Home
| Databases
| WorldLII
| Search
| Feedback
Supreme Court of Queensland - Court of Appeal |
Last Updated: 6 May 2008
SUPREME COURT OF QUEENSLAND
CITATION:
|
Arnold Electrical & Data Installations P/L v Logan Area Group
Apprenticeship/Traineeship Scheme Ltd
[2008] QCA 100 |
PARTIES:
|
LOGAN AREA GROUP APPRENTICESHIP/TRAINEESHIP SCHEME LIMITED
ACN 010 799 809 (plaintiff/respondent/cross-applicant) v ARNOLD ELECTRICAL & DATA INSTALLATIONS PTY LTD ACN 056 068 896 (defendant/applicant/cross-respondent) |
FILE NO/S:
|
Appeal No 10788 of 2007
Appeal No 10942 of 2007 DC No 106 of 2007 |
DIVISION:
|
Court of Appeal
|
PROCEEDING:
|
Application for Leave s 118 DCA (Civil)
|
ORIGINATING COURT:
|
District Court at Brisbane
|
DELIVERED ON:
|
2 May 2008
|
DELIVERED AT:
|
Brisbane
|
HEARING DATE:
|
15 April 2008
|
JUDGES:
|
|
ORDER:
|
|
CATCHWORDS:
|
APPEAL AND NEW TRIAL – APPEAL – PRACTICE AND PROCEDURE –
QUEENSLAND – WHEN APPEAL LIES BY LEAVE OF COURT –
GENERALLY –
where
s 118(3) of the District Court of Queensland Act 1967 (Qld) confers a general discretion on the Court of Appeal to grant or refuse leave to appeal – where the Court of Appeal held that the primary judge erred in construing the contract – where the argument relied upon to demonstrate that error before the Court of Appeal was not raised before the trial judge – where the evidence placed before the trial judge was unclear – where the pleadings at the trial did not identify any material facts to support the claim – where the quantum in issue was relatively small – where the matter had already been litigated in two courts – whether leave to appeal should be granted in the circumstances CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND
INTERPRETATION OF CONTRACTS – OTHER MATTERS –
where the contract
contained a ‘change clause’ – where the change clause referred
to an ‘award rate’
– where the term ‘award rate’
referred to labour costs – where the relevant labour costs were changed by
an ‘enterprise bargaining agreement’ – whether, on a correct
interpretation of the contract, the change effected
by the ‘enterprise
bargaining agreement’ amounted to a change of the ‘award rate’
for the purposes of the
contract
EVIDENCE – ADMISSIBILITY AND RELEVANCY – OPINION EVIDENCE
– EXPERT OPINION – IN GENERAL – where the
defendant alleged
that its witness was an expert – where the witness relied upon facts which
were not identified and proved
or admitted – whether the evidence had any
probative effect
EVIDENCE – ADMISSIBILITY AND RELEVANCY – IN GENERAL –
OBJECTIONS – where evidence was tendered that allegedly
proved various
material facts – where no objection was made – whether because of
the absence of an objection to its tender
the evidence had probative
effect
PROCEDURE – SUPREME COURT PROCEDURE – QUEENSLAND –
PROCEDURE UNDER RULES OF COURT – PLEADING GENERALLY –
where there
was a dispute as to the applicable rate of labour cost to be applied –
where the defendant contented that a particular
applicable rate of labour
applied – where the plaintiff pleaded an explanation for its denial of the
defendant’s contention
– where the defendant submitted that the
denial in the plaintiff’s pleadings was insufficient – where the
defendant’s
pleadings did not allege any facts to support the contention
– where the defendant submitted that r 166 of the Uniform Civil
Procedure Rules 1999 (Qld) had the effect that the insufficient reply
amounted to a deemed admission – whether the insufficient reply amounted
to
a deemed admission by the plaintiff of the defendant’s contention
District Court of Queensland Act 1967 (Qld), s
118(2)
Industrial Relations Act 1990 (Qld) Industrial Relations Act 1999 (Qld), s 136(2) Uniform Civil Procedure Rules 1999 (Qld), r 149(1)(b), r 149(1)(c), r 149(3)(a), r 157(a), r 166 ACI Operations Pty Ltd v Bawden [2002] QCA 286, cited Cohen & Co v Ockerby & Co Ltd (1917) 24 CLR 288; [1917] HCA 58, followed Gollin & Co Ltd v Karenlee Nominees Pty Ltd (1983) 153 CLR 455; [1983] HCA 38, cited Groves v Australian Liquor, Hospitality and Miscellaneous Workers’ Union & Anor [2004] QSC 142, cited Hughes v National Trustees, Executors and Agency Co of Australasia Ltd (1979) 143 CLR 134; [1979] HCA 2, cited Magburry Pty Ltd v Hafele Australia Pty Ltd (2001) 210 CLR 181; [2001] HCA 70, followed Pacific Carriers Ltd v BNP Paribas (2004) 218 CLR; [2004] HCA 35, followed R v Ping [2006] 2 Qd R 69; [2005] QCA 472, cited Suttor v Gundowda Pty Ltd (1950) 81 CLR 418; [1950] HCA 35, cited Toll (FGCT) Pty Ltd v Alphapharm Pty Ltd (2004) 219 CLR 165; [2004] HCA 52, followed Worchild v Petersen [2008] QCA 26, cited |
COUNSEL:
|
D R Kent, with A R Fitzsimons, for the
plaintiff/respondent/cross-applicant
N H Ferrett for the defendant/applicant/cross-respondent |
SOLICITORS:
|
Hall Payne Lawyers for the plaintiff/respondent/cross-applicant
Woods Prince Lawyers for the defendant/applicant/cross-respondent |
[1] McMURDO P: Both applications for leave to appeal should be refused with
costs for the reasons given by Fraser JA.
[2] FRASER JA: Logan Area Group
Apprenticeship/Traineeship Scheme Limited ("the plaintiff") obtained a judgement
in the Magistrates
Court against Arnold Electrical & Data Installations Pty
Ltd ("the defendant") for $12,834.53. The plaintiff's claim was made
under a
labour supply contract made in 1998 pursuant to which the plaintiff
“hired” electrical apprentices to the defendant
at an hourly rate
until late 2003.
[3] The defendant pleaded various defences and
counterclaimed $89,621.98 by way of restitution on the basis that the plaintiff
had
overcharged the defendant that amount during the currency of the contract.
The Magistrates Court dismissed the defendant’s
counterclaim with
costs.
[4] The District Court allowed an appeal by the defendant against the
plaintiff’s judgment but refused the defendant's appeal
against the
dismissal of its counterclaim.
[5] Each of the plaintiff and the defendant
now seek leave to appeal to this Court pursuant to s 118(3) of the District
Court of Queensland Act 1967 (Qld). The provision confers a general discretion
on this Court to grant or refuse leave to appeal which is exercisable according
to the nature of the case[1]. That discretion is
not circumscribed, but leave will usually be granted only where an appeal is
necessary to correct a substantial
injustice to the applicant and there is a
reasonable argument that there is an error to be
corrected.[2]
Plaintiff's
application
[6] The contract described the hourly rates to be charged by the
plaintiff (in the contract called "GTA") in the following terms:
"The hourly rate charged by GTA covers base pay, sick pay, annual leave (including 17.5%), gazetted holidays, TAFE block release, occupational superannuation, workers compensation insurance, award fares & travel if applicable to trade and includes the award tool allowance.
The hourly rate does not include site allowances, additional travel over standard award rate.
In case of wet days the first wet day will be charged at the normal charge out rate to your account, subsequent consecutive wet days provided the apprentice telephones the office before 8.30am will be paid by Group Training."
[7] The particular provision (which I will call the "change clause") pursuant to which the plaintiff's claim was made provided:
"If an award rate is changed and backdated whilst the apprentice/trainee is with you the amount will be charged to your account for the relevant period."
[8] The Magistrate found that when that contract was made there was a State
award pursuant to which the plaintiff paid its apprentices
and that the
plaintiff invoiced the defendant throughout the period of the contract with
reference to the rates set out in that award.
[9] It is now common ground
that, as the Magistrate found, on 26 May 2003 the provisions of that award,
insofar as they applied to
regulate the plaintiff's obligations to its employed
apprentices whilst they were employed at the defendant’s workplace, were
replaced by a certified agreement (also known as an “Enterprise Bargaining
Agreement” or “EBA”) entitled
"Arnold Electrical & Data
Installations Pty Ltd Certified Agreement 2003."
[10] Subsection 136(2) of
the Industrial Relations Act 1999 (Qld) had the effect that the plaintiff was
obliged to pay those apprentices
at the rates stated in the certified agreement
from 26 May 2003 until the termination of the contract between the plaintiff and
the
defendant in November 2003. When the plaintiff discovered in November 2003
that the certified agreement had been made some six months
earlier it made
additional payments to those of its apprentices who had worked at the
defendant’s workplace in that period
to make up the difference between the
award rates the plaintiff had paid them and the higher rates payable under the
certified agreement.
[11] The Magistrate decided that the plaintiff was
entitled to recover those additional costs to it pursuant to the change clause.
That decision was set aside in the District Court. The critical reasoning was
contained in the following paragraph of the primary
judge’s
reasons:
"As at 17 August 1991 payment of the apprentices the subject of the agreement was regulated by the State Award. No EBA [meaning "enterprise bargaining agreement", ie the Certified Agreement] was then in existence and there was no evidence to indicate that the term "award" was envisaged by the parties to encompass anything other than award rates. In particular there was nothing to indicate that any instrument, such as a Certified Agreement, was in any way within the contemplation of the parties. Clearly, in my view, the terms "EBA" and "award" cannot be regarded as being interchangeable. The basis of the hiring agreement in this case was that the appellant should be obliged to pay a share of the expenses associated with the particular apprentices determined according to the length of the period of hiring. In my view, on a proper construction of the agreement those charges are to be calculated in accordance with the relevant award and not in accordance with the subsequently introduced Certified Agreement. In my view, those matters which can properly be the subject of charge are those matters expressly provided for in the written agreement."[3]
[12] The plaintiff seeks leave to appeal to argue that the primary judge erred
in that construction of the parties' contract.
[13] The construction of the
contract is to be determined by what a reasonable person in the parties’
position would have understood
it to mean having regard to its text, the
surrounding circumstances known to them, and the purpose and object of the
transaction
it embodies.[4]
[14] Although the
text is ambiguous, on a literal construction it is not "the award" which is
required to be changed before the clause
operates but the "award rate"; and the
change clause does not require that the award rate be changed or backdated by
another award.
Literally construed, the change clause applies whenever the rate
specified in the award is increased by any mechanism (only increases
were
contemplated, at least in the express terms).
[15] The contrary view is open,
but the apparent aim of the change clause also suggests that it should not be
construed so narrowly
as to exclude reference to increases in labour costs
effected by any mechanism having the force of law. In a labour supply agreement
under which the supplier recovers from its customer essentially only the
supplier's labour costs it is to be expected that the parties
will provide for
increases to the rate of recovery commensurate with statutorily mandated
increases in those costs. Otherwise the
supplier will be out of pocket and the
“hirer” will receive an unmerited windfall.
[16] The surrounding
circumstances point in the same direction. The relevant background information
that may be used to inform the
proper construction of a contract includes not
only that which the parties subjectively knew but also that which was reasonably
available
to the parties in the situation in which they found themselves at the
time of the contract, including matters of
law.[5] The legislation current when the
contract was made, the Industrial Relations Act 1990 (Qld), gave the force of
law not only to "awards"
but also to "industrial
agreements".[6] The prospect of future
amendments to the industrial relations legislation must also have been within
the contemplation of a reasonable
person in the parties’ position. The
parties must be taken to have appreciated when the contract was made that awards
were
not the only means by which the effect of law might be given to future
increases in labour costs. In this case there was no evidence
contradicting
that expectation.
[17] I accept both that the construction I prefer creates
some tension with the contractual references to the “award”
and that
the construction propounded by the defendant (in effect, that the change clause
covers only labour cost increases reflected
in a new or amended award) is
certainly open on the text. Nevertheless, I would reject the defendant’s
construction for the
reasons I have given: it reads the contract in a "narrow
spirit of construction" of a kind long condemned by the
courts.[7] Numerous authorities establish that
the construction which is adopted must accord with commercial efficacy and
commonsense.[8] The manifest unreasonableness of
the defendant’s approach to which I have referred is emphasised by the
fact that the increases
in the plaintiff’s labour costs flowed from an
agreement to which the defendant was, but the plaintiff was not a party.
[18] In fairness to the primary judge it must be pointed out that in the
District Court, the appellant’s argument was the different
one that the
term “award” was broad enough to encompass a certified agreement.
It was that argument which the primary
judge was concerned to reject in the
passage quoted earlier. The argument which I regard as much more substantial is
that, on a
literal and purposive construction, the change clause is not confined
to changes to the award itself or changes made by a new award:
it comprehends
also increases in the plaintiff’s labour costs brought about by other
means that similarly have the force of
law, including by certified agreements.
[19] The point concerns only the proper construction of a written contract
and it was not submitted that this new argument might have
been met by
additional evidence. It follows that if leave to appeal were granted it might
fairly be contended that it would be “not
only competent but expedient, in
the interests of justice”[9] to entertain
the new argument.
[20] But it does not follow that the fact that the
argument relied upon in this Court is new is irrelevant. The plaintiff’s
failure to put this argument either to the Magistrate or in the District Court
is a factor opposed to the grant of leave.[10]
I would add that the parties’ failure to adduce evidence at trial
concerning the surrounding circumstances which I have mentioned
lessens the
significance of any decision in this litigation as a precedent concerning the
proper construction of this contract.
[21] That the amount in issue is
relatively small and the matter has already been litigated in two courts also
weigh against leave
being granted. Furthermore, the construction point was not
the only reason given by the primary judge for setting aside the plaintiff's
judgment. His Honour also found that the Magistrates Court erred in finding
that the plaintiff was entitled to be paid an “administrative
cost”
(that amount being included in the invoices with reference to which the
plaintiff’s claim was
calculated):[11]
"There is one further matter to consider, that being the finding by the Magistrate that the respondent was entitled to be paid an administrative cost. This finding seems to have been based upon a concession made by the witness Arnold during cross-examination.
In my view that concession represents no more than a statement of
opinion by the witness. As the High Court observed in Toll (FGCT) Pry Limited v Alphapharm Pry Limited and Ors [2004] HCA 52; (2004) 219 CLR 165 at 179 "(it) is not the subjective beliefs or understandings of the parties about their rights or liabilities that govern their contractual relations". The written agreement here makes express provision for those items which may be subject of permissible charge but these do not include any allowance for administration costs. The finding of the Magistrate in this regard cannot in my view be sustained."
[22] That the plaintiff included in its invoices an "administrative" charge of
25 cents per hour emerged in cross-examination of
the plaintiff’s
operational manager, Mr Taylor. The plaintiff's admission of the
defendant's pleaded allegation that the contract
entitled the plaintiff to
charge for the items expressly described in the contract, coupled with the
plaintiff’s failures to
plead facts supporting its argument that it was
also entitled to charge for "administration" and to give particulars of that
charge,
render it doubtful that the plaintiff was entitled to sustain this
charge on the pleadings upon which it went to
trial.[12] It is not clear that it was even
open to the plaintiff to argue, as it successfully did before the Magistrate,
that the contract
did not comprehensively identify the permissible charges so
that it was entitled to charge the administration fee.
[23] On that
construction question, the apparent status of the plaintiff as a non-profit
company acting within a governmental scheme
is a fact that might well prove to
be relevant to the proper construction of the contract. The Court was told of
that fact in general
terms during argument but no evidence was led about it at
trial. If leave to appeal were granted for the purpose of deciding that
question, this Court’s decision would therefore not necessarily govern any
future cases on the same form of contract.
[24] If, as the primary judge
concluded, the charge was unsustainable, the amount of the plaintiff’s
claim (if otherwise successful)
theoretically might be sustained in a reduced
amount, but the overall financial impact of the charge appears not to have been
quantified
either by the pleadings or by the evidence. Whether that exercise
could now be done with reference to the evidence led at trial
was not made
clear; whether it would be appropriate to proceed in that way despite the
deficiencies in the pleadings is doubtful.
What is clear is that deduction of
the charge would further reduce the already small amount in issue in the
proposed appeal.
[25] It also emerged in argument that the plaintiff's claim
under the change clause was premised on the view that the apprentices
were doing
"construction" work in terms of Schedule B of the certified agreement and not
"services" in terms of Schedule C of that
agreement. (Much the same issue arose
on the counterclaim in the context of an apparently similar division in the
former award:
I return to this below.) The rate for "other construction work"
was higher than it was for "service work". The evidence on behalf
of the
plaintiff was that it used the charge out rate for "other construction work"
because the majority of its apprentices were
doing construction work.
[26] It may well be that the plaintiff was correct in charging in that way
but the evidence before the Magistrate on the point was
quite unclear. This
issue was not raised by the pleadings. The plaintiff did not plead any material
facts in support of its claim
(exposed during cross-examination) to recover this
cost.
[27] There are therefore a number of factors opposed to the grant of
leave, but the plaintiff contends that the decision of the District
Court,
particularly that aspect of it concerning the construction of the change clause,
sets an important precedent because this
contract was in its standard form. Its
counsel stated from the bar table (without objection) that there might still be
a very large
number of such contracts still in force. That is open to serious
doubt, as the plaintiff’s counsel properly recognised, because
no other
claim has been made against the plaintiff even though it wrote a form letter to
all of its “customers” in late
2003 seeking to impose a new form of
contract. Furthermore, for the reasons I have given the District Court decision
should not
be regarded as having the effect as a precedent which the plaintiff
feared.
[28] For these reasons, although in my respectful opinion the
primary judge’s construction of the change clause in the contract
was
wrong (for reasons not agitated in argument before his Honour), I am not
persuaded either that there is a substantial argument
that the actual decision
to set aside the judgment in the plaintiff’s favour was incorrect or that
an appeal is necessary to
correct any substantial injustice. I would therefore
refuse the plaintiff's application for leave to appeal.
Defendant's
application
[29] The defendant's counterclaim was premised on its contention
that the plaintiff had calculated its invoices with reference to
the
"construction” rate in the former award when the plaintiff should have
only charged the lesser "service rate" under that
award. The Magistrate
dismissed the counterclaim because he was not persuaded that the evidence showed
that the apprentices should
have been paid at the lesser rate and because of his
Honour’s conclusion that for the period after commencement of the
certified
agreement the award did not apply.
[30] The primary judge refused
the defendant's appeal against the dismissal of its counterclaim. His Honour
concluded:
"Although there was some generalised evidence before the court as to the type of work done by the appellant company, there was no detailed evidence as to precisely what sort of work was carried out by the apprentices or as to what proportion of their work could properly be described as construction as opposed to service work. The state of the evidence was such in my view that the Magistrate's finding that he was unable to determine which of the service or construction rates should have been charged was one which was reasonably open to him."[13]
[31] In my respectful opinion his Honour’s decision was correct for those
reasons.
[32] On behalf of the defendant it was submitted that the necessary
evidence was supplied by Mr Arnold, who swore that it was the
service rate that
"applied" to the work that his company was doing. It was submitted that he had
an extensive knowledge of and expertise
in the industry. So much may be
accepted but the difficulty remains that only the vaguest description of the
work done by the apprentices
was given. It was described as "generally
commercial, electrical and data installations". Even the award itself was not
in evidence.
[33] It is far from being clear that there was any question
upon which expert evidence of the character relied upon by the defendant
was
admissible. But if this was a proper subject for expert evidence Mr
Arnold’s evidence was of no value because the facts
upon which it was
premised were not identified. No matter what qualifications are possessed by an
expert witness, opinion evidence
lacks probative value if the facts upon which
it is based are not both identified and proved or
admitted.[14]
[34] Contrary to another
submission made on behalf of the defendant, the admission at trial without
objection of the defendant’s
four volumes of analyses of the
plaintiff’s invoices prepared on the premise reflected by Mr
Arnold’s evidence did not
provide the missing evidence of the underlying
facts. It was not submitted that these volumes of material contained any
information
about the precise nature of the work done by the apprentices or as
to the precise terms of the award. The submission is also not
easy to reconcile
with the conduct of the defendant’s counsel in making it plain when he
tendered those documents that it was
proposed to prove them by
Mr
Arnold’s evidence. As I have already indicated, it transpired that Mr
Arnold’s evidence did not prove the facts necessary
to support the
counterclaim. In those circumstances, the documentary evidence is not to be
treated as having probative effect it
otherwise lacked merely because of the
absence of objection to its tender.[15]
[35] The defendant’s counsel sought to overcome this difficulty by
arguing that the defendant was entitled to rely upon a deemed
admission under
UCPR r 166 that the service rate was the correct rate. It was contended that
the plaintiff’s pleaded explanation
for its denial of the
defendant’s allegation that it overpaid the plaintiff (that it was not
true) was insufficient.[16] These submissions
must be rejected. The rule is concerned with allegations of facts in pleadings.
The allegation of an overpayment
asserted a conclusion based on various matters
that were not pleaded. The defendant’s counterclaim did not allege any of
the
facts (as to the nature of the work done by the apprentices and the terms of
the award) required to support the conclusion (which
was also not pleaded) that
the service rate was applicable. Rule 166 cannot be called in aid of a
claimant who fails to plead or
prove the material facts required to support the
claim.
[36] There is another reason why this pleading point is an
inappropriate basis for the grant of leave to appeal. The defendant’s
counsel did not take the point when he tendered the documentary evidence and
undertook to prove it through the witness at the trial.
That conduct was wholly
inconsistent with his proposition, not made until final submissions at the
trial, that the fact of the overpayment
was not in issue.
[37] Further, in
light of my conclusion that the proper construction of the contract permitted
the plaintiff to charge at the rates
expressed in the certified agreement, the
defendant's counterclaim also suffers from the fatal deficiency that it was
calculated
with respect to the different award rates.
[38] In my opinion the
defendant has failed to advance any reasonable argument that the primary judge
erred in dismissing the defendant's
appeal from the decision of the Magistrate.
I would therefore refuse the defendant’s application for leave to
appeal.
[39] I would order that the applications for leave to appeal by both
parties be dismissed, in each case with costs to be assessed
on the standard
basis.
[40] LYONS J: I have had the advantage of reading the reasons of
Fraser JA. I agree with his Honour’s reasons and with the
orders
proposed.
[1] ACI Operations P/L v Bawden [2002] QCA 286.
[2] Worchild v
Petersen [2008] QCA 26; Monte Carlo Caravan Park P/L v Curyer [2006]
QCA 363; [2007] 2 Qd R 57; Pickering v MacArthur [2005] QCA 294;
Rigney v Littlehales [2005] QCA 252; Pugin v WorkCover Queensland
[2005] QCA 66 at [15]; [2005] QCA 66; [2005] 2 Qd R 37 at 40;
Labaj v Brown
[2005] QCA 54.
[3] Arnold Electrical & Data Installations P/L v Logan Area Group Apprenticeship/Traineeship Scheme Limited [2007] QDC at [6].
[4]
Pacific Carriers Ltd v BNP Paribas [2004] HCA 35; (2004) 218 CLR 451 at [22]; [2004]
HCA 35;
Toll(FGCT) P/L v Alphapharm P/L [2004] HCA 52; (2004) 219 CLR 165 at [40];
[2004] HCA 52.
[5] Maggbury P/L v Hafele Australia P/L [2001] HCA 70; (2001) 210 CLR 181 at [11] per Gleeson CJ, Gummow and Hayne JJ; [2001] HCA 70.
[6] Industrial Relations Act 1990 (Qld), Pt 10, Div 1 (Awards), Div II (Industrial Agreements).
[7]
Cohen & Co v Ockerby & Co (1917) 24 CLR 288 at 300 per Isaacs J;
[1917] HCA 58; see also, for example, Upper Hunter County District v
Australian Chilling & Freezing Co Ltd
[1968] HCA 8; (1968) 118 CLR 429 at
437; [1968] HCA 8.
[8] See, for
example, Gollin & Co Ltd v Karenlee Nominees P/L [1983] HCA 38; (1983) 153 CLR 455
at 463;
[1983] HCA 38; McCann v Switzerland Insurance Australia Ltd
[2000] HCA 65; (2000) 203 CLR 579 at [22];
[2000] HCA 65.
[9]
Connecticut Fire Insurance Co v Kavanagh [1892] AC 473 at 480, quoted
with approval in
Suttor v Gundowda P/L [1950] HCA 35; (1950) 81 CLR 418 by Latham
CJ, Williams and Fullagar JJ at 438;
[1950] HCA 35; and, in a different
context, in Crampton v R [2000] HCA 60; (2000) 206 CLR 161 by Gleeson CJ at [12] and by
Gaudron, Gummow and Callinan JJ at [50]; [2000] HCA
60.
[10]
Cf Monte Carlo Caravan Park P/L v Curyer [2006] QCA 363; [2007] 2 Qd R 57 at [21] per
Keane JA (Jerrard and
Holmes JJA agreeing); [2006] QCA
363.
[11]
Arnold Electrical & Data Installations P/L v Logan Area Group
Apprenticeship/Traineeship
Scheme Limited [2007] QDC at [9].
[12] Cf Uniform Civil Procedure Rules 1999 (Qld), rr 149(1)(b), 149(1)(c), 149(3)(a), 157(a).
[13] Arnold Electrical & Data Installations P/L v Logan Area Group Apprenticeship/Traineeship Scheme Limited [2007] QDC at [8].
[14] R v Ping [2005] QCA 472; [2006] 2 Qd R 69 at [43]- [46]; [2005] QCA 472.
[15] Cf Hughes v National Trustees, Executors and Agency Co of Australasia Ltd [1979] HCA 2; (1979) 143 CLR 134 at 153; [1979] HCA 2.
[16] Cf Groves v Australian Liquor, Hospitality and Miscellaneous Workers’ Union [2004] QSC 142 at [15]
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/qld/QCA/2008/100.html