You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2021 >>
[2021] NSWSC 530
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Context | No Context | Help
PNJ Investment Holding Pty Ltd v ST.K Family Pty Ltd atf ST.K Family Trust [2021] NSWSC 530 (14 May 2021)
Last Updated: 14 May 2021
|
Supreme Court
New South Wales
|
Case Name:
|
PNJ Investment Holding Pty Ltd v ST.K Family Pty Ltd atf ST.K Family
Trust
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
4 May 2021
|
Date of Orders:
|
7 May 2021
|
Decision Date:
|
14 May 2021
|
Jurisdiction:
|
Equity - Duty List
|
Before:
|
Henry J
|
Decision:
|
Interlocutory relief sought by the cross-claimants refused.
|
Catchwords:
|
EQUITY – interlocutory injunctions – application to restrain
members’ meeting of unit trustee and other proposed
actions of trustee
– whether serious question to be tried as to validity of share and unit
transfers, removal of director of
trustee and replacement of trustee –
whether balance of convenience in favour of imposition of restraints
–serious questions
to be tried established but claims not strong –
risk of losing commercially favourable refinance – questions about
adequacy
of undertaking as to damages – interlocutory injunctions
refused
|
Legislation Cited:
|
|
Cases Cited:
|
|
Texts Cited:
|
J D Heydon, Heydon on Contract (2019, Thomson Reuters) Robert P Austin
and Ian M Ramsay, Ford, Austin and Ramsay’s Principles of Corporations Law
(17th ed, 2018, LexisNexis Butterworths)
|
Category:
|
Procedural rulings
|
Parties:
|
PNJ Investment Holding Pty Ltd ACN 621 816 439 (Plaintiff/First
Cross-Defendant) ST.K Family Pty Ltd ACN 610 890 778 atf ST.K Family Trust
(First Defendant/First Cross-Claimant) Havilah Green Pty Limited ACN 620 452
502 atf Havilah Green Unit Trust (Second Defendant/Second
Cross-Defendant) Heyday Investment Pty Ltd ACN 649 300 970 (Third
Defendant/Second Cross-Claimant) Everpro Investment Pty Ltd ACN 630 605 088
(Fourth Defendant/Third Cross-Claimant) AONE Development Partners Pty Ltd ACN
632 439 582 (Third Cross-Defendant) Lindfield Development Pty Ltd ACN 621 866
920 (Fourth Cross-Defendant) Lindvest DM Pty Ltd ACN 621 965 660 (Fifth
Cross-Defendant)
|
Representation:
|
Counsel: D Pritchard SC with J Lee (Plaintiff/First, Third and Fourth
Cross-Defendants) A Flecknoe-Brown (First, Third and Fourth Defendants/First,
Second and Third Cross-Claimants)
Solicitors: Yingke Law Firm (Sydney)
(Plaintiff/First, Third and Fourth Cross-Defendants) L’Orient Legal
(First, Third and Fourth Defendants/ First, Second Cross-Claimant and Third
Cross-Claimants)
|
File Number(s):
|
2021/102403
|
Publication Restriction:
|
Nil
|
JUDGMENT
- On
4 May 2021, I heard an application by the cross-claimants for interlocutory
relief seeking to restrain the second defendant, Havilah
Green Pty Ltd
(Company), from holding a meeting of members that was scheduled to take
place on 5 May 2021 and from taking certain steps in relation to a
real estate
development project on land located on Havilah Road, Lindfield (Project)
which is owned by the Company.
- Given
the urgency of the circumstances, the parties were content for me to indicate my
decision at the end of the hearing, which I
did in short, summary form, with
more detailed reasons to follow. These are my reasons for declining to grant
the interlocutory
relief sought.
- The
cross-claimants’ application, and the opposition to it, arises out of
disputes primarily between the plaintiff and first
cross-defendant, PNJ
Investment Holding Pty Ltd (PNJ), and the first defendant and first
cross-claimant, ST.K Family Pty Ltd (ST.K), about rights to units in the
Havilah Green Unit Trust (HG Unit Trust) and shares in the Company, and
whether the Company continues to be the trustee of the HG Unit Trust or has been
replaced by the
third defendant and second cross-claimant, Heyday Investment Pty
Ltd (Heyday). The cross-claimants contend that PNJ has invalidly
transferred ST.K’s units and shares to itself and its related companies
and that Heyday was validly appointed as trustee on 9 April 2021.
- There
was no dispute about the legal principles to be applied.
- In
determining the cross-claimants’ application for interlocutory relief, the
Court must first determine whether the cross-claimants
have made out a prima
facie case in the sense that, if the evidence remains as it is, there is a
probability they will be entitled
to the final relief claimed. This does not
mean that the cross-claimants must establish that it is more likely than not
they will
succeed on a final hearing, but only that there is a “sufficient
likelihood of success” to justify the preservation of
the status quo
pending the trial in the circumstances: Australian Broadcasting Corporation v
O’Neill (2006) 227 CLR 57; [2006] HCA 46 (ABC v O’Neill)
at [65] (Gummow and Hayne JJ), quoting Beecham Group Ltd v Bristol
Laboratories Pty Ltd [1968] HCA 1; (1968) 118 CLR 618 at 622–3; [1968] HCA 1
(Beecham v Bristol).
- The
other inquiry required is whether the inconvenience and injury the
cross-claimants would be likely to suffer if interlocutory
relief were refused
outweighs or is outweighed by the injury which PNJ and the other
cross-defendants would suffer if the injunctions
were granted: Beecham v
Bristol at 623.
- Also
relevant to the exercise of the Court’s discretion, and as raised in this
case, is the relative strengths of the parties’
cases and the adequacy of
the undertaking as to damages. The stronger the case for final relief, the less
may be required to tip
the balance of convenience to one side’s favour.
The greater the balance of convenience falls to one side, the less strong
a case
for final relief may be required: ABC v O'Neill at [65], [71].
- PNJ
submitted that the cross-claimants had not established the existence of a prima
facie case or serious question to be tried, or
at the least that their case was
weak. It also submitted that the balance of convenience was against the grant of
injunctive relief
in circumstances where a refinance of the Project on
commercially advantageous terms was at risk if injunctive relief was granted
and
there was reason to doubt the worth of ST.K’s undertaking as to damages.
- Before
addressing these matters, it is necessary to summarise the factual background
and claims made in these proceedings.
Factual background
- On
14 July 2017, the HG Unit Trust was established, and the Company was appointed
as the trustee.
- The
initial unit holders of the HG Unit Trust were ST.K, which held 82 units, and
Sydrock Pty Limited (Sydrock), which held 18 units: Unit Trust Fixed Deed
of the HG Unit Trust dated 14 July 2017 (HG Trust Deed), Schedule 1.
- On
25 September 2017, PNJ acquired all of Sydrock’s units in the HG Unit
Trust.
- PNJ
had been incorporated on 20 September 2017. At that time, Mr Sam You was
PNJ’s sole director. Mr You is currently the sole
director of ST.K.
Between 10 October 2017 and 20 November 2017, Mr Xing Huang was the sole
director and secretary of PNJ. Since 20
November 2017, Mr Zecheng Huang (Xing
Huang’s son) has been PNJ’s sole director secretary and
shareholder.
- From
31 October 2017 to 19 March 2021, PNJ owned 80% of the shares in the Company.
ST.K owned the other 20%. During that period, Xing
Huang and Ms Jie Tan (Mr
You’s wife and a shareholder of ST.K) were the directors of the Company.
- The
principal assets of the HG Unit Trust are three properties located on Havilah
Road, Lindfield (Project properties). The Company, as trustee for the HG
Unit Trust, is the registered proprietor of the Project properties. There is a
development approval
(DA) for the construction of a five-storey
residential building containing 43 units and two basement levels over the
Project properties.
The DA was obtained on 19 May 2020 following proceedings in
the Land and Environment Court.
- According
to Zecheng Huang’s evidence, at the time PNJ became a unit holder in the
HG Unit Trust, there was no property in the
HG Unit Trust other than the rights
and interests in relation to a put and call option deed over 7 Havilah Road,
Lindfield. Sydrock
had paid $230,000 in relation to the put and call option,
which PNJ had agreed to reimburse as a condition of acquiring Sydrock’s
units in the HG Unit Trust.
- In
September to October 2017, prior to settling the purchase of the Project
properties, there were discussions between Mr You and
Xing Huang about funds
needed for the Project. There is a dispute on the evidence as to precisely what
was discussed, although it
is common ground that ST.K did not have funds
available and PNJ agreed to lend it $3,000,000.
- On
or about 31 October 2017, a range of documents relating to the Project, the
$3,000,000 loan, the Company and the HG Trust were
signed by PNJ, ST.K and the
Company. Zecheng Huang’s evidence is that he had instructed a solicitor
to draft those documents
to reflect the agreements reached between the parties.
- Mr
You’s evidence is that he and Ms Tan signed the documents at the offices
of PNJ’s solicitor although they had not seen
them before signing. Mr You
gives evidence that he was told by PNJ’s solicitor, “You can sign
these documents now. If
you don’t agree with their terms, you can ask for
amendments later.”
- The
following documents were signed by the parties and are dated 3 November
2017:
(a) the Shareholders Agreement between the Company, PNJ and
ST.K, which records that PNJ holds 80% and ST.K holds 20% of the shares
and that
Xing Huang is PNJ’s and Ms Tan is ST.K’s representative director;
(b) the Commercial Loan Agreement between PNJ and ST.K;
(c) the Side Deed between PNJ and ST.K ;
(d) the Deed of Variation of Fixed Trust; executed by the Company, ST.K and
PNJ; and
(e) the Project Development Agreement between the Company, as Owner, and the
fifth cross-defendant, Lindvest DM Pty Ltd (Lindvest), as Developer of
the Project. Zecheng Huang is Lindvest’s sole director and shareholder.
Lindvest lodged the DA for the Project
properties.
- There
is evidence of communications between the solicitor for PNJ and the solicitor
for ST.K, in the form of emails during the period
from 3 to 8 November 2017,
that refer to amendments proposed by ST.K to the Commercial Loan Agreement, the
Shareholders Agreement
and the Project Development Agreement.
- The
Commercial Loan Agreement in evidence includes changes that are identified as
having been ‘agreed’ in the emails exchanged
between ST.K and
PNJ’s solicitors. These changes included an extension to the repayment
date of the $3,000,000 loan from 31
August 2018 to 31 January 2019 and a new
clause 27 that had been requested by ST.K’s solicitor.
- Zecheng
Huang’s evidence is that the documents referred to at [20] were exchanged on 8
November 2021. Presumably, the reference to ‘2021’ is in error and
Mr Huang intended to refer to
8 November 2017.
- The
Commercial Loan Agreement is between PNJ as Lender and ST.K as Borrower for the
principal sum of $3,000,000 and is stated to be
for the purpose of investment
within the Project. It relevantly includes the following
provisions:
7. DELAY
...
7.5 Without limiting the Lender’s power, on and after
the 31 January 2019, the Lender is entitled to issue a Notice of Demand
requesting the Borrower to repay all Money Owing within fourteen (14) days from
the issuing date of the Notice of Demand. The parties
agree and accept that the
time under this clause is reasonable.
7.6 If the Borrower failed to comply with such Notice, the
event will be treated as an event of default by the Borrower thereby
entitled
(sic) the Lender to exercise its power as the Borrower’s attorney to
rescind this Agreement and refund all repayment
made by the Borrower, if any,
and thereby sever the Borrower’s connection with those rights,
entitlements and benefits within
the Project.
7.7 Further to subclause 7.6, the Borrower hereby gives consent
irrevocably that the Principal Sum borrowed from the Lender, held
in the Unit
Trust, together with all rights, entitlements and benefits in the Project, will
be automatically transferred from the
Borrower’s name to the
Lender’s name in the Project.
...
9. DEFAULT AND TERMINATION
9.1 Consequences of default
(a) If any of the events described in
sub-clause 9.2 occurs, the Money Owing, including the Principal Sum, together
with all interest
accrued on the Principal Sum and not then paid and all other
amount payable under this Agreement and unpaid shall, at the option
of the
Lender and notwithstanding any delay or previous waiver of the right to exercise
that option, become due and payable upon
demand by the Lender.
(b) If the Borrower is unable to repay the Money Owing when it
becomes due and payable, the Borrower irretrievably appoints the
Lender as its
attorney to sever the Borrower’s connection with the rights, benefits and
entitlements within the Project. The
Lender needs to pay no consideration to the
Borrower for such severance irrespective the (sic) past, current or future
market value
of the Project at that time.
...
17. POWER OF ATTORNEY
17.1 The Borrower irrevocably appoints
(a) the Lender and its successors and
assigns; and
(b) after the occurrence of an event of default under Clause 9
or an event which, with the giving of notice or the lapse of time
or
both, would be an event of default; or
(c) after the Borrower has failed to comply with any of the
Borrower’s obligations under this Agreement or the security or
under any
Agreement or instrument required under or for the purposes of this Agreement or
the security or under any Agreement or
instrument collateral to this Agreement
or the security or to which this Agreement or the security is collateral, upon
request by
the Lender,
To do all acts and things and to execute all documents as may, in the
Lender’s opinion, be reasonably necessary or desirable
or expedient to
give effect to any right or power conferred on the Lender by this Agreement or
the security.
17.2 If this Agreement is executed on behalf of the Borrower or
the Lender by a person authorised to execute it under power of
attorney, that
person, by his or her execution of this Agreement, states that at the time of
such execution he or she had no notice
of the revocation of that power of
attorney.
...
27. NEW CLAUSE
Notwithstanding any other provisions in this Agreement, if the Lender exercises
its right under Clause 7 thereof to sever the Borrower’s
connection with
those interests, entitlements and benefits within the Project, then, such right
will be conditional upon the Lender
having procured, at its own costs and
liabilities, an unconditional full release and discharge of any guarantees
provided by the
Borrower (including Borrower’s directors and/or
shareholders) for the purpose of any mortgage within the Project only.
- The
Side Deed provides that it is interdependent with the Commercial Loan Agreement
and, by the Deed, the parties agreed to make additional
arrangements in
connection with the Project: Background A and B, cl 2.1. It includes the
following:
3. AGREEMENT TO INTEREST PAYMENT
3.1 STK acknowledges that the $3,000,000 it loaned to the Unit
Trust is borrowed from PNJ by five instalments.
3.2 STK accepts that it holds its part of the unit shares on
trust for PNJ.
3.3 STK therefore understands and accepts that it will not be
entitled to any interest payment on the $3,000,000 from the Unit
Trust unless
the full amount of $3,000,000 has been fully repaid to PNJ together with other
money payment described under the Commercial
Loan Agreement.
- Clause
4.1 of the Side Deed provides that PNJ will have the exclusive right to the
management and access to the Bank Accounts for
the purpose of the development of
the Project.
- The
Deed of Variation between the Company, ST.K and PNJ relates to the HG Trust
Deed, which is referred to as the “Fixed Deed”.
It includes the
following:
RECITALS
...
D. Under clause 89 of the Fixed Deed, the Trustee may vary the
Fixed Deed but only by a special resolution of the Unit Holders;
E. The Unit Holders have passed a special resolution and the
trustee has signed the resolution to vary the Fixed Deed.
F. The Trustee varied the Fixed Deed in the manner set out in
this Deed and the Unit Holders are the parties to this Deed to record
their
irrevocable consent to those amendments hereunder.
...
2. AMENDMENTS TO FIXED DEED
2.1 With effect from the Effective Date, the Fixed Deed is
irrevocably amended by:
...
(b) Page 17 – Clause 85
by delete (sic) the current Clause 85 and
insert (sic) new clause 85 read as follows:
“The unit holders must not remove any trustee at any time unless by
passing a unanimous resolution”
(c) Page 16 – Clause
82
by delete (sic) the current clause 82 and
insert (sic) new clause 82 read as follows:
“The unit holders may only appoint a new trustee by passing a unanimous
resolution. They may appoint a single trustee or more
than one. The appointment
is effective when the new trustee executes a deed binding the trustee to comply
with this Deed. Registration
of the Deed is not required unless the law demands
it.”
- The
HG Trust Deed provided that a new trustee may be appointed by passing a
resolution passed by 75% of unit holders (special resolution): cl 82. It
also provided that the Company could vary the HG Trust Deed by resolving to do
so in writing, although variations concerning
the issue, transfer or redemption
of units, the appointment or removal of a trustee and the variation of the deed
itself will not
be effective unless the unit holders consent to it by passing a
special resolution at the time of variation or before it: cl 89.
- Settlement
on the purchase of the Project properties occurred between 6 December 2017 and
14 March 2018. The evidence on this application
indicates
that:
(a) the total amount paid to settle the purchase of the
Project properties was $20,354,387.90, of which $13,354,387.90 was paid by
PNJ.
The amount paid by PNJ included the $3,000,000 that it had loaned to ST.K. The
balance of $7,000,000 was funded by way of loan
finance from NAB; and
(b) except for its assistance in applying for the mortgage with NAB, ST.K did
not make any financial contribution to the purchase,
exchange or settlement of
the Project properties.
- On
or about 8 February 2018, PNJ agreed to loan a further $500,000 to ST.K. Zecheng
Huang’s evidence is that this loan was also
due for repayment on 31
January 2019. He deposes that the $500,000 was advanced by PNJ to LSM
Constructions Pty Ltd, a company of
which Mr You is the sole director and
secretary.
- Zecheng
Huang deposes that, during 2019 and 2020, he sent a number of communications to
Mr You in which he sought repayment of the
loans to ST.K. His evidence is that
ST.K paid $230,000 towards the $500,000 loan during that period but no repayment
was made towards
the $3,000,000 loan.
- On
23 February 2021, PNJ’s solicitor sent a letter to ST.K demanding
repayment of the sum of $3,493,150.68, comprising the $3,000,000
principal sum
plus interest, within 14 days (letter of demand). The demand was stated
to be made pursuant to cl 7.5 of the Commercial Loan Agreement.
- The
letter of demand asserts that failure to comply with the demand would be treated
as an event of default by ST.K entitling PNJ
to exercise its power under
cl 7.6 of the Commercial Loan Agreement to rescind the Agreement and refund
all repayments made by ST.K
(which on their instructions was none) and
“thereby sever [ST.K’s] connection with those rights, entitlements
and benefits
within the Havilah Project”. The letter went on to state
that, if that occurred, PNJ would be ready, willing and able to procure
an
unconditional full release and discharge of any guarantees provided by ST.K for
the purpose of any mortgage within the Project.
- It
is common ground that ST.K did not pay any amount in response to the letter of
demand. Zecheng Huang’s evidence is that
he was informed by his solicitor
that the letter of demand was not complied with.
- On
19 March 2021, Zecheng Huang, in his capacity as the sole director and secretary
of PNJ and purporting to act as attorney of ST.K
pursuant to cl 17.1 of the
Commercial Loan Agreement, signed a share transfer form transferring the two
shares in the Company held
by ST.K to PNJ “for $2 or in accordance with
clauses 7.6 and 7.7 of the Commercial Loan Agreement”.
- On
the same day, Zecheng Huang, in his capacity as the sole director and secretary
of PNJ and on the basis that PNJ was the only member
of the Company, held a
meeting of the Company and passed a special resolution that purported
to:
(a) remove Ms Tan and Xing Huang from their position as
directors and Ms Tan as secretary of the Company;
(b) appoint Zecheng Huang as sole director and secretary of the Company;
and
(c) authorise the Company to enter into a loan agreement and associated
documents with Centennial LN Pty Ltd (Centennial) for the purposes of the
Project. Centennial was a financier who had made an offer to the Company for a
loan of $30 million in order
to refinance the NAB facility and undertake
construction on the Project.
- On
19 and 22 March 2021, Zecheng Huang, in his capacity as the sole director of PNJ
and purporting to act as attorney of ST.K under
cl 17.1 of the Commercial Loan
Agreement, signed two Deeds of Transfer of Units pursuant to which 41 units in
the HG Unit Trust were
transferred from ST.K, as vendor, to AONE Development
Partners Pty Ltd (AONE), as purchaser, on 19 March, and 41 units were
transferred from ST.K, as vendor, to Lindfield Development Pty Ltd
(Lindfield), as purchaser, on 22 March.
- On
19 March 2021, ST.K lodged caveat AQ890598 on the title to the Project
properties, which had by then been amalgamated, claiming
a beneficial interest
in them by virtue of the operation of cls 14 and 15 of the HG Trust Deed.
- Clauses
14 and 15 of the HG Trust Deed provide:
14 Trustee holds the assets of the trust as a separate fund on
trust for the unit holders. The beneficial interest in the trust
at any time is
vested in the holders of units in the trust at that time, in proportions
determined in accordance with the rights
attaching to the units.
Each unit entitles the holder to an equal share with each other unit holder of a
unit in the beneficial interest in the trust as
a whole.
15. Despite any other provision of this deed, in accordance
with clause 14, each unit holder is presently entitled to their proportionate
share in:
• the income of the trust, subject only
to the proper payment of expenses by and of the trustee relating to the
administration
of the trust; and
• the trust’s
assets.
- On
26 March 2021, PNJ’s solicitor sent a letter to ST.K’s solicitor
advising that, as a result of ST.K’s failure
to make any substantive
response to the 23 February letter of demand, “all necessary enforcement
actions pursuant to the Commercial
Loan Agreement” as prescribed in the
letter of demand had been taken and effected. The letter went on to assert that
ST.K was
no longer a unit holder of the HG Unit Trust and that all rights,
benefits and entitlements held by ST.K had been severed or otherwise
relinquished and the shares in the Company held in ST.K’s name had been
assigned and transferred pursuant to the Commercial
Loan Agreement and the
letter of demand.
- On
2 and 7 April 2021, further correspondence was exchanged between ST.K and
PNJ’s solicitors. In that correspondence, PNJ requested
that ST.K withdraw
the caveat. ST.K refused to withdraw the caveat and asserted that the purported
transfers of ST.K’s interests
under the Commercial Loan Agreement were
invalid because they were not in writing, PNJ had not rescinded the Commercial
Loan Agreement,
and Ms Tan remained a director of the Company.
- On
7 April 2021, PNJ called for a meeting of members of the Company to be held on
29 April 2021 at 10 am to pass a resolution that
Ms Tan be removed as director.
Zecheng Huang’s evidence is that he called the meeting because of the
dispute as to whether
or not Ms Tan had been validly removed as a director of
the Company with effect from 19 March 2021. The meeting was postponed due
to the
orders made by consent on 28 April 2021 in these proceedings, referred to at [52] below.
- On
9 April 2021, ST.K purported to hold a meeting of unit holders in the HG Unit
Trust. Zecheng Huang attended the meeting on behalf
of PNJ. A representative of
Everpro Investment Pty Ltd (Everpro), the fourth defendant and third
cross-claimant and a company to whom ST.K had purportedly transferred one unit
in the HG Unit Deed,
was also in attendance.
- During
the meeting, a vote was taken on a resolution proposed by ST.K to remove the
Company and appoint Heyday as trustee of the HG
Unit Trust. Mr You is the sole
director and secretary of Heyday. Zecheng Huang voted against the resolution,
having noted his objection
to the vote on the basis that any change in trustee
had to be by unanimous resolution according to the Deed of Variation. ST.K and
Everpro voted for the resolution and it was announced that the resolution passed
by a majority.
- On
12 April 2021, ST.K’s solicitor sent to PNJ’s solicitor a copy of
the minutes of the meeting held on 9 April 2021 and
a Deed of Appointment in
relation to Heyday’s appointment as trustee.
- On
14 April 2021, Heyday lodged caveat AQ960440 on the title to the amalgamated
Project properties claiming that the land was held
by the Company on trust for
the benefit of unit holders and that, by special resolution on 9 April 2021, the
unit holders had resolved
to remove the registered proprietor and appoint the
caveator as the trustee.
These proceedings
- On
13 April 2021, PNJ commenced these proceedings by summons against ST.K, the
Company, Heyday and Everpro seeking urgent interlocutory
and final relief.
- By
way of final relief, PNJ seeks declarations that it is the sole legal and
beneficial owner of all unit shares within the HG Unit
Trust, that ST.K’s
units were validly transferred to AONE and Lindfield, and that the resolution at
the 9 April meeting and
the transfer of one unit in the HG Unit Trust to Everpro
are void and have no effect. PNJ also seeks judgment in the sum of $270,000.
- On
15 April 2021, consent orders were made by Slattery J that dealt with
PNJ’s application for interlocutory relief. Those orders
restrain Heyday
from exercising its alleged power as trustee of the HG Unit Trust and restrain
ST.K and Everpro from disposing, encumbering
or otherwise dealing with the units
they contend they hold until further order of the Court.
- On
21 April 2021, ST.K, Heyday and Everpro filed a cross-summons against PNJ, the
Company, AONE, Lindfield and Lindvest. The cross-summons
seeks a range of
declarations by way of final relief, including that:
(a) cls 7.6 and
7.7 of the Commercial Loan Agreement are void by reason of uncertainty, penalty
or forfeiture or, alternatively, that
it is a precondition to their operation
that the Commercial Loan Agreement be rescinded;
(b) the purported transfers of 82 units in the HG Unit Trust from ST.K to
AONE and Lindfield were invalid;
(c) ST.K remains the beneficial owner of 82 units in the HG Unit Trust and 18
shares in the Company;
(d) the purported removal of Ms Tan as a director of the Company on 19 March
2021 was void;
(e) cls 2.1(b) to (e) of the Deed of Variation are void because no special
resolution of unit holders was passed at the time of the
variation;
(f) Heyday was validly appointed as trustee of the HG Unit Trust on 9 April
2021;
(g) the Property Development Agreement is not binding on the Company; and
(h) the Company is indebted to ST.K in the sum of $3,000,000.
- The
cross-summons also seeks interlocutory relief to restrain the meeting of members
of the Company which PNJ had called to be held
on 29 April 2021.
- On
28 April 2021, I made orders by consent listing the hearing of the
cross-claimants’ claim for interlocutory relief before
me on 4 May 2021
and noted, on a without admissions basis, the undertaking of PNJ and the
Company, by its director, Zecheng Huang,
not to proceed with and to adjourn the
meeting of members of the Company until 4 pm on 5 May 2021.
- At
the hearing on 4 May 2021, I granted the cross-claimants leave to file an
amended cross-summons to include an additional claim
for interlocutory relief
seeking to restrain the Company from taking any of the actions described in the
affidavit of Zecheng Huang
affirmed 30 April 2021 at [56] (proposed Trustee
actions), being:
(a) to remove the caveats lodged by ST.K and
Heyday;
(b) to finalise and settle the finance on offer from Centennial;
(c) to commence construction of the Project using the proceeds of the loan
from Centennial; and
(d) to otherwise act as trustee and in the best interest of the HG Unit
Trust.
- There
was no appearance by the Company at the hearing. I was informed this was because
ST.K’s solicitor had taken issue with
PNJ’s solicitor purporting to
act on its behalf. The only parties who appeared at the hearing were ST.K,
Heyday and Everpro
(the cross-claimants) and PNJ.
- At
the start of the hearing, the cross-claimants made an open offer to resolve the
matters in dispute. The offer was for Ms Tan, in
her capacity as a director of
the Company, to agree to the lodging of lapsing notices in relation to the
caveats on the Project properties
on the condition that PNJ relented from
attempting to remove Ms Tan as a director.
- The
offer was not accepted by PNJ because of its conditionality and the hearing
proceeded.
- In
support of their application for interlocutory relief, the cross-claimants read
the affidavit of Sam You dated 21 April 2021. Mr
You gave evidence of dealings
between ST.K and PNJ, details of which are included in the background section
above. He also asserted
that ST.K’s rights as a holder of the majority of
units on the HG Unit Trust and minority shareholder in the Company may be
affected if the meeting of the Company proceeded as proposed by PNJ and Ms Tan
was removed as director.
- PNJ
relied on two affidavits of Zecheng Huang affirmed 13 April and 30 April 2021
and the documents exhibited to those affidavits
(Exhibits A and B).
- In
addition to matters set out in the background section above, Mr Huang deposes
that the current mortgage and loan with NAB is due
to expire on 30 September
2021 and that the terms offered by the loan from Centennial, which he had been
negotiating since October
2020, are commercially favourable. His gives evidence
that, in his view, mortgage loans from commercial banks with lower interest
rates normally include pre-sale conditions, which the HG Unit Trust is unlikely
to meet before the NAB loan expires in September
2021, and that
Centennial’s interest rate of 7% is lower than the rates of 13% to 14%
which would otherwise be available on
loans without pre-sale conditions, based
on his enquiries.
- Mr
Huang deposes that the Centennial loan had been due to settle on 21 April 2021,
that the date for settlement had been extended
and that Centennial would
consider not proceeding if the loan is unable to settle by 17 May 2021. He
states that the Company would
be exposed to costs if the Centennial loan did not
settle, which he estimated to be around $100,000 as at 30 April 2021.
- At
the end of oral submissions, the cross-claimants sought to adduce a further
affidavit to address issues raised by PNJ regarding
the adequacy of the
undertaking as to damages. I adjourned the hearing until 4 pm and stated that I
would consider any application
at that time, noting PNJ’s objection to any
further evidence.
- When
the matter resumed, the cross-claimants sought to rely on a second affidavit by
Mr You dated 4 May 2021, which I admitted in
part noting that some of the
admitted parts were read as submission. In the affidavit, Mr You deposes that
Hong Da Investment Pty
Ltd (Hong Da), a company of which Ms Tan is the
sole director and he and Ms Tan are the only shareholders, has developed and
owns townhouses in
Turramurra, some of which are available for sale. Mr
You’s evidence is that some townhouses have already been sold for $1.7
million each, and the remaining townhouses still owned by Hong Da give rise to
available net assets of the company of about $5 million
after accounting for its
debts.
- At
that time, Counsel for the cross-claimants also informed the Court that he was
instructed by Ms Tan that Hong Da would give the
undertaking as to damages.
Cross-claimants’ application for interlocutory
relief
- Three
aspects of the cross-claimants’ case for final relief were relevant to
their claims for interlocutory relief.
- The
first two aspects are the claims that the transfers of ST.K’s shares in
the Company to PNJ and units in the HG Unit Trust
to AONE and Lindfield pursuant
to the terms of the Commercial Loan Agreement were invalid, and the resolution
of the Company on 9
April 2021 to remove Ms Tan as a director was void. These
aspects were said to be relevant to the claim for interim relief seeking
to
restrain the meeting of members on 5 May 2021.
- The
third aspect is the claim that parts of the Deed of Variation are void and that
Heyday was validly appointed as trustee of the
HG Unit Trust on 9 April 2021.
This was submitted to be the basis of the second interim injunction sought to
restrain the proposed
Trustee actions.
Prima facie case
- The
cross-claimants submitted that they had established a prima facie case in
relation to the three aspects of their claims for final
relief. As noted above,
PNJ disputed the existence of any serious questions to be tried and submitted,
in the alternative, that
the claims propounded by the cross-claimants for final
relief were weak.
- As
to the validity of the purported transfer of ST.K’s shares and units
pursuant to the Commercial Loan Agreement, the cross-claimants
submitted that
there are four bases on which they would be entitled to the final relief
claimed, each of which was said to give rise
to a prima facie case.
- The
first is the claim that cls 7.6 and 7.7 of the Commercial Loan Agreement are
void for uncertainty, in the sense of being devoid
of any ascertainable meaning.
The cross-claimants submitted that the concept of “sever[ing] the
Borrower’s connection
with those rights, entitlements and benefits within
the Project” prescribed no identifiable legal consequence with respect
to
the Borrower’s rights, entitlements and benefits, and there was a lack of
clarity as to what was meant by the reference
in those clauses to “within
the Project”.
- PNJ’s
primary position was that the transfer of ST.K’s shares and units was
authorised by cls 7.6 and 7.7 of the Commercial
Loan Agreement. It submitted
that the clauses were not void for uncertainty, contending that the high
threshold required for clauses
in commercial arrangements to be void for
uncertainty had not been met in this case. It argued that the reference to
“severance”
of the “Borrower’s rights, entitlements and
benefits within the Project” would be given meaning by the Court having
regard to the relevant documents, the position of the parties and the language
used.
- Given
the urgency and interlocutory nature of the application, I did not determine the
question of construction of cls 7.6 and 7.7
of the Commercial Loan Agreement,
and cl 9.1(b) which also includes the expression “sever the
Borrower’s connection with
[the] rights, entitlement and benefits within
the Project.” However, I was of the view that there was merit in
PNJ’s
position on the interpretation of those clauses.
- The
Courts generally strive to uphold commercial bargains and construe the terms of
commercial contracts, with an inclination to give
effect to the intention of the
parties even if that intention may be somewhat obscurely or unclearly expressed
and the language used
open to more than one interpretation: Upper Hunter
County District Council v Australian Chilling & Freezing Co Ltd [1968] HCA 8; (1968)
118 CLR 429 at 436–7; [1968] HCA 8.
- As
PNJ submitted, the recitals and cl 4.1 of the Commercial Loan Agreement identify
that PNJ loaned $3,000,000 to STK for the sole
purpose of enabling STK to invest
in the Project, with the “Project” defined in the Commercial Loan
Agreement to mean
“the project for the development and, either sale or
rental or a combination of sale and rental, of real property comprised
in the
Project Land”. The interests of ST.K in the “Project” so
defined were, in reality, its units in the HG Unit
Trust and its shareholding in
the Company, such that the power to “sever” ST.K’s connection
with its “rights,
entitlements and benefits” within the Project, as
contemplated within cls 7.6, 7.7 and 9.1(b), could be interpreted as relating
to
those units and shares.
- Although
“sever” is an unusual word to use, its usual meaning is to
“separate”, “remove” or “end
connection
with”, which suggests that the parties contemplated that, in the event
that ST.K defaulted on the loan, PNJ, acting
as ST.K’s attorney, would be
entitled to “transfer out or away” ST.K’s rights and benefits
in the Project,
in the sense of its interests in the units and shares. I was
also of the view that the existence of the trust language in cl 6.6
of the
Commercial Loan Agreement and in cls 3.1 and 3.2 of the Side Deed, under which
STK acknowledges that its contribution to the
unit trust is borrowed from PNJ
and that it holds its unit shares on trust for PNJ, supported PNJ’s
position, as did the evidence
on the application that the parties had been
negotiating the terms of the Commercial Loan Agreement, including cls 7 and 27.
- It
was also difficult to see what meaning, other than that advanced by PNJ, could
be given to cls 7.6, 7.7 and 9.1(b) based on the
language used, the
circumstances addressed by the Commercial Loan Agreement, the commercial purpose
or objects to be secured, and
its context by reference to the suite of documents
entered into: Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd
(2015) 256 CLR 104; [2015] HCA 37 at [46]–[47].
- That
said, I accepted the cross-claimants’ submission that cls 7.6, 7.7 and
9.1(b) of the Commercial Loan Agreement were “idiosyncratically
drafted”, it was reasonably arguable that there was some ambiguity as to
precisely what was meant by those clauses and there
was a serious question as to
how the clauses would be interpreted. I was also of the view that this question,
and any ambiguity,
would need to be resolved at a final hearing with the benefit
of further evidence of the surrounding circumstances objectively known
to the
parties: Lawrence v Ciantar [2020] NSWCA 89 at [101].
- Thus,
I concluded that there was a serious question to be tried as to the proper
construction and operation of cls 7.6 and 7.7 of
the Commercial Loan Agreement,
including what rights they gave to PNJ to transfer ST.K’s units and
shares, but that the cross-claimants’
case that the clauses were void
because of uncertainty was weak.
- The
second prima facie case asserted by the cross-claimants was that cls 7.6 and 7.7
of the Commercial Loan Agreement are unenforceable
as either an unconscionable
forfeiture of proprietary rights or a contractual penalty as they purported to
entitle PNJ to not only
rescind the Agreement and refund all repayments but also
to confiscate ST.K’s shares and units on no or inadequate consideration,
such as the $1 per unit which was applied.
- The
cross-claimants submitted that the forfeiture of rights was an additional
liability that secured enjoyment of a collateral object
and beyond any kind of
pre-estimate of the loss occasioned by a default, and hence an invalid penalty,
relying on Legione v Hateley (1983) 152 CLR 406; [1983] HCA 11
(Legione v Hateley), Andrews v Australia & New Zealand Banking
Group Ltd (2012) 247 CLR 205; [2012] HCA 30 and Paciocco v Australia
& New Zealand Banking Group Ltd (2016) 258 CLR 525; [2016] HCA 28. It
was also submitted that the clauses operated as an unconscionable forfeiture of
property against which equity relieved because
the shares and units were
property which went beyond a mere contractual licence, referring to Auburn
Shopping Village Pty Ltd v Nelmeer Hoteliers Pty Ltd [2017] NSWSC 1230 at
[211]–[212].
- In
denying that a serious question arose that cls 7.6 and 7.7 were unenforceable as
a contractual penalty or an impermissible forfeiture,
PNJ submitted that the
arrangement agreed to by the parties was for ST.K’s units to operate as
security for the $3,000,000
loan advanced to STK and were held on trust for PNJ,
relying on cl 3.2 of the Side Deed and cl 6.6 of the Commercial Loan Agreement.
It was submitted that cls 7.6 and 7.7 could not be a penalty where ST.K’s
failure to repay the loan on demand meant that PNJ’s
beneficial interest
in the trust arrangement over the units converted to a proprietary interest
which was beneficial and, consequentially,
legal. It was also submitted that the
transfer of units away from ST.K was not an unconscionable assumption of
property where PNJ
was, at all times, the beneficial owner of the units.
- While
there was merit to PNJ’s submission based on the trust language used in
the Side Deed and the Commercial Loan Agreement,
I considered it to be arguable
that ST.K retained a proprietary interest in the units and that a claim based on
forfeiture could
arise. This was because the clauses operated to determine
ST.K’s interests in the Project (namely its units and shares) in
favour of
PNJ by way of forfeiture as a means of securing performance of the primary
stipulation to repay the loan and arose on the
occurrence of the event of
default in repayment of the loan and breach of the Commercial Loan Agreement.
- However,
based on the evidence on the application, I came to the view that the claim was
not a strong one.
- It
was difficult to see how cls 7.6, 7.7 or 9.1(b) operated in a penal way or
involved an unconscionable forfeiture of proprietary
rights in circumstances
where ST.K accepted at the hearing that it owed PNJ $3,000,000 and, according to
the unchallenged evidence
on this application, ST.K had not contributed any
monies towards the purchase of the Project properties, the only real assets of
the HG Unit Trust. There was also no evidence led by the cross-claimants that
supported a finding that the forfeiture of ST.K’s
units and shares for
non-payment of the loan far exceeded or was out of all proportion with the value
to ST.K of its units and shares
and thus, was unconscionable or inappropriate in
the circumstances. Based on the arrangements between the parties and PNJ’s
legitimate commercial interests as the funder of the Project, this did not seem
to me to be a case of an “ill-merited windfall”
for PNJ. There was
also no suggestion that PNJ’s conduct contributed to ST.K’s breach
of the Commercial Loan Agreement
or that the breach was trivial or slight. The
loan had been outstanding for two years and no payments had been made:
Legione v Hateley at 429 (Gibbs CJ and Murphy JJ), 449 (Mason and Deane
JJ).
- The
third basis on which the cross-claimants contended there was a prima facie case
that the purported transfers were invalid was
the contention that the
consequences prescribed by cl 7.6 and 7.7 could only operate if PNJ took the
step of rescinding the Commercial
Loan Agreement. It was submitted that PNJ had
not demonstrated that rescission of the Agreement had occurred and that, absent
such
evidence, it must be presumed that it had not occurred.
- PNJ
did not take issue that rescission was necessary under cl 7.6. Rather, it
submitted that there was evidence that rescission of
the Commercial Loan
Agreement had occurred by PNJ’s conduct, of which ST.K was aware, of
transferring the units of ST.K to
AONE and Lindfield and the shares to itself as
attorney of ST.K. PNJ also relied on the letter from PNJ’s solicitor to
ST.K’s
solicitor dated 26 March 2021 which states that “All
necessary enforcement actions pursuant to the Commercial Loan Agreement
...
prescribed in [the letter of demand] have been taken and effected”, ST.K
was no longer a unit holder in the HG Unit Trust
and the shares in the Company
had been transferred to others.
- An
innocent party may elect to rescind a contract by disaffirming it. The
rescission will not be effective unless an unequivocal intention
to disaffirm
the contract is communicated to the other party, which may be done by words or
conduct: J D Heydon, Heydon on Contract (2019, Thomson Reuters) at
[31.170], [31.190].
- The
terms of the letter of demand from PNJ’s solicitor dated 23 February 2021
seemed to me to unequivocally communicate an intention
on the part of PNJ to
exercise powers under cl 7.6 and 7.7 of the Commercial Loan Agreement in the
event ST.K did not make payment
in accordance with the demand, which included
the rescission of the Agreement. I was also of the view that the 26 March 2021
letter
unequivocally communicated that PNJ had purportedly exercised those
powers.
- However,
there is no express reference to any rescission or termination of the Commercial
Loan Agreement in the 26 March letter and
no notice was given to ST.K that PNJ
disaffirmed that agreement after ST.K’s default. While ultimately this may
give rise to
an issue of form over substance, I was persuaded that it was
arguable that the cross-claimants had established a prima facie case
on the
documents although, again, I accepted that it was not a strong case.
- The
fourth matter relied on by the cross-claimants was the contention that the
purported compulsory transfer of ST.K’s units
in the HG Unit Trust was
unenforceable as it did not comply with ss 52A and 54A of the Conveyancing
Act 1919 (NSW). The cross-claimants made three submissions on this issue:
that the transfer of ST.K’s beneficial interests as unit holders
in the
trust properties was a transfer of interests in land and must have amounted to a
sale of land; that the Commercial Loan Agreement
itself did not purport to
effect the transfer of units and thus is not a contract for the sale of land;
and, absent such a contract,
the transfer was unenforceable as it could not
comply with ss 52A and 54A of the Conveyancing Act 1919 (NSW).
- PNJ
submitted that the writing requirements of ss 52A and 54A of the Conveyancing
Act 1919 (NSW) did not apply to a transfer of units in the HG Unit Trust
and, therefore, those sections were no impediment to the efficacy
of the
transfer of ST.K’s units.
- The
parties did not refer me to any particular aspects of the HG Trust Deed and its
related agreements or any authorities in support
of their submissions on the
question of whether ss 52A and 54A of the Conveyancing Act applied in
this case.
- A
unit holder in a unit trust may have a proprietary interest in trust property.
Whether this is so will depend on the terms of the
unit trust: Jonsue
Investments Pty Ltd v Balweb Pty Ltd [2013] NSWSC 325 (Jonsue
Investments) at [20], [25], [36]. Based on cl 14 of the HG Trust Deed,
aspects of which are similar to the terms considered in Jonsue
Investments, I accepted that there was a serious question to be tried that a
transfer of ST.K’s units in the HG Unit Trust would involve
a transfer of
ST.K’s equitable and beneficial interests as unit holder in the trust
properties and, thus, a disposition of
an interest in land.
- That
said, I had some doubt that the transfers of units in the HG Unit Trust from
ST.K amounted to sales of land within the meaning
of s 52A of the
Conveyancing Act or that the present is an action or proceeding brought
upon a contract for the disposition of an interest in land within the meaning
of
s 54A.
- Further,
even if the purported exercise by PNJ of the right to sever and effect a
“compulsory transfer” of ST.K’s
units involved a disposition
of an interest in land, it seemed to me that the requirement of writing was
likely satisfied as the
relevant dispositions were evidenced by the Deeds of
Transfer of Units dated 19 and 22 March 2021 between ST.K and AONE and ST.K
and
Lindfield respectively rather than the Commercial Loan Agreement itself which,
as the cross-claimants contended, did not purport
to effect the transfer.
- In
summary, I was satisfied that the cross-claimants had established the existence
of a serious question to be tried or a prima facie
case as to the validity of
the transfers of ST.K’s units and shares but accepted PNJ’s
submission that the claim was
not strong and aspects of it were weak.
- In
relation to the removal of Ms Tan as a director of the Company, the
cross-claimants submitted there was a serious question to be
tried that this
amounted to oppression or unfair discrimination against a minority shareholder,
relying on the principles set out
in Re Bicher & Son Pty Ltd [2020]
NSWSC 711 at [76]–[79]. It was submitted that the purpose of removing Ms
Tan was to enable PNJ to determine the commercial decisions to be made
by the
Company as purported trustee, contrary to the wishes of ST.K as the minority
shareholder and majority unitholder, and prevent
ST.K from having any
opportunity to participate in the Company’s decision making. This was
submitted to be unfair, particularly
in the context of the alleged penal
operation of cls 7.6 and 7.7 of the Commercial Loan Agreement.
- PNJ
submitted that Ms Tan’s removal does not amount to oppression because she
is not presently acting in the interests of the
Trust. It argued that this was
evidenced by her refusal, until the morning of the hearing, to take steps to
permit the Company to
protect its position by lodging lapsing notices for the
caveats or to appoint a solicitor to appearing in these proceedings. It also
said that the prior attempts to remove Ms Tan and any associated defects in
procedure are irrelevant to the present application,
which concerned the
members’ meeting scheduled for Wednesday 5 May 2021.
- The
removal of a director which has been appointed by a member may constitute
oppression where doing so excludes the member from participating
in management
of the company contrary to the common understanding between members and a
legitimate expectation of that member of
such participation in management:
Remrose Pty Ltd v Allsilver Holdings Pty Ltd (2005) 225 ALR 588; [2005]
WASC 251 at [73]–[74], [125]–[127]; Re Mosman & Co Pty
Ltd [2019] NSWSC 1155 [83]–[84]; see also Robert P Austin and Ian M
Ramsay, Ford, Austin and Ramsay’s Principles of Corporations Law
(17th ed, 2018, LexisNexis Butterworths) at [10.460.15] and the cases cited
therein.
- I
was persuaded that it is arguable that the removal of Ms Tan as a director would
be in breach of the Shareholders Agreement, as
it provides that only ST.K could
remove its representative and appoint a replacement: cl 3.7(b). This was a
factor that supported
ST.K’s prima facie case of oppression as the
Shareholders Agreement could be said to provide a basis for which ST.K, as a
minority
shareholder, had a legitimate expectation of a right to be involved in
the management of the Company.
- The
claim of oppression and unfair discrimination is, however, dependent on the
success of ST.K’s claim about the validity of
PNJ’s actions in
transferring ST.K’s units and shares. It was only if those transfers were
invalid that ST.K remains
a minority shareholder in the Company and majority
unitholder in the HG Unit Trust, although arguably ST.K holds the units on trust
for PNJ.
- The
evidence on this application also suggests that there will be a significant
dispute about whether Ms Tan’s removal would
be considered to be
commercially unfair and oppressive in the circumstances of this case. As noted
above, the evidence is that PNJ,
as majority shareholder, had contributed the
settlement funds for the Project properties. There is also evidence that Zecheng
Huang
took the lead in seeking out refinance for the Project, was liaising with
the NAB in relation to paying out the existing mortgages
and took the lead in
pursuing the DA approval for the Project properties. No evidence was led by the
cross-claimants that Ms Tan
had been actively involved in the management of the
Company or had sought such involvement, or what expectation she and ST.K had
to
be involved in the day to day management of the Company.
- Accordingly,
I accepted that STK’s claim of oppression was also arguable but that it
was a weak case based on the evidence on
this application.
- Turning
to the third aspect of their case, the cross-claimants submitted a prima facie
case arose that Heyday had been validly appointed
as the replacement trustee of
the HG Unit Trust based on the documents in evidence.
- They
submitted that the Deed of Variation, which provided for a unanimous resolution
for removal of a trustee, contravened the entrenching
provision of cl 89 of the
HG Trust Deed in relation to variations concerning “the appointment or
removal of a trustee”
as there was no evidence that a special resolution
of unitholders had been made consenting to that variation. As a consequence,
they
submitted that it was seriously arguable that the resolution voted on at
the 9 April 2021 meeting appointing Heyday as trustee was
passed by a sufficient
majority of unitholders to comply with the requirements of the HG Trust Deed
(cls 82, 85) and the Company
was “immediately” required under that
Deed to take steps to transfer its interests in the Project properties to Heyday
as the new trustee.
- In
response, PNJ contended that it was not arguable that Heyday had been validly
appointed as trustee. It submitted that the Deed
of Variation amended the
procedure for removing a trustee to require a unanimous resolution of
unitholders and that ST.K was estopped
from denying that it did so. PNJ pointed
to the recitals to the Deed of Variation which stated that the unit holders had
passed the
special resolution required to amend the HG Trust Deed.
- Where
an unambiguous proposition or allegation of distinct facts is made within a
deed, including statements made in the recitals,
a party to the deed is estopped
from denying the truth or operation of that proposition: Dabbs v Seaman
[1925] HCA 26; (1925) 36 CLR 538 at 549–550; [1926] HCA 26; Re Application of
Sutherland [2014] NSWSC 821 at [90]. The principle is founded on the
solemnity of a deed: Labracon Pty Ltd v Cuturich [2013] NSWSC 97 at
[132].
- Estoppel
by deed only operates in an action on the deed. In other proceedings, the
recitals can operate as an admission, but not as
an estoppel: Lescap Group
Pty Ltd v Pacific Resort Holding Pty Ltd [2012] NSWSC 580 at [43].
- The
parties did not make submissions on the question of whether the claim raised in
the present proceedings involves an action on
the Deed of Variation or is more
properly characterised as proceedings brought in respect of transactions which
are collateral to
the Deed, and, in the time available, I did not come to a
final view on that matter. Nevertheless, in the absence of any evidence
being
adduced by the cross-claimants that negated the implication of fact from the
recitals that a special resolution had been passed
and in circumstances where
the Deed of Variation was signed by Ms Tan on behalf of the Company and
representatives of ST.K and PNJ,
I was not persuaded that it was seriously
arguable that ST.K could resile from the recitals and claim that the Deed of
Variation
was not binding on it.
- Accordingly,
I was not satisfied that the cross-claimants had established a prima facie case
that Heyday was validly appointed as
trustee of the HG Unit Trust on 9 April
2021, in the sense that, if the evidence remained as it was, there was a
sufficient likelihood
that they would be entitled to the final relief claimed on
that aspect of the case.
Balance of convenience
- The
cross-claimants submitted that the balance of convenience favoured the grant of
interlocutory relief because the terms of refinance
proposed by Centennial
created potential issues as the Event of Default and Material Adverse Effect
provisions would be triggered
if the Company had been validly removed and
replaced by Heyday as trustee. It was submitted that this could lead to
liability for
damages secured against the Project properties which may give rise
to prejudice to the beneficiaries under the HG Unit Trust, whoever
they may be.
Pausing here, as I was not persuaded of a prima facie case that Heyday had been
validly appointed as trustee, this risk
did not seem to me to be significant to
the assessment of where the balance of convenience lay in this case.
- The
cross-claimants also contended that, absent interim relief being granted, ST.K
would be shut out from having a say in the conduct
of the HG Unit Trust to its
potential prejudice. They argued that the Company (and PNJ) would retain power
to deal with the Project
properties in a manner that may expose the trust assets
to other claims, such as unsecured loans, noting that a liability of around
$48,289.32 had already been incurred in relation to Centennial’s proposal.
- The
cross-claimants further submitted that there was no particular or immediate
benefit to be secured if PNJ’s proposal to remove
Ms Tan goes ahead as
ST.K and Heyday could apply to extend the caveats if the Company issued lapsing
notices. In other words, it
could not be assumed that the Centennial refinancing
would be able to proceed quickly in the absence of clear title to the Project
properties.
- PNJ
submitted that the balance of convenience did not favour the cross-claimants in
this case as the grant of interim relief would
risk the loss of the commercially
favourable loan on offer from Centennial and delay the progress of the Project.
It argued that
the Centennial loan was preferable to the cross-claimants’
position, which did not involve any alternative financing proposal,
and did not
give rise to any real risk of prejudice for the cross-claimants.
- PNJ
also took issue with the adequacy of the undertaking as to damages proffered.
- The
cross-claimants’ claims are concerned with a dispute about the respective
interests in a private unit trust and corporate
trustee. The principal assets of
the trust are the Project properties, in respect of which PNJ, not ST.K, had
invested significant
sums of money and which have DA approval for a real estate
development to be carried out on behalf of the Company by Lindvest. It
is common
ground that some refinancing will need to be put in place in order for the
Project to progress within the next four months.
- An
issue with the cross-claimants’ submission that, at a commercial level, it
wished to have the opportunity to be involved
in this development and, absent
interim relief restraining the meeting, it would be “shut out” from
doing so, is that
the evidence did not, in my view, demonstrate a desire or
willingness on the part of ST.K, Ms Tan or the other cross-claimants to
be
involved in and make decisions to progress the development of the Project with
PNJ. There was no indication that, if the relief
sought was granted, Ms Tan
would participate in and carry out her role as a director in the best interests
of the HG Unit Trust.
- The
evidence and the open offer made at the start of the hearing suggested that
there would be little co-operation from Ms Tan in
relation to the Company and
the Project, noting that there had been no agreement by her to the Company
issuing lapsing notices. Relevantly,
this is in the context where ST.K’s
caveat was lodged only after the notice of demand to repay the loan was issued,
the refinancing
with Centennial was being progressed, and a clause in the HG
Trust Deed provides that units holders must not lodge a caveat in relation
to an
asset or claim any interest in an asset of the trust in any other way: cl 16.
- The
Company has an offer from Centennial of a loan on financially advantageous terms
that provides for Zecheng Huang to be the sole
guarantor and which the evidence
indicates would be at risk if the interlocutory injunctions were granted. The
hearing proceeded
on the basis that the cross-claimants, and presumably Ms Tan,
will not accede to Centennial’s offer despite there being no
evidence from
Mr You or Ms Tan as to why the terms proposed were not acceptable to ST.K or
alternative financing options.
- Overall,
there was a lack of evidence put forward by the cross-claimants as to precisely
what was prejudicial with the proposals put
forward by Zecheng Huang, on behalf
of the Company, in finalising and settling the finance with Centennial and
commencing the construction
using the proceeds from that loan. There was also a
lack of evidence from which to infer that, if the meeting of members went ahead
and Ms Tan was removed as a director, Zecheng Huang, on behalf of the Company,
would act otherwise than in the best interests of
the HG Unit Trust or expose
the trust assets to claims which would cause injury or prejudice to the
cross-claimants.
- To
the extent that ST.K and Everpro have interests in the HG Unit Trust and
ST.K’s representative, Ms Tan, should have continued
as a director, it
seemed to me that those claims could be maintained at a final expedited hearing.
In the event they succeed and
there is evidence that they have suffered losses,
such as the asserted loss of the opportunity to make a profit from the sale of
their interests in the Project, any such losses could be expected to be fully
compensable by damages.
- The
evidence, as it stands, is that if the Company does not secure the Centennial
loan and it has to go to market, based on interest
rate differences, there is a
potential loss of $5.4 to $6.3 million over a three-year period. In addition,
and while more speculative,
it is to be expected that the grant of interlocutory
relief would delay the Project and the opportunity for the beneficiaries of
the
HG Unit Trust to obtain the sale proceeds and realise profits. As PNJ submitted,
delay would also carry with it some risk of
change in the market.
- In
the above circumstances, in my view, there a was a greater risk of injury and
prejudice to the Company, the HG Unit Trust and PNJ
if the relief was granted,
than to the cross-claimants if the relief was refused.
- In
coming to that view, the value of the undertaking as to damages was also a
relevant factor. I was not satisfied that the undertaking
proffered by ST.K had
real substance and provided adequate protection. The reference in the 12 April
2021 letter from ST.K’s
solicitor that ST.K intended to repay all the
debts of the Company, including PNJ’s loan, did not dispel the doubts
created
by ST.K’s failure to repay the $3,000,000 loan. The evidence that
ST.K had ongoing funding issues also indicated that it would
be unlikely to be
able to meet a significant damages award in the event the cross-claimants were
unsuccessful at trial.
- I
also accepted PNJ’s submission that the evidence adduced late in the day
about Hong Da’s financial position was insufficient
to conclude that there
was no risk that the undertaking as to damages it proffered would be inadequate.
The evidence identifies that
all but two of the eight townhouses owned by Hong
Da are subject to a registered mortgage. Three of them also have caveats on
their
title. Although the draft profit and loss statement and balance sheet for
2020 suggested that Hong Da has sufficient assets to support
the undertaking, I
was hesitant to accept them given the most recent final financial statement for
2018 showed it operating at a
loss of $311,000 and the financial records
produced by Hong Da and tendered by PNJ indicated that Hong Da has not filed a
tax return
since 2018.
Conclusion
- Viewing
the matter overall, I concluded that the cross-claimants’ application for
interlocutory relief should be refused. This
was primarily because I came to the
view that the balance of convenience and the issues raised regarding the
adequacy of the undertaking
as to damages did not favour the grant of
interlocutory relief.
- In
reaching my conclusion on the balance of convenience, I also took into account
that, based on the current evidence, the prima facie
case established by the
cross-claimants that formed the basis of its claim for interlocutory relief to
restrain the meeting of members
was not, in my view, strong and there were
aspects of their case which I considered to be weak.
- Finally,
and while not at all determinative, it was a relevant factor in the exercise of
my discretion not to grant interlocutory
relief that the cross-claimants only
moved the Court in response to the proceedings commenced by PNJ. It seemed to me
that it could
have taken urgent steps to restrain PNJ from exercising any rights
under cls 7.6 or 7.7 of the Commercial Loan Agreement after receiving
the letter
of demand or taken action to restrain PNJ from dealing with the units and shares
that ST.K contends were invalidly transferred
after receiving notice of those
matters in the 26 March letter.
Costs and orders
- On
the issue of costs, PNJ submitted, and the cross-claimants accepted, that it was
appropriate for costs to follow the event.
- The
parties also agreed that the matter should be heard on an expedited basis and
indicated they would seek to agree timetabling orders
which they would send to
chambers.
- For
these reasons, on 7 May 2021, I made the following orders:
(1) The
first and second cross-claimants’ claim for interlocutory relief as set
out in prayers 1 and 2 of the Amended Cross
Summons filed 4 May 2021 be
dismissed.
(2) The first and second cross-claimants pay the first
cross-defendant’s costs of and incidental to the cross-claimants’
claims for interlocutory relief as set out in prayers 1 and 2 of the Amended
Cross Summons filed 4 May 2021 on the ordinary basis.
(3) List the proceedings for directions before the Expedition List Judge at
9.30am on 14 May 2021 for consideration of whether the
proceedings ought to be
expedited and, if appropriate, orders for disclosure and/or the allocation of a
hearing date.
(4) Liberty to restore on 3 days’ notice.
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2021/530.html