You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2021 >>
[2021] NZCA 44
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Minister for Land Information v Dromgool [2021] NZCA 44 (5 March 2021)
Last Updated: 10 March 2021
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
MINISTER FOR LAND INFORMATION Appellant
|
|
AND
|
SHANE DROMGOOL AND DOROTHY DROMGOOL First
Respondents
ALAN DARVALL POULTON AND JENNIFER POULTON Second
Respondents
NEWMAN FARMS LIMITED Third Respondents
|
Hearing:
|
7 and 8 July 2020
|
Court:
|
Cooper, Clifford and Goddard JJ
|
Counsel:
|
A N Isac QC, M C McCarthy and E M Jamieson for Appellant D M Salmon
and A W McDonald for Respondents
|
Judgment:
|
5 March 2021 at 3 pm
|
JUDGMENT OF THE COURT
- The
appeal is allowed.
- The
decision of the High Court is set aside.
- The
report of the Environment Court is confirmed.
- The
matter is referred back to the Environment Court to finalise the terms of the
easements.
- There
is no order as to costs.
____________________________________________________________________
REASONS
OF THE COURT
(Given by Cooper J)
Table of
Contents
Para No.
Introduction
- [1] This
appeal raises an important issue concerning the role and obligations of the
Minister for Land Information (the Minister)
under s 186(1) of the Resource
Management Act 1991 (the RMA).[1]
- [2] Section
186(1) of the RMA provides that a network utility operator that is a requiring
authority may apply to the Minister to
have land required for a project or work
acquired or taken under pt 2 of the Public Works Act 1981 (the PWA) “as if
the project
or work were a government work within the meaning of that
Act”. The provision then states that the land may be taken or acquired
“if the Minister ... agrees”.
- [3] Under pt 2
of the PWA land may be acquired by agreement, or compulsorily. In either case,
there must be a period of negotiation
in good faith in an attempt to reach an
agreement for the acquisition of the
land.[2] If agreement cannot be
reached, the Minister may proceed to take the land under the
PWA.[3]
- [4] Every person
having any estate or interest in the land may object to the Environment
Court,[4] which considers the
objection in accordance with s 24 of the PWA. Section 24(7) states what
the Environment Court is required to
do. It must ascertain the Minister’s
objectives; enquire into the adequacy of the consideration given to alternative
sites,
routes or other methods of achieving those objectives; and decide whether
it would be “fair, sound, and reasonably necessary”
for achieving
the objectives of the Minister for the land of the objector to be
taken.[5] It must then submit a
written report to the Minister setting out its
findings.[6] The Environment
Court’s report and findings are binding on the
Minister.[7]
- [5] In this
case, Top Energy Ltd (TEL), a requiring authority, sought to acquire easements
to enable construction of an electricity
transmission line between Kaikohe and
Kaitaia. It made requests to the Minister under s 186(1) of the RMA, in
relation to land along
the route. The Minister gave her agreement. There were
objections to the Environment Court from affected landowners.
- [6] In its
report on the objections the Environment Court held that the Minister’s
response to a request under s 186(1) was
“fully
discretionary”.[8]
It rejected an argument advanced by counsel for the objectors that the Minister
was obliged to consider the matters that would be
considered subsequently by the
Environment Court in dealing with, and reporting on, an objection under
s 24 of the PWA.[9] It found
that adequate consideration had been given to alternative sites, routes and
methods to achieve the objectives of the Minister
and
TEL.[10] The Court concluded that
the taking of the land would be fair, sound and reasonably necessary for
achieving those objectives, and
furnished a written report to the Minister
accordingly.[11]
- [7] The
objectors appealed the Environment Court’s report to the High
Court.[12] Courtney J allowed the
appeal and set aside the Environment Court’s
report.[13]
This Court then granted leave for the present
appeal,[14] stating that the
approved question was whether the High Court erred in law in allowing the
appeal and setting aside the Environment
Court’s
report.[15] In granting leave, this
Court also said:
C Counsel should focus their submissions on:
(a) the role and obligations of the Minister under s 186 of the Resource
Management Act 1991; and
(b) whether the inquiry into the adequacy of consideration of alternatives
contemplated by s 24(7) of the Public Works Act 1981 is
an inquiry into the
adequacy of consideration of alternatives by the requiring authority, by the
Minister, or by both.
- [8] For the
reasons we address, we allow the Minister’s appeal and confirm the
Environment Court’s report. We hold that
where the Minister’s
agreement is sought under s 186 of the RMA, the Minister needs to be
satisfied that the project of the
network utility operator is capable of
achieving a favourable report from the Environment Court under s 24(7) of
the PWA. But the
Minister need not personally assess the merits of, and choose
between, alternative means of achieving the objectives of the network
utility
operator. We further hold that the Minister may withhold consent if the
proposal is contrary to the purpose and principles
of the RMA, or is undesirable
for other reasons that are consistent with the statutory framework. We consider
that where the Minister
has agreed to the taking under s 186(1), it is
likely that the main consideration of alternatives will have been by the network
utility
operator (which can be expected to have the institutional knowledge and
expertise required for that purpose) and it is legitimate
for the Environment
Court to focus its enquiry
accordingly.
Relevant facts
- [9] TEL
owns and operates a 110kV transmission line which runs between Kaikohe and
Kaitaia. The Environment Court accepted evidence
from TEL’s
Chief Executive Officer, establishing
that:[16]
(a) the line
requires maintenance as it is around 60 years old, and requires replacement
within the foreseeable future (around 2030);
(b) maintenance works on poles and repairs of breakages have been an ongoing
and significant requirement since the takeover. In particular,
around 6km of the
line runs through the Mangamuku Gorge and is vulnerable to major events;
(c) between 2013 and 2017 there were some nine outages of 47.7 hours to
substantial parts of the network. Measured in terms of the
economic impact of
those outages, the cost to the Far North economy is estimated to be
$13,368,956;
(d) the Juken timber mill in Kaitaia is a major employer, and particularly
susceptible to outages. An unplanned outage can mean a
cost to the production
line through a restart of some $150,000 each time[;]
(e) the historic pattern of demand has changed from the urban centres of
Kaikohe and Kaitaia, with increasing population on the eastern
seaboard area
(Kerikeri Peninsula and the Bay of Islands);
(f) it was considered that an alternative route to the eastern seaboard
would increase supply through the 11kV local network lines,
and permit some
upgrading to 33kV (for example in Kaeo and Wiroa). Examples were given by Mr
Shaw, including Mt Pokaka having to
supply their own power for a timber mill
employing 100 people, and an 800 unit accommodation in Karikari Peninsula having
no secure
supply of power;
(g) the existing GXP 110kW single circuit was on a route involving the
Mangaweka Gorge, and is susceptible to failure through natural
events.
Significant resilience would be achieved by creating a second circuit to
Kaitaia.
- [10] TEL
instructed Boffa Miskell, an environmental planning and design consultancy,
to investigate a potential new route to serve
the eastern side of the region by
means of a proposed “ring circuit”, incorporating the substations at
Kaikohe and Kaitaia
which are used for the existing line. The infrastructure
would be upgraded, and a second line installed closer to the new areas
of
demand. As part of the overall project, TEL investigated a potential route
linking a new substation in Wiroa near Kerikeri to
a substation at Pamapuria
near Kaitaia. That proposed route would affect about 96 properties, over most
of which TEL was able to
secure easements. The objections heard by the
Environment Court related to a route option for an approximately 7-km stretch,
known
as the “Mangakaretu” section which would run between Wiroa and
Kaeo, in respect of which agreement could not be reached.
- [11] Boffa Miskell’s
initial evaluation identified a route passing over land owned by the Office of
Treaty Settlements and land-banked
for the purpose of claims for redress under
the Treaty of Waitangi (the OTS land). In addition to crossing the OTS land,
this route
(the OTS route) ran through rural land referred to by the Environment
Court as the Taylor property, the Poulton property and
“Greenacres”.[17]
- [12] Between
2012 and 2014, TEL pursued the OTS route as its preferred route.
It entered into an agreement to grant easements with
the owners of the
Poulton and Greenacres properties, but could not secure agreement from the
owners of the Taylor property or the
Office of Treaty Settlements. By October
2014 it was clear that agreement from those parties would not be forthcoming.
- [13] Between
March and October 2014 TEL investigated alternative routes, which included three
that were described by the Environment
Court as
follows:[18]
(a) the
FGT/Sutcliffe Route, slightly to the west of the original route and
travelling through the length of the FGT and Sutcliffe properties, relying on
the
AGE with Poulton and the agreement of Greenacres eventually obtained. This
route, of course, still involved crossing the Taylor
property, who had already
indicated they would not consent, and also further crossing of the FGT Farms
Limited, Sutcliffe and Cornelius
properties;[19]
(b) ... the Objection Route, travelling through a different portion
of the Poulton farm (for which there was no AGE), Newman Farms, Dromgool (the
Objectors),
Sutcliffe, Kearney and Cornelius properties. This utilised a
section of public road between Newman Farms and the Jones property
for around
1.5km. ... ; and
(c) ... a route to the far west (Far Western Route), skirting the
North Star Dairies Ltd land (on Crown land) and then utilising public road to
travel from the west to join up at the
Greenacres property. It appears
that route was discounted not only for length but impact very early, and no
party ... suggested
that this was a reasonable alternative.
- [14] Various
alignments between the three routes just described were also examined, and
discussions continued with a number of landowners
in the area into 2016. In the
event, an agreement to grant an easement was reached with respect to the
Sutcliffe property along
what the Environment Court called the Objection Route,
and the FGT/Sutcliffe Route was no longer being pursued.
- [15] It was not
possible to reach agreement with the present respondents, and in May 2016 TEL
applied to the Minister under s 186(1)
of the RMA to have easements in respect
of those properties acquired or taken. The Minister granted those
applications. The landowners
objected to the taking of the easements,
resulting in a hearing before the Environment
Court.[20]
The
Environment Court’s report
- [16] The
Environment Court proceeded on the basis that s 186 of the RMA did not
contain an explicit requirement that the Minister
take into account any
particular matters.[21] Rather, the
Minister’s decision was “fully
discretionary”.[22]
Any failures in the consideration of alternatives would be relevant to the
report and findings of the Environment Court under s
24(7) of the PWA, but
not at the stage of ministerial agreement under s 186 of the
RMA.[23] In reaching that
conclusion, the Environment Court referred to and was guided by the decision of
the Supreme Court in Seaton v Minister for Land
Information.[24]
The Environment Court held:
[53] Notwithstanding the repeated
submissions of Mr Salmon as to the necessity for the Minister to comply
with s 24(7) when a decision
under s 186 is made, we can find no reference
in this or any other case to such a requirement. Mr Salmon’s own
submissions
... noted that references to the Minister in s 186 and s 24(7) (a)
and (d) must be read as reference to [TEL], relying on Seaton, paragraph
[83]. We agree. Thus, it is difficult to read into s 186 a requirement
that the Minister, at the time they agree to proceed
with Part 2 of the Public
Works Act, has an obligation to ensure that the taking complies with s 24(7) of
the Act.
- [17] The
Environment Court concluded that there had been “extensive consideration
of alternatives by both Boffa Miskell and
TEL”.[25] While TEL would
have preferred the OTS route, the refusal of the Minister for Treaty of Waitangi
Negotiations to provide an easement
over the OTS land meant that route could not
proceed because of the absence of power to compulsorily acquire Crown
land.[26]
- [18] After
discussing the various alternatives considered, the Environment Court
said:
[125] We are satisfied that, at the time of the
Minister’s agreement under s 186, three takes were required on the
Objection
route and three takes (Taylor, FGT and Sutcliffe) would have been
involved in the FGT/Sutcliffe route.
[126] We are in no doubt that consideration had been given by TEL to the
FGT/Sutcliffe route, and that this is demonstrated not only
by the
Sutcliffe’s agreement to an alternative route but by a consideration of
the impact [of] the other route upon the Sutcliffe
and FGT properties. It
is likely that the impact upon the Taylor properties was considered by TEL
to be acceptable, but concerns
had been identified as to the impact on the FGT
and Sutcliffe properties.
[127] We are satisfied that the Western Deviation of the [Mangakaretu]
Alignment was developed in an iterative process, including
consultation with
landowners. It is not for this Court to reach a conclusion as to which is
the best route alternative. We are
satisfied that alternatives have been
considered on a reasonable basis, and that the choice of route is reasonable in
the Wednesbury
sense. Our finding is that there has been an adequate
consideration of sites and routes to achieve the objectives.
The appeal to the High Court
- [19] On
appeal to the High Court, the objectors alleged the Environment Court had
made five errors of law.[27] One
alleged error focussed on the Environment Court’s conclusion that the
Minister had an unfettered discretion in determining
TEL’s applications
under s 186 of the RMA, and was not required to consider any specific
factors including those identified
in s 24(7)(b) and (d) of the PWA. Those
provisions refer respectively to the consideration given to alternative sites,
routes or
methods of achieving the objectives of the Minister or local authority
and whether the proposed takings were “fair, sound,
and reasonably
necessary”.
- [20] The Judge
accepted the objectors’ argument that the s 186 discretion is not
unfettered. As she pointed out, a statutory
power is subject to limits, even if
conferred in unqualified terms, and Parliament must be taken to have intended
that a broadly
framed discretion should always be exercised to promote the
policy and objects of the
legislation.[28]
That raised the question of what the Minister was required to consider, and the
significance of TEL’s knowledge. The Judge
saw it as significant that
s 186 of the RMA is not the source of the Minister’s power to take or
acquire land.[29] That power
is in s 16 of the PWA, and s 186 of the RMA merely allows a network
utility operator to request the exercise of the power.
The Judge considered
that this meant it was necessary for the Minister to consider any relevant
matters. She held:
[47] It follows that it must be the Minister
alone who has the obligation to consider any relevant factors. The exercise of
the statutory
power of compulsory acquisition process involved a recognised
decision-making process beginning with a formal application by the
requiring
authority under s 186 and the provision of the usual briefing material from
Ministry officials. The statutory power and
the decision-making process are the
antithesis of an agent acting for a private entity. Such an approach could, as
Mr Salmon pointed
out, result in deficiencies and inaccuracies being attributed
to the Minister, with no apparent recourse by those affected. I therefore
do not accept that the Minister acts as TEL’s agent in the true sense so
that the Minister is impressed with TEL’s knowledge
for the purposes
of making a decision to take land under the PWA.
- [21] The Judge
did not consider that the Minister was required to consider all the factors in s
24(7).[30] But she held that it was
“implicit and obvious from s 24(7)(b) that the Minister is required to
consider alternative routes
and
methods”.[31] It followed
that the Environment Court had erred in concluding that there was no obligation
on the Minister to consider the relevant
factors in s 24(7)(b) in making the
decision to compulsorily acquire easements over the subject
land.[32]
- [22] A second
alleged error challenged the Environment Court’s decision that any defects
in the acquisition process could be
cured at any point up to the date of
the Environment Court hearing. This alleged error turned on the fact that
the Environment Court
found that the Minister had not considered
alternative routes, and that in fact “no alternatives were ever before the
Minister”.[33] This was
because the s 186 applications were dealt with by staff at Land Information
New Zealand (LINZ) who relied on the evaluations
undertaken by TEL, and the
briefing papers provided to the Minister contained no details of alternative
sites.
- [23] The Judge
considered the Environment Court was entitled to take into account information
that became available following the
making of the s 186
decision.[34] However, the Judge
held that in finding that there had been adequate consideration of alternatives,
the Environment Court had wrongly
relied on the consideration given to
alternatives by TEL. This was wrong because the consideration given to
alternatives by TEL
was not relevant: the Environment Court was required to
examine what consideration had been given to alternatives by the
Minister.[35]
- [24] In respect
of these two grounds of appeal the Judge concluded:
[64] The
Environment Court erred in holding that the Minister’s discretion was
unfettered. It should have approached the question
of consideration of
alternatives under s 24(7)(b) on the basis that this was a factor (among others)
that the Minister was required
to consider.
[65] In examining the adequacy of the Minister’s consideration of
alternative sites, the Environment Court found that there
was no information of
alternative routes before the Minister. As TEL’s knowledge cannot be
attributed to the Minister, it is
clear that the Minister’s consideration
of any alternatives was inadequate. It follows that the Court’s conclusion
that,
notwithstanding the lack of any consideration of alternatives by the
Minister, there had been adequate consideration was an error.
For the same
reason, the Environment Court’s iterative approach proceeded on the
wrong premise that there had been adequate
consideration of alternatives.
- [25] To that
extent, the appeal succeeded.[36]
The Judge rejected the other grounds of appeal. One of those grounds alleged
that TEL’s route selection had been based on
improper and irrelevant
considerations, and that TEL had withheld material information from the
Minister. It was claimed that the
Environment Court had erred in treating the
Minister’s decision as valid when it was defective for these reasons. The
Judge
considered that this ground of appeal did not raise an appealable question
of law. She considered the objectors were effectively
trying to review the
validity of the Minister’s decision rather than advancing a relevant error
of law in the Environment Court’s
decision.[37]
- [26] A further
ground of appeal alleged that the Environment Court had erred in failing to
consider that, as a matter of law, the
Crown could have granted easements over
the OTS land, thereby avoiding the need to acquire private land. There was
another related
complaint, that the Environment Court had not taken into account
the fact TEL failed to challenge the Crown’s decision not
to grant an
easement over the OTS land.
- [27] The Judge
considered the Environment Court’s approach was correct. In the absence
of a challenge by the objectors to the
exercise of the discretion not to make
the OTS land available for construction of the lines, the Environment Court had
been entitled
to proceed on the basis that the decision of the Minister for
Treaty of Waitangi Negotiations not to grant consent was a valid
one.[38] Further, the Judge
considered the Crown was correct in its contention that a requiring authority
need not exhaust legal pathways
in respect of each alternative prior to
focussing on another route.[39] The
question of whether the OTS route was objectively better than the route in fact
chosen was also a question of fact and not a
question of
law.[40]
- [28] The final
ground of appeal concerned the failure of the Minister to provide sufficient
reasons for the taking of the easements
over the objectors’ land. This
was rejected by the Judge on the basis that errors in the Minister’s own
decision-making
were properly within the ambit of judicial review, not an appeal
from the Environment Court.[41]
Accordingly, that ground of appeal was also
rejected.
The relevant statutory
provisions
- [29] Before
dealing with the arguments on appeal to this Court, it will be helpful to
summarise the relevant statutory provisions.
The most relevant for present
purposes are s 186 of the RMA and s 24 of the PWA. However, the
resolution of the issues raised by
the appeal requires those provisions to be
read together, and in each case, having due regard to the role that each
provision plays
in the respective statutory schemes.
The RMA
- [30] We
begin with the RMA. Part 8 of that Act provides for designations and heritage
orders. Designations are defined as provisions
made in district plans to give
effect to a requirement made by a requiring authority under s 168,
s 168A or cl 4 of
sch 1.[42] Network utility
operators may be approved as requiring
authorities,[43] and are generally
companies or public authorities who undertake works of public utilities. The
statute lists various kinds of utility,
as well as allowing for regulations to
define utility operations additional to those set out in the
Act.[44]
- [31] A notice of
requirement may be given to a territorial authority under s 168(1) for a
public work, or in respect of any land,
water, subsoil or airspace where a
restriction is necessary for the safe or efficient functioning or operation of a
public work.
For similar purposes, a territorial authority may issue a notice
of requirement for a public work within its own district for which
it has
financial responsibility under s 168A. In each case, the notice of requirement
is for a designation in a district plan.
Designations inserted under the power
given by cl 4 of sch 1 are in relation to designations sought to be
included in a new district
plan or review of a district plan under s 79. By
contrast, ss 168(1) and 168A contain powers able to be exercised at any time.
- [32] Where what
is proposed is not otherwise allowed by a district plan, a designation will
confer the necessary authority under the
RMA for the work to proceed. That is
because s 176(1)(a) provides that s 9(3), which prohibits the use of land
in a manner that
contravenes a district rule, does not apply to a public work
undertaken pursuant to a designation. Section 176(1)(b) further provides
that
no person may, without the prior written consent of the requiring authority, do
anything in relation to land that is subject
to a designation that would prevent
or hinder the public work.
- [33] A
designation is necessary only if a district plan does not provide that the
proposed public work may be carried out without
a resource consent. In the
present case, for example, the relevant rural environment zone of the operative
Far North District Plan
provided for “above ground utility services
for supply of electricity including lines, structures, and support structures
for
the transformation, transmission or distribution of electricity” as
permitted activities. It appears from the Environment
Court’s report
that TEL’s project may require resource consent in respect of some parts
of the line. However, the Environment
Court recorded that TEL was evidently
confident of obtaining any necessary consent and had not served a notice of
requirement on
the Far North
District Council.[45]
- [34] Section 185
is the first provision of pt 8 which addresses land ownership as opposed
to land use. Under s 185(1), an owner of an estate or interest in
land that is subject to a designation or requirement (including one who may
have
unsuccessfully opposed the relevant designation) may apply at any time to the
Environment Court for an order obliging the relevant
requiring authority to
acquire or lease all or part of the owner’s estate or interest in the land
under the PWA. The Environment
Court is empowered to make such an order in the
circumstances set out in s 185(3). That subsection
provides:
(3) The Environment Court may make an order applied for
under subsection (1) if it is satisfied that—
(a) the owner has tried but been unable to enter into an agreement for the
sale of the estate or interest in the land subject to
the designation or
requirement at a price not less than the market value that the land would have
had if it had not been subject
to the designation or requirement; and
(b) either—
(i) the designation or requirement prevents reasonable use of the
owner’s estate or interest in the land; or
(ii) the applicant was the owner, or the spouse, civil union partner, or
de facto partner of the owner, of the estate or interest
in the land when the
designation or requirement was created.
- [35] Section
185(5) provides that if the Environment Court makes an order under
s 185(3), the owner is deemed to have entered into
an agreement with the
requiring authority responsible for the designation or requirement for the
purposes of s 17 of the
PWA.[46] In addition, where
s 185(5) applies in respect of a requiring authority which is a network
utility operator, s 185(6) provides that:
(a) any agreement shall be
deemed to have been entered into with the Minister of Lands on behalf of the
network utility operator as
if the land were required for a government work;
and
(b) all costs and expenses incurred by the Minister of Lands in respect of
the acquisition of the land shall be recoverable from the
network utility
operator as a debt due to the Crown.
- [36] It is
relevant to note that the connection between s 185 and the relevant PWA
provisions in the case of designations or requirements
of network utility
operators is made by deeming there to have been an agreement between the owner
of the estate or interest ordered
to be taken, and the Minister. But the
Minister is effectively deemed to have entered into an agreement to purchase the
land or
interest concerned “as if the land were required for a government
work”,[47] without having
formed any view as to the appropriateness or otherwise of the work in question
proceeding. The absence of any such
requirement reflects the role of s 185: it
provides relief for an affected landowner from the consequences of a
designation.
- [37] It is in
that context that we now turn to s 186 itself. In a sense, this section is
the converse of s 185, setting out a process
by which a requiring authority
may be authorised to take land it requires for a project or work it intends to
undertake, whether
or not it also requires authority under the RMA to undertake
that project or work. The section provides as
follows:
186 Compulsory acquisition
powers
(1) A network utility operator that is a requiring authority may apply to
the Minister of Lands to have land required for a project
or work acquired or
taken under Part 2 of the Public Works Act 1981 as if the project or work
were a government work within the meaning
of that Act and, if the Minister of
Lands agrees, that land may be taken or acquired.
(2) The effect of any Proclamation taking land for the purposes of
subsection (1) shall be to vest the land in the network utility
operator instead
of the Crown.
(3) Land which is subject to a heritage order shall not be taken without the
consent of the heritage protection authority.
(4) Any land held under any enactment or in any other manner by
the Crown or a local authority may, with the consent of the Crown
or that
authority and on such terms and conditions (including price) as may be agreed,
be set apart for a project or work of a network
utility operator in the manner
provided in sections 50 and 52 of the Public Works Act 1981 (with the necessary
modifications), but
the setting apart shall not be subject to sections 40 and 41
of that Act. Any land so set apart shall vest in the network utility
operator.
(5) Any claim for compensation under the Public Works Act 1981 in respect of
land acquired or taken in accordance with this section
shall be made against the
Minister of Lands.
(6) All costs and expenses incurred by the Minister of Lands in respect of
the acquisition or taking of land in accordance with this
section (including any
compensation payable by the Minister) shall be recoverable from the network
utility operator as a debt due
to the Crown.
(7) Sections 40 and 41 of the Public Works Act 1981 shall apply to land
acquired or taken in accordance with this section as if the
network utility
operator concerned were the Crown.
(7A) This section does not apply if—
(a) the network utility operator is a responsible SPV; and
(b) the land is protected Māori land.
(8) For the purposes of this section, an interest in land, including a
leasehold interest, may be acquired or taken as if references
to land were
references to an interest in land.
- [38] As can be
seen, s 186(1) authorises a network utility operator that is a requiring
authority to apply to the Minister for land
which is required for a project or
work to be acquired or taken. The process takes place under pt 2 of the PWA
“as if the
project or work were a government work within the meaning of
that Act”.
- [39] Proclamations
under s 26 of the PWA are the means by which land is formally taken and vested
in the Crown, or a local authority
which has financial responsibility for the
work. The drafting of s 186(2) reflects the fact that where the
proclamation is made
to authorise the taking of land for the purposes of a
project or work to be undertaken by a network utility operator, the land is
vested in the network utility operator, not the Crown.
The PWA
- [40] Before
we consider s 24(7) of the PWA in detail, it is appropriate to explain the
context in which it comes into effect. The
relevant provisions begin at
s 16. By s 16(1), the Minister is empowered to acquire under the PWA
any land required for a government
work. By s 16(2), every local authority
is empowered to acquire under the Act any land required for a local work for
which it has
financial responsibility. Such acquisitions may be by agreement,
or as the result of a compulsory process.
- [41] Where any
land is required for a public work, s 18(1)(a) provides that the Minister or
local authority must first serve a notice
of the desire to acquire the land on
every person having a registered interest in it. The notice must also be lodged
with the Registrar-General
of
Land.[48] This is followed by an
invitation to the owner to sell the land, with an estimate, after a valuation
carried out by a registered
valuer, of the amount of compensation to which the
owner would be entitled.[49] The
Minister or local authority concerned is required to “make every endeavour
to negotiate in good faith with the owner in
an attempt to reach an agreement
for the acquisition of the
land”.[50]
- [42] If
negotiations are successful, s 17(1) authorises the Minister or local authority
to enter into an agreement to purchase any
land for any public work for which
the Minister or local authority is
responsible.[51] Section 20(1)
provides that if satisfied that the owner of the land has agreed to the land
being acquired and that no private injury
will be done by the acquisition
(or compensation is provided by the Act for any private injury resulting
from the acquisition), the
Minister may issue a declaration in writing that the
land is thereby acquired for the purpose for which it was authorised to be
acquired.
Section 20(2) provides that every declaration issued under
subs (1) has the effect of and is deemed to be a proclamation under
s
26.
- [43] If there is
no response to the invitation to sell, the owner refuses to negotiate, or an
agreement for the sale and purchase
of the land has not been made with the owner
after a period of three months, the Minister or local authority is authorised by
s 18(2)
to proceed to take the land under the Act.
- [44] The
principal provisions of the PWA dealing with the compulsory acquisition of land
are ss 23 and 24. Under s 23(1), when land,
other than land owned by the Crown,
is required to be taken for any public work, the Minister (in the case of a
government work)
or the local authority (in the case of a local work) must take
a number of steps. First, they must cause a survey to be made and
a plan to be
prepared and lodged with the Chief Surveyor showing the land required to be
taken and the names of its
owners.[52] Secondly, they must
cause a notice to be published in the Gazette and twice publicly
notified. This notice must give a general description of the land required to
be taken, a description of the
purpose for which the land is to be used, the
reasons why the taking of the land is considered reasonably necessary and a
period
within which objections may be
made.[53]
- [45] The owners
of the land, and persons with a registered interest in it, must be served with a
notice of intention to take the land
in the form set out in sch
1.[54] The notice contains, amongst
other things, a description of the public work, the purposes for which the land
is to be used and the
reasons why the Minister or local authority considers it
essential to take the interest in the land. It advises that the recipient
has a
right to object, and, if that right is to be exercised, that a written objection
must be sent to the Registrar of the Environment
Court within 20 working days
after service of the notice. It further advises that if the recipient makes an
objection, a public
hearing will be held unless written notice is given to the
Environment Court that the owner wishes the hearing to be held in private.
The
notice also advises that the objector will have the right to appear and be heard
personally or be represented by a barrister
and solicitor or any other person
authorised. The notice concludes with advice about the right to full
compensation under the PWA
if the interest in the land is taken. The recipient
of the notice must be advised that if the amount of compensation cannot be
agreed,
it can be determined in separate proceedings before the Land Valuation
Tribunal.
- [46] Section
23(3) provides that every person having any estate or interest in the land
intended to be taken may object to the taking
of the land to the Environment
Court in accordance with the provisions of the notice. Under s 23(4) every
notice of intention to
take land under s 23 ceases to have effect on the
expiration of one year after the date of publication in the Gazette
unless, prior to the expiration of that period:
(a) a
proclamation taking the land has been published in the Gazette; or
(b) the Minister or local authority has served a further notice confirming
the intention to take the land; or
(c) the intention to take is the subject of any inquiry by the Environment
Court or an ombudsman, or of any application for judicial
review. In such
cases, the notice of intention remains valid for three months after the date of
the Environment Court’s report,
the date on which the Environment
Court receives written notice of the withdrawal of the objection, the date
of the completion of
any inquiry by an ombudsman, or the judicial decision, as
the case may be.
- [47] Section 24
then provides for the processes which take place in the Environment Court after
it receives a written objection under
s 23(3). It relevantly
provides:
24 Objection to be heard by Environment Court
(1) On receiving a written objection under section 23, the Environment Court
shall, as soon as practicable, send a copy of the objection
to the Minister
or local authority, as the case may require.
(2) Within 1 month after receiving a copy of the objection or within such
further period as the Environment Court may allow, the Minister
or local
authority, as the case may require, shall send to the Environment Court and
serve on the objector a reply to the objection
containing the following
information:
(a) the statutory or other authority under which it is proposed to take the
land; and
(b) the nature of the work to be constructed or the purpose for which the
land is required; and
(c) such other matters as may be appropriate having regard to the objections
made and to any practice directions issued by the Environment
Court.
(3) The Environment Court shall inquire into the objection and
the intended taking and for that purpose shall conduct a hearing at
such
time and place as it may appoint.
...
(6) At every such hearing the Minister or the local authority may be
represented by counsel or by an officer of the Minister’s
department or
local authority, as the case may require, and the objector may appear and act
personally or by counsel or any duly
authorised representative.
...
(7) The Environment Court shall—
(a) ascertain the objectives of the Minister or local authority, as the case
may require:
(b) enquire into the adequacy of the consideration given to alternative
sites, routes, or other methods of achieving those objectives:
(c) in its discretion, send the matter back to the Minister or local
authority for further consideration in the light of any directions
given by the
court:
(d) decide whether, in its opinion, it would be fair, sound, and reasonably
necessary for achieving the objectives of the Minister
or local authority, as
the case may require, for the land of the objector to be taken:
(e) prepare a written report on the objection and on the court’s
findings:
(f) submit its report and findings to the Minister or local authority, as
the case may require.
...
(9) At the same time as the Environment Court submits its report and findings
to the Minister or local authority, it shall send a
copy of the report and
findings to the objector, and make copies of them available to the public.
(10) The report and findings of the Environment Court shall be binding on the
Minister or, as the case may be, the local authority.
(11) Any objection filed under section 23 may be withdrawn by the objector at
any time before the court makes its report and findings
under this section.
(12) Where the objection is withdrawn by the objector pursuant to subsection
(11), the court shall not be obliged to make a report
and findings under this
section.
(13) The Environment Court may award such costs as it considers just either
in favour or against the objector, the Crown, or the local
authority.
(14) Subject to sections 299 and 308 of the Resource Management Act 1991, no
appeal shall lie from any report or recommendation of
the Environment Court
under this section.
- [48] The
important points to note about s 24 are as follows. First, consistently
with the other provisions of the PWA we have mentioned,
the section reflects a
dichotomy between the Minister or local authority as the person or body
responsible for the taking of the
land on the one hand, and the objectors to the
taking on the other. The Minister or local authority, as the case may be, must
carry
out the required steps under s 23, including service of the necessary
notice on the landowner and persons with a registered interest
in the land of
the intention to take the land. But any objection is not considered by the
Minister or local authority: they are
simply served with a copy of the
objection by the Environment
Court.[55] The Minister or local
authority must then file and serve a reply to the objection giving the details
required by s 24(2). They
are essentially in the position of being a party
to the hearing of the objection by the Environment Court, at which they will be
the proponent of the taking of the land, and the objectors will be the opponents
of it. Both the proponents and the objectors are
heard by the Environment Court
and may be represented as set out in s 24(6).
- [49] Secondly,
the role of the Environment Court is to submit a binding report on its findings
to the Minister or local authority
having carried out the steps required by
s 24(7). While the Court, in its discretion, can send the matter back to
the Minister or
local authority for further consideration in the light of any
directions which it gives,[56] it is
clear that in such cases it is not sending the matter back for decision.
It is only where an objection is withdrawn by the
objector that the Court
is not obliged to make a report and findings under the
section.[57] Otherwise, it must
proceed to decide whether it would be “fair, sound, and reasonably
necessary for achieving the objectives”
it has ascertained for the land of
the objector to be taken.[58]
- [50] Thirdly,
the requirement of s 24(7)(a) to ascertain the objectives of
the Minister or local authority is plainly, in context,
a reference to the
nature of the work to be constructed or the purpose for which the land is
required. These are the matters to
which reference is made in s 24(2)(b),
and in briefer language (but to similar effect) the requirement in s
23(1)(b)(ii) that the
notice published in the Gazette state the purpose
for which the land is to be used. And the enquiry required by s 24(7)(b) into
the adequacy of the consideration
given to alternatives is clearly into the
alternatives examined by the Minister who, or local authority which, will have
financial
responsibility for the work.
- [51] In summary,
the scheme for the compulsory acquisition of land under the PWA contemplates
that the Environment Court will decide
whether a proposed compulsory acquisition
is fair, sound and reasonably necessary for achieving objectives which
the Minister or
local authority will have developed. While the Court must
consider whether there has been adequate consideration given to alternative
means of achieving the objectives, it is not required or empowered to consider
which option is preferable.
The
interrelationship between the RMA and PWA
- [52] It
is clear from the discussion to this point that the PWA contemplates the
compulsory acquisition of land either by the Minister
or by a local authority.
It does not in terms provide for compulsory acquisition of land by a network
utility operator that is a
requiring authority.
- [53] It is
s 186 of the RMA which makes that possible. It does so by the simple
expedient of empowering the network utility operator
to apply to the Minister to
have land required for a project or work acquired or taken under the PWA
“as if the project or
work were a government work within the meaning of
that Act”. The acquisition or taking may occur “if the Minister of
Lands agrees”. In simple terms, s 186(1) has the effect that pt 2 of the
RMA applies to the proposed work of the network utility
operator as if it were a
government work.
- [54] We return
to s 186 of the RMA and its implications below.
The appeal
Appellant’s argument
- [55] In
accordance with this Court’s suggestion in granting leave to appeal,
Mr Isac QC addressed the Minister’s principal
arguments on
appeal under two headings: first, the role and obligations of the Minister
under s 186 of the RMA and second, whether
the focus of the enquiry
required by s 24(7)(b) of the PWA should be on the consideration of
alternatives by the Minister, by the
requiring authority or by both.
- [56] On the
first issue, Mr Isac submitted that s 186 of the RMA contains a
“consent power”, in respect of which it is
for the Minister to
determine what is relevant to the manner and intensity of the enquiry into any
matter. The Minister’s
role is supervisory and involves carrying out a
check on the work carried out by the requiring authority to ensure that it has
made
an analysis of alternatives sufficient to enable the process to
proceed to the next statutory phase. To perform the Minister’s
function,
and in accordance with the LINZ Standard for the Acquisition of Land under the
PWA
(LINZS15005),[59]
the Minister receives details of the assessment of alternatives made by the
requiring authority, and decides to accept or decline
the application under
s 186 after considering that assessment. It is not the Minter’s role
to consider the merits of the proposal
beyond satisfying himself or herself that
the proposal is one that is capable of being confirmed by the Environment Court.
- [57] It is for
the Court to decide whether the proposal should be accepted, applying
s 24(7) of the PWA. Mr Isac submitted that in
carrying out its function
the Environment Court can consider any relevant information available as at
the date of the hearing, whether
or not the information was before the Minister
when he or she exercised the power under s 186(1). In accordance with what
Mr Isac
described as this “iterative approach”, changes to the
project might occur after the Minister has made a decision. For
example,
landowner consultation and negotiation might result in changes to the final
location of necessary infrastructure. In addition,
given the inevitable
time-lapse between consideration by the Minister and the hearing before the
Environment Court, updated information
might disclose errors in conclusions
relied on at an earlier stage. The High Court was therefore wrong to conclude
that the relevant
consideration of alternatives was completed when the Minister
decided to give her agreement under s 186.
- [58] Mr Isac
argued the High Court was wrong to conclude that the Minister had not considered
alternatives, because no alternatives
were ever before the
Minister.[60] While it was correct
that the Minister was not presented with alternatives to choose between, she had
been adequately advised of
the alternatives considered by TEL as the requiring
authority, and that was all that was required for the purposes of s 186.
It
also followed that the High Court was wrong to conclude the Environment Court
erred when it held that there had been adequate consideration
of
alternatives.
- [59] Mr Isac
submitted that in carrying out its enquiry under s 24(7)(b) of the PWA, the
Environment Court is not limited to any consideration
by the Minister when
assessing an application under s 186 of the RMA. Rather, the Environment
Court’s focus is on the adequacy
of all consideration of alternatives up
to the date of its enquiry, whether by the requiring authority, or the Minister,
or both.
Mr Isac argued that the statutory scheme, which involves steps by
both the requiring authority and the Minister, as well as receipt
by the
Environment Court of all relevant information, does not support the High
Court’s conclusion that the Minister “alone”
must consider
alternatives.[61]
Respondents’
argument
- [60] For
the respondents, Mr Salmon first submitted that the role of the Minister when
making a decision under s 186 of the RMA is
to decide whether to exercise
the powers of acquisition under s 16 of the PWA. In making that
decision, the Minister is obliged
to consider mandatory relevant factors,
including alternative routes. Secondly, Mr Salmon submitted it is the adequacy
of the Minister’s
consideration of alternatives that is examined as part
of the s 24(7)(b) enquiry.
- [61] In support
of his first contention, Mr Salmon submitted that although the Minister’s
power in s 186 of the RMA is broadly
framed, the Minister is obliged to
consider any mandatory relevant considerations when making his or her decision.
Here, he submitted
the mandatory considerations were as
follows:
(a) Alternative sites, routes or other methods of achieving
the relevant objectives. Mr Salmon submitted this was clear from the
statutory
framework, and s 24(7)(b) of the PWA in particular.
(b) The information required to be provided to the Minister in accordance
with LINZS15005.
(c) The contents of the s 186 applications.
- [62] Mr Salmon
contended it was misconceived to describe the Minister’s role under
s 186(1) as “supervisory”. The
plain words of s 186
provide that a private network utility operator may apply to the Minister to
have land taken by the Crown that
will vest in the network utility operator at
the time of proclamation. The process requires the active use of the
Minister’s
power to take private land. Mr Salmon submitted the
Minister’s role in the circumstances cannot be a passive one. Once the
s 186 application has been made and granted, the applicant has no
further role until the Governor-General issues a proclamation vesting the land
in
the applicant. Even if the landowner files an objection, the network utility
operator is not a party to the proceedings in the Environment
Court.
- [63] Mr Salmon
submitted that at the s 186 stage, the Minister must decide whether to
exercise his or her powers of acquisition under
the PWA. The Minister can
proceed to take the land if he or she is unable to negotiate an outcome three
months after the acquisition
process has been initiated. It would not make
sense if a private entity, a network utility operator, could initiate the
Crown’s
coercive powers of acquisition on the basis of a flawed, incorrect
or misleading route-selection process with the only check occurring
when the
matter comes before the Environment Court after an objection has been filed.
This would be to reduce the exercise of the
Minister’s power to a
rubber-stamping exercise. Such a conclusion would be inappropriate given that
compulsory acquisition
by its nature results in the “trammelling” of
private property rights.
- [64] Mr Salmon
submitted the High Court was right to uphold the Environment Court’s
conclusion that “no alternatives were
ever before the
Minister”.[62] On this issue
the High Court noted that the s 186 applications were dealt with by LINZ
employees who relied on the evaluations undertaken
by
TEL.[63] While the report provided
by TEL provided some background information on how route selection was made, Mr
Salmon submitted there
was insufficient information on alternative routes to
allow a proper consideration of alternatives by the Minister.
- [65] Mr Salmon
also noted that LINZS15005 requires the s 186 applications to provide an
“analysis of requirement”, including
“details of the
assessment of any alternative sites, routes or methods of achieving the
applicant’s
objectives”.[64] Effectively
then, the Crown’s own application criteria required sufficient information
to allow alternative routes to be considered.
Similarly, Mr Salmon argued that
the Minister is obliged to consider the contents of the s 186 applications. He
submitted it was
self-evident that an application needs to be considered before
any decision can properly be made to grant it.
- [66] In this
case, Mr Salmon said the applications were inadequate because they contained
insufficient information as to alternatives,
as the High Court held. The
Minister had taken a fundamentally passive approach, with the result that her
decision was affected
by substantive defects in TEL’s own approach. In
fact, TEL misled the Minister as to the necessity of the taking, by failing
to
advise that its board had not yet decided whether to construct the transmission
line, and by representing the objection route
as the only economic and
practicable route available when there were multiple potential routes, two of
which TEL regarded as preferable.
The most preferred route was in fact over the
OTS land, but this was abandoned by TEL because the Minister for Treaty of
Waitangi
Negotiations refused to grant an easement. The second preferred
route was abandoned on grounds that should have been regarded as
objectionable
and disqualifying: specifically, it was claimed, because of political
connections of an affected landowner.
- [67] On the
second issue, Mr Salmon submitted the High Court correctly held that under
s 24(7)(b) of the PWA the Environment Court
must enquire into the adequacy
of the Minister’s consideration of alternative sites and routes. This
reflected the fact the
decision to take private land pursuant to an application
under s 186 is the Minister’s decision to make, and involves exercise
of
the Minister’s power. While it was correct to treat the relevant
objectives to be considered under s 24(7)(a) as being
those of the requiring
authority, it would be an unjustified leap of logic to conclude this meant that
the consideration of alternatives
under s 24(7)(b) was limited to the
consideration carried out by the requiring authority.
- [68] Mr Salmon
argued that would essentially contemplate the abdication of decision-making
power by the Minister, and had that been
the intention of the legislature, it
would have been set out expressly in the statute. Mr Salmon submitted the High
Court’s
approach was correct, and consistent with an earlier
High Court decision, Kett v Minister for Land
Information.[65]
- [69] Mr Salmon
addressed various other arguments purportedly in support of the High Court
judgment but in fact based on alleged errors
in the Environment Court’s
decision. We deal separately with those issues later in this
judgment.
Decision
The nature of the Minister’s power under
s 186 of the RMA
- [70] The
words “if the Minister ... agrees” in s 186 of the RMA are
couched in open language consistent with the conferral
of a broad discretion.
But it is trite law that there is no such thing as an unfettered discretion. As
was said by the Supreme
Court in Unison Networks Ltd v Commerce
Commission:[66]
[53] A
statutory power is subject to limits even if it is conferred in unqualified
terms. Parliament must have intended that a broadly
framed discretion should
always be exercised to promote the policy and objects of the Act. These
are ascertained from reading the
Act as a whole. The exercise of the power will
be invalid if the decision maker “so uses his discretion as to thwart or
run
counter to the policy and objects of the
Act”.[67]
A power granted for a particular purpose must be used for that purpose but the
pursuit of other purposes does not necessarily invalidate
the exercise of public
power. There will not be invalidity if the statutory purpose is being pursued
and the statutory policy is
not compromised by the other
purpose.[68]
- [71] The
statutory context in which the Minister’s power is to be exercised
necessarily establishes broad parameters for the
exercise of the power. The
purpose of s 186(1) is to authorise a network utility operator to apply for
the Minister’s agreement
to the proposed taking or acquisition of land
required for a proposed project or work, and to give the Minister the power to
decide
whether or not to agree to the taking of the land. Although the
Minister’s power in s 186(1) is exercised prior to the commencement
of the
formal PWA processes, it is implicit, having regard to the statutory scheme
comprising the relevant provisions of the RMA
and the PWA, that the power must
be exercised on the basis that in the case of objection the issue of whether or
not the land should
be taken will be determined by the Environment Court.
- [72] We consider
this means the Minister must be satisfied that the proposed taking is capable of
meeting the statutory test in s
24(7)(d) that the Environment Court would apply
if there was an objection: namely that it is fair, sound and reasonably
necessary
for achieving the objectives of the network utility operator that
the land should be taken. That requires the Minister to have sufficient
information to ascertain what the objectives are, and also that there has been
appropriate consideration of alternative sites, routes
or other methods of
achieving those objectives. But we do not consider it is the Minister’s
role to decide which of a number
of alternatives should be pursued. Rather, it
is for the Minister to decide whether the proposal which is the subject of the
s 186
application can meet the statutory test.
- [73] The open
language in which the power is conferred on the Minister, however, suggests that
the Minister’s decision might
also properly be affected by policy
considerations relevant to the proposed project or work. The Minister is being
asked to lend
the coercive powers of the state to the acquisition of land by
another party. It is inappropriate in the circumstances to suggest
that
there can be no room for the application of government policy (provided that
policy does not frustrate the purpose of the Act)
and broad considerations of
where the public interest lies. Putting that another way, given the nature of
the Minister’s power,
we think it would be wrong to characterise taking
into account broadly relevant government policy as using the Minister’s
discretion
to run counter to the policy and objects of the legislation. The
relevant legislative policy and objects here are derived not just
from
considering the PWA, but also the RMA, which requires all decision-makers to
take into account the principles of the Treaty
of
Waitangi.[69]
- [74] For
example, a proposal that otherwise appeared meritorious might be considered
inappropriate because of its implications for
land of particular cultural or
spiritual value to Māori. Similarly, the facts of the present case
included consideration of
a potential route (the apparently less costly OTS
route) over land which was land‑banked for the provision of potential
redress
in the settlement of claims under the Treaty of Waitangi. We consider a
decision made in good faith not to consent to the acquisition
of such land under
s 186(1) would be appropriate even if the project might otherwise be
considered suitable to meet the objectives
of a network utility operator. It is
also possible that projects might be advanced by network utility operators that
might be contrary
to central government policies relevant to climate change or
the preservation of natural landscapes of outstanding quality or other
environmental policies.[70] Again,
in such cases the Minister might lawfully withhold agreement under
s 186(1).
- [75] These
conclusions are supported by the more detailed reasoning that
follows.
The role of the Minister
- [76] Section
186 of the RMA was discussed in the judgments delivered in the Supreme Court in
Seaton v Minister for Land
Information.[71] The question
in that case was whether the Minister had properly invoked the compulsory
acquisition powers under the PWA to acquire
easements over land necessary to
relocate supporting towers for electricity lines owned by a network utility
operator because of
the widening of the carriageway forming part of State
Highway 1 on which the towers had been located. It was held by the majority
that the easements were not reasonably required for the widening of the road,
but rather for the conveyance of electricity, the latter
not being
undertaken by the Crown.[72] The
correct course for acquisition of the easements would have been for the utility
company to apply under s 186(1) of the RMA for
the Minister to agree to the
compulsory acquisition of the easements.
- [77] The issue
in that case does not arise here. We note however that Elias CJ observed that
whether land is taken under s 16(1)
of the PWA for a government work or
whether it is taken under s 186 of the RMA for a project or work of a
network utility operator,
the procedures are those contained in pt 2 of the PWA.
She noted that “[i]n both cases the acquisition is conducted by the
Minister of Lands either for himself or for the network utility operator, as the
case may be.”[73] She
contrasted the position of network utility operators and local authorities,
pointing out that the latter are empowered to act
directly in the case of local
works for which they have financial responsibility and “not through the
Minister or under any
deeming provision such as that which treats applications
on behalf of network operators as if their proposed works were Government
works”.[74]
- [78] William
Young J (writing for himself and McGrath J) explained that when the PWA was
enacted in 1981, utilities were generally
publicly owned and, where that was not
the case, usually operated under and exercised statutory powers conferred in
private Acts
of Parliament.[75]
However, the corporatisation and privatisation of the functions of such
utilities which subsequently occurred “significantly
reduced the scale of
central and local government utility activities and thus the potential scope for
compulsory acquisition”.[76]
Section 186 was designed to address the “resulting
lacuna”.[77]
- [79] Later, in a
passage which we think is directly relevant here, after setting out s 24(7)
of the PWA William Young J wrote:
[83] Where s 186(1) of the
Resource Management Act has been invoked, the references to
“Minister” in (a) and (d) must
be read as a reference to
the network utility operator (because the proposed taking will be to give
effect to its objectives, rather
than those of the Minister). ...
- [80] We
respectfully agree with that approach. It is similar to the reasoning of
Chambers J (who also wrote for Glazebrook J), who
emphasised the importance of
the Minister following the correct procedure by referring to the effect on
matters relevant to the Environment
Court’s inquiry under
s 24(7).[78] Thus, if
s 186 were not invoked, the Environment Court’s focus would be on the
extent to which the easements were required
for road widening purposes. On the
other hand, if s 186 had been
invoked:[79]
... the
focus would be on the utilities’ need for these easements compared with
other relocation measures that might be open
to them. The difference is subtle,
but there is a difference.
- [81] We think
the discussion in Seaton implies that where s 186 of the RMA has
been relied on, the enquiry into the adequacy of the consideration of
alternatives under
s 24(7)(b) of the PWA must embrace the consideration of
alternatives by the network utility operator.
- [82] In this
case, the Judge took a different view. Her essential reasoning was set out at
[47] of the High Court judgment, which
we have quoted
above.[80] While we agree that the
Minister’s particular statutory role is not captured by describing her as
the agent of the network
utility operator, we consider the Judge’s
statement that “it must be the Minister alone who has the obligation to
consider
any relevant factors” is
incorrect.[81] If by saying that
the Judge intended to imply that the Minister must personally consider
alternatives additional to those that the
network utility operator has
considered, or decide which of the alternatives considered should be preferred,
we do not consider that
would be in accordance with the statutory scheme. We
accept that the Minister might reach the view, after considering an application,
that further alternatives should be considered and decline the application for
that reason. That would be an available course given
the openness of the
statutory language. But that is a different proposition from the Judge’s
conclusion that the Minister
alone has the obligation to consider any relevant
factors.
- [83] The
proposal after all is that of the network utility operator, which will
inevitably be much more familiar with the purpose
of and need for the intended
works. It will have developed the proposal having identified its objectives for
the project or work.
As all the Judges seem to have accepted in
Seaton, by the stage s 24(7)(a) and (d) of the PWA are
reached it is the network utility operator’s objectives that are being
considered.[82] This seems to us
inconsistent with the notion that the Minister has the central role contemplated
by the High Court at the earlier
stage of the process. It also seems
inconsistent with the idea that in a case involving s 186 of the RMA, it is
the adequacy of
the Minister’s consideration of alternatives that is to be
assessed under s 24(7)(b) of the PWA.
- [84] The
statutory scheme in fact assumes that the network utility operator will have
identified its objectives, the means of achieving
them and a preferred option
prior to making an application to the Minister under s 186(1). The
Minister is the Minister for Land
Information, and could not be expected to have
access to institutional knowledge and expertise equivalent to that of the
network
utility operator, so far as assessment of the technical and economic
feasibility of different alternatives is concerned. Nor is
there any indication
in the statutory scheme that the Minister has the role of deciding that the
proposal is one that should be approved
on the merits. That is an issue
deliberately left to the Environment Court where there is an
objection.
- [85] We do not
consider that in deciding whether or not to agree to a request under
s 186(1) of the RMA the Minister is required to
be satisfied that the
proposal will definitely meet the requirements of s 24(7) of the PWA. It
will be enough if the Minister is
satisfied it is capable of doing so. The
s 186(1) decision occurs prior to the matter being considered by the
Environment Court.
If the legislative intent was that both the Minister and
the Environment Court were required to be satisfied of the same matters
it would
be surprising if the statutory regime specified the criteria to be applied at
the subsequent stage, but not the former.
We think that if that was what was
intended, the legislature would have stipulated the considerations relevant to
the Minister’s
decision, and then said they should also govern
the Environment Court’s decision. The Environment Court could then
have been
placed in a role analogous to its role in determining an appeal in
exercise of its functions under the RMA, but that is obviously
not what s
24 of the PWA contemplates.
- [86] There are
also practical reasons why requiring the Minister to be satisfied the proposal
will definitely meet the s 24(7) requirements
would not work. When the
Minister is acting under s 186(1) of the RMA, the PWA procedures will not
have been commenced. Whether
or not a particular proposal will be accepted by
the affected landowners or whether there will be objections cannot at that
point
be ascertained. And any consideration of the merits at the s 186
stage would take place in the absence of the information produced
as a result of
the receipt and consideration of objections, and without there being any
equivalent process designed to achieve input
from affected parties, which is a
feature of the hearing of objections by the Environment Court. It is
consistent with this that
the Environment Court is the body which actually
exercises the power to decide whether or not the land of the objector may be
taken.
Its decision is binding on the
Minister.[83] In the present case
information from objectors was referred to in the briefing materials given to
the Minister, including criticisms
of TEL’s failure to pursue the OTS
route and other issues raised by the objectors’ solicitors. Although this
added to
the material before the Minister relevant to the question of
alternatives, and it was open to the Minister to consider it when making
the s
186 decisions, it was not the Minister’s role under s 186 to reach a view
on the merits of different routes and the provision
of this information in the
present case did not require the Minister to do so.
- [87] In
addition, negotiations with those affected may well result in modifications to a
proposal by the time the matter reaches the
Environment Court. Those changes
may be designed to respond to issues that have been raised by objectors. We do
not see any suggestion
in the legislation that this iterative approach cannot
occur. Indeed, the possibility of modification is inherent in the concept
of
mandatory prior negotiation, which is a central feature of the procedures
required by pt 2 of the PWA.[84] It
can be said in fact that the statutory procedures must leave room for the
ongoing consideration of alternatives after a notice
of intention to take land
has been given under s 23. It would be artificial and inconsistent with
the obligation to negotiate in
good faith if the serving of the notice of
intention to take were seen as necessarily bringing negotiations to an end.
Similarly,
negotiation might result in the withdrawal of a notice of intention
to take under s 23(8) on the basis that it was no longer considered
necessary to
take the land.
- [88] The fact
that a proposal is initiated by a network utility operator does not put it in an
exceptional category in this respect.
On the contrary, s 186(1) has clearly
been drafted with the intention that the PWA procedures will apply.
- [89] Mr Salmon
placed considerable emphasis on the fact that it is only if the Minister agrees
under s 186 that the compulsory acquisition
procedures may be implemented.
As noted above, he submitted that the Minister must decide at the s 186
stage to exercise the powers
of acquisition under the PWA. Once the Minister
has agreed, if unable to negotiate an outcome after three months he or she can
proceed
to take the land.[85] Mr
Salmon submitted the prospective exercise of the Crown’s coercive powers
of acquisition means the Minister needs to be
in a position to ensure that using
those powers is appropriate, which must include the consideration of
alternatives by the Minister.
- [90] However, it
is not accurate to describe the Minister’s role under s 186 as
involving a decision to exercise the powers
of compulsory acquisition. If the
affected landowners agree, there will be no compulsory acquisition, and no use
of the Crown’s
coercive powers. There may be a proclamation, but that
will be implementing the agreement. Absent agreement by the affected
landowners,
the acquisition will be able to proceed only if the Environment
Court considers there has been an adequate examination of
alternatives,[86] and reaches the
evaluative judgement that the land should be
taken.[87] If the Environment Court
were to reach the view that the consideration of alternatives was inadequate it
could send the matter back
to the Minister for further
consideration,[88] or simply report
adversely on the proposal.
- [91] These
possible outcomes do not mean the Minister has the sole responsibility to
consider “any relevant factors” as
the High Court
held.[89] On the contrary, they are
consistent with the fact that where a network utility operator is involved, it
will have assumed primary
responsibility for the consideration of alternative
means of achieving its objectives. Of course it is open to the Minister, in
an
appropriate case, to decide that the consideration of alternatives has been
inadequate. But where the Minister agrees to the
land being taken or acquired
under pt 2 of the PWA, and the matter proceeds to the Environment Court, the
question the Court will
ask is whether there has been adequate consideration
given to the alternatives. The Court’s obligation under s 24(7)(b) is
to
enquire into that issue and report on it, as well as the other matters it is
required to consider. It is not directed to enquire
into whether the
Minister personally has given adequate consideration to
alternatives.
- [92] In
describing the nature of the Minister’s decision under s 186 as
“supervisory”, Mr Isac relied on the decision
of the Supreme Court
in Schmuck v Opua Coastal Preservation
Inc.[90]
That case required the Court to consider the power given in s 48(1)(f) of
the Reserves Act 1977 to the administering body of a reserve
to grant rights of
way and other easements over any part of the reserve for various purposes in
respect of land not forming part
of the reserve. The power of the administering
body to grant the rights of way and other easements was exercisable “with
the
consent of the Minister and on such conditions as the Minister thinks
fit”.[91] The Supreme Court
considered that the terms “check” and “supervisory” were
useful shorthand descriptions
of the role of the Minister in giving consent to a
grant,[92] but
added:[93]
... we do not
consider that the Minister is under any obligation in process terms to
reconsider the matters taken into account by
the administering body in granting
the easement, so long as they are within the administering body’s
powers.
[131] In characterising the Minister’s power as supervisory, we are not
intending to create any artificial limit on that power.
All we are saying is
that there is no requirement to re-run the process already undertaken by the
administering body of the reserve.
However, if the Minister takes a different
view of the situation from that taken by the administering body, there is
nothing to
stop the Minister refusing to consent to a decision that the
administering body has made lawfully and which the administering body
considers
is reasonable. We agree with the Court of Appeal that the Minister is free to
take a different view from that of the administering
body as grantor. But there
is also nothing requiring the Minister to reconsider matters decided by the
administering body and the
Minister does not act unlawfully if he or she does
not do so.
- [93] The Court
agreed with a submission that the Minister’s decision is not a
rubber‑stamping exercise. However, in the
absence of any statutory
requirements as to process, it was for the Minister to determine what was
relevant to the decision, and:[94]
... the manner and intensity of the inquiry into any such matter
(beyond the essentials of checking that the statutory process has
been
undertaken by the administering body and that the easement was lawfully
granted), subject only to challenge on grounds of unreasonableness.
- [94] Mr Salmon
invited us to distinguish Schmuck on the basis that
the administering body had the power to grant the easement and the
Minister’s role in granting consent was
simply a final check on the
exercise of that power. In those circumstances it was appropriate to describe
the power as “supervisory”,
especially as the Minister’s
consent was being given to a voluntary granting of an easement by the owner of
the land. Moreover,
the decision to grant the easement was subject to specific
requirements as to compliance with the RMA, and mandatory public notification
and consideration of public
submissions.[95] Given that the
Minister’s consent power was being exercised after a prior decision-making
process that was public and contestable,
a narrow view of the power was
understandable. By contrast, in the present case requiring the Minister to
consider alternative sites
and routes when acting under s 186 of the RMA
would not be to require repetition of a process already undertaken by another
public
body, the situation that applied in Schmuck.
- [95] We agree
that the statutory setting here is clearly different from that considered by the
Supreme Court in Schmuck, and the case can be distinguished for the
reasons advanced by Mr Salmon. Nor do we think the word
“supervisory” an accurate
description of the Minister’s role
under s 186(1). Where s 186 is engaged the Minister is doing more than
approving an action
which the network utility operator is itself able to carry
out. The Minister is taking a crucial step to facilitate the project,
which
could not proceed without the Minister’s agreement. For these reasons we
think the “supervisory” label is
inappropriate and might in fact be
misleading.
- [96] However,
some aspects of the reasoning in Schmuck may properly be applied by
analogy. In both cases the Minister’s power is expressed in open language
without reference to
statutory criteria governing its exercise, and in both
cases the exercise of the Minister’s power is contingent on another
entity
making a decision, subject to public rights of participation and process. In
this case, the result of the Minister’s
agreement under s 186(1) of
the RMA is that the taking may proceed, but, if the taking is opposed, it may
occur only after the Environment
Court agrees, after carrying out its function
under s 24(7) of the PWA. As in Schmuck, there is a justification
for reading the relevant statutory provisions in a way that avoids duplication
of process, especially when
the PWA gives such a pivotal role to the Environment
Court.
- [97] Further, as
in that case, we see nothing in the statutory language which prevents the
Minister from reaching his or her own view
as to the intensity of the enquiry it
is appropriate for him or her to undertake. Doubtless the Minister should be
satisfied that
the proposal is one that is capable of passing muster in the
Environment Court, but we do not see how a reasonable decision to that
effect
could render unlawful the PWA process that ensues. And importantly, as
mentioned above, we consider the broad statutory language
in s 186(1) of
the RMA leaves room for the Minister to consider relevant government policies
that might make it inappropriate to
facilitate a project or work proposed by a
network utility operator by agreeing to the taking or acquisition.
- [98] The Judge
found persuasive the discussion of s 24(7)(b) of the PWA by High Court
in Kett v Minister for Land
Information,[96] a case
on which Mr Salmon also relied. The case involved a proposed acquisition of
land for the purposes of the realignment of State
Highway 1 between Orewa and
Puhoi. In the present case, the Judge noted that the Environment Court’s
duty to enquire into
alternatives under s 24(7)(b) presupposed that someone
would have considered the alternatives before the matter reaches the Environment
Court, and held that “[t]hat person must, self‑evidently, be the
Minister”,[97] citing what
Paterson J said in
Kett:[98]
If this
phrase is given its normal plain and dictionary meaning, the Court was required
to consider whether the Minister sufficiently
and with due regard, chose the
route, after taking into account circumstances which were reasonably relevant
relating to that route
and alternative routes. I see no reason, from the
context of the Act or statements made when the Bill was introduced, to give the
term any other meaning. ... The Court was not itself required to determine
whether the route was the most suitable of the available
alternatives. Its role
was to ensure that the Minister had carefully considered the possibilities,
taken into account relevant matters
and come to a reasoned decision.
- [99] We do not
think this statement has the significance that the Judge afforded it, for a
number of reasons. First, in the quoted
passage Paterson J was giving reasons
for rejecting an argument advanced on behalf of an objector that the Environment
Court had
applied the wrong test in determining that the Minister had given
adequate consideration to alternative routes. It was submitted
that the
Environment Court should have required the Minister to establish that there was
no alternative to the option that required
the compulsory acquisition of land to
which the landowner had objected. Paterson J disagreed. But the discussion was
about the
role of the Environment Court, not the Minister.
- [100] Secondly,
the requiring authority was Transit New Zealand, a Crown entity responsible for
the designation of the realigned section
of the State Highway. The case did not
involve a network utility operator or, therefore, a request to the Minister
under s 186 of
the RMA. For this reason, it does not assist with the
definition of the Minister’s role under that section.
- [101] Thirdly,
although in the passage set out above Paterson J referred to the Minister
choosing the route, the actual discussion
in the judgment, about whether
there was evidence on which the Environment Court could have concluded
the Minister had given adequate
consideration to alternative routes,
focused on the consideration of alternatives by Transit New
Zealand.[99] The Judge did not draw
any distinction between the Minister and Transit New Zealand insofar as the
consideration of alternatives
was concerned, and it does not appear to have been
argued that he should have. We suspect that reflects the fact that the
Environment
Court defined the relevant objectives of the Minster as
being:[100]
... to
enable Transit to give effect to the proposal to construct and operate the
Realignment of State Highway 1 between Orewa and
Puhoi generally in accordance
with the designation for it in the district plan as part of a safe and efficient
highway system.
- [102] In any
event, we consider it is clear from the relevant discussion in the judgment that
the High Court considered the relevant
history of investigation of various
alternatives by Transit New Zealand, which led to the development of the
particular proposal,
should be considered as relevant to the enquiry under
s 24(7)(b). We do not consider the Court was requiring a number of
alternatives
to be put before the Minister to enable him to choose between
various alternatives at the stage of deciding to give notice of an
intention to take land for a particular proposal.
- [103] In this
case, having held that the Minister was required to consider alternative routes
and that the Environment Court was required
to examine the adequacy of that
consideration, the Judge thought it significant that the evidence before the
Environment Court from
Mr Sun, a LINZ official, was that “no alternatives
were ever before the
Minister”.[101] The Judge
took that quotation from the Environment Court’s report, but Mr Isac
drew our attention to the context in which
it appeared. The Environment Court
recorded a submission made to it by Mr Salmon that the Minister should have
considered alternative
routes, and should then have chosen between
them.[102] It then
continued:[103]
Mr Sun
noted that no alternatives were ever before the Minister. The Ministry of Land
Information deals with the application made
by the requiring authority.
Although the report by the requiring authority does indicate some background
information on how the
route selection was made, we agree that this cannot bind
the Minister at the s 186 decision stage.
- [104] Mr Isac
noted that in this part of its report the Environment Court was dealing with Mr
Salmon’s submission that the s
186 applications should have set out
alternatives for the Minister to choose between. Mr Sun’s evidence was
effectively that
an application setting out two options and requiring the
Minister to choose the route she preferred would not be provided to the
Minister. He explained:
It’s not my understanding of the
s 186 process ... It’s a requirement that the applicant
identifies what it’s applying
for. The Minister does not pick (a),(b) or
(c). She decides “yes” or “no”. ... [If an applicant
advised
that there were two equally good routes] ... the relevant official would
say to the applicant, “decide which one’s better
and tell us
why”.
- [105] Mr Isac
contrasted this with the proposition that no information was before the Minister
about the alternatives that had been
examined, which was not correct. He
emphasised in this respect that the material provided by TEL for the purposes of
the s 186 applications
was substantial and dealt with a number of relevant
matters, including the need for the project, the efforts that had been made to
negotiate agreements with affected landowners and the assessment of
alternatives. The applications identified four routes that TEL
had considered,
and were placed before the Minister with the briefing papers prepared by LINZ
officials, which referred the Minister
to the various parts of the applications
where the assessment of alternatives was addressed. The papers given to the
Minister included
a “decision sheet” which she marked to indicate
that the consideration of alternatives had been assessed.
- [106] The
Environment Court found that there had been adequate consideration of
alternatives by TEL, and that was sufficient for the
purposes of its enquiry
under s 24(7)(b) of the
PWA.[104] On the view we take,
the summary given by LINZ officials to the Minister of the consideration of
alternatives by TEL was adequate
for her to reach the view that TEL’s
applications were capable of achieving a favourable report from the Environment
Court.
A second appeal on questions of law is not an appropriate proceeding for
the merits of the Environment Court’s report to be
challenged.
- [107] We note
further that it is clear from the Minister’s decision that she took into
account the contents of the applications
made by TEL, which were attached to the
briefing papers prepared for her by LINZ officials. The arguments that she did
not consider
the contents of the applications, and that the requirements of
LINZS15005 were not met, appear to be further manifestations of the
argument
that the Minister was obliged to personally consider and decide between the
alternatives. Those arguments cannot be sustained
for the reasons we have
earlier discussed.
Other
issues
- [108] Mr
Salmon endeavoured to support the outcome in the High Court on grounds
additional to those given by the Judge. He submitted
in particular that the
Environment Court erred by:
(a) treating the Minister’s
decision as valid when it was defective because TEL’s route selection was
based on improper
and irrelevant considerations (including a landowner’s
alleged political connections) and the s 186 applications contained
“fatal
omissions”;
(b) failing to consider that, as a matter of law, the Crown could have
granted easements over the OTS land without requiring compulsory
acquisition;
and
(c) treating the reasons given in the Minister’s notice of intention to
take land as sufficient, when they were not.
Improper/irrelevant considerations and
omissions
- [109] The
first issue was based on the contention that TEL had decided against one of the
potential routes on the basis that the landowner
concerned was connected to a
Minister of the Crown. Mr Salmon secured a concession in
cross‑examination in the Environment
Court that the relationship had been
considered in the route selection process, a matter that had not been referred
to in the briefing
papers given to the Minister. However, the Environment Court
rejected this contention, noting that the landowner concerned had in
fact signed
an agreement to grant an easement in respect of his property, although in a
different location and for a shorter distance
than had been proposed at one
stage.[105] The Court considered
that the previous proposal would have had a greater impact on some parties than
the route in fact selected.[106]
In the High Court, the Judge considered the issue did “not raise an
appealable question of
law”.[107] She expressed
the view that the Minister’s decision-making process could not bear on an
appeal against the Environment Court’s
decision.[108]
- [110] We think
it would be possible in an appropriate case for the Environment Court to
consider, in the course of its inquiry under
s 24(7) of the PWA, the
processes that had been followed by the Minister in making a decision under
s 186(1) of the RMA. An unfair
process might have the implication that
there had been an inadequate consideration of alternatives or justify a finding
that it would
not be fair for the land of the objector to be taken. In either
case, it would need to be shown that what had occurred had a material
impact on
the decision. There is no basis upon which we could reach that view in this
case. We do not consider any error has been
demonstrated.
- [111] As to the
suggestion of a “fatal omission”, the argument is that TEL’s
applications to the Minister had been
premised on urgency and necessity whereas
board documents made available prior to the Environment Court hearing
demonstrated that
the board had not yet decided to proceed with constructing the
line, and that diesel generation might be a possible means of avoiding
the need
for the line altogether. The Environment Court considered this argument in the
course of ascertaining TEL’s objectives.
It decided that the relevant
objectives were the construction of lines for a network distribution system, not
the production of
power.[109] Mr
Salmon also contended that TEL misrepresented the objection route as the
“only practical and economic route”, and
withheld its costing
modelling for the various routes from the Minister.
- [112] The High
Court considered that these various omissions could not be relevant to the
appeal against the Environment Court’s
decision.[110] We
agree.
The OTS land
- [113] The
second issue raised by Mr Salmon concerned the possibility the Crown might grant
easements over the OTS land. The Environment
Court considered that since the
PWA did not permit compulsory acquisition of land owned by the Crown, there was
no means of obtaining
the OTS land without the agreement of the Minister for
Treaty of Waitangi
Negotiations.[111] While
recording that it could not review the decision of that Minister, it
thought there was a reasonable basis for that Minister
to refuse to allow the
easements, given the objections of tangata whenua and evidence from a witness at
the Office of Treatment
Settlements.[112]
- [114] The
evidence for that view was summarised in the Environment Court’s report.
It recorded, amongst other things, that
the OTS land was part of an area of some
4000 ha, referred to as the OTS block, the taking of which had been
disputed by Te Whiu,
a hapū of Ngāpuhi, over the years since
1868. Some 2000 acres had been re-vested in Te Whiu in 1921. What was referred
to as the OTS remnant land was part of the original tūrangawaewae of
Te Whiu, and contained urupā and a pā site.
The Court observed
that it had been “repeatedly identified as of significant cultural value
to Te Whiu”.[113]
Further, it was the sole remnant land available of their original ancestral
lands, which increased its importance for the purposes
of cultural redress under
the Treaty of
Waitangi.[114]
- [115] The Judge
considered the Environment Court’s approach was
correct.[115] No challenge
had been mounted in relation to the refusal of the Minister for Treaty of
Waitangi Negotiations to make the OTS land
available for the construction of
transmission lines, and the Environment Court was entitled to proceed on the
basis that the decision
of that Minister not to grant consent was
valid.[116] Further, TEL was not
obliged to exhaust the legal pathways available in respect of the OTS route
before seeking consent under s
186(1) of the
RMA.[117]
- [116] In this
Court, Mr Salmon again submitted the Environment Court erred by failing to
consider that as a matter of law the Crown
was able to grant easements over its
own land-banked land without resorting compulsory acquisition to allow TEL to
proceed with its
project. He contended that the reasons for the Crown’s
refusal were “policy-driven, and as such, irrelevant”.
He referred
to Phillip A Joseph, Constitutional and Administrative Law in New Zealand
for the proposition that considerations such as the public interest,
administrative efficiency or government policy may not excuse
an unauthorised
statutory purpose or reliance on an irrelevant
consideration.[118] He also
repeated the argument advanced in the High Court that the Environment Court
erred by failing to take into account that TEL
had not challenged the refusal of
the Crown to grant an easement over the OTS land.
- [117] It will be
apparent from the discussion earlier in this judgment that we cannot accept
these arguments. In the High Court,
Mr Salmon relied on the decision of the
High Court in Dannevirke Borough Council v
Governor-General.[119]
Although he did not refer to it in this Court, that judgment reflects the basis
of the argument he advanced, based on a narrow conception
of the purpose of the
statutory scheme. The case concerned a resolution by the Council that land
be compulsorily acquired under
the Public Works Act 1928 (the PWA 1928) for the
purposes of a new rubbish dump. In accordance with constitutional procedures,
it was necessary for the Minister
of Works to recommend to the Governor-General
that land be taken for the purposes of the proposed work. The Minister declined
to
recommend to the Governor-General that the subject land be taken, giving as
his reason the fact that the land was Māori land
and it was government
policy not to allow its compulsory acquisition.
- [118] After
reviewing the scope and purposes of the PWA 1928, Davison CJ referred to
Padfield v Minister of Agriculture, Fisheries and
Food.[120]
He held that the Act did not enable particular classes of land or land
owned by particular classes of persons to be excluded from
the compulsory taking
provisions of the legislation by the exercise of the discretion of the Minister
or Governor-General, and that
by making a decision based on the policy not to
compulsorily acquire Māori land, the Minister exercised his powers for an
improper
purpose. In this regard, Davidson CJ
stated:[121]
The
Government policy to which the Minister referred is contrary to the policy and
objects of the Act. It is a consideration which
did not entitle him to refuse
to recommend the compulsory taking of the land. If the Government wishes to
implement the stated policy
in relation to Maori land then it must be given
legislative effect by an appropriate statutory enactment. It cannot apply a
policy
which is contrary to the statute.
- [119] This
reasoning appears anachronistic judged in the light of today’s enhanced
appreciation of the importance of the Treaty
of Waitangi and the need to ensure
that land use issues of significance to Māori are properly recognised and
provided for.
Further, the legislation has undergone significant change, which
makes application of the approach adopted in Dannevirke inappropriate as
a general proposition. The Minister’s power in s 186(1) of the RMA
must now be exercised in a statutory setting
which requires application of the
purposes and principles expressed in pt 2 of the RMA, including the requirement
to recognise and
provide for “the relationship of Māori and their
culture and traditions with their ancestral lands, water, sites,
waahi
tapu, and other
taonga”.[122] And under
s 8 of the Act, the Minister is obliged to take into account the principles
of the Treaty of Waitangi.
- [120] Given
these provisions of the RMA, it cannot possibly be said that allowing such
considerations an influential role in the decision-making
process would do
anything other than promote the purposes of the statutory
scheme.[123] If such matters can
legitimately be considered under s 186(1) of the RMA it would be odd if
they could not be brought into account
under the PWA. In this field both
statutes clearly need to operate in a complementary manner.
- [121] More
fundamentally, treating the significance of land to Māori as a
policy‑driven and therefore “irrelevant”
consideration in
determining whether land should be acquired or taken under pt 2 of the PWA runs
counter to the principles of the
Treaty of Waitangi. While s 24(7) does
not expressly require the Environment Court to have recourse to the Treaty
of Waitangi or
its principles, where the acquisition of land of significance to
Māori is at issue the Treaty is clearly relevant to the Environment
Court’s inquiry.[124]
- [122] These
considerations underline the correctness of the conclusion of the Courts below
that the refusal to grant an easement over
the OTS land, and the
“failure” of TEL to challenge that decision, were not matters that
needed to be weighed against
the
project.
Notice of intention
- [123] The
final issue raised by Mr Salmon was based on the requirement in s 23(1)(c) of
the PWA that notices be served on the landowners
explaining, amongst other
things, why the taking of the land is considered reasonably necessary. Here,
the respective notices of
intention relevantly asserted that the project would
allow TEL to construct a single circuit high-voltage transmission line and other
electrical and communication works. Further, it was said that the project was
required:
... to improve the capacity, security and reliability of
the electricity distribution network in the Far North region to meet growth
and
increasing demand for electricity in the region; and to remedy underlying
network weaknesses which will provide a more secure
supply for the region.
- [124] Mr Salmon
criticised this on the basis that the reasons given were generic statements
about the benefits of the transmission
line project as a whole. He argued that
they did not enable the landowners to know why the decision to take the
easements over their
land was made, and to be satisfied that it was lawful.
- [125] The
Environment Court rejected this argument. It held that in the case of a linear
project affecting (as was the case here)
some 96 properties, there was no
requirement for the objectives to relate to each specific
property.[125] The High Court
then rejected the appeal on this issue on the basis that errors affecting the
Minister’s decision-making were
properly within the ambit of judicial
review, not appeal.[126]
- [126] We do not
consider the Environment Court made any relevant error of law in dealing with
this issue. It is possible that an
error of a fundamental kind affecting a
notice issued under s 23(1) of the PWA might mean that the appropriate response
of the Environment
Court is to refer the matter back to the Minister for further
consideration under s 24(7)(e) or to report adversely on the proposal.
At least
theoretically a failure by the Environment Court to take such steps might give
rise to an appealable question of law.
But this case is far from that. There
is no suggestion that anyone was misled by the nature of the works or the need
for the acquisition
of easements along the intended route. There is no error of
law.
Costs
- [127] For
the reasons we have expressed, we conclude that the High Court was wrong to set
aside the Environment Court’s report,
and the appeal must be allowed. In
that event, the Minister sought costs calculated for a standard appeal. Having
considered this
issue, we record our view that the issues raised have resulted
in important clarification of the statutory powers relevant to the
compulsory
acquisition of land required for a project or work of a network utility
operator. In the circumstances, although the
Minister has succeeded, we
consider costs should lie where they
fall.
Result
- [128] The
appeal is allowed.
- [129] The
decision of the High Court is set aside.
- [130] The report
of the Environment Court is confirmed.
- [131] As
requested by Mr Isac, we refer the matter back to the Environment Court to
finalise the terms of the easements as contemplated
by the
report.[127]
- [132] We make no
order as to costs.
Solicitors:
Crown Law
Office, Wellington for Appellant
Lee Salmon Long, Auckland for
Respondents
[1] Section 186 of the Resource
Management Act 1991 refers to the Minister of Lands. Although the statute has
not been amended, there
is now no Minister of Lands and the powers are
exercisable by the Minister for Land Information.
[2] Public Works Act 1981,
s 18(1)(d).
[3] Section 18(2).
[4] Section 23(3).
[5] Section 24(7)(a), (b) and (d).
[6] Section 24(7)(e) and (f).
[7] Section 24(10).
[8] Dromgool v Minister for
Land Information [2018] NZEnvC108 [Environment Court report] at [40].
[9] At [44].
[10] At [129].
[11] At [165] and [169].
[12] Section 299 of the Resource
Management Act authorises an appeal against such a report to the High Court on a
question of law.
[13] Minister for Land
Information v Dromgool [2019] NZHC 1563 [High Court judgment].
[14] Section 308 of the Resource
Management Act provides for further appeals to the Court of Appeal. Section
308(1) provides that sub-pt
8 of pt 6 of the Criminal Procedure Act 2011 applies
as if the decision of the High Court under s 299 of the Resource Management
Act
had been made under s 300 of the Criminal Procedure Act. This means a
further appeal to the Court of Appeal is by leave, under
s 303(1) of the
Criminal Procedure Act.
[15] Minister for Land
Information v Dromgool [2019] NZCA 508.
[16] Environment Court report,
above n 8, at [7].
[17] At [12].
[18] At [14].
[19] “AGE” in this
passage stands for an agreement to grant an easement.
[20] Public Works Act, s 24.
[21] Environment Court report,
above n 8, at [37].
[22] At [40].
[23] At [43].
[24] At [45]–[53], citing
Seaton v Minister for Land Information [2013] NZSC 42, [2013] 3 NZLR 157.
[25] At [109].
[26] At [109]. The Minister for
Treaty of Waitangi Negotiations is referred to as the “Minister of Treaty
Settlements” in
the Environment Court report and the High Court judgment.
[27] High Court judgment, above
n 13, at [2].
[28] At [42], referring to
Unison Networks Ltd v Commerce Commission [2007] NZSC 74, [2008]
1 NZLR 42 at [53].
[29] At [46].
[30] At [48]. See also
[53].
[31] At [48].
[32] At [53].
[33] Environment Court report,
above n 8, at [42].
[34] High Court judgment, above
n 13, at [63].
[35] At [63].
[36] At [66].
[37] At [68].
[38] At [73].
[39] At [74].
[40] At [75].
[41] At [76].
[42] Resource Management Act, s
166, definition of “designation”.
[43] Section 167.
[44] Section 166, definition of
“network utility operator”. In the present case, TEL was a network
utility operator because
of its status as an “electricity operator”
or “electricity distributor” as defined in s 2 of the
Electricity
Act 1992 for the purpose of line function services as defined in
that section.
[45] Environment Court report,
above n 8, at [10].
[46] Section 17 of the Public
Works Act provides for acquisition by agreement.
[47] Section 2 of the Public
Works Act provides that a “government work” means a work or an
intended work that is to be constructed,
undertaken, established, managed,
operated or maintained by or under the control of the Crown or any Minister of
the Crown for any
public purpose. It includes land held or to be acquired for
the purposes of the Conservation Act 1987 or any of the Acts specified
in sch 1
of that Act (except the marine and coastal area), even where the purpose of
holding or acquiring the land is to ensure it
remains in an undeveloped state.
[48] Public Works Act, s
18(1)(b).
[49] Section 18(1)(c).
[50] Section 18(1)(d).
[51] Section 17(2) provides that
an agreement to sell land to the Crown or a local authority under
the section may be implemented by
a declaration under s 20 or by a transfer
instrument under the Land Transfer Act 2017 for the stated public work.
[52] Section 23(1)(a).
[53] Section 23(1)(b). The
period within which objections must be made in this section does not apply to
objections by persons served
with a copy of a notice under s 23(1)(c).
[54] Section 23(1)(c).
[55] Section 24(1).
[56] Section 24(7)(c).
[57] Section 24(12).
[58] Section 24(7)(d).
[59] Land Information New
Zealand Standard for the Acquisition of Land under the Public Works Act 1981:
LINZS15005 (2 June 2017) [LINZS15005].
[60] High Court judgment, above
n 13, at [59].
[61] At [47].
[62] At [47].
[63] At [59].
[64] LINZS15005, above n 59, at 33.
[65] Kett v Minister for Land
Information HC Auckland AP404/151/00, 28 June 2001.
[66] Unison Networks Ltd v
Commerce Commission, above n 28.
[67] Padfield v Minister of
Agriculture, Fisheries and Food [1968] UKHL 1; [1968] AC 997 (HL) at 1030 per
Lord Reid.
[68] Attorney-General v
Ireland [2002] NZCA 40; [2002] 2 NZLR 220 (CA) at [42] and [43]; and Poananga v State
Services Commission [1985] 2 NZLR 385 (CA) at 393–394.
[69] Resource Management Act, s
8.
[70] The matters of national
importance set out in s 6 of the Resource Management Act must be recognised by
all persons exercising functions
and powers under the Act, so would extend to
the Minister acting under s 186(1).
[71] Seaton v Minister for
Land Information, above n 24.
[72] At [21]–[22] per
Elias CJ and [67] per Chambers and Glazebrook JJ.
[73] At [5] (footnote
omitted).
[74] At [5], n 6.
[75] At [76], n 52.
[76] At [76].
[77] At [77].
[78] At [66].
[79] At [66].
[80] Above at [20].
[81] High Court judgment, above
n 13, at [47].
[82] Seaton v Minister for
Land Information, above n 24, at
[24] per Elias CJ, [66] per Chambers and Glazebrook JJ and [83] per William
Young and McGrath JJ.
[83] Public Works Act, s
24(10).
[84] Section 18(1)(d). A
modification resulting in a proposal affecting different land might of course
require the statutory procedures
to be recommenced in the absence of agreement
from the newly affected landowners.
[85] Section 18(2).
[86] Section 24(7)(b).
[87] Section 24(7)(d).
[88] Section 24(7)(c).
[89] High Court judgment, above
n 13, at [47].
[90] Schmuck v Opua Coastal
Preservation Inc [2019] NZSC 118, [2019] 1 NZLR 750.
[91] Reserves Act 1977, s
48(1).
[92] Schmuck v Opua Coastal
Preservation Inc, above n 90, at
[130].
[93] At [130]–[131].
[94] At [132] (footnote
omitted).
[95] Reserves Act, s 48(2).
[96] Kett v Minister for Land
Information, above n 65.
[97] High Court judgment, above
n 13, at [49].
[98] At [51], citing Kett v
Minister for Land Information, above n 65, at [32].
[99] Kett v Minister for Land
Information, above n 65, at
[37]–[38].
[100] Kett v Minister of
Land Information EnvC Auckland A110/2000, 15 September 2000 at [44].
The Environment Court’s finding in this respect was not challenged on
appeal.
[101] High Court judgment,
above n 13, at [59].
[102] Environment Court
report, above n 8, at [42].
[103] At [42].
[104] At [109].
[105] At [113].
[106] At [114].
[107] High Court judgment,
above n 13, at [68].
[108] At [68].
[109] Environment Court
report, above n 8, at [83].
[110] High Court judgment,
above n 13, at [68].
[111] Environment Court
report, above n 8, at [64].
[112] At [66].
[113] At [60(c)].
[114] At [65(d)].
[115] High Court judgment,
above n 13, at [73].
[116] At [73].
[117] At [74].
[118] Phillip A Joseph
Constitutional and Administrative Law in New Zealand (4th ed, Thomson
Reuters, Wellington, 2014) at [23.2.6].
[119] Dannevirke Borough
Council v Governor-General [1981] 1 NZLR 129 (HC).
[120] Padfield v Minister
of Agriculture, Fisheries and Food, above n 67.
[121] Dannevirke Borough
Council v Governor-General, above n 119, at 134–135.
[122] Resource Management Act,
s 6(e). As earlier discussed, other subsections of s 6 could be relevant where
a project gives rise to
issues of environmental concern.
[123] See Huakina
Development Trust v Waikato Valley Authority [1987] NZHC 130; [1987] 2 NZLR 188 (HC) at
210–211 where Chilwell J noted that the Water and Soil Conservation Act
1967 and Country Planning Act 1977 comprised a “comprehensive
statutory
scheme” providing for the terms of one statute to be useful for
interpreting another.
[124] See New Zealand
Maori Council v Attorney-General [2007] NZCA 269, [2008] 1 NZLR 318
at [74], citing Barton-Prescott v Director-General of Social Welfare
[1997] 3 NZLR 179 (HC) at 184. See also Tukaki v Commonwealth of
Australia [2018] NZCA 324, [2018] NZAR 1597 at [36]; and Takamore v
Clarke [2011] NZCA 587, [2012] 1 NZLR 573 at [248] per Chambers J.
[125] Environment Court
report, above n 8, at [91].
[126] High Court judgment,
above n 13, at [76].
[127] Environment Court
report, above n 8, at
[176]–[177].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2021/44.html