You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2023 >>
[2023] NZHC 3034
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Body Corporate 406198 v Argon Construction Limited [2023] NZHC 3034 (30 October 2023)
Last Updated: 16 November 2023
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
|
CIV-2017-404-001772 [2023] NZHC 3034
|
IN THE MATTER OF
|
The Bianco Apartments
|
BETWEEN
|
BODY CORPORATE 406198
Plaintiff
|
AND
|
ARGON CONSTRUCTION LIMITED
First Defendant
AUCKLAND COUNCIL
Second Defendant
|
Hearing:
|
1-5, 8, 10-11, 15-19, 22-26, 29-31 May and 1, 6-7, 19-20 and
22 June 2023
|
Appearances:
|
D R Bigio KC, R D Butler, S C I Jeffs, I J Stephenson, R J H Scott, H Chung
and J C Wedlake for Plaintiffs
W A McCartney and D A Cowan for First Defendant
S C Price, M J Ferrier, C M Fairnie and S H Ji for Second Defendant
|
Judgment:
|
30 October 2023
|
JUDGMENT OF ANDREW J
This judgment was delivered by Justice
Andrew on 30 October 2023 at 3.00 pm
pursuant to r 11.5 of the High Court Rules 2016 Registrar /
Deputy Registrar
Date ..................................
BODY CORPORATE 406198 v ARGON CONSTRUCTION LTD & OR [2023] NZHC 3034 [30
October 2023]
TABLE OF CONTENTS
Introduction [1]
The parties [6]
Factual background [10]
Building consents [14]
Construction [17]
Auckland Council inspections [37]
Discovery of the defects by the plaintiffs
[39]
Agreed defects [40]
The history of the claims and pleadings
[41]
The pleadings [46]
The issues [47]
Defects and liability framework [50]
Scope and quantum [51]
Expert evidence [54]
The defects at issue [55]
Defect 1 – Cantilevered balconies
[57]
Defect 2 – Podium
[72]
The damage caused by the defects
Is the damage in respect of defect 1 of
such a nature that the requirements of the Building Code are not met – is it actionable damage?
[76]
Is the damage in respect of defect 2
actionable damage? [93]
Liability of Argon
Did Argon owe a non-delegable duty of
care? [102]
Argon’s responsibilities
[115]
Conclusion – Argon’s
liability [120]
Liability of the Auckland
Council
Standard of care [123]
Defect 1 [129]
Causation [163]
Defect 2 [166]
Conclusion on liability [169]
Reasonable remedial scope
Legal principles [170]
The plaintiffs’ proposed scope of
remedial works [180]
Interpretation of ss 17 and 112 of the
Building Act 2004 [186]
Is the plaintiffs’ scope
reasonable? [203]
Evidence of the façade engineers
– cladding [213]
Mr Earley’s evidence –
Auckland Council [237]
Mr Alexander’s scope of repair
[241]
The acoustic matting [254]
What will it cost to repair the
defects?
The parties’ positions
[261]
Preferred approach [272]
Betterment [281]
Consultants’ costs [283]
Consequential losses [287]
General damages [288]
Standing [296]
Contributory negligence [322]
GST [334]
Affirmative limitation defences
[337]
Apportionment between defendants
[340]
Other issues
The non-legally
represented plaintiffs [343]
Former
owners/assignees [345]
Result
[351]
Introduction
- [1] This
is defective building litigation. It involves the 157-unit residential unit
title development (comprised of two towers) known
as the Bianco Off Queen
Apartments (Bianco Off Queen).1
- [2] The Body
Corporate and individual unit owners sue in negligence. The defendants are the
building contractor, Argon Construction
Ltd (Argon), and the Auckland Council
(i.e. the territorial authority).
- [3] The
remaining defects at issue are weathertight-related.2 The plaintiffs
say the building was built with cantilevered balconies that have defective
waterproofing (defect 1). They also say
that the waterproofing on the ground
level (including the podium common areas) suffers from similar problems (defect
2). The overwhelming
majority of the damages sought relate to the cost of
remedying defect 1.
- [4] The
plaintiffs seek total damages of $40,739,870.3 Their remedial scope
(i.e. what is reasonably required to remedy the defects) involves
wholesale/building-wide repairs including replacement
of all cladding, joinery
and balcony balustrades.
- [5] The
defendants deny liability. In particular, the Auckland Council contests
virtually every element of the plaintiffs’ claims,
including the nature
and extent of the defects. A central issue is the reasonable scope of repairs
and the costs to carry out those
repairs. There is also an issue of standing;
the ability of the Body Corporate to sue for the costs of repairs. On the
critical issues,
the respective positions are very far apart.
The parties
- [6] The
first plaintiff is Body Corporate 406198. There are 93 second plaintiffs who
constitute the current or former proprietors
of 132 of the 157 legal units. I
note
1 The original name of the building was Turner Waverly.
- A
number of claims against other defendants and third parties were settled on the
eve of or during the early part of the trial. This
removed the fire and hot
water defects from the scope of the remaining claims as well as a significant
number of parties.
3 Plaintiffs’ closing
submissions – claim summary, dated 22 June 2023.
that there are 178 units in total if dual key units are counted as two units,
where the second plaintiffs represented by Lane Neave
in these proceedings own
147 of the 178 total units.4 Some of the second plaintiffs own more
than one unit.
- [7] Two of the
second plaintiffs are self-represented. They are Yinling Linda Wu and Haixin
Wang. These two plaintiffs seek a discrete
award of damages in favour of them
individually, although their claims are based wholly on the expert evidence in
the case generally
advanced by the Body Corporate.
- [8] Some of the
units are rented out via the Residential Tenancies Act 1986 and some are used
for temporary accommodation as part
of a serviced accommodation business (Hotel
Pool) that operates in the towers. The 147-total units owned by the second
plaintiffs
are comprised of the following:
(a) 67 units are rented out to tenants;
(b) 30 units are part of the Hotel Pool;
(c) 38 units are owned by Kāinga Ora; and
(d) 12 units are owner-occupied.
- [9] A number of
the second plaintiffs purchased their respective units in either 2016 or 2017.
Most of these owners received pre-contract
disclosure statements which referred
to Body Corporate AGM minutes. Most of these owners also had solicitors acting
for and advising
them on their respective purchases.
Factual background
- [10] Bianco
Off Queen is located in central Auckland, between Symonds Street and Queen
Street. Tower A consists of 14 storeys and
3 basement levels. Tower B
consists
- As
stated, Bianco Off Queen comprises 178 units in total if dual key units are
counted as two units. There are 21 dual key units,
so if counted as one legal
unit, there are 157 legal units. Of the 178 total units, there are 21 studio
units, 41 one-bedroom units,
115 two-bedroom units and one three- bedroom unit.
147 of these units are owned by second plaintiffs, of which 31 are one-bedroom
units, 96 are two-bedroom units, one is a three-bedroom unit and 19 are studio
units.
of 13 storeys, including one mezzanine level, and two basement levels. The
basement levels include car parks.
- [11] The
above-ground units are individual apartments which, as stated, are a mix of
rentals, short-term accommodation and owner-occupied
units. The only exception
is a unit on level 1 which is used as the hotel reception and hotel
offices.
- [12] A central
podium and pedestrian walkway separate the two towers. These areas are covered
with ceramic floor tiles over liquid-applied
waterproof membrane.
- [13] Each tower
is served by a staircase and two lifts which extend to all levels, including
basement levels. Above ground, the staircases
are situated on external walls and
are partially exposed to weather.
Building consents
- [14] On 1 March
2007, Argon and the original developer, Bianco Limited, entered into a contract
for the construction of Bianco Off
Queen. The critical consents for the purposes
of these proceedings are as follows:
(a) BLD 20041713901 – which concerned the super-structure and building
services (this was referred to by the parties and their
witnesses as the
“901” consent.);
(b) BLD 20041713904 – which concerned a change of cladding.
- [15] Argon
completed construction around January 2009. The Auckland Council issued the
relevant Code Compliant Certificates on 30
January 2009.
- [16] The
apartments were designed to be affordable and relatively low-cost. They were
described by Mr Stephen Alexander, expert building
surveyor witness for Argon,
as “a low initial cost/high life cycle cost
building”.
Construction
- [17] The
building structure is reinforced concrete with steel frame infill sections to
the external walls.
- [18] The steel
framing of the main structural exterior wall is designed to resist wind loads,
hold the interior lining (plasterboard),
contain the insulation, and hold the
rigid air barrier (RAB). The purpose of the RAB is to prevent uncontrolled air
infiltration
through the wall and also to deflect any water that gets past the
outer portion of the wall.
- [19] The
majority of the external walls are clad with a rainscreen cladding system,
comprising of prefabricated “Moduclad”
cladding modules. This system
is denoted as a James Hardie ExoTec façade panel rainscreen and RAB (with
James Hardie’s
rigid air barrier product being called RAB™
Board).
- [20] The
rainscreen portion (i.e. the outer portion of the wall) consists of narrow steel
battens fixed over the outside of the RAB.
The exterior cladding of the building
is then fixed to these rainscreen battens. The purpose of the rainscreen is to
resist water
entry into the inner portion of the wall. Water that enters behind
the exterior cladding should drain out the bottom of the rainscreen
without
causing damage to the other parts of the wall.
- [21] Attached
and marked ‘Appendix A’ is a copy of the structural drawings of the
cladding system contained in the consent
drawings by the manufacturer Jacobson
Façade Systems Ltd.
- [22] Each of the
157 units have at least one balcony. The balconies to the apartments above
ground-level are cantilevered. The balconies
are covered with ceramic tiles,
installed over liquid-applied waterproofing membranes and acoustic matting, with
metal-framed railings
providing fall protection.
- [23] The
structure and waterproofing of the balconies were designed by ADC Architects and
Buller George Engineers Ltd. The initial
drawings for the balconies specified
that the concrete was to be poured off-site, with screed to be applied
on-site
to provide the balconies with a slope towards the building. This included
forming a drain into the pre-cast concrete slab prior to
installation. However,
Argon proposed, and the architects approved, an alternative construction
methodology. That alternative provided
for the entirety of the structure to be
completed off-site using pre-cast concrete and installed on-site by Argon. No
screed was
applied in the construction of the balconies.
- [24] Concretec
New Zealand Ltd supplied the pre-cast balconies which Argon subsequently
installed. TAL Ltd (TAL), the tiling sub-contractor,
waterproofed and tiled the
balconies. Argon placed grates (or grills) over the balcony drains. The Auckland
Council carried out some
inspections of the waterproofing of the balconies
throughout the construction.
- [25] A diagram
showing the design elements of the cantilevered balconies, as they were built,
is set out below.
- [26] The
balconies are constructed with one or more pre-cast concrete slabs. As
constructed, the pre-cast slabs extend into the building
by approximately 250
mm. The steel holding the balcony to the building is contained in the bottom of
the slab (the slab itself is
a 200 mm slab). The steel, that does all the work
of holding the balcony to the building, is about 50 mm from the bottom. On the
slab, there is a raised perimeter nib, also made of concrete. The nib is located
on the exterior face of the balconies.
- [27] The
apartments situated on the corners of the towers have larger balconies. For
these balconies, there is more than one pre-cast
concrete slab, meaning that
multiple slabs butt together to form joins or joints. Those joints are more
vulnerable to ingress from
moisture. This is one of the areas where there has
been water ingress through the balconies.
- [28] The
waterproofing membrane was to be reinforced with mesh. A cementitious adhesive
was to be applied on top of the waterproof
membrane, to which the tiles were to
be affixed.
- [29] Once
constructed, the balconies had a fall of 20 mm, with the higher part of the fall
being located adjacent to the perimeter
nib. Water, once it lands on the tiles
of the balconies, runs towards the apartments, where it was designed to be
diverted away from
the apartments by a channel drain with a downpipe.
- [30] A diagram
demonstrating the “bottom of wall detail” and where the wall
intercepts with the balcony drain on the interior
face of the balcony is
attached as ‘Appendix B’.
- [31] The
consented drawings showed “Mapelastic Waterproofing on [Mapefonic]
Acoustic System”, a BRANZ-approved proprietary
system including a
waterproof membrane and an acoustic mat. However, as built on most balconies,
the acoustic matting was made of
cork. In some instances, a rubber matting was
used instead of Mapefonic. Cork is absorbent and biodegradable.
- [32] The
specified Mapelastic membrane is a cementitious (two-part) liquid-applied
membrane system produced by Mapei New Zealand Ltd.
The consented drawings show
that the membrane was to terminate around the perimeter by “sawcut to seal
waterproofing membrane”.5
- [33] Changes to
the original design, including the dispensing of the sawcut were agreed between
Argon, Mapei and the architect. As
part of the change process Mapei,
- In
his evidence, Mr Gabriel, general manager for Argon (and site engineer during
the construction of Bianco Off Queen), described
this as follows “[t]he
original design provided that the liquid applied membrane would terminate into
the balcony chase, which
is a slot cut into the balcony for this purpose”
(i.e. a sawcut). He says that following discussions with Mapei it was decided
that the liquid-applied membrane could be terminated at the up-stand without the
need for a chase.
in an email to Mr Gabriel of Argon on 27 June 2007, stated “[a]s long as
the membrane is allowed to turn up onto the up-stand,
the sawcut is not a
necessary.” That email also stated:
Mapei’s Mapefonic System has been specified by the architects as the
under- tile acoustic product. We would very much like this
specification to
stand. However, if acoustic cork is utilised, we can offer a system of
adhesives, waterproof membranes, grouts and
sealants that will be covered by a
Mapei Product Performance Warranty.
- [34] The
products that would be covered by that warranty are then listed in the email and
included alkali resistant fibreglass mesh
“for reinforcing waterproof
membrane over acoustic cork”.
- [35] As built,
none of the balconies investigated by the plaintiffs’ experts had membrane
to the inside face of the nib. The
membrane terminated on the horizontal surface
of the balcony before the nib as shown in the drawing above at [25]. The
plaintiffs
say that the as-built detail was a high-risk detail.
- [36] TAL issued
two producer statements for the tiling and waterproofing. One was dated 21
November 2008 and covered tower A and the
podium, and the other one was dated 12
December 2008. Mapei was a supplier to TAL. Argon did not have a direct contract
with Mapei.
Mapei issued a product performance warranty for their Mapelastic
product on 29 October 2008.
Auckland Council inspections
- [37] Between 6
and 8 November 2008, Mr Pulu from the Auckland Council inspected some of the
balconies, including all of the balconies
on levels 4, 5, 6, 7 and 8 in tower A.
The waterproof membrane was given a pass and the overflow and discharge drain
was regarded
as “not applicable”. At the time of these inspections,
the “grill over [the] deck area[s]” had not been put
in
place.
- [38] There was
only one inspection of the podium area by the Auckland Council. That occurred on
12 November 2008 and resulted in a
“pass”. It appears that the
inspector only inspected “2/3 of the north-west side of the podium
area”.
Discovery of the defects by
the plaintiffs
- [39] The
possibility of defects 1 and 2 were first communicated to the unit owners at the
15 February 2017 AGM. A preliminary report
from Maynard Marks, building
surveyors and remediation specialists, was received by the Body Corporate in May
2017 which advised
that there were enough concerns about aspects of the
construction of the building, including balcony and podium waterproofing, that
further investigation was necessary. The findings of this report and the
prospect of litigation was communicated to the unit owners
at an Extraordinary
General Meeting on 21 June 2017.
Agreed defects
- [40] At the
experts’ conferral for waterproofing, convened under r 9.44 of the High
Court Rules 2016, the experts commenting
on the defects to the cantilevered
balconies agreed that:
(a) there are failures to the membrane which have allowed water underneath the
waterproofing membrane;
(b) water ingress is causing damage to the cork acoustic layer;
(c) in respect of damage to the cork acoustic layer, clauses E2.3.2 and B2 of
the Building Code have been breached; and
(d) water has also entered the exterior walls causing damage in some locations,
resulting in further breaches of E2.3.2 and B2 of
the Building Code.
The history of the claims and pleadings
- [41] Maynard
Marks Ltd began its investigations in 2016. It raised a lengthy list of matters
they considered to be defects or issues
with the building. The original
statement of claim filed in July 2017 asserted 99 specific defects.
- [42] The Maynard
Marks building assessment report of November 2018 again raised numerous issues
with the building. The report and
enclosures comprise 997 pages and included a
long list of scope items. An initial, preliminary scope of remedial works was
also prepared
by Maynard Marks in 2018. An eighth version of that scope,
referred to as MMSOW8 was prepared and dated 20 September 2021. This is
described by the plaintiffs as a “foundation document” and is an
essential component of their claims.
- [43] Many of the
alleged defects fell away with the plaintiffs’ sixth amended statement of
claim of 1 July 2019. The ninth,
and current, amended statement of claim dated
21 June 2022 contains four defects. As noted above, two of those have settled,
leaving
only defects 1 and 2 for me to determine. It is notable that despite the
significant reduction in the number of defects pleaded,
the plaintiffs’
alleged scope of remedial works has changed very little. Mr Price, on behalf of
the Auckland Council, described
this as a curiosity and submitted that this case
“has all the hallmarks of the plaintiffs and/or Maynard Marks getting in
too
deep and being unable to find a way out”. A theme of the Auckland
Council’s case is that what has happened here is that
the plaintiffs have
identified a large number of issues of concern and have been advised as to a
scope of works to address those
concerns, which have now been
“shoe-horned” into what has become defects 1 and 2.
- [44] The ninth
amended statement of claim seeks judgment against the first and second
defendants in the sum of $60,024,824.60 (including
GST), together with general
damages of $1,575,000 and consequential losses of $5,545,000. The damages sought
has since been revised.
The sum now claimed is $40,739,870.
- [45] At the time
the plaintiffs served their evidence in relation to scope and quantum, namely in
February 2022, the damages claimed
were based on an estimated 79–90 weeks
duration for the remedial works. Since then, and in part because of the
settlement of
the fire and hot water claims, the quantum sought by the
plaintiffs has reduced considerably. The plaintiffs’ expert programmer,
Mr
Gould, has also substantially revised his estimated duration of the remedial
works to between 36 and 43 weeks. However, it remains
the case that the vast
majority of the plaintiffs’ quantum now sought relates to assertions that
they are entitled to a full
re-clad, new
joinery, new balustrades, a better tile system, better drainage and a raft of
other upgrades or repairs (that have nothing to do
with the membrane issues).
The defendants say that even if the pleaded defects are made out, the
plaintiffs’ scope is unreasonable
and disproportionate; it is not
recoverable damage.
The pleadings
- [46] In
the ninth amended statement of claim of June 2022, the plaintiffs claim that the
defendants breached their duties of care
in that Bianco Off Queen contains
defects 1 and 2, as set out below:
(a) Defect 1 – cantilevered concrete balconies: failure to install or to
ensure the balcony membrane was installed in accordance
with the design and/or
good trade practice, including failure to supervise contractors, failure to
provide design details necessary
to install proprietary waterproofing, and
failure to inspect or call inspections of waterproofing.
(b) Defect 2 – Podium: failure to install or ensure the podium, truck
dock, access ramps, and enclosed balconies had a waterproof
membrane installed
in accordance with the design and/or good trade practice, including failure to
supervise contractors, failure
to provide design details necessary to install
proprietary waterproofing, and failure to inspect or call inspections of
waterproofing.
The issues
- [47] As
noted, the defendants (particularly the Auckland Council) challenge and put the
plaintiffs to proof on virtually every element
of its claim. There are thus
multiple issues. They include each of the elements of the tort of negligence
which the plaintiffs carry
the burden of proving. This includes: the nature and
scope of the duties of care owed (and in Argon’s case, whether it owed
non-delegable duties), breaches of the standard of care, damage, causation, the
scope of repairs, calculation of quantum, consequential
damages and contributory
negligence. A further issue is the standing of
the Body Corporate to sue for recovery of the remedial costs and the
consequences of my finding on that issue for any proven contributory
negligence.
- [48] The
physical realities of the building are not seriously disputed in the sense that
there is no challenge to what the plaintiffs’
building surveying experts
(i.e. Maynard Marks) saw and photographed during the investigation of the
building. However, the plaintiffs
have presented a case based on the existence
of systemic defects calling for wholesale/building-wide repairs. The defendants
say
that their evidence falls well short of establishing such systemic defects.
The defendants say that Maynard Marks identified a small
number of balconies
which leak and then investigated the cause of those leaks; they did not
investigate the workmanship on non-leaking
balconies. The defendants say that
the problems with such an approach are obvious.
- [49] I will deal
with each of the many issues in accordance with the following road
maps.
Defects and liability framework
- [50] I
adopt the following approach in respect of each alleged defect (i.e. in relation
to defect 1 and 2) to determine liability:
(a) What is the alleged defect and does it exist?
(b) Is there a “defect” – does it breach the Building Code and
what is the extent of damage?
(c) Did Argon owe non-delegable duties of care in respect of the defect?
(d) Should it have been identified by the Auckland Council?
(e) Would it have been prevented by the Auckland Council?
Scope and quantum
- [51] I will
approach the scope and quantum issues (if liability is established) in
accordance with the following road map:
(a) What is reasonably required to remedy the alleged defect and any damage it
has caused?
(b) What are the costs of the reasonable remedial scope?
- [52] This
assessment includes addressing the issue of whether the reasonable cost of
carrying out the remedial works is to adopt the
least expensive method. It also
involves an interpretation of ss 17 and 112 of the Building Act 2004.
- [53] At the
conclusion of the judgment, I address a number of subsidiary issues, including
the standing of the Body Corporate to sue,
GST, general damages and contributory
negligence.
Expert evidence
- [54] Expert
evidence was given by a range of experts, including the following:
(a) Building surveyors – Mr Richard Angell (plaintiffs), Mr Darryl August
(plaintiffs) and Mr Stephen Alexander (Argon).
Mr Angell and Mr Alexander
participated in an expert conferral on waterproofing under r 9.44 of the High
Court Rules and signed
a Scott Schedule which was filed with the Court.6
Mr Matthew Earley for the Auckland Council also participated in the
conferral but was not called as a witness.
- “Scott
Schedules” are frequently used in the Technology and Construction Court
(TCC) in the UK. Their aim is to identify
the main issues in dispute between the
parties; they set out the defects alleged and the defendant’s responses,
as well as
joint comments setting out points of agreement and disagreement. See
Napier City Council v Local Government Mutual Funds Trustee Ltd [2021]
NZHC 1477 at [143], n 79; see also Emden’s Construction Law by Crown
Office Chambers (online ed, LexisNexis) at [26.75]; and Jones v Onyut
[2012] EWCA Civ 1816.
(b) Façade engineers – Mr Andrew Hakin (plaintiffs), Mr Matthew
Paget (Argon) and Dr Gerrard Winter (Auckland Council).
These witnesses also
participated in an expert conferral under r 9.44 and filed a Scott Schedule.
(c) Quantity surveyors – Ms Heidi van Eeden (plaintiffs), Mr Clinton Brock
(Argon) and Mr James White (Auckland Council). There
was no expert conferral of
the quantity surveyors.
(d) Engineering programmers – Mr Christopher Gould (plaintiffs) and Mr
David Andrews (Argon). The Auckland Council had no
expert programmer witness.
There was no joint expert conferral. These witnesses address the estimated
duration of the remedial works.
(e) Council practice – Mr Simon Paykel (plaintiffs) and Mr Anthony Hutt
(Auckland Council).
(f) Property law/conveyancing expert – Mr Peter Nolan (Auckland
Council).
(g) Consequential losses (including loss of rental and alternative accommodation
costs) – Mr Bernard Wright (plaintiffs)
and Mr Venkatakrishnan
Dheenadayalan (Housing New Zealand Ltd).
The defects at issue
- [55] The
term “defect” is not defined in either the Building Act 2004 or the
Building Code. Its meaning was discussed by Downs J in Minister of Education
v H Construction North Island
Ltd:7
... I use the term in
an untechnical way, and as meaning only some error, shortcoming or imperfection
in relation to an aspect of
construction.
- [56] I adopt his
Honour’s definition as a reasonable working definition. I accept the
Auckland Council’s submission that
such definition must be assessed
through a
7 Minister of Education v H Construction North Island Ltd
[2018] NZHC 871 at [63].
2007–2009 lens (i.e. when the buildings were constructed). I begin by
identifying the existence of each defect in accordance
with the framework set
out at [50] above.
Defect 1 – Cantilevered balconies
- [57] In relation
to defect 1 (the balconies) the plaintiffs’ plead:
(a) a failure to construct membrane up-stands to the perimeter nib of the
balconies;
(b) a failure to ensure that reinforcing mesh was encapsulated within the
membrane;
(c) a failure to ensure the membrane was adequately lapped into and over the
drainage outlets;
(d) a lack of Mapeband; and
(e) a failure to ensure the membrane was applied with sufficient thickness.
- [58] The essence
of the plaintiffs’ claim (in relation to both defects 1 and 2) is that
there has been the failure of an integrated
system designed to keep the building
weathertight. That failure is pleaded primarily as a failure in respect of the
installation
and performance of the membrane.
- [59] The factual
premise (i.e. the situational facts) of defect 1 is not really at issue. These
agreed situational facts include:
(a) the membranes were not dressed into sawcuts and in many cases there was cork
matting under the membrane rather than Mapefonic;
(b) the cork has become wet and/or decayed in the locations identified by the
plaintiffs;
(c) the consented plans (as a matter of fact) required a chase/sawcut to the
inside face of the balcony nib, but as built, there
were no sawcuts;
(d) there was no membrane up-stand on the perimeter nib;
(e) on some balconies the membrane was poorly dressed into the outlet and in
some cases not pressed into the outlet at all; and
(f) the thickness of the membrane was highly variable and on many balconies the
mesh was not encapsulated within the membrane.
- [60] However,
the defendants do not accept that each of these factual state of affairs
constitute an actionable defect; the extent
of damage (if any) and whether there
has been a breach of the performance and functional requirements of the Building
Code are at
issue.
- [61] In
addressing the critical issue of whether the matters pleaded are actionable
defects for which the defendants might be liable,
the Scott Schedule for the
waterproofing defects (covering both defects 1 and 2) is obviously a helpful
starting point.8 The participating experts, which included Mr Earley,
expert witness for the Auckland Council, agreed that there had been breaches
of
the Building Code including B2 (durability) and E2 (external moisture). However,
in the relation to the truly disputed issues
of the extent of damage and
reasonable scope of remediation, there are substantial differences between the
experts that I need to
address.
- [62] I generally
agree with the submission of the plaintiffs that in addressing their contention
that there has been a failure of
an integrated system designed to keep the
building weathertight, it is important not to focus unduly on individual
specific defects
in isolation. It is often not possible to determine with 100
per cent precision what contribution they individually have made to
the problem
of moisture ingress, particularly where the obvious remedial solution is to
remove and replace the whole membrane or
some equivalent. I also acknowledge
that a plaintiff does not have to “wait for physical damage to
occur” before it is
regarded as having suffered loss or
8 See [40] above.
harm.9 The plaintiffs do not need to show
the existence of leaks on every balcony leading to visibly manifested damage
within every apartment.
However, the plaintiffs do carry the burden of proving
actionable damage, namely damage that is more than de minimis. They must also
prove that their proposed scope of repairs is a reasonable and proportionate one
having regard to the nature and extent of the defects
and the damage or likely
damage suffered.
- [63] The
practical application of the burden of proof is also important. As discussed by
the Supreme Court in Z v Dental Complaints Assessment Committee, there is
a single civil standard, the balance of probabilities, however the cogency of
evidence required may depend upon the seriousness
of the matters to be proved
and the consequences of proving them.10
This principle is of importance here. The plaintiffs’ allegations
are serious in the sense that if they establish the existence
of the alleged
defects and breaches of the Building Code, as well as their alleged remedial
scope, then they say that the defendants
are liable for tens of millions of
dollars in damages. Those are of course serious matters and consequences, and
the Court is entitled
to expect the plaintiffs to adduce cogent evidence with
sufficient probative force to prove them.
- [64] Mr
Alexander, Argon’s expert building surveyor, was a model witness. His
evidence was substantially helpful, presented
in a coherent and well-structured
manner, and his criticisms of the plaintiffs’ experts was restrained and
measured. I agree
with his criticism. I accept Mr McCartney’s submission
that Mr Alexander’s evidence was unassailable. I acknowledge the
significant constraints that the plaintiffs’ expert building surveyors
were operating under, but by comparison their evidence
falls short of the
quality and standard adopted by Mr Alexander. I agree with and accept the
problems he identifies, and his analysis
of them, as well as his remedial
scope.
- [65] The
plaintiffs’ criticisms of Mr Alexander are misplaced. Mr Alexander is well
qualified to speak about concrete balconies
over non-habitable spaces and to
place
- Body
Corporate 207624 v North Shore City Council [2012] NZSC 83, [2013] 2 NZLR
297 [Spencer on Byron] at [45].
10 Z v Dental
Complaints Assessment Committee [2008] NZSC 55, [2009] 1 NZLR 1 at
[112].
some emphasis on that fact in diagnosing the problems and proposing a solution.
He has substantial and relevant experience in the
New Zealand building industry.
His company, Alexander & Co Ltd, has been investigating building failure and
assisting with dispute
resolutions since the beginning of 2000.
- [66] I agree and
accept Mr Alexander’s analysis that there were two problems that arose
with the balconies:
(a) Some of the downpipe connections leak where the downpipe connected to the
channel drain in the balconies. Due to the downpipe
being located very close to
the exterior wall, this allowed some water to enter the wall.
(b) Many of the balcony joints allowed water to pass through due to voids in the
concrete that had not flowed well into the joints.
As the joint extended over
the top of the exterior wall, some water damage has occurred in that local area,
but this only happens
on balconies that have joints.
- [67] The
plaintiffs’ expert witnesses focus on the failure of the membrane as the
main mechanism of failure. However, I agree
with Mr Alexander that that is not
entirely correct. As Mr Alexander stated, pre-cast concrete balconies on the
outside of a building
should not need any waterproofing membrane at all (except
where that is required to protect an acoustic mat from water). The real
problem
is the fault under the membrane.
- [68] In
addressing (below) the critical issues of extent of damage and what might be a
reasonable scope of repair, it is important
to focus on these two specific
pathways for water to get into the apartments (i.e. moisture ingress around the
outlet pipes and the
concrete joint between two sections of balconies). I note
that Mr Angell in cross- examination accepted that these are the only two
avenues for water to get in behind the cladding.
- [69] Mr
Alexander’s evidence, which I accept and adopt, does however provide
substantial support for the plaintiffs’ contention
that the matters
pleaded are actionable defects and sufficiently widespread to be described as
systemic. This includes a failure
to use a Mapeband tape. Mr Alexander notes
that the application of the membrane was not uniform across all 179 balconies
but that
the application was “typically” of poor quality. As with Mr
Angell, he did not observe any Mapeband tape on any of the
balconies that he
investigated. I find that it is reasonable to infer from the technical
literature that the use of Mapeband tape
is an integral part of the
waterproofing product.
- [70] The
Auckland Council responsibly accepts that the following matters are
“patently defects”: missing membranes over
some outlet flanges, a
lack of thickness with the membrane,11 and the reinforcing mesh not
being encapsulated within the membrane in accordance with the requirements of
the technical literature.
What of course is in dispute is whether these matters
are ultimately of any consequence – are they systemic and what is the
extent of any damage that has resulted? I discuss this below in the second stage
of my analysis.
- [71] I also find
that, as pleaded, the failure to construct membrane up-stands to the perimeter
nib of the balconies (or to construct
an equivalent sawcut/chase) was a defect.
As Mr Angell noted, for a waterproofing system to be effective it must be
terminated in
a way that prevents moisture from entering behind and under the
membrane system. That is widely acknowledged in the contemporaneous
literature,
including the Mapei Mapelastic technical literature and the BRANZ Appraisal
Certificate No 485 (2005).12 I note also that Mapei, in its email to
Mr Gabriel of Argon of 27 June 2007, expressly stated “[a]s long as the
membrane is
allowed to turn up onto the up-stand, the sawcut is not a
necessary”. There may have been a meeting subsequent to that fact
and a
design change, however that does not affect my finding that this was a
defect.
11 The Mapei Mapelastic technical literature and the BRANZ
appraisal require the membrane to be a minimum of 2 mm thick. The undisputed
evidence of Mr Keesing concluded that the thickness was highly variable, and
only 2 out of the 28 membrane samples had a minimum
thickness exceeding 2 mm
across the entire membrane.
12 The Mapei Mapelastic technical literature notes that
“special care” must be taken when waterproofing check joints and
fillet joints between horizontal and vertical surfaces. In those locations
either Mapeband or other specified products must be used.
Defect 2 – Podium
- [72] It is
agreed defect 2 was and is a much less significant issue than defect 1. The
parties also agree that logically my findings
in relation to defect 1 will be
applicable to the conclusions that I reach in relation to defect 2.
- [73] Defect 2
relates to defective waterproofing on the ground level, including ground floor
balconies, the exterior podium, the adjoining
walkways and stairs, vehicle
access ramps, and the truck dock. The plaintiffs plead that there is moisture
ingress beneath the waterproof
membrane applied to these areas.
- [74] There are
two areas of alleged damage in relation to defect 2:
(a) At the podium or ground level, which is exposed, there are common walkways,
a truck dock and a series of enclosed balconies.
These balconies are distinct
from those captured in defect 1 as they are at ground/street level and are
“enclosed”. They
are not cantilevered as with defect 1.
(b) Below the podium level are two basement levels, “B2” and
“B3”, which are carparks. It is said that water
has travelled
beneath the podium levels (balconies, stairways and walkways) and into the
basement levels.
- [75] I accept
that the plaintiffs have established the existence of defect 2. As with defect
1, however, the key issue in dispute
is the extent of this defect and whether it
is actionable damage. I, once again, will address this in the second step of my
analysis.
The damage caused by the defects
Is
the damage in respect of defect 1 of such a nature that the requirements of the
Building Code are not met – is it actionable
damage?
- [76] As Gwyn J
held in Bates v Auckland
Council:13
- Bates
v Auckland Council [2021] NZHC 2558 at [177]; citing Body Corporate
188529 v North Shore City Council [2008] NZHC 2300; [2008] 3 NZLR 479 (HC).
[177]
The plaintiff has the legal burden of proof as to alleged damage and also, as a
matter of fact, has the power to investigate
and prove damage. In Sunset
Terraces [High Court decision] Heath J said:
... evidence must be weighed according to the proof which it was within the
power of one side to have produced and in the power of
the other to have
contradicted.
- [77] I also
adopt the following principles set out by Downs J in Minister of Education v
H Construction North Island Ltd:14
(a) Clause E2.3.2 provides that roofs and exterior walls must prevent the
penetration of water that “could” cause damage
to building elements.
Anticipation and prohibition of potential damage makes clear actual damage is
not required for a breach of
the Code.
(b) As Tipping J held in Spencer on Byron:15
... A duty of care should be recognised in respect of pre-emptive expenditure
as well as expenditure necessary to reinstate or repair
physical damage which
has actually occurred.
(c) The Code does not contemplate “reasonable” damage in consequence
of water ingress. Rather, it seeks to prevent damage.
(d) The Building Code is clearly concerned with undue dampness and potential
undue dampness. Consequently, not every instance of
water ingress will breach
the Code. Some water may be able to harmlessly escape. Or evaporate. However,
the Code does not envisage
dampness arising from leakage. Rather, and as with
damage, it seeks to prevent just that.
(e) The relevant objective of the Building Code is to “safeguard people
from illness or injury that could result from external
moisture entering the
building”.16 As Tipping J held in Spencer on Byron, the
“primary statutory purpose” of the Building Act 1991 was “the
construction of
14 Minister of Education v H Construction North Island Ltd,
above n 7, at
[116]–[121].
15 Spencer on Byron, above n 9, at [45].
16 Building Regulations 1992, sch 1 cl E2.1 [Building Code].
buildings that do not pose health and safety risks to their
occupants”.17 That purpose is reflected in s 3 of the Building
Act 2004.
- [78] The
question of whether there has been a breach of the requirements of the Building
Code is ultimately a matter for me to determine.
However, the agreed approach of
the building surveyor experts is helpful in addressing that issue. They
concluded that where there
was water under the waterproofing membrane on the
balconies inspected that this was a breach of cl B2 (durability) with respect to
damage to the cork acoustic mat. They also agreed that there was a breach of cl
E2.3.2 to the extent that water has entered and damaged
the cork (being a
building element) and also to the extent that water had entered the exterior
walls causing damage in some locations.
- [79] I find that
the following breaches of the Building Code have been established: a breach of
cl B2 with respect to damage to the
cork acoustic mat, breaches of cl E2.3.2 to
the extent that water has entered the exterior walls and caused damage in some
locations
and a breach of cl E2.3.7 where the balconies and membrane were
constructed in a way that did not make due allowance for the consequences
of
failure. On the latter point, I agree with the submission of Mr Bigio KC that
the location of the downpipe, being located in some
instances very close to the
exterior wall, created a risk that if it was not sealed and constructed properly
and consequently failed,
it could cause a breach of E2.
- [80] Clause
B2.3.1 of the Building Code sets out the required durability of building
elements. “Building element” is defined
broadly in cl A2 of the Code
to be any structural or non-structural component and assembly incorporated into
or associated with a
building. I find that this definition encompasses cork
acoustic matting. The required durability is either 5, 15 or 50 years depending
on the characteristics of the particular building element, in particular how
difficult it is to access or replace and whether the
failure of the element
would be detected during the normal use or maintenance of the
building.
17 Spencer on Byron, above n 9, at [50].
- [81] Clause
B2.3.1(b) provides that building elements must satisfy the performance
requirements of the Building Code for at least
15 years where such elements are
moderately difficult to access or replace, or failure to comply with the Code
would go undetected
during normal use of the building (but would be easily
detected during normal maintenance). Clause 1.2.1 of Acceptable Solution B2/AS1
sets out some guidelines to evaluating the durability requirements of building
elements and states that “moderately difficult
to access or replace”
applies to building elements where access or replacement involves the removal or
alteration of other
building elements.18 To replace the cork acoustic
matting, it would be necessary to remove the membranes and other parts of the
balconies. Clause 1.3.1
refers to Table 1, which contains a list of nominated
building elements and their durability requirements; the durability requirement
for “surface mounted” acoustic elements is deemed to be 15
years.
- [82] Based on
this, I find that the cork acoustic matting has a durability period of 15 years
(at minimum). On the evidence, this
requirement has clearly been
breached.
- [83] Strictly
speaking, a balcony is not a roof or an exterior wall for the purposes of cl
E2.3.2. However, given the nature of the
construction here, the balconies do, to
some extent, perform a roof and exterior wall function.19
Furthermore, it logically makes no sense to exclude balconies from the
operation of cl E2.3.2 when, as here, the construction of the
balcony and in
particular the waterproof membrane system has failed to prevent penetration of
water that could cause damage or undue
dampness. Although
‘balconies’ are not expressly referred to, the failure of the
waterproofing of the balconies has,
at least to some extent, led to the
penetration of water into the exterior walls (which is, of course, expressly
referred to). There
is no other subclause within cl E2 that deals specifically
with balconies, and I find that the balconies here were constructed in
breach of
E2.3.2. In reaching that conclusion, it is important to have regard to the
overall objective in cl E2.1 (i.e. safeguarding
people from injury
18 See Bates v Auckland Council, above n 13, at [48], n 2: Acceptable solutions are
documents that set out methods of complying with the Building Code. Anyone who
complies exactly
with the methods described in the acceptable solution for a
Building Code clause is deemed to comply with the Building Code (see
s 19(1)(b)
of the Building Act 2004).
19 Mr Alexander noted that the pre-cast balcony, built off-site,
is incorporated on-site into the structure of the building. When the
concrete
floor is cured the balcony “becomes integral with the main
structure”. This is demonstrated at figure 05 of
his evidence at [10.2] of
his Brief of Evidence dated 28 October 2022.
that could result from external moisture entering the building) and the overall
functional requirement in cl E2.2 of adequate resistance
to penetration of
water.
- [84] In reaching
those conclusions as to breaches of the requirements of the Building Code, I
find that the damage at issue is more
than de minimis. As noted above, actual
damage is not required for a breach of the Code.
- [85] There is,
however, a real issue as to the extent to which the plaintiffs have established
actionable damage (beyond the threshold
of de minimis) and, in particular, in
and behind the cladding. On that critical issue I agree with and adopt the
findings reached
by Mr Alexander, namely that water penetration “into and
through the façade wall assembly” has been limited. I
agree with Mr
Alexander that to the extent that water has entered the inner part of the wall
assembly then that would represent a
breach of cl E2 (external moisture). I also
find that there is some merit to his statement that water entry into the
rainscreen cavity
is not necessarily a breach of E2 because the purpose of the
cavity is to collect rainwater and drain it back to the exterior (to
protect the
inner portion of the wall). However, in applying the principle of anticipation
and prohibition of potential damage, where
actual damage is not required, I
ultimately consider that there has been a breach of E2.
- [86] One of the
fundamental difficulties with the plaintiffs’ expert building surveyor
evidence is their failure to provide
an adequate scientific and reasoned basis
to reach the conclusions for which the plaintiffs contend, namely that there has
been significant
water penetration, or the very real risk of it, into and
through the façade wall assembly.
- [87] I
acknowledge that an assessment of the extent of damage, and in particular latent
damage, can be a difficult exercise. I agree
that a 100 per cent scientifically
accurate approach, particularly with a building of Bianco’s kind, cannot
be achieved. I
also accept Mr Bigio’s submission that the standard
destructive testing required in a case like this cannot be at such a level
that
it would effectively create an obligation on owners to repair first and sue
later. In principle, Mr Bigio is correct that one
will only ever know what the
actual loss is after the remedial work is completed.
- [88] I
acknowledge that the extensive photographs taken by Mr Angell are a helpful
starting point. However, it is not good enough
simply to rely upon the
photographs; some expert analysis, as carried out by Mr Alexander, needs to be
done to squarely address the
issue of extent of damage, including likely future
damage if remedial action is not taken. Furthermore, as noted above, the cogency
of the evidence required depends upon the seriousness of matters to be proved
and the consequences of proving them.20 Here, the allegations are
very serious; the plaintiffs seek tens of millions of dollars in
damages.
- [89] In
cross-examination, Mr Angell properly accepted that there was very limited
evidence of corrosion to the steel battens. In
my view, there is substantial
merit to the criticism Mr Alexander makes of the plaintiffs’ witnesses,
including a failure to
adequately appreciate that Bianco Off Queen, unlike other
leaky buildings, was constructed with concrete cantilevered decks above
non-habitable spaces, where there is in fact a cavity and where there is no
untreated timber framing. I also agree with the general
tenor of Mr
Price’s submission that if there is the degree of damage for which the
plaintiffs contend, then after the extensive
investigations undertaken and
monies spent on these (beginning in 2016) the plaintiffs would surely have been
able to provide more
substantive and probative evidence as to moisture
ingress.
- [90] I accept
and adopt the following findings made by Mr Alexander:
(a) a failure of both the waterproofing membrane and the sealant between pipe
and concrete must happen at the same location for leaking
to occur;
(b) the gutters do not drain large quantities of water;
(c) evidence of water damage to date is minimal; and
(d) the most vulnerable area is the rainscreen portion of the wall.
- [91] The
Auckland Council was correct in pointing out that the failures associated with
concrete joins are not pleaded defects. However,
that is somewhat beside
the
20 Z v Dental Complaints Assessment Committee, above n 10, at [112].
point. The membrane was supposed to protect the joins in the concrete as well as
the internal gutter. The sealant that was applied
to the underside of the
concrete joins was purely cosmetic. Water got into these joins because, amongst
other things, the membrane
directly above the joins failed. The pleadings
understandably focus on the failure with the membranes.
- [92] In
conclusion on the issue of defects and damage, I find that the plaintiffs have
established actionable damage in respect of
defect 1. However, to date, water
penetration into and through the façade wall assembly has been limited.
The plaintiffs’
building surveyor experts overstate the risk of future
water penetration. The consequence of these findings, namely the measure of
the
damage/loss established, is addressed below.
Is the damage in respect of defect 2 actionable
damage?
- [93] As set out
above, the alleged damage in relation to defect 2 concerns two areas; the podium
level (comprised of common walkways,
a truck dock and a series of enclosed
balconies) and the basement levels below.
- [94] The Scott
Schedule in relation to defect 2 records the agreement of Mr Angell and Mr
Alexander that there has been moisture ingress
from the podium to the carpark
below and that this has caused breaches of cls B2 and E2.3.2 of the Building
Code. However, Mr Alexander
considered that any breaches are confined to fire
collars and air-conditioning ducts.
- [95] Messrs
Angell and Alexander disagreed as to the primary cause of the water ingress. Mr
Angell said it was one of a number of
causes, all of which relate to the
negligent installation of the membrane. Mr Alexander’s view on the other
hand is that the
primary cause of damage was the inadequate use of waterproofing
membrane associated with the services pipe, fire collars and ducting.
He
considered damage was localised to areas where pipes and ducts penetrate
into the basement carpark. Mr Angell’s
view is that the membrane, as
applied across the podium area, has failed and has led to damage beyond that
associated with pipe and
duct penetration.
- [96] For the
reasons given above, I prefer and accept the evidence of Mr Alexander on these
issues.
- [97] Mr
Alexander investigated every penetration through the podium and identified which
of them were leaking. In cross-examination,
Mr August accepted that none of the
plaintiffs’ experts have carried out an exercise similar to Mr
Alexander’s investigation
of the podium leaks. Mr August acknowledged that
it “could be true” that Mr Alexander’s solution of simply
fixing
the penetrations that are leaking would work.
- [98] I note also
that Mr Alexander was the only witness who established that the largest cause of
leaking into the carpark was via
the services duct.
- [99] I find that
the plaintiffs have established the following actionable damage with respect to
the podium and the areas covered
by alleged defect 2. My findings are based in
large part upon the evidence of Mr Alexander:
(a) There is water leaking down the walls on either side of the external stairs
between the podium of building A and building B into
a cupboard below, partially
due to the use of an unreinforced and very thin membrane on the stairs.
(b) Of the 35 podium drainage outlets across both towers, 11 were found to be
leaking. These outlets are leaking for the same reasons
as with defect 1, namely
a poor connection between the concrete/membrane and the PVC drainpipe.
(c) As to the apartments at ground level with enclosed balconies, there was
insufficient membrane to outlets in drainage pipes.
- [100] I agree
with Mr Alexander that it is also important to place the defects in context. The
carpark was designed as a wet space.
The perimeter walls that retain the earth
have not been waterproofed. Some below-ground structures are waterproofed with
the intention
that groundwater will never enter the space, but that was not
the
intention with this design. The exterior retaining walls of the carpark allow
groundwater to enter and on the bottom level there
are drains to collect water.
This is a common and acceptable design choice.
- [101] I also
agree with Mr Alexander that efflorescence on the block work does not
necessarily constitute damage. As Mr Alexander
notes, efflorescence does not
indicate any diminution of structural capacity and is a visual nuisance rather
than damage. On the
other hand, severe efflorescent left untreated for a long
period would constitute damage, but that threshold has not been reached.
I also
agree that cars are not building elements and are therefore not protected by the
provisions of the Building Code. Although
it might have been arguable that any
damage to cars is a reasonably foreseeable consequence of the actionable defects
that I have
identified, no such claim has been made and such damage cannot be
established on the evidence before the Court.
Liability of Argon
Did
Argon owe a non-delegable duty of care?
- [102] The
plaintiffs sue in negligence. They must establish on the balance of
probabilities that the defendants owed them a duty of
care, that the duty of
care was breached (i.e. the standard of care was not met), that the breach(es)
caused damage, and that the
damages resulted in a loss to the
plaintiff.21
- [103] The case
law is settled; builders and local authorities in the performance of their
statutory functions relating to building
work owe duties of care to owners and
subsequent purchasers of buildings.22 As the Privy Council held in
the well-known case of Invercargill City Council v
Hamlin:23
In a succession of cases in New Zealand over the last 20 years it has been
decided that community standards and expectations demand
the imposition of a
duty of care on local authorities and builders alike to ensure compliance with
local bylaws.
21 Johns v Hamilton City Council [2022] NZHC 379 at
[69].
22 Johns v Hamilton City Council, above n 21, at [70].
23 Invercargill City Council v Hamlin [1996] 1 NZLR 513
(PC) at 521.
- [104] Builders
owe a duty to take reasonable care to prevent damage to persons reasonably
expected to be affected by their work, including
purchasers.24 The
scope of this duty is to ensure compliance with the Building
Code,25 good trade practice,26
and other relevant statutory requirements.27
- [105] Argon does
not dispute they owed duties of care to the plaintiffs. However, its primary
defence is that it did not breach any
duty of care. Argon contends:
(a) it was never its job to install the membrane, that was the job of the
specialist sub-contractor, TAL;
(b) Argon had no duty to ensure TAL installed the membrane correctly because it
did not have a non-delegable duty;
(c) as the principal, it had no vicarious/secondary responsibility for any
negligence of the independent contractor, TAL;
(d) Argon had no duty to supervise TAL;
(e) the architect was inspecting TAL’s work as it was done;
(f) TAL was a specialist water-proofer and Argon reasonably believed TAL to be
competent in its specialist field; and
(g) Argon was also entitled to believe that the Mapei product would be fit for
purpose.
- [106] The
critical issue for me to address is whether Argon owed non-delegable duties of
care.
- Bowen
v Paramount Builders (Hamilton) Ltd [1977] 1 NZLR 394 (CA) at 406 and 413;
Minister of Education v Econicorp Holdings Ltd [2011] NZCA 450; [2012] 1
NZLR 36 at [55].
25 Hotchin v New Zealand Guardian
Trust Co Ltd [2016] NZSC 24, [2016] 1 NZLR 906 at [198].
26 Boyd v McGregor HC Auckland CIV-2009-404-5332, 17
February 2010 at [60].
- Findlay
(trustees of the Lee Findlay Family Trust) v Auckland City Council HC
Auckland CIV- 2009-404-6497, 16 September 2010 at [33].
- [107] Todd on
Torts describes non-delegable duties as follows:28
The concept of a non-delegable duty is problematic... However, the category
is well established, if indeterminate, and is generally
associated with
relationships which give rise to a duty of care “of a special and
‘more stringent’ kind, namely a ‘duty to ensure that
reasonable care is taken’”.
(emphasis added)
- [108] The
classic case and the starting point for the analysis is Mount Albert Borough
Council v Johnson. There, the Court of Appeal imposed, for the first time, a
non- delegable duty of care on a development
company.29 Since then, it has been held in
some cases that a builder (i.e. a construction company), as head contractor, has
a non- delegable
duty of care.30 Where a
principal owes a non-delegable duty of care they will also be liable for
breaches by independent contractors they have hired.31 A head
contractor who had a primary duty of care would, therefore, be liable for the
acts of sub-contractors.
- [109] The nature
of the builder’s role and responsibilities are key to determining whether
it owes a non-delegable duty, as
opposed to being liable solely for its own
independent acts and/or omissions. Whether non-delegable duties are owed must be
decided
on the facts of each individual case. It is necessary to address whether
the builder is in substance the “head contractor”
and the extent to
which it controlled and supervised the building work. The label is not always
helpful. It is also apparent from
Mount Albert Borough Council v Johnson,
that public policy factors inform the ultimate
conclusion.32
- [110] In
Morton v Douglas Homes Ltd, Hardie Boys J framed the duty of care owed by
a builder to purchasers as a duty to “observe the bylaws and the permit
conditions,
and to take reasonable care to prevent loss or damage from defective
construction”.33
28 Stephen Todd “Vicarious Liability” in Stephen Todd
(ed) Todd on Torts (9th ed, Thomson Reuters, Wellington, 2023) at
[21.9.2] (footnotes omitted).
29 Mount Albert Borough Council v Johnson [1979] NZCA 46; [1979] 2 NZLR 234
(CA).
30 Body Corporate 346799 v KNZ International Co Ltd
[2017] NZHC 511 at [79]; citing Carrington v Easton [2013] NZHC 2023
at [80]; Lee v Ryang HC Auckland CIV-2011-404-2779, 28 September 2011 at
[20].
31 Body Corporate 346799 v KNZ International Co Ltd, above
n 30, at [80]; citing Cashfield
House Ltd v David and Heather Sinclair Ltd [1995] 1 NZLR 452 (HC) at
463–464.
32 Mount Albert Borough Council v Johnson, above n 29.
33 Morton v Douglas Homes [1984] 2 NZLR 548 (HC) at
589.
His Honour held that the builder’s duty to observe the bylaws and the
permit was a non-delegable duty and the fact that the
company engaged someone
else to assist it in discharging this duty could not excuse it for
noncompliance.34
- [111] In
Carrington v Easton, the responsibility of two sub-contractors, who
carried out defective building work under the head contractor, was in issue.
While
Venning J considered that the sub-contractors may have, in fact, carried
out some of the defective work, his Honour found they did
not owe the homeowners
a duty of care. Venning J considered the head contractor to be in control of the
site; the sub-contractors
were working under his direction and
supervision.35 It was the head contractor who directly contracted
with the homeowners, and it was his obligation to observe the relevant building
codes, regulations and plans and specifications. In reliance on Morton v
Douglas Homes Ltd, Venning J considered this to be a non-delegable
duty.36
- [112] In Body
Corporate 346799 v KNZ International Co Ltd (Victopia Apartments),
the developer (KNZ) entered into a contract with Multiplex (a construction
company) for it to “design, construct, complete,
deliver and remedy
defects” in the works described in the contract.37 The special
conditions required Mulitplex to exercise reasonable skill, care and diligence
in the construction. Multiplex was also
required to “provide all necessary
supervision during the contract” and all work was to be carried out under
the supervision
of Multiplex’s representative. Multiplex engaged various
consultants to provide specialist design services, including fire
engineering
design, and a contractor to supply and install the cladding systems.
- [113] Thomas J
held that Multiplex was solely in control of the aspects of design and
construction in respect of which the defects
occurred.38 Her Honour
noted that Multiplex made the stage two and stage three building consent
applications on behalf of the developer and had
issued a producer statement to
the Council in respect of the building work undertaken. As a result of its role
and responsibilities
as described,
34 Morton v Douglas Homes, above n 33, at 592.
35 Carrington v Easton, above n 30, at [79].
36 At [80]; citing Morton v Douglas Homes, above n 33, at 592.
37 Body Corporate 346799 v KNZ International Co Ltd, above
n 30, at [83].
38 Body Corporate 346799 v KNZ International Co Ltd, above
n 30, at [86].
Thomas J held that Multiplex owed a non-delegable duty of care in respect of the
defects.39
- [114] Gilbert
J’s decision in Body Corporate 326421 v Auckland Council
(Nautilus) is particularly relevant.40
His Honour concluded that the head contractor was liable in tort for the
creation and existence of all defects within the building
despite not having
designed or built all of them itself.41 This included the
waterproofing carried out by a sub-contractor. The head contractor was jointly
liable with the waterproofing company
for the failure to comply with the
manufacturer’s technical specifications, specifically a failure to allow
the waterproofing
membrane to cure sufficiently.42 The same finding
was made in relation to membrane which had not been dressed into outlets and for
a failure to ensure the membrane
was continuous at balcony nibs. Gilbert J
considered the head contractor to have “overall responsibility for the
works”,43 including the responsibility of ensuring that the
works met the requirements of the code.44
Argon’s responsibilities
- [115] Argon was
the head contractor and the builder at the centre of the construction work. It
had project management functions. It
was a key party with significant control
over and capacity to influence the quality of the construction and its adherence
to Building
Code standards. It entered into the construction contract, dated 1
March 2007, with the developer, Turn & Wave Ltd, to “construct,
complete, deliver and remedy defects” in the contract works and do all
things described in the contract documents (Construction
Contract). Argon
further agreed, as a matter of contract, to be responsible for the acts or
omissions of sub-contractors or sub-contractor’s
agents under cl 4.4 of
the special conditions.
- [116] The terms
of the Construction Contract are significant; the “contract price”
is described as $28,726,987. Under
cl 2.2.7 of the special conditions (attached
as the
39 At [89].
40 Body Corporate 326421 v Auckland Council [2015] NZHC 862
[Nautilus].
- At
[316]; see Thomas J’s description in Body Corporate 346799 v KNZ
International Co Ltd, above n 30,
at [90].
42 Nautilus, above n 40, at [183].
43 At [206].
44 At [227].
first schedule), Argon agreed to review certain aspects of the design or
specification of the contract works. The purpose of that
review was “to
reduce the construction cost and increase efficiency of the construction”.
Under cl 5.1.5, Argon took
full responsibility for the “adequacy,
stability and safety of all [s]ite operations and methods of
construction”. Under
cl 5.4.1, Argon was responsible for programming the
contract works and in accordance with cl 5.17.1 was required to provide a
documented
quality management system. Under cl 6.1 of Appendix 2: Scope of
Contract Works, Argon was also responsible for “complying with
all
necessary permits, consents and approvals under the Building Act 2004 for the
construction of the Contract Works.”
- [117] Argon was
responsible for engaging TAL and was privy to all relevant communications
between the architects (ADC), the engineers,
Mapei and TAL. It identified issues
with the consented plans and played a role in the design change to dispense with
the sawcut.
Argon was also responsible for the last step of the building-
related work that took place on the balconies, giving it an opportunity
to
observe the work that had been carried out by TAL (Argon placed a grate, or
grill, over the internal gutters on each of the balconies).
- [118] I
acknowledge that the design change that Mr Gabriel was involved with did result
in an improved design. However, there were
still defects, as I have identified.
I also note that Mr Gabriel himself conceded that the termination of the
membrane at the base
of the exterior nib was not a design that he had seen
before.
- [119] The terms
of the sub-contractor’s agreement between Argon and TAL are also
informative; the sub-contractor, TAL, was required
to comply with all
instructions from the contractor [Argon] and was specifically prohibited from
having any direct communications
with or taking instructions from the architect.
Furthermore, TAL indemnified Argon against any loss or liability arising out of
TAL’s
failure to comply with cl 19.1. That clause required TAL to comply
with the provisions of all legislation and bylaws, which must
include the
Building Code. The sub-contract expressly contemplated that Argon might be
liable for the acts or omissions of TAL with
respect to the Building
Code.
Conclusion – Argon’s
liability
- [120] In
considering the particular role of Argon in the construction of Bianco Off Queen
and having regard to the relevant contractual
documents, I conclude that Argon
did owe non-delegable duties of care to the plaintiffs (as subsequent
purchasers). Argon’s
claim that it is not liable for the acts or omissions
of TAL is rejected. I find that Argon is liable for each of the pleaded defects
(i.e. defects 1 and 2). The fact that the architect and/or TAL might also bear
some responsibility for the defects does not absolve
Argon from its liability as
head contractor and builder. There are also important public policy reasons of
accountability and loss
distribution which point firmly in favour of the
imposition of a non-delegable duty of care in this case.
- [121] In
relation to defect 1, Argon breached the standard of care required of a
builder/head contractor to construct Bianco Off Queen
in a code-compliant manner
and in accordance with good trade practice. It is responsible for the failures
with the installation and
performance of the balcony membranes and associated
defects. The negligent acts and omissions of Argon have caused the
plaintiffs’
loss. The issue of loss, including its measure and
calculation, is addressed below.
- [122] I also
find that Argon is liable in negligence for the defects I have identified in
relation to alleged defect 2. As I have
held above, Argon owed non-delegable
duties of care to the plaintiffs. Its contention that it is not responsible for
poor design
or poor workmanship by others is rejected. Argon cannot, in law,
rely on having engaged a specialist water-proofer or upon the Auckland
Council
inspecting the water-proofer’s work or the water-proofer issuing a
PS3.
Liability of the Auckland Council
Standard
of care
- [123] It is well
settled law that local authorities owe a duty of care to building owners when
performing their inspection and certification
functions under the Building
Act.45 The Supreme Court has held that this
duty of care “marches in step” with,46 and is
- North
Shore City Council v Body Corporate 188529 (Sunset Terraces) [2010] NZSC
158, [2011] 2 NZLR 289 [Sunset Terraces] at [51]; Spencer on Byron,
above n 9, at [6] and
[73]–[97].
46 Spencer on Byron, above n 9, at [71].
limited to, a local authority’s statutory functions under the Act.47
All building work must comply with the Building Code.48
Therefore, the duty imposes no higher obligation than the exercise of
reasonable care with a view to ensuring compliance with the
Code.49
Heath J, in the High Court Sunset Terraces decision, held as
follows:50
[183] In carrying out its inspection role, it is plain that the Council ought
not to be regarded as a clerk of works or as a project
manager. Even before the
Building Act was passed, the Council’s duty to third parties was “to
exercise reasonable care, not an absolute duty to ensure compliance”.
The
Council’s role is to provide an appropriate degree of oversight for public
policy reasons. Its performance must be judged
against the standards of the day
and knowledge of the quality (or otherwise) of particular products used in the
construction process.
It does not take on any responsibility for ensuring, in
fact, that all completed work complies with the [Building] Code.
- [124] The
standard of care to be applied is that of a reasonable skilled Council at the
time “but common industry practice is
not determinative.”51
A court might appropriately conclude that the standards of a Council at
the relevant time fell below the standard required by
law.52
- [125] The test
for, or standard of, a reasonable inspector has been referred to in many
decisions dealing with leaky buildings. Ronald
Young J held in Body Corporate
90247 v Wellington City Council:53
- [156] I accept,
in part, the Council’s criticism of his [one of the plaintiff’s
experts’] evidence. Mr Wutzler sets
a “gold” standard in the
identification of building trouble spots. Mr Wutzler’s expectation of what
a competent
building inspector should see is, I consider, set at his own
standard of knowledge of leaky buildings in 2013. Council building inspectors
could not be expected to have reached this advanced level of knowledge in
2000/2001. Any assessment of what a building inspector
could be expected to
identify is to be tempered by taking into account reasonable standards of the
day. I stress the word “reasonable”.
- [157] However,
it is not enough for an inspector to simply say “that’s how we did
it in those days”. If what the
inspectors were doing was
inadequate,
47 At [146] and [193].
48 Building Act 2004, s 17.
49 Section 18(1); and Spencer on Byron, above n 9, at [193].
50 Body Corporate 188529 v North Shore City Council, above
n 13.
51 Johns v Hamilton City Council, above n 21, at [74].
52 At [74]; citing McLaren Maycroft & Co v Fletcher
Development Co Ltd [1972] NZCA 29; [1973] 2 NZLR 100 (CA) at 102 and 108; Body Corporate
90247 v Wellington City Council [2014] NZHC 295 at [157]; and Dicks v
Hobson Swan Construction Ltd (in liq) [2005] NZHC 1657; (2006) 7 NZCPR 881 at [76].
53 Body Corporate 90247 v Wellington City Council, above n
52.
judged by a reasonable standard of the day, then it is no excuse to simply
say “that’s how we did it then”. There
was a significant
element of this approach in Mr Tait’s evidence as to his inspections of
the building work.
- [126] Ultimately
it is for the Court to determine the question of negligence as a matter of fact
in all the circumstances of the case.54 As the Court of Appeal held
in McLaren Maycroft & Co v Fletcher Development Co Ltd, the Court may
come to the conclusion that the standards deposed to by witnesses as to general
practice of a profession do not reach
the standard required by
law.55
- [127] Equally,
it is important to have regard to s 94 of the Building Act 2004. Section 94(1)
provides that a building consent authority must issue a code compliance
certificate if it is satisfied on reasonable grounds that
the building work
complies with the building consent (s 94(1)(a)). I agree with the submission of
the Auckland Council that the scheme of the 2004 Act, including s 94, was not
intended to bring about
a change in the territorial authority’s role and
responsibilities. As Whata J held in Body Corporate 160361 v BC 2004 Ltd and
BC 2009 Ltd (Fleetwood Apartments), the Council’s obligations
under the Building Act 2004 are not materially different from those under the
1991 Act,56 therefore the authorities
referred to above that were decided under the 1991 Act continue to
apply.
- [128] I further
note that inspection is defined in s 90(3) of the 2004 Act to mean the
“taking of all reasonable steps to ensure
that building work is being
carried out in accordance with a building consent”.
Defect 1
- [129] The
evidence and dispute in this case in relation to defect 1 focused very much on
the inspections carried out by the Auckland
Council and whether there was,
indeed, an obligation to inspect the balconies at all. There is also an issue as
to whether the Auckland
Council was entitled to rely on the PS3 statement from
TAL.
54 McLaren Maycroft & Co v Fletcher Development Co Ltd,
above n 52, at 107–108.
55 At 107–108; citing Sulco Ltd v Redit & Co Ltd
[1959] NZLR 45. See also Auckland Council v Ryang HC Auckland
CIV-2011-470-2570, 28 September 2011 at [24]; and Northern Farm Services Ltd
v Codylan Farms Ltd [2015] NZCA 567 at [16]–[18].
56 Body Corporate 160361 v BC 2004 Ltd and BC 2009 Ltd
[2015] NZHC 1803 [Fleetwood Apartments] at [142]; citing Spencer
on Byron, above n 9, at [217].
- [130] There were
substantial differences between the expert witnesses on these issues. The focus
of Mr Paykel’s evidence on
behalf of the plaintiffs was on specific
defects with the waterproofing membrane that Mr Paykel says the Auckland Council
inspectors
should have identified during their inspection(s). Mr Hutt, for the
Auckland Council, on the other hand, gave evidence of a more
generalised kind;
he obviously lacks the familiarity with the Bianco Off Queen apartments that Mr
Paykel has. The ultimate test in
assessing the admissibility and probative value
of expert opinion evidence is whether it offers “substantial help”
in
determining matters at issue.57
- [131] I accept
and agree in principle with Mr Hutt’s view that the Bianco Off Queen
balconies, being concrete and over non-habitable
areas, could properly be
regarded as less risky than other types of construction and, in particular,
cantilevered balconies with
timber framing over habitable spaces. However, I
reject the Auckland Council’s contention that there was no obligation to
inspect
the balconies at Bianco Off Queen. The Auckland Council did in fact
inspect the balconies; it assumed a responsibility to do so.
The notifiable
inspection schedule issued by the Auckland Council as part of the building
consent (where a total of 300 inspections
were estimated) expressly contemplated
an inspection of the membranes on the decks. This was a significant inner-city
high-rise apartment
block and at the relevant time, there was a heightened
awareness of general problems and failures with waterproofing membranes
generally,
as shown in the Council’s practice note from the relevant time
on external and internal membranes.58 The Auckland Council itself
appears to have set a higher standard of inspections than Mr Hutt would have
personally.
- [132] I also
note that the BRANZ Appraisal Certificate No 485 (2005), which relates to
Mapelastic external waterproofing membranes
(as well as Mapegum WPS), expressly
contemplated that there would be inspections of the membrane installations using
the Mapelastic
product. Clause 17(1) of the appraisal certificate states that
the technical literature must be referred to during the inspection
of membrane
installations
57 Evidence Act 2006, s 25.
58 See Auckland Council’s Practice Note on external and
internal membranes – alternative solutions (BLD-142-PN). Auckland
Council’s technical objections to the admissibility of that practice note
(including its relevance) are overstated. This is,
after all, an internal
Council document which expressly deals with membrane failures on decks. The
general heightened awareness of
problems with waterproofing membranes cannot
credibly be denied. Furthermore, the practice note does not make a clear
distinction
between timber and concrete substrate.
by building consent authorities and territorial authorities. Clause 17(2) notes
that critical areas of inspection for waterproofing
systems include installation
of the membrane to the correct thickness (according to manufacturer’s
instructions) and membrane
curing and integrity prior to the installation of
tiles.
- [133] I accept
that Mr Hutt has significantly more experience as a Council officer than Mr
Paykel. However, the Auckland Council’s
criticism of Mr Paykel’s
evidence, contending that he lacks expertise, is misplaced. Mr Paykel may have
been a Council officer
for a relatively short period of time, but he has
substantial experience as a building surveyor and generally in the construction
industry. He has previously given evidence as an expert witness for the Auckland
Council on matters of Council practice. Generally,
I found his evidence to be
substantially helpful.
- [134] Mr Hutt
was also a professional witness. However, in my view he tended to downplay the
responsibility of territorial authorities
in the discharge of their regulatory
functions. His perspective is inevitably informed by his very long period of
employment with
the Christchurch City Council. That does not, of course,
disqualify him as an expert witness but it is a factor here which goes to
the
weight that I attach to his evidence.
- [135] Mr Hutt
noted that the Building Code is a minimum standard, “often lower than the
industry recommendations (e.g. BRANZ)
or what is considered best (or even good)
trade practice, or indeed even the published Acceptable Solutions”. He
noted that
the benchmark that the Council must apply is the Building Code,
“nothing more”. I agree that the Building Code, a performance-based
code, imposes minimum standards, but the differences between this and good trade
practice should not be overstated. In this case,
poor and unacceptable
workmanship is a principal cause of the systemic membrane failure and the key
reason why there have been breaches
of the Building Code. I accept that the
Council inspectors are not “clerks of works” or specialists of every
element
of building construction. However, it is essential that the regulatory
regime has integrity, and that the inspection regime is sufficiently
robust so
that public confidence in its effectiveness is maintained. One of the public
policy reasons for the Council providing an
appropriate degree of oversight is
to promote
good trade practices with a view to avoiding breaches of the requirements of the
Building Code.
- [136] Like
Harland J in Johns v Hamilton City Council, I have reservations about
whether the kind of general evidence given by Mr Hutt is ultimately
substantially helpful to the Court.59 As her Honour noted, even if
such general evidence can be given:60
... what is more significant is what actually happened, and the best evidence
of that is the evidence of those who approved the consent,
undertook the
inspections and/or approved the code compliance certificate.
- [137] Harland J,
in commenting on the general rather than specific nature of Mr
Hutt’s evidence (and why it was not substantially
helpful), observed that
Mr Hutt did not know whether the Hamilton Council’s technical library
included relevant technical literature,
in particular the literature that Mr
Hutt had referred to in his evidence.61
- [138] The
Auckland Council submitted that Council officers in this case would not have
been familiar with the Mapelastic product and
how it was to be applied. However,
the evidence suggests an awareness by the relevant Council inspector at the time
of the Mapei
membrane that was being applied. In my view, it is reasonable to
expect the Council officer to have some familiarity with products
of this kind,
or at least to familiarise himself/herself with the technical
literature.
- [139] The
Auckland Council contends that it has a complete answer to the issue of
liability, namely its request and receipt of, and
reliance upon, the PS3
producer statement from TAL, who installed the membrane.62 It says
that the plaintiffs’ case relies on the evidence of Mr Paykel, including
his assertions that:
59 Johns v Hamilton City Council, above n 21, at [101]–[102] and [261].
60 Johns v Hamilton City Council, above n 21, at [101].
61 Johns v Hamilton City Council, above n 21, at [261].
62 There are four types of producer statements in use: design
(PS1), design review (PS2), construction (PS3) and construction review
(PS4).
Although the Building Act 2004 (unlike the 1991 Act) does not expressly provide
for the general use of producer statements, the Supreme Court held in Spencer
on Byron, above n 9, at [311], that
there is nothing in the 2004 Act to prevent territorial authorities from relying
on them and they are regularly used.
As Whata J noted in Fleetwood
Apartments, above n 56, at [165],
it makes practical sense for a territorial authority to rely on independent
expert verification that the installation of
the works have been undertaken in
accordance with plans and specifications.
(a) the Council did not request nor rely upon a producer statement from the
exterior membrane installer;
(b) the Council therefore chose to carry out its own inspections of the exterior
membranes, yet had “failed” to so inspect;
and
(c) if the Council had carried out membrane inspections on the balconies and
podium, it would have identified the alleged defects.
- [140] The
evidence of Mr Hutt for the Council on the other hand was that the membrane
application was specialised work carried out
by an approved applicator and was
being applied to concrete balconies that were not above habitable spaces, and
that the Auckland
Council would rely on those facts to be satisfied on
reasonable grounds that the works complied with the Code even without a producer
statement.
- [141] The
Auckland Council further argues that this difference in opinion became academic
when it came to light (during cross examination
of Mr Gabriel) that the Council
had requested producer statements be provided by the applicator, TAL, in respect
of both the balconies
and the podium. The relevant PS3s were in fact provided,
and the Council says that the evidence therefore “incontrovertibly
establishes” that the application of Mapelastic is a specialised exercise
(only to be done by an approved applicator) and that
the Auckland Council did
not undertake substantive inspections of the exterior Mapelastic membranes
(consistent with Mr Hutt’s
evidence).
- [142] The
Auckland Council contends that in all these circumstances it did exactly what Mr
Paykel considered it could permissibly
have done in the circumstances: it
sought, received and relied upon producer statements from the membrane
applicator rather than
carrying out its own inspections of specialist
work.
- [143] I reject
the submission that the Auckland Council has a complete answer to the liability
issue. It is regrettable that Mr Paykel,
at the time of serving his evidence in
chief, was unaware of the particular circumstances of the producer statements.
That is not
fatal to the plaintiffs’ claim.
- [144] As Gilbert
J held in Nautilus, it is not appropriate for a territorial authority to
accept any producer statement without question:63
The extent to which a particular producer statement should be relied on in
considering whether code requirements have been met would
depend on all relevant
circumstances. This would include, for example, the skill, experience and
reputation of the person providing
the statement, the independence of the person
in relation to the works, whether the person was a member of an independent
professional
body and subject to disciplinary sanction, the level of scrutiny
undertaken and the basis for the opinion. The territorial authority
would also
need to consider any other information relevant to whether the works had been
carried out to an appropriate standard and
could be expected to meet code
requirements.
- [145] Gilbert J
described the relevant producer statement in that case, from a Mr McEvoy
of Façade Technologies (who
manufactured and installed the exterior
cladding), as follows:64
Mr McEvoy simply completed a
pre-prepared form confirming that he was a duly authorised representative or
agent of Façade Technologies
and believed on reasonable grounds that it
had completed all building works in accordance with its contract ...
- [146] His Honour
further noted that Mr McEvoy made no reference to the Building Code and his
statement was “not even addressed
to
Council”.65
- [147] Gilbert J
rejected the Council’s “blind acceptance” of the PS3 from
Façade Technologies and stated:66
Whether or not
it was common for councils to accept PS3s from installers at the time the
Nautilus was built does not mean that it
was appropriate to rely on the
certificate provided in this case. What will be sufficient in one case may not
be in another. It obviously
depends on the particular circumstances. I accept Mr
Rainey’s submission that the process for determining code compliance is
not simply a matter of collecting pieces of papers, judgment is required.
- [148] The
Nautilus case is similar to the facts here. In this case, TAL’s PS3
did not do more than state that a representative of TAL “believes
on
reasonable grounds” that TAL’s work was carried out “in
accordance with the contract”. The Council did
not
63 Nautilus, above n 40, at [115].
64 Nautilus, above n 40, at [121].
65 Nautilus, above n 40, at [121].
66 At [125].
have a producer statement from TAL which certified that its work complied with
the Building Code. The Council’s own code of
practice for building
inspections, in force at the relevant time (first printed 1 November 2008),
noted that:
[PS3s] are usually issued by contractors stating their view that part (or)
all of the building work as described on nominated plans
and specifications has
been constructed and meet certain performance requirements of the Building Code
and/or conditions of building
consent.
- [149] In
essence, compliance with the Code and/or building consent is what matters.
Compliance with the contract is in my view insufficient
and should not have been
accepted by the Council.
- [150] Furthermore,
the Council’s code of practice made it plain that:
Producer statements can only be accepted from people who have applied to be
included on the Council’s producer statement register
and have had their
competence assessed. All producer statements must be completed in full and be
signed and dated. Photocopies will
not be accepted.
- [151] Mr Hutt
did refer to a register of approved producer statement authors. However, no such
register was produced in evidence.
Whether TAL (or its representative) was on
the register is unknown.
- [152] In any
event, TAL could not accurately have given the declaration of compliance with
the contract in this case because the balconies,
as built, did not comply with
the plans and specifications in the building consent. As is clear, the
sawcut/chase had been dispensed
with and so had the ACO drain (or
similar).
- [153] I further
note that Argon’s standard form PS3 expressly provided for a declaration
that the building work “has been
completed to the extent required by [the]
building consent and complies with the building consent. I understand that this
producer
statement, if accepted, will be relied on by [Auckland Council] for the
purposes of establishing compliance with the building consent.”
Both Mr
Gabriel, of Argon, and Mr Hutt, of the Council, gave evidence that a producer
statement is a statement of professional opinion
confirming that building work
will or does comply with the Building Code.
- [154] Having
disposed of Auckland Council’s “complete answer” submission, I
now address the particular allegations
of negligence against the Council that
the plaintiffs make.
- [155] The
plaintiffs contend that when Auckland Council officers were inspecting the
construction of the cantilevered balconies, they
should have
identified:
(a) That the membrane at the perimeter:
(i) was not terminated in accordance with the consented sawcut detail; and
(ii) was not terminated with an up-stand.
(b) That the membrane was not lapped into the drain.
(c) That the Mapefonic system was not used as the acoustic layer.
- [156] In
relation to the final point, I apprehend from the plaintiffs’ closing
submissions that they no longer claim that the
Auckland Council is liable for
the cost of installing replacement acoustic matting. I discuss this point in
greater detail below
in relation to the reasonable remedial scope.
- [157] The
plaintiffs say that upon identifying the remaining issues, the Auckland Council
should have failed the inspections and required
further information in order to
be satisfied that the waterproofing system would comply with the Building Code.
They say that the
Auckland Council should not have issued a code compliance
certificate (CCC) covering the cantilevered balconies until it was reasonably
satisfied of such.
- [158] The
Auckland Council accepts that the lack of an up-stand would be physically
observable if an inspector had carried out such
an inspection. However, it says
that an inspector checking the consented plans would see that no up-stand was
expected. Rather, a
sawcut was to be used. It further says that there is no
evidence to support
the plaintiffs’ contention that a council inspector ought to have
identified the lack of a sawcut.
- [159] The
Auckland Council also accepts, in relation to inadequately lapped membrane into
the outlets, that “missing membrane”
in some areas was sufficiently
obvious to even a lay person as being physically observable and falling short of
acceptable workmanship.
The Council similarly accepts that the lack of mesh
encapsulation in certain locations would be physically observable and would be
considered to fall short of acceptable workmanship.
- [160] As noted
above, a territorial authority’s duty is to exercise reasonable care in
performing its relevant regulatory functions.
That includes inspecting premises
to ensure compliance with the building consent and certification of compliance
with the Building
Code. In discharging its inspection functions in this case, I
find that the Auckland Council breached its duties of care in failing
to check
and observe that the balconies were constructed without the consented sawcut
detail. The Council’s own internal publications
at the time reinforced the
expectation that Council officers should be viewing and ensuring compliance with
the consented plans.
Had the non- compliance with those plans been observed and
then addressed, a Council officer, properly directed, should then have
turned
his attention to the issue of a membrane up- stand.67 This should
have directed the Council inspector’s attention to the waterproofing of
the membranes generally.
- [161] I further
find that the Council inspectors failed to sufficiently observe and identify the
poor workmanship associated with
the lack of mesh encapsulation and the failure
of the membrane to adequately to lap into the outlets. Both Mr Angell and Mr
Alexander
observed that the lack of mesh encapsulation was widespread. There was
a clear breach of the standard of care. I also find that the
Council inspectors
were negligent in failing to observe during inspections that no Mapeband tape or
gaskets had been used. I reject
the Auckland Council submission that this
alleged failure is
67 The BRANZ Appraisal Certificate No 485 referred to above
referred to the use of up-stands at cl 12.8: “Penetrations and up-stands
of the membranes must be raised above the level of any possible flooding caused
by blockage of deck and balcony drainage.”
unproven. As noted above, a reasonable reading of the Mapei technical literature
is that Mapeband tape or gaskets are an integral
part of achieving a watertight
function.
- [162] As to the
lack of thickness of the membrane, a failure to meet the thickness requirement
specified by the Mapei technical literature
is obviously (and accepted by the
Auckland Council) unacceptable workmanship. I accept the evidence of Mr
Paykel that in
instances where the membrane has been poorly applied and has the
appearance of a thin paint-type coating, concrete substrate imperfections
are
visible. In those circumstances, an inspector would have been able to assess
that the membrane had been inadequately applied.
Causation
- [163] In
relation to each of the defects, the Auckland Council raises the issue of
whether causation has been established, both factual
and legal.
- [164] I am
satisfied that in this case the plaintiffs have proven causation, both factual
and legal. I find that the Council’s
omissions were a substantial and
material cause of the loss suffered by the plaintiffs, as required for legal
causation to be established.68 The plaintiffs are not seeking here to
hold the Auckland Council liable for something more than protection against
non-compliance
with the Building Code. I agree with the conclusion reached by Mr
Paykel as follows:
Had the Council undertaken inspections of the balcony waterproofing [at the
time the membrane was applied], as required by their own
list of notifiable
inspections, the Council would have been able to identify the work that
didn’t conform with the approved
building consent and the balcony membrane
related defects. The [C]ouncil officer should have then failed the inspections.
A subsequent
re-inspection should have been required to ensure the work had been
completed in a compliant manner. A code compliance certificate
should not have
been issued unless all relevant inspections had been passed.
- [165] I conclude
therefore that the Auckland Council is liable in negligence to the plaintiffs
for defect 1.
- Price
Waterhouse v Kwan [1999] NZCA 311; [2000] 3 NZLR 39 (CA) at [28]; Party Bus Co Ltd v New
Zealand Transport Agency [2017] NZHC 413, [2017] 3 NZLR 185 at
[72].
Defect 2
- [166] It appears
there was only one inspection of the podium area, enclosed balconies and truck
dock by the Auckland Council. That
occurred on 12 November 2008 and resulted in
a “partial” pass.
- [167] There was
no challenge to Mr Paykel’s conclusion that the defects in this area would
have been observable at the time
and either would have been identified by a
competent Council officer during this inspection or should have been identified
had a
further inspection been undertaken of this area as indicated on the
checklist.
- [168] I find
that there was a breach of the standard of care by the Auckland Council in
relation to its inspections and the subsequent
decision to issue a code
compliance certificate. The plaintiffs have also established both factual and
legal causation and damage.
Conclusion on liability
- [169] I
find that Argon and the Auckland Council are liable as concurrent tortfeasors
for the damage caused by defects 1 and 2 (except
for the acoustic matting for
which Argon is solely liable). Apart from the acoustic matting, both defendants
are liable in full for
the entire indivisible damage and subsequent
loss.69
Reasonable remedial scope
Legal
principles
- [170] The
guiding principle for compensatory tort damages is the sum required to put the
plaintiff in the position it would have been
in had the wrong not
occurred.70
69 Chee v Stareast Investment Ltd [2010] BCL 300 at
[134]–135]; see also Morton v Douglas Homes Ltd, above n 33, at 613; and Hotchin v New Zealand
Guardian Trust Co Ltd, above n 25,
where the majority of the Supreme Court adopted a broad approach to the
meaning of “same damage” in s 17(1) of the Law
Reform Act 1936.
70 Bill Atkin “Remedies” in Stephen Todd (ed) Todd
on Torts (9th ed, Thomson Reuters, Wellington, 2023) at [24.2.1].
- [171] The
orthodox position in relation to property damage, as recently addressed by the
Court of Appeal in Leisure Investments NZ Ltd Partnership v Grace, is as
follows:71
(a) The basic measure for compensatory damages for physical damage to land and
improvements was traditionally the amount by which
the value is diminished,
rather than the usually higher cost of reinstating the property to its former
state.
(b) In more recent times, the courts have taken a more flexible, pragmatic
approach and will award the cost of reinstatement where
the plaintiff intends to
restore the property and it is reasonable to do so. In Chase v de Groot
it was held that the plaintiff “must” intend to reinstate before
such an award may be made and therefore the fact the
plaintiffs had already sold
the damaged property meant they were only entitled to the reduction in value.
- [172] The court
must ascertain the amount required to rectify the defects,72 and
damages should reflect the extent of the loss actually and reasonably suffered
by the claimant.73
- [173] In this
case, there is no dispute that the plaintiffs intend to repair the building. The
controlling question is whether the
remedial scope proposed, and the costs of
implementing that remedial scope, are reasonable in all the
circumstances.
- [174] I agree
with the Auckland Council’s submission that the appropriate measure of
loss is the reasonable cost of bringing
the defective building work up to
Building Code compliance – i.e. the reasonable cost of carrying out the
remedial works reasonably
required to be carried out to repair the specific
defects for which a party is liable. However, I reject its submission that the
reasonable cost is automatically to be equated with the least expensive
method.
- [175] In support
of its position, the Auckland Council relies upon the Supreme Court decision
Spencer on Byron, where Tipping J held that loss should be measured by
“the cost of bringing the building up to the standard required by the code
and thereby
- Leisure
Investments NZ Ltd Partnership v Grace [2023] NZCA 89, [2023] 2 NZLR 724 at
[176] (footnotes omitted). See also Johnson v Auckland Council [2013]
NZCA 662 at [110].
- Johnson
v Auckland Council, above n 71, at
[110]; citing Warren & Mahoney v Dynes CA49/88, 26 October 1988 at
22.
73 Leisure Investments NZ Ltd Partnership v
Grace, above n 71, at [184(c)].
removing the potential for physical damage and the associated health and safety
concerns.”74 The Auckland Council also relies on the decision
of Fisher J in J & B Caldwell Ltd v Logan House Retirement Home Ltd,
a contract case where his Honour referred to the “least expensive
method” of remedying loss.75
- [176] I agree
with the Council that Spencer on Byron makes it clear that a local
authority’s duty of care is directed at code compliance and that a
plaintiff’s loss is therefore
measured by the cost of bringing the
defective works up to Code. However, the above comment of Tipping J was made in
the context
of an argument that the Council’s duty of care should not
extend to protecting economic loss (rather than physical injury or
damage). This
finding does not stand for the proposition that the remedial works reasonably
required, and the reasonable cost of
carrying out those remedial works, always
requires adopting the least expensive method. As I have noted, the controlling
question
is reasonableness in all the circumstances. It is thus wrong to rigidly
conflate reasonableness with the least expensive method.
- [177] In
assessing that critical question of reasonableness, the most cost-effective
manner is obviously relevant and important, but
not determinative. As already
stated above, courts are approaching the measurement of loss in an increasingly
flexible and pragmatic
way.
- [178] There is
clear support for this approach in the decision of Gilbert J in Nautilus.
In that case, his Honour held that an enduring solution was required.76
He held that the plaintiffs should not have to accept makeshift repairs
and be left with the risk that this would not be effective
or durable. His
Honour accepted the plaintiffs’ claim in relation to wall cladding which
although was not based on the lowest
tender, had been recommended by the
plaintiffs’ experts because of its proven track record in New
Zealand.77 Gilbert J considered that it was reasonable to proceed
with the more proven system in accordance with expert advice and therefore
awarded damages on this basis.78
74 Spencer on Byron, above n 9, at [45].
75 J & B Caldwell Ltd v Logan House Retirement Home Ltd
[1998] NZHC 988; [1999] 2 NZLR 99 (HC) at 105.
76 Nautlilus, above n 40, at [39].
77 At [256].
78 At [257].
- [179] Similarly,
in Minister of Education v H Construction North Island Ltd Downs J
favoured the plaintiffs’ “tried and true”, and more expensive,
method despite it not necessarily being the
only Code-compliant method.79
The defendant’s proposed scope attracted heightened risk to the
plaintiffs to which Downs J considered they should not be exposed
to in
consequence of the defendant’s negligence.
The plaintiffs’ proposed scope of remedial
works
- [180] A scope of
works document was produced following the investigation process undertaken by
Maynard Marks in 2018. The plaintiffs
say that revision 8 of the scope of works
(MMSOW8) dated 20 September 2021 is the “foundation document” for
their remedial
scope. That document was audited by Mr August. It is to be read
together with the “Trade Breakdown Scope of Works 8 Estimate”
dated
15 November 2021. That trade breakdown is the work of the plaintiffs’
expert quantity surveyor witness, Ms van Eeden.
The plaintiffs say that updates
to the scope of works required to remedy defect 1 have been particularised, with
the works set out
and incorporated into a trade report dated 16 May 2023. That
trade report is said to be the product of discussions between Mr August,
Ms van
Eeden, Mr Angell and Mr Reddin.
- [181] The
plaintiffs’ case is that the defects identified require the removal and
replacement of the waterproof membrane. They
say that their experts and the
Council’s expert, Mr Matt Earley (who participated in the experts’
conferral), agree on
this. The plaintiffs describe the required replacement of
the joinery, balustrades and cladding as “consequential works”
that
arise from the requirement to replace the waterproof membrane and say that both
defendants are liable for this. They say that
building-wide repairs are required
in order to obtain building consent.
- [182] As Mr
August notes “the scope proposed by Maynard Marks is, broadly, replacing
the waterproof membrane system and then
consequential works to the balustrades
and other building junctions and materials required in order to obtain a
building consent
and code compliance.” The consequential works of the
proposed scope includes the removal and replacement of all joinery units
with
new ones, and a complete replacement of the cladding across the entire building.
That cladding work
79 Minister of Education v H Construction North Island Ltd,
above n 7, at [273].
would include the entirety of the cladding system, including metal battens, the
RAB board, and the building paper to be removed and
disposed of. The
re-cladding, in accordance with MMSOW8, would also include alteration of the
steel framing, including replacement
of corroded sections. The replacement of
all of the cladding and the joinery, with both new cladding and new joinery, is
a substantial
part of the total quantum sought by the plaintiffs.
- [183] In
relation to these consequential works, i.e. replacement of the joinery,
balustrades and cladding, the plaintiffs submit:
(a) These are “consequential” works in the sense that in order to
obtain a building consent and to complete the direct
remedial works, other works
must be completed, even though they relate to building elements that are not
necessarily defective themselves.
(b) There is no real dispute between the experts about the need for
consequential works. The Scott Schedule for waterproofing defects
acknowledges
that “[b]alustrades, joinery and cladding are consequential dependent on
the need to replace the membrane”.
(c) Once it is accepted that the waterproof membrane must be replaced, then the
extent of any consequential works must be determined.
- [184] The
plaintiffs submit that removal and replacement of the membrane will require
these other building elements, namely the joinery,
balustrades and cladding
sheets, to be removed for access. They assert that putting these elements back
into the building must be
done in the way that meets current Building Code
requirements, and that this will require the upgrading of the balustrades,
joinery
and cladding. They rely on s 17 of the Building Act 2004 for
this.
- [185] In
assessing the plaintiffs’ proposed remedial scope, I will first address
the legal requirements of the Building Act 2004. I will then consider the
evidence and factual basis of their scope and assess whether they have proven
that their scope is a reasonable
one that the Court should
adopt.
Interpretation of ss 17 and 112
of the Building Act 2004
- [186] The
parties filed an agreed joint statement dated 11 May 2023 regarding the proposed
replacement of the balustrades pursuant
to s 9(1)(b) of the Evidence Act 2006.
It records that:
- [4] The
plaintiffs, Council and Argon agree that:
...
|
(e)
|
These results mean that:
|
|
(i) As installed, the balustrades on the building complied with (and still
comply with) the standards used at the time of construction
to establish
compliance with the building code.
|
(ii) If the balustrades need to be removed for any remedial works to
the balcony membranes, and were to be reinstalled after
such works, they would
continue to comply with those standards.
|
(iii) However, the balustrades would not meet the standards used now to
establish compliance with the
building code if installed as new balustrades now.
|
- [5] The parties
further agree that the question of whether the balustrades can be reinstalled,
if they need to be removed for the
remedial works to the balcony membranes, is a
legal question for your Honour to determine in light of ss 17 and/or 112 of the
Building Act ...
- [187] While that
joint memorandum is confined to the issue of balustrades, the same issue, namely
the interpretation of ss 17 and 112 of the Building Act 2004, applies equally to
the joinery and cladding, which the plaintiffs say requires replacing.
All building work must comply with the building code to the extent required
by this Act, whether or not a building consent is required
in respect of that
building work.
- [189] The
defendants dispute the plaintiffs’ interpretation of the legislation. They
rely on s 112 of the Building Act. That section provides that a building consent
must not be granted for the alteration of an existing building, or part of an
existing
building, unless the overall building, following the alteration, will
continue to comply with the Building Code to at least the same
extent as before
the alteration.
- [190] The
question I must determine is as follows: is removing and reinstating such
balustrades, joinery and/or cladding sheets to
carry out work to the balcony
membranes, and then putting the same back afterwards, “building
work” as defined in the
Building Act 2004?
- [191] The
defendants say that this issue should be answered “no”. They rely
upon Determination 2009/60 of the Department of Building and Housing
dated 4 August 2009.80 In that case the issue for determination was
whether the local authority was correct to refuse to issue a building consent
that allowed
for the re-use of existing balcony barriers in their current
form.
- [192] The
decision-maker held that the reinstatement of the balcony barriers did not fall
within the definition of “building
work” (for the purpose of s 17).
Section 112 therefore applied. The decision-maker reasoned as
follows:81
- The barriers
were incidental to the remedial work being undertaken.
- The barriers
themselves are only subject to minor alterations to accommodate the recladding
works.
- The barriers are
to be reinstated in exactly the same location as before.
- The barriers
comply with the Building Code to the same extent as before the
alteration.
My opinion may have been different had the decks themselves been altered or
extended.
- [193] A similar
approach was adopted in a subsequent determination, namely Determination
2018/009 of Ministry of Business, Innovation and Employment (Building and
Housing) dated 23 March 2018, which involved remedial work carried
out to eight
decks of a building.82 The balustrades were removed in order to carry
out the remedial works to the decks. The balustrades, as an existing building
element,
were then reinstated to the same position and at the same height as
they were prior to
80 DepBH Determination 2009/60, 4 August 2009: Refusal to
issue a building consent that incorporates the re-use of existing barriers for a
house at 2/7 View Road,
Campbells Bay, North Shore City.
81 At [6.6].
82 MBIEBH Determination 2018/009, 23 March 2018: Regarding
the refusal to issue a code compliance certificate in respect of remedial work
to the decks to Units 220,
221, 224, 225, 228, 229, 232, and 233 at Terrace
Downs Villas, Lake Coleridge Road, Darfield.
the remedial works being carried out. The decision-maker held that their removal
and re-use was incidental to the remedial work being
undertaken.83
- [194] The
decision-maker ultimately considered that the building work undertaken, as
detailed and approved in the building consent
was the installation of suitable
fixings to re-position the balustrades in place. The removal and re-use of the
balustrades was not
in itself building work.84
- [195] I agree
with the approach adopted in those two determinations. In my view, they
correctly interpreted the provisions of the
Building Act.
- [196] The
approach adopted in these two determinations is consistent with the following
decisions of this Court.
- [197] In
Bates v Auckland Council, Gwyn J held that s 112 means that the proposed
alteration(s) to a building “must make the existing building no worse
(subject to the limited exceptions
referred to in s 112 itself)
and”:85
... there is no obligation – either
for the owner to do, or for a council to require
– to improve an existing building’s performance against the
Building Code, even where the existing building does not comply
with the
Building Code pre- works.
- [198] In
Wheeldon v Body Corporate 342525, Muir J approved the following summary
from Building Law in New Zealand summarising the interaction between ss
17 and 112:86
In other
words:
- Any new work
must comply completely with the Building Code subject to any waiver or
modification granted by the territorial authority
(for example, if a shower
compartment made of ordinary glass is being replaced, then the replacement must
be made of safety glass
as required to comply with the Building Code);
and
- After the
alteration, the whole building must comply with the Building Code to the extent
specified by s 112.
83 At [6.5.11].
84 At [6.5.12].
85 Bates v Auckland Council, above n 13, at [83].
- Wheeldon
v Body Corporate 342525 [2015] NZHC 884, (2015) 16 NZCPR 829 at [160];
referring to Building Law in New Zealand (online ed, Thomson Reuters) at
[BL112.02].
- [199] Gendall J,
in Fitzgerald v IAG New Zealand Ltd, considered the application of s 112
in relation to the repair of an earthquake-damaged house. His Honour held
that:87
... the [Building Act] only requires the aspects of the house that are being
repaired to be brought up to current compliance levels.
Elements that are not
repaired may be left at the same level of compliance as they were
originally.
- [200] In
applying all these principles to the facts of this case, I agree with the
submissions of the defendant and find that the
legal question set out at [190]
above is to be answered “no”. The proposed removal and reinstating
of balustrades, joinery
and/or cladding sheets to carry out work to the balcony
membranes is not “building work”. The position is as
follows:
(a) Replacement of the membrane must comply with the Code (i.e. that is
“building work” for the purpose of s 17); but
(b) Removal and reinstatement of the balustrades, joinery and cladding
sheets:
(i) are incidental to the replacement of the membrane;
(ii) these elements need not be altered (at least not significantly) to effect
replacement of the membrane;
(iii) they can be reinstated in exactly the same location as before; and
(iv) doing so will not worsen the extent to which they complied with the
Building Code before the alteration.
- [201] To put
this another way, the “new work” is the replacement and removal of
the membrane. It is governed by s 17 (all
building work must comply with the
Building Code). The balustrades, joinery and cladding sheets are all
“part[s] of an existing
building” governed by s 112 and therefore
must continue to comply with the Code at least to the same extent as
before.
87 Fitzgerald v IAG New Zealand Ltd [2018] NZHC 3447
at [50].
- [202] In my
view, this approach is entirely consistent with the stated purposes of the
Building Act 2004. The Act’s stated purposes at s 3 are directed at
regulation of building work and the setting of performance standards for
buildings to ensure (primarily) the healthy and safe use of buildings. This is
reflected by the comments of the Supreme Court in
Spencer on
Byron.88 The Building Act does not require existing buildings to
be upgraded to comply with the Code (other than in relation to fire and
accessibility, and
in other certain circumstances), even if existing buildings
are altered.
Is the plaintiffs’ scope
reasonable?
- [203] In
considering a reasonable scope of repairs, it is important to place this
building in context. It is a low-cost building with
high maintenance
requirements, with the cladding nearing the end of its 15-year minimum
durability life cycle. The fundamental problem
relates to concrete cantilevered
balconies over non-habitable spaces. There is no evidence that the concrete is
failing and there
was very limited evidence of water ingress in and behind the
cladding. I accept that the evidence of Dr Wakeling, biodeterioration
consultant, records detection of the toxigenic mould Stachybotrys, but
his evidence is confined to cork samples taken from beneath the balcony membrane
and tiles. This is not a timber-framed building,
and it has a rain- screen
cavity which appears to be in general workable order. The Maynard Marks proposed
scope of works (i.e. MMSOW8)
would require substantial expense and inconvenience
to the residents (on the plaintiffs’ own evidence, up to 43 weeks of
construction
works). This is a wholly disproportionate and unreasonable response
to the defects for which the defendants might properly be held
to be
responsible.
- [204] No party
in this case contends that the measure of the plaintiffs’ loss should be
diminution in value; the critical issue
is the reasonable scope of repairs.
Having said that, were I to accept the plaintiffs’ scope of repairs and
the significantly
increased costs associated with that scope, the appropriate
measure of loss, whether diminution in value or cost of reinstatement,
may
become a live issue. In total, the plaintiffs seek damages of $40,739,870. The
total construction cost portion of that sum is
88 Spencer on Byron, above n 9, at [44], [163]–[165] and
[171].
$33,376,240.89 In evidence, Ms van Eeden, the plaintiffs’
expert quantity surveyor, accepted that to demolish and re-build the Bianco Off
Queen
towers from scratch might actually be less expensive than her original
remedial costs estimate (where it was roughly in the range
of $50m to demolish
and re-build). I acknowledge that Ms van Eeden has not actually carried out
the necessary exercise to reach
a clear and definitive view, but that evidence
does tend to suggest that the plaintiffs’ scope is a disproportionate and
unreasonable
response to the actionable defects established. As noted, this is a
low-cost, high-maintenance building with a cladding system nearing
the end of
its 15-year minimum durability requirement. There are relatively few residents
for whom Bianco is a permanent home.
- [205] As
recorded above, the plaintiffs have faced some formidable challenges in
preparing for this hearing. As a result of the late
settlement of the fire and
hot water claims, the remaining pleaded defects (i.e. defects 1 and 2), and what
therefore remains of
the appropriate scope of repairs, have inevitably changed.
Those changes have also inevitably impacted the quantum of damages that
the
plaintiffs can appropriately claim. Immediately prior to and in the early stages
of the trial, I granted considerable indulgences
to the plaintiffs to file
supplementary evidence to address these significant changes. However, even
allowing for all of these factors,
I find that there are still substantial
problems with the plaintiffs’ proposed scope of repairs.
- [206] As the
defendants submitted, none of the plaintiffs’ witnesses, including those
from Maynard Marks, accepted that they
were the author of the scope of works
(MMSOW8). Ms van Eeden, formerly of Maynard Marks, was the author of the trade
breakdown of
15 November 2021, but she is a quantity surveyor and not a building
surveyor. The hearsay objection that the Auckland Council adopts
is a red
herring; I heard from at least three Maynard Marks witnesses and the MMSOW8 is
clearly a Maynard Marks product and document.
The real problem is the incomplete
nature of MMSOW8 and the fact that it is not adequately and sufficiently
tailored to the pleaded
defects.
89 The balance is general damages, consequential losses,
consultant costs and professional fees.
- [207] As stated,
the previous Maynard Marks building assessment report of 2018, together with its
enclosures, comprises 997 pages.
It includes a long list of scope items which
bear remarkable similarity to what is now before the Court in MMSOW8.
- [208] Mr August,
a building surveyor, but not associated with Maynard Marks, gave expert opinion
evidence on the scope of repair.
His evidence addresses whether the scope will
achieve a building consent and certificate of code compliance and whether there
is
a less costly or more efficient alternative. Mr August inspected the site as
part of a peer-review of the Maynard Marks investigations.
There are, however,
significant limitations with Mr August’s evidence. He responsibly
acknowledged as such. At the commencement
of his evidence, he states that he
would require a full detailed design review and input from various external
consultants in order
to be assured that a design scope would be “very
likely” to obtain building consent. In cross-examination, Mr August
accepted that MMSOW8 is a “broad scope” that outlines the
remediation of the project; “it is not a detailed scope,
and it is not a
detailed design”. He accepted that MMSOW8 is addressed at fixing
“all of these defects in the round”,
as opposed to identifying what
is required for any one specific issue. Mr August was ultimately unable to say
that the plaintiffs’
proposed scope could achieve a building consent. He
described it as hypothetical.
- [209] I accept
the plaintiffs’ submission that the vast majority of cases of this nature
are taken by bodies corporate before
remedial work is undertaken; the simple
reason is that owners are not in a financial position to fund the cost of the
remedial work
without a contribution from the responsible defendants. In such
cases, a scope of work is proposed without knowledge of the full
extent of the
damage. Assumptions must be made as to the scope of work required to remediate
the building. The scope needs to be
costed by quantity surveyors unless it
reaches the point of being converted into a set of drawings, which are then the
subject of
tenders from contractors.
- [210] I also
accept that the plaintiffs were not required to produce a full and comprehensive
set of drawings and/or a draft building
consent application – albeit that
ultimately will be required. However, it is for the plaintiffs to prove
causation and damage,
and sufficient evidence with structure and coherence is
required so that the Court adequately can assess whether the alleged loss
is
proven. As Mr Price
submitted, in this case the plaintiffs have put “all their eggs in one
basket”; they have not provided an alternative
methodology or basis for
the Court to find in favour of an alternative and reduced scope of works.
- [211] In support
of their claim for a full and complete replacement of the cladding (as part of
the scope), the plaintiffs rely on
an expert façade engineer, Mr Andrew
Hakin. Mr Hakin participated in a joint expert conferral with Dr Winter
(Auckland Council’s
façade engineer expert) and Mr Paget
(Argon’s façade engineer expert). There is very little agreement
between
Mr Hakin on the one hand and Dr Winter and Mr Paget on the other. The
Scott Schedule is notable for its extensive recording of
disagreements.
- [212] Mr August,
for the purposes of his evidence on scope, accepted that the cladding requires
complete replacement. He says his
view is based on the evidence of Mr Hakin. I
agree with the Auckland Council submission that Mr August relies substantially
on Mr
Hakin in support of the view that the cladding is unsuitable. The critical
evidence therefore on the cladding issue is that of Mr
Hakin.
Evidence of the façade engineers –
cladding
- [213] Mr
Hakin’s evidence is that the ExoTec cladding system used on Bianco Off
Queen was not suitable (and never was) and should
be removed and replaced with
high-density fibre cement cladding. Mr Hakin did not recommend a partial re-clad
of the building and
says that a partial re-clad of Bianco Off Queen using
medium-density fibre cement cladding (i.e. the current ExoTec panels) would
not
be granted a building consent. In Mr Hakin’s view, as set out in the Scott
Schedule, a reasonable façade engineer
would not provide a PS1 or PS2 for
a partial re-clad or for any re-clad using ExoTec panels. Mr Hakin identified
the following reasons
for his opinions:
(a) The current panels are medium-density panels that are unsuitable for a
building like Bianco Off Queen (i.e. high-rise towers
in contrast to a
“beach house” where such panels might be appropriate).
(b) ExoTec has high maintenance requirements that will not be met on this
building.
(c) The building does not have the required thermal break for the use of
ExoTec.
(d) Existing studs are at centres that are not in accordance with the technical
documents and do not comply with design requirements.
(e) The RAB board may be damaged during the removal of ExoTec panels or may be
of inferior condition.
(f) Light gauge galvanised steel battens have been used that are unlikely to
meet the criteria of clause B2 of the Building Code.
- [214] The
defendants’ experts, Dr Winter and Mr Paget, take issue with virtually all
of these reasons. The defendants say that
the costs of what Mr Hakin proposes
“would be enormous”. They say that it cannot be the reasonable cost
of repair unless
the consent for the balcony remedial works (if that is made
out) would only be granted on the basis that Mr Hakin proposes.
- [215] I agree
with Mr Bigio that Mr Hakin was “a passionate professional”. The
issues that he and the other façade
engineer witnesses address are
complex and difficult. However, Mr Hakin’s evidence, as he candidly
acknowledged, reflects his
professional engineering judgement. It is a
conservative, risk averse approach and I apprehend that it is based in part on
what appears
to be a philosophical objection to the low-cost/high-maintenance
model of the Bianco kind. Ultimately, of course, it is for the Court
to
determine how the Building Code is to be interpreted and applied; the
Court’s role is not to re-shape or amend that Code.90
- [216] A
fundamental premise of Mr Hakin’s evidence is his opinion that “the
existing cladding system”, which in
his view is a medium-density painted
fibre cement board, was not a suitable choice for the cladding of Bianco Off
Queen. He emphasised
the onerous maintenance requirements of the James Hardie
technical specifications for ExoTec, which he considers inherently unlikely
to
be carried out on a building like Bianco Off Queen. He explained that “the
whole point of [his] evidence is that we
90 There is no suggestion that the Building Code (i.e. delegated
legislation) is ultra vires.
must use appropriate products that limit the risk of non-maintenance related
failure early on, on a product’s life”.
- [217] As the
Auckland Council submits, Mr Hakin’s evidence presents the plaintiffs with
a significant causation problem. If
Mr Hakin is right, and the cladding system
is defective and the building requires a full re-clad regardless of the works to
the balcony
membranes, then the proposed full re-clad fails the “but
for” causation test (or at least raises a significant issue
of
betterment). The plaintiffs’ reliance on the “egg skull”
principle and the judgment of Downs J in Minister of Education v H
Construction North Island Ltd is misplaced.91 There is no
pre-existing vulnerability; the status quo of the cladding system is not
non-compliant with the Building Code. The plaintiffs
do not plead that the
cladding system was defective, and the as-built situation is that Bianco Off
Queen’s cladding system,
as approved by the building consent and accepted
as part of the code compliance process, is code compliant. There is no
evidential
foundation for me to reach any other conclusion.
- [218] Mr Hakin
is on sound ground when he contends that Bianco Off Queen is a high-maintenance
building. I note that Mr Alexander
shares that view. Again, however, that is the
“as-built” situation and the cladding system was, and remains, code
compliant.
In any event, the evidence is far from clear that the onerous
maintenance requirements on this building have not been met. The Janus
Façades report of 2018, commissioned by Maynard Marks, describes the
cladding as being “in good condition”, although
I accept that the
report also identified some deferred maintenance issues and is now some five
years old.
- [219] I agree
with the defendants that much of Mr Hakin’s evidence is premised on his
engineering judgement that exceeds the
minimum requirements of the Building Code
and rather than what the Building Act 2004 and Building Code actually require. I
respect Mr Hakin’s professional judgement but as noted, I must apply the
existing legal
framework. That includes the application of s 18 of the Building
Act 2004, which provides that a person who carries out building work is not
required to “achieve performance criteria that are additional
to, or more
restrictive than, the performance
91 Minister of Education v H Construction Ltd, above n 7, at [292].
criteria prescribed in the building code in relation to that building
work.” See also
Spencer on Byron.92
- [220] I agree
with the Auckland Council submission that the density issue is a red herring.
The critical question is whether the cladding
sheets comply with the relevant
performance requirements of the Building Code and not the label attaching to
them. As Dr Winter explained,
the relevant New Zealand (and comparable
international) standards do not classify fibre cement sheets based on density.
Rather, Australian/New
Zealand Standard (AS/NZS) 2908.2:2000, which Mr Hakin
agrees was the relevant standard both at the time of construction and now,
classifies sheets into type A and type B. It provides that “type A sheets
are intended for external applications where they
may be subjected to the direct
action of sun, rain and/or snow”. ExoTec is classified as a type A
sheet.
- [221] In any
event, the actual density of the board is 1552 kg/m³ or 97 per cent of Mr
Hakin’s definition of high-density.
Dr Winter would not expect any
material difference in the performance between sheets which are 1600 and 1552
kg/m³ respectively.
- [222] On the
critical issue of whether a façade engineer would approve a partial re-
clad of the building and whether a building
consent would thus be granted, I
prefer the evidence of Dr Winter and Mr Paget. Their opinions are premised on
what, in my view,
is the correct legal premise, including a minimum durability
requirement of 15 years under the Code for the ExoTec product.
- [223] In his
supplementary brief, Mr Hakin expresses the view that the absence of a thermal
break is a further reason why the cladding
is unsuitable. In his oral evidence
he described this as a “fundamental reason” why he considers the
cladding system
fails to meet the performance requirements of the Code. However,
for the reasons submitted by Auckland Council, I prefer the evidence
of Dr
Winter on this issue.
- [224] Clause
E3.3.1 of the Code provides that “an adequate combination of thermal
resistance, ventilation, and space temperature
must be provided to all ...
spaces where
92 Spencer on Byron, above n 9, at [193].
moisture may be generated or may accumulate”.93 There is no
evidence that establishes that this requirement has been breached, despite the
fact that the building is now towards the
end of the 15-year durability period
for the building envelope.
- [225] As
explained by Dr Winter in his supplementary brief, “a thermal break can be
used to prevent the dew point for condensation
occurring within the framing such
that condensation will not form on the steel studs.” The in-service
performance apparent
from the plaintiffs’ investigations shows that after
nearly 15 years the as-built construction is performing adequately in
terms of
the E3 performance requirements.
- [226] Mr Hakin
agreed that any problems with the absence of a thermal break or an inadequate
thermal break would have manifested by
now. I note that Dr Winter’s
opinion in this respect was not challenged by the plaintiffs in
cross-examination.
- [227] Both Dr
Winter and Mr Paget considered that the RAB board is a thermal break (and Mr
Paget noted that the RAB is a wood fibre
insulating board). In addition to the
RAB, Dr Winter refers to the air gap and isolation created by the shim packers
shown on the
extract from the structural drawings set out in Mr Hakin’s
reply brief. Dr Winter was of the view that this isolates the steel
battens from
the RAB and the steel framing in terms of the transfer of heat.
- [228] I accept
the opinion of Dr Winter and Mr Paget. The presence of a thermal break is a
complete answer to Mr Hakin’s evidence
on that point, where the relevant
Acceptable Solution (E3/AS1) simply calls for a thermal break (rather than
requiring a particular
type of thermal break).
- [229] On the
remaining issues of the existing stud centres, including applicable wind loads,
damage to the RAB board during removal
of ExoTec panels and the durability of
the steel battens, I also prefer the evidence of Dr Winter. The plaintiffs have
not established
that the existing stud centres are not in accordance with the
original James Hardie technical documents or that the RAB board may
be damaged
during removal of the ExoTec panels. As Dr Winter noted, if any damage does
occur, it “should be relatively simple
to remediate”.
93 See also cl E3.2, the functional requirement element.
- [230] I also
agree with the defendants that the 15-year durability period in cl
B2.3.1(b) of the Building Code expressly
applies to the cladding system here, as
well as the steel battens. Clause B2.3.2 effectively provides that
“hidden” elements
(such as the battens) must have the same
durability as those elements which hide them (the cladding). I note also that
the 15-year
durability for the battens is made expressly clear in Acceptable
Solution B2/AS1.94 Clause 1.0.1 of B2/AS1 provides that it applies to
“materials and components required to satisfy the performances as
specified
in other NZBC clauses.” Clause 1.3.1 states that “table 1
is an acceptable solution establishing the durability requirements
of nominated
building elements.” Table 1 then provides that:
(a) For non-structural cladding systems, such as the ExoTec system used at
Bianco Off Queen, the minimum durability period is 15
years; and
(b) For cavity battens for wall cladding systems, the minimum durability period
is 15 years where the wall cladding durability is
15 years.
- [231] As a
matter of engineering judgement, there may be some merit to the views of Mr
Hakin about the durability standards in the
Building Code. However, it is not
the role of the Court to decide what are ultimately policy decisions about the
merits of the standards
and content of the Building Code.
- [232] On the
final issue of whether a PS1 or PS2 from a façade engineer would be
required for the cladding remedial works (and
whether it would likely be
issued), I prefer the evidence of Dr Winter. I also agree with the submission of
the Auckland Council.
- [233] Dr Winter,
who has over 50 years’ experience as a civil/structural engineer, with a
particular focus on façade
engineering, says he is not aware of any
situation in which a PS1 or PS2 has been sought, let alone required, by a
building consent
authority for the removal and reinstatement of cladding sheets.
Dr Winter notes that that is a very different situation from one
of targeted
repairs or a partial re-clad, where only the
- In
accordance with s 19(1)(b) of the Building Act 2004, compliance with an
acceptable solution establishes compliance with the Building Code.
defective parts of a cladding system are repaired/replaced, where the concern
might arise that not all weathertightness problems
will be identified and
further similar problems might develop in the future. Dr Winter says that he
would expect a façade
engineer to be comfortable providing a PS1 or PS2
if one was sought for removal and reinstatement of cladding sheets. He notes
that
he would be comfortable himself providing either a PS1 or a PS2.
- [234] As the
Auckland Council submits, there is no dispute that the Council would need to be
satisfied that a proposed new external
envelope would comply with the Building
Code as new “building work”. However, Dr Winter and Mr Paget do not,
as noted,
propose a “new exterior envelope”. The cladding sheets can
simply be removed and replaced.
- [235] I also
agree with the Auckland Council’s submission that there could be no
suggestion that the Council could require the
Body Corporate to apply for a full
re- clad or refuse a consent for the balcony remediation if the Body Corporate
did not propose
a full re-clad, based on the unsuitability concerns that Mr
Hakin raises. The Auckland Council is statutorily obliged to issue a
building
consent for proposed works if those works will comply with the Building Code
(subject to s 112 of the Building Act 2004, for existing
buildings).95
- [236] In
conclusion on the façade engineering expert evidence, I find that the
plaintiffs have not established that there is
a need for a full replacement of
the cladding.
Mr Earley’s evidence – Auckland
Council
- [237] The
Auckland Council elected not to call expert building surveyor evidence on either
the defects or scope of remedial works.
Instead, it sought to challenge and put
the plaintiffs to proof. It did brief and serve a witness statement from Mr
Matthew Earley,
building surveyor. However, and presumably for tactical reasons,
the Council elected not to call him to give evidence. Mr Earley
did participate
in the expert
95 See DepBH Determination 2012/023, 30 March 2012: The
exercise of the powers of an authority in refusing to grant an amendment to a
building consent for remedial work
to a house at 107 Realm Drive,
Paraparaumu.
conferral for waterproofing defects and to that limited extent there is some
evidence from him before me.
- [238] Mr Earley
agreed, as set out in the Scott Schedule, that removal of the balustrades,
joinery and cladding would be dependent
on the need to replace the membrane. He
expresses no view on whether the balconies required a membrane, noting that that
depends
on whether concrete requires protection from water. Mr Earley is
of the view that instead of the jack-tile system, a reasonable
repair option is
a direct-fixed tiling system by Ardex, which involves an exterior membrane and
drainage mat and has acoustic properties.
Based on the evidence of Dr
Winter, Mr Earley is of the view that the cladding replacement could be
limited to one sheet either
side, and above, the balcony door openings. He is
also of the view that the removed panels could then be replaced with new ones
(using
the same or similar product). Mr Earley states that without a
waterproofing membrane, the existing balustrades, joinery and cladding
would not
need to be removed.
- [239] That
limited evidence from Mr Earley does not constitute a comprehensive and
sufficiently detailed scope of remedial works for
me to adopt in this case. It
does, however, provide some support for the scope proposed by Mr
Alexander.
- [240] I find
that Mr Alexander’s scope of repairs is the appropriate, reasonable scope
of repairs to address the proven defects
in this case.
Mr Alexander’s scope of repair
- [241] I accept
and adopt the alternative scope of repair prepared and proposed by Mr Alexander.
As Mr Alexander notes, the key to
the repair of the building is to address the
two very specific points of leaking rather than the substantive replacement of
components
as proposed by the plaintiffs.
- [242] Mr
Alexander’s proposed scope of works, in relation to defect 1, includes the
following:
(a) removing the failed membrane;
(b) removing the cork acoustic layer;
(c) fixing any visible hairline cracks in the balcony concrete with an epoxy;
(d) filling the construction joint, where it exists, with an epoxy mortar so
that water cannot track to the building wall;
(e) moving the outlet hole further from the building wall, and sealing into the
hole a new downpipe fitting so that water cannot
track to the building wall;
(f) leaving the balustrades in place;
(g) leaving the aluminium joinery in place (the old membrane that extends under
the joinery does not need to be removed because it
is not being replaced);
(h) waterproofing the balcony concrete with Aquaron 2000, as an extra layer of
protection; and
(i) installing a new under-flashing as designed by Mr Alexander.
- [243] As Mr
Alexander notes, the balconies are entirely outside the exterior wall of the
building except for the portion where the
exterior wall butts to the underside
of the balcony, a width of about 150 mm. I accept his evidence that there is no
possibility
of liquid water leaking into the interior beyond the outside face of
the concrete beam (as shown by the red line in the drawing at
figure 24 of his
brief of evidence). That means, as Mr Alexander explains, the only at-risk area
is the portion of balcony shaded
pink in figure 24.
- [244] A detailed
scope of remedial works prepared by Mr Alexander is set out at Appendix D to his
brief. That includes a remedial
scope for defect 2 which is split into three
parts: part 1, podium to building A (2 White Street); part 2, podium to building
B (8 White Street); and part 3, services duct building B (8 White Street).
In
respect of parts 1 and 3, this involves the application of Aquaron 2000 to the
entire area.
- [245] I find
that the plaintiffs’ criticism of Mr Alexander’s proposed scope is
misplaced. It is not, as contended, a
“lab experiment”. It may have
novel elements to it but that does not, of itself, mean that it will not obtain
the necessary
building consent or that it is somehow unreasonable. I find that
Mr Alexander’s scope is a viable and realistic means of repairing
this
building. I also accept Mr Alexander’s evidence on the proposed
application of Aquaron 2000 and the associated verification
method.
- [246] I reject
the plaintiffs’ submission that Mr Alexander’s evidence is somehow
tainted by the involvement of Argon
in the development of his scope. Argon
clearly has an interest in minimising the cost of any remedial scope, but it was
not wrong
of Mr Alexander to test aspects of his scope with Argon, the party
with, after all, the best first-hand knowledge about these buildings.
Ironically, if I were to accept the plaintiffs’ criticisms of Mr Alexander
and reject his evidence, then there would be no
scope before the Court that
could be accepted. Ultimately, it is for the plaintiffs to prove their case,
including a reasonable scope
of repairs for which the defendants might properly
be responsible.
- [247] Mr
Alexander responsibly acknowledged that aspects of the plaintiffs’
remedial scope were commonplace. He described the
jack-tile system as popular
and part of an industry-wide response to concerns with bonding tiles directly to
the membrane. He also
accepted that the Auckland Council had recognised the
jack-tile system was one way of achieving a maintainable membrane system.
However,
none of those factors support a finding that Mr Alexander’s scope
is unworkable or not viable.
- [248] Mr
Alexander’s proposed scope requires none of a number of problematic
elements contained in the plaintiffs’ proposed
scope. This includes the
following:
(a) In cross-examination Mr August accepted that the plaintiffs’ proposed
scope would involve an increase to the height of
the nib walls and that this
would add weight to the balconies. In his original evidence,
Mr August said that this was not recommended by the structural engineer. In his
amended brief of evidence, he said instead that this
would need to be reviewed
by the structural engineer. In cross- examination, Mr August was unable to
explain why these statements
differed.
(b) The plaintiffs’ proposed new nib wall would be higher than the
apartment floor level. That creates an obvious flooding
risk. In cross-
examination, Mr August accepted that if both the proposed new “overflow
hole” and the adjacent new outlet
hole became blocked, the apartment would
flood because the water would enter the apartment before it could overflow the
balcony.
(c) The plaintiffs’ proposed raised tile system would make the relative
height of the existing balustrades too low, requiring
new higher balustrades,
which would add weight.
(d) The plaintiffs’ proposed new balcony channel would be twice as wide as
the existing channel and would run the length of
the balcony. This would
therefore involve removing a lot more concrete than Mr
Alexander’s proposal. That is an
obvious stress point, so the less
concrete removed the better.
- [249] Mr
Alexander’s scope requires none of these problematic elements. The nib
walls would remain as they are, as would the
balustrades. The tiles would not be
raised. There would be no additional weight. There would be minimal removal of
concrete.
- [250] Mr August
accepted that a competently installed sealant around a new outlet pipe, as
proposed by Mr Alexander, would prevent
leaking. He also accepted that if the
outlet hole is moved away from the building, as (again) proposed by Mr
Alexander, then even
if it did leak, water running down the pipe could not
physically enter the building wall.
- [251] Furthermore,
Mr August accepted that proper filling of the construction joint with epoxy
mortar, as included in Mr Alexander’s
scope, would prevent water entering
the building wall. I accept the submission that Mr Alexander’s flashing
detail is easily
buildable, and that his overall scope provides several layers
of protection.
- [252] I accept
that Mr Alexander’s statement that he was 100 per cent confident that his
proposal would obtain a building consent
is a little surprising. However, as I
have noted, he was an impressive witness whose evidence is unassailable. I have
no doubt that
Mr Alexander expressed that view fully aware of the reputational
consequences for him if it proved not to be correct. It is not a
reason to
reject his evidence.
- [253] I agree
that ordinarily it would be good trade practice to remove all of the membrane
including that extending under the joinery.
However, as agreed by the experts,
that would require removal of all or most of the joinery which, in my view,
would be a wholly
unreasonable and disproportionate approach. I
accept Mr Alexander’s evidence that the existing membrane will need
to
be cut in line with the bottom of the joinery.
The acoustic matting
- [254] The
relevant evidence about acoustic matting was given by Mr Jon Styles. That brief
was admitted by consent. It addresses the
issue of whether the Building Code
imposes any acoustic attenuation requirements relevant to the balconies of
Bianco Off Queen.
- [255] Argon and
the plaintiffs agreed that it was not necessary to call Mr Styles to give
evidence on the basis that the plaintiffs
could submit that Mr Styles’
opinion that the Building Code imposes no acoustic continuation requirements
relevant to the Bianco
Off Queen balconies is applicable only after
Determination 2015/007.96
- [256] The
plaintiffs take the position that the acoustic layer was part of the original
design of Bianco Off Queen. They contend that
an acoustic matting layer is
a
96 MBIEBH Determination 2015/007, 2 March 2015:
Regarding the authority’s exercise of powers in refusing to issue a
modification of clause G6 for an apartment
block at 105–109 Apollo Drive,
Rosedale, Auckland.
reasonable cost of repair in order to restore the plaintiffs to the position
they would be but for the negligence of Argon.
- [257] They also
accept that the Auckland Council will not likely require acoustic matting on the
balconies in order to comply with
the Building Code. As stated above, the
plaintiffs accept that the Auckland Council cannot be liable for the cost of
replacement
acoustic matting.
- [258] This issue
was given relatively cursory attention throughout the hearing and in closing
submissions.
- [259] Argon was
clearly negligent in installing cork matting instead of the proposed Mapefonic
acoustic matting. It was reasonably
foreseeable that if a membrane failed, the
cork matting would be particularly vulnerable to rotting. I find that Argon is
liable
for the replacement cost of the acoustic matting ($111,628) on
conventional negligence principles. It owed the plaintiffs a duty
of care, it
breached that duty, and the plaintiffs have suffered loss caused by the
defendant’s negligence. It is reasonable
to require Argon to restore the
plaintiffs to the position they would have been but for the negligence of
Argon.
- [260] I conclude
that the plaintiffs’ claim in respect of the acoustic matting is made
out.
What will it cost to repair the defects?
The
parties’ positions
- [261] The
plaintiffs seek total damages of $40,739,870 calculated as follows:
97
(a) Total construction costs – $33,376,240;
(b) Total professional fees – $2,114,871;
- The
sub-total figures are those which I have taken from the plaintiffs’
closing submissions – claim summary dated 22 June
2023.
(c) Consultant costs incurred to date (investigations) – $576,699;
(d) Consequential losses (relocation costs, alternative accommodation costs,
loss of rent, etc) – $3,332,060;
(e) General damages – $1,340,000.
- [262] In support
of their claim for construction costs of $33,376,000, the plaintiffs rely on
their expert quantity surveyor, Ms van
Eeden. The estimate for those costs is
based on a 43-week construction duration. The largest items of expenditure in Ms
van Eeden’s
estimate relate to a full re-clad and replacement of all the
joinery units and associated costs. This includes rainscreen and cladding
costs
of $7,497,704, joinery unit costs of $3,858,869 and internal linings and
services costs of $2,685,792. Ms van Eeden’s
total cost for the
replacement of the balcony membrane, namely
$7,130,921, includes costs of $1,656,690 for supplying and installing new
powder- coated aluminium cap flashing to the nibs and $844,550
for supplying and
installing a new jack-tile system. It also includes costs of $771,750 for
constructing new reinforced concrete
nibs to raise the height of the existing
nibs on the outer edges of the cantilevered balconies. Of the total site set-up
and general
work items estimate of
$5,903,005, Ms van Eeden estimates scaffolding costs of $1,476,000. That is, of
course, based on a 43-week construction duration.
- [263] Mr Brock,
the expert quantity surveyor witness for Argon, estimates that Mr
Alexander’s scope of remedial works would
cost in the region of $4.5
– $4.7 million plus GST (i.e. total budget estimate of $5,776,000 plus
GST, minus the fire protection
remedial work (settled) of $805,000 plus
P&G).98
- [264] The
Auckland Council position on quantum is as follows. If I accept, as I have done,
the Council’s s 17 Building Act 2004 interpretation and also conclude (as
I have done) that there is no need to replace the joinery units and balustrades,
then the cost
of any reasonable repair scope, even with the addition of margins
and contingencies, is in the order of “about $2m.”
In support of
its position, the Auckland Council has
- In
his evidence in chief Mr Brock stated that “ball park” it would cost
$4.5 million plus GST. His handwritten notes on
his brief of evidence, recorded
during the presentation of evidence, record
$4.7 million.
filed a comprehensive cost estimate and cost calculation schedules containing
lowest common numbers as between the expert quantity
surveyors.
- [265] As Mr
White of Auckland Council stated, the first step in any methodology for
assessing the value of a scope of works and preparing
a detailed cost estimate
is to understand the scope of what is being costed; “[w]ithout a
reasonable understanding of the scope
of works, a quantity surveyor cannot
reasonably cost the works”.
- [266] The
plaintiffs submit, correctly, that the “departure point” for the
quantity surveyors is the scope of works.99
- [267] My
rejection of the plaintiffs’ proposed scope of remedial works and
acceptance and adoption of Mr Alexander’s scope
presents challenges and
difficulties for the plaintiffs’ case and my calculation of quantum. I
have rejected the “foundation
document” upon which Ms van Eeden for
the plaintiffs bases her estimates. In light of my findings on scope, the
critical factual
premise of many of her calculations, which involve a 43-week
construction duration, are simply not relevant. That is particularly
the case
for those “big ticket” items relating to rainscreen cladding and
joinery. Further important estimates, including
Auckland Council fees,
scaffolding requirements, architect’s fees, quantity surveyor costs and
contract administration and
project management costs, while of relevance to the
scope I accept, were developed for a particular design and scheme of works that
I have rejected. A substantial adjustment to those figures would obviously be
required to quantify the cost of those particular items
for Mr Alexander’s
scope.
- [268] In making
these findings, I do not criticise Ms van Eeden’s integrity or her
professional approach. She obviously did
her best in difficult circumstances
with the scope of works evolving and lacking coherence. She also responsibly
accepted that she
would need to further revise her costs estimate in light
of the plaintiffs’ expert
99 In the case of Mr White, his replacement brief of evidence
addresses Ms van Eeden’s trade breakdown provided with her February
2022
brief of evidence, and a subsequent trade report provided with her May 2023
evidence, referred to as her “supplementary
trade report”. In his
original brief of evidence, Mr White had addressed a revised scope of works that
Mr Matthew Earley had
intended to give evidence about. As noted, Mr Earley was
not ultimately called to give evidence. In cross-examination, reference
was made
by Mr White to the revised scope of Mr Earley. In contrast to Argon, the
Auckland Council did not produce an alternative
scope of works.
programmer, Mr Gould, revising his construction duration estimate. In her
original brief of evidence Ms van Eeden estimated costs
of $62,698,000
(inclusive of GST) based on a 90-week construction duration and a scope of works
that included claims (i.e. fire and
hot water) that have now been settled. In
her supplementary brief of evidence of 16 May 2023, Ms van Eeden estimated costs
of $45,972,972.70
based on a reduced scope and a reduced construction duration.
Ms van Eeden further accepted that if a different construction duration
was
required, then she would again have to adjust her costs estimate.
- [269] The only
expert quantity surveyor witness who squarely and directly addresses Mr
Alexander’s scope is Mr Brock. He presented
his evidence in a professional
and competent manner. His evidence is the obvious starting point for my costs of
repair determination.
- [270] I reject
the Auckland Council’s submission that I should, on a line-by-line basis,
determine each individual scope item
that is reasonably required to address the
defects for which I have held the defendants responsible for – and then
determine
costs in accordance with the least expensive estimate based on the
comparison schedule that the Auckland Council has provided. While
there is
undoubtedly overlap with the items that Mr Brock has costed, neither Mr
White nor Ms van Eeden has costed
Mr Alexander’s scope. That is, of
course, a matter for expert evidence and as noted above, the quantity surveyor
undertaking
the exercise must have a reasonable understanding of the particular
scope at issue. There is a real danger, were I to adopt the Auckland
Council’s approach, of determining items and quantifying their cost in an
uninformed and unscientific manner. There are simply
too many variables.
Furthermore, as Mr Price submitted, the plaintiffs’ evidence does not
provide a clear methodology or mechanism
for applying Ms van Eeden’s
various cost items to the much more limited scope (i.e. Mr Alexander’s)
that I have accepted.
- [271] Mr
Price’s submission was that the “line-by-line” approach was
the only way that I could credibly address
the quantification of scope issue,
were I to reject the Council’s primary defence that the plaintiffs have
failed to prove
scope and quantum (on the basis that they are, in essence,
seeking an all or nothing
scope).
Preferred approach
- [272] The better
approach, which I adopt, is as follows. I accept Mr Brock’s calculation as
the starting point. It is based
on Mr Alexander’s scope, which I have
accepted as the reasonable scope of repairs. To the extent the evidence allows,
I will
then make factual findings on issues such as construction duration which
impact on Mr Brock’s calculations. I will then call
for further
submissions from the parties (but not evidence) as to whether and what further
adjustments ought to be made to
Mr Brock’s calculations in light of
my findings. Alternatively, it may be that the parties could reach agreement on
some final
calculation without my involvement.
- [273] A similar
approach was adopted by Whata J in Fleetwood Apartments.100 In
that case, his Honour determined that the proper measure of loss (for
compensatory damages) was a “wasted cost” measure.
However, only the
Auckland Council’s expert, Mr White, had assessed the quantum of
compensatory damages on that basis; the
plaintiffs had sought costs arising from
repairs with adjustments for collateral benefit as the tort measure. Whata J
granted leave
to the parties to address him on final quantum on the basis that
he had endorsed the methodology of the Council expert and subject
to certain
factual findings set out in the judgment.101
- [274] A broadly
similar approach was also adopted by Tahana J in Body Corporate 207624 v
Grimshaw & Co.102 In the substantive judgment, and following
the determination of liability, her Honour reached a conclusion on what the Body
Corporate
plaintiff was generally entitled to recover (i.e. the costs of the
interpleader proceedings and the repair costs that arose as a
consequence of the
18-month delay). Her Honour then prepared a summary table of her conclusions on
each head of loss.103 Some heads of loss required further
calculations to be undertaken in accordance with the relevant methodology her
Honour had determined
earlier in the judgment. Tahana J directed the plaintiff
to undertake the calculations of damages in accordance with the methodologies
prescribed in the judgment and to confer with the
100 Fleetwood Apartments, above n 56.
101 At [237].
102 Body Corporate 207624 v Grimshaw & Co [2023] NZHC
979.
103 At [525].
defendants.104 She then made separate orders on the papers as to the
quantum of damages following the filing of a joint memorandum.
- [275] I turn to
address the details of Mr Brock’s evidence. His quantum assessment is
based on a full scaffolding of the building.
It is also based on the
construction duration estimate of Mr Andrews, the expert programmer for Argon,
of 116 working days (or 164
calendar days). This is the gross estimated
construction period, including contingency. Mr Andrews’ evidence is of
course the
only expert programming evidence that directly addresses the issue of
construction duration for Mr Alexander’s proposed scope
of
works.
- [276] I find
that there should be some adjustment to the estimated duration figure for which
Mr Andrews contends. Having heard from
the expert witnesses generally on this
issue I find, based on the more practical experience of Mr Gould with local
Auckland conditions
(and the particular disruptions caused by inclement
weather), that Mr Andrews’ figure should be increased by 10 per
cent.
- [277] Mr
Brock’s estimate includes a ‘project contingency’ sum of 10
per cent. There seems to be little dispute
amongst the experts on that
percentage figure, regardless of the nature of the scope.
- [278] Mr
Alexander’s scope does not require any of the unit owners or tenants to
move out of their apartments during the construction
period. I generally agree
with that assessment. However, in terms of quantum I find that some modest
allowance should be made to
account for a small number of apartment owners
having to move out. It seems likely that in respect of a small number of
apartments,
the disruption caused by the remedial works to particular unit
owners and/or tenants will be such that it is reasonable to make some
allowance
for this. I stress that this contingency would be of a modest kind.
- [279] I further
find that some adjustment should be made to Mr Brock’s quantum assessment
to account for project escalation
costs. On the issue of project escalation
costs, I generally prefer the evidence of Ms van Eeden. She has an
economics
104 At [591(b)] and [592(a)].
background and stated in evidence that her original project costs escalation
estimate is proving in fact to be “fairly on track”.
Ms van Eeden
calculated an escalation factor for the period March 2023 to completion of
construction at 6 per cent per annum.
- [280] I accept
Mr August’s evidence that even with limited replacement of cladding, a
design will need to be prepared for a
weathertight detail between the existing
cladding and any new cladding. This does not appear to have been provided for in
Mr Brock’s
estimate and some allowance also needs to be made for
that.
Betterment
- [281] The
defendants have pleaded that any damage recoverable by the plaintiffs ought to
be reduced to such extent as the Court thinks
just and equitable to account for
the betterment the plaintiffs would otherwise receive at the defendants’
cost.
- [282] I have
already addressed above the competing interpretations of ss 112 and 17 of the
Building Act 2004 in relation to the joinery, balustrades and cladding. In
particular, by reaching the conclusion that the plaintiffs have not established
that there is a need for a full replacement of the cladding, the main issue with
regard to betterment has been dispensed with. There
is no further betterment
issue for me to address.
Consultants’ costs
- [283] Defects 1
and 2 have resulted in the plaintiffs incurring consultants’ costs with
respect to the investigation of the
defects.
- [284] The
plaintiffs claim for consultants’ costs the sum of $576,699 (exclusive of
GST).
- [285] I accept
that consultants’ costs are properly recoverable. I also accept that the
plaintiffs have made reasonable and
genuine efforts to calculate the amount
properly claimable, taking into account the settlement of the fire and hot water
defects
and excluding costs such as litigation work.
- [286] My
assessment is that the amount claimed is somewhat excessive. I have to proceed,
of course, on the evidence that is available.
I conclude that the plaintiffs are
entitled to consultants’ costs of $450,000, exclusive of GST. That amount
is to be awarded
to the Body Corporate.
Consequential losses
- [287] It follows
from my finding that I should adopt Mr Alexander’s scope of repairs that
the plaintiffs’ claim for loss
of rent, cost of alternative accommodation
and moving and storage costs must be dismissed. There is no requirement for any
of the
plaintiffs (except to a very limited extent and as addressed above) to
move out of the apartments in order for the remedial works
to be carried
out.
General damages
- [288] General
damages are a form of compensatory damages. They compensate for losses that
cannot be objectively quantified in monetary
terms.105 They cover,
for example, pain and suffering, indignity and humiliation and mental distress.
Todd on Torts explains:106
Mental suffering that
is insufficiently severe or permanent to qualify as a recognisable psychiatric
illness may be compensated by
an award of general damages if it is a consequence
of other actionable damage that makes the tort complete, or the claim is brought
under a tort that is complete without proof of actual damage.
- [289] Where the
plaintiff has a cause of action in negligence, general damages will be available
for distress, vexation, inconvenience
and the like if a reasonably foreseeable
consequence of the breach of duty.107 As Richardson J noted in
Mouat v Clark Boyce (No 2):108
... where there is
a duty of care to the plaintiff, the scope of the damages recoverable is
essentially a question of remoteness of
damage which turns on whether the
particular harm was a reasonably foreseeable consequence of the particular
breaches of duty which
have been established.
105 Body Corporate 346799 v KNZ International Co Ltd, above
n 30, at [104].
106 Atkin, above n 70, at
[24.2.9(2)].
107 Mouat v Clark Boyce (No 2) [1992] 2 NZLR 559 (CA) at
568 per Cooke P.
108 At 573.
- [290] The second
plaintiffs who claim general damages are those who are natural persons and whose
causes of action have not been assigned.
Unit owners who are companies cannot
claim general damages as a company does not suffer mental
stress.109
- [291] In
Victopia Apartments, the Body Corporate and unit owners of a 203-unit
complex successfully sued for defects relating to the cladding, balconies,
podium
and passive fire protection of the building.110 The defendants
were held to be liable for approximately $41 million for the remediation of the
defects. In addressing the issue of
general damages, Thomas J considered that a
“tariff style” analysis with adjustments for inflation was not
appropriate.111 Rather, her Honour adopted a “holistic
assessment” of the impact on the individual claiming general damages. I
agree with
and adopt that approach.
- [292] In
Victopia Apartments, the remedial works required meant that all those
living in the apartments had to relocate, causing significant inconvenience and
stress to those individuals.112 In awarding general damages, Thomas J
acknowledged that the plaintiffs had not been required to live in an uncompleted
building with
actual leaks and that the damage to the plaintiffs’
apartments had not, for the most part, caused any actual health risks to
the
occupants.113 Her Honour then made awards for general damages as
follows:114
(a) $15,000 for single non-resident owners;
(b) $25,000 for joint non-resident owners;
(c) $25,000 for single owner-occupiers; and
(d) $35,000 for joint owner-occupiers.
109 Harvey McGregor McGregor on Damages (19th
ed, Sweet & Maxwell, London, 2014) at [5-014];
O’Hagan v Body Corporate 189855 [2010] NZCA 65; [2010] 3 NZLR
486 at [153].
110 Body Corporate 346799 v KNZ International Co Ltd, above
n 30.
- At
[117]; referring to Johnson v Auckland Council, above n 71, at [118]–[120]. See also
Weaver v HML Nominees Ltd [2015] NZHC 2080.
112 At
[121].
113 At [120].
114 At [127].
- [293] The main
impact suffered by unit owners in this case has been financial and associated
stress. These owners have experienced
considerable uncertainty and distress for
a lengthy period; the diagnosis for Bianco Off Queen has clearly not been an
easy or simple
exercise. In some cases, there has been exacerbated stress and
inconvenience as a result of some unit owners, being non-New Zealand
residents
or nationals, having no familiarity with the local circumstances. I accept that
the damage has not, for the most part,
caused any actual health risks to the
occupants, although there has clearly been stress associated with the ongoing
uncertainty about
potential health risks. I must also assess general damages
here on the basis that none of the unit owners will have to move out or
the
remedial works (except for a small number for a very limited period as analysed
at [278] above).
- [294] I find
that general damages are to be awarded as follows:
(a) $10,000 for single non-resident owners;
(b) $16,500 for joint non-resident owners;
(c) $16,500 for single owner-occupiers;
(d) $23,000 for joint owner-occupiers.
- [295] There is
to be no award of general damages to the six second plaintiffs who were assigned
their causes of action.115
Standing
- [296] The
defendants do not dispute that the Body Corporate has standing to sue on behalf
of the owners of the apartments in respect
of common property. In this case,
that is the property the subject of defect 2. However, the Auckland Council
challenges the standing
of the Body Corporate to sue as a representative agent
of the owners in respect of the individual units (i.e. defect 1).
- Those
six second plaintiffs are named at [597] of the plaintiffs’ closing
submissions. The plaintiffs acknowledge that no general
damages are claimed for
these six assignees.
- [297] This
standing issue is of some significance because the Auckland Council advances the
affirmative defence of contributory negligence
against some of the individual
second plaintiffs. The Auckland Council submits that it does not owe the Body
Corporate duties of
care in respect of individual units. It further argues that
each unit owner must claim and authorise the Body Corporate to claim
on their
behalf in respect of damage to their individual unit. The plaintiffs on the
other hand, and in reliance on s 138 of the
Unit Titles Act 2010 (UTA 2010),
contend that the duty of care in respect of the relevant unit property is owed
to the Body Corporate
and that the affirmative defence of contributory
negligence does not apply to the losses at issue; those are the losses of the
Body
Corporate. The plaintiffs dispute the Auckland Council’s contention
that each unit owner must claim and authorise the Body
Corporate to
claim.
- [298] The
starting point is the Unit Titles Act 1972 (UTA 1972) and the foundational
authorities that address the issue of standing
under that now repealed
legislation. In Sunset Terraces, the Supreme Court held that unit owners
were owed duties of care and a body corporate’s status as plaintiff was
essentially
pursuant to a statutory agency created by s 13 of the UTA 1972 and
limited to the common property.116
(a) A unit owner could sue for the loss that they suffered as owner of the unit
(and thus, via operation of the UTA 1972, a joint
owner of the common property,
managed by the Body Corporate), such loss not requiring any consideration of
delineation between unit
versus common property; and
(b) The body corporate could sue as the unit owners’ statutory agent under
the UTA 1972 but only in respect of common property
(and, as agent, the claim
was only as good as each unit owner’s – including as to affirmative
defences such as limitation,
causation, contributory negligence and volenti).
- Sunset
Terraces, above n 45, at
[57]–[58]: “The subsection is obviously intended to enable bodies
corporate to sue on behalf of unit owners who, as
tenants in common, own the
common property”.
- [300] The UTA
2010 imposes duties on bodies corporate to repair and maintain building elements
and infrastructure that relate to or
serve more than one unit.117
Those provisions, including s 138 which the plaintiffs rely upon, distinguish
the UTA 2010 Act from its predecessor, the UTA 1972.
- [301] Section
138(1) of the UTA 2010 reads:
Body corporate duties of repair and maintenance
(1) The body corporate must repair and maintain –
(a) the common property; and
(b) any assets designed for use in connection with the common property; and
(c) any other assets owned by the body corporate; and
(d) any building elements and infrastructure that relate to or serve more than 1
unit.
- [302] In Body
Corporate 199380 v Cook, van Bohemen J referred to the mandatory
requirements of s 138 and
held:118
[67] Sections 84(1)(p) and 138 are new provisions that take the UTA 2010 into
territory – namely the maintenance and repair
of unit property –
that the UTA 1972 dealt with only in the context of schemes approved under s 48
or pursuant to rules where
the repairs could fairly be seen as incidental to the
body corporate’s duty to maintain and repair common property. Under ss
84(1)(p) and 138, not only can the body corporate maintain and repair unit
property, it is required to repair and maintain unit property
where it is either
building elements or infrastructure that serve more than one unit. Under s 5,
“building elements”
specifically includes roofs, balconies, decks
and cladding systems, while “infrastructure” includes all of the
utilities
and services to the development.
- [303] These
provisions were seen as important in overcoming difficulties that had arisen
under the UTA 1972. This was particularly
the case in relation to leaky
buildings where bodies corporate had been unable to step in to remedy defects
that may have been present
in individual units but which adversely affected
common
117 Unit Titles Act 2010, ss 84(1)(p) and 138(1)(d).
118 Body Corporate 199380 v Cook [2018] NZHC 1244, (2018)
19 NZCPR 522.
property, other units or the building as a whole.119 It is apparent
that the UTA 2010 shifts to place more emphasis on the Body Corporate as a whole
rather than the individual rights
of owners. That is apparent from Parliamentary
discussion introducing the Unit Titles Bill,120 as well as the
purpose sections of the Act.
- [304] The Court
of Appeal in Body Corporate S73368 v Otway, referred to the intention of
s 138 as follows:121
[45] In our view, the legislative policy is clear and s 138(4) can be
interpreted in a manner consistent with it. We reach this conclusion
for reasons
relating directly to the legislative purpose of Parliament in passing the UTA
2010. In addressing the mischief to which
this enactment was directed, the
legislature sought to address difficulties that had arisen when defects within a
unit affected other
units or the common property. It did so by assigning to
bodies corporate responsibility for building elements and infrastructure
found
within units and limiting owners’ rights and obligations accordingly. The
legislation permits a body corporate to act
to prevent harm that has the
potential to harm the common property, or any building element or any other
unit. In s 126 the legislature
created the necessary corollary, a flexible
mechanism to recover from owners the costs of remedial work done by the body
corporate:
an owner who benefits in a substantial way must pay, and in other
cases those owners who derive a substantial benefit must pay rateably
according
to the utility interest ...
- [305] In Body
Corporate 324525 v Stent (No 2), Associate Judge Bell held that a body
corporate has standing to sue for damage to unit property where the damage is
within the body
corporate’s responsibilities under s 138, even in the
situation where the unit owners are not joined as plaintiffs in leaky
building
proceedings.122 That case was an
application for summary judgment by the Body Corporate against the owners of
five apartments seeking unpaid levies.
His Honour held that it should matter
little to a tortfeasor whether the plaintiff is the Body Corporate or a unit
owner, stating:123
[147] Under the 2010 Act the body
corporate has repair and maintenance responsibilities both for common property
and for building
elements and infrastructure in principal units. In Wheeldon
1 Muir J and the Court of Appeal held that those responsibilities extended
to work on the defendants’ apartments. The body corporate
must be able to
fund its work under s 138. Where it has incurred or will incur expenses for that
work, it ought to have the means
to recoup those expenses from those responsible
for causing damage, including by suing for recovery. It would short change a
body
corporate to
119 At [68].
120 See (30 March 2010) 661 NZPD 10216.
121 Body Corporate S73368 v Otway [2018] NZCA 612, [2019] 3
NZLR 759 (footnotes omitted).
122 Body Corporate 324525 v Stent (No 2) [2017] NZHC 2857
at [150].
123 Body Corporate 324525 v Stent (No 2), above n 122, at
[147] (footnotes omitted).
give it repair and maintenance powers and duties under s 84(1)(p) without
also recognising that it may recoup its expenses, including
by suing
tortfeasors.
- [306] In a
subsequent decision, Body Corporate 207624 v Grimshaw & Co, Associate
Judge Bell confirmed his earlier finding that unit owners are required as
plaintiffs only for unit property that is not
covered by the Body
Corporate’s repair responsibility.124
- [307] In
assessing the plaintiffs’ submissions on standing, it is first necessary
to address the issue of whether the cantilevered
balconies of Bianco Off Queen,
the subject of defect 1, fall within the scope of s 138(1)(d) of the UTA 2010.
It cannot seriously
be contended that the Body Corporate has standing to sue in
respect of loss or damage that falls outside its responsibility under
s 138. The
Body Corporate does not have repair responsibility for unit property, except as
provided in s 138.
- [308] As stated
above, under s 5 of the UTA 2010, balconies are a “building
element”. Muir J, in Wheeldon v Body Corporate 342525, addressed
the issue of whether balconies related to or served more than one unit for the
purposes of s 138(1)(d). His Honour held
that the requirements of s 138(1)(d)
will be satisfied if the relevant building element or
infrastructure:125
(a) naturally attaches to another unit (as in physically adjoining units); or
(b) is causally relevant to another unit whether physically or economically (as
in non-adjoining units); or
(c) is referable to another unit whether physically or economically (as in both
adjoining and non-adjoining units); or
(d) is concerned with another unit whether physically or economically.
- [309] Furthermore,
Muir J held that the inclusion of “aesthetics” in the definition of
building elements and the emphasis
on “integrity of the development as a
whole” in s 3 (the purpose section) meant that the economic relationship
should
include those factors.126 The Court of Appeal confirmed this
approach.127
124 Body Corporate 207624 v Grimshaw & Co [2020] NZHC
34 at [18].
125 Wheeldon v Body Corporate 342525, above n 86, at [85].
126 Wheeldon v Body Corporate 342525, above n 86, at [86].
127 Wheeldon v Body Corporate 342525, [2016] NZCA 247,
(2016) 17 NZCPR 353 at [55].
- [310] One of the
issues in Wheeldon was whether decks located within individual units
could be considered to relate to or serve more than one unit. There were
“ingress
risk factors” present by virtue of the building’s
design which meant that the decks created, or were very likely to create,
a risk
of water ingress into adjoining units. The Court of Appeal upheld Muir J’s
conclusion that every deck affected more
than just the unit of which it formed a
direct part, thereby bringing the decks within the scope of s 138(1)(d).128
The Court of Appeal’s rationale for bodies corporate undertaking
these repair and maintenance obligations is that it is not
realistic for unit
owners to arrange such repair work individually; building-wide repairs that have
implications for the structural
integrity and aesthetics of the development
require co-ordinated and professional management.129
- [311] When
applying the principles of Wheeldon to this case, I find that the
cantilevered balconies of Bianco Off Queen, the subject of defect 1, fall within
the scope of s 138(1)(d)
of the UTA 2010. Given the widespread nature and extent
of the defects, the construction of this building and the location of the
balconies, I find that every balcony affects more than just the unit of which it
forms a direct part. That conclusion is entirely
consistent with the rationale
for bodies corporate undertaking building-wide repairs of the kind at issue
here, as identified by
the Court of Appeal in Wheeldon. This is the very
sort of case where it is not realistic for unit owners to arrange the repair
work individually. The necessary building-wide
repairs require coordinated and
professional management.
- [312] I find
that the Body Corporate here does have standing to sue for damage to unit
property in these circumstances. In my view,
its status goes beyond the role
bodies corporate had as statutory agents under the UTA 1972 in respect of common
property. The Body
Corporate, under the UTA 2010, is entitled to sue in its own
name and to recover in its own name damages that fall within the scope
of its s
138 responsibilities. That is entirely consistent with the legislative policy of
assigning responsibility to bodies corporate
for building elements and
infrastructure that relate to or serve more than one unit and limiting
owners’ responsibilities accordingly.
It is not necessary for all
individual owners to agree to that course of action, provided of course that
the
128 Wheeldon v Body Corporate 342525, above n 127, at
[67].
129 Wheeldon v Body Corporate 342525, above n 127, at
[68].
damage at issue is properly within the scope of s 138. This finding is
consistent with the Court of Appeal’s conclusion in
Otway; s 138
was intended to limit owners’ rights and obligations.130
- [313] There are
sound policy reasons, aside from obvious efficiency, in support of my conclusion
on standing. The nature of the loss
here, being economic loss arising from
physical damage, falls on the general body of owners, no matter when they bought
their unit,
whether their own unit has damage, and whether or not they took
proper care when buying or not. It falls on them generally because
of the Body
Corporate’s responsibility under s 138 and its power to collect levies
fixed by ownership interests.
- [314] However,
this finding on standing is not determinative of whether the Auckland Council
can raise an affirmative defence of contributory
negligence. Unit owners may, as
in this case, have claims that fall outside the Body Corporate’s s 138
repair responsibility,
including such costs as alternative accommodation while
remedial work is carried out and general damages for mental distress. In
respect
of heads of damage of that kind, and for which the Body Corporate has no claim,
in principle damages in favour of unit owners
could be reduced on account of
contributory negligence. A critical and more difficult question is whether
contributory negligence
defences can be advanced, and consequential quantum
deductions offset, in relation to damage to units that falls within the scope
of
s 138(1)(d).
- [315] That
question is answered, in my view, by analysing the nature of the duties of care,
the type of loss at issue and the scheme
of the 2010 Act, in the context of the
broad discretion that arises under s 3(1) of the Contributory Negligence Act
1947.
- [316] As van
Bohemen J held in Body Corporate 199380 v Cook, s 3 of the UTA 2010 makes
clear that the basic legal structure of unit title developments set out in the
UTA 1972 is retained; so
too, is the fundamental theme identified by Heath J in
Fraser v Body Corporate S63621 of the distinction between individual
units owned by unit
130 Body Corporate S37668 v Otway, above n 121, at [45].
owners and common property for which the body corporate is responsible.131
However, as noted by the Court of Appeal in Wheeldon, the rights of
unit owners are derived from the statute and are of a limited kind.132
They are not akin to the ownership of fee simple in land. The unit owners
do not enjoy a right to undertake repairs and maintenance
and the rights
conferred on them by ss 79(d) and 79(e) are limited.
- [317] On the
other hand, the scheme of the UTA 2010 and in particular ss 142 and 143,
indicate that the legislation does not intend
to cut across the general law of
tort or to impact on general duties of care except to the extent expressly
provided for.
- [318] Against
that background, I am of the view that the defendants owed concurrent duties of
care to both the Body Corporate and
the individual owners. The Body Corporate
has sufficient interest in the units and is required to repair and maintain
damage that
falls within the scope of s 138, even if the individual owner does
not agree. Its interest is more than contractual. It is only the
Body Corporate
which can undertake the necessary remedial action to which s 138 applies. Its
pocket is damaged as a result of the
negligence of the defendants, even if it
can recoup expenses from the individual owners.133 In principle, the
affirmative defence of contributory negligence is available, and deductions can
legitimately be made for contributory
fault of either the Body Corporate or
individual owners from any quantum sum awarded to the Body Corporate.
- [319] The
discretion under s 3(1) of the Contributory Negligence Act 1947 is, however, a
wide one. The person suffering the damage
can include both the body corporate
and the individual unit owner. The ultimate test, once fault is determined, is
what is just and
equitable. This wide provision gives the Court sufficient
flexibility to make the necessary adjustments in any individual case.
- [320] In
reaching the conclusion that the defendants owed concurrent duties of care, I
reject the Auckland Council’s submission
that there is not the necessary
element of
131 Body Corporate 199380 v Cook, above n 118, at [64]; citing Fraser v Body
Corporate S63621
[2009] NZHC 1222; (2009) 10 NZCPR 674 (HC) at [34].
132 Wheeldon v Body Corporate 342525, above n 127, at [36].
133 See Sunset Terraces, above n 45, at [53].
reliance by the Body Corporate to support the imposition of a duty of care.
Although the Body Corporate is a statutory construct,
at its inception and the
commencement of its s 138 responsibilities, it does rely, as do the individual
owners, on the diligence
and skill of those involved in the construction of the
building and the certification of its status as code compliant. There are
also
sound policy reasons for the imposition of a concurrent duty of care. There is a
clear level of efficiency in such an approach,
but it also allows, in the
exercise of the Court’s broad discretion, to have regard to fault by
individual owners.
- [321] I do,
however, accept that it does matter to the tortfeasor whether the plaintiff is
the Body Corporate or a unit owner. I respectfully
disagree with the contrary
view referred to above, as expressed by Associate Judge Bell in Body
Corporate 324525 v Stent (No 2).134 The status of the plaintiff
does matter because not only are there potential GST implications, as well as
the contributory negligence
issue and issues of limitation and the like, but
also what the Auckland Council describe as the risk of “double
jeopardy”
for defendants. The Council gives the example of where an owner
sells their unit at a loss (due to impending remedial costs regarding
defects
for which the Council might be liable), allowing them to pursue a claim for that
loss, yet (based on the plaintiffs’
proposed approach) the Body Corporate
could also sue for those impending remedial costs.
Contributory negligence
- [322] Section
3(1) of the Contributory Negligence Act, as referred to above, provides for the
apportionment of liability in cases
of contributory negligence. It
provides:
Where any person suffers damage as the result partly of his own fault and
partly of the fault of any other person or persons, a claim
in respect of that
damage shall not be defeated by reason of the fault of the person suffering the
damage, but the damages recoverable
in respect thereof shall be reduced to such
extent as the court thinks just and equitable having regard to the
claimant’s share
in the responsibility for the damage: ...
- [323] “Fault”
is defined to mean “negligence, ... or other act or omission which gives
rise to a liability in tort
...”.135 This has been interpreted
as a failure by the plaintiff
134 Body Corporate 324525 v Stent (No 2), above n 122, at [150].
135 Contributory Negligence Act 1947, s 2.
to take ordinary care to look after itself and its
property.136 The question is whether the
plaintiff acted reasonably in all of the circumstances in safeguarding his or
her own interests.137 The assessment of fault “requires an
objective test but expressed in terms of the person’s own general
characteristics”.138
- [324] The damage
that may be apportioned must be the foreseeable consequence of a lack of care on
the part of the plaintiff and caused
by such lack of care. As stated by the
Court of Appeal in Johnson v Auckland
Council:139
[87] There is no dispute that in making
the apportionment, it is necessary to consider both relative blameworthiness
and causative
potency. The question of the appropriate apportionment is a
question of fact involving matters of impression and not some sort of
“mathematical computation”...
- [325] Given the
nature of the apportionment exercise, comparisons with the figures in other
cases are not particularly helpful.140 As stated in Todd on
Torts, it is sufficient that the plaintiff’s conduct should contribute
to the damage that he or she suffers. It is not essential
that it should
contribute to the event that causes the damage.141 In the context of
a building that is not weathertight, this means the plaintiff is not required to
have contributed to the construction
of the building itself for there to be
contributory negligence.142
- [326] There are
16 units in respect of which the Auckland Council asserts contributory
negligence.143 The Auckland Council says that the second
plaintiff
136 Invercargill City Council v Southland Indoor Leisure Centre
Charitable [2017] NZCA 68, [2017] 2 NZLR 650 at [136]; citing Helson v
McKenzies (Cuba Street) Ltd [1950] NZGazLawRp 70; [1950] NZLR 878 (CA) at 920; Johnson v
Auckland Council [2013] NZHC 165 at [13]; and O’Hagan v Body
Corporate 189855, above n 109, at
[76]–[77].
137 Nautlius, above n 40, at [294].
- O’Hagan
v Body Corporate 189855, above n 109,
at [79]; cited in Lee v Auckland Council [2016] NZHC 2377 at
[67].
139 Johnson v Auckland Council, above n 71 (footnotes omitted).
140 Johnson v Auckland Council, above n 71, at [88].
141 Stephen Todd “Defences” in Stephen Todd (ed)
Todd on Torts (9th ed, Thomson Reuters, Wellington, 2023) at
[20.2.3].
142 Johnson v Auckland Council, above n 136, at [12(a)].
143 The units and their respective owners are set out in Appendix
7 to the Auckland Council’s submissions. This includes J Bodle
101 Ltd (in
liquidation). The plaintiffs’ instructing solicitors, Lane Neave, have
confirmed that they do not have instructions
from the liquidator to advance this
claim. However, the plaintiffs continue to include this unit in their claim and
quantum schedules
appended to their opening submissions. The Auckland Council
says that out of an abundance of caution it has included this unit in
the
assessment but maintains that a claim cannot be advanced without the consent of
the liquidator.
owners of these units fell short of the standard of a reasonable purchaser. The
Auckland Council contends that these second plaintiffs
signed their agreements
for sale and purchase without obtaining and/or reviewing the Body
Corporate’s annual general meetings
(AGM) minutes for the past two to
three years. The Council says that if they had done so, they would have been
placed on alert that
Bianco Off Queen was suffering from defects, or that there
was a risk that it had defects requiring repair and that litigation was
anticipated. This would have allowed them to avoid the purchase or, at the very
least, allowed them to negotiate a suitable reduction
in price.
- [327] On an
alternative basis the Auckland Council contends that if these owners did in fact
obtain the minutes of the Body Corporate
AGM, they knew prior to purchase that
Bianco Off Queen had defects (or risks of defects) requiring repair and that
litigation was
anticipated. Accordingly, the Auckland Council contends that
those second plaintiffs either:
(a) voluntarily assumed the risk that Bianco Off Queen had defects and that
repairs were required;
(b) agreed to buy the unit based on their own judgement of the value of the
abatement of the purchase price for those defects and
associated risks; or
(c) did not safeguard their own interests by avoiding the purchase or seeking a
reduction in the purchase price.
- [328] Expert
evidence was given on behalf of the Auckland Council by Mr Peter Nolan, retired
lawyer, on the contributory negligence
issue. Mr Nolan is a very experienced
property and conveyancing solicitor. I find his evidence to be unassailable; he
is extremely
well qualified and presented his evidence in a professional and
measured fashion. It was substantially helpful, and I adopt his
conclusions.
- [329] Of the 16
second plaintiffs in which the Auckland Council asserts contributory negligence
against, 12 purchased their units
after the 2016 AGM minutes became
available (but prior to the 2017 AGM minutes becoming available) and four
purchased their unit after the date of the 2017 AGM minutes.
The agreements to
purchase these units were not conditional on obtaining Body Corporate minutes,
except for unit 6A’s agreement
which contained a further term (cl 20)
specifically drawing the second plaintiff’s attention to the 2016 AGM
minutes, with
the owner accepting as read all matters contained therein.
However, most of these owners received pre-contract disclosure statements
which
referred to or attached the relevant AGM minutes
- [330] In his
evidence, Mr Nolan provided a detailed review of the 2016 and 2017 AGM minutes.
In respect of the 2016 minutes, Mr Nolan
identified a number of “red
flags” including the fact that the Body Corporate was obtaining a building
condition report
requiring consultant input from multiple disciplines. Mr Nolan
was of the view that the minutes disclosed anticipated litigation.
- [331] Mr Nolan
was also of the view that the following “red flags” were raised in
the 2017 AGM minutes:
(a) Maynard Marks had been engaged and attended the AGM to provide a progress
update on the current building audit;
(b) Maynard Marks was looking at issues with the internal plumbing;
(c) Maynard Marks had identified issues in terms of general claddings e.g.,
corrosions, fixings and poppings;
(d) leaks were identified in the concrete deck;
(e) there were leaks through some glazed atrium rooves;
(f) there was corrosion to some decorative steel; and
(g) there was a need for additional consultants.
- [332] Several
second plaintiffs said that they had not been advised by either their lawyer
(after having reviewed the 2016 AGM minutes)
and/or by the real estate
agent
that there were leaks, issues or defects at Bianco Off Queen. Mr Nolan was
surprised that a lawyer would have come to that decision.
He also noted that a
real estate agent represents the vendor, but if they did have duties to the
purchaser, he would have expected
the agent to elaborate on the whole section on
the building condition report contained in the minutes.
- [333] In
reviewing all this evidence, I conclude that there was a degree of carelessness
by the second named plaintiffs which has
contributed in some way to their loss.
In the circumstances here, I find that the moral blameworthiness can properly be
considered
to be low, particularly in relation to those who purchased their unit
after the date of the 2016 AGM minutes, but before the 2017
AGM minutes.144
In the circumstances, I find that there should be a deduction of the sum
of $7,500 from any award of general damages to those of the
second plaintiffs
who purchased their unit after the 2016 AGM minutes but before the 2017 AGM
minutes. In respect of those second
plaintiffs who purchased after the 2017 AGM
minutes I find that there should be no award of general damages to them. In the
circumstances
and having regard to the broad discretion in s 3(1) of the
Contributory Negligence Act, in particular the just and equitable threshold,
I
conclude that there should be no further deductions. That would be
disproportionate to the level of fault I have identified. It
would also not be
just and equitable in this case to make any further deduction, given the nature
and extent of the loss and the
fact that it falls on the general body of
owners.
GST
- [334] The
parties agree that any award to the Body Corporate should be on a GST exclusive
basis.
- [335] I record
the parties’ agreement that owners that use their units either for
“personal use” or for “residential
tenancy purposes”
cannot receive GST input tax credits in respect of expenditure for their unit.
Neither personal use nor residential
tenancies are taxable activities. However,
given my determination on the standing of
144 I note that the plaintiffs accept as a general proposition
that the failure to obtain Body Corporate minutes may in some circumstances
amount to contributory negligence; O’Hagan v Body Corporate 189855,
above n 109, at [137]. It is also
accepted that some reduction should be made to the claims of the four second
plaintiffs who entered into agreements
to purchase their unit after the 2017 AGM
minutes were available.
the Body Corporate and my conclusion that the cost of repairs damages should be
awarded to it, I apprehend that this is no longer
a live issue.
- [336] GST is not
payable in respect of the general damages that I have awarded
above.145
Affirmative limitation defences
- [337] The
defendants plead that the plaintiffs’ claims are time-barred under s 4 of
the Limitation Act 1950 to the extent that
the alleged defects which are the
subject of those claims were discovered or reasonably discoverable more than six
years from the
date on which the proceedings were commenced. The defendants also
allege that pursuant to s 393(2) of the Building Act 2004, to the extent that
any of the plaintiffs’ claims are based upon acts or omissions which took
place more than ten years before,
these claims are also statute
barred.
- [338] Neither of
these defences were pursued with any vigour by the defendants. Neither of them
addressed limitation issues in their
closing submissions.
- [339] I find
that the plaintiffs’ claims are not time barred. No limitation defence has
been made out.
Apportionment between defendants
- [340] I
accept the submission of the Auckland Council that the appropriate apportionment
of liability between the defendants is 85
per cent for Argon and 15 per cent for
the Auckland Council.
- [341] It cannot
be disputed that Argon had the primary responsibility to ensure that Bianco Off
Queen was constructed without defects
and was compliant with the
145 Grant Pearson, Mark Keating and Craig Macalister Taxation
– GST – A to Z of New Zealand Law (online ed, Thomson Reuters)
at [57.G.36.8.5]: Inland Revenue policy IS3387 expressly details that payments
for general damages do
not constitute taxable supplies. It states: “When a
payment is made under a court award or out of court settlement and it is
consideration for a taxable supply (or an adjustment to a consideration for a
taxable supply) this will be taxable. If the payment
is made for compensation or
damages it is not taxable.” See also Case S77 (1996) 17 NZTC 7,483
(TRA).
relevant sections of the Building Code. The Auckland Council’s role was
secondary to Argon’s primary acts and/or omissions.
- [342] My
conclusion on this issue is consistent with that of Thomas J in Victopia
Apartments,146 and Body Corporate 324371 v Clark Brown
Architects Ltd.147
Other issues
The
non-legally represented plaintiffs
- [343] It follows
from my finding on standing above, that the two non-legally represented second
plaintiffs, Yinling Linda Wu (unit
4E/8 White Street) and Haixin Wang (unit 1A/8
White Street), are not entitled to a separate award of damages for the cost of
repairs.
- [344] These two
plaintiffs are entitled to an award of general damages in accordance with my
findings above.
Former owners/assignees
- [345] There are
six second plaintiffs who have assigned their causes of action.
- [346] At a very
late stage in the proceedings, the plaintiffs sought the following
orders:148
(a) an order substituting the second plaintiff associated with unit 2A2 from
Sarin Enterprises Ltd to Usar Investments Ltd;
(b) an order adding five new parties, being assignees who have purchased a unit
and taken an assignment of the claim from former
owners/second plaintiffs;
146 Body Corporate 346799 v KNZ International Co Ltd, above
n 30, at [168].
147 Body Corporate 324371 v Clark Brown Architects Ltd
[2021] NZHC 2379 at [96].
- See
memorandum of counsel for the plaintiffs seeking receipt of documents into
evidence and addition/substitution of plaintiffs dated
18 June 2023.
(c) a direction that certain documents related to the assignment of claims be
received into evidence; and
(d) leave under r 1.9 of the High Court Rules 2016 to amend Schedules A and E of
the ninth amended statement of claim to add these
new plaintiffs pursuant to
these orders.
- [347] The
plaintiffs contend that the proposed assignee second plaintiffs are entitled to
recover repair costs and consequential losses.
No general damages are claimed
for these proposed plaintiffs.
- [348] The
Auckland Council filed a memorandum (with my leave) subsequent to the hearing
addressing the issue of assignment and addition/substitution
of
plaintiffs.149 Those submissions raise complex issues which the
plaintiffs have not adequately addressed.
- [349] I wish to
hear further argument from the parties on the issue of assignment, should that
be necessary. It may be, in light of
my findings on the standing of the Body
Corporate, that I do not need to determine the assignment issue given that the
repair costs
are recoverable by the Body Corporate.150 Again,
however, I require further analysis of that issue before reaching a
conclusion.
- [350] The Court
apprehends that the dollar value at issue in relation to the assignment issue is
not significant. If the parties cannot
resolve the issue, I reserve leave for
the parties to address this issue further.
Result
- [351] I
enter judgment for the plaintiffs against the first defendant, Argon
Construction Ltd, on liability in respect of the first
cause of action
(negligence).
- [352] I enter
judgment for the plaintiffs against the second defendant, the Auckland Council,
on liability in respect of the second
cause of action (negligence).
149 Second defendant’s submissions in response to the
plaintiffs’ application seeking receipt of documents into evidence in
addition/substitution of plaintiffs dated 26 June 2023.
150 The Auckland Council submitted that if I decide that the claim
is in the hands of owners (i.e. it is the unit owners who can recover
losses for
breach of duties owed by the Council to them) there will need to be an analysis
of the relevant unit ownership interests.
- [353] The two
defendants are jointly and severally liable for damages. Those damages are to be
calculated as follows:
(a) based on the factual findings already made in this judgment; and
(b) upon receipt of further submissions (if necessary) from the parties
addressing the quantification of such damages based on the
starting point of Mr
Brock’s estimate, based on Mr Alexander’s scope of repairs.
- [354] Liability
is apportioned 85 per cent to the first defendant, Argon, and 15 per cent to the
second defendant, the Auckland Council.
- [355] I order
that the defendants are to pay to the respective second plaintiffs general
damages calculated in accordance with the
determinations made at [294] above,
with adjustments made as required based on my determination on the contributory
negligence issue
at [333]. Leave is
reserved to apply for further directions and final orders as to the
quantification of general damages and the named individual
second plaintiffs to
whom those awards are to be made.151
- [356] I order
that the first defendant, Argon, is to pay damages in the sum of $111,628 to the
first plaintiff for the acoustic matting.
- [357] I dismiss
the plaintiffs’ claims for consequential losses relating to alternative
accommodation, loss of rent and moving
and storage costs, except to the limited
extent allowed for in the calculation process referred to in [278] and [287]
above.
- [358] Costs are
reserved. The parties are to confer and to propose a timetable for the
determination of costs. A memorandum is to
be filed and served within 21
days.
Andrew J
- This
is a matter I expect the parties to be able to reach agreement on without the
need for further court involvement.
APPENDIX ‘A’
APPENDIX ‘B’
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2023/3034.html