You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2023 >>
[2023] NSWSC 615
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Context | No Context | Help
A.N.T. Building Pty Ltd v Vibe Electrical Pty Ltd [2023] NSWSC 615 (8 June 2023)
Last Updated: 8 June 2023
|
Supreme Court
New South Wales
|
Case Name:
|
A.N.T. Building Pty Ltd v Vibe Electrical Pty Ltd
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
8 June 2023
|
Date of Orders:
|
8 June 2023
|
Decision Date:
|
8 June 2023
|
Jurisdiction:
|
Equity - Technology and Construction List
|
Before:
|
Stevenson J
|
Decision:
|
Application to dismiss proceedings to be dismissed; plaintiff to pay the
costs of the application on an indemnity basis and by 28
July 2023; such costs
to be assessed as a global figure; proceedings to be dismissed if those costs
not paid
|
Catchwords:
|
CIVIL PROCEDURE – whether proceedings should be dismissed for want of
prosecution with due dispatch
|
Legislation Cited:
|
|
Cases Cited:
|
|
Category:
|
Procedural rulings
|
Parties:
|
A.N.T. Building Pty Ltd (Plaintiff) Vibe Electrical Pty Ltd
(Defendant)
|
Representation:
|
Counsel: B Le Plastrier (Plaintiff) B Lloyd
(Defendant)
Solicitors: Flame Tree Legal (Plaintiff) Brander Smith
McKnight Lawyers (Defendant)
|
File Number(s):
|
2021/284342
|
EX TEMPORE JUDGMENT (REVISED)
- The
plaintiff ("the Builder") brings these proceedings against the defendant ("the
Contractor"). The claim relates to contracts between
the Builder and the
Contractor in June 2015 and April 2016 arising from developments at
Manly and Woollahra. The claim made by the
Builder against the Contractor
relates to alleged incomplete and defective work and delay.
- The
matter before me today is the defendant's Notice of Motion of
12 April 2023 seeking an order under Uniform Civil Procedure Rules
2005 (NSW), r 12.7(1), that the proceedings be dismissed for, in effect, want of
diligent prosecution.
- In April 2019,
the Builder commenced proceedings in the District Court of New South Wales
against the Contractor making the same claims
for incomplete and defective work
and delay as are being made in these proceedings. The Builder prosecuted those
proceedings so unsatisfactorily
that in April 2020 the Contractor sought
and obtained an order that those proceedings be dismissed for want of
prosecution.
- The
Builder commenced these proceedings on 6 October 2021 seeking, as I
say, the same relief arising from the same matters as were
made in the District
Court proceedings.
- In
these proceedings, on 2 July 2022, by consent, an order was made
that the Builder serve its lay and expert evidence by 14 October
2022.
No evidence was served.
- The
matter was before the Court on 3 February 2023, on which occasion the
Builder proposed that the time to serve its lay evidence
be extended to
28 February 2023 and the time to serve its expert evidence be extended
to 6 April 2023.
- Recognising
the position that it was in, the Builder proposed that those orders be subject
to a guillotine order. Indeed, in his
affidavit made on
3 February 2023, the sole director of the Builder, Mr Gleeson,
deposed that, "I understand that this means unless
I comply with the
order it is likely I will not be able to file any further evidence in the
proceedings".
- The
solicitor for the Builder deposes he spent much time in February 2023
working with Mr Gleeson to prepare Mr Gleeson's affidavit
including,
Mr Wells said, working with Mr Gleeson for 15 hours on
27 February and 19 hours on 28 February 2023.
- The
affidavit was served in the early hours of 1 March 2023. Nothing turns
on that slight delay.
- However,
the affidavit referred to an exhibit containing 1534 pages. That
exhibit was not served with the affidavit due to, apparently,
difficulties
uploading its bulk into Mr Wells' email system. It was not served until
early May. The "explanation" given for that
is that there was "pagination" and
"cross-referencing" (or similar) problems. It is hard to understand how this
could have caused
such a delay.
- Mr Wells
also has deposed that, despite all the work he did in February 2023, he did
not have an opportunity to "review" the affidavit
as he would "usually do" let
alone have counsel cast his or her eye over the document.
- Ultimately,
late in March 2023, Mr Wells got instructions to brief counsel.
- It
was in that circumstance that the Contractor filed its motion of
12 April 2023 seeking to have the proceedings dismissed for want
of
prosecution.
- Despite
the consent guillotine order of 3 February 2023 that the Builder
serve its expert evidence by 6 April 2023, the relevant expert,
Mr Adrian Jamieson, a quantity surveyor, was not retained until
12 May 2023. Again, no sensible explanation has been given for that
delay.
- The
position now is that the Builder has foreshadowed serving a further affidavit of
Mr Gleeson today. This is said to be in the final
stages of preparation,
despite the fact that Mr Wells deposed on 12 May 2023 that
Mr Gleeson's supplementary affidavit was "well
advanced".
- Mr Wells
has also deposed:
“Generally, the supplementary affidavit is required to rectify various
admissibility issues and rectify the exhibit (that is,
replace black and white
photographs with colour photographs, A4 pages with A3 pages and replace
incomplete documents with complete
documents). The supplementary affidavit will
include evidence as to the time and date photographs were taken. It will also
provide
foundation for conclusions and include more precise details with respect
to various aspects of Mr Gleeson’s evidence so that
they plaintiff’s
case can be better understood by experts, the defendant and the Court.”
- Mr Le Plastrier,
who appears today for the Builder, informed me that as well as dealing with the
matter to which Mr Wells deposed,
the new affidavit will deal with some
matters of substance.
- Mr Jamieson
has sworn an affidavit confirming that he has been retained, and foreshadowing
that he expects to be in a position to
be able to produce a report by
28 June.
- Before
me today also is the Builder's notice of motion of 2 June seeking leave to
rely upon "further lay evidence" and "expert evidence"
in these proceedings. The
leave that will be sought is to rely on Mr Gleeson's further affidavit and
Mr Jamieson's report once they
are to hand.
- The
circumstances in which a court will dismiss proceedings for want of prosecution
are well-established, and include, as Simpson
J (as her Honour then was) stated
in Hoser v
Hartcher:[1]
(a) the ultimate question is whether, on balancing the prejudice to the
respective parties by making or not making an order, justice
demands that the
action be dismissed;
(b) the discretion should be exercised only in a clear case where it is
manifestly warranted ... as is generally the case with discretionary
decisions,
each case depends upon its own facts;
(c) any explanation offered by the plaintiff for the delay in proceeding must be
considered;
(d) personal blamelessness on the part of a plaintiff (as distinct from any
tardiness or other fault on the part of his/her/its legal
representative) is
relevant. (Footnotes omitted.)
- This
is a case where I have given serious consideration to taking the drastic step of
dismissing the proceedings.
- I
am however persuaded that notwithstanding the manner in which the Builder has
been vexed by the way these proceedings have been
conducted, it would not be in
the interests of justice to shut the plaintiff out from pursuing a claim which
may well have merit.
- Accordingly,
I propose to give what the Builder should understand to be one last chance to
get its house in order, and to diligently
prosecute these proceedings to their
conclusion. The Builder should understand that no further procedural delinquency
of any kind,
let alone of the kind that I have described in these reasons, will
be tolerated.
- Accordingly,
I propose to dismiss the Contractor's notice of motion.
- Mr Le
Plastrier, in his written submissions, somewhat ambitiously I thought, suggested
the motion should be dismissed with costs.
I do not propose to do that. I
propose to order that, notwithstanding the fact that the motion is to be
dismissed, the Builder pay
the Contractor's costs of the motion on an indemnity
basis. I propose to assess those costs on an indemnity basis under section 98(4)
of the Civil Procedure Act 2005 (NSW). I propose then
order that that figure be paid within 14 days, and order that if that
amount is not paid, for that reason alone,
the proceedings will stand
dismissed.
- I
propose to defer considering whether the Builder should have leave to rely upon
Mr Gleeson's further affidavit, and Mr Jamieson's
foreshadowed report,
and also defer the question of whether, how and what terms, the Builder should
pay any costs of the Contractor
that will be thrown away should leave be
granted.
[The Court adjourned to enable the parties to consider His
Honour’s reasons]
- Since
giving the above judgment earlier today, the Builder has adduced evidence from
Mr Gleeson to the effect that it issues payment
claims under the
Building and Construction Industry Security of Payment Act 1999 (NSW) at
the end of each month and usually receives payments in response to those
building claims around the middle of the following
month.
- The
moneys to be received in respect of the payment claims served at the end of May
2023 have been, Mr Gleeson says, "wholly allocated
to pay staff wages,
trade subcontractors and suppliers".
- Mr Gleeson
deposes that the Builder anticipates serving payment claims at the end of June
and to receive funds in respect of those
payment claims around the middle of
July. In those circumstances, Mr Gleeson deposes that, were the Builder
obliged to pay a sum
on account of the costs of the Contractor's motion prior to
that, it would "need to pay that in priority to trades and suppliers
and this
will have adverse consequences on [the Builder] carrying out and complying with
its contract obligations to its clients".
- It
appears to me that it is not in the interests of either party that the Builder's
ability to continue trading be jeopardised.
- In
those circumstances I am persuaded that I should vary what I said this morning
and order that if the Builder does not pay the sum
I propose to fix as the
Contractor's costs of its motion by 28 July 2023, then the proceedings will
stand dismissed.
- As
to what the gross sum costs order should be, I have received evidence from the
Contractor's solicitor to the effect that the actual
costs sustained by the
Contractor is $19.594, comprising solicitors' fees of $6,300, counsel's fees of
$10,300 and the motion filing
fee of $1,334.
- That
total figure obviously represents the total of the costs actually incurred by
the Contractor. I foreshadowed this morning that
I would make an order that
costs be on an indemnity basis. It may be that the total of $19,594 is
marginally above the costs that
the Contractor would recover on an indemnity
basis. However, I see no reason to discount that figure for today's
purpose.
- The
parties should bring in short minutes to give effect to these
reasons.
**********
[1] [1999] NSWSC 527 at
[20]- [23].
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2023/615.html