You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2022 >>
[2022] NZCA 380
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Davies v K M Smith Builder Limited [2022] NZCA 380 (15 August 2022)
Last Updated: 23 August 2022
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
SIMON BERNARD DAVIES AND JUDITH GAY DAVIES Appellants
|
|
AND
|
K M SMITH BUILDER LIMITED First Respondent
KERRY MICHAEL
SMITH Second Respondent
|
Hearing:
|
11 July 2022
|
Court:
|
Clifford, Peters and Downs JJ
|
Counsel:
|
L A Andersen QC and S Gaskell for Appellants A D G Hitchcock for
Respondents
|
Judgment:
|
15 August 2022 at 10.30 am
|
JUDGMENT OF THE COURT
- The
appeal is dismissed.
- The
appellants must pay the respondent one set of costs for a standard appeal on a
band A basis and usual
disbursements.
____________________________________________________________________
REASONS OF THE COURT
(Given by Clifford J)
Introduction
- [1] The
appellants, Dr Simon and Mrs Judith Davies (the Davies), entered into a labour
and materials contract with the respondent
K M Smith Builder Ltd (the
Firm) for the building of a new home (the House). The second respondent, Kerry
Smith, is the half‑owner,
sole director and an employee of the Firm.
- [2] The
contractual relationship broke down and the Firm abandoned the site before the
House was completed.
- [3] The Davies
then sued the Firm and Mr Smith for damages of $1,031,690.54, representing
overcharging for building work and additional
fees incurred by the Davies.
- [4] The Davies
based that claim on nine causes of action. In the High Court Doogue J found in
favour of the Firm and Mr Smith as
regards each of those causes of
action.[1]
At the same time, the Judge upheld the Firm’s counterclaim for unpaid
invoices totalling $99,299.24. The Davies now challenge
the Judge’s
finding as regards one of those causes of action only, that is for misleading
and deceptive conduct under the Fair
Trading Act 1986.
- [5] In their
amended statement of claim the Davies formulated the Fair Trading Act 1986
causes of action against the Firm by reference
to an estimate of costs to
completion, and by reference to an initial estimate of overall costs. In the
judgment of the High Court,
those two factually separate causes of action
would appear to have been treated as one, and as involving both the Firm and Mr
Smith
on the same basis. That was the approach taken in this appeal, as
regards the completion estimates. We proceed on that basis.
- [6] In their
notice of appeal, the Davies say the Judge failed to specifically address their
eighth cause of action which alleged
that Mr Smith and the Firm had
misrepresented that the costs of completing construction of the House would not
exceed $700,000.
That misrepresentation, which occurred at a certain point in
the building process when difficulties had already arisen between the
parties, constituted a breach of the Fair Trading
Act.
Background
- [7] The facts
are not now in dispute. The following summary is based on the narrative set out
in the comprehensive judgment of Doogue
J in the High Court.
- [8] In 2001 the
Davies, through their family trust, purchased a property at Closeburn Station, a
high-country station in the Queenstown
Lakes district. Closeburn consists of 27
individual lots. With the purchase of a lot comes ownership of 1/27th of the
balance of
the station, and of that proportion of the shares in the management
company that conducts the farming operations on Closeburn and
maintains
the common areas. The Davies then employed an architect, Mr Scaife, to
design the House. At Mr Scaife’s suggestion
the Davies,
who lived overseas at the time, first built a cottage on the property.
- [9] In 2006 the
Davies commissioned a pricing process based on Mr Scaife’s plans. That
process generated an estimated cost
for the House alone, excluding hard
landscaping, driveways and the like, of $2.5 million exclusive of GST. The
Davies did not continue
with the building practitioner or the quantity surveyor
who conducted that process.
- [10] It was not
until mid-2014, after the Davies had met Mr Smith at the Christmas party of the
local medical centre of which Dr Davies
was an owner and at which Mrs Smith
was employed, that the Davies and the Firm entered into a contract to construct
the House.
- [11] The
contract required the Firm to build the “dwelling house and works ...
shown and described in the drawings and specifications
... signed for the
purposes of identification”, together with any variations agreed by the
owner, in a “thorough and
workmanlike manner” and in conformity with
the bylaws and regulations of local authorities having jurisdiction in respect
thereto.
Hourly rates were agreed for all work, together with a margin on
materials and subcontractors’ charges. Payment arrangements
and
other matters were also agreed.
- [12] The Judge
described the steps then taken to enable construction to begin in the following
way:[2]
[28] Between the
pre-building preparations in June 2014 and early 2016 the Davies and Mr Smith
oversaw a dynamic co-design construction
process. Both the Davies (primarily
Mrs Davies) and Mr Smith were adding layers of necessary detail to Mr
Scaife’s sparse
plans, and both parties were adding innovations to the
construction in an organic way. The relationship between the parties appeared
to be harmonious throughout this time.
[29] As the house plans had minimal detail it took a high level of project
management and building expertise to bring the plans to
life. There were
numerous areas where Mr Smith was required to interpret Mr Scaife’s
vision.
- [13] The Judge
described the subsequent construction process as follows:
[36] Mr
Smith said during the construction the Davies made multiple changes to what had
been set out in the original plans. Mrs Davies
would spend long periods perusing
building and design online and then would come to him with ideas and ask him to
achieve various
outcomes. She often selected products that would be considered
much more expensive than even an average high-end build.
- [14] The Judge
then provided various examples of ways in which that process worked,
concluding:
[42] These are just some examples of the number of
decisions that added to the overall build cost. More importantly, they
demonstrate
the fluidity with which the Davies approached the interpretation of
Mr Scaife’s design. Mrs Davies had many ideas and Mr Smith
worked
through the practicalities and logistics to make them a reality.
- [15] By early
2016 the Davies were becoming increasingly concerned at the time being taken to
complete the project and the costs they
were incurring to do so. Dr Davies
asked Mr Smith to advise him of some, but not all, of the estimated costs of
completion of the
House and for an itemised list of estimates for certain
subcontractors.
- [16] On 16 March
2016 Mr Smith provided the Davies with the requested estimate —
$448,295.27 — for specified subcontractors’
costs. At the same
time, he raised a series of questions about additional matters which, in terms
of Dr Davies’ request, he
had not provided for.
- [17] On 16 March
2016 Dr Davies sent the following email to Mr Smith:
Hi Kerry,
Could you please provide me with a letter (preferably on headed paper) that
the estimated costs of completion of our project will
be $700,000 please.
This will be used for the release of funds.
Regards,
Simon
PS give me a call if you need to discuss.
- [18] Mr Smith
provided a letter to the BNZ on 16 March 2016, as requested by Dr Davies,
confirming the “estimated” completion
costs were $700,000. It is
that letter which the Davies said in the eighth cause of action, exposes Mr
Smith and the Firm to liability
under the Fair Trading Act.
- [19] On 1 July
2016, and although the House was not by then completed, the Davies moved in.
The Davies stopped paying the Firm’s
invoices on 15 July 2016. By that
stage they had been charged a total of $3,607,429.54. The Firm issued a further
invoice on 20
July 2016 for $180,355.18.
- [20] The Firm
withdrew its services from the Davies in August 2016 without any discussion with
the Davies.
- [21] In 2017
after the dispute had arisen, Mr Smith gave a further estimate for completion of
$280,520.12. This was not accepted.
The Davies used other contractors to
complete the House at a cost of $183,620.15, almost $100,000 less than
Mr Smith’s quote.
The Davies’
claims
- [22] The Davies
commenced these proceedings in August 2019.
- [23] The Judge
summarised their claims in the following
way:[3]
(a) That Mr Smith made inducing representations that:
(i) he had the time and ability to project manage the building work;
(ii) construction of the House (including landscaping) would cost between $2.5
and $2.8 million (inclusive of GST); and
(iii) construction would be completed by March 2016, namely within 15 to 18
months of commencement of construction (November 2014).
(b) That the contract contained the following implied terms:
(i) Mr Smith would project manage the building work to ensure the cost of the
building work would be reasonable and in accordance
with the estimate of
costs;
(ii) the cost estimate was between $2.5 and $2.8 million (inclusive of GST);
(iii) the Firm would ensure the subcontractors costs were reasonable; and
(iv) the actual cost of the building work would be no more than $3 million.
(c) If the Court found Mr Smith did not make the alleged representations and the
contract did not include the implied terms, the
Davies claimed against the Firm
in contract and against Mr Smith in negligence for failing to adequately project
manage the construction
of the House.
(d) The Firm and Mr Smith were liable under s 9 of the Fair Trading Act for
misleading or deceptive conduct constituted by the provision
of the March 2016
estimate. The Davies’ allegation of misleading and deceptive conduct
against the Firm was the estimate of
costs given by Mr Smith and the reassurance
he gave that the cost would not exceed $3 million. Against Mr Smith, they
relied on
his letter of 16 March 2016 to the BNZ wherein he represented he
expected the cost of completion of construction at that time to
be no more than
$700,000.
High Court judgment
- [24] The Judge
first considered challenges the Davies had made to Mr Smith’s
credibility, and specifically — as the Judge
put it — that he was
“a dishonest man who both generally and in relation to the specific
allegations in this case acts
in bad
faith”.[4] It was in that
portion of her judgment, to which we return, that the Judge considered the claim
of misleading and deceptive conduct
as regards the estimate letter, and two
other instances of actions of Mr Smith in connection with the contract said to
demonstrate
his dishonesty.
- [25] The Judge
concluded the matters the Davies had raised did not establish Mr Smith
generally acted in bad faith and
lied.[5]
- [26] She then
went on to consider the claims of misrepresentation and breach of implied terms.
In general terms she found Mr Smith
had not made the alleged inducing
pre-contractual representations.[6]
Nor were there implied terms in the contract the cost of construction did not
exceed $3 million or that the building would be completed
by March 2016. There
was an implied term in the contract the cost of construction would be
reasonable, but the Davies had failed
to prove it was
not.[7] Likewise, there was an
express term in the contract the Firm would project manage the construction, and
Mr Smith owed the Davies
a duty of care to do so adequately. He had failed
to discharge that duty, but only to a limited extent entitling the Davies to
damages
of $4,364.50.[8]
- [27] The Judge
noted it had been agreed by the parties that if the Davies failed in their
causes of action the amount they owed the
Firm was $75,334.74 plus interest of
$23,964, totalling $99,299.24. Deducting the amount of $4,364.50 meant that the
Davies were
ordered to pay the Firm
$94,934.74.[9]
The
appeal
- [28] On appeal,
and reflecting the Davies’ notice of appeal, Mr Andersen QC argued the
Judge had failed to address the Davies’
Fair Trading Act claim, so that we
should do so. In the alternative, he argued that, to the extent the Judge had
addressed that
claim, she had erred in her finding that Mr Smith had not
incurred liability when he gave the estimate as Mr Smith must have known
it was
incomplete and that the Davies would rely on it. For Mr Smith,
Mr Hitchcock argued that, on the evidence, the Davies knew
full well the
Firm and Mr Smith had not made a full estimate of anticipated or actual
completion costs. Whilst Mr Smith had regretted
sending the letter, he had done
so because the Firm was owed a significant amount of money by the Davies at that
time.
- [29] This matter
is best considered in the context of the analysis the Judge undertook of Mr
Smith’s conduct in providing the
estimate when she considered
the Davies’ general challenge to his credibility.
- [30] There was
no doubt, the Judge found, that Mr Smith, as he had acknowledged, had sent the
estimate to the bank as a result of
the Davies’ request to do so. It was
also apparent that the estimate of $700,000 fell short of the actual amount
required
to finish the building of the House and was itself incomplete.
- [31] Reviewing
the circumstances in which the estimate was provided by Mr Smith, the Judge made
the following factual findings:
(a) It was apparent that Dr Davies had requested itemised costs for certain
sub‑trades only.[10]
(b) The figure Mr Smith sent provided estimated costs to completion for a number
of sub-trades but not all. Nor did it include labour
costs generally, or labour
and material costs for sub-trades for major components of the overall
building.[11]
(c) Nor did it contain an estimate of costs for the Firm’s labour, as
Dr Davies preferred to undertake that exercise himself.
It was evident on
the face of the written estimate that Mr Smith was raising as many questions as
he was providing answers.[12]
- [32] The Judge
then went on:
[78] Initially Dr Davies insisted in
cross-examination that the document Mr Smith had provided was a list of all
outstanding work
and an estimate of all completion costs. He did subsequently
concede that a large number of quite fundamental building elements
were not
included in the document. Dr Davies was questioned by Mr Hitchcock on the
document as follows:
- This
is just his attempt to respond to your request,
isn’t it?
A. And my request was unfortunately
inaccurate.
[79] Thus the estimate was already compromised by three significant
omissions. It did not contain the full complement of subcontractor
costs, nor
did it contain the labour costs. The parties were also yet to settle on the
full extent and design of the hard landscaping
so that was not costed
either.
[80] In cross-examination, Dr Davies accepted that he sent the email asking
Mr Smith to write the letter to the BNZ and he explained
how the $700,000 figure
was arrived at. The evidence established that the figure of $700,000 was a
figure devised by Dr Davies and
his banker, not by Mr Smith.
[81] It is unfortunate Mr Smith sent the letter, but it was commissioned for
the purpose of assisting the Davies and the bank with
financial planning. It
was not commissioned for the purpose of Mr Smith undertaking and crystallising
the actual costs of construction.
That would have been obvious to both parties
because of the exclusion of the major components identified ...
[82] I note further that it would not have been possible to ascertain an
accurate estimate of the trades excluded from the estimate,
as the parties were
still working through what was required in respect of these elements as part of
their organic collaborative interpretation
and co-design.
[83] I consider it is disingenuous of the Davies in these circumstances
(which they created) to assert Mr Smith represented to them
the actual costs
completion in March 2016 were $700,000 and to rely on it to allege he acted in
bad faith and misled them.
[84] For the reasons I have set out above, I also do not consider this
letter is proof that Mr Smith represented to the Davies the
actual costs of
completion to be $700,000. I find that he was obviously misguided in sending
the letter to the bank, but I do not
consider the letter proves in and of itself
that Mr Smith has been dishonest in his dealings with the Davies
Analysis
- [33] In face of
those findings, which in our view constitute the Judge’s assessment and
determination in Mr Smith and the Firm’s
favour of the Davies’ Fair
Trading Act claims, Mr Andersen argued the Judge had missed the point. The
Davies’ claim
was not that Mr Smith was misleadingly representing the
actual costs of completion (see [83] and [84] of the judgment). It was
clear
what was provided was an estimate.
- [34] Rather the
Davies’ argument was that Mr Smith knew the estimate was incomplete and
that he knew the Davies were relying
on it — in effect as if it were an
estimate of all construction costs to completion. Hence his action of providing
the letter
requested by the bank and by Dr Davies without further comment or
qualification was misleading and deceptive. Moreover, it did not
matter under
the Fair Trading Act that Mr Smith may not have intended to deceive the
Davies. Dishonesty is not a requirement of
a claim under that Act.
- [35] The 16
March 2016 letter was clearly not, as the Judge described it on several
occasions, a statement of the actual costs of
completion. That is clear from
the terms of Mr Smith’s letter to the bank itself. Nor was it, understood
in context, a statement
of an estimate of all costs to completion.
The following, unchallenged, findings of fact in our view mean that the
estimate could
not have misled or deceived the Davies so as to constitute, as
between them and Mr Smith, misleading and deceptive conduct by Mr
Smith:
(a) The original list of estimated costs of outstanding work responded to Dr
Davies’ request which, as he acknowledged, “was
unfortunately
inaccurate”.[13]
(b) Dr Davies accepted he sent the email asking Mr Smith to write the letter to
the BNZ and that the figure of $700,000 was one reached
by Dr Davies and
his banker, not by Mr Smith.[14]
(c) At the time of Dr Davies’ original request, and of Mr Smith writing
the letter, it would not have been possible to ascertain
an accurate estimate of
the elements of outstanding work that were not included in the list
Dr Davies sent to Mr Smith as the parties
were still to finalise the scope
of required work.[15]
- [36] Both the
Davies and Mr Smith were under pressure: the Davies it would appear from their
bank and Mr Smith from the financial
difficulties of the Davies. Dr
Davies’ agreement with the bank as to the quantum of additional funding to
be provided, and
Mr Smith’s unfortunate decision to provide the requested
letter, were both products of those pressures. But, as the Judge
found, in all
the factual circumstances it would be unrealistic and unfair to categorise the
sending of the requested letter as constituting
misleading and deceptive conduct
in trade as between Mr Smith and the Davies.
Result
- [37] The appeal
is dismissed.
- [38] The
appellants must pay the respondents one set of costs for a standard appeal on a
band A basis and usual
disbursements.
Solicitors:
Teresa Chan Law
Ltd, Dunedin for Appellants
AWS Legal, Invercargill for Respondents
[1] Davies v K M Smith Builder
Ltd [2021] NZHC 2865 [Judgment under appeal].
[2] Judgment under appeal, above n
1.
[3] Judgment under appeal, above n
1, at [3]–[7].
[4] At [58].
[5] At [66] and
[84]–[85].
[6] At [93], [118], and
[125]–[128].
[7] At [152].
[8] At [153], [157], [192] and
[215].
[9] At [242]–[244].
[10] At [73].
[11] At [75].
[12] At [76]–[77].
[13] At [78].
[14] At [80].
[15] At [82].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2022/380.html