You are here:
NZLII >>
Databases >>
Court of Appeal of New Zealand >>
2024 >>
[2024] NZCA 417
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Watson v Zhou [2024] NZCA 417 (4 September 2024)
Last Updated: 9 September 2024
|
IN THE COURT OF APPEAL OF NEW
ZEALANDI
TE KŌTI PĪRA O AOTEAROA
|
|
|
BETWEEN
|
ELIZABETH WATSON Appellant
|
|
AND
|
LEI ZHOU AND QIUYING ZHANG Respondents
|
Hearing:
|
17 June 2024
|
Court:
|
Cooke, Venning and van Bohemen JJ
|
Counsel:
|
D M Frandorfer for Appellant J T Wollerman and D A Fry and
Respondents
|
Judgment:
|
4 September 2024 at 10.30 am
|
JUDGMENT OF THE COURT
A The appeal is
allowed.
B The cross-appeal is allowed in part.
- The
proceedings are remitted to the High Court to address the further damages
arising from the respondents’ claim for breach
of warranty on the basis
outlined in paragraphs [100]–[101].
- The
costs of the appeal and cross-appeal are to lie where they
fall.
____________________________________________________________________
REASONS OF THE COURT
(Given by Cooke J)
Table of Contents
Para
No
Introduction [1]
Background [4]
Misrepresentation [13]
Analysis [17]
Mistake [29]
Arguments [30]
Analysis [37]
Conclusion [56]
Breach
of warranty [60]
Arguments [66]
Analysis [71]
(i) What damages were recoverable? [74]
(ii) The deck work [78]
(iii) The drainage work [80]
(iv) Was a consent required for the drainage work? [83]
(v) Damage caused by the breach [88]
Costs [102]
Conclusion [104]
Introduction
- [1] The
appellant, Mrs Watson, appeals from a decision of the High Court awarding the
respondents, Mr Zhou and Ms Zhang, $271,600
for mistake under the Contract and
Commercial Law Act 2017 (the CCLA) and $15,000 for breach of a vendor warranty
in relation to
the sale of a residential property on standard terms and
conditions.[1]
- [2] Mr Zhou and
Ms Zhang purchased the property from Mrs Watson. After settlement, they
discovered that the property suffered from
leaking issues. The High Court
held that there was a common mistake between the parties that the property was
sound and did not
leak,[2] and that
Mrs Watson was also liable for breach of warranty in connection with certain
work undertaken on the property which required
a consent which had not been
obtained.[3] Mrs Watson appeals
against the High Court’s finding of common mistake, and alternatively,
submits that the High Court erred
in assessing the quantum of relief for the
cause of action.
- [3] Mr Zhou and
Ms Zhang cross-appeal against the Court’s conclusion that there was no
oral misrepresentation, and in relation
to findings associated with the claim
for breach of contractual warranty.
Background
- [4] In 1969, Mrs
Elizabeth Watson and her late husband, Mr Alan Watson, purchased a section on
which a residential house was later
constructed. Mr and Mrs Watson had
undertaken various alterations and repairs to the property over the years.
- [5] In early
2020, Mr and Mrs Watson listed the property for sale through their real estate
agents, RedCoats Ltd. The selling agent
from RedCoats Ltd was Ms Christine
Kibblewhite. Ms Annie Liu also worked for RedCoats Ltd. She assisted
Mr Zhou and Ms Zhang with
a possible purchase of the property.
- [6] Mr Lei Zhou
(sometimes known as “Rocky”) and Ms Qiuying Zhang (sometimes known
as “Veronica”) were recent
immigrants to New Zealand.
In February 2020, they went to see the property which was being marketed
for sale. It was largely in
its original condition.
- [7] Mr Zhou and
Ms Zhang viewed the property on three occasions before making a purchase offer.
An important viewing took place on
10 February 2020. Ms Liu had arranged for a
builder, Mr Huang, to come along with Mr Zhou and Ms Zhang for that visit. Mr
and Mrs
Watson were both also present. At the time, Mr Watson was suffering
from dementia, and subsequent to the sale but prior to the High
Court hearing,
he died. Mrs Watson is in her 80s.
- [8] It is agreed
that there were some discussions about features of the property at the time of
this inspection. There is a dispute
whether there were particular statements
made by Mrs Watson about whether the house suffered from leaks or not. We will
address
this below.
- [9] Following
the inspection, Mr Huang advised Mr Zhou and Ms Zhang that “the property
looked to be in good condition”
and there was only minor wear to some
weatherboards and deck support that would require remediation. Mr Zhou and
Ms Zhang subsequently
decided to make an offer for the property, and they
decided to do so unconditionally on the standard ADLS/REINZ
terms.[4] After some brief
negotiations, the parties entered into the sale and purchase agreement on
13 February 2020 for $848,000 (the Agreement).
There was a
pre-settlement inspection on 18 March 2020 during which Mr Zhou and Ms Zhang
identified some minor issues with the property,
but these were not resolved.
Settlement proceeded in accordance with the Agreement on 19 March 2020.
- [10] Just over a
week after settlement, the property experienced substantial leaks during
rainfall. Cellphone videos were introduced
in evidence showing those leaks
occurring at the time. Mr Zhou and Ms Zhang then obtained a report from a
building specialist firm,
Check Home Ltd, which identified significant defects
and damage. Ms Zhang said that this suggested to her that the previous
owners
were likely aware of these issues. Subsequent expert advice was then
obtained.
- [11] The above
events gave rise to the claim against Mrs Watson. Three main causes of action
were advanced:
(a) misrepresentation (both orally and by concealment);
(b) common mistake;[5] and
(c) breach of warranty.
- [12] By a
judgment dated 24 August 2023, Gendall J dismissed the claim for
misrepresentation and upheld the claims for common mistake
and breach of
warranty.[6] In relation to mistake
he awarded $271,600 together with interest based on 70 per cent of the
difference in value between the property
in its damaged state and its value if
it had been in an undamaged state.[7]
He awarded $15,000 plus interest for breach of warranty representing the cost to
make one of the walls where leaking had occurred
compliant.[8]
Misrepresentation
- [13] We deal
first with the cross-appeal advanced by Mr Zhou and Ms Zhang in relation to the
Judge’s factual findings giving
rise to his dismissal of the claim for
misrepresentation.
- [14] Both Mr
Zhou and Ms Zhang gave evidence that Mrs Watson was asked during the property
inspection on 10 February 2020 “[are
there] any other leaks elsewhere in
the house?”, to which she responded “no”. Mrs Watson denied
that she had done
so. The Judge concluded that it had not been proved that such
a statement had been made. He held:
[109] It is a somewhat vexed
question, in light of all the circumstances I have outlined above, as to whether
or not Mrs Watson did
make the alleged representation to the effect that there
were no leaks elsewhere in the house. On balance, and by a rather fine
margin,
I find that the plaintiffs have not been able to establish to the balance of
probabilities that the representation was made,
such that for present purposes,
I must conclude that the alleged representation was not made.
[110] If I may be wrong in that conclusion, however, then in any event I am
satisfied it makes little difference here. This is because
in my view if I was
to find that the representation in question had been made then it was
Mrs Watson’s honest and reasonably
held opinion that, as earlier
leaks elsewhere in the house had been fixed, at the point of sale, there were no
other leaks elsewhere
in the house. The alleged statement, accordingly, could
not reasonably be taken as a representation that the house was an entirely
sound
one with no future likelihood of weathertightness issues.
[111] Again, if I may be wrong on that issue as well, then questions also
arise as to whether any alleged representation would have
itself induced Rocky
and Veronica to enter into the SPA, bearing in mind first, the favourable advice
about the house they had received
from their builder, Mr Huang, and secondly,
issues of reasonable reliance that arise here.
[112] For all these reasons, but again by only a rather fine margin, I find
that the plaintiffs have not been able to establish that
an oral
misrepresentation occurred here in terms of their second cause of action in
their [amended statement of claim].
- [15] On behalf
of Mr Zhou and Ms Zhang, Mr Wollerman argued that the Court erred in making
these findings. In terms of whether this
statement was made, the evidence of Mr
Zhou and Ms Zhang was clear and consistent, and it was corroborated by the only
independent
witness, the real estate agent, Ms Liu. By contrast,
Mrs Watson’s evidence was less definitive — she could not
remember
being asked by Ms Liu whether there were any leaks elsewhere, and her
evidence was there were quite a few people around going around
the property, a
lot of voices, and she was being bombarded with questions. The claim for
misrepresentation should accordingly have
been accepted on the basis
advanced.
- [16] For Mrs
Watson, Mr Fraundorfer supported the Judge’s findings, stressing that
these were based on findings of fact that
should not be lightly overturned on
appeal.
Analysis
- [17] In
accordance with the approach to general appeal identified by the
Supreme Court in Austin, Nichols & Co Inc v Stichting Lodestar,
an appellant is entitled to judgment in accordance with the opinion of the
appellate
court.[9]
This includes an assessment of the facts whilst recognising the advantages that
the lower court will have had in making factual
findings.[10] The appellate court
should nevertheless exercise caution in considering the challenges to findings
based on credibility.[11] We
approach the cross-appeal on that general basis, focusing on the Judge’s
factual findings which were the primary reason
why this claim was dismissed, and
which also have implications for the mistake claim.
- [18] All
witnesses agreed that there was a discussion with Mrs Watson concerning part of
the ceiling in one room where a pipe had
been plastered over/patched. Both Mr
Zhou and Ms Zhang then gave evidence that the question about any other leaks was
then asked
by Ms Liu and answered by Mrs Watson. Ms Liu gave slightly different
evidence, saying that the question was asked by Ms Zhang, but
that she had
translated it for Ms Zhang, and Mrs Watson then gave the answer.
- [19] We agree
with the Judge that it is difficult to reconcile this evidence with the
contemporaneous documents.[12]
After the leaking at the property was discovered, there were a series of WeChat
exchanges between Ms Liu, Mr Zhou, and Ms
Zhang.[13] On 13 May 2020,
Ms Liu sent Mr Zhou and Ms Zhang a messages asking:
Do you
remember you asked the vendor face to face some questions the first time we
visited the house together? I remember we asked
the vendor about the patched
ceiling in the bedroom downstairs. She said it was fixed with no problem. Had
you asked whether there
was any leak elsewhere or something like that? What did
she answer? Because I was with the kids mostly on that day, I am not sure
about
all the questions that you raised to the vendor.
A little later she further asked before Ms Zhang had replied:
Back then the vendor did not disclose the water leak around the window to
you, right?
And then a little later:
Then I will confirm with our manager that the vendor did not tell us there
was water leak issue.
- [20] Mr Zhou
then replied to these text messages in the following way:
The vendor
did not share any leak issue. Regarding that area she said it was a pipe
popping out only.
A little later Ms Zhang said:
We didn’t talk to her on our own. I raised the question to her whether
there was any asbestos. She said no, and you were beside
us.
- [21] These
exchanges are not consistent with Ms Liu’s evidence at trial that she
asked Mrs Watson the question about leakiness
herself, translating for Ms Zhang,
or with the evidence of Ms Zhang and Mr Zhou that Ms Liu had asked Mrs Watson
the question, and
Mrs Watson had given the answer they described. Rather, Ms
Liu was saying she did not know what, if anything Mrs Watson had said,
and Mr
Zhou stated that Mrs Watson “did not share any leak
issue”.
- [22] Also on 13
May 2020, Ms Liu provided a formal report to Mr Morgan Philips at RedCoats Ltd
explaining the events. She said:
The first time they viewed the
house was through the open home. As the Vendors are old people we didn’t
like to bother them.
The second time I viewed the property (which after school
time) the Buyers took 2 kids to the property. During that time the vendor,
other groups of buyers, listing agent and I were there as well. As the vendors
were old people they didn’t like noise, so
I looked after children
downstairs outside. I let the buyer and builder look over the house by
themselves and told them if they
have any questions, they can ask vendors
directly.
When was I upstairs with the buyers we did ask some questions about the
hot-water cylinder, insulation in the walls, also what happened about a
trace of plaster that was fixed in the ceiling. The vendor
explained there was
a pipe in the ceiling that didn’t look not nice, and they plastered it
themselves.
The Buyer also asked some other questions with the vendor face to face when I
was outside looking after their young children.
But the vendor had disclosure about the leaking problems.
- [23] This
confirms what was said in a more formal way. Given the evidence that it was Ms
Liu herself who was said to have asked the
question and received the answer from
Mrs Watson, this email and the earlier exchanges are significant. If
Mrs Watson had stated
there were no leaks in the house Mr Zhou, Ms Zhang,
and Ms Liu would have naturally emphasised this in their exchanges. This
is
particularly so as the exchanges were closer in time to the events, and at a
stage where it was apparent that there was a significant
issue about leaks in
the house, and where the responsibility for the position that Mr Zhou and
Ms Zhang were in was very much a live
issue.
- [24] We also see
it as significant that it is apparent from the evidence of Mr Zhou and Ms Zhang
that they understood that the vendors
were obliged to point out any such leaking
issues. Such an understanding could easily lead a person in their position to
misremember
a failure to disclose as inaccurate disclosure.
- [25] Finally,
whilst we agree that Mrs Watson’s evidence appears less certain, she was
ultimately clear in her evidence that
she did not, and would not have said that
the house did not leak. Her evidence was to the effect that, had she been asked
she would
have said there had been leaks which she believed had been fixed. We
read her evidence as being consistent with her answering the
questions at trial
honestly and to the best of her ability.
- [26] We
accordingly agree with the High Court Judge that Mr Zhou and Ms Zhang did not
prove, on the balance of probabilities, that
Mrs Watson made the alleged
statement.[14]
- [27] We also
agree with the Judge’s observation that, even if such an answer had been
given, there would have been an issue
over whether it could reasonably be relied
on given the circumstances.[15]
This would have been a brief question and answer between a couple for whom
English was a second language and a person in her 80s,
who was finding the
number of people in her home, and the noise they were making, a little difficult
to manage. Even if the question
and answer had in fact been given in these
circumstances, it may well have been necessary for the communication to have
been more
clear cut before it would have been reasonable to rely on such an
answer — for example by more formal follow up questions and
answers.
There was too much scope for miscommunication and misunderstandings for a single
question and answer in these circumstances
to be the sole basis for a claim of
misrepresentation under the CCLA.
- [28] Given these
findings, we agree with the High Court Judge that the claim in misrepresentation
based on an oral misrepresentation
was not made
out.[16] The
cross-appeal on
this issue is dismissed.
Mistake
- [29] The Judge
upheld the claim of common mistake under the CCLA. He held that both parties
thought the house was sound and did not
leak in any significant
way.[17] In awarding discretionary
relief under the CCLA he used the value of the property without its defects
compared with its value with
those defects, and then deducted 30 per cent
because Mr Zhou and Ms Zhang contributed to their own loss and they potentially
had
a remedy against the builder which they did not
pursue.[18] He dismissed other
claims. This resulted in an award of
$271,600.[19]
Arguments
- [30] For Mrs
Watson, Mr Fraundorfer argued that there was no evidence that Mr Zhou and
Ms Zhang turned their minds to the question
of the leakiness of the building at
all, and accordingly that there was no mistake under the CCLA. Neither did
Mrs Watson turn her
mind to the issue of leaking, so she was not mistaken
either.
- [31] Moreover,
the contract was the standard ADLS/REINZ agreement which is carefully drafted to
fairly apportion risk through disclosure
obligations and due diligence. No
conditions were inserted by Mr Zhou and Ms Zhang notwithstanding that they had
brought a builder
along with them to the inspections. Such agreements proceed
on the basis of caveat emptor. To allow this claim to succeed was inconsistent
with s 21(2)(b) of the CCLA as it is inconsistent with the general security of
contractual relationships.
- [32] This is an
old house, with potential issues apparent on inspection, and, as noted, a
builder was with the purchasers during the
inspection. The position can be
distinguished from other cases where mistake has been upheld with the sale and
purchase of real
estate of these terms, including the decision of the High Court
in Shen v Ossyanin (No 2) where there had been an express discussion
between vendor and purchaser about
leakiness.[20]
- [33] Mr
Fraundorfer also criticised the findings of the Court relating to relief and
quantum, including those concerning mitigation,
betterment, and additional
adjustments that should have been made under s 28 of the CCLA.
- [34] For the
respondents, Mr Wollerman supported the Judge’s analysis. The Judge had
considered the relevance of caveat emptor
and the requirement for common
mistake. A number of decisions have held that a claim for mistake under the
CCLA could apply in the
context of agreements for the sale of
land.[21]
- [35] The Judge
assessed the factual circumstances leading up to the sale, including the repair
work that Mrs Watson had engaged in
to deal with the leakiness. Mrs Watson
believed that the repair work meant that when she sold the house it was sound
and did not
have leaks. This was a mistake. Mr Zhou and Ms Zhang had been told
to avoid monolithic clad houses as they may be prone to leaking.
They wanted a
sound house, and asked relevant questions relating to the status of the house at
the time. Had they known the house
was leaking they would not have proceeded
with the sale. The house itself appeared to be sound and in good condition,
although rugs
had been placed in a manner that meant that prior leaking was not
identified. Mr Zhou and Ms Zhang would not have proceeded with
the sale if they
were aware of the issues with the property that were discovered
post-settlement.
- [36] In relation
to the arguments regarding the level of damages, Mr Zhou and Ms Zhang
supported the High Court Judge’s
conclusions.
Analysis
- [37] Broadly
speaking, the requirements for the application of the CCLA for common mistakes
are that:[22]
(a) both parties made the same mistake, or a different mistake about the same
matter of fact or law; and
(b) the mistake influenced both parties in their decisions to enter the
contract; and
(c) the mistake(s) resulted in a substantially unequal exchange of values or
disproportionate consideration.
- [38] There are
other statutory limitations on the claim, including that arising from
s 24(1)(c) of the CCLA that there not be a term
of the contract which
obliges a party to assume the risk of the mistake. It was not argued that s
24(1)(c) applied in the present
case.
- [39] Section 21(2)(b)
also provides that the powers under subpt 2 “must not be exercised in a
way that prejudices the general
security of contractual relationships”.
There has been little assessment on the meaning and effect of s
21(2)(b).[23] It was included in
the predecessor to the CCLA, the Contractual Mistakes Act 1977 after
consideration of the Contractual Mistakes
Bill 1977 by the Statutes Revision
Committee.[24] The reasons for its
addition were explained by the Minister of Justice in the following
terms:[25]
A number of
submissions to the select committee expressed concern at what was thought to be
the effect of the Bill on the certainty
that normally attaches to a written
contract. While some of these submissions failed to take account of the
existing law relating
to mistake, the select committee nevertheless felt it
desirable to spell out that the general security of contractual relationships
should not be prejudiced by the Bill.
- [40] We consider
that s 21(2)(b) potentially limits the exercise of the remedial powers under the
CCLA. The expression “prejudices
the general security of contractual
relationships” contemplates a situation where the grant of a remedy under
the CCLA would
be inconsistent with the certainty that is intended to apply in
relation to the particular type of contract in question. A contract
may not
have a provision that is within the concept contemplated by s 24(1)(c), but the
general nature of the contract, including
in relation to questions such as the
understood allocation of risk, may restrict the application of powers under the
CCLA.
- [41] This case
involves the sale of residential real estate under the standard ADLS/REINZ
terms. This is a standard form contract
that is used in almost all residential
property sales in New Zealand. One feature of this standard contract is that it
generally
proceeds on the basis of the common law principle of caveat emptor.
The buyer is taking the risk associated with the acquisition
of the property
subject only to the contractual warranties set out in the standard terms, any
other express conditions included the
contract (including any additional
warranties), and the application of any other principles of law such as
misrepresentation under
the CCLA, or the potential application of the Fair
Trading Act 1986, which limit caveat
emptor.[26] If there is some
important issue that affects the value but this issue does not go to one of the
exceptions, the risk of this matter
is taken by the purchaser.
- [42] Risks
associated with the acquisition of residential property under these terms are
commonly addressed by offers to enter a contract
under those terms being
conditional on a satisfactory builder’s report, or other techniques of
this kind. It is also reflected
in the statement on the final page of the
standard form ADLS/REINZ contract which relevantly says:
BEFORE
SIGNING THE AGREEMENT
...
- It is
recommended both parties seek professional advice before signing. This is
especially so if:
...
○ the purchaser wishes to check the weathertightness and soundness of
the construction of any dwellings or other buildings
on the land.
- [43] This is not
a term of the contract, but is advice contained within the standard terms that
reflects the risk allocation that
underlies the contract, and accordingly
notifies the parties that caveat emptor is operating. In the present case, this
feature
was also reflected in the presence of a builder accompanying the
prospective purchasers on their visit. They were also aware of
weathertightness
issues as a result of a previous unsuccessful potential purchase. Mr Zhou and
Ms Zhang decided not to make their
offer conditional on a satisfactory
builder’s report, however.
- [44] We consider
that this general contractual framework means that s 21(2)(b) restricts the
exercise of the remedial powers under
the CCLA through limiting what may be
accepted as a qualifying mistake. There is no definition of
“mistake” contained
in the CCLA apart from it being specified to
include a mistake of fact or law, although more extensive definitions were
considered
during the legislative process for the Contractual Mistakes
Act.[27]
- [45] It has been
held that when a party fails to turn their mind to a particular matter there is
no qualifying mistake — in
other words, ignorance is not a
mistake.[28] In other contexts,
however, when both parties have forgotten about a particular matter, a mistake
has been found.[29] As has been
pointed out by commentators, the difference in these cases may depend on how the
mistake contended for is formulated,
and it may be possible to reformulate the
ignorance cases so that a mistake is
identified.[30]
It is accordingly for the court to assess and determine whether a qualifying
mistake arises from the states of belief held by parties
to the contract.
Section 21(2)(b) limits what can be held to be sufficient in the context of
the contract in question.
- [46] The mistake
identified here by the Judge was expressed in slightly different ways, but the
key finding was a belief of the parties
that “the house was sound and did
not leak in any significant
way”.[31] We consider that
the operative concept associated with this finding is that there was a belief by
the purchaser that the house was
sound — the reference to leakiness is
really an illustration of the soundness.
- [47] The
difficulty with this being a qualifying mistake in this contractual context is
that it could arise in any situation where
there is any underlying problem that
the parties are unaware of. For example, an issue with subsidence, or even
other unknown matters
such as a plan by a public authority that the property be
compulsorily acquired, could become a qualifying mistake. Both parties
could
erroneously believe there were no such issues. Such scenarios could be treated
as a qualifying mistake with a formulation
that the house was sound, or that it
did not suffer from issues that substantively affected value, or alternative
formulations of
that kind.
- [48] We do not
consider that general beliefs of this kind can found a claim for mistake under
the CCLA in this contractual setting.
Allowing such formulations to qualify as
mistakes would undermine the concept of caveat emptor that still generally
exists with
residential property sales on the standard ADLS/REINZ terms, and the
certainty of contract that the standard terms promote in connection
with the
sale and purchase of real estate in New Zealand. It is especially
important for the everyday subject of property sales
that the law be as
straightforward as possible.[32] If
this kind of mistake operated in this context, the CCLA could be applied in any
sale of property on the standard terms whenever
it transpired that there was an
unknown issue of significance affecting the value of the property. This would
generally undermine
the certainty of property sales.
- [49] It is
relevant to consider the history of the application of the CCLA in relation to
mistake in recent decisions involving the
standard ADLS/REINZ terms. In
Magee v Mason, this Court considered an appeal against a
decision upholding a claim for misrepresentation associated with a sale on these
terms.[33] The purchasers had asked
one of the vendors whether the house was a leaky building, and the vendor had
replied: “Absolutely
not, we have never had any issues with the
property.”[34] The house
turned out to have weathertightness issues. The majority held that the
vendor’s statement did not involve a misrepresentation
and the appeal was
allowed.[35]
Professor McLauchlan subsequently suggested the result in this case may
have been different if it had been addressed as a claim
for mistake under the
CCLA.[36]
- [50] In Shen
v Ossyanin (No 2), the High Court then upheld a claim for common mistake
under the CCLA applying the approach proposed by Professor
McLauchlan.[37]
The Court had earlier held that there had been no misrepresentation about
whether the house leaked, but that the purchaser had asked
the vendor whether
the house leaked, and that vendor had (honestly) replied that it did
not.[38]
A claim for common mistake was upheld on the basis that both parties were
mistaken about the house’s
leakiness.[39]
- [51] In both
these cases the question of weathertightness/leakiness was expressly raised
between vendor and purchaser. A basis for
a mistaken belief in relation to the
weathertightness/leakiness of the house potentially arose as a consequence. But
in the present
case, the Judge did not find that there was any relevant
discussion between vendor and purchaser about the weathertightness/leakiness
of
the house.[40] For the reasons
outlined above, we agree with this finding. There was no other evidence that
the vendors or purchasers directly
considered leakiness. The absence of
evidence that weathertightness/leakiness was a matter that was raised or
considered has resulted
in the Court identifying the relevant mistake based on a
belief in the “soundness” of the property, with weathertightness
essentially seen as part of that concept. The mistake was described by the
Judge as mistake about:
(a) “the physical characteristics and water-tightness of the
house”;[41]
(b) that “the house was sound and did not leak in any significant
way”;[42]
(c) “as to what were very important physical characteristics of the house
including its general
watertightness”;[43]
(d) “that the house was indeed sound and had no significant leaking
issues”;[44] and
(e) “the house was sound and did not have significant
leaks”.[45]
- [52] In all of
these formulations it is the “soundness” of the building that is
first identified, with leakiness then
said to be included within that concept.
The pleaded mistake in the amended statement of claim was that “the
property did
not leak and/or was a sound one with no likelihood of
weathertightness problems”. It was necessary for the mistake to be
formulated
in those more general terms given that, on the Judge’s
findings, weathertightness/leakiness was itself not raised by the purchasers
with the vendors, or otherwise specifically considered by either party at the
time of purchase. There was nevertheless a basis for
the Judge to find that the
purchasers wanted, and thought they were getting, a “sound” home.
It is relevant that the
Judge considered that it was arguable that Mrs Watson
had “caused” the mistake, which we consider was a finding that
she
had greatest responsibility for what was an unsatisfactory
situation.[46]
- [53] We consider
that these findings reflect the difficulty with this state of belief founding a
claim for mistake under the CCLA
under the standard ADLS/REINZ contract. There
are a number of factors that could affect the soundness, or the inherent value
of
a property. To allow this kind of belief, or assumption about the
characteristics of the property to give rise to a claim for mistake
under the
CCLA would be inconsistent with the essential nature of this contract, and
accordingly how this standard form contract
is intended to operate in the market
for house sales.
- [54] It is also
necessary for the mistake to have influenced the entry of the
contract.[47] The High Court Judge
proceeded on the basis that neither the vendors nor the purchasers would have
proceeded with this contract
had the true position been known about the
leakiness of the property.[48] But
that is not what must be proved under s 24(1)(a)(ii). It must be shown
that all parties were “influenced in their respective
decisions to enter
the contract by the same
mistake”.[49]
- [55] This would
normally require parties to have turned their mind to the mistaken matter for it
to have had an influence on the decision
to enter the contract. In this
particular context, we consider that the satisfaction of those elements required
greater particularity
about the erroneous matter of fact, and how it influenced
the decision of the parties to enter the contract, before the elements
could be
said to be satisfied. If that level of particularity is not satisfied then
the requirements of the CCLA are being applied
in a way that undermines the
desirability for general certainty in relation to contracts for the sale of real
estate in New Zealand.
Conclusion
- [56] For these
reasons, we accept Mrs Watson’s argument that the appeal should be
allowed.
- [57] In this
contractual context, the requirement that there be a common mistake and that it
influence the parties in their decision
to enter the contract must involve a
more specific mistake before the CCLA can be applied in the way that does not
undermine the
general security of contractual relationships in the way
contemplated by s 21(2)(b).
- [58] There is
still room for the CCLA to operate in this contractual context, but it requires
a level of particularity. The parties’
general belief that the building
is sound, and that there are unlikely to be unknown defects or other matters
that may affect its
value, will not be sufficient to be a qualifying mistake,
and neither can such a belief be said to have influenced the entry of a
contract
without something more explicit.
- [59] Given these
findings, it is not necessary to address Mrs Watson’s further grounds of
appeal relating to the quantum of
damages awarded on the mistake
claim.
Breach of warranty
- [60] We now
address the remaining aspect of Mr Zhou and Ms Zhang’s cross‑appeal.
Mr Zhou and Ms Zhang advanced, as their
first cause of action in the High Court,
a claim for breach of contractual warranty under the Agreement. The Agreement
provided:
7.3 The vendor warrants and undertakes that at
settlement:
...
(6) where the vendor has done or caused or permitted to be done on the
property any works:
(a) any permit, resource consent, or building consent required by law was
obtained; and
(b) to the vendor’s knowledge, the works were completed in compliance with
those permits or consents; and
(c) where appropriate, a code compliance certificate was issued for those works.
- [61] Mr Zhou and
Ms Zhang contended that there were three categories of unconsented building
works that had been undertaken which
required a consent. The first related to
work undertaken on an upper deck. The second related to a retaining wall. The
third related
to drainage work undertaken on a lower storey of the
building.[50]
- [62] Mr Zhou and
Ms Zhang argued that, had the required building consents been applied for, the
Hutt City Council (the Council) would
have undertaken wider weathertightness
assessments of the property and discovered further defects with the
weathertightness of the
property, not just in relation to the work to which the
application related, but to the whole property. In the High Court, Mr Zhou
and
Ms Zhang sought the full cost of remediating the whole property (or the
equivalent diminution in value) on this basis.
- [63] The Judge
accepted the work undertaken on the deck may have been undertaken in 2006 and
that if that was so it was accepted by
Mrs Watson’s expert that a consent
was required.[51] In relation to
the retaining wall, the Judge held that the wall was over 1.5 m, and accordingly
that it required a building consent
as the experts had
agreed.[52] In relation to the
drainage work, the Judge indicated there was some doubt as to whether this work
required building consent.[53]
- [64] The Judge
held that the proper award of damages for breaches of warranty should be limited
to the cost of bringing the relevant
building work up to the standard required
by the Building
Code.[54]
He recorded that the warranty should only bear its ordinary and natural meaning
and that it was not a warranty that the home in question
was
watertight.[55]
He rejected Mr Zhou and Ms Zhang’s argument that the costs for remedying
the water damage to the property could be recovered
on this basis. He held that
it was too uncertain as to what the Council may have done when inspecting the
work for which consents
were required, and the lack of consent was not causative
of the damage done to the house.[56]
He found that this damage was too remote, albeit “by a reasonably fine
margin”.[57]
- [65] Given those
findings, the award of damages was limited to $15,000 excluding GST, being the
cost of making the retaining wall
compliant.[58]
Arguments
- [66] Mr
Wollerman, for Mr Zhou and Ms Zhang, argued that the High Court had erred in
finding that there was doubt that the drainage
work required a building consent.
The Judge was correct in finding the deck work required a building consent. If
the building consents
had been sought for the drainage work and the deck work,
the Council would have undertaken a wider assessment of the weathertightness
of
the property. Whilst the argument was similar to that advanced in Newton v
Stewart, there were distinguishing features in the present
case.[59]
- [67] Where a
consent is required but has not been sought, it is a question of assessing what
would have happened if it had been sought.
It was wrong for the Judge to say
there would have been doubt about what the Council would have done as the
Council would have considered
weathertightness to be of critical significance.
The expert evidence was that the work had interrelated aspects, and inspections
would have been required. The authorities relied upon by the Judge were not
instructive. The case was more similar to Anderson v De Marco, where the
Court had held that, had a consent been applied for, the interrelated
weathertightness problems with the property would
have been
discovered.[60]
- [68] Even if the
Judge did not award damages for the cost of remediating the entire property,
evidence was also produced for costs
required to remediate the retaining wall,
deck, and drainage, and corresponding valuation evidence was also provided.
Damages should
at least have been awarded on that basis.
- [69] For Mrs
Watson, Mr Fraundorfer argued that neither the work on the deck nor the drainage
work required a building consent. In
relation to the drainage work, this was a
minor alteration to a drain falling within sch 1 of the
Building Act 2004. It was also prejudicial to allow the drainage
claim to be advanced which had not been within Mr Zhou and Ms Zhang’s
pleading,
with a later application for amendment not addressed by the
Court.[61]
- [70] Mr
Fraundorfer also supported the Judge’s findings in relation to causation.
It was not established that the Council would
have addressed any wider issues
concerning weathertightness. The way that Mr Zhou and Ms Zhang had presented
their case in this
respect meant that this claim was rightly dismissed.
Analysis
- [71] The
starting point for assessing the remedy for a breach of a contractual warranty
is the normal approach for breach of contract.
When a party has warranted that
a particular matter is true, a breach of contract is established by the
plaintiff showing that the
matter is not true. The plaintiff need not show that
the defendant was fraudulent or negligent in making the relevant statement,
only
that it is false. The obligation of the defendant is strict — liability
flows from
non-performance.[62]
- [72] The basis
for the award of damages for breach of warranty is the same as for other
contractual breaches. A plaintiff is entitled
to be put in the position they
would have been in had the contract been
performed.[63] So Mr Zhou and Ms
Zhang were entitled to an award that put them in the position they would have
been had the relevant work been
conducted with any required building consents.
Usually, an award of damages would be based on the diminution in value, but the
approach
is not inflexible.[64]
- [73] If a
consent was not obtained when it should have been, then Mr Zhou and
Ms Zhang may be entitled to an award representing the
cost of now obtaining
a consent, and having work undertaken so that the building is compliant. In
addition, Mr Zhou and Ms Zhang
may be entitled to an award of damages to
compensate for any damage to the property arising from the non-compliant nature
of the
work undertaken, particularly if the non‑compliance and damage were
not apparent to them when purchasing the
property.[65]
(i) What
damages were recoverable?
- [74] We agree
with the Judge that damages could not be awarded to Mr Zhou and Ms Zhang on the
basis advanced at trial.[66]
- [75] Mr Zhou and
Ms Zhang contended that, had the required consents been applied for, the more
profound problems with the leakiness
of the house would have been identified by
the Council, and more widespread remediation would then have been required. We
agree
that this consequential effect was not established on the evidence. Mr
Zhou and Ms Zhang did not show the Council would have required
an extensive
remediation exercise over the whole property. Indeed, we consider it unlikely
that any other weathertightness issues,
not directly associated with the work in
question, would have been identified by any inspections by the Council or
otherwise. It
was not shown that the cost of this remediation was caused by the
breach of the warranty.
- [76] But we do
not consider that these findings are sufficient to fully address Mr Zhou
and Ms Zhang’s claim for damages for
breach of warranty. Whilst Mr Zhou
and Ms Zhang were seeking to recover the entire cost of remediating the whole
building, this
did not disqualify them from being awarded the direct loss
attributable to the breach of warranty in a more particular
way.[67]
- [77] The Judge
did address this category of damages with respect to the retaining wall, finding
that a building consent was required
for this wall, that it had not been
obtained, and that $15,000 was the cost of now bringing that wall up to Building
Code standards.[68] That was the
basis of the award in relation to breach of warranty. There is no challenge to
these findings. But the Judge did
not make such findings with respect to the
deck or the drainage work.
(ii) The deck work
- [78] With
respect to the deck, the Judge did not make a definitive finding that a building
consent was required for this work, although
he noted that Mrs Watson’s
expert appeared to agree with Mr Zhou and Ms Zhang’s expert that a consent
would have been
required if the work had been undertaken in
2006.[69] If so, Mr Zhou and
Ms Zhang could have been awarded damages representing the cost of now
bringing the deck up to Building Code standards,
and possibly for any
consequential damage arising from the work not being done to that standard.
- [79] However, Mr
Zhou and Ms Zhang did not provide any clear identification of the particular
costs that would have been necessary
to bring the deck up to standard, or
identification of any damage caused to the property because the deck work was
not at that standard.
We therefore do not see a basis upon which Mr Zhou and Ms
Zhang could have been awarded additional damages on the more limited basis.
We accordingly agree with the Judge that no additional award associated
with the deck could properly be made.
(iii) The drainage work
- [80] We consider
the drainage work to be in a different category, however. The drainage work was
important because it is clear from
the evidence that there has been significant
water ingress at this location which has caused damage to the building. The
very purpose
of the building work for which consent was alleged to be required,
but not obtained, was to prevent this water ingress. Mrs Watson
explained that
she had had work done on the property prior to sale to remedy this problem. It
is also apparent that Mr Zhou and
Ms Zhang were not aware of this water ingress,
or the water damage, at the time of the property sale.
- [81] We consider
that an award of damages to Mr Zhou and Ms Zhang for breach of warranty in
relation to this work could involve the
cost of now bringing the drainage work
associated with the building up to Building Code standards, and the remediation
of the damage
caused to the building by that work not being undertaken pursuant
to a building consent that would have required that standard to
be met.
- [82] The
position concerning the drainage work had an additional complication.
A claim in relation to that work had not been specified
in Mr Zhou and Ms
Zhang’s amended statement of claim dated 31 October 2022, but they had
made an application at trial to amend
their pleadings to include it. Mrs Watson
opposed the grant of leave. The Judge did not expressly rule on the
application, but
he nevertheless addressed the drainage work in the
judgment.[70] Given those
circumstances, we consider that the only appropriate course is to proceed on the
basis that the Judge implicitly granted
leave to amend the pleading. We
consider that there is no real prejudice to Mrs Watson in the grant of leave.
Two matters then
needed to be addressed:
(a) whether the work undertaken in relation to the drainage required a consent;
and
(b) whether any loss arose from the work being done with a consent.
(iv) Was a consent required for the drainage work?
- [83] The Judge
held there was some doubt about whether the December 2019 work required a
consent on the basis it was more in the nature
of general maintenance to an
existing drain, and accordingly a minor alteration which would be exempt
work.[71]
- [84] We do not
agree with the Judge’s analysis.
- [85] Mr Zhou and
Ms Zhang’s expert, Mr Tidd, gave evidence that a consent would have been
required for this work given cl E2
of the Building Code. The Judge recorded
that it appeared that Mrs Watson’s expert, Dr Stahlhut, agreed that if
water proofing
was carried out to the foundation wall of the building, a
consent, or at least an application for an exemption, would have been
required.[72] It is also apparent
from the evidence that the area of the building in question suffers from
significant water ingress in certain
conditions, and that damage was caused by
that water ingress when it occurred.
- [86] We consider
that the evidence shows that this work fell into a category where the
weathertightness system for this part of the
building had failed. We do not
consider that the work to address this can be classified as general repair,
maintenance, or replacement
under sch 1 of the Building Act as the Judge
suggested and as Mr Fraundorfer
argued.[73] Schedule 1 relevantly
provides that a building consent is not required for the following
work:
1 General repair, maintenance, and replacement
(1) The repair and maintenance of a building product or an assembly
incorporated in or associated with a building, provided that
a comparable
building product or assembly is used.
...
(3) However, subclauses (1) and (2) do not include the following building
work:
...
(c) repair or replacement (other than maintenance) of a building product or an
assembly incorporated in or associated with a building
that has failed to
satisfy the provisions of the building code for durability, for example, through
a failure to comply with the
external moisture requirements of the building
code; or
...
- [87] It is clear
that a building consent is not required simply because building elements such as
roofing or cladding need to be repaired
and there is leaking. This kind of
repair work happens all the time and no consent is required. But when a
weathertightness system
has completely failed and there is significant leaking
causing damage to the building interior, the work cannot accurately be
categorised
as only maintenance. We consider that the warranty was breached
here for this reason. The work to repair the failed weathertightness
system in
this part of the house required a consent.
(v) Damage caused by
the breach
- [88] The next
question is to identify the damages that arise from the work being undertaken
without a building consent. Mr Zhou and
Ms Zhang are potentially entitled to
the cost of bringing that building up to Building Code standards. We agree with
the Judge that
the relevant warranty was not that the house did not
leak.[74] Rather, it is a warranty
that all work done on the house was undertaken with a consent when required.
But Mr Zhou and Ms Zhang
are still potentially entitled to the cost of repairing
the damage to the property caused by the work not being up to the standard
that
would have been required if a consent had been sought.
- [89] There
appears to be little doubt that Mrs Watson and her husband had work undertaken
to fix this weathertightness problem in
2019, at a time when the
Building Act was in force, and when a building consent would have been
required. But the work in 2019 was, on Mrs Watson’s evidence, a
second
attempted repair. An earlier attempt to fix the problem had been unsuccessful.
It was unclear from the evidence when the
earlier repair work took place and
there can be issues arising from the fact that the standards of the Building
Code have changed
since the relevant work was
undertaken.[75] But, as the Judge
found, the relevant dates would not have been known to the
respondents.[76] Neither could Mr
Zhou and Ms Zhang know when and how the relevant damage occurred.
- [90] In those
circumstances, an evidential burden fell to Mrs Watson to show that that earlier
building repair work occurred at a
time before a building consent was required,
that the relevant standards under the Building Code were then lower so that the
work
done was compliant with the Building Code, or that the damage to the
building was not the consequence of the repair work not being
undertaken in
accordance with a building
consent.[77]
- [91] It is plain
that Mrs Watson and her husband were very aware of the leaking occurring in this
area. It had previously caused
reasonably significant damage. Part of the
carpet had been cut away because water had entered into the adjacent living
room. Rugs
had been placed over the areas where the carpet had been cut away.
The placement of those rugs over this area meant that this damage
was not
apparent to Mr Zhou and Ms Zhang when they undertook their inspections of
the property. Mr Zhou and Ms Zhang’s claim
for misrepresentation by
concealment was rejected by the High
Court,[78] but these actions
nevertheless played a part in Mr Zhou and Ms Zhang being unaware of the
previous water damage.
- [92] Mr Zhou and
Ms Zhang have proved that there was a failure of the weathertightness system in
this location, that work to address
this had been undertaken by the vendors
without a building consent when it was required, that the work had failed to
address the
issue, and that damage had been caused by water ingress. In the
absence of evidence from Mrs Watson showing that damage had occurred
before the
building works requiring consent were undertaken, or that the Building Code
requirements were lower at the time the work
was done, we consider that Mrs
Watson did not discharge the evidential burden on her, and that Mr Zhou and Ms
Zhang have proved their
claim on the balance of probabilities.
- [93] They are
entitled to an award of damages representing the cost of repairing the damage
caused by the water ingress resulting
from a failure of the building work to
meet the requirements of the Building Code at this location in addition to
the cost of bringing
the building to Code standards. That is because that
damage would not have occurred if it were true, as Mrs Watson warranted, that
the building work had been undertaken in accordance with a consent, and Mr Zhou
and Ms Zhang were unaware of the problem, or the
damage when they made their
successful offer.
- [94] We also
consider that this is the correct basis for the award of damages rather than
damages based on diminution of value in
this context. The area of leakiness,
and the damage caused by the leaks, needs to be repaired. This is a residential
property where
people such as Mr Zhou and Ms Zhang and their children will live
and it is necessary to bring it up to appropriate standards for
habitation.
(vi) Quantum of damages for breach of warranty
claims
- [95] Given the
above conclusions, there remains the difficulty that the High Court Judge did
not make any findings in relation to
damages flowing from any breach of warranty
in respect of the drainage works. He rejected the broader claim by Mr Zhou and
Ms Zhang,
although “only by a reasonably fine margin” but did not
address this more particular
claim.[79]
- [96] At the
hearing of the appeal, we gave leave to Mr Zhou and Ms Zhang to file a
memorandum to identify whether the evidence before
the High Court identified the
cost of now bringing this area up to the requirements of the Building Code, and
whether the evidence
also addressed the cost of remediating the damage
associated with this weathertightness failure. We also gave leave to Mrs Watson
to respond.
- [97] Mr Zhou and
Ms Zhang filed a memorandum contending that the supplementary evidence of Mr
Robertson at trial had addressed these
issues, and using his evidence they
identified the cost of remedying the weathertightness issue at $46,830.30, and
the cost of remedying
the water damage at $48,208.50, a total of $95,110.81
including GST.
- [98] In
response, Mrs Watson noted a number of issues concerning Mr Zhou and Ms
Zhang’s calculations, including a number of
margins that had been added.
She filed a revised calculation of cost based on the evidence of
Dr Stahlhut and Ms van Eden. This
totalled $33,916.87 including
GST. Mrs Watson also then deducted the amount awarded in relation to the
retaining wall already awarded
($15,000 excluding GST), leading to an amount of
$14,492.93 plus GST. In relation to any wider award for the water damage, Mrs
Watson
argued that there was no coherent evidence before the High Court that
could form the basis of a further award.
- [99] The
relevant range for the award accordingly appears to be between approximately
$15,000 and approximately $95,000.
- [100] Somewhat
reluctantly, we have reached the view that we are not in a position to finally
resolve what the award should be. We
are conscious that there is a significant
need for finality in this litigation. It is being conducted between ordinary
members of
the community in relation to a residential property sale that has
gone wrong. Mrs Watson has been in receipt of legal aid. Unfortunately,
however, any attempt by us to determine the amount of the award runs the risk of
being arbitrary. In these circumstances we feel
we have no option but to remit
this question to the High Court for determination. It is our expectation that
the parties, with the
assistance of their lawyers, will be able to resolve the
remaining difference without further litigation, and litigation cost.
- [101] For
the avoidance of doubt, we give the following directions about the matter
remitted to the High Court:
(a) Mr Zhou and Ms Zhang have established that Mrs Watson is liable for breach
of warranty in respect of the drainage works. Mr
Zhou and Ms Zhang are
entitled to damages representing the cost of bringing this area of failed
weathertightness up to the weathertightness
standards of the Building Code, and
the costs of remediating the water damage that has occurred to the property as a
consequence
of water entry at this point. Questions of liability and causation
are no longer alive to be addressed. The question is simply
the calculation of
damages on the above basis but taking into account what has already been awarded
(if relevant).
(b) The parties should be allowed to update their expert evidence directed to
these issues along the lines of what has been provided
in their supplementary
memoranda filed in this Court. The objective is to fairly and accurately
identify the costs in question.
We do not anticipate this being an elaborate
exercise, however. It may be possible for the experts to agree on the amount.
Expert
conferral under r 9.44 of the High Court Rules may well be appropriate if
the matter has not been able to be resolved by prior discussions.
(c) Mr Zhou and Ms Zhang are not to reargue their other claims, such as any
other claims for water damage elsewhere. The inquiry
is to be limited in the
way identified above.
(d) As we see it, given that the remaining issue is limited to the award of
damages, the matter falls within the jurisdiction of
an Associate Judge under s
20(1)(f) of the Senior Courts Act 2016. We do not say this to suggest that this
is how the matter must
proceed, but simply identify it as an option.
Costs
- [102] As to
costs, given that both parties have been successful with their respective
appeals, we consider that costs in this Court
should lie where they fall. We
note that Mrs Watson has been legally aided.
- [103] The High
Court awarded costs in the respondents’ favour. Whilst the award of
damages will now be lower we consider that
this award remains
appropriate.
Conclusion
- [104] The appeal
is allowed.
- [105] The
cross-appeal is allowed in part.
- [106] The
proceedings are remitted to the High Court to address the further damages
arising from the respondents’ claim for
breach of warranty on the basis
outlined in paragraphs [100]–[101].
- [107] The costs
of the appeal and cross-appeal are to lie where they
fall.
Solicitors:
Bush Forbes, Tauranga for
Appellant
Dalzell Wollerman, Wellington for Respondents
[1] Zhou v Watson [2023]
NZHC 2328 [judgment under appeal].
[2] At [149].
[3] At [48] and [71].
[4] Auckland District Law Society
and Real Estate Institute of New Zealand “Agreement for Sale and Purchase
of Real Estate”
(10th ed, 2019).
[5] Unilateral mistake was also
pleaded but not considered by the High Court Judge given his conclusions on
common mistake, see Judgment
under appeal, above n 1, at [150].
[6] Judgment under appeal, above n
1.
[7] At [194].
[8] At [195].
[9] Austin, Nichols & Co
Inc v Stichting Lodestar [2007] NZSC 103, [2008] 2 NZLR 141 at [16].
[10] Green v Green [2016]
NZCA 486, [2017] 2 NZLR 321 at [26]–[32].
[11] Austin, Nichols & Co
Inc v Stichting Lodestar, above n 9, at [13].
[12] Judgment under appeal,
above n 1, at [97]–[104].
[13] These messages were
translated for evidence at trial.
[14] Judgment under appeal,
above n 1, at [109].
[15] At [110]–[112].
[16] At [112].
[17] At [136] and [149].
[18] At [155]–[169].
[19] At [169].
[20] Shen v Ossyanin (No
2) [2019] NZHC 2430, (2019) 20 NZCPR 590.
[21] See, for example, Ware v
Johnson [1983] NZHC 155; [1984] 2 NZLR 518 (HC); Snodgrass v Hammington (1995)
10 PRNZ 672 (CA); and Shen v Ossyanin (No 2), above n 20.
[22] Contract and Commercial Law
Act 2017, s 24(1).
[23] See Ian Gault (ed) Gault
on Commercial Law (online ed, Thomson Reuters) at [CCL21.01].
[24] It was not included in the
Bill when first introduced: see Contract Mistakes Bill 1977 (11-1). The Bill
followed on from a 1976
report of the Contracts and Commercial Law Reform
Committee: Contracts and Commercial Law Reform Committee Report on the Effect
of Mistakes on Contracts (Wellington, May 1976).
[25] (8 November 1977) 416 NZPD
4287. See also Andrew Beck and Richard Sutton “Contractual Mistakes Act
1977” in Law Commission Contract Statutes Review (NZLC R25,
1993) at [2.89].
[26] See D W McMorland Sale
of Land (4th ed, Cathcart Trust, Auckland, 2022) at [2.01].
[27] The original form of the
Contractual Mistakes Bill contained a more detailed definition of
“mistake”: Contractual Mistakes
Bill 1977 (11-1). This was removed
from the final version of the Bill following discussion in the House, see (8
September 1977) 413 NZPD 2804. The definition of “mistake” in the
Contractual Mistakes Act 1977, s 2 was simply “means a mistake, whether of
law or of fact”. This definition was carried through to the Contract and
Commercial Law Act 2017 in s 23(1).
[28] New Zealand Refining Co
Ltd v Attorney-General [1992] NZCA 308; (1993) 15 NZTC 10,038 (CA) at 10,045 per Cooke P,
10,047 per Gault J and 10,051 per McKay J; Ladstone Holdings Ltd v Leonora
Holdings Ltd [2006] NZHC 300; [2006] 1 NZLR 211 (HC) at [70]–[87]; and Camelot Court
Motel Ltd v Anderson [2012] NZHC 153, (2012) 13 NZCPR 355 at [46].
[29] Slater Wilmshurst Ltd v
Crown Group Custodian Ltd [1991] 1 NZLR 344 (HC) at 356–357.
[30] See D W McLaughlin and C E
F Rickett “Mistake and Ignorance under the New Zealand Contractual
Mistakes Act 1977” (1995) 8 JCL 193 at 196; and Stephen Todd and Matthew
Barber Burrows, Finn and Todd on The Law of Contract in New Zealand (7th
ed, LexisNexis, Wellington, 2022) at [10.3.3].
[31] Judgment under appeal,
above n 1, at [136].
[32] Hunt v Wilson [1978]
2 NZLR 261 (CA) at 273 per Cooke J.
[33] Magee v Mason [2017]
NZCA 502, (2017) 18 NZCPR 902. The agreement in question was under the
8th edition of ADLS/REINZ terms, but the difference in the versions
is not material.
[34] At [34] per Miller and
Gendall JJ.
[35] At [55] per Miller and
Gendall JJ.
[36] David McLauchlan
“Misrepresentation? Or was it a case for relief on the ground of common
mistake?” [2018] NZLJ 13.
[37] Shen v Ossyanin
(No 2), above n 20. The Judge
had reached a preliminary view that contractual mistake was established in an
earlier decision: see Shen v Ossyanin [2019] NZHC 135. These
observations were confirmed in the later decision: see Shen v Ossyanin
(No 2) at [16]–[55].
[38] Shen v Ossyanin,
above n 38, at [110].
[39] Shen v Ossyanin
(No 2), above n 20, at
[16]–[55]. See also Shen v Ossyanin, above n 37,
at [105]–[109].
[40] Judgment under appeal,
above n 1, at [109].
[41] At [136].
[42] At [136].
[43] At [137].
[44] At [146].
[45] At [149].
[46] At [142]–[143].
[47] Contract and Commercial Law
Act, s 24(1)(a).
[48] Judgment under appeal,
above n 1, at [137]–[138].
[49] Contract and Commercial Law
Act, s 24(1)(a)(ii).
[50] The claim relating to the
drainage work was not pleaded in the amended statement of claim. An application
to amend the pleadings
was advanced at trial but not expressly addressed by the
Judge. The Judge acknowledged the dispute about this aspect of the pleadings
in
the judgment and ultimately addressed the issue regardless: see Judgment under
appeal, above n 1, at
[35]–[36].
[51] Judgment under appeal,
above n 1, at [47].
[52] At [48].
[53] At [61]–[62].
[54] At [64]–[66], citing
Bhargav v First Trust Ltd [2023] NZHC 174 at [44]; and Ford v Ryan
[2007] NZHC 1454; (2007) 8 NZCPR 945 (HC) at [46].
[55] At [69], citing Newton v
Stewart [2013] NZHC 970 at [98].
[56] At [70], citing Newton v
Stewart, above n 55, at [52].
[57] At [70].
[58] At [68] and [72].
[59] Newton v Stewart,
above n 55.
[60] Anderson v De Marco
[2020] NZHC 2979, (2020) 21 NZCPR 758 at [123].
[61] Mrs Watson acknowledged
that the Judge addressed the pleadings issue in the judgment, see Judgment under
appeal, above n 1, at [36].
[62] See John Cartwright
Misrepresentation, Mistake and Non-Disclosure (6th ed, Sweet &
Maxwell, London, 2022) at [8–02] and [8–23]. See also Gedye v
South [2010] NZCA 207, [2010] 3 NZLR 271, aff’d Gedye v South
[2010] NZSC 97, [2010] 3 NZLR 271 at [3]–[4].
[63] See Todd and Barber
Burrows, Finn and Todd on The Law of Contract in New Zealand, above
n 30, at [21.2.1].
[64] Marlborough District
Council v Altimarloch Joint Venture Ltd [2012] NZSC 11, [2012] 2 NZLR 726 at
[24] and [27] per Elias CJ, [156] per Tipping J, and [191] per McGrath J; and
Leisure Investments NZ Ltd v Grace [2023] NZCA 89, [2023] 2 NZLR 724 at
[184].
[65] If a purchaser is aware of
the damage, it can be presumed to have been reflected in the purchase price such
that no loss would have
arisen.
[66] Judgment under appeal,
above n 1, at [71].
[67] High Court Rules 2016, r
5.31(2).
[68] Judgment under appeal,
above n 1, at [59]–[60], and
[67]–[68].
[69] At [45]–[47].
[70] At [35]–[36].
[71] At [61].
[72] At [49].
[73] At [61].
[74] At [69].
[75] See, for example, Ford v
Ryan, above n 54, at
[46]–[47].
[76] Judgment under appeal,
above n 1, at [36].
[77] See Halsbury’s
Laws of England (5th ed, 2020, online ed) vol 12 Civil Procedure at [700].
See also Ansley v Prospectus Nominees Unlimited [2004] NZCA 14; [2004] 2 NZLR
590 (CA) at [42]–[48].
[78] Judgment under appeal,
above n 1, at [113]–[120].
[79] At [70].
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZCA/2024/417.html