You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2004 >>
[2004] NZCA 443
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Jack v Guy CA164/03 [2004] NZCA 443 (1 December 2004)
Last Updated: 15 September 2024
IN THE COURT OF APPEAL OF NEW ZEALAND
CA164/03
|
BETWEEN
|
NORMAN WILLIAM JACK AND
JUDITH ANN JACK
|
|
|
Appellant
|
|
AND
|
MURRAY CLIVE GUY
Respondent
|
Hearing: 5 August 2004
Court: Hammond, William Young, and Chambers JJ Counsel: B P Henry and D A Watson
for Appellants
P J Reardon for Respondent Judgment: 1 December 2004
JUDGMENT OF THE COURT
- The
appeal is dismissed.
- The
appellants must pay costs to the respondent in the sum of $6,000 together with
reasonable disbursements, including counsel’s
reasonable travelling and
accommodation costs. If counsel cannot agree disbursements, they are to be fixed
by the registrar. The
appellants’ liability for costs is joint and
several.
JACK V GUY CA CA164/03 [1 December 2004]
REASONS
Hammond and Chambers JJ [1]
William Young J [59]
HAMMOND AND CHAMBERS JJ
(Given by Chambers J)
Harvesting pine trees
- [1] In
1973 Bill and Judith Jack bought a hill country farm just north of Feilding.
Some time after purchase they planted pine trees
on parts of the farm.
- [2] In 1993, Mr
Jack decided it was time for at least some of the trees to be harvested and
sold. He had discussions with Murray Guy,
a farm consultant. There is no
dispute that in August 1993, as a result of those discussions, Mr Jack and
Mr Guy entered into
a contract. The nature of that contract, however, was
seriously in dispute in the High Court and remained in dispute before us. Mr
Jack contended that he agreed to sell some of the pine trees to Mr Guy. It was
Mr Guy’s responsibility to harvest the trees
and to pay for them. In fact,
the harvesting never took place. Indeed, even today, 11 years later, the trees
have still not been
harvested. Mr Jack claims that this is because Mr Guy
breached their contract and failed to harvest the trees and to pay for them.
Mr
Jack seeks damages for the loss he says he suffered as a result of Mr
Guy’s breach.
- [3] Mr Guy
asserts that he never agreed to buy the trees. Rather, he says he agreed to act
as Mr Jack’s agent and to find a
buyer for the trees. He says he did just
that. He says he carried out all his obligations to Mr Jack insofar as that was
possible.
The reason why the trees were not harvested is that Mr Jack had not
performed certain tasks he had agreed to do by the time the purchaser
of the
logs, ITT Rayonier Limited, wanted them harvested.
- [4] It was not
until 2003 that the dispute between the Jacks and Mr Guy was finally heard.
Durie J heard the case and delivered a
reserved judgment on 1 August last year.
He found in favour of Mr Guy. He held that the contract between the Jacks and
Mr Guy was
an agency and that Mr Guy had not breached any obligations he had
undertaken.
- [5] From this
judgment Mr and Mrs Jack have appealed.
Issues on the appeal
- [6] Mr
Henry and Ms Watson appeared for Mr and Mrs Jack on the appeal. Neither was
counsel in the High Court. They took only two points
on the Jacks’
behalf.
- [7] The first
issue, Mr Henry submitted, was the nature of the agreement. Mr Henry
submitted that the agreement was one
of sale and purchase: Mr and Mrs Jack
agreed to sell certain of their trees to Mr Guy, who was responsible for
harvesting them
and paying for them. Durie J had found that the agreement was
“an agency”: Jack v Guy HC PMN CIV-2003-454-202 1
August 2003 at [56]. Mr Reardon, for Mr Guy, supported the judge’s
finding. Mr Henry accepted
that, if he failed to persuade us on this ground, the
appeal must fail.
- [8] If the
agreement was one of sale and purchase, then the second issue was whether Mr Guy
had breached the contract. Mr Henry contended
that he had, because he had
refused to harvest or pay for the trees. Mr Henry submitted that in late
September 1993 Mr Guy had advised
that he would not be continuing with the
contract, purportedly on the basis that Mr Jack had not arranged the required
resource
consent and had not put in the necessary roading to enable harvesting
to take place. Mr Henry accepted that Mr Jack had not by that
time done those
things, but said Mr Guy still did not have the right to cancel. This was because
Mr Guy failed to make time of the
essence. Further, the time for performance of
Mr Jack’s obligations had not yet arisen and it was not inevitable that he
would
not be able to perform.
- [9] Mr Guy
disputed all this. He contended, as a fallback argument, that, if the agreement
was one of sale and purchase, then a term
of that agreement was that Mr Jack
should obtain a resource consent to permit the tree felling and put in necessary
roading before
harvesting was due to take place. Mr Guy contended that Mr Jack
had failed to do that and that there was no likelihood of his doing
that before
harvesting was due to take place. As a consequence, Mr Guy contended he was
entitled to cancel the contract and did so.
- [10] So the
second issue becomes: did Mr Guy repudiate the contract or was Mr Jack in
breach, the breach being one entitling
Mr Guy to cancel?
- [11] We shall
consider the issues in turn.
Nature of the contract
- [12] Mr
Jack and Mr Guy met at the Jacks’ farm on 2 August 1993. The following
day Mr Guy sent a letter to Mr Jack. Because
that letter is of fundamental
importance in this case, we set it out in full. For the sake of the analysis
that follows, we have
numbered the paragraphs:
GUY & ASSOCIATES 59 MANCHESTER STREET
FARM MANAGEMENT & FINANCE CONSULTANTS P.O. BOX 22
FARM FORESTRY CONSULTANTS FEILDING
TELEPHONE: (06) 323-9918
FAX: (06) 323-9918
3 August 1993
Mr N.W. Jack “Ngapuhi” R.D.
REWA
Dear Bill,
RADIATA PINE WOODLOT PRODUCE – REWA
- Further
to our inspection and discussions with you on site yesterday, we are now in a
position to confirm nett stumpage prices to
you for your logs on a graded basis.
We anticipate logging your trees sometime during the summer period,
but
as you will appreciate we will be scheduling your harvesting with other woodlots
in the general area and will keep you informed on
the likely timing of this. We
are aware that your preferred harvest time is February/March 1994 and will, if
practicable, comply
with this however contractors schedules and an early onset
of winter have to be considered.
- The
logs will be sold on a maximised graded basis for which you will receive the
following nett stumpage prices, exclusive of GST:
-
Export pruned peeler 4.1 & 6.1m. $252 per tonne Japan C. & I.
Sawlog $146 per tonne
Hyundai peeler sawlog $73 per M3
Domestic pulp (Karioi) $18 per tonne
- We
will be endeavouring to maximise the cutting of the high valued logs. The log
specifications for these grades are enclosed. If
practicable, depending on
volumes yielded, short pruned logs (i.e. less than 4.1m) and post logs will be
further graded and sold
to best advantage on the domestic market.
- A
logging cost of $22 has been built into our calculations of net stumpage. This
may be on the high side and if so then the difference
will be credited to your
net proceeds. The provision of internal roading and tracking and its cost will
be your responsibility.
- The
logs are marked by ITT Rayonier with proceeds paid fortnightly to us and net
stumpages forwarded to you within 7 days of our receiving
and paying
contractors.
- Should
there be any significant price increases between now and harvest, these will be
added to our quoted net prices.
- As
discussed Resource Consents, further investigation of logging technique and road
siting, are necessary. Therefore confirmation
of our harvesting contract is
vital to ensure adequate time for planning and preparation. Confirmation within
7 days would be appreciated.
Costs associated with Resource Management
application, consent and requirements are to be met by you.
- If
acceptable, please sign one copy of this letter as acceptance of our terms and
your authority to us to proceed with harvesting.
As we will be creating invoices
could you please supply your GST number.
- Should
you have any queries do not hesitate to contact us.
Yours sincerely,
GUY & ASSOCIATES
Farm Management & Finance Consultants Farm Forestry Consultants
Murray C. Guy, M.Agr.Sc.(Hons), M.N.Z.S.F.M. PRINCIPAL
Accepted by...................................
GST Number.................................. Date.........................
- [13] Attached to
the letter were separate sheets containing the log specifications for each grade
of log mentioned.
- [14] Mr Jack did
sign the letter and send it back to Mr Guy. He did not do it within the seven
days stipulated: Mr Guy in fact contended
he did not receive the acceptance
until 16 August. But nothing turns on that. Durie J accepted that the letter of
3 August was a
crucial part of the parties’ contractual relationship.
There was no dispute about that before us. Although the agreement
was not
made on 3 August, we shall refer to it as “the 3 August
agreement” as that was the date of Mr Guy’s
letter which is at
the heart of it.
- [15] Durie J
held that this letter (once accepted) did not constitute an agreement for sale
and purchase of the trees. Rather,
he said that it created an agency.
His Honour did not attempt to elucidate what the terms of the agency were. Nor
are Mr Reardon’s
submissions any more helpful in terms of identifying
precisely what, on the agency argument, Mr Guy was undertaking to do.
- [16] With
respect to Durie J, we consider that the contract between Mr Jack and Mr Guy was
a contract of sale and purchase. Mr Guy’s
promises are inconsistent with a
mere agency arrangement. In paragraph 1, he promises to log the trees. In
paragraph 2, he promises
Mr Jack what he will receive for the logs. In paragraph
3, he promises to maximise the cutting of the high valued logs. In paragraph
4,
he promises an increased price if his logging cost of $22 turns out to be lower.
In paragraph 5, he promises when he will be paying
Mr Jack. In paragraph 8, he
refers to this letter, once accepted, as being his authority to proceed with
harvesting. Certainly in
its own terms none of that is consistent with this
letter creating an agency.
- [17] We turn to
consider the judge’s reasons for finding that the 3 August letter
constituted merely the creation of an agency
relationship. First, at [37], the
judge referred to the letterhead, in which Mr Guy was referred to as
“neither a lumberer
nor a wood buyer but a farm and forestry
consultant”. With respect, we see nothing in that point. The heading to
the letter
did not constitute part of the contract. In any event, Mr Guy’s
normal occupation could not override the clear terms of the
parties’
promises to each other. Further, as we shall show later, Mr Guy, as a result of
a contract he had earlier entered
into with ITT Rayonier Limited
(“Rayonier”), was obliged to source 4000 m3 of logs.
Since he was bound to sell those logs to Rayonier and since he did not own a
timber plantation himself, it followed he was
bound to buy logs if he was not to
breach his Rayonier contract. He was therefore a “wood buyer”,
whatever his letterhead
might proclaim.
- [18] The judge
accepted that paragraph 1 did indicate “that what was involved was indeed
a sale”: at [38]. But the judge
went on to say that, notwithstanding that,
the paragraph “is not inconsistent with an agency in which [Mr
Guy’s] firm
is acting in no larger role than that of an advisor”.
That proposition requires closer analysis. What is the judge saying Mr
Guy’s promise is? It is important to recognise that Mr Guy has never
contended that he was acting as agent for Rayonier
when entering into the
contract with Mr Jack. What, then, is he promising? The judgment under appeal
does not make this clear. Is
it a promise that he will find a buyer who will log
the trees? Or is it merely a promise to use reasonable endeavours to find such
a
buyer? Neither is consistent with the clear words of the first paragraph. There
is nothing tentative about the promise to log the
trees (provided, of course, Mr
Jack met his obligations, as set out later in the letter). Nor is there any
suggestion that anyone
other than Mr Guy (or his contractor) will be doing the
logging. With respect to the judge, we are simply unable to accept that this
paragraph is consistent with Mr Guy’s role being that merely of an advisor
to Mr Jack.
- [19] Durie J did
not refer to paragraph 2 of the letter. But he thought that “the third to
sixth paragraphs [were] indicative
of an agency arrangement”: at [39]. He
referred in particular to the third paragraph commencing “We will be
endeavouring...”.
That is certainly not inconsistent with a sale: it
amounts to a promise by the logger (buyer) that he will use reasonable
endeavours
to maximise the
cutting of the high valued logs, obviously intending thereby to reassure Mr Jack
that the cutting would be done in such a way as
to maximise his returns. Durie J
considered that, were this a sale of a forest, “an explanation of [Mr
Guy’s] on-sale
proposals for post logs, the marketing of logs by Rayonier,
and the reference to net stumpage (for the return after logging and other
expenses) would all be inexplicable”: at [39]. With respect, they would
not be. It was relevant to tell Mr Jack who
would ultimately be marketing
the logs, because Mr Jack’s payments, as to timing, were contingent on
when Rayonier paid Mr
Guy. The reference to net stumpage is quite consistent
with a sale. Mr Guy was informing Mr Jack that he had calculated a logging
cost
of $22 in his calculation of net stumpage. If his logging cost was lower than
that, then he promised that the difference would
be added to the price to be
paid to Mr Jack. There is nothing inexplicable about such a pricing arrangement
on a sale.
- [20] The judge
discussed paragraph 7 of the letter in which Mr Guy had referred to “our
harvesting contract”. Durie J
accepted that that reference was “more
suggestive of an outright sale of the cut trees than it is of an agency”.
He gave
no explanation as to why Mr Guy would have referred to the agreement as
being “our harvesting contract” if Mr Guy was
not in fact
undertaking to harvest.
- [21] The judge
then referred to paragraph 8 where Mr Guy had asked Mr Jack to sign and return a
copy of the letter, signifying his
acceptance of “our terms and [his]
authority to [Mr Guy] to proceed with harvesting”. The judge thought that
wording
consistent with either a sale and purchase or an agency arrangement.
With respect, we disagree. If this were merely an agency arrangement,
then its
signing could not possibly give Mr Guy authority to harvest, because Mr Guy
would not be the harvester. Presumably his obligation
was to find one, who would
then enter into a contract with Mr Jack, if Mr Jack was satisfied with the
proposed harvester and the
terms the harvester was offering. But that is not
what the 3 August letter provides. Nor did Mr Guy’s proposed harvester
ever
make or attempt to make a contract with Mr Jack.
- [22] The judge
considered that his interpretation of the 3 August letter was reinforced by
other “contextual evidence”:
at [43]. In particular, His Honour
referred
to an agreement entered into between Mr Guy and Rayonier earlier in 1993
(“the Rayonier agreement”). That agreement,
which is dated 14 April
1993, was in written form. Under it, Rayonier agreed to purchase and Mr Guy
agreed to sell logs specified
in the schedule to the agreement upon the terms
contained in it. We shall set out these terms in some detail because we consider
that they, far from reinforcing an agency relationship between Mr Jack and Mr
Guy, in fact reinforce the conclusion that the 3 August
agreement was one of
sale and purchase. Under clause 2 of the Rayonier agreement, Mr Guy agreed to
deliver to Rayonier between 14
April 1993 and 14 October 1993 approximately
4,000 m3 of logs. The logs were to be sourced from “various
blocks in the Manawatu, Horowhenua and Rangitikei area”. The purchase
price for the logs was specified and was exclusive of GST, which was payable by
Rayonier: see clause 3. (GST was, of course, payable
because Mr Guy as seller
was making a supply of goods to Rayonier.) It was Mr Guy’s responsibility
to transport the logs to
the Port of Wellington: see clause 5. Title and risk in
the logs passed from Mr Guy to Rayonier upon Mr Guy delivering the logs at
Wellington: see clause 6. Mr Guy warranted that, upon the passing of title, no
other person would have any title or other interest
in the logs delivered: see
clause 6.1(a). It was Mr Guy’s obligation to insure the logs, at his cost,
until title to the logs
passed to Rayonier: see clause 7. Mr Guy had the
responsibility to employ and pay contractors for work he had to do under the
contract
(eg harvesting and delivering the logs): see clause 11. Importantly,
clause 15 provided that the written agreement constituted the
entire agreement
between the parties “and there is no other agreement written or
oral”. The parties further agreed that
“no amendment to this
Agreement shall be effective unless made in writing and signed by both
parties”.
- [23] Nothing
could be clearer than that, by that agreement, Mr Guy was undertaking to source
logs meeting Rayonier’s specifications
which he would then sell and
deliver to Rayonier. It could not possibly be the case that Mr Guy was entering
into that contract as
agent. For a start, he had not at that stage sorted out
exactly where he was going to source the logs. But further, it is completely
inconsistent with the written terms of the Rayonier agreement that Rayonier was
agreeing to contract with a number of individual
woodlot owners. The judge
appears to have considered that Mr Guy entered into that agreement as an agent,
and that this then in some
way confirmed that his relationship with Mr Jack was
also that of an
agent. We cannot agree. It was essential under the Rayonier agreement that Mr
Guy acquire title in the logs which he was bound to
supply and deliver to
Rayonier. His subsequent agreement with Mr Jack was a step taken to acquire
title to Mr Jack’s logs,
obviously at the time logs he intended to sell on
to Rayonier pursuant to his obligations to that company.
- [24] The
confusion in Mr Guy’s stance is reflected in Mr Reardon’s submission
before us. He appears to consider that the
High Court found that a contract was
formed between Mr Jack and Rayonier, pursuant to which Mr “Jack was
selling the trees
directly to Rayonier”. In fact, Durie J made no such
finding. And indeed, Mr Reardon does not explain how and when this
alleged
agreement came into existence. There is no evidence that anyone from Rayonier
ever saw the 3 August letter and agreed to
its terms. Nor is there any evidence
that Mr Jack ever saw the Rayonier agreement and agreed to be substituted for Mr
Guy, or indeed
that Rayonier ever agreed to such a substitution. Further, there
are clear inconsistencies between the two agreements, not least
on price. Mr
Jack and Rayonier were never in a contractual relationship, and, contrary to Mr
Reardon’s submission, Durie J
never found that they were.
- [25] We have not
overlooked that the 3 August agreement appears to have been subject to an oral
condition that Rayonier would have
to approve the suitability of the trees,
something which happened later in August. That was no doubt a sensible
precaution on Mr
Guy’s part, as he clearly would not want to buy trees
which were not going to be suitable for supply by him under the Rayonier
agreement. We do not see this as assisting the agency argument. It was always
clear in the 3 August agreement that the trees would
eventually be finding their
way to Rayonier.
- [26] On the
first issue, we find in favour of Mr Jack. The agreement between him and Mr Guy
was one of sale and purchase.
- [27] We
therefore proceed to consider the second issue.
Who breached the agreement?
- [28] Each
party to the contract alleges the other breached it. To work out who is right
requires a close analysis of the parties’
agreement.
- [29] For the
reasons already given, we have found that Mr Guy undertook the obligation of
buying and harvesting the trees. As to when
that harvesting would take place, we
refer to paragraph 1 of the 3 August letter:
We anticipate logging your trees sometime during the summer period, but as you
will appreciate we will be scheduling your harvesting
with other woodlots in the
general area and will keep you informed on the likely timing of this. We are
aware that your preferred
harvest time is February/March 1994 and will, if
practicable, comply with this however contractors schedules and an early onset
of
winter have to be considered.
- [30] Effectively
the parties’ arrangement on timing of harvesting was this:
- Mr
Guy will harvest the logs at some time before the winter of 1994, in the same
general period as he is harvesting other woodlots
in the general area.
- Mr
Guy’s present intention is that harvesting will take place in the summer
period.
- Mr
Guy will keep Mr Jack informed of the likely time of harvesting.
- Subject
to clause 1, the trees will be harvested at Mr Jack’s preferred time,
namely February/March 1994.
- [31] Mr Guy was
taking something of a risk when setting out such timing, as under his contract
with Rayonier, he was bound to deliver
the logs by no later than 14 October
1993. Perhaps he thought that there would be a degree of flexibility on
Rayonier’s part.
- [32] In any
event, an important event occurred on 3 September 1993. Mr Guy received a fax
from Mark Allardice, at that time Rayonier’s
Southern North Island Log
Procurement Supervisor. Apparently the fax was to the effect that the market had
steadied and that Rayonier
“were not interested in any new contracts at
the old prices and no longer wanted certain grades”. Later that month, Mr
Allardice rang Mr Guy again. He said that the market was falling “and
that Rayonier needed to market the logs it was committed
to as soon as
possible”. Mr Guy in his evidence thought “that it had to be done by
the end of October”. That was
in fact in accordance with Rayonier’s
contract with Mr Guy. If Mr Guy thought that he was going to have much leeway
under
it, Mr Allardice’s telephone call would have disabused him. (As a
matter of interest, it does appear that subsequently the
contract period under
the Rayonier agreement was extended to 8 November 1993.)
- [33] The second
call from Mr Allardice caused Mr Guy to act. According to his evidence, he then
approached the various woodlot owners
whose forests were yet to be harvested. He
told them about Mr Allardice’s advice. He said in evidence, “I
believe I told
each of them I was worried that Rayonier might try to pull out of
the contract unless the forest was harvested promptly.” It
is unclear as
to the basis for the advice Mr Guy gave to the woodlot owners. Mr Allardice had
not said anything contrary to Rayonier’s
contract with Mr Guy. Mr Guy said
that he spoke to Mr Jack at that time. According to Mr Guy, he told Mr Jack that
Rayonier had been
in contact with him, that the market was falling, and that
they [Rayonier] wanted all woodlots harvested that they had a commitment
to. He
asked Mr Jack whether he had obtained his resource consent and had done the
necessary roading to facilitate the harvesting
process. Mr Jack said that he had
not. According to Mr Guy, he then told Mr Jack that his lot needed to be
harvested in conjunction
with the others. He said that, as a result of Mr Jack
not being ready, Rayonier were saying to him that they would have to bypass
his
woodlot. Mr Jack said, according to Mr Guy, that he still wanted his woodlot
harvested. Mr Guy replied that that would be something
that Rayonier would have
to decide in that they were telling him [Mr Guy] that they wanted his [Mr
Jack’s] woodlot now, in
conjunction with the other woodlots that they were
committed to. Later in evidence, Mr Guy said that he had told Mr Jack in the
course
of this conversation that, in view of the fact he was not ready,
“he would have to take pot luck with the market”.
- [34] There are
some difficulties with Mr Guy’s account of that conversation. This was the
first time Mr Guy knew that Mr Jack
was not ready. In light of that, it is
somewhat difficult to see how Mr Guy was able to say that “as a result of
him not being
ready Rayonier were saying to me [i.e. Mr Guy] that they would
have to bypass his woodlot”. Perhaps the explanation is that
Mr Guy has by
error kaleidoscoped two conversations with Mr Jack, in between which Mr Guy had
been back to Rayonier.
- [35] There is no
rival account of this conversation (or these conversations) as Mr Jack
denied that he had had any telephone conversation
with Mr Guy at that time.
Durie J did not believe him. He appears to have accepted Mr Guy’s account:
at [17]. Mr Henry acknowledged
that on appeal he had to accept that factual
finding. He was prepared to argue this matter on the basis that there was a
conversation
between Mr Guy and Mr Jack in late September 1993 and that the
gist of it was as relayed by Mr Guy. The enquiry therefore becomes:
what are the
legal consequences of that conversation?
- [36] The first
question which must be answered is whether Mr Guy was within his rights in
stipulating to Mr Jack towards the end of
September 1993 that the trees would
have to be harvested by the end of October. In our view, Mr Guy was within his
rights. He had
always stipulated that the harvesting was to be “in the
same general period as he [was] harvesting other woodlots in the general
area”. It is true that harvesting was now to take place before the summer,
but, in the 3 August agreement, he had never given
more than a “present
intention” that harvesting would take place in the summer. There is no
evidence that, as at the
date of the 3 August agreement, that was not Mr
Guy’s intention. We appreciate that under the Rayonier agreement he was
obliged
to deliver the logs by 14 October, but he appears to have had an
expectation that later delivery would be satisfactory for Rayonier.
Indeed, it
appears that his expectation in that regard was reasonable; it was only the fall
in wood prices which became evident in
September 1993 that caused panic within
Rayonier. Rayonier clearly decided that harvesting should take place urgently so
that they
could offload the logs they had bought as quickly as possible, before
prices perhaps deteriorated further. Although, in terms of
clause 4 of our
reformulation of the timing obligation, the trees were to be harvested, if
practicable, at Mr Jack’s
preferred time, namely February/March 1994, that promise was always subject to
the overriding requirement that harvesting of Mr Jack’s
lot was to take
place in the same general period as the harvesting of other woodlots in the
general area. There is no suggestion
in the evidence that the hauling forward of
harvesting was done in bad faith or for an improper purpose.
- [37] It is
common ground that, as at the date of this telephone call in late September
1993, Mr Jack was not in a position to allow
harvesting on his farm to take
place. That was because he had not by that time obtained the necessary resource
consent. Nor had he
put in the roading required before harvesting was to take
place. He had to provide and pay for internal roading and tracking: see
paragraph 4 of the letter of 3 August 1993. He was to obtain and pay for the
necessary resource consent: see paragraph 9 of the
same letter. By the end of
September, Mr Jack had done nothing on either matter.
- [38] Mr Jack
blamed his lack of action in applying for the resource consent on Mr Guy. He
said that Mr Guy had promised to send
a harvesting plan and that the Manawatu
Wanganui Regional Council required such a plan to support the application for
consent to
cut the trees. There was no reference to Mr Guy having any such
obligation in the 3 August letter. Mr Guy disputed that he had ever
agreed to
provide the harvesting plan and Durie J believed him: at [12].
- [39] Mr Jack
explained his inactivity on the roading front on the basis that he was waiting
for Mr Guy to send his roading expert
before taking any steps himself. Once
again, Durie J did not believe Mr Jack’s explanation: at [14] and [16].
There is nothing
in the 3 August agreement to support the view that Mr Guy had
any obligations with respect to roading. Insofar as Mr Jack alleged
that the
obligation had arisen from an oral amendment of the agreement on or about 27
August, Durie J found such alleged variation
unproved: at [13]. Mr Henry
accepted that he could not challenge that finding, which was essentially a
credibility finding.
- [40] So we reach
the position that, at the time of the telephone conversation between Mr Guy and
Mr Jack in late September 1993, Mr
Jack had taken no steps on either matter.
When Mr Guy learned this, he concluded that it was not going to be
possible for Mr Jack to be ready so that his trees could be harvested in the
same general period as he was harvesting other woodlots
in the general area.
There is no doubt, on Durie J’s findings, that Mr Guy then indicated to Mr
Jack (whether in that conversation
or another shortly after) that the deal was
off. Was that intimation a wrongful repudiation of the 3 August agreement or was
it a
valid cancellation?
- [41] There was
some discussion in counsel’s submissions as to the time within which Mr
Jack had to obtain the resource consent.
(We note at this point that Mr
Henry in his submissions appeared to overlook completely Mr Jack’s
obligation to put
in roading. We shall return to that matter shortly.) Mr Henry
submitted that there was no stipulated time for the performance of
the
obligation to obtain resource consent, with the consequence that by implication
Mr Jack had a reasonable period of time in which
to obtain it. If Mr Guy was
concerned about timeliness in this regard, he had to give notice making time of
the essence. Only if
the resource consent was not obtained within a reasonable
period of such notice being given could Mr Guy cancel the contract.
- [42] We do not
agree with that submission. We consider the time for performance of Mr
Jack’s obligations to obtain the resource
consent and to put in the
necessary roading was fixed under the contract. Those obligations clearly had to
be fulfilled before the
nominated time for harvesting. If those obligations were
not fulfilled by the time of harvesting, then clearly Mr Guy would have
been
entitled to cancel the 3 August agreement. The performance of those
obligations was essential to Mr Guy, as he would not
be permitted by law to
harvest the trees without the requisite resource consent having been obtained.
But that was not the position
as at the end of September. Mr Guy was not ready
immediately to harvest the trees, although he wished to do so by the end of the
following month. Mr Jack was not then in breach of the 3 August agreement, as
the time by which his obligations had to be fulfilled
had not yet arrived. Mr
Guy was not at that time entitled to cancel the contract on the basis that Mr
Jack had repudiated the agreement
or on the basis that Mr Jack had broken a
stipulation in the contract: see Contractual Remedies Act 1979, s 7(2) and
(3)(b). In the
circumstances, the law did not require Mr Guy to make time of the
essence. He had no need to do so.
- [43] The real
question in this case was whether it was clear that Mr Jack was going to
default on his obligations. Under s 7(3)(c)
of the Contractual Remedies Act, a
party to a contract may cancel it if it is clear that the stipulation in the
contract will be
broken by another party to that contract. It is Mr Jack’s
contention that it was still possible for him to comply with his
obligations in
time. Mr Henry submitted that the evidence demonstrated that a resource consent
could normally be obtained in 20 working
days or, if urgent, within “a
couple of days”. He submitted that Mr Guy had not established on the
balance of probabilities
that Mr Jack’s failure was clear. The legal
consequence therefore was that Mr Guy’s information was a repudiation of
the contract, not a cancellation.
- [44] The test
under s 7(3)(c) was comprehensively discussed by Blanchard J in Brooklands
Motor Company Limited (in rec) v Bridge Wholesale Acceptance Corporation
(Australia) Limited (1993) 7 NZCLC 260,449. In that case, His Honour
concluded that the test to be applied is “whether a reasonable bystander,
aware
of all relevant existing and future facts, would have believed that by the
time of the purported cancellation it was clear that there
would be a breach of
the requisite essentiality or seriousness”: at 260,461. That test appears
to meet with the approval of
the editors of the leading New Zealand contract
text: see Burrows, Finn & Todd Law of Contract in New Zealand (2ed
2002) at 632-3. We apply Blanchard J’s test.
- [45] The first
comment we make is as to onus of proof. Mr Henry submitted, without citing
authority, that the onus was on Mr Guy to
establish that Mr Jack’s
anticipated breach was inevitable. We do not accept that. It is Mr Jack who has
brought a claim for
damages. An essential part of that claim, which Mr Jack must
prove, is that Mr Guy breached the contract – in this case, by
repudiating
it. It is for Mr Jack to establish that Mr Guy’s acts amounted to a
repudiation rather than a cancellation (as
he claims). It is accordingly for Mr
Jack to establish, on the balance of probabilities, that the reasonable
bystander would not
have believed it was clear that Mr Jack would not fulfil his
obligations in time.
- [46] Secondly,
there is no evidence as to how quickly Mr Jack could have obtained a resource
consent in 1993. The only evidence to
which Mr Henry referred us came from Aaron
Madden, a Land Management Officer (Soils) for the Manawatu
Wanganui Regional Council. He gave evidence that he was satisfied that the
application could have been dealt with on a non-notified
basis “provided
it was supported by the necessary documentation”. He also noted that
councils had a legal obligation
to process non-notified consents within 20
working days – and indeed, in certain circumstances of urgency, consents
had been
made available in an even shorter time.
- [47] But that 20
working day period (approximately a month) starts running from the date on which
a council receives a proper application,
with all supporting documentation. At
the time of Mr Guy’s conversation with Mr Jack in late September, Mr Jack
had done nothing
to get this application under way. There is no evidence as to
how quickly he could have got the necessary information. Clearly it
would have
required roading information, but at that stage Mr Jack had made no effort to
obtain a roading expert for advice.
- [48] There may
be some doubt as to the extent to which, when applying the “reasonable
bystander” test, the court may look
at subsequent events. In so far as
that is permissible, we would observe that Mr Jack’s optimism now that he
could have got
the resource consent in double-quick time is not supported by the
evidence of what later happened when he did try to get a resource
consent. Mr
Jack in subsequent years made three different applications for a resource
consent to log and extract his trees.
- [49] The first
was made on 15 April 1996. An officer at the regional council made the following
annotation on the application on 17
April: “trees are being removed from
difficult area (erosion). Aaron [Madden] will need to do inspection –
arrange with
him to visit site, I’ll come as well as this will not be an
easy consent to write conditions for.” Mr Madden did in fact
make
“an initial site inspection” on 24 April. He noted that Mr Jack had
not finalised “the extraction route for
the logs”. The location of
the proposed new tracking was “dependent on further recommendations from
roading consultants/contractors”.
Mr Madden noted that “a critical
section of the proposed extraction route is far too steep for conventional
logging trucks”.
Mr Madden recommended that the application be put on
hold until the council received the additional information on track siting from
Mr Jack. It would appear
that nothing further was heard from Mr Jack. On 1 May the following year, the
council wrote to Mr Jack withdrawing [sic] his application
“due to the
time lapse since [the] request” for a resource consent.
- [50] The next
application was made two years later, on 27 March 1999. The council responded on
31 March 1999 requesting a harvesting
plan, a tracking plan, and written
approval of neighbours. The council also noted that “a preliminary
assessment of [the] application”
by Mr Madden had raised concerns. Mr
Madden said that he was concerned with the potential impacts of intended
tracking across a stream
“to the extent that at this stage he does not
support tracking through the streambed”. By 21 October 1999, the
additional
information requested had still not been provided.
- [51] That
appears to have led Mr Jack to make a fresh application (his third) on 27
October 1999. On this occasion a resource
consent was granted
– on 24 November. The consent was subject to 16 conditions. A
harvesting plan was still required:
condition 15 did not permit any harvesting
or tracking until the harvesting plan had been approved in writing. That
harvesting
plan was not approved until 9 May the following year.
- [52] While that
subsequent history is not definitive, it is scarcely supportive of Mr
Jack’s optimism that he could have got
the resource consent in time for
harvesting by the end of October or early November.
- [53] The third
point we would make is that we have to date been concentrating solely on the
likelihood of Mr Jack’s getting
the resource consent in time. But that was
not all that he had to do: he also had to put in place the necessary
roading. Mr
Henry made no reference to that in his submissions. He concentrated
purely on the resource consent. The roading could not be done
until the resource
consent was granted. There is no expert evidence as to what the council’s
roading requirements would have
been in 1993. We do know, however, what their
requirements were in 1999, as they are detailed as conditions to the resource
consent.
We do not set out the details of the tracks, culverts, and drains
required. Suffice it to say that it is
obvious that putting in the tracks to the requisite council standards would have
required some considerable time.
- [54] We also
attach some significance to Mr Jack’s reaction (or perhaps lack of
reaction) to Mr Guy’s advice that the
sale would not be going ahead. If Mr
Jack had truly believed that he could get the resource consent and put in the
roading in time,
one would have expected some protest from him. So far as the
evidence discloses, there was none. He appears to have accepted that
Mr Guy was
acting within his rights. The lack of adverse reaction provides support for the
view we have reached on the other evidence.
- [55] Based on
the evidence we have – somewhat sparse though it is – we are quite
satisfied that a reasonable bystander
would have believed in late September 1993
that it was clear that Mr Jack would not be able to fulfil his obligations with
respect
to a resource consent and roading by the time of harvesting. There can
be no doubt that the parties had impliedly agreed that the
performance of those
obligations falling on Mr Jack was essential to Mr Guy: indeed, he could not
fulfil his obligations unless Mr
Jack first fulfilled his. And Mr Guy had always
made it clear that his undertaking to harvest and buy Mr Jack’s trees was
contingent
on the work being done at the same time as other woodlots in the area
were harvested.
- [56] It follows,
therefore, that we are satisfied that Mr Guy was entitled to cancel the 3 August
agreement pursuant to s 7(3)(c)
of the Contractual Remedies Act and that he did
so. It follows therefore that Mr Jack’s claim for breach of the 3 August
agreement
must fail.
Result
- [57] For
different reasons from those articulated by Durie J, we have found that Mr Guy
was not in breach of the 3 August agreement
and was entitled to cancel and did
cancel that agreement in late September 1993.
- [58] Accordingly,
we dismiss the appeal.
WILLIAM YOUNG J
- [59] I
agree that the appeal should be dismissed but my reasons differ from those which
appear in the judgment prepared by Chambers
J.
- [60] Given that
the outcome of the case is the same on my approach as it is on that preferred by
Hammond and Chambers JJ, and that
the issue is simply one of fact, I see no
point in giving elaborate reasons.
- [61] I see four
possible ways of analysing Mr Guy’s role:
(a) He could have been acting independently as an entrepreneur, buying and
selling timber on his own account. This is what Mr and
Mrs Jack allege and is
how Hammond and Chambers JJ view the situation.
(b) He could have been acting as agent for Mr and Mrs Jack. This is what he
alleges and Durie J found to be the case.
(c) He could have been acting as agent for Rayonier.
(d) He could have been acting as agent for both Mr and Mrs Jack and Rayonier.
- [62] I doubt if
Mr Guy analysed his role with precision. He probably just saw himself as an
intermediary, bringing buyers and sellers
together and making a profit. I think
that this may explain the not entirely consistent trail of documents which he
created.
- [63] I agree
that the 3 August 1993 letter which Mr Guy sent to Mr Jack and the 14 April 1993
agreement between Mr Guy and Rayonier,
particularly if viewed together but in
isolation from the facts as a whole, strongly indicate that Mr Guy was acting as
an entrepreneur,
obtaining a commitment from Rayonier to acquire logs (and thus
committing himself to their supply) and then buying logs to meet his
obligations. It is, however, not entirely uncommon for a person who is
ostensibly (ie on the face of the relevant contractual documentation)
a party to
a contract to be held
to have been only an agent. On this basis, the status of Mr Guy in his dealings
with Mr Jack involves an issue of fact and not just
construction.
- [64] On the
findings of fact made by Durie J, the letter of 3 August 1993 was preceded by
discussions on 2 August between Mr Guy and
Mr Jack in the course of which Mr Guy
made it clear that the prices which were to be agreed would be subject to
Rayonier’s
approval and that Rayonier would also be required to inspect
the trees and confirm that it was willing to take them. The first of
these two
points was picked up in the letter of 3 August as, on the findings made by Durie
J, Mr Guy spoke by telephone to Rayonier
before sending the letter of 3 August.
The second of these points (inspection of the trees by Rayonier and confirmation
of its willingness
to take them) was not.
- [65] Durie J
also found that a Rayonier representative, Mr Mark Allardice inspected the trees
in 25 August 1993 and duly confirmed
that Rayonier was prepared to take them and
that Mr Jack was told of this the next day.
- [66] I think it
possible to treat the 14 April 1993 “agreement” from Rayonier as an
ill-expressed commitment by Rayonier
to take approximately 4,000 m3
of logs which Mr Guy was to procure and thus to see his later agreement with Mr
and Mrs Jack as part of that procurement. On this
basis, the dealings direct
between Mr Jack and Mr Guy in August 1993 brought about a contract between Mr
and Mrs Jack as vendors
and Rayonier as purchaser which was eventually finalised
on 26 August 1993 when Mr Jack was told that Rayonier would take the
trees.
- [67] Viewed in
this light, I think that the approach taken by Durie J was open to him and
indeed I think preferable to the view that
Mr Guy was a principal. There are
indeed, as Durie J pointed out, aspects of the 3 August 1993 letter which are
suggestive of agency.
As well, and importantly, the externalities of Mr
Guy’s role are indicative of him acting as an agent rather than as an
entrepreneur.
Further, I think it of at least some significance that when
problems arose, Mr Jack himself seems to have acted on the basis that
he had
been in contract with Rayonier.
Solicitors:
Dennis Gates, Whangaparaoa, for Appellants Cooper Rapley, Palmerston North,
for Respondent
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2004/443.html