![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales |
Last Updated: 21 May 2004
NEW SOUTH WALES SUPREME COURT
CITATION: McIntyre v Marshall [2004] NSWSC 412 revised - 20/05/2004
CURRENT JURISDICTION:
FILE NUMBER(S): 1699/04
HEARING DATE{S):
11/05/04
JUDGMENT DATE: 17/05/2004
PARTIES:
Ian Gregory
McIntyre - Plaintiff
Neville Noel Marshall - Defendant
JUDGMENT OF:
Gzell J
LOWER COURT JURISDICTION: Not Applicable
LOWER
COURT FILE NUMBER(S): Not Applicable
LOWER COURT JUDICIAL OFFICER: Not
Applicable
COUNSEL:
Mr P Taylor SC/ Mr R R I Harper - Plaintiff
Mr
R D Wilson/Ms A Tibbey - Defendant
SOLICITORS:
Sage Solicitors &
Accountants
Thorntons Lawyers
CATCHWORDS:
CONVEYANCING -
Matters arising between Contract and Conveyance - Vendor issuing notice to
complete - Whether vendor free of default
by way of breach or antecedent
relevant delay - Whether inaccurate answers to requisitions constituted breach
or relevant delay -
Whether the purchaser was entitled to issue the requisitions
- Whether any antecedent breach remained relevant to the relative situation
of
the parties - Whether the purchaser was entitled to serve further requisitions
within 21 days from service of earlier answers
- Notice to complete issued
within the 21 day period - Whether the notice of termination was justified on
the ground of repudiation
- Whether the purchaser had the capacity to finance
the purchase
ACTS CITED:
Environmental Planning and Assessment Act
1979
DECISION:
Declaration that a binding contract existed and
specific performance
JUDGMENT:
IN THE SUPREME
COURT
OF NEW SOUTH WALES
EQUITY
DIVISION
GZELL J
MONDAY 17 MAY
2004
1699/04 IAN GREGORY MCINTYRE v NEVILLE NOEL
MARSHALL
JUDGMENT
1 A contract for sale of land from
the defendant to the plaintiff was executed by the parties. The defendant
purported to terminate
that contract.
2 In the period leading up to the
execution of the contract, the plaintiff became aware of road widening proposals
by the local authority
that would affect the boundary of the land. The plaintiff
caused a survey to be carried out and took account of the road widening
in plans
forming the basis of a development application for the construction of self
storage units on the land. The plaintiff said
what was not clear to him was
whether compensation had been paid to the defendant by Hastings Council and
whether any lease-back
arrangements had been entered into.
3 There was
also discussion in the period leading up to the execution of the contract of the
retention of two lean-tos and an awning
constructed on the land without Council
approval. The contract included a shed. The awning was demolished by the
defendant. He had
initially said this occurred after the contract had been
executed but in a later affidavit he said this occurred prior to contract.
He
was cross examined on this issue. In light of that evidence, Mr Taylor SC who
with Mr Harper appeared for the plaintiff, did not
press any submissions with
respect to that event.
4 The counterparts were exchanged on 6 August
2003. Requisitions were issued on 12 August 2003 well within the time prescribed
in
the contract. Requisition 12(f) asked whether the vendor was aware of the
erection or alteration after 16 April 1958 of any building
or improvement on the
land. Requisition 22(d) asked whether the vendor was aware of any proposal to
realign or widen any road adjacent
to the property.
5 The contract
defined a requisition as an objection, question or requisition not including a
claim. Mr Wilson, who appeared for the
defendant, submitted that the above
requests were not requisitions.
6 The requests for information fell
within the broad definition of a requisition. Furthermore, they were not mere
reminders to the
vendor of his obligations under the contract. They were
inquiries related to structures on the land and defects as to title. They
fall
within the types of inquiry that can be made properly by way of requisition
identified by Sir Garfield Barwick in Godfrey Constructions Pty Ltd v
Kanangra Park Pty Ltd [1972] HCA 36; (1972) 128 CLR 529 at 536.
7 Clause 10.1.9 of
the standard conditions of the contract provided that the purchaser could not
make a requisition in respect of
anything the substance of which was disclosed
in the contract. The contract was for the sale and purchase of two lots,
described
in the contract as 199-207 Hastings River Drive and Lot 2 Hibbard
Drive, Port Macquarie. A planning certificate under the Environmental
Planning and Assessment Act 1979, s 149 with respect to the former stated
that the land was affected by proposed road widening and attached a plan. The
certificate in relation
to the latter stated that the land was not so affected.
It was submitted on behalf of the defendant that requisition 22(d) was not
a
valid requisition and required no answer. I will return to this issue because
the defendant did respond in the negative and that
led to further requisitions.
8 Clause 5 of the special conditions of contract provided that
completion was to take place on 1 October 2003 and if not completed
on that
date, either party was entitled to give the other a notice to complete within 14
days of the notice, time being of the essence
and it being agreed that 14 days
was a reasonable period of notice.
9 Settlement did not take place on 1
October 2003 and on 16 October 2003 the defendant issued a notice to complete.
The plaintiff
complained that he had not received answers to his requisitions.
On 30 October 2003, the defendant withdrew the notice to complete
and provided
answers to requisitions. In answer to requisition 12(f) the defendant said he
was not aware of such alterations. He
answered requisition 22(d) in the
negative.
10 The next day, the defendant gave a further notice to
complete requiring settlement on 19 November 2003 and making time of the
essence.
11 On 17 November 2003, the plaintiff issued further
requisitions. With respect to the answer to requisition 12(f) it was noted that
there were two sheds and a wash bay on the land and further inquiry was made as
to the year when the improvements were constructed,
the identity of the person
who constructed them, whether any plans had been prepared, whether Council
approval had been sought or
was to be sought prior to settlement and if not how
the defendant intended to compensate the plaintiff.
12 With respect to
the answer to requisition 22, it was pointed out that the plaintiff was aware
that there was a proposal to widen
the road adjacent to the properties and the
defendant was asked what notification had been received in respect of the
proposed road
widening, whether he had negotiated an amount of monetary
compensation from the authority wishing to widen the road and, if so, what
amount had been negotiated, whether any agreements had been executed by him in
respect of the road widening and, if so, what parts
of the property being
purchased would be lost as a result.
13 On 18 November 2003, the
defendant responded to the requisitions. He said he had constructed two
lean-tos, had offered to demolish
them but the plaintiff requested they remain.
He said the wash bay shed had been approved by Council and a copy of the
construction
certificate was enclosed. He said the plan of acquisition with
respect to the road widening had been disclosed in the contract and
in the
certificates under the Environmental Planning and Assessment Act 1979, s
149. He said the Council had not paid for the acquisition of the property.
14 The plaintiff did not attend on settlement on 19 November 2003. The
defendant served a notice of termination on the plaintiff on
24 November 2003.
15 Before a notice to complete making time of the essence can be given,
not only must the other party be in breach or guilty of unreasonable
delay, but
also the party giving the notice must be free of default by way of breach or
antecedent relevant delay (Neeta (Epping) Pty Ltd v Phillips [1974] HCA 18; (1974) 131
CLR 286 at 299 per Barwick CJ and Jacobs J, followed in Louinder v Leis
[1982] HCA 28; (1982) 149 CLR 509).
16 In Winchcombe Carson Trustee Co Ltd v
Ball-Rand Pty Ltd [1974] 1 NSWLR 477, Wootton J held a vendor who issued a
notice to complete to be in default for failure to answer requisitions until the
letter enclosing
the notice to complete.
17 The contract did not specify
a time within which requisitions were to be answered. It follows that they were
to be answered within
a reasonable time. In failing to answer the requisitions
until 30 October 2003, the plaintiff argued the defendant was in default
and not
entitled to issue the notice to complete on 31 October 2003, either because he
breached the contract by failing to answer
the requisitions within a reasonable
time, or because he was guilty of antecedent relevant delay in failing to answer
them.
18 It was also submitted that the defendant was guilty of a breach
of contract in providing inaccurate answers to requisitions 12(f)
and 22(d). I
accept both submissions. In the context of a contemplated completion within 56
days and the issue of the requisitions
in 6 days, the defendant’s failure
to answer them accurately in under 79 days constituted a breach of contract and
unreasonable
delay.
19 It was submitted that the plaintiff was precluded
from issuing further requisitions with respect to the road widening under cl
10.1.9 of the standard conditions of contract because of the statements in the
certificates under the Environmental Planning and Assessment Act 1979, s
149. The plaintiff responded that the substance of the later requisitions was
not the road widening as such, but the question whether
compensation had been
paid and whether there were any lease-backs affecting the property. It was
pointed out that the fact of road
widening had been accepted by the plaintiff
who had caused a survey to be performed and had planned his development of the
land taking
account of the road widening.
20 It seems to me the later
inquiry was permissible. The requisitions were directed to matters resultant
from road widening rather
than the road widening itself.
21 As to the
other inaccurate answer, the defendant submitted that the plaintiff had waived
objection to it because in the pre-contract
negotiations the defendant had
volunteered to knock down the lean-tos but had been requested to leave them
there. The plaintiff objected
that pre-contractual negotiations could not
supplant the contract and it included improvements on the land.
22 The
defendant submitted that the plaintiff was not affected by the inaccurate
answer. He intended to demolish the sheds. The plaintiff
said his ultimate aim
was to demolish the structures but he planned a staged development and intended
to use the structures on the
land for a workshop in the early stage. In my view
the history of the structures was a legitimate area of inquiry.
23 In
Jillinda Pty Ltd v McCourt (1983) NSW ConvR 55-145, a contract required
the vendor to furnish a certificate not less than seven days before completion.
A certificate was furnished
the day before completion was due to take place. The
contract was not completed on the due date and the vendor gave notice within
seven days of furnishing the certificate requiring completion 14 days
thereafter. McLelland J held that the antecedent breach remained
relevant to the
relative situation of the parties when the notice to complete was given. The
purchaser was entitled to seven days
after the furnishing of the certificate
before being required to complete. The vendor was not entitled to issue the
notice to complete
until that period had expired.
24 Clause 5.2 of the
standard conditions of contract allowed 21 days after anything served by the
vendor for requisitions to be issued
by the purchaser. The answers to
requisitions were served by the defendant on 30 October 2003. The plaintiff had
until 20 November
2003 to issue further requisitions.
25 The defendant
submitted that Neeta, Jillinda and Louinder were limited to
breaches of provisions specifying specific times for performance and that a more
commercial approach should be taken
to the question of antecedent relevant delay
such as that adopted by Young J in Mulkearns v Chandos Developments Pty
Ltd [2003] NSWSC 1132. At par 44 his Honour observed that it would be quite
opposed to the presumed intention of parties to contracts that settlement could
be delayed indefinitely because of some minor problem and that while the
category of breaches that went to readiness, willingness
and ability extended
beyond matters of title or vacant possession, it was certainly the main subject
matter of such breaches.
26 First, the giving of the second notice to
complete within the 21 days vouchsafed to the plaintiff for requisitions under
the contract,
involved the breach of a specific time provision. Secondly,
Mulkearns involved the allegation that the vendor was not in a position
to give a notice to complete because it was in breach of an obligation
to one of
its lessees. That is not the situation in the instant circumstances.
27 In Louinda at 523, Mason referred to debate as to whether in
Neeta their Honours intended that mere breach of contract as distinct
from a serious breach of contract debarred a party giving a notice
to complete.
His Honour concluded that their Honours meant what it said and they had in mind
a breach of contract, whether serious
or slight.
28 In my view, the
antecedent breach or relevant delay remained relevant to the relative situation
of the parties when the second
notice to complete was given. I respectfully
adopt the approach taken in Jillinda. It follows that the defendant was
not entitled to issue the second notice to complete until after 20 November
2003.
29 In light of that finding, it is unnecessary for me to address
the other issues with respect to that notice. However, because of
the further
submissions made on both sides, I will indicate my views.
30 The
plaintiff submitted that he was not guilty of delay when the second notice was
given. The defendant relied on the plaintiff’s
failure to deliver a
transfer to enable completion to take place on 1 October 2003. In my view,
however, time was not of the essence
and that failure did not constitute a
breach of the contract.
31 The contract provided that the plaintiff could
direct a conveyance to a nominee. The plaintiff wished a nominee to take the
conveyance.
In an endeavour to avoid further stamp duty, his then solicitor
wrote on 3 October 2003 seeking rescission of the existing contract
and a fresh
contract in identical terms with the nominee. That proposal was not accepted by
the defendant and, in those circumstances,
it did not constitute a breach of
contract. I will return to the question of repudiation later in these reasons.
32 In my view, the plaintiff was not in breach of the contract when the
second notice to complete was issued and for that reason,
as well, the defendant
was not entitled to issue it.
33 The plaintiff submitted that cl 5 of the
special conditions of contract enabled a party to issue but one notice to
complete and
the defendant had expended that right when he issued his first
notice to complete. I do not read the clause in that fashion. It was
a mechanism
by which time might be made the essence of the contract and it was expressed in
general terms. If it were meant to be
utilised but once, one would have expected
the parties to have said so.
34 The plaintiff submitted that the form of
the second notice to complete was irregular. What is required, by whatever means
are chosen
to give notice, is that the attention of the other party should, by
the means chosen, be drawn with reasonable explicitness to the
acts required of
that party in relation to the contract (Taylor v Raglan Developments Pty
Ltd [1981] 2 NSWLR 117 at 132).
35 The notice stated that the
defendant was ready and willing to transfer the property situate at 199-207
Hastings River Drive in
accordance with the contract and required the plaintiff
to complete the purchase and pay the balance of purchase moneys at a specified
time and place, stating that time was of the essence of the contract.
36 The plaintiff submitted that the notice expressed a willingness to
convey only part of the property. It did not expressly require
completion of the
contract. It did not expressly require payment of the balance of the contract
price for the whole land. It did
not assert any ability or willingness to convey
Lot 2 Hibbard Drive.
37 I reject those submissions. The parties had at
an early stage in their communications adopted the heading 199-207 Hastings
River
Drive to describe both lots. For example, the plaintiff’s
supplementary requisitions were so headed. The construction of the
notice is to
be approached objectively and the question is how a reasonable recipient would
have understood it, bearing in mind its
context (Mannai Investment Co Ltd v
Eagle Star Life Assurance Co Ltd [1997] UKHL 19; [1997] AC 749). In my view, a reasonable
recipient aware of the above context would have understood the notice to state
that the vendor was ready
willing and able to convey the lands and called upon
the purchaser to take a conveyance of both lots upon payment of the balance
of
purchase price.
38 While the defendant relied on the second notice to
complete to ground his notice of termination, it was submitted that it could
be
justified upon any ground that existed at the time whether or not it had been
relied upon (Luna Park (NSW) Ltd v Tramways Advertising Pty Ltd [1938] HCA 66; (1938) 61
CLR 286 at 305). It was submitted that in failing to pay the balance of the
deposit when due (it was subsequently paid), in failing to submit
a transfer
prior to 1 October 2003, in failing to complete on 1 October 2003, in seeking a
four week extension of the completion
date on 26 September 2003 and in seeking
rescission and the substitution of a different purchaser, the plaintiff had
evinced an intention
no longer to be bound by the contract.
39 I reject
that submission. As I have indicated, time was not of the essence with respect
to the completion date of 1 October 2003
and, suggested rescission and new
contract not having been accepted by the defendant, the plaintiff continued to
indicate that he
was subject to the terms of the contract. The correspondence
proceeded on the basis of the contractual terms. The issue of the supplementary
requisitions was hardly indicative of an intention on the part of the plaintiff
no longer to be bound by the terms of the contract.
40 It was submitted
that the plaintiff lacked the capacity to finance the acquisition of the land
and the issue of the supplementary
requisitions was a ploy on his part, playing
for time. However, evidence was led from Nasser Kalache that he had indicated to
the
plaintiff that he would, and he remained prepared to, finance the
acquisition of the land on first mortgage in consideration for
the payment of
fees in the order of $10,000, the provision of a second mortgage over another
property of the plaintiff and a deed
from the first mortgagee that it would not
lend further funds secured in priority to the second mortgage. There was further
evidence
that such a request from a second mortgagee was standard practice and
financial institutions were in the habit of granting such deeds
of priority. In
my view the plaintiff demonstrated that he was able to take the
conveyances.
41 In my judgment the plaintiff has established his case and
is entitled to a declaration that there is a binding and enforceable
agreement
between he and the defendant and he is entitled to specific performance of that
agreement. I will hear the parties on appropriate
terms of such orders. I will
hear the parties on costs. I direct the parties to bring in short minutes of
orders reflecting these
reasons.
**********
LAST UPDATED:
20/05/2004
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2004/412.html