You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2021 >>
[2021] NZCA 351
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Keller v Daisley [2021] NZCA 351 (29 July 2021)
Last Updated: 3 August 2021
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
PAUL GERRARD KELLER AND KAREN ELIZABETH KELLER First
Appellants
ARK CONTRACTORS LIMITED Second Appellant
|
|
AND
|
MALCOLM JAMES DAISLEY Respondent
|
CA30/2021
|
|
BETWEEN
|
MALCOLM JAMES DAISLEY First Appellant
HPL DISTRIBUTION
LIMITED Second Appellant
ACTION FENCING LIMITED Third
Appellant
|
|
AND
|
ARK CONTRACTORS LIMITED First Respondent
PAUL GERRARD
KELLER Second Respondent
|
CA31/2021
|
|
BETWEEN
|
MALCOLM JAMES DAISLEY First Appellant
HPL DISTRIBUTION
LIMITED Second Appellant
|
|
AND
|
ARK CONTRACTORS LIMITED Respondent
|
Hearing:
|
29–30 June 2021
|
Court:
|
Cooper, Collins and Goddard JJ
|
Counsel:
|
J A Browne for Appellants in CA271/2020 and Respondents in CA30/2021
and CA31/2021 E L Smith for Respondents in CA271/2020 and Appellants in
CA30/2021 and CA31/2021
|
Judgment:
|
29 July 2021 at 3.00 pm
|
JUDGMENT OF THE COURT
CA271/2020
- The
appeal in CA271/2020 is allowed.
- The
award of damages/equitable compensation to Mr Daisley is set
aside.
- The
cross-appeal in CA271/2020 is dismissed.
- The
respondent must pay the appellants costs in respect of the appeal and
cross-appeal, in each case for a standard appeal on a band
A basis, with usual
disbursements.
CA30/2021
- The
appeal in CA30/2021 is allowed in part. The damages awarded are increased by
$577.50. The appeal is otherwise dismissed.
- The
appellants must pay the respondents 90 per cent of the costs for a standard
appeal on a band A basis, with usual
disbursements.
CA31/2021
- The
appeal in CA31/2021 is dismissed.
- The
appellants must pay the respondent costs for a standard appeal on a band A
basis, with usual
disbursements.
____________________________________________________________________
Table of contents
Para no
REASONS OF THE COURT
(Given by Goddard J)
Introduction
- [1] A
business transaction between the Daisley interests and the Keller interests in
2009/2010 quickly turned sour. It spawned three
sets of proceedings, which were
heard before Walker J in the High Court over some three weeks in 2019 and 2020.
From each of those
decisions, the unsuccessful parties appeal to this
Court.
- [2] The main
dispute concerns the performance of agreements entered into on the eve of the
first of four mortgagee sales of four properties
owned by the
Daisley interests. As contemplated by that arrangement, the Kellers
established Ark Contractors Ltd (Ark). Ark purchased
the four properties,
using equity provided by the Kellers and bank funding. Ark was to be owned by
the Kellers and the Daisleys,
with shareholdings set by reference to initial
equity contributions (the funds introduced by the Kellers, and the
Daisleys’
remaining equity in the properties).
- [3] The parties
signed an agreement setting out the essential elements of this arrangement on 2
December 2009 (the Ark agreement).
Shortly afterwards, Mr Daisley claimed
that this agreement had been entered into under duress. There was a
re-negotiation in the
period leading up to the date by which Ark needed to
complete a purchase of the properties, to avoid a mortgagee sale. An agreement
was reached to enable the transaction to proceed (the January 2010 agreement).
That agreement included the terms of a shareholders
agreement for Ark. Ark
purchased the properties.
- [4] The Kellers
then claimed that the January 2010 agreement was entered into under duress, and
purported to set it aside, restoring
the original terms.
- [5] The duress
allegations — running both ways — occupied a significant part of the
hearing time in the High Court. The
Judge rejected these
allegations.[1]
Those findings are not challenged on appeal. Thus the parties’
mutual rights and obligations are governed by the Ark agreement,
as modified by
the January 2010 agreement.
- [6] Further
differences arose. The Daisley interests were to rent one of the properties,
known as “the Depot”. They
continued to occupy it. But they did
not pay the agreed rent, and in August 2010 they moved out. They removed two
office buildings
from that property, and were in the process of removing more
buildings when they were prevented from doing so by the Kellers. The
Kellers
say that the Daisleys converted those two buildings. The Kellers then locked
the Daisleys out of the Depot. The Daisleys
say that the Kellers converted
various chattels which the Daisleys had not yet removed from the property before
they were locked
out. They say they were denied the opportunity to recover
those chattels.
- [7] As a result
of the various disputes that arose between the parties, Mr Daisley never
received the shareholding in Ark that he
had been promised. The Kellers have
consistently taken the position that they are willing to issue those shares to
Mr Daisley, once
certain pre-conditions are
met.
The
main proceedings (CA271/2020)
- [8] The
primary claim brought by the Daisley interests against the Keller interests
alleged (as well as duress) breaches of contract,
breaches of fiduciary duty and
a constructive trust. The Judge did not accept any of those claims as
pleaded. But the Judge found
that the Kellers and Ark had breached a
contractual obligation to issue shares to Mr
Daisley.[2] The Judge found that this
was also a breach of fiduciary
duty.[3] She made an award of
equitable compensation/damages of $541,721 against Ark and the Kellers. This
was the amount that Mr Daisley
was treated as contributing to Ark by way of
equity in the properties, under the Ark agreement as
amended.[4] Effectively, the Judge
ordered that he be repaid his initial investment.
- [9] No claim for
breach of an obligation to issue shares in Ark had been pleaded, and no formal
application to amend the pleadings
was made at trial — indeed the
Daisleys’ claim was only framed in this way in closing.
- [10] The Judge
declined to award interest to Mr Daisley on the compensation/damages awarded, on
the basis that no claim for interest
had been
pleaded.[5]
- [11] On appeal,
the Kellers challenge the award of equitable compensation/damages. The Daisleys
challenge the Judge’s refusal
to award
interest.
The
Depot proceedings (CA31/2021)
- [12] Ark
brought proceedings against Mr Daisley for conversion of the two office
buildings. Ark also claimed against two companies
owned by the Daisleys —
Action Fencing Ltd (Action Fencing) and HPL Distribution Ltd (HPL
Distribution) — for unpaid
rent in respect of the Depot. There was also a
claim for reimbursement for certain expenses which Ark had met on behalf of the
Daisleys.
Those claims were largely
successful.[6]
- [13] Mr Daisley
appeals in relation to the conversion finding, and HPL Distribution appeals in
relation to liability for rent.
The
chattel conversion proceedings (CA30/2021)
- [14] Action
Fencing, HPL Distribution and Mr Daisley claimed for conversion of property left
behind at the Depot, which they say they
were not permitted to remove, and some
of which was delivered to third parties rather than to them. That claim was
partly successful
in the High
Court.[7]
They appeal from the Judge’s decision dismissing their conversion claim in
respect of a number of other items of property.
Background
The Daisleys face
significant financial pressure
- [15] Mr
Malcolm Daisley (known as Jimmy Daisley) is a contractor, company director and
businessman in the Whangārei district.
At the relevant time, he was living
at the Depot: a property in Maungakaramea, about 10 kilometres south of
Whangārei. Mr
Daisley also ran his businesses from the Depot.
- [16] Mr
Daisley’s son, Scott Daisley, works with him in his contracting business.
Scott Daisley was closely involved in the
events giving rise to the
parties’ litigation with the Kellers. He was also a director of SDD Ltd
(SDD), one of the parties
in the High Court (but not before this Court).
- [17] In late
2009 Mr Daisley and his companies were under significant financial stress. He
was facing a mortgagee sale of four properties:
(a) the Depot at 1
Maungakaramea Road (NA61B/263) — a one-hectare property owned by Mr
Daisley;
(b) Tangowahine Valley Road (NZ30A/927) — a 45-hectare rural property
located between Whangārei and Dargaville, owned by
SDD;
(c) Knight Road (NZ 1949/37) — a 47-hectare property located out of
Whangārei; owned by Mr Daisley; and
(d) Valley View Road (Lot 4 NA 130B/848; Lot 5 identifier 39602; Lot 6
identifier 39602) — three properties owned by Mr Daisley
totalling about
19 hectares.
- [18] Mr Daisley
and SDD owed Westpac New Zealand Ltd (Westpac) approximately $1.5 million. Mr
Daisley also owed around $110,000 to
a solicitor’s trust company which
held second mortgages over a number of the
properties.
The
Kellers come onto the scene
- [19] The
Kellers lived across the road from Mr Daisley. In the course of a visit to Mr
Daisley to follow up work done by one of his
companies, Mr Keller learned of
Mr Daisley’s financial predicament. Mr Keller suggested that he and
his wife had savings,
and might be able to help to refinance the bank debt and
securities.
- [20] Discussions
took place between the Kellers and the Daisleys. Scott Daisley provided the
Kellers with a “Finance Proposal”
dated November 2009, which had
been prepared for Kiwibank as part of the Daisleys’ refinancing efforts.
That Finance Proposal
included valuations of each of the four properties. The
valuation of the Depot is relevant to one of the disputes before this Court,
and
is discussed in more detail below.
- [21] On 27
November 2009 the Kellers and their accountant, Mr Lay, met with
Mr Daisley, Scott Daisley and Mr Daisley’s then-lawyer,
Mr Jackson.
A proposal was discussed which would enable the mortgagee sales to be avoided.
A new company (Ark) would be formed.
Ark would buy the four properties, with
funding from the Kellers’ savings of approximately $800,000 and bank
borrowing. The
shareholding in Ark would be in proportion to the respective
contributions of the Kellers and the Daisley interests. The property
values to
be used for the purchase of those properties, and to value the Daisleys’
contribution, would be the registered valuations
included in the Finance
Proposal, less a 25 per cent discount to reflect the mortgagee sale context and
the passage of time since
the valuations were done.
- [22] There were
further discussions, and some email correspondence. Additional issues emerged,
including Mr Keller learning for the
first time about the second mortgage over
the properties. In light of the further information received, the Kellers
became concerned
about the proposed arrangements. At a further meeting on
30 November 2009, the Kellers told Mr Daisley that they were backing out.
The Kellers say that Mr Daisley’s response was a persuasive pitch to
keep them in. They were persuaded to continue with the
proposal.
- [23] On 1
December 2009 the Kellers incorporated Ark, with themselves as sole directors
and shareholders.
- [24] The
Kellers’ solicitor, Mr Badham, was engaged to put the arrangement
together. He communicated with Westpac, with the
solicitors holding the second
mortgages, and with the Daisleys’ lawyer, Mr Jackson. On 2 December 2009
Westpac, through its
solicitors, confirmed that it would agree to a sale of the
properties to Ark subject to a number of conditions, including payment
of a
$200,000 non-refundable deposit on execution of the sale and purchase
agreements.
The
Ark agreement
- [25] On
2 December 2009 a further meeting took place at Mr Badham’s office,
attended by the Kellers, Mr Daisley and Scott Daisley,
and Mr Badham. The
purpose of the meeting was to execute various documents, including an
overarching agreement in relation to the
arrangement (the Ark agreement). Mr
Badham had drafted the Ark agreement with input from Mr Lay. The draft Ark
agreement was sent
to Mr Jackson at 12.31 pm on the day of the
meeting. The meeting itself took place at 2.00 pm. The context of that
meeting is important.
There was significant time pressure if a deal was to be
done: the first mortgagee auction was due to take place the next day. The
Kellers remained wary about the proposal, and had not made a final decision
about whether or not they would proceed. The new information
obtained about the
Daisleys’ indebtedness under the second mortgages had implications for
Ark’s funding needs, and for
the parties’ interests in Ark.
- [26] Against
that backdrop, Mr Badham presented three agreements to the parties at the 2
December 2009 meeting. The first was the
Ark agreement, to be entered into by
Ark, Mr and Mrs Keller, SDD, Mr Daisley and Scott Daisley. It was
accompanied by two agreements
for sale and purchase in relation to the
properties. One agreement for sale and purchase named Mr Daisley as vendor and
Ark as purchaser.
The other named SDD as vendor and Ark as purchaser.
- [27] At the
meeting, Mr Badham explained that the proposal set out in the three agreements
was the Kellers’ only offer. Due
to time constraints imposed by the
imminent mortgagee sale, it was effectively a “take it or leave it”
proposal. If
the offer was not acceptable, it was likely the mortgagee sale
would proceed. Mr Badham went through the three contracts clause
by clause,
explaining them to all present.
- [28] Mr Daisley
and Scott Daisley signed the agreements. They say they did so under immense
pressure, without the benefit of independent
advice.
- [29] The
operative provisions of the Ark agreement read as
follows:
OPERATIVE PART:
- Once
settlement of the Sale and Purchase Agreements has taken place, the debts owed
by Ark to SDD under clause 20.0(b) of the SDD
Agreement, and to [Mr
Daisley] under clause 20.0(b) of the Daisley Agreement shall be repaid by the
issue to SDD and [Mr Daisley],
of shares in Ark, such that the resulting
shareholdings of [Mr and Mrs Keller] (or their nominees), and SDD and
[Mr Daisley] (or
their nominees) shall be determined in accordance with
Schedule B.
- In
the event that settlement of the Sale and Purchase Agreements does not occur as
a result of any default by SDD or [Mr Daisley]
in their obligations as vendors
under those agreements, then [Mr Daisley] and SDD acknowledge liability to [Mr
and Mrs Keller] for
all costs and losses incurred by [Mr and Mrs Keller] in
relation to the Sale and Purchase Agreements (including the negotiation and
preparation of the agreements and all related documentation), including
accountancy and legal fees, lost deposit moneys, and interest
thereon at the
interest rate for late settlement in the Sale and Purchase Agreements.
- Prior
to the issue of shares in Ark to [Mr Daisley] and SDD in accordance with clause
1, Ark will adopt a constitution in usual form,
subject to the following
specific provisions, some of which may, in the absolute discretion of [Mr and
Mrs Keller], be provided for
in a Shareholders Agreement that will be
signed by all of the shareholders of Ark at the time of the issue of the shares
to SDD and
[Mr Daisley].
- There
shall be two classes of shares. [Mr and Mrs Keller]’s shares shall be A
shares. [Mr Daisley] and SDD’s shares shall
be B shares.
- The
A shares shall have all the usual rights and powers, including voting powers,
provided that the A shares shall not entitle the
holders to make any changes to
the company’s constitution without the prior written consent of the
holders of all of the B
shares. The A shares shall entitle the holders to
appoint two directors.
- The
B shares shall have no voting rights or powers but shall have all other usual
rights and powers. The B shares shall entitle the
holders to appoint one
director.
- A
quorum for a directors’ meeting shall be two directors.
- Interest
shall be payable by Ark on shareholders’ advances at the ASB Bank Ltd
residential first mortgage variable interest
base rate plus a margin of 6%. The
interest rate as at 1 December 2009 will apply initially, subject to a six
monthly review.
- The
Shareholders Agreement shall otherwise be in usual form.
- [30] The Kellers
paid a deposit of $200,000 to Westpac. They also paid $50,000 to the
solicitors’ trustee company to enable
the second mortgages to be
removed.
- [31] The parties
continued to discuss other aspects of the arrangement, including a proposal
that Mr Daisley have a right to re-purchase
the Depot.
Claim that
the Ark agreement was entered into under duress
- [32] Around
this time, Mr Daisley engaged a new lawyer, Mr Skeates. On 9 December
2009 Mr Skeates wrote to Mr Badham asserting that
the Daisleys had signed the
agreements under duress, without adequate opportunity for independent advice.
He proposed a renegotiation
of the arrangements. Mr Badham denied the
allegations of duress, but proposed a meeting to resolve all outstanding issues.
- [33] The first
renegotiation took place by telephone conference on 22 December 2009.
Mr Keller, Mr Badham, Mr Daisley and Mr Skeates
participated.
Various agreements reached at that telephone conference were recorded in a
letter from Mr Badham to Mr Skeates dated
23 December 2009. Mr Skeates
confirmed by email later that day that the letter accurately recorded the
discussion and “appear[ed]
to [him] to meet [the Daisleys’] bottom
line requirements”. The parties proceeded on the basis that these were
agreed
variations to the Ark agreement.
- [34] Further
meetings took place in December 2009 and early January 2010, mostly focussed on
practical matters in relation to the
proposal.
The
January 2010 agreement
- [35] On
15 January 2010, Mr Badham sent a draft shareholders agreement to
Mr Skeates for review.
- [36] By 19
January 2010, the day before the intended settlement of the property
transactions, Mr Daisley had not signed certain documents
needed to enable Ark
to drawdown funds from its lender, Kiwibank. That delayed settlement. Various
explanations for delay were
proffered by the Daisley interests. However it
appears that the explanation was that the Daisleys were playing for time, while
exploring
alternative options. For example, Mr Daisley was in discussion
with a potential third party buyer of one of the properties.
- [37] On 22
January 2010, a week before Westpac’s deadline for settlement of the
property purchases, Mr Skeates wrote to Mr Badham
seeking to renegotiate aspects
of the Ark agreement. He also commented on specific clauses of the draft
shareholders agreement.
- [38] On 25
January 2010 Mr Badham responded to Mr Skeates’ letter. He accepted many
of the points made by Mr Skeates in relation
to the draft shareholders
agreement, and asked for specific proposed wording in relation to some points.
- [39] On 28
January 2010, the day before the Westpac deadline, Mr Skeates responded to Mr
Badham’s letter of 25 January 2010.
His response proposed further
variations to the Ark agreement. Some were commercially significant. He also
proposed some more
mechanical amendments to the agreement.
- [40] This put
the Kellers under considerable pressure. In their briefs of evidence the
Kellers said they considered they were faced
with a stark choice: agreeing to
these further demands in order to achieve settlement of the property transfers,
or pulling out and
losing the approximately $285,000 they had already put into
the venture. However in the course of giving evidence at trial Mr Keller
struck
a somewhat different tone, conceding that the variations sought to the Ark
agreement were not objectionable.
- [41] In any
event, early on the morning of 29 January 2010 Mr Badham faxed Mr Skeates
confirming acceptance of all the amendments
sought “including the
substantive matters specified on page 2 of [the 28 January 2010] letter”.
- [42] Settlement
of the property transactions took place on 29 January
2010.
Claim
that the January 2010 agreement was entered into under duress
- [43] A
few weeks later, however, the apparent consensus unravelled. Mr Badham wrote to
Mr Skeates on 11 February 2010, advising that
the Kellers considered that they
had been subject to duress in entering into the agreement reflected in the
correspondence in late
January 2010 (that is, the January 2010 agreement).
They advised that they “hereby exercise their option to void that
contract”.
Thus, Mr Badham said, matters should continue by
reference to the original Ark agreement of 2 December 2009.
- [44] Mr Skeates
responded on 15 February 2010, rejecting any right to avoid that contract.
The lease
of the Depot
- [45] Around
the same time, the Kellers and the Daisleys discussed arrangements for the
proposed lease of the Depot. As contemplated
by the parties, Mr Daisley and his
companies had continued to occupy the Depot. The parties agreed informally to
the property being
rented on the basis that it was divided into three separate
lettable areas: one area containing the house (from which Mr Daisley
also ran
his various businesses), a second area containing a half-round barn, large
office and small office, and a third area containing
a large shed. The area
containing the house was to be rented by “HPL”. (A number of
companies controlled by Mr Daisley
had names incorporating the acronym
“HPL”. Some confusion arose about which company was intended to be
the tenant, as
discussed in more detail below.)
- [46] Mr Badham,
on behalf of the Kellers, prepared a draft one-year lease of the Depot and sent
it to Mr Skeates for execution. The
tenants named in the draft lease were two
of Mr Daisley’s companies: Action Fencing and HPL Northland & North
Harbour Ltd
(HPL Northland & North Harbour).
- [47] That draft
lease was never signed. The version discovered by the Daisley interests had
“HPL Northland & North Harbour
Ltd” crossed out, and
“HPL Distribution Ltd” substituted. The Judge considered that
it was likely that this change
was made by Mr
Skeates.[8] As explained in more
detail below, HPL Northland & North Harbour was no longer trading at
this time. HPL Distribution was.
It seems likely that the parties
intended that HPL Distribution would be the tenant.
- [48] By May
2010, Mr Daisley’s companies were seriously behind with their rent. This
in turn put Ark in a difficult financial
position, as it needed to service its
bank
borrowings.
The
Daisleys leave the Depot
- [49] In
March and April 2010, three of Mr Daisley’s companies were placed in
voluntary liquidation. The liquidation reports
record that they were hopelessly
insolvent. Further correspondence between the solicitors and the parties
continued between May
and August 2010, but no resolution was reached.
- [50] Mr Daisley
then proposed an exit from the overall arrangement, on terms which the Kellers
rejected. The Daisleys then moved
out from the Depot in late August 2010.
However they still had various items of property on the site.
On 26 August 2010, following
a meeting, Mr Daisley emailed
Mr Keller confirming that the house would be cleaned out by the weekend. He
asked for three to four
weeks with no charge to remove “all our gear from
the
yard”.
The
removal of the office buildings
- [51] On
1 September 2010 an event occurred which led to an irretrievable breakdown in
the relationship between the Daisleys and the
Kellers. The Daisleys arranged to
remove two office buildings from the Depot. The Daisleys say they believed they
had the right
to remove those buildings. The Kellers say the buildings formed
part of the land, and had been purchased by Ark.
- [52] Scott
Daisley, on behalf of his father, had sought legal advice from Mr Skeates about
whether the Daisleys could take these buildings
from the Depot. Privilege was
waived in respect of that correspondence. The answer given by Mr Skeates on the
afternoon of 1 September
2010 was:
If the sheds are on skids and not
attached to the land and have no building permits then I believe they are
chattels that belong to
your businesses or to [Mr Daisley] personally and do not
belong to Ark.
- [53] That same
evening, Scott Daisley, with some assistance, removed the two buildings from the
Depot by loading them onto transporters.
Mr Keller was not present. He had not
been warned in advance that this would happen. He learned of it overnight. He
returned
to the Depot the following day. He went to the Whangārei police
station. On returning to the Depot, he found Scott Daisley
in the process of
lifting another shed onto a truck. Mr Keller phoned the police and Mr Badham,
who came to the site. The police
advised Scott Daisley that he could remove
items from the yard, but the sheds and container had to stay until the matter
was sorted.
Mr Keller’s evidence, which the Judge accepted, was that
he told Scott Daisley that he had until Sunday, 5 September 2010
to remove his
things from the site.
- [54] Mr Keller
soon located the offices removed from the Depot. The larger
“front office” was located in Ngāruawāhia,
where Mr
Daisley was setting up new business premises. It appears that Mr Daisley was at
the Ngāruawāhia site, awaiting
the arrival of the building, at the
time when it was removed from the Depot.
- [55] The smaller
“back office” was located in the yard of Tracta Tranz Ltd, an
equipment hire business.
- [56] The
Kellers’ lawyers wrote to the Daisleys’ lawyers about the taking of
the offices. An exchange of correspondence
followed. Mr Badham pointed out
that the valuation of the Depot had included an amount in respect of the two
office buildings that
had been removed — so the price Ark had paid Mr
Daisley included an amount in respect of those buildings. In a letter dated
21
September 2010, Mr Skeates wrote:
Our client was actually totally
surprised to find that [the two offices] were included in the valuation. On a
completely without prejudice
basis our client is prepared to recognise that
because the valuer had included them in his calculation of the price of that
property,
then our client recognises that your client believed that Ark had
purchased them. Rather than trying to rely on various aspects of
mistake under
the Contractual Mistakes Act our client is prepared to acknowledge that 3/4 of
the value of the items may be deducted
from the value for the purposes of
calculating our client’s shareholding interest.
- [57] The
Daisleys’ actions in removing the offices marked a point of no return for
the parties’ relationship. The locks
on the gates were changed, to
prevent the Daisleys continuing to access the Depot. On 7 September 2010, with
the encouragement and
assistance of the liquidators of Daisley Contracting Ltd,
Ark issued a trespass notice to the Daisleys.
The
Daisleys’ chattels left at the Depot
- [58] A
number of items of property remained at the Depot at this time.
The Daisleys say that Ark and the Kellers converted these
chattels. This
topic is discussed in more detail below.
Subsequent
events
- [59] An
attempt to resolve all of these issues was made in September and
October 2010. But no resolution was reached.
- [60] Shares in
Ark were never issued to Mr Daisley. Mr Daisley has had no involvement in
running Ark. The Kellers have continued
to operate Ark. Three of the four
properties have been sold. Ark retains one of the properties.
Proceedings
are issued
- [61] In
November 2015 the Daisley interests issued proceedings
(the main proceedings) against Ark, the Kellers and Thompson Wilson
Law (the Kellers’ lawyers). The timing seems likely to have been
influenced by the imminent expiry of the six-year limitation
period for certain
types of claim.
- [62] That in
turn led to the issue of two further sets of proceedings. Ark brought
proceedings against Mr Daisley, Action Fencing
and HPL Distribution in relation
to the removal of the two offices, unpaid rent for the Depot, and various debts
which Ark had paid
on behalf of the Daisley interests (the Depot proceedings).
And Mr Daisley, HPL Distribution and Action Fencing brought proceedings
against Ark and the Kellers claiming that they had converted the various items
of property left at the Depot in September 2010 (the
chattel conversion
proceedings).
The main
proceedings
- [63] The
Kellers argue on appeal that the Judge erred by awarding equitable
compensation/damages for claims that were not pleaded.
It is therefore
necessary to review in some detail the pleadings in the main proceedings.
The
pleaded claims
- [64] The
plaintiffs in the main proceedings were Mr Daisley and SDD, the vendors of the
land purchased by Ark. They pleaded five
causes of action.
- [65] The first
cause of action alleged that the Ark agreement was entered into under duress or
undue influence. Mr Daisley sought
an order that the Ark agreement be avoided,
and that he receive compensation including return of his initial equity in the
land and
a “refund” of the 25 per cent discount from the property
valuations in the Finance Proposal. He also sought compensation
for increases
in the value of the land, and an accounting of profits, since entry into the
transaction.
- [66] The second
cause of action was a claim by Mr Daisley for breach of the Ark agreement
as amended by the January 2010 agreement.
He alleged that the
Ark agreement (as amended) had been breached by the Kellers when they
purported to avoid the January 2010 agreement
on the grounds of duress. He
claimed that the Kellers’ breach of the Ark agreement had caused him loss,
but did not give any
particulars of that loss. He sought the same relief as in
the first cause of action.
- [67] The third
cause of action was based on an alleged constructive trust.
Both plaintiffs pleaded that the Kellers had repudiated
the terms of the
Ark agreement, and the “joint venture” had failed. The Kellers had
asserted “unconditional rights
to the land”, including selling some
of the land and transferring other land to a family trust associated with the
Keller family
(the Keller Family Trust). The plaintiffs sought imposition of
a constructive trust requiring Ark and the Kellers to disgorge any
benefit
they derived from their dealings with the land, account for the current market
value of the properties, and reconvey to Mr
Daisley the land which had been
conveyed to the Kellers’ family trust.
- [68] The fourth
cause of action, alleging breach of fiduciary duty, was pursued by Mr Daisley
against the Kellers alone. The allegation
was that the parties’
relationship under “the JV Agreement” — a defined term
used in the pleadings to refer
to the arrangements entered into orally in
November and early December 2009 — was characterised by trust, reliance
and confidence,
which gave rise to fiduciary duties of loyalty and good faith.
They alleged that the Kellers breached their fiduciary duties to
Mr Daisley by
placing themselves “in conflict of interest”. The particulars
given of those breaches of duty were as
follows:
44.1. misleading
[Mr Daisley] by indicating that they were prepared to re‑negotiate the JV
Contract as to contentious issues;
44.2. misleading [Mr Daisley] that they agreed to proposals to settle issues
of contention arising out of the draft shareholder agreement;
44.3. agreeing to [Thomson Wilson Law] presenting to [Mr Daisley] the take
it or leave it JV Contract which was materially different
to the
JV Agreement, whereby the differences materially improved the
[Kellers’] position at the expense of [Mr Daisley’s]
interest in the
JV;
44.4. being party to duress and or undue influence to coerce [Mr Daisley] to
sign the JV Contract
- [69] Mr Daisley
pleaded that the Kellers’ breach of fiduciary duties had caused him loss.
The relief sought was essentially
the same as the relief sought in the first and
second causes of action.
- [70] The fifth
cause of action was brought against Thompson Wilson Law, Mr Badham’s
firm, alleging breach of a fiduciary duty
owed to Mr
Daisley.
The
pleaded defences and counterclaims
- [71] Ark
and the Kellers denied that they owed any fiduciary obligations to the Daisley
interests. They pleaded that the Daisleys
were, and remain, entitled to be
issued shares in Ark once the contractual pre-conditions to issuing those shares
have been satisfied.
They pleaded that those conditions had never been
satisfied as a result of the Daisleys’ various defaults. They denied the
Daisleys were induced to enter into the Ark agreement by duress or undue
influence. They say that in any event the Ark agreement
was affirmed by
the Daisleys.
- [72] The Kellers
in turn claimed that they were induced to enter into the January 2010
agreement by duress, and had lawfully avoided
those variations to the
Ark agreement. They pleaded that the Daisleys’ entitlement to a
shareholding in Ark should be determined
by reference to the Ark agreement
as it stood before the January 2010 agreement.
- [73] The Kellers
also pleaded a limitation defence in relation to aspects of the claim.
- [74] Thompson
Wilson Law denied that there was ever any solicitor/client relationship between
them and the Daisley interests. They
only ever acted for the Kellers, and
subsequently Ark. They did not owe any fiduciary duties to the Daisley
interests.
High
Court judgment in main proceedings
- [75] The
main proceedings were heard by Walker J over two weeks in
September 2019.[9]
- [76] The claim
brought by the Daisley interests underwent a number of shifts in direction at
trial. The Kellers say this resulted
in the proceeding going off track, and
relief being awarded against them that had not been properly pleaded, which they
did not have
a fair opportunity to address at trial. Because of the importance
of the issue, we set out the Judge’s description of this
“change in
course”:
[21] Ms Smith, who inherited the case after the
filing of the second amended statement of claim, opened the case for the
plaintiffs
on a different basis. There was no application to amend the
pleadings. She submitted that the asserted cancellation of the “joint
venture agreement” by the Kellers in February 2010 amounted to:
(a) a breach of the “joint venture agreement” resulting in an
entitlement to compensation for the loss of the initial
investment and loss of
rights that would have been enjoyed as a result; or
(b) a complete rescission of the transaction, resulting in a right of the
parties to be restored to their pre-contractual position;
or
(c) a unilateral waiver by the defendants of the requirement for
a collateral agreement to issue shares in settlement of the debt,
resulting
in an obligation to settle the debt recorded in the sale and purchase agreements
on commercially reasonable terms.
[22] Ms Smith also recast the constructive trust claim. The property
transferred to the Kellers’ family trust was no longer
the focus of the
constructive trust claim. Rather, she submitted that all the rights, title and
benefits which ought to have flowed
to the plaintiffs under the Ark Agreement
are held on constructive trust by Ark. This includes all dividends, income,
interest or
distributions and the loss of the contractual option to acquire the
Depot from Ark. In this context, Ms Smith expressly disavowed
any constructive
trust in respect of the shareholding entitlement, on the basis that there could
not be a constructive trust in respect
of non-existent property.
[23] By closing, there was a further evolution in the plaintiffs’ case.
The plaintiffs elected compensatory relief rather than
an accounting.
More materially, the plaintiffs now allege that Ark breached its
obligations under the Ark Agreement by failing to
issue the shares, failing to
adopt a company constitution and by using the plaintiff’s
contribution to Ark “to balance
the equity position of Ark without
issuing shares”. This was to reshape the breach of contract cause of
action which faced
vigorous opposition.
[24] In summary, the relief claimed by the end of the case is:
(a) An order that the commercial arrangements be set aside;
(b) Damages of $541,721 (representing the equity in the properties
transferred or ‘vendors’ advance’) plus a contractual
rate of interest;
(c) An institutional constructive trust over Ark property to the extent of
the Daisley interests;
(d) Damages for loss of opportunity.
[25] The shifts in approach are unsurprising. Ark’s asset position
today is markedly different. Only one of the properties transferred
by the
plaintiffs is still owned by Ark. Mr Daisley’s preferred remedy does not
necessarily lend itself easily to established
causes of action. He has no
interest in a shareholding in Ark. Instead he is looking for financial
compensation, effectively in lieu
of his shareholding entitlement.
[26] Mr [Browne] objected to the plaintiffs straying from the pleaded case.
He submitted that the defendants’ case should not
be prejudiced by
allowing the plaintiffs to take advantage of deficiencies or generalities in
their own pleadings to justify arguing
points not specifically pleaded.
[27] Mr [Browne’s] point is valid. Where the basis for the relief
sought, or the precise manner in which it is alleged that
contractual breaches
have occurred, is recast, careful assessment and comparison against the pleaded
case is necessary to ensure
the interests of justice are met. I return to this
point later in my judgment.
(Footnotes omitted.)
- [77] The Judge
identified six issues which the Court needed to determine.
- [78] Issue one
was whether Ark and the Kellers had legitimately avoided the January 2010
agreement on the basis of duress. The Judge
found that there had been no
duress.[10] A binding shareholders
agreement was entered into by the parties as at 29 January 2010, recorded
in the following
documents:[11]
(a) the
draft shareholders agreement sent by Mr Badham to Mr Skeates on 15 January
2010;
(b) the letter of 22 January 2010 from Mr Skeates to Mr Badham;
(c) the letter of 25 January 2010 from Mr Badham to Mr Skeates;
(d) the letter of 28 January 2010 from Mr Skeates to Mr Badham; and
(e) the letter of 29 January 2010 from Mr Badham to Mr Skeates.
- [79] Issue two
was whether the Ark agreement itself was liable to be avoided by the Daisleys
for duress or undue influence. The Daisleys’
position at trial was that
if issue one was determined in their favour, it was not necessary to deal with
issue two. They did not
seek to set aside the Ark agreement, provided it
had been modified by the January 2010 agreement. So the Judge did not need to
decide
this issue. However she observed that if she had been required to do so,
she would have found that the Daisleys were not induced
to enter into the
Ark agreement by duress or undue influence. And in any event, they had
affirmed the Ark agreement so could no
longer seek to avoid
it.[12]
- [80] Issue three
was whether a constructive trust should be imposed. The Judge found that there
was no basis for imposition of any
form of constructive trust in relation to the
properties transferred to
Ark.[13]
- [81] Issue four
was whether Thompson Wilson Law had breached any fiduciary obligations owed to
the Daisley interests. The Judge found
that Thompson Wilson Law never acted for
the Daisleys, and did not owe them any relevant obligations. The claim
against Thompson
Wilson Law was
dismissed.[14]
- [82] Issue five
was whether the Kellers breached any fiduciary obligations to the plaintiffs.
The Judge did not accept that the Kellers
had the particularised fiduciary
duties in the period up to and including 2 December
2009.[15] That was sufficient to
dispose of the allegations that fiduciary duties had been breached by the
Kellers in connection with the
take it or leave it offer made on 2 December
2009, entry into the Ark agreement in December 2009, and the renegotiations in
January
2010.
- [83] However the
Judge considered that on execution of the Ark agreement the relationship between
the parties changed fundamentally.
It was arguable that once the Daisleys were
contractually bound to transfer properties as their contribution to the joint
venture,
and once the property settlements had taken place, the Kellers had
equitable or fiduciary obligations until issue of the contractually
promised
shareholding.[16] The Judge
considered that four factors supported this
conclusion:[17]
(a) Mr
Daisley and SDD were particularly vulnerable before any issue of shares because
of the imbalance of power through their lack
of participation in Ark.
(b) The nature of the Ark agreement required the Daisley interests to repose
trust in the Kellers. The Kellers had an absolute discretion
to determine which
of the specific provisions stipulated in the Ark agreement would be
provided for in the shareholder agreement,
which “compounded the
imbalance”.
(c) Once the properties were transferred, the relationship had advanced to
the implementation stage of the venture. There was a common
purpose and goal to
develop the properties for joint profit.
(d) The venture was one in which both were intended to participate, despite
the evidence that the Daisleys’ participation was
in fact fleeting.
“While characterising the venture as a ‘joint venture’ is not
determinative of the question
of whether fiduciary obligations are owed, it
informs the analysis”.
- [84] The Judge
summarised her view on the fiduciary nature of the obligation as
follows:
[222] Once matters were agreed as at 29 January 2010, the
obligation on the Kellers was to issue shares to the Daisley interests
reflecting
their proportionate contribution to assets in Ark. Once issued, the
obligations of each shareholder to the other would have been
of a different
character. Until that point, in my judgment, the relationship was a
fiduciary one. The Kellers were in an analogous
position to Mr Fay in
Chirnside notwithstanding they considered they had a legitimate reason to
withhold the issue of shares. The result of not issuing shares was
a de facto
appropriation of the venture.
[223] The fiduciary obligations each owed to the other party once the venture
had commenced after 29 January 2010 included duties
of loyalty and a duty of
good faith. ...
[224] I also consider that each party had obligations to the other to act
equitably to bring the affairs of the joint venture to a
conclusion in a way
fair to all parties once the point of no return was reached.
[225] I am not in a position to apportion responsibility for the failure of
the parties to settle their claims in September/October
2010. I suspect that
both were worn down by the vicissitudes of the ongoing dispute. However, in my
assessment, the Kellers’
failure to issue shares to the Daisley interests
by 29 January 2010 was a breach of fiduciary duty. While there were ongoing
disputes
and it might be said that neither party negotiated in good faith, the
Kellers were not entitled to avoid their obligation to issue
shares. The
allegation of duress and the conjoining of the dispute over rent with the
shareholder issues operated as a form of “in
terrorem” strategy and
a breach of the duty of good faith.
(Footnote omitted.)
- [85] Thus the
Judge found for Mr Daisley in respect of this cause of action.
She considered that her analysis of the nature of the
fiduciary obligation
“amounts to a development of the second particular pleaded in this cause
of action and thus has a pleaded
basis”.[18] We return to this
below.
- [86] The Judge
recorded that Mr Daisley had “elected compensation rather than an account
of profit for practical
reasons”.[19] She awarded
damages of $541,721 as equitable compensation against the Kellers and Ark. The
Judge considered that this was the value
of Mr Daisley’s contribution of
equity to the venture, which had been retained by Ark and thereby enriched the
Kellers without
benefit to Mr Daisley. The measure of Mr Daisley’s
loss “equates to disgorgement of the benefit to [Ark and the
Kellers]”.[20]
- [87] Issue six
was whether Ark and/or the Kellers were in breach of contract. The only
pleaded breach of contract was the Kellers’
purported voiding of the
January 2010 agreement. The Judge held that this was not a breach. It may
have been a repudiation. But
the Daisleys did not accept that repudiation.
So the only pleaded breach of contract was not made
out.[21]
- [88] However Ms
Smith, counsel for the Daisleys, submitted on closing that the failure to issue
shares on the basis of the position
as at 29 January 2010 amounted to an ongoing
breach of the Ark agreement. The Judge agreed. She said:
[234] I
agree. I note that there was no application to amend the pleading to incorporate
this breach. [Ark and the Kellers] with some
justification, resist this
recasting of the breach of contract cause of action. In the alternative,
they maintain that [Mr Daisley]
has failed to prove any loss. They remain
entitled to the shareholding for which they contracted, being a minority
shareholding in
Ark. There have been no dividends paid by Ark to shareholders
and there is no evidence of any diminution in value of the company
by virtue of
the management decisions that the Kellers have made.
[235] In the ordinary course, I would be reluctant to permit such a shift in
the case to the extent implicitly sought. However, in
the unusual circumstances
of this case, I do not accept that there is any material prejudice to the
defendants by permitting this
approach to the breach of contract cause of
action. It is obvious that, once the claim to duress does not succeed, the
failure to
issue shares to the Daisley interests amounts to unjustified
non‑performance of contractual obligations. This view does not
depend on
new and different facts but rather, a different legal characterisation as to the
effect of my finding that the Kellers
were not induced to enter into the January
2010 Variations by duress.
(Footnote omitted.)
- [89] The Judge
found that the failure to perform the promise to issue shares had caused loss to
Mr Daisley. She did not consider
that an ongoing entitlement to
a shareholding in Ark still represented the bargain he entered into. Mr
Daisley sought return of
the “failed consideration” for entry into
the joint venture on the basis he had never received the benefit contracted
for,
and that benefit is no longer available to him. The Judge saw this as
equivalent to his equity contribution on settlement of
the property transactions
of $541,721.[22]
- [90] The Judge
considered that another way to look at this was to examine what Mr Daisley
would have been entitled to as at 29 January
2010 had the contract been
performed:[23]
The
answer is the shares representing the proportionate value of his contribution so
that the award of damages is thus the value of
those shares at that point in
time.
- [91] The Judge
considered that given her findings of breach of fiduciary obligation, it was
unnecessary to determine the question
of appropriate remedy for breach of
contract.[24]
- [92] At trial Mr
Daisley also sought interest on his equity contribution, effectively treating it
as a shareholder advance. The Judge
rejected this aspect of his claim for three
reasons. First, the Ark agreement did not contemplate payment of contractual
interest
for initial shareholder contributions. Second, a contractual rate of
interest was not pleaded. Nor was a claim to statutory interest.
The High
Court Rules 2016 require a statement of claim to state specifically the
basis of any claim for interest, and the rate at
which interest was claimed.
That had not been done. Third, the way in which the contributions were treated
in the Ark financial
statements (as shareholder advances) was presentational
only, and did not provide a basis for a substantive claim to
interest.[25] The Judge concluded
that “there is no entitlement to an award [of] interest on damages, there
being no claim to interest in
the prayer for
relief”.[26]
- [93] The Judge
summarised the result of the various claims advanced in the
main proceedings as follows:
[242] In summary, I:
(a) dismiss the claim of duress against all defendants (first cause of
action).
(b) award damages to [Mr Daisley] against [Ark and the Kellers] jointly and
severally for breach of contract (second cause of action).
(c) dismiss the claim for a constructive trust (third cause of action).
(d) award equitable compensation to [Mr Daisley] against the [Kellers] for
breach of fiduciary duty (fourth cause of action).
(e) dismiss the claim against [Thomson Wilson Law] (fifth cause of
action).
[243] I award damages/equitable compensation to [Mr Daisley] of $541,721 in
total. I make no award of interest as interest has not
been pleaded.
Appeal in relation
to main proceedings
- [94] We
begin by considering the appeal and cross-appeal from the judgment in the main
proceedings, before describing in more detail
the judgments in the two other
proceedings and addressing the appeals from those judgments.
- [95] The key
issues raised by the appeal and cross-appeal are:
(a) Was it open to
the Judge to award compensation for failure to issue shares in Ark?
(b) Did the Judge err in awarding relief for breach of contract and breach of
fiduciary duty, if those claims were properly pleaded?
(c) Should the Judge have awarded interest on the equitable
compensation/damages?
Issue 1: Was it open
to the Judge to award compensation for failure to issue shares in Ark?
The issue
- [96] In
the main proceedings, Mr Daisley succeeded in a claim against the Kellers
and Ark for failure to issue shares in Ark. The
Judge held that this amounted
to a breach of fiduciary duty, and a breach of contract. The Kellers say
that these claims were not
properly before the Court. They were not pleaded.
They were not raised until Ms Smith’s closing submissions. They had no
opportunity to respond to them by calling relevant fact and expert evidence, and
advancing submissions on the issues raised by those
claims.
- [97] Mr Browne,
counsel for the Kellers, emphasises that the Judge accepted that these claims
were not squarely raised on the pleadings,
and recorded that they were only
advanced in closing. No application to amend the pleadings to add these claims
was made at any
stage.
- [98] Mr Browne
submits that in these circumstances, claims for failure to issue the shares in
Ark were not properly before the Court.
And as a result, the hearing was
procedurally unfair. Because he closed first, with Ms Smith closing after him,
the only opportunity
he might have had to respond to these claims would have
been in a reply. But the hearing had already run over time, and the Judge
made
it clear that a reply would not be welcome. In any event, he says, the more
fundamental problem is that key issues relevant
to these claims were not
addressed in evidence, or in argument by either party.
- [99] In
particular, Mr Browne says that if these claims had been properly pleaded, the
Kellers would have defended them on the basis
that the Ark agreement and the
shareholders agreement only required shares to be issued to Mr Daisley once
certain pre-conditions
had been met. Those pre-conditions, in particular the
completion of a signed shareholders’ agreement, had never been
satisfied.
So the obligation to issue shares had not yet fallen due. The
Kellers have always acknowledged that when the pre-conditions were
met, shares
in Ark would need to be issued.
- [100] Mr Browne
also points to the absence of any pleading in relation to the loss claimed to
have been caused by the non-issue of
the shares. If there had been an
obligation to issue the shares on a particular date, and if there had been a
wrongful failure to
do so, then the appropriate measure of loss would presumably
be the value of the shares as at that date. But as a claim of this
kind was not
pleaded, the Keller interests had not had the opportunity to call evidence and
make submissions in relation to the value
of Ark, and thus of the promised
shareholding in Ark.
- [101] Mr Browne
also submits that the relief awarded — return of an amount representing
the Daisley interests’ initial
equity contribution to Ark — could
only be awarded for breach of contract if the contract had been cancelled. But
it was not
pleaded that the contract had been cancelled. The question of
cancellation was not addressed by the Judge, which was unsurprising
in
circumstances where it was not squarely before the Court. Nor did the Judge
engage with the availability of this measure of damages
in the absence of
cancellation. Again, that was unsurprising in circumstances where Mr Browne had
not had an opportunity to make
submissions on this issue. The result of the
significant change in the way the claim was presented in closing was that
critical
issues were not the subject of submissions, and were not addressed in
the judgment.
- [102] Mr Browne
also says that if an application had been made to amend the pleadings at trial
to allege a failure to issue shares
in Ark in April 2010, that application could
have been successfully opposed on limitation grounds. A pleading cannot be
amended
to add a time-barred claim. But because no formal application was made
to amend the pleadings, there had been no opportunity to
raise that issue.
- [103] Ms Smith
says that the failure to issue shares was adequately pleaded. Paragraph 26 of
the second amended statement of claim,
which was located in the background
section relevant to all causes of action, read as follows:
Following
[Ark and the Kellers] voiding the JV Contract, [Ark and the Kellers] have
retained for themselves all of the benefits of
the JV, in particular [Mr
Daisley’s] equity in the land conveyed to [Ark], and they have not issued
or caused to be issued
to [Mr Daisley] any shares in Ark; nor have they
accounted to [Mr Daisley] any dividend from Ark, howsoever earned.
- [104] Ms Smith
also pointed out that the fact that shares had not been issued to
Mr Daisley was not disputed. Although the statement
of defence denied para
26 of the claim, it went on to say:
They accept that the plaintiffs
are entitled to a shareholding in [Ark] based on the formula set out in the 2
December 2009 agreement
but the plaintiffs have not attempted to reach agreement
with the [Kellers] as to quantifying that nor met the pre-conditions to
the
issue of shares.
- [105] Ms Smith
submitted that the claims for failure to issue the shares were implicit in the
breach of contract and breach of fiduciary
duty causes of action, in light of
para 26 of the second amended statement of
claim.
Discussion
- [106] We
accept Mr Browne’s submission that no claim for failure to issue shares in
Ark was pleaded, whether as a breach of
contract or as a breach of fiduciary
duty.
- [107] The
contract cause of action pleaded only one breach: the purported
“voiding” of the agreement entered into by correspondence
in January
2010:
- On
11 February [2010], the defendants purported to void the “agreement”
made on 28 January 2010, on the grounds of duress.
- The
defendants voiding of their agreement given on 28 January 2010
was:
34.1. A breach of the terms of the JV Contract as
varied by the agreements of 23 December 2009 and 28 January 2010; and/or
34.2. The completion of an unconscionable ruse to trick the plaintiffs into
believing that the defendant was willing to agree variations
to the contract,
when the defendants had no intention of creating new legal obligations over and
above those contained in the JV
Agreement.
- [108] Ms Smith
is right to say that it was alleged — and was common ground — that
shares in Ark had not been issued.
But nowhere was it alleged that this was a
breach of contract. There is no reference to the failure to issue shares in the
second
cause of action alleging breach of contract. The pleaded breach cannot
be read as extending to the non-issue of shares in Ark.
The date on which the
shares should have been issued is not pleaded. There is no pleading of the loss
caused by any such breach.
- [109] Nor is it
pleaded that any relevant contract was cancelled. At the hearing we asked Ms
Smith whether the Daisleys claimed that
the Ark agreement had been cancelled.
She confirmed that the Daisleys considered that the contract was still on foot
— hence
her response to the Kellers’ limitation argument that this
was a continuing obligation. As we explain below, this suggests
that Mr
Daisley is still entitled to the Ark shares, and any claim would be confined to
loss caused by delay in issuing the shares.
But the pleading is silent on all
of this.
- [110] Similarly,
nothing in the fourth cause of action for breach of fiduciary duty identifies
the non-issue of shares in Ark as a
breach of a fiduciary duty owed to
Mr Daisley. The sole allegation of breach read as follows:
- The
[Kellers] breached their fiduciary duties to [Mr Daisley] when they placed
themselves in conflict of interest:
Particulars
44.1. misleading [Mr Daisley] by indicating that they were prepared to
re-negotiate the JV Contract as to contentious issues;
44.2. misleading [Mr Daisley] that they agreed to proposals to settle issues
of contention arising out of the draft sharehol[d]er
agreement;
44.3. agreeing to [Thomson Wilson Law] presenting to [Mr Daisley] the
take it or leave it JV Contract which was materially different
to the JV
Agreement, whereby the differences materially improved the [Kellars’]
position at the expense of [Mr Daisley’s]
interest in the JV;
44.4. being party to duress and or undue influence to coerce
[Mr Daisley] to sign the JV Contract
- [111] Ms Smith
submits that an allegation of breach by failing to issue shares was implicit in
para 44.2. The Judge described the
allegation as an “extension” of
this particular.[27] However this
particular must be read in context. It is clear that the complaint of
“conflict of interest” in para 44
relates to the “take it or
leave it” contract presented on 2 December 2009, and a complaint that Mr
Daisley was misled
by the suggestion that the Kellers were willing to
renegotiate that contract in January 2010. The purpose of a pleading is to show
the general nature of the plaintiff’s claim to the relief sought, and to
give sufficient particulars to “inform the court
and the party or parties
against whom relief is sought of the plaintiff’s cause of
action”.[28] A defendant
reading para 44 of the second amended statement of claim could not be expected
to discern from it that the complaint
was that shares had not been issued in
Ark, and that relief was sought for loss caused by the failure to issue those
shares. We
do not consider that this paragraph can reasonably be read as
pleading a claim that Mr Keller and Ark had breached fiduciary duties
owed to Mr
Daisley by failing to issue shares in Ark.
- [112] Pleadings
are essential for the fair trial of a claim. A defendant is entitled to know
what claims are being made against them,
and a plaintiff is entitled to know
what defences they have to meet. “If the parties do not know, unnecessary
evidence may
be got together and led or, even worse, necessary evidence may not
be led.”[29] That is what
happened in the present case. Issues relevant to a claim for breach of contract
or breach of fiduciary duty in failing
to issue shares in Ark were not addressed
in evidence, or submissions. Those issues include, as Mr Browne rightly
submits, whether
any relevant pre-conditions to the issue of shares had been
satisfied, the date on which the obligation to issue the shares arose,
whether
the Ark agreement had been cancelled, and the value of the promised interest in
Ark as at the date of any breach.
- [113] If Ms
Smith wished to advance such an argument despite it not being pleaded, it was
insufficient simply to refer to it in closing
submissions. A formal application
to amend the pleadings was required. The importance of a formal application to
amend, where a
materially different claim is pursued, was emphasised recently by
this Court in Yan v Mainzeal Property and Construction Ltd (in
liq).[30] Pleadings play
a fundamental role in defining the parameters of a trial. The parties are
entitled to prepare for a trial on the
basis that the pleadings identify the
facts in issue and the nature and scope of the case that the plaintiff will
present and the
defendant must meet. As this Court said:
[31]
For good reason, after
the close of pleadings any amendment requires the leave of the court.
It is not open to a plaintiff to present
a case beyond the scope of
pleadings at trial without seeking leave to amend. The process of seeking leave
to amend serves two purposes:
(a) It identifies the additional facts and issues raised by the new argument
that the plaintiff wishes to present, and that must be
established by the
plaintiff if they are to succeed. If there is a change of course part way
through a trial, the defendant is entitled
to have that new course mapped with
the same clarity that is required in advance of trial.
(b) The application for leave requires the parties, and the court, to engage
squarely with the question whether the new departure
can fairly be accommodated.
In some cases, where the change in approach is essentially a matter of law that
raises no new questions
of fact, the trial will be able to continue with little
or no interruption. In some cases, fairness will require that the defendant
have an opportunity to consider the new argument and prepare evidence —
fact and/or expert — to respond to the modified
case they now need to
meet. They may also need to carry out further research and analysis in relation
to legal aspects of the modified
claim. An adjournment may be needed to give
the defendant a fair opportunity to understand, and respond to, the modified
claim.
In some cases, the only way to provide that fair opportunity will
be by re-starting the trial after such an adjournment. And in
some cases,
especially where a trial is well advanced, the burden on the defendants of
having to re-frame their defence and prepare
for a resumed trial (or fresh
trial) many months down the track will be so great that amendment should not be
permitted. It is important
that these issues be squarely confronted where a
plaintiff wishes to change tack in a material way.
- [114] In this
case, it is difficult to see how a formal application to amend the pleadings to
add this claim, made in the course of
the plaintiffs’ closing, could have
been allowed. If an amended pleading which set out the facts relevant to such a
claim
had been prepared by the plaintiffs, and provided to the Court, it would
have been immediately apparent that the defendants needed
to have an opportunity
to plead in response to it. Additional issues of fact would have been
identified which had not been addressed
in the course of the trial. The parties
would have needed time to prepare, and exchange, expert evidence on valuation of
Ark at
one or more relevant dates. And the percentage shareholding to which Mr
Daisley was entitled, in accordance with Schedule A to the
shareholders’
agreement, needed to be addressed in evidence. It would not be possible to
calculate the value of the shares
to which Mr Daisley was entitled without
knowing the result of this calculation.
- [115] At the
very least, an adjournment and a further hearing would have been needed. And
there would have been a strong argument
that it would be unfair to the
defendants to be expected to engage with the new arguments, and prepare for
a resumed trial some time
down the track, rather than having the claims
against them determined.
- [116] Depending
on the shape the pleaded claim took, there might also have been limitation
issues that would need to be determined
before leave could be given to make the
proposed amendment.
- [117] We
consider that the claims that the Judge upheld were not properly before the
Court on the pleadings as they stood. Permitting
the claims to be expanded
informally, in the course of the plaintiffs’ closing, resulted in
significant procedural unfairness
to the defendants. They were deprived of any
opportunity to argue that the necessary amendments to the pleadings should not
be made,
and of any opportunity to respond to the reframed claims with relevant
fact evidence, expert opinion evidence, and submissions.
- [118] Ms Smith
submits that there was no real prejudice to the Kellers and Ark as a result
of the approach adopted by the Judge.
As she points out, that was the view
taken by the
Judge:[32]
[235] In the
ordinary course, I would be reluctant to permit such a shift in the case to the
extent implicitly sought. However, in
the unusual circumstances of this case, I
do not accept that there is any material prejudice to the defendants by
permitting this
approach to the breach of contract cause of action. It is
obvious that, once the claim to duress does not succeed, the failure to
issue
shares to the Daisley interests amounts to unjustified non‑performance of
contractual obligations. This view does not
depend on new and different facts
but rather, a different legal characterisation as to the effect of my finding
that the Kellers
were not induced to enter into the January 2010
[agreement] by duress.
- [119] We take a
different view. For the reasons explained above, we consider that the claims in
contract and for breach of fiduciary
duty in relation to non-issue of shares do
depend on new and different facts. This is not merely a different legal
characterisation
of the finding that the Kellers were not induced to enter into
the January 2010 agreement by duress. The question of pre-conditions
to the
issue of shares needed to be pleaded and considered. And, critically, the
question of loss raised a number of factual issues
that the Court did not have
sufficient evidence to determine. The limitation issues also — depending
on the way in which the
revised claim was framed — may have required
evidence about additional facts.
- [120] In these
circumstances, the appeal by the Kellers and Ark must be
allowed.
Issue
2: Merits of claims for breach of contract/fiduciary duty
The issues
- [121] Mr
Browne submits that even if the claims for breach of contract and breach of
fiduciary duty in respect of the non-issue of
shares in Ark were properly
pleaded, they should have failed. There was no fiduciary duty to issue shares.
There was no breach
of the contractual obligation to issue shares. And it was
not open to the Judge to award equitable compensation/damages for such
breaches
by reference to the original contribution of Mr Daisley to Ark.
Discussion
- [122] The
Judge did not refer to the provisions of the Ark agreement and shareholders
agreement governing the issue of shares in Ark.
Clause 3 of the
Ark agreement (set out at [29] above) provided for various steps to
be taken before shares in Ark were issued to Mr Daisley and SDD. In particular,
it provided
for a shareholders’ agreement to be signed by all of the
shareholders of Ark at the time of the issue of shares to SDD and
Mr Daisley.
- [123] The
January 2010 agreement established the terms of the shareholders agreement
between the parties. But no agreement recording
those terms was prepared in
final form, and signed by the parties.
- [124] Clause 5.1
of the shareholders agreement recorded that the initial capital and funding of
the company would be as set out in
Schedule A. Schedule A provided for
determination of the respective financial contributions of the Kellers and Mr
Daisley to the
acquisition of the properties by
Ark.[33] The way in which that
would be calculated was set out in some detail. The agreement provided for
amendment of Ark’s constitution
to create A shares to be held by the
Kellers, and B shares to be held by Mr Daisley. Clause 9 of the Schedule
then provided that
the Kellers and Mr Daisley would give written notice to
Ark’s solicitors nominating their nominee(s) to hold their respective
share entitlements. “Before the nominees receive their respective share
entitlements, such nominees shall sign a Deed of Accession
to this Shareholders
Agreement in accordance with Schedule B.”
- [125] Plainly
there are steps that should have been taken by the Kellers under the agreement,
such as calculation of the financial
contributions and, thus, shareholding
percentages in Ark. As Mr Browne accepted in argument, the Kellers could not
rely on their
failure to take these steps to defend a claim for breach of an
obligation to issue the shares. But there is more force in the argument
that a
signed shareholders agreement was necessary, before the shares would be issued.
It would be inappropriate for us to determine
whether this pre-condition was
met, and whether responsibility for that state of affairs was borne, at least in
part, by Mr Daisley.
Because the issue was not pleaded, there was no evidence
directed to precisely that question. But the argument cannot be dismissed
out
of hand.
- [126] We also
accept Mr Browne’s submission that the relief awarded — in effect,
return of the nominal amount of Mr Daisley’s
equity contribution to Ark
— could not properly have been awarded for breach of contract in this
case.
- [127] We note
that it is not clear whether the Judge did award relief for breach of contract.
She said it was unnecessary to determine
the question of appropriate remedy for
breach of contract, given her findings of breach of fiduciary
obligation.[34] But she then went
on to award damages for breach of contract equal to the amount awarded for
breach of fiduciary duty.[35] We
proceed on the basis that she did make an award of damages for breach of
contract, and examine whether that award could be justified.
- [128] If a claim
had been brought for breach of an obligation to issue the shares, and breach was
made out, damages for that breach
of contract would fall to be assessed on an
expectation measure. That is, the damages would be the amount of money required
to put
Mr Daisley in the same position that he would have been in if the promise
had been performed.
- [129] Ms Smith
submitted that the breach occurred in April 2010: that was an essential step in
her argument that interest from April
2010 onwards should have been allowed on
the compensation/damages awarded on this claim. If that were right, then the
starting point
for assessing damages would be the value of Ark as at the date of
the relevant breach. Mr Daisley would be entitled to a percentage
of that
value, determined in accordance with the Ark agreement. But this approach
provides no support for the Judge’s award,
for two reasons.
- [130] First, a
claim advanced on this basis would have faced significant limitation issues.
A claim for damages in respect of a breach
in April 2010 could not be added
by amendment in 2019. It would be time-barred.
- [131] Second,
the amount awarded by the Judge was not based on an assessment of the value of
the Ark shares to which Mr Daisley was
(and remains) entitled. There was
no evidence before the Court about the value of Ark in
2010.[36] Nor was there any
evidence about the percentage of the company’s shares to which Mr Daisley
was entitled under the Ark agreement.
Ms Smith argued before us that the amount
awarded by the Judge did represent the value of the promised shareholding in
Ark. The
Judge appears to have taken this view:
[237] Another way
to look at this is to examine what Mr Daisley was entitled to as at 29 January
2010 had the contract been performed.
The answer is the shares representing the
proportionate value of his contribution so that the award of damages is thus the
value
of those shares at that point in time.
- [132] However
there is no necessary relationship between the nominal value of
Mr Daisley’s contribution to Ark in January 2010,
assessed in
accordance with the shareholders’ agreement, and his percentage
entitlement to the value of Ark as at that date.
Where a claim is brought for
failure to transfer shares, the damages awarded will depend on the value of
those shares on the date
on which the transfer should have taken place. That
value is often — indeed almost invariably — different from the
contract
price for the shares. It may be more, or less. But critically, this
is an issue that needs to be pleaded, and proved by relevant
evidence. In this
case, the statement of claim did not contain any allegation in relation to the
date of breach or the value of
the shares on that date. There was no evidence
on the issue before the Court. The Court was not in a position to decide
it.
- [133] Ms Smith
submitted that the loss to Mr Daisley would not be fairly represented by a
percentage entitlement to the value of Ark
today. He had also lost the
opportunity to be involved in the operation of the company as a director, and
the potential gains in
value from development of the properties. She submitted
that Ark would have been more valuable if Mr Daisley — who had
relevant
expertise — had not been excluded from its management.
- [134] A claim
for loss of opportunity to participate in the management of Ark, and to derive
profits that could have been made as
a result of that participation, would in
principle be available. But it would need to be pleaded, and established by
relevant evidence.
That did not occur.
- [135] A claim
might have been made for recovery of Mr Daisley’s initial equity
contribution following cancellation of the Ark
agreement, in the exercise of the
Court’s remedial discretion under s 43 of the Contract and Commercial
Law Act 2017. But
as noted above, Ms Smith disclaimed any submission that the
Ark agreement had been cancelled. So this approach also was not open.
- [136] In
summary, we cannot identify any proper basis on which an award could have been
made for breach of contract on the basis that
appears to have been adopted in
the High Court judgment.
- [137] We also
accept Mr Browne’s submission that the Court erred in finding that Mr
Keller and Ark owed a fiduciary duty to
Mr Daisley to issue shares in Ark, and
had breached that duty. We very much doubt that the relationship between the
Kellers and
Mr Daisley was a fiduciary relationship, in which the Kellers were
required to prefer the interests of Mr Daisley to their own interests.
The term
“joint venture” was used by the parties on occasion, in
correspondence and records of meetings. But this does
not of itself establish
that there was a fiduciary relationship between the parties. The term
“joint venture” can cover
many forms of arrangement, not all of
which give rise to fiduciary
obligations.[37] This point was
made by Blanchard J, delivering the judgment of the Supreme Court in
Paper Reclaim Ltd v Aotearoa International
Ltd:[38]
To style a
contractual relationship as a joint venture may be apt to distract. It is a
term to be applied with caution. When parties
have formed a contract the
correct approach is first to decide exactly what they have agreed upon. Only
then should the court consider
whether any particular aspect of their agreement
gives rise to a relationship which can properly be characterised as fiduciary,
imposing
an obligation of loyalty on one or both parties, which supplements the
express or implied contractual terms. It is not enough to
attract an obligation
of loyalty that one party may have given up more than the other in entering into
the contract or that the contract
may be more advantageous for one party than
for the other. Nor is a relationship fiduciary in nature merely because the
parties
may be depending upon one another to perform the contract in its terms.
That would be true of many commercial contracts which require
cooperation. A
fiduciary relationship will be found when one party is entitled to repose and
does repose trust and confidence in
the other. The existence of an agreement,
express or implied, to act on behalf of another and thus to put the interests of
the other
before one’s own is a frequent manifestation of a situation
in which fiduciary obligations are owed.
- [138] In this
case, the parties set out their mutual obligations in contracts which provided
for the issue of shares in Ark, and for
their continuing relationship as
shareholders in Ark. The “joint venture” that was contemplated was
a joint venture
to be conducted through a company. The shareholders
agreement entered into by the parties expressly provided that nothing in that
agreement constituted the shareholders “as partners, trustees or as agents
for each other”.
- [139] In
Amaltal Corp Ltd v Maruha Corp the Supreme
Court said:[39]
These
were commercial companies who had elected not to continue as partners and,
instead, to frame their relationship by internal
and external rules applicable
to a company, supplemented by a contract between them in their capacity as
shareholders. There is no
warrant then for imposing upon them generally
obligations not found in the company’s own constitution, in companies
legislation
or in the terms of the contract. As partners they would have owed
fiduciary duties to one another, but their relationship no longer
took that
unincorporated form. They had deliberately substituted the Companies Act regime
for that of the Partnership Act.
- [140] And even
if some aspects of the relationship between the Kellers and Mr Daisley had
been fiduciary, that would not mean that
the obligation to procure the issue of
shares in Ark was a fiduciary obligation. At the risk of stating the obvious,
not every obligation
owed by a fiduciary is itself a fiduciary
obligation.[40] The obligation
of the Kellers to procure the issue to Mr Daisley of an ascertainable number of
shares in Ark was prescribed in detail
in the shareholders agreement.
No discretion or power to affect Mr Daisley’s interests was
involved.[41] Mr Daisley was
dependent on the Kellers only in the sense that he depended on them to perform
their contractual obligation. Plainly
that is not enough to give rise to a
fiduciary duty.
- [141] In these
circumstances, the Kellers’ contractual obligation to Mr Daisley to
procure the issue of shares in Ark was not
(also) a fiduciary obligation.
- [142] Thus the
claim for breach of fiduciary duty in failing to issue shares in Ark would
necessarily have failed, even if it had
been properly
pleaded.
Issue
3: Mr Daisley’s claim for interest
- [143] Mr
Daisley’s cross-appeal seeks an award of interest from 30 April 2010 on
the amount of equitable compensation/damages
awarded by the High Court against
Ark and the Kellers, for failure to issue shares in Ark to Mr Daisley.
- [144] Because we
have allowed the appeal from that finding of the High Court, the question of
interest on the equitable compensation/damages
awarded does not arise. The
cross-appeal must fail. However we make a few observations on this claim.
- [145] First,
there was an irresolvable tension between Ms Smith’s argument that
interest should have been awarded from the date
of breach, which she identified
in argument as 24 April 2010, and her argument that the claim was not
time-barred because the obligation
to issue the shares was an ongoing one. If
the obligation to issue shares was ongoing, and continued in existence as at the
date
of trial, the appropriate relief would presumably be an order that the
shares now be issued. As already mentioned, there could also
be a claim
for any loss suffered as a result of delay in issuing the shares from April 2010
through to the date of trial. But we
struggle to see how it could be argued
that any loss suffered as a result of delay in issuing the shares from April
2010 through
to the date six years before the pleadings were amended to include
such a claim would not be time-barred. So at trial, any claim
would have been
restricted to loss suffered between 2013 and 2019. And as this analysis makes
clear, the award would not be an award
of interest on compensation that became
payable in 2010: it would have been a different type of claim altogether.
- [146] Second, we
have some difficulty with Ms Smith’s argument that an obligation to
transfer shares that fell due on 24 April
2010 could be characterised as a
continuing obligation. If an orthodox claim had been brought for failure to
issue or transfer shares
on that date, by reference to the value of the shares
on that date, that claim would have become time-barred six years after that
date. The fact that the breach had not been remedied after the due date would
not mean that the obligation could be described as
a continuing obligation, and
would not prevent time running from the due date. Such a claim could
not have been added by amendment
in 2019.
- [147] Similarly,
if the argument had been that the Ark agreement was cancelled as a result
of a serious breach by the Kellers, and
relief was sought under s 43 of the
Contract and Commercial Law Act, that claim would have accrued on the date of
cancellation and
could not have been added more than six years after that date.
But as already mentioned, Ms Smith disclaimed any argument that the
Ark
agreement had been cancelled.
- [148] In short,
we cannot identify any principled basis on which interest could have been
claimed, which would not have resulted in
insuperable limitation issues in
relation to the underlying substantive
claim.
The
Depot proceedings — office conversion claim
- [149] The
Depot proceedings arose out of the Daisleys’ removal of the two offices
from the Depot. There were also claims for
unpaid rent in relation to the
Depot, and a claim in debt against Mr Daisley to recover miscellaneous amounts
paid by Ark on his
behalf. That last claim (which was mostly successful) was
not the subject of any appeal, and we need not address it here.
- [150] Ark’s
claim for conversion against Mr Daisley in respect of the two offices turned on
whether the two offices had passed
to Ark along with the Depot land, or whether
ownership of those two buildings had remained with Mr Daisley. That in
turn depended
on:
(a) whether the offices were fixtures that formed
part of the land, so passed with it in the absence of express agreement to the
contrary;
and
(b) whether (even if the offices were not fixtures) Mr Daisley had agreed to
sell them to Ark as part of the transfer of the Depot,
by agreeing
(as between the parties) that they would be treated as forming part of the
land.
- [151] The
Finance Proposal provided by the Daisleys to the Kellers in the period leading
up to the Ark agreement provides important
context in relation to this question.
As noted above, the Finance Proposal included valuations for each of the
four properties sold,
including a valuation for the Depot dated 9 February 2009.
- [152] That
valuation described the Depot as a residential lifestyle property and
agricultural depot. It comprised a modest dwelling,
in which Mr Daisley was
living at the time, and a contractor’s yard which included a three bay
barn, sheds and offices.
- [153] Under the
heading “improvements”, and a sub-heading “other
buildings” the valuation described the two
offices as
follows:
Front Office ± 27m2, plywood
cladding, iron roof and aluminium joinery. Lined and ceiled with a Carrier air
conditioning unit. Power connected but not
on permanent foundations.
(Average/good condition)
Back Office ± 18m2, plywood cladding, iron roof and
aluminium joinery. Lined and ceiled with a Fujitsu air conditioning unit. Power
connected but not
on permanent foundations. (Average/good condition)
- [154] Further
down, under the heading “determination of value” the valuation read
as follows:
Conclusion:
Following due comparative alignment and adjustment of the above sales and
the unique value forming characteristics of the subject
property, we assess the
value of this property as follows:
7.1 Market Value:
Land value
|
$200 000
|
(Two Hundred Thousand)
|
Value of Improvements
|
$375 000
|
(Three Hundred & Seventy Five Thousand)
|
Sub Total
|
$575 000
|
(Five Hundred & Seventy Five Thousand)
|
Added Value of Chattels
|
$5 000
|
(Five Thousand)
|
Current Market Value
|
$580 000
|
(Five Hundred & Eighty Thousand)
|
(Inclusive of chattels & GST, if any)
|
|
|
7.2 Nature and Separate Value of Improvements: (Cost less depreciation
basis)
Dwelling and garage
|
$230 000
|
Nissen workshop
|
$29 000
|
Front office
|
$20 000
|
Back office
|
$16 000
|
New workshop
|
$45 000
|
Sundry storage sheds
|
$6 000
|
Site development & fencing
|
$29 000
|
Total
|
$375 000
|
- [155] The
overall value assessed for the land thus included an allowance of $36,000 for
the two offices, assessed on a cost less depreciation
basis.
- [156] The
valuation also contained the following italicised note:
Caution:
the two office buildings and the sundry storage sheds, while connected to
services, are not on Council approved permanent
foundations and therefore could
be deemed to be temporary structures.
- [157] As already
mentioned, the purchase price of the four properties sold by the Daisley
interests to Ark was set by reference to
the valuations contained in the
Finance Proposal. Ark paid the Daisley interests the total of those
valuations, less 25 per cent.
So the purchase price for the four
properties included an amount of $27,000 reflecting the contribution of those
two office buildings
to the assessed value of the Depot.
- [158] The Judge
described the two offices as
follows:[42]
[17] Photographs
taken in February 2010 of the two offices were produced in evidence. They had
the appearance of simple plywood structures
with an iron or tin roof connected
to phone and power cables entering from an underground channel, lined and
sitting on skids. The
front office was attached to a deck with what appeared to
be a veranda. It is not clear whether the deck was concreted in or on piles.
Mr Keller recollects that they were on piles. The Daisleys say the
deck was merely sitting on the ground. Each had aluminium windows
and a door or
sliding door.
High Court judgment
— office conversion claim
- [159] The
Judge began her analysis of the claim that Mr Daisley had converted the offices
by noting that the answer depended on whether
Ark or Mr Daisley owned the
offices. If Ark owned the offices, then by removing them from the property
Mr Daisley converted
them.[43]
- [160] The Judge
also noted that “[it] could not seriously be argued that removal was not
an act by Mr Daisley. Although he
was not present at the time of removal, he
and his son directed that
operation.”[44]
- [161] The Judge
recorded that the parties were in general agreement in relation to the legal
principles of accession of chattels to
land. It was the application of those
principles which was contested. The test focuses on two
factors:[45]
(a) the
degree or mode of annexation; and
(b) the object or purpose of annexation, assessed objectively.
- [162] However as
the Judge noted, each case depends on its particular facts and a common
sense approach is required.[46]
- [163] In this
case, the offices were annexed to the land, because of the underground
connection to the electricity supply. The Judge
considered indications that the
offices were temporary structures: no water was connected and there was no
sewerage connection.
But the Judge considered that viewed in the round, the
degree of connection was slight but sufficient to amount to
annexation.[47]
- [164] That
finding engaged a rebuttable presumption that an article which is affixed to the
land, even slightly, is considered part
of the land unless the circumstances
show that it was intended to continue to be a
chattel.[48]
- [165] The Judge
considered that the object and purpose of the annexation indicated that the
office buildings were attached to the
land. Objectively assessed, the purpose
of the structures at the time of their placement, and immediately prior to the
transfer
to Ark, was to benefit or improve the Depot land and its utility as
commercial business
premises.[49]
- [166] Thus the
Judge considered that the office buildings formed part of the land, and passed
with it in the absence of an agreement
to the contrary.
- [167] The Judge
went on to say that there was a second reason why she concluded that Ark owned
the office buildings.[50] It was
apparent from the parties’ agreement that the office buildings were
“part and parcel of the sale transaction
on any objective measure, having
expressly been part of the negotiated
consideration”.[51] As
between the parties, Mr Daisley could not now argue that the offices remained
chattels when the Ark agreement was based on the
offices having acceded to the
land, for all intents and
purposes.[52]
- [168] Ark claimed
the replacement cost of the buildings: $67,519.72 plus GST. That estimate
of replacement cost was not disputed
at trial. But Ms Smith argued that this
was not the correct measure of compensation. Rather, their value was $27,000,
representing
the discounted amount paid by Ark based on the value attributed to
the offices by the valuer who prepared the valuation included
in the Finance
Proposal.
- [169] The Judge
did not consider that either of these approaches fairly reflected the value of
the offices at the time of conversion.
A replacement cost approach to value
would respond more appropriately to the overall aim of providing just
compensation for the
true loss suffered by Ark. However such an approach also
involved a degree of betterment. The Judge therefore discounted the pleaded
replacement cost to $50,000, which she considered was a fair assessment of
Ark’s loss. Damages of $50,000 were awarded to
Ark.[53] The Judge awarded interest
under s 87 of the Judicature Act 1908 on this
amount.[54]
Issue 4:
Conversion of office buildings
The issue
- [170] Ms
Smith submits that the Judge was wrong to find that ownership of the two offices
passed to Ark when the Depot was sold in
January 2010. They were temporary
buildings, sitting on skids, that were not affixed to the land. The connection
to electricity
was so minor as to be negligible. There was no other affixation.
- [171] She
submits that the Judge also erred in relation to the purpose for which the
offices were placed on the land and (minimally)
affixed to it. That was to
enable them to be used as chattels, not to enhance the enjoyment of the
land.
- [172] Ms Smith
drew our attention to various photographs of the buildings. She submits
that the suggestion of the Judge that there
was “landscaping” around
the offices was an overstatement. In particular, so far as the back office was
concerned, all
that the so-called landscaping amounted to was a couple of pot
plants sitting outside. That did not amount to landscaping in any
relevant
sense.
- [173] Ms Smith
also submitted that Mr Daisley personally should not have been found liable for
the conversion. He had not been physically
present when the offices were
removed from the Depot. Any involvement that he had in relation to their
removal was in his capacity
as a director of Action Fencing. Just as the Judge
had found that Mr Keller personally was not liable for conversion of chattels
left at the Depot,[55] so Mr Daisley
should not have been found personally liable for any conversion of the office
buildings.
Discussion
- [174] As
Ms Smith accepted, Mr Daisley was involved in the removal of the offices from
the Depot. The basis on which the Daisleys
claimed to be entitled to remove the
offices was that Mr Daisley owned them. It could not sensibly be suggested that
their removal
by Scott Daisley was not authorised by his father. That same day,
Scott Daisley had told their lawyer that “[Mr Daisley] and
I intend
to remove the two offices at the yard on the basis that they belong to
us”. Mr Daisley was involved in planning the
removal: he was at the new
yard that Action Fencing was establishing in Ngāruawāhia at the time
of the removal, awaiting
the delivery of the front office to that yard, where it
would be used for his business activities.
- [175] A person
is liable not only for torts that they physically commit themselves, but also
for torts they have authorised by instigating
or procuring another person to
commit that
tort.[56]
The evidence clearly establishes that if there was a conversion, Mr Daisley
authorised that conversion, and was liable in respect
of it.
- [176] Ms
Smith’s argument really boiled down to the proposition that Mr
Daisley’s involvement in the removal of the offices
was exclusively in his
capacity as a director of Action Fencing. But the capacity in which a person
commits the tort of conversion
is
irrelevant.[57] There are some
torts which depend on concepts of reliance, or assumption of responsibility,
where an individual director or employee
may escape liability on the basis that
the plaintiff was relying on (or responsibility was assumed by) the company of
which they
were a director or employee. The plaintiff could not reasonably look
to them as an individual. Trevor Ivory Ltd v Anderson was such
a case.[58] But conversion is
not a tort in that category, any more than (say) assault. A defendant
cannot say “I assaulted you in my
capacity as a director of company X, so
I am not liable”. Ditto conversion.
- [177] We accept
Ms Smith’s submission that the Judge’s approach to personal
liability for conversion was inconsistent
as between Ark’s claim for
conversion of the office buildings, and the Daisley interests’ claim for
conversion of chattels.
The correct approach is the one adopted by the
Judge in relation to the office building claim: an individual who converts
chattels,
or authorises the conversion of chattels, is liable regardless of the
capacity in which that act was done.
- [178] So the
critical issue is whether it was Ark or Mr Daisley who owned the offices.
- [179] As the
Judge held, the offices were affixed to the land, albeit minimally, by the
underground electricity supply running to
each office. The purpose for which
they were affixed, assessed objectively, appears to have been to enhance the
enjoyment of the
land. That is clearer in relation to the front office
than the back office. So far as the back office is concerned, we accept Ms
Smith’s submission that the placement of the office appears less
deliberate, and the landscaping was so rudimentary as to be
irrelevant. But we
are not persuaded that the Judge was wrong in her overall assessment that the
offices formed part of the land.
- [180] And in any
event, we agree with the Judge that it is quite clear that as between Mr Daisley
and Ark, the sale and purchase of
the Depot proceeded on the basis that the
offices formed part of, and would be sold with, the land. The purchase price
for the Depot
was assessed by reference to the valuation of that property
included in the Finance Proposal. The inclusion of the offices in that
valuation resulted in Mr Daisley receiving an increase in consideration for the
Depot of some $27,000. In light of the mechanism
for setting the sale price,
the inference that the office buildings were treated by the parties as included
in the sale is irresistible.
- [181] Ms Smith
referred us to the letter from Mr Skeates recording Mr Daisley’s surprise
at finding that the offices were included
in the
valuation.[59] She submitted that
this showed that it was not Mr Daisley’s intention to include the offices
in the sale of the Depot. But
this letter evidences Mr Daisley’s own
(subjective) understanding of the scope of the transaction. The interpretation
of the
agreement for sale and purchase turns on how a reasonable person with
access to all the relevant information reasonably available
to the parties at
the time would have understood it. On that approach, it is clear that the
offices were included.
- [182] Ms Smith
also put some emphasis on the note of caution attached to the valuation,
flagging the possibility that the offices
were not fixtures. This, she said,
showed that an experienced professional considered that it was arguable that the
offices were
temporary buildings that were not part of the land. However this
submission does not assist the Daisleys, for two reasons.
- [183] First, it
is clear from the way in which the valuation was presented that the valuer
considered that the better view was that
the offices did form part of the land.
That was the basis on which the value of the land was assessed. However
recognising that
the valuation might be used by a lender for the purpose of
assessing security when lending to Mr Daisley, the valuer prudently added
a note
of caution about the status of the offices. That would enable any lender to
make specific provision in relation to the offices,
if their value was relevant
to the adequacy of the land as security. Notwithstanding this note of caution,
the valuation read as
a whole supports the conclusion reached by the Judge, not
the contrary result contended for by Mr Daisley.
- [184] Second,
the parties clearly proceeded on the basis that the office buildings were to be
treated as included when setting the
purchase price for the Depot. That is,
they proceeded on the basis of the approach reflected in the valuation analysis,
not on the
basis of the caution appended to it.
- [185] The appeal
in relation to the claim for conversion of the office buildings must be
dismissed.
The
Depot proceedings — HPL Distribution’s liability for rent
- [186] The
parties anticipated that, at least initially, the Daisley interests would
continue to occupy the Depot. Mr Daisley aspired
to buy it back, if his
finances improved. The summary of the parties’ meeting on 27 November
2009 recorded an understanding
that Mr Daisley should be able to purchase back
the Depot at an agreed value, and that Mr Daisley was to pay rent for the house
and
yard.
- [187] The
agreement for sale and purchase entered into by Mr Daisley and Ark in respect of
the Depot in December 2009 included a “subject
to tenancy” clause in
respect of the Depot. The named tenant was HPL Northland & North
Harbour. The rent was described
as market rent as at the date of the
agreement. The term was one year.
- [188] As the
Judge noted, Mr Daisley and/or Scott Daisley, ran multiple businesses through
multiple companies. It appeared that Mr
Daisley did not draw any distinction
for practical purposes between the various entities. Many of those companies
had names that
included the acronym “HPL”, including HPL
Distribution, HPL Northland & North Harbour and also HPL Parts &
Services
Ltd and HPL Hawkes Bay (2008) Ltd.
- [189] The
Finance Proposal prepared on behalf of the Daisleys, which as already mentioned
had been provided to the Kellers, recorded
that HPL Northland & North
Harbour had ceased trading and was being wound down. In evidence, Mr Scott
Daisley accepted that
by early 2010, HPL Distribution was the only
“HPL” company that was still operational. The other HPL entities
may have
been completing existing jobs, but were otherwise winding down.
- [190] Mr Keller
decided that the Depot should be divided into three rentable lots to maximise
the potential rental income from the
property.
- [191] The
subject of rent for the Depot was mentioned in the minutes of the parties’
meeting on 23 December 2009:
1 Maungakaramea Road
A/ Rent for top house / office.
B/ Rent for office half round bar / workshop and yard.
C/ Rent for back yard and uncompleted 3 bay shed.
A B C above Action Fencing to look at what they wish to lease. This will
depend on what other tenants we may find and how the sheds,
office space
& fencing are put in place.
...
Action Fencing to pick up the cost of leasing this property until such time
we find other people to lease the bits Action Fencing
don’t want.
- [192] A note in
the minutes of the parties’ 5 January 2010 meeting recorded that
“[Mr Daisley] wants to rent House &
3 bay shed”.
- [193] Mr
Keller’s evidence at trial was that some time later in January 2010 he
discussed rental for the three areas with Mr
Daisley, who suggested the figure
of $350 plus GST and outgoings per week for each area. Mr Daisley denied
this. However Mr Daisley
acknowledged the discussions, and that the figure of
$1,050 was mentioned and that “we went along with it”. Mr Keller
gave instructions to his accountant along these lines on 8 February 2010,
recording what had been agreed from his perspective, and
noting that Mr Daisley
had asked that invoices be made out to Action Fencing.
- [194] An email
dated 22 March 2010 sent to Mr Keller by Steve Jennings, the General Manager of
Action Fencing, confirmed that Mr Keller
should send invoices to
“HPL” for the house area, and to Action Fencing for all of the
yard.
- [195] Ark
proceeded to issue invoices for rent to “HPL” and Action Fencing.
The invoices specified the areas rented by
each of the entities, and
specifically referred to the offices. For example, an invoice to Action Fencing
referred to area 3 as
consisting of the “front office, barn and
yard” and invoices issued to “HPL” referred to “area 1
consisting
of house, garage/spare parts, office, yard”. Invoices for area
2 were also issued to Action Fencing.
- [196] Meanwhile,
on 3 March 2010, the Kellers had proposed formal lease terms for a one-year
lease of the Depot through their lawyers.
The tenants identified in the draft
lease were Action Fencing and HPL Northland & North Harbour. The
Kellers’ lawyers
sent the proposal to Mr Skeates, Mr Daisley’s then
lawyer.
- [197] The
version of this letter produced in evidence from the Daisley interests’
discovery was annotated by hand. Above the
printed name of the party
“HPL Northland & North Harbour Ltd” someone had crossed out
“Northland & North
Harbour Ltd”, and written “Distribution
Ltd”. The Judge considered that common sense suggested that someone from
Mr Daisley’s camp annotated the letter to change the name of the proposed
lessee. That was likely to have been
Mr Skeates.[60]
- [198] The
parties never entered into a formal lease, because of other unresolved issues.
The Daisley business interests continued
to operate from the Depot, and
Mr Daisley continued to live in the dwelling.
- [199] Some rent
was paid. But as noted above, by May 2010 there were substantial rental
arrears. Mr Keller chased payment of rent
on multiple occasions. The Daisley
interests did not deny the existence of an obligation to pay rent at that time,
or raise any
issues about which entity was liable for the rent. Rather, they
proffered a range of excuses for non-payment.
- [200] As already
mentioned, in late August 2010 the Daisley interests advised the Kellers they
were going to vacate the Depot, and
proceeded to do
so.
High
Court judgment — HPL Distribution’s liability for rent
- [201] The
Judge carefully reviewed the parties’ correspondence and dealings in
relation to rent for the three areas of the Depot.
The Judge considered that
the ambiguity in relation to which HPL company was to rent the house area was
resolved by the surrounding
circumstances. She was satisfied that HPL
Distribution was in occupation of the Depot at the relevant time: HPL
Distribution pleaded
this in the chattel conversion proceedings, and the
statement of defence in the Depot proceedings admitted that entities including
HPL Distribution occupied the Depot. Informal leases at will had been entered
into between Ark, Action Fencing and HPL
Distribution.[61]
- [202] The
contemporaneous correspondence from the Daisley interests did not contain any
denial of an informal agreement to lease,
or of an obligation to pay rent. The
Judge considered that the argument that it was Mr Daisley in person who had the
rental obligation,
under the draft shareholders’ agreement, was a red
herring. That agreement contemplated a formal lease with Mr Daisley and/or
his nominees. No such lease was entered into. That agreement sheds no light on
whether informal leases were entered into with particular
companies, or on the
rental terms.[62]
- [203] The Judge
accepted Mr Keller’s evidence about the informal agreements, including the
rent payable. Ark succeeded in its
claim for outstanding rent as
follows:[63]
(a) against
Action Fencing for $11,468.71; and
(b) against HPL Distribution for $11,248.21.
- [204] The Judge
awarded interest under s 87 of the Judicature Act on these
amounts.[64]
Issue
5: HPL Distribution’s liability for rent
The issue
- [205] Ms
Smith submits that the Judge was wrong to find that there was an informal lease
of part of the Depot site to HPL Distribution.
She submits that the house was
in fact occupied by Mr Daisley personally, not by HPL Distribution. She also
submits that the HPL
company that was referred to in the parties’
discussions, and in the draft lease prepared by the Kellers, was HPL Northland
& North Harbour, not
HPL Distribution.
Discussion
- [206] We
agree with the Judge that there was clear evidence of an agreement between the
parties that HPL Distribution would lease
the part of the Depot containing the
house. The clearest indication of that agreement is the express confirmation by
Mr Jennings
in his email of 22 March 2010 that invoices be sent to
“HPL” for the house. At this time, HPL Northland & North
Harbour was in liquidation. It had not been trading for some time. Read in
context, the reference to “HPL” could only
be a reference to
the one HPL company that was still trading at the relevant time:
HPL Distribution.
- [207] That
arrangement is confirmed by the absence of any objection to the invoices sent to
“HPL” from the end of March
2010 through to 10 September 2010.
Again, as a matter of context, the relevant company must have been HPL
Distribution, which was
still trading, not HPL Northland & North Harbour.
- [208] And as the
Judge noted, in the chattel conversion proceedings HPL Distribution and
Action Fencing pleaded that they occupied
the Depot from 29 January 2010
onwards. It would be odd if the HPL company in occupation of the land was HPL
Distribution, but the
HPL company that was liable for rent under the informal
lease entered into by the parties was the (non-trading) entity HPL Northland
& North Harbour.
- [209] It was not
suggested by Mr Daisley in 2010 that he was the tenant of part of the Depot, or
that he was personally liable for
the rent in respect of the Depot. If he had
objected to invoices being sent to “HPL”, and required that they be
sent
to him personally, it is difficult to envisage any reason why that would
not have been done. A claim could then have been brought
against him personally
for the unpaid rent. In the absence of such a request, and in the presence
of an express request that “HPL”
be billed for the rent, the Judge
was in our view plainly right to find that HPL Distribution was liable to
pay rent for this part
of the
Depot.
The
chattel conversion proceedings
- [210] In
the chattel conversion proceedings Action Fencing, HPL Distribution and Mr
Daisley claimed that 38 items of property that
they left at the Depot were
converted by Ark, Mr and Mrs Keller, and the trustees of the Keller Family
Trust. The claim against
the trustees of the Keller Family Trust was
unsuccessful in the High Court, and there was no appeal from that finding. We
say no
more about it. Similarly, the claim against Mrs Keller failed, and that
decision was not challenged on appeal. We need not discuss
that issue. We
therefore focus on the claim that Ark and Mr Keller converted the 38 items,
which the plaintiffs said had a replacement
cost of $225,553.
- [211] Mr Keller
acknowledged that some (but not all) of the items listed in the claim had been
left on the land after the Daisley
interests moved out, and were then locked
out. However the defendants put the plaintiffs to proof of ownership or the
right to possess
the items.
- [212] Mr Keller
also argued at trial that he was justified at the time in requiring proof of
entitlement before releasing items, due
to the confused situation which
developed and competing claims by third parties. He acknowledges that he used
some of the items
left behind, but only after he considered they had been
abandoned. If those items were not abandoned, he concedes they were converted
by Ark. But he challenges the values asserted by the plaintiffs for those
items, and indeed for all of the items that were the subject
of the
claim.
High
Court judgment — chattel conversion proceedings
- [213] The
Judge held that Mr Keller was acting in his capacity as director of Ark, rather
than in his personal capacity. She described
this as “not an issue of
vicarious liability but rather the orthodox principle that Mr Keller’s
actions as director are
treated as actions of Ark
itself”.[65] The Judge
therefore treated the claim as brought against Ark, and not Mr Keller.
- [214] The Judge
noted that the relevant events took place some 10 years before the trial. Much
of the oral evidence given in the
proceeding was inherently unreliable due to
faded memories. The contemporaneous correspondence, and records made by
Mr Keller of
certain events, were the best evidence available. It was for
the plaintiffs to persuade the Judge on the balance of probabilities
that their
claims were made out, based on the evidence presented. Where the gaps were too
great to discharge that burden, the claim
had to be
dismissed.[66]
- [215] The Judge
set out in considerable detail the events relevant to this conversion claim. On
26 August 2010 Mr Daisley emailed
Mr Keller, following a meeting.
He confirmed that the house at the Depot would be cleaned out by the
weekend. He wrote:
We would like to have three to four weeks
with no charge to remove all our gear from the yard.
...
... Scotty can drive the digger to finish off before you take it away. In
return I ask if we can use it to load some of our belongings
with it, eg power
[poles], the steel beams, posts etc.
- [216] There was
no written response to the email.
- [217] It appears
that Mr Daisley vacated the house by 29 August 2010, but there was still
property left on the yard.
- [218] The
removal of the two offices by the Daisleys on 1 September 2010, and the attempt
to remove other sheds the following day,
have already been described.
As mentioned, Mr Keller phoned the police and his lawyer, Mr Badham, who
arrived on site. Mr Keller’s
evidence was that the police advised Scott
Daisley that he could remove other things from the yard, but the sheds and
container had
to stay in place until the dispute was sorted. Mr Keller says it
was stipulated then that Scott Daisley had until Sunday, 5 September
2010 to
remove the items from the site. Scott Daisley’s evidence was that he had
no recollection of any agreement about a
time period.
- [219] Mr Keller
subsequently emailed Mr Badham and Mr Whimp, the liquidators of Daisley
Contracting Ltd, informing them of the 5 September
2010 date for the Daisleys to
remove items.
- [220] By letter
dated 6 September 2010, delivered the following day, the lawyers for the
liquidators wrote to “the occupier”
of the Depot. They advised that
they acted for the liquidators of Daisley Contracting Ltd. They said they also
had the authority
of Ark as land owner. They asserted that the Daisleys had
been removing buildings and assets owned by Daisley Contracting Ltd.
The letter
also stated:
We also confirm that all fixtures and personal property
including equipment and other chattels on the subject land, and those removed
from it without the authority of the liquidator, are the property of Ark or the
company in liquidation, as the case may be.
- [221] The letter
attached trespass notices signed by Ark. Mr Keller’s evidence was that
this was done at the instigation of
the liquidators. He signed the trespass
notices on behalf of Ark, and delivered the trespass notices together with a
representative
of the liquidators.
- [222] Between 7
and 9 September 2010, the liquidators had discussions with Mr Daisley and
Scott Daisley about which assets belonged
to Daisley Contracting Ltd and to
other Daisley companies that were in liquidation. The liquidation reports refer
to difficulties
the liquidators encountered in identifying assets and interests.
They describe the issues as legal issues arising from shareholder
activities and related party transactions; investigation of numerous voidable
transactions; debtor disputes; investigation and recovery
of missing or stolen
plant and machinery; and investigation of assets intermingled with related
companies.
- [223] On
9 September 2010, the liquidators emailed Mr Daisley agreeing that they had no
interest in certain specified assets. Mr
Whimp also emailed this confirmation
to Mr Keller on the same day. The liquidators wrote:
I refer to our
meeting of today. It is agreed that the liquidators have no claim over certain
assets (listed below 1–3) that
are held on the site managed by
Paul Keller. Gary Whimp will contact Paul Keller to discuss. We have no
objection to the secured
creditor or the registered owner arranging to uplift
the following assets. Paul Keller (and his interests) however will need to
also
confirm that he/they have no interest in these assets:
- Gough
Finance to collect the Mazda bounty Ute TM 7063. (The registered owner
is Daisley Fencing Ltd and the vehicle is subject to a security interest held by
Gough.)
- The
container on site belongs to [Mr Daisley] as director of Action Fencing
Limited (AFL). (AFL bought it off us on 2 June and paid our repo agent
Abraham Black Limited on 2 June.)
- The
fencing, panels, old tractors, posts, etc. belong to Action Fencing or
3rd parties as follows (as advised by [Mr Daisley]):
- Power poles
owned by Bruce Paterson
- Steel Beams
owned by John Templeton
- Trailer in the
yard is owned by Cooper Wilson
- Small Tractor is
owned by John Morrow
- Forklift is
owned by Tractor Trans.
- Old Cortina car
(do up) is owned by [Mr Daisley] personally
The trailer
held by Turners Actions is owned by the company. The VIN number confirms
this. We disagree that the trailer is owned by
you personally.
- [224] On 13
September 2010 Mr Whimp emailed Mr Daisley as follows:
We have no
problems with the release of gear from the yard( as detailed in the e mail to
you by Peri) The persons picking up gear
will have to show ownership of the
items to [Mr Keller].
He has been instructed by us to then release it.
- [225] Mr Keller
gave evidence about various individuals arriving at the Depot and asserting
ownership to items, along with trade creditors
seeking money. Mr Keller
described the situation as confused. He was concerned about what might happen
if he released items to
the wrong person. He says that was the reason he
adopted a policy of not releasing anything unless a person had some proof of
ownership.
He said that he was not after receipts or perfect proof — just
some indication that the items were owned by the person wanting
to remove them.
- [226] Although
Mr Keller referred to proof of ownership, Ark’s lawyers understood that
the critical issue was the right to possession
of the chattels left onsite.
They wrote to Mr Skeates on 14 October 2010 as follows:
There are a
number of chattels situated on the property, and the right to possession of
those different items is unclear. The liquidator
of some of your client’s
companies claims the right to possession of much of the equipment. Other agents,
servants and contractors
of your client have turned up on different occasions
attempting to remove chattels and have attempted to assert the right to
possession
on behalf of your client, in some cases using false documentation.
Without creating any duty to your client, our client will release
possession of
the chattels to the persons who establish their legal right to possession.
- [227] The
Daisleys did not provide any proof of their ownership or right to possess any of
the items, but continued to assert their
entitlement in a general sense, and
without specifying what the relevant items were.
- [228] Sometime
after mid-October 2010, Mr Keller says he moved some items from the Depot
out to the Ark property at Knight Road because
no one had turned up to collect
them. This included the steel beams said to be owned by a Mr John Templeton.
He also moved a tractor
and trailer to his home across the road to free up
the Depot for potential tenants.
- [229] On
17 October 2010 Scott Daisley emailed Mr Keller to make arrangements to
pick up the trailer. He said:
There are a lot of items of Action
Fencing that you have, you know you don’t own them and I would like them
back, however the
trailer is a good start.
If you want to discuss this in person, I am happy for you and [Mrs Keller] to
do this ...
If you do not want to give back the company gear that does not belong to you,
I will have to explore other avenues.
- [230] Mr Keller
replied, denying that he had any Action Fencing equipment. He made no
reference to the trailer.
- [231] A
day later, Mr Keller saw Scott Daisley driving his ute up the Keller
driveway. Scott Daisley turned into a neighbour’s
house. Within a few
days the trailer and tractor stored at the Kellers’ property disappeared.
Scott Daisley denied taking
the items, or being aware of the items in the
Kellers’ paddock.
- [232] In
October 2010, Tracta Tranz, an equipment hire business, twice attended the
Depot with security guards. Mr Keller’s
evidence is that on one of
these occasions he was physically restrained by the security guards while the
owner of Tracta Tranz, wrote
down information from the nameplate of the
forklift.
- [233] Sometime
after this, Mr Keller used some second-hand guard rail left at the Depot to
build a retaining wall. In January 2011,
he concreted 33 temporary fencing
panels left at the Depot into the ground to create a fence. He did not
discuss these steps with
Mr Daisley or advise him of his intention. At
around this time, a concrete toilet block was affixed to the land at the Depot
and
at Knight Road.
- [234] On 2
February 2011, Mr Whimp arranged for a container containing digger parts to be
uplifted from the Depot and sent to Scottish
Pacific Business Finance Ltd
(Scotpac). In the same month, Tracta Tranz again attended at the property.
This time they removed
the forklift.
- [235] Some time
later, in 2013, Mr Daisley and Scott Daisley arrived at the Depot and removed
the remaining temporary fence panels.
Mr Keller was not present at the
Depot at the time. It is not clear on the evidence how many fence panels
remained or were taken.
It may have been around 10.
- [236] On
24 April 2014, Ark sold the Depot to the trustees of the Keller Family
Trust. The sale settled on 30 April 2014. After
this, there were no
further demands for the return of items.
- [237] Then in
2015, Mr Daisley issued the first set of proceedings against Ark.
Ark responded with its claim. And on 31 August 2016,
the Daisley
interests issued the chattel conversion proceeding, shortly before the expiry of
six years from the lock out date.
- [238] The 38
items that were the subject of the claim are listed in a schedule to the High
Court conversion judgment. The Judge noted
that by closing, claims to six items
appeared to have been abandoned. No satisfactory identification evidence was
presented in respect
of another claim, which she treated as implicitly
abandoned. A further eight items were trivial in value, even on the
plaintiffs’
own case. And the evidence relating to them was so slim that
the Judge declined to make findings in respect of those items. That
left 23
items.[67]
- [239] The Judge
set out the legal principles relating to the tort of conversion, which were not
in dispute. The essential feature
of conversion is an unlawful denial of the
possessory interest or title of the plaintiff in goods. Conversion requires
conduct inconsistent
with the rights of the owner of the goods or any other
person entitled to possession. The conduct must be deliberate rather than
accidental.[68]
- [240] Liability
is strict. Conversion may be committed with no moral fault or blameworthy
conduct which goes beyond the act which
is inconsistent with the
plaintiff’s right of possession. Thus, a person who innocently hands over
goods to the wrong person,
in the mistaken belief that he or she is delivering
the goods to the true owner, may be liable in
conversion.[69]
- [241] Where a
person innocently comes into possession of the goods of another, they are a mere
custodian rather than a converter of
the goods until they do some act that
amounts to an assertion of dominion inconsistent with the plaintiff’s
rights. There
is an assertion of dominion if there is an unqualified and
unjustified refusal to return the goods in the face of an unequivocal
demand for
them. However simply retaining goods which are left on land does not amount to
conversion.[70]
- [242] It is not
always unlawful to refuse to deliver up goods immediately demand is made. A
person detaining the goods is entitled
to take adequate time to inquire into the
rights of the person claiming the goods. This is because detention is for a
lawful purpose
if it is to ascertain that the claimant is justified in demanding
the goods. As the Judge noted, it is implicit in this proposition
that the
reason for the qualified refusal must be genuine uncertainty that the claimant
is entitled to the goods.[71]
- [243] The Judge
held that as at 7 September 2010, Ark was in possession of the remaining items
at the Depot as an involuntary
bailee.[72]
- [244] The Judge
accepted that the liquidation, combined with the actions of the Daisleys,
contributed to a confusing picture for Mr
Keller. But the plaintiffs had
standing to pursue a claim for conversion in respect of the items left at the
Depot at the date of
the trespass notice, as they were in possession of those
items at the time. The plaintiffs had a better possessory right at that
time
than the defendants, unless they had abandoned the chattels. The Judge rejected
the submission that the plaintiffs needed to
prove which plaintiff was entitled
to possession. Given the relationship between the plaintiffs, the Judge
proceeded on the basis
that the possessory interest of one was impliedly an
interest of all.[73]
- [245] The Judge
found that Mr Keller’s policy of only releasing items on proof of
ownership was not motivated solely by caution.
The removal of the offices by
the Daisleys had contributed to his adoption of a hard-line attitude. But that
did not make his policy
unreasonable. The Judge was persuaded that there was
sufficient doubt about title to or interest in the items to justify Mr
Keller’s
requirement of some proof. His refusal to allow the Daisleys
access to the Depot to uplift items without this did not amount to
an
unqualified or unjustified interference with the items. The demands for return
of the items had also been general, without specific
identification for the most
part. And there was no explanation for the Daisleys’ failure to provide
anything resembling an
explanation of ownership or right to
possession.[74]
- [246] In light
of those principles, and the findings set out above, the Judge proceeded to
analyse the claims in respect of each of
the 23 items.
- [247] The Judge
found that the claims for conversion were made out in respect of
a container (but not its contents), fence panels,
gates and guard rail, and
two concrete toilets. In each case she awarded damages and interest under
s 87 of the Judicature Act.
She dismissed the remaining
conversion claims. We set out in more detail below the Judge’s reasons
for rejecting the claims
that are pursued on
appeal.
Issue
six: Chattel conversion issues
- [248] The
Daisley interests appealed in respect of a subset of the items in respect of
which their claims were unsuccessful in the
High Court. They very sensibly did
not pursue claims in respect of a number of lower value items.
- [249] Ms Smith
submitted that the Judge had been right to approach the question of conversion
of chattels left at the Depot on the
basis that the Daisley interests had
a better possessory right to the chattels, unless they had been abandoned.
However the Judge
had then incorrectly, when reviewing the position concerning
particular items, focussed on ownership of those items.
- [250] Ms Smith
also submitted that the Judge erred in finding that Ark was in possession of the
items left at the Depot as an involuntary
bailee, because Ark had not given
notice to terminate the tenancy at will that complied with the requirements of
the Property Law
Act 2007. We consider that this is a red herring. The
Daisleys had moved out of the Depot. They had asked for a period of
“three
to four weeks with no charge” to remove their items: they
were not suggesting that the tenancy was still on foot. The termination
of
the tenancy at will was in our view proposed by the Daisleys to limit their
obligation to pay rent, and agreed to by Ark. The
question of notice by Ark did
not arise. And in any event, the mere taking of possession of the Depot while
permitting items to
be removed by the person(s) entitled to possession of those
items would not constitute a conversion. So it is necessary to examine
the
claims item by item, to ascertain whether particular items were converted by Mr
Keller and/or Ark.
- [251] In her
oral argument before us, Ms Smith focussed on the claims in respect of a
forklift and excavator parts in the container.
(As already mentioned, the Judge
found Ark had converted the container, but not its contents.) We will begin by
addressing those
claims. We will then consider, briefly, the remaining items
that were the subject of the appeal, which were addressed in the parties’
written submissions but not in oral argument before
us.
The
forklift
- [252] Ms
Smith says that the starting point is that the forklift was in the lawful
possession of the Daisley interests on hire/rental
terms from Tracta Tranz. Mr
Keller’s refusal to permit Tracta Tranz, or the plaintiffs, to uplift the
forklift was an interference
with their rights of possession which amounted to a
conversion.
- [253] We were
not taken to any evidence that the Daisleys, who on the face of it were entitled
to possession of the forklift, made
a demand for the forklift or were prevented
from removing it themselves.
- [254] We agree
with the Judge that Mr Keller was justified in requiring proof of some form of
entitlement to the forklift before releasing
it to Tracta
Tranz.[75] There was no evidence
before the Court that Tracta Tranz owned the forklift, or that it was entitled
to possession of the forklift
at the times it sought to uplift it. Nor was
there any evidence that Tracta Tranz advised Mr Keller that it was acting on
behalf
of the Daisley interests in attempting to take possession of the
forklift, or demanding possession of the forklift. Tracta Tranz
did not
provide any evidence to Mr Keller of authority to uplift the forklift on behalf
of the Daisleys.
- [255] Nor was
Tracta Tranz a plaintiff in the High Court proceedings. So the unsuccessful
attempts by Tracta Tranz to uplift the
forklift do not appear to be relevant to
the proceedings, except to the extent that they cast doubt on the Daisley
interests’
right to possession of the forklift.
- [256] In any
event, the forklift was ultimately removed by Tracta Tranz in
February 2011. In those circumstances it was common ground
that any
damages for conversion would be limited to damages for loss of use of the
forklift between the time of any conversion by
Mr Keller — at the
earliest, September 2010 — and February 2011. The Daisleys’
claim for such loss was based on
an invoice from Tracta Tranz dated
15 February 2011 for a total of $74,903.52, described as the cost of hire
between 6 September
2010 and 11 February 2011. The invoice referred to a
daily rate of $390 plus GST per day.
- [257] No
evidence was produced of any hire purchase agreement between Tracta Tranz
and the Daisleys. No earlier invoices were produced
for rent for periods when
the Daisleys had possession of the forklift. No evidence was given of any
previous payments of rent for
the forklift. No-one from Tracta Tranz gave
evidence in relation to the arrangements for hire of the forklift. The invoice
was
produced late in the day, with no explanation. The Kellers’ expert
valued the forklift at around $5,000, and expressed concern
about its safety,
and suitability for hiring. That in turn casts doubt on the amount claimed by
way of rent. As the Judge said,
in these circumstances the invoice “has
to be viewed with
scepticism”.[76]
- [258] Still more
problematically for this claim, the Daisleys confirmed in evidence that no
payment had been made by them in respect
of this invoice. There was no evidence
that any steps had been taken by Tracta Tranz to seek payment of the invoiced
amount. Ms
Smith confirmed from the bar that no enforcement proceedings had
been taken by Tracta Tranz in respect of that amount. In those
circumstances,
any claim to recover it would now be time-barred. Ms Smith suggested her
clients felt a moral obligation to make
the payment. But we give that little
weight, in the absence of any evidence that they had made payments of rent on a
similar basis
in respect of earlier periods.
- [259] We share
the Judge’s doubts about the genuineness of the debt that the invoice
purports to record. But in any event,
the debt has not been paid by the
plaintiffs and is not now recoverable. So the plaintiffs have not suffered any
loss.
- [260] In these
circumstances, the claim for conversion of the forklift
fails.
Excavator
parts
- [261] The
Daisleys left a container at the Depot when they moved out. The container
contained a range of items including Kato and
Kobelco excavator parts.
On 9 September 2010, the liquidators advised Mr Keller that the
container belonged to Action Fencing.
There appears to have been some confusion
about ownership of the contents of the container. The Judge found that at some
stage (but
it was murky when and how) Mr Keller came to understand that the
contents of the container belonged to Scotpac. A security firm
made attempts to
uplift the container and its contents on 21 September 2010, but they had no
documentation to provide as proof of
ownership or any other interest, so were
not permitted to do so.
- [262] In October
2010 Mr Keller asked the liquidators what was happening in relation to the parts
and the container. One of the liquidators
replied by email shortly afterwards
saying “Leave it to me”. The Judge found that there were telephone
discussions between
the liquidators, Mr Keller and a Mr Clayton of Scotpac in
relation to uplifting of the contents of the container. The Judge found
that Mr
Keller actively pressed Scotpac to arrange removal. He was led to believe that
Scotpac had a legitimate interest in those
parts.
- [263] The Judge
was satisfied that it was the liquidators in conjunction with Scotpac who
ultimately uplifted the container with the
digger parts. The Judge held that
Mr Keller’s acquiescence in this removal amounted to a conversion of
the container, but
did not amount to conversion of the contents of the
container.
- [264] We accept
Ms Smith’s submission that Mr Keller, by playing an active role in the
removal of the container and its contents
by Scotpac, acted inconsistently with
the Daisleys’ right to possession of both the container and its contents.
We accept
that Mr Keller acted in good faith: but that is irrelevant, as
conversion is a strict liability tort.
- [265] We
therefore find that Mr Keller converted the contents of the container, as well
as the container itself.
- [266] However
there was no reliable evidence before the Court in relation to the value of the
contents of the container. The only
evidence the plaintiffs provided in
relation to the value of the container contents was a table listing all the
items that they said
were converted. This table included a single line
item for “Kato and Kobelco excavator parts in container”, with a
round
figure of $25,000 described as the “cost” of those parts. The
parts were not separately listed, or otherwise identified.
Neither Mr Daisley
nor Scott Daisley described the items in their evidence, or expressed
a reasoned view on their value. No evidence
was provided in relation to
their purchase: from whom they were purchased, when, or for what price. The
Daisleys did not provide
any relevant invoices, receipts, or even bank
statements with relevant entries identified. They called no expert evidence.
And
the expert called by the defendants in relation to the value of items left
on the property did not consider that he was able to value
these parts, based on
the limited information available. So there was no evidence before the High
Court that would enable us to
identify, or ascribe a value to, these
excavator parts. In those circumstances, the claim in respect of those parts
cannot succeed.
Fence
panels
- [267] The
Judge found that Ark had converted 33 temporary fence panels and four fence
gates. It was common ground before us that
the Judge erred in applying a value
of $132.50 per panel for those fence panels, in circumstances where the Kellers
had called expert
evidence valuing fence panels at $150–$200 per panel for
New Zealand made panels. These were New Zealand made panels.
- [268] It follows
that the damages awarded were understated by $17.50 per panel for
33 panels: a total of
$577.50.
Steel
beams
- [269] There
were a number of used steel beams left at the Depot when the Daisley interests
moved out. They had been left out in the
open and were weathered.
The email from the liquidators set out at [223] above recorded that Mr Daisley had
identified a Mr John Templeton as the owner of these beams. Mr Keller gave
evidence that he had
never heard from Mr Templeton or anyone else concerning the
beams since 2010. At some stage, Mr Keller moved the beams to Ark’s
property at Knight Road, with a view to making the Depot more attractive to
potential tenants.
- [270] The claim
in respect of the steel beams was dismissed in the High Court for a number
of reasons, including concern about an
apparently fabricated invoice relied on
by Action Fencing as proof of ownership of the steel
beams.[77] There was a lack of
evidence about whether the Daisleys or Mr Templeton owned the beams.
And Mr Keller’s evidence was that
the beams remained available
for collection. There had never been an unqualified refusal to return the
beams.
- [271] We accept
Ms Smith’s submission that the question of ownership of the beams is not
relevant. Rather, in the context of
a claim for conversion the focus is on the
right to possession of the beams. The beams were in the Daisleys’
possession before
they moved out of the Depot. If the Daisleys had sought to
collect the steel beams, Mr Keller and Ark could not properly have refused
to
permit them to do so without committing the tort of conversion.
- [272] However
there was no evidence of a demand for possession of the steel beams that was
refused by Mr Keller, or of any attempt
by the Daisleys to collect them.
Mr Keller’s evidence that the beams remained available for collection
from his other property
was not seriously challenged. The mere fact that he
moved the beams to another location did not itself amount to a conversion, as
in
doing so Mr Keller had no intention to take possession of the beams or deprive
the Daisley interests of their right to possession
of
them.[78]
- [273] We
therefore dismiss the appeal in respect of the steel
beams.
Hydraulic
press and toolbox
- [274] The
items left on site included a hydraulic press and toolbox. The Judge found
that ownership of the press and toolbox was
unclear. It was likely that
HPL Distribution had at least a possessory right, in the absence of any
information to the
contrary.[79]
- [275] It appears
that HPL Distribution never made any demand for the hydraulic press or toolbox.
Mr Keller’s evidence was that
Scotpac asserted ownership of the hydraulic
press, but chose not to uplift it because of the inconvenience.
Mr Keller’s company,
Electrical Marine Services Ltd, then purchased
the hydraulic press and toolbox from the liquidators for a total of $500.
- [276] The Judge
considered that in these circumstances, none of the defendants converted the
hydraulic press and toolbox. If there
was a conversion, it could only have been
by another entity.[80]
- [277] We accept
Ms Smith’s submission that if HPL Distribution had a possessory right to
these items, it is irrelevant that
Scotpac or the liquidators wrongly asserted
ownership of the items: if Ark or Mr Keller was involved in dealings with these
items
that were inconsistent with the possessory right of HPL Distribution, they
would be liable in conversion.[81]
Nor, as explained above, can Mr Keller escape liability for acts amounting to a
conversion on the basis that he was acting on behalf
of a company.
- [278] Mr
Keller’s evidence was that he had agreed with Mr Whimp that he would
purchase these items from Daisley Contracting
Ltd, through his company. He said
he has the toolbox. If HPL Distribution had a right to possession of these
items at the time
the Daisleys left the Depot, those dealings would amount to a
conversion.
- [279] However as
the Judge said, ownership of these items was unclear. The hydraulic press
appeared in the depreciation schedule
of HPL Northland & North Harbour.
There was also some suggestion it was owned by another Daisley company, Parts
2009 Ltd. It
could equally well have been on site at the Depot in the
possession of some other Daisley entity, through the Daisleys, given the
confusion surrounding dealings with the assets of those entities. The evidence
is insufficient to persuade us that HPL Distribution
had a sufficient possessory
interest to support a claim for conversion in respect of the hydraulic
press.
- [280] The
position in relation to the toolbox is, if anything, less clear. The Judge
considered that it was likely that HPL Distribution
had a possessory right in
respect of the toolbox. But the claim alleged that it was owned by, and in the
possession of, Action Fencing.
There was also some evidence that the
toolbox had been in the possession of Daisley Contracting. Again, the evidence
is insufficient
to persuade us that HPL Distribution or Action Fencing had a
sufficient possessory interest to support a claim for conversion in
respect of
the toolbox. This claim also
fails.
Tractor
and trailer
- [281] The
items left at the Depot also included a tractor and trailer. As noted above,
on 17 October 2010 Scott Daisley emailed Mr
Keller to make
arrangements to pick up the trailer and other items. Mr Keller replied denying
that he had any Action Fencing equipment.
He made no mention of the trailer.
- [282] Mr
Keller’s evidence was that the tractor was moved to his home along with
the trailer, to enable the Depot to be let
out. It was removed from there by
unknown persons. Shortly before that, Mr Keller said he had seen Scott Daisley
driving his ute
up the Keller driveway. Scott Daisley denied taking the
items, or being aware of the items in the Kellers’ paddock.
- [283] The Judge
found that it was more likely than not that Scott Daisley had removed the
tractor and trailer from the Kellers’
property. There had been no
unqualified refusal to hand over either of them. Removal of those items from
the Kellers’ property,
whether by Scott Daisley or some other person,
did not amount to conversion by the Kellers. She therefore dismissed that
claim.
- [284] We accept
Ms Smith’s submission that there was little evidence that
Scott Daisley had taken the tractor and trailer.
Mr Keller did not suggest
that in his evidence. That finding was not supported by the evidence.
- [285] However
there was no unqualified refusal to permit the Daisleys to remove these items.
Mr Keller did not convert the tractor
and trailer merely by moving them to his
property.[82] The taking of those
items by unknown persons does not amount to a conversion by any of the
Keller interests. The Judge was therefore
right to dismiss the claim in respect
of this
item.
Summary
- [286] In
summary, we have found that the appeal by Action Fencing and
HPL Distribution in relation to the chattel conversion claims
succeeds in
just one respect: the damages in respect of the fence panels should be increased
by
$577.50.
Costs
- [287] The
parties agreed that each of the appeals should be treated for costs purposes as
a standard appeal falling within band A.
- [288] The Keller
interests have succeeded in relation to the appeal and cross‑appeal in
CA271/2020. They are entitled to costs
in respect of the appeal and
cross-appeal.
- [289] The Keller
interests have succeeded in the Depot proceedings appeal (CA31/2021). They are
entitled to costs in respect of that
appeal.
- [290] The
Daisley interests had a minor degree of success in relation to the chattel
conversion appeal (CA30/2021). The damages awarded
were increased in respect of
one item by a very small amount, which was not contested by the Kellers in
their submissions. The appeal
failed in relation to all other items,
including all the items in respect of which significant sums were claimed. In
those circumstances,
we consider that — adopting an approach that is
generous to the Daisley interests — the costs of this appeal should be
awarded to the Keller interests subject to a 10 per cent
deduction.
Result
CA271/2020
- [291] The
appeal in CA271/2020 is allowed.
- [292] The award
of damages/equitable compensation to Mr Daisley is set aside.
- [293] The
cross-appeal in CA271/2020 is dismissed.
- [294] The
respondent must pay the appellants costs in respect of the appeal and
cross‑appeal, in each case for a standard appeal
on a band A basis, with
usual disbursements.
CA30/2021
- [295] The appeal
in CA30/2021 is allowed in part. The damages awarded are increased by $577.50.
The appeal is otherwise dismissed.
- [296] The
appellants must pay the respondents 90 per cent of the costs for a standard
appeal on a band A basis, with usual
disbursements.
CA31/2021
- [297] The appeal
in CA31/2021 is dismissed.
- [298] The
appellants must pay the respondent costs for a standard appeal on a band A
basis, with usual disbursements.
Solicitors:
Henderson Reeves Lawyers, Whangarei for Appellants in CA271/2020 and
Respondents in CA30/2021 and CA31/2021
Tailored Legal Solutions Ltd,
Dargaville for Respondents in CA271/2020 and Appellants in CA30/2021 and
CA31/2021
[1] Daisley v Ark Contractors
Ltd [2020] NZHC 793 [Main proceedings judgment] at [148] and [159].
[2] At [233]–[234].
[3] At [222]–[228].
[4] At [229].
[5] At [238]–[240].
[6] Ark Contractors Ltd v
Daisley [2020] NZHC 3508 [Depot proceedings judgment] at [88]–[89],
[106], [115] and [118]–[121].
[7] Action Fencing Ltd v Ark
Contractors Ltd [2020] NZHC 3509 [Chattel conversion proceedings
judgment].
[8] Depot proceedings judgment,
above n 6, at [35].
[9] Main proceedings judgment,
above n 1.
[10] At [148].
[11] At [149].
[12] At [159].
[13] At [184].
[14] At [189]–[201].
[15] At [217].
[16] At [218].
[17] At [219]–[221].
[18] At [228].
[19] At [229].
[20] At [229].
[21] At [232].
[22] At [236].
[23] At [237].
[24] At [241].
[25] At [239].
[26] At [240].
[27] Main proceedings judgment,
above n 1, at [228].
[28] High Court Rules 2016,
r 5.26(a) and (b).
[29] Rolled Steel Products
(Holdings) Ltd v British Steel Corp [1986] Ch 246 (CA) at 309.
[30] Yan v Mainzeal Property
and Construction Ltd (in liq) [2021] NZCA 99.
[31] At [493].
[32] Main proceedings judgment,
above n 1 (footnote omitted).
[33] By January 2010 it had
become clear that SDD had no equity in its property, so Mr Daisley alone would
receive shares in Ark.
[34] Main proceedings judgment,
above n 1, at [241].
[35] At [242(b)] and [243].
[36] The Kellers’ evidence
was that the value of Ark today was in the region of $500,000.
[37] Chirnside v Fay
[2006] NZSC 68, [2007] 1 NZLR 433 at [52].
[38] Paper Reclaim Ltd v
Aotearoa International Ltd [2007] NZSC 26, [2007] 3 NZLR 169 at
[31] (footnote omitted).
[39] Amaltal Corp Ltd v
Maruha Corp [2007] NZSC 40, [2007] 3 NZLR 192 at [19].
[40] See for example, Andrew
Butler (ed) Equity and Trusts in New Zealand (2nd ed, Thomson Reuters,
Wellington, 2009) at 477 and 553; AUAG Resources Ltd v Waihi Mines Ltd
[1994] 3 NZLR 571 (HC) at 577; and McLachlan v Mercury Geotherm Ltd (in
rec) CA142/02, 28 August 2003 at [49], approved in McLachlan v Mercury
Geotherm Ltd (in rec) [2006] UKPC 27, (2006) 7 NZCPR 135 at [25].
[41] See Dold v Murphy
[2020] NZCA 313 at [58].
[42] Depot proceedings judgment,
above n 6.
[43] At [49].
[44] At [50].
[45] At [58], citing Holland
v Hodgson [1872] UKLawRpCP 24; (1872) LR 7 CP 328 at 334–335 per Blackburn J, applied in
New Zealand in Lakes Edge Developments Ltd v Kawarau Village Holdings Ltd
[2017] NZCA 205, [2017] 3 NZLR 336 at [57].
[46] At [59].
[47] At [66].
[48] At [60].
[49] At [67] and [72].
[50] See [74]–[79] where
the Judge relies on Lockwood Buildings Ltd v Trust Bank Canterbury Ltd
[1995] 1 NZLR 22 (CA) for the proposition that parties are able to regulate the
doctrine of accession as between themselves: at [76].
[51] At [80].
[52] At [82].
[53] At [93]–[95].
[54] At [122(f)].
[55] Chattel conversion
proceedings judgment, above n 7, at
[111].
[56] Michael Jones (ed) Clerk
& Lindsell on Torts (23rd ed, Sweet & Maxwell, London, 2020) at
[6‑01]. In relation to the tort of conversion, see Stephen Todd (ed)
Todd on Torts (8th ed, Thomson Reuters, Wellington, 2019) at 632.
[57] Johnson Matthey (Aust)
Ltd v Dascorp Pty Ltd [2003] VSC 291, (2003) 9 VR 171 at
[85]–[90].
[58] Trevor Ivory Ltd v
Anderson [1992] 2 NZLR 517 (CA).
[59] See [56] above.
[60] Depot proceedings judgment,
above n 6, at [35].
[61] At [98]–[99].
[62] At [104].
[63] At [106].
[64] At [122(f)].
[65] Chattel conversion
proceedings judgment, above n 7, at
[10] (footnote omitted).
[66] At [14]–[15].
[67] At [66].
[68] At [74], citing Todd, above
n 56, at [12.3.01]; Cuff v
Broadlands Finance Ltd [1987] NZCA 93; [1987] 2 NZLR 343 (CA) at 346; and Wilson v New
Brighton Panelbeaters Ltd [1988] NZHC 457; [1989] 1 NZLR 74 (HC) at 80.
[69] At [75], citing Todd, above
n 56, at [12.3.01]; and Wilson v New
Brighton Panelbeaters Ltd, above n 68, at 80.
[70] At [75]–[76], citing
Todd, above n 56, at [12.3.02(2)].
[71] At [78]. See also Todd,
above n 56, at [12.3.02(2)].
[72] At [81].
[73] At [83]–[85], citing
Glenmorgan Farm Ltd (in rec and in liq) v New Zealand Bloodstock Leasing
Ltd [2011] NZCA 672, [2012] 1 NZLR 555 at [28].
[74] At [87]–[88].
[75] At [96].
[76] At [97].
[77] At [102]–[103].
[78] See Todd, above n 56, at 634.
[79] Chattel conversion
proceedings, above n 7, at [109].
[80] At [111].
[81] See Helson v McKenzies
(Cuba Street) Ltd [1950] NZGazLawRp 70; [1950] NZLR 878 (CA).
[82] See above at [272].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2021/351.html