![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 5 December 2013
IN THE HIGH COURT OF NEW ZEALAND WHANGAREI REGISTRY
CIV-2012-488-000834 [2013] NZHC 3039
UNDER the Judicature Amendment Act 1972
IN THE MATTER of an application for review of various decisions under the
Resource Management Act 1991 not to publicly notify or serve
notice of a
resource consent applicaton
BETWEEN MICHAEL COLLINS and ROBERTA COLLINS
First Applicants
PETER WILLIAM RICHARDS Second Applicant
NEVILLE COLIN THORNE Third Applicant
MARK CAMERON GURR and HEATHER ANGELA GURR Fourth Applicants
AND NORTHLAND REGIONAL COUNCIL First Respondent
WHANGAREI DISTRICT COUNCIL Second Respondent
Hearing: 16-17 October 2013
Counsel: RJB Fowler QC and E Coburn for Applicants
M Casey QC and AJ Davidson for First Respondent
G Mathias for Second Respondent
Judgment: 15 November 2013
JUDGMENT OF ASHER J
This judgment was delivered by me on Friday, 15 November 2013 at 4.45 pm
pursuant to r 11.5 of the High Court Rules.
Registrar/Deputy Registrar
COLLINS v NORTHLAND REGIONAL COUNCIL [2013] NZHC 3039 [15 November 2013]
Table of Contents
Para No
Introduction [1] The history of the claims [2] The issues [21] Approach to the question of scope [23] The 2004 application [30] The developments between 2004 and 2009 [38] The 2010 consent [42] My assessment of the effects of the change to the spillway dimensions
The nature of the original application [50]
The change between 2004 and 2010 [55] Would the applicants have done anything different? [62] The actual consideration of notification [69] Prejudice to Mr Collins [74] Delay [80] Futility of relief [85] Conclusion [88] Result [90] Costs [91]
Introduction
[1] In Hikurangi, north of Whangarei, there is an area of fertile land
primarily used for the farming of dairy cattle. The
applicants, Michael and
Roberta Collins and Peter Richards, farm in the area. They seek a declaration
that a resource consent permitting
certain modifications to the Hikurangi swamp
scheme is invalid and an order that the decision to grant that consent be
quashed, because
of a failure to adequately notify the application in the form
granted.
The history of the claims
[2] In the early 1970s, the Hikurangi swamp scheme (the scheme) was constructed. It was aimed to ameliorate flooding and as a consequence significantly improve the economies of farming in the area. The goal was to reduce both flood frequency and flood duration. The construction of the scheme was completed by
1977. That scheme provides flood protection to approximately 5,600 hectares
of now highly productive agricultural land.
[3] The work carried out under the scheme involved a variety of works including the creation of stop banks. The scheme could not contain the waters in the event of
extreme rainfall events when there would be river flows in excess of the
containment threshold. The height of the stop banks was
designed to achieve
five year flood protection based upon an assessment of storm events.
[4] The scheme was designed so that at times of very heavy rain, the
excess water flooded into seven areas of land called “pockets”.
That flooding would be in a controlled manner in certain proportions. Seven
pumping stations were created, one for each pocket,
so that when the river flow
eased the flooded waters could be pumped out.
[5] The concept was that in the event of a flood that exceeded the
capability of the stop banks there would be pre-determined
flooding through
spillways cut in the banks into the various pockets. The volume of
water into each pocket was determined
by the length and crest level of the
spillway. The proportions of water that would go to each pocket were
established by examining
the known significant floods prior to the
scheme’s inception. Thus, it was an aspect of the scheme that in flood
events there
would be overspill through the purpose built spillways cut in the
stop banks and into the seven pockets in various calculated
proportions.
[6] The Hikurangi flood plain fell within the area of responsibility of the first respondent, the Whangarei District Council (the WDC). In 1998 it began a review of the scheme to examine its performance and how it could be improved. This led to it deciding on various works that could be carried out to improve performance. On
8 November 2004, the WDC applied to the first respondent, the Northland
Regional Council (the NRC) for consent for work “...
including
maintenance, repair and modification of certain operational issues as set out in
the detailed application documents attached”.
At the time both the
Collins and Mr Richards were farming in the scheme area.
[7] As part of the 2004 application, the amounts of spilled water to be received by each pocket was to be changed. This was to be effected by altering the length and depth of the spillways. It will be necessary to examine the details of the amounts to be received and the extent of the modifications of the spillways in greater depth later in this judgment.
[8] The seven pockets had various names. The pocket in which the two applicants had their farms is known as the Te Mata pocket. There are 2,490 hectares of land making up a considerable number of farms in the Te Mata pocket. The volumetric distribution at the scheme’s inception for the Te Mata pocket was to be
20 per cent of the controlled spill. Other pockets were to receive greater
or lesser amounts of that total spill.
[9] Although this was the original intention, at the time of the 2004
application the Te Mata pocket had been receiving considerably
less than the
intended spill percentage of 20 per cent. Other pockets had also been getting
more or less than their planned percentage.
[10] This spill system, with floodwaters in excess of capacity being
distributed to the pockets, only worked in flood events up
to a certain level.
Extreme flood events, which resulted in the spilling of water from the river not
just through the spillways
but along the banks, fell outside of the planning of
the scheme. Once the banks themselves overflowed and there was general spill,
the function of the spillways was greatly reduced and farmers within the scheme
were at the mercy of the elements.
[11] The surface of the spillways are referred to as spillway crests. Small changes in the spillway crest levels can have a significant effect on the overflow volume and the apportionment that each pocket receives on flood events. However, the proportions of spill can also depend on the characteristics of each flood, such as the peak flow rate and how quickly the flood rises and falls, and how long it lasts. The Te Mata stop bank spillway was designed as being 670 metres long and the height of the spillway was 91.30 metres. However, as of 2004 it was 350 metres long and
91.32 metres in height.
[12] As part of the 2004 application, a model was prepared by a civil engineer, Phillip Wallace. His model predicted a proposed spillway dimension under the reviewed scheme which, amongst other things, would result in the Te Mata pocket actually receiving 20 per cent of the overflow, rather than the lesser amounts it had received up to that point. The spillway for the Te Mata pocket would have a length of 700 metres and a level of 91.35.
[13] The 2004 application was not immediately processed. Discussions and
work continued. There was a significant flood event
in March 2007 when various
pockets, including Te Mata, received extreme inflow volumes.
[14] In December 2006 the 2004 application was publicly notified. In
March
2007, the date for submissions on the original application closed. Many
farmers in the Te Mata pocket made submissions in relation
to the 2004
application. However, the applicants in this proceeding, the Collins and Mr
Richards, did not do so.
[15] After 2004, concerns had developed that the design changes proposed
in the initial model for the 2004 application would not
achieve what was
intended. There was a review process and an amended model produced. The
review and further modelling resulted
in the WDC applying to the NRC to amend
the original application. This was done by a letter from the WDC’s
engineers Hawthorn
Geddes to the NRC on 12 August 2009 attaching a document
headed “Assessment of effects on the environment of the Hikurangi
swamp
scheme (amended)”.
[16] That assessment proposed amendments to the activities and structures, and amongst other things suggested adjusting spillway crest lengths and levels to ensure distribution of floodwaters to reflect more proportionally the design distributions for each pocket. In relation to the Te Mata pocket, it was proposed that the spillway level and length be different from that proposed in the 2004 application. It was reduced to a length of 575 metres and a height of 91.30. The implication of this change is a core factual issue in this case, and will be considered in detail later in this judgment. It was also proposed to improve the rate of floodwater return to river channels. This amendment proposal was not treated as a new application, and was not re-notified. This decision against notifying or omission to decide to re-notify in
2009/2010 is the critical act or omission that is the subject of this
proceeding.
[17] The amended application and supporting documents were circulated to every person who had made a submission on the original application. On 13 April 2010 the NRC granted consent to the 2004 application in its 2009 amended form. In 2011 work began on the scheme. Mr Wallace, who was no longer retained by the NRC, was retained by the applicants and produced a report. That report was dated May
2012. It included data from flood events in July 2005 and March 2012. It indicated that in the event of floods modelled on the new spillway dimensions, Te Mata could receive more than 20 per cent of the spill. The figure he put forward was a
28 percentage. On 3 December 2012 proceedings were issued.
[18] The applicants plead in their first cause of action that
the Council was required under the Resource Management
Act 1991 to make a
decision as to whether to notify the amended application. The Council did not
do so and neither the Collins nor
Mr Richards received any notice of the amended
application. It is pleaded that the actual effects of the amended application
are
significantly more adverse than those in the original 2004 application. On
this basis it is claimed that the decision to grant the
consent was invalid and
should be quashed.
[19] The alternative claim, which is in the fifth cause of action (the
second, third and fourth causes of action having been abandoned)
is based on
illegality. It is said that the Council in making its ultimate decision to
grant a resource consent based on the 2010
application was required to act in
accordance with the Resource Management Act. It is asserted that the 2009
application was different,
with significantly greater adverse effects on the Te
Mata pocket, which were beyond the scope of the original application. It is
said, therefore, that the Council acted illegally in granting the consent to the
amended application because it was outside the scope
of the original
application. A declaration is sought that the NRC’s decision not to
notify was invalid.
[20] The parties originally included two other applicants from a
different pocket, the Okarika pocket, who also claimed a variance
in effects
resulting from the amendment. Their claim was abandoned during the course of
submissions in the second and final day
of hearing.
The issues
[21] The parties all agreed that the core issue was whether the amendments made by the WDC to its application for resource consents were within the scope of the original application. If they were within the scope then the NRC was not required to re-notify the application and the applicants’ case fails. If the changes were outside
the scope of the original application then the NRC ought to have treated the
amendment as a new application and made a decision on
notification.
[22] The respondents also argued that the Court should decline to grant
any relief in its discretion, even if the applicants do
show that the amendment
was outside the scope of the original application. The primary grounds put
forward were unreasonable delay
on the part of the applicants, the
implementation of the resource consent, and the lack of any established
significant prejudice
to the applicants.
Approach to the question of scope
[23] There was no real difference between counsel as to the approach that should be taken in evaluating whether amendments to a resource management application have gone beyond the scope of the original application so as to make it a new application where re-notification must be considered. The Supreme Court stated in
Waitakere City Council v Estate Homes Ltd:1
We accept that in the course of its hearing the Environment Court may permit
the party which applied for planning permission to amend
its application, but we
do not accept that it may do so to an extent that the matter before it becomes
in substance a different application.
(Emphasis added.)
[24] There have been a considerable number of Planning Tribunal, High
Court and Court of Appeal cases which have grappled with
the issue of whether an
amendment to an application means that re-notification should be considered.
In Atkins v Napier City Council Wild J reviewed a number of Court of
Appeal and Environment Court decisions.2 He considered the issue to
be whether the activity for which resource consent is ultimately proposed
is:
... significantly different in its scope or ambit from that originally
applied for and notified (if notification was required) in
terms of:
The scale or intensity of the proposed activity, or
The altered character or effects/impacts of the proposal.
[25] He also added in a paragraph that has been given some weight by all
parties:3
Whether there might have been other submitters, had the activity as
ultimately proposed to the consent authority been that
applied for and notified,
is a means of applying or answering the test. But it is not the test
itself.
[26] It was observed by the Planning Tribunal in Haslam v Selwyn
District:4
The Resource Management Act provides procedures for applications for
resource consent that are designed to enable all persons
who wish to take part
to do so. ... In practice, the lodging of submissions and the
presentation of opponents’
cases frequently leads to applicants or consent
authorities modifying proposals to meet objections that are found to
be
sound. That must surely be part of the statutory intent in providing for
making submissions.
[27] I respectfully accept that statement from a Tribunal expert in the
field of Resource Management Act applications. It
is part of the
resource application consent process that sensible modifications will take
place. Whether there is a need to
re-notify will turn on the facts and will
often be a question of degree. The extent of the modification and its impact
are critical
factors. These are best considered on the knowledge of the parties
at the time of the change. It will be difficult to establish
a need to notify
if the change appears to be minor, even if it is later shown to have effected a
significant change. It is the fairness
of the process that is at issue, not the
merits of different proposals.
[28] Mr Fowler QC in his submissions emphasised that in the analysis of the original application it is necessary to distinguish between the objective of the application and its scope. He conceded that in relation to Te Mata, the objective of a spill of 20 per cent was the same both in 2004 and 2010. It was his argument, however, that the method of achieving that objective changed significantly between
2004 and 2010 with the change in spillway dimensions, and that change of
scope made the application in substance a different application.
[29] Mr Casey QC and Mr Mathias on the other hand submitted that the fact that the objective remained the same was critical, and that the modifications that occurred
were the sort of modifications that could have been expected to occur within
the ambit of the original application in any event.
They submitted that there
was no difference that made the ultimate application in substance a different
application, or which, in
fairness, required re-notification. I will now
consider the history of the application in more detail.
The 2004 application
[30] A report on the hydraulic performance of the Hikurangi swamp
system included in the 2004 application stated that
the initial calculations
undertaken during the design stage of the swamp scheme project showed that the
distribution of flood spillage
volume to the pocket should be in various
proportions to each of the seven pockets. Te Mata’s was shown as 20 per
cent.
It was intended that the design objective of 20 per cent should be
maintained for Te Mata.
[31] The assessment noted that the scheme’s hydraulic
performance “was not achieving the objectives of the original
design”. It also said that “monitoring of the scheme’s
performance ... [has] identified ... modification and upgrading
[as necessary]
in order to ensure that the scheme performs as originally designed” by
modifications in lengths and levels of
the spillways. It did so, however, on
the basis that the hydraulic performance modelling work resulted in
“Findings and recommendations
provided in this report”.
[32] Because Te Mata had been until then getting less than the
20 per cent intended by the original scheme, there
were changes proposed to
the spillway for Te Mata. It was proposed that the length of the Te Mata
control bank spillway be increased
from 350 metres to 700 metres. It was also
proposed that the crest level of the control bank spillway be increased from
91.32 metres
to 91.35 metres. The objective was that the Te Mata spill
remained at 20 per cent, but the spillway length and height was to be
altered to
correct, amongst other things, the fact that Te Mata has been getting too little
of the floodwaters. It was stated later
in an annexure to the application
headed “Assessment of effects on the environment” that:
There is also a need to provide for modifications to the scheme as analysis tools and information concerning its operation and effectiveness improves. Any such modifications proposed would be in line with the effects provided
by the scheme design, be with a view to reducing effects and more closely
complying with the assessed effects.
[33] It can be observed that the effects referred to are those
of the intended distribution proportions. The goal therefore
was to make
certain adjustments to the banks so that the intended effects could be better
achieved. It was also stated:
The following adjustments to control bank spillway crest lengths [levels] to
correct the existing distribution of floodwaters to those
more proportionately
reflective of the designed distributions.
[34] There were a number of provisions relating to modification. It was
stated in the application at paragraph three under the
heading
“Description of Activity”, where the details of activities to be
undertaken pursuant to the obtaining of the
land use consent were provided, that
there would be:
Continuing modifications to the scheme as analysis tools and
information improves [the WDC’s] ability to identify improvements
able to made in the Scheme’s performance with these modifications
being limited to either reducing effects or improving the
scheme’s ability
to control water to the extent provided for in the application and that will
be consistent with the assessment of effects.
(Emphasis added.)
[35] It was also stated in paragraph five:
Modification and repair work to control bank spillways is
necessary to ensure that the scheme distributes floodwater as was intended
in the original design.
There is also a need to provide for modifications to the scheme as
analysis tools and information concerning its operation and effectiveness
improves.
(Emphasis added.)
[36] It was then stated in the assessment of effects:
As described in the application and above in section 1.3, the application
also includes request for consent to continuing modifications
over time.
This is to provide for modifications that may become identified as desirable
as analysis tools and information improves. Such modifications
would be
concerned with improving the Scheme’s performance in line with the
distribution of effects the Scheme was designed
to have.
Due to this part of the application relying on improvements of information on the Scheme’s performance, these alterations can not be identified or described in any detail at this stage. However they are expected to be of the
type described in the specific modifications included in this application,
and result in the same or similar distribution of effects as these
specific modifications provide for and are provided for in the design of the
scheme.
Provision for such work will provide for on-going continuing improvement of
the scheme’s operation through regular maintenance
and operations
activities.
(Emphasis added.)
[37] It is clear that there was no certainty that the objectives would be
achieved, and that there could be modifications to the
scheme as effects were
assessed in order to achieve the desired distributions. However, there is not
any forecast of changes to
the application prior to consent being
granted.
The developments between 2004 and 2009
[38] The activity for which the consent was sought in December
2006 and
February 2007 was:
Provision for maintenance, repair and modification of certain operational
issues relating to the scheme ... modification and repair
work to control bank
spillways is necessary to ensure that the scheme distributes floodwater as was
intended in the original design.
... Any such modifications proposed would be
in line with the effects provided for by the scheme design, with the view to
reducing
effects and more closely complying with the existing
effects.
[39] In 2006, Mr Wallace commented to the NRC on a response by the WDC to
his 2004 review. In July 2009, he was commissioned
again by the NRC to
independently review the hydraulic modelling undertaken for the amended resource
consent application. He responded
on 20 October 2009 concluding that the model
was well constructed and that the calibration was satisfactory. However, he
pointed
out that the revised proposed spillway dimensions had not been run
through the model to ensure that the desired apportionment of
total overflow
would be achieved. He recommended that this be done as the volume of overflow
was sensitive to small differences in
spillway crest levels. Some changes were
suggested. Mr Wallace stated in his evidence:
Included in my response was a comment that the proposed changes in weir crest levels were small in some cases, and beyond the construction tolerances that could be expected. In layman’s terms, a bulldozer cannot be
expected to make accurate changes to the level of 2 to 3 centimetres
differences.
[40] In Mr Wallace’s report of 20 October 2009 he
noted:
With very flat flood profiles, the scheme is a finely balanced system for
spilling during flood events, and a model is unlikely to
be able to always
accurately predict the spilling distributions. Thus, one should not rely too
closely on its results.
Nonetheless, the model has been used in setting the proposed spillway
dimensions and it will remain a valuable tool in managing the
scheme.
[41] Ultimately, changes were proposed in relation to the Te Mata spillway. The average level would stay the same at 91.30 but the length would change to
575 metres. Mr Wallace was contacted again by the NRC in March
2010 to comment on alternative conditions immediately
prior to the consent
hearing.
The 2010 consent
[42] The NRC granting the consent to the spillway changes decision noted
that “the original design intent and capability
of the scheme is not
materially altered by the application”. It went on:
Monitoring of the scheme will continue and as further data is gathered the
model for the scheme will be refined and further crest
level and length
adjustments may apply. Similarly, if modelling technology advances further,
adjustments may be highlighted as being
required. Active modification to
“improve” the performance of the scheme in terms of overall spill
protection is not
being sought.
[43] The consent noted that when five consecutive overflow events for
which the existing points could be measured to within plus
or minus 15 per cent
had occurred, the consent holder would review the initial adjustments to crest
lengths using appropriate modelling
techniques. This was done to determine
whether the average apportionment as set out in the table were, to all
intents
and purposes, being achieved or whether additional adjustments to
crest lengths were required.
[44] It was also noted that the NRC could serve notice of an intention to review the conditions. This could be done two years after the date of commencement of the consents, and thereafter at yearly intervals during the month of April annually to deal
with a variety of issues. Those issues could include any material
inaccuracies that might be found in the information made available
with the
application.
[45] In his 2012 report, Mr Wallace set out further modelling analysis of
how the updated spillway dimensions would work. Amongst
his findings was a
conclusion that in relation to Te Mata, there would be a 28 per cent spill and
not 20 per cent. He qualified
his findings by noting that he was unsure if the
model had been revised since he carried out his review, and that the flow
assumptions
used were subject to some uncertainty. He was unsure whether
spilling outside of the defined spillways had occurred. He accepted
that the
model had limitations, but described it as a useful tool for comparing the
effects of spillway changes.
[46] Mr Wallace’s results were then criticised by the
respondents’ experts. A natural resources engineer, Tristan
Jamieson,
was unable to reproduce his results. Mr Jamieson was critical of Mr
Wallace’s modelling. He observed:
My conclusion was that there was insufficient documentation of the
calibration results to draw any conclusions on the predictive capability
of the
model that was being relied upon.
[47] Mr Wallace filed a further affidavit in which he changed his
conclusion on the Te Mata spillway effects. His evidence is
now that the
correct predicted apportioned overflow for Te Mata is not 28 per cent but 32 per
cent.
[48] It is the finding of a more severe effect for the Te Mata pocket
than the intended objective that is the basis for this judicial
review
application. The essential point made by the applicants is that rather than the
spill proportion received by the Te Mata
pocket being 20 per cent, it will be 32
per cent. They submit that this was a consequence of the change to the spillway
and that
the Council should have made a decision whether to notify the amended
application, and that if there was a decision not to notify,
that decision was
invalid.
[49] Thus in summary, the dimensions at the relevant times are:
Original design
Existing as at 2004
2004 consent application
2009 amended application
Spillway crest length
670 m 350 m 700 m 575 m
Spillway crest height
91.30 m 91.32 m 91.35 m 91.30 m
My assessment of the effects of the change to the spillway
dimensions
The nature of the original application
[50] The change to the spillway dimensions was seen by the Council officers and experts as an adjustment, aimed to better achieve the Te Mata spill objective result of
20 per cent of the total. That objective of 20 per cent did not change
between 2004 and 2010. The position was well expressed by
one of the
applicants, who is no longer actively involved because his farm was in the
Okarika pocket:
... Once I read through the documentation provided by MWH I realised that
there were to be small changes of spillway crest and length.
However, at the
time, I thought these changes were simply in line with the equitable
distribution of stormwater to all pockets in
the scheme.
[51] It would seem then that the understanding of submitters was the same
as that of the council officers and experts. This is
a significant factor in
assessing whether there was a substantive change.
[52] Mr Fowler’s submission is that a change to the means of obtaining an objective can be a substantive change, even if the end objective remains the same. If the change in the scope of what is to be done is sufficient, re-notification is required. As a general proposition I accept that submission. However, in assessing the impact of the modification in this case it is necessary to recognise that the changes to the spillway were, in a sense, tuning changes, aimed to ensure that the flood control machinery that had been set up by the scheme worked better. The language quoted shows this. The spillway modifications were to achieve the distribution of floodwater as intended in the original design. Further, there were to be continued modifications as information about how the scheme worked was gathered. This
would improve the ability of those involved to identify the best steps to
improve performance.
[53] I recognise that the references to later modifications in the
application were to modifications after the proposed set of
changes had been
implemented. There was no indication in the application documents that there
were to be further changes to the application
before it was finally considered
by the NRC.
[54] Thus, I see the relevance of the fact that these were proposals to
adjust spillway crests and lengths to achieve a consistent
objective as
supportive of the respondents’ arguments that there was no change to
scope, but not conclusive. It is necessary
to turn to the nature of the actual
changes.
The change between 2004 and 2010
[55] It is entirely clear that predicting whether changes to spillways
will affect flooding when it occurs is not an exact science.
Mr Wallace in his
20 October 2009 report noted the limitations of the modelling of engineers such
as himself. He commented that
it was highly unlikely that a small change of
height would be particularly significant. He commented that a bulldozer could
not
be expected to make accurate changes to the level of two or three
centimetres. In fact the proposed change to the level of the spillway
was 0.3
metres. Although the change to the length was far more significant it was in
fact a reduction of length from 700 metres
to 575 metres. On the face of it,
the change worked for farmers in the Te Mata pocket such as the
applicant.
[56] In my view, it is relevant that the Te Mata spillway length (the change of which lies at the heart of the applicants’ case) was not a matter that was highlighted at any stage. I accept Mr Casey’s submission that the core of the application was not about spill bank dimensions. It concerned the continuation of the scheme and modifications to better achieve the intended floodwater distribution proportions. In the original application, the proposed Te Mata spillway length could be read about but it was not a matter that was given particular emphasis. When the various modifications were proposed in 2009 which contained a proposed change to the
spillway length, again it was not a matter of particular emphasis. There
was no precise explanation as to how the change in the
spillway length would
impact on the spill. The impression given by the material was that the new
modelling that had been carried
out indicated that the change to the spillway
length would better achieve the end object of 20 per cent. That would be
expected
as there was a reduction in length.
[57] There is nothing in the material provided by the applicants to indicate that at any stage there was any particular concern or debate about spillway lengths. The changes were just a part of the process. Moreover, it was clear that no one could be certain about what result a particular spillway length would produce. Clearly this is so as the experts at the time did not question whether the 2009 spillway length of
575 metres was the correct spillway length, but by 2012 were discussing
whether this was not the right spillway length and would actually
involve a
greater spill than intended. This demonstrates just how tentative the
conclusions were in the application proposals.
As I have observed, Mr
Wallace’s 20 October 2009 report noted the limitations of
modelling.
[58] It must be appreciated that it was not the intention of the NRC that the Te Mata pocket would receive 28 or 32 per cent and not 20 per cent of the flood distribution. To the contrary, the intention of the 2009 modification was that the Te Mata pocket would receive the 20 per cent distribution and the new dimensions would achieve this. The applicants did not know that the original proposals, and indeed the later modifications, would not have achieved the 20 per cent level until they commissioned Mr Wallace to prepare a report which was made available in
2012. Nor did the NRC, which thought that they would achieve or come close
to achieving the desired effect of a 20 per cent spill.
That, and achieving
the other objectives, was the whole point of the exercise.
[59] There are statements by all of the experts about the inadequacies of modelling in terms of predicting with certainty the outcomes of floods. It is understandable that this would be so, given the variables of flow and intensity that arise when there is an extreme flood situation. The difficulties are further demonstrated by Mr Wallace changing his prediction as to spill from 28 per cent to
32 per cent in the course of giving his evidence. The respondents’
experts do not accept the correctness of Mr Wallace’s
analysis.
[60] There remains real doubt as to how the scheme will work. Since the
modifications were made to the Te Mata spill bank following
the 2010 consent,
there has been no flood event that could demonstrate whether the
spillway cut was working as intended.
There has been at least one severe
flood since the modification to the spillway, but that was an acute and unusual
event and it
was ultimately not submitted by the applicants that it provided any
reliable test. I am not satisfied that the modification is a
material change to
the scope of the original application.
[61] Given the lack of real certainty as to how the desired objectives
will be achieved shown in the application, this is the
sort of detail change
that might be expected in the application process.
Would the applicants have done anything different?
[62] A number of the submissions filed by submitters to the 2004
application questioned whether the dimensions of the spill
bank that were
proposed would achieve the outcome sought. But none of the submitters appear
to have carried out their own modelling
and there is no evidence that if the
proposed dimensions had been changed on further occasions between 2004 and 2010
that submitters
would have done anything different.
[63] There is also no evidence from the sole deponent for the
applicants, Mr Collins, that he would have done anything
even if he would have
known about the change to the dimensions. Mr Collins did not even profess to
have read the 2004 application
nor understood any effect the modification to the
spillways would have had in any precise way. His only comment in his affidavit
was that if he had known about the effects of the amendments on his land he
would have fought them.
[64] But, the proposed change between 2004 and 2009 did not highlight any difference in effects. The effect was to be the same. The change was to the dimensions of the spillway to better achieve the effect. The applicants have not
shown that they would have made any submission if they had been notified of
the amended application with the final spillway dimensions.
The new 2009 length
was shorter than before and therefore notionally better for them.
[65] Mr Wallace’s 2012 comments were not available in 2009. That
is when the applicants assert there should have been a
re-notification.
Without that 2012 information it can be assumed that the applicants would have
done nothing even if there had
been re-notification in 2009.
[66] The core submission by the applicants of change of scope is made therefore on the basis of material tentatively expressed, uncertain even today in its prediction, and dependent on information not available at the time of the non-notification decision. I am unable to see how an unidentified problem could have been notified. What was available in 2010 was a change to the spillway dimensions that was intended to lead to a better achievement of the publicised and accepted objective of
20 per cent. The assessment as to whether there has been a substantive
change must be on the basis of evidence known to those making
the notification
decision at the time of notification and not with hindsight.
[67] Of course, subsequent reports can highlight an error in an application, and if the error is of sufficient moment that in itself may lead to possible remedies. But that does not mean that a Court should find that there should have been re- notification at the time. This is a judicial review application and concerns process and not the merits of the consent. The Court must examine the position “as is” at
2009. Then, there was nothing to indicate that the modification would lead
to a significantly worse spill for Te Mata than that
which was
intended.
[68] What has happened here is that an expert has expressed an opinion (which he has changed and which remains tentative) that a technical assumption made in 2010 about the effects of a spillway change was wrong. But saying that does not mean that the application should have been re-notified. Given the information that was available in 2009, the re-notification would have had no consequences as there was nothing to indicate a problem. In such circumstances there was no failure to consider notification or to notify on the Council’s part.
The actual consideration of notification
[69] The two Council officers, Mr Lieffering who was employed as a
consent senior programme manager and Mr Stuart Savill who was
employed as a
consent programme manager, thought about whether there was a need to notify and
decided that the amendments were within
the scope of the original application
and unlikely to affect the public in a manner different from the original
application. They
concluded that any person who may have been adversely
affected by the spill redistributions had been given the opportunity to
lodge a submission in the original 2004 application, and would not be
adversely affected to any greater extent by the amendments
than they could
have reasonably have expected if the original application had not been
amended. In particular, Mr Jamieson
gave evidence that was not challenged
that he was acutely aware of the potential implications of allowing
amendments
to be made which seek to broaden the scope of an application, or may
affect new persons. He concluded that the amendments did not
cross that
threshold.
[70] It is therefore the case that the affidavit evidence shows that in
fact the Council did turn its mind to whether it should
notify, and decided that
it did not need to. As I have outlined, I do not think that their decision was
wrong.
[71] It is to be noted that Mr Wallace carried out a peer review in 2009 and did not come up with the objection to the plan that he then came up with in 2012. In contrast, Mr Jamieson, a senior engineer who has been involved in the modelling since 2004, is not aware of any information that has come to light since 2010 including that arising from the affidavit evidence of Mr Wallace which would detract from or cause him to change his evidence given at the WDC application hearing in
2010. He sees no reason to propose any change to the spillway lengths and
crests from those that have been approved.
[72] Mr Wallace relied in part on his analysis on the 2012 flood. Mr Jamieson criticises Mr Wallace for his use of the 2012 flood for the adaptive management process. That 2012 flood, I am satisfied, was a one-off event involving massive control bank overtopping and unlimited inflows. As a consequence, modelling based
on that event would have been of little use. That flood was not therefore a
relevant flood in the sense of a flood where it could
be expected that there
could be spill as planned from the spill banks. It was a flood event that was
more severe than that.
[73] Thus I am left unsure as to whether Mr Wallace’s predictions
are accurate. The Council officers in 2010 thought the
change was a tuning
change which would better achieve the objects of the scheme.
Prejudice to Mr Collins
[74] The only Te Mata deponent is Mr Collins. I have observed that I am
not satisfied that Mr Collins would have made a submission,
even if he had
received notice of the amended dimensions of the Te Mata spillway. In the
absence of any statement by him on the
point, I assume that if he had focused on
the dimensions of the Te Mata spillway, he would have made the assumption that
the experts
were making their best estimate of what dimensions would best
achieve the 20 per cent outcome. I also assume that he would have
gone along
with it knowing that if 20 per cent was not achieved, there would be further
modification and the process would continue
until the 20 per cent spill was
indeed achieved.
[75] I have also observed that Mr Collins asserted that if he had known
about the amendments to the original application and the
effects of the
amendments he would have fought them. However, that is no more than an
assertion that if he had made the effort to
carry out research into the
consequences of the changes to the spillway he would have done something. At
no stage while the 2004
consent was being considered did he do that. If he had
done so, it is perfectly possible that he might have protested on the same
basis
even in 2005 on the original spillway dimensions, particularly so since 2005 the
spillway length diminished.
[76] He was clearly content with the objective of 20 per cent spill, and the fact that the Council was involved in changing the spillway dimensions as part of a continuing process to achieve the objective. It must be born in mind that in fact if Mr Wallace is right and the effect of the cut is that the Te Mata pocket receives
32 per cent, there will be further changes. It may be that if Mr Collins had known of the effects of the amendments on his land he would have been concerned. But no
one knew the effects of the amendments in 2010. It was assumed correctly in
2010 that the Council was working towards achieving the
20 per cent spill over
to the Te Mata pocket.
[77] Thus, it has not been shown that Mr Collins has suffered any
prejudice as a consequence of the lack of notification.
[78] Further, Mr Collins is farming in a small way. I do not know the
exact dimensions of his farm, but he had 40 head of cattle.
Now he says that
because of flooding difficulties this is reduced to 20. Such a limited degree
of prejudice on its own would not
have warranted the Court’s intervention.
I am not able to infer any wider suffering on the part of Te Mata farmers. No
others
have participated in this proceeding as applicants or expressed their
support.
[79] I record that I accept Mr Fowler’s submission that it could be
a number of years before there are further modifications
to the scheme. The
consent states that there have to be five flood events before this can occur.
It is not possible to predict
how long this will be. If the spillway crest
obviously requires further modification it seems likely that steps would be
taken given
the fact that the 20 per cent objective is unchanged, and that the
scheme is stated to be effectively a work in progress. It is
possible of course
that the spillway dimensions will prove to be satisfactory.
Delay
[80] There has been significant delay by the applicants. The consent was
given on
30 April 2010. These proceedings were filed some two years and seven months
later. This included a delay of approximately six months
after Mr
Wallace’s 2012 report was obtained.
[81] In my assessment the delay is not because of carelessness on the part of the applicants. Rather it further demonstrates the fundamental problem in the applicants’ position. The fact that the 2009 modification was not going to achieve the objective was not known in 2010, and not indicated until the 2012 report.
[82] I accept Mr Mathias’ submission that the differences relied
upon by the applicants were patently evident on the
day the consent issued.
However, I disagree with his submission that there was no good reason to explain
the delay of two and a
half years. There was a very good reason. That was that
no one was aware that there was a problem with the change of dimensions until
the report of Mr Wallace.
[83] I am not critical of the applicants for doing nothing between 2010
and 2012. They, like the Council, were not aware of any
problem. The delay
just goes to demonstrate that the change was not seen as significant and had not
required notification.
[84] Thus I do not see delay as a stand-alone ground for denying the
applicants relief.
Futility of relief
[85] There is no evidence to show that if the Court now set aside the Te
Mata spillway consent and there was a reconsideration,
that this would result in
a different decision by the NRC. Mr Wallace has presented his views. However,
the evidence of the respondents’
experts Mr Summer, Mr Jamieson and Mr
Blackburn is that there is no new information, and that nothing has arisen since
2010, which
would lead them to change the views they had in 2010. There
is nothing to suggest that technology and science has evolved.
Mr Wallace
does not propose any specific adjustment to spillway lengths and crest levels
which would in fact achieve the intended
and accepted design distribution of
floodwater in the Te Mata pocket.
[86] So the whole expensive consent exercise could be repeated, and
nothing might change. And if there was a change to the spillway
dimension, that
change in itself could ultimately be shown to be insufficient or flawed, such is
the imprecision of the science.
There is nothing to suggest that there is
another model which could lead to a better result.
[87] I accept therefore that if relief were granted, it is a real possibility that any further notification and consent process would be a futile exercise. If I had upheld
either of the causes of action, this would have militated against the
granting of any relief.
Conclusion
[88] I am satisfied that the question of notification was considered by
Council officers. They made a decision that notification
was unnecessary, and
that decision has not been shown by the applicants to have been incorrect. The
officers’ decision against
re-notifying was fair and justified in terms of
the expectations of affected parties as the original modification was a matter
of
tuning to achieve a stated and unchanged objective. It has not been shown
that if the applicants had known of the change they
would have done
anything different. The applicants have not established any
prejudice.
[89] The modifications to the Te Mata pocket spillway dimensions in the
2009 application process to better achieve the end goal
of a 20 per cent spill
fell within what could be expected in this resource management
process.
Result
[90] The application for judicial review is dismissed and judgment is
entered for the respondents.
Costs
[91] It could be expected that the respondents would be entitled to costs on a 2B basis, but I have had no submissions on the point. The parties should endeavour to reach an agreement on the question of costs. If they fail the respondents are to file
submissions within 14 days and the applicants within a further seven
days.
Solicitors/Counsel:
RJB Fowler QC, Wellington. M Casey QC, Auckland.
DLA Philips Fox, Wellington.
Hornabrook Macdonald Lawyers, Auckland. Thomson Wilson, Whangarei.
...................................
Asher J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2013/3039.html