You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2021 >>
[2021] NZCA 10
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Kaimai Properties Limited v Queen Elizabeth the Second National Trust [2021] NZCA 10 (15 February 2021)
Last Updated: 24 February 2021
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
KAIMAI PROPERTIES LIMITED Appellant
|
|
AND
|
QUEEN ELIZABETH THE SECOND NATIONAL TRUST Respondent
|
Hearing:
|
29 October 2020
|
Court:
|
Kós P, Cooper and Gilbert JJ
|
Counsel:
|
A R Galbraith QC and K E Cornegé for Appellant R J B Fowler
QC and F B Q Collins for Respondent
|
Judgment:
|
15 February 2021 at 9 am
|
JUDGMENT OF THE COURT
- The
appeal is dismissed.
- The
appellant must pay costs to the respondent for a standard appeal on a band
A basis, with usual
disbursements.
____________________________________________________________________
REASONS OF THE COURT
(Given by Kós P)
- [1] This appeal
is about two blocks of land in the Kaimai Ranges. The landowner entered open
space covenants over parts of the land
with the Queen Elizabeth the Second
National Trust.[1] At the time one of
the blocks was subject to a licence enabling a third party to quarry that land.
The landowner did not consult
the quarry operator. It now seems one of the
covenanted areas may restrict expansion of the quarry. The quarry
operator then sought
to purchase the two blocks from the landowner. During
negotiations it discovered the covenants, but proceeded with the purchase
notwithstanding. It later applied to the High Court for declarations that
the terms of the covenants permitted expansion of the
quarry into the
covenanted areas. Alternatively, it sought rectification of the covenants.
- [2] Edwards J
dismissed the
claim.[2]
The quarry operator, now also owner of the land,
appeals.
Background
- [3] The two
blocks of relevant land are adjoining titles in the Kaimai Ranges. Bartons
Kaimai Farm Ltd operated a quarry on the main
block from 1973 and then purchased
that block in June 1979. In March 1982 it sold it to Hiona Heights Ltd, owned
by a Mr Ian Diprose.
Mr Diprose already owned the smaller block.
In September 1982 Bartons and Hiona entered an agreement giving Bartons the
right to
operate the quarry in a defined area for a 40-year term commencing 21
December 1981.[3] During that term no
royalties were payable on rock mined.
- [4] In 1983,
Hiona entered a Land Improvement Agreement (LIA) with the Hauraki Catchment
Board, whereby Hiona agreed that 100 ha of
the mainly southern parts of the main
block would be held as a reserve and protected from stock grazing.
- [5] In 1986, the
Swap family purchased Bartons. The appellant, Kaimai Properties Ltd, is part of
a group of companies owned by the
Swaps.
- [6] In 1993,
Hiona and Bartons reached an agreement under which Bartons retained its
entitlement to operate the quarry within a defined
quarry area until 2021 with
no payment of royalties to Hiona.[4]
The 1993 agreement provided for a right of renewal for a further 40 years at a
royalty rate to be agreed. It also contemplated
the expansion of the
quarry beyond the south eastern boundary. Clause 6 provided expansion outside
of the quarry area, if necessary,
would be subject to further negotiations
between Hiona and Bartons, as would the question of any additional royalty
payments.
- [7] We record
the Judge below found the boundary of the quarry area in the 1982 and 1993
agreements did not change.[5] Though
both agreements record the quarry area as 39.4242 ha, the relevant plans in fact
show the quarry area was extended to the
east to a feature marked on a plan as
the “point on crag”.
- [8] In April
1998 the Matamata-Piako District Council granted a certificate of compliance for
the quarry operation. This confirmed
existing land use rights. Relevantly
these provided for expansion of the quarry to the east.
- [9] In 2003,
Hiona reached an agreement with the Matamata-Piako District Council regarding
the proposed establishment of a green belt.
A Development Concept Plan (DCP)
was developed and agreed in April 2003. The plan allowed quarrying, as well as
conservation and
commercial forestry, in the quarry area. The proposed
expansion of the quarry, at least for that 10-year timeframe, was to
the east.
- [10] In November
2004, Mr Diprose began looking for ways to reduce his rates burden and get some
fencing assistance. The Waikato
Regional Council suggested he place parts of
the land under covenant and put him in contact with Mr Hamish Dean of the
Trust.
- [11] In February
2005, Mr Diprose met with Mr Dean and Mr Rien van de Weteringh of the Waikato
Regional Council at the blocks to discuss
the possibility of covenanting the
land. Messrs Diprose and Dean met several times subsequently.
- [12] Exactly
what was said between Messrs Diprose and Dean at those meetings is disputed and
central to the claim for rectification.
Both Messrs Diprose and Dean accepted
they cannot recall exactly what was said. The contested nature of the content
of the meetings
can be summarised.
- [13] Mr Diprose
believes he made it clear to Mr Dean that flexibility would be needed to allow
the quarry to expand. Mr Diprose’s
belief that flexibility would be
provided for in the covenant was to a degree corroborated by Mr Taris, the
surveyor we refer to
below. In cross-examination, Mr Diprose accepted he may
not have stated the quarry would need to expand into the covenanted areas
“in direct terms”, but that reality would have been obvious to Mr
Dean from his site visits.
- [14] Mr Dean
on the other hand stated he would remember if Mr Diprose had said expansion was
to be into the covenanted areas. If
it had been said, Mr Dean said he would
have explained it would not be possible. When cross-examined, Mr Dean stated he
believed
from the DCP the quarry would expand to the east; he did
not recall any mention by Mr Diprose of expansion to the south. He said he was
depending on Mr Diprose to advise him of any
issue of
conflict:
... if somebody had said that to me it would have been a
simple matter of making the covenant boundary back to where it needed to
be.
[There] ... was no drive to have it right next to the quarry so ... if that
discussion had taken place ... it would have been
dealt with.
- [15] Mr
Dean compiled a report following these visits. That report mentioned three
special conditions which were carried through
into sch 3 of the covenants
(outlined at [20] below). The report
does not mention expansion of the quarry.
- [16] The Trust
board approved two open space covenants over 151.2 ha of land in the blocks on
18 May 2005. The approval documents
contained indicative boundaries. The
proposed covenants were sent to Mr Diprose and his wife in June 2005.
The Diproses signed
the covenants in September 2005.
- [17] The
covenanted land was described by area and by reference to an attached aerial
plan. This plan was not however attached until
2007, following a survey
undertaken by Mr Taris. Mr Diprose showed Mr Taris around the land and
subsequently made several changes
to the indicative boundaries during the
survey. One of those changes was to the boundary of the main block covenant to
allow an
area for overburden from the quarry to be deposited. Mr Diprose
deposed Mr Dean agreed to the alteration and commented “it’s
better
to change now as it will be difficult to change later”.
- [18] The
covenants, featuring the now-agreed boundaries depicted in aerial plans, were
registered over the blocks on 15 October 2007.
The economic benefits of
the covenants to Mr Diprose were modest: a sum of approximately $11,000
from the Trust for surveying, fencing
and planting, and approximately
$7,000 from the Regional Council for the latter two, together with a
modest annual rates remission
in respect of the land (which was less than $150).
- [19] The most
relevant clauses of the covenants are cls 2.1, 2.2(g) and 4.1 of sch 2.
Clause 2.1 provides:
2.1 No act or thing shall be done or
placed or permitted to be done or remain upon the Land which in the opinion of
the Board materially
alters the actual appearance or condition of the Land or is
prejudicial to the Land as an area of open space as defined in the Act.
Clause 2.2(g) provides the owner agrees not to “[c]arry out any ...
quarrying of any minerals ... or other substance”
without the prior
written consent of the Trust. Clause 4.1 provides:
4.1 If notified by any authority, body or person of an intention to erect any
structure or carry out any other work on the Land, the
Owner agrees:
(a) to inform the authority, body or person of this Deed;
(b) to inform the Trust as soon as possible; and
(c) not to consent to the work being done without consulting
the Trust.
- [20] Schedule
3 of the covenants recorded special conditions relating to the use of the land.
Both covenants allowed the continued
use of farm tracks and water for farming
purposes, and cl 3 of sch 3 of the main block covenant allowed the continued use
and expansion
of communications and radar facilities located in the south-east
corner of the main block. There is no special condition allowing
expansion of
the quarry into the covenant areas.
- [21] In 2009
Hiona (and Mr Diprose) agreed to sell both blocks to Kaimai. During
negotiations, the Swaps first became aware of the
open space covenants.
Following legal advice, the sale proceeded in September 2009 with ownership of
the blocks transferring to
Kaimai.
- [22] In 2012,
the Swaps determined the quarry would soon need to expand south, thereby
affecting 40 ha of the covenanted area. Following
a formal proposal by its
sister company, Bartons, to expand the quarry, Kaimai advised the Trust of the
request in October 2015.
Kaimai took the position that cl 4.1 only obliged it
to consult with the Trust, but the Trust had no right of veto over the
expansion.
- [23] In November
2015, the Trust advised it considered it had a veto right and did not consent to
the expansion.
- [24] Kaimai
commenced this proceeding in 2017.
Some observations on the
evidence
- [25] We turn
from this summary to make three observations on the evidence.
- [26] First, Mr
Diprose plainly made a series of errors. It was certainly an error not to
consult with the licensee quarry-operator
about the proposed covenants. It was
probably an error not to obtain legal advice. It is possible Mr Diprose also
made a mistake
as to the meaning of the covenants, although he plainly
appreciated that the covenants would affect flexibility in development, to
some extent. In fact, cls 2.1 and 2.2 could hardly be clearer. That is
why he made boundary changes in 2007 at the time of the
survey, and had the
discussion with Mr Dean about it being better to fix it now rather than later.
But he cannot sensibly have imagined
that cl 4 had the effect he claimed in
evidence: it would have meant he did not need to reorder the boundaries in
the way he had
done in 2007 when finalising the covenants for registration.
- [27] Secondly,
the appellant has not demonstrated on the evidence Mr Dean had any apprehension
of a mistaken understanding by Mr Diprose
about the effect of
the covenants. Quite the contrary; Mr Dean did remind Mr Diprose of the
restrictive effects of the covenants
generally and was quite willing to alter
the boundaries — as evidenced by his actions in 2007 and the evidence
noted at [14]. In any case, it was not
the Trust’s responsibility to provide legal advice on the effect of the
covenants to applicants.
- [28] Thirdly,
Kaimai of course bought the land with its eyes open. The sale agreement
expressly recorded the issue:
24.0 The parties hereto acknowledge
that there may be difficulties with the QEII National Trust in relation to
the Open Space Covenant
on the land. The director of the Vendor, Ian Bruce
Diprose, will assist the Purchaser in resolving the difficulties with the Trust.
The parties will review the situation in relation to the negotiations with the
Trust on or before 24 September 2009. In the event
that satisfactory progress
has not been made the parties agree to revisit either the price or the
settlement date. It is not anticipated
that there will be a problem with the
boundary adjustment with the QEII National Trust.
- [29] The last
sentence proved optimistic. Kaimai’s solicitor conferred with
the Trust’s lawyer before settling. The
Trust advised him that any
proposal for adjustment to the extent of the covenanted land would require
careful consideration and a
unanimous decision by the Trust board. Further,
that if any loss of protected areas was proposed, that loss might well need to
be
compensated by formal protection of other areas in the locality. Ultimately
the issue has not been resolved by agreement. At least,
not
yet.
Issues
- [30] Counsel for
the appellant identified six issues for our consideration. We are satisfied
these can be decanted into two more
general issues:
(a) Did the
Judge err in construing the covenants?
(b) Did the Judge err in refusing to rectify the covenants?
Did the Judge err in construing the covenants?
- [31] The Judge
began by setting out the approach to the construction of instruments creating
interests in land.[6] The Judge noted
the approach to the admissibility of extrinsic evidence taken by William Young
and O’Regan JJ in Green Growth No 2 Ltd v
Queen Elizabeth the Second National
Trust.[7]
She did not need however to address the question of extrinsic evidence because
the Judge considered the meaning of cl 4.1 to be plain
on its
text.[8]
- [32] The
Judge first rejected Kaimai’s construction giving the owner a power to
consent to works in the covenanted area as inconsistent
with cl 2.1, which
focusses on the nature of activity rather than who does the activity and
reserves decision‑making power
to the Trust
board.[9]
- [33] Secondly,
the Judge found such a construction would also be at odds with cl 2.2,
which provides the owner will not carry out
the specific listed activities in
paras (a)–(j) except with written consent of the Trust (or as
provided for in sch 3).[10]
Kaimai’s interpretation would allow the owner to circumvent cl 2.2 by
permitting third parties to carry out the activity the
owner had by covenant
agreed not to.[11]
- [34] Thirdly,
the Judge also found Kaimai’s construction would be inconsistent with cl
2.3, which provides the board will not
unreasonably withhold consent to requests
under cl 2.2. The Judge considered this meant control over activities in the
covenanted
land rests with the Trust and the owner’s rights were severely
curtailed.[12]
- [35] Fourthly,
the Judge also considered a broad discretion for the owner to consent to
activities would be inconsistent with the
“carefully delineated
carve-outs” of the listed activities in sch 3 which were permitted in
the covenant boundaries.[13]
- [36] Finally,
the Judge considered Kaimai’s construction would be inconsistent with the
purposes of the covenants — to
protect the environmental value of the land
in perpetuity by preserving the natural character of the land —
interpreted in
light of the Queen Elizabeth the Second National Trust Act
1977.[14]
- [37] Recourse to
extrinsic evidence or the contra proferentem rule was unnecessary as the meaning
of cl 4.1 was clear on its terms.
In any respect, and for the reasons discussed
when considering rectification, the Judge found extrinsic material did not
favour
the construction Kaimai
advanced.[15]
Submissions
- [38] Kaimai
makes three submissions on the construction of cl 4.1. First, Kaimai submits
the Judge failed to consider the differences
in experience and sophistication
between Mr Diprose and the Trust when considering what meaning an objective
observer would take
them to have intended.
- [39] Secondly,
Kaimai submits the construction the Judge adopted is inconsistent with the
admissible background context. It argues,
applying Green Growth No 2 Ltd v
Queen Elizabeth the Second National Trust, the admissible extrinsic evidence
should include those facts a reasonable reader of the covenants could be
expected to be aware
of, including facts necessary to avoid a perverse
outcome.[16]
- [40] Kaimai
submits the following extrinsic evidence is admissible as a starting point: the
location of the quarry proximate to the
covenanted areas; the inevitable
expansion of the quarry; publicly available documents showing the quarry was
expected to expand
into covenanted areas; and the likelihood the landowner would
receive financial benefits from the operation of the quarry.
- [41] The
following further extrinsic evidence is also said to also be admissible by
reason of Kaimai’s historical involvement
in the area: Mr Diprose’s
reliance on Mr Dean to reflect his needs in a
bespoke clause; the comparatively small financial benefits to Mr Diprose of
covenanting; Mr Diprose’s
communicated expectation he would receive
royalties when the quarry expanded over the stream to the south;
the flexible approach
to adjusting quarry boundaries between Mr Diprose and
the Swaps; the terms of the covenant being put forward on a take it or
leave
it basis; Mr Dean’s reassurance Mr Diprose would remain the
owner of the land; and Mr Diprose’s relative lack of legal
sophistication (relevant to its first submission set out at [38] above).
- [42] Third,
Kaimai submits cl 4.1 is silent as to who may consent to third party requests
and this ambiguity should be resolved by
application of the contra proferentem
rule given the differing expertise of Messrs Diprose and Dean, and
the former’s reliance
on the
latter.
Discussion
- [43] We do not
think the Judge’s construction of the covenants can be faulted.
We identify no error in the five reasons given
by the Judge for rejecting
Kaimai’s construction, summarised at [32] to [36] above.
- [44] In Firm
PI 1 Ltd v Zurich Australian Insurance Ltd the Supreme Court identified
three fundamental aspects of the construction of contracts: the objectivity of
the interpretation exercise,
the primacy of the text, and the relevance of third
parties to the scope of the
exercise.[17] In particular, in New
Zealand the aim of contract interpretation is to ascertain the meaning the
contract would convey to a reasonable
person, having the background knowledge
reasonably available to the parties in the situation they were in at the
time of the contract.[18] The
greater the extent of potential third party dependence (such as in long-term
utility contracts or covenants that are registrable),
the less receptive the
common law is to receipt of extrinsic evidence to “explain”, or to
controvert, the objective meaning
found by the method described in the preceding
sentence.
- [45] In Green
Growth No 2 Ltd v Queen Elizabeth the Second National Trust William
Young and O’Regan JJ (joined on this specific point by Glazebrook J)
postulated that, generally, registered documents
should be construed without
regard to extrinsic evidence which is particular to the original parties and is
not apparent on the face
of the
register.[19] That was subject to
this qualification: that “facts which a reasonable future reader of
the document could be expected to
be aware of and would recognise as relevant
and which they have access to, such as the configuration of land, any physical
features
to which the document relates or refers and any material referred to in
the document” would be admissible.
[20]
- [46] In
this appeal the extrinsic evidence really does not take Kaimai far. That is for
two reasons. First, because, as the Supreme
Court also held in Lakes
International Golf Management Ltd v Vincent, the objective meaning of
the provisions here are crystal
clear.[21] In this respect we agree
entirely with the Judge’s conclusions summarised at [32] to [37] above.
Secondly, because nothing
in the extrinsic evidence advanced justifies departure
from that clear meaning. A more insightful landowner might have been more
careful in fixing the boundaries of the covenanted areas, but Mr Diprose
did not exercise that caution here, despite two opportunities.
There is nothing
in the extrinsic evidence to suggest an objective common intention as between Mr
Diprose and the Trust to qualify
the covenant boundaries, to enable southward
expansion of the quarry into covenanted land. Rather, this was a clearly
drafted agreement,
the objective effect of which was readily apparent in 2005.
It was then given certainty by the subsequent inclusion in 2007 of the
aerial
plans, which themselves incorporated specific agreed changes. At the end of the
day it is simply a bargain Mr Diprose repents
making.
- [47] It is
unnecessary for us to say more on that subject. The Judge did not err in
construing the covenants.
Did the Judge err in refusing to
rectify the covenants?
- [48] The Judge
first set out the requirements for rectification of a common
mistake.[22] The Judge also
considered rectification may be ordered where one party made a unilateral
mistake and the other party actually knew
of that
mistake.[23]
- [49] As to the
former, the Judge noted much rested on the evidence of discussions between
Messrs Diprose and Dean at the time. Both
witnesses were said to be honest and
candid, but there were issues of reliability given over 12 years has passed
since the events
in question.[24]
The Judge held though Messrs Diprose and Dean contemplated the quarry expanding,
they shared no common intention the covenants would
provide for a right for the
quarry to expand into the covenanted
areas.[25]
- [50] First, in
2005 the quarry was intended to expand to the east and not south into the
covenanted areas.[26] There was no
intention to expand the quarry into the area covered by the LIA at the time it
was agreed. The quarry boundary did
not change between the 1982 and 1993
agreements. The certificate of compliance granted in 1998 only covered existing
quarry rights
that extended to the east and not into the now covenanted areas.
The DCP showed expansion was to be to the east. In the Judge’s
view the
DCP was significant — it involved Mr Diprose and the Swaps and could be
taken to provide the best evidence of contemplated
quarry expansion in 2005, as
the DCP was agreed only two years prior and was appended by Mr Dean to his
report. The conservation
areas in the DCP generally corresponded with the
covenant areas. The Judge found southward expansion was only contemplated in
2012
following consultation with local iwi, the Swaps having consulted
Ngāti Hinerangi and better understanding the significance
of Te Weraiti and
the Mangapiko stream (both situated to the east) for that iwi.
- [51] Secondly,
evidence of the discussions at the time the covenant boundaries were surveyed
suggested expansion was to be provided
for, if at all, by changing
the covenant boundaries, rather than by giving Mr Diprose a right to
consent to expansion into covenanted
areas.[27] The surveyor, Mr Taris,
recorded Mr Diprose saying in 2007 that quarry operations “are not allowed
to extend past or disrupt
the stream”, which the Judge considered
inconsistent with an expectation in 2005 that the quarry “would, in the
future,
do just that”. The evidence noted at [17] above was
to same effect.
- [52] Thirdly,
there was no outward expression of
accord.[28] Mr Diprose in evidence
did not go as far as saying he told Mr Dean the covenants would allow expansion
into the covenant areas.
Neither could Mr Dean recall, nor did his
contemporaneous report mention, Mr Diprose referring to southward
expansion.
- [53] Having
ruled out rectification of a common mistake by Messrs Diprose and Dean, the
Judge also found the covenants could not be
rectified to reflect Mr
Diprose’s unilateral mistaken intention. First, Mr Diprose’s
evidence he was mistaken as to
the effect of cl 4 was corroborated to some
extent by Mr Taris.[29] But the
Judge doubted the reliability of their 12-year-old recollections, particularly
as expansion of the quarry into the covenanted
areas was not intended in 2005.
The Judge therefore doubted Mr Diprose was actually mistaken. Secondly,
there was no evidence Mr
Dean knew of any mistake by Mr
Diprose.[30] There was no direct
evidence of discussion of the clauses. Clause 4 was a “boiler
plate” clause and not specially drafted
for Mr Diprose’s
circumstances. There would be no indication from Mr Dean’s perspective,
the Judge found, that Mr Diprose
might have misinterpreted cl 4. Thirdly, the
Judge dismissed Kaimai’s argument that Mr Diprose was discouraged from
seeking
legal advice by the
Trust.[31] A letter to Mr Diprose
from the Trust dated 20 June 2005 stated Mr Diprose must pay for any
independent legal advice. The Judge
rejected that Mr Diprose’s
decision to seek no legal advice could be attributed to the Trust on the basis
of the letter. Regardless,
the Judge considered the question of legal
advice irrelevant to the issue of rectification — it showed no awareness
by the
Trust of Mr Diprose’s alleged
mistake.
Submissions
- [54] Kaimai
submits the Judge should have ordered rectification of Messrs Diprose and
Dean’s common mistake. The Judge is said
to have erred in requiring an
outward expression of accord rather than simply requiring Messrs Diprose and
Dean’s common intention
be objectively apparent. Mr Diprose’s
evidence as to his intentions and discussions with Mr Dean is said to not have
been
challenged. In concluding Messrs Diprose and Dean did not share the
contended common continuing intention, the Judge is said to
have relied on a
number of factual findings that were in error: (1) that the quarry
boundary did not change between the 1982 and
1993 agreements; (2) that there was
no intention to expand the quarry into the area covered by the LIA: the
existing quarry pit
sat within the area covered by the agreement and it related
to grazing, not quarrying; (3) in relying on the DCP, which was only
intended to
last 10 years whereas the quarry would operate far beyond: future
expansion to the south may not have been shown on
the plan; (4) in ignoring
Bartons’ actions at the quarry which were intended to allow expansion to
the south; and (5) in relying
on Mr Dean’s report (described at [15] above) as corroborating his evidence,
as it may have been incomplete.
- [55] In the
alternative, Kaimai submits the Judge erred in not ordering rectification to
give effect to Mr Diprose’s unilateral
mistaken belief. Kaimai asks this
Court to overturn its earlier decision in Tri-Star Customs and Forwarding Ltd
v Denning in which it held rectification for unilateral mistake is no longer
available.[32] Kaimai argues the
Judge was wrong to doubt Mr Diprose was actually mistaken. The Judge’s
reasoning rested on her (allegedly)
incorrect finding southward expansion of
the quarry was not contemplated. Kaimai says rectification should be
ordered as: (1) Mr
Dean had actual knowledge of Mr Diprose’s
mistake, knowing Mr Diprose wanted the quarry dealt with in the covenants
and that
it was not; (2) Mr Dean was wilfully blind to Mr Diprose’s
mistake as he was eager to execute the covenants; or (3) the Trust
effectively
discouraged Mr Diprose from seeking legal advice creating an environment in
which the relevant type of mistake could
be
made.
Discussion
- [56] At some
point it will be necessary to reconsider whether an outward expression of accord
is essential for rectification of a
common mistake, or whether it should suffice
that the common intention be objectively apparent, regardless of formal
communication.[33] Prevailing
authority within this Court favours the former approach, relying in turn on
English authority.[34] But
authority is divided: a 2014 judgment of this Court favoured Tipping J’s
formulation in Westland Savings Bank v
Hancock:[35]
That
while there need be no formal communication of the common intention by each
party to the other or outward expression of accord,
it must be objectively
apparent from the words or actions of each party that each party held ... an
intention on the point in question
...
- [57] Likewise,
it will eventually be necessary to reconsider the authority of this
Court’s decision in Tri-Star Customs and Forwarding Ltd v Denning.
A powerful case has been made by academic critics for its
reconsideration.[36]
- [58] But this is
not the case for either exercise. That is because, as we observed at the
hearing, this aspect of the appeal fails
in limine on the facts,
regardless of the legal analysis.
- [59] First, as
we noted at [46] above, there is nothing
in the extrinsic evidence to suggest an objective intention as between Mr
Diprose and the Trust to qualify
the covenant boundaries, to enable southward
expansion of the quarry into covenanted land. The same is true of a common
subjective
intention to the same effect. While
Mr Tarris corroborates Mr Diprose’s
evidence that he discussed expansion of the quarry with Mr Dean, publicly
available documentation
at the time showed the quarry would expand
eastwards rather than southwards. Expansion was expressly dealt with in
negotiating the
aerial plans (in effect, renegotiating the covenants) in 2007.
Mr Dean’s evidence, when cross-examined, was that he had no
intention of
shutting down the quarry. He understood it may need to expand, but
considered southward expansion (if raised) would
have been dealt with by setting
the covenanted areas back from the quarry. As it was, his understanding
was that the intended expansion
lay eastward.
- [60] Arguable
factual errors in the judgment regarding boundary changes between the 1982 and
1993 agreements and in finding the quarry
was not intended to expand into the
area covered by the LIA are all de minimis and beside the point. Similarly
immaterial are the
other points raised at [54] above. They take Kaimai nowhere
in establishing a common intention at variance to the written covenants.
Ultimately there is no proof here of the alleged common intention sufficient to
overcome, on the balance of probabilities, the inherent
likelihood the
written covenants represent the parties’
intentions.[37]
- [61] Secondly,
while Mr Diprose may have been mistaken as to the effect of the covenants, there
is no basis on the evidence to infer
that Mr Dean was aware of that such that an
equity might be raised against him.
- [62] We accept
Mr Diprose may have been mistaken about the effect of the covenants, albeit
(as we find) their objective meaning is
actually crystal clear. While Kaimai
points to Mr Dean’s knowledge Mr Diprose wanted the quarry dealt with
by the covenants
the evidence suggests Mr Dean considered the quarry was dealt
with by the location of the covenants and the likely location of any
expansion.
The covenants themselves offered no flexibility. Hence Mr Dean’s
advice (attested to by Mr Diprose) that “it’s
better to change now
as it will be difficult to change
later”.[38] Kaimai also fails
to highlight any real evidence from which Mr Dean would (or could, in the sense
of wilful blindness) have surmised
Mr Diprose’s mistake. Kaimai focused
instead on Mr Dean’s motives in encouraging execution of the covenants.
But equity
does not assail enthusiasm alone. Even if rectification for
unilateral mistake were available here, what is missing is any conduct
by Mr
Dean on which equity might fasten. He neither led Mr Diprose to his
misunderstanding, nor evidently was aware of it. Nor
do we accept
Kaimai’s allegation that the Trust discouraged Mr Diprose from
obtaining legal advice, an allegation which lacks
solid evidential
foundation.
Concluding observation
- [63] We
observe that this is an unusual case, in that covenants appear to have been
entered without complete understanding by the
former owner. It also appears
likely that, had the issue been raised in 2005 or 2007, the Trust would have
accepted a smaller covenanted
land area, accommodating potential quarry
expansion to the south. As we noted at the hearing, these circumstances might
be addressed
in an application for variation under s 22A of the Act, should
one be advanced.
Result
- [64] The appeal
is dismissed.
- [65] The
appellant must pay costs to the respondent for a standard appeal on a band A
basis, with usual disbursements.
Solicitors:
Tompkins Wake, Hamilton for Appellant
Gibson Sheat, Wellington for
Respondent
[1] Under s 22 of the Queen
Elizabeth the Second National Trust Act 1977.
[2] Kaimai Properties Ltd v
Queen Elizabeth the Second National Trust [2019] NZHC 1591 [High Court
judgment].
[3] The 1982 agreement.
[4] The 1993 agreement. It was
reached in 1993 but executed only in 1995.
[5] High Court judgment, above n
2, at [68].
[6] High Court judgment, above n
2, at [39]–[41].
[7] At [41], quoting Green
Growth No 2 Ltd v Queen Elizabeth the Second National Trust [2018] NZSC 75,
[2019] 1 NZLR 161 at [73]–[74].
[8] At [42].
[9] At [46]–[47].
[10] At [48].
[11] At [49].
[12] At [50].
[13] At [51].
[14] At [52].
[15] At [53].
[16] Green Growth No 2 Ltd v
Queen Elizabeth the Second National Trust, above n 7, at [73]–[74] per
William Young and O’Regan JJ.
[17] Firm PI 1 Ltd v Zurich
Australian Insurance Ltd [2014] NZSC 147, [2015] 1 NZLR 432 at
[60]–[63].
[18] At [60]. See the further
discussion of these principles in Bathurst Resources Ltd v L&M Coal
Holdings Ltd [2020] NZCA 113 at [34]–[48].
[19] Green Growth No 2
Ltd v Queen Elizabeth the Second National Trust, above n 7, at [74(a)] per
William Young and O’Regan JJ and [151], n 100 per Glazebrook J.
[20] At [74(c)].
[21] Lakes International Golf
Management Ltd v Vincent [2017] NZSC 99, [2017] 1 NZLR 935 at [28].
[22] High Court judgment, above
n 2, at [57].
[23] At [58], citing Andrew
Butler (ed) Equity and Trusts in New Zealand (2nd ed, Thomson Reuters,
Wellington, 2009) at [29.2.6]; and David McLauchlan “The
‘Drastic’ Remedy of Rectification
for Unilateral Mistake”
(2008) 124 LQR 608.
[24] At [59].
[25] At [63].
[26] At [64]–[74].
[27] At [75]–[77].
[28] At [78]–[81].
[29] At [85]–[86].
[30] At [87].
[31] At [88]–[90].
[32] Tri-Star Customs and
Forwarding Ltd v Denning [1999] 1 NZLR 33 (CA).
[33] See McLauchlan, above n 23, at 616–617; and Simon Connell
“Is an ‘outward expression of accord’ required for
rectification in New Zealand?”
[2018] NZLJ 186 at 188–189.
[34] Davey v Baker [2016]
NZCA 313, [2016] 3 NZLR 776 at [37]; and Hanover Group Holdings Ltd v AIG
Insurance New Zealand Ltd [2013] NZCA 442, (2013) 13 TCLR 702 at [30],
citing Swainland Builders Ltd v Freehold Properties Ltd [2002] EWCA Civ
560 at [33]; and Chartbrook Ltd v Persimmon Homes Ltd [2009] UKHL 38,
[2009] AC 1101 at [48].
[35] Robb v James [2014]
NZCA 42 at [21]–[22], quoting Westland Savings Bank v Hancock
[1987] 2 NZLR 21 (HC) at 30.
[36] Jeremy Finn, Stephen Todd
and Matthew Barber Burrows, Finn and Todd on the Law of Contract in New
Zealand (6th ed, LexisNexis, Wellington, 2018) at 356–357; Bridget
McLay “Rectification for Unilateral Mistake: Time for a Conceptual
Revision?” [2016] AukULawRw 11; (2016) 22 Auckland U L Rev 315; and David McLauchlan
“Rectification for Unilateral Mistake” (1999) 18 NZULR 360.
[37] Thomas Bates and Son Ltd
v Wyndham’s (Lingerie) Ltd [1980] EWCA Civ 3; [1981] 1 WLR 505 (CA) at 521; and
Westland Savings Bank v Hancock, above n 35, at 26–27.
[38] See [17] above.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2021/10.html