the whole of the secured money unless the Financiers had served a notice declaring all of the money actually or contingently owing under the MOFA immediately due and payable (an acceleration notice).[728] The Financiers contested this construction. It is unnecessary to refer to the detail of the submissions made on this issue as in Westgem's written closing submissions it conceded that the Financiers' construction was to be preferred. Westgem's concession was rightly made.
  2. There is an issue as to whether the MOFA provisions entitling the Financiers to apply the default rate of interest constituted a penalty but it has been agreed that this issue be considered as part of the quantum hearing.
PART 7 - Financiers' counterclaims for monies due under the MOFA, the Restated MOFA and the securities
  1. In summary the Financiers claim:

(a) outstanding amounts advanced pursuant to the facility made available under the MOFA and the Restated MOFA;

(b) interest, including interest charged at the Default Rate; and

(c) outstanding fees, costs and expenses.

The amount claimed is net of the amount recovered from the sale of the Raine Square development and the enforcement of various securities. The quantum is to be determined at the quantum hearing.

  1. The pleading required to articulate the Financiers' claims was extensive but the issues were limited in nature and extent and, in light of the findings already made, can be dealt with quite shortly.
  2. The first issue is whether there were events of default during the period 25 September 2009 to 6 September 2010 which entitled the financiers to charge interest at the Default Rate. Westgem's failure to pay the second Cost Overrun constituted an Event of Default under the MOFA. Further, the notice of default served on 5 March 2010 specified a number of Events of Default including the Salta Termination. On the basis of the Events of Default constituted by failure to pay the second Cost Overrun and I am satisfied that the Financiers were entitled to apply the Default Rate from 25 September 2009 to 6 September 2010 and, independently of the second Cost Overrun default, I am satisfied that the Salta Termination was an Event of Default which entitled the Financiers to apply the Default Rate from 5 March 2010.
  3. The second issue relates to the basis upon which the Financiers claim the repayment of the money advanced by them. The Financiers advance their claims on a number of alternative bases: on the basis of the Restated MOFA but if the Restated MOFA is set aside, on the basis that the terms of the MOFA continued to apply to financial accommodation provided by the Financiers and, as a final alternative, on the basis of the application of restitutionary principles. As I have not upheld the MOFA redocumentation claims and not set aside the Restated MOFA, the terms of the Restated MOFA govern the Financiers' claims for repayment. Had I set aside the Restated MOFA then, in my view, the terms of the MOFA would have applied to the further finance provided by the Financiers -Westgem accepted that this would have been so.[729]
  4. The third issue, or set of issues, concern the Security Trustee's claims against the guarantors and security providers. With the exception of two issues, namely, the capacity in which the Second Additional Securities were provided by the Second Additional Securities providers and whether the liability of the Second Additional Securities providers was unlimited or limited to the amounts the subject of guarantees provided, it was common ground that outcome of the Security Trustee's claims would be determined by the success or failure of Westgem's primary claims in these proceedings. As Westgem's claims have failed, other than in respect of the capacity and quantum issues to which I have referred, the guarantors and security providers have no defence to the claims brought by the Security Trustee and it is entitled to the relief sought by it.
PART 8 - Liquidator's voidable transactions claims Overview
  1. The liquidator seeks orders under s 588FF of the Corporations Act setting aside various transactions as voidable transactions under s 588FE of the Corporations Act. The transactions, and the basis upon which they are impugned, are as follows:

(a) the AFL Supplementary Agreement - insolvent transaction and uncommercial transaction - s 588FE(3);[730]

(b) the 18 November Letter Agreement (in its original terms and as amended on 24 December 2010), the First Additional Securities and the first DCA - insolvent transactions and uncommercial transactions - s 588FE(3);[731]

(c) The Fourth Deed of Variation - insolvent transaction and uncommercial transaction - s 588FE(3);[732]

(d) the Fifth Deed of Variation - insolvent transaction and uncommercial transaction - s 588FE(2) and (3);[733]

(e) the Amended AFL Supplementary Agreement executed on about 16 September 2010 - insolvent transaction and uncommercial transaction - s 588FE(2) and (3);[734]

(f) the Second Supplementary Deed executed on or about 16 September 2010 - insolvent transaction and uncommercial transaction - s 588FE(2) and (3);[735]

(g) the Restated MOFA, the Restated MOFA Guarantees, the Restated MOFA Raine Square mortgage, the Second Additional Securities and the second DCA - insolvent transaction and uncommercial transaction - s 588FE(2) and (3) and unfair loan ‑ s 588FE(6);[736] and

(h) the 13 October 2010 Letter Agreement - insolvent transaction and uncommercial transaction - s 588FE(2) and (3) and unfair loan - s 588FE(6).[737]

  1. The liquidator's primary targets are the 18 November Letter Agreement (including the First Additional Securities) and the Restated MOFA (including the Restated MOFA Guarantees and Second Additional Securities). The other impugned transactions are of secondary significance: the Fourth and Fifth Deeds of Variation embodied transactions which were steps on the way to the Restated MOFA; and the Amended AFL Supplementary Agreement and the Second Supplementary Deed were transactions required by the Restated MOFA and are to be considered in that context.
  2. Section 588FF is within pt 5.7B of the Corporations Act which is titled 'Recovering property or compensation for the benefit of creditors of insolvent company'. The object of pt 5.7B is to prevent the depletion of the assets of a company which is insolvent, or in the process of winding up, by transactions of the nature described in the provisions entered into within certain specified time limits.
  3. Primarily, this case is concerned with uncommercial transactions. Very commonly such transactions will have been undertaken at an undervalue but undervalue is not a necessary characteristic and any transaction that results in a party 'obtaining a bargain of such a magnitude that it could not be explained by normal commercial practice' may constitute an uncommercial transaction.[738] I give more detailed consideration to what constitutes a 'transaction' and an 'uncommercial transaction' later in this part of the judgment.
  4. Section 588FE relevantly provides:
Voidable transactions

(1) If a company is being wound up:
(a) a transaction of the company may be voidable because of any one or more of subsections (2) to (6) if the transaction was entered into on or after 23 June 1993; and

(b) a transaction of the company may be voidable because of subsection (6A) if the transaction was entered into on or after the commencement of the Corporations Amendment (Repayment of Directors’ Bonuses) Act 2003.
(2) The transaction is voidable if:
(a) it is an insolvent transaction of the company; and

(b) it was entered into, or an act was done for the purpose of giving effect to it:
(i) during the 6 months ending on the relation-back day; or

(ii) after that day but on or before the day when the winding up began.
(2A) ...

(2B) ...

(3) The transaction is voidable if:
(a) it is an insolvent transaction, and also an uncommercial transaction, of the company; and

(b) it was entered into, or an act was done for the purpose of giving effect to it, during the 2 years ending on the relation-back day.
...

(6) The transaction is voidable if it is an unfair loan to the company made at any time on or before the day when the winding up began.
  1. In this case s 588FE(1)(a) does not give rise to any issue. Likewise, there was no controversy over the relation-back day (determined by the application of s 91 and s 513C of the Corporations Act) - it was 11 January 2011, the date on which Westgem went into administration.
  2. To succeed, in respect of each impugned transaction, the liquidator was required to establish the transaction:

(a) was a transaction of Westgem - there is an issue as to whether the third party guarantees and securities were transactions of Westgem; and

(b) the transaction was:[739]

(i) an insolvent transaction - that is, it was entered into at a time when Westgem was insolvent or, that Westgem became insolvent as a result of the transaction; and

(ii) also an uncommercial transaction.

(c) alternatively, in respect of the Restated MOFA and the 13 October 2010 Letter Agreement, that they were unfair loans made to Westgem.

  1. As part of their defence to the insolvent and uncommercial transaction claims the Financiers rely on s 588FG(2) of the Corporations Act and contend they acted in good faith and without reasonable grounds to suspect insolvency.
  2. The order in which I have addressed the issues and the conclusions I have reached are as follows:

(a) I have dealt with the issue of insolvency first and, after referring to the statutory provisions and the authorities, have explained why I have concluded Westgem was insolvent between 25 September 2009 and 13 October 2010.

(b) Next, I have considered whether each of the impugned transactions was an uncommercial transaction. In this section I have explained why I consider the various dealings associated with the 18 November Letter Agreement and the Restated MOFA were 'composite dealings' which, in each case, formed part of a single transaction of Westgem and were thus susceptible to being set aside under s 588FF. And I explain why I have reached the conclusion that none of the transactions were uncommercial transactions.

(c) I have then considered the liquidator's claims that the Restated MOFA and the 13 October 2010 Letter Agreement were 'unfair loans' and explain why they were not unfair loans.

(d) Finally, though not necessary to do so in the light of the conclusions I have reached in relation to the liquidator's claims, I have addressed the Financiers' reliance on s 588FG of the Corporations Act and have explained why I consider that provision would not have assisted the Financiers had it been necessary for them to rely on it.

The insolvency issue

The meaning of insolvent transaction

  1. A transaction of a company is an insolvent transaction pursuant to s 588FC of Corporations Act if, and only if:
(1) [I]t is an unfair preference given by the company, or an uncommercial transaction of the company, and:
(a) any of the following happens at a time when the company is insolvent:
(i) the transaction is entered into; or

(ii) an act is done, or an omission is made, for the purpose of giving effect to the transaction; or
(b) the company becomes insolvent because of, or because of matters including:
(i) entering into the transaction; or

(ii) a person doing an act, or making an omission, for the purpose of giving effect to the transaction.

The meaning of insolvency

Statutory definition

  1. Section 95A of the Corporations Act defines 'insolvency' as follows:
(1) A person is solvent if, and only if, the person is able to pay all the person's debts, as and when they become due and payable.

(2) A person who is not solvent is insolvent.
  1. Section 588E(3)(b) of the Corporations Act provides if a company is being wound up, and it is proven that the company was insolvent at a particular time during the 12 months ending on the relation‑back day, then it must be presumed the company was insolvent throughout the period beginning at that time and ending on that day.

General observations

  1. The question of whether a company is able to pay its debts as and when they become due and payable is a question of fact to be determined having regard to all the company's circumstances, including the nature of its assets and business and commercial reality.[740] The test is an objective one.
  2. Solvency and insolvency are determined by the 'cash flow test' which focuses on the liquidity and viability of the business. The test is not whether the company has an excess of assets over liabilities. A company may be cash flow insolvent but show a positive balance sheet on which assets exceed liabilities.
  3. The adoption of the cash flow test does not render the balance sheet irrelevant. The balance sheet may provide contextual evidence which can assist in answering the cash flow question because the cash flow position must be assessed by reference to the company's financial position as a whole.[741]
  4. A temporary lack of liquidity does not equate to insolvency. In Hymix Concrete Pty Ltd v Garritty, Jacobs J (with whom Barwick CJ and Gibson J agreed) said:[742]
A temporary lack of liquidity must be distinguished from an endemic shortage of working capital whereby liquidity can only be restored by a successful outcome of business ventures in which the existing working capital has been deployed.

Commercial realities

  1. In Southern Cross Interiors Pty Ltd v Deputy Commissioner of Taxation,[743] Palmer J said:[744]
Whether, and in what circumstances, the court can determine a company's inability to pay its debts by taking into account the apparent laxity of its creditors in pressing for prompt payment has been the subject of much judicial attention. There is conflict in the authorities as to whether, for the purpose of ascertaining insolvency, a trading debt is to be regarded as payable when it is required to be paid under the terms of the relevant contract or whether the court can take into account normal or likely indulgences granted to the company by its creditors. The cases recognise that the former proposition may produce a test of unrealistic rigidity while the latter may produce a test which is so imprecise as to be impossible of consistent and principled application. Many judges have, therefore, struggled to find some middle ground between the two competing views. The result, unfortunately, is that the law on this point is in a state of some uncertainty.
  1. In Southern Cross, in the course of dealing with a submission that the court should take cognisance of what was said to be a common business practice of debtors delaying payment to creditors for as long as possible and of creditors accepting that practice as a feature of commercial life, Palmer J identified the following propositions drawn from the authorities concerning 'commercial realities':[745]
(i) whether or not a company is insolvent for the purpose of the Corporations Act (Cth), ss95A, 459B, 588FC or 588G(1)(b), is a question of fact to be ascertained from a consideration of the company's financial position as a whole.

(ii) ... Commercial realities will be relevant in considering what resources are available to the company to meet its liabilities as they fall due, whether resources other than cash are realisable by sale or borrowings upon security, and when such realisations are achievable.

(ii) In assessing whether a company's position as a whole reveals surmountable temporary illiquidity or insurmountable endemic illiquidity resulting in insolvency, it is proper to have regard to the commercial reality that, in normal circumstances, creditors will not always insist on payment strictly in accordance with their terms of trade but that does not result in the company thereby having a cash or credit resource which can be taken into account in determining solvency.

(iii) The commercial reality that creditors will normally allow some latitude in time for payment of their debts does not, in itself, warrant a conclusion that the debts are not payable at the times contractually stipulated and have become debts payable only upon demand.

(iv) In assessing solvency, the court acts upon the basis that a contract debt is payable at the time stipulated the payment in the contract unless there is evidence, proving to the court's satisfaction, that:
  • there has been an express or implied agreement between the company and the creditor for an extension of the time stipulated for payment; or
  • there is a course of conduct between the company and the creditor sufficient to give rise to an estoppel preventing the creditor from relying upon the stipulated time for payment; or
  • there has been a well established and recognised course of conduct in the industry in which the company operates, or as between the company and its creditors as a body, whereby debts are payable at a time other than that stipulated in the creditors' terms of trade or are payable only on demand.


(vii) It is for the party asserting that a company's contract debts are not payable at the times contractually stipulated to make good that assertion by satisfactory evidence. (citations omitted)
  1. It is legitimate to take into account forbearance by a company's creditors as to trading terms.[746] An arrangement not to enforce a right to payment of a debt otherwise due and payable may be taken into account in assessing solvency.[747] In Perrine v Carrello, Martin CJ, Mitchell and Beech JJA observed:[748]
In assessing the question of insolvency, the primary judge applied the well‑known outline of principles set out by Palmer J in Southern Cross Interiors Pty Ltd v Deputy Commissioner of Taxation. While different understandings may be open, those principles do not clearly state a hard and fast rule that an arrangement by which a creditor provides some forbearance can only be relevant to an assessment of solvency if it is established that the arrangement had the effect that the debt was not due and payable. Rather, on our reading of the primary judge's reasons, his Honour took into account the arrangement between Perrinepod and Perrine Architecture on the basis that an arrangement by which a creditor provides some forbearance may be relevant to an assessment of solvency, as part of the 'commercial realities', without it being established that the arrangement meant the debt was not payable. The appellants' grounds of appeal and submissions do not raise any issue as to the correctness of that approach. (emphasis supplied) (footnotes omitted)
  1. The reference, in the passage of the Court of Appeal's judgment in Perrine v Carrello cited above, to 'different understandings' may be a reference to a conflict in the authorities as to the approach to be taken to forbearance by a creditor which stops short of an agreement that the debt is not due to which Palmer J alluded in Southern Cross.
  2. In Re New World Alliance Pty Ltd; Sycotex Pty Ltd v Baseler [No 2],[749] Gummow J, however, suggested that the conflict in the authorities might be more illusory than real and emphasised the factual nature of the solvency inquiry. His Honour stated:[750]
Any conflict between the authorities may be more illusory than real and factual rather than legal. I would not consider such an issue to be a question of law to be decided by the application of a rigid rule. Rather, the statute appears to focus attention upon what it is reasonable to expect in a given set of circumstances, such a consideration necessarily being made by someone operating in a practical business environment. Attention is focused at whether a person would expect that at some point the company would be unable to meet a liability. Such a question is necessarily a factual one to be decided in light of all the circumstances of the case. At one end of the spectrum a company may be operating in an industry where a code of practice of paying 60 days after invoicing has arisen, despite stated terms of 30 days. If the company has a large number of creditors, it may be reasonable to expect that all of them would not suddenly insist on being paid in 30 days. At the other end of the spectrum would be a case where a single creditor had granted an indulgence on one occasion. It may well not be reasonable to expect a repetition of that event.
  1. The significance to be attached to the absence of enforcement action by creditors will vary from case to case depending on whether the apparent benevolence of creditors is real or whether the creditors are hostages to the company's fortune. That a company may ultimately survive does not establish it was not insolvent at an earlier time. In JTS Property & Investments No 1 Pty Ltd (in liq) v Sadri,[751] Bryson AJ (as his Honour was at that time) referred to the propositions stated by Palmer J in Southern Cross to which I have referred earlier and, in relation to the circumstances in which a court might have regard to indulgences granted by creditors, said:[752]
... My primary concern is to give effect to s 95A in accordance with its terms, which clearly relate to ability to pay by the due date, not to the ability to cope with the debtor's commercial situation in such a way as to extricate himself from difficulty.
  1. In Hussain v CSR Building Products Ltd,[753] Edelman J also stressed the importance of the statutory test saying at [63]:
[I]t does not matter even if it is unlikely that a creditor will enforce its debt because the statutory test is whether the debt is due and payable.

The importance of reality and a reasoned view

  1. In Bell Group Ltd (in liq) v Westpac Banking Corporation, Owen J (as his Honour then was) emphasised the importance of the word 'reality' in the expression 'commercial reality' and observed:[754]
Insolvency is to be judged by a proper consideration of the company's financial position, in its entirety, based on commercial reality. It is not to be found or inferred simply from evidence of a temporary lack of liquidity. Nor should it be assessed as if the company had to keep cash reserves sufficient to meet all outstanding indebtedness, however distant the date for payment might be in the fullness of time. But nor can directors reliance on faint hope that help is at hand and that all will be well. The word 'reality' in the phrase 'commercial reality' has a bite. Commercial reality dictates that the assessment of available funds is not confined to the company's cash resources. It is legitimate to take into account funds the company can, on a real and reasoned view, realise by sale of assets, borrowing against of the security of its assets, or by other reasonable means. It is a question of fact to be determined in accordance with the evidence.
Support from directors and shareholders
  1. The commercial reality of a company's situation may include the availability of financial support and unsecured borrowings from shareholders or directors. In Williams v Scholz,[755] Muir JA said:[756]
Unsecured borrowings are also relevant, provided that they do not give rise to obligations which the company is unable to meet. Where the Court has the benefit of assessing insolvency with the advantage of hindsight, as is the case here, it will tend to be in a better position to evaluate the true bearing of unsecured borrowings on the Company’s ability to meet its financial obligations. There is some authority for the proposition that unsecured loans by directors cannot be taken into account. There should, however, be no objection in principle to regarding such financial support as relevant where the evidence establishes that the directors are likely to continue it. Loans by related corporations have been regarded as relevant to the determination of solvency. And there is no reason in principle why a loan from directors should be treated any differently to loans from companies controlled by directors. The most important consideration is the degree of commitment to the continuation of financial support. (emphasis supplied) (footnotes omitted)
  1. The views expressed by Muir JA were discussed with approval by Morrison JA (with whom Holmes and Gotterson JJA agreed) in International Cat Manufacturing (in liq) v Rodrick,[757] and again in the later decision of Chan v First Strategic Development Corp (in liq).[758] In Chan Morrison JA (with whom Gotterson JA and Boddice J agreed) said:[759]
... [W]here the financial support is from a source which cannot be compelled by legal arrangement, for there to be a degree of assuredness that the financial support will be forthcoming and at such a level that one could say the company was able to pay its debts as and when they fall due, rather than being possibly able to do so. Just as a conclusion that the relevant financial support does not have to be absolutely certain in order to be sufficient to meet the test in Lewis v Doran, Scholz and International Cat, equally the financial support does not have to be absolutely uncertain in order to be insufficient to qualify. Between the two extremes the factual circumstances of each case will provide a variety of points at which one might conclude that the financial support was of such a degree of commitment that it was likely to continue, and with the result that the company was able to pay its debts, and therefore that it has sufficient financial support to draw the conclusion of solvency.

However, in my view there is no benefit in attempting to achieve some precise formula as to likelihood, by reference to which the financial support qualifies or does not. To say that the likelihood of it being provided is 'probable' or 'improbable' adds no more to what has been said in the authorities to which I have referred. Given that the resolution of this issue will almost always depend upon an assessment of facts, in my view it is better to proceed on the basis that, where the financial support is being provided by a director or related entity, and in circumstances where there is no formalised agreement or understanding, what is required is cogent evidence which enables the court to conclude that there is such a degree of commitment on the part of the provider of the financial support to continue it, such that it can be said that at any point of time it was likely to be continued, with the result that, at any of those times, the company was able to pay its debts as and when they fell due. (emphasis in original)
  1. The availability of support from directors and shareholders may be of particular relevance where the company is, as Westgem was, a vehicle for a development project.[760] In Mulherin v Bank of Western Australia Ltd, Muir JA, with whom McMurdo P agreed, relevantly observed:[761]
There is some authority for the proposition that unsecured loans by directors cannot be taken into account. But where it can be shown that directors are likely to continue to support the company, whether by unsecured loans or otherwise, there is no reason in principle why such support should be regarded as irrelevant. The likely existence of continued support of directors and/or shareholders may be a significant consideration in assessing the solvency of a development project vehicle such as UTC. Its only capacity to pay its debts on or before the conclusion of the development was dependent on the sale of the developed real property for a price higher than the outgoings of the development. In such circumstances, there will tend to be an expectation, once the development is embarked upon financed by loans secured and otherwise, that as long as loan conditions are observed the loans will be extended until the conclusion of the project through sale of the developed lots. That assumes, of course, that lenders continue to have a reasonable expectation that the borrower will have a continued ability to perform its obligations under its loan agreements. And the continued existence of confidence on the part of lenders will depend largely on their assessment of whether the development is likely to result in a net profit or loss. (emphasis supplied)
  1. The provision of unsecured loans will only 'cure' what would otherwise be an insolvent position if the terms of the loan are such that the company can re-order its affairs and pay its other debts as they fall due.[762] In this regard the observations of Barrett J in Australian Securities and Investments Commission v Edwards are of particular relevance:[763]
I accept that funds which, on a realistic commercial assessment, are capable of being raised from outside sources are relevant to the question whether a company is solvent. But the availability of such funds in the form of a loan will not enhance solvency (or have the potential to avoid a finding of insolvency) unless the loan terms are such as to exclude the loan liability from consideration in its own right as part of the debts due or near due. In other words, availability of loan funds for a very short term or payable on demand, as a source from which debts overdue may be paid, does not enhance solvency: it merely substitutes one form of immediate (or near immediate) obligation for another. There is also the point (emphasised by the Court of Appeal in Expile Pty Ltd v Jabb's Excavations Pty Ltd (2003) 45 ACSR 711; [2003] NSWCA 163) that the capacity to raise funds from external sources must be judged in a practical and businesslike way by reference to the commercial realities of the case, not by way of some theoretical textbook exercise. Possibilities are not enough. Genuine and realistic availability, as a matter of commercial reality, must be seen.

The immediate future and hindsight

  1. The words 'as and when they become due and payable' make it clear that although the issue of prima facie insolvency must be determined as at a particular date, the determination calls for a degree of 'forward looking'.[764] How far into the future this 'forward looking' assessment will go depends on the nature and amount of the debts, present and (if known) future liabilities, and on all the circumstances of the company including the nature of its business.[765]
  2. In Lewis v Doran,[766] Giles JA observed:[767]
Solvency or insolvency is a state on which directors and others act in current conduct, for example if the issue is trading while insolvent. Section 95A speaks of objective ability to pay debts as and when they become due and payable, but ability must be determined in the circumstances as they were known or ought to have been known at the relevant time, without intrusion of hindsight. There must of course be 'consideration ... given to the immediate future' ... , and how far into the future will depend on the circumstances including the nature of the company’s business and, if it is known, of the future liabilities. Unexpected later discovery of a liability, or later quantification of a liability at an unexpected level, may be excluded from consideration if the liability was properly unknown or seen in lesser amount at the relevant time. (emphasis supplied) (citation omitted)
  1. In Bell, Owen J explained the reference made by Giles JA to determining insolvency 'without the intrusion of hindsight' as follows:[768]
In my opinion, Giles JA's reference in Lewis v Doran to an assessment made 'without the intrusion of hindsight' means that, when determining the company's ability to pay, it must be done according to the circumstances or state of affairs which were known or 'knowable' at the time. In other words, if an event or fact was either not in existence or was not properly knowable, it is impossible that anyone would have or should have considered it. That fact, therefore, cannot be relevant to an assessment of a company's ability to pay. Giles JA (at [95]) gives an example (on the inflow side) of 'a hopelessly insolvent person who wins the lottery', and (at [103]) (on the liabilities side) of an 'unexpected later discovery of a liability'.

In my view, a court can take into account facts available in hindsight (that is, after the determinative date of solvency) if the facts help determine which version of conflicting accounts as to the state of affairs is the more likely. The fact that an event actually took place might weigh in favour of the alleged expectation as being a commercial reality. But that fact alone is not determinative. It is one only of a host of matters that may intrude into the decision-making process.

Consequently, the court can apply its knowledge of post event facts to determine whether the proffered expectations of the parties (the commercial realities with regard to cash flow) were or were not realistic. For there, the court can make an assessment of the company's ability to pay. But the trier of fact cannot simply look at the facts in hindsight, determine the value of a particular asset or liability which could not have been anticipated at the time, and, without more, include that amount in a cash flow analysis.

... To be admissible, the evidence must shed light on the state of affairs at the time and on what was, or ought then to have been, known about that state of affairs. For example, the reason why a later windfall from a lottery cannot be considered is not just because it is a supervening event, but because the event was properly unknown at the time and therefore can shed no light on the state of affairs.

Sale of a company's assets

  1. In assessing the assets available to pay the company's debts, the relevant question is, what assets are capable of realisation within the time available to meet the company's indebtedness.[769] Realisable property can only be taken into account in assessing solvency 'if that property is in such a position as to title and otherwise that it could be realised in time to meet the indebtedness as the claims mature.[770]
  2. In Re Timbatec Pty Ltd,[771] Bowen CJ in Eq held that a debtor cannot rely on realising assets that would involve a cessation or breaking up of its business.[772] If a company has to resort to selling assets that are essential to the continuation of its business, those assets are not to be included in a determination of solvency.[773]
  3. The decision in Re Timbatec was applied by Hodgson CJ in Eq in Switz Pty Ltd v Glowbind Pty Ltd.[774] That case concerned an application by Switz as a creditor to wind up Glowbind, a property development company. A statutory demand had been made by Switz with which Glowbind failed to comply, and as a result a debt of $1.3 million was immediately payable by Glowbind. His Honour found that an undeveloped property (known as the Erskinville property) owned by Glowbind was fairly valued at $2.5 million and if sold would put the company in a net positive position of $540,000. There were no other assets owned by Glowbind which could sufficiently discharge its indebtedness. His Honour accepted the plaintiff's argument which was put in the following way:[775]
Next, Mr Coles submitted that, treating the real estate owned by the Company as its stock-in-trade, that stock-in-trade was not an asset available to be realised to meet current debts, except in the ordinary course of the Company’s business: see ex parte Russell [1882] UKLawRpCh 45; (1882) 19 Ch D 588 at 601; Re Timbatec Pty Ltd (1974) 24 FLR 30 at 36-7; Rees v Bank of NSW [1964] HCA 47; (1964) 111 CLR 210 at 218. An immediate sale of the Erskineville property would not be a sale in the ordinary course of business: plainly, the ordinary course of business contemplated the completion of the development and the carrying out of contracts for the sale of units which had already been entered into. However, even if the immediate sale of the land were contemplated, the Court could not infer that the proceeds of such a sale would be received in anything less than about three months; and no case had ever suggested that three months to pay an immediate debt of $1.3 million is only a temporary illiquidity. (emphasis supplied)
  1. In his judgment, his Honour observed in relation to a company engaged in property development:[776]
Although s 95A does set a cash flow test, it is conceivable that solvency might be inferred from such a preponderance of current assets over current liabilities.

However, in my opinion an insuperable obstacle to this approach is the debt of $1.3 million to the plaintiff, which must be considered as payable immediately; and the circumstance that there are no assets from which this money can be paid except the Erskineville property ...

Even if the Erskineville property were put on the market immediately, there is no evidence as to when it could be sold and when the proceeds of sale could be expected; and I could not use judicial notice to come to a conclusion that the proceeds of sale could be received any earlier than about three months from now. Furthermore, as submitted by Mr Coles, this is not in fact intended, and would be inconsistent with the course actually being undertaken of developing the site and selling units from the completed development. Plainly, that process will take much longer than three months: again there is no evidence, but I could not take judicial notice that the proceeds of that process would be available any earlier than about one year from now. Again, as submitted by Mr Coles, the immediate sale of the property would be akin to the realisation of stock-in-trade otherwise than in the ordinary course of business, as discussed in the cases of Russell, Timbatec and Reese.
  1. The decision in Switz may be contrasted with the decision of Kearney J in Re Adnot Pty Ltd,[777] which also involved an assessment of solvency in the context of creditor's petition to wind up the company. Adnot was a single venture company - the venture being the development of a shopping centre - and the company was dependent for working capital on loans from a related company. Kearney J held the company was solvent on the basis that negotiations for the sale of the shopping centre were underway and, pending the sale, the company had financial support from its related company. Kearney J also found there were no further steps other than the sale to take place.
  2. In Re Legend International Holdings Inc (in liq),[778] Randall AsJ was concerned with the insolvency of two related companies. One of the questions to be determined was whether the company, Legend International Holdings, was insolvent at the time it entered into a number of transactions. Legend's primary business was the development of mining tenements in Queensland. After canvassing the relevant authorities his Honour explained why certain undeveloped mining tenements were not 'realisable assets' for the purpose of determining Legend's solvency. His Honour said:[779]
If Legend were to realise the mining tenement it would have been selling its chief asset and the basis for its existence. That asset was necessary to the continuation of the business ...

This approach has been applied in the context of property development, which in some ways bears similarities with mining development projects (ie limited cash flow and ongoing investment required in order to eventually realise a profit).
  1. On appeal, sub nom, Queensland Phosphate Pty Ltd v Korda [No 2], it was argued that the approach taken by Randall AsJ was of no application to a cash flow test of insolvency.[780] The Court of Appeal in Victoria reviewed the authorities and stated the principle, which it termed 'the essential business asset principle', as follows:[781]
An asset will not be realisable where it is necessary to the conduct of the business or where its sale, other than in the ordinary course of business, would deprive the company of any future as a going concern.
An overview of the parties' contentions

The liquidator's contentions

  1. The liquidator relies on different grounds for alleging insolvency for different periods:

(a) He alleges that Westgem was insolvent from no later than 25 September 2009 until 5 October 2010 on the basis of the Financiers' refusal to allow Westgem to drawdown on the MOFA as and when Westgem requested drawdowns to pay debts incurred in completing the Project. The relevant debts were principally the 'soft costs', that is, costs incurred to the various consultants working on the Project.[782]

(b) In the alternative, he alleges that if Westgem was solvent prior to entry into the 18 November Letter Agreement or prior to the date on which the 18 November Letter Agreement was amended, 24 December 2009, it became insolvent when it entered the agreement or when it was varied, because Westgem did not have the ability to make the payments due under the agreement in its original or varied form.[783]

(c) He alleges that Westgem was insolvent in the period between 22 September 2010 and 31 December 2010 because Westgem was unable to pay the amounts due to the Financiers under the Restated MOFA when required by its terms and its terms as varied by the 13 October 2010 Letter Agreement.[784]

  1. The liquidator's case was entirely based on the documentary evidence. The evidence included 'Ageing Summaries' (detailing the ageing of debts due to creditors) to which I refer in more detail later.
  2. The liquidator did not give evidence in support of the allegations of insolvency and nor did he adduce any expert evidence. In statements made by him about Westgem's solvency in a report to creditors prepared in his capacity as administrator prior to his appointment as liquidator and, subsequently in a report by him as liquidator, he expressed opinions in relation to Westgem's solvency which are contrary to the allegations made by him in these proceedings.
  3. In a report dated 10 October 2012 prepared by him as administrator for the purposes of s 439A of the Corporations Act he stated:[785]
From my review of the accounting information to hand, together with discussions with the Company's management, it appears the Company was not experiencing difficulty in meeting trade creditor payments leading up to my appointment. The only instances in which the Company was unable to meet its financial obligations prior to my appointment, were in respect of two payments due to the Bank. The first payment was due on 30 September 2010 and the amount of $23 million. This payment was renegotiated and the Bank extended the due date by 90 days. In this regard to the Company was required to pay a total amount of $50 million to the Bank on or before 31 December 2010.
  1. In the liquidator's annual report to creditors prepared on 2 December 2016 pursuant to s 508 of the Corporations Act, the liquidator expressed the following opinion on the solvency of Westgem:[786]
I have investigated the complex matters pertaining to the Company's solvency in detail during the course of the liquidation.

...

An assessment of a company's solvency is a complex exercise which requires consideration of a wide range of factors which can impact a company's financial position. In this regard, in my assessment of the Company's solvency I have also considered the funds the Company had available from both internal sources and also, as a matter of commercial reality, monies obtainable from unsecured and secured borrowings ...

I note that a determination regarding the Company's solvency is dependent upon matters which will be determined in the Damages Claim, primarily regarding the Financiers' conduct in issuing the $23M and $50M default notices to the Company. If the Company succeeds wholly or substantially in the Damages Claim, it is my view that the Company was not insolvent prior to my appointment.

In the event the Company is unsuccessful in the Damages Claim it is possible the Company was or was likely to become insolvent from as early as 30 September 2010 (being the date the company was required to repay $23M to the Financiers). My investigations indicate the Company had insufficient net assets to be able to repay this debt at this time. (emphasis supplied)
  1. The liquidator was not appointed by the court and was not acting as an officer of the court.[787] That said, it is regrettable the liquidator did not give evidence to assist in reconciling the contradiction between the opinions expressed by him in his reports and the position adopted by him in this litigation. As noted earlier, however, the solvency or insolvency question is one of fact for the court to resolve irrespective of any opinion expressed by the liquidator. The facts as I have found them speak for themselves. The liquidator's opinion about Westgem's solvency is inconsistent with the assessment made by me on the facts as I have found them. I have not attached any significance to the fact the liquidator did not give evidence.

The Financiers' contentions

  1. Unsurprisingly, the Financiers relied on the statements, made in the reports to creditors to which I have just referred, as admissions.
  2. The Financiers emphasised Westgem was incorporated as a 'special purpose vehicle' to be funded by the MOFA with further financial support, 'Sponsor Support' provided by Mr Saraceni and Mr Pourzand and entities controlled by them and their families.[788] The Financiers drew attention to the guarantees given by the Saraceni and Pourzand entities, in particular, the unlimited guarantees given by Mr Saraceni and Mr Pourzand in respect of Cost Overruns.
  3. In short, on the Financiers' case, Westgem's solvency was dependent on two things: first, the willingness of Mr Saraceni and Mr Pourzand or their entities to provide funding (or security for funding), and second, whether the Financiers had grounds to refuse drawings under the MOFA, and if such grounds existed, whether the Financiers were prepared to permit drawings notwithstanding the default or whether they would terminate the MOFA.[789]
  4. In respect of the 'commercial realities' the Financiers contended:

(a) Mr Saraceni and Mr Pourzand had the financial capacity to support Westgem (having access to cash in amounts ranging between $6 million and $18.7 million at various times in 2009 - 2010 and access to a 'net equity asset pool' of between $167 million and $202 million prior to entry into the Restated MOFA),[790] they had a history of supporting Westgem and an incentive to do so.[791]

(b) The Raine Square project was itself a valuable asset which Westgem could have sold to meet its liabilities. They point to the evidence of Westgem's own valuer, Mr Mark Foster‑Key, who expressed the opinion that, as at 30 June 2010, the partially completed Raine Square had a value of $385 million (exclusive of GST). The Financiers contended it could be inferred that the value of Raine Square was not much less in February 2010 when Salta left the site because little work was completed between February and June 2010.[792]

(c) Their own willingness not to enforce their claims assisted Westgem to remain solvent. They did not take action in respect of the second Cost Overrun default or act on the 5 March 2010 default notice by the appointment of a receiver. Rather, the Financiers negotiated the 18 November Letter Agreement (and renegotiated its terms when Westgem was unable to comply with the original terms) and in March 2010 began the negotiations that led to the Restated MOFA.[793]

(d) Not only were they willing to forbear but they permitted drawings to meet soft costs amounting to approximately $16.5 million between 8 January 2010 and 5 October 2010,[794] ($11.4 million between 8 January 2010 and 19 August 2010).

(e) Those of Westgem's creditors who were related to Mr Saraceni were prepared to extend their terms for payment.[795]

(f) Other creditors did not take action to enforce payment of the debts owed to them and it could be inferred that Mr Saraceni had made arrangements with creditors about their terms of payment.[796]

(g) The ageing of creditors was not substantial. It would be 'incredible' to think that either Mr Saraceni and Mr Pourzand or the Financiers would have allowed the Project to flounder due to non-payment of amounts which were, in comparison to the overall Project costs comparatively minor, and they did not do so.[797]

  1. In addition the Financiers rely on: the statements made by Mr Saraceni to Salta to the effect that Westgem had sources of finance available to it in addition to the MOFA; the fact Mr Saraceni did not put Westgem into administration before 11 January 2011; and to various statutory declarations made by him for the purposes of documenting variations to the MOFA in which he stated Westgem was solvent.[798]
Consideration
  1. In this case the solvency question is addressed retrospectively and so I have had regard to subsequent events (in particular for the purposes of considering the Financiers' contentions Westgem was able to rely on their support and Sponsor Support) to the extent to which those events reflect on Westgem's solvency on the dates on which the impugned transactions were concluded.

25 September 2009

Inability to pay the $17 million Cost Overrun

  1. 25 September 2009 marks the beginning of the period of insolvency alleged by the liquidator. This was the date the AFL Supplementary Agreement was made and also the date on which Westgem was required to pay the second Cost Overrun of $17 million. In the context of the liquidator's claim the existence of this debt was not in dispute nor was the fact that it was due and payable on 25 September 2009.
  2. The liquidator did not rely on Westgem's indebtedness to trade creditors to establish insolvency on 25 September 2009. Rather he relied on the inability of Westgem to pay the $17 million Cost Overrun debt.
  3. For the reasons set out below I find Westgem was insolvent on 25 September 2009 because it was unable to pay the $17 million debt then due and payable and it remained insolvent for this reason until 1 December 2009.
  4. I infer Westgem was unable to pay the $17 million debt on 25 September 2009 out of its own funds and that there were no other resources available to it with which to pay this debt. I draw this inference from the following facts: Westgem was unable to pay the first Cost Overrun without borrowing from Bankwest; at the meeting held on 21 September 2009 Mr Saraceni said Westgem could not pay the full amount of the Cost Overrun by 25 September 2009,[799] and not only did Westgem not pay the $17 million when it fell due but it did not pay any more than approximately $7 million of the debt despite time to pay being extended, initially to 31 January 2010, and thereafter being extended by the 'tranche payment' arrangement embodied in the variation to the 18 November Letter Agreement made on 24 December 2009.

Solvency not maintained by 'Sponsor Support'

  1. In considering the extent to which Westgem could rely on support from Mr Saraceni and Mr Pourzand I acknowledge they had given unlimited guarantees in respect of Cost Overruns and these guarantees provided an incentive to support Westgem which was additional to the incentive provided by their considerable investment in the Raine Square Project. Westgem, however, had no right to compel them or their entities to provide the cash required to pay Cost Overruns when they became due and payable.
  2. In September 2009 the commercial reality was that Westgem's financial resources did not include an ability to rely on a voluntary commitment by Mr Saraceni or Mr Pourzand and their respective entities to provide financial support to maintain a state of solvency and, in particular, to pay $17 million in respect of the Cost Overrun. In addition to the matters to which I have already referred I rely on the following to make this finding.

(a) First, I rely on the Financiers' contemporaneous assessment of the capacity of each of Mr Saraceni and Mr Pourzand to provide financial support to Westgem to pay Cost Overruns. The assessment of Mr Saraceni's position (as it was in September 2009) was summarised in a strategy paper dated 30 November 2009 prepared for the Executive Risk Committee of Bankwest as follows:[800]

(i) There is no evident capacity for Saraceni to contribute to further Cost Overruns on the Project based on existing cashflows and funding limits;

(ii) The capacity of Saraceni to contribute to a required pay-down of Development Funding to secure long-term debt finance will be subject to his ability to:
  • Generate equity through asset sales;
  • Identify new sources of external capital;
  • Re-structure joint venture asset structures to access additional equity.


(iii) Concern is held over his capacity to meet interest commitments under existing facilities with an estimated ICR of 1.00 times based on recurrent property net rental income. This is likely to have deteriorated in recent months following the application of higher credit margins from various financiers.

(iv) The ability to meet principal repayment commitments under existing BankWest facilities seem dependent upon asset sales being achieved.

(v) Land banking transactions and other non-income earning development projects will place a strain on the group over the next few years.

(vi) The Group faces short-term challenges to gain the continued support of main financiers Westpac/St George and BankWest/CBA.

(vii) Industry concerns over the Raine Square commitments will limit refinancing/re-gearing opportunities in the medium term.

(viii) Concern over management information systems and general risk management practices adopted by the group.

Since the date of the report Saraceni has sold a shopping centre in Busselton WA (sale price circa $13 [million]) and has put a number of assets on the market for sale including a newly completed Coles supermarket in Perth.

The assessment of Mr Pourzand's position was summarised as follows:

A review of the Pourzand position has yet to be completed, but it is understood that his financial position is more liquid based on a greater proportion of cash flow generating property investments.

The asset and liability position for Pourzand group has been reported as follows:

$000
March 2009
Total Assets
473,008
Total Liabilities
138,791
Net worth
334,217

We understand that similar to Saraceni, Pourzand's financial position and ability to access equity in projects has been restricted by limited financing opportunities impacted by aggregation issues with St George/Westpac.

333 is undertaking a complete due diligence on the financial position of the sponsors, and it is expected that this report will be finalised in December 2009.

(b) Second, I rely on the fact that Mr Saraceni and Mr Pourzand or their entities did not provide the support required to pay the amount owing in respect of the second Cost Overrun in the period between 25 September 2009 and 22 September 2010. The failure to provide the funds required to pay this debt not only belies the professions of commitment to support Westgem made by them (in particular those made by Mr Saraceni in his correspondence with Salta to which I referred in the course of dealing with the Salta Stoppage and Salta Termination claims) but also suggest the Financiers' September 2009 assessment of the lack of capacity of Mr Saraceni and Mr Pourzand to provide support to Westgem to meet Cost Overruns was accurate.

  1. Further, though perhaps illustrative of the fragility of the concept of 'Sponsor Support' rather than being of decisive significance, 25 September 2009 was the day Mr Saraceni threatened to 'throw the keys across the table' and 'watch you guys finish the building' in the course of a meeting with senior members of Bankwest's management team.

Financiers' preference for an agreement not a credit resource

  1. With the benefit of hindsight it may be noticed that the Financiers did not enforce their rights in respect of the $17 million Cost Overrun but entered into the 18 November Letter Agreement. The Financiers' reticence to appoint a receiver did not alter the fact that, as at 25 September 2009, Westgem was unable to pay the $17 million then due to the Financiers.
  2. On 25 September 2009 Bankwest gave notice by letter to Westgem that the failure to pay the $17 million Cost Overrun was a breach of the undertaking in the MOFA to pay Cost Overruns within five Business Days of demand by the Facility Agent. In that letter Bankwest reserved the Financiers' rights as follows:[801]
We advise that the Financiers and each other Finance Party (as relevant) by this notice reserve all and any rights and remedies that are available to them under the Facility Agreement and any other provision of the Transaction Documents (including all supporting Security Documents) arising out of that breach of that Project undertaking.
  1. Such an unequivocal reservation of rights presents significant difficulties for the contention that Westgem's solvency was preserved because the Financiers did not take immediate enforcement action in respect of the $17 million debt by appointing a receiver and, implicitly, that the Financiers should be regarded as having provided credit support of $17 million to Westgem.
  2. The commercial reality was Westgem was unable to pay a $17 million debt which was then due and, which remained due because the Financiers had reserved all of their rights. The reservation of rights (being rights and remedies available to be taken in respect of recovering the moneys due) precludes the existence of some agreement, arrangement or understanding that could be regarded as the provision of credit to Westgem that maintained it in a solvent state.
  3. The Financiers attempted to draw support for their contention that the absence of enforcement action by them preserved Westgem's solvency by reliance on Mr Griffiths' evidence that:[802]
I recognised that the appointment of a receiver at this time was a right available to the Financiers as a result of the Raine Square Facility default and was likely a simpler process than the continued frustrating negotiations with the Sponsors. Despite this position I wanted to give the Sponsors every opportunity to remain in control of the Project but on a commercially sensible (to the Financiers) terms.
  1. I accept that Mr Griffiths described the Financiers' preferred position but, from Westgem's perspective, the position was very precarious. That this was so is apparent from an email sent by Mr Deans to Mr Griffiths on 22 October 2009 and a subsequent conversation between them. The catalyst for Mr Deans' email was a discussion between Mr Pavisich and Mr Mentha about Raine Square. In his email to Mr Griffiths, Mr Deans said:[803]
Alan has just come from a meeting with Mark Mentha on Raine Sq. Alan got the general vibe from Mark that you may be leaning toward an appointment on this. Can we have a chat about strategy/reconfirm the current position or discuss if you have changed your position trying to keep the builder going until we have something closer to completion and a project manager in place?
  1. Following receipt of the email, Mr Griffiths and Mr Deans had a telephone discussion. After that discussion Mr Griffiths forwarded Mr Deans' email, under cover of his own email, to Mr Sutton and Mr Lowen with the following comments:[804]
Peter and I had a discussion post his note.

Wanted to confirm I have not changed my view on hopefully how this might go forward.

I have always been of the view that the builder is more important to us than the developer.

My thoughts;

The developer is to some extent treating our very reasonable requests for additional security with contempt.

Therefore we should be prepared for an insolvency appointment but would not rush into this until it suits us.

We should have a project manager available to replace the developer as a matter of some urgency.

We should understand what, if any, value the developer brings to the project i.e. why should we let them continue.

Probably most important thing to understand why workers slowed on the project and what is needed to be done to get it back on track. (emphasis supplied)
  1. In his witness statement Mr Griffiths was at some pains to explain that the comments I have quoted were only intended to convey that 'an insolvency appointment' was only one option available to the Financiers and was not his preferred option.[805] Mr Griffiths was not cross‑examined on this evidence and I accept it. However, in my view the Financiers' reticence to appoint a receiver cannot be construed as some form of commitment by the Financiers to provide Westgem with the ongoing financial support required to maintain it in a solvent state. The possibility that the Financiers would make an 'insolvency appointment' when it suited them was a real one.
  2. In making an assessment of the significance of the Financiers' support for Westgem's solvency I do not ignore that the Financiers did permit drawings to enable Salta to be paid. When the context is appreciated, it is apparent the payments to Salta were not indicative of a commitment by the Financiers to provide financial support for Westgem. Rather, those payments were made out of a concern to keep Salta on site and working because, as Mr Griffiths had said, 'the builder is more important to [the Financiers] than the developer'. BOSI's concern to ensure that Salta was paid was motivated by similar thinking.[806] That the Financiers' motivation for paying Salta was to keep it on site, as opposed to providing financial support for Westgem, is reinforced by their refusal to permit drawings for 'soft costs' between 25 September 2009 and 8 January 2010.
  3. Looking forward from 25 September 2009, the possibility the Financiers might rely on some of their rights arising on the happening of an Event of Default became a reality when the Financiers applied the default rate of interest with effect from 16 October 2009. This is part of the wider commercial context which undermines the proposition that the Financiers' reticence to appoint a receiver was an indication of a commitment on their part to provide financial support to Westgem.
  4. The Financiers' position is to be contrasted with the forbearance discussed in Perrine v Carrello, a decision on which the Financiers rely. In Perrine v Carrello, one of the creditors, a company controlled by the same directors who controlled the debtor company, allowed the company to pay its debts when cashflow permitted, with consequential benefits for that company's solvency.

1 December 2009 - 28 January 2010

  1. Westgem's case requires the solvency question to be considered on 1, 14 and 24 December 2009 and 11 and 28 January 2010. I will begin by considering Westgem's ability to pay debts due to its trade creditors as and when they became payable.

Trade creditors - some preliminary points

  1. In appendix 3 to this judgment I reproduce 'Ageing Summaries' (produced by the liquidator) of the debts due to Westgem's creditors derived from the Quickbooks accounting software on the following dates: 16 October, 29 October, 1 December and 14 December 2009, 11 January, 31 March, 28 April, 29 June, 13 August, 19 August and 5 October 2010 which were attachments A to K respectively to the liquidator's statement of claim. Also included in appendix 3 is an Ageing Summary for 28 January 2010, once again, produced by the liquidator.[807]
  2. The Financiers also prepared Ageing Summaries using data extracted from the Quickbooks accounting software. The Financiers' Ageing Summaries excluded 'current debts' and all amounts due to Salta or Probuild and showed the amounts due to Saracen Project Management Pty Ltd, Saraceni Project Engineering Pty Ltd and Saracen Properties Pty Ltd - the 'Saracen creditors' separately. The Ageing Summary produced by the Financiers for 24 December 2009 is included in appendix 3.
  3. The terms of trade of the consultants, as established by reference to invoices rendered by them, were as follows:[808]

(a) Bollig Design Group - 15 days from date of invoice;

(b) Campaign Focus - 30 days from date of invoice;

(c) David Hewitt & Co - 7 days from date of invoice;

(d) Greg Rowe & Associates - 21 days from date of invoice;

(e) Hocking Planning and Architecture - payment on receipt of invoice;

(f) Jackson McDonald - no later than 30 days after receipt of invoice;

(g) MGB Legal - 14 days from date of invoice;

(h) Ralph Beattie Bosworth - 30 days from date of invoice;

(i) Rider Levett Bucknall - 21 days from date of invoice;

(j) Robert Bird Group - 30 days from date of invoice; and

(k) WSP Lincolne Scott - 30 days from date of invoice.

  1. Based on the terms of trade of the 11 consultants listed in the preceding paragraph I infer the terms of the other consultants who provided services to Westgem, required Westgem to pay their accounts no later than 30 days from the date on which invoices were rendered.
  2. Based on handwritten annotations on a number of invoices, it appears that for its internal accounting purposes, Westgem allocated dates to invoices rendered by some external consultants which were later than the dates originally appearing on the face of the invoices. This was done by crossing out the printed date and handwriting a later date - in one instance an invoice dated 1 September 2009 was changed to 1 November 2009. I infer that the changes to the dates of the invoices were made by someone within Westgem because the same handwriting appears on each invoice on which the date has been changed. The invoices were entered into the accounting system on yet a further later date. For example, invoices rendered by Hocking Planning and Architecture dated 26/08/2009 were annotated by crossing out the printed invoice date and inserting in handwriting '1.10.09' and the invoices appear to have been 'entered' on '30.10.09'. Although the dates differ, a similar approach appears to have been taken in relation to invoices rendered by other consultants. By way of further examples: Campaign Focus rendered an invoice dated 23 October 2009 for $17,496 on which the date was changed to 1.11.09 and it was entered on '2.12.09'; RBB rendered an invoice dated 1 September 2009 for $102,575 on which the date was changed to '1.11.09' and entered on 2.12.09. Changing the invoice dates in this way had the effect of distorting the ageing of creditors to make Westgem's financial position look better than it was. For example, the RBB invoice dated 1 September 2009 for $102,575 does not appear to have been taken into account in the Ageing Summaries for 16 and 29 October 2009 although it does appear in the 1 December 2009 Ageing Summary.
  3. In December 2009 Mr Saraceni is reported to have offered that sums due to 'his companies' - the Saracen creditors - would accrue but not be payable, at least on a temporary basis.[809] For this reason, in the analysis which follows, I have identified separately the amounts due to the Saracen creditors on each relevant date.
  4. The Ageing Summaries for 1 December and 14 December 2009 and 11 January 2010 record amounts due to 'Helen Trust2'. Mr Pourzand and Mrs Jenny Pourzand were the trustees of the Helen Trust, a MOFA Guarantor. I infer the reference to Helen Trust2 is a reference to a trust associated with Mr Pourzand and Mrs Pourzand. The evidence does not permit a finding as to whether Helen Trust2 was, in fact, the MOFA Guarantor, or another trust.

Trade creditors - 1 December 2009

  1. On 1 December 2009 Westgem had:

(a) cash of $1,095,182;[810]

(b) trade creditors other than Salta of $1,728,538 (approximately $1.4 million excluding debts due to the Saracen creditors);[811]

(c) Overdue trade creditors, other than Salta, of $1,402,236 (approximately $1 million excluding debts due to the Saracen creditors).[812]

Trade creditors - 14 December 2009

  1. As at 14 December 2009 trade creditors (other than Salta) amounted to approximately $1.86 million ($1.65 million if the Saracen creditors are excluded) and of this sum approximately $1.4 million ($1.03 million if the Saracen creditors are excluded) was overdue.

Trade creditors - 24 December 2009

  1. The liquidator did not produce an Ageing Summary for 24 December 2009 (the date on which the 18 November Letter Agreement was varied) but the Financiers produced an Ageing Summary (excluding current creditors) for 24 December 2009.
  2. The only material change (in non-current creditors) from the position as at 14 December 2009 was a reduction in the indebtedness to Bollig Design. Between 14 December and 24 December the overdue debt due to Bollig Design (excluding for this purpose the then 'current' debt of $71,390) reduced by $189,414 from $337,414 to $148,000. On 8 January 2010 the Financiers permitted a drawing to pay 'soft costs'. In the Financiers' records, Westgem was noted as a payee for the sum of $189,244 with the annotation 'Bollig Design', from which I infer Westgem had made the reduction in the Bollig debt of $189,414. I note by 1 December 2009 the Helen Trust2 had become a creditor of Westgem in the sum of $192,578. By 28 January 2010 it was no longer a creditor. It is reasonable to infer, and I find, that the Helen Trust2 advanced Westgem the funds required to make the payment of $189,414 to Bollig Design and that this sum was paid back to the Helen Trust2 out of the funds paid to Westgem on 8 January 2010.
  3. Following the payment to Bollig Design of $189,414 the total debt remaining due to it was $219,560, of which $148,000 was overdue.

Trade creditors - 11 January 2010

  1. On 8 January 2010 the Financiers allowed a drawing on the MOFA to pay 'soft costs' amounting to $391,859. This figure included the payment of $189,244 to reimburse Westgem for the payment made to Bollig Design. The balance of $202,615 was applied in the reduction of Westgem's indebtedness to seven creditors but with one exception (Transcore) the payments did not have the effect of discharging Westgem's liability to those creditors for overdue debts. The payments made and the remaining indebtedness is shown in the table below:
Creditor
Payment
Remaining overdue indebtedness
Jackson McDonald
82,616
24,193
WSP Lincolne Scott
44,877
28,754
Maitland Consulting
3,539
11,945
Robert Bird Group
11,000
54,120
Wood & Grieve
32,565
28,853
Ralph Beattie Bosworth
26,400
155,375
Transcore
1,617
-

  1. As at 11 January 2010 trade creditors (other than Salta) amounted to $1.57 million (approximately $1 million if debts due to the Saracen creditors are excluded) and of this sum $1.52 million was overdue (approximately $1 million if overdue debts due to the Saracen creditors) are excluded.
  2. I infer that on 11 January 2010 Westgem did not have the cash available to it to pay the amounts due to its non-Saracen creditors in respect of overdue debts.

Trade creditors - 28 January 2010

  1. On 28 January 2010 Westgem had:

(a) cash of $469,400;[813]

(b) trade creditors other than Salta of $1,577,985 (approximately $887,985 excluding debts due to the Saracen creditors);[814]

(c) Overdue trade creditors, other than Salta, of $1,361,985 (approximately $842,000 excluding overdue debts due to the Saracen creditors).[815]

Support from Mr Saraceni and Mr Pourzand

  1. As outlined above Westgem received some financial assistance to pay its trade creditors from an entity associated with Mr Pourzand, the Helen Trust2, but this was insufficient to do more than reduce the balance of the overdue debt due to Bollig Design to $148,000 - it did not enable Westgem to pay its debts to non-Saracen creditors as and when they became payable - the overdue balance to non-Sararcen creditors was approximately $1 million on 24 December 2009. Moreover, there was no evidence of the basis upon which the Helen Trust2 became a creditor of Westgem. On the face of the Ageing Summaries, all that appears to have occurred is that there was a reduction in the long outstanding debts due to Bollig Design and the creation of new current liability to the Helen Trust2, which was discharged in January 2010 before much older debts due to unrelated consultants were discharged.
  2. Mr Saraceni and Mr Pourzand were unable to comply with the condition in the 18 November Letter Agreement which required them to provide additional security by 14 December 2009 and they required an extension of time until 31 January 2010 to provide that security. The inability to comply with this condition coupled with the inadequate level of support actually provided to Westgem compel the conclusion that Westgem could not rely on support from Mr Saraceni and Mr Pourzand for the purposes of enabling it to pay its debts to trade creditors as and when they became due.
  3. In assessing the significance of Westgem's indebtedness to its trade creditors for the purposes of making an assessment of Westgem's solvency it is not decisive that the trade creditors were ultimately paid, that is, paid long after the debts due to them had become due and payable - that the debts were ultimately paid is not the relevant statutory test.
  4. There is no evidentiary foundation for inferring Westgem had any arrangements or understandings with the creditors that their standard trading terms were varied. That none of the creditors appear to have taken action is not a sufficient basis for inferring that such arrangements were in place. The creditors were hostages to fortune.
  5. On the basis of the evidence to which I have referred I find that Westgem was unable to pay the debts it owed to its trade creditors as and when those debts fell due between 1 December 2009 and 28 January 2010.

Westgem could not rely on support from Financiers

  1. When dealing with the issue of Westgem's solvency on 25 September 2009 I explained why the Financiers' reticence to appoint a receiver could not be understood as an informal credit arrangement which improved Westgem's solvency. There was no change in the position up to the moment the 18 November Letter Agreement was entered into on 1 December 2009. Until the 18 November Letter Agreement was made the $17 million was due and payable and Westgem did not have the ability to pay it.
  2. Indeed further insight into the precarious nature of Westgem's position prior to entry into the 18 November Letter Agreement is obtained from the conditional nature of the Financiers' agreement to extend Westgem's time to pay the $17 million. Of particular relevance was the reservation of the right to the Financiers to obtain a report from an Independent Consultant, upon receipt of which the Financiers could, if they chose to do so, renegotiate the terms of the MOFA, and if agreement could not be reached, the debt could be called in. The Financiers' insistence on the inclusion of this condition in 18 November Letter Agreement suggests that before the agreement was made, there was no basis upon which Westgem could rely on any form of commitment from Financiers to support its solvency.
  3. The Financiers provided no financial support to enable Westgem to pay its trade creditors until they permitted the drawing on 8 January 2010 and that drawing was not sufficient, with the one exception noted earlier, to enable Westgem to clear the debts due to the those creditors who received payment out of the drawing. Comparatively substantial sums remained due to those creditors and the total amount owed to non‑Saracen trade creditors was approximately $1 million.

Raine Square - not a realisable asset

  1. Raine Square was Westgem's principal asset and its only asset of significant value.
  2. Westgem was incorporated to undertake the Project, it was the reason for Westgem's existence and its sole business. The sale of Raine Square in a partially completed state was not in anyone's contemplation. Such a sale would have had the effect of depriving Westgem of its sole asset and undertaking, and it could not be regarded as a sale in the ordinary course of Westgem's business.
  3. In making an assessment of Westgem's solvency, in my judgment, it is not permissible to consider Raine Square a realisable asset from which the company's debts could have been paid. To hold otherwise would be inconsistent with the notions underlying the essential business asset principle discussed earlier. The sale of a partially completed Raine Square would be analogous to a trading company selling its stock‑in‑trade otherwise than in the ordinary course of business.
  4. Further, even if it were accepted that a sale of a partially developed Raine Square may have enabled Westgem to clear all of its debts, that does not compel the conclusion that pending the sale Westgem would have been solvent. The evidence does not support the conclusion that if Raine Square had been put on the market in an incomplete state on, say, 1 December 2009 proceeds of sale would have been received in time to enable Westgem to pay its debts as and when they fell due. By that date Westgem was already unable to pay its debts as they became payable and that was the position from 25 September 2009 to 28 January 2010.

Conclusion on solvency - 1 December 2009 - 28 January 2010

  1. As recorded earlier, throughout this period Westgem was unable to pay its trade creditors as and when they became due and payable. Significant debts were substantially overdue. The reasons why Westgem was unable to pay its debts as and when they became payable was because it had insufficient cash resources on which to draw and no current assets capable of being realised and its only non-current asset was Raine Square, which was its sole undertaking and its raison d'être. Further, it was unable to rely on voluntary commitments of support from Mr Saraceni or Mr Pourzand and the limited assistance received from the Financiers on 8 January 2010 was insufficient. Westgem's situation cannot be characterised as a temporary lack of liquidity. It suffered from an endemic shortage of working capital and was insolvent for the entirety of this period.

The effect of the 18 November Letter Agreement

  1. The 18 November Letter Agreement extended Westgem's time to pay the $17 million in respect of the Cost Overrun to 31 January 2010. The liquidator contends that this extension was conditional upon additional security with a net equity of $50 million being provided by 14 December 2009 and, because the additional security was not provided, the $17 million became due on 14 December 2009. I think that there is force in that submission. Alternatively, the liquidator contends that Westgem was unable to pay the $17 million on 31 January 2010 and that by entering into the 18 November Letter Agreement it became insolvent because it incurred a debt it was unable to pay when it became due and payable.
  2. I have concluded that Westgem was insolvent before it entered the 18 November Letter Agreement and was insolvent after it entered into that agreement because of its inability to pay its trade creditors as and when they fell due. Additionally, however, I am satisfied that on 1 December 2009 Westgem did not have the ability to pay $17 million on either 14 December 2009 or 31 January 2010. I find this was the case based on the following matters.

(a) The request by Westgem for further time to pay the $17 million, a request acceded to by the Financiers, resulted in the variation to the 18 November Letter Agreement made on 24 December 2009.[816]

(b) Mr Pavisich's understanding of Westgem's situation as set out in an email sent by him to Mr McDonald on 21 December 2009 in which he said:[817]

I believe the sponsors are committed to getting us the $17M shortfall in C2C as soon as possible but given the time of year it is difficult to get the asset sales away and settled in that time. Luke Saraceni has also passed on feedback from the parties he is talking to that while they are looking to assist in meeting this commitment in taking an equity stake in the project they will need more time to complete their due diligence. It is difficult for either of us to be able to rely on the opinion of the other but I suggest that we continue to utilise Berrick/333 to be presented where current discussions are at, review any correspondence between the parties and then come back to us with a recommendation on how we should approach it. It is clear with where they are at that a fire sale tomorrow will not get $17M in the door by 31/1/10 but at the same time I am keen that the Sponsors explore alternative equity sources. I personally do not think it will assist the sponsors if they put pressure on these interested parties to meet the $17M equity commitment by 31/1/10. As important as the immediate commitments are we should try to balance that against the longer term requirement to get this re-financed and/or sold to repay the construction debt.

  1. As a consequence, if it were not for the fact that Westgem was insolvent on 1 December 2009, it would have become insolvent on that date by entering the 18 November Letter Agreement.

28 January to 22 September 2010

  1. The finding Westgem was insolvent on 11 and 28 January 2010 engages the statutory presumption that Westgem must be presumed to be insolvent up to the date of the relation back day, 11 January 2011.[818] This statutory presumption is capable of being rebutted by evidence.
  2. In this case the presumption of insolvency was not rebutted. In this respect I rely both on the state of Westgem's indebtedness to the Financiers and to its trade creditors, in particular:

(a) The fact Westgem did not pay the balance of the $17 million Cost Overrun debt (due to be paid in tranches of $5 million due on 28 February 2010 and $7 million on 15 March 2010) out of its own resources and it was unable to rely on a voluntary commitment from Mr Saraceni and Mr Pourzand to meet this payment. And, there is no doubt the Financiers regarded the outstanding balance of approximately $10 million as due and owing and not the subject of a forbearance on the part of the Financiers on which Westgem could depend. This was made clear by Mr Griffiths when he gave the following evidence in cross‑examination.[819]

In November we had had the agreement, in that 18 November letter that was signed on 1 December, that if there wasn't a liability to the bank for $17 million beforehand, most certainly created such a liability; correct?---Correct.

And in January, Westgem paid $5 million of that amount down; correct?---Correct.

And I can tell you that another amount was credited to that particular debt and it actually came from that same Tyne Square sale. You might not remember that; just accept that from me?---Yes.

And that was about $2 million. Okay? I think that happened, maybe, April - March/April. And so from whatever time that happened there’s about $10 million outstanding; do you understand that?---Yes.

Now, in contradistinction to the rest of the money that was owed by Westgem to the bank, that 17 which became $10 million was at all times during 2010 due and payable; correct?---Correct.

And your understanding was, apart from the 5 million and the 2 million that we've talked about - your understanding was that the reason it wasn’t being paid was that Westgem, even with the support of its sponsors, simply did not have the money to pay it; correct?---Correct.

And, in fact, in your mind, that $17 million had, in fact, been outstanding since 25 December 2009; correct?---Sorry. The 17 or the remaining 10?

Well, it started at 17?---Yes.

Your position was 17 had been outstanding since September 2009, it had been reduced by 5 million in January, and I'm sure you knew at the time - you might not remember now - it's reduced a little bit more a month or so later. So the 17 becomes 10; correct?---Correct.

But part of it has been outstanding for the whole period from 25 September 2009; correct?---Correct.

And what that means is, as a matter of legal obligation, each and every day Westgem has to pay that money to the bank; correct?
---It’s a legal issue, so that’s one for you, but - -

Well, you're a banker? ---yes, Unless the ---

It's grist for the mill, isn’t it? - - - Unless the bank - - -

Yes, but - - - - - - agreed to let that go whilst it was considering some other proposals.

Yes. And the bank never made such an agreement; correct?---The bank was always looking for proposals which had gone beyond the second Cost Overrun to the completion of the whole project.

The bank never entered such an agreement; correct?---There was no written agreement that that 10 million wasn’t due and payable.

The bank never entered such an agreement, did it?---No.

Oral, written, implied, anything: correct, did it?---Not that I know.

Well, you would know if it had, would you not?---Most likely.

Mr Mahaffy gave evidence to a similar effect in a passage of his cross-examination, which I reproduce when dealing with the Financiers' defence under s 588FG(2) of the Corporations Act.

(b) In an email sent on 16 June 2010 Mr Dower sent an email to Mr Nagle in which he stated:[820]

... As previously advised we are under extreme pressure from consultants to pay outstanding invoices. We were required to pay Kalagow $6,583 yesterday to ensure they attended a programming meeting. Natale Security are threatening to cease services if they are not paid the $110,089 for services to 10 May by Friday.

On 29 June 2010 the Financiers permitted a drawing to pay Westgem's trade creditors of $3,857,636. Many of the debts to be paid by this drawing were significantly overdue.[821] After the payments made out of this drawing on the Financiers' figures Westgem owed non-current creditors $842,000 and this figure excluded approximately $186,000 owed to Helen Trust2.[822]

The effect of entering the Restated MOFA

  1. On entering the Restated MOFA Westgem was obliged to pay $23 million on 30 September 2010, an obligation it was unable to fulfil. As a consequence, had I not concluded that Westgem was insolvent for other reasons, on 22 September 2010 it became insolvent because it was unable to make the $23 million repayment it had agreed to make on 30 September 2010.
  2. On the various dates on which Westgem entered into the impugned transactions it was insolvent, and had it not already been insolvent it would have become insolvent on entering the 18 November Letter Agreement and Restated MOFA.
Uncommercial transactions

Meaning of uncommercial transaction

  1. A transaction of a company is an uncommercial transaction pursuant to s 588FB of Corporations Act if, and only if:
(1) [I]t may be expected that a reasonable person in the company's circumstances would not have entered into the transaction, having regard to:
(a) the benefits (if any) to the company of entering into the transaction; and

(b) the detriment to the company of entering into the transaction; and

(c) the respective benefits to other parties to the transaction of entering into it; and

(d) any other relevant matter.
(2) A transaction may be an uncommercial transaction of a company because of subsection (1):
(a) whether not a creditor of the company is a party to the transaction; and

(b) even if the transaction is given effect to, or is required to be given effect to, because of an order of an Australian court or a direction by an agency.

Relevant principles

  1. The concept of an uncommercial transaction is directed at transactions which result in the recipient 'obtaining a bargain of such a magnitude that it could not be explained by normal commercial practice'.[823] The 'reasonable person' test and its accompanying relevant matters have widened the scope of operation beyond that which would be encompassed by a provision based merely upon the concept of transactions at an undervalue.[824]
  2. In Queensland Phosphate Pty Ltd v Korda [No 2] the Victorian Court of Appeal summarised the principles applicable to determining whether a transaction is uncommercial according to the test in s 588FB of the Corporations Act as follows:[825]
(a) Under s 588FB, an objective standard is to be applied.

(b) The four criteria set out in s 588FB(1) are to be considered by reference to the company's circumstances, which must include the state of knowledge of those who were the directing mind of the company, such as its directors.

(c) For a transaction to be uncommercial it must result in 'the recipient receiving a gift or obtaining a bargain of such magnitude that it [cannot] be explained by normal commercial practice' or where 'the consideration ... lacks a "commercial quality'".

(d) Courts have adopted a purposive approach in interpreting s 588FB by having regard to the objects and purpose of the provision. The purpose of s 588FB is to prevent a depletion of the assets of a company which is being wound up by voiding transactions at an undervalue entered into within a specified time period prior to the commencement of the winding up. Although s 588FB has been said to focus on transactions entered into at an 'undervalue', uncommercial transactions are not limited to such transactions.

(e) It must positively appear that a reasonable person in the position of the company would not have entered into the transaction.

(f) It has been recognised that the court must view the transaction prospectively 'according to the circumstances at the time, including proper perception of the future, but without the influence of hindsight'.

(g) Consideration of 'detriment' in s 588FB is not limited to monetary detriment, but encapsulates the broader concept of commercial detriment.

(h) The court will have regard to the totality of the business relationship of the parties. The court will also consider whether there is a relationship between the parties to the transaction that may require greater scrutiny. This may include consideration of any personal relationship between the individuals involved in the transaction. (citations omitted)
  1. In McDonald v Hanselmann,[826] in which the issue was whether the impugned sale was transacted at an undervalue, Young J emphasised the importance of the commercial context observing that:[827]
The prime thrust is that one takes a reasonable person in the company's circumstances and asks whether that person would have entered into the transaction. To do this, one focuses on the benefits and detriment to the company in entering into the transaction. However, one then has to focus as well on the benefits to the other parties to the transaction. It is not completely clear why one does this as a matter of logic, but the purpose behind the Division was mainly to stop transactions to related entities or to relatives ...

These remarks are necessary because I have to deal with the questions of value. Value is not a matter which is to be decided in a vacuum. Value usually is associated with a person. The pure concept of value is, of course, what a reasonable objective person would pay for the property rather than lose it, but very often property will have a special value to a person because of factors unique to that person. For instance, a particular copy of a book may have special value because the inscription once showed it belonged to the intending purchaser's grandfather. If that special fact is known to the vendor and to other persons, it may be a matter to take into account when working out what the hypothetical objective purchaser would pay rather than lose it, but very often the special feature will not be known to the vendor or to the general market.

Again, when one is looking at a company on the verge of liquidation, one bears in mind the words Shakespeare attributed to Richard the Third 'A horse! A horse! My kingdom for a horse!' Because of the company's need for current liquid funds, the value of its assets to it may be affected. Normally one does not involve such exigencies in the valuation question and it may be here that it is better to deal with them in seeing whether there is any proper explanation for the transaction, but strictly speaking, such matters do have an effect on the value of the asset to the company.
  1. In White v ACN 153 152 731 Pty Ltd,[828] the Court of Appeal adopted a number of propositions identified by the New South Wales Court of Appeal in Cussen v Commissioner of Taxation,[829] concerning the expression 'in the person's circumstances', as it appears in s 588FG(2)(b)(ii) of the Corporations Act. The propositions included that the expression referred to the person's actual circumstances as they exist at the time they entered into the relevant transaction, and denotes external, objective factors or circumstances rather than factors personal to the person concerned, such as their particular perspicacity, financial acumen and the like. I consider that the expression 'in the company's circumstances' as it appears in the chapeau in s 588FB(1) should be construed in a like manner, that is, as referring to the company's actual circumstances, as they exist at the time the relevant transaction is entered into and denoting external, objective factors or circumstances rather than factors personal to the person concerned, though, the actual knowledge of the directing mind and will of the company is to be taken into account.
  2. The mere fact that a company is insolvent at the time that the transaction is entered into is not itself sufficient to establish that the transaction is uncommercial.[830] This is apparent from the fact that an insolvent transaction must both be an unfair preference or an uncommercial transaction, and be entered into at a time when the company was insolvent or be a transaction resulting in the company's insolvency.
  3. In making an assessment of whether a transaction is an uncommercial transaction it is important to view the transaction as a whole in its commercial context. A focus on one aspect of the bargain in isolation ignores the reality of the give and take inherent in the making of commercial bargains.
The liquidator's pre-action position
  1. In the report to creditors prepared by the liquidator when he was acting as administrator, to which I referred when addressing the insolvency issue, by which time he must have been aware of each of the impugned transactions, he recorded:[831]
My preliminary investigations have not identified any uncommercial transactions or unfair loans; however, further investigations will be conducted during the period of Liquidation, should creditors resolve to place the Company into Liquidation.
  1. I have not attached any significance to the liquidator's provisional view.
The AFL Supplementary Agreement[832]

Terms

  1. The AFL Supplementary Agreement was made on or about 25 September 2009.
  2. On 10 June 2009 Westgem made claims against Bankwest for costs relating to the IFO works. The claims were set out in two letters from Westgem and totalled approximately $3.6 million. By letter sent on 16 July 2009, Bankwest rejected Westgem's claims.[833] Bankwest denied that Westgem had any contractual entitlement to make the claim.
  3. The AFL Supplementary Agreement recited:
The parties seek to modify the arrangements in place under the Agreement for Lease by:

(i) providing for the Lessee to pay a Development Management Fee to the Lessor to enable the parties to proceed with their obligations under the Agreement for Lease with greater certainty as to cost; and

(ii) incorporating processes and procedures to allow transparent, efficient and expedient assessment of entitlements.
  1. By cl 3 Westgem settled claims of $3,605,325 in respect of costs relating to the administration of the IFO works incurred between 13 October 2006 and 15 May 2009 for the sum of $500,000 and agreed to limit its fees for such administration in the future to $17,500 per month for a further 10 months. These categories of payments were referred to as the 'Development Management Fee' and payment of these amounts released Bankwest from any claim in relation to costs for Westgem's administrative functions and expenses. In addition the AFL Supplementary Agreement prescribed the circumstances in which Westgem would be entitled to an extension of time and permitted Bankwest (in its absolute discretion) to direct a variation to the 'Lessors Works' or the IFO Works (as defined under the AFL). In summary the agreement sought to reconcile and synchronise certain processes under the AFL relating to the Bankwest fit out works with like processes in the Salta Building Contract.

The liquidator's contentions

  1. The liquidator alleged that the AFL Supplementary Agreement was an uncommercial transaction by reason of the following:

(a) The claims foregone by Westgem were significantly and disproportionately greater than the benefits of perceived satisfaction of those claims.

(b) The future claims foregone by Westgem were significantly and proportionately greater than the future payments which it agreed to accept in satisfaction of those claims.

(c) The additional control given by Westgem to Bankwest in relation to extension of time claims and variation claims by the builder and the additional power given to Bankwest to direct variations to the project regardless of agreement as to cost were of significant benefit to the Financiers but were of no benefit to Westgem and had the capacity to give rise to commercial and financial detriment.

(d) Westgem was insolvent and therefore in desperate need of funds at the time because of the first and second Cost Overruns and it entered into the transaction for that reason. In short, it was alleged Westgem had no commercial bargaining power.

(e) In all of the circumstances the detriment to Westgem and the AFL guarantors of entering into the transaction far outweighed the benefits to them.

(f) The benefits to Bankwest in entering into the transaction far outweighed any detriment caused to Bankwest as a result the transaction.

The Financiers' contentions

  1. The Financiers submitted the AFL Supplementary Agreement was not uncommercial for the following reasons:

(a) There was no evidence to suggest that the settlement of Westgem's $3.6 million claim for $500,000 was not a settlement on commercial terms and the court should not 'second guess' Westgem's decision to settle.

(b) From a wider perspective the settlement of Westgem's claim facilitated the completion of the Project.

(c) While cl 8 of the AFL Supplementary Agreement set out a mechanism for Bankwest to direct variations, there was a mechanism for the procuring quotations for the work and for payment.

(d) There was nothing inherently uncommercial about the AFL Supplementary Agreement

Consideration

  1. I do not accept that the matters relied on by the liquidator taken individually or in combination are sufficient to justify the conclusion that the AFL Supplementary Agreement was an uncommercial transaction. In reaching this conclusion I have accepted the substance of the Financiers' submissions.
  2. The liquidator led no evidence to establish that the claims made on 10 June 2009 in relation to expenses incurred in relation to the administration of the IFO works were valid claims. There was no evidence establishing a contractual or other entitlement and no evidence the claims had a sound basis in fact. In short, there was no material upon which the court could be satisfied that, if they had been pressed, the claims had the capacity to generate a payment in Westgem's favour of $3.6 million.
  3. The absence of evidence meant the liquidator's claim that the past and future claims foregone were significantly, and disproportionately, greater than the benefits Westgem received (the $500,000 lump sum) and the future payments which it agreed to accept (the monthly instalments of the Development Management Fee payable between 1 September 2009 and 30 June 2010) did not rise above the level of assertion.
  4. Clauses 5 to 7 of the AFL Supplementary Agreement contained detailed provisions regulating the administration of extension of time and variation claims. These provisions gave Bankwest a greater role in the contractual processes but I accept, as the Financiers submitted, and was recited in the AFL Supplementary Agreement itself, the purpose of the provisions was to 'allow transparent, efficient and expedient assessment of entitlements'. Objectively, this was in the interests of both parties and was not indicative of an uncommercial transaction.
  5. Clause 8 of the AFL Supplementary Agreement enabled Bankwest to direct variations. No doubt this benefited Bankwest, and was a detriment to Westgem. The clause, however, included an agreed process for procuring quotations and for payment by Bankwest of both the cost of obtaining the quotations and the cost of undertaking the work the subject of the variations, so the detriment to Westgem was attenuated.
  6. Further, these provisions in cl 5 to cl 8 are not to be assessed in isolation - they were part of the bargain struck between Westgem and Bankwest compromising Westgem's claims. There was no evidence to suggest that the bargain was lacking a 'commercial quality'.
  7. I do not accept that the liquidator has proven that a reasonable person in Westgem's circumstances would not have entered into the transaction when regard is had to the matters outlined in s 588FB(1).
The 18 November Letter Agreement[834]

Terms

  1. I have described the terms of the 18 November Letter Agreement and the circumstances in which it was executed (on 1 December 2009) earlier in this judgment. By way of a summary it is sufficient to say that the Financiers agreed to extend Westgem's time for payment of the second Cost Overrun to 31 January 2010 and Westgem agreed to procure additional security with a net equity value of $50 million. On 24 December 2009 the 18 November Letter Agreement was varied to provide for payment of the $17 million by instalments of $5 million on 31 January 2010, $5 million on 28 February 2010 and $2 million on 15 March 2010. The Financiers also agreed to accept securities with a value in the range of $37.5 million - $44.5 million.[835] I have set out the specific terms which were the focus of the parties' submissions in the paragraphs which follow.

Single transaction

  1. An issue arose as to whether the 18 November Letter Agreement and the First Additional Securities should be regarded as a single transaction of Westgem to which it was a party and, whether as a consequence the First Additional Securities could be set aside by way of an order made under s 588FF. I will deal with this issue first.

The statutory provisions

  1. There are four aspects of the statutory regime to be noted. First, 'transaction' is defined by enumeration in s 9 of the Corporations Act as follows:
[A] transaction to which the body is a party, for example (but without limitation):

(a) a conveyance, transfer or other disposition by the body of property of the body; and

(b) a security interest granted by the body in its property (including a security interest in the body's PPSA retention of title property); and

(c) a guarantee given by the body; and

(d) a payment made by the body; and

(e) an obligation incurred by the body; and

(f) a release or waiver by the body; and

(g) a loan to the body;

and includes such a transaction that has been completed or given effect to, or that has terminated.
  1. Second, for a transaction to be voidable, it must be a transaction of the company: s 588FE.
  2. Third, 'party' is defined inclusively (and unhelpfully) in s 9 of the Corporations Act as follows:
party, in relation to a transaction that has been completed, given effect to or terminated, includes a person, who was a party to the transaction.
  1. Fourth, s 588FF(1) and (2) provide:
(1) Where, on the application of a company’s liquidator, a court is satisfied that a transaction of the company is voidable because of section 588FE, the court may make one or more of the following orders:
(a) an order directing a person to pay to the company an amount equal to some or all of the money that the company has paid under the transaction;

(b) an order directing a person to transfer to the company property that the company has transferred under the transaction;

(c) an order requiring a person to pay to the company an amount that, in the court’s opinion, fairly represents some or all of the benefits that the person has received because of the transaction;

(d) an order requiring a person to transfer to the company property that, in the court’s opinion, fairly represents the application of either or both of the following:
(i) money that the company has paid under the transaction;

(ii) proceeds of property that the company has transferred under the transaction;
(e) an order releasing or discharging, wholly or partly, a debt incurred, or a security or guarantee given, by the company under or in connection with the transaction;

(f) if the transaction is an unfair loan and such a debt, security or guarantee has been assigned - an order directing a person to indemnify the company in respect of some or all of its liability to the assignee;

(g) an order providing for the extent to which, and the terms on which, a debt that arose under, or was released or discharged to any extent by or under, the transaction may be proved in a winding up of the company;

(h) an order declaring an agreement constituting, forming part of, or relating to, the transaction, or specified provisions of such an agreement, to have been void at and after the time when the agreement was made, or at and after a specified later time;

(i) an order varying such an agreement as specified in the order and, if the Court thinks fit, declaring the agreement to have had effect, as so varied, at and after the time when the agreement was made, or at and after a specified later time;

(j) an order declaring such an agreement, or specified provisions of such an agreement, to be unenforceable.
(2) Nothing in subsection (1) limits the generality of anything else in it.

The authorities

  1. The authorities recognise the term transaction has a very broad meaning. In Capital Finance Australia Ltd v Tolcher,[836] Gordon J, with whom Heerey J agreed, stated:[837]
As the trial judge said (at [25] and [26]), the term 'transaction' is a word of wide connotation. It may include a series of events in a course of dealings initiated by a debtor intended to extinguish a debt. The events can occur at different times and in different forms. The categories are not closed. It is not confined to transactions that are lawful or enforceable. The complexity of modern business relations necessarily requires the court to look objectively at the totality of the relationship between the parties in identifying and characterising the 'transaction' for the purposes of the relevant provisions of Pt 5.7B of the Corporations Act. (citations omitted)
  1. In order to determine whether a transaction is uncommercial and, if so, to address the question of appropriate relief, the impugned transaction must be identified with precision.[838]
  2. That is not to say that the concept of a transaction must be distilled into its most narrow formulation. The court is obliged to look at the transactions between the parties in a manner which accords with commercial reality.[839] The transaction may be constituted by the totality of dealings through which the company procures the outcome it intends. In Re Emanuel; Macks v Blacklaw & Shadforth Pty Ltd,[840] the Full Court of the Federal Court (O'Loughlin, Branson & Finn JJ) considered the meaning of transaction and said:[841]
... [W]e do not see the language of s 9 (which exemplifies but does not define 'transaction') as precluding a finding of a transaction to which the debtor A is a party merely because that transaction itself is made up of a composite of dealings in not all of which A participates.

It is not necessary for the purpose of this appeal to determine in any exhaustive fashion when a composite of dealings can together be said to constitute a s 9 transaction notwithstanding that not all of its component parts considered in isolation could rightly be said individually to be transactions.

While s 9 does not define 'transaction', it does through the process of exemplification typify the forms of conduct or dealing engaged in by a company that will be characterised as a transaction for its purposes - 'a conveyance ... of property', 'an obligation incurred', 'a release or waiver' etc. Common to the examples is the characteristic that the conduct or dealing engaged in by the debtor company has the consequence of effecting a change in the rights, liabilities or property of the company itself.

We confine our observations for present purposes simply to a course of dealing initiated by a debtor for the purpose of, and having the effect of, extinguishing a debt. It is not apparent to us why it should not be said that, where a debtor so acts and extinguishes a debt, the relevant 'transaction' is the totality of the dealings through which the debtor procures the intended outcome, irrespective of whether one or more of the dealings in the sequence in question does not involve or require the participation of the debtor but does require that of a third party. The transaction, in other words, is the totality of the dealings initiated by the debtor so as to achieve the intended purpose of extinguishing the debt.

Such a conclusion is consonant with standard dictionary meanings given 'transaction'. It finds some support in decisions on the Bankruptcy Act 1966 (Cth) provisions dealing with voidable transactions and, most notably, Richardson v Commercial Banking Co of Sydney Ltd [1952] HCA 8; (1952) 85 CLR 110 which recognised that a discrete dealing (eg, the payment of money) may itself merely be part of an 'entire' or 'whole transaction': at 129. And, given the characteristics we have identified as being integral to the forms of 'transaction' envisaged by s 9, it is consistent with the burden of the statutory 'definition' itself.

We conclude, then, that a course of dealing initiated by a debtor that is intended to, and does, extinguish a creditor's debt can in its totality be a transaction for the purposes of Pt 5.7B of the Corporations Law notwithstanding that the achievement of that end can only be realised through the participation of a third party in a particular dealing (or dealings) within the overall transaction, being a particular dealing (or dealings) to which the debtor is not or may not be a party.
  1. In Hosking v Extend N Build Pty Ltd,[842] Bathurst CJ (with whom Beazley P and Gleeson JA agreed) cited the observations of the Full Federal Court in Re Emanuel; Macks v Blacklaw & Shadforth Pty Ltd, quoted above with approval.
  2. The meaning of the expression 'transaction of the company' was considered in Kalls Enterprises Pty Ltd (in liq) v Baloglow.[843] Giles JA did not accept (at [102]) that all that was required for there to be a transaction of a company was that the transaction be one to which the company was a party. Similarly, Ipp JA stated (at [212]) that the mere fact that a company is a party to a contract or contracts that form part of a transaction does not necessarily mean it is a transaction 'of' the company. His Honour said:
Whether a company is so bound up in the transaction that it is a transaction 'of' the company is a question of judgment dependent on fact and degree.
  1. Basten JA said (at [236]) that being a transaction 'of' a particular company can be said to involve something more than the concept of a company being 'party to' a transaction.[844]
  2. In Cashflow Finance Pty Ltd v Westpac Banking Corporation,[845] Einstein J considered the meaning of 'party' and (consistently with what was said by the Full Federal Court in Re Emanuel; Macks v Blacklaw & Shadforth Pty Ltd) held that a body could be a party to a transaction even though it did not involve action on the part of the body, that is, a body could be a party to a transaction without any voluntary or deliberate action on its part. Conformably with this wide conception of transaction, it is not necessary for a company to be named as a party to a transaction for it to be a transaction of the company for the purposes of s 588FB of the Corporations Act.

The liquidator's submissions

  1. The liquidator contended that the 18 November Letter Agreement, the first DCA and the First Additional Securities are properly identified and characterised as a single transaction for the purposes of pt 5.7B of the Corporations Act. He argued the three dealings were connected in being directed to bringing about a change in Westgem's rights, liabilities or property. In this respect the 18 November Letter Agreement concerned Westgem's obligation to pay the second Cost Overrun of $17 million, the First Additional Securities were provided to secure that obligation, and the first DCA provided for a payment from Westgem to the Financiers for deferring payment and for the payment of fees as consideration for the provision of the First Additional Securities.
  2. The liquidator contended that the characterisation of the three dealings as a single transaction was supported by the express links between them, a matter to which I refer in more detail later.

The Financiers' submissions

  1. On the 'single transaction' issue the Financiers made one set of submissions addressing both the 18 November Letter Agreement, the First Additional Securities, the first DCA and the Restated MOFA, the Restated MOFA Guarantees, the Second Additional Securities and the second DCA.
  2. The essential point made by the Financiers in their submissions was that s 588FF should not be construed as conferring a discretion to set aside guarantees and collateral securities given by third parties to which the insolvent company was not a party,[846] and which were provided for the very purpose of ameliorating the creditor's position in the event of the insolvency of the principal debtor.
  3. The Financiers contended there had been no case in which a court had relied on s 588FF to set aside a guarantee affecting the rights and obligations of a guarantor of a company in liquidation. They contended that this was significant because if the section could be used in that way it would reduce the utility of a third-party guarantee given to protect a financial institution against the supervening insolvency of a corporate creditor. In support of this contention the Financiers pointed out that s 588FF(1)(e) contemplates that it may be relied upon to set aside a guarantee given by the company in liquidation but does not enable a court to make an order of the nature sought by the liquidator in this action, releasing or setting aside a guarantee as between two parties not including the company in liquidation.
  4. The Financiers contended that, for the purposes of this application, the liquidator must rely on s 588FF(1)(h) which enables the court to make an order declaring 'an agreement constituting, forming part of, or relating to, the transaction or specified provisions of such an agreement, to have been void at and after the time when the agreement was made, or at or after a specified later time'. The Financiers contended this provision simply conferred remedial powers to change the effect of a 'transaction of the company' which has been successfully challenged under one of the substantive provisions of pt 5.7B but does not confer a power or jurisdiction to alter the rights and obligations of other parties to an agreement when this is unnecessary to remedy the effect of a transaction upon an insolvent company. This, they contended, was consistent with: the importance of not interfering with the remedies of financiers (generally) against solvent guarantors, simply because a corporate creditor has become insolvent, and the terms of the mortgages (in this case), which provided that the obligations assumed by the mortgagors were principal obligations of a continuing nature.

Consideration

  1. The outcome Westgem sought to achieve in November 2009 was to remedy the default constituted by its failure to pay the second Cost Overrun of $17 million and thereby enable it to draw on the MOFA again. Several dealings were necessary to achieve that outcome. The Transaction Parties (essentially the parties to the MOFA other than the Finance Parties) were required to agree to the terms set out in Bankwest's letter of 11 November 2009 and each Transaction Party was required to provide Additional Mortgages or Additional Credit Support with a net equity value of at least $50 million. All the Transaction Parties (including those entities that provided the First Additional Securities) were required to sign the letter of 11 November 2009.
  2. The provision of Additional Mortgages or Additional Credit Support was a central and essential requirement that had to be fulfilled to remedy the default. There was unity of purpose between the First Additional Securities, the first DCA and the 18 November Letter Agreement. They were so bound up with each other as to constitute a single transaction. The transaction was a transaction of Westgem because each of its elements had as its object a change in the rights and liabilities of Westgem. Westgem was a party to the transaction both in a narrow sense, because it undertook obligations as specified in the 18 November Letter Agreement and, in a wider sense, because it benefited from the provision of the First Additional Securities.
  3. This conclusion is reinforced by the links between the documents to which the liquidator referred in his submissions. These were:

(a) The 18 November Letter Agreement required the provision of an additional $50 million of securities - cl 3.3.

(b) The First Additional Securities were expressed to secure a principal sum of $17 million, being the Cost Overrun specified in the 18 November Letter Agreement, and were to be discharged on payment of the Cost Overrun, accrued interest and expenses.

(c) The operative provisions of the First DCA, which was executed on the same day as the First Additional Securities, provided that in consideration for the Financiers not 'immediately exercising the Reserved Rights pursuant to the terms of the Letter Agreement' Westgem agreed to pay the amount of $500,000 to the Financiers and Westgem agreed to pay the First Additional Security Providers a 'Security fee' of $51,000 per annum - cl 2.1, cl 3.2.

(d) All of the promises were conditional on the other promises.

  1. I do not accept the Financiers' contention that s 588FF(1) should be construed as not extending to a discretion to set aside a guarantee or collateral security given by a third party to a creditor of a company, and to which the company is not a party.
  2. A purposive approach is to be adopted to the construction of s 588FF.[847] It is to be construed having regard to the object of pt 5.7B, which is to prevent the depletion of assets of an insolvent company by voidable transactions. The difficulty with the construction for which the Financiers contend is that it appears to me to proceed (implicitly at least) from the posited proposition that it could not have been the legislature's intention for s 588FF to be used to set aside a guarantee or, a collateral security given to secure a guarantee, as opposed to proceeding from the text of the statute, and determining the purpose of the provision from the words themselves.[848] There is no support in the text for the limitation on the operation of s 588FF for which the Financiers contend. To the contrary s 588FF(1)(h) is drawn in wide terms and extends declaring 'an agreement constituting, forming part of, or relating to, the transaction ... to have been void ...'. Thus, if a guarantee forms part of a 'transaction of a company', which is a voidable transaction, it may be set aside.
  3. Further the potential for the asset pool available to creditors to be depleted by operation of any rights of indemnity and subrogation held by third parties who have provided guarantees or collateral securities is a reason why s 588FF should be construed as conferring a discretion to set aside such guarantees or securities. In determining in a particular case, whether the remedy of an order setting aside guarantees or collateral securities should be made, no doubt the court would have regard to the nature and effect of the impugned transaction, including the effect of any rights of indemnity and subrogation, on the asset pool available for creditors.

Uncommercial transaction

The liquidator's submissions

  1. In support of the contention there were no practical commercial benefits derived by Westgem from entering into the 18 November Letter Agreement, the liquidator focussed on the following terms:

(a) Clause 3.1 - the liquidator contended this clause reserved to the Financiers their rights to 'exercise all rights available to [them] arising from the Cost Overrun Default (Reserved Rights) to take whatever action [they] deemed appropriate to preserve or enforce [their] rights under any Transaction Document, including, without limitation, taking any of the steps set out in cl 18.1 of the Facility Agreement' with the result that Westgem still faced the risk that the Financiers would take enforcement action in respect of the identified defaults. In short, the Financiers' promise not to 'immediately' enforce the rights under the MOFA was of no practical benefit to Westgem.

(b) The liquidator made substantially the same point in relation to cl 5.1 and cl 5.2 which recorded the consideration moving from the Financiers as 'not immediately exercising the Reserved Rights pursuant to the terms of this letter as they are entitled to do so in accordance with the Facility Agreement'.

  1. The liquidator contended the detriment suffered by Westgem by entering the 18 November Letter Agreement was evident from the following provisions of the agreement:

(a) Clause 3.3(2), by which Westgem undertook to provide Additional Security or Credit support 'acceptable to the Financiers in their sole and absolute discretion' of 'at least $50 million' by no later than 14 December 2009. The liquidator contended the promise to provide 'at least' an additional $50 million in security was 'at large' and open-ended. Further, $50 million was nearly three times the amount of the second Cost Overrun and the Financiers had the 'sole and absolute discretion' whether to accept the proffered security or not.

(b) Clause 5.2 which the liquidator contended gave the Financiers the right to revise the terms of the MOFA and if the revised terms were not acceptable to call in the debt.

(c) Clause 5.1(3) which obliged Westgem to pay a $500,000 'amendment fee'.

(d) The term (not numbered but appearing at the end of the operative provisions) to the effect that a failure to comply with any of the provisions of the letter by any Transaction Party would constitute an immediate Event of Default. The liquidator contended this term created a risk of default which would not have otherwise existed for Westgem.

(e) Clause 3.3(1) contained an acknowledgement by Westgem that the second Cost Overrun had occurred when this did not represent the true state of affairs or Westgem's state of mind.

  1. The liquidator contended the detriment outweighed any benefits and as a consequence the 18 November Letter Agreement and the First Additional Securities were part of a single uncommercial transaction.

Financiers' submissions

  1. The Financiers contended that the liquidator's uncommercial transaction case should not be accepted for the following reasons:

(a) The 18 November Letter Agreement was entered into without any bad faith on their part in order to keep the Project afloat in circumstances in which Westgem was in default in respect of the second Cost Overrun and the Project was beset by problems in the relationship between Westgem and Salta and the relationship between them was in 'terminal decline'.

(b) If the 18 November Letter Agreement was not entered into, the Financiers would have taken immediate enforcement action by reason of the Events of Default that had occurred and were subsisting within the meaning of cl 18.1 of the MOFA.

(c) One of the benefits that the Financiers provided to Westgem under the 18 November Letter Agreement was forbearance. The non-enforcement of their rights by the Financiers involved a significant increase in Project and financing risk under the MOFA that the Financiers had effectively agreed to accept. This risk was common to a number of the impugned transactions and the Financiers characterised it as the 'Forbearance Risk'.

(d) Westgem derived benefits from the 18 November Letter Agreement including:

(i) that the Financiers allowed Westgem to continue to draw and spend substantial funds on the Project; and

(ii) Westgem remained solvent and remained in control of the Project as owner.

(e) The 18 November Letter Agreement gave Westgem the opportunity to complete the Project, an opportunity of significant value to Westgem (and the guarantors). The opportunity embraced:

(i) the opportunity to realise a significant income and return on investment - (the Financiers pointed out that Westgem's valuer, Mr Foster-Key, valued Raine Square in its incomplete state in June 2010 at $385 million);

(ii) the opportunity to build valuable reputation and goodwill in the construction industry in Western Australia; and

(iii) the opportunity to avoid loss of existing security and investment. (The opportunities in (i), (ii) and (iii) were described compendiously as the 'Project Completion Opportunity' by the Financiers.)

(f) As to the $500,000 amendment fee the Financiers made two points. First, they argued such fees are common in the context of amending commercial financing agreements. Secondly, the payment of the fee was a condition and given partly in exchange for a significant reduction of Westgem's liabilities owed to the Financiers, as provided under the 18 November Letter Agreement - namely, the cessation of the Default Rate of interest from 14 December 2009.

(g) The amendment to the 18 November Letter Agreement to provide for tranched payments was obviously beneficial to Westgem - if the 18 November Letter Agreement was not an uncommercial transaction, neither was the amendment to introduce a tranched payment arrangement.

Consideration

  1. There is a factual overlap between the matters bearing upon whether the Financiers acted unconscionably within the meaning of the ASIC Act and whether the 18 November Letter Agreement was an uncommercial transaction. In the paragraphs that follow, for ease of reference, I have repeated some of the provisions of the 18 November Letter Agreement and other matters, notwithstanding they are set out or dealt with in earlier parts of this judgment.
  2. Central to the liquidator's argument that the 18 November Letter Agreement provided no practical or commercial benefits to Westgem was the contention the agreement contained no promise by the Financiers to forbear to exercise their rights in respect of the failure to pay $17 million in respect of the second Cost Overrun (defined in the 18 November Letter Agreement as the Cost Overrun Default). As outlined earlier the liquidator relies on the reservation of rights in cl 3.1 and provisions to a similar effect in cl 5.1 and cl 5.2. It is helpful to reproduce cl 3, cl 4 and cl 5.
  3. Clause 3 provided:
    1. Reservation of rights and additional terms
3.1 Without limiting any other part of this notice, the Facility Agreement or any other Transaction Document, each of the Finance Parties continues to reserve it [sic] right to, among other things, exercise all rights available to it arising out of the Cost Overrun Default (Reserved Rights) to take whatever action it deems appropriate to preserve or enforce its rights under any Transaction Document, including, without limitation, taking any of the steps set out in cl 18.1 of the Facility Agreement.

3.2 As previously notified to you by way of notice dated 9 October 2009, certain Finance Parties and the Borrower agreed the following terms at various meetings and telephone discussions held between 24 September 2009 and until the date of this letter:
(1) the Borrower must facilitate the ongoing Works and successful completion of the Project strictly in accordance with the Building Contract; and

(2) the Transaction Parties must fully co-operate with the Independent Consultant from 333 Real Estate Pty Ltd appointed by the Facility Agent to advise and report to the Finance Parties on such matters as the Finance Parties may require in their absolute discretion in connection with the Project, the Transaction Documents, the Transaction Parties and their business or operations.
3.3 In addition to the terms set out above at paragraph 3.2, the Finance Parties propose the following additional terms for acceptance by the Borrower and other Transaction Parties, subject to each of the Finance Parties obtaining its own necessary internal credit approvals (which have not yet been obtained and in respect of which the Finance Parties make no assurances or representations will be obtained):
(1) each Guarantor acknowledges that all Cost Overruns, including the Cost Overruns in the amount of $12,921,000 and $17,000,000 as set out in the notice to the Borrower dated 18 September 2009 sent by the Facility Agent for and on behalf of the Finance Parties, form part of the Guaranteed Money (as that term is defined in the Guarantees) for which each Guarantor is liable in accordance with the terms of that Guarantor's Guarantee;

(2) each Transaction Party undertakes, and by their execution of this letter here by gives the undertaking (Undertaking), to provide to the Security Trustee, by no later than 14 December 2009:
(a) valid and enforceable second ranking mortgages over all land owned by the Transaction Parties that is currently mortgaged in favour of the Bank of Western Australia Ltd or the Commonwealth Bank Of Australia, and which land is acceptable to the Financiers (in their sole and absolute discretion) (Additional Mortgages); and/or

(b) any other security or credit support acceptable to the Financiers in their sole and absolute discretion (Additional Credit Support),
which is to act as additional security for the repayment of the Facility. The aggregate of the net equity value (as determined by the Financiers in their sole and absolute discretion) in the properties the subject of the Additional Mortgages and the Additional Credit Support must be at least $50,000,000.
3.4 Each of the terms set out in paragraphs 3.2 and 3.3 above is each a Term.
  1. Clause 4 provided:
    1. Cost Overruns and release of additional security
(1) The Borrower must not permit Cost Overruns to exceed $17,000,000 (Cost Overrun Base Amount). Any Cost Overruns, when aggregated with all other Cost Overruns current at that time, in excess of the Cost Overrun Base Amount must be paid from the Borrower's own resources in the manner and at the time prescribed by any document requiring that Cost Overrun to be paid.

(2) The Borrower must ensure that the Cost Overrun Base Amount reduces to zero on 31 January 2010.

(3) The Borrower must provide to the Facility Agent on or before 31 January 2010, evidence satisfactory to the Facility Agent in its sole and absolute discretion, that all Cost Overruns have been paid from the Borrower's own resources and all Cost Overrun Defaults have been remedied.

(4) If the Borrower complies with clause 4(3) above and no Event of Default subsists, the Financiers agree to instruct the Security Trustee to release the Additional Mortgages and Additional Credit Support.
  1. Clause 5 provided:
    1. Acknowledgement and agreement
5.1 The Transaction Parties each acknowledge that, in consideration of the Finance Parties not immediately exercising the Reserved Rights pursuant to the terms of this letter as they are entitled to do in accordance with the Facility Agreement:
(1) the terms of the Additional Mortgages and the Additional Credit Support must be agreed with the Finance Parties and finalised on or before 30 November 2009;

(2) the Additional Mortgages and the Additional Credit Support (in each case duly executed, valid and in registrable form) must be provided to the Security Trustee on or before 14 December 2009; and

(3) if the Borrower complies with paragraphs 5.1(1) and 5.1(2) above, the Finance Parties will discontinue applying the Default Rate to the Secured Money on and from 14 December 20090, subject first to the payment of an amendment fee of $500,000 which must be paid on or before 14 December 2009.
5.2 The Transaction Parties also agree that, in consideration of the Finance Parties not immediately exercising the Reserved Rights pursuant to the terms of this letter as they are entitled to do in accordance with the Facility Agreement, the Financiers may review the Multi-Option Facility and the conditions of the Multi-Option Facility, including, without limitation, pricing, the Cost to Complete and the Security for the Multi-Option Facility after the report, or any interim report, of the Independent Consultant from 333 Real Estate Pty Ltd (IC Report) has been provided to the Facility Agent. Following a review by the Financiers of the IC Report:
(1) the Facility Agent may give a notice to the Borrower stating that the Financiers require amendments to the Multi-Option Facility. The Borrower and the Facility Agent agree to negotiate in good faith for a period of 5 Business Days from the date of service of that notice (Negotiation Period) to determine those amendments; and

(2) if the amendments required by the Financiers are not agreed by the end of the Negotiation Period, the Facility Agent may give a notice to the Borrower under which it nominates a date (being not less than 60 days from the date of service of that notice) (Nominated Date) by which the Financiers require the Borrower to pay to the Facility Agent the Secured Money in full.
  1. In cl 3.1 the reservation of rights is expressed to operate '[w]ithout limiting any other part of this notice' (my emphasis). Plainly, the document was intended to operate as an agreement when countersigned by Westgem and the other parties. While the use of the word 'notice' in the introductory words in cl 3.1 was thus inapt, it did convey the reservation of rights was to be read subject to the other provisions of the letter - provisions which it was contemplated would become binding contractual terms. In my view the reservation of rights is to be read as being subject to the amendment to the terms of the MOFA constituted by the extension of Westgem's time to pay the $17 million (subject to the satisfaction of the additional security conditions) and to the discontinuance of Default Interest on and from 14 December 2009 (subject to the payment of the $500,000 fee). Subject to the satisfaction of the specified conditions, these provisions modified the Financiers' rights in a manner favourable to Westgem. It is necessarily implicit in the liquidator's contention that the reservation of rights meant the agreement provided no practical commercial benefit to Westgem that he contended the reservation of rights is to be construed as taking precedence over the operation of cl 4 and cl 5. In my judgment such a construction does not reflect the text of cl 3.1 ‑ 'without limiting any other part of this [agreement]' - and does not reflect business common sense. In my view, the Financiers' description of the effect of the 18 November Letter Agreement as one involving forbearance by them is a correct characterisation when regard is had to these provisions.
  2. The 18 November Letter Agreement conferred commercial benefits to Westgem in at least three related ways. First, the Financiers agreed not to take enforcement action in respect of the default constituted by the second Cost Overrun. This enabled Westgem to retain control of the Project. The importance of this is not to be underestimated. It provided Westgem with the opportunity to sell all or part of the Project and to seek debt or equity finance from elsewhere. This was an opportunity Mr Saraceni sought to exploit at about this time by commencing negotiations with Charter Hall for it to acquire Mr Pourzand's interest and to recapitalise the Project. Second, rather than being faced with a demand for immediate payment of all monies owing under the MOFA, the Financiers extended Westgem's time for payment until 31 January 2010. Third, before the 18 November Letter Agreement, Westgem's equity in the Project was in serious jeopardy of being devalued as a result of enforcement action. An important consequence of entering the agreement was that the equity was preserved, and with it, as I have said, the potential for Westgem to reach agreement with third parties in relation to refinancing or equity participation.
  3. In addition to the benefits described in the preceding paragraph the 18 November Letter Agreement provided Westgem with the opportunity to put an end to the payment of interest at the Default Rate.
  4. The context in which the 18 November Letter Agreement was made is of particular importance when making an assessment of the Financiers' rights (cl 5.2) to have an independent consultant undertake an investigation. Given the state of the relationship between Westgem and Salta, the competing construction cost estimates, the existence of an Event of Default and Mr Saraceni's threats to sue the Financiers, the Financiers' concern to obtain a report from 333 was justifiable from an objective point of view. This was a prudent step for a lender to take and, of itself, did not impose an additional onerous detriment on Westgem - the Financiers had an unqualified right to appoint an Independent Consultant under the MOFA in any event.[849]
  5. The reservation by cl 5.2 of the right to undertake a review of the terms of the MOFA, negotiate revised terms and if no agreement could be reached, demand repayment of the outstanding debt on not less than 60 days' notice is potentially more contentious. The provision must be assessed, however, in the context of the Financiers having an accrued right to demand repayment of all monies owing under the MOFA by reason of Westgem's failure to pay $17 million in respect of the second Cost Overrun. In those circumstances it was not unreasonable for the Financiers, as part of the consideration for giving Westgem further time to pay the $17 million and forbearing to act on the existing Event of Default, to seek to preserve their right to make a further assessment of the MOFA terms after the receipt of the report from 333. Moreover, the Facility Agent was required to negotiate any revised terms in good faith - no such condition governed the exercise of the Financiers' rights to take action in respect of an Event of Default constituted by the failure to pay the second Cost Overrun. Further, if negotiations were unsuccessful, the Financiers were required to give Westgem 60 days' notice of the requirement to repay the outstanding money rather than being in a position to demand immediate repayment, as the Financiers were entitled to do before entering the 18 November Letter Agreement.
  6. I do not accept that the requirement for additional security having a net equity value of 'at least $50,000,000' is to be construed as enabling the Financiers to seek security with a net equity value of more than $50 million. Nor do I accept that the fact the Financiers sought security with a value of just under three times the amount of the Cost Overrun is sufficient (either on its own or taken with the other matters relied on by the liquidator) to justify the conclusion that the agreement constituted an uncommercial transaction. Rather than being indicative of an uncommercial transaction, it was prudent commercial practice for the Financiers to seek security with a net equity value of $50 million to provide cover against the risk that the securities might not realise that amount if they were called on.
  7. In the preceding three paragraphs I have focused on the benefits derived by the Financiers by entering into the 18 November Letter Agreement. Of course the test is not whether a reasonable person in the Financiers' circumstances would have entered into the agreement. The point to be made is that viewed in the commercial context in which the transaction was entered into, the benefits derived by the Financiers were explicable by reference to the objective circumstances, and were not disproportionate so as to amount to a bargain of such magnitude that it could not be explained by normal commercial practice.
  8. The liquidator did not adduce any evidence that would enable a comparison to be made of the amendment fee and the fees commonly charged by banks and other financiers providing credit of the nature provided by the Financiers. In any event, however, the requirement to pay the amendment fee of $500,000 cannot be considered in isolation, it has to be assessed as part of the bargain struck by Westgem and the benefits obtained by it, which I have outlined above.
  9. In the light of my earlier finding that the second Cost Overrun occurred, it is immaterial that when the 18 November Letter Agreement was made, Westgem may have been of the view that the second Cost Overrun had not occurred.
  10. Finally, viewed from a balance sheet perspective, and leaving to one side the amendment fee, the 18 November Letter Agreement effected no change to Westgem's current liabilities. It owed $17 million in respect of the second Cost Overrun to the Financiers before entering into the transaction and it owed the same amount and not more, after entering into the transaction.
  11. Having regard to the matters to which I have referred not only am I not persuaded of the negative proposition, that is that a reasonable person in Westgem's circumstances would not have entered the 18 November Letter Agreement but I am satisfied that entering the 18 November Letter Agreement was a rational commercial decision that a reasonable person in Westgem's position would have taken. It was a transaction that can readily be explained by normal commercial practice.
Fourth Deed of Variation[850]

Terms

  1. The Fourth Deed of Variation included the following:

(a) An acknowledgement by Westgem and the guarantors that Westgem was in default under the terms of the MOFA as alleged in the notice of default served on 5 March 2010.

(b) A condition precedent requiring evidence that Westgem and Bankwest as tenant had agreed to vary the AFL by amending the date for Practical Completion and the Latest Completion Date in a form and substance satisfactory to Bankwest as the Facility Agent.

(c) A condition subsequent that Westgem and Probuild agree in form and substance satisfactory to Bankwest as Facility Agent contract price and terms in respect of Probuild's engagement is builder for the remaining work required to complete the Project.

Liquidator's contentions

  1. The liquidator contended the Fourth Deed of Variation was an uncommercial transaction for the following reasons:

(a) The acknowledgement of default did not represent Westgem's state of mind nor did it represent the fact and was in any event unnecessary as the MOFA expired on 30 June 2010.

(b) The condition precedent and the condition subsequent were untimely, unreasonable and unnecessary as they conferred a benefit on Bankwest as tenant when it had already determined it would occupy the office space in Raine Square when completed regardless of whether it was complete by Westgem or if receivers were appointed, by the Financiers.

(c) At the time the transaction was entered into Westgem was, to the knowledge of the Financiers, insolvent and desperate for funds to allow it to complete construction of the Project.

(d) The detriment to Westgem and the guarantors of entering into the transaction far outweighed the benefits to Westgem and the guarantors of entering into the transaction.

(e) The benefits to the Financiers and to Bankwest as tenant far outweighed any detriment to the Financiers as a result of the transaction.

Financiers' contentions

  1. The Financiers argued the Fourth Deed of Variation was not an uncommercial transaction for the following reasons:

(a) The expiry date of the MOFA was extended thus relieving Westgem of the obligation to repay the debt in full on 30 June 2010 and providing it with the opportunity to complete the Project - the Project Completion Opportunity. Conversely, the Financiers extended their assumption of the Forbearance Risk.

(b) The liquidator adduced no evidence of Westgem's state of mind in June 2010.

(c) The deed cannot be viewed in isolation - it facilitated the efforts of the parties to conclude a complex web of negotiations directed to the recommencement of the Project which both sides of the transaction considered was to their advantage.

(d) The condition that the terms of the contract between Westgem and Probuild were satisfactory to Bankwest as Facility Agent was a legitimate requirement from the Financiers' perspective given that there were concerns about the building contract with Salta and the fact Salta had 'walked off' the site.

(e) The condition that there be agreement between Bankwest and Westgem to vary the AFL Date for Practical Completion and Latest Completion Date was to ensure that there was a measure of coherence between the MOFA and the AFL. The dates under the AFL required amendment in any event as Westgem was not going to achieve practical completion under the AFL on time. It was of particular importance from BOSI's perspective that the AFL be amended to ensure that Bankwest, in its capacity as lessor, could not terminate the AFL and thereby devalue Raine Square as a commercial development.

Consideration

  1. In my view there is no substance in the liquidator's contention that the Fourth Deed of Variation was an uncommercial transaction. It was clearly to Westgem's advantage to extend the term under the MOFA and thereby extend the time for repayment of the principal debt and allow the refinancing negotiations to be concluded. The other terms about which the liquidator complains were part of the bargain embodied in the deed. They were not inherently uncommercial nor did they constitute a detriment to Westgem or a benefit to the Financiers, that could be characterised as uncommercial. The agreement embodied in the deed was patently commercial in its object and terms. I am not satisfied that a reasonable person in Westgem's circumstances would not have entered into the Fourth Deed of Variation.
Fifth Deed of Variation[851]
  1. The Fifth Deed of Variation contained an acknowledgement in terms identical to the acknowledgement of default contained in the Fourth Deed of Variation save that those who had provided the First Additional Securities were also parties to the 31 August deed and made the acknowledgement.
  2. The liquidator contended that the Fifth Deed of Variation was an uncommercial transaction for largely the same reasons as he contended that the Fourth Deed of Variation was an uncommercial transaction, save that unlike the Fourth Deed of Variation, it did not contain a condition precedent relating to a variation of the AFL or a condition subsequent relating to entry into a construction contract with Probuild. The Financiers' submissions in relation to the Fifth Deed of Variation were relevantly to the same effect as those made in relation to the Fourth Deed of Variation.
  3. In my view the Fifth Deed of Variation was not an uncommercial transaction for substantially the same reasons I concluded that the Fourth Deed of Variation was not an uncommercial transaction.
The Amended AFL Supplementary Agreement[852]
  1. The Amended AFL Supplementary Agreement was entered into on 16 September 2010. It effected minor variations to the terms of the AFL Supplementary Agreement but, as described by the liquidator, it 'was generally in the same terms as the AFL Supplementary Agreement'.[853]
  2. The liquidator contended that the Amended AFL Supplementary Agreement was an uncommercial transaction for the same reasons he contended that the AFL Supplementary Agreement was an uncommercial transaction and, for the additional reason, that the Amended AFL Supplementary Agreement was required to be executed by the provisions of the Restated MOFA.
  3. The Amended AFL Supplementary Agreement was not an uncommercial transaction for substantially the same reasons the AFL Supplementary Agreement was not an uncommercial transaction. I do not accept the liquidator's contention that, because it was a requirement of the Restated MOFA that it be executed, the AFL Supplementary Agreement was an uncommercial transaction - for the reasons explained later, I have found that the Restated MOFA was not an uncommercial transaction.
The Second Supplementary Deed[854]

Terms

  1. The Second Supplementary Deed was entered into on 16 September 2010. It amended the AFL. Among other matters it provided that:[855]

(a) The date for Practical Completion be varied to '14 months after the date of execution of this deed'[856] and the definition of 'Latest Completion Date' be amended by substituting 'the date to 16 months and 2 weeks after the date of execution of this deed' for the date '31 December 2010'.[857]

(b) Liquidated damages would be payable if the Lessor's Works and the IFO Works did not reach practical completion by the Date for Practical Completion in the amount of $15,000 per day.[858]

(c) The tunnel works would not form part of the work that was required to be brought to practical completion by the Date for Practical Completion. Rather Westgem was required to use its best endeavours to bring the tunnel works to practical completion by eight months after the date of Practical Completion.[859]

(d) Westgem was required to pay Bankwest $10,000 per week for each week or part thereof that practical completion of the tunnel was not achieved other than in the circumstance where the only cause of the delay was that Westgem had not secured all relevant consents.[860]

(e) The circumstances in which the Latest Completion Date could be delayed were restricted.[861]

(f) A dispute between Westgem and Bankwest in respect of the costs of the IFO works would be settled by the payment by Bankwest of $12,687,780 to Westgem.[862]

(g) Mr Saraceni was required to provide a personal guarantee of Westgem's obligations.[863]

(h) A new Superintendent was to be appointed.[864]

Liquidator's contentions

  1. The liquidator contended the Second Supplementary Deed was an uncommercial transaction for the following reasons:

(a) The AFL did not require the tunnel to be completed by any specified date and did not provide for any payment resulting from the failure to construct it or a delay in its construction.

(b) The AFL did not provide for any daily payment resulting from any delay in achieving Practical Completion of the Lessor's Works.

(c) The agreed costs of completion of the IFO and the cost of the internal stairs could possibly have been significantly greater than the agreed cost in the deed.

(d) Bankwest had already determined that it would occupy the office space in Raine Square when completed regardless of whether it was completed by Westgem or receivers appointed by the Financiers.

(e) It was unreasonable for the Financiers to insist that Westgem agree with Bankwest (in its capacity as tenant) an extension of the date for Practical Completion as a condition of extending the MOFA.

(f) On 16 September 2010 Westgem was, to the knowledge of the Financiers, insolvent and desperate for funds to allow it to complete the construction of the Project.

(g) In all the circumstances, the detriment to Westgem and the AFL Guarantors of entering into the transaction far outweighed the benefits to Westgem and the AFL Guarantors of entering into the transaction.

(h) The benefits to Bankwest as tenant outweighed any detriment caused to Bankwest as tenant as a result of the transaction.

The Financiers' contentions

  1. The Financiers argued the Second Supplementary Deed was not an uncommercial transaction for the following reasons:

(a) Postponing the dates for practical completion and the Latest Completion Date under the AFL by 14 months and 16 months and two weeks respectively was to Westgem's advantage because it had no prospect of complying with its obligations by the original dates.

(b) The removal of the tunnel from the requirements of Practical Completion was to the benefit of Westgem. Instead Westgem was required to complete construction of the tunnel within eight months of the date of practical completion under the AFL failing which it would be liable to pay liquidated damages. The eight month period was selected because that was the amount of time Westgem had said it needed to complete the tunnel and to align completion of the tunnel with the completion of Bankwest's relocation to its new office premises within Raine Square.

(c) The deed did not impose a new obligation on Westgem in the form of an obligation to complete the tunnel by a certain date. There was already an obligation to do that, and to do so to achieve practical completion under the AFL, so as to trigger Bankwest's rental obligations.

(d) So far as the liquidated damages provision was concerned the effect of the deed was to remove a requirement to complete work by a certain date 'as a fundamental condition of this Agreement', breach of which would have given rise to a right to terminate and to replace the termination right with a liquidated damages provision.

Consideration

  1. In my view it cannot be said that the Second Supplementary Deed was so lacking in commerciality that it constituted an uncommercial transaction. From Westgem's perspective, if it was to avoid being in breach of the terms of the AFL, an agreement varying its terms was necessary. The liquidator has failed to show that the bargain constituted by the terms of the Second Supplementary Deed involved the Financiers obtaining a bargain of such magnitude that it cannot be explained by normal commercial practice. I am not satisfied that a reasonable person in Westgem's circumstances would not have entered into the Second Supplementary Deed.
The Restated MOFA

Terms

  1. To recap, the Restated MOFA increased the borrowing limit under the MOFA by $132.6 million to $448.6 million.[865] It provided the principal was to be repaid in four tranches: $23 million by 30 September 2010; $27 million by 31 December 2010; $33.1 million by 30 June 2011; and the balance on the expiry of the facility on 30 September 2011. It was a term of the Restated MOFA that: a further mortgage over Raine Square, the Restated MOFA Guarantees and the Second Additional Securities, be granted in favour of the Security Trustee and they duly were. At the time the Second Additional Securities were granted it was estimated that the equity in the properties over which security had been taken was approximately $72 million.
  2. Contemporaneously with the execution of the Restated MOFA, the second DCA was executed.

The liquidator's contentions

  1. The liquidator contended the Restated MOFA, the Second DCA, the Restated MOFA Guarantees and the Second Additional Securities are properly identified and characterised as a single transaction for the purposes of pt 5.7B of the Corporations Act. In support of this contention the liquidator argued that the instruments were dealings connected in being directed to bring about the change in Westgem's rights, liabilities or property effected by the Restated MOFA. The liquidator emphasised that the Restated MOFA Guarantees and the Second Additional Securities were provided to secure Westgem's performance under the Restated MOFA, and that the Second DCA provided for a 'security fee' to the Second Additional Securities Providers for providing the Second Additional Securities - the execution of these instruments was a condition precedent of the Restated MOFA.[866]
  2. At the forefront of the liquidator's case was the proposition that the benefits received by Westgem as a result of entering the Restated MOFA - the provision of additional credit and an extension of the life of the facility to 30 September 2011 were entirely illusory because, inevitably, Westgem was going to default in its obligations under the MOFA within a matter of days. The liquidator contended Westgem was, to the knowledge of the Financiers, insolvent and desperate for funds to allow it to complete the construction of the Project.
  3. The liquidator contended that the 'illusory' benefits were outweighed by the serious detriments to Westgem in entering the Restated MOFA and that a reasonable person in Westgem's circumstances would not have entered into the Restated MOFA, apart from anything else, the Restated MOFA required payment of $23 million in little over a week in circumstances where Westgem did not have available to it the funds to make that payment.
  4. Conversely, the benefits to the Financiers far outweighed any detriment caused to them by entering into the transaction.
  5. The serious detriments relied upon by the liquidator were constituted by the following terms of the Restated MOFA.

(a) Westgem was required to repay the principal in instalments which it could not pay (and which the Financiers knew it could not pay).[867]

(b) Westgem was required to pay an extension fee of $1.5 million.[868]

(c) The margin component of the interest rate was increased from one percent per annum to 3% per annum,[869] (the liquidator alleged that the cost of funds had reduced since entry into the MOFA).

(d) The line fee was increased from 0.5% per annum to 1.5% per annum and was payable on 30 September 2011.[870]

(e) The bank guarantee fee was increased from 1% percent per annum to 3% per annum and was payable on the issue of each bank guarantee and on each 30 June and 31 December in advance thereafter.[871]

(f) The letter of credit fee was increased from 1% per annum to 3% per annum.[872]

(g) Westgem was required to pay Bankwest for its own account (in its capacity as Facility Agent) an agency fee of $75,000 per annum payable yearly in advance from 22 September 2010.[873]

(h) Westgem was required to pay the Security Trustee for its own account a fee of $45,000 per annum payable yearly in advance from 22 September 2010.[874]

(i) The guarantors were required to market the properties the subject of all securities given by them, including Mr Saraceni's interest in the Vasse Newtown project, to the extent that the receipt of proceeds of sale of those properties was necessary to meet the obligation to repay the principal debt under the Restated MOFA.[875]

(j) The Financiers could appoint one or more Independent Consultants at any time in their absolute discretion and as at 22 September 2010 had appointed 333 as an Independent Consultant and Westgem was required to pay the costs thereof.[876]

  1. The liquidator relied also on the facts that when the Restated MOFA was executed the Undrawn Commitment under the MOFA was approximately $44,914,636 and Westgem had incurred approximately $12.1 million in penalty interest, approximately $1.4 million in respect of the Financiers' legal costs in connection with the MOFA, and approximately $2.55 million in respect of 333's costs.

The Financiers' contentions

  1. The Financiers contended that, 'in some respects, the Restated MOFA was the most obviously commercial' of the transactions impugned by the liquidator. They identified the benefits received by Westgem as a result of entering into the Restated MOFA as follows:

(a) The expiry date of the facilities was extended to 30 September 2011.

(b) Additional funding of $132.6 million was made available to Westgem based on the revised estimate of construction costs.

(c) Westgem remained solvent and out of receivership.

(d) The informal extension of the obligation to pay the balance of the second Cost Overrun was effectively formalised.

(e) Westgem continued to enjoy the benefits of the opportunity to complete the Project.

  1. The Financiers argued that the 'core matters' about which Westgem complained were misconceived in the following ways:

(a) first, the reduced cost of funds available to the Financiers was passed on to Westgem through the bank bill rate as the interest rate under the restated MOFA was the sum of the bank bill rate plus the margin and it was the margin that had increased from 1% to 3%;

(b) second, the increased margin reflected the Financiers' assessment of the credit risk;

(c) third, the fees charged by the Finance Parties were common to financing transactions and were not disproportionate to risk, usurious, extortionate or otherwise offensive to commerciality;

(d) fourth, the additional equity and repayment obligations, had been the subject of negotiations between the parties since March 2010, and were not disproportionate to the risk of the increase in the funds made available to Westgem and the additional time provided for it to make repayment - they provided a 'glide path' to bring the facility within the usual LVR parameters and later transition to term finance;

(e) fifth, the guarantors made separate commercial decisions weighing the value of the security provided by them against the value of the Project upon completion and the loss of the securities already provided, the provision of the Second Additional Securities did not result in Westgem suffering a detriment as it did not provide the securities.

  1. The Financiers contended also that the Restated MOFA exposed them to the ongoing risks inherent in financing Westgem (the Forbearance Risk), when Westgem had already committed a series of defaults and had demonstrated a questionable ability to complete the Project (completion being necessary to perfect the Financiers' principal security), and their prospective exposure to Westgem had increased substantially.

Consideration

  1. I have set out the principles governing whether composite dealings are to be considered a single transaction of a company for the purposes of pt 5.7B of the Corporations Act in the course of dealing with the issue of whether the 18 November Letter Agreement and the First Additional Securities constituted a single transaction of Westgem to which it was a party. In my view, conformably with those principles, the Restated MOFA, the Restated MOFA Guarantees, and the Second Additional Securities are to be regarded as a single transaction for the reasons contended by Westgem. The object of each of these dealings was to bring about a change in the rights, liabilities and property of Westgem by giving effect to the terms of the Restated MOFA. Accordingly, they are properly characterised as a single transaction of Westgem.
  2. The range of 'benefits' and 'detriments' to be considered of the purpose of assessing whether the Restated MOFA and related dealings constituted an uncommercial transaction are identified in my summary of the parties' submissions and it is unnecessary to repeat them here. I propose to analyse the issue by describing the circumstances in which the 'reasonable person' would have found themselves in September 2010 as they contemplated Westgem's options. Those circumstances, and my assessment of them, are as follows:

(a) Work on the Project could not recommence without refinancing. Mr Saraceni and Mr Pourzand were unable to provide the funding required to remedy the defaults and meet the increased construction costs. Consequently, Westgem was dependent on refinancing by the Financiers to enable Probuild to start work on the completion of the Project. The MOFA had to be renegotiated to remedy the default and to make provision for the increased construction costs.

(b) On the evidence available to the court, the only options for Westgem were to allow its business - the Project - to fail and acquiesce (in the commercial sense) in the appointment of receivers or enter into the best revised financing arrangement with the Financiers it could negotiate. I infer from the pressure Mr Clohessy brought to bear on the Financiers to finalise the terms of the Restated MOFA that it was not possible for Westgem to obtain equity or debt finance on acceptable terms from other external sources without work first having recommenced.

(c) The terms of the Restated MOFA had been negotiated over a period of six months. There was no reason to think that terms more preferential to Westgem could be negotiated with the Financiers.

(d) Westgem had a substantial investment in the Project. Mr Saraceni and Mr Pourzand had represented to the Financiers that they considered their equity in the Project had a value of more than $100 million. A rough indication of the value of the investment at stake can be obtained by taking Mr Foster-Key's valuation of the partially completed Raine Square as at 30 June 2010 - $385 million and deducting the debt due to the Financiers at 30 June 2010 - $265 million,[877] leaving a balance of $120 million. This figure does not take into account current liabilities of approximately $3 million or the long term loans to Westgem made by entities associated with Mr Saraceni and Mr Pourzand amounting to approximately $74 million.[878]

(e) The value of Westgem's interest in Raine Square provided a substantial incentive for it to retain control of the Project and to negotiate refinancing with the Financiers.

(f) In September 2010, from Westgem's perspective, it would have been reasonable to fear that the outcome of the appointment of a receiver would not only result in no return to Westgem on its investment but that the investment itself would be lost with no return to unsecured creditors. In this respect it is to be noted that default interest of over $12 million had accrued over a period of 11 months and the fees charged by the Financiers' professional advisers were in the region of $4 million of which (at least) $2.55 million (333's fees) had accrued over some 11 months. It would be reasonable to fear that if a receiver were appointed Raine Square would be regarded as a distressed asset and this would have a significant adverse effect on its value.

(g) Viewed in isolation the extension fee and the other fees charged pursuant to the terms of the Restated MOFA were substantial but viewed in the context of the amounts involved in the refinancing, the value of Raine Square and Westgem's investment, they were to be accorded much less significance - they were part of the cost of the transaction.

(h) The element of the consideration with the most substantive value, the $72 million of security constituted by the Second Additional Securities and the Restated MOFA Guarantees, which passed to the Financiers pursuant to the terms of the Restated MOFA, was provided by entities associated with Mr Saraceni and Mr Pourzand and not by Westgem itself. Faced with the alternative of receivership and the consequences likely to follow, it would have been difficult to identify a compelling reason why Westgem would not have accepted the benefit of the support, in the form of security that Mr Saraceni and Mr Pourzand could procure. It is important to remember that the question to be addressed is whether a reasonable person in Westgem's position would not have entered the Restated MOFA, and not whether a reasonable person in the position of the Restated MOFA Guarantors and Second Additional Securities providers, would not have taken the risk of providing those guarantees and securities.

(i) Westgem knew it would not be able to pay the $23 million repayment of principal due on 30 September 2010. In assessing whether to enter into a contractual commitment that the reasonable person knew could not be met, the reasonable person would make an assessment of what would be likely to follow from a failure to meet the commitment, what other options were open and what was at stake. A reasonable person in Westgem's situation would have known that entering the Restated MOFA was the only alternative to receivership - there were no other commercial options. Westgem's only asset was already mortgaged in favour of the Financiers. Entering the Restated MOFA put third party assets at risk, but that was a matter for those third parties, in other words the cost to Westgem of entering the Restated MOFA and thereafter defaulting was limited. But not entering the Restated MOFA would lead to receivership and commercial catastrophe. The decision faced by Westgem involved choosing between two unattractive alternatives. There was, however, at least some reason for believing that the Financiers would not take immediate enforcement action. In this respect I refer to my earlier findings that the possibility that Westgem would not be able to make the $23 million payment on 30 September 2010 had been raised with Mr Galbraith before 12 September 2010, and that by 22 September 2010 Mr Galbraith had reason to think the payment would not be made and this had not caused the Financiers to call a halt to the process of finalising the Restated MOFA. Further, the Financiers had exercised restraint in dealing with earlier defaults and this would create a level of confidence that a default in paying the $23 million would be met with a similar degree of restraint. Such confidence, though, might be tempered by the knowledge that the Financiers' earlier restraint had been exercised whilst they were negotiating to obtain the Second Additional Securities and having obtained the benefit of those securities, there was less reason for the Financiers to be accommodating.

(j) A reasonable person in Westgem's position would have known that Raine Square was of interest to investment funds and investment bankers and, if it could retain control and have work recommence on the Project with (conditional) access to a further $132.5 million in finance, there was the possibility of one or more of a partial sale, an investment of equity, or debt refinancing on terms more suited to Westgem's interests than those contained in the Restated MOFA. A reasonable person would have known that: in January 2010 Charter Hall had entered into a conditional agreement to purchase Mr Pourzand's interest in Raine Square;[879] Goldman Sachs had expressed interest and had provided Westgem with materials for discussion in early September 2010;[880] JP Morgan had provided a terms sheet on 13 September 2010;[881] and there had been discussions with another interested party, 'Forum Partners', which I infer (from an email sent by Mr Joel Saraceni on 30 September 2010)[882] had been on foot for some time.

  1. Confronted with the prospects of the failure of its business undertaking, receivership and the loss of its investment in Raine Square, I am not persuaded that a reasonable person, knowing that third parties were prepared to provide support by risking their assets as security, would not have entered into the Restated MOFA. To the contrary, while it may not have been an easy decision, objectively entering into the Restated MOFA would have been a rational commercial decision for a reasonable person to make.
  2. In the preceding paragraphs I have focussed on the benefits and detriments to Westgem. Turning to the benefits received by the Financiers, in my judgment, the increase in interest rates and the fees about which the liquidator complains were not disproportionate to the risk that was assumed by the Financiers. The liquidator's complaints in these respects were not supported by evidence. Further, while it is true the Financiers obtained the benefit of the Second Additional Securities with an estimated value of $72 million, the benefit was contingent on the securities realising the values attributed to them and of course the Financiers agreed to provide further funding of $132.5 million over an extended term.
13 October 2010 Letter Agreement
  1. Under 13 October 2010 Letter Agreement the Financiers agreed to defer payment of the $23 million repayment of principal that had been payable on 30 September 2010 until 31 December 2010. The Financiers required Westgem to pay a default fee of $230,000.
  2. The liquidator and the Financiers supported, and resisted, respectively, the claim the 13 October 2010 Letter Agreement was an uncommercial transaction generally by reference to the submissions made in respect of the Restated MOFA.
  3. The purpose of the 13 October 2010 Letter Agreement was to remedy a default by Westgem. It was being granted an indulgence by the Financiers in circumstances which, save for the default and the recommencement of work, had not changed materially in the three weeks since the Restated MOFA had been executed. The default fee may be regarded as the consideration for the Financiers' waiver of their accrued right to charge default interest. The default fee was not a detriment disproportionate to the benefit derived by Westgem when the circumstances in which Westgem found itself are taken into account. I have outlined those circumstances in dealing with the claim regarding the Restated MOFA.
  4. In summary the considerations that led me to conclude that the Restated MOFA was not an uncommercial transaction also lead me to conclude that the 13 October 2010 Letter Agreement was not an uncommercial transaction.
Unfair loans
  1. The liquidator alleged that the Restated MOFA and the 13 October 2010 Letter Agreement were unfair loans within the meaning of s 588FD of the Corporations Act.

Meaning of 'unfair loan'

  1. Section 588FD of the Corporations Act provides:
(1) A loan to a company is unfair if, and only if:
(a) the interest on the loan was extortionate when the loan was made, or has since become extortionate because of a variation; or

(b) the charges in relation to the loan were extortionate when the loan was made, or have since become extortionate because of a variation;

even if the interest is, or the charges are, no longer extortionate.

(2) In determining:
(a) whether interest on a loan was or became extortionate at a particular time as mentioned in paragraph (1)(a); or

(b) whether charges in relation to a loan were or became extortionate at a particular time as mentioned in paragraph (1)(b);

regard is to be had to the following matters as at that time:

(c) the risk to which the lender was exposed; and

(d) the value of any security in respect of the loan; and

(e) the term of the loan; and

(f) the schedule for payments of interest and charges and for repayments of principal; and

(g) the amount of the loan; and

(h) any other relevant matter.

Authorities

  1. In the case of many borrowers approaching insolvency it may be difficult to establish that a particular interest rate is extortionate, as many borrowers in such a position will pose an otherwise unacceptable credit risk. In Emanuel Management Pty Ltd (in liq) v Foster's Brewing Group Ltd,[883] Chesterman J (as his Honour then was) observed:[884]
The considerations discussed earlier when considering the complaint about profit fees is relevant to the complaint about extortionate rates of interest. The rate charged in any given set of circumstances will reflect the risk to the lender, the ability of the borrower to repay the principal and to service the loan in the interim, the value of the property taken to secure the loan and the cost and difficulty involved in selling the property if the lender is obliged to act in that regard. The rate will also reflect competition between lenders for business and the attractiveness of a borrower to lenders.
  1. His Honour went on to say:[885]
Section 588FD uses strong words when describing when a loan will be unfair. The interest rate must be 'extortionate'. This means it must be exorbitant, or grossly excessive, or characterised by extortion. This latter term is the act of extorting, i.e. wresting or wringing something from a person by violence, intimidation or abuse of authority, or obtaining money etc. by force, torture, threats or the like. See the Macquarie Dictionary. It is not enough to make a loan unfair for the purposes of s 588FD that the interest rate charged is higher, even substantially higher, than the market rate for similar transactions. There must be something in the fixing of the rate which brings to mind the concepts implicit in the word I have just identified. There is a particular difficulty when there are no similar transactions and one is forced to compare interest rates charged on 'ordinary' transactions with those which are unusual and which by their nature would attract a higher rate of interest.
  1. In Re Essendon Apartment Developments Pty Ltd (in liq) [No 2],[886] Robson J held that a loan with an interest rate of 60% and a default interest of 75% was not extortionate when the court took into account the relatively high risk to the lender, the mortgage was a second mortgage on an undeveloped development, the loan was for three months and the loan was only for $120,000.
  2. In Guardian Mortgages Pty Ltd v Miller,[887] Wood CJ at CL considered whether a secured loan which provided for an effective interest rate of 174% per annum, reducible to 144% per annum, was an unjust contract or alternatively an unconscionable agreement. His Honour held that the 'interest rate, although admittedly high, does not constitute of itself an unconscionable or unjust provision, in a case such as the present involving a commercial loan, where there was no unconscionable pressure, placed on the Defendant by the Plaintiff, to enter into the transaction'.[888]

The liquidator's case

  1. In the statement of claim the liquidator alleged that the Restated MOFA and the 13 October 2010 Letter Agreement were unfair loans having regard to the following matters:

(a) the fact that the interest on the loan made under the MOFA became extortionate because of the variation contained in the Restated MOFA;

(b) the fact that the charges in relation to the loan made under the MOFA became extortionate because of the variations contained in the Restated MOFA;

(c) the risk to which the Financiers were exposed;

(d) the value of the security in respect of the loan;

(e) the term of the loan;

(f) the schedule for payment of interest and charges and for payments of principal under the Restated MOFA;

(g) the amount of the loan; and

(h) the matters pleaded [in support of the uncommercial transaction claims].

  1. The liquidator did not make any submissions specifically directed to the unfair loans claim but relied, as I understand it, on the submissions made in support of the uncommercial transaction claims in respect of the Restated MOFA and the 13 October 2010 Letter Agreement.

The Financiers' contentions

  1. The Financiers submitted that the increase in the interest rate of which the liquidator complains was a reflection of the increased risk presented by Westgem in September and October 2010. They also submitted that the failure by the liquidator to adduce any evidence in support of his claim that the interest rate and fees and charges were extortionate was fatal to his claim as the question what is extortionate can only be answered by reference to industry practice as applied to the circumstances of the transaction in question, that is because industry practice establishes what rates and charges are regarded as appropriate by the market (ie, not extortionate) to compensate the relevant levels of risk.

Consideration

  1. Although I consider that the Financiers' submission that the question of whether interest rates and fees and charges can only be determined by reference to evidence of industry practice may overstate the position,[889] in this case the absence of any evidence to support the liquidator's claim is fatal to it. Neither the interest rate nor the fees and charges appear to be extortionate. I accept that Westgem's 'risk profile' had deteriorated since April 2008 when it entered into the MOFA. I have no hesitation in concluding that the Restated MOFA and the 13 October 2010 Letter Agreement were not unfair loans.
Financiers' defences to insolvent and uncommercial transaction claims
  1. In their defence of the liquidator's insolvent and uncommercial transaction claims the Financiers rely on s 588FG(2) of the Corporations Act. The liquidator has not established that any of the impugned transactions were uncommercial transactions but lest I am wrong in the conclusions I have reached in relation to those matters I will consider the Financiers' s 588FG(2) defence.

Section 588FG(2)

  1. Section 588FG(2) provides:
(2) A court is not to make under section 588FF an order materially prejudicing a right or interest of a person if the transaction is not an unfair loan to the company, or an unreasonable director-related transaction of the company, and it is proved that:
(a) the person became a party to the transaction in good faith; and

(b) at the time when the person became such a party:
(i) the person had no reasonable grounds for suspecting that the company was insolvent at that time or would become insolvent as mentioned in paragraph 588FC(b); and
(ii) a reasonable person in the person's circumstances would have had no such grounds for so suspecting; and
(c) the person has provided valuable consideration under the transaction or has changed his, her or its position in reliance on the transaction.

Applicable principles

  1. There was no material dispute between the parties as to the principles that guide the application of s 588FG(2). The following summary of the relevant principles is derived from the judgment of the Court of Appeal in White v ACN 153 152 731 Pty Ltd, at [105] - [127] and the authorities referred to by the Court:

(a) The onus is on the creditor to establish the defences under s 588FG(2).[890]

(b) The matters identified in s 588FG(2) must be considered through the contemporary eyes of the parties in the commercial circumstances then prevailing and without the benefit of hindsight.[891]

(c) A person acts in good faith within the meaning of s 588FG(2)(a) if he or she acts with propriety or honesty. It is a wholly subjective test.[892]

(d) A creditor receiving payment who actually knows of the insolvent circumstances of the debtor, or who actually suspects insolvency on reasonable grounds, would not ordinarily be said to be acting in good faith. The test of good faith is not, however, confined to those matters.[893]

(e) Both limbs of s 588FG(2)(b) involve a consideration of whether there were grounds for 'suspecting' the company was or would become insolvent. The 'suspicion' is something more than a mere idle wondering whether a matter exists or not but rather a positive feeling of actual apprehension or mistrust, a 'real apprehension though with insufficient warrant for a positive conclusion'.[894]

(f) The reference to suspicion of insolvency is suspicion of actual insolvency, and not a suspicion (or even belief) the debtor might be insolvent. It is a suspicion of actual and existing insolvency as distinct from pending or potential insolvency.[895]

(g) As to s 588FG(2)(b)(i) - the person had no reasonable grounds for suspecting - (the first limb):

(i) A statutory requirement that there are 'reasonable grounds for suspecting' a particular state of mind requires the existence of facts which are sufficient to induce that state of mind in a reasonable person.[896]

(ii) Though the first limb appears to be directed to the facts and matters actually (subjectively) appreciated by 'the person', if the facts and matters appreciated by 'the person', from the range of information in 'the person's' possession, were sufficient to induce a suspicion of insolvency in the mind of a reasonable person, the first limb cannot be satisfied. Unless the relevant creditor can prove that the facts and matters appreciated by the creditor were insufficient to induce a suspicion of insolvency in the mind of a reasonable person, the defence is not made out.

(iii) There is thus an objective element involved in the application of the first limb. It is insufficient for 'the person' merely to establish, that on the facts and matters which they appreciated, they had no actual (subjective) suspicion of insolvency. It is sufficient, however, to prove that they had no reasonable grounds to suspect insolvency. If a creditor, in fact, suspects insolvency that would ordinarily provide good evidence that the creditor had reasonable grounds to suspect insolvency.

(iv) In considering what facts and matters 'the person' appreciated, regard will ordinarily be had to the training, skills and experience of 'the person' in question. For example, the matters appreciated by sophisticated creditor such as a bank with accounting and economic expertise may be different from the matters appreciated by relatively unsophisticated sole trader.[897]

(k) As to s 588FG(2)(b)(ii) - 'a reasonable person in the person's circumstances' - (the second limb), the Court adopted the following propositions drawn from the decision of the New South Wales Court of Appeal in Cussen v Commissioner of Taxation:[898]

(i) The words 'in the person's circumstances' referred to the actual circumstances as they exist at the time they entered into the relevant transaction, and denote external, objective factors or circumstances rather than factors personal to the person concerned, such as their particular perspicacity, financial acumen and the like.[899]

(ii) The reference to whether a 'reasonable person' in the person's circumstances 'would have had' reasonable grounds for suspecting the company was insolvent is a reference to the 'reasonable person's' assessment of the information, in fact, in the possession of the creditor.

(iii) Information in the possession of the creditor includes the fact (if it be the fact) of the absence of enquiries, but not information which a 'reasonable person' would theoretically have attained had enquiries been made and responded to.

(iv) The test is an objective one, and the standard of measurement is that of a hypothetical person who is assumed to have the knowledge and experience of the 'average business person'. It does not require an examination of whether the particular creditor, with their skills, training and experience acting reasonably, would have had reasonable grounds for suspecting insolvency.

(l) If the creditor receiving the impugned payment does not in fact infer insolvency or find grounds to suspect its existence and, in particular, continues to provide credit to the company, that may provide some evidence, although not determinative, of how a reasonable person in the person's circumstances would regard the matter.[900]

  1. The Court of Appeal summarised the difference between the first and second limbs of s 588FG(2)(b) as follows:[901]
Accordingly, the question raised by the first limb is whether the facts and matters actually appreciated by 'the person', ie, the particular creditor, were sufficient to induce a suspicion as to insolvency in the mind of a reasonable person. The question raised by the second limb is whether the facts and matters which would have been appreciated by a hypothetical person with the knowledge and experience of the average business person in the creditor's circumstances, were sufficient to induce a suspicion as to insolvency in such a hypothetical person. In each case, the negative must be proved by the creditor.
  1. The test in s 588FG(2)(b) is demanding because it imposes on the person who seeks the protection of s 588FG(2)(b) the burden of proving two negative propositions.[902] And, the requirement in s 588FG(2)(b)(ii) to prove that a reasonable person in the defendants' position would have no reasonable grounds to suspect insolvency is a 'fairly demanding test'.

The Financiers' contentions

  1. The Financiers contended that they did not know that Westgem was insolvent. In relation to the period between September 2009 and October 2010 they pointed to their support for Westgem in allowing drawdowns to pay Salta and soft costs 'as required' and contended that it followed from this conduct that the Financiers must have intended to support Westgem and, in effect, prevent it from becoming insolvent, and this precluded a finding that the Financiers knew Westgem was insolvent. In relation to the period between October and December 2010 the Financiers contended that the obligations assumed by Mr Saraceni and Mr Pourzand and their interests to sell assets to meet the repayments of principal due under the Restated MOFA and the Financiers' own commitment (motivated by self-interest) to support Westgem compelled the conclusion that the Financiers acted in good faith. The Financiers contended that on a proper analysis, evidence given by Mr Griffiths in the course of cross‑examination, upon which the liquidator relied as an admission by Mr Griffiths that he thought Westgem was insolvent, involved no such admission.
  2. The Financiers contended there were no reasonable grounds for them to suspect 'endemic insolvency' in circumstances where:

(a) Westgem owned a saleable asset in the form of Raine Square valued at approximately $385 million.

(b) They, and Mr Saraceni and Mr Pourzand, were offering ongoing support to Westgem, and Mr Saraceni and Mr Pourzand had substantial assets.

(c) Westgem was maintaining to Salta that it was solvent and Mr Saraceni had certified its solvency to the Financiers before a number of transactions.

(d) Westgem, Mr Saraceni and Mr Pourzand had agreed to undertake asset sales to make the principal repayments required by the Financiers.

(e) Westgem, Mr Saraceni and Mr Pourzand were undertaking refinancing negotiations.

(f) It may be inferred that Mr Saraceni and Mr Pourzand only decided to cease supporting Westgem after 13 October 2010.

  1. The Financiers contended that the liquidator had not identified any relevant difference between a reasonable person in their position and themselves and consequently they had established that a reasonable person in their position would have had no reasonable grounds for suspecting that Westgem was insolvent.

The liquidator's contentions

  1. In relation to the Financiers' state of mind at the time the 18 November Letter Agreement was entered into the liquidator relies upon the following matters to support the conclusion that the Financiers knew they were dealing with a company that could not pay its debts as and when they fell due:

(a) As early as 21 September 2009 Westgem had told the financiers it could not pay $17 million by 25 September 2009.[903]

(b) The Financiers' own review of the position of Mr Saraceni and Mr Pourzand had concluded that 'there is no evident capacity for Saraceni to contribute to further Cost Overruns on the Project based on existing cashflows and funding limits'.[904]

(c) A statement in a strategy paper dated 22 December 2009 recording:[905]

Given that the financiers ceased paying consultant's progress claims approx. three months ago a number of urgent payments totalling $356k are now well overdue to third party providers, including the Financiers QS plus legal costs associated with the response/defence of the builder's Show Caused notices etc. to this end Westgem have requested that this amount now be made available as a matter of priority.

(d) It was the Financiers' view that $17 million had been due and payable since 25 September 2009 and that they understood it had not paid because Westgem could not pay it.

  1. The liquidator contended that at the very least the Financiers suspected they were dealing with an insolvent company because 333 had been retained on 25 September 2009 to, among other tasks, 'comment on the potential insolvency risks and the implications for the Financiers'.[906]
  2. In relation to the Financiers' state of mind at the time the Fourth and Fifth Deeds of Variation were entered into the liquidator relies upon the following further matters to support the conclusion that the Financiers knew they were dealing with a company that could not pay its debts as and when they fell due:

(a) Evidence given by Mr Griffiths, which the liquidator contended, established he knew Westgem was insolvent from February 2010.[907]

(b) Evidence given by Mr Mahaffy to the effect he knew Westgem could not pay its debts as and when they fell due and the reason why the Financiers had not appointed a receiver was because the Financiers saw it advantageous not to do so and to work towards a transaction of the nature of the Restated MOFA.[908]

(c) The explanation of the Financiers' deliberations about whether to proceed in a 'solvent or insolvent environment', given by Mr Mahaffy in the credit proposal dated 27 July 2010, and in particular the comments in that proposal about 'the de-facto director risk inherent in the situation, as a result of which the Joint Financiers' tier #1 lawyers Norton Rose have been intimately involved every step of the way'.[909]

(d) The Financiers' knowledge of threats by the suppliers of cranes used on the site and the creditors who provided security to withdraw their services if not paid.[910]

Consideration

  1. The facts relevant to each element of the s 588FG(2)(b) defence will often overlap and so it is with this case.
  2. I will begin by considering the significance of the following objective facts known to the Financiers:

(a) The $17 million Cost Overrun was due and payable on 25 September 2009. Westgem was unable to pay it on that date and remained unable to pay it until the 18 November Letter Agreement was made on 1 December 2009 when an extension of time for payment was granted on a conditional basis.

(b) Westgem was unable to pay the debts due to its consultants and trade creditors as and when they fell due from at the latest 1 December 2009 until 22 September 2010.

(c) Westgem was unable to pay the balance of the second Cost Overrun, $10 million, which remained due and owing from February 2010 until the Restated MOFA was entered into.

  1. In my view the inability of Westgem to pay the second Cost Overrun when it was due and payable on 25 September 2009 was a fact that constituted a reasonable ground for suspecting that Westgem was insolvent at that time. Further, the Financiers' contemporaneous assessment that Mr Saraceni and Mr Pourzand did not then have the capacity to meet further Cost Overruns gave added significance to the inability to pay the second Cost Overrun as a reasonable ground for suspecting insolvency. Accordingly, a reasonable person in the Financiers' circumstances on 25 September 2009, and with their knowledge of the facts referred to in this paragraph, would have had reasonable grounds for suspecting Westgem was insolvent. I do not accept this conclusion is undermined by the notion that Westgem had the benefit of support from the Financiers. There was no express or implied agreement or understanding that the second Cost Overrun debt was not due and payable and, as explained earlier, the Financiers' reticence to appoint a receiver in September and October 2009 did not reflect a concern to support Westgem but a concern to keep Salta on site.
  2. From December 2009 onwards Westgem's inability to pay its trade creditors the debts due to them as they became due, coupled, from 28 February 2010 onwards, with the inability of Westgem to meet its liability to pay the $10 million balance of the Cost Overrun were facts which constituted reasonable grounds to suspect actual insolvency and a reasonable person in the Financiers' circumstances and with the Financiers' knowledge, would have had reasonable grounds to suspect insolvency.
  3. Mr Griffiths and Mr Mahaffy were cross-examined about the significance of the matters to which I have referred.
  4. Before setting out the relevant passages of Mr Griffiths' evidence it is to be remembered that on 22 October 2009 he wrote in an email to colleagues (from which I have quoted in an earlier section of this part of the judgment) that: '... we should be prepared for an insolvency appointment but would not rush into this until it suits us'. Mr Griffiths was a very experienced and senior banker. It is most unlikely that he would have referred to an 'insolvency appointment' had he not been of the view that Westgem was insolvent.
  5. Mr Griffiths was cross‑examined about Westgem's inability to pay its debts to the Financiers as follows:[911]
And you knew throughout the whole of 2009 up to the moment the restated MOFA was signed that Westgem could not pay its debts as and when they fell due; correct?---In respect of debts other than the bank debt, I don't know.

No. I accept that. I’m just focusing what - you knew it couldn't pay the bank debt as and when it fell due?---It couldn’t, and the bank was entering - or waiting for proposals to vary that amount.

Yes. So it couldn't pay its debt to the bank as and when it fell due; correct?---If it was due every day, yes, that's correct.

You know it was due every day, don't you? That was your position, wasn't it?---In a legal perspective, yes. We were waiting for proposals from the borrower to regularise the position.

You had written - or the bank had written two, three, four - a number of letters making it as clear as it possibly could that the bank considered that that money was due and owing and was positively not waiving any right that it had to be paid that money immediately; correct?---Correct.

And when the bank sent those letters, they were meant to convey what they meant; correct?---Correct.

And they did represent the legal position as between the bank and Westgem concerning that debt; correct?---Correct.

And you've already agreed that there was no oral, written or implied understanding that you were aware of between the bank and Westgem to, in some way, defer payment of that money; correct?---Correct, other than we were waiting for proposals to regularise the amount owing.

So much may be accepted, but the bank's formal position and informal position was that money was owing; correct?---Yes.
  1. In the context of the Financiers' concern to obtain further security for Westgem's indebtedness, Mr Griffiths gave the following evidence:[912]
So you had to be very careful in your negotiations with the sponsors not to push them too hard because there was always the risk that they might just give back the keys; correct? That is what you are saying here?---That is correct, yes.

And so you say, well, that is the alternative so let us try and get this extra $150 million worth of security; right?---Yes.

And you are doing this in relation to a transaction that will involve Westgem, a company which you understood at the time was insolvent; correct?---Going back to your earlier argument, yes.

...

In other words, if the bank just blunders in and puts a receiver in, that is the end of any prospect of getting further security; correct?---Correct.

So you, doing your job properly, were trying to bolster the bank's commercial position as best you could; correct?---Correct.

Knowing that you were dealing with an insolvent entity; correct?---Correct.
  1. Mr Griffiths was cross-examined about an email sent by him in February 2010 in which he wrote:
I continue to favour keeping this out of insolvency if we can continue to exert sufficient control over the whole project without becoming shadow directors.
  1. The cross-examination went as follows:[913]
Do you see that?---Yes.

Now, of course, shadow directors is one of the things that you knew at the time was a risk for a bank in dealing with a company that either was or it seemed to be insolvent; correct?---Correct.

You had to be very careful to not assume too much control because later on, a liquidator might rightly or wrongly accuse the bank of being liable for insolvent trading; correct?---Correct.

And so when you said in that recommendation you wanted to keep this out of insolvency, what you meant was you wanted to keep it out of a formal insolvency-type appointment; correct?---Correct.
  1. The Financiers submitted that Mr Griffiths' evidence should:[914]
... be understood as being qualified. Griffiths effectively accepted that Westgem may have been insolvent if the Project was not further funded by the Banks, but there was nothing which he said which indicated that he accepted that Westgem would continue to be insolvent if the Financiers provided further funding'. (emphasis supplied)
  1. I do not accept that Mr Griffiths' evidence should be understood in this way. The qualification identified in the submission did not emerge from Mr Griffiths' evidence itself and the submission appears to be a bold attempt at rationalising evidence thought to be unfavourable. When I have regard to the references made by Mr Griffiths to insolvency in his emails in October 2009 and February 2010, and his evidence in cross‑examination, I have no hesitation in concluding that he thought Westgem was insolvent from September 2009 but considered it was not in the Financiers' interests to make 'an insolvency appointment'. I do not accept Mr Griffiths thought that Westgem was not insolvent because it had the benefit of support from the Financiers. At the very least, Mr Griffiths suspected that Westgem was insolvent and he had reasonable grounds for so suspecting, those grounds being Westgem's failure to pay debts due to the Financiers as and when they fell due.
  2. Mr Mahaffy was also cross-examined about whether he considered that Westgem was insolvent. He was asked about Westgem's failure to pay the second Cost Overrun and gave the following evidence:[915]
And your understanding was that the reason Westgem was not paying it, was because Westgem, with the help of its sponsors, simply was not able to get that cash together so as to discharge that debt?---Not able to contribute cash. Yes, that is correct.

And, therefore, you knew that Westgem was insolvent?---No.

All right. Well, you knew it could not pay that debt as and when it fell due; correct?---That is correct. However, the banks did not insist that that money be paid. If the banks had insisted, Westgem would become insolvent according to the definition you put to me earlier because a controller would have been appointed by the banks. The banks would have acted on their rights. The fact is the banks did not do that.
  1. At a later stage of his cross-examination, Mr Mahaffy was asked about Westgem's inability to pay the $10 million balance of the second Cost Overrun. The cross-examination went as follows:[916]
There was no arrangement in place between the bank and Westgem for deferral of obligation to pay that money, as far as you knew?---That is correct. The banks agreed to forbear.

The banks did not agree to forbear?---Well, they did not - sorry, they did not act on their rights, as they could have, sooner.

There was no arrangement in place, so far as you knew, whereby the banks had agreed expressly or impliedly that they would - that the did not expect that money to be paid; correct?---Correct.

It was legally due and payable?---Correct.

And it had been due and payable every single day since the end of February?---Correct.

...

And so let there be no doubt about it: you understood at the time that the financiers, the banks, were not supporting Westgem to assist it to pay that debt; correct?---Not in the sense that you have described, no. We - the banks - - -

What sense were they?---The banks did not formally, what I would describe as regularise the position by formally increasing the facility. They did, however, refrain from appointing a controller acting on the basis of the one or more defaults which had occurred to that point. That is a form of support.

But that does not stop the money being due and payable, does it?---No, it does not.

No. And they were not - and then they were the soft costs. The banks were not supporting Westgem so as to allow it to pay its consultants bills as and when they fell due; correct?---Not as a matter of course, no.

No. And you knew, because Westgem was telling you, that Westgem did not have the cash from other sources to pay those consultants; correct?---That is true.

Right. So you knew you were dealing with an insolvent company?---You keep putting that to me.

I do?---And I can only respond in the way to which I have responded to date which was that the banks did not seek to appoint a receiver Westgem at that time.
  1. Mr Mahaffy was cross-examined about the potential effect of a supervening insolvency regime on the Financiers' desire to obtain further security as part of the negotiations for the Restated MOFA. The cross‑examination went as follows:[917]
So the bank, to your knowledge, was deliberately not taking steps to appoint a formal insolvency regime because the bank wanted to improve its position; correct?---I know you want me to answer yes or no to that proposition.

Well, I do?---And I will answer by saying that the opportunity to improve the position was certainly part of the equation. There is no doubt. It was certainly part of the equation. It was not, however, the whole story.

Well, the bank also wanted to improve its position because it wanted to get the building work back up and running, all of which might have been delayed by the formal appointment of some insolvency person?‑‑‑Delayed ‑ yes, there would have been some delay, had a controller been appointed. That might or might not have been made up. The real issue, in my mind, regarding the appointment of a controller was the additional, very substantial cost that would entail.

...

But the fact is you knew you were dealing with a company that could not pay its debts as and when they fell due. The reason you were not making formal appointments is because you saw it advantageous to the bank's position to not do that and to work towards something like the restated MOFA?---Correct.
  1. In his evidence about insolvency Mr Mahaffy attached some importance to the fact the Financiers did not appoint 'a controller' but it was clear that he was of the view that the Financiers could have made such an appointment, if they had chosen to do so. The fact that Mr Mahaffy considered the Financiers could have brought about a 'formal insolvency regime' is powerful evidence that Mr Mahaffy knew Westgem was insolvent or, at the least, that he had reasonable grounds (in his case the knowledge that Westgem could neither pay the Financiers the debt due to them nor pay soft costs as and when they fell due) for suspecting Westgem was insolvent.
  2. In addition, I infer Mr Nathan's reference to a 'warm body approach' being more beneficial to the Financiers (in his email to Mr Nagle of 5 May 2010)[918] was a metaphor for keeping Westgem out of insolvent administration and reflected an appreciation on his part that Westgem was insolvent, or at least, that there were reasonable grounds to suspect that Westgem was insolvent.
  3. The views I have expressed in the preceding paragraphs mean that had it been necessary for the Financiers to rely on the s 588FG(2) defence they would not have been able to establish it.
PART 9 - Seaport Guarantor proceedings Introduction
  1. Bankwest has separate claims in CIV 1596, 1651 and 1652 of 2011 in respect of guarantees given to Bankwest by three defendants, Mr Saraceni (CIV 1596), Tokyo City Pty Ltd as trustee for The Tokyo City Trust (CIV 1651) and LMS Holdings Pty Ltd as trustee for the Saraceni Family Trust (CIV 1652). These actions were commenced before the damages action was commenced.
  2. The guarantees were given in August 2006 and guaranteed payment by Seaport Pty Ltd (Seaport) of amounts owing to Bankwest under certain finance facilities relating to the acquisition and development of properties in Warrnambool, Victoria (the Seaport Facilities).
  3. The facts relevant to the claims in each of these proceedings are generally agreed and were the subject of an agreed statement of facts.[919] I set out the agreed facts later in this part of the judgment. For introductory purposes the following summary will suffice.
  4. Seaport was a guarantor and security provider under the terms of the MOFA.
  5. On 6 January 2011 demand was made of Seaport and the other guarantors of Westgem by the Security Trustee to pay the sum of $332,274,512.58 being the amount owed by Westgem to the Security Trustee under the MOFA by 10 January 2011. Neither Seaport nor the other guarantors of Westgem paid that amount or any part of it.
  6. On 14 January 2011 Bankwest issued a notice of default and demand to Seaport demanding that it pay the sum of $15,002,432.39, being the amount owed under the Seaport Facilities by 18 January 2011. Seaport failed to pay that amount or any part of it.
  7. Following further demands the payment, and non‑payment by Seaport, Bankwest appointed receivers to Seaport on 20 January 2011. The receivers were subsequently appointed as receivers and managers of the Warrnambool mortgaged property on 28 March 2011.
  8. On 18 January 2011 Bankwest demanded that the guarantors pay the amount of $15,002,432.39, being the amount due and payable by them under their respective guarantees in relation to the Seaport Facilities as at 14 January 2011. The guarantors failed to pay that amount or any part of it.
  9. Bankwest claims the amount owing under the guarantee together with interest is due and payable by each of the guarantors. There is an alternative claim on the basis that Seaport was liable to repay Bankwest all amounts outstanding on the expiry of the Seaport Facilities, namely 31 January 2011 and it did not do so. Demand was also made of the guarantors on 3 May 2011 the amount owing as at the date of $15,372,252.10. That amount has not been paid.
  10. Seaport is a plaintiff in the damages action and it claims that it is entitled to set off any amount held in those proceedings to be owed to it by Bankwest against any amount it owes to Bankwest under the Seaport Facilities.
  11. The guarantors are also plaintiffs in the damages action and rely on the defence and counterclaim in those proceedings and also claim they are entitled to set of any amounts held to be owed by them in the damages action against any amount they owe to Bankwest as guarantors of the Seaport Facilities.
Factual findings
  1. I will make findings in accordance with the statement of agreed facts as set out in the following paragraphs (the facts are reproduced substantially in the form agreed by the parties even though this involves some repetition of findings set out earlier).
Statement of Agreed facts Guarantees provided by Luke Saraceni, Tokyo City and LMS Holdings
  1. On or about 17 August 2006, Luke Saraceni, Tokyo City and LMS Holdings each executed a guarantee and indemnity under which each guaranteed to Bankwest the payment by Seaport of certain amounts owing to Bankwest (Seaport Guarantees).[920]
  2. The Seaport Guarantees are unsecured.
Guarantee provided by Newport
  1. On or about 17 August 2006, Newport Securities Pty Ltd (Newport) executed a guarantee and indemnity under which Newport guaranteed to Bankwest the payment by Seaport of certain amounts owing to Bankwest (Newport Guarantee).[921]
Seaport Facility Agreement
  1. On or about 12 October 2006, Bankwest entered into a written agreement (Seaport Facility Agreement) with Seaport as trustee for the Seaport Trust as borrower, and Luke Saraceni, Newport as trustee for the Newport Family Trust, LMS Holdings as trustee for the Saraceni Family Trust and Tokyo City as trustee for the Tokyo City Trust as guarantors (together Seaport Guarantors and each a Seaport Guarantor).
  2. Pursuant to the Facility Agreement, Bankwest agreed to provide to Seaport financial accommodation, namely, a land acquisition facility, a development facility and an overdraft facility (together Seaport Facilities).[922]
  3. The Seaport Facility Agreement was varied by written agreement between Bankwest, Seaport, Luke Saraceni, Newport, LMS Holdings and Tokyo City on the following occasions:

(a) on or about 5 June 2008, pursuant to a letter of 5 June 2008 from Bankwest to Seaport;[923]

(b) in or about September 2008, pursuant to a letter of 5 September 2008 from Bankwest to Seaport;[924]

(c) on or about 20 January 2009, pursuant to a letter of 16 January 2009 from Bankwest to Seaport;[925]

(d) on or about 23 January 2009, pursuant to a letter of 24 November 2008 from Bankwest to Seaport;[926]

(e) on or about 30 March 2009, pursuant to a letter of 16 March 2009 from Bankwest to Seaport;[927]

(f) in or about April 2010, pursuant to a letter of 1 April 2010 from Bankwest to Seaport;[928]

(g) on or about 6 May 2010, pursuant to a letter of 30 April 2010 from Bankwest to Seaport;[929]

(h) on or about 25 June 2010, pursuant to a letter of 22 June 2010 from Bankwest to Seaport;[930]

(i) on or about 30 August 2010, pursuant to a letter of 27 August 2010 from Bankwest to Seaport; and[931]

(j) on or about 22 October 2010, pursuant to a letter of 19 October 2010 from Bankwest to Seaport.[932]

  1. Each of the letters referred to in (a) - (j) above were executed by Luke Saraceni, LMS Holdings, Tokyo City and Newport as guarantors.
  2. The terms and conditions that applied to the Seaport Facility Agreement (as varied) are to the effect contained in Bankwest's General Terms for Business Lending (March 2006) (2006 General Terms).[933]
Security provided by Seaport
  1. The Seaport Facilities were secured by the following securities granted by Seaport:

(a) a limited fixed and floating charge dated on or about 17 August 2006 registered with ASIC as charge number 1340685 limited to the 'Secured Property' and 'Fixed Charge Property' to the extent that property is located at or directly relevant to the 'Project', being in relation to the property known as 221-223 Timor Street, Warrnambool (Warrnambool Properties) (Seaport Charge);[934]

(b) a mortgage dated on or about 17 August 2006, in relation to the Warrnambool Properties (Seaport Mortgage 1); and[935]

(c) a mortgage dated on or about 20 November 2006, in relation to the property contained in certificate of title volume 10411 folio 949 known as Unit 5, 36 Fairy Street, Warrnambool (Seaport Mortgage 2).[936]

  1. In April 2009, the properties the subject of the five certificates of title listed in (h), (i), (j), (k) and (l) under the definition of 'Project' in the Seaport Charge were sold by Seaport.
Multi Option Facility Agreement
  1. On 23 April 2008, Westgem, Bankwest, BOSI, the Security Trustee and others entered into the MOFA.
  2. The MOFA was amended, restated or varied from time to time, including by the Deed of Amendment and Restatement dated 22 September 2010.[937]
Seaport Guarantees
  1. On or about 23 April 2008, Security Trustee, Seaport and others entered into a deed of guarantee and indemnity under which Seaport (with other guarantors) guaranteed to the Security Trustee the payment by Westgem of certain amounts owing to Bankwest and BOSI.[938]
  2. On or about 28 January 2010, Seaport and Queen Street Properties Pty Ltd (together the Seaport Mortgagors) granted a mortgage in favour of the Security Trustee (January 2010 Mortgage).[939]
  3. Seaport entered into the January 2010 Mortgage in its capacity as trustee of the Seaport Trust and Queen Street Properties Pty Ltd entered into the January 2010 Mortgage in its capacity as trustee of the Queen Street Properties Trust.[940]
  4. By cl 1.5 of the January 2010 Mortgage, the parties each acknowledged and agreed that the Seaport Mortgagors entered into the January 2010 Mortgage and was bound in its own right and as trustee for the Sherin Trust.[941]
  5. Pursuant to cl 1.5 of the January 2010 Mortgage, Seaport and Queen Street Properties Pty Ltd guaranteed to the Security Trustee the payment by Westgem of certain amounts owing to Bankwest and BOSI (January 2010 Seaport Guarantee).[942]
  6. On or about 22 September 2010, the Security Trustee, Seaport and others entered into a deed of guarantee and indemnity under which Seaport (with other guarantors) guaranteed to the Security Trustee the payment by Westgem of certain amounts owing to Bankwest and BOSI (September 2010 Seaport Guarantee).[943]
Default by Westgem
  1. By letter dated 31 December 2010, the Security Trustee on behalf of the Financiers:[944]

(a) gave notice to Westgem and declared that all of the 'Secured Money' under the MOFA (which was stated in the letter to be as at the date of the letter $332,274,512.58) was immediately due and payable, but without limiting any of the Finance Parties' rights and entitlements arising out of or in connection with (and without prejudice to) that declaration, the Financiers agreed to allow Westgem until 10 January 2011 to repay all of the 'Secured Money'; and

(b) gave notice to Westgem that the 'Default Rate' would otherwise apply to the 'Secured Money' at all times after the date of the letter.

  1. Westgem did not pay that amount (or any amount) by 10 January 2011.
Seaport
  1. By letter dated 5 January 2011, the Security Trustee demanded that Seaport pay the whole of $332,274,512.58, which was the amount stated to be owed by Westgem to the Security Trustee under the MOFA, under the 2008 Seaport Guarantee, the January 2010 Seaport Guarantee and the September 2010 Seaport Guarantee.[945]
  2. On 6 January 2011, the Security Trustee demanded that Seaport pay the whole of $332,274,512.58, which was the amount stated to be owed by Westgem to the Security Trustee under the MOFA by no later than 10 January 2011.
  3. This demand was made pursuant to the following mortgages:

(a) a real property mortgage dated on or about 28 January 2010 in respect of certificate of title volume 1805 folio 731 granted by Seaport and Queen Street Properties Pty Ltd ACN 076 299 477 as trustee for the Queen Street Properties Trust;[946]

(b) a real property mortgage dated on or about 22 September 2010 in respect of certificate of title volume 1805 folio 731 granted by Seaport and Queen Street Properties Pty Ltd ACN 076 299 477 as trustee for the Queen Street Properties Trust; and[947]

(c) a real property mortgage dated on or about 22 September 2010 in respect of certificate of title volume 2709 folio 787 granted by Seaport.[948]

  1. Seaport failed to make payment of any part of the $332,274,512.58 demanded on or before 10 January 2011.
Newport
  1. By letters dated 5 January 2011, the Security Trustee demanded that Newport (as trustee for the Pakwest Trust, and separately, as trustee for the Newport Family Trust) pay the whole of $332,274,512.58, which was the amount stated to be owed by Westgem to the Security Trustee under the MOFA, by no later than 10 January 2011.[949]
  2. These demands were made pursuant to the following instruments:

(a) Deed of Guarantee and Indemnity dated 23 April 2008 between the Security Trustee and, among others, Seaport, Newport as trustee for the Pakwest Trust as guarantors and several other guarantors;[950]

(b) Deed of Guarantee and Indemnity - unlimited dated 22 September 2010 between the Security Trustee, Seaport, Newport as trustee for the Pakwest Trust as guarantors and several other guarantors;[951]

(c) Deed of Guarantee and Indemnity - limited dated 22 September 2010 between the Security Trustee, Newport as trustee for the Newport Family Trust as guarantor and several other guarantors; and[952]

(d) the guarantee set out at clause 15 of the real property mortgage dated on or about 28 January 2010 in respect of certificate of title volume 2069 folio 895 granted by Newport in favour of the Security Trustee.[953]

  1. By letter dated 6 January 2011, the Security Trustee demanded that Newport pay the whole of $332,274,512.58, which was the amount stated to be owed by Westgem to the Security Trustee under the MOFA, by no later than 10 January 2011.[954]
  2. This demand was pursuant to the following mortgages:

(a) a real property mortgage dated on or about 28 January 2010 in respect of certificate of title volume 2069 folio 895 granted by Newport in favour of BOSI; and[955]

(b) a real property mortgage dated on or about 22 September 2010 in respect of certificate of title volume 2069 folio 895 granted by Newport in favour of BOSI.[956]

  1. Newport failed to make payment of any part of the $332,274,512.58 demanded on or before 10 January 2011.
Luke Saraceni
  1. By letter dated 5 January 2011, the Security Trustee demanded that Luke Saraceni pay the whole of $332,274,512.58, which was the amount stated to be owed by Westgem to the Security Trustee under the MOFA, by no later than 10 January 2011.[957]
  2. This demand was made pursuant to the following guarantees:

(a) a Guarantee and Indemnity dated 23 April 2008 granted by Luke Saraceni as guarantor in favour of the Security Trustee; and[958]

(b) a Guarantee and Indemnity dated 22 September 2010 granted by Luke Saraceni as guarantor in favour of the Security Trustee.[959]

  1. By letter dated 6 January 2011, the Security Trustee demanded that Luke Saraceni pay the whole of $332,274,512.58 by no later than 10 January 2011.[960]
  2. This demand was made pursuant to the following mortgages:

(a) an equitable mortgage over shares dated 23 April 2008 granted by Luke Saraceni and Mr Hossean Pourzand over all of their shareholding in the Borrower in favour of BOSI; and[961]

(b) an equitable mortgage over shares dated 22 September 2010 granted by Luke Saraceni over all of his shareholding in Seaport in favour of BOSI.[962]

  1. Luke Saraceni failed to make payment of any part of the $332,274,512.58 demanded on or before 10 January 2011.
Demands under the Seaport Facility Agreement, Seaport Charge and Seaport Mortgage 2

Seaport Facility Demand

  1. On or about 14 January 2011, Bankwest issued a notice of default and demand to Seaport (copied to Luke Saraceni, LMS Holdings and Tokyo City as guarantors) by which Bankwest demanded that Seaport pay the amount of $15,002,432.39 by 18 January 2011 (Seaport Facility Demand).[963]
  2. Seaport failed to make the $15,002,432.39 payment in part or in full by 18 January 2011, or at all.

Seaport Charge Demand

  1. On or about 18 January 2011, Bankwest issued a notice of demand to Seaport by which Bankwest demanded that Seaport pay the amount of $15,002,432.39 by 19 January 2011(Seaport Charge Demand).[964]
  2. Seaport failed to make the $15,002,432.39 payment in part or in full by 19 January 2011, or at all.

Appointment of Receivers

  1. On 20 January 2011, Bankwest appointed Martin Jones and John Lindholm (Receivers) as joint and several receivers and managers of the assets and undertakings the subject of the Seaport Charge.[965]

Seaport Mortgage 2 Demand

  1. On or about 24 March 2011, Bankwest issued a notice of default and demand to Seaport by which Bankwest demanded that Seaport pay the amount of $15,283,574.52 by 25 March 2011 (Seaport Mortgage 2 Demand).[966]
  2. Seaport failed to make the $15,283,574.52 payment in part or in full by 25 March 2011, or at all.
  3. On 28 March 2011, Bankwest appointed the Receivers as joint and several receivers and managers of the property known as Unit 5, 36 Fairy Street, Warrnambool, being the property the subject of the Seaport Mortgage 2.[967]
  4. In 2012, the Receivers completed a sale of the remaining properties the subject of the Seaport Charge, Seaport Mortgage 1 and Seaport Mortgage 2 (Seaport Securities Sale).
  5. The net proceeds of the Seaport Securities Sale were less than the aggregate of the amount advanced plus interest accrued under the Seaport Facility Agreement as varied from time to time less all payments made by Seaport and the guarantors under the Seaport Facility Agreement as varied from time to time.

Expiry of the Seaport Facility Agreement

  1. The Seaport Facility Agreement expired on 31 January 2011.[968]
  2. Seaport failed to make the $14,949,900.21 payment in part or in full on or before 31 January 2011, or at all.
Section 76 Demand
  1. On 21 December 2011, Bankwest issued a notice of demand under section 76 of the Transfer of Land Act 1958 (Vic) to Seaport (copied to Luke Saraceni, LMS Holdings and Tokyo City as guarantors).[969]
  2. Seaport did not pay Bankwest any amounts in response to the demand.
  3. On 29 May 2012, Bankwest issued a notice of demand to Seaport (copied to Luke Saraceni, LMS Holding and Tokyo City as guarantors) under the Seaport Facility Agreement in which Bankwest demanded payment of the shortfall then owing under the Facility Agreement, which was stated to be $10,539,568.[970]
  4. Seaport, nor any other third party, paid to Bankwest the amount stated in the above demand by the date stated in the demand, or at all.
Demands made of Luke Saraceni, LMS Holdings and Tokyo City

First Demand

  1. On or about 18 January 2011, Bankwest issued notices of demand to each of Luke Saraceni, LMS Holdings and Tokyo City under the Seaport Guarantees by which Bankwest demanded that each of Luke Saraceni, LMS Holdings and Tokyo City pay the amount of $15,002,432.39 by 19 January 2011 (First Guarantor Demand).[971]
  2. Luke Saraceni, LMS Holdings or Tokyo City did not make the $15,002,432.39 payment in part or in full by 19 January 2011, or at all.

Second Demand

  1. On or about 3 May 2011, Bankwest issued notices of demand to each of Luke Saraceni, LMS Holdings and Tokyo City under the Seaport Guarantees by which Bankwest demanded that each of Luke Saraceni, LMS Holdings and Tokyo City pay the amount of $15,372,252.10 by 5 May 2011 (Second Guarantor Demand).[972]
  2. Luke Saraceni, LMS Holdings or Tokyo City did not make the $15,372,252.10 payment in part or in full by 5 May 2011, or at all.
Conclusion
  1. Both sides of this dispute agreed that the fate of the claims in these actions depended on the outcome of the damages action. The outcome of the damages action is adverse to Seaport and Mr Saraceni, Tokyo City Pty Ltd and LMS Holdings Pty Ltd and accordingly Bankwest is entitled to succeed in its claims. There are, however, issues bearing on the quantum of the claims that remain to be determined as part of the quantum trial.

PART 10 - Summary and next steps
  1. Westgem's damages claims and the related claims made by the MOFA Guarantors, the First Additional Security providers and the Restated MOFA Guarantors have failed.
  2. The MOFA Share Mortgage will be rectified as sought by Mr Saraceni and Mr Pourzand and ultimately not opposed by the Financiers. I will hear the parties as to directions to be made for the determination of the Second Additional Securities rectification claim.
  3. The Financiers succeed on their money claim counterclaims but not on the Vasse Newtown counterclaim. I will hear the parties as to the directions to be made for the determination of the quantum issues and the remaining issue concerning Default Interest. In the context of the Vasse Newtown counterclaim, the Financiers have established misleading conduct, in breach of the statutory provisions and the Restated MOFA warranties and the Seaport Share Mortgage warranties but have not established loss of the nature claimed by them. I will hear from the parties in relation to the orders to be made consequent upon these findings.
  4. The liquidator's voidable transactions claims fail.
  5. Bankwest has established liability in the Seaport Guarantee proceedings and I will hear the parties as to the directions to be made for the determination of the quantum issues.
  6. I will hear the parties as to the orders for costs to be made on the issues determined thus far.

APPENDIX 1
_________________________________________________________________________




Table A: Security Providers and Guarantors under the Multi-Option Facility Agreement


Provider
Description / Document Reference
MOFA Securities
Westgem Investments Pty Ltd
Mortgage of the Raine Square Land.
RSQ.006.0001.0208
A fixed and floating charge registered as charge 1629143.
RSQ.006.0001.0242
Luke Saraceni
Mortgage over his shares in Westgem and any associated rights.
RSQ.006.0001.0399
Hossean Pourzand
Mortgage over his shares in Westgem and any associated rights.
RSQ.006.0001.0399
MOFA Guarantors
Pakwest Pty Ltd
Joint and several guarantee and indemnity as trustee for Newport Securities Pty Ltd ACN 050 217 439 as trustee for the Pakwest Trust.
RSQ.006.0001.0300
As trustee for:
(a) Newport Securities Pty Ltd ACN 050 217 439 as trustee for the Pakwest Trust; and
(b) Oakcure Pty Ltd ACN 075 388 564 as trustee for the Parry Trust
RSQ.006.0001.0370
Newport Securities Pty Ltd
Joint and several guarantee and indemnity as trustee for the Pakwest Trust.
RSQ.006.0001.0300
Oakcure Pty Ltd
Joint and several guarantee and indemnity as trustee for the Parry Trust.
RSQ.006.0001.0300
Seaport Pty Ltd
Joint and several guarantee and indemnity as trustee for the Seaport trust.
RSQ.006.0001.0300
Luke Saraceni
Guarantee and indemnity in his personal capacity.
RSQ.006.0001.0331
Hossean Pourzand
Guarantee and indemnity in his personal capacity.
RSQ.006.0001.0349
Hossean Pourzand and Jenny Maria Pourzand
Joint and several guarantee and indemnity as Trustees for the Helen Trust.
RSQ.006.0001.0349
St George Bank
Bank guarantee in favour of the Security Trustee. Replaced on or about 7 October 2008 with a guarantee of that date in the amount of $1,600,000 provided by Pourzand and Mrs Pourzand as trustee for the Pourzand Family Trust, and later assigned to the Security Trustee.
RSQ.007.0072.0001; RSQ.006.0001.0542




Table B: First Additional Securities


Provider
Description / Document Reference
First Additional Securities
Seaport and Queen Street Properties
Second mortgage of Myer Fremantle registered as dealing L231313.
BOS.014.001.0109; RSQ.007.0086.0001
Newport Pty Ltd
Second mortgage L218363 of Saracen Estate 884 Caves Road, subsequent to mortgage I334923 in favour of Bankwest.
BOS.014.001.0109; RSQ.007.0082.0001
Mayport Pty Ltd
Second mortgage L218396 of 218 Rockingham Road, being subsequent to mortgage I015622 in favour of Bankwest.
BOS.014.001.0109; RSQ.007.0084.0001
Pakwest Pty Ltd
Second mortgage L218382 of 18 The Esplanade, being subsequent to mortgage K293816 in favour of CBA.
BOS.014.001.0109; RSQ.007.0083.0001
Unregistered mortgage of Tyne Square.
BOS.014.001.0109; RSQ.007.0093.0001
Hossean Pourzand and Mrs Pourzand
Second mortgage L221602 of 251 St Georges Terrace, being subsequent to mortgage J526332 in favour of CBA.
BOS.014.001.0109; RSQ.007.0085.0001




Table C: Security providers and guarantors under the Restated MOFA


Provider
Description / Document Reference
Second Additional Securities
Westgem Investments Pty Ltd
Restated MOFA mortgage of the Raine Square Land
Seaport Pty Ltd as trustee for the Seaport Trust and Queen Street as trustee for the Queen Street Properties Trust
Second mortgage Myer Fremantle Mortgage.
RSQ.006.0002.0535
Seaport Pty Ltd as trustee for the Seaport Trust
Second mortgage Lot 1001 Paris road, Australind.
RSQ.007.0088.0001
Newport Securities Pty Ltd as trustee for the Newport Family Trust
Second mortgage Saracen Estate 884 Caves Road Mortgage.
RSQ.006.0002.0605
Charge by Newport as trustee for the Newport Family Trust over all of its units in the Tuart Investments Unit Trust.
RSQ.006.0002.0393
Mayport Nominees Pty Ltd as trustee for the Mayport Unit Trust
Second mortgage 218 Rockingham Mortgage.
RSQ.006.0002.0569
Pakwest Pty Ltd as trustee for:
(a) Westview Asset Pty Ltd as trustee for the Westview Trust; and
(b) Oakcure Pty Ltd as trustee for the Zahra No.2 Trust
Second mortgage 18 The Esplanade Mortgage.
RSQ.006.0002.0499
Pakwest Pty Ltd as trustee for:
(a) Cityscape Investments Pty Ltd as trustee for the Faramaz Trust; and
(b) Rangeway Investments Pty Ltd as trustee of the Rangeway Investments Trust
Second mortgage 500 & 502 Hay Street Mortgage.
RSQ.006.0002.0639
Hossean Pourzand and Jenny Maria Pourzand as trustees for the Sherin Trust
Second mortgage 251 St Georges Tce Mortgage.
RSQ.006.0002.0463
Grand Edition Pty Ltd as trustee for the Farah Investment Trust No. 4
Second mortgage 1 Keane Road, Forrestdale Mortgage.
RSQ.007.0087.0001
Luke Saraceni
Mortgage over all his shareholding in Seaport Pty Ltd.
RSQ.006.0002.0351
Restated MOFA Guarantors
Pakwest Pty Ltd
As trustee for Newport Securities Pty Ltd ACN 050 217 439 as trustee for the Pakwest Trust.
Restated MOFA Unlimited Guarantee in favour of the Security Trustee.
RSQ.006.0002.0239
As trustee for:
(a) Newport Securities Pty Ltd ACN 050 217 439 as trustee for the Pakwest Trust; and
(b) Oakcure Pty Ltd ACN 075 388 564 as trustee for the Parry Trust
Restated MOFA Unlimited Guarantee in favour of the Security Trustee.
RSQ.006.0002.0239
As trustee for:
(a) Westview Asset Pty Ltd ACN 119 774 266 as trustee for the Westview Trust; and
(b) Oakcure Pty Ltd ACN 075 388 564 as trustee for the Zahra No.2 Trust
Restated MOFA Limited Guarantee in favour of the Security Trustee, limited to the amount the Security Trustee can obtain from enforcing its rights in connection with the Security Documents granted by that Guarantor.
RSQ.006.0002.0269
As trustee for:
(a) Cityscape Investments Pty Ltd ACN 143 905 l3las trustee for the Faramaz Trust; and
(b) Rangeway Investments Pty Ltd ACN 1 11 258 087 as trustee of the Rangeway Investments Trust
Restated MOFA Limited Guarantee in favour of the Security Trustee, limited to the amount the Security Trustee can obtain from enforcing its rights in connection with the Security Documents granted by that Guarantor.
RSQ.006.0002.0269
Oakcure Pty Ltd
As trustee for the Parry Trust.
Restated MOFA Unlimited Guarantee in favour of the Security Trustee.
RSQ.006.0002.0239
Seaport Pty Ltd
As trustee for the Seaport trust.
Restated MOFA Unlimited Guarantee in favour of the Security Trustee.
RSQ.006.0002.0239
Luke Saraceni
Guarantee and indemnity in his personal capacity.
RSQ.006.0002.0303
Hossean Pourzand
Guarantee and indemnity in his personal capacity.
RSQ.006.0002.0319
Hossean Pourzand and Jenny Maria Pourzand
As trustees for the Helen Trust.
RSQ.006.0002.0319
As trustees for the Sherin Trust
Second Restated MOFA guarantee in favour of the Security Trustee
RSQ.006.0002.0335
Mayport Nominees Pty Ltd
As trustee for the Mayport Unit Trust.
Restated MOFA Limited Guarantee in favour of the Security Trustee, limited to the amount the Security Trustee can obtain from enforcing its rights in connection with the Security Documents granted by that Guarantor.
RSQ.006.0002.0269
Newport Securities Pty Ltd
As trustee for the Newport Family Trust.
Restated MOFA Limited Guarantee in favour of the Security Trustee, limited to the amount the Security Trustee can obtain from enforcing its rights in connection with the Security Documents granted by that Guarantor.
RSQ.006.0002.0269
As trustee for the Pakwest Trust.
Restated MOFA Unlimited Guarantee in favour of the Security Trustee.
RSQ.006.0002.0239
Queen Street Properties Pty Ltd
As trustee for the Queen Street Properties Unit Trust.
Restated MOFA Limited Guarantee in favour of the Security Trustee, limited to the amount the Security Trustee can obtain from enforcing its rights in connection with the Security Documents granted by that Guarantor.
RSQ.006.0002.0269
Grand Edition Pty Ltd
As trustee of the Farah Investment Trust No. 4.
Restated MOFA Limited Guarantee in favour of the Security Trustee, limited to the amount the Security Trustee can obtain from enforcing its rights in connection with the Security Documents granted by that Guarantor.
RSQ.006.0002.0269








Table D: Parties - CIV 2722 of 2012

Party
Involvement
Relief Sought
Westgem Investments Pty Ltd
(First plaintiff)
Developer
Damages
Orders:
  1. declaring the 18 November 2009 Letter Agreement and AFL Supplementary Agreement to be void ab initio;
  2. Order declaring each of the Restated MOFA, Second Additional Securities (and Second DCA) and 13 October 2010 Letter Agreement, Amended AFL Supplementary Agreement and AFL Second Supplementary Deed to be void ab initio;
  3. Order that Bankwest and the Finance Parties repay monies payed to them under the above agreements.
Declarations:
  1. that the Financiers were not authorised to debit interest at the default rate, or alternatively, the First MOFA Collateral Stipulation and the Second Collateral Stipulation are unenforceable and/or void;
  2. Westgem is entitled to repayment, or alternatively, the amount payed was overpaid.
Hossean Pourzand (personal capacity), Hossean and Jenny Maria Pourzand as trustees for the Helen Trust
(Second plaintiff)
Guarantor under the MOFA
Guarantor under the Restated MOFA
First Additional Security Provider
Second Additional Security Provider
Guarantor under the AFL
Damages
Orders:
  1. declaring each of the Restated MOFA, Second Additional Securities (and Second DCA) and 13 October 2010 Letter Agreement, Amended AFL Supplementary Agreement and AFL Second Supplementary Deed to be void ab initio;
  2. declaring the 18 November 2009 Letter Agreement to be void ab initio
  3. declaring the First Additional Securities to be void ab initio;
  4. declaring the Fourth Deed of Variation, Fifth Deed of Variation, Restated MOFA and Second DCA to be void ab initio;
  5. declaring the Second Additional Securities to be void ab initio.
Rectification of the MOFA Share Mortgage such that it does not contain an unlimited obligation to pay.
Declaration that the Saraceni/Pourzand Guarantees Collateral Stipulation is unenforceable and/or void as a penalty.
Pakwest Pty Ltd
(Third plaintiff)
Guarantor under the MOFA
Guarantor under the Restated MOFA
First Additional Security Provider
Second Additional Security Provider,
Guarantor under the AFL
Damages
Orders:
  1. declaring each of the Restated MOFA, Second Additional Securities (and Second DCA) and 13 October 2010 Letter Agreement, Amended AFL Supplementary Agreement and AFL Second Supplementary Deed to be void ab initio;
  2. declaring the 18 November 2009 Letter Agreement to be void ab initio;
  3. declaring the First Additional Securities to be void ab initio;
  4. Order declaring the Fourth Deed of Variation, Fifth Deed of Variation, Restated MOFA and Second DCA to be void ab initio;
  5. Order declaring the Second Additional Securities to be void ab initio.
Newport Pty Ltd
(Fourth plaintiff)
Guarantor under the MOFA
Guarantor under the Restated MOFA
First Additional Security Provider
Second Additional Security Provider
Guarantor under the AFL
Same claim as the third plaintiff
Oakcure Pty Ltd
(Fifth plaintiff)
Guarantor under the MOFA
Guarantor under the Restated MOFA
Guarantor under the AFL
Damages
Orders:
  1. declaring each of the Restated MOFA, Second Additional Securities (and Second DCA) and 13 October 2010 Letter Agreement, Amended AFL Supplementary Agreement and AFL Second Supplementary Deed to be void ab initio;
  2. Order declaring the 18 November 2009 Letter Agreement to be void ab initio;
  3. Order declaring the Fourth Deed of Variation, Fifth Deed of Variation, Restated MOFA and Second DCA to be void ab initio.
Seaport Pty Ltd
(Sixth plaintiff)
Guarantor under the MOFA
Guarantor under the Restated MOFA
First Additional Security Provider
Second Additional Security Provider
Guarantor under the AFL
Same claim as the third Plaintiff
Luck Saraceni
(Seventh plaintiff)
Guarantor under the MOFA
Guarantor under the Restated MOFA
Second Additional Security Provider
Guarantor under the AFL pursuant to the AFL Second Supplementary Deed
Damages
Orders:
  1. declaring each of the Restated MOFA, Second Additional Securities (and Second DCA) and 13 October 2010 Letter Agreement, Amended AFL Supplementary Agreement and AFL Second Supplementary Deed to be void ab initio;
  2. declaring the 18 November 2009 Letter Agreement to be void ab initio;
  3. declaring the Fourth Deed of Variation, Fifth Deed of Variation, Restated MOFA and Second DCA to be void ab initio;
  4. declaring the Second Additional Securities to be void ab initio;
Rectification of the MOFA Share Mortgage such that it does not contain an unlimited obligation to pay.
Declaration that the Saraceni/Pourzand Guarantees Collateral Stipulation is unenforceable and/or void as a penalty.
Mayport Nominees Pty Ltd
(Eighth plaintiff)
Guarantor under the Restated MOFA
First Additional Security Provider
Second Additional Security Provider
Damages
Orders:
  1. declaring the First Additional Securities to be void ab initio;
  2. declaring the Fourth Deed of Variation, Fifth Deed of Variation, Restated MOFA and Second DCA to be void ab initio;
  3. declaring the Second Additional Securities to be void ab initio.
Queen Street Properties Pty Ltd
(Ninth plaintiff)
Guarantor under the Restated MOFA
First Additional Security Provider
Second Additional Security Provider
Same claim as the eighth plaintiff
Grand Edition Pty Ltd
(Tenth plaintiff)
Guarantor under the Restated MOFA
Second Additional Security Provider
Orders:
  1. declaring the Fourth Deed of Variation, Fifth Deed of Variation, Restated MOFA and Second DCA to be void ab initio;
  2. declaring the Second Additional Securities to be void ab initio.
LMS Holdings Pty Ltd
(Eleventh plaintiff)
Consequential Loss Plaintiff
Guarantor under: the first registered mortgage of Myer Fremantle securing debt to National Mutual; the Seaport Facility; and various loan obligations of Mayport and Newport under loan facilities with Bankwest.
Damages pursuant to s 12GF of the ASIC Act and/or s 79 of the FTA
Tokyo City Pty Ltd
(Twelfth plaintiff)
Consequential Loss Plaintiff
Trustee for various related entities
Guarantor under the first registered mortgage of Myer Fremantle securing debt to National Mutual; Guarantor of Seaport's obligations to Bankwest under the Seaport Facility.
Same claim as the eleventh plaintiff
Maree Saraceni Pty Ltd
(Thirteenth plaintiff)
Consequential Loss Plaintiff
Trustee for the Tokyo City Trust and the Luke Saraceni Family Trust
Same claim as the eleventh plaintiff
Maree Ann Saraceni
(Fourteenth plaintiff)
Consequential Loss Plaintiff
Registered proprietor of 72 undivided 250th shares in The Esplanade South Perth
Same claim as the eleventh plaintiff
Single Holdings Pty Ltd
(Fifteenth plaintiff)
Consequential Loss Plaintiff
Trustee for the Tuart Investments Unit Trust and formerly registered proprietor of land comprised in Vasse Newtown subject to securities in favour of St George
Guarantor under loan facilities relating to Vasse Newtown
Same claim as the eleventh plaintiff
Saracen Project Management Pty Ltd
(Sixteenth plaintiff)
Consequential Loss Plaintiff
Trustee for the Saracen Project Management Trust and manager of the Raine Square Project under fee income agreement with Westgem
Same claim as the eleventh plaintiff
Cardup Industrial Land Holdings Pty Ltd
(Seventeenth plaintiff)
Consequential Loss Plaintiff
Trustee and registered proprietor of land subject to a mortgage and charge in favour of St George
Same claim as the eleventh plaintiff
Goldcup Nominees Pty Ltd
(Eighteenth plaintiff)
Appointed trustee of Pakwest Trust on 23 November 2011 in lieu of Newport
Damages
Orders:
  1. declaring each of the Restated MOFA, Second Additional Securities (and Second DCA) and 13 October 2010 Letter Agreement, Amended AFL Supplementary Agreement and AFL Second Supplementary Deed to be void ab initio;
  2. declaring the 18 November 2009 Letter Agreement to be void ab initio;
  3. declaring the First Additional Securities to be void ab initio;
  4. declaring the Fourth Deed of Variation, Fifth Deed of Variation, Restated MOFA and Second DCA to be void ab initio;
  5. declaring the Second Additional Securities to be void ab initio.
Goldenwest Properties Pty Ltd
(Nineteenth plaintiff)
Consequential Loss Plaintiff
From 28 May 2010 trustee for the Pourzand Family Trust and from 7 March 2012 the registered proprietor of land subject to a mortgage in favour of St George
Same claim as the eleventh plaintiff



APPENDIX 2

_________________________________________________________________________

Table A: Natural Persons

No
Person
Company
Role
1
Artelaris, Steve
Saracen Properties
Senior Project Manager and Architect
(October 2006 - November 2010)
2
Baker, Stephen
Salta Constructions Pty Ltd
Commercial Manager WA (April 2008 - February 2010)
3
Bollig, Edwin
Bollig Design Group
Senior Architect, Managing Director
(September 2005 - August 2011)
4
Boyes, Quentin
CBA
Executive General Manager Corporate Services
(October 2008 - October 2010)
5
Burton, Dougal
Bankwest
Facility Agent
(October 2009 - November 2010)
Director, Property Finance Unit
(October 2009 - October 2011)
6
Cargill, Brian
Salta Constructions Pty Ltd
Chief Operating Officer
(May 2009 -March 2010)
7
Carmichael, Iain
Saracen Properties
External QS working for Luke Saraceni
(December 2006 - May 2010)
8
Clohessy, Mark
Structured Property Finance Pty Ltd; Security Capital
Director of Security Capital Australia Pty Ltd (2008)
Advisor, consultant and agent for Westgem re: Raine Square (2008 - 2010)
Managing Director of Structure Property Finance
(2009 - 2017)
9
Codling, Nicholas (Nick)
KordaMentha
Director
(February 2011 - June 2013)
10
Crocker, Ray
Bollig Design Group
Senior Architect, Director
(July 2007 - August 2011)
11
David Hewitt
David Hewitt & Co
Principal of Davit Hewitt & Co (Westgem's/Luke Saraceni's external accountant)
12
Davis, Tom
KordaMentha, 333
Director
13
Deans, Peter
CBA; Bankwest
Chief Risk Officer of Bankwest (October 2008 - June 2010)
Member of Bankwest Executive Credit Committee
14
Desousa, Gus
Salta Constructions Pty Ltd
Contractor's Representative (2006 - October 2010)
Senior Project Manager
(April 2009 - February 2010)
15
Dower, Greg
Saracen Properties Pty Ltd
CFO from around January 2010 Financial Controller (2010)
16
Ellis, Matthew
MGB Legal
Partner at Hammond Worthington
(February 2009)
Director of MGB Legal
(May 2009 - September 2010)
17
Fitzgerald, Ray
St Ives Group
Director
18
Fleming, Cheryl
Saracen Properties
Executive Assistant
(June 2007 - January 2010)
19
Foster-Key, Mark
Savills Valuations Pty Ltd
State Director, Valuation & Advisory
20
Frankl, Alex
CBA
Head of Commercial Property,
Design & Delivery
(October 2008 - October 2012)
Project Manager, Raine Square Development
21
Fyfe, Paul
Jackson McDonald
Partner
(August 2007 - December 2013)
22
Galbraith, Donald
Bankwest
Head of Credit Sanctioning for HBOS Australia
(June 2004 - 2008)
Head of Credit Sanctioning within Risk Management Division
(2008 - April 2010)
Head of Credit Asset Management Division
(April 2010 - 2012)
23
Gerrard, Steve
Salta Constructions Pty Ltd
Commercial Manager
24
Goerke, Graham
Jackson McDonald
Partner
(August 2006 - December 2010)
25
Gowdie, John
Gowdie Management Group
Construction and development adviser of 333 Advisory (2008)
Director and Principal of GMG
(2004 - 2017)
26
Griffiths, Ross
CBA
Head of Credit Management (1995 - 2007)
Chief Credit Officer
(2007 - March 2014)
Active member of Bankwest Executive Credit Committee and CBA Executive Risk Committee (unknown period)
27
Hanson, Geoff
Hanson Property
Managing Director
28
Hughes, Bryan
Pitcher Partners
Managing Director
Liquidator of Westgem
29
Hume, Andrew
Salta Constructions Pty Ltd
Cost Planning Manager (February - November 2007)
Branch Manager (WA) (November 2007 - March 2010)
30
Huston, Jessica
Deacons, Norton Rose
Lawyer/Associate
(May 2009 - September 2010)
31
Ingram, Geoffrey
BOSI Australia
Senior Analyst
(prior to March 2009)
Manager of Structured Property Finance for Queensland (March 2009 - July 2010)
32
Josland, Stephen
Josland
Barrister & Solicitor
(August 2008 - February 2011)
33
Kolagow, Dietrich Wolfgang
DW Kolagow & Associates Pty Ltd
Project Planning Consultant
34
Lafferty, Nigel
Newport Securities Pty Ltd; Grand Edition Pty Ltd
Director of Stevens Lafferty Sellers Pty Ltd
(as per emails of March 2009 - December 2010)
35
La Marca, John
Bankwest
Head of Property Finance (August 2005 - June 2009)
36
Langdon, Scott
KordaMentha; 333 Advisory
Associate Director of 333 Real Estate/KordaMentha (December 2008- August 2010)
Director of 333 Real Estate/KordaMentha (August 2010 -July 2012)
37
Leber, Troy
Bankwest
State Manager, Property Finance Unit
(November 2006 - March 2012)
38
Lowan, Grant
Bankwest
CBA Executive Officer
39
MacLaughlin, Wendy
HKA
Partner
Chartered Civil Engineer
40
Mahaffy, Larry
BOSI
Managing Director, Structured Property Financing (Vic) (2006 - 2010)
Senior Director, Business Support Unit, Property (Vic and NZ) (Lloyds International) (2010 - 2012)
41
McDonald, Stephen
BOSI; Lloyds Banking Group
Associate Director, Structured Property Finance (BOSI) (January 2006 - November 2007)
Director in Structured Property Finance
(November 2007 - July 2009)
Head of Property Finance for Queensland within the Property Finance Division of Lloyds (August 2009 - January 2012)
42
Mentha, Mark
333 Real Estate
Partner
(October 2009 - June 2013)
Appointed as one of two Receivers and Managers of Westgem (January 2011)
43
Merson, Robert
Saracen Properties
Quantity Surveyor / Senior Project Manager
(April 2009 - January 2011)
Superintendents Representative
44
Nagle, Steve
Bankwest
Senior Manager, Property Finance Unit
(2006 - September 2008)
Facility Agent
(April 2008 - October 2009)
Director, Property Finance Unit
(October 2009 - 2010)
Senior Manager, Credit Asset Management Division (secondment) (August 2010 - November 2011)
45
Nathan, Les
Bankwest
Senior Manager, Credit Sanctioning, HBOS Australia (2006 to October 2008)
State Manager WA, Credit Asset Management (October 2008 - 2012)
46
Parker, Dennis
Saracen Properties Pty Ltd
Alternative Director for Maree Saraceni (2008 -2010)
47
Pavisich, Alan
Bankwest
Senior Manager in Business Credit team
(September 2006 - December 2008)
Head of Credit Asset Management Division (Late 2008 - March 2010)
Head of Corporate, Specialised & Property Finance (March 2010 - 2013)
48
Pazin, Alen
Deacons, Norton Rose
Partner
(October 2007 - January 2011)
49
Peter Byford
E3 Advisory
Principal, Founding Director and Co-Chairman
(September 2014 onwards)
50
Potalivo, Jason
Saracen Properties
Executive Director, Development (November 2008 - November 2010)
51
Pourzand, Farah
Grand Edition
Director
52
Pourzand, Hossean
Westgem
  • Shareholder
  • Joint trustee with Jenny Pourzand
  • Married to Jenny Pourzand
53
Pourzand, Jenny Maria
Westgem; Oakcure Pty Ltd; Cityspace Pty Ltd
  • Director
  • Joint trustee with Hossean Pourzand
  • Married to Hossean Pourzand
54
Regan, Andrew
Salta Constructions Pty Ltd
Director Legal
(November 2007 - February 2010)
Executive Director - Legal (February - March 2010)
55
Regan, Peter
Bankwest
Chief Manager Property Management Services (September 2005 - May 2009)
Bankwest Shared Services/Bankwest Corporate Services (May 2009 - May 2014)
56
Rocke, Clifford
KordaMetha, 333
Partner Receiver
57
Ryan, William (Bill)
Deacons, Norton Rose
Partner
(July 2010 - September 2010)
58
Sanders, Trevor
RBB
Director (1986 - June 2016)
59
Saraceni, Frank
Saracen Properties; Saracen Project Engineering; Saracen Project Management Pty Ltd
Executive Director, Projects (May 2006 - December 2010)
60
Saraceni, Joel
Saracen Properties
Project Director
(January 2010 - December 2010)
61
Saraceni, Luke
Westgem Saracen Project
Management Pty Ltd
  • Director and shareholder
  • Founder
62
Saraceni, Maree Ann
Saracen Properties Pty Ltd; Grand Edition
  • Director
  • Married to Luke Saraceni (1977 to 9 June 2011)
63
Simpson, Paul
Saracen Properties
Project Manager and Quantity Surveyor
(June 2007 - January 2011)
64
Stephenson, Andrew
Clayton Utz
Partner
65
Stevens, Geoff
Lavan Legal
Partner
66
Sutton, Jon
Bankwest
CEO / Managing Director of Bankwest (December 2008 - March 2012)
67
Tarascio, Sam
Salta Constructions Pty Ltd
Managing Director
(June 2007 - June 2010)
68
Tarascio, Sam Jnr
Salta Constructions Pty Ltd
Director
(May 2007 - March 2010)
69
Taveira, Sheldon
BOS Australia
Associate Director, Business Support Unit - Property (October 2008 - December 2010)
Manager, Business Support Unit – Property
(May 2010- December 2012)
70
Taylor, Steve
Bankwest
Senior Project Manager, Raine Square (leasing) (August 2007 - October 2010)
71
Varsani, Prakash
Currie Brown (renamed Aquenta Consulting in October 2010)
Associate
(September 2007 - October 2010)
72
Vinnicombe, Simon
Gowdie Management Group; KordaMentha
Gowdie Management Group (April 2010 - December 2010)
Manager at KordaMentha (January 2011 - October 2016)
73
Veevers, Peter Charles
Salta Constructions Pty Ltd
Director
74
Walsh, Simon
Bankwest
Managing Director of Bankwest
(December 2007 - October 2008)
75
Wheeler, David
Saracen Properties
Executive Director
(June 2010 - March 2011)
76
Wilenski, Richard
Tottle Partners
Partner
77
Wilson, Berrick
KordaMentha
Partner
(July 2006 - October 2009)
Managing Director 333 Real Estate
Appointed by Facility Agent as an independent consultant
(25 September 2009)
780
Wlossak, Mark
Bankwest
Head of Credit Asset Management (East)
79
Young, John
Saracen Properties
Property Analyst
(March 2008 – August 2008)
Development Manager (September 2008 – December 2009)




Table B: Corporate Entities

No
Company
Description
1
333 Advisory Pty Ltd
A company appointed by the Financiers to review the financial position of Luke Saraceni and Hossean Pourzand in November 2009.
2
333 Real Estate Pty Ltd
Consultants engaged by the Financiers in September 2009 to provide consultancy services, in respect of various matters, including a review and comment on the status of the project and cost to complete of the cost to complete.
3
Arccon (WA) Pty Ltd
Alternative builder on the Raine Square Project. Provided a building proposal to Westgem to complete the construction works in February 2010.
4
Bank of Western Australia Ltd (Bankwest)
Joint financier of the Raine Square Project with BOSI and tenant of Raine Square.
Bankwest has been a wholly owned subsidiary of CBA (the First Defendant) since October 2008.
5
Bollig Design Group
Architects contracted by Westgem for the base build works and design of the Raine Square Project
6
BOS International (Australia) Ltd (BOSI)
Joint Financier of the Raine Square Project with Bankwest. BOSI:
  • was, at all material times, a wholly owned subsidiary of HBOS Australia Pty Ltd; and
  • from 16 May 2014, has been known as Westpac Administration 2 Limited (the Second Defendant in these proceedings).
7
BOSI Security Services Ltd
Security Trustee under the Multi-Option Facility Agreement
8
Cardup Industrial Land Holdings Pty Ltd
Seventeenth Plaintiff and corporation of which Hossean Pourzand was the sole director. Trustee for:
  • the Cardup Industrial Land Trust; and
  • the Cardup Industrial Land Trust # 2.
9
CB Richard Ellis Pty Ltd (CBRE)
Commercial real estate services and investment firm, engaged by Bankwest to provide services in connection with Bankwest’s proposed tenancy of Raine Square relating to corporate assessment, market evaluation, building assessment, negotiation and lease or equity risk participation.
CBRE acquired Swale Hynes in September 2007.
10
Charter Hall Funds Management Ltd
Entered into provisional agreement to purchase Pourzand's 50% share in the Project, however decided not to proceed consequent to the Salta Stoppage.
11
Commonwealth Bank of Australia Ltd (CBA)
First Defendant. Acquired Bankwest in October 2008.
12
D W Kolagow & Associates Pty Ltd
Project planning consultants engaged to review construction programmes and prepare revised construction programmes.
13
David Hewitt & Co
Westgem’s accountants in relation to the Raine Square Project.
14
Deacons / Norton Rose
Solicitors for the Banks in relation to the financing aspects of the Raine Square Project.
15
Diploma Constructions (WA) Pty Ltd
Forward works builder on the Raine Square Project in 2007. Provided a building proposal to Westgem in February 2010 to complete the construction works on the Raine Square Project following Salta’s termination.
16
Forum Partners Asia (HK) Ltd
Provided refinance recapitalisation proposals for the Raine Square Project from approximately September 2010 to January 2011.
17
Gallagher Group Limited
Engaged by Salta as a concrete and structural work subcontractor for the Raine Square Project.
18
Goldman Sachs Group Inc
Provided finance recapitalisation proposals for the Raine Square Project from approximately September 2010 to December 2010.
19
Goldcup Nominees Pty Ltd
Eighteenth Plaintiff in its capacity as trustee for the Pakwest Trust (from 23 November 2011).
20
Golden West Properties Pty Ltd
Nineteenth Plaintiff in its capacity as trustee (from 28 May 2010) for:
  • the Pourzand Family Trust;
  • the Ozra Trust;
  • the Gold House Trust; and
  • Jenny’s Trust.
21
Gowdie Management Group
Programming, project management and construction services consultancy company, engaged by the Financiers in September 2009 to assist 333 to undertake a review of the Raine Square Project and report on certain construction and leasing components of the Project. Later provided assisting in observing the management of the project following Probuild’s appointment.
22
Grand Edition Pty Ltd
Tenth Plaintiff and corporation of which Farah Pourzand was sole director. Plaintiff in its own right and as trustee for the Farah Investment Trust No. 4
23
HBOS Australia Pty Ltd (HBOSA)
Parent company of:
  • Bankwest until approximately 19 December 2008; and
  • BOSI (at all material times).
24
Jackson McDonald
Solicitors for Westgem in relation to various matters relating to the Raine Square Project.
25
JCA Project Planning
Professional project planning and scheduling consultancy company engaged by Bankwest as an independent programming consultant in relation to the fit-out works.
26
JP Morgan Securities (Asia Pacific) Limited
Provided finance recapitalisation proposals for the Raine Square Project from approximately September 2010 to October 2010.
27
Stephen Josland (Barrister)
Barrister engaged by Luke Saraceni / Westgem in relation to various matters.
28
Kann Finch Group Pty Ltd
Architecture and interior design firm engaged by Bankwest to provide services in connection with the construction of the Raine Square Project and the fitout of the building
29
Knight Frank (WA) Pty Ltd
Commercial property consultant and real estate agency, appointed as joint leasing agent with CB Richard Ellis in relation to the office space in Raine Square in approximately April 2005.
30
Lavan Legal
Solicitors engaged by Westgem in relation to various matters related to the Raine Square Project, including in relation to the Cost Overruns.
31
Lincolne Scott Pty Ltd (later known as WSP Lincolne Scott)
Consulting engineering company engaged by Saracen Property Ptd Ltd in relation to the mechanical and fire services work on the Raine Square Project. Lincolne Scott merged with WSP Group in 2007 and was renamed as WSP Lincolne Scott in around 2009.
32
LMS Holdings Pty Ltd
Eleventh plaintiff and corporation of which Luke Saraceni and Maree Saraceni were directors. Plaintiff in its capacity as trustee for the Saraceni Family Trust.
33
Mayport Nominees Pty Ltd
Eight plaintiff and corporation of which Luke Saraceni and Maree Saraceni were directors at all material times. Plaintiff in its own right and as trustee for the Mayport Unit Trust.
34
MGB Legal
Solicitors engaged by Hossean Pourzand and Westgem on Raine Square Project matters.
36
Newport Securities Pty Ltd
Fourth plaintiff and corporation of which Luke Saraceni and Maree Saraceni were directors at all material times. Plaintiff in its own right and as trustee for:
  • the Pakwest Trust;
  • the Newport Family Trust; and
  • the Luke Saraceni Family Trust.
37
NS Projects Pty Ltd
Project manager and superintendent of the Raine Square Project from approximately May 2010.
38
Oakcure Pty Ltd
Fifth plaintiff and corporation of which Hossean Pourzand and Jenny Pourzand were directors at all material times. Plaintiff in its own right and as trustee for the Parry Trust.
Also trustee for:
  • the Zahra No. 2 Trust; and
  • the Zahra No. 3 Trust
39
Pakwest Pty Ltd
Third plaintiff and corporation of which Luke Saraceni and Maree Saraceni were directors. Plaintiff in its own right and as trustee for:
  • Newport Securities as trustee for the Pakwest Trust;
  • Oakcure Pty Ltd as trustee for the Parry Trust;
  • Westview Asset Ltd as Trustee for the Westview Trust;
  • Oakcure Pty Ltd as trustee for the Zahra No. 2 Trust;
  • the trustees of the Faramaz Trust, being:
    • Hossean Pourzand and Mrs Pourzand, until 11 June 2010; and
    • Cityscape Investments Pty Ltd, after 11 June 2010 (of which Pourzand and Mrs Pourzand were directors)
  • Rangeway Investments Pty Ltd as trustee for Rangeway Investments Trust;
  • Gold Rain Holdings Pty Ltd as Trustee for Gold Rain Family Trust; and
  • Oakcure Pty Ltd as trustee for the Zahra No. 3 Trust
40
Perron Developments Pty Ltd
Property investment company and potential purchaser of Vasse Newtown.
41
Probuild Constructions (Aust) Pty Ltd
Construction company engaged:
  • to complete the forward works on the Raine Square Project in 2007; and
  • as head builder in September 2010 to complete the remaining construction works on the Raine Square Project following Salta’s termination.
42
Ralph Beattie Bosworth Pty Ltd (RBB)
Construction cost consultancy company engaged by the Financiers as quantity surveyor in approximately August 2007 and as Project Certifier under the MOFA around April 2008.
43
Rider Levett Bucknall WA Pty Ltd
Quantity surveying consultants engaged by Westgem to provide consultancy services on the Raine Square Project.
44
Queen Street Properties Pty Ltd
Ninth plaintiff and corporation of which Luke Saraceni and Maree Saraceni were directors. Trustee for the Queen Street Properties Trust.
45
Salta Constructions Pty Ltd (Salta)
Engaged by Westgem as head builder in relation to the base build construction works on the Raine Square Project in 2007, until termination of the building contract in February 2010.
46
Salta Properties Pty Ltd
Parent company of Salta Constructions Pty Ltd.
47
Saracen Project Engineering
Corporation of which Frank Saraceni was the sole director, appointed as Superintendent under
Westgem’s building contract with Salta for the Raine Square Project.
48
Saracen Project Management Pty Ltd
Sixteenth plaintiff and corporation appointed as manager of the Raine Square Project under agreement with Westgem dated August 2005. Plaintiff in its capacity as trustee for the Saracen Project Management Trust.
49
Saracen Properties Pty Ltd
Project management and construction management company established by Luke Saraceni in 1995 to undertake development projects, responsible for coordinating and overseeing the Raine Square Project, including in relation to financial management and administration.
50
Seaport Pty Ltd
Sixth plaintiff and corporation of which Luke Saraceni was the sole director at all material times. Plaintiff in its own right and as trustee for the Seaport Trust.
51
Security Capital Corporation Pty Ltd
Company of which Mark Clohessy was a director. Licenced finance broker and commission agent for Bankwest until September 2008.
52
Single Holdings WA Pty Ltd
Fifteenth plaintiff and corporation of which Luke Saraceni was a director, and from 14 October 2011, Maree Saraceni was a director. Plaintiff in its capacity as trustee for the Tuart Investments Unit Trust.
53
Structured Property Finance Pty Ltd
Company providing finance for commercial property purchase developments, established by Mark Clohessy in September 2008. Entered into an Origination Agreement with Bankwest in April 2009 as a commission agent.
54
Tokyo City Pty Ltd
Twelfth plaintiff and corporation of which Luke Saraceni and Maree Saraceni were directors. Plaintiff as trustee for the Tokyo City Trust.
55
Westgem Investments Pty Ltd
First plaintiff and special purpose vehicle created with a view to be the purchaser of Raine Square, and of which Luke Saraceni and Hossean Pourzand each held one share.
Trustee for:
  • Pourzand and Mrs Pourzand as trustees for the Helen Trust;
  • Pakwest Pty Ltd as trustee for:
  • Newport Securities Pty Ltd as trustee for the Pakwest Trust; and
  • Oakcure Pty Ltd as trustee for the Parry Trust.
56
Westpac Administration 2 Limited
Second Defendant, previously known as BOSI. Acquired BOSI on approximately 16 May 2014.
57
Westpac Administration 3 Limited
Third Defendant, previously known as BOSI Security Services Ltd (BOSIS). Acquired BOSIS on approximately 16 May 2014.
58
Wood & Grieve Engineers Limited
Electrical engineers on the Raine Square Project.


APPENDIX 3
________________________________________________________________
Ageing Creditor Tables
































I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.

AS
Associate to the Honourable Justice Tottle

27 AUGUST 2020


[1] Bankwest and BOSI were both owned by HBOS Australia Pty Ltd (HBOSA). In October 2008 the Commonwealth Bank of Australia Ltd acquired Bankwest and in 2012 it became the successor in law to Bankwest. In October 2013 HBOSA sold its remaining Australian holdings to Westpac Banking Corporation; BOSI is now known as Westpac Administration 2 Ltd and is the second defendant.
[2] BOSI Security Services Pty Ltd was originally named BWA Custodians Ltd. It is now named Westpac Administration 3 Ltd and is the third defendant.
[3] RSQ.006.0001.0046, cl 1.1(48). (The number of documents tendered in the course of the trial was such that documents were tendered by tender lists in which each document tendered was identified by a unique document identifier. Footnoted references to documents use the unique document identifier allocated to each document. The same system is used for identifying pleadings, submissions and other documents to which reference was made in the course of the trial).

[4] The claims are made in the proceedings numbered CIV 2722 of 2012.

[5] The claims are made in the proceedings numbered CIV 2722 of 2012.

[6] The claims are made in the proceedings numbered CIV 2722 of 2012.

[7] The claims are made in the proceedings numbered CIV 2722 of 2012.

[8] The claims are made in the proceedings numbered COR 77 of 2014.

[9] These claims are made in proceedings numbered CIV 1596 of 2011, CIV 1651 of 2011 and CIV 1652 of 2011.
[10] Westgem Investments Pty Ltd v Commonwealth Bank of Australia Ltd [No 5] [2019] WASC 310.

[11] SAR.069.001.076548.
[12] RSQ.001.0138.0001; RSQ.001.0138.0003.
[13] RSQ.006.0001.0030.
[14] BOS.013.001.1181; RSQ.006.0001.0172; RSQ.006.0001.0188; SAR.115.004.024292; RSQ.007.0095.0001.
[15] RSQ.006.0002.0001.
[16] The Fourth and Fifth Deeds of Variation dated 30 June 2010 and 31 August 2010 respectively.

[17] RSQ.007.0034.0001.

[18] RSQ.006.0002.0001.

[19] BKW.502.003.8616.
[20] BKW.600.013.4285. In this judgment, unless otherwise apparent, quoted portions of documents and communications have been reproduced in their original form without correction of errors of spelling or grammar.
[21] SUB.101.004.0028, par 116.
[22] The Second Additional Securities were provided pursuant to the Restated MOFA and are listed in appendix 1, table C.
[23] See Westgem Investments Pty Ltd v Commonwealth Bank of Australia Ltd [No 5] [2019] WASC 310.
[24] DEF.201.041.0016, par 28 - 30; Jones v Dunkel [1959] HCA 8; (1959) 101 CLR 298.

[25] BKW.001.062.0092; Exhibit D8, BKW.999.031.0001, par 29 - 75.
[26] Westgem held the title of Raine Square Area 1 on trust for Mr Pourzand and Mrs Pourzand in their capacities as trustees for the Helen Trust (RSQ.006.0001.0061, cl 1.3(1).
[27] Westgem held the title of Raine Square Area 2 on trust for Pakwest Pty Ltd as trustee for Newport Securities Pty Ltd in its capacity as trustee for the Pakwest Trust and as trustee for Oakcure Pty Ltd as trustee for the Parry Trust (RSQ.006.0001.0061, cl 1.3(1).
[28] RSQ.006.0001.0208.
[29] RSQ.006.0001.0242.
[30] RSQ.006.0001.0300; RSQ.006.0001.0370; RSQ.006.0001.0331; RSQ.006.0001.0349.
[31] RSQ.006.0001.0030, 8.
[32] RSQ.006.0001.0030, 15 - 16.
[33] RSQ.006.0001.0030, 34 - 35.

[34] RSQ.001.0138.0001.
[35] RSQ.001.0138.0003.

[36] Unless otherwise stated the monetary amounts exclude GST.

[37] RSQ.001.0138.0003, 3.

[38] RSQ.001.0138.0003, 3.

[39] RSQ.001.0138.0003, 54.

[40] RSQ.001.0138.0003, 13.
[41] SAR.072.001.001233; SAR.069.001.019468; SAR.069.001.021437; SAR.072.001.000988; SAR.100.003.007975.
[42] SAR.108.002.062724.
[43] SAR.108.002.062724.
[44] SAR.100.003.008427.
[45] SAR.100.003.008434.
[46] SAR.100.003.008438.
[47] SAR.100.003.008657.

[48] RSQ.007.0107.0001.
[49] RSQ.006.0002.1145.
[50] RSQ.006.0002.1174.

[51] PLE.101.011.0001, par 187.4.
[52] PLE.101.011.0001, par 187.4, par 189.

[53] PLE.101.011.0001, par 193.

[54] PLE.101.011.0001, par 193A.

[55] PLE.101.011.0001, par 227.

[56] PLE.101.011.0001, par 194.

[57] PLE.101.011.0001, par 195.

[58] Electricity Generation Corporation t/as Verve Energy v Woodside Energy Ltd [2014] HCA 7; (2014) 251 CLR 640 [35] (French CJ, Hayne, Crennan & Kiefel JJ); Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 256 CLR 104 [46] (French CJ, Nettle & Gordon JJ).
[59] Ecosse Property Holdings Pty Ltd v Gee Dee Nominees Pty Ltd [2017] HCA 12; (2017) 261 CLR 544 [17] (Kiefel, Bell & Gordon JJ); Electricity Generation Corporation v Woodside Energy [35]; Mount Bruce Mining Pty Ltd v Wright Prospecting [51].
[60] Black Box Control Pty Ltd v Terravision Pty Ltd [2016] WASCA 219 [42] (Newnes & Murphy JJA & Beech J).
[61] Torre Asset Funding Ltd v The Royal Bank of Scotland plc [2013] EWHC 2670 (Ch) [152].
[62] See also Maggbury Pty Ltd v Hafele Australia Pty Ltd [2001] HCA 70; (2001) 210 CLR 181 [43] (Gleeson CJ, Gummow and Hayne JJ).
[63] Skanska Rashleigh Weatherfoil Ltd v Somerfield Stores Ltd [2006] EWCA Civ 1732.
[64] Skanska v Somerfield Stores [21] - [22].
[65] RSQ.006.0001.0030, cl 1.1(8).

[66] RSQ.006.0001.0030, cl 13.1, Sch 5(11).
[67] RSQ.006.0001.0030, cl 13.1, Sch 5(15)(a).
[68] RSQ.006.0001.0030, cl 13.1, Sch 5(20).
[69] RSQ.006.0001.0030, cl 13.1, Sch 5(21).
[70] RSQ.006.0001.0030, cl 1.1(120).
[71] So much was effectively acknowledged by senior counsel for Westgem who, at ts 3,526, in the context of referring to the Cost to Complete element of the definition of Cost Overrun, accepted that the provision was 'mostly to protect the Financiers', though it had some protections built in for Westgem, being the obligation to calculate Cost to Complete in the manner specified in the MOFA.
[72] SUB.101.006.0001, par 20.
[73] BKW.995.001.0001, par 379.
[74] Australian Vintage Ltd v Belvino Investments No 2 Pty Ltd [2015] NSWCA 275; (2015) 90 NSWLR 367.
[75] Veba Oil Supply & Trading GmbH v Petrotrade Inc [2001] EWCA Civ 1832; [2002] 1 All ER 703, 711 - 712.
[76] ts 3513 - 3514.
[77] DEF.201.041.0001, par 59 - 74.

[78] RSQ.006.0001.0030, 59.

[79] BKW.995.001.0001, par 379.
[80] BKW.995.001.0001, par 379 - 380.
[81] DEF.201.041.0001, par 82 - 98.
[82] DEF.201.041.0001, par 76, 88.
[83] DEF.201.041.0001, par 77.
[84] DEF.201.041.0001, par 78 - 79.

[85] DEF.201.041.0001, par 80 – 87.
[86] DEF.201.041.0001, par 89, 90.
[87] DEF.201.041.0001, par 91.
[88] ts 3087.
[89] Arida v Arida [2015] NSWCA 170 [89] (Sackville AJA, Bathurst CJ & Macfarlan JA agreeing); BOS International (Australia) Ltd v Babcock & Brown International Pty Ltd [2011] NSWSC 1382 [38].

[90] ts 2537.

[91] ts 3509 - 3510.
[92] BHP Petroleum (Australia) Pty Ltd v Sagasco South East Inc [2001] WASCA 159 [24]; Apache Finance Pty Ltd v Quadrant Energy Pty Ltd [2018] WASC 68 [29].
[93] Perpetual Custodians Ltd v IOOF Investment Management Ltd [2013] NSWCA 231; (2013) 278 FLR 49 [86]. See also Apache Finance v Quadrant Energy [29] - [31]; Segelov v Ernst & Young Services Pty Ltd [2015] NSWCA 156; (2015) 89 NSWLR 431 [87], [101] (Gleeson JA, Meagher & Leeming JJA agreeing).
[94] Halford v Price [1960] HCA 38; (1960) 105 CLR 23, 33.
[95] ts 3511.

[96] RSQ.006.0001.0507.

[97] RSQ.006.0001.0507, cl 1.1(32).

[98] RSQ.006.0001.0507, cl 1.1(18).

[99] McMahon v State Bank of NSW (1990) 8 ACLC 315, 316 - 317 (Priestley JA); Canberra Advance Bank Ltd v Benny [1992] FCA 823; (1992) 38 FCR 427, 432 (Neaves, Miles & O'Loughlin JJ).
[100] Taylor Woodrow International Ltd v Minister of Health (1978) 19 SASR 1, 22 (Bray CJ).
[101] BOS.501.006.1064.
[102] RSQ.007.0030.0001.
[103] Fitzgerald v Masters [1956] HCA 53; (1956) 95 CLR 420, 426 - 427(Dixon CJ & Fullagar J); Dodds v Kennedy [No 2] [2011] WASCA 131; (2011) 42 WAR 16 [28] (Pullin JA, Hall J agreeing).

[104] PLE.101.011.0001, par 189.1.
[105] PLE.101.011.0001, par 189.2.
[106] PLE.101.011.0001, par 190.
[107] RSQ.007.0384.0001, 4.
[108] Bold typeface was used in the original to denote defined terms.
[109] RSQ.007.0384.0001, 6.

[110] The definition also dealt with 'retail clients' and 'wholesale clients' in terms not presently relevant.
[111] SUB.101.006.0001, pars 2 - 4.
[112] Sam Management Services (Aust) Pty Ltd v Bank of Western Australia Ltd [2009] NSWCA 320 [5]; Commonwealth Bank of Australia v Starrs [2012] SASC 222 [107] - [110]; International Skin Care Suppliers Pty Ltd v Commonwealth Bank of Australia [2013] NSWSC 1768 [548].
[113] Seeto v Bank of Western Australia Ltd [2010] NSWSC 922 [38] - [39].

[114] DEF.201.041.0001, par 30.
[115] BKW.996.012.0001, par 189(a)(ii)(C).
[116] PLE.101.009.0001.

[117] PLE.101.011.0001, par 188.2.
[118] Port Jackson Stevedoring Pty Ltd v Salmond & Spraggon (Aust) Pty Ltd [1978] HCA 8; (1978) 139 CLR 231, 271 (Mason & Jacobs JJ)
[119] R v Clarke [1927] HCA 47; (1927) 40 CLR 227, 244.
[120] Dalgety Australia Ltd v Harris [1977] 1 NSWLR 324.
[121] Dalgety v Harris, 328.
[122] SUB.101.006.0001, par 3.
[123] Junker v Hepburn [2010] NSWSC 88 [52] - [54]; Pet Tech Pty Ltd v Batson [2013] NSWSC 1954 [9]; Professor Glanville Williams, Joint Obligations (1949), 24.

[124] Sam Management Services (Aust) Pty Ltd v Bank of Western Australia Ltd [2009] NSWCA 320 [72].
[125] PLE.101.011.0001, par 193.

[126] ts 3529 - 3532.
[127] ts 3532.
[128] Philips Electronique Grand Public SA v British Sky Broadcasting Ltd [1995] EMLR 472, 481.
[129] Attorney General of Belize v Belize Telecom Ltd [2009] UKPC 10; [2009] 1 WLR 1988, [21].
[130] Marcus Clark (Victoria) Ltd v Brown [1928] HCA 12; (1928) 40 CLR 540.
[131] Brambles Holdings Ltd v Bathurst City Council [2001] NSWCA 61; (2001) 53 NSWLR 153 [28] - [31].
[132] New South Wales Rifle Association Inc v Commonwealth [2012] NSWSC 818; (2012) 266 FLR 13 [115], [126] - [127].
[133] Servcorp WA Pty Ltd v Perron Investments Pty Ltd [2016] WASCA 79; (2016) 50 WAR 226 [66(a)] (Buss JA, Martin CJ & Murphy JA agreeing).
[134] WFI Insurance Ltd v Manitowoq Platinum Pty Ltd [2018] WASCA 89 [107] (Martin CJ, Murphy JA & Chaney J agreeing).
[135] Marcus Clark v Brown, 552 - 555.
[136] Brambles Holdings Ltd v Bathurst City Council [28].

[137] Equitable Life Assurance Society v Hyman [2002] AC 408.
[138] Equitable Life Assurance Society v Hyman, 459.
[139] See Marks & Spencer plc v BNP Paribas Securities Services Trust Co (Jersey) Ltd [2015] UKSC 72; [2016] AC 742 [23] - [24] (Lord Neuberger, Lords Sumption & Hodge agreeing).
[140] cf the facts of Burger King Corporation v Hungry Jack's Pty Ltd [2001] NSWCA 187; (2001) 69 NSWLR 558.
[141] Vodafone Pacific Ltd v Mobile Innovations Ltd [2004] NSWCA 15 [216]; Tomlin v Ford Credit Australia [2005] NSWSC 540 [120].
[142] BP Refinery (Westernport) Pty Ltd v Shire of Hastings (1977) 180 CLR 266.
[143] Codelfa Construction Pty Ltd v State Rail Authority of NSW [1982] HCA 24; (1982) 149 CLR 337, 347.
[144] BP Refinery (Westernport) Pty Ltd v Shire of Hastings, 283; Codelfa Construction Pty Ltd v State Rail Authority of NSW, 347.

[145] PLE.101.011.0001, par 193A.
[146] ts 3530.

[147] Burger King Corporation v Hungry Jack's Pty Ltd [2001] NSWCA 187; (2001) 69 NSWLR 558.

[148] Commonwealth Bank of Australia Ltd v Renstel Nominees Pty Ltd [2001] VSC 167, [47].
[149] Commonwealth Bank of Australia Ltd v Spira [2002] NSWSC 905; (2002) 174 FLR 274.
[150] ts 3532.
[151] ts 3077 - 3078.
[152] ts 3074.
[153] Mineralogy Pty Ltd v Sino Iron Pty Ltd [No 6] [2015] FCA 825; (2015) 329 ALR 1.
[154] ts 3091 - 3092.
[155] Central Exchange Ltd v Anaconda Nickel Ltd [2001] WASC 128; (2001) 24 WAR 382 [22] - [23]; Central Exchange Ltd v Anaconda Nickel Ltd [2002] WASCA 94; (2002) 26 WAR 33; Expectation Pty Ltd v Pinnacle VRB Ltd [2004] WASCA 261; Ammon v Consolidated Minerals Ltd [No 3] [2007] WASC 232 [209]; Topseal Concrete Services Pty Ltd v Sika Australia Pty Ltd [2008] WASC 57 [53] - [69]; Strzelecki Holdings Pty Ltd v Cable Sands Pty Ltd [2010] WASCA 222; (2010) 41 WAR 318; Trans Petroleum (Australia) Pty Ltd v White Gum Petroleum Pty Ltd [2012] WASCA 165; (2012) 268 FLR 433; Hampton v BHP Billiton Minerals Pty Ltd [No 2] [2012] WASC 285 [259] - [269]; Caratti Holdings Co Pty Ltd v Coventry Group Ltd [2014] WASC 403.
[156] Royal Botanic Gardens and Domain Trust v South Sydney City Council [2002] HCA 5; (2002) 240 CLR 45 [40]; Commonwealth Bank of Australia v Barker [2014] HCA 32; (2014) 253 CLR 169 [42].
[157] Renard Constructions (ME) Pty Ltd v Minister for Public Works [1992] 26 NSWLR 234.
[158] Renard Constructions, (256) - (260).
[159] Renard Constructions, (261) - (262).
[160] Renard Constructions, (263).
[161] Renard Constructions, (258).
[162] Renard Constructions, (279) - (280).
[163] Hughes Bros Pty Ltd v Trustees of the Roman Catholic Church for the Archdiocese of Sydney (1993) 31 NSWLR 91.
[164] Hughes Aircraft Systems International v Airservices Australia [1997] FCA 558; (1997) 76 FCR 151.
[165] Alcatel Australia Ltd v Scarcella [1998] NSWSC 483; (1998) 44 NSWLR 349.
[166] Alcatel Australia Ltd v Scarcella, (369).
[167] Burger King v Hungry Jack's [169] - [171].
[168] Burger King v Hungry Jack's [183].
[169] Commonwealth Bank of Australia v Renstel Nominees [47].
[170] Commonwealth Bank of Australia v Renstel Nominees [95].
[171] Commonwealth Bank of Australia v Spira [140].
[172] Commonwealth Bank of Australia v Spira [155].
[173] Vodafone Pacific Ltd v Mobile Innovations Ltd [2004] NSWCA 15.
[174] Vodafone v Mobile Innovations [191].
[175] Vodafone v Mobile Innovations [192].
[176] Androvitsaneas v Members First Broker Network Pty Ltd [2013] VSCA 212.
[177] Androvitsaneas v Members First Broker Network [108] - [109].
[178] Specialist Diagnostic Services Pty Ltd v Healthscope Ltd [2012] VSCA 175; (2012) 41 VR 1 [87]. Citing Tote Tasmania Pty Ltd v Garrott [2008] TASSC 86; (2008) 17 Tas R 320, 326 [16].
[179] Paul Kennedy Transport Pty Ltd v Australia and New Zealand Banking Group Ltd (1993) 6 BPR 13,883.
[180] Canberra Advance Bank Ltd v Benny [1992] FCA 823; (1992) 38 FCR 427, 432 - 434.

[181] Macquarie International Health Clinic Pty Ltd v Sydney South West Area Health Service [2010] NSWCA 268.

[182] Braganza v BP Shipping Ltd [2015] UKSC 17; [2015] 1 WLR 1661.
[183] A view supported in other contractual contexts by Cromwell Property Securities Ltd v Financial Ombudsman Service Ltd [2014] VSCA 179; (2014) 288 FLR 374 [93]; Bartlett v Australia and New Zealand Banking Group Ltd [2016] NSWCA 30; (2016) 92 NSWLR 639 [49].
[184] Minumbra Lancewood Pty Ltd v AM Lancewood Investment Nominees Pty Ltd [2013] NSWSC 1929; (2013) 9 BFRA 130.
[185] Minumbra Lancewood v AM Lancewood [28].
[186] Although the context in which the issue arose differs from the circumstances of the present case, the decision of the High Court in Park v Brothers [2005] HCA 73; (2005) 80 ALJR 421 [39] is authority for the proposition that, in the context of a contract for the sale of farming land, whether a vendor was required to act reasonably in considering a request by a purchaser concerning the use of the land prior to settlement, was a matter to be determined by construing the relevant contractual provision. The issue was not determined by implication as a matter of law.
[187] RSQ.006.0001.0030, 76.
[188] RSQ.006.0001.0030, cl 1.1(74).
[189] RSQ.006.0001.0030, 75.
[190] RSQ.006.0001.0030, 75.
[191] RSQ.006.0001.0030, 75.
[192] RSQ.006.0001.0030, 77.
[193] Caratti Holdings v Coventry Group [190].
[194] PLE.101.011.0001, par 227.

[195] SUB.101.006.0001, par 23.
[196] DEF.201.041.0001, 27, par 109.

[197] PLE.101.011.0001, par 194.

[198] Citing Cheall v Association of Professional Executive Clerical and Computer Staff [1983] 2 AC 180, 189; TCN Channel 9 Pty Ltd v Hayden Enterprises Pty Ltd (1989) 16 NSWLR 130, 147; Brothers v Park [2004] NSWCA 241; (2004) 12 BPR 22,501, 22,515; Ruthol Pty Ltd v Tricon (Australia) Pty Ltd [2005] NSWCA 443; (2005) 12 BPR 23,923, 23,926 - 23,927; Sydney Attractions Group Pty Ltd v Schulman [2013] NSWSC 858 [188]-[191].
[199] Heydon JD, Heydon on Contract, (2019) [8.1320] and the cases cited there.
[200] Heydon JD, Heydon on Contract, (2019) [8.1320] citing Richo International Ltd v Alfred C Toepfer International Gmbh (The Bonde) [1991] 1 Lloyd's Rep 136, 144; Antclizo Shipping Corporation v Food Corporation of India (The Antclizo) (No 2) [1992] 1 Lloyd's Rep 558, 567 - 568.
[201] Sydney Attractions Group Pty Ltd v Schulman; Ruthol Pty Ltd v Tricon (Australia) Pty Ltd [19] - [21].
[202] Breen v Williams [1996] HCA 57; (1996) 186 CLR 71, 115 (Gaudron & McHugh JJ).
[203] BOS.501.006.1063.
[204] Exhibit D8, BKW.999.031.0001, par 192.
[205] BOS.003.001.0581.
[206] SAR.115.004.006539.
[207] SAR.115.004.006539.
[208] BKW.001.009.0408.
[209] BOS.007.002.0139.
[210] RBB.501.001.2683.
[211] BKW.502.011.7667.
[212] BKW.600.012.8787.
[213] BKW.502.011.7784.
[214] BKW.600.012.8857.
[215] BOS.501.007.6828, 5.
[216] BKW.001.009.0024.
[217] BKW.502.011.7958.
[218] RSQ.003.0081.0136.

[219] RSQ.003.0080.0071, RSQ.003.0080.0062, RSQ.003.0080.0053.
[220] RSQ.003.0080.0041.

[221] RBB.501.001.2907.
[222] RBB.501.001.2908.

[223] BKW.362.001.5520.
[224] RBB.001.017.0219.
[225] SAR.115.001.001704.
[226] SAR.115.001.001704.
[227] BKW.001.010.0002.
[228] Exhibit D3, BKW.999.024.0001, par 104.
[229] BKW.001.010.0002.

[230] Exhibit D3, BKW.999.024.0001, par 105 - 106.
[231] There was no dispute about this telephone conversation. It was pleaded in the Sixth Further Amended Substituted Statement of Claim, PLE.101.011.0001, par 65.
[232] BKW.600.013.2235.
[233] BKW.502.011.8215.
[234] BKW.600.013.2597.

[235] BKW.003.001.0002.
[236] Exhibit D8, BKW.999.027.0001, par 237 - 239.
[237] BKW.001.054.0171.
[238] BKW.001.054.0172.
[239] BKW.501.002.4105.
[240] RBB.001.013.0039.
[241] DEF.201.041.0001, Sch 2.1.
[242] Exhibit D3, BKW.999.024.0001, par 133.
[243] DEF.201.041.0001.
[244] BKW.600.013.3346.
[245] SAR.115.004.007194.
[246] BKW.001.011.0011.
[247] SAR.114.005.008056.
[248] BKW.591.001.2378.
[249] BKW.502.003.8614.
[250] BKW.502.011.8523; BKW.502.011.8525.
[251] BKW.502.011.8332, BKW.502.011.8334.
[252] BKW.001.012.0527.
[253] BKW.600.013.4868.
[254] SAR.100.006.012648.
[255] SAR.100.006.012649.
[256] SAR.100.006.012649.

[257] SAR.100.006.012744.
[258] SAR.100.006.012744.
[259] BKW.600.013.4868.

[260] PLE.101.011.0001, par 229.

[261] PLE.101.011.0001, par 233 & 233A.

[262] PLE.101.011.0001, par 234.

[263] PLE.101.011.0001, par 234(ii).

[264] PLE.101.011.0001, par 234(iii).

[265] PLE.101.011.0001, par 234(iv)(C).

[266] PLE.101.011.0001, par 234(v).

[267] PLE.101.011.0001, par 235.

[268] PLE.101.011.0001, par 235(i).

[269] PLE.101.011.0001, par 235(ii).

[270] PLE.101.011.0001, par 235(iii).

[271] PLE.101.011.0001, par 235(iv).
[272] PLE.101.011.0001, par 236.

[273] SUB.101.006.0001, par 29 - 33.

[274] SUB.101.006.0001, par 34 - 35.

[275] SUB.101.006.0001, par 36.

[276] SUB.101.006.0001, par 37.

[277] SUB.101.006.0001, par 38 - 41.

[278] Exhibit D3, BKW.999.024.0001, par 105.

[279] Exhibit D3, BKW.999.024.0001, par 108.

[280] BKW.600.013.2597.
[281] PLE.101.011.0001, par 234(iv)(C).
[282] BKW.502.003.7951.
[283] RBB.001.005.0282.
[284] Exhibit D3, BKW.999.024.0001, par 112.
[285] RSQ.006.0001.0030, Sch 5, cl 15.
[286] Macquarie Dictionary (7th ed, 2017).
[287] Australian Concise Oxford Dictionary (7th ed, 1987).
[288] PLE.101.011.0001, par 234(v).

[289] Arcos Ltd v EA Ronaasen & Son [1933] UKHL 1; [1933] AC 470, 479 (Lord Aitkin).
[290] Margaronis Navigation Agency Ltd v Henry W Peabody & Co of London Ltd [1965] 2 QB 430, 444.
[291] See Commonwealth v Verwayen [1990] HCA 39; (1990) 170 CLR 394, 424 - 428 (Brennan J), 470 (Toohey J); Craine v Colonial Mutual Fire Insurance Co Ltd [1920] HCA 64; (1920) 28 CLR 305, 325; Pacific Brands Sport & Leisure Pty Ltd v Underworks Pty Ltd [2006] FCAFC 40; (2006) 149 FCR 395 [113] (Finn & Sundberg JJ).
[292]Australian Securities and Investments Commission Act 2001 (Cth) (incorporating amendments up to Act No 116 of 2008).
[293] Ipstar Australia Pty Ltd v APS Satellite Pty Ltd [2018] NSWCA 15; (2018) 329 FLR 149 [185] - [199] (Bathurst CJ) and [275] - [278] (Leeming JA).

[294] See also Australian Securities and Investments Commission v Kobelt [2019] HCA 18; (2019) 93 ALJR 743 [91] (Gageler J).
[295] Australian Securities and Investments Commission v Kobelt [59], [92].
[296]Australian Securities and Investments Commission v Kobelt [115], [120], [150]; Kakavas v Crown Melbourne Ltd [2013] HCA 25; (2013) 250 CLR 392 [18]; Tonto Home Loans Australia Pty Ltd v Tavares [2011] NSWCA 389; (2011) 15 BPR 29,699 [291] ‑ [293].

[297] Mastronardo v Commonwealth Bank of Australia Ltd [2018] NSWCA 136 [22].

[298] Paciocco v Australia and New Zealand Banking Group Ltd [2016] HCA 28; (2016) 258 CLR 525 at [189] (Gageler J).

[299] SUB.101.006.0001, par 47.

[300] BKW.501.001.0436.

[301] Exhibit D8, BKW.999.031.0002, par 162.

[302] PLE.101.011.0001, par 237.
[303] SAL.020.027.0001, 19.
[304] BKW.600.013.4868.
[305] Exhibit D3, BKW.999.024.0001, par 137.
[306] RBB.001.012.0033.
[307] Exhibit D3, BKW.999.024.0001, par 138.

[308] BKW.001.015.0191.
[309] Exhibit D3, BKW.999.024.0001, par 139.
[310] BKW.501.002.5589.
[311] BKW.001.012.0303.
[312] BKW.600.013.5129.
[313] BKW.001.012.0240.
[314] SAR.100.003.008852.

[315] SAR.100.003.008851.
[316] BKW.600.013.5512.
[317] BKW.600.013.5512.

[318] SAR.108.002.057229.

[319] BKW.600.013.5510.

[320] BKW.001.012.0239.
[321] BKW.600.013.5261.
[322] Exhibit D3, BKW.999.024.0001, par 148.
[323] Exhibit D3, BKW.999.024.0001, par 146.
[324] ts 1841.
[325] BKW.600.013.5262.
[326] BKW.999.024.0001, par 147.
[327] ts 1824 - 1825.
[328] ts 1826.
[329] ts 1827.
[330] ts 1827 - 1828.
[331] BKW.600.013.2253.
[332] ts 1831.
[333] ts 1831.
[334] SAR.108.002.018220.
[335] BKW.001.012.0213.
[336] BKW.551.001.4607.
[337] BKW.551.001.4607, 6.

[338] BOS.501.002.3401.
[339] BOS.501.002.3407.
[340] ts 1072.
[341] Exhibit D8, BKW.999.031.0001, par 267.

[342] BKW.001.013.0424.
[343] BOS.713.001.4197.

[344] BKW.632.050.6123.
[345] BKW.001.013.0424.
[346] Exhibit D4, BKW.999.025.0001, par 40.
[347] BKW.632.051.5639.
[348] BKW.632.051.5639.
[349] SAR.108.002.018151.
[350] Exhibit D11, BKW.999.036.0001.
[351] BKW.001.013.0314.

[352] BKW.501.002.6874.
[353] BKW.502.011.8694.
[354] BKW.502.011.8703.
[355] Exhibit D4, BKW.999.025.0001, par 68 - 69.
[356] Exhibit D4, BKW.999.025.0001, par 69.
[357] BKW.502.011.8703.
[358] BKW.511.001.1153.
[359] BOS.001.003.0098.
[360] BKW.502.004.2063.
[361] BKW.502.004.2063.
[362] BKW.502.004.2063; exhibit D4, BKW.999.025.0001, par 85.

[363] BKW.632.050.6338.
[364] BKW.511.001.1169.
[365] BKW.632.024.0165.
[366] SAR.115.001.002210.
[367] BKW.501.002.8937.
[368] BOS.501.002.3196.
[369] RBB.501.001.3368.
[370] RBB.501.001.3375.
[371] RSQ.007.0288.0109.
[372] SAR.115.004.007529.
[373] BKW.501.002.9316.
[374] BKW.501.002.9320.
[375] SAR.100.007.005907.
[376] SAR.100.007.005907.
[377] SAR.100.006.014408.
[378] Exhibit D11, BKW.999.036.0001, par 147 - 152.

[379] SAR.115.001.002324.
[380] BKW.213.001.1400.
[381] BKW.001016.0317.
[382] BKW.502.011.8936.
[383] BKW.501.002.9810.
[384] BKW.001.016.0621; BKW.001.016.0619.
[385] Exhibit D11, BKW.999.036.0001, par 153.
[386] Exhibit D11, BKW.999.036.0001, par 156 - 157.
[387] SAR.101.002.084059.
[388] BKW.001.016.0376.
[389] BKW.001.016.0376.
[390] Exhibit D11, BKW.999.036.0001, par 218.
[391] Exhibit D11, BKW.999.036.0001, par 160.
[392] BKW.502.004.3990.
[393] BKW.001.016.0431.

[394] SAR.115.001.002388.
[395] BKW.001.016.0321.
[396] BOS.501.002.2649.
[397] BOS.501.002.2651.
[398] Exhibit D4, BKW.999.025.0001, par 137.
[399] ts 1862 - 1863.
[400] BOS.501.002.2705.
[401] SAR.115.001.002400.
[402] BOS.501.002.2705.
[403] BKW.502.011.9040.
[404] SAR.115.001.002443.
[405] LAV.001.001.0039.
[406] LAV.001.001.0044.
[407] BKW.632.050.6107.
[408] BOS.712.001.2715.
[409] BKW.501.003.1771; BKW.502.004.5916.

[410] SAR.108.002.019715 & SAR.108.002.019714 respectively.
[411] Exhibit P10, SAR.999.018.000001.
[412] Exhibit P11, JER.201.002.0001.
[413] JER.201.002.0001, 4.
[414] JER.001.002.0036.

[415] Exhibit D11, BKW.999.036.0001, par 186.
[416] PLE.101.011.0001, par 250.

[417] PLE.101.011.0001, par 272.

[418] ts 1063.
[419] Exhibit D3, BKW.999.024.0001, par 150.
[420] ts 1062.
[421] In the course of dealing with Westgem's claims in respect of the first Cost Overrun I rejected its claim that it was entitled to a credit in respect of the removal of the tunnel from Salta's scope of works.

[422] BKW.501.002.4105.
[423] Exhibit D3, BKW.999.024.0001, par 146; BKW.501.001.3375.
[424] SUB.101.006.0001, par 126.

[425] Commonwealth Bank of Australia v Doggett [2014] VSC 423.
[426] Barton v Armstrong [1976] AC 104, 121.
[427] ts 1911.
[428] ts 1914.
[429] BKW.001.084.0164, cl 3.3(1).
[430] BKW.001.084.0164, cl 3.3(2).
[431] BKW.001.084.0164, Clause 5.2(2).
[432] ts 1885.
[433] ts 1876.
[434] BKW.001.084.0164.

[435] BKW.521.005.8518.
[436] RSQ.007.0095.0001.
[437] BKW.001.019.0668.
[438] Labracon Pty Ltd v Cuturich [2013] NSWSC 97.
[439] Labracon Pty Ltd v Cuturich [105].
[440] Greer v Kettle [1938] AC 156, 170 - 171 (Lord Maugham)
[441] Feltham P, Leech T, Crampin P & Winfield J, Spencer Bower: Reliance-Based Estoppel (2017, 5th ed) 2.25, 2.26 and 2.28 and the cases cited.
[442] Labracon Pty Ltd v Cututrich [127].
[443] PW & Co v Milton Gate Investments Ltd [2004] Ch 142 [155].
[444] PLE.101.011.0001, pars 92 and 94.

[445] ts 981.
[446] ts 984.

[447] RSQ.001.0138.0003, 47.
[448] RSQ.006.0001.0507.

[449] Clause 7 conferred 'step-in' rights on the Security Trustee.
[450] BKW.001.010.0122; BKW.001.010.0120.
[451] SAR.101.002.071363.
[452] SAR.115.001.011915.
[453] SAR.115.001.011915.
[454] SAR.108.002.056354.
[455] SAR.108.002.056354.
[456] SAR.115.001.011921.
[457] SAL.020.015.0073.
[458] BKW.001.011.0144.
[459] BKW.001.012.0614.
[460] BKW.501.003.1366.
[461] BKW.502.011.8476.
[462] SAR.100.002.008598.
[463] SAR.100.007.014372.
[464] SAR.100.003.008827.
[465] SAR.100.003.008827.

[466] SAR.100.007.013974.
[467] SAR.101.002.076925.
[468] BKW.001.015.0561.
[469] BOS.003.002.0267.
[470] SAR.115.001.011976.
[471] SAR.115.001.011975.
[472] SAR.115.001.011976.
[473] BKW.001.014.0499.
[474] BOS.501.002.3538.
[475] RSQ.007.0251.1299.
[476] RSQ.007.0251.1305.
[477] BKW.501.002.7441.
[478] BKW.001.014.0420.
[479] SAL.501.001.000452.
[480] SAL.501.001.000452.
[481] SAL.500.104.002466.
[482] BOS.501.007.8960.
[483] SAL.500.036.001169.
[484] SAL.500.036.001170.
[485] RSQ.007.0251.1636.
[486] BKW.501.003.0459.
[487] BOS.005.001.0809.
[488] BOS.005.001.0801.
[489] BOS.006.001.0197.
[490] BOS.006.001.0197.
[491] BOS.501.002.0268.
[492] SAL.020.001.0025.
[493] BKW.501.003.1353; BKW.501.003.1355.
[494] BKW.501.003.1366.
[495] Exhibit D11, BKW.999.036.0001, par 309, 386 and 390.
[496] SAR.100.002.010475.
[497] Exhibit D4, BKW.999.025.0001, par 162 - 163; ts 1923 - 1924.
[498] SAR.100.007.014322; SAR.100.003.009048; SAR.100.003.009047; SAR.100.007.014321.
[499] SAR.100.007.014322.
[500] SAR.100.007.014322.
[501] BKW.501.003.2025.
[502] BKW.501.003.2025.
[503] BKW.632.050.6107.
[504] BKW.502.004.5916.
[505] Exhibit D4, BKW.999.025.0001, par 190.
[506] Exhibit D4, BKW.999.025.0001, par 193.
[507] BKW.501.003.3813.
[508] BKW.001.017.0025.
[509] Exhibit D11, BKW.999.036.0001, par 356 - 369; Exhibit D8, BKW.999.031.0001, par 504, 510 - 511; Exhibit D4, BKW.999.025.0001, par 226 - 228.
[510] Exhibit D11, BKW.999.036.0001, par 356 - 368; GOW.002.001.0063.

[511] SAR.100.007.014352.
[512] SAR.115.001.012675.
[513] BKW.001.018.0500.
[514] BKW.001.018.0500.
[515] BOS.501.002.5867.
[516] The report provided was RBB's report of 14 September 2009.
[517] BKW.501.003.6043.
[518] BKW.501.003.6043.
[519] SAL.502.001.000354; BOS.005.001.0037.
[520] BKW.501.003.6060.
[521] RSQ.007.0251.3752.
[522] BKW.501.003.6127.
[523] BKW.632.054.7262.
[524] BKW.632.054.7287.
[525] BKW.501.003.6468.
[526] BOS.501.002.3599.
[527] BOS.501.002.3599.
[528] RBB.501.001.4050.
[529] RBB.501.001.4050.
[530] Exhibit D4, BKW.999.025.0001, par 315.
[531] BKW.501.003.6678.
[532] Exhibit D11, BKW.999.036.000, par 415 - 417.
[533] BKW.501.003.6680.
[534] BKW.501.003.6527.
[535] SAR.100.007.007632.
[536] SAR.100.007.007634.
[537] BKW.501.003.8605.
[538] SAR.100.007.007022.
[539] SAR.100.007.007022.
[540] BKW.501.003.7775.
[541] SAR.100.007.007019.
[542] BOS.521.003.3121.
[543] BOS.521.003.3119; Exhibit D4, BKW.999.025.0001, par 330.
[544] BKW.501.003.7346.
[545] Exhibit D4, BKW.999.025.0001, par 339 - 341.
[546] Exhibit D6, BKW.999.005.0001, par 69 - 70.
[547] BOS.721.002.6402.
[548] BKW.501.003.8243.
[549] PLE.101.011.0001.
[550] This allegation relates to the late payment in response to drawdown request No 18 in respect of Payment Certificate 27 which was due for payment on 28 September 2009 but which was not paid until 16 October 2009.

[551] The Leasing Covenant Breach Assertion is the term adopted by Westgem to describe the allegation made by the Financiers to the effect that Westgem was in breach of the obligations imposed on it by cl 15.23 of the MOFA - 'the Leasing Covenant'. As I have found that the first Cost Overrun and the second Cost Overrun occurred it is not necessary for me to make a findings in relation to the Leasing Covenant.

[552] In particulars (v) Westgem referred to the Financiers' allegation that Westgem had breached the Leasing Covenant and in particulars (vi) and (vii) Westgem referred to the Financiers' allegations that Westgem was in breach of other obligations owed by it under the MOFA. As noted in the immediately preceding footnote, I have found that the first Cost Overrun and the second Cost Overrun occurred it is not necessary for me to make a findings in relation to the alleged breach of the Leasing Covenant or the breaches of the other provisions of the MOFA that had been relied upon by the Financiers to establish that Westgem was in breach of the MOFA.

[553] PLE.101.011.0001, par 297.

[554] PLE.101.011.0001, par 298.
[555] PLE.101.011.0001, par 302.

[556] Trade Practices Act 1974 (Cth) s 52; ASIC Act, s 12DA; FTA s 10.
[557] Trade Practices Act 1974 (Cth) s 4(2)(a); ASIC Act, s 12BA(2)(c); FTA s 5(4)(a).
[558] Butcher v Lachlan Elder Realty Pty Ltd [2004] HCA 60; (2004) 218 CLR 592.
[559] Butcher v Lachlan Elder Realty [109].
[560] Demagogue Pty Ltd v Ramensky [1992] FCA 851; (1992) 39 FCR 31, 32 (Black CJ).
[561] Miller & Associates Insurance Broking Pty Ltd v BMW Australia Finance Ltd [2010] HCA 31; (2010) 241 CLR 357 [20] (French CJ & Kiefel J).
[562] Miller & Associates Insurance Broking v BMW Australia Finance [21] (French CJ & Kiefel J).
[563] Poseidon Ltd v Adelaide Petroleum NL [1991] FCA 663; (1991) 105 ALR 25 (Burchett J); Miller & Associates Insurance Broking v BMW Australia Finance [21] (French CJ & Kiefel J).
[564] Miller & Associates Insurance Broking v BMW Australia Finance [21] (French CJ & Kiefel J).
[565] Lam v Ausintel Investments Australia Pty Ltd (1989) 97 FLR 458, 475.
[566] Demagogue Pty Ltd v Ramensky, 40 (Gummow J).
[567] Fraser v NRMA Holdings Ltd [1995] FCA 9; (1995) 55 FCR 452, 467G (Black CJ, Von Doussa & Cooper JJ).
[568] Campbell v Backoffice Investments Pty Ltd [2009] HCA 25; (2009) 238 CLR 304 [25] (French CJ).
[569] Owston Nominees No 2 Pty Ltd v Clambake Pty Ltd [2011] WASCA 76; (2011) 248 FLR 193 [60].
[570] Owston Nominees No 2 v Clambake [60].
[571] Campbell v Backoffice Investments [24] (French CJ).
[572] PLE.101.011.0001, par 292.
[573] In its opening written submissions Westgem contended at [69]: 'The Salta Stoppage and Salta Termination part of the case depends on the existence of at least the Second Alleged Cost Overrun'.
[574] Exhibit D8, BKW.999.031.0001, par 554.
[575] Clause 39 of the MOFA imposed limited obligations of confidentiality in respect of 'unpublished information or documents supplied by any Transaction Party'.
[576] PLE.101.011.0001, par 288, 291 - 292.
[577] SAL.020.001.0025.
[578] BOS.005.001.0801.
[579] SAR.100.007.014322.

[580] BKW.001.016.0431.
[581] ts 3731 - 3733, 3743 - 3744, and 3751.
[582] BKW.632.054.7262.
[583] Exhibit D11, BKW.999.036.0001, par 169, 190 - 191, and 231; exhibit D8, BKW.999.031.0001, par 489; exhibit D6, BKW.999.005.0001, par 81.
[584] See FTA s 9(1); Trade Practices Act 1974 (Cth) s 51A(1).
[585] RSQ.006.0002.0001.
[586] The Multi-Option Facility Limit was increased from $316 million to $446.6 million and the Overdraft (GST Float) Facility Limit was increased from $3 million to $5 million.

[587] BKW.001.019.0668.
[588] SUB.101.006.0001, par 319(a) & (b), 321 - 323 and 362 - 363.

[589] SUB.101.006.0001, par 319(a) & (b), 321 - 323 and 362 - 363.
[590] RSQ.007.0252.0001.
[591] BKW.651.001.0449 cl 2.1, 2.2 and 8.

[592] BKW.001.019.0668.
[593] BOS.512.003.8348.
[594] BOS.512.003.5231.

[595] BOS.512.003.5231.

[596] BKW.502.005.6654.
[597] BKW.632.054.3508.
[598] BKW.632.054.3510.
[599] BKW.632.054.6586.
[600] BKW.501.004.5555.
[601] Exhibit D1, BKW.999.003.0001, par 328 - 330.
[602] BKW.632.054.3538.
[603] BKW.502.012.2272; BKW.501.004.6934.

[604] BKW.502.012.2305.
[605] BKW.512.004.0101.
[606] BKW.001.022.0464.
[607] SAR.101.002.106655; SAR.117.001.0068.
[608] BKW.502.006.0287; BKW.502.006.0288.
[609] BKW.502.006.0354.
[610] BKW.632.027.4579.
[611] BKW.502.006.2117.
[612] Exhibit D5, BKW.998.004.000, par 85 and 91.
[613] BOS.521.003.7174; BOS.521.003.7170.
[614] BOS.521.003.7174.
[615] POU.100.002.1110.
[616] POU.100.002.1110.
[617] SAR.115.004.024292.
[618] BKW.502.006.1253.
[619] BKW.551.002.3525; BKW.551.002.3526.
[620] BOS.512.003.0345; SAR.115.001.004868.
[621] Exhibit D4, BKW.998.004.0001, par 99.
[622] BKW.001.025.0535.
[623] SAR.115.001.007108.
[624] SAR.101.002.116917.
[625] SAR.115.001.007112.
[626] SAR.115.001.007252.
[627] RSQ.007.0241.0001.
[628] RSQ.007.0241.0001, cl 2.1(g).
[629] RSQ.007.0241.0001, cl 9A.
[630] SAR.115.001.008219.
[631] BKW.501.006.0332.
[632] BKW.001.028.0087.
[633] BKW.001.028.0087.
[634] BKW.501.006.0332.
[635] BKW.551.002.4748.

[636] POU.100.002.1109.
[637] POU.100.002.1941; POU.100.003.0030.
[638] RSQ.007.0095.0001.
[639] BKW.501.006.1548.
[640] BKW.501.006.1548.
[641] RSQ.007.0331.0002; RSQ.007.0252.0088.
[642] RSQ.007.0331.0002.
[643] BKW.651.001.0449.
[644] SAR.115.001.008510.
[645] SAR.115.001.008522.
[646] BKW.502.007.4475.
[647] BKW.001.051.0089.
[648] BKW.502.007.4602.
[649] BKW.661.002.1832.
[650] BKW.632.053.7446.
[651] BKW.632.053.7446.
[652] SAR.115.001.008548.
[653] SAR.115.001.008805.
[654] BKW.501.006.6915; BKW.501.006.6950.
[655] BKW.501.006.6950.
[656] Exhibit D5, BKW.998.004.0001, par 116; Exhibit D6, BKW.999.005.0001, par 298, 303.
[657] BKW.551.002.6524 - under heading 'Background'.

[658] RSQ.006.0002.0001, cl 14.1(28).

[659] RSQ.006.0002.0001, cl 14.1(29).

[660] RSQ.006.0002.0001, cl 14.1(30).

[661] RSQ.006.0002.0001, cl 14.1(31).

[662] RSQ.006.0002.0351, cl 6.1(7).

[663] RSQ.006.0002.0351, cl 6.1(8).

[664] RSQ.006.0002.0351, cl 6.1(11).
[665] BKW.551.002.6510.
[666] BKW.551.002.6636.
[667] BKW.551.002.6524; BKW.501.006.7678.
[668] BKW.632.029.5317.
[669] Exhibit D1, BKW.999.003.0001, par 420(a), 420(b); ts 1758.
[670] ts 1747 - 1790.
[671] ts 1717, 1784.
[672] ts 1761 - 1762.
[673] ts 1764, 1788.
[674] Exhibit D1, BKW.999.003.0001, par 425.
[675] Exhibit D1, BKW.999.003.0001, par 428.
[676] ts 1778 - 1780.
[677] Exhibit D5, BKW.998.004.000, par [110] - [111].
[678] ts 2056.
[679] ts 2050 - 2051.
[680] ts 2056.
[681] ts 2060.
[682] ts 2070.
[683] ts 2070.
[684] ts 2072.
[685] ts 2074.
[686] ts 2074, 2096.
[687] ts 2080.
[688] BOS.521.003.7174; BOS.611.001.5298.
[689] ts 2022.
[690] ts 2033, 2038.
[691] Mr Mahaffy was in the process of receiving treatment for a serious illness.
[692] BKW.001.051.0089.
[693] ts 2057.
[694] ts 2096.
[695] BKW.501.004.5555.
[696] ts 1786.
[697] ts 2054.
[698] BKW.004.002.0060.
[699] BKW.501.006.7910; BKW.501.006.7913.
[700] BKW.501.006.7912.
[701] BKW.501.006.7913.
[702] BKW.004.002.0057.
[703] BKW.501.006.8061.

[704] BKW.581.001.5220.

[705] BKW.004.002.0052.
[706] BKW.501.006.9176.
[707] PLE.101.011.0001, par 333.

[708] To the extent that there were any textual differences between the version of the ASIC Act cited above (incorporating amendments up to Act No 116 of 2008) and the version of the ASIC Act applicable during the period of the conduct giving rise to the MOFA Redocumentation claims, they are of no material significance.
[709] Serventy v Commonwealth Bank of Australia [No 2] [2016] WASCA 223 (Newnes JA, Murphy JA & Beech J) [20].
[710] Permanent Mortgages Pty Ltd v Vandenbergh [2010] WASC 10; (2010) 41 WAR 353.
[711] Permanent Mortgages Pty Ltd v Vandenbergh [214].
[712] Provident Capital Ltd v Papa [2013] NSWCA 36; (2013) 84 NSWLR 231.

[713] BKW.996.012.0001 (counterclaim), par 47.

[714] BKW.996.012.0001 (counterclaim), par 44.

[715] BKW.996.012.0001 (counterclaim), par 45, 46 & 48.

[716] BKW.996.012.0001 (counterclaim), par 49 & 50.
[717] BKW.996.012.0001 (counterclaim), par 53 & 54.

[718] BKW.996.012.0001 (counterclaim), par 51.
[719] BKW.996.012.0001 (counterclaim), par 52.
[720] DEF.201.041.0001, par 286 - 287.
[721] SUB.101.006.0001, par 381 - 394.

[722] BKW.001.051.0089.
[723] DEF.201.041.0001, 279.
[724] I & L Securities Pty Ltd v HTW Valuers (Brisbane) Pty Ltd [2002] HCA 41; (2002) 210 CLR 109 [33].
[725] Leadenhall Australia Ltd v Peptech Ltd [2001] NSWCA 272; (2001) 39 ACSR 265.
[726] I say 'essentially' to allow for the variations to the Restated MOFA terms effected by the 13 October 2010 Letter Agreement.
[727] PLE.101.011.0001, Part G1A.
[728] PLE.101.011.0001, par 406 - 411C.

[729] PLE.101.012.0001, 222, par 97.

[730] PLE.101.008.0001, pars 12, 21, 30 and 32.

[731] PLE.101.008.0001, pars 10xxiii, 13, 22, 30 and 32; par 14, 23, 30 and 32.

[732] PLE.101.008.0001, pars 15, 24, 30 and 32.

[733] PLE.101.008.0001, pars 10lxxvi, 17, 25, 30 and 32.

[734] PLE.101.008.0001, pars 18.1, 26, 30, 31 and 32.

[735] PLE.101.008.0001, pars 18.2, 27, 30, 31 and 32.

[736] PLE.101.008.0001, pars 19, 28, 30, 31, 32 and 33.

[737] PLE.101.008.0001, pars 20, 29, 30, 31, 32 and 33.
[738] Demondrille Nominees Pty Ltd v Shirlaw [1997] FCA 1220; (1997) 25 ACSR 535, 547 - 548.

[739] It was necessary for Westgem to establish both insolvency and uncommerciality of the transactions because an insolvent transaction must either be an unfair preference or an uncommercial transaction and Westgem did not suggest that there was an unfair preference (see Corporations Act, s 588FC). Although there was some equivocation in Westgem's position, this point was accepted in oral closing submissions.

[740] Southern Cross Interiors Pty Ltd v Deputy Commissioner of Taxation [2001] NSWSC 621; (2001) 53 NSWLR 213 [54]; Queensland Phosphate Pty Ltd v Korda [No 2] [2019] VSCA 215 [99]; Bell Group Ltd (in liq) v Westpac Banking Corporation [No 9] [2008] WASC 239; (2008) 39 WAR 1.
[741] Trinick v EM & RM Williams & Sons [2009] WASC 297 [104]; Lee Kong v Pilkington (Australia) Ltd (1997) 25 ACSR 103, 120.
[742] Hymix Concrete Pty Ltd v Garritty (1977) 13 ALR 321, 328.
[743] Southern Cross Interiors Pty Ltd v Deputy Commissioner of Taxation [2001] NSWSC 621; (2001) 53 NSWLR 213.
[744] Southern Cross Interiors [34].
[745] Southern Cross Interiors [54].
[746] Powell v Fryer [2001] SASC 59; (2001) 37 ACSR 589 [75] (Olsson J, Duggan & Williams JJ agreeing).
[747] Perrine v Carrello [2017] WASCA 151 [56] - [57] (Martin CJ, Mitchell & Beech JJA).
[748] Perrine v Carrello [57] - [58].
[749] Re New World Alliance Pty Ltd; Sycotex Pty Ltd v Baseler [No 2] [1994] FCA 332; (1994) 51 FCR 425.
[750] Re New World Alliance Pty Ltd; Sycotex Pty Ltd v Baseler [No 2], 434.
[751] JTS Property & Investments No 1 Pty Ltd (in liq) v Sadri [2010] NSWSC 1384.
[752] JTS Property & Investments No 1 Pty Ltd (in liq) v Sadri [48] - [50].
[753] Hussain v CSR Building Products Ltd [2016] FCA 392; (2016) 246 FCR 62.
[754] Bell Group v Westpac [No 9] [1090].
[755] Williams v Scholz [2008] QCA 94.
[756] Williams v Scholz [110].
[757] International Cat Manufacturing (in liq) v Rodrick [2013] QCA 372; (2013) 97 ACSR 200 [104].
[758] Chan v First Strategic Development Corporation Ltd (in liq) [2015] QCA 28.
[759] Chan v First Strategic Development Corp [43] - [44].

[760] Mulherin v Bank of Western Australia Ltd [2006] QCA 175. The High Court has relevantly observed in other contexts that cash flow is the lifeblood of the construction industry. Put another way, any interruption to the cash flow of a person carrying out construction work is apt to create the risk of financial failure (Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd [2018] HCA 4; (2018) 264 CLR 1 [40] (Kiefel CJ, Bell, Keane, Nettle & Gordon JJ).

[761] Mulherin v Bank of Western Australia Ltd [115] (footnotes omitted).
[762] Trinick v EM & RM Williams & Sons [101].
[763] Australian Securities and Investments Commission v Edwards [2005] NSWSC 831; (2005) 54 ACSR 583 [99].
[764] Melbase Corporation Pty Ltd v Segenhoe Ltd [1995] FCA 1225; (1995) 17 ACSR 187, 198 (Lindgren J).
[765] Sandell v Porter [1966] HCA 28; (1966) 115 CLR 666, 670 - 671 (Barwick CJ); Bell Group v Westpac [No 9] [1124] - [1129] (Owen J).
[766] Lewis v Doran [2005] NSWCA 243; (2005) 219 ALR 555.
[767] Lewis v Doran [103].
[768] Bell Group v Westpac [No 9] [1115] - [1118].
[769] Pearce v Gulmohar Pty Ltd [2017] FCA 660 [153].
[770] Bank of Australasia v Hall [1907] HCA 78; (1907) 4 CLR 1514, 1543.
[771] Re Timbatec Pty Ltd [1974] 1 NSWLR 613.
[772] See also Pearce v Gulmohar [154].
[773] Pearce v Gulmohar [153].
[774] Switz Pty Ltd v Glowbind Pty Ltd [2000] NSWSC 222.
[775] Switz Pty Ltd v Glowbind Pty Ltd [28].
[776] Switz Pty Ltd v Glowbind Pty Ltd [37] - [39].
[777] Re Adnot Pty Ltd (1982) 7 ACLR 212.
[778] Re Legend International Holdings Inc (in liq) [2018] VSC 789.
[779] Re Legend International Holdings [2018] VSC 789 [123]. Referring to Re Adnot Pty Ltd (1982) 7 ACLR 212; Taylor v Carroll (1991) 6 ACSR 255; Jingellic Minerals NL v Beach Petroleum NL [1991] SASC 3099; (1991) 56 SASR 532.
[780] Queensland Phosphate Pty Ltd v Korda [No 2] [124].
[781] Queensland Phosphate Pty Ltd v Korda [No 2] [101].

[782] PLE.101.008.0001, pars 9 and 10.

[783] PLE.101.008.0001, par 15A.

[784] PLE.101.008.0001, par 11.
[785] RSQ.007.0387.0120, 32.
[786] BKW.902.003.0001.
[787] Clutha Ltd (in liq) v Millar [No 5] [2002] NSWSC 833; (2002) 43 ACSR 295; Saraceni v Jones [2012] WASCA 59; (2012) 42 WAR 518 [168] (McLure P).
[788] BKW.006.002.0001, par 9.
[789] BKW.006.002.0001, par 9(f).

[790] BKW.996.002.0001, pars 10(a) - (c), 64 - 65.
[791] DEF.201.041.0001, par 66.

[792] DEF.201.041.0001, pars 51 - 61.

[793] DEF.201.041.0001, pars 82 - 85.

[794] DEF.201.041.0001, par 80.

[795] DEF.201.041.0001, par 93.

[796] DEF.201.041.0001, par 96(b).

[797] DEF.201.041.0001, par 96(d) and (g).
[798] DEF.201.041.0001, par 69.
[799] BKW.001.013.0424.

[800] BKW.632.051.4499, par 8.

[801] BKW.001.013.0384.
[802] Exhibit D1, BKW.999.003.0001, par 124.
[803] BKW.708.001.1803.
[804] BKW.708.001.1803.
[805] Exhibit D1, BKW.999.003.0001, par 128.
[806] Exhibit D8, BKW.999.031.0001, par 345.
[807] RSQ.007.0389.0034.
[808] These findings are made on the basis of the invoices attached to the Raine Square Bankwest Drawdown notice No 20 - SAR.114.005.065226.

[809] SAR.115.001.002523.

[810] RSQ.007.0389.0020.

[811] PLE.101.008.0053.

[812] PLE.101.008.0053.

[813] RSQ.007.0389.0035.

[814] RSQ.007.0389.0034.

[815] PLE.101.008.0053.

[816] To facilitate payment of the $17 million by tranches of $5 million by 31 January, $5 million by 28 February and $7 million by 15 March 2010.

[817] BOS.712.001.2730.

[818] Corporations Act, s 588E.

[819] ts 1721 - 1722.

[820] SAR.115.001.003786.

[821] SAR.103.004.026790.
[822] DEF.201.041.0001, 344.
[823] Demondrille Nominees v Shirlaw, 547 - 548.
[824] Featherstone v Ashala Model Agency Pty Ltd (in liq) [2017] QCA 260; [2018] 3 Qd R 147 [62] - [63] (Sofronoff P, Morrison JA agreeing).
[825] Queensland Phosphate Pty Ltd v Korda [No 2] [164].
[826] McDonald v Hanselmann [1998] NSWSC 171; (1998) 144 FLR 463.
[827] McDonald v Hanselmann, 466 - 467.
[828] White v ACN 153 152 731 Pty Ltd [2018] WASCA 119; (2018) 53 WAR 234.
[829] Cussen v Commissioner of Taxation [2004] NSWCA 383; (2004) 51 ACSR 530.
[830] Buzzle Operations Pty Ltd (in liq) v Apple Computer Australia Pty Ltd [2010] NSWSC 233; (2010) 238 FLR 384 [222] (White J); Re Kazar, in the matter of Frontier Architects Pty Ltd (in liq) [2010] FCA 1381; (2010) 81 ACSR 158 [20] (Flick J).
[831] RSQ.007.0387.0120, 25.
[832] RSQ.007.0107.0001.
[833] SAR.100.002.008191.

[834] BKW.632.023.1250.
[835] BKW.501.003.1771.
[836] Capital Finance Australia Ltd v Tolcher [2007] FCAFC 185; (2007) 164 FCR 83. But see Capital Finance Australia Ltd v Tolcher  [2008] HCATrans 316. 
[837] Capital Finance Australia Ltd v Tolcher [120].
[838] Kalls Enterprises Pty Ltd (in liq) v Baloglow [2007] NSWCA 191; (2007) 63 ACSR 557 [237] (Basten JA).
[839] Cussen v Sultan [2009] NSWSC 1114; (2009) 74 ACSR 496 [21].
[840] Re Emanuel [No 14] Pty Ltd (in liq); Macks v Blacklaw & Shadforth Pty Ltd [1997] FCA 667; (1997) 147 ALR 281.
[841] Re Emanuel [No 14] Pty Ltd (in liq), 288 - 289.
[842] Hosking v Extend N Build Pty Ltd [2018] NSWCA 149; (2018) 128 ACSR 555 [108].
[843] Kalls Enterprises Pty Ltd (in liq) v Baloglow [2007] NSWCA 191; (2007) 63 ACSR 557.
[844] See also Capital Finance Australia Ltd v Tolcher [71] (Lindgren J - dissenting in the result).
[845] Cashflow Finance Pty Ltd v Westpac Banking Corporation [1999] NSWSC 671 [519] - [521].
[846] The issue, discussed in Great Investments Ltd v Warner [2016] FCAFC 85; (2016) 243 FCR 516 [141], as to whether s 588FF(1) confers a discretion or a jurisdiction was not raised in this case. The weight of intermediate appellate authority supports the view that the subsection confers a discretion, and that is the basis upon which I will proceed.

[847] Acts Interpretation Act 1901 (Cth) s 15AA.
[848] New South Wales Aboriginal Land Council v Minister Administering the Crown Lands Act [2016] HCA 50; (2016) 260 CLR 232 [33] citing Victims Compensation Fund Corporation v Brown [2003] HCA 54; (2003) 201 ALR 260, 269.

[849] RSQ.006.001.0030, cl 15.15, 18.1(3).
[850] BKW.521.005.8518.

[851] RSQ.007.0095.0001.
[852] RSQ.006.0002.1145.
[853] SUB.101.005.0001, par 18.
[854] RSQ.006.0002.1174.
[855] RSQ.006.0002.1174.

[856] RSQ.006.0002.1174, cl 2.2(a).
[857] RSQ.006.0002.1174, cl 2.3(a).

[858] RSQ.006.0002.1174, cl 2.5.

[859] RSQ.006.0002.1174, cl 2.2(c) and (d).

[860] RSQ.006.0002.1174, cl 2.2(d).

[861] RSQ.006.0002.1174, cl 2.3(b).

[862] RSQ.006.0002.1174, cl 5.

[863] RSQ.006.0002.1174, cl 2.6.

[864] RSQ.006.0002.1174, cl 6.

[865] The Multi-Option Facility Limit was increased from $316 million to $446.6 million and the Overdraft (GST Float) Facility Limit was increased from $3 million to $5 million.
[866] RSQ.006.0002.0001, cl 2.1.

[867] RSQ.006.0002.0001, cl 9.1, Schedule 4.

[868] RSQ.006.0002.0001, cl 1.1(15), cl 2.1, Schedule 3 (14)(a).

[869] RSQ.006.0002.0001, cl 1.1(82).

[870] RSQ.006.0002.0001, cl 19.2.

[871] RSQ.006.0002.0001, cl 19.3.

[872] RSQ.006.0002.0001, cl 19.4.

[873] RSQ.006.0002.0001, cl 19.5; BKW.502.007.0520.

[874] RSQ.006.0002.0001, cl 19.6 and security trustee fee letter.

[875] RSQ.006.0002.0001, cl 15.20(2), 133.2(7), 1.1(7), (125), (143) and Schedule 5.

[876] RSQ.006.0002.0001, cl 15.15,1.1(1), 1.1(68).

[877] BKW.503.002.0004 at cell AY63.
[878] RSQ.007.0389.0069 - Balance sheet as of 19 August 2010.

[879] RSQ.007.0342.0002.
[880] SAR.102.002.007009.
[881] SAR.117.001.2858.
[882] SAR.101.002.123404.

[883] Emanuel Management Pty Ltd (in liq) v Foster's Brewing Group Ltd [2003] QSC 205; (2003) 178 FLR 1.
[884] Emanuel Management Pty Ltd (in liq) v Foster's Brewing Group Ltd [620].
[885] Emanuel Management Pty Ltd (in liq) v Foster's Brewing Group Ltd [621].
[886] Re Essendon Apartment Developments Pty Ltd (in liq) [No 2] [2013] VSC 210.
[887] Guardian Mortgages Pty Ltd v Miller [2004] NSWSC 1236.
[888] Guardian Mortgages v Miller [104]. See also Takemura v National Australia Bank Ltd [2003] NSWSC 339; Accom Finance Pty Ltd v Mars Pty Ltd [2007] NSWSC 726 [54].

[889] As the discussion of Chesterman J in Emanuel Management reveals.

[890] White v ACN 153 152 731 Pty Ltd [106]

[891] White v ACN 153 152 731 Pty Ltd [107].

[892] White v ACN 153 152 731 Pty Ltd [108].

[893] White v ACN 153 152 731 Pty Ltd [109].

[894] White v ACN 153 152 731 Pty Ltd [111]; Queensland Bacon Pty Ltd v Rees [1966] HCA 21; (1966) 115 CLR 266, 303 - 304.

[895] White v ACN 153 152 731 Pty Ltd [112].

[896] White v ACN 153 152 731 Pty Ltd [117]-[118] citing George v Rockett [1990] HCA 26; (1990) 170 CLR 104 [111] - [113].

[897] White v ACN 153 152 731 Pty Ltd [122].

[898] Cussen v Commissioner of Taxation [2004] NSWCA 383; (2004) 51 ACSR 530. White v ACN 153 152 731 Pty Ltd [123].

[899] The Western Australian Court of Appeal added that the objective circumstances may include the nature and practices of the industry in which the relevant transactions occurred, in so far as they are established as objective matters of fact but not merely the creditor's subjective views as to the operation of the industry and its practices: White v ACN 153 152 731 Pty Ltd [124].

[900] White v ACN 153 152 731 Pty Ltd [125].
[901] White v ACN 153 152 731 Pty Ltd [126].
[902] Pegulan Floor Coverings Pty Ltd v Carter (1997) 24 ACSR 651, 658 (Doyle CJ).

[903] BKW.001.013.0424.

[904] BKW.501.003.0835.

[905] BKW.632.050.6107.

[906] BOS.501.002.3552.

[907] ts 1723, 1735 - 1736, 1740 - 1741.

[908] ts 1994, 2065 - 2068.

[909] BOS.521.003.7174.

[910] SAR.115.001.005453; SAR.115.001.006387.

[911] ts 1723.
[912] ts 1735 - 1736.
[913] ts 1740 - 1741.
[914] DEF.201.041.0001, par 211.
[915] ts 1993 - 1994.
[916] ts 2064 - 2066
[917] ts 2068.
[918] BKW.501.004.5555.
[919] BKW.999.019.0001.
[920] BKW.661.004.2420; RSQ.007.0302.0457; RSQ.007.0302.0457.
[921] BKW.661.004.2433.
[922] BKW.661.004.2126.

[923] BKW.661.004.2162.

[924] BKW.661.004.2162, 2169.

[925] BKW.661.004.2162, 2213.

[926] BKW.661.004.2162, 2175.

[927] BKW.661.004.2162, 2251.

[928] BKW.661.004.2162, 2288.

[929] BKW.661.004.2162, 2294.

[930] BKW.661.004.2162, 2299.

[931] BKW.661.004.2162, 2304.

[932] BKW.661.004.2162, 2309.
[933] BKW.661.004.2315.

[934] BKW.661.004.2372.

[935] BKW.661.004.2400.

[936] BKW.661.004.2418.
[937] RSQ.006.0002.0001.
[938] BOS.013.001.0030.
[939] BOS.014.001.0421.
[940] BOS.014.001.0421.
[941] BOS.014.001.0421.
[942] BOS.014.001.0421.
[943] BOS.012.001.0246.
[944] BKW.551.003.0458.

[945] BKW.661.004.2444.

[946] BOS.014.001.0421.

[947] BOS.012.001.0542.

[948] BOS.012.001.0682.
[949] BKW.661.004.2444.

[950] BOS.013.001.0030.

[951] BOS.012.001.0246.

[952] BOS.012.001.0276.

[953] BOS.014.001.0252.
[954] BKW.661.004.2444.

[955] BOS.014.001.0252.

[956] BOS.012.001.0612.
[957] BKW.661.004.2444.

[958] BOS.013.001.0794.

[959] BOS.012.001.0310.
[960] BKW.661.004.2444

[961] BOS.013.001.0747.

[962] BOS.012.001.0358.
[963] BKW.661.004.2465.
[964] BKW.661.004.2474.
[965] BKW.661.004.2488.
[966] BKW.661.004.2490.
[967] BKW.661.004.2493.
[968] BKW.661.004.2162.
[969] BKW.661.003.6428.
[970] BKW.700.004.0359.
[971] BKW.502.012.8478; BKW.502.012.8475; BKW.502.012.8488.
[972] BKW.661.002.7533; BKW.661.002.7530; BKW.661.002.7536.


AustLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.austlii.edu.au/au/cases/wa/WASC/2020/302.html