NZLII Home | Databases | WorldLII | Search | Feedback

Court of Appeal of New Zealand

You are here:  NZLII >> Databases >> Court of Appeal of New Zealand >> 2022 >> [2022] NZCA 380

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Davies v K M Smith Builder Limited [2022] NZCA 380 (15 August 2022)

Last Updated: 23 August 2022

IN THE COURT OF APPEAL OF NEW ZEALAND

I TE KŌTI PĪRA O AOTEAROA
CA694/2021
[2022] NZCA 380



BETWEEN

SIMON BERNARD DAVIES AND JUDITH GAY DAVIES
Appellants


AND

K M SMITH BUILDER LIMITED
First Respondent

KERRY MICHAEL SMITH
Second Respondent

Hearing:

11 July 2022

Court:

Clifford, Peters and Downs JJ

Counsel:

L A Andersen QC and S Gaskell for Appellants
A D G Hitchcock for Respondents

Judgment:

15 August 2022 at 10.30 am


JUDGMENT OF THE COURT

  1. The appeal is dismissed.
  2. The appellants must pay the respondent one set of costs for a standard appeal on a band A basis and usual disbursements.

____________________________________________________________________

REASONS OF THE COURT

(Given by Clifford J)

Introduction

Background

[28] Between the pre-building preparations in June 2014 and early 2016 the Davies and Mr Smith oversaw a dynamic co-design construction process. Both the Davies (primarily Mrs Davies) and Mr Smith were adding layers of necessary detail to Mr Scaife’s sparse plans, and both parties were adding innovations to the construction in an organic way. The relationship between the parties appeared to be harmonious throughout this time.

[29] As the house plans had minimal detail it took a high level of project management and building expertise to bring the plans to life. There were numerous areas where Mr Smith was required to interpret Mr Scaife’s vision.

[36] Mr Smith said during the construction the Davies made multiple changes to what had been set out in the original plans. Mrs Davies would spend long periods perusing building and design online and then would come to him with ideas and ask him to achieve various outcomes. She often selected products that would be considered much more expensive than even an average high-end build.

[42] These are just some examples of the number of decisions that added to the overall build cost. More importantly, they demonstrate the fluidity with which the Davies approached the interpretation of Mr Scaife’s design. Mrs Davies had many ideas and Mr Smith worked through the practicalities and logistics to make them a reality.

Hi Kerry,

Could you please provide me with a letter (preferably on headed paper) that the estimated costs of completion of our project will be $700,000 please.

This will be used for the release of funds.

Regards,

Simon

PS give me a call if you need to discuss.

The Davies’ claims

(a) That Mr Smith made inducing representations that:
(i) he had the time and ability to project manage the building work;

(ii) construction of the House (including landscaping) would cost between $2.5 and $2.8 million (inclusive of GST); and

(iii) construction would be completed by March 2016, namely within 15 to 18 months of commencement of construction (November 2014).

(b) That the contract contained the following implied terms:

(i) Mr Smith would project manage the building work to ensure the cost of the building work would be reasonable and in accordance with the estimate of costs;

(ii) the cost estimate was between $2.5 and $2.8 million (inclusive of GST);

(iii) the Firm would ensure the subcontractors costs were reasonable; and

(iv) the actual cost of the building work would be no more than $3 million.

(c) If the Court found Mr Smith did not make the alleged representations and the contract did not include the implied terms, the Davies claimed against the Firm in contract and against Mr Smith in negligence for failing to adequately project manage the construction of the House.

(d) The Firm and Mr Smith were liable under s 9 of the Fair Trading Act for misleading or deceptive conduct constituted by the provision of the March 2016 estimate. The Davies’ allegation of misleading and deceptive conduct against the Firm was the estimate of costs given by Mr Smith and the reassurance he gave that the cost would not exceed $3 million. Against Mr Smith, they relied on his letter of 16 March 2016 to the BNZ wherein he represented he expected the cost of completion of construction at that time to be no more than $700,000.

High Court judgment

The appeal

(a) It was apparent that Dr Davies had requested itemised costs for certain sub‑trades only.[10]

(b) The figure Mr Smith sent provided estimated costs to completion for a number of sub-trades but not all. Nor did it include labour costs generally, or labour and material costs for sub-trades for major components of the overall building.[11]

(c) Nor did it contain an estimate of costs for the Firm’s labour, as Dr Davies preferred to undertake that exercise himself. It was evident on the face of the written estimate that Mr Smith was raising as many questions as he was providing answers.[12]

[78] Initially Dr Davies insisted in cross-examination that the document Mr Smith had provided was a list of all outstanding work and an estimate of all completion costs. He did subsequently concede that a large number of quite fundamental building elements were not included in the document. Dr Davies was questioned by Mr Hitchcock on the document as follows:

  1. This is just his attempt to respond to your request, isn’t it?

A. And my request was unfortunately inaccurate.

[79] Thus the estimate was already compromised by three significant omissions. It did not contain the full complement of subcontractor costs, nor did it contain the labour costs. The parties were also yet to settle on the full extent and design of the hard landscaping so that was not costed either.

[80] In cross-examination, Dr Davies accepted that he sent the email asking Mr Smith to write the letter to the BNZ and he explained how the $700,000 figure was arrived at. The evidence established that the figure of $700,000 was a figure devised by Dr Davies and his banker, not by Mr Smith.

[81] It is unfortunate Mr Smith sent the letter, but it was commissioned for the purpose of assisting the Davies and the bank with financial planning. It was not commissioned for the purpose of Mr Smith undertaking and crystallising the actual costs of construction. That would have been obvious to both parties because of the exclusion of the major components identified ...

[82] I note further that it would not have been possible to ascertain an accurate estimate of the trades excluded from the estimate, as the parties were still working through what was required in respect of these elements as part of their organic collaborative interpretation and co-design.

[83] I consider it is disingenuous of the Davies in these circumstances (which they created) to assert Mr Smith represented to them the actual costs completion in March 2016 were $700,000 and to rely on it to allege he acted in bad faith and misled them.

[84] For the reasons I have set out above, I also do not consider this letter is proof that Mr Smith represented to the Davies the actual costs of completion to be $700,000. I find that he was obviously misguided in sending the letter to the bank, but I do not consider the letter proves in and of itself that Mr Smith has been dishonest in his dealings with the Davies

Analysis

(a) The original list of estimated costs of outstanding work responded to Dr Davies’ request which, as he acknowledged, “was unfortunately inaccurate”.[13]

(b) Dr Davies accepted he sent the email asking Mr Smith to write the letter to the BNZ and that the figure of $700,000 was one reached by Dr Davies and his banker, not by Mr Smith.[14]

(c) At the time of Dr Davies’ original request, and of Mr Smith writing the letter, it would not have been possible to ascertain an accurate estimate of the elements of outstanding work that were not included in the list Dr Davies sent to Mr Smith as the parties were still to finalise the scope of required work.[15]

Result






Solicitors:
Teresa Chan Law Ltd, Dunedin for Appellants
AWS Legal, Invercargill for Respondents


[1] Davies v K M Smith Builder Ltd [2021] NZHC 2865 [Judgment under appeal].

[2] Judgment under appeal, above n 1.

[3] Judgment under appeal, above n 1, at [3]–[7].

[4] At [58].

[5] At [66] and [84]–[85].

[6] At [93], [118], and [125]–[128].

[7] At [152].

[8] At [153], [157], [192] and [215].

[9] At [242]–[244].

[10] At [73].

[11] At [75].

[12] At [76]–[77].

[13] At [78].

[14] At [80].

[15] At [82].


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2022/380.html