Home
| Databases
| WorldLII
| Search
| Feedback
Court of Appeal of New Zealand |
Last Updated: 28 January 2019
IN THE COURT OF APPEAL OF NEW
ZEALAND C.A.289/96
BETWEEN IAN LUKE DUSTIN Appellant
AND JERZY BOLESLAW PESZYNSKI
and HAZEL JOAN PESZYNSKI
Respondents
Coram: McKay J Barker J Tipping J
Hearing: 18 February 1997
Counsel: F.B. Barton for appellant
L.A. Andersen for respondent
Judgment: 18 February
1997
JUDGMENT OF THE COURT DELIVERED BY BARKER
J
This is an appeal from a decision of Master Venning given in the High Court at Dunedin on 11 November 1996. This had been an interim judgment in which the Master had indicated that specific performance was the appropriate remedy for the plaintiffs. In a subsequent judgment delivered on 4 December 1996, the Master settled the
terms of the Court’s formal order of specific
performance.
The case concerns the interpretation of a clause in an agreement for sale
and purchase dated 14 May 1994 between the present respondents,
Mr and Mrs
Peszynski, as vendors and the appellant, Mr Dustin, as purchaser.
The appellant, a property developer, owned land adjoining Lake Dunstan in Central Otago which he wished to subdivide. The respondents also owned land adjoining Lake Dunstan; they indicated that they might possibly
wish to subdivide this land in the future. Under the agreement, the
appellant was to purchase a block of land from the respondents
which would yield
25 sections. Clearly, the advantage to him of purchasing this additional land
would be to spread the cost of development
over a greater number of
sections.
As part of the agreement between the parties, two clauses were included
which placed certain obligations on the appellant. The aim
of these clauses was
that the respondents would be able to connect any sections from their future
subdivision to services in the
subdivision being promoted by the
appellant.
Although the two clauses of this agreement for sale and purchaser were in
issue in the Master’s judgment, there is no argument
now concerning his
interpretation of
clause (1); the only contention relates to clause (2)
which reads -
“The purchaser agrees and undertakes to ensure that he will carry out his proposed subdivision both on the land sold herein and on his existing subdivision on the land adjacent to this property in such a manner as to ensure that all services such as water, sewage, power, telephone and stormwater shall be of such size and capacity to enable the vendor to carry out a subdivision of his own on his adjoining property of up to 100 sections. These services
shall not include any pump or pumps required except
that the purchasers service pumping facilities must
be able to cope with the first 20 of these sections.
The purchaser hereby agrees as further consideration
in respect of the signing of this agreement
(irrespective of its completion) that he will allow
the vendor to connect his property into these
services and grant to the vendor as and for
easements forever appurtenant to the vendors land
(section 66 block 4 Wakefield Survey District) such
easements as are required to bring all of the
abovementioned services from their closest point on
the purchasers adjoining land (section 17 block 4
Wakefield Survey District) to the southeast corner
of the vendors land. The purchaser shall at his
cost have his engineer certify that the size and
capacity of the services available to and in place
for the vendors land are as required for this clause
prior to the vendor being required to pass
title.”
The purchase price for the land was $400,000 plus GST to be paid as to
$20,000 plus GST upon the signing of the agreement; at that
time, the appellant
as purchaser was entitled to enter into possession. A further $200,000 plus GST
was payable on 28 February 1995;
the balance plus GST was payable on 31 January
1996 or earlier, at the option of the purchaser.
The contract also provided in the event that the second payment of
$200,000 due on 28 February 1995 was not paid on time, then the
only remedy
available to the vendors was to charge interest at the penalty rate until
payment was made. Although the deposit was
paid and the appellant entered into
possession, the second instalment of $200,000 due on 28 February 1995 has not
been paid; interest
continues to be charged thereon.
The appellants issued summary judgment proceedings
seeking payment of the unpaid purchase price plus arrears of interest. The Master quite rightly held that the payability of the money sought by the respondents was interdependent on the vendors’ obligation to provide title. It is unclear why summary judgment proceedings were issued which asked only for judgment for a monetary sum without any reference to the vendors’ corresponding obligation to give title. Anyhow, the Master rightly held that the proper remedy available to the respondents was that of specific performance; there is no dispute
over that conclusion of the Master.
Essentially, the interpretation of clause (2) revolves around the last sentence. The solicitors who drew up the agreement were acting for both parties. These solicitors were not the solicitors now acting for either
party. There was no consultation by them over the terms
of the agreement with Mr Potter the surveyor who organised the
subdivision for the appellant. It was unfortunate that such consultation
did not
occur over the requirement for a certificate.
One must look at the agreement as a whole, in particular, at clause (6)
of the special conditions; this clause speaks about certain
consequences of the
vendors’ proceeding with further subdivision of the balance of their
land. The expression in clause (6),
“should they proceed with further
subdivision of the balance of their land”, indicates that there was no
obligation on
the respondents ever to subdivide the balance of their land;
indeed, Mr Peszynski in his affidavit in the summary judgment proceedings
indicated that they had no present plans.
Although the clause refers to an “engineer’s”
certificate, affidavits from both sides came from registered surveyors
who
considered themselves competent in designing and servicing subdivisions; it
seems that their certificates would be acceptable
to the Central Otago Local
Authority. No point was taken of the fact that Mr Potter was not an
“engineer”, although one
would have thought that this term was
reasonably well known in contracts of this nature.
Mr Potter considered that he could not certify in terms
of clause (2) without considerable technical information, concerning particularly the form of the subdivision of
the respondents’ land. As noted by the Master, Mr
Potter required information about -
(a) The length of cable and voltage in relation to the power supply. Any
certificate about power would have to come from the local
electricity
authority;
(b) The nature and siting of the subdivision to enable calculation of the
pressure required for water supply;
(c) The elevation of allotments in order to confirm sewerage
service;
(d) Stormwater services; there is no piped stormwater service upon the
appellant’s existing subdivision.
Mr Potter also noted the implication of certifying that the services were sufficient, given the potential of a subdivision of up to 120 sections. However,clause (2) speaks only of 100 sections; one would have thought that the certificate should only relate to a subdivision of
100 sections maximum. Mr Potter was also justifiably concerned about his
possible civil liability; for that
reason, he did not consider it prudent to give a certificate until he had
sufficient detail of any subdivison.
Against that evidence, Mr Hughes, another Cromwell surveyor, made an
affidavit to the effect that it was possible for the certificate
required by
clause (2) to be given; that a subdivisional concept plan, actually provided by
the respondents, would be adequate for
calculating design
requirements.
As noted by the Master, it was not claimed by the appellant that the
condition in clause (2) was impossible to perform or that the
contract was
frustrated. Correspondence shows that various attempts were made to ascertain
the intention of the respondents with
regard to the subdivison of the balance of
their land; the contention was made throughout by the appellant that no engineer
could
give a certificate until certain information was known.
The question for this Court, as it was for the Master, is one of the
proper construction of clause (2). The clear intention of the
clause, as the
Master found, was to enable the respondents to have the benefit of services such
as water, sewerage etc installed
by the appellant on his subdivision, available
for any future subdivision
they may choose to undertake. By entering into the contract, the appellant accepted the obligation at his cost to have his engineer certify the size and capacity of the services available to enable the respondents to
carry out a subdivision of up to 100 sections. There is no reference to
the respondents being required to submit the concept plan
or indeed any
information.
In our view, to give the clause meaning and business efficacy, it would be incumbent on the respondents to make it possible for the appellant’s expert or engineer
to enter on their land if necessary to check measurements or ascertain
such other technical information as might be required. That
is not to say there
is any financial obligation on the respondents to obtain professional assistance
to enable them to supply the
information upon which the appellant was wrongly
insisting be supplied by them at their cost.
We note that there must have been some discussion about this clause at pre-contract negotiations. The words “an independent” are deleted and the word “his” is
substituted before the word “engineer”. Clearly, the parties
turned their minds to the situation that it could be the
appellant’s
expert or certifier; there was no requirement to involve somebody completely
independent.
Before the Master and before this Court, the respondents accepted that any plan could be prepared in the most advantageous way to the appellant, consistent with his obligation to obtain a certificate as to size, capacity and services relating to the subdivision; of course,
there would be no requirement for the respondents, should they ever
choose to subdivide, to work in accordance with that plan. However,
there would
be an obvious advantage to them in doing so, but there was no requirement that
they should do so.
There is no basis for an implied term to give “business efficacy” to the contract. Indeed, the acknowledgment
of the appellant that the clause is capable of fulfilment would certainly
mitigate against any implied term. That was the finding
of the Master with
which we agree.
We agree that, in the circumstances of this case, if a subdivision
concept plan of 100 sections would enable the certificate to be
given, or if
further information is required to enable the certificate to be given, the
obligation to obtain that information lies
with the defendant, i.e. the
appellant. The provision of such information is incidental to and part of
obtaining the engineer’s
certificate at the appellant’s
cost.
Consequently, we find that the Master was correct in his interpretation
of the clause; therefore there is no arguable defence; the
plaintiffs in the
Court below were entitled to summary judgment for specific
performance.
At the hearing before us, counsel for the appellant sought leave to file
an additional affidavit from Mr Potter which put times on
the fulfilment of the
various procedures required for the omnibus certificate; that is a certificate
covering several utilities.
Mr Andersen did not oppose the admission of this
further affidavit. In effect, the affidavit said it would take about 15 weeks
from
start to finish to assemble the necessary information to enable a proper
certificate to be given.
So, with that information in mind and purely to deal with the effluxion of time since the Master’s judgment was delivered, we propose to vary the order that he made
viz -
(a) The time for settlement is extended from 19 December
1996 to 4 March 1997;
(2) The amount to be tendered on that date is now increased to
$501,550.40 which is an agreed calculation including the additional
interest
required;
(3) The time for supplying the certificate by the appellant’s
engineer is extended from 2 April 1997 to 1 July 1997.
The appeal is dismissed with costs to the respondents of
$3,500 plus disbursements as fixed by the Registrar including reasonable
travelling and accommodation expenses of
counsel.
Solicitors: Caudwells, Dunedin, for appellant
Calvert & Co, Dunedin, for respondents
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/1997/319.html