You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2024 >>
[2024] NZHC 1280
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Body Corporate 172108 v Meader [2024] NZHC 1280 (23 May 2024)
Last Updated: 13 June 2024
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE
|
|
CIV-2009-404-6868
|
BETWEEN
|
BODY CORPORATE 172108
Applicant
|
AND
|
MEADER & ORS
(MANCHESTER SECURITIES LIMITED) 37TH RESPONDENT
|
|
CIV-2019-404-1445
|
BETWEEN
|
BODY CORPORATE 172108
Applicant
|
AND
|
MANCHESTER SECURITIES LIMITED
Respondent
|
Hearing:
|
14-18 November 2022
|
Appearances:
Further submissions completed:
|
J B Orpin-Dowell and T J G Allan for Applicant
K C Francis and T P Westaway for 37th Respondent (Manchester Securities Ltd
(in liquidation))
J D Haig for 43rd Respondent (Sage Securities Ltd)
13 December 2022
|
Judgment:
|
23 May 2024
|
JUDGMENT (No.4) OF POWELL J
This judgment was delivered by me on
23 May 2024 at 4.00 pm.
Pursuant to R 11.5 of the High Court Rules.
.......................
Registrar/Deputy Registrar
Solicitors:
Grove Darlow & Partners, Auckland Lindsay Francis, Auckland
Paul Cheng & Co, Wellington
Counsel:
J Orpin-Dowell, Wellington J D Haig, Wellington
BODY CORPORATE 172108 v MEADER & ORS [2024] NZHC 1280 [23 May 2024]
Introduction
[1]
Relevant background [13]
The approval of the initial
scheme [17]
The remediation commences [23]
The variation [25]
Manchester changes approach
[36]
The cross applications
[47]
The applications
in issue [48]
The position of the Body Corporate
[50]
The position of Manchester [51]
The position of Sage [57]
What was the original effect of the
scheme? [61]
The Fogarty variation judgment
[67]
Did the variation remove the 11.88 per
cent cap? [71]
Is any further variation required?
[95]
Is a declaration required? [122]
Conclusion — cross applications
[127]
The arbitration appeal
[128]
Legal principles – issue estoppel and
abuse of process [134]
Discussion – The
arbitration appeal [141]
Decision [147]
Introduction
- [1] This
judgment is the latest instalment in a protracted and complex dispute over
remediation, carried out and underway, at Hobson
Apartments, a 12-storey
apartment block located on Hobson Street in Auckland (“the
building”).
- [2] The
remediation has been undertaken pursuant to a court approved scheme of
remediation (“the scheme”) under the Unit
Titles Act 1972
(“the 1972 Act”). The scheme was first sanctioned by this Court on
31 August 2010 (“the initial
scheme”)1 and subsequently
varied on 3 March 2017 (“the variation”)2 after the
building was discovered to have serious weather tightness issues requiring
remediation.
- [3] The
principal protagonists are the applicant Body Corporate 172108 (“the Body
Corporate”), which has been responsible
for completing remediation to
levels 1–11 of the building, and the 37th respondent Manchester Securities
Ltd (in liquidation)
(“Manchester”), the owner of level
12.3
- [4] This
judgment ostensibly addresses two issues:
(a) cross applications by the Body Corporate and Manchester seeking declarations
as to the effect of the cost allocation provisions
in the scheme or, in the
alternative, variations to the scheme to reflect their respective contentions as
to the appropriate effect
of the scheme (“the cross applications”);
and
(b) an appeal by the Body Corporate against a preliminary determination by an
arbitrator, Brian Keene KC,4 that he had jurisdiction to proceed
- Body
Corporate 172108 v Meader (Nos 2 & 3) [2010] NZHC 1647; (2010) 12 NZCPR 181 (HC) [Heath
judgment No 2] and [Heath judgment No 3].
- Body
Corporate 172108 v Manchester Securities Ltd [2017] NZHC 329 [Fogarty
variation judgment].
- It
is noted that works undertaken by Manchester on level 12 have resulted in the
addition of a small 13th floor. The evidence established
there are now three
apartments in total under construction on levels 12 and 13. As collectively all
three apartments come under the
same title held by Manchester, all references to
Manchester’s private property on level 12 include the new construction at
level 13 unless the context specifically requires
otherwise.
4 Partial Award on Arbitrator’s
Jurisdiction dated 25 October 2018 [Keene Award].
with an arbitration to interpret the effect of cl 10.3 of the scheme (“the
arbitration appeal”).
- [5] The present
issues are symptoms of a much broader dispute between the parties. They have
arisen because, despite the fact the
scheme has been in place for nearly 14
years, Manchester, as the trustee of the Manchester Securities Trading Trust
(“MSTT”)
between 1997–2019 and acting for the most part under
the direction of its sole director and current trustee of MSST, Robert
Cummins,
has signally failed to complete remediation of level 12, and the evidence
confirms level 12 is still not weathertight. Neither
Manchester, which (having
been placed in liquidation by the Body Corporate for failure to pay amounts
owing) now claims it cannot
complete the remediation of level 12, nor Mr Cummins
have the resources to carry out further work on level 12. This is because the
primary funder of the level 12 work to date, the 43rd respondent Sage Securities
Ltd (“Sage”), is no longer prepared,
or does not have the resources,
to advance further monies to complete the remediation of level 12.
- [6] As a result,
Manchester, supported by Sage, and notwithstanding numerous judgments of the
senior courts and the terms of the scheme,
seeks financial contribution from the
Body Corporate and the other owners of the building to complete the remediation
of its unit
property on level 12, and, ultimately, to recover significant
amounts of the monies it has expended on level 12 to date.
- [7] Counsel for
both Manchester and Sage, while not conceding full causal responsibility on
behalf of their clients, acknowledge the
attempted remediation and concomitant
redevelopment of level 12 by Manchester has been a disaster. This position is
also accepted
by Mr Cummins who stated in evidence he now bitterly regrets
taking on the remediation. The issue has not been resourcing. There
is no
dispute that Manchester has received more than adequate funding to complete the
remediation of level 12,5 having according to Mr Cummins so far spent
nearly $9
- The
evidence showed to date Manchester had received some $2 million in settlement
from Auckland City in respect of the weathertightness
issues and has borrowed
close to $11 million from Sage. In addition, it is not in dispute that
Manchester has not paid the Body Corporate
approximately $1.5 million owing in
levies and Court judgments over the same period.
million (exclusive of GST) on level 12 as at March 2022,6 and has
throughout been in receipt of plentiful expert advice.
- [8] There is,
however, little to show for the monies Manchester has spent. Until recently
there appears to have been little in the
way of a clear plan, little in the way
of reports justifying the work undertaken and, it appears, only limited records
of what has
actually been done at any given time or indeed the detail of repairs
that have had to be redone or repeated.
- [9] By the date
of the present hearing, Manchester was in liquidation and, according to Mr
Cummins, at least $1.6 million was still
required simply to make level 12
weathertight and to obtain a code compliance certificate so it could be sold.
Moreover, Manchester’s
principal funder Sage was either no longer able nor
willing to provide further funding to complete the remediation.
- [10] The
responsibility for what has taken place and the future to complete the
remediation of level 12 must rest largely with Mr
Cummins. As the sole director
of Manchester,7 it was his decision to oppose the Body Corporate
carrying out the remediation work on level 12,8 and subsequently
taking a “dilatory and prevaricating” approach to the remediation of
level 12,9 notwithstanding it had required a change in the scheme
initially proposed by Heath J so it could complete the remediation of level
12
prior to the Body Corporate undertaking its repairs to levels 1-11.10
There is also no doubt Manchester’s behaviour was substantively
enabled by the failure of Sage to impose any discipline on Mr
Cummins and
Manchester in the way the monies it advanced have been expended. Although Sage
claims to have been in a normal commercial
relationship with Manchester
(“strictly lender/borrower”) and has a long standing business
relationship with Mr Cummins,
it is clear that the support Sage has
- By
Mr Cummins figures as at 31 March 2022, the total amount expended by Manchester
on level 12 was $8,788,632.94 (exclusive of GST)
consisting of
remediation/repairs of $6,588,593.63, “betterment” of $1,974,914.42
and “wasted expenditure”
of
$225,124.89.
7 See above at [5].
8 See below at [15], [20], [21] and [23].
- Fogarty
variation judgment, above n 2, at [147]; and Manchester Securities Ltd v
Body Corporate 172108 [2017] NZCA 527, (2017) NZCPR 65 [variation appeal
judgment] at [44]; and Manchester Securities Limited v Body Corporate
172108 [2019] NZCA 408 at [39]; Cummins v Body Corporate 172108
[2022] NZCA 68 at [69]; and Cummins v Body Corporate 172108 [2022]
NZHC 774 at [127].
10 Heath judgment No.2, at [6];
and see below at [21]-[22].
provided to Manchester has far exceeded any rational limits, as has its failure
to enforce its mortgage security over level 12 in
a timely manner, with the
result that Sage’s only hope to recover any of the monies advanced to
Manchester is through supporting
Manchester’s claims for contribution
against the Body Corporate and the other owners of the building.
- [11] The abject
failure of Manchester to complete the remediation of level 12, aided and abetted
by Sage, stands in stark contrast
to the actions of the Body Corporate. The Body
Corporate, having settled its own litigation with Auckland Council, completed
the
remediation of levels 1–11 by December 2013. Having completed
remediation of the rest of the building, the Body Corporate’s
focus since
then has been to pursue Manchester for Manchester’s contribution to the
remediation of the common property on levels
1–11 and has consistently
opposed any attempt by Manchester to pass on the costs of Manchester’s
remediation of its unit
property on level 12.
- [12] I apologise
to the parties for the delay in producing this judgment. The delay was the
result of a number of factors. Overall
though there has been insufficient time
to complete the judgment at any earlier point prior to its release.
Relevant background
- [13] Manchester
purchased level 12 in May 2006 and has remained the legal owner of level 12
since that date. It purchased level 12
from Philip McGaveston, the director of
Sage. There is no dispute that level 12 is the largest unit in the building and,
at the time
it was acquired by Manchester, was the most valuable. This is
reflected in its unit entitlement of 11.88 per cent of the building
as a whole.
Level 12 had been constructed separately to the rest of the building and as a
result had a different appearance. Unusually,
but apparently deliberately,
Manchester’s unit property on level 12 includes the external walls and the
roof, with only a limited
number of small discrete areas of common property
being located on level 12. Ownership of the roof gave Manchester rights to a
further
35 metres of airspace above the existing building, giving Manchester the
option to develop the building through the potential addition
of further
floors.
- [14] At the time
Manchester purchased level 12 from Mr McGaveston, there had already been a
history of leaks reported to the three
apartments on level 11, notwithstanding
the application of a liquid polyurethane waterproof membrane over the decks and
fittings
on level 12; and a range of remedial work to level 12, albeit
relatively minor, had been proposed.
- [15] It was
ultimately recognised that the building as a whole had suffered significant
damage as a result of severe water ingress
issues. As a result, considerable
remediation was required. Attempts by the Body Corporate to repair the common
property as well
as the roof and exterior walls of level 12 pursuant to amended
rules adopted by the Body Corporate in 1996 were opposed by Manchester.
These
amended rules had varied the default rules contained in sch 2 of the 1972 Act by
requiring the Body Corporate to maintain the
exterior of the building.
Manchester argued that the amended rules were ultra vires the 1972 Act and that
the Body Corporate had
no right to undertake repairs to Manchester’s unit
property: the exterior walls and roof on level 12.
- [16] Manchester’s
position was eventually accepted by the Body Corporate. As a result, in 2009 the
Body Corporate applied to
the High Court under s 48 of the 1972 Act for approval
of a scheme of remediation, to empower it to carry out the necessary repairs
to
both unit and common property in the building, including level 12.
The
approval of the initial scheme
- [17] The Body
Corporate’s application was opposed by Manchester. Manchester’s
objections were subsequently summarised
by Heath J in the following terms in the
course of his Honour’s interim judgment approving the
scheme:11
...
(a) [Manchester] does not consider that the Body Corporate should have any
decision-making role in respect of remediation to Unit
12A;
(b) remedial works have not been defined in sufficient detail and too broad a
discretion is conferred upon the Body Corporate in
relation to management of the
proposed construction work; and
11 Body Corporate 172108 v Meader [2010] NZHC 187; (2010) 12 NZCPR 101 (HC)
(“Heath judgment No.1”), at [4].
(c) a more equitable apportionment of cost is required. [Manchester] considers
that the work to be undertaken on its own property
is “relatively
minor”, as opposed to “the major re-cladding work apparently
required on the remainder of the building”.
- [18] As Mr
Cummins explained at the time in his evidence in opposition:
[Manchester] intends to carry out significant alterations to level 12 in the
foreseeable future. Level 12 has 35 metres of air space
rights around and above
the Building and essentially owns the roof. I have investigated various
development options for the property
to take advantage of these rights, such as
expanding [Manchester’s] property by creating a second storey or creating
a self
contained apartment. CoveKinloch has prepared concept plans for such a
development for [Manchester]. Inevitably any development of
this type would
result in substantial changes to the roof area, quite apart from other
structural considerations. The consent of
the [the Council] would be required
and significant cost would be involved.
Until these options are evaluated, I believe only remedial work that is
necessary to keep the Building watertight should be undertaken
on level 12.
- [19] In opposing
the scheme Mr Cummins noted:
[Manchester] recognises that it is obliged under the Unit Titles Act 1972
(see the default Body Corporate rules in Schedule 2, particularly
Rule 1(e)) to
repair and maintain its unit property on level 12 in sufficiently good condition
such that no damage or harm shall
ensue to the common property or any other unit
in the Building. There should be no suggestion that [Manchester] is not willing
to
meet its obligations in this respect. To date [Manchester] has carried out
all interim work recommended by CoveKinloch and has done
so in a timely
manner.
- [20] As a result
of this opposition, Heath J declined to give approval for the scheme proposal by
the Body Corporate. Instead, in
his Honour’s first judgment, Heath J
identified a number of principles that provided that the repairs to levels
1–11
would be undertaken by the Body Corporate, while the repairs to level
12, whether in respect of its unit or common property, would
be carried out by
Manchester.12 At that point in the proceedings, his Honour envisaged
a single contractor would undertake all of the necessary work to ensure the
building was remediated at the same time.13 While Manchester’s
total contribution was capped at 11.88 per cent, consistent with its unit
entitlement, on the information
available his Honour envisaged that
approximately a third of Manchester’s contribution would go towards the
repairs to common
property
12 Heath judgment No 1, above n 13, at [31].
13 At [30]–[33].
on levels 1–11.14 Specifically, on the information available at
that time, Heath J understood that the total cost of repairs to levels
1–11 was
estimated to be around
$5,750,00015 and the cost of repairs to level 12 around
$500,000, a total of
$6,250,000.16 As Manchester’s share was 11.88 per cent, this
would see Manchester contributing approximately $242,500 to the cost of repairs
to common property on levels 1–11 in addition to completing the repairs to
level 12.17
- [21] Following
receipt of a further draft scheme from the parties, in the course of two further
judgments Heath J finalised the scheme.18 A single contractor was not
ultimately possible due to the fact that the Body Corporate had not completed
its litigation against the
Auckland Council and needed to delay the commencement
of its own works, while Manchester gave notice it wished to undertake the
immediate
remediation of level 12 immediately.
- [22] The scheme
finally approved by Heath J enabled Manchester to proceed with the remediation
of level 12, with Manchester responsible
for repairing both its own unit and the
common property on level 12. It is not in dispute that in undertaking this work
Manchester’s
costs were to be capped at 11.88 per cent of the total costs
of the remediation, reflecting Manchester’s unit entitlement of
ownership
in the building.
The
remediation commences
- [23] Manchester
did not, in fact, proceed with the remediation as envisaged by Heath J. Instead,
it was the Body Corporate, having
settled with Auckland Council, that commenced
work first, in July 2012. The repairs to levels 1–11 were completed in
December
2013. The total cost of the repairs was $8,131,002.55 (including GST
and fees) of which 61 per cent or $4,320,266.00 (excluding GST)
was attributed
to the repair of the common property.19
14 At [49].
15 It is unclear whether this sum included the cost of repairs to
private property on levels 1–11.
16 At [47].
17 At [47]–[49].
18 Heath judgment No 2 and Heath judgment No 3,
above n 1.
19 Fogarty variation judgment, above n 2, at
[80]–[81].
- [24] During that
same period, Manchester found that the costs of remediating level 12 were
considerably greater than it had first
estimated. As a result, Manchester
concluded that its 11.88 per cent contribution would not even cover the costs of
its own repairs
to level 12. From 2012, it has therefore refused to pay any
contribution whatsoever towards the amounts incurred by the Body Corporate
to
remediate levels 1–11, or indeed any other levies raised by the Body
Corporate since then. Manchester took the position
that rather than contributing
to the costs of common property repairs on level 1-11, it was the other owners
who would be required
to top up Manchester for the cost of the repairs to level
12.
The variation
- [25] The Body
Corporate responded by applying for a variation of the scheme. Manchester sought
to strike out the application on the
basis the Court had no jurisdiction to vary
the scheme following the repeal of the 1972 Act by the Unit Titles Act
2010
(“the 2010 Act”), submitting that any changes would require an
entirely new remediation scheme under the 2010 Act.20
Manchester’s argument was however rejected by Katz J who concluded
pursuant to s 277 of the 2010 Act that the Body Corporate
retained an ability to
apply to this Court to vary the remediation scheme pursuant to s 48 of the 1972
Act.21
- [26] By the time
the Body Corporate’s variation application was heard by Fogarty J in
August 2016, Manchester’s experts
estimated the total amount required to
complete remediation of level 12 was $2,303,231 (plus GST) comprising the actual
costs incurred
to that point and the estimated costs required to complete the
project,22 the costs having more than quadrupled since the estimate
provided to Heath J in 2010.23
- [27] Concluding
that a variation to the scheme was required, Fogarty J noted that the original
scheme approved by Heath J appeared
to be inconsistent “with the statutory
policy of demarcating common costs from unit costs (enshrined in ss 9
and
- Body
Corporate 172108 v Manchester Securities Ltd [2013] NZHC 2441, (2013) 14
NZCPR 745 at [2].
21 At [25].
22 Fogarty variation judgment, above n 2, at [82].
23 At [148].
15).”24 His Honour noted that the law had developed since the
scheme was originally approved, with particular reference to the decision of
the
Court of Appeal in Tisch v Body Corporate 318596,25 which
Fogarty J considered he was required to follow.26
- [28] Even more
fundamentally, Fogarty J concluded:
- [67] Furthermore,
independently of the reasoning in Tisch, the blowout in costs, which was
unforeseeable at the time, has rendered the logic of the High Court, Heath J,
inapplicable, in my
opinion, to a just response to the present problem. Mr Allan
is right that it cannot possibly be the case that Manchester should
avoid making
its contribution to the repair of the common property, most of which is on
levels 1 to 11 and only a small amount on
level 12, because of its unit repair
costs, almost all not being common property remediation.
- [68] Mr Harris
is right, that at the time the scheme was approved the costs were treated as
indications only available at the time.
But, it is the degree of magnitude of
the variance in the costs which drives the merit of Mr Allan’s
argument.
- [69] Another way
of looking at the facts is that, had the parties known what they know now, that
Manchester was going to do the work
last, and that the sheer scale of the
expenditure in level 12 was way off the scale contemplated, then the scheme
which Manchester
is now trying to hold on to would not have been approved by the
High Court. I am in no doubt that justice requires this Court to
amend the
scheme to reflect the present circumstances, and to return to the scheme of the
Act.
- [29] Rejecting
an argument on behalf of Manchester that arbitration was the more appropriate
forum in accordance with the dispute
resolution provisions in the scheme,
Fogarty J ordered that:27
Manchester shall pay the cost
of repairs of common property to all levels calculated in accordance with the
units entitlement (now
known as ownership interest) of Manchester’s
unit.
- [30] As Fogarty
J then explained, “the effect of that order is [to] set aside the limit of
11.88 per cent and to reinstate the
policy of the
Act.”28
- [31] In addition
to removing the cap on Manchester’s total contribution to the repairs to
the building, Fogarty J also ordered
Manchester to make an interim
payment
24 At [30].
25 Tisch v Body Corporate 318596 [2011] NZCA 420, [2011] 3
NZLR 679.
26 Fogarty variation judgment, above n 2, at [66].
27 At [156].
28 At [157].
in the sum of $321,264.79 (plus GST).29 This was calculated by
identifying Manchester’s contribution to the cost of repairs to the common
property on levels 1–11
based on unit entitlement ($513,247.60 excluding
GST)30 less the contribution of the other owners to the estimated
cost of repairs to the common property on level 12 ($191,982)31, a
total of $321,264.79 (excluding GST). This sum was “to be adjusted upon
completion of remediation of the common property
on level 12, to the extent that
the [estimate relied upon] varies [from the actual cost].”32
Justice Fogarty commented that the judgment sum would be “a minimum
cost that Manchester will have to pay in contribution to
the remedial works of
common property on level 12”.33
- [32] Manchester
appealed. Upholding the variation, the Court of Appeal noted the effect of the
variation adopted by Fogarty J:34
[51] ...was to reinstate the default statutory scheme regarding cost
allocation, thereby rendering unit owners liable to contribute
to the
remediation of common property on the basis of their unit entitlement.
- [33] The Court
likewise accepted that Fogarty J was correct to vary the scheme:
- [40] ...As
Fogarty J recognised, what marks this case out is not the fact of costs
increases which would have been anticipated but
the sheer magnitude of those
increases as compared with those contemplated by the author of the scheme. That
is the correct “counterfactual”.
On anyone’s view of it, a 430
per cent increase is a radical change of circumstances. As Fogarty J put it, the
actual expenditure
and the ongoing expenditure is “simply in another scale
from that presented to the High Court back in 2010”.
- [41] Further, as
Fogarty J also recognised, it was undeniably part of the logic of the scheme
that Manchester would benefit from the
common property repairs to levels 1-11
and therefore should make some contribution to the cost of those repairs. That
was the whole
purpose of the formula. We are confident Heath J would never have
sanctioned a scheme whereby Manchester paid nothing for that benefit
but instead
received a windfall at the expense of the other unit holders.
(footnotes omitted)
29 At [157].
30 Being 11.88 per cent of $4,320,266 (excluding GST).
31 Being the then estimated cost of repairs to the common property
on level 12 ($217,865.20) less Manchester’s contribution of
11.88 per
cent. It is noted that the estimated cost of repairs was the higher of the
estimates provided by the experts instructed
by both the Body Corporate and
Manchester of the costs of repairs to common property on level 12 if undertaken
promptly. See Fogarty variation judgment, above n 2, at
[150]–[155].
32 At [155].
33 At [153].
34 Variation appeal judgment, above n 10.
- [34] Finally,
the Court of Appeal upheld the interim payment ordered by Fogarty
J.35
- [35] Manchester’s
subsequent application for leave to appeal to the Supreme Court was
dismissed.36
Manchester
changes approach
- [36] Notwithstanding
the ostensible removal of the cap on Manchester’s liability and its
unsuccessful challenge to the variation
on appeal, Manchester, in what can only
be described as being in a studied and deliberate way, has nonetheless refused
to make any
payment to the Body Corporate as ordered.
- [37] Instead,
within eight days of the dismissal of Manchester’s final appeal against
the variation, Manchester fundamentally
changed its approach and commenced
arguing that notwithstanding the variation, and as a result of cls 10.3 and 21.3
of the scheme,
Manchester was still only required to contribute a maximum of
11.88 per cent of the total cost of repairs to common property and
the unit
property on level 12. Manchester’s initial focus was on the cost of the
roof replacement foreshadowed in the Fogarty variation judgment.
Manchester argued that it was only required to pay
11.88 per cent of the cost of replacing the roof, with the balance to be paid by
the other owners of the building in accordance with
their respective unit
entitlement. At the same time, it was signalled that it was likely that
Manchester would adopt a similar approach
to the remediation of the external
walls which were also part of Manchester’s unit property on level 12.
Manchester requested
that the Body Corporate “accepts Manchester’s
apportionment approach for the roof or, if not, that the Body Corporate
will
promptly appoint an arbitrator to solve the matter.”
- [38] As the Body
Corporate refused to do so, Manchester initiated the arbitration with Mr Keene.
In its notice pursuant to art 1(4)
of sch 2 of the Arbitration Act 1996,
Manchester advised that the dispute between the parties was:
Does clause 10.3 apply to apportion the cost of repair of the unit property
[at] level 12 among all owners by unit entitlement, or
has the High Court
and/or
35 At [69].
36 Manchester Securities Ltd v Body Corporate 172108 [2018]
NZSC 19.
the Court of Appeal determined that Manchester alone must pay the cost of
repair of unit property at level 12? (“the Dispute”)
- [39] Manchester
explained:
...the variation decision did not determine the allocation of unit property
repair costs (at any level of the building) or that Manchester
is to be solely
responsible for the cost of repairs to the unit property at level 12.
- [40] The Body
Corporate objected, but Mr Keene dismissed the Body Corporate’s protest to
jurisdiction.37 The Body Corporate filed the arbitration appeal.
Although Manchester subsequently applied to strike out part of the arbitration
appeal,
the arbitration was effectively put on hold in December 2018, when
Jagose J issued interim orders prohibiting the parties’
continued
participation in the arbitration pending further order of the
Court.38
- [41] The
cross-applications also followed the issue of the Keene Award as both
parties sought to clarify the effect of the scheme as varied, and to vary the
scheme if it was found it did not have the effect
contended for.
- [42] In the
meantime, Manchester continued to refuse to pay the judgment sum and the Body
Corporate responded by seeking to wind up
Manchester. Manchester repeatedly
challenged the liquidation proceedings, primarily on the basis that it had
counterclaims or set-offs
against the amounts claimed by the Body Corporate
notwithstanding that these had never been formally notified.39 It was
unsuccessful in its opposition and Manchester was placed into liquidation on 11
March 2020.40
- [43] Immediately
prior to the liquidation, Mr Cummins appointed himself to replace Manchester as
the trustee of the MSTT. Further
litigation ensued when Mr Cummins then sought
to be joined to the present proceedings in place of or in addition to
Manchester, while
at the same time attempting to ensure he did not have to pay
the amounts still outstanding from Manchester to the Body Corporate.
Mr
Cummins’s
37 Keene Award, above n 4, at [12.1].
38 Body Corporate 172108 v Meader [2018] NZHC 3356 at
[22].
39 Body Corporate 172108 v Manchester Securities Ltd [2018]
NZHC 3307; Manchester Securities Ltd v Body Corporate 172108, above n 12;
and Body Corporate 172108 v Manchester Securities Ltd [2020] NZHC 198;
and Cummins v Body Corporate 172108 [2021] NZCA 145, [2021] 3 NZLR
17.
40 Body Corporate 172108 v Manchester Securities Ltd [2020]
NZHC 198 at [43].
pursuit of this course of action ultimately substantially delayed the hearing of
the present proceedings.41
- [44] When
Manchester entered liquidation, it ceased work on level 12. Mr Cummins, in his
capacity as trustee of the MSTT, continued
with the works until funding from
Sage ceased in 2022. While Sage has taken no steps at any point to enforce its
security, a company
controlled by Mr Cummins, Flat Bush Finance Ltd (“Flat
Bush”) has purported to enter into possession of level 12 as a
mortgagee,
and yet more litigation resulted when Flat Bush unsuccessfully attempted to
remove a caveat lodged by the Body Corporate
over the level 12
title.42
- [45] With
Manchester remaining the legal owner of level 12, the entry into possession of
level 12 by Flat Bush and Mr Cummins self-appointment
as trustee of the MSTT, as
foreshadowed in recent cases it is difficult to know where any counterclaims or
set-offs originally
claimed by Manchester may now reside.43 Mr
Cummins, with the apparent support of Sage and the liquidators of Manchester,
calculates that based on Manchester being liable
only for 11.88 per cent of the
total cost of repairs to date to this point the net amount payable by other
owners of the building
to the MSTT (after deductions for
“betterment” and “wasted expenditure and a still to be
quantified figure for
“dilatory remediation” by Manchester)
is
$5,084,418.64 as at 31 March 2022, plus interest. It would follow that those
same owners would also have to pay 88.12 per cent of
the estimated $1.6 million
required to complete the remediation of level 12.
- [46] In the
meantime, level 12 remains not only not weathertight, but a conspicuous eyesore,
covered in plastic wrapping on the top
of the building. It is against this
background that the cross applications and arbitration appeal stand to be
considered.
41 Body Corporate 172108 v Manchester Securities Ltd
[2021] NZHC 365; Body Corporate 172108 v Manchester Securities Ltd
[2021] NZHC 686; Cummins v Body Corporate 172108 [2022] NZCA 68;
Cummins v Body Corporate 172108 [2022] NZCA 153; and Cummins v Body
Corporate 172108 [2022] NZSC 95.
42 Body Corporate 172108 v Flat Bush Finance Ltd [2020]
NZHC 3135, (2020) 21 NZCPR 622.
43 Cummins v Body Corporate 172108, above n 43, at
[69].
The cross applications
- [47] I
commence my analysis by considering the cross applications, as my conclusions on
those applications and, in particular, the
effect of the scheme bear heavily on
my analysis of the arbitration appeal.
The
applications in issue
- [48] Throughout
the hearing both parties referred to the applications in issue as the variation
applications. Although, like the variation
determined by Fogarty J, both are
made pursuant to s 48(6) of the 1972 Act which permits a Court to “from
time to time cancel,
vary, modify, or discharge any order made by it under this
section”, the primary relief sought by both the Body Corporate and
Manchester was, as noted, declarations as to the effect of the scheme. In both
cases, a variation of the scheme is not the primary
relief sought. In
particular, by way of its amended interlocutory application dated 3 April 2019,
the Body Corporate seeks:
(a) declaratory relief that Manchester is estopped from seeking to apportion the
costs of repairing its unit property on level 12
between it and the other unit
holders under cls 10.3 and 21.2 of the scheme as it says to do so is a
collateral attack on the variation
decision; or
(b) in the alternative, a series of interlocking alternative variations to the
scheme that would restrict Manchester’s ability
to claim contributions
from the Body Corporate or other owners of the building towards the cost of
repairs to level 12.
- [49] Manchester
and Sage oppose the Body Corporate’s application and by way of
Manchester’s cross application seek either
a declaration or (if required)
a variation to the scheme to the effect that the total cost of building repairs
is apportioned between
all unit owners according to unit entitlement subject
only to Manchester being responsible for any additional costs arising from
Manchester’s dilatory
remediation.
The
position of the Body Corporate
- [50] The Body
Corporate’s position is based on its understanding of the effect of the
2017 variation as it has been explained
in both the Fogarty variation
judgment and the variation appeal judgment. The Body Corporate
submits that those judgments, implemented by the variation, without question
removed the 11.88 per cent cap on
Manchester’s liability imposed by Heath
J when his Honour set up the scheme. As a result, it submitted that any attempt
by
Manchester to argue that the cap remains in place by virtue of cls 10.3 and
21.2 of the scheme, by way of arbitration or otherwise
in this Court, is an
abuse of process and/or a collateral attack on those earlier
decisions.
The
position of Manchester
- [51] Manchester
contends the position is not so clear cut. Overall, and as asserted in the
arbitration, it is Manchester’s submissions
that notwithstanding the
Fogarty variation judgment and the variation appeal judgment an
effective 11.88 per cent cap remains on Manchester’s contribution to the
total cost of repairs to the building.44 If Manchester’s
interpretation is correct it would result in the type of outcome contended for
by Mr Cummins.45 To interpret the scheme in this way, notwithstanding
the Fogarty variation judgment and variation appeal judgment,
Manchester relies on cl
10.3 of the scheme which provides:
...where repairs involve both Units and Common Property, the Costs of such
Repairs shall to the extent possible be apportioned to
each Owner on the basis
of that owner’s legal title to part of the Building.
- [52] In
Manchester’s submission no issue estoppel can arise because the effect of
cl
10.3 was never clearly determined. On the contrary there has been no final
determination of the apportionment of costs of repairs
to Manchester’s
unit property on level 12 between it and other unit holders with regard to cls
10.3 and 21.2. On
44 This is according to Mr Cummins’s calculation which
calculates Manchester’s liability based on the 11.88 per cent of the
total
costs repairs to the building. His calculation of the cost of repairs to level
1-11 was $7,070,437.00 (exclusive of GST) less
a sum described as “per
Doogue J” of
$997,625.00 which is not explained, nor apparent from the one judgment of
Associate Judge JP Doogue issued in connection with the
proceeding. It is noted
that for its part the Body Corporate has only sought an 11.88 per cent
contribution from Manchester to the
repairs of the common property on levels
1-11 (11.88 per cent of $4,320,266 (excluding GST) which as noted at [23] above
was 61 per
cent of the total cost of the repairs to levels 1-11). See Fogarty
variation judgment, above n 2, at [81] and [102], and the variation
appeal
judgment above n 10, at [24].
45 See [45] above.
behalf of Manchester, Mr Francis disputed that the Fogarty variation judgment
had determined that Manchester has to contribute the costs of remediation of
common property in accordance with its unit entitlement
while having to pay for
remediation to its own level 12 unit. In Mr Francis’ submission, nowhere
in either the Fogarty variation judgment or the variation appeal
judgment does either the High Court or the Court of Appeal state that
Manchester alone is responsible for all costs in relation to its unit
property.
- [53] It should
be noted that while there appears to be no dispute as to Manchester’s
position on the effect of the variation,
given it is what it has asserted in its
cross application and it is also entirely consistent with its assertion in the
notice initiating
the arbitration, Mr Francis was demonstrably reluctant to
advance this argument before me, or even to acknowledge that this was
Manchester’s
position. Instead, it appeared to be Manchester’s
primary position at the hearing was that the appropriate outcome would be
to let
the issue of interpretation of both cls 10.3 and 21.2 be determined by
arbitration. It therefore appears that Manchester’s
cross application
actually represents a fallback position in the event the arbitration is not
permitted to proceed and the criteria
for a further variation of the scheme is
met.
- [54] Given that
position, it is not surprising that Manchester submits that the restrictions on
arbitration sought by the Body Corporate
are unnecessary given it had already
undertaken not to refer any dispute to arbitration “until the level 12
repair work...is
complete (except for the clause 10.3 already referred to Mr
Keene QC)”.46 Instead, Manchester argues that the Body
Corporate’s attempt to use the variation to stop the arbitration is itself
an abuse
of process.
- [55] Manchester’s
primary position is, therefore, that as the effect of cl 10.3 has never been
determined, arbitration is the
appropriate forum given the wording of the
dispute resolution provisions contended in cl 13 of the scheme.
- [56] Likewise,
and consistent with Manchester’s overall submissions as to the present
effect of the scheme, Manchester’s
proposed variation seeks the
explicit
- An
undertaking given by Manchester in the course of the hearing before Jagose J and
reasserted before me. See Body Corporate 172108, above n 42, at
[13].
reimposition of an 11.88 per cent cap in Manchester’s liability on the
grounds that the variation removed the cap and was unfair
to Manchester. Instead
Manchester submitted it is appropriate for the other owners in the building to
contribute to the costs of
remediating Manchester’s property on level 12
as well as the common property throughout the building because they all benefit
from that work taking place.
The position
of Sage
- [57] Although
Sage also seeks a reimposition of an 11.88 per cent cap on Manchester’s
contribution for the overall repairs undertaken
in the building, its reasons
diverge somewhat from Manchester’s. Mr Haig, on behalf of Sage, prefaced
his submissions by suggesting
that while the long overdue remediation of level
12 had been difficult for the other owners it had equally been a disaster for
both
Manchester and Sage. He submitted that it was important, and necessary for
the other owners, to look for a solution that ensured
the work that could no
longer be funded by either Manchester or Sage was nevertheless
completed.
- [58] In addition
to supporting Manchester’s arguments on cl 10.3, Mr Haig raised two
alternative approaches on behalf of Sage
which he submitted would ensure the
works on level 12 could be completed. With regard to the first alternative, Mr
Haig submitted
it was relevant that most of the other owners of the building had
purchased at a time when the modified rules were in force and,
therefore, in
accordance with the owners’ expectations at the time of purchase the Body
Corporate should have responsibility
for the external walls and roof of level
12.
- [59] The second
alternative posited by Sage is that the Court should consider simply terminating
the scheme, which would mean that
remediation to the building would have to be
completed under the 2010 Act which would, again, make the Body Corporate
responsible
for completing remediation to the external walls and roof of level
12.
- [60] In making
its submission, Sage confirmed that it did not seek the Body Corporate to
actually complete the necessary remediation
on level 12, but saw the alternative
approaches it proposed as providing a further basis for the other owners
in
the building to fund the completion of the remediation so that the level 12
apartments could be sold.
What
was the original effect of the scheme?
- [61] In order to
consider the effect of the variation, the first step is to consider how the cost
allocation provisions in the scheme
originally worked prior to the
variation.
- [62] There is no
dispute as to how costs were to be allocated under the scheme as established by
Heath J. Generally, the scheme provided
that the costs of the repairs were to be
allocated as follows:47
- Allocation
of Costs
- 10.1 Where
Repairs can be identified with a specific Unit, the Cost of such Repairs shall
be borne by the Owner or Owners of that
Unit.
- 10.2 Where
Repairs are carried out to Common Property, the provisions of the Act shall
apply.
- 10.3 Subject to
any specific provision to the contrary in this scheme, where repairs involve
both Units and Common Property, the Cost
of such Repairs shall to the extent
possible be apportioned to each Owner on the basis of that owner’s legal
title to part
of the Building.
- [63] In terms of
the scheme, it is cl 10.1 that requires owners to pay the cost of repairs to
their specific unit and cl 10.2 that
brings in the scheme of the 1972 Act making
owners liable for the costs of repairs to common property according to
individual unit
entitlement. These general provisions apply throughout and
establish the basis of liability for all owners including Manchester.
It was the
operation of these clauses that meant that Manchester has no liability for
repairs to unit property on levels 1–11
of the building, and why, but for
the specific limitation of liability contained in cl 21 of the original scheme,
Manchester was
required to meet the costs of repairs to its unit property on
level 12, including the external walls and roof. Clause 10.3 does not
derogate
from the starting point set out in cls 10.1 and 10.2 where the repair is
identifiably common property or unit property.
Instead, cl 10.3 deals with the
specific instance where the repair involves both common property and unit
property, for example where
there is a join between common property and unit
property, although
47 Heath judgment No 3, above n 1, at sch A.
as Fogarty J noted even then apportionment between common property and unit
property can be carried out relatively precisely.48
- [64] The
principles set out in cl 10 were amended, but not displaced, by cl 21 which
provided a specific regime for cost allocation
in respect of the works on level
12 and, in particular, Manchester’s liability for those repairs that would
have otherwise
been determined by cls 10.1–10.3. In relation to cost
allocation, cl 21 relevantly provided:
- 21.1 Manchester
Securities Limited (“Manchester”) is the Owner of the penthouse on
level 12 of the Building. This clause
of the scheme provides for:
(a) the carrying out of Repairs to level 12 as contemplated by the Building
Consent by Manchester; and
(b) Manchester’s share of the total Cost of the Repairs of the entire
Building
- 21.2 Manchester
shall not be liable to pay more than 11.88% of the total Cost of the Repairs
carried out pursuant to this Scheme provided however that any Costs incurred
by Manchester in respect of Project management consultants or other
construction-related
advisors that do not provide benefit to all other
individual proprietors or the body corporate shall be borne solely by
Manchester.
The costs in respect of project management consultants or other
construction-related advisors that Manchester contends provide a
benefit to all
individual proprietors (other than Manchester) or the body corporate shall be
made available in writing, together
with supporting documentation to the
secretary of the body corporate. Any dispute about whether benefit is provided
to all individual
proprietors (other than Manchester) or the body corporate
shall be determined under the dispute resolution provisions of this
Scheme.
- 21.3 The Cost of
Repairs to the Units and Common Property situated at level 12 of the Building
shall be separately assessed and paid
by Manchester, provided that Manchester
shall give to and consult with the Body Corporate all documents and or
information in connection
with any design element, pricing, quantity
surveyor’s or other review of prices, contracts and or sub-contracts with
the intent
that any works undertaken and to be paid by Manchester shall be
transparent from the outset.
- 21.4 Subject to
clauses 21.1 and 21.2, the amount payable by Manchester on account of
Repairs to the building other than the works to level 12 listed in clause 21.7
shall be 11.88% of the total Cost of Repairs less the costs of repairs
assessed and paid for in accordance with clause 21.3.
48 See below at [87] and fn 69.
- [65] Clause 21
clearly did not displace cl 10 or else Manchester’s liability would have
been 11.88 per cent of the total costs
of the repairs of the building.49
This is because the scope of “costs” and “repairs”
in terms of cl 2 and 3 of the scheme would have included
the costs of repairs to
the individual units on levels 1–11 as well. Instead, as both the Heath
and variation judgments made
clear, there is no dispute that the references to
11.88 per cent contained in cls 21.2 and 21.4 coupled with cls 10.1 and 10.2
limited
Manchester’s contribution to 11.88 per cent of the repairs to
common property on levels 1–11 and the repairs to both
unit property and
common property on level 12.
- [66] This
interpretation is supported by the illustration provided by Heath J in the
Heath judgment No 1 when his Honour described how after completing
repairs on level 12 the balance of Manchester’s 11.88 per cent
contribution (estimated
to be
$242,500) would be paid towards the costs of repairs to common property in the
rest of the building.50 A similar illustration was provided by
Fogarty J when considering the effect of the cost blow-out on level 12 on the
original scheme.
At that point, when the estimated cost of the repairs to level
12 had blown out to $2.3 million (an increase of some 460 per cent),51
the effect of the 11.88 per cent cap imposed by Heath J was that not only
would Manchester not be required to make a contribution
to the cost of common
property repairs on levels 1–11, but the other owners in the building
would be required to pay Manchester
for the cost of both its repairs to its unit
on level 12 and the common property on level 12 once the cost of those repairs
exceeded
11.88 per cent of the cost of repairs to all levels.52
The
Fogarty variation judgment
- [67] As noted in
the relevant background section, Fogarty J concluded that as a result of the
costs blow-out on level 12 a limitation
of Manchester’s liability of
the
49 Although as noted in n 48 this seems to be what Mr Cummins is
now saying.
50 Heath judgment No 1, above n 13, at [49].
- Not
430 per cent as stated by the Court of Appeal in the variation appeal
judgment, above n 10, at [26].
52 Fogarty
variation judgment, above n 2, at [67].
type imposed by Heath J was no longer appropriate.53 Instead the
scheme of the 1972 Act was to be applied with regard to cost allocation.54
As Fogarty J explained:55
The Court is guided, as it must be, by the reasoning of the Court of Appeal
in Tisch. The effect of that reasoning is that the Court cannot lightly
depart from the scheme of the Unit Titles Act. At the core of that
scheme is the
proposition that repair and maintenance of common property is a burden shared by
all unit holders in proportion to
the unit entitlement. It matters not what
other costs such unit holders have to bear in respect of repair and maintenance
to their
units.
- [68] Although
both Manchester and Sage submitted that the Fogarty variation judgment
and the variation appeal judgment were only concerned with common
property and not the cost of Manchester’s repairs to its unit property on
level 12, that is
clearly incorrect. As Mr Orpin-Dowell observed in
closing:
It is not open to Manchester to now contend that whether it was liable to pay
for the cost of repairs to its unit property on level
12 was not an issue before
Fogarty J. The whole point of Manchester’s position was that because it
had to pay for repairs to
its unit property on level 12, the 11.88 per cent cap
was exceeded and other unit owners therefore had to make a contribution to
the
cost of repairing its unit property. The issue Forgarty J had to decide was
whether Manchester’s liability should remain
limited to 11.88 per cent or
whether there should be a return to the default statutory scheme under which it
would pay 11.88 per
cent of common property repairs, plus the cost of repairing
its unit property. This is exactly how the Court of Appeal understood
the
position: see [56]-[57] above.
- [69] With
references to Tisch56 and Young,57 Fogarty J
accepted the Body Corporate’s submissions that under the 1972 Act it
“was a deliberate policy that the unit
holders were responsible jointly
for the common property, and individual holders of units for their individual
units.”58
- [70] There can
be absolutely no doubt that Fogarty J believed that the 11.88 per cent cap on
Manchester’s liability should be
removed and his Honour clearly varied the
scheme with the intention of achieving that outcome. Specifically, the two
explicit references
to Manchester not being liable for more than 11.88 per cent
were removed.
53 See above at [26]–[31].
54 Fogarty variation judgment, above n 2, at [30].
55 At [78].
56 Tisch v Body Corporate No 318596, above n 27.
57 Young v Body Corporate 120066 [2007] NZHC 1401; (2007) 8 NZCPR 932.
58 Fogarty variation judgment, above n 2, at [57].
His Honour amended cls 12.2 and 21.4 by removing any reference to the 11.88 per
cent figure and inserting replacement wording, so
that the relevant parts of cl
21 now read:59
- 21.1 Manchester
Securities Limited (“Manchester”) is the Owner of the penthouse on
level 12 of the Building. This clause
of the scheme provides for:
(a) the carrying out of Repairs to level 12 as contemplated by the Building
Consent by Manchester; and
(b) Manchester’s share of the total Cost of the Repairs of the entire
Building.
- 21.2 Manchester
shall pay the cost of repairs of common property to all levels calculated in
accordance with the unit entitlement
(now known as ownership interest) of
Manchester’s unit provided however that any Costs incurred by
Manchester in respect of project management consultants or other
construction-related
advisors that do not provide benefit to all other
individual proprietors or the body corporate shall be borne solely by
Manchester.
The costs in respect of project management consultants or other
construction-related advisors that Manchester contends provide a
benefit to all
individual proprietors (other than Manchester) or the body corporate shall be
made available in writing, together
with supporting documentation to the
secretary of the body corporate. Any dispute about whether benefit is provided
to all individual
proprietors (other than Manchester) or the body corporate
shall be determined under the dispute resolution provisions of this
Scheme.
- 21.3 The Cost of
Repairs to the Units and Common Property situated at level 12 of the Building
shall be separately assessed and paid
by Manchester, provided that Manchester
shall give to and consult with the Body Corporate all documents and or
information in connection
with any design element, pricing, quantity
surveyor’s or other review of prices, contracts and or sub-contracts with
the intent
that any works undertaken and to be paid by Manchester shall be
transparent from the outset.
- 21.4 Manchester
shall pay the cost of repairs of common property to all levels calculated in
accordance with the unit entitlement
(now known as ownership interest) of
Manchester’s unit.
(emphasis added to replacement wording)
59 It should be noted that the scheme was not reprinted in full
following the Fogarty variation judgment. Instead the sealed order following
the
judgment indicates the specific words to be deleted and the words that replaced
them in cls 21.2 and 21.4 respectively.
Did
the variation remove the 11.88 per cent cap?
- [71] Although
both Manchester and Sage now contend that the changes made to the scheme by
Fogarty J did not affect Manchester’s
liability, there was no suggestion
to that effect when the Fogarty variation judgment was released.
- [72] The Fogarty
variation judgment was, in fact, initially released to the parties in draft on
22 September 2016. Justice Fogarty
provided the draft judgment solely to enable
further submissions as to the calculations of sums.60
- [73] In
response, Manchester took what it described as the exceptional step of inviting
Fogarty J to receive further submissions beyond
those that his Honour had been
called for. The reason given by Manchester was:
By any measure, the proposed order, in bluntly removing the cap, has a
major financial impact on Manchester. In percentage terms, it would increase
Manchester’s share of the repair costs
from 11.88% (the cap) to
approximately 28% (on the costings before the Court with the adjustment sought
by the Body Corporate). In
dollar terms, Manchester’s contribution would
increase from
$1,104,840 (11.88% of circa $9.3 million) to $2,624,296 (2,203,231 as
estimated by Mr Maddren plus the immediate payment of $321,265
that the Body
Corporate seeks).
(emphasis added)
- [74] As the Body
Corporate submitted, Manchester accepted in its memorandum to Fogarty J that the
effect of the Fogarty variation judgment was to render Manchester liable
for all of the repairs to its unit property on level 12 (then estimated to
cost
$2,303,231) together with its 11.88 per cent share of repairs to the common
property represented by the figure of $321,265. At the
invitation of Fogarty J,
the Body Corporate confirmed it too understood the effect of the judgment in the
same way. Justice Fogarty
declined to call for the further submissions sought by
Manchester, instead noting:61
- [11] ...As the
draft shows, I was aware of the scope and brought the consequences of the
judgment.
- Body
Corporate 172108 v Manchester Securities Ltd HC Auckland
CIV-2009-404-6868, 22 September 2016 (Draft judgment No 1) at
[152]–[153].
61 Body Corporate 172108 v
Manchester Securities Ltd CIV-2009-404-006868, 7 December 2016.
- [12] Therefore
in as much as Manchester is dissatisfied with the judgment, the proper course is
for Manchester to appeal it...
- [75] Unsurprisingly,
Manchester reiterated the same arguments when it appealed the Fogarty
variation judgment to the Court of Appeal. In dismissing the appeal, there
is equally no doubt the Court of Appeal considered the effect of the Fogarty
variation judgment was that the 11.88 per cent cap on Manchester’s
liability had been removed.62
- [76] Instead,
the Court of Appeal specifically confirmed that Manchester should not receive a
subsidy from the other owners for the
costs of works to its unit property when
it stated:63
...it was undeniably part of the logic of
the scheme that Manchester would benefit from the common property repairs to
levels 1–11
and therefore should make some contribution to the cost of
those repairs. That was the whole purpose of the formula. We are confident
Heath
J would never have sanctioned a scheme whereby Manchester paid nothing for that
benefit but instead received a windfall at
the expense of the other unit
holders.
(footnotes omitted)
- [77] The Court
went on to approve Fogarty J’s summary of the law post-Tisch which,
with regard to the scheme of the 1972 Act, was to impose a burden upon all unit
holders to repair and maintain common property
in proportion to their unit
entitlement, regardless of the cost each have to bear in respect of the repair
and maintenance to their
units.64
- [78] Manchester’s
arguments did not change when it sought leave to appeal to the Supreme Court.
The notice of application stated
that the Court of Appeal had erred, amongst
other things, because:
[T]he scheme as varied will relieve the other owners from costs they would
have incurred if the Body Corporate had been free to carry
out all repairs under
a single contract, free from delays by Manchester (such costs being over
$1,000,000).
62 Variation appeal judgment, above n 10, at [29](f).
63 At [41].
64 At [54]–[55].
- [79] In
addition, Manchester argued that a substantial miscarriage of justice would
occur due to the variation, which Manchester considered
would have the following
effect:
Instead of directing that the additional costs of dilatory remediation be
quantified and borne by Manchester alone, the scheme as
varied effectively
releases the other owners from making any contribution to the substantial costs
that they would otherwise have
occurred.
In an effort to avoid Manchester enjoying a “windfall” from
having the common property repaired, the scheme as varied
gives the other owners
far greater windfall at Manchester’s expense because they no longer have
to contribute anything to replacing
the roof and other unanticipated exterior
property repairs for which they would have been liable under the original
scheme.
- [80] This
section of the application makes it clear that Manchester considered the other
owners would now not have to contribute to
the repair and remediation of
Manchester’s property on level 12, specifically the roof and the external
walls, which are “substantial
costs they would have otherwise
incurred”. This point was made even more clear in Manchester’s
submissions that accompanied
the application:
Given retroactive effect, this seemingly simple variation shifted huge costs
onto Manchester that were in no way attributable to the
“consequences” of dilatory remediation. Under the original scheme,
for example, all owners would have had to contribute
to the costs of replacing
the roof (some
$622,000). Now, even though no one could suggest that the need to replace the
defective roof is attributable to dilatory remediation,
the varied scheme shifts
the entire cost to Manchester alone.
(footnote omitted)
- [81] It is
therefore beyond any question that all parties, together with the High Court and
Court of Appeal, were clear that the variation
had the effect of removing the
11.88 per cent cap on Manchester’s liability.
- [82] As I
discussed with Mr Francis at the hearing, for Manchester to seriously claim at
the hearing before me that, notwithstanding
the removal of the claims limiting
the liability of Manchester to 11.88 per cent, the retention of cl 10.3 has the
effect of maintaining
the 11.88 per cent cap would have meant that both Fogarty
J and the Court of Appeal failed to understand the effect of the variation.
Had
I been satisfied, however unlikely, that this was the case, the appropriate
course of action would be to
consider a variation to the scheme to reflect the intention of the variation as
set out in those earlier judgments.
- [83] Such a
course is, however, not necessary. Manchester’s argument is clearly
untenable and is nothing more than a blatant
collateral attack on both the
Fogarty variation judgment and variation appeal judgment.65
It is clear that when these judgments are considered in context there is
absolutely no room to assert that some sort of de facto cap
on
Manchester’s liability remains.
- [84] While Mr
Francis was correct that there is little explicit discussion of
Manchester’s liability to pay for the remediation
of its own unit property
on level 12 in addition to its liability to meet 11.88 per cent of the costs of
all common property repairs,
that does not mean that the position has yet to be
determined.
- [85] First, as
noted, both Fogarty J and the Court of Appeal did note the difference between
the original scheme and the scheme as
varied would no longer require the other
owners to subsidise the costs of repairing Manchester’s property on level
12.66
- [86] Secondly,
while I accept Manchester’s submission that the responsibility for unit
holders, including Manchester for the
costs of repairs to their units was not
the focus of Fogarty J it did not need to be, albeit it is in any event clear
that Fogarty
J understood this was the effect of the Fogarty variation
judgment.67 As noted, this was what was provided for in cl 10.1 of
the scheme which explicitly provides that the cost of repairs to unit property
are to be borne by the owner or owners of the relevant unit.68
Following the variation, cl 10.1 was no longer limited by the overall limitation
of Manchester’s liability to the 11.88 per
cent hitherto contained in cls
21.2 and 21.4. Given that position, and in the absence of any specific
limitation of liability, it
is not open to Manchester to claim that
notwithstanding the variation some sort of limitation has remained. Certainly,
when considered
in context with cls 10.1 and 10.2, cl 10.3 does not provide any
basis for Manchester to assert that it is entitled to claim a contribution
for
work undertaken to its own property.
65 Faloon v Planning Tribunal at Wellington [2020] NZCA 170
at [2].
66 See above at [73]–[77].
67 See above at [74].
68 See above at [62]–[63].
- [87] In
particular, and as noted previously, cl 10.3 only applies where the repairs
“involve both Units and Common Property”.
Given the clear and
unambiguous effect of cls 10.1 and 10.2, which surely underpinned the analysis
of both Fogarty J and the Court
of Appeal, cl 10.3 can only apply effectively at
the junction or boundary between common property and a unit where it is,
therefore,
impossible to apportion between unit property or common property.
Clause 10.3 simply provides a mechanism where particular repairs
have been made
to both a specific unit or units and common property. This was in fact the very
exercise undertaken by Fogarty J when
he considered the apportionment of costs
between common property and private property on levels 1–
11.69 As a result, it is wholly clear that cl 10.3 does not provide
a basis for Manchester
to claim some sort of overall contribution by the other unit owners for work
undertaken to Manchester’s unit property on level
12. Specifically, it
does not provide a vehicle to enable Manchester or Mr Cummins to attempt to
argue that all of the monies (however
unwisely) expended by Manchester on level
12 and, in particular, to the roof and exterior walls, which are clearly unit
property
owned by Manchester, can be apportioned according to unit
entitlement.
- [88] This
interpretation is not surprising. This of course what Manchester argued was the
position when it considered Fogarty J’s
draft judgment, and when it
appealed the Fogarty variation judgment to the Court of Appeal. It was
only after the application for leave to appeal was rejected by the Supreme Court
that Manchester first
raised the argument that, despite the best efforts of
Fogarty J and the Court of Appeal, the 11.88 per cent cap somehow remained.
Contrary to Manchester’s current arguments, however, there has never been
any confusion about the effect of the variation.
- [89] Likewise,
nothing in cls 21.2–21.4, as varied by Forgarty J, changes the position
with regard to the cost allocation for
the repairs to unit and/or common
property set out in cl 10. Clauses 21.2 and 21.4 do not provide any basis for
contending
69 There is a lengthy discussion in the Fogarty variation
judgment about the apportionment of the cost of repairs to private property
and common property on levels 1–11. In the course of determining
that the
repairs to common property contributed 61 per cent of the repairs undertaken by
the Body Corporate, Fogarty J noted the
evidence before him of “specific
examples of different splits” including where particular window joinery
was identified
as 96 per cent common property and 4 per cent to the unit;
Fogarty variation judgment, above n 2, at [87]–[102].
that the costs of repairs to the unit property on level 12 by Manchester should
not be paid for by Manchester. On the contrary, Manchester
was, in terms of the
scheme as varied, required to undertake all of the repairs, both to its own unit
and to the common property
on level 12, and was required to separately assess
and pay for “the cost of repairs to the Units and Common Property situated
on level 12”.
- [90] For
completeness it should be noted that cl 21.2 does not affect the overall cost
allocation between unit property and common
property repairs. Instead, it
provides a limited mechanism for Manchester to make claims for consultant fees.
As previously noted,
cl 21.2 now reads:
Manchester shall pay the cost of repairs of common property to all levels
calculated in accordance with the unit entitlement (now
known as ownership
interest) of Manchester’s unit provided however that any Costs incurred
by Manchester in respect of project management consultants or other
construction-related
advisors that do not provide benefit to all other
individual proprietors or the body corporate shall be borne solely by
Manchester. The costs in respect of project management consultants or
other construction-related advisors that Manchester contends provide a benefit
to all individual proprietors (other than Manchester) or the body corporate
shall be made available in writing, together with supporting
documentation to
the secretary of the body corporate. Any dispute about whether benefit is
provided to all individual proprietors
(other than Manchester) or the body
corporate shall be determined under the dispute resolution provisions of this
Scheme.
(emphasis added)
- [91] The words
inserted as part of the variation sit uneasily with the proviso, which made more
sense when it provided an exception
to the overall limitation of
Manchester’s liability to 11.88 per cent. As cl 21.2 now reads, in
conjunction with cl 10.1,
the proviso does not appear to relate to the
obligation to contribute to the repair of common property but simply confirms
that the
costs of “project management consultants or other
construction-related advisors” where such costs are not found to
“provide
[a] benefit to all individual proprietors or the body
corporate” are to be borne by Manchester. There is in fact nothing in
cl
21.2 that enables Manchester to pass on the costs of project management
consultants or other construction related advisors it
has incurred with regard
to the repair of its own unit property.
- [92] It appears
from the figures provided by Mr Cummins that as of March 2022 the maximum amount
of “project management consultants
or other
construction-related advisors” claimed to come within cl 21.2 is
$1,194,552.61 (excluding GST).70 It is thus at most only a reasonably
small proportion of the total cost expended by Manchester on level 12. It is, in
any event, not
clear whether all invoices have been made available still less
whether at any point any supporting documentation to justify why those
costs
benefit all of the other owners or the Body Corporate, and it therefore appears
that any claim under cl 21.2 remains pending
rather than actual.
- [93] Finally,
with regard to the effect of the scheme, cl 21.3 also can have no bearing on
Manchester’s liability to bear the
costs of repair of its unit property on
level 12 as well as 11.88 per cent of common property throughout the building.
Clause 21.3
simply recognises that, as it was Manchester that was responsible
for carrying out all works on level 12 to both unit and common
property, it is
necessary for those repairs to “be separately assessed and paid by
Manchester” so that the other owners
88.12 per cent share of the costs of
the repairs of the common property could be subsequently reimbursed to
Manchester. Notwithstanding
the figures relied upon by Fogarty J, this does not
appear to have occurred when common property repairs to level 12 were being
carried
out, while Mr Cummins calculations as to the quantum of the costs for
common property repair on level 12 are clearly wrong, given
they include amounts
for the roof, external walls of level 12 and decks, which are all undeniably
part of Manchester’s unit
property in terms of cl 10.1. Likewise, there is
no suggestion that, as the repairs to common property were undertaken,
Manchester
gave to and consulted with the Body Corporate on “all documents
and or information in connection with any design element, pricing,
quantity
surveyor’s or other review of prices, contracts and or sub-contracts with
the intent that any works undertaken and
to be paid by Manchester shall be
transparent from the outset.”
- [94] Taking
these various points together it follows that the scheme as properly interpreted
provides:
70 According to Mr Cummins the total project management
consultants or other construction-related advisors comes to $1,355,597.60
(excluding
GST), from which he deducted Manchester’s 11.88 per cent share
of those costs ($161,045.00).
(a) With regard to remedial work undertaken on Manchester’s unit, the
costs are to be borne solely by Manchester pursuant to
cl 10.1 of the scheme,
subject to any decision Manchester may have pursuant to cl
21.2 of the scheme.
(b) With regard to remedial work undertaken to the common property on level 12,
the costs of remediation are to be borne according
to unit entitlement pursuant
to cl 10.2, subject to any claims by Manchester pursuant to cl 21.2 of the
scheme.
(c) It is only at the junction between common and unit property that cl 10.3 can
have any application. Given the clear effect of
cls 10.1,10.2 and
21.2–21.4, cl 10.3 is not a provision that can be used to claim
contributions from the other owners in the
building to repairs to
Manchester’s unit on level 12.
Is
any further variation required?
- [95] Having
concluded the overall effect of the scheme as varied by Fogarty J is clear, the
question turns to whether any aspect of
the scheme should be varied, considering
in turn the changes proposed by the Body Corporate, Manchester and
Sage.
- [96] Given the
conclusions I have reached about the effect of the scheme, I conclude it is not
necessary to make any of the changes
sought by the Body Corporate to confirm
that Manchester is required to meet the costs of repairs to its unit property,
while contributing
11.88 per cent of all common property repairs.
- [97] In general
terms, the type of variation sought by the Body Corporate would have only been
required in the event there was a lacuna
— a gap between what Fogarty J
and the Court of Appeal stated in their respective judgments as to the effect of
the variation
and what in fact resulted. Contrary to the submissions of both
Manchester and Sage, it is clear that any overall cap on Manchester’s
liability was indeed removed in 2017.
- [98] With regard
to the specific variations sought by the Body Corporate, I note that these were
couched in the alternative in the
event that the Court did not issue
declarations to the effect that:
Manchester is estopped from seeking to apportion the costs of repairing its
private property on level 12 between it and other unit
holders whether under
clause 10.3 of the Scheme or under clause 21.2 of the Scheme or otherwise,
except in relation to the Body Corporate’s
common property on level 12 and
then only to the extent that this was specifically contemplated by the
Maddren/Johnson difference
in the [Fogarty variation judgment and
variation appeal judgment].
- [99] The issue
as to whether declarations are required and, if so, the terms of any
declarations will be considered in the next subsection.
- [100] It is even
more clear that, having confirmed the effect of the scheme earlier in this
judgment, none of the possible variations
identified by Manchester and Sage are
at all appropriate. There can be no doubt that the variation sought by
Manchester attempts
to revisit the effect of both the Fogarty variation
judgment and variation appeal judgment by seeking an effective cap of
11.88 per cent for Manchester’s contribution to common property repairs
and its costs of remediating
its own private property on level 12 subject only
to “any additional cost incurred in the building repairs at level 12 to
the
extent that these arise from dilatory remediation by Manchester, to be fixed
by arbitration in the absence of agreement”.
- [101] There is
no basis whatsoever for such a variation. The logic of the scheme remains. It
is, in fact, as valid now as at the time
it was varied by Fogarty J in 2017 and
upheld by the Court of Appeal.
- [102] Both the
High Court and Court of Appeal concluded it was unconscionable to continue with
the original scheme approved by Heath
J given the extent of the costs increase
to level 12 in the interim. As noted in the background section, the estimated
costs of repairing
level 12 had increased 460 per cent in the interval between
approval of the scheme by Heath J and the hearing before Fogarty J in
2016.
- [103] The
situation has not improved since then. At the hearing before me, Mr Cummins
produced spreadsheets he had prepared showing
that the total costs of
the
works undertaken to level 12 as at March 2022 totalled nearly $9 million (GST
exclusive) with a minimum of a further $1.6 million
required simply to make
level 12 weathertight and obtain a code compliance certificate. Even if
allowance is made for the approximately
$1.9 million “betterment”
costs and for the “wasted expenditure” calculated by Mr Cummins
(which has not
been corroborated), and not allowing for any deductions for
dilatory remediation by Manchester (which Manchester has not attempted
to
quantify), the total actual and estimated cost of repairs of approximately
$8.2 million (GST exclusive) is now not less than 1640 per cent greater than
originally estimated to Heath J, and three and a half
times the estimate
provided to Fogarty J in 2016. As a result, and for the reasons set out in both
the Fogarty variation judgment and the variation appeal judgment,
the magnitude of the cost increases on level 12 by themselves justify retention
of the scheme as varied by Fogarty J.
- [104] This
represents a best-case scenario. Leaving aside the historical failures of
Manchester to provide anything approaching accurate
estimates of the costs of
remediation for level 12, the reality is that the figures provided by Manchester
are, at best, opaque.
Contrary to the scheme,71 Manchester has
throughout shown a distinct lack of transparency as to what it has been doing on
level 12 with the result that there
is real uncertainty about what has been done
by way of development to level 12 — an example is the additional area on
level
13 that has been constructed as part of one of the apartments, as opposed
to repairs and maintenance. It is also unclear to what
extent expenditure
ostensibly on repairs has been entirely wasted. By way of example, Mr Cummins
stated on a number of occasions
in the course of his evidence that level 12 had
been taken down to a bare slab as a result of the damage found. There has,
however,
been no reports let alone photographic evidence produced to show that
this was in fact what has occurred. Similarly, a report by
Kaizon Building Ltd
is relied upon by Mr Cummins and Manchester as justification for the total
replacement of the roof. The report
relied on does not however recommend the
total replacement of the roof, and no other report has been specifically
identified by Mr
Cummins to that effect, let alone placed before the
Court.
71 Including cls 21.2, 21.3 and 21.9 of the scheme.
- [105] Given this
position and the fundamental lack of any transparency, as I discussed with
counsel at the hearing it would be quite
unjust and simply inconceivable for the
Court to reimpose any sort of limit on Manchester’s liability that could
possibly have
the effect of allowing Manchester to seek contribution from the
Body Corporate and the other owners of the building for repairs to
its unit
property, let alone to allow a virtually open-ended arbitration to commence
allowing for the possibility, however small,
that the other owners could be
required to contribute anything approaching the current $5 million sum Mr
Cummins considers they should
be contributing (less any amount for dilatory
remediation).
- [106] The
alternative argument advanced by Manchester is that the Body Corporate is
somehow bound by a resolution made in April 2010
which would have the effect of
binding it to limiting Manchester’s overall liability to 11.88 per cent.
This suggestion has
no merit whatsoever. It quite simply ignores everything that
has happened since then. The resolution relied upon by Manchester predated
the
establishment of the scheme by Heath J and has long since been overtaken by
events, and in particular the Fogarty variation judgment and the
variation appeal judgment.
- [107] Overall, I
am in no doubt that Manchester’s cross application for variation must be
dismissed in its entirety.
- [108] The
alternatives proposed by Sage in the course of its submissions are equally
unattractive. For completeness I make the following
comments on their merits
putting to one side the fact that Sage had not formally applied for any form of
variation and which, given
it had not been served on the other owners (who were
separately represented), could not have been accepted in the absence of further
delay.
- [109] Specifically,
Sage’s suggestions that the scheme revert to the original amended rules or
a cancellation of the scheme
so that the 2010 Act would apply are unashamedly
directed at getting a financial contribution from the other owners in the
building
so as to avoid the consequences of poor investment decisions made by
Sage in providing ongoing funding to Manchester. Contrary to
the submissions
made by Mr Haig on behalf of Sage, I do not accept that Sage has lost anything
as a result of the scheme. Sage is
simply a secured creditor that has made a
series of commercial decisions to
continue to fund Manchester who, unfortunately for Sage, appears incapable of
either completing the work required or repaying the
monies advanced. The fact
Sage has continued to support Manchester unconditionally has meant that it has
actively contributed to
the present unsatisfactory situation whereby the repairs
to level 12 have not been completed, notwithstanding the amounts provided.
- [110] Like the
proposals made by Manchester, the proposals made by Sage have little or no
regard to previous decisions about the scheme,
nor are they in any way
practical. Given this position, the specific proposals can be addressed
relatively briefly. The suggestion
that the scheme should be varied to revert to
the original amended rules was in fact an argument put forward by Manchester
before
the Court of Appeal in 2017 and addressed in the variation appeal
judgment in the following terms:72
- [57] The
argument is an unattractive one. Previously, Manchester had asserted to Heath J
that r 4 along with the other “changed
rules” was ultra vires and
that the rules to be applied were the default statutory rules. Manchester made
that assertion in
its efforts to prevent the Body Corporate from carrying out
the repairs on level 12, something the Body Corporate could not do without
a
court sanctioned s 48 scheme if r 4 were invalid. The Body Corporate had
reluctantly accepted Manchester’s assertion that
r 4 was invalid. That was
why it had made its application for a court sanctioned scheme under s 48 in the
first place.
- [58] We agree
with Mr Allan that having claimed r 4 was unlawful in a bid to control its own
repairs, it ill-behoves Manchester now
four to five years into a re-development
to switch course and pray in aid the very rule it once eschewed. As Mr Allan
also pointed
out, there is no evidence indicating that had it not been for the
perceived invalidity of r 4 Manchester would have foregone its
redevelopment
opportunity and permitted the Body Corporate to repair level 12. We note further
that r 4 said nothing about the cost
allocation which was the critical variation
issue. In all these circumstances, we consider this argument is without
merit.
- [111] The
argument has no more merit for having now belatedly been raised by Sage, even
less so given that almost all of Sage’s
advances, some $8.65 million,
appear to have been made after the Fogarty variation judgment was issued
in March 2017. A bald assertion made by Mr McGaveston on behalf of Sage
following the conclusion of the hearing before
me to the effect that he was
never informed of the variation and had no understanding of its effect is
entirely inconsistent with
his earlier affidavit that deposed he had been
“kept aware of the key developments in the various proceedings
72 Variation appeal judgment, above n 10.
relating to the mediation scheme by Mr Cummins”. Any suggestion to the
contrary is simply unbelievable in the context of this
case, particularly given
the amounts advanced by Sage to Manchester, and I reject his assertion
outright.73
- [112] Likewise,
while the 2010 Act repealed the 1972 Act in which the scheme was proved, this is
not a new issue. The 2010 Act was,
in fact, passed only shortly before the
scheme was first approved by Heath J and came into force in June 2011. The issue
of whether
a scheme under the 1972 Act could be varied after the repeal of the
1972 Act was indeed brought to this Court in 2018. In considering
that the
repeal of the 1972 Act did not preclude a subsequent variation of the scheme
approved under the 1972 Act, Katz J pointed
out that if a new scheme was
acquired under the 2010 Act:74
- [21] Applying
for a new scheme would require a new proceeding, with potentially onerous and
expensive notice and service requirements.
For example, over 40 respondents were
originally named as parties and served with these proceedings. They included all
unit holders
and all identifiable charge holders and
insurers...
- [22] If a new
scheme under the 2010 Act is required, unit holders will not necessarily be
limited to only opposing those aspects of
the proposed scheme that are
“new”. For example, where units have changed hands subsequent to the
original scheme being
settled, new unit holders may well have new issues or
grounds of opposition they wish to raise in respect of the proposed scheme.
The
Court would need to consider and determine such issues on their merits (albeit
in the context of a prior scheme having been approved).
Considerable delay,
expense and uncertainty could result. This would clearly be undesirable,
particularly where the works under the
original remediation scheme are partially
completed.
- [113] It is
moreover clear that the scheme was varied by Fogarty J notwithstanding the
repeal of the 1972 Act, and it is difficult
indeed to see any advantages in so
fundamentally changing course at this time given that, as noted, I conclude the
overall logic
of the scheme remains sound.
- [114] I
therefore conclude that no variation to the overall effect of the scheme is
required. I instead turn to consider various specific
variations proposed in the
alternative by the Body Corporate. Most of these proposed variations are aimed
at restricting the scope
of any future arbitration, specifically:
- Applying
a similar approach to Eng Mee Yong v Letchumanan [1979] UKPC 13; [1980] AC 331(PC); see
Krukziener v Hanover Finance Ltd [2008] NZCA 187, [2010] NZAR 307 at
[26].
74 Body Corporate 172108 v Manchester Securities
Ltd, above n 22.
(a) deleting cl 21 in its entirety, thereby restricting the ambit of any
arbitration with regard to project management consultants
or other
construction-related advisors in terms of cl 21.2; or
(b) restricting the ambit of any arbitration on the level 12 costs of
construction:
(i) “to the extent of the Maddren/Johnson difference specifically
contemplated by the [Fogarty variation judgment and Variation appeal
judgment]”; or
(ii) if not restricted solely to the extent of the Maddren/Johnson difference,
to limit claims to project manager or construction-related
advisor costs
“solely in relation to the juncture of levels 11 and 12” incurred by
Manchester “prior to the Body
Corporate commencing its work to the
juncture at levels 11 and 12” and with “[a]ll owners below level 12
[having to]
receive the benefit”.
- [115] The
deletion of cl 21 cannot be considered appropriate when, notwithstanding the
delay, the Court of Appeal has been clear that
those claims are open to
Manchester.75 Likewise, having determined the effect of the scheme, I
do not accept the Body Corporate’s submission that the other alternatives
are necessary to clarify the effect of the variation. Instead, they seem to
inappropriately restrict the application of clause 21.2.
It is already
self-evident that for the Body Corporate to benefit from reports of project
management consultants or other construction-related
advisors such reports must
have had to been provided to the Body Corporate prior to undertaking work of its
own. Clause 21.2 however
specifically does not require both the Body Corporate
and all the other owners to benefit, it specifies either, and I am
not prepared to change that aspect of the scheme at this late
juncture.
- Manchester
Securities Ltd v Body Corporate 172108 [2018] NZCA 190, [2018] 3 NZLR 455 at
[41]–[43].
- [116] There is
more merit in the final alternative variation put forward by the Body Corporate,
fixing a timeframe for the commencement
of any arbitration with reference to the
issue of the code compliance certificate for level 12. As I discussed with
counsel at the
hearing, it is important that all matters, both construction and
litigation, be brought to a close as soon as possible. Moreover,
given the
overall history of the remediation of the building and in particular
Manchester’s “dilatory and prevaricating”
behaviour to date,
it would be simply unconscionable to allow the prospect of arbitration on cl
21.2 to endlessly hang over the heads
of the other owners.
- [117] As a
result I conclude some type of timetable to ensure that any arbitration is
commenced promptly after the issue of a code
compliance certificate is
appropriate. Any such requirement should not prejudice the party seeking to
arbitrate. The quantification
of the claim can surely be commenced already,
including undertaking a detailed assessment of the dilatory remediation, while
the
remainder can be completed after the conclusion of works and prior to the
issue of the code compliance certificate. Taking these
matters together, I am
satisfied cl 13 of the scheme should be varied so as to require any arbitration
to commence within one month
of the issue of the code compliance certificate for
level 12.
- [118] In
considering this variation I am concerned that the current status quo will
continue that Manchester or its successor will
not complete the remediation of
level 12 in a timely fashion, with the result that the prospect of arbitration
will continue to hang
over the other owners for some time to come. As a result,
I reserve leave for the Body Corporate to seek a further variation to the
dispute resolution provisions with a view to restricting the ability of
Manchester or its successor to arbitrate in the event the
remediation of level
12 is not completed within 6 months of the date of this judgment.
- [119] In the
meantime, I also conclude two other amendments to the dispute resolution
provisions in the scheme are required. First,
while Manchester has undertaken
not to arbitrate further until a code compliance certificate has been
issued,76 as has been noted Manchester is now in liquidation and it
is not clear who
76 See above at [54].
may ultimately attempt to prosecute any claims it may have by way of cl 13. I
therefore consider it necessary to vary cl 13 to make
it clear that no
arbitration is to be commenced, by Manchester or deriving from
Manchester’s claims, prior to issue of a code
compliance certificate.
- [120] The second
amendment is linked to the lack of certainty as to whether it will be Manchester
or some other party that would be
prosecuting any arbitration, together with
Manchester’s studied refusal to pay the judgment sum ordered by Fogarty J
and the
other amounts owning to the Body Corporate. This has already been an
issue when Mr Cummins attempted to join these proceedings in
Manchester’s
stead as the replacement trustee for the MSTT. Given this position, I am
satisfied it is appropriate to vary cl
13 so as to require Manchester or any
other party seeking to arbitrate in Manchester’s stead to pay the amounts
owing to the
Body Corporate prior to commencing any arbitration. Such a
variation is entirely consistent with the “pay now, argue later”
approach endorsed in successive decisions in this proceeding and which, indeed,
was advanced by Manchester in the hearing before
me in opposing the Body
Corporate’s attempts to limit the scope of arbitration, somewhat
ironically given Manchester has not
paid the amounts it has been ordered to
pay.
- [121] A marked
up copy of cl 13 giving effect to these variations are annexed in the schedule
to this judgment.
Is a
declaration required?
- [122] The final
issue with the cross applications is whether a declaration is required. As
foreshadowed in the preceding subsection,
I consider that a declaration as to
the effect of the scheme is appropriate.
- [123] Although
both the Body Corporate and Manchester sought declarations in the context of
their respective cross applications pursuant
to s 48(6) of the 1972 Act, Sage
formally opposed the declaration sought by the Body Corporate on the grounds
there was no jurisdiction
for the Court to give such relief.
- [124] I reject
Sage’s submission on the jurisdictional issue. It is clear that this Court
has the inherent jurisdiction to make
declarations at any point should it be
necessary
to do so.77 In any event, the respective cross applications under s
48(6) necessarily engaged the jurisdiction of the Court to establish a scheme
pursuant to s 48(1) and consequently the wide powers provided pursuant to s
48(5) which enables “the Court [to] make such orders
as it considers
expedient or necessary for giving effect to the scheme...”.
- [125] In terms
of the declarations necessary, so as to avoid any further attempt by Manchester
to argue that some type of cap remains
on Manchester’s liability, I am
satisfied declarations in the nature of the summary set out at [94] above will
be appropriate.
- [126] These
declarations are more limited than sought by the Body Corporate but I consider
they provide sufficient guidance to the
parties as to the effect of the scheme
and to the scope of any future arbitration pursuant to cl 13.
Conclusion
— cross applications
- [127] Overall,
and for the reasons set out above, I am satisfied that the meaning and effect of
the scheme is clear such that there
is no basis for contending there is any
overall limit on Manchester’s liability. Declarations as to the effect of
the scheme
are therefore appropriate. In addition, while I conclude there is no
need to vary the overall scheme, variations to cl 13 are appropriate
given
Manchester’s changed status and ongoing failure to pay the amounts
ordered, as is the reservation of leave to provide
for further variation should
Manchester not complete remediation of level 12 within a further six
months.
The arbitration appeal
- [128] The
matters at issue in the arbitration appeal follow on from those considered in
relation to the cross applications.
77 See Telecom Corporation of New Zealand Ltd v Commerce
Commission [2012] NZCA 278 at [295], quoting from Lord Woolf and Jeremy
Woolf Zamir & Woolf: The Declaratory Judgment (4th ed, Sweet &
Maxwell, London, 2011) at [3–19].
- [129] The Body
Corporate submitted that Manchester is estopped from seeking to apportion all
the costs of repairs to its unit property
on level 12 among all owners. It
therefore contends that any attempts to apportion the costs of repairs to its
unit property on level
12 on the basis of unit entitlement under cl 10.3 is
nothing more than a collateral attack on the outcome of the earlier variation
proceeding and therefore an abuse of process.
- [130] In the
Body Corporate’s submission, the earlier judgments in the variation
litigation finally determined that Manchester
should pay for the costs of
repairing the building in accordance with the default statutory scheme. Under
that default statutory
scheme Manchester is required to pay for repairs to its
unit property on level 12 plus contribute 11.88 per cent to the cost of repairs
to the common property on all levels. In addition to submitting that the
estoppel arises as a result of the earlier judgments, the
Body Corporate also
submits that it arises through the conduct of Manchester which clearly
acknowledged the effect of those earlier
judgments itself. In the Body
Corporate’s submission, it is not open to Manchester to collaterally
attack the outcome of the
earlier variation litigation because it has thought of
a new legal argument.
- [131] By way of
relief, the Body Corporate seeks that the injunction imposed by Jagose J be
permanently extended.
- [132] In
response, while Manchester acknowledges it is well established that the
doctrines of res judicata, estoppel, and abuse of
process apply equally to
arbitration just as they do to litigation, Manchester submits that there is no
issue estoppel and/or abuse
of process in this case because there has not been a
final determination by any Court or arbitral tribunal in relation to the
apportionment
of costs to repairs to Manchester’s unit property on level
12 between it and the other unit holders under cls
- 10.3 or 21.2 of
the scheme. In particular, Manchester says that Mr Keene was correct in
concluding that:
(a) No Court has previously determined that Manchester is solely responsible for
the costs of repairs to the level 12 unit property
and that, rather, previous
decisions were limited to the issue of the cost of common property repairs.
(b) That the Fogarty variation judgment and the variation appeal
judgment were limited to the question of Manchester’s contribution to
the common property on levels 1–11 and stand without determining
the
question of Manchester’s responsibility for the cost of repairing level 12
unit property.
- [133] Sage took
no position on the arbitration appeal.
Legal
principles – issue estoppel and abuse of process
- [134] The Body
Corporate relies upon Hoystead v Commissioner of Taxation to assert that
a fundamental factual admission made in litigation cannot be subsequently
withdrawn in an attempt to obtain a different
decision, even where the original
factual assumption was erroneous or mistook the legal quality of the
fact.78 Accordingly, the Body Corporate argues that because
Manchester conducted earlier litigation on the basis that the scheme, if varied,
would require Manchester to pay for the costs of repair to its unit property and
contribute 11.88 per cent to common property repairs,
it cannot now depart from
that admission/assumption.
- [135] The Body
Corporate also relies upon Virgin Airways Ltd v Zodiac Seats UK Ltd for
the proposition that:79
Except in special circumstances where this would cause injustice, issue
estoppel bars the raising in subsequent proceedings of points
which (i) were not
raised in the earlier proceedings or (ii) were raised but unsuccessfully.
- [136] In
particular, the Body Corporate submits that where a “party against whom a
judgment has been made has failed to raise
some question [they] could have
raised, the judgment includes a decision on the omitted question.”80
Accordingly, Manchester failed to satisfy their positive obligation to
raise their arguments in the earlier proceedings, and in doing
so now is simply
conducting a collateral attack on the earlier and final decision.
78 Hoystead v Commissioner of Taxation [1926] AC 155 (PC)
at 165-166.
79 Virgin Atlantic Airways Ltd v Zodiac Seats UK Ltd [2013]
UKSC 46, [2014] AC 160 at [22].
80 Shepherd v Disputes Tribunal [2004] NZAR 319 (HC) at
[35].
- [137] In
contrast, Manchester submits that an issue estoppel only arises where a judgment
has determined an issue as an essential
and fundamental step in the logic of the
judgment and without which it cannot stand.81 In particular,
Manchester argues that the Court should be cautious in finding issue estoppel
and alert to unfairness caused by a “too
ready application of issue
estoppel principles”.82
- [138] Manchester
also disputed that it breached a positive obligation to raise its arguments in
the earlier proceedings. Rather, Manchester
argued that this Court must apply
a:83
broad, merits-based judgment which takes account of
the public and private interests involved and also takes account of all the
facts
of the case, focusing attention on the crucial question whether, in all
the circumstances, a party is misusing or abusing the process
of the court by
seeking to raise before it the issue which could have been raised before.
- [139] Manchester
submits that the emphasis in Hoystead v Commissioner of Taxation is on
“fundamental” facts and does not apply to facts which are only
subsidiary or collateral.84 Manchester also submits that the
rationales behind issue estoppel are less powerful in an interlocutory
context.
- [140] On the
facts, Manchester submits that no previous court has determined the issue of
apportionment of costs to repair Manchester’s
private property on level 12
between it and other unit holders under cls 10.3 or 21.2 of the Scheme and,
therefore, no issue estoppel
or abuse of process arises. Manchester claims that
treatment of these issues by previous courts, if any, was insufficient or
contradictory
to a finding of issue estoppel.
Discussion
– The arbitration appeal
- [141] There is a
general presumption of non-intervention by courts in arbitral proceedings, and
this is enforced by art 5 in sch 1
of the Arbitration Act 1996. However, art
16(3) of that schedule expressly provides scope for parties to appeal
- Greymouth
Petroleum Holdings Ltd v Empresa Nacional Del Petróleo [2017] NZCA
490, [2017] NZAR 1617 at [51].
- See
Arbuthnot v Chief Executive of the Department of Work and Income [2007]
NZSC 55, [2008[ 1 NZLR 13 at [29].
83 Johnson v Gore
Wood & Co (a firm) [2002] 2 AC 1 (HL) at 31.
84 Blair v Curran [1939] HCA 23; (1939) 62 CLR 464
arbitral awards on jurisdiction to this Court. As the Body Corporate filed their
originating application appealing the arbitral award
within the 30 days required
by art 16(3), I therefore have jurisdiction to hear this matter. Contrary to
Manchester’s claim,
Mr Keene’s award as to jurisdiction is not res
judicata in this proceeding, as such an approach would clearly defeat the
intended
appellate function within art 16(3), sch 1 of the Arbitration Act
1996.
- [142] As a
result of conclusions I have reached with regard to the effect of the scheme,
and now recorded in the declarations set
out below, my discussion of the
arbitration appeal can be relatively brief. It is apparent that
Manchester’s attempt to arbitrate
the effect of cl 10.3 not only fell
outside the dispute resolution provisions in the scheme but was, as the Body
Corporate submitted,
nothing more than a collateral attack on the Fogarty
variation judgment and variation appeal judgment.
- [143] With
regard to the first of these issues, I accept the Body Corporate’s
submission to Mr Keene that the dispute fell outside
the scope of the dispute
resolution clause. The jurisdiction to arbitrate disputes arising from the
scheme pursuant to cl 13 is in
fact limited:
- 13.1 The Body
Corporate’s decision shall be final in respect of all matters arising
under this scheme, except where 5 or more
Owners whose objection in monetary
value cumulatively exceeds $30,000, or where one Unit Owner has an objection
which in monetary
terms exceeds
$10,000. Upon receiving notice of
such an objection, the Body Corporate shall refer the matter to arbitration.
- 13.2 The
objecting Owners must give notice to the Body Corporate of their objection
within 15 working days of receiving an assessment
as to Costs or other notice
from the Body Corporate which is the subject of the objection outlining the
grounds on which such objection
is made. On receipt of the notice the Body
Corporate will refer the matter to an arbitrator (to be appointed by the
President of
the Quantity Surveyors Association) and the arbitrator shall
determine the issue under the provisions of the Arbitration Act 1996.
The
arbitrator’s decision shall be final and the costs of the arbitration
shall be borne as between the objecting Owners and
the other members of the Body
Corporate generally as the arbitrator shall decide.
- 13.3 No Owner
shall be entitled to withhold payment of a Levy on the basis that the matter is
in the process of dispute resolution.
- [144] As can be
seen, a prerequisite for the dispute resolution provisions to be invoked and a
dispute referred to an arbitrator is
a decision of the Body Corporate.
There was no decision of the Body Corporate in this case. What was at issue was
the effect of the scheme itself following the variation
which had already been
determined by this Court and the Court of Appeal over Manchester’s
specific objections, and in no sense
could the variation be considered a
decision of the Body Corporate. It follows that the terms of this scheme and in
particular the
ambit of liability are matters for the Court rather than for
arbitration.
- [145] Likewise,
in determining that he had jurisdiction, Mr Keene failed to understand the
default scheme of the 1972 Act which both
the Fogarty variation judgment
and the variation appeal judgment confirmed was in place as a result
of the variation. As has been detailed in this judgment, the default scheme is
reflected by cls
10.1 and 10.2 of the scheme such that the scheme permits no
argument as to the scope of Manchester’s liability as a result
of cl 10.3.
Indeed, I note that Mr Keene did not even mention either cls 10.1 or 10.2 in his
decision but appeared to treat 10.3
as a standalone provision which meant that
his analysis of both the Fogarty variation judgment and variation
appeal judgment were manifestly in error. On the contrary, as I have found
earlier in this judgment, the meaning and effect of the earlier judgments
was
clear and effected by the changes Fogarty J made to the scheme in effecting the
variation. It follows that the attempt to arbitrate
a different interpretation
of cl 10.3 did amount to a collateral attack on the earlier judgments and were
therefore an abuse of process
such that an appeal must be allowed, and the
orders made by Jagose J made permanent.
- [146] In the
alternative, even if I am I am wrong in concluding that the initiation of the
arbitration was outside cl 13 or otherwise
amounted to an abuse of process,
given the conclusions reached with regard to the meaning and effect of the
scheme in my consideration
of the cross applications, the arbitration is in any
event rendered effectively moot such that a permanent extension of the Jagose
J
injunction would have been warranted.
Decision
- [147] For
the reasons set out above, I make the following declarations as to the effect of
the scheme:
(a) With regard to remedial work undertaken on Manchester’s unit, the
costs are to be borne solely by Manchester pursuant to
cl 10.1 of the scheme,
subject to any claims Manchester may have pursuant to cl 21.2 of the scheme.
(b) With regard to remedial work undertaken to the common property on level 12,
the costs of remediation are to be borne according
to unit entitlement pursuant
to cl 10.2, subject to any claims Manchester may have pursuant to cl 21.2 of the
scheme.
(c) It is only at the junction between Manchester’s unit property and
common property that cl 10.3 can have any application.
Given the clear effect of
cls 10.1, 10.2 and 21.2–21.4, it is not a provision that can be used to
claim contribution from the
other owners in the building to repairs to
Manchester’s unit.
- [148] Clause 13
of the scheme is varied as set out in the schedule annexed to this judgment, and
leave is reserved for the Body Corporate
to apply for any further variation
necessary to effect completion of the remediation of level 12 in the event
Manchester does not
obtain a code compliance certificate within six months of
the date of this judgment.
- [149] The appeal
by the Body Corporate against the Keene Award is allowed. The orders made by
Jagose J on 7 February 2019 are made
permanent.85
- [150] The Body
Corporate is entitled to costs against both Manchester and Sage on both the
cross applications and the arbitration
appeal, and I leave open whether there
are other individuals or entities against whom costs might be claimed. If costs
cannot be
agreed, the submissions of the Body Corporate setting out the
individuals and/or entities against whom costs are sought are to be
filed by 25
June 2024, and those individuals and/or entities against whom costs are sought
will have until 3 July 2024 to respond.
Depending on the issues raised, I will
determine whether a hearing is necessary or whether I will determine the issue
of costs on
the papers.
85 See above at [40].
- [151] Leave is
reserved for either party to seek such further directions as may be necessary to
give effect to the orders made in
this judgment.
Powell J
Schedule
Variations to cl 13 of the Scheme
[Changes Italicised]
- Dispute
resolution
- 13.1 The Body
Corporate’s decision shall be final in all respect all matters arising
under this scheme, except where 5 or more
Owners whose objection in monetary
value cumulatively exceeds $30,000, or where one Unit Owner has an objection
which in monetary
terms exceeds
$10,000. Upon receiving notice of
such an objection and subject to cl 13.4, the Body Corporate shall refer
the matter of arbitration.
- 13.2 The
objecting Owners must give notice to the Body Corporate of their objection
within 15 working days of receiving an assessment
as to Costs or other notice
from the Body Corporate which is the subject of the objection outlining the
grounds on which such objection
is made. On receipt of the notice the Body
Corporate will refer the matter to an arbitrator (to be appointed by the
President of
the Quantity Surveyors Association) and the arbitrator shall
determine the issue under the provisions of the Arbitration Act 1996.
The
arbitrator’s decision shall be final and the costs of the arbitration
shall be borne as between the objecting Owners and
the other members of the Body
Corporate generally as the arbitrator shall decide.
- 13.3 No Owner
shall be entitled to withhold payment of a Levy on the basis that the matter is
in the process of dispute resolution.
Arbitration of Manchester’s objections
- 13.4 In the
event a notice of objection is given by, for, under or on behalf of Manchester,
arising out of or otherwise derived from
any rights provided to or claimed by
Manchester under this scheme including any claim based on any claim or
entitlement arising out
of cl 21.2, the dispute is not to be referred to an
arbitrator unless:
(a) the notice of objection is given within 20 working days of a code
compliance certificate being issued in respect of all works
on level 12 and 13;
and
(b) Manchester or the person or entity claiming for, under or on behalf of
Manchester has paid to the Body Corporate prior to the
notice of objection being
issued:
(i) all levies currently outstanding for level 12 (and 13 (if any)) at the
date of the notice of objection;
(ii) the judgment sum of $321,264.79 (plus GST if any) ordered by Fogarty J
to be paid by Manchester to the Body Corporate ([2017]
NZHC 329); and
(iii) all costs awarded against Manchester in favour of the Body Corporate
and unpaid at the date of the notice of objection.
- 13.5 For
avoidance of doubt any dispute as to whether notice has been given in time
pursuant to cl 13.4(a) or that all amounts have
been paid pursuant to cl 13.4(b)
are not matters for arbitration pursuant to cl 13 but fall within the leave
reserved provisions
of the judgment of Powell J dated 23 May 2024 ([2024] NZHC
1280).
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2024/1280.html