![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 16 December 2013
IN THE HIGH COURT OF NEW ZEALAND NAPIER REGISTRY
CIV-2012-441-406 [2013] NZHC 3166
UNDER the Arbitration Act 1996
IN THE MATTER OF an application for leave to appeal to the Court of Appeal
under clause 5(5) of the Second Schedule of the Act
BETWEEN NAPIER CITY COUNCIL Applicant
AND CITYSCAPE NEW ZEALAND LIMITED
Respondent
Hearing: 22 November 2013
Counsel: J O Upton QC for Plaintiff
J R Parker and L D Tidey for Defendant
Judgment: 29 November 2013
JUDGMENT OF GODDARD J
This judgment was delivered by me on 29 November 2013 at 3.00 pm, pursuant to r 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Solicitors:
Lawson Robinson, Napier for Plaintiff
Morrison Kent, Wellington for Defendant
NAPIER CITY COUNCIL v CITYSCAPE NEW ZEALAND LIMITED [2013] NZHC 3166 [29 November
2013]
[1] This matter concerns an application for leave to appeal to the
Court of Appeal from a judgment of Dobson J given on 26 March
2013.1
In his judgment, Dobson J determined two questions of law arising out of
an arbitral award. The questions were stated for the Court
in the following
terms:
(a) whether the arbitrator misconstrued cl 20.1 of the lease as
requiring reinstatement of the premises at the end of the term
to their
condition as they were prior to the fit-out being completed;
(b) whether the arbitrator misconstrued cl 20.1 of the lease by
holding that [Cityscape] had incurred costs in reinstating the premises
within six months of the end of the term of the lease by entering into a
reinstatement contract
on 28 September 2011 for the work to be done, even
although the reinstatement work was not carried out within that six month
period.
[2] The present application for leave to appeal to the Court of Appeal
is only in respect of the second stated question of law.
[3] The leave application as brought is not, however, confined to
Dobson J’s determination of the question as stated and
argued before him.
The Napier City Council now seeks to re-argue the question on an
entirely new ground. The argument
now advanced focuses solely on the
applicability of the Construction Contracts Act 2002 (the Act) to cl 20.1 of
the lease.
This was not raised or argued before either the arbitrator or Dobson
J.
[4] In support, Mr Upton QC referred to and relied upon two decisions concerning general appeals (as opposed to an appeal on a stated point of law) in which leave has been granted to adduce additional argument in the interests of justice. First, Mr Upton referred to and relied upon the decision of French J in Tait-Jamieson v Cardrona Ski Resort Ltd, in which leave was granted to the defendant to rely on estoppel or part-performance of a contract founded on an oral
agreement.2 The second decision referred to and relied upon by
Mr Upton was
Foodstuffs (Auckland) Ltd v Commerce Commission, in which the
Privy Council
1 Pursuant to cl 5(5) of Schedule 2 to the Arbitration Act 1996, any party may appeal to the Court of Appeal from any determination of the High Court under that clause with the leave of the High Court.
2 Tait-Jamieson v Cardrona Ski Resort Ltd [2012] 1 NZLR 105 (HC).
gave leave to argue a new point on the basis of a lack of material prejudice
and because it was important for the case to be determined
on the correct legal
footing.3
[5] As I have noted, both of those decisions concerned the exercise of
a general right of appeal and therefore are of little
assistance in the present
situation.
[6] The application as advanced must be declined on jurisdictional
grounds as the scope of an appeal from Dobson J’s determination
of the
question of law posed in this case must necessarily be confined to that question
of law, as he determined it, and as also
initially determined by the arbitrator
in the first instance.
[7] However, there are two further reasons as to why leave should be
declined in any event. Both were raised by Mr Parker in
his
submissions.
[8] The first is that the Construction Contracts Act has no
relevance to the situation of the parties to the subject
arbitration; nor is
it referenced in the lease document which was the subject of the arbitration and
the appeal before Dobson J.
Nor does the fact that the Act has a “no
contracting out” provision in s 12 alter that situation or imbue the Act
with
relevance to the lease.
[9] The second matter is the purpose of the Arbitration Act 1996. Its
clear contemplation is of only minimal intervention
by the Court in the arbitral
process. The Act’s purposes are as set out in s 5. In Gold and
Resource Developments New Zealand Ltd v Doug Hood Ltd, Blanchard J observed
of these purposes as follows:4
From this section, it is apparent that in passing the 1996 Act, Parliament
intended to encourage the use of arbitration to resolve
disputes between
parties, and to limit the High Court's involvement in reviewing and setting
aside arbitral decisions.
[10] His Honour further
commented:5
4 Gold and Resource Developments (NZ) Ltd v Doug Hood Ltd [2000] 3 NZLR 318 (CA) at [14].
5 At [52].
But our Parliament, like those in the United Kingdom and Australia, has
chosen to favour finality, certainty and party autonomy over
these
considerations. It intended to encourage arbitration as a dispute resolution
mechanism. By enacting a statute with the express purpose of redefining
and clarifying the limits of judicial review of arbitral
awards, Parliament has
made clear its intention that parties should be made to accept the arbitral
decision where they have chosen
to submit their dispute to resolution in such
manner. It plainly intended a strict limitation on the involvement of the
Courts
where this choice has been made.
Result
[11] For all of the above reasons, the application for leave to appeal to
the Court of Appeal on the question of law determined
by the arbitrator and by
Dobson J is declined.
Costs
[12] The defendant is entitled to costs and memoranda may be
submitted by counsel.
Goddard J
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2013/3166.html