![]() |
[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of New South Wales |
Last Updated: 18 June 2007
NEW SOUTH WALES SUPREME COURT
CITATION: Downsouth Constructions v
Jigsaw Corporate Childcare [2007] NSWSC 597
JURISDICTION:
Technology & Construction List
FILE NUMBER(S):
55036/07
HEARING DATE{S): 24 May 2007
JUDGMENT DATE: 15 June
2007
PARTIES:
Downsouth Constructions Pty Ltd (Plaintiff)
Jigsaw
Corporate Childcare Australia Pty Limited (Defendant)
JUDGMENT OF:
McDougall J
LOWER COURT JURISDICTION: Not Applicable
LOWER COURT FILE NUMBER(S): Not Applicable
LOWER COURT JUDICIAL OFFICER:
Not Applicable
COUNSEL:
J A N Hogan-Doran (Plaintiff)
F P
Hicks (Defendant)
SOLICITORS:
Wilkinson Building & Construction
Lawyers (Plaintiff)
RBHM Commercial Lawyers
(Defendant)
CATCHWORDS:
BUILDING AND CONSTRUCTION CONTRACTS -
where numerous payment claims relating to four different construction contracts
served at once
- whether open to plaintiff to make adjudication application in
respect of some only of those payment claims relating to one only
of those
contracts - where payment claims assert matters of "defence" and matters of
cross claim - where adjudication response asserts
defence by way of set-off
based on mutuality of dealings in respect of matters alleged by way of "cross
claim" - where adjudicator
concluded that the defence of set-off is not
available by reason of s 20(2B) of the Building and Construction Industry
Security of Payment Act 1999 - whether denial of natural justice - whether
failure to exercise powers in good faith
LEGISLATION CITED:
Building
and Construction Industry Security of Payment Act 1999
Civil Procedure Act
2005
CASES CITED:
Brodyn Pty Ltd t/as Time Cost and Quality v
Davenport & Anor [2004] NSWCA 394; [2004] 61 NSWLR 421
John Goss Projects v Leighton
Contractors & Anor [2006] NSWSC 798
Rawson v Samuel (1841) Cr & Ph
161
Re Just Juice Corporation Pty Limited; James v Commonwealth Bank of
Australia [1992] FCA 420; (1992) 37 FCR 445
DECISION:
See para [67] of
judgment
JUDGMENT:
Downsouth Constructions v Jigsaw Corporate Childcare [2007] NSWSC 597
INDEX TO JUDGMENT
|
Para |
Factual background |
3 |
The Atrium payment schedules |
10 |
The adjudication application and adjudication response |
22 |
The adjudication determination |
31 |
The issues |
39 |
First issue: contents of the adjudication application |
42 |
Second issue: denial of natural justice |
51 |
Conclusion and orders |
67 |
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY
DIVISION
TECHNOLOGY & CONSTRUCTION
LIST
McDOUGALL J
15 June 2007
55036/07 DOWNSOUTH CONSTRUCTIONS PTY LTD v
JIGSAW
CORPORATE CHILDCARE AUSTRALIA PTY
LIMITED
JUDGMENT
1 HIS HONOUR: On 1 July 2006
the plaintiff (Downsouth) and the defendant (Jigsaw) entered into a construction
contract (the Atrium contract).
In essence, Downsouth undertook to construct
and fit out a childcare centre for Jigsaw at 9 Castlereagh Street, Sydney (the
Atrium
project). The Atrium contract was one of four (each relating to
different premises) made between Downsouth and Jigsaw (or, in one
case, between
Downsouth and a related company of Jigsaw known as Balanced Investment Group Pty
Limited).
2 The essential question that I am required to resolve is
whether the determination of an adjudicator, Ms Rosemarie Risgalla, on an
adjudication application based on a number of payment claims relating to the
Atrium contract, is void. I conclude that it is not.
Factual
background
3 On 2 March 2007, Jigsaw received from Downsouth a bundle
of invoices (and two summaries) claiming payment for construction work
(or
related goods and services) that Downsouth said it had carried out (or provided)
pursuant to one or other of the four contracts.
Each of those invoices was said
to be “issued under” the Building and Construction Industry
Security of Payment Act 1999 (the Act). There is no doubt that each of the
four contracts was a “construction contract” to which the Act
applied.
Jigsaw accepts that each of the invoices is a payment claim for the
purposes of the Act. Some 21 of those more than 40 invoices
related to the
Atrium contract; I will refer to those 21 as “the Atrium payment
claims”.
4 On 9 March 2007, Jigsaw provided (although with one
exception) payment schedules in response to the more than 40 payment claims
that
it had received on 2 March 2007. The payment schedules were generic in form,
and it will be necessary to return to some of
the detail. In substance, Jigsaw
denied liability for all the amounts claimed, and said in addition that it was
owed money.
5 The exception to which I have referred relates to
Downsouth’s invoice number #200841 for some $2,035.00. That was one of
the 21 invoices relating to the Atrium contract. There was no payment schedule
responding to that invoice.
6 Downsouth applied to an authorised
nominating authority for adjudication of the dispute relating to the Atrium
payment claims.
The adjudicator was nominated, and accepted appointment. She
was given an adjudication application (including submissions) and an
adjudication response (including submissions).
7 The original total of
the Atrium payment claims was, in round figures, $420,000.00. However, the
amount claimed by the adjudication
application was less: in round figures,
$318,000.00. The adjudicator determined that Downsouth was entitled to a lesser
amount
again: in round figures, $202,000.00. Jigsaw complains that the
adjudicator failed to afford it such measure of natural justice
as the Act
requires to be given, and failed to carry out her statutory functions, because
she did not consider and deal with an element
of its response, relating to an
alleged overpayment of $100,000.00 on another of the four projects.
8 Downsouth has recovered judgment for the adjudicated amount. It has
tried to enforce that judgment. Jigsaw sought and obtained
a stay, on the basis
that the adjudicated amount together with an amount for interest and costs be
paid into Court (which has been
done).
9 By notice of motion filed in
Court on 16 May 2007, Jigsaw sought a declaration that the adjudication
determination was void, and
(on an interim basis) a stay of execution on the
judgment. It expanded its claim to include an order that the judgment be set
aside.
It sought in the alternative an order staying the judgment on the ground
that Downsouth would not be in a position to repay any
amount that it might be
found to owe to Jigsaw. Jigsaw asserted that a director of Downsouth had
threatened in effect to strip it
of what assets it had and continue its business
through a different corporation. The parties agreed that this alternative claim
should be put off to another day. The only questions that I was required to
resolve were those relating to the validity of the adjudication
determination
and the judgment founded upon it.
The Atrium payment
schedules
10 Each of the Atrium payment claims related to individual
aspects of work that Downsouth claim to have carried out on the Atrium
project.
Some were said to be variations; others were said to result from design changes
and the like; and others again appear to
be for works carried out under the
contract. It is not necessary to go to the detail of those payment
claims.
11 As I have said, the payment schedules followed a similar, and
generic, format. The parties agreed that it was sufficient to consider
the
payment schedule relating to Downsouth’s invoice number #200669. That
payment schedule stated, among other things, that
the scheduled amount was
“$0.00”. It continued by stating “If the scheduled amount is
less than the claimed amount,
the reasons why it is less and the reason for
withholding payment are set out in the Attachment(s)
below”.
12 There followed, not as “Attachment(s)” but
as part of the text of the document, a number of assertions. The first
group of
assertions was preceded by the word “DEFENCE”. Although the
particular payment schedule to which the parties
referred was said to relate to
the Atrium project, some of the reasons set out under the heading
“DEFENCE” related not
to the Atrium contract but to another
contract, which in turn related to the St Martins Tower premises in Market
Street.
13 The next heading, following the statement of the
“DEFENCE”, was “Downsouth: Cross Claim”. There were
eight headings set out under that:
“1. Failure to fulfil terms of
contract - defects
2. Downsouth indebted to Jigsaw for other
monies
3. Monies overpaid to Downsouth by Jigsaw
4. Additional
Damages Claim
5. Breach of Obligations under Fair Trading Act and/or
Trade Practices Act
6. Cost of Arranging Alternate
Certification
7. Interest
8. Moneys owed for Negative
Variations”.
14 The first, fifth, sixth and eighth stated no
monetary amount, and said that the amount of the claim would “be
advised”.
The adjudicator disregarded most of them. I shall do likewise,
since no complaint is made of that.
15 The second item comprised a number
of individual components. The first (sub para (a)) related to “Liquidated
Damages”.
There was a claim for $203,500.00 for the Market Street
project, $500,500.00 for the Atrium project, and $258,000.00 for a project
at
Walker Street, North Sydney.
16 The second sub para of item 2 should be
set out in full:
“ Invoices overpaid pursuant to other
contract.
Jigsaw claim repayment of monies paid to Downsouth in
error.
Particulars:
$100,000.00 paid to Downsouth that was claimed to be
for variations.
Being claims for variations not in accordance with any
contracts or
are not otherwise liable to be paid.
TOTAL:
$100,000.00”.
17 Likewise, item 3 should be set out in
full:
“3. Monies Overpaid to Downsouth by Jigsaw
Jigsaw
had paid monies on behalf of Downsouth for items which were included in the
Scope of Works and are properly payable by Downsouth
under the
contract.
Particulars:
Payment to Eagle Lighting for 9 Castlereagh Street
- $24,118.49
Payment to Eagle Lighting for Level 2, 31 Market Street -
$20,794.06
TOTAL to date: $44,912.55
Reports are still currently
being collated to determine the final figure.” (emphasis in
original)
18 Item 4 purported to quantify a claim relating to the
Market Street project.
19 The form of the particular payment
schedule on which the parties focussed their attention was repeated throughout
all the payment
schedules. In particular, the “Cross Claim” in each
followed the same format. A number of items (including, of present
relevance,
items 2, 3 and 4) appeared to be copied identically from one payment schedule to
the other, regardless of the particular
contract or particular invoice to which
the payment schedule related. That is certainly the case in respect of the
payment claim
constituted by Downsouth invoice number #200844. (I mention that
one because it featured in the submissions of Mr F P Hicks of counsel
for
Jigsaw.)
20 At the end of the individual payment schedules (which
comprised in all 171 pages) was another bundle of documents that appeared
to
relate to all of them. It included such things as a copy of the construction
contract. The last group of documents in it was
described as “Emails and
Correspondence as referred to in Responses”. One of those documents was
something purporting
to be a tax invoice from Jigsaw to Downsouth dated 21
January 2007 (the set-off invoice). That invoice was headed “Credit
on
Walker Street Payment”. It specified some six invoices as “owing to
Downsouth”. They included invoices numbered
#200841 and #200844, each of
which related to the Atrium project. The other invoices related to other
projects. The total of all
six invoices was $32,436. The set-off invoice
stated “$100,000 paid to Downsouth by Jigsaw to be allocated to invoices
owing”
and claimed a “total credit owing to Jigsaw” of
$67,564.00. Mysteriously, and in a manner that Mr Hicks was quite unable
to
explain, the total owing was then stated to be
“$76,911.00”.
21 It may be the case that the set-off invoice
was referred to in one or other of the more than 270 pages of documentation that
preceded
it. If it was, neither Mr Hicks nor Mr J A N Hogan-Doran of counsel
(for Downsouth) took me to any document in which reference was
made to it. I
note in this context that I made it plain to both counsel that it was their
obligation to refer me to all documents
that they contended to be relevant, and
that I would not undertake my own investigation of documents to which no
reference was made.
The adjudication application and adjudication
response
22 The adjudication application said the following, in
relation to the “Payment Claim” and “Payment
Schedule”:
“Payment Claim
13. On 1 March 2007
the Claimant issued a statutory payment claim, pursuant to the Building and
Construction Industry Security of Payment Act 1999 (“The Act”)
to the respondent by express post.
14. The respondent admits in its
payment schedule that it received this document, stating on each payment
schedule in response to
each invoice issued in the payment claim:
“Date of Payment Claim: 2 March 2007.”
15. The
payment claim consisted of a series of invoices issued by the claimant on 1
March 2007, under the Act in relation to four
(4) contracts or arrangements the
claimant had with the respondent. These may be summarised as
follows:
(a) St Martins Tower, Market Street, Sydney in the sum of
$706,917.20;
(b) 9 Castlereagh Street, “Cheeky Monkies” in the
sum of $318,007.10;
(c) Walker Street, North Sydney “Head Office”
in the sum of $48,075.00;
(d) The Maintenance Contract/Arrangement in the sum
of $28,000.00.
Payment Schedule
16. On 13 March 2007 the
respondent provided the claimant with four (4) bound bundles of documents as its
payment schedule (containing
an individual payment schedule for each invoice)
within each of these four bundles (one for each contract, and containing
exhibits
or annexures for each contract. These documents are described as
follows:
(a) Payment Schedule: Project Head Office valuing the works at
nil or ($0.00);
(b) Payment Schedule: Project 9 Castlereagh Street valuing
the works at nil or ($0.00);
(c) Payment Schedule: Project St Martins Tower
valuing the works at nil or ($0.00); and
(d) Table of Contents (Containing
Annexures A to F) valuing the works at nil or ($0.00).”
23 The
adjudication application did not deal explicitly with the assertion that there
had been an overpayment of $100,000.00 on another
contract. It did however give
a generic denial in paragraph 30:
“30. The respondent has provided
reasons in an adhoc and disorganized fashion as an alleged justification for not
paying the
claimant the proper value of the claimant’s work. The claimant
rejects these reasons in their entirety and says its claim
should be valued in
full as claimed.”
24 In addition, Downsouth provided an individual
summary in respect of particular invoices. Of the two invoices referable to the
Atrium project that were referred to in Jigsaw’s set-off invoice,
Downsouth submitted the following:
(1) As to invoice number #200841:
“The claim should be valued in full. The respondent is estopped from
providing any reasons
in relation to this claim by section 20(2B) of the
Act.”
(2) As to invoice number #200844: “The respondent
agree [sic] that these works have been completed and are payable to the
claimant.”
25 As to the first proposition: neither party has been
able to refer me to a payment schedule relating to invoice number #200841.
Thus, it would seem, the position taken by Downsouth was correct.
26 As
to the second proposition: Downsouth referred to a particular point of the
relevant payment schedule, the whole of which was
attached. The payment
schedule showed that invoice number #200844 was one for which Jigsaw admitted
liability in full. However,
Jigsaw’s position was that it should be
“paid” by set-off: based on the alleged credit of $100,000.00
relating
to the Walker Street project.
27 The adjudication response
made specific responses to a number of paragraphs in the adjudication
application. Of present relevance,
it said, in relation to para 15 of the
adjudication application:
“15. This statement is consistent with
the respondent’s view that the parties have considered that the claimant
had established
a “running account” with the respondent whereby it
performed work and made claims. In particular the Claimant was performing
multiple contracts for the respondent, on at least one occasion, the claimant
requested the respondent pay an amount of $100,000
without reference to any
specific contract. The respondent paid such amount and accordingly the parties
have established a mutuality
arrangement whereby there is an interlinking of
set off rights between various contract rights as a “running
account”.
For this reason monies owed by one party under one contract may
be set off against monies owed by the other party under another
contract.
Further the respondent is otherwise entitled to set off monies owed under this
contract by the Claimant to the respondent
against monies owed or alleged to be
owed by the respondent to the defendant under this contract under the general
established principles
of contract law.”
28 The adjudication
response also contained a section titled “RESPONSE”. That section
said, among other things:
“B. The mutuality of dealings between the
claimant and the respondent requires that the total claim of the claimant under
all
contracts which it alleges exists is determined and set off against the
total counter claims by the respondent.”
29 There was included with
or attached to the adjudication response a schedule or annexure “I”.
That document had three
headings: “Invoice”, “Cost” and
“Jigsaw’s reason for non payment”. Under the first heading
it
listed, by invoice number, if not all then substantially all the Atrium payment
claims. Under the second heading it set out the
amount claimed by each. Under
the third heading it set out in most cases and in abbreviated form the material
that the heading would
suggest. I say “in most cases” because there
were some 5 invoices (including number #200841 relating to the Atrium project)
in respect of which no reason for non payment was stated.
30 On no
possible construction of any stated “reason for non payment”
relating to any of the payment claims could one
deduce, infer or understand that
Jigsaw was seeking to raise a defence by way of set-off in respect of the
“cross claim”
items set out in each payment schedule. Again,
counsel did not refer in their submissions to any other aspects of the documents
attached to or forming part of the adjudication response save for the schedule
or attachment “L”, a spreadsheet summarising
Jigsaw’s position
in relation to each item of the claim.
The adjudication
determination
31 After setting out formal matters, the adjudicator
summarised the contract and the parties’ positions. She noted the
following
in relation to the adjudication response:
“The Respondent
has submitted in the adjudication response that ‘the mutuality of
dealings between the claimant and the respondent requires that the total claim
of the claimant under all contracts
which it alleges exists is determined and
set off against the total counter claims by the Respondent’. While
amounts relating to other contracts were included as offsets against the
Claimant’s payment claim, this reason was not
included in the payment
schedule. In accordance with Section 20(2B) of the Act, the respondent cannot
include in the adjudication
response any reasons for withholding payment unless
those reasons have already been included in the payment schedule provided to
the
claimant. Accordingly, I cannot consider this reason in completing this
adjudication.”
32 The quotation in that paragraph was taken from
item B of the “Response” in the adjudication response, set out in
para
[28] above.
33 The adjudicator then turned her attention to
the topic of “Valuing the Works”. She said:
“I will
now deal with the disputed items claimed for work done and in doing so will have
regard to Section 10 of the Act and
the contract between the
parties.”
34 The adjudicator considered the various invoices that,
in her view, Downsouth had agreed to pay and quantified their amount. She
then
turned to a different topic: “Respondent’s Cross Claim”. She
dealt with this item by item under headings
that were taken or adapted from the
payment schedules. However, as I have said, she did not in most cases deal with
“Cross
Claim” items that were not quantified.
35 The first
item with which the adjudicator dealt was “Liquidated Damages:
$203,500.00”. As will be seen from what
I have said in para [15]
above, that item related to the Market Street project. However, I think
(having regard to the text of this part of the determination)
that the
adjudicator misread this aspect of the payment schedules and thought that the
amount to which she referred related to the
Atrium project. (She did not deal
with the amount of $500,500 claimed on the Atrium project; and it seems clear
from her discussion
of the claim for $203,500 that she understood it to relate
to that project.) In any event, she was not satisfied that Jigsaw had
“demonstrated an entitlement to the amount claimed”.
36 The
adjudicator then turned to “moneys overpaid to Downsouth by Jigsaw:
$24,118.49”. It is apparent that she focussed
on the amount of the claim
relating to the Atrium project, and ignored the amount relating to the Market
Street project. That having
been said, she was not satisfied that Jigsaw was
entitled to the amount claimed.
37 The adjudicator then turned to the
“Additional Damages Claim”. That claim related only to the Market
Street project.
The adjudicator gave a number of reasons for rejecting it
including:
“The project included in the payment schedule for which
the damages are submitted to have occurred is Level 2, 31 Market Street,
Sydney.
This is a separate project and is not included in the contract between the
parties and [sic] which is relevant to this adjudication.”
38 The
adjudicator then turned briefly to those other claims in respect of which costs
were to be advised, and said that she would
not consider them because there was
no amount advised.
The issues
39 Mr Hicks submitted that
the adjudication determination was void for two reasons. The first related to
that which was submitted
to adjudication. He submitted that there was but one
payment claim, being the bundle of more than 40 individual invoices received
by
Jigsaw on 2 March 2007. He submitted that neither the whole “Payment
Claim” thus constituted, nor any individual
invoice within it, was
referred to adjudication. He submitted that it was not open to Downsouth to do
as it had done: extract from
the original bundle of invoices those relating to
the Atrium project, and refer only those to adjudication.
40 Secondly,
Mr Hicks submitted that the determination was void because the adjudicator had
failed to consider the set-off relating
to the alleged overpayment of
$100,000.00, or alternatively had failed to exercise her powers in good faith
for the purposes for
which they were given, because she had excluded that
set-off from consideration on an irrelevant ground (namely, s 20(2B) of the
Act).
41 In oral address, Mr Hicks accepted that if this aspect of his
client’s case failed on the ground of denial of natural justice,
it could
not succeed on the alternative “want of good faith” (in the
“Brodyn” sense) ground. (My reference to Brodyn is of
course a reference to the decision of the Court of Appeal in Brodyn Pty Ltd
t/as Time Cost and Quality v Davenport & Anor [2004] NSWCA 394; [2004] 61 NSWLR 421; see
in particular the decision of Hodgson JA (with whom Mason P and Giles JA agreed)
at 441-442 [55]). Thus, and consistent with
what I have said in a number of
cases (see, by way of example only, John Goss Projects v Leighton Contractors
& Anor [2006] NSWSC 798 at [56] to [59]), I shall say no more about good
faith in this sense.
First issue: contents of the adjudication
application
42 Each individual invoice in the bundle of more than 40
received by Jigsaw on 2 March 2007 was itself a payment claim. Mr Hicks
accepted that this was so. Thus, each could have been referred to adjudication.
Mr Hicks submitted that this was what the Act required,
when it said in s 17
that “[a] claimant may apply for adjudication of a payment
claim”.
43 Mr Hicks referred also to Hodgson JA’s (non
exhaustive) list of “basic and essential requirements” that, in his
Honour’s view, were “the conditions laid down for the
adjudicator’s determination” (Brodyn at 441 [53]). The list
given by his Honour was as follows:
“53 What then are the
conditions laid down for the existence of an adjudicator’s determination?
The basic and essential
requirements appear to include the following:
1.
The existence of a construction contract between the claimant and the
respondent, to which the Act applies (ss.7 and 8).
2. The service by the
claimant on the respondent of a payment claim (s.13).
3. The making of an
adjudication application by the claimant to an authorised nominating authority
(s.17).
4. The reference of the application to an eligible adjudicator, who
accepts the application (ss.18 and 19).
5. The determination by the
adjudicator of this application (ss.19(2) and 21(5)), by determining the amount
of the progress payment,
the date on which it becomes or became due and the rate
of interest payable (ss.22(1)) and the issue of a determination in writing
(ss.22(3)(a)).”
44 Mr Hicks relied on Downsouth’s statement
in its adjudication application, that the “Payment Claim” was
comprised
of all the documents served by it, that were received by Jigsaw on 2
March 2007. However, that ignores the covering letter (dated
22 February 2007,
and said to have been “re issued by post – 23/2/07”) under
cover of which those invoices (and
the two summaries to which I have referred)
were served. That letter said (omitting formal parts):
“Please
find enclosed copies of all outstanding invoices and summaries, with detail of
request to confirm and clarify all costs.”
45 Each individual
invoice, and for that matter each summary, had at its foot the following
words:
“All invoices are issued under the [Act] ...
“.
46 I see nothing in this to indicate that Downsouth intended the
whole of the invoices served by it to constitute together one payment
claim.
Each invoice was served as a separate payment claim. To the extent that
Downsouth in its adjudication application may have
sought to categorise them
together as one payment claim (and I am not sure that it sought to do so), I do
not see why the Court should
be bound by that.
47 As Mr Hicks accepted,
it was open to Downsouth to refer all or any one of those separate payment
claims to adjudication.
48 If Mr Hicks’ construction of s 17 were
to be adopted, absurd results might follow in a particular case. Suppose, for
example,
that Jigsaw had admitted liability for some of the invoices, and had
not asserted any cross-claim or set-off in respect of them.
There would be no
dispute in respect of those invoices; but, on Mr Hicks’ approach,
Downsouth would be required to refer them
(together with all the disputed
invoices) to adjudication, and the adjudicator would be required to consider
them.
49 Mr Hicks conceded that his client could suffer no prejudice by
the reference to adjudication of a sub group of the payment claims
received on 2
March 2007. I think it is possible to express the point more generally: the
practice adopted by Downsouth would not
be capable of causing prejudice in any
likely or “real world” situation. On the contrary, it is likely to
lead to efficiency,
and to substantial savings of both time and money. I do not
see why the Court should adopt a construction that compels it to ignore
those
matters, and to accept potentially absurd results, unless there is no
alternative. I do not think that the language of s 17
is intractable to the
point where it offers no alternative but the construction proposed by Mr
Hicks.
50 Thus, I reject this aspect of Downsouth’s challenge to
the determination. I note, in connection with this aspect of the
challenge,
that Mr Hicks did not put any submission based on s 13(5) of the
Act.
Second issue: denial of natural justice
51 Hodgson JA
said in Brodyn at 441-442 [55] that a number of matters, including
“a substantial denial of the measure of natural justice that the Act
required
to be given” will mean that “a purported determination will
be void”. That concept has been explored and developed
in a number of
cases subsequently. Without wishing to be thought to be disrespectful either to
those decisions or to the submissions
founded on them, it is not necessary to
refer to them. The basic principle is clear. The question is one of its
application.
52 Mr Hicks’ submissions on this point encompassed two
elements. The first was that it was not open to the adjudicator to conclude,
as
she did in that part of her reasons that I have set out in para [31] above, that
the set-off based on mutuality of dealings had
not been raised in the payment
schedule, and was therefore something that should not have been included in the
adjudication response.
53 The second element of this aspect of Mr
Hicks’ submissions was based on the adjudicator’s failure to refer
to “a
substantial matter of payment that was expressly referred to in the
payment schedule/s and submissions of” Jigsaw: the reference
to the
alleged overpayment of $100,000.00 and the claim for its repayment.
54 There is a substantial overlap between those two elements of the
“denial of natural justice” challenge.
55 At this point I
note that there is one aspect of Jigsaw’s submissions that is difficult to
accept. Jigsaw raises as an issue
in its points of claim and submissions dated
21 May 2007 (para 29) that Downsouth did not assert that “the sum of
$100,000.00
was not referable to the claims made in relation to the [Atrium]
project ... “. However, it is clear on the face of Jigsaw’s
payment
schedules that Jigsaw accepted that this payment (or, as it would have it,
overpayment) was not referable to the Atrium payment.
Item 2(b) of the payment
schedule says that it was “overpaid pursuant to other contract”.
Further, if anyone had troubled
to refer the adjudicator to the set-off invoice,
it would have been plain that Jigsaw’s position was that the credit
related
not to the Atrium project but to the Walker Street project.
56 I
have to say that I have some difficulty in seeing why Downsouth should have
asserted that the sum of $100,000.00 was not referable
to the Atriuim project,
when on a fair reading of the material provided by Jigsaw to the adjudicator, it
was clear that this was
Jigsaw’s position also.
57 Leaving that
aside, the question in relation to the first aspect (s 20(2B)) is whether it was
reasonably open to the adjudicator,
in the exercise of her powers and duties
under the Act, to conclude as she did that the defence of set-off arising out of
mutual
dealings, raised in para 15 and again in item B of Jigsaw’s
adjudication response, was not a “reason ... included in
the payment
schedule”.
58 The resolution of that question depends in part on an
analysis of the payment schedule. The following matters bear on that
analysis:
(1) The “DEFENCE” and the “Cross Claim”
were treated separately, and were comprised of distinct categories
of reasons.
(2) The “Cross Claim” did not identify specifically the way
in which the particularised items operated to reduce the claimed
amount.
(3) Nonetheless, the “Cross Claim”, including item 2(b)
relating to the alleged overpayment, was given as one of the reasons
why the
scheduled amount was less than the claimed amount.
(4) Many of the items
referred to in the cross-claim, and specifically many of the items quantified
(as opposed to those in respect
of which no amount was stated), related to
projects other than the Atrium project.
(5) At no point in the payment
schedule did Jigsaw assert expressly that it was entitled to rely by way of
set-off on claims relating
to contracts other than the Atrium contract because
there was some course of dealings between the parties by reason of which the
mutual debits and credits between them were taken not on each contract
individually, but across all contracts from time to time in
force.
59 This is not the appropriate place to deal in detail with the
principles relating to set-off. It is sufficient to note that set-offs
and
counter-claims (or cross-claims) are conceptually different. A counter-claim is
not a defence. It does not diminish or abate
the plaintiff’s case. At
most, it leads to a situation where there may be two verdicts – one in the
action and one on
the counter-claim – and judgment for the balance. By
contrast, set-off is a defence. A plea by way of set-off, if successful,
will
reduce the plaintiff’s claim (if otherwise proved) to the extent of the
set-off. There will be verdict and judgment only
for the balance. (Section
90(2) of the Civil Procedure Act 2005 modifies this position, enabling
the Court either to give judgment for the balance or to give judgments in
respect of each claim;
but nothing of present moment turns on this.)
60 Set-off at law now arises under s 21 of the Civil Procedure Act.
There is no point in going into the complicated reasons why this is so. It
depends on the existence of “mutual debts between
a plaintiff and a
defendant in any proceedings”. Thus, assuming for the moment that set-off
at law would be available in the
present case through s 21 (a point on which I
express no view), liquidated claims may be set off one against the other to the
extent that the requirement of
mutuality can be met.
61 Set-off in
equity includes a number of different concepts. The traditional form of
equitable set-off arises where the defendant’s
claim against the plaintiff
raises some equity, the effect of which is to impeach the plaintiff’s
claim. As Lord Cottenham
LC put it in the leading case of Rawson v Samuel
(1841) Cr & Ph 161 at 179; 41 ER 451 at 458, the party seeking the
benefit of equitable set-off must be able to show “some equitable ground
for being protected
against his adversary’s demand. The mere existence of
cross-demands is not sufficient ... ”. His Lordship’s test
has been
applied on innumerable occasions; it is sufficient to refer to the judgment of
Gummow J in Re Just Juice Corporation Pty Limited; James v Commonwealth Bank
of Australia [1992] FCA 420; (1992) 37 FCR 445.
62 In the present case, the payment
schedules on their face distinguish between matters of “DEFENCE” and
matters of “Cross
Claim”. I accept that the payment schedules may
not have been prepared with an eye to the fundamental principles governing
set-off (whether at law or in equity). Nonetheless, I do not see why a
reference merely to matters of “Cross Claim”,
without more, must be
taken to signify that the matters relied upon were being asserted as a set-off,
having the effect not just
that there might be claim and counter-claim but that
any amount found in Downsouth’s favour should be diminished, or
extinguished,
by any amount found in Jigsaw’s favour. This general
impression is in my view confirmed by the circumstance that some of the
matters
relied upon by way of “Cross Claim” are plainly claims for damages
and not liquidated claims.
63 Further, the payment schedules give no
hint as to the fundamental requirement of mutuality (if the relevant concept now
said to
have been relied upon was set-off at law) or as to the matters going to
impeachment of Downsouth’s claim (if equitable set-off
was the relevant
concept). I do not suggest that it would be necessary to refer to these
concepts by name. But the failure to refer
to or identify facts relevant either
to the concept of mutuality or to the concept of impeachment means that the
reader is left to
work out for himself or herself the nature of the defence or
(in terms of s 14(3) of the Act) “the reasons for withholding
payment.”
64 It is obvious that the adjudicator had read the
payment schedules. In the passage to which I have referred in para [31] above,
she referred to “amounts relating to either contracts [that] were included
as offsets against [Downsouth] payment claim.”
Clearly enough, in
context, this must have been a reference to the various matters grouped under
the heading “Downsouth:
Cross Claim”. Thus, I think, one may
conclude that the adjudicator considered the payment schedule (see s 22(2)(d)).
If she misunderstood the nature of the reasons for withholding payment that were
being asserted, that was not a mistake of such
a kind as to indicate either a
failure to carry out the statutory duty to “consider” the payment
schedule or a breach
of one of the basic and essential requirements listed by
Hodgson JA in Brodyn.
65 In summary, I think, this aspect of the
adjudicator’s reasons reveals no error that would entitle this Court to
intervene.
That is sufficient to dispose of the first way in which Jigsaw put
its case based on denial of natural justice. It is also sufficient
to dispose
of the second way.
66 The adjudicator did deal expressly with a number
of the items that were raised under the heading “Cross Claim”. She
did so, as I have noted, under the heading “Respondent’s Cross
Claim”. She did not deal with all items listed
under that heading. In
general, she appears to have dealt only with those that related to the Atrium
contract. It seems to be clear
that, again in general, she excluded other
quantified items from consideration because of her view that the reason for
relying on
them – set-off – was an excluded reason having regard to
s 20(2B). If, as I have said, any error revealed in that conclusion is not
error of a kind that entitles this Court to intervene, it must
follow that the
adjudicator did not deny Jigsaw natural justice by refusing, on her
understanding of the application of s 20(2B) to the facts of this case, to
consider some aspects of the payment schedule. In effect, she gave reasons for
that refusal; this
is not a case where she simply failed at all to turn her mind
to the relevant subjects.
Conclusion and
orders
67 Thus, Jigsaw’s challenges to the determination fail.
However, there are other aspects of Jigsaw’s notice of motion
that have
not been dealt with (because the parties only argued those aspects going to the
enforceability of the determination and
the judgment based upon it). Clearly
enough, Downsouth should have its costs to date. However, having regard in part
to the drafting
of the notice of motion and in part to the way the hearing
before me proceeded, the only order that I make is to stand the proceedings
over
to 9.30 am on 28 June 2007 before me for the parties to bring in short minutes
of order to give effect to these reasons and
to provide for any further hearing
under Jigsaw’s notice of motion.
******
LAST
UPDATED: 15 June 2007
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2007/597.html