NZLII Home | Databases | WorldLII | Search | Feedback

Court of Appeal of New Zealand

You are here:  NZLII >> Databases >> Court of Appeal of New Zealand >> 2024 >> [2024] NZCA 415

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Moorhouse Commercial Park Limited v Vero Insurance New Zealand Limited [2024] NZCA 415 (3 September 2024)

Last Updated: 9 September 2024

IN THE COURT OF APPEAL OF NEW ZEALAND

I TE KŌTI PĪRA O AOTEAROA
CA37/2023
[2024] NZCA 415



BETWEEN

MOORHOUSE COMMERCIAL PARK LIMITED
Appellant


AND

VERO INSURANCE NEW ZEALAND LIMITED
Respondent

Hearing:

17-18 April 2024

Court:

Cooke, Moore and Osborne JJ

Counsel:

S P Rennie, J E Bayley and F H Scrase for Appellant
C M Brick and A R Cornwell for Respondent

Judgment:

3 September 2024 at 10.30 am


JUDGMENT OF THE COURT

  1. The appeal and cross-appeal are dismissed.
  2. The appellant must pay the respondent costs for a standard appeal on a band B basis together with usual disbursements. We certify for second counsel. There is no award of costs on the cross-appeal.

____________________________________________________________________

REASONS OF THE COURT

(Given by Cooke and Osborne JJ)

Table of Contents

Para No

Introduction [1]
Background [3]
The Policy [7]
Epoxy repair and bond loss [18]
Appellant’s arguments [23]
Analysis [28]
Particular repairs [54]
Relevant legal principles [55]
Northern exterior wall at 41 Moorhouse Avenue [64]
Southern or eastern exterior walls at 41 Moorhouse Avenue [82]
Inter-tenancy walls at 33–35 Moorhouse Avenue [87]
The east wall at 43 Moorhouse Avenue [107]
Suspended first floor slab [115]
Building consent [121]
Other issues [132]
Indemnity value: Vero’s cross-appeal [133]
Indemnity value: Moorhouse’s appeal [136]
Interest [141]
Costs [144]
Result [146]

Introduction

Background

The Policy

If, during the Period of Insurance, any:

then, subject to the terms, conditions and exclusions of this Policy, the Company will indemnify the Insured for the loss, damage and costs.

REINSTATEMENT

In the event of any Insured Property to which this Memorandum applies being lost, damaged or Destroyed, the basis on which the amount payable under this Policy is to be calculated will be the cost of Reinstatement of the property, subject to the special provisions of this Memorandum.

(a) “Reinstatement” means:

(i) where property is lost or Destroyed, its replacement by Equivalent Property;

(ii) where property is damaged but not Destroyed, the repair of the damage and the restoration of the damaged portion of the property to a condition substantially the same as, but not better or more extensive than, its condition when new, but incorporating such alterations as are necessary to comply with any Act of Parliament or Regulation.

(a) if the Insured elects not to Reinstate the property;

(b) if the work of Reinstatement is not commenced and carried out with reasonable despatch;

(c) until the cost of Reinstatement has actually been incurred, or agreed between the Company and the Insured.

Indemnity Value: The reinstatement cost of the property to a condition not better or more extensive than when new less due allowance for depreciation and deferred maintenance.

Epoxy repair and bond loss

Appellant’s arguments

Analysis

[7] [The plaintiff] bears the burden of making out his claim at trial and on appeal. In particular, the burden is on [the plaintiff] to establish that the house suffered damage caused by the Canterbury earthquakes. It is not sufficient for him to point to the (undisputed) dislevelment of the house’s floor, or to establish that it is possible that this might have been caused or contributed to by the earthquakes. He needs to show on the balance of probabilities that differential settlement of the house was caused or materially contributed to by the earthquakes.

[129] These issues are important because, as she said in her evidence, it was the inability to restore the bond between the reinforcement and the concrete which was the key reason for rejecting epoxy injection as a means to restore the concrete columns in most of the 33 – 41 Moorhouse Avenue building. If I am not satisfied on the balance of probabilities that such damage has occurred, her main reservation about the use of epoxy is addressed.

[132] Having reached the view that, on the balance of probabilities, there is no material damage to the reinforcement, nor is there debonding between it and the concrete, the primary concerns about the efficacy of epoxy to restore the stiffness of the building are eliminated. That accords with the conclusions in the Hamburger report (which Ms Stanway’s evidence endorses), which supports the use of epoxy repairs for minor or moderate concrete cracking but raises doubts about its use to repair significant damage, or to completely restore the bond between concrete and reinforcing steel, when that has been lost.

Particular repairs

Relevant legal principles

DEMOLITION, REMOVAL OF DEBRIS AND OTHER COSTS

This Policy extends to cover costs necessarily incurred for any of the following purposes in consequence of loss or damage covered by this Policy:

...

[82] The “when new” standard does not require exact replication of the original; modern materials and techniques may be used. The standard of repair required is to render the fact of earthquake damage immaterial. When deciding what standard of remediation is required by the policy, regard must also be had to the purpose of the damaged component. Where an item has a functional purpose only, then so long as the repair or replacement restores that functional purpose to a “when new” condition, the obligations under the policy will be met. Where the component also has an aesthetic purpose, the remediation strategy must restore the former aesthetic to a “when new” quality.

Northern exterior wall at 41 Moorhouse Avenue

We have decided to deconstruct and permanently replace the blockwall with a hardie board type construction at the request of the owner. Could you please contact the owner (Peter Dennis) ... to confirm the type of construction he would like so you can then detail it for Joseph builders.

(a) the walls as repaired were not as durable and impact resistant as concrete block walls;

(b) the email reference to “permanent” replacement came from Vero’s consultants and did not support a finding that Moorhouse had accepted the repairs were permanent; and

(c) there was other documentary evidence (including a subsequent tax invoice) which described the works as “Temporary Works”.

Southern and eastern exterior walls at 41 Moorhouse Avenue

Inter-tenancy walls at 33–35 Moorhouse Avenue

The original firewall was concrete block. The insured had an engineer inspect and was advised that the damaged and weakened area of the concrete block fire wall should be removed and replaced with timber framing and double layered gib on each side of the fire wall. This work was completed prior to our inspection. The property manager advised that the removal of the wall was approximately $7,000.00 and we have included the removal in our estimate. We also included the replacement of the wall as recommended by the engineer and has been completed. The property manager advised that he has not received an invoice for the replacement of the firewall; therefore, we have used standard pricing for replacement. The fallen area of concrete firewall fell through the suspended ceiling in the storeroom, the gib ceiling in the kitchen and also caused damage to the bathroom ceiling. We also noted minor cracking in the mortar of the concrete block walls in the storeroom, bathroom and bike repair area.

We have reviewed the prior estimate for [damage] from 4 September 2010 which includes much of the same damage. However, the amount included for the replacement of the firewall was much less than has been done and the total amount of suspended ceiling was less than what is now damaged. Our enclosed estimate includes only new damages based on our inspection with the property manager and our review of the prior estimate. The insured has now hired Hawkins, whom we met with during our inspection, to [effect] repairs.

A. If that’s a statement I must accept it, but I remember –

Q. Do you accept that Vero was not told?

A. Sorry?

  1. Do you accept that Vero was not told to your knowledge that this replacement was intended to be temporary?
  2. From the information I have on hand I believe that Vero had the information, they didn’t digest it. So what did stick in my head is the property manager was absolutely chastised, how did the conversation go: “We don’t have an association with Hawkins, we don’t know what they’re doing there, you need to be dealing with” and I think that’s when it was swung away from Hawkins through to being supported by MWH Mainzeal at the time. As I said I’d need to go through the information I have to support this statement but that’s my understanding. The reports, I think an email from Knight Frank directed me to that.

[149] As with any contract, an insured party is able to agree with an insurer to have repairs effected and paid for in a manner other than a “like for like” fashion. In this case, the repair which Moorhouse implemented is a properly finished repair that repairs the wall to an “as new standard”, albeit in different materials from the original. While the materials differ from the lower half of the wall, this is not unusual in this building which was developed in stages using a range of construction materials.

[150] In my view, Vero was entitled to conclude that by paying for the reinstatement undertaken by Moorhouse, it had discharged its obligation to repair this section of the building. Mr Dennis accepted in cross-examination that Vero wasn’t told that this replacement was intended to be a temporary replacement, although he says he subsequently “chastised” the property manager for authorising Hawkins to do this. However, whatever was occurring internally within Moorhouse does not change the fact that, from Vero’s perspective, Moorhouse asked for the wall to be repaired in this way and Vero agreed, and made payment. That is reflected in Vero’s pleadings. Clearly, had Vero known Moorhouse was reserving its position to have the wall reinstated in block, it would have resisted paying for works which were obviously more sophisticated than a temporary repair.

[151] For these reasons, I do not consider Moorhouse has substantiated its claim that these were simply temporary works to make it safe or suitable for continued use and, therefore it cannot claim an almost equivalent cost ($40,800 plus GST) to subsequently reinstate it in block. It agreed to a repair that restored the building to a when new condition, albeit in different materials from the original. This aspect of Moorhouse’s claim is rejected.

The east wall at 43 Moorhouse Avenue

Suspended first floor slab

[194] Regardless of what type of reinforcing there was, Moorhouse needed to prove, on the balance of probabilities, that there was damage to the reinforcement which was caused by earthquake shaking and which warranted the floor being scoped for replacement. This was not established by Moorhouse’s experts simply asserting that they could not rule out the possibility of damage to reinforcing. On the contrary, it was for Moorhouse to satisfy me that there had been damage to the reinforcing that affected the performance or structural integrity of the floor.

Building consent

Part 1

Exempted building work

General

1 General repair, maintenance, and replacement

(1) The repair and maintenance of a building product or an assembly incorporated in or associated with a building, provided that a comparable building product or assembly is used.

(2) Replacement of a building product or an assembly incorporated in or associated with a building, provided that—

(a) a comparable building product or assembly is used; and

(b) the replacement is in the same position.

(3) However, subclauses (1) and (2) do not include the following building work:

(a) complete or substantial replacement of a specified system; or

(b) complete or substantial replacement of a building product or an assembly contributing to the building’s structural behaviour or fire-safety properties; or

...

Other issues

Indemnity value: Vero’s cross-appeal

Indemnity value: Moorhouse’s appeal

Interest

Costs

Result






Solicitors:
Rhodes & Co, Christchurch for Appellant
Fee Langstone, Auckland for Respondent


[1] Moorhouse Commercial Park Ltd v Vero Insurance New Zealand Ltd [2022] NZHC 3260 [Judgment under appeal].

[2] At [130]–[133], [166]–[168], [185]–[187], [194]–[195], and [197].

[3] See, for example, TJK (NZ) Ltd v Mitsui Sumitomo Insurance Co Ltd [2013] NZHC 298, which concerned a similar provision in an insurance contract.

[4] Judgment under appeal, above n 1, at [120]–[143].

[5] Aktieselskabet de Danske Sukkerfabrikker v Bajamar Compania Naviera SA [1983] 2 Lloyd’s Rep 210 (QB) [the Torenia] at 215.

[6] Daubert v Merrell Dow Pharmaceuticals Inc [1993] USSC 99; 509 US 579 (1993) at 593–594, adopted in Lundy v R [2013] UKPC 28, [2014] 2 NZLR 273 [Lundy v R (PC)] at [139]. See also Attorney-General v Strathboss Kiwfruit Ltd [2020] NZCA 98, [2020] 3 NZLR 247 at [491]–[492], citing Lundy v R (PC), above n 6; and Lundy v R [2018] NZCA 410 [Lundy v R (CA)].

[7] Judgment under appeal, above n 1, at [37].

[8] Evaluation of Epoxy and FRP Repair of Earthquake-damaged Concrete Structures (Simpson, Gumpertz & Heger Inc, California, November 2014) [Hamburger Report] at 29–30.

[9] Judgment under appeal, above n 1, at [127].

[10] The Torenia, above n 5, at 215.

[11] At 215.

[12] See Dawson v Monarch Insurance Co [1977] 1 NZLR 372 (SC) at 374, citing Bond Air Services Ltd v Hill [1955] QB 417 at 426.

[13] Robert Merkin and Chris Nicoll (eds) Colinvaux’s Law of Insurance in New Zealand (2nd ed, Thomson Reuters, Wellington, 2017) at [4.8.2(4)].

[14] Myall v Tower Insurance Ltd [2017] NZCA 561 at [20].

[15] At [22].

[16] Austin, Nichols & Co Inc v Stichting Lodestar [2007] NZSC 103, [2008] 2 NZLR 141 at [16].

[17] He v Earthquake Commission [2019] NZCA 373 (footnote omitted).

[18] Hamburger Report, above n 8, at 36.

[19] Judgment under appeal, above n 1, at [131].

[20] At [129].

[21] At [127]–[133].

[22] At [131].

[23] At [127].

[24] At [131].

[25] At [127]. Yielding is the further stage of damage when the reinforcing bars bend or yield.

[26] See, for example, Aizhen Liu and Robert Park “Seismic Load Tests on Two Concrete Interior Beam-Column Joints Reinforced by Plain Round Bars Designed to Pre-1970s Codes” (1998) 31(3) Bulletin of the New Zealand National Society for Earthquake Engineering 164 at 164 notes that the “utilisation of plain round bars [leads] to bond slip”.

[27] See Lundy v R (PC), above n 6; Lundy v R (CA), above n 6; and Attorney-General v Strathboss Kiwifruit Ltd, above n 6.

[28] Lundy v R (PC), above n 6, at [138]–[139]; and Lundy v R (CA), above n 6.

[29] Attorney-General v Strathboss Kiwifruit Ltd, above n 6, at [491]–[492] and [499].

[30] See, for example, Lundy v R (CA), above n 6, at [202]–[204], where the Court considered that one category of scientific evidence was not a “novel technique” so that the Daubert criteria did not apply.

[31] See, for example, Lundy v R (CA), above n 6, at [241]–[242] and [248]; and Attorney-General v Strathboss Kiwifruit Ltd, above n 6, at [499].

[32] Other than the potential of destructive testing, which is not practicable.

[33] Kai Marder and others “Quantifying the effects of epoxy repair of reinforced concrete plastic hinges” (2020) 53(1) Bulletin of the New Zealand Society for Earthquake Engineering 37; Catherine French, Gregory Thorp, and Wen-Jen Tsai “Epoxy Repair Techniques for Moderate Earthquake Damage” ACI Structural Journal (Technical Paper 87-S41, 1990); and Joseph Plecnik and others “Behavior of Epoxy Repaired Beams under Fire” J Struct Eng 112 (1986) 906.

[34] Judgment under appeal, above n 1, at [135].

[35] Body Corporate 335089 v Vero Insurance NZ Ltd [2020] NZHC 2353 at [57].

[36] A similar approach applies for indemnity value, although this involves deductions for depreciation and deferred maintenance.

[37] Judgment under appeal, above n 1 (footnotes omitted).

[38] See, for example, Prattley Enterprises Ltd v Vero Insurance New Zealand Ltd [2015] NZHC 1444 at [220]–[226]. Such an agreement would normally be evidenced by a formal release/settlement agreement.

[39] Such an approach has not yet been recognised in New Zealand, but see generally National Westminster Finance NZ Ltd v National Bank of NZ Ltd [1996] 1 NZLR 548 (CA). We note also that there may be considerable conceptual overlap with the doctrine of waiver in this context, see the discussion in Hugh G Beale (ed) Chitty on Contracts (35th edition, Thomson Reuters, London, 2023) vol 1 at [7-036].

[40] See [29] above.

[41] Judgment under appeal, above n 1, at [155].

[42] At [156].

[43] At [161].

[44] At [163].

[45] Judgment under appeal, above n 1.

[46] At [189].

[47] Judgment under appeal, above n 1.

[48] At [195].

[49] Building Act 2004, ss 40 and 41(1)(b). Section 41 also provides for other circumstances in which a building consent is not required.

[50] Sections 112 and 133AT.

[51] Judgment under appeal, above n 1, at [208].

[52] At [210].

[53] At [211]–[212].

[54] At [212].

[55] At [213].

[56] At [231].

[57] At [225]–[226], citing Prattley Enterprises Ltd v Vero Insurance New Zealand Ltd [2016] NZSC 158, [2017] 1 NZLR 352.

[58] Judgment under appeal, above n 1, at [226].

[59] SR International Business Insurance Co Ltd v World Trade Centre Properties LLC 44 F Supp 2d 320 (SD NY 2006) at 347–348.

[60] Australian Property Institute and others Valuations for Insurance Purposes (ANZVGP 104, June 2021) at [5.1].

[61] Mandic v Cornwall Park Trust Board [2011] NZSC 135, [2012] 2 NZLR 194 at [9].

[62] Judgment under appeal, above n 1, at [245]–[246].

[63] See Worldwide NZ LLC v NZ Venue and Event Management [2014] NZSC 108, [2015] 1 NZLR 1 at [76].


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2024/415.html