NZLII Home | Databases | WorldLII | Search | Feedback

Court of Appeal of New Zealand

You are here:  NZLII >> Databases >> Court of Appeal of New Zealand >> 2022 >> [2022] NZCA 423

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Lysaght v Whakatâne District Council [2022] NZCA 423 (8 September 2022)

Last Updated: 12 September 2022

IN THE COURT OF APPEAL OF NEW ZEALAND

I TE KŌTI PĪRA O AOTEAROA
CA103/2021
[2022] NZCA 423



BETWEEN

IAN WALLACE LYSAGHT AND ADRIANNE JUNE LYSAGHT
Appellants


AND

WHAKATĀNE DISTRICT COUNCIL
First Respondent


AND

GULATI ENTERPRISES LIMITED
Second Respondent

Hearing:

16 November 2021

Court:

French, Cooper and Gilbert JJ

Counsel:

M J E Williams for Appellants
A M B Green for First Respondent
V J Hamm and T J Conder for Second Respondent

Judgment:

8 September 2022 at 4:00 pm


JUDGMENT OF THE COURT

  1. The appeal is dismissed.
  2. The appellants must pay the respondents’ costs for a standard appeal on a band A basis and usual disbursements.

____________________________________________________________________

REASONS OF THE COURT

(Given by Cooper J)




Table of Contents

Para No
Introduction
The application and the district plan
The High Court proceeding
The appeal
Summary of arguments on appeal
The condition precedent argument
The r 13.4.7.1 and cumulative effects argument
Analysis
The statutory scheme
The condition precedent argument
The r 13.4.7.1 and cumulative effects argument
Result

Introduction

The application and the district plan

(a) The proposed Mobil pylon sign would exceed the maximum permitted signage display area of 12 m2 under r 11.2.19.1. The proposed sign would be 12.5 m2 in area. This aspect of the proposal required discretionary activity consent.

(b) The Roadway would not meet the required minimum width of 18 m under r 13.2.2. Works proposed to be carried out in conjunction with the service station development would widen the Roadway to 10 m. For this, discretionary activity consent was required.

2.2 Site access is proposed to be provided from SH30 via the Māori Roadway. Two new vehicle crossings are located on the western boundary of the lot to facilitate this. Other physical works are also proposed within the Māori Roadway to facilitate access. Egress is proposed to be provided by way of a new vehicle crossing to SH30 at the south-east corner of the site. No-right-turn rules will be imposed for traffic entering SH30 from the Māori Roadway and at the site egress.

2.3 The applicant proposes to install a median strip within the New Zealand Transport Agency (NZTA) SH30 corridor for a distance of approximately 150m from the western end of the existing median leading to the SH30/Keepa Road roundabout. The new median will therefore extend past the Māori Roadway to approximately halfway along the frontage of the property to the west ... A deceleration lane is also proposed. ...

Further consideration of this matter has been undertaken following close consideration and refinement of the areas of non-compliance, including the matters to which discretion is restricted, and after seeking a legal opinion. It is now concluded that written approvals are not required to enable the application to be processed non-notified. This is addressed further elsewhere in this report.

This was communicated to the applicant on 30 March and a written response was provided on 6 April, followed by a meeting between the engineers and the applicant on 14 April. Conditions were agreed as a consequence. An amended plan was provided by the applicant on 20 April and accepted by Council Manager Transportation on 22 April 2020.

Any new road or accessway shall be designed, constructed and located to accommodate the volume and type of traffic likely to use it in a safe and efficient manner.

Compliance with the following standards shall satisfy Rule 13.2.2.1. Non‑compliance with these standards shall be considered a Restricted Discretionary activity:

  1. Roads and accessways shall be designed to meet the design standards set out in Appendix 13.7.5. Widths shall be selected to ensure that adequate movement lanes, footpaths, berms, and batters can be provided to retain amenity values (including landscaping) and enable utility services to be provided safely and in economical and accessible locations;

...

13.4.7.1 Council shall restrict its discretion to;

a. traffic volumes and traffic mix relative to existing and future patterns, access, parking and loading on-site;

b. pedestrian and cyclist safety;

c. construction traffic volumes, traffic mix and hours of operation;

d. the ability of the site to accommodate the traffic anticipated and the nature of the adjacent roading pattern, including the position of the road in the roading hierarchy;

e. formation of the road or access;

f. the total land area proposed to be used for access, parking and loading in the Rural Plains Zone; and

g. aspects of the proposal that could compromise the safety and convenience of pedestrians as well as individual and cumulative adverse effects associated with traffic movements.

Traffic volumes and traffic mix relative to existing and future patterns, access, parking and loading on-site;

6.11 The effects on the state highway, the intersection with State Highway 30, and the wider roading network have been addressed through the Transportation Assessment provided as part of the application with further information provided by the applicant between 14 February and 2 March 2020. These effects have been concluded to be less than minor.

6.12 In relation to the traffic flow and existing and future traffic patterns within the Māori Roadway, the applicant provided additional evaluation on 28 February 2020 highlighting the low traffic generated by existing activities which future use for industrial purposes would increase from 1-2 trips per hour (tph) to 8tph. Additional information was requested to review the potential for conflict between safe pedestrian access and service station traffic, including in particular heavy vehicles turning into the roadway, with the need to cross into the opposing traffic lane and then enter the service station from the roadway. This was provided on 6 April 2020 and an amended plan provided to Council on 20 April 2020.

6.13 The additional information has been reviewed by Council’s Transportation team. The Council is now satisfied that the amended design provides appropriately for safe access for all users of the roadway and into the site from the roadway. It will minimise the potential effects on other sites served by the Māori Roadway and the potential conflict arising from vehicles crossing the roadway to enter the service station. The assessment provided by Traffic Solutions Ltd ... identified that there were potential benefits for future users of the roadway arising from the upgrade, as follows:

“The trafficable width of the roadway is presently about 7m where vehicles turn into it from the highway. This is quite narrow for an access to industrial zoned land where truck movements are expected to be generated, and the kerbs at the intersection with the highway presently require all trucks, even rigid trucks, to cross the centreline when turning into the roadway. If the fuel facility proceeds then the roadway at its entry will be widened considerably to accommodate large truck rigs that the development will generate. This will provide a benefit to the other lots served by the roadway because more width will be available for heavy vehicles associated with any future industrial development to turn into the roadway without unduly obstructing exiting vehicles, a situation that cannot presently occur.”

6.14 The upgrade will therefore provide appropriately for future industrial use of sites served by the roadway. There will be some change in effects for those living on or served by the roadway, but the level of changes [is] not unreasonable or unanticipated since the land was subdivided in 1999 ... and zoned for industrial use. In addition, the applicant has demonstrated that large trucks can still practically manoeuvre within the 10m width, albeit utilising the full width, and two-way traffic movements are possible. The proposal and technical non-compliance with width does not change the overall type and volume of traffic anticipated and legally able to use the roadway now and in the future, based on the zoning of the land. The scale of adverse effects is therefore concluded to be generally acceptable and less than minor as a result of the non-compliant width.

6.20 The evaluation relates to the under width roadway and the effect on both these aspects has been evaluated above.

6.21 The upgrade works to the intersection of the state highway and roadway, including the deceleration lane and widening, are expected to be compatible and support further development of the other light industrial land served by the roadway and may avoid the need for further works in the future by subsequent developers. This could in turn facilitate development of the land, as anticipated [by] the District Plan. Whilst not a consideration for the notification decision, these positive effects may be considered as part of the substantive decision under [s 104] of the RMA.

6.24 The effects of the proposal have been considered in relation to adjacent properties, particularly those at 46B and 46D State Highway 30 which are used for residential purposes, but are zoned Light Industrial. The service station itself would be a permitted activity if the roadway was 8m wider to meet the access standard. The aspects such as noise, lighting, and traffic generation are compliant with the permitted activity standard and on-going compliance can be required through conditions. Therefore, although the relationship may not be favourable for the existing residential activities, there are no rules in the [district plan] through which more rigorous standards can be imposed.

(a) to provide a report to the Council’s General Manager of Planning and Infrastructure from an independent, qualified road pavement engineer on the current structural capacity of the Roadway, the impact of increased traffic and the need for any additional structural strengthening of the Roadway pavement. If structural strengthening was required, Gulati would need to reconstruct the pavement to meet any new design life requirements; and

(b) before commencing the service station operation, to complete all road‑upgrading works as shown in a report from Traffic Solutions Ltd and the road pavement report mentioned above. The road-upgrading works were to be undertaken in accordance with the Council’s Engineering Code of Practice and certified by the General Manager of Planning and Infrastructure.

The High Court proceeding

[76] In the present case, there is no requirement for agreement to be reached with the Lysaghts and the consent does not otherwise purport to derogate from (or deprecate) the Lysaghts’ existing property or consented rights. Quite the reverse, the required roadworks are expressly framed as a condition precedent to the operation of the station, which carries no implication that the Lysaghts must agree to or otherwise implement the proposed mitigation works. Rather, it places the entire burden on Gulati to either obtain the Lysaghts’ agreement or otherwise obtain lawful authority to undertake the requisite roadworks. In this respect, the condition is a paradigm example of a valid condition precedent referred to by Fisher J in Westfield v Hamilton City Council.

[77] Mr Williams sought to distinguish the Westfield v Hamilton City [Council] condition precedent on the basis that the present condition related to private land, not public land or public works. But that is a distinction without consequence because, as I have said, Gulati must obtain the Lysaghts’ agreement or otherwise obtain lawful authority to undertake the roadworks. In the result, the Lysaghts’ property rights, including to the use and enjoyment of the Roadway, remain unaffected until that agreement or the requisite court order has been obtained.

The appeal

Summary of arguments on appeal

The condition precedent argument

The reason for that is that in this situation the Consent Decision is being relied on as the platform for seeking orders from the Māori Land Court, directing that the owners of the roadway ‘permit’ the very improvements to the Roadway required by the resource consent for the service station.

The r 13.4.7.1 and cumulative effects argument

(a) the effects of physical works associated with widening and reforming the Roadway, including proposed curb realignments;

(b) the delays and inconvenience experienced during the construction phase of the project;

(c) the permanent and ongoing effects resulting from the greater frequency of vehicles using the Roadway, including by multi-rig trucks crossing the Roadway’s centre line on an irregular but ongoing basis; and

(d) the possibility of further widening being required, encroaching directly on the Lysaght Developments’ office site. This was in reference to a plan showing a possible widening of the Roadway on the Lysaghts’ land with the label “[p]ossible alternative kerb setback by others”. However, this was not proposed as part of the resource consent application, nor required by the consent, and we do not need to address it further.

Analysis

The statutory scheme

87A Classes of activities

...

(3) If an activity is described in this Act, regulations (including any national environmental standard), a plan, or a proposed plan as a restricted discretionary activity, a resource consent is required for the activity and—

(a) the consent authority’s power to decline a consent, or to grant a consent and to impose conditions on the consent, is restricted to the matters over which discretion is restricted (whether in its plan or proposed plan, a national environmental standard, or otherwise); and

(b) if granted, the activity must comply with the requirements, conditions, and permissions, if any, specified in the Act, regulations, plan, or proposed plan.

The condition precedent argument

[47] With respect, we think the Environment Court was wrong not to decide the issue. And Hexton was wrong not to press that issue to finality before commencing its s 129B application. The structure of the Resource Management Act is such that “any person” may apply for resource consents affecting land over which they might have no ownership or other rights ... What consent authorities are concerned with is the proposed activity’s effects, not the nature of the applicant’s legal rights or interest in the particular land. Of course, obtaining a resource consent in circumstances where the applicants have no rights to the land in question will not avail those applicants unless they can acquire an interest in the land which permits them to make use of the resource consent obtained. In this case, there is no reason why the Environment Court could not have evaluated the three access options Hexton put up. If minded to grant the resource consent, the Environment Court could have specified which of the various options it found satisfactory. Hexton would then have known which option to pursue in the High Court. What we have said the Environment Court should have done is exactly what the Gisborne District Council had done at first instance.

[56] ... a condition precedent which defers the opportunity for the applicant to embark upon the activity until a third party carries out some independent activity is not invalid. There is nothing objectionable, for example, in granting planning permission subject to a condition that the development is not to proceed until a particular highway has been closed, even though the closing of the highway may not lie within the powers of the developer ...

The r 13.4.7.1 and cumulative effects argument

... must, if the activity is a ... restricted discretionary activity, disregard an adverse effect of the activity on the person if the effect does not relate to a matter for which a rule ... restricts discretion ...

... the consenting officers had adequate information upon which to base their findings that the pleaded effects of the proposed activity on the Lysaghts, in terms of the safe and efficient use of the Roadway, were less than minor.

We have no reason to disagree with that conclusion.

Based on these flows it can be calculated that there is a 1% probability that a multi-rig truck accessing the fuel facility will be present on that part of the roadway adjacent to the fuel facility site at any given time. There is a 0.01% probability that a multi-rig truck and any other opposing vehicle will be on that part of the roadway simultaneously, at any given time. This is a very small incidence where a conflict could occur between a large multi-rig truck and an opposing vehicle, and hence my conclusion that the operational and safety effects of the fuel facility as proposed will be negligible.

Result





Solicitors:
Neverman Bennett Lawyers, Hamilton for Appellants
Brookfields Lawyers, Auckland for First Respondent
Holland Beckett Law, Tauranga for Second Respondent


[1] Lysaght v Whakatāne District Council [2021] NZHC 68, [2021] NZRMA 423 [High Court judgment] at [114]–[115].

[2] At [113].

[3] Te Rūnanga o Ngāti Awa, having succeeded in their application, did not appear at the hearing of this appeal.

[4] High Court judgment, above n 1, at [35].

[5] Italics in original.

[6] High Court judgment, above n 1, at [48]. Section 95E(2)(a) of the RMA allows a consent authority to disregard an adverse effect of an activity if a rule permits an activity with that effect.

[7] At [48].

[8] At [68].

[9] At [68].

[10] At [58].

[11] At [60].

[12] At [61]. Although the Judge refers to “r 13.4.7.2” in this paragraph, it is apparent this is meant as a reference to “r 13.4.7.1” of the district plan.

[13] At [70].

[14] At [76]–[77]. Gulati has made an application to the Māori Land Court for orders permitting the necessary works to take place on the Roadway; that proceeding stands adjourned pending the determination of these judicial review proceedings.

[15] Westfield (New Zealand) Ltd v Hamilton City Council [2004] NZRMA 556 (HC).

[16] Dart River Safaris Ltd v Kemp [2000] NZHC 448; [2000] NZRMA 440 (HC).

[17] Footnote omitted.

[18] Resource Management Act 1991, s 104C(1)(b).

[19] Section 104C(3)(b).

[20] Auckland Council v Wendco (NZ) Ltd [2017] NZSC 113, [2017] 1 NZLR 1008.

[21] At [37] per William Young, O’Regan and Ellen France JJ, followed in Speargrass Holdings Ltd v van Brandenburg [2019] NZCA 564 at [53] and [55]–[58].

[22] Resource Management Act, s 2 definition of “natural and physical resources”.

[23] Section 9(3)(a).

[24] Section 2 definition of “use”.

[25] Section 87(a).

[26] Section 87(b)-(e).

[27] Consents can attract some of the incidents of property, but only pursuant to specific provisions of the RMA, as explained in Hampton v Canterbury Regional Council (Environment Canterbury) [2015] NZCA 509, [2016] NZRMA 369 at [105].

[28] There are restrictions for trade competitors, under pt 11A of the RMA.

[29] Hampton v Canterbury Regional Council (Environment Canterbury), above n 27, at [104].

[30] MacLaurin v Hexton Holdings Ltd [2008] NZCA 570, (2008) 10 NZCPR 1.

[31] The appeal was allowed because this Court determined that the land was not landlocked, a point not relevant here.

[32] Citation omitted.

[33] At [47] and [50].

[34] Westfield (New Zealand) Ltd v Hamilton City Council, above n 15.

[35] See generally Resource Management Act, s 104A.

[36] Westfield (New Zealand) Ltd v Hamilton City Council, above n 15, at [55].

[37] At [60].

[38] Dart River Safaris Ltd v Kemp, above n 16.

[39] At [27].

[40] High Court judgment, above n 1, at [61]–[62].

[41] High Court judgment, above n 1, at [68].


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2022/423.html