[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales |
Last Updated: 23 April 2004
NEW SOUTH WALES SUPREME COURT
CITATION: John Holland Pty Limited v
Cardno MBK (NSW) Pty Limited & Ors [2004] NSWSC 258
CURRENT
JURISDICTION: Equity Division
Technology and Construction List
FILE
NUMBER(S): 55002/04
HEARING DATE{S): 31/03/04
JUDGMENT DATE:
20/04/2004
PARTIES:
John Holland Pty Limited (Plaintiff)
Cardno
MBK (NSW) Pty Limited (First Defendant)
Graeme Robinson (Second
Defendant)
The Institute of Arbitrators and Mediators Australia (Third
Defendant)
JUDGMENT OF: Einstein J
LOWER COURT
JURISDICTION: Not Applicable
LOWER COURT FILE NUMBER(S): Not
Applicable
LOWER COURT JUDICIAL OFFICER: Not Applicable
COUNSEL:
Mr M Christie (Plaintiff)
Mr D Miller (First Defendant)
No appearance
for Second and Third Defendants
SOLICITORS:
Clayton Utz
(Plaintiff)
David Campbell-Williams Construction Lawyer
Bradfield Scott
(Sydney Agent) (First Defendant)
Philips Fox (submitting
appearance)
CATCHWORDS:
Challenge to determination of adjudicator
under the Building and Construction Industry Security of Payment Act
1999
Statutory scheme dictates that the adjudication response be relevantly
tied to the payment schedule [such that the adjudication response
cannot include
any reasons for withholding payment unless those reasons have already been
included in the payment schedule - Section 20 (2B)]
Whether adjudication
application should also be relevantly tied to the payment claim [such that the
adjudication application cannot
include reasons supporting the payment claim
unless those reasons had been included in the payment claim]
Scheme of
legislation
Adjudicator's powers
Adjudicator does not have the power to
consider materials supplied by a claimant in its adjudication application which
go outside
[ie fall outside the ambit or scope of] the materials which were
provided in the payment claim
ACTS CITED:
Building and Construction
Industry Security of Payment Act 1999
Supreme Court Act
DECISION:
Jurisdictional error and denial of natural justice shown to have
occurred.
JUDGMENT:
IN THE SUPREME COURT
OF
NEW SOUTH WALES
EQUITY DIVISION
TECHNOLOGY &
CONSTRUCTION LIST
Einstein J
Tuesday 20 April
2004
55002/04 John Holland Pty Limited v Cardno MBK (NSW) Pty
Limited & Ors
JUDGMENT
The
proceedings
1 These proceedings concern an adjudication application
under the Building and Construction Industry Security of Payment Act 1999
["the Act"].
Section 20 (2B) of the Act
2 The critical
issue which is raised is encapsulated in the following contention by the
plaintiff, John Holland Pty Ltd [“John
Holland” or “the
respondent”] which had entered into an agreement ["the Contract"] with the
first defendant, Cardno
MBK (NSW) Pty Ltd [“the applicant” or
“the defendant”] pursuant to which the latter was to provide design
services:
· An applicant is entitled to submit a progress claim and
a respondent is entitled to reply to the claim by providing a payment
schedule.
· The payment schedule must indicate why the scheduled amount is
less and the reasons for withholding payments.
· If an applicant
disputes the payment schedule it can apply for an adjudication.
· In that adjudication a respondent is expressly prevented from
including in the adjudication response any reasons for withholding
payment
unless those reasons have already been included in the payment schedule provided
to the claimant (s 20(2B) of the Act).
· Given that prohibition an
applicant could not, for reasons of procedural fairness or natural justice,
raise for the first time
in its adjudication application reasons which had not
been included in the payment schedule, as a respondent would not have been
able
to deal with those reasons in its payment schedule and would thus be unable to
respond to them in its adjudication response
due to the prohibition in section
20 (2B) of the Act.
3 There is no provision to be found in section 17
which deals with adjudication applications equivalent to section 20 [2B]: as for
example by providing that the claimant cannot include in the adjudication
application, any reasons for claiming payment
unless those reasons have already
been included in the payment claim. The defendant's stance before this Court has
been that the
plaintiff’s submissions seek to read such a provision into
Section 17, which is said to be an impermissible exercise in terms of statutory
construction.
4 Whilst logic and the authorities cited in this judgment
would tend to suggest that in order to achieve consistency in the four steps
[payment claim, payment schedule, adjudication application, adjudication
response]:
· the statutory scheme dictates that the adjudication
response be relevantly tied to the payment schedule [such that the adjudication
response cannot include any reasons for withholding payment unless those reasons
have already been included in the payment schedule-section
20
(2B)]
· the adjudication application should also be relevantly tied
to the payment claim [such that the adjudication application cannot
include
reasons supporting the payment claim unless those reasons had been included in
the payment claim]
the fact is that the Act does not expressly require
any form of reasons for the making of a payment claim to be included in
the payment claim.
5 This judgment treats with the legislative scheme
where in applying that scheme it becomes necessary to cope with these
difficulties.
6 As will appear from what follows, the devil will often
lie in the detail: what precisely in a given case, can be said to have been
"reasons not already [included] in the payment schedule"?
7 The broader
issues which arise are as follows:
· whether the adjudication
application made by the adjudicator contains submissions which were not duly
made in support of the
defendant's payment claim for the purposes of 17(3)(h)
and 22(2)(c) of the Act;
· whether the adjudicator relied on
submissions of the defendant in the adjudication application which were not duly
made in
support of the payment claim contrary to section 22(2)(c) of the
Act;
· whether the adjudicator committed a jurisdictional error or
otherwise committed an error justifying an order in the nature
of certiorari
quashing the determination;
· whether the plaintiff was denied
natural justice in the adjudication.
The stance taken by the
defendant
8 The defendant:
· denies that it made
submissions in the adjudication application on new claims which were not raised
in the payment claim;
· asserts that the matters alleged to be new
matters in the defendant’s adjudication submissions were in fact claims
included
in the payment claim and/or were further submissions made in response
to the plaintiff’s payment schedule and says that no
claims were made in
the adjudication submission that had not been incorporated in the payment
claim;
· in the alternative, asserts that it was entitled to include
in its adjudication application any such further submissions relevant
to the
adjudication application as the first defendant chooses to include in accordance
with section 17(3)(h) of the Act.
The relevant provisions of the
Act
9 The Act includes:
· Section 13 which relevantly
provides:
"(1) A person referred to in section 8(1) who is or who claims
to be entitled to a progress payment (the claimant) may serve a payment
claim on
the person who, under the construction contract concerned, is or may be liable
to make the payment.
(2) A payment claim:
(a) must identify the
construction work (or related goods and services) to which the progress payment
relates; and
(b) must indicate the amount of the progress payment that
the claimant claims to be due (the claimed amount), and
(c) must state
that it is made under this Act.
(3) The claimed amount may include any
amount:
(a) that the respondent is liable to pay the claimant under
section 27(2A), or
(b) that is held under the construction contract by
the respondent and that the claimant claims is due for
release."
· Section 14 which relevantly provides:
"(1) A
person on whom a payment claim is served (the respondent) may reply to the claim
by providing a payment schedule to the claimant.
(2) A payment
schedule:
(a) must identify the payment claim to which it relates,
and
(b) must indicate the amount of the payment (if any) that the
respondent proposes to make (the scheduled amount).
(3) If the scheduled
amount is less than the claimed amount, the schedule must indicate why the
scheduled amount is less and (if it
is less because the respondent is
withholding payment for any reason) the respondent's reasons for withholding
payment."
· Section 17 which relevantly provides:
"(1) A
claimant may apply for adjudication of a payment claim (an adjudication
application) if:
(a) the respondent provides a payment schedule under
Division 1 but:
(i) the scheduled amount indicated in the payment
schedule is less than the claimed amount indicated in the payment
claim..."
· Section 20 which relevantly
provides:
"(1) Subject to subsection (2A), the respondent may lodge with
the adjudicator a response to the claimant's adjudication application
(the
adjudication response) at any time within:
(a) 5 business days after
receiving a copy of the application, or:
(b) 2 business days after
receiving notice of an adjudicator's acceptance of the
application,
whichever time expires later.
(2) The adjudication
response:
(a) must be in writing, and
(b) must identify the
adjudication application to which it relates, and
(c) may contain such
submissions relevant to the response as the respondent chooses to
include.
(2A) The respondent may lodge an adjudication response only if
the respondent has provided a payment schedule to the claimant within
the time
specified in section 14(4) or 17(2)(b).
(2B) The respondent cannot
include in the adjudication response any reasons for withholding payment unless
those reasons have already
been included in the payment schedule provided to the
claimant."
· Section 22 which relevantly
provides:
"(1) ...
(2) In determining an adjudication application,
the adjudicator is to consider the following matters only:
(a) the
provisions of this Act,
(b) the provisions of the construction contract
from which the application arose,
(c) the payment claim to which the
application relates, together with all submissions (including relevant
documentation) that have
been duly made by the claimant in support of the
claim,
(d) the payment schedule (if any) to which the application
relates, together with all submissions (including relevant documentation)
that
have been duly made by the respondent in support of the schedule,
(e) the
results of any inspection carried out by the adjudicator of any matter to which
the claim relates."
The principles
Generally –
relief for jurisdictional error
10 It is convenient before turning to
the particular facts which are before the court, to briefly examine the current
position in
terms of principle. The matter was the subject of a recent summary
by Master Macready in Transgrid v Siemens Ltd [2004] NSWSC 87 (in turn
adopted by Barrett J in Quasar Constructions v Demtech Pty Ltd [2004] NSWSC 116 (at [4]):
“The parties are not at issue on the question
of whether or not the decision of the adjudicator is reviewable for
jurisdictional
error. It is worth noting the general principles which do apply
in this regard because, as has been made plain in the authorities,
it is only
where there is jurisdictional error rather than an error of law on the face of
the record that there might be a right
to review.
The defendant referred
to Craig v The State of South Australia [1995] HCA 58; (1995) 184 CLR 163 at 178,
where the High Court has considered the following passage from Lord Reid’s
speech in Anisminic Limited v Foreign Compensation Commission
[1968] UKHL 6; [1969] 2 AC 147 at 171, to be applicable to tribunals but not inferior
courts:
‘there are many cases where, although the tribunal had
jurisdiction to enter on the inquiry, it has done or failed to do something
in
the course of the inquiry which is of such a nature that its decision is a
nullity. It may have given its decision in bad faith.
It may have made a
decision which it had no power to make. It may have failed in the course of the
inquiry to comply with the requirements
of natural justice. It may in perfect
good faith have misconstrued the provisions giving it the power to act so that
it failed to
deal with something which it was required to take into account. Or
it may have based its decision on some matter which, under the
provisions
setting it up, it had no right to take into account. I do not intend this list
to be exhaustive. But if it decides a question
remitted to it for decision
without committing any of these errors it is as much entitled to decide that
question wrongly as it is
to decide it rightly.’
There have been a
series of cases in this jurisdiction dealing with the principles as they are
applied to an adjudicator under the
Act. The matter was first considered in some
detail in Musico & Ors v Davenport & Ors [2003] NSWSC 977.
In that case McDougall J held that a determination of an adjudicator was open to
judicial review. In Brodyn Pty Limited t/as Time Cost and Quality (ACN 001
998 830) v Philip Davenport & Ors [2003] NSWSC 1019, Einstein J
also came to the same conclusion. At paragraph 19 he summarised his conclusions
in these terms:
‘This then provides the essential reason as to why
upon the proper construction of the Act the following conclusions may be
drawn:
· that apart from any privative effect the Act might have,
relief under section 69 of the Supreme Court Act would in principle lie
against an adjudicator appointed under section 19 of the Act;
·
that the determination of an adjudicator made pursuant to section 22 of the Act
is in principle susceptible to judicial review;
· that judicial
review of adjudication determinations made under the Act may be undertaken on
jurisdictional grounds (at least
in the sense that involves refusing to
exercise, or acting in excess of, jurisdiction);
· that judicial
review of adjudication determinations made under the Act may be undertaken for
denial of natural justice or
for fraud; and
· that relief in the
nature of certiorari will not lie to quash the determination of an adjudicator
on the basis of non-jurisdictional
error of law on the face of the record
[because the legislative scheme set out in section 25 (4) is inconsistent with
the availability of this ground of review].’
In Abacus v
Davenport & Ors [2003] NSWSC 1027, McDougall J again had to
consider the question. His Honour referred to his earlier judgment in
Musico and made the following comments:
‘I dealt
with these issues in my judgment in Musico at paras [21] to [60]. I
concluded that:
1. Relief in the nature of prerogative relief would in
principle lie against the determination of an adjudicator under the
Act;
2. Relief would lie for jurisdictional error (including refusal to
exercise jurisdiction, acting in excess of jurisdiction and what
I described as
jurisdictional error of law on the face of the record) and denial of natural
justice (on the basis that the requirements
of natural justice had to take into
account, not only the circumstances of the particular case, but also the
legislative scheme);
and
3. Relief would not lie in the case of
non-jurisdictional error of law on the face of the record.
I should make
it quite clear that, in Musico, I was not intending to express in a
comprehensive way all the grounds on which review might be available. What I
said was, of course,
said in the context of, and in the course of, deciding the
particular issues propounded for decision in that case. There may be
circumstances
beyond those that I described that might ground an application for
relief in the nature of prerogative relief. However, consideration
of that
question should wait until it is raised on the facts of a particular
case.
I adhere to the views that I expressed in Musico. I note
that the approach that I took in that case has been followed by Einstein J in
Brodyn Pty Ltd v Davenport & Ors [2003] NSW SC 1019.
Accordingly, the remaining issue for decision in this case is whether Abacus
has demonstrated jurisdictional error, including jurisdictional
error of law on
the face of the record (there being no claim of denial of natural
justice).’
The matter was again dealt with by Palmer J in
Multiplex Constructions Pty Limited v Luikens & Ors [2003] NSWSC 1140, His Honour came to the same conclusion and he summarised the type of
jurisdictional error which would lead to the setting aside
of a decision at
paragraph 34 in these terms:
‘It seems clear enough that relief
will be granted where the adjudicator's determination is the result of
jurisdictional error:
see Musico at paragraphs 42ff. Jurisdictional error
will arise where, for example, the adjudicator's decision:
- was given
in bad faith or was procured by fraud;
- was one which the adjudicator
had no power under the Act to make;
- was made without complying with
the limited requirements of natural justice provided by s.17(5), s.20(1), (2)
and (3), s.21(1), s.21(4)(a) and s.18(4) of the Act; and see paragraph 15
above;
- did not deal with the question remitted for
adjudication;
- determined a question not remitted for
adjudication;
- did not take into account something which the Act
required to be taken into account; or
- was based upon something which
the Act prohibited from being taken into account.
See generally Anisminic
Ltd v Foreign Compensation Commission [1968] UKHL 6; [1969] 2 AC 147, at
171.’
His Honour also carefully considered the question of whether
or not non-jurisdictional error on the face of the record could lead
to the
setting aside of a determination. He concluded, in agreement with McDougall J
and Einstein J, that an adjudicator’s
determination under s 22 of the Act
may not be reviewed under s 69 (1)(a) of the Supreme Court Act for
non-jurisdictional error of law on the face of the record.
The defendant
emphasised in submissions that the onus of establishing jurisdictional error
clearly lies upon the prosecutor. Reference
was made to Hill v King
(1993) 31 NSWLR 654 at 661, where the Court of Appeal held:
‘On an application for prerogative relief the prosecutor bears the
burden of establishing clearly the facts which show an absence or excess
of jurisdiction: see R v Alley; Ex parte New South Wales Plumbers and Gas
Fitters Employees’ Union [1981] HCA 61; (1981) 153 CLR 376 at 382, 392-393,
397.’”
The principles more particularly going to issue
definition
11 Standing back from the particular wording of the
sections the propositions thus far which are supported by final stance
authorities
are as follows:
· the only issues which the respondent
is entitled to agitate in the adjudication response are those issues squarely
dealing
with reasons for withholding payment which have been indicated in the
payment schedule in accordance with section 14 (3) [Multiplex, Palmer J
at paragraph 67];
· the purpose of s.13(1) and (2), s.14(1), (2) and
(3), and s.20(2B) is to require the parties to define as early as possible what
are the issues in dispute between them [Multiplex, Palmer J supra];
· the issues so defined are the only issues which the
parties are entitled to agitate in their dispute and they are the only issues
which the adjudicator is entitled
to determine under s.22. [Multiplex,
Palmer J supra];
· where an adjudicator determines an adjudication
application upon a basis not notified by either party to the other and not
contended for and not notified by the adjudicator to the parties, the
requirements of natural justice are not satisfied [Musico, McDougall J at
108].
12 To be more precise Palmer J in Multiplex expressed the
principle as follows:
“67 The evident purpose of s.13(1) and (2),
s.14(1), (2) and (3), and s.20(2B) is to require the parties to define clearly,
expressly and as early as possible what are the issues in dispute between them;
the issues so defined are the only issues which the parties are entitled to
agitate in their dispute and they are the only issues
which the adjudicator is
entitled to determine under s.22. It would be entirely inimical to the quick and
efficient adjudication of disputes which the scheme of the Act envisages if a
respondent
were able to reject a payment claim, serve a payment schedule which
said nothing except that the claim was rejected, and then “ambush”
the claimant by disclosing for the first time in its adjudication response that
the reasons for the rejection were founded upon a
certain construction of the
contractual terms or upon a variety of calculations, valuations and assessments
said to be made in accordance
with the contractual terms but which the claimant
has had no prior opportunity of checking or disputing. In my opinion, the
express
words of s.14(3) and s.20(2B) are designed to prevent this from
happening.
68 Section 14(3) requires that if the respondent to a
payment claim has “any reason” for
“withholding payment”, it must indicate that reason in the
payment schedule. To construe the phrase “withholding
payment” as meaning “withholding payment only by reason of a
set-off or cross claim” is to put a gloss on the words which their
plain
meaning cannot justify. The phrase, in the context of the subsection as a whole,
simply means “withholding payment of
all or any part of the claimed amount
in the payment claim”. If the respondent has any reason whatsoever for
withholding payment
of all or any part of the payment claim, s.14(3) requires
that that reason be indicated in the payment schedule and s.20(2B) prevents the
respondent from relying in its adjudication response upon any reason not
indicated in the payment schedule. Correspondingly,
s.22(d) requires the
adjudicator to have regard only to those submissions which have been
“duly made” by the respondent in support of the payment
schedule, that is, made in support of a reason for withholding payment which has
been
indicated in the payment schedule in accordance with
s.14(3).”
13 McDougall J in Musico put the matter as
follows:
“107 ... It may readily be accepted that the Act provides
for a somewhat rough and ready way of assessing a builder’s
entitlement to
progress claims. It may also be accepted that the procedure is intended not only
to be swift, but also to be carried
out with the minimum amount of formality and
expense. Nonetheless, what an adjudicator is required to do is to decide the
dispute
between the parties. Under the scheme of the Act, that dispute is
advanced by the parties through their adjudication application
and adjudication
response (which, no doubt, will usually incorporate the antecedent payment claim
and payment schedule). If an adjudicator
is minded to come to a particular
determination on a particular ground for which neither party has contended then,
in my opinion,
the requirements of natural justice require the adjudicator to
give the parties notice of that intention so that they may put submissions
on
it. In my opinion, this is a purpose intended to be served by s 21(4) of the Act
(although the functions of s 21(4) may not be limited to this).
108 It
follows, in my opinion, that where an adjudicator determines an adjudication
application upon a basis that neither party has
notified to the other or
contended for, and that the adjudicator has not notified to the parties, there
is a breach of the fundamental
requirement of natural justice that a party to a
dispute have “a reasonable opportunity of learning what is alleged against
him and of putting forward his own case in answer to it”. (See Lord
Diplock in O’Reilly at 279)”
The content of payment
claims
14 Some attention has been given in the authorities to the
content of payment claims, usually at the same time as dealing with the
content of the payment schedule. Hence McDougall J observed in Multiplex
Constructions v Luikens, op cit, at [76]:
“A payment claim and
a payment schedule are, in many cases, given and received by parties who are
experienced in the building
industry and are familiar with the particular
building contract, the history of construction of the project and the broad
issues
which have produced the dispute as to the claimant’s payment claim.
A payment claim and a payment schedule must be produced
quickly; much that is
contained therein in an abbreviated form which would be meaningless to the
uninformed reader will be understood
readily by the parties themselves. A
payment claim and a payment schedule should not, therefore, be required to be as
precise and
as particularised as a pleading in the Supreme Court. Nevertheless,
precision and particularity must be required to a degree reasonably
sufficient
to apprise the parties of the real issues in dispute.”
Proper
approach to statutory construction
15 It is trite to note that the
Court approaches the question of statutory construction by looking at the words
of the statute which
are to be interpreted in accordance with their ordinary
meaning and that the endeavour is a purposive one whereby the Court pays
close
attention to the particular legislative scheme in place. Resort may be had to
the second reading speech although this will
not of itself be determinative: cf
Brambles Australia Ltd v Davenport [2004] NSWSC 120 at
16.
16 Further, as put by McHugh J in Newcastle City Council v GIO
General Ltd [1997] HCA 53; [1997] 191 CLR 85 [at 109]:
“In applying a
purposive construction, ”the function of the court remains one of
construction and not legislation”.
When the express words of a
legislative provision are reasonably capable of only one construction and
neither the purpose of the
provision nor any other provision in the legislation
throws doubt on that construction, a court cannot ignore it and substitute a
different construction because it furthers the objects of the
legislation.”
17 A difficulty which arises concerns the fact that
section 13 of the Act does not, at least expressly, require the payment claim to
include reasons for the claimed entitlement to a particular
progress payment.
The sole requirements provided for in subsection 2 are that a payment
claim:
(a) must identify the construction work (or related goods and
services) to which the progress payment relates;
(b) must indicate the
amount of the progress payment that the claimant claims to be due (the claimed
amount);
(c) must state that it is made under the Act.
18 As will
be seen from what follows below, my own view is that one commences with
identifying what the statutory scheme puts forward
as constituting a payment
claim. A payment claim clearly is a claim to an entitlement to be paid a
progress payment. The whole notion of a payment claim, it seems
to me, requires
as an essential condition thereof that the document by which the payment
claim is put forward, include, whether in shorthand or in longhand and
whether by one means or another, sufficient information to identify what the
claim is.
19 There is a powerful argument that this effectively means
that the statutory regime requires that the claim to be valid must be
comprehensible by the respondent. The argument is supported by reference to the
whole of the statutory scheme and most particularly
by reference to the
following considerations:
· section 22(2)(c) clearly suggests (as
does the whole of the environment being dealt with) [cf McDougall J in
Multiplex supra at 76] that there will have been relevant documentation
provided by the claimant in support of its claim;
· the requirement
stipulated for in section 14 (3) for the respondent to indicate why the
scheduled amount is less than the claimed amount [and if it is less because the
respondent is withholding payment for any reason,
then to give the respondents
reasons for withholding payment], can only be justified by the proposition that
the payment claim will
identify in a fashion comprehensible to a respondent,
just what the claim is;
· the statutory scheme is for an application
[called an adjudication application]. The application must “relate
to the payment claim" [section 22(2)(c)]. The application is for the
adjudication of no more and no less than the payment claim
as
contradicted/traversed by the payment schedule.
20 However, as
earlier observed, there are no words within section 13 (1) which require the
claimant to do otherwise than:
· to identify the subject
construction work to which the progress payment relates [subsection (1)
(a)];
· to indicate the amount of the progress payment that the
claimant claims to be due [subsection (1) (b)];
· to state that
the claim is made under the Act. [subsection (1) (c)].
21 Ultimately it
seems to me that the accepted principles of statutory construction simply do not
permit the Court to take the further
step of holding that in order to be valid,
a payment claim must be comprehensible by the respondent in terms of its
supporting materials
[cf especially the abovementioned citation from McHugh J in
Newcastle City Council v GIO General].
Approaching the question
in terms of section 20 (2B)
22 The primary touchstone it seems to me,
is section 20 (2B). Whilst a claimant which provides the most minimal amount of
information in its payment claim may even so, be seen to technically
comply with
section 13, such a claimant will expose itself to an abortive adjudication
determination if it be that:
· the respondent is simply unable to
discern from the content of the payment claim, sufficient detail of that claim
to be in
a position to meaningfully verify or reject the claim: hence not then
being in a position to do otherwise than to reject the whole
of the claim on
the basis of its inability to verify any part of the claim;
· the
claimant then elects to include the missing detail in the adjudication
application with the inexorable consequence that
the respondent is barred by
section 20 (2B) from dealing with that detail/matter in its adjudication
response;
· the adjudicator relies in determining the adjudication
application upon the detail supportive of the payment claim which first
emerged
as part of the adjudication application
23 For those reasons whilst it is
not permissible to construe section 13 as providing that in order to be a
valid payment claim, such a claim must do more than satisfy the
requirements stipulated for by subsection 2 (a), (b) and (c), the consequence to
a claimant which does not include sufficient detail of that claim to be in a
position to permit
the respondent to meaningfully verify or reject the claim,
may indeed be to abort any determination.
Approaching the question in
terms of the adjudicator's power
24 The matter may also be analysed
by reference to the power of an adjudicator. An adjudicator does not have the
power to consider
materials supplied by a claimant in its adjudication
application which go outside [ie fall outside the ambit or scope of]
the materials which were provided in the payment claim, for the reason that
the adjudicator only has power to make a determination
based
upon:
· The payment claim [together with the claimant's submissions
(and relevant documentation) in the adjudication application, which
submissions
have to have been "duly made by the claimant in support of the
(payment) claim": see section 22 (2) (c)].
· The payment
schedule (if any) [together with the respondents submissions (and relevant
documentation) in the adjudication response,
which submissions have to have been
“duly made by the respondent in support of the (payment)
schedule”: see section 22 (2) (d)].
· The provisions of
the Act: see section 22 (2) (a).
· The provisions of the
construction contract from which the application arose: see section 22 (2)
(b).
· The results of any inspection carried out by the adjudicator
of any matter to which the claim relates: see section 22 (2) (e).
25 The
emphasis upon submissions "duly made" makes clear that the scheme really
addresses the issues which have been thrown up once the payment claim has been
served and the
responsive payment schedule then served. The steps which follow
generally concern the materials to be exchanged and most particularly
furnished
to the adjudicator. The adjudication application will relate to a
particular payment claim and payment schedule [section 17 (3) (f)]. The central
significance of the entitlement of the applicant
to include submissions as part
of its adjudication application is because those submissions have to be
supportive of the payment
claim. Those submissions cannot constitute a
payment claim or part of it. The central significance of the entitlement of the
respondent to include submissions as part of its
adjudication response is
because those submissions have to be supportive of the payment schedule. Those
submissions cannot constitute a payment schedule or part of
it.
Section 21 (4) - additional submissions
26 Whether or
not any of these problems may be addressed by the adjudicator requesting further
written submissions from either party
may become the subject of curial
examination on another occasion. However it would seem unlikely that the
legislature would have
intended the provisions of section 21 (4) (a) and (b) to
permit a radical departure from the statutory scheme described above. Rather it
seems likely that these sub-sections
are to be read as permitting no more than
additional submissions which clarify earlier submissions: those earlier
submissions being constrained in the manner above described.
Turning
from the general to the particular
27 If one turns from the general
to the particular, the circumstances in which a claimant for the first time
treats in the adjudication
application with parameters which were not
telegraphed in the payment claim may occur across a number of different
situations as
for example:
· where the claimant for the first time
advances a new contractual basis for a payment claim in the adjudication
application;
· where the claimant for the first time seeks to deploy
in the adjudication application, supporting documentation of one type
or
another.
28 These situations may have differing results.
New
contractual basis
29 The first situation seems to me to generally be
quite plain. The abortive adjudication determination likely to result from the
advancing [, within the adjudication application] of a new contractual basis for
a payment claim, has already been explained.
Supporting
documentation
30 The deploying for the first time in the adjudication
application, of supporting documentation will require careful attention and
becomes a matter of degree and detail. However in the main I do not see that a
respondent which, by reason of insufficient information
supplied with the
payment claim, is unable to verify that claim, and says as much in the payment
schedule [only later to receive
as part of the adjudication application, the
supporting documentation which should have been earlier supplied in order to
permit
a meaningful payment schedule response], will be otherwise than barred by
section 20 (2B) from including in its adjudication response reasons for
withholding payment arising by reference to the later supporting documentation.
It could not be said that those reasons were already included in the
payment schedule provided to the claimant. A complaint about inability to
verify a claim because of insufficient information
is not synonymous with
reasons for dealing with a properly supported claim.
Approaching the
facts
31 As earlier noted the application of this analysis throws up
particular difficulties: the devil lies in the detail. Hence as one
approaches
the particular matters presently arising for determination it is necessary in
each case to ask for what may be properly
described as "reasons not already
[included] in the payment schedule"?
The facts
32 The
relevant facts fall into small compass although the volume of relevant materials
[six lever arch folders having accompanied
the adjudication application], may be
considered somewhat daunting:
· on or about 3 July 2003 the
plaintiff entered into the Contract with the first defendant pursuant to which
the defendant was
to provide design services for an amount of $390,000 plus
GST;
· the Contract is comprised in a written document titled
Parramatta Rail Link Project GC-3 Works Contract - Civil Works Boundary
Street
to Rail Enclosure Structure O'Brien Street - Agreement for Engagement of
Consultant - Cardno MBK (NSW) Pty Ltd - July 2003;
· on 10 November
2003 the defendant issued a purported payment claim under section 13 of the Act
seeking payment of an amount of $1,281,703 plus GST;
· on 24
November 2003 the plaintiff responded to the payment claim by issuing a payment
schedule under section 14 of the Act disputing that any amount was payable to
the defendant;
· on 9 December 2003 the defendant served an
adjudication application dated 8 December 2003 under section 17 of the Act on
the plaintiff;
· on 11 December 2003 the third defendant issued a
letter nominating the second defendant as the adjudicator;
· on 16
December 2003 the plaintiff served its adjudication response dated 16 December
2003 under section 20 of the Act on the first and second
defendants;
· the plaintiff informed the second defendant in the
adjudication response that the plaintiff was precluded by section 20(2B) of the
Act from including reasons for withholding payment which were not included in
the payment schedule and that it would be a
jurisdictional error if the second
defendant relied on the new matters raised by the first defendant in the
adjudication application;
· following receipt of the adjudication
application and the adjudication response, the second defendant did not request
further
written submissions from the plaintiff in relation to the matter
particularised in paragraph 8 above, as he was entitled to do pursuant
to
section 21(4) of the Act;
· the second defendant made his
adjudication determination on 2 January 2004 and amended it on 2 January 2004
and 9 January 2004.
Challenges numbers 1, 2, and 4 - ultimately
pressed at the hearing. [challenge 3 was abandoned]
33 It is
convenient to commence with challenge 4 as it seems to me to be the clearest
case in which to consider and apply the above
described statutory construction
analysis.
Detail of Challenge 4
34 This challenge is
addressed by the plaintiff as
follows:
Determination
· the adjudicator determined
that an amount of $12,280.00 was payable to Cardno MBK in relation to variation
claim no. 6 which
related to the investigation of requirements for drainage and
downstream overland flow [see PX 284];
Challenges as jurisdictional
error
· John Holland challenges this award on the basis that it
was a jurisdictional error for the adjudicator to rely on matters which
were the
subject of the adjudication application, which had not previously been raised in
Cardno MBK's payment claim;
Challenge as denial of natural
justice
· in the alternative, John Holland submits that it was
denied natural justice by not having an opportunity to adequately respond
to
this claim in its Payment Schedule and therefore was not able to present an
adequate defence to this claim in its adjudication
response, being expressly
barred from doing so pursuant to s.20(2B) of the Act.
Payment claim is
a variation claim
· Cardno MBK's payment claim gave
notification, for the first time, of a claim for a variation pursuant to clause
7 of the Contract
in respect of investigations for the requirement of drainage
and downstream overland flow. It was stated by Cardno MBK that John
Holland had
directed Cardno MBK to carry out an investigation and an assessment in relation
to this issue. Cardno MBK then alleged
that this task constituted a variation
[see PX 62 ];
Payment schedule rejection
· in
response, John Holland rejected this claim in its Payment Schedule [see PX 122]
on the basis that this work was already
included in the scope of works under the
Contract. John Holland referred to a number of provisions in the Contract in
relation to
this position;
Adjudication application invokes clause
3.14
· in the adjudication application, for the first time,
Cardno MBK asserted that the basis of its claim was clause 3.14 of the
Contract
which is to the effect that Cardno MBK would be entitled to an additional fee
where a correction or clarification arose
from an act, default or omission of
John Holland and/or its principal. In regards to the adjudication application
John Holland refers
to pages 184-189 of JP Exhibits;
Adjudication
response rejection
· John Holland rejected this claim in its
adjudication response (see page 270.104-270.106 of JP Exhibits) on the basis
that:
- the works were within the scope of Cardno MBK's agreed works
under the Contract; and
- that John Holland had not issued any direction
for a variation.
Determination
· ultimately, the
adjudicator awarded Cardno MBK an amount of $12,280.00 in respect of this
alleged variation. The adjudicator
determined that:
"...this was a
design modification as a result of further information and accordingly was a
variation to the CMBK scope of work under
clause 3.14 and the costs can be
claimed under clause 7 of the Agreement" (see page 284 of JP
Exhibits).
· the adjudicator determined this claim by reference to
and reliance upon clause 3.14 of the Contract which was a claim which
had not
been put by Cardno MBK in its payment claim. Pursuant to s20(2B) of the Act
John Holland was denied any opportunity to advance a defence based on clause
3.15 of the Contract (see page 15 of JP Exhibits)
which provides that only John
Holland is entitled to ask for variations, rather than other parties, and that
Cardno MBK was not to
act upon any requests of others unless it received written
approval from John Holland.
35 The submission is that the adjudicator
could have exercised his discretion pursuant to section 21(5) to invite John
Holland to make further submissions with respect to the adjudication
application. This could have cured the denial
of natural justice, but it did
not occur.
Dealing with challenge 4
36 Challenge 4 quite
clearly amounts to a circumstance in which the claimant for the first time in
its adjudication claim, changed
its ground by putting an alternative contractual
basis. There can be no doubt but that it had initially in its payment claim
squarely
raised this as a variation claim. Such a claim was regulated by and
only by the variations clause 7 [PX 22]. That clause was in
the following
terms:
“7.1 VARIATIONS PERMITTED
John Holland may from time
to time and at any time prior to completion of the Project give written
Directions to the Consultant to
do all or any one or more of the following
things:
(i) vary the nature and extent of the
Services;
(ii) increase, change, decrease or omit any part of the
Services;
(iii) carry out additional Services;
(iv) deploy
additional resources to complete the Services or any part thereof, before the
due date.
The Consultant shall be bound to comply with such Directions
and be bound by the same terms and conditions, so far as applicable,
as if the
Directions were part of the Consultant’s Services originally included in
the Agreement.
No Direction shall vitiate the Agreement, but the monies
otherwise payable under the Agreement shall be increased or decreased having
regard to the value (if any) of the Direction, determined in accordance with
clause 7.2.
7.2 VALUATION OF VARIATIONS
Wherever appropriate a
Direction for a variation shall be valued on the basis of the proportion that
the variation represents in relation
to the original Services to be provided by
the Consultant expressed as percentage and applied to the Consultancy Fee and
adjusted
upwards or downwards, as necessary, to take into account any economies
or diseconomies of scale and any other relevant factors.
If the above
method of valuation is not appropriate, John Holland may request the Consultant
to submit an estimate of its fees for
the variation as a basis for negotiation
and agreement on the valuation of the variation or, alternatively, the parties
may agree
to value the variation on a time, costs and expenses basis.
In
appropriate circumstances, a variation may be valued on the basis of any
combination of the above mentioned methods.”
37 The respondent
squarely addressed this basis in its payment schedule, its proposition being
that the work for which the claim was
made had already been included in the
scope of works.
38 What then occurred was that the adjudication
application now raised an alternative provided for by clause 3.14 which was in
the
following terms:
“3.14 CORRECTIONS
Notwithstanding any
reviews, approvals or Directions undertaken or given by John Holland or the
Principal with respect to documents
prepared under this Agreement, any error,
ambiguity or deficiency which subsequently becomes apparent and is referred to
the Consultant
for correction or clarification, shall be corrected or clarified
by the Consultant to the satisfaction of John Holland or the Principal
in a
timely manner.
The Consultant shall only be entitled to an additional
fee where the correction or clarification arises from an act, default or
omission
of John Holland and/or the Principal or parties authorised by
either.
The Consultant shall provide all copies, documentation,
assistance, explanations, liaison and the like as may be necessary to enable
such review or checking to proceed expeditiously.
[I interpolate to note
the terms of Clause 3.15:
3.15 LIAISON WITH REVIEWERS AND
CHECKERS
The work of the Consultant may be subject to review or checking
by John Holland and/or the Principal or parties authorised by either.
The
Consultant shall provide all copies, documentation, assistance, explanations,
liaison and the like as may be reasonably necessary
to enable such review or
checking to proceed expeditiously.
If the Consultant receives any
comments or the like from other than John Holland, he shall promptly inform John
Holland in writing
with particulars of the comments and their standing,
potential impact and any other relevant matters. Only John Holland is entitled
to ask for alterations, alternatives or the like and the Consultant shall not
agree to or act upon requests of others without the
written approval of John
Holland. “]
39 Ultimately the adjudication determination accepted
the alternative basis relying upon clause 3.14.
40 In those circumstances
the respondent was clearly prevented by section 20 (2B) from including in its
adjudication response a reason for withholding payment, which reason had not
already been included in
the payment schedule. But it needed in order to so
respond, to treat with clause 3.14 and to invoke in particular the last sentence
of clause 3.15. It could not do so. It did not do so. The Adjudicator
nonetheless expressly determined the matter by upholding
by the clause 3.14
proposition which had first come forward in the adjudication
application.
41 The adjudication determination miscarried in this regard.
This was jurisdictional error. It was also a denial of natural justice.
The
adjudicator took into account a new contractual basis for a claim which basis
had not been put forward as part of the payment
claim. The respondent was not
invited to address submission in relation to the new contractual
basis.
Detail of challenge 1 pressed by the plaintiff – Progress
Claim 39
42 This challenge, described as a timesheet related
challenge, is addressed by the plaintiff as
follows:
Determination
· the adjudicator determined
that an amount of $29,767.13 was payable to Cardno MBK in relation to progress
claim no. 39 which
was a claim for the amount of $43,700.00;
Challenge
as jurisdictional/error
· John Holland challenges this award on
the basis that it was either a jurisdictional error for the adjudicator to rely
on the
matters the subject of the adjudication application, which had not
previously been raised in Cardno MBK's payment claim;
Challenge as
denial of natural justice
· in the alternative, John Holland
submits that it was denied natural justice by not having an opportunity to
respond to this
claim in its Payment Schedule and therefore was not able to
present a defence to this claim in its adjudication response, being expressly
barred from doing so pursuant to s.20(2B) of the Act;
Shortcomings in
payment claim
· Cardno MBK's payment claim included a claim for
$43,700.00 in respect of consulting engineering services alleged to have been
performed in the period 9 August 2003 to 31 October 2003 [PX 46]. There was no
reference to any time sheets supporting this claim
nor was there any basis put
forward as to how the claim was being made or pursuant to which clause of the
Contract the claim was
being made;
Payment schedule
rejection
· John Holland rejected this claim in its Payment
Schedule [see PX 129], (claim No. 39) on the basis, inter alia, that no time
sheets approved by John Holland had been submitted by Cardno
MBK;
· in this regard John Holland relied upon item 1.3 of Annexure
C of the Contract which provides that:
"The rates quoted shall be for
additional work as directed by John Holland. Invoices shall be itemised as per
category of consult
staff, at the quoted hourly rates and supported by Time
Sheets approved by John Holland Site personnel." [emphasis added - see PX
35])
Adjudication application draws in time sheets and construction
stage services
· presumably in answer to John Holland's
complaint that no timesheets had been submitted in support of its payment claim,
Cardno
MBK's adjudication application, for the first time, included various time
sheets which were said to support the claim of $43,700.00
[see PX 162 to
169];
· Cardno MBK's adjudication application, also for the first
time, set out the contractual basis for the claim. In particular,
Cardno MBK
advised [at PX 162] that its claim was being made pursuant to clause 3 of
Annexure B of the Contract, which states as
follows:
"If requested by
John Holland during the Construction Stage, the Consultant shall undertake the
following tasks. The Consultant shall
be paid for the Construction Stage
services at the rates indicated in Annexure C, items 1.3 and 1.4" (see page 31
of JP Exhibits).
· Item 1.3 of Annexure C of the Contract set out
the relevant hourly rates for different categories of personnel from Cardno
MBK.
This term also sets out a requirement for the provision of "Time Sheets approved
by John Holland Site personnel". None of the
time sheets, belatedly submitted
by Cardno MBK, had been approved by John Holland, but John Holland was deprived
of the opportunity
of validly making such submission to the
adjudicator;
Adjudication response rejection
· John
Holland rejected this claim in its adjudication response (see page 270.147 of JP
Exhibits) on the basis that Cardno MBK
had not provided any substantiation of
this claim prior to the adjudication application. In the absence of any time
sheets with
the payment claim John Holland was unable to respond to this claim
in the adjudication;
· all invoices for construction stage services
were required to be accompanied by approved time sheets. Cardno MBK failed to
provide any time sheets prior to the adjudication application. This was
entirely new material put forward in the adjudication
application;
Determination
· the adjudicator
determined that an amount of $29,767.13 was payable to Cardno MBK in respect of
this claim (see page 286 of
JP Exhibits). The adjudicator noted that the time
sheets supporting the claim may not have been approved by John Holland, in
accordance
with item 1.3 of Annexure C of the Contract. However, the
adjudicator found that he had inspected the works and that the time sheets
generally supported the labour hours claimed. Thus, the adjudicator determined
this issue on the basis of time sheets which had
never formed any part of the
payment claim.
43 The burden of the plaintiff’s submission is that
in these circumstances:
(a) John Holland consequently did not mount any
defence with respect to these matters in its payment schedule (pursuant to
s.14).
(b) The matters in (a) were raised by Cardno MBK for the first
time in its adjudication application.
(c) John Holland was confined, in
preparing its adjudication response, to matters included by it in its payment
schedule: s.20(2B) of the Act.
(d) Even if the course adopted by Cardno
MBK (in (c) above) did come within the scope of s.17(3)(f) , the effect of the
above course has been to deny John Holland natural justice.
(e) The
adjudicator could have exercised his discretion pursuant to section 21(5) to
invite John Holland to make further submissions with respect to the adjudication
application. This could have cured the denial
of natural justice, but it did
not occur.
44 Hence John Holland submits that it has been denied natural
justice by not being able to respond to this claim adequately.
Dealing
with challenge 1
45 Clearly upon receipt of the payment claim the
plaintiff was put on notice that Progress Claim 39 was being pressed as part of
the
Construction Stage Services provisions of the Contract. The problem faced
by the plaintiff was an inability to substantiate or otherwise
meaningfully
respond to the payment claim. There was of course a contractual obligation [PX
31/35] binding the defendant to itemise
Construction Stage Services by reference
to the relevant category of the consultant's staff, the quoted hourly rates and
timesheets
approved by the plaintiff. In the absence of being provided with the
timesheets, the plaintiff was confined to making the point in
its payment
schedule that there was no basis on which it could substantiate the claim value.
It did so.
46 It is clear from the evidence that:
· Cardno
MBK did not, in its payment claim, refer to or in any way rely
upon:
(i) any time sheets;
(ii) clause 3 of Annexure B of the
Contract.
· John Holland did not mount any defence with respect to
these matters in its payment schedule (pursuant to s.14).
· The same
matters were raised by Cardno MBK for the first time in its adjudication
application.
47 Whilst the matter is certainly not clear beyond doubt my
own view is that in this particular state of affairs it was impermissible
for
the claimant to raise these matters for the first time in the adjudication
application. Had the respondent sought to treat with
these issues in its
adjudication response, it would have been in breach of section 20
(2B).
48 In result the adjudication miscarried – for the same
reasons as have been given in relation to challenge 4. It was also
a denial of
natural justice – for the same reasons as have been given in relation to
challenge 4.
Challenge 2
49 Challenge 2 concerns a
situation in which no detail whatever of how the claimed amount was
comprised or made up was included in the payment claim. Ultimately the
adjudicator treated with this
as a claim for $59,370.00 awarding $54,019.90.
However there was simply no reference in the payment claim to a claim for
$59,370.00
[unless in some fashion, not apparent to me, this figure should be
regarded as part of some global claim appearing in the payment
claim].
50 The matter is curious for the reason that somehow [again not
explained to the Court] the respondent was able in the payment schedule [PX 116]
to identify the payment claim number
and the amount claimed.
51 This
challenge, also a timesheet issue, is addressed by the plaintiff as
follows:
· the adjudicator determined that an amount of $54,019.90
was payable to Cardno MBK in relation to progress claim no. 8 [see
PX 282].
John Holland challenges this award on the basis that it was either a
jurisdictional error for the adjudicator to rely on
the matters the subject of
the adjudication application, which had not previously been raised in Cardno
MBK's payment claim;
· in the alternative, John Holland was denied
natural justice by not having an opportunity to respond to this claim in its
Payment
Schedule and therefore was not able to present a defence to this claim
in its adjudication response, being expressly barred from
doing so pursuant to
s.20(2B) of the Act;
· Cardno MBK's payment claim did not include
any claim in respect of this amount. Cardno MBK did not provide any details
whatsoever in the payment claim of how the amount was comprised or how
the claim was being made;
· John Holland rejected this claim in its
Payment Schedule [see PX 116] on the basis that no time sheets were provided in
support
of the claim in accordance with item 1.3 of Annexure C of the Contract;
[I interpolate to note that clearly John Holland must have
believed that this
was a claim for Construction Stage Services will out how it came to that belief
is not apparent]
· in the adjudication application Cardno MBK, for
the first time, set out various details in relation to this claim [see PX
156
to 161]. In particular, Cardno MBK included various time sheets which were said
to support the claim. John Holland asserts
that these time sheets were not
approved by John Holland site personnel as required by item 1.3 of Annexure C of
the Contract [see
PX 35]. Cardno MBK alleged in its adjudication application
that the works were performed pursuant to various directions by John
Holland.
Because it was introduced for the first time in Cardno MBK's adjudication
application, John Holland asserts that it was
denied the opportunity to make any
submissions that the claimed extra work had not been the subject of directions
by John Holland:
· John Holland rejected this claim in its
adjudication response [see PX 270.146] on the basis that Cardno MBK had not
provided
any substantiation of this claim prior to the adjudication
application;
· Ultimately, the adjudicator determined that an amount
of $54,019.90 [see PX 282] was payable to Cardno MBK in respect of this
claim.
The adjudicator noted that the time sheets supporting the claim may not have
been approved by John Holland, contrary to the
requirements of item 1.3 of
Annexure C of the Contract. However, the adjudicator found that he inspected
the works and that the
time sheets generally supported the labour hours claimed.
The adjudicator determined this claim on the basis of time sheets which
had
never formed any part of the payment claim.
52 The burden of the
plaintiff submission is that in these circumstances:
(a) Cardno MBK
did not, in its payment claim, refer to or in any way rely upon:
(a) any
time sheets;
(b) clause 3 of Annexure B of the Contract.
(b) John
Holland consequently did not mount any defence with respect to these matters in
its payment schedule (pursuant to s.14).
(c) The matters in (a) were
raised by Cardno MBK for the first time in its adjudication
application.
(d) John Holland was confined, in preparing its adjudication
response, to matters included by it in its payment schedule: s.20(2B) of the
Act.
(e) Even if the course adopted by Cardno MBK (in (c) above) did come
within the scope of s.17(3)(f) - which John Holland denies - the effect of the
above course has been to deny John Holland natural justice.
(f) The
adjudicator could have exercised his discretion pursuant to section 21(5) to
invite John Holland to make further submissions with respect to the adjudication
application. This could have cured the denial
of natural justice, but it did
not occur.
53 Hence John Holland submits that it has been denied natural
justice by not being able to respond to this claim adequately, in circumstances
where Cardno MBK never provided any details of this claim or any time sheets
prior to the adjudication application.
Dealing with challenge
2
54 Whilst the Court would obviously be entitled to an explanation
as to how it had come about that the respondent was able to summarise
the claim
by giving the amount of the claim in the payment schedule by thumbnail sketching
it as a claim for “Construction
Stage Services”, no such explanation
was given by either party.
55 In that state of affairs the Court proceeds
upon the basis that challenge 2 concerns a claim for an amount, however
grounded, which
was never advanced in the subject payment claim [which payment
claim covered other items only] and which was advanced in the adjudication
application for the first time.
56 In those circumstances I do not see
that the relevant provisions of the Act were enlivened at all in relation to
this item. There
is no warrant for the Court speculating as to how the
respondent came to attribute any detail to this item in its payment schedule.
If
the fact be, for example, that there was a missing page which should have been
included with the payment claim was later identified
in some conversation or
e-mail between the parties, so that the respondent, by the time it submitted its
payment schedule could give
the relevant detail, this would not assist the
Court. It would simply throw up a need for a further payment claim [cf Act
section 13(6) to be subjected to the regime thrown up by the Act.
57 The
adjudicator determined the whole of the item the subject of challenge 2 upon the
mistaken assumption that the Act had been
enlivened. The determination clearly
miscarried in relation to the item the subject of challenge 2.
58 The
payment claim was defective. The determination was misconceived. The claim was
invalid and effectively “writ in water”.
Discretionary
considerations
59 The second defendant submitted that the present was
a case in which the exercise of the courts discretion should be to refuse to
grant the prerogative relief sought. My own view is that the plaintiff has made
good an entitlement to the relief sought. The amounts
involved are significant
in terms of so much of the determination as has miscarried. Clearly enough the
content of the obligation
to afford natural justice to the parties depended upon
the circumstances of the particular case and here the legislative scheme.
The
circumstances the subject of the judgment make clear that the determination has
gone forward in an entirely misconceived fashion.
The plaintiff has never been
given a proper opportunity to deal with properly substantiated claims in the
fashion mandated by the
statutory scheme.
Short Minutes of
Order
60 The parties are to bring in short minutes of order when
costs may be argued.
I certify that paragraphs 1 - 60
are a
true copy of the reasons
for judgment herein of
the Hon.
Justice Einstein
given on 20 April
2004
___________________
Susan
Piggott
Associate
20 April 2004
LAST
UPDATED: 22/04/2004
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2004/258.html