You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2024 >>
[2024] NZCA 33
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
HWD NZ Investment Co Limited v Body Corporate 392418 [2024] NZCA 33 (27 February 2024)
Last Updated: 4 March 2024
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
HWD NZ INVESTMENT CO LIMITED Appellant
|
|
AND
|
BODY CORPORATE 392418 Respondent
|
Hearing:
|
3 May 2023 (further submissions received 24 August 2023)
|
Court:
|
Katz, Hinton and Churchman JJ
|
Counsel:
|
J D Haig and S J Wong for Appellant T J G Allan for Respondent
|
Judgment:
|
27 February 2024 at 11.30 am
|
JUDGMENT OF THE COURT
- Leave
to adduce further evidence is declined.
- The
appeal is dismissed.
- The
appellant must pay the respondent costs for a standard appeal on a band A
basis together with usual
disbursements.
____________________________________________________________________
REASONS OF THE COURT
(Given by Hinton J)
- [1] On
16 December 2022 Associate Judge Brittain declined to set aside a statutory
demand served by the respondent, Body Corporate
392418, on the appellant,
HWD Investment Co Ltd (HWD) under s 289 of the Companies Act 1993 (the
Act).[1]
The statutory demand related to non-payment of building repair levies under a
scheme of arrangement ordered by Robinson J in the
High Court on
18 March 2022.[2]
HWD appeals.
- [2] By consent
order, the parties have agreed that the decision on this appeal will apply also
to a second judgment of Associate Judge
Brittain dated 17 March 2023 declining
to set aside a second statutory demand for building repair
levies.[3]
- [3] Subsequent
to the hearing of this appeal, on 16 May 2023 HWD filed a further memorandum as
to the merits of a separate substantive
claim brought by it against the Body
Corporate in light of the recent High Court decision in Body Corporate 207624
v Grimshaw &
Co.[4]
HWD also filed updating submissions and evidence setting out a revised
calculation of its claim against the Body Corporate on 15
August 2023.
The Body Corporate filed memoranda in response on 18 May and
23 August 2023 respectively. Leave is required in respect
of these
matters.
Background
- [4] The scheme
under which the relevant levies were issued relates to a unit title development
at 132 Stancombe Road, Flat Bush, Auckland.
The development consists of 47
units spread across three blocks, referred to as A, B and C. Blocks A and C
were developed by HWD
which retained nine of the units in those blocks.
- [5] The
development had weathertightness and fire issues. The Body Corporate alleged
those defects were attributable to negligence
by Auckland Council, HWD and other
parties involved in the development’s construction. In November 2016, the
Body Corporate
commenced proceedings against those parties (the negligence
proceeding), claiming approximately $13.6 million in repair costs. The
unit
owners, bar HWD, were included as second plaintiffs. They claimed general
damages and consequential losses of approximately
$2.6
million.[5]
- [6] The Body
Corporate advised HWD at the outset of the negligence proceeding that it was not
included as a second plaintiff, despite
its ownership of nine
units.[6] HWD was also advised that
it would be levied its share of any repair costs as an owner but would be
“unable to recover any
of those levies through the litigation
process”.
- [7] On 7 April
2021 the Body Corporate applied to the High Court for an order under
s 74 of the Unit Titles Act 2010 (the UTA) to
settle a scheme for the
repair and remediation of the development. The scheme application was opposed
by HWD.
- [8] Unbeknown to
HWD, on 15 September 2021, the Body Corporate and second plaintiffs entered into
a conduct and distribution agreement
(the distribution agreement) authorising a
settlement committee to represent the plaintiffs in settlement negotiations and
address
the apportionment of any settlement proceeds. That agreement was not
before the Associate Judge, although the effect of it was able
to be
surmised.[7] It was disclosed in
February 2023 after a number of requests were made to the Body Corporate by
HWD. The distribution agreement
provided that the settlement funds must first
be used to pay all outstanding fees incurred by the Body Corporate or the
unit owners
in relation to the proceeding, including legal and expert fees. The
balance was to be apportioned to remedial costs required to
be paid by the
second plaintiffs and to claims for loss on sale, in the proportion that these
categories of claim represented to
the overall claim (excluding general damages
and legal costs).
- [9] On 3
November 2021 the negligence proceeding was settled in full by payment of $9.75
million from the Council to the Body Corporate.
HWD declined to participate in
the settlement in its capacity as defendant. The settlement agreement did not
allocate the funds
either as between the second plaintiffs or in respect of
different heads of damages. The Council’s cross-claims and third-party
claims were preserved, including its cross-claim against HWD.
- [10] From the
settlement sum, the Body Corporate paid to the second plaintiffs a sum of
approximately $2.2 million on account of “all
legal fees and or charges
associated with litigation”.
- [11] In February
2022 the Body Corporate held an extraordinary general meeting. It resolved to
enter into a building contract for
repairs in the sum of $9.5 million plus GST
and to levy owners a sum of $12 million including GST, for payment on
27 May 2022. It
was recorded that the second plaintiffs’ share
of the $12 million levy would be covered by the settlement from the Council,
with top-up levies only being raised if final costs were greater than expected.
In the event of delayed payment by corporate owners
(of which there were only
two, one being HWD) the Body Corporate resolved to allow immediate issue of
statutory demands.
- [12] Instead of
allocating levies split by common property, building elements and unit property
(as the defects claim had been drawn)
the Body Corporate determined to levy
based on the proportionate split between each block. No allocation was made for
common property.
- [13] Based on
HWD’s ownership interest and the resolutions at the extraordinary general
meeting, on 16 February 2022 the Body
Corporate levied HWD in the total sum
of $2,166,184 — $1,314,264 for its block A units and $851,919 for its
block C units —
with payment due on 27 May 2022. HWD queried
the quantum on the basis that no credit had been allocated to it from the
settlement
funds received by the Body Corporate. It requested, among
other things, a copy of the distribution agreement. The Body Corporate
did not
provide the information sought.
- [14] On 18 March
2022 the s 74 scheme application was
approved.[8] HWD did not appeal. HWD
says it expected at that point that the Body Corporate would ultimately retain
funds to pay for the cost
of common property.
- [15] Having
failed to obtain the information it sought, on 20 May 2022 HWD filed
proceedings against the Body Corporate, seeking damages
for misapplication of
the settlement funds (HWD’s substantive proceeding). HWD alleged it was
improper for the Body Corporate
to divest its own interest in the settlement
funds entirely for the benefit of the second plaintiffs, to the detriment of
HWD. HWD’s
substantive proceeding relies on the Body Corporate, as the
owner of the common property and the party responsible for repairs, owing
statutory and equitable duties under ss 54 and 138 of the UTA to all owners
including HWD.
- [16] On 22 May
2022 the Body Corporate resolved to reverse the levies issued in February 2022
and to re-issue levies for the same
amount and on the same basis, but with
staggered payment dates to reflect construction completion dates and slightly
varied block
allocations. On 1 June 2022 HWD was levied $2,099,510 —
$1,392,896 for block A and $706,614 for block C. The block C levy
was due on 17
June 2022 and the block A levy on 13 August 2022.
- [17] In June
2022 HWD settled the Council’s cross-claim against it, which was then
discontinued. HWD says it “thus contributed
to the settlement sum paid to
settle the [Body Corporate]’s defects claim”. No mention is made as
to the quantum of
HWD’s contribution.
- [18] HWD did not
pay the block C levy by 17 June 2022, relying on its previous correspondence and
noting its substantive proceeding
seeking allocation of a share of the
settlement proceeds. Following that non-payment, on 27 June 2022 the
Body Corporate served
a statutory demand on HWD in the sum of $706,614.
- [19] Also on 17
June 2022, the Body Corporate, instead of filing a statement of defence in
HWD’s substantive proceeding, filed
a notice of appearance protesting
jurisdiction on the basis that HWD’s claim was caught by cls 19–22
of the scheme, being
arbitration and dispute resolution provisions. HWD applied
to set aside the protest, saying these provisions did not apply.
- [20] By letter
dated 1 July 2022, HWD objected to the quantum of the 27 June 2022 statutory
demand and on 18 July 2022 it paid $210,000,
being HWD’s calculation of
the sum due after subtracting its assessment of an appropriate credit from the
settlement funds.
The Body Corporate declined to withdraw the statutory demand
and HWD applied to set it aside.
- [21] HWD also
failed to pay the block A levy, leading the Body Corporate to issue a second
statutory demand, for the sum of $1,392,896.
HWD paid $390,000 on
16 September 2022, again its assessment of what was due, and applied
to set aside the statutory demand.
Relevant law and scheme
provisions
- [22] Section
290(4) of the Act addresses an application to set aside a statutory demand as
follows:
(4) The Court may grant an application to set aside a statutory demand if it is
satisfied that—
(a) there is a substantial dispute whether or not the debt is owing or is
due; or
(b) The company appears to have a counterclaim, set-off, or cross-demand and
the amount specified in the demand less the amount of
the counterclaim, set-off,
or cross-demand is less than the prescribed amount; or
(c) The demand ought to be set aside on other grounds.
- [23] The appeal
engages s 290(4)(b). In Manchester Securities Ltd v Body Corporate 172108
this Court provided guidance on the application of that
subsection:[9]
Just as any defence must be shown to be reasonably arguable, so
must any set-off, counterclaim or cross-demand. However, the obligation
is not
to prove the actual claim. It is not expected that the dispute itself is to be
tried in the course of hearing the application.
It has been said that
“clear and persuasive” grounds must be shown for a set-off, rather
than a mere assertion. There
must be a real evidential basis for the claim, and
the claim must be arguable as a matter of law.
In relation to contingent and unquantified counterclaims or set-offs, it has
been held that the court must be able to determine from
the material provided
whether the amount of the set-off or counterclaim is more than the amount
claimed in the statutory demand.
- [24] Ordinarily
it will only be a “rare case” where the court will exercise the
discretion to refuse to set aside a statutory
demand when an applicant has
clearly made out grounds for setting aside under s
290(4).[10] However, the court is
hesitant to set aside statutory demands where, as in the present case, the
alleged counterclaim arises in
the context of what is referred to as a
“pay now argue later” provision. This is particularly true in the
context of
unit title schemes, the principle being that “pay now
argue later” provisions facilitate the management of body corporate
developments which otherwise would be unworkable, while preserving unit title
holders’ right to object to/challenge body corporate
levies. This
approach is considered fair because if a unit holder is ultimately successful in
disputing a levy, the net result is
they are only required to bear the cost of
the (unjustified) levy for a relatively short period.
- [25] The
relevant clauses of the current scheme are as follows:
Dispute
Resolution
- The
Body Corporate’s decisions on any matter arising under the Scheme shall be
final in all respects except where 2 or more
Owners whose objection in monetary
value cumulatively exceeds $30,000, or where one unit holder has an objection
which in monetary
terms exceeds $15,000.
- Any
Owner wishing to object to a decision of the Body Corporate must give notice to
the Body Corporate manager of their objection
within 10 working days of
receiving notice from the Body Corporate of the relevant decision (the notice
shall be received by the
Owner one day after it is sent to the Owner’s
last known physical or email address provided to the Body Corporate).
- Upon
receipt of any objection notice the Body Corporate will refer the matter to an
arbitrator (to be appointed by the President of
the Arbitrator’s and
Mediator’s Institute of New Zealand) and the arbitrator shall determine
the matter in accordance
with the provisions of the Arbitration Act. The costs
of the arbitration shall be borne between the objecting Owner(s) and the Body
Corporate as the arbitrator decides.
- No
Owner shall be entitled to withhold payment of levies that fall due on the basis
that an objection has been raised or an objection
is pending
arbitration.
The judgment of Associate Judge Brittain
- [26] The
Associate Judge addressed the two interlocutory issues in HWD’s
substantive proceeding against the Body Corporate.
- [27] He found in
favour of HWD on its application to set aside the Body Corporate protest to
jurisdiction, on the basis that HWD’s
substantive proceeding was not a
dispute involving a decision of the Body Corporate under the
scheme.[11] HWD’s substantive
proceeding was therefore not required to be referred to arbitration under
cl 21. The apportionment of the
settlement sum by the Body Corporate and
owners was inferred to have been made pursuant to the distribution
agreement.[12] The Associate Judge
found the Body Corporate was not in fact empowered to determine distribution of
the settlement funds under the
scheme
itself.[13]
- [28] The
jurisdiction finding has not been appealed by the Body Corporate (which has
now filed a statement of defence in HWD’s
substantive proceeding).
- [29] With regard
to HWD’s application to set aside the Body Corporate’s statutory
demand, the Associate Judge found:
(a) HWD’s objection to the payment of levies amounts to a set-off or
counterclaim.[14]
(b) HWD had met the threshold of establishing clear and persuasive grounds for
the set-off or counterclaim in terms of s 290(4) of
the
Act.[15]
(c) The policy argument in favour of “pay now argue later” clauses
in schemes ordered under s 74 of the UTA applied such
that a broad
interpretation of cl 22 of the scheme was justified, similar to this
Court’s approach in Manchester
Securities.[16] The Associate
Judge said the policy argument is of general application with no distinction to
be made on the basis of body corporate
cash flow, which will be different under
every scheme.[17]
(d) The “pay now argue later” obligation in cl 22 applied such
that the statutory demand ought not be set aside because
an objection for the
purposes of cl 22 included objections in the form of legal proceedings and
therefore “an objection had
been
raised”.[18]
- [30] The
Associate Judge briefly considered the merits of HWD’s substantive claim
which he described as complex both in terms
of fact and
law.[19] But he seemed to address
that point only in terms of his conclusion that the threshold in
s 290(4)(b) had been met. He did not
consider the merits of HWD’s
substantive proceeding further when addressing his
discretion.
Issues on appeal
- [31] The parties
agree that the sole issue on appeal is whether the Associate Judge erred in
finding that cl 22 of the scheme, which
it is accepted is a “pay now argue
later” clause, justified exercising the discretion under s 290(4) of the
Act to not
set aside the statutory demand.
- [32] The appeal
is against exercise of a discretion. The decision will not be upset unless
contrary to principle, it considered an
irrelevant factor, disregarded a
relevant factor, or was wholly
wrong.[20]
Submissions
- [33] HWD says
that the Associate Judge erred in exercising his discretion under s 290(4)
because HWD’s substantive proceeding
is not “an objection”
under cl 22 and that clause, on which the Judge relied, is therefore not
applicable.
- [34] In any
event, if cl 22 does apply, HWD submits the Associate Judge failed to consider
the statement in Manchester Securities that it would only be a
“rare case” where the discretion would be exercised and he failed to
provide reasons as to why
this case fell into that category. HWD submits that
the present case is not a “rare case” where the exercise of the
discretion could be justified:
(a) The case can be distinguished from Manchester Securities where it was
clear that the “pay now argue later” clause was engaged. Further,
unlike in Manchester Securities, HWD’s substantive claim has not
already been considered by the courts, HWD has acted in good faith and its claim
is particularised
to the requisite degree.
(b) The cooperative principle behind the UTA should not have primacy because the
“pay now argue later” scheme does not
apply to HWD’s
substantive proceeding, HWD has suffered a cash drain due to the
Body Corporate failing to act prudently and
HWD has already contributed a
significant amount in respect of the defects claim and levies for the building
work.
(c) Other unit holders are unfairly attempting to make HWD meet the shortfall
between the settlement sum and the cost of redevelopment
works.
- [35] As noted
above, in supplementary submissions filed after the hearing, HWD referred to the
recent decision of Tahana J in Grimshaw &
Co.[21] HWD submits that
this decision supports its substantive proceeding. It says if its appeal is
dismissed liquidation would likely follow
which would automatically stay any
proceeding and enable the Body Corporate to avoid HWD’s meritorious case.
That would be
highly unjust.
- [36] In
response, the Body Corporate takes the position that the Associate Judge
correctly applied the law. It emphasises that HWD
was notified from the
commencement of the negligence proceeding (November 2016) that it would not
be receiving any of the proceeds.
It could have taken action much earlier.
The Body Corporate disputes that Grimshaw & Co has any relevance
to whether the Associate Judge erred in exercising his discretion.
Leave to adduce new evidence and memoranda
- [37] HWD seeks
leave to adduce further evidence in the form of various statements, financial
reports and documentation pertaining
to the apportionment and distribution of
settlement funds by the Body Corporate. The application falls to be considered
under r
45 of the Court of Appeal (Civil) Rules 2005. That rule requires
further evidence to be fresh, credible and
cogent.[22]
- [38] HWD submits
the further evidence “informs the Court further as to the sums in dispute
and what is to be determined at the
substantive hearing of HWD’s
claim”. The Body Corporate opposes the application on the basis that HWD
has not acted
with alacrity and the evidence is not cogent to an issue on
appeal.
- [39] We agree
with the Body Corporate that leave to adduce further evidence should be
declined. Evidence as to the quantum of HWD’s
substantive claim is
primarily relevant to whether the counterclaim meets the s 290(4)(b) threshold.
That is not in dispute. At
issue is whether the Associate Judge was right to
exercise his discretion under s 290(4). The quantum of the counterclaim is not
sufficiently cogent to that assessment. The evidence does not meet the
threshold for granting leave under r 45.
- [40] We accept
HWD’s submission that Grimshaw & Co has some relevance to the
issues on appeal as briefly discussed below. We grant leave for filing of the
further memoranda on that
point.
Does cl 22 of the scheme apply
to HWD’s outstanding unpaid levies?
- [41] HWD says
the Associate Judge’s finding that its substantive proceeding does not
amount to “an objection” for
purposes of cl 22 means the clause
does not apply to its application under s 290(4)(b) of the Act.
- [42] However,
the question for the purposes of HWD’s application under s 290 is not
whether its substantive proceeding is “an
objection”, but whether
the Body Corporate’s decision to levy HWD is “a matter arising
under the scheme”
in terms of cl 19 and whether HWD’s non-payment is
an objection. The answer to both questions is plainly yes. Under cl 19
the decision to levy is final in all respects except where owners object (and
the objection meets the relevant monetary threshold).
HWD has clearly objected
to the decision to levy. It objects to and is withholding payment (at least in
substantial part).
- [43] It follows
that cl 22 applies and HWD is not entitled to withhold payment of levies on
the basis that it has raised an objection.
- [44] The fact
that HWD did not give notice of its objection in time in terms of cl 20 or
seek to have it referred to arbitration in
terms of cl 21 does not detract
from HWD’s non-payment being an objection in terms of cl 19. An objection
is not limited for
the purpose of cl 22 to an objection given within a specific
period or an objection referred to arbitration. While the clauses are
not
clearly drawn, it would be illogical if a unit owner who did not pay a levy and
did not comply with the provisions of cls 20
and 21 was in a better position to
stave off a statutory demand than one who did comply with the objection
process.
Was the Associate Judge wrong to exercise his
discretion under s 290(4) by not setting aside the statutory
demand?
- [45] HWD
satisfied the Associate Judge in terms of s 290(4)(b) that it “has
met the threshold of establishing clear and persuasive
grounds showing a
set-off or counterclaim”.[23]
It is implicit in this finding that the Judge accepted that the quantum of the
set-off or counterclaim was at least equal to the
amount of the statutory
demand. In those circumstances, the Court may set aside the statutory demand.
- [46] For HWD to
successfully appeal the Associate Judge’s decision it needs to show, as
set out above, that he failed to take
account of a relevant factor, took account
of an irrelevant factor or his decision was plainly wrong.
- [47] We consider
that the Associate Judge was right to use his discretion not to set aside the
statutory demands but for slightly
different reasons to those he advances.
- [48] The
Associate Judge held that the statutory demand must stand because of the
“pay now argue later” clause, and this
Court’s decision in
Manchester Securities. As is clear from our finding above, we agree that
the “pay now argue later” clause is engaged. We also agree that the
application of that clause is an important factor in the exercise of the s
290(4) discretion. However, we consider the issue is
more nuanced than is
expressed in the judgment under appeal.
- [49] This
Court’s decision in Manchester Securities is not authority for the
proposition that where a “pay now argue later” scheme applies it
will always be appropriate for a court to use its discretion not to set
aside a statutory demand. The Court specifically said it was not necessary
to
formulate a test for exercise of the
discretion.[24]
- [50] In
Manchester Securities, the Court exercised the discretion not to set
aside the statutory demand, even though the applicant had satisfied the
threshold
requirement. However, the applicant’s ability to “argue
later” was only one factor the Court
considered.[25] The Court was also
influenced by the fact that the applicant was attempting to “relitigate
matters already decided”,[26]
including a court order that the applicant make payment immediately, that the
applicant had acted in a “dilatory” and
“prevaricating”
manner and that its claim was poorly
particularised.[27] As HWD submits,
these factors are not present here, although as subsequently noted, we consider
there has been delay on HWD’s
part.
- [51] We also
accept HWD’s submission that a number of factors additional to those
referred to in Manchester Securities can be relevant to the exercise of
discretion under s 290(4) even where a “pay now argue later”
scheme applies. Unlike
the Associate Judge, we consider the financial
position of the parties to be a relevant factor, particularly where the Body
Corporate
is not in pressing need of funds and the applicant faces potential
loss of a counterclaim through liquidation or otherwise. The
strength of a
counterclaim would also be relevant in this context.
- [52] However, in
this case, the financial position of the Body Corporate supports the decision
not to set aside the statutory demand.
While the Body Corporate received a
substantial settlement from the Council, it will clearly suffer a shortfall on
the building
contract, if it has not already, if HWD does not pay the levies.
It may even be unable to complete the repair works required.
- [53] Also,
although HWD argues that it stands to lose its ability to counterclaim because
of the risk of liquidation, there is no
evidence that it is unable to meet the
statutory demands and therefore unable to pursue its substantive
proceeding.
- [54] There is
also no suggestion that the Body Corporate would not be able to pay an award in
the event HWD successfully disputed
the levies. As touched on above, the
benefit of the “pay now argue later” scheme is that it preserves
HWD’s ability
to dispute the levies while enabling the Body Corporate to
fund the remedial works required. If HWD is ultimately successful in
its
objection, it will recover what it is owed. Any issue with HWD having unfairly
paid more towards levies or remedial work than
it should have can be resolved
through its substantive proceeding.
- [55] We do not
need to address HWD’s associated point regarding its alleged significant
contribution to the defects claim, as
the quantum of that contribution is not
evidenced. It would be difficult also to measure the significance and relevance
of any such
contribution in the present context.
- [56] We accept
HWD’s submission that Tahana J’s decision in Grimshaw & Co
is relevant to the merits of its substantive proceeding. That case suggests
that body corporate recipients of negligence proceeding
settlements are required
to allocate a portion of settlement funds to cover the common property
proportion of any defects claim.[28]
Body Corporates are also required to distribute settlement funds having regard
to body corporate repair obligations under s 138 of
the UTA, including the
duty to repair and maintain the common
property.[29] However,
notwithstanding Grimshaw & Co, we do not consider the merits of
HWD’s substantive proceeding so obviously strong as to prevail over cl 22.
As the Associate
Judge said, HWD’s substantive proceeding is complex.
- [57] Even if the
merits of HWD’s substantive proceeding were obviously strong, we would
still be of the view that the Associate
Judge appropriately exercised his
discretion. In addition to the factors considered above, HWD had been on notice
since November
2016 as to the Body Corporate’s position (whether correct
or otherwise) regarding HWD’s inability to recover levies through
the
negligence proceeding, yet its substantive proceeding was only served in May
2022. We acknowledge the position may not have
been clear to HWD particularly
with regard to common areas, but nonetheless, it had the opportunity to bring
its claim much earlier.
This is a material factor in the exercise of the
discretion.[30]
- [58] In the
round, we are satisfied that the combination of the “pay now argue
later” scheme, financial position of the
parties and delay in HWD’s
substantive proceeding render this an appropriate case for the exercise of the s
290(4) discretion.
The statutory demands stand.
Result
- [59] Leave to
adduce further evidence is declined.
- [60] The appeal
is dismissed.
- [61] The
appellant must pay the respondent costs for a standard appeal on a band A
basis together with usual disbursements.
Solicitors:
Davidson Legal,
Christchurch
Grove Darlow & Partners, Auckland
[1] HWD NZ Investment Co Ltd v
Body Corporate 392418 [2022] NZHC 3472 [judgment under appeal].
[2] Body Corporate 392418 v
Chan [2022] NZHC 503.
[3] HWD NZ Investment Co Ltd v
Body Corporate 392148 [2023] NZHC 526.
[4] Body Corporate 207624 v
Grimshaw & Co [2023] NZHC 979. The judgment was issued on 28 April
2023.
[5] The quantum sought was
finalised only in a fourth amended statement of claim dated
22 October 2021.
[6] The second plaintiffs were
owners of individual units in the development.
[7] Judgment under appeal, above n
1, at [53].
[8] Body Corporate 392418 v
Chan, above n 2.
[9] Manchester Securities Ltd v
Body Corporate 172108 [2018] NZCA 190, [2018] 3 NZLR 455 at [27]–[28],
citing Covington Railways Ltd v Uni-Accommodation Ltd [2000] NZCA 230; [2001] 1 NZLR 272
(CA) at 274–275; and Provida Foods Ltd v Foodfirst Ltd [2012] NZCA
326, (2012) 21 PRNZ 546 at [32] (footnotes omitted).
[10] Manchester Securities
Ltd v Body Corporate 172108, above n 9, at [49].
[11] Judgment under appeal,
above n 1, at [68].
[12] At [53].
[13] At [65]–[67].
[14] At [58].
[15] At [90].
[16] At [91], citing
Manchester Securities Ltd v Body Corporate 172108, above n 9.
[17] At [91].
[18] At [92]–[93].
[19] At [86]–[90].
[20] May v May (1982) 1
NZFLR 165 (CA) at 170.
[21] Body Corporate 207624
v Grimshaw & Co, above n 4.
[22] Rae v International
Insurance Brokers (Nelson Marlborough) Ltd [1998] 3 NZLR 190 (CA)
at 192.
[23] Judgment under appeal,
above n 1, at [90].
[24] Manchester Securities
Ltd v Body Corporate 172108, above n 9.
[25] At [56]–[58].
[26] At [54].
[27] At [61], citing Body
Corporate 172108 v Manchester Securities Ltd [2017] NZHC 329 at [14]; and
Manchester Securities Ltd v Body Corporate 172108 [2017] NZCA 527 at
[44].
[28] Body Corporate 207624 v
Grimshaw & Co, above n 4, at
[287(a)].
[29] At [287(c)]; and Unit
Titles Act 2010, s 138(1)(a).
[30] See Sunglass Hut New
Zealand Ltd v Amtrust Pacific Properties Ltd HC Auckland, M1710/02, 24 June
2003 at [46]–[47]; and Luxe One Ltd v Body Corporate 68792 [2017]
NZHC 2672 at [172] where failure to challenge amounts claimed over a significant
period was a factor justifying the exercise of discretion not to set
aside a
statutory demand.
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2024/33.html