[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Land and Environment Court of New South Wales |
Last Updated: 29 March 2005
NEW SOUTH WALES LAND AND ENVIRONMENT COURT
CITATION: T. C. Punnett
and Associates Pty Limited v Shoalhaven City Council (No 2) [2005] NSWLEC 37
PARTIES:
APPLICANT
T. C. Punnett and Associates Pty
Limited
RESPONDENT
Shoalhaven City Council
CASE NUMBER: 11479 of 2003
CATCH WORDS:
Development Application
LEGISLATION CITED:
Environmental
Planning and Assessment Act 1979
CORAM: Brown C
DATES OF HEARING:
Written submissions
DECISION DATE: 15/02/2005
LEGAL
REPRESENTATIVES
APPLICANT
Ms L Finn, solicitor
SOLICITORS
Abbott
Tout
RESPONDENT
Mr G Gleeson, solicitor
SOLICITORS
Morton &
Harris
JUDGMENT:
THE LAND AND
ENVIRONMENT COURT
OF NEW SOUTH
WALES
Brown C
15 February
2005
11479 of 2003 T. C. Punnett and Associates Pty Limited v
Shoalhaven City
Council
JUDGMENT
1 COMMISSIONER: This is an
appeal against the deemed refusal of Development Application 03/202 by
Shoalhaven City Council for the construction
of a housing development for older
persons or persons with a disability at 22 Victoria Street, Berry.
2 The
matter was heard on 26, 27 and 28 October 2004. On 8 December 2004 findings on
the merits were published stating that there
were no substantive reasons why
development consent should not be granted however the conditions contained a
number of omissions
and inappropriate conditions that needed to be addressed
prior to the issuing of formal Orders.
3 The parties were directed to
confer on the draft conditions to address these anomalies and provide further
conditions within a period
of seven days. If agreement could not be reached on
all conditions, leave was granted for the parties to restore the matter on 48
hours notice
4 In accordance with these Directions, the parties requested
a Mention on 23 December 2004 where further Directions were given.
The
conditions in dispute
5 The principal area of dispute centres on whether
9 deferred commencement conditions should be imposed as deferred commencement
conditions
or as standard conditions, although the parties only make specific
submissions on condition 2. This conditions states:
2.Stormwater
Drainage Design & Easement (s)
The development must comply
with Council’s Development Control Plan 100 (DCP100) –
‘Subdivision Code’, in
respect to how the resultant stormwater will
be discharged by pipe work and conveyed to an approved discharge point, or the
Council’s
stormwater system. Details of this condition including the
Legal Provision of any stormwater easements over adjoining land(s) (if
required), must be submitted to Council prior to the issue of an Operational
Development Consent. A revised stormwater concept plan
is to be prepared and
submitted with the application for an operational consent. Any drainage swales
proposed along the boundaries
of the site are to be located so as to permit the
planting of trees in accordance with the approved landscape concept
plan.
6 Ms Finn, on behalf of the applicant submits that this
condition should not be a deferred commencement condition as there is no
evidence
to indicate that the flow of water will constitute a nuisance. In any
event, any nuisance will not be remedied by the creation of
an easement. She
states that Mr Gaskell, the applicant’s engineer, provided the only
hydrological engineering evidence that
indicated that there was no requirement
for an easement. It is further submitted that a reference to DCP 100 is
irrelevant and should
be deleted, considering the requirements of SEPP
5.
7 Mr Gleeson, on behalf of the council submits that the condition
should remain as a deferred commencement condition. He submits
that the
applicant proposes concentrating drainage to a specified point at the common
boundary and thereafter to flow into adjoining
land. Without an easement, this
will constitute a nuisance that would be actionable by the adjoining landowner.
A reference to
DCP 100 is necessary as it provides specific requirements for
inter allotment drainage.
8 In considering the submissions, I accept that
Mr Gaskell's hydrological evidence was the only evidence placed before the Court
on
this issue. However, my reading of Mr Gaskell’s evidence indicates
that the need for an easement is uncertain and not necessarily
that there is no
need for an easement (Exhibit O, pars 11 and 12). I also note that his evidence
outlines previous unsuccessful
attempts by the applicant to obtain an easement
over a down stream property.
9 I accept Mr Gleeson's submission that
the potential exists for a nuisance to be created through the collection of
stormwater from
the proposed development and its ultimate discharge into the
natural drainage system.
10 I also accept Mr Gleeson's submission that
the reference to DCP 100 should remain. This document provides the detailed
requirements
for stormwater disposal. Clause 25(d) of SEPP 5 identifies
stormwater disposal as a matter to be considered but could not be seen
as
addressing the stormwater disposal to the level expected in a condition of
approval.
11 Even accepting that the council raised no issue with the
disposal of stormwater, the ongoing question of whether an easement is
required
and in the absence of any substantive level of detail on the means of disposing
of stormwater, I agree that the deferred
commencement condition should
remain.
12 Deferred commencement conditions 1, 9 and 10 provide
information and direction on compliance with the deferred commencement
conditions
and as deferred commencement condition 2 is to remain, these
conditions should also remain.
13 The remaining deferred commencement
conditions in dispute relate to the provision of a pathway (deferred
commencement condition
3), compliance with the archaeological reports (deferred
commencement condition 5), the submission of a water and sewerage strategy
(deferred commencement condition 6), the submission of a traffic and access
management plan (deferred commencement condition 7) and
the provision of details
of contract or arrangement for care and facilities (deferred commencement
condition 8).
14 In my view, these matters are appropriately dealt with
as general conditions of approval as they were matters dealt with at the
hearing
or simply require the provision of further information that does not challenge
the substance of the approval.
15 The applicant also seeks the deletion
of condition 13 that identifies the proposed development as a staged
development. As the
staging set out in condition 14, I accept that condition 13
may be deleted.
16 The parties also agreed to the deletion of conditions
33, 52(a), 52(b), 56, 61, 68 and 76 and deferred commencement condition 4.
Orders
17 For the foregoing reasons, the Orders of the Court
are;
1. The appeal is upheld.
2. Development Application 03/202 for the
construction of a housing development for older persons or persons with a
disability at
22 Victoria Street, Berry is approved subject to the conditions in
Annexure A.
3. The Exhibits are returned with the exception of Exhibits 11
and A.
___________
G T Brown
Commissioner of the
Court
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWLEC/2005/37.html