NZLII Home | Databases | WorldLII | Search | Feedback

High Court of New Zealand Decisions

You are here:  NZLII >> Databases >> High Court of New Zealand Decisions >> 2005 >> [2005] NZHC 1289

Database Search | Name Search | Recent Decisions | Noteup | LawCite | Download | Help

Heli Harvest Limited v Marlborough District Council HC Wellington CIV 2004 485 1669 [2005] NZHC 1289 (24 February 2005)

Last Updated: 18 June 2020


IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY

CIV 2004 485 1669



IN THE MATTER OF
of an appeal under s299 of the Resource Management Act
BETWEEN
HELI HARVEST LIMITED
First Appellant
AND
GEMINI BARGE CO. LIMITED
Second Appellant
AND
MARLBOROUGH DISTRICT COUNCIL
Respondent
Hearing:
24 February 2005


Appearances: L Herzog for the Appellants
B P Dwyer for the Respondent Judgment: 24 February 2005
2005_128900.jpg

ORAL JUDGMENT OF WILD J




Introduction


Heli Harvest Limited And Anor V Marlborough District Council HC WN CIV 2004 485 1669 [24 February 2005]

discouragements by appellate Judges apply here because the appeal is against the Employment Court’s decision under s285(1)(a) of the Resource Management Act 1991 which provides:

285 Awarding costs

(1) The Environment Court may order any party to pay—

(a) To any other party, such costs and expenses (including witness expenses) incurred by that other party as the Court considers reasonable:

The Court will interfere with decisions of the Tribunal only if it considers that the Tribunal:

Factual background

alternative mooring for the barge. It did not, in express terms, require the removal of the barge by 1 December 2002.
  1. An order for the removal of the barge from the coastal marine area.
  1. An order requiring the appellants prior to commencing removal to decontaminate the barge.
  1. An order requiring the appellants, after removal of the barge, to commission the Cawthron Institute to survey Shakespeare Bay to ascertain the extent of any spread of the Didemnum.
  1. An order requiring the appellants to undertake an eradication programme of any Didemnum contamination identified by the Cawthron survey.
scientist at the Cawthron Institute who carried out the various surveys for Heli Harvest.
  1. That Didemnum was a potential threat to the sounds.
  1. That the barge had no resource consent to remain where it was.

Outcome

[17] Accordingly the Court orders (by consent) under section 319 of the Resource Management Act 1991 that ...

(5) Costs are reserved.

a fair one, that it was Judge Jackson and not Judge Kenderdine who had presided at the 17 April hearing.

The Environment Court’s costs decision


Grounds of appeal


Generally


that effect were the likely, if not inevitable, outcome if the hearing continued to a judgment. The untenability of the appellants’ “neither party succeeded” submission permeates many, if not all, of the eight grounds of appeal, to which I now turn.

Ground 1


[22] The respondents consider too that they had inadequate time to file substantive affidavits refuting the concerns as to the seaworthiness of the barge, and the alleged biosecurity risk caused by the Didemnum sp. They contest that the council’s evidence given in the morning of the hearing would not have stood up to cross-examination scrutiny.

Ground 2


[25] Referring to the decisions of Goldfinch v Auckland City Council, which discussed Rowell v Tasman District Council, I conclude the successful party is more likely to get an award of costs for enforcement proceedings. The respondents have submitted that this principle is not applicable, as costs are likely to be awarded to a successful litigant in enforcement proceedings, and neither party was successful in this case.

facts and submitted that, and as there was no successful party in this proceeding, no costs should be awarded.
  1. A successful party is more likely to get an award of costs in enforcement proceedings.
  1. Heli Harvest submits this principle is not applicable in this case as neither party was successful.

Ground 3


simply reflected the parties’ agreement. This is the same fundamental point over again. I reiterate, consenting was a concession. I accept that the parties had, out of Court, come to terms. But the point is, they then came back into Court and invited the Court to make enforcement orders by consent, which the Court did. Yes, that certainly obviated the need to continue with the proceeding, but, as the Council submits, the ongoing legal costs which would have resulted from that would have been reflected in a higher award of costs, had the Council been ultimately successful.

Ground 4


[28] Nor is it appropriate in terms of a cost application for the respondents to attempt to relitigate what occurred in the enforcement proceedings. The contents of some of the respondents’ submissions appear to challenge the merits of the proceedings issued by the council. It is not now open to the respondents to do so. Such issues were determined when the orders were made by the Environment Court. Having conceded that was appropriate for the orders to be made, it is now inappropriate for the respondents to imply that the orders were not justified, or that the application was premature.

Ground 5


[29] Contrary to their submissions, the sequence of events does not show the respondents went out of their way to contain a potentially devastating environmental risk either. The council granted a resource consent to enable the Steel Mariner to occupy the coastal marine area for a period expiring 1 December 2002. This gave the respondents a period of approximately 10 months (in addition to the period of previous illegal occupation) within which to make arrangements to remove the boat. They did not do so. On the lapse of the resource consent, the respondents took no other steps to remove Steel Mariner and simply left it where it was. That the respondents ignored the abatement notice requiring the removal of the Steel Mariner and failed, until a later date, to renew their resource consent, indicates to the Court that they were not as concerned about the risk presented by the presence of Didemnum sp. as the council. The abatement notice was served on 6 December 2002 requiring the barge’s removal by 20 December 2002. As late as February 2003 Mr K J Heather for the council deposed that still no response had been received by the officers from the respondents. In lieu of that response enforcement proceedings were begun. By the end of February the respondents then opposed those proceedings and the matter had to be set down for a contested hearing.

required Heli Harvest to take all reasonable efforts to obtain alternative berthage within the adjoining port zone. He submitted that the Council did not dispute that Heli Harvest took all reasonable efforts. He also submitted that the Court did not take into account undisputed evidence of the considerable, but unsuccessful, consultation between the appellants and the Harbourmaster during the term of the resource consent. He submitted that it was difficult to understand how an adverse finding against Heli Harvest could be made that it was not as concerned as the Council about the risk presented by Didemnum by virtue of the timing of its application for resource consent.
  1. Heli Harvest had been granted a 10 month resource consent authorising it to moor the barge in Shakespeare Bay, that consent expiring on 1 December 2002.
  1. That period of time was available to Heli Harvest to make arrangements to go elsewhere by the expiry of the resource consent.
  1. Heli Harvest had not removed the barge by the expiry of the consent on 1 December 2002, but left it there, notwithstanding that it had no consent to do so.
  1. That the Council issued an abatement notice requiring the removal of the barge by 20 December. Heli Harvest did not comply with or appeal against or seek a stay of that notice.

In the course of argument I put each of those four points to Mr Herzog and he accepted each of them as being factually correct. In my view the Judge was entitled to draw from those facts the inference she did about the relative lack of concern by the appellants about the Didemnum risk.

Ground 6


[30] For the contested hearing, it was necessary for the council to arrange for counsel and its witnesses to prepare for, and to travel to Christchurch, to attend the hearing. The hearing commenced with a detailed opening by counsel for council and the presentation of evidence on its behalf. The respondents consented to the issue of enforcement orders only after the completion of the first morning of the hearing and after the Court identified two undisputed factual matters which were fundamental to the enforcement order applications, mainly:

sought by the Council, and did not concede that those orders were appropriate. Rather, that they came to terms with the Council, terms reflected by the orders made by the Court. I have already squarely rejected that submission, and I see no need to go into it again. This ground is dismissed.

Ground 7


[31] In my assessment of this costs application, one of the most important facts of which I took notice is the seriousness of the effect of the spread of Didemnum sp. Its impact on the marine farming industry in the Marlborough Sounds could be catastrophic. Attached to the second affidavit of Mr Heather, in support of the enforcement order application dated 7 April 2003, were notes of a meeting at NIWA Nelson on 26 March 2003 which indicated that the biomass of the organism on the Steel Mariner had returned within three months of its vacuum removal in August 2002 and exceeded its pre-vacuum mass by March 2003. The notes indicated the organism had already spread elsewhere in Shakespeare Bay. The simple fact of the matter is that simply the ongoing presence of the Steel Mariner at Kaipupu Point was a serious threat to mussel farms and salmon cages in the Marlborough Sounds.

4.3 Risks to the aquaculture industry

Considering that the Didemnum sp. colonises artificial structures, it would almost certainly colonise Greenshell mussel lines. Artificial structures (like the barge), provide shaded areas, which the larvae of the Didemnum sp are likely to be attracted to during their exploration phase before settlement (Lambert 2001). However, the Didemnum sp had also completely smothered

mature Greenshell mussels on submerged chains, which were illuminated, at the front of the barge. This suggests that the species has a preference for artificial structures even in highly illuminated areas, although this needs to be further investigated.

It is also likely that the smothering capabilities of the Didemnum sp resulted in the death of some of the Greenshell mussels on the submerged chains at the front of the barge. This is because some dead shells, which were still covered by the Didemnum sp, were found isolated on red algae weed beds at the deepest point underneath the barge. This could have been a result of Greenshell mussels realigning themselves in an attempt to compete for food and space, thereby dislodging the dead mussels (K. Heasman, pers. comm.). It would appear, therefore, that the Didemnum sp has similar smothering capabilities to the cosmopolitan solitary ascidian Ciona Intestinalis, which in a one off event cost the mussel industry an estimated NZ$10 million in lost production in 1998 (Mussel Industry Council 2000). Hence, this particular Didemnum sp is a very real threat to the Greenshell mussel industry. The Didemnum sp may also pose a great to the Salmon Farming Industry by potentially fouling salmon cages, however it is unlikely to pose any significant threat to the oyster industry given their predominantly intertidal farming methods.

Ground 8


[32] The long delays in resolving this case, delays caused only by the respondents, put the marine environment and the aquaculture industry of the Marlborough Sounds at serious risk. The respondents seem to be totally unaware of the expense to the council and its advisers that their actions triggered. These costs are ultimately borne by the ratepayer.

commenced by the Council on 26 February 2003, opposed by the appellants and disposed of by the Environment Court on 16 April 2003. In my view that chronology justifies the Court’s criticism of long delays by the appellants, in the face of the quite serious risk imposed by the Didemnum. This eighth and final ground accordingly also fails.
[2004] NZRMA 289 and by the Environment Court itself in Heritage Trust v Auckland City Council [1992] NZPT 63; (1991-2) 1 NZRMA 174 is that, in a case such as this, a territorial authority’s costs, if not paid by the unsuccessful party, fall on ratepayers generally, and that is neither a just nor a satisfactory outcome. In particular, it does not encourage compliance with abatement notices or, for that matter, enforcement orders.

Result


Costs of the appeal


receiving memoranda. I simply observe that if the Council’s costs are at the entirely reasonable level allowed by Judge Kenderdine, then there ought not to be any contest about them.




Solicitors:

Hunt Edwards, Orewa, Auckland for the Appellants Radich Dwyer, Blenheim for the Respondent


NZLII: Copyright Policy | Disclaimers | Privacy Policy | Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2005/1289.html