![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales |
Last Updated: 9 December 2003
NEW SOUTH WALES SUPREME COURT
CITATION: Leighton Contractors Pty
Limited v Campbelltown Catholic Club Limited, Campbelltown Catholic Club Limited
v Leighton Contractors
Pty Limited [2003] NSWSC 1103
CURRENT
JURISDICTION: Equity Division
Technology and Construction List
FILE
NUMBER(S): 55030/02
55033/02
HEARING DATE{S): 27/11/03,
28/11/03
JUDGMENT DATE: 03/12/2003
PARTIES:
Leighton
Contractors Pty Limited (Plaintiff in 55030/02, Defendant in
55033/02)
Campbelltown Catholic Club Limited (Plaintiff in 55033/02,
Defendant in 55030/02)
JUDGMENT OF: Einstein J
LOWER COURT
JURISDICTION: Not Applicable
LOWER COURT FILE NUMBER(S): Not
Applicable
LOWER COURT JUDICIAL OFFICER: Not Applicable
COUNSEL:
Mr GE Underwood (Plaintiff 55030/02, Defendant 55033/02)
Mr MLD Einfeld
QC, Mr TD Castle (Plaintiff 55033/02, Defendant 55030/02)
SOLICITORS:
Mallesons Stephen Jaques (Plaintiff 55030/02, Defendant 55033/02)
Dibbs
Barker Gosling ((Plaintiff 55033/02, Defendant 55030/02)
CATCHWORDS:
Contract
building and construction
Building and Construction Industry
Security of Payment Act 1999 (NSW)
Consideration of interrelationship of
sundry provisions and analysis of principal's claimed entitlement to commence
separate proceedings
and/or to avoid summary judgment by invoking discretionary
considerations
Progress claim submitted to Superintendent on same date as
document purporting to be payment claim under the Act submitted to
principal
Principal fails to serve payment schedule complying with sections
14(1) and (2)
Contractor commences proceedings and seeks summary
judgment
Principal commences separate proceedings and seeks declaration that
it does not owe any amount to contractor in respect of specific
progress claim
in excess of the amount specified in progress certificate issued by
Superintendent and order that principal pay to
the contractor such sum as it
might recover against principal in the first proceedings
second proceedings
held to be an abuse of process
Principal in first proceedings contends (as
defendant) - That alleged payment claim was not a valid payment claim within
s.13(2) of the Act because: (i) it did not identify construction work (or
related goods and services) as required by s.13(2)(a); (ii) there was no
progress payment claimed as required by s.13(2)(b); (iii) it did not bear the
endorsement required by s. 13(2) (c);
That contractor was and is not a
person entitled or who claims to be entitled to a progress payment within s.
13(1) because: (i) it was not a person entitled to a progress payment under s.
8(1); (ii) as at the date of the Alleged Payment Claim there was no reference
date as and from which contractor was entitled to a progress
payment within s.
8(1) and (2); (iii) there was no amount calculated in accordance with the terms
of the Contract which constituted a progress payment to
which contractor was
entitled under s. 9(a); (iv) as at the date of the Alleged Payment Claim there
was no progress payment under the Contract which had become due and payable
within the meaning of s. 11(1); - That Alleged Payment Claim was not a valid
payment claim (in whole or in part) under s. 13 of the Act: (i) to the extent
that it claimed for rock excavation, because it was not served within 12 months
after such work was
last carried out as required by s. 13(4)(b); (ii) to the
extent that it claimed for Delay Costs, because such claim was not permitted by
the Act, the Delay Costs not being construction
work to which the progress
payment claimed by contractor related. - Alternatively, that if the Alleged
Payment Claim were a valid
payment claim, defendant was not liable to pay the
amount claimed by contractor by reason that defendant served on plaintiff a
payment
schedule within the meaning of s. 14 of the Act, being the Certificate
issued by Superintendent.
ACTS CITED:
Building and Construction
Industry Security of Payment Amendment Act 2002
Building and Construction
Industry Security of Payment Act 1999 (NSW)
Evidence Act 1995
(NSW)
Interpretation Act 1987 (NSW)
Supreme Court Act 1970
(NSW)
DECISION:
Summary judgment to be entered for Leighton
Contractors Pty Limited.
JUDGMENT:
IN THE SUPREME
COURT
OF NEW SOUTH WALES
EQUITY
DIVISION
TECHNOLOGY AND CONSTRUCTION LIST
Einstein
J
3 December 2003
55030/02 Leighton
Contractors Pty Limited v Campbelltown Catholic Club Limited
55033/02 Campbelltown Catholic Club Limited v Leighton
Contractors Pty Limited
JUDGMENT
The
proceedings
1 The two sets of proceedings before the Court concern a
dispute under a building contract dated 13 February 2002 ["the contract"]
between Leighton Contractors Pty Ltd ["Leighton"] and Campbelltown Catholic Club
Ltd ["the Club"] for the carrying on of works at
certain premises at
Campbelltown. The general conditions of contract were in the form AS 4000-1997.
Leighton was the "Contractor"
and the Club was the "Principal" under the
contract.
2 The Club's architect, Scott Carver Pty Ltd ["Carver"] was
appointed as the Superintendent under the contract.
3 In proceedings
55030 of 2003 ["the first proceedings"] Leighton as plaintiff, seeks summary
judgment against the Club in respect
of a payment claim [referred to during the
proceedings as “progress claim 18”] for an amount of $3,068,468.70
which Leighton
asserts complied with the Building and Construction Industry
Security of Payment Act 1999 (NSW) ["the Act"] and was served pursuant to
section 13 (1) of the Act.
4 In proceedings 55033 of 2003 ["the second
proceedings"] the Club as plaintiff seeks:
· a declaration that the
Club does not owe any amount to Leighton in respect of progress claim 18 in
excess of the amount specified
in progress certificate 00188.18 issued by Carver
on 6 August 2003; and
· an order that Leighton pay to the Club such
sum as it might recover against the Club in the first
proceedings.
5 Leighton by Notice of Motion seeks orders dismissing the
Summons as disclosing no reasonable cause of action or as an abuse of
process.
6 The essence of the competing positions taken by the parties
requires close analysis of the Act and its application to the communications
between the parties. It is appropriate to note that the Act which has been
amended once, has been the subject of recent curial examination
and remains a
source of difficulty, there having been a number of sometimes consistent and
sometimes inconsistent judicial pronouncements
in relation to aspects of its
interpretation and application.
The evidence
The
facts
28 November 2001
7 On 28 November 2001 Leighton
submit a tender to the Club for the “alterations and additions to
Campbelltown Catholic Club
including the new underground carpark”. (TB
177)
13 February 2002
8 Leighton and the Club enter into
the Contract whereby Leighton agrees to undertake certain construction and
refurbishment works
for the Club. Under the Contract, Carver was appointed as
the Superintendent. (TB 734-836)
1 March 2002
9 Leighton
submits progress claim 1 on 1 March 2002. (TB 1)
3 April
2002
10 Leighton submits progress claim 2 on 3 April 2002. (TB
3)
8 April 2002
11 On 8 April 2002 Leighton first gives
notice to the Club that they will be making a claim for a variation as a result
of the excavation
of rock. The facsimile reads as follows:
”We are
submitting notification that we are encountering rock material in the southern
end of the bulk excavation works.
We are monitoring the extent of the
rock and we will be submitting a variation and extension of time claim once the
extent of the
material has been established.” (TB 180)
12 April
2002
12 The Superintendent advises Leighton that it needs to
demonstrate that the material encountered by Leighton on site falls within
the
contractual definition of “rock” as a variation. (TB
186)
1 May 2002
13 Leighton submits progress claim 3 on 1
May 2002. (TB 5)
4 June 2002
14 Leighton submits progress
claim 4 on 4 June 2002. (TB 6)
4 July 2002
15 Leighton
submits progress claim 5 on 4 July 2002. (TB 8)
24 July
2002
16 On 24 July 2002 Mr Thebridge, an Architect and an associate
director of Carver, visits the site and photographs the construction
area above
the rock excavation. (TB 254 – 286)
31 July
2002
17 Leighton submits progress claim 6 on 31 July 2002. (TB
10)
18 On the same day as the submission of the progress claim, Leighton
submits variation LV12 in the amount of $736,487 for a latent
condition –
rock excavation. (TB 287)
23 August 2002
19 By two letters
dated 23 August 2002 Leighton notifies the Superintendent that disputes have
arisen under clause 42.1 of the Contract
in relation to the removal of rock and
the replacement of granular fill beneath the car park (“First Notice of
Dispute”).
(TB 891-892) These letters were copied to Mr Muter of the
Club.
4 September 2002
20 Leighton submits progress claim 7
on 4 September 2002. (TB 12)
2 October 2002
21 Leighton
submits progress claim 8 on 2 October 2002. (TB 14)
1 November
2002
22 Leighton submits progress claim 9 on 1 November 2002. (TB
15)
2 December 2002
23 Leighton submits progress claim 10
on 2 December 2002. (TB 18)
13 December 2002
24 Site
meeting to assess the issue of practical completion. (TB 309)
19
December 2002
25 Leighton submits progress claim 11 on 19 December
2002. (TB 21)
3 February 2003
26 Leighton submits progress
claim 12 on 3 February 2003. (TB 24)
3 March
2003
27 Leighton submits progress claim 13 on 3 March 2003. (TB
27)
31 March 2003
28 Leighton submits progress claim 14 on
31 March 2003. (TB 29)
2 April 2003
29 Leighton issue
Notice to Show Cause. (TB 893 – 897)
11 April
2003
30 The Club issues a Notice in Reply to the Notice to Show
Cause. (TB 898 – 901)
30 April 2003
31 Leighton
submits progress claim 15 on 30 April 2003. (TB 32)
19 May
2003
32 Leighton issue Second Notice of Dispute (“Second Notice
of Dispute”). (TB 902-906)
28 May 2003
33 Leighton
submits progress claim 16 on 28 May 2003. (TB 34)
1 July
2003
34 Leighton submits progress claim 17 on 1 July 2003. (TB
35)
3 July 2003
35 The Club issues a Reply to the Second
Notice of Dispute. (TB 907-912)
28 July 2003
36 By
facsimile Leighton writes to the Club enclosing Progress Claim no. 18. (TB
36-43, 913-920) The covering letter was in the following
terms:
“Dear Sir,
CAMPBELLTOWN CATHOLIC CLUB
PROGRESS
CLAIM NO.18 – JULY 2003
We attach Progress Claim No. 18 for work
complete on the above Project for the period ending 28 July 2003 for the sum of
$2,789,517.00
(excluding GST) for your review and subsequent
certification.
The Statutory Declaration for this Claim is also
attached.
This is a payment claim made under the Building and
Construction Industry Security of Payments Act 1999 (NSW) (as
amended).” (TB 36)
37 Leighton writes to the Superintendent
enclosing Progress Claim No.18. (TB 44, 921-928) The covering letter, addressed
to Mark
Thebridge of Scott Carver Pty Limited was in almost identical
terms:
“Dear Sir,
CAMPBELLTOWN CATHOLIC CLUB
PROGRESS
CLAIM NO.18 – JULY 2003
We attach Progress Claim No. 18 for work
complete on the above Project for the period ending 28 July 2003 for the sum of
$2,789,517.00
(excluding GST) for your review and subsequent
certification.
The Statutory Declaration for this Claim is also
attached.” (TB 921)
6 August 2003
38 The
Superintendent issues a letter to Leighton in relation to progress claim no. 18,
including progress payment certificate, certifying
the amount due to Leighton as
$23,674. (TB 45) The letter was in the following terms:
“Attn: Mr
Jack Boulenaz
Dear Sir
RE: Campbelltown Catholic Club
We
enclose our certificate No 00188.18 to the value of $23,674 including GST
covering your progress claim No. 18.
We enclose Rider Hunt’s report
relating to the assessment of the progress claim. This documentation combined
with the previous
correspondence issued in relation to the various claims for
works, identified as rejected or not approved in the Rider Hunt report,
outlines
the difference between the claimed amount and the certified value.
We
have not received any reply correspondence for the majority of the L or LV
variation claims made. We have previously requested
further details about these
claims.
The Contract Summary identifies variations (note 5) with which
Rider Hunt have had ongoing dialogue with Leightons. We understand
that the
majority of these variations have agreement in principal, however, we have
previously requested that Leightons confirm this
as correct and accepted. We
await this confirmation.”
13 August 2003
39 Leighton
sends a letter to the Club requesting payment of $23,674 pursuant to the payment
certificate. The letter, attaching a
tax invoice (TB 945) and the progress
payment certificate (TB 946), stated:
“Dear Sir
CAMPBELLTOWN CATHOLIC CLUB
PROGRESS CLAIM NO. 18 JULY 2003
In
accordance with Clause 37 of the Contract we attach our Tax Invoice No. 16468 in
the amount of $23674.00 (GST inclusive) together
with the Progress Claim
Certificate issued by Scott Carver Pty Ltd....
In requesting payment we
register the fact that the Certified Amount is significantly less than that
requested in our Progress Claim,
and that we do not agree with all the reasons
relating to the reduction of the Claim.
Should you have any queries on
the above please contact Jack Boulenaz [number given]” (TB 944-946)
40 Leighton also sends a letter to the Club demanding payment of
$3,068,468.70. The letter was in the following terms:
“Dear Mr
Muter
CAMPBELLTOWN CATHOLIC CLUB
On 28 July 2002 we served on the
Club by facsimile a payment claim made pursuant to section 13(1) of the
Building and Construction Industry Security of Payment Act 1999 (NSW)
(“Act”).
The Club had, pursuant to section 14(4) of the Act,
10 business days from 28 July 2003 to serve a payment schedule. That time
expired
on 11 August 2003 and no payment schedule was served.
The
consequences of this failure by the Club is that the Club has become liable to
pay the full amount claimed in the payment claim
being $2,789,517.00 plus
GST, by the due date for payment.
Section 11(1) of the Act provides
that the due date for payment is the date on which the payment becomes due and
payable in accordance
with the terms of the contract. The relevant contractual
provision is clause 37.2 which is unclear. The due date for payment appears
to
be either 7 days from receipt by the Club of the two certificates issued by the
Superintendent, or 17 days from the payment claim.
Further, the parties have to
date, adopted a different course of acting in relation to payment. The
Superintendent issues one certificate
to us, we pass on a copy to you and issue
you with a tax invoice, and you pay within 7 days of receipt of the certificate
and tax
invoice.
Accordingly, it is not clear when the due date for
payment is. The latest it can possibly be however, is 7 days from the date we
issue you with a copy of the latest payment certificate and tax invoice. We
issued these to the Club by an earlier fax today, 13
August 2003. The Club must
pay the full amount to which we are entitled, $3,068,468.70 by Wednesday 20
August 2003. We enclose a tax invoice for $3,068,468.70.
If
you fail to pay the full amount claimed, the following consequences are imposed
by the Act:
(a) we may recover the unpaid amount as a debt due to us in
any court of competent jurisdiction, pursuant to section 15(2)(a);
(b)
if we commence proceedings to recover the amount as a debt due then in those
proceedings the Club is not entitled to bring any
cross-claim or raise any
defence in relation to matters arising under the contract, pursuant to section
15(4)(b);
(c) interest is payable on the full amount at the rate of 9%
(being the rate currently prescribed under the Supreme Court Act 1970) pursuant
to section 11(2) of the Act; and
(d) we are entitled to suspend works
on 2 days’ notice to the Club pursuant to sections 15(2)(b) and
27(1).
If we do not receive payment of the full amount as required by 20
August 2003 then we will commence proceedings in the Supreme Court,
and take any
other action available to us, without any further notification to the
Club.” (TB 947-948)
14 August 2003
41 Mr Muter of
the Club sends a facsimile to Leighton remitting payment of $23,674, however
rejecting the demand for payment of $3,068,468.78.
The letter dated 14 August
2003 was in the following terms:
“Dear Mr Bouton,
I refer to
your letter of 13 August 2003.
On 28 July 2003 you served progress claim
number 18 for the sum of $2,789,517.00 (excluding GST) on the Superintendent as
well as
on me.
On 6 August 2003, the Superintendent sent to you a
progress certificate payment schedule evidencing the Superintendent’s
opinion
of the monies due from us to you pursuant to the progress claim and the
reasons for any difference. In my view that schedule complies
with the
requirements of the Building and Construction Industry Security of Payment
Act as it identifies the payment of the progress claim, the amount of the
payment that the Superintendent proposes to make and the Superintendent’s
reasons for withholding payment.
Also on 6 August 2003, the
Superintendent sent me a certificate for the sum of $23,674 including GST, the
amount certified by him
as due under progress claim number 18. We received your
tax invoice for that sum on 13 August 2003 and the funds transfer is currently
being done.
I reject your demand for payment of the sum of
$3,068,468.70.” (TB 950)
18 August 2003
42 On 18
August 2003 Leighton sends a letter to the Club in response to the Club’s
facsimile of 14 August 2003. The letter
reads as follows:
“Dear Mr
Muter,
CAMPBELLTOWN CATHOLIC CLUB
I refer to your facsimile of
14 August 2003.
The Club appears to have misunderstood the Building
and Construction Industry Security of Payment Act 1999 (NSW).
On 28
July 2003 we made a progress claim in accordance wit the Contract to the
Superintendent as required by clause 37.1 of the Contract.
In accordance with
clause 37.2 of the Contract the Superintendent responded on 6 August 2003. The
Superintendent certified an amount
due to us of $23,674 including GST. In
accordance with previous practice that we have adopted we sent you a copy of
that certificate
by our facsimile of 13 August 2003 together with a tax invoice
for $23,674. We note you are in the process of transferring that
money to
us.
Also on 28 July 2003 and separately, we made a payment claim under
section 13(1) of the Act to the Club, being the person liable to
make payment in
accordance with the terms of the Contract. The Club was required by section
14(4) of the Act to provide to us a
payment schedule in response to the payment
claim within 10 business days which expired on 11 August 2003. Having failed to
serve
that payment schedule the Club is now liable for the full amount claimed
in the payment claim. Given that the Club has now paid
$23,674, the amount due
to us by the due date for payment, being no later than 20 August 2003, is
$3,044,794.70. If we do not receive
payment of that amount by 20 August 2003 we
will, as previously indicated, commence proceedings to recover that amount
without any
further notification to you.” (TB 951)
21 August
2003
43 Leighton commences proceedings no 55030 of 2003 on 21 August
2003.
9 September 2003
44 9 September 2003 is the date
certified by the Superintendent for practical completion. (TB 476g)
19
September 2003
45 The Club commences proceedings no 55033 of
2003.
The Issues
46 There are a number of disparate issues
raised by the pleadings. These are generally the subject of careful submissions
by the
parties. The convenient course is to commence by identifying the issues
for determination in the first proceedings as set out in
the overview written
submissions of the Club. Where either party sought to litigate other issues or
moved slightly outside the initial
description of the issues given by the Club
which follows, those issues will be identified later in the
judgment.
Relevant sections of the Act
47 A number of
sections of the Act required to be examined during these proceedings.
48 They included, inter alia:
“3 Object of
Act
(1) The object of this Act is to ensure that any person who
undertakes to carry out construction work (or who undertakes to supply
related
goods and services) under a construction contract is entitled to receive, and is
able to recover, progress payments in relation
to the carrying out of that work
and the supplying of those goods and services.
(2) The means by which
this Act ensures that a person is entitled to receive a progress payment is by
granting a statutory entitlement
to such a payment regardless of whether the
relevant construction contract makes provision for progress
payments.
(3) The means by which this Act ensures that a person is able
to recover a progress payment is by establishing a procedure that involves:
(a) the making of a payment claim by the person claiming payment,
and
(b) the provision of a payment schedule by the person by whom the
payment is payable, and
(c) the referral of any disputed claim to an
adjudicator for determination, and
(d) the payment of the progress
payment so determined.
(4) It is intended that this Act does not limit:
(a) any other entitlement that a claimant may have under a
construction contract, or
(b) any other remedy that a claimant may have
for recovering any such other
entitlement....
4 Definitions
In this Act...
payment claim means a claim referred to in section
13.
payment schedule means a schedule referred to in
section 14.
progress payment means a payment to which a
person is entitled under section 8, and includes (without affecting any such
entitlement):
(a) the final payment for construction work carried out
(or for related goods and services supplied) under a construction contract,
or
(b) a single or one-off payment for carrying out construction work
(or for supplying related goods and services) under a construction
contract,
or
(c) a payment that is based on an event or date (known in the
building and construction industry as a “milestone
payment”)....
5 Definition of “construction
work”
(1) In this Act, construction work means any of
the following work:
(a) the construction, alteration, repair,
restoration, maintenance, extension, demolition or dismantling of buildings or
structures
forming, or to form, part of land (whether permanent or
not),
(b) the construction, alteration, repair, restoration,
maintenance, extension, demolition or dismantling of any works forming, or
to
form, part of land, including walls, roadworks, power-lines, telecommunication
apparatus, aircraft runways, docks and harbours,
railways, inland waterways,
pipelines, reservoirs, water mains, wells, sewers, industrial plant and
installations for purposes of
land drainage or coast protection,
(c)
the installation in any building, structure or works of fittings forming, or to
form, part of land, including heating, lighting,
air-conditioning, ventilation,
power supply, drainage, sanitation, water supply, fire protection, security and
communications systems,
(d) the external or internal cleaning of
buildings, structures and works, so far as it is carried out in the course of
their construction,
alteration, repair, restoration, maintenance or
extension,
(e) any operation which forms an integral part of, or is
preparatory to or is for rendering complete, work of the kind referred
to in
paragraph (a), (b) or (c), including:
(i) site clearance, earth-moving,
excavation, tunnelling and boring, and
(ii) the laying of foundations,
and
(iii) the erection, maintenance or dismantling of scaffolding,
and
(iv) the prefabrication of components to form part of any building,
structure or works, whether carried out on-site or off-site,
and
(v)
site restoration, landscaping and the provision of roadways and other access
works,
(f) he painting or decorating of the internal or external
surfaces of any building, structure or works,
(g) any other work of a
kind prescribed by the regulations for the purposes of this
subsection.
(2) Despite subsection (1), construction work does not
include any of the following work:
(a) the drilling for, or extraction
of, oil or natural gas,
(b) the extraction (whether by underground or
surface working) of minerals, including tunnelling or boring, or constructing
underground
works, for that purpose,
(c) any other work of a kind
prescribed by the regulations for the purposes of this
subsection....
8 Rights to progress payments
(1) On and
from each reference date under a construction contract, a person:
(a)
who has undertaken to carry out construction work under the contract,
or
(b) who has undertaken to supply related goods and services under
the contract, is entitled to a progress payment.
(2) In this section,
reference date, in relation to a construction contract, means:
(a) a date determined by or in accordance with the terms of the
contract as the date on which a claim for a progress payment may
be made in
relation to work carried out or undertaken to be carried out (or related goods
and services supplied or undertaken to
be supplied) under the contract,
or
(b) if the contract makes no express provision with respect to the
matter—the last day of the named month in which the construction
work was
first carried out (or the related goods and services were first supplied) under
the contract and the last day of each subsequent
named month.
9 Amount
of progress payment
The amount of a progress payment to which a
person is entitled in respect of a construction contract is to be:
(a)
the amount calculated in accordance with the terms of the contract,
or
(b) if the contract makes no express provision with respect to the
matter, the amount calculated on the basis of the value of construction
work
carried out or undertaken to be carried out by the person (or of related goods
and services supplied or undertaken to be supplied
by the person) under the
contract.
10 Valuation of construction work and related goods and
services
(1) Construction work carried out or undertaken to be
carried out under a construction contract is to be valued:
(a) in
accordance with the terms of the contract, or
(b) if the contract makes
no express provision with respect to the matter, having regard to:
(i)
the contract price for the work, and
(ii) any other rates or prices
set out in the contract, and
(iii) any variation agreed to by the
parties to the contract by which the contract price, or any other rate or price
set out in the
contract, is to be adjusted by a specific amount, and
(iv)
if any of the work is defective, the estimated cost of rectifying the
defect.
(2) Related goods and services supplied or undertaken to be
supplied under a construction contract are to be valued:
(a) in
accordance with the terms of the contract, or
(b) if the contract makes
no express provision with respect to the matter, having regard to:
(i)
the contract price for the goods and services, and
(ii) any other rates or
prices set out in the contract, and
(iii) any variation agreed to by the
parties to the contract by which the contract price, or any other rate or price
set out in
the contract, is to be adjusted by a specific amount, and
(iv) if
any of the goods are defective, the estimated cost of rectifying the
defect,
and, in the case of materials and components that are to form
part of any building, structure or work arising from construction work,
on the
basis that the only materials and components to be included in the valuation are
those that have become (or, on payment, will
become) the property of the party
for whom construction work is being carried out.
11 Due date for
payment
(1) A progress payment under a construction contract becomes
due and payable:
(a) on the date on which the payment becomes due and
payable in accordance with the terms of the contract, or
(b) if the
contract makes no express provision with respect to the matter, on the date
occurring 10 business days after a payment
claim is made under Part 3 in
relation to the payment.
(2) Interest is payable on the unpaid amount of
a progress payment that has become due and payable at the rate:
(a)
prescribed under the Supreme Court Act 1970 in respect of unpaid
judgments of the Supreme Court, or
(b) specified under the construction
contract,
whichever is the greater.
(3) If a progress payment
becomes due and payable, the claimant is entitled to exercise a lien in respect
of the unpaid amount over
any unfixed plant or materials supplied by the
claimant for use in connection with the carrying out of construction work for
the
respondent.
(4) Any lien or charge over the unfixed plant or
materials existing before the date on which the progress payment becomes due and
payable takes priority over a lien under subsection (3).
(5) Subsection
(3) does not confer on the claimant any right against a third party who is the
owner of the unfixed plant or materials....
13 Payment
claims
(1) A person referred to in section 8 (1) who is or who
claims to be entitled to a progress payment (the claimant) may
serve a payment claim on the person who, under the construction contract
concerned, is or may be liable to make the payment.
(2) A payment claim:
(a) must identify the construction work (or related goods and
services) to which the progress payment relates, and
(b) must indicate
the amount of the progress payment that the claimant claims to be due (the
claimed amount), and
(c) must state that it is made under
this Act.
(3) The claimed amount may include any amount:
(a)
that the respondent is liable to pay the claimant under section 27 (2A),
or
(b) that is held under the construction contract by the respondent
and that the claimant claims is due for release.
(4) A payment claim may
be served only within:
(a) the period determined by or in accordance
with the terms of the construction contract, or
(b) the period of 12
months after the construction work to which the claim relates was last carried
out (or the related goods and
services to which the claim relates were last
supplied),
whichever is the later.
(5) A claimant cannot serve
more than one payment claim in respect of each reference date under the
construction contract.
(6) However, subsection (5) does not prevent the
claimant from including in a payment claim an amount that has been the subject
of
a previous claim.
14 Payment schedules
(1) A person on
whom a payment claim is served (the respondent) may reply to the
claim by providing a payment schedule to the claimant.
(2) A payment
schedule:
(a) must identify the payment claim to which it relates,
and
(b) must indicate the amount of the payment (if any) that the
respondent proposes to make (the scheduled amount).
(3) If
the scheduled amount is less than the claimed amount, the schedule must indicate
why the scheduled amount is less and (if
it is less because the respondent is
withholding payment for any reason) the respondent’s reasons for
withholding payment.
(4) If:
(a) a claimant serves a payment
claim on a respondent, and
(b) the respondent does not provide a
payment schedule to the claimant:
(i) within the time required by the
relevant construction contract, or
(ii) within 10 business days after the
payment claim is served,
whichever time expires earlier,
the
respondent becomes liable to pay the claimed amount to the claimant on the due
date for the progress payment to which the payment
claim
relates.
15 Consequences of not paying claimant where no payment
schedule
(1) This section applies if the respondent:
(a)
becomes liable to pay the claimed amount to the claimant under section 14 (4)
as a consequence of having failed to provide a
payment schedule to the claimant
within the time allowed by that section, and
(b) fails to pay the whole
or any part of the claimed amount on or before the due date for the progress
payment to which the payment
claim relates.
(2) In those circumstances,
the claimant:
(a) may:
(i) recover the unpaid portion of the
claimed amount from the respondent, as a debt due to the claimant, in any court
of competent
jurisdiction, or
(ii) make an adjudication application under
section 17 (1) (b) in relation to the payment claim, and
(b) may serve
notice on the respondent of the claimant’s intention to suspend carrying
out construction work (or to suspend
supplying related goods and services) under
the construction contract.
(3) A notice referred to in subsection (2)
(b) must state that it is made under this Act.
(4) If the claimant
commences proceedings under subsection (2) (a) (i) to recover the unpaid portion
of the claimed amount from the
respondent as a debt:
(a) judgment in
favour of the claimant is not to be given unless the court is satisfied of the
existence of the circumstances referred
to in subsection (1), and
(b)
the respondent is not, in those proceedings, entitled:
(i) to bring
any cross-claim against the claimant, or
(ii) to raise any defence in
relation to matters arising under the construction contract.
32 Effect
of Part on civil proceedings
(1) Subject to section 34, nothing in
this Part affects any right that a party to a construction contract:
(a)
may have under the contract, or
(b) may have under Part 2 in respect
of the contract, or
(c) may have apart from this Act in respect of
anything done or omitted to be done under the contract.
(2) Nothing done
under or for the purposes of this Part affects any civil proceedings arising
under a construction contract, whether
under this Part or otherwise, except as
provided by subsection (3).
(3) In any proceedings before a court or
tribunal in relation to any matter arising under a construction contract, the
court or tribunal:
(a) must allow for any amount paid to a party to
the contract under or for the purposes of this Part in any order or award it
makes
in those proceedings, and
(b) may make such orders as it
considers appropriate for the restitution of any amount so paid, and such other
orders as it considers
appropriate, having regard to its decision in those
proceedings.
34 No contracting out
(1) The provisions of
this Act have effect despite any provision to the contrary in any
contract.
(2) A provision of any agreement (whether in writing or not):
(a) under which the operation of this Act is, or is purported to be,
excluded, modified or restricted (or that has the effect of
excluding, modifying
or restricting the operation of this Act), or
(b) that may reasonably
be construed as an attempt to deter a person from taking action under this Act,
is void.”
The issues for determination in the first
proceedings as set out in the Club's overview written submissions
49 The Club identified these issues as follows:
“The
Club denies that Leighton is entitled to summary judgment in the amount of
$3,043,694.70 or at all under the Act upon the
following grounds:
(a) The
Alleged Payment Claim was not a valid payment claim within s.13(2) of the Act
because:
(i) it did not identify construction work (or related goods and
services) as required by s.13(2)(a);
(ii) there was no progress payment
claimed as required by s.13(2)(b);
(iii) it did not bear the endorsement
required by s.13(2)(c);
(b) Leighton was and is not a person entitled or
who claims to be entitled to a progress payment within s.13(1)
because:
(i) it was not a person entitled to a progress payment under
s.8(1);
(ii) as at the date of the Alleged Payment Claim there was no
reference date as and from which Leighton was entitled to a progress
payment
within s.8(1) and (2);
(iii) there was no amount calculated in accordance
with the terms of the Contract which constituted a progress payment to which
Leighton
was entitled under s.9(a);
(iv) as at the date of the Alleged
Payment Claim there was no progress payment under the Contract which had become
due and payable
within the meaning of s.11(1);
(c) The Alleged Payment
Claim was not a valid payment claim (in whole or in part) under s.13 of the
Act:
(i) to the extent that it claimed $736,487 for rock excavation,
because it was not served within 12 months after such work was last
carried out
as required by s.13(4)(b);
(ii) to the extent that it claimed $936,325 for
Delay Costs, because such claim was not permitted by the Act, the Delay Costs
not
being construction work to which the progress payment claimed by Leighton
related.
(d) Alternatively, if the Alleged Payment Claim were a valid
payment claim, the Club was not liable to pay the amount claimed by Leighton
by
reason that the Club served on Leighton a payment schedule within the meaning of
s.14 of the Act, being the Certificate issued
by Carver on 6 August
2003.
[Overview submissions [2.1]]
50 The convenient course is to next
set out a deal of the Club's detailed overview submissions addressing these
issues. As appropriate
the responsive submissions of Leighton will be referred
to, the convenient course being to determine the issues seriatim.
Is
there a Payment Claim? [section 13(2)(a)]
The Club's
submission
“Construction Work Not
Identified
3.1 To be valid and effective under the Act, a payment
claim must “identify the construction work (or related goods and
services) to which the progress payment relates”: s.13(2)(a). The
progress payment is that referred to in s.13(1) as elsewhere defined in the Act.
3.2 It is clear that the Act contemplates a regime for the presentation
by a builder to a proprietor (in cases such as the present)
of a series of
payment claims, each of which has its own reference date under the subject
contract on and from which the builder
becomes entitled to a progress payment:
s.8(1). In the case of the Contract, a new reference date (whenever it is) will
arise at
monthly intervals. Indeed, Leighton sent to the Club in the period
leading to the Alleged Payment Claim other purported payment
claims at monthly
intervals.
3.3 The response to a payment claim by the proprietor is the
provision of a “payment schedule” under s.14, which must
not only
indicate the amount of payment the proprietor is prepared to make but also the
reasons for withholding payment: s.14(3).
It is manifest, therefore, that if a
proprietor is to provide proper reasons for rejecting items claimed in the
payment claim in
a meaningful and informative manner, the proprietor must itself
receive an adequate, specific and descriptive identification of the
construction
work to which the builder’s payment claim relates. This accords not just
with general principle in respect of
demands for payment with
“self-executing” consequences, but particularly with the objects,
structure and intention of
the Act.
3.4 Moreover, the builder must
provide sufficient identification of the work to which the particular claimed
progress payment relates
(eg having regard to items and amounts claimed in
earlier payment claims) as will enable the proprietor to make an informed
decision
as to whether to make or deny payment.
3.5 The Alleged
Payment Claim does not satisfy any of these requirements.
3.6 Leighton’s document, as appears on its face, is a generic
claim in respect of the whole of the contract works and claimed
variations,
covering a period of 18 months (this was Progress Claim No. 18). It purports to
set out the whole of the work carried
out under the Contract, and the amount
claimed for the whole of that work, giving credit for all amounts previously
certified by
the Superintendent (and presumably paid). It does not identify the
items of work for which Leighton asserts it has been paid, and
the items of work
for which it alleges it has not been paid. It is simply not possible for the
reasonable reader of the Alleged
Payment Claim to discern, let alone make any
informed decision about, just what construction work it is to which this
specific claimed
progress payment relates. The use of such generic terms as
“electrical”, “external works” and the like compound
the
problem. The Alleged Payment Claim is not a payment claim under s.13 of the
Act.
3.7 The above analysis reflects the principles expressed by Austin
J in Jemzone Pty Limited v Trytan Pty Limited (2002) 42 ACSR 42 at 50-1:
“43 Section 13(2)(a) requires the payment claim to identify
the construction work to which the progress payment relates. In
my opinion,
this requires the claimant to identify the particular work that is the subject
of the progress payment, rather than simply
to identify in general terms the
work that is the subject of the construction contract as a whole. The document
in question refers
to “motel construction for Jemzone Pty Ltd”.
That falls well short of satisfying the requirement of s.13(2)(a). The
letter
sets out a table which calculates the amount due, but the table does not
identify any particular construction work other than
variations. It merely
begins by specifying a balance owing as at 9 February 2001, and then makes
adjustments for variations and
payments and other matters. At no stage is there
any statement purporting to identify the work carried out since the making of
the
last payment claim.
44 Section 13(2)(b) requires that the
progress claim must indicate the amount of the progress payment that the
claimant claims to
be due for the construction work done. This requirement is
also not satisfied by the document in question. Since the document fails
to
identify the construction work to which the progress payment relates, it cannot,
and does not, indicate the amount of the progress
payment said to be due for
that construction work. It merely identifies an overall balance owing and makes
some adjustments to that
balance”.
3.8 Austin J’s view
was not shared by Nicholas J in Walter Construction Group Limited v CPL
(Surry Hills) Pty Limited [2003] NSWSC 266 where it was said at [63]-[66]
that it was sufficient if the claim document merely identified the construction
work in terms of the
contract and location with respect to which it was
undertaken. The principles enunciated by Austin J are, the Club submits, those
which would satisfy the ordinary expectations of the construction industry and
the community generally, and which give purpose and
effect to the statutory
provisions.”
Holding
51 In my view the following
submissions of Leighton on this issue are of substance. In short:
· Section 13(2)(a) requires to be construed in a manner which
facilitates the operation of the Act.
· By section 9(a), the
amount of a progress payment is “the amount calculated in accordance
with the terms of the contract”. The requirement in section 13(2)(a)
to “identify the construction work ... to which the progress payment
relates” requires to be construed in a manner which facilitates
this calculation.
· Under clause 37.1 of the Contract, each
progress claim “shall include details of the value of WUC done and may
include details of other moneys then due to the Contractor pursuant
to the
provisions of the Contract”. Clause 37.2(a) of the Contract then
requires the Superintendent to issue “a progress certificate payment
schedule evidencing the Superintendent’s opinion of the moneys due from
the Principal
to the Contractor”.
· The contractual scheme
contemplates a claim for, and an assessment of, inter alia, “the value
of WUC done” and a credit for the amount previously certified.
· Accordingly, it is necessary to assess the value of the relevant
work done and to give an appropriate credit for the purposes
of both the
Contract and the Act. It follows that the Payment Claim will not fail to comply
with section 13(2)(a) merely because
it has been prepared on this
basis.
52 I would respectfully agree with the view taken by Nicholas J in
Walter at [65] that a purpose of the Section 13(2)(a) requirement
is that a
respondent served with a payment claim be provided with adequate information to
enable it to provide a payment schedule
under section 14.
53 Nicholas J
was in that case satisfied that the subject payment claim adequately identified
the work (or related goods and services)
to which the progress payment related.
This was essentially a question of fact and it is somewhat difficult from the
description
(given at [13], [14] and [15] ) in that judgment to follow the
precise detail which would have appeared in the documents giving
particulars
identifying the items of work claimed to have been carried out under the
Contract [the documents appear to have been
included in Exhibit A before his
Honour]. It does not seem to me to be a proper reading of the judgment (at [66]
and in particular
the last sentence of that paragraph) to regard it as a holding
that all that was necessary was to state in a payment claim that it
covered work
and related goods and services provided under a particular contract in respect
of a named project.
54 I am further in agreement with the following view
taken by Davies AJA in Hawkins Construction (Aust) Pty Ltd v Mac’s
Industrial Pipework Pty Ltd [2002] NSWCA 136, paragraph
20:
“However, subs (2) of s13 of the Act should not be approached
in an unduly technical manner keeping in mind the considerations
to which
counsel pointed. The terms used in subs (2) of s13 are well understood words of
the English language. They should be given
their normal and natural meanings.
As the words are used in relation to events occurring in the construction
industry, they should
be applied in a common sense practical
manner.”
55 To the extent that the authorities disclose a
difference of approach in this regard, my view is that the analyses and
expressions
of opinion by Nicholas J in both Walter Construction Group Ltd v
CPL (Surry Hills) Pty Ltd [2003] NSWSC 266 (“Walter”),
paragraphs 63-66 and 81-85, and in Parist Holdings Ltd v WT Partnership
Australia Pty Ltd [2003] NSWSC 365 (“Parist”), paragraphs 27-29
adopted by Bergin J in Paynter Dixon Constructions Pty Ltd v JF & CG
Tilston Pty Ltd [2003] NSWSC 869, paragraphs 30-34, should be preferred to
the views expressed as obiter by Austin J in Jemzone Pty Ltd v Trytan
Pty Ltd [2002] NSWSC 395 (“Jemzone”), generally for the reasons
set out above.
56 In the result each of the Club's submissions in respect
of the proposition that the subject Payment Claim was invalid for the reason
that it failed to identify the construction work (or related goods and services)
to which the progress payment relates is rejected.
In the present case I am
satisfied that the payment claim identified the construction work (or related
goods and services) to which
it related. The Payment Claim complied with section
13(2)(a), the salient considerations being that it:
(i) identified the
Contract and the Campbelltown Catholic Club project (TB 838,
845);
(ii) provided a main summary of the Contract price, the amount
approved to date, the amount previously certified and the balance due
(TB
839);
(iii) included a summary of the work carried out broken down into
different trades and stating the % complete for each trade. 34
items are
specifically set out under the heading “Trade” (TB 840-841);
and
(iv) included a breakdown of all the variations claimed which states
the % complete for each variation. There are in excess of 100
variations
individually described over more than 2 pages (TB 842-844).
Was a
Progress Payment claimed? [section 13(2)(b)]
The Club's
submission
No Progress Payment
Claimed
3.9 S.13(2)(b) requires that a payment claim, to be valid
and effective, must “indicate the amount of the progress payment that
the claimant claims to be due”. The Alleged Payment Claim fails this
requirement.
3.10 In providing the Alleged Payment Claim, Leighton
elected to adopt a format which duplicated the material it sent under the
contract
to the Superintendent from whom it sought review and certification.
Thus, the Alleged Payment Claim did not seek any payment from
the Club at all,
but rather attached Progress Claim No. 18 for the “review and
subsequent certification”. Clearly, the expression of a sum (which
itself is not precise having regard to the GST exclusion) for review and
certification
does not constitute an amount claimed to be due under the Act from
the Club. Leighton’s attempt to pass off what was, and
was intended to
be, a progress claim made to the Superintendent as a payment claim under the Act
fails.
3.11 The reference to the “Total Amount Due” on the
first page of the attachment to the covering letter does not save
the document,
for that is merely the amount submitted to the Superintendent for review and
certification by him.
3.12 Finally, the incorporation of the Statutory
Declaration “for this Claim” confirms that the Alleged
Payment Claim was not in fact a payment claim under s.13.
57 I have given close consideration to the particular submission
appearing in paragraphs 3.9 – 3.12 of the above submissions
on the special
facts presently before the Court. In Emag Constructions Pty Limited v
Highrise Concrete Contractors (Aust) Pty Limited [2003] NSWSC 903 the Court
had occasion in another context to consider the necessity for strict compliance
to the letter with the codified procedures provided for in the Act. That
judgment made the point that the whole of the rationale underpinning
the
procedures laid down by the Act is directed at providing a quick and efficient
set of procedures permitting recovery of progress
payments and the quick
resolution of disputes in that regard; hence time limits under the Act being
strict, and the consequence of
failure to comply with the stipulated time limits
being significant (cf Emag at [35] [38] [41]-[43]).
58 The same
approach requires to be taken to the very special significance of the wording to
be found in a payment claim made under
the Act. That this is apparent is to be
seen from the draughtsman having included the express requirement in section
13(2)(c) that
a payment claim must state that it is made under the Act.
There is no room for ambiguity of any type and it is critical that the recipient
of a payment
claim be made aware by the terms of that claim that the
provisions of the Act have been engaged. The appropriate test is that
identified in Parist by Nicholas J at paragraph 28:
“The
principles relevant to the question of compliance with s13(2) were discussed in
Hawkins Construction (Aust) Pty Ltd v Mac’s Industrial Pipework Pty
Ltd [2002] NSWCA 136 par 20; Beckhaus v Brewarrina Council [2002] NSWSC 960 para 73-76; Walter Construction Group Ltd v CPL (Surry Hills) Pty
Ltd [2003] NSWSC 266 paras 63-65; 81-85. It must be clear on the face of
the document(s) which constitute the statutory payment claim that the
information conveyed meets the requirements of s13(2). ‘The test is
an
objective one. In deciding the meaning conveyed by a notice a court will ask
whether a reasonable person who had considered the
notice as a whole and given
fair and proper consideration would be left in any doubt as to its
meaning” [Walter Construction Group Pty Ltd para 82]
59 The
question is a close one in terms of the document here claimed to have
constituted the relevant payment claim. The so-called
progress claim is in fact
enclosed as an attachment to the covering letter. The covering letter which
uses the words "This is a
payment claim made under the [Act] ". The attached
document does not use those words. Whilst in other fields of discourse this
may
be regarded as a matter of no moment, it must be appreciated that one could have
a circumstance where a covering letter may enclose
a number of documents, yet
still itself purporting to be the vehicle conveying the section 13(2)(c)
endorsement. It would not be appropriate to hold that the endorsement
provision
had been complied with if, for example, only some of those enclosed
documents were claimed to be the relevant payment claim. This is not an
area in which the recipient of the payment claim should be in any doubt from
its terms as to what it is and as to the fact that it is made
under the Act.
60 The covering letter of the document in question in
fact attaches as the last sheet, what is referred to in the covering letter
as
"the statutory declaration for this claim". Those words are meaningless
in this context, having no part to play in relation to the procedure under the
Act which purports to
be engaged by the last sentence of the covering letter.
The statutory declaration would be relevant where a progress claim was made
to
the Superintendent, but is not relevant where the Act is sought to be engaged
and forms no part of a payment claim.
61 For those reasons the attachment
of the statutory declaration was otiose. Further the words "for this
claim" which appear in the sentence "the statutory declaration for
this claim is also attached", suggest quite incorrectly, that the
attachment is an attachment by way of a document forming part of the payment
claim made under
the Act. These are matters which are calculated to lead to
confusion to the recipient of the covering letter and of its enclosures.
They
are calculated to logically put the recipient in mind of the progress claim
procedure generally adopted under the contract
condition.
62 Then there
is the question concerning the tail end of the first paragraph of the covering
letter. It will be recalled that this
paragraph was in the following
terms:
“We attach Progress Claim No. 18 for work complete on the
above Project for the period ending 28 July 2003 for the sum of $2,789,517.00
(excluding GST) for your review and subsequent
certification.”
63 The words "for your review and subsequent
certification" are unnecessary and otiose. They could and should have been
left out. There is no particular occasion for comment once the necessary
section
13(2)(c) endorsement appears. What might, in place of these tail end words,
have been unexceptional, but would be neither
necessary nor particularly
desirable, could have been words such as: "your attention is drawn to the
provisions of section 14 (1) of the Act in this regard". Even that form of
wording could cause difficulty because it is no part of the role of the sender
of a payment claim to endeavour
to inform the recipient of any particular
provisions of the Act.
64 What then is to be made of the tail end words
to this paragraph? The sending of a payment claim is a formal act so that if
the
words "for your review" are to be read as no more than as synonymous
with "for your attention", there would not, it seems to me, be any
particular problem raised by those words. However the words "for your review
and subsequent certification" are the very words used and to be expected to
be used when the contractor submits progress claims to the Superintendent under
contract
condition 37.1. So that arguably the recipient of the covering letter
could be expected to find the full phrase curious, and the
more so because of
the reference to the anticipated "subsequent certification" by the
recipient of the claim. These words are not particularly apt at all to describe
the entitlement of a person on whom a payment
claim is served, to reply to the
claim by providing a payment schedule to the claimant. Here again they are apt
to cause confusion
and in an environment where the statutory scheme requires
strict compliance to the letter with the codified
procedures.
65 Ultimately I have come to the conclusion that
notwithstanding the above described anomalies in the unnecessary use of the tail
end words in the first paragraph of the covering letter and the attachment of
the so-called "Statutory Declaration for this claim",
a reasonable person
reading the covering letter and the attachments as a whole would have been left
in no material doubt as to its
meaning essentially conveyed by the last sentence
in the covering letter.
66 There is no, it seems to me, substance in the
Club's submission that the reference in the first paragraph of the covering
letter
to the claim being "for the sum of $2,789,517 (excluding GST)" is
problematic in the circumstances. The page which follows makes
plain that the
total amount due and the subject of the claim was $3,068,468.
67 For
those reasons the Club's submissions on the section 13 (2) (b) "No Progress
Payment Claimed" issues are rejected.
The Endorsement [section
13(2)(c)]
The Club's submission
“3.13 The
document which purports to identify the construction work for the purpose of
s.13(2)(a) is the attached Progress Claim
No. 18. If the requirements of the
Act as to form are to be satisfied, it is that document (if it were otherwise a
payment claim
within s.13) which must bear the required endorsement to satisfy
s.13(2)(c). It does not do so and there has been no strict compliance
with the
statutory provisions, as is required.”
68 As will appear from the
reasons already given, the issue here raised is one of particular moment in the
context of the rigorous
provisions of the Act. The Act gives a very short
window of opportunity to the recipient of a payment claim to reply to that
claim.
There is no occasion provided for in the Act for any request for more
particulars [as for example for confirmation as to which part
of the materials
served are said to comprise the payment claim] to be made by the respondent to
the person who serves the payment
claim. Strict compliance with the statutory
provisions is required and in relation to this particular subsection there is
the greatest
of importance in it being complied with to the letter. Only the
payment claim itself must state that it is made under the Act.
69 At a
factual level the matter is resolved by answering the question as to whether or
not on the one hand the “payment claim”
comprised the covering first
page letter or on the other hand, comprised the whole of the subject materials
including that page.
In my view the latter is the correct analysis leading to
the result that Leighton in fact complied with the section 13(2)(c) requirement.
Leighton not within s13(1) [“Person referred to in section
8(1)”; General Analysis]
The Club's
submission
“Structure of the Act
4.1 As is
obvious from the array of judicial views expressed in the series of cases
spawned by this legislation, the Act does not
lend itself to ready
comprehension. However, the following emerges from an analysis of the
provisions:-
- Leighton may serve a payment claim if it is a
“person referred in s.8(1) who is or who claims to be entitled to a
progress
payment”.
- Turning to s.8(1), it provides that on and
from “each reference date under a construction contract” a person
who undertakes
work or supplies goods and services is entitled to a progress
payment.
- To give meaning to this provision, it is necessary to
consider the meaning of two of its terms ie. “reference date”
and
“progress payment”. “Reference date” is defined in
s.8(2) to mean a date determined by or in accordance
with the terms of the
contract as the date on which a “claim for a progress payment” may
be made (provided that if there
is no express provision therefore the reference
date will be the last day of the month).
- The meaning of
“progress payment” in s.8 is to be determined from its definition in
s.4, which strangely is that it
is a “payment to which a person is
entitled under s. 8”.
4.2 Read literally, these circular and
inelegant provisions permit a payment claim to be served by a person who under
s.8(1) is at
each reference date a person entitled to a progress payment, being
a payment to which that person is entitled under s.8(1). To understand
how the
provisions can have any effective operation, it is necessary to analyse the
requirements for the reference date and progress payment.
Reference Date
4.3 Reference date is fixed by
s.8(2), firstly (by s8(2)(a)) as being a date determined by or in accordance
with the “terms of the contract as the date on which a claim for a
progress payment may be made”. This may mean either:
(i) the
date fixed by the contract for the making of a claim for a progress payment
under the Act; or
(ii) the date fixed by the contract for the making of a
claim for a progress payment under the contract.
Secondly, if no date is
fixed by the contract then (by s8(2)(b)) the date is
(iii) the last day
of the month.
4.4 Clearly the Contract between Leighton and the Club did
not fix a date for a claim to a progress payment under the Act (ie. (i)
above)
– it makes no reference to the Act.
4.5 It is submitted that the
term “claim for a progress payment” in s.8(2)(a), properly
construed, refers to a progress payment under the contract (i.e (ii) above); if
so, the Contract here provided
that the date for a claim for a progress payment
could only be made by Leighton upon the Club, after the Superintendent received
and processed Leighton’s progress claim. Clause 37 lays down a regime by
which Leighton was to lodge, with the Superintendent,
by the 28th day of each
month its monthly progress claim for the Superintendent’s review and
certification. Only after certification
under clause 37.2 was Leighton entitled
to submit a claim to the Club. Leighton became entitled to make to the Club its
claim for
its progress payment based on Progress Claim No. 18 only on 6 August
when the Superintendent issued the Certificate. Accordingly,
the appropriate
reference date was 6 August, so that Leighton was not a person entitled
to a progress claim in terms of s.13(1) and s.8(1) as at 28 July when it
issued
the Alleged Payment Claim (the Club will seek leave to amend this Defence
accordingly).
4.6 The only other possibility, for which Leighton
contends, is that the term refers to the date on which under Clause 37.1 of the
Contract Leighton may lodge a progress claim i.e 28th day of the month. But
that cannot be the date to which the Act refers, because
such a progress claim
is not a claim on the Club as proprietor but is made to the Superintendent for
review and certification.
4.7 Alternatively, if (as per (iii) above) the
Contract makes no express provision as to when a claim for a progress payment
may be
made (because the claim to the Superintendent envisaged by clause 37.1 is
not a claim upon the Club) then s.(2)(b) deems the reference date to be
the last day of the month, here 31 July and again the Alleged Payment Claim will
be ineffective (again, leave will be sought
to incorporate this alternative in
the Defence).
4.8 For the above reasons, the Alleged Payment Claim could
have only have been valid if it had been issued upon the Superintendent’s
certification on 6 August 2003. It was not and consequently is ineffective.
Leighton will still not be a person entitled to a progress payment as
that term is properly to be construed:...”
70 In my view the
submissions of Leighton on this issue are of substance. They are broadly
adopted in what follows.
71 The contention of the Club that as at the
date upon which the Plaintiff served the Payment Claim, the Plaintiff was not
entitled
to a progress payment in any amount, in that the Superintendent had not
certified the amount claimed or any part thereof as payable,
so that there
simply was no amount calculated in accordance with the terms of
the Contract as required by section 9 of the Act (Defence, paragraph C18(a)) is
rejected.
The contention has been considered and in my view correctly rejected
on a number of occasions:
“Fyntray Constructions Pty Ltd v
Macind Drainage & Hydraulic Services Pty Ltd [2002] NSWCA 238,
paragraphs 74-75:
[74] “Section 8 means that, on and from
25th of each month (s8(2)(a)(i)), the plaintiff became entitled to a progress
payment in
accordance with the provisions of the Act. The amount of that payment
was as calculated in accordance with the contract (s9(a)).
Such payment became
payable in accordance with the provisions of the Act at the end of the following
month (s11(a)). In so far as
the plaintiff submitted to the contrary, on the
basis that the contract made no provision as to when a progress payment became
due
and payable in accordance with the terms of the Act, I would reject that
submission: in my opinion, s11(a) is referring to the terms
of the contract in
respect of progress payments payable under the contract.
[75]
Accordingly, on and from 25 April 2001, the plaintiff was entitled to make
a payment claim under the Act, and was entitled to be paid
pursuant to that
payment claim the amount calculated in accordance with the terms of the
contract. That amount contemplated the accumulation
of entitlements from
previous monthly progress claims. The claim under the Act which the plaintiff
made on 2 May 2001 enclosed copies
of the three progress claims (Nos. 9, 10 and
11) and thereby sufficiently particularised under s13(2) a claim for a total of
$74,191.65,
being the total of the amounts specified under those three progress
claims, less GST. The defendant disclaimed any submission that
the inclusion of
the additional $231.93 invalidated the payment claim; and accordingly, the
plaintiff's claim under the Act was a
valid claim to the extent of
$74,191.65.”
Beckhaus v Brewarrina Council [2002] NSWSC 960,
paragraphs 55 and 60-65:
[55] “Thus, in the present
circumstances as the contract has the relevant provisions a contractor is
entitled under s8 to a statutory
‘progress payment’ under the Act on
the date the progress claim may be made under the contract. Such a statutory
progress
payment becomes due and payable under s11 on the date when the
contractual payment becomes due and payable. In this case it is 14
days after
the submission of the contractual progress claim.”
[60]
“The Act obviously endeavours to cover a multitude of different
contractual situations. It gives rights to progress payments
when the contract
is silent and gives remedies for non-payment. One thing the Act does not do is
affect the parties' existing contractual
rights. See ss3(1), 3(4)(a) and 32. The
parties cannot contract out of the Act (see s34) and thus the Act contemplates a
dual system.
The framework of the Act is to create a statutory system alongside
any contractual regime. It does not purport to create a statutory
liability by
altering the parties' contractual regime. There is only a limited modification
in s12 of some contractual provisions.
Unfortunately, the Act uses language,
when creating the statutory liabilities, which comes from the contractual scene.
This causes
confusion and hence the defendant's submission that the words
"person who is entitled to a progress payment under a construction
contract" in
s13(1) refers to a contractual entitlement.
[61] The trigger
that commences the process that leads to the statutory rights in s15(2) is the
service of the claim under s13. That can
only be done by a person who ‘is
entitled to a progress payment under a construction contract’. The words
‘progress
payment’ are a defined term in the Act. It means a payment
to which a person is entitled under s8. That section fixes the time
of the
‘entitlement’ given by the section by reference to the contractual
dates for making claims or, if there is no
contractual provision, for making
claims by reference to a four week period. Section 9 deals with the amount of
such a statutory
progress payment. Importantly, s9 uses similar words to s13 in
that it refers to ‘a progress payment to which a person is entitled
in
respect of a construction contract’ and then directs determination of that
amount by reference to both contractual amounts
or if no contractual amount on
the basis of the value of the work done.
[62] Section 11 then
deals with the due date for payment in respect of ‘a progress payment
under a construction contract’.
It does it also by reference to
contractual due dates and if no such provision then by reference to a two-week
period. One thus has
a series of sections which create a statutory right to a
progress payment by fixing entitlement, the date for making claims, amount
of
claims and due date for payment of claims. The statutory right to claim is for
both situations, namely, where a contract provides
for such claims and where it
does not.
[63] Thus s13 merely continues on the statutory
procedure and the opening words must be a reference to the statutory entitlement
created
in the previous sections not the contractual entitlement submitted by
the defendant. If the defendant's submission were correct it
would mean that in
respect of contracts which do not provide for progress payments there is no
ability to recover the statutory right
to progress claims in Division 3. This
consequence makes otiose the earlier provisions of the Act and defeats its
express object
which is to:-
‘ensure that any person who carries
out construction work (or who supplies related goods and services) under a
construction
contract is entitled to receive, and is able to recover, specified
progress payments in relation to the carrying out of such work
and the supplying
of such goods and services.’
[64] In my view the
submissions of the defendant are simply not arguable.
[65] As
under 42.1 the plaintiff is entitled to progress payments there is no reason why
he cannot make the statutory claim at the same
time as his contractual claim.
The statutory claim must comply with Section 13(2). On its face the document
appears to do this and
there was no submission to the
contrary.”
Walter Construction Group Ltd v CPL (Surry Hills) Pty
Ltd [2003] NSWSC 266, paragraphs 28-32 and 52-55:
[28]
“...it was submitted that as a precondition to being entitled to
serve a payment claim the claimant must be, in the words of
s13(1),
“entitled to a progress payment under a construction contract”.
Reliance was placed upon the process under cl
42.1 of the contract which follows
delivery by the Contractor of a claim for payment whereby liability of the
principal for payment
is established. This process obliges the Superintendent to
assess the claim within 14 days and to issue a payment certificate stating
the
amount of payment to be made. It also provides that within 28 days of receipt of
a claim for payment, or within 14 days of issuing
a payment certificate,
(whichever is the earlier) the principal is obliged to pay an amount not less
than that shown on the payment
certificate, or if no certificate is issued, the
amount of the claim.
[29] It was submitted that under the
contract no obligation to pay arises until the expiry of the relevant time
period. In this case, the
time for issuing the payment certificate expired on 3
January 2003 absent which the Plaintiff became entitled to payment upon expiry
of the period ending 17 January 2003. Thus it was put that as at 20 December
2002 under the contract the Plaintiff was not entitled
to payment of progress
payment 20, and the Defendant was not liable to pay it. In other words, until
the process by either certification
or lapse of time had taken place the amount
payable would not be established.
[30] This situation attracted
consideration of s9(a) of the Act which provides:
‘9 The amount of
a progress payment to which a person is entitled in respect of a construction
contract is to be:
(a) The amount calculated in accordance with the
terms of the contract, or’
[31] It was then submitted that,
absent proof of entitlement to an amount calculated in accordance with the terms
of the contract, the
amount of a progress payment to which a person was entitled
would not be established within the meaning of s9(a). It followed that
the
requirement of s13(2)(b) would not be met. It was argued that the expression in
this sub-para “the amount of the progress
payment that the claimant claims
to be due for the construction work done” refers to the amount which has
actually been determined
under the contract to be due and payable to the
claimant. In this case, therefore, there having been no determination as at 20
December
2002, of an amount pursuant to cl 42.1 of the contract, no amount could
properly be indicated in the payment claim “to be due”
and,
consequentially, it was not a valid claim within the meaning of
s13(1).
[32] Reference was made to Beckhaus v Brewarrina
Council [2002] NSWSC 960 in which the court considered a submission to
similar effect, namely that unless a progress payment under a contract is due
and payable
in accordance with the terms of the contract there is no statutory
entitlement under the Act, that is to say the words “person
who is
entitled to a progress payment under a construction contract” in s13(1)
refers to a contractual entitlement. It was
submitted that Macready, AJ, erred
in rejecting the submission when he held (para 63) that the opening words of
s13(1) must be a
reference to the statutory entitlement created in the previous
sections and not to the entitlement under the contract....
[52]
In Beckhaus v Brewarrina Council, Macready, AJ, considered a
submission with reference to s13(1) of the Act that unless a progress payment
under a contract is due
and payable in accordance with the terms of the contract
there is no statutory entitlement under the Act. After detailing relevant
provisions of the Act he expressed his conclusions as follows:
[At this
point, Justice Nicholas set out paragraphs 60-65 of Beckhaus which are
set out above]
(There was no challenge to these findings in the appeal from
His Honour's order for summary judgment: Brewarrina Shire Council v Beckhaus
Civil Pty Ltd [2003] NSWCA 4).
[53] I respectfully agree with
his Honour's analysis and conclusion. They are consistent with the opinion of
Heydon JA in Fyntray Constructions Pty Ltd v Macind Drainage and Hydraulic
Services Pty Ltd [2002] NSWCA 238 at para51).
‘51 Fourthly,
the two limbs of that part of the definition of “reference date”
appearing in section 8(2)(a) reveal
a legislative intention to permit payment
claims to be made either by reference to a contractual date for making a claim
(that is,
under cl 42.1) or by reference to a contractual date by reference to
which the amount of the progress payment is to be calculated
(that is, taking
into account cl 42.2). .... While cl 42.1 compels monthly claims, section 8
contemplates entitlements to progress
payments arising not only by reason of the
dates for making claims under cl 42.1, but by reason of a date by reference to
which the
amount of the progress payment is to be calculated under cl 42.2, and
the latter date includes periods which may be greater than
the preceding
month’.
(See also Hodgson, JA paras 74, 75).
[54] As has
been found, it was agreed that the contract date for making the claim for
December was 20 December 2002. That being so, in
my opinion the Plaintiff, on
that date, was a person entitled to a progress payment within the meaning of
s13(1).
[55] In my opinion, therefore, the Defendant's submission
that a claimant's entitlement to the amount claimed must be established under
the contract before a person is entitled to make or serve a payment claim under
s13(1) of the Act is unsound.”
Karimbla Construction v Alliance
Group Building [2003] NSWSC 617, paragraph 6:
[6] “In
view of the way the alleged debt is described in the statutory demand and the
fact that the so-called "payment claim" of
3 January 2002 is asserted by
Alliance as the sole source of that debt, the only issues relevant to the
question whether, as Karimbla maintains, there is a genuine dispute as to
the existence of the debt are issues going to the effect of the 3 January 2002
document
from the perspective of the Security of Payment Act. The debt's source
is precisely stated in the statutory demand: it is said to
be the payment claim
under s13, with the result that it is a payment liability under s14(4) that is
asserted in the statutory demand
to be the debt claimed. For that reason, I
consider it inappropriate to address the question whether the parties' contract
or any
other matter may have been the source of a debt of $394,364.13 on the
part of Karimbla, independently of the Security of Payment
Act.”;
72 The defendant’s submission in terms of the proper
interpretation of sections 9, 10 and 11 has the potential to frustrate
the
operation of the Act whenever the relevant construction contract requires
certification of a progress claim and payment of the
amount certified.
73 That submission is also inconsistent with the following views
expressed by McDougall J in Abacus v Davenport [2003] NSWSC 1027:
“30 Although it is not clear from the summons, Abacus' case,
so far as I could understand it (and I interpose that my understanding
was
hindered by the failure of Abacus specifically to address its submissions,
written or oral, to the individual errors of law and
jurisdictional errors
asserted in the summons) was that the five errors of law that I have set out
constituted jurisdictional errors
of law. That was said to be the case because
the Act did not permit an adjudicator to ‘step into the shoes of architect
[sic]’.
In other words, as I understood the submission, it was Abacus'
case that where, under a contractual mechanism such as clause 10.02,
the
architect (or person fulfilling the role of the architect) had certified the
amount of a progress claim, the builder's only entitlement
was to the progress
claim so certified, and an adjudicator under the Act had no power to re-evaluate
the architect's certification
...
33 I do accept the submission that was
put for Abacus that the legislature intended that, so far as possible, an
adjudicator should
determine a builder's entitlement to a progress payment in
accordance with any applicable terms of the contract. That follows from
ss 9(a)
and 10(1)(a) of the Act; cf Musico at para [77].
34 Clause 10 of
the contract deals with payment and adjustment of the contract sum. Clause 10.01
provides for the making of progress
claims. Clause 10.02 provides for the issue
(by the architect) of progress certificates. Clause 10.07 provides that, in
effect, the
builder's entitlement is to be paid, as a progress payment,
‘the amount specified by that certificate’.
35 It cannot be
correct to say that an adjudicator under the Act is bound by the terms of any
progress certificate issued, under
a contractual regime of the kind that I have
described, by the architect or someone in the position of the architect. That
would
mean that an adjudicator could not make a determination that was
inconsistent with a certificate that was (for example) manifestly
wrong. Indeed,
it would mean that an adjudicator could not make a determination that was
inconsistent with a certificate that had
been issued in bad faith, or as the
result of fraudulent collusion to the disadvantage of the builder.
36
Further, as was submitted for Renascent, it is not uncommon for building
contracts to provide that it is the proprietor, or someone
who is the
proprietor's alter ego or agent, to occupy the certifying role that, under the
form of contract presently under consideration,
is occupied by the architect. In
those circumstances, if the submission for Abacus be correct, an adjudicator
would be bound by a
certificate issued by a proprietor, or by its agent or alter
ego, in bad faith, or one that flatly and obviously disregarded the
rights of
the builder.
37 Such a construction would undermine in a very serious
way the evident intention of the legislature that is embodied in the Act.
It
would enable an unscrupulous proprietor (either by itself, if the contract so
permitted, or with the collusion of an unscrupulous
certifier) to set at nought
the entitlement to progress payments that the Act provides and
protects.
38 I do not think that the construction advocated by Abacus is
required by the Act. It is correct to say that the amount of a progress
payment
is to be ‘the amount calculated in accordance with the terms of the
contract’ where the contract makes provision
for that matter (s 9(a)). It
is equally correct to say that construction work is to be valued ‘in
accordance with the terms
of the contract’ where the contract makes
provision for that matter (s 10(1)(a)). However, a reference to calculation or
valuation
‘in accordance with the terms of the contract’ is a
reference to the contractual mechanism for determination of that
which is to be
calculated or valued, not to the person who, under the contract, is to make that
calculation or valuation. In the
present case, it means that Mr Davenport was
bound to calculate the progress payment in accordance with cl 10.02 of the
contract.
It does not mean that Mr Davenport was bound by the architect's
earlier performance (or attempted or purported performance) of that
task.
39 In the present case, what Mr Davenport was required to do was
to undertake for himself the task that the architect had purported
to undertake.
He was not required simply and only to apply his rubber stamp and initials to
the results of the architect's labours.
40 I therefore reject the
fundamental proposition on which Abacus' case was based. Nonetheless, it is
necessary to examine each of
the errors of law to see whether jurisdictional
error is demonstrated.”
74 Whilst there is some substance in the
Club's submission concerning the circularity where section 4 defines
"progress payment" as meaning "a payment to which a person is entitled
under section 8", when section 8 then merely uses the same term "progress
payment", it is plainly necessary to make sense of the statutory scheme. And
it is also necessary to endeavour to keep in mind the terms of
[and reason for]
the amendment to section 13 (1) which inter alia added the words "or who
claims to be", hence expanding the description of persons having the right
to serve a payment claim as provided for under the anterior form of wording.
In
that regard the legislature clearly intended to broaden the scope of section
13(1).
75 The particular focus placed by the Club on the meaning of
the words "claim for a progress payment may be made" appearing in section
8(2)(a) is shortly answered in the present context by the fact that Leighton was
entitled under the subject
contract to make a progress claim by a procedure, the
first stage of which involved written notification to the superintendent.
[Contract
clause 37.1] Hence the section 8(2)(a) “date
determined by or in accordance with the terms of the contract as the date on
which a claim for a progress payment may be made", was the date when
Leighton was entitled to give its progress claim to the Superintendent.
76 I note in passing that the 2nd sentence of clause 37.1 appears to
mean that if a progress claim is lodged with the Superintendent
on a date
earlier than the 28th day of a particular month, it is deemed to have been made
on the 28th day of the month.
77 For those reasons the Club's broader
submission that Leighton was not as at 28 July a person entitled to make a claim
for a progress
payment within the meaning of section 8(2)(a) is
rejected.
Progress Payment [Section 13(1) – Person entitled to a
progress payment]
The Club’s
submission
“4.9 Whether Leighton is a person entitled to, or
claims to be a person entitled to, a progress payment in terms of s.13(1)
also
depend upon the meaning to be attributed to progress payment ie in s.8(1)
and s.13(1). As observed above, the definition provision in the Act is of little
assistance however; the term is to be
construed in its statutory context:
Project Blue Sky Inc. v Australian Broadcasting Authority [1998] HCA 28; (1998) 194 CLR
355 at 381. In that context, in particular by reference to ss.9, 10 and 11, its
meaning can be readily discerned. Thus, a builder will
become entitled to a
progress payment (s.8) in the sense used in those sections, that is, in the
amount specified in s.9 or s.10,
and at the time identified by
s.11.
4.10 S.9 expressly provides that the amount of any progress payment
to which Leighton became entitled is to be determined by reference
to the amount
calculated in accordance with the terms of the contract, and the progress
payment so calculated becomes due and payable under s.11 on a date calculated
in accordance with the terms of the contract.
4.11 Upon its proper
construction, this is the only sensible way the Act can be read and can take
effect. In this way, the sections
are coherent and cohesive. The result is that
Leighton will be a person entitled under the Act, at the relevant reference
date, to
a progress payment in the amount and upon the date determined in
accordance with the terms of the contract. In this case, as at 28 July when
the Alleged Payment Claim was issued, Leighton was not entitled to any amount
calculated in accordance
with the Contract. It became so entitled only upon
issue of the Superintendent’s Certificate on 6 August (and then only for
$23,674 being the amount certified – since paid). Leighton was not on 28
July a person entitled to a progress payment under
s.13(1) of the
Act.”
78 For the reasons already given these submissions which
supplement and/or overlap with the earlier submissions are
rejected.
Claim to be entitled [section 13(1)]
The
Club’s submission
“4.12 Leighton alternatively says it is
a person who claims to be entitled to a progress payment within s.13(1). It is
accepted
that these additional words recently inserted by amendment must have
some meaning. Clearly enough the legislature intended to broaden
the scope of
the section. Nevertheless, the legislation could not contemplate a specious or
spurious claim and must be taken to
refer to a claim which is genuine or bona
fide. The peremptory procedures available under the Act, with their potentially
serious
consequences for the parties, would otherwise be open to ready abuse. A
contractor could serve a purported payment claim, knowing
full well that there
were no monies owing, in the expectation that (if the requirements for a payment
schedule under the Act were
overlooked or not appreciated), he might thereby
acquire a right to a substantial sum without
justification.
4.13. Leighton did not have a genuine claim to any sum
from the Club on 28 July, or before 6 August (upon certification) as it well
knew. Even then, its claim was limited to a small sum which was soon paid.
Leighton cannot assert that, in terms of the statutory
provisions properly
construed, it has any genuine or bona fide claim that would bring it
within s.13(1) of the Act.”
79 This submission is rejected. The
intention of the legislature is clear from the terms of section 13 (1). A
person who has undertaken
to carry out construction work or who has undertaken
to supply related goods and services under the construction contract, who
is or who claims to be entitled
to a progress payment under the contract, may serve a payment
claim on the person who is or may be liable to make a payment under the
contract.
Dual or Inter-related Systems [General
matters]
The Club’s submission
“5.1 In its
Outline of Submissions, Leighton places heavy reliance upon authorities cited
[at para 3.8] for its contention that
the regime for certification and payment
under the Contract has no relevance, in particular having regard to the
so-called “dual
system” of statutory and contractual liability
contemplated by the Act [paragraph 3.9].
5.2 Significantly, Leighton does
not refer to the recent decision of the Court of Appeal in De Martin and
Gasparini Pty Limited v Energy Australia [2002] NSWCA 330; (2002) 55 NSWLR 577. Santow JA,
with whom the other members of the Court agreed, said [at 590]:
The
term “progress payments” is not fully articulated in the Building
and Construction Act. Austin J recently considered
that term in Jemzone Pty Ltd
v Trytan Pty Ltd (2002) 42 ACSR 42. He considered that the definition of
progress payment under the Building and Construction Act was
“unhelpful”. Austin
J held in that case that the meaning of the term
was rather to be derived from the specific contract in question. The Building
and
Construction Act was seen as making “default provisions to fill in
contractual gaps He concluded at (49[37]) that:“...If
the act was intended
to apply in the case of final payment on practical completion, it would have
been a simple matter for the drafter
...to refer to the entitlement to receive
all payments due...rather than only “specified progress
payments”.
I agree with that conclusion.
Santow
JA expressly agreed with the conclusion of Austin J at [57].
5.3 The
views so expressed are consistent with the analysis of the statutory provisions
undertaken above and with the operation and
effect of the Act indicated above.
With respect to further authorities cited by Leighton in its Outline of
Submissions, the following
observations are made.
5.4 Leighton relies on
Walter Construction Group Ltd v CPL (Surry Hills) Pty Limited [2003] NSWSC 266 in which Nicholas J decided that decided that a “progress
payment” referred to the amount claimed by the contractor under
the Act,
rather than under the contract. Nicholas J at [52] followed the decision of
Macready AJ in Beckhaus v Brewarrina Council [2002] NSWSC 960 at
[60]- [65] that the Act creates a “dual system” in relation to
progress payments, which creates rights, irrespective of the contractual
provisions. However, this line of authority is inconsistent with the decision of
Austin J in Jemzone, which was approved by the Court of Appeal in De
Martin.
5.5 In Beckhaus there was no appeal from the decision
of Macready AJ on this issue [Brewarrina Shire Council v Beckhaus Civil Pty
Ltd [2003] NSWCA 4] (as Nicholas J noted in Walter at [52]). However,
this may be explained on the basis that resolution of the question could not
have affected the outcome of the appeal.
On the facts of that case, the
Superintendent’s certificate was issued after the expiry of the
relevant time period, with the consequence that the amount stated in the
progress claim became the amount payable
by way of a progress payment under the
contract In the instant case, the certificate by Carver was served within the
required period [Beckhaus Civil Pty Ltd v Brewarrina Shire
Council [2002] NSWSC 960 at [2], [17] and [19]].
5.6 The
second matter on which Nicholas J relied in Walter at [53] concerned the
observations of Heydon JA in Fyntray Constructions Pty Ltd v Macind Drainage
& Hydraulic Services Pty Limited [2002] NSWCA 238 at [51]. In fact,
Fyntray is distinguishable on its facts from Walter and the
present case. In Fyntray, the progress payment was immediately payable
upon lodgement of the progress claim under clause 42.1, subject to a right in
the payee
to make deductions for which it was obliged to give reasons
[Fyntray at [6]]. There was no requirement for certification by a
Superintendent, as a precondition to the payee’s liability, as in the
present case and in Walter [See at [12]].
5.7 Accordingly, the
Court ought apply De Martin and Jemzone, with the consequence that
the progress payment referred to in the relevant section is that which falls
duly under the Contract albeit
the Act provides an expeditious means of recovery
of amounts so due. In the present case there was no amount due under the
Contract
as at 28 July, being the date of the alleged payment claim. This result
also gives effect to the object of the Act as specified in
s.3 and the
Minister’s second reading speeches. [See also Second Reading Speakers for
the Act on 8.9.99, Hansard, page 107
(Legislative Assembly) and the Amendment
Act on 12.11.02, Hansard page 6541 (Legislative Assembly)]”
80 It
seems to me that there is substance in Leighton's submission that absent an
appropriate definition, Austin J in Jemzone, paragraphs 35-39, is
seen to have only decided that the expression “progress
payment” should be given the meaning it has under the construction
contract. On that basis, his Honour held that this expression did not
include a
final payment. Santow JA expressed his agreement with this view in De Martin
& Gasparini Pty Ltd v Energy Australia [2002] NSWCA 330.
81 The
definition of “progress payment” has, it should be noted,
been amended expressly to include, inter alia, a final
payment.
Alleged Payment Claim Invalid – Rock Excavation
[section 13(4)(b)]
The Club’s
submission
“6.1 A payment claim may only be served within the
time limit set by s.13(4), relevantly for present purposes the period of
twelve
months “after the construction work to which the claim relates was last
carried out”; s.13(4)(b).
6.2 In the present case, the Alleged
Payment Claim includes an amount of $736,487 for rock excavation carried out
more than twelve
months before 28 July 2003 (date of the Alleged Payment Claim
[Affidavit of M Thebridge 13 November 2003 paragraph 25]). Other items
totalling $274,798 were similarly carried out twelve months before 28 July [M
Thebridge Affidavit paragraph 57].
6.3 Having regard to the substantial
nature of this statute-barred component (and the impermissible Delay Costs Claim
referred to
below), the Alleged Payment Claim falls. Two decisions of the Court
to contrary effect [Walter Construction Group Ltd v CPL (Surry Hills) Pty
Ltd [2003] NSWSC 266 at [64]- [69] per Nichols J; Paynter Dixon
Construction Pty Ltd v JF & CG Tiltson Pty Ltd [2003] NSWSC 869 at [34]
per Bergin J] are explained by the comparatively lesser substance of the invalid
portions of the payment claims there considered.
Where the amount claimed is
substantially denied efficacy by the Act, the whole payment claim is infected by
such invalidity. This
must necessarily be so where the factor which results in
exclusion from the reach of the Act is not merely a characterisation of
the item
claim (eg was item X construction work or something else? Were goods in fact
supplied?), but rather the absolute time for
bringing of a claim. This is
consistent with the requirements of the Act for expedition.. However the Club
respectfully submits
that these decisions are in
error.
6.4 Alternatively, if the Alleged Payment Claim is not invalid in
its entirety, it is certainly so to the extent of the rock excavation
and other
time barred claims. Moreover, in the exercise of it’s discretion, the
Court ought not give judgment, whether a summary
or otherwise, in respect of a
payment claim, the substantial portion of which offends the Act’s
requirements. S.15(4) does
not, in terms, eliminate all judicial discretion in
awarding judgment under the Act. The present case is an appropriate case for
the refusal of judgment.”
82 There is no issue but that some of the
rock excavation work the subject of the payment claim was carried out earlier
than twelve
months prior to 28 July 2003.
83 It is appropriate as a
general matter to note the holdings (at [67] and [68]) by Nicholas J in
Walter Construction:
· that to demonstrate compliance with
section 13 (2) (a) it is irrelevant that an item which is a component of
a payment claim may be disputed, albeit on the ground that such item cannot be
categorised as
either work or goods and services within the meaning of section 5
or section 6 respectively; and
· that in a challenge which raises
the question of compliance with section 13 (2) (a), the question is not
whether an item of the payment claim relates to construction work or related
goods and services within section 5 and section 6 respectively,
but
whether the payment claim adequately identified such work will goods and
services [68].
84 As is accepted by the Club that line of reasoning was
expressly followed by Bergin J in Paynter. In my view that line of
reasoning was correct. The matter is clearly relevant to the proper approach to
be taken to the similar
but by no means identical question albeit now raised in
the context of the prohibition to be found in section 13 (4) (b).
85 No
previous decision appears to have dealt with the requirements of section 13 (4)
(b).
86 It seems necessary to stand back from the issue and to seek to
place it into context.
87 Construction work involves as the norm, work
which may be expected to be carried out over a period of time. The laying of
foundations
is an example. This is unlikely to take one hour and may take days
or weeks or even longer.
88 Presumably the same may be said in relation
to the provision of related goods and services.
89 The legislature
appears to have had to cope with these realities in determining how to describe
the period of time within which
a payment claim could be served.
90 By
definition or real world practice it would be likely that a payment claim would
cover disparate forms of construction work carried
out over the same or
different periods/brackets of time and would similarly likely cover the
provision of related goods and services
over the same or different
periods/brackets of time.
91 It would seem unlikely that the legislature
would have intended that a payment claim in respect of any particular item of
construction
work [as for example the laying of a particular brick] could only
be served within the period of 12 months after completion of the
work comprising
that particular item.
92 Possibly the same may also be said in relation
to it being unlikely that the legislature would have intended that a payment
claim
in respect of a particular unit of construction work [as for
example the laying of a brick course or concourse] could only be served within
the period of 12 months
after completion of the work comprising that unit of
construction work. On the other hand perhaps it is arguable that the
legislature
may have so intended.
93 The legislature in fact enacted
section 13 (4) in the following terms:
“A payment claim may be
served only within....
(b) the period of 12 months after the
construction work to which the claim relates was last carried out (or the
related good and services to which the claim relates were last
supplied)...”
94 To my mind properly construed the subsection in
its reference to "the construction work to which the claim relates"
should be regarded as referring in a general way to the construction work or to
the related goods and services. Hence as long as
any item of construction work
to which the claim relates [in that general sense], was carried on during
the 12 month period prior to the service of a payment claim, that payment claim
could
also, unexceptionally, include items of construction work carried on prior
to that 12 month period.
95 The same proposition would hold good in terms
of the supply of related goods and services.
96 This construction is in
effect that contended for by Leighton which submitted
that:
· necessarily the phrase "the construction work to which
the claim relates" is the entirety of the works the subject of the
claim;
· it is then necessary to determine when that work "was
last carried out; and
· if any work has been carried out within
12 months of the date of the payment claim, the payment claim would have been
served
within the required period.
97 The Club submitted that this
construction would necessarily involve a rewriting of the subsection by shifting
the word "last" so
that the subsection would in effect read as
follows:
“A payment claim may be served only within....
the
period of 12 months after the last construction work to which the claim
relates was carried out (or the related good and services to which the claim
relates were last
supplied)"
98 Whether this submission of the Club be
correct or incorrect, to my mind the construction to which I have referred is
the correct
construction. It is consistent with the Minister’s second
reading speech for the Amendment Act:
“There will also be a limit
upon how long after construction work is completed that a claimant can
continue to make payment claims under the Act. The period will be 12 months
after the last work was carried
out or the goods or services were last provided,
or a later date if provided for under the contract.” (emphasis
added).
99 Likewise this construction seems to be consistent with the
amendment to the definition in section 4 of “progress
payment” to include “final payment”. A final
payment typically involves a final accounting for the entire project, a
significant portion of which will have been carried
out in many cases more than
12 months before any claim for a final payment may be
made.
100 Any other construction would it seems to me, as a matter of the
practicable working of the section, pose real difficulties of
application. The
construction avoids a limitation period seen to run on a daily basis. Further it
would seem to avoid an otherwise
necessary vouching of the particular items or
units of work in terms of the precise dates when such work was carried out which
would
seem to raise particular difficulties.
101 Ultimately the matter
is one of impression aided it seems to me, with some legitimacy, by reference to
the Minister's second reading
speech for the Amendment Act.
102 It
follows that the challenge to the validity of the payment claim based upon
section 13 (4) (b) and other items raising the same
issue
fails.
Payment Claim Invalid – Delay Costs [section 13(2)(a);
section 5]
The Club’s
submission
“7.1 S.13(2)(a) limits the ambit of a payment claim
to identified “construction work” and s.5 provides a definition
of
“construction work”. In the present case, the summaries attached to
the Alleged Payment Claim include an amount of
$936,325 described as
“Delay Costs – to 28/07/03 (Contract rate for delay)”. This
claim does not constitute “construction
work” under s.5 of the Act.
Rather, the Delay Costs appear to be a claim for damages under clause 34 of the
Contract, which
is entirely different from “construction work”, as
defined in s.5.
7.2 Accordingly, for the reasons set out in relation to
the rock excavation claim, the Alleged Payment Claim was invalid, or at least,
the amount of the Delay Costs ought be excised from any consideration by the
Court of the Alleged Payment Claim.”
103 This matter may be dealt
with very shortly indeed. In my view the approach taken by Nicholas J in Walter
(at [67] and [68]) is
squarely in point and is correct. An item which is a
component of a payment claim may be disputed, albeit on the ground that such
item cannot be categorised as either work or goods and services within the
meaning of section 5 or section 6 respectively. That
approach was expressly
followed in Paynter (at [39]) where Bergin J said:
"It may well be that a
payment claim might include amounts for services or other matters that do not
fall within the definition of
construction work or related goods and services.
But that does not mean that a payment claim that also has within it claims for
construction work is invalid."
104 It follows that the payment claim was
not invalid insofar as the inclusion within it of the so-called delay
costs.
Leighton was served with a Payment Schedule [section
14(1)]
The Club’s submission
“8.1 S.14(1)
makes provision for a reply to a payment claim by the provision of a
“payment schedule”. If (contrary
to the foregoing submissions) it be
held that the Alleged Payment Claim constitutes a payment claim under s.13, then
the Club served
a payment schedule in the form of Carver’s letter of 6
August 2003. Should the Court hold that the Alleged Payment Claim is
valid,
though it takes the form of a claim upon the Superintendent for certification,
it follows that Carver’s letter and its
enclosures should equally be
regarded as satisfying the requirements of s.14 as a payment schedule from the
Club.
8.2 In summary, on the basis that the Certificate constituted the
service of a payment schedule upon Leighton, Leighton had no entitlement
to
bring these proceedings or seek summary judgment against the Club, and the
proceedings and application for summary judgment ought
be
dismissed.”
105 Leighton’s short answer to this submission of
the Club is that it is clear from the evidence (paragraphs 14-16 of the
affidavit
of Stephen John Muter sworn on 7 November 2003 and paragraphs 10-12 of
the Thebridge Affidavit) that the Superintendent was not even
aware of the
Payment Claim. Accordingly, there is no basis on which it can properly be
suggested that the Superintendent’s
certificate was a payment schedule for
the purposes of section 14.
106 This short answer provides some useful
adjectival information. The question of whether or not the certificate was a
payment schedule
within the meaning of section 14 is however one of analysis of
the document. That analysis permits a negative answer to the question.
In this
respect I adopt as correct the following Leighton
submissions:
“6.4 The Plaintiff says that the Certificate is
not a payment schedule complying with sections 14(1) and (2) of the Act in
that:
(a) it does not reply to the Payment Claim, but instead, clearly on
its face, to the Contract Progress Claim. The Defendant’s
facsimiles of
14 and 19 August 2003 (paragraphs 15 and 18 and Exhibits “MEB7” and
“MEB9” to the First Bouton
Affidavit”) use the phrase
“evidencing the Superintendent’s opinion” which makes
it clear that the Defendant is of the view that the Superintendent, when issuing
the Certificate, was acting in accordance
with the requirements of clause 37.2
of the Contract to respond to a progress claim made under the
Contract;
(b) it does not identify the Payment Claim, being the payment
claim to which it relates; and
(c) it does not indicate the amount of the
payment that the Defendant proposes to make (“Scheduled
Amount”).
6.5 The Defendant submits that the Certificate
indicates the Scheduled Amount (Defence, paragraph C5). The Plaintiff says that
the
Certificate fails to comply with section 14(3) of the Act in that does not
indicate:
(a) why the Scheduled Amount is less than the claimed amount;
or
(b) the Defendant’s reasons for withholding
payment.”
107 The more extensive answer to this submission of
the Club is that provided for in Leighton’s overview submissions which are
adopted as correct in this regard and were as follows:
“Was the
Certificate served by the Defendant, or an agent of the
Defendant?
6.2 The Plaintiff says that the Certificate is not a
payment schedule complying with section 14(1) of the Act in that it was not
served
by the Defendant, being the person on whom the Payment Claim was served,
and being the person who is or may be liable to make the
payment.
6.3 The
Defendant submits that it provided the Certificate by the Superintendent, its
architect (Defence, paragraph C5). The Plaintiff
says that:
(a) this is
inconsistent with the Defence in which the Defendant has accepted that the
Certificate was issued by the Superintendent
under the Contract, rather than the
Act. This necessarily follows from paragraphs C10 and C11 of the Defence and
paragraphs 15 and
18 and Exhibits “MEB7” and “MEB9” to
the First Bouton Affidavit;
(b) in Karimbla, paragraph 11,
Justice Barrett found that a payment schedule could be provided by an agent of
the principal. However, in issuing
progress certificates pursuant to clause
37.2 of the Contract the Superintendent was acting as an independent certifier
and not as
an agent of the Defendant. This clear from:
(i) His Honour
Hodgson JA (with whom Mason P and Stein JA agreed) who said in Abigroup
Contractors Pty Ltd v Peninsula Balmain Pty Ltd (“Abigroup”)
[2002] NSWCA 211, paragraph 50:
“The authorities ... are
not altogether clear as to whether a person in the position of a superintendent
of a building contract
is the owner’s agent in exercising all the
functions of the superintendent. However, in my opinion the better view
(supported
by Perini, Dixon, Egan and London Borough of Merton and not refuted
by Sutcliffe) is that the superintendent is the owner’s
agent in all
matters only in a very loose sense, and that, when exercising certifying
functions in respect of which the superintendent must act honestly and
impartially, the superintendent is not acting as the owner’s agent, in
the strict legal sense. In my opinion, this is confirmed by the
consideration that the issue of a certificate by the superintendent does not
bind the owner
to any extent beyond what is prescribed in the building contract
itself, so that the owner can challenge such certificates. If the
superintendent was acting as the owner’s agent in the strict sense, the
issue of the certificate would be an act done by the
owner through its agent,
which the owner could not then challenge.” (emphasis
added).
The authorities referred to by His Honour Hodgson JA
were:
Perini Corporation v Commonwealth of Australia [1969] 2 NSWLR
530;
Dixon v South Australian Railways Commissioner [1923] HCA 45; (1923) 34 CLR
71;
South Australian Railways Commissioner v Egan [1973] HCA 5; (1973) 130 CLR
506;
London Borough of Merton v Stanley Hugh Leach Ltd (1985) 32 BLR
51; and
Sutcliffe v Thackrah [1974] AC 727.
The contract in
question in Abigroup was AS2124-1992 which is the immediate predecessor
to AS4000-1997 which forms part of the Contract. The Superintendent’s
role
under both contracts is identical for present purposes; and
(ii) Dorter and Sharkey who consider it “...almost unreasonable
and unrealistic to expect a person in such a situation to wear
two hats
simultaneously and be a professional contortionist” at paragraph 7.520;
and
(c) the Defendant has made it clear in correspondence to the
Plaintiff that the Superintendent was acting independently when issuing
the
Certificate. The Defendant’s facsimiles of 14 and 19 August 2003
(paragraphs 15 and 18 and Exhibits “MEB7”
and “MEB9” to
the First Bouton Affidavit”) both provide relevantly
“...evidencing the Superintendent’s opinion...”
and “...the payment that the Superintendent proposes to make
and the Superintendent’s reasons for withholding payment.”
(emphasis added)”
Dealing with the second set of
proceedings
108 In my view the second set of proceedings require to
be summarily dismissed. The reasons are as follows:
· Clearly
enough the proceedings are brought only to frustrate the application for summary
judgment in the first proceedings.
· Contract condition 37.2 makes
plain that neither a progress certificate payment schedule nor a payment of
moneys is to be evidence
that the subject work under the contract has been
carried out satisfactorily and further makes plain that payment other than final
payment is to be payment on account only. Hence the declaration sought in
paragraph 1 of the summons would not be declaratory of
the parties rights inter
se in any final sense.
· The proceedings amount to an abuse of
process, being a backdoor route to in substance, outflank section 15 of the Act.
· The overriding purpose rule [Part 1, Rule 3 (1), (2)] may be
mobilised where as here the forensic tactic in commencing the
second proceedings
is antithetic to the facilitation of the just, quick and cheap resolution of the
real issues in the proceedings.
In the present context the reference to "real
issues in the proceedings" translates into the issues which will be
determinative
of the parties final rights against one another.
· Section 63 of the Supreme Court Act expresses a fundamental
principle of the Act which is the avoidance of multiplicity of proceedings. The
second set of proceedings
flies in the face of that principle.
109 These
reasons are sufficient to justify the summary dismissal of the second
proceedings. There are disparate other reasons to
the same end. Declarations
of right are final and not interlocutory orders having the effect of creating a
res judicata or an issue
estoppel: Marra Developments Ltd v B W Rofe Pty
Ltd [1977] 2 NSWLR 616 per Hutley JA at 626. The subject declaration sought
in the second proceedings fails to comply with this criterion.
110 Further as a general rule the power to make a declaration will not
be exercised when the Court is called upon to answer a question
that is purely
hypothetical. In its submission in relation to this principle, the Club
contended that "[t]here would appear to be
a genuine dispute between Leighton
and the Club as to the amount which was owing under the contract at the time
progress claim No.
18 was served". The purpose of the Act is to permit a
contractor to sidestep curial proceedings concerning resolution of that form
of genuine dispute by utilising the payment claim and other provisions of
the Act with the expressed aim that in so doing, the contractor may have the
benefit of the peremptory interim determination of such issue. That purpose
would be turned on its head if proceedings in the nature
of the second
proceedings were permitted to go forward.
111 During the hearing,
reference was made to the entitlement of the Club to commence substantive
proceedings for relief concerning
the parties rights under the contract, which
relief would be final in character and would upon final determination have the
effect
of creating a res judicata or an issue estoppel. The entitlement of
parties to commence proceedings of this type at an appropriate
time is
recognised in section 32 of the Act.
The discretionary power to order
summary judgment
112 The Club put forward a number of submissions in
support of the proposition that it was inappropriate for the Court to exercise
its discretion to grant summary judgment in the first proceedings. None of these
submissions were of substance. They generally contended
that even if the Club
failed to resist the force of the Leighton claim in the first proceedings, the
Club had demonstrated a bona
fide arguable case that it had powerful defences as
to substantial portions, if not the whole of the claims made against it in the
first proceedings, so that although Leighton may be shown to have satisfied the
requirements of the Act, this was a case where the
exercise of the discretion to
grant summary judgment should be withheld. The submissions fly in the face of
the clear intent of the
Act and are calculated to undermine section 15 [and in
particular section 15 (4)], and section 16 [and in particular section 16 (4)].
The terms of subsections (4) (a) of each of sections 15 and 16 make plain that
judgment in favour of the relevant claim is not to
be given in curial
proceedings unless the Court is satisfied of the existence of the circumstances
referred to in subsections 1.
The Court here being satisfied of the existence
of those circumstances, there is no occasion presently shown for an otherwise
exercise
of the Court's undoubted discretion to give or to withhold summary
judgment in any proceedings, for the Court presently to withhold
the grant of
that relief. The discretion requires to be exercised in a principled way. The
legislative scheme constituted by the
Act makes quite plain that the proper
exercise of the discretion presently is to grant summary judgment in favour of
Leighton as
sought in the first proceedings.
Short Minutes of
Order
113 The parties are to bring in short minutes of order. Costs
may then be argued.
Rulings on procedure and
evidence
114 During the hearing some questions as to procedure were
raised. The Court approached the hearing upon the basis that the convenient
course was to determine the issues raised by the application for summary
judgment in the first proceedings at the same time as hearing
the Club's motion
in the second proceedings.
115 During the hearing certain rulings on
evidentiary matters were reserved for decision in the judgment. The rulings are
as follows:
MFI P 1 The Review Discussion Paper entitled “Options
for enhancing the [Act]”
This document is sought to be tendered
pursuant to section 34 (2) (e) of the Interpretation Act, the assertion
being that it is the document referred to in the second paragraph of the second
reading speech concerning the amendment
Bill. It may be technically admissible
on this basis but the discussion paper is not of assistance in relation to the
issues presently
before the Court and in my view should be rejected under
section 135 of the Evidence Act 1995 on the basis that the probative
value of the document is outweighed by the danger that the admission into
evidence of the document
would amount to a waste of time.
MFI P 2 The
“Report on a Review of the [Act]” said to be the document referred
to in Hansard at page 7539, is allowed
but is of no particular assistance on the
matters litigated.
MFI P 3 This is simply the Hansard extract page 7539
which is unexceptional and is only admitted to identify the subject page so that
the ruling in relation to MFI P 2 may be given.
I certify that
paragraphs 1 -115
are a true copy of the reasons
for
judgment herein of
the Hon. Justice Einstein
given on 3
December 2003
___________________
Susan
Piggott
Associate
3 December 2003
LAST UPDATED: 08/12/2003
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2003/1103.html