You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2023 >>
[2023] NZCA 648
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Body Corporate Number DPS 91535 v 3A Composites GMBH [2023] NZCA 648 (15 December 2023)
Last Updated: 18 December 2023
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
BODY CORPORATE NUMBER DPS 91535 First Appellant
ARGOSY
PROPERTY NO. 1 LIMITED Second Appellant
|
|
AND
|
3A COMPOSITES GMBH First Respondent
TERMINUS 2
LIMITED Second Respondent
SKELLERUP INDUSTRIES LIMITED Third
Respondent
|
Hearing:
|
7–8 June 2023
|
Court:
|
Gilbert, Goddard and Mallon JJ
|
Counsel:
|
J A Farmer KC, J L W Wass and S C I Jeffs for Appellants A R
Galbraith KC, J Q Wilson, A M Boberg and S L Cahill for First Respondent M C
Harris and Z A Brentnall for Second Respondent M D O’Brien KC, R M
Irvine-Shanks and L C Bercovitch for Third Respondent
|
Judgment:
|
15 December 2023 at 3.00 pm
|
JUDGMENT OF THE COURT
- The
appeal is dismissed.
- The
appellants must pay each respondent costs for a standard appeal on a band A
basis, with usual disbursements. We certify for second
counsel for each
respondent.
____________________________________________________________________
REASONS OF THE COURT
(Given by Goddard
J)
Table of contents
Para no
Schedule
Introduction and summary
- [1] The
appellants own buildings which are, to varying extents, clad in building
products branded as “Alucobond” manufactured
by the first
respondent, 3A Composites GmbH (3AC). The second and third respondents
were, at various times, importers, distributors
and suppliers in New Zealand of
Alucobond products. The appellants say that two Alucobond products used as
cladding on their buildings
— Alucobond PE and Alucobond Plus — are
combustible, and give rise to an unacceptable risk of spread of
fire.[1] Their proceedings allege
that the Alucobond products are inherently unsuitable for use as an external
building cladding material,
and do not comply with relevant New Zealand Building
Code requirements.
- [2] In a
separate judgment, delivered today, we have determined an appeal in relation to
3AC’s protest to the jurisdiction of
the New Zealand
Courts.[2] The appellants are
entitled to pursue their claims before the New Zealand Courts against 3AC in
negligence, negligent misstatement,
negligent failure to warn and for breach of
the Fair Trading Act 1986. We have held that their claim against 3AC under the
Consumer
Guarantees Act 1993 is not seriously arguable, and cannot proceed in
New Zealand. (The other respondents are New Zealand companies,
in relation to
which no question of jurisdiction arises.)
- [3] The
appellants wish to bring their claims as representative proceedings, on an opt
out basis. The group of plaintiffs they seek
to represent is all current and
former owners and leaseholders of buildings or parts of buildings with the
Alucobond products as
exterior cladding. Their application for orders
authorising them to sue as representative plaintiffs under r 4.24 of the
High Court
Rules 2016 was unsuccessful in the
High Court.[3]
They appeal against that decision.
- [4] We agree
with Jagose J that this is not a suitable case for representative proceedings
brought on an opt out basis. We are not
persuaded that the appellants are
sufficiently representative of the full range of plaintiffs on whose behalf they
seek to claim.
Although common issues across such a class can be framed at a
high level of generality, we do not consider that it would be just
or efficient
for the wide-ranging claims advanced by the appellants, many of which do not
relate directly to their own circumstances,
to be litigated before the High
Court in the manner they propose.
- [5] For example,
the appellants seek to litigate claims in relation to Alucobond Plus even though
that product does not appear to
have been used on any of their buildings. They
seek to have the court determine the suitability of the Alucobond products as
exterior
cladding products, and their compliance with the Building Code, in
buildings that have very different characteristics from their
own buildings, and
that use Alucobond to very different extents ranging from minor decorative
features of a building through to complete
exterior cladding. Some —
perhaps, many — of the issues that they ask the court to determine at
Stage 1 of their proposed
representative proceeding may not in fact be relevant
to any building in respect of which a specific claim is advanced at Stage 2.
A
trial of these issues, some of which may prove hypothetical, would not be an
efficient use of the court’s resources and
would be disproportionately
burdensome and unjust for the respondents.
- [6] The appeal
must therefore be
dismissed.
Background
- [7] As
already mentioned, the proceedings relate to two Alucobond products manufactured
by 3AC: Alucobond PE and Alucobond Plus.
Each product consists of two aluminium
cover sheets with a core containing polyethylene (PE) and other materials
laminated and bonded
together. The core of Alucobond PE cladding is
approximately 100 per cent PE. The core of Alucobond Plus is approximately
30 per cent PE
and another ethylene compound, and 70 per cent mineral compounds.
- [8] Alucobond is
one of a number of aluminium composite panel (ACP) cladding products used in New
Zealand. The appellants say there
has been growing recognition of fire risks
associated with the use of ACP cladding in recent years, in particular following
the fire
at Grenfell Tower in London. They say that ACP panels, including
Alucobond panels, are combustible and are not fit for use in external
cladding
in many buildings due to the risk that they will fuel the rapid spread of fire.
The appellants say that they are concerned
about the risks posed by the
Alucobond cladding used on their buildings, and that addressing those risks by
removing and replacing
the panels will cause them loss and expense. They wish
to bring representative proceedings against 3AC and two New Zealand distributors
of Alucobond products in relation to the Alucobond products used on their
buildings.
- [9] The
distributors against whom the claim is brought are the third respondent,
Skellerup Industries Ltd (Skellerup) and the second
respondent, which at the
relevant time was called Kaneba Ltd (Kaneba).
- [10] Skellerup
imported and distributed Alucobond in New Zealand between 2005 and 2009.
- [11] Kaneba
carried on business importing and supplying Alucobond products in New Zealand
from 2009, when it acquired Skellerup’s
Alucobond business, until
September 2014 when it sold the business to another company. From September
2014 until 2020 Kaneba continued
to import Alucobond products for on-sale to
other
fabricators.
Cutterscove
Building
- [12] The
first appellant (Cutterscove) is the body corporate for a three-storey apartment
building in Mt Maunganui known as the Cutterscove
Resort Apartments (Cutterscove
Building). Cutterscove says that Alucobond PE was supplied to it and affixed to
the exterior of the
Cutterscove Building in 2006 to 2008 pursuant to a
construction contract that Cutterscove entered into with Moyle Construction Ltd.
Moyle Construction Ltd was supplied with the Alucobond by
Skellerup.
Argosy
Buildings
- [13] The
second appellant (Argosy) owns an extensive property portfolio
including:
(a) A property at 140 Don McKinnon Drive, Albany, Auckland (Don McKinnon
Drive). Don McKinnon Drive is a Burger King restaurant.
It has two strips of
Alucobond PE totalling approximately 39 m² affixed to its exterior.
(b) A property at 80 Favona Road, Māngere, Auckland (Favona Road).
A substantial part of the cladding of Favona Road is Alucobond.
Most of that cladding was fitted in 2003. In 2011 Kaneba was engaged to
fabricate and fit approximately 26 m² of Alucobond
PE to a new
pedestrian link bridge connecting two office buildings.
The
proceedings
- [14] The
appellants plead six causes of action against 3AC, Kaneba and
Skellerup:
(a) First cause of action: Breach of the guarantee of acceptable quality in
s 6 of the Consumer Guarantees Act.
(b) Second cause of action: Negligence.
(c) Third cause of action: Negligent misstatement.
(d) Fourth cause of action: Negligent failure to warn.
(e) Fifth cause of action: Breach of s 9 of the Fair Trading Act
(misleading or deceptive conduct).
(f) Sixth cause of action: Breach of s 13 of the Fair Trading Act (false
or misleading representations).
- [15] The
appellants’ pleading is lengthy (some 53 pages) and complex. But in
essence they plead that there is a material risk
that Alucobond PE and Alucobond
Plus, when used as cladding, will cause or contribute to the rapid spread and
severity of a fire,
including the rapid vertical spread and/or horizontal spread
of a fire in a building. They allege that these Alucobond products
are
inherently unsuitable for use as external cladding due to their combustibility,
and did not and do not comply with the Building
Code, which sets performance
standards for buildings including (in cl C) standards relating to
protection from fire. They say that
the products have been negligently
designed, that the respondents have made misleading claims about the suitability
of the products
for use as external cladding, and that the respondents have
failed to give appropriate warnings about the risks inherent in use of
the
products as external cladding.
- [16] When the
proceeding was first filed in December 2020, the sole plaintiff was Cutterscove.
Cutterscove pleaded that it had commenced
the proceeding on its own behalf and
in a representative capacity on behalf of all persons with the same interest in
the subject
matter of this proceeding, which it identified as persons
who:
(a) either:
(i) own or have previously owned a building situated in New Zealand
(“Relevant Building”), or have previously had an ownership
interest in a part of a building situated in New Zealand
(“Relevant Building Part”); or
(ii) have or have previously had a leasehold interest in a Relevant Building
and/or a Relevant Building Part;
(b) where the Relevant Building and/or the Relevant Building Part is or was
fitted with Alucobond PE Core Cladding; and
(c) have suffered or will suffer loss or damage for which compensation is
claimed in this proceeding;
(together, “Group Members”).
- [17] Kaneba
pointed out to the appellants that it had nothing to do with the supply of
Alucobond at the time that Cutterscove was
reclad with Alucobond PE, so
Cutterscove could have no claim against it. Kaneba applied to strike out the
proceedings against it.
In December 2021, in response to that strike out
application, the appellants filed an amended statement of claim (ASC) which
added
Argosy as second plaintiff. The ASC pleads that Cutterscove brings the
claim on behalf of the “Group Members” as defined
above. It adds
that Argosy brings its claims on behalf of all Group Members whose Relevant
Building and/or Relevant Building Part
is or was fitted with Alucobond cladding
that was directly or indirectly supplied by Kaneba.
- [18] The
appellants claim damages for themselves and on behalf of each of the Group
Members. Those damages are primarily assessed
as the cost of removing and
replacing the Alucobond cladding used on the relevant
buildings.
Representative actions:
relevant principles
- [19] Representative
actions are provided for in r 4.24 of the High Court
Rules:
4.24 Persons having same interest
One or more persons may sue or be sued on behalf of, or for the benefit of,
all persons with the same interest in the subject matter
of a
proceeding—
(a) with the consent of the other persons who have the same interest; or
(b) as directed by the court on an application made by a party or intending
party to the proceeding.
- [20] The
appellants seek to bring proceedings on behalf of all relevant
“Group Members”, as defined in the ASC. They
have not obtained
the consent of all such persons to sue on their behalf: to do so would be
impractical. So they seek directions
under r 4.24(b).
- [21] In
Southern Response Earthquake Services Ltd v Ross the Supreme Court
confirmed that representative actions may be brought on an opt out basis, and
provided guidance on when an opt
out claim may be
appropriate.[4]
As the Supreme Court noted, in construing r 4.24 the objective of the
High Court Rules is also relevant. Rule 1.2 provides that
the objective is
to ensure the just, speedy and inexpensive determination of any proceeding or
interlocutory application.[5]
- [22] The
objectives of a representative action are to improve access to justice,
facilitate the efficient use of judicial resources,
and strengthen incentives
for compliance with the law.[6] In
particular, an opt out approach has advantages in improving access to justice.
- [23] As
this Court explained in Cridge v Studorp
Ltd, r 4.24 derived from an equitable
procedure designed to facilitate the disposition of cases where the parties were
so numerous the
proceedings would be unmanageable if all were
named.[7]
The principles governing the application of the rule are well established,
and were summarised by this Court as
follows:[8]
(a) The rule should be applied to serve the interests of expedition and judicial
economy, a key underlying reason for its existence
being efficiency. A single
determination of issues that are common to members of a class of claimants
reduces costs, eliminates
duplication of effort and avoids the risk of
inconsistent findings.
(b) Access to justice is also an important consideration. Representative
actions make affordable otherwise unaffordable claims that
would be beyond the
means of any individual claimant. Further, they deter potential wrongdoers by
disabusing them of the assumption
that minor but widespread harm will not result
in litigation.
(c) Under the rule, the test is whether the parties to be represented have the
same interest in the proceeding as the named parties.
(d) The words “same interest” extend to a significant common
interest in the resolution of any question of law or fact
arising in the
proceeding.
(e) A representative order can be made notwithstanding that it relates only to
some of the issues in the claim. It is not necessary
that the common question
make a complete resolution of the case, or even liability, possible.
(f) It must be for the benefit of the other members of the class that the
plaintiff is able to sue in a representative capacity.
(g) The court should take a liberal and flexible approach in determining whether
there is a common interest.
(h) The requisite commonality of interest is not a high threshold and the court
should be wary of looking for impediments to the
representative action rather
than being facilitative of it.
(i) A representative action should not be allowed in circumstances that would
deprive a defendant of a defence it could have relied
on in a separate
proceeding against one or more members of the class, or conversely allow a
member of the class to succeed where
they would not have succeeded had they
brought an individual claim.
- [24] As the
Supreme Court noted in Southern Response Earthquake Services Ltd v Ross,
the concern not to work injustice on a defendant is met at least in part by the
requirement that applicants under r 4.24 have to
satisfy the court as to
the requisite common interest.[9] The
Supreme Court also noted that the question of proportionality of cost to the
size of the claim and burden on the defendant will
be relevant in terms of the
objective of the High Court
Rules.[10]
- [25] The Supreme
Court made a number of comments intended to assist in the exercise of the
discretion under r 4.24, where an applicant
proposes to bring
representative proceedings on an opt out
basis:[11]
[95] First,
generally, the court should adopt the procedure sought by the applicant unless
there is good reason to do otherwise.
We see no basis in policy or practical
terms for not adopting that course so long as the court turns its mind to all of
the relevant
factors. But it is not necessary to characterise the situations in
which the court may depart from an opt out order as rare, as
Mr and Mrs
Ross submit. Rather, it is a question of considering the relevant factors in
light of what will best meet the permissible
objectives of the representative
action in the particular case. We consider that approach meets the Law
Society’s concern
that requiring claims to proceed on an opt out basis may
have the unintended result of creating a barrier to justice because some
litigation funders may be less willing to fund open class claims absent a
legislative framework that deals with funding equalisation
or common fund
orders.
...
[97] Second, in terms of departures from this starting point, where there is
a real prospect some class members may end up worse
off or adversely affected by
the proceeding, that favours an opt in approach. Cases where there is a
counterclaim or the potential
for one to emerge would fall into this
category.
[98] Given the objectives of a representative proceeding, class size will
have some relevance. In particular, an opt in approach
may be the preferable
option where the class is small. By that we mean where the number of members in
the class is small relative
to other claims and there is a natural community of
interest, or, as the Court of Appeal put it, a “pre-existing
connection”.
... That said, class size will not necessarily be
determinative.
[99] We agree ... that participation at stage two may be a relevant
consideration warranting a departure from an opt out approach
if persisting with
an opt out approach at that point lessens the benefits of the representative
proceeding, or increases any unfairness
or prejudice.
[100] Third ... a universal approach may be appropriate where the only
relief sought is declaratory or injunctive and where the outcome
will affect all
class members identically. That is because in those cases it may be
impractical, and indeed sometimes almost impossible,
to provide the necessary
notice for either an opt in or opt out approach. ... In these types of claims,
opt in or opt out orders
will be neither necessary nor conducive to a speedy and
inexpensive determination.
[101] Finally, applications under r 4.24 should include proposed conditions
as to the court’s supervision of settlement and
discontinuance. We agree
with the Law Society that settlement or discontinuance may operate unfairly to
either absent plaintiffs
in an opt out claim or to a subset of plaintiffs under
either option. As we have noted, the Court of Appeal in this case added a
requirement that the plaintiffs seek the court’s leave to settle the claim
or to discontinue it. As we have indicated, we
endorse that approach.
- [26] The parties
did not differ on the principles that govern the making of orders under
r 4.24. Rather, the focus of the argument
we heard was on the application
of the rule, and the principles set out above, to the particular facts of this
claim.
The representation order
sought in this case
- [27] The
appellants applied to the High Court for directions authorising them to bring
the proceedings on behalf of the pleaded “Group
Members”, as defined
in the ASC. They say that there are many buildings in New Zealand that were
fitted with Alucobond cladding.
They refer to lists published by the Auckland,
Wellington and Christchurch local authorities of buildings in their territories
that
are clad with ACPs. Those lists identify some 271 buildings with ACP
cladding. In many cases the type of cladding is not known.
In others, it is
ACP manufactured by a company other than 3AC. But there are a significant
number of buildings on the lists identified
as having Alucobond cladding.
The estimated percentage of total cladding that is ACP varies
significantly: for many buildings use
of ACP appears to be confined to signage,
or architectural features such as street canopies or entrance areas.
- [28] The public
statement issued by Te Kaunihera o Tāmaki Makaurau | Auckland Council to
accompany its list recorded that over
the past 12 months the Council had carried
out an investigation into buildings with ACP cladding. The Council expressed
the view
that none of the buildings assessed by it so far qualify as unsafe or
dangerous. It noted that some ACPs, whether PE or plastic
core, had been linked
to fire risks in tall buildings. The Council also noted that ACP is a
common material used for many purposes,
including building signage,
architectural features and full building facades. The Council went on to
say:
Building owners have the option to replace all or any of the
cladding.
For many buildings with ACP, coverage is limited and the likelihood of it
being involved in a fire will be very small. For buildings
with a large amount
of ACP, full removal of the cladding may be an option.
However, there are typically many safety features present within the
buildings and whilst full or partial removal of any cladding
will reduce any
potential risk, there are many options available that could mitigate the risk.
We advise seeking advice from your insurers and ensuring all fire safety
features are in good working order.
- [29] The Council
stated that it takes building safety “extremely seriously and will issue a
formal warning for buildings that
pose a significant risk”. There was no
evidence before us of any such formal warnings by the Auckland Council or any
other
council.
- [30] The
appellants say that they believe that the class of Group Members is large, based
on these lists, which are not exhaustive
and relate only to three cities. They
note that Kaneba says that since November 2008, it has supplied or installed the
Alucobond
products on “hundreds of properties”. They also note
that on 10 May 2005, Skellerup wrote a letter stating that since
1985 Alucobond
had been installed to “approximately 2,000 buildings through New Zealand
and the South Pacific”. The
appellants say that it is not possible
to say definitively how many Group Members there will be without discovery from
the respondents.
However they are expected to be numerous.
- [31] A
representative of Cutterscove says that he understands that High Court
litigation is expensive, and that would be the case
for their claim. If
Cutterscove were to commence unfunded and non-representative proceedings, it
would need to levy each of the
unit owners. That would be a significant burden
on each of them. They therefore decided to bring the proceeding on a
representative
and funded basis.
- [32] When Argosy
was added as a plaintiff, in December 2021, the appellants filed an amended
application for an order under r 4.24(b)
of the High Court Rules,
reflecting the addition of Argosy as a proposed representative of a subset of
claimants.
- [33] The
appellants have entered into a litigation funding agreement with an Australian
funder, Omni Bridgeway (Fund 5) Cayman Invt.
Ltd, an investment vehicle wholly
owned by Omni Bridgeway (Fund 5) LP, a limited partnership incorporated in the
Cayman Islands,
which is advised by Omni Bridgeway Ltd, an Australian public
company listed on the Australian Securities Exchange. A redacted copy
of the
funding agreement was provided to the Court.
- [34] Cutterscove
subsequently advised that there are 14 claimants who collectively own 30
buildings who have signed litigation funding
agreements. Those claimants own
buildings across New Zealand including in Auckland, Christchurch, Wellington, Mt
Maunganui and Whangārei
and include buildings supplied with Alucobond as
recently as 2016. The material before the Court does not include the names of
those
14 claimants, or any information about the buildings they own or the
extent of ACP cladding on those buildings.
- [35] In addition
to evidence from representatives of Cutterscove and Argosy, the appellants filed
expert evidence setting out the
basis for their claim. Mr Weaver, a chartered
professional engineer with particular experience in fire engineering, was asked
to
provide opinion evidence about whether Alucobond PE and Alucobond Plus are
combustible, and about relevant requirements of the Building
Code when the
Cutterscove Building was reclad in 2006–2008. He was also instructed that
the plaintiffs were seeking leave
to bring their claims as a representative
claim, and he was therefore asked to provide his opinion as to whether, where
there are
combustibility requirements in compliance documents for the Building
Code, those requirements are met for the Alucobond products.
- [36] Mr
Weaver referred in his first affidavit to “growing recognition that
combustible ACP panels are not fit for use in external
cladding in many
buildings due to the risk that they fuel the rapid spread of fire”. He
expressed the view that Alucobond
Plus and Alucobond PE are both combustible as
determined by the relevant acceptable standard under the Building Code, and are
“combustible
building material” within the meaning of that term
under the Building Code. He summarised his conclusions as follows:
- In
summary, in my opinion, based on the facts, assumptions, reasons and literature
referred to above:
(a) Alucobond PE and Alucobond Plus are combustible; and
(b) when the Cutterscove complex was reclad in 2006–2008, the New Zealand
Building Code relevantly required external walls
and roofs to have resistance to
the spread of fire, appropriate to the fire load within the building and to the
proximity of other
household units and other property. In my opinion the
presence of Alucobond PE cladding is inconsistent with these requirements;
and
(c) where there are combustibility requirements in the compliance documents of
the New Zealand Building Code, there is no evidence
that those requirements have
been met for Alucobond PE and Plus.
- [37] The
respondents contest various aspects of Mr Weaver’s evidence. Skellerup
filed expert evidence in response from Gillian
Stopford, a chartered
professional fire engineer with extensive experience as a fire engineering
consultant. Ms Stopford emphasised
that different requirements in relation to
protection from fire apply to different buildings. A large number of variables
may be
relevant. The term “combustible” does not necessarily signal
a problem or defect with cladding. Combustible cladding
may be used as part of
an external wall cladding system on tall buildings provided it has passed
relevant full scale fire tests.
There are no combustibility requirements for
certain categories of building. The factors that Ms Stopford would need to
consider,
in order to determine whether a particular building complies with the
Building Code in relation to external wall cladding, would
include
the:
26.1 date of issue of building consent, date of construction,
date of issue of certificate of code compliance (and accordingly what
Building
Code requirements, Acceptable solutions, Verification Method, MBIE guidelines
and sprinkler standard were in place at that
time);
26.2 building height;
26.3 use of the building (Purpose Group or Risk Group), such as whether it is
residential, industrial, office, aged care, mixed use
26.4 nature and extent and location of cladding used in the building;
and
26.5 fire safety design for the building, including whether the building is
sprinklered, and
26.6 external wall construction, fire rating requirements, proximity to
boundary, title boundaries, presence of spandrel panels or
aprons, and
26. 7 any ‘alternative solutions’ or engineering judgements that
may have been accepted by the building consent authority
at the time and hence
deemed to meet Building Code requirements.
- [38] Ms Stopford
commented on the lists of buildings prepared by the three city councils. She
expressed the view that a detailed
review of each building listed would be
required to determine the location of the ACP cladding on the building and
whether it would
present a material fire risk in terms of horizontal or vertical
fire spread. She gave examples of buildings on the lists with very
limited
areas of ACP.
- [39] Each of the
experts filed a number of further affidavits. However these are of limited
assistance, in circumstances where it
is not the role of the Court to resolve
disputes between expert witnesses. In particular, Mr Weaver and Ms Stopford
disagree about
whether any combustibility requirements under the Building Code
applied to the Cutterscove Building when it was constructed. That
is not an
issue we need to resolve for present purposes: we proceed on the basis that it
is seriously arguable that such requirements
did
apply.
High Court Judgment
- [40] The
Judge began by summarising the proceedings, and setting out the principles that
govern representative proceedings. He then
set out the issues identified by the
appellants as common issues appropriate for resolution in a representative
claim. The Judge
said these were essentially the denied allegations in the
proceeding, including disputed factual issues relating to PE’s
flammability
and aluminium and ACP combustibility as latent defects, materially
risking spread and severity of fire and consequent loss of life
and property
damage.[12] He identified as the
proposed common legal issues the respondents’ alleged duty of care to
ensure that Alucobond
cladding:[13]
(a) complied with the Building Act 2004 and with the Building Code;
(b) was not subject to the Material Fire Risk Properties (or any of them);
(c) was not subject to the Building Code Non-compliance Properties (or any
of them);
(d) was not subject to the Building Code Non-compliance Risk Properties (or any
of them); and
(e) was fit for all the purposes for which good of its type are commonly
supplied and/or the Purposes ...
- [41] The Judge
recorded his understanding that the appellants argued that
“fitness for purpose” was not to be understood
as constrained
by the state of the Building Code at any time. That, he said, involved
acceptance that any particular failure to
comply with the Building Code is more
for building-by-building assessment by reference at least to the
building’s height, distance
from a relevant boundary, fire suppression
means, and use. These factors, the Judge said, were less susceptible to
“common
issue”
analysis.[14]
- [42] The Judge
considered that the negligence causes of action could not be read without
reference to the Building Code.[15]
He did not think that either appellant, or any other individual member of the
intended group, would seek to argue in their own interests
that the Alucobond
products were inherently incapable of meeting Building Code requirements. Left
to their own devices, he said,
each would be more likely to argue for their
particular cladding’s failure to meet the Building Code requirements
applicable
to their buildings. However, he said, a legitimate reason for
alleging the cladding’s inherent capability may be to incorporate
all
possible Building Code requirements that may apply across the intended
representative group, enabling the representative plaintiffs
to escape the
prohibition against advancing claims other than those which their own claim
represents.[16]
- [43] The Judge
considered that he needed to be satisfied the intended represented group’s
claims would engage a broader range,
if not the whole, of Building Code fire
spread requirements than may apply in the Cutterscove and Argosy cases.
Otherwise he could
not be satisfied a representative proceeding was for the
benefit of the intended represented
group.[17]
- [44] The Judge
noted the limited information available to the Court about other members of the
proposed group, including the 14 claimants
who had signed a litigation funding
agreement. He saw it as commercially unreal to think either appellant would
find it necessary
or desirable to embark on the “inherent
unsuitability” allegation in a claim about their own building(s). Rather,
the
proposed representative proceeding appeared to be sought primarily to enable
the appellants to engage a litigation funder in return
for a share of any
ultimate recoveries.[18]
- [45] The Judge
also had regard to the prejudice to 3AC, Skellerup and Kaneba in terms of time
and expense if they had to defend their
manufacture, supply or installation of
the Alucobond products “against a potentially contrived allegation the
products inherently
are incapable of meeting [Building Code] requirements ...
determination of any contrivance is not an efficient use of scarce Court
and
other resources”.[19]
- [46] Ultimately,
the Judge did not consider that determination of a claim that the Alucobond
products are inherently incapable of
providing for a low probability of fire
spread was a substantial or even proportionate aspect of any claim against the
respondents.[20] The objectives of
representative proceedings were not demonstrably furthered by making the orders
sought by the appellants. The
application for representative orders was
dismissed.[21]
Submissions
on appeal
- [47] The
appellants do not take issue with the principles identified by the Judge as
governing the application of r 4.24(b). Rather,
they say that the Judge
erred in a number of respects in applying those principles.
- [48] First, they
submit that the Judge erred by considering a single common issue. The Judge
should have assessed each of the common
issues in the proceeding before deciding
whether to grant representative orders. Mr Farmer KC submitted that the courts
take an
expansive view of whether group members have the same interest in a
proceeding for the purposes of r 4.24. Group members do not
need to have
the same claims or causes of action; rather, they must only have the same
interest in the subject matter of a
proceeding.[22] That can include a
significant common interest in the resolution of any question of law or fact
arising in the proceeding. A representative
order can be made even though it
only relates to some of the issues in the claim. The threshold is not a
high one.
- [49] Mr Farmer
identified numerous common issues, factual and legal, which he says would arise
in the proceedings. The appellants
provided a litigation plan which set out the
common and individual issues identified by the appellants, which would be
resolved at
Stage 1. Stage 2 of the proceeding would then address individual
issues for Group Members. The appellants’ proposed litigation
plan, which
is central to their argument on appeal, is set out in a schedule to this
judgment.
- [50] The
appellants say that if the Judge had taken into account each of the common
issues in the proceeding, it would have concluded
that the proposed Group
Members have a significant interest in those common issues, and would have
concluded that resolution of those
common issues would lead to the efficient
resolution of much of the proceeding, leaving individual issues to be resolved
at a second
stage.
- [51] Second, Mr
Farmer submitted that the Judge erred in finding that the appellants’
causes of action could not be read without
reference to the Building Code, and
were contrived. The appellants allege that, when installed on a building, there
is a material
risk that the Alucobond products cause or contribute to the rapid
spread and severity of fire. As a result, they say, the Alucobond
products
materially increase the risk of harm to building occupants and damage to the
building itself and to neighbouring buildings.
These are inherent risks that do
not rely solely upon the Building Code, although they are consistent with the
requirements of the
Code. The appellants note that their allegations go
beyond the Building Code: for example, they allege that the Alucobond products
increase the risk of damage to the building and its contents, the protection of
which is not within the scope of the objectives of
cl C of the Code.
- [52] Third, Mr
Farmer submitted that the Judge erred in finding that the appellants had not
established that the inherent unsuitability
of the Alucobond products was
“either a substantial or even proportionate aspect of any claim against
the defendants or any
of
them”.[23] Mr Farmer said
that the inherent unsuitability of the Alucobond products is a central feature
of the pleaded allegations, and is
supported by the expert evidence from Mr
Weaver. That evidence established that the claims were arguable and needed to
be resolved
at trial. The Court could not decline to make representative orders
based on the strength of the claim.
- [53] Mr Farmer
also submitted that the appellants’ allegation that the Alucobond products
are in breach of the Building Code
does not need to be assessed on a
building-by-building basis. The various pathways to compliance under the
Building Code, which
have changed over time, allow for sub-groups to be
established. The litigation plan provided by the appellants referred to four
possible sub-groups.[24] Mr Jeffs,
who appeared with Mr Farmer for the appellants, said that at Stage 1 the trial
judge could assess whether the Alucobond
products met the requirements of the
Building Code in respect of each sub-group. The respondents would not be
prejudiced by this
approach, as they could raise any individual issues at Stage
2 (for example, whether any individual buildings were sprinklered, if
relevant).
- [54] Next, Mr
Jeffs submitted that the Judge erred by focusing on the 14 claimants who
had signed litigation funding agreements, rather
than focussing on the Group
Members as a whole. The proposed Group Members were not limited to persons that
had entered into a funding
agreement. There was affidavit evidence before the
High Court that 14 persons, who collectively owned 30 buildings, had
signed funding
agreements. This indicated there was a group of engaged
plaintiffs committed to advancing the proceeding and thus that it was a
proceeding of substance. It should not have been necessary to lead any further
evidence about Group Members or their potential claims.
A proper assessment of
who the Group Members were was relevant to whether the proceeding would have
economies of scope and scale.
The Judge failed to identify what the alternative
to a representative action would be. That alternative, Mr Jeffs said, would be
for each Group Member to commence a separate action against the respondents.
That would be unwieldy and inefficient. It is precisely
the situation the
representative action procedure is intended to avoid.
- [55] Mr Farmer
submitted that the Judge took into account a number of irrelevant or
unsubstantiated matters in reaching his decision:
(a) The Judge observed that “grant of representative orders is not
intended to recruit the group’s
members”.[25] That
observation was based on a misunderstanding of an earlier decision concerning
notification orders, not the making of representative
orders as
such.[26] Representative orders do
not “recruit” members. Rather, the scope of the Group Members is
determined by the definition
of the Group, and whether a proceeding is opt in or
opt out.
(b) Mr Farmer said that the Judge appears to have considered that litigation
funding was inappropriate or unwelcome in this case.
That seems to have
informed the Court’s finding that the proceeding was contrived. However
litigation funding is an increasingly
common way for plaintiffs to fund a
representative action, and allows claims to proceed that might not have been
brought, levelling
the playing field with well-resourced
defendants.[27] This was not a case
where the litigation funding arrangement was an abuse of process.
(c) The Judge erred in placing emphasis on the prejudice to the respondents from
defending the proceeding. He did not identify any
particular reason why they
would be prejudiced by defending such a proceeding, over and above the ordinary
prejudice to a defendant
of facing a claim.
- [56] The
appellants went on to address a number of additional grounds relied on by the
respondents in their notice of intention to
support the judgment.
- [57] The first
additional ground relied on by the respondents is that the appellants are not
appropriate representatives for a number
of reasons, including that they do not
own buildings with Alucobond Plus, there is no evidence of their suitability to
act as representatives,
and they do not have sufficiently strong claims. Mr
Farmer submitted that none of these arguments is credible. The Cutterscove
Building has Alucobond PE. But Mr Farmer submitted it is not yet
determined whether Argosy’s properties at Favona Road and
Don McKinnon
Drive have Alucobond PE or Alucobond Plus. Although the evidence on behalf of
Kaneba is that it supplied Alucobond
PE for use on Favona Road and Don McKinnon
Drive, no documentary evidence has been proffered to support that claim.
Thus it is a
trial issue. There was no basis for the respondents’
argument that the appellants are unsuitable representatives.
The appellants’
claims are not amenable to summary dismissal and must
be addressed at trial. That is sufficient for the provisional assessment of
merits required for the grant of representative orders. The respondents should
not be permitted to turn the application for representative
orders into a
mini-trial.
- [58] The next
additional ground relied on by the respondents is that they would be unfairly
prejudiced by the proposed representative
orders. Mr Jeffs submitted that this
was not the case. The litigation plan demonstrates how the proceeding could be
managed in
a two-stage trial. The alternative of each Group Member commencing
an individual proceeding, and case managing them together, could
result in
dozens if not hundreds of individual claims against the respondents. That would
be inefficient, and would be likely to
increase the burden on the appellants,
the respondents and the court.
- [59] Nor, Mr
Jeffs submitted, would the respondents be prejudiced by an inability to pursue
affirmative limitation defences and to
pursue claims against third parties.
They would be able to raise affirmative defences. The limitation period for a
contribution
claim does not begin until a tortfeasor’s liability to a
plaintiff has been determined.[28]
So there is little risk of prejudice to the respondents from the time it would
take for this proceeding to be resolved.
- [60] The
respondents’ submissions are addressed, as relevant,
below.
Discussion
Common issues
- [61] We
accept Mr Farmer’s submission that it is possible to identify issues that
would be common to all members of the proposed
group. So, for example, issue 4
in the proposed litigation plan — whether Alucobond cladding was and is
goods of a kind ordinarily
acquired for personal, domestic or household use or
consumption — would arise in each Group Member’s claim under the
Consumer Guarantees Act.[29]
- [62] The
properties of the Alucobond products, including their combustibility and
behaviour when exposed to fire, could also be resolved
as a common issue.
- [63] We also
accept Mr Farmer’s submission that the threshold for establishing that
Group Members have “the same interest
in the subject matter of a
proceeding” is not a high one. It is well established that the court
should take a liberal and
flexible approach in determining whether there is a
common interest. The requisite commonality of interest is not a high
threshold.[30] A representative
order can be made even though it relates only to some of the issues in the
claim. The common question need not
make a complete resolution of the case, or
even liability, possible.[31]
- [64] In these
circumstances, we accept that the threshold for application of r 4.24 is
met: there are persons with the same interest
in the subject matter of this
proceeding.
Should a representative
proceeding be authorised?
- [65] However
that does not mean that a representative proceeding order will automatically be
made. Rather, all it means is that the
minimum threshold for the making of such
an order has been crossed. The real question in this case is whether the
objectives of
the High Court Rules — the just, efficient and speedy
resolution of proceedings — will be advanced by making the opt
out
representation order sought by the
appellants.
Would the proposed
representative proceeding be an efficient use of the court’s
resources?
- [66] We
begin by considering whether the proposed representative proceeding would
contribute to the efficient resolution of claims
relating to the Alucobond
products.
- [67] We
accept Mr Farmer’s submission that the appellants allege that Alucobond is
inherently unsuitable for use as external
cladding, as well as alleging that its
use fails to comply with the Building Code. But inevitably a large part of the
proceeding
will be concerned with compliance with the Building Code. Under the
Code, there are no combustibility requirements for some buildings.
The
requirements that apply to other buildings have varied over time, and depend on
factors such as the height of the building,
its distance from the boundary, its
use, the external wall construction, and other fire safety measures such as
sprinklers. That
reflects the obvious correlation between those factors and
fire safety risk.
- [68] The mere
fact that a cladding material is combustible does not mean that it is inherently
unsuitable for all uses on all buildings:
as the respondents note, wood and wood
products are commonly used as a cladding material in New Zealand for a range of
buildings.
It is we think significant that Mr Weaver’s conclusion was not
expressed at the level of generality that characterises the
issues in the
appellants’ litigation plan. His view, set out at [36] above, was that “where
there are combustibility requirements in the compliance documents of the New
Zealand Building Code, there is no evidence that those requirements have
been met for the [Alucobond products]”. He implicitly accepted that those
products may be consistent with the Building Code where there are no applicable
combustibility requirements. That is clear from
a reading of the Code. He does
not express a view about the inherent unsuitability of the Alucobond products
for use as exterior
cladding independent of the Building Code and its
combustibility requirements, or independent of the features of the building
identified
at [67] above.
- [69] It seems
highly implausible that a single undifferentiated answer could be given to the
question: “Is Alucobond inherently
unsuitable for use as an exterior
cladding material in any quantity and on any building?” Rather, it seems
inevitable that
the answer will correspond to the approach in the Building Code:
that is, “it depends”.
- [70] A more
nuanced approach to risks associated with ACP has been adopted in all of the
regulatory responses that were drawn to our
attention in New Zealand, Australia
and elsewhere, with different measures being adopted in relation to buildings of
a particular
height, or without particular fire safety systems, or with
particular uses.
- [71] The
existence of a material risk to people and structures of the kind that lies at
the heart of the appellants’ claims
does not admit of a single answer when
viewed through the lens of the Building Code. Nor is there any reason to think
it will admit
of a single answer when viewed through the lens of inherent risk.
There was no evidence before us to support such a sweeping proposition,
or even
to suggest that it is arguable.
- [72] We are
therefore sceptical about the potential for useful answers of general
application to be provided at a Stage 1 hearing,
in a manner that would
materially contribute to resolution of individual building owners’ claims
at Stage 2.
- [73] Indeed it
seems to us that there is a real prospect of inefficiency in the hearing of
these proceedings if the Court embarks
on the wide-ranging Stage 1 inquiry that
the appellants contemplate. Their proposed litigation plan would require the
Court to determine,
at the Stage 1 hearing, questions about inherent suitability
and compliance with the Building Code for a very wide range of permutations
of
building characteristics, including many characteristics that are not shared by
the appellants’ buildings. So for example
the appellants’ Subgroup
B focuses on the use of Alucobond products on buildings with a height of 60
metres or more, from 24
November 2017 onwards. The Court could find itself
determining a range of issues in relation to tall buildings of this kind,
including
the risk associated with different extent and location of such
cladding, and the interplay between cladding properties and other
aspects of
external wall construction, and other fire precautions (such as sprinklers) only
to find when Stage 2 is reached that
no such building is the subject of a claim
before the Court. And any findings in relation to this subgroup clearly would
not be
relevant to the claims against the second and third respondents, neither
of which was involved in supply of Alucobond products from
November 2017
onwards.
- [74] Examples
could readily be multiplied. As the respondents point out, the proposed
subgroups are not mutually exclusive, do not
reflect all relevant building
characteristics, and are not comprehensive. Some buildings within the pleaded
claim will not fall
within any of the subgroups: for example, buildings less
than 7 metres high that are more than one metre from a boundary. The subgroups
do not reflect all the factors relevant to assessing compliance with the
Building Code over the relevant period, so the answer to
some issues may vary
within the specified subgroups.
- [75] Put another
way, in circumstances where different categories of building are subject to
materially different regulatory requirements,
conducting a hearing into whether
the requirements are met for every conceivable category would be inefficient and
a poor use of
the resources of the Court and the parties absent a good reason to
think that the inquiry will be relevant to one or more eventual
claimants.
The appellants’ buildings are not representative of all subgroups.
The limited material before this Court about
likely claimants does not enable us
to form a view on whether claimants in each proposed subgroup are likely to
participate in the
proceeding. So we cannot be satisfied that the proposed
inquiry into the position of each subgroup would be a sensible use of the
Court’s time.
- [76] A related
difficulty is illustrated by the inclusion of Alucobond Plus in the
appellants’ claims. The litigation plan
would require the courts to
determine a range of issues relating to that product. The appellants accept
that the Cutterscove Building
is clad with Alucobond PE, not Alucobond Plus. Mr
Gouws, the principal of Kaneba, has given evidence that the small quantities of
Alucobond that Kaneba supplied for the Favona Road and Don McKinnon Drive
buildings were in each case Alucobond PE. The appellants
say there is
no documentary evidence to this effect. But there is no reason to think that Mr
Gouws is in error on this point, and
no evidence to that effect. If Argosy does
not have access to relevant records, the panels could have been removed for
inspection
and/or tested to ascertain which product was used. We are not
prepared to speculate about the possibility that Alucobond Plus was
used (in
very small quantities) on one of Argosy’s buildings absent such evidence.
- [77] If as seems
likely the product supplied by Kaneba for the Argosy buildings is Alucobond PE,
the trial of the appellants’
claims can and should be confined to the
characteristics and risks associated with that product. The different
characteristics and
risk profile of Alucobond Plus will not need to be explored
by the courts at all, let alone in relation to a wide range of different
types
of building and uses.
- [78] This
difficulty can be seen as casting doubt on whether the appellants are
sufficiently representative of the proposed group
of claimants. Alternatively,
and in our view more accurately, it can be seen as going to the (in)efficiency
of the proposed representative
proceeding, which would require the courts to
inquire into issues that would (at Stage 1) be entirely hypothetical so far as
the
parties are concerned. They might become practically relevant at Stage
2, but on the information available to this Court that is
a matter of
speculation.
The burden on the
respondents of defending the proposed claim
- [79] For
the same reasons that the appellants’ proposed representative proceeding
risks being an inefficient use of court time,
it is likely to be
disproportionately burdensome and oppressive for the defendants. They would be
required to engage on, and provide
discovery and fact and expert evidence about,
scenarios that are not raised by either appellant’s buildings and may not
be
raised by any eventual claimant.
- [80] The
oppressive and burdensome nature of such a claim is especially clear in relation
to Kaneba, a small business with a single
principal. Cutterscove has no claim
against Kaneba. Argosy’s claims against Kaneba relate to two small strips
of Alucobond
for the installation of each of which Kaneba charged around
$10,000. If Argosy considers that there is a material risk associated
with
these small quantities of Alucobond, they could readily be removed and replaced
with alternative cladding.[32] But
it appears that Argosy has not done so. A claim for the cost of taking remedial
measures on this modest scale would not normally
be brought in the High Court.
It seems likely that considerably more than the cost of such measures has
already been spent on including
Argosy.
- [81] As Kaneba
submits, if the litigation funder and the lawyers conducting the claim are aware
of a building owner with a more substantial
or more typical claim relating to a
building clad using Alucobond supplied by Kaneba, that building owner could have
been named as
a plaintiff in place of Argosy. But despite the lengthy period
since this claim was first advertised, it seems none has come forward.
- [82] Nor is
there any material before this Court to establish that there is a substantial
number of similarly situated claimants who
wish to pursue claims against 3AC and
Kaneba, but are unable to do so for cost reasons. Representative proceedings
can be an important
way of solving the problem of access to justice where there
is a large class of similarly situated claimants with low value claims,
none of
which would individually be worth pursuing, but which collectively justify the
cost of proceedings. But there is no evidence
before us to suggest that is the
position here.
- [83] We have
some sympathy for Kaneba’s submission that Argosy’s claims are too
minor and too idiosyncratic to serve as
useful representative claims. An
inquiry into the risks associated with using small strips of Alucobond products
for signage on
a single storey Burger King restaurant in the middle of a carpark
seems unlikely to shed light on the use of that product in the
circumstances
where the risks that are the focus of the proceeding are most likely to be
material. This claim is not a promising
springboard for requiring Kaneba to
participate in proceedings relating to every supply it made of Alucobond, for a
wide range of
uses on a wide range of buildings, over a five year period.
- [84] There is
also real force in the respondents’ submission that they will be
prejudiced by a representative claim brought
on an opt out basis because they
will not be able to ascertain what buildings are the subject of the claim until
a much later date
(realistically, identification of claimants at Stage 2 is
unlikely before 2026). That will affect their ability to identify, and
join as parties, the persons who were responsible for design of each relevant
building and for ensuring compliance of each building
with relevant provisions
of the Building Code. Delay in identifying parties against whom contribution is
sought may not give rise
to limitation problems, on the current state of the
authorities. But it will inevitably give rise to practical difficulties as
documents
are lost or destroyed, and as people with relevant knowledge became
unavailable. As Mr Leaming, the chief financial officer of Skellerup,
explained in his affidavit, Skellerup has had no involvement in Alucobond supply
since 2009. Nobody who worked in Skellerup’s
Alucobond business is
currently employed by Skellerup. Because of the time that has passed, Skellerup
has limited records from its
Alucobond business. Similar difficulties are
likely to be encountered in relation to architects, fire engineers and others
involved
in the construction of relevant buildings from that era. The interests
of justice would be better served by identification of all
live claims sooner
rather than later, in these circumstances.
- [85] In short,
we do not consider that a representative claim of the breadth and generality
proposed by the appellants would give
the respondents fair notice of the nature
and scale of the claims against them, and a fair opportunity to defend those
claims.
Alternative pathways for
resolving claims
- [86] Mr
Farmer suggested that the alternative to making representation orders sought was
a large number of individual claims brought
by building owners.
- [87] We are
somewhat sceptical about the number of claims that are likely to materialise, on
the basis of the material before us.
This is not a case where hundreds, or even
tens, of claimants have confirmed that they wish to bring a claim against the
respondents
in respect of the Alucobond products. The evidence of Mr Gouws for
Kaneba and of Mr Leaming for Skellerup was that neither had received
notification of any claims relating to fire safety in respect of any Alucobond
installation work undertaken by them, apart from these
proceedings. And as
already mentioned, there is no evidence before us that regulators in
New Zealand have taken any compliance action
in relation to any building
clad with Alucobond. The absence of complaints or claims directed to Skellerup
and Kaneba, and the absence
of widespread regulatory action, cast doubt on the
likely number of individual claims if a representative proceeding is not
authorised.
- [88] Rather than
commit extensive resources to resolving the proposed representative claim on the
basis of speculation about the likely
number of potential claimants, it seems
preferable to wait to see what claims are actually filed in the High Court,
and then manage
those appropriately. If there are common issues which arise in
more than one proceeding, those could be tried together. That would
avoid the
court being called on to hear and determine a wide range of issues that
ultimately prove to be relevant to no claim at
all.
- [89] An opt in
proceeding might also be a workable alternative that would enable the just and
efficient co-ordinated resolution of
claims relating to Alucobond products. An
opt in claim would enable multiple claims (including claims that might not
otherwise be
viable for cost reasons) to be heard together, without giving rise
to the concerns identified above. But as that approach was not
proposed by the
appellants, we do not consider it further here.
Summary
- [90] Standing
back, our overall view is that the directions sought by the appellants would be
likely to result in inefficiency, poor
use of the court’s resources, and
unjustified and disproportionate burdens on the respondents. It would not be in
the interests
of justice, and would not be consistent with the objectives of the
High Court Rules, to make such an
order.
Result
- [91] The
appeal is dismissed.
- [92] Costs
should follow the event in the ordinary way. The appellants must pay each
respondent costs for a standard appeal on a
band A basis, with usual
disbursements. We certify for second counsel for each
respondent.
Solicitors:
Russell McVeagh,
Auckland for Appellants
Bell Gully, Auckland for First Respondent
Gilbert
Walker, Auckland for Second Respondent
Chapman Tripp, Auckland for Third
Respondent
Schedule
DRAFT LITIGATION PLAN
Note: Paragraph references are to the Amended Statement of Claim dated
23 December 2021 (ASoC) and defined terms have the same meaning as
in the ASoC.
The listed issues are disputed by one or more of the defendants (fully or in
part).[33]
STAGE ONE ISSUES
Common issues (including sub-group issues) and the representative plaintiffs'
individual issues, which can be determined at stage
one of the proceeding.
Factual matters
- Whether
Alucobond Plus had a core of approximately 30% PE (ASoC at [14(b)]).
- Whether
Alucobond PE Core Cladding had one or more of the Relevant Uses (ASoC at
[16]).
- Whether
Alucobond PE Core Cladding was and is commonly bought or supplied in New Zealand
for one or more of the Relevant Uses (ASoC
at [17(a)]).
- Whether
Alucobond PE Core Cladding was and is goods of a kind ordinarily acquired for
personal, domestic or household use or consumption
(ASoC at [17(d)]).
- Whether
PE is a highly flammable synthetic thermoplastic polymer; has a high calorific
value similar to that of petrol or propane
gas; and when ignited has heat of
combustion similar to that of petrol or diesel fuel (ASoC at [18]).
- Whether,
in the event of a fire, the aluminium cover sheets of Alucobond PE Core Cladding
do not protect the PE Core from ignition
for any of the reasons given at [19] of
the ASoC.
- Whether
Alucobond PE Core Cladding is combustible building material within the meaning
of that term under the Building Code (ASoC
at [20]).
- Whether,
when used as cladding fitted as part of, or as an attachment to, an external
wall or other building element, there was, and
is, a material risk that
Alucobond PE Core Cladding will (ASoC at [21]):
- cause
or contribute to the rapid spread and severity of a fire, including the rapid
vertical spread and/or horizontal spread of a
fire in the building; and
- as a
result, will:
- increase
the risk of loss of life in the event of a building fire;
- increase
the risk of damage to the building and/or building contents in the event of a
building fire;
- increase
the risk of damage to adjacent land or property;
- in
the event of a building fire, adversely impact the ability of occupants of the
building to evacuate;
- in
the event of a building fire, adversely impact the ability of the firefighting
authorities to minimise the damage to the building
and building contents, and to
mitigate against the loss of life or injury to persons in the building; and
- represent
a material risk to occupants’ health and safety in terms of the Health and
Safety at Work Act 2015.
- Whether,
and to what extent, the Building Code regulated the use of Alucobond PE Core
Cladding (ASoC at [28]).[34] This
could be determined at stage one by using sub-groups as follows:
- Whether,
and to what extent, the Building Code regulated the use of Alucobond PE Core
Cladding in Relevant Buildings with external
walls that are 1 metre or less from
a boundary, except if that boundary is a road, railway or open public space.
(Subgroup A)
- Whether,
and to what extent, the Building Code regulated the use of Alucobond PE Core
Cladding to Relevant Buildings with a height
of 60 metres or more (from 24
November 2017). (Subgroup B)
- Whether,
and to what extent, the Building Code regulated the use of Alucobond PE Core
Cladding to Relevant Buildings with a height
of 7 metres or more (until 10
April 2012) or 10 metres or more (from 10 April 2012) and which have
sleeping on the upper levels of
the building. (Subgroup C)
- Whether,
and to what extent, the Building Code regulated the use of Alucobond PE Core
Cladding to Relevant Buildings with any one
of the following height-to-boundary
ratios and which are not otherwise subject to combustibility requirements under
the Building
Code: (Subgroup D)
- 20 m
wide x 25 m tall and 30 m or less to the boundary;
- 20 m
wide x 40 metres tall and 36 m or less to the boundary;
- 20 m
wide x 60 metres tall and 42 m or less to the boundary.
- Whether,
and to what extent, any Relevant Buildings are excluded from any of Subgroups
A–D if they are sprinkler protected (ASoC
at [28]).
- Whether
Alucobond PE Core Cladding satisfied Acceptable Solution C/AS1 or C/AS2 when
used in relation to any of Subgroups A–D
(ASoC at [31]).
- Whether
Alucobond PE Core Cladding satisfied Verification Method C/VM2 when used in
relation to any of Subgroups A–D (ASoC at
[32]).
- Whether
Alucobond PE Core Cladding satisfied any Alternative Solution when used in
relation to any of Subgroups A–D (ASoC at
[33]).
- Whether
Alucobond PE Core Cladding was subject to any CodeMark certificate for any of
the Relevant Uses (ASoC at [34]–[35]).
- Whether
Alucobond PE Core Cladding when fitted as part of, or as an attachment to, an
external wall or other building element did
not comply with clauses C1, C2.1,
C2.2, C2.3, C3.1, C3.2 (except for on importance level 1 buildings), C3.3, C3.5
and/or C3.7 of
the Building Code at the time of supply to any of Subgroups
A–D (ASoC at [36]).
- Whether
there was a material risk that Alucobond PE Core Cladding when fitted as part
of, or as an attachment to, an external wall
or other building element did not
comply with clauses C1, C2.1, C2.2, C2.3, C3.1, C3.2 (except for on importance
level 1 buildings),
C3.3, C3.5 and/or C3.7 of the Building Code at the time of
supply to any of Subgroups A–D (ASoC at [37]).
- Whether
the Cutterscove Building is fitted with Alucobond PE in or about 2008 (ASoC at
[39]).
- Whether
the use of Alucobond PE on the Cutterscove Building did not, and does not,
comply with the Building Code (ASoC at [42]–[43]).
- Whether
the use of Alucobond PE Core Cladding on the Don McKinnon Drive did not, and
does not, comply with the Building Code (ASoC
at [44]–[45]).
- Whether
the use of Alucobond PE Core Cladding on Favona Road did not, and does not,
comply with the Building Code (ASoC at [46]–[47]).
- Whether
the state and condition of Alucobond PE Core Cladding were of a kind that: (ASoC
at [48])
- visual
inspection would not detect; and/or
- would
require specialist skill or expertise to:
- detect;
and/or
- understand
the implications thereof; and/or
- once
Alucobond PE Core Cladding is incorporated into a building are not able to be
inspected; and/or
- are
latent, in that until Alucobond PE Core Cladding is incorporated into a building
and a fire at that building occurs, the relevant
state and condition of the
goods will not be known.
Second cause of action:
Negligence
- Whether
3A Composites owed Group Members a duty to take reasonable care to ensure it
designed, manufactured and/or supplied Alucobond
PE Core Cladding in accordance
with the matters at [71] of the ASoC.
- Whether
3A Composites breached that duty for the reasons at [74] of the ASoC.
- Whether
Kaneba owed Group Members a duty to take reasonable care to ensure that the
Alucobond PE Core Cladding it imported, distributed
and supplied was in
accordance with those matters at [72] of the ASoC.
- Whether
Kaneba breached that duty for the reasons at [75] of the ASoC.
- Whether
Skellerup owed Group Members a duty to take reasonable care to ensure that the
Alucobond PE Core Cladding it imported, distributed
and supplied was in
accordance with those matters at [73] of the ASoC.
- Whether
Skellerup breached that duty for the reasons at [75] of the ASoC.
- Whether
Cutterscove and/or Argosy has suffered or will suffer loss and damage by reason
of the negligence of 3A Composites, Kaneba
and/or Skellerup (ASoC at [76]).
- Whether
Cutterscove and/or Argosy are entitled to damages, interest, costs and/or any
other relief against 3A Composites, Skellerup
and/or Kaneba (ASoC at
[77–79]).
Third cause of action: Negligent
misstatement
- Whether
expressly or by implication 3A Composites, Kaneba and/or Skellerup made the:
(ASoC at [81]–[84]):
- Suitability
Representation (including that Alucobond PE Core Cladding was suitable, among
other things, use on buildings with residential,
commercial or government
purposes);
- Fabrication
Representation (including that the various methods by which third parties could
fabricate and install Alucobond PE Core
Cladding would not materially affect the
performance and safety of the cladding);
- Performance
Representation (including that Alucobond PE Core Cladding protected against, and
did not increase the risks associated
with, fire in buildings to which it was
fitted); and/or
- Compliance
Representation (including that Alucobond PE Core Cladding had passed all fire
safety tests required by the Building Code
and standards in New
Zealand).
- Whether
the Representations were continuing representations (ASoC at [85]).
- Whether
3A Composites, Skellerup and/or Kaneba qualified or contradicted the
Representations and/or gave the Relevant Quality Warnings
and/or Relevant
Limitation Warnings (ASoC at [86]).
- Whether
3A Composites, Skellerup and/or Kaneba owed Group Members a duty of care not to
make false, misleading and negligent statements
in relation to Alucobond PE Core
Cladding that might result in economic loss or physical harm (ASoC at
[87]–[89]).
- Whether
the Representations were false or misleading for the reasons at
[91]–[94] of the ASoC.
- Whether
3A Composites, Skellerup and/or Kaneba breached that duty of care by making any
of the Representations (ASoC at [90]).
- Whether
Cutterscove relied upon the Suitability Representation in relation to the
Cutterscove Building or alternatively, derived its
ownership or leasehold
interests through a predecessor in title who had relied upon the Representations
(ASoC at [95] and [97]).
- Whether
Argosy relied upon the Suitability Representation in relation to Don McKinnon
Drive and/or Favona Road or alternatively, derived
its ownership or leasehold
interests through a predecessor in title who had relied upon the Representations
(ASoC at [95]–[96]).
- Whether
Cutterscove and/or Argosy has suffered or will suffer loss and damage by reason
of the negligence of 3A Composites, Kaneba
and/or Skellerup (ASoC at [98]).
- Whether
Cutterscove and/or Argosy are entitled to damages, interest, costs and/or any
other relief against 3A Composites, Skellerup
and/or Kaneba (ASoC at
[99–101]).
Fourth cause of action: Negligent
failure to warn
- Whether
3A Composites, Kaneba and/or Skellerup knew or ought to have known about the
matters at [103] of the ASoC.
- Whether
3A Composites, Kaneba and/or Skellerup had a duty to warn Group Members of the
matters at [104] of the ASoC.
- Whether
3A Composites, Kaneba and/or Skellerup breached that duty by failing, adequately
or at all, to make the Relevant Quality Warnings
and/or Relevant Limitation
Warnings (ASoC at [105]–[109]).
- Whether
Cutterscove and/or Argosy has suffered or will suffer loss and damage by reason
of the negligence of 3A Composites, Kaneba
and/or Skellerup (ASoC at
[110]).
- Whether
Cutterscove and/or Argosy are entitled to damages, interest, costs and/or any
other relief against 3A Composites, Skellerup
and/or Kaneba (ASoC at
[111]–[113]).
First cause of action: Breach of s 6,
Consumer Guarantees Act 1993
- Whether
Cutterscove was supplied with Alucobond PE Core Cladding as a consumer or,
alternatively, derived its ownership or leasehold
interest in the Cutterscove
Building through a predecessor in title who was a consumer (ASoC at
[50]–[53]).
- Whether
Argosy was supplied with Alucobond PE Core Cladding as a consumer or,
alternatively, derived its ownership or leasehold interest
in Don McKinnon
Drive and/or Favona Road through a predecessor in title who was a consumer (ASoC
at [50], [54]–[62]).
- Whether
Alucobond PE Core Cladding is not and was not fit for the purposes for which
goods of that type are commonly supplied and/or
the Purposes and/or safe as a
reasonable consumer fully acquainted with the state and condition of the goods,
including any hidden
defects, would regard as acceptable having regard to the
nature of the goods and all relevant circumstances of the supply of the
goods
(ASoC at [63]).
- Whether
Alucobond PE Core Cladding does not and did not satisfy the Acceptable Quality
Guarantee (ASoC at [64]).
- Whether
the failure of Alucobond PE Core Cladding to satisfy the Acceptable Quality
Guarantee is and was of a substantial character
because of the reasons at [65]
of the ASoC.
- Whether
Cutterscove has suffered or will suffer loss and damage by reason of the
Alucobond PE Core Cladding that was fitted to the
Cutterscove Building and the
failure to comply with the Acceptable Quality Guarantee (ASoC at [66]).
- Whether
Argosy has suffered or will suffer loss and damage by reason of the Alucobond PE
Core Cladding that was fitted to Don McKinnon
Drive and/or Favona Road and the
failure to comply with the Acceptable Quality Guarantee (ASoC at [66]).
- Whether
Cutterscove and/or Argosy are entitled to damages, interest, costs and/or any
other relief against 3A Composites, Skellerup
and/or Kaneba (ASoC at
[67]–[69]).
Fifth cause of action: Breach of s 9,
Fair Trading Act 1986
- Whether
3A Composites, Kaneba and/or Skellerup were in trade (ASoC at
[115]).[35]
- Whether
3A Composites, Kaneba and/or Skellerup engaged in the Misleading or Deceptive
Conduct as at [116] of the ASoC.
- Whether
Cutterscove was misled or deceived by, or relied upon, the Misleading or
Deceptive Conduct in relation to the Cutterscove
Building or alternatively,
derived its ownership or leasehold interests through a predecessor in title who
had relied upon the Misleading
or Deceptive Conduct (ASoC at
[117]–[119]).
- Whether
Argosy was misled or deceived by, or relied upon, the Misleading or Deceptive
Conduct in relation to Don McKinnon Drive and/or
Favona Road or alternatively,
derived its ownership or leasehold interests through a predecessor in title who
had relied upon the
Misleading or Deceptive Conduct (ASoC at
[117]–[119]).
- Whether
Group Members have suffered or will suffer loss and damage by reason of the
Misleading or Deceptive Conduct (ASoC at [120]).
- Whether
Cutterscove and/or Argosy are entitled to damages, interest, costs and/or any
other relief against 3A Composites, Skellerup
and/or Kaneba (ASoC at
[121]–[123]).
Sixth cause of action: Breach of s 16,
Fair Trading Act 1986
- Whether
3A Composites, Kaneba and/or Skellerup were in trade (ASoC at
[125]).[36]
- Whether
3A Composites, Kaneba and/or Skellerup made the false and misleading
representations at [126] of the ASoC.
- Whether
Cutterscove was misled or deceived by, or relied upon, the false and misleading
representations in relation to the Cutterscove
Building or alternatively,
derived its ownership or leasehold interests through a predecessor in title who
had relied upon the false
and misleading representations (ASoC at [127]).
- Whether
Argosy was misled or deceived by, or relied upon, the false and misleading
representations in relation to Don McKinnon Drive
and/or Favona Road or
alternatively, derived its ownership or leasehold interests through a
predecessor in title who had relied upon
the false and misleading
representations (ASoC at [127]).
- Whether
Cutterscove and/or Argosy are entitled to damages, interest, costs and/or any
other relief against 3A Composites, Skellerup
and/or Kaneba (ASoC at
128]–[130]).
STAGE TWO ISSUES
The group members’ individual issues, which can be determined at stage
two of the proceeding.
- Whether
each Group Member is within the definition of “Group Member” in [9]
of the ASOC.
- Whether
each Group Member owns or previously owned, or leases or previously leased, a
Relevant Building fitted with Alucobond PE Core
Cladding manufactured by 3A
Composites.
- Whether
each Group Member owns or previously owned, or leases or previously leased, a
Relevant Building fitted with Alucobond PE Core
Cladding supplied by Kaneba
and/or Skellerup.
- Whether
there are any individual reasons specific to a Group Member as to why the use of
Alucobond PE Core Cladding would not be in
breach of the Building Code.
- In
relation to the third cause of action, whether each Group Member, their agents
and/or people involved in the design, construction
and maintenance of buildings
to which Alucobond PE Core Cladding is now or was a part relied on any of the
Representations to their
detriment.
- In
relation to the first cause of action, whether each Group Member was supplied
with Alucobond PE Core Cladding as a consumer or,
alternatively, derived its
ownership or leasehold interest in a Relevant Building through a predecessor in
title who was a consumer.
- In
relation to the fifth cause of action, whether the Misleading or Deceptive
Conduct misled, deceived and/or was relied upon by each
Group Member, their
agents and/or other people whose conduct relied on the Misleading or Deceptive
and caused loss or damage to each
Group Member.
- Generally,
whether Group Members have suffered or will suffer loss and damage by reason of
any of the first to sixth causes of action
against 3A Composites, Kaneba
and/or Skellerup.
- Generally,
whether Group Members are entitled to damages, interest, costs and/or any other
relief by reason of any of the first to
sixth causes of action against 3A
Composites, Skellerup and/or Kaneba.
- Whether
the entitlement of each Group Member to relief is barred or reduced by any
affirmative defence pleaded by any one of 3A Composites,
Kaneba and/or
Skellerup.
[1] We refer to these two products
together as “the Alucobond products”. There are other cladding
products branded as “Alucobond”
that are outside the scope of these
proceedings.
[2] Body Corporate Number DP
91535 v 3A Composites GmbH [2023] NZCA 647.
[3] Body Corporate Number DP
91535 v 3A Composites GmbH [2022] NZHC 2355 [High Court judgment].
[4] Southern Response
Earthquake Services Ltd v Ross [2020] NZSC 126, [2021] 1 NZLR 117.
[5] At [26].
[6] At [37] and [40].
[7] Cridge v Studorp Ltd
[2017] NZCA 376, (2017) 23 PRNZ 582 at [11].
[8] At [11] (footnotes
omitted).
[9] Southern Response
Earthquake Services Ltd v Ross, above n 4, at [41].
[10] At [89].
[11] Footnotes omitted.
[12] High Court judgment, above
n 3, at [16].
[13] At [16] (footnotes
omitted).
[14] At [17].
[15] At [21].
[16] At [22].
[17] At [23].
[18] At [26]–[27].
[19] At [28].
[20] At [29].
[21] At [30] and [31].
[22] Credit Suisse Private
Equity LLC v Houghton [2014] NZSC 37, [2014] 1 NZLR 541 at [55].
[23] High Court judgment, above
n 3, at [29].
[24] See para 9 of the
litigation plan, in the schedule to this judgment.
[25] High Court judgment, above
n 3, at [23].
[26] Ross v Southern Response
Earthquake Services Ltd [2021] NZHC 2452 at [26].
[27] Referring to the Law
Commission Ko ngā Hunga Take Whaipānga me ngā Pūtea
Tautiringa | Class Actions and Litigation Funding (NZLC R147, 2022) at
54.
[28] Citing Beca Carter
Hollings & Ferner Ltd v Wellington City Council [2022] NZCA 624 at [47],
[123]–[125] and [147]–[148].
[29] In our judgment on the
appellants’ appeal in relation to 3AC’s protest to jurisdiction,
delivered with this judgment,
we have concluded that on the material before this
Court it is not seriously arguable that Alucobond cladding meets this test. But
that is not a final determination of the issue on the merits at trial.
[30] Cridge v Studorp
Ltd, above n 7, at
[11(g)–(h)], set out at [23] above.
[31] At [11(e)], set out at [23] above.
[32] Mr Gouws’ uncontested
evidence was that the Alucobond strips on the Burger King restaurant at Don
McKinnon Drive that Kaneba
had supplied could be removed by a tradesperson with
a ladder and a screwdriver.
[33] There are two instances
where it is unclear if the matters are disputed. This uncertainty is noted as
it arises.
[34] It is unclear if this is
disputed.
[35] It is unclear if this is
disputed.
[36] It is unclear if this is
disputed.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2023/648.html