You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2023 >>
[2023] NZHC 2676
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Newell v Sam Pemberton Civil Limited [2023] NZHC 2676 (26 September 2023)
Last Updated: 13 October 2023
IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY
I TE KŌTI MATUA O AOTEAROA KIRIKIRIROA ROHE
|
CIV-2019-019-813 [2023] NZHC 2676
|
BETWEEN
|
WAYNE WILLIAM NEWELL and DENISE MARION NEWELL
Plaintiff
|
AND
|
SAM PEMBERTON CIVIL LIMITED
Defendant
|
Hearing:
|
17-21 July 2023
|
Appearances:
|
M D Talbot for the Plaintiff
V A Whitfield for the Defendant
|
Judgment:
|
26 September 2023
|
JUDGMENT OF ANDERSON J
This judgment was delivered by me
on 27 September 2023 at 3.00 pm pursuant to Rule 11.5 of the High Court Rules
2016.
....................................
Registrar/Deputy Registrar
Solicitors: Talbot Law Ltd, Hamilton
Bluett Legal, Hamilton
NEWELL v SAM PEMBERTON CIVIL LIMITED [2023] NZHC 2676 [26 September 2023]
TABLE OF CONTENTS
Para No
INTRODUCTION [1]
WITNESSES [5]
LANDSDALE CLAIM [7]
Issues [7]
Factual and technical background [12]
Placement of suitable fill [24]
Geotechnical specifications [31]
Discovery of non-compliant fill [37]
Engineer’s decision on cause of fill failing
specification [67]
Contractual obligations [84]
Preliminary [84]
When were the Addendum Specifications provided? [91]
Contractual position on the Addendum Specifications [96]
Breach of contract [101]
Breach of obligation to meet Addendum Specifications [101]
Breach of implied obligations [103]
Damages for breach of contract [115]
Remediation costs [118]
Right to remedy defective works [119]
Mitigation [123]
Liquidated damages [136]
Legal fees [151]
Tort claim [156]
Conclusion on the Landsdale claim [158]
Interest [159]
RANGITAHI CLAIM [162]
Item (a) – Deduction of $21,625.52 [164]
Item (b) – Deduction of
$3,910 [172]
Item (c) – Deduction of $4,260.75 [178]
Conclusion [182]
OVERALL CONCLUSION [183]
INTRODUCTION
- [1] Mr
and Mrs Newell operated a partnership (the Partnership) providing bulk
earthmoving services from 1979 until Mr Newell’s
recent retirement. Sam
Pemberton Civil Limited (SPC) is a civil works and earthworks contractor. SPC
and its predecessor company
had engaged the Partnership as subcontractor on
numerous projects over approximately 18 years.
- [2] The present
case arises due to disputes between the parties under two such projects, both
residential subdivisions – the
Landsdale development in Horsham Downs,
Hamilton and the Rangitahi development in Raglan. Until these disputes the
parties had a
good working relationship.
- [3] The dispute
in relation to the Landsdale development (the Landsdale Claim) arises because
the Partnership claims it should be
paid outstanding retentions of
$140,139.621 whereas SPC says it is entitled to set-off and
counterclaim for losses
suffered due to the Partnership’s defective works. Specifically, Lots
71–74 at the site contained fill which was unsuitable
and failed to meet
specifications. The net total of SPC’s claim is for $108,775.66. SPC
claims in contract or alternatively
in tort for negligence by the Partnership in
carrying out the earthworks.
- [4] The dispute
in relation to the Rangitahi development (the Rangitahi Claim) is relatively
modest. The Partnership claims a net
sum of $25,543.06 involving certain
disputed deductions made by SPC to an invoice issued by the Partnership. The
primary deduction
relates to an asserted overclaim of quantities for works
undertaken by the Partnership.
WITNESSES
- [5] The
Partnership called only one witness being Mr Newell himself. Mr Newell read his
first brief of evidence plus a brief of evidence
responding to the evidence of
SPC.
- [6] SPC called
five witnesses:
1 All figures are GST inclusive as they were presented this way by
the parties.
(a) Samuel Pemberton, a director and shareholder of SPC. Mr Pemberton gave
evidence of the contractual arrangements between the parties
and the events
giving rise to the disputes.
(b) Anthony Burman, Chief Financial Officer for SPC. Mr Burman provided
calculations of amounts owing and amounts paid by SPC. His
evidence was taken as
read (with a minor correction being made) and these numbers as corrected are now
undisputed.
(c) Nathan Sweetman, a contractor manager employed by SPC. Mr Sweetman assessed
the correct quantities and amount owed to the Partnership
in response to its
invoice on the Rangitahi development.
(d) Andrew Holland, a geotechnical engineer and director and shareholder of HDG
Geo Ltd (HDG). He was involved in relevant events
and provided expert views on
technical aspects including why the Landsdale lots required remediation.
(e) Stephen Crawford, an independent geotechnical engineer. Mr Crawford gave
evidence on his views of the most likely cause of the
deficient fill and on what
can be expected of a reasonable earthworks contractor.
LANDSDALE CLAIM
Issues
- [7] Broadly
the issues I need to decide are:
(a) What was the scope of the Partnership’s obligations in contract or
tort in respect to the cut to fill earthworks?
(b) Was the Partnership in breach of those obligations?
(c) If so, what damages are recoverable?
- [8] The trial
proceeded on the basis that the Partnership contested that it had placed fill
that failed to meet the specifications
(non-compliant fill). Essentially, Mr
Newell’s
evidence was that when the Partnership placed the fill it was compliant but
subsequently became non-compliant. He said this was due
to deficiencies in the
sub-soil drainage design or installation and/or because compliant fill had
degraded due to the deposit by
SPC of unsuitable materials on the surface of
Lots 72–74 at the instruction of Landsdale. In closing submissions, the
Partnership
advised that it no longer sought to advance these hypotheses for how
the site came to need remediation. It conceded that it placed
non-compliant
fill. That was a responsible concession. Neither of the hypotheses advanced by
Mr Newell were technically or factually
credible.
- [9] The
Partnership’s concession did not go so far as to accept SPC’s
evidence as to the mechanism by which the Partnership
placed non-compliant fill.
That is because the mechanism does or might bear on whether there was any breach
of the Partnership’s
obligations in undertaking the earthworks.
- [10] The scope
of the concession means that I still need to outline the factual background
relating to the non-compliant fill and
give some consideration to how the fill
came to be non-compliant. However, the concession also means that the only
evidence before
me on why the fill failed to meet specification are the
explanations advanced by SPC.2 It is potentially open to me to reject
SPC’s expert and fact evidence, although that would leave me in a vacuum
without alternative
explanations. I return to the facts and my conclusions on
the evidence later.
- [11] First, I
need to provide some technical and factual context to enable the issues to be
addressed.
Factual and technical background
- [12] The
Landsdale development is a large residential development on the corner of Kay
and Horsham Downs Roads on the outskirts of
Hamilton (Landsdale Development).
There are four stages. Stage one comprises 37 building lots, stage two comprises
36 building lots,
and stages three and four comprise 28 building lots.
- That
is because Mr Newell’s evidence at trial as to why the fill was
non-compliant is inconsistent with the concession because
he was contending that
it was other than because the Partnership deposited non-compliant
fill.
- [13] SPC entered
into two contracts with Landsdale Developments Ltd (the Principal):
(a) A contract dated 15 January 2015 for earthworks for stages one to four, and
civil works for stage one (the Stage One Contract).
(b) A contract dated 3 October 2016 for civil construction works for stages two
to four (the Stage Two Contract).
- [14] In late
2014, SPC subcontracted the Partnership to complete the cut to fill bulk
earthworks on the Landsdale Development. Cut
to fill earthworks involve fill
(soil) being taken (cut) from one area of an earthworks site to build up (fill)
in another area so
that in both cases the designed ground level is achieved.
Fill is placed in layers approximately 200 millimetres to 300 millimetres
thick
by being spread using a bulldozer with a scoop. Each layer placed is then
compacted using a soil compactor to achieve appropriate
compaction.
- [15] The
Partnership owned a bulldozer and compactor whereas SPC did not. SPC owned a
digger (excavator) whereas the Partnership did
not. Mr Newell did not have the
experience to operate the latter machinery.
- [16] The parties
have never dealt with each other on the basis of detailed written contracts and
there is a dispute between the parties
as to precisely what documents Mr Newell
was provided with and which form part of the contract. It is common ground
however that
he provided priced unit rates against scheduled quantities for
works.
- [17] In respect
to cut to fill, the schedule of quantities quoted against required the
Partnership to:
Cut from formation alignments to subgrade level Roads, Row’s [sic],
berms, footpath, batters, vehicle crossings and building
platforms. Spread and
compact on site as controlled fill where shown on the plans, and as directed by
the Geotechnical Engineer.
- [18] It is not
in dispute that the Partnership contracted on the basis that SPC would retain 10
per cent of any invoices issued for
a period of 12 months after practical
completion for the relevant works.
- [19] The
particular part of the site relevant to the Landsdale Claim is known variously
as “Gully 2” and “Lots 71–74”.
Lots 71–73
were fill areas whereas Lot 74 was both a cut and fill area. The delineation of
roles between SPC and the Partnership
was as follows: SPC first stripped the
site using its equipment. It then installed subsoil drainage in the bottom of
the gully. Once
the swampy bottom of the gully area was dug out SPC placed a
layer of geo filter cloth on the cleaned out fill area, then placed
imported
rock followed by another layer of geo filter cloth over the rock. This is what
is described as a rock blanket. On completion
of the rock blanket the site was
handed over to Mr Newell to bring his bulk earthwork equipment on site to cut
and fill the area
as required. Once the site had been brought up to the required
finished level, either SPC or the Partnership would spread topsoil
when and
where instructed by the Principal or its representatives.
- [20] It is worth
emphasising that the Partnership carried out all cut to fill operations
on site and the payment for these works was passed through to it. This was
confirmed by Mr Pemberton’s
evidence:3
We never
placed any cut to fill on this job. Everything that we were paid by the engineer
of the contract as certified quantities
within the payment certificates was
handed straight through to [the Partnership].
- [21] The
rock blanket and subsoil drainage had two functions. The first was a temporary
purpose. There needed to be a sufficiently
stable platform for the bulk
machinery to work on. The subsoil drainage and rock blanket created a building
platform. Secondly, the
subsoil drainage and rock blanket provided a permanent
drainage infrastructure. Specifically, they fulfilled a function of reducing
the
water pressure in the site. The function was not to prevent water entering
engineered fill placed on top of it for the long term.
The expert evidence
(which I accept) was that ingress of water is inevitable and expected. If
suitable fill is laid, water ingress
has no more than a 10 per cent effect on
the strength of the soil. In contrast, where soil is
3 Notes of Evidence (NoE), page 174, lines 34 and 35, page 175,
line 1.
placed too dry or too thick, air voids are created and will absorb the water,
causing the soil to lose strength.
- [22] Gully 2 was
on the northern border of the site at a point where the Waikato Expressway was
to be constructed adjacent. At the
time of the earthworks the construction of
this had not started. The neighbouring land was still a paddock. Along the
northern border,
but still within the subdivision, was a temporary sediment pond
required for Regional Council purposes. When this was decommissioned
for a
period there was a five-metre unfilled strip adjacent to where the Expressway
was to be constructed on the border of the Landsdale
site.
- [23] The
Partnership completed the cut to fill earthworks on site in January and February
2015 other than the filling of this five-metre
strip. Mr Newell came back to
undertake this in January 2016. At that time there was an incident that caused
Mr Newell concern
as to the robustness of the geotechnical services being
provided and the sufficiency and design of the drainage. The incident was
relevant to liability when the Partnership was asserting his theories for why
the remediation work to Gully 2 was later required.
In light of the concession
made in closing, it now only has some relevance to a position taken by Mr Newell
as to whether he would
have carried out the remedial works in Gully 2 had he
been given the opportunity (relevant to damages). Accordingly, I come back
to
the facts around that in the context of considering damages issues.
Placement of suitable fill
- [24] Fill
must not be placed too wet or too dry. That means that it may require
conditioning by the earthworks contractor before being
placed (i.e. wetting or
drying it on site). Mr Newell accepted that an experienced contractor can assess
in general terms whether
material is too wet or too dry. There are three ways
this can be done without technical measuring tools.
- [25] First is a
visual assessment of the material. Secondly, an experienced contractor can use
feel to assess whether the fill is
appropriate. When it is in a workable
condition, it is like a pliable plasticine. When it is too dry it is too
granular
and does not bind. When it is too wet it is too sloppy (and unworkable with
machinery).
- [26] Thirdly,
and most practically for the earthworks contractor, a check can be made as the
fill is deposited. The methodology is
as follows: each scoop load of fill is
spread at approximately 200–300 millimetres deep over an area
approximately three metres
wide and 45 metres long. The next scoop load
continues from where the last finished until the area to be filled is covered.
While
placing fill the soil compactor works continuously on the fill already
placed leaving the outside tyre mark on the spread untouched
as the guide for
the next lot of fill to be spread.
- [27] After about
six or eight passes of the compactor, each layer of fill is compacted to the
appropriate thickness. The operator’s
observation of the compactor wheels
and pads is a guide to the quality of the fill. The compactor pad indent left on
the fill is
ideally a constant 30 millimetres, meaning the fill will be within
the required specifications. Indents that are shallower mean the
fill is getting
drier than the optimum required moisture content and air voids in the material
will start to climb above the maximum
allowable. If indents get deeper than 30
millimetres, this indicates fill is wetter than the optimum required moisture
content and
the shear strength of the material will begin to fall.
- [28] There are
also tools used to test the fill for moisture content and for compaction. A
shear vane is the tool used generally to
measure fill to ensure it is not too
wet or soft. This tests the strength of the material in kilopascals (kPa). The
other tool used
is a nuclear densometer which is used to test for air voids.
This determines whether fill is too dry and whether it is sufficiently
compacted. It is a more sophisticated device and is usually employed by a
geotechnical engineer or similarly qualified person. The
samples are taken from
the soil using an augur and tested using the densometer. Samples are then oven
baked before being further
tested to complete the testing procedure.
- [29] Neither SPC
nor Mr Newell owned a nuclear densometer. Both owned and used a shear vane. Mr
Newell used a shear vane for his internal
purposes to confirm whether a
particular area needed reworking. He did not record the results of
these
tests and has never been required by SPC or any other head contractor to provide
those test results, including on the Landsdale Development.
- [30] Appropriate
compaction is achieved with soil of the required strength (kPa) and low air
voids. As noted above, air voids are
a problem because when water enters the
soil (which, as discussed at [21], it
inevitably will) soil with high air voids will absorb the water and lose its
strength. Air voids will occur where fill is placed
too dry and/or in too thick
layers.
Geotechnical specifications
- [31] HDG
was engaged by the Principal as geotechnical engineer to the project. Clauses
17.1.14 and 17.1.15 of the Stage One Contract
stated:
- 17.1.14 [HDG]
has been engaged as Geotechnical Engineers for the contract. Earthworks
operations are to be carried out under their
direction. Contact details will be
provided to the successful tenderer.
- 17.1.15 To
remove any doubt please note that the appointment of the Geotechnical Engineer
does not remove the responsibility of the
contractor to undertake all necessary
testing to ensure compliance with the relevant standards and specifications in a
uniform manner
across the full extent of works. The Geotechnical Engineer has
been appointed to observe and certify works for the principle [sic],
not to
demonstrate that the contractor has met their obligation under this
contract.
- [32] Earthworks
specifications prepared by HDG formed part of the head contract between SPC and
the Principal. At trial these were
referred to as the “Addendum
Specifications” to distinguish them from other specifications in that
contract. There is
a dispute about when the Addendum Specifications were
provided to Mr Newell which I will return to. A coloured version of the material
pages of this document were among the Partnership’s discovered documents.
Mr Newell accepted that he received this at the latest
during undertaking the
earthworks.
- [33] The
Addendum Specifications recorded in their “Introduction” that
“HDG has been engaged by [the Principal]
to provide earthworks design and
construction
observation for the Landsdale Development”.4 The document
provided for HDG to undertake independent inspection and acceptance testing to
enable completion reporting and to assist
the Engineer in determining whether
the placed fill met specification.
- [34] The
Addendum Specifications provided that:
The Contractor is required to do sufficient testing to ensure that they are
meeting the specification in relation to compaction. [HDG]
will be undertaking
independent testing to enable completion reporting and to assist the Engineer in
determining if the placed fill
meets the Specification. During fill construction
each lift may be subject to inspection and approval by the Engineer to confirm
that the required compaction standards have been achieved. This testing is
completed as a check in addition to the testing completed
by the contractor.
- [35] In
accordance with the Addendum Specifications, HDG visited the site virtually
daily to undertake representative testing at every
600 millimetre
“lift.” The specific requirements in the specification for fill
included:
Cohesive material
- Cohesive fill
material is to be compacted with a sheeps foot roller.
- Testing will be
required in 0.5m lifts for the first 1m of fill and average 1m lifts above
this.
- Maximum air
voids of 10% and average of no more than 8% over 10 consecutive tests.
- [36] There
was also a table of shear vane requirements (minimum and average requirements).
These specifications also set out optimum
moisture content that fill was
required to meet.5
- Mr
Newell said in evidence that: “Until [the Partnership] received discovery
documents in this proceeding, I understood HDG
was the Geotechnical Engineer to
the contract responsible for all testing. I did not know that HDG was working
for the developer
Landsdale, not for SPC, so I did not know that SPC was also
responsible for a tier of testing in the contract.” If this is
intended to
suggest Mr Newell did not have the document until then, it is incorrect, given
that the material pages of the document
were produced in the Partnership’s
discovery.
- Specifications
[307.1455]. Refer also email to Mr Newell with table setting out requirements
[303.0410].
Discovery of non-compliant fill
- [37] HDG
had carried out testing as fill was deposited as indicated by the Addendum
Specifications. This led to fill being reworked
at times, where the testing
showed that fill was non-compliant. In addition, HDG carried out completion
testing for the purposes
of obtaining Council sign off in November 2016. On 8
November 2016, HDG informed SPC that some poor material had been discovered
below compliant fill placed towards the centre of Lot 74. Within the fill area,
at depths of
1.2 metres and 1.4 metres, there were low shear vane readings of 34 kPa and 65
kPa. These are extremely low readings. The specifications
required average
strength of 150 kPa. By the same communication, HDG told SPC that “we will
need a digger to do some pot holing
in this area to chase out the soft
material”.
- [38] On 25
November 2016, CKL Surveys Ltd (CKL) issued formal notice under the head
contract to SPC requiring it to remediate the
defective fill; and advising that
if it failed to do so, the Principal had the right to instruct others to do so
at SPC’s cost.
SPC commenced work on Lot 74. It was subsequently
discovered that the area of non- compliant fill extended to Lots 72 and 73 and
subsequently Lot 71.
- [39] It is
significant to the issue of damages to note that the earthworks in Lot 74 were
works in Stage 1b, the last works to be
completed under the Stage One Contract.
The earthworks for Lots 71–73 (the other lots in Gully 2) were being
completed under
the Stage Two Contract. Completion date under the Stage One
Contract was 31 December 2016. Completion date for the separable portion
for the
Lot 72 and Lot 73 earthworks under the Stage Two Contract was originally 16
January 2017 but later assessed as 3 March 2017
due to a delay in commencement.
Liquidated damages payable by SPC accrued at $20,000 per week for late
completion under the Stage
One Contract and at $10,684.64 per week for late
completion of the relevant stage under the Stage Two Contract.
- [40] At the
start of the defective fill issue arising, the size or cause of the problem was
not known. It was in SPC’s interests
to have the work required
characterised as a variation rather than work for which it was responsible. This
affected both who would
pay for the remediation, and whether any resulting delay
would be covered by an extension of time or involve liquidated damages for
late
completion under one or both
contracts. SPC notified its insurers with a view to seeking to claim under its
liability policy.
- [41] On 29
November 2016 SPC advised the Principal that it had started chasing out the soft
material in Lot 74. As the term suggests
“chasing out” describes
finding and following the unsuitable material. “Find and follow” is
the term Mr Newell
used. By the same communication, SPC advised that the
non-compliant material was observed to be 400 millimetres thick and not changing
in condition (not getting much better). SPC advised that it intended to deal
with the material in Lot 74 first so as not to hold
up the Stage 1b lots (with
its 31 December completion date) before moving on to Lot 73 and so on. SPC
informed the Principal that
it had spoken to Mr Newell who they reported was
“coming to site in the next couple of days to hopefully shed some more
light
on this”.6 In evidence, Mr Newell accepted that he had
had a discussion with SPC at about this time.
- [42] On
13 December 2016 John Sheppard, the then Contracts Manager of SPC, emailed Mr
Newell referring back to their conversation
a few weeks prior in regard to the
fill in Gully 2 and said:
... can you please make yourself available ASAP to come to site to discuss
the filling and compacting you undertook there. It looks
like at this point the
wet, failing material is chasing out over multiple lots and may end up being a
rather large issue. There may
be some significant remediation work involved. We
are keen to try and get to the bottom of it prior to doing too much work, that
way everyone knows where we are all at before commencing. At this stage it is
difficult to ascertain where the problem lies, with
the client and ground
conditions being the issue, with the Geotechs and their testing or with yourself
and the placement of the fill.
We have also engaged another Geotech engineer to
review all of the test results and he has been to site to view the material,
which
will have a cost associated. We are also awaiting his determination. If
you are available over the next few days to look at the area
let me know when
would suit you. If you have any diary notes from instructions given by the [HDG]
guys, this may be beneficial to
pull out and bring along.
- [43] Mr Newell
had responded that he regarded the issue as a design problem. He concluded
with:7
Will call you next time we are rained off and come have a look.
6 Email 29/11/16 [304.0669].
7 Email 13 02/16 [304.0677].
- [44] Mr Sheppard
emailed back on 14 December 2016 asking whether Mr Newell had time to head out
to the site, noting that the weather
was starting to turn a bit that day and the
next.8
- [45] The
next communication from Mr Newell came on Friday 16 December. He
recorded:9
The area that you guys dug out was filled in
the 14/15 season. Andrew and Emily did the inspections and testing. The first
season
the fill was mainly on the dry side. The gully was filled to design and
the preload placed. The areas to be filled were inspected
by [HDG] before any
fill was placed. The fill was placed in 200/300 mm layers and compacted, every
600 mm a compaction test was then
done. When the tested layer was confirmed to
be within spec more fill was then placed. The size of the area and the shear
strength
of 30 kPa, a soft area would have been easily noticed The problem is
water moving from the natural ground into the fill. Your photo
of water in the
hole after excavating the soft area goes a long way to confirming that. As there
was no attempt to prevent water
from getting into the new fill placed, a test in
say 12 months’ time will be further confirmation.
- [46] The email
did not respond to the request to head out to the site. It is important to note
here the Mr Newell is accepting in
his email that an area of fill with such a
low shear strength would have easily been noticed.
- [47] On 20
December 2016 SPC outlined its position in relation to the non- compliant fill
issue to CKL as engineer to the Principal,
advising that it did not accept
liability for the material encountered. It sought an urgent resolution of the
issue. SPC asserted
that the most glaring issue was photos showing there was
water pooling at the bottom of the digout, indicating water down at that
level
with fill above and below hard and dry. The email recorded that the earthworks
contractor (the Partnership) had placed fill
at 300 millimetre lifts and testing
was done at 600 millimetre lift intervals and suggested that it would be
unlikely that testing
would miss these areas. The email concluded that the fill
was placed dry and met compaction criteria but water had infiltrated
afterwards.10 This email in substance relayed Mr Newell’s views
on the issues that had arisen. However, Mr Newell’s views on the issue
reflected misconceptions he held as to the function and nature of infrastructure
that had been designed and installed. It was not
correct to say there was a
design issue. As discussed
8 Email 14/12/16 [304.0679].
9 Email 16/12/16 [304.0678].
10 Email 20/12/16 [304.0682].
at [21], water moving into soil above
the rock blanket is intended and not an issue, provided the fill placed is
compliant fill.
- [48] It is now
accepted that the Partnership placed non-compliant fill. Having heard the expert
evidence and having regard to this
concession, the view that the non- compliant
fill was caused by water infiltrating after the fill was placed was
incorrect.
- [49] SPC
reported to Mr Newell on 21 December 2016 that there had been a site meeting the
previous day in which SPC had outlined its
position on the Gully 2 fill issue.
This advised:11
Will keep you in the loop how things
proceed. At this stage once we chase more of the wet material out and see how
far it goes / possibly
find the cause, a determination will be made then. So
looking at early next year.
...
[Stage Two] is due to be completed in early Feb and as with the 1st
stage Liquidated damages will apply for late completion. We would like to
get to the bottom of the issue in this area ASAP, as this
area will need
remediated [sic] and completed prior to the end of Jan 2017. Do you have gear
available for this?
Again I will be onsite during this week if you would like to head out, and we
will be happy to dig a couple of test pits for inspection.
- [50] Mr Newell
stated in evidence that he then went out to the site, but provided no details as
to when, or how many times.
- [51] On 22
December 2016, after the remediation works for Lot 74 were completed, practical
completion under the Stage One Contract
was certified prior to its contractual
completion date.
- [52] The next
communication between Mr Newell and SPC was on 31 January 2017. Mr Sheppard was
about to go away. He said:12
I am leaving in a couple of weeks and thought I would get something on email
in relation to the couple of issues we have encountered
at Landsdale with the
earthworks. I have had a conversation with Josh in regards to these couple of
issues as he wants to get these
sorted ASAP, but understand given the nature of
them may not be sorted until after I go.
11 Email 21/12/16 [304.0684].
12 Email 31/01/17 [304.0702].
- [53] In respect
to the Gully 2 issue he said:
Wet material in lot 74 (and continuing into lot 73 etc) at a depth of approx
2-3 m. At this stage we have lodged an insurance claim
with our insurers who
have appointed another geotech company to investigate. We are awaiting their
report but should be through in
the next few days fingers crossed. We have to
date used our machinery to remediate lot 74 as this lot was in stage 1B which
had a
fast completion date and liquidated damages applying to it. In hindsight
an insurance claim with your insurance company might have
been the better way to
go as you were the earthworks contractor. It maybe [sic] something you might
like to look into as although
we are fighting the fight so to speak in regards
to what the issue is down there we don’t know how that will end and what
decision
will be made. To date in this area we have kept our hours and costs and
is currently sitting at $20,140 ex GST. We are hoping the
wet material yet to
chase out isn’t a large amount more. To remediate this work looks to be
digger and roller work which we
will keep the hours on.
- [54] The email
concluded:
Happy to meet again on site to discuss further if you wish. Given that im
[sic] taking off in a couple of weeks probably a good idea
that we get Josh
along too so the next person knows whats [sic] going on. He’s currently
working in Auckland a bit so might
need a day or so notice to come out. Let me
know what you’d like to do.
- [55] There was
then an exchange between Mr Sheppard and Mr Newell in which Mr Sheppard
interposed comments to an email. Mr Newell
continued to contend (incorrectly)
that the problem was nothing to do with earthworks but to do with poor or
insufficient drainage
design. Specifically, Mr Newell asserted that the design
failed to take the rock blanket to a level that would collect and stop water
getting into the fill. He referred back to having seen water entering the
natural ground and the photo taken of this in January 2016.
He also emphasised
that fill areas had been inspected by HDG before fill was placed. Mr Newell
stressed that there was no sign of
moisture when the fill was placed. He said
that the issue did not lie between himself and HDG.
- [56] Mr Sheppard
responded that he agreed HDG signed off the tests and carried out the
inspections so should hold some responsibility.
He relayed that HDG had said
that it was employed to do scattered testing and not to sign off every cubic
metre of fill installed.
The email response recorded that the unsuitable
material excavated was about one-and-a-half metres above the rock blanket to the
base, with good hard clay placed in between this unsuitable layer and the rock
blanket which did not need to be removed. Mr Sheppard
also noted that Mr Sam
Pepper, a representative of the Principal, had a theory that the haul road was
pushed in without compaction.
- [57] Mr Sheppard
subsequently advised on 1 February 2017:13
The bottom line is on this issue, is that once the problem was raised through
[HDG] doing the lot validation testing in their completion
report, we had a
matter of days to complete the remediation of this unsuitable in lot 74 in stage
1. Otherwise [liquidated damages]
of $21,369.27 per week would apply. We were
instructed by the client in accordance with our contract NZS:3910 to make good
and had
5 days to commence. You don’t have the appropriate equipment to
remediate this issue, as it is isolated and confined and is
digger work, so we
have done this work. We still have lots 73 and beyond to excavate and remediate
at this point, but they are in
the next stage and still to be done.
You may be getting the wrong end of the stick from my emails. We have already
been battling this with all parties for the last three
months, and have got to
the point of getting our insurer involved. What we are after is the support from
you in the form of records,
photos, reports, emails etc to come out the other
end of this at the very least covering our costs, as we think it will end in
court
with Pepper/[HDG] as the costs are building fast. The issue does lie
between you and [HDG], as you are the earthworks contractor,
however we are the
meat in the sandwich trying to achieve an outcome to resolve this at no cost to
either of us.
- [58] Mr Newell
responded that he supported SPC in the battle with the Principal and HDG
saying:
I fully understand what you are going through its not nice arguing about
these things. I don’t keep records etc when placing
fill, all emails on
tests and inspections are sent to you and me this is all we have.
- [59] Mr Newell
then emailed again on 3 February 2017 and described concerns he had had when he
was filling up the five-metre strip
by the expressway in January 2016. Wet
material was found, and he said HDG were then suggesting it was because the
Partnership had
placed unsuitable fill. On that occasion Mr Newell had refuted
this. He had confirmed his stance that the reason for this was that
the fill was
sitting in water on the drainage blanket by having one of SPC’s staff use
SPC’s digger to dig down to the
rock blanket where it was observed that
200–300 millimetres of fill on the blanket was wet. Mr Newell reported
that Mr Holland
refused to accept that water had got into the fill or that the
drainage blanket was the problem.
- [60] He reported
that Mr Holland said it was an isolated area and so recommended to fill the hole
in. This was the gist of Mr Newell’s
contention that the drainage blanket
design was the problem. He recorded:14
13 Email 1/02/17 [304.0712].
14 Email 3/02/17 [304.0717].
You say you have engaged your insurance co and a geotech and it could end up
in court it might be a good idea to pass this info on
to them I am happy to meet
with your Geotech and show him where he can augur down to confirm this
You say in your email that I might have the wrong end of the stick on
something in all of this
The info and comments from me are as it happened, as the work was done, no
more no less, and for your use as you see fit
- [61] A 7
February 2017 team site meeting was held in which the earthworks were
discussed:15
Earthworks continuing within lots 70-73. Pot hole observed within Lot 73 to
determine extent of unsuitable material. Material generally
looked consistent
and hard. [HDG] to complete augers around area to determine if all unsuitables
have been removed.
- [62] The
remediation works continued into February and March. SPC continued to dispute
its liability in respect to the remediation
works with CKL as engineer. SPC
asserted in early March that HDG was holding up obtaining reports from
SPC’s insurer by not
providing its reports or answers to questions. The
Principal was contending that liquidated damages would be payable under the
Stage
Two Contract.
- [63] On 23 March
2017 SPC provided a practical completion letter for Stage Two. In response CKL
advised that there were several items
still outstanding for Stage Two
completion:16
These items include cut to fill within lots
69-73/remediation of lots 72/73, Topsoil and seed within 69-73, removal and
replacement
of dish channel damaged within both parking bays on Road 1, chip
seal and hot mix of parking bays within Road 1, Road Markings and
street signs
for the stage.
- [64] The letter
recorded that practical completion could not be issued until those works were
complete.
- [65] Mr
Pemberton replied saying, among other things:17
Dishchannel [sic] won’t be removed I’ve view [sic] the repairs
and am happy, [L]ance was also happy with this on the last
stage.
15 Minutes 7/02/17 [304.0722] at [304.0724].
16 Email 24/3/17 [305.0778].
17 Email 24/03/17 [305.0778].
Go and view the site, I did yesterday and it looks great.
Please issue practical completion and start this process with HCC.
- [66] Practical
completion for the relevant works in Lots 71–73 was certified on 16 May
2017. This was beyond the contractual
completion date of 3 March 2017.
Engineer’s Decision on cause of fill failing specification
- [67] As
outlined above at [9], while the
Partnership concedes it placed the non-compliant fill, it does not concede the
mechanism by which this occurred.
- [68] On 13
December 2016 Mr Holland of HDG set out his summary of what he had observed and
views on probable causes. He then updated
this in an email dated 28 March
2017.
- [69] Mr Holland
outlined that the non-compliant fill that was chased out in Lots 70-74 was
not an isolated layer in the base
of the fill, but layers of varying thickness
throughout the fill placed in this area. When HDG undertook testing in the area
of Lot
74 (and later Lots 70–73), it found generally good fill with layers
in zones of wet, soft material. These were not isolated
to the base of the fill
but scattered throughout the fill. Mr Holland’s initial assessment of the
probable causes of the soft
material being encountered in his email of 13
December 2016 and update on 28 March 2017 was that it was more likely that fill
was
placed dry and therefore wetted up and lost strength after placement. He
concluded it was possible but less likely that the fill
was placed wet
initially.
- [70] Mr
Holland’s conclusion was:18
While it is not possible to definitively identify the cause of the soft fill
in the area of Lot 74, there are a number of observations
that suggest
possible/probable causes. The contractor who placed the majority of the fill in
gully 2 typically favoured a dry, hard
fill and was often struggling with the
air voids specification. Lot 74 is in a transition area from fill to natural,
and lift control
appears to be less accurate than in the layers above the soft
fill (where the transition is buried). My opinion is that these factors
combined
to create an area with thicker lifts, sometimes uncontrolled, minimal compaction
in some layers and high voids that was
placed below specification and in some
places has been able to soften significantly with an increase in moisture
18 Email 13/12/16 [305.0781] at [305.0783].
content. It may have been put in place wet, and further softened, or dry and
hard with high voids and subsequently softened. It is
likely a combination of
both mechanisms for the various layers.
- [71] In terms of
the observations on site of this material, Mr Holland observed:
(a) The material found as at 13 December 2016 was typically a mix of ash soil
with layers of what appeared to be swamp deposits (unsuitables
in the base of
the gullies).
(b) Soft material was encountered in layers and often observed in large
thicknesses. He noted that directly above the subgrade was
the thickest mass
which included a large portion of swamp material. The soft material then
extended into layers, the most significant
being approximately one metre
thick.
(c) He observed at least two layers of significant unsuitable material in the
overall layer of soft material with a few isolated
layers at shallower depths.
Layers of swampy soft material were encountered in layers up to 100 millimetres
thick within hard “EC
Fill”. In the lower part of the excavated
area, the soft material (ash mixed with swamp deposits) was more than one metre
thick.
The main layers of swamp material were up to 200 millimetres to 300
millimetres thick and within soft ash.
(d) Natural subgrade exposed was hard and relatively dry.
(e) Engineered fill above and below was high strength with obvious thin
layering.
- [72] HDG
postulated that the main layers of swamp material could have been dropped as the
gully was cleared out and covered over by
fill material. It also noted that Lot
74 is on the edge of the Gully 2 fill area. Mr Holland referred to the numerous
temporary access
tracks in the area and the transition from fill to natural land
nearby.
- [73] In his
later email on 28 March 2017 Mr Holland referred to continuation of the soft
material encountered in Lot 74 towards Lot
73 and that this was dug out to
continue chasing out the thick layer of soft material (being approximately a
bucket-width removed).
He considered that all observations made were
consistent
with the original opinion expressed on 13 December. He referred to isolated
areas within Lots 72–73 noting that soft material
was encountered at a
shallower depth to the initial Lot 74 excavation containing a large amount of
unsuitable alluvial material mixed
with ash.
- [74] Mr Holland
noted that a soft area around the settlement marker was encountered and
expressed his belief that hand compaction
or compaction of fill with small plant
was not undertaken around the pin. He also noted a soft layer at the back of
Lots 72–74
which he believed was caused from an old haul track that had
not been cleared before placing fill. He advised that soft material
underlying a
stockpile of unsuitable material that had been placed on site was continuing to
be encountered and chased out.
- [75] On receipt
of Mr Holland’s updated report on the Lot 74 soft fill issue on 28
March 2017, CKL requested any further
response from SPC before the engineer
moved to decide whether SPC had responsibility for the issue. SPC continued to
refute HDG’s
position both factually and legally. At that point,
additional costs on remedial work to date were $44,148 excluding GST and
rising.19
- [76] Mr Newell
was provided with Mr Holland’s observations and continued to reject the
conclusions.20 He was angry at the accusations of poor quality
control and rejected the opinions. Mr Pemberton responded advising that SPC was
going
to pull together HDG site visit dates, instructions, test results and the
like and once they had done this they would get Mr Newell
in for an hour to pin
some dates on when some of the more critical meetings/instructions would have
taken place. He observed that
he would need more concrete evidence “so if
we all collectively try and pull some of this together – I am sure we have
a solid case”. Mr Pemberton advised he had been told that the Principal
was taking six weeks of liquidated damages from SPC.
- [77] There were
further exchanges between SPC and CKL regarding the rework in Lots 71–74
with SPC maintaining its position that
it was not liable. As part of SPC’s
case that responsibility for fill being within specification was with HDG, SPC
referred
19 Email 28/03/17 [305.0780].
20 Email 29/03/17 [305.0786].
to a pre-start meeting held on site in which it was recorded that SPC did not
own a nuclear densometer and that therefore shear vanes
would be carried out for
indicative kPa testing only and recorded daily. SPC sought to tie this into
clauses of the contract relating
to the respective responsibility between the
parties.21
- [78] The final
inspection of the excavation for Lots 70–73 was completed on or about 4
May 2017.
- [79] On 21 June
2017 CKL issued its engineer’s decision in respect to the Gully 2
remediation works.22 This concluded that the defect was likely a
result of SPC not achieving the required specifications. It recorded:
It is important to note that no physical evidence, testing results or expert
analysis was provided with the Contractors [sic] arguments.
As [HDG] are experts
in the field of soils and have provided information based on investigations,
sampling and testing a level of
weighting to their findings has been given.
- [80] The
decision effectively adopted the information HDG had provided.23 It
also rejected the contention SPC was advancing that it was not contractually
responsible for the fill meeting specification. The
decision noted that the
material described as swamp deposits or unsuitables was clearly visible as soft
darker material in layers
during remediation works and that this had been backed
up by low shear vane results within the material.
- [81] The
decision was provided to Mr Newell. Mr Pemberton commented in his covering
email:24
Well I’ve done my best.
Its lawyers now, if we want to go any further. What’s your
thoughts?
- [82] Mr Newell
continued to deny that the issue was one for which he bore any
responsibility.
21 Email 1/05/17 [305.0819].
22 Letter 21/06/17 [305.0918].
23 Mr Holland’s reports reference to above.
24 Email 22/06/17 [305.0923].
- [83] By letter
dated 5 July 2017 SPC formally recorded to the Principal that it disputed
CKL’s findings. There then followed
some engagement between the lawyers on
the issue. Ultimately SPC did not pursue any continued objection through the
contractually
available steps.
Contractual obligations
Preliminary
- [84] The
first issue is what contractual obligations were owed by the Partnership. The
Partnership accepts that it owed a number of
implied obligations, which I
address later. Here I deal with disputed issues relating to obligations on the
Partnership to comply
with the Addendum Specifications referred to above at [32]–[36].
- [85] It is
common ground that Mr Newell was provided with a schedule of quantities and
quoted based on providing his proposed cut
to fill rate on these. The schedule
included the following:
Spread and compact [fill] on site as controlled fill where shown on the
plans,
and as directed by the Geotechnical Engineer.
- [86] The parties
agree that these words form part of the contract but disagree about what they
convey.
- [87] The
Partnership says the words “as directed by the Geotechnical
Engineer” meant that it was to do what was directed
by HDG but that it did
not itself have any obligation to comply with the Addendum Specifications (or
more particularly, the specifications
contained within the Addendum
Specifications as to air voids and optimum water level). Rather, it says this
was the job of HDG to
ensure compliance using the testing it was undertaking.
This required a nuclear densometer, which everyone knew neither the Partnership
nor SPC owned.
- [88] Mr Talbot
submitted that if SPC took on the risk of ensuring compliance with the
specifications in the Addendum Specifications
despite not having a nuclear
densometer, this risk was not passed through to the Partnership. The Partnership
also says it was not
provided with the Addendum Specifications until it was on
site doing the work and they do not form part of the contract for that
reason.
As noted at [32], it
is common ground that Mr Newell did receive the Addendum Specifications at some
point, as the document was provided on discovery
by the Partnership.
- [89] SPC says
that the words “as directed by the Geotechnical Engineer” required
the Partnership to place fill that met
specifications provided by HDG and it was
for the Partnership to ensure that this was so. SPC pointed to Mr Newell’s
acknowledgment
that he could tell when fill was too wet or dry by the various
non- technical methods in his standard methodology. While HDG undertook
scatter
testing at the surface of each 600 millimetre lift, this did not and could not
ensure all fill met specification, nor did
it detract from an obligation to meet
specifications.
- [90] SPC says
for this purpose it is irrelevant whether the Addendum Specifications were
provided to the Partnership before or after
the contract was formed. However, it
says these were provided by Mr Pemberton at a first walkover of the site (back
when the Partnership
provided its rates) and if that is not accepted, then prior
to work commencing.
When were the Addendum Specifications provided?
- [91] As
referred to above, the parties differed in their recollections on the documents
provided at the outset. They also differed
on the circumstances in which SPC
came to tender on the contract. Mr Newell said he obtained the schedule of
quantities for the project
from Schick Construction (Schick), another earthworks
contractor, who had been invited to tender. Mr Newell said it was he who
approached
SPC to enquire whether it was going to tender for the earthworks
contract, and it is through this that SPC was introduced to the
work. Mr
Newell’s evidence was that he had not obtained any other material
documents at this time.
- [92] Mr
Pemberton does not recall Mr Newell introducing SPC to the project. He said that
this was unlikely given that SPC was a preferred
contractor for CKL. In
particular, SPC had worked for CKL on the very substantial Huntingdon
development. Also, Mr Pemberton said
that he recalled walking around the site
with Mr Newell and providing him with the contract documents, which included the
Addendum
Specification. He said it was the usual course to provide Mr Newell
with the contract
documents, and also noted that at the time Mr Newell’s daughter was
working with SPC so it was no issue retrieving them.
- [93] I accept Mr
Newell’s evidence that he did obtain the schedule of quantities from
Schick and that he went into Schick’s
offices and viewed some documents on
screen. This is such a specific memory and Mr Newell had no particular reason to
invent this
scenario. However, I also accept Mr Pemberton’s evidence that
SPC was asked to tender independently, so was not introduced
to the project by
Mr Newell. More significantly, I accept that Mr Pemberton walked with Mr Newell
around the site and gave him the
contract documents which included the Addendum
Specifications. Mr Talbot was critical that this particular scenario (walking
around
the site and providing the documents) was not put to Mr Newell. I do not
agree that it was necessary to do so given Mr Newell’s
recollection was
that he had received no documents from SPC and he was cross-examined generally
about this.
- [94] I conclude
on the facts that the Addendum Specifications were provided to Mr Newell at or
about the time that he quoted on the
work. I also conclude that the particular
copy of the Addendum Specifications discovered by the Partnership was provided
before Mr
Newell started work on the site. I agree with Ms Whitfield that on any
view it is much more likely he received them prior to commencing.
- [95] In my view,
the Addendum Specifications form part of the contract between the Partnership
and SPC as the specification to which
the works were to be undertaken.
Contractual position on the Addendum Specifications
- [96] The
Addendum Specifications placed ultimate responsibility on the contractor, not
HDG to place compliant fill, notwithstanding
that testing was being undertaken
by HDG. It is correct that HDG undertook testing and required reworking by the
contractor where
tests failed as it went along. It tested fill at each 600
millimetre lift at the surface of that lift. Its testing was random and
completed after the fill was placed. I accept the proposition that this testing
was not intended to be, nor was it able to be, a
confirmation that all fill met
specification. HDG could not and did not observe the fill placement on a
continual basis.
- [97] I do not
agree that this obligation was negated by the prior site meeting where it was
acknowledged that SPC/the Partnership
did not own a “nuke” (nuclear
densometer). I agree with the finding of CKL in the engineer’s report that
it was
for the contractor to meet the specifications and it was up to it how
this was done. My conclusion on this matter is supported by
the evidence I heard
from both parties that from a practical perspective a competent contractor can
tell whether fill is too wet
or too dry.
- [98] In my view,
the Partnership stood in SPC’s shoes insofar as the Addendum
Specifications obligations are concerned. The
Partnership was to undertake (and
did undertake) all the cut to fill works, with a straight pass through of all
payments received
by SPC for those works. The fact that the whole of these works
were subcontracted to the Partnership which received the full payments
for them
supports that the Partnership as compared to SPC assumed the obligations for
those works under its subcontract. Moreover,
if the Partnership was not
responsible for fill meeting specification, this would deprive the
Partnership’s acknowledged obligations
(discussed below at [103]) to exercise reasonable care and to
act in a proper and competent manner of any sufficient content.
- [99] In summary,
the Partnership was obliged to comply with the Addendum Specifications. This
obligation is unaffected by HDG’s
testing.
- [100] There is a
suggestion that the Partnership was not required to undertake testing and that
therefore it cannot be liable. I agree
with SPC’s submission that this is
a red herring. The Partnership’s contractual obligations were to achieve
the standards
set out in the Addendum Specifications, that is, not to place fill
that was too wet or too dry. How it achieved these was a matter
for
them.
Breach of Contract
Breach of obligation to meet Addendum
Specifications
- [101] I
have concluded that the Partnership was contractually obliged to meet the
Addendum Specifications. The Partnership concedes
that it deposited
non-compliant fill. Therefore the Partnership was in breach of contract.
- [102] I note
that my conclusions on the disputed issue of the status and applicability of the
Addendum Specifications are not determinative
of the Partnership’s
liability. That is because, as discussed below, I also find that the Partnership
was in breach of the
suite of implied obligations that the Partnership
acknowledges it owed.
Breach of implied obligations
- [103] The
Partnership admits that it owed the following contractual duties:
(a) To exercise reasonable skill and care when performing its
services.25
(b) To undertake its work in a proper and competent manner.
(c) To use the “placement and compaction” methodology referred to in
the “CKL specification” to the head
contract.26 In
closing, Mr Talbot described this as an obligation to use the “industry
standard placement and compaction methodology”
described in Mr
Newell’s evidence, being the methodology he had used for 40 years as
follows:
- I
do not accept that the Partnership placed any unsuitable fill. I used the same
methodology I have used for 40 years on this job.
Each scoop load of carefully
selected fill is spread at approximately 200-300 millimetres deep over
an area approximately
3 metres wide and 45 metres long. The next scoop load
continues on from where the last spread finished and so on until the area to
be
filled is covered. As we are placing the fill, our soil compactor works
continuously on the fill that has already been placed,
leaving the outside tyre
mark on the spread untouched as the guide for the next lot of fill to be spread.
Any area of fill before
compaction that appears thicker than 200- 300
millimetres is trimmed by the compaction blade.
- Each
layer of fill, after about 6 or 8 passes of the compactor, is compacted to
approximately 200 millimetres thick. My observation
of the compactor wheels and
pads is a constant guide to the quality of the compaction. The compactor pad
indent left on the fill
is ideally a constant 30 millimetres, meaning the fill
will be within the required compaction specifications. Indents any shallower
than 30 millimetres means the fill material is likely to be getting drier than
the optimum required moisture content, and air voids
will start to climb above
the maximum allowable 8%. If fill appears drier than the optimum required
moisture content, that fill needs
to be reworked and wet.
- Para
14 of the Reply by Plaintiffs to Defendant’s Statement of Defence and
Counterclaim dated 30 June 2023 [101.0026].
26 Refer
2.17.1-2.17.8 at [302.0106].
- If
the indents left by the compactor are getting deeper than 30
millimetres, this indicated fill wetter of the optimum
required moisture content
and the sheer strength will begin to fall. I monitor these areas of plus or
minus of the 30 millimetres
with my own shear vane. This methodology has served
me well over my 40 years of earthmoving as it did in the placement of 122,000
cubic metres of fill at Landsdale.
- I
do have a shear vane, which I use on site to test areas that may not appear to
have passed our own compaction requirements. These
shear vane tests are carried
out for our internal purposes only to confirm whether a particular area needs
reworking. We do not record
the results of these tests and we have never on the
Landsdale contract, or on any other contract, been required by SPC or any other
head contractor to provide our test results.
- When
we placed each 600 millimetre layer, so 3 layers of 200
millimetres, the filling process stopped, and we had to
notify the SPC that a
layer is ready for testing. SPC then requested HDG to complete the testing. All
instructions to me or from
me were through SPC. We always had a good working
relationship with HDG and always enacted any recommendations and instructions
regarding
the placement of the fill. There is fill that is either too dry or too
wet according to the Geotech tests on all cut to fill jobs,
and we have always
managed these to the Geotech’s satisfaction by reworking the fill as
instructed.
- [104] Because Mr
Newell’s position until closing was that the fill the Partnership placed
was compliant, in his evidence-in-chief
and cross-examination he rejected that
the Partnership, as a competent and experienced contractor, could have done
this. In particular:
(a) He accepted that an experienced earthworks contractor would be able to
identify where fill is too dry.27 He said that fill could be placed
dry of optimum moisture but still be within specification. The operator looks at
how the compactor
is operating but that this does not regulate two to three per
cent out of specification, for which he said he relied upon HDG
testing
every 600 millimetre lift.28
(b) Mr Newell’s evidence was that it was impossible for the Partnership to
place fill too thick, adopting the industry standard
placement and compaction
methodology.29 More specifically, he was referring to the fact that
when the
27 NOE page 39 at line 30.
28 NOE 57-58.
29 NOE page 93 at line 23 – page 94 at line 1.
scoop is set at the 200–300 millimetres required, the fill cannot come out
thicker.
(c) In his evidence Mr Newell rejected that the Partnership could have been
responsible for an area of unsuitable fill,30 a subject of the failed
fill noted by Mr Holland in his observations (and visible in a photograph that
was produced). Mr Newell said:
Based on my significant experience in earthworks, it is not possible that we
placed organics/unsuitable material like swamp material
in gully 2. It is not
credible to suggest a person with my knowledge and earthworks experience of
earthworks material would do this.
- [105] When the
issue of non-compliant fill in Lot 74 emerged in December 2016, Mr Newell had
also rejected that this could have been
non-compliant when it was placed by the
Partnership. He commented on the low shear strengths of the non- compliant fill
that had
been identified:31
The size of the area and the
shear strength of 30 kPa, a soft area would have been easily noticed.
- [106] Once the
Partnership accepts (as it now has) that it deposited the non-compliant fill in
issue, by the above evidence Mr Newell
is acknowledging in substance
that:
(a) The Partnership has in fact placed fill that is too dry by such a margin
that it would be something an experienced contractor
can identify.
(b) A competent contractor, acting with reasonable care, should have noticed the
non-compliant fill in Lot 74.
(c) The Partnership has placed fill too thick (described by Mr Holland as one
metre thick in places).
(d) The Partnership did place organic or unsuitable fill despite this being
extraordinary for an experienced earthworks contractor.
30 Brief of Evidence (BoE) of Wayne Newell , para 33
[201.0013].
- Email
of Wayne Newell to John Sheppard regarding the Landsdale Gully 2 Fill (16
December 2016), set out above at [45].
- [107] These are
plainly breaches of the Partnership’s admitted obligations to exercise
reasonable skill and care, to undertake
its work in a proper and competent
manner and to use the “placement and compaction” methodology.
Although probably inadvertently,
something has gone wrong in the
Partnership’s implementation of their standard work methodology, and it
was not complied with.
- [108] In his
contemporaneous reports and in evidence, Mr Holland provided his views on how
these things could have occurred. For example,
he hypothesised that the
inorganic/unsuitables may have been a contamination of the surface of the fill
as unsuitables were trucked
across it. He referred to Lot 74 being on the edge
of a gully where there had been numerous access tracks in the area and a
transition
from fill to natural ground. He suggested that these may have
inadvertently been left in place by the contractor.
- [109] Mr
Crawford referred to the most probable cause of the non-compliant fill as being
an overly thick zone of excessively dry and/or
uncontrolled fill (possibly from
a ramp created and left behind and buried, probably inadvertently, at the then
current edge of the
permanent fill). Given the significantly low strength
observed in this fill, it was not a marginal failure caused simply by a few
layers of fill placed a little dry of optimum water content.
- [110] I agree
with SPC that the evidence shows that there was not simply one mechanism
involved. The key point is that the explanations
seek to explain how plainly
non-compliant fill came to be deposited. In my view the explanations provide the
probable causes and
whether the hypotheses are correct or not, in placing such
material, the Partnership has failed to meet the standards of a competent
earthworks contractor.
- [111] I
emphasise that it was not necessarily Mr Newell himself who deposited
non-compliant fill (given that the Partnership had a
number of workers). I also
acknowledge that it is common ground that the Partnership works generally had
been to a good standard.
However, in this instance the work fell below the
standard of a reasonably competent contractor.
- [112] Finally on
the issue of liability, Mr Talbot placed some emphasis on communications between
SPC and CKL/the Principal in which
SPC was advancing the contractual position
that the head contract did not place liability on SPC for ensuring fill
complied with
specification and which adopted and advanced Mr
Newell’s arguments as to why there should be no responsibility on
the
facts.
- [113] As SPC
said in some of its communications with Mr Newell it was “fighting the
fight” for that purpose. It was also,
as it said, “the meat in the
sandwich” between the Principal and the Partnership. In those
circumstances, the contentions
SPC was advancing to the Principal do not amount
to some sort of admission by SPC, nor does it preclude SPC taking an
inconsistent
position now. SPC, in reliance on assertions the Partnership now
accepts were incorrect, was pragmatically seeking to avoid any liability
for the
issue that had arisen.
- [114] These
attempts failed, with the Engineer’s decision concluding that, factually
and technically, the defects in Gully 2
were likely because the earthworks
specifications had not been met, for which SPC as contractor was liable. SPC did
not go on to
pursue the matter to mediation or arbitration. It did continue to
advance a case that there was no liability in communications passing
between the
parties’ lawyers, but ultimately did not pursue further legal process in
that direction. It cannot be criticised
for that course. In my view it did not
have any reasonable prospects of success in taking the matter further.
Damages for breach of contract
- [115] Having
concluded that the Partnership is liable in contract, I now consider damages for
breach of contract. The usual position
in contract is that SPC is entitled to be
put in the position it would have been had the Partnership not breached the
contract.32
(a) costs to undertake the remedial work of $133,212.93;33
32 Stirling v Poulgrain [1980] 2 NZLR 402 (SC & CA) at
419 per Cooke J.
33 Brief of Evidence of Sam Pemberton, paras 85 to 87
[201.0073].
(b) liquidated damages of $109,899.15 that it was required to pay the Principal
for delays said to be caused by having to remediate
the Partnership’s
defects;34 and
(c) legal costs of $5,803.20.
- [117] Once these
are set-off against the retentions outstanding on Landsdale the net amount
claimed by SPC is $108,775.66.35
Remediation costs
- [118] The
Partnership’s position is that the remediation costs claimed by SPC are
excessive. In substance, Mr Newell said he
was entitled to be given the
opportunity to remedy the defective works, he was not, and had this happened he
would have taken up
the opportunity. He says in that event he could have
completed remediation for around $10,000.
Right to remedy defective works
- [119] SPC
says that the Partnership did not plead any implied term or principle that the
Partnership was entitled to be given reasonable
opportunity to remedy defective
works. If there is such an obligation, I agree that it can only be by an express
or implied term
or alternatively as a facet of a party’s obligation to
mitigate loss.36 Neither was pleaded, nor
was an application to amend made, despite the issue being raised by SPC in
opening submissions. I do not
need to rely on any pleading point because of my
views on the substance of the matter.
- [120] Where
there is an express term providing for the contractor to remedy defects during a
defects liability period, it is generally
implicit that they are entitled to the
opportunity to return to remedy them.37 If
the principal denies the contractor of that right, it is usually unable to
recover damages of any greater value than what the works
34 BoE of Sam Pemberton, paras 73 to 84 [201.0072].
35 BoE of Anthony Burman, para 21 [201.0059].
- See
Stephen Furst and Vivian Ramsey Keating on Construction Contracts (11th
ed, Sweet & Maxwell, London, 2022) at
[11-031].
37 Pearce & High Ltd v Baxter &
Baxter [1999] EWCA Civ 789; [1999] BLR 101 (CA).
would have cost had the contractor completed them.38 However, here
there is no express term between the parties entitling the Partnership to remedy
defects, nor an express term entitling
the Partnership to notice giving the
opportunity to remedy them. It is common ground that there is an express
provision for payment
of retentions of 10 per cent but that says nothing about
any right to remedy defects arising. Retentions can be held for security
to
either secure performance, or to pay others to remedy the
defects.39
- [121] The
Partnership relied upon Smeaton Construction Ltd v Garrett Pasquale
Ltd40 as supporting some general
principle or implied term in the context of an oral contract. That case does not
assist. The basis for
the High Court’s decision in Smeaton that the
head contractor could not recover the costs of rectifying an issue with sealing
the decks of a house was because there was
no breach of contract by the
subcontractor in the first place.41 That is a different proposition
to contending, as the Partnership does here, that in the event of a breach,
there is an implied right
to be given an opportunity to rectify.
- [122] The
correct legal assessment requires a consideration of SPC’s conduct through
a lens of the duty to mitigate. That is,
where one party breaches a contractual
term, the other party to whom the obligation is owed has a duty to mitigate
their loss.42 The Partnership did not plead a failure to mitigate,
but in any event, I accept SPC’s submission that there is no breach of
that duty for the reasons set out below.
- Pearce
& High Ltd v Baxter & Baxter, above n 37. Compare Maersk Oil UK Ltd v
Dresser-Rand (UK) Ltd [2007] EWHC 752 (TCC) at
[649]–[651].
39 Compare the definition of
“retention money” in the Construction Contracts Act 2002, s 18A.
40 Smeaton Construction Ltd v Garrett Pasquale Ltd [2012]
NZHC 3079.
41 At [31] and [35]–[36].
42 Wu v Body Corporate 366611 [2014] NZSC 137, [2015] 1
NZLR 215 at [134]. This seems to me to be the effect of Owners – Strata
Plan 89041 v Galyan Pty Ltd [2019] NSWSC 619 at [20]–[21], referred to
me by the Partnership; and see Smeaton Construction Ltd v Garrett Pasquale
Ltd, above n 40, at [35].
Mitigation
- [123] A
party need only act reasonably in mitigation.43 It is for the
Partnership to establish that SPC did not meet this
obligation.44 It is a difficult burden to
discharge, even where a party has acted badly.45 The onus on the
defendant is not met simply by demonstrating that it would cost less in nominal
terms if different steps were
taken.46
- [124] The
plaintiff’s response to the defendant’s wrong is judged, not in
hindsight, but according to the circumstances
as they appeared at the
time.47 The Court will not scrutinise too closely a plaintiff’s
actions to mitigate taken reasonably and in good faith for this purpose,
and
will avoid the temptation to judge by hindsight. Moreover, if mitigating steps
are in fact reasonably taken, the claimant is
entitled to recover as damages any
additional expenditure incurred in pursuing those reasonable
steps.48
- [125] I set out
at [42]–[65] the communications between the
parties during December 2016 and into the following year as remediation
continued. In summary, the
position was this: following identification of the
unsuitable fill issue and as it was being remediated, SPC endeavoured to keep
Mr
Newell up to date and sought his input. Mr Newell’s position continued to
be that the issue was one of poor design. He
was asked on 13 December 2016 to
“make [himself] available ASAP to come to site to discuss the filling and
compacting [he]
undertook there.” Mr Newell’s immediate response on
that same day was to outline why he regarded the issue as a design
problem and
he did not respond to the request to head out to the site. Mr Newell said:
“Will call you next time we are rained
off and come have a look.”
Following these communications, SPC wrote to Mr Newell on 21 December providing
an update of a meeting
with the Principal and other parties on site. It was
obvious that SPC was taking steps to remediate in the meantime, given the
upcoming
completion date for
43 Marlborough District Council v Altimarloch Joint Venture Ltd
[2012] NZSC 11, [2012] 2 NZLR 726 at [55] per Elias CJ citing British
Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways
Company of London Ltd [1912] UKLawRpAC 43; [1912] AC 673 (HL) at 689.
44 Payzu Ltd v Saunders [1919] 2 KB 581 (CA) as cited in
Pipes NZ Ltd v Steel Co Ltd [2014] NZHC 1216 at [102].
45 Pilkington v Wood [1953] 1 Ch 770.
46 White v Rodney District Council (2009) 11 NZCPR (HC) at
[30]–[32].
47 Hooker v Stewart [1989] NZCA 407; [1989] 3 NZLR 543 (CA) at 547 affirmed
in Frucor Beverages Ltd v Blumberg [2019] NZCA 547, [2020] 2 NZLR 51
at [96].
48 White v Rodney District Council, above n 46, at [30]. See also Pipes NZ Ltd v
Steel Co Ltd, above n 44, at [103]
citing Andros Springs (Owners) v World Beauty (Owners) [1970] P 144 (CA)
at 156.
Stage One and the risk of an adverse finding that it was responsible for the
delay resulting.
- [126] When Mr
Sheppard became more direct about the Partnership’s potential liability
for the non-compliant fill that was being
discovered (in February 2017) Mr
Newell continued to say that the issue lay between HDG and SPC. Mr Newell was
aware remediation
work was ongoing.
- [127] Reading
the chain of communications as a whole, I have formed the view that this is not
a situation where a contractor has been
denied the opportunity to remediate when
it otherwise would have. Nor is there any issue of SPC acting unreasonably.
Rather, as some
of the SPC emails convey, SPC was seeking Mr Newell’s
engagement and was keeping him in the loop. Mr Newell was aware that
SPC was
undertaking the works required to remediate.
- [128] Accordingly,
even if there was an implied contractual obligation to offer the Partnership an
opportunity to remediate, or seen
another way, that this was appropriate as a
mitigating step by the Partnership, there has been no breach of those duties.
The Partnership
was kept appropriately informed and could have stepped in to
undertake the work, had it wished to.
- [129] Before
moving on I note a further issue raised. The Partnership says that its conduct
in January 2016 is relevant to the issue
of whether it would have remediated the
defective work. Mr Talbot submitted that when water was observed in the pit when
Mr Newell
came back to fill in the five-metre expressway area, Mr Newell did in
fact get a digger in to look into this and remediate despite
his position at the
time that this was an issue caused by defective infrastructure design and
implementation. Mr Talbot submitted
that this shows he would have remediated the
defective fill in 2016/2017 if given the opportunity. I disagree that the
January 2016
incident provides any particular evidential assistance. The matters
in issue here relate to ongoing remediation being undertaken
over a course of
months. Moreover, as Ms Whitfield submitted, the work done in January 2016 was
using SPC’s digger and operator,
not work done by Mr Newell/the
Partnership.
- [130] I now turn
to the contention that the Partnership could have done the remediation work for
only $10,000 in the space of a week.
Mr Newell’s proposition was that his
bulk earthwork machinery (bulldozer) was appropriate and that he could have
applied an
approach of “find and follow” using that equipment. The
issue here is not with the rates charged for SPC’s equipment,
but that the
bulldozer would have done the job much more efficiently in terms of cost and
time.
- [131] I reject
this assertion. First, it is made in hindsight. Secondly, I heard evidence on
how a digger operates relative to a bulldozer.
The former can work in a more
confined space or isolated area and I accept the evidence that use of a digger
was more appropriate
for the work than the bulldozer Mr Newell said he would
have used. In particular:
(a) When an issue with Lot 74 was first identified, HDG told SPC that “we
will need a digger to do some pot holing in this
area to chase out the soft
material”.
(b) The failed fill was originally thought to be limited to Lot 74 but as SPC
sought to chase out the fill it became apparent it
extended further. The full
scope was not something that could have been known in advance. In substance,
what started as an exploratory
process in a small area expanded as remediation
played out into a much bigger issue.
(c) While Mr Newell said he could have chased out fill with the bulldozer by
pushing material around, Mr Pemberton said that by the
time this work was being
undertaken the area surrounding it included finished footpaths and a reserve,
installed utilities and services,
a road and a finished right of way. It was a
situation where care needed to be taken not to damage any completed areas, nor
was it
appropriate to push material into those areas. I accept that evidence.
(d) The proposition that the work could have been done far more effectively
using a bulldozer suggests that SPC, as an experienced
contractor faced with the
events as they unfolded, was not endeavouring to remediate as cost effectively
as possible. Although it
was seeking to avoid any liability for the
remediation
work and any basis for liquidated damages, it was in SPC’s interests to
minimise the costs and time in the event its argument
did not prevail.
- [132] Accordingly,
there was nothing unreasonable or irrational about SPC’s use of a digger
for the remediation work on Lot
74 or then on the other affected lots. To the
contrary, I accept it was the appropriate equipment for the job.
- [133] Mr Newell
did not own a digger, nor could he operate one. Had he recognised a digger was
needed and was faced with undertaking
remediation, he would have needed to
engage a third party (no doubt, SPC). Therefore, if Mr Newell did take up an
opportunity to
remediate, in my view, in effect, the appropriate course would
have been for SPC to undertake that role in any event.
- [134] In
evidence, Mr Newell said he offered to meet with the geotechnical engineer
appointed by SPC’s insurer and is critical
that this offer was not taken
up. With due respect to Mr Newell, he does not have geotechnical expertise. He
was advancing a position
that was contrary to expert views. He continued to
maintain that position contrary to the expert evidence until the last day of
trial.
Mr Pemberton advised that the geotechnical engineer appointed by
SPC’s insurer confirmed it had no claim. I do not consider
SPC can be
criticised, or can be regarded as acting unreasonably for mitigation purposes,
for not taking up Mr Newell’s offer.
- [135] The costs
of remediation are recoverable.
Liquidated damages
- [136] The
Partnership says that the liquidated damages paid by SPC to the Principal are
not recoverable as damages from the Partnership
because they are too
remote.
- [137] SPC was
subject to an obligation to pay liquidated damages under the Stage One Contract
if Lot 74 was not complete by the end
of 2016 at a rate of $20,000 per week. Had
remediation works been ongoing on Lot 74 after that date, these would have
become payable.
However, remediation works on that lot were completed in
time.
- [138] The
Principal did apply liquidated damages of $109,899.15 to SPC under the Stage Two
Contract relating to delay in completing
Lots 71–73. SPC claimed that
these were due to delay due to the remediation works. Liquidated damages applied
at a rate of
$10,684.64 per week. SPC sought to resist this but failed. The
deductions were made under the Stage Two Contract not the Stage One
Contract
because it is under the former contract that the Lots 71–73 earthworks
were undertaken.
- [139] The
Partnership asserts that liquidated damages ought not to have been incurred in
any event because remediation could have
been done by Mr Newell in a week at a
cost of $10,000. I have rejected this contention above. It further says that it
has not been
established that the delays were only attributable to the
remediation of the non-compliant fill. For this contention, the Partnership
refers to communications about practical completion between CKL and SPC where
CKL identifies other matters that needed to be attended
to before practical
completion being:49
Topsoil and seed within 69-73,
removal and replacement of dish channel damaged within both parking bays on Road
1, chip seal and hot
mix of parking bays within Road 1, Road Markings and street
signs for the stage.
- [140] SPC
responded to this email that the site was ready for practical completion to be
issued.50 But in any event, I accept Mr Pemberton’s evidence
that to the extent outstanding matters had any materiality, they were matters
requiring SPC’s attendance consequent on the remediation works that had
been required.
- [141] Moving to
the legal basis for recoverability, in denying liability for the liquidated
damages, the Partnership pleaded the fact
that there was no provision for
liquidated damages in SPC’s contract with the Partnership. That is not
however the key legal
issue. If the liquidated damages SPC paid to the Principal
are recoverable here, it is by usual remoteness
principles.51
- [142] I need not
rehearse the long-established principles cited to me on the test for remoteness
of damage in contract.52 SPC referred me to Steel Co Ltd v Pipes
NZ Ltd.53
49 Email 24/3/17 [305.0778].
50 Email 24/03/17 [305.0778].
51 Furst and Ramsey, above n 36, at [13-093].
- Hadley
v Baxendale (1854) 9 Exch 341 at 345; Koufos v C Czarnikow Ltd (The Heron
II) [1969] 1 AC 350.
53 Steel Co Ltd v Pipes NZ
Ltd [2016] NZCA 175.
There the defendant’s delay in supplying pipes to the plaintiff resulted
in the plaintiff failing to meet strict time constraints
in its contracts to
on-supply the pipes to two third parties. The Court of Appeal upheld the High
Court’s conclusion that liquidated
damages payable by the plaintiff to the
third parties were not too remote on the facts of that case. The Court of Appeal
recognised
that whether these were recoverable depended on the defendant’s
knowledge that the end purpose involved the use of the pipes
in the head
contract and that the defendant would be liable to the third
parties.54
- [143] A head
contractor’s liability to pay liquidated damages to the principal
for delay due to the subcontractor’s breach is not a natural consequence
of delay and hence requires special
knowledge within the second limb of
the principle in Hadley v Baxendale. However, depending on the
factual context, a head contractor’s liability for delay caused to the
principal may be damage that
a subcontractor should have contemplated as a
result of its breach under the first limb. Losses flowing from such delay may in
many
cases be no less than the liquidated damages payable under the head
contract and hence recoverable.55
- [144] Here, Mr
Newell said he did not know at the time of contracting with SPC the details of
the head contract so he did not have
special knowledge that liquidated damages
were payable or at what rate. However, I find that under the first limb of
Hadley v Baxendale it was in the reasonable contemplation of the parties
that SPC was likely to become liable for the consequence to the Principal of
delays in achieving practical completion due to the Partnership’s breach
of contract. That is underlined by the fact that the
parties are experienced in
the industry and had worked together for 18 years.
- [145] The
Partnership contended that the sums paid for liquidated damages were not
reasonably foreseeable by it because they were
paid under the Stage Two
Contract, being a contract between the Principal and SPC entered into two months
after the Partnership had
finished its works.
54 At [76]–[77].
- Furst
and Ramsey, above n 36, at [13-093].
The earlier edition of the same text was cited by the Court of Appeal in
Steel Co Ltd v Pipes NZ Ltd, above n 53, at [73].
- [146] Mr Newell
said he was not aware of the details of the relationships. But accepting that to
be correct, he did know that all
work done by the Partnership would in turn be
work that SPC was contracted to do for the Principal. 56 Moreover,
the parties had arranged for 10 per cent retentions to be held by SPC for 12
months following practical completion of the
relevant works. The
“relevant” works are the earthworks in question, here being those
under the Stage Two Contract.
- [147] Where all
work by the Partnership was being done under subcontract, I do not consider it
makes a difference that SPC became
liable for delay under the Stage Two Contract
not the Stage One Contract. In my view, SPC’s liability to the Principal
for
damages for delay in completion is loss flowing in the ordinary course of
things on the present facts.
- [148] That being
the case, is the sum paid in liquidated damages recoverable as damages for
delay? Liquidated damages provisions are
commonly imposed in a contract to
remove the need to prove actual loss. They are payable provided they are not a
penalty. Until relatively
recently, that has been answered by reference to the
question of whether they are a genuine pre-estimate of a loss likely to flow
from the breach – which in the present context, is the consequence of
delay.57
- [149] In
Steel Co Ltd v Pipes NZ Ltd, the defendant sought to contend in the Court
of Appeal that the plaintiff had failed to lead evidence to satisfy an onus on
it to
prove the liquidated damages it had paid to the third parties were
reasonable. The Court of Appeal considered that there was force
in the
submission that if Party A (in this case SPC) seeks to recover damages from
Party B (the Partnership) equating to the liquidated
damages Party A has paid to
a third Party C (the Principal) then Party A has to prove the reasonableness of
the damages it paid.
However, the Court did not need to determine that issue
because it was too late to raise this evidential issue in the Court of
Appeal.
56 Newell [201.0003] at [7].
57 The test now is whether the consequence is out of all
proportion to the legitimate interests of the innocent party in performance
of
their primary obligations. 127 Hobson Street Ltd v Honey Bees Preschool Ltd
[2020] NZSC 53, [2020] 1 NZLR 179 [Honey Bees] at [56].
- [150] Here, the
Partnership did not place in issue before me whether the liquidated damages
payable by SPC to the Principal were a
genuine pre-estimate of the loss the
Principal would suffer due to delay.58 In my view I am entitled to
take the view that the liquidated damages payable are a reasonable assessment of
damages recoverable by
the Principal from SPC for delay. Hence, the liquidated
damages are recoverable from the Partnership.
Legal fees
- [151] SPC
claims legal fees of $5,803.20 paid to its lawyers, CMC, which were seeking to
contest SPC’s liability for the non-compliant
fill in communications with
the Principal’s lawyers.59 The Partnership rejects that legal
costs incurred by SPC are recoverable in damages.
- [152] CMC’s
total costs are $11,606.40 but no breakdown of the invoices was provided to SPC
by CMC to identify fees relating
to attendances on this dispute and an unrelated
dispute being addressed in the correspondence between the lawyers. The claimed
amount
represents half of the invoiced fees to reflect the costs likely relating
to communications over the non-compliant fill which is
the subject of this
proceeding.
- [153] The fees
are for SPC contesting a position that I have found to be correct, that SPC was
liable under the head contract factually
and legally for the non-compliant fill
discovered in Lots 70–74. These fees are recoverable for similar reasons
to the liquidated
damages claim, being the Partnership’s knowledge that
SPC is subject to contractual obligations to the Principal to complete
the
works. It is within the reasonable contemplation of the parties that if the
Partnership failed to meet its obligations, that
could well involve SPC seeking
to contest that liability for the benefit of both parties.
58 The fact that the test in Honey Bees, above n 57, does not rely on whether the amount
payable is a genuine pre-estimate of loss has no bearing on my analysis. The
point under consideration
here is whether it is appropriate to regard the
liquidated damages as in substance equivalent to damages/reasonable as payable
for
the usual consequences of delay on the present facts.
59 BoE of Anthony Burman, para 17. The invoices and time records
of CMC are at [307.1439], [307.1440], [307.1441], [307.1442] and [307.1443].
- [154] Alternatively,
I consider that SPC contesting liability was a step reasonably incurred by SPC
attempting to mitigate its loss.
In my view, the legal fees incurred by SPC
would therefore be recoverable from the Partnership on this basis.
- [155] I also
consider the allocation of half of the fees is appropriate. This claim
succeeds.
Tort claim
- [156] I
need say relatively little about the cause of action on tort given my findings
on the contract cause of action. The tortious
duty to take reasonable care is
the same as pleaded in the contract claim, with the applicable standard of care
that of a reasonable
and prudent earthworks operator in the particular
circumstances. The Partnership admits they owed this duty. For the same reasons
I identify above in respect to the contract claim, the Partnership was in breach
of their duty to take reasonable care.
- [157] SPC
differentiated the test for foreseeability and remoteness in contract and tort.
On the issue of damages, the Partnership
argued instead that because the causes
of action in contract and negligence lie concurrently, only the contractual test
is applicable
to both claims. That was on the basis that where responsibility is
assumed under a contract it would be anomalous if a party could
say that the
defaulting party had assumed a responsibility for a wider range of damage in
tort. 60 I have found the contractual test met so it is not necessary
for me to address this submission. All three heads of loss would be recoverable
in tort as in contract.
Conclusion on the Landsdale Claim
- [158] SPC
suffered loss in the amount of $248,915.28 ($109,899.15 for liquidated damages,
$133,212.93 for remedial costs and $5,803.20
in legal fees). 61 Once
these amounts are set-off against the retention value outstanding on Landsdale,
the amount owing to SPC is $108,775.66.62
60 Wellesley Partners LLP v Withers LLP [2014] EWHC 556
(Ch) at [68.].
61. BoE of Mr Pemberton at 85 to 87 [201.0073].
62 BoE of Mr Burman at 21 [201.0059].
Interest
- [159] SPC
seeks interest in accordance with section 24 of the Interest on Money Claims Act
2016 (IMCA) which applies to contracts
that were entered into prior to 1
January 2018. This section provides that for pre-judgment interest, s 10 of the
IMCA is not to
be used, rather the matter of interest is left to the
Court’s discretion.
- [160] Under s
24, the Court has a wide discretion to award interest. Even when the IMCA does
not apply, the Courts have frequently
used the internet site calculator of
interest maintained under s 13 of the IMCA.63 I accept SPC’s
submission that this is appropriate here as it is predictable and based on sound
rationale.
- [161] Interest
should run from 30 November 2016 being the date upon which the cause of action
arose.64 I therefore award interest in accordance with the calculator
maintained under s 13 of the IMCA from 30 November 2016 to the date of
payment.
RANGITAHI CLAIM
- [162] I
move now to the Rangitahi Claim. The dispute relates to whether SPC was entitled
to make three deductions from an invoice
issued by the Partnership in September
2018 for works undertaken in May 2018. The deductions total $29,796.27. However,
SPC overpaid
the Partnership from the amount invoiced in the sum of
$4,253.21 so the net amount in dispute is $25,543.06. The issues in relation to
Rangitahi are modest relative to a contract value
to the Partnership of over
$1.2 million.65
- [163] There was
disproportionate oral and documentary evidence devoted to these issues given
their monetary value. I have considered
all this evidence but have not
explicitly addressed all of it in this judgment. Rather, I express my views in
relatively conclusionary
form by reference to the facts as I find
established.
- See,
for example Blumberg v Frucor Beverages Ltd [2018] NZHC 1876, [2018] 3
NZLR 672 at [76].
- Interest
on Money Claims Act 2016, s 9(1)(a)(i). CKL’s notice on 25 November
advised that if the earthworks were not completed
in 5 days (so by 30 November),
the reasonable costs of the
works undertaken by others shall be
recoverable by the contractor, and it was therefore from that date that costs
began to accrue:
304.0666.
65 BoE of Anthony Burman, para 16.
Item (a) – Deduction of $21,625.52
- [164] SPC
says that the Partnership wrongly invoiced $21,625.52 for cut to fill volumes
that relate to fill actually placed by SPC
not the Partnership in the month of
May 2018.
- [165] Mr Newell
left the Rangitahi project part way through a month, on 16 May 2018. I accept
SPC’s evidence that it continued
to undertake cut to fill works after the
Partnership left.66 However, the invoice issued by the Partnership
reflects the full certified volumes for the whole month. I agree that a
deduction needs
to be made so as to allocate the sum claimed between the volume
of works undertaken by the Partnership and the volume of works undertaken
by
SPC.
- [166] The way
this came about needs some explanation. It is common ground that until this
invoice, the Partnership invariably invoiced
on the basis of topographical
information provided by SPC from which the Partnership worked out quantities of
fill it had placed.67 In this instance, SPC was dilatory in providing
any topographical information. Mr Newell was pressing for the information so he
could
invoice for the works he had done in May. It is part of the context for
the dispute that by this time the parties were falling out
and there was
significant distrust by Mr Newell.
- [167] Mr Newell
obtained screenshots of topographical information for May from his daughter, who
at that time, was working with SPC.
I accept SPC’s evidence that these
convey that the total quantity moved in May 2018 was 8,689 m3.68
Mr Newell says that he then invoiced for 8,660 m3 and that this
was derived from the load counts that he had recorded in his notebook for May
2018, and which he produced. This volume
is in effect the whole of the certified
quantities for May, not just those moved up until 16 May 2018.
- [168] The
evidence was that load counts are an inaccurate means of measurement, given that
loads are not necessarily full loads, and
that it relies on manual recording. Mr
Newell acknowledged this in communications with SPC. The Partnership
says
66 BoE of Nathan Sweetman, para 7.1.
67 NoE, page 165, lines 19 to 25.
- Calculated
by adding the 3,018.7m3 (measured in the cut); 2,542.7m3
(measured in the fill); 3,127.6m3 (measured in the
cut).
that in this instance the load counts in Mr Newell’s notebook are an
accurate measure. It says that if SPC completed any work
after Mr Newell left
the site, it was in addition to the cut to fill volumes placed by the
Partnership.
- [169] However,
the certified amounts for the month cannot be disputed. I accept SPC’s
evidence that it took over with further
works when Mr Newell left. That is
supported by whiteboard daily activity information referred to by Mr Sweetman
recording cut to
fill by SPC. It is also supported by Mr Pemberton’s
evidence, which I accept, that SPC continued work on the site.
- [170] I also
accept Mr Sweetman’s evidence that the allocation in the invoice between
the work done by the Partnership and SPC
was undertaken based on the
topographical information. He confirmed the area of work undertaken by SPC by
the use of topographical
survey using Leica equipment.69 He referred
to the software that could run a volume report on a surface comparing to another
surface, or could run an area report,
so that it would have been an area report
used.70 He said, and I accept, that he erred on the side of caution
and was more generous to the Partnership.71 The allocations made were
reasonable.
- [171] Accordingly,
the Partnership is entitled to be paid for 6,148 m3 (being the
certified volume of 8,724 m3 less 2,576 m3 calculated as
being undertaken by SPC). This is reflected in the deduction made to the
Partnership’s invoice.
Item (b) – Deduction of $3,910
- [172] SPC
made a deduction of $3,910.00 for remedial works undertaken by SPC to remove
fill placed by the Partnership that was too
wet.
- [173] The
Partnership acknowledges that fill it placed had become wet due to the weather
and did not pass compaction testing. However,
it says that SPC is not entitled
to charge for this work as the weather caused the issue, and standard practice
would be to wait
for the weather to get better, dry the fill and recompact
it.72
69 BoE of Nathan Sweetman, para 9.
70 NoE, page 188, lines 1 to 3.
71 BoE of Nathan Sweetman, para 9.
72 [201.0001], para 59(e).
- [174] Mr Newell
said the Partnership left the site due to bad weather with the agreement of SPC
rather than abandoning the site. I
do not see that anything turns on whether he
is correct.
- [175] The cost
to remove the wet fill was calculated by using a rate of $6.80 per
m3, being the rate that Mr Newell used for “cut to
stockpile” as evidenced in his May 2018 invoice. Mr Pemberton’s
evidence was that:73
This was a comparable rate because
it reflected the same scope of work to be carried out. We did not consider it
fair to use the rate
that we would have charged to Rangitahi because this
included a margin, so we used Wayne’s own rates for this rework.
- [176] Remediation
of the failed fill was required. The quantity of failed fill is included in the
quantities the Partnership has claimed
payment for. It should not have been as
it was fill that, to Mr Newell’s knowledge, had failed specification and
was going
to require remediation. Accordingly, in my view the deduction is
appropriately characterised as a deduction to remove a fee for the
placement of
non-compliant fill that should not have been charged for. If a deduction is not
made, the Partnership is being paid
in full for fill which needed to be
remediated, that is, the work by the Partnership was of no benefit to
SPC.
- [177] Mr
Sweetman’s evidence was that the deduction is significantly less than
justified given that it reflected a quantity
of non-compliant fill of 500
m3 not 1,030.4 m3. He believes that it was because Mr
Wright of SPC was trying to err on Mr Newell’s side of the equation.
SPC’s deduction
is fair and reasonable (that is, lower than contractually
justified) and I accept it.
Item (c) – Deduction of $4,260.75
- [178] SPC
made a deduction of $4,260.75 for works SPC says it undertook to rectify topsoil
that was placed too thick by the Partnership.
- [179] The
Partnership invoiced for spreading topsoil in an area of the site. The topsoil
was spread too thickly. This was recognised
by Mr Newell. In the invoice
the
73 BoE of Mr Pemberton, para 116.
Partnership had charged $5.00 per m3, not his usual rate of $5.30 per
m3. In an email of 3 October 2018, he explained: “Trimming of
topsoil. Extra thick in some areas in my a/c you will see I charged
some at
stockpile rate this covers extra work”. By this Mr Newell meant he charged
less than his usual rate for spreading topsoil
(which is
$5.30 per m3) and instead charged $5.00 per m3,
his stockpiling rate, to leave
30 cents per m3 for someone to remove the additional thickness to
stockpile or some other use.
- [180] Rather
than accepting this approach to dealing with the excessively thick layer of
topsoil deposited by the Partnership, SPC
instead adjusted the amount invoiced
to pay the Partnership for the full thickness of topsoil at the
Partnership’s full rate
of
$5.30 per m3 but SPC then deducted the actual costs it incurred to
trim the topsoil so that it was to the right thickness.
- [181] In my view
SPC’s approach is correct. It pays for the work done at the charge for
spreading, but appropriately deducts
from the invoice a sum reflecting the cost
of remediation required due to the topsoil being placed too thickly.
Conclusion
- [182] I
acknowledge Mr Newell’s frustrations with the delays he experienced in SPC
providing information for him to produce
his invoice. I also acknowledge
that Mr Newell has come to be highly distrustful of SPC with the breakdown of
what had previously
been a positive and mutually respectful relationship.
However, in my view on the evidence before the Court the deductions are
appropriate.
Moreover, the evidence demonstrates that SPC was seeking to be
reasonable in the way it approached the May invoice. It halved its
claim for the
area of remediation of the failed fill. It also provided a higher amount for the
compactor and diesel than Mr Newell
himself had allowed. The overall result is
fair to the Partnership, if not favourable.
OVERALL CONCLUSION
- [183] I
award judgment in favour of SPC on liability in the sum of $108,775.66 on the
Landsdale Claim plus interest in accordance
with the calculator maintained under
s 13 of the IMCA from 30 November 2016 to the date of payment.
- [184] I dismiss
the Partnership’s claim for deductions from its Rangitahi
invoice.
- [185] SPC has
been successful. I will receive submissions on costs and as to interest
calculation by SPC within 14 days and from the
Partnership within a further 14
days.
Anderson J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/2676.html