Home
| Databases
| WorldLII
| Search
| Feedback
Land and Environment Court of New South Wales |
Last Updated: 12 April 2018
|
Land and Environment Court New South Wales
|
Case Name:
|
JET Group Australia Pty Ltd v Environment Protection Authority
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
10 April 2018
|
Date of Orders:
|
12 April 2018
|
Decision Date:
|
12 April 2018
|
Jurisdiction:
|
Class 1
|
Before:
|
Moore J
|
Decision:
|
(1) The appeal is upheld;
(2) The decision and orders made by the Commissioners on 19 October 2017 are set aside; (3) The proceedings are remitted to be determined by a Commissioner in accordance with this decision; (4) The Respondent is to pay the Appellant’s costs of the appeal as agreed or assessed; and (5) The exhibits are returned. |
Catchwords:
|
APPEAL - appeal pursuant to s 56A of Land and Environment Court Act 1979 -
appeal confined to questions of law - appeal against conditions imposed by
Commissioners on an Environment Protection Licence
APPEAL - first ground of appeal that Commissioners failed to give reasons for imposing contested element of an operational condition - issue clearly in contest - issue subject to partial agreement by relevant experts - although this contested issue was not subject of submissions by counsel for the Appellant before the Commissioners, it was expressly addressed by counsel for the Respondent who clearly set out the nature of the competing positions - issue not merely subsidiary or incidental or subsumed by matter in contest addressed by the Commissioners - condition sought by the Respondent incorporated in conditions imposed by order (2) made by the Commissioners - no explanation given by the Commissioners for adopting the position advanced by the Respondent in preference to that sought by the Appellant - absence of reasons on contested issue vitiated the Commissioners’ decision to impose the condition - matter remitted for determination of contested condition APPEAL - second ground of appeal that Commissioners relied on the provisions of the wrong statute in imposing a condition requiring the Appellant to provide financial assurance in a specified amount to the Respondent - ground conceded by the Respondent - concession properly made - matter remitted for determination of financial assurance issue pursuant to correct statutory provisions COSTS - costs follow the event in s 56A appeals - Respondent to pay Appellant’s costs as agreed or assessed |
Legislation Cited:
|
Civil Procedure Act 2005, s 98
Environmental Planning and Assessment Act 1979 Land and Environment Court Act 1979, s 56A Protection of the Environment Operations Act 1997, ss 53 and 287, Sch 1 Uniform Civil Procedure Rules 2005, Pt 42 r 42.1 and Sch 1 |
Cases Cited:
|
Brimbella Pty Ltd v Mosman Municipal Council (1985) 79 LGERA 367
Jet Group Australia Pty Ltd v Environment Protection Authority [2017] NSWLEC 1588 Segal & Anor v Waverley Council (2005) 64 NSWLR 177; [2005] NSWCA 310 Soulemezis v Dudley (Holdings) Pty Ltd (1987) 10 NSWLR 247 Wiki v Atlantis Relocations (NSW) Pty Limited (2004) 60 NSWLR 127; [2004] NSWCA 174 |
Category:
|
Principal judgment
|
Parties:
|
JET Group Australia Pty Ltd (Appellant)
Environment Protection Authority (Respondent) |
Representation:
|
Counsel:
Mr P Clay SC/Ms N Hammond, barrister (Appellant) Mr C Norton, barrister (Respondent) Solicitors: Hicksons Lawyers (Appellant) Environment Protection Authority (Respondent) |
File Number(s):
|
345340 of 2017
|
Publication Restriction:
|
No
|
TABLE OF CONTENTS
The appeal against the Commissioners’ decision
Financial assurance requirements issue
Conclusion on the financial assurance requirements issue
The Commissioners’ summary of the evidence
The Joint Expert Report on the gas relief layer issue
Mr Dixon’s oral evidence on the gas relief layer issue
Mr Astill’s closing submissions for the Company
Mr Norton’s closing submissions on the gas relief layer issue
Mr Astill’s closing submissions in reply
The Commissioners’ findings on the leachate dam matters
JUDGMENT
Introduction
4 The parties agree that an EPL can be issued for the proposed operation on the site, however the parties disagree on the conditions to be attached to the EPL. The areas of dispute still remaining after the submission of further information from the Applicant are:
• the specification for the leachate liner for the operations area and leachate dam, and
• the appropriate financial assurance as security against environmental harm.
Composting - 20,000 tonnes per annum green waste and 8000 tonnes per annum of additives - soil, sand, fly ash etc to produce mulch and compost as per resource recovery exemptions and 593 orders to raw mulch, pasteurised mulch and compost including AS44SA Category organics only.
The appeal against the Commissioners’ decision
Introduction
(1) A party to proceedings in Class 1, 2, 3 or 8 of the Court’s jurisdiction may appeal to the Court against an order or a decision of the Court on a question of law, being an order or a decision made by a Commissioner or Commissioners.
(2) On the hearing of an appeal under subsection (1), the Court shall:
remit the matter to the Commissioner or Commissioners for determination by the Commissioner or Commissioners in accordance with the decision of the Court, or
...
(3) ...
The appeal grounds
4 In relation to the need for a ’gas relief layer’ imposed by the Court in Condition O6.2C of the environment protection licence:
(a) The Court erred in law by failing to make a finding or explain its finding in its judgment that Condition O6.2C should include a requirement that “a gas relief layer must be included beneath the HDPE membrane ...”
(b) The Court erred in law by imposing at Condition O6.2C a requirement that “a gas relief layer must be included beneath the HDPE membrane ...” without evidence to support the need for such.
(c) The Court erred in law by imposing at Condition O6.2C a requirement that “a gas relief layer must be included beneath the HDPE membrane ...” when the evidence was all to the effect that a gas relief layer was not required.
5 In relation to the financial assurance imposed by the Court in Condition E1 of the environment protection licence:
(a) The Court erred in law by applying “section 86(6) to (10)” of an unidentified Act as a basis for, or in its determination of, its decision to impose a financial assurance in Condition E1.
(b) The Court erred in law by applying the text of Section 80A(6)-(10) of the Environmental Planning and Assessment Act 1979 (“EPA Act”) as a basis for, or in its determination of, its decision to impose a financial assurance in Condition E1.
(c) The Court erred in law by failing to apply Part 9.4 of the Protection of the Environment Operations Act 1997 to its determination of the issue of financial assurance.
Financial assurance requirements issue
Introduction
70 Conditions for financial assurances
The conditions of a licence, including the conditions of the suspension, revocation or surrender of a licence, may require the holder or former holder of the licence to provide financial assurances, as provided by Part 9.4.
296 Purpose of this Part
(1) The purpose of this Part is to provide (by way of conditions of environment protection licences) financial assurances to secure or guarantee funding for or towards the carrying out of works or programs (such as remediation work or pollution reduction programs) required by or under a licence.
(2) ....
The Commissioners’ decision
Consideration
Conclusion on the financial assurance requirements issue
The gas relief layer issue
Introduction
In addition, a gas relief layer must be included beneath the HDPE membrane which also has the capacity to be extract any leachate entering it.
Condition O6.2c contended for by the EPA:
O6.2c The Leachate Storage System is to be lined with a HDPE membrane with a minimum thickness of 1.5 mm and is to be underlain by 600m of compacted clay with permeability of no more than 10-9 m/sec. The HDPE membrane must meet or exceed the requirements for manufacture and performance contained in relevant specifications in GRI Test Method GM 13 for HDPE geomembranes. The membrane must have material properties that ensure it can maintain its performance for a period of at least equivalent to the desired working life of the leachate containment system. In addition, a gas relief layer must be included beneath the HDPE membrane which also has the capacity to extract any leachate entering it.
ALTERNATIVE VERSION OF CONDITION 6.2c:
Should the Court determine that a gas relief layer is not to be required in Condition O6.2c, the EPA contends for the condition in the form below, plus a further condition (Condition O10.4a) as follows:
O6.2c The Leachate Storage System is to be lined with a HDPE membrane with a minimum thickness of 1.5 mm and is to be underlain by 600m of compacted clay with permeability of less than 10-9 m/sec. The HDPE membrane must meet or exceed the requirements for manufacture and performance contained in relevant specifications in GRI Test Method GM 13 for HDPE geomembranes. The membrane must have material properties that ensure it can maintain its performance for a period of at least equivalent to the desired working life of the leachate containment system.
Condition O10.4a The Operational Management Plan is to include operating procedures to ensure that the capacity in the Leachate Storage System is no less than 8.3 Megalitres at all times.
• O6.2c and O10.4 contended for by the Applicant:
O6.2c The Leachate Storage System is to be lined with a HDPE membrane with a minimum thickness of 1.5mm. The HDPE membrane must meet or exceed the requirements for manufacture and performance contained in relevant specifications in GRI Test Method GM 13 for HDPE geomembranes. The membrane must have material properties that ensure it can maintain its performance for a period of at least equivalent to the desired working life of the leachate containment system.
O10.4a The Operational Management Plan is to include operating procedures with appropriate contingency measures to be implemented in order to manage environmental risks in the event of a loss of capacity in the leachate Storage System.
The Commissioners’ summary of the evidence
20 Mr Bozinovski agreed with Mr Dixon that there is potential for gas build-up beneath the leachate liner, that could have the effect of causing the liner to bubble (referred to as a ‘hippo’ or ‘whale’ effect) and thereby resulting in reduced storage volume within Dam 3; potentially increasing the need for overflow. He also agreed that a gas relief layer could be used to reduce this effect, although he proposed that there are ‘other methods’ that could be as effective and less costly although no specific methods were stipulated. Mr Bozinovski suggested that the possibility of other methods would depend on the size of the ‘hippo’ and could be detailed further in the Construction Environmental Management Plan (CEMP).
21 Mr Bozinovski stated that only the NSW Composting Guidelines are applicable for consideration at this site. Any suggestion that the Victorian Composting Guidelines are relevant, even though newer, do not relate to the situation in NSW and should be rejected.
22 Mr Bozinovksi indicated that the Applicant would need a further 18 months from the date of the EPL, to better understand the hydrological and hydrogeological conditions, and that would better inform the understanding of potential water pollution risk, design of the leachate control system and support remediation of any observed impact. He suggested that further groundwater and surface water monitoring could be used ‘to catch the leak before it went too far’, and that this should form a component of contingency planning to mitigate impact. He is also of the view that there is sufficient hydrogeological and water quality data, at and around the site, to provide a basis to support the minimum design requirement in the NSW Composting Guidelines, of 600 mm compacted clay layer with permeability of 1 x 10-7 m/s, for both the operational area and leachate Dam 3. A 100 mm cover layer of material was suggested over the liner for protection of its integrity.
23 Mr Bozinovksi stated that as they are only seeking an EPL at this stage and that the CEMP could be developed after a period of 18 months to allow more detailed site specific data collection that would inform the required design of the leachate control system.
24 Mr Bozinovski provided a cost estimate (Exhibit A) to install a range of different leachate control systems at the site, including those proposed by the Applicant and the EPA. He agreed that the lower permeability leachate liner as proposed by the EPA would result in a higher cost. The cost estimate for the applicants design (1 x 10-7 m/s liner) is $214,515 and the EPA’s suggested design (1 x10-9 m/s liner) is $1,287,090. Further to this, Mr Bozinovski suggests that costs could be reduced by using existing clay soils onsite or where appropriate (such as in the operational area), the sandstone basement rock could be utilised as a natural barrier below the leakage liner. This could then be supported by an appropriate groundwater monitoring system to facilitate mitigation of any offsite water pollution impacts.
25 Mr Bozinovski believes that there is sufficient understanding of the hydrogeological conditions beneath and around the site to ‘make an opinion’ on the applicability of the minimum requirements for a leachate control system at the site, for the operations area and Dam 3.
26 Mr Dixon position is that there is insufficient hydrogeologic information for the site to provide an understanding of baseline conditions. He agreed with Mr Bozinovski that the regional aquifer held a lower risk, however he disagreed that the current land uses had lowered the ‘groundwater sensitivity’ of the area. He was unable to define the beneficial use for this groundwater around the site.
27 Mr Dixon was also not of the same opinion as Mr Bozinovski that the sandstone geology could feasibly be used as an effective barrier to leachate infiltration into the regional aquifer. Mr Dixon notes that a study undertaken for a nearby waste disposal facility at Awaba for the Centennial Coal Environmental Impact Assessment in 2010, determined the permeability of the sandstone geology in the order 5.8 x 10-7 m/s. He also notes that the Awaba site is licensed for composting and waste disposal (Exhibit B), and has a ‘double liner’ beneath the leachate dam, although the operational area is not lined; this may contribute to pollution through leachate infiltration.
28 To mitigate the potential environmental risk to receiving waters, Mr Dixon applies the ‘precautionary principle’ in the design of the leachate control system at the site. He states that as information on the hydrologic/hydrogeologic characteristics of the site is very limited based on two water samples between the period 2011 and 2016, and the presence of existing water pollution potentially sourced from the site under ‘existing’ conditions, then a lower leachate liner permeability is required, in the order of 1 x 10-9 m/s. Mr Dixon states that ‘prescriptive liner’ conditions, as provided in the Victorian Composting Guidelines, are required to mitigate the potential, and as yet poorly defined, risk of water pollution. He noted that whilst older more established composting sites had not generally adopted the more stringent leachate liner control standards, newer composting development sites have often adopted a concrete pad across the operational area to minimise leachate infiltration. Mr Dixon considers that a minimum of 1 year’s monitoring of both groundwater (quarterly intervals) and surface water (monthly intervals) would be required to properly assess the hydrological/hydrogeological characteristics of the site, and the potential risk of water pollution. Mr Dixon is of the opinion that without such a period of data, the lower leachate liner permeability is required to mitigate the risk.
29 To support his position, Mr Dixon utilises a model, United States Hydrological Evaluation of Landfill Performance, to facilitate his understanding of the potential leakage volumes under different scenarios using the input data provided from the DG report and subsequent discussions with Mr Bozinovski. The model results (Exhibit 3) suggest it is most sensitive to permeability, and that under the minimum requirement for a leachate liner (permeability of 1 x 10-7 m/s), the estimated leachate leakage would be approximately 2.5 Megalitres/annum (ML/a), and with a liner permeability of 1 x 10-9 would be 1.8 ML/a, which is similar to a geosynthetic clay liner (GCL) with 1.8 ML/a estimated leakage. He further states that these estimates were likely to be conservative as the volume of infiltration across the operational area from the irrigation of leachate was not considered in this model.
30 Mr Dixon accepts that the NSW Composting Guidelines are appropriate for use in NSW; the Victorian Composting Guidelines provide a more up to date and ‘better industry standards’ for management of leachate control. He indicates this was applicable for this site due to the existence of water pollution and need to apply the precautionary principle due to lack of understanding of the water dynamics. He states that the operational area and leachate control for Dam 3 be underlain by either, a 600 mm thick compacted clay layer with permeability of 1 x 10-9 or a GCL. A 100 mm cover layer of material is suggested over the compacted clay layer for protection of its integrity.
31 Mr Dixon considers that a delay of 18 months before a CEMP could be developed (with the design of a leachate control system based on groundwater and surface monitoring data gathered during this time) is unacceptable. It also noted that as Mr Bozinovski explained, a further 18 month delay in the completion of a leachate control system would be necessary to allow tendering and construction design/installation. Mr Dixon notes that that the Applicant was required, as part of its previous general terms and conditions in 2011, to undertake water monitoring, and this was not undertaken.
Extracts from the judgment
33 The experts agree that the site is already subject to existing water pollution due to the historic operation of composting and potentially other activities, and that there is insufficient data to understand the hydrological and hydrogeological regime at the site. The parties also agree that a leachate liner is required beneath the operational area and Dam 3. The experts disagree whether the permeability of any leachate barrier should be 1 x 10-7 m/s (Bozinovski) or 1 x 10-9 m/s (Dixon). While the approach of Mr Bozinovski is consistent with the NSW Composting Guidelines, Mr Dixon maintains that the lack of baseline data for the site requires a more conservative approach.
34 While the experts do not agree on whether there is sufficient data to assess water pollution risk, or hydrological/hydrogeological understanding to inform the adoption of the ‘minimum requirements’ for design of a leachate control system, we agree with Mr Dixon. We also accept the NSW Composting Guidelines are the appropriate standard to consider the question of permeability and that the exceedance of the standards can be justified because of the absence of data to determine the hydrological/hydrogeological characteristics of the site.
...
39 The assessment of the bedrock as having a potentially moderate risk of pollution from this activity suggests that the underlying sandstone has some potential risk. We are satisfied that the Applicant has not produced sufficient evidence to support the consideration of the sandstone geology having sufficient permeability to act a barrier to leachate infiltration beneath a liner of higher permeability, such as 1 x 10-7 m/s.
40 It follows, in our opinion, that the lack of scientific certainty on the extent and consequence of water pollution emanating from site, invokes the precautionary principle and leads the Court to reject the assertion of the Applicant that there is sufficient evidence to assess the water pollution risk as minimal and therefore adopt ‘minimal requirements’ for design of a leachate control system.
41 The precautionary principle is one of the principles of ecologically sustainable development. As stated in Telstra Corporation Limited v Hornsby Shire Council [2006] NSWLEC 133, 146 LGERA 10; (2006) 67 NSWLR 256 (at 113).
113 ...There are numerous formulations of the precautionary principle but the most widely employed formulation adopted in Australia is that stated in s 6(2)(a) of the POEO Act. This provides:
“...If there are threats of serious or irreversible environmental damage, lack of full scientific certainty should not be used as a reason for postponing measures to prevent environmental degradation.
In the application of the precautionary principle, public and private decisions should be guided by:
(i) careful evaluation to avoid, wherever practicable, serious or irreversible damage to the environment, and
(ii) an assessment of the risk-weighted consequence of various options”.
42 We accept that in order to reduce the potential risk of water pollution from the site to receiving waters, the precautionary principle is activated. We accept the evidence of Mr Dixon that the “threats of serious or irreversible environmental damage” are justified and can only be addressed through the imposition of the more rigorous permeability criterion suggested by Mr Dixon given the lack of baseline data on which to make any learned decisions on protecting groundwater from leachate infiltration.
43 For these reasons, we reject the assertion by the Applicant that the ‘minimum requirements’ established in the NSW Composting Guidelines are appropriate for the design of the leachate control system at the site. We acknowledge that the adoption of the more stringent permeability (1 x 10-9 m/s) for the leachate liner beneath both the operational area and Dam 3, is appropriate in the particular circumstances of this case.
The Joint Expert Report on the gas relief layer issue
CONTENTION 83: Liner for leachate dam
|
|||
55
|
To minimise the risk of impact from the escape of leachate from the
Leachate Dam, a condition be imposed on any licence granted requiring
the
Leachate Dam to be designed and constructed to the following standard:
a) the leachate Dam must be constructed using an liner system comprising a
minimum 1.5mm HDPE liner with a permeability of no more
than 10-9
m/second.
|
...
CB and AD agree that a gas relief layer with capacity to collect leachate
is not required as a condition of the licence.
AD agrees to the removal of the gas relief layer as a mandatory requirement
of the licence, provided the licence states that the designer
of the dam
considers its inclusion and also measures are required in the CEMP and OEMP (and
agreed to by the EPA) to reinstate the
lost capacity of the leachate storage dam
within 1 week of identifying liner uplift in the main leachate dam (ie lost
capacity) and
within 3 months of identifying a liner uplift in the biofiltration
portion (ie lost capacity) of the leachate dam.
...
|
...
AD advises the designer of the HDPE lined leachate dam to include a gas
relief layer on the basis it is recommended by the Geosynthetic
Institute, but
recognises other methods to address liner uplift (like weighting) may be
possible. See http://www.geosynthetic-institute.org/papers/paper33.pdf.
AD on advice from RT notes that it is more critical for the main leachate
dam to maintain its capacity, hence the suggested different
timing advice for
providing for the lost capacity.
CB and AD agree to the exclusion of gas relief layer (if agreed to by the
designer) with capacity to collect leachate, subject to
conditions for
inspection, maintenance and repair of the liner in the event of a whale/hippo
(liner uplift). CB stated that installation
of a gas relief layer with leachate
extraction capabilities was not industry standard based on discussions with over
six dam lining
suppliers and review of 6 current Environment Protection Licences
(EPL’s) for similar composting facilities. In AD’s
experience the
lining supply companies do not generally design dam liners and it is AD’s
experience who has overseen the design
of dams (for construction with associated
professional indemnity details obligations) that gas relief layers are included
in HDPE
lined dams. AD asked CB for the details of the lining companies and the
EPLs and these were not provided by CB for AD’s consideration.
...
|
Mr Dixon’s oral evidence on the gas relief layer issue
WITNESS DIXON: I'm not sure what happens in the next stage. I'd like to respond to these points. There's some new information that was provided late yesterday about using the rock as the barrier, and that was new to me. I was unaware of that until 5 minutes before 4 yesterday when that was identified. So I'd like to address that. If I could start with the whale and hippo and then the leakage issue. On the whale and hippo issue, it sort of comes down to what's the risk. The risk then is looking at it holistically is in terms of then the dam doesn't have the capacity. When you get a lot of rain, all of a sudden those volumes appear very quickly. If you don't have the capacity available, if a hippo or whale occurs, then the risk of an overflow and a more substantial impact can occur. In discussing with Mr Bozinovski, I conceded that it wasn't necessary to have it as an obligation in the licence, but my suggestion was that it would be considered as a condition to be required to be considered by the designer. In my experience, a lot of designers aren't aware of these nuances because they're not always designing HDPE line dams and that's a little bit of a nuance. I haven't seen it at a compost facility, but I have seen it at at least three landfills where they can the liner lifts up because it's a close density to water. So it doesn't need much pressure underneath it.
When they do lift up, one of the causes can be leakage, slight leakage through and the bacteria then produces a gas that can lift it up, but it can also be groundwater. And we get rainfall; we've got a shallow system here which can then rise up and then drop back down as it discharges, and there's air within the unsaturated zone, and those papers also mention that as another reason why it can occur, not just through leakage; there are other mechanisms. I concede that there are other ways of potentially weighting it down. That might be an option and that's why I considered that point, other than a request like suggesting it be considered by the designer in their designing the facility.
Mr Astill’s closing submissions for the Company
Mr Norton’s closing submissions on the gas relief layer issue
In relation to the issue of swelling of the liner, this is the causing of the bubbles either through infiltration of gases to cause what are colloquially known as whales and hippos which reduce the volume in the dam, it is agreed by the experts that a gas relief liner is not essential, but they also agree that conditions should provide for inspection, maintenance and repair of the liner in the event that swelling occurs. Mr Dixon has recommended that this be addressed in the CEMP and OEMP, and there is the paper which I referred you to behind tab 28 regarding various methods for dealing with swelling. The EPAs position is that the simplest and safest method of dealing with this is simply requiring the installation of a gas relief layer. It does not require the constant monitoring and inspection and maintenance work that is required by other mechanisms. Jet objects to requirement for installation of a gas relief layer. Obviously, the experts say it is not essential, but if the Court were to adopt Jet's position and delete those words, then they should also adopt the position of the experts requiring that this issue be addressed in some way. At the top of p 10, the EPA has an alternative wording condition that should be inserted should the Court reject a gas relief layer as condition 10.4A: that the OEMP include operation procedures to ensure the capacity in the leachate storage system is no less than 8.2 megalitres at all times.
Mr Astill’s closing submissions in reply
The Commissioners’ findings on the leachate dam matters
Consideration
(a) Although a Commissioner of the Land and Environment Court is obliged to consider the principal contested issues before him or her, each of those issues is the genus of which the various arguments in favour or against the resolution of the issue in a particular way are species.
(b) It is unnecessary for a Commissioner or a judge of the Court to consider each of the species provided he or she has considered the genus. It is that which must be addressed in the Commissioner's or judge's reasons. Those reasons must be adequate to explain, by way of findings and reference to the evidence supporting the findings, the reasoning process adopted by the Commissioner or judge and which has led to his or her conclusion.
Costs
Orders
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWLEC/2018/49.html