![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales |
Last Updated: 5 December 2003
NEW SOUTH WALES SUPREME COURT
CITATION: Multiplex
Constructions Pty
Ltd v
Luikens
and Anor [2003] NSWSC 1140
CURRENT JURISDICTION:
Equity Division
Technology & Construction List
FILE NUMBER(S):
55036/03
HEARING DATE{S): 18 September, 2003
JUDGMENT DATE:
04/12/2003
PARTIES: Multiplex
Constructions Pty Limited -
Plaintiff
Jan Luikens
- First Defendant
Lahey Detailed Joinery Pty Ltd -
Second Defendant
JUDGMENT OF: Palmer J
LOWER COURT
JURISDICTION: Not Applicable
LOWER COURT FILE NUMBER(S): Not
Applicable
LOWER COURT JUDICIAL OFFICER: Not Applicable
COUNSEL:
M.G. Rudge SC and D.A.C. Robertson - Plaintiff
F.C. Corsaro SC and J.J.
Young - Second Defendant
SOLICITORS:
Minter Ellison -
Plaintiff
Sparke Helmore - First Defendant
Colin Biggers & Paisley -
Second Defendant
CATCHWORDS:
ADMINISTRATIVE LAW - Whether the
determination of an adjudicator under the Building and Construction Industry
Security of Payment Act 1999 is open to judicial review - whether an
adjudication may be reviewed for error of law on the face of the record - the
extent of an
adjudicator's jurisdiction - what must be disclosed by a payment
schedule under the Act - whether there were errors of law going
to jurisdiction
- whether whole Determination must be quashed - discretionary considerations as
to granting of relief - consequences
where Determination quashed.
ACTS
CITED:
- Building and Construction Industry Security of Payment Act 1999
(NSW) - s.2, s.3, s.8, s.9, s.10, s.11, s.13, s.14, s.15, s.16 s.17, s.18, s.19,
s.20, s.21, s.22, s.23, s.24, s.25, s.26, s.27, s.32, s.34
- Corporations Act
2001 (Cth) - s.459E
- Migration Act 1958 (Cth)
- Supreme Court Act 1970
(NSW) - s.69
DECISION:
Jurisdictional error of law shown;
adjudicator's Determination quashed.
JUDGMENT:
Introduction
1 By Summons filed in the
Administrative Law List of the Common Law Division on 8 August 2003, the
Plaintiff (“ Multiplex
”)
seeks:
i) an order in the nature of
certiorari to quash, on the ground of error on the face of the record, a
Determination dated 24 July
2003 made by the First Defendant (“Mr
Luikens
”) in favour of the Second Defendant (“Lahey”) against
Multiplex
pursuant to the Building and Construction Industry Security of
Payment Act 1999 (NSW) (“the Act”);
ii) an order in the
nature of certiorari to quash the Determination on the ground that Mr Luikens
had no jurisdiction to make certain
decisions which underlie the
Determination;
iii) an order that Lahey be restrained from taking any
step to enforce the Determination.
2 On 13 August 2003,
the Court gave certain directions and accepted an undertaking from Lahey that it
would not file the Determination
as a judgment in accordance with s.25(2) of the
Act without first giving Multiplex
’s solicitors two clear business
days’ notice.
3 On 2 September the Summons was
transferred to the Technology and Construction List of the Equity Division. On
5 September, Multiplex
filed in Court a Notice of Motion seeking an
interlocutory injunction in terms of the injunction sought in its Summons. On
that
day, Bergin J accepted an undertaking from Lahey that it would not seek to
file the Determination under s.25(2) until one business day after the
determination of
Multiplex
’s Notice of Motion for an interlocutory
injunction.
4 On 11 September, Bergin J set the matter
down for hearing and accepted a varied undertaking from Lahey, namely, that it
would
not seek to file the Determination until one business day “after
judgment in these proceedings”. What was meant was “final
judgment” so that the undertaking dispensed with a hearing of
Multiplex
’s Notice of Motion
for an interlocutory injunction. Thus, the
hearing before me has been conducted as a final hearing.
The facts
5 The dispute arises out of the
construction by Multiplex
of a large project at Pyrmont.
Multiplex
entered into
a subcontract
with Lahey whereby Lahey was to carry out work including heritage
window refurbishment and joinery.
6 From time to time
Lahey submitted progress claims to Multiplex
in accordance with the subcontract.
On 24 May 2003, Lahey served
on
Multiplex
a Payment Claim under s.13 of the Act
for the sum of $708,823.12.
7 On 4 June 2003, Multiplex
responded with a Payment Schedule under s.14 of the Act. On 19 June, Lahey
applied for adjudication of the Payment Claim under s.17(1) and Mr
Luikens
was
appointed to adjudicate the dispute.
8 Multiplex
served
its submissions on or about 26 June and Mr
Luikens
delivered the Determination
under s.22 of the Act on 1 August. He found that Lahey was entitled to payment
from
Multiplex
in the sum of $582,298.04, inclusive of
GST.
9 By s.23(2) of the Act, Multiplex
was thereupon
required to pay the adjudicated amount to Lahey by 8 August. On that date
Multiplex
commenced
these proceedings.
10 Mr Luikens
has filed a submitting appearance and does not wish to be heard except as to
costs, if necessary.
Whether certiorari lies
11 Multiplex
seeks an
order in the nature of certiorari under s.69(1) and (3) of the Supreme Court
Act 1970 (NSW). Section 69(1) provides in effect that where the Court
formerly had jurisdiction to grant relief by prerogative writ it now has
jurisdiction to
grant relief by judgment or order under the Supreme Court
Act. Section 69(3) provides:
“It is declared that the
jurisdiction of the Court to grant any relief or remedy in the nature of a writ
of certiorari includes
jurisdiction to quash the ultimate determination of a
court or tribunal in any proceedings if that determination has been made on
the
basis of an error of law that appears on the face of the record of the
proceedings.”
12 The first question which the
parties have debated is whether a determination of an adjudicator under s.22 of
the Act is amenable to relief in the nature of certiorari. At the time of
hearing this question had not yet been decided by a
superior court of this
State. Elaborate argument was, therefore, presented by Counsel for both sides.
After I had reserved my decision,
however, McDougall J delivered his reasons for
judgment in Musico v Davenport [2003] NSWSC 977, in which his Honour held
that the determination of an adjudicator made under s.22 of the Act was
susceptible to judicial review in the nature of certiorari. I respectfully
agree in his Honour’s conclusions.
However, in deference to the careful
submissions which were made to me and because some of those submissions were
not, it seems,
made to McDougall J in Musico, I have thought it
appropriate to deal with the question of principle a little more fully than
simply by following the decision in
Musico.
13 Mr F. Corsaro SC, who appears with Mr
J. Young for Lahey, submits that certiorari does not lie in respect of such a
determination
for a number of reasons. First, he says that the Court has power
to make an order in the nature of certiorari only if the order
is directed to an
inferior court or a tribunal exercising governmental powers: Craig v State
of South Australia [1995] HCA 58; (1995) 184 CLR 163, at 174. An adjudicator appointed
under s.19 of the Act is neither an inferior court nor a tribunal exercising
governmental powers, says Mr Corsaro.
14 I agree that
an adjudicator appointed under the Act is not an “inferior
court”. Whether he or she is a “tribunal” is
debatable but unnecessary to decide because it has long been held that the reach
of the prerogative writs extends beyond courts
or tribunals, strictly so called,
to include any person or body having legal authority to determine questions
affecting common law
or statutory rights or obligations of others, as long as
the person or body, in making such determination, is required expressly,
or by
implication from the nature of the duty being performed, to act judicially. In
this context, a duty to act judicially means
a duty to observe the basic rules
of natural justice, namely, to afford a person who might be adversely affected
by the decision
a reasonable opportunity of presenting an informed case in
opposition and, second, to arrive at the relevant decision uninfluenced
by bias
or self-interest: R v Electricity Commissioners; Ex parte London
Electricity Joint Committee Co (1920) Ltd [1924] 1 KB 171, at 205; Ridge
v Baldwin [1963] UKHL 2; [1964] AC 40, at 74-79; O’Reilly v Mackman [1983] UKHL 1; [1983] 2
AC 237, at 279; Craig at 175 fn 53; Musico at paragraphs
28ff.
15 It is clear that an adjudicator appointed
under s.19 of the Act has legal authority to make a determination for the
purposes of the Act. It is clear also that an adjudicator is required
to act
judicially in the sense explained above. A respondent must be given the
opportunity to present an informed case to the adjudicator
which the adjudicator
must consider: s.17(5) requires that the adjudication application be served on
the respondent; provision is made for the respondent to serve on the claimant
and lodge with the adjudicator an adjudication response containing its
submissions (s.20(1), (2) and (3)); the adjudicator must
give consideration to
an adjudication response if it is lodged within the prescribed time (s.21(1));
if one party is given the opportunity
to make further submissions, the other
must be afforded a right of reply (s.21(4)(a)). Further, the adjudicator must
be impartial
at least to the extent that he or she is not directly interested in
the construction contract as a party: s.18(2).
Whether an adjudication affects common law or statutory
rights
16 Mr Corsaro says, however, that an
adjudicator’s determination under s.22 does not affect anyone’s
common law or statutory rights or obligations. This is so, he says, because the
rights and obligations
of parties to a building contract are as provided in that
contract or by the general law and nothing in the Act operates to change
either
the terms of the contract or the general law relating to the contract and the
rights of the parties. He relies upon s.32 of the Act, which provides:
“Effect of Part on civil
proceedings
(1) Subject to section 34, nothing in this Part
affects any right that a party to a construction
contract:
(a) may have under the contract,
or
(b) may have under Part 2 in respect of the contract, or
(c) may have apart from this Act in respect of anything done or
omitted to be done under the contract.
(2) Nothing done under or
for the purposes of this Part affects any civil proceedings arising under a
construction contract, whether
under this Part or otherwise, except as provided
by subsection (3).
(3) In any proceedings before a court or
tribunal in relation to any matter arising under a construction contract, the
court or tribunal:
(a) must allow for any amount paid to a party
to the contract under or for the purposes of this Part in any order or award it
makes
in those proceedings, and
(b) may make such orders as it
considers appropriate for the restitution of any amount so paid, and such other
orders as it considers
appropriate, having regard to its decision in those
proceedings.”
17 I am unable to accept this
submission. A determination in favour of a claimant can produce serious,
substantial and coercive
legal consequences for a respondent: rights may be
given to the claimant which the claimant did not previously have and rights
which
the respondent previously had may be taken away. For example, s.23(1)
provides that if an adjudicator determines that a respondent to a payment claim
under the Act is required to pay an adjudicated amount,
then the respondent must
pay that amount to the claimant on or before the expiration of five business
days after the date of service
of the determination on the respondent. A
statutory right to payment within a prescribed time is thereby created,
regardless of
what the contract may, on its true construction, provide and a
corresponding statutory obligation to pay is, likewise,
created.
18 If the respondent fails to make payment
within the time required by s.23(1) the claimant may obtain an
“adjudication certificate” from the adjudicator stating the names of
the claimant and the
respondent, the adjudicated amount and the date upon which
the amount was due for payment: s.24(1)(a), (3). The claimant may then file
the adjudication certificate “as a judgment for a debt in any court of
competent jurisdiction” and may enforce that judgment accordingly:
s.25(1). By s.25(4) that judgment is made immune from challenge in certain
circumstances. The subsection provides:
“(4) If the respondent
commences proceedings to have the judgment set aside, the respondent:
(a) is not, in those proceedings, entitled:
(i) to bring any cross-claim against the claimant, or
(ii) to raise any defence in relation to matters arising under
the construction contract, or
(iii) to challenge the
adjudicator’s determination, and
(b) is required to pay
into the court as security the unpaid portion of the adjudicated amount pending
the final determination of
those
proceedings.”
19 A decision of an adjudicator
under the Act may be transformed, simply by the process of filing, into a
judgment of a court of
law, binding on the parties and yet, seemingly,
unimpeachable for error. I cannot see how it can be said that such a decision
does
not affect rights and obligations of the parties under a construction
contract or the rights which the parties would have had under
the common law if
they were to litigate their contractual dispute in the normal
way.
20 For example, the object of an
adjudicator’s determination under the Act is to give effect to the
parties’ rights
and obligations under the construction contract but,
supposedly, only on an interim basis: s.32(2). Nevertheless, the
determination, once filed as a judgment, is capable of producing all of the
consequences of a final judgment,
for good or ill. A respondent may be served
with a statutory demand under s.459E Corporations Act 2001 (Cth) founded
on the judgment, yet the respondent will have been deprived by s.25(4)(a)(i) of
the Act of its right under the common
law to extinguish or reduce the claimed
judgment debt by establishing any cross claim which it might have and it will
have been deprived
by s.25(4)(a)(iii) of its right to appeal from the judgment
entered pursuant to s.25(1) on the ground of error of law in the
adjudicator’s
determination, which constitutes the reasons for the
judgment. The respondent may be wound up if it does not comply with the
statutory
demand although it might have been able to demonstrate in litigation
conducted in the normal way that, in fact, it was not indebted
to the claimant
under the construction contract at all.
21 Again, a
respondent may choose to pay a statutory demand founded on an
adjudicator’s judgment and may successfully contest
liability for the
payment in subsequent litigation only to find that the claimant has since become
insolvent and that the money paid
under the “interim judgment” is
now irrecoverable.
22 Another consequence of a
respondent’s failure to pay in accordance with an adjudicator’s
determination is that the
claimant may serve on the respondent a notice
specifying an intention to suspend construction work under the construction
contract:
s.24(1)(b). If the respondent fails to pay the adjudicated amount
after two business days the claimant may suspend construction
work and will then
be immune from liability for any loss or damage which may be caused thereby:
s.27(1), (3). Clearly, the immunity
applies regardless of the provisions of the
contract (s.34(1)), even if it be found in later proceedings that the claimant
was not
entitled to the payment.
23 It is not necessary
to found the Court’s jurisdiction to grant relief in the nature of a
prerogative writ that the impugned
decision itself directly creates or affects
rights or obligations. As Malcolm CJ put it in Re Real Estate and Business
Agents Supervisory Board; Ex parte Cohen [1999] WASCA 47; (1999) 21 WAR 158, at
189:
“Unless the remedy is effectively excluded by statute, any
statutory authority on which Parliament has conferred statutory powers
and
duties, which when exercised may lead to the detriment of a person who may
have to submit to its jurisdiction, is subject to supervision by the courts
by way of the prerogative writs and certiorari, in particular: R v National
Joint Council for Dental Technicians; Ex parte Nate [1953] 1 QB 704 at 707
per Lord Goddard CJ.” [Emphasis added.]
24 A
consideration of the consequences which may flow directly from a determination
by an adjudicator under the Act shows clearly,
in my opinion, that the decision
may affect the rights and obligations of parties to a construction contract or,
to put it more broadly,
may lead to the detriment of a respondent to a payment
claim under the Act. It follows that the determination of the adjudicator
is
subject to the supervision of the courts in the nature of certiorari unless, as
Mr Corsaro next submits, the remedy is effectively
excluded by the Act.
Whether certiorari excluded by the Act
25 Mr
Corsaro says that the Act in general, and s.25(1) in particular, demonstrates an
intention on the part of the legislature
that an adjudicator’s decision is
not to be challenged in any way until the rights of the parties are finally
determined by
other established mechanisms such as by litigation in the ordinary
way, arbitration or negotiation and agreement. Mr Corsaro points
to:
– section 3(1) and (2), which state the objects of the Act as
being to “ensure” that persons undertaking construction work
are entitled to receive and able to recover progress payments for that
work;
– section 8(1), which provides an unqualified entitlement on
the part of a claimant to receive progress payments;
– the remedies
provided to a claimant to suspend construction work under s.15(2)(b), s.16(2)(b)
and s.27 and to exercise a lien under s.11(3), which remedies, says Mr Corsaro,
“the legislature would not have been likely to contemplate if it was
envisaged that the adjudicator’s decision were reviewable”;
– section 25(1) which provides for direct enforcement of an
adjudicator’s decision as a judgment;
– section 24(4), set
out above, which, Mr Corsaro says, evidences a clear legislative intent that the
adjudicator’s determination
is not to be open to judicial
review.
26 Further, Mr Corsaro relies heavily on the
Second Reading Speech introducing the amendments to the Act which were effected
in
2002. He places particular emphasis on the following
passage:
“Under the new procedure there will no longer be need for a
summons and a hearing before a magistrate or judge. Claimants will
be able to
obtain judgment for the adjudicated amount without the need to engage a
solicitor. A claimant will be able to obtain judgment
on the day that the
claimant files the adjudication certificate with the court. These measures not
only will expedite recovery of
progress payments but will considerably reduce
the cost of doing so. If a respondent applies to the court to have the judgment
set
aside after an adjudication, the respondent will have to pay into court as
security the unpaid portion of the adjudicated amount.
This will defeat the
practice of using legal proceedings to simply delay payment.
There will be some instances where a court may set aside the
judgment. The respondent may be able to demonstrate to the court that
the
requirements of the Act have not been complied with; for example, that there has
not been a valid adjudication. But in proceedings
to set aside the judgment the
respondent will not be entitled to bring a cross-claim or to raise any defence
in relation to matters
arising under the construction contract or to challenge
the determination by the adjudicator.”
27 Mr
Corsaro’s submission amounts to this: the intention of the legislature,
to be deduced from a consideration of the
Act as a whole, is to deprive the
citizen of a right firmly established by the common law for his or her
protection, namely, the
right to call upon the superior courts to supervise, by
granting relief in the nature of prerogative writ, decisions of bodies or
persons exercising a statutorily conferred power to affect the citizen’s
rights and interests.
28 I am unable to accept Mr
Corsaro’s submission. I must, of course, construe and apply the Act
itself, not the Second Reading
Speech. I approach construction of the Act
bearing in mind the admonition of Gleeson CJ in Plaintiff S157/2002 v
Commonwealth of Australia (2003) 77 ALJR 454, a case in which the Court
considered the extent and effectiveness of a privative clause in the
Commonwealth Migration Act 1958. The Chief Justice said at
462:
“... courts do not impute to the legislature an intention to
abrogate or curtail fundamental rights or freedoms unless such
an intention is
clearly manifested by unmistakable and unambiguous language. General words will
rarely be sufficient for that purpose.
What courts will look for is a clear
indication that the legislature has directed its attention to the rights or
freedoms in question,
and has consciously decided upon abrogation or
curtailment: Coco v R [1994] HCA 15; (1994) 179 CLR 427. As Lord Hoffmann recently
pointed out in the United Kingdom (R v Home Secretary; Ex parte Simms
[1999] UKHL 33; [2000] 2 AC 115), for parliament squarely to confront such an issue may involve
a political cost, but in the absence of express language or necessary
implication, even the most general words are taken to be “subject to the
basic rights of the individual”: Annetts v McCann [1990] HCA 57; (1990) 170 CLR
596.
...
... privative clauses are construed
‘by reference to a presumption that the legislature does not intend to
deprive the citizen
of access to the courts, other than to the extent expressly
stated or necessarily to be implied’: Public Service Association (SA)
v Federated Clerks’ Union [1991] HCA 33; (1991) 173 CLR 132.”
See
also Darling Casino Ltd v New South Wales Casino Control Authority [1997] HCA 11; (1997)
191 CLR 602, at 633.
29 I do not find anywhere in the
Act unmistakeable and unambiguous language depriving a party to a construction
contract of the
right to apply to the Court for review by way of certiorari of
an adjudicator’s determination.
30 On the
contrary, it appears clear enough that it was not the intention of Parliament to
prohibit, by s.25(4)(a), review by way of certiorari of a judgment entered by
the filing of an adjudication certificate under s.25(1). Such a judgment cannot
be “set aside” by appeal because challenge to the
adjudicator’s determination is proscribed
by s.25(4)(a)(iii). On what
ground, then, could such a judgment be “set aside” – as the
subsection expressly contemplates it may be
– if not upon grounds which
would found relief in the nature of certiorari, such as that the adjudication
giving rise to the
judgment had been conducted contrary to the provisions of the
Act and, therefore, without jurisdiction. This is the very example
referred to
in the Second Reading Speech as a basis for setting aside a judgment entered
pursuant to s.25(1):
“There will be some instances where a court may
set aside the judgment. The respondent may be able to demonstrate to the court
that the requirements of the Act have not been complied with; for example, that
there has not been a valid
adjudication.”
31 If Parliament did not
intend that a judgment entered pursuant to an adjudication determination should
be immune from review
by way of certiorari, it would be strange indeed to impute
to it an intention that the determination itself, which founds the judgment,
should nevertheless have the protection of that
immunity.
32 I conclude that there is nothing in the
Act which prohibits review by way of certiorari of an adjudicator’s
determination
under s.22. I am fortified in this conclusion by the decisions to
the same effect of Gzell J in Abacus Funds Management Ltd v Davenport
([2003] NSWSC 935), at paragraphs 21 and 22, of McDougall J in Musico at
paragraphs 34-39, and of Einstein J in Brodyn Pty Ltd v Davenport [2003] NSWSC 1019, at paragraph 19. I respectfully agree in the views which their
Honours there express.
Whether certiorari lies for error of
law
33 While, in general principle, relief in the
nature of certiorari in respect of a determination under s.22 is not precluded
by
the Act, further questions arise as to the grounds upon which such relief can
be given and the circumstances in which relief may
be granted or withheld in the
Court’s discretion.
34 It seems clear enough that
relief will be granted where the adjudicator’s determination is the result
of jurisdictional
error: see Musico at paragraphs 42ff. Jurisdictional
error will arise where, for example, the adjudicator’s
decision:
– was given in bad faith or was procured by
fraud;
– was one which the adjudicator had no power under the Act
to make;
– was made without complying with the limited requirements
of natural justice provided by s.17(5), s.20(1), (2) and (3), s.21(1),
s.21(4)(a) and s.18(4) of the Act; and see paragraph 15
above;
– did not deal with the question remitted for
adjudication;
– determined a question not remitted for
adjudication;
– did not take into account something which the Act
required to be taken into account; or
– was based upon something
which the Act prohibited from being taken into account.
See generally
Anisminic Ltd v Foreign Compensation Commission [1968] UKHL 6; [1969] 2 AC 147, at
171.
35 The fact that it is an error of law on the part
of the administrator which gives rise to any one of the above errors in no way
alters the character of that error as one going to jurisdiction: see
Craig at 179. The difficult question is whether relief in the nature of
certiorari is available if the adjudicator’s determination
is the result
of error of law which does not give rise to jurisdictional error. The question
arises because of the provisions of
s.69(3) and (5) of the Supreme Court
Act and their effect upon the construction of the
Act.
36 Section 69 provides, in so far as is
relevant:
“(3) It is declared that the jurisdiction of the Court to
grant any relief or remedy in the nature of a writ of certiorari includes
jurisdiction to quash the ultimate determination of a court or tribunal in any
proceedings if that determination has been made on
the basis of an error of law
that appears on the face of the record of the
proceedings.
...
(5) Subsections (3) and (4) do not
affect the operation of any legislative provision to the extent to which the
provision is, according
to common law principles and disregarding those
subsections, effective to prevent the Court from exercising its powers to quash
or
otherwise review a decision.”
37 It seems
to me that s.69(3) Supreme Court Act, in conjunction with subsection (1),
vests the Court with jurisdiction to grant relief in the nature of certiorari
for error of law
on the face of the record in relation to every decision which
would, according to the principles of the common law, be susceptible
to
certiorari and that, under subsection (5), that jurisdiction it taken away only
if, and to the extent that, “any legislative provision” takes
it away. Is there, then, “any legislative provision” in the
Act which takes away the jurisdiction, conferred by s.69(3) of the Supreme
Court Act, to quash an adjudicator’s determination for error of law
not giving rise to jurisdictional error?
38 In
Musico, McDougall J expressed the opinion that the legislative scheme set
out in s.25(4) of the Act was inconsistent with the availability of
non-jurisdictional error of law as a ground for quashing an adjudicator’s
determination. At paragraph 55 his Honour said:
“By s
25(4)(a)(iii), a respondent seeking to set aside a judgment based on an
adjudication certificate cannot challenge the adjudicator’s determination.
That must mean that in any such proceedings, the judgment cannot be set aside
upon the basis that the adjudicator (for example) erred
in law in some step of
his or her reasoning. It would be quite inconsistent with the legislative
intention that is evident in s 25(4) to permit a challenge to be raised, by way
of relief in the nature of prerogative relief, upon the ground of error of law.
The legislature
could hardly be taken to have intended that, having forbidden
entry by the front door, it was nonetheless happy for access to be
obtained from
the rear.”
39 His Honour’s reasoning
depends upon an implied, rather than an express, provision of the Act:
s.25(4)(a)(iii) concerns the setting aside of a judgment entered in accordance
with s.25(1), not the quashing of a determination made in accordance with s.22.
There is no other provision of the Act which (to borrow the words of s.69(5)
Supreme Court Act) expressly “prevents the Court from exercising
its power to quash or otherwise review” the adjudicator’s
determination on the ground of non-jurisdictional error of
law.
40 I bear in mind the extreme reluctance of the
Courts to impute to the legislature an intention to curtail fundamental rights
– especially a right to review such as is conferred by s.69(1) and (3)
Supreme Court Act -– in the absence of “clear and
unmistakable language”: see per Gleeson CJ in Plaintiff
S157/2002, quoted at paragraph 28 above. Nevertheless, the Courts recognise
that a legislative intention to abrogate such rights does not
always have to be
explicit: such an intention may be found in legislation “by necessary
implication”: see Annetts v McCann [1990] HCA 57; (1990) 170 CLR 596, at 599;
Public Service Association (SA) v Federated Clerks Union of Australia
[1991] HCA 33; (1991) 173 CLR 132, at 160 per Dawson and Gaudron JJ; Darling Casino at
633 per Gaudron and Gummow JJ.
41 In my opinion, it is
necessarily implicit in s.25(4)(a)(iii) of the Act that because a judgment
entered pursuant to s.25(1) is immune from review by way certiorari on the
ground of non-jurisdictional error of law, so also is the adjudicator’s
determination
which founds that judgment. I respectfully agree with McDougall J
that it would be absurd to suppose that the legislature intended
that an
adjudication determination could not be reviewed for error of law once a
judgment founded upon it had been entered but was
wide open for review and
quashing if a party were quick enough to commence proceedings prior to the entry
of the judgment. If such
a construction of the Act were embraced, very few
judgments would be entered under s.25(1) before the respondent had concluded a
full appeal against the determination under the guise of seeking a review in the
nature of
certiorari for error of law. Clearly, that is not what the
legislature intended by the scheme of the Act, as has been cogently demonstrated
by Einstein J in Brodyn at paragraph 14.
42 For
these reasons, I respectfully concur in the views expressed by McDougall J in
Musico and by Einstein J in Brodyn that an adjudicator’s
determination under s.22 of the Act may not be reviewed under s.69(1) and (3)
Supreme Court Act for non-jurisdictional error of law on the face of the
record.
What constitutes “the
record”
43 Mr Corsaro submits that
“the record” for the purpose of this application is confined
“only to those parts of the determination that contain findings
relevant to the value of the progress payments, rather than
any reasons
therefore”: Outline, paragraph 20. In support of this submission he
relies upon the following passage from the joint judgment in Craig at
181:
“... in the absence of some statutory provision to the
contrary, the record of an inferior court for the purposes of certiorari
does
not ordinarily include the transcript, the exhibits or the reasons for
decision.”
44 I am unable to accept Mr
Corsaro’s submission that “the record” does not include
the adjudicator’s reasons for his determination. The law, as stated in
the above passage from Craig, has been modified in New South Wales by
statute. In Kriticos v State of New South Wales (1996) 40 NSWLR 297,
Kirby P, at 299ff, criticised the “narrow view” of what
constituted “the record” which had been adopted by the High
Court in Craig, and his Honour called for legislative review. That call
did not go unheeded.
45 In 1996 s.69 of the Supreme
Court Act was amended by the insertion of new subsections (3), (4) and (5)
which made it clear that the Court had jurisdiction to quash a determination
on
the ground of error of law on the face of the record and that the face of the
record included the reasons expressed by a tribunal
for its ultimate
determination: see New Redhead Estate & Coal Co Ltd v New South Wales
Coal Compensation Board [1999] NSWCA 464, at paragraph 24. There was no
legislative amendment, however, to the general rule stated in the passage from
Craig cited above that “the record” does not
ordinarily include evidence upon which the impugned decision is said to be
founded.
46 In Musico, at paras 65-70, McDougall
J concluded that in proceedings to quash an adjudicator’s determination
for error of law on the face
of the record, the record would include the reasons
for the determination (by virtue of s.69(4) Supreme Court Act ) and, in
addition, the adjudication application and any adjudication response since, in
the absence of pleadings, those documents
served to define the issues for
determination. If additional written submissions of the parties provided
pursuant to s.24(4)(a) of the Act narrowed or clarified the issues, then such
submissions would also form part of the record. If the determination referred
to provisions of the contract and expressed views as their meaning and
application, then those provisions would, likewise, form part
of the
record.
47 In the present case, as will doubtless occur
in most cases, Lahey’s adjudication application attached and incorporated
its Payment Claim dated 23 May 2003 and Multiplex
’s Payment Schedule dated
4 June 2003. Those documents also form part of
the record because the issues
which the adjudicator had to determine cannot be understood without reference to
them.
48 It is clear from the observations of McDougall
J in Musico that the payment claim, the payment schedule, the
adjudication application, the adjudication response and any further submissions
may form part of the record for the purpose of defining the issues submitted for
adjudication, but that does not mean that the whole
of the contents of those
documents thereby becomes part of the record as well. The adjudication
application, the adjudication response
and further submissions may append or
refer to a considerable volume of evidence both oral and in the form of
documents. Evidence
is not normally part of the record, as the High Court
observed in the passage quoted from Craig at paragraph 43 above.
While the New South Wales legislature has altered the law as stated by the High
Court in Craig so as to include reasons for the decision as part of the
record for the purposes of review under s.69 of the Supreme Court Act, it
has gone no further: it has not included as part of the record all of the
material before the Tribunal or decision-maker, as
it might have done in
accordance with a suggestion of Kirby P in Commissioner of Police v District
Court of New South Wales (1993) 31 NSWLR 606, at
618E.
49 It would be especially unfortunate if
adjudication under the Act, intended to be a quick and cheap interim dispute
resolution
mechanism, could be subjected to review under s.69 Supreme Court
Act by a proceeding which becomes “a discretionary general appeal
for error of law on the face of the record” – to borrow the
words of the High Court in Craig at 181 – simply because the record
is allowed to include evidence and submissions generally, rather than being
strictly confined
to the adjudicator’s reasons and to such part of the
documents before the adjudicator as defined the issues for adjudication.
Alleged jurisdictional errors of law
50 By
paragraph 2 of its Summons, Multiplex
seeks orders quashing the Determination
for error of law on the face of the record
in respect of eleven specified
alleged errors. By paragraph 3 of the Summons
Multiplex
seeks, additionally or
alternatively, orders
quashing the Determination for jurisdictional error on the
ground of three specified errors.
51 The Determination
adjudicated upon sixteen Items of claim. Multiplex
originally asserted in
paragraph 2 of its Summons that
error of law had occurred in respect of most of
the sixteen Items of claim; however, at the hearing it abandoned several of its
complaints. As paragraph 3 of the Summons relies upon certain errors of law
alleged in paragraph 2 as giving rise to jurisdictional
error as well, it is
necessary to set out all alleged errors upon which
Multiplex
now
relies.
52 Omitting those allegations now abandoned by
Multiplex
, paragraph 2 of the Summons is as follows:
“Orders in the
nature of certiorari to quash the Determination for error of law on the face of
the record in that:
(a) In respect of items numbered 1, ... 8, 9,
10, 11, 12, 13 and 14 in the Determination the First Defendant erroneously
failed to
assess the value of the work performed.
(b) In respect
of items numbered 1, ... in the Determination the First Defendant erroneously
purported to determine the value of work
performed under the construction
contract between the Plaintiff and the Second Defendant dated 28 May 2002
(Contract) at 100% of the sum agreed for performance of the work in
circumstances where the First Defendant determined that the work was not
completed.
(c) In respect of items numbered 1, ... 8, 9, 10, 11,
12, 13 and 14 in the Determination the First Defendant erroneously purported
to
place the onus of providing evidence as to the value of work performed on the
Plaintiff.
(d) The First Defendant erroneously purported to
determine the value of work performed under the Contract without having carried
out
any inspection of the work or the premises.
(e) The First
Defendant erroneously determined that the Plaintiff’s waiver in February
2003 of the bars on making a claim under
clause 3 of the Contract was
retrospective.
(f) The First Defendant erroneously applied the
terms of clause 3(e) of the Contract to matters extraneous to the Contract, by
determining
that the Plaintiff was required to notify the Second Defendant of
its disagreement with the terms of the Second Defendant’s
letter of 17
February 2003 within the time laid down in clause 3(e) for notification of
disputes arising under the Contract.
(g) The First Defendant
erroneously determined that the Plaintiff’s failure to respond within a
short period to the Second Defendant’s
letter of 17 February 2003,
constituted an acceptance of the assertions contained in that
letter.
(h) In respect of items numbered 10, 11, 12, 13 and 14 in
the Determination the First Defendant erroneously determined that the Plaintiff
was required to indicate in the payment schedule “reasons for withholding
payment” when the scheduled amount was less
than the claimed amount
because the work claimed had been deleted from the Contract by variation and had
therefore not been performed.
(i) The First Defendant erroneously
determined that the description of the deduction for cleaning charges at item
BC14 of the payment
schedule was not, or not sufficient, “reasons”
for withholding payment for the purpose of sub-section 14(3) of the Act
(item
numbered 15 in the Determination).
(j) The First Defendant
erroneously determined that in respect of item numbered 9 in the determination,
the Plaintiff did not provide
‘reasons’ in its payment schedule for
withholding moneys.
(k) The First Defendant erroneously failed to
determine the amount of the progress payment to be paid by the Plaintiff to the
Second
Defendant in accordance with the provisions of the
Act.”
Paragraph 3 of the Summons is as
follows:
“Further, or in the alternative, orders in the nature of
certiorari to quash the Determination for jurisdictional error in
that:
(a) The First Defendant had no jurisdiction to determine
that the Plaintiff had on 13 February 2003 waived reliance upon clause 3
of the
Contract retrospectively or at all.
(b) The First Defendant had no
jurisdiction to determine that the Second Defendant was entitled to payment for
variations other than
in accordance with the terms of the
Contract.
(c) The First Defendant had no jurisdiction to determine
the amount of a progress payment other than by reference to the Contract
or by
assessing the value of work performed.”
The extent of an adjudicator’s
jurisdiction
53 The jurisdictional error asserted
in paragraph 3(a) of the Summons is founded upon the error of law alleged in
paragraph 2(e)
of the Summons and relates to Item 8 in the Determination. That
Item is a claim by Lahey for $195,648 in respect of variations described
in its
progress claim as Item 33 and particularised in a fifteen page addendum to the
Payment Claim. Multiplex
responded to this
claim in its Payment Schedule as
follows: “V(ariation) 33 previously rejected as per correspondence sent
27 May 2003”. In a letter of 27 May 2003 to Lahey,
Multiplex
had
denied liability for the claim on the ground that clause 3(a) of the contract
required notification by Lahey of a variation claim within a certain time, the
claim had not been notified within time and, in consequence,
the claim was
“absolutely and conclusively barred”. This was the only
ground relied upon by
Multiplex
in its Payment Schedule to deny liability for
Item 8.
54 In its Adjudication Submission, Lahey
asserted an oral agreement made between the parties on 13 February 2003 and
confirmed
by Lahey in a letter dated 17 February 2003. Lahey submitted that by
this agreement Multiplex
had waived its right to rely on clause
3(a) of the
contract in respect of the variation claimed in Item 8.
55 In paragraph 5.12 of its Adjudication Response,
Multiplex
conceded that an agreement had been made in February 2003 between
the
parties whereby
Multiplex
waived compliance with clause 3(a) in respect of
variations, but it asserted that the waiver had been
prospective, not
retrospective, so that it did not apply to the variations claimed in Item
8.
56 Mr Luikens
proceeded to determine the issue thus
raised between the parties. He found that, by the agreement made in February
2003,
Multiplex
had waived the notification requirements of clause 3(a) in
respect in respect of the variations claimed in Item 8
and he allowed that claim
accordingly.
Multiplex
now submits that the adjudicator fell into
jurisdictional error of law in determining
the question at all. It says that an
adjudicator has no jurisdiction under the Act to decide whether or not a term of
a construction
contract has been waived.
57 Multiplex
’s argument proceeds
thus:
– an adjudicator’s jurisdiction is limited by ss.8, 9
and 10 of the Act, which specify the matters in respect of which the adjudicator
may make a determination;
– by s.9(a) the amount of a progress
payment to which a person is entitled in respect of a construction contract is
the amount calculated in
accordance with the terms of the
contract;
– clause 3(a) was an express term of the contract and Mr
Luikens
had no power under the Act to calculate the amount of Lahey’s
progress claim except by giving effect to that clause;
– the
adjudicator exceeded his jurisdiction in purporting to determine the amount of
the progress claim on the basis of a finding
that Multiplex
had waived clause
3(a).
I note that this submission was never made by Multiplex
to Mr
Luikens
.
58 I am unable to accept this submission.
When s.9(a) and s.10(1)(a) and (2)(a) speak of calculating a progress payment or
valuing construction work and related goods and services “in accordance
with the terms of the contract” they must mean “in accordance
with the relevant or applicable terms of the contract”. What
are the relevant or applicable contractual terms which affect the calculation or
valuation which the adjudicator must make
might depend on the construction of
the express terms of the contract, or upon whether a term is to be implied in
order to give the
contract business efficacy, or it might depend on whether a
term has been waived or cannot be relied upon because of an estoppel.
If
determination of a disputed progress claim depends upon resolution of a question
as to what are the relevant terms of a contract,
it must necessarily be implicit
in the jurisdiction conferred on the adjudicator by the Act that he or she have
jurisdiction to decide
that question.
59 Accordingly, I
hold that Mr Luikens
did not exceed his jurisdiction in determining the question
which both parties raised for
his decision, namely, whether or not
Multiplex
had
waived compliance with clause 3(a) of the contract in respect of the work
comprised
in Item 8. If he fell into error of law in reaching his conclusion
that the clause had been waived retrospectively, that is a non-jurisdictional
error which is not susceptible to review under s.69(1) and (3) Supreme Court
Act, for the reasons I have given earlier.
Construction of s.14(3) and s.20(2B)
60 The
second ground upon which Multiplex
asserts that Mr
Luikens
fell into
jurisdictional error of law is, I think, not very clearly
articulated either in
paragraph 3(b) of the Summons or in
Multiplex
’s written submissions,
although it received a little more
elaboration in Mr Rudge’s oral
submissions. Mr Rudge says that the adjudicator excluded from his consideration
matters to
which he was required to give consideration by reason of his
misconstruction of the Act. This error of law, he says, infects the
adjudicator’s findings in relation to a number of Items in the
Determination. If Mr Rudge is correct in this assertion, the
adjudicator’s error would be a jurisdictional error of law rendering the
Determination susceptible to review and quashing under
s.69(1) and (3)
Supreme Court Act.
61 The circumstances in which
the adjudicator arrived at his conclusion in respect of Item 8 in the
Determination illustrate how
this issue
arises.
62 Multiplex
’s Payment Schedule gave only
one reason for rejecting the amount claimed in respect of variation work
referred
to in Item 8, namely, that the claim was barred by clause 3(a) of the
contract. Accordingly, the Payment Schedule allowed nothing
for the claim in
Item 8.
Multiplex
’s Adjudication Response, however, contained a detailed
assessment of Lahey’s claim
for variation work in Item 8 asserting, for
example, that the claim incorporated a provision for overhead of 17.5% rather
than 10%,
as provided by clause 3(e)(vii) and clause 6.04 of the Special
Conditions.
Multiplex
’s assessment of the claim in Item 8 was
less than a
third of what Lahey had claimed.
63 Mr Luikens
concluded that because
Multiplex
’s Payment Schedule gave as
Multiplex
’s only reason for rejection of
the claim its reliance upon
clause 3(a) of the contract, he was precluded by s.20(2B) of the Act from having
regard to the manner
in which
Multiplex
now assessed the value of the variation
work in Item 8 in its Adjudication Response. Having rejected
Multiplex
’s
submissions and its evidence as to assessment of the variation work on this
ground, and having accepted Lahey’s submission
that
Multiplex
had waived
reliance on clause 3(a) of the contract in respect of the work in Item 8, the
adjudicator allowed the whole
of Lahey’s claim for that
Item.
64 The relevant provisions of the Act are as
follows. Section 13 relevantly provides:
“(1) A person referred to
in section 8 (1) who is or who claims to be entitled to a progress payment (the
claimant) may serve a payment claim on the person who, under the
construction
contract concerned, is or may be liable to make the payment.
(2) A
payment claim:
(a) must identify the construction work (or
related goods and services) to which the progress payment relates,
and
(b) must indicate the amount of the progress payment that the
claimant claims to be due (the claimed amount), and
(c) must
state that it is made under this Act.
(3) The claimed amount may
include any amount:
(a) that the respondent is liable to pay the
claimant under section 27 (2A), or
(b) that is held under the
construction contract by the respondent and that the claimant claims is due for
release.”
Section 14 relevantly provides:
“(1) A
person on whom a payment claim is served (the respondent) may reply to the claim
by providing a payment schedule to the
claimant.
(2) A payment
schedule:
(a) must identify the payment claim to which it
relates, and
(b) must indicate the amount of the payment (if any)
that the respondent proposes to make (the scheduled
amount).
(3) If the scheduled amount is less than the claimed
amount, the schedule must indicate why the scheduled amount is less and (if it
is less because the respondent is withholding payment for any reason) the
respondent’s reasons for withholding payment.”
Section 17
relevantly provides:
“(1) A claimant may apply for adjudication of a
payment claim (an adjudication application) if:
(a) the
respondent provides a payment schedule under Division 1 but:
(i)
the scheduled amount indicated in the payment schedule is less than the claimed
amount indicated in the payment claim ...”
Section 20
relevantly provides:
“(1) Subject to subsection (2A), the respondent
may lodge with the adjudicator a response to the claimant’s adjudication
application (the adjudication response) at any time within:
(a) 5
business days after receiving a copy of the application, or
(b) 2
business days after receiving notice of an adjudicator’s acceptance of the
application,
whichever time expires later.
(2) The
adjudication response:
(a) must be in writing,
and
(b) must identify the adjudication application to which it
relates, and
(c) may contain such submissions relevant to the
response as the respondent chooses to include.
(2A) The respondent
may lodge an adjudication response only if the respondent has provided a payment
schedule to the claimant within
the time specified in section 14 (4) or 17 (2)
(b).
(2B) The respondent cannot include in the adjudication
response any reasons for withholding payment unless those reasons have already
been included in the payment schedule provided to the
claimant.”
Section 22 relevantly
provides:
“(1) ...
(2) In determining an adjudication
application, the adjudicator is to consider the following matters
only:
(a) the provisions of this Act,
(b) the
provisions of the construction contract from which the application
arose,
(c) the payment claim to which the application relates,
together with all submissions (including relevant documentation) that have
been
duly made by the claimant in support of the claim,
(d) the
payment schedule (if any) to which the application relates, together with all
submissions (including relevant documentation)
that have been duly made by the
respondent in support of the schedule,
(e) the results of any
inspection carried out by the adjudicator of any matter to which the claim
relates.”
65 Mr Rudge submits that the words
in s.14(3), “if it is less because the respondent is withholding
payment for any reason”, are to be construed as meaning “if it
is less because the respondent is holding back a payment, otherwise properly due
under
the contract, by reason of a cross claim or set-off”: see e.g.
T22.51ff, T5.1-.17. Where a cross claim or set-off is the reason
for not paying
the amount claimed in the Payment Claim, says Mr Rudge, that reason must be
disclosed in the Payment Schedule. But
where the respondent refuses to pay the
amount claimed on the ground that it is not due and payable according to the
terms of the
contract, that is not “withholding payment”
within the meaning of that phrase in s.14(3) and the reason for not paying the
amount claimed is not required to be shown in the Payment
Schedule.
66 In the present case, Mr Rudge says, one
reason for not paying the amount claimed for Item 8 was that the claim was
excessive
when valued according to the terms of the contract. That reason was
not required to be disclosed in the Payment Schedule and, consequently,
the
adjudicator was not entitled to exclude it from his consideration by reason of
s.20(2B). That reason, together with the evidence
in support of it, was,
therefore, properly part of Multiplex
’s Adjudication Response and the
adjudicator had a duty under s.22(2)(d) to consider it. His error of law in
refusing to consider it was a jurisdictional error requiring that the
determination be quashed.
67 I am unable to accept this
submission. The evident purpose of s.13(1) and (2), s.14(1), (2) and (3), and
s.20(2B) is to require the parties to define clearly, expressly and as early as
possible what are the issues
in dispute between them; the issues so defined are
the only issues which the parties are entitled to agitate in their dispute and
they are the only issues which the adjudicator is entitled to determine under
s.22. It would be entirely inimical to the quick and efficient adjudication of
disputes which the scheme of the Act envisages if a respondent
were able to
reject a payment claim, serve a payment schedule which said nothing except that
the claim was rejected, and then “ambush”
the claimant by disclosing
for the first time in its adjudication response that the reasons for the
rejection were founded upon a
certain construction of the contractual terms or
upon a variety of calculations, valuations and assessments said to be made in
accordance
with the contractual terms but which the claimant has had no prior
opportunity of checking or disputing. In my opinion, the express
words of
s.14(3) and s.20(2B) are designed to prevent this from
happening.
68 Section 14(3) requires that if the
respondent to a payment claim has “any reason” for
“withholding payment”, it must indicate that reason in the
payment schedule. To construe the phrase “withholding
payment” as meaning “withholding payment only by reason of a
set-off or cross claim” is to put a gloss on the words which their
plain
meaning cannot justify. The phrase, in the context of the subsection as a
whole, simply means “withholding payment of
all or any part of the claimed
amount in the payment claim”. If the respondent has any reason whatsoever
for withholding payment
of all or any part of the payment claim, s.14(3)
requires that that reason be indicated in the payment schedule and s.20(2B)
prevents the respondent from relying in its adjudication
response upon any
reason not indicated in the payment schedule. Correspondingly, s.22(d) requires
the adjudicator to have regard only to those submissions which have been
“duly made” by the respondent in support of the payment
schedule, that is, made in support of a reason for withholding payment which has
been
indicated in the payment schedule in accordance with s.14(3).
69 A subsidiary argument which Mr Rudge appeared to
advance in his oral submissions was that Multiplex
had given a sufficient reason
in its Payment Schedule for withholding payment of the claim in respect of Item
8 simply by stating that the claim was “rejected”;
Multiplex
had
thereby complied with the requirements of s.14(3) and was permitted to amplify
that reason in its Adjudication Response by giving particulars of valuations and
calculations on the
basis of which the claim had been rejected.
70 I am unable to accept this submission. For a
respondent merely to state in its payment schedule that a claim is rejected is
no more informative than to say merely that payment of the claim is
“withheld”: the result is stated but not the reason
for arriving at
the result. Section 14(3) requires that reasons for withholding payment of a
claim be indicated in the payment schedule with sufficient particularity to
enable
the claimant to understand, at least in broad outline, what is the issue
between it and the respondent. This understanding is necessary
so that the
claimant may decide whether to pursue the claim and may know what is the nature
of the respondent’s case which
it will have to meet if it decides to
pursue the claim by referring it to
adjudication.
71 For these reasons, I am of the view
that Mr Luikens
did not fall into error in his construction of s.14(3) and
s.20(2B) of the Act and that he rightly rejected the submissions and evidence of
Multiplex
in its Adjudication Response in support
of reasons for withholding
payment of Item 8 which were not indicated in the Payment Schedule. It follows
that Mr
Luikens
did not
commit jurisdictional error of law in his determination
of Item 8.
What a Payment Schedule should
show
72 Multiplex
asserted in its Adjudication
Response that it was not liable to pay the claims in Items 9, 10, 11, 12, 13 and
14 because
the work claimed in those Items had been deleted from the contract.
Mr
Luikens
rejected that reasons for non-payment on the ground
that it had not
been indicated by
Multiplex
in its Payment Schedule, as required by s.14(3) and
s.20(2B) of the Act. It is to be noted that Lahey did not concede that the work
in those Items had been deleted from the contract
and had not been performed.
Multiplex
now submits that Mr
Luikens
fell into jurisdictional error of law in
failing to take into
account its reasons for non-payment of these
Items.
73 Item 9 relates to a claim by Lahey which
depends on the value of work said to have been deleted by Multiplex
from
Lahey’s
contract. Lahey said that the value of the work deleted was
$334,401. In its Payment Schedule,
Multiplex
dealt with the claim in
the
following way. In a summary on the front page of the Schedule
Multiplex
said
merely: “Back charges/contra charges/scope deletions
(BC1-BC16)”. Attached to the summary was a document entitled
“Assessment of progress claim number 14”. Under a heading
“Back charges/contra charges/ scope deletions” appears
relevantly “BC1 Deletion of southern tenancies wall panels (by
others)”; then the deduction claimed by
Multiplex
is shown at
$434,010 and the deduction claimed by Lahey is shown at $334,401. No further
explanation is given.
74 In its Adjudication Response
at Tab B, Multiplex
asserted in relation to Item 9 that there had been an
agreement between itself
and Lahey in November 2002, confirmed by letter dated 2
December 2002, that
Multiplex
would award the panelling in respect of the
southern tenancies to another sub-contractor in order to alleviate delay and
that the cost of engaging such other contractor would
be about $90,000 and would
be charged to Lahey’s account.
Multiplex
asserted that it had ultimately
awarded the sub-contract
to Batoma Commercial Interiors Pty Ltd and that under
clause 5 of the contract with Lahey,
Multiplex
was entitled to set off against
the claim now made by Lahey the amount which
Multiplex
had paid to
Batoma.
75 Mr Luikens
was of the view that the Payment
Schedule had not sufficiently indicated
Multiplex
’s reasons for
withholding
payment of the full amount claimed which
Multiplex
sought to advance
in its Adjudication Response. In my opinion, the adjudicator
erred in so
holding.
76 A payment claim and a payment schedule
are, in many cases, given and received by parties who are experienced in the
building
industry and are familiar with the particular building contract, the
history of construction of the project and the broad issues
which have produced
the dispute as to the claimant’s payment claim. a payment claim and a
payment schedule must be produced
quickly; much that is contained therein in an
abbreviated form which would be meaningless to the uninformed reader will be
understood
readily by the parties themselves. A payment claim and a payment
schedule should not, therefore, be required to be as precise and
as
particularised as a pleading in the Supreme Court. Nevertheless, precision and
particularity must be required to a degree reasonably
sufficient to apprise the
parties of the real issues in the dispute.
77 A
respondent to a payment claim cannot always content itself with cryptic or vague
statements in its payment schedule as to
its reasons for withholding payment on
the assumption that the claimant will know what issue is sought to be raised.
Sometimes the
issue is so straightforward or has been so expansively agitated in
prior correspondence that the briefest reference in the payment
schedule will
suffice to identify it clearly. More often than not, however, parties to a
building dispute see the issues only from
their own viewpoint: they may not be
equally in possession of all of the facts and they may not equally appreciate
the significance
of what facts are known to them. This will be so especially
where, for instance, the contract is for the construction of a dwelling
house
and the parties are the owner and a small builder. In such cases, the parties
are liable to misunderstand the issues between
them unless those issues emerge
with sufficient clarity from the payment schedule read in conjunction with the
payment claim.
78 Section 14(3) of the Act, in
requiring a respondent to “indicate” its reasons for withholding
payment, does not require that a payment
schedule give full particulars of those
reasons. The use of the word “indicate” rather than
“state”, “specify”
or “set out”, conveys an
impression that some want of precision and particularity is permissible as long
as the essence
of “the reason” for withholding payment is made known
sufficiently to enable the claimant to make a decision whether
or not to pursue
the claim and to understand the nature of the case it will have to meet in an
adjudication.
79 In the present case, Multiplex
wished
to resist payment of the claim in Item 9 on the ground that the work had been
taken away
from Lahey and awarded to another sub-contractor, and that the cost
charged by the other sub-contractor was for Lahey’s account.
Cryptic
though the statements in the Payment Schedule were in respect of BC1, I think
that they were sufficient to indicate to Lahey
the reason for non-payment of
that claim for the purposes of s.14(3). The project in which
Multiplex
and
Lahey were engaged was a large one and Lahey’s sub-contract was for very
extensive work.
It must be assumed that Lahey was highly experienced in the
building industry and was generally aware of the history of its own
involvement
in that project by the time it received the Payment Schedule. BC1 was referred
to in the summary page in the Payment
Schedule under the heading “back
charges/contra charges”, indicating to a person in the position of Lahey
that non-payment
was said to be due to an offsetting charge that
Multiplex
was
entitled to make against Lahey or for its account. The attached assessment
indicated the scope of the work: “Deletion of southern
tenancies’ wall panels”. It is a fair assumption that Lahey
must have known what particular work in its sub-contract was meant by that
reference. The statement
“(by others)” must reasonably have
indicated to a person in Lahey’s position that work on the
“southern tenancies’ wall panels” had been done by
other sub-contractors. The fact that the Item was included as a “Back
Charge” or “Contra Charge”
must reasonably have indicated that
Multiplex
claimed to be entitled to charge to Lahey’s account the cost of
the work which
had been done by the other sub-contractors. The difference
between the amount allowed for this work by Lahey in its Payment Claim
and the
amount allowed by
Multiplex
for this Item, as shown in the assessment, must
reasonably have indicated to Lahey the cost of
the work done by other
sub-contractors which
Multiplex
claimed it was entitled to charge back to Lahey.
By reference to the work
for this Item as specified in its own sub-contract,
Lahey must reasonably have been able to form a view whether the cost charged
by
the other sub-contractors for the work was fair and
reasonable.
80 In these circumstances, in my view,
Lahey was given a sufficient indication of Multiplex
’s reasons for
withholding payment
of Item 9/BC1 it to determine whether it should persist in
its claim for this Item and to understand the nature of the case it would
have
to meet in an adjudication.
81 In my opinion, Mr
Luikens
erred in concluding that he was required to exclude from his
considerations the submissions and evidence
advanced by
Multiplex
in opposition
to the claim in Item 9. Accordingly, he failed to take into account matters
which s.22(2)(d) required him to take into account and he thereby fell into
jurisdictional error. I will return to the consequences shortly.
Items 10 to 15
82 Mr Rudge says that
Multiplex
’s complaints as to Items 10, 11, 12, 13, 14 and 15 of the
Determination fall into the same
category as the complaint as to Item 9:
T23.35, T25.44. Those items relate to the alleged deletion of work from the
contract or
to “back charges” and
Multiplex
’s Payment
Schedule treats each of the claims in the same way as the claim for Item
9.
83 Whereas Mr Luikens
rejected
Multiplex
’s
submissions as to Item 9 on one ground, namely, non-compliance with s.14(3), he
rejected
Multiplex
’s submissions as to Items 10, 11, 12, 13, 14 and 15 on
two grounds: first, the documentation provided
by
Multiplex
in its Adjudication
Response did not support its reasons for rejecting the claims and second,
Multiplex
had not given
a sufficient indication of its reasons for rejecting the
claims in its Payment Schedule in accordance with s.14(3) of the
Act.
84 In my view, it does not matter in the result
whether Mr Luikens
was correct to reject
Multiplex
’s submissions on the
second
ground. He took into account in his consideration
Multiplex
’s
reasons for non-payment of those Items by reference to the submissions
and the
material included in the Adjudication Response and he was not convinced of their
sufficiency. If he erred in his evaluation
of that material, the error was
clearly non-jurisdictional so that I would not have quashed the Determination in
respect of those
Items even if Mr
Luikens
had committed jurisdictional error in
his second reason for rejecting
Multiplex
’s submissions.
Whether adjudicator must assess value by
inspection
85 It is not clear from
Multiplex
’s submissions whether it asserts that the error in respect of
Item 1 of the Determination
was jurisdictional error. Mr Rudge seemed to
suggest (Summons para.3(c) and T25.10ff) that Mr
Luikens
had made no real
attempt to
assess the value of the work claimed in this Item, with the result
that he had not discharged his duty under the Act and had therefore
fallen into
jurisdictional error. I cannot agree. Mr
Luikens
noted that
Multiplex
had not
stated the basis for its assessment and,
with some misgivings, he determined
that the Tender Breakdown which formed part of the contract was the best
evidence available of
the value of the work comprised in the subject claim. If
his Determination on this basis was erroneous, the error did not go to
jurisdiction and is therefore not reviewable, for the reasons which I have
given.
86 Mr Rudge seemed to suggest (Outline, para.52)
that Mr Luikens
, in failing to inspect the works in dispute so that he could
value
them for himself, failed to determine the value of Lahey’s progress
claim by reference to the value of the work performed,
as required by s.9(b) of
the Act. By reason of that failure, Mr Rudge submits, I gather, that Mr
Luikens
asked himself a wrong question and ignored relevant
material, thereby falling
into jurisdictional error.
87 This submission seems to
found on the proposition that because s.21(4)(d) provides that an adjudicator
“may carry out an inspection of any matter to which the claim
relates”, it follows that the adjudicator must carry out such
an inspection so that if an inspection is not carried out, matter has not been
taken into account which the Act requires
to be taken into
account.
88 In my view, this proposition cannot be
supported: s.21(4) makes it clear that it is within the discretion of the
adjudicator
whether or not to take any of the steps set out in paragraphs (a) to
(d). Exercise of that discretion one way or another will depend
upon the
adjudicator’s judgment as to whether or not he or she will be assisted in
reaching a decision within the constraints,
particularly the time constraints,
imposed by the Act. If the adjudicator commits an error of judgment in making
that discretionary
decision, it is an error within jurisdiction and is not
reviewable by way of certiorari.
89 The errors of law
assigned in paragraph 2 of the Summons which are not said to produce
jurisdictional error are not reviewable
for the reasons which I have given and I
therefore do not need to discuss them further.
Whether the Determination should be
quashed
90 For the above reasons, I am not
satisfied that Multiplex
has made out any ground for the quashing of the
Determination under
s.69(1) of the Supreme Court Act save in respect of
Item 9. As I have found in paragraphs 79-81, the error into which Mr
Luikens
fell led him to exclude from his
consideration
Multiplex
’s evidence and
submissions in respect of Item 9, which was matter which he was required to take
into
account by s.22(2)(d) of the Act. The difference between the parties as to
what
Multiplex
owes in respect of Item 9 is $99,609. That is not a trivial
sum
in the context of a total of $529,034.59 (excluding GST) which Mr
Luikens
determined was the adjudicated amount for the purpose
of s.22(1)(a) of the Act.
It seems to me, therefore, that the Determination is flawed by reason of a
jurisdictional error. Remedies by way of
judicial review are discretionary.
The question now arises whether, in the exercise of the Court’s
discretion, the Determination
should be quashed.
91 The
first point to note is that although the jurisdictional error in this case has
affected only one disputed claim amongst
the sixteen which Mr Luikens
considered
in his adjudication, the Court cannot quash just the decision which affects Item
9, leaving
the rest of the Determination intact. That is because the
adjudication process is required by s.22(1) of the Act to produce only three
findings: the adjudicated amount (if any), the date upon which that amount
becomes payable and
the rate of interest payable. Only these findings are
reflected in the adjudication certificate which is issued under s.24(3) of the
Act and filed as a judgment under s.25(1). The adjudicator has no power to
correct the adjudication amount where it is shown to have been produced by error
of law, whether
or not jurisdictional. There is power to correct a
determination under s.22(5) only in accordance with what might loosely be called
the “slip rule”. None of the circumstances provided in s.22(5) is
applicable in the present case.
92 It seems to me that
because the Act requires a determination to produce only one amount for payment
pursuant to a payment claim
served under s.13(1), despite the fact that the
payment claim might have comprised numerous claims for separate and distinct
items of work, and because
the Act does not provide for variation of the
adjudicated amount, or the judgment debt, if the adjudicator’s decision as
to
any component part of the adjudicated amount is shown to be liable to be set
aside on judicial review, the consequence is that, subject
to other
discretionary considerations, the whole of the determination must be quashed if
jurisdictional error infects any part of
the process whereby the adjudication
amount has been produced. This is, no doubt, a highly inconvenient result.
However, I do not
see any means of avoiding it, as the Act presently
stands.
93 I turn now to the discretionary
considerations as to whether relief under s.69(1) Supreme Court Act
should be granted.
94 It is well established that
relief in the nature of the prerogative writs may be withheld in the
Court’s discretion if
there is another “equally effective and
convenient remedy”: see e.g. R v Hillingdon London Borough Council; Ex
parte Royco Homes Ltd [1974] QB 720, at 728 per Lord Widgery CJ; Ex
parte Waldron [1986] QB 824, at 852 per Glidewell LJ; Boral Gas (NSW)
Pty Ltd v. Magill (1993) 32 NSWLR 501, at 508ff per Kirby P. In the case of
an adjudication under the Act, it might be said that the legislature has
provided within the
Act itself the means whereby errors of law, jurisdictional
or non-jurisdictional, may be corrected. The effect of s.32 is to render a
determination and a judgment founded upon it merely of temporary duration until
all matters in dispute may be determined
finally by litigation or other dispute
resolution procedures. It might be said, therefore, that errors made in the
adjudication
process should await correction and restitution by the process
envisaged by s.32 and not by invocation of the judicial review process under
s.69 Supreme Court Act.
95 I do not think that
there can be a hard and fast rule upon which the Court acts in exercising the
discretion whether to grant
relief by way of certiorari in respect of an
adjudication under the Act which is shown to be flawed by jurisdictional error.
The
authorities show that the Courts take a pragmatic approach to the question
whether there is another equally effective and convenient
remedy besides the
grant of prerogative relief, and that the discretion is very much grounded upon
the particular facts of the case.
In Ex parte Waldron, Glidewell LJ said
at 852:
“Whether the alternative statutory remedy will resolve the
question at issue fully and directly; whether the statutory procedure
would be
quicker, or slower, than procedure by way of judicial review; whether the matter
depends on some particular or technical
knowledge which is more readily
available in the alternative appellate body; these are amongst the matters which
a court should take
into account when deciding whether to grant relief by way of
judicial review when an alternative remedy is
available.”
96 When an adjudication under the
Act is shown to have resulted from jurisdictional error, a weighty circumstance
in the exercise
of the discretion whether to grant relief under s.69(1)
Supreme Court Act is the fact that the scheme of the Act requires that a
respondent “pay now, argue later”: s.25. In some cases
adherence to this scheme by refusal of prerogative relief on discretionary
grounds may produce no great hardship to
the respondent; in other cases, it
may. For example, where the amount in dispute is fairly small and the whole
dispute may be speedily
and cheaply resolved in the Local Court, a respondent in
an adjudication may be shown to have a more effective and convenient remedy
for
redress of an erroneous determination in proceedings conducted in the Local
Court rather than by debating esoteric questions
of administrative law at great
expense in the Supreme Court in an application for review under s.69(1)
Supreme Court Act. Indeed, in such a case the Supreme Court may be able
to come to the conclusion at an early stage of an application for relief under
s.69 that the proceedings are doomed to failure because relief, even if
otherwise available, would be withheld on discretionary grounds
so that it could
simply dismiss the application, or stay it on terms, under Pt 13 r5(1). In the
circumstances postulated, such a result would be in accordance with the general
policy of the Act. In different circumstances,
the interests of justice may
require the policy of the Act to give way.
97 In the
present case, the amount involved in Item 9 is nearly $100,000. There is no
evidence that the whole of the dispute between
Multiplex
and Lahey is in the
process of litigation or resolution by arbitration or mediation. There is no
evidence as to how long
it would take before the jurisdictional error which
produced rejection of
Multiplex
’s evidence and submissions as to Item 9
could be remedied and relief, if appropriate, given in litigation conducted on a
final basis.
98 Prima facie, it seems to me that
jurisdictional error in the adjudication process which produces an obligation on
the part of
Multiplex
to make a substantial payment should be corrected by the
grant of relief under s.69 unless an equally effective and convenient remedy is
shown. On the evidence before the Court, no such remedy has been shown to be
available so that the Determination should be quashed.
Consequences of
quashing a determination
99 The consequences of the
Court’s order in this case will doubtless be inconvenient and expensive
for the parties. That
is, principally, the result of the way in which the Act
is structured and because it makes no express provision for what is to happen
if
a determination under s.22 or a judgment entered pursuant to s.25(1) is set
aside for jurisdictional error of law.
100 If a payment
claim which originates an adjudication comprises the whole of the claims made by
that claimant under the contract,
the consequence of quashing a determination
may be relatively straightforward: the whole of the dispute, instead of being
determined
on an interim basis by the adjudicator under the Act, may simply
await final determination by litigation or other dispute resolution
procedures.
If, on the other hand, a payment claim is in respect of many progress claims
made under a contract and considerable
construction work remains to be carried
out under the contract, the matter will probably not be so straightforward. The
claimant
will no doubt want the payment claim determined before completing
construction work. Can the claimant re-submit the dispute constituted
by the
payment claim and the payment schedule to the same adjudicator to be determined
according to the reasons given by the Court
in quashing the original
determination? Or is the adjudicator, having made a determination under
s.22(1), functus officio?
101 In my opinion, the
solution lies in s.26 of the Act, which is as follows:
“(1) This
section applies if:
(a) a claimant fails to receive an
adjudicator's notice of acceptance of an adjudication application within 4
business days after
the application is made, or
(b) an
adjudicator who accepts an adjudication application fails to determine the
application within the time allowed by section 21
(3).
(2) In
either of those circumstances, the claimant:
(a) may withdraw
the application, by notice in writing served on the adjudicator or authorised
nominating authority to whom the application
was made, and
(b) may make a new adjudication application under section 17.
(3) Despite section 17 (3) (c), (d) and (e), a new adjudication
application may be made at any time within 5 business days after the claimant
becomes entitled
to withdraw the previous adjudication application under
subsection (2).
(4) This Division applies to a new application
referred to in this section in the same way as it applies to an application
under section 17.”
102 An adjudicator may
fail to determine an adjudication application for the purposes of s.26(1)(b) for
a number of reasons. The adjudicator may become incapable of making the
determination within the time required or may for some
reason refuse to do so or
become disqualified from doing so. But, in my opinion, an adjudicator may also
fail to determine an adjudication
within time for the purposes of the subsection
if the determination is purportedly delivered within time but is not given
according
to law. For example, where the adjudicator has given a determination
within time but it has been procured by fraud, it could hardly
be said that the
adjudicator has performed the task which the Act requires of him or her within
the time stipulated in s.21(3).
The same may be said of a case in which the
adjudicator delivers a determination within the time stipulated but the
determination
has been given without jurisdiction. In such cases, it may be
said that the determination is of no effect: it is as if the adjudicator
had
made no decision at all.
103 When an adjudication under
the Act is quashed pursuant to judicial review, in my opinion the claimant
becomes entitled to withdraw
its adjudication application under s.26(2) upon and
from the date upon which the quashing order is made because on that date it has
been ascertained that the adjudicator did
not determine the adjudication
according to law within the time allowed by the Act, for the purposes of
s.26(1)(b). The claimant may then, within five business days of the quashing
order, make a new adjudication application under s.26(3). That subsection, in
conjunction with s.17(3)(c), (d) and (e), makes it clear that the adjudication
process does not start all over again from the beginning. Rather, there is an
adjudication pursuant to a fresh adjudication application, of the dispute as
defined by the original payment claim and the original
payment schedule. The
respondent may not, therefore, make any submissions to the new adjudicator in
reliance upon reasons for withholding
payment of the original payment claim
which were not indicated in its original payment schedule, as provided in
s.14(3) and s.20(2B). The new adjudicator appointed by the nominating authority
under s.19 may, or may not, be the adjudicator who conducted the original
adjudication, as considerations of convenience, saving of expense
and
perceptions of pre-judgment may require. In conducting the new adjudication,
the adjudicator would, doubtless, have regard to
the reasons of the Supreme
Court for quashing the original determination. By this procedure, the saving in
time and expense envisaged
by the adjudication machinery of the Act may not be
totally lost.
Orders
104 For the reasons I have given, I
propose to order that the Determination of the First Defendant dated 24 July
2003 be quashed.
105 I will stand the proceedings over
for a short time to enable the parties to bring in Short Minutes of Order
reflecting these
reasons. I will then hear argument as to
costs.
106 If the Second Defendant declines to continue
the undertaking which it has given until the making of final orders, I will
immediately
entertain an application for an injunction in terms of paragraph 1
of the Summons.
– oOo –
LAST UPDATED: 04/12/2003
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2003/1140.html