You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2024 >>
[2024] NZCA 415
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Moorhouse Commercial Park Limited v Vero Insurance New Zealand Limited [2024] NZCA 415 (3 September 2024)
Last Updated: 9 September 2024
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
MOORHOUSE COMMERCIAL PARK LIMITED Appellant
|
|
AND
|
VERO INSURANCE NEW ZEALAND LIMITED Respondent
|
Hearing:
|
17-18 April 2024
|
Court:
|
Cooke, Moore and Osborne JJ
|
Counsel:
|
S P Rennie, J E Bayley and F H Scrase for Appellant C M Brick and A
R Cornwell for Respondent
|
Judgment:
|
3 September 2024 at 10.30 am
|
JUDGMENT OF THE COURT
- The
appeal and cross-appeal are dismissed.
- The
appellant must pay the respondent costs for a standard appeal on a band B
basis together with usual disbursements. We certify
for second counsel. There
is no award of costs on the
cross-appeal.
____________________________________________________________________
REASONS OF THE COURT
(Given by Cooke and Osborne
JJ)
Table of Contents
Para
No
Introduction [1]
Background [3]
The
Policy [7]
Epoxy repair and bond
loss [18]
Appellant’s
arguments [23]
Analysis [28]
Particular
repairs [54]
Relevant legal principles [55]
Northern
exterior wall at 41 Moorhouse Avenue [64]
Southern or eastern
exterior walls at 41 Moorhouse Avenue [82]
Inter-tenancy walls at
33–35 Moorhouse Avenue [87]
The east wall at 43 Moorhouse
Avenue [107]
Suspended first floor slab [115]
Building
consent [121]
Other issues [132]
Indemnity value:
Vero’s cross-appeal [133]
Indemnity value: Moorhouse’s
appeal [136]
Interest [141]
Costs [144]
Result [146]
Introduction
- [1] Moorhouse
Commercial Park Ltd (Moorhouse) appeals from the decision of the High Court
largely dismissing its claim for breach
of contract against Vero Insurance
New Zealand Ltd
(Vero).[1]
Moorhouse claimed under its insurance policy with Vero for damage to its
buildings at 33 to 41 and 43 Moorhouse Avenue, Christchurch,
arising out of the
Canterbury earthquakes in late 2010 and early 2011. Before the High Court,
Moorhouse alleged that Vero had breached
the insurance policy in a number of
ways. Dunningham J dismissed Moorhouse’s claims that the damage to
its buildings had been
more extensive than Vero had
accepted.[2]
- [2] Moorhouse
appeals this finding, and also advances other claims in relation to particular
matters. Vero cross-appeals one finding
made concerning the basis upon which
Moorhouse’s entitlement is to be calculated.
Background
- [3] The insured
buildings are on a large commercial site covering approximately 4,500
m2 on the north side of Moorhouse Avenue. There are two insured
buildings, one at 33 to 41 Moorhouse Avenue, and a separate building
at
43 Moorhouse Avenue (the Buildings).
- [4] The building
at 33 to 41 Moorhouse Avenue has shallow concrete strip footings and concrete
slab on grade, reinforced concrete
columns and beams, and brick or concrete
block infill walls between the columns and steel rafters. The roof is largely
comprised
of corrugated asbestos sheets with some glass panels to let in light.
The roof over one smaller portion is made from corrugated
iron. The overall
building was progressively built between 1954 and 1997. It now comprises six
separate areas occupied by tenants
which operate two gymnasiums, food retail,
offices, and other retail premises. The first building was constructed in 1954
as a single
storey warehouse (35 Moorhouse Avenue) and a single storey office
(37 Moorhouse Avenue). By 1961, two further single storey warehouses
were
added at 33 and 41 Moorhouse Avenue. Between 1961 and 1964, a second
storey was added to 37 Moorhouse Avenue, and in 1962 the
two warehouses at
33 and 35 Moorhouse Avenue were extended to the north. There was a further
extension in 1980 to form what is now
39 Moorhouse Avenue. In 1980, a
mezzanine floor was also added at the southern end of 35 Moorhouse Avenue. In
1992, a reinforced
concrete block masonry partition wall was added between 33
and 35 Moorhouse Avenue, and a mezzanine floor was added within the two
southern
bays of 33 Moorhouse Avenue. At some point between 1994 and 1997, reinforced
concrete block masonry partition wall was
added between 33 and 39 Moorhouse
Avenue, and a mezzanine floor was added over the southern bays of
41 Moorhouse Avenue.
- [5] 43 Moorhouse
Avenue was built in 2004 as a separate two storey office building. It is
constructed from reinforced pre-cast concrete
tilt panels which were constructed
between concrete columns and steel beams. The foundations comprise reinforced
concrete shallow
strip footings and pads and a concrete slab floor. The first
floor consists of a concrete slab cast on steel tray decking. The
roof
comprises long run steel.
- [6] One further
feature of both buildings is they are constructed in very close proximity to
neighbouring buildings. The property
at 33 to 41 Moorhouse Avenue abuts a
neighbouring property to the west, and the east wall of 43 Moorhouse Avenue is
also only 100
mm away from a neighbouring property.
The
Policy
- [7] The
Buildings were covered by a material damage policy that Moorhouse had with Vero
(the Policy). It provided:
If, during the Period of Insurance,
any:
- Physical Loss
or Damage unintended and unforeseen by the Insured happens to any Insured
Property;
- Costs or
Losses arise for which this Policy is expressly extended;
then,
subject to the terms, conditions and exclusions of this Policy, the Company will
indemnify the Insured for the loss, damage
and costs.
- [8] The Policy
then specified the required basis of the insurance settlement. For buildings
identified covered by the Policy’s
“Reinstatement Memoranda”
reinstatement cover was prescribed. This cover applied to the Buildings. Cover
was also expressly
extended to damage arising from earthquakes. Under the
prescribed basis, Vero had the ability to elect either to make payment or
to
undertake the reinstatement or repair required.
- [9] The
reinstatement cover was identified in the following
way:
REINSTATEMENT
In the event of any Insured Property to which this Memorandum applies being
lost, damaged or Destroyed, the basis on which the amount
payable under this
Policy is to be calculated will be the cost of Reinstatement of the property,
subject to the special provisions
of this Memorandum.
- [10] “Reinstatement”
was defined in the following
terms:
(a) “Reinstatement” means:
(i) where property is lost or Destroyed, its replacement by Equivalent
Property;
(ii) where property is damaged but not Destroyed, the repair of the damage and
the restoration of the damaged portion of the property
to a condition
substantially the same as, but not better or more extensive than, its condition
when new, but incorporating such alterations
as are necessary to comply with any
Act of Parliament or Regulation.
- [11] This
reinstatement cover was subject to a limitation in the following terms:
- In
any of the following circumstances, no payment will be made beyond the amount
which would have been payable had this Memorandum
not been incorporated in the
Policy:
(a) if the Insured elects not to Reinstate the
property;
(b) if the work of Reinstatement is not commenced and carried out with
reasonable despatch;
(c) until the cost of Reinstatement has actually been incurred, or agreed
between the Company and the Insured.
- [12] Such a
limitation on reinstatement cover is common. An insured is usually only
entitled to recover the cost of reinstating their
property — with a
building, essentially the cost of rebuilding it to the specified standard
— if they actually do rebuild.
They do not have the option of being paid
the cost of rebuilding but then not doing so.
- [13] When an
insured does not actually rebuild, they are nevertheless covered for the
indemnity value.[3] The indemnity
value is defined in the following way:
Indemnity Value: The
reinstatement cost of the property to a condition not better or more extensive
than when new less due allowance for depreciation
and deferred maintenance.
- [14] The main
difference between reinstatement cover and indemnity cover is accordingly the
deduction for depreciation and deferred
maintenance.
- [15] There is no
dispute that the Buildings were damaged by the Canterbury earthquakes that
occurred between September 2010 and February
2011. But there is a significant
dispute as to the extent of the damage, and what is required to reinstate the
building to the Policy
standard. There is also a dispute about the calculation
of the indemnity value. Notwithstanding that the earthquakes and resulting
damage occurred more than 13 years ago, Moorhouse maintains the stance that
unless and until Vero accepts the extent of the damage
caused, and what is
required to reinstate the Buildings to the Policy standard, it cannot make the
decision on whether it will actually
rebuild and be eligible for reinstatement
cover, or whether it is now limited to recovering only the indemnity value as
prescribed.
- [16] It would
appear that the reinstatement work Moorhouse says is required would require the
Buildings to be largely demolished and
reconstructed given their integrated
character. There may be some artificiality in the suggestion that buildings
which have had
substantial repair and upgrade works, and which are occupied by
tenants, will nevertheless be demolished and reinstated some 13 years
after they
were damaged. But we accept that there is a genuine dispute about the extent of
that damage and that Moorhouse may not
be able to know how to proceed until it
knows what its entitlements are. In any event, there is no issue before us
arising out of
the extent of the delay since the insured events, other than its
relevance to the determination of interest payable.
- [17] The main
dispute focus is on the extent of the damage caused to the Buildings by the
earthquakes, and Moorhouse’s insurance
entitlement as a consequence.
There are other issues in relation to particular work that has been undertaken
at the Buildings.
There is also a dispute about the calculation of
“depreciation and deferred maintenance” under the definition of
indemnity
value.
Epoxy repair and bond loss
- [18] The main
area of dispute arises from Moorhouse’s allegation that the Buildings
suffered greater damage than Vero assessed,
primarily arising out of what is
called “bond loss” (outlined at [20] below), and that Vero’s
“epoxy repair” methodology would not repair the Buildings to
the Policy standard —
namely that they be restored to a condition
substantially the same as when new.
- [19] Vero’s
epoxy repair solution essentially involves repairing the cracks that had
occurred throughout the Buildings by injecting
them with epoxy resin. Moorhouse
says that whilst this fills in the cracks caused by the earthquake, it does not
address underlying
earthquake damage to the Buildings, primarily the loss of
“stiffness” caused by that underlying damage.
- [20] That
underlying damage is said to have arisen by a concept known as “bond
loss” or “bond slippage”.
In short, this is a kind of damage
that can arise with steel reinforced concrete, particularly when the steel
reinforcing is not
“ribbed” but is “smooth”. There was
a period of construction where it was not appreciated that having ribbed
steel
reinforcing rods within concrete assisted the steel rods to grip the concrete.
Smooth steel reinforcing rods, such as those
used in these Buildings, are more
likely than ribbed steel reinforcing rods to lose their connection with the
concrete during an
earthquake event causing the phenomena known as bond loss.
This damage occurs before a further stage of damage, referred to as
“yielding”,
where the steel reinforcing rods bend or yield during
the event causing further damage. But bond loss alone can cause damage and
result in a loss of stiffness of the building overall.
- [21] Expert
evidence was given for Moorhouse by Ms Jan Stanway, a structural engineer. She
is familiar with bond loss damage, including
from work she has undertaken on
damage to structures in Wellington following the Kaikōura earthquake. She
gave evidence that
Vero’s epoxy injection solution did not meet the Policy
standard, including because the Buildings had suffered bond loss damage
and a
consequential loss of stiffness. She disagreed with the opinion of Vero’s
expert, Dr Nicholas Brooke, also a structural
engineer, that the epoxy
injection approach met, what was reasonably required to repair the damage to the
Policy standard. Ms Stanway’s
opinions were supported by further
expert evidence of Mr Adam Walker who had conducted the initial engineering
assessments that she
had reviewed.
- [22] The High
Court preferred the evidence of Dr Brooke and dismissed Moorhouse’s claims
in this
respect.[4]
Appellant’s
arguments
- [23] Mr Rennie,
for Moorhouse, argued that the opinions of Mr Walker and Ms Stanway should
have been preferred by the High Court.
Epoxy repair is a repair technique that
can be used for some aspects of construction, repair, and maintenance of
buildings, but
there are no textbooks or standards to follow for a repair to the
kind of damage arising here. No testing has been performed by
Dr Brooke to
quantify the loss of stiffness, and none is established by the literature, with
knowledge of what epoxy repair can restore
in its infancy. The Policy standard
of restoring the building to substantially the same as new can accordingly not
be met. This
was reflected in the fact that the epoxy applicator had not given
a warranty.
- [24] The Policy
standard of “substantially the same as ... when new” does not allow
the insured to be left with diminished
functionality through a reduced ability
to resist future seismic forces. Relying on the decision in Aktieselskabet
de Danske Sukkerfabrikker v Bajamar Compania Naviera SA (the Torenia), Mr
Rennie argued the onus was on Vero to establish that the epoxy repair would meet
the Policy
standard.[5]
The Judge could not, in reliance on Dr Brooke’s opinion, safely conclude
that the Policy standard would be met by the epoxy
injection repair. He relied
on the rigour required for establishing the validity of expert opinion
identified by the Daubert factors that have been applied in New
Zealand.[6]
- [25] The Judge
also erred in relying on engineering evidence and reports that described the
damage to the building as minor or moderate
and in observing that the damage was
“mostly cosmetic”.[7] The
appearance of cracks after an earthquake event does not evidence how wide they
were at the time of the event itself, or the
consequential damage. Cracking to
concrete elements compromises the stiffness of the building and its ability to
resist future seismic
forces. Ms Stanway had analysed the cracking that
appeared in the building, including cracking at the base of the columns at 33
to
41 Moorhouse Avenue. She said that this cracking was consistent with bond loss.
Dr Brooke did not have an explanation for why
the cracking appeared at the base
of the columns.
- [26] Further,
the Judge erred in relying on Dr Brooke’s further evidence that, even if
there had been bond loss, the calculated
loss of stiffness to the building was
not material. Ms Stanway’s evidence was that bond loss could result in an
overall reduction
of stiffness of more than 20 per cent after epoxy repair. She
was of the view that in future earthquakes there would be increased
non-structural damage as a result of the reduction in stiffness.
- [27] The Judge
also erred in finding support from Dr Brooke’s opinions which relied on
materials that related to the use of
epoxy repairs generally, rather than the
specific question of building stiffness. Mr Rennie referred to the so-called
Hamburger
Report, commissioned by the Christchurch City Council (the
Council), which concluded that epoxy injection would generally not restore
earthquake damaged structures to the substantially as when new standard where
there was damage of the kind arising
here.[8]
The Judge also erred in characterising Ms Stanway’s evidence as
“overly
risk-averse”.[9]
Analysis
- [28] In our
view, this is a case that had factual challenges. But, in the end, we consider
that the case was and is resolved by the
application of the burden of proof.
- [29] An
insurance policy is a contract. A plaintiff alleging that the contract has not
been performed must prove that
breach.[10] Here, it is accepted
that there has been damage to the Buildings which engaged Vero’s
contractual obligations. Vero considers
it those obligations are met by its
epoxy repair solution. Moorhouse alleges that that is not so because the damage
to the Buildings
is more profound than Vero has assessed meaning that
Vero’s proposed repair solution is insufficient to repair the damage.
To
establish this, and thereby prove a breach of contract, Moorhouse must prove
that this further damage occurred.
- [30] Mr Rennie
relied on The Torenia for the proposition that the burden shifted to Vero
to establish that its repair strategy met the policy standard. The Torenia
stands for the general proposition that the person who alleges must
prove.[11] But it is Moorhouse
alleging that Vero has breached the contract. Vero said in its defence that its
repair solution meets the policy
standard, but that does not mean that it has a
burden to prove it has not breached the contract by adopting that stance.
Moorhouse
still has the burden.
- [31] The
burden of proof does not shift to the insurer because this is an insurance
contract. The burden can shift to the insurer
to show that any relevant
exclusion of liability under the policy
applies.[12] But that was not the
case here. The insurer’s duty of good faith will also mean that it has
certain obligations in relation
to a
claim.[13] The insurer would be
obliged to investigate the claim in good faith to assess what it considers the
damage to the property to be.
That will likely require the instruction of
competent experts to provide their impartial opinion. But it is not the
insurer’s
burden to prove that suggested damage did not arise. The
insured must still prove its allegation that there was additional damage
not
accepted by the insurer.
- [32] As Ms Brick
submitted, for Vero, an argument similar to that advanced by Moorhouse was made
in Myall v Tower Insurance
Ltd.[14] This Court concluded
that “[n]o question of shifting burdens arises; the Court was applying a
policy standard ... not considering
whether an exclusion applied, and it was
doing so in a particular factual
context”.[15] The same
approach applies here.
- [33] On appeal,
Moorhouse also has the burden of establishing the High Court was wrong. Such an
appeal is approached without any
question of deference to the High Court in
accordance with the standard outlined by the Supreme Court in
Austin, Nichols & Co Inc v Stichting
Lodestar.[16] The overall
position was summarised in He v Earthquake
Commission:[17]
[7] [The
plaintiff] bears the burden of making out his claim at trial and on appeal. In
particular, the burden is on [the plaintiff]
to establish that the house
suffered damage caused by the Canterbury earthquakes. It is not sufficient for
him to point to the (undisputed)
dislevelment of the house’s floor, or to
establish that it is possible that this might have been caused or contributed to
by
the earthquakes. He needs to show on the balance of probabilities that
differential settlement of the house was caused or materially
contributed to by
the earthquakes.
- [34] Equally
here, it is not sufficient for Moorhouse to point to the undisputed fact that
earthquake damage has been occasioned to
the Buildings, or to establish that it
is possible that greater damage may have been caused. It needs to show, on the
balance of
probabilities, that greater damage was caused or materially
contributed to by the earthquakes.
- [35] We
accordingly need to assess whether Moorhouse discharged the burden of proof by
showing that the Buildings suffered additional
damage, and that epoxy repair is
not a sufficient method of repairing that damage. As Mr Rennie accepted, epoxy
repairs can be appropriate
in some circumstances. The Hamburger Report on which
he relied appears to have accepted
this.[18] If there has been no
greater damage caused to the Buildings other than the cracking itself, then
epoxy repairs are an established
repair technique. We agree with the High Court
Judge that Moorhouse needed to prove that additional damage had been caused in
order
to demonstrate that epoxy repairs were not
appropriate.[19] In reviewing
Ms Stanway’s evidence criticising the epoxy repair, the Judge
concluded:[20]
[129]
These issues are important because, as she said in her evidence, it was the
inability to restore the bond between the reinforcement
and the concrete which
was the key reason for rejecting epoxy injection as a means to restore the
concrete columns in most of the
33 – 41 Moorhouse Avenue building. If I
am not satisfied on the balance of probabilities that such damage has occurred,
her
main reservation about the use of epoxy is addressed.
- [36] The Judge
then reviewed the evidence of Ms Stanway and Dr Brooke and concluded she
preferred that of Dr Brooke.[21]
She said:
[132] Having reached the view that, on the balance of
probabilities, there is no material damage to the reinforcement, nor is there
debonding between it and the concrete, the primary concerns about the efficacy
of epoxy to restore the stiffness of the building
are eliminated. That accords
with the conclusions in the Hamburger report (which Ms Stanway’s evidence
endorses), which supports
the use of epoxy repairs for minor or moderate
concrete cracking but raises doubts about its use to repair significant damage,
or
to completely restore the bond between concrete and reinforcing steel, when
that has been lost.
- [37] Part of the
reason for the Judge’s conclusions was that Ms Stanway had, herself,
approached the issues on the basis that
Vero had an obligation to prove that the
damage had not occurred.[22] The
Judge also concluded that Ms Stanway had taken an “overly risk-averse
approach”.[23] We agree that
there is some force in these criticisms. The example identified by the Judge
was Ms Stanway’s evidence that
there had been no testing of the lost
strain capacity of the
reinforcement.[24] The Judge also
observed that, in her evidence, Ms Stanway was not prepared to discount the
possibility that there had even been
yielding of the reinforcing during the
earthquakes.[25] We agree that the
substance of these opinions involves a suggestion that Vero had to disprove the
possibility that Moorhouse’s
allegations raised, including by conducting
tests of some kind.
- [38] We have
some sympathy for the position that Moorhouse was in. However, we consider that
Moorhouse has not proved, on the balance
of probabilities, that bond loss did
occur. Bond loss during earthquakes is a recognised phenomenon that can arise
with smooth reinforcing
bars within
concrete.[26] We accept that
Moorhouse has demonstrated that it is possible that bond loss occurred in these
buildings. The Buildings were vulnerable
to this phenomenon because smooth
round bars were used in some of the construction. There has been earthquake
damage to the Buildings
as evidenced by the cracking. Ms Stanway, a
well-qualified expert, believes bond loss has occurred. But there is no real
way of
knowing whether it has actually occurred, even on the balance of
probabilities. No evidence was led to suggest a way of conducting
a test to
establish whether it has happened. Neither is there any recognised way of
establishing it from external damage such as
the cracking that has been
identified. The fact that it is possible does not mean it has probably
occurred. In those circumstances
we do not accept that bond loss has been
proved.
- [39] Mr Rennie
was critical of Vero’s epoxy injection repair strategy on the basis that
it was not a well-established approach.
He raised the Daubert criteria,
used to assess the admissibility and weight to be attached to expert scientific
evidence,[27] arguing that the epoxy
injection strategy did not meet such standards. He argued that the epoxy repair
approach had not been sufficiently
peer reviewed, tested, subjected to
measurable performance criteria, or generally accepted by the industry, and
therefore should
not have been relied on by the Judge.
- [40] We do not
accept these arguments. The first point is that the Daubert criteria
were developed and applied for a different purpose. They exist to establish
whether a particular novel scientific method
or technique can be relied upon by
a court as admissible expert evidence. They were not developed as criteria to
be applied to determine
whether a particular method or technique should be used
to repair damage to buildings. They can, perhaps, be a helpful guide for
the
reliability of novel techniques. But that is not their purpose.
- [41] Secondly,
we also do not consider that the Daubert criteria directly apply to
expert engineering evidence. The criteria are applicable to novel scientific
evidence. The criteria
have been applied in New Zealand in relation to
cutting edge questions of science in both
criminal[28] and
civil[29] proceedings to address
whether particular evidence is admissible. We do not consider that approach
applies in the same way to expert
opinion evidence about engineering issues,
such as the extent of damage to buildings. Such engineering issues involve the
application
of judgment and experience as much as the validity of scientific
techniques. The criteria do not apply with the same force in this
context.[30] Whilst failure to meet
the criteria in the context of novel scientific evidence may lead to exclusion
of the evidence, or little
reliance being placed on it by the court, this is not
the case here.[31] But the
Daubert criteria can nevertheless be helpful — the more criteria
are met by a proposed approach or technique of an engineering expert,
the more
reliable it may be.
- [42] More
importantly, we consider that the need to follow criteria to establish the
validity of particular methods or techniques
ultimately has more relevance to
Moorhouse’s claim than it does to their criticism of Vero’s repair
strategy. Moorhouse
contends, on the basis of Ms Stanway’s evidence, that
there has been substantial latent damage to the Buildings, primarily
arising
from bond loss. Based on Dr Brooke’s evidence, this is disputed.
There are then no well-established tests or standards,
known error rates, or
peer reviewed articles, that have been provided to us, that can then be applied
to identify whether this damage
has occurred or
not.[32] We do not consider that
the High Court can be criticised for concluding that Moorhouse had failed to
meet the burden of proof against
that background.
- [43] The point
is illustrated by the competing expert evidence relating to the significance of
the location of the cracks at the base
of some of the columns. Ms Stanway
gave evidence that the existence and location of this cracking was consistent
with bond loss.
But no literature or other material was identified
demonstrating that such cracking can be used to establish the existence of bond
loss. The Daubert criteria, if applicable, would suggest the need for
tests, known error rates, peer review, and wide acceptance if such cracking were
to be used to establish the existence of bond loss within the Buildings. As we
say, we do not suggest that the Daubert criteria need to be satisfied for
the evidence to be admissible. But the absence of any recognised way to assess
whether the cracking
is consistent with bond loss makes the ability to make
findings more difficult. The position became further complicated by Ms
Stanway’s
evidence that the cracks appeared in this location in some
columns, but not others, because in some cases the reinforcing would not
have
been anchored to the foundations. Whether that was factually correct or not was
then questioned when plans associated with
the original construction were found.
They suggested that the reinforcing may have been anchored.
- [44] It very
difficult for the Court to make findings based on expert evidence of this kind.
The opinion of an expert may be enough,
by itself, in some cases. But the lack
of some accepted basis that the court could use to reach conclusions is
significant. The
position is no easier on appeal where the court is seeking to
assess the expert evidence based on the transcript. Moorhouse is unable
to
prove, on the balance of probabilities and through the application of some
recognised test or other technique accepted as reliable
in the industry, that
the damage occurred. We consider that ultimately means that the High Court was
right to reject Ms Stanway’s
opinion.
- [45] For the
above reasons, we are of the view that the High Court did not err in rejecting
Moorhouse’s claim.
- [46] But there
is a further element. Dr Brooke gave evidence that, even if bond loss had
occurred as Ms Stanway suggested, it would
not have had any material impact on
the ability of the Buildings to resist future earthquakes. He gave evidence
that a 20 per cent
or less reduction in the stiffness as a result of
bond loss — the range assessed by Ms Stanway — would have an
insignificant
impact on the buildings movement in future earthquakes. For
example, he assessed that during the February 2011 earthquake there
may have
been a movement of approximately 25 mm at the top of the columns at 33 to 41
Moorhouse Avenue. The increase in movement
from the reduced stiffness (if it
had occurred) was assessed by him as limited to approximately 1 mm.
- [47] Ms Stanway
had relied on laboratory studies on the extent of impact of reduced stiffness of
5 to 20 per cent.[33] She did not
agree with Dr Brooke’s evidence, but the point was made by Vero before us
that the materials used in the laboratory
work had been more significantly
damaged, and that it had not been tested in real world situations. The Judge
ultimately found that
the additional displacement of the building under a
moderate earthquake would be so minimal that she accepted that the epoxy repair
would restore the building to policy
standard.[34]
- [48] Mr Rennie
argued that the Judge erred in relying on Dr Brooke’s evidence. We accept
that this evidence only represented
Dr Brooke’s opinion, and that it was
not based on a well-established technique for measuring the effects of decreased
stiffness
recognised by the engineering profession. But it was for Moorhouse to
prove that there had been damage to the Buildings as alleged.
- [49] As Ms Brick
submitted, the trigger for cover under the Policy is “physical
damage” to the Buildings. Not all changes
to a building after an
earthquake will necessarily meet this definition. The courts have defined
physical damage in this context
as meaning a detrimental physical change to the
insured property which impairs the value, amenity, or usefulness of the property
in a way that is material and not de
minimis.[35]
- [50] If bond
loss occurred, there will likely have been physical change within
the Buildings. But that change is only relevant if
it detrimentally
affects the value, amenity, or usefulness of the Buildings. We consider it
important that bond loss was not alleged
to have made the Buildings any weaker
in terms of their ability to resist future seismic events. The contest between
the experts
was more specific — that the Buildings were less stiff.
That is that they would move more in future earthquakes. If they
moved more, it
could cause greater damage, including to the contents of the buildings, in
future earthquakes.
- [51] For
Moorhouse to prove its claim, it needed to prove not only that bond loss had
occurred, but also the detrimental effect that
bond loss had in terms of the
value, amenity, or usefulness of the Buildings. Dr Brooke conducted an analysis
and his conclusion
was that even with a 20 per cent reduction in stiffness, any
increases in displacement of the building during an earthquake would
still be
“insignificant”. Ms Stanway did not agree based on the
laboratory tests she referred to. But it was for Moorhouse
to prove this
detrimental effect. We are satisfied that it did not do so. Once again, it
raised only a possibility that the potential
latent damage had caused such a
detrimental effect.
- [52] Again, we
acknowledge the potential problem for Moorhouse. It is possible that such
latent damage occurred, and its Buildings
are less stiff in a way that could
cause greater damage in future earthquakes. There appears to be no way of
establishing this,
however. To succeed with a claim before the court, the party
must satisfy the burden of proof. Moorhouse did not do so and has
not done so
on appeal.
- [53] We
accordingly reject Moorhouse’s arguments on this aspect of its
appeal.
Particular repairs
- [54] The next
aspect of Moorhouse’s appeal relates to the findings of the High Court in
relation to particular repairs conducted
at the Buildings. The High Court found
that the repairs conducted or scoped to be conducted had met Vero’s
obligations under
the Policy. On appeal, Moorhouse submits that the Judge erred
in this finding.
Relevant legal principles
- [55] Much of the
argument in this Court, as in the High Court, on two of these repair areas
focused on whether the repair work undertaken
was a permanent repair, or a
temporary repair. The Policy included the following
term:
DEMOLITION, REMOVAL OF DEBRIS AND OTHER COSTS
This Policy extends to cover costs necessarily incurred for any of the
following purposes in consequence of loss or damage covered
by this Policy:
...
- temporary
repairs and other measures (including the erection and maintenance of street
and/or pavement hoardings and/or scaffolding)
to secure the property or to make
it safe or suitable for continued use.
- [56] On appeal,
Moorhouse says that for two areas of repair work there was only a temporary
repair under this clause, and that it
was entitled to have a permanent repair
meeting the Policy standard undertaken.
- [57] Before
addressing those two areas, we first address the appropriate legal principles
that are to be applied in relation to these
arguments. They were not referred
to other than in passing by the parties, and neither were they addressed in any
detail by the
High Court Judge given the arguments advanced in that Court.
- [58] We consider
that the starting point is that the insured is entitled to have any repairs
undertaken to the standard specified
by the Policy. In the contemporaneous
documents and the parties’ submissions, reference was made to a standard
of “like
for like”. That is not the standard set by the Policy.
The standard is “restoration of the damaged portion of the property
to a
condition substantially the same as, but not better or more extensive than, its
condition when new” in accordance with
the definition of
“reinstatement”.[36] We
agree with the High Court Judge’s formulation of that standard in the
following way:[37]
[82]
The “when new” standard does not require exact replication of the
original; modern materials and techniques may
be used. The standard of repair
required is to render the fact of earthquake damage immaterial. When deciding
what standard of
remediation is required by the policy, regard must also be had
to the purpose of the damaged component. Where an item has a functional
purpose
only, then so long as the repair or replacement restores that functional purpose
to a “when new” condition, the
obligations under the policy will be
met. Where the component also has an aesthetic purpose, the remediation
strategy must restore
the former aesthetic to a “when new”
quality.
- [59] Whether
repairs are intended to be temporary, or permanent, may ultimately not matter.
What matters is whether the Policy standard
has ultimately been met.
- [60] It is not
uncommon for the insured and the insurer to have discussions about the nature of
repairs that are to be undertaken
to satisfy the Policy. It is possible that
the nature of those discussions may reach the point where a fresh agreement or
variation
to the original agreement is reached pursuant to which the insurer is
no longer obliged to meet the Policy standard — that
is that there has
been accord and satisfaction.[38]
Alternatively, the point might be reached where the insured is estopped from
claiming that particular works did not meet the Policy
standard because it would
be unconscionable to allow the insured to assert that new work is required
because of their effective agreement
to work of a different, or lesser
standard.[39] Care would need to be
applied in reaching a conclusion that an estoppel has operated when the insured
may not have a full appreciation
of the ramifications of particular repairs,
particularly where the insurer had a contractual right to undertake those
repairs. The
burden would be on the insurer to establish accord and
satisfaction or an
estoppel.[40]
- [61] The
discussions between the insurer and insured can have a further dimension
relevant to the “substantially as new”
standard. Assessing whether
that standard is met includes an examination of the purpose and use of the
element of the building that
is in issue. The discussions between the insured
and the insurer may shed light on that question. Agreement may be reached on
how
the relevant element is to be restored to substantially the same standard as
when it was new, bearing in mind its particular purpose
and use. The insured
may be happy with an alternative construction method, or material, because it is
substantially the same in
terms of its utility and other factors. So,
agreements reached in such discussions may be good evidence that the
substantially as
new standard has been met.
- [62] Given the
analysis above, it may be that much of the argument advanced before us on the
two disputed areas does not focus on
the key issue. It is not whether the
repairs were temporary or permanent that counts. It is whether the repairs meet
the Policy
standard. If they do not meet the Policy standard, then Vero remains
contractually obliged to meet that standard unless accord and
satisfaction, or
possibly an estoppel, is made out by Vero.
- [63] We address
the various elements of the building in dispute against that
background.
Northern exterior wall at 41 Moorhouse Avenue
- [64] The
northern exterior wall of 41 Moorhouse Avenue was originally constructed with
unfilled concrete masonry block. The lower
sections were concrete block, and
the upper sections were lightweight timber construction with metal
cladding.
- [65] The wall
suffered earthquake damage and was repaired in 2012 by removing the infill
elements and replacing those and the block
elements with a Hardie Board type
construction. Vero met the cost of this work at $10,865.52.
- [66] The repair
scope put forward by Moorhouse at trial provided for the replacement of this
repaired wall with concrete filled masonry
block. Moorhouse did not directly
refer to the 2012 repair in its evidence. At trial, it was submitted for
Moorhouse that the 2012
repair was a temporary repair as defined in the
Policy.
- [67] In his
evidence for Vero, Mr Allott, a Commercial Resolution Teams Manager,
recorded:
- During
2012, MWH arranged for some urgent works which the owners’ engineer
advised were required to 33 – 43 Moorhouse
Avenue. This included repairs
to the northern external wall at 41 Moorhouse Avenue, where sections of
block wall were replaced with
a timber framed wall. Correspondence on
Vero’s claims file shows that this work was intended to be a permanent
replacement
of the block wall. The nature of the replacement wall was as
requested by the owner, with involvement from Structex, and the scope
of work
was agreed by MWH on Vero’s behalf. The work was done by Josephs
Builders, who discussed the work to be done with
Peter Dennis. ... Vero
paid $10,865.52 (incl GST) for this work ... Vero considers it has met its
obligations in relation to the
earthquake damage to this wall.
- [68] Mr Allott
referred to email correspondence discussing and agreeing on arrangements for the
repair. In particular, he referred
to an email on 18 May 2012 from Michael Kean
at Vero to Adam Walker at Structex, which says:
We have decided to
deconstruct and permanently replace the blockwall with a hardie board type
construction at the request of the owner.
Could you please contact the owner
(Peter Dennis) ... to confirm the type of construction he would like so you can
then detail it
for Joseph builders.
- [69] Mr Allott
was not cross-examined in relation to this (or his other evidence).
- [70] Mr Dennis,
the director of Moorhouse, was cross-examined in relation to the wall’s
repair and the sentence in the email
referring to the permanent replacement of
the wall. This exchange occurred:
- Do
you accept that it’s at your – at the owner’s request that
this wall was deconstructed and permanently replaced
with the block wall –
with the Hardie –
- I
think my statement or comments were at the time were you’re wasting
various money if you’re doing a temporary repair.
My preference is I
can’t see any reason why we can’t end up with a permanent solution.
And there are emails to that
effect.
- And
that’s then what happened, isn’t it?
- What’s
that?
- And
that’s what then happened?
- That’s
what was engaged. The architectural detailing came from the Buchan
Group.
- [71] In closing
submissions in the High Court, counsel for Moorhouse submitted Moorhouse was
still entitled to a repair scope which
provided for a “like for
like” replacement because:
(a) the walls as repaired were not as durable and impact resistant as concrete
block walls;
(b) the email reference to “permanent” replacement came from
Vero’s consultants and did not support a finding that
Moorhouse had
accepted the repairs were permanent; and
(c) there was other documentary evidence (including a subsequent tax invoice)
which described the works as “Temporary Works”.
- [72] The Judge
was nevertheless satisfied on the totality of the correspondence and Mr
Dennis’s evidence in cross-examination
that Moorhouse and its agents
represented to Vero that the work was to be a permanent replacement and that
Vero agreed to pay for
it on that
basis.[41] The Judge found although
it was not a like for like replacement, Moorhouse was not now able to resile
from its acceptance at the
time that the proposed replacement would constitute a
permanent repair.[42] Vero was
therefore entitled to exclude further work on the wall from the repair
scope.
- [73] Mr Bayley,
who addressed Moorhouse’s appeal submissions on this point, accepted that
Moorhouse “evidently wanted
a permanent repair” and submitted the
evidence had not established that Moorhouse made an “informed and
unequivocal decision
to compromise or waive its policy entitlement”. Mr
Bayley also noted Vero had not pleaded there had been a compromise of the
policy
entitlement.
- [74] We consider
the Judge correctly concluded Moorhouse was not entitled to include the cost of
any further repair of the wall in
the repair scope.
- [75] First,
there is nothing in the pleading point. Whether the cost of any further repair
to the wall should be included in Moorhouse’s
repair scope was in issue at
the trial and Mr Allott’s previously served brief had clearly set out
Vero’s evidence with
specific reference to the discussions as to the 2012
wall repair.
- [76] The second
point is that “like for like” is not the Policy standard. The
Policy standard is that the repair had
to restore the Buildings to a condition
substantially the same as, but not better or more extensive than its condition
when new.
That includes both functional and aesthetic elements. The fact that
it is not identical to what was there before does not mean
it has not met the
Policy standard.
- [77] Finally,
the Judge effectively concluded there had been a meeting of minds on the repair
that was to be undertaken, and the materials
that were to be used. That was the
only reasonable conclusion available once Mr Dennis gave his answers in
cross‑examination.
Mr Dennis opted for a permanent, rather than a
temporary repair, and Mr Kean’s email clearly identifies that was his
(Vero’s)
understanding of Mr Dennis’s request.
- [78] It may be
doubted whether this meeting of minds would meet the requirements for accord and
satisfaction. It might, however,
amount to estoppel in the sense that Moorhouse
cannot now, in good conscience, contend that Vero must demolish this work and
start
again simply because it now says the new walls are not as durable and
impact resistant as concrete block walls.
- [79] But, in any
event, we consider the engagement between the parties, in the context of what
was intended to be a final repair,
informs whether that repair meets the
“substantially as new” standard. That is because it is good
evidence going to
whether in both functional and aesthetic terms it is
substantially the same as new. The suggestion, now, that the repair is not
as
durable and impact resistant as a concrete block wall, was not raised at the
time.
- [80] The
photographic evidence shows that the walls are of the same appearance. They
also perform the same function. They are to
an “as new” standard.
The fact that more modern and lightweight materials have been used in the
reconstruction does
not mean that they are not substantially the same as new.
More modern and lightweight walls may have some advantages over solid
walls. If
this particular building was rebuilt today, it may well be that this is the
material that would be used. We consider
that any differences exist within a
margin of appreciation that the insurer and insured can be expected to address
and agree upon
at the time, and that this is what the parties did here.
- [81] For these
reasons we do not accept Moorhouse’s arguments in relation to these infill
panels.
Southern and eastern exterior walls at 41 Moorhouse
Avenue
- [82] Moorhouse
also claimed for replacement of the southern and eastern exterior walls at 41
Moorhouse Avenue. In April 2019, two
sections of the eastern exterior wall were
demolished and replaced with lightweight cladding.
- [83] Vero has
scoped to replace two infill panels at the southern exterior wall and two infill
panels at the eastern exterior wall
with filled 150 series block panels.
Moorhouse submits that 200 series block is necessary. Using 200 series block
would necessitate
additional works to the foundations of the building due to the
increased weight of the walls.
- [84] It appears
that 200 series blocks are now more commonly used by the building industry. The
Judge found that use of 150 series
blocks was nevertheless appropriate and met
current building standards.[43] The
Judge found that the consequential differences in wall width resulting in an
internal setback could be addressed by lining and
strapping.[44]
- [85] We consider
that this is the kind of matter that can be expected to be accommodated in
discussions between the insured and the
insurer at the time the work is
undertaken. Such discussions are relevant to establishing whether the Policy
standard has been met.
The Policy standard does not require the repair to be
identical, only that it restores the building substantially to an as new
condition.
We do not consider that Moorhouse has demonstrated that this
standard has not been met simply because of this difference in the
size of
blocks used. They are substantially the same in terms of functionality and
aesthetics with the lining and strapping proposed.
We do not consider that
Moorhouse can insist on the use of 200 series blocks given the implications for
the foundations of the building.
This is not necessary to restore this element
to the “substantially as new” standard.
- [86] Accordingly,
we consider that the High Court Judge was correct to conclude that Vero’s
scoping using 150 series blocks
was appropriate.
Inter-tenancy
walls at 33–35 Moorhouse Avenue
- [87] The
inter-tenancy walls between the buildings at 33 and 35 Moorhouse Avenue were, at
the time of the 4 September 2010 earthquake,
wholly constructed of infilled 150
series block. Cunningham Lindsey, loss adjusters, were appointed to assess the
damage caused
in September 2010 (and later). They reported the top layer of
blocks on the inter-tenancy wall had fallen out of position and caused
damage to
surrounding areas.
- [88] Moorhouse’s
property manager, Steven Marshall, managed arrangements for the needed repairs
and it was he who engaged Hawkins
as the builder. As the wall was a firewall,
specifications were obtained from Powell Fenwick for the repair of the damage.
The
upper portion of the wall was to be demolished and reconstructed with a
timber framing and GIB Fyreline. The 22 February 2011 earthquake
caused some
further damage. Cunningham Lindsey in April 2011 provided a further report into
fresh damage. They summarised what
had happened and to the inter-tenancy wall
to date:
The original firewall was concrete block. The insured had
an engineer inspect and was advised that the damaged and weakened area
of the
concrete block fire wall should be removed and replaced with timber framing and
double layered gib on each side of the fire
wall. This work was completed prior
to our inspection. The property manager advised that the removal of the wall
was approximately
$7,000.00 and we have included the removal in our estimate.
We also included the replacement of the wall as recommended by the engineer
and
has been completed. The property manager advised that he has not received an
invoice for the replacement of the firewall; therefore,
we have used standard
pricing for replacement. The fallen area of concrete firewall fell through the
suspended ceiling in the storeroom,
the gib ceiling in the kitchen and also
caused damage to the bathroom ceiling. We also noted minor cracking in the
mortar of the
concrete block walls in the storeroom, bathroom and bike repair
area.
- [89] Moorhouse’s
engineer, referred to in that summary, was Wilton Joubert Ltd. The repair they
had recommended involved removing
the blocks from the mezzanine level
upwards.
- [90] Cunningham
Lindsey estimated the total cost to be around $42,530.32 (excluding GST). In
their report, they explained the relationship
of the further damage to the
earlier damage:
We have reviewed the prior estimate for [damage]
from 4 September 2010 which includes much of the same damage. However, the
amount
included for the replacement of the firewall was much less than has been
done and the total amount of suspended ceiling was less
than what is now
damaged. Our enclosed estimate includes only new damages based on our
inspection with the property manager and
our review of the prior estimate. The
insured has now hired Hawkins, whom we met with during our inspection, to
[effect] repairs.
- [91] The repairs
effected by Hawkins totalled $57,804.74 (including GST), which includes the
costs incurred with Wilton Joubert and
Powell Fenwick. Vero paid those costs in
2011.
- [92] Mr Allott
explained Vero’s understanding thus:
- I
understand that Moorhouse now includes in its claim in the proceeding costs to
replace this section of firewall again, this time
with concrete block. Vero
does not consider it is obliged to pay to replace this section of wall again.
Vero was not advised at
the time that it paid for the Hawkins work that the
replacement wall was intended as a temporary rather than a permanent
reinstatement,
nor is there any record of Vero being asked whether it would
agree to fund both a temporary replacement of the wall and then a permanent
replacement. Vero is not aware of any reason why the 2011 replaced wall is
unsatisfactory as a permanent fire wall. The information
available to Vero
demonstrates that the wall replacement was arranged by Moorhouse to the
specification of its engineer, and the
work was paid for by Vero on the
understanding that the cost incurred was for the repair of earthquake damage.
Vero considers that
it has already met its obligations in respect of the
earthquake damage to the firewall.
- [93] Mr Allott
was not cross-examined in relation to this evidence.
- [94] Mr Dennis
was cross-examined in relation to the repair. He described
Wilton Joubert’s recommendation as a “make
safe”.
- [95] Mr Dennis
was also cross-examined in relation to Mr Allott’s evidence, through this
exchange:
- You
know that Vero says it wasn’t told that this replacement was intended to
be a temporary replacement and so wasn’t
asked and so just pausing there,
do you accept that?
A. If that’s a statement I must
accept it, but I remember –
Q. Do you accept that Vero was not told?
A. Sorry?
- Do
you accept that Vero was not told to your knowledge that this replacement was
intended to be temporary?
- From
the information I have on hand I believe that Vero had the information, they
didn’t digest it. So what did stick in my
head is the property manager
was absolutely chastised, how did the conversation go: “We don’t
have an association with
Hawkins, we don’t know what they’re doing
there, you need to be dealing with” and I think that’s when it
was
swung away from Hawkins through to being supported by MWH Mainzeal at the time.
As I said I’d need to go through the information
I have to support this
statement but that’s my understanding. The reports, I think an email from
Knight Frank directed me
to that.
- [96] Neither Mr
Dennis nor counsel for Moorhouse pointed to any information which recorded the
repair was intended to be temporary.
Accordingly, Mr Allott’s assertion
that Vero was not told the repair was intended to be temporary has not been
contradicted
in the evidence.
- [97] The reports
commissioned by Moorhouse were initially written in the context of ensuring safe
entry to the properties. The evidence
at trial identified the relevant parts of
the buildings were untenanted at the time of the earthquakes. The repair
reports contained
a specific recommendation that the walls be removed from
mezzanine level upwards and replaced with the timber-frame. Wilton Joubert
recorded they could assist in construction specifications. Other evidence
indicates Wilton Joubert then had that role. There is
nothing in the Wilton
Joubert reports to indicate, as Mr Dennis apparently understood, that Wilton
Joubert were simply recommending
a “make safe” repair. There was no
evidence to indicate Moorhouse has, since 2011, effected any material alteration
to the walls as repaired in accordance with Wilton Joubert’s design.
- [98] The repair
to the inter-tenancy walls between 33 and 35 Moorhouse Avenue was not the
subject of a discussion about permanent
replacement, as had occurred in relation
to 41 Moorhouse Avenue.
- [99] At trial,
Moorhouse asserted it was entitled, in relation to the inter-tenancy wall (as
well as the northern wall of 41 Moorhouse
Avenue), to a further replacement, as
that would achieve a like for like repair. Moorhouse’s evidence costed
the proposed
replacement of the wall in block masonry at $40,800 (exclusive of
GST).
- [100] The Judge
found Moorhouse was not entitled to the further repair of the wall in block
masonry. She
recorded:[45]
[149] As
with any contract, an insured party is able to agree with an insurer to have
repairs effected and paid for in a manner other
than a “like for
like” fashion. In this case, the repair which Moorhouse implemented is a
properly finished repair that
repairs the wall to an “as new
standard”, albeit in different materials from the original. While the
materials differ
from the lower half of the wall, this is not unusual in this
building which was developed in stages using a range of construction
materials.
[150] In my view, Vero was entitled to conclude that by paying for the
reinstatement undertaken by Moorhouse, it had discharged its
obligation to
repair this section of the building. Mr Dennis accepted in cross-examination
that Vero wasn’t told that this
replacement was intended to be a temporary
replacement, although he says he subsequently “chastised” the
property manager
for authorising Hawkins to do this. However, whatever was
occurring internally within Moorhouse does not change the fact that, from
Vero’s perspective, Moorhouse asked for the wall to be repaired in this
way and Vero agreed, and made payment. That is reflected
in Vero’s
pleadings. Clearly, had Vero known Moorhouse was reserving its position to have
the wall reinstated in block, it
would have resisted paying for works which were
obviously more sophisticated than a temporary repair.
[151] For these reasons, I do not consider Moorhouse has substantiated its
claim that these were simply temporary works to make it
safe or suitable for
continued use and, therefore it cannot claim an almost equivalent cost ($40,800
plus GST) to subsequently reinstate
it in block. It agreed to a repair that
restored the building to a when new condition, albeit in different materials
from the original.
This aspect of Moorhouse’s claim is rejected.
- [101] Accordingly,
the Judge did not consider the competing claims about the scope of works
appropriate to reinstate the wall.
- [102] For
Moorhouse, Mr Bayley submitted the Judge incorrectly concluded the inter-tenancy
wall repairs did not constitute temporary
repair (for which Moorhouse had cover
under the policy). Mr Bayley noted Moorhouse was not under an obligation to
clarify for Vero
the policy entitlement. He submitted it was incumbent on Vero
to secure from Moorhouse an unequivocal release of Moorhouse’s
entitlements to a like for like repair. As Vero did not do so, he submitted,
Moorhouse was entitled to the approval of the repair
scope which provided for
the wall to be “permanently rebuilt”.
- [103] The
central premise of Moorhouse’s case in relation to this repair is that the
2011 repair was not a like for like replacement.
But that is not the Policy
standard. What Moorhouse had designed through Powell Fenwick and Wilton
Joubert, and then had constructed
by Hawkins, was a repaired wall to an
“as new” standard. The cost of that repair, representing the
greater part of the
$57,804.66 (exclusive of GST) met by Vero in 2011, can be
compared with the $40,800 (exclusive of GST) put forward by Moorhouse at
the
time of the 2022 trial as the cost of what it proposed as a
“permanent” repair (some 11 years later).
- [104] This was
not a situation where the insurer was, in 2011, being asked for prior approval
to undertake modest repair works. In
2011, the insurer was asked, after the
event of design and construction carried out by the insured, to cover the cost
of an expensive
repair to an “as new” condition.
- [105] We
consider that the Judge was correct to conclude that this repair work met the
Policy standard. This is not a situation where
there has been accord and
satisfaction, or an estoppel. To the extent that the Judge concluded that it
was we do not agree. But
the engagements between Vero and Moorhouse over
precisely what repair work was to be undertaken are relevant to assessing
whether
the substantially the same as new standard has been met. The repair has
been undertaken using modern materials. They are not exactly
the same materials
as the initial construction. But that does not mean that the wall has not been
restored to substantially the
same condition as new. Aesthetically and
functionally it is effectively the same. Any argument that could be mounted
about this
now was not advanced at the time, and may just amount to a matter of
perspective. We do not accept that Moorhouse has established
that the Policy
standard has not been met by the work the parties earlier agreed upon.
- [106] For these
reasons Moorhouse’s allegations in relation to this inter-tenancy wall are
dismissed.
The east wall at 43 Moorhouse Avenue
- [107] The
remaining issues in dispute about particular repairs do not raise any issue
about temporary repairs. Rather, they turn
on whether Vero’s repair meets
the Policy standard.
- [108] The Judge
upheld Vero’s argument concerning the east wall of 43 Moorhouse
Avenue.[46] The east wall of 43
Moorhouse Avenue is approximately 100 mm from the neighbouring building. It is
approximately 32 metres long,
constructed of second‑hand pre-cast concrete
panels. As a result, most of the external wall cannot be observed and access
for any repairs is practically impossible.
- [109] There was
earthquake cracking to this wall observed on the interior. It is not possible
to inspect the exterior for cracking
apart from a limited inspection by a
camera. Given the cracking to the interior wall, cracking to the exterior wall
is likely.
It was not disputed that the cracking could be properly repaired by
epoxy injection — lost stiffness was not an issue with
this wall. But
Moorhouse contends that Vero’s epoxy repair solution does not meet the
Policy standard as the likely cracking
to the external wall will not be fully
repaired. First, because there may have been external cracking that did not
make its way
through to the internal wall and therefore will not be filled with
epoxy. Secondly, because the repair to the cracks will not be
properly finished
on the external wall. Moorhouse says that the entire wall needs to be replaced.
This will have implications for
the rest of the building given the structural
role of the wall.
- [110] Mr
Walker’s evidence was the cracking on the inside would not necessarily
match the cracking on the outside, and Ms Stanway
said that in her experience
with 150 mm thick panels the cracks do not match from front to back, and they
have different crack patterns.
Moorhouse criticises the Judge’s reliance
on the evidence of Mr Peter Higgins, a Regional Manager at a company that
carries
out specialist concrete crack injection repair work, that the relative
thinness of the walls would mean the cracks would likely travel
right through,
and as long as there is a visible crack of at least 0.2 mm on the interior
face, the crack would be appropriately
filled. Moorhouse also argues that
cracking ought to be sealed on both sides of the wall to be a proper repair to
the Policy standard.
- [111] We accept
Moorhouse’s argument that, notwithstanding Mr Higgins’ evidence
relied upon by the Judge, it established
that there will likely be cracking
damage to the exterior of the wall that will not be fully repaired by the epoxy
repair solution.
We accept that, on the balance of probabilities, there will
likely be cracks on the exterior wall that do not fully correspond to
the cracks
on the interior wall. That will never be known for sure as inspecting the
exterior wall is not feasible. We also accept
that the repairs will not be able
to be properly finished on the outside.
- [112] However,
we consider, on balance, that Vero’s repair strategy nevertheless meets
the Policy standard. The appropriate
repair can be done to the cracking to the
wall as the cracks appear from the inside, and there is no complaint about the
repair to
the damage visible to the internal wall. Some external cracks that do
not appear on the inside will not be repaired, and we also
accept the cracking
repair will not be properly finished on the outside in the sense that they will
not meet normal trade standards.
But this does not mean that they do not meet
the Policy standards. It does not mean that the wall will not have fully
restored
functionality to an as new standard.
- [113] As
indicated, it was not suggested that there was any damage to the structural
integrity of this wall through loss of stiffness
arising from the cracking. The
fact that the repair is not properly finished on the outside has aesthetic
implications. But those
implications are not material precisely because that
side of the wall will not be seen. What remains is the potential that the
unfinished
repair, or external cracking that has not been repaired, will have
implications over time that adversely affects the functionality
of the wall in
some way, for example by leaks developing through fine cracks. But
Moorhouse’s evidence did not establish this
simply because of the likely
existence of unfinished or untreated cracks. Finishing might normally be
required to do what might
be called a “proper job”, but there is no
evidence that this has implications for the integrity of the repair. These
implications will again only likely be aesthetic. Neither do we accept that the
lack of an applicator’s warranty means that
the Policy standard will not
be met.
- [114] In the
absence of Moorhouse having evidence that these limitations of the repair have
actual effects on the functionality of
the wall, including over time, we do not
accept that Moorhouse proved that Vero’s epoxy repair solution does not
meet the Policy
standard.
Suspended first floor slab
- [115] The first
floor of 43 Moorhouse Avenue is concrete and suspended. After the earthquakes,
cracks were identified. There was
a dispute at trial about whether those cracks
were caused by the earthquakes or were pre-existing arising from shrinkage after
construction.
But in cross-examination, Dr Brooke accepted that some of the
cracks to the floor were probably caused by the earthquakes. There
was also
some dispute as to what reinforcing had been used in the floor slab.
- [116] Ms Stanway
gave evidence that the crack widths were highly indicative of reinforcement
damage, and that as soon as there had
been yield in the reinforcing there was
likely loss of strength capacity. Ms Stanway considered that the floor needed
to be replaced.
Again, that would have implications for other parts of the
building, and in terms of the requirement for a building consent. When
she gave
evidence, however, Ms Stanway said she had reached her conclusions “on the
balance of the probabilities” and
elaborated on this by saying “I
have come to it on the balance of probabilities that you’re unable to rule
out damage
to the reinforcements”. Given that, we do not consider that
the Judge can be criticised in making the following
findings:[47]
[194]
Regardless of what type of reinforcing there was, Moorhouse needed to prove, on
the balance of probabilities, that there was
damage to the reinforcement which
was caused by earthquake shaking and which warranted the floor being scoped for
replacement. This
was not established by Moorhouse’s experts simply
asserting that they could not rule out the possibility of damage to reinforcing.
On the contrary, it was for Moorhouse to satisfy me that there had been damage
to the reinforcing that affected the performance or
structural integrity of the
floor.
- [117] We also
agree with the Judge’s further finding that significance could not be
placed on hearsay statements that this floor
was “lively” after the
earthquakes.[48] This could not be
properly taken into account in the absence of any evidence from witnesses who
made such observations.
- [118] We do not
accept Moorhouse’s submissions that there had been a level of agreement
between the experts that there had been
damage because Ms Stanway’s
evidence was consistent with an earlier report from an expert who was not
called. Dr Brooke’s
evidence was that there had been no damage to
the reinforcing steel, and any movement of the steel did not cause damage.
- [119] Neither do
we accept the criticism that Dr Brooke provided no adequate foundation for this
view. The finding of the Judge was
based on the conclusion that Moorhouse had
not proved this damage had occurred. It was not for Vero to disprove damage
through some
robust test or other technique conducted by Dr Brooke. It was for
Moorhouse to prove it by such techniques. Such damage was not
established by Ms
Stanway’s opinions alone. Having reviewed the evidence on appeal, we are
not satisfied that the Judge’s
conclusions were wrong.
- [120] We
accordingly do not accept this aspect of Moorhouse’s
appeal.
Building consent
- [121] The
Building Act 2004 requires building work to be carried out in accordance with a
building consent, unless the work falls within the provisions in sch
1 of that
Act.[49] The requirement for a
building consent triggers certain requirements, including that the building be
seismically strengthened to
34 per cent of the New Building Standard, as
well as other requirements, such as fire
standards.[50]
- [122] The Judge
accepted Vero’s arguments that its repair strategy did not require a
building consent as the work fell within
the exemptions in sch 1. This
relevantly provides:
Part 1
Exempted building work
General
1 General repair, maintenance, and replacement
(1) The repair and maintenance of a building product or an assembly
incorporated in or associated with a building, provided that
a comparable
building product or assembly is used.
(2) Replacement of a building product or an assembly incorporated in or
associated with a building, provided that—
(a) a comparable building product or assembly is used; and
(b) the replacement is in the same position.
(3) However, subclauses (1) and (2) do not include the following building
work:
(a) complete or substantial replacement of a specified system; or
(b) complete or substantial replacement of a building product or an assembly
contributing to the building’s structural behaviour
or fire-safety
properties; or
...
- [123] Moorhouse
criticises the Judge’s findings. First, it is argued that such a
determination by the Judge was inappropriate
in the absence of Vero seeking a
declaration that no such consent was required, and without the consenting
authority, the Council,
being heard.
- [124] We do not
accept this argument. Vero could have sought a declaration, but it was not
obliged to. It was able to put in issue
the need to obtain a building consent
in other ways, and it did so by contending that its proposed repair scope did
not require a
building consent. The Judge appropriately addressed that issue as
part of the claim. Moorhouse knew that was in issue, and called
evidence itself
on the question. So, there was no procedural unfairness in the Court addressing
the issue.
- [125] In oral
submissions, Mr Bayley also challenged the findings of the Judge in relation to
each of the building repairs under Vero’s
scope of repairs that were said
to give rise to a need for a building
consent.[51] We address those
elements in turn.
- [126] In
relation to new roof cladding, Mr Walker gave evidence that this would affect
the weathertightness of the building and therefore
the work would require a
consent. Mr Tolley, an experienced building surveyor, gave evidence that
the work fell within cl 1(2) as
it was a replacement with a comparable material
or component. We agree with the conclusion of the Judge that the exemption
applies,
and that there will be no change to the weathertightness as a result of
the work.[52] The fact that a
replacement could theoretically affect weathertightness does not mean that the
exemption does not apply. If it
did, any repair to the external roofing or
cladding of a building would require a consent. The material questions are
whether a
comparable building product is being used, whether it is in the same
position, and whether it was a complete replacement of a system.
We are
satisfied that the relevant requirements to exclude the requirement for building
consent were met.
- [127] In
relation to the epoxy crack injection repairs, Mr Walker gave evidence that they
would require consent because the repair
did not use comparable material,
although the Council may be prepared to grant an exemption under its power to do
so. Both Dr Brooke
and Mr Tolley gave evidence that a consent would not be
required as it qualified under cl 1(1) as a repair with comparable material.
We
agree with the High Court’s conclusion that the exemption
applied.[53] As the Judge found,
the extent of the epoxy injection was not great given the size of the building,
and it simply repairs and rebonds
cracking within the existing building
material.[54] In that sense, no new
building material is used at all. It simply restores the existing concrete
construction to its pre-earthquake
state by a repair.
- [128] In
relation to the block infill panels at 41 Moorhouse Avenue,
Mr Walker’s evidence was that they would not be exempt
because the
wall contributed substantially to the structural behaviour of the building. We
agree with the Judge that they fall within
the exemption as the repairs involve
comparable materials, do not involve a complete or substantial replacement under
cl 1(3)(a)
because the repair comprises less than 50 per cent of the wall, and
they do not contribute to the building’s structural behaviour
given Dr
Brooke’s evidence that the wall could be removed and replaced without any
appreciable impact on the
building.[55]
- [129] In
reaching these conclusions, we do not place particular weight on a 2012 email
from the Council concerning epoxy repairs,
or the MBIE determinations referred
to in argument, notwithstanding that the MBIE determinations in particular have
relevance. In
the end, the questions involve the application of the provisions
in the schedule to the Building Act in light of the facts, and we consider it
preferable to have directly addressed the relevant questions.
- [130] Neither do
we place significance on the evidence of Mr Walker concerning his meeting with
the Council on 13 May 2019. This
suggested that the Council would not grant an
exemption for epoxy crack injection at 33 to 43 Moorhouse Avenue because of its
earthquake
prone status. But there would only be a need for such an exemption
if there is a requirement for a building consent in the first
place. We do not
consider such a consent is required given the factual position. In that
context, we have agreed with the findings
of the High Court that there is no
underlying damage to the structural integrity of the building that this repair
is addressing,
including from a lack of a reduction in stiffness. We also do
not read the notes of the meeting with the Council as being definitive.
- [131] For these
reasons, we uphold the findings of the High Court in relation to building
consent.
Other issues
- [132] There are
other issues to address to resolve the appeal and
cross-appeal.
Indemnity value: Vero’s cross-appeal
- [133] In its
cross-appeal, Vero challenges the High Court determination that the indemnity
value entitlement of Moorhouse could exceed
the calculations of the depreciated
replacement costs calculated by its expert property valuer, Mr Stanley. The
Judge concluded
that Moorhouse’s entitlement was specifically defined
under the Policy by reference to the reinstatement cost of the property
less due
allowance for depreciation and deferred maintenance, and that this definition
would prevail whether or not it exceeded Mr
Stanley’s
calculations.[56]
- [134] In
advancing the cross-appeal, Vero accepted that the cross-appeal would have no
practical effect and would not require determination
if the Court upheld the
High Court’s determination concerning Vero’s scope of repairs.
Moorhouse contended that the
cross-appeal lacked a jurisdictional basis because
Vero did not seek any declaration concerning the measure of indemnity in the
High
Court.
- [135] Given the
stance of the parties, and our findings above, we accordingly do not address the
cross-appeal.
Indemnity value: Moorhouse’s appeal
- [136] The
position is different with respect to Moorhouse’s appeal. Moorhouse
criticises aspects of the Judge’s analysis
in relation to indemnity value.
In particular, Moorhouse criticises her finding that the parties had not sought
a declaration in
the pleadings on what should be considered as part of
depreciation, in determining the indemnity value. As Mr Rennie submitted,
Moorhouse did seek such a declaration through its claim for “modified
relief” in the closing address. A further reformulation
of the
declarations sought was provided to us.
- [137] We agree
with Moorhouse’s submission, accepted by the Judge, that the position here
is distinguishable from that addressed
in Prattley Enterprises Ltd v Vero
Insurance New Zealand Ltd.[57]
In Prattley, there was no clause that prescribed how to assess the
indemnity value, so the insured’s entitlement was assessed in accordance
with the underlying principle of insurance law that the insured be indemnified,
but not more than fully indemnified for their loss,
where economic
considerations were relevant. But here there was a clause, and it is the
meaning and effect of that clause that determines
Moorhouse’s entitlement.
- [138] We also
agree with the Judge that that entitlement is based on the cost of reinstating
the damaged property, less an allowance
for depreciation and deferred
maintenance.[58] In that context,
depreciation is referring to the physical life of the property, or part of a
property that is in issue. The clause
is not based on the market value of the
property. Moorhouse was not insured for the market value of the property, or
the leasehold
income. This was a material damage policy insuring the physical
buildings themselves from damage to those buildings. The indemnity
clause made
it clear it was the physical life of the asset, not its economic life that is
relevant in this case.
- [139] We also
agree that, given the physical attributes of a building will likely age at
different rates, with some components needing
to be replaced earlier than other
components, an “elemental” approach where different depreciation
rates are applied
to particular elements of the building may be appropriate.
These concepts were explained in SR International Business Insurance Co Ltd v
World Trade Centre Properties LLC by the United States District Court for
the Southern District of
New York.[59] They are also
referred to in the guidance issued by the New Zealand Institute of
Valuers.[60]
- [140] But we
nevertheless agree with Vero’s submission that it is not appropriate to
make declarations in this case. It is
not always necessary to have a genuine
dispute or lis before declarations are made by a
court.[61] But here there is a lis,
and the declaration should correspond to what is in dispute. There are factual
matters that will be relevant
to the appropriateness of the declaration. For
the reasons addressed above in relation to Vero’s cross-appeal, it may be
that
any dispute about the application of indemnity value principles is now
irrelevant given we have upheld the Judge’s view that
Vero’s scope
of repairs applies. To the extent that that is not so, what we have said above
can guide the parties.
Interest
- [141] Moorhouse
criticised the High Court’s conclusions in relation to interest. The
Court found that there were significant
delays in this proceeding and that they
were attributable to Moorhouse and did not award interest for some of the
period.[62]
- [142] Moorhouse’s
submissions were advanced on the basis that this was only relevant if its
arguments on the cost of repair
were accepted. We accordingly do not address
the issue.
- [143] However,
we observe that delay is relevant to the discretion to award interest under s 87
of the Judicature Act 1908, and there
is no reason to question the Judge’s
conclusions in relation to delay. But we also think that it may be generally
preferable
in cases involving an insurance entitlement for the consequences of
delay to be reflected in the interest rate being applied rather
than depriving a
successful party of interest for periods of time altogether. In the present
case, if Moorhouse had shown that Vero
was obliged to pay it under the Policy,
Vero would have been benefited from deferring its obligation. An interest rate
that compensated
for the time value of money, but no more, may still be
appropriate.[63]
Costs
- [144] Given our
conclusions as to the appeal and cross-appeal, we consider it is appropriate for
Vero to be awarded costs on the appeal
as they have been successful. Vero seeks
costs for a standard appeal on a band B basis. We agree that this is
appropriate.
- [145] There is
no award for costs on the cross-appeal given that it only needed to be
determined if Vero did not succeed on the appeal.
Result
- [146] The appeal
and cross-appeal are dismissed.
- [147] The
appellant must pay the respondent costs for a standard appeal on a band B
basis together with usual disbursements. We certify
for second counsel.
There is no award of costs on the
cross-appeal.
Solicitors:
Rhodes & Co,
Christchurch for Appellant
Fee Langstone, Auckland for Respondent
[1] Moorhouse Commercial Park
Ltd v Vero Insurance New Zealand Ltd [2022] NZHC 3260 [Judgment under
appeal].
[2] At [130]–[133],
[166]–[168], [185]–[187], [194]–[195], and [197].
[3] See, for example, TJK (NZ)
Ltd v Mitsui Sumitomo Insurance Co Ltd [2013] NZHC 298, which concerned a
similar provision in an insurance contract.
[4] Judgment under appeal, above n
1, at [120]–[143].
[5] Aktieselskabet de Danske
Sukkerfabrikker v Bajamar Compania Naviera SA [1983] 2 Lloyd’s
Rep 210 (QB) [the Torenia] at 215.
[6] Daubert v Merrell Dow
Pharmaceuticals Inc [1993] USSC 99; 509 US 579 (1993) at 593–594, adopted in
Lundy v R [2013] UKPC 28, [2014] 2 NZLR 273 [Lundy v R
(PC)] at [139]. See also Attorney-General v Strathboss Kiwfruit Ltd
[2020] NZCA 98, [2020] 3 NZLR 247 at [491]–[492], citing Lundy v R
(PC), above n 6; and Lundy v R
[2018] NZCA 410 [Lundy v R (CA)].
[7] Judgment under appeal, above n
1, at [37].
[8] Evaluation of Epoxy and FRP
Repair of Earthquake-damaged Concrete Structures (Simpson, Gumpertz
& Heger Inc, California, November 2014) [Hamburger Report] at
29–30.
[9] Judgment under appeal, above n
1, at [127].
[10] The Torenia, above n
5, at 215.
[11] At 215.
[12] See Dawson v Monarch
Insurance Co [1977] 1 NZLR 372 (SC) at 374, citing Bond Air Services Ltd
v Hill [1955] QB 417 at 426.
[13] Robert Merkin and Chris
Nicoll (eds) Colinvaux’s Law of Insurance in New Zealand (2nd ed,
Thomson Reuters, Wellington, 2017) at [4.8.2(4)].
[14] Myall v Tower Insurance
Ltd [2017] NZCA 561 at [20].
[15] At [22].
[16] Austin, Nichols & Co
Inc v Stichting Lodestar [2007] NZSC 103, [2008] 2 NZLR 141 at [16].
[17] He v Earthquake
Commission [2019] NZCA 373 (footnote omitted).
[18] Hamburger Report, above n
8, at 36.
[19] Judgment under appeal,
above n 1, at [131].
[20] At [129].
[21] At [127]–[133].
[22] At [131].
[23] At [127].
[24] At [131].
[25] At [127]. Yielding is the
further stage of damage when the reinforcing bars bend or yield.
[26] See, for example, Aizhen
Liu and Robert Park “Seismic Load Tests on Two Concrete Interior
Beam-Column Joints Reinforced by
Plain Round Bars Designed to Pre-1970s
Codes” (1998) 31(3) Bulletin of the New Zealand National Society for
Earthquake Engineering
164 at 164 notes that the “utilisation of plain
round bars [leads] to bond slip”.
[27] See Lundy v R (PC),
above n 6; Lundy v R (CA),
above n 6; and Attorney-General v
Strathboss Kiwifruit Ltd, above n 6.
[28] Lundy v R (PC),
above n 6, at [138]–[139]; and
Lundy v R (CA), above n 6.
[29] Attorney-General v
Strathboss Kiwifruit Ltd, above n 6, at [491]–[492] and [499].
[30] See, for example, Lundy
v R (CA), above n 6, at
[202]–[204], where the Court considered that one category of scientific
evidence was not a “novel technique”
so that the Daubert
criteria did not apply.
[31] See, for example, Lundy
v R (CA), above n 6, at
[241]–[242] and [248]; and Attorney-General v Strathboss Kiwifruit
Ltd, above n 6, at [499].
[32] Other than the potential of
destructive testing, which is not practicable.
[33] Kai Marder and others
“Quantifying the effects of epoxy repair of reinforced concrete plastic
hinges” (2020) 53(1) Bulletin
of the New Zealand Society for Earthquake
Engineering 37; Catherine French, Gregory Thorp, and Wen-Jen Tsai “Epoxy
Repair Techniques
for Moderate Earthquake Damage” ACI Structural Journal
(Technical Paper 87-S41, 1990); and Joseph Plecnik and others “Behavior
of
Epoxy Repaired Beams under Fire” J Struct Eng 112 (1986) 906.
[34] Judgment under appeal,
above n 1, at [135].
[35] Body Corporate 335089 v
Vero Insurance NZ Ltd [2020] NZHC 2353 at [57].
[36] A similar approach applies
for indemnity value, although this involves deductions for depreciation and
deferred maintenance.
[37] Judgment under appeal,
above n 1 (footnotes omitted).
[38] See, for example,
Prattley Enterprises Ltd v Vero Insurance New Zealand Ltd [2015] NZHC
1444 at [220]–[226]. Such an agreement would normally be evidenced by a
formal release/settlement agreement.
[39] Such an approach has not
yet been recognised in New Zealand, but see generally National
Westminster Finance NZ Ltd v National Bank of NZ Ltd [1996] 1 NZLR 548 (CA).
We note also that there may be considerable conceptual overlap with the doctrine
of waiver in this context,
see the discussion in Hugh G Beale (ed) Chitty on
Contracts (35th edition, Thomson Reuters, London, 2023) vol 1 at
[7-036].
[40] See [29] above.
[41] Judgment under appeal,
above n 1, at [155].
[42] At [156].
[43] At [161].
[44] At [163].
[45] Judgment under appeal,
above n 1.
[46] At [189].
[47] Judgment under appeal,
above n 1.
[48] At [195].
[49] Building Act 2004, ss 40
and 41(1)(b). Section 41 also provides for other circumstances in which a
building consent is not required.
[50] Sections 112 and 133AT.
[51] Judgment under appeal,
above n 1, at [208].
[52] At [210].
[53] At [211]–[212].
[54] At [212].
[55] At [213].
[56] At [231].
[57] At [225]–[226],
citing Prattley Enterprises Ltd v Vero Insurance New Zealand Ltd
[2016] NZSC 158, [2017] 1 NZLR 352.
[58] Judgment under appeal,
above n 1, at [226].
[59] SR International
Business Insurance Co Ltd v World Trade Centre Properties LLC 44 F Supp 2d
320 (SD NY 2006) at 347–348.
[60] Australian Property
Institute and others Valuations for Insurance Purposes (ANZVGP 104, June
2021) at [5.1].
[61] Mandic v Cornwall Park
Trust Board [2011] NZSC 135, [2012] 2 NZLR 194 at [9].
[62] Judgment under appeal,
above n 1, at [245]–[246].
[63] See Worldwide NZ LLC v
NZ Venue and Event Management [2014] NZSC 108, [2015] 1 NZLR 1 at [76].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2024/415.html