You are here:
NZLII >>
Databases >>
High Court of New Zealand Decisions >>
2005 >>
[2005] NZHC 1289
Database Search
| Name Search
| Recent Decisions
| Noteup
| LawCite
| Download
| Help
Heli Harvest Limited v Marlborough District Council HC Wellington CIV 2004 485 1669 [2005] NZHC 1289 (24 February 2005)
Last Updated: 18 June 2020
IN THE HIGH COURT OF NEW ZEALAND WELLINGTON REGISTRY
CIV 2004 485 1669
|
IN THE MATTER OF
|
of an appeal under s299 of the Resource Management Act
|
BETWEEN
|
HELI HARVEST LIMITED
First Appellant
|
AND
|
GEMINI BARGE CO. LIMITED
Second Appellant
|
AND
|
MARLBOROUGH DISTRICT COUNCIL
Respondent
|
Hearing:
|
24 February 2005
|
|
Appearances: L Herzog for the Appellants
B P Dwyer for the Respondent Judgment: 24 February 2005
ORAL JUDGMENT OF WILD J
Introduction
- [1] By a notice
of appeal filed on 22 July 2004 the appellants appeal against a costs order made
by Judge Kenderdine in the Environment
Court on 2 July
2004.
- [2] Appeals
against costs orders are difficult, because costs are quintessentially a
discretionary area. Appeal Courts, perhaps particularly
the Court of Appeal,
have repeatedly sought to discourage such appeals. The appellants refer to one
such expression of discouragement
by the Court of Appeal in Wellington City
Council v Norwich Union Life Society CA97/98 20/11/997. There are plenty of
others: see the commentary in McGechan on Procedure para HR46 Intro.10 at
p1-307. Those
Heli Harvest Limited And Anor V Marlborough District Council HC
WN CIV 2004 485 1669 [24 February 2005]
discouragements by appellate Judges apply here because the appeal is against the
Employment Court’s decision under s285(1)(a)
of the Resource Management
Act 1991 which provides:
285 Awarding costs
(1) The Environment Court may order any party to pay—
(a) To any other party, such costs and expenses (including
witness expenses) incurred by that other party as the Court considers
reasonable:
- [3] Nevertheless,
under s299 of the Resource Management Act, an appeal can be entertained if the
test spelt out by the Court of Appeal
in May v May (1982) 1 NZFLR at 165
is met. That test was correctly reiterated, in the resource management context,
in Countdown Properties (Northlands) Ltd v Dunedin City Council [1994] NZHC 67; [1994]
NZRMA 145 at 153 where the Court stated:
The Court will interfere with decisions of the Tribunal only if
it considers that the Tribunal:
- Applied a wrong
legal test; or
- Came to a
conclusion without evidence or to one which, on evidence, it could not
reasonably have come; or
- Took into
account matters which it should not have taken into account;
or
- Failed to take
into account matter which it should have taken into
account.
- [4] The
appellants have referred to Rowell v Wairoa Quarries Ltd 7/9/96 Ellis J,
HC Nelson M14/96 and Goldfinch v Auckland City Council [1998] NZRMA (97),
both decisions of this Court, in relation to the award of costs on an
application for enforcement orders. In my
view the fact that the Environment
Court was required to make enforcement orders is an obviously relevant factor
for it in considering
the award of costs, together with all the other
considerations relevant in the particular case.
Factual background
- [5] I
take this largely from the respondent Council’s submissions, in which it
is concisely and accurately set out.
- [6] The
appellant, Heli Harvest Ltd (“Heli Harvest”) moored a barge called
“The Steel Mariner” in the Marlborough
Sounds and failed to remove
it following the expiry of its resource consent. The barge was found to be
contaminated with the sea
squirt Didemnum sp. The Council sought
enforcement orders under the Resource Management Act requiring, amongst other
things, Heli Harvest to remove the
barge and to clean up the Didemnum.
Heli Harvest opposed the making of the orders sought up until part way through
the hearing of the Council’s application, at
which point it consented to
orders being made. In making those orders the Environment Court reserved
costs.
- [7] More
specifically, the chronology of events relevant to costs is
this:
- The barge had
been in Shakespeare Bay, just around the peninsula from Picton, since 23 April
2001. It had been taken there at the
suggestion of the Harbourmaster, having
dragged its anchors from its mooring elsewhere in Queen Charlotte Sound. In
making that suggestion
the Harbourmaster pointed out to the appellants that they
would need to apply for a resource consent to moor the barge in Shakespeare
Bay.
The appellants applied for that consent on 8 December 2001 (so the barge had
been in Shakespeare Bay from 23 April 2001, until
a resource consent was
eventually granted on 3 April 2001 without resource
consent).
- In February 2002
it was discovered that the barge was contaminated with Didemnum. This
discovery resulted from a dive made by scientists from the Cawthron Institute in
Nelson in the course of scientific studies.
The appellants promptly reported
that discovery to the Council.
- On 3 April 2002
the Council, by this stage aware of the Didemnum infestation, granted a
short term resource consent for the barge to be moored in Shakespeare Bay. That
consent expired on 1 December
2002. That consent required the appellants to take
active steps to find an
alternative mooring for the barge. It did not, in express terms, require the
removal of the barge by 1 December 2002.
- On 6 December
2002, as the barge still being moored in Shakespeare Bay, the Council issued to
the appellants an abatement notice requiring
the removal of the barge by 20
December 2002. The barge was not removed by that date, nor was any appeal filed
against the abatement
notice, nor any stay of the notice
sought.
- On 23 December
2002 the appellants applied to the Council for a fresh resource consent to
permit the barge to remain moored in Shakespeare
Bay.
- On 26 February
2003 the Council applied to the Environment Court for enforcement orders in the
following terms:
- An
order for the removal of the barge from the coastal marine
area.
- An
order requiring the appellants prior to commencing removal to decontaminate the
barge.
- An
order requiring the appellants, after removal of the barge, to commission the
Cawthron Institute to survey Shakespeare Bay to ascertain
the extent of any
spread of the Didemnum.
- An
order requiring the appellants to undertake an eradication programme of any
Didemnum contamination identified by the Cawthron
survey.
- [8] The
application for the enforcement orders was opposed by Heli Harvest. A defended
hearing was fixed for 16 April 2003 in the
Environment Court at Christchurch. In
preparation for that hearing both parties filed affidavits. There were five
for the Council,
which also subpoenaed a Lloyds ships surveyor. Two affidavits
were filed for Heli Harvest. There was also a detailed statement by
the
scientist at the Cawthron Institute who carried out the various surveys for Heli
Harvest.
- [9] The hearing
began in the Environment Court on 16 April, presided over by Judge Jackson.
Submissions were made on behalf of the
Council and responded to on behalf of
Heli Harvest. The Council’s first witness, the Lloyds surveyor, gave
evidence and was
cross-examined. Toward the end of the first morning’s
hearing, the Court identified matters which it thought were not disputed
by the
parties. They were:
- That
Didemnum was a potential threat to the sounds.
- That
the barge had no resource consent to remain where it was.
- [10] After
discussions between the parties and those advising them, counsel came back
before the Court and invited it to make, by
consent, enforcement orders. Those
orders were essentially the first two which the Council had sought (i.e. I) and
ii) set out in
the last bullet point in paragraph [7] above. I note that Mr
Herzog accepts that there is no material difference between the first
two orders
sought by the Council and the two orders that the Court made by consent. There
is thus no need to set out the precise
terms of those orders. They were preceded
in the Court’s sealed judgment by the following:
Outcome
[17] Accordingly the Court orders (by consent) under
section 319 of the Resource Management Act 1991 that ...
- [11] The Court
then ordered that orders 1 and 2 were to be carried out fully no later than 31
August 2003. It adjourned the remaining
applications to the Court sitting at
Blenheim in the week of 12 May. It then ordered:
(5) Costs are reserved.
- [12] The Council
subsequently applied for costs pursuant to the Court’s reservation. The
parties filed memoranda. The costs
decision appealed against is, as I have
mentioned, that of Judge Kenderdine. The appellants make the point, and it
is
a fair one, that it was Judge Jackson and not Judge Kenderdine who had presided
at the 17 April hearing.
The Environment Court’s costs decision
- [13] I
need not summarise this in any general way, since in dealing with the
appellant’s grounds of appeal I will refer to those
parts of the decision
that are challenged. I should add that the decision, when I read it for the
purposes of this appeal, seemed
to me to be a clearly expressed, well reasoned
and balanced one.
Grounds of appeal
Generally
- [14] There are
eight specific grounds of appeal. The nub of the appeal is that the Environment
Court was wrong to find that the Council
succeeded in its enforcement
proceeding. The submission is that neither party succeeded, the enforcement
orders being made by consent,
after the parties had come to terms. That
submission is not, in my view, an effective opening salvo. The fact that orders
were made
with the appellant’s consent does not negate, and is not
inconsistent with, Judge Kenderdine’s finding that the Council
had
succeeded. Consent often indicates capitulation. The Council submits that that
is exactly the position here.
- [15] Having read
and heard the parties’ submissions, written and oral, and read both Judge
Jackson’s 16 April decision
and Judge Kenderdine’s costs decision, I
am in no doubt that the Council’s submission is sound. Half a day or so
into
a defended hearing of the Council’s application for enforcement
orders, the Court identified for the parties two points which
it seemed to the
Court were not in dispute. I have already mentioned them in paragraph [8] above.
What the Court was signalling
to the parties, particularly, I think, to the
present appellants, was that the almost inevitable outcome of those two points
was
that the barge must be removed from the Marlborough Sounds, and in a manner
which minimised the risk of the spreading of Didemnum. Judge Jackson was,
in my view, signalling to the parties that orders to
that effect were the likely, if not inevitable, outcome if the hearing continued
to a judgment. The untenability of the appellants’
“neither party
succeeded” submission permeates many, if not all, of the eight grounds of
appeal, to which I now turn.
Ground 1
- [16] This
challenges paragraph [22] of the Court’s decision, which
is:
[22] The respondents consider too that they had inadequate time
to file substantive affidavits refuting the concerns as to the seaworthiness
of
the barge, and the alleged biosecurity risk caused by the Didemnum sp.
They contest that the council’s evidence given in the morning of the
hearing would not have stood up to cross-examination
scrutiny.
- [17] The
appellant’s submission is that the Judge erred in her observation that the
respondents considered they had had inadequate
time to prepare for the hearing
and file their evidence. Mr Herzog submits that the appellants were fully
prepared for the hearing.
If that is so, then it surely reinforces the
fundamental point that, even with their case fully prepared and ready to go, the
appellants
capitulated. This is in some ways a more compelling reason for
awarding costs against the appellants than had they capitulated because
they
were not fully prepared. I dismiss ground 1.
Ground 2
- [18] This
challenges paragraph [25] of the Court’s decision, which
states:
[25] Referring to the decisions of Goldfinch v Auckland City
Council, which discussed Rowell v Tasman District Council, I
conclude the successful party is more likely to get an award of costs for
enforcement proceedings. The respondents have submitted
that this principle is
not applicable, as costs are likely to be awarded to a successful
litigant in enforcement proceedings, and neither party was successful in
this case.
- [19] The
appellants submit that the principle “that the successful party is more
likely to get an award of costs for enforcement
proceedings”, was not
applicable here. They submit that, in fact, they submitted the opposite position
to Judge Kenderdine,
stating that it was applicable. Heli Harvest applied the
principle to the
facts and submitted that, and as there was no successful party in this
proceeding, no costs should be awarded.
- [20] For the
Council, Mr Dwyer submits that this misinterprets what the Judge said. He
submits that paragraph [25] says no more than:
- A
successful party is more likely to get an award of costs in enforcement
proceedings.
- Heli
Harvest submits this principle is not applicable in this case as neither party
was successful.
- [21] I agree
that that is the correct interpretation of paragraph [25]. A further difficulty
with this second ground is, of course,
that I have already upheld Judge
Kenderdine’s view that the Council was successful in its enforcement
proceeding.
Ground 3
- [22] This
challenges paragraphs [26] and [27] of the Court’s
decision:
- [26] I disagree
with this proposition. The council applied for enforcement orders, several of
which were made by agreement with the
respondents. In terms of the outcome it
sought, the council was successful. The enforcement orders made by the Court set
out a process
for the obtaining of the relevant Maritime Safety Authority
permits for moving the barge, for cleaning of the barge and its subsequent
removal no later than 31 August 2003. The respondents’ submission that the
fact that the orders were made by consent in some
way absolves them from
liability for costs, is thoroughly misplaced. The concession on the part of the
respondents (that it was appropriate
for enforcement orders to issue) was made
party way through the Court proceedings. Consenting to the issue of orders
simply limited
the costs to both parties as the contested proceedings were
terminated at that stage.
- [27] It is
important to recognise the Environment Court specifically reserved the issue of
costs notwithstanding the fact that the
enforcement orders were made by
consent.
- [23] Mr Herzog
submits that consenting to the enforcement orders was not a concession, but
simply the consequence of an agreement
reached between the parties. He makes the
same submission in relation to the reservation of costs:
it
simply reflected the parties’ agreement. This is the same fundamental
point over again. I reiterate, consenting was a concession.
I accept that the
parties had, out of Court, come to terms. But the point is, they then came back
into Court and invited the Court
to make enforcement orders by consent, which
the Court did. Yes, that certainly obviated the need to continue with the
proceeding,
but, as the Council submits, the ongoing legal costs which would
have resulted from that would have been reflected in a higher award
of costs,
had the Council been ultimately successful.
- [24] The Court
reserved costs. It actually matters not, in my view, whether the Court, by
order, reserved costs or whether the parties
had in an out of Court agreement
(not the position here), agreed to reserve costs for further application to the
Court if thought
fit. In either case the position is to be distinguished from
that where the parties either agreed that there should be no costs paid,
or the
Court expressly made an order that it did not award costs.
Ground 4
- [25] This
challenges paragraph [28] of the Court’s decision, which
states:
[28] Nor is it appropriate in terms of a cost application for
the respondents to attempt to relitigate what occurred in the enforcement
proceedings. The contents of some of the respondents’ submissions appear
to challenge the merits of the proceedings issued
by the council. It is not now
open to the respondents to do so. Such issues were determined when the orders
were made by the Environment
Court. Having conceded that was appropriate for the
orders to be made, it is now inappropriate for the respondents to imply that
the
orders were not justified, or that the application was premature.
- [26] The nub of
the appellants’ submission here is that the Judge erred in suggesting that
the appellants were attempting to
relitigate the merits. The appellants say
they were not attempting to do that. The Court said they could not do that. In
the absence
of any suggestion that the Court had, through costs, punished or
penalised the appellants for any such attempt, and no such suggestion
is made, I
cannot see any substance in this point. Costs were to be based on the outcome of
the enforcement proceeding, and they
were.
Ground 5
- [27] This is a
detailed challenge to paragraph [29] of the Court’s decision, which
states:
[29] Contrary to their submissions, the sequence of events does
not show the respondents went out of their way to contain a potentially
devastating environmental risk either. The council granted a resource consent to
enable the Steel Mariner to occupy the coastal marine area for a period
expiring 1 December 2002. This gave the respondents a period of approximately 10
months
(in addition to the period of previous illegal occupation) within which
to make arrangements to remove the boat. They did not do
so. On the lapse of
the resource consent, the respondents took no other steps to remove Steel
Mariner and simply left it where it was. That the respondents ignored the
abatement notice requiring the removal of the Steel Mariner and failed,
until a later date, to renew their resource consent, indicates to the Court that
they were not as concerned about the
risk presented by the presence of
Didemnum sp. as the council. The abatement notice was served on 6
December 2002 requiring the barge’s removal by 20 December 2002. As late
as February 2003 Mr K J Heather for the council deposed that still no response
had been received by the officers from the respondents.
In lieu of that response
enforcement proceedings were begun. By the end of February the respondents then
opposed those proceedings
and the matter had to be set down for a contested
hearing.
- [28] Mr
Herzog’s submission was that the Court came to these conclusions without
evidence, and took into account a matter which
it ought not to have taken into
account. He contended that no findings were made at the hearing regarding the
lack of concern Judge
Kenderdine found Heli Harvest had displayed for the risk
posed by the Didemnum on its barge. He referred to the filing by Heli
Harvest of affidavits detailing the steps it had taken. He argued that the
Court
specifically relied on Heli’s failure to comply with an abatement
notice issued on 6 December 2002 and expiring on 20 December
as an indication
that it was not concerned about the Didemnum risk. He also took issue
with the Court referring to the absence of steps taken to remove the barge on
the expiry of the resource
consent, and with the statement that that consent
“gave the respondents a period of approximately 10 months within which to
make arrangements to remove the boat. They did not do so. On the lapse of the
resource consent, the respondents took no other steps
to remove Steel Mariner
and simply left it where it was.” He submitted that that statement was
factually incorrect. His point was that the resource
consent did not, in its
terms, require the removal of the barge during the term of the resource consent.
It only
required Heli Harvest to take all reasonable efforts to obtain alternative
berthage within the adjoining port zone. He submitted
that the Council did not
dispute that Heli Harvest took all reasonable efforts. He also submitted that
the Court did not take into
account undisputed evidence of the considerable, but
unsuccessful, consultation between the appellants and the Harbourmaster during
the term of the resource consent. He submitted that it was difficult to
understand how an adverse finding against Heli Harvest could
be made that it was
not as concerned as the Council about the risk presented by Didemnum by
virtue of the timing of its application for resource consent.
- [29] The
responses to these submissions for the Council were these. First, that paragraph
[29] did no more than state a series of
simple factual propositions, from which
the Judge had drawn an inference or conclusion. Those propositions
are
- Heli
Harvest had been granted a 10 month resource consent authorising it to moor the
barge in Shakespeare Bay, that consent expiring
on 1 December
2002.
- That
period of time was available to Heli Harvest to make arrangements to go
elsewhere by the expiry of the resource consent.
- Heli
Harvest had not removed the barge by the expiry of the consent on 1 December
2002, but left it there, notwithstanding that it
had no consent to do
so.
- That
the Council issued an abatement notice requiring the removal of the barge by 20
December. Heli Harvest did not comply with or
appeal against or seek a stay of
that notice.
In the course of argument I put each of those four points to Mr Herzog and he
accepted each of them as being factually correct. In
my view the Judge was
entitled to draw from those facts the inference she did about the relative lack
of concern by the appellants
about the Didemnum risk.
- [30] Secondly,
the Council accepted that the resource consent did not expressly require the
removal of the barge during its term,
but Mr Dwyer submitted that that is not in
fact what the Judge said, and I agree with him.
- [31] Thirdly,
the Council submitted that many of the factual contentions Mr Herzog makes under
this fifth ground cannot be grappled
with because the hearing on 16 April before
Judge Jackson came to an end before all but one of the witnesses had given
evidence.
He submits that it simply is not possible for this Court to make
anything of those allegations, and I agree.
- [32] Finally,
the Council emphasises that the appellants’ application on 23 December
2002 for a fresh resource consent to permit
the barge to remain where it was was
made after its existing consent had expired, and also after the Council’s
abatement notice
had also expired. The Council submits that s124 of the Resource
Management Act, which sets out the circumstances in which the holder
of a
resource consent due to expire may continue to act in accordance with that
consent, was not complied with by Heli Harvest. I
consider the Council’s
points effectively deprive this ground of any substance. It
fails.
Ground 6
- [33] This
challenges paragraph [30] of the Court’s decision, which
states:
[30] For the contested hearing, it was necessary for the
council to arrange for counsel and its witnesses to prepare for, and to
travel
to Christchurch, to attend the hearing. The hearing commenced with a detailed
opening by counsel for council and the presentation
of evidence on its behalf.
The respondents consented to the issue of enforcement orders only after the
completion of the first morning
of the hearing and after the Court identified
two undisputed factual matters which were fundamental to the enforcement order
applications,
mainly:
- That the
Didemnum sp. was a potential threat to the Sounds;
and
- That the barge
Steel Mariner had no resource consent for remaining where it
was.
- [34] The
appellants’ submission here is, in my view, essentially a repetition of
their fundamental submission that they did
not consent to the enforcement
orders
sought by the Council, and did not concede that those orders were appropriate.
Rather, that they came to terms with the Council,
terms reflected by the orders
made by the Court. I have already squarely rejected that submission, and I see
no need to go into it
again. This ground is dismissed.
Ground 7
- [35] This
challenges paragraph [31] of the Court’s decision, which
states:
[31] In my assessment of this costs application, one of the most
important facts of which I took notice is the seriousness of the
effect of the
spread of Didemnum sp. Its impact on the marine farming industry in the
Marlborough Sounds could be catastrophic. Attached to the second affidavit of
Mr
Heather, in support of the enforcement order application dated 7 April 2003,
were notes of a meeting at NIWA Nelson on 26 March
2003 which indicated that the
biomass of the organism on the Steel Mariner had returned within three
months of its vacuum removal in August 2002 and exceeded its pre-vacuum mass by
March 2003. The notes indicated
the organism had already spread elsewhere in
Shakespeare Bay. The simple fact of the matter is that simply the ongoing
presence of
the Steel Mariner at Kaipupu Point was a serious threat to
mussel farms and salmon cages in the Marlborough Sounds.
- [36] The
appellants’ submission is that no finding was made by the Court about the
seriousness of the effect of the spread of
Didemnum. Nor were any
findings made by the Court that the ongoing presence of the barge at its
mooring was a serious threat to the mussel
farms and salmon cages in the
Marlborough Sounds. It is accordingly submitted that there is no basis for the
statements or findings
made by the Court in paragraph [31]. I reject this
submission. Before the Environment Court at the 16 April hearing was a report
by
the Cawthron Institute entitled “A biosecurity investigation of a barge in
the Marlborough Sounds”. That report had
been commissioned by Heli
Harvest. It was put in evidence before the Environment Court both by Heli
Harvest and by the Council. In
other words, its contents were common ground. In
that report there is the following paragraph:
4.3 Risks to the aquaculture industry
Considering that the Didemnum sp. colonises artificial
structures, it would almost certainly colonise Greenshell mussel lines.
Artificial structures (like the barge),
provide shaded areas, which the larvae
of the Didemnum sp are likely to be attracted to during their exploration
phase before settlement (Lambert 2001). However, the Didemnum sp had also
completely smothered
mature Greenshell mussels on submerged chains, which were illuminated, at the
front of the barge. This suggests that the species has
a preference for
artificial structures even in highly illuminated areas, although this needs to
be further investigated.
It is also likely that the smothering capabilities of the
Didemnum sp resulted in the death of some of the Greenshell mussels on
the submerged chains at the front of the barge. This is because some
dead
shells, which were still covered by the Didemnum sp, were found isolated
on red algae weed beds at the deepest point underneath the barge. This could
have been a result of Greenshell
mussels realigning themselves in an attempt to
compete for food and space, thereby dislodging the dead mussels (K. Heasman,
pers.
comm.). It would appear, therefore, that the Didemnum sp has
similar smothering capabilities to the cosmopolitan solitary ascidian Ciona
Intestinalis, which in a one off event cost the mussel industry an estimated
NZ$10 million in lost production in 1998 (Mussel Industry Council
2000). Hence,
this particular Didemnum sp is a very real threat to the Greenshell
mussel industry. The Didemnum sp may also pose a great to the Salmon
Farming Industry by potentially fouling salmon cages, however it is unlikely to
pose any significant
threat to the oyster industry given their predominantly
intertidal farming methods.
- [37] In my view
that paragraph in a report to Heli Harvest about the Didemnum which had
been discovered on Heli Harvest’s barge the Steel Mariner provided
an appropriate factual basis for what the Court said in paragraph [31]. Ground 7
fails.
Ground 8
- [38] This
challenges paragraph [32] of the Court’s decision, which
states:
[32] The long delays in resolving this case, delays caused only
by the respondents, put the marine environment and the aquaculture
industry of
the Marlborough Sounds at serious risk. The respondents seem to be totally
unaware of the expense to the council and
its advisers that their actions
triggered. These costs are ultimately borne by the ratepayer.
- [39] The
submission is that there was no evidence of any delay caused by Heli Harvest in
resolving the case, and that no findings
were made of delay by Heli Harvest
resulting in a threat to the marine environment and aquaculture industry in the
Marlborough Sounds.
- [40] I have
already set out in some detail the relevant chronology of events, starting with
the discovery, in February 2002, by the
Cawthron Institute, of Didemnum
on the Steel Mariner, and ending with the enforcement
proceeding
commenced by the Council on 26 February 2003, opposed by the appellants and
disposed of by the Environment Court on 16 April 2003.
In my view that
chronology justifies the Court’s criticism of long delays by the
appellants, in the face of the quite serious
risk imposed by the
Didemnum. This eighth and final ground accordingly also fails.
- [41] I now deal
briefly with two further submissions made by the appellants in conclusion. The
first was that the Environment Court’s
costs order was contrary to the
accepted principle that Courts should encourage settlements. I do not accept
that. Judge Jackson
certainly encouraged settlement. It seems that his comments
triggered, or at least encouraged, the parties to negotiate and assisted
in the
consent orders he subsequently made. The costs order of Judge Kenderdine simply
awards the costs which the Council had incurred
up to that stage. If the matter
had not terminated at that point with consent orders, then much higher costs
against the losing party
would inevitably have resulted. Mr Herzog accepts that.
I cannot see how the order would work to discourage future compromises. Rather,
it simply reflects, in its incidence and quantum, the compromise reached by the
parties and given effect in the consent orders.
- [42] Finally, Mr
Herzog submitted that indemnity costs were inappropriate, that the appropriate
order was an award which represented
a contribution toward the Council’s
actual costs. That judgment was absolutely one for Judge Kenderdine. Factors
which clearly
weighed with her, in addition to all those I have canvassed in
this judgment, were that the Council’s costs were entirely reasonable.
The
$36,000 she awarded the Council can be contrasted with the approximately
$100,000 costs the appellants were seeking against the
Council. Relevant also is
the point I am about to make in relation to where costs would otherwise fall in
a case like this, if not
awarded against the appellants.
- [43] The costs
reasonably incurred by and awarded to the Council were brought about by the
appellants. Although it may not have been
the appellants’ fault that
their barge became contaminated with the Didemnum, unfortunately it
was the appellants’ barge, and therefore it was
their problem. A relevant point made by this Court in cases such as
Canterbury Regional Council v Waimakarere District
Council
[2004] NZRMA 289 and by the Environment Court itself in Heritage Trust v
Auckland City Council [1992] NZPT 63; (1991-2) 1 NZRMA 174 is that, in a case such as this,
a territorial authority’s costs, if not paid by the unsuccessful party,
fall on ratepayers generally, and that is neither a just nor a satisfactory
outcome. In particular, it does not encourage compliance
with abatement notices
or, for that matter, enforcement orders.
Result
- [44] The
appellants have not established, applying the established test, that the costs
decision appealed against was wrong. I go
further, and say that in my view it
was an entirely appropriate one in the circumstances of this case. Neither the
fundamental submission
of the appellants which underlies all its grounds, nor
any of its eight specific grounds of appeal has succeeded. The appeal is
accordingly
dismissed.
Costs of the appeal
- [45] For
the Council Mr Dwyer submits that this appeal was fundamentally without merit.
He seeks indemnity costs to be fixed by the
Court if they cannot be agreed. Mr
Herzog, for the unsuccessful appellants, submits that there is no basis for
indemnity costs, and
that scale costs should be awarded. I accept Mr
Dwyer’s submission. I have comprehensively rejected the appeal. In my
view
Mr Dwyer is on sound ground in submitting that this appeal against a costs
order of the Environment Court was devoid of any real
merit.
- [46] I also take
into account the point I have already referred to, namely that, to the extent
that the Council does not recover costs
against the appellants, they will fall
on ratepayers, and I have expressed the view that that is neither a fair nor a
satisfactory
situation.
- [47] Accordingly,
I order the appellants to pay the Council’s actual costs and disbursements
of the appeal. If those cannot
be agreed, then I will fix them
upon
receiving memoranda. I simply observe that if the Council’s costs are at
the entirely reasonable level allowed by Judge Kenderdine,
then there ought not
to be any contest about them.
Solicitors:
Hunt Edwards, Orewa, Auckland for the Appellants Radich Dwyer,
Blenheim for the Respondent
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2005/1289.html