![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
Supreme Court of New South Wales |
Last Updated: 6 April 2023
|
Supreme Court New South Wales
|
Case Name:
|
Ceerose Pty Ltd v A-Civil Aust Pty Ltd (No 2)
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
1-2 December 2022
|
Date of Orders:
|
6 April 2023
|
Decision Date:
|
6 April 2023
|
Jurisdiction:
|
Equity - Technology and Construction List
|
Before:
|
Richmond J
|
Decision:
|
Adjudication determination set aside, in part, in relation to the claim for
retention monies.
|
Catchwords:
|
BUILDING AND CONSTRUCTION — adjudication — whether adjudication
determination was affected by jurisdictional error —
whether the
adjudicator failed to afford the parties procedural fairness —
jurisdictional error in respect of part of the adjudication
determination in
relation to retention monies — where the Court has the power to set aside
the whole or part of the adjudication
determination pursuant to s 32A of the
Act
|
Legislation Cited:
|
|
Cases Cited:
|
Abigroup Contractors Pty Ltd v ABB Service Pty Ltd [2004] NSWCA 181; (2005)
21 BCL 12
Acciona Infrastructure Australia Pty Ltd v Chess Engineering Pty Ltd [2020] NSWSC 1423 Acciona Infrastructure Australia Pty Ltd v Chess Engineering Pty Ltd (No 2) [2020] NSWSC 1788 Acciona Infrastructure Australia Pty Ltd v Holcim (Australia) Pty Ltd [2020] NSWSC 1330 Brolton Group Pty Ltd v Hanson Construction Materials Pty Ltd [2020] NSWCA 63 Ceerose Pty Ltd v A-Civil Aust Pty Ltd [2022] NSWSC 1487 Equa Building Services Pty Ltd v A&H Floors 2 Doors Australia Pty Ltd [2022] NSWSC 152 Futurepower Developments Pty Ltd v TJ & RF Fordham Pty Ltd [2017] NSWSC 232 Galileo Miranda Nominees Pty Ltd v Duffy Kennedy Pty Ltd [2019] NSWSC 1157 Holmwood Holdings Pty Ltd v Halkat Electrical Contractors Pty Ltd [2005] NSWSC 1129; (2006) 22 BCL 285 Hossain v Minister for Immigration and Border Protection (2018) 264 CLR 123; [2018] HCA 34 Jadwan Pty Ltd v Secretary, Department of Health and Aged Care (2003) 145 FCR 1; [2003] FCAFC 288 JKC Australia LNG Pty Ltd v Inpex Operations Australia Pty Ltd (2018) 41 NTLR 149; [2018] NTCA 6 McNab Building Services Pty Ltd v Demex Pty Ltd (No 2) [2022] NSWSC 1496 Minister for Immigration & Multicultural Affairs v Bhardwaj (2002) 209 CLR 597; [2002] HCA 11 Minister for Immigration and Border Protection v SZMTA (2019) 264 CLR 421; [2019] HCA 3 MZAPC v Minister for Immigration and Border Protection [2021] HCA 17; 95 ALJR 441 Nathanson v Minister for Home Affairs [2022] HCA 26; 96 ALJR 737 New South Wales Netball Association Ltd v Probuild Construction (Aust) Pty Ltd [2015] NSWSC 1339 Parrwood Pty Ltd v Trinity Constructions (Aust) Pty Ltd [2020] NSWCA 172 Perkins (WA) Pty Ltd v Weston (No 2) [2022] WASCA 111 Pinnacle Construction Group Pty Ltd v Dimension Joinery & Interiors Pty Ltd [2018] NSWSC 894 Plaintiff S157/2002 v Commonwealth of Australia (2003) 211 CLR 476; [2003] HCA 2 Probuild Constructions (Aust) Pty Ltd v DDI Group Pty Ltd (2017) 95 NSWLR 82; [2017] NSWCA 151 Probuild Constructions (Aust) Pty Ltd v Shade Systems Pty Ltd (2018) 264 CLR 1; [2018] HCA 4 Quickway Constructions Pty Ltd v Hick [2017] NSWSC 830 Rhomberg Rail Australia Pty Ltd v Concrete Evidence Pty Ltd [2019] NSWSC 755 Seymour Whyte Constructions Pty Ltd v Ostwald Bros Pty Ltd (2019) 99 NSWLR 317; [2019] NSWCA 11 Trysams Pty Ltd v Club Constructions (NSW) Pty Ltd [2008] NSWSC 399 Watpac Constructions (NSW) Pty Ltd v Austin Corp Pty Ltd [2010] NSWSC 168 |
Category:
|
Principal judgment
|
Parties:
|
Ceerose Pty Ltd (Plaintiff)
A-Civil Aust Pty Ltd (First Defendant) Paul Roberts (Second Defendant) ABC Dispute Resolution Service (Third Defendant) |
Representation:
|
Counsel:
S Robertson SC with D Hume (Plaintiff) L Gor (Defendant) Solicitors: Salim Rutherford Lawyers (Plaintiff) M&A Lawyers (First Defendant) |
File Number(s):
|
2022/307139
|
JUDGMENT
Background
The Contract
5. Security5.1 Provision
Security shall be provided in accordance with Item 19 or 20. All delivered security, other than cash or retention monies, shall be transferred in escrow.
Except for any security provided in respect of unfixed plant or material, the total value of all security held by the Main Contractor shall not exceed:
(a) Prior to practical completion of the head contract – 5% of the subcontract sum; and
(b) After practical completion of the head contract – 2.5% of the subcontract sum.
5.2 RecourseA party may have recourse to security:
(a) Where the amount due to that party under the Subcontract or otherwise remains unpaid after the time for payment; and
(b) In respect of any Claim to payment (liquidated or otherwise) that party may have against the other under the Subcontract or otherwise,
On the giving of written notice to the other party.5.3 Change of security
At any time, a party providing retention monies or cash security may substitute, with the written consent of the other in its absolute discretion, form of security. To the extent that another form of security is provided, the other party shall not deduct, and shall promptly release and return, retention moneys and cash security.
5.4 Reduction and release
Upon the issue of the certificate of practical completion under the head contract, a party’s entitlement to security (other than in Item 19(e)) shall be reduced by the percentage or amount in Item 19(f) or 20(d) as applicable, and the reduction shall be released and returned within 28 days to the other party.
A party’s entitlement otherwise to security shall cease 28 days after final certificate is issued under the head contract.
Upon a party’s entitlement to security ceasing, that party shall release and return forthwith the security to the other party.
5.5 Trusts and interest
Except where held by a government department or agency or a municipal, public or statutory authority, any portion of security which is cash or retention monies, shall be held in trust for the parties in accordance with the terms of this agreement.
39.1 Preservation of other rightsIf a party breaches (including repudiates) the Subcontract, nothing in this clause shall prejudice the right of the other party to recover damages or exercise any other right or remedy.
39.2 Subcontractor’s default
If the Subcontractor commits a substantial breach of the Subcontract, the Main Contractor may give the Subcontractor a written notice to show cause.
Substantial breaches include, but are not limited to:
(a) Failing to:
i. Perform properly the Subcontractor’s design obligations;
ii. Provide security;
iii. Provide evidence of insurance;
iv. Comply with clause 34.1 or 31;
v. Comply with clause 29.3;
vi. Comply with a direction of the Subcontract Superintendent; or
vii. Use the materials or standards of work required by the Subcontract;
viii. Comply with any clause of this contract.
(b) Wrongful suspension of work;
(c) Substantial departure from a construction program without reasonable cause;
(d) Failing to proceed with due expedition and without delay; and
(e) In respect of clause 38, knowingly providing documentary evidence containing an untrue statement.
39.3 Main Contractor’s notice to show causeA notice under subclause 39.12 shall state:
(a) That it is a notice under clause 39 of these Subcontract Conditions;
(b) The alleged substantial breach;
(c) That the Subcontractor is required to show cause in writing why the Main Contractor should not exercise a right referred to in subclause 39.4;
(d) The date and time by which the Subcontractor must show cause (which shall not be less than 5 business days after the notice is received by the Subcontractor); and
(e) The place at which cause must be shown.
39.4 Main Contractor’s rightsIf the Subcontractor fails to show reasonable cause by the stated date and time, the Main Contractor may by written notice to the Subcontractor:
(a) Take out of the Subcontractor’s hands the whole or part of the work remaining to be completed and suspend payment until it becomes due and payable pursuant to clause 39.6; or
(b) Terminate the Subcontract.
...39.10 Termination
If the Subcontract is terminated pursuant to subclause 39.4(b) ... the parties’ remedies, rights and liabilities shall be the same as they would have been under the law governing the Subcontract had the defaulting party repudiated the Subcontract and the other party elected to treat the Subcontract as at an end and recover damages.
...
The dispute
17. A Civil has not complied with its obligations under the Subcontract including without limitation:
(a) A Civil has not complied with directions made by Ceerose in accordance with the Subcontract.
(b) A Civil has abandoned the works and refused to complete the works despite repeated requests by Ceerose.
(c) A Civil has not completed the works as required by the Subcontract.
(d) A Civil has not satisfied the definition of ‘Practical Completion’ under the Subcontract and frankly could not do so as it was terminated due to its repudiation of the Subcontract.
(e) As a result of A Civil’s refusal to perform works, Ceerose has had to engage others to perform the works required to be performed by A Civil under the Subcontract.
18. Amongst other non-compliances, at the time that A Civil abandoned the site, the works were not complete. Ceerose has incurred costs, expenses and loss and damage significantly in excess of the retention sum including in engaging others to complete its works under the Subcontract.19. In these circumstances, where A Civil have not complied with all of its obligations under the Subcontract and has not satisfied the contractual requirement for release of retention which include, but are not limited, to matters set out above, A Civil has no entitlement to make a claim for retention.
23. Ceerose is entitled to an amount in excess of $3,221,374.40 from A Civil resulting from deductions and loss and damage suffered by Ceerose due to A Civil’s acts, default and omissions.24. Ceerose applies the monies held on retention against the amount of $3,221.374.40 owed by A Civil to Ceerose. On this basis, Ceerose assesses the Purported Payment Claim as $NIL. Notwithstanding the recourse to retention monies, monies remain owed by A Civil to Ceerose.
B. PRECONDITION TO ENTITLEMENT TO CLAIM RETENTION(54) In response to paragraph 17 of the PS, A-Civil submits as follows:
(a) A-Civil has complied with the directions and instructions made by Ceerose in accordance with the Subcontract dated 2 March 2022, with respect to the excavation services undertaken on site.
(b) Further, A-Civil has replied to Ceerose’s Show Cause Notice issued on 7 June 2022 [TAB D1, pp. 734 to 738] (Refer: TAB – A-Civil Reply on GCOR-435). A-Civil’s response outlined that the cause of the delays were a result of Ceerose’s poor management of the site, which hindered the commencement of A-Civil’s bulk excavation works.
(55) In response to paragraph 18 of the PS, A-Civil submits as follows:
(a) On 9 June 2022, A-Civil had a meeting with Ceerose’s Construction Manager, Roy Massoud, whereby it was discussed and made clear that A-Civil would acquire full control of the works, as outlined in the executed subcontract.
(b) On 10 June 2022, the Construction Manager Roy Massoud and Project Manager Jonathan Bayeh of Ceerose, had a meeting at A-Civil’s office. As an outcome of the meeting, A-Civil and Ceerose entered into a Commercial Agreement which was emailed by Roy Massoud to A-Civil representatives on 11 June 2022. This agreement between Ceerose and A-Civil provided that A-Civil will have, full control of the site and are to ensure that progress onsite is accelerated [TAB D2, pp. 739 to 741] (Refer: Email ALX2 – A-Civil & Ceerose Commercial Agreement).
(c) As a result of the site meeting, A-Civil organized an additional 6 excavator floats to the site on 14 June 2022 and 15 June 2022 [TAB D3, pp. 742 to 747] (Refer: Email – RE ALX2 – Float Approval – Tue 14 06 22).
(56) In response to paragraph 19 of the PS, A-Civil submits as follows:
(a) A-Civil did not abandon the site and complied with it’s obligations under the Subcontract, as indicated in the progressive site photos of June 2022 [TAB D4, pp.748 to 771] (Refer: TAB- Site Photos June’22).
(b) A Notice of Delay was submitted by A-Civil on 1 July 2022, requesting an Extension Of Time (“EOT”) for the delay caused by inclement weather in reaching practical completion. [TAB D5, pp.772 to 778] (Refer: Rain Delay 22 – Alexandria).
(c) The photograph located in paragraph 41 of the PS indicates that A-Civil had five excavator’s and a screener working on the site on 29 June 2022 [TAB D6, pp.779 to 780) (Refer: TAB – CEEROSE Item 41 Photo).
(d) The Project Manager of Ceerose sent Mr Nasser Matta of A-Civil an email on 1 July 2020 [TAB D7, pp. 781 to 788] (Refer: TAB – ALX2 – A-Civil – Termination Letter) attaching the contract termination letter, without providing any reasons as to why the project was terminated.
(57) Ceerose deprived A-Civil of the opportunity to carry out its obligations under the Contract by wrongfully terminating the Contract. A-Civil request the Adjudicator to determine that A-Civil is entitled to payment of retention moneys.
C. RECOURSE TO RETENTION(58) In response to paragraph 23 of the PS, A-Civil submits that the termination of the Contract by Ceerose was intentional and wrong for the reasons set out in these submissions.
19. The issues in dispute are summarised as follows:
(a) Contract works – the Claimant purports to maintain 7 items of contract works which are in the aggregate of $565,522.95 (plus GST).
(b) Variations – the Claimant maintains 2 purported variations which are in the aggregate of $28,840 (plus GST). Without limitation to all of the reasons for withholding payment, the 2 purported variations may be summarised as items which fall squarely within the Claimant’s scope of works under the Subcontract and/or are a claim for damages and not matters that can be determined under the Act.
(c) Retention – the Claimant claims its retention in the sum of $115,577.79. The Claimant has no entitlement to claim its retention under the Subcontract. If the Subcontract was terminated unlawfully (which is denied) as asserted by the Claimant, the claim for retention is a claim for damages and a claim that cannot be made under the Act. There is no mechanism under the Subcontract which permits the release of retention for purported unlawful termination.
(d) Deductions – the Respondent applies deductions in the amount of $2,990,656.90 (excl GST).
Retention160. The Claimant purports to be entitled to retention money notwithstanding no entitlement under the Subcontract.
161. The Claimant is not owed any amount by the Respondent and in fact the Claimant is indebted to the Respondent. There is no basis to claim retention monies under the contract or under the Act.
162. Further, as the Respondent is entitled under the Subcontract, the Respondent has already had recourse to the retention money and further and alternatively any claim for retention moneys is a claim for damages and cannot be made under the Act.
163. The Respondent repeats and relies on paragraphs 14 to 24, and 121 to 125 of its Payment Schedule.
164. On any reasonable assessment of the value of works carried out to the date the Subcontract was terminated, the Claimant has been significantly overpaid and has no entitlement to any retention money.
165. As stated in the Payment Schedule, the Claimant has clearly decided to ‘roll the dice’ and see if it can get back its retention money, in circumstances where it has no entitlement. The Adjudicator should not be encouraging this behaviour.
166. At paragraphs [54] and [58] of the Claimant’s Adjudication Application, the Claimant asserts that the Respondent wrongfully terminated the Subcontract and therefore depriving the Claimant to carry out its obligations under the Subcontract. If the Subcontract was wrongfully terminated (which is denied), that is a claim for damages and not a claim that can be brought under the Act. It is well settled that a claim for general damages for breach of contract is impermissible under the Act.
...
175. There is no right or entitlement under the Subcontract for the Claimant to claim its retention. In accordance with section 10 of the Act, the Adjudicator must have regard to the terms of the Subcontract and the terms of the Subcontract do not give rise to an entitlement for the Claimant to make this claim.
1. This application arises from payment claim number 8 for $780,934.81 (including GST) served by the Claimant on the Respondent on 29 July 2022 and payment schedule number 8 for -$3,543,511.84 (including GST) dated 12 August 2022.2. In summary, the parties’ respective positions are:
a. According to the Claimant, the Respondent wrongfully terminated the Contract and that the Claimant’s rights to progress payment is not affected by termination [Adjudication Application, [48] and [49]].
b. The Claimant also contends that the Respondent is not entitled to set off any of its claimed amounts because the amounts are unliquidated and not an amount due but amounts claimed to be due and that in the alternative, the respondent’s set offs are damages and are not able to be considered as part of my adjudication decision [Adjudication Application, [51] – [53]].
c. According to the Respondent, the Claimant has not established an entitlement to the amounts claimed for variations because, amongst other things, the claims do not describe the work, the works are outside the Claimant’s Subcontract scope, the Subcontract terms have not been complied with and a breakdown of the costs or reasonableness of costs has not been provided [Adjudication Response, [8]].
3. The details of the parties respective positions are set out below.4. The Respondent issued an undated show cause notice by email on 27 May 2022 under Clause 39 – Default or insolvency of the Subcontract stating that the Respondent was in substantial breach of the following Clauses:
a. Clause 31 – failure to have adequate resources on site and to comply with a Superintendent direction in respect to adequacy of resources;
b. Clause 32 - departure from the construction programme durations without reasonable cause; and
c. Clause 34.1 – failure to comply with a Superintendent direction in respect to a delay to the Works under Subcontract (WUS).
5. The show cause notice required the Claimant to respond by 5pm on 7 June 2022.6. The Claimant responded to the show cause notice on 7 June 2022 stating:
a. It always provided the required resources;
b. Despite its recommendations it was “pushed” by the Respondent to remove wet materials from site which resulted in returned loads;
c. It had already notified the Respondent that its CSM wall contractor had cross-contaminated the dam materials;
d. Following an instruction from the environmental consultant, EI Australia, not to remove stockpile materials off site until it received a classification report, it is still awaiting a report.
e. Various works could not be completed due to the Respondent’s subcontractors;
f. It intends to back charge the Respondent for the major delay in the shoring works which hindered commencement, at full capacity, of the bulk excavation works; and
g. The Respondent caused it significant cost and delays and it formally rejects the claims in the show cause letter.
7. The Respondent terminated the Subcontract on 1 July 2022 on the alternate bases below:
a. Firstly, the claimant’s conduct is repudiatory and despite repeated warnings evinced a clear intention to no longer be bound by the terms of the Subcontract;
b. Secondly, if it is found that the above bases are invalid the Claimant has substantially breached the terms of the Subcontract;
c. Thirdly, if it is found that the above bases are invalid the Claimant has failed to show reasonable cause why it should not exercise a right under Clause 39.4 – Main Contractor’s rights; and
d. Fourthly, if it is found that the above bases are invalid it terminates under Clause 40B – Termination for Convenience.
8. The Respondent also stated:
a. In accordance with terms of the Subcontract, it is entitled to set off and/or deduct amounts otherwise payable to the Claimant; and
b. The Claimant should remove all plant, equipment and materials immediately, but not later than 12pm on 4 July 2022.
9. Based on the above, I consider that the parties respective rights regarding the payment claim under the Subcontract and the Act are:
a. Under section 13(1C) of the Act, the Claimant is entitled to serve a payment claim on and from the date of termination;
b. Under Clause 39.4 – Main Contractor’s rights: if the Subcontractor fails to show reasonable cause, the Main Contractor may by written notice:
39.4(a) – Take out of the Subcontractor’s hands the whole or part of the work remaining to be completed and suspend payment until it becomes due and payable pursuant to clause 39.6; or
39.4(b) – Terminate the Subcontract.
c. Under Clause 39.5 - Take out: the Main Contractor shall complete the works using materials, equipment and other things intended for WUS but it does not appear that the Respondent has taken possession of such. The Clause also requires the Subcontract Superintendent to keep records of the cost of completing the works taken out.
d. Clause 39.6 – Adjustment of completion of work taken out: requires that when work taken out of the Subcontractor’s hands has been completed, the Subcontract Superintendent shall assess the cost incurred and certify the difference between the cost and the amount that would otherwise have been paid to the Subcontractor had it completed the works.
e. Under Clause 39.10 – Termination, if the Subcontract is terminated pursuant to subclause 39.4(b), the parties’ remedies, rights and liabilities shall be the same as they would have been under the law governing the Subcontract had the defaulting party repudiated the Subcontract and the other party elected to treat the Subcontract as at an end and recover damages.
f. Clause 40B – Termination for Convenience of the Main Contractor, if the Mian (sic) Contractor terminates the Subcontract pursuant to this Clause, the Subcontractor is entitled to be paid:
40B(a)(i) the value of work properly performed and executed prior to the date of termination; and
40B(a)(ii) the cost of materials reasonably ordered for the work.
10. Accordingly, if the Subcontract is terminated, pursuant to subclause 39.4(b), payment shall be per the Subcontract.
Item
|
Claimed Amount
|
Scheduled Amount
|
Difference
|
Contract Works
|
$565,522.95
|
-$230,728.50
|
-$796,251.45
|
Variations
|
$28,840.00
|
$0.00
|
-$28,840.00
|
Claim for retention
|
$115,577.79
|
$0.00
|
-$115,577.79
|
Deductions
|
$0.00
|
-$2,990,645.90
|
-$2,990,645.90
|
Total (GST exclusive)
|
$709,940.74
|
-$3,221,374.40
|
-$3,931,315.14
|
GST
|
$70,994.07
|
-$322,137.44
|
-$393,131.51
|
Total (GST inclusive)
|
$780,934.81
|
-$3,543,511.84
|
-$4,324,446.65
|
Claim for Retention Release107. In the payment claim, the Claimant claims $115,577.79 for release of its retention.
108. In the payment schedule, the Respondent assesses this item as $0.00 for the following reasons:
a. There is no right or entitlement under the Subcontract;
b. The Claimant has not satisfied the Subcontract pre-conditions to an entitlement to claim retention money;
c. It has an express right under the Subcontract to have recourse to retention money;
d. The Claimant is indebted to the Respondent “for an amount enormously in excess of the retention money”; and
e. When the Subcontract was terminated, the Claimant did not accrue any right to retention money and cannot satisfy the contractual rights to claim its retention.
109. In the adjudication application, the Claimant states:
a. It did not abandon the site and complied with its obligations under the Subcontract;
b. A Notice of Delay was submitted by A-Civil on 1 July 2022, requesting an Extension of Time for the delay caused by inclement weather in reaching practical completion;
c. The Respondent sent it the termination letter on 1 July 2022 without providing any reasons as to why the project was terminated; and
d. The Respondent deprived it of the opportunity to carry out its obligations under the Contract by wrongfully terminating the Contract which was intentional.
110. In the adjudication response, the Respondent states:
a. There is no basis to claim retention monies under the contract or under the Act;
b. The Respondent is entitled under the Subcontract to have recourse to the retention money and alternatively, any claim for retention monies is a claim for damages and cannot be made under the Act;
c. It repeats and relies on the reasons in its Payment Schedule;
d. The payment claim is not a claim for construction work or related goods or services and is therefore not a payment claim for the purposes of the Act; and
e. There is no right or entitlement under the Subcontract for the Claimant to claim its retention. In accordance with section 10 of the Act, the Adjudicator must have regard to the terms of the Subcontract and the terms of the Subcontract do not give rise to an entitlement for the Claimant to make this claim.
111. Pursuant to Clause 5.4, the Subcontractor’s entitlement to security is:
a. reduced by 50% upon practical completion of the head contract with the reduction released within 28 days; and
b. the balance released 28 days after the final certificate is issued under the head contract.
112. Clause 5.4 of the Subcontract links the Subcontractor’s entitlement to security to practical completion and issue of the final certificate under the head contract which I find is void for contracting out of the Act. Notwithstanding, the Subcontract has been terminated and, therefore, the Claimant is entitled to the release of its security.113. Therefore, I value the claim for retention at $115,577.79.
|
Adjudicated Amount
|
Contract works
|
$38,288
|
Variations
|
$4,835.00
|
Retention
|
$115,577.79
|
Deductions
|
-$6,000.00
|
|
$152,700.79
|
GST
|
$15,270.08
|
Total Amount
|
$167,970.87
|
163. Pursuant to section 29(3) of the Act, I determine that the parties shall be liable to contribute to the Adjudicator’s and AMA’s fees and expenses in the following proportions:
Claimant: 50%
Respondent: 50%
What did the Adjudicator decide on the retention monies claim?
The alleged denial of procedural fairness
18. The basis of the Adjudicator’s decision in respect of A-Civil’s claim for retention was:
(a) The Adjudicator’s conclusion that cl 5.4 of the contract was void (Determination at [112]);
(b) Alternatively, the Adjudicator’s further conclusion that there was a right to release of the retention upon the termination of the contract (Determination at [112]);
19. In respect of the conclusions described in par 18 above:
(a) Neither was a conclusion sought by either party in the adjudication;
(b) The Adjudicator gave no advance notice that he was considering reaching that conclusion.
(c) Each conclusion was reached in denial of procedural fairness.
Statutory scheme
8 Right to progress paymentsA person who, under a construction contract, has undertaken to carry out construction work or to supply related goods and services is entitled to receive a progress payment.
9 Amount of progress payment
The amount of a progress payment to which a person is entitled in respect of a construction contract is to be—
(a) the amount calculated in accordance with the terms of the contract, or
(b) if the contract makes no express provision with respect to the matter, the amount calculated on the basis of the value of construction work carried out or undertaken to be carried out by the person (or of related goods and services supplied or undertaken to be supplied by the person) under the contract.
12 Effect of “pay when paid” provisions(1) A pay when paid provision of a construction contract has no effect in relation to any payment for construction work carried out or undertaken to be carried out (or for related goods and services supplied or undertaken to be supplied) under the contract.
(2) In this section—
money owing, in relation to a construction contract, means money owing for construction work carried out or undertaken to be carried out (or for related goods and services supplied or undertaken to be supplied) under the contract.
pay when paid provision of a construction contract means a provision of the contract—
(a) that makes the liability of one party (the first party) to pay money owing to another party (the second party) contingent on payment to the first party by a further party (the third party) of the whole or any part of that money, or
(b) that makes the due date for payment of money owing by the first party to the second party dependent on the date on which payment of the whole or any part of that money is made to the first party by the third party, or
(c) that otherwise makes the liability to pay money owing, or the due date for payment of money owing, contingent or dependent on the operation of another contract.
(2) A payment claim –
(a) must identify the construction work (or related goods and services) to which the progress payment relates, and
(b) must indicate the amount of the progress payment that the claimant claims to be due (the claimed amount), and
(c) must state that it is made under this Act.
(3) The claimed amount may include any amount –
...
(b) that is held under the construction contract by the respondent and that the claimant claims is due for release.
(2) A payment schedule –
(a) must identify the payment claim to which it relates, and
(b) must indicate the amount of the payment (if any) that the respondent proposes to make (the scheduled amount).
(3) If the scheduled amount is less than the claimed amount, the schedule must indicate why the scheduled amount is less and (if it is less because the respondent is withholding payment for any reason) the respondent’s reasons for withholding payment.
(2) In determining an adjudication application, the adjudicator is to consider the following matters only –
(a) the provisions of this Act;
(b) the provisions of the construction contract from which the application arose,
(c) the payment claim to which the application relates, together with all submissions (including relevant documentation) that have been duly made by the claimant in support of the claim;
(d) the payment schedule (if any) to which the application relates, together with all submissions (including relevant documentation) that have been duly made by the respondent in support of the schedule;
(e) the results of any inspection carried out by the adjudicator of any matter to which the claim relates.
29 Adjudicator’s fees
(1) An adjudicator is entitled to be paid for adjudicating an adjudication application—
(a) such amount, by way of fees and expenses, as is agreed between the adjudicator and the parties to the adjudication, or
(b) if no such amount is agreed, such amount, by way of fees and expenses, as is reasonable having regard to the work done and expenses incurred by the adjudicator.
(2) The claimant and respondent are jointly and severally liable to pay the adjudicator’s fees and expenses.
(3) The claimant and respondent are each liable to contribute to the payment of the adjudicator’s fees and expenses in equal proportions or in such proportions as the adjudicator may determine.
(4) An adjudicator is not entitled to be paid any fees or expenses in connection with the adjudication of an adjudication application if he or she fails to make a decision on the application (otherwise than because the application is withdrawn or the dispute between the claimant and respondent is resolved) within the time allowed by section 21(3).
32A Finding of jurisdictional error in adjudicator’s determination(1) If, in any proceedings before the Supreme Court relating to any matter arising under a construction contract, the Court makes a finding that a jurisdictional error has occurred in relation to an adjudicator’s determination under this Part, the Court may make an order setting aside the whole or any part of the determination.
(2) Without limiting subsection (1), the Supreme Court may identify the part of the adjudicator’s determination affected by jurisdictional error and set aside that part only, while confirming the part of the determination that is not affected by jurisdictional error.
34 No contracting out(1) The provisions of this Act have effect despite any provision to the contrary in any contract.
(2) A provision of any agreement (whether in writing or not) —
(a) under which the operation of this Act is, or is purported to be, excluded, modified or restricted (or that has the effect of excluding, modifying or restricting the operation of this Act), or
(b) that may reasonably be construed as an attempt to deter a person from taking action under this Act,
is void.
Procedural fairness
Relevant principles
[32] As explained in MZAPC, the materiality of a breach requires consideration of “the basal factual question of how the decision that was in fact made was in fact made”. This question is determined by proof of historical facts on the balance of probabilities. Then, it is necessary to consider whether the decision that was in fact made could have been different had the relevant condition been complied with “as a matter of reasonable conjecture within the parameters set by the historical facts that have been determined”. The burden falls on the plaintiff to prove “on the balance of probabilities the historical facts necessary to enable the court to be satisfied of the realistic possibility that a different decision could have been made had there been compliance with that condition”.[33] There will generally be a realistic possibility that a decision-making process could have resulted in a different outcome if a party was denied an opportunity to present evidence or make submissions on an issue that required consideration. The standard of “reasonable conjecture” is undemanding. It recognises that a fundamental purpose of affording procedural fairness is to afford an opportunity to raise relevant matters which are not already obvious, or not liable to be advanced by the apparently persuasive “story” of the opposing party. Where a Tribunal errs by denying a party a reasonable opportunity to present their case, “reasonable conjecture” does not require demonstration of how that party might have taken advantage of that lost opportunity. Nothing said in MZAPC denies this. To the contrary, the standard of “reasonable conjecture”, correctly applied, proceeds on assumptions that are derived from the rationale for procedural fairness, namely that, if given a fair opportunity to present their case, a party will take advantage of that opportunity and that, by doing so, the party could achieve a favourable outcome.
Submissions of the parties
Consideration
Adjudicator’s fees and expenses
Submissions of the parties
(a) A material denial of procedural fairness in the making of a determination gives rise to jurisdictional error.(b) An adjudication determination affected by a jurisdictional error is void ab initio: New South Wales Netball Association Ltd v Probuild Construction (Aust) Pty Ltd [2015] NSWSC 1339 at [49]; Parrwood Pty Ltd v Trinity Constructions (Aust) Pty Ltd [2020] NSWCA 172 at [37]- [43]. That reflects the conventional administrative law position: e.g. Plaintiff S157/2002 v Commonwealth of Australia (2003) 211 CLR 476; [2003] HCA 2 at [76].
(c) Section 32A confers a discretionary power prospectively to confirm, and revivify, parts of an otherwise invalid determination. There is no “self-executing” severance. Rather, severance is conditional on the making of an order by the Court under s 32A, and any such order operates prospectively and therefore will not change the historical fact that there was no adjudication determination within the relevant time for the purposes of s 29(4) of the Act.
Consideration
In our view, Bhardwaj cannot be taken to be authority for a universal proposition that jurisdictional error on the part of a decision-maker will lead to the decision having no consequences whatsoever. All that it shows is that the legal and factual consequences of the decision, if any, will depend upon the particular statute. As McHugh, Gummow, Kirby and Hayne JJ said in Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355 at 388 - 389:
‘An act done in breach of a condition regulating the exercise of a statutory power is not necessarily invalid and of no effect. Whether it is depends upon whether there can be discerned a legislative purpose to invalidate any act that fails to comply with the condition. The existence of the purpose is ascertained by reference to the language of the statute, its subject matter and objects, and the consequences for the parties of holding void every act done in breach of the condition’ [42].
New powers will enable the Supreme Court to sever part of an adjudicator’s determination affected by jurisdictional error and confirm the balance to be enforceable. In Multiplex Constructions Pty Ltd v Luikens & Anor [2003] NSWSC 1140, the New South Wales Supreme Court held that jurisdictional error invalidates the whole of an adjudicator’s determination. This is the case even where the error is confined to one part of the determination and does not affect the remaining part or parts. This outcome unfairly and unnecessarily deprives a party of an interim payment with adverse consequences for cash flow. It also serves to incentivise a party to challenge unfavourable determinations. The purpose of section 32A is to address this by making clear that decisions can be set aside in part and as such are theoretically severable where jurisdictional error has infected a part but not the whole of the decision.
Conclusion
**********
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2023/345.html