You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2023 >>
[2023] NZHC 2418
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Intop Homes Limited v Lot 77 Limited [2023] NZHC 2418 (31 August 2023)
Last Updated: 7 September 2023
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
|
|
BETWEEN
|
INTOP HOMES LIMITED
Plaintiff
|
AND
|
LOT 77 LIMITED
Defendant
|
Hearing:
|
25 July 2023
|
Appearances:
|
E MacPherson for the Plaintiff J P Wood for the Defendant
|
Judgment:
|
31 August 2023
|
JUDGMENT OF ASSOCIATE JUDGE C B TAYLOR
Application that caveat not
lapse
This judgment was delivered by me on 31 August 2023
at 3:00pm
pursuant to Rule 11.5 of the High Court Rules
............................... Registrar/Deputy Registrar
Solicitors:
INTOP HOMES LIMITED v LOT 77 LIMITED [2023] NZHC 2418 [31 August 2023]
TABLE OF CONTENTS
Paragraph
Introduction [1]
Background [2]
Intop’s application for order that caveat not
lapse [5]
Affidavit of Geng Wu, dated 6 April
2023 [7]
Lot 77’s opposition [18]
Affidavit of David Duggan, dated 2
May 2023 [19]
Reply affidavit of Gen Wu, dated 9 May 2023 [26]
Legal principles [32]
Analysis [38]
Does Intop have a caveatable interest in the
property? [40]
Determination of the issues [41]
Issuing of invoices [42]
Conclusion in respect of issuing invoices [52]
Disputed debts [54]
Conclusion in respect of disputed debts [58]
A caveatable security interest [60]
Conclusion in respect of caveatable interest [66]
Cancellation of the contracts [69]
Conclusion in respect of cancellation [76]
Discretion to remove the caveat [77]
Result [79]
Orders [80]
Introduction
- [1] Intop
Homes Ltd (Intop) has applied for an order sustaining caveat number
12677045.1 (the caveat) lodged by them against two units owed by Lot 77
Ltd (Lot 77) with the records of title 1006681 (unit 2) and
1006683 (unit 4) (together, Lot 77’s land).
Background
- [2] Intop
is a commercial and residential construction company that agreed to construct
units for Lot 77 in accordance with standard
Master Builders Association
contracts. Intop says that, in accordance with their contractual rights, they
issued invoices and upon
their non-payment they were entitled to demand a
registerable memorandum of mortgage capable of sustaining a caveat, which they
lodged on 14 March 2023. Lot 77 disputes that a caveatable interest exists
claiming the correct contractual process was not followed
and the contract has
now been cancelled. They applied to lapse the caveat on 27 March 2023.
- [3] Initially,
the caveat and this application applied to a further two units with records of
title 1006680 (unit 1) and 1006682 (unit 3). After agreement
between the parties to remove the caveat on those two units, this application
now proceeds only to sustain the
caveat against units 2 and 4.
- [4] Given the
timeframe under the Land Transfer Act 2017 (the Act), Gault J on 18 April
2023 made an order that the caveat not lapse until further order of this
Court.1 This proceeding determines Intop’s application to
sustain the caveat.
- Intop
Homes Ltd v Lot 77 Ltd HC Auckland CIV-2023-404-640, 18 April
2023 (Minute of Gault J).
Intop’s application for order that caveat not
lapse
- [5] Intop
seeks an order that the caveat 12677045.1 affecting dealing ID 12697627 and
records of title 1006681 and 1006683 not lapse.2
- [6] The grounds
on which the order is sought are:3
(a) Intop has a contractual right to lodge a caveat pursuant to clauses 123 and
124 of two Master Builders Association contracts
dated 10 June 2021 (the
Contracts) entered into with David Rennie Duggan (David) / Lot 77 Limited (Lot
77) respectively for the Land.
(b) On 17 February 2023 Intop issued:
(i) Two invoices for units 3, 4 and 15 on the Land under the Contracts; and
(ii) One invoice in respect of Units 1 and 2 on the Land under the Contracts.
(Invoices)
(c) Lot 77 failed to pay the invoices on the due date totalling $73,027.38.
(d) Pursuant to clause 123, where Lot 77/David fails to pay on the due date for
payment, then on demand Lot 77/David must straight
away provide Intop with an
executed and registrable memorandum of mortgage over the Land as described in
the Contracts.
(e) Pursuant to clause 124, Intop is entitled to register a caveat against the
title to the Land in circumstances where Lot 77/David
is entitled to demand a
registrable memorandum of mortgage.
(f) Intop is entitled to demand a registerable memorandum of mortgage.
(g) On 14 March 2023 Intop lodged the Caveat against the Land.
(h) On 27 March 2023 Land and Information New Zealand notified Intop that Lot 77
had applied to lapse the Caveat.
(i) Pursuant to its rights under the Contracts, Intop is entitled to sustain the
Caveat.
2 Originating application that caveat not lapse dated 6 April 2023
at [1].
3 At [2].
Affidavit of Geng Wu
dated 6 April 2023
- [7] Mr Geng
(Henry) Wu (Mr Wu), director of Intop, has made an affidavit in support
of Intop’s application that the caveat not lapse.4 He deposes
that Intop is owed
$73,027.38 for building work completed for Lot 77.
- [8] Mr Wu
deposes that Intop was engaged to build units on Lot 77’s land and
executed two standard Master Builders Association
contracts to that effect on 10
June 2021. He says construction commenced around May 2021 and Intop invoiced Lot
77 monthly for works.
He says that construction was affected by COVID and that
the expected completion date was extended without issue to February
2023.
- [9] Having
achieved practical completion of the units in mid-February, Mr Wu says Intop was
entitled to issue final invoices under
cl 108 of the contracts, which they
issued in three invoices on 17 February 2023 with payment due by 24 February
2023.
- [10] On 24
February 2023, Mr Wu deposes he received a letter, dated 23 February, from Lot
77’s then lawyers advising that Lot
77 refused to pay and suggesting an
80 per cent reduction as Intop was charging for work which had not been
completed or was completed
late. The letter maintained that Intop was not able
to issue final invoices absent issuance of code compliance certificates
(CCC), a view of the contractual provisions which Mr Wu disputes. Mr Wu
says his lawyer then emailed in response stating that Lot 77 could
not take
possession unless the invoices were fully paid. He notes that a CCC for one
unit, unit 15, was issued on 24 February 2023.
- [11] On 25
February 2023, Intop’s project manager went to meet with Lot 77’s
director, Mr David Duggan (Mr Duggan), who admitted he had possession of
all units’ keys and refused to return them. Mr Wu says that Mr Duggan then
emailed with
a list of concerns and alleged breaches of contract, which he did
not regard as genuine.
- [12] Mr Wu says
a search of title shows that unit 15 was sold and title changed, without
Intop’s knowledge or consent, as soon
as the CCC was issued and before
Intop was paid or had even sent its letter on 24 February 2023.
4 Affidavit in support of originating application that caveat not
lapse dated 6 April 2023.
- [13] Given
occupation had occurred, Mr Wu says Intop issued a notice to vacate in
accordance with cl 109 to which Lot 77 responded
with a dispute notice under cl
130 and mediation begun.
- [14] Given unit
15’s sale and Intop’s concern other units would be sold without
their consent, Mr Wu says Intop lodged
the caveat on four units’ titles on
27 February 2023. He claims they were entitled to demand a memorandum of
mortgage and lodge
a caveat as they had not been paid. Land Information New
Zealand (LINZ) confirmed on 14 March 2023 that the caveat had been
issued.
- [15] Mr Wu
deposes that on 6 March 2023 Intop exercised its right to cancel the contracts
within the contractual two working day window,
given Lot 77 had not
paid.
- [16] Mr Wu then
lays out subsequent correspondence attempting to resolve the dispute between the
parties and engage in mediation.
- [17] Mr Wu
received notice that Lot 77 had applied to lapse the caveat on 27 March 2023,
which Intop lodged this application to prevent.
He says while mediation is
ongoing to resolve their disputes, Intop is entitled to rely on the contract to
lodge a caveat to protect
its interests and recover payment of the
invoices.
Lot 77’s opposition
- [18] Lot
77 opposes the application on the following grounds:5
I. No caveatable interest
- The
caveat has been lodged pursuant to two building contracts between Intop Homes
and David Duggan each on a Master Builders standard
form Residential Building
Contract RBC1 — 2018 (New Build) for building two units (the "Unit 1 and 2
Contract) and three units
(the "Unit 3, 4 and 15 Contract") (together "the
Contracts");
- The
true construction of the security interest in the Contracts is contingent, in
that:
- There
must be debt due to Intop Homes under the contract;
5 Notice of opposition dated 2 May 2023.
- Notice
must given by Intop Homes to Mr Duggan that he is in breach of an obligation to
pay that debt on the due date in writing and
providing him with 5 working days
to remedy the default;
- Following
the elapse of 5 working days Intop may demand that Mr Duggan provides a
registerable memorandum of mortgage;
- When
Intop Homes has a right to call for a registerable memorandum of mortgage it
becomes entitled to register a caveat.
- Under
the Contracts:
- Claims
for payment could be issued by way of an invoice at certain fixed stages only.
The final stage being after a code compliance
certificate was issued for the
building works under the Contracts.
- An
invoice was to be paid within 5 working days after the invoice was
issued;
- Mr
Duggan could dispute payment within 5 working days of the service of an
invoice.
- On
17 February 2023 Intop Homes issued Mr Duggan 3 invoices that purported to be
final payments being:
- Time
for payment of the invoices, had they been valid which is denied, was 24
February 2023;
- At
the time the invoices were issued a code compliance certificate had not been
issued for the building works under the Contracts;
- On
23 February 2023 Mr Duggan wrote to Intop Homes and disputed the
invoices;
- On
27 February 2023 Intop Homes lodged a caveat over Unit 2 and Unit 4.
- On
6 March 2023 Intop Homes cancelled the Contracts.
- Intop
Homes had and has no caveatable interest in Unit 2 or Unit 4 as:
- There
was no debt due under the Contracts as the pre-conditions for issuing a final
invoice had not been met;
- If
the preconditions to issue a final invoice under the Contracts had been met,
there was no debt due under the Contracts as Mr Duggan
had disputed the
invoices;
- If
the preconditions to issue a final invoice under the Contracts had been met and
after 24 February 2023 Mr Duggan was in default
of an
obligation to
pay, the contingent security interest of Intop Homes did not arise as it failed
to provide notice under cl 125 of the
Contracts and had no right to call for a
registerable memorandum of mortgage or to lodge a caveat;
- Once
the Contracts were cancelled, Intop Homes no longer has a contingent contractual
right to security;
Affidavit of David
Duggan dated 2 May 2023
- [19] Mr Duggan,
director of Lot 77, has made an affidavit in support of Lot 77’s
opposition.6 He accepts that an interim arrangement has been made
which means Intop has released the caveat over units 1 and 3 and therefore this
application only relates to units 2 and 4.
- [20] Mr Duggan
deposes he has paid the sum of $87,023, being the total disputed invoice amounts
regarding units 1, 2, 3, 4 and 15
alongside Intop’s estimated legal costs,
also disputed, into a trust fund in good faith. He says he has done so in the
hope
that Lot 77 can proceed with all units’ sales, which the caveat over
units 2 and 4 is inhibiting. He claims that Intop’s
application to oppose
the caveat lapsing is an abuse of process, in bad faith and an attempt to bypass
the contractual dispute mechanism.
- [21] On the
contracts, Mr Duggan generally agrees that they were entered into but disputes
that work started around May 2021, claiming
it was October 2021 instead. He says
despite the impacts of COVID being well known by then, Intop agreed to
completion by mid-March
and no extensions were agreed to. He says that while the
contracts generally provided for monthly payments the parties specified
a
different formula based on the completion of various stages.
- [22] On the
disputed final invoices, Mr Duggan agreed they were issued but says the contract
did not permit that as there was no agreement
they could be issued upon
practical completion and the majority of the work had not been fully completed.
His understanding was that
CCC issuance was required before final payment was
due. While Intop could not control when the CCC would be issued, he says it was
Intop’s job under the contract to apply for them. He disagrees that his
concerns raised with
6 Affidavit in support of opposition by David Duggan dated 2 May
2023.
Intop were not genuine, stating that they represent his genuine dissatisfaction
with performance below the Registered Master Builder
standard.
- [23] On the
caveatable interest, Mr Duggan agreed that the caveats were lodged and that
Intop eventually cancelled the contract. He
disputes that Lot 77 required
Intop’s consent to sell unit 15 and says that the requisite notice of
default under cl 125 before
a caveatable interest arose was not issued. Thus, Mr
Duggan says he understands that Intop was not entitled to demand a memorandum
of
mortgage or caveat.
- [24] Mr Duggan
appends additional correspondence about the parties’ negotiation and
mediation efforts.
- [25] In
concluding, Mr Duggan asserts that he has paid all possibly disputed amounts
into the trust account and therefore claims Intop
is appropriately secured and
is pursuing its application for the collateral purpose of forcing early
settlement.
Reply affidavit of
Geng Wu dated 9 May 2023
- [26] Mr Wu has
made and affidavit in reply to Mr Duggan’s.7 In it he primarily
explains the mediation agreement reached, which led to this proceeding only
concerning units 2 and 4.
- [27] Mr Wu
disputes that the funds Mr Duggan has set aside are sufficient to cover the
caveat costs or ongoing costs and interest.
He disagrees that this application
is an abuse of process, in bad faith or bypassed the contractual disputes
process.
- [28] Mr Wu
agrees that construction actually commenced in October 2021 and reiterates the
delays caused by COVID.
- [29] Mr Wu
deposes that before all the units were completed Mr Duggan had already begun
residing in unit 3 and using unit 1 as a show
home, so it was disingenuous to
say practical completion was not achieved. He further says that all
7 Affidavit of Geng Wu in reply dated 9 May 2023.
proper CCC paperwork was filed and that any slight delays were due to technical
issues for which Mr Duggan knew Intop was not responsible.
- [30] Regarding
performance below the Master Builder guarantee, Mr Wu says that Mr Duggan did
not decide to include the Master Builder
guarantee when offered it based on the
cost involved.
- [31] In
conclusion, Mr Wu again reiterates that the caveat was necessary in light of the
rapid sale of unit 15 and was correctly lodged
in good faith and in accordance
with the contractual requirements. He reaffirms that the amounts paid into the
trust by Mr Duggan
are insufficient.
Legal principles
- [32] Section
138 of the Land Transfer Act 2017 provides, relevantly:
138 Caveats against dealings with land
(1) A person may lodge a caveat against dealings with an estate or interest
in land (a caveat against dealings) on the basis that the
person—
(a) claims an estate or interest in the land, whether capable of registration or
not; or
(b) has a beneficial estate or interest in land under an express, implied,
resulting or constructive trust[.]
...
- [33] Schedule 2
of the Land Transfer Regulations 2018 provides:
Caveat against dealings document s 138 of the Act
A description of the nature of the estate or interest claimed by the caveator
(which must be stated with sufficient certainty) or,
for a caveat under section
138(1)(d)(ii) of the Act, the matters that establish that there is a risk that
the estate of interest
may be lost through fraud.
Details of how the estate or interest claimed is derived from the registered
owner.
- [34] The
principles governing the determination of applications to sustain caveats are
well-established.8 The onus is on the caveator to demonstrate an
interest in the land that suffices to support the caveat, and the caveator must
demonstrate
a reasonably arguable case to support the claimed interest.9
This means the caveator need not definitively establish their right to the
interest.
- [35] The process
by which applications to sustain a caveat are determined is ill-suited to
resolving disputed factual questions. An
order for removal will only be made if
it is clear the caveat cannot be maintained — either because there was no
valid ground
for its lodging in the first place, or because the ground on which
it was lodged has now ceased to exist.
- [36] Although
the onus of proof lies with the caveator, any conflict between affidavits will
generally be resolved in the caveator’s
favour.10 This is not
to say that the Court is bound to accept uncritically statements in an affidavit
that lack precision, are equivocal, inconsistent
with the documentary evidence
or other statements of the same deponent, or inherently
improbable.11
- [37] While the
Court retains a residual discretion to remove a caveat or allow it to lapse even
if the caveator has a legitimate and
caveatable interest, that discretion is to
be exercised cautiously. The Court must be completely satisfied removal would
not prejudice
the caveator’s legitimate interests.12
Analysis
- [38] The
issues to be determined in this judgment are:
(a) Does Intop have a caveatable interest in Lot 77’s land?
- See
generally Philpott v Noble Investments Ltd [2015] NZCA 342 at [26]. And,
for a general statement of the principles, see Wallace v Studio New Zealand
Ltd [2021] NZCA 392 at [39]–[41].
9 Botany
Land Development Ltd v Auckland Council [2014] NZCA 61 at
[24]–[25].
10 Bethell v Rickard [2013] NZCA 68 at [22]. See also
MacRae v Rapana HC Auckland M633/94, 17 June 1994.
11 Barrett v IBC International Ltd [1995] 3 NZLR 170 (CA)
at 175, citing Eng Mee Yong v Letchumanan s/o Velayutham [1979] UKPC 13; [1980] AC 331
(PC) at 341; and Xie v 126 Waimumu Ltd [2020] NZHC 1109 at [8].
12 Pacific Homes Limited (in rec) v Consolidated Joineries Ltd
[1996] NZCA 264; [1996] 2 NZLR 652 (CA) at 656.
(b) If so, should the Court exercise its residual discretion to remove the
caveat or allow it to lapse?
- [39] I deal with
each of these in turn.
Does Intop have a caveatable interest in the property?
- [40] The issue
of whether Intop has a caveatable interest in the property breaks down into a
series of issues which Lot 77 raises
in asserting that Intop has no caveatable
interest:
(a) There was no debt due under the contracts as Intop had not met the
pre-conditions required to issue its final invoices;
(b) if Intop was able to issue its final invoices, no debt was due as Lot 77 had
disputed the invoices and that dispute had not (and
has not since) been
resolved;
(c) the contracts provide for only a potential security interest over Lot
77’s land. Intop did not follow the contractual machinery
to create the
security interest, and therefore, has no caveatable interest in Lot 77’s
land;
(d) Intop has cancelled the contracts, and any potential to create a security
interest it may have had has not survived cancellation.
Determination of the issues
- [41] In dealing
with the issues set out at [40](a) to (d), I have determined, as set out at [66]
to [68] of this judgment that in
relation to the issue raised at [40](c), Intop
did not have a caveatable interest in Lot 77’s land when it lodged the
caveat
as it did not follow the machinery in the contracts to create such an
interest. While it is not necessary for me to determine the
issues raised in
[40](a) and (b) to dispose of Intop’s application, I have considered these
issues and express my views on
them. As to the issue raised in [40](d), this
issue addresses whether Intop could potentially perfect its
security interest in Lot 77’s land after cancelling the contracts, and
accordingly is an issue which requires determination
notwithstanding the
findings at [66] to [68] of this judgment.
Issuing of invoices
- [42] Mr
Macpherson, for Intop, submits that Intop was entitled to issue the invoices on
practical completion because:
(a) cl 3 of pt 7 of the contracts states, inter alia, that final payment under
the contract will be claimed on the “final”
stage;
(b) “final” is not defined in the contracts, but it is reasonably
inferred to be practical completion. It is Intop’s
position that it was
never agreed that final payment would be due on the CCC being issued by the
Taupō District Council (the
Council);
(c) cl 108 of the contracts provides:
On Practical Completion of the Works and as soon as the Owner has paid to the
RMB the Contract Price, the Owner is entitled to immediate
possession of the
Site and the Works.
This clause is consistent with Intop’s position that payment of the
contract price is due on practical completion;
(d) it is otherwise clear from the terms of the contracts that practical
completion does not require the issue of the CCC, which
is dealt with separately
in cl 54 of the contracts.
- [43] Mr
Macpherson further submits that in any event Intop had applied for the CCC for
each of the units by 7 February 2023 and issued
the invoices on or about 17
February 2023. Insofar as Intop was aware, the CCC has been granted for each of
the units.
- [44] On this
issue Mr Wood, for Lot 77, submits that Intop was not entitled to issue final
invoices for two reasons:
(a) on a proper interpretation of the contracts, final invoices could not be
issued until the CCC was issued by the territorial authority;
and
(b) even if the final invoices could be issued on practical completion of the
contracts, practical completion in accordance with
the contracts had not
occurred at the time the final invoices were issued.
- [45] Mr Wood
expanded on this submission by referring to s 14 of the Construction Contracts
Act 2002 (CCA) under which the parties to construction contracts are free
to set the terms of payment. In this instance the parties had chosen
staged
payment claims payable on particular milestones being reached during the period
of construction. He submits that the parties
had these staged payments as set
out in cl 3 of pt 7 of the contracts: upon signing the contract; upon
foundation; roof up; close-in;
upon gib-board; final.
- [46] Mr Wood
acknowledges that “final” is not a defined term in the contracts and
Intop has invited the Court to read
the word “final” as meaning
“practical completion”. He submits that this approach must be
incorrect as “practical
completion” is a defined term (pt 6, cl
1(l)) and this definition triggers certain obligations under the contracts. He
submits
that if the parties had chosen to line up the final payment with
practical completion they would have done so, with reference to
the defined
term. The fact they did not suggests that some other milestone in the progress
of the construction would be used to trigger
the right to issue the final
invoice.
- [47] Mr Wood
submits that it is unlikely that the parties would have expected final invoices
to be issued before practical completion,
and therefore consideration needs to
be given to events that occur after practical completion that could trigger the
issue of a final
invoice. He submits the correct event is the issue of the CCC
by the Council, this being an appropriate trigger for the issue of
a final
invoice, as the issue of the CCC
means that the Council is reasonably satisfied that the building works comply
with the requirements of the building consent.13
- [48] Mr Wood
makes the following further submission in answer to objections raised by Intop
in respect of using the issue of the CCC
by the Council as the trigger to issue
final invoices:
(a) As to the objection that the contracts could not have intended to use the
issue of the CCC as the trigger as Intop could not
control when the Council
would issue it, Mr Wood submits that while Intop had no control over the
Council’s decision, it was
in complete control of making the application
and taking such further steps as were necessary to ensure the CCC was issued.
Intop
was in charge of the works and under cl 54, Lot 77 had given its authority
for Intop to act as its agent for the purposes of obtaining
the CCC.
(b) The Council must, under the Building Act 2004, issue the CCC when it is
satisfied the work complies with the consent within 20 working days of the
application for a CCC. If the
Council for any reason was not satisfied, the
obligation would be on Intop to rectify any issues under the implied warranties
in
the Building Act, and accordingly its obligations and the right to claim the
final payment cannot be said to have been discharged until the Council
gives its
approval through the issue of the CCC.
- [49] Mr Wood
then submits that even if the trigger for invoice’s issue is the
achievement of practical completion, practical
completion had not been achieved
in terms of the contracts. He submits that page 4 of the contracts has a
checklist of what is required
of the builder on practical completion, it must:
issue a notice of practical completion (cl 106); provide details of ongoing
maintenance
requirements; give copies of guarantees and warranties; provide
details of any applicable insurance.
13 Building Act 2004, s 94.
- [50] Mr Wood
submits that Intop did not issue a notice of practical completion and nor has it
provided evidence that the other requirements
have been met. He submits that the
issuing of a notice of practical completion is mandatory under cl 106 and it
needs to be countersigned
by the owner, who cannot unreasonably withhold its
signature. If the owner does not sign the notice or does not provide a reason
why it will not be signed, practical completion is deemed to have occurred
within five working days after the notice is issue (cl
107), and therefore,
practical completion cannot happen before expiry of the five working days
period.
- [51] In summary,
Mr Wood submits that practical completion is not the trigger entitling Intop to
issue the final invoices, as issue
of the CCC by the Council was the logical
trigger for issuing them. He further submits even if practical completion was
the trigger
for issue of the final invoices, practical completion had not been
achieved in terms of the contracts.
Conclusion in respect of issuing invoices
- [52] As I have
noted at [41], it is not necessary for me to decide whether the final invoices
were validly issued by Intop to dispose
of Intop’s application. However,
I express the following views:
(a) I accept Mr Wood’s argument that if the parties had intended practical
completion to be the trigger for the issue of the
final invoices, then it would
be logical that they would have referred to the defined term in the contracts. I
also agree with Mr
Wood that if practical completion is not the trigger for the
issue of final invoices, the logical trigger is the issue of the CCC
by the
Council, as this is the point at which the Council considers the works are
completed in accordance with the building consent.
(b) Even if practical completion is the correct trigger for the issue of the
final invoices, I agree with Mr Wood’s submission
that practical
completion had not been achieved in accordance with cl 106 of the contracts at
the time Intop issued the invoices, as Intop failed
to issue the correct notice
pursuant to cl 106 of the contract, and either have it signed by Lot 77 or
allowed the five working day
period to elapse resulting in practical completion
being deemed to have occurred.
- [53] Therefore,
I am of the view that Intop was not entitled to issue the final invoices when it
did so.
Disputed debts
- [54] Mr
Macpherson rejects Lot 77’s allegation that there was no debt due under
the contracts because Lot 77 had disputed the
invoices. Mr Macpherson submits
this position is incorrect for the following reasons:
(a) pursuant to cl 29 of the contracts, if Lot 77 wanted to dispute the amounts
claimed by Intop, it was required to serve a payment
schedule on Intop within
five working days of the invoices — and Lot 77 did not serve any payment
schedule;
(b) the only response to the invoices from Lot 77 was a letter from Lot
77’s then lawyer, dated 23 February 2023 (the Lot 77 Letter), which
only disputed an amount of $5,750 under the invoices. Even if the Lot 77 Letter
could be deemed a payment schedule there
remains an amount of $67,277.38 payable
under the invoices that is not disputed;
(c) the Lot 77 Letter otherwise:
(i) raises a claim for additional costs incurred of $7,150;
(ii) raises a claim for additional costs being incurred, estimated at
$32,250;
(iii) claims a failure to carry out the works to specification to a value of
$12,500; and
(iv) alludes to a possible claim for delay which has not been pursued by Lot
77.
Mr Macpherson submits that these claims do not avoid the invoices being due as
pursuant to cl 33 of the contracts Lot 77 has no entitlement
to set-off.
(d) The invoices total $73,027.38 and the total of Lot 77’s claims is
$57,650, and accordingly on Lot 77’s best case, the set-off if available,
leaves an undisputed amount of $15,377.38 which is
payable.
(e) Of the $57,650 particularised in the Lot 77 Letter, $20,000 relates to an
estimated cost to obtain a Master Builder’s Guarantee
for the five units,
which was never part of the agreement under the contracts. Accordingly, the
undisputed portion of Lot 77’s
best case is actually
$35,377.38.
- [55] In the
circumstances, Mr Macpherson submits that the full amount of the invoices
remains due and owing, giving Intop a caveatable
interest pursuant to cls 123
and 124 of the contracts.
- [56] Mr Wood, on
the other hand, rejects the proposition that invoices were payment claims under
the CCA and Lot 77 was obliged to
issue a payment schedule under cl 29 and did
not do so. He submits that the invoices were not payment claims and, even if
they were,
Lot 77’s response to Intop’s invoices nevertheless met
the requirements of the payment schedule in substance and in timing
—
submitting it substantially complied with s 21 of the CCA.
- [57] Mr Wood
expands on these submissions:
(a) payment claims under the CCA are subject to formal requirements and in
particular must state that it is a claim made under the
CCA as required by s
20(2)(f) which is a mandatory requirement, and must also be accompanied by the
prescribed statutory information required by
s 20(3) and (4). The invoices did not comply with these requirements and are
therefore not payment claims. Accordingly, cl 29 of the contracts
is not
engaged.
(b) The election by Intop to avoid the CCA regime could not have been intended
to leave Lot 77 with no mechanism to dispute invoices
that were incorrectly
issued, and accordingly recourse should then be had to the dispute resolution
mechanisms of the contracts which
were then engaged and the dispute must follow
the path of cls 130 to 136 of the contracts. Accordingly, until the dispute is
resolved,
the debt cannot be due and owing.
Conclusion in respect of disputed debts
- [58] As I have
noted at [41], it is not necessary to decide whether the invoices were due and
owing to dispose of Intop’s application.
However, my views in relation to
this issue are:
(a) Mr Wood is correct that the invoices were not payment claims for the
purposes of the CCA and accordingly cl 29 of the contracts
was not engaged.
(b) Mr Wood is correct in his proposition that the dispute of the invoices by
the Lot 77 Letter engaged cls 130 to 136 of the contracts.
In my view, Mr Wood
is also correct that the disputed invoices were not due and payable until the
dispute had been resolved.
- [59] Accordingly,
in my view the disputed invoices were not due and owing for the purposes of the
contracts. In particular, for the
purposes of cl 123 of the contracts, Lot 77
was not in a position where it has failed to pay any money payable to
Intop.
A caveatable security interest
- [60] Mr
Macpherson rejects Lot 77’s proposition that Intop does not have a
caveatable interest as it failed to provide notice
under cl 125 of the contracts
and had
no right to call for a registrable mortgage or to lodge a caveat. He submits Lot
77’s position is inconsistent with the terms
of the contracts:
(a) Pursuant to cl 123:
If the Owner fails to pay any money payable to the RMB under this Building
Contract on due date for payment, then on demand the Owner
will straight away
provide the RMB with an executed and registrable memorandum of mortgage over the
Land...
(b) It is not disputed that Lot 77 failed to pay the invoices when due.
(c) Clause 124 then provides that:
... the RMB is entitled to register a caveat ... against the title to the
Land in circumstances where the RMB is entitled to demand
a registrable
memorandum of mortgage.
(d) Accordingly, Intop has a caveatable interest which arose on Lot 77’s
failure to pay invoices on their due date entitling
Intop to demand a
registrable memorandum of mortgage. Intop’s caveatable interest is not
dependent on giving notice to remedy
or calling for a registrable memorandum of
mortgage as alleged by Lot 77.
- [61] Mr
Macpherson further submits that while Intop accepts that it did not give formal
notice under cl 125 of the contracts before
registering its caveat,
however:
(a) any notice was redundant as Lot 77 had already notified Intop that it would
not pay the invoices by means of the Lot 77 Letter
in response to the
invoices;
(b) on 27 February 2023, Mr Duggan sent an email to Mr Wu which reinforced Lot
77’s refusal to pay the invoices and advising
that, in the absence of an
agreed resolution, the matter should be determined by mediation, arbitration or
litigation. In addition,
on 27 February 2023, Lot 77’s lawyers sent an
email to Intop’s lawyers stating that Lot 77 had served a notice of
dispute
pursuant to cl 130 of the contracts, again reinforcing Lot 77’s
refusal to pay the invoices. Lot 77 had already
transferred unit 15 and, in response, Intop had to lodge the caveat to protect
its position;
(c) Intop’s non-compliance with cl 125 of the contracts does not
extinguish Intop’s caveatable interest or the lodgement
of a caveat. In
any event, if Intop is in breach of cl 125 of the contracts, Lot 77 has not
suffered any prejudice or loss from such
breach as all that Lot 77 lost was an
opportunity to remedy its own breach by paying the invoices, which Lot 77
clearly was not going
to do.
- [62] Mr Wood, on
the other hand, submits that Intop did not have a caveatable interest in Lot
77’s land and had not followed
the machinery in the contracts to allow
that interest to be created. Mr Wood submits that the process for creating a
security interest
is set out in cls 123 to 127 of the contracts and on an
objective reading of these clauses together, the contractor does not have
a
caveatable interest in the land until:
(a) money is payable to the contractor;
(b) the due date for payment must have passed without payment;
(c) the contractor has issued a demand for payment in writing and provided the
owner with five working days’ notice to remedy
its default;
(d) the five day notice must have elapsed.
- [63] Mr Wood
submits that even if the Court is of the view that the invoices were validly
issued and the amounts claimed under the
invoices were payable, notwithstanding
the dispute raised by Lot 77, Intop had not complied with agreed conditions of
the contract
which allowed it to create a caveatable interest: no notice of
default was issued; self-evidently, Lot 77 did not fail to remedy
the default
notified.
- [64] Mr Wood
acknowledges that while Intop did not need to call for a registrable mortgage
before it could lodge a caveat, Intop had
to be in a position that it had a
right to call for a registrable mortgage and that right would only arise on
default, notice, and
consequent failure to remedy — none of which
occurred. Mr Wood also points out
that Mr Wu’s evidence makes it clear that Intop chose to lodge the caveat
as a matter of expediency.
- [65] Finally on
this issue, Mr Wood submits that to allow the caveat to be sustained in these
circumstances would be to provide Intop
with a right it had not bargained for or
had been agreed to by Lot 77. He submits that by taking this approach, Intop has
already
forced Lot 77 to pay money, more than the total of the invoices, into
its solicitors’ trust account pending resolution of the
dispute. That was
done to allow Lot 77 to progress the sale of the two units originally subject to
the caveat to avoid the consequences
of Lot 77 breaching its agreements for sale
and purchase. He submits that while the caveat remains in place, Lot 77 cannot
progress
the sale of the units still subject to the caveat, and Intop are using
the caveat as a pressure point and unfairly and improperly
relying on such
pressure to enforce payment of a disputed debt.
Conclusion in respect of a caveatable security interest
- [66] In my view,
Intop does not have a caveatable interest in Lot 77’s land. I
consider that Mr Wood’s submissions
that failure by Intop to comply with
the mechanism set out in cls 123 and 125 of the contracts is fatal to the
creation of a caveatable
interest. It is clear from cl 125 that the right to
demand the registrable memorandum of mortgage over the land and register a
caveat
only arises when Intop has given notice under cl 125 and the five working
days cure period has expired without the default being
remedied.
- [67] While Intop
lodging the caveat as a matter of expediency after discovering the transfer of
the title of unit 15 is understandable,
those circumstances do not, in my view,
allow Intop to disregard the contractual mechanism by which a security interest
in Lot 77’s
land sufficient to support a caveat is created. Nor does the
fact that it may have been clear to Intop that Lot 77 did not intend
to pay the
invoices, relieve Intop of the obligation to comply with the terms of cl 125 of
the contracts.
- [68] Accordingly,
I find that Intop did not have a caveatable interest in Lot 77’s land when
it lodged the caveat as it was
not in a position to demand a registrable
mortgage from Lot 77 or lodge the caveat, and the caveat should lapse.
Cancellation of the contracts
- [69] Mr
Macpherson submits that cancellation of the contracts did not affect
Intop’s caveatable interest in the present circumstances
because:
(a) on a plain reading of cls 123 and 124 of the contracts, Intop is entitled to
register a caveat when Lot 77 fails to pay any money
payable under the
contracts. There is no question that the money payable under the contracts
remains payable following cancellation;
(b) Intop’s caveatable interest is otherwise preserved pursuant to cl 129
of the contracts, which provides that termination
is without prejudice to any
other rights or remedies the terminating party may have arising from the
default.
- [70] Mr
Macpherson also seeks to distinguish from the present case the position in the
two authorities relied upon by Lot 77 in support
of its proposition that Intop
no longer has a caveatable interest past cancellation of the contracts. These
were the decisions in
Moeke v South Waikato District Council,14
and Whitford Village Holdings Ltd v Coumat Ltd.15 Mr
Macpherson submits that both decisions concerned a caveatable interest by an
unregistered purchaser under an agreement for sale
and purchase of the land. He
submits it is clear from Associate Judge Sargisson’s observations in
Moeke that the decision is specifically in relation to a pre-registration
purchaser’s equitable interest in land and, in the Whitford Village
Holdings case, there was no discussion on the issue.
- [71] Mr
Macpherson submits that the decisions of Moeke and Whitford Village
Holdings concern a caveatable interest for pre-registration purchasers
under
14 Moeke v South Waikato District Council [2019] NZHC 2282,
(2019) 20 NZCPR 385.
15 Whitford Village Holdings Ltd v Coumat Ltd [2015] NZHC
1787.
agreements for sale and purchase of land, and do not automatically extend to
other agreements such as the building contracts in the
present circumstances. He
submits that this is because under the normal ADLS sale and purchase agreement,
where a party is faced
with cancelling a contract, they can either choose to
affirm the contract (despite any breach) or cancel it and seek damages.
- [72] Mr Wood, on
the other hand, submits that if the Court accepts a proposition that the
contracts only created a contingent security
interest in the land (which I have
determined is the case at [66] to [68]), Intop is also prevented from
retroactively perfecting
that interest if it now attempted to go through the
default notice process under cl 125 of the contracts.
- [73] Mr Wood
submits that while s 43 of the Contract and Commercial Law Act 2017 preserves
the law on the effect of cancellation on
accrued rights, at common law
cancellation avoided the responsibility of both parties’ future
performance and did not wholly
undo any accrued rights of the parties up to the
point of cancellation. However, Mr Wood submits that the Court of Appeal in
Garratt v Ikeda confirmed that for a right to be accrued it must, at the
time of cancellation, meet two requirements:16
(i) there must have been no impediment, by unfilled condition or otherwise, to
the enforcement of the right at the point of rescission
or discharge; and
(ii) enforcement must not have been subject to any reciprocal obligation on the
part of the enforcing party.
- [74] Mr Wood
submits in this case Intop had not fulfilled the conditions required to create a
caveatable interest in the property
at the time it lodged the caveats or when it
cancelled the contracts, and the cancellation of the contracts extinguished
Intop’s
contingent interest in Lot 77’s land.
- [75] As to the
distinction which Mr Macpherson attempted to draw between the present instance
and the situations in Moeke and Whitford Village Holdings
decisions, Mr Wood submits that there is no principled basis for any
distinction between agreements for sale and purchase and cancellation
of any
other contract. He points
16 Garratt v Ikeda [2001] NZCA 316; [2002] 1 NZLR 577 (CA) at
[5]–[7].
out that, again if the Court accepts the proposition that Intop only had a
contingent interest in the property, it is not necessary
to contend that an
accrued right which can support a caveat is terminated on cancellation. Lot
77’s point is that there was
no accrued right and Intop cannot now rely on
the contractual machinery under the cancelled contract to put itself in the
position
of possessing that right. Put another way, Intop — like the
purchasers in Moeke and Whitford Village Holdings — cannot
effectively unwind its cancellation and revive its right to perfect its interest
under the cancelled contract.
Conclusion in respect of cancellation
- [76] My view in
relation to the effect of Intop cancelling the contracts is that, as I have
determined at [66] to [68], that Intop
only had a contingent interest in Lot
77’s land, this contingent interest did not constitute an accrued right
which would survive
cancellation. Applying the test in the Garratt
decision, there is an unfilled condition which attached to Intop’s
right to hold a security interest in Lot 77’s land,
in that it had to
comply with the procedures under cls 123 and 125 of the contracts to perfect its
security interest. As it had not
done so, cancellation invalidated Intop’s
rights in the contracts to create a security interest
post-cancellation.
Discretion to remove the caveat
- [77] Mr
Macpherson argues that if the Court determined that Intop had a caveatable
interest in the land, funds paid into trust by
Lot 77 would not be a sufficient
reason for the Court to exercise its discretion to remove the caveat. As I have
determined that
Intop did not have a caveatable interest in the property, the
issue of exercise of the Court’s discretion to remove the caveat
notwithstanding the existence of a caveatable interest does not arise.
- [78] Similarly,
the submission by Mr Wood as to residual discretion does not arise given my
finding that Intop has no caveatable interest.
Result
- [79] As
a result of the conclusions I have reached at [66] to [68] and [76], I am of the
view that the caveat should be allowed to
lapse. In addition, as I have noted
at
[52] while not determinative in disposal of the application, my view is that
Intop were not entitled to issue final invoices. And
further as I have noted at
[58], although again not determinative in disposal of the application, my view
is that the debts recorded
in the invoices were not due and payable.
Orders
- [80] I
order that the caveat lodged by Intop against Lot 77’s land shall
lapse.
- [81] I direct
counsel to endeavour to agree costs. My view is that costs should follow the
event, and Lot 77 as the successful party
is entitled to costs on a 2B basis
plus disbursements. If costs cannot be agreed within 20 working days of the date
of this judgment,
counsel for Lot 77 shall file a memorandum as to costs (not to
exceed 5 pages) within 5 working days of the expiry of the 20 working
day
period, and counsel for Intop shall file a reply (not to exceed 5 pages ) within
5 working days of receipt of counsel for Lot
77’s memorandum. A decision
on costs will then be made on the papers.
................................... Associate Judge
Taylor
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/2418.html