![]() |
Home
| Databases
| WorldLII
| Search
| Feedback
High Court of New Zealand Decisions |
Last Updated: 18 December 2013
IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY
CIV-2013-404-3185 [2013] NZHC 3204
BETWEEN ELLIS BUILD 2008 LIMITED Plaintiff
AND NZ CHEMICAL CARE & STORAGE LIMITED
First Defendant
CHEMICAL STORAGE PROPERTIES LIMITED
Second Defendant
Hearing: 6 November 2013
Counsel: K Badcock for Plaintiff
S Ladd and L Mannis for Defendants
Judgment: 3 December 2013
JUDGMENT OF ASSOCIATE JUDGE
SARGISSON
This judgment was delivered by me on 3 December 2013 at 2.30 p.m. pursuant to Rule 11.5 of the High Court Rules.
Registrar/Deputy Registrar
Date...................................
Solicitors: K A Badcock, Rotorua
Bell Gully, Auckland
ELLIS BUILD 2008 LTD v NZ CHEMICAL CARE & STORAGE LTD [2013] NZHC 3204 [3 December 2013]
[1] The plaintiff, Ellis Build 2008 Limited, claims summary
judgment for
$421,684.70 by way of part payment of its total claim for $633,350.16 from
either the first or second or third defendants or a combination
of them. It
also seeks interest and costs.
[2] The first to third defendants, NZ Chemical Care and
Storage Limited, Chemical Storage Properties Limited and Middlemore
Properties
Limited oppose summary judgment. They are related companies, and have the same
director and shareholder, John Bardebes.
Though Mr Bardebes is named as fourth
defendant, Ellis Build no longer wishes to proceed against him and at the
hearing I made
an order by consent striking out the claim against him.
Relevantly, there is no dispute that he acted as agent for all three defendants
in the dealings that Ellis Build’s director, Mr Jorna, had with them at
material times.
[3] The application for summary judgment is made pursuant to r 12.2(1)
of the
High Court Rules which states:
The court may give judgment against a defendant if the plaintiff satisfies
the court that the defendant has no defence to a cause
of action in the
statement of claim or to a particular part of any such cause of
action.
[4] Broadly at issue is whether the defendants have a tenable defence
to the second cause of action in the statement of claim
or to a particular part
of that cause of action.
[5] The onus is on Ellis Build to prove its claim on a prima facie
basis and to establish the absence of a tenable defence.
Ellis Build’s claim as pleaded
[6] The basis of Ellis Build’s claim as pleaded in its statement of claim is a contract1 for building and construction works that it entered into with one or more of the first to third defendants (it is unsure which) in early November 2009. It alleges that under the contract it agreed to carry out and complete building and construction
works at 252 – 254 James Fletcher Drive, Otahuhu and that, in
consideration, one or
1 The contract is apparently partly written and partly oral.
more of these defendants agreed to pay $797,500 plus GST for the
work plus additional sums for any variation. It further
alleges that it
completed the works in the period from November 2009 to December 2010 pursuant
to the contract and issued the seven
progress payment claims for amounts
totalling $799,500 plus GST between 29 July and 23 December 2010.
[7] The statement of claim relies on two causes of action. Materially,
the second cause of action is for breach of the Construction
Contracts Act 2002.
Essentially, it alleges that:
(a) Ellis Build served the seven progress claims on Mr Bardebes;
(b) The amount claimed in the first payment claim, inclusive of GST,
was
$585,493.48 which made due allowance for all progress payments that had been
made by the defendants to that date.
(c) Because no payment schedules were issued in respect of any of the
payment claims, the overall amount outstanding became
a payment due under the
contract and s 23 of the Act and that at least one of the defendants became
liable for payment.
(d) It has received payment for a portion of the total amount of the overall sum claimed of $779,500 plus GST but the amount outstanding is
$663,350.16.
[8] Ellis Build’s position as to quantum was modified at the
hearing. Counsel advised that it accepts that taking account
of all it has
received as part payment of the overall sum claimed. Hence the reduced amount
that it seeks is now $421,684.70.
[9] The first to third defendants accept that a contract was negotiated in early November 2009 pursuant to which building and construction works were carried out at 252 – 254 James Fletcher Drive. They also accept the seven payment claims refer to works that were undertaken for one or more of them at that property. However, they avoid saying for which one and each disputes that it is liable for any of the
payment claims, claiming to have a good arguable defence which makes summary
judgment inappropriate.
[10] The defendants also take issue with Ellis Build’s allegations
that all of the works were done pursuant to the November
2009 contract, pointing
out that there were five separate construction contracts relating to the
property and asserting that all
but two of the payment claims are to entities
that are not party to that contract and are not defendants. Additionally, they
deny
that the contract was with Ellis Build, contending that it was with a
company called Jorland Developments Limited, a company related
to Ellis
Build.
[11] At the hearing counsel for the defendants emphasised the
following:
(a) The statement of claim claims a global amount as outstanding on
seven payment claims without identifying which defendant
is said to be liable as
payer for any individual claim. Additionally, the payment claims themselves
fail to comply with the requirements
of the Construction Contracts Act and are
not valid claims. The claims do not contain sufficient details of the specific
payer,
or the contract to which each claim relates, as required by s 20(2) (b).
It is not possible therefore for the defendants to identify
which one is alleged
to be liable or for what amount. The payment claims also do not set out the
identity of the payer.
(b) If any defendant is liable for any of the payment claims relating to the November 2009 contract, its liability can only be for an unpaid portion of a payment claim. Additionally, there is in fact no unpaid portion of the total claimed amount of $779,500 as that amount contains duplication and payments that have not been accounted for. Therefore it is arguable that there is little or nothing that Ellis Build may recover from any of the defendants as “the unpaid portion of the claimed amount” on any of the payment claims pursuant to s 23(2), or on the overall amount claimed.
(c) Mr Jorna, the director of the plaintiff, has acknowledged that
the payment claims are incorrect and agreed to withdraw
them and to issue
corrected claims.
Legal principles on summary judgment
[12] It is trite law that the plaintiff who applies for summary judgment
has the overall onus of proving its case and showing
that there is no defence.
It is important for the plaintiff to establish sufficient basic facts to raise
at least a prima facie
case against the defendant. Where there is insufficient
detail, the Court may not be persuaded that there is no possible defence.2
Where the evidence is sufficient, the defendant will have to respond if
the application is to be defeated.3
[13] The Court of Appeal set out a succinct summary of the legal
principles applying to applications for summary judgment in
Krukziener v
Hanover Finance Limited:4
The principles are well settled. The question on a summary judgment application is whether the defendant has no defence to the claim; that is, that there is no real question to be tried: Pemberton v Chappell [1987] 1 NZLR
1; (1986) 1 PRNZ 183 (CA), at p 3; p 185. The Court must be left without any real doubt or uncertainty. The onus is on a plaintiff, but where its
evidence is sufficient to show there is no defence, the defendant will have to respond if the application is to be defeated: MacLean v Stewart (1997) 11
PRNZ 66(CA). The Court will not normally resolve material conflicts of evidence or assess the credibility of deponents. But it need not accept uncritically evidence that is inherently lacking in credibility, as for example
where the evidence is inconsistent with undisputed contemporary documents or other statements by the same deponent, or is inherently improbable: Eng
Mee Yong v Letchumanan [1980] AC 331; [1979] 3 WLR 373 (PC), at p 341;
p 381. In the end the Court’s assessment of the evidence is a matter of judgment. The Court may take a robust and realistic approach where the
facts warrant it: Bilbie Dymock Corp Ltd v Patel (1987) 1 PRNZ 84
(CA).
[14] Where it is alleged that one or other of two defendants is liable, but the specific defendant against whom judgment is sought is not identified, the procedure should not be used. As stated in Seeley v Webb, the specific defendant must be
identified and the court must be able to make the identification with
confidence.5
2 Andrew Beck and others McGechan on Procedure (looseleaf ed, Brookers) at HR 12.2.
3 MacLean v Stewart (11) PRNZ 341 (CA).
4 Krukziener v Hanover Finance Limited [2008] NZCA 187, [2010] NZAR 307 at [26].
5 Seeley v Webb Ross & Co HC Whangarei CP22/86, 25 July 1986.
The issues
[15] The issues for determination are these:
(a) Has Ellis Build identified in its statement of claim the
defendant against who judgment is sought, and established
sufficient basic facts
to show that the Court can make that identification with confidence – as
required in Seeley?
(b) Has Ellis Build shown that the defences that the relevant defendant
relies upon are fanciful or not bona fide? Do the
payment claims provide
sufficient detail to comply with the requirements of s 20(2)(b)?
Is there are genuine dispute
as to the unpaid portion of any of the payment
claims under s 23.
Discussion
Has Ellis Build identified the defendant so that the Court can
make that identification with confidence – as required
in
Seeley?
[16] In this case, Ellis Build’s statement of claim fails to
identify which of the named relevant defendant or defendants
were in fact
parties to the November 2009 contract. It states that one or all or a
combination of the defendants were parties to
the contract.
[17] Counsel for Ellis Build contends that one of the three defendants must be liable. Though recognising that the statement of claim is equivocal on the issue of identity he argues that it is for the defendants to sort out which of them should meet the overall unpaid portion of the combined payment claims. He also argues that if satisfied that the evidence clearly shows which defendant is the correct contracting party under the November 2009 contract (and therefore the payer under the Construction Contracts Act) the court could properly make an order amending the statement of claim and enter judgment against that defendant on the payment claims. I accept as a broad proposition that if there is sufficient evidence the court may
amend the claim in the way counsel has suggested6 but the
evidence as to which defendant or defendants contracted for the work is not
clear and unequivocal and the defendants have
elected not to clarify the
position.
[18] Materially, the defendants have been unwilling to assist by
providing any specific acknowledgment as to the correct contracting
party or
parties to assist the plaintiff’s case and it remains therefore for Ellis
Build to provide proof of its case against
at least one of the defendants.
In the circumstances, the claim is not amenable to the summary judgment
jurisdiction.
I agree with counsel for the defendants that the Court cannot
make that identification with confidence.
[19] Summary judgment must therefore fail. I am satisfied that given the
claim as presently pleaded and the evidence, such as
it is, the application must
be dismissed.
Has Ellis Build shown that the relevant defences that the defendant relies
upon are fanciful or not bona fide? Do the payment claims
provide sufficient
detail to comply with the requirements of s 20(2)(b)? Is there a genuine
dispute as to the unpaid portion of
any of the payment claims under s
23(2)?
[20] Given these findings it is unnecessary to make any findings in
relation to these matters. However, without wishing to be
determinative, I
observe that there are at least some factors suggestive of a case that is not
suitable for summary judgment:
(a) It is not immediately apparent that each payment claim
contains sufficient detail to identify that it relates to
the 9 November 2009
contract as required by s 20(2)(b) – in which case each or some may be
invalid. The need for such detail
is not academic because, as counsel for the
plaintiff accepts, there were five contracts for different works.
(b) Section 23(2) permits a claimant (the payee) to recover as a debt the
unpaid portion of a payment claim where a payment schedule has not
been provided. It therefore appears to permit a defence
where
6 Cambria Commercial 2009 Ltd v Pedley HC Palmerston North CIV-2011-454-457, 7 December
2011.
payment has been made of part or all of a payment claim despite the failure
to challenge it by providing a payment schedule.
That is hardly surprising
– there would be no need for a payment schedule if payment is made
instead. The defendants say
that as a matter of fact payments were made that
have significantly reduced and possibly cleared the overall amount claimed.
Counsel for the defendants points out that the plaintiff now accepts that an
even greater amount than previously acknowledged has
been paid.
[21] I also make a few observations that may assist the parties to bring
this claim to a resolution by avoiding significant delay
and cost despite the
unavailability of summary judgment. First, the real issues appear to be
limited to quantum and to which one
of the three defendants is liable for the
outstanding quantum. These issues should be capable of resolution by agreement
failing
which an early trial date should be achievable. Secondly, the
defendants suggest that the real plaintiff is Jorland Developments
Limited.
Again without wishing to be determinative, the documentary exchanges between the
parties appear to lend little support
for this. Almost invariably the invoices
are from Ellis Build or require payment to Ellis Build, and other correspondence
is largely
from Ellis Build. But in any event if early resolution of this issue
or the entire dispute by agreement fails, then the issue can
be progressed by
Jorland’s being added as a plaintiff to further resolution through
discovery, interrogatories (if
necessary) and trial.
Result
[22] The application for summary judgment is declined. Costs are
reserved in
accordance with the Court of Appeal’s decision in ANZ Bank v
Philpott.7
[23] The Registrar is to allocate the soonest available case
management conference for the initial conference. In
the meantime I
direct:
7 ANZ Bank v Philpott [1992] NZLR 403.
(a) An amended statement of clam is to be filed and served not later
16
December 2013. (The plaintiff will need to set out amended
particulars as to quantum among other things).
(b) Leave is given to add Joyner Developments Limited if issues remain
between the parties as to the correct plaintiff.
(c) A statement of defence to the amended statement of claim is to be filed
and served by 30 January 2014.
Associate Judge H Sargisson
NZLII:
Copyright Policy
|
Disclaimers
|
Privacy Policy
|
Feedback
URL: http://www.nzlii.org/nz/cases/NZHC/2013/3204.html