You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2021 >>
[2021] NZCA 225
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Arnerich v DHC Assets Limited [2021] NZCA 225 (3 June 2021)
Last Updated: 8 June 2021
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
ANTONY IVO ARNERICH Appellant
|
|
AND
|
DHC ASSETS LIMITED Respondent
|
Hearing:
|
4–5 November 2020
|
Court:
|
Goddard, Duffy and Nation JJ
|
Counsel:
|
J D McBride, and A J Steel for Appellant F J Thorp and L J Turner
for Respondent
|
Judgment:
|
3 June 2021 at 10.00 am
|
JUDGMENT OF THE COURT
- Mr
Arnerich’s appeal is allowed in so far as it relates to the award of
interest on the sum of $367,768.12. The award of interest
in the
High Court is set aside, and remitted back to that Court to be
determined in accordance with this judgment.
- DHC’s
cross-appeal is allowed. The proceedings are remitted back to the High Court to
determine the amount of any further claim
DHC may have against Vaco under the
construction contract, and, in light of that determination, to make such further
orders against
Mr Arnerich under s 301 of the Companies Act 1993 as may be
appropriate.
- Mr
Arnerich must pay costs to DHC on the appeal and cross-appeal, in each case for
a standard appeal on a band A basis, with usual
disbursements. We certify for
second
counsel.
____________________________________________________________________
Table of contents
Para No
REASONS OF THE COURT
(Given by Goddard J)
Introduction and summary
- [1] The
respondent, DHC Assets Ltd (DHC), is a construction company. It is an unpaid
creditor of Vaco Investments (Lincoln Road)
Ltd (Vaco). Vaco was put into
voluntary liquidation on 1 July 2014. Mr Arnerich, an experienced property
developer, was the sole
director of Vaco. Vaco was the vehicle through which Mr
Arnerich carried out a property development at a site on Lincoln Road in
Auckland.
- [2] The
structure Mr Arnerich put in place for the Lincoln Road development project also
involved a trading trust: the Vaco Investments
(Lincoln Road) Trust
(Vaco Trust). Vaco was the sole trustee of the Vaco Trust. The
discretionary beneficiaries of the Vaco Trust
were (ultimately) Mr Arnerich
and members of his family. Vaco acquired the property at Lincoln Road as
trustee for the Vaco Trust,
and carried out the development project in that
capacity.
- [3] DHC claims
it is owed some $1,088,156 plus interest by Vaco under the construction contract
it entered into with Vaco to design
and build a commercial building on the
Lincoln Road property. DHC was awarded $367,768 in an adjudication under the
Construction
Contracts Act 2002. DHC has pursued claims against Vaco for the
further amounts to which it says it is entitled. Vaco cannot pay
DHC any part
of the sum awarded in the adjudication, or the further sums DHC has claimed:
Vaco has no assets of its own, and there
are no remaining assets of the
Vaco Trust out of which the payment could be made by Vaco as trustee.
- [4] DHC brought
proceedings under s 301 of the Companies Act 1993 alleging that Mr Arnerich
had breached his duty to act in the best
interests of Vaco (as required by s 131
of the Companies Act) by causing Vaco to make substantial distributions to the
beneficiaries
of the Vaco Trust before DHC’s contractual claims had been
ascertained and paid by Vaco. DHC sought an order under s 301 that
Mr Arnerich
pay the amount DHC is owed by Vaco direct to DHC.
- [5] DHC’s
claim succeeded in part in the High
Court.[1]
Davison J found that Mr Arnerich had breached his duty to act in the best
interests of Vaco.[2] He made orders
requiring Mr Arnerich to pay DHC the sum of $367,768 awarded in the
adjudication.[3] But he declined to
determine whether DHC was owed further amounts by Vaco, and declined to make any
further orders against Mr Arnerich,
on the basis that the construction contract
required DHC’s claims against Vaco to be determined by other mechanisms,
and those
claims had previously been referred to
arbitration.[4]
- [6] Mr Arnerich
appeals to this Court. He says that he acted throughout in good faith and in
what he believed to be the best interests
of Vaco: he did not breach s 131
of the Companies Act. He genuinely believed that DHC had ceased to pursue its
claims, and that
those claims lacked any merit. He made provision for the
further claims that he believed might be made against Vaco by DHC and other
creditors, then distributed the balance of the Vaco Trust’s assets to the
beneficiaries of the Vaco Trust.
- [7] DHC cross
appeals, seeking orders that the High Court determine the amount it is owed by
Vaco, and that Mr Arnerich be required
to pay the whole of that amount direct to
DHC under s 301 of the Companies Act.
- [8] We have
concluded that Mr Arnerich breached s 131 of the Companies Act by causing
Vaco to distribute its remaining funds to his
family and associated interests as
beneficiaries of the Vaco Trust, without ensuring that Vaco retained sufficient
funds to meet
contingent claims by DHC. Mr Arnerich had an obvious conflict of
interest in making these decisions, which directly benefited him
and his family
while depriving Vaco of access to trust funds to meet any successful claims by
DHC. We doubt Mr Arnerich turned his
mind to the interests of Vaco as
a separate entity. But in any event, no rational director could have considered
that it was in
Vaco’s best interests to make those distributions, and risk
having insufficient trust funds in hand to meet DHC’s claims
if
successful.
- [9] We therefore
uphold the High Court’s order under s 301 of the Companies Act that Mr
Arnerich must pay DHC $367,768.12 plus
interest, though we modify the interest
award.
- [10] We have
also concluded that the High Court should have determined the total amount that
Vaco owed to DHC, and awarded DHC compensation
from Mr Arnerich for the full
amount of Vaco’s unpaid debt to DHC — a debt which Vaco would have
been able to meet but
for Mr Arnerich’s breaches of s 131. We
therefore refer the proceeding back to the High Court to determine the
amount that
DHC was owed by Vaco, and to make such further orders for
compensation as may be required in light of that finding.
Background
- [11] The
history of the dealings between DHC and Vaco is set out in considerable detail
in the High Court judgment.[5] For
the purposes of this appeal, a summary of those dealings is
sufficient.
Establishment of Vaco and
Vaco Trust and purchase of Lincoln Road property
- [12] On 5 November
2010, Vaco Investments Ltd (VIL) entered into a conditional agreement to
purchase a property at Lincoln Road for
the sum of $1.4 million.
Mr Arnerich is the sole director and shareholder of VIL. The parties
subsequently agreed to reduce the
purchase price to $1.325 million.
- [13] On 15 April
2011, Mr Arnerich incorporated Vaco as his vehicle to carry out a proposed
development at the Lincoln Road property.
The company’s initial name was
Rawhiti Property Holdings Ltd. On 16 August 2011, the name of the company was
changed to Vaco
Investments (Lincoln Road) Ltd. VIL was the sole
shareholder of Vaco, and Mr Arnerich was Vaco’s sole director.
- [14] On 4
November 2011, Mr Arnerich executed a deed establishing the Vaco Trust.
The deed appointed Vaco as the sole trustee of
the Vaco Trust.
The discretionary beneficiaries of the Vaco Trust were (ultimately, via
other trusts) Mr Arnerich and members of
his family.
- [15] The
purchase of the Lincoln Road property settled on 17 November 2011. There is a
dispute between the parties about the manner
in which that purchase was
effected. DHC says that Vaco had been nominated as the purchaser of the
property by VIL, and purchased
it for $1.325 million. Mr Arnerich says that VIL
agreed to sell the property to another company which he controlled, VDT
Securities
Ltd (VDT) for $1.325 million. VDT entered into an agreement for sale
and purchase with Vaco, under which Vaco, as trustee of the
Vaco Trust, agreed
to purchase Lincoln Road from VDT for the sum of $3.2 million. However, it is
common ground that Vaco only ever
paid $1.325 million for the property, and
that the balance of the purchase price that Mr Arnerich says was payable to
VDT has never
been paid. Mr Arnerich says it was a contingent liability that
VDT has never claimed. We return to this below at [174].
- [16] Mr Arnerich
identified ASB Bank as the principal tenant for the two-storey commercial
building that he proposed to build on the
Lincoln Road site. An agreement was
entered into between VIL and ASB to lease retail commercial banking premises to
be constructed
on the site. The lessor was to be VIL “or an associated
company related to the Lessor yet to be formed”. VIL also entered
into an
agreement to lease with The Coffee Club Properties (NZ) Ltd for a smaller
tenancy on the ground floor of the
building.
Vaco enters into
construction contract with DHC
- [17] On
18 October 2011, Vaco and DHC entered into a fixed price lump sum design and
build contract which provided for DHC to carry
out the construction work on the
development for the sum of $2,129,838. The construction contract included terms
that significantly
limited the scope for claims by DHC for extensions of time,
and for additional payment for variations. The construction contract
also set
out detailed procedures to be followed in relation to variations and extensions
of time. These terms — which had
been proposed by DHC — were
intended to give Vaco a high degree of confidence that the construction work
would be completed
by the agreed date of 27 July 2012, with liquidated
damages of $600 per calendar day excluding GST payable from that date until
practical
completion.
- [18] The
construction contract contained detailed provisions in relation to determination
of disputes between the parties. The dispute
resolution mechanisms contemplated
by the contract included formal engineers’ reviews, mediation, and
arbitration. The contract
also recognised the ability of the parties to
refer disputes to adjudication under the Construction Contracts
Act.
Financing arrangements with
ANZ
- [19] With
those agreements in place, Vaco was able to obtain financing for the project.
On 10 October 2011, ANZ National Bank Ltd
(ANZ) conditionally approved
Vaco’s application for project finance. On 10 February 2012, Vaco entered
into a facility agreement
for $5,155,000 with ANZ. The facility
agreement was entered into by Vaco as trustee of the Vaco Trust.
Vaco Investments (Basque
Road) Ltd as trustee of the Vaco Investments
(Basque Road) Trust and Mr Arnerich were named as guarantors. The facility
was intended
to fund the purchase of the site for $1.325 million, and to
fund the amount payable to DHC under the construction contract.
- [20] Mr Beagley
of Davis Langdon was appointed as the engineer under the construction contract.
The construction contract described
the role of the engineer as
follows:
6.2 Role of Engineer
6.2.1 The dual role of the Engineer in the administration of the
contract is:
(a) As expert adviser to and representative of the Principal, giving
directions to the Contractor on behalf of the Principal and issuing
Payment
Schedules on behalf of the Principal at due times; and
(b) Independently of either contracting party, fairly and impartially to
make the decisions entrusted to him or her under the Contract
Documents, to
value the work and to issue certificates.
...
- [21] Mr Beagley
was also appointed by ANZ as the bank’s quantity surveyor for the purposes
of payment arrangements in relation
to the construction work. The manner in
which DHC’s progress claims under the contract would be processed was set
out in a
letter dated 11 November 2011 from ANZ to DHC which read as
follows:
VACO INVESTMENTS (LINCOLN RD) LIMITED – BANKING
AND RETAIL CENTRE AT 290 LINCOLN ROAD, HENDERSON
With regard to the above project, I can confirm as follows:
ANZ National Bank Limited (the “Bank”) has an approved
Development Facility available to Vaco Investments (Lincoln Rd)
Limited that
includes an allocation sufficient to meet the Construction Contract Sum of
$2,129,838 (excluding GST). Upon receipt
of QS certification of each progress
claim and subject to there being no defaults under the Transaction Documents,
the Bank will
pay the progress claim direct to the account nominated by
[DHC].
The Bank will retain the monthly retention sums within the Development
Facility until Practical Completion has been achieved. Upon
Practical Completion
being achieved and the initial release of retentions having been certified, the
balance of the retentions will
be paid to an account in the joint name of Vaco
Investments (Lincoln Rd) Limited and [DHC] for subsequent payment in accordance
with
the Construction Contract.
If you have any queries, please let me know.
Kind regards
Michael Wright
Manager – Property Finance
DHC carries out the construction work —
disputes develop
- [22] DHC
proceeded to carry out the construction work at the Lincoln Road property. Mr
Arnerich was closely involved in the construction
process. So too were
representatives of ASB. At an early stage of the construction work, ASB
notified its requirements for a number
of variations from the original drawings
for the building, on the basis of which DHC had priced the building work, and
which had
been submitted for building consent. In the course of the
construction project, ASB required approximately 18 contract variations,
some of
which were significant and resulted in additional planning, construction work
and time for DHC.[6]
- [23] The project
encountered a number of delays as a result of the ASB variations, delays at the
front end of the project affecting
design work, ground conditions which required
piling work that had not been contemplated by the construction contract, and a
number
of other matters. DHC ultimately, towards the end of the project,
submitted four formal extension of time claims to the engineer
under the
contract. Vaco disputed DHC’s entitlement to claim extensions of time
under the construction contract and rejected
all four of these claims.
- [24] Some of the
contract variation instructions were dealt with in the formal manner
contemplated by the construction contract.
However, in many other instances,
the variation requests were made in a less formal manner, with Vaco forwarding
requests from ASB
on to DHC by email. In some instances, the variation requests
were made by Mr Arnerich orally to DHC’s site manager, during
visits by Mr
Arnerich to the site, or by telephone to the DHC project manager. These
variation requests were usually confirmed by
DHC in an email to Vaco.
Variations and their status were noted in construction reports prepared and
distributed by DHC for the
regular project control group meetings attended by
DHC, Vaco and Davis Langdon.
- [25] As the
construction work progressed, DHC made monthly payment claims in accordance with
the procedure contemplated by the construction
contract. DHC submitted its
payment claim to Vaco and to the engineer. The engineer then assessed the claim
and issued a provisional
Progress Payment Schedule to Vaco, copied to DHC. Vaco
had three working days to notify the engineer of any amendments or deductions
that it required. The engineer, acting as Vaco’s agent, would then issue
a Progress Payment Schedule (PPS) showing the sum
certified by the engineer
under the contract as the value of DHC’s payment claim, taking into
account Vaco’s amendments.
- [26] By
September 2012, the construction work was nearing completion. ASB took
possession of its tenancy area in the building to
begin its fitout work on 7
September 2012. This was later than the date contemplated by the construction
contract which, as noted
above, was 27 July 2012. In his email to ASB
confirming that date, Mr Arnerich said:
As discussed in our
recent telephone conversation regarding the handover date I have a confirmed
date [from DHC] of 7 September 2012.
We have collectively tried very hard to
keep as close as possible to the end of August. [DHC] realise the importance of
this handover
date and really put in the extra effort to make this happen.
- [27] By this
stage of the project, disagreements had arisen between DHC and Vaco in relation
to DHC’s claims for variations
and for extensions of time.
- [28] On 20
September 2012, Mr Beagley issued PPS 11, noting the value of the work completed
to 31 August 2012 was $2,134,743.00 (excluding
GST) and certifying the value of
payment under PPS 11 at $307,665.44 (excluding GST). Mr Beagley then issued a
Drawdown Valuation
and Payment Schedule to ANZ to enable a drawdown of
$265,439.00 (excluding GST) to be made on the Vaco Lincoln Road project finance
facility.
- [29] On 30
September 2012, DHC issued Payment Claim 12 for $528,807.87 (excluding GST).
The payment claim was addressed to Vaco and
copied to Mr Beagley. The
payment claim was to be reviewed and assessed by Mr Beagley in accordance with
the terms of the construction
contract. On 2 October 2012,
Mr Arnerich sent an email to Mr Beagley attaching a copy of Payment Claim
12 on which he had crossed
out the amount claimed and written: “Crap! ...
We need to go through this — fine tooth comb!” Mr Arnerich had
made
a series of handwritten comments on the payment claim indicating which of
the variations Vaco accepted or rejected, querying
the claimed amounts, and
commenting that there was a need for a number of items to be substantiated.
In his email to Mr Beagley,
Mr Arnerich said:
Hi Scott
I have attached my comments on [DHC’s] claim for you to review and have
copied in Anthony Parkin though I am not sure if he
will be assisting you on
this?
In any event I think we are getting very close to the point of having to take
these guys to task on allot [sic] of these additional
variations which are
clearly not approved or warranted.
I will be away from Friday 5th till Monday 15th and
will be available by phone or email if you need to contact me to discuss. In
terms of the ASB variations some of these have almost
doubled again which they
will no doubt flip out over so any correspondence I receive to that regard I
will copy you into. This time
round the points I think need to be covered
off are the Liquidated damages which currently stand at $39,000 Plus Gst and the
rejection
of all of the [extension of time] claim based on the email below which
outlines our contractual position on [extensions of time]
for weather and time.
I know that you though[t] it might be antagonistic last time but I think it
needs to be done now.
Also I think it is important that you reiterate your comments to the
contractor regarding the ground risk conditions they accepted
as part of the
initial review. This is getting really ridiculous now again more than
doubling!!
Apart from these minor technicalities the site is looking better now every
day and the ASB are make [sic] good progress on their fitout....and
we should
have our subdivision consent [out] next week.
Thanks
Antony Arnerich.
- [30] On 11
October 2012, Mr Beagley issued provisional PPS 12. The value of payment
certified for was $114,187.50 (excluding GST)
compared with the sum of
$528,807.87 (excluding GST) sought in Payment Claim 12. In his covering email
of 11 October 2012 sending
the provisional PPS to Vaco and DHC, Mr Beagley
said that the ASB variation payment values had not been included in the
schedule,
and that they would be included once confirmation was received of
agreed progress payment values by Vaco, ASB and DHC. The provisional
PPS noted
a number of other items claimed that had not been certified for payment.
- [31] Mr Moore of
DHC responded in an email sent to Mr Beagley and Mr Arnerich on 16 October
2012:
Scott [and] Antony
Please be advised that we are in disagreement to the attached Payment
Schedule and wish to arrange [an] urgent meeting to discuss.
In particular we
refer you to our emails (5 October) attached that addressed our concerns to the
Provisional Payment Schedule to
which we have had no response or correspondence
in an attempt to address. We find this situation very disappointing considering
we
have made concerted efforts to provide as much information as possible to our
entitlements with the claims we have made and all
we have received in return is
a Payment Schedule with minimal response to what we believe to be demonstrated
entitlements.
Given the difference in claim and certification I would have thought some
urgency would have been put into meeting to discuss in an
attempt to at least
understand all parties positions and viewpoints. This level of difference is
untenable and we kindly request
[an] urgent meeting before the certificate is
issued.
Please advise your availability.
Regards
Andy
- [32] Mr Beagley
summarised the situation as regards completion of the works and the outstanding
DHC payment claims and extension of
time claims in a letter to ANZ on 26 October
2012, reporting the status of the funding facility for the project for the
period ending
30 September 2012. In his letter, Mr Beagley confirmed that
handover of the premises to the ASB to commence its fitout had occurred
on
7 September 2012, and DHC had applied for practical completion on 15
October 2012 subject to connection of the electric power
supply (which was
connected on 16 October 2012).
- [33] DHC issued
Payment Claim 13 on 31 October 2012, in which it claimed $489,805.44 (excluding
GST). In a covering email, DHC advised
that substantiation for any new
variations or increases to existing variations would follow shortly.
Mr Arnerich responded requesting
invoices and information for each and
every variation requested by ASB and Vaco. On 2 November 2012, Mr Reyneke of
ASB sent an email
to Mr Arnerich commenting on the variation claim, which
had been received by ASB the previous day. Mr Reyneke said that ASB considered
the costs to be extremely high. He set out a list of information the bank
required regarding completion of items on ASB’s
defects list and other
items that were yet to be completed or attended to. On 15 November
2012, Mr Beagley issued PPS 13 for an
amount of $269.20 (excluding GST).
- [34] On 10
November 2012, prior to practical completion having been certified and without
DHC’s consent, Vaco took possession
of the premises other than the ASB
tenancy area. Almost a year later, on 4 October 2013, Davis Langdon, on behalf
of the engineer
to the contract, issued a certificate dated 28 June 2013 that
the contract works had reached a state of practical completion on 21
November
2012.
Further payment claims and
disputes
- [35] DHC
issued Payment Claim 14 on 30 November 2012 seeking payment of $429,193.96
(excluding GST). On 13 December 2012, Mr Beagley
prepared provisional
PPS 14 in which he calculated that DHC owed Vaco $41,132.77. In this
schedule, Mr Beagley disallowed the DHC
variation claims for the extensions
of time and for the soft spots in the basement area, as well as disallowing the
majority of DHC’s
claims for variations, noting in each case that Vaco had
assessed there to be no entitlement until the variation costs were
substantiated.
In relation to variation 38751, in which DHC claimed extension
of time costs of $75,000, Mr Beagley’s schedule reads:
[Extension of time] Claim (received 17Sept12) has been referred to
the Engineer for review. Details of $40k claim value (time?) increase
in the
period to be provided by [DHC]. Time related costs to date are deemed to have
been included within the P&G costs associated
with the respective variations
- [36] DHC
responded to provisional PPS 14 in an email sent to Davis Langdon and Mr
Arnerich on 27 December 2012:
Antony [and] Scott
We acknowledge receipt of your Progress Payment Certificate No.14 and the
content and comments made, however despite our best efforts
in both meetings,
discussions and correspondence to provide additional information and
substantiation to the significant differences
between claims made and
certification it appears we are no nearer in reaching any agreement. This
situation and difference has now
been ongoing for some months now and has become
untenable from our perspective as we believe the negotiable approach is not
being
reciprocated by all parties concerned.
Based on the Progress Payment Certificate issued by The Engineer under Clause
12.2 we wish to further formally record that we are
in disagreement and see no
further reason to proceed with the disputed amounts pursuant to Clause 13.2
(Engineer’s Review)
as The Engineer has been involved in the initial
meetings, discussions and correspondence and has issued the Payment Schedule
continuing
to agree with the disputed items, noting a “formal
decision” has not been stated. We therefore wish to notify of our
intention to seek reimbursement of the disputed items pursuant to either Clause
13.3 (Mediation) or 13.4 (Arbitration) of the Conditions
of Contract.
To reiterate, these disputes have been ongoing sometime now with our belief
that no real or reasonable consideration or urgency has
been shown to resolve
considering the significant amounts involved, therefore leaving us no other
option than to pursue the items
and amounts through the disputes provision of
the Contract.
It should also be noted that we do not consider the ASB Payment Schedule
(review of our variations) to be a document that can be
relied on as a true
review [of] our claims pursuant to Clause 9 of the Conditions of Contract.
We have no contractual relationship
with the ASB (being the Principals
Tenant), therefore any review of our variation claims should be carried out and
issued under Clause
9.3, at this moment “Assessed in accordance with ASB
Payment Claim attached” is contrary to the provision of the Contract.
I trust you will understand our position here and advise we will be in
contact in order to commence proceedings as soon as possible,
noting any
response from yourselves in respect of this notification will be considered and
reviewed.
Regards
Andy
- [37] DHC issued
Payment Claim 15 on 31 December 2012, seeking payment of $388,246.96 (excluding
GST). Mr Beagley issued provisional
PPS 15 on 7 January 2013 in which the value
of the payment was negative $12,070.00 (excluding GST).
- [38] DHC issued
Payment Claim 16 on 31 January 2013, seeking payment of $392,582.41 plus GST.
- [39] On 4
February 2013, Mr Arnerich forwarded to Mr Beagley and Mr Parkin of Davis
Langdon a marked up copy of DHC’s Payment
Claim 16 on which he had
made handwritten comments relating to a number of contract variations for which
payment was claimed. For
example, his comment in relation to 14 of the claims
was simply: “No”. Other claim items were noted: “$0 -
refer
to Eng[ineer].” In some instances, Mr Arnerich wrote,
“ASB”, indicating that he considered that ASB was responsible
for
that claim. In his covering email Mr Arnerich said:
Hi Scott and
Anthony
Please see my marked up version of the claim.
Please accept this as notification that under no circumstances are you to
release any part of the retentions as claimed. The contractor
has not made any
progress as to making good works [on] site which are substandard most particular
the faulty drainage resulting in
water egress [through] the block walls and
piles etc.
There has been no one on site for a long time.
...
- [40] On 13
February 2013, Davis Langdon sent Mr Arnerich Provisional Progress Valuation No
16. In the covering email, Davis Langdon
advised Mr Arnerich that as principal
to the contract, Vaco had two working days after receipt of the PPS to notify
the contract
engineer of any amendments or deductions that the principal
required to be made from the sum certified by the contract engineer.
The
schedule prepared by Mr Beagley listed some 80 variations for which payment was
claimed by DHC. In the “Comments/Reasons”
column were notations
which directly correlated to Mr Arnerich’s handwritten comments as
previously provided to Davis Langdon.
In those instances, where Mr
Arnerich had noted, “No” in his handwritten note,
Mr Beagley’s schedule states: “Vaco
do not agree this
cost”. In relation to the extension of time claim (item 38751) the
schedule states:
No Entitlement, [extension of time] Claim referred
to the Engineer for review. Details of claim value to be provided by [DHC]. Time
related costs to date are deemed to have been included within the P&G costs
associated with the respective variations. Further
request for information
submitted.
- [41] Mr Beagley
issued provisional PPS 16 on 13 February 2013, in which he certified the value
of payment as $0.00.
- [42] On 5 March
2013, Mr Beagley sent Drawdown Valuation 15 to ANZ, copied to Mr Arnerich. Mr
Beagley noted that practical completion
had been effectively achieved on 28
November 2012 with the code compliance certificate being issued by Auckland
Council, although
the practical completion certification was yet to be obtained.
He said:
....
We note as previously report[ed] that significant construction variation
claims/risk ($567,000 claimed vs. cost liability provisioning
of $363,000
included in the current cost to complete assessment) remain, with the major
disputed claims having been recently referred
for a formal Engineer’s
Review.
...
VARIATIONS
Construction variations (actual and potential, although excluding ASB and
Coffee Club changes) identified to date remain provisionally
assessed at
approximately $160,000.
We note that [DHC] have identified variation claims to date in the total
amount of approximately $629,000 (including credits for works
not completed and
including unsubstantiated [extensions of time] and soft-spot claims etc.) for
which liability of $363,000 ($174,109
paid) has been included within the current
budget and cost to complete provision as summarised below:
...
Vaco / [DHC] continue to negotiate variation claims and incomplete/defect
works with a view to conclude a Final Account value. We
note (as above) that
variation claims totalling $320,000 have recently been referred for
a Engineer’s Review in accordance
[with] the conditions of contract.
ASB tenant variations (identified and noted for separate payment to Vaco from
that ASB) [sic] remain assessed in the order of $205,000.
Extension of time claims (EOT), variation claims relating to “soft
spots” in the basement, time related construction expenses
and credits for
contract works not completed remain identified as the remaining significant
variation cost risk at this stage of
the project.
...
CONTINGENCY
...
There is effectively no remaining unallocated contingency for the
project. Which whilst not ideal, we note that with the project having achieved
both Practical Completion and [Code Compliance
Certificate] subject now only to
sale (waiting for settlement), we do not anticipate any further significant cost
to complete requirements.
We do however note that there remains significant
construction variation/final account agreement risk that identifies a potential
shortfall, that would require additional equity/funding to be contributed should
[DHC] be awarded variation values as currently claimed.
Negotiation and settlement of the construction variation claims,
associated Final Construction Account agreement and incidental consultant
and
holding costs associated with a protracted development period are identified as
the significant remaining contingent cost risk
at this stage of the
project.
...
- [43] Mr Arnerich
sent an email to Mr Irvine of ANZ on the same day, 5 March 2013,
recording that he disputed the DHC claims:
Hi Mr I[rvine]
By all means give me a call to reconfirm that most of if not all of the
contractors [sic] claims are fanciful and not worth printing
out and are
comprised of items clearly outside the [contract]...Also I not[e] there is no
mention of the pending $72,000 + GST liquidated
damages that are yet to be
applied.
I am very confident regarding the entitlement to these...and [in] any event
this will drag on way past settlement of the property
and will in effect become
solely my problem as the bank will not have any exposure.
I have forwarded you a copy of the instruction to Davis Langdon to review
these outrageous claims.
PPS[sic]-No problem for the survey
Speak to you tomorrow
Thanks
Antony Arnerich
DHCs letter to Mr
Beagley (6 March 2013) enclosing extension of time related materials and
submissions
- [44] On
6 March 2013, Mr McClatchy of DHC sent an email and letter to Mr Beagley
responding to requests for information to support
DHC’s claims for
variations and extensions of time. The email and its attachments, which
included detailed marked‑up
project programme schedules, were also copied
to Mr Arnerich. In the letter, Mr McClatchy set out a summary of the
circumstances
which had given rise to the project time delays and the grounds
upon which Extensions of Time 1, 2 and 3 were based. Mr McClatchy
advised
that DHC would welcome the opportunity to meet with Mr Beagley to clarify
any other items that he might require and to discuss
the claims in more
depth.
- [45] On 12 March
2013, Mr Parkin sent DHC a list of the variation claims that “[they were]
currently reviewing”. He asked
if the list was complete.
DHC replied with comments on each of the claims to be reviewed. Davis
Langdon forwarded DHC’s email
to Mr Arnerich for his
information.
DHC
Final Payment Claim — Payment Claim 17
- [46] On
15 March 2013, DHC submitted their final account, Payment Claim 17, which was
sent to Vaco and copied to Mr Beagley. The
payment claim was for $553,095.10
(excluding GST), which was the total calculated pursuant to the
Variation Schedule listing each
of the claimed contract variations. As at
that date Mr Beagley was yet to issue his further formal review
decision.
- [47] Upon
receipt of Payment Claim 17, Mr Arnerich sent an email to Mr Beagley:
Hi Scott
Please refer to the final account from [DHC]. There seem to be new items in
this claim please review and add those to the Engineers
reviews that are
currently underway.
Also after receipt of this claim it seems an appropriate time to review and
re-evaluate where everything sits.
I still do not have the required documentation to get a practical completion
certificate so will need to review and re-evaluate the
date of when this finally
gets resolved as clearly it isn’t. Also as part of this process works to
be completed to my satisfaction
on site will need to be taken into account.
Thanks
AA
- [48] On 15 March
2013, Mr Arnerich sent an email to Mr Beagley and Mr Parkin, attaching a copy of
Payment Claim 17 on which he had
entered either “X” against those
items that he did not accept, or “ASB” against those items which he
considered
were ASB’s responsibility. Apart from marking the items in
that way, he did not provide any other comments. In his email
to Mr Beagley and
Mr Parkin, Mr Arnerich said:
Hi Scott/Anthony
Looking at the final claim [from] [DHC] there seems to be more wild movements
in items [from] claim to claim. I have marked up the
variation schedule as
attached noting items to look at. In terms of the [practical completion] date
they are now technically 231
day[s] late or $138,600 plus GST. As mentioned in
my previous correspondence based on the information contained in the claim I
will
now re-look at the date for [practical completion] when we get all the
required information ...
- [49] On 18 March
2013, following a meeting between Mr Tim Fraser of DHC and Mr Parkin to discuss
the variation claims, Mr Fraser of
DHC sent Mr Parkin an email addressing each
of the claims which were to be reviewed by Davis Langdon and
Mr Beagley. Mr Parkin referred
Mr Fraser’s email to Mr Arnerich, who
then forwarded some further comments to Mr Parkin and Mr Beagley regarding
the variations
which he disputed.
- [50] On 28 March
2013, Mr Parkin sent an email to Mr Arnerich in which he set out his assessment
of the DHC variation claims. Mr
Parkin explained that he was still working on
three of the variation claims and that his assessment did not cover all of them.
In
a schedule he had prepared, Mr Parkin noted the differences in the amounts
claimed by DHC compared to the Davis Langdon assessment.
The schedule recorded
that several of the items listed were being reviewed. Mr Arnerich said in his
evidence that having regard
to this assessment and to DHC’s late extension
of time claims which had only been substantiated by DHC’s further
materials
provided in March 2013, he considered at that time that there was no
prospect of any further payments to DHC being certified by Davis
Langdon.
- [51] On 3 April
2013, Mr McClatchy sent an email to Mr Beagley in which he said he wanted to get
an update from him as to where he
understood everything was at regarding the ASB
project. Mr McClatchy said that DHC was keen to get some sort of movement on the
matter,
have a payment certificate issued and any outstanding money due to DHC
paid. On the afternoon of 4 April 2013, Mr Arnerich sent
an email to
Mr McClatchy inquiring about when some remaining work at the building would
be done. Mr McClatchy responded the same
day. He said that he had been trying
to contact Mr Beagley to find out how long it would take him to provide a
response to DHC on
all the matters that had been referred to him for
determination, and he asked Mr Arnerich whether he had received any updated
information
on the matter.
Vaco sale
of Lincoln Road property
- [52] Meanwhile,
on 7 November 2012, Vaco had entered into an agreement to sell the Lincoln Road
property for $8.4 million, with settlement
in April 2013. DHC was not aware of
this sale.
- [53] In an email
dated 27 March 2013, ANZ advised Vaco’s solicitors of the amount required
to discharge the bank’s mortgage
over the property that secured the
project finance facility. In addition to the amount required to repay the
principal and accrued
interest of the project finance facility, ANZ stipulated
that it would retain a total sum of $641,674 to be held on term deposit,
to
cover retentions and the outstanding costs of completion of the project. Of
that amount, $515,076 was to be retained to cover
the construction costs to
complete, and $80,559 would be retained as contractor retentions.
- [54] The Lincoln
Road property sale settled on 3 April 2013.
Payments made by Vaco following sale
of Lincoln Road property
- [55] The
Lincoln Road proceeds of sale of $8.4 million were applied to repay the ANZ
facility, which then totalled some $5,507,700.
In addition, ANZ retained
$561,115 to cover costs to complete, as contemplated by its 27 March 2013 email.
The sum of $80,559 which
ANZ had said would be held to cover contractor
retentions was not however retained by ANZ. Instead it was paid direct to
Vaco’s
ANZ bank account. The reason for this departure from ANZ’s
earlier indication is unclear.
- [56] Over the
following days, the bulk of the balance of $2,312,761 was distributed to Mr
Arnerich himself, to Arnerich’s family
members, and to related business
interests. On 8 April 2013, approximately $1,175,000 was paid to ASB to repay
borrowings by Mr
Arnerich’s interests. On 9 April 2013, the sum of
$1,036,131 was paid into Mr and Mrs Arnerich’s joint bank account.
These
payments are the primary focus of DHC’s claims that Mr Arnerich breached s
131 of the Companies Act.
- [57] In May
2013, ANZ agreed to release to Vaco the full balance of the costs to complete
amount it was holding on term deposit, on
the basis that there was no
“Direct Agreement” in place requiring ANZ to make payments to
DHC, the property had been
sold and settled, the ANZ facility had been repaid,
and the final account had been issued with $96,000 shown as owing to Vaco. Mr
Irvine of ANZ noted in an email dated 17 May 2013 that:
The Bank
expects that any further payments which may become payable under the
construction contract (e.g. [extensions of time], retentions
or otherwise) will
be settled between the parties to the contract.
- [58] Over the
period May 2013 to October 2013, Mr Arnerich made, or authorised, a number of
payments from Vaco’s bank account
to creditors of Vaco out of this
“cost to complete” provision. In particular, Mr Arnerich paid
ASB an agreed amount
for fitout credits of $363,838.50 (excluding GST).
- [59] Mr Arnerich
also authorised further payments to his family and business interests out of the
funds in Vaco’s bank account,
including:
(a) $50,000 on 11
June 2013;
(b) $30,000 on 2 July 2013;
(c) $30,000 on 25 July 2013;
(d) $45,000 on 20 August 2013; and
(e) $9,900 on 19 September 2013.
- [60] DHC says
these further payments to the Arnerich interests also involved breaches by Mr
Arnerich of s 131 of the Companies Act.
Vaco tax liability paid by other
Arnerich entities
- [61] It
appears that Vaco incurred a liability for tax in connection with the
Lincoln Road development of at least $311,218. This
was paid on behalf of
Vaco on 20 May 2014 by Mr Arnerich’s solicitors, Martelli McKegg. They
advised that to “make the
tax payment for Vaco Investments (Lincoln
Road) Trust, we journaled funds of $239,396.24 from Vaco Investments (Basque
Road) Limited
and $71,821.76 from Vaco Investments
Limited”.
Final Payment Schedule
No 17
- [62] On
1 May 2013, Davis Langdon issued Final Payment Schedule No 17. The value
assigned to the payment amount certified was $0.00,
and the schedule stated that
the net position was that the Principal’s Deductions totalling $95,728.00
(plus GST) were payable
by DHC to Vaco. Attached to the Certificate of
Payment was a schedule on which each of the DHC variation claims was listed and
in
respect of which there was a brief note setting out the reason or reasons why
the variation was disallowed. In many instances the
reason given was:
“Vaco do not agree ...”.
- [63] Although it
was described as a “final” payment schedule, in relation to
DHC’s extension of time claim for $182,462
the schedule
noted:
No Entitlement, [extension of time] Claim referred to the
Engineer for review. Details of claim value to be provided by [DHC]. Time
related costs to date are deemed to have been included within the P&G costs
associated with the respective variations. Further
request for information
submitted.
- [64] It appears
that in preparing Final Payment Schedule No 17, Davis Langdon had overlooked the
letter from DHC to Mr Beagley dated
6 March 2013 which provided additional
information requested by Mr Beagley in relation to the variation and extension
of time claims.
DHC says that this letter contained much of the information
that Final Payment Schedule No 17 treated as outstanding, and as preventing
certification of further claims.
- [65] In his
evidence, Mr Arnerich said that as he heard nothing from DHC following receipt
of Final Payment Schedule No 17, he concluded
that DHC had finally accepted that
they had no further claims against Vaco given their delay achieving practical
completion and their
consequential exposure to significant liquidated
damages.
- [66] However, on
6 May 2013, Mr McClatchy sent an email to Mr Beagley which was copied to Mr
Arnerich. He wrote:
Scott
Further to our conversation last week and all my previous emails can you
please advise where we stand with the [practical completion]
documentation for
this project.
In the latest schedule the client has made a deduction of 118 days for
[liquidated damages] that given the fact a [practical completion]
date
hasn’t been finalised and that all of the [extensions of time] have not
been responded to and also deducted off the schedule
seems extremely harsh.
Hence we would like to have some direction on where the [practical completion]
sits and also if we would
have a response on the [extension of time]
situation.
Regards
Stuart McClatchy
- [67] On 13 May
2013, Mr Fraser sent an email to Mr Parkin and copied it to Mr Beagley. In
his email Mr Fraser advised that DHC did
not agree with the assessments which
had been made in Final Payment Schedule No 17. He addressed a number of
the variation claims
in detail, referring to the supporting documentation that
had previously been provided by
DHC.
DHC’s follow-up email on 8
August 2013
- [68] On
8 August 2013, Mr McClatchy sent an email to Mr Arnerich to inquire about the
final account. He noted that DHC had not heard
anything from Davis Langdon
for a “very long time”. He said that DHC was not prepared to waste
any more time with Davis
Langdon, and would prefer to deal directly with
Mr Arnerich over the final account, if he was willing to do so. He asked
if a meeting
could be arranged. Mr McClatchy received an automated reply
advising that Mr Arnerich was out of his office for an extended period
and
would be returning to New Zealand in mid-September 2013. The automated message
advised that any queries should be referred to
relevant staff or to Mr
Arnerich’s solicitor.
- [69] Mr Arnerich
said in evidence that he was “shocked” when he received
Mr McClatchy’s 8 August 2013 email, and
he immediately sent an email
to Mr Parkin which read:
...
I have had an email from Stuart McClatchy saying they haven’t heard
anything from [Davis Langdon] for a long time? He also
says that he wants to
sort out the final account? I thought it was sorted in that they owe us almost
$100k?
You think they are fishing ?
AA
- [70] Mr Parkin
responded to Mr Arnerich by email that evening. He said:
I
wasn’t aware we needed to contract [sic] [DHC], I understand we are still
waiting on outstanding documentation in order to
issue [practical completion]?
Final account I am not sure where we got to. I will follow up with Scott but to
the best of my knowledge
we had communicated our stance on the outstanding
issues.
- [71] Mr Arnerich
replied:
Yes I thought so. Can you please check but I thought we
issued the final account as at minus $99k ish.
If you could see where we are at with this and let me know?
Once we know I will suggest to [Mr McClatchy] he contact you for an update.
- [72] On 19
September 2013, Mr Arnerich sent an email to Mr Beagley attaching a copy of
Progress Claim No 17. He said:
Hi Scott
Yes they did issue their final claim....I will forward the final progress
valuation to them that [Davis Langdon] sent. If you can
review with
Mr Parkin on Monday that would be good....Looking at this though it is
pretty clear what the position is ie we are owed
plenty.
Thanks
AA
- [73] Shortly
following this email, Mr Arnerich sent another email to Mr Beagley attaching
Final Payment Schedule 17 and commenting:
“This was the final progress
valuation/payment made to them. Let’s talk Monday...”
- [74] On 24
September 2013, Mr McClatchy telephoned Mr Arnerich and asked for a meeting with
him. Mr Arnerich said he would be unable
to meet until after he had seen the
engineer to the contract’s decision on the variations.
- [75] On 4
October 2013, Mr McClatchy followed up his telephone conversation by email to Mr
Arnerich asking if he could advise when
he would be available to meet in order
to finalise the account. Later that same day, Mr Parkin sent an email to
Mr McClatchy that
he copied to Mr Arnerich and Mr Beagley, attaching
the certificate of practical completion for the project. The certificate was
dated 28 June 2013, and certified that practical completion was achieved on
Wednesday 21 November 2012.
- [76] By 4
October 2013, Vaco had ceased trading. The only remaining asset of the company
at that time was a credit balance of $6,440.25
in its ANZ cheque account.
Further correspondence in relation to
DHC’s claims
- [77] It
is unnecessary for us to set out in detail the extensive continuing dealings
between DHC and Vaco in relation to the DHC claims.
Correspondence continued
into 2014. By letter dated 24 March 2014, DHC wrote to Vaco and Mr Arnerich to
advise that as their attempts
at negotiating a resolution had failed, DHC were
giving formal notice that DHC was in dispute under the contract. On 2 April
2014,
Vaco’s lawyers wrote to DHC denying any further liability.
Liquidation of Vaco
- [78] On
1 July 2014, Mr Arnerich, acting in his capacity as the sole director of VIL,
passed a shareholder’s resolution appointing
Victoria Toon, a chartered
accountant, as liquidator of Vaco. In his evidence, Mr Arnerich said that by
that point he had had enough.
The Vaco Trust had been wound up, and Vaco had no
assets.
- [79] On 2 July
2014, a lawyer acting for DHC sent an email to Mr McBride, attaching by way of
service a notice of adjudication. Mr
McBride replied stating that he was
“instructed to respond as follows:”
- Neither
DHC Assets Ltd nor Vaco Investments Limited were parties to the construction
contract, which was between Clearwater Construction
Ltd and Vaco Investments
(Lincoln Rd) Limited. Your Notice of Adjudication is of no effect.
- Vaco
Investments (Lincoln Rd) Limited was placed into liquidation on 1 July
2014. If Clearwater Construction Ltd wishes to commence
any adjudication claim
against it, it will first need to seek the leave of the court: Companies Act
1993, s 248(1)(c)(i).
- [80] On 4 July
2014, DHC lodged a proof of debt with the liquidator claiming that as at the
date Vaco was placed into liquidation
it was indebted to DHC in the sum of
$703,731.68.
- [81] DHC’s
Proof of Debt was noted by the liquidator, and DHC was included in the list of
Vaco’s creditors prepared under
s 255(2)(c)(ii) of the Companies Act and
attached to the liquidator’s first report dated 8 July 2014. In her
report, the liquidator
said:
4. Events Leading to
Appointment
The liquidator has been informed by the Director that the company ceased
trading last year as the purpose for which the company was
incorporated is no
longer applicable. We have been advised that the company has no known assets.
- [82] On 10 July
2014, DHC filed an amended proof of debt in which the debt claimed was increased
to $809,291.
- [83] By notice
of rejection dated 31 July 2015, the liquidator rejected DHC’s claim to be
a creditor on the basis that the DHC
debt included claims for variations to
the building contract which had been the subject of formal reviews by the
engineer, and the
decisions made by the engineer had not been challenged under
the disputes procedure in the contract. The liquidator’s notice
of
rejection stated that the engineer had decided in the final Payment Schedule
that DHC was not a creditor of Vaco, but a debtor
owing the company $95,728
plus GST, and Davis Langdon had advised that the time limit for challenging the
engineer’s decisions
under the disputes procedure in the contract had
expired.
- [84] At a
meeting of creditors on 1 August 2014, the liquidator informed the creditors
that Vaco was a corporate trustee which had
no assets and which had held the
land at Lincoln Road as a trustee
only.
Adjudication proceedings
- [85] In
February and March 2015, DHC, through its solicitors, requested the liquidator
to take steps to investigate the distribution
of funds by Vaco following the
sale of the Lincoln Road Property in April 2013, and to pursue recovery of those
funds. DHC contended
that the distributions were effected by Mr Arnerich in
breach of his duties as a director, as he was aware of DHC’s claim to
be a
creditor of Vaco at the time he arranged the distributions. In its
correspondence with the liquidator, DHC also maintained
that the
engineer’s review was fundamentally flawed and could not be relied upon.
DHC asked the liquidator to ascertain the
value of DHC’s claim by either
consenting to proceedings being commenced by DHC against Vaco, or directing the
engineer or
another expert to consider and advise on the claim. However, the
liquidator responded that she was not prepared to have the validity
and quantum
of DHC’s claim against Vaco determined by means of an adjudication.
- [86] In May
2015, DHC applied to the High Court for an order granting it leave to commence
adjudication proceedings against Vaco (in
liquidation). The application was
opposed by the liquidator on several grounds. Duffy J heard the application on
2 September 2015
and 3 February 2016. In a judgment delivered on 12
February 2016, Duffy J granted leave to DHC under s 248(1)(c)(i) of the
Companies
Act to commence adjudication proceedings under the Construction
Contracts Act against
Vaco (in liquidation).[7]
- [87] In October
2015, Mr Arnerich executed a deed of indemnity under which he indemnified the
liquidator in respect of all the liquidator’s
costs, expenses and
disbursements in relation to the liquidation of Vaco. The terms of the deed
included an acknowledgment that
Vaco had insufficient funds to pay the
indemnified sums, and provided for the liquidator to render invoices to Mr
Arnerich for all
indemnified sums. The recitals to the deed recorded that the
liquidation had been presented to the liquidator on the basis that
the company
was solvent at the time of liquidation on 1 July 2014.
The recitals also recorded that a third party had issued proceedings
against the liquidator, claiming to be a creditor of Vaco, and that the
indemnifier had agreed to indemnify the liquidator against
potential costs
arising from the liquidation of Vaco, and in particular against the costs of
defending the litigation.
- [88] After leave
had been granted by the High Court, DHC commenced the adjudication proceedings.
Although he was not a party to the
adjudication, Mr Arnerich participated
in the proceedings. He funded the liquidator’s participation in the
adjudication, and
also made his own submissions.
- [89] The
Adjudicator’s determination was dated 5 October 2016, and was released to
the parties on 12 October 2016.[8]
The Adjudicator, Mr John Green, recorded that DHC sought the following
determinations:
-
[Vaco (in liquidation)] is liable to pay [DHC] the sum of $686,208.11 including
GST or any other sum the Adjudicator may determine;
and
- [Vaco
(in liquidation)] is liable to pay interest on the above sum at the contractual
rate of 12.4%;
- [Vaco
(in liquidation)] is liable to pay [DHC]’s legal
costs;
- [Vaco
(in liquidation)] is liable to pay the whole of the adjudicator’s fees and
expenses in accordance with section 57 of the
Act;
- a
determination in respect of [DHC]’s entitlement to an extension of time
under the Contract; and
f a determination regarding the
release of the Performance Bond.
- [90] The
Adjudicator rejected Vaco’s submission that the engineer’s review
decisions were an effective bar to the DHC
claims because those claims were made
out of time. He noted that under the relevant general conditions of contract,
any decision
by the engineer to reject a late claim is discretionary, as there
may be valid reasons for delay and the lateness may not prevent
a proper
investigation. He further noted that the relevant guideline in the construction
contract provides that an engineer should
not refuse to grant an extension of
time on the ground of late application unless the lateness is such as to cause
real difficulty
in making a proper assessment. He concluded:
- Contrary
to Vaco’s submission, it is clear that under the Contract, an Engineer, in
the proper exercise of his or her duties
under the Contract, should investigate,
and where appropriate, grant an extension of time where the Contractor is
properly entitled
to the same in circumstances where the contractor fails to
give adequate and timely notice in terms of GC10.3.1, unless the lateness
is
such as to cause real difficulty in the making of a proper assessment.
- There
is no evidence in this case that the lateness of [DHC]’s applications for
[extensions of time] caused the Engineer any
difficulty investigating and
assessing those claims. In fact, by letter dated 20 December 2012, the Engineer
expressly invited [DHC]
to provide further information in support of claims for
[Extensions of Time] 1, 2, and 3. [DHC] responded substantively by letter
dated
6 March 2013. The Engineer then dallied and delayed for some seven months
before ruling on [DHC]’s [extension of time]
claims, even if his assertion
that he made and posted his Engineers Review 2 on [21] October 2013 were
accepted, which it is not.
- Rather,
I have found it more likely that the Engineer’s Review 2 was provided to
[DHC] on 20 January 2014 for the first time,
irrespective of when it was
actually made, and that such review did not take into account the further
information provided by [DHC]
on 6 March 2013 when rejecting [DHC]’s
[extension of time] claims.
- Taken
overall, I reject any suggestion by Vaco that delay on the part of [DHC] making
applications for [extension of time] caused
any difficulty for the Engineer in
making a proper assessment of those claims, such that the Engineer had any basis
for rejecting
the applications on that ground alone.
- [91] The
Adjudicator upheld all four of DHC’s extension of time claims totalling
147 calendar days.[9] As a
consequence, the Adjudicator also upheld DHC’s claim that Vaco was wrong
to deduct $70,800 from the Final Payment Schedule
as liquidated damages for a
period of 118 days from 28 July 2012 to the date of practical completion on
21 November 2012.[10]
- [92] The
Adjudicator also determined that Vaco was required to pay DHC the sum of
$300,763.12 together with interest at a daily rate
until payment. Included
within that sum was an amount of $131,909.15 for contract
variations.[11]
- [93] However,
the Adjudicator disallowed DHC’s claim for time-related costs related to
extensions of time to the due date for
completion totalling approximately
$200,000.[12] The Adjudicator found
that the insuperable difficulty for DHC was that the time-related costs it had
claimed related to P&G
costs, which were precluded by the terms of cl 4.4 of
the Contract Performance
Agreement.[13]
- [94] The Adjudicator
considered that the merits of the parties’ cases should be reflected in
the costs awards. He said:
- [DHC]
has clearly been the successful party in this adjudication. Each party took the
risk that its stance on the matters at issue
would be vindicated in an
adjudication and, on that point, it is [DHC]’s view as to its entitlement
to extensions of time,
release of the bond and payment for improper deductions
in respect of liquidated damages, variations and Principal’s deductions
that has prevailed substantially.
- [95] The
Adjudicator allocated responsibility for paying his fees and expenses between
DHC and Vaco at 25 per cent and 75 per cent
respectively. He directed that Vaco
pay 75 per cent of DHC’s costs and expenses, and directed Vaco to pay
costs to DHC of
$29,775 together with a further $7,590 as part reimbursement for
the payment DHC had made of $20,000 as security for the Adjudicator’s
fees
and expenses.[14]
The Adjudicator also directed that DHC was entitled to release of the
performance bond it had provided under the terms of the
contract.[15]
DHC
refers its claims to arbitration
- [96] Following
receipt of the Adjudicator’s determination on 12 October 2016, DHC sought
the liquidator’s consent to refer
the DHC claims which the Adjudicator had
disallowed to arbitration pursuant to cl 13.4.2 of the General Conditions of the
Contract.
The liquidator declined to consent to the commencement of arbitration
proceedings.
- [97] On 15 March
2017, following a formal proof hearing in the High Court, Lang J made
orders granting DHC leave under s 248(1)(c)
of the Companies Act to commence
arbitration proceedings against Vaco (in liquidation), and to apply to the
District Court pursuant
to s 73(2) of the Construction Contracts Act for the
Adjudicator’s determination to be enforced by entry as a
judgment.[16] On 26 April 2017, DHC
applied to the District Court at North Shore for the Adjudicator’s
determination dated 5 October 2016
to be enforced by entry as a judgment. Vaco
was served but took no steps. On 11 May 2017, the District Court entered the
determination
as a judgment of the District Court in favour of DHC against Vaco
in the sum of $367,768.12 (including
GST).[17]
- [98] DHC then
proceeded to refer to arbitration the claims in relation to time-related costs
and P&G costs that had been disallowed
by the Adjudicator. Mr John Walton
was appointed as the arbitrator.
- [99] In August
2017, Mr Arnerich commenced a separate proceeding in the High Court against
Vaco (in liquidation), the liquidator,
and DHC, seeking orders directing the
liquidator to bring a counterclaim in the arbitration, or in the alternative
that he be given
leave pursuant to s 165 of the Companies Act to bring a
counterclaim in Vaco’s name in the arbitration as a derivative action.
All three defendants opposed Mr Arnerich’s application. On 28 March 2018,
Associate Judge Sargisson declined to grant Mr
Arnerich leave to seek an
order that the liquidator be directed to file a counter‑claim in the
arbitration.[18] Mr
Arnerich’s application to rescind that order was dismissed by Associate
Judge Sargisson on 3 August
2018.[19] The application for leave
to bring a derivative action was subsequently discontinued.
- [100] The
arbitration has not proceeded to a hearing. It appears the parties saw it as
superseded by the proceedings brought by DHC
against Mr Arnerich which are the
subject of this appeal.
DHC’s
proceedings against Mr Arnerich
- [101] In
March 2017, DHC brought proceedings against Mr Arnerich under s 301 of the
Companies Act. DHC applied for summary judgment.
The application was
unsuccessful.[20]
- [102] Following
the refusal of summary judgment, DHC re-pleaded its claim and proposed that the
liquidator be joined as a party in
the proceeding. However, that
application was made at a late stage, and by minute dated 26 July 2018
Associate Judge Bell ruled
that the proceeding should continue without
the liquidator being joined, on the basis that any judgment in the decision
would be
binding on both DHC and Mr Arnerich in relation to the standing of
DHC as a creditor of Vaco, and in relation to the amount of any
liability of
Vaco to DHC. In response to that minute, the liquidator filed a memorandum
dated 17 August 2018 in which she noted,
among other things, that the liquidator
had previously advised the Court by memorandum dated 3 November 2017 that
she was willing
to abide the decision of the Court on the amount that is found
to be due under the construction contract in the proceedings between
DHC and Mr
Arnerich, and that remained her position.
- [103] From this
point onwards all parties proceeded on the basis that the amount (if any)
owed by Vaco to DHC, over and above the
amount awarded in the adjudication,
would be determined in these proceedings. Hence their decision not to progress
the arbitration
before Mr
Walton.
DHC’s allegations
against Mr Arnerich
- [104] The
proceedings went to trial on the basis of DHC’s third amended statement of
claim dated 2 August 2018, in which DHC
pleaded two causes of action.
DHC’s pleading set out its claims against Vaco under the construction
contract. The pleading
alleged that with full knowledge of those outstanding
claims by DHC as a creditor of Vaco, Mr Arnerich procured Vaco to make
distributions
out of the proceeds of sale of the Lincoln Road property to
himself and his family interests.
- [105] The first
cause of action alleged that by distributing Vaco’s assets to himself and
his family interests Mr Arnerich had
breached his fiduciary duties and his duty
under s 131 of the Companies Act. DHC sought orders under s 301 of the
Companies Act
that Mr Arnerich pay DHC $1,088,156.17 plus contractual
interest. Alternatively, DHC sought an order requiring Mr Arnerich to
contribute
such sum to the assets of Vaco by way of compensation as would serve
to cover all monies owing by Vaco to DHC, including GST and
contractual
interest, taking into account any liquidator’s fees and any claims that
might be lodged by other creditors.
- [106] The second
cause of action was concerned with alleged misapplication of the retention
monies. DHC claimed that retention monies
of approximately $80,559 should have
been paid to DHC in May 2013. DHC alleged that Mr Arnerich breached s 131
of the Companies
Act by procuring payment by ANZ to Vaco of the retention monies
held by ANZ, and paying those retention monies out to third parties
rather than
to DHC. DHC sought orders under s 301 of the Companies Act that Mr
Arnerich pay to DHC the amount of the retention monies
plus contractual
interest.
Mr Arnerich’s
defence
- [107] Mr
Arnerich denied that he had breached s 131 of the Companies Act.
In his defence to the third amended statement of claim,
he denied that
any further sums were owed by Vaco to DHC. He denied that DHC was entitled to
payment of the retentions under the
construction contract. He said that while
he was aware that DHC was unhappy with some of the engineer’s decisions
under the
construction contract, DHC never took any steps to formally challenge
those decisions within the timeframes required by the construction
contract. At
the time he authorised distributions to himself and his interests from
Vaco’s ANZ Bank account, DHC had taken
no steps to formally challenge any
of the engineer’s decisions, and had not commenced or threatened to
commence any mediation
or arbitration process. He had proceeded on the basis
that DHC had no valid claims against Vaco, and DHC was not taking any formal
steps to pursue the claims it had raised in correspondence.
- [108] Mr
Arnerich pleaded by way of affirmative defence that no further monies were owing
to DHC under the construction contract.
As a second affirmative defence, he
pleaded that he had relied on the advice given by Mr Beagley to ANZ about the
appropriate amounts
to be retained on term deposit to meet the forecast cost to
complete the development, including an allowance for possible claims
for
additional variations by DHC. He had acted in good faith and reasonably in
relying on that advice.
High Court
judgment
- [109] The
trial took place before Davison J in late 2018, with two further hearing days in
March 2019. Davison J delivered his judgment
on 27 September 2019.
The judgment was re-issued on 2 October
2019.[21]
Legal framework for the claim
- [110] As
the Judge noted, both causes of action were founded on an alleged breach by Mr
Arnerich of s 131 of the Companies Act, which
as relevant provides:
- Duty
of directors to act in good faith and in best interests of
company
(1) Subject to this section, a director of a
company, when exercising powers or performing duties, must act in good faith and
in what
the director believes to be the best interests of the company.
...
- [111] After
referring to relevant authorities and texts, the Judge summarised the question
he was required to decide as
follows:[22]
... if it
appears that when [Mr Arnerich] authorised the payments from Vaco’s bank
account in order to distribute all its assets
to [the Vaco] Trust and which
progressively reduced and ultimately exhausted the assets of the company thereby
rendering it insolvent,
he was not acting bona fide and in good faith by failing
to have proper regard to [DHC] and its claims asserting that it was a creditor
of [Vaco], he will have breached the duty in s 131 of the Companies Act 1993,
and will accordingly be liable.
- [112] As the
Judge noted, a director’s duty under s 131 of the Companies Act
is owed to the company, not to creditors of the
company.[23] DHC was able to bring
its claim in relation to alleged breach of s 131 by virtue of s 301 of the
Companies Act, which as relevant
provides:
- Power
of court to require persons to repay money or return
property
(1) If, in the course of the liquidation of a
company, it appears to the court that ... a past or present director ... of the
company,
has misapplied, or retained, or become liable or accountable for, money
or property of the company, or been guilty of negligence,
default, or breach of
duty or trust in relation to the company, the court may, on the application of
the liquidator or a creditor
or shareholder,—
(a) inquire into the conduct of the promoter, director, manager,
administrator, liquidator, or receiver; and
(b) order that person—
(i) to repay or restore the money or property or any part of it with interest
at a rate the court thinks just; or
(ii) to contribute such sum to the assets of the company by way of
compensation as the court thinks just; or
(c) where the application is made by a creditor, order that person to pay or
transfer the money or property or any part of it with
interest at a rate the
court thinks just to the creditor.
...
- [113] The Judge
proceeded on the basis that it was open to him to award compensation direct to
DHC under s 301(1)(c), if a breach
of s 131 was
established.[24]
- [114] The Judge
briefly touched on the relationship between Mr Arnerich’s duties as a
director of Vaco, and Vaco’s role
as trustee of the Vaco
Trust.[25] The Judge referred with
approval to the observation of Associate Judge Bell, in an earlier judgment in
the proceeding dealing with
an interlocutory application, to the effect that the
trusteeship was irrelevant to DHC’s claim against Mr
Arnerich.[26] A director of a
corporate trustee may come under duties to have regard to the interests of
creditors in the same way as the director
of any other company. Whether or not
Vaco owned the Lincoln Road property as trustee, Mr Arnerich arguably
breached his duties as
director if he disposed of company assets without
providing for the alleged creditor,
DHC.[27]
Ability
of the High Court to determine Vaco’s liability to DHC
- [115] The
Judge then addressed what he saw as the preliminary question of whether he was
able to determine the liability of Vaco to
DHC for the purpose of assessing the
compensation that might be awarded against Mr Arnerich, independently of the
Adjudicator’s
determination and in spite of the contractual disputes
procedure set out in the construction
contract.[28]
- [116] The Judge
concluded that the High Court did not have jurisdiction to determine
Vaco’s contractual liability to
DHC.[29] He considered that the
contractual dispute procedure agreed by DHC and Vaco required disputes under the
construction contract to
be addressed by prescribed processes, which could
include adjudication, formal review by the engineer, mediation and
arbitration.[30] The contract
did not anticipate either party bringing court proceedings in relation to a
dispute arising under the
contract.[31]
- [117] The Judge
considered that in the proceedings before him, Mr Arnerich could not challenge
the existence of the debt found owing
by Vaco to DHC by the Adjudicator.
Accordingly, the Judge proceeded on the basis that DHC had established the debt
owed to it by
Vaco as determined by the
Adjudicator.[32]
- [118] However,
as regards the parts of DHC’s contractual claim that had been disallowed
by the Adjudicator, and subsequently
referred to arbitration, the Judge found
that the dispute provisions of the contract were engaged and underway, but were
yet to be
completed. The Judge could not determine whether Vaco was liable to
meet the DHC claims that had been rejected by the Adjudicator.
The process for
determining those issues under the contract was by
arbitration.[33]
Findings
in relation to Mr Arnerich’s knowledge about DHC’s claims
- [119] The
Judge considered that at all relevant times Mr Arnerich was aware that DHC had
not given up on its claims, and was still
pursuing those
claims.[34] DHC was asserting those
claims in correspondence with the engineer and with Vaco. Contemporaneous
documents prepared by Davis Langdon
referred to outstanding and unresolved
claims by DHC. In the Drawdown Valuation 15 dated 5 March 2013 that Mr Beagley
had prepared
for ANZ, (and copied to Mr Arnerich), Mr Beagley advised that
significant construction variation claims, and risk, remained “with
the
major disputed claims having been recently referred for a formal
Engineer’s Review”. Mr Beagley’s report to
ANZ concluded
by commenting that negotiation and settlement of the construction variation
claims were identified as the significant
remaining contingent cost risk at that
stage. Although Mr Arnerich dismissed DHC’s claims as
“fanciful” and “not
worth printing out”, he was well
aware that DHC was pursuing
them.[35]
- [120] The Judge
found that DHC’s claims, and their yet to be determined status, meant that
DHC was a contingent creditor of
Vaco. Mr Arnerich’s duties as a director
required him to have proper regard to DHC’s interests as a contingent
creditor
when making decisions about distributing Vaco’s
assets.[36]
- [121] The Judge
did not accept Mr Arnerich’s evidence that he had concluded that DHC must
have accepted that it had no further
claims against Vaco. The Judge
said:[37]
Despite his
assertions to that effect, I do not consider that Mr Arnerich could have
actually held that subjective belief, as no sensible
basis existed for him to
reach such a conclusion. Moreover, and without taking any steps to ascertain
whether his belief that [DHC]
had abandoned its claims against Vaco was indeed
correct, he proceeded with energy and haste to secure release of the retention
funds
held by the ANZ. ... All of this occurred ... while dispute resolution
mechanisms for establishing its claim were still available
to [DHC] under the
contract.
- [122] The Judge
was satisfied that throughout the relevant period, Mr Arnerich did not genuinely
believe that DHC had abandoned its
claims.[38] He found that DHC was
asserting itself as a creditor, and Mr Arnerich was aware that there was a real
dispute between the parties.
The Judge found that Mr Arnerich did not believe
that DHC’s claims had been finally determined by Final Payment Schedule No
17.[39]
Breach
of s 131 of the Companies Act
- [123] The
Judge then went on to consider whether Mr Arnerich had breached his duties under
s 131 of the Companies Act when he authorised
the payments to himself and
his family interests. Mr Arnerich gave evidence that he was comfortable with
making those payments for
five reasons:
(a) the payments were made
by the Vaco Trust, to its creditor, ANZ, and to its beneficiaries.
(b) DHC had contracted with Vaco and not the Vaco Trust.
(c) DHC had acknowledged that Mr Arnerich had no personal liability and their
recourse for payment pursuant to the contract was with
ANZ, who would pay on
receipt of a certificate issued by the engineer.
(d) DHC’s work at Lincoln Road had concluded, and there were no
outstanding monies owing as had been determined by the engineer.
Despite
threatening to commence legal proceedings in an email of 27 December 2012,
DHC had not taken any steps.
(e) ANZ had retained $561,115 to be held on term deposit to cover costs to
complete should the engineer decide to approve some of
the DHC claims in Payment
Claim 17 or any future claims relating to the project.
- [124] The Judge
considered each of these five reasons and rejected them as grounds on which Mr
Arnerich could have considered that
it was in Vaco’s best interests to
distribute funds to himself and his
interests.[40]
- [125] The Judge
held that at the time Mr Arnerich made those distributions, he was not acting in
good faith, as he was not having
sufficient regard to the interests of DHC as an
unpaid creditor of
Vaco.[41]
Relief
under s 301 of the Companies Act
- [126] The
Judge considered that this was a case where it was appropriate for
Mr Arnerich to compensate DHC
directly.[42] He directed Mr
Arnerich to pay DHC the amount found owing in the adjudication:
$367,768.12.[43] The Judge
considered that DHC was entitled to interest on that sum from the date of the
adjudicator’s determination at the
contractual rate of 12.4 per cent
compounding monthly.[44]
- [127] The Judge
said that because the final amount of Vaco’s indebtedness to DHC was yet
to be determined, and could not be
determined other than by means of the
arbitration which was adjourned, DHC could not recover any further sum found
owing by Vaco
directly from Mr Arnerich under s 301 of the Companies Act
other than by means of a further proceeding. The Judge considered that
this
situation was unfortunate, but was the consequence of DHC having chosen to
pursue the s 301 proceeding before concluding the
arbitration with
Vaco.[45]
- [128] The Judge
made an order under s 301(1)(c) of the Companies Act that Mr Arnerich
pay directly to DHC the sum of $367,768.12,
with interest on that amount from
the date of adjudication compounding monthly at the contractual rate of
12.4 per cent per annum.
DHC was awarded
costs.[46]
Issues
on appeal
- [129] The
central issue raised by the appeal is whether the Judge was right to find that
Mr Arnerich breached s 131 of the Companies
Act by authorising
distributions to himself and his family interests in the period April to
September 2013.
- [130] The appeal
also raises the following issues:
(a) Did the High Court err in
declining to determine the amount of DHC’s claims against Vaco?
(b) Did the High Court err by treating the adjudication as determining the
(minimum) amount of Vaco’s liability to DHC?
(c) Did the High Court err in its approach to compensation under s 301
of the Companies Act? In particular, should the High Court
have identified
which (if any) of the payments made by Vaco breached s 131, and why, and
whether these had to be repaid to Vaco?
(d) Did the High Court err in awarding compensation on a basis that included
the GST payable by Vaco to DHC?
(e) Did the High Court err in awarding interest on the whole of the
adjudication award, including GST and costs components, at the
contractual rate
of 12.4 per cent?
- [131] Mr
Arnerich sought orders allowing his appeal and setting aside the judgment
against him.
- [132] The
central issue raised by the cross-appeal was the same as the first issue raised
by the appeal: whether the High Court erred
in declining to determine the amount
owing by Vaco to DHC. DHC sought orders remitting that issue, and the award of
relief against
Mr Arnerich under s 301 in respect of any further amount
owing by Vaco, to the High Court. DHC also sought, in the alternative,
orders
that would enable the amount of DHC’s claims against Vaco to be determined
by the arbitrator, with the question of relief
against Mr Arnerich under s 301
to be addressed by the High Court following the
arbitration.
Principles governing
DHC’s s 301 claim
Liability under s 131 of the Companies
Act
- [133] As
noted above, DHC brought its claim under s 301 of the Companies Act, which
permits a creditor of a company in liquidation
to apply to the court for relief
in connection with breaches of duty by a director of that company. The breach
alleged in this case
is a breach of Mr Arnerich’s duties under s 131 of
the Companies Act to act in good faith and in what he believed to be the
best
interests of that company.
- [134] The
Supreme Court has recently confirmed in Madsen-Ries v Cooper
(Debut Homes) that the test under s 131 is
subjective:[47]
[112]
... The test is subjective. This follows from the wording of s 131 (expressed
subjectively) and the legislative history (the
fact that the
Law Commission’s reasonableness requirement was not enacted). This
aligns with the common law test and policy
considerations. Courts are not well
equipped, even with the benefit of expert evidence, to second-guess the business
decisions made
by directors in what they honestly believed to be in the best
interests of the company. The courts would also be judging directors’
decisions with all the dangers of judging with the benefit of hindsight.
A subjective test is consistent with English authority.
Further, there is
also already an objectively-judged statutory duty of care in s 137.
[113] Commentary and caselaw suggest that there are, however, a number of
exceptions and qualifications to the subjective test:
(a) where there is no evidence of actual consideration of the best
interests of the company;
(b) where, in an insolvency or near-insolvency situation, there is a
failure to consider the interests of creditors;
(c) where there is a conflict of interest or where the action was one no
director with any understanding of fiduciary duties could
have taken (although
some would suggest these may rather be treated as breaches of the duty of good
faith (as the High Court did
in this case) or of s 133 (powers must be
exercised for a proper purpose)); and
(d) where a director’s decisions are irrational.
- [135] As
the Supreme Court went on to explain, factors (a) and (b) are not in fact
exceptions or qualifications to the subjective
test:[48]
The point is
that directors cannot subjectively believe they are acting in the best interests
of the company if they have failed to
consider the interests of the company or,
where required, the interests of all the creditors, including prospective
creditors.
- [136] The Court
did not need to decide whether factors (c) and (d) are qualifications or
exceptions to the subjective test. The Court
noted that in an insolvency
situation where the interests of creditors have not been considered, a conflict
of interest may well
exacerbate the
breach.[49]
The
implications of the trading trust structure
- [137] In
determining whether Mr Arnerich failed to comply with s 131 when
authorising the payments to himself and his interests, it
is important to bear
in mind the “trading trust” structure he put in place to carry out
the Lincoln Road development.
Vaco was the sole trustee of the Vaco Trust. It
purchased the Lincoln Road property in that capacity. It entered into the
project
finance agreement with ANZ in that capacity. Although the construction
contract was entered into by Vaco shortly before the trust
was settled, it is
clear that the development of the property was undertaken by Vaco in its
capacity as trustee of, and for the benefit
of, the Vaco Trust.
The construction work took place on land that was held by Vaco in that
capacity, and was paid for by funds borrowed
by Vaco in that capacity. The
proceeds of sale of the completed development were treated by Vaco as funds held
pursuant to the Vaco
Trust, and were distributed for the benefit of the
beneficiaries of that trust.
- [138] At an
earlier point in the proceedings, Mr Arnerich appears to have argued that the
construction contract was entered into by
Vaco for its own benefit, and not as
trustee of the Vaco Trust.[50] But
it was not suggested before us that the obligations incurred by Vaco to DHC for
work performed under the construction contract
were incurred other than in
Vaco’s capacity as a trustee of the Vaco Trust, or that expenditure by
Vaco on the construction
work that DHC performed on the property was not
properly payable out of the assets of the Vaco Trust. An argument to that
effect
would have had no prospect of success, on the facts of this case.
- [139] It follows
that:
(a) Vaco incurred liabilities as work progressed under the
construction contract to make payments to DHC as and when they fell due
under
that contract.
(b) Those liabilities were incurred by Vaco in its capacity as trustee of the
Vaco Trust.
(c) Vaco was entitled to meet those liabilities directly from the trust
property. Alternatively, if Vaco paid amounts due under the
construction
contract out of its own funds, Vaco was entitled to reimbursement from the trust
property.[51]
(d) Vaco as trustee was entitled to a lien over the trust property to protect
its right of indemnity in respect of existing and future
liabilities (including
contingent liabilities) to which it was exposed as a trustee. This lien arises
by operation of law and can
be asserted even against absolutely entitled
beneficiaries.[52]
- [140] When Vaco
made distributions of trust funds to discretionary beneficiaries of the Vaco
Trust, Vaco was not paying away money
that Vaco owned beneficially.
These were not Vaco’s own funds. But by making those payments, Vaco
lost its ability to meet
liabilities it incurred in its capacity as trustee out
of those trust funds, lost the ability to reimburse itself out of those funds,
and lost its lien over those funds. When considering whether Mr Arnerich
breached s 131, the focus must therefore be on whether
he acted in the best
interests of Vaco in deciding that Vaco should make those distributions at the
relevant time and, as a consequence,
lose its ability to have recourse to those
funds in the event that an existing or future claim by DHC (or any other
creditor of Vaco
in its capacity as trustee) was made out.
Relief under s 301
- [141] As
this Court recently observed in Yan v Mainzeal Property and Construction Ltd
(in liq), s 301 is essentially procedural in
nature.[53]
Where a claim is brought under s 301 in respect of a breach of duty by a
director, the plaintiff must establish all the elements
of a cause of action for
breach of that duty. Directors cannot be required to pay more under s 301
than could have been awarded
against them in a direct claim by the company for
breach of that duty.[54] The court
has a discretion to award less under s 301 than would be awarded in a
direct claim for breach of duty brought in the name
of a company. There remains
some uncertainty about the extent of the s 301
discretion.[55]
- [142] Section
301(1)(c) expressly provides for an application under s 301 to be made by a
creditor of the company. As this Court
observed in Mainzeal, where the
application is made by a creditor, the court can order the defendant to pay or
transfer money or property to the creditor
under
s 301(1)(c).[56] It has been
held in the High Court that this power is available where the defendant has
misapplied or retained or become liable
or accountable for money or property of
the company, but not in relation to compensation for breaches of a duty owed by
a director
to the company.[57]
However, in Debut Homes, the Supreme Court expressly left the
question of when an award can be made to a creditor for decision in a case where
the issue
arises directly.[58] We
do not consider that the issue needs to be resolved in the present case, in
circumstances where:
(a) The liquidator was aware of the proceedings
and advised the Court that she abided by the Court’s decision.
(b) Mr Arnerich did not oppose an order that any amount found to be payable
be paid direct to DHC. In response to a minute issued
by this Court on 2
November 2020, before the hearing of the appeal, Mr Arnerich filed a
memorandum submitting that an order could
not be made for payment direct to a
creditor under s 301(1)(c) in respect of a claim for breach of a
director’s duties owed
to the company. But in the course of the hearing,
Mr McBride, counsel for Mr Arnerich, confirmed that there had been no argument
in the High Court about the appropriateness of a direct payment to DHC. In
response to questions from the Court about whether it
was too late to take the
issue now, Mr McBride indicated that the issue had no practical
significance because DHC is the only remaining
creditor in the liquidation. In
those circumstances, the issue was not pursued further before us.
- [143] Thus if Mr
Arnerich breached s 131, the starting point for determining the appropriate
relief under s 301 is the compensation
that Vaco could have recovered from
Mr Arnerich if it had brought a direct claim for breach of that
duty.[59] That sets a ceiling
on the amount that could be awarded under s 301. It is then necessary to go on
and consider whether there is
good reason to award a lesser amount.
- [144] The
approach to awarding relief for breach of a duty owed by a director to
a company, where that claim is brought by the company,
depends on the
provision breached and on the nature of the breach. If a director breaches the
fiduciary obligations set out in s
131, the remedy will be assessed in
accordance with the principles governing claims for breaches of fiduciary
duty.[60]
Should
the High Court have determined the amount of DHC’s claim against
Vaco?
- [145] We
begin by considering whether the High Court should have determined the amount
(if any) that DHC was owed by Vaco under the
construction contract.
- [146] Before
this Court, both DHC and Mr Arnerich submitted that the High Court erred in
failing to determine whether DHC had valid
claims against Vaco for payments in
respect of variations and extensions of time. We accept that submission. As we
explain below,
the High Court had jurisdiction to determine this issue
and needed to do so in order to determine DHC’s claim.
- [147] It was an
integral element of DHC’s claim that it was owed further amounts by Vaco,
and had been denied payment of those
further amounts as a result of
Mr Arnerich’s breaches of s 131 of the Companies Act. In order
to determine the amount that
DHC could have recovered from Vaco but for the
alleged breaches, it was necessary for the High Court to determine what amount,
if
any, DHC was contractually entitled to claim from Vaco.
- [148] At the
risk of stating the obvious, the High Court had jurisdiction to hear and
determine DHC’s claim against Mr Arnerich.
It necessarily had
jurisdiction to determine any question of fact or law relevant to that claim,
absent some limit on its jurisdiction
established by statute or by common law.
In this case, there was no relevant limit on the High Court’s
jurisdiction. There
was no arbitration agreement between DHC and Mr Arnerich
referring a dispute between them to arbitration. And even where parties
have agreed to arbitration of their dispute, that does not deprive the court of
jurisdiction. Rather, where parties to proceedings
before the court have agreed
to refer that dispute to arbitration, the court will at the request of a party
decline to exercise its
jurisdiction, and stay the proceedings as required by
the Arbitration Act 1996, unless one of the exceptions set out in that Act
applies.[61] One of those
exceptions is where a stay is requested by a party after submitting their
“first statement on the substance of
the dispute”. Thus, for
example, if one party brings proceedings before the court and the other party
does not seek a stay,
or takes a substantive step in the proceedings before
requesting a stay, the court has jurisdiction to hear the claim and will proceed
to do so.
- [149] The court
may also, in the exercise of its inherent jurisdiction, grant a stay where
essentially the same issue has been referred
to arbitration by related
parties.[62] But the court will do
so only in rare and compelling
circumstances.[63] And of course it
will do so only if a party seeks a stay.
- [150] In this
case, neither party sought a stay at any point in the proceedings before the
High Court. Both parties agreed that the
issue of DHC’s contractual
entitlement against Vaco should be determined by the Court. Vaco also agreed to
this approach,
through its liquidator. The Court had jurisdiction to determine
that issue and should have done so.
- [151] We accept
DHC’s submission that in these circumstances, the proceeding should be
remitted back to the High Court to determine
the question of what, if anything,
Vaco owes to DHC over and above the amount determined by the adjudication
process, if that issue
is relevant to the award of relief under s 301 of the
Companies Act in this proceeding. We return to the question of relief
below.
Did Mr Arnerich breach
s 131 of the Companies Act?
Mr Arnerich’s submissions on appeal in
relation to s 131
- [152] Mr
Arnerich submitted that the High Court Judge erred in finding that
Mr Arnerich had failed to act in what he believed —
subjectively
— to be the best interests of Vaco. He says that at the time the
Lincoln Road property was sold, and the trust
funds distributed, he genuinely
believed that DHC had no further valid claims under the construction contract.
He knew that DHC
was unhappy with Vaco’s refusal to pay any further
amounts, and with the decisions made by the engineer to issue payment schedules
denying their claims. But he considered that DHC had, albeit reluctantly,
decided not to take any formal steps to pursue those claims.
And in any event,
even if DHC did pursue its claims further, he saw those claims as hopeless.
So there was no need to retain funds
to meet such claims.
- [153] In support
of that proposition, Mr Arnerich pointed to his correspondence with Mr Beagley,
in which he consistently expressed
a firm view that DHC had no further claim.
When DHC sent an email to Mr Arnerich on 8 August 2013 inquiring about the final
account,
Mr Arnerich’s email to Mr Parkin recorded that he thought the
claim was “sorted in that they owe us almost $100K”.
Mr Arnerich
asked if Mr Parkin thought they were “fishing”. His views as
recorded in other correspondence at the relevant
time were that the claims by
DHC were “fanciful”, “outside the contract”,
“outrageous”, and that
he was “very confident” that they
had no basis.
- [154] Mr
Arnerich also emphasised that following the sale of the Lincoln Road property,
Vaco set aside a provision of $561,115 at
the instigation of ANZ, to cover costs
to complete the project. Mr Arnerich submitted that he genuinely believed in
April 2013 that
this provision was adequate to meet any further claims from DHC
or others. He says he relied on the fact that this amount was seen
by ANZ as an
adequate provision, based on advice from Mr Beagley (the engineer under the
construction contract and the quantity surveyor
advising ANZ). The figure
recommended by Mr Beagley included $197,161 for claims by DHC and $317,915
for ASB’s tenant fitout
contribution.
- [155] That
provision was progressively depleted by Mr Arnerich over the balance of 2013, by
way of payments to Vaco’s creditors.
Some payments were also made to his
interests, but these were of relatively modest amounts. Throughout this period,
DHC failed
to take any formal steps to pursue its foreshadowed claims.
- [156] By
retaining this provision, Mr Arnerich submitted, he had acted in good faith in
the best interests of Vaco. Even if it was
subsequently established that DHC
had further claims against Vaco, that did not cast doubt on whether Mr Arnerich
had acted in good
faith when authorising payments in 2013.
- [157] In those
circumstances, Mr Arnerich submitted, it was not open to the High Court
Judge to make adverse findings about Mr Arnerich’s
conduct.
In particular, it was not open to the Judge to find that he did not
genuinely believe that DHC was not likely to take any
further formal steps to
pursue its claims. And the Judge failed to address his argument that having
regard to his genuine view of
the merits of those claims, he had made adequate
provision for any such claims at the time the Lincoln Road property was sold.
In
the absence of any further steps by DHC to pursue its claims, he then acted
in good faith in paying away that provision over a period
of months. The
Judge was wrong to suggest that he had done so with
“haste”.[64]
DHC’s submissions in relation
to s 131 breach
- [158] DHC
sought to uphold the Judge’s findings. Mr Thorp, counsel for DHC,
emphasised that DHC had consistently advanced its
claims for further payment.
The Judge was right to find that Mr Arnerich could not have genuinely
believed that DHC had abandoned
the pursuit of those claims.
- [159] Mr Thorp
emphasised that the letter dated 4 March 2013 from Davis Langdon to ANZ, which
was copied to Mr Arnerich, was the source
of the figures on which the $561,115
provision was based. But in that same letter Davis Langdon advised ANZ
that:
(a) Significant construction variation claims/risk ($567,000
claimed versus cost liability provision of $363,000 included in the current
cost
to complete assessment) remained, with the major disputed claims having recently
been referred for a formal engineer’s
review.
(b) DHC had identified variation claims to date amounting to approximately
$629,000, of which $363,000 had been included within the
current budget and cost
to complete provision.
(c) Extension of time claims, variation claims relating to “soft
spots” in the basement, time-related construction expenses
and credits for
contract works not completed were the remaining significant variation cost risks
at this stage of the project.
(d) There was effectively no remaining unallocated contingency for the
project.
(e) There remained “significant construction/final account agreement
risk that identifies a potential shortfall, that would
require additional
equity/funding to be contributed should [DHC] be awarded variation values as
currently claimed”.
(f) Negotiation and settlement of the construction variation claims,
associated Final Construction Account agreement and incidental
consultant and
holding costs associated with a protracted development period were the
significant remaining contingent cost risks
at this stage of the project.
- [160] Mr Thorp
drew our attention to the email Mr Arnerich sent to ANZ on 5 March 2013, in
which he emphasised that he was “very
confident” in relation to the
DHC claims, and added that “in any event this will drag on way past
settlement of the property
and will in effect become solely my problem as the
bank will not have any exposure”. Mr Thorp submitted that this was an
acknowledgement
that the dispute was likely to continue, with the risk of
liability to be borne by Vaco.
- [161] Mr Thorp
also emphasised that DHC’s final account, Payment Claim 17, was sent to
Vaco on 15 March 2013 after the correspondence
between Mr Beagley and ANZ and Mr
Arnerich earlier that month. So it would have been obvious to Mr Arnerich
that the views expressed
in Davis Langdon’s 4 March 2013 letter did
not take into account the additional claims made by DHC in Payment Claim 17.
Upon
receipt of that payment claim, Mr Arnerich sent an email to Mr Beagley
asking him to review the claims, and add them to the engineer’s
reviews
that are currently underway. This was a further acknowledgement that the claims
had not been finally
resolved.
Discussion
- [162] We
consider that it was open to the Judge to find that Mr Arnerich did not
(subjectively) believe that DHC had abandoned its
claims. Just a matter of
weeks before the sale of the Lincoln Road property, DHC submitted its Payment
Claim 17. DHC had been rather
disorganised and desultory in pursuing its
claims, and had been reluctant to escalate those claims to formal dispute
resolution procedures.
But it remained open to DHC to do so. It was
implausible that DHC would fail to take further steps to pursue the very
substantial
amounts that it claimed were owing to it, if an agreed resolution
could not be achieved. Similarly, it is implausible that Mr Arnerich
believed
that DHC would take no further steps to pursue its claims.
- [163] The Judge
did not make a finding on whether Mr Arnerich believed that the claims were so
lacking in merit that there was no
need to retain funds to cover them. There is
considerable force in Mr Arnerich’s submission that the contemporaneous
correspondence
confirms that this was indeed his view. We accept that he
believed that the risk of a successful claim by DHC was very low.
- [164] Thus if
the s 131 test were purely subjective, Mr Arnerich would have a respectable
argument that in making decisions about
dealings with funds held by Vaco, he
could disregard the risk of claims by Vaco in excess of the amount set aside by
way of provision
when the Lincoln Road property was sold.
- [165] That is
not the end of the matter, however, as it remains necessary to consider whether
any of the four riders in relation to
the subjective approach to s 131
recognised by the Supreme Court in Debut Homes applies. We set them out
again for ease of
reference:[65]
(a)
where there is no evidence of actual consideration of the best interests of the
company;
(b) where, in an insolvency or near-insolvency situation, there is a failure
to consider the interests of creditors;
(c) where there is a conflict of interest or where the action was one no
director with any understanding of fiduciary duties could
have taken (although
some would suggest these may rather be treated as breaches of the duty of good
faith (as the High Court did
in this case) or of s 133 (powers must be
exercised for a proper purpose)); and
(d) where a director’s decisions are irrational.
- [166] We
consider that in this case, a number of the four riders do apply.
- [167] In early
April 2013, Vaco had a choice: it could pay out the funds as distributions to
beneficiaries of the Vaco Trust, or it
could retain sufficient funds to meet any
possible DHC claims until such time as those claims were finally resolved. Vaco
had no
obligation as trustee of the Vaco Trust to make any distributions to the
trust’s discretionary beneficiaries at that time.
Vaco had a lien over
the Vaco Trust’s funds to protect it from any contingent liability in
respect of DHC’s potential
claims, and Vaco was entitled to rely on, and
exercise, that lien.
- [168] Making
substantial distributions before all claims arising out of the development
project had been ascertained, and paid or
provided for, conferred no benefit of
any kind on Vaco as a separate entity. Vaco’s interests were not advanced
in any way
by making distributions at that time.
- [169] Conversely,
there was a clear disadvantage to Vaco as a separate entity in making those
distributions: it lost the ability to
have recourse to the trust assets to meet
any liabilities that might subsequently be established. Making distributions
that left
Vaco exposed to any (non-negligible) risk of liability to DHC or other
claimants, without the ability to resort to trust funds to
meet those claims,
was self-evidently contrary to Vaco’s interests as a separate entity.
- [170] A rational
director who turned their mind to the best interests of Vaco would take steps to
identify all (non-negligible) risks
Vaco faced, and the amounts that Vaco needed
to retain to protect itself from those risks. A rational director would not
disregard
the possibility that their personal assessment of the risk —
without the benefit of legal advice — might be proved wrong.
At the very
least, before taking the irreversible step of paying away all or almost all of
the trust funds, a rational director
who was considering whether payment was in
the best interests of Vaco would identify all potential liabilities that Vaco
might face
in its capacity as trustee of the Vaco Trust, including the maximum
conceivable liability to DHC, and ensure that Vaco retained access
to funds
sufficient to meet that maximum liability if it
materialised.[66]
- [171] It seems
clear from the reasons Mr Arnerich put forward to explain why he felt
comfortable with making the distributions that
he did not in fact understand, or
give consideration to, the interests of Vaco as a separate entity during the
period when he was
approving substantial distributions to himself and to his
interests. There was no evidence that he actually turned his mind to
Vaco’s
best interests. He did not seek any formal advice on Vaco’s
exposure to DHC. He did not prepare, or ask anyone else to prepare,
a schedule
of Vaco’s potential future liabilities to DHC, the IRD and other
creditors. This was not mere carelessness: rather,
the interests of Vaco as
distinct from the Vaco Trust and his family simply were not on his radar.
- [172] The reason
for Mr Arnerich’s lack of concern about Vaco’s interests appears to
have been the result of two factors:
his failure to understand the implications
of the legal structure he had put in place, and his obvious conflict of interest
in relation
to the payments to his interests. The irresistible inference is
that Mr Arnerich was acting throughout in the best interests of
himself and his
family, and did not genuinely turn his mind to the interests of Vaco as a
separate entity, or seek to pursue those
interests.
- [173] In these
circumstances, riders (a), (c) and (d) apply in relation to all the payments
made to Mr Arnerich and his interests,
from April 2013 onwards. It is in our
view clear that Mr Arnerich did not actually consider the best interests of
Vaco as a separate
entity before authorising these payments. He had an obvious
conflict of interest. No director with any understanding of fiduciary
duties
could have acted as he did. It would be irrational for a director who
understood their fiduciary duties, and was seeking
to act in Vaco’s best
interests, to act in that way.
- [174] There
is also a strong argument that rider (b) applies. The effect of the
distributions was that Vaco became insolvent or near-insolvent
as it
progressively lost the ability to resort to trust assets to meet claims. Indeed
one of the puzzling features of this case
is that on Mr Arnerich’s
evidence, Vaco (in its capacity as trustee of the Vaco Trust) was substantially
indebted throughout
the relevant period to VDT for the balance of the purchase
price of the Lincoln Road property. And Vaco had a contingent tax liability
in
connection with the profit it made on the project, which as noted at [61] above resulted in a payment of
$311,218 in May 2014. Taking into account the unpaid purchase price that
Mr Arnerich said was owed
to VDT, and contingent tax liabilities, it appears
Vaco was seriously insolvent as a result of the distributions made in early
April
2013. The financial statements for the Vaco Trust as at 31 March
2014 record a balance sheet deficit of $2,269,280 even without
taking into
account DHC’s claims. If Mr Arnerich genuinely believed that Vaco owed
$1.875 million to VDT, it is difficult
to see how the distributions made in 2013
could have been made after taking into account the interests of creditors. But
we put
this to one side, as it is not essential to our conclusion, and DHC did
not plead the case on the basis that Vaco was insolvent or
near-insolvent
because of liabilities to third
parties.
Liability under s 301 of the
Companies Act
Potential liability to Vaco under s 131
- [175] If
Vaco had brought proceedings against Mr Arnerich for breach of fiduciary duty in
authorising the 2013 distributions for the
benefit of himself and his family,
without turning his mind to whether Vaco retained access to sufficient trust
funds to meet any
claims that might be made against it in connection with the
development, Vaco would have been entitled to recover the lesser of the
value of
the distributions made from 3 April 2013 onwards, and the amount of the
indemnity of which it had been deprived as a result
of those actions. If Mr
Arnerich could show that some distributions could properly have been made,
consistent with his fiduciary
duties, then that would in principle reduce his
liability. But Mr Arnerich did not make any attempt to establish an amount that
could have been distributed while still retaining sufficient funds to protect
Vaco as trustee in respect of all the claims that a
trustee acting properly
would have taken into account. So we need not consider that possibility.
- [176] It follows
that Vaco could have recovered from Mr Arnerich the full amount of any liability
it had to DHC in respect of the
claims advanced by DHC, which are substantially
less than the amount of the distributions authorised in breach of
s 131.
Liability under s
301
- [177] If
a liquidator of Vaco had brought a claim against Mr Arnerich under s 301 of
the Companies Act in respect of these breaches
of s 131, there would be no
good reason to award less than the amount required to enable the liquidator to
meet creditors’
claims in full. These were clear breaches of fiduciary
duty by Mr Arnerich for his own personal benefit, and for the benefit of
his
associated interests. There is no conceivable justification for exercising a
discretion to reduce the amount of compensation
awarded.
- [178] Essentially
the same reasoning applies in relation to the present claim by DHC as a creditor
of Vaco. There is no good reason
to deny DHC the full recovery that it would
have obtained in the absence of Mr Arnerich’s breaches, or to allow
Mr Arnerich
and his interests to retain any part of the proceeds of those
breaches at the expense of DHC.
- [179] Vaco took
no steps to challenge the determination by the Adjudicator in respect of
the claims on which DHC was successful at
adjudication. We consider that
the Judge was right to direct that Mr Arnerich pay the amount awarded by the
Adjudicator to DHC immediately.
But for Mr Arnerich’s breaches, Vaco
would have been able to pay the whole of this debt, which became enforceable as
a judgment
against Vaco.
- [180] However,
the Judge erred in declining to determine DHC’s claims for additional
payments. The Judge also erred in proceeding
on the basis that DHC could bring
a further s 301 claim in respect of any additional amounts to which it
might be found to be entitled.
Quite apart from any limitation issues that
might arise in respect of a further s 301 claim, a creditor must bring all
its claims
under s 301 in one proceeding. It would be an abuse of
process to seek to bring successive s 301 claims.
Treatment of GST
- [181] We
consider that the Judge was right to make an award against Mr Arnerich that
included the GST claimed by DHC and awarded in
the adjudication. DHC’s
claim is in effect a claim for payment for services that it supplied to Vaco.
We are not persuaded
that DHC will avoid liability for GST merely because the
award is made against Mr Arnerich, a director of Vaco, and requires
direct
payment from Mr Arnerich to DHC rather than payment via Vaco. It is
still a payment in respect of services provided by DHC, even
if it is made by a
person other than the person to whom the services were provided. The
GST difficulties that this may give rise
to for Mr Arnerich are of his own
creation, and should not result in DHC being
under-compensated.
Interest
- [182] Mr
Arnerich submitted that interest should not have been awarded by the
High Court from the date of liquidation onwards. He
submitted that s 311
of the Companies Act prevents the payment of contractual interest
post-liquidation.
- [183] Section
311 provides:
311 Interest on claims
(1) The amount of a claim may include interest up to the date of commencement
of the liquidation—
(a) at such rate as may be specified or contained in any contract that makes
provision for the payment of interest on that amount;
or
(b) in the case of a judgment debt, of the amount that is payable on the
judgment debt.
(2) If any surplus assets remain after the payment of all admitted claims,
the specified interest must be paid on those claims from
the date of
commencement of the liquidation to the date on which each claim is paid, and if
the amount of the surplus assets is insufficient
to pay interest in full on all
claims, payment shall abate rateably among all claims.
(3) If any surplus assets remain after the payment of specified interest in
accordance with subsection (2), interest must be paid,
on all admitted claims
referred to in subsection (1)(a), of an amount equal to the difference between
the specified interest paid
under subclause (2) and the interest that would have
been payable under the contract for that period and, if the amount of the
surplus
assets is insufficient to pay interest in full on all those claims,
payment must abate rateably among them.
(4) For the purpose of subsection (2), specified interest means
interest calculated in accordance with Schedule 2 of the Interest on Money
Claims Act 2016.
- [184] We do not
accept this submission. Section 311(3) expressly provides for payment of the
full contractual rate of interest applicable
to any debt, if the company’s
assets are sufficient to meet all claims. In this case, the assets are
insufficient only as
a result of the breaches of duty by Mr Arnerich. The
compensation he pays to DHC should be assessed on the basis that his breaches
did not occur, and thus on the basis that if Vaco had been placed in liquidation
on 1 July 2014, it would have retained access to
sufficient trust funds to meet
the whole of the debt to DHC.
- [185] Mr
Arnerich is on surer ground in relation to his challenge to the award of
contractual penalty interest at a rate of 12.4 per
cent per annum, compounding
monthly, in respect of the whole of the sum awarded by the adjudicator.
Contractual interest should
be confined to the items in respect of which it is
properly payable under the construction contract, and should not include the
amounts
which the adjudicator held should not attract penalty interest, or the
amounts awarded in respect of GST and the costs of the adjudication.
Interest
in respect of those components of the determination — which was entered as
a judgment — is recoverable in the
same manner as interest on any other
judgment.
- [186] We allow
Mr Arnerich’s appeal against the award of interest in the High Court, and
remit that issue back to the High Court
for determination (if the parties cannot
reach agreement).
Remittance back to
High Court
- [187] The
proceeding should be remitted back to the High Court to determine the
amount which Vaco owes to DHC, and to make any further
order for compensation to
be paid by Mr Arnerich to DHC in light of that finding.
- [188] We note
that this staged approach is consistent with the approach adopted by the High
Court in Debut Homes, where leave was granted to the liquidators to
re-apply to the High Court for an increase in compensation in certain
circumstances.
The orders made in the High Court were restored by the Supreme
Court on
appeal.[67]
DHC’s
retention claims
- [189] In
light of our findings set out above, we need not address DHC’s claims in
relation to payment of the retentions to Vaco.
These claims add nothing to
DHC’s successful claims in relation to the distributions made to
beneficiaries of the Vaco Trust.
However, we note that we have real
difficulty in seeing how steps taken by Mr Arnerich to procure payment to
Vaco of sums held by
ANZ could be contrary to the best interests of Vaco. Mr
Arnerich did not owe any duty to DHC to ensure that Vaco (or ANZ) complied
with
their contractual obligations to DHC in relation to retentions.
Result
- [190] Mr
Arnerich’s appeal is allowed in so far as it relates to the award of
interest on the sum of $367,768.12. The award
of interest in the High Court is
set aside, and remitted back to that Court to be determined in accordance with
this judgment. Mr
Arnerich’s appeal is otherwise dismissed.
- [191] DHC’s
cross-appeal is allowed. The proceedings are remitted back to the
High Court to determine the amount of any further
claim DHC may have
against Vaco under the construction contract and, in light of that
determination, to make such further orders
against Mr Arnerich under s 301
of the Companies Act as may be appropriate.
- [192] Costs
should follow the event in the usual way. Mr Arnerich must pay costs to DHC on
the appeal and cross-appeal, in each case
for a standard appeal on a band A
basis, with usual disbursements. We certify for second
counsel.
Solicitors:
Doug Cowan, Auckland
for Appellant
Duthie Whyte, Auckland for Respondent
[1] DHC Assets Ltd v
Arnerich [2019] NZHC 1695 [High Court judgment].
[2] At [345] and [352].
[3] At [348]–[350] and
[353].
[4] At [351].
[5] At [5]–[218].
[6] The High Court judgment, above
n 1, refers at [64] to ASB requiring
approximately 80 contract variations. This appears to be a typographical
error.
[7] DHC Assets Ltd v Toon
[2016] NZHC 140 at [35].
[8] DHC Assets Ltd t/a
Clearwater Construction v Vaco Investments (Lincoln Road) Ltd (in liq)
BDT2016-08744, 5 October 2016.
[9] At [107].
[10] At [108]–[110].
[11] At [268].
[12] At [176]–[180].
[13] At [142]–[146].
[14] At [283]–[286].
[15] At [262] and [292(b)].
[16] DHC Assets Ltd v Vaco
Investments (Lincoln Road) Ltd (in liq) [2017] NZHC 454.
[17] DHC Assets Ltd v Vaco
Investments (Lincoln Road) Ltd (in liq) DC North Shore
CIV-2017-044-546,
11 May 2017.
[18] Arnerich v Vaco
Investments (Lincoln Road) Ltd (in liq) [2018] NZHC 560 at [22(d)].
[19] Arnerich v Vaco
Investments (Lincoln Road) Ltd (in liq) [2018] NZHC 1974 at
[40]–[43].
[20] DHC Assets Ltd v
Arnerich [2017] NZHC 1460.
[21] High Court judgment, above
n 1.
[22] At [244].
[23] At [242], quoting
Nicholson v Permakraft (NZ) Ltd [1985] NZCA 15; [1985] 1 NZLR 242 (CA) at 249.
[24] At [249], quoting
Sanders v Flay (2005) 9 NZCLC 263,906 (HC) at [18]–[19].
[25] At [250]–[253].
[26] At [252].
[27] At [252], quoting DHC
Assets Ltd v Arnerich [2018] NZHC 1865 at [28].
[28] At [256].
[29] At [259].
[30] At [260].
[31] At [261].
[32] At [268].
[33] At [269].
[34] At [293]–[298].
[35] At [310].
[36] At [314].
[37] At [317].
[38] At [320].
[39] At [327].
[40] At [331]–[344].
[41] At [345].
[42] At [347].
[43] At [348]–[349].
[44] At [350].
[45] At [351].
[46] At [353]–[354].
[47] Madsen-Ries v Cooper
[2020] NZSC 100, (2020) 29 NZTC 24-088 [Debut Homes] (footnotes
omitted).
[48] At [114].
[49] At [115].
[50] It appears this argument
was advanced in opposition to DHC’s summary judgment application: see
DHC Assets Ltd v Arnerich, above n 20, in particular at [26]–[30].
[51] Compare s 81 of the
Trusts Act 2019, which reflects the pre-existing law.
[52] Andrew Butler (ed)
Equity and Trusts in New Zealand (2nd ed, Thomson Reuters, Wellington,
2009) at [16.6.6]; In Re Pauling’s Settlement Trusts (No 2) [1963]
Ch 576; and X v A [2000] 1 All ER 490 (Ch) at 493–494.
[53] Yan v Mainzeal Property
and Construction Ltd (in liq) [2021] NZCA 99 at [299].
[54] At [301].
[55] At [303]–[307].
[56] At [309].
[57] Mitchell v Hesketh
(1998) 8 NZCLC 261,559 (HC) at 261,562.
[58] Debut Homes, above n
47, at nn 179 and 191.
[59] Yan v Mainzeal Property
and Construction Ltd (In Liq), above n 53, at [301].
[60] At [288].
[61] See Arbitration Act 1996,
cl 8(1) of sch 1.
[62] See for example Danone
Asia Pacific Holdings Pty Ltd v Fonterra Co-operative Group Ltd
[2014] NZHC 1681 at [33]–[39].
[63] At [55], citing
Reichhold Norway ASA v Goldman Sachs International [1999] EWCA Civ 1703; [2000] 1 WLR 173 (CA)
at 186.
[64] High Court judgment, above
n 1, at [317].
[65] Debut Homes, above n
47, at [113] (footnotes omitted). As
the Supreme Court noted, not all of these are truly exceptions to a subjective
approach: see [135] above.
[66] Either by actually
retaining the funds, or (depending on the circumstances) by retaining the
ability to have recourse to the funds,
for example by providing them to
beneficiaries as advances rather than outright distributions, or by making
distributions subject
to indemnities from the beneficiaires.
[67] See Debut Homes,
above n 47, at [4] and [190].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2021/225.html