You are here:
AustLII >>
Databases >>
County Court of Victoria >>
2023 >>
[2023] VCC 655
[Database Search]
[Name Search]
[Recent Decisions]
[Noteup]
[Download]
[Context] [No Context] [Help]
Owners Corporation & Ors v Shangri-La Construction & Anor (No 2) [2023] VCC 655 (28 April 2023)
Last Updated: 4 May 2023
IN THE COUNTY COURT
OF VICTORIAAT
MELBOURNECOMMERCIAL
DIVISION
|
Revised Not Restricted Suitable for Publication
|
BUILDING CASES
LIST
Case No. CI-22-05416
Owners Corporation 1 Plan
No. PS707553K and Ors
|
|
|
|
|
|
|
|
Shangri-La Construction Pty Ltd and Anor
|
|
|
|
|
|
---
JUDGE:
|
HIS HONOUR JUDGE ANDERSON
|
WHERE HELD:
|
|
DATE OF HEARING:
|
|
|
|
CASE MAY BE CITED AS:
|
Owners Corporation & Ors v Shangri-La
Construction & Anor (No 2)
|
|
[2023] VCC 655
|
|
REASONS FOR
JUDGMENT
---
Catchwords: Practice and procedure - Defendant’s application to adjourn
trial – Delays by defendant not satisfactorily
explained – Whether
trial should await issue of third party proceedings – No adequate draft
third party claims produced.
Charter of Human Rights - Application to refer question to the Court of
Appeal – s33 Charter of Human Rights and Responsibilities Act 2006
(Vic) – Question hypothetical and premature – Preferable for the
referring court to first find facts and make a determination
- De Simone v.
Bevnol Constructions and Developments Pty Ltd [2010] VSCA 231 applied.
---
APPEARANCES:
|
Counsel
|
Solicitors
|
|
Mr N Pane KC and Mr R Chaile of Counsel
|
Corrs Chambers Westgarth
|
|
|
|
|
Dr M Wolff
|
Prior Law
|
HIS HONOUR:
- Shangri-La
Construction Pty Ltd (“Shangri-La”) was the builder of an apartment
block in Caulfield that was completed in
2015. The apartments were sold by the
developer. Later, it was found that the apartments had been constructed with
flammable external
cladding. This led to the present litigation, commenced in
VCAT in 2019 and that was referred to the Court by order of to the Tribunal
made
on 15 December 2022.
- The
trial of the proceeding was fixed for March 2023 and this date was later
extended, at the request of the parties, to 17 April
2023. After many years of
interlocutory proceedings both in the Tribunal and the Court, the trial was to
involve:
- claims
by the owners corporation and individual apartment owners against Shangri-La for
the cost of rectifying defects (other than
the combustible cladding);
- claims
by the State of Victoria against Shangri-La and its sole director, Obaid
Naqebullah, for the cost of replacing the combustible
cladding.
- On
31 March 2023, Shangri-La went into voluntary liquidation. As a consequence, the
claims against Shangri-La could not proceed without
the leave of a superior
court.
- On
11 April 2023, Mr Naqebullah issued a summons seeking orders that the trial
“be adjourned sine die, or in the alternative, to a date not before
1 November 2023”.
- On
20 April 2023, Mr Naqebullah gave notice that he “intends to make an
application for referral of a question of law in this
proceeding to the Court of
Appeal pursuant to section 33 of the Charter of Human Rights and
Responsibilities Act 2006 (Vic)”.
Application for
referral of question to the Court of Appeal
- At
the hearing on 21 April 2023, after hearing argument on the referral issue, I
determined that the application for referral should
be refused. I now give
reasons for my decision.
- The
“question” for referral was “whether section 137F of the
Building Act 1993 (Vic) (Building Act) as applied and to be
applied in this proceeding violates sections 8, 20 and 24 of the Charter of
Human Rights and Responsibilities”.
- The
notice of the application for referral stated that, “Section 137F
discriminates without proper basis between people who were officers at relevant
times of an entity engaged in the installation or
use of non-compliant or
non-conforming external wall cladding product on one hand, and others on the
other hand, including:
- Persons
or officers of entities producing non-compliant or non-conforming external wall
cladding products;
- Persons
or officers of entities distributing non-compliant or non-conforming external
wall cladding products;
- Persons
in a position of authority of an entity engaged in the installation or use of
non-compliant or non-conforming external wall
cladding products that are not
officers;
- Officers
of entities producing, distributing, installing, or otherwise commercially
dealing with other potentially dangerous building
materials.
Finally, section 137F of the Building Act
does not state explicitly that it has retrospective, not retroactive,
application”.
- In
De Simone v. Bevnol Constructions and Developments Pty Ltd [2010] VSCA
231, the Court of Appeal discussed the matters which should be taken into
account by a referring court or tribunal in its consideration
under s33(1)(b) of
the Charter as to whether “the question is appropriate for
determination”, in this case, by the Court of Appeal.
- The
matters, to which the Court of Appeal referred, included:
- “the
[referring] court ... has an overriding discretion whether to refer the
question” [at 35];
- the
discretion is “unfettered” although “it is to be exercised in
light of the relevant facts and circumstances
including such considerations as
may be contained in and drawn from the Charter” [at 35];
- the
“nature and scope of the question and the circumstances in which it arose
for consideration” should be taken into
account [at 37];
- whether
the court should, before referral, make a “judgment on the issues arising
for determination” before the court
so that the question for referral
might be “conditioned on any facts found or assessed or conclusions of law
reached by a primary
judge” [at 38 and 40];
- to
avoid a reference that involves a referred question of an “abstract
nature” [34], a question that is “raised
in the air” [37] or
where the question “bypasses any facts and asks a purely hypothetical
question” [40].
- In
my view, the question proposed for referral by Mr Naqebullah is inappropriate,
not simply because its wording might be “improved”,
as counsel
suggested, but because it offends the principles the Court of Appeal has
determined are to be considered.
- I
have refused the application primarily for the following reasons:
- the
notice was given prematurely, without a determination of the adjournment
application and upon the assumption that Mr Naqebullah’s
application for
an adjournment of the trial would be refused;
- the
notice was based on issues not presently before the Court. The Charter issues
were first raised in Mr Naqebullah’s affidavit
sworn 11 April 2023 and
only formalised in a draft Proposed Amended Defence filed on 20 April 2023, in
respect of which no leave
to deliver had been given;
- whilst
the determination of the question of whether s137F of the Building Act has
retrospective operation might, if decided in the negative, be a successful
defence for Mr Naqebullah to the State of Victoria’s
claim and other
potential claims involving Shangri-La, the question is primarily one of
statutory construction that is unlikely to
be assisted by reference to the
Charter provisions;
- the
issues relating to Mr Naqebullah’s position as the sole director of
Shangri-La and the defence of lack of “knowledge
or consent”
provided by s137F(4) of the Building Act, are issues that, whilst they may
depend on the relevant construction of the sub-section, will primarily depend on
evidence and findings
of fact;
- Mr
Naqebullah has not presently filed a witness statement on matters relating to
the claim against him, as he was required to do by
14 March 2023. Further, his
counsel anticipates that Mr Naqebullah may wish to lead expert evidence on the
issue of what a “reasonable
person in the position of Mr Naqebullah”
should have known in 2014 when decisions were made about the appropriate
cladding
to be used on the project;
- the
evidence given and the findings of fact by the referring court on these matters
would be a desirable, and no doubt a necessary,
pre-condition to any
determination by the Court of Appeal. An adequate agreed statement of facts
could not satisfactorily be prepared
in advance of a
trial.
Adjournment of the trial
- The
application by Mr Naqebullah was made by summons dated 11 April 2023 supported
by an affidavit of Mr Naqebullah and extensive
written submissions by his
counsel, Dr Wolff. In correspondence, the solicitors for the State of Victoria
highlighted what were alleged
to be deficiencies in Mr Naqebullah’s
material supporting his application.
- At
directions hearings on 12 and 14 April, these alleged deficiencies were
discussed. As a consequence, further affidavits from Mr
Naqebullah and his
solicitor Daniel Prior were later filed together with a Proposed Amended
Defence. This further material helpfully
narrowed and clarified the matters in
dispute. Answering material was also filed on behalf of the State of
Victoria.
- The
principal reasons advanced for an adjournment of the trial were:
- the
time since the joinder of Mr Naqebullah as a defendant in the proceeding on 15
December 2022, and his service with papers on 13
January 2023, was too short for
him to adequately prepare for a trial on 14 March (or the refixed date of 17
April 2023);
- the
defence filed by Mr Naqebullah on 21 February 2023 was filed “in order to
avoid default judgment”, and Mr Naqebullah
wished to file an amended
defence;
- Mr
Naqebullah was facing a “novel” claim based on recent legislation
that had not been the subject of any consideration
by the courts;
- Mr
Naqebullah had had many matters to deal with during this period,
including:
- determining
whether there was a conflict of interest between the interests of Shangri-La and
his own and whether this necessitated
his engagement of separate legal
representation. This matter was on-going from at least mid-December 2022 until
it was resolved on
about 15 February 2023;
- the
work involved in the liquidation of Shangri-La occupied him during 2023
culminating in the appointment of a liquidator and the
actual liquidation on 31
March 2023. The “landscape” of the proceeding, and therefore the
trial, was significantly affected
by the liquidation of Shangri-La. The
imperative of an “early” trial was removed as the apartment
owners’ claims
could not proceed;
- there
were delays in instructing appropriate expert witnesses and formulating third
party claims for contribution and indemnity;
- there
was a substantial body of material filed by the State of Victoria in advance of
the trial;
- Mr
Naqebullah had been “frozen” by the demands of the litigation;
- Mr
Naqebullah would potentially suffer substantial financial losses if he were
unsuccessful in the proceeding, as the case might be
a precedent for a number of
similar actions he was likely to face. The possible claims against him may
bankrupt him;
- the
legislation which gave the State of Victoria the right to claim against him
personally was new and complex;
- there
would be minimal prejudice to the State of Victoria if the adjournment were
granted.
- I
propose to discuss the application by Mr Naqebullah under the following
headings:
- Mr
Naqebullah’s explanation for delays;
- the
proposed amended defence;
- expert
evidence;
- third
party proceedings;
- prejudice
to the parties;
- adjournment
options;
- the
liquidation of Shangri-La.
Explanations for
delays
- The
proceeding has a long and tortuous history. The proceeding was referred by VCAT
to the County Court as part of a tranche of cases
which had not been able to be
heard during COVID. The tranche of about 80 cases was referred to the Court in
early 2022. It was intended
that the Shangri-La proceeding would be heard by a
VCAT Vice President on the date listed by VCAT of 16 May 2022.
- Since
that time there have been a series of interlocutory hearings heard by me. These
hearings have mostly been related to the inadequacy
of Shangri-La’s
pleadings against 3 “building surveying parties” and 2 “fire
engineer parties”. The
most recent of these matters was determined by me
with written reasons for decision delivered on 22 February 2023 ([2023] VCC
222).
In those reasons I referred to the history of the proceeding and previous
reasons for decision.
- The
most relevant dates for present purposes are as follows:
- 13 April 2022
– proceeding refixed for hearing on 13 March 2023 with a timetable for
interlocutory steps.
- 4 October, 3
November and 6 December 2022 – decisions made following interlocutory
hearings.
- 15 December 2022
– proceeding referred to the County Court as a more appropriate forum.
State of Victoria joined as an applicant/plaintiff
and Mr Naqebullah as a
respondent/defendant.
- 1 February 2023
– the Court indicated that it would agree to the proceeding refixed for
hearing on 17 April 2023.
- 2 March 2023
– claims by Shangri-La against the building surveying parties and the fire
engineer parties struck out, as well
as allegations in Shangri-La’s
defence that those parties were concurrent wrongdoers for the purposes of the
apportionment
provisions of the Wrongs Act.
- 10 March 2023,
Prior Law wrote to the solicitors for the State of Victoria requesting its
consent to the adjournment of the trial
between the State of Victoria and Mr
Naqebullah until November 2023.
- There
are some general comments which might be made about the conduct of the
proceeding by the respondents/defendants during this
period:
- there
has been no indication that any person, other than Mr Naqebullah, has provided
instructions to Shangri-La’s lawyers;
- Mr
Naqebullah’s solicitors and counsel are presently the same as those who
acted for Shangri-La in the proceeding until its
liquidation;
- Shangri-La
repeatedly failed to comply with the requirements of Tribunal and Court orders
which put at risk the trial commencement
dates that had been fixed
- matters
alleged in affidavits or argument during the interlocutory applications have
often been misleading or exaggerated. This has
also been reflected in the
present applications.
- In
these circumstances, it has been necessary to carefully examine the material
filed in support of Mr Naqebullah’s adjournment
application. There have
been statements made concerning the problems faced by Mr Naqebullah, in the
preparation for trial of his
defence in the State of Victoria’s action
against him, which have been problematic.
- I
will briefly examine, both shortly and later in these reasons, certain specific
matters, including:
- the
available time Mr Naqebullah has had information about the claim by the State of
Victoria;
- the
time required by Mr Naqebullah to clarify whether there was a conflict of
interest between him and Shangri-La which necessitated
him having separate
representation;
- the
delay by Mr Naqebullah in finalising a proper defence to the State’s
claim;
- delays
in obtaining expert evidence;
- delays
in formulating third party claims;
- the
liquidation of Shangri-La.
- It
is correct that Mr Naqebullah was served with the papers in the proceeding on 13
January 2023. He was, however, in attendance at
the Zoom hearing on 15 December
2022 when he was joined as a party to the proceeding and matters were discussed
about the action
against him. Mr Naqebullah said that he attended the hearing in
his “personal capacity as an observer”.
- In
addition, the State of Victoria had apparently provided his solicitors with a
draft of the statement of claim concerning him in
October 2022. At the hearing
on 3 November 2022, Mr Prior in an affidavit deposed to what Mr Naqebullah had
informed him would be
Mr Naqebullah’s attitude to certain matters if he
were personally joined as a party. Shangri-La’s counsel, Dr Wolff,
referred to these matters in his written submissions and stated “the
joinder of Mr. Naqebullah will make it improbable that
the hearing date in March
2023 can be maintained”.
- Notwithstanding
these matters, Mr Naqebullah has deposed that, the question of separate
representation for himself was not resolved
until about 15 February 2023. Mr
Naqebullah was represented by separate counsel (Mr Moon) and solicitors at the
directions hearings
on 1, 9, 10 and 28 February 2023. At those hearings, Mr Moon
did not inform the Court that Mr Naqebullah would not be able to meet
the trial
date of 17 April 2023 or would be unable to comply with the orders proposed for
interlocutory steps.
- Mr
Prior’s firm apparently commenced acting for Mr Naqebullah shortly after
15 February 2023. On 21 February 2023, Prior Law
gave notice to the Court that
it was acting on behalf of Mr Naqebullah and filed his defence to the State of
Victoria’s statement
of claim. On 28 February 2023, Mr Prior swore an
affidavit stating that the affidavit was filed on behalf of both Shangri-La and
Mr Naqebulah. It referred to delays in engaging experts and Mr Prior stated that
this would be finalised by “the end of this
week” (by 3 March 2023).
I will return to this matter shortly.
- In
a letter from Prior Law to the solicitors for the State of Victoria dated 10
March 2023, an adjournment of the hearing was sought
until “October
2023”. The letter commenced, “I refer to the above matter and
confirm that my office now acts on
behalf of Mr Obaid Naqebullah in his personal
capacity”. The letter made the following further comments:
- “For the
sake of clarity, it would only be the State’s claim against Mr Naqebullah
that would be heard in October. The
Applicants’ claim against Shangri La
would continue as ordered”. [Four days later on 14 March 2023, according
to Mr Naqebullah’s
affidavit dated 19 April 2023, Shangri-La’s
accountants contacted the subsequent liquidator’s firm “regarding
their
potential appointment as liquidator”. I note, however, that in his
affidavit sworn 19 April 2023, Mr Naqebullah states, “I
advised my
solicitors of my decision to appoint a liquidator to the company, after the
company was placed into liquidation on 31
March 2023”. Mr Prior in his
affidavit states that during a meeting in his office with Mr Naqebullah on 31
March 2023, “I
was instructed he had appointed a liquidator for
Shangri-La”. Mr Prior does not say that this was the first he knew of the
proposal to liquidate the company. Mr Prior, in the affidavit, deposes to a
number of steps he took in relation to the proceeding
during March, without
referring to any contact he had with Mr Naqebullah during the month. In relation
to the letter to Corrs Chambers
Westgarth dated 10 March 2023, Mr Prior states,
that ‘he caused the letter to be sent to Corrs Chambers Westgarth on
behalf
of the First Defendant [Shangri-La] seeking the State’s consent to
the final hearing being heard in October 2023”. That
statement is
inconsistent with the terms of the letter.].
- “it is
inconceivable that the cladding case against Mr Naqebullah in his the
State’s personal capacity can proceed in
less than six (6) weeks in
circumstances that either comply with the State’s obligations [as a model
litigant], or adequately
protect Mr Naqebullah’s rights. [The reference to
six “weeks” is inconsistent with the later reference in the letter
to “October 2023” as the proposed adjourned hearing date. It may be
likely that the letter had intended to refer to a
period of six
“months”].
- “Mr
Naqebullah has to date not been provided with any opportunity to obtain expert
evidence to support his claims. Expert evidence
is generally obtained and
provided in County Court proceedings after the pleadings are closed and the
issues have been identified”.
[There is no such rule of practice in the
Court. In building cases involving defective work, expert evidence is invariably
required
before claims or defences are filed].
- “to date,
Mr Naqebullah has not been provided with a reasonable opportunity to advance his
defences. The unfortunate timing
of the orders against him meant that he was
unable to obtain specialist counsel advice until very recently, when the
Victorian Bar
returned to chambers en masse after their summer holidays”.
[Both Shangri-La and Mr Naqebullah were represented by competent
and experienced
counsel during the hearings on 31 January and early February 2023. Mr Prior
similarly provided appropriate representation
for Shangri-La on 15 December
2022].
Proposed amended defence
- When
Prior Law filed Mr Naqebullah’s defence on 21 February 2023, there was no
indication that the time provided in the Court
orders was inadequate. In
counsel’s written submissions dated 12 April 2023, it was stated that
“Obaid Naqebullah filed
a defence in order to avoid default
judgment”.
- In
those written submissions, it was stated that Mr Naqebullah wished to raise a
number of defences that had not been raised in the
defence that had been filed
in February. The further defences included:
- Section 237F of
the Building Act, as a matter of construction, could have no retrospective
operation.
- The issue of the
possible retrospective operation of the legislation raised a
“constitutional question” in respect of
which Mr Naqebullah proposed
to give notice under the Judiciary Act 1904 (Cth).
- The claim by the
State of Victoria was an apportionable claim under the Wrongs Act and Mr
Naqebullah wished to name the building surveying
parties, the fire engineer
parties, the manufacturer/supplier of the cladding and the Victorian Building
Authority as parties which
should be added to the proceeding.
- The standing of
the owners corporation and the apartment owners to remain as
applicants/plaintiffs once the State of Victoria had
commenced paying for the
rectification works for the combustible cladding.
- Further,
it was claimed that the State of Victoria’s statement of claim was
inadequate because it did not contain adequate particulars
of matters such as
the identification and location of the alleged combustible cladding installed at
the project.
- Following
discussion about these matters at the hearings on 12 and 14 April 2023, Dr Wolff
agreed to file and serve a draft proposed
amended defence. The draft, when
delivered on 19 April 2023, contained references to the following matters:
- It maintained
the admission that the cladding installed by Shangri-La was combustible.
- It maintained
the non-admission that the rectification works to replace the cladding paid for
by the State of Victoria was necessary
and that the cost was reasonable.
- Raised the
defence that, once the State of Victoria had commenced to pay for the
rectification works, the rights of the owners corporation
and the apartment
owners to bring or maintain a proceeding were subrogated to the State and the
original rights of the owners corporation
and the apartment owners in respect of
the combustible cladding were extinguished. As a consequence, the joinder of
both the State
of Victoria and Mr Naqebullah to the proceeding was a
nullity.
- Raised the
defence that, as a matter of construction, s137F had no retrospective
operation.
- Raised the
defence that Mr Naqebullah did not have “informed knowledge” at the
time in 2014 the combustible cladding was
specified for the development.
- Raised a defence
that s137F offended sections 8, 20 and 24 of the Charter of Human Rights and
Responsibilities and was therefore unenforceable.
- Did not raise a
defence that the claim by the State of Victoria was an apportionable claim and
that other parties should be joined
to the proceeding as concurrent wrongdoers
under the Wrongs Act.
- Senior
Counsel for the State of Victoria, Mr Pane KC, submitted that there was little
basis for any of these defences and that, accordingly,
Mr Naqebullah should not
be permitted to raise defences in this form. He submitted further that, if the
amended defence were permitted,
it essentially raised matters of law, with
little need for further evidence, and accordingly the amended defence should not
delay
the early commencement of the trial.
- In
my view, there was little to be gained by a further interlocutory dispute over
the proposed amended defence, and that it should
be permitted to be filed,
without further argument, provided no further changes were made without leave of
the Court.
Expert evidence
- The
issue of expert evidence has been a troubling issue over the last 12 months of
the proceeding. In March 2022, upon the hearing
of an application by two of the
building surveying parties to strike out Shangri-La’s statement of claim
against them for lack
of proper particulars, Shangri-La requested a lengthy
period to replead, as its chosen building surveying expert was not then
available
and, when the expert would become available, he would need further
time to prepare a report. As a consequence, Shangri-La was given
a further
period of about 4 months to 5 August 2022 to replead. In fact, the chosen expert
did not prepare a report and a replacement
expert was not engaged until about 26
July 2022. The amended pleading was essentially prepared without expert input
and remained
inadequate.
- This
pattern of behaviour was repeated in relation to Shangri-La’s attempt to
claim against a third building surveyor, Mr Kromidellis,
and it became apparent
that the third party claim against the fire engineering parties suffered from
the same problem. On 2 March
2023, I made orders striking out Shangri-La’s
claims against the building surveying parties and the fire engineering parties.
My reason was that Shangri-La had neglected over many months to properly
particularise its third party claims and it was only by
striking out those
claims and by limiting the trial fixed for 17 April 2023 to the claims by the
owners corporation, the apartment
owners and the State of Victoria against
Shangri-La and Mr Naqebullah, that the trial date could be maintained.
- This
situation arose basically as a result of Shangri-La’s failure to engage
experts in a timely manner so that it was able
to prosecute its third party
claims. These were also the principal matters debated at the hearings in early
February 2023.
- It
is in this context that Mr Prior swore an affidavit on 28 February 2023 in which
Mr Prior, “on behalf of both Shangri-La
and Mr Naqebullah”, informed
the Court that there had been further contact with Mr Shafto (a building
surveying expert who
had been engaged by Shangri-La on 26 July 2022 and 4 August
2022 and had prepared two reports on 1 and 4 August 2022) and also with
Mr
Salomonsson, a fire engineering expert, who had not been previously
consulted.
- Although
Mr Prior stated in the affidavit sworn 28 February 2023 that letters of
engagement would be sent to both experts “by
the end of the week”,
this was not done for a further 5 weeks, on 6 April 2023. This was after the
liquidation of Shangri-La
and was pursued by the solicitors on Mr
Naqebullah’s behalf. The matters that each of the experts was asked to
advise on were
related to the potential liability of the building surveying
parties and the fire engineering parties for the use of the combustible
cladding
on the project.
- Although
I indicated to Dr Wolff at the hearings on 11 and 21 April 2023 that Mr Prior
should provide some explanation for the delay
in engaging the experts, this was
not referred to in Mr Prior’s affidavit sworn 19 April 2023. After I
repeated the request
at the hearing on 21 April 2023, Dr Wolff obtained
instructions that Mr Shafto would not be available to deliver a report until 9
June 2023 when he returned from leave and it was not clear when Mr Salomonsson,
would be able to report.
- The
issue of expert’s reports, until the submissions on behalf of Mr
Naqebullah at the hearing on 21 April 2023, was primarily
related to the
possible third party claims and to the “building” matters forming
part of Mr Naqebullah’s defence
of the State of Victoria’s
claim.
- In
Mr Prior’s affidavit sworn 19 April 2023, he expressed the view that the
witness statement served by the State of Victoria
on 14 March 2023 would oblige
Mr Naqebullah to “to consider various new issues pertaining to expert and
lay evidence including
in relation to:
(a) Whether expert evidence is required to assess whether the tender was
normal/standard;
(b) Whether expert evidence is required to assess whether the prices/costs were
fair and reasonable;
(c) Whether expert evidence is required to assess whether the scope of works was
accurate and reasonable;
(d) Whether expert evidence is required to assess whether the tender process was
rigorous”.
- These
matters were not pursued by Dr Wolff in his submissions on 21 April 2023.
- At
the hearing on 21 April 2023, Dr Wolff informed the Court that the principal
matter of expert evidence that would be pursued would
relate to the question of
Mr Naqebullah’s “knowledge” concerning combustible cladding in
2014, when it was specified
as a material for the project. Dr Wolff said that it
was contemplated that evidence might be led from an expert (of unnamed
expertise)
as to what a reasonable director of a building company who was also
himself a registered builder would be expected to know in 2014
about the use of
external cladding materials and their combustibility.
Proposed
third party claims
- Until
this possibility was raised, the central issue for determination in relation to
the adjournment application related to the proposed
third party claims. Although
Dr Wolff conceded in argument on 21 April 2023 that Mr Naqebullah’s
amended defence could not
raise the issue of apportionment, he still pressed the
appropriateness of adjourning the trial until third party claims could be
pursued by Mr Naqebullah. Dr Wolff, however, agreed that any such claims would
be limited to the building surveying parties and the
fire engineering parties,
and would not include the manufacturer/supplier of the cladding or the Victorian
Building Authority.
- There
were a number of concerns I raised with Dr Wolff:
- Over the last 12
months, Shangri-La’s failure to properly plead its third party claims had
continually put at risk the ability
of the parties to adhere to fixed trial
dates, and also the liquidation of Shangri-La had left the third parties, as
well as the
applicants/plaintiffs, with substantial costs orders in their favour
that they would be unlikely to recover.
- Why should the
Court not take account of this behaviour by Mr Naqebullah, as Shangri-La’s
sole director, in the conduct of the
Shangri-La proceeding as relevant to the
bona fides of the present application?
- Mr Naqebullah
had, on 19 April 2023, filed and served a proposed amended defence. However, in
relation to the proposed third party
notices, the best drafts offered as an
exhibit to Mr Naqebullah’s first affidavit were counsel’s drafts
with highlighting,
annotations and requests for instructions. The draft
pleadings against both the building surveying parties and the fire engineering
parties are dated 22 February 2023.
- These documents
were little different to the Shangri-La pleadings against those parties that I
determined should be struck out on
2 March 2023.
- I had also
indicated in those reasons for decision and the subsequent orders, that any
future application by Shangri-La for leave
to file third party claims against
these parties should be supported by appropriate affidavit material sworn by Mr
Naqebullah. Although
Mr Naqebullah’s affidavit sworn 11 April 2023 had
exhibited counsel’s draft third party pleadings, no further material
of
the nature that I had suggested in my reasons for decision on 22 February 2023
as necessary, was included in Mr Naqebullah’s
affidavit. This included,
for example, the reasons for the change in the latest pleading as compared with
earlier pleadings about
the “design meeting”, including the date and
place of the meeting, the attendees at the meeting and what was purportedly
said
at the meeting.
- Dr
Wolff submitted that I should be very reluctant to “lift the corporate
veil” and that Mr Naqebullah was a separate
person to Shangri-La. I should
disregard Mr Naqebullah’s past actions as Shangri-La’s sole director
and judge him only
by his conduct as a litigant in his own right.
- In Lumbers
v W Cook Builders Pty Ltd (in liquidation) [2008] HCA 27; (2008) 232 CLR 635 (“Lumbers”),
a critical issue was whether the contracting party with the owners (the Lumbers)
was the plaintiff, W Cook
Builders Pty Ltd (“Builders”) or a related
company W Cook & Sons Pty Ltd (“Sons”), the company with whom
the Lumbers thought they were dealing, and who had orally agreed to construct
their house.
- The
plurality, Gummow, Hayne, Crennan and Kiefel JJ, at paragraph 96, stated that,
“To say that ‘Builders did the work,
and Sons did not’, elides
a number of different ideas. Neither Builders nor Sons ‘did’ any
work. Each is a corporation.
The work that was done in the construction of the
house, whether it was done at the building site or in an office, was done by
individuals.
Before deciding which company ‘did’ the work it would
be necessary to identify for which company the relevant individuals
were
working”.
- In
my view, there is no issue of going behind the corporate veil but simply of
recognising the guiding hand behind the actions of
Shangri-La since Mr
Naqebullah became the sole director on 28 June 2013.
- It
is necessary and appropriate to consider whether Mr Naqebullah has demonstrated
that he might possibly have third party claims
against the building surveying
parties or the fire engineering parties, and if so, whether the trial of any
third party proceedings
should be heard at the same time as the trial of the
proceeding between the State of Victoria and Mr Naqebullah.
- Dr
Wolff submitted that this course was both necessary and desirable. Generally,
this course is followed in order to avoid the duplication
of hearings and the
possibility of inconsistent findings and decisions. Further, if Mr Naqebullah
were not permitted to raise third
party claims in the present proceeding, it was
suggested he may be met with an Anshun estoppel argument if he sought to raise
the
claims in a subsequent proceeding or proceedings.
- It
is necessary to examine Mr Naqebullah’s counsel’s draft pleadings
against the building surveying parties and the fire
engineering parties.
- There
are three building surveying parties, CODEHQ Pty Ltd (formerly Nicholson Wright
Pty Ltd) (“Nicholson Wright”), the
company retained by the developer
to provide building surveying services, Jim Tsaganas, the building surveyor
employee of Nicholson
Wright who was appointed as a building surveyor for the
project and who carried out early site inspections, and Mr Kromidelis, the
building surveyor employee of Nicholson Wright who was appointed as a building
surveyor for the works and who carried out later site
inspections, issued
amended building permits and issued the certificate of occupancy.
- It
is alleged in the draft pleading against the building surveying parties
that:
- In or around
2014, Nicholson Wright was retained by the Developer to provide building
surveying services (para. 10).
- On 14 June 2014,
Pat Richardson of Nicholson Wright attended a Design Meeting with other persons
including Mr Naqebullah to discuss
the project (para. 13).
- During, or
around the time of, the Design Meeting, Shangri-La provided to Nicholson Wright
and/or Jim Tsaganis a specification referring
to “75mm foam board
render” for “external rendering” and a finishes schedule
referring to “Styro Foam
Rendered” (para. 14).
- At the Design
Meeting, Mr Naqebullah “said words to the effect that RMAX orange
board” would be used “where render
finish was specified”, and
the fire engineer, Mr Verheijden “said words to the effect that as long as
the wall was fire
rated he was ok with attaching RMAX orange board render finish
on top” (para. 15).
- Building permits
were issued by Nicholson Wright and/or Mr Tsaganis in July and December 2014
(para. 16).
- Further building
permits were issued by Nicholson Wright and/or Mr Kromidelis in June 2015 (para.
18).
- The building
surveying parties “approved” the building specifications and
finishes schedule which included references
to the external render as part of
the building permits (para. 20).
- Nicholson Wright
and Mr Kromidelis “knew or ought to have known that Shangri-La
intended” to use RMAX orange board (para.
22).
- In September
2015, at the request of Nicholson Wright, Shangri-La provided “an
installers compliance certificate” stating
that “RMAX orange had
been utilised” in the project (para. 24).
- Nicholson Wright
and Mr Kromidelis should have known that Shangri-La had used RMAX orange board
(para. 25).
- As
a result of these matters, it was alleged against Nicholson Wright, Mr Tsaganis
and Mr Kromidelis that each of them owed a duty
of care and a statutory duty to
the original owner (the developer) and subsequent owners (the owners corporation
and the apartment
owners), which each of the third parties had breached (paras.
26 – 41).
- In
the draft pleading, the following highlighted notes follow paras. 37 and
38:
“[NOTE: in the FASOC against Kromidellis, we allege that a
duty of care was owed to Shangri-La as well. We did not allege that
a duty of
care was owed to Shangri- La by Nicholson Wright and/or Tsaganas. Please confirm
whether we wish to maintain that Kromidellis
owed Shangri-La (or Obaid) a duty
of care]” (follows para. 37).
“[NOTE: same comment/question as above re duty of care – applies
equally to
statutory duty.]” (follows para. 38).
- In
para. 42ff, the draft pleading alleges that:
- The whole or
part of any recovery by the State of Victoria against Mr Naqebullah would be due
to the “breach of duty and/or
breach of statutory duty” of each of
the building surveying parties.
- The owners
corporation and the apartment owners “would not have suffered the cost of
rectifying the defects and any consequential
damage”, which under s137F of
the Building Act “may be recovered by the State in accordance with the
subrogation of the Building Owners’ rights and remedies”.
- Accordingly, Mr
Naqebullah is “entitled to recover contribution and indemnity” from
the building surveying parties pursuant
to s23B of the Wrongs
Act.
- The
draft pleading against the fire engineering parties follows a similar format.
The factual matters include:
- Integrated Fire
Services was engaged by the developer “to provide fire safety engineering
services” in respect of the
project (para. 4 b).
- Mr Verheijden
was a director and employee of Integrated Fire Services and a registered
“Fire Safety Engineer” and supplied
fire safety engineering services
for the project (paras. 6 a - c).
- Prior to 2014,
Integrated Fire Services was “retained (‘the first retainer’)
to provide fire safety engineering
services in connection with [the project] by
the Developer or alternatively ‘EyeQ Constructions’” (para
9).
- The first
retainer “is inferred by reason of the ‘Fire Protection System
Design Report’ dated 30 June 2014, which
states that it was
‘prepared for ‘EyeQ Consultants’” (particulars to para.
9).
- On about 11 June
2014, Integrated Fire Services was “retained by Shangri-La (‘the
second retainer’) to provide fire
safety services in connection with the
Project” (para. 10).
- The “fire
safety services” to be provided were specifically:
- “to
review the design documentation for the Project; and
- prepare,
review and advise as to any alternative solutions and/or variations in relation
to the Project that were required in order
to satisfy the requirements of the
BCA” [not defined in the draft pleading] (para. 10).
- The second
retainer was “partly written and partly to be inferred” (particulars
to para. 10).
- The written part
was “Purchase Order No. 19 dated 11 June 2014” [presumably issued by
Shangri-La in response to the request
by email from Mr Verheijden of a purchase
order instructing Integrated Fire Services to “attend a design
meeting” in
relation to the project at Shangri-La’s offices on 11
June 2014].
- The inferred
part was “to be inferred by reason of” the email from Mr Verheijden
dated 10 June 2014 requesting the purchase
order.
- “There
were implied terms of the Second Retainer” (para. 11). [The terms and how
they are to be “implied as a matter
of law” are set out in a
highlighted part of the draft pleading at para. 11, and its particulars. The
implied terms are extensive
and their implication is said to arise in accordance
with the principles “explained in cases such as Astley v Austrust Ltd
(1999) 197 CLR 1 at [47]”].
- “Integrated
Fire Services and/or Verheijden” attended the Design Meeting at
Shangri-La’s offices on 11 June 2014
(para. 14).
- “During,
or around the time of the Design Meeting, Shangri-La provided to ... Integrated
Fire Services/Verheijden” a specification
referring to “75mm foam
board render” for “external rendering” and a finishes schedule
referring to “Styro
Foam Rendered” (para. 14).
- At the Design
Meeting, Mr Naqebullah “said words to the effect that RMAX orange
board” would be used “where render
finish was specified”, and
the fire engineer, Mr Verheijden “said words to the effect that as long as
the wall was fire
rated he was ok with attaching RMAX orange board render finish
on top” (para. 15).
- From “June
2014, Integrated Fire Services and/or Verheijden knew or ought to have known
that Shangri-La intended” to use
RMAX orange board (para. 16).
- Subsequently, Mr
“Verheijden and/or Integrated Fire Services”, in performing the fire
safety services, provided two reports
to both “Shangri-La and Nicholson
Wright”:
- “Fire
Protection System Design Report for the Fire Protection Services” dated 1
December 2014; and
- “Alternative
Solution of the DTS Provisions of the BCA” dated 8 December 2014 (para.
17).
- [A draft para.
18 stating that, “The I December 2014 Report ... was stamped as forming
part of the building permit for stage
2”, and contained certain purported
provisions, has been highlighted and crossed through].
- [A draft para.
19 stating that, “The 8 December 2014 Report” contained certain
purported provisions, has been highlighted
and crossed through].
- The
draft pleading alleges that these matters give rise to the following causes of
action by Mr Naqebullah against the fire engineering
parties, as
follows:
a. as against Integrated Fire Services:
i. in misleading and deceptive conduct;
ii. in negligence;
iii. for contribution and indemnity pursuant to s23B of the Wrongs Act;
b. as against Mr Verheijden:
i. involvement in misleading and deceptive conduct;
ii. in negligence;
iii. for contribution and indemnity pursuant to s23B of the Wrongs Act.
- The
claim by Mr Naqebullah against Integrated Fire Services pursuant to the ACL is
pleaded as follows:
- At the Design
Meeting on 11 June 2014, in response to Mr Naqebullah stating “words to
the effect that RMAX orange board”
would be used “where render
finish was specified”, Mr Verheijden’s statement “to the
effect that as long
as the wall was fire rated he was ok with attaching RMAX
orange board render finish on top”, was a representation to
“Shangri-La
and/or the Second Defendant that the use of RMAX orange board
by Shangri-La was appropriate, and otherwise complied with all relevant
[statutory and regulatory] provisions” (‘the cladding
representation’) (para. 20).
- It was
reasonable, in these circumstances, for “Shangri-La and/or the Second
Defendant” to expect that [Integrated Fire
Services] would disclose to
“Shangri-La and/or the building surveyor” if 75mm foam board or RMAX
orange board were unsuitable
or non-compliant (‘the non-disclosure”)
(para. 21).
- The cladding
representation and the non-disclosure constituted “misleading or deceptive
conduct, and/or conduct which was likely
to mislead or deceive in contravention
of section 18 of the Schedule 2 to the Competition Consumer Act 2010 (Cth)
(ACL)” (para.
25).
- Shangri-La
and/or the Second Defendant relied upon the cladding representation and the
non-disclosure in carrying out the works and
installing the cladding (para.
26).
- Mr Naqebullah
has suffered loss and damage by reason of the contraventions of the ACL by
Integrated Fire Services (para. 27).
- “Were it
not for the Integrated Fire Services Contraventions, Shangri-La would not have
installed RMAX orange board cladding
at the property. Had Shangri-La not
installed RMAX orange board cladding at the property, the Owners would not have
suffered loss
and damage, the State would not have been subrogated to the
Owners’ rights (as alleged in the SOC), and the Second Defendant
would not
be liable to the State” (particulars to para. 27).
- Mr
Naqebullah’s “loss and damage includes the costs of defending this
proceeding (insofar as it arises out of the EPS
cladding), and the extent to
which it is found liable to the State in respect of the EPS cladding and
consequential loss” (particulars
to para. 27).
- In
the claim by Mr Naqebullah against Integrated Fire Services in negligence,
paragraphs 28 to 31 of the draft pleading are highlighted
and contain
counsel’s comments about the relevance of the decision of Pullen v
Gutteridge Haskins & Davey Pty Ltd [1993] VicRp 4; [1993] 1 VR 27 to a claim that a duty of
care was owed to Mr Naqebullah personally to “inform” or
“warn” him of the non-compliance
of the cladding material.
- In
the pleading of the claims by Mr Naqebullah against Mr Verheijden for his
alleged involvement in misleading and deceptive conduct
(paras. 32 to 35) and
for negligent acts or omissions (paras. 36 to 38), there was a similar comment
by counsel in the draft pleading.
The question is asked, “[C]an we say
that he [Mr Verheijden] knew or ought to have known that they [the cladding
representation
and non-disclosure] were false?”
- The
draft pleading of the allegation of the claim in negligence by Mr Naqebullah
against Mr Verheijden (paras. 36 to 38) is followed
by the comment, “see
comments above re duty of care”.
- The
pleading of the claim for contribution and indemnity by Mr Naqebullah against
each of the fire engineering parties pursuant to
s23B of the Wrongs Act relies
upon the following matters:
- the State of
Victoria would only be entitled to recover from Mr Naqebullah the same loss and
damage as “was caused in part or
in whole” by:
- Integrated
Fire Services’ “breach of duty to the Plaintiffs [the owners
corporation and the apartment owners?] as pleaded
at paragraphs 25 to 26”,
and/or contravention of the ACL as pleaded at paragraphs 16 to 23”;
and/or
- Mr
“Verheijden’s breach of duty to the Plaintiffs as pleaded at
paragraphs 30 to 31 above and/or contravention of the
ACL as pleaded at
paragraphs 32 to 34” (paras. 39 and 40).
- It
is clear that the proposed third party notices require further work and
explanation from Mr Naqebullah as the reasons for variations
from earlier
drafts. This is particularly the case where the pleadings allege the
“substance” of critical conversations
in 2014. It would be
appropriate for Mr Naqebullah to provide his best recollection of the
conversations and any documents recently
located by him which are relevant to
the specific matters alleged.
- Dr
Wolff also submitted that, if the State of Victoria’s claim against Mr
Naqebullah proceeded separate to the third party claims,
Mr Naqebullah may face
a plea of Anshun estoppel if he were to later pursue the third parties with a
claim for damages or seeking
contribution and indemnity.
- In Tomlinson
v Ramsey Food Processing Pty Ltd [2015] HCA 28; (2015) 323 ALR 1, at paragraph 22, in the
judgment of four of the five judges, (French CJ, Bell, Gageler and Keane JJ),
the three forms of estoppel
“recognised by the common law of Australia as
having the potential to result from the rendering of a final judgment in an
adversarial
proceeding”, were discussed.
- The
plurality at [22] stated that “...The third form of estoppel is now most
often referred to as "Anshun estoppel" [after Port of Melbourne
Authority v Anshun Pty Ltd (1981) 147 CLR 589; [1981] HCA 45] ... That third form of estoppel is
an extension of the first [cause of action estoppel] and of the second [issue
estoppel]. Estoppel in
that extended form operates to preclude the assertion of
a claim, or the raising of an issue of fact or law, if that claim or issue
was
so connected with the subject matter of the first proceeding as to have made it
unreasonable in the context of that first proceeding
for the claim not to have
been made or the issue not to have been raised in that proceeding. The extended
form has been treated in
Australia as a "true estoppel" and
not as a form of res judicata in the strict sense. Considerations similar to
those which underpin this form of estoppel may support
a preclusive abuse of
process argument”.
- The
judgment, at [24], sought “to explain the relationship between the
doctrine of estoppel and the doctrine of abuse of process
as it has since come
to be recognised and applied in Australia”. The judges stated that,
“The doctrine of abuse of process
is informed in part by similar
considerations of finality and fairness. Applied to the assertion of rights or
obligations, or to
the raising of issues in successive proceedings, it overlaps
with the doctrine of estoppel. Thus, the assertion of a right or obligation,
or
the raising of an issue of fact or law, in a subsequent proceeding can be
simultaneously: (1) the subject of an estoppel which
has resulted from a final
judgment in an earlier proceeding; and (2) conduct which constitutes an abuse of
process in the subsequent
proceeding”.
- At
[25], the judgment continued: “Abuse of process, which may be invoked in
areas in which estoppels also apply, is inherently
broader and more flexible
than estoppel. Although insusceptible of a formulation which comprises closed
categories, abuse of process
is capable of application in any circumstances in
which the use of a court’s procedures would be unjustifiably oppressive to
a party or would bring the administration of justice into disrepute. It can for
that reason be available to relieve against injustice
to a party or impairment
to the system of administration of justice which might otherwise be occasioned
in circumstances where a
party to a subsequent proceeding is not bound by
estoppel”.
- I
am not persuaded that any future claim by Mr Naqebullah against third parties
would be barred. If there is such a risk, it essentially
would arise as a result
of the conduct of Shangri-La in the proceeding against it, and more recently
after Mr Naqebullah was joined
as a party. I do not, therefore, consider that
the trial of the proceeding by the State of Victoria against Mr Naqabullah
should
be delayed further because of this matter.
- At
present, the pleadings against the building surveying parties and the fire
engineering parties are in draft form only. Shangri-La
first filed points of
claim against Nicolson Wright and Mr Tsaganis in the Tribunal on 22 December
2021 and that pleading, and subsequent
pleadings by Shangri-La against those
parties, and later against Mr Kromidelis and the fire engineering parties, have
been the subject
of a number of interlocutory hearings between March 2022 and
February 2023.
- In
written reasons for decision on 13 April 2022 ([2022] VCAT 400), 4 October 2022
([2022] VCAT 1140), 3 November 2022 ([2022] VCAT
1247) and 22 February 2023
([2023] VCC 222), I have discussed at length the inadequacies of those
pleadings. On 22 February 2023,
at paragraphs 72 to 73 the reasons, I set out
matters I suggested should be satisfied in draft pleadings and affidavit
material if
there were to be a further application by Shangri-La to join those
parties as third parties. Those comments are equally applicable
to any future
application by Mr Naqebullah.
Prejudice to the parties
- Mr
Naqebullah is obviously not ready to defend the claim by the State of Victoria
against him. That is due in large part to the approach
Mr Naqebullah has taken
to the litigation, both as the sole director of Shangri-La and on his own
behalf. The proceeding is undoubtedly
a serious matter for him as the litigation
concerns novel legislation and a relatively large sum of money.
- With
the liquidation of Shangri-La, the Court can do no more to bring the litigation
by the owners corporation and the apartment owners
closer to resolution or to
otherwise address the prejudice they have suffered as a result of the past
delays. However, the liquidation
does mean that the proceeding is now focused
solely on Mr Naqebullah and no longer on Shangri-La.
- The
State of Victoria will suffer the inconvenience and expense of any claimant in
the Court. However, it is better placed than most
litigants to deal with that.
Nevertheless, it is appropriate that this proceeding should be brought to trial
within a reasonable
time.
- The
building surveying parties and the fire engineering parties have been previously
involved in the litigation over a considerable
period. They have received a
number of costs orders made in their favour and against Shangri-La which they
will have difficulty recouping.
I consider that the Court should make
appropriate orders to ensure that a similar position does not result from the
proceeding involving
Mr Naqebullah.
- In
reaching my decision, I have applied the directions provided by the Court of
Appeal in Northern Health v Kuipers [2015] VSCA 172 particularly at the parts of
the judgment I referred to at paragraphs 93 to 94 of my reasons for decision
dated 22 February 2023.
Adjournment options
- The
options open to the Court in refixing the trial of the proceeding between the
State of Victoria and Mr Naqebullah are as follows:
- commence
the hearing in early May 2023, as a special fixture;
- refix
the hearing on 31 July 2023; the next available date available through
Listings;
- delay
refixing the hearing until Mr Naqebullah has completed all the interlocutory
steps he wishes to take, including joining third
parties.
- The
State of Victoria would prefer the first option and Mr Naqebullah the last
option. In my view, the matter requires a fixed hearing
date, and the trial of
the proceeding between the State of Victoria and Mr Naqebullah should, if
necessary, be heard and determined
before any possible third party claims. The
31 July hearing date will allow a reasonable time for Mr Naqebullah to obtain
appropriate
expert evidence.
Liquidation of Shangri-La
- An
issue arose concerning the liquidation of Shangri-La. Ultimately, I consider
that the matters raised might go to the credibility
of Mr Naqebullah. Invariably
these matters are difficult to determine upon an interlocutory examination. In
reaching my decision
on the adjournment application, I have not found it
necessary to reach any concluded views. I propose to briefly record how the
issues
were raised during the course of the application.
- In
summary, the relevant matters were as follows:
- On 12 April
2023, Mr Pane KC informed the Court that documents filed in the liquidation by
the liquidator indicated that:
- Shangri-La
had not traded for some time before the liquidation.
- In
2021, Shangri-La had sold some of its assets to a related entity.
- In his affidavit
dated 19 April 2023, Mr Naqebullah stated:
- The
sale of assets in July 2021 to a related party was for “market value
determined by an independent valuer”.
- In Mr
Pane’s written submissions dated 20 April 2023, he stated at paragraph 37,
“There is a real prejudice to the State
that, as any adjournment
continues, Mr Naqebullah will dissipate his assets so as to deprive the State of
recovery”.
- Dr Wolff
challenged this statement in his oral submissions on 21 April 2023, submitting
that there was no basis for the assertion.
- Later during the
hearing, Mr Pane sought to tender in evidence an affidavit by his instructing
solicitor Joseph Barbaro sworn 21 April
2023. Dr Wolff objected and that
objection continued to be maintained on the basis of “hearsay”. I
allowed Mr Pane to
inform me of the contents of the affidavit but indicated I
would not receive the affidavit in evidence on the application until Mr
Naqebullah had had the opportunity to respond. This happened on 26 April
2023.
- Mr
Barbaro’s affidavit deposed to a conversation he had on 20 April 2021 with
the liquidator of Shangri-La, David Coyne, and
exhibited certain searches. In
summary, that material disclosed:
- In
2021, assets of Shangri-La were sold to SLC Bayside Pty Ltd.
- The
assets transferred “included business chattels and building
contracts”.
- SLC
Bayside Pty Ltd was a building company in which Obaid Naqebullah was involved
with his brother.
- In
around June 2020, dividend payments totalling approximately $1.4 million was
made by Shangri-La to its sole shareholder SMM No.
9 Pty Ltd.
- The
sole shareholder of SMM No. 9 Pty Ltd at that time was Obaid
Naqebullah.
- Mr Naqebullah
swore a further affidavit on 26 April 2023. The points of contention with the
material previously filed were as follows:
- The
total of the assets sold by Shangri-La to SLC Bayside “was in the vicinity
of $146,890 and such assets were sold for proper
value”.
- “No
building contracts were sold to SLC Bayside”.
- Both
the “sale of assets and the dividend were disclosed to the liquidator when
he was appointed”.
- Rachael
Ahne-Hawley, a solicitor from Prior Law and acting for Mr Naqebullah, swore an
affidavit on 27 April 2023 about the enquiries
she had made from 24 April 2023
onwards to the liquidator Mr Coyne as to his recollection of the conversation he
had with Mr Barbaro
on 20 April 2023. Mr Coyne responded by telephone on 26
April 2023 and the following day by email. He referred to “our discussion
of yesterday” and continued, “In that call I confirmed that the
extract provided by you largely reflected the tone of
my discussion with Mr
Barbaro and Ms Salvo. As mentioned it is unlikely that I would have used the
word ‘chattels’ and
more likely referred to ‘physical
assets’”.
Proposed orders
- In
the circumstances, the following orders should be made:
- The
trial of the proceeding between the thirteenth plaintiff, the State of Victoria,
and the second defendant, Obaid Naqebullah, is
refixed to commence on 31 July
2023 with an estimate of 5-10 hearing days.
- Leave
to the parties, pursuant to the liberty to apply hereby reserved, to make
application for the commencement of the hearing to
be deferred by no more than 5
sitting days if the estimate of time for the hearing is reduced to no more than
and the application
is made in a timely manner and the Court listings can
accommodate the deferral to commence the trial on 7 August 2023.
- On
or before 4:00 pm on XX May 2023, leave to the second defendant to file and
serve an Amended Defence in the form of the document
dated 20 April 2023. If the
second defendant wishes to file an amended pleading which differs from the
numbered paragraphs of the
draft document, he must first obtain the written
consent of the thirteenth plaintiff, or failing that, the leave of the
Court.
- On
or before 4:00 pm on XX May 2023, leave to the thirteenth plaintiff to file and
serve a reply.
- On
or before 4:00 pm on XX May 2023, the second defendant must file and serve any
expert reports upon which he intends to rely.
- On
or before 4:00 pm on XX June 2023, the thirteenth plaintiff must file and serve
any responsive expert reports.
- No
third party notice shall be filed or served by the second defendant without the
leave of the Court.
- Any
application by the second defendant to file and serve a third party notice must
be served on the proposed third parties and be
supported by affidavit material
that, as well as matters which would ordinarily be required, must
include:
- a
draft proposed fully particularised statement of claim;
- an
affidavit by the second defendant, or if the second defendant does not have
direct personal knowledge of a particular matter, an
affidavit by another person
who does have that knowledge, or if the matter involves expert opinion, by
reference to the relevant
expert report;
- any
supporting affidavit must:
- provide
full details of any contract, retainer, engagement or other arrangement alleged
in the draft statement of claim as involving
the party proposed to be joined,
and
- must
exhibit all documents referred to in the proposed pleadings or documents that
are directly related to those referred to documents.
- [the
exchange of witness statements].
- [the
usual pre-trial directions].
- Reserve
liberty to apply.
- [Costs].
- The
second defendant’s application for the referral of a question of law in
this proceeding to the Court of Appeal pursuant
to section 33 of the Charter
of Human Rights and Responsibilities Act 2006 (Vic) is refused.
- By
4:00 pm on 3 May 2023, each party must file and serve written submissions on the
proposed orders, the costs of the second defendant’s
applications and the
thirteenth plaintiff’s costs thrown away by reason of the adjournment of
the trial and advise whether
the party wishes to be heard further on these
matters.
- I
propose to publish these reasons and seek the views of the parties as to the
appropriate form of the orders proposed, and on the
question of costs.
- - -
Certificate
I certify that these 26 pages are a true copy of the judgment of His Honour
Judge Anderson delivered on 28 April 2023.
Dated: 28 April 2023
Nikki Thomson
Associate to His Honour Judge Anderson
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/vic/VCC/2023/655.html