You are here:
AustLII >>
Databases >>
Supreme Court of New South Wales >>
2024 >>
[2024] NSWSC 552
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Context | No Context | Help
G&S Engineering Services Pty Ltd v MACH Energy Australia Pty Ltd (No 12) [2024] NSWSC 552 (10 May 2024)
Last Updated: 10 May 2024
|
Supreme Court
New South Wales
|
Case Name:
|
G&S Engineering Services Pty Ltd v MACH Energy Australia Pty Ltd (No
12)
|
Medium Neutral Citation:
|
|
Hearing Date(s):
|
8 May 2024
|
Decision Date:
|
10 May 2024
|
Jurisdiction:
|
Equity - Technology and Construction List
|
Before:
|
Stevenson J
|
Decision:
|
Defendants/Cross-Claimants given leave to file and serve Fourth Further
Amended Cross-Claim List Statement; parties to confer and
agree on proposed
revised directions needed to ready matter for trial
|
Catchwords:
|
CIVIL PROCEDURE – pleadings – amendment – late
application for amendment – where cross-claimants allege that
but for
cross-defendants’ alleged misleading or deceptive conduct it would have
engaged alternative contractor to construct
coal handling plant in accordance
with number of counter factual circumstances – where
cross-defendants’ experts identified
factual operational matters that
would allegedly also occur in the counterfactual circumstances – where
cross-defendants amended
their Cross-Claim Response to reflect these matters
– where cross-claimants seek to amend Cross-Claim List Statement to meet
that claim – where cross-claimants’ current case might fail absent
such amendment – where trial date imminent –
whether directions can
be made to ensure cross-defendants not prejudiced
|
Legislation Cited:
|
|
Cases Cited:
|
G&S Engineering Services Pty Ltd v MACH Energy Australia Pty Ltd (No 6)
[2022] NSWSC 628
|
Category:
|
Procedural rulings
|
Parties:
|
G&S Engineering Services Pty Ltd (First Plaintiff/First
Cross-Defendant) DRA Pacific Pty Ltd (Second Plaintiff/Second
Cross-Defendant) DRA Group Holdings (Pty) Ltd (Third Cross-Defendant) DRA
Global Limited (Fourth Cross-Defendant) MACH Energy Australia Pty Ltd (First
Defendant/First Cross-Claimant) MACH Mount Pleasant Operations Pty Ltd
(Second Defendant/Second Cross-Claimant) J.C.D. Australia Pty Ltd (Third
Defendant/Third Cross-Claimant)
|
Representation:
|
Counsel: M Lyons / D Johnson
(Plaintiffs/Cross-Defendants/Respondents) N Kidd SC / M Doyle
(Defendants/Cross-Claimants/Applicants)
Solicitors: HFW Australia
(Plaintiffs/Cross-Defendants/Respondents) Corrs Chambers Westgarth
(Defendants/Cross-Claimants/Applicants)
|
File Number(s):
|
2019/71358
|
JUDGMENT
- The
background to this matter is set out in the earlier judgments of the Court,
including my judgment of 17 May
2022.[1]
- This
is the Court’s 12th and my 10th interlocutory judgment in the proceedings.
- On
23 June 2023, I set these proceedings down for hearing before me for eight weeks
commencing on 19 August 2024.
- The
proceedings relate to a contract made in March 2017 (the
“Contract”), pursuant to which the defendants/cross-claimants
(“MACH”) contracted with the plaintiffs/cross-defendants
(“CDJV”) to design, construct, and commission a
coal handling and
processing plant and train load-out facility (the “Plant”) at Mount
Pleasant in the Hunter Valley.
- I
am now dealing with an application by MACH, made by Notice of Motion filed on 29
April 2024, although foreshadowed at an earlier
directions hearing on 15 April
2024, seeking leave to file and serve a Fourth Further Amended Cross-Claim List
Statement, which would
introduce an alternative case. MACH contends that this
alternative case is responsive to expert evidence served last year by CDJV
and
to an amendment made in November 2023 by CDJV to its Cross-Claim Response.
- I
have decided to grant MACH such leave. This will necessarily result in
significant adjustments to the current directions in relation
to the forthcoming
hearing.
- During
construction of the Plant, disputes arose between MACH and CDJV. Those disputes
were resolved by entry into a Settlement and
Variation Agreement on 20 April
2018. Amongst other things, the Settlement and Variation Agreement compromised
various claims made
by CDJV against MACH, provided for payment of further monies
to CDJV, and amended the Dates for Practical Completion under the Contract
such
that the Plant was to reach Practical Completion by 20 December 2018.
- Delays
ensued and MACH replaced CDJV with an alternative contractor to complete the
construction of the Plant. The Plant ultimately
achieved Practical Completion in
November 2019.
- In
these proceedings, CDJV claims some $15 million from MACH for various
entitlements under the Contract.
- MACH
contends that it was induced to enter into the Settlement and Variation
Agreement by representations, said to be misleading or
deceptive for the purpose
of s 18 of the Australian Consumer
Law.[2]
- MACH’s
case, as currently articulated in its Third Further Amended Cross-Claim List
Statement, is that but for CDJV’s
alleged misleading or deceptive
conduct:
(a) it would not have entered the Settlement and Variation Agreement;
(b) in one of four alternative counterfactual circumstances it would have
engaged an alternative contractor to complete some or alternatively
all of the
work necessary to design and construct the Plant;
(c) this would have caused Practical Completion to occur earlier than the actual
date of November 2019;
(d) the Plant would then have been complete and capable of producing coal
product to the maximum designed output specified in the
Contract; and
(e) it has suffered loss ranging from $675 million to $698 million (depending on
which counterfactual is adopted).[3]
- It
can thus be seen that CDJV’s claim, as significant as it is, is dwarfed by
MACH’s cross-claim.
- Until
the events to which I refer below occurred, CDJV’s response to
MACH’s claim included that:
(a) the Plant was only capable of producing the maximum designed output
specified in the Contract if particular outputs referrable
to identified
Separable Portions of the Plant were achieved not only from Practical
Completion, but also from Functional Completion;
and
(b) Functional Completion for each Separable Portion could only occur after
successful Performance Testing of each Separable Portion,
which would take
approximately three months to complete from the date of Practical
Completion.[4]
- An
issue thus was whether the Plant was capable of producing these outputs from
Practical Completion, as MACH contends, or from Functional
Completion, likely to
be three months later, as CDJV contended.
- In
April and May 2023, in support of this case, MACH served reports from its coal
processing expert, Mr Rodney Lamb, its mine planning
expert, Mr Ian Alexander,
and its financial accounting expert, Mr Greg Meredith.
- Between
September and November 2023, CDJV served responsive reports from its coal
processing expert, Mr Darren Mathewson, its mine
planning expert, Mr Adriaan
Benson, and its financial accounting expert, Mr Brian Wood.
- Mr
Mathewson opined that MACH would not have been able to produce coal product in
the quantities and at the times set out in Mr Lamb’s
and Mr
Alexander’s reports because of various issues affecting the available
capacity and feed rate of the Plant. Mr Mathewson
opined that these matters
affected the actual operation of the Plant operation, and would also have
affected the Plant’s operation
in the counterfactual circumstances the
subject of MACH’s claim. Similarly, Mr Benson opined that mining
operations would not
have been carried out in accordance with MACH’s
counterfactual mining plan, as the rate of mining was in fact restricted by
various matters which would also affect the rate of mining in the counterfactual
circumstances the subject of MACH’s claim.
- On
15 November 2023, CDJV amended their Cross-Claim Response to incorporate these
matters, and to abandon the matters set out at [13].
- As
Mr Lyons, who appeared with Mr Johnson for CDJV, submitted:
“Mr Mathewson’s report and the amended List Response did not advance
a positive case as to how the [Plant] would in fact
operate in the
counterfactuals. Rather, the case pleaded by [CDJV] and expert evidence in
support is destructive of the [Plant] performance hypothesis pleaded by
[MACH].” (Emphasis in original.)
- In
March 2024, MACH served responsive reports from each of Mr Lamb, Mr Alexander,
and Mr Meredith.
- The
combined effect of these reports is said by MACH to develop modelling of coal
production and processing and loss cash flows taking
into account the impact of
the matters said by CDJV’s experts to reflect the actual production at the
Plant, and which matters
CDJV contends would also affect its hypothetical
production in the various counterfactual circumstances posited by MACH.
- The
amendments that MACH seeks to make to its Cross-Claim List Statement seek to
give effect to these opinions. In substance, by the
proposed amendments, MACH
seeks to contend that if the issues identified by CDJV’s experts as
affecting actual coal production
at the Plant would also have affected coal
production in the counterfactual circumstances, it would nonetheless have
suffered loss
ranging from $263 million to $319 million; again, depending on
what counterfactual scenario is adopted.
- Mr
Kidd SC, who appeared with Mr Doyle for MACH accepted that its proposed amended
case is a true alternative to MACH’s presently
pleaded case, and that the
alternative cases are inconsistent with each other.
- Mr
Kidd also accepted that, as matters are presently pleaded, were CDJV to
establish the case propounded by its experts and since
incorporated into its
Cross-Claim Response last November, MACH’s cross-claim would fail.
- Thus,
Mr Kidd and I had this exchange:
“HIS HONOUR: Just so I am clear, so you accept that MACH would fail ... on
its presently pleaded case, if what I call the Mathewson
thesis is accepted.
KIDD: I think that seems to be the likely outcome.”
- Mr
Lyons submitted that MACH had not offered an adequate explanation for its
application, at this late stage, to amend its Cross-Claim
List Statement in the
manner I have described.
- In
my opinion, what I have set out above provides an adequate explanation for
MACH’s application to amend. Mr Lyons accepted
that, whatever else may be
said about the effect of the amendments by CDJV to its Cross-Claim Response in
November 2023, those amendments
did introduce, for the first time, a contention
that various aspects of production at the Plant which actually occurred would
also
affect the hypothetical production from the Plant in the counterfactuals
for which MACH contends. It is obvious why MACH seeks to
respond as it has.
- Mr
Lyons also submitted that the proposed amended case is, in any event, bound to
fail. This submission, put very briefly by Mr Lyons
in writing and orally,
focussed on the manner in which Mr Lamb’s and Mr Alexander’s reply
reports responded to the matters
identified in Mr Mathewson’s and Mr
Benson’s reports concerning the Plant’s operation in the actual, and
in MACH’s
counterfactual, circumstances.
- These
are not matters that I consider I should investigate in the context of this
application. They would involve detailed consideration
of the expert reports far
beyond the scope of a pleading amendment application and are matters that must
be left for the trial.
- I
see the real question before me as being one of case management, the question
being whether, at this very late stage, MACH’s
proposed amended case can
be accommodated in a way that allows CDJV a fair opportunity to respond to
it.
- In
that regard, in their submissions in chief, Mr Kidd and Mr Doyle proposed a
series of detailed directions for the service of responsive
reports from
CDJV’s expert witnesses, Messrs Mathewson, Benson and Wood, and for the
engagement of conclaves between those
experts and MACH’s experts, Messrs
Lamb, Alexander and Meredith.
- At
my suggestion, the parties prepared a Redfern Schedule setting out the detailed
directions suggested by MACH with responses from
CDJV and a rejoinder from MACH.
I am very grateful to the parties for the alacrity with which they produced that
document.
- What
emerges is that Messrs Mathewson and Benson can produce responsive reports in
time for them to conclave with Messrs Lamb and
Alexander and to produce a joint
report prior to the hearing.
- Mr
Wood is unable to produce a responsive report until mid-August 2024, with the
result that it will not be possible for him to conclave
with and produce a joint
report with Mr Meredith until several weeks after the trial commences on 19
August 2024.
- However,
as Mr Kidd submitted, the matters that will be the subject of Messrs
Wood’s and Meredith’s evidence, namely matters
of quantification,
would typically be dealt with near the conclusion of the evidence. It should not
be difficult for opening submissions,
and the matter generally, to proceed
reserving such matters for later consideration. Nor should there be any
insurmountable difficulty
with the lay evidence proceeding before the outcome of
Messrs Wood’s and Meredith’s conclave is known. I am told there
will
be 44 lay witnesses called, including witnesses dealing with CDJV’s claim
under the Contract and MACH’s misleading
or deceptive conduct case.
Accepting that it may be that not all those witnesses will be required for
cross-examination, it will
take many hearing days to deal with those witnesses.
Further, although neither party is now able to identify any lay witness who
might need to be recalled for further cross-examination once the Wood/Meredith
conclave has concluded and their joint report is to
hand, there is agreement in
principle that, if necessary, this could be done.
- Following
production of the Redfern Schedule to which I have referred, I circulated a
proposed future timetable, which is set out
in substance
below:
Coal processing experts
(1) By 5 June 2024, the Plaintiffs/Cross-Defendants will serve on the
Defendants/Cross-Claimants any rejoinder expert report of Mr
Darren
Mathewson.
(2) By 5 July 2024, Mr Rodney Lamb and Mr Darren Mathewson are to confer and
produce a joint expert report.
Mine planning experts
(1) By 7 June 2024, the Plaintiffs/Cross-Defendants will serve on the
Defendants/Cross-Claimants any rejoinder expert report of Mr
Adriaan
Benson’s report.
(2) By 5 July 2024, Mr Ian Alexander and Mr Adriaan Benson are to confer and
produce a joint expert report.
Financial accounting experts
(1) By 16 August 2024, the Plaintiffs/Cross-Defendants will serve on the
Defendants/Cross-Claimants any rejoinder expert report of
Mr Brian Wood.
(2) By 13 September 2024, Mr Greg Meredith and Mr Brian Wood are to confer
and produce a joint expert report.
Further orders
(1) By 2 August 2024, the parties are to:
(a) file and serve written opening submissions; and
(b) file and deliver a Court Book which includes witness statements and experts
statements, but not annexures and exhibits to those
statements.
(2) By 9 August, the parties are to:
(a) file and deliver a Court Book which includes all other documents to be
relied on at hearing, including exhibits and annexures
to witness statements;
(b) file a joint statement of objections to lay witnesses; and
(c) provide a trial plan.
(3) By 23 August, the parties are to file a joint statement of objections to
expert witnesses.
(4) Order that both parties be free to confer with their experts, other than
in relation to their joint reports, but including as
to the agenda for any
conclave.
(5) Order that both parties have liberty to seek orders requiring the other
to recall, for further cross-examination, any witness
whose evidence has
otherwise been concluded prior to the circulation of the joint expert report of
Mr Greg Meredith and Mr Brian
Wood.
- Subject
to hearing from the parties as to matters of detail, I propose to make orders
granting MACH leave to amend its Cross-Claim
List Statement as proposed, and to
make directions to this effect. The directions should also make provision for
filing and service
by CDJV of an amended cross-claim response to the Amended
Cross-Claim List Statement.
- The
parties should now confer and agree on the orders needed to give effect to these
reasons.
**********
[1] G&S Engineering Services
Pty Ltd v MACH Energy Australia Pty Ltd (No 6) [2022] NSWSC
628.
[2] Competition and Consumer
Act 2010 (Cth), Sch 2 – Australian Consumer
Law.
[3] By its proposed Fourth
Further Amended Cross-Claim, MACH contends that it has in fact suffered loss
ranging from $718 million to
$743
million.
[4] See [C10(b)-(c)] and
[C68(c)(ii)] of CDJV’s then Third Further Amended Cross-Claim
Response.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/nsw/NSWSC/2024/552.html