Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 26 November 2013
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2013-404-003390 [2013] NZHC 2831
IN THE MATTER of an appeal against the decision of the
Weathertight Homes Tribunal at Auckland
BETWEEN CARL SANTO SAFFIOTI and EIJA MARITA LINDEN SAFFIOTI
Appellants
AND GREGORY PAUL WARD and KIM MICHELLE WARD
First Respondents
TONY HERON Second Respondent
Hearing: 8-9 October 2013
Counsel: TJ Rainey for Appellants
S Grant for First Respondent
Second Respondent in person
Judgment: 29 October 2013
JUDGMENT OF ASHER J
This judgment was delivered by me on Tuesday, 29 October 2013 at 11.00 am
pursuant to r 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Solicitors/Counsel: Rainey Law, Auckland. Kennedys, Auckland.
S Grant, Auckland.
Copy to:
Second Respondent
SAFFIOTI v WARD [2013] NZHC 2831 [29 October 2013]
Table of Contents
Para No
Introduction [1] Lead up to the claim [2] The Tribunal decision [5] The Ward appeal
Introduction [12]
Case law [18] Interpretation of cl 6.2(5)(d) [24] Subclause (b) [45] Breach [57] The Heron appeal [72] Result [83]
Introduction
[1] In 2004, Carl and Eija Saffioti purchased a home at 34 Wairere Avenue, Mt Albert. It proved to be a leaky building and was re-clad. The Saffiotis sought to recover the cost of that re-cladding by issuing proceedings in the Weathertight Homes Tribunal against a number of parties. Those parties included the first respondents Gregory and Kim Ward from whom they had purchased the property, and the second respondent Tony Heron, who had signed the code compliance certificate. Although they succeeded against some parties, the Saffiotis failed in their claims against the Wards and Mr Heron. This is an appeal against those two parts of
the Weathertight Homes Tribunal decision.1
Lead up to the claim
[2] In 2002, Gregory and Kim Ward built a home for themselves at 34 Wairere Avenue, Mt Albert (the property). They had no particular knowledge of or skill in building. They used an architect and employed builders. There was a building consent for the work done, and after the work was completed they obtained a code compliance certificate (CCC). They employed Approved Building Certifiers Ltd (ABC), a building certifier, to carry out the certification process. One of the employees of ABC was the second respondent, Mr Heron. There were no
weathertightness issues evident after completion of the work or through
the duration
1 Saffioti v Ward [2013] NZWHT Auckland 17.
of the Wards’ ownership of the property. There was no suggestion that
they were aware of any problems.
[3] On 26 September 2004, the Wards and Saffiotis entered into an
agreement for sale and purchase of the property to the Saffiotis
for $600,000.
The agreement was conditional on obtaining a LIM report and a
satisfactory pre-purchase building report.
These reports were obtained and
did not contain significant adverse information.
[4] The Saffiotis settled and occupied the property for almost five
years without any leaking issues becoming apparent. Then,
in June 2009, they
experienced a leak in the lounge. On 26 November 2009, they made an
application for an assessor’s report
under s 32 of the Weathertight Homes
Resolution Services Act 2006 (WHRSA). In due course the Saffiotis re-clad
their house (but
not the roof). Ultimately this led to a hearing, the decision
of the Weathertight Homes Tribunal (the Tribunal) and this appeal.
The Tribunal decision
[5] Two building experts gave evidence before the Tribunal, an expert
assessor Mr Noel Casey appointed under the WHRSA,
and Mr Barry Gill, a
registered building surveyor who gave evidence for Mr and Mrs Saffioti. It was
Mr Gill’s uncontradicted
evidence, which was accepted by the Tribunal,
that the defects which caused or contributed to the leaks in the house were as
follows:2
A. The timber barge boards were imbedded within the EIFS cladding. B. The joinery penetrations lacked an adequate weathertight seal.
C. The parapet cap flashings were ineffective.
E. The service penetrations were not sealed.
2 Saffioti v Ward, above n 1, at [11].
[6] All of the defects arose from the original construction of the house and were present at the time of the CCC issuing on 16 April 2002, as well as when the agreement for sale and purchase between the Wards and the Saffiotis was settled on
8 December 2004. At the hearing, the experts agreed that a full re-clad of
the house had been required save for the roof of the house
or eaves replacing
the former parapet caps. Mr Gill’s evidence, which the Tribunal accepted,
was that defect “B”
on its own had required a full re-clad. With
some windows there was no sealant between the sill and jamb flashings, and with
others
inadequate sealant. This defect was accentuated by a lack of correct
drip detail at the base of the cladding. There was no dispute
before the
Tribunal as to the reasonableness of the amount spent on re-cladding of
$281,588.87.
[7] The Tribunal’s decision covered a range of claims. The
appeal is limited to two aspects of its determination, namely:
The decision to dismiss the claim against the Wards
alleging a breach
of the vendor warranties; and
The decision to dismiss the claim against Mr Heron alleging that as an employee of ABC he was negligent in issuing the building certificate in reliance on which the building consent was issued, and in issuing
the code compliance certificate.
[8] The Tribunal determined that the claim against the Wards
turned on the interpretation of the warranties contained
in cls 6.2(5)(b) and
(d) of the agreement for sale and purchase. It concluded that the warranties
did not extend to a warranty that
there had been compliance with the Building
Code when the house was built, or a warranty that the Building Code had been
complied
with in all respects. Therefore, the Saffiotis’ claims against
the Wards failed. The Tribunal’s reasoning will be considered
in greater
detail later in this judgment.
[9] The claim against Mr Heron was dismissed on the basis
that although
Mr Heron owed a duty to exercise due skill and care in performing his building
control functions, there was no evidence that he had breached that duty of
care or done any work in a negligent fashion.
[10] I accept Mr Rainey’s submission that this is an appeal by way
of a rehearing and that the Court has the responsibility
of arriving at its own
assessment of the merits of the case.3 The appellant bears an onus
of satisfying the appeal Court that it should differ from the decision
below.4
[11] There are in effect two separate appeals before the Court: the
appeal against the claims against Mr and Mrs Ward, and
the appeal against
the claim against Mr Heron. They will be considered separately.
The Ward appeal
Introduction
[12] Clause 6.2(5) of the agreement for sale and purchase
read:
The vendor warrants and undertakes that at the giving and taking
of possession:
...
(5) Where the vendor has done or caused or permitted to be done on the
property any works for which a permit or building consent
was required by
law:
(a) The required permit or consent was obtained; and
(b) The works were completed in compliance with that permit or
consent; and
(c) Where appropriate, a code compliance certificate was issued for those
works; and
(d) All obligations imposed under the Building Act 1991 were fully
complied with.
(emphasis added)
[13] The form of agreement was the seventh edition of the Auckland
District Law
Society form. There is now an eighth edition and cl 6.2(5)(d) has been
deleted.
3 Austin, Nichols & Co Inc v Stichting Lodestar [2007] NZSC 103, [2008] 2 NZLR 141 at [5].
4 At [4].
[14] Mr Rainey, who appeared for the Saffiotis, asserted that both cls
6.2(5)(b) and (d) were breached and that the Tribunal’s
decision to the
contrary was in error. There are common themes running through his submissions
on both cls 6.2(5)(b) and (d), and
in the submissions of Ms Grant who appeared
for the Wards. The principles on interpretation that are to be applied were not
the
subject of debate between counsel, and do not require
elaboration.
[15] As was observed by the Court of Appeal in Pyne Gould Guinness Ltd v Montgomery Watson (NZ) Ltd, the “best start to understanding a document is to read the words used, and to ascertain their natural and ordinary meaning in the context of the document as a whole”.5 The natural and ordinary meaning of the words used by the parties must be understood in the proper context, not just of the document, but against the background facts. In that regard, the Court can look
outside a written contract to ascertain from the background facts the
objective intentions of the parties.6 The background can be used as
a cross-check or to assist in difficult interpretation points.
[16] In this case, part of the immediate context is the Building Act 1991, which is referred to in cl 6.2(5)(d), and the New Zealand Building Code (the Building Code).7
The Building Code was enacted under s 48, which provides for the making of
regulations. Mr Rainey made submissions first in relation
to cl 6.2(5)(d), and
submitted that it must include the obligation under s 7(1) of the Building Act
1991 which provides that all
building work shall comply with the Building
Code.
[17] The Tribunal concluded that subcl (d) added nothing to the warranties in (a)-(c) and did not involve any warranty that the works done complied with the requirements of the Building Act and therefore the Building Code. The reference to compliance with the Building Act 1991 was to the house being “... the plans
attached to that consent and any relevant conditions contained in that
consent”.8
5 Pyne Gould Guinness Ltd v Montgomery Watson (NZ) Ltd [2002] NZEmpC 79; [2001] NZAR 789 (CA) at [29].
6 See Airwork (NZ) Ltd v Vertical Flight Management Ltd [1999] 1 NZLR 641 (CA) at 650–651.
7 The Building Act 1991 has now been replaced by the Building Act 2004.
8 Saffioti v Ward, above n 1, at [55].
Case law
[18] Mr Rainey submitted that the Tribunal’s interpretation of the
warranties was wrong. He relied in particular
on the High
Court decision of Van Huijsduijnen v Woodley where Ronald Young J
stated:9
I am satisfied that there is no reason to read down cl 5(d) by restricting
its breadth only to Building Act requirements that relate to the code compliance
certificate or the permit. To read down cl 5(d) in this way is, in my view, to
reduce
the clause to a superfluous provision except where the consent or code
compliance certificate was wrongly granted.
However, in that situation, in terms of cl 6.2, the vendor will still be
liable because of the warranty the vendor has given
pursuant to cl
5(d). Irrespective of the warranties in cls 5(a), (b) and (c), the vendor
warrants compliance with the Act and,
therefore, the Code.
Thus, in most cases the warranty in cl 5(d) will add nothing to the
warranties given in cl 5(a), (b) and (c). But the cl 5(d) warranty
will be
operative where the local authority’s process has failed and the permit or
code compliance certificate wrongly granted.
But I do not consider cl
5(d)’s meaning is restricted in the way identified by MacKenzie J in
Ford v Ryan.
[19] It was observed in that case that the meaning of subcl (d) was
“not at all clear”10 and that it had been removed from
subsequent versions of the standard form agreement for sale and purchase,
possibly because of the
uncertainty of its breadth.11
[20] The case can be contrasted with the decision of Ford v Ryan,12 which Ronald Young J did not follow.13 MacKenzie J in Ford v Ryan took the view that under subcl (d) there had to be evidence that an obligation imposed under the Building Act, apart from those contained in the Building Code and to which a CCC would relate,
“had not been complied with”. He referred to a failure to comply with any part of the Building Code “which would prevent the issue of a [code compliance certificate] constituting a breach of subclause (d)”. He held that subcl (d) was “not a warranty
as to quality”.14
9 Van Huijsduijnen v Woodley [2012] NZHC 2685 at [32]–[34].
10 At [24].
11 At [30].
12 Ford v Ryan [2007] NZHC 1454; (2007) 8 NZCPR 945 (HC) at [21].
13 Van Huijsduijnen v Woodley, above n 9, at [34].
14 At [25].
[21] Ford v Ryan was followed by Williams J in Newton v
Stewart15 in relation to the interpretation of cl 6.2(5) in the
same form as in the present case. He noted:
The first point to make is that cl 6.2(5) of the agreement for sale and
purchase is not a warranty as to the quality of the home.
Specifically, it is
not a warranty that the home is watertight.
[22] An approach which is consistent with Ford v Ryan and
Newton v Stewart has in my view been since applied by this
Court in Keven Investments Ltd v Montgomery16 and
Brebner v Collie,17 which are considered later in
this judgment.
[23] The approach in Ford v Ryan and Newton v Stewart was
applied by the Tribunal in Heath v Auckland City Council18 and
in the original Tribunal decision of Van Huijsduijnen v Woodley.19
The Tribunal decision in this case also followed the line of reasoning in
Ford v Ryan and Newton v Stewart.20 In particular,
the Tribunal stated:21
We consider that the ordinary and natural meaning of sub-clause (d) of the
contract between Mr and Mrs Ward and Mr and Mrs Saffioti
was that a building
consent had been obtained before the house was built, the house had been built
in accordance with that consent,
and that a CCC had been issued after the house
had been completed. We consider that there was no intention for the warranty in
sub-clause
(d) to include compliance with the Building Code beyond the
compliance necessary to obtain the consents referred to in the preceding
sub
clauses. At the time of settlement there had been no failure by Mr and Mrs
Ward that would have prevented the CCC from being
issued and the CCC
demonstrated that the Building Code had been complied with.
Interpretation of cl 6.2(5)(d)
[24] The operative words to be drawn from cl 6.2(5)(d) conflating the
words of the clause are:
15 Newton v Stewart [2013] NZHC 970 at [98].
16 Keven Investments Ltd v Montgomery [2012] NZHC 1596.
17 Brebner v Collie [2013] NZHC 63.
18 Heath v Auckland City Council [2012] NZWHT Auckland 20 at [63]–[67].
20 At [57]–[64].
21 At [64].
The vendor warrants and undertakes that at the giving and taking of
possession ... where the vendor has done or caused or permitted
to be done on
the property works for which a permit or building consent was required by law
... all obligations imposed under the Building Act 1991 were fully complied
with.
(emphasis added)
[25] As one of the “obligations” imposed under the Building
Act 1991, Mr Rainey
relies on s 7, which provides:
7 All building work to comply with building code
(1) All building work shall comply with the building code to the extent
required by this Act, whether or not a building consent
is required in respect
of that building work.
(2) Except as specifically provided to the contrary in any Act, no person,
in undertaking any building work, shall be
required to achieve
performance criteria additional to or more restrictive in relation to that
building work than the performance
criteria specified in the building
code.
[26] It is his submission that this section places an obligation on a non-builder owner to comply with the Building Code in respect of any building, and that therefore the Wards have warranted that the Building Code has been complied with in all respects. The Building Code22 contains express provisions that the building shall be constructed to provide adequate resistance to penetration by and the accumulation of moisture,23 and that the exterior walls shall prevent the penetration of water that could cause undue dampness or damage to building elements.24 It was Mr Rainey’s core argument that through s 7, the Wards warranted there had been
compliance with the watertightness provisions of the Building Code. Since
the building had been proven to leak, the Wards were in
breach. He also
referred to a BRANZ document which contained express “good practice”
for sealing window joints, but
this document was not part of the Building Code,
and he did not argue that the BRANZ requirements were part of the s 7
obligation.
[27] So the starting point is: what do the words in subcl (d) mean on a
plain reading? The reference to compliance with
“all obligations
imposed under the
22 Building Regulations 1992.
23 E 2.2.
24 E 2.3.2.
Building Act 1991” is on its face a reference to all obligations in an
Act which, including schedules, is 51 closely typed pages
long.25
There is no reference in subcl (d) to the Building Code, which is not a
part of the Building Act 1991. Rather, it is a schedule to
regulations made
under the Act.26
[28] As Ms Grant pointed out in submissions, the Act places obligations
on not just the owner of a building who has applied for
a building consent and
carried out a construction, but on a number of parties. For example, there are
obligations placed on territorial
authorities relating to the audit of the issue
of building consents27 and to submit estimates of expenditure to the
Minister.28 The Act also imposes obligations on the
Minister,29 and on the Building Industry
Authority.30
[29] However, Mr Rainey did not suggest that subcl (d) placed a warranty
on a vendor that all obligations by all parties upon
whom obligations were
placed under the Building Act 1991, were complied with. As I understand his
submission, it was that subcl
(d) meant that the vendor warranted that where the
vendor had done or caused or permitted to be done works on the house, all
obligations
imposed on the owner (as distinct from every party) under the
Building Act 1991 were fully complied with. Such a limitation
does not
necessarily flow from the wording of subcl (d) which refers to “all
obligations” without reference to any particular
party’s
obligations.
[30] Mr Rainey submitted that the issue was whether subcl (d) meant what it said. However, to succeed Mr Rainey’s submission requires subcl (d) to be read as referring only to obligations under the Act that fall on the owner under the Act. Mr Rainey is effectively arguing that the warranty means more than it says. Further, the warranty he argues does not just relate to obligations on owners under the Building Act 1991, but on the appellants’ submission, a warranty that another
document altogether, the Building Code, will be complied with because it
is referred
25 It has now been replaced by the Building Act 2004.
26 Building Regulations 1992.
27 Building Act 1991, s 23E(1), (3) and (4).
28 Section 23J(2). See also ss 23K(3), 23L(1) and (2); 24, 25(2) and (3); 27(1), (3) and (4); 29(4),
31(1), (2), (3) and (5); 33(2A) and (6); 34(1) and (5); 34A(3); 35(1) and (2).
29 See for example ss 23I and 23J.
30 See for example ss 20 and 23D(2).
to by s 7 of that Act. The appellants are seeking a wide interpretation of
the subclause.
[31] The Building Act 1991 unambiguously does impose various obligations
on owners. For instance, at s 33(1) it was stated that
an owner intending to
carry out any building work shall, before the commencement of work, apply for a
building consent. If work
is commenced without a building consent the owner
shall take all reasonable steps to obtain one.31
[32] In contrast to the specific duties in the Act placed on “the owner” and other parties,32 s 7 is not worded so as to expressly impose a duty on “an owner” or to comply with the Building Code should that owner undertake building work. Section 7 is placed in pt 2 of the Act which is headed “Purposes and principles”. It is clearly a principle and purpose of the Act that all building work shall comply with the Building Code, but this is a very different matter from s 7 imposing an “obligation” on all owners to so comply. The word “obligation” is not used in s 7 and there is no reference to owners, or any other party for that matter. It reads as a
“principle”, rather than as an “obligation”. It is
“all building work” and not the “owner”
that must
comply. It is difficult to transform a principle of compliance with the
Building Code into a specific duty on an owner
to ensure compliance with all of
its requirements. If s 7 was intended to place obligations on specific parties
it could be expected
that it would have said so, and not place the
obligation under a “Purposes and principles” heading.
[33] As has been observed in other cases, there has been no implied warranty for vendors in New Zealand that residential houses they sell have any quality or fitness for any particular purpose. There is no implied term of merchantable quality for houses. The law on this point has been clearly articulated and is well known.33
Caveat emptor applies to contracts for the sale and purchase of
land.34
31 S 32(2)(A). See also for example ss 33(1), 43(1), 44(4), 45(1) and (2), 46(1) and 65(5).
32 For example, s 33 of the Building Act 1991.
33 Lynch v Thorne [1956] 1 WLR 303 (CA); Ware v Johnson [1984] 2 NZLR 518 (HC) at 534.
34 Spooner v Eustace [1963] NZLR 913 (HC) at 916; Riddell v Porteous [1999] 1 NZLR 1 (CA) at
8; Ford v Ryan, above n 12.
[34] It could be expected that if the parties intended to depart
radically from that principle, as they would have done if the
clause has
the meaning proposed by Mr Rainey, this would be clearly articulated in the
subclause by words to the effect that
“the vendor warrants that all works
done or caused or permitted by the vendor comply with the provisions of the
Building Code”.
There are no such words. This indicates that the
expansive interpretation of “all obligations” urged by the appellant
should be rejected. Section 7 does not create a bridge that turns a warranty
of compliance with the Building Act 1991 into a warranty
of compliance with the
Building Code.
[35] A refusal to read subcl (d) as a vendor warranty of compliance with the Building Code is consistent with the Ford v Ryan and Newton v Stewart line of cases.35 There, an interpretation of cl 6.2(5) that it was a warranty as to quality by the vendor was not accepted. It is also consistent with the approach taken to the interpretation of cl 6.2(5)(b) in Keven Investments Ltd v Montgomery. In that decision, Woodhouse J noted the distinction between an obligation to comply with a
building consent and an obligation to build in compliance with the Building
Code. He observed in the context of subcl (b) that if
the warranty was given an
extended meaning it could operate unfairly.36 An owner, who has
not been involved in the detail of a building and was innocent of any fault in
relation to it, could be liable for
an error of which that owner had no
knowledge. He noted:37
If it was the intention of the parties that the vendor was warranting that,
at the giving and taking of possession the building complied
with the building
code or, more broadly, complied with all obligations imposed under the relevant
Building Act, the straightforward
and conventional way of achieving this would
be to insert an express provision to that effect. It was not done.
[36] Although Woodhouse J was referring to subcl (b), I consider that his reasoning applies equally to subcl (d). In my view, when cl 6.2(5)(d) is read in the context of the words of the Building Act 1991 and s 7, it is not possible to interpret the clause as involving a warranty that all of the provisions of the Building Act 1991
including the Building Code have been complied with. It was
referring to the
35 Referred to above at [20]–[23].
36 Keven Investments Ltd v Montgomery, above n 16, at [51].
37 At [52].
obligations that are specifically placed on owners under the Building Act
1991. This does not include s 7, which does not place any
specific obligation
on an owner, but rather sets out a general purpose and principle. It would be a
massive jump from the usual
position of caveat emptor to a position where there
was a guarantee that the design and workmanship of a house complied with the
Building Code. If it was the intention of the parties that a warranty of
compliance with the Building Code was being given, it could
be expected that
subcl (d) would have said so.
[37] It is necessary to consider subcl (d) in relation to the other
subclauses in cl 6. There is already at (a) an obligation
on a vendor to have
obtained the required permit or consent, and at (b) a warranty that the works
were completed in compliance with
that permit or consent. I will consider subcl
(b) in more detail later in this judgment, but it can be observed that (a), (b)
and
(c) all relate to obligations already imposed by the Building Act 1991. The
question must be considered whether (d) actually has
any meaning in addition to
(a)–(c) if this interpretation is correct, bearing in mind the assumption
that the clause should
be assumed to have been intended to have
meaning independent of the other clauses.
[38] In my view it does, as there are references to obligations on
vendors in the Building Act 1991 that go beyond the obligations
to obtain a
permit, consent, CCC and complete the works in compliance with those
requirements. These include the obligation of an
owner to provide compliance
schedules (if applicable),38 provide a building warrant of
fitness,39 and the liability of an owner for the cost of work done by
a territorial authority.40
[39] It has been noted that the current ADLS/REINZ form of agreement for sale and purchase no longer contains subcl (d). I decline Mr Rainey’s invitation to draw an inference from this that the change supports the broad meaning for which he contends. It does not seem to me that the later actions of the Auckland District Law Society, or the observations of Law Society commentators, years after the agreement for sale and purchase assist in interpretation in the way that Hansard reports on a Bill
assist in interpreting the statute that follows the debates. The later
actions and
38 Building Act 1991, s 44(2).
39 Section 45.
40 Sections 65(5) and 75(1).
commentaries by Law Society commentators are not in themselves a guide to the
meaning of the agreement between the Saffiotis and the
Wards.
[40] I note that the commentators in the New Zealand Law Society seminar
appear to assume that cl 6.4(2)(d) does impose a broad
warranty of the type
contended for by Mr Rainey, but with respect for the reasons set out, I do not
agree with that view.
[41] Insofar as there is a conflict between the approach
favoured by Ronald Young J in Van Huijsduijnen v Woodley,41
and Ford v Ryan I respectfully prefer the approach in Ford v
Ryan for the reasons I have set out. I note that the relevant observations
in Van Huijsduijnen v Woodley were obiter as ultimately on the facts the
Judge found that there had been no breach of warranty. I have been also
referred to the
decision of Aldridge v Boe.42 That case
considered a clause that did not include subcls (b) and (d) and does not
assist.
[42] Thus in summary, in relation to subcl (d):
The words refer to compliance with the Building Act 1991, not the
Building Code. The Building Code is a schedule to the Act, but not part of
the Act.
For the words to extend to the Wards’ obligations under the Building
Code, a gloss has to be read into the clause that it is only obligations of
owners under the Act that are warranted.
Further, s 7 would need to be read as imposing a duty on owners to comply with the Building Code. However, s 7 of the Building Act
1991 does not impose an obligation in the sense of a duty on an owner to comply with the Building Code, but rather sets out a principle or
objective.
41 Van Huijsduijnen v Woodley, above n 9 at [32]–[36].
42 Aldridge v Boe HC Auckland CIV-2010-404-7805, 10 January 2012.
Against the background of caveat emptor for purchasers of real estate in New Zealand, if it was intended to impose a warranty of fitness on
a vendor, the clause could be expected to say so
expressly.
The majority of relevant New Zealand cases do
not support the
interpretation put forward by the appellant.
[43] I conclude that subcl (d) does not either expressly or by
implication provide a warranty by the Wards of compliance with
the Building
Code. This being my conclusion as to interpretation it follows that the
Wards have not breached cl 6.2(5)(d).
They obtained a CCC and appear to have
met all obligations that are specifically placed on an owner under the Building
Act 1991.
They did nothing that would have prevented the issue of the
certificate. They took the steps that they were obliged to take.
[44] I should refer to the fact that in support of her argument Ms Grant
referred to the fact that the agreement provided for
a builder’s report,
and that this suggested that viewed objectively the parties were not relying on
a long term warranty as
to the fitness of the building. I am unable to accept
that submission. It is not stated what type of building report was being
sought. The report could well have been to discern the level of wear and tear,
or whether any problems had arisen since building.
The fact that the buyers of
cars may have them checked by the Automobile Association does not negate the
existence of the implied
warranty of fitness for purpose in chattels contracts.
I do not regard the building report condition as assisting the
respondents’
argument.
Subclause (b)
[45] The operative words of cl 6.5(2)(b) conflating the divisions in the
section are:
The vendor warrants and undertakes that at the giving and taking of
possession ... where the vendor has done or caused or permitted
to be done on
the property any works for which a permit or building consent was
required by law ... the works were completed in compliance with that permit
or consent.
(emphasis added)
[46] It is necessary to turn to the words of the permit. The first
paragraph on the first page under the box of details reads
as follows:
The Building Consent is a consent under the Building Act 1991 to undertake
building work in accordance with the attached plans and
specifications so as to
comply with the provisions of the New Zealand Building Code. It does not affect
any duty or responsibility
under any other Act nor permit any breach of any
other Act. All endorsements on plans form part of the Building
Consent and must be adhered to.
(emphasis added)
[47] It is the last sentence on which Mr Rainey relies. It can be seen that the first sentence states that there were works undertaken in accordance with the attached plans and specifications “so as to comply” with the Building Code. This was interpreted by Woodhouse J in Keven Investments Ltd v Montgomery as recording an objective, namely a statement of what was intended to be achieved if the plans were
complied with. It was not a directive. As he
observed:43
This interpretation, confined to the words of immediate relevance, would mean
that, if the house was built in accordance with the
plans, but if it did not
comply with the building code for some reason, there would be no breach of the
warranty.
[48] Woodhouse J noted a sharp distinction between an obligation to
comply with the building consent and an obligation to build
in compliance with
the Building Code.44 He made the observation already referred to
that if an undertaking of compliance with all obligations imposed under the
relevant Building
Act was intended, it could be expected that this would be
stated. This approach, which was followed by Peters J in Brebner v
Collie,45 is not contested by Mr Rainey. I record with respect
that I consider Woodhouse J’s interpretation to be correct.
[49] Rather, Mr Rainey in focussing on the last sentence of the paragraph in the building consent submitted that the sentence distinguished this case from Keven Investments v Montgomery and Brebner v Collie. That sentence read “all endorsements on plans form part of the building consent and must be adhered to”.
Mr Rainey referred to a plan that had been drafted by the Wards’
architects that was
43 Keven Investments Ltd v Montgomery, above n 16, at [41].
44 At [50].
45 Brebner v Collie, above n 17.
part of the building consent. Under the heading “Architectural
Notes”, the plan had
on it six bullet points, the first of which read:
All works to comply with the NZ Building Code 1999, all amendments and
compliance documents and all local council bylaws.
[50] Mr Rainey submitted that the obligation to comply with the building
consent involved an obligation to comply with this endorsement
on the plan
attached to the consent. Therefore, it was a warranty that the Building Code
would be complied with. Because the Building
Code weathertightness requirement
had not been met, the warranty had been breached. This submission was not made
to the Tribunal
where there was no particular reliance placed on the sentence,
and the Tribunal did not deal with it in its decision.
[51] I consider that as a matter of contractual interpretation,
the warranty at subcl (b) did not impose a warranty
that the Building Code had
been complied with. I am unable to convert the sentence that all endorsements on
the building consent
plans be converted into an obligation to complete works in
compliance with the Building Code. There is no warranty in subcl (b)
that the
Building Code has been complied with. The reference to complying with the
Building Code both in the first sentence of the
building consent, and the
inferred reference to the Building Code in the third sentence, do not make a
warranty of compliance with
the consent into a warranty of compliance with the
Building Code. If that had been the intention, given the background of caveat
emptor already referred to, it could be expected that this would be
stated.
[52] The appellants’ argument in this respect fails for a further
reason. I do not regard the architectural note as an
“endorsement”
and therefore a building consent requirement that had to be complied with. The
architect’s plan
was provided to the certifier with the building permit
application. The architect’s note in the first bullet point on that
plan
does not have the flavour of a condition or endorsement, and was no more than a
general observation as to the standard to be
observed by the builder. In later
bullet points there are requirements set out, and explanations provided. For
instance, the last
bullet point reads:
Window schedule: 1218/200
Denotes 1200 high and 1800 wide
Unit with 200 x 100 lintel
Window heads above F.L.
[53] In light of the above, I consider that with the first bullet point,
the architect has provided a general reminder in the
nature of an explanatory
note for the builder. It is not an endorsement.
[54] It could be expected that any requirements that fell within the
wording of the last sentence relied on by Mr Rainey would
be specific
endorsements imposed by the certifier, in this case ABC. While the word
“endorsements” is not defined in
the building consent, I accept
Ms Grant’s submission that in context it means an endorsement
imposed by Auckland
City or, when there is a private certifier, by that
certifier. I note that in the earlier part of the paragraph the building
consent
is noted as issued subject to conditions and endorsements overleaf, and
there are a number of specific endorsements which in terms
of the consent must
be adhered to. They are the type of “endorsements” referred to as
part of the building consent.
These are entirely different from informal
architect’s notes set out on a plan attached to the building permit
application.
[55] I conclude that the works had to be completed in compliance with the
plans and specifications attached to the consent, and
the relevant conditions
and endorsements expressly recorded by the Council or certifier on that consent.
But subcl (b) is not thereby
converted into a warranty by the vendor that the
works also comply with the provisions of the Building Code.
[56] It is not argued that there was any failure to construct in accordance with what was shown on the plans and specifications, or that there had been any failure to adhere to any endorsements on the plans (save for the architect’s note argument which I have rejected). Therefore the appeal in relation to the Tribunal’s finding as to the meaning of and breach of subcl (b) must be dismissed.
Breach
[57] The Tribunal noted that the consent contained seven specific
conditions, none of which related to any of the six defects
that had been
established. It also noted that there had been no allegation made of a breach
of any specific provision of the building
consent or Building Code. There was
no attempt to link any of the defects to any specific provision in the building
consent or in
the plans. The Tribunal, adopting its interpretation of (b), was
unable to link any of the six defects to a relevant requirement
of the building
consent. None of the seven conditions listed in the consent had relevance to
the defects. Therefore there had
been no breach of subcl (b). There was also
no breach of subcl (d) as the defects were not a result of departures from the
building
consent.
[58] The Tribunal went on to observe:46
There is also no evidence that at the time Mr and Mrs Ward sold the house it
did not comply with the performance based Building Code.
To the contrary the
information before the Tribunal suggests that house was not at that stage
leaking. Mr and Mrs Ward were not
aware of any potential issues with the
property and the pre-purchase inspection report that Mr and Mrs Saffioti
obtained before
they declared the purchase unconditional concluded the
house was in very good condition and had been very well maintained.
It also
stated that “the installation of the plaster system has initially been
well carried out and we have found no areas
of concern in terms of water
tightness”. In addition when the assessor carried out his investigation
over five years later
there were relatively few high moisture
readings.
[59] Mr Rainey argued that there had been a breach of the Building Code
at the time of the building, pointing to the fact it had
ultimately been shown
to be not weatherproof. He referred to Mr Gill’s unchallenged evidence
of a failure to seal and construct
the window joints in a manner that would
ensure no water ingress, in breach of good practice.
[60] Ms Grant submitted that the Tribunal was correct in finding that there was no proven breach of the Building Code. She submitted that there was a failure to plead any breach of the code and the particulars of the claim, and that the evidence of breach provided by Mr Gill was too general and lacking in specificity to constitute
an adequate allegation of breach. No witness had given evidence to the
effect that
46 Saffioti v Ward, above n 1, at [71].
the house was not constructed as the Council had required it to be, and there
was no allegation that the CCC was wrongly issued.
[61] It is not necessary for me to make any final determination on the
issue of breach given my conclusion that the appellants’
challenge to the
meaning of the cl 6.2(5) warranties does not succeed. However, out of
deference to the extensive arguments I have
received I record my views on the
issue of breach.
[62] I accept Mr Rainey’s argument that there was no procedural
unfairness in the way in which the allegation of a warranty
of compliance with
the Building Code and a breach of that warranty was particularised.
[63] Section 57 of the WHRSA provides that the Tribunal must manage adjudication proceedings in a manner that tends best to ensure that they are speedy, flexible and cost effective. Adjudication is not commenced by the filing of a statement of claim but rather by application, which includes a statement as to the nature and brief description of the claim, and of the parties involved.47 A Tribunal
may conduct the proceedings in any manner it thinks fit,48
including adopting
processes that enable it to perform “an investigative role”. It
may request further written submissions49 and set its own
deadlines,50 and appoint experts.51 It may request
the parties to do things in the course of proceedings to enable the effective
and complete determination of questions.52
[64] It is clear, therefore, that pleading rules that apply to High Court litigation and, are likely in the future to apply to District Court proceedings under the District Court Rules,53 do not apply in the Tribunal. However, s 57(2) provides that in managing adjudication proceedings the Tribunal must comply with the principles of natural justice. Despite the lack of a formal pleading process, there can be no doubt
that a respondent is entitled to know what it is that is being alleged
and what relief is
47 Weathertight Homes Resolution Services Act 2006, s 62(3)(b).
48 Section 73(1)(a).
49 Section 73(1)(b).
50 Section 73(1)(e).
51 Section 73(1)(f).
52 Section 73(1)(i).
being sought so that the
respondent has a fair opportunity to answer the allegations against it and
respond.
[65] I accept Mr Rainey’s submission that in this hearing an allegation of breach of the weathertightness requirements in the Building Code at the time the house was built was clearly signalled through the brief of Mr Gill. Mr Gill, and indeed the assessor Mr Casey, both agreed that the house had been built with defects including the defect recorded by the Tribunal, that the joinery penetrations lacked an adequate
weathertight seal.54 Mr Gill had set out his detailed
investigation of the property in
his evidence. There was as Ms Grant submitted only evidence of moisture
ingress in
2011 when Mr Gill carried out his investigation. However, Mr Gill also
addressed the relevant performance requirements of the Building
Code, and he set
out breaches of those performance requirements.
[66] Mr Gill had viewed the property during deconstruction and had observed the lack of adequate seal to the windows. He set out what he observed in detail. It was a failure to seal junctions and not a deterioration of materials used that had caused the defect. He stated that the defects were contrary to BRANZ55 good practice, and that this was a breach of the performance requirements of the Building Code, cls E2 and B2. He elaborated on how this had arisen. His evidence in this regard was
consistent with that of the assessor, who observed that moisture could enter
along the
PVC sill junctions where they were not sealed to the vertical jamb
junction.
[67] I conclude therefore that there was clear notice given to the words
of these alleged failings prior to the hearing. Although
it is correct that
they were not detailed in opening submissions, there is nothing to show that
this resulted in unfairness. It
was open to the Wards to call an expert
disputing Mr Gill’s evidence if they had wished to do so, but they did not
do so.
[68] The wording of the Building Code at E2.2 and E2.3.2 is
clear:
54 Saffioti v Ward, above n 1, at [11].
FUNCTIONAL REQUIREMENT
E2.2 Buildings shall be constructed to provide adequate
resistance to penetration by, and the accumulation of, moisture from the
outside.
PERFORMANCE
E2.3.2 Roofs and exterior walls shall prevent the penetration of water that
could cause undue dampness, or damage to building elements.
[69] It seems to me that a window which has joins with inadequate
sealant, with the consequence that at some stage, which might
not be immediate
but in the future, there can be water ingress, will not be weathertight whether
or not there are leaks immediately.
I conclude there was evidence that when the
house was built there was a lack of compliance with the Building Code and that
the weathertightness
defects led to loss. In my view that was sufficient to
establish a breach.
[70] I emphasise that this is not necessarily inconsistent with the
Tribunal’s views. It may well have been that the intention
of the Tribunal
was to say no more than that there was no actual leaking at the time of
construction. The Tribunal did not
necessarily go so far as to say that this
meant that there was no breach; clearly the fact that there was no actual
leaking taking
place did not mean that the building was in fact weathertight.
If there were failures to seal joins properly, and for one reason
or another it
took some years for water to find its way through those defectively built
joints, there was still a breach of the Building
Code.
[71] Thus, I would have upheld Mr Rainey’s submissions on this
point if the issue
of breach had been material to this appeal.
The Heron appeal
[72] Mr Heron was an employee of ABC. At the time the house was built, ABC was the approved building certifier under s 51 of the Building Act 1991. Mr Heron was one of a number of building control officers employed by ABC. He was one of six designated signatories approved by the Building Industry Authority to sign building certificates and CCC’s issued by ABC. He was not a director or shareholder of ABC, and did not have a senior management role. However, he was clearly a
senior certifier. He would receive information from other ABC employees
working in the field, consider that information, and sign
certificates.
[73] In relation to the construction of the Wards’ house, he signed
on the building certificate “on behalf”
of ABC that the proposed
building work would comply with the list of provisions of the Building Code if
properly completed in accordance
with the listed plans. He also signed
“for and on behalf of” ABC the CCC issued by ABC.
[74] The ABC job cards record 15 building inspections carried out on 11
separate dates during the process of construction of the
Wards’ house.
These were all carried out by a lower level employee of ABC, Martin
Cleary, apart from a drainage
inspection which was carried out by Mr Heron.
That inspection was not connected to any of the defects that contributed to the
leaks.
In addition to the building inspections, there was also a final
document vetting check which was approved by Mr Cleary and provided
to Mr Heron
before he signed the CCC.
[75] Mr Rainey submitted that by signing the certificate and CCC, Mr
Heron assumed responsibility for the proposed building work
to comply with the
applicable provisions of the Building Code. He submitted that there
were no reasonable grounds for
Mr Heron to have been satisfied that
weathertightness had been achieved. Mr Heron represented himself before both
the
Tribunal and this Court56 and submitted that no blame could be
placed on him for any failure to note the defects.
[76] It is undoubtedly arguable that Mr Heron could have owed the Saffiotis a duty of care. However, it is not necessary to consider that issue further as it is clear that even if such a duty existed, there was no breach of it by Mr Heron. By signing the certificate on behalf of ABC in accordance with his obligations as an employee, Mr Heron was not assuming a warranty obligation as to the fitness of the work done, to subsequent purchasers. The actual act of signing was perhaps more than the
“formality” indicated by the Tribunal, but nevertheless was
a step taken by Mr Heron
56 See my Minute of 9 October 2013.
where he was entitled to rely on reports of others, and where there was
nothing to suggest to him that there had not been compliance.
[77] There was no evidence before the Tribunal that Mr Heron did anything
wrong when he signed the CCC. In particular, as Mr
Rainey fairly acknowledged,
there was no evidence that he failed to follow what was the usual professional
course of conduct in signing
the document. He appears to have had appropriate
information before him in the form of processing sheets and other documents from
employees of ABC, all of which indicated compliance with the Building
Code.
[78] It seems also that a final review of the plans was carried out by
another employee of ABC, a Mr Nick Ward who was a building
control officer. Mr
Ward has signed a “scope of building certifiers engagement” form
which is attached to the building
certificate.
[79] Mr Heron’s role in signing the certificate was to ensure that
the reviews by ABC staff had been carried out. It was
not to actually perform
that function himself or in some way audit on site the checks already carried
out by other employees.
[80] ABC was a certifier under the Act. It was audited on a yearly basis
by the Building Industry Authority. It had a duty of
care and may well have
breached it, but its employees, including its approved certifiers, did not
assume strict liability for their
employer’s errors. Mr Heron had
material before him which indicated that there had been compliance with the
building consent
and that it was appropriate for ABC to issue the permit.
He signed accordingly. I agree with the Tribunal’s conclusion
that
in those circumstances there was no evidence that Mr Heron breached any
duty of care.
[81] If Mr Rainey is right about Mr Heron, then employees who are guilty
of no negligence at all can be required to assume absolute
responsibility for
the errors of their employers. There is no legal principle or policy
consideration that could support
such absolute liability.
[82] The claim against Mr Heron was properly dismissed.
Result
[83] The appeal is dismissed.
[84] The parties’ will I have no doubt endeavour to settle costs.
I would expect that they would follow the event and that
there would be a 2B
award in favour of the first respondents. However, I will reserve the question
of costs. If the parties cannot
agree the respondent is to file submissions
within 14 days, and the appellant within a further 14
days.
...................................
Asher J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2013/2831.html