You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2019 >>
[2019] NSWSC 1098
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Context | No Context | Help
Longjing Pty Ltd v Perpetual Nominees Limited [2019] NSWSC 1098 (27 August 2019)
Last Updated: 30 August 2019
|
Supreme Court
New South Wales
|
Case Name:
|
Longjing Pty Ltd v Perpetual Nominees Limited
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
13-15 May 2019; 30 May 2019
|
Date of Orders:
|
27 August 2019
|
Decision Date:
|
27 August 2019
|
Jurisdiction:
|
Equity
|
Before:
|
Hallen J
|
Decision:
|
The Court: 1. Orders that the Plaintiff’s Statement of Claim
be dismissed. 2. Orders that there be judgment for the
Cross-Claimant against each of the Cross-Defendants in the sum of
$252,936. 3. Orders that the Plaintiff pay the Defendant’s
costs of the Statement of Claim. 4. Orders that the
Cross-Defendants pay the Cross-Claimant’s costs of the
Cross-Claim. 5. Orders that the Court Books be
returned. 6. Orders that the Exhibits be dealt with in accordance
with the Uniform Civil Procedure Rules 2005 (NSW) (rule 31.16A and rule 33.10)
and Practice Note No SC Gen 18.
|
Catchwords:
|
CONTRACTS – Construction – Principles – Determining when
Lease commenced pursuant to clauses within “Agreement
to Lease” and
“Lease” – Several potential dates for commencement of lease
were submitted by Defendant –
Plaintiffs argued lease did not commence and
no Lease Commencing Date – Commercially unrealistic to conclude that no
lease
had commenced in the light of the parties’
conduct CONTRACTS – Unconscionable conduct – Misleading
or deceptive conduct – Whether Defendant’s conduct in terminating
lease is unconscionable pursuant to meaning within s 46A of the Retail Shop
Leases Act 1974 (Qld) or pursuant to s 20 or s 21 of
the Australian Consumer
Law, or misleading or deceptive conduct CONTRACTS – Breach of
contract – Parties entered into a contract consisting of an Agreement for
Lease and Lease of certain
premises – Whether Plaintiff in breach of
contract – Whether Defendant entitled to terminate
lease CONTRACTS – Breach of contract – Consequences of
breach – Right to damages – Quantum of damages agreed to
by the
parties during course of hearing
|
Legislation Cited:
|
|
Cases Cited:
|
|
Category:
|
Principal judgment
|
Parties:
|
Longjing Pty Ltd (Plaintiff) Merry Ng (Cross-Defendant) Perpetual
Nominees Limited (Defendant/Cross-Claimant)
|
Representation:
|
Counsel: Mr J A Raftery (Plaintiff/Cross-Defendant) Mr C N Bova and
Ms B A Ng (Defendant/Cross-Claimant) Solicitors: Somerset
Ryckmans (Plaintiff/Cross-Defendant) Dentons Australia
(Defendant/Cross-Claimant)
|
File Number(s):
|
2016/269217
|
JUDGMENT
Introduction
- HIS
HONOUR: This case concerns, principally, a commercial lease of shops 203,
204, 205 and 206 (“the Premises”), in a retail shopping
centre known
as “Orion Springfield Central” (“the Centre”), situated
at Springfield Lakes, in Queensland;
whether the lease was validly terminated by
the Defendant; and the consequences that follow upon termination of the
lease.
- The
Premises comprised seven individual stalls in the Centre. They were to be used
by the Plaintiff, and/or its licensees, for operating
an Asian store selling
groceries and vegetables and an Asian Hawker-Style Market selling pre-prepared,
and prepared to order, Asian
cuisine and beverages. The Centre consisted of over
110 specialty stores.
- At
the commencement of the hearing, each of the parties contended that the
Defendant had granted, and the Plaintiff had taken, the
Lease on alternative
dates, the Defendant submitting dates earlier than 24 November 2015, and the
Plaintiff indicating there was
a binding lease on 24 November 2015: Tcpt, 13 May
2019, p 22(11-36). However, ultimately, there was no real dispute that the
Defendant
granted, and the Plaintiff took, a lease of the Premises, by no later
than 24 November 2015, being the date on which the Defendant
executed the Lease,
and that on that date, the Lease became binding on the parties: Tcpt, 15 May
2019, p 189(13-25).
- During
the course of the hearing, the Defendant seemed to suggest that the Lease became
binding when the Plaintiff entered into possession:
Tcpt, 15 May 2019, p
190(8-50), but it is clear from the correspondence, to which reference will be
made, that the Defendant asserted,
during the course of negotiations, that it
was not to be legally bound until it had executed the Lease.
- More
specifically, the issues for determination relate to whether the Lease had
“commenced” at the time a Notice to Remedy
Breach of Covenant
(“the Breach Notice”) was issued on 22 January 2016; whether the
Plaintiff was in breach of the Lease
as a result of its failure to open the
Premises during Core Trading Hours; whether the Defendant was entitled to
terminate the Lease
on 1 March 2016; and whether the Defendant’s conduct,
in terminating the Lease, was unconscionable pursuant to s 46A of the Retail
Shop Leases Act 1994 (Qld) (“the RSL Act”) or pursuant to s 20
and/or s 21 of the Australian Consumer Law (“the AC Law”), being
Schedule 2 to the Competition and Consumer Act 2010 (Cth), or
“misleading and deceptive” conduct.
- (Initially,
in the discussions that took place between the parties, and in some of the
documents, there was a reference to the lease
of another shop (“Shop
MM5”), which was to be used by the Plaintiff, or its licensee, for a Yum
Cha restaurant, but,
at the hearing, this did not form part of either
party’s case, other than in respect of one head of damage for a limited
amount,
that the Plaintiff advanced.)
- Depending
upon how the issues stated above are determined, the further issue for
determination will be which party is to pay the losses
sustained, and the
quantum of the losses, said to have been sustained, by one party, or the other,
in relation thereto.
- Whilst
the Plaintiff accepted that the Lease came to an end in March 2016, it claimed
damages for the Defendant’s repudiation
of the Lease, which repudiation it
accepted. The Defendant denied that it is liable to the Plaintiff for such
damages and disputes
the Plaintiff’s calculation of damages. The Defendant
made its own claim for damages said to have been suffered as a result
of the
breaches of the Lease, against both the Plaintiff and against Ms Merry Ng, the
Cross-Defendant, as the guarantor of the Plaintiff’s
obligations under the
Lease.
- Very
little attention was given, during the first three days of the hearing, to the
issue of damages. There had been a suggestion
by leading counsel for the
Defendant that “the damages, with respect, should be either able to be
agreed or able to be succinctly
argued by the time your Honour rises on
Wednesday. My learned friend was going to propose a schedule of damages, which I
haven't
seen yet, but we'll look at that. The damages I claim are reasonably
small in the bigger scheme of things ...”: Tcpt, 13 May
2019, p
13(26-41).
- At
various times, during the course of the hearing, the Court reminded the legal
representatives of the issue of damages, and that
very little time had been
devoted to that issue: Tcpt, 14 May 2019, p 92(13-38), p 178(50) – p
179(36).
- Shortly
prior to the adjourned date, each party provided a schedule of damages that it
claimed. I shall refer to the various claims
later in these reasons.
- In
the events that occurred, it was necessary to leave the issue of damages, as
well as the Defendant’s submissions, until a
fourth day of hearing time,
which had to be arranged, being 30 May 2019. On the fourth day of the hearing,
the parties confirmed
they had agreed upon an amount for damages claimed by the
Defendant, discussed later in these reasons. Then, counsel for the Plaintiff
referred to an e-mail that had been sent, by my Associate at my request, to the
parties, in respect of damages, and he “confirm[ed]
that the damages
claimed by the defendant are agreed” and that the agreed amount for
damages claimed by the Defendant was $252,936:
Tcpt, 30 May 2019, p
251(21-48).
- On
the fourth day, the issue of the Plaintiff’s damages was otherwise dealt
with, as were the Plaintiff’s submissions
on the topic. The case concluded
on the fourth day of hearing.
- I
should mention that despite submissions made as to the readiness of the
Plaintiff at the time the Defendant served the Notice of
Termination, no steps
were taken by the Plaintiff to seek relief from forfeiture or any interlocutory
relief to enable it to remain
in possession.
The pleadings and
the documentary evidence
- The
pleadings relied upon, in their final iteration, were an amended Statement of
Claim, filed on 14 May 2019; a Defence to the amended
Statement of Claim, filed
on 30 April 2018; a first Cross-Claim and Statement of Cross-Claim, filed on 30
April 2018; and a Defence
to the first Cross-Claim, filed on 5 June 2018.
- (It
was necessary to give leave to the Plaintiff to file the amended Statement of
Claim. Although it appeared that it had been filed
on 18 April 2018, the filing
was described in JusticeLink as having been “Void” (for reasons not
entirely clear). There
being no dispute that it should be filed, the Court
granted leave to file the amended Statement of Claim, which was done in
accordance
with the leave granted. The Court noted that, in the amended
Statement of Claim to be filed, the Plaintiff would omit paragraphs
23 and 24
and the particulars (l) and (n) of paragraph 33: Tcpt, 13 May 2019, p 46(5)
– p 47(16). The amended Statement of
Claim, as filed, now forms part of
the Court file.)
- In
the Defence to the amended Statement of Claim and in the Defence to the first
Cross-Claim, some admissions were made in relation
to the facts alleged and,
where appropriate, I have included a number of the admitted facts as uncontested
facts.
- Prior
to the commencement of the hearing, the Plaintiff’s legal representatives
provided the Court with three folders of documents,
in date order, and
consecutively paginated, comprising the relevant documents, upon which one, or
both, parties relied. At the hearing,
these folders were together marked as Ex.
A. Subsequently, each party, without objection, added some documents to that
Exhibit. Five
folders of additional documents were also tendered, each being the
Exhibit accompanying its corresponding affidavit. I have used
the contents of
the Exhibit, where appropriate, as the basis of some of the facts not in issue,
and to which I shall refer.
- Counsel
also provided a statement of agreed facts which has been used as an aide
memoire. Each also provided written submissions,
both opening, and closing,
which I have found very helpful.
- I
am grateful to all of the legal representatives of the parties for the efforts
made in order to provide the Court with the documents,
and also for the
submissions. Co-operatively, they have made a commendable attempt to limit the
real issues in dispute and to assist
the Court in determining those issues.
- Ultimately,
the parties agreed that the issues to be determined were:
- (a) When did
the Lease commence?
- (b) Was the
Defendant entitled to terminate the Lease on account of the Plaintiff’s
breach of cl 10.4 of the Lease?
- (c) Did the
Defendant engage in misleading or deceptive conduct or unconscionable conduct in
terminating the Lease on 1 March 2016?
- (d) What is the
quantum of damages suffered by the Defendant or by the Plaintiff (depending upon
the Court’s determination of
the first three issues set out
above)?
The Dramatis Personae
- I
shall limit the identity of the persons referred to in this section to the
parties and to the principal witnesses. I shall name
other persons who played a
part in the events, and who are referred to, in passing, in the evidence.
- In
circumstances to which I shall come, the Plaintiff, Longjing Pty Limited, at all
material times, was said to be the lessee of the
Premises. Ms Ng was its sole
director and the secretary, and the guarantor of the Plaintiff’s
obligations under the Lease.
As earlier noted, she is named as the first
Cross-Defendant in the first Cross-Claim and Statement of Cross-Claim.
- Ms
Ng swore one affidavit that was read in the proceedings and she was
cross-examined. At all relevant times, she seems to have been
the controlling
mind of the Plaintiff, although it is clear that her husband, Eddie Fong Chung
Ng, also participated in some of the
events that occurred. He did not give
evidence in the proceedings.
- Hilton
Edward Hedley was a leasing agent employed by Allied Property Group, a business
that he had established, and which specialised
“in retail project planning
and leasing, site acquisitions and disposals, and retailer
representation”. He has had 20
years’ experience in the commercial
property industry and had negotiated both on behalf of tenants and on behalf of
landlords:
Tcpt, 13 May 2019, p 27(49) – p 28(16).
- Mr
Hedley had known Ms Ng and Mr Ng for a number of years prior to 2015. He had
previously acted for them in connection with various
lease transactions in New
South Wales. Ms Ng and Mr Ng had owned, and operated, a number of Chinese
restaurants in the Sydney Metropolitan
Area.
- It
seems clear from Mr Hedley’s affidavit evidence that Ms Ng was not an
ingénue in relation to the leasing of retail
premises.
- The
Plaintiff engaged Mr Hedley, as its duly authorised agent, for the purpose of
dealing with, amongst others, the Defendant. In
the subject transaction, he was
to be remunerated, by way of commission, and was to be paid by the Plaintiff.
“Because the
deal was pulled”, he had not received any commission,
which was to have been paid to him “once the tenancies opened”:
Tcpt, 13 May 2019, p 30(4-13).
- Mr
Hedley could not state, precisely, the quantum of the commission he would seek,
but thought that it could be either $25,000 or
$50,000. He would only receive
remuneration for the work that he undertook on behalf of the Plaintiff if it was
successful in these
proceedings.
- It
was not Mr Hedley’s usual practice to read or understand the formal legal
documents such as an agreement for lease or a lease,
although he would
understand the commercial terms: Tcpt, 13 May 2019, p 31(1-6).
- Mr
Hedley swore three affidavits that were read and he was cross-examined.
- In
about May 2015, the Plaintiff retained Space Cubed Pty Limited (“Space
Cubed”), an architect and interior graphic designer,
to perform certain
work relating to the Premises. Mr Arran Woollams, of Space Cubed, was the
relevant representative with whom the
Plaintiff dealt. He did not give evidence
in the proceedings but copy emails to, and from, him, are included in Ex.
A.
- Kevin
Brennan was the engineering and project manager for the Plaintiff in respect of
the Premises. He did not give evidence in the
proceedings.
- In
or about mid-November 2015, the Plaintiff retained Alex Su, a commercial real
estate agent based in Sunnybank Hills, Queensland,
to assist with the marketing,
and the obtaining of prospective sub-tenants/licensees of the Premises: Tcpt, 13
May 2019, p 57(16-27).
Mr Su was not a witness in the proceedings, but copy
emails to, and from, him, are included in Ex. A.
- The
Defendant/Cross-Claimant, Perpetual Nominees Limited, at all material times, as
custodian and agent for Mirvac Funds Management
Limited (“Mirvac”)
as trustee for the Springfield Regional Shopping Centre Trust, was, and remains,
the owner of the
Centre. Mirvac is a subsidiary of Mirvac Limited. (In the
evidence, it was Mirvac, rather than the Defendant, to which counsel referred:
Tcpt, 13 May 2019, p 29(14) p 30(2). (On occasions, during the hearing, the
witnesses and the parties also referred to the Defendant
as
“Mirvac”.)
- Mirvac
Projects Pty Limited (“Mirvac Projects”) is, and was, at all
material times, a wholly owned subsidiary of Mirvac
Limited.
- Glenn
Dumbrell is the project leasing manager of Mirvac Property Group. Mr Dumbrell
and Mr Hedley had known each other, professionally,
for a number of years, and
had worked together during the period 2003 to 2006. Mr Dumbrell was the first
person to have discussions
with Mr Hedley about the Centre and the lease of the
Premises. He was not a witness in the proceedings.
- From
about May 2012, Mirvac Projects engaged Theo van Veenendaal as a development
consultant. From about June 2012, he was engaged
by Mirvac Projects to consult
with its management and to work on the development of the Centre. His principal
role in the development
was to negotiate leases with key tenants. From about
August 2015, he was involved in negotiating an Agreement to Lease and the Lease
with the Plaintiff. His discussions with Mr Hedley commenced in about August
2015 and completed in late February or early March 2016.
He affirmed two
affidavits, read in the Defendant’s case, and he was cross-examined.
- From
about 2013, Benjamin Conlon was the Portfolio Manager at Mirvac Projects in
respect of the Centre. In that role, he had responsibility
for “managing
day-to-day activities for the Centre, including liaising with the centre
management team, managing operational
expenses, capital expenditure, leasing,
marketing, administrative matters, managing tenant relationship[s] and asset
strategy and
forecasting”. He also had “responsibility for
Mirvac’s dealings with the [P]laintiff ...including instructing the
solicitors for the [D]efendant in its dealings with the [Plaintiff], both in
relation to negotiations and the subsequent dispute”:
Affidavit, Benjamin
Conlon, 2 August 2018 at par 4. Mr Conlon swore two affidavits that were read in
the Defendant’s case and
he was cross-examined.
- It
was to Mr Conlon that Mr van Veenendaal reported.
- James
Mutch was the Tenancy Co-ordinator Manager for Mirvac. According to Mr van
Veenendaal, he was responsible for co-ordinating
the works that the Defendant
was required to perform within the tenancy area: Tcpt, 14 May 2019, p
121(41-47). He was not a witness
in the proceedings.
- Ms
Manuella Di Rossi was the National Leasing Manager at Mirvac Property Group. She
was not a witness in the proceedings.
- The
firm of solicitors acting for the Plaintiff and Ms Ng, until about 25 November
2015, was Raymond Lee & Co. Then, between 25
November 2015 and 2 March 2016,
the Plaintiff retained Thomas Kung Lawyers, or Thomas Kung, to act on its behalf
in respect of the
lease of the Premises and to assist in drafting
sub-leases/licence agreements for prospective sub-tenants/licensees of the
Premises.
- At
all relevant times, the firm of solicitors acting for the Defendant, in the
Lease transaction, was Gadens.
- None
of the lawyers, on behalf of any party involved in the transactions, was a
witness, although many emails passing between them
formed part of Ex.
A.
Background Facts
- The
following facts, which trace the history of the events leading to this dispute,
are not controversial. To the extent that any
facts are disputed, what is stated
under this heading should be regarded as findings of the Court. (It is not
necessary, or practicable,
to set out all of the events that occurred prior to
the signing of the relevant lease documents. I have used the parties’
statement
of agreed facts and the admissions made in the oral evidence as a
guide to identifying the relevant events.)
- The
discussions for the lease of the Premises commenced in late January 2015, when
Mr Dumbrell approached Mr Hedley, to find a tenant
to lease the Premises. Mr
Dumbrell told Mr Hedley that he had been in discussions with Golden Vision
Retail Pty Limited (“Golden
Vision”) in respect of the Premises but
that those negotiations had reached a standstill. Mr Dumbrell enquired whether
Mr Ng
would be interested in leasing the Premises.
- On
about 4 February 2015, Mr Hedley attended a meeting at the Centre with Mr
Dumbrell and Mr Ng.
- At
about this time, Mr Dumbrell also advised Mr Hedley that Shop MM5 was available,
and that he thought it would be suitable for use
as a large format Yum Cha
restaurant. Mr Dumbrell then enquired whether Ms Ng and Mr Ng would be
interested in the lease of that
shop also.
- On
5 February 2015, the Defendant provided a document headed “Orion
Springfield Central ... Retail Lease Proposal” which
was said to be
“subject to Lessor approval, availability and contract” for the
Premises. In this document, it was made
clear that “[t]hese premises do
not exist and will need to be constructed”: Ex A/1-30. A draft Floor Plan
for the Premises
was attached to the Proposal.
- The
“permitted use” identified in the Retail Lease Proposal
was:
“The operation of a retail store selling Asian groceries and vegetables
and an Asian Hawker-Style Market selling pre-prepared
and prepared to order
Asian cuisine and beverages...”
- On
18 February 2015, Mr Dumbrell, through Mr Hedley, provided a further proposal to
the Plaintiff, in respect of the Premises: Ex.
A/31-48. (It appears that the
principal change related to the name of the area of the Premises.)
- Also,
on 18 February 2015, the Defendant provided a document headed “Orion
Springfield Central ... Retail Lease Proposal”
which was said to be
“subject to Lessor approval, availability and contract” for Shop
MM5. In this document, it was also
made clear that “[t]hese premises do
not exist, and will need to be constructed”. A draft Floor Plan,
delineating MM5,
was attached: Ex. A/49-62 to this Proposal.
- In
about mid-March 2015, the Plaintiff executed each Retail Lease Proposal.
- On
23 March 2015, Mr Dumbrell sent an email to Mr Hilton confirming that there had
been “Approval internally” and “Will
now processes [sic]
formally and instruct I would say by the end of the week”: Ex. A/63.
- On
26 March 2015, the Plaintiff paid to the Defendant a deposit of $64,166.70,
which was apportioned as to $27,500 for the Shops and
as to $36,666.70 for Shop
MM5. (The parties’ Statement of Agreed Facts, which was provided as an
aide memoire states that the
deposit was paid to “Mirvac”. The
affidavit of Mr Hedley made 5 October 2016, to which the Statement of Agreed
Facts
refers, and identifies as the source of that fact (at par 18)),
“Mirvac” is defined to mean Mirvac Property Group (at
par 6). In any
case, there is no dispute that the Plaintiffs paid those sums, on that date.
This document was treated as an aide
memoir: Tcpt 15 May 2019, p, 187(44)
– p 188(6)).
- Under
cover of a letter dated 24 April 2015, Gadens sent to Raymond Lee & Co a
proposed Agreement for Lease, Lease and other documents
for Shop MM5, for review
by the Plaintiff, all of which documents were said to be subject to the
Defendant’s approval. The
request was made that if the documents were in
order, they should be executed and returned “as soon as possible”. A
cheque
for $202.10, payable to Gadens, was also sought: Ex. A/66-67.
- On
6 May 2015, Mr Hedley attended a design meeting with representatives of the
Defendant.
- On
7 May 2015, Mr Mutch sent an email to Mr Hedley noting the following
timetable:
“Initial Concept Design issue to Mirvac 15th may [sic]
2015
Handover of Tenancy to Commence Fitout 13th August 2015
Fit Out works to be completed by 8th October
2015”
- On
19 May 2015, Mr Dumbrell provided Mr Hedley with plans, scale drawings and
colour schematics from Mirvac, of the plans that had
previously been submitted
by Golden Vision, the previous proposed tenant, for the Premises.
- On
20 May 2015, Mr Hedley attended an on-site meeting with Mr Mutch, other Mirvac
representatives, Ms Ng and Mr Ng.
- On
22 May 2015, Mr Woollams, of Space Cubed, sent Mr Hedley an email attaching a
layout for the Premises.
- In
the weeks leading up to 21 July 2015, Mr Hedley had a conversation with Mr
Dumbrell regarding the delay in the handover dates.
- On
21 July 2015, Mr Angus White, the Development Manager, Mirvac, and Mr Hedley had
an email exchange in which, amongst other things,
Mr White confirmed
“following our conversation today, your commitment to take handover of the
store at Orion on 12th August
2015 and open on 7th October 2015 as per our
agreed program”: Ex. A/76-77.
- Also,
on 21 July 2015, Gadens sent an email, addressed to “Anson”, with a
copy to Raymond Lee & Co, regarding the
Premises, in the following terms
(Ex. A/79):
“We refer to the above matter and are instructed by our client that the
terms of the documents are now agreed... We have re-engrossed
the documents to
include the agreed amendments.”
- (At
the hearing, the parties agreed that “Anson” was Anson Cheang, a
solicitor at Raymond Lee & Co: Tcpt, 15 May 2019,
p 185(25-37).
- The
email attached a copy of the Agreement for Lease of the Premises in marked-up
form, the Agreement for Lease, in final form, of
the Premises, Lease in
marked-up form, and the Agreement for Lease, in final form, for Shop MM5. It was
noted that the Defendant
“had not had the opportunity to review the
documents prior to them being issued and that the Defendant reserved its rights
to make further amendments”.
- On
29 July 2015, Mirvac emailed a “Handover Notice” (Ex. A/84-85) to Mr
Hedley which provided:
“The Lessor hereby notifies the Lessee that as of the Handover Date set
out below the above premises will become the sole responsibility
of the Lessee
for the commencement of the Lessee’s works.
Applicable dates are confirmed as follows:
• Handover Date:
12th
August 2015
• Date of completion of Lessee's
works: 7th October 2015
• Trade Commencement
Date: 7th October 2015
• Lease & Rent Commencement
date The earlier of:
(i) The day after the end of the Fitout Period; or
(ii) Trade commencement date
Before the Handover Date, the Lessee and/or its shopfitter is to contact
James Mutch on 04XX XXX XXX to organise an inspection of the
Premises.
During the inspection, the Lessee or its shopfitter will be provided with a
notice called ‘Site Condition at Handover’
which outlines the
condition of the Premises as at the Handover Date.
There will be a deemed handover of the Premises on the ‘Handover
Date’ regardless of whether the Lessee or its shopfitter
attend the
inspection or access the Premises unless the Lessor provides a further Handover
Notice in which case the Handover Date
will be the date in the further Handover
Notice.
Please note however that access to the Premises to commence the Lessee’s
works will only be granted to the Lessee upon satisfaction
of the following
items marked with X:
Lease Documentation Checklist
X LEASE EXECUTED
X PUBLIC LIABILITY INSURANCE, CERTIFICATE OF CURRENCY RECEIVED
X BANK GUARANTEE RECEIVED
Design and fitout checklist
X FINAL DESIGN APPROVAL
XTENANT TO PAY FEES AND SERVICES ADJUSTMENT COSTS
TENANT APPOINTED SHOPFITTER
X SHOPFITTER PAPERWORK RECEIVED”
- At
the time the “Handover Notice” was issued, Mr Mutch and Mr Angus
White, the Development Manager, Mirvac, informed Mr
Hedley that the lease
documentation had been finalised. Despite that having been said, it is clear
that at that time, negotiations
as to the Agreement for Lease and Lease were
ongoing between the solicitors. There is no dispute that Mr White, at the
relevant time,
was employed by the group known as “Mirvac”.)
- On
30 July 2015, Gadens sent an email to Raymond Lee & Co, requesting those
solicitors to “advise when we can expect to
receive the executed lease
documents for Shops 203-206 and Shop MM5 [sic]”: Ex. A/73.
- On
4 August 2015, Mr Hedley sent an email to Mr White regarding the contribution
payable by the Defendant and suggested amendments
to the Lease.
- On
6 August 2015, at 9:07 a.m., Mr Hedley wrote to Mr Dumbrell noting “We are
all meeting on site next Wednesday to finalise
everything prior to taking
handover...”: Ex. A/89.
- On
6 August 2015, at 5:15 p.m., by letter sent via email to Mr Lee at Raymond Lee
& Co from Gadens, the Defendant elected to withdraw
from offering the
Plaintiff the leases due to the failure to return executed documents: Ex.
A/93-94.
- Another
letter, also of the same date, in almost identical terms as that sent to Mr Lee,
from Gadens to Mr Cheang at Raymond Lee &
Co, noted (Ex.
A/95):
“You will appreciate that there is no binding agreement in place until the
documents are signed by both parties. To date, the
documents have not been
signed by both parties.”
- Despite
the withdrawal from the negotiations, Ms Di Rossi requested a meeting with Mr
Hedley to discuss the Lease.
- On
about 7 August 2015, Mr Hedley had a meeting with Ms Di Rossi, and Sepideh
Vahdat, a retail leasing executive for the Defendant,
at which Mr Ng also
attended. When Ms Vahdat and Ms Di Rossi raised concerns about the guarantors
under the lease and whether the
Plaintiff would be able to commence its tenancy
fitout following handover, Mr Hedley responded (Affidavit, Hilton Hedley, 5
October
2016 at par 37):
“I really can't understand why you have only decided to raise issues about
the guarantors in August when the deals were approved
back in March. I also
don't understand why we are being pressured about a handover when the leases
aren't even signed and in fact
the deals have been terminated. This just seems
to be another example of no-one within Mirvac speaking to the other
side...”
- Following
the discussion referred to, Ms Di Rossi said that the Defendant had
“terminated the lease as a precaution” and
that she was happy to
proceed with the negotiations for the Lease.
- On
7 August 2015, Mr Hedley sent an email to Ms Vahdat regarding the shop design,
guarantor and Lease: Ex. A/97
- Between
7 August 2015 and 24 August 2019, Mr Hedley continued to liaise with the
Plaintiff’s designer and shopfitter to ensure
that all requirements of
Mirvac were being attended to and completed. He also continued to liaise with
Mirvac's delivery team in
relation to the tenancy design and handover.
- On
11 August 2015, Mr Hedley informed Ms Ng and Mr Lee that Ms Di Rossi “is
resubmitting these details to the CEO tomorrow”:
Ex. A/99.
- On
24 August 2015, Mr Brennan sent Mr Hedley an email, which stated (Ex.
A/106):
“We confirm that we have been waiting on the owner’s consent form to
be filled out for the plumbing application which
we requested on 4th
August.”
- Following
a meeting on 31 August 2015 between Mr Hedley, Mr van Veenendaal and Ms Justine
Hughes, the Head of Retail Management, Mirvac
provided the Plaintiff with Heads
of Agreement for the Yum Cha restaurant, which was to be located at Shop 116A,
rather than Shop
MM5, as had previously been agreed. (For the same reason that
has been outlined earlier in these reasons, it is unclear from the
evidence
whether Mr Hughes was employed by Mirvac, Mirvac Property Group, or another
subsidiary. I do not think anything turns on
this.)
- On
the same date, Gadens sent an email to Raymond Lee & Co stating that she had
received instructions that the “parties
have now reached agreement
regarding the guarantor for Shops 203-206...”. She also enclosed the
“lease documents with
the proposed changes shown tracked as well as the
final from [sic] for signing by the parties”: Ex. A/112.
- On
18 September 2015, Raymond Lee & Co sent a letter to Gadens in respect of
the Agreement of Lease and Lease: Ex. A/146-147.
That letter
stated:
"We refer to the above and note that we are still waiting for copies of draft
lease documents relation [sic] to the yum cha restaurant.
We had expected to
receive such documents by now however understand that lease of the yum cha
restaurant and we have been advised
to expect to receive draft lease documents
shortly.
In the meantime, we have also been advised as follows in relation to the lease
by Kowloon City of Shop 203-206:
1. The Lessor will complete, at the Vendor's expense, the previously agreed
scope of Lessor's works for Shops 203-206 including but
not limited to all
category one items.
2. The dates for the provision of plans, such as services layout plans do not
need to be strictly comply with. We understand from
our client that some plans
have been previously provided including an initial concept drawing and layout
plan.
3. We understand from our client that on a meeting with your client's
representative, your client advised that it would require copies
of lease
documents executed by the Lessee to allow our client to commence fitout works on
and from 28 September 2015.
4. We are instructed to confirm that the lease by Longjing Pty Ltd of Shops
203-206 Orion Springfield Central is to proceed only
on the basis that an
agreement for lease and lease satisfactory to our client with respect to the yum
cha/Chinese restaurant is entered
into with respect to premises satisfactory to
our client within the Orion Springfield Central Shopping Centre.
On the above basis, we attach hereto the following:
1. Copy of signed agreement for lease.
2. Copy of lease.
3. Copy of Lessor's disclosure statement. We note that such was the one
initially issued by the Lessor. We note that some of the
terms as contained in
the original Lessor disclosure statement have been superseded by subsequent
negotiations.
4. Signed Lessee's disclosure statement.
We would be grateful if you would acknowledge receipt.
We also note that the lease documents attached hereto are to be held in
escrow.”
- In
the “Disclosure Statement by the lessor” (Ex. A/162ZCL-162ZDB), the
copy of which bears, on the final page, what appears
to be Ms Ng’s
signature and the date 4 September 2015, in the box headed “Estimated
commencement date of the lease”,
the date “10/09/2015” was
inserted and described as “Actual”. Similarly, in the box headed
“Estimated
handover date of the premises” “10/09/2015”
was inserted and described as “Actual”: Ex. A/162ZCL.
- In
the Disclosure Statement referred to, important is Part 3 “Works Fit Out
and Refurbishment” and in the box headed “Date of handover (if
different to the date the lease commences
indicated at Item 5),” the date
“10/09/15” was inserted and described as “Actual”: Ex.
A/162ZCO.
- On
about 18 September 2015, Ms Ng, on behalf of the Plaintiff, and in her capacity
as a guarantor, executed the Agreement for Lease,
and the Net Retail Lease, for
the Premises. (Each of the Agreement for Lease and Net Retail Lease that was
signed by Ms Ng, copies
of which were sent by Raymond Lee & Co to Gadens on
18 September 2015, appear to be undated.)
- On
21 September 2015, the Plaintiff provided the Defendant with a bank guarantee in
the sum of $165,000.
- On
24 September 2015, Mr Mutch sent an email to Mr Hedley and others (Ex. A/163)
confirming the following dates :
“3rd October - Handover (8 week fitout)
5th November - Entire shopfront completed with the Mall/Town Walk tenancies
fully open and trading
28th November - Full completion of any outstanding works with all tenancies open
and trading.”
- On
1 October 2015, Mr Hedley sent an email to Mr van Veenendaal asking for the
contribution that the Defendant was to make. He noted
“they are supposed
to be taking handover on Saturday and won’t be doing so until they have
some money”: Ex. A/167.
(The reference to “taking handover this
Saturday” is consistent with the email of 24 September 2015 from Mr
Mutch.)
- On
2 October 2015, the Plaintiff delivered to the Defendant the hard originals of
the Agreement for Lease and the Lease.
- On
8 October 2015, Gadens sent a letter to Raymond Lee & Co, in response to the
letter dated 18 September 2015, which included:
“1. We refer to your letter of 18 September 2015 and the
original signed documents for the above Premises which were returned
to our
client directly on 2 October 2015. We are instructed that the matters raised in
your letter of 18 September 2015 are not agreed
by the Lessor.
2. We are further instructed that your client has requested
that the Lessor release the first instalment of the Fitout Contribution
to the
Lessee.
3. Our client instructs us that the Premises will not be handed
over to the Lessee or its fitout contractor and the first instalment
of the
Fitout Contribution will not be released to the Lessee (despite any contrary
position in the Agreement for Lease) until your
client acknowledges, accept and
agrees that:
(a) the final agreed terms between the parties for the Premises are as set out
in the documents returned to the Lessor signed by
the Lessee on 2 October 2015
(Agreed Documents);
(b) the Lessee will not seek any further amendments to the Agreed Documents,
subject to any amendments being required to correct
any errors, to give effect
to the Agreed Documents or to enable registration of the Lease. In this regard,
we particularly refer
you to paragraph 4 below;
...
4. Our client advises that the original signed documents
returned by your client include certain hand writing on page 26 of the
Agreement
of Lease which cannot be deciphered. Can you please confirm by return that this
hand writing is not intended to vary the
signed documents and, if so, please
authorise us to replace this page in the signed documents held with a new clean
page 26 (a copy
of which is attached for your reference).
5. Please have your client confirm its agreement to the above
by signing and returning the duplicate of this letter before close
of business
on Thursday 8 October 2015.”
- On
9 October 2015, Mr Hedley sent an email to Ms Ng, Mr van Veenendaal and Raymond
Lee & Co (Ex. A/187A), stating:
“Merry,
Theo and I have just spoken and the reality of finalising the outstanding legal
terms by today - are slim.
The payment for the fitout contribution should hit your account today, but maybe
not be until Monday. Theo and I have agreed that
the opening date will be pushed
back (so no longer the 5th of November), and that realistically we all work
together in starting
on site as soon as possible, and opening as soon as
possible, rather than committing to new dates that will just be missed
again.
I will explain to Leigh the builder that he will not be starting on site this
weekend.
Theo suggested a meeting on Monday with all of us to go through where we are at
and to provide you both with a degree of comfort
as to where we are heading.
I'll come back to you once a time has been set. If any progress is made today on
any of the above I will let you know, otherwise
have a nice weekend and I'll see
you Monday.”
- On
13 October 2015, in a letter from Raymond Lee & Co to Gadens, it was
confirmed that the Plaintiff had not accepted the terms
put forward in the
letter dated 8 October 2015 from Gadens, but that there had been certain without
prejudice discussions between
the parties and that some amendments to the Lease
would be made (particularly referring to Shop MM5 no longer being available):
Ex.
A/187ABA-187ABB.
- On
about 14 October 2015, Mr van Veenendaal attended a meeting with Mr Hedley,
during which meeting, a conversation to the following
effect took place
(Affidavit, Theodorus van Veenendaal, 24 July 2018 at par
20):
“[Mr Hedley]: There is additional work that needs to be
done, such as the mechanical exhaust and fire services. Mirvac should pay for
this work.
[Mr van Veenendaal]: This work was never part of the Lessor's
Works but we will do the additional work as Lessor's Works, if Longjing agrees
to pay an
extra $10,000 in rent, and reduce the incentive payment for the Yum
Cha Restaurant. We will handover the Premises on 19 October 2015,
and Longjing
can commence the fitout works then. This will mean the Opening Date will be 14
December 2015.”
- On
14 October 2015, Raymond Lee & Co sent a letter dated 13 October 2015 to
Gadens. That letter stated:
“I refer to your letter of the 8th of October 2015 received by e-mail at
3pm on that date requiring our client's instructions
and confirmation to the
matters contained herein by 5pm on Thursday the 8th of October 2015.
Our client was unable to and cannot accept and agree to the terms set out in
your letter of the 8th of October 2015. In this regard,
we are instructed that
matters, particularly Point 3 (d) is incorrect.
It had always been the case that our client was to lease Shop 203 to 206 and
Shop MM5 and our client had made plans and arrangements
and made commercial
decisions on this basis.
Subsequent to our client making arrangements with respect to the leasing of both
of the premises, we are instructed that your leased
Shop MM 5 to a retail tenant
for your client’s own commercial gain, not having regard to our client's
position.
We have been advised that your client has been unable to commit to other
possible premises within the Centre to allow our client
to open a yum cha
restaurant.
Without prejudice to our client's rights, we are instructed that our respective
clients have recently undertaken discussions. We
are instructed that the Lease
with respect to Kowloon City and the yum cha restaurant are to remain as
"hand-in-hand" however, in
the event that your client is unable to confirm the
terms of a deal with respect to the lease of the yum cha restaurant premises
by
the 1st of July 2016, at premises satisfactory to our client and on terms
satisfactory to our client then our client requires
an amount of $350,000.00
plus GST by way of compensation. This would be in addition to the amount of
compensation of $50,000.00 plus
GST which, we understand, your client has agreed
to reimburse or pay to our client due to the premises at MM 5 now not being
available
to our client.
We look forward to hearing from you in relation to the
above.”
- On
about 14 October 2015, Mr Hedley and Mr van Veenendaal agreed to make certain
amendments to the Agreed Documents (“the Amendments”).
The
Amendments included, amongst other things (Ex. A/188, 190-91):
- (a) A variation
to the Agreement for Lease to reflect that “the Lessee’s contraction
[sic] will take physical possession”
of the Premises on 19 October 2015,
and the “rent commencement date” was to be 14 December 2015;
- (b) A variation
to the Agreement for Lease to alter the scope of the Lessor’s Works;
and
- (c) A variation
to the Lease to increase rent by $10,000 per annum for the term of the
Lease.
- On
15 October 2015, Mr Hedley sent an email to “Merry and Raymond”
confirming that “Mirvac will pay Leigh directly
for the work he is doing
and pay their contractor for the work they are doing...Please confirm you accept
this and if so we can have
it sorted out asap so that your fitout
can start today”: Ex. A/187B.
- On
15 October 2015, the Defendant paid the Plaintiff $313,500, being 33 per cent of
the total "Fitout Contribution" (as defined in
the Agreement for Lease).
- In
an email from Mr van Veenendaal to Mr Hedley sent 16 October 2015 (Ex. A/188),
the following appears:
“Hi Hilton
Further to recent conversations, I confirm the following in response to your
request for further contribution to the Lessee’s
fitout and in relation to
Raymond Lee & Co’s email below:
The additional works for Kowloon that you have requested the Lessor to undertake
is as
follows:
Item
|
Cost
|
Notes
|
Under slab drainage works
|
$35,000
|
Work undertaken by Lessee’s Contractor
|
Gas and potable water
|
$26,565
|
Work undertaken by Mirvac
|
Wet & Dry Fire
|
$59,141
|
Work undertaken by Mirvac
|
Addition support for Exhaust Hoods
|
$20,000
|
Work undertaken by Lessee’s Contractor
|
A/C changes
|
$104,000
|
Work undertaken by Mirvac
|
Electrical
|
$11,213
|
Work undertaken by Mirvac
|
Additional Mech Ventilation
|
$20,000
|
Work undertaken by Mirvac
|
Total
|
$275,919
|
|
It is proposed that the following variations be made to the Agreements for
Kowloon and Hong Kong Yum Cha to cover these additional
tenancy fit out
costs:
Mirvac will pay for the costs of the works outlined above;
The incentive for Hong Kong Yum Cha to be reduced by $100,000 and the rent
increased by $5,000 p.a. for the ten year term of the
lease;
The rent for Kowloon be increased by $10,000 p.a. for the ten year term of the
lease;
If Mirvac is unable to confirm an alternate premises for the Hong Kong Yum Cha
restaurant premises by the 1st July 2016 satisfactory
to your client (acting
reasonably) Mirvac will pay your client an amount of $300,000.00 plus GST by way
of compensation which include
the $50,000 plus GST which Mirvac has agreed to
pay to your client due to the premises at MM5 now not being available to our
client
and the costs incurred in relation to that tenancy;
and
The Lessee’s Contraction [sic] will take physical possession of the
Kowloon Premise [sic] (Shop 203-206) on Monday 19th October
2015 and the rent
commencement date will be 14th December 2015.”
- (The
parties agreed that the word “Contraction” should be read as
“Contractor”: Tcpt, 13 May 2019, p 35(23-25).)
- On
16 October 2015, Mr Hedley forwarded to Ms Ng and Raymond Lee & Co, a copy
of Mr van Veenendaal’s email. Ms Ng responded
as
follows:
“Hilton and Raymond,
We agreed to the proposed response below and please proceeding
accordingly.”
- Mr
Hedley forwarded to Mr van Veenendaal Ms Merry Ng’s email,
writing:
“Theo
Please see below and instruct Gadens accordingly.
Can you please ensure the second instalment of the contribution is paid asap as
the builder will be on site Monday.”
- On
16 October 2015, Ms Ng, on behalf of the Plaintiff, and on her own behalf,
agreed to the amendments. Her agreement was noted in
an email from her to Mr
Hedley and to Raymond Lee & Co, sent on 16 October 2015, a copy of which was
provided to Mr van Veenendaal
on the same date.
- On
19 October 2015, Gadens sent an email to Raymond Lee & Co, with attachments
that:
- (a) included
replacement pages for the Agreement for Lease and Lease to reflect the
Amendments; and
- (b) sought the
written confirmation by Ms Ng on behalf of herself and the Plaintiff that she,
and it, acknowledged, accepted and agreed
that the final terms between the
parties for the Lease of the Premises were as set out in the Agreed
Documents.
- The
letter, stated, amongst other things:
“1. We refer to your email of 14 October 2015 in response to our letter of
8 October 2015.
2. We are instructed that the parties have had further discussions regarding the
Premises and the proposed lease for a Yum Cha Restaurant
at the Centre. We are
instructed that the parties have agreed the following:
(a) ...
(b) The rent for the first year of the Term for the Premises is to be increased
to $242,858.10 per annum which will be payable on
and from 14 December 2015.
Again, to document this we propose to amend the signed Agreement for Lease (page
2) and the Lease (page
5) by inserting the attached replacement pages. Please
provide us with your client’s authority to insert the proposed replacement
pages by return.
...”
- There
was attached a document (Ex. A/218) that stated:
“Item 11 Opening Date
5 November 14 December
2015
Item 12 Opening Contribution
$1,500.00
Item 13 Design Approval Fee
$800.00
- On
19 October 2015, Mr van Veenendaal sent Mr Hedley an email and, with an
attachment entitled "Handover Notice" (Ex. A/221). The
email
stated:
“Please see attached signed Handover Notice acceptance form for S203/206,
Kowloon City. Handover has been accepted by the tenant
as of the 19th October
2015.”
- To
the email was attached a document headed “Site Inspection Handover”.
The date of the Site inspection was said to be
16 October 2015 and appears to
have been accepted on behalf of the Plaintiff: Ex. A/222.
- Ms
Ng admitted (in paragraphs 3 and 5 of her affidavit of 10 April 2019), that on
about 19 October 2015, the Defendant “formally
handed over the [Premises]
to the Plaintiff in order to enable the Plaintiff to begin “the
lessee’s fitout works”.
- On
23 October 2015, Raymond Lee & Co sent to Gadens (with a copy to Ms Ng and
Mr Hedley) an email on the following terms:
“Thank you for your email and your letter of 19 October. In relation to
Point 2 of your said letter, we are instructed that
the parties had agreed that
in the event that a Lease is entered into with respect to Premises for use a Yum
Cha Restaurant, your
client will reimburse our client for expenses thrown away
relating to the proposed Lease of Shop MM5 by way of a payment to our client
of
$50,000.00 plus GST. We note that we had raised this in an email to you on 13
October but had not been addressed by you. After
receipt of your letter of 19
October, we had raised this with our client's agent who had confirmed that this
had been agreed to and
expected an amended letter from you reflecting such
arrangement. Would you urgently confirm by return email that such an arrangement
is correct and is agreed to by your client.
We advise that subject to your confirmation of the above, our client is making
arrangements with respect to the Advice Certificates
required, the execution of
the amended pages of the Lease and the Agreement for Lease and the Registration
Fees for delivery to your
client.”
- On
26 October 2015, Gadens sent another email to Raymond Lee & Co attaching an
amended copy of the letter referred to above, which
was said to reflect a
further agreement between the parties. The email referred to a chain of emails,
all sent on 23 October 2015,
being an email from Mr Hedley to Mr van Veenendaal;
an email from Mr van Veenendaal to Mr Hedley; and an email from Raymond Lee
&
Co to Gadens. Also included was an amended copy of the letter dated 19
October 2015 to reflect further agreement between the Plaintiff,
the Defendant
and Ms Ng. (Relevantly, paragraph 2(b) of the letter dated 26 October was the
same as paragraph 2(b) of the 19 October
letter.) The letter required Ms Ng, as
the sole director and secretary of the Plaintiff, to acknowledge, accept, and
agree to, the
terms of the letter dated 26 October 2015 by signing and dating a
copy of the letter: Ex. A/195-197.
- The
letter dated 26 October 2015 specifically stated that “The rent for first
year of the Term ...which will be payable on and
from 14 December
2015”.
- On
26 October 2015, the Defendant paid the Plaintiff $313,500, being the second
instalment of 33 per cent of the total "Fitout Contribution"
(as defined in the
Agreement for Lease).
- On
30 October 2015, Raymond Lee & Co sent to Gadens, by email (and, apparently,
by courier), the copy letter dated 26 October
2015, and the further amended
pages of the Lease and Agreement for Lease for the Premises, both signed by Ms
Ng (which were said
to have been provided to replace the pages in the previous
document). The letter was also said to enclose the signed Legal advice
report,
Financial report and a cheque to the Department of Natural Resources and Mines.
In relation to the amended pages to the Lease
and Agreement to Lease, whilst the
“Commencing Date” (Item 7) and the “Terminating Date”
(Item 8) remained
incomplete, the “Opening Date” (Item 11) was
stated to be 14 December 2015. However, in the definitions, “Lease
commencing date” was said to mean “the Fitout Access Date”:
Ex. A/231A-231M.
- In
the “Legal advice report”, which is a document required to be
completed by a legal practitioner, in this case Raymond
Lee, and which was
signed by Mr Lee on 23 October 2015 and by another person, perhaps, Jenny Zhuang
(the signature is indecipherable)
on 30 October 2015, the legal practitioner
confirmed that he had provided, and the “lessee/assignee” certified
that “I
have received the explanations referred to... and have understood
them”, and advice on, among other things, the “term
of the
lease”, and “consequences of the prospective lessee/assignee ...
breaching lease conditions”: Ex. A/231J
– 231K.
- It
appears that on 30 October 2015, Ms Ng as “sole director [and]
secretary of Longjing” did acknowledge, accept and agree to the terms
of the letter dated 26 October 2015 from Gadens: Ex. A/197.
- By
email dated 16 November 2015 sent to Mr van Veenendaal, Mr Hedley forwarded an
email from Leigh Weber, who was carrying out the
fitout works on behalf of the
Plaintiff, in which he explained the reasons for the delays and proposed that
“due to delays
out of our control ... the works will not be completed on
the 14/12/15. I suggest a time extension from Mirvac” (earlier in
the
email, the extension proposed was “until 23/12”.): Ex.
A/236-238.
- In
an email sent on 17 November 2015, from Raymond Lee to Gadens, a request was
made to “urgently provide to our office a copy
of the Agreement for Lease
and the Lease executed by your client...”. Shortly thereafter, Gadens
responded that “[T]he
documents have not yet been signed by the Lessor and
are still being processed...” Ex. A/241A-241B.
- On
18 November 2015, Mr van Veenendaal sent an email to Mr Hedley under the heading
“Request for time extension for works to
Kowloon City” and stated
“I have asked Mirvac to look into the claim ... We need to ensure that the
tenant opens as close
to the 14 December as possible”: Ex. A/246.
- On
19 November 2015, a new shop location for the yum cha restaurant was
agreed.
- On
20 November 2015, an error in relation to the Marketing Levy in the signed lease
documents was detected and a request was made
for an amendment to Item 12 of the
Reference Schedule.
- On
23 November 2015, Mr Hedley sent an email to TKA Lawyers stating that the
Plaintiff “requires the services of a solicitor
in Brisbane to act on its
behalf to prepare sales contracts and licence agreement for a number of food
court tenancies...There are
7 businesses in total, so that will be 7 sales
contracts and 7 licence agreements...”: Ex. A/259A.
- Also
on 23 November 2015, Mr Hedley sent an email to Mr van Veenendaal stating the
following (Ex. A/260):
“As mentioned to you last week and the week prior, we urgently require
copies of the executed agreements for Kowloon City.
It is preventing LongJing [sic] entering into licence agreements with proposed
operators and it's reaching the point where one of
these tenants is losing
interest.
...”
- (There
was no evidence given by the Plaintiff of any “proposed operators”
or of any tenant losing interest.)
- On
24 November 2015, the Defendant executed the counterpart of the Agreement for
Lease and the Lease for the Premises and provided
it to the Plaintiff.
- It
was agreed, at the hearing, that amendments to the Lease that had been signed on
18 September 2015 by the Plaintiff and Ms Ng were
inserted into the Lease that
was signed by each of them as agreed amendments were made: Tcpt, 15 May 2019, p
216(8-46).
- As
has been stated earlier in these reasons, between 25 November 2015 and 2 March
2016, the Plaintiff engaged Thomas Kung or Thomas
Kung Lawyers to act as its
solicitors in respect of the Premises and to assist in drafting
sub-leases/licence agreements for prospective
tenants of the Premises. The
Plaintiff also engaged in the same period Mr Su, to assist with marketing and
obtaining prospective
tenants for the Premises.
- On
18 December 2015, the Plaintiff had not opened any part of the Premises for
trading.
- On
21 December 2015, Daryl Gabagas, a Development Manager at Mirvac, sent an email
to Hala Nagy, an accounts payable manager at Mirvac,
Fizzah Salahuddin, a
development assistant (finance) at Mirvac, and Rod Moynahan, the National
Director, Retail Delivery, at Mirvac,
stating:
“Further to our discussion on Friday, Mirvac Retail have requested that...
Longjing Pty Ltd be paid urgently
If payment is not made before Christmas closure this would result in Mirvac been
[sic] in breach of agreement with both Tenants
...”
- On
21 December 2015, Mr Gabagas sent an email to Fizzah Salahuddin and Rod Moynahan
stating:
“A bit of Good [sic] and bad news.
Only Diamond Properties will be paid this week and Longjing on the
6th”
- Also
on 21 December 2015, Mr Moynahan sent an email to Mr van Veenendaal, Andrew
Paterson and Mr Mutch stating:
“We have been begging to corporate and Treasury and no luck for
Longjing.”
- The
final fitout works were completed on 23 December 2015.
- On
11 January 2016, Melanie Hodge, the Centre Manager, sent an email to Mr van
Veenendaal, in which she stated (EX. A/663):
“Just spoke with Merry [Ng], they haven't opened as the licence with the
sub-tenant has not been finalised and is going back
and forth. She will be at
the centre on Wednesday and will meet with me to go through it further and
hopefully have more news. She
is hoping they will open on Friday or Next [sic]
week.”
- On
11 January 2016, the Defendant paid the Plaintiff $220,000, being the third
instalment of 23 per cent of the total "Fitout Contribution"
(as defined in the
Agreement for Lease).
- On
12 January 2016, Mr van Veenendaal forwarded Ms Hodge's email to Mr Hedley with:
"Hi Hilton, What's the status of this". Mr Hedley
responded later that same day
with: "People are only now coming back from their break and shops will
tentatively be opening in stages
likely from this Friday or Monday of next
week": Ex. A./663.
- On
13 January 2016, Ms Hodge sent an email to Mr Conlon and Mr van Veenendaal,
which stated (Ex. A/665A):
“...
Just spoke with Merry from Kowloon.
She has been advised by Hilton that rent is not payable until she opens and was
unaware of the current invoice and outstanding amount
of $19k.
She advised they have not finalised the details with the sub-tenants and are not
expected to open for another week or two.
She has not made payment for the furniture although believes it is in the
country and at the store.”
- On
14 January 2016 at 7.05 p.m., Ms Hodge sent an email and an attachment being a
tax invoice for outstanding rent to Ms Ng. Ms Hodge’s
email stated (Ex.
A/667A-667B):
“...
Further to our discussion yesterday please see attached a copy of the tax
invoice for outstanding rent. Please advise when payment
of $19,170.42 is to be
expected.”
- On
14 January 2016 at 7.37 p.m., Ms Ng forwarded Ms Hodge's email to Mr Hedley. Mr
Hedley forwarded on the email to Mr van Veenendaal
at 7.41 p.m. stating (Ex.
A/667A):
“...
Can we discuss this please.
Thanks
...”
- On
22 January 2016, the Defendant served a Notice to Remedy Breach of Covenant
(“the Breach Notice”) (Ex. A/692) on the
Plaintiff, that relevantly
stated:
“Breach Notice. On behalf of the Lessor we enclose a Notice to Remedy
Breach of Covenant (Notice) relating to the breaches
that have occurred under
the Lessee's lease of the above premises, namely:
1. The Lessee's failure to open the Premises for business during the core
trading hours of the Centre in accordance with clause 10.4(a)(1)
and clause 45.1
of the Lease, for the period 18 December 2015 up to and including 22 January
2016; and
2. The Lessee's failure to make payment of Rent and other occupancy charges
totalling $15,553.98 (Arrears)...
Opening the Premises for trade. We are instructed that the Lessor considers 7
days from the date of service of this letter to be
a reasonable timeframe within
which the Lessee is to commence trading at the Premises. If the breach is not
remedied within this
period, the Lessor reserves its rights to terminate the
Lease without further notice to the Lessee.
Time for Payment of Arrears. On behalf of the Lessor we demand payment of the
Arrears by the date which is 14 days from the date
of this letter. Payment must
be made to the office of the Centre Manager.
Consequences if Arrears are not paid. Please note that if full payment of the
Arrears is not made on or before the date which is
14 days after the date of
this letter, the Lessor reserves its legal rights in relation to the recovery of
the Arrears and the breach
by the Lessee of its obligations under the Lease.
Those rights may include institution of court proceedings for recovery of the
arrears
together with interest, without further notice to the Lessee.
...”
- The
Breach Notice provided:
“With reference to the lease of the Premises between Perpetual Nominees
Limited... and the Lessee... and the covenants by the
Lessee:
1. under clause 3 of the Lease, to pay to the Lessor the Rent in advance, on or
before the first day of each month, without set-off,
counter-claim, withholding
or deduction;
2. under clause 7 of the Lease, to pay for all services specific tenancy
charges, services and electricity charges;
3. under clause 9 of the Lease, to pay GST on any supply under or in accordance
with the Lease; and
4. under clause 10.4 and clause 45.1 [sic] of the Lease, to keep the Premises
open for business during the core trading hours of
the Centre,
and the breach by you of those covenants by failing to make those payments and
failing to open the premises for business during the
period 18 December 2015 up
to and including 22 January 2016, the Lessor gives you notice and requires you
to remedy those breaches
by opening the Premises for trade... and by paying to
it the amount outstanding...”
- Mr
Conlon gave instructions for the Breach Notice to be issued to the Plaintiff. He
said he did so because “the tenant wasn’t
trading and hadn’t
paid rent”: Tcpt, 14 May 2019, p 170(3-11).
- On
22 January 2016, Mr Hedley sent an email to Mr van Veenendaal which had attached
to it the notice of 22 January 2015, and which
stated:
“Really??”.
- Mr
Hedley gave evidence that he was “sure [I would have advised her to pay
[the outstanding rent] immediately”: Tcpt,
13 May 2019, p 65(9-12).
- (This
evidence is inconsistent with Ms Ng’s evidence, which I do not accept,
that she did not know that the Plaintiff was required
to pay rent, or that the
Defendant could deduct the outstanding rent from the Bank guarantee so that it
did not actually have to
pay the rent: Tcpt, 13 May 2019, p 78(29-44). It is
also inconsistent with her evidence, which I also do not accept, that he told
her that “We don’t even need to pay the money. Nothing we owe to
Mirvac, we’re not owing Mirvac anything”:
Tcpt, 13 May 2019, p
80(49) – p 81(1). It was also inconsistent with Ms Ng’s evidence
that Mr Hedley told her not to
worry about the rent: Tcpt, 14 May 2019, p
95(27-29).
- On
28 January 2016, Ms Merry Ng sent an email to Ms Hodge, which stated (Ex.
A/694):
“Apologies for missing your call yesterday and for not giving you an
updates on the late opening.
We also want to get Kowloon City open as quick as possible and we are doing our
best to finalising all the legal matters now.
We will have some of the furniture, like stools delivered tomorrow and the rest
will follow early next week and the opening should
follow after.
I will confirm again the date prior to the opening date.”
- On
1 February 2016, Mr Hedley sent to each of Mr Kung, Mr Su and Ms Ng an email
which stated:
“Alex, this is all super urgent as Merry is now under extreme pressure by
Mirvac to open these tenancies
Please ensure these contracts are signed and returned as soon as possible and
that these tenants open next week.
There is no reason for them not to open as they are fully fitted out and ready
to go.
Please also provide a written update on the balance of the tenancies and quite
[sic] to re-advertise for the remaining shops.”
- On
3 February 2016, there was a meeting between Mr Hedley, Mr van Veenendaal and Mr
Conlon. At this meeting, Mr Hedley outlined the
progress that had been
undertaken so far in relation to ascertaining the potential licensees; Mr Hedley
outlined that there were
three or four that could open within a relatively short
period of time; and he expected the Premises to be open within approximately
2
weeks. Mr Conlon stated that “Termination is not an outcome that Mirvac
desires” and asked how much more time did the
Plaintiff require to remedy
the breach, to which Mr Hedley responded “Two weeks from today would be
sufficient for Longjing
to open the Premises for trading”: Tcpt, 13 May
2019, p 65(49) – p 66(25).
- Mr
Conlon submitted, under cross-examination, that at the meeting, it was agreed
that if the Plaintiff opened with four licensees
and operated one shop itself,
within the agreed time frame, then the Defendant would not terminate the
Lease: Tcpt, 14 May 2019, p 175(19-24).
- Under
cross-examination, Mr van Veenendaal stated that at the meeting, no agreement
was reached that if the Plaintiff opened with
four licensees and operated one
shop itself, within the agreed time frame, then the Defendant would not
terminate the Lease. He expressed
this several times in answer to questions put
to him: Tcpt, 14 May 2019, p 151(8-11, 21-26, 42-47).
- His
evidence, under cross-examination by counsel for Longjing and also in answer to
my question on the topic, was that the agreement
that had been reached at the
meeting was that Mr Hedley had, at the meeting, indicated he would “come
back to us within 24
hours to say what - to say which tenancies he would have
open”: Tcpt, 14 May 2019, p 150(46) – p 151(4), p 152(7-8).
This
evidence appears consistent with an email dated 3 February 2016, at Ex. A/708A,
from Mr Hedley, to which reference is to be
made. This was pointed out to
counsel for Longjing during the course of the hearing: Tcpt, 14 May 2019, p
154(47) – p 155(4)).
- Under
cross-examination, Mr van Veenendaal also stated that such an agreement had been
made on, or at least by, 15 February 2016,
pursuant to the letter sent by Gadens
to Raymond Lee & Co on that date, which outlined the agreement that had been
reached: Tcpt,
14 May 2019, p 148(32-33). (The content of that letter is
outlined later in these reasons.)
- On
3 February 2016 at 1:56 p.m., Mr Hedley sent an email to Mr Su and Mr Kung as
follows (Ex. A/708A):
“Alex and Thomas,
I met with Mirvac today and I need to provide them with an update as to when the
operators of the shops will be opening within Kowloon
City.
Alex, can you please speak to all of the tenants and seek confirmation of when
they will be opening
Remember that we agreed to certain terms based on these operators opening
asap
Thomas,
Can you please send me return email confirming how many contracts have been
issued and when you are expecting these to be signed
and returned.
As you know this project was completed on 23 December and as of today no one has
opened.”
- On
3 February 2016 at 2:46 p.m., Mr Hedley sent an email to Mr Kung, Mr Su and Ms
Ng which stated (Ex. A/708B):
“Alex
Can you please call Thomas and clarify these details
It's becoming urgent that these operators are trading as our mutual client
LongJing are paying rent to Mirvac and no income is coming
in.
Alex
I need a written update from you as to the status of these deals and future
tenants.”
- On
4 February 2016, Mr Conlon and Mr van Veenendaal received an email from Ms Meri
Suleman, the Retail Lease Administrator, in which
she wrote (Ex. A/
709):
“Hi Ben and Theo,
The time for the Lessee to remedy the breach pursuant to the notice expires at
5pm, tomorrow Friday 5 February 2016.
Has there been any progress? If not, please advise how the lessor proposes to
move forward. The options are as follows:
1. Terminate the lease;
2. Commence action against the lessee to recover the rent / monies owing; or
3. Allow the lessee more time to remedy the breach.
Gadens will need to prepare the notice / letter (if required) and it would
therefore be prudent to advise them of the option the
lessor is likely to pursue
as soon as possible to allow them sufficient time to prepare the documentation
(if required).
Let me know if you need any further information.”
- On
5 February 2016, Mr Conlon responded to Ms Suleman's email in the following
terms (Ex. A/710):
“Sorry for the late reply.
...
Kowloon were supposed to be sending us a letter regarding the dates for trade
for each of their shops within Kowloon. Let's just
hold fire on this until we
see the letter.”
- In
an email dated 8 February 2016, sent by Raymond Lee & Co to Gadens, the
Defendant was informed that “4 Licence Agreements
have been issued ... our
client anticipates that 4 of the 7 shop [sic] will be open and trading by 28
February 2016”: Ex. A/712.
- In
an email dated 10 February 2016, Mr Hedley advised Mr van Veenendaal that
“more ads are appearing in the Chinese, Vietnamese
and Korean newspapers
this weekend...I’ll keep you posted in [sic] the level of enquiry”:
Ex. A/725.
- On
15 February 2016, Gadens sent correspondence to the Plaintiff and Ms Ng that
relevantly stated (Ex. A/ 737-738):
“We are instructed by our client that it has been in direct negotiations
with the Lessee regarding the breaches specific in
the Notice to Remedy Breach.
As a result of these negotiations the parties have agreed the following:
The Lessee has advised the Lessor that, pursuant to the Permitted Use and clause
A7.1 of the Lease, the Lessee has entered into four
licence agreements...
1. The Lessee has also advised that it will operate its own food stall within
the Premises bringing the total number of food stalls
within the Premises to
five (Food Stalls).
In reliance on the Lessee's representations as set out above, the Lessor agrees
to allow the Lessee further time within which to
open the Premises for business
and to keep the Premises open for business. The Lessor will allow the Lessee
until 5.00pm on Sunday
28 February 2016 to have all of the Food Stalls
operational, open for trade and to thereafter remain open for trade in
accordance
with clauses 10.4 and A5.1 of the Lease.
Nothing in the preceding paragraphs or the negotiations had between the Lessee
and the Lessor waives the Lessee's obligations further
to clause A7.1 of the
Lease. Without limitation, the Lessee is required to provide to the Lessor the
written certification required
further to clause A7.1(3) of the Lease.
The Lessor reserves its rights in this regard;
2. The Lessee must make payment of the Arrears listed in the Notice to Remedy
Breach on or before 5.00pm on 28 February 2016 (or
the next business day
thereafter); and
3. In the event the outstanding Arrears are not received in full as cleared
funds by the Lessor from the Lessee before 5.00 pm on
28 February 2016 (or the
next business day thereafter), the Lessor will call on the Bank Guarantee
further to clause 21.2 of the
Lease to recover its loss, without 2further notice
to the Lessee. In the event that the Lessor calls on the Bank Guarantee, the
Lessee
must comply with clause 21.3 of the Lease and replace the Bank Guarantee
or the proportion of the Bank Guarantee recovered by the
Lessee within 7 days of
receiving notice from the Lessor to do so.
Failure to comply with the Revised Obligations
If the Lessee does not comply with the Revised Obligations by the time and dates
set out in this letter, we are instructed that the
Lessor reserves its legal
rights in relation to the termination of the Lease. We are also instructed that
if the Lessor proceeds
to terminate the Lease, the Lessor will also withdraw its
offer to the Lessee for Premises known as Shops 262 to 264 trading as Hong
Kong
Yum Cha.”
- Ms
Ng gave evidence that she had received a copy of the letter dated 15 February
2016 and that she understood that it was an important
letter; that it contained
revised obligations that the Defendant required the Plaintiff to comply with;
that there had been discussions
regarding the breaches specified in the Breach
Notice; that as a result of statements made by the Plaintiff to the Defendant,
the
Defendant was prepared to give the Plaintiff “further time within
which to open the premises for business and to keep the premises
open for
business”; that the Plaintiff had until 5:00 p.m. on Sunday 28 February
2016 “to have all food stalls operational,
open for trade and thereafter
to remain open for trade”; and that if the Plaintiff did not pay the
outstanding arrears of rent,
“on or before 5:00 p.m. on 28 February 2016
or the next business day thereafter”, the Defendant would call on the bank
guarantee and if that occurred, the Plaintiff “was required to comply with
the Lease and replace the Bank guarantee or the
proportion of the bank guarantee
with the amount that had been claimed”; and that if the Plaintiff did not
comply with the
revised obligations, by the time and date set out in the letter,
“Gadens were instructed that Mirvac reserved its legal rights
in relation
to termination of the Lease”: Tcpt, 14 May 2019, p 102(16) – p
104(37).
- On
19 February 2016, Raymond Lee & Co sent a letter dated 18 February 2016, to
Gadens, that relevantly stated (Ex. A/751-752):
“...
We are instructed that our client had not advised that our client had entered
into four License Agreements with respect to food stalls
however, as set out in
our e-mail to you of the 8th of February 2016 four Licence Agreements had been
issued to prospective licencees
[sic]...
We also note that the Lessee proposes to operate the bar rather than a food
stall.
Would you please provide us with a statement of the ‘Outstanding
Arrears’. We will then confirm our client's instructions
in relation to
this. We have been instructed by our client that payments have been made to the
Lessor on or prior to entering into
the Lease and our client wishes to ensure
that such amounts have been taken into account.”
- Under
cover of an email dated 24 February 2016, sent by Gadens to Raymond Lee &
Co, the statement of outstanding arrears was provided.
- On
24 February 2016, Mr Greenwood sent an email to Mr Lee which relevantly stated
:
“We note your advice that Licence Agreements have been issued to
prospective Licensees but not yet executed.
...
We continue to reserve our client's rights.”
- On
25 February 2016, Mr Hedley sent an email to Raymond Lee & Co and Ms Ng as
follows (Ex. A/825):
“I spoke with Theo from Mirvac this morning and they require urgently a
response to Gadens most recent letter. Can you please
go back to them and
confirm the following (Merry you will need to review the below and either amend
or give Raymond formal instructions),
however based on advice received from
Longjings Brisbane based lawyer Thomas Kung we can confirm the following:
Two tenants will open on the 3rd of March, being the Chinese Sizzle Place
operator in tenancy 4, and the bar.
We anticipate but cannot confirm at this stage that a 3rd operator will open the
following week, being the Malaysian operator in
tenancy 3. That agreement is
close to being finalised and we will let you know as soon as its executed.
We have received an offer for the Asian Grocery site to be run as a combination
of butcher with Asian grocery items - can you please
confirm your acceptance of
this amended usage for this tenancy (we note that it will be subject to Lessors
final design approval).
We will await your instructions regarding this usage
prior to confirming the licence with the proposed tenant.
Longjing will keep Mirvac updated in writing via Hilton Hedley of Allied
Property Group on progress with respect to the other license
agreements every 48
hours so you are up to date as to where each deal is upto. There have been 2
weeks of full page colour advertisements
in the Chinese Newspaper and enquiries
and inspections are occurring regularly.
We also confirm that a cleaner has been engaged to clean the tenancy as
requested by Mirvac last week.”
- On
28 February 2016 by 5:00 p.m., the Plaintiff had not opened any of the Premises
for trading and had not paid rent.
- On
29 February 2016, Mr Hedley received an email which indicated that a prospective
licensee had received a copy of the Breach Notice.
He forwarded the email on to
Mr Van Veenendaal noting that it had “poisoned” a deal (Ex.
A/840):
“Naturally the question is:
How did a potential tenant for Kowloon City get their hands on this letter?
It has just poisoned a deal.
We need to discuss.”
- There
is no evidence about how the copy Breach Notice came into the possession of the
prospective licensee. However, as stated earlier,
the allegation that the
Defendant had given it was withdrawn at the hearing.
- On
29 February 2016, in an email sent to Gadens by Raymond Lee & Co (Ex.
A/838), it was confirmed that a licence that had been
expected to be executed by
a third party, on 26 February 2016, had not been executed “due to
unforeseen circumstances”
but was “due to be signed tomorrow”
and that “other Licences are progressing”. The email
concluded:
“As your client may appreciate from inspecting the Premises, our client
has made substantial progress and investment in the
Premises. Our client looks
forward to its continuing relation with your client.”
- Shortly
thereafter, Gadens responded (Ex. A/838-839):
“1. We note your advice that Licence Agreements have been
issued to prospective Licensees but not yet executed;
2. We note your advice that the Lessee proposes to operate the
bar rather than a food stall;
3. Please find the statement of outstanding arrears
attached.
We continue to reserve our client’s rights.”
- On
about 29 February 2016, Ms Ng received an email from the solicitor of a
potential licensee which enclosed a copy of the Breach
Notice. Mr Hedley then
forwarded the email referred to in the previous paragraph to Mr Van Veenendaal
in which he stated:
“Naturally the question is:
How did a potential tenant for Kowloon City get their hands on this letter?
It has just poisoned a deal.
We need to discuss.”
- On
1 March 2016, the Defendant served a notice of termination of lease (“the
Termination Notice”) (Ex. A/848-850) that,
relevantly, stated
:
“Perpetual... hereby gives you notice, pursuant to clause 18 of the Lease
described below, that as a result of the Lessee failing
to comply with the
Notice to Remedy Breach of Covenant dated 22 January 2016 within a reasonable
time, the Lessor hereby terminates
the Lease. The termination will take effect
on service of this Notice on the Lessee.”
- In
the Termination Notice, the Lease referred to was one said to have been
“signed by the Lessee on 2 October 2015”, the
“Commencement” was said to be 14 December 2015 and the
“Expiry” was said to be 13 December 2025.
- On
3 March 2016, at 6:12 p.m., Mr Hedley sent an email to Ms Hughes and to Mr van
Veenendaal requesting “you undo or reverse
the breach”. He pointed
out that the losses that the Plaintiff was likely to suffer was $1.4 million and
stated that “the
domino effect of this is catastrophic”: Ex.
A/909.
- There
is evidence that whilst the Plaintiff was in negotiations with a number of
different potential licensees, none of them had signed
any proposed Licence
Agreement sent by, or on behalf of, the Plaintiff. As Ms Ng put it, “I
believe you're in negotiation at
that time and you hoping that that will
happen”: Tcpt, 14 May 2019, p 106(17-26).
- I
note that on 3 March 2016, in an email exchange between Thomas Kung Lawyers and
Mr Hedley, it was said that on 1 March and 2 March
2016 respectively, two
potential licensees had each signed a “licence to occupy”. On 3
March 2016, Mr Hedley forwarded
that email to Ms Hughes, and copied in Mr van
Veenendaal: Ex. A/909-911. It is difficult to accept that what was stated
correctly
records what had occurred as no such “licence[s] to
occupy” formed part of the Plaintiff’s evidence relied upon
at the
hearing.
- In
her evidence, in answer to questions from the Bench, Ms Ng said (Tcpt, 14 May
2019, p 110(12-31):
“Q. Ms Ng, I'm having some difficulty understanding some of your evidence.
You told Mr Bova that you had several conversations
I think principally with Mr
Hedley
A. Yes.
Q. in which he told you that effectively Mirvac would be satisfied if you opened
one or two shops. Is that what you told me?
A. At the later stages yes, when we are very late.
Q. Yes, and
A. Because they push up to open as - yeah.
Q. Yes, and you told Mr Bova that the conversations that you had with Mr Hedley
about this matter
A. Yes.
Q. were contradicted by, for example, the letter sent to you I think on 15
February 2016.
A. Yes.
Q. You also told Mr Bova that your conversation with Mr Hedley in your
affidavit
A. Yes.
Q. was a conversation that you recollect?
A. That I - yes.
Q. That you remember, and also that I think you said you thought that the
conversation occurred after the letter of 15 February 2015
from Mirvac to
you.
A. Yes.
Q. You also said to Mr Bova that despite all of this
A. Yes.
Q. series of events
A. Yes.
Q. you did not open any shops at all. Have I understood your evidence
correctly?
A. Yes I did not. I was late but I intend to open it but I was there on the day
that, that, that they put the, the barricade on the
shop.
Q. The simple fact is
A. Yeah.
Q. as I understand your evidence, is that even if you believed that you only had
to open one shop
A. Yes.
Q. you didn't even open one shop, did you?
A. Not on time.
Q. That is, you did not open one shop by 5pm on 28 February 2016?
A. No.
Q. Do you agree or disagree?
A. (No verbal reply)
Q. You did not open any shop
A. Yes.
Q. by 5pm on 28 February 2016, is that right?
A. Yes.
Q. And you knew that whether it was one shop or all of the shops that was the
last date by which you were required to open one or
more than one of the shops.
Have I understood your evidence correctly?
A. Yes.”
- On
11 May 2016, the Defendant re-let the Premises to a new
tenant.
The Lease Documents
- Counsel
for the parties identified the following provisions of the Agreement for Lease
of the Premises (Ex. A/261-304):
- (a) The
Reference Schedule – identified the Defendant as “The Lessor”,
the Plaintiff as “The Lessee”
and Ms Ng as “The
Guarantor” (Items 2, 3 and 4); “The Fitout Period” –
Eight (8) weeks (Item 8); “The
Opening Date” as 14 December 2015
(Item 11);
- (b) Agreed
Terms (Clause 1), which defined:
“Fitout Access Date means the date
specified in the notice given by the Lessor under clause 4.2.
Fitout Contractor means a contractor engaged by the Lessee to carry out
the Fitout Works (or any part of them) and includes its employees and
subcontractors.
...
Fitout Period means the period of time set out in Item 8
commencing on the Fitout Access Date.
...
Fitout Works means the works to be carried out by the Lessee to the
Premises to fit out and stock the Premises for the Lessee’s occupation
and
use.
Fitout Contribution means the sum of $950,000.00 plus GST.
...
Lease means the lease of the Premises between the Lessor and the Lessee
to be granted under this agreement in the form of Annexure A.
Lease Commencing Date means the Fitout Access Date.
...
Lessor’s Works means the development of the Centre in accordance
with the Development Plan and the Fitout Guide...
...
Opening Date means the date set out in Item 11.
...
Rent Free Period means the period starting on the Lease Commencing Date
and ending on the earlier of:-
(a) the last day of the Fitout Period; and
(b) the day on which the Lessee first trades from the
Premises.
(c) Clause 3 referred to “Lessor’s Works” and provided that
the Defendant was required to carry out works to the
Premises.
(d) Clause 3.4 referred to “Works Completion
Date”
“(a) The anticipated time for Substantial
Completion of the Lessor’s Works is the Opening Date.
...”
(e) Clause 4.2 – Fitout Access Date
(a) The Lessor must give to the Lessee a notice
specifying:
(1) the Fitout Access Date; and
(2) the last day of the Fitout Period.
(b) The notice under clause 4.2(a) must be given at least fourteen (14)
[days] before the Fitout Access Date specified in it.
(c) The Lessor may vary the Fitout Access Date by notice to the Lessee.
(1) less than 5 Business Days after the date on which the variation notice is
given; or
(2) earlier than the date set out in the notice given under clause 4.2(a).
...
(e) The Fitout Access Date must be a date which allows for expiration of the
Fitout Period on or before the Opening Date.
(f) Clause 4.3 – Lessor’s Works during Fitout
Period
(a) The Lessee acknowledges that the Lessor may complete
the Lessor’s Works during the Fitout Period and the Lessee may not
make
any Claim arising out of the Lessor’s activities in that regard, subject
to the Lessor complying with clause 4.3(c).
(b) The Lessee and Fitout Contractor must not interfere with or delay the
activities of the Lessor and the Lessee and the Fitout
Contractor must submit to
the reasonable directions of, and be under the control of, the
Lessor.
(g) Clause 4.6(a) – Access:
4.6 Access
(a) If:
(1) the Lessor has approved the Fitout Plans
and Specifications;
(2) the Lessee provides evidence to the Lessor that the Lessee has obtained all
required Lessee’s Approvals;
(3) the Lessee has complied with clauses 5 and 13 and provided the documents
required under those clauses;
(4) the Fitout Contractors have completed the Lessor’s required safety
induction processes; and
(5) the Lessee has paid the Design Approval Fee, any amounts payable under
clause 3.6 and any amounts payable under the Fitout
Guide
the Lessor must, from the Fitout Access Date, provide
the Lessee with access to the Centre on such days and during such hours as the
Lessor reasonably determines to enable the Lessee to carry out the Fitout Works
in accordance with the approved Fitout Plans and
Specifications.
(h) Clause 4.7 – Conduct of Fitout Works
(a) The Lessee must cause the Fitout Works to be carried
out:
(1) promptly after the Lessee obtains access to the Premises under clause
4.6;
(2) in accordance with:
(A) all Lessee’s Approvals;
(B) the approved Fitout Plans and Specifications (including any conditions of
that approval)
(C) the Fitout Guide;
(D) the Lessor’s reasonable directions (including, for example, directions
about the way in which the Lessor’s Fitout
Contractors take access to the
Premises or conduct in the Fitout Works);
(3) in a good and workmanlike manner by experienced contractors approved by the
Lessor (which must not be unreasonable withheld);
(4) at its own costs in all respects.
(b) The Lessee must complete the Fitout Works and stock the business ready for
commencement of trade by the Opening Date. To avoid
doubt, the obligation of the
Lessee under this clause 4.7(b) is an essential term of this agreement,
the breach of which entitles the Lessor to take action including termination of
this agreement
and/or claiming on the Bank Guarantee.
(i) Clause 4.9 – Commencement of Trading
Except with the prior approval of the Lessor (which is
at its absolute discretion), the Lessee must:-
(a) not trade from the Premises before the Opening date;
(b) trade from the Premises on and from the Opening
Date.
(j) Clause 6.1 – Fitout Contribution – Payment
by Lessor
Subject to clause 6.4 and the Lessee not being in
default of this Agreement or the Lease, the Lessor will pay the Fitout
Contribution to the Lessee as
a contribution to the Lessee’s Costs of
carrying out the Fitout Works, payable by way of
instalments
(k) Clause 7 – Rent Free
7.1 Lessor to Allow
(a) This clause 7.1 applies despite any provision of the Lease.
(b) Subject to clause 7.2, the Lessor waives the Lessee’s
obligation to pay Rent, Lessee’s Proportion of Operating Costs and
Marketing Levy during
the Rent Free Period when the Lessee has provided to the
Lessor:
(1) the Lease in triplicate duly executed by the Lessee and if applicable, the
Guarantors;
(2) the Bank Guarantee in accordance with clause 21 of the Lease;
(3) the certificates of currency in accordance with clause 12 of the
Lease;
(4) if the Lessor’s waiver under this clause is consideration for a
taxable supply, a tax invoice in accordance with clause 9 of the Lease;
and
(5) where required by the Lessor, any other Costs, certificates, documents or
other items to be provided by the Lessee under or in
relation to the Lease on
[or] before the Lease Commencing Date.
7.2 refund of Waived Amounts
If this Lease is at any time terminated by reason of the Lessee’s default,
the Lessee must immediately pay to the Lessor the
Waived Amount as a liquidated
debt.
7.3 No Prejudice
The Lessee’s obligation to make a payment under clause 7.2 does not
affect any other rights or remedies which the Lessor may have against the Lessee
in respect of the termination of the Lease.
(l) Clause 9.1 provided:
9.1 Grant
With effect from the Lease Commencing Date, the Lessor must grant to the Lessee
and the Lessee must take from the Lessor a lease
of the Premises for a term
commencing on the Lease Commencing Date at the rent and on the covenants, terms
and conditions contained
in the Lease.
(m) Clause 9.2(a)(1) provided that “simultaneously with the execution and
delivery of this agreement, the Lessee must deliver
to the Lessor or the
Lessor’s solicitor the Lease in triplicate correctly executed by the
Lessee and the Guarantors (if any).”
(n) Clause 9.3 provided:
9.3 Lessor and Lessee bound
(a) The obligations of the Lessor and the Lessee under the Lease are not
conditional or dependent upon the preparation or execution
of the Lease and are
not affected by any default or delay in or waiver or extension of time for the
preparation and execution of
the Lease.
(b) Until the Lease has been prepared and executed I accordance with clause 9.2
the Lessor and the Lessee shall be deemed to take
the benefit of and be bound by
the provisions of the Lease as if all formalities relating to the preparation
and execution of the
Lease had been complied with.
(o) Clause 12.1 provided:
12.1 Liability of Guarantor
(a) The Guarantor acknowledges that the Lessor has entered itno this agreement
at the Guarantor’s request.
(b) The Guarantor is liable to the Lessor if the Lessee breaches this agreement
or the Lease and must pay the Lessor any money for
the Lessor’s loss
arising from the Lessee’s breach of this agreement or the Lease.
(c) The Guarantor, as a separate undertaking, indemnifies the Lessor against the
Lessor’s loss arising from the Lessee’s
breach of this agreement or
the Lease.
(p) Clause 13 provided:
13.2 Use of Bank Guarantee
The Lessor may, without notice to the Lessee, recover from the Bank Guarantee
any Cost incurred or loss suffered by the Lessor if
the Lessee breaches this
agreement or the Lease.
13.3 Replacement
The Lessee must either replace the Bank Guarantee or the proportion of the Bank
Guarantee recovered by the Lessor in accordance with clause 13.2 within 7
days of receiving notice from the Lessor to do so.
(q) Clause 17 provided – Default
17.1 Events of Default
(a) The following events are events of default:
(1) breach of agreement – either party commits or permits to occur
any breach or default in the due and punctual performance of any of the
provisions
of this agreement;
(2) Insolvent – a party is insolvent; and
(3) mortgage powers – any of the business affairs or undertaking of
a party is taken over by a receiver under any mortgage, charge or debenture.
(b) If an event of default occurs:
(1) the non-defaulting party may terminate this agreement by notice in writing
to the other party;
(2) the termination will be effective from the date of the notice;
(3) any termination will not affect any action or other right or remedy of the
non-defaulting party; and
(4) on giving notice, the non-defaulting party will be freed and discharged from
any action or demand by or obligation under this
agreement.
17.2 Notice of Default
Before exercising any right under clause 17.1, the non-defaulting party
must give written notice to the defaulting party setting out details of the
event of default which has occurred.
17.3 Content of Notices
A notice given under clause 17.2 must require the defaulting party
to:
(a) rectify the event of default within a reasonable time if the event of
default is capable of rectification; or
(b) pay compensation to the reasonable satisfaction of the non-defaulting party
(as specified in the notice) in lieu of rectification
if the event of default is
not capable of rectification but that payment of compensation will result in the
non-defaulting party
being restored to the position in which it would have been
had the event of default not occurred.
within the period reasonably specified by the non-defaulting party in the notice
(that period to be at least 15 Business Days).
17.4 Compliance with Notice
If:
(a) the notice given under clause 17.2 requires the defaulting party to
comply with either clause 17.3(a) or clause 17.3(b); and
(b) the defaulting party complies fully with the notice,
the non-defaulting party must not exercise any right under clause 17.1 or
any other provision of this agreement as a result of any default which has
occurred.
17.5 Damages
If a party terminates this agreement under clause 17.1 then the party
will be entitled to recover damages from the defaulting
party.
(r) Clause 18 provided:
18.1 Form of Notice
A notice given by a party under this agreement:
(a) must be in writing;
(b) may be signed by the solicitor for that party or any person authorised by
the party (and in the case of the Lessor can be given
by its tenancy
co-ordinator or project manager);
(c) is sufficiently served on a party if left at or posted to the address or
sent to the facsimile number of that party set out in
Item 2, 3 or 4;
and
(d) following the Fitout Access Date, is sufficiently served on the Lessee if
left at the premises.
18.2 Time of Service
A notice is taken to be given:
(a) if sent by post, on the fourth day after posting; and
(b) if sent by facsimile, on the next Business Day after it is sent unless the
sender is aware that the transmission is impaired.
(s) Clause 21.5 provided:
21.5 Entire Agreement
This agreement comprises the whole agreement between the parties in relation to
the letting of the Premises and supersedes all previous
negotiations,
understandings and agreements.
- Neither
counsel relied on Clause 16 of the Agreement for Lease (a matter I raised at the
hearing): Tcpt, 15 May 2019, p 209(17-23).
Clause 16 provided a process for
dispute resolution, as follows:
“16 Disputes
16.1 Dispute resolution
If a Dispute arises (excluding any dispute as to the proper construction of the
terms of this agreement or breach or termination
of this agreement) a party may
not commence any court or other proceedings relating to the Dispute (but
excluding urgent interlocutory
relief) unless that party has first complied with
this clause 16.”
- Accordingly,
as the proceedings continued, nothing more needs to be said about it.
- Counsel
for the parties identified the following provisions of the Lease of the Premises
(Ex. A/305-374):
- (a) The
Reference Schedule – identified the Defendant as “The Lessor”,
the Plaintiff as “The Lessee”
and Ms Ng as “The
Guarantor” (Item5); The Term – Ten (10) years (Item 6); The
Commencing Date (Item 7) was not
completed; The Terminating Date (Item 8) was
not completed; The Rent (Item 9); The Core Trading Hours (Item 13);
- (b) Clause A1.5
of the Lease provided:
Assignment and Sub-Licensing, stated “[t]he Lessee
may assign this licence to a person to whom the Lessee assigns the Lease
if that
assignment of the Lease has been approved by the
Lessor”.
(c) Clause A5.1 – Extended Trading Hours
A5.1 Extended Trading Hours
(a) Subject to clause A5.1(b), it is agreed that whilst the business conducted
at the Premises continues to trade as “Kowloon
City” then despite
the provisions of clause 10.4(a)(2) and 10.4(a)(4) the Lessee may trade from the
Premises between the hours
of 11.00am and 9.00pm seven days a week (unless
prohibited by law) at no extra costs to the Lessee. For the avoidance of doubt,
if
the Lessee trades after 9.00pm on any day the Lessee will be required to pay
the Lessor’s Costs in accordance with clause 10.4(a)(4).
(b) The Lessee must:
(1) only allows [sic] its customers to enter the premises from the Town Walk
entrance to the premises during such extended trading
hours;
(2) close the internal mall entrance to the Premises whenever the internal mall
is closed to the public during such extended trading
hours;
(3) notify Centre Management prior to the Lessee proposing to trade outside of
the Core Trading Hours; and
(4) despite clause A5.1, ensure that lights both within and external to the
Premises are on and are illuminating the premises during
the Centre’s Core
Trading Hours.
(c) Clause 10.4(c) is deleted and replaced with the following:
“(c) The Lessor is not required to provide the Lessee with access to the
common areas (including toilets) outside the Core
Trading Hours or outside the
extended trading hours in clause A2;”
(d) Clause A7.1 – Consent to Licence Parts
(a) It is agreed that whilst Longjing Pty Ltd CAN 167
130 181 is the Lessee under the Lease then despite the provision of clause
14.1(b)
the Lessee may licence part only (and not the whole) of the Premises to
a maximum of six (6) licensees (other than franchisees) provided
that the
Lessee:
(1) gives to the Lessor prior notice of the Lessee’s intention to licence
a part of the Premises to a licensee;
(2) is not in default under this Lease other than a default that has been
remedied by the Lessee or waived by the Lessor;
(3) certifies in writing to the Lessor that:-:
(A) the licensees’s proposed use of
that part of the Premises is strictly in accordance with the terms of the
Permitted Use;
(B) the terms of the licence agreement are consistent with this Lease;
(C) the licence agreement terminates on the earlier
of:
(i) a day not later than one day before the Terminating Date; and
(ii) earlier termination of this Lease; and
(4) Indemnifies and keeps the Lessor indemnified against
all Claims arising from the:
(A) occupation and use of the Premises;
and
(B) conduct of the licensee’s business from the
Premises
(b) The Lessee acknowledges that a licence which is
allowed to be granted under this clause:-
(1) operates in contract only and does not grant an estate or interest in the
Premises to the licensee;
(2) does not operate as an assignment of this Lease or the grant of a
sublease;
(3) does not in any way affect the enforceability against the Lessee of the
Lessee’s covenants and obligations under the Lease;
and
(4) must not contain provisions which would cause the Lessee to be in breach of
its covenants and obligations under this Lease and
to the extent it would, the
relevant provisions of the Licence are of no force or effect.
(c) The Lessor may accept payment from the Licensee of the Rent or other amounts
owing by the Lessee under this Lease without prejudicing
or affecting the
Lessor’s rights against the Lessee or affecting the operation of any
provisions of this Lease or being deemed
to have consented to an assignment or
sublease of this Lease to the Licensee.
(e) Clause 1 – Agreed terms – “Agreement for Lease;
“Commencing Date”; “Core Trading Hours”
Agreement for Lease means the deed entered into
between the Lessor and the Lessee contemporaneously with this Lease.
Commencing Date means the commencing date set out in Item 7.
Core Trading Hours means the core trading hours of the Centre set out in
Item 13(b) but excludes those hours on Christmas Day, Good Friday and any
other public holiday which the Lessor designates from time to
time.
(f) Clause 2.1 provided:
2.1
Grant
Subject to the provisions of this Lease, the Lessor:
(a) leases the Premises to the Lessee; and
(b) grants to the Lessee the right to use the Services and the Common Areas in
common with others
for the Term commencing on the Commencing Date and terminating on the
Terminating Date.
(g) Clause 3 – Rent provided:
3.1 Rent
(a) The Lessee must pay the Rent to the Lessor by equal monthly instalments in
advance.
(b) The Lessee must pay:
(1) the first instalment on the Commencing Date; and
(2) thereafter an instalment on the first day of each subsequent month of the
Term.
(c) If necessary, the Lessor and Lessee must apportion the first and last
instalments of rent on a daily basis.
(h) Clause 3.2 was headed “Turnover Rent”. It provided that (a)
“if Item 9(b) says that the Lessee is obliged to
pay Turnover Rent, the
Lessee must pay Turnover Rent to the Lessor in addition to the Rent”; and
that (b) the Turnover Rent
for each Accounting Year is the positive amount, if
any, in accordance with a formula that was outlined in the clause, and does not
need to be repeated in these reasons.
(i) Clause 6 – The Term of the Lease was incomplete except as to the
year.
(j) Clause 7 – Utilities provided:
7.1 Specific tenancy charges
The Lessee must pay:
(a) to the relevant authority all rates, taxes and other charges imposed on or
in relation to the Lessee’s use of the Premises,
the Lessee’s
Property and Permitted Use; and
(b) to the Lessor, to the extent not included in clause 7.1(a), the
Lessor’s Costs for trade waste, water and the other Costs
which the lessor
reasonably determines to have been incurred in respect of the Premises as a
result of the Lessee’s use of
the Premises.
7.2 Services
(a) The Lessee must pay for all Services separately connected and supplied to
the Premises or connected and supplied to the Centre
and separately metered to
the Premises, including water, electricity, gas and telephone.
(b) The Lessee must pay for the Cost of the Installation of meters to separately
service the Premises if:
(1) required by the Lessor (acting reasonably); or
(2) requested by the relevant Authority.
(c) The Lessee must pay the Lessor for all Services supplied to the Premises by
the Lessor. If a Service is supplied to multiple
premises in the Centre and not
separately metered, the Lessee must pay its share of the Lessee’s cost of
supplying that Service.
The Lessee’s share is the proportion that the
gross lettable area of the Premises stands to the gross lettable area of all
premises in the Centre that unmetered Service from time to time.
7.3 Payment of electricity charges
(a) The Lessor advises that, for the purposes of section 20F of the
Electricity Act 1994:
(a) the electricity consumed by lessees of the Centre in their premises is
metered separately to the electricity consumed in the
Common Areas;
(b) some air conditioning equipment provides conditioned air to both Common
Areas and to premises occupied by lessee of the Centre;
(c) the electricity that is consumed by the air conditioning equipment which
provides conditioned air to both Common Areas and to
premises occupied by
lessees of the Centre is apportioned on a floor areas basis;
(d) the total Common Areas electricity consumption is worked out by deducting
form the toal electricity consumed at the centre, the
sum of:
(1) the electricity consumed by lessees of the centre in their premises; and
(2) that part of the electricity consumed by the air conditioning equipment that
is apportioned to premises occupied by tenants of
the Centre; and
(3) the Lessee must pay its proportion of the electricity consumed in the Common
Areas in the manner described in clause 7.3.
(k) Clause 10.4 (a) and (d) provided:
10.4 Core trading hours
(a) The Lessee:
(1) must keep the Premises open for business during the Core Trading Hours
unless prohibited by law;
(2) must not open the Premises for business outside the Core Trading Hours
without the Lessor’s prior consent;
(3) must not open the Premises for business if prohibited by law; and
(4) must pay the Lessor’s Costs of opening the Centre at the
Lessee’s request outside the Core Trading Hours.
...
(d) If the Lessee does not observed its obligations under clause 10.4(a)(1),
then for each hour (or part of an hour exceeding 15 minutes) that the Lessee
is in breach, it must pay to the Lessor the sum of $100.00
as any by way of
additional rent.
(l) Clause 14.1 provided:
Clause 14.1 Consent
(a) The Lessee must not assign this Lease without the Lessor’s prior
consent (such consent not to be reasonably withheld).
(b) Except or an assignment with the Lessor’s consent under clause 14.1(a)
or a licence with the Lessor’s consent under
clause 14.9, the Lessee must
not part with the possession of the Premises.
(c) To avoid doubt, the Lessee may not sublet the whole or part of the
Premises.
(m) Clause 15.1 provided:
15.1 Quiet Enjoyment
Except as this Lease otherwise provides, the Lessee may peacefully occupy the
Premises for the term without interruption or disturbance
by the Lessor provided
the Lessee pays the Rent and other money payable and complies with the
Lessee’s obligations under this
Lease.
(n) Clause 18 provided:
18 Default
18.1 Essential Terms
The obligations of the Lessee under clauses 3, 6, 7, 8, 9, 10.1, 10.4, 11.2,
11.4, 11.5, 12.1, 12.2, 14.1, 14.7 and 21 of this Lease are essential terms.
Other obligations under this Lease may also be essential terms.
18.2 Lessor’s Right to Terminate
The Lessor may terminate this Lease if the Lessee:
(a) Is Insolvent;
(b) ceases or threatens to cease to carry on business from the Premises;
(c) repudiates this Lease;
(d) does not comply with an obligation under this Lease (and if the Lessor is
required to send a notice under any law in relation
to that breach, the Lessee
does not comply with that notice).
18.3 Damages
(a) If the Lessor lawfully terminates this Lease for any reasons (including, for
example, for breach of a non-essential term), the
Lessor may recover from the
Lessee any loss Cost or damages in connection with:
(1) the Lessee’s breach of this Lease; and
(2) the termination of this Lease
including:-
(3) the Lessor’s loss of the benefit of the Lessee performing the
Lessee’s obligations under this Lease from the date
of termination until
the Terminating Date; and
(4) the value of any Incentive paid or allowed to the Lessee or the
Lessee’s predecessor in title under this Lease (including,
for example,
any cash incentive, rent free period or redcued rent period).
(b) If the Lessor terminates this Lease, the Lessor must take reasonable steps
to mitigate the Lessor’s Cost, loss or damage.
18.4 No waiver
(a) The Lessor’s failure to exercise the Lessor’s rights or delay in
exercising the Lessor’s rights arising from
the Lessee’s breach is
not a waiver of that default.
(b) A demand for or acceptance of any overdue payment does not prevent the
Lessor from exercising or enforcing the Lessor’s
other rights under this
Lease.
18.5 Performance of obligations
(a) Subject to clause 18.5(b), the Lessor may at its election perform any
obligations of the Lessee under this Lease which the Lessee
fails to perform
and:-
(1) may for that purpose enter onto the Premises; and
(2) the Lessee must pay to the Lessor any Cost which the Lessor incurs in
performing the obligation immediately upon demand by the
Lessor.
(b) Before exercising its powers under clause 18.5(a), the Lessor must give
notice to the Lessee of its failure to perform the obligation
and allow the
Lessee a reasonable opportunity to remedy its failure. However, the Lessor does
not need to give a notice or allow
an opportunity in the case of
emergency.
(o) Clause 20.1 and 20.2 provided:
20.1 Liability of Guarantor
(a) The Guarantor acknowledges that the Lessor has entered into the Lease at the
Guarantor’s request.
(b) The Guarantor is liable to the Lessor if the Lessee breaches this Lease and
must pay the Lessor any money for the Lessor’s
loss arising from the
Lessee’s breach of this Lease.
(c) The Guarantor, as a separate undertaking, indemnifies the Lessor against the
Lessor’s loss arising from the Lessee’s
breach of this Lease.
20.2 Extent of Liability
The Guarantor is liable under clause 20.1 even:
(a) if the Lessor does not make a demand of or sue the Lessee;
(b) if this Lease is varied;
(c) if this Lease is unregistered; or
(d) after this Lease ends, for any breach that occurred before this Lease ends
or arises from this Lease ending.
(p) Clause 21.1 provided:
21.1 Giving of Bank Guarantee
The Lessee must give the Bank Guarantee to the Lessor on or before the
Commencing Date.”
(q) Clause 21.2 provided:
21.2 Use of Bank Guarantee
The Lessor may, without notice to the Lessee, recover from the Bank Guarantee
any Cost incurred or loss suffered by the Lessor if
the Lessee breaches this
Lease.
(r) Clause 21.3 provided:
21.3 Replacement
The Lessee must either replace the Bank Guarantee or the proportion of the Bank
Guarantee recovered by the Lessor in accordance with
clause 21.3 within 7 days
of receiving notice from the Lessor to do so.
(s) Clause 25.7 provided:
25.7 Entire agreement
This Lease and the Agreement for Lease comprises the whole agreement between the
parties in relation to the letting of the Premises
and supersedes all previous
negotiations, understanding and agreements.
(t) Clause 25.9 provided:
25.9 Construction
In the interpretation of this Lease no rule of construction applies to the
disadvantage of one party on the basis that that party
prepared the
Lease.
- (It
has been necessary to refer all of these Clauses as they were referred to by one
or both of the parties during the course of the
proceedings.)
- Mr
Hedley, although he did not read the Agreement for Lease or the Lease, said that
he understood that there was a rent free period
which commenced after the
opening of the relevant restaurants and which was distinct from the fitout
period in which the tenant took
possession in order to fit out the Premises:
Tcpt, 13 May 2019, p 31(11) – p 32(25).
The verbal
representations that are relied upon by the Plaintiff
- According
to Mr Hedley, on 22 January 2016, he had a conversation with Mr Van Veenendaal
in which the latter was asserted to have
said in relation to the Breach Notice
that:
“Don't worry. We are just protecting ourselves in the event Longjing never
opens the food court. As long as you get 1 or 2
shops open then this will all go
away.”
- During
the same conversation Mr Hedley says that he said:
“We are yet to agree a revised opening date given we only completed the
fitouts on the 23rd of December... The 1 month deposit
bond Longjing have
already paid covers this period anyway so technically we are not in breach
because of any shortfall in the rent.
Once we agree a revised opening date we
can start paying rent from then....”
- Mr
van Veenendaal is said to have responded :
“Mate it will not be a problem. I'm not worried about the rent arrears as
we can pay that from the bond... If they just see
progress with getting the food
court open for trading all will be good. I know you guys are doing everything to
get it open and finishing
the job 2 days before Christmas doesn't help
things.”
- It
was submitted that the representations said to have been made by Mr van
Veenendaal, that the Defendant would not exercise its rights
under the Breach
Notice, was that if the Plaintiff showed it was taking steps to open at least
one, or two, food stalls, and would
satisfy, or pay, the rental arrears from the
deposit bond, or bank guarantee, the Defendant would not seek to rely upon the
Notice.
(The Plaintiff referred to these as “the January
Representations”.)
- Mr
van Veenendaal denied that he made any of the January representations said to
have been made by him.
- Mr
Hedley also gave evidence that on 15 February 2016, he had another meeting with
Mr van Veenendaal, and Mr van Veenendaal had said:
“Regarding the breach notice all we need to see is that you have at least
one licensee signed up very soon. As for the rental
arrears we can pay this from
the bank guarantee or from the deposit bond provided for the yum cha
restaurant.”
“As I have told you, don't worry about the default notice. We will not
terminate as long as you show that you will be able
to have one licensee signed
up soon. We just need to see that you are close. We know the first licensee is
the hardest to get and
that after that people are happier to sign
up.”
- The
Plaintiff referred to these representations as “the February
Representations”.
- Mr
van Veenendaal denied that he made any of the February representations said to
have been made by him. He said that whilst he was
aware of the contents of the
Breach Notice, he did not have any discussion with Mr Hedley about its contents
on 22 January 2016.
He accepted that there were discussions on 3 February 2016
in relation to the time by which the Plaintiff was to open the Premises
and make
payment of the arrears listed in the breach notice: Tcpt, 14 May 2019, p 135(35)
– p 136(44).
- It
was in relation to the January representations and the February representations
that the parties were in substantial dispute.
- Counsel
for the Plaintiff criticised the evidence of Mr van Veenendaal and Mr Conlon,
noting the similarity of one paragraph (paragraph
43) of Mr van
Veenendaal’s affidavit with one paragraph (paragraph 16) of Mr
Conlon’s affidavit.
- I
have, of course, remembered what was written by Palmer J in Macquarie
Developments Pty Ltd & Anor v Forrester & Anor [2005] NSWSC 674, at
[90]:
“Save in the case of proving formal or non-contentious matters, affidavit
evidence of a witness which is in the same words
as affidavit evidence of
another witness is highly suggestive either of collusion between the witnesses
or that the person drafting
the affidavit has not used the actual words of one
or both of the deponents. Both possibilities seriously prejudice the value of
the evidence and Counsel usually attacks the credit of such witnesses, with good
reason.
Where the identity of evidence is due to collusion, the devaluation of the
evidence is justified but where, as in the present case,
the identity of
evidence is due entirely to a mistake on the part of a legal adviser, a witness'
credit and a party's case may be
unjustly damaged."
- In
this case, the criticism made of the two witnesses, whilst relevant, is not as
critical since there are contemporaneous documents
relating to the February 2016
meeting, to which reference has been made. In this regard, as was written by
Keane JA (as his Honour
then was) in Camden v McKenzie [2008] 1 Qd R 39;
[2007] QCA 136, at [34]:
"...usually, the rational resolution of an issue involving the credibility of
witnesses will require reference to, and analysis of,
any evidence independent
of the parties which is apt to cast light on the probabilities of the
situation." (Footnote omitted)
- I
accept the following evidence given by Mr van Veenendaal about the meeting on 3
February 2016 at Tcpt, 14 May 2019, p 141(25-30):
“A. The meeting was to discuss the breach notice. The meeting was there to
try and get an understanding of what action Longjing
would take to actually have
the shops open and to pay the rent, so that was the purpose of the meeting. The
result of that meeting
was that Mr Hedley made a representation that a number of
shops would be open and we gave Mr Hilton - Mr Hedley time in which to
come back
to us and actually tell us how he would remedy that.”
- Where,
as here, part of the case is based upon what are said to be verbal
representations, the well-known words of McLelland CJ (in
Eq) in Watson v
Foxman (2000) 49 NSWLR 315 at 318-319 must be
remembered:
“Where the conduct is the speaking of words in the course of the
conversation, it is necessary that the words spoken be proved
with a degree of
precision sufficient to enable the court to be reasonably satisfied that they
were in fact misleading in the proved
circumstances. In many cases (but not all)
the question whether spoken words were misleading may depend upon what, if
examined at
the time, may have been seemed to be relatively subtle nuances
flowing from the use of one word, phrase or grammatical construction
rather than
another, or the presence or absence of some qualifying word or phrase, or
condition. Furthermore, human memory of what
was said in a conversation is
fallible for a variety of reasons, and ordinarily the degree of fallibility
increases with the passage
of time, particularly where disputes or litigation
intervene, and the processes of memory are overlaid, often subconsciously, by
perceptions of self-interest as well is conscious consideration of what should
have been said or could have been said. All too often
what is actually
remembered is little more than an impression from which plausible details are
then, again often subconsciously,
constructed. All this is a matter of ordinary
human experience.”.
- The
seriousness of what is asserted, the inherent unlikelihood of an occurrence of a
given description, or the gravity of the consequences
flowing from a particular
finding, are all considerations that affect the answer to the question whether
the representations alleged
by the Plaintiff have been proved to the reasonable
satisfaction of the Court.
- I
am not persuaded that either the January representations or the February
representations were made by Mr van Veenendaal. Most importantly,
whilst there
was a large amount of email correspondence passing between Mr Hedley and Mr van
Veenendaal, there is not one email in
evidence in which any of the
representations was referred to. Mr Hedley, after initially indicating he did
not recall, conceded as
much in cross-examination: Tcpt, 13 May 2019, p
61(47-48), 72(34-50) – p 73(1), p 73(37-43). Nor were instructions given
to
the Plaintiff’s solicitors in accordance with the alleged
representations: Tcpt, 13 May 2019, p 72(47) – p 73(35). Nor
are there any
contemporaneous notes created, which, under cross-examination, Mr Hedley also
conceded: Tcpt, 13 May 2019, p 73(41)
– p 74(4).
- It
is highly likely that had such conversations occurred, a reference to them would
have been included in the email correspondence
passing between Mr Hedley and Mr
van Veenendaal, or they would have been the subject of the correspondence
between the solicitors.
In this regard, on 8 February 2016, Mr Lee sent an email
to Ms D Mountney (the solicitor at Gadens) noting that “our respective
clients have held discussions in relation to the matter and outstanding
issues” There was no mention made of the January representations:
Ex.
A/712.
- Importantly,
in the email sent by Mr Hedley to Mr Lee and to Ms Ng and Mr Ng on 25 February
2016, again there was no reference to
any representations of the type asserted.
When the Court asked Mr Hedley about the failure to include a reference to any
of these
representations in that email, he responded, at Tcpt, 13 May 2019, p
74(26-42):
“Q. Having written that email to both the lawyer and Mr and Mrs Ng,
there’s no reference in that document to any conversation
with Mr van
Veenendaal where you say that he said that if one or two shops were open by 28
February Mirvac would not enforce its
rights?
A. Yes.
Q. Can you tell me why that is?
A. Well, I guess we can only [rely] on documents from lawyers not verbally from
agent to agent.
Q. No, but--
A. I mean, there’s no point in me telling Mr Lee or Ms Ng something that
contradicts something that we’d received from
their lawyers on the same
day. I, I think the basis of it was Mr van Veenendaal was telling me for me not
to tell everybody else
because we wanted to maintain the pressure of getting
these shops opened. If I was to go and tell Ms Ng just get one or two open,
the
pressure would be off and who knows how long it would take to lease
them.”
- It
is hard to accept the evidence of Mr Hedley if, as is submitted, the
representations were intended to be relied upon, and were
relied upon, by the
Plaintiff and by Ms Ng. The evidence is also inconsistent with his subsequent
evidence in answer to a further
question from counsel for the Defendant, at
Tcpt, 13 May 2019, p 75(10-14), that:
Q. Is it the case that you, excuse the colloquial term, but took with a grain of
salt, anything that Mr van Veenendaal said, but
understood that the legal
position was set out in the formal correspondence from Gadens?
A. I - if anything I, I took what he said more so 'cause he was the one running
the project.
- Whilst
it is true that the Plaintiff endeavoured to keep the Defendant up to date with
the progress made in respect of the licences,
that progress does not refer
simply to steps taken to open one or two shops, but required information about
the negotiations being
conducted with a number of potential licensees.
- In
relation to the February representations, what was said to be required was to
show that “you will be able to have one licensee
signed up soon. We just
need to see that you are close”. In each case, that is not what
subsequently occurred.
- I
am far from persuaded that the contemporaneous records of the Plaintiff keeping
the Defendant updated are consistent with the January
representation and
February representation having been made.
- If
that were not enough, there are additional reasons not to accept the evidence of
Mr Hedley in relation to the January representations.
These
include:
- (a) Mr Hedley
could not remember when the conversation relied upon with Mr van Veenendaal
occurred (Tcpt, 13 May 2019, p 61(22-31));
he could not remember whether it was
before, or after, the Breach Notice was issued (Tcpt, 13 May 2019, p 61(50
– p 62(18)),
and he then placed the conversation before the Breach Notice
was issued (Tcpt, 13 May 2019, p 63(43-45), p 64(26-29)).
- (b) Mr Hedley
only “vaguely” recalled having a conversation with Mr van Veenendaal
in January 2016 in relation to the
Breach Notice issued (Tcpt, 13 May 2019, p
61(40-42)).
- (c) Mr Hedley
did not keep a note of the conversation that was said to have taken place (Tcpt,
13 May 2019, p 61(44-45)), despite
accepting that his practice was
“sometimes” to take notes of (or send emails, or text messages
relating to) important
conversations, but “usually” to communicate
in writing and if it was important to send an email or a text straight away
(Tcpt, 13 May 2019, p 28(29) – p 29(12)). One would have thought this was
an important conversation.
- (d) The
substance of the conversation that he remembered was that “As long as you
get a few of the shops open you’ll be
okay” (Tcpt, 13 May 2019, p
61(50) – p 62(3)). See also Tcpt, 13 May 2019, p 62(5-7), in particular Mr
Hedley’s
recollection being “the best I can do”.
- (e) Mr van
Veenendaal’s evidence of this conversation is more plausible. Mr van
Veenendaal denied the conversation as set out
in paragraphs 69-69 of Mr
Hedley’s first affidavit took place and said that the conversation with Mr
Hedley occurred immediately
after receipt of Mr Hedley’s email which
stated “Really??” (Ex. A/688) and Mr Hedley told Mr van Veenendaal
“This
is bullshit” (Tcpt, 13 May 2019, p 131(43)).
- Furthermore,
even if the January representations were made as is alleged, the simple fact is
that the Plaintiff did not even open
one shop, then or at any time.
- In
relation to the February representations, the following should be
noted:
- (a) These
representations are not said to have been made at the meeting between Mr Hedley,
Mr van Veenendaal and Mr Conlon on 3 February
2016, which meeting, ultimately,
led to the agreement set out in the letter dated 15 February 2016 to which
reference has been made.
- (b) Mr Hedley
accepted that the letter dated 15 February 2016 reflected the position that had
been reached as at 15 February 2016
(Tcpt, 13 May 2019, p 70(50) – p
71(2)).
- (c) Mr Hedley
did not recall having any conversation with Mr van Veenendaal on 15 February
2016 which was contrary to the position
set out in the letter dated 15 February
2016 letter (Tcpt, 13 May 2019, p 71(4-6)) or that was inconsistent with the
letter (Tcpt,
13 May 2019, p 71(8-11)).
- (d) The letter
dated 15 February 2016 is wholly inconsistent with any other agreement or
representations having been made.
- (e) Mr Hedley
did not accept that if Mr van Veenendaal had represented that only or two food
stalls needed to be open, he would have
told Mr Lee or instructed Mr Lee to
respond to the 15 February 2016 letter to that effect (Tcpt, 13 May 2019, p
73(3-17)).
- (f) On 25
February 2016, Mr Hedley conveyed to Mr Lee a conversation that he had had with
Mr van Veenendaal but did not say anything
to Mr Lee that Mr van Veenendaal had
told him that if one or two shops were open by 28 February 2016, then Mirvac
would not enforce
its rights (Tcpt, 13 May 2019, p 74(11-42)).
- Furthermore,
on one aspect of the evidence, Mr Hedley appears to have been factually in
error. He gave the following evidence at Tcpt,
13 May 2019, p
64(9-12)):
Q. Just so I get the chronology right, the conversation you had with him
preceded this breach notice and the purpose for your email
really was that the
breach notice was inconsistent with an earlier conversation that you'd had?
A. That's correct, and he, and he said it in, in front of Ms Ng as
well.”
- Ms
Ng admitted, however, that she had not been present, but that Mr Hedley had told
her of the conversation alleged to have had with
Mr van Veenendaal (Tcpt, 13 May
2019, p 80(7-24)). (In this evidence, it is clear that Ms Ng realised, by
January 2016, that the
Plaintiff was late in opening the Premises.)
- Any
conversation of the type suggested was also inconsistent with the email dated 1
February 2016, from Mr Hedley to her, in which
he stated that “Merry is
under extreme pressure by Mirvac to open these tenancies”: Ex. A/704.
- I
also do not accept Ms Ng’s evidence regarding the payment for furniture.
In the email dated 13 January 2016 sent by Ms Hodge,
to which reference has
earlier been made, there is a specific reference to Ms Ng having told Ms Hodge
that payment for the furniture
was not made: Ex. A/665A. I do not accept her
denial of this conversation (Tcpt, 14 May 2019, p 96(38) – p
97(20)).
The Plaintiff’s Submissions
- So
as to follow some of the submissions to which reference will be made, it is
necessary to refer, first, to the RSL Act as it was
in 2015. (The RSL Act has
been amended by the Retail Shop Leases Amendment Act 2016 (Qld). As the
parties did, I refer to sections of the RSL Act as they were in 2015, and in
present tense, noting the provisions referred
to may differ from the current
Act, or may no longer exist.) The object of that Act is said to be “to
promote efficiency and
equity in the conduct of certain retail businesses in
Queensland: s 3.
- Section
11 of the RSL Act specifies when a lease is entered into. It is the earlier of
either the date the lease becomes binding on
the parties, or the date the lessee
enters possession of the shop.
- Section
18 of the RSL Act provides that if, under the Act, a duty is imposed or an
entitlement is conferred on a lessor or lessee
under a retail shop lease, the
duty or entitlement is taken to be included in the lease.
- A
provision of a retail shop lease is void if it purports to exclude the
application of a provision of the RSL Act that applies to
the lease: s 19.
- Section
46A(1) of the RSL Act provides that “a lessor must not, in connection with
a retail shop lease, engage in conduct that
is, in all the circumstances,
unconscionable”.
- In
relation to the date on which the Lease commenced, the Plaintiff contended that
although the Lease became valid and binding on
the parties from 24 November
2015, it “was yet to commence” by 22 January 2016 (the date the
Defendant issued the Breach
Notice) or by 1 March 2016 (the date the Defendant
terminated the Lease) because the Defendant had failed to serve the notice in
accordance with Clause 4.2 of the Agreement for Lease (which was
said to be a “collateral agreement”: Tcpt, 15 May 2019, p 191(39)
– p 192(47). Thus, even though the Lease was
binding, there was no date
set for the Plaintiff to open the Premises or to commence to pay rent to the
Defendant. On that basis,
the Breach Notice was invalid as was the termination
of the Lease by the Defendant. It followed that the termination was wrongful
and
constituted a repudiation of the Lease, which repudiation the Plaintiff had
accepted.
- Counsel
submitted that there was a difference between the date when the Lease was
entered into, and the “Commencement Date”
of the Lease, and that the
Court was required to determine the “Commencement Date” of the Lease
by reference to the Agreement
for Lease.
- Counsel
pointed out that the “Lease Commencing Date” specified in the Lease
had been left blank: Ex. A/305; Ex. A/309.
Whilst the Plaintiff received the
Lease executed by the Defendant on 24 November 2015, that was not the
“Commencement Date”,
which was specifically defined in the Agreement
for Lease as being “the Fitout Access Date”, which had earlier been
defined
as “the date specified in the notice given by the Lessor under
clause 4.2”.
- Compliance
with Clause 4.2 was said to be mandatory – “must give to the Lessee
a notice” – and the notice
was required to specify certain things
identified therein. Furthermore, any notice served had not been served on the
Plaintiff in
accordance with Clause 18.1 of the Agreement for Lease. That Clause
required the notice given under the Agreement for Lease to be
served in a
particular way.
- The
notice relied upon by the Defendant was sent, by email, to Mr Hedley. The
sending of the notice to Mr Hedley did not comply with
the Defendant’s
obligations pursuant to the Agreement for Lease with the result that there was
no Lease Commencing Date.
- It
was then submitted that, in any event, the notice that was sent by the Defendant
provided that the Fitout Access Date was 19 October
2015. It followed that
pursuant to the Agreement for Lease, the “Lease Commencing Date”
must also have been 19 October
2015. However, the date upon which the Defendant
signed the Lease and provided it to the Plaintiff was 24 November 2015. It
would
“make a commercial nonsense” for the “Lease Commencing
Date” to be a date prior to the Lease having become
binding on the
parties. If the Lease became binding on the parties on 24 November 2015, no
notice was served upon the Plaintiff thereafter.
(A notice was sent on 16
October 2015 but that was not a notice that complied with the Lease or Agreement
for Lease.)
- The
Defendant, by executing the Lease agreed to be bound by its terms, one of which
was clause 4.2. It did not comply with that clause
by serving the required
notice. Therefore, so it was submitted, although the Plaintiff and the Defendant
had entered into the Lease,
the trigger for determining the Lease Commencing
Date was the date the notice was given by the Lessor under clause 4.2. As no
notice
had been given, the Lease had not commenced.
- It
was then submitted (possibly in advance of the likely submission from the
Defendant) that the Plaintiff did not waive the requirement
for notice to be
given to it.
- By
way of further submission, counsel stated that, at least, until 16 November
2015, there were works being undertaken by the Defendant
in respect of the
Premises. Possession was required to be exclusive for there to have been a
“Commencing date” within
the meaning of the RSL Act and when the
Plaintiff entered into possession on 19 October 2015, it was not granted
exclusive possession,
as the Defendant was still on site carrying out works that
it was required to complete: Ex. A/236-238.
- Furthermore,
counsel for the Plaintiff said that “there is one other potential date for
the lease commencement date and that
is if notice - if the agreement for lease
is taken to be the notice, then notice is required 14 days before the fitout
access date,
so the agreement for lease was provided on 24 November. In those
circumstances, the fitout access date would be 8 December 2015,
and that would
mean that the end of the fitout period which seems to be the same as the opening
date would be 2 February 2016, a
date after the Breach Notice”: Tcpt, 15
May 2019, p 238(10-16).
- Counsel
for the Plaintiff submitted that the manner in which the parties proceeded, and
how they treated their contractual arrangements,
including the payments that
were made by the Defendant to the Plaintiff, should be ignored: Tcpt, 15 May
2019, p 206(33) –
p 207(29).
- (I
should mention, in passing, that there was some discussion about the meaning of
the term “opening date”, but ultimately
the parties agreed that it
was “the date on which, or by which the Premises were to be opened and
trading”: Tcpt, 15
May 2019, p 236(50) – p 237(3)).
- In
relation to the second issue, namely, whether the Plaintiff was in breach of the
Lease as a result of the Plaintiff’s failure
to open the Premises during
Core Trading Hours, the Plaintiff submitted that since the Lease had not
commenced, it was not required
to pay rent and other occupancy charges or to
open the Premises during Core Trading Hours. It followed that the Plaintiff was
not
in breach of the Lease, and that it was, in fact, the Defendant which had
repudiated the Lease by issuing the termination notice
and then by terminating
it.
- In
oral submissions, it was put at Tcpt, 15 May 2019, p
191(31-33):
“Whilst the lease was binding there was no set date for [the Plaintiff] to
open the shops or pay rent and on that basis the
breach notice and termination
were invalid and repudiations of the lease.”
- It
was also submitted that even if the Plaintiff did not open the Premises during
Core Trading Hours, that did not entitle the Defendant
to terminate the Lease.
Clause 10.4(d) of the Lease provided the Defendant’s remedy, which was
damages, calculated in accordance
with that Clause. When reference was made to
Clause 18 (which provided that Clause 10.4 was an essential term), counsel for
the Plaintiff
submitted that the two Clauses were inconsistent because they
provided inconsistent remedies.
- By
way of alternative submission, counsel accepted that having issued the Breach
Notice, if the asserted breach was sufficiently serious,
the Defendant could
terminate the Lease. However, he submitted that, here, the breaches relied upon
were not sufficiently serious.
- In
relation to the third issue, namely whether the Defendant was entitled to
terminate the Lease for breach on 1 March 2016, the Plaintiff
contended that
there was an inconsistency in the Lease between Clause 10.4(d) and Clause 18.1.
The former Clause provided the clear
remedy for the breach of Clause 10.4(a)(1),
namely a payment to the Defendant for each hour that the Premises were not
opened during
Core Trading Hours. Clause 18.1, on the other hand, provided that
Clause 10.4 was an essential term.
- The
Plaintiff also contended that a breach of Clause 10.4(a)(1) ought not be held to
be a fundamental breach because, when considering
the factual scenario
objectively, the Plaintiff had not abandoned the Premises. Only upon abandonment
would the Defendant have been
entitled to terminate the lease for a fundamental
breach.
- It
followed that the notice given by the Defendant on 22 January 2016 ought to have
requested the Plaintiff to open the Premises during
Core Trading Hours and
should have stated that the failure to do so would result in the requirement for
the Plaintiff to pay the
Defendant $100 for each hour that the Premises were not
opened.
- The
Plaintiff also submitted that the requirement to pay rent and other expenses was
waived by the Defendant as it had been stated
that there would be a call on the
Bank Guarantee, which, if such a call was made, would have required the
Plaintiff to replace the
Bank Guarantee within seven days.
- Counsel
also submitted that the Notice of Termination stated that the Lease was to be
terminated “as a result of the Lessee
failing to comply with the Notice to
Remedy of Covenant dated 22 January 2016”, which suggested that the
Defendant did not
rely upon clause 18.2(b) of the Lease. As clause 18(b) of the
Lease was not referred to in the Breach Notice, or the Termination
Notice, the
Defendant ought not to be entitled to rely upon that provision.
- Counsel
submitted, despite the terms of the Lease, that a clause requiring a shop to
remain open during core trading hours had previously
been held not to be an
essential term of the Lease: Leda Commercial Properties Pty Ltd v DHK
Retailers Pty Ltd (1992) 111 FLR 81. He maintained, in his opening written
submissions, that:
“... where clause 10.4 is referred to in clause 18.1 it ought to be read
as a reference to clause 10.4(a)(2) – 10.4(a)(4).
Clearly, clauses 10.4(b)
and 10.4(c) do not relate to obligations of the Lessee and could not be held to
be essential terms.
Further, clauses 10.4(a)(2) to 10.4(a)(4) are in the nature of fundamental
breaches. That is for the following reasons:
a. in the event the Shops were opened outside the Core Trading
Hours, as considered in clause 10.4(a)(2), that would increase the
potential
liability and/or costs of Perpetual. The liability may arise as a result of
Perpetual not having cleaners available to
clean spills which may result in a
claim for personal injury damages and the additional costs would potentially be
cleaners and staff.
Therefore, to act in such a way would be a fundamental
breach;
b. similarly, opening the Shops when prohibited by law, in
contravention of clause 10.4(a)(3), would also provide an additional
liability
on Perpetual; and
c. failure to make the required payment, pursuant to clause
10.4(a)(4), would be similar to a failure to pay rent and would have
exposed
Perpetual to additional costs.
...
In the event clause 10.4(d) was read as contended by Perpetual; it would be
entitled to terminate the Lease if Longjing did not open
the Shops for 15
minutes during the Core Trading Hours.
It follows that the notice provided by Perpetual on 22 January 2016 ought to
have requested Longjing to open the Shops during Core
Trading Hours and that the
failure to do so would result in the requirement for Longjing to pay Perpetual
the sum of $100 for each
hour that it was not opened.”
- In
relation to the failure to pay rent, it was submitted that the Defendant was not
entitled to terminate the Lease as the requirement
to pay rent and other
expenses had been waived, the Defendant stating that it would call on the Bank
Guarantee which would require
the Plaintiff to replace the Bank Guarantee within
seven days.
- In
relation to the fourth issue, namely whether the Defendant’s conduct, in
terminating the Lease, was unconscionable pursuant
to s 46A of the RSL Act or
pursuant to s 20 and/or s 21 of the the AC Law, being Schedule 2 to the
Competition and Consumer Act 2010 (Cth), or misleading or deceptive
conduct, the Plaintiff relied on the following provisions.
- (The
phrase “misleading or deceptive conduct” was used in written
submissions, and throughout the course of the hearing;
indeed, it was a part of
one of the issues to be determined. I note that neither the Plaintiff nor
Defendant relied on the specific
legislative provisions pertaining to
“misleading or deceptive conduct” as they appear in s 18 of the AC
Law. The phrase “misleading or deceptive conduct” was left
undefined. For a recent discussion of those principles,
see H20 Learning Pty
Ltd v Swim Loops Pty Ltd t/as Jump Swim Schools [2019] NSWDC 165.)
- Section
20 of the AC Law provides:
“A person must not, in trade or commerce, engage in conduct that is
unconscionable, within the meaning of the unwritten law
from time to
time.”
- Section
21 of the AC Law provides:
“(1) A person must not, in trade or commerce, in connection with:
the supply or possible supply of goods or services to a person (other than a
listed public company); or
the acquisition or possible acquisition of goods and services from a person
(other than a listed public company);
engage in conduct that is, in all the circumstances, unconscionable.
...
(3) For the purpose of determining whether a person has contravened subsection
(1):
(a) the court must not have regard to any circumstances that were not reasonably
foreseeable at the time of the alleged contravention;
and
(b) the court may have regard to conduct engaged in, or circumstances existing,
before the commencement of this section
(4) It is the intention of Parliament that:
(a) this section is not limited by the unwritten law relating to unconscionable
conduct; and
(b) this section is capable of applying to a system of conduct or pattern of
behaviour, whether or not a particular individual is
identified as having been
disadvantaged by the conduct or behaviour; and
(c) in considering whether conduct to which a contract relates is
unconscionable, a court's consideration of the contract may include
consideration of:
(i) the term of the contract; and
(ii) the manner in which and the extent to which the contract is carried
out;
and is not limited to consideration of the circumstances relating to formation
of the contract.”
- The
Plaintiff relied upon the following facts as demonstrating the unconscionable
conduct of the Defendant:
- (a) The
Defendant, through its agent, made the January representations and the February
representations;
- (b) The
Defendant acted unreasonably when it terminated the Lease as the Plaintiff had
expended considerable resources by improving
the Premises, and by readying them
for opening. It was unconscionable for the Defendant to terminate the Lease at a
time when it
knew of the efforts being made and the expenses incurred by the
Plaintiff to ready the Premises for opening and when it was consistently
being
informed of the progress the Plaintiff was making in respect of obtaining
licensees to open food stalls within the Premises.
(Reliance was placed on
emails sent on 23 February 2016, and on 29 February 2016 (each of which emails
have been referred to earlier).
- (A
third matter (relating to the Defendant having provided a copy of the Breach
notice to a third party which was a potential licensee),
that had been relied
upon in the Plaintiff’s outline of submissions, was abandoned during the
hearing.)
- Finally,
on the issue of damages, counsel for the Plaintiff submitted that the Defendant,
having repudiated the Lease, which repudiation
the Plaintiff accepted, entitled
the Plaintiff to damages.
- In
his closing written submissions, counsel maintained:
“The claim for the amount which Longjing has incurred is based upon Ms
Ng’s evidence as to the sums paid, the bank statements,
the Commercial
Building Contract with Hammer Brothers Pty Ltd dated 8 October 2015 and the Loan
Agreement with Property IQ No 3 Pty
Ltd dated 1 December 2015.” (Footnotes
omitted)
- He
added that the purpose of the Lease was for the Plaintiff to run one of the
Shops itself and to licence the remaining shops. The
profit it expected to make
was the difference between the amount it received from each of the licensees and
its fiscal obligations
under the Lease. He also submitted that the Court should
find that the Plaintiff “would have entered into the ...
licences”.
- He
concluded by stating, in writing:
“As a result of the repudiation by Perpetual, Longjing suffered lost
profits in the sum of $521,770.18. A copy of the calculation
is at annexure
A.
Given the Shops are located within the Orion Shopping Centre, Longjing submits
that once opened the Shop would have been occupied
throughout the Lease. It
follows that there should be no, or minimal, reduction on the claim for loss of
profits.”
The Defendant’s Submissions
- The
Defendant’s answer to the Plaintiff’s contention that although the
Lease was valid and binding on the parties from
24 November 2015, it had not
“commenced” by 22 January 2016 (being the date the Defendant issued
the Notice of Breach)
or 1 March 2016 (being the date the Defendant terminated
the Lease) because no notice was issued by the Defendant in accordance with
clause 4.2 of the Agreement for Lease, was that the Lease Commencement date was
either (a) 19 October 2015, being the date that the
Defendant formally handed
over the Premises to the Plaintiff to begin the Fitout Works as defined; (b) 24
November 2015, being the
date on which the Defendant executed the Lease and sent
it to the Plaintiff; or (c) 14 December 2015, being the rent commencement
date.
It was put, however, that whilst the Lease became binding on 24 November 2015,
the parties were entitled to, and did, choose
a commencement date prior to that
date. The “Commencement Date” chosen by them was 19 October 2015,
that being the “Fitout
Access Date”.
- (I
should mention, although not referred to by either counsel, that there is some
support for the Defendant’s submission that
the parties were entitled to,
and did, choose a commencement date prior to that date. In the Disclosure
Statement referred to, Part 3 “Works Fit Out and Refurbishment”, in
the box headed “Date of handover (if different to the date the lease
commences
indicated at Item 5.1)”, the date stated as the “Date
lease commences” at Item 5.1, and the “Date of handover”
at
Item 7.1, is “10/09/2015”): Ex. A/162ZCO.)
- The
Defendant submitted that reliance on clause 4.2 of the Agreement for Lease was
misplaced because any requirement to give a notice
pursuant to clause 4.2 was
superseded by the Plaintiff giving the signed documents to the Defendant on 2
October 2015; by the Defendant
granting access to the Premises on 19 October
2015 to enable the Plaintiff to undertake its "Fitout Works" (as defined in the
Agreement
for Lease); and the agreement made by the parties that the "Opening
Date" (as defined in the Agreement for Lease) would be on 14
December 2015,
later amended to 24 December 2015 (on and from which date the rent would
commence to be payable).
- The
"Fitout Period", was defined in the Agreement for Lease as 8 weeks, commencing
on the Fitout Access Date. Working from what was
to be the Opening Date, 8 weeks
previous, was 19 October 2015.
- The
Defendant also relied upon the undisputed fact that during the period between 2
October 2015 and 14 December 2015, the Defendant
had paid $627,000 to the
Plaintiff on account of the Fitout Works (as defined in the Agreement for Lease)
that had to be carried
out by the Plaintiff.
- Counsel
also submitted that if notice was required to be given by the Defendant to the
Plaintiff, pursuant to clause 4.2 of the Agreement
for Lease, the requirement
was waived by the Plaintiff because the parties had agreed that the "Fitout
Access Date" was 19 October
2015 and the last day of the "Fitout Period" was 13
December 2015. It was also submitted that the Plaintiff was estopped, by its
conduct, from contending that no notice under Clause 4.2 of the Agreement for
Lease had been given or that that the Lease had not
commenced.
- Alternatively,
to the extent that notice was required, it was given by the email dated 16
October 2015, which email included the relevant
information that was required by
Clause 4.2. On the proper construction of Clause 4.2 of the Agreement for Lease,
notice was only
necessary to be given if the Fitout Access Date and the last day
of the Fitout Period were not known.
- The
Defendant submitted that there was no inconsistency between Clauses 10.4(d) and
18.2(d) and that the two clauses operated concurrently.
Clause 10.4(d) was an
agreed damages clause, being a contractual term that quantified the amount of
damages payable for a designated
breach of the Lease, whilst Clause 18.2(d) gave
the Defendant the right to terminate the Lease for breach of Clause 10.1(a) of
the
Lease (upon the giving of a notice to remedy required by law and the failure
of the Plaintiff to comply with that notice).
- The
Defendant’s position was simply that it was entitled to damages for the
Plaintiff’s breach of Clause 10.4(a)(i) of
the Lease, and also entitled to
terminate the Lease in accordance with Clause 18.2(d) of the Lease.
- The
Defendant submitted that none of the representations relied upon by the
Plaintiff should be found to have been made. Even if they
had been, reliance and
causation had not been established in circumstances where the Plaintiff failed
to open even one or two shops
prior to 5:00 p.m. on 28 February 2016.
- Moreover,
even if what were described as “the January Representations” had
been made (which was denied), they were overtaken
by events including the
agreement reached on 15 February 2016, which was contrary to those
representations.
- The
Defendant accepted that in the event that the Court accepted that if the
contentions advanced by the Plaintiff, namely that the
Lease had not "commenced"
and that the Defendant was not entitled to terminate the Lease for a breach of
Clause 10.4(a) of the Lease,
the letter dated 1 March 2016 was not a repudiation
of the Lease or the Agreement for Lease because the Defendant’s
termination
of the Lease in accordance with what it considered its contractual
right to do so did not evince an absence of readiness and willingness
to perform
the Lease. There was no allegation that the Defendant would not perform its
obligations under the Lease in the event that
its termination was held to be
wrongful. Moreover, there was no suggestion that the Defendant was in breach of
the Lease prior to
1 March 2016.
- In
relation to the claims made by the Plaintiff, the following table, and the
response to each claim made by the Defendant, is instructive
(with editorial
corrections):
With respect to other payments made by Longjing, if Longjing is successful,
Perpetual agrees with the amount of $192,500.00 for the reasons set out
in the table
below.
Item
|
Amount claimed by Longjing
|
Amount Perpetual agrees with
|
Explanation
|
Initial deposit to Mirvac for 1 month rent of two deals for foodcourt and
the yumcha restaurant
From total rent of $700,000 pa + GST
|
$64,166.00
|
$27,500.00
|
Disagree – The deposit in respect of the Shops was
$27,500.00.
|
Bank guarantees – 6 months’ rent for Kowloon City
|
$165,000.00
|
$165,000.00
|
Agree – The Defendant accepts that this amount was
paid.
|
Architectural designer & Engineering consultant
|
$75,000.00
|
$0
|
Disagree – The amount claimed does not appear to be
substantiated by evidence.
|
Council & Liquor Licence
|
$12,000.00
|
$0
|
Disagree – The amount claimed does not appear to be
substantiated by evidence.
|
Equipment
|
$50,000.00
|
$0
|
Disagree – The amount claimed does not appear to be
substantiated by evidence.
|
Furniture
|
$10,000.00
|
$0
|
Disagree – The amount claimed does not appear to be
substantiated by evidence.
|
Advertisements on local newspaper/online/RE Agent
|
$20,000.00
|
$0
|
Disagree – The amount claimed does not appear to be
substantiated by evidence.
|
Other related expenses for travelling
|
$60,000.00
|
$0
|
Disagree – The amount claimed does not appear to be
substantiated by evidence.
|
|
Not Agree - $456,166.00
|
Agree - $192,500.00
|
|
- In
relation to outstanding payments, the following table depicts the claims made by
the Plaintiff and the Defendant’s response
thereto:
With respect to other outstanding payments, if Longjing is successful, Perpetual
agrees with the amount of $1,432,386.40 for the
reasons set out in the table
below:
Item
|
Amount claimed by Longjing
|
Amount Perpetual agrees with
|
Explanation
|
Money owing to Hammer Bros
|
$1,267,386.40
|
$1,267,386.40
|
Agree – This is the agreed contract price between the
Plaintiff and Hammer Bros for the fit out of the Shops, and includes payments
made to Hammer Bros by the Plaintiff of $670,000.
|
Loan to Property IQ No 3 Pty Ltd
|
$458,491.66
|
$0
|
Disagree – There is no evidence that the loan was used by the
Plaintiff in relation to or for the purpose of the Premises.
|
Loan to Merry/director on bank guarantee and deposit
|
$229,166.00
|
$165,000.00
|
Disagree –The Defendant agrees with the amount of the bank
guarantees of $165,000.
It does not agree with the deposit of $27,500.00 because to the extent that
the Plaintiff argues that the Lease never commenced, by
Clause 19 of the lease
proposal (Ex. A/3), where the Plaintiff does not proceed with a lease, the
deposit is forfeited.
|
Spacecubed design for yum cha restaurant
|
$15,000.000
|
$0
|
Disagree – The amount claimed does not relate to the
Premises.
|
|
Not Agree - $1,970,044.30
|
Agree - $1,432,386.40
|
|
- In
relation to its claim for damages, the Defendant claimed the amount of
$252,936.03. The Plaintiff accepted that that this is the
amount payable under
the Cross-Claim in the event that the Cross-Claim succeeded. As has been
outlined earlier in these reasons,
this amount is agreed.
- The
Defendant, in relation to the claim against Ms Ng, submitted that pursuant to
Clauses 12.1(b) and 12.1(c) of the Agreement for
Lease and Clauses 20.1(b) and
20.1(c) of the Lease, Ms Ng was liable to the Defendant and that she was
required to indemnify the
Defendant in the amount of $252,936.03.
- In
relation to the Plaintiff’s claim for damages, counsel for the
Defendant submitted that in the event the Court concluded that the
Lease had commenced on 19 October 2015, the Defendant was entitled to terminate
the Lease.
- Even
if this was wrong, the letter dated 1 March 2016 was not a repudiation of the
Lease or the Agreement for Lease because the Defendant’s
termination of
the Lease in accordance with what it considered its contractual right to do so
did not evince an absence of readiness
and willingness to perform. Furthermore,
it had not been alleged by the Plaintiff that the Defendant would not perform
its obligations
under the Lease in the event that its termination was held to be
wrongful. Moreover, there was no suggestion that the Defendant was
in breach of
the Lease prior to 1 March 2016.
- It
was noted that the Plaintiff itself was in breach of the Lease, even if the
Defendant’s purported termination on 1 March
2016 was repudiatory. The
Plaintiff was not entitled to claim "damages calculated as the profit that
Longjing would have earned during
the duration of the Lease" (as asserted in the
amended Statement of Claim, at [38]) i.e. loss of bargain damages) because a
party
may only recover damages for loss of bargain where that party, itself, was
in a position to perform its side of the bargain. If it
were otherwise, it could
not sensibly be said that it was the other side's conduct which caused the loss
of the profit involved in
the bargain. That advantage could not have been
obtained even if the other side had fulfilled its obligations: Highmist Pty
Ltd v Tricare Ltd [2005] QCA 357 per Keane JA (as his Honour then was) with
whom Jerrard JA and Cullinane J agreed, at [61].
- Finally,
counsel for the Defendant submitted that even if Longjing is entitled to claim
loss of bargain damages, no damages would
be awarded because Longjing has
suffered no loss. This is because on its own analysis the Lease was loss-making.
Longjing's alleged
profit of $521,770.18 is swamped by its alleged costs of
$1,970,044.30 or $1,919,367.43.
- It
was noted that the object of damages in this context is to put Longjing in the
same position as though the Lease had been performed
(i.e. loss of bargain
damages is the difference between the value of the unperformed obligations of
the promisor and the contract
price, or money equivalent).
- It
was also noted that if Longjing was put in the same position as though the Lease
had been performed, then it would have lost approximately
$1.45
million.
The Law
- In
Willmott Growers Group Inc v Wilmott Forests Ltd (2013) 251 CLR 592;
[2013] HCA 51, at [39]-[40], French CJ, Hayne J and Kiefel J (as her Honour then
was) wrote:
“...it is now firmly established that a lease is a species of contract. As
Deane J said in Progressive Mailing House Pty Ltd v Tabali Pty Ltd,
‘[a] lease for a term of years ordinarily possesses a duality of character
which can give rise to conceptual difficulties.
It is both an executory contract
and an executed demise’ (emphasis added). Hence, as Mason J said,
‘the ordinary principles
of contract law, including that of termination
for repudiation or fundamental breach, apply to leases’.
The rights and duties which a landlord and tenant have under a lease are bundles
of rights and duties which together can be identified
as species of property.
The origins of those rights and duties lie in the contract which the landlord
and tenant or their predecessors
in title made. In every case, the rights and
duties of the landlord and tenant, whether as an original party to the lease or
as a
successor in title, stem from the contract of lease and any later contract
made in relation to that lease. When a company is the
landlord, the rights and
duties which that company has in respect of the lease are properly described as
‘property of the company
that consists of ... a contract’. The
landlord's rights and duties are a form of property; those rights and duties
‘consist
of’, in the sense of derive from, the contract of
lease.” (Footnotes omitted)
- Gageler
J wrote at [62]:
“Progressive Mailing House Pty Ltd v Tabali Pty Ltd confirmed that,
save perhaps in exceptional cases, a right to the exclusive possession of land
for a term is given by contract between
the lessor and the lessee. The legal
consequence, that rights conferred and obligations imposed by a contract that is
a lease become
attached to the respective estates or interests in land of the
lessor and the lessee, does not detract from the underlying legal
character of a
lease as a species of contract....” (Footnotes omitted)
- Keane
J wrote at [107]:
“The first to third respondents relied upon the decision in Tabali
to support the propositions that a lease is essentially a contractual interest,
dependent on the continued subsistence of the contract
between lessor and
lessee, and that as such it is susceptible of annihilation upon the termination
of the contract. In this regard,
they invoked the statement of Deane J in
Tabali:
‘[O]nce it is accepted that the principles of the
law of contract governing termination for fundamental breach are, as a matter
of
theory, applicable to leases generally, there is no difficulty in applying them
in the present case in much the same fashion as
to an ordinary executory
contract: “[i]f the contract is avoided or dissolved ... the estate in
land falls with it”’.
(Footnotes omitted)
- At
common law, a breach of an essential term of a lease entitles the party who is
not in breach to terminate the lease, without notice
(see Walsh Investments
Pty Ltd v SCK Properties Pty Ltd [2016] QCA 258; Progressive Mailing
House Pty Ltd v Tabali [1985] HCA 14; (1985) 157 CLR 17 at 55).
- Section
124 of the Property Law Act 1974 (Qld) provides:
“(1) A right of re-entry or forfeiture under any proviso
or stipulation in a lease, for a breach of any covenant, obligation,
condition
or agreement (express or implied) in the lease, shall not be enforceable by
action or otherwise unless and until the lessor
serves on the lessee a
notice—
(a) specifying the particular breach complained of; and
(b) if the breach is capable of remedy, requiring the lessee to
remedy the breach; and
(c) in case the lessor claims compensation in money for the
breach, requiring the lessee to pay the same;
and the lessee fails within a reasonable time after service of the notice to
remedy the breach, if it is capable of remedy, and,
where compensation in money
is required, to pay reasonable compensation to the satisfaction of the lessor
for the breach.
...
(8) The notice mentioned in this section shall be in the approved form.
(9) This section applies to leases made either before or after
the commencement of this Act, and shall have effect despite any
stipulation to
the contrary.”
- It
is clear that s 124(1) does not create a right of re-entry or forfeiture. It
imposes a pre-condition on the exercise of the right
that is conferred by a
lease. The right is exercisable for a breach of a covenant, obligation,
condition or agreement in the lease.
Section 124(1) is engaged only where a
right of re-entry or forfeiture is to be exercised on the basis of a breach
or breaches of
the lease.
- In
Koompahtoo Local Aboriginal Land Council v Sanpine Pty Ltd [2007] HCA 61; (2007) 233 CLR
115, at 135; [2007] HCA 61, at [44], the plurality wrote that the term
repudiation is used in different senses. Their Honours
wrote:
“First, it may refer to conduct which evinces an unwillingness or an
inability to render substantial performance of the contract.
This is sometimes
described as conduct of a party which evinces an intention no longer to be bound
by the contract or to fulfil it
only in a manner substantially inconsistent with
the party’s obligations. It may be termed renunciation. The test is
whether
the conduct of one party is such as to convey to a reasonable person, in
the situation of the other party, renunciation either of
the contract as a whole
or of a fundamental obligation under it. ... Secondly, it may refer to any
breach of contract which justifies
termination by the other party. ... There may
be cases where a failure to perform, even if not a breach of an essential term
...
manifests unwillingness or inability to perform in such circumstances that
the other party is entitled to conclude that the contract
will not be performed
substantially to its requirements. This overlapping between renunciation and
failure of performance may appear
conceptually untidy, but unwillingness or
inability to perform a contract often is manifested most clearly by the conduct
of a party
when the time for performance arrives. In contractual renunciation,
actions may speak louder than words.” (Footnotes omitted)
- As
a matter of general law, the question when the Lease commenced requires a
consideration of what was communicated between the parties
by their words and
their conduct, and whether, objectively assessed, that led to the conclusion
that they intended to create a legally
binding relationship and that they had
agreed to all the terms that the law requires as essential for that
purpose.
- Lord
Wright wrote in G Scammel & Nephew Ltd v HC and JG Ouston [1941] AC
251, at 268:
“The object of the court is to do justice between the parties, and the
court will do its best, if satisfied that there was
an ascertainable and
determinate intention to contract, to give effect to that intention, looking at
substance and not mere form.
It will not be deterred by mere difficulties of
interpretation. Difficulty is not synonymous with ambiguity so long as any
definite
meaning can be extracted. But the test of intention is to be found in
the words used. If these words, considered however broadly
and untechnically and
with due regard to all the just implications, fail to evince any definite
meaning on which the court can safely
act, the court has no choice but to say
that there is no contract. Such a position is not often
found.”
- Section
11 of the RSL Act relevantly provides:
“A retail shop lease is entered into on whichever is the earlier of the
following dates -
(a) the date the lease becomes binding on the lessor and
lessee;
(b) the date the lessee enters into possession of the leased
shop.”
- In
this case, Ms Ng accepted that the Plaintiff entered into possession of the
Premises on about 19 October 2015: by her affidavit
made 10 April 2019, at [3],
Ms Ng stated “[o]n or about 19 October 2015, the Defendant formally handed
over the Property to
the Plaintiff” and at [5], “[o]n or around 19
October 2015, Mirvac proceeded with the handover to Longjing for Shops
203-206
to begin the lessee’s fitout works”. By her counsel, it was accepted
at Tcpt, 15 May 2019, p 186(6-12) that “on
19 October the defendant
formally handed over the premises to the plaintiff to begin the lessee's fit out
works”. Mr Hedley
also agreed that from the middle to end of October 2015,
the Plaintiff was allowed into occupation of the Premises to “do their
[sic] works”: Tcpt, 13 May 2019, p 32(49) – p 33(1-2). In an email
dated 16 October 2015 from Mr van Veenendaal to Mr
Hedley, it was stated that
“[t]he lessee’s [contractor] will take physical possession of the...
Premises on Monday 19th
October 2015...”: Ex. A/188. He later agreed,
under cross-examination, that it was on 19 October 2015 that the Plaintiff took
physical possession of the Premises: Tcpt, 13 May 2019, p
43(38-41).
Determination
- I
shall deal with the four issues that were identified by the parties. Naturally,
what follows should be read in the context of the
findings of fact identified
earlier in these reasons.
(a) When did the
Lease commence?
- Looking
at the two relevant documents being the Agreement for Lease and the Lease, I am
satisfied that the “Lease Commencing
Date” meant the
“Fitout Access Date” and that the “Fitout Access Date”
meant the date on which the Plaintiff obtained
access to the Premises.
- In
the present case, there can be no doubt that the Fitout Access Date was 19
October 2015. Ms Ng admitted so much in her affidavit
and there is other
evidence to which reference has been made that confirms that it was on that date
the Plaintiff entered into possession
of the Premises to commence the fitout
works.
- In
addition, that date accords with the RSL Act which provides that one of the
dates that a retail shop lease is entered into is the
date the lessee enters
into possession of the leased premises.
- It
is impossible to accept the submission of the Plaintiff that the Lease
Commencing Date cannot be a date prior to the Lease becoming
binding on the
parties. That the RSL Act refers to “the earlier of the following
dates” makes clear that a lessee may
enter into possession before the date
the lease becomes binding on the lessor and the lessee.
- In
addition, I have earlier referred to Ex. A/162ZCO being part of the Disclosure
Statement which in Part 3 “Works Fit Out and
Refurbishment” stated
in the box headed “Date of handover (if different to the date the lease
commences indicated at
Item 5), which suggests that the parties contemplated the
same possibility.
- If
those matters were not enough, in Whitlock v Brew [1968] HCA 71; (1968) 118 CLR 445, a
case in which a purchaser of land agreed to lease the land to a third party upon
entering into possession of the land, Kitto J
wrote at
456:
“As regards the term of the lease, it sufficiently appears, I think, that
the commencing date is to be the date when the purchaser
obtains
possession.”
- In
Selever v Klaskova (Supreme Court of New South Wales, Powell J, 15 March
1988, unrep) Powell J wrote, at [7]:
“... It is true to say that an agreement for lease, to be valid and
enforceable, must mention the term, and from what day it
is to commence,
otherwise there is no complete agreement ... However, it is not impossible to
limit the commencement of the contemplated
term upon a contingency; it is
sufficient if the date of commencement should be capable of being definitely
ascertained at the time
the proposed lease takes effect in interest or
possession.”
- Recently,
in Donau Pty Ltd v ASC AWD Shipbuilder Pty Ltd [2019] NSWCA 185, at
[154]-[168], Basten JA held that an objective approach to contractual
interpretation frees the courts from the constraining influence
of reflecting
upon the actual intention of the parties; and that such an approach controls
factual disputes relating to pre-contractual
negotiations and post-contractual
conduct.
- I
reject the Plaintiff’s submissions that because notice in writing was not
given in accordance with clause 4.2 of the Lease,
that there was no “Lease
Commencing Date”. The parties themselves agreed that the Plaintiff would
take possession on
19 October 2015, and it did so. They also agreed that the
last day of the Fitout period was 13 December 2015, which was subsequently
extended. Both these matters are unarguable on the evidence. In addition, in
October 2015, the Plaintiff had received $627,000 from
the Defendant. It
received another $220,000 in January 2016. To suggest that the Lease had not
commenced does not accord with the
actions of the parties themselves. It would
be commercially unrealistic to conclude that no Lease had commenced in the light
of the
parties’ conduct.
- To
the extent that it is relevant, I am satisfied that the reasonable bystander
would conclude, from the parties’ words and
conduct, that the Lease
commenced when the Plaintiff went into possession.
- It
does not matter that the Plaintiff was not given exclusive possession of the
Premises. The purpose of it being given possession
was so that it could carry
out the fitout works.
- One
also asks, in the circumstances of this case, following agreement having been
reached on 16 October 2015, what would have been
achieved by the
service of a notice. Clause 4.2 required the notice to specify only two
things, namely, the Fitout Access Date, and the last day of
the Fitout Period,
both of which dates had already been agreed by the parties and were known to the
Plaintiff.
- In
the event that I am wrong in reaching the conclusion set out above, I am
satisfied that the email sent by Mr van Veenendaal to
Mr Hedley on 16 October
2015, contained that information. Although that notice was not given “at
least fourteen (14) [days]
before the Fitout Access Date specified in it”,
the parties had been negotiating terms for several months. Strict compliance
with clause 4.2, therefore, was not necessary.
- The
submissions made by the Defendant, which I shall not repeat, and which are set
out above, are far more persuasive than those of
the Plaintiff on this first
issue.
(b) Was the Defendant entitled to
terminate the Lease on account of the Plaintiff’s breach of cl 10.4 of the
Lease?
- As
stated, the Plaintiff’s arguments on this issue depend on the finding of
inconsistency between Clause 10.4 and Clause 18.2(d).
I am not satisfied that
there is any such inconsistency. The two clauses simply deal with different
aspects of a breach and operate
concurrently. Clause 10.4(d) provided the method
by which damages could be calculated – it was an agreed damages clause. As
was submitted by the Defendant, it “is a contractual term which quantifies
the amount of damages payable by a promisor for
designated breaches of contract:
see Carter’s Breach of Contract at [12-27]”. Clause 18.2(d) provided
the Defendant with
the right to terminate the Lease for breach of an essential
term, one of which was Clause 10.1(a) of the Lease (upon the giving of
a notice
to remedy required by law and the failure of the Plaintiff to comply with that
notice). The Defendant gave such a notice.
- Again,
the facts of the case, as set out, lead to me being unpersuaded that the
Defendant was not entitled to terminate the Lease.
The Plaintiff did not pay
rent. It did not assert that the Defendant should call on the Bank to satisfy
outstanding rent. To the
extent that the Defendant stated that it would do so
and require the Plaintiff to replace the Bank Guarantee, or the proportion of
the Bank Guarantee recovered by the Defendant, the statement was made in the
context of the Plaintiff not complying with the Breach
Notice, which required
the Plaintiff to pay to the Defendant the amount outstanding. The statement did
not relieve the Plaintiff
of the obligation to pay rent.
- Furthermore,
the failure to open the Premises during “Core Trading Hours” had
continued from 24 December 2015 until 22
January 2016. It continued then until 1
March 2016. Even then, there was no specific indication when trading would
commence. All
that the Plaintiff seemed to be doing was making suggestions about
when licenses might be signed, not when the Premises would be
open for business
during core trading hours. It follows that the answer to the question is
Yes.
(c) Did the Defendant engage in misleading
or deceptive conduct or unconscionable conduct in terminating the Lease on 1
March 2016?
- I
have earlier referred to the evidence of the representations and explained the
reasons why I do not accept the evidence regarding
the January representations
or the February representations. It was these representations that formed the
cornerstone of the Plaintiff’s
claim of unconscionable conduct and
misleading or deceptive conduct.
- In
my view, there was no such conduct otherwise. The Defendant’s
representatives asked the Plaintiff’s representative
to advise the period
of time the Plaintiff required to remedy the breaches. The Plaintiff indicated
14 days, initially from 3 February
2016. The agreement reached on 16 February
2016 provided for 12 more days from that date, until 28 February 2016. Even
then, an additional
day elapsed before, on 1 March 2016, the notice of
termination was given.
- I
am simply not satisfied that any conduct by the Defendant, as alleged by the
Plaintiff, was misleading or deceptive conduct or was
unconscionable
conduct.
(d) What is the quantum of damages
suffered by the Defendant or by the Plaintiff (depending upon the Court’s
determination
of the first three issues set out above)?
- The
quantum of the Defendant’s damages, in the circumstances, was agreed in
the sum of $252,936.03. There should be judgment
for the Defendant against the
Plaintiff for that amount on the Cross-Claim.
- There
was no suggestion that Ms Ng, as guarantor of the Plaintiff’s obligations,
would not be liable.
- In
light of the conclusions, it is unnecessary to deal with the Plaintiff’s
claim for damages as the Statement of Claim will
be dismissed.
- Although
there were no submissions made on costs, there is no reason why the usual costs
order should not be made. Also, an order
should be made dealing with the
exhibits.
- In
the circumstances, the Court:
- (1) Orders that
the Plaintiff’s Statement of Claim be dismissed.
- (2) Orders that
there be judgment for the Cross-Claimant against each of the Cross-Defendants in
the sum of $252,936.
- (3) Orders that
the Plaintiff pay the Defendant’s costs of the Statement of Claim.
- (4) Orders that
the Cross-Defendants pay the Cross-Claimant’s costs of the
Cross-Claim.
- (5) Orders that
the Court Books be returned.
- (6) Orders that
the Exhibits be dealt with in accordance with the Uniform Civil Procedure Rules
2005 (NSW) (rule 31.16A and rule 33.10) and Practice Note No SC Gen
18.
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2019/1098.html