NZLII Home | Databases | WorldLII | Search | Feedback

High Court of New Zealand Decisions

You are here:  NZLII >> Databases >> High Court of New Zealand Decisions >> 2023 >> [2023] NZHC 2418

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Intop Homes Limited v Lot 77 Limited [2023] NZHC 2418 (31 August 2023)

Last Updated: 7 September 2023

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
CIV-2023-404-640
[2023] NZHC 2418
BETWEEN
INTOP HOMES LIMITED
Plaintiff
AND
LOT 77 LIMITED
Defendant
Hearing:
25 July 2023
Appearances:
E MacPherson for the Plaintiff J P Wood for the Defendant
Judgment:
31 August 2023

JUDGMENT OF ASSOCIATE JUDGE C B TAYLOR

Application that caveat not lapse

This judgment was delivered by me on 31 August 2023 at 3:00pm

pursuant to Rule 11.5 of the High Court Rules

............................... Registrar/Deputy Registrar

Solicitors:

INTOP HOMES LIMITED v LOT 77 LIMITED [2023] NZHC 2418 [31 August 2023]

TABLE OF CONTENTS

Paragraph

Introduction [1]

Background [2]

Intop’s application for order that caveat not lapse [5]

Affidavit of Geng Wu, dated 6 April 2023 [7]

Lot 77’s opposition [18]

Affidavit of David Duggan, dated 2 May 2023 [19]

Reply affidavit of Gen Wu, dated 9 May 2023 [26]

Legal principles [32]

Analysis [38]

Does Intop have a caveatable interest in the property? [40]

Determination of the issues [41]

Issuing of invoices [42]

Conclusion in respect of issuing invoices [52]

Disputed debts [54]

Conclusion in respect of disputed debts [58]

A caveatable security interest [60]

Conclusion in respect of caveatable interest [66]

Cancellation of the contracts [69]

Conclusion in respect of cancellation [76]

Discretion to remove the caveat [77]

Result [79]

Orders [80]

Introduction

Background

  1. Intop Homes Ltd v Lot 77 Ltd HC Auckland CIV-2023-404-640, 18 April 2023 (Minute of Gault J).

Intop’s application for order that caveat not lapse

(a) Intop has a contractual right to lodge a caveat pursuant to clauses 123 and 124 of two Master Builders Association contracts dated 10 June 2021 (the Contracts) entered into with David Rennie Duggan (David) / Lot 77 Limited (Lot 77) respectively for the Land.

(b) On 17 February 2023 Intop issued:

(i) Two invoices for units 3, 4 and 15 on the Land under the Contracts; and

(ii) One invoice in respect of Units 1 and 2 on the Land under the Contracts.

(Invoices)

(c) Lot 77 failed to pay the invoices on the due date totalling $73,027.38.

(d) Pursuant to clause 123, where Lot 77/David fails to pay on the due date for payment, then on demand Lot 77/David must straight away provide Intop with an executed and registrable memorandum of mortgage over the Land as described in the Contracts.

(e) Pursuant to clause 124, Intop is entitled to register a caveat against the title to the Land in circumstances where Lot 77/David is entitled to demand a registrable memorandum of mortgage.

(f) Intop is entitled to demand a registerable memorandum of mortgage.

(g) On 14 March 2023 Intop lodged the Caveat against the Land.

(h) On 27 March 2023 Land and Information New Zealand notified Intop that Lot 77 had applied to lapse the Caveat.

(i) Pursuant to its rights under the Contracts, Intop is entitled to sustain the Caveat.

2 Originating application that caveat not lapse dated 6 April 2023 at [1].

3 At [2].

Affidavit of Geng Wu dated 6 April 2023

$73,027.38 for building work completed for Lot 77.

4 Affidavit in support of originating application that caveat not lapse dated 6 April 2023.

Lot 77’s opposition

I. No caveatable interest

  1. The caveat has been lodged pursuant to two building contracts between Intop Homes and David Duggan each on a Master Builders standard form Residential Building Contract RBC1 — 2018 (New Build) for building two units (the "Unit 1 and 2 Contract) and three units (the "Unit 3, 4 and 15 Contract") (together "the Contracts");
  1. The true construction of the security interest in the Contracts is contingent, in that:
  1. There must be debt due to Intop Homes under the contract;

5 Notice of opposition dated 2 May 2023.

  1. Notice must given by Intop Homes to Mr Duggan that he is in breach of an obligation to pay that debt on the due date in writing and providing him with 5 working days to remedy the default;
  1. Following the elapse of 5 working days Intop may demand that Mr Duggan provides a registerable memorandum of mortgage;
  1. When Intop Homes has a right to call for a registerable memorandum of mortgage it becomes entitled to register a caveat.
  1. Under the Contracts:
  1. Claims for payment could be issued by way of an invoice at certain fixed stages only. The final stage being after a code compliance certificate was issued for the building works under the Contracts.
  1. An invoice was to be paid within 5 working days after the invoice was issued;
  1. Mr Duggan could dispute payment within 5 working days of the service of an invoice.
  1. On 17 February 2023 Intop Homes issued Mr Duggan 3 invoices that purported to be final payments being:

2023_241800.jpg

  1. Time for payment of the invoices, had they been valid which is denied, was 24 February 2023;
  1. At the time the invoices were issued a code compliance certificate had not been issued for the building works under the Contracts;
  1. On 23 February 2023 Mr Duggan wrote to Intop Homes and disputed the invoices;
  1. On 27 February 2023 Intop Homes lodged a caveat over Unit 2 and Unit 4.
  1. On 6 March 2023 Intop Homes cancelled the Contracts.
  1. Intop Homes had and has no caveatable interest in Unit 2 or Unit 4 as:
  1. There was no debt due under the Contracts as the pre-conditions for issuing a final invoice had not been met;
  1. If the preconditions to issue a final invoice under the Contracts had been met, there was no debt due under the Contracts as Mr Duggan had disputed the invoices;
  1. If the preconditions to issue a final invoice under the Contracts had been met and after 24 February 2023 Mr Duggan was in default of an

obligation to pay, the contingent security interest of Intop Homes did not arise as it failed to provide notice under cl 125 of the Contracts and had no right to call for a registerable memorandum of mortgage or to lodge a caveat;

  1. Once the Contracts were cancelled, Intop Homes no longer has a contingent contractual right to security;

Affidavit of David Duggan dated 2 May 2023

6 Affidavit in support of opposition by David Duggan dated 2 May 2023.

Intop were not genuine, stating that they represent his genuine dissatisfaction with performance below the Registered Master Builder standard.

Reply affidavit of Geng Wu dated 9 May 2023

7 Affidavit of Geng Wu in reply dated 9 May 2023.

proper CCC paperwork was filed and that any slight delays were due to technical issues for which Mr Duggan knew Intop was not responsible.

Legal principles

138 Caveats against dealings with land

(1) A person may lodge a caveat against dealings with an estate or interest in land (a caveat against dealings) on the basis that the person—

(a) claims an estate or interest in the land, whether capable of registration or not; or

(b) has a beneficial estate or interest in land under an express, implied, resulting or constructive trust[.]

...

Caveat against dealings document s 138 of the Act

A description of the nature of the estate or interest claimed by the caveator (which must be stated with sufficient certainty) or, for a caveat under section 138(1)(d)(ii) of the Act, the matters that establish that there is a risk that the estate of interest may be lost through fraud.

Details of how the estate or interest claimed is derived from the registered owner.

Analysis

(a) Does Intop have a caveatable interest in Lot 77’s land?

  1. See generally Philpott v Noble Investments Ltd [2015] NZCA 342 at [26]. And, for a general statement of the principles, see Wallace v Studio New Zealand Ltd [2021] NZCA 392 at [39]–[41].

9 Botany Land Development Ltd v Auckland Council [2014] NZCA 61 at [24]–[25].

10 Bethell v Rickard [2013] NZCA 68 at [22]. See also MacRae v Rapana HC Auckland M633/94, 17 June 1994.

11 Barrett v IBC International Ltd [1995] 3 NZLR 170 (CA) at 175, citing Eng Mee Yong v Letchumanan s/o Velayutham [1979] UKPC 13; [1980] AC 331 (PC) at 341; and Xie v 126 Waimumu Ltd [2020] NZHC 1109 at [8].

12 Pacific Homes Limited (in rec) v Consolidated Joineries Ltd [1996] NZCA 264; [1996] 2 NZLR 652 (CA) at 656.

(b) If so, should the Court exercise its residual discretion to remove the caveat or allow it to lapse?

Does Intop have a caveatable interest in the property?

(a) There was no debt due under the contracts as Intop had not met the pre-conditions required to issue its final invoices;

(b) if Intop was able to issue its final invoices, no debt was due as Lot 77 had disputed the invoices and that dispute had not (and has not since) been resolved;

(c) the contracts provide for only a potential security interest over Lot 77’s land. Intop did not follow the contractual machinery to create the security interest, and therefore, has no caveatable interest in Lot 77’s land;

(d) Intop has cancelled the contracts, and any potential to create a security interest it may have had has not survived cancellation.

Determination of the issues

security interest in Lot 77’s land after cancelling the contracts, and accordingly is an issue which requires determination notwithstanding the findings at [66] to [68] of this judgment.

Issuing of invoices

(a) cl 3 of pt 7 of the contracts states, inter alia, that final payment under the contract will be claimed on the “final” stage;

(b) “final” is not defined in the contracts, but it is reasonably inferred to be practical completion. It is Intop’s position that it was never agreed that final payment would be due on the CCC being issued by the Taupō District Council (the Council);

(c) cl 108 of the contracts provides:

On Practical Completion of the Works and as soon as the Owner has paid to the RMB the Contract Price, the Owner is entitled to immediate possession of the Site and the Works.

This clause is consistent with Intop’s position that payment of the contract price is due on practical completion;

(d) it is otherwise clear from the terms of the contracts that practical completion does not require the issue of the CCC, which is dealt with separately in cl 54 of the contracts.

(a) on a proper interpretation of the contracts, final invoices could not be issued until the CCC was issued by the territorial authority; and

(b) even if the final invoices could be issued on practical completion of the contracts, practical completion in accordance with the contracts had not occurred at the time the final invoices were issued.

means that the Council is reasonably satisfied that the building works comply with the requirements of the building consent.13

(a) As to the objection that the contracts could not have intended to use the issue of the CCC as the trigger as Intop could not control when the Council would issue it, Mr Wood submits that while Intop had no control over the Council’s decision, it was in complete control of making the application and taking such further steps as were necessary to ensure the CCC was issued. Intop was in charge of the works and under cl 54, Lot 77 had given its authority for Intop to act as its agent for the purposes of obtaining the CCC.

(b) The Council must, under the Building Act 2004, issue the CCC when it is satisfied the work complies with the consent within 20 working days of the application for a CCC. If the Council for any reason was not satisfied, the obligation would be on Intop to rectify any issues under the implied warranties in the Building Act, and accordingly its obligations and the right to claim the final payment cannot be said to have been discharged until the Council gives its approval through the issue of the CCC.

13 Building Act 2004, s 94.

Conclusion in respect of issuing invoices

(a) I accept Mr Wood’s argument that if the parties had intended practical completion to be the trigger for the issue of the final invoices, then it would be logical that they would have referred to the defined term in the contracts. I also agree with Mr Wood that if practical completion is not the trigger for the issue of final invoices, the logical trigger is the issue of the CCC by the Council, as this is the point at which the Council considers the works are completed in accordance with the building consent.

(b) Even if practical completion is the correct trigger for the issue of the final invoices, I agree with Mr Wood’s submission that practical

completion had not been achieved in accordance with cl 106 of the contracts at the time Intop issued the invoices, as Intop failed to issue the correct notice pursuant to cl 106 of the contract, and either have it signed by Lot 77 or allowed the five working day period to elapse resulting in practical completion being deemed to have occurred.

Disputed debts

(a) pursuant to cl 29 of the contracts, if Lot 77 wanted to dispute the amounts claimed by Intop, it was required to serve a payment schedule on Intop within five working days of the invoices — and Lot 77 did not serve any payment schedule;

(b) the only response to the invoices from Lot 77 was a letter from Lot 77’s then lawyer, dated 23 February 2023 (the Lot 77 Letter), which only disputed an amount of $5,750 under the invoices. Even if the Lot 77 Letter could be deemed a payment schedule there remains an amount of $67,277.38 payable under the invoices that is not disputed;

(c) the Lot 77 Letter otherwise:

(i) raises a claim for additional costs incurred of $7,150;

(ii) raises a claim for additional costs being incurred, estimated at

$32,250;

(iii) claims a failure to carry out the works to specification to a value of $12,500; and

(iv) alludes to a possible claim for delay which has not been pursued by Lot 77.

Mr Macpherson submits that these claims do not avoid the invoices being due as pursuant to cl 33 of the contracts Lot 77 has no entitlement to set-off.

(d) The invoices total $73,027.38 and the total of Lot 77’s claims is

$57,650, and accordingly on Lot 77’s best case, the set-off if available, leaves an undisputed amount of $15,377.38 which is payable.

(e) Of the $57,650 particularised in the Lot 77 Letter, $20,000 relates to an estimated cost to obtain a Master Builder’s Guarantee for the five units, which was never part of the agreement under the contracts. Accordingly, the undisputed portion of Lot 77’s best case is actually

$35,377.38.

(a) payment claims under the CCA are subject to formal requirements and in particular must state that it is a claim made under the CCA as required by s 20(2)(f) which is a mandatory requirement, and must also be accompanied by the prescribed statutory information required by

s 20(3) and (4). The invoices did not comply with these requirements and are therefore not payment claims. Accordingly, cl 29 of the contracts is not engaged.

(b) The election by Intop to avoid the CCA regime could not have been intended to leave Lot 77 with no mechanism to dispute invoices that were incorrectly issued, and accordingly recourse should then be had to the dispute resolution mechanisms of the contracts which were then engaged and the dispute must follow the path of cls 130 to 136 of the contracts. Accordingly, until the dispute is resolved, the debt cannot be due and owing.

Conclusion in respect of disputed debts

(a) Mr Wood is correct that the invoices were not payment claims for the purposes of the CCA and accordingly cl 29 of the contracts was not engaged.

(b) Mr Wood is correct in his proposition that the dispute of the invoices by the Lot 77 Letter engaged cls 130 to 136 of the contracts. In my view, Mr Wood is also correct that the disputed invoices were not due and payable until the dispute had been resolved.

A caveatable security interest

no right to call for a registrable mortgage or to lodge a caveat. He submits Lot 77’s position is inconsistent with the terms of the contracts:

(a) Pursuant to cl 123:

If the Owner fails to pay any money payable to the RMB under this Building Contract on due date for payment, then on demand the Owner will straight away provide the RMB with an executed and registrable memorandum of mortgage over the Land...

(b) It is not disputed that Lot 77 failed to pay the invoices when due.

(c) Clause 124 then provides that:

... the RMB is entitled to register a caveat ... against the title to the Land in circumstances where the RMB is entitled to demand a registrable memorandum of mortgage.

(d) Accordingly, Intop has a caveatable interest which arose on Lot 77’s failure to pay invoices on their due date entitling Intop to demand a registrable memorandum of mortgage. Intop’s caveatable interest is not dependent on giving notice to remedy or calling for a registrable memorandum of mortgage as alleged by Lot 77.

(a) any notice was redundant as Lot 77 had already notified Intop that it would not pay the invoices by means of the Lot 77 Letter in response to the invoices;

(b) on 27 February 2023, Mr Duggan sent an email to Mr Wu which reinforced Lot 77’s refusal to pay the invoices and advising that, in the absence of an agreed resolution, the matter should be determined by mediation, arbitration or litigation. In addition, on 27 February 2023, Lot 77’s lawyers sent an email to Intop’s lawyers stating that Lot 77 had served a notice of dispute pursuant to cl 130 of the contracts, again reinforcing Lot 77’s refusal to pay the invoices. Lot 77 had already

transferred unit 15 and, in response, Intop had to lodge the caveat to protect its position;

(c) Intop’s non-compliance with cl 125 of the contracts does not extinguish Intop’s caveatable interest or the lodgement of a caveat. In any event, if Intop is in breach of cl 125 of the contracts, Lot 77 has not suffered any prejudice or loss from such breach as all that Lot 77 lost was an opportunity to remedy its own breach by paying the invoices, which Lot 77 clearly was not going to do.

(a) money is payable to the contractor;

(b) the due date for payment must have passed without payment;

(c) the contractor has issued a demand for payment in writing and provided the owner with five working days’ notice to remedy its default;

(d) the five day notice must have elapsed.

that Mr Wu’s evidence makes it clear that Intop chose to lodge the caveat as a matter of expediency.

Conclusion in respect of a caveatable security interest

Cancellation of the contracts

(a) on a plain reading of cls 123 and 124 of the contracts, Intop is entitled to register a caveat when Lot 77 fails to pay any money payable under the contracts. There is no question that the money payable under the contracts remains payable following cancellation;

(b) Intop’s caveatable interest is otherwise preserved pursuant to cl 129 of the contracts, which provides that termination is without prejudice to any other rights or remedies the terminating party may have arising from the default.

14 Moeke v South Waikato District Council [2019] NZHC 2282, (2019) 20 NZCPR 385.

15 Whitford Village Holdings Ltd v Coumat Ltd [2015] NZHC 1787.

agreements for sale and purchase of land, and do not automatically extend to other agreements such as the building contracts in the present circumstances. He submits that this is because under the normal ADLS sale and purchase agreement, where a party is faced with cancelling a contract, they can either choose to affirm the contract (despite any breach) or cancel it and seek damages.

(i) there must have been no impediment, by unfilled condition or otherwise, to the enforcement of the right at the point of rescission or discharge; and

(ii) enforcement must not have been subject to any reciprocal obligation on the part of the enforcing party.

16 Garratt v Ikeda [2001] NZCA 316; [2002] 1 NZLR 577 (CA) at [5]–[7].

out that, again if the Court accepts the proposition that Intop only had a contingent interest in the property, it is not necessary to contend that an accrued right which can support a caveat is terminated on cancellation. Lot 77’s point is that there was no accrued right and Intop cannot now rely on the contractual machinery under the cancelled contract to put itself in the position of possessing that right. Put another way, Intop — like the purchasers in Moeke and Whitford Village Holdings — cannot effectively unwind its cancellation and revive its right to perfect its interest under the cancelled contract.

Conclusion in respect of cancellation

Discretion to remove the caveat

Result

[52] while not determinative in disposal of the application, my view is that Intop were not entitled to issue final invoices. And further as I have noted at [58], although again not determinative in disposal of the application, my view is that the debts recorded in the invoices were not due and payable.

Orders

................................... Associate Judge Taylor


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/2418.html