![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales |
Last Updated: 17 October 2002
NEW SOUTH WALES SUPREME COURT
CITATION: Reid & Anor v Shearan
& Anor [2002] NSWSC 902 revised - 8/10/2002
CURRENT
JURISDICTION: Equity
FILE NUMBER(S): 2097/2002
HEARING DATE{S):
19 September 2002
JUDGMENT DATE: 01/10/2002
PARTIES:
William George Reid and
Margaret Law Reid
(Plaintiffs)
John
Charles Shearan and
Joyce Evelyn Weller
(Defendants)
JUDGMENT OF:
Acting Master Berecry
LOWER COURT JURISDICTION: Not
Applicable
LOWER COURT FILE NUMBER(S): Not Applicable
LOWER COURT
JUDICIAL OFFICER: Not Applicable
COUNSEL:
Mr P
Friedlander
(Plaintiffs)
Mr G
Grinter
(Defendants)
SOLICITORS:
Hartcher Reid with Writer Ryan
Boesen
(Plaintiffs)
Cutlers The Law
Firm
(Defendants)
CATCHWORDS:
Discontinuance - leave -
entitlement to costs -reasonableness of plaintiffs' actions
ACTS CITED:
Part 21 r 2 & Part 52A r 21 Supreme Court Rules
DECISION:
(1)
Leave be granted to the plaintiffs to file a notice of discontinue
(2) The
defendants pay half the plaintiffs' costs.
JUDGMENT:
IN
THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY
DIVISION
ACTING MASTER BERECRY
TUESDAY, 1
OCTOBER 2002
2097/2002 - WILIAM GEORGE REID & ANOR v
JOHN CHARLES SHEARAN &
ANOR
JUDGMENT
1 MASTER: On 23 February 1988 the
plaintiff entered into an agreement for sale of land with the defendant to
purchase Lot 1 in DP 730853.
The land was part of a subdivision of the
defendants’ land. The defendants held Lot 2. Both lots had a boundary
with Stimsons
Lane. However, access to the public road was over a bridge on the
defendants’ land (Lot 2). Discussions and correspondence
had been entered
into between the parties’ solicitors concerning access to the
plaintiffs’ property. It appears that
the question of access was never
formalised. The parties agreed that the plaintiffs could have access over part
of the defendants’
land. Between 1988 and 17 January 2002, the plaintiffs
continued to use the access that the defendants had granted.
2 In
February 2001 the plaintiffs commenced to build on their land. At about this
time the defendants submitted an application to
the local Council for
subdivision of Lot 2. During the survey of the land, the defendants were
informed of certain encroachments
on to their land. A meeting took place on 29
September 2001 between the parties’ surveyors, the plaintiffs and Mr
Shearan.
Mr Shearan was prepared to grant a right of way provided the
plaintiffs paid all of the costs of the upgrading of the access. He
was not
prepared to negotiate of any other terms or variation of this term. The nature
of the work was agreed and the defendants’
surveyors estimated the cost at
about $7,000.00. The plaintiffs accepted the terms on the basis that the costs
would be approximately
$7,000.00.
3 Subsequently, the plaintiffs were
informed by their surveyor that the costs would be between $20,000.00 and
$25,000.00. The plaintiffs
were not prepared to meet all of this expense.
Attempts were made by the plaintiffs to formalise the access by creation of
appropriate
easements. Initially, there was no response from the defendants.
However, on 25 October 2001 the plaintiffs were advised that the
defendants were
prepared to meet on 26 October 2001 to discuss the matter. At the last moment
the defendant advised that they would
not negotiate any further.
4 A
suggestion was made by the defendants’ solicitor that the plaintiffs could
create their own access on that part the existing
easement that gave direct
access to their property. They were reluctant to do that as it would mean
clearing some trees which they
regarded as fine specimens of Australian
rainforest trees. In addition, they considered that they were bound by Wyong
Shire Council’s
(the Council) 1993 Development Consent which required the
retention of all native emergent vegetation along the northern boundary
of the
property (Lot 1).
5 On 29 November 2001, William Reid (the first
plaintiff) had an on-site meeting with an officer of the Council. This officer
was
from the Development Control Department. He informed the first plaintiff
that he would recommend that the defendants’ subdivision
development
consent be altered to provide that the parties negotiate an extension of the
right of way. This was subsequently confirmed
by the Council.
6 Notwithstanding this requirement the defendants refused to negotiate.
Subsequently, the defendants dug ditches in the roadway,
placed star pegs and
tape across the boundary and erected a gate. The gate was locked for a period
of three days in January 2002.
Thus, preventing access to the plaintiffs’
land.
7 In January 2002 the defendants’ solicitor, without
instructions, suggested to the plaintiffs that the matter might be resolved
if
they offered to pay half the costs of constructing the access. Despite having
reservations about the likelihood about the offer
being accepted, the plaintiffs
engaged an engineer to cost the works. He informed the plaintiffs that he would
require a copy of
the defendants’ Development Consent relating to the
up-grading of the access to enable him to prepare a proper quote. The
first
defendant agreed to send a copy however, a copy was never sent and subsequently
correspondence was not answered. Further discussions
took place between the
first plaintiff and the defendants’ solicitor. On 18 March 2002, the
plaintiff’s sent to the defendants’ solicitor an offer of
settlement. In a subsequent telephone attendance, the defendants’
solicitor
indicated that the offer seemed to be all right but the defendants
were still considering some contribution for granting the easement.
He said he
would get back to the plaintiffs again once he had instructions. On 26 March
2002, the plaintiffs had not heard from
the defendants. A final letter was sent
to the defendants’ solicitor advising that they proposed to take
proceedings.
8 It appears that the problem of access arose in mid 2001
when the plaintiffs’ builders moved on site to construct the dwelling.
The defendants objected to the way that they drove onto the land and the damage
their vehicles were causing to the land. The dispute
reached a critical stage
in January 2002 with the placing of the star posts and gate thus restricting
access to the plaintiffs’
land. It would appear that the limited access
that the plaintiffs had, meant that the contractor could not get reasonable
access
to the building site, and thus construction could not be completed. By
March, with the issue still not resolved, the plaintiffs
were faced with the
prospect of renting alternate accommodation until this dispute was resolved.
The plaintiffs allege that they
were denied access which would have enable their
tradesmen to complete the work. As negotiations has broken down these
proceedings
were commenced.
9 The plaintiffs filed a summons on 2 April
2002 seeking, inter alia, an order that the plaintiffs and their agents be given
free
and inhibited access by foot and vehicle at all times over the disputed
part of the defendants’ land, and secondly, that the
plaintiffs do all
things necessary to create a right of carriageway and easement for
services.
10 On 5 April 2002 consent orders were made in the following
terms:
Consent Orders
(1) Application adjourned to 10 May
2002.
(2) Costs reserved.
(3) Liberty to apply on two days
notice.
(4) Noted without prejudice to the ultimate rights of the parties
that they have reached agreement for the defendants to give the
plaintiffs
temporary access across the defendants’ property.
11 Subsequently,
the defendants demanded additional work be carried out in respect of the
agreement reached on 5 April 2002. Sometime
after 8 April 2002 the plaintiffs
sought to obtain an easement over another neighbour’s property. However,
that neighbour
declined to consent to the easement. As a result of the refusal,
the plaintiffs lodged a development application with the Council
for access to
their land through the northern portion of the carriageway and easement abutting
Stimson Lane. Environmental issues
were raised by the Council and the
plaintiffs responded to those issues by lodging a further development
application. This development
application was accepted by Council. The
plaintiffs now have access to their property which does not impinge on any part
of the
defendants’ land. It was contended for the defendants that the
plaintiffs should have sought access for Lot 1 from the Council
when they
commenced construction of their house. Further, it was submitted that they were
dilatory in not pursuing the application
until 18 months after the commence of
construction.
12 However, the plaintiffs had used the disputed access
for 13 years without any concern being raised by the defendants. It was not
unreasonable to assume that they would be able to use the access to enable the
builders to entered upon the plaintiffs’ land.
13 Whilst with
hindsight, it might be thought that the plaintiffs were dilatory that, in fact,
was not the case.
14 They had used the disputed land for 13 years. The
development consent they obtained from Council required the vegetation on the
northern boundary to be retained. True it is that on part of the land, for
aesthetic reasons, they did not wish to fell trees.
Nevertheless, they were
bound by the conditions of the development application. The defendants did not
put on any evidence which
would show that the plaintiffs could have put in
access on Lot 1 and still comply with the Council’s condition.
15 In late November 2001, Council informed all parties that as a
condition of the defendants’ subdivision of Lot 2 that they
(the
defendants) had to negotiate access with the plaintiffs. It was reasonable for
the plaintiffs to assume that access to Lot
1 would only be permitted by Council
through Lot 2. Those negotiations broke down. The plaintiffs have put on
evidence concerning
the delays that they experienced with completion of their
house because of the dispute with the defendants. It would seem that the
actions of the defendants in January 2002 meant that the plaintiffs may have
been trespassers had they and the builders continued
to use the roadway. It was
not unreasonable in the circumstances to negotiate with the defendants
concerning access and formalise
the access that they had been granted and used
over a period of 13 years.
16 The plaintiffs seek leave to file and
serve a notice of discontinuance. Part 21 r 2 permits the plaintiff to
discontinue with
consent of the other part or by leave of the court. Part 52A r
21 provides, inter alia, that a party discontinuing proceedings without
leave
must pay the other party’s costs. The defendants submit that the
plaintiffs should either pay the defendants’
costs or that each party
should pay their own costs. It is further submitted that the plaintiffs would
not have succeeded in obtaining
their remedies.
17 In Hill v
Copeland [1999] NSWSC 632; unreported BC9903587 Master Macready review a
numbered of cases dealing with the questions of costs when a plaintiff seeks
leave
to discontinue. The learned Master referred to a number of cases which
suggest that in the ordinary case the plaintiff cannot usually
apply to
discontinue on terms that an order for costs be made against the defendant
– see Mulcahey v Wilkinson (1887) 9 ALT 22, Lambton & Co v
Parkinson (1887) 35 WLR 545 and Denman Homes Pty Ltd v Madnara
(unreported, Needham J, 14 September 1983). He then referred to recent
cases which suggest that in exceptional cases a costs order
may be made against
a defendant. He cited the cases of Garwolin Nominees Pty Ltd v Statewide
Building Society [1984] VicRp 38; (1984) VR 469, Telstra Corporation v Australian
Telecommunications Authority unreported Haynes J VICSC 10 June 1994, and
Australian Securities Commission v Aust-Home Investments Ltd 34 FCR 194.
18 In the last case Hill J summarised cases in the following
way:
"(1) Where neither party desires to proceed with litigation the
Court should be ready to facilitate the conclusion of the proceedings
by making
a cost order: Stratford and the SEQEB case.
(2) It will rarely, if ever,
be appropriate, where there has been no trial on the merits, for a Court
determining how the costs of
the proceeding should be borne to endeavour to
determine for itself the case on the merits or, as it might be put, to determine
the
outcome of a hypothetical trial: Stratford. This will particularly be the
case where a trial on the merits would involve complex
factual matters where
credit could be an issue.
(3) In determining the question of costs it
would be appropriate, however, for the Court to determine whether the applicant
acted
reasonably in commencing the proceedings and whether the respondent acted
reasonably in defending them (SEQEB).
(4) In a particular case it might
be appropriate for the Court in its discretion to consider the conduct of a
respondent prior to
the commencement of the proceedings where such conduct may
have precipitated the litigation: cf Sunday Times Newspaper Co Ltd v McIntosh
[1933] NSWStRp 37; (1933) 33 SR (NSW) 371.
(5) Where the proceedings terminate after
interlocutory relief has been granted, the Court may take into account the fact
that interlocutory
relief has been granted: cf Re Asiatic Electric Co Pty Ltd
[1973] 1 NSWLR 603 at 606, a case which, however, depended upon the specific
working of the statute under consideration."
19 In Re Minister for
Immigration & Ethnic Affairs; Exparte QIN [1997] HCA 6; 71 ALJR 533 McHugh J made the
following comments:
"In an appropriate case, a court will make an order
for costs even when there has been no hearing on the merits and the moving party
no longer wishes to proceed with the action. ...
... In some cases,
however, the court may be able to conclude that one of the parties has acted so
unreasonably that the other party
should obtain the costs of the action.
...
Moreover, in some cases a judge may feel confident that, although
both parties have acted reasonably, one party was almost certain
to have
succeeded if the matter had been fully tried. ...”
20 After
review of these cases the learned Master in Hill v Copeland supra at para
[26] made the following comments:
“As is clearly indicated by these
excerpts it is inappropriate for the court to determine the case on the merits
or to determine
the outcome of a hypothetical trial. However, the court can take
the preliminary step of determining whether the plaintiff acted
reasonably in
commencing the proceedings.”
21 In my view the facts as they were
at the time the plaintiffs commenced these proceedings show that the plaintiff
had acted reasonably
throughout the period of this dispute and took great pains
to negotiate a settlement with the defendants. It seems to me that up
to a
point the defendants also acted reasonably in that they instructed a solicitor,
agreed to negotiate and came up with proposals
to reach a satisfactory outcome.
However, there were also actions taken by the defendants which caused the
negotiations to breakdown,
ie., refusal to attend meetings, respond to
correspondence and impede access to the plaintiffs’ land.
22 There
has been no interlocutory determination on any of the merits in these
proceedings. It is therefore dangerous to venture
into the dispute to attempt
to determine what might have been the outcome. Steps taken subsequent to the
commencement of proceedings
by the plaintiffs result in a position that the
plaintiffs no longer need to proceed with its action. It seems to me that the
plaintiffs
were forced to bring these proceedings. As a result of commencing
these proceedings an agreement was reached on 5 April in respect
of the disputed
access. In my view however, the plaintiffs are not entitled to an order for all
their costs in these proceedings.
It could not be said that the defendants were
totally unreasonable in the approached in which they took. Time was of the
essence
for the plaintiffs in relation to the building works. It was in my view
possible for the plaintiffs at least on an interim basis
to obtain the order
that was sought in paragraph (1) of the summons. Therefore, the appropriate
orders I make are as follows:
(1) Leave be granted to the plaintiffs to
file a notice of discontinuance.
(2) The defendants pay half the
plaintiffs’ costs.
**********
LAST UPDATED:
08/10/2002
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2002/902.html