NZLII Home | Databases | WorldLII | Search | Feedback

Court of Appeal of New Zealand

You are here:  NZLII >> Databases >> Court of Appeal of New Zealand >> 2021 >> [2021] NZCA 44

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Minister for Land Information v Dromgool [2021] NZCA 44 (5 March 2021)

Last Updated: 10 March 2021

IN THE COURT OF APPEAL OF NEW ZEALAND

I TE KŌTI PĪRA O AOTEAROA
CA364/2019
[2021] NZCA 44



BETWEEN

MINISTER FOR LAND INFORMATION
Appellant


AND

SHANE DROMGOOL AND DOROTHY DROMGOOL
First Respondents

ALAN DARVALL POULTON AND JENNIFER POULTON
Second Respondents

NEWMAN FARMS LIMITED
Third Respondents

Hearing:

7 and 8 July 2020

Court:

Cooper, Clifford and Goddard JJ

Counsel:

A N Isac QC, M C McCarthy and E M Jamieson for Appellant
D M Salmon and A W McDonald for Respondents

Judgment:

5 March 2021 at 3 pm


JUDGMENT OF THE COURT

  1. The appeal is allowed.
  2. The decision of the High Court is set aside.
  1. The report of the Environment Court is confirmed.
  1. The matter is referred back to the Environment Court to finalise the terms of the easements.
  2. There is no order as to costs.

____________________________________________________________________

REASONS OF THE COURT

(Given by Cooper J)

Table of Contents

Para No.

Introduction

C Counsel should focus their submissions on:

(a) the role and obligations of the Minister under s 186 of the Resource Management Act 1991; and

(b) whether the inquiry into the adequacy of consideration of alternatives contemplated by s 24(7) of the Public Works Act 1981 is an inquiry into the adequacy of consideration of alternatives by the requiring authority, by the Minister, or by both.

Relevant facts

(a) the line requires maintenance as it is around 60 years old, and requires replacement within the foreseeable future (around 2030);

(b) maintenance works on poles and repairs of breakages have been an ongoing and significant requirement since the takeover. In particular, around 6km of the line runs through the Mangamuku Gorge and is vulnerable to major events;

(c) between 2013 and 2017 there were some nine outages of 47.7 hours to substantial parts of the network. Measured in terms of the economic impact of those outages, the cost to the Far North economy is estimated to be $13,368,956;

(d) the Juken timber mill in Kaitaia is a major employer, and particularly susceptible to outages. An unplanned outage can mean a cost to the production line through a restart of some $150,000 each time[;]

(e) the historic pattern of demand has changed from the urban centres of Kaikohe and Kaitaia, with increasing population on the eastern seaboard area (Kerikeri Peninsula and the Bay of Islands);

(f) it was considered that an alternative route to the eastern seaboard would increase supply through the 11kV local network lines, and permit some upgrading to 33kV (for example in Kaeo and Wiroa). Examples were given by Mr Shaw, including Mt Pokaka having to supply their own power for a timber mill employing 100 people, and an 800 unit accommodation in Karikari Peninsula having no secure supply of power;

(g) the existing GXP 110kW single circuit was on a route involving the Mangaweka Gorge, and is susceptible to failure through natural events. Significant resilience would be achieved by creating a second circuit to Kaitaia.

(a) the FGT/Sutcliffe Route, slightly to the west of the original route and travelling through the length of the FGT and Sutcliffe properties, relying on the AGE with Poulton and the agreement of Greenacres eventually obtained. This route, of course, still involved crossing the Taylor property, who had already indicated they would not consent, and also further crossing of the FGT Farms Limited, Sutcliffe and Cornelius properties;[19]

(b) ... the Objection Route, travelling through a different portion of the Poulton farm (for which there was no AGE), Newman Farms, Dromgool (the Objectors), Sutcliffe, Kearney and Cornelius properties. This utilised a section of public road between Newman Farms and the Jones property for around 1.5km. ... ; and

(c) ... a route to the far west (Far Western Route), skirting the North Star Dairies Ltd land (on Crown land) and then utilising public road to travel from the west to join up at the Greenacres property. It appears that route was discounted not only for length but impact very early, and no party ... suggested that this was a reasonable alternative.

The Environment Court’s report

[53] Notwithstanding the repeated submissions of Mr Salmon as to the necessity for the Minister to comply with s 24(7) when a decision under s 186 is made, we can find no reference in this or any other case to such a requirement. Mr Salmon’s own submissions ... noted that references to the Minister in s 186 and s 24(7) (a) and (d) must be read as reference to [TEL], relying on Seaton, paragraph [83]. We agree. Thus, it is difficult to read into s 186 a requirement that the Minister, at the time they agree to proceed with Part 2 of the Public Works Act, has an obligation to ensure that the taking complies with s 24(7) of the Act.

[125] We are satisfied that, at the time of the Minister’s agreement under s 186, three takes were required on the Objection route and three takes (Taylor, FGT and Sutcliffe) would have been involved in the FGT/Sutcliffe route.

[126] We are in no doubt that consideration had been given by TEL to the FGT/Sutcliffe route, and that this is demonstrated not only by the Sutcliffe’s agreement to an alternative route but by a consideration of the impact [of] the other route upon the Sutcliffe and FGT properties. It is likely that the impact upon the Taylor properties was considered by TEL to be acceptable, but concerns had been identified as to the impact on the FGT and Sutcliffe properties.

[127] We are satisfied that the Western Deviation of the [Mangakaretu] Alignment was developed in an iterative process, including consultation with landowners. It is not for this Court to reach a conclusion as to which is the best route alternative. We are satisfied that alternatives have been considered on a reasonable basis, and that the choice of route is reasonable in the Wednesbury sense. Our finding is that there has been an adequate consideration of sites and routes to achieve the objectives.

The appeal to the High Court

[47] It follows that it must be the Minister alone who has the obligation to consider any relevant factors. The exercise of the statutory power of compulsory acquisition process involved a recognised decision-making process beginning with a formal application by the requiring authority under s 186 and the provision of the usual briefing material from Ministry officials. The statutory power and the decision-making process are the antithesis of an agent acting for a private entity. Such an approach could, as Mr Salmon pointed out, result in deficiencies and inaccuracies being attributed to the Minister, with no apparent recourse by those affected. I therefore do not accept that the Minister acts as TEL’s agent in the true sense so that the Minister is impressed with TEL’s knowledge for the purposes of making a decision to take land under the PWA.

[64] The Environment Court erred in holding that the Minister’s discretion was unfettered. It should have approached the question of consideration of alternatives under s 24(7)(b) on the basis that this was a factor (among others) that the Minister was required to consider.

[65] In examining the adequacy of the Minister’s consideration of alternative sites, the Environment Court found that there was no information of alternative routes before the Minister. As TEL’s knowledge cannot be attributed to the Minister, it is clear that the Minister’s consideration of any alternatives was inadequate. It follows that the Court’s conclusion that, notwithstanding the lack of any consideration of alternatives by the Minister, there had been adequate consideration was an error. For the same reason, the Environment Court’s iterative approach proceeded on the wrong premise that there had been adequate consideration of alternatives.

The relevant statutory provisions

The RMA

(3) The Environment Court may make an order applied for under subsection (1) if it is satisfied that—

(a) the owner has tried but been unable to enter into an agreement for the sale of the estate or interest in the land subject to the designation or requirement at a price not less than the market value that the land would have had if it had not been subject to the designation or requirement; and

(b) either—

(i) the designation or requirement prevents reasonable use of the owner’s estate or interest in the land; or

(ii) the applicant was the owner, or the spouse, civil union partner, or de facto partner of the owner, of the estate or interest in the land when the designation or requirement was created.

(a) any agreement shall be deemed to have been entered into with the Minister of Lands on behalf of the network utility operator as if the land were required for a government work; and

(b) all costs and expenses incurred by the Minister of Lands in respect of the acquisition of the land shall be recoverable from the network utility operator as a debt due to the Crown.

186 Compulsory acquisition powers

(1) A network utility operator that is a requiring authority may apply to the Minister of Lands to have land required for a project or work acquired or taken under Part 2 of the Public Works Act 1981 as if the project or work were a government work within the meaning of that Act and, if the Minister of Lands agrees, that land may be taken or acquired.

(2) The effect of any Proclamation taking land for the purposes of subsection (1) shall be to vest the land in the network utility operator instead of the Crown.

(3) Land which is subject to a heritage order shall not be taken without the consent of the heritage protection authority.

(4) Any land held under any enactment or in any other manner by the Crown or a local authority may, with the consent of the Crown or that authority and on such terms and conditions (including price) as may be agreed, be set apart for a project or work of a network utility operator in the manner provided in sections 50 and 52 of the Public Works Act 1981 (with the necessary modifications), but the setting apart shall not be subject to sections 40 and 41 of that Act. Any land so set apart shall vest in the network utility operator.

(5) Any claim for compensation under the Public Works Act 1981 in respect of land acquired or taken in accordance with this section shall be made against the Minister of Lands.

(6) All costs and expenses incurred by the Minister of Lands in respect of the acquisition or taking of land in accordance with this section (including any compensation payable by the Minister) shall be recoverable from the network utility operator as a debt due to the Crown.

(7) Sections 40 and 41 of the Public Works Act 1981 shall apply to land acquired or taken in accordance with this section as if the network utility operator concerned were the Crown.

(7A) This section does not apply if—

(a) the network utility operator is a responsible SPV; and

(b) the land is protected Māori land.

(8) For the purposes of this section, an interest in land, including a leasehold interest, may be acquired or taken as if references to land were references to an interest in land.

The PWA

(a) a proclamation taking the land has been published in the Gazette; or

(b) the Minister or local authority has served a further notice confirming the intention to take the land; or

(c) the intention to take is the subject of any inquiry by the Environment Court or an ombudsman, or of any application for judicial review. In such cases, the notice of intention remains valid for three months after the date of the Environment Court’s report, the date on which the Environment Court receives written notice of the withdrawal of the objection, the date of the completion of any inquiry by an ombudsman, or the judicial decision, as the case may be.

24 Objection to be heard by Environment Court

(1) On receiving a written objection under section 23, the Environment Court shall, as soon as practicable, send a copy of the objection to the Minister or local authority, as the case may require.

(2) Within 1 month after receiving a copy of the objection or within such further period as the Environment Court may allow, the Minister or local authority, as the case may require, shall send to the Environment Court and serve on the objector a reply to the objection containing the following information:

(a) the statutory or other authority under which it is proposed to take the land; and

(b) the nature of the work to be constructed or the purpose for which the land is required; and

(c) such other matters as may be appropriate having regard to the objections made and to any practice directions issued by the Environment Court.

(3) The Environment Court shall inquire into the objection and the intended taking and for that purpose shall conduct a hearing at such time and place as it may appoint.

...

(6) At every such hearing the Minister or the local authority may be represented by counsel or by an officer of the Minister’s department or local authority, as the case may require, and the objector may appear and act personally or by counsel or any duly authorised representative.

...

(7) The Environment Court shall—

(a) ascertain the objectives of the Minister or local authority, as the case may require:

(b) enquire into the adequacy of the consideration given to alternative sites, routes, or other methods of achieving those objectives:

(c) in its discretion, send the matter back to the Minister or local authority for further consideration in the light of any directions given by the court:

(d) decide whether, in its opinion, it would be fair, sound, and reasonably necessary for achieving the objectives of the Minister or local authority, as the case may require, for the land of the objector to be taken:

(e) prepare a written report on the objection and on the court’s findings:

(f) submit its report and findings to the Minister or local authority, as the case may require.

...

(9) At the same time as the Environment Court submits its report and findings to the Minister or local authority, it shall send a copy of the report and findings to the objector, and make copies of them available to the public.

(10) The report and findings of the Environment Court shall be binding on the Minister or, as the case may be, the local authority.

(11) Any objection filed under section 23 may be withdrawn by the objector at any time before the court makes its report and findings under this section.

(12) Where the objection is withdrawn by the objector pursuant to subsection (11), the court shall not be obliged to make a report and findings under this section.

(13) The Environment Court may award such costs as it considers just either in favour or against the objector, the Crown, or the local authority.

(14) Subject to sections 299 and 308 of the Resource Management Act 1991, no appeal shall lie from any report or recommendation of the Environment Court under this section.

The interrelationship between the RMA and PWA

The appeal

Appellant’s argument

Respondents’ argument

(a) Alternative sites, routes or other methods of achieving the relevant objectives. Mr Salmon submitted this was clear from the statutory framework, and s 24(7)(b) of the PWA in particular.

(b) The information required to be provided to the Minister in accordance with LINZS15005.

(c) The contents of the s 186 applications.

Decision

The nature of the Minister’s power under s 186 of the RMA

[53] A statutory power is subject to limits even if it is conferred in unqualified terms. Parliament must have intended that a broadly framed discretion should always be exercised to promote the policy and objects of the Act. These are ascertained from reading the Act as a whole. The exercise of the power will be invalid if the decision maker “so uses his discretion as to thwart or run counter to the policy and objects of the Act”.[67] A power granted for a particular purpose must be used for that purpose but the pursuit of other purposes does not necessarily invalidate the exercise of public power. There will not be invalidity if the statutory purpose is being pursued and the statutory policy is not compromised by the other purpose.[68]

The role of the Minister

[83] Where s 186(1) of the Resource Management Act has been invoked, the references to “Minister” in (a) and (d) must be read as a reference to the network utility operator (because the proposed taking will be to give effect to its objectives, rather than those of the Minister). ...

... the focus would be on the utilities’ need for these easements compared with other relocation measures that might be open to them. The difference is subtle, but there is a difference.

... we do not consider that the Minister is under any obligation in process terms to reconsider the matters taken into account by the administering body in granting the easement, so long as they are within the administering body’s powers.

[131] In characterising the Minister’s power as supervisory, we are not intending to create any artificial limit on that power. All we are saying is that there is no requirement to re-run the process already undertaken by the administering body of the reserve. However, if the Minister takes a different view of the situation from that taken by the administering body, there is nothing to stop the Minister refusing to consent to a decision that the administering body has made lawfully and which the administering body considers is reasonable. We agree with the Court of Appeal that the Minister is free to take a different view from that of the administering body as grantor. But there is also nothing requiring the Minister to reconsider matters decided by the administering body and the Minister does not act unlawfully if he or she does not do so.

... the manner and intensity of the inquiry into any such matter (beyond the essentials of checking that the statutory process has been undertaken by the administering body and that the easement was lawfully granted), subject only to challenge on grounds of unreasonableness.

If this phrase is given its normal plain and dictionary meaning, the Court was required to consider whether the Minister sufficiently and with due regard, chose the route, after taking into account circumstances which were reasonably relevant relating to that route and alternative routes. I see no reason, from the context of the Act or statements made when the Bill was introduced, to give the term any other meaning. ... The Court was not itself required to determine whether the route was the most suitable of the available alternatives. Its role was to ensure that the Minister had carefully considered the possibilities, taken into account relevant matters and come to a reasoned decision.

... to enable Transit to give effect to the proposal to construct and operate the Realignment of State Highway 1 between Orewa and Puhoi generally in accordance with the designation for it in the district plan as part of a safe and efficient highway system.

Mr Sun noted that no alternatives were ever before the Minister. The Ministry of Land Information deals with the application made by the requiring authority. Although the report by the requiring authority does indicate some background information on how the route selection was made, we agree that this cannot bind the Minister at the s 186 decision stage.

It’s not my understanding of the s 186 process ... It’s a requirement that the applicant identifies what it’s applying for. The Minister does not pick (a),(b) or (c). She decides “yes” or “no”. ... [If an applicant advised that there were two equally good routes] ... the relevant official would say to the applicant, “decide which one’s better and tell us why”.

Other issues

(a) treating the Minister’s decision as valid when it was defective because TEL’s route selection was based on improper and irrelevant considerations (including a landowner’s alleged political connections) and the s 186 applications contained “fatal omissions”;

(b) failing to consider that, as a matter of law, the Crown could have granted easements over the OTS land without requiring compulsory acquisition; and

(c) treating the reasons given in the Minister’s notice of intention to take land as sufficient, when they were not.

Improper/irrelevant considerations and omissions

The OTS land

The Government policy to which the Minister referred is contrary to the policy and objects of the Act. It is a consideration which did not entitle him to refuse to recommend the compulsory taking of the land. If the Government wishes to implement the stated policy in relation to Maori land then it must be given legislative effect by an appropriate statutory enactment. It cannot apply a policy which is contrary to the statute.

Notice of intention

... to improve the capacity, security and reliability of the electricity distribution network in the Far North region to meet growth and increasing demand for electricity in the region; and to remedy underlying network weaknesses which will provide a more secure supply for the region.

Costs

Result







Solicitors:
Crown Law Office, Wellington for Appellant
Lee Salmon Long, Auckland for Respondents


[1] Section 186 of the Resource Management Act 1991 refers to the Minister of Lands. Although the statute has not been amended, there is now no Minister of Lands and the powers are exercisable by the Minister for Land Information.

[2] Public Works Act 1981, s 18(1)(d).

[3] Section 18(2).

[4] Section 23(3).

[5] Section 24(7)(a), (b) and (d).

[6] Section 24(7)(e) and (f).

[7] Section 24(10).

[8] Dromgool v Minister for Land Information [2018] NZEnvC108 [Environment Court report] at [40].

[9] At [44].

[10] At [129].

[11] At [165] and [169].

[12] Section 299 of the Resource Management Act authorises an appeal against such a report to the High Court on a question of law.

[13] Minister for Land Information v Dromgool [2019] NZHC 1563 [High Court judgment].

[14] Section 308 of the Resource Management Act provides for further appeals to the Court of Appeal. Section 308(1) provides that sub-pt 8 of pt 6 of the Criminal Procedure Act 2011 applies as if the decision of the High Court under s 299 of the Resource Management Act had been made under s 300 of the Criminal Procedure Act. This means a further appeal to the Court of Appeal is by leave, under s 303(1) of the Criminal Procedure Act.

[15] Minister for Land Information v Dromgool [2019] NZCA 508.

[16] Environment Court report, above n 8, at [7].

[17] At [12].

[18] At [14].

[19] “AGE” in this passage stands for an agreement to grant an easement.

[20] Public Works Act, s 24.

[21] Environment Court report, above n 8, at [37].

[22] At [40].

[23] At [43].

[24] At [45]–[53], citing Seaton v Minister for Land Information [2013] NZSC 42, [2013] 3 NZLR 157.

[25] At [109].

[26] At [109]. The Minister for Treaty of Waitangi Negotiations is referred to as the “Minister of Treaty Settlements” in the Environment Court report and the High Court judgment.

[27] High Court judgment, above n 13, at [2].

[28] At [42], referring to Unison Networks Ltd v Commerce Commission [2007] NZSC 74, [2008] 1 NZLR 42 at [53].

[29] At [46].

[30] At [48]. See also [53].

[31] At [48].

[32] At [53].

[33] Environment Court report, above n 8, at [42].

[34] High Court judgment, above n 13, at [63].

[35] At [63].

[36] At [66].

[37] At [68].

[38] At [73].

[39] At [74].

[40] At [75].

[41] At [76].

[42] Resource Management Act, s 166, definition of “designation”.

[43] Section 167.

[44] Section 166, definition of “network utility operator”. In the present case, TEL was a network utility operator because of its status as an “electricity operator” or “electricity distributor” as defined in s 2 of the Electricity Act 1992 for the purpose of line function services as defined in that section.

[45] Environment Court report, above n 8, at [10].

[46] Section 17 of the Public Works Act provides for acquisition by agreement.

[47] Section 2 of the Public Works Act provides that a “government work” means a work or an intended work that is to be constructed, undertaken, established, managed, operated or maintained by or under the control of the Crown or any Minister of the Crown for any public purpose. It includes land held or to be acquired for the purposes of the Conservation Act 1987 or any of the Acts specified in sch 1 of that Act (except the marine and coastal area), even where the purpose of holding or acquiring the land is to ensure it remains in an undeveloped state.

[48] Public Works Act, s 18(1)(b).

[49] Section 18(1)(c).

[50] Section 18(1)(d).

[51] Section 17(2) provides that an agreement to sell land to the Crown or a local authority under the section may be implemented by a declaration under s 20 or by a transfer instrument under the Land Transfer Act 2017 for the stated public work.

[52] Section 23(1)(a).

[53] Section 23(1)(b). The period within which objections must be made in this section does not apply to objections by persons served with a copy of a notice under s 23(1)(c).

[54] Section 23(1)(c).

[55] Section 24(1).

[56] Section 24(7)(c).

[57] Section 24(12).

[58] Section 24(7)(d).

[59] Land Information New Zealand Standard for the Acquisition of Land under the Public Works Act 1981: LINZS15005 (2 June 2017) [LINZS15005].

[60] High Court judgment, above n 13, at [59].

[61] At [47].

[62] At [47].

[63] At [59].

[64] LINZS15005, above n 59, at 33.

[65] Kett v Minister for Land Information HC Auckland AP404/151/00, 28 June 2001.

[66] Unison Networks Ltd v Commerce Commission, above n 28.

[67] Padfield v Minister of Agriculture, Fisheries and Food [1968] UKHL 1; [1968] AC 997 (HL) at 1030 per Lord Reid.

[68] Attorney-General v Ireland [2002] NZCA 40; [2002] 2 NZLR 220 (CA) at [42] and [43]; and Poananga v State Services Commission [1985] 2 NZLR 385 (CA) at 393–394.

[69] Resource Management Act, s 8.

[70] The matters of national importance set out in s 6 of the Resource Management Act must be recognised by all persons exercising functions and powers under the Act, so would extend to the Minister acting under s 186(1).

[71] Seaton v Minister for Land Information, above n 24.

[72] At [21]–[22] per Elias CJ and [67] per Chambers and Glazebrook JJ.

[73] At [5] (footnote omitted).

[74] At [5], n 6.

[75] At [76], n 52.

[76] At [76].

[77] At [77].

[78] At [66].

[79] At [66].

[80] Above at [20].

[81] High Court judgment, above n 13, at [47].

[82] Seaton v Minister for Land Information, above n 24, at [24] per Elias CJ, [66] per Chambers and Glazebrook JJ and [83] per William Young and McGrath JJ.

[83] Public Works Act, s 24(10).

[84] Section 18(1)(d). A modification resulting in a proposal affecting different land might of course require the statutory procedures to be recommenced in the absence of agreement from the newly affected landowners.

[85] Section 18(2).

[86] Section 24(7)(b).

[87] Section 24(7)(d).

[88] Section 24(7)(c).

[89] High Court judgment, above n 13, at [47].

[90] Schmuck v Opua Coastal Preservation Inc [2019] NZSC 118, [2019] 1 NZLR 750.

[91] Reserves Act 1977, s 48(1).

[92] Schmuck v Opua Coastal Preservation Inc, above n 90, at [130].

[93] At [130]–[131].

[94] At [132] (footnote omitted).

[95] Reserves Act, s 48(2).

[96] Kett v Minister for Land Information, above n 65.

[97] High Court judgment, above n 13, at [49].

[98] At [51], citing Kett v Minister for Land Information, above n 65, at [32].

[99] Kett v Minister for Land Information, above n 65, at [37]–[38].

[100] Kett v Minister of Land Information EnvC Auckland A110/2000, 15 September 2000 at [44]. The Environment Court’s finding in this respect was not challenged on appeal.

[101] High Court judgment, above n 13, at [59].

[102] Environment Court report, above n 8, at [42].

[103] At [42].

[104] At [109].

[105] At [113].

[106] At [114].

[107] High Court judgment, above n 13, at [68].

[108] At [68].

[109] Environment Court report, above n 8, at [83].

[110] High Court judgment, above n 13, at [68].

[111] Environment Court report, above n 8, at [64].

[112] At [66].

[113] At [60(c)].

[114] At [65(d)].

[115] High Court judgment, above n 13, at [73].

[116] At [73].

[117] At [74].

[118] Phillip A Joseph Constitutional and Administrative Law in New Zealand (4th ed, Thomson Reuters, Wellington, 2014) at [23.2.6].

[119] Dannevirke Borough Council v Governor-General [1981] 1 NZLR 129 (HC).

[120] Padfield v Minister of Agriculture, Fisheries and Food, above n 67.

[121] Dannevirke Borough Council v Governor-General, above n 119, at 134–135.

[122] Resource Management Act, s 6(e). As earlier discussed, other subsections of s 6 could be relevant where a project gives rise to issues of environmental concern.

[123] See Huakina Development Trust v Waikato Valley Authority [1987] NZHC 130; [1987] 2 NZLR 188 (HC) at 210–211 where Chilwell J noted that the Water and Soil Conservation Act 1967 and Country Planning Act 1977 comprised a “comprehensive statutory scheme” providing for the terms of one statute to be useful for interpreting another.

[124] See New Zealand Maori Council v Attorney-General [2007] NZCA 269, [2008] 1 NZLR 318 at [74], citing Barton-Prescott v Director-General of Social Welfare [1997] 3 NZLR 179 (HC) at 184. See also Tukaki v Commonwealth of Australia [2018] NZCA 324, [2018] NZAR 1597 at [36]; and Takamore v Clarke [2011] NZCA 587, [2012] 1 NZLR 573 at [248] per Chambers J.

[125] Environment Court report, above n 8, at [91].

[126] High Court judgment, above n 13, at [76].

[127] Environment Court report, above n 8, at [176]–[177].


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2021/44.html