You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2021 >>
[2021] NZCA 296
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
NZ Southern Rivers Society Incorporated v Gore District Council [2021] NZCA 296 (5 July 2021)
Last Updated: 13 July 2021
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
NZ SOUTHERN RIVERS SOCIETY INCORPORATED Appellant
|
|
AND
|
GORE DISTRICT COUNCIL First Respondent
|
|
|
PHILLIP RAYMOND JOOSTENS Second Respondent
|
Hearing:
|
6 May 2021
|
Court:
|
Cooper, Gilbert and Goddard JJ
|
Counsel:
|
M R Walker and B B Gresson for Appellant M R Garbett and G R Cassidy
for First Respondent No appearance for Second Respondent
|
Judgment:
|
5 July 2021 at 11 am
|
JUDGMENT OF THE COURT
A The
appeal is dismissed.
- The
appellant must pay the first respondent costs calculated for a standard appeal
on a band A basis, together with usual disbursements.
We certify for second
counsel.
____________________________________________________________________
REASONS OF THE COURT
(Given by Cooper J)
- [1] In March
2019, the second respondent, Mr Phillip Joostens, applied to the first
respondent, the Gore District Council (the Council),
for resource consent
to establish a river rafting tourism activity on the Mataura
River.[1] On 10 October 2019 an
independent Commissioner appointed by the Council to consider the application,
Mr Andrew Henderson, granted
consent on a non-notified basis.
- [2] The
appellant, NZ Southern Rivers Society Inc (the Society), comprises a group of
anglers who fish on rivers located within the
Southland and Gore Districts. It
was incorporated on 12 December 2019, about two months after the consent was
granted. It sought
judicial review of the decision to grant the application on
a non‑notified basis. The Society’s application was declined
by
Osborne J in a judgment delivered on 7 August
2020.[2]
The Society now appeals to this Court.
- [3] Mr Joostens
has taken no steps in the proceeding. But the Council opposed the application
for judicial review in the High Court
and has also resisted the appeal in this
Court.
- [4] For the
reasons that we address, we have concluded that the High Court was right to
decline the application for judicial review
and the appeal must be
dismissed.
Relevant facts
- [5] The Mataura
River is located in the Southland and Gore Districts. It is well known for
trout fishing and has been recognised
by the Water Conservation
(Mataura River) Order 1997 (WCO) as having outstanding fisheries and
angling amenity features. Protection
for the Mataura River is achieved through
the WCO which, among other things, stipulates minimum rates of flow, restricts
water and
discharge permits and prevents damming. However, the WCO does not
otherwise address what uses may be made of the Mataura River or
what land use
consents may be granted in relation to it.
The application for
resource consent
- [6] Mr
Joostens’ application was lodged on his behalf by Mr Hamish Weir of
Landpro Ltd on 25 March 2019. The proposal involved
rafting routes over the
Mataura, Oreti and Waikaia Rivers.
- [7] The
application sought resource consent for three excursions catering for tourists,
described as “Excursion 2”, “Excursion
3” and
“Excursion 4”, which were located within the Mataura River Floodway
contained in the Gore District
Plan.[3] The excursions related
to different parts of the river, as described in the application. They may be
summarised as follows:
(a) Excursion 2: Otamita or Monaghan’s
Beach to Gore. This excursion would have three components involving rafting,
short stops
and gold prospecting experiences. The rafting would involve a
maximum of three rafts capable of carrying six clients and one guide
each, but
there would be only two trips on any one day and a maximum of 10 per week.
(b) Excursion 3: Gore to Mataura. Rafting would be the only activity
offered. There would be a maximum of three excursions on any
one day and a
maximum of 15 per week. Each excursion would involve one raft, capable of
carrying six clients and the option of one
guide per trip.
(c) Excursion 4: Mataura to Wyndham. This excursion would begin in the Gore
District and travel along the Mataura River for approximately
five kilometres before entering the Southland District. It would comprise
both rafting and short stops. There would be a maximum
of two rafts, each
capable of carrying six clients and one guide. One excursion was proposed
on any given day, giving a maximum
number of 14 people per day for the activity.
There would be a maximum of two excursions per week.
- [8] The relevant
parts of the river corridor affected in the Gore District were within the Rural
Zone of the District Plan, with the
exception of the Mataura carpark, located in
the Industrial Zone. Under the relevant rules of the District Plan the activity
was
not specifically referred to in the list of permitted activities. This
meant the proposal required resource consent as a discretionary
activity.
- [9] The
application stated that the proposed activity would require meeting places where
paying clients would assemble. The excursions
were to commence from the Mataura
carpark, which was described as a “sparsely used” area providing
parking for the town
centre. The base of operations would be Mr Joostens’
property adjacent to Mataura. An existing home office would function
as an
administrative hub for the business; vehicles, rafting and camping equipment
would be stored at that address when not in use.
- [10] For present
purposes it is relevant to note that the application briefly addressed
interaction with other users of the river.
The application set out
that:
The applicant proposes that short stops, during the excursions
proposed, will not be undertaken within 200m of any other river users
unless
their permission is obtained. Specific care will be taken not to intrude on
Anglers encountered during any excursion.
- [11] The
application also included an assessment of environmental effects.
These were addressed under headings that reflected matters
listed for
assessment in the District Plan and included effects on ecology, wildlife
habitats and water quality; effects on other
existing surface water activities
and safe and efficient navigation; noise; visual amenity effects; and the
protection of the habitat
of trout and salmon. One subject discussed in the
assessment was the effect on recreational opportunities and public use of water
bodies and their margins. After noting that the activity proposed would improve
the public’s ability to access the rivers
by providing additional means of
access, the application stated:
The rafting and recreational use of
the rivers will not prevent existing users of other river craft from travelling
along the river.
The rafts are slow moving and do not pose a threat to people
swimming or wading in the rivers. Fishermen currently using the river
may be
momentarily affected as the rafts pass along the river or by one of the short
stops. This effect could currently be experienced
by general members of the
public using the river and is not considered to be unreasonable or unexpected.
Mitigation strategies when
encountering anglers has been discussed earlier in
this report.
- [12] Another
issue addressed in the assessment of environmental effects was the effect on
“natural character, amenity and cultural
values”. It was said
that:
The dependency of the activity on the state of the environment
ensures that natural character and amenity will be preserved.
Consultation with Te Ao Marama Inc & Ngai Tahu has not identified any
effect on indigenous values associated with the rivers.
- [13] The written
consent of a number of interested parties was also provided with the
application. This included the written approval
of the Southland Fish &
Game Council (Fish and Game), which had provided its written approval to
Excursions 2, 3 and 4.[4] Te
Rūnanga o Ngāi Tahu and Te Ao Marama Inc, representing Māori
interests, also provided written approval, as did
the Department of Conservation
and Environment Southland (the Southland Regional Council). Written approval
was also provided by
Land Information New Zealand as the “assumed
owner of: part bed of Mataura River”.
Processing the
application
- [14] The Council
instructed an independent planning consultant, Mr Robert Buxton, to review and
assess the application. After he
had considered it he sought further
information and asked that the written approval of affected persons be obtained.
His email of
11 April 2019, addressed to Mr Weir, relevantly read as
follows:
... I consider the owners and occupiers of the land over
which the operation will be undertaken (drop off points, pick up points and
access to the river, as well as the car parking area in Mataura) are deemed to
be affected.
Pursuant to section 92 of the Resource Management Act 1991:
1. Identify the owners and occupiers of land over which the operation will
be undertaken (drop off points, pick up points and access
to the river, as well
as the car parking area in Mataura).
2. Advise how the car parking arrangement in Mataura will be legally secured
for the use by the operator.
3. Advise the toileting arrangement for day trips.
Pursuant to Section 92(3) of the Resource Management Act 1991, the [reason]
for requesting this further information is to ensure full
understanding of the
proposal.
In accordance with Section 92A of the Act, within 15 working days of
receiving this request, you have the options of:
(a) providing the information, or
(b) advising the Gore District Council in a written notice that you agree to
provide the information, or
(c) advising the Gore District Council in a written notice that you refuse to
provide the information.
Once you have identified each of the owners, and occupiers (if different from
the owner), please get each of the owners, and occupiers,
to fill in the
Affected Person Approval Form and to sign or initial a copy of the plans.
Alternatively, if you do not obtain all
written approvals, you may request that
the Council process the consent on a Limited Notified basis where the owners and
occupiers
who have not provided written approval will be served a copy of the
application and given 20 working days to provide a submission
to the Council.
[Additional] deposit fees will be required to proceed with Limited Notification.
The processing of the application
will be suspended until you have provided the
written approvals or requested Limited Notification and paid the fees as
outlined above.
- [15] Mr Weir
provided a comprehensive reply to the issues raised in Mr Buxton’s
request for further information in a letter
(with various attachments) dated
25 July 2019, but apparently not received by the Council until 8
August 2019.
- [16] Between 22
August 2019 and 28 September 2019, the Council and the Southland District
Council received a substantial number of
emails from concerned members of the
angling community opposing Mr Joostens’ application and requesting
public notification.
- [17] Mr Buxton
was satisfied there was sufficient information to report on the application. On
3 October 2019, he provided a recommendation
to the Council in the form of a
draft decision granting consent. This also contained his assessment for the
purposes of deciding
whether the application should be notified. The report was
framed as a draft grant of consent on a non-notified basis.
The consent
- [18] On 10
October 2019, the Council by its delegate, Mr Henderson, granted resource
consent on a non-notified basis for Excursions
2, 3 and the portion of Excursion
4 that fell within the Gore District. In the decision, the Council recorded
that no person, other
than those who had already given their approval, could
reasonably claim to be affected by the proposal to the extent that their
approval
or notification was required.
- [19] Specifically,
the decision recorded that:
Any disturbance of aquatic wildlife will
also be infrequent and short-term. The Applicant has advised that on his own
trips through
Excursion 1 (the Upper Mataura River in the Southland District),
trout have been observed and continued feeding while the raft drifted
past. I
note that this experience appears to be similar to that of the Manager of
Rafting NZ who has provided (in further information
from the applicant) a
statement about their operation on the Tongariro River, noting:
“The rafts have a minimal effect on the fishing, with the fish
looking quite relaxed in the water as we float over them from
above.”
While it is acknowledged that the Tongariro River is a deeper river, I accept
Mr Buxton’s view that the experience of observing
the fish will encourage
clients to reduce any activities that would disturb the fish. In the
description of the excursions, the
Applicant has mentioned that the trips will
involve leisurely travel, and it is accepted this can occur without significant
disturbance
to aquatic life.
Overall, I am satisfied that the proposal will have less than minor adverse
effects on ecology, wildlife habitats and water quality
due to the infrequent
and short-term contact time, and the small scale of the operation. In reaching
this view I also note that
[the Department of Conservation], Environment
Southland and [Fish and Game] have given their written approvals to the
proposal.
- [20] As to
potential interactions with existing river users, the decision included the
following:
Existing users of the surface of the water will mainly be
trout anglers and jet boating events ...
Similar to the adverse effects on ecology and wildlife habitats discussed
above, I consider that any interaction with trout anglers
will be infrequent and
short-term, at both the launching and landing sites as well as during the trip.
I agree that any interaction
can be managed by the rafting operators to minimise
any impact. For example, the Applicant has stated
“The Applicant proposes that short stops, during the excursions
proposed, will not be undertaken within 200m of any other river
users unless
their permission is obtained.”
The rafting operator can also manage interactions at launch and retrieval
sites by undertaking pre-trip briefings well away from any
anglers, and
launching and removing the rafts efficiently so that time spent at the
river’s edge is minimised. The launch
and retrieval sites generally have
enough space for the operation to provide a suitable separation from other
users.
- [21] The Society
sought judicial review of the decision, claiming that the Council had made three
errors, each of which each rendered
the decision not to notify invalid. The
Society claimed the Council had erred by:
(a) treating Fish and
Game’s approval as representative of the interests and views of the
angling community when it was not;
(b) failing to take account of relevant considerations for the purposes of
s 95A of the Resource Management Act 1991 (the RMA); and
(c) failing to be sufficiently informed before deciding to proceed on a
non‑notified basis.
Statutory scheme
- [22] Section
95A(1) of the RMA provides that a consent authority must follow the steps
prescribed in that section to determine whether
to publicly notify an
application for resource consent. Under subs (7)(a), public notification
is required if:[5]
...
the consent authority decides, in accordance with section 95D, that the activity
will have or is likely to have adverse effects
on the environment that are more
than minor.
- [23] Section
95D(e) provides that in determining whether adverse effects are more than minor,
the consent authority must disregard
any effect on a person who has given
written approval to the relevant application.
- [24] If an
application is not publicly notified, a consent authority must consider limited
notification under s 95B.[6] Provided
limited notification is not precluded, a consent authority must notify
“affected person[s]” under s 95B(8).
Pursuant to s 95E(1), a
person is an “affected person” if the consent authority decides the
proposed activity’s
adverse effects on the person will be minor or more
than minor (but not less than minor). It has not been suggested that there
should
have been limited notification of the application in this case.
- [25] The
statutory provisions as they stood before the RMA was amended to assume its
current form by the Resource Management (Simplifying
and Streamlining) Amendment
Act 2009 were discussed by the Supreme Court in Discount Brands Ltd v
Westfield (New Zealand) Ltd.[7]
In that case, Blanchard J summarised the information required before a
decision could be made on whether an application for resource
consent should be
publicly notified in the following passage:
[114] So, in summary to
this point, the information in the possession of the consent authority must be
adequate for it: (a) to understand the nature and scope of the proposed
activity as it relates to the district plan; (b) to assess the magnitude of
any
adverse effect on the environment; and (c) to identify the persons who may be
more directly affected. The statutory requirement is that the information
before the consent authority be adequate. It is not required to be
all-embracing
but it must be sufficiently comprehensive to enable the consent
authority to consider these matters on an informed basis.
[115] The statutory requirement addresses more than the scope of the
information. The consent authority must necessarily be satisfied
as well that
the information is reliable, especially so where an expert opinion is tendered.
The authority will need to consider
whether the author of the opinion is both
appropriately qualified to speak on the subject and sufficiently independent of
the applicant
so as to be seen as giving expert advice rather than acting as an
advocate for the applicant.
[116] Because the consequence of a decision not to notify an application is
to shut out from participation in the process those who
might have sought to
oppose it, the Court will upon a judicial review application carefully
scrutinise the material on which the
consent authority’s non-notification
decision was based in order to determine whether the authority could reasonably
have been
satisfied that in the circumstances the information was adequate in
the various respects discussed above.
(Emphasis added).
- [26] Blanchard J
had earlier said that the information before the consent
authority:[8]
... can be
supplied by the applicant, gathered by the authority itself or derived from the
general experience and specialist knowledge
of its officers and decision makers
concerning the district and the district plan. But in aggregate the information
must be adequate
both for the decision about notification and, if the
application is not to be notified, for the substantive decision which follows
to
be taken properly – for the decisions to be informed, and therefore of
better quality.
- [27] The 2009
amendments to the RMA changed the statutory provisions, and in Coro
Mainstreet (Inc) v Thames-Coromandel District Council this Court observed
that the amendments to the statute since Discount Brands were substantial
and had been directed at “providing greater facility for
non-notification”.[9] The Court
held out the possibility that the law articulated in Discount Brands
might need further evaluation in the revised statutory
setting.[10] It was however
unnecessary to carry out such further evaluation in that case and the Court did
not do so.
- [28] In this
case there is also no need to revisit the standard set out in
Discount Brands, as neither party has sought to argue that a less
exacting standard is appropriate. Further, in the High Court, Osborne J
held that
notwithstanding the 2009 amendments, Discount Brands continued
to be good law on the information that a consent authority should have when
deciding whether to notify a resource consent
application.[11] The absence
of any argument by the parties that he was wrong makes it inappropriate for us
to reach a different view on appeal in
this case.
High Court
decision
- [29] Osborne J
rejected the Society’s challenge. As to the first alleged error, he held
that the Society’s submissions
misconstrued the Commissioner’s
report by suggesting that he had treated the written approval from Fish and Game
as representing
the interests and views of the angling
community.[12] Rather, the
Commissioner identified Fish and Game’s provision of its consent, before
considering whether there were adverse
effects on anglers. This was the
“antithesis of treating Fish and Game’s approval as representing the
interests of the
entire angling
community”.[13] The Judge
noted the existence of the emails expressing concerns about the proposal, and
summarised the Society’s submission
on the emails as follows:
[68] The Society has not pleaded that the Council erred in the
consideration or scrutiny the Council might have given to the email
correspondence. The Society pleads the existence of the email
correspondence simply as a basis for the assertion that the Council
treated the
Fish and Game approval as given on behalf of the angling community.
- [30] Accordingly,
the Judge considered that on the facts, it was not necessary to consider further
what the substance of the email
correspondence may have shown or
suggested.[14] However, the Judge
noted that:[15]
There
may be a tenable argument that, in some circumstances, particularly where such
correspondence involves incontrovertible information,
the decision-maker might
be required to consider further such information. This is not an
appropriate case in which to consider
such an approach or to identify what would
be its limits.
- [31] Turning to
the second alleged error, the Judge held that the Council did not fail to take
into account relevant considerations.
It was not correct, as the Society
alleged, to dismiss as a mere assertion the content of the proposal which set
out the restrictions
and circumstances under which the rafting would
occur.[16] The Council had reached
its conclusions from the information properly before it as to the nature and
duration of the rating excursions,
which the Council had found to be “not
significantly different to a non-commercial operation” and to be
“infrequent
and
short‑term”.[17]
- [32] Given the
Judge’s findings on the earlier issues, he also dismissed the third
alleged error based on the Council’s
alleged failure to be sufficiently
informed.[18]
Appeal
- [33] The Society
appeals the High Court judgment on three grounds. It concedes that the Council
did not treat Fish and Game’s
approval as given on behalf of the whole
angling community, but nevertheless claims that:
(a) The Judge was
wrong to dismiss the Society’s claim that the Council had insufficient
information for its decision not to
notify the application.
(b) The Judge was wrong to find that the Society had not pleaded that the
Council erred in failing to consider the email correspondence
sent to it by
members of the angling community.
(c) As a result of the error in (b), the Judge erred in not determining
whether the Council made an error of law as a result of the
information not
being referred to by Mr Buxton in his recommendations on notification to the
Commissioner.
- [34] We deal
with each of these grounds of appeal in turn.
First issue
— insufficient information to make the decision not to notify the
application
- [35] In
advancing this aspect of the appeal, Mr Walker, counsel for the Society,
noted that the Judge held there was sufficient information
before the
Commissioner on the basis that the application had set out the frequency and
duration of the proposed rafting excursions,
the controls which were proposed in
terms of the management plans submitted with the application and what
Mr Walker described as
“Mr Joostens’ assertions as to his
own experience and observations through the Mataura River”.
- [36] Mr Walker
submitted that the information was insufficient for the Council to make an
informed decision as to whether the adverse
effects of the proposal on angling
and recreational amenity would be minor or more than minor. While the opinions
of the angling
community, set out in the emails forwarded to the Council but not
considered by the Commissioner, did not amount to expert evidence,
the views of
anglers as to why they appreciated the amenities of the Mataura River was of
more relevance and probative value than
the applicant’s own observations.
Mr Walker contended that an assessment of an effect on amenity values was
necessarily subjective,
and a “values based” judgment of the kind
required in this case must commence with an understanding of the subjective
appreciation of the relevant amenity values as articulated by those who enjoy
them. Information about the frequency and duration
of the activity could not
properly be assessed without reference to that subjective appreciation.
- [37] In the High
Court, the argument that the Council had not considered all relevant potential
adverse effects of the proposal because
the Commissioner did not consider the
numerous emails which had been received from the members of the angling
community was advanced
in the context of a pleading which asserted that the
Council had failed to consider those emails because it had wrongly treated the
written approval of Fish and Game as an effective approval of the application
“by the angling community”. That argument
has not been pursued in
this Court, but an argument based on failure to take the emails into account has
nevertheless been advanced
on the basis that the views of the angling community
should have been considered. In essence, the allegation now is that without
having the views of anglers who fish on the Mataura River, the Council lacked
the information necessary to determine that the adverse
effects of the proposed
activity on the environment would not be more than minor.
- [38] In dealing
with the argument in the High Court, the Judge rejected the Society’s
proposition that the content of the application
was “mere
assertion”.[19] The
application had set out restrictions and circumstances under which the proposed
activities would occur. The three excursions
for which consent was sought had
been defined and a maximum number of trips on a daily and weekly basis had been
provided. The Judge
considered the information contained in the application was
“the very material on which the Council was able to reach reliable
conclusions as to such key matters as the period of
interaction”.[20] He
continued:[21]
Such
details were not challenged in this proceeding. The Commissioner for instance
observed in relation to ecology considerations
that, at a speed of approximately
4 km/hr, it would take approximately three minutes for the rafts to travel from
100 m above a nesting
site to 100 m below a nesting site. Similarly, in
relation to trout anglers in particular, the Commissioner recorded that:
... a trout angler may experience up to two rafts passing within 100m of
their location over a period of approximately 3 minutes for
each raft over
the period of the day.
- [39] The Judge
also dealt with the argument that the Commissioner had given too much weight to
observations of Mr Joostens based on
his own experience, and comparisons that
had been drawn with the Tongariro River. The Judge
observed:
[91] The point at which the Commissioner recorded those
was in the assessment of effects on ecology and wildlife habitats. The context
is relevant and I set out the section in question:
Any disturbance of aquatic wildlife will also be infrequent and short-term.
[Mr Joostens] has advised that on his own trips through
Excursion 1 (the Upper
Mataura River in the Southland District), trout have been observed and continued
feeding while the raft drifted
past. I note that this experience appears to be
similar to that of the Manager of Rafting NZ who has provided (in further
information
from [Mr Joostens]) a statement about their operation on the
Tongariro River, noting
“The rafts have a minimal effect on the fishing, with the fish
looking quite relaxed in the water as we float over them from
above.”
While it is acknowledged that the Tongariro River is a deeper river, I
accept Mr Buxton’s view that the experience of observing
the fish will
encourage clients to reduce any activities that would disturb the fish. In the
description of the excursions, [Mr Joostens]
has mentioned that the trips will
involve leisurely travel, and it is accepted this can occur without significant
disturbance to
aquatic life.
[92] Mr Joostens’ information as to his own experience cannot be viewed
as independent evidence and there was no detailed analysis
to measure the impact
of fish on the Tongariro River. But those matters were demonstrably secondary,
serving to provide some explanation
of the dominant conclusions in the first and
last sentences of the Commissioner’s reasoning set out at [91] above. The
Council’s
conclusions were clearly driven by the timing detail of the
proposal for excursions (“Any disturbance of aquatic wildlife will
also be
infrequent and short-term”) and in the description of the excursions
(Mr Joostens having “mentioned that the
trips will involve leisurely
travel ... without significant disturbance to aquatic life”).
(Footnote omitted.)
- [40] On this
basis, the Judge found that the Commissioner’s conclusions were derived
from information properly before the Council
as to the nature and duration of
the rafting excursions which the Commissioner considered would not be
“significantly different
to a non-commercial operation” and would be
“infrequent and
short-term”.[22] On this
basis, the Judge rejected the Society’s challenge based on insufficient
information.[23]
- [41] The
Commissioner discussed the assessment of effects forming part of the application
in some detail. He noted that existing
users of the surface of the water would
mainly be trout anglers and those involved in jet boating events. There would
also be occasional
recreational users in the form of kayaks or similar
activities. He expressed the view that “any interaction with trout
anglers
will be infrequent and short-term, at both the launching and landing
sites as well as during the trip”. He considered that
any such
interaction could be managed by the rafting operators to minimise any impact and
he noted that the application proposed
that short stops during the excursions
would not be undertaken within 200 meters of any other river users unless their
permission
was obtained. He also observed that the rafting operator could
manage interactions at the launch and retrieval sites by undertaking
pre-trip
briefings in a location distanced from any anglers, and launching and removing
the rafts efficiently so that time spent
at the river’s edge was
minimised. There was enough space for the operation to provide suitable
separation from other users.
- [42] The
Commissioner concluded that at the scale of operation proposed, the proposal was
not significantly different to a non-commercial
operation. He said:
Although a commercial operation by its very nature will generally
be more regular than a non-commercial use, the level of interaction
by the
proposal is still considered to be infrequent and short-term. For example, a
trout angler may experience up to two rafts
passing within 100m of their
location over a period of approximately 3 minutes for each raft over the period
of the day. It is also
noted that some of the clients may be trout anglers who
want to access some parts of the river inaccessible by land.
- [43] We accept
Mr Garbett’s submission for the Council that these facts were all
able to be ascertained from the details and
description of the proposal in the
consent application. They enabled the Commissioner to assess the likely
interaction between anglers
and rafts and the time a raft would take to pass an
individual angler. We accept that it was reasonably open to the Commissioner
to
determine that the level of interaction with and potential effect on anglers
would be infrequent, short-term and small in scale.
- [44] It is also
worth noting that conditions were imposed requiring provision of an operational
management plan, including procedures
covering the launching and retrieval of
rafts, rafting, short stops, interaction with other users of the river
(including times when
it might be appropriate to cease activity) and other
matters. The operational management plan was required to be provided
before
commencement of the operation.
Second issue —
failure to consider email correspondence not pleaded
- [45] We have
already touched on this issue in the preceding discussion. The Judge held that
the Society had not pleaded that the
Council erred in failing to consider the
email correspondence sent to it by members of the angling
community.[24] Rather, he
considered the pleaded claim to be that the Council had wrongly treated Fish and
Game’s written approval as given
on behalf of the angling community, the
emails from the anglers being relied on to negate any suggestion that Fish and
Game spoke
for them. Since he considered the Council had not proceeded on the
basis that Fish and Game’s approval was given on behalf
of anglers
generally, that was sufficient to dispose of this cause of action. It was
therefore unnecessary to consider a direct
allegation that the Council had
wrongly failed to consider the
emails.[25]
- [46] Mr Walker
complained that as a result of this approach, the Judge had found it unnecessary
to consider further the substance
of the emails and the information they
contained. He argued that the Judge misconstrued the statement of claim, and
that the Society
had pleaded directly that the Council erred by not considering
the emails.
- [47] We do not
consider the Judge made any error in the way he construed the statement of
claim. The relevant allegation in the pleading
was that in making the decision
to process the application on a non-notified basis, the Council misdirected
itself and was in breach
of its obligations under s 95A of the RMA by
treating the written approval received from Fish and Game as representing the
interests
and views of the angling community on the proposal and amounting to an
approval by them in relation to the adverse effects on the
recreational amenity
of the anglers. That was the allegation that the Judge rejected on the basis
that the Council had considered
the potential effects of the proposal on actual
river users. His reasoning was encapsulated in the following paragraph of
judgment:
[60] Having identified trout anglers and jet boating
events as the main existing users of the surface of the water, the Council then
noted Fish and Game’s provision of its written approval (my
emphasis). The Council then immediately proceeded to consider whether there
were adverse effects on anglers,
including by reference to the frequency and
duration of interactions and distancing, the management commitments within the
Proposal,
and the potential for satisfactory co-existence of activities (such as
rafting and fishing in particular). The consideration, through
the lengthy
section of the Decision in pages 6–10, is the antithesis of treating Fish
and Game’s approval as representing
the interests and views of the entire
angling community.
(Footnote omitted, emphasis in original.)
- [48] We cannot
fault this reasoning and we reject the second ground of appeal.
Third issue — relevant information not made available to
the decision maker
- [49] The third
error alleged is that the Commissioner did not have sufficient information as to
the actual potential effects of the
proposal because the email correspondence
was not made available to him. This argument obviously overlaps to a
considerable degree
with the first and second alleged error. In this context it
is said that the planning consultant who reported to the Council,
Mr
Buxton, had contributed to the error by not referring the emails to the
Commissioner. If the emails had been provided to the Commissioner
he could then
have made a judgment as to the value of the material.
- [50] In support
of this ground of appeal, Mr Walker referred to the judgment of the High
Court in Videbeck v Auckland City
Council.[26] In that case,
there was criticism of a planning officer preparing an assessment of whether an
application for resource consent should
be publicly notified without providing
to the decision maker correspondence received from a neighbour claiming to be
adversely affected
by the proposal and a supporting opinion provided by an
arborist.
- [51] However, on
the facts of Videbeck the High Court was able to conclude that without
provision of the letter received from the affected neighbour and a further
letter
from his lawyer, the report about notification had lacked
balance.[27] The Judge held that a
balanced report should alert the decision maker not only to the facts and view
formed by the person reporting
on the application, but also to contrary views
known to the reporter which the decision maker could then
consider.[28]
- [52] In this
case however, we do not consider that the report prepared for the
Commissioner’s consideration could be said to
lack balance. We have
already referred to Mr Walker’s submission that “balance”
required that the Commissioner
be informed of the subjective views of anglers
about how their amenity might be affected by the proposal. For the reasons we
have
discussed, we do not accept that proposition.
- [53] The amenity
of anglers wishing to fish on the Mataura River is a relevant issue because of
the need to assess, both at the notification
stage and in relation to the grant
of consent, the potential adverse effects on the environment of the proposed
activity. All applications
for resource consent must provide the information
set out in cl 2 of sch 4 of the RMA, including an assessment of the
activity against
the matters set out in pt 2 of that Act (including
s 5, among other provisions). Avoiding, remedying and mitigating any
adverse
effects of activities on the environment is central to the concept of
sustainable management set out in s 5(2). And applicants for
resource
consent must provide an assessment of environmental effects which addresses the
actual or potential effects on the environment
of the activity, in accordance
with cl 6(1)(b) of sch 4.
- [54] The term
“environment” is defined in s 2(1) of the RMA so as to embrace,
amongst other things, “amenity values”,
which is defined as meaning
“those natural or physical qualities and characteristics of an area that
contribute to people’s
appreciation of its pleasantness, aesthetic
coherence, and cultural and recreational attributes”. There is thus no
difficulty
in bringing within the ambit of the relevant matters that needed to
be assessed in this case the natural and physical qualities of
the Mataura River
and its surroundings which contribute to, amongst other things, the appreciation
by anglers of its pleasantness
and recreational attributes.
- [55] But it is
important to note that what is to be assessed is those qualities and
characteristics which contribute to the appreciation
of the recreational
attributes, not the appreciation itself. Mr Walker’s submission that
reference to the subjective views
of the anglers was necessary to assess the
effects of the application cannot therefore be sustained under the relevant
statutory
provisions.
- [56] What was
necessary was that the Commissioner be informed about the characteristics of the
area, and the effects of the proposed
activity on those characteristics. On
those issues, we consider there was sufficient information before him for the
purposes of
both the notification and consent decisions. He was aware of all
the necessary facts, and able to draw inferences and apply his
understanding of
them in making his decision. The subjective views of anglers would not have
added anything of value to his consideration
of the application.
- [57] We
therefore reject the third ground of appeal.
Result
- [58] For the
reasons we have given the appeal is dismissed.
- [59] The
appellant must pay the first respondent costs calculated for a standard appeal
on a band A basis, together with usual disbursements.
We certify for second
counsel.
Solicitors:
Todd & Walker Law, Queenstown
for Appellant
Anderson Lloyd, Dunedin for First Respondent
[1] Another application lodged
with Southland District Council also sought resource consents for activities
focused on other sections
of the Mataura River, in addition to the Oreti and
Waikaia Rivers. The application was also granted on a non-notified basis on 18
November 2019. That decision has not been the subject of litigation.
[2] NZ Southern Rivers Society
Inc v Gore District Council [2020] NZHC 1996 [High Court judgment].
[3] Excursions 1, 5 and 6 were
located within the Southland District and were considered by the Southland
District Council.
[4] In a letter of 19 March 2019
addressed to Mr Joostens and attached to the resource consent application, Fish
and Game provided approval
in principle for Excursions 2, 3, 4 and 5 but
withheld approval for Excursions 1 and 6. That position was later confirmed in
an
email dated 25 September 2019.
[5] Resource Management Act 1991,
s 95A(8)(b).
[6] Section 95B(1).
[7] Discount Brands Ltd v
Westfield (New Zealand) Ltd [2005] NZSC 17, [2005] 2 NZLR 597.
[8] At [107].
[9] Coro Mainstreet (Inc) v
Thames-Coromandel District Council [2013] NZCA 665, [2014] NZRMA 73 at
[34].
[10] At [41].
[11] High Court judgment, above
n 2, at [44], citing Ferrymead
Retail Ltd v Christchurch City Council [2012] NZHC 358 at [80].
[12] At [59].
[13] At [60].
[14] At [69].
[15] At [69].
[16] At [88].
[17] At [93].
[18] At [96].
[19] At [88].
[20] At [88].
[21] At [88] (footnotes
omitted).
[22] At [93].
[23] At [96].
[24] At [68].
[25] At [69].
[26] Videbeck v Auckland City
Council [2002] 3 NZLR 842 (HC).
[27] At [65] and [68].
[28] At [60].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2021/296.html