Home
| Databases
| WorldLII
| Search
| Feedback
Court of Appeal of New Zealand |
Last Updated: 18 May 2021
|
|
BETWEEN |
MELCO PROPERTY HOLDINGS (NZ) 2012 LIMITED Appellant |
|
AND |
ANTHONY JOHN HALL Respondent |
Hearing: |
16 March 2021 |
Court: |
Collins, Brewer and Dunningham JJ |
Counsel: |
A C Beck and J M Perry for Appellant A L Holloway and T A Cunningham for Respondent |
Judgment: |
14 May 2021 at 10.00 am |
JUDGMENT OF THE COURT
____________________________________________________________________
REASONS OF THE COURT
(Given by Brewer J)
Introduction
19.0 Due Diligence
19.1 This agreement is subject to and conditional upon the Purchaser being satisfied that the property is suitable for the Purchaser’s requirements following the Purchaser carrying out due diligent verification of the property, including by way of example and without limitation;
(a) the value and condition of the property;
(b) the terms of all encumbrances, rights and interests registered against the property;
(c) the terms and implications of the zoning or permitted use related aspects of the property and any statutory protection notices or designations on the property;
(d) compliance schedule requirements under the Building Act 2004;
(e) the overall financial suitability of the Purchaser’s proposed investment in the property, their ability to obtain necessary finance to complete the purchase and financial suitability of the tenant(s).
19.2 The Vendor shall provide the Purchaser upon request with such information (except insofar as the vendor is legally bound to keep such information confidential) which the Vendor has in respect of the property in order to assist the Purchaser to fulfil this condition.
19.3 The date of fulfilment is fifteen (15) working days following execution of this agreement.
19.4 The parties acknowledge that the conditions in clause 19.1 are inserted for the sole benefit of the Purchaser and at any time prior to this agreement being avoided may be waived by the Purchaser giving written notice of waiver to the Vendor.
Grounds of appeal
(a) The Associate Judge’s jurisdiction was a summary one. The Associate Judge could not determine whether Mr Hall was in breach of his obligations under the agreement and accordingly he was wrong to dismiss the application.
(b) The Associate Judge was wrong to hold that Mr Hall had no obligations of good faith in relation to the agreement, and failed to apply correctly the law relating to fulfilment of conditions.
The High Court decision
[4] At issue is whether Mr Hall was unable to avoid the agreement because Melco’s failure to satisfy the due diligence condition was due to Mr Hall’s default under the agreement in:
(a) failing to allow Melco access to the property to complete due diligence; or
(b) failing to advise Melco he did not intend to grant an extension of time for fulfilment of the due diligence condition.
[10] In an email of 12 December 2019, John Ellison, an Operations Manager, wrote to Mr Dee [a real estate agent acting for Melco] on behalf of Melco asking if there was an earthquake report and/or a building report available for the property. Mr Dee forwarded Mr Ellison’s email to Mr Hall with his recollection Mr Hall had advised him he did not have these reports. Mr Dee’s email to Mr Hall was copied to Mr Ellison.
[11] Mr Hall gave Melco access to the property on both 16 and 17 December 2019.
[12] During Melco’s inspection on 16 December 2019, Mr Hall confirmed he did not have reports on the building. Later that day, Melco engaged Silvester Clark, a structural engineering firm, to do a seismic assessment of the building.
[13] Melco’s builder and roofer inspected the property on 17 December 2019.
[14] On 23 December 2019, Silvester Clark advised Melco that it would not be able to do a physical assessment of the building until the week of 13 January 2020 with a view to completing a report by 17 January 2020. In an email that day, Mr Ellison asked Mr Dee to talk to Mr Hall to see if it would be possible to extend the due diligence deadline to 17 January 2020.
[15] On 24 December 2019, Mr Dee sent Mr Hall an email requesting an extension of the due diligence condition to 17 January 2020. On 26 December 2019, Mr Hall responded that he did not see any issues concerning the request but he would discuss any changes to the agreement with his solicitor, Paul May, in the New Year. Mr May was expected to return to work on 9 January 2020.
[16] On 6 January 2020, Melco, concerned about the expiry of the due diligence condition, decided to engage a second structural engineer, EQ Struc Ltd (EQSTRUC) to prepare a report on the property.
[17] On 7 January 2020, Mr Hall travelled for a camping trip in the Tararua Ranges, where there is apparently limited cellphone coverage. That day, at 8.06 am Melco’s Operations Support Coordinator, Jessica Isaacs, sent Mr Hall a text asking for the keys or access to the property.
[18] In an email at 1.24 pm on 7 January 2020, Ms Isaacs advised Alden Balili of EQSTRUC that she had spoken to her manager and asked if it would be possible for EQSTRUC to provide their report “prior to 10am on Friday as the deposit is due on Friday – this way he should have enough time to review your findings.” The Friday she refers to was 10 January 2020 which was after the due diligence condition expired. Mr Balili responded at 2.04 pm that: “If we can start tomorrow that is possible.” Ms Isaacs emailed Mr Balili again at 3.27 pm and wrote: “Awesome, thank you! Still trying to get through to get an answer on the whereabouts of the key.”
[19] During the afternoon of 7 January 2020, Mr Hall spoke to both Mr Dee and Ms Isaacs and said he would get back to them the next day as to whether he could give Melco access to the property. Later that day, Mr Hall sent a text to Ms Isaacs that he would be in Wellington on 9 January 2020 and would speak to Mr May about Melco’s request for an extension of the due diligence condition.
[20] Early on 8 January 2020, Mr Hall sent Ms Isaacs a text that he would provide access to the property if Melco’s engineer was available. It was arranged that Mr Hall would meet Ms Isaacs and Mr Balili at the property at 12 pm that day. At 10.22 am, Mr Hall sent a text to Ms Isaacs that due to an unforeseen delay he would need to postpone the meeting. Mr Hall says this was because he realised he had told friends he would be returning to his campsite and was unable to contact them to tell them of his changed plans.
[21] Mr Hall says he then received a telephone call from a person who had heard the property was on the market. This caused him to reflect on his decision to sell the property.
[22] At 6.10 am on 9 January 2020, Melco’s solicitor sent an email to Mr May requesting an extension of the due diligence condition to 17 January 2020. Mr May forwarded this email to Mr Hall. Mr Hall instructed Mr May he was not to respond to the request and was to cancel the agreement as soon as he was able to do so.
[23] During the morning on 9 January 2020, Melco received a preliminary seismic report on the property prepared by Silvester Clark. It indicated concerns and an inspection of the building was required but Silvester Clark could not carry out an inspection until the following week.
[24] Later that day, Melco’s solicitor telephoned the office of Mr May seeking an answer to the request for an extension of the due diligence condition. Mr May did not return the call.
[25] Melco neither confirmed nor waived the due diligence condition.
[26] At 5.03 pm, Mr May sent by email a letter to Melco’s solicitor purporting to cancel the agreement on the basis that Melco had failed to confirm the due diligence condition.
[51] Here, there is a case that Mr Hall satisfied his obligation to provide Melco with reasonable access. Melco was aware by at least 12 December 2019 (and possibly earlier) that a seismic report was not available for the property. It carried out inspections on 16 and 17 December 2019 and made no request of Mr Hall to inspect again until 7 January 2020; just two days before cl 19 expired and while Mr Hall was away from Wellington. Although Mr Hall initially agreed to a further inspection he says he could not keep that appointment. Whether Mr Hall was in breach in failing to provide access on 8 January 2020 is a matter about which there can be much argument. It is a trial issue which cannot be determined on this application.
(Our emphasis)
[53] As at 7 January 2020, when Mr Hall was asked for access, Melco had engaged two firms of engineers. Neither engineer was in a position to provide the report it required before the expiry of the due diligence condition.
[56] I am unable to accept Mr Collins’s submission. His counterfactual analysis requires for its validity upon the acceptance it is arguable that:
(a) had Melco been given access to the property on 8 January 2020 it would have requested EQSTRUC to provide an oral report prior to the expiry of the due diligence condition;
(b) that EQSTRUC would have been both able and willing to provide such a report knowing it was to be relied upon by Melco;
(c) that such a report would have been provided and satisfactory for Melco’s purposes; and
(d) that Melco would have acted on such a report and confirmed (or waived) the due diligence condition prior to Mr Hall cancelling the agreement.
[57] These are matters that are not addressed in Melco’s evidence. What is clear, Melco did not ask EQSTRUC to provide an oral report despite knowing its written report would not be available until 10 January 2020. There is no evidence from EQSTRUC that it would have been in a position to provide an oral report and would have done so if requested. Such a suggestion is inconsistent with Mr Balili’s email to Ms Isaacs of 7 January 2020 that its report required sign-off from EQSTRUC’s directors. There is no evidence about what an oral report would contain. There is no evidence, either, that Melco would upon the basis of an oral report have been prepared to confirm or waive the due diligence condition. There is, however, evidence to suggest otherwise. Ms Isaacs’s email to Mr Balili of 1.24 pm on 7 January 2020 notes that her manager would need the report prior to 10 am on 10 January 2020 so that he had time to review the findings.
[59] Melco submits that Mr Hall’s failure to communicate he would not grant an extension of cl 19 deprived Melco of the opportunity to waive the condition. I do not accept this argument.
[60] There was no obligation upon Mr Hall to advise Melco he would not extend cl 19. He had no express obligation to do so under the agreement and an obligation to do so cannot be implied. It is not necessary to make the agreement work nor is it so obvious it goes without saying. To imply such a term would require Mr Hall to prefer the commercial interests of Melco in the performance of the agreement to the detriment of his own interests in bringing it to an end and that cannot be correct.
[61] I do not accept the submission, either, that in deciding not to grant an extension of cl 19 or in failing to communicate that decision Mr Hall was subject to the default rule. Mr Hall was not exercising a unilateral contractual power. Clause 19 could only be extended by agreement of both parties. Even if a default rule applied, it did not require Mr Hall to sacrifice his own commercial interest for those of Melco. An agreement for the sale and purchase of land is not a contract requiring good faith.
(footnotes omitted)
Melco’s submissions on appeal
(a) The onus is on the applicants to demonstrate that they hold an interest in the land that is sufficient to support the caveat, but they need not establish that definitively;
(b) It is enough if the applicants put forward a reasonably arguable case to support the interest they claim;
(c) The summary procedures involved in applications of this nature are not suited to the determination of disputed questions of fact. An order for the removal of a caveat will only be made if it is patently clear that the caveat cannot be maintained — either because there is no valid ground for lodging it in the first place, or because such a ground no longer exists; and
(d) When an applicant has discharged the burden upon it, the Court retains discretion to remove the caveat which it exercises on a cautious basis. Before it does so the Court must be satisfied that the caveator’s legitimate interest would not be prejudiced by removal.
(footnotes omitted)
A party could be seen as benefiting from its own wrong if it seeks by cancellation to deprive the other party of the benefit of the contract in circumstances where the other party’s breach is a direct result of breach committed by the party seeking to cancel the contract. ... A party could also be seen as benefiting from its own wrong where it is unable or unwilling to perform its obligations under the contract and seeks to avoid liability for its own breach by cancelling the contract on the basis of the other party’s breach.
Mr Hall’s submissions
4.1 The High Court was right to find that Melco’s failure to fulfil clause 19 was not caused by Mr Hall. Melco’s own delay meant that, irrespective of Mr Hall’s actions and any problems accessing the Property, Melco was never going to receive an engineer’s seismic report by the contractual deadline. Melco also could have waived clause 19 and confirmed the contract before the deadline if it wished — as it ultimately purported to do on 24 January 2020.
4.2 The above finding does not result in Mr Hall ‘benefitting from his own wrongful act’. It was not ‘wrongful’ for Mr Hall to be out of town on 7, 8 and 9 January 2020. Nor did Mr Hall have a duty to tell Melco that he would not extend the due diligence deadline.
4.3 It is also open for the Court to find that Mr Hall did provide Melco with reasonable access to the Property.
32.1 It would have been unreasonable for Melco to take Mr Hall’s 26 December 2019 email or anything subsequent as:
(a) assurance than an extension would be granted; or
(b) assurance Mr Hall’s extension decision would be communicated to Melco in time for it to elect to confirm or waive clause 19.
32.4 Melco did not in fact rely on the 26 December 2019 email. It engaged a second engineer out of concern that no extension would be granted and instructed its solicitors to email a fresh extension request on the morning of 9 January 2020. The solicitors’ email shows Melco knew no extension had been granted and it is not consistent with any expectation that either party would forbear exercising their termination rights under clause 10.8(5). Melco could have waived clause 19 at any time until receipt of Mr Hall’s notice. Missing is evidence from Melco that it chose not to confirm the contract because something Mr Hall did or did not do caused it to believe that it would be given either an extension or an opportunity to confirm.
Discussion
(a) There are no complexities relevant to whether the Associate Judge was correct to exercise his summary jurisdiction;
(b) If Mr Hall was in breach of the agreement, he did not benefit from his wrong by cancelling the agreement; and
(c) Mr Hall did not prevent Melco from fulfilling the cl 19 condition.
Decision
Solicitors:
Gibson Sheat, Wellington for Appellant
Wotton Kearney,
Wellington for Respondent
[1] Melco Property Holdings (NZ) 2012 Ltd v Hall [2020] NZHC 2831 [High Court judgment].
[2] As required by cl 10.8 of the agreement.
[3] High Court judgment, above n 1.
[4] Philpott v Noble Investments Ltd [2015] NZCA 342 at [26].
[5] Noble Investments Ltd v Keenan [2006] NZAR 594 (CA) at [47].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2021/184.html