[Home]
[Databases]
[WorldLII]
[Search]
[Feedback]
Supreme Court of Victoria |
Last Updated: 17 May 2000
SUPREME COURT OF VICTORIA |
|
COMMERCIAL AND EQUITY DIVISION |
|
No. 4272 of 1998
WIMMERA-MALLEE RURAL WATER AUTHORITY |
Plaintiff |
|
|
v |
|
|
|
FCH CONSULTING PTY LTD (ACN 007 254 864) |
First Defendant |
- and - |
|
R & L TANK FABRICATIONS PTY LTD (ACN 058 389 864) |
Second Defendant |
|
|
JUDGE: |
Byrne J | |
WHERE HELD: |
Melbourne | |
DATE OF HEARING: |
28 April 2000 | |
DATE OF JUDGMENT: |
16 May 2000 | |
CASE MAY BE CITED AS: |
Wimmera-Mallee Rural Water Authority v FCH Consulting Pty Ltd (No.2) | |
MEDIUM NEUTRAL CITATION: |
|
APPEARANCES: |
Counsel |
Solicitors |
For the Plaintiff |
Mr S. O'Meara |
Deacons Graham & James |
For the First Defendant |
Mr P.J. Cosgrave |
Phillip Quinn & Associates |
For the Second Defendant |
No Appearance |
|
For the Third Party (MGZ Pty Ltd) |
No Appearance |
|
HIS HONOUR:
"3. At all material times FCH was a project manager engaged by the Authority in respect of the construction of the tank. 4. R&L constructed the tank pursuant to a design and construct contract made 29 April 1996 between it and the Authority. 5. R&L engaged MGZ as a sub-contractor to prepare the design.PARTICULARS Particulars will be provided after discovery. 6. R&L constructed the tank pursuant to the design prepared by MGZ. 7. At all material times the Authority: a) knew or assumed that MGZ was the designer of the tank; b) relied upon MGZ to prepare the necessary documentation to enable a building permit to be obtained in respect of the construction of the tank. c) relied entirely or partly upon MGZ to properly design the tank.PARTICULARS MGZ had previously designed a similar tank to the tank for the Authority at Piangil (`the Piangil tank') as sub-contractor to R&L. The Authority project managed the design and construction of the Piangil tank. The Authority had sought and received tenders prior to engaging FCH in respect of the construction of the tank. Prior to the award of the tender for the tank, Mr Heydon of the Authority informed FCH that it knew and had no problem with R&L as tenderer as a result of the construction of the Piangil tank. The Authority accepted the recommendation of R&L as successful tenderer and must have assumed or known that MGZ was the relevant sub-contractor. The Authority knew that the building permit could not be obtained without the documentation to be prepared by the designer and relied upon him to properly prepare the same. 8. At all material times MGZ: a) knew that its drawings and computations would be relied upon to construct the tank; b) knew that if there was any error in its design and computations the Authority was vulnerable to suffering loss and damage by reason of the tank collapsing as it did; c) knew or must have assumed, even if FCH checked its drawings and computations that, if there was any error in its design and computations the Authority was vulnerable to suffering loss and damage by reason of the tank collapsing as it did; d) knew that a building permit could not be obtained without its design and computations; e) assumed responsibility (or some responsibility) for the proper design of the tank.PARTICULARS FCH refers to and repeats, so far as relevant, the particulars to paragraph 8 [7?]. Further Mr Lewis of MGZ was aware that the tank was to be built for the Authority. Mr Lewis also knew that no building permit could be obtained without his drawings and computations. Otherwise the matters set out can be inferred. 9. By reason of the matters set out in paragraphs 4-8 above, in preparing the design of the tank[s], MGZ owed the Authority a duty of care in respect of the design of the tank[s]. 10. Wrongfully, and in breach of its duty of care to the Authority, MGZ failed to properly design the tank[s].PARTICULARS MGZ was negligent in that it: (a) Failed to prepare a detailed design when requested to do so by both FCH and R&L; (b) Failed to prepare a detailed design as a term of its retainer by R&L; (c) Failed to prepare an adequate and proper design to ensure the tank did not collapse; (d) Failed to include in the design [or] any adequate bracing so as to prevent the collapse of the tank; (e) Failed to prepare a design that was capable of ready interpretation and was not confusing."
I would suppose that these paragraphs would be followed by allegations in terms of s.131(1) that, as a consequence, the Authority has suffered its loss and damage; that MGZ is jointly or severally liable to the Authority for those damages; and that the Authority is, by reason of s.131(1) of the Building Act 1993, entitled to judgment against MGZ for such proportion of those damages as the court considers to be just and equitable, having regard to the extent of the responsibility of MGZ for the Authority's loss and damage.
Date |
Activity |
? |
R & L submits a tender for the design and construction of the water tank (defence, para. 5(b)). |
26 February 1996 |
FCH offer to undertake project management (Ex "BH1"). |
March 1996 |
FCH enters into a contract with the Authority (statement of claim, para. 3; defence, para. 3). |
26 March 1996 |
Authority accepts FCH offer and forwards certain tenders received (Ex "BH1"). |
29 March 1996 |
R&L tender design SK1 prepared (defence, para. 5(b)). |
? |
R&L tender design checked by FCH (statement of claim, para. 5(b); defence para. 5(b)(vi)). |
17 April 1996 |
FCH tender evaluation (4 tenders) recommends acceptance of the R&L tender (statement of claim, para. 5(a); Ex "BH3"). |
25 April 1996 |
Authority accepts recommendation and advises FCH (Ex "BH4"). |
7 June 1996 |
Authority asks FCH for a copy of the design (Ex "BH5"). |
July 1996 |
Detailed design prepared by MGZ including SK1 (possibly a different sketch), SK2 and eight sheets of computations (Exhibit A). |
12 August 1996 |
FCH "eventually" obtains a copy of the MGZ computations and drawings (Ex "BH6"). |
12 August 1996 |
FCH applies for building permit (statement of claim, para.5(b); Ex "BH6"). |
? |
R&L detail design checked by FCH (statement of claim, para 5(b); defence para. 5(b)(vi)). |
7 January 1997 |
Certificate of Practical Completion (statement of claim, para. 6). |
17 February 1997 |
The tank fails. |
§ That this was not a domestic building.[4]
§ That there might have been some contractual provision as between MGZ and FCH which affected the former's duty.[5]
§ That there was nothing to suggest actual reliance by the Authority on the design of MGZ.[6]
§ That there was the prospect of informed and critical examination of the work of MGZ before it was implemented.[7]
§ That, unlike the flooring sub-contractor in Junior Books Ltd v Veitchi Co Ltd,[8] MGZ was not nominated by the Authority; it was selected by R&L for the performance of part of the work for which R&L itself assumed responsibility to the Authority. It is not possible, therefore, to say that the Authority relied upon the expertise of MGZ or that its relationship with the Authority was akin to that of contract.
§ That there was nothing to suggest that the Authority, supported as it was by its own engineering consultant, was particularly vulnerable to the harm to which the defective work of MGZ exposed it.[9]
§ That there was nothing to suggest that MGZ assumed any responsibility towards the Authority for the consequence of its work if defectively performed.
§ That the role of MGZ was that of designer, not that of a constructor. Its work, insofar as it is, when performed negligently, capable of causing damage to a party which implements it or relies on it, has more in common with a representation or an advice than with the manufacture or construction of a thing.
§ That I was not referred to, nor have I been able to find a case where a design sub-contractor or, indeed any sub-contractor, other than a nominated sub-contractor, has been held liable in negligence to a proprietor for loss of the present kind in the absence of special circumstances.[10]
Date |
Activity |
4 February 1998 |
The Authority's writ is filed. |
3 June 1998 |
FCH applies orally to join R&L as second defendant which application was refused at first instance. |
20 May 1999 |
The FCH application is ultimately allowed by the Court of Appeal. |
27 August 1999 |
The proceeding is set down for trial after management in the building cases list. |
14 October 1999 |
The proceedings is fixed for trial to commence on 8 March on an estimate of seven to 10 days. |
9 February 2000 |
I gave leave to FCH to serve a third party notice on MGZ as a first step in the process of adding this party as a defendant. As a consequence the trial date is vacated. |
16 February 2000 |
The first application of FCH to add MGZ as defendant is filed. |
|
|
[2] 2000 VSC 102 at [8].
[3] 2000 VSC 102 at [18].
[4] See Bryan v Moloney (1995) 182 CLR 609 at 630 per Mason CJ, Deane and Gaudron JJ; Zumpano v Montagnese [1997] 2 VR 525 at 529, per Brooking JA.
[5] Bryan v Moloney (1995) 182 CLR 609 at 625, per Mason CJ, Deane and Gaudron JJ; at 641-4, per Brennan J dissenting; Zumpano v Montagnese [1997] 2 VR 525 at 534-5, per Brooking JA.
[6] If reliance be a requirement, as to which, see Pyrenees Shire Council v Day [1998] HCA 3; (1998) 192 CLR 330 at 386, per Gummow J; Zumpano v Montagnese [1997] 2 VR 525 at 533-4, per Brooking JA.
[7] See Bryan v Maloney (1995) 182 CLR 609 at 627, per Mason CJ, Deane and Gaudron JJ.
[8] [1982] UKHL 4; [1983] 1 AC 520, a much criticised decision which has now been disapproved in England: D & F Estates Ltd v Church Commissioners for England [1988] UKHL 4; [1989] AC 177, and Scotland: Landcatch Ltd v International Oil Pollution Compensation Fund [1998] 2 Lloyd's Rep 552 at 570-1, per Lord Gill.
[9] Perre v Apand Pty Ltd [1999] HCA 36; (1999) 164 ALR 606.
[10] See too Hudson's Building and Engineering Contracts 11th ed. 1995, par 1.292.
[11] [2000] VSC 102 at [19].
[12] Boral Resources (Vic) Pty Ltd v Robak Engineering and Construction Pty Ltd [1999] VSCA 66 at [13], per Batt JA and at [76], per Chernov JA.
AustLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.austlii.edu.au/au/cases/vic/VSC/2000/193.html