You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2022 >>
[2022] NZCA 423
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Lysaght v Whakatâne District Council [2022] NZCA 423 (8 September 2022)
Last Updated: 12 September 2022
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
IAN WALLACE LYSAGHT AND ADRIANNE JUNE LYSAGHT Appellants
|
|
AND
|
WHAKATĀNE DISTRICT COUNCIL First Respondent
|
|
AND
|
GULATI ENTERPRISES LIMITED Second Respondent
|
Hearing:
|
16 November 2021
|
Court:
|
French, Cooper and Gilbert JJ
|
Counsel:
|
M J E Williams for Appellants A M B Green for First Respondent V
J Hamm and T J Conder for Second Respondent
|
Judgment:
|
8 September 2022 at 4:00 pm
|
JUDGMENT OF THE COURT
- The
appeal is dismissed.
- The
appellants must pay the respondents’ costs for a standard appeal on a band
A basis and usual
disbursements.
____________________________________________________________________
REASONS OF THE COURT
(Given by Cooper
J)
Table of Contents
|
|
Para No
|
Introduction The application and the district plan
The High Court proceeding The appeal Summary of
arguments on appeal The condition precedent argument The r
13.4.7.1 and cumulative effects argument Analysis
The statutory scheme
The condition precedent argument
The r 13.4.7.1 and cumulative effects argument
Result
|
|
Introduction
- [1] The
Whakatāne District Council (Council) granted a non-notified application for
resource consent by Gulati Enterprises Ltd
(Gulati) to develop an unmanned
service station with four petrol pumps and a truck stop, which would operate
under the Mobil brand.
The site has frontage both to
State Highway 30 and an unnamed
Māori roadway (Roadway). Vehicles would enter the site from the
Roadway, having made a left-hand
turn off State Highway 30 before turning right
into the station. After refuelling, vehicles would leave the site by
turning left
at a vehicle crossing giving access directly onto State
Highway 30.
- [2] The
appellants, Ian and Adrianne Lysaght, are co-owners of the Roadway together with
Gulati and two whānau of Ngāti
Awa. The Lysaghts have been
engaged in property development in the area for decades. They are trustees of
two family trusts which
have formed a partnership trading as Lysaght
Developments. They are in the course of promoting an industrial subdivision on
land
opposite the proposed service station. They considered they were adversely
affected by Gulati’s proposal and commenced an
application under the
Judicial Review Procedure Act 2016 challenging the Council’s decision to
deal with Gulati’s application
without either public or limited
notification under the Resource Management Act 1991 (RMA).
- [3] An
application for judicial review was also made by Te Rūnanga o Ngāti
Awa. Both applications were heard by Whata J
in the High Court.
The application by Te Rūnanga o Ngāti Awa was successful in
part and resulted in the High Court setting
aside the decision to grant the
resource consent application on a non-notified
basis.[1]
But the Judge dismissed the Lysaghts’ application and they have
appealed against
that decision.[2]
- [4] Given that
the result of the High Court judgment was to set aside the consent granted to
Gulati, we initially entertained some
doubt as to whether the appeal was moot;
however, in the absence of opposition by the respondents, we decided that
we should hear
the appeal and determine it. Principally, that was because the
issues of concern to the Lysaghts are likely to arise again in the
context of
the Council’s reconsideration of Gulati’s resource consent
application, which must now be dealt
with afresh.[3]
The application and the district plan
- [5] Gulati’s
proposed service station would be located on land zoned
“Light Industrial” in the Council’s operative
district
plan. Under r 3.4.1.1(27) of the district plan, “Service stations”
in the Light Industrial zone are a permitted
activity. That means, pursuant to
s 87A(1) of the RMA, that the service station activity does not require resource
consent unless
it fails to meet some other requirement of the district plan. In
this case, resource consent was required because:
(a) The proposed Mobil pylon sign would exceed the maximum permitted signage
display area of 12 m2 under r 11.2.19.1. The proposed sign
would be 12.5 m2 in area. This aspect of the proposal required
discretionary activity consent.
(b) The Roadway would not meet the required minimum width of 18 m under r
13.2.2. Works proposed to be carried out in conjunction
with the service
station development would widen the Roadway to 10 m. For this,
discretionary activity consent was required.
- [6] As is often
the case, a report was prepared for the purposes of the Council’s decision
which dealt with both the notification
issue and the decision of whether consent
should be granted (the Report). Dated 23 April 2020, the Report reflected
modifications
to the application that had taken place in discussions and
correspondence between representatives of both the Council and Gulati
as the
notification issue was being considered. In its final form, the proposal was
granted consent for a 24-hour, 7‑days-a-week,
unmanned service station
with four petrol pumps and a truck stop. There would be two 60,000 litre
underground fuel storage tanks,
four light vehicle petrol pumps and one truck
petrol pump. The tank installation would require earthworks, and there would be
landscaping
around the perimeter of the site.
- [7] On the
question of site access, the Report recorded:
2.2 Site access is
proposed to be provided from SH30 via the Māori Roadway. Two new
vehicle crossings are located on the western
boundary of the lot to facilitate
this. Other physical works are also proposed within the Māori Roadway
to facilitate access.
Egress is proposed to be provided by way of a new vehicle
crossing to SH30 at the south-east corner of the site. No-right-turn
rules will
be imposed for traffic entering SH30 from the Māori Roadway and at the site
egress.
2.3 The applicant proposes to install a median strip within the
New Zealand Transport Agency (NZTA) SH30 corridor for a distance of
approximately 150m from the western end of the existing median leading to the
SH30/Keepa Road roundabout.
The new median will therefore extend past the
Māori Roadway to approximately halfway along the frontage of the
property to
the west ... A deceleration lane is also proposed. ...
- [8] Because of
the egress to State Highway 30, written approval of the New Zealand
Transport Agency (NZTA) was required, and this
was provided on 9 October
2019. The Council asked Gulati to provide written approvals from the other
co-owners of the Roadway, but
Gulati declined to do so. The Report
observed:
Further consideration of this matter has been undertaken
following close consideration and refinement of the areas of non-compliance,
including the matters to which discretion is restricted, and after seeking a
legal opinion. It is now concluded that written approvals
are not required
to enable the application to be processed non-notified. This is addressed
further elsewhere in this report.
- [9] During the
processing of the application the Council’s roading engineers raised some
concerns about heavy vehicles needing
to cross the centre line of the Roadway
while making the left-hand turn from State Highway 30. Issues were raised as to
whether
the Roadway was sufficiently wide to enable safe and efficient access to
heavy vehicles, and whether there was the potential for
unacceptable conflict
with other users of the Roadway. The Report recorded:
This was
communicated to the applicant on 30 March and a written response was provided on
6 April, followed by a meeting between the
engineers and the applicant on 14
April. Conditions were agreed as a consequence. An amended plan was provided
by the applicant
on 20 April and accepted by Council Manager Transportation
on 22 April 2020.
- [10] The Report
took the approach that the non-compliance of the Mobil pylon sign would not have
an impact on the potential effects
of the activity as a whole. This meant
that although discretionary activity consent was required to exceed the maximum
signage area
allowed by the district plan, that would not have the effect of
requiring the whole application to be considered as a discretionary
activity.
In the result, the remaining issue that required consent, being the width of the
Roadway, was able to be considered as
a restricted discretionary activity
under the relevant district plan rules.
- [11] Rule 13.2.2
of the district plan is headed “Roads and Property Access (excluding State
Highway)”. Rule 13.2.2.1
provides:
Any new road or
accessway shall be designed, constructed and located to accommodate the
volume and type of traffic likely to use it in a safe and efficient
manner.
- [12] Rule
13.2.2.2 then relevantly provides:
Compliance with the following
standards shall satisfy Rule 13.2.2.1. Non‑compliance with these standards
shall be considered
a Restricted Discretionary activity:
- Roads
and accessways shall be designed to meet the design standards set out in
Appendix 13.7.5. Widths shall be selected to ensure that adequate movement
lanes, footpaths, berms, and batters can be provided to retain amenity values
(including landscaping) and enable utility services
to be provided safely and in
economical and accessible locations;
...
- [13] The
design standards set out in Appendix 13.7.5 require a minimum road width of 18
m, eight metres more than what was proposed.
Rule 13.4.7 specifies matters that
the Council can consider when determining an application that is not compliant
with r 13.2.2.2.
That Rule, also headed “Roads and Property Access
excluding State Highway”,
provides:
13.4.7.1 Council shall restrict its discretion
to;
a. traffic volumes and traffic mix relative to existing and future
patterns, access, parking and loading on-site;
b. pedestrian and cyclist safety;
c. construction traffic volumes, traffic mix and hours of operation;
d. the ability of the site to accommodate the traffic anticipated and the
nature of the adjacent roading pattern, including the
position of the road in
the roading hierarchy;
e. formation of the road or access;
f. the total land area proposed to be used for access, parking and loading
in the Rural Plains Zone; and
g. aspects of the proposal that could compromise the safety and convenience
of pedestrians as well as individual and cumulative
adverse effects associated
with traffic movements.
- [14] The Report
examined each of these considerations with the exception of r 13.4.7.1(f),
which did not apply. The High Court quoted
this section of the Report in
full.[4] It is not necessary for us
to set it all out again. It is sufficient for present purposes to give a
summary highlighting the most
relevant extracts.
- [15] In relation
to the first consideration the Report went into some detail. This was as
follows:[5]
▪ Traffic
volumes and traffic mix relative to existing and future patterns, access,
parking and loading on-site;
6.11 The effects on the state highway, the intersection with
State Highway 30, and the wider roading network have been addressed
through
the Transportation Assessment provided as part of the application with
further information provided by the applicant between 14 February
and 2 March
2020. These effects have been concluded to be less than minor.
6.12 In relation to the traffic flow and existing and future traffic patterns
within the Māori Roadway, the applicant provided
additional evaluation on
28 February 2020 highlighting the low traffic generated by existing
activities which future use for industrial
purposes would increase from 1-2
trips per hour (tph) to 8tph. Additional information was requested to review
the potential for
conflict between safe pedestrian access and service station
traffic, including in particular heavy vehicles turning into the roadway,
with
the need to cross into the opposing traffic lane and then enter the service
station from the roadway. This was provided on
6 April 2020 and an amended plan
provided to Council on 20 April 2020.
6.13 The additional information has been reviewed by Council’s
Transportation team. The Council is now satisfied that the amended
design
provides appropriately for safe access for all users of the roadway and into the
site from the roadway. It will minimise
the potential effects on other sites
served by the Māori Roadway and the potential conflict arising from
vehicles crossing the
roadway to enter the service station. The assessment
provided by Traffic Solutions Ltd ... identified that there were potential
benefits for future users of the roadway arising from the upgrade, as
follows:
“The trafficable width of the roadway is presently about 7m where
vehicles turn into it from the highway. This is quite narrow
for an access to
industrial zoned land where truck movements are expected to be generated, and
the kerbs at the intersection with
the highway presently require all trucks,
even rigid trucks, to cross the centreline when turning into the roadway. If
the fuel
facility proceeds then the roadway at its entry will be widened
considerably to accommodate large truck rigs that the development
will generate.
This will provide a benefit to the other lots served by the roadway because
more width will be available for heavy
vehicles associated with any future
industrial development to turn into the roadway without unduly obstructing
exiting vehicles,
a situation that cannot presently occur.”
6.14 The upgrade will therefore provide appropriately for future industrial
use of sites served by the roadway. There will be some
change in effects for
those living on or served by the roadway, but the level of changes [is] not
unreasonable or unanticipated since
the land was subdivided in 1999 ... and
zoned for industrial use. In addition, the applicant has demonstrated that
large trucks
can still practically manoeuvre within the 10m width, albeit
utilising the full width, and two-way traffic movements are possible.
The
proposal and technical non-compliance with width does not change the overall
type and volume of traffic anticipated and legally
able to use the roadway now
and in the future, based on the zoning of the land. The scale of adverse
effects is therefore concluded
to be generally acceptable and less than minor as
a result of the non-compliant width.
- [16] The Report
also addressed pedestrian and cyclist safety, the second of the district plan
assessment considerations. It noted
that there was currently limited pedestrian
and bicycle movement along the Roadway and State Highway 30, and said the
service station
activity was not expected to change demand or use because
it lacked a retail component that could attract pedestrians or cyclists.
Future
development leading to increased movement of people and cyclists on the Roadway
would be accommodated, in the amended design,
by means of a footpath to be
located on the eastern side of the Roadway.
- [17] The Report
went on to state that the potential effects of construction traffic would be
controlled by consent conditions, and
any adverse effects were considered to be
temporary and less than minor. No adverse effects on State Highway 30 and the
wider roading
network were anticipated as a result of traffic generated by the
service station. The Roadway would be able to accommodate the traffic
leaving State Highway 30 on its way into the service station.
- [18] As
to “formation of the road or access”, the consideration in
r 13.4.7.1(e), the Report noted simply that Council standards would
be complied with and “conditions are
recommended”. The Report then
addressed the final consideration, that in r 13.4.7.1(g), as
follows:
6.20 The evaluation relates to the under width roadway and
the effect on both these aspects has been evaluated above.
6.21 The upgrade works to the intersection of the state highway and roadway,
including the deceleration lane and widening, are expected
to be compatible and
support further development of the other light industrial land served by the
roadway and may avoid the need
for further works in the future by subsequent
developers. This could in turn facilitate development of the land, as
anticipated
[by] the District Plan. Whilst not a consideration for the
notification decision, these positive effects may be considered as part
of the
substantive decision under [s 104] of the RMA.
- [19] It was in
the context of that discussion that the Report reached the conclusion that the
effects of the proposal on the environment
would be less than minor. Further,
the Report stated:
6.24 The effects of the proposal have been
considered in relation to adjacent properties, particularly those at 46B and 46D
State
Highway 30 which are used for residential purposes, but are
zoned Light Industrial. The service station itself would be a permitted
activity if the roadway was 8m wider to meet the access standard.
The aspects such as noise, lighting, and traffic generation are
compliant
with the permitted activity standard and on-going compliance can be required
through conditions. Therefore, although the
relationship may not be favourable
for the existing residential activities, there are no rules in the [district
plan] through which
more rigorous standards can be imposed.
- [20] The Report
formed the basis of the Council’s decision. The Council’s
Manager of Resource Consents, Mr Avery, granted
consent under delegated
authority by signing the last page of the Report on 24 April 2020, ticking a box
marked “[g]ranted
subject to the conditions of consent specified [in the
Report]”.
- [21] It is
relevant to note that among the conditions were some requiring the development
to take place in accordance with plans submitted.
Gulati was also required,
amongst other things:
(a) to provide a report to the Council’s General Manager of Planning and
Infrastructure from an independent, qualified road
pavement engineer on the
current structural capacity of the Roadway, the impact of increased traffic and
the need for any additional
structural strengthening of the Roadway pavement.
If structural strengthening was required, Gulati would need to reconstruct the
pavement to meet any new design life requirements; and
(b) before commencing the service station operation, to complete all
road‑upgrading works as shown in a report from Traffic
Solutions Ltd and
the road pavement report mentioned above. The road-upgrading works were to be
undertaken in accordance with the
Council’s Engineering Code of Practice
and certified by the General Manager of Planning and Infrastructure.
- [22] Other
conditions dealt comprehensively with the specifics of the road‑upgrading
works, and their formation and construction.
The works on
State Highway 30 were also required to be implemented in accordance
with NZTA’s requirements prior to the commencement
of the operation of the
service station.
The High Court proceeding
- [23] In
the High Court, the Lysaghts advanced three grounds in support of their
application for judicial review. First, it was said
the Council had failed to
have regard to the effects of the proposed median strip to be located on
State Highway 30, which was said
to be a mandatory consideration under
r 13.4.7.1 of the district plan. Secondly, it was claimed the decision was
unreasonable insofar
as the co-owners of the Roadway were not considered to
be affected persons and there was no reasonable basis for the Council’s
conclusion that the effects on the Lysaghts would be less than minor.
Thirdly, it was said the Council erred in law in determining
that there would be
no adversely affected parties on the basis of the mitigation works
proposed, which was reliant on both third‑party
land and third-party
approval in order to proceed. This allegation included a claim that it was
beyond a consent authority’s
lawful powers to approve a resource consent
application on the basis of mitigation that would involve or infringe on a third
party’s
rights.
- [24] The Judge
rejected each of these grounds. Insofar as the median strip was concerned, he
noted it was a permitted activity and
could be built at any time with approval
of the NZTA. It was therefore open to the Council, pursuant to s 95E(2) of the
RMA, to
disregard any effects of the median strip on the co-owners of the
Roadway.[6] The Judge considered
there was nothing in the evidence to suggest that the Council’s decision
on this issue was unreasonable.
He noted that although the issue had not been
expressly addressed in the Report, correspondence between the Council and the
NZTA
showed that the Council’s transportation team had accepted the
installation of the median strip was
appropriate.[7] The Judge’s
conclusions on this issue were not challenged in this Court.
- [25] In respect
of the second cause of action, the Judge considered the
“central evaluative issue for the Council” was
whether the
co-owners of the Roadway and the occupiers of the land adjacent to it (including
the Lysaghts) would be adversely affected
by the proposal in terms of the safe
and efficient use of the Roadway, to a minor or more than minor degree, having
regard to the
considerations in r 13.4.7.1. The Judge considered it was
clear from the Report that the issue had been carefully considered on
the basis
of adequate information. He was satisfied the information demonstrated the
likely level of traffic movement that would
be generated was broadly what might
be expected in a Light Industrial zone and the probability of conflict between a
vehicle exiting
the Roadway and a heavy vehicle was “exceedingly small:
about 0.01 [per cent]”.[8]
- [26] This meant
that the Council’s conclusion as to the low level of effects on the
Lysaghts in terms of safe and efficient
use of the Roadway was plainly available
to it. The Judge said he was fortified in this conclusion by the absence
of any evidence
from an independent expert to the
contrary.[9]
- [27] The Judge
held, rejecting the Lysaghts’ argument to the contrary, that the need for
consent of the other co-owners of the
Roadway to the works proposed was a
separate property issue, not relevant under the RMA. He held that the RMA is
not concerned with
the enforcement of property rights, and a resource consent
does not authorise infringement of such
rights.[10] Here, the condition
imposed by the Council requiring the works to be carried out meant the Lysaghts
would need to consent or Gulati
would need to obtain a court order to enable the
works to be undertaken.[11]
The physical impacts on the Roadway were not, in any event, a relevant
consideration under
r 13.4.7.1.[12]
- [28] The
essence of the Judge’s reasoning for rejecting the third cause of action
appears from the following passages of the
judgment:
[76] In the
present case, there is no requirement for agreement to be reached with the
Lysaghts and the consent does not otherwise
purport to derogate from (or
deprecate) the Lysaghts’ existing property or consented rights. Quite the
reverse, the required
roadworks are expressly framed as a condition precedent to
the operation of the station, which carries no implication that the Lysaghts
must agree to or otherwise implement the proposed mitigation works. Rather, it
places the entire burden on Gulati to either obtain
the Lysaghts’
agreement or otherwise obtain lawful authority to undertake the requisite
roadworks. In this respect, the condition
is a paradigm example of a valid
condition precedent referred to by Fisher J in Westfield v Hamilton City
Council.
[77] Mr Williams sought to distinguish the Westfield v Hamilton City
[Council] condition precedent on the basis that the present
condition related to private land, not public land or public works. But
that is a distinction without consequence because, as I have said, Gulati
must obtain the Lysaghts’ agreement or otherwise obtain lawful
authority to undertake the roadworks. In the result, the Lysaghts’
property rights, including to the use and enjoyment of the Roadway,
remain unaffected until that agreement or the requisite court order has
been obtained.
- [29] The Judge
noted a further submission by the Lysaghts that it did not make resource
management sense to impose conditions requiring
a range of works to be carried
out on a road without involving the other co-owners of
it.[13] However, he considered
it significant that the relevant conditions were expressed in terms that
required the works to be carried
out before the service station operation could
commence on the site. He considered this was a valid condition precedent. To
the
extent that the works would be necessary on private land, that simply meant
that Gulati would need to obtain agreement from the Lysaghts
or otherwise obtain
lawful authority to undertake the
works.[14]
The
appeal
Summary of arguments on appeal
- [30] The
principal argument addressed in this Court was that the High Court was
wrong to determine the Lysaghts were not affected
parties on the basis of the
“condition precedent” principle addressed in Westfield (New
Zealand) Ltd v Hamilton City
Council.[15]
- [31] Mr Williams
also submitted the High Court erred in finding that the effects of the physical
impacts on the Roadway, which the
Court accepted were adverse on the
environment, were not relevant under r 13.4.7.1 of the district plan. Mr
Williams further argued
that the combination of the effects of the modifications
to the Roadway and the traffic that would be generated by the service station
amounted to effects on the Lysaghts that were at least minor, and it was
unreasonable for the Council to have concluded otherwise.
The latter submission
reflects the relevant provisions of the RMA concerning public notification and
limited notification, which
we discuss below.
The condition
precedent argument
- [32] Turning
to the “condition precedent” issue, Mr Williams argued that because
they were co-owners of the Roadway, the
Lysaghts should have been regarded as
affected persons for the purposes of the RMA. He noted that they faced the
prospect, recognised
by the High Court, of a significant increase in use of the
Roadway and multi-rig trucks crossing the centre line when turning into
it. The
Lysaghts’ land would be called upon to mitigate those effects. Mr
Williams submitted that the principle discussed
in Westfield was not
designed to address this type of situation. He argued that a resource
consent condition that infringes third-party rights
or requires the consent of a
third party is invalid, relying on Dart River Safaris Ltd v
Kemp.[16]
- [33] Mr Williams
also submitted that, as a matter of principle, it did not make resource
management sense to impose conditions requiring
a range of works to be carried
out on the Roadway without involving all its co-owners. Mr Williams contended
that, on the facts
of this case, the condition precedent imposed by
the Council could not and would not cure what he described as
“property related
physical impacts”, which the High Court had
otherwise found to be relevant effects on the environment. He
submitted:[17]
The
reason for that is that in this situation the Consent Decision is being relied
on as the platform for seeking orders from the
Māori Land Court, directing
that the owners of the roadway ‘permit’ the very improvements to
the Roadway required
by the resource consent for the service station.
- [34] Mr Williams
claimed the road-improvement works required by the conditions of consent could
be completed against the Lysaghts’
will by the direction of the
Māori Land Court. He complained that, at the very least, the Lysaghts
will be forced to defend
their position in that Court, “the resourcing of
which [would be] an adverse effect occasioned by the Consent Decision, in
its
own right”. Mr Williams said this was another basis upon which the
present case could be distinguished from Westfield.
The r
13.4.7.1 and cumulative effects argument
- [35] Mr
Williams then mounted a separate argument based on r 13.4.7.1.
He submitted the High Court was wrong to decide that the physical
impacts
of the works on the Roadway, which were necessary to meet the conditions of
consent, did not fall within the scope of the
discretion reserved for the
Council under r 13.4.7.1(e), which we have set out at [13] above.
- [36] Mr Williams
accepted the High Court was right to hold that the considerations in
r 13.4.7.1 are directed to the achievement of
the objective expressed in
r 13.2.2.1, namely that any new road or accessway must be “designed,
constructed and located to
accommodate the volume and type of traffic likely to
use it in a safe and efficient manner”. Mr Williams emphasised the fact
that the objective referred to construction and argued that it should not be
interpreted in an unduly narrow way. On that basis
he submitted the High
Court was wrong to conclude on the one hand that property‑related physical
impacts were environmental
effects of legitimate relevance under the RMA for
general purposes but then, on the other hand, exclude them from the ambit of the
restricted discretion available to the Council in this particular case.
- [37] He
also submitted there were cumulative effects establishing that the Lysaghts were
adversely affected to an extent that was
at least minor in terms of s 95E
of the RMA. He listed the effects of concern as:
(a) the effects of physical works associated with widening and reforming the
Roadway, including proposed curb realignments;
(b) the delays and inconvenience experienced during the construction phase of
the project;
(c) the permanent and ongoing effects resulting from the greater frequency of
vehicles using the Roadway, including by multi-rig
trucks crossing the
Roadway’s centre line on an irregular but ongoing basis; and
(d) the possibility of further widening being required, encroaching directly on
the Lysaght Developments’ office site. This
was in reference to a plan
showing a possible widening of the Roadway on the Lysaghts’ land with the
label “[p]ossible
alternative kerb setback by others”. However,
this was not proposed as part of the resource consent application,
nor required
by the consent, and we do not need to address it further.
- [38] Mr Williams
also criticised the reasoning in the Council’s decision, which he claimed
had been endorsed by the Judge, that
drew on the assumed benefits of the works
on the Roadway in concluding that the effects would be less than minor.
This, Mr Williams
said, was wrong: the test for notification is limited to
adverse effects and should not take into account compensating or offsetting
positive effects.
- [39] For all
these reasons Mr Williams submitted that the decision to exclude the Lysaghts
from the consent process on the basis they
were not adversely affected persons
was unlawful, irrational and unreasonable.
- [40] Mr Green,
for the Council, and Ms Hamm and Mr Conder, for Gulati, made submissions in
support of the reasoning in the High Court
judgment. Their submissions are
reflected in the analysis that follows.
Analysis
The statutory scheme
- [41] Although
the statement of claim before the High Court alleged error by the Council in
deciding both not to publicly notify the
application or require limited
notification, the focus of the argument in this Court was on ss 95B and 95E
of the RMA, which relate
to limited notification. Under s 95E(1), for
the purposes of giving limited notification of an application for resource
consent,
a person is an affected person if the consent authority decides the
activity’s adverse effects on that person are “minor
or more than
minor (but are not less than minor)”. Mr Williams’ arguments were
designed to establish that the adverse
effects on the Lysaghts were
at least minor.
- [42] Under
s 95E(2)(b), because of the proposal’s status as a restricted
discretionary activity, the Council was obliged, in
assessing adverse effects on
the Lysaghts, to disregard any adverse effects that did not relate to a
matter to which the Council
had restricted its discretion. So the necessary
analysis could only relate to the matters set out by the Council in
r 13.4.7.1 of
the district plan.
- [43] The
provisions of s 95E(2) are consistent with s 87A(3) of the RMA,
which provides:
87A Classes of activities
...
(3) If an activity is described in this Act, regulations (including any
national environmental standard), a plan, or a proposed plan
as a restricted
discretionary activity, a resource consent is required for the activity
and—
(a) the consent authority’s power to decline a consent, or to
grant a consent and to impose conditions on the consent, is restricted
to
the matters over which discretion is restricted (whether in its plan or proposed
plan, a national environmental standard, or otherwise);
and
(b) if granted, the activity must comply with the requirements,
conditions, and permissions, if any, specified in the Act, regulations,
plan, or
proposed plan.
- [44] Consistent
with that again, under s 104C of the RMA, when considering an application
for resource consent for a restricted discretionary
activity, the Council must
consider only those matters to which it has restricted the exercise of its
discretion.[18] Further, under
s 104C(3), if the Council grants the application, it may impose conditions
only in respect of those same
matters.[19]
- [45] These
provisions together form a coherent group which makes it plain that, in the
case of restricted discretionary activities,
at each stage of the consent
process only those matters to which the Council has restricted the exercise of
its discretion may be
considered. This was underlined by the Supreme Court in
Auckland Council v Wendco (NZ)
Ltd.[20] The Court confirmed
that unless a relevant adverse effect can be said to be a matter to which the
Council has reserved discretion,
it must be disregarded. In so holding the
Court rejected an argument that would have introduced “a disconnect
between ss 95E(2)
and 104C”, which would not be “consistent with the
overall legislative
scheme”.[21]
- [46] Before
turning to the matters to which the Council reserved the exercise of discretion
in this case, some general observations
are appropriate.
- [47] First, it
is appropriate to emphasise that the RMA is an environmental statute: its
purpose, set out in s 5(1), is “to
promote the sustainable management
of natural and physical resources”. “Natural and physical
resources” is a widely
defined term embracing “land, water, air,
soil, minerals, and energy, all forms of plants and animals (whether native to
New
Zealand or introduced), and all
structures”.[22] Similarly,
the definition of sustainable management in s 5(2) refers to the
“use, development, and protection of natural and
physical
resources”, and “avoiding, remedying, or mitigating any adverse
effects of activities on the environment”.
- [48] Resource
consents must be obtained for land uses that, amongst other things, contravene a
rule in a district plan.[23]
“Use” is another term comprehensively defined to include a wide
range of actions in relation to
land.[24] Consistent with these
provisions, s 87 defines the term “resource consent” as meaning
a consent to do something that
otherwise would contravene s 9 or s 13:
this is a “land use
consent”.[25] Other kinds of
consent are subdivision consents, coastal permits, water permits and discharge
permits.[26] These are all
activities in relation to natural resources.
- [49] A resource
consent for a restricted discretionary activity is a particular kind of land use
consent. None of the relevant statutory
provisions discussed above, whether
expressly or by implication, extends to property rights. Property rights arise
under the general
law or pursuant to statutes other than the RMA. This is
reflected in the fact that under s 122(1) of the RMA, a resource consent
is
said to be neither real nor personal
property.[27]
And while the holder of a land use consent to do something that would otherwise
contravene s 9 may transfer the consent under s 134(3),
that is the
exercise of a statutory right, not a property right.
- [50] The RMA
enables a resource consent application to be made in respect of any land.
The applicant does not have to own the land,
or occupy it actually or
prospectively (although implementation of a consent will obviously require
permission from the landowner
if that person is not the consent holder).
Additionally, rights to make submissions if an application is notified are given
broadly
without a standing qualification: s 96(2) states simply that any
person may make a submission.[28]
- [51] We note
further that s 95E(1) makes it plain that a person is an
“affected person” if the consent authority considers
that the
activity’s adverse effects on the person are minor or more than minor.
The effects are on the person; they include
effects on the person’s
property, but not the person’s property rights. Such rights are not
natural and physical resources.
- [52] These
general observations establish the appropriate context in which to address two
of the arguments advanced in support of
the appeal. First, it is not possible
to ground in the statutory scheme an argument that a person should be regarded
as an “affected
person” for the purposes of s 95E because an
application for resource consent might have an impact on that
person’s property
rights as opposed to the property itself. The RMA
is concerned with the latter, not the former. Secondly, a resource consent
cannot
confer a right to use land which the consent holder does not own, or have
the right to occupy, so as to enable exercise of the consent.
A council cannot
confer such a right by granting resource consent. It obviously has no general
power to do so and no such power
is conferred by the RMA
itself.[29] Mr Williams’
contention that the Council should in some way have been influenced by the fact
that interested parties other
than Gulati share property in the Roadway is not a
proposition which finds support in the RMA.
The condition
precedent argument
- [53] These
general observations about the nature of the RMA also point to the resolution of
the Lysaghts’ “condition precedent”
argument. Unless or until
Gulati obtains the authority necessary to carry out the works on the Roadway
required as a condition of
consent, there will be no impact on the
Lysaghts’ property interests.
- [54] The
resource consent could not and did not purport to authorise the carrying out of
works against the wishes of the other co-owners
of the Roadway. It is doubtless
for this reason and in anticipation of the Lysaghts not agreeing that Gulati has
applied to the
Māori Land Court for an order which would enable the works
to be carried out. If such an order is made it will be because it
is considered
appropriate by that Court under Te Ture Whenua Māori Act 1993. We heard no
submissions as to the considerations
that would be relevant to the application
made to that Court, nor would it have been appropriate for us to be influenced
by those
considerations in this Court. It is not an RMA matter and we are
sitting on an application for judicial review of a decision to
grant resource
consent on a non-notified basis. The tenor of Mr Williams’
submissions was to suggest that if the resource
consent were upheld then a
decision of the Māori Land Court authorising the works would almost be
inevitable. We are not in
a position to say whether or not that will be the
case. But if that were true, it would be because of the nature of the land
interests
concerned and the Māori Land
Court’s view of the merits of the application before it. We do not see
how this can possibly influence the
decision to be made on the present
appeal.
- [55] Situations
commonly arise where the implementation of a resource consent is dependent upon
the consent holder obtaining some
other statutory authority or the agreement of
landowners that some necessary element of the consent may take place on their
land.
That does not make the landowner an affected party in RMA terms.
Mr Green addressed the relevant principles in his submissions,
which he
illustrated by reference to this Court’s decision in MacLaurin v Hexton
Holdings Ltd.[30]
- [56] In that
case, Hexton sought to construct a bottling plant on its property, which it
claimed was landlocked. It applied for land
use consent, and made an
application to the High Court under s 129B of the Property Law Act 1952 to
secure vehicular access to its
property. The Gisborne District Council
granted consent to the bottling activity and there was an appeal to the
Environment Court. That Court
delivered an interim decision in which it
approved the establishment of the proposed bottling plant in principle, but
indicated it
was not prepared to grant resource consent until the access issue
was resolved. In the High Court, Hexton put up for consideration a
number of access options; one involved a proposed route over the
MacLaurins’ land, the other two involved proposed routes
over the MacLaurins’ land and the land of others. The High Court
granted Hexton’s
application, having found its land was landlocked, and
granted an easement over the MacLaurins’ land. The MacLaurins appealed
against both the Environment Court and High Court decisions.
- [57] When the
matter reached this Court, it held that the Environment Court should have
brought the proposal to a
conclusion.[31] This Court
observed:[32]
[47] With
respect, we think the Environment Court was wrong not to decide the issue. And
Hexton was wrong not to press that issue
to finality before commencing its s
129B application. The structure of the Resource Management Act is such
that “any person”
may apply for resource consents affecting
land over which they might have no ownership or other rights ... What consent
authorities
are concerned with is the proposed activity’s effects, not the
nature of the applicant’s legal rights or interest in
the particular land.
Of course, obtaining a resource consent in circumstances where the applicants
have no rights to the land in
question will not avail those applicants unless
they can acquire an interest in the land which permits them to make use of the
resource
consent obtained. In this case, there is no reason why the
Environment Court could not have evaluated the three access options Hexton
put
up. If minded to grant the resource consent, the Environment Court could have
specified which of the various options it found
satisfactory. Hexton would then
have known which option to pursue in the High Court. What we have said the
Environment Court should
have done is exactly what the Gisborne District Council
had done at first instance.
- [58] In the
circumstances of that case this Court considered the appropriate course to
follow was to secure resource consent, and
then make the necessary application
to secure the right of access to the
land.[33] We see no reason to
reject that approach in the circumstances of this case.
- [59] This brings
us to the decision of the High Court in
Westfield.[34] This
was an appeal from an Environment Court decision upholding aspects of the
proposed Hamilton City district plan providing for
additional retail activity in
commercial services and industrial zones. One of the issues in the case
concerned the power contained
in the proposed plan to impose conditions on
retail activities classified as controlled activities. It was argued this power
was
not a valid means of avoiding adverse traffic effects because the conditions
that would need to be imposed would nullify the consents
to which they were
attached. That argument rested on assumptions that the conditions would be
either so onerous as to remove the
substance of the consent or would be
dependent upon the activities of third parties over whom the applicant for
consent had no control.
- [60] The Council
had provided in its proposed district plan that, when consenting to controlled
activities, it could impose conditions
relating to the impact of proposals on
the external roading network with respect to access, traffic volumes and
traffic capacity.
The Council gave itself the power to require the
provision of new roads, the upgrading of existing roads or the payment of a
levy
as conditions of consent. There was a tension between the breadth of those
powers and the nature of a controlled activity, to which
the Council was obliged
to grant consent subject to appropriate
conditions.[35]
- [61] Fisher J
held that a condition attached to a consent will usually be regarded as
unreasonable if incapable of performance. He
gave as an example a consent to
erect additional dwellings subject to a condition requiring access over a 4.8 m
wide strip when access
to the applicant’s property was in fact possible
only through an existing strip with a width of 3.7
m.[36] He
continued:
[56] ... a condition precedent which defers the
opportunity for the applicant to embark upon the activity until a third party
carries
out some independent activity is not invalid. There is nothing
objectionable, for example, in granting planning permission subject
to a
condition that the development is not to proceed until a particular highway has
been closed, even though the closing of the
highway may not lie within the
powers of the developer ...
- [62] The Judge
observed that there was a critical distinction between two ways in which a
condition might be framed. One would require
an applicant to bring about a
result that was not within the applicant’s power, for example a
requirement to construct a new
roundabout on a nearby roadway when the roadway
was controlled by NZTA. The other kind of condition would require that a
development
not proceed until an event occurred, for example until the
roundabout was constructed. The Judge considered it was clear that, by
wording
a condition in appropriate terms, a council would have the power to impose
valid conditions of the kind challenged in the
case before
him.[37]
- [63] Mr Williams
was right to point out that the discussion in Westfield took place in a
very different context from the present, but we do not consider that point
assists him. The discussion in Westfield was about the lawfulness of
conditions imposed on applicants requiring work to be carried out on property
beyond their control. The
concern was such applicants would be powerless
to bring about the requisite state of affairs with the consequence that the
consent
itself would be rendered nugatory. But Westfield, and the other
cases referred to in that judgment, were not cases about protecting the rights
of third-party landowners. They proceeded
on the basis of considerations of
fairness to the applicant for resource consent.
- [64] This case
concerns a completely different situation. We have already quoted — at [28] above — what Whata J said on
this issue in the High Court. Here Gulati has sought resource consent on the
basis that it would
carry out the works required by the conditions of consent.
It has voluntarily submitted to the imposition of the conditions, and
they must
be complied with before it can commence its service station activity. The works
can be carried out if the other co-owners
of the Roadway consent, or the
Māori Land Court makes an appropriate order. Westfield does not
found an argument for the invalidity of the conditions, still less the consent
itself, in these circumstances. We also agree
with the Judge’s conclusion
that the fact the works will be required on private land as opposed to public
land is not a distinction
of any significance.
- [65] For
completeness, we add that Dart River Safaris Ltd v Kemp does
not assist the Lysaghts either.[38]
In that case, resource consent was granted by the Environment Court for a
new jet boating tourism activity on the Dart River subject
to a condition that
the applicant and an existing jet boat operator file an agreed draft operating
memorandum for jet boat operations
on the river. It was argued by the existing
operator that the condition was unlawful, and that it could not be required to
agree
to such a memorandum, which would have the effect of curtailing its rights
under its own resource consent. Panckhurst J held the
condition was invalid to
the extent it was couched in obligatory
terms.[39] We see that case as very
different from the present. There is no attempt to require a third party to
take any steps in the present
case. The reverse is true; unless Gulati can
secure the right to carry out the works on the Roadway the works will not be
able to
be carried out, and the resource consent will not be able to be
implemented.
- [66] For these
reasons, we reject the ground of appeal based on the condition precedent issue.
We turn now to consider the issue
of whether the cumulative effects of the
proposal are at least minor.
The r 13.4.7.1 and cumulative
effects argument
- [67] As
has been seen, one of the matters to which the Council restricted its discretion
under r 13.4.7.1 of the district plan was
the “formation of the road
or access”. Whata J held that the considerations in r 13.4.7.1 did
not encompass the physical
impacts of the works necessary to achieve a
design that complied with the objective in r 13.2.2.1, namely that any new
road be designed,
constructed and located to accommodate the volume and type of
traffic likely to use it in a safe and efficient
manner.[40]
- [68] The
considerations set out in r 13.4.7.1 follow r 13.4.7, which lists the
various rules to which the considerations relate.
One of those is
r 13.2.2. As has been seen, restricted discretionary activity consent was
required under r 13.2.2.2 because the
Roadway did not comply with the
design standards set out Appendix 13.7.5.
- [69] We are not
persuaded the Judge erred in his approach to these rules. They are a coherent
set of provisions that address what
is necessary to ensure access is provided
over a road that is appropriate to accommodate the volume and type of traffic
likely to
use it, safely and efficiently. The emphasis is on the physical
aspects of the Roadway and how it will function. It is not about
any adverse
effects of the method of construction during the construction process. It was
not inconsistent for the Judge to hold
that while there would be physical
impacts from the carrying out of the works, the impacts were not relevant to
whether the modified
Roadway could be used safely and efficiently once the works
were carried out. The construction impacts were not relevant, in other
words,
to the considerations to which the Council had restricted the exercise of its
discretion.
- [70] Ultimately
Mr Williams’ argument on this point cannot overcome the effect of
s 95E(2)(b) of the RMA with its clear direction
that, in assessing an
activity’s adverse effects on a person for the purposes of the section,
the consent authority:
... must, if the activity is a ... restricted
discretionary activity, disregard an adverse effect of the activity on the
person if
the effect does not relate to a matter for which a rule ... restricts
discretion ...
- [71] These
conclusions have obvious implications for Mr Williams’ argument based on
cumulative effects. We listed the matters
of concern to the Lysaghts at [37] above. The issues relating to the
physical works associated with the widening and reforming of the Roadway, and
the delays and inconvenience
experienced during the construction phase, are not
matters which can be taken into account under the restricted list of
considerations
in r 13.4.7.1.
- [72] However,
what Mr Williams described as the permanent and ongoing effects resulting from
the greater frequency of vehicles using
the Roadway, by contrast,
are plainly relevant. But the difficulty the Lysaghts then face is the
extensive discussion those issues
were given in the Report, which addressed the
relevant considerations. We have earlier quoted and summarised what was said in
the
Report on the relevant matters, and need not repeat it here. The Report
formed the basis upon which the Council decided that the
application did not
need to be notified, whether publicly or on a limited basis. The
Council’s conclusion that the effects
of the proposal on the environment
would be less than minor was reached after a thorough examination of the
relevant matters, given
the restricted ambit of the considerations set out in
r 13.4.7.1. And contrary to Mr Williams’ submission,
the decision about
notification did not take into account the positive
effects of the proposal, as para 6.21 of the Report (quoted in [18] above) made plain. We see
no basis to differ from the High Court’s conclusion confirming the
Council’s assessment that
the effects on the Lysaghts were less than
minor.
- [73] We
emphasise this is not a case in which it is argued that the Council did not have
adequate information on which to make its
decision about notification.
The Report was comprehensive. The Judge
found:[41]
... the
consenting officers had adequate information upon which to base their findings
that the pleaded effects of the proposed activity
on the Lysaghts, in terms
of the safe and efficient use of the Roadway, were less than minor.
We have no reason to disagree with that conclusion.
- [74] Contained
in the material before the Council was a letter dated 6 April 2020 from
Gulati’s traffic engineer, Mr Constable,
in which he assessed the existing
and future traffic flows on the Roadway such as the vehicle movements generated
by the proposal,
including by multi-rig trucks. He wrote:
Based on
these flows it can be calculated that there is a 1% probability that a multi-rig
truck accessing the fuel facility will be
present on that part of the roadway
adjacent to the fuel facility site at any given time. There is a 0.01%
probability that a multi-rig
truck and any other opposing vehicle will be on
that part of the roadway simultaneously, at any given time. This is a very
small
incidence where a conflict could occur between a large multi-rig truck and
an opposing vehicle, and hence my conclusion that the
operational and safety
effects of the fuel facility as proposed will be negligible.
- [75] This advice
was directly relevant to what we have held was the only relevant cumulative
effect identified in Mr Williams’
submissions. It went to the heart of
the concerns raised. And, as noted by the Judge, no expert evidence to
the contrary was adduced
in the High Court.
Result
- [76] The
appeal is dismissed.
- [77] The
appellants must pay the respondents’ costs for a standard appeal on a
band A basis and usual
disbursements.
Solicitors:
Neverman Bennett
Lawyers, Hamilton for Appellants
Brookfields Lawyers, Auckland for First
Respondent
Holland Beckett Law, Tauranga for Second Respondent
[1] Lysaght v Whakatāne
District Council [2021] NZHC 68, [2021] NZRMA 423 [High Court judgment] at
[114]–[115].
[2] At [113].
[3]
Te Rūnanga o Ngāti Awa, having succeeded in their
application, did not appear at the hearing of this appeal.
[4] High Court judgment, above n
1, at [35].
[5] Italics in original.
[6] High Court judgment, above n
1, at [48]. Section 95E(2)(a) of the
RMA allows a consent authority to disregard an adverse effect of an activity if
a rule permits
an activity with that effect.
[7] At [48].
[8] At [68].
[9] At [68].
[10] At [58].
[11] At [60].
[12] At [61]. Although the
Judge refers to “r 13.4.7.2” in this paragraph, it is apparent this
is meant as a reference to
“r 13.4.7.1” of the district plan.
[13] At [70].
[14] At [76]–[77]. Gulati
has made an application to the Māori Land Court for orders permitting the
necessary works to take
place on the Roadway; that proceeding stands adjourned
pending the determination of these judicial review proceedings.
[15] Westfield (New Zealand)
Ltd v Hamilton City Council [2004] NZRMA 556 (HC).
[16] Dart River Safaris Ltd v
Kemp [2000] NZHC 448; [2000] NZRMA 440 (HC).
[17] Footnote omitted.
[18] Resource Management Act
1991, s 104C(1)(b).
[19] Section 104C(3)(b).
[20] Auckland Council v
Wendco (NZ) Ltd [2017] NZSC 113, [2017] 1 NZLR 1008.
[21] At [37] per William Young,
O’Regan and Ellen France JJ, followed in Speargrass Holdings Ltd v
van Brandenburg [2019] NZCA 564 at [53] and [55]–[58].
[22] Resource Management Act, s
2 definition of “natural and physical resources”.
[23] Section 9(3)(a).
[24] Section 2 definition of
“use”.
[25] Section 87(a).
[26] Section 87(b)-(e).
[27] Consents can attract
some of the incidents of property, but only pursuant to specific
provisions of the RMA, as explained in
Hampton v Canterbury Regional Council (Environment Canterbury)
[2015] NZCA 509, [2016] NZRMA 369 at [105].
[28] There are restrictions for
trade competitors, under pt 11A of the RMA.
[29]
Hampton v Canterbury Regional Council (Environment
Canterbury), above n 27, at
[104].
[30] MacLaurin v Hexton
Holdings Ltd [2008] NZCA 570, (2008) 10 NZCPR 1.
[31] The appeal was allowed
because this Court determined that the land was not landlocked, a point not
relevant here.
[32] Citation omitted.
[33] At [47] and [50].
[34] Westfield (New Zealand)
Ltd v Hamilton City Council, above n 15.
[35] See generally Resource
Management Act, s 104A.
[36] Westfield (New Zealand)
Ltd v Hamilton City Council, above n 15, at [55].
[37] At [60].
[38]
Dart River Safaris Ltd v Kemp, above n 16.
[39] At [27].
[40] High Court judgment, above
n 1, at [61]–[62].
[41] High Court judgment, above
n 1, at [68].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2022/423.html