Home
| Databases
| WorldLII
| Search
| Feedback
New South Wales Civil and Administrative Tribunal - Appeal Panel |
Last Updated: 26 November 2015
|
Civil and Administrative Tribunal New South Wales
|
Case Name:
|
Steele & Associates Pty Ltd v Heath
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
9 September 2105
|
Date of Orders:
|
10 November 2015
|
Decision Date:
|
10 November 2015
|
Jurisdiction:
|
Appeal Panel
|
Before:
|
A Coleman SC, Senior Member
P Boyce, Senior Member |
Decision:
|
1. Appeal dismissed
2. There be no order as to costs of the appeal. 3. The limited stay granted by order 4 made on 7 May 2015 is lifted with the intent that there is no stay of the Tribunals original orders. |
Catchwords:
|
CONTRACT- whether repudiation or non-performance of contractual obligations
precludes claim under warranties implied by Home Building
Act. PROCEDURE-
procedural fairness- right to cross-examine – whether party denied
procedural fairness. HOME BUILDING ACT –
implied warranties.
|
Legislation Cited:
|
|
Cases Cited:
|
Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613
Britannia v Parkline Constructions Pty Ltd [2009] NSWSC 1302 Collins v Urban [2014] NSWCATAP 17 Gallo v Duflou [2014] NSWCATAP 115 John Prendergast & Vanessa Prendergast v Western Murray Irrigation Ltd [2014] NSWCATAP 69 Keith v Gal [2013] NSWCA 339 The Owners Strata Plan No 76674 v Di Blasio Constructions Pty Ltd [2014] NSWSC 1067 |
Category:
|
Principal judgment
|
Parties:
|
Steele Associates Pty Ltd (Appellant)
Timothy Heath (Respondent) |
Representation:
|
Counsel:
Ms Clarke (Appellant) Mr De Buse (Respondent) Solicitors: Melanie J Palmer & Associates (Appellant) Watson & Watson, Solicitors (Respondent) |
File Number(s):
|
AP 15/07259
|
Decision under appeal:
|
|
Court or Tribunal:
|
NSW Civil & Administrative Tribunal
|
Jurisdiction:
|
Consumer & Commercial Division
|
Citation:
|
Timothy Heath v Steele Associates Pty Ltd [2015] NSWCATCD 8
|
Date of Decision:
|
13 January 2015
|
Before:
|
S Thode, Senior Member
|
File Number(s):
|
HB 13/5555; HB 13/51291
|
REASONS FOR DECISION
Overview
The Proceedings Below
4. The parties acknowledge and agree that:
(i) [Mr Heath] has paid the [original builder] $3,143,891 being all amounts due to the [original builder] from [Mr Heath] under the Contract at the date of this deed; and
(ii) [Mr Heath] will pay the [appellant] $120,936 in respect of [Mr Heath's] outstanding obligations under the Contract.
The Material Before the Appeal Panel
Is Leave to Appeal Required?
Grounds of Appeal
Ground 2
The Tribunal erred at law in its decision that the owners were entitled to be paid monies by the builder on account of breaches of statutory warranty, as defined by section 18 (sic) of the Home Act, in that:
(a) The Tribunal found that the alleged repudiation by the owners of the building contract with the builder was irrelevant to the consideration of whether the owners were entitled to damages for breach of statutory warranty;
(b) The Tribunal found that the failure on the part of the owners to mitigate their loss under the contract with the builder was irrelevant to the consideration of whether the owners were entitled to damages for breach of statutory warranty;
(c) The Tribunal found that despite the fact that the owners had failed to follow the correct contractual procedure under the contract with the builder to set off any alleged cost for defective workmanship against monies owed to the builder under the contract, the owners were still entitled to damages for breach of statutory warranties
Ground 3
And in making the findings referred to in [ground] 2 above, the Tribunal erred at law, in that:
the fact that the owners had repudiated by unlawfully terminating the contract with the builder, the owners were not entitled to any damages for breach of statutory warranty as their loss was occasioned by their own conduct;
the fact that the owners had failed to mitigate their loss by refusing to allow the builder to remedy the defect to the glass panels of the swimming pool, meant that the owners’ loss was occasioned as a result of their own conduct and not the conduct of the builder...
[81] Even though it was open to the plaintiffs to seek damages for defective work which was the result of the breach of statutory warranties, notwithstanding that they did not pursue the procedures for rectification under clause 6.11, it was still necessary for the plaintiffs to show that the carrying out of rectification work by a third party was necessary and reasonable (Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613 at 619; Westpoint Management Ltd v Chocolate Factory Apartments Ltd [2007] NSWCA 253 at[45]). Moreover, if the defective work was included on one of the lists given by the architect pursuant to clause 6.11, Parkline was both obliged and entitled to do the work. It is one thing to say that s 18G precludes the plaintiffs from being compelled to follow the procedures in clause 6.11 in the case of a breach of statutory warranty. It is another to say that the section enables the plaintiffs to ignore procedures in clause 6.11 once they have been invoked.
Contractor’s obligations during and after defects liability period
1 If there is any remaining *defect or incomplete work, or the contractor becomes aware by instruction from the architect or from its own observations of any *defect or incomplete work during the defects liability period, it must *promptly return to the *site and correct the defect or finalise the incomplete work. This obligation continues until the *defect is rectified all the incomplete work is finalised, and does not come to an end when the defects liability period is over.
2 The architect cannot give the first instruction to correct an outstanding *defect or to finalise any incomplete work after the end of the defects liability period, unless it is for the rectification of a latent *defect and the final certificate has not been issued." (bold emphasis added)
[44] In the case of building contracts, it is also generally accepted that the owner must give the builder a reasonable opportunity to rectify any defects. Often, of course, the building contract itself requires the builder to repair defects or sets out a procedure by which defects are to be made good: see, e.g., Brittania Pty Ltd v Parkline Constructions Pty Ltd... But, even if it does not, the owner is required to give the builder an opportunity to minimise the damages it must pay by rectifying the defects, except where its refusal to give the builder that opportunity is reasonable or whether builder has repudiated the contract by refusing to conduct any repairs (references omitted). The obligation may be an aspect of the duty to mitigate, since it may be less expensive for the builder rather than a third party to rectify the defects, particularly if the builder is still on-site. But the obligation is not simply an aspect of the duty to mitigate. The cost to the builder of undertaking the repairs is likely to be less than the amount that a third party would charge the owner for the same work. In that case, the owner is not mitigate its loss, but rather the builders damages.
[45] The question of what is reasonable depends on all the circumstances of the particular case. One relevant factor is what attempts the builder has made to repair the defects in the past and whether, in the light of the builder's conduct, the owner has reasonably lost confidence in the willingness and ability of the builder to do the work (references omitted).
[46] It is for the defendants to prove that the plaintiff has acted unreasonably. It is not for the plaintiff to prove it acted reasonably.(references omitted).
[47] The obligation not to act unreasonably does not come to an end once court proceedings are commenced. But the existence of court proceedings is relevant to the content of the obligation. Once there is a dispute concerning whether the plaintiff failed to mitigate it's lost, or failed to act reasonably in some other respect, the plaintiff is entitled to have a question tested in court; in the mid fact that it does so is not itself evidence that it has failed to act reasonably (references omitted).
[48] In the present case, the claim is for breach of the warranty is implied by the Act. However, it was not suggested by the party the different principles apply for that reason.
Ground 4
4. The Tribunal ended at law in that it found:
(a) That the contract was not repudiated by the owners but that the contract was finalised by each party completing its obligations under the contract, when there was still extant obligations of both parties under the contract;
(b) That both parties were in breach and therefore the contract was not repudiated by either party, when this proposition was never argued by either party, the Tribunal gave no notice that it will be deciding the matter on this point of law, and where this finding is against the authorities on what is relevant to obtaining damages for breach of statutory warranty.
Ground 5
5 The Tribunal erred at law in that it denied the builder procedural fairness, and acted in excess of jurisdiction, in that:
(a) Made a ruling that the parties be limited in their capacity to cross examine expert witnesses;
(b) Allow the builder limited time at the hearing to put its case;
(c) Made a finding that the builder had not contested the expert evidence of the owner when the builder had contested that evidence but was limited in his capacity to cross-examine the owners’ (sic) experts or put its own case by the previous rulings of the Tribunal limiting cross examination and by the Tribunal limiting the amount of time available to the builder to present its case.
MEMBER MEADOWS: All right (sic). Now, you both need to understand that you don't call your own witnesses, strangely enough. They have given statements or reports and you rely on those. You only need to have that witness available if the other side requires them for cross-examination, otherwise all the evidence just goes in and the tribunal makes its mind up. So if you know that your witness is not required for cross-examination then you don't have to call that weakness, you just file their evidence, that's all that's needed. Okay. You don't put him in the box-you can't get new evidence out of them, it's too late, and there's no point going through their report to say, "you said it's worth 10,000. Did you mean that?" You are just repeating what's in there. So do you follow that? So you may not need all the witnesses that you have unless someone wants to cross-examine them on their evidence.
MR STEELE: If I may ask about that, the cross-examining being the other side asking questions.
MEMBER MEADOWS: Yes
MR STEELE: does that mean it's up to me to call the other side's weaknesses advice first or I nominate witnesses to appear if I think the other side would want to cross-examine them.
MEMBER MEADOWS: No, the order will be that you will write to the other side and say, "I want to cross-examine witness X and witness Y".
MR STEELE: Yes
MEMBER MEADOWS: The other side then arranges for them to be present, and by reverse if they want to cross-examine your witnesses they write to you and the tribunal saying that, and you arrange for the witness to be present. If the other side requires a witness for cross-examination and the witness is not present a cross-examination, you won't be able to rely on the evidence so it's an important issue. But you decide of (sic) the other side's witnesses who you want. Of your own, you are just going to put in their documents, and if they are not required for cross-examination then you will only do that if you know you have got something that you think they are-not telling lies, but if you think they are weak on something.
MR STEELE: If you think something, kind of in the logic of it can be clarified really or changed through cross-examination, rather than just, as you say, saying, you know, "Do you really support that?"
MEMBER MEADOWS: Yes. You can't just say, "Did you really mean that?" You have got to have something that you really are going to be relying on.
MR STEELE: Yes.
MEMBER MEADOWS: If you require someone for cross-examination and you don't cross-examine them all your cross-examination is just a waste of time, then the other side may request the cost of that (indistinct) and the like. So that's an important issue. So the matter is adjourned for today...
MR STEELE: May I please make the point that my clear recollection from the last hearing was that we were going to run out of time regardless of the quantum meruit issue, and it was agreed that we come back for a half day, the first two hours of which would be devoted to giving me the opportunity to make verbal submissions, as Mr Heath had spent a large part of the first day, and then the final hour would be for Mr Heath to make a reply to my verbal submissions.
SENIOR MEMBER THODE: Only because we've run out of time.
MR STEELE: Sure. So my written submissions will be made in lieu on all issues that we would have covered in verbal submissions?
SENIOR MEMBER THODE: Yes. I think that-I have had time to go off the bench, reflect on my own notes, and reflect on the history of the file, and I'm quite comfortable that the proceedings have finished, and that we were coming back for submissions....
38 Procedure of Tribunal generally
(1) The Tribunal may determine its own procedure in relation to any matter for which this Act or the procedural rules do not otherwise make provision.
(2) The Tribunal is not bound by the rules of evidence and may inquire into and inform itself on any matter in such manner as it thinks fit, subject to the rules of natural justice.
(3) Despite subsection (2):
(a) the Tribunal must observe the rules of evidence in:
(i) proceedings in exercise of its enforcement jurisdiction, and
(ii) proceedings for the imposition by the Tribunal of a civil penalty in exercise of its general jurisdiction, and
(b) section 128 (Privilege in respect of self-incrimination in other proceedings) of the Evidence Act 1995 is taken to apply to evidence given in proceedings in the Tribunal even when the Tribunal is not required to apply the rules of evidence in those proceedings.
Note. Section 67 also prevents the compulsory disclosure of certain documents in proceedings in the Tribunal that would, in proceedings before a court, be protected from disclosure by reason of a claim of privilege.
(4) The Tribunal is to act with as little formality as the circumstances of the case permit and according to equity, good conscience and the substantial merits of the case without regard to technicalities or legal forms.
(5) The Tribunal is to take such measures as are reasonably practicable:
(a) to ensure that the parties to the proceedings before it understand the nature of the proceedings, and
(b) if requested to do so—to explain to the parties any aspect of the procedure of the Tribunal, or any decision or ruling made by the Tribunal, that relates to the proceedings, and
(c) to ensure that the parties have a reasonable opportunity to be heard or otherwise have their submissions considered in the proceedings.
(6) The Tribunal:
(a) is to ensure that all relevant material is disclosed to the Tribunal so as to enable it to determine all of the relevant facts in issue in any proceedings, and
(b) may require evidence or argument to be presented orally or in writing, and
(c) in the case of a hearing—may require the presentation of the respective cases of the parties before it to be limited to the periods of time that it determines are reasonably necessary for the fair and adequate presentation of the cases.
Ground 6
6. The Tribunal erred at law in that:
(a) It accepted the owners’ (sic) experts, Mr. Jacobs and Mr. Barnes, in respect of the cause of the defect to the swimming pool, and it rejected the builders expert evidence as to the cause of the defect without giving any reasons for doing so;
(b) It accepted the owners’ expert evidence on the quantum of loss incurred, and rejected the builders expert evidence on quantum, without giving any reason for doing so;
(c) It disclosed no logical basis for the acceptance of the owners’ expert evidence on the cause of the defects and the quantum of loss and why the Tribunal rejected the builders evidence on these issues.
The builder's method of rectification was rejected by both experts as the builder was unable to establish that the old sealant and the new sealant were able to bond satisfactorily to rule out new leaks. This is a reasonable conclusion to draw in light of all of the evidence and it was therefore reasonable by the owner to adopt a more costly repair method.
He also stated that “in all joint sealant replacement repairs the surfaces must be cleaned and be free of the old sealant material and any laitance”...
Conclusion
**********
I hereby certify that this is a true and accurate record of the reasons for
decision of the Civil and Administrative Tribunal of New
South
Wales.
Registrar
Amendments
26 November 2015 - Final paragraph quoted in paragraph 66 highlighted in bold.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWCATAP/2015/239.html