Home
| Databases
| WorldLII
| Search
| Feedback
County Court of Victoria |
Last Updated: 29 June 2012
AT
MELBOURNE
CIVIL
DIVISION
COMMERCIAL LIST
EXPEDITED DIVISION
|
|
v
|
|
|
|
|
|
and
|
|
|
|
DEER PARK PROPERTY PTY LTD
(ACN 131 137 347) |
Third Party
|
|
|
and
|
|
|
|
MERIDIAN CONCRETE AUSTRALIA PTY LTD
(ACN 128 225 098) |
Fourth Party
|
---
JUDGE:
|
||
WHERE HELD:
|
||
DATE OF HEARING:
|
||
DATE OF RULING:
|
||
CASE MAY BE CITED AS:
|
||
|
Costs – plaintiff unsuccessful- Calderbank offers – indemnity costs - proceedings between third party and fourth party - defendant connected with third party - whether defendant should pay the fourth party’s costs
---
APPEARANCES:
|
Counsel
|
Solicitors
|
For the Plaintiff
|
Vadarlis & Associates / Law 554
|
|
|
|
|
For the Defendant and Third Party
|
B2B Lawyers
|
|
|
|
|
For the Fourth Party
|
Mr A Laird
|
Herbert Geer
|
1 On 15 December 2011, I delivered judgment in this proceeding and stated that I would make orders that:
(a) the proceeding by Carpenters Motorcraft Pty Ltd (“Carpenters Motorcraft”) against Novalane Pty Ltd (“Novalane”) be dismissed;
(b) that there be judgment for Novalane against Carpenters Motorcraft in respect of the amount of Novalane’s counterclaim save for Items 9, 10, 13 and 17;
(c) the third party claim by Novalane against Deer Park Property Pty Ltd (“Deer Park Property ”) be dismissed; and
(d) the third party claim by Deer Park Property against Meridian Concrete Australia Pty Ltd (“Meridian”) be dismissed.
2 On 20 December 2011, I heard argument about, and reserved my decision on,
costs. These reasons determining the costs issues should
be read with the
judgment delivered on 15 December 2011.
3 No order for costs was sought by
the third party Deer Park Property against Novalane.
4 Novalane sought
judgment on its counterclaim in accordance with the judgment of 15 December 2011
in the sum of $90,763.20 plus interest
as from 20 April 2009. The calculation
of this sum of $90,763.20 was not disputed by Carpenters Motorcraft and I will
make an order
to that effect.
Costs Between Carpenters and Novalane
5 Novalane sought an order against Carpenters Motorcraft that it should pay
Novalane’s costs of the proceeding including reserved
costs. These costs
were claimed from the date of commencement of the proceeding to 4 November 2010
on Scale D and on an indemnity
basis from 5 November 2010 on, because of the non
acceptance of a Calderbank offer made by Novalane.
6 Novalane argued that
it had been wholly successful in defending Carpenter Motorcraft’s
proceeding against it and largely successful
on its counterclaim against
Carpenters Motorcraft.
7 I accept that Scale D is the appropriate scale of
costs because of the amount of the claim and the complexity of the proceeding.
This proceeding was conducted before the changes to the Court’s scale of
costs took effect on 1 September 2011.
8 The Calderbank offer was sent by
Novalane’s solicitors to Carpenter Motorcraft’s solicitor in a
letter dated 5 November
2010. The letter set out a number of reasons why it was
contended that the plaintiff’s claim was without merit.
9 Some of those
reasons were accepted in the judgment of 15 December 2011. They included that
the Agreement to Lease did not impose
any obligations on Novalane itself to
construct the floor surface at the Deer Park premises. The Calderbank letter
also addressed
the counterclaim and argued that the plaintiff’s defence to
the counterclaim was without merit.
10 The settlement offer was as
follows:
“Notwithstanding the matters set out above, the defendant offers to settle the claim and the counterclaim, without admission of liability, as follows:
(1) The claim and counterclaim be dismissed.
(2) Each party bear their own costs.
(3) The defendant will, as soon as practical but subject to (4) below, procure (at no cost to the plaintiff) the repairs to the floor surface in the spare parts/workshop area that are specified in the joint expert report dated 30 June 2010. We enclose a copy of that report for your reference with the proposed repairs underlined.
(4) Such repairs to occur outside the normal operating hours of the plaintiff’s business.
(5) The parties otherwise release each other from all claims the subject of the claim and the counterclaim, including interest and costs.”
11 The offer was expressed to be made without prejudice save as to costs and in
accordance with the principles enunciated in Calderbank
v
Calderbank[1]. It was foreshadowed that if the
offer was not accepted and the claim and counterclaim were determined so that
the outcome was no
more favourable to the plaintiff than the terms of this
offer, the defendant would tender the letters in support of an application
that
Carpenters Motorcraft pay Novalane’s costs of the proceeding be paid on an
indemnity basis from the date of the letter.
12 The offer was open for
acceptance until 4.00 pm Friday, 12 November 2010.
13 The offer was made
twelve days before the trial was then scheduled to commence, at which point
pleadings were closed, discovery
had been completed, experts’ reports and
a joint report of experts had been provided, mediation had occurred, a judicial
settlement
conference had occurred and the trial was scheduled to commence on 15
November 2010, although that date was subsequently vacated.
The offer contained
a discussion of the merits of the proceeding.
14 The defendant also sought
certification of counsel’s fees as set out in counsel’s fees slips
in the sum of $82,820,
in accordance with the practice adopted by the Court in
Birek Industries Pty Ltd v McKenzie Group Consulting (Vic) Pty
Ltd[2].
15 Counsel for the defendant
referred to the recent decision of J Forrest J in Ultra Thoroughbred Racing Pty
Ltd t/as Baree Stud v
Those Certain Underwriters at Lloyd’s
London[3] and the decision of the Court of Appeal
in Commissioner of State Revenue v Challenger Listed Investments Ltd
(No.2),[4] which in turn had considered the
decision in Hazeldene’s Chicken Farm Pty Ltd v Victorian Workcover
Authority (No.2).[5]
16 In the
Hazeldene’s Chicken Farm Case the Court of Appeal listed a range of
considerations to take into account in determining
whether a rejection of a
Calderbank offer was unreasonable. These included: the stage of the proceeding
at which the offer was received;
the time allowed to the offeree to consider the
offer; the extent of the compromise; the offeree’s prospects of success
assessed
as at the date of the offer; the clarity with which the terms of the
offer were expressed and whether the offer foreshadowed an application
for
indemnity costs in the event of the offeree rejecting it.
17 Counsel for
Carpenters Motorcraft submitted that I should not apply hindsight, but apply a
consideration of the matters that prevailed
at the time the offer was made.
Counsel referred in particular to that part of the Calderbank offer which said
that:
“The defendant will, as soon as practicable but subject to (4) below, procure (at no cost to the plaintiff) the repairs to the floor surface in the spare parts/workshop area that are specified in the joint expert report dated 30 June 2010. We enclose a copy of that report for your reference with the proposed repairs underlined.”
18 Counsel for the plaintiff accepted that the offer did represent a
contribution towards settlement because it involved the giving
up of the
counterclaim in the sum of $96,000, but submitted that the real issue was
whether the offer was an offer with certainty
to make the Deer Park floor
equivalent to the floor at Etheridge Ford.
19 Counsel pointed out the first
part of the offer was in effect to undertake the site trial carried out on a
delaminated area with
a saw cut of 1 x 1 metre and 40 millimetres deep as the
minimum depth and dimensions, all dimensions to be decided on site. Aitken
Freeman, who was the supplier of the Floor Roc S product, was to advise on the
patch repair materials for the three trial areas.
20 Page 5 of the
attachment to the Calderbank offer, which described the offer for work was
headed “Further Proposals from Kevin Campbell
for Consideration following
Conference at County Court”. It then proposed that Mr Campbell produce a
specification based
on a number of concepts. These included eliminating the
eight patch repairs at the centre driveway of the workshop. The second
concept
was that the drummy areas were to be repaired by epoxy injection with surface
mounted connections. The holes in the surface
were to be 6 mms or
less.
21 Novalane submitted that it was offering to do $62,000 worth of
work.
22 Counsel for Carpenters Motorcraft contended that at the time this
offer was made, the trial repair had not been conducted. There
was no colour
matching that was proposed and there was no indication as to whether the current
colour matching could be achieved.
23 Counsel contended that the lack of
certainty created by this offer was relevant to the determination of whether
Carpenters Motorcraft
had acted reasonably in rejecting the offer. The real
issue was whether the offer was an offer with certainty about the steps being
taken to achieve a floor equivalent to that at Etheridge Ford.
24 Novalane
disputed these submissions and contended that the Court should award indemnity
costs from the date of the Calderbank offer.
25 I consider that it was
unreasonable for Carpenters Motorcraft to reject the offer. A broad view of
the offer has to be considered.
Novalane offered to agree to the proceeding
being dismissed without seeking costs and agreed to relinquish its counterclaim.
Novalane
has succeeded in recovering a substantial proportion of that
counterclaim. The offer also involved a proposal for further work to
be carried
out on the Deer Park floor to eliminate defects.
26 I have determined that
the Carpenters Motorcraft had no contractual right to sue Novalane for a
failure to construct a floor,
the equivalent of the Etheridge Ford floor.
27 Taking the matters as a whole and after considering the matters mentioned
in the Hazeldene’s Chicken Farm Case, I consider
that at the time the
offer was made it was unreasonable for Carpenters Motorcraft to reject it. It
provided an outcome substantially
superior to that that Carpenters Motorcraft
has achieved. It was made at a point in the proceeding when Carpenters
Motorcraft was
in a position to assess it. A reasonable time was given for its
acceptance. Novalane warned that it would seek indemnity costs.
The fact that
there was uncertainty as to the effect of the further work that was to be
performed does not detract from the other
elements of the offer to which I have
referred.
28 In all the circumstances, I consider that an appropriate order
is that the plaintiff pay the defendant’s costs, including
any reserved
costs, on a party/party basis on Scale D until 5 November 2010 and thereafter on
an indemnity basis.
29 I do not consider that I should certify for the
amount of preparation to be allowed to counsel. I consider that that is now a
matter for the Costs Court. I am not in a position to assess an appropriate
amount of preparation. I do not have the detail necessary
to carry out that
task. I take a similar view in respect of appearances other than at trial. I
will, however, certify for Novalane’s
counsel’s daily trial fees and
preparation rate at the rates proposed by Novalane, which were $4000 per day for
each trial
day and $380 per hour until 20 November 2010 and thereafter $400 per
hour for preparation. I consider those rates reasonable in
view of the nature
of the proceeding and the issues raised in it.
Costs Between Deer Park Property and Meridian
30 I indicated that I would order that the fourth party claim brought by Deer
Park Property against Meridian be dismissed.
31 In Kheirs Financial
Services Pty Ltd v Aussie Home Loans Pty Ltd[6],
the Court of Appeal identified the following principles as applicable to the
costs where a plaintiff had failed and claims by the
defendant against third and
fourth parties had also failed:
“(1) The usual rule as to costs applies to proceedings as between defendant and third party, the “event” being the success or failure of the defendant’s claim against the third party.
(2) Where the third party claim is dismissed because the plaintiff’s claim against the defendant fails, the defendant will ordinarily be liable for the third party’s costs of the third party proceeding.
(3) The award of costs remains a matter of discretion, however, and there may be circumstances of the case which justify a departure from the usual rule.
(4) In deciding (in a case of the kind referred to in (2)) whether any departure from the usual rule is warranted, the court will ordinarily need to consider at least the following matters:
• the reasonableness of the defendant’s decision to join the third party;
• whether the joinder of the third party was reasonably foreseeable by the plaintiff, such that the plaintiff might be viewed as having some responsibility for the costs of the third party proceeding. (An order for the plaintiff to pay the defendant’s costs may thus include the defendant’s liability to pay the third party’s costs of the third party proceeding.);
• the responsibility of plaintiff, defendant and third party, respectively, for the time taken up in the hearing of the third party proceeding.
These principles would apply equally to fourth party proceedings.”
32 Deer Park Property submitted that in the principal judgment I had made
findings that the floor constructed by Meridian was defective
and that the cost
of repair to produce a result that most closely approximated compliance with the
sub-contract according to the
fourth party’s own expert was $262,380.94.
Deer Park Property submitted that I had overlooked making a determination of
paragraphs
17 and 18 of its Amended Statement of Claim against Meridian dated 6
July 2010, in which damages for breach of the sub-contract were
sought. It
argued that this omission could not be rectified by the Court and the third
party needed to pursue its claims on appeal.
33 Deer Park Property submitted
that the appropriate order was that the question of costs as between it and
Meridian be reserved pending
the outcome of appeals; or alternatively that there
be no order as to costs. Any other result would be unjust. It was also
submitted
that I should grant leave to appeal.
34 I do not consider that I
should grant leave to appeal but, rather, that if leave is required, any such
application should be determined
by the Court of Appeal.
35 Meridian argued
that in the first instance it was entitled to an order that Deer Park Property
pay its costs of the proceeding
on the appropriate County Court scale. In
addition Meridian relied on a Calderbank offer of 16 August 2010 to argue for an
order
that its costs after 16 August 2010 be paid on an indemnity basis.
36 On 16 August 2010, Meridian made a Calderbank offer to Deer Park Property
in which it offered to pay the sum of $92,000. The offer
explained why the
proceeding appeared to be headed towards a lengthy and expensive trial and why
the offer was under all the circumstances
very reasonable. Meridian has
achieved a much more favourable outcome than the terms of the Calderbank offer.
It was unreasonable
for Deer Park Property not to have accepted the offer in
view of the particular circumstances of the case.
37 Meridian’s offer
was as stated, that it would pay Deer Park Property the sum of $92,000 inclusive
of costs, interest and
taxes, in full and final settlement within fourteen days
of acceptance of the offer. The offer was made on 16 August 2010 and it
was
open for acceptance until 27 August 2010. In return for the offer, Meridian
required a full release and discharge and full indemnity
in relation to any
claim that Carpenters Motorcraft and/or Novalane may purport to bring against it
in relation to the work. Upon
acceptance of the offer, Deer Park Property and
Meridian agreed to the claim by Deer Park Property against Meridian being struck
out with the right of reinstatement. Meridian reserved its right to seek
indemnity costs if the offer was not accepted.
38 Deer Park Property argued
that the offer of $92,000 was much less than the cost to repair the floor of
$262,380.94. It submitted
that as an offer inclusive of costs, the actual value
of the rectification work it represented was uncertain.
39 Deer Park
Property also argued that the offer imposed the condition that it fully
indemnify Meridian for any claim which Carpenters
Motorcraft might bring
against it in relation to the works. That condition was unreasonable and beyond
the judgment that might
have been obtained in the proceedings. If Deer Park
Property accepted the offer, it would have exposed itself to unknown unlimited
liability for any claim that Carpenters Motorcraft may any time in the future
bring against Meridian in relation to the works. The
indemnity extended beyond
defects alleged in the proceeding to claim in relation to the works.
40 I
accept Deer Park Property’s submissions. I take into account particularly
Meridian’s demand for the indemnity.
That demand is relevant to
determining the extent of the compromise offered and the prospect of Meridian
achieving what it required
to settle. I do not consider it was unreasonable for
Deer Park Property to refuse the Calderbank offer. The offer involved a
requirement
that Deer Park Property agree to an indemnity that Meridian was
unlikely to have achieved from the proceeding. It was a wide indemnity
and may
have exposed Meridian to liability far greater than its liability in the fourth
party proceeding.
41 However Deer Park Property’s fourth party
proceeding against Meridian has not succeeded. It is appropriate that Deer
Park
Property should pay Meridian its costs of the proceedings on a party/party
basis to be taxed on Scale D in default of agreement.
I do not consider that I
should depart from that usual rule by attempting to predict Deer Park
Property’s prospects on any
appeal that it may bring.
42 I again
apply the approach to certification of counsel’s fees that I indicated in
respect of Novalane’s costs. I certify
for the fees for Meridian’s
counsel at the rates sought, which I consider are reasonable. They are $3950
for each day of
the trial and a rate of $395 per hour for each hour of
preparation allowed by the Costs Court. Both fees are inclusive of GST.
The
amount of preparation allowed is properly determined by the Costs Court. I
again leave for the Costs Court to determine the
appropriate fee for counsel for
appearances in the proceeding other than at trial.
Costs between Novalane and Meridian
43 Meridian argued that the third and fourth party proceedings were clearly
structured in a manner that sought to use Deer Park Property
as a conduit in an
attempt to pass off any potential liability that Novalane had to Carpenters
Motorcraft onto Meridian. There
were common directors between the two
companies. If Deer Park Property was ultimately unable to satisfy what was
likely to be a
large costs order in favour of Meridian, it would unfair in view
of the particular circumstances of the case if Novalane could simply
wash its
hands of the matter.
44 I was referred to no authority for that
proposition. While the determination of costs is always in the discretion of
the court,
I do not consider that there should be any costs order in favour of
Meridian against Novalane. I do not propose to make such an
order.
45 Accordingly, the orders I will make are:
(1) The proceeding by Carpenters Motorcraft Pty Ltd against Novalane Pty Ltd is dismissed.
(2) That there be judgment for Novalane Pty Ltd on its counterclaim against Carpenters Motorcraft Pty Ltd in the sum of $90,763.20,plus interest.
(3) Novalane Pty Ltd pay Carpenters Motorcraft Pty Ltd’s costs of the proceeding, including any reserved costs, on a party/party basis to be taxed on Scale D in default of agreement until 5 November 2010 and thereafter on an indemnity basis. Certificates granted for counsel for Novalane for each day of trial at a daily rate of $4000. All fees for other appearances are to be determined by the Costs Court in default of agreement. Certificates granted for counsel for Novalane’s preparation at the rate of $ 380 per hour until 20 November 2010 and thereafter at the rate of $400 per hour. The amount of counsel’s preparation to be allowed is to be determined by the Costs Court in default of agreement.
(4) The third party claim by Novalane Pty Ltd against Deer Park Property Pty Ltd is dismissed with no order as to costs.
(5) The fourth party claim by Deer Park Property Pty Ltd against Meridian Concrete Australia Pty Ltd is dismissed.
(6) Deer Park Property Pty Ltd pay the costs of Meridian Concrete Australia Pty Ltd, including any reserved costs, on a party/party basis to be taxed on Scale D in default of agreement. Certificates granted for counsel for Meridian Concrete Australia Pty Ltd for each day of trial at the rate of $3,950 per day. All fees for other appearances are to be determined by the Costs Court in default of agreement. Certificates granted for counsel for Meridian Concrete Australia Pty Ltd’s preparation at the rate of $395 per hour. The amount of counsel’s preparation to be allowed is to be determined by the Costs Court in default of agreement.
(7) All fees certified for counsel are inclusive of GST.
- - -
[5] (2005) 13 VR 435
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/vic/VCC/2012/352.html