You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2023 >>
[2023] NSWSC 980
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Context | No Context | Help
In the matter of One Mastery Developments Pty Ltd [2023] NSWSC 980 (18 August 2023)
Last Updated: 18 August 2023
|
Supreme Court
New South Wales
|
Case Name:
|
In the matter of One Mastery Developments Pty Ltd
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
14 August 2023
|
Date of Orders:
|
18 August 2023
|
Decision Date:
|
18 August 2023
|
Jurisdiction:
|
Equity - Corporations List
|
Before:
|
Williams J
|
Decision:
|
See conclusion at [46]
|
Catchwords:
|
CORPORATIONS — Winding up — Statutory demand — Failure to
comply with statutory demand — No application to
set aside statutory
demand — Leave sought under s 459S to oppose winding up application on the
ground that the existence or
amount of debt disputed — Where dispute is
material to proving that the debtor company is solvent — Where serious
question
to be tried established — Where explanation for failure to apply
to set aside the statutory demand insufficient — Applicant
unreasonably
failed to attend to correspondence delivered to its registered office
|
Legislation Cited:
|
Building and Construction Industry Security of Payment Act 1999 (NSW), ss
4, 5, 6, 6(1)(b)(ii), 8, 13, 13(1), 14(4), 15Corporations Act 2001 (Cth), ss
459G, 459S, 459S(2), Part 5.4
|
Cases Cited:
|
|
Texts Cited:
|
N/A
|
Category:
|
Principal judgment
|
Parties:
|
Ceerose Pty Ltd ACN 088 827 678 (Respondent/Plaintiff) One Mastery
Developments Pty Ltd ACN 661 384 532 (Applicant/Defendant)
|
Representation:
|
Counsel: Mr M T Fernandes (Respondent/Plaintiff) Mr A D Bailey
(Applicant/Defendant)
Solicitors: Centurion Lawyers
(Respondent/Plaintiff) MurdockCheng Legal Practice
(Applicant/Defendant)
|
File Number(s):
|
2023/115232
|
Publication Restriction:
|
N/A
|
JUDGMENT
Introduction
- By
originating process filed on 11 April 2023, the plaintiff seeks an order winding
up the defendant in insolvency. The plaintiff
relies on the defendant’s
failure to comply with a statutory demand in respect of a debt of $202,462.08.
That statutory demand,
together with a verifying affidavit sworn by the director
of the plaintiff, was served on the defendant at its registered office
on 9
March 2023.
- The
statutory demand describes the debt as a statutory debt arising by operation of
s 14(4) of the Building and Construction Industry Security of Payment Act
1999 (NSW) (the SOP Act) in respect of payment claim PC02
served on the defendant on 20 December 2022, in response to which the defendant
served no payment
schedule. The verifying affidavit sworn by the
plaintiff’s director, Mr Edward Doueihi, described the debt in those
terms.
Mr Doueihi deposed that he had inspected the plaintiff’s business
records, that the debt remained due and payable by the defendant,
and that he
believed that there was no genuine dispute about the existence and amount of the
debt.
- The
defendant did not apply to set aside the statutory demand. These reasons for
judgment concern the defendant’s application
made by interlocutory process
filed on 6 July 2023, for leave under s 459S of the Corporations Act 2001
(Cth) to oppose the winding up application on the ground that the existence
of the alleged statutory debt is disputed.
- The
basis of that dispute, as articulated in the defendant’s submissions, is
that no statutory debt arose by operation of s
14(4) of the SOP Act because the
contract or arrangement between the parties was not a “construction
contract” within the meaning of the SOP Act, having not been a
contract or arrangement for the defendant to carry out “construction
work” or to supply “related goods and services” to
the plaintiff, as those terms are defined in ss 5 and 6 of the SOP Act.
Accordingly, in the defendant’s submission, the
plaintiff had no right to
progress payments under s 8 of the SOP Act, the plaintiff had no right to issue
a payment claim under s
13 of the SOP Act, and no statutory debt arose under s
14(4) of the SOP Act by reason of the defendant’s failure to serve a
payment schedule in response to the payment claim.
- The
defendant’s submissions described Mr Doueihi’s verifying affidavit
that accompanied the statutory demand as inadequate.
That is, in substance,
merely another way of expressing the defendant’s dispute about the
existence of the alleged statutory
debt in respect of which the plaintiff issued
the demand.
- There
was no dispute about the applicable principles. The matters relevant to an
application for leave under s 459S
are:[1]
- (1) whether
there is a serious question to be tried on the ground sought to be raised;
- (2) the
sufficiency of any explanation as to why that ground was not raised in an
application to set aside the creditor’s statutory
demand, involving an
evaluation of the reasonableness of the debtor’s conduct at the time when
the application might have been
made; and
- (3) whether the
Court is satisfied that the relevant ground is material to proving whether the
debtor is solvent.
- It
has been said that the discretion under s 459S is to be exercised
“cautiously and sparingly and with regard to the purpose of Part 5.4 of
the Corporations Act to provide for determination of any objections to a
creditor’s statutory demand by an application under s 459G of the
Corporations Act, rather than at the time of the winding up
application”.[2] More
recently, however, the description of the proper approach to the exercise of the
discretion as “cautious” or “sparing” has
been eschewed, recognising that careful scrutiny of each application on its
facts and keeping in mind the purpose and policy of
Part 5.4 is not equivalent
to caution or reluctance.[3]
- In
the present case, the plaintiff accepts that the dispute about the existence of
the statutory debt on which the defendant seeks
leave to rely in opposing the
winding up application is material to proving that the defendant is solvent,
irrespective of whether
the narrower or broader approach to s 459AS(2) is to be
preferred.[4] Accordingly, the
defendant’s application under s 459S turns on the first and second matters
referred to above.
- For
the reasons that follow, I have determined that leave should be refused.
Salient evidence
- The
defendant relied on affidavits affirmed by Mr Iwan Sunito on 20 June 2023 and 6
July 2023. The plaintiff, Ceerose Pty Ltd, relied
on an affidavit sworn by Mr
Doueihi on 6 August 2023.
- Mr
Sunito gave evidence that the defendant—One Mastery Developments Pty
Ltd—is a wholly owned subsidiary of One Mastery
Developments Holdco Pty
Ltd, which is in turn a wholly owned subsidiary of Global Capital Pty Ltd.
Sunito Capital Pty Ltd (as trustee
of the One Global Trust) is the holding
company of Global Capital Pty Ltd, and the ultimate holding company of the
defendant. Mr
Sunito is the sole director of Sunito Capital Pty Ltd, Global
Capital Pty Ltd, One Mastery Developments Holdco Pty Ltd, and the defendant.
Each of these entities, together with other related entities, has its registered
office at Level 29, 1 Market Street, Sydney.
- Mr
Sunito also gave evidence that Crown Group Holdings Pty Ltd (CGH) is the
parent company of a group of companies in the business of property development,
including Crown W48 Pty Ltd (Crown W48). Mr Sunito and his business
partner, Mr Paul Sathio, are the directors of CGH and Crown W48. Those entities
also have their registered
office at Level 29, 1 Market Street, Sydney.
- On
about 1 February 2021, the plaintiff submitted a tender to CGH or Crown W48 for
the finalisation of the design and construction
of certain buildings as part of
a high-rise and low-rise development at Waterloo known as
“Mastery” (the Development).
- At
a tender review meeting between representatives of the plaintiff and
representatives of CGH on 16 February 2021, CGH requested
that the plaintiff
submit a formal proposal for Early Contractor Involvement (ECI).
- The
plaintiff submitted its ECI proposal to CGH on or about 25 February 2021. The
proposal records CGH’s objective that “... the preferred Tenderer
will undertake an Early Contractor Involvement process to refine the design and
achieve a cost-effective
Final Tender Price”. The nature of the work
that the plaintiff proposed in order to achieve this objective was described in
Schedule 4 of the proposal
as involving the review of the design for the
Development in six specified stages (and on a building-by-building basis for
each stage)
to identify potential design changes to achieve cost savings without
sacrificing design integrity or the appearance, quality, and
functionality of
the buildings, the costing of those potential changes, and updates to the design
documentation to reflect the decisions
made. The proposal stated that this
process—referred to as “value engineering”, or
“value management”—would require the input and advice
of the architects, landscape architects, structural engineer, and building
services consultant.
- In
his affidavit affirmed on 6 July 2023, Mr Sunito deposed that Crown W48 did not
accept the plaintiff’s ECI tender.
- From
about February 2022, CGH representatives Mr William Lam and Ms Christine Chan
engaged with the plaintiff’s representatives
about changes to the pricing
that the plaintiff had submitted in its February 2021 tender. The plaintiff
submitted a revised tender
on or about 26 April 2022. According to Mr
Sunito’s evidence, he was in discussions with Mr Sathio at about this time
about
the possibility of “splitting” the Development so that
Mr Sunito would assume the development and construction of the low-rise
buildings within the development.
Mr Sunito deposed that he wanted to obtain
further information about the construction costs to determine whether the
proposed split
was feasible.
- On
or about 5 July 2022, CHG requested that the plaintiff submit a further ECI
proposal based on an engagement of six weeks, noting
that the plaintiff’s
previous proposal had been for a three-month engagement at a fee of
$250,000.00.
- On
or about 15 July 2022, CGH sent a letter to the plaintiff stating that the
plaintiff was the preferred tenderer for the component
of the Development
referred to as “Mastery Low Rise (Building A, B, D and E)”,
and that CGH wished to engage the plaintiff in “Early Contractor
Involvement (ECI)” for that component. It is convenient to refer to
this letter as the ECI engagement letter.
- The
ECI engagement letter described the work to be undertaken by the plaintiff under
the ECI engagement as including working with
“the Consultant
team” to workshop “Value Management savings”,
including savings to be derived from changes to the design and specifications.
The ECI engagement letter stipulated that the resources
to be provided by the
plaintiff were to include—at a minimum—a project director, a chief
estimator, and a design manager.
The plaintiff was to be paid a fee of
$80,000.00 (excluding GST) for the ECI services on the basis that any
third-party consultant
fees for value management exercises during the ECI would
be paid directly by “OGC”. The reference to
“OGC” appears to be a reference to Global Capital Pty Ltd.
The ECI engagement letter stated that the plaintiff would “forgo the
ECI fee if a D&C Contract is signed for the design and construction of the
Mastery Low Rise development”.
- It
is common ground between the plaintiff and the defendant that the plaintiff
performed ECI work during the period from about 15
July 2022 until 13 September
2022.
- Mr
Sunito gave evidence that the defendant company was incorporated on 1 August
2022 for the sole purpose of managing the Development
if the proposed split
between low-rise and high-rise proceeded.
- On
13 September 2022, the plaintiff was instructed to cease all further work
because a decision had been made not to award the tender
for the construction of
the Development to the plaintiff.
- Mr
Doueihi replied to that instruction by email dated 13 September 2022, expressing
his disappointment and describing the nature and
extent of the work that the
plaintiff had done in relation to the Development prior to and during the ECI
engagement. Mr Doueihi’s
email described that work as involving the
preparation and revision of estimates, the development of initiatives to be
incorporated
into the design to achieve cost savings, and participation in
programming and costing discussions and design meetings. Mr Doueihi
argued that
the plaintiff should be reimbursed for the costs of all of this work, including
work that the plaintiff had undertaken
prior to the commencement of the ECI
engagement. Mr Doueihi attached to his email a schedule entitled “Claim
for Reimbursable Costs” totalling $252,238.25 (excluding GST) and
$277,462.07 (including GST), calculated on the basis of the number of hours
worked by the
plaintiff’s managing director, construction manager, project
manager, design manager, chief estimator, estimator, and contractor
administrator, and personnel or third-party service providers referred to as
“programme”, “legals”, and “bill
of quantities”.
- Mr
Sunito gave evidence that, on 27 October 2022, he caused the sum of $75,000.00
to be paid to the plaintiff, “which covers close to the $80,000 ECI
Fee”. Mr Sunito did not proffer any explanation for failing to pay the
full $80,000.00 fee stipulated in the ECI engagement letter, plus
GST. Mr Sunito
gave evidence that he has “never agreed” with the
plaintiff’s claim of $277,462.07.
- It
is not necessary for present purposes to refer to all of the email
correspondence passing between the plaintiff and representatives
of the
defendant, its related companies, and CGH after 27 September 2022 in relation to
the plaintiff’s demand to be reimbursed
for its costs. It suffices to note
that the following communications between the parties occurred after the
$75,000.00 payment had
been made on or about 27 October 2022.
- On
3 November 2022, Mr William Lam of OGC sent emails to Mr Doueihi and to Ms Rima
Doueihi, the plaintiff’s Finance Director,
nominating the defendant as the
entity to which invoices were to be issued and stipulating that “[t]his
first invoice to be to the value of $75K excl. GST”.
- The
plaintiff issued invoice MAS1-PC01 to the defendant on 3 November 2022 for an
amount of $75,000.00, which was described as an
agreed “part
payment” of an ECI Engagement Fee of $252,238.25. As I have already
mentioned, the sum of $75,000.00 had already been paid, although not the
GST
component of $7,500.00 included in the invoice.
- During
the period from about 9 November to 8 December 2022, Mr Sunito sought, and the
plaintiff provided, further information about
its costing of the Development. It
was in that context that Mr Doueihi sent an email to Mr Sunito on 8 December
2022 reiterating
the plaintiff’s requirement for payment of the balance of
its costs, noting that the first invoice had been short-paid because
the GST
component had not been paid. On 9 December 2022, the plaintiff issued invoice
MAS1-PCO2 to the defendant for the balance
of $202,462.08. The plaintiff
re-issued that invoice on 20 December 2022. The re-issued invoice contained a
statement that it was
a payment claim made under the SOP Act.
- On
12 January 2023, Mr Jason Cameron—who appears to be a solicitor employed
by the plaintiff—sent an email to Mr Sunito
and others noting that no
response had been received to the plaintiff’s payment claim, and setting
out the provisions of ss
14(4) and 15 of the SOP Act.
- On
19 January 2023, Mr Doueihi sent an email to Mr Sunito referring to that email,
and to a meeting on 18 January 2023. Mr Doueihi’s
email foreshadowed legal
action to enforce payment but invited a resolution in the event that Mr Sunito
simply required additional
time to pay.
- Mr
Sunito replied by email dated 2 February 2023, disputing the plaintiff’s
entitlement to the sum invoiced and requesting confirmation
that the invoice had
been withdrawn. Mr Sunito stated that his email would be relied on in support of
an application for costs in
the event that the plaintiff initiated legal
action.
- As
I have mentioned earlier in these reasons, the plaintiff’s statutory
demand for $202,462.08, together with Mr Doueihi’s
verifying affidavit,
was served on the defendant at its registered office on 9 March
2023.[5]
- In
his affidavits affirmed on 20 June 2023 and 6 July 2023, Mr Sunito gave evidence
that he had not received any written correspondence
posted to the
defendant’s registered office in March 2023. Mr Sunito added that he had
not attended that office during 2023,
with the exception of two or three
occasions, “due to an internal dispute between the co-founders of the
Crown Group”. Mr Sunito gave evidence that he had been provided with a
copy of the statutory demand on 21 April 2023. Mr Sunito also gave evidence
of
having received a text message on 21 April 2023 attaching a photograph of the
winding up application. As I have already mentioned,
it was not until 6 July
2023 that the defendant filed its interlocutory process seeking leave under s
459S of the Corporations Act to oppose the winding up application on the
ground that the existence of the alleged statutory debt is
disputed.[6]
A serious
question to be tried?
- The
first matter referred to at [6] above directs attention to whether the defendant has
a seriously arguable case that the plaintiff’s payment claim, and the
defendant’s failure to serve a payment schedule in response to it, did not
give rise to a statutory debt under s 14(4) of the
SOP Act.7
- There
were two limbs to the defendant’s submission that it has a seriously
arguable case.
- The
first limb of the defendant’s submission was that the work done by the
plaintiff was not “construction work” or “related
goods and services” as defined in ss 5 and 6, and that the work was
therefore not carried out under a “construction contract” as
defined in s 4, of the SOP Act. The plaintiff was not entitled to make a payment
claim under s 13(1) because it had no entitlement
to progress payments under s 8
of the SOP Act, not being a person who had undertaken to “carry out
construction work or to supply related goods and services” under a
construction contract.
- The
second limb of the defendant’s submission, which received far less
attention than the first limb both in the written submissions
and during the
hearing, was that the work done by the plaintiff prior to 15 July 2022 was not
the subject of any “contract or other arrangement” under
which the plaintiff had undertaken to carry out construction work or to supply
related goods and services. The plaintiff had
simply performed the work as part
of its continuing efforts to succeed in its tender for the design and
construction work submitted
in February 2021 and revised in April 2022. That was
a further or alternative reason relied on by the defendant as giving rise to
an
arguable case that the plaintiff had no entitlement to progress payments under s
8 of the SOP Act (insofar as the work was done
prior to 15 July 2022) and
therefore no entitlement under s 13(1) to issue a progress claim. It was
submitted that, insofar as the
work was performed after 15 July 2022, it was
done on the terms of the ECI engagement letter, which entitled the plaintiff to
payment
of a fee of $80,000.00 (plus GST), of which the defendant paid
$75,000.00 before the statutory demand was issued.
- The
plaintiff submitted that the work done is properly characterised as design and
quantity surveying services, which fall within
the definition of
“related goods and services” in s 6 of the SOP Act. It was
further submitted that, even if the court considered that the defendant
established a serious question
to be tried, its application under s 459S should
be dismissed due to the absence of a sufficient explanation for its failure to
apply
to set aside the statutory demand on the basis of that dispute.
- In
my opinion, the evidence referred to at [20] and [24] above concerning the nature of the work that the
defendant agreed to undertake as described in the ECI engagement letter, and the
evidence of the nature of the work that it did undertake as described in Mr
Doueihi’s 13 September 2022 email, does not disclose
a serious question to
be tried that the work was not “construction work” or
“related goods and services” within the meaning of the SOP
Act. In my opinion, the work is properly described as design and quantity
surveying services—which
fall within the definition of “related
goods and services” in s 6(1)(b)(ii) of the SOP Act.
- However,
the defendant has established a seriously arguable case, in my opinion, that
most of the work was not done under a “construction contract”
as defined in s 4 of the SOP Act. The evidence summarised above raises
serious questions to be tried about whether the work done prior
to the ECI
engagement on 15 July 2022 was done under a “contract or other
arrangement” pursuant to which the plaintiff undertook to perform the
“construction work”. To the extent that work was
carried out after the parties entered into the ECI engagement on 15 July 2022,
the fee stipulated in the
ECI engagement letter was $80,000.00 (plus GST). As
referred to at [25]
above, $75,000.00 of that fee was paid by the plaintiff before the statutory
demand was issued. The defendant has therefore established
a serious question to
be tried about the existence or amount of the debt.
A sufficient
explanation?
- The
defendant’s submissions accepted that an applicant for leave under s 459S
must provide a sufficient explanation for failing
to apply to set aside the
statutory demand on the basis of the ground that it seeks leave to rely on in
opposing the winding up application.
The reasonableness of the applicant’s
conduct can be taken into account in assessing the sufficiency of the
explanation proffered.
Leave is less likely to be granted where there is some
default on the part of the applicant or its advisers in that
regard.[8]
- On
the basis of Mr Sunito’s evidence referred to at [34] above, I infer that
the defendant failed to put in place adequate arrangements to ensure that
correspondence delivered to its registered
office was brought to the attention
of its sole director, or to the attention of some other person to whom the sole
director delegated
the responsibility for dealing with and responding to such
correspondence on behalf of the company. There is no evidence that Mr
Sunito or
the defendant put in place any such arrangements. Nor is there is any evidence
that the dispute between Mr Sunito and the
other co-founders of the Crown Group
prevented him, as the sole director of the defendant, from attending the
defendant’s registered
office to check for, and attend to, correspondence,
during the month of March 2023. Mr Sunito simply says that he did not do so.
Even if the dispute precluded Mr Sunito from attending the registered office
personally, there is no evidence of any reason why arrangements
could not have
been put in place for the defendant’s mail to be sent to Mr Sunito. It
would not have been difficult to make
such arrangements, yet there is no
evidence that any steps were taken to do so. As the plaintiff submitted, the
failure to put any
arrangements in place was unreasonable, particularly having
regard to the emails passing between Mr Doueihi and Mr Sunito in January
and
February 2023 in which Mr Doueihi foreshadowed that the plaintiff may commence
legal action against the defendant in respect
of its claim for
payment.9 [9]n short, there is no
evidence that the statutory demand did not come to Mr Sunito’s attention
within the 21-day period for any
reason other than his, and the
defendant’s, failure to act reasonably in relation to systems or
arrangements for the distribution
or collection of mail addressed to the
defendant and delivered to its registered office.
- In
my opinion, Mr Sunito’s evidence does not disclose a sufficient
explanation for the defendant’s failure to apply to
set aside the
statutory demand within 21 days after it was served on the grounds of the
dispute that it now seeks to rely on in opposition
to the winding up order. The
policy objective of s 459G of the Corporations Act is to ensure
that disputes about the existence of a debt are determined at the point of an
application to set aside a creditor’s
statutory demand, rather than at the
point of the winding up
application.[10] To grant leave under
s 459S in this case would allow that policy objective to be displaced by a
debtor’s failure to take reasonable steps which were available
to it to
attend to correspondence served at its registered office in circumstances where
the debtor was well aware of the dispute
that gave rise to the issue of the
statutory demand, and where the creditor had foreshadowed legal action. In my
opinion, leave should
be refused in this case for that reason. As Black J said
in Vangory Holdings, “inattention and inactivity cannot provide
a satisfactory explanation for a failure to comply with or set aside a statutory
demand, since otherwise the statutory scheme in relation to statutory demands
would be significantly
undermined.”[11]
- As
counsel for the plaintiff submitted, the circumstances of this case do not call
for me to express a view about whether, as a matter
of statutory construction,
non-receipt of the statutory demand correctly served on the defendant’s
registered office would
have afforded a basis for granting leave under s 459S if
Mr Sunito had acted reasonably with respect to arrangements for the collection
of mail from the registered
office.[12]
Conclusion
- For
all of the foregoing reasons, the order of the Court is that the
defendant’s interlocutory process filed on 6 July 2023
is dismissed.
- I
am not aware of any reason why the defendant should not be ordered to pay the
plaintiff’s costs, but I will hear the parties
in relation to
costs.
**********
[1] In the matter of Vangory
Holdings Pty Ltd [2015] NSWSC 546 at [10], [20] (Black J) (Vangory
Holdings).
[2] Vangory Holdings at
[10] (Black J).
[3] In the matter
of Garslev Holdings Pty Ltd [2023] NSWSC 609 at [11]- [16] (Hammerschlag CJ in
Eq).
[4] Switz Pty Ltd v Glowbind
Pty Ltd (2000) 48 NSWLR 661; (2000) 155 FLR 282; (2000) 33 ACSR 723; [2000]
NSWCA 37 at [53]- [56] (Spigelman CJ, Handley and Giles JJA agreeing); Hanson
Construction Materials Pty Ltd v FEC Civil Pty Ltd [2009] NSWSC 161 at [28]
(Barrett J); see also the discussion of the narrow approach, as against the
broad approach, in Vangory Holdings at [24]-[33] (Black
J).
[5] See above at
[1].
[6] See [3]
above.
[7] Vangory Holdings at [11]
(Black J).
[8] Vangory Holdings at
[20] (Black J), and the authorities there referred
to.
[9] See above at
[30]-[32].
[10] In the matter of
ACN 151 738 135 Pty Ltd [2015] NSWSC 1216 at [14] (Black J) (ACN 151 738
135).
[11] Vangory Holdings at
[21] (Black J); see also ACN 151 738 135 at [14] (Black
J).
[12] Perpetual Nominees Ltd v
Masri Apartments Pty Ltd; Perpetual Nominees Ltd v Aus Constructions Pty Ltd
(2004) 49 ACSR 719; (2004) 22 ACLC 975; [2004] NSWSC 551 at [19] (Austin J);
Nick Scali Ltd v JSK Logistics Pty Ltd [2008] NSWSC 597 (Rein J); Hadley v BetHQ
Pty Ltd [2016] FCA 1263 at [39]- [42] (Farrell J); In the matter of Kornucopia
Pty Ltd (ACN 615 630 316) [2020] VSC 7 at [165]- [183] (Sifris J).
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2023/980.html