[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales |
Last Updated: 8 April 2004
NEW SOUTH WALES SUPREME COURT
CITATION: Isis Projects Pty Limited v
Clarence Street Limited [2004] NSWSC 222
CURRENT JURISDICTION:
Equity Division
Technology and Construction List
FILE NUMBER(S):
55032/03
HEARING DATE{S): 23/03/04, 24/03/04
JUDGMENT DATE:
29/03/2004
PARTIES:
Isis Projects Pty Limited
(Plaintiff)
Clarence Street Limited (Defendant)
JUDGMENT OF: Einstein
J
LOWER COURT JURISDICTION: Not Applicable
LOWER COURT
FILE NUMBER(S): Not Applicable
LOWER COURT JUDICIAL OFFICER: Not
Applicable
COUNSEL:
Mr R J Powell SC, Mr Elliott (Plaintiff)
Mr
RJH Darke SC, Mr M Southwick (Defendant)
SOLICITORS:
Turtons Lawyers
(Plaintiff)
Watson Mangioni (Defendant)
CATCHWORDS:
Contract
Building and Construction
Building and Construction Industry
Security of Payment Act 1999 (NSW)
Amendments effected by the Building and
Construction Industry Security of Payment Amendment Act 2002
Whether
following amending legislation the Act requires the respondent upon receiving a
payment claim to set out any objection it
may have to the claim (whether it be
an objection arising out of the contract or otherwise) in a payment schedule,
failing which
the respondent is liable to pay the claim whether or not the
claimant be in fact entitled to the progress payment
Application for summary
judgment
Whether General Steel principles apply upon an application for
summary judgment pursued by reference to the Building and Construction Industry
Security of Payment Act 1999 where the parties final rights are
reserved
ACTS CITED:
Building and Construction Industry Security of
Payment Amendment Act 2002.
Building and Construction Industry Security of
Payments Act 1999 (NSW)
DECISION:
Appeal to be dismissed on the
bringing in of short minutes of order
JUDGMENT:
IN THE
SUPREME COURT
OF NEW SOUTH WALES
EQUITY
DIVISION
TECHNOLOGY AND CONSTRUCTION LIST
Einstein
J
Monday 29 March 2004
55032/03 Isis Projects
Pty Limited v Clarence Street Pty
Limited
JUDGMENT
The Appeal
1 There is
before the court an appeal from the judgment of Master Macready delivered on 23
February 2004 dismissing a notice of motion
by which the appellant, the
plaintiff below, Isis Projects Pty Ltd ["Isis"] had sought summary judgment
pursuant to Part 15 rule
2 of the Supreme Court Rules in the sum of $770,
347.11. The respondent, the defendant below, Clarence Street Pty Limited
[“Clarence
Street”] has filed a notice of contention.
2 The
issues, which are raised, concern the proper construction and application of
particular sections of the Building and Construction Industry Security of
Payment Act 1999 ["the Act"]. The Act has been the subject of much attention
over the past few years there now being a reasonably considerable body
of first
instance decisions covering a variety of disparate issues.
3 The
significance of the central issue here raised for decision concerns the effect
of the amendments to the Act effected by the
Building and Construction
Industry Security of Payment Amendment Act 2002.
4 The principal
issue concerns the amendments to section 13(1) and to section 15(4) of the
Act.
5 Section 13 (1) prior to the amendment provided:
"A person
who is entitled to a progress payment under a construction contract (the
claimant) may serve a payment claim on the person
who under the contract is
liable to make the payment."
The amendment replaced this provision with
the following:
"A person referred to in section 8 (1) who is or
who claims to be entitled to a progress payment (the claimant) may serve a
payment claim on the person who under the construction contract
concerned is or may be liable to make the payment."
[emphasis
added to identify the new wording-note also that some words were
removed]
6 Section 15(4) prior to the amendment provided:
Judgment
in favour of the claimant is not to be entered unless the court is satisfied of
the existence of the circumstances referred
to in subsection (1).
The
amendment replaced this provision with the following:
If the claimant
commences proceedings under subsection (2)(a)(i) to recover the unpaid portion
of the claimed amount from the respondent
as a debt:
(a) judgment in
favour of the claimant is not to be given unless the court is satisfied of the
existence of the circumstances referred
to in subsection (1),
and
(b) the respondent is not, in those proceedings,
entitled:
(i) to bring any cross-claim against the claimant,
or
(ii) to raise any defence in relation to matters arising under the
construction contract.
The proper construction of the words
appearing in subsection (4) (b) "in relation to matters arising under the
construction contract" is crucial to the central proposition contended for
by the appellant.
7 The proposition for which the appellant contends
[“the critical issue”] is that the now scheme of the Act
requires the recipient of a payment claim to set out any objection it may have
to the claim (whether it be an objection
arising out of the contract or
otherwise) in a payment schedule. The proposition is that if it fails to do so
it is liable to pay
the claim, whether or not the claimant was in fact entitled
to the progress payment. The proposition is that the recipient may not
later
defend proceedings brought against it by the claimant for the payment of the
claim by raising matters arising under the contract,
or on the basis that the
claimant was not entitled to the payment in question.
The Principles
Appeals from a Master to the Court
8 An appeal from a
decision of a Master lies to a judge of the Court as of right. Generally the
present appeal requires to be approached
by reference to the same considerations
and principles as inform appeals to the Court of Appeal. It is necessary for an
appellant,
therefore, to show that the Master acted on a wrong principle,
allowed extraneous or irrelevant matters to guide or affect him or
her, mistook
the facts, did not take into account some material consideration, or that the
decision was unreasonable or plainly unjust;
see House v R [1936] HCA 40; (1936) 55 CLR
499 at 505; see also Hession v Century 21 South Pacific Limited (In
Liquidation) (1992) 28 NSWLR 120 at 122 per Meagher JA with whom the Court
agreed.
General Steel
9 Applications for summary judgment
generally require to be determined by well-established principles. However, it
has been submitted
that the Act may require an adjustment in terms of parameters
of those principles. This is because an adjudication pursuant to the
Act does
not finally determine the rights of the parties. The matter is examined
below.
10 The well established general principles which treat with the
entitlement of a party to a final determination of his/legal rights
make clear
that a party will not be denied a trial unless the absence of a cause of action
is clearly demonstrated: General Steel Industries Inc v Commissioner for
Railways (NSW) [1964] HCA 69; (1964) 112 CLR 125 at 129. Once it is apparent that
there is a real question to be determined the court does not deal with the
matter summarily: Dey v Victorian Railways Commissioners [1949] HCA 1; (1949) 78 CLR 62
at 91. The test to be applied has been variously described as whether the
matter is "so obviously untenable that it cannot possibly
succeed", "manifestly
groundless", "so manifestly faulty that it does not admit of argument", one
which "the court is satisfied cannot
succeed", one where "under no possibility
can there be a good cause of action", or one which "would involve useless
expense": General Steel at 129; Pannizutti v Trask (1987) 10 NSWLR
531 at 536; Rajski v Powell (1987) 11 NSWLR 522 at 524; Brimson v
Rocla Concrete Pipes Limited [1982] 2 NSWLR 937 at 942.
The
relevant background
11 Early in the Master's judgment the following
background was set out:
“2 On 17 May 2002 plaintiff entered into
a construction contract with the defendant for the refurbishment and fit out of
an
office building at 50 Clarence Street Sydney. The contract includes the
general conditions of contract (AS 2124 -- 1992).
3 The plaintiff's
claims in the summons are for statutory progress claims under the Building
and Construction Industry Security of Payments Act 1999 (NSW)(the Act) which
was recently amended on 3 March 2003. The relevant progress claims were issued
after the commencement of
the amendments. The claims in the summons are not made
pursuant to the plaintiff's contractual entitlement.
4 Practical
completion in respect of the contract was achieved on 4 April 2003 at the
request of the plaintiff company and the certificate
was issued on 14 April
2003.
5 On 15 May 2003 the plaintiff served a progress claim number 12
on the defendant claiming the sum off $1,702,579.34. Under the terms
of the
contract this progress claim would be due on 28 June 2003. Between 26 June 2003
and 4 July 2003 various payments were made
in relation to this progress claim
amounting to $984,225.85 leaving outstanding the sum of $718,353.45. No payment
schedule under
the Act was supplied by the defendant.
6 On 15 July 2003
the plaintiff served a further progress claim number 13 on the defendant
claiming $749,091.72. This included the
$718,353.45 outstanding under progress
claim number 12 and new work valued at $30,738.23. Under the contract this would
become due
for payment on 28 August 2003.
7 There is correspondence in
response to this progress claim on 17 and 25 July 2003. Although the defence
raised a defence that this
was a payment schedule it was conceded for the
purposes of this application that the correspondence did not amount to a payment
schedule.
Therefore in respect of this claim there was no payment schedule
supplied under the Act.
8. Proceedings were commenced by way of a summons
on 29 August 2003.”
The decision of the
Master
Master's description of the triable issues contended for by
the respondent
12 The Master described the respondent’s
contentions as raising triable issues including the following:
(a)
Whether Claims 12 and 13 were payment claims made under s 13 of the Act in
relation to a progress payment. ["The first issue"]
(b) Whether
Progress Claims 12 and 13 were supported by the evidence and information
required by the contract and the Act ["the second issue"].
(c)
Whether Progress Claims 12 and 13 involve a contravention of s 13(5) of the Act
["the third issue"].
13 The holding was that neither the first nor
the third issues could be said to be triable but that the second issue
constituted a
triable issue.
14 There is no notice of contention ground
challenging the finding that the third issue did not constitute a triable issue.
It may
be noted that the issue concerned whether the appellant had purported to
serve more than one payment claim in respect of each reference
date under the
subject contract. It is unnecessary to examine that section of the Master's
judgment.
15 Counsel addressing submissions on the appeal challenged the
accuracy of the above-described short summaries of the first and second
issues.
In particular the appellant contended that the Master, in finding for the
respondent on the second issue, had failed to address
at all the
principal contention advanced by the appellant to the Master.
Agreed
Statement of Issues
16 The parties were able to agree upon a
'Statement of Issues' for the purpose of the Appeal as follows:
Issue
1
Whether the exercise of discretion by the Master not to order
summary judgment in favour of the appellant miscarried by reason of
the failure
to deal with the effect of the amendments made in March 2003 to the Building
and Construction Industry Security of Payment Act 1999 (“the
Act”) and in particular the amendments made to sections 13(1) and 15(4) of
the Act.
Issue 2
In light of the provisions of the Act and
the evidence do any of the following defences give rise to a triable
issue:
a) That the progress claims were not supported by evidence and
information required by the contract;
b) That the progress claims did not
relate to progress payments within the meaning of the Act;
c) That the
progress claims did not sufficiently identify the construction work to which
they related, and therefore failed to satisfy
the requirements of s13(2)(a) of
the Act.
Application to withdraw concession made before the
Master
17 It will be noticed that the Master in his early statement
of the background, had stated that no payment schedule under the Act
had been
supplied by the defendant in relation to progress claim number 12 or in relation
to progress claim number 13.
18 A notice of motion was filed before the
Court on the hearing of the Appeal by which the respondent sought leave to
withdraw a concession
it had made before the Master to the effect that no
payment schedule had been served by the respondent in response to progress
claim 13. If that leave was to be granted the respondent further sought
leave to raise as a ground in its notice of contention that there
was a triable
issue as to whether on the proper construction of the 17 July 2003 communication
to the appellant from DG Jones, this
document comprised a payment schedule
within the Act.
Dealing with the critical issue
19 It may
be that the best approach is to deal with the critical issue immediately and to
then deal with such of the matters which
were before the Court as may still
require determination.
20 This issue is raised by grounds of appeal 2 and
3. It is also identified as an agreed issue in paragraphs 1 and 2 (b) of the
agreed
statement of issues.
21 The Appellant submits that although
submissions were addressed to the Master on the issue, he effectively simply
failed to deal
with the submission at all, albeit briefly referring to the issue
[at 35].
22 To paraphrase sections 3, 8, 13, 14(4) and 15 of the Act they
essentially [and of course subject to the definitions to be found
in section 4]
provide as follows:
· On and from each reference date under a
construction contract a person who has undertaken to carry out construction
work under the construction contract is entitled to a progress payment (section
8);
· a person referred to in section 8 (1) who is or who claims to
be entitled to a progress payment may serve a payment claim on
the person who
under the construction contract concerned is or may be liable to make the
payment (section 13);
· if a claimant serves a payment claim on a
respondent and the respondent does not provide a payment schedule to the
claimant
within the time required by the construction contract or within 10
business days after the payment claim is served, whichever time
expires
earlier, the respondent becomes liable to pay the claimed amount to the
claimant on the due date for the progress payment to which the payment
claim relates (section 14(4));
· if a respondent becomes liable to
pay the claimed amount to the claimant under section 14(4) as a consequence
of having failed to provide a payment schedule within the time allowed by that
section and fails to pay the whole or any part of the claimed amount on or
before the due date for the progress payment to which the payment claim
relates (section 15(1)) then the claimant may recover the unpaid portion of the
claimed amount from the respondent as a debt due to the claimant in any court of
competent jurisdiction (section 15(2)(a)(i));
· if a claimant
commences proceedings under section 15(2)(a)(i) to recover the unpaid portion of
the claimed amount from the
respondent as a debt the respondent is not in those
proceedings entitled to bring any cross-claim against the claimant or to raise
any defence in relation to those matters arising under the construction
contract (section 15(4)).
23 The appellant’s submission was
that the scheme of the amended Act is that:
· Section 15(4)(b) of
the Act prohibits the respondent from raising by way of defence a matter arising
under the contract; and
· section 13 of the Act provides that it is
only necessary for a claimant to claim to be entitled to a progress
payment in order to serve a payment claim: s13 of the Act.
24 The
appellant asks rhetorically: why would the Act permit a person who only claims
to be entitled to a progress payment to serve
a payment claim, but then deny it
the rights that accrue under the Act to persons who serve such a claim?
25 The appellant submits that the legislative scheme is such that the
claimant need not later demonstrate by reference to the contract
that it was,
in fact, entitled to a progress payment. The Master, it is submitted,
therefore erred by approaching this matter on the basis that a triable
issue in
these proceedings was whether Isis was in fact entitled to payment of the
subject payment claims in the proceedings.
26 The submission is that
rather than giving proper effect to s13(1) and s15(4)(b)(ii) of the Act, the
Master erred by ignoring the
amendments to the Act since the decision of the
Court of Appeal in Brewarrina Shire Council v Beckhaus Civil Pty Ltd
[2003] NSWCA 4; (2003) 56 NSWLR 576.
27 The mainstay of the contradictor argument
put by the respondent is as follows:
· that the summary judgment
which was pursued by the appellant before the Master, could only be given if the
Court was satisfied
of the existence of the circumstances referred to in section
15 (1);
· that section 15 (1) in turn requires that the respondent
be shown to have:
- become liable to pay the claimed amount under section
14 (4) as a consequence of having failed to provide a payment schedule within
the time allowed by that section;
- failed to pay the whole or any part
of the claimed amount on or before the due date for the progress payment to
which the payment
related.
· that section 14 (4) [as indeed section
15 (1) (b)] presuppose that the Court will be in a position to identify what is
the
due date for the progress payment to which the payment claim
relates;
· that this is a case in which there was no relevant due
date for the subject progress payments because the proper construction of
the construction contract [clause 42.1 as varied] was [or was
arguably-this raising a triable issue], that no progress claim could be made in
respect of work carried out
after the date of practical completion and before
the final payment claim [the final payment claim entitlement being found in
clause
42.7].
28 In Brewarrina the Court held that the obligation
of the superintendent to issue a payment certificate in relation to a progress
claim [under the
contract which was there examined] was subject to a condition
precedent that the claimant supports the claim with such information
as the
superintendent might reasonably require. Brewarrina was decided at a time
when s13(1) of the Act provided that in order for a party to serve a progress
claim it must be entitled to the progress payment.
29 The
appellant relies upon the Ministers statement in paragraph 4 of the Second
Reading Speech of 12 November 2002 (when the Building and Construction
Industry Security of Payment Amendment Bill was introduced in
Parliament):
“By raising in court defences such as that the work
does not have the value claimed or that the claimant has breached the contract
by doing defective work, some respondents have been able to delay making
progress payments for a long time. Those respondents have
forced claimants to
incur considerable legal costs. They have effectively defeated the intention of
the Act. To overcome the problem,
the bill clarifies that in court proceedings
by a claimant to enforce payment of the debt due under the Act, a respondent
will not
be able to bring any cross-claim against the claimant and will not be
able to raise any defence in relation to matters arising under
the construction
contract. A respondent who wants to raise these matters must do so in a payment
schedule in response to a payment
claim under the Act, or in separate
proceedings.”
30 An anterior question arises as to whether recourse
may be had to the Second Reading Speech. That turns upon whether or not there
is a clear ambiguity thrown up in respect of the issue.
31 In my view
the appellants proposition would be made good if and only if it was possible to
construe:
· Section 14 (4) as concluding with the
words:
- the respondent becomes liable to pay the claimed amount to the
claimant on the claimed due date for the progress payment to which
the payment
claim relates;
· Section 15 (1) (b) as providing that the section is
to apply if the respondent:
- fails to pay the whole or any part of the
claimed amount on or before the claimed due date for the progress payment
to which the payment claim relates.
32 Notwithstanding the terms of the
Second Reading speech it does not seem to me that the appellant’s
above-described proposition
can be accepted. To read the word "claimed" into
each of sections 14 (4) and 15 (1) (b) would be to do violence in an
unprincipled
way to the proper construction of these sections.
33 Hence
it is clearly necessary in order that a claimant prove that a respondent's
liability has accrued under section 15 (1) (a)
[to satisfy the precondition to
be found in subsection (4) (a)], that the claimant prove that a valid
payment claim has been served and also clearly prove what is the due date for
the progress payment. There will of course always
be a due date for a progress
payment under a construction contract because the Act [section 11] provides for
such a date as being
either:
· the date on which the payment becomes
due and payable in accordance with the terms of the contract;
or
· if the contract makes no express provision with respect to the
matter, the date occurring 10 business days after a payment
claim is made in
relation to the payment.
34 The Master found (at [26]) that there was no
triable issue of the type raised by the respondent. That proposition was
effectively
that:
· upon the true construction of clause 42.1,
there is no reference date between the issue of the Certificate of Practical
Completion,
and the period for the making of the Final Payment Claim under
clause 42.7 (save perhaps in respect of work performed in execution
of a
variation directed after Practical Completion);
· it follows that
in this case there was no entitlement to a progress payment in respect of work
done between those times, yet
Progress Claims 12 and 13 impermissibly assert
such an entitlement;
· by Progress Claims 12 and 13 the Appellant
has purported to make progress claims in respect of dates, and work performed,
subsequent
to practical completion yet prior to the period for the making of the
Final Payment Claim under clause 42.7.
35 In short the proposition
depended upon the proper construction of clause 42.1 which read inter
alia:
"At the times for payment claims stated in the Annexure [it is
common ground that the Annexure required payment claims to be made
monthly on
the 15th day of the month or the nearest working day after the 15th
day] and upon issue of a Certificate of Practical Completion and within the
time prescribed by Clause 42.7, the Contractor shall deliver
to the
Superintendent claims for payment supported by evidence of the amount due to the
Contractor and such information as the Superintendent
may reasonably
require..."
36 Clause 42.7 provided inter alia:
"Within 28 days
after the expiration of the Defects Liability Period, or where there is more
than one, the last to expire, the Contractor
shall lodge with the Superintendent
a final payment claim and endorse it 'Final Payment Claim'..."
37 The
real question, which arises on the Appeal, is as to whether the Master is shown
to have committed an appellable error on the
approach which he took to this
construction issue in the environment of a summary judgment application.
38 In my view, for the reasons given below, the answer to this question
is in the affirmative.
General Steel and the construction issue
39 Before dealing with the construction issue it is necessary and
appropriate to examine the extent to which the General Steel test
remains
applicable to the subject field of discourse.
40 The appellant has
submitted that for the very reason that the legislative scheme preserves
ultimate final rights [cf section 32]
this is an environment in which the
General Steel test should not be strictly applied. The submission is
that the underpinning for that test concerns preserving the rights of a party to
its day
in court for the purpose only of determination of its ultimate rights at
law.
41 I do not see the matter in this way. Notwithstanding the fast
track legislative scheme aimed at ensuring quick adjudication of
disputed
progress claims, the fact remains that the pre-conditions stipulated for by the
Act as requiring to be satisfied in order
to permit a claimant to procure a
judgment do require to be strictly complied with.
42 Where
established, the entitlement of a claimant to enter judgment under the Act is
likely to have very real consequences to the
respondent in any given case. A
respondent may be forced into liquidation by reason of the effect of the
judgment or otherwise dramatically
affected by the financial effect of the
immediate requirement to pay the judgment debt. This is not an occasion for
moving one jot
outside of the General Steel principles.
43 Returning to
the question of construction the following may be said:
· The
approach taken by the Master was to regard the respondent’s construction
as seeking "to imply a term to the effect
that no payment claim could be made
between the date of practical completion and the final payment claim under 42.7,
on the face
of the contract contradicts the express terms [of the
contract]”.
· The Master expressed the view that he would not
have thought that such an implied term was so obvious that it went without
saying and that the contract was quite effective without the implied term.
· In my view this is not the territory of implication. It is
rather the territory of contractual construction requiring to be
determined in
accordance with well-established principles in that regard.
· I do
accept that there is clearly something to be said in favour of the proposition
that the respondents construction does
not take into account the possibility
that prior to the expiration of the Defects Liability Period, the Superintendent
may direct
the Contractor to rectify any omission or defect in the work under
the Contract existing at the date of practical completion or which
becomes
apparent prior to the expiration of the Defects Liability Period [clause 37].
Further and as the Master noted, clause 40.1
permits the Superintendent to
direct the Contractor to execute variations within the general scope of the
Contract although it also
provides that the Contractor is not to be bound to
execute a variation directed after Practical Completion unless the variation is
in respect of rectification work referred to in clause
37.
· However, in my view the approach taken by the respondent
cannot be said to be so obviously untenable that it cannot possibly
succeed",
"manifestly groundless", "so manifestly faulty that it does not admit of
argument", one which "the court is satisfied cannot
succeed".
· The
respondent has thrown up an area where there is a real issue to be tried and for
that reason the summary judgment application
required is to be
dismissed.
44 The respondent having thrown up an area where there is a
real issue to be tried, the Master's approach having been shown to fail
on
General Steel bases to accept this as a triable issue, the summary judgment
application was appropriate to be dismissed on this basis. It has been
unnecessary in this regard to consider any particular aspect of the dates of the
instant progress claims [both
of which were served well after the date of
practical completion and many many months prior to the expiration of the Defects
Liability
Period].
45 Further in my view the appellant is incorrect in
its ‘outflanking’ submission that on this particular issue
the respondent is debarred by section 15 (4) (b) (ii) from raising a defence in
relation to this as a matter arising under the construction contract. The
holding is that section 15 only applies if subsections (1) (a) and (b) are
satisfied and that the claimant must affirmatively
establish what [within the
meaning of section 14 (4)] was the due date for the progress payment to which
the payment claim related.
The point reached on the
Appeal
46 The Court has now held that:
· grounds 2 and 3
of the Notice of Appeal require to be dismissed;
· there was a
triable issue on the construction matter which was put to the Master who failed
to uphold the respondent’s
argument.
47 It is unnecessary to go
further and to deal with any of the other matters which were the subject of
submissions on the Appeal and/or
notice of contention. In particular it is not
necessary to treat with the holding [at [40]] following the reasons given [at
[27]-[39]]
where the Master did uphold the respondents claim that there was a
triable issue in relation to another matter. Nor is it necessary
to deal with
the motion seeking leave to withdraw the concession made to the
Master.
48 The appellant did submit that this was a circumstance in which
the Court should proceed to finally determine the question of construction.
That course is not available on the appeal.
Short minutes of order
49 The parties are to bring in short minutes of order when costs may
be argued.
I certify that paragraphs 1-49
are a true copy
of the reasons
for judgment herein of
the Hon. Justice
Einstein
given on 29 March 2004
___________________
Susan
Piggott
Associate
29 March 2004
LAST
UPDATED: 07/04/2004
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2004/222.html