You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2023 >>
[2023] NSWSC 25
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Context | No Context | Help
El Khouri & Anor v Gemaveld Pty Ltd & Ors [2023] NSWSC 25 (2 February 2023)
Last Updated: 5 April 2023
|
Supreme Court
New South Wales
|
Case Name:
|
El Khouri & Anor v Gemaveld Pty Ltd & Ors
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
28 November and 15 December 2022
|
Decision Date:
|
2 February 2023
|
Jurisdiction:
|
Equity
|
Before:
|
White J
|
Decision:
|
I answer the questions remitted as follows: (1) Q: For the
purposes of clause 4.3(2) of the Kogarah LEP, does the proposed dwelling house
approved by the Consent exceed the maximum
building height shown for the Site on
the relevant height of buildings map in that instrument? A: Yes, but this did
not appear from the plans submitted to the consent authority. (2)
Q: If the answer to question 1 is yes, did the First and Second Applicants
excavate the Site prior to 7 April 2022 in the portion
of the Site that is in
breach of the height of buildings development standard for the purposes of
question 1, and if so, to what
extent? A: No. (3) Q: For the
purposes of the notification of the DA, was a written notice forwarded to the
Third Applicant within the meaning of
the Georges River Council –
Community Engagement Strategy 2018 – 2028 prior to 7 April 2022? A:
Unnecessary to answer. (4) Q: If the answer to (3) is no, having
regard to the environmental impacts of the proposed development on the
applicants was any
denial of procedural fairness material? A: Does not
arise.
|
Catchwords:
|
ENVIRONMENT AND PLANNING – judicial review of decision to grant
development consent to respondent for erection of new dwelling-house
and
associated structures – development consent granted to respondent by a
Commissioner of the Land and Environment Court on
a consent basis without
intervention by applicants – where applicants contend that the Land and
Environment Court as consent
authority had no jurisdiction to grant consent
because height limit was exceeded and there was no application to vary the
standard
as required by the Local Environmental Plan – factual questions
arising on summons for judicial review remitted to Equity Division
for
determination - where the parties dispute the method of calculating the height
of a dwelling-house in accordance with cl 4.3
of the Kogarah Local Environmental
Plan 2012 – where respondent alleges that applicants excavated parts of
the site said to
contravene height limit – held that the proposed building
exceeds maximum building height, though that is not apparent from
the plans
submitted to the consent authority – held that applicants did not excavate
relevant parts of respondent’s land
– unnecessary to answer other
questions
|
Legislation Cited:
|
|
Cases Cited:
|
|
Category:
|
Procedural rulings
|
Parties:
|
Peter John El Khouri (First Applicant) Goumana Therese El Khouri (Second
Applicant) Effi Theodorakopoulos (Third Applicant) Gemaveld Pty Ltd (First
Respondent) Land and Environment Court (Second Respondent) Georges River
Council (Third Respondent)
|
Representation:
|
Counsel: J Lazarus SC with J Farrell (Applicants) C Leggat SC with S
Berveling and C Koikas (First Respondent) Submitting appearance (Second
Respondent) R M O’Gorman-Hughes (Third
Respondent)
Solicitors: Pikes & Verekers Lawyers
(Applicants) Salim Rutherford Lawyers (First Respondent) New South Wales
Crown Solicitor (Third Respondent)
|
File Number(s):
|
2022/00197368
|
JUDGMENT
- HIS
HONOUR: On 6 July 2022, the applicants, Mr Peter and Ms Goumana El Khouri
and Ms Effi Theodorakopoulos, filed a summons for judicial review
in the Court
of Appeal. The respondents to that summons are Gemaveld Pty Ltd
(“Gemaveld”), the Land and Environment Court,
and the Georges River
Council. The Land and Environment Court filed a submitting appearance.
- Gemaveld
is a company controlled by Mr Antonio Maiolo, who lives at 117 Stuart Street,
Blakehurst. Gemaveld is the registered proprietor
of that property. On 29 May
2020 a firm of architects engaged by it lodged a Development Application seeking
development approval
for demolition of the existing building and erection of a
new dwelling house, swimming pool and associated landscape works with the
Georges River Council.[1] The
application was refused on 15 October 2020 by the Georges River Local Planning
Panel.[2]
- On
15 October 2021, Gemaveld commenced Class 1 proceedings in the Land and
Environment Court, appealing against the refusal of the
application.
- On
29 March 2022, Gemaveld and the Council filed an agreement in the Land and
Environment Court as to the terms of a decision that
would be acceptable to
them.
- On
7 April 2022, a Commissioner of the Land and Environment Court granted
development approval on conditions in accordance with that
agreement pursuant to
s 34(3) of the Land and Environment Court Act 1979 (NSW) (Gemaveld Pty
Ltd v Georges River Council [2022] NSWLEC 1182).
- The
applicants were not parties to the proceedings in the Land and Environment
Court.
- By
the summons as subsequently amended on 2 August 2022 the applicants seek
judicial review of the decision of the Land and Environment
Court. They contend
that the order of the Land and Environment Court was void on grounds that may be
summarised as follows:
(a) the Court had no power
to grant consent because the height of the proposed development exceeded the
relevant height control
in the Kogarah Local Environmental Plan
(“LEP”) and there was no request to vary that standard as required
by cl 4.6
of that LEP;
(b) the decision to grant the development consent was
affected by jurisdictional error as the development application was not notified
in accordance with the community participation requirements of the
Environmental Planning and Assessment Act 1979 (NSW) in that the third
applicant, Ms Theodorakopoulos, who is an adjoining land owner to the site, was
not notified of the development
application and was thereby denied procedural
fairness.
- The
application for judicial review is assigned to the Court of Appeal. It raised
questions of fact that would not be appropriate
for determination before a bench
of three. The parties resisted the proceedings being referred to the Land and
Environment Court
to determine questions of fact and I was satisfied that that
course would not be appropriate (Young v King [2016] NSWCA 282 at [18];
Al Maha Pty Ltd v Huajun Investments Pty Ltd [2018] NSWSC 867 at
[11]- [16]; [2018] NSWCA 137 at [27]- [33]).
- The
matter came before me as Referrals Judge in my capacity as a judge of appeal. I
doubted that s 46 of the Supreme Court Act 1970 (NSW) conferred authority
on a single judge of appeal, acting in that capacity, to decide the separate
questions of fact that appeared
to arise. I was satisfied that it was
appropriate pursuant to s 51(4) of the Supreme Court Act to remit
separate questions of fact that arose in the proceedings to a Division for
determination by a judge of a Division.
- On
9 November 2022, I made the following order:
“Pursuant to section 51(4) of the Supreme Court Act 1970, the Court
orders that part of the proceedings be remitted to the Equity Division for
determination of the following questions arising
in the proceedings:
1) For the purposes of clause 4.3(2) of the KLEP, does the
proposed dwelling house approved by the Consent exceed the maximum building
height shown for the Site on the relevant height of buildings map in that
instrument?
2) If the answer to question 1 is yes, did the First and Second
Applicants excavate the Site prior to 7 April 2022 in the portion
of the Site
that is in breach of the height of buildings development standard for the
purposes of question 1, and if so, to what
extent?
3) For the purposes of the notification of the DA, was a
written notice forwarded to the Third Applicant within the meaning of
the
Georges River Council – Community Engagement Strategy 2018 – 2028
prior to 7 April 2022?
4) If the answer to (3) is no, having regard to the
environmental impacts of the proposed development on the applicants was any
denial of procedural fairness material?
In these questions,
• the Consent is a reference to development consent DA
No. 2020/0247 granted by the Land and Environment Court on 7 April
2022 for
demolition works, construction of a multi level dwelling house, swimming pool,
front fence, landscaping and site works on
Lot B DP 33563 known as 117 Stuart
Street Blakehurst.
• the DA is Development Application No. 2020/0247 lodged
with the third respondent for demolition works, construction of
a multi level
dwelling house, swimming pool, front fence, landscaping and site works on Lot B
DP 33563 known as 117 Stuart Street
Blakehurst.
• the Site is Lot B DP 33563 known as 117 Stuart Street,
Blakehurst.
• the KLEP is Kogarah Local Environmental Plan
2012.”
- I
listed the above questions for hearing on 28 November 2022 before me in my
capacity as a judge of the Equity Division.
- The
hearing had been estimated to take one day. The evidence was not concluded at
the end of the first day of hearing and the hearing
had to be adjourned. It was
completed on 15 December 2022.
- The
Council took a neutral position on questions 1, 2 and 4, but adduced evidence
that it had given notice to Ms Theodorakopoulos
for the purposes of question
3.
- On
the evening of 14 December 2022, the solicitors for Mr and Mrs El Khouri and Ms
Theodorakopoulos advised my Associate that, in
the light of recent evidence
filed by the Council, the applicants no longer pressed Grounds 2 and 3 of the
Amended Summons and, as
a consequence, it was no longer necessary for the Court
to determine questions 3 and 4. Accordingly, question 3 will be answered
“not necessary to answer” and question 4 does not arise.
- Gemaveld
submitted and contends in its response to the Amended Summons for Judicial
Review, that whether or not the height of the
proposed building exceeds the
height limit prescribed by the Kogarah LEP is not a fact on which the
jurisdiction of the Land and
Environment Court depended. That is a question of
law for determination by the Court of Appeal, if need be, but is not raised by
the questions for determination. Nonetheless Gemaveld raised issues which may be
relevant to that question which I have addressed
below.
Question
1
- Clause
4.3 of the Kogarah LEP provided:
“4.3 Height of buildings
1. The objectives of this clause are as follows –
(a) to establish the maximum height for buildings,
(b) to minimise the impact of overshadowing, visual impact and
loss of privacy through height controls,
(c) to provide appropriate scale and intensity of development
through height controls.
2. The height of a building on any land is not to exceed the
maximum height shown for the land on the Height of Buildings
Map.[3]
- The
maximum height shown on the relevant Height of the Buildings Map is
9 metres.
- Building
height or height of buildings is relevantly defined as
follows:
“(a) in relation to the height of a building in metres
– the vertical distance from the ground level (existing) to
the highest
point of the building”
- Ground
level (existing) is defined as follows:
“ground level (existing) means the existing level of a site
at any point”
- The
subject property at 117 Stuart Street is on a sloping block of land which runs
from the street frontage to the Georges River.
The plans approved by the Land
and Environment Court included drawing DA-6.02, which is reproduced as Annexure
A (761698, pdf) to
these reasons.
- Exhibit
1 is a blown-up copy of part of drawing DA-6.02 in the vicinity of the location
where the applicants contend the proposed
building will exceed the maximum
building height. Exhibit 1 is reproduced as /asset/186061ffb8b3c310365db1f1.pdf/asset/186061ffb8b3c310365db1f1.pdfAnnexure
B (1635438, pdf).
- In
its written submissions Gemaveld referred to decisions of the Land and
Environment Court which grapple with the problem where a
building to be
demolished occupies the whole of a site and there is no natural existing ground
level on the site because the whole
of the natural ground level has been
excavated to provide foundations or a basement for the existing building. No
such issue arises
in this case and I do not find those authorities to be of
assistance.
- In
their final submissions, counsel for Gemaveld submitted that the maximum
building height for the proposed dwelling house should
be measured vertically
from the plane of the highest part of the proposed building above sea level
(being the solar panels depicted
on Annexure A and Annexure B) to the existing
ground level. The applicants did not contend that there was a height breach in
that
location.[4] Gemaveld’s
submission had not been identified in its Response to the Amended Summons, nor
in its original written submissions.
It does not raise a disputed question of
fact, but it does need to be addressed in order for me to answer question 1.
- I
do not accept Gemaveld’s submission. The definition of “height of
building” provides that the height of a building
is measured not from the
highest point of the proposed building vertically downwards to existing ground
level, but from existing
ground level vertically upwards to the highest point of
the proposed building above existing ground level. Existing ground level
is the
existing level of a site at any point. Accordingly, height is to be measured
from any point of the existing ground level over
which the proposed building is
to be erected to the highest point (measured vertically) of the proposed
building above any point
at existing ground level.
- If
the only purpose of the prescription of maximum building heights were to
regulate the skyline then there might be much to be said
for Gemaveld’s
construction. But it is clear from cl 4.3(1)(c) that one of the objectives of
establishing maximum height for
buildings was to regulate the scale of
buildings, not just maximum height above sea levels.
- Gemaveld
denied that the height of the proposed building above any point of existing
ground level exceeded the maximum building height.
It acknowledged that, on the
particular sloping site involved, reasonable minds could differ on that
question.
- Gemaveld
also submitted that, for the purposes of the operation of the Kogarah LEP
definition of building height, the building height
is to be measured by
reference to the documents that are required to form part of the Development
Application for the proposed building.
It submitted that the Environmental
Planning and Assessment Regulation 2000 (NSW), which specifies what documents
are to accompany a development application, does not require a survey of every
point of existing
ground level below the proposed building. It submitted that,
on the plans provided with the development application to the consent
authority,
the proposed building did not contravene the maximum building height. For the
reasons below I accept this last submission.
- Clause
50 of the Environmental Planning and Assessment Regulation (as in force on 29
May 2020) provided that a Development Application must contain the information
and be accompanied by the documents
specified in Pt 1 of Sch 1 to the
Regulation. Clause 2 of Sch 1 provided that a Development Application must be
accompanied by documents including
a site plan that referred to existing levels
of the land in relation to buildings and roads (cl 2(2)(d)) and a sketch plan
that indicated,
amongst other things, elevations and sections showing heights of
any proposed buildings (other than temporary structures) and proposed
finished
levels of the land in relation to existing and proposed buildings and roads (cl
2(3)(c) and (d)).
- The
drawings DA-6.02 reproduced as Annexure A, and Exhibit 1 being a blown-up copy
of part of that drawing, show a green line which
at times is the same as the
solid black line. The line coloured in green appears to be (and I am satisfied
it is) the architect’s
depiction of ground level (existing) that is, the
current natural surface of the land. The building shown is the as-yet-unbuilt
building
for which development approval was given. An orange line is drawn 9
metres above the green line. On the face of the drawing the proposed
building
would comply with the 9 metre height limit.
- The
applicants contended to the contrary in reliance on evidence given by a town
planner, a Mr Steven Layman. Referring to plan DA-6.02,
Mr Layman deposed that
the plan indicated that, on the northern elevation, the level described as
ground level, which approximated
the roof of Level -1, was at RL (Reduced Level)
29.1. This was common ground. He deposed that the floor level of Level -3
immediately
below the north-western corner of Level -1 was shown at RL 18. The
difference between those points is 11.1 metres.
- However,
Mr Layman misread the plan. The 11.1 metre height difference is not the
difference between the proposed height of the building
and the existing ground
level, but the difference between the proposed height of the building and the
depth to which the land will
be excavated as part of the building works. That
is, with respect, self-evident from the plan. The surveyor called by the
applicants,
Mr Victor Mansell, accepted that the green dotted line was intended
to record the ground level (existing) at that particular point
of the
site.[5] The orange dotted line
reflects a 9 metre height plane above the green dotted
line.[6]
- Mr
Layman was unable to say what the dotted green line might
be.[7] He interpreted the solid black
line to be the ground level
(existing).[8] I do not accept that
that is so. The Environmental Planning and Assessment Regulation required the
applicant to show both the existing ground level and the proposed finished
levels of the land and that is what drawing
DA-6.02 purports to do.
- The
applicants submitted that, as a surveyor, Mr Mansell’s evidence in
cross-examination relating to the interpretation of the
architectural plans was
of little probative value. They correctly submitted that Gemaveld failed to call
the author of the architectural
plans or its own expert with appropriate
expertise to interpret them. But I do not accept that Mr Layman as a town
planner had any
greater expertise in this regard than did Mr Mansell. Mr Layman
said that the convention for depicting a ground line on an elevation
is to show
the ground line in a heavy continuous line such as the black
line.[9] But he was not able to say
what the dotted green line might be. Given that the Environmental Planning and
Assessment Regulation required a depiction of both the existing ground level and
the proposed finished level, the obvious implication is that the green
dotted
line represents the existing ground level and the continuous black line
represents the proposed finished level. That is how
Mr Mansell interpreted the
drawings.
- The
applicants submitted that Mr Layman had proffered an explanation for the
discrepancy between the dotted green line and the heavy
black line being that it
was attributable to the cross fall on the site. As I understood the submission,
it was that the green dotted
line represented a ground level at 117 Stuart
Street away from the boundary with 115 Stuart Street and closer to 121 Stuart
Street.
That is not what Mr Layman said. He said:
“7. It appears that the nominated ground levels in the North and South
Elevations do not take into account the cross fall of
the Site or the fall away
of the rock platform under the north-western most part of level 1of the
building. The architectural plans
omit the spot levels in this
location.”[10]
- The
cross fall to which Mr Layman referred was not a cross fall from 121 Stuart
Street to 115 Stuart Street, but the cross fall from
Stuart Street to Georges
River.
- The
applicants also submitted that a plan entitled “115 Stuart Street Site
Analysis”, being DA-3.01, depicted the fall
of the existing ground levels
with a heavy black line. That is true, but it is not an explanation for the
different lines on DA-6.02.
- The
applicants also submitted that a cut and fill plan (DA-9.07) showed that no cut
and fill was proposed in the area subject to the
height exceedance. No question
was asked of any witness about the cut and fill plan. It is not self-evident, as
the applicants submitted,
that it can be discerned from the cut and fill plan
that if the black line on drawing DA-6.02 was to represent excavated levels
post-development,
that this was inconsistent with the cut and fill plan.
- For
these reasons I do not accept Mr Layman’s evidence.
- Mr
Mansell accepted that the drawings provided to the Council as part of the
Development Application showed that the building complied
with the 9 metre
height plane, including in respect of an area about which he gave evidence
referred to below.[11]
- Mr
Mansell attended 115 Stuart Street on 5 May 2022 to determine the ground levels
of 117 Stuart Street at the north western corner
of Level 1 of the proposed
building. He conducted a survey of part of 117 Stuart Street from within the
boundary of 115 Stuart Street
and deposed as follows:
“I found:
(a) Various ground levels which are shown in red on the diagram
attached and marked ‘E’ (also referred to as Sheet
2 of our survey
report). The levels in black are those from the merged two surveys of 2004 and
2016 in annexure ‘D’.
(b) One of the levels I found on site was a natural surface at
ground level of RL 17.50 for the point of the north western corner
of Level 1 of
the proposed building at the Site. This is marked with a green asterisk (*) on
the diagram attached as Annexure ‘E’.
(c) The asterisk point, and points directly above and below at
other proposed levels, are shown marked up in handwriting by me
on the GFA plan
annexed hereto and marked ‘F’.
(d) At the asterisk point, for a maximum building height of 9m
above ground level, the proposed building height should be RL 26.5
or lower. I
have marked up in handwriting on architectural plan DA 6.02 Rev. F Mar 2022 by
MKD Architects entitled North and South
Elevation (North and South Elevation
plan) to show that for a 9m building height, the proposed building height of
RF 29.10 at the asterisk point would exceed the 9m building
height plane by 2.6
m. The other parts of the north elevation of the proposed building that would
breach the 9m height control are
shown by the handwritten red dashed line, and
the ground level is also shown below by another handwritten red dashed line. The
North
and South elevation plan so marked is annexed hereto and marked
‘G’.
(e) In addition to the asterisk point, an outline of the
overall area on floor plan where the building height of RL29.10 of the
proposed
residence would exceed the 9 m heigh plane is shown in blue hatching on annexure
E. The ground level at these points is
less than RL 20.10.
...”
- Annexure
E to Mr Mansell’s affidavit is reproduced in these reasons as /asset/18606206b24f0669f678e18f.pdf/asset/18606206b24f0669f678e18f.pdfAnnexure
C (1165858, pdf),
Annexure F as /asset/1860620c677ab995e74daabc.pdf/asset/1860620c677ab995e74daabc.pdfAnnexure
D (935502, pdf),
and Annexure G as Annexure
E (839568, pdf).
- Mr
Mansell did not say that his survey results meant that, in his opinion, the
depiction of the green line on drawing DA-6.02 was
wrong. He gave the following
evidence:
“Q. Now, my question is this. To the extent that the depiction of the
green line departs from your spot levels in your survey,
do you say that that
green line is correct or incorrect?
A. It may be correct for the area or the line that it is shown as. I don't know,
other than I would assume it was the architect who
prepared it. How he prepared
it with surveying interpolation, I do not know. But then you should always
consider every point to determine
the nine metre height
plane.”[12]
- Mr
Mansell was cross-examined on an enlargement of an extract of drawing
DA‑13.01, which was a survey that formed part of the
Development
Application. The extract became Exhibit 6. It is reproduced as Annexure
F (1663754, pdf). In
the course of Mr Mansell’s cross-examination, survey points that were
referred to in his cross-examination were highlighted
in green highlighter to
make the transcript intelligible. (One point referred to in cross-examination
(NS 20.54) should have been
highlighted in green but was highlighted by me in
yellow as being a further point referred to in cross-examination.) More
importantly,
Mr Mansell identified by highlighting in yellow the approximately
triangular section that he said, to the best of his ability, without
being able
to take measurements, was the area which represented the blue hatched area of
his drawing on Annexure E to his affidavit.
- The
survey shows a contour line moving in a southerly direction, with RLs of between
20.20 and 20.87 metres. As the roof of the proposed
building above the hatched
area identified by Mr Mansell would have an RL of 29.1 metres, if the ground
level (existing) below that
roof line were above 20.1 metres, the building would
not contravene the height limits specified by cl 4.3(2) of the Kogarah LEP.
Mr
Mansell was asked about the contour line and agreed that it would be recognised
surveying practice to take into account particular
points, for example points
20.50 and 20.87, to describe a “ground level (existing)” for the
purpose of setting a 9 metre
height plane for the
site.[13] He agreed that it would be
in accordance with recognised surveying practice to interpolate between a point
shown as NS 20.50 and
20.73 on the survey (running from the top right diagonally
to bottom left of the drawing) only in order to depict the ground level
(existing) across the contour of the site, but only if one interpolated the
other points in between.[14] Right
to left is also north east to south west. However, Mr Mansell did not accept
that, consistently with recognised surveying practice,
a surveyor would take
levels as far away from the triangular marked area corresponding with the area
he hatched blue to establish
a height plane, being the areas shown as RS 20.29
and 20.30.[15] He said that to
interpolate a level, consistently with recognised surveying practice, it would
be necessary to use other levels on
Exhibit 6 which did not include the spot at
RS 20.29 or RS 20.30 which he considered to be too far away from the area in
question.[16]
- It
was put to Mr Mansell that if there were any difference between the levels
depicted on Exhibit 6 and the levels he derived on his
survey taken from 115
Stuart Street, the levels shown on Exhibit 6 were more likely to be accurate
than the levels he derived. He
accepted that that would be so but only at the
point that the level was shown.[17]
- Mr
Mansell gave evidence as to how the survey of points on 117 Stuart Street was
taken from the adjoining
property.[18] As one might expect,
that did not depend upon his taking a digital measurement using theodolites to a
spot on number 115 and then
making a visual estimate or guess as to the
difference in height between where he was located on number 115 and the spot
whose height
was to be determined on lot 117. He said:
“A. We have a laser theodolite so it sends out a signal, it will reflect
off a particular point and it will then give us a
reading in distance and in
height.
Q. And what point are you aiming at?
A. It may be a rock, it may be a leaf; it could be anything that we can choose
to pick.
Q. And in this case, where you determine or assess these figures which you have
included in your report as being the levels on 117?
A. Correct.
Q. What did you do?
A. On exhibit six, there are shown, where I have highlighted the relevant area
in yellow, there are a few points with crosses which
say 20.44, top of retaining
wall.
Q. Yes?
A. I have in my survey done a similar thing, taken a number of spots where the
figures were shown in red on exhibit F, I think it
was, in the original
affidavit.
LEGGAT: Annexure E, Mr Mansell.
WITNESS: E.
HIS HONOUR:
Q. Annexure E, yes.
A. And we compare those when we are back in the office, to see if they are in
close agreement. If it's an irregular wall, some of
the points were plotting
very close to each other, we assume then that those points are consistent with
each other from the different
planes. And then we will take other points below
that level, because along that top of the wall and to the east, we did not
really
see any reason to say that the nine metre height plane could be exceeded
with the natural levels that are shown. It was only in the
area to the west.
Q. Well, correct me if I am wrong, as I understand it then, where you are
standing on the location on property 115, you can determine
the height above sea
level of that property in the way you have described?
A. Correct.
Q. And then you have another device, or maybe it's the same one doing a
different function, where you aim it at a point on property
117, and it will
then give you what figure, what will be the, what will it show you from that?
A. It will give us a level of the point that is on 117.
Q. As a difference between where you are on 115 or adjusted to the
A. Well, we can set our level on 115. We know a level that we have started from
on 115. And the measurement will automatically tell
us what the level is on
117.”[19]
- He
said that the level of accuracy would be accurate within
20mm.[20]
- Mr
Mansell agreed in cross-examination that he was not saying that the bottom lines
shown on Exhibit 1 were wrong or had been depicted
wrongly.[21] He said he had not
verified them by survey and that he could only verify particular levels in an
area that he surveyed himself. He
said that the lines shown were usually taken
along a section line. Every line is taken from an individual point. Once one
moves from
a section line you can get a different
answer.[22]
- Gemaveld
did not adduce any evidence from a surveyor, nor the architect who prepared the
drawings showing, or purporting to show,
the height planes.
- I
accept Mr Mansell’s evidence. His credit was not in issue. His evidence
was uncontradicted and given carefully. He made appropriate
but careful
concessions. His concessions should not be extrapolated.
- I
accept that in the area Mr Mansell surveyed there was a point on the natural
surface of the ground that was 11.6 metres below the
proposed building height
and that the area shown in the blue hatching in the plan that is Annexure E to
his affidavit shows the area
where the proposed residence would exceed the 9
metre height plane above the existing ground level. I conclude that if the green
dotted line on Exhibit 1 that formed part of the approved drawings was intended
to depict the existing ground level at all points
rather than along a particular
section line, the drawing was wrong.
- Gemaveld
submitted that the top section of Drawing DA-7.01 showed that at the location of
the southern line (on Drawing DA-6.02) the
9 metre height limit was not
exceeded. Mr Mansell agreed that a southern line on drawing DA‑6.02 went
through the blue hatched
area depicted by him where the height limit was
exceeded. Gemaveld submitted that DA-7.01 showed that the 9 metre height
limitation
was not exceeded. I accept that that is so. I also accept on the
basis of Mr Mansell’s evidence that in fact the height limit
was exceeded.
- Therefore
I conclude that measuring from each point of existing ground level to the top of
the proposed building the maximum height
level would be exceeded in the area
depicted by Mr Mansell. I also conclude that that was not apparent from the
plans submitted which
in this respect were in error.
- Accordingly,
I answer question 1, yes, but this did not appear from the plan submitted to the
consent authority.
Question 2
- In
its response to the Summons, Gemaveld contended that:
“The First and Second Applicants caused the soil level on the Site to be
lowered (Excavation). The excavation was carried out without the consent
or knowledge of the First Respondent. The excavated portion of the Site is the
portion of the Site purportedly in breach of the height of buildings development
standard. Accordingly, the excavation by the First
and Second Applicants was an
immediate and necessary relation to the alleged breach of the height of
buildings development standard.
In the premises, it is unconscionable and in bad
faith for the Applicants to now seek the relief in prayers 1, 2 and 3 of the
Summons.
The relief ought to be withheld in the exercise of the Court’s
discretion having regard to the equitable maxim of clean hands.”
- The
first and second applicants, Mr and Mrs El Khouri, dispute the facts alleged in
the above paragraph. Question 2 is directed to
that dispute.
- Mr
and Mrs El Khouri own the property at 115 Stuart Street, which lies directly to
the north of 117 Stuart Street. Between November
2017 and early 2020, they
carried out building works on 115 Stuart Street which involved the construction
of two dwellings, one on
the upper part of the lot and one on the lower part. Mr
El Khouri was the director of the building company. He deposed that he was
present on a full-time basis during construction works and saw the earth and
civil works including any activities when access was
obtained over 117 Stuart
Street. There is no dividing fence between the properties over the lower part of
the two blocks.
- Mr
Maiolo deposed that in around early 2017 he advised Mr El Khouri that Mr El
Khouri could use the bottom part of his property to
store building materials and
for his tradesmen to use it to work around the construction site on 115 Stuart
Street. Mr El Khouri
said that this conversation occurred in August 2017.
Nothing turns on this difference. Mr El Khouri deposed that demolition work
commenced on 115 Stuart Street on 27 November 2017. The house to be demolished
was situated on the upper half of the property. Mr
El Khouri deposed that on or
about 12 December 2017 he asked Mr Maiolo for access for excavator machines to
pass through 117 Stuart
Street around the bottom of a rock wall and to access
another part of 117 Stuart Street for the stockpiling of dirt if and when
necessary
during works for the lower dwelling. These requests were agreed to.
Machine access over the site at 117 Stuart Street commenced on
5 January
2018.[23]
- Mr
Maiolo and his family left 117 Stuart Street for a family holiday and returned
on 21 January 2018. Machine access over 117 Stuart
Street commenced on 5 January
and ceased on about 2 February 2018.
- Mr
Maiolo deposed that on 24 January 2018 he saw an excavator in his yard and
watched while it worked in an area that in these proceedings
has been designated
as the “Hatched Area”, that is, the area where the applicants
contend the building height limit is
exceeded. He took a photo of the excavator
on the land.[24] He also took photos
on 22 January, 27 February and 23 March 2018 that included photos of what he
deposed is now known as the Hatched
Area. The photographs were taken from an
elevated position and do not capture what lies immediately below a rock wall and
a Swiss
cheese plant. The large yellow excavator shown in the photograph
Annexure C to Mr Maiolo’s affidavit appears to be parked near
a stand of
trees at the bottom of the site not far from the Georges River and not in the
vicinity of what is known as the Hatched
Area.
- Mr
Maiolo deposed:
“24. On or shortly after 7 March 2020, I inspected the area I now know as
the Hatched Area. I noticed that the outcroft at
the Hatched Area had been
excavated.
25. Before Peter’s excavation, the area I now know as the Hatched Area was
level with the rock outcroft. I estimate that Peter
excavated at a depth of 2.5m
of earth in a 4m x 1.5m triangle shape at what I now know as the Hatched
Area.”
- The
“outcroft” referred to by Mr Maiolo is the rock outcrop that appears
in the photo which is Annexure D to his affidavit
and appears in photographs
annexed to Mr El Khouri’s affidavit.
- The
photos annexed to Mr Maiolo’s affidavit do not corroborate his evidence
that the yellow excavator carried out excavation
work on 24 January 2018 in the
vicinity of the Hatched Area.
- Mr
El Khouri denied that any excavation work was carried out in the Hatched Area.
He said that at all times throughout January 2018
he was present on site when
the excavators were operating.[25] I
accept that evidence.
- In
his cross-examination Mr Maiolo said that when he referred to having noticed
that the outcroft at the Hatched Area had been excavated,
he was referring to
the outcrop having been supported by a batter, and actual fall of earth, that
covered the rock wall and which
had been
excavated.[26] He said that the
batter was formed by 15m3 of soil which he said was shown in photographs taken
by Mr El Khouri on 14 December
2017[27] which was shown to have
been removed in a photograph taken on 5 January
2018.[28]
- This
was before the excavation that Mr Maiolo deposed to having seen on 24 January
2018. His proposition that there had been such
excavation of a batter between 14
December 2017 and 4 January 2018 was not put to Mr El Khouri in Mr El
Khouri’s cross examination.
- Most
of the “batter area” referred to by Mr Maiolo in his
cross-examination fell below the Hatched
Area[29] (Exhibit B). Contrary to Mr
Maiolo’s evidence, I do not accept that the photographs annexed to Mr El
Khouri’s affidavit
show an excavation after 14 December in the Hatched
Area. To the contrary, although the photographs annexed to the affidavits of
Mr
El Khouri and Mr Maiolo are taken from different angles and show different
perspectives, the photograph shows no excavation over
the Hatched Area between
that date and 24 October 2018.[30]
- Mr
Maiolo’s evidence in cross-examination to the
contrary[31] was unconvincing.
- Mr
Maiolo gave evidence in re-examination that ought to have been led in chief and
which was allowed on the basis that I would allow
cross-examination on the
further evidence. He produced a further photograph taken some two or three
months before the hearing. He
said that the further photograph (Exhibit 8)
showed that the “whole area” had been stripped and what had been
covered
had been removed so that the height was completely different from the
height shown in Mr El Khouri’s
photograph[32] of 14 December
2017.[33] A comparison with the
photographs at CB 111 and 112 and Exhibit 8 does not enable me to draw any such
conclusion.
- The
argument advanced by Mr Maiolo in his cross-examination and re-examination had
not been advanced in his affidavit. Nor was it
put to Mr El Khouri in his
cross-examination, as it should have been if Mr Maiolo had given instructions to
his legal representatives
to the effect of his evidence in cross-examination and
re-examination. However, it was not suggested to Mr Maiolo in cross-examination
that his evidence was recent invention and I do not discount it on that basis.
It suffices to say that I accept the evidence of Mr
El Khouri that no excavation
in the vicinity of the Hatched Area occurred.
- For
these reasons I answer question 2, no.
Conclusion
- For
these reasons I answer the questions remitted as follows:
- (1) Q: For the
purposes of cl 4.3(2) of the Kogarah LEP, does the proposed dwelling house
approved by the Consent exceed the maximum
building height shown for the Site on
the relevant height of buildings map in that
instrument?
A: Yes, but this did not appear from the plans
submitted to the consent authority.
- (2) Q: If the
answer to question 1 is yes, did the First and Second Applicants excavate the
Site prior to 7 April 2022 in the portion
of the Site that is in breach of the
height of buildings development standard for the purposes of question 1, and if
so, to what
extent?
A: No.
- (3) Q: For the
purposes of the notification of the DA, was a written notice forwarded to the
Third Applicant within the meaning of
the Georges River Council –
Community Engagement Strategy 2018 – 2028 prior to 7 April
2022?
A: Unnecessary to answer.
- (4) Q: If the
answer to (3) is no, having regard to the environmental impacts of the proposed
development on the applicants was any
denial of procedural fairness
material?
A: Does not arise.
- The
costs of the determination of the above questions fall for determination by the
Court of Appeal.
Amendments
06 February 2023 - Addition of counsel name for First Respondent
05 April 2023 - Typo corrected on coversheet and in para [9]: s 54(1) amended
to s 51(4) of the Supreme Court Act 1970 (NSW).
[1] White Folder (“WF”)
348
[2] WF
438
[3] WF
261
[4] Transcript
(“T”) 4.42
[5] T
11.42
[6] T
12.1
[7] T
78.30
[8] T
78.50
[9] T
78.15
[10] Layman affidavit 5
July 2022, para 7, WF 577
[11] T
14.40
[12] T
68.11-17
[13] T
32.45
[14] T
33.14-23
[15] T
56.28
[16] T
57.16-31
[17] T
35.32-36
[18] T
65-66
[19] T
65-66
[20] T
67.13
[21] T
45.3-10
[22] T
44.44-46
[23] Court Book
(“CB”) 103
[24]
Annexure C to Maiolo affidavit of 28 October 2022 at CB
148
[25] T
94-95
[26] T
116
[27] CB
111
[28] CB
113
[29] T
118
[30] Photo at Annexure E to
Maiolo affidavit.
[31] T
123-124
[32] CB
111
[33] T 129
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2023/25.html