NZLII Home | Databases | WorldLII | Search | Feedback

High Court of New Zealand Decisions

You are here:  NZLII >> Databases >> High Court of New Zealand Decisions >> 2023 >> [2023] NZHC 2676

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Newell v Sam Pemberton Civil Limited [2023] NZHC 2676 (26 September 2023)

Last Updated: 13 October 2023

IN THE HIGH COURT OF NEW ZEALAND HAMILTON REGISTRY
I TE KŌTI MATUA O AOTEAROA KIRIKIRIROA ROHE
CIV-2019-019-813
[2023] NZHC 2676
BETWEEN
WAYNE WILLIAM NEWELL and DENISE MARION NEWELL
Plaintiff
AND
SAM PEMBERTON CIVIL LIMITED
Defendant
Hearing:
17-21 July 2023
Appearances:
M D Talbot for the Plaintiff
V A Whitfield for the Defendant
Judgment:
26 September 2023

JUDGMENT OF ANDERSON J

This judgment was delivered by me on 27 September 2023 at 3.00 pm pursuant to Rule 11.5 of the High Court Rules 2016.

....................................

Registrar/Deputy Registrar

Solicitors: Talbot Law Ltd, Hamilton

Bluett Legal, Hamilton

NEWELL v SAM PEMBERTON CIVIL LIMITED [2023] NZHC 2676 [26 September 2023]

TABLE OF CONTENTS

Para No

INTRODUCTION [1]

WITNESSES [5]

LANDSDALE CLAIM [7]

Issues [7]

Factual and technical background [12]

Placement of suitable fill [24]

Geotechnical specifications [31]

Discovery of non-compliant fill [37]

Engineer’s decision on cause of fill failing specification [67]

Contractual obligations [84]

Preliminary [84]

When were the Addendum Specifications provided? [91]

Contractual position on the Addendum Specifications [96]

Breach of contract [101]

Breach of obligation to meet Addendum Specifications [101]

Breach of implied obligations [103]

Damages for breach of contract [115]

Remediation costs [118]

Right to remedy defective works [119]

Mitigation [123]

Liquidated damages [136]

Legal fees [151]

Tort claim [156]

Conclusion on the Landsdale claim [158]

Interest [159]

RANGITAHI CLAIM [162]

Item (a) – Deduction of $21,625.52 [164]

Item (b) – Deduction of $3,910 [172]

Item (c) – Deduction of $4,260.75 [178]

Conclusion [182]

OVERALL CONCLUSION [183]

INTRODUCTION

$140,139.621 whereas SPC says it is entitled to set-off and counterclaim for losses

suffered due to the Partnership’s defective works. Specifically, Lots 71–74 at the site contained fill which was unsuitable and failed to meet specifications. The net total of SPC’s claim is for $108,775.66. SPC claims in contract or alternatively in tort for negligence by the Partnership in carrying out the earthworks.

WITNESSES

1 All figures are GST inclusive as they were presented this way by the parties.

(a) Samuel Pemberton, a director and shareholder of SPC. Mr Pemberton gave evidence of the contractual arrangements between the parties and the events giving rise to the disputes.

(b) Anthony Burman, Chief Financial Officer for SPC. Mr Burman provided calculations of amounts owing and amounts paid by SPC. His evidence was taken as read (with a minor correction being made) and these numbers as corrected are now undisputed.

(c) Nathan Sweetman, a contractor manager employed by SPC. Mr Sweetman assessed the correct quantities and amount owed to the Partnership in response to its invoice on the Rangitahi development.

(d) Andrew Holland, a geotechnical engineer and director and shareholder of HDG Geo Ltd (HDG). He was involved in relevant events and provided expert views on technical aspects including why the Landsdale lots required remediation.

(e) Stephen Crawford, an independent geotechnical engineer. Mr Crawford gave evidence on his views of the most likely cause of the deficient fill and on what can be expected of a reasonable earthworks contractor.

LANDSDALE CLAIM

Issues

(a) What was the scope of the Partnership’s obligations in contract or tort in respect to the cut to fill earthworks?

(b) Was the Partnership in breach of those obligations?

(c) If so, what damages are recoverable?

evidence was that when the Partnership placed the fill it was compliant but subsequently became non-compliant. He said this was due to deficiencies in the sub-soil drainage design or installation and/or because compliant fill had degraded due to the deposit by SPC of unsuitable materials on the surface of Lots 72–74 at the instruction of Landsdale. In closing submissions, the Partnership advised that it no longer sought to advance these hypotheses for how the site came to need remediation. It conceded that it placed non-compliant fill. That was a responsible concession. Neither of the hypotheses advanced by Mr Newell were technically or factually credible.

Factual and technical background

  1. That is because Mr Newell’s evidence at trial as to why the fill was non-compliant is inconsistent with the concession because he was contending that it was other than because the Partnership deposited non-compliant fill.

(a) A contract dated 15 January 2015 for earthworks for stages one to four, and civil works for stage one (the Stage One Contract).

(b) A contract dated 3 October 2016 for civil construction works for stages two to four (the Stage Two Contract).

Cut from formation alignments to subgrade level Roads, Row’s [sic], berms, footpath, batters, vehicle crossings and building platforms. Spread and compact on site as controlled fill where shown on the plans, and as directed by the Geotechnical Engineer.

We never placed any cut to fill on this job. Everything that we were paid by the engineer of the contract as certified quantities within the payment certificates was handed straight through to [the Partnership].

3 Notes of Evidence (NoE), page 174, lines 34 and 35, page 175, line 1.

placed too dry or too thick, air voids are created and will absorb the water, causing the soil to lose strength.

Placement of suitable fill

and does not bind. When it is too wet it is too sloppy (and unworkable with machinery).

tests and has never been required by SPC or any other head contractor to provide those test results, including on the Landsdale Development.

Geotechnical specifications

observation for the Landsdale Development”.4 The document provided for HDG to undertake independent inspection and acceptance testing to enable completion reporting and to assist the Engineer in determining whether the placed fill met specification.

The Contractor is required to do sufficient testing to ensure that they are meeting the specification in relation to compaction. [HDG] will be undertaking independent testing to enable completion reporting and to assist the Engineer in determining if the placed fill meets the Specification. During fill construction each lift may be subject to inspection and approval by the Engineer to confirm that the required compaction standards have been achieved. This testing is completed as a check in addition to the testing completed by the contractor.

Cohesive material

  1. Mr Newell said in evidence that: “Until [the Partnership] received discovery documents in this proceeding, I understood HDG was the Geotechnical Engineer to the contract responsible for all testing. I did not know that HDG was working for the developer Landsdale, not for SPC, so I did not know that SPC was also responsible for a tier of testing in the contract.” If this is intended to suggest Mr Newell did not have the document until then, it is incorrect, given that the material pages of the document were produced in the Partnership’s discovery.
  2. Specifications [307.1455]. Refer also email to Mr Newell with table setting out requirements [303.0410].

Discovery of non-compliant fill

1.2 metres and 1.4 metres, there were low shear vane readings of 34 kPa and 65 kPa. These are extremely low readings. The specifications required average strength of 150 kPa. By the same communication, HDG told SPC that “we will need a digger to do some pot holing in this area to chase out the soft material”.

contracts. SPC notified its insurers with a view to seeking to claim under its liability policy.

... can you please make yourself available ASAP to come to site to discuss the filling and compacting you undertook there. It looks like at this point the wet, failing material is chasing out over multiple lots and may end up being a rather large issue. There may be some significant remediation work involved. We are keen to try and get to the bottom of it prior to doing too much work, that way everyone knows where we are all at before commencing. At this stage it is difficult to ascertain where the problem lies, with the client and ground conditions being the issue, with the Geotechs and their testing or with yourself and the placement of the fill. We have also engaged another Geotech engineer to review all of the test results and he has been to site to view the material, which will have a cost associated. We are also awaiting his determination. If you are available over the next few days to look at the area let me know when would suit you. If you have any diary notes from instructions given by the [HDG] guys, this may be beneficial to pull out and bring along.

Will call you next time we are rained off and come have a look.

6 Email 29/11/16 [304.0669].

7 Email 13 02/16 [304.0677].

The area that you guys dug out was filled in the 14/15 season. Andrew and Emily did the inspections and testing. The first season the fill was mainly on the dry side. The gully was filled to design and the preload placed. The areas to be filled were inspected by [HDG] before any fill was placed. The fill was placed in 200/300 mm layers and compacted, every 600 mm a compaction test was then done. When the tested layer was confirmed to be within spec more fill was then placed. The size of the area and the shear strength of 30 kPa, a soft area would have been easily noticed The problem is water moving from the natural ground into the fill. Your photo of water in the hole after excavating the soft area goes a long way to confirming that. As there was no attempt to prevent water from getting into the new fill placed, a test in say 12 months’ time will be further confirmation.

8 Email 14/12/16 [304.0679].

9 Email 16/12/16 [304.0678].

10 Email 20/12/16 [304.0682].

at [21], water moving into soil above the rock blanket is intended and not an issue, provided the fill placed is compliant fill.

Will keep you in the loop how things proceed. At this stage once we chase more of the wet material out and see how far it goes / possibly find the cause, a determination will be made then. So looking at early next year.

...

[Stage Two] is due to be completed in early Feb and as with the 1st stage Liquidated damages will apply for late completion. We would like to get to the bottom of the issue in this area ASAP, as this area will need remediated [sic] and completed prior to the end of Jan 2017. Do you have gear available for this?

Again I will be onsite during this week if you would like to head out, and we will be happy to dig a couple of test pits for inspection.

I am leaving in a couple of weeks and thought I would get something on email in relation to the couple of issues we have encountered at Landsdale with the earthworks. I have had a conversation with Josh in regards to these couple of issues as he wants to get these sorted ASAP, but understand given the nature of them may not be sorted until after I go.

11 Email 21/12/16 [304.0684].

12 Email 31/01/17 [304.0702].

Wet material in lot 74 (and continuing into lot 73 etc) at a depth of approx 2-3 m. At this stage we have lodged an insurance claim with our insurers who have appointed another geotech company to investigate. We are awaiting their report but should be through in the next few days fingers crossed. We have to date used our machinery to remediate lot 74 as this lot was in stage 1B which had a fast completion date and liquidated damages applying to it. In hindsight an insurance claim with your insurance company might have been the better way to go as you were the earthworks contractor. It maybe [sic] something you might like to look into as although we are fighting the fight so to speak in regards to what the issue is down there we don’t know how that will end and what decision will be made. To date in this area we have kept our hours and costs and is currently sitting at $20,140 ex GST. We are hoping the wet material yet to chase out isn’t a large amount more. To remediate this work looks to be digger and roller work which we will keep the hours on.

Happy to meet again on site to discuss further if you wish. Given that im [sic] taking off in a couple of weeks probably a good idea that we get Josh along too so the next person knows whats [sic] going on. He’s currently working in Auckland a bit so might need a day or so notice to come out. Let me know what you’d like to do.

The bottom line is on this issue, is that once the problem was raised through [HDG] doing the lot validation testing in their completion report, we had a matter of days to complete the remediation of this unsuitable in lot 74 in stage 1. Otherwise [liquidated damages] of $21,369.27 per week would apply. We were instructed by the client in accordance with our contract NZS:3910 to make good and had 5 days to commence. You don’t have the appropriate equipment to remediate this issue, as it is isolated and confined and is digger work, so we have done this work. We still have lots 73 and beyond to excavate and remediate at this point, but they are in the next stage and still to be done.

You may be getting the wrong end of the stick from my emails. We have already been battling this with all parties for the last three months, and have got to the point of getting our insurer involved. What we are after is the support from you in the form of records, photos, reports, emails etc to come out the other end of this at the very least covering our costs, as we think it will end in court with Pepper/[HDG] as the costs are building fast. The issue does lie between you and [HDG], as you are the earthworks contractor, however we are the meat in the sandwich trying to achieve an outcome to resolve this at no cost to either of us.

I fully understand what you are going through its not nice arguing about these things. I don’t keep records etc when placing fill, all emails on tests and inspections are sent to you and me this is all we have.

13 Email 1/02/17 [304.0712].

14 Email 3/02/17 [304.0717].

You say you have engaged your insurance co and a geotech and it could end up in court it might be a good idea to pass this info on to them I am happy to meet with your Geotech and show him where he can augur down to confirm this

You say in your email that I might have the wrong end of the stick on something in all of this

The info and comments from me are as it happened, as the work was done, no more no less, and for your use as you see fit

Earthworks continuing within lots 70-73. Pot hole observed within Lot 73 to determine extent of unsuitable material. Material generally looked consistent and hard. [HDG] to complete augers around area to determine if all unsuitables have been removed.

These items include cut to fill within lots 69-73/remediation of lots 72/73, Topsoil and seed within 69-73, removal and replacement of dish channel damaged within both parking bays on Road 1, chip seal and hot mix of parking bays within Road 1, Road Markings and street signs for the stage.

Dishchannel [sic] won’t be removed I’ve view [sic] the repairs and am happy, [L]ance was also happy with this on the last stage.

15 Minutes 7/02/17 [304.0722] at [304.0724].

16 Email 24/3/17 [305.0778].

17 Email 24/03/17 [305.0778].

Go and view the site, I did yesterday and it looks great.

Please issue practical completion and start this process with HCC.

Engineer’s Decision on cause of fill failing specification

While it is not possible to definitively identify the cause of the soft fill in the area of Lot 74, there are a number of observations that suggest possible/probable causes. The contractor who placed the majority of the fill in gully 2 typically favoured a dry, hard fill and was often struggling with the air voids specification. Lot 74 is in a transition area from fill to natural, and lift control appears to be less accurate than in the layers above the soft fill (where the transition is buried). My opinion is that these factors combined to create an area with thicker lifts, sometimes uncontrolled, minimal compaction in some layers and high voids that was placed below specification and in some places has been able to soften significantly with an increase in moisture

18 Email 13/12/16 [305.0781] at [305.0783].

content. It may have been put in place wet, and further softened, or dry and hard with high voids and subsequently softened. It is likely a combination of both mechanisms for the various layers.

(a) The material found as at 13 December 2016 was typically a mix of ash soil with layers of what appeared to be swamp deposits (unsuitables in the base of the gullies).

(b) Soft material was encountered in layers and often observed in large thicknesses. He noted that directly above the subgrade was the thickest mass which included a large portion of swamp material. The soft material then extended into layers, the most significant being approximately one metre thick.

(c) He observed at least two layers of significant unsuitable material in the overall layer of soft material with a few isolated layers at shallower depths. Layers of swampy soft material were encountered in layers up to 100 millimetres thick within hard “EC Fill”. In the lower part of the excavated area, the soft material (ash mixed with swamp deposits) was more than one metre thick. The main layers of swamp material were up to 200 millimetres to 300 millimetres thick and within soft ash.

(d) Natural subgrade exposed was hard and relatively dry.

(e) Engineered fill above and below was high strength with obvious thin layering.

with the original opinion expressed on 13 December. He referred to isolated areas within Lots 72–73 noting that soft material was encountered at a shallower depth to the initial Lot 74 excavation containing a large amount of unsuitable alluvial material mixed with ash.

19 Email 28/03/17 [305.0780].

20 Email 29/03/17 [305.0786].

to a pre-start meeting held on site in which it was recorded that SPC did not own a nuclear densometer and that therefore shear vanes would be carried out for indicative kPa testing only and recorded daily. SPC sought to tie this into clauses of the contract relating to the respective responsibility between the parties.21

It is important to note that no physical evidence, testing results or expert analysis was provided with the Contractors [sic] arguments. As [HDG] are experts in the field of soils and have provided information based on investigations, sampling and testing a level of weighting to their findings has been given.

Well I’ve done my best.

Its lawyers now, if we want to go any further. What’s your thoughts?

21 Email 1/05/17 [305.0819].

22 Letter 21/06/17 [305.0918].

23 Mr Holland’s reports reference to above.

24 Email 22/06/17 [305.0923].

Contractual obligations

Preliminary

Spread and compact [fill] on site as controlled fill where shown on the plans,

and as directed by the Geotechnical Engineer.

is common ground that Mr Newell did receive the Addendum Specifications at some point, as the document was provided on discovery by the Partnership.

When were the Addendum Specifications provided?

documents, and also noted that at the time Mr Newell’s daughter was working with SPC so it was no issue retrieving them.

Contractual position on the Addendum Specifications

Breach of Contract

Breach of obligation to meet Addendum Specifications

Breach of implied obligations

(a) To exercise reasonable skill and care when performing its services.25

(b) To undertake its work in a proper and competent manner.

(c) To use the “placement and compaction” methodology referred to in the “CKL specification” to the head contract.26 In closing, Mr Talbot described this as an obligation to use the “industry standard placement and compaction methodology” described in Mr Newell’s evidence, being the methodology he had used for 40 years as follows:

  1. I do not accept that the Partnership placed any unsuitable fill. I used the same methodology I have used for 40 years on this job. Each scoop load of carefully selected fill is spread at approximately 200-300 millimetres deep over an area approximately 3 metres wide and 45 metres long. The next scoop load continues on from where the last spread finished and so on until the area to be filled is covered. As we are placing the fill, our soil compactor works continuously on the fill that has already been placed, leaving the outside tyre mark on the spread untouched as the guide for the next lot of fill to be spread. Any area of fill before compaction that appears thicker than 200- 300 millimetres is trimmed by the compaction blade.
  1. Each layer of fill, after about 6 or 8 passes of the compactor, is compacted to approximately 200 millimetres thick. My observation of the compactor wheels and pads is a constant guide to the quality of the compaction. The compactor pad indent left on the fill is ideally a constant 30 millimetres, meaning the fill will be within the required compaction specifications. Indents any shallower than 30 millimetres means the fill material is likely to be getting drier than the optimum required moisture content, and air voids will start to climb above the maximum allowable 8%. If fill appears drier than the optimum required moisture content, that fill needs to be reworked and wet.

  1. Para 14 of the Reply by Plaintiffs to Defendant’s Statement of Defence and Counterclaim dated 30 June 2023 [101.0026].

26 Refer 2.17.1-2.17.8 at [302.0106].

  1. If the indents left by the compactor are getting deeper than 30 millimetres, this indicated fill wetter of the optimum required moisture content and the sheer strength will begin to fall. I monitor these areas of plus or minus of the 30 millimetres with my own shear vane. This methodology has served me well over my 40 years of earthmoving as it did in the placement of 122,000 cubic metres of fill at Landsdale.
  1. I do have a shear vane, which I use on site to test areas that may not appear to have passed our own compaction requirements. These shear vane tests are carried out for our internal purposes only to confirm whether a particular area needs reworking. We do not record the results of these tests and we have never on the Landsdale contract, or on any other contract, been required by SPC or any other head contractor to provide our test results.
  1. When we placed each 600 millimetre layer, so 3 layers of 200 millimetres, the filling process stopped, and we had to notify the SPC that a layer is ready for testing. SPC then requested HDG to complete the testing. All instructions to me or from me were through SPC. We always had a good working relationship with HDG and always enacted any recommendations and instructions regarding the placement of the fill. There is fill that is either too dry or too wet according to the Geotech tests on all cut to fill jobs, and we have always managed these to the Geotech’s satisfaction by reworking the fill as instructed.

(a) He accepted that an experienced earthworks contractor would be able to identify where fill is too dry.27 He said that fill could be placed dry of optimum moisture but still be within specification. The operator looks at how the compactor is operating but that this does not regulate two to three per cent out of specification, for which he said he relied upon HDG testing every 600 millimetre lift.28

(b) Mr Newell’s evidence was that it was impossible for the Partnership to place fill too thick, adopting the industry standard placement and compaction methodology.29 More specifically, he was referring to the fact that when the

27 NOE page 39 at line 30.

28 NOE 57-58.

29 NOE page 93 at line 23 – page 94 at line 1.

scoop is set at the 200–300 millimetres required, the fill cannot come out thicker.

(c) In his evidence Mr Newell rejected that the Partnership could have been responsible for an area of unsuitable fill,30 a subject of the failed fill noted by Mr Holland in his observations (and visible in a photograph that was produced). Mr Newell said:

Based on my significant experience in earthworks, it is not possible that we placed organics/unsuitable material like swamp material in gully 2. It is not credible to suggest a person with my knowledge and earthworks experience of earthworks material would do this.

The size of the area and the shear strength of 30 kPa, a soft area would have been easily noticed.

(a) The Partnership has in fact placed fill that is too dry by such a margin that it would be something an experienced contractor can identify.

(b) A competent contractor, acting with reasonable care, should have noticed the non-compliant fill in Lot 74.

(c) The Partnership has placed fill too thick (described by Mr Holland as one metre thick in places).

(d) The Partnership did place organic or unsuitable fill despite this being extraordinary for an experienced earthworks contractor.

30 Brief of Evidence (BoE) of Wayne Newell , para 33 [201.0013].

  1. Email of Wayne Newell to John Sheppard regarding the Landsdale Gully 2 Fill (16 December 2016), set out above at [45].

Damages for breach of contract

(a) costs to undertake the remedial work of $133,212.93;33

32 Stirling v Poulgrain [1980] 2 NZLR 402 (SC & CA) at 419 per Cooke J.

33 Brief of Evidence of Sam Pemberton, paras 85 to 87 [201.0073].

(b) liquidated damages of $109,899.15 that it was required to pay the Principal for delays said to be caused by having to remediate the Partnership’s defects;34 and

(c) legal costs of $5,803.20.

Remediation costs

Right to remedy defective works

34 BoE of Sam Pemberton, paras 73 to 84 [201.0072].

35 BoE of Anthony Burman, para 21 [201.0059].

  1. See Stephen Furst and Vivian Ramsey Keating on Construction Contracts (11th ed, Sweet & Maxwell, London, 2022) at [11-031].

37 Pearce & High Ltd v Baxter & Baxter [1999] EWCA Civ 789; [1999] BLR 101 (CA).

would have cost had the contractor completed them.38 However, here there is no express term between the parties entitling the Partnership to remedy defects, nor an express term entitling the Partnership to notice giving the opportunity to remedy them. It is common ground that there is an express provision for payment of retentions of 10 per cent but that says nothing about any right to remedy defects arising. Retentions can be held for security to either secure performance, or to pay others to remedy the defects.39

  1. Pearce & High Ltd v Baxter & Baxter, above n 37. Compare Maersk Oil UK Ltd v Dresser-Rand (UK) Ltd [2007] EWHC 752 (TCC) at [649]–[651].

39 Compare the definition of “retention money” in the Construction Contracts Act 2002, s 18A.

40 Smeaton Construction Ltd v Garrett Pasquale Ltd [2012] NZHC 3079.

41 At [31] and [35]–[36].

42 Wu v Body Corporate 366611 [2014] NZSC 137, [2015] 1 NZLR 215 at [134]. This seems to me to be the effect of Owners – Strata Plan 89041 v Galyan Pty Ltd [2019] NSWSC 619 at [20]–[21], referred to me by the Partnership; and see Smeaton Construction Ltd v Garrett Pasquale Ltd, above n 40, at [35].

Mitigation

43 Marlborough District Council v Altimarloch Joint Venture Ltd [2012] NZSC 11, [2012] 2 NZLR 726 at [55] per Elias CJ citing British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Company of London Ltd [1912] UKLawRpAC 43; [1912] AC 673 (HL) at 689.

44 Payzu Ltd v Saunders [1919] 2 KB 581 (CA) as cited in Pipes NZ Ltd v Steel Co Ltd [2014] NZHC 1216 at [102].

45 Pilkington v Wood [1953] 1 Ch 770.

46 White v Rodney District Council (2009) 11 NZCPR (HC) at [30]–[32].

47 Hooker v Stewart [1989] NZCA 407; [1989] 3 NZLR 543 (CA) at 547 affirmed in Frucor Beverages Ltd v Blumberg [2019] NZCA 547, [2020] 2 NZLR 51 at [96].

48 White v Rodney District Council, above n 46, at [30]. See also Pipes NZ Ltd v Steel Co Ltd, above n 44, at [103] citing Andros Springs (Owners) v World Beauty (Owners) [1970] P 144 (CA) at 156.

Stage One and the risk of an adverse finding that it was responsible for the delay resulting.

(a) When an issue with Lot 74 was first identified, HDG told SPC that “we will need a digger to do some pot holing in this area to chase out the soft material”.

(b) The failed fill was originally thought to be limited to Lot 74 but as SPC sought to chase out the fill it became apparent it extended further. The full scope was not something that could have been known in advance. In substance, what started as an exploratory process in a small area expanded as remediation played out into a much bigger issue.

(c) While Mr Newell said he could have chased out fill with the bulldozer by pushing material around, Mr Pemberton said that by the time this work was being undertaken the area surrounding it included finished footpaths and a reserve, installed utilities and services, a road and a finished right of way. It was a situation where care needed to be taken not to damage any completed areas, nor was it appropriate to push material into those areas. I accept that evidence.

(d) The proposition that the work could have been done far more effectively using a bulldozer suggests that SPC, as an experienced contractor faced with the events as they unfolded, was not endeavouring to remediate as cost effectively as possible. Although it was seeking to avoid any liability for the remediation

work and any basis for liquidated damages, it was in SPC’s interests to minimise the costs and time in the event its argument did not prevail.

Liquidated damages

Topsoil and seed within 69-73, removal and replacement of dish channel damaged within both parking bays on Road 1, chip seal and hot mix of parking bays within Road 1, Road Markings and street signs for the stage.

49 Email 24/3/17 [305.0778].

50 Email 24/03/17 [305.0778].

51 Furst and Ramsey, above n 36, at [13-093].

  1. Hadley v Baxendale (1854) 9 Exch 341 at 345; Koufos v C Czarnikow Ltd (The Heron II) [1969] 1 AC 350.

53 Steel Co Ltd v Pipes NZ Ltd [2016] NZCA 175.

There the defendant’s delay in supplying pipes to the plaintiff resulted in the plaintiff failing to meet strict time constraints in its contracts to on-supply the pipes to two third parties. The Court of Appeal upheld the High Court’s conclusion that liquidated damages payable by the plaintiff to the third parties were not too remote on the facts of that case. The Court of Appeal recognised that whether these were recoverable depended on the defendant’s knowledge that the end purpose involved the use of the pipes in the head contract and that the defendant would be liable to the third parties.54

54 At [76]–[77].

  1. Furst and Ramsey, above n 36, at [13-093]. The earlier edition of the same text was cited by the Court of Appeal in Steel Co Ltd v Pipes NZ Ltd, above n 53, at [73].

56 Newell [201.0003] at [7].

57 The test now is whether the consequence is out of all proportion to the legitimate interests of the innocent party in performance of their primary obligations. 127 Hobson Street Ltd v Honey Bees Preschool Ltd [2020] NZSC 53, [2020] 1 NZLR 179 [Honey Bees] at [56].

Legal fees

58 The fact that the test in Honey Bees, above n 57, does not rely on whether the amount payable is a genuine pre-estimate of loss has no bearing on my analysis. The point under consideration here is whether it is appropriate to regard the liquidated damages as in substance equivalent to damages/reasonable as payable for the usual consequences of delay on the present facts.

59 BoE of Anthony Burman, para 17. The invoices and time records of CMC are at [307.1439], [307.1440], [307.1441], [307.1442] and [307.1443].

Tort claim

Conclusion on the Landsdale Claim

60 Wellesley Partners LLP v Withers LLP [2014] EWHC 556 (Ch) at [68.].

61. BoE of Mr Pemberton at 85 to 87 [201.0073].

62 BoE of Mr Burman at 21 [201.0059].

Interest

RANGITAHI CLAIM

$4,253.21 so the net amount in dispute is $25,543.06. The issues in relation to Rangitahi are modest relative to a contract value to the Partnership of over $1.2 million.65

  1. See, for example Blumberg v Frucor Beverages Ltd [2018] NZHC 1876, [2018] 3 NZLR 672 at [76].
  2. Interest on Money Claims Act 2016, s 9(1)(a)(i). CKL’s notice on 25 November advised that if the earthworks were not completed in 5 days (so by 30 November), the reasonable costs of the

works undertaken by others shall be recoverable by the contractor, and it was therefore from that date that costs began to accrue: 304.0666.

65 BoE of Anthony Burman, para 16.

Item (a) – Deduction of $21,625.52

66 BoE of Nathan Sweetman, para 7.1.

67 NoE, page 165, lines 19 to 25.

  1. Calculated by adding the 3,018.7m3 (measured in the cut); 2,542.7m3 (measured in the fill); 3,127.6m3 (measured in the cut).
that in this instance the load counts in Mr Newell’s notebook are an accurate measure. It says that if SPC completed any work after Mr Newell left the site, it was in addition to the cut to fill volumes placed by the Partnership.

Item (b) – Deduction of $3,910

69 BoE of Nathan Sweetman, para 9.

70 NoE, page 188, lines 1 to 3.

71 BoE of Nathan Sweetman, para 9.

72 [201.0001], para 59(e).

This was a comparable rate because it reflected the same scope of work to be carried out. We did not consider it fair to use the rate that we would have charged to Rangitahi because this included a margin, so we used Wayne’s own rates for this rework.

Item (c) – Deduction of $4,260.75

73 BoE of Mr Pemberton, para 116.

Partnership had charged $5.00 per m3, not his usual rate of $5.30 per m3. In an email of 3 October 2018, he explained: “Trimming of topsoil. Extra thick in some areas in my a/c you will see I charged some at stockpile rate this covers extra work”. By this Mr Newell meant he charged less than his usual rate for spreading topsoil (which is

$5.30 per m3) and instead charged $5.00 per m3, his stockpiling rate, to leave

30 cents per m3 for someone to remove the additional thickness to stockpile or some other use.

$5.30 per m3 but SPC then deducted the actual costs it incurred to trim the topsoil so that it was to the right thickness.

Conclusion

OVERALL CONCLUSION

Anderson J


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/2676.html