NZLII Home | Databases | WorldLII | Search | Feedback

High Court of New Zealand Decisions

You are here:  NZLII >> Databases >> High Court of New Zealand Decisions >> 2024 >> [2024] NZHC 1280

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Body Corporate 172108 v Meader [2024] NZHC 1280 (23 May 2024)

Last Updated: 13 June 2024

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
I TE KŌTI MATUA O AOTEAROA TĀMAKI MAKAURAU ROHE

CIV-2009-404-6868
BETWEEN
BODY CORPORATE 172108
Applicant
AND
MEADER & ORS
(MANCHESTER SECURITIES LIMITED) 37TH RESPONDENT

CIV-2019-404-1445
BETWEEN
BODY CORPORATE 172108
Applicant
AND
MANCHESTER SECURITIES LIMITED
Respondent
Hearing:
14-18 November 2022
Appearances:


Further submissions completed:
J B Orpin-Dowell and T J G Allan for Applicant
K C Francis and T P Westaway for 37th Respondent (Manchester Securities Ltd (in liquidation))
J D Haig for 43rd Respondent (Sage Securities Ltd)

13 December 2022
Judgment:
23 May 2024

JUDGMENT (No.4) OF POWELL J

This judgment was delivered by me on 23 May 2024 at 4.00 pm.

Pursuant to R 11.5 of the High Court Rules.

.......................

Registrar/Deputy Registrar

Solicitors:

Grove Darlow & Partners, Auckland Lindsay Francis, Auckland

Paul Cheng & Co, Wellington

Counsel:

J Orpin-Dowell, Wellington J D Haig, Wellington

BODY CORPORATE 172108 v MEADER & ORS [2024] NZHC 1280 [23 May 2024]

Introduction [1]

Relevant background [13]

The approval of the initial scheme [17]

The remediation commences [23]

The variation [25]

Manchester changes approach [36]

The cross applications [47]

The applications in issue [48]

The position of the Body Corporate [50]

The position of Manchester [51]

The position of Sage [57]

What was the original effect of the scheme? [61]

The Fogarty variation judgment [67]

Did the variation remove the 11.88 per cent cap? [71]

Is any further variation required? [95]

Is a declaration required? [122]

Conclusion — cross applications [127]

The arbitration appeal [128]

Legal principles – issue estoppel and abuse of process [134]

Discussion – The arbitration appeal [141]

Decision [147]

Introduction

(a) cross applications by the Body Corporate and Manchester seeking declarations as to the effect of the cost allocation provisions in the scheme or, in the alternative, variations to the scheme to reflect their respective contentions as to the appropriate effect of the scheme (“the cross applications”); and

(b) an appeal by the Body Corporate against a preliminary determination by an arbitrator, Brian Keene KC,4 that he had jurisdiction to proceed

  1. Body Corporate 172108 v Meader (Nos 2 & 3) [2010] NZHC 1647; (2010) 12 NZCPR 181 (HC) [Heath judgment No 2] and [Heath judgment No 3].
  2. Body Corporate 172108 v Manchester Securities Ltd [2017] NZHC 329 [Fogarty variation judgment].
  3. It is noted that works undertaken by Manchester on level 12 have resulted in the addition of a small 13th floor. The evidence established there are now three apartments in total under construction on levels 12 and 13. As collectively all three apartments come under the same title held by Manchester, all references to Manchester’s private property on level 12 include the new construction at level 13 unless the context specifically requires otherwise.

4 Partial Award on Arbitrator’s Jurisdiction dated 25 October 2018 [Keene Award].

with an arbitration to interpret the effect of cl 10.3 of the scheme (“the arbitration appeal”).

  1. The evidence showed to date Manchester had received some $2 million in settlement from Auckland City in respect of the weathertightness issues and has borrowed close to $11 million from Sage. In addition, it is not in dispute that Manchester has not paid the Body Corporate approximately $1.5 million owing in levies and Court judgments over the same period.
million (exclusive of GST) on level 12 as at March 2022,6 and has throughout been in receipt of plentiful expert advice.

  1. By Mr Cummins figures as at 31 March 2022, the total amount expended by Manchester on level 12 was $8,788,632.94 (exclusive of GST) consisting of remediation/repairs of $6,588,593.63, “betterment” of $1,974,914.42 and “wasted expenditure” of $225,124.89.

7 See above at [5].

8 See below at [15], [20], [21] and [23].

  1. Fogarty variation judgment, above n 2, at [147]; and Manchester Securities Ltd v Body Corporate 172108 [2017] NZCA 527, (2017) NZCPR 65 [variation appeal judgment] at [44]; and Manchester Securities Limited v Body Corporate 172108 [2019] NZCA 408 at [39]; Cummins v Body Corporate 172108 [2022] NZCA 68 at [69]; and Cummins v Body Corporate 172108 [2022] NZHC 774 at [127].

10 Heath judgment No.2, at [6]; and see below at [21]-[22].

provided to Manchester has far exceeded any rational limits, as has its failure to enforce its mortgage security over level 12 in a timely manner, with the result that Sage’s only hope to recover any of the monies advanced to Manchester is through supporting Manchester’s claims for contribution against the Body Corporate and the other owners of the building.

Relevant background

The approval of the initial scheme

...

(a) [Manchester] does not consider that the Body Corporate should have any decision-making role in respect of remediation to Unit 12A;

(b) remedial works have not been defined in sufficient detail and too broad a discretion is conferred upon the Body Corporate in relation to management of the proposed construction work; and

11 Body Corporate 172108 v Meader [2010] NZHC 187; (2010) 12 NZCPR 101 (HC) (“Heath judgment No.1”), at [4].

(c) a more equitable apportionment of cost is required. [Manchester] considers that the work to be undertaken on its own property is “relatively minor”, as opposed to “the major re-cladding work apparently required on the remainder of the building”.

[Manchester] intends to carry out significant alterations to level 12 in the foreseeable future. Level 12 has 35 metres of air space rights around and above the Building and essentially owns the roof. I have investigated various development options for the property to take advantage of these rights, such as expanding [Manchester’s] property by creating a second storey or creating a self contained apartment. CoveKinloch has prepared concept plans for such a development for [Manchester]. Inevitably any development of this type would result in substantial changes to the roof area, quite apart from other structural considerations. The consent of the [the Council] would be required and significant cost would be involved.

Until these options are evaluated, I believe only remedial work that is necessary to keep the Building watertight should be undertaken on level 12.

[Manchester] recognises that it is obliged under the Unit Titles Act 1972 (see the default Body Corporate rules in Schedule 2, particularly Rule 1(e)) to repair and maintain its unit property on level 12 in sufficiently good condition such that no damage or harm shall ensue to the common property or any other unit in the Building. There should be no suggestion that [Manchester] is not willing to meet its obligations in this respect. To date [Manchester] has carried out all interim work recommended by CoveKinloch and has done so in a timely manner.

12 Heath judgment No 1, above n 13, at [31].

13 At [30]–[33].

on levels 1–11.14 Specifically, on the information available at that time, Heath J understood that the total cost of repairs to levels 1–11 was estimated to be around

$5,750,00015 and the cost of repairs to level 12 around $500,000, a total of

$6,250,000.16 As Manchester’s share was 11.88 per cent, this would see Manchester contributing approximately $242,500 to the cost of repairs to common property on levels 1–11 in addition to completing the repairs to level 12.17

The remediation commences

14 At [49].

15 It is unclear whether this sum included the cost of repairs to private property on levels 1–11.

16 At [47].

17 At [47]–[49].

18 Heath judgment No 2 and Heath judgment No 3, above n 1.

19 Fogarty variation judgment, above n 2, at [80]–[81].

The variation

  1. Body Corporate 172108 v Manchester Securities Ltd [2013] NZHC 2441, (2013) 14 NZCPR 745 at [2].

21 At [25].

22 Fogarty variation judgment, above n 2, at [82].

23 At [148].

15).”24 His Honour noted that the law had developed since the scheme was originally approved, with particular reference to the decision of the Court of Appeal in Tisch v Body Corporate 318596,25 which Fogarty J considered he was required to follow.26

Manchester shall pay the cost of repairs of common property to all levels calculated in accordance with the units entitlement (now known as ownership interest) of Manchester’s unit.

24 At [30].

25 Tisch v Body Corporate 318596 [2011] NZCA 420, [2011] 3 NZLR 679.

26 Fogarty variation judgment, above n 2, at [66].

27 At [156].

28 At [157].

in the sum of $321,264.79 (plus GST).29 This was calculated by identifying Manchester’s contribution to the cost of repairs to the common property on levels 1–11 based on unit entitlement ($513,247.60 excluding GST)30 less the contribution of the other owners to the estimated cost of repairs to the common property on level 12 ($191,982)31, a total of $321,264.79 (excluding GST). This sum was “to be adjusted upon completion of remediation of the common property on level 12, to the extent that the [estimate relied upon] varies [from the actual cost].”32 Justice Fogarty commented that the judgment sum would be “a minimum cost that Manchester will have to pay in contribution to the remedial works of common property on level 12”.33

[51] ...was to reinstate the default statutory scheme regarding cost allocation, thereby rendering unit owners liable to contribute to the remediation of common property on the basis of their unit entitlement.

(footnotes omitted)

29 At [157].

30 Being 11.88 per cent of $4,320,266 (excluding GST).

31 Being the then estimated cost of repairs to the common property on level 12 ($217,865.20) less Manchester’s contribution of 11.88 per cent. It is noted that the estimated cost of repairs was the higher of the estimates provided by the experts instructed by both the Body Corporate and Manchester of the costs of repairs to common property on level 12 if undertaken promptly. See Fogarty variation judgment, above n 2, at [150]–[155].

32 At [155].

33 At [153].

34 Variation appeal judgment, above n 10.

Manchester changes approach

11.88 per cent of the cost of replacing the roof, with the balance to be paid by the other owners of the building in accordance with their respective unit entitlement. At the same time, it was signalled that it was likely that Manchester would adopt a similar approach to the remediation of the external walls which were also part of Manchester’s unit property on level 12. Manchester requested that the Body Corporate “accepts Manchester’s apportionment approach for the roof or, if not, that the Body Corporate will promptly appoint an arbitrator to solve the matter.”

Does clause 10.3 apply to apportion the cost of repair of the unit property [at] level 12 among all owners by unit entitlement, or has the High Court and/or

35 At [69].

36 Manchester Securities Ltd v Body Corporate 172108 [2018] NZSC 19.

the Court of Appeal determined that Manchester alone must pay the cost of repair of unit property at level 12? (“the Dispute”)

...the variation decision did not determine the allocation of unit property repair costs (at any level of the building) or that Manchester is to be solely responsible for the cost of repairs to the unit property at level 12.

37 Keene Award, above n 4, at [12.1].

38 Body Corporate 172108 v Meader [2018] NZHC 3356 at [22].

39 Body Corporate 172108 v Manchester Securities Ltd [2018] NZHC 3307; Manchester Securities Ltd v Body Corporate 172108, above n 12; and Body Corporate 172108 v Manchester Securities Ltd [2020] NZHC 198; and Cummins v Body Corporate 172108 [2021] NZCA 145, [2021] 3 NZLR 17.

40 Body Corporate 172108 v Manchester Securities Ltd [2020] NZHC 198 at [43].

pursuit of this course of action ultimately substantially delayed the hearing of the present proceedings.41

$5,084,418.64 as at 31 March 2022, plus interest. It would follow that those same owners would also have to pay 88.12 per cent of the estimated $1.6 million required to complete the remediation of level 12.

41 Body Corporate 172108 v Manchester Securities Ltd [2021] NZHC 365; Body Corporate 172108 v Manchester Securities Ltd [2021] NZHC 686; Cummins v Body Corporate 172108 [2022] NZCA 68; Cummins v Body Corporate 172108 [2022] NZCA 153; and Cummins v Body Corporate 172108 [2022] NZSC 95.

42 Body Corporate 172108 v Flat Bush Finance Ltd [2020] NZHC 3135, (2020) 21 NZCPR 622.

43 Cummins v Body Corporate 172108, above n 43, at [69].

The cross applications

The applications in issue

(a) declaratory relief that Manchester is estopped from seeking to apportion the costs of repairing its unit property on level 12 between it and the other unit holders under cls 10.3 and 21.2 of the scheme as it says to do so is a collateral attack on the variation decision; or

(b) in the alternative, a series of interlocking alternative variations to the scheme that would restrict Manchester’s ability to claim contributions from the Body Corporate or other owners of the building towards the cost of repairs to level 12.

The position of the Body Corporate

The position of Manchester

10.3 of the scheme which provides:

...where repairs involve both Units and Common Property, the Costs of such Repairs shall to the extent possible be apportioned to each Owner on the basis of that owner’s legal title to part of the Building.

10.3 was never clearly determined. On the contrary there has been no final determination of the apportionment of costs of repairs to Manchester’s unit property on level 12 between it and other unit holders with regard to cls 10.3 and 21.2. On

44 This is according to Mr Cummins’s calculation which calculates Manchester’s liability based on the 11.88 per cent of the total costs repairs to the building. His calculation of the cost of repairs to level 1-11 was $7,070,437.00 (exclusive of GST) less a sum described as “per Doogue J” of

$997,625.00 which is not explained, nor apparent from the one judgment of Associate Judge JP Doogue issued in connection with the proceeding. It is noted that for its part the Body Corporate has only sought an 11.88 per cent contribution from Manchester to the repairs of the common property on levels 1-11 (11.88 per cent of $4,320,266 (excluding GST) which as noted at [23] above was 61 per cent of the total cost of the repairs to levels 1-11). See Fogarty variation judgment, above n 2, at [81] and [102], and the variation appeal judgment above n 10, at [24].

45 See [45] above.

behalf of Manchester, Mr Francis disputed that the Fogarty variation judgment had determined that Manchester has to contribute the costs of remediation of common property in accordance with its unit entitlement while having to pay for remediation to its own level 12 unit. In Mr Francis’ submission, nowhere in either the Fogarty variation judgment or the variation appeal judgment does either the High Court or the Court of Appeal state that Manchester alone is responsible for all costs in relation to its unit property.

  1. An undertaking given by Manchester in the course of the hearing before Jagose J and reasserted before me. See Body Corporate 172108, above n 42, at [13].
reimposition of an 11.88 per cent cap in Manchester’s liability on the grounds that the variation removed the cap and was unfair to Manchester. Instead Manchester submitted it is appropriate for the other owners in the building to contribute to the costs of remediating Manchester’s property on level 12 as well as the common property throughout the building because they all benefit from that work taking place.

The position of Sage

the building to fund the completion of the remediation so that the level 12 apartments could be sold.

What was the original effect of the scheme?

47 Heath judgment No 3, above n 1, at sch A.

as Fogarty J noted even then apportionment between common property and unit property can be carried out relatively precisely.48

(a) the carrying out of Repairs to level 12 as contemplated by the Building Consent by Manchester; and

(b) Manchester’s share of the total Cost of the Repairs of the entire Building

48 See below at [87] and fn 69.

$242,500) would be paid towards the costs of repairs to common property in the rest of the building.50 A similar illustration was provided by Fogarty J when considering the effect of the cost blow-out on level 12 on the original scheme. At that point, when the estimated cost of the repairs to level 12 had blown out to $2.3 million (an increase of some 460 per cent),51 the effect of the 11.88 per cent cap imposed by Heath J was that not only would Manchester not be required to make a contribution to the cost of common property repairs on levels 1–11, but the other owners in the building would be required to pay Manchester for the cost of both its repairs to its unit on level 12 and the common property on level 12 once the cost of those repairs exceeded 11.88 per cent of the cost of repairs to all levels.52

The Fogarty variation judgment

49 Although as noted in n 48 this seems to be what Mr Cummins is now saying.

50 Heath judgment No 1, above n 13, at [49].

  1. Not 430 per cent as stated by the Court of Appeal in the variation appeal judgment, above n 10, at [26].

52 Fogarty variation judgment, above n 2, at [67].

type imposed by Heath J was no longer appropriate.53 Instead the scheme of the 1972 Act was to be applied with regard to cost allocation.54 As Fogarty J explained:55

The Court is guided, as it must be, by the reasoning of the Court of Appeal in Tisch. The effect of that reasoning is that the Court cannot lightly depart from the scheme of the Unit Titles Act. At the core of that scheme is the proposition that repair and maintenance of common property is a burden shared by all unit holders in proportion to the unit entitlement. It matters not what other costs such unit holders have to bear in respect of repair and maintenance to their units.

It is not open to Manchester to now contend that whether it was liable to pay for the cost of repairs to its unit property on level 12 was not an issue before Fogarty J. The whole point of Manchester’s position was that because it had to pay for repairs to its unit property on level 12, the 11.88 per cent cap was exceeded and other unit owners therefore had to make a contribution to the cost of repairing its unit property. The issue Forgarty J had to decide was whether Manchester’s liability should remain limited to 11.88 per cent or whether there should be a return to the default statutory scheme under which it would pay 11.88 per cent of common property repairs, plus the cost of repairing its unit property. This is exactly how the Court of Appeal understood the position: see [56]-[57] above.

53 See above at [26]–[31].

54 Fogarty variation judgment, above n 2, at [30].

55 At [78].

56 Tisch v Body Corporate No 318596, above n 27.

57 Young v Body Corporate 120066 [2007] NZHC 1401; (2007) 8 NZCPR 932.

58 Fogarty variation judgment, above n 2, at [57].

His Honour amended cls 12.2 and 21.4 by removing any reference to the 11.88 per cent figure and inserting replacement wording, so that the relevant parts of cl 21 now read:59

(a) the carrying out of Repairs to level 12 as contemplated by the Building Consent by Manchester; and

(b) Manchester’s share of the total Cost of the Repairs of the entire Building.

(emphasis added to replacement wording)

59 It should be noted that the scheme was not reprinted in full following the Fogarty variation judgment. Instead the sealed order following the judgment indicates the specific words to be deleted and the words that replaced them in cls 21.2 and 21.4 respectively.

Did the variation remove the 11.88 per cent cap?

By any measure, the proposed order, in bluntly removing the cap, has a major financial impact on Manchester. In percentage terms, it would increase Manchester’s share of the repair costs from 11.88% (the cap) to approximately 28% (on the costings before the Court with the adjustment sought by the Body Corporate). In dollar terms, Manchester’s contribution would increase from

$1,104,840 (11.88% of circa $9.3 million) to $2,624,296 (2,203,231 as estimated by Mr Maddren plus the immediate payment of $321,265 that the Body Corporate seeks).

(emphasis added)

$2,303,231) together with its 11.88 per cent share of repairs to the common property represented by the figure of $321,265. At the invitation of Fogarty J, the Body Corporate confirmed it too understood the effect of the judgment in the same way. Justice Fogarty declined to call for the further submissions sought by Manchester, instead noting:61

  1. Body Corporate 172108 v Manchester Securities Ltd HC Auckland CIV-2009-404-6868, 22 September 2016 (Draft judgment No 1) at [152]–[153].

61 Body Corporate 172108 v Manchester Securities Ltd CIV-2009-404-006868, 7 December 2016.

...it was undeniably part of the logic of the scheme that Manchester would benefit from the common property repairs to levels 1–11 and therefore should make some contribution to the cost of those repairs. That was the whole purpose of the formula. We are confident Heath J would never have sanctioned a scheme whereby Manchester paid nothing for that benefit but instead received a windfall at the expense of the other unit holders.

(footnotes omitted)

[T]he scheme as varied will relieve the other owners from costs they would have incurred if the Body Corporate had been free to carry out all repairs under a single contract, free from delays by Manchester (such costs being over

$1,000,000).

62 Variation appeal judgment, above n 10, at [29](f).

63 At [41].

64 At [54]–[55].

Instead of directing that the additional costs of dilatory remediation be quantified and borne by Manchester alone, the scheme as varied effectively releases the other owners from making any contribution to the substantial costs that they would otherwise have occurred.

In an effort to avoid Manchester enjoying a “windfall” from having the common property repaired, the scheme as varied gives the other owners far greater windfall at Manchester’s expense because they no longer have to contribute anything to replacing the roof and other unanticipated exterior property repairs for which they would have been liable under the original scheme.

Given retroactive effect, this seemingly simple variation shifted huge costs onto Manchester that were in no way attributable to the “consequences” of dilatory remediation. Under the original scheme, for example, all owners would have had to contribute to the costs of replacing the roof (some

$622,000). Now, even though no one could suggest that the need to replace the defective roof is attributable to dilatory remediation, the varied scheme shifts the entire cost to Manchester alone.

(footnote omitted)

consider a variation to the scheme to reflect the intention of the variation as set out in those earlier judgments.

65 Faloon v Planning Tribunal at Wellington [2020] NZCA 170 at [2].

66 See above at [73]–[77].

67 See above at [74].

68 See above at [62]–[63].

11.69 As a result, it is wholly clear that cl 10.3 does not provide a basis for Manchester

to claim some sort of overall contribution by the other unit owners for work undertaken to Manchester’s unit property on level 12. Specifically, it does not provide a vehicle to enable Manchester or Mr Cummins to attempt to argue that all of the monies (however unwisely) expended by Manchester on level 12 and, in particular, to the roof and exterior walls, which are clearly unit property owned by Manchester, can be apportioned according to unit entitlement.

69 There is a lengthy discussion in the Fogarty variation judgment about the apportionment of the cost of repairs to private property and common property on levels 1–11. In the course of determining that the repairs to common property contributed 61 per cent of the repairs undertaken by the Body Corporate, Fogarty J noted the evidence before him of “specific examples of different splits” including where particular window joinery was identified as 96 per cent common property and 4 per cent to the unit; Fogarty variation judgment, above n 2, at [87]–[102].

that the costs of repairs to the unit property on level 12 by Manchester should not be paid for by Manchester. On the contrary, Manchester was, in terms of the scheme as varied, required to undertake all of the repairs, both to its own unit and to the common property on level 12, and was required to separately assess and pay for “the cost of repairs to the Units and Common Property situated on level 12”.

Manchester shall pay the cost of repairs of common property to all levels calculated in accordance with the unit entitlement (now known as ownership interest) of Manchester’s unit provided however that any Costs incurred by Manchester in respect of project management consultants or other construction-related advisors that do not provide benefit to all other individual proprietors or the body corporate shall be borne solely by Manchester. The costs in respect of project management consultants or other construction-related advisors that Manchester contends provide a benefit to all individual proprietors (other than Manchester) or the body corporate shall be made available in writing, together with supporting documentation to the secretary of the body corporate. Any dispute about whether benefit is provided to all individual proprietors (other than Manchester) or the body corporate shall be determined under the dispute resolution provisions of this Scheme.

(emphasis added)

construction-related advisors” claimed to come within cl 21.2 is $1,194,552.61 (excluding GST).70 It is thus at most only a reasonably small proportion of the total cost expended by Manchester on level 12. It is, in any event, not clear whether all invoices have been made available still less whether at any point any supporting documentation to justify why those costs benefit all of the other owners or the Body Corporate, and it therefore appears that any claim under cl 21.2 remains pending rather than actual.

70 According to Mr Cummins the total project management consultants or other construction-related advisors comes to $1,355,597.60 (excluding GST), from which he deducted Manchester’s 11.88 per cent share of those costs ($161,045.00).

(a) With regard to remedial work undertaken on Manchester’s unit, the costs are to be borne solely by Manchester pursuant to cl 10.1 of the scheme, subject to any decision Manchester may have pursuant to cl

21.2 of the scheme.

(b) With regard to remedial work undertaken to the common property on level 12, the costs of remediation are to be borne according to unit entitlement pursuant to cl 10.2, subject to any claims by Manchester pursuant to cl 21.2 of the scheme.

(c) It is only at the junction between common and unit property that cl 10.3 can have any application. Given the clear effect of cls 10.1,10.2 and 21.2–21.4, cl 10.3 is not a provision that can be used to claim contributions from the other owners in the building to repairs to Manchester’s unit on level 12.

Is any further variation required?

Manchester is estopped from seeking to apportion the costs of repairing its private property on level 12 between it and other unit holders whether under clause 10.3 of the Scheme or under clause 21.2 of the Scheme or otherwise, except in relation to the Body Corporate’s common property on level 12 and then only to the extent that this was specifically contemplated by the Maddren/Johnson difference in the [Fogarty variation judgment and variation appeal judgment].

works undertaken to level 12 as at March 2022 totalled nearly $9 million (GST exclusive) with a minimum of a further $1.6 million required simply to make level 12 weathertight and obtain a code compliance certificate. Even if allowance is made for the approximately $1.9 million “betterment” costs and for the “wasted expenditure” calculated by Mr Cummins (which has not been corroborated), and not allowing for any deductions for dilatory remediation by Manchester (which Manchester has not attempted to quantify), the total actual and estimated cost of repairs of approximately

$8.2 million (GST exclusive) is now not less than 1640 per cent greater than originally estimated to Heath J, and three and a half times the estimate provided to Fogarty J in 2016. As a result, and for the reasons set out in both the Fogarty variation judgment and the variation appeal judgment, the magnitude of the cost increases on level 12 by themselves justify retention of the scheme as varied by Fogarty J.

71 Including cls 21.2, 21.3 and 21.9 of the scheme.

continue to fund Manchester who, unfortunately for Sage, appears incapable of either completing the work required or repaying the monies advanced. The fact Sage has continued to support Manchester unconditionally has meant that it has actively contributed to the present unsatisfactory situation whereby the repairs to level 12 have not been completed, notwithstanding the amounts provided.

72 Variation appeal judgment, above n 10.

relating to the mediation scheme by Mr Cummins”. Any suggestion to the contrary is simply unbelievable in the context of this case, particularly given the amounts advanced by Sage to Manchester, and I reject his assertion outright.73

  1. Applying a similar approach to Eng Mee Yong v Letchumanan [1979] UKPC 13; [1980] AC 331(PC); see Krukziener v Hanover Finance Ltd [2008] NZCA 187, [2010] NZAR 307 at [26].

74 Body Corporate 172108 v Manchester Securities Ltd, above n 22.

(a) deleting cl 21 in its entirety, thereby restricting the ambit of any arbitration with regard to project management consultants or other construction-related advisors in terms of cl 21.2; or

(b) restricting the ambit of any arbitration on the level 12 costs of construction:

(i) “to the extent of the Maddren/Johnson difference specifically contemplated by the [Fogarty variation judgment and Variation appeal judgment]”; or

(ii) if not restricted solely to the extent of the Maddren/Johnson difference, to limit claims to project manager or construction-related advisor costs “solely in relation to the juncture of levels 11 and 12” incurred by Manchester “prior to the Body Corporate commencing its work to the juncture at levels 11 and 12” and with “[a]ll owners below level 12 [having to] receive the benefit”.

  1. Manchester Securities Ltd v Body Corporate 172108 [2018] NZCA 190, [2018] 3 NZLR 455 at [41]–[43].

76 See above at [54].

may ultimately attempt to prosecute any claims it may have by way of cl 13. I therefore consider it necessary to vary cl 13 to make it clear that no arbitration is to be commenced, by Manchester or deriving from Manchester’s claims, prior to issue of a code compliance certificate.

Is a declaration required?

to do so.77 In any event, the respective cross applications under s 48(6) necessarily engaged the jurisdiction of the Court to establish a scheme pursuant to s 48(1) and consequently the wide powers provided pursuant to s 48(5) which enables “the Court [to] make such orders as it considers expedient or necessary for giving effect to the scheme...”.

Conclusion — cross applications

The arbitration appeal

77 See Telecom Corporation of New Zealand Ltd v Commerce Commission [2012] NZCA 278 at [295], quoting from Lord Woolf and Jeremy Woolf Zamir & Woolf: The Declaratory Judgment (4th ed, Sweet & Maxwell, London, 2011) at [3–19].

(a) No Court has previously determined that Manchester is solely responsible for the costs of repairs to the level 12 unit property and that, rather, previous decisions were limited to the issue of the cost of common property repairs.

(b) That the Fogarty variation judgment and the variation appeal judgment were limited to the question of Manchester’s contribution to the common property on levels 1–11 and stand without determining the question of Manchester’s responsibility for the cost of repairing level 12 unit property.

Legal principles – issue estoppel and abuse of process

Except in special circumstances where this would cause injustice, issue estoppel bars the raising in subsequent proceedings of points which (i) were not raised in the earlier proceedings or (ii) were raised but unsuccessfully.

78 Hoystead v Commissioner of Taxation [1926] AC 155 (PC) at 165-166.

79 Virgin Atlantic Airways Ltd v Zodiac Seats UK Ltd [2013] UKSC 46, [2014] AC 160 at [22].

80 Shepherd v Disputes Tribunal [2004] NZAR 319 (HC) at [35].

broad, merits-based judgment which takes account of the public and private interests involved and also takes account of all the facts of the case, focusing attention on the crucial question whether, in all the circumstances, a party is misusing or abusing the process of the court by seeking to raise before it the issue which could have been raised before.

Discussion – The arbitration appeal

  1. Greymouth Petroleum Holdings Ltd v Empresa Nacional Del Petróleo [2017] NZCA 490, [2017] NZAR 1617 at [51].
  2. See Arbuthnot v Chief Executive of the Department of Work and Income [2007] NZSC 55, [2008[ 1 NZLR 13 at [29].

83 Johnson v Gore Wood & Co (a firm) [2002] 2 AC 1 (HL) at 31.

84 Blair v Curran [1939] HCA 23; (1939) 62 CLR 464

arbitral awards on jurisdiction to this Court. As the Body Corporate filed their originating application appealing the arbitral award within the 30 days required by art 16(3), I therefore have jurisdiction to hear this matter. Contrary to Manchester’s claim, Mr Keene’s award as to jurisdiction is not res judicata in this proceeding, as such an approach would clearly defeat the intended appellate function within art 16(3), sch 1 of the Arbitration Act 1996.

$10,000. Upon receiving notice of such an objection, the Body Corporate shall refer the matter to arbitration.

There was no decision of the Body Corporate in this case. What was at issue was the effect of the scheme itself following the variation which had already been determined by this Court and the Court of Appeal over Manchester’s specific objections, and in no sense could the variation be considered a decision of the Body Corporate. It follows that the terms of this scheme and in particular the ambit of liability are matters for the Court rather than for arbitration.

Decision

(a) With regard to remedial work undertaken on Manchester’s unit, the costs are to be borne solely by Manchester pursuant to cl 10.1 of the scheme, subject to any claims Manchester may have pursuant to cl 21.2 of the scheme.

(b) With regard to remedial work undertaken to the common property on level 12, the costs of remediation are to be borne according to unit entitlement pursuant to cl 10.2, subject to any claims Manchester may have pursuant to cl 21.2 of the scheme.

(c) It is only at the junction between Manchester’s unit property and common property that cl 10.3 can have any application. Given the clear effect of cls 10.1, 10.2 and 21.2–21.4, it is not a provision that can be used to claim contribution from the other owners in the building to repairs to Manchester’s unit.

85 See above at [40].

Powell J

Schedule

Variations to cl 13 of the Scheme [Changes Italicised]

  1. Dispute resolution

$10,000. Upon receiving notice of such an objection and subject to cl 13.4, the Body Corporate shall refer the matter of arbitration.

Arbitration of Manchester’s objections

(a) the notice of objection is given within 20 working days of a code compliance certificate being issued in respect of all works on level 12 and 13; and

(b) Manchester or the person or entity claiming for, under or on behalf of Manchester has paid to the Body Corporate prior to the notice of objection being issued:

(i) all levies currently outstanding for level 12 (and 13 (if any)) at the date of the notice of objection;

(ii) the judgment sum of $321,264.79 (plus GST if any) ordered by Fogarty J to be paid by Manchester to the Body Corporate ([2017] NZHC 329); and

(iii) all costs awarded against Manchester in favour of the Body Corporate and unpaid at the date of the notice of objection.


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2024/1280.html