[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Land and Environment Court of New South Wales |
Last Updated: 4 December 2003
NEW SOUTH WALES LAND AND ENVIRONMENT COURT
CITATION: Austcorp No 459
Pty Ltd v Baulkham Hills Shire Council [2003] NSWLEC 318
PARTIES:
Austcorp No 459 Pty Ltd (Appl)
Baulkham Hills Shire Council
(Resp)
CASE NUMBER: 10351/02
10463 of 2003
CATCH
WORDS: Development Consent
LEGISLATION CITED:
Environmental
Planning and Assessment Act 1979
CORAM: McClellan CJ
DATES OF
HEARING: 13 November 2003
DECISION DATE: 28/11/2003
LEGAL
REPRESENTATIVES
M G Craig QC (Barrister - Appl)
Baker & McKenzie
(Solicitor - Appl)
P J McEwen SC (Barrister - Resp)
Maddocks
(Solicitor - Resp)
JUDGMENT:
- 9 -
IN THE LAND
AND
ENVIRONMENT COURT
OF NEW SOUTH
WALES
10463/03
10351/02
McCLELLAN
J
FRIDAY 28 NOVEMBER 2003
AUSTCORP No 459 PTY LTD
Applicant
v
BAULKHAM HILLS SHIRE COUNCIL
Respondent
JUDGMENT
Introduction
1 HIS HONOUR: The parties have raised
two questions for separate determination in these proceedings. The questions
are:
1. Whether in the event of the grant of development consent an
occupation certificate can issue in respect of the building.
2. If the answer
to the first question is no whether there is any utility in the
proceedings.
Background
2 On 2 November 1999 the court
granted development consent for the erection of a residential flat building
comprising 26 apartments
on property conveniently described as Lot 1 in DP
1035154. The development contemplated by that consent included 26 apartments in
two buildings, a swimming pool, basement car parking on two levels, and below
ground on-site detention for storm water.
3 After development consent
had been granted the applicant purchased the property, the transfer being
effected on 29 June 2000. On
12 September 2000 Mr Bernie Cohen of Essential
Certifiers Pty Limited purported to issue a construction certificate certifying
construction
plans pursuant to the development consent. However, there were a
number of differences between the construction plans and the development
consent. Those differences are summarised in the reasons for judgment of Cowdroy
J in proceedings 10007/99 dated 7 June 2002 ((2002)
[2002] NSWLEC 90; 122 LGERA 205 at 211 para
23). They included:
· Raising the top level of the storm water
detention tank by 2.5 metres above ground level instead of finishing at natural
ground
level with landscaping;
· Deletion of a swimming pool;
and
· Deletion of the lower basement level of car parking.
4 The
applicant proceeded to construct the development in accordance with the
construction certificate.
5 On 26 October 2001 the applicant applied for
consent from the council to the strata subdivision of the development. The
council
refused consent for the reason that the constructed development differed
from the development consent which had been granted by the
court.
6 On 18
December 2001 the applicant lodged an application seeking modification of the
1999 consent pursuant to s 96 of the Environmental Planning and Assessment
Act 1979. By this means retrospective authorisation for the departures from
the approved plans was sought (see Windy Dropdown Pty Ltd v Warringah Council
[2000] NSWLEC 240; (2000) 111 LGERA 299). On 7 June 2002 Cowdroy J refused to approve the
application for modification.
7 On 20 December 2001 the council commenced
proceedings seeking orders for demolition or rectification of the development.
On 20 December
2001 Bignold J declined to grant an interlocutory injunction
restraining future work on the property.
8 On 16 May 2002 the applicant
lodged an application for a building certificate for the development and on 8
July 2002 commenced proceedings
appealing against the deemed refusal of the
building certificate.
9 The applicant also lodged a development
application seeking development consent for the occupation of the buildings for
residential
purposes. That application was not considered by the council and an
appeal was lodged with the court.
10 At the present time there are three
proceedings in the court. They are:
1. Class 1 proceedings 10463/03
seeking development consent for occupation and some alterations to the existing
buildings designed
to meet the requirements of the relevant
authorities;
2. Class 1 proceedings 0351/02 seeking a building certificate
for the development as built and as it will be modified if consent is
granted
for alterations to the building;
3. Class 4 proceedings 40273/01 brought by
the council seeking orders for demolition or rectification of the
development.
11 The council submits that an occupation certificate cannot
be issued for the building even if the court approves alterations to
it and
grants development consent for occupation of the altered building. As I
understand it the council’s submission is that
although the building, when
altered, may comply with all relevant planning and building health and safety
laws and regulations it
could not be lawfully occupied and must be
demolished.
12 Before a building can be erected it will almost always be
the case that the local environmental plan will operate so that development
consent is required. Section 81A of the Act provides that a development consent
that enables the erection of a building is sufficient to authorise the use of
the
building when erected for the purpose which was specified in the development
application. However, s 81A(1) makes the provision expressly subject to s 109M.
That section prohibits the occupation or use of a new building unless an
occupation certificate has been issued.
13 Section 81A(2) provides that
the erection of a building in accordance with the development consent must not
be commenced until a construction certificate
has been issued. The subsection
provides as follows:
“(2) The erection of a building in
accordance with a development consent must not be commenced
until;
(a) a construction certificate for the building work has
been issued by:
(i) the consent authority,
or
(ii) an accredited certifier, and
(b) the person
having the benefit of the development consent;
(i) has appointed a
principal certifying authority, and
(ii) has notified the consent
authority and the council (if the council is not the consent authority) of the
appointment, and
(c) the person having the benefit of the
development consent has given at least two days notice to the council of the
person’s
intention to commence the erection of the
building.”
14 Regulations have been made concerning the issue
of construction certificates.
15 Part 4A of the Act provides for the
certification of development. Various certificates are contemplated. Section
109C(1)(b) provides
that a “construction certificate” is “a
certificate to the effect that the work completed in accordance with the
specified plans and specifications will comply with the requirements of the
regulations referred to in s 81A(5).”
16 Occupation certificate is
defined in s 109C(1)(c) as being “a certificate that authorises: (i) the
occupation or use of a
new building, or (ii) a change of building use for an
existing building.” “New building” is not defined although
s
109C(4) provides that a new building:
“Includes an altered
portion of, or an extension to, an existing building.”
17 An
occupation certificate may be an interim or final certificate and may be issued
for the whole or only part of a building (s
109C(2)).
18 Section 109H
provides for the circumstances in which an occupation certificate can be issued.
The section provides as follows:
“109H Restriction on issue of
occupation certificates
(1) A final occupation certificate must
not be issued to authorise a person to commence occupation or use of a new
building unless
the certifying authority is satisfied:
(a) that a
development consent or complying development certificate is in force with
respect to the building, and
(b) in the case of a building erected
pursuant to a development consent but not a complying development certificate,
that a construction
certificate has been issued with respect to the plans and
specifications for the building, and
(c) that the building is suitable
for occupation or use in accordance with its classification under the Building
Code of Australia,
and
(d) that such other matters as are required by
the regulations to be complied with before such a certificate may be issued have
been
complied with.
(2) A final occupation certificate must not be
issued to authorise a person to commence a change of building use for an
existing building
unless the certifying authority is
satisfied:
(a) that a development consent or complying development
certificate is in force with respect to the change of building use,
and
(b) that the building is suitable for occupation or use in
accordance with its classification under the Building Code of Australia,
and
(c) that such other matters as are required by the regulations to
be complied with before such a certificate may be issued have been
complied
with.
(3) An interim occupation certificate must not be issued to
authorise a person:
(a) to commence occupation or use of a
partially completed new building,
(b) to commence a change of building
use for part of an existing building.
Unless the certifying
authority is satisfied that such matters as are required by the regulations to
be complied with before such
a certificate may be issued have been compiled
with.
(4) In this section:
‘New
building’ includes an altered portion of, or an extension to, an existing
building.”
19 Section 109M makes it an offence for a person to
occupy or use the whole or any part of a new building unless an occupation
certificate
has been issued.
20 In the present case, as I understand it,
the building which has been built conforms with the construction certificate
which was
issued but that certificate does not conform with the development
consent. Accordingly parts of the building which have been built
are not
authorised by any relevant development consent. In one of the class 1
proceedings, that position is proposed to be rectified,
consent being sought to
alter the buildings which have been built. It is agreed that a construction
certificate may then be issued
to authorise construction of the alterations to
the already constructed building.
21 It is also proposed that development
consent to use the building, including the alterations, will be sought. This
would follow
as a matter of course in relation to any approved alterations. (s
81A(1))
22 The applicant makes three submissions. It is submitted that s
109H is not a constraint because:
“Section 109H(1) requires the
certifier to be satisfied as to certain matters before an occupation certificate
may be issued
to legitimise occupation or use of a new building. If the building
in question is not a new building, then an occupation certificate
may still be
issued, but the certifier is not bound to be satisfied as to the s 109H(1)
matters.
Hence, if the Built Development is not a new building,
then the certifier need not be constrained by the matters listed in s 109H(1),
and can issue an occupation certificate for the Built Development without
impediment under s 109H(1). The certifier will only need
to consider the s
109H(1) matters in relation to the rectification works. These will be
constructed pursuant to certified construction
plans, and will be capable of
being subject to an occupation certificate.
New building is not
defined, other than by s 109H(4) to include an alteration of, or an extension
to, an existing building.
Section 109H(4) does not give any
indication of when the Built Development might have ceased to be a new building
and has become an
existing building. Whether the Built Development is a new
building for the purposes of s 109H is best determined by its
age.
The Built Development has existed since October 2001. It is
now 2 years old. It is an existing, not a new, building.
In
circumstances where the Approved Development is ultimately assessed under s 79C
of the EP & A Act to be worthy of occupation,
it does no injustice to the EP
& A Act to allow it to be occupied with an occupation certificate issued
without constraint by
s 109H(1) (save in so far as it relates to the
rectification works) on the basis that it was no longer a new
building.”
23 It is further submitted by the applicant that if
development consent to use the building is granted the development consent
required
by s 109H(1)(a) will exist. It is submitted that s 109H(1)(a), when it
refers to development consent, is referring only to consent
to use the building
and s 109H(1)(b) is concerned with consent to erect it.
24 It is conceded
by the applicant that the present building has not been erected in accordance
with the existing development consent
as contemplated by s 109H(1)(b) and
accordingly has not been erected pursuant to a development consent. Accordingly
it is submitted
that, although if consent is granted to alter the building, s
109H(1)(b) may require a construction certificate before occupation
of the
altered sections it cannot require a construction certificate before occupation
of the part of the building erected without
development consent.
25 The
applicant emphasises the fact that although a building which has been
constructed without development consent has been constructed
in breach of the
Act, which may attract criminal sanctions, it may nevertheless be allowed by the
council to remain. Immunity from
demolition is available if a building
certificate is issued (s 149E). This obviously sensible provision ensures that a
community
resource, albeit privately owned, is not wasted by unnecessary
demolition. Criminal sanctions are available to discipline and punish
those who
break the law. The use and occupation of illegally constructed buildings is a
different matter.
26 Finally, the applicant submits that, although the
building may have been built, a construction certificate may still be issued.
Section 81A makes it an offence to build without a construction certificate but
it does not preclude the issue of such a certificate
after construction. All
that the certificate does is certify the plans, not the building, the certifier
is saying nothing as to the
actual building but merely expressing the requisite
conclusion with respect to building plans. The reference to the table in s 121B
in Section 2 to “prior construction certificate” is an indication
that a certificate may be issued after construction.
If it could only issue
before construction the inclusion of the word “prior” when
describing a certificate would be unnecessary.
27 Beyond these matters
the applicant submits that the current proceedings have utility
because:
“(a) A grant of development consent will have
potentially persuasive effect in the court’s exercise of its jurisdiction
in the class 4 proceedings no 40237/01; and
(b) A grant of
development consent will have potentially persuasive effect in the court’s
exercise of its jurisdiction in any
proceedings taken by any person to prevent
the Approved Development being occupied in future.”
28 The
respondent council has filed tightly reasoned written submissions. It is
submitted that the building, as built, is not old
and accordingly the argument
based on s 109H should not be accepted.
29 With respect to the argument
that because the building was built otherwise than in conformity with the
development consent s 109H(1)(b)
is not relevant the council submits the
following:
“The applicant’s assertion depends implicitly
upon construing ‘pursuant to’ to mean ‘in accordance
with’
or ‘consistent with’. Therefore, the argument runs, by
not constructing the development consistent with the consent,
the requirement
for a construction certificate does not arise.
If this is correct,
a developer can build outside the Act, ignore all of its requirements and yet be
rewarded with the fruits of that
illegality.
Rather, the meaning
of ‘pursuant to’ means ‘in reliance upon the authority
of’, as distinct from ‘in
accordance with’ or
‘consistent with’, to give foundation to the legislation being
implemented. The scheme requires
a development consent, followed by a
construction certificate, followed by construction in accordance with the terms
of the consent
and construction certificate and thereafter an occupation
certificate. Departure from these requirements result in
breach.
The respondent says that a final occupation certificate
cannot be issued consistently with the terms of section
109H(1).”
30 It is further submitted that a construction
certificate can only ever be issued before construction work is undertaken.
Emphasis
is placed on the regulations and the definition of “construction
certificate” in s 109C(1)(b) which uses the words “will
comply”.
31 Although I tentatively held a different view, I have
decided that at this stage of the proceedings it is not appropriate to finally
resolve the first question. As the final form of the development and the extent
to which it may be authorised by an existing development
consent, or a new one,
are unknown the factual context is uncertain. The final form of the development
and the extent it is approved
by a new development consent and authorised by a
construction certificate granted before the work is undertaken, may be
significant
in resolving the correct approach to the present
difficulties.
32 In this respect I believe it to be most unlikely that if
the ultimate form of the building is sanctioned by the court in class
1
proceedings and the building, as constructed, is found to be safe and healthy
the court would require its complete demolition or
prohibit its occupation. A
submission in those terms bespeaks punishment, a matter for the criminal law,
and not a principled approach
to the effective utilisation of an existing asset.
In these circumstances there is utility in the merit determination being made.
If nothing else it may inform the exercise of any discretion in class 4
proceedings.
33 For these reasons I decline to answer the first question.
The second question is answered - yes. Costs may be
argued.
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWLEC/2003/318.html